Findings Of Fact In early September of 1979, John and Ruth E. Lockwood contracted with P & P Custom Pools, Inc. (P & P), for the construction of a swimming pool at their home, 231 El Dorado Drive, Debary, Florida. Respondent, Philip J. Mains, signed the contract on behalf of P & P and later obtained a building permit. He and his men began excavating on site in mid-September. The Lockwoods paid respondent $700.00 on September 6, 1979. As construction progressed, they paid him $1,706.25 on September 27, 1979; $1,000.00 on October 26, 1979; $1,047.50 on October 29, 1979; and $1,706.25 on November 20, 1979. At the appropriate times, a building inspector was summoned, who inspected the project, including the placement of reinforcing steel, ground wiring, and lights. Neither the "steel inspection" nor the "deck inspection" revealed any problem. The workmanship was excellent, as far as it went, but the Volusia County building inspector's office was never asked to perform a final inspection. As respondent promised there would be, there was water in the swimming pool by Christmas of 1979, but respondent did no further work after December, 1979. He never installed the pump, filter, diving board, or hand bars called for in the Lockwoods' contract. Earlier in 1979, Patrick T. Ryan, the other principal in P & P, left town and abandoned the business which was then $37,000 in debt. In November of 1979, respondent turned the company's books over to an accountant. In January of 1980 the business' financial problems became critical and, at the accountant's suggestion, respondent so advised the eight homeowners for whom he was building swimming pools, including, in January or February, Mr. Lockwood, who reacted angrily. Respondent testified that Mr. Lockwood "cussed him out." Thereafter respondent avoided the Lockwoods until April of 1980 when they found him working on another pool. There was enough money owed on the eight contracts as a group to finish all the pools, according to respondent's uncontroverted testimony, at the time the Internal Revenue Service levied on respondent's bank account and seized his tools and equipment. Even then respondent offered to finish the Lockwoods' pool if they would buy the materials. Respondent's wife asked Mrs. Lockwood to write a check to a supplier for a pump and filter so that respondent could install them and get water in the pool circulating. Instead, during the last week of April, 1980, the Lockwoods contracted with somebody else to finish the job and paid him $1,200. Respondent subcontracted with a Jacksonville cement company to pour concrete for the pool. After the concrete had been poured, the Lockwoods got a registered letter from the subcontractor threatening to place a lien on their property if he were not paid. According to Mr. Lockwood, the problem was that some check [supposedly drawn by respondent in favor of the subcontractor] had been delayed in the mail. In any event, there was no indication in the evidence that the Lockwoods heard anything further from the subcontractor.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration for thirty (30) days. DONE AND ENTERED this 29th day of April, 1981, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1981. COPIES FURNISHED: Charles F. Tunnicliff, Esquire 130 North Monroe Street Tallahassee, Florida 32301 Philip J. Mains c/o Sue Mains Route 2, Box 799A DeLand, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs. CASE NO. 80-2231 PHILIP J. MAINS, RP 0024663, Respondent. /
Findings Of Fact At all times relevant hereto, respondent, Jerry A. Jennings, held certified general contractor license number CG C020766 and certified residential contractor license number CR CO2OO84 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. He has held the licenses since June, 1981 and February, 1982, respectively. Then the relevant events herein occurred, Jennings was operating a construction business under the name of Quality Control Construction in Port St. Lucie, Florida. He now resides in Casselberry, Florida and is no longer active in the construction business. Respondent formed Quality Control Construction (QCC) in January, 1981 and operated under that name as a subcontractor doing interior trim work on condominium projects in the Port St. Lucie, Florida area. Respondent did not qualify QCC with the State. In May, 1982, Jennings met with the project manager for Riverside Associates, Limited (Riverside), a development firm in Fort Pierce, Florida, and agreed to serve as general contractor and construction coordinator on a Riverside project in Fort Pierce. The job involved the renovating of an old three-story structure known as the Fort Pierce Hotel into an office building. The agreement was entered into by Riverside and respondent doing business as Quality Control Construction. Jennings applied for and obtained all applicable building permits on the job using his state contractor's license. Under the terms of the agreement Riverside agreed to make payments to QCC which in turn was responsible for insuring payment to the subcontractors and materialmen on the job. The work on the project was done in phases. The first phase was completed in January, 1983 when a partial certificate of occupancy was issued by the City of Fort Pierce. Because of a cash flow problem on the part of the developer, work on the next phase did not commence until June, 1983. At that time, QCC and Jennings agreed to finish the job and Jennings obtained all applicable permits. Although Jennings claims it did not include any electrical work, it is found that the last phase included a subcontract agreement by Jennings and White Electric Company (White) for White to do all remaining electrical work for a cost of $2,994. This is evidenced by the fact that Jennings obtained a permit on July 18, 1983 to do additional structural, electrical and air conditioning work on the project, and corrobarative testimony by a representative of White. On August 9, 1983, White submitted a bill to QCC for $2,994 representing the work performed by that subcontractor. Jennings forwarded the bill to Riverside, and on August 22, 1983, Riverside cut a check in that amount payable to QCC. The check contained the notation "For Payment to White Electric." The check was deposited by QCC into its bank account the following day. When White did not receive payment from QCC it contacted Riverside to obtain payment. A representative of Riverside attempted to locate Jennings but learned he had moved and his telephone was disconnected. After some investigation, Riverside determined that respondent had moved to Pinellas County. A certified letter was sent by Riverside to Jennings in October, 1983 requesting payment of the money due White but he did not reply. In November, 1983 a Riverside representative talked by telephone with Jennings who advised Riverside that he had financial problems and used the money due White to relocate to the west coast. Respondent did not timely notify petitioner of his change in address from Fort Pierce to Pinellas County. Riverside eventually set up a payment schedule and finally fully reimbursed White in April, 1984. To date, Jennings has not repaid Riverside. Jennings now resides in Central Florida, is in the process of filing a bankruptcy petition, and does not use his contracting licenses. Jennings claimed at hearing that Riverside never fully paid him for his services and therefore he was justified in retaining the $2,994 intended for White. However, he did not file a lien on the job, made no formal demands for the money allegedly due, and presented no documentation to support the claim.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that respondent be found guilty as charged in Counts I, II and III of the administrative complaint and that he pay a $1,000 administrative fine. It is further recommended that his two contracting licenses be suspended for one year, but if full restitution is made to Riverside, the suspension period be reduced to thirty days. DONE and ORDERED this 2nd day of May, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 2nd day of May, 1985. COPIES FURNISHED: W. Douglas Beason, Esquire 130 North Monroe St. Tallahassee, Florida 32301 Jerry A. Jennings 420 Copperstone Circle Casselberry, Florida 32707
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following facts were found: At all times material to these proceedings, the Respondent, Victor S. Davis, held a registered general contractor's license, numbered RG 0013635 issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board in April, 1973. At all times material to these proceedings, Respondent's general contractor's license, number RG 0013635, was in a delinquent status and had been in a delinquent status since July 1, 1977. Respondent failed to renew his license after June 30, 1975 but in May, 1976 made application to reinstate license number RG 0013635 which was approved and reinstated on an active status by Petitioner in May, 1976 and issued to Respondent, Victor S. Davis, qualifying Conch Construction Corp., of Key West, Florida. There was no evidence that the reinstated license was issued for Monroe County, Florida or that Respondent ever held a certificate of competency for Monroe County, Florida. At all times material to these proceedings, Respondent was an officer (Secretary) of Classic Marketing and Development, Inc. (Classic). On July 28, 1983, the Respondent, as Secretary of Classic, entered into a contract with William Dees to construct a shell home on the Dees' property located at Lot 14, Block 7, Breezeswept Estates, Ramrod Key, Florida for a contract price of $27,000.00. On September 13, 1983, William Dees applied for and obtained building permit No. 10902-A as owner/builder for the construction of the Dees's home. Construction of the Dees home began on or about September 13, 1983. Gregory H. O'Berry, President of Classic had knowledge of, and approved of, Respondent entering into contracts for construction of homes in Monroe County, Florida, including the contract with Dees. O'Berry was aware that Respondent did not hold a certificate of competency in Monroe County, Florida and that Respondent's registered general contractor's license did not cover contracting in Monroe County, Florida. O'Berry understood that Phillip A. Braeunig, a properly licensed general contractor in Monroe County, Florida, was acting as the general contractor for Classic- in the construction of homes by Classic, including the construction of the Dees home. Braeunig did not act as general contractor on the construction of the Dees' home. Respondent supervised the contraction of the Dees' home, until Respondent abandoned the construction of the Dees' home, and in performing these supervisory duties fulfilled the responsibilities of a general contractor. No other officer or authorized agent of Classic had any responsibility for the supervision of, or acted in any manner as a general contractor, in the construction of the Dees' home. Braeunig prepared and submitted to Respondent an application to qualify Classic with Petitioner using Braeunig's license but this application was never filed with Petitioner during- anytime material to these proceedings. Classic was never qualified by anyone, including Respondent or Braeunig, at any time material to these proceedings. Braeunig~acted as general contractor for Classic on the Conti home, which was in the beginning stages of Classic and prior to the Dees' job. Braeunig was brought into Classic for the purpose of acting as general contractor because of the Respondent's invalid license.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the Board enter a final order Dismissing Count I of the Amended Administrative Complaint filed against the Respondent. It is further RECOMMENDED that the Board enter a final order finding Respondent guilty of the violation charged in Count II of the Amended Administrative Complaint and for such violation it is RECOMMENDED that the Board suspend the Respondent's registered general contractor's license for a period of two (2) years and assess the Respondent with an administrative fine of $500.00, stay the suspension and place Respondent on probation for a period of two (2) years, provided the Respondent pays the $500.00 fine within ninety (90) days. Respondent's failure to pay the $500.00 fine within the time specified will result in his registered general contractor's license being suspended for a period of two (2) years with the requirement that when the fine is paid and the suspension lifted, the Respondent must appear before the Board for reinstatement of his license. Respectfully submitted and entered this 3rd of December, 1985, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 3rd day of December, 1985. APPENDIX Department of Professional Regulation, Construction Industry Licensing Board v. Victor S. Davis, Division of Administrative Hearings Case No. 85-1963 Ruling on Petitioner's Proposed Findings of Fact: Adopted in Finding of Fact No. 1 except for the statement that "Respondent's license was issued for Okaloosa County only" which is rejected as not being based upon competent substantial evidence. Hearsay alone is not sufficient to support a finding of fact. Adopted in Finding of Fact No. 1 except for statement that "said license has been delinquent since July, 1981" which is rejected as being contrary to the evidence in Petitioner's Exhibit No. 1 which shows delinquent status as of July 1, 1977. Adopted in Finding of Fact No. 3. Rejected as a conclusion of law rather than a proposed finding of fact. Considered as background information and not as a finding of faet. Adopted in Finding of Fact No. 4. Adopted in Finding of Fact No. 5. Adopted in Finding of Fact Nos. 4 and 5. Adopted in Finding of Fact Nos. 5 and 7. Adopted in Finding of Fact No. 5. Adopted in Finding of Fact No. 6. Adopted in Finding of Fact No. 6. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of feet No. 10 Adopted in Finding of Fact No. 10 Rejected as a conclusion of law rather than a proposed finding of fact. Respondent did not submit Proposed Findings of Fact. COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Board P. O. Box 2 Jacksonville, FL 32202 Nancy M. Snurkowski, Esq. Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Victor S. Davis 2169 North Hercules Avenue Clearwater, FL 33575 and 6290 Sandcrest Circle Orlando, FL 32819
Findings Of Fact At all times relevant to this proceeding, the Respondent was licensed as a contractor by the Florida Construction Industry Licensing Board. His license for the 1979-1981 license period had not been renewed at the time that the hearing was conducted, and he was therefore delinquent. [This finding is determined from Petitioner's Exhibit 1.] During June, 1977, the Respondent entered Into a contract with Emily D. Wohanka and Ruby Sue Dennard. Ms. Wohanka and Ms. Dennard, who are sisters, agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a single-family dwelling on the lot. The parties agreed to an addendum to the contract during July or August, 1977. The addendum included some specifics with respect to construction and provided: Home will be complete and ready for occupancy within a reasonable period of time--normally three to five months. [This finding is determined from Petitioner's Exhibits 8 and 9, and the testimony of Wohanka and Jordan.) The lot which Ms. Wohanka and Ms. Dennard purchased was not cleared until December, 1977. No progress on construction was made during January or February, 1980. The Respondent obtained a building permit from the City of Satellite Beach, Florida, on February 20, 1978. Construction work commenced in either March or April, 1978. By June, 1978, Ms. Wohanka became concerned that work was commencing too slowly. She told the Respondent that she needed to move in by the end of July. Respondent told her that it was probable that construction would not be completed until mid-August. By September, the project was still not completed. Ms. Wohanka tried to reach Respondent by telephone, but he would not return her calls. She tried to locate him at home, but no one would answer the door. She complained to the building official in the City of Satellite Beach, but the building official had similar problems reaching the Respondent. Ms. Wohanka also complained to N. M. Jordan, the real estate agent who had negotiated the contract. Ms. Jordan was able to locate the Respondent, and the Respondent told Ms. Jordan that he could not complete the project because he was losing money. In late September or early October, Ms. Wohanka and her sister located the Respondent at his home. The Respondent was just walking out of the front door when they arrived. The Respondent told them that he could not discuss the matter, that he had turned it over to Ms. Jordan, and that he was not a part of it anymore. [This finding is determined from Petitioner's Exhibits 2 and 3; and from the testimony of Wobanka, Hijort, and Jordan.] When Ms. Wohanka contacted the Respondent in late September or early October, no work had been done on the project for at least a month, and the house was not completed. Light fixtures, appliances, and air conditioning had not been installed. Cabinets and other fixtures were stored in a bathroom. Inside doors had not been installed. Flooring was not completed. No sidewalks or concrete driveway had been constructed. There had been no landscaping or sodding, and the sprinkler system had not been installed. The plumbing was not operational. Ms. Wohanka contracted with a new builder to complete the project. She was able to move into the residence on December 28, 1978, but work was not finally completed until late January, 1979. Additional expenses beyond those agreed to by the Respondent were incurred by Ms. Wohanka. The Respondent had drawn on a construction loan; but, there is no evidence in the record that the Respondent used these funds for any purposes other than the construction of the dwelling. [This finding is determined from the testimony of Wohanka.] During July, 1977, the Respondent entered into a contract with James and Eleanor A. Lawrence. The Lawrences agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a duplex dwelling on the lot. The Respondent obtained a building permit from the City of Satellite Beach on February 22, 1978. Unknown problems developed, and the project was not being completed. The Satellite Beach building official had difficulty locating the Respondent, but he was ultimately assured by the Respondent that the project would be completed. The Respondent told the realtor who negotiated the contract, Ms. Jordan, that he could not complete the 3 reject because he was losing money. The Lawrences did not testify at the hearing, and specifics regarding their relationship with the Respondent are not known. It is not known whether the Respondent abandoned the project uncompleted without notifying the Lawrences, or whether some agreement was made between them regarding completion of the project. There is no evidenced that the Respondent diverted any funds from the project. [This finding is determined from the testimony of Hjort and Jordan.] No building codes from the City of Satellite Beach were received into evidence. There is no evidence in the record from which it could be concluded that the Respondent violated any provisions of the building codes in either the Wohanka or Lawrence transactions.
The Issue At issue herein is whether or not the Respondent/Licensee, Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Lifetime), engaged in conduct which will be set forth hereinafter in detail, which warrants the Florida Construction Industry Licensing Board (Board) to take disciplinary action respecting his license and to impose an administrative fine based on said alleged conduct.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Respondent), is a certified general contractor who holds license No. CGCA 04170, which is active. On September 24, 1975, Mr. Perez used his license to qualify Lifetime Chemicals of America, Inc., as the entity through which he would conduct his business activities (Petitioner's Exhibit 1). On August 15, 1978, Lifetime Chemicals of America, Inc. , entered into an agreement with James Laughery of Fort Myers, Florida, for a franchise agreement to use Lifetime's license in the immediate area of Fort Myers, Florida (Petitioner's Exhibit 5). That agreement provides, among other things, that Respondent Lifetime authorized James Laughery to use its license in the Fort Myers area for a fee of $50.00 per job or $1,500.00. The agreement does not provide, nor was any evidence offered to establish that Respondent Perez played any supervisory or managing role in agent Laughery's contracting activities in the Fort Myers area. During October of 1978, Mr. Andrew Szarfran entered into an agreement with Respondent's agent, Laughery, to perform certain roofing repairs to his residence for the sum of $1,000.00. Mr. Szarfran paid Laughery $500.00 and Laughery abandoned the project prior to completion (Testimony of Szarfran and Petitioner's Composite Exhibit 4). Mr. Szarfran engaged the services of another contractor to complete the project. On May 17, 1979, the Lee County Construction Board reviewed a complaint filed against Respondent by the Szarfrans. Based on that review, the Lee County Construction Board revoked Respondent's licensing privileges in the county at its June, 1979, meeting (Petitioner's Exhibits 3 and 4 and testimony of witnesses Richard M. McDole and Maxine Allred, Administrative Director of Court Enforcement and Permit Clerk, respectively, for Lee County). On or about October 17, 1978, Respondent's agent, Laughery, also entered into an agreement with Mr. and Mrs. Arthur Swanson for the erection of aluminum siding to the exterior walls of their residence for a full price of $5,000.00. The Swansons gave Respondent's agent, Laughery, a downpayment of $2,500.00 and agent Laughery abandoned the project prior to the commencement of any work (Petitioner's Exhibits 7 and 8 and testimony of Mrs. Swanson). Richard Newmes, the chief inspector for building and zoning, Cafe Coral, Florida, testified that the Construction Industry Licensing Board for Cape Coral, Florida, revoked Respondent's contractor license on January 17, 1979, based on his violation of Cape Coral Code Section 5-1/2 - 21(J), to wit: "Failure to make good faulty workmanship or materials performed or installed to evade performance of the contract or specifications as agreed upon." (Petitioner's Exhibit 9.) On or about January 4, 1979, Lifetime Chemicals of America, Inc., became aware of its agent, James Laughery's mismanagement of funds and his failure to honor contractual obligations he had entered in the Fort Myers area. Respondent and its agent Laughery therefore entered into an agreement which rendered the franchise agreement between the parties null and void. Agent Laughery, in said agreement, promised to pay, from his commissions due, monies owed to Lifetime Chemicals, Inc., which apparently was brought about due to the restitution that Lifetime Chemicals had made to customers whom agent Laughery had defaulted. As mitigating evidence, it was noted that the Respondent, Tomas Perez, was not party to or familiar with the activities and/or difficulties that the designated agent for Lifetime Chemicals of America, Inc., James Laughery, was encountering in the Fort Myers vicinity before early January, 1979. As soon as Respondent became aware of Laughery's problems, steps were immediately taken to halt such acts insofar as they related to Respondent (Testimony of Tomas Perez and Michael Arfaras).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law and the mitigating evidence which revealed that although the Petitioner is authorized and in fact holds the qualifier license of a registered entity responsible for the acts of its agents, in view of the undisputed evidence which reflects that neither Respondent Perez or Respondent Lifetime Chemicals of America, Inc., in any manner benefited from the acts of its agents and in fact attempted to thwart the illegal acts of its agent as soon as such became known, it is hereby RECOMMENDED: l. That the Respondent, Tomas Perez's Certified General Contractor's license, CGCA 04170, be placed on probation for a period of one (1) year. 2. That the Respondents, Tomas Perez and Lifetime Chemicals of America, Inc. , be issued a written letter of reprimand. RECOMMENDED this 24th day of April, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of April, 1980. COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 Tomas Perez 2395 West 12th Avenue Hialeah, Florida 33010 Michael Harold Arfaras 820 S.W. 20th Avenue Miami, Florida 33135 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 79-2173 THOMAS PEREZ, CGCA 04170 Respondent. /
Findings Of Fact At all times material to this proceeding Respondent was a registered building contractor in the State of Florida having been issued license number RB 0009164. At no time material to this proceeding was Domingo Alonzo (a/k/a Domingo Alonzo) registered, certified or otherwise licensed by the Florida Construction Industry Licensing Board. Respondent and Alonzo signed and submitted a proposal to Myron M. Gold and Roberta Fox for remodeling and additions to their residence located at 1550 Zuleta Avenue, Coral Gables, Florida in accordance with plans prepared by Frese - Camner Associates on file with the City of Coral Gables, Florida, File No. 2897 for a contract price of $65,940.00 with draw schedules attached. On December 6, 1982, Myron M. Gold and Roberta Fox (Homeowners) accepted the Proposal (Contract). On December 6, 1982, the Homeowners paid Respondent and Alonzo jointly $3,297.00 in accordance with the contract whereby they were to receive 5 percent of the contract amount as a down payment upon signing. The draw schedule provided for a 10 percent retainage from each draw which was to be paid to Respondent and Alonzo upon completion and the issuance of a certificate of occupancy. On December 21, 1982 the Homeowners paid Respondent and Alonzo jointly $2,025.00 which represented a draw on Schedule I - Item 3 for $1,350.00, Schedule II - Item 2 for $360.00 and Item 5 for $315.00. On December 17, 1982 the Homeowners and Respondent filed the affidavit required by ordinance with the City of Coral Gables for the purpose of having a building permit issued covering the work under the contract. 9. On January 19, 1983 Respondent using his building contractors license applied for building permit to cover the work anticipated under the contract and on the same day was issued building permit, No. 28214. Under the contract the Homeowners were to pay for the building permit and the bond required by the city. On January 26, 1983 the Homeowners paid Respondent and Alonzo jointly $3,000.00 which along with a payment on January 27, 1983 of $500.00 and January 31, 1983 of $544.60 represented a draw on Schedule I - Item 2 for $405.00, Item 5 for $1,260.00, Item 6 for $1,547.10 and Item 13 for $832.50. All payments from December 6, 1982 through January 31, 1983 under the contract by the Homeowners totaled $9,366.50 and were paid jointly to Respondent and Alonzo. On February 4, 1983 Respondent and Alonzo entered into an agreement, prepared by Myron Gold in the law office of Gold and Fox, whereby the Homeowners were to pay the balance of the funds remaining under the contract to Alonzo individually. After this date all payments were made to Alonzo. It was the Homeowners understanding after the February 3, 1983 agreement that Respondent would still be responsible for the supervision of the construction although they never saw Respondent again until October 1983. Edward Borysiewicz testified that he dealt with Respondent during March 1983 when he made the floor slab inspection on March 3, 1983 and the columns inspection on March 14, 1983. The record is clear that shortly after the agreement on February 3, 1983 Respondent no longer came to the construction site and supervised the work of Alonzo. On February 8, 1983 the Homeowners paid Alonzo $3,060.00 which represented a draw on Schedule I - Item 1 for $810.00, Item 5 for $1,417.50 and Item 13 for $832.50. On February 28, 1983 the Homeowners paid Alonzo $3,155.40 which represented a draw on Schedule I - Item 4 for $1,705.50 and $729.90 for extras apparently not covered by the contract but whether the balance of check No. 1161 (Pet. Ex. 13) of $720.00 was for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 18, 1983 the Homeowners paid Alonzo $1,000 which represented a draw on Schedule I - Item 9 for $819.00. Again whether the balance of check No. 1206 (Petitioner's Exhibit No. 13) of $181.00 is for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 21, 1983, the Homeowners paid Alonzo $6,400.00 which represented a draw on Schedule I - Items 10, 11, 12, 14 and 15. On March 21, 1983 the Homeowners paid Alonzo $2,166.90 but Petitioner's Exhibit No. 15 does not list check No. 1210 as being a payment under the contract or for extras. On March 31, 1983 the Homeowners paid Alonzo $4,230.00 which represents a draw under Schedule I - Item 7 for $2,520.00 and a payment for extras not covered under the contract in the amount of $1,710.00. On April 21, 1983 the Homeowners paid Alonzo $5,207.40 which represented a draw Schedule I - Items 1, 5, 6, 9 and 14. On June 24, 1983 the Homeowners paid Alonzo $5,788.00 which represented a draw on Schedule I - Item 12 for $667.00, Item 14 for $3,024.00 and payment for extras not under contract for $2,097.00. After March 14, 1983 Respondent was not seen on the job site and there was no longer any apparent supervision of Alonzo by Respondent. After Respondent left the job site there was no licensed building contractor involved in the construction. After Respondent left the construction site the Homeowners soon realized that Alonzo did not know how to proceed with the work and experienced problems with the pace and manner in which the work was being accomplished. On July, 1983, Alonzo stopped working altogether. Although the Homeowners were aware of the problems that Alonzo was having with the construction and that Respondent was not on the job, the record does not reflect that they ever attempted to contact Respondent after the meeting on February 3, 1983. On August 1, 1983 the Homeowners notified Respondent and Alonzo that the contract had been terminated. The Homeowners paid Respondent and Alonzo $42,174.20 total under the contract (pages 1-5, Petitioner's Exhibit No. 15) and paid Alonzo $10,766.37 for extras (Pages 6- 10, Petitioner's Exhibit No. 15). On August 31, 1983 the Homeowners paid Edward Bryant, plastering contractor the sum of $3,100.00 for plastering performed by Edward Bryant. This was for work under the contract that had not been completed or work necessary to correct problems that were already completed. Roberta Fox testified that there were no extras on plaster, however, page 7, line 11 and page 9, line 21 of Petitioner's Exhibit 15 indicates that there was extra plastering. On August 29, 1983 and September 29, 1983 the Homeowners paid Southwest Plumbing Services, Inc. the total amount of $4,875.00 for work contemplated under the contract that had not been completed or needed correction. Homeowners had paid Alonzo $3,591.00 for plumbing under the contract. Both Alonzo and Southwest Plumbing, Inc. were paid for extra plumbing not covered by the contract in the amount of $567.00 and $391.50, respectively by the Homeowners. From September 13, 1983 through June 13, 1984 the Homeowners paid Charles Brueg, Jim Brueg, Charles Buffington and Dan, Inc. the total amount of $4,192.91 for electrical work contemplated under the contract that was not completed or required correction after Alonzo left the construction site. Page 6 lines 6 and 11 of Petitioner's Exhibit No. 15 indicate that there were extras not covered by the contract. The total amount for electricity contemplated by the contract was $3,649.00. Alonzo was paid $2,627.10 under the contract and $1,710.00 for extras. The Homeowners were required to obtain the services of an air conditioning contractor to complete the work contemplated under the contract after Alonzo left the job site and as a result were required to pay Cameron, Inc., the air conditioning contract the amount of $5,181.60 between August 16, 1983 and January 24, 1984. The total amount contemplated under the contract was $3,600.00 of which $1,134.00 had been paid to Alonzo. Debris was dumped in the swimming pool requiring the Homeowners to pay $7,000 to refurbish the swimming pool. This amount included the repair contemplated under the contract and the extra work caused by Alonzo. The contract contemplated $2,300.00 for repairs of which none had been paid to Respondent or Alonzo. The Homeowners paid $1,150.00 to a painting contractor to finish the painting contemplated under the contract. Alonzo had been paid $1,125.00 for painting. (Petitioner's Exhibit No. 15) The contract provided $2,500.00 for all painting required under the contract. Respondent failed to notify the building department that he was no longer responsible for the construction. After the Homeowners terminated the contract due to Respondent's and Alonzo's nonperformance, the Homeowners had to expend a substantial amount of extra money to complete the construction. The evidence is insufficient to determine an exact or approximate amount. Roberta Fox's testimony was conflicting with regard to her understanding as to whether or not the Respondent would continue to supervise the construction after the meeting in the Homeowners' law office on February 3, 1983 when Respondent and Alonzo entered into this agreement. Myron Gold testified that it was his understanding that Respondent would continue to supervise Alonzo after the agreement. However, the Homeowners action in this regard subsequent to February 3, 1983, in making no effort to bring the matter to a "head" and requiring Respondent to supervise the work or terminate the contract and in continuing to deal with Alonzo although Homeowners were aware shortly after February 3, 1983 that Alonzo could not perform without Respondent's supervision and that they knew Respondent was not on the job, tends to show that they were aware or should have been aware that Respondent was no longer involved in the day to day supervision of the construction. Alonzo installed a fireplace pursuant to the contract that the building department determined to be a fire hazard and recommended against its use. The Homeowners applied for and were granted a "owner/builder" permit on September 1, 1983 and requested cancellation of the building permit issued to Respondent which was cancelled on September 6, 1983. They have not received a certificate of occupancy because the building department has not performed the following inspection: electrical final; plumbing final; air conditioning final; roofing final and public works final. The building department would have issued a "stop-work order" had it been aware that Respondent was not supervising the construction and would have required the Homeowners to obtain another licensed building contractor or proceed as a owner/builder. The plans prepared by Frese-Camner Associates that were made a part of the contract by reference were not introduced into evidence with the contract and thus the record is insufficient to determine what was required to meet the specifications of the plans and thereby determine if the specifications had been met. There was a permit issued for the septic tank and drain field which work was started in December, 1982. The construction of the house itself was started in January 1983. The first inspection (foundation) on the house was made by the building department of January 21, 1983.
Recommendation Based on the findings of fact and conclusions of law recited herein, it is Recommended that the Board enter a final order finding Respondent guilty of violating Section 489.129(1)(h)(k)(m), Florida Statutes (1981) and for such violations it is Recommended that the Board assess the Respondent with an administrative fine of $500.00 and suspend the Respondent's contracting license for a period of three (3) years, provided, however, that if Respondent submits to the Board competent and substantial evidence of restitution to Myron Gold and Roberta Fox within one (1) year from the date of the final order herein, then the suspension shall be stayed and Respondent placed on probation for the balance of the suspension. Respectfully submitted and entered this 6th day of February, 1986, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of February, 1986. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 84-2529 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties to this case. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY THE PETITIONER: Adopted in Finding of Fact 1. Adopted in Finding of Fact 2. Adopted in Finding of Fact 3 but clarified. Adopted in Findings of Fact 4 and 5. Adopted in Finding of Fact 4. Adopted in Finding of Fact 6. Adopted in Finding of Fact 5. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12 except clarified as to the last date on construction site. Adopted in Finding of Fact 13. Adopted in Finding of Fact 14 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 16. Adopted in Finding of Fact 17 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 19. Adopted in Finding of Fact 20 but clarified. Adopted in Finding of Fact 21. Adopted in Finding of Fact 11. Adopted in Finding of Fact 21. Adopted in Finding of Fact 22. Adopted in Findings of Fact 22 and 23. Adopted in Finding of Fact24 but clarified to show correct amount paid under contract as indicated by Petitioner's Exhibit 15. Adopted in Finding of Fact 25 but clarified to show that extra plastering not under contract was required. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 29 but clarified. Adopted in Finding of Fact 30 but clarified. Rejected as immaterial. Rejected as not supported by competent substantial evidence. Rejected as not supported by substantial competent evidence. Adopted in Finding of Fact 31. Rejected as immaterial. Adopted in Finding of Fact 32 but clarified to show that the record does not support a figure that approximate $32,000.00. Rejected as not supported by substantial competent evidence even though the Homeowners' testimony supported this fact because the Homeowners' actions with regard to Respondent after February 3, 1983, was to the contrary. Adopted in Finding of Fact 33. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 35. Adopted in Finding of Fact 36. Adopted in Finding of Fact 36. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY RESPONDENT: No Findings of Fact was submitted by the Respondent. COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 W. Douglas Beason Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. George J. Soler, Pro Se 3315 S.W. 96th Avenue Miami, Florida 33165
The Issue The issues are whether Respondent violated Sections 489.129(1)(i) and 489.129(1)(o), Florida Statutes, and if so, what discipline should be imposed.
Findings Of Fact At all times material to this proceeding, Respondent was licensed as a Certified Plumbing Contractor, holding License No. CF C056847. Respondent has maintained an active license since October 19, 1995. At all times material to this proceeding, Respondent conducted his business under the name of Ron Price Plumbing and Tile. On May 18, 2000, Respondent's business was located at 2043 Mike Street, South Daytona, Florida. On May 18, 2000, Respondent gave Edward Carlson a written proposal to perform some repair work in a bathroom at Mr. Carlson's residence, which was located in Daytona Beach, Volusia County, Florida. The letterhead on the written proposal indicates that Respondent's business address was 2043 Mike Street, Daytona Beach, Florida. The written proposal states that for the sum of $1,200, Respondent would perform the following work : (a) remove floor and bottom two rows of tile; (b) install PVC pan and drain; (c) install dura rock to walls; (d) install four-by-four wall tile; (e) install second floor; (f) install two-by-two floor tile; (g) use white grout; and (h) haul away refuse. Mr. Carlson accepted this proposal. Respondent did not pull a permit from the City of Daytona Beach Building Department before commencing the work in Mr. Carlson's bathroom. The City of Daytona Beach, Florida, requires a permit for the type of work performed by Respondent, even though very few plumbers or contractors actually take the time to pull one. Specifically, City of Daytona Beach Ordinance 104.1.4.1 requires a permit for minor repairs exceeding $500. Respondent, subsequently, completed the work in Mr. Carlson's bathroom. Mr. Carlson inspected the work and paid Respondent $1,200 as agreed. There is no credible evidence that Respondent's work was substandard or that he damaged Mr. Carlson's property in any respect. Thereafter, Respondent moved his business to 6089 Airport Road, Port Orange, Volusia County, Florida. As of September 1, 2000, Petitioner's records correctly reflect Respondent's current address of record at the new business location. Petitioner expended $312.48 in total cost, excluding attorney's fees, for investigating, filing, and pursuing the complaint against Respondent through the administrative complaint process.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Petitioner enter a final order finding Respondent guilty of violating Section 489.129(1)(o), Florida Statutes, imposing an administrative fine in the amount of $500, and assessing investigative costs in the amount of $312.48. DONE AND ENTERED this 8th day of November, 2001, in Tallahassee, Leon County, Florida. SUZANNE F. HOOD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of November, 2001.
The Issue Whether disciplinary action should be taken against Respondent, Michael Hill's, contracting license based on the violations as charged in the Administrative Complaint in this proceeding.
Findings Of Fact Based on the evidence and testimony of the witnesses presented and the entire record in this proceeding, the following Findings of Fact are made: Respondent is a certified contractor, having been issued License No. CR C057409 by the Florida Construction Industry Licensing Board. Respondent's license as a certified residential contractor is currently active. Respondent was not certified with the Construction Industry Licensing Board as doing business as "Michael Hill Homes, Inc." On or about April 11, 2005, Kenneth and Aldith Farquharson ("Farquharson") entered into a written contractual agreement with Respondent, d/b/a Michael Hill Homes, Inc., for the construction of a single-family residence at Lot 17, Hattaras Terrace, Palm Bay, Florida. The original contract price of the contract between Respondent and Farquharson was $240,900.00. The original contract price was subsequently increased, via change orders executed by Respondent and Farquharson, by $4,500.00, for a total contract price of $245,400.00, adding the value of the change order for the fill dirt needed for the lot. On June 19, 2005, Farquharson paid a total of $28,590.00 to Respondent. The scope of work under contract required appropriate permits from the City of Palm Bay Building Department before work could commence. Respondent failed to apply for the permits necessary to commence work under the contract. Respondent delivered some sand to the lot on or before October 2005. After delivering the sand, Respondent failed to continue any more of the contracted work. From November 2005 to December 2006, Respondent performed no work on the project under contract. From October 2005 to February 2006, Farquharson made multiple attempts to contact Respondent regarding the lack of work under the contract. Farquharson did not prevent Respondent from commencing and completing the work under contract or agree to delay the project for any reason. Farquharson did not terminate the contract with Respondent. Respondent did not refund any money to Farquharson. The amount of actual damages that Respondent caused Farquharson is calculated as follows: Amount paid: $28,590.00 Amount of work performed by Respondent (dirt fill): _ 4,500.00 $24,090.00 The Petitioner's total investigative cost for the case is $439.79.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered as follows: Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count I of the Administrative Complaint, for violating Subsection 489.119(2), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count II of the Administrative Complaint, for violating Subsection 489.126(2)(a), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(g), Florida Statutes, as alleged in Count III of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(j), Florida Statutes, as alleged in Count IV of the Administrative Complaint, and imposing as a penalty an administrative fine of $5,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(o), Florida Statutes, as alleged in Count V of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Section 489.129(1)(m), Florida Statutes, as alleged in Count VI of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Respondent be ordered to pay financial restitution in the amount of $24,090.00 to Kenneth and Aldith Farquharson; Assessing cumulative cost of investigation and prosecution in the total amount of $439.79, which excludes costs associated with any attorney's fees; and Permanently revoking Respondent's license as a result of the numerous violations and the financial harm sustained by Kenneth and Aldith Farquharson. DONE AND ENTERED this 12th day of October, 2007, in Tallahassee, Leon County, Florida. S JEFF B. CLARK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of October, 2007.
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following facts are found: At all times material to these proceedings Respondent was licensed by the State of Florida as a registered residential contractor, having been issued license number RR 0033727. Respondent's license was first issued in February, 1974. In April, 1983, Respondent submitted a change of status application and requested to qualify Regency Builders, a proprietorship. License number RR 0033727 was then issued to William B. Pitts, qualifying Regency Builders. Regency Builders, Inc., has never been qualified by a license of the Florida Construction Industry Licensing Board pursuant to Chapter 489, Florida Statutes or any predecessor of Chapter 489, Florida Statutes. There is nothing in the record to show that Regency Builders was ever properly incorporated in the State of Florida. However, the record reflects that Respondent did register Regency Builders under the fictitious name statutes Section 685.09, Florida Statutes and complied with the requirements of Section 489.117, Florida Statutes after being contacted by Petitioner's employee sometime in February, 1983. Respondent has been a contractor in Bay County, Florida for 10-12 years and has constructed 150-200 homes during this period of time without any disciplinary action against him, excluding the present proceeding. Respondent prepared a proposal for the construction of a home for Mr. and Mrs. Lee Munroe under the name of Regency Builders, Inc., and submitted the proposal to them. Although the Agreement which was prepared by Lee R. Munroe and signed by Respondent on April 11, 1982 and signed by Lee R. Munroe and Sara W. Munroe (Munroes) but undated, incorporates certain portions of the Proposal, the record reflects that the proposal, per se, was never accepted by the Munroes. The Agreement referenced in paragraph 5 was an agreement entered into by the Respondent and the Munroes for the construction of the Munroes' residence in Gulf Air Subdivision, Gulf County, Florida. The agreed upon contract price was $74,129.33 but, due to changes requested by the Munroes, the Respondent was paid approximately $95,000.00. The Munroes' residence was constructed by Respondent pursuant to the Agreement and was essentially completed in December, 1982. The Munroes moved into this "completed" residence in December, 1982. DeWayne Manuel, building inspector for Gulf County, Florida, during the construction of the Munroe's residence by Respondent, performed the framing inspection, the rough electrical inspection, the rough plumbing inspection, the mechanical inspection (the heating and air conditioning systems) and all other inspections required by the 1982 Southern Standard Building Code, as adopted by the Board of County Commissioners, Gulf County Florida (Code) with the exception of the final inspection. At the beginning of construction, but before the framing inspection, Lee Munroe contacted Manuel with a general concern about the construction. As a result of this meeting with Lee Munroe, Manuel requested Charles Gaskins (Gaskins) an architect with Gaskins Architect of Wewahitchka, Florida, to inspect the pilings, girders and floor joist. After this inspection, Gaskins made some recommendations in regard to the attachment of girders to the pilings which Respondent followed in making the corrections to the attachments. Gaskins Architect provided the Piling Layout 1st and 2nd Floor Framing (Petitioner's Exhibit No. 8) at the request of the Munroes. Generally, Gaskins found no major problems with the pilings and girders other than the work was "sloppy". Both Manuel's and Gaskins' inspection revealed that Respondent had complied with the requirements of the Piling Lay Out and Manuel found no Code violations. After Gaskins inspected the pilings and girders, Respondent was allowed to continue construction by both Manuel and Munroe. The House Plans (Plans) for the construction of the Munroes' home were prepared by the Munroes' daughter who is an unlicensed architect. Although in several instances the Plans requirements were less stringent than Code requirement, the Plans were approved by the Gulf County Building Department. While the Plans were lacking in detail a competent licensed contractor should have known how to fill in the details. Once the Plans were approved, Manuel would allow a change in the Plans provided the change was as stringent as the Code and would allow the structure to be built in compliance with the Code. The change could be a downgrade or an upgrade provided the Plans, as changed, complied with the Code requirements. Respondent did not request any additional or more comprehensive plans from the Munroes or inform the Munroes in any manner that the plans were inadequate. The Plans called for 2 x 12 solid floor joists to be placed on 16 inch centers. The house as constructed by Respondent had engineered floor truss (I- Beams) placed on 24 inch centers. Those I-Beams carrying a significant load were not blocked and in some instance the I-Beams were not "end-blocked." The Code allows the use of wood I-Beams in place of solid wood floor joists provided the wood I-Beams are constructed in accordance with Code requirements. The record does not reflect that the I-Beams as used in this construction were built in accordance with the Code, and the testimony of both consulting engineering experts, that the placement of I-Beams in this structure required blocking along both sides and the end went unrebutted. There were holes and notches in the plywood web of the I-Beams. However, in reviewing the photographs in Petitioners Exhibits Nos. 11 and 14, and, in particular, photograph 1 of Exhibits 11 and photographs 4, 5, 6, and 7 of Exhibit 14, and the testimony surrounding those photographs, there is insufficient evidence to determine: (1) the size of the holes or notches (2 inch hole, 4 inch notch, etc.); (2) placement of hole or notch in relation to depth of I-Beam (upper 1/3, lower 1/4, etc.); or, (3) the depth of the I-Beams. Although there was no testimony concerning the size of the hole for the duct work and the depth of the I-Beam in photograph 7 of Exhibit No. 14, it is clear that the hole for the duct work is greater than 1/3 the depth of the I-Beam. The evidence is insufficient to show that Respondent did not use 5 - 2 x 12's in the main girder as required by Piling Layout. The evidence is clear that the 2 x 12's used in girders were not always butted at a support. The evidence is insufficient to show where the 2 x 12's were butted in the span or if the butting was staggered. No set-in braces or plywood sheathing was used in the bracing of exterior stud walls. However, diagonal metal strapping and thermoply was used and two layers of weatherboard were put on horizontally. The evidence was insufficient to show that water penetrated into the wood framework after the second siding was put on. A 32/16, 1/2 inch plywood was used for subflooring. There was no top plate on dining room wall which was a weight bearing wall. Ventilation in the attic was in accordance with plans but no cross ventilation was provided in the attic. The evidence is insufficient to show that hurricane clips were not applied to the center exterior wall in that neither engineer inspected the outside of the wall to determine if hurricane clips were on the outside. Manuel did not find a violation of Code in regard to the hurricane clips. In February, 1983, James Van Orman (Orman), a licensed engineer, was employed by the Munroes to do a structural analysis of the home constructed by Respondent. Orman's report (Petitioner's Exhibit No. 10) contained certain calculations in regard to the structural integrity of the home. The calculations and Orman's testimony surrounding the calculations went unrebutted. Orman and Lee Munroe were associated through their work and Orman, also a general contractor, was hired to make the necessary corrections in the construction to make it structurally sound. On December 5, 1984, after reviewing the case file and exhibits, Harold Benjamin, Jr. (Benjamin), a licensed consulting engineer, conducted an inspection on the structure. While Benjamin's inspection was cursory and he made no calculations Benjamin noted the same Code violations as did Orman and concurred in Orman's conclusion that the structural integrity of the home had been compromised. Respondent was notified in March, 1983, of the problems with the structure but due to problems with the Munroes and with his subcontractor he was only able to replace the siding and do some cosmetic work between March, 1983 and October, 1983. In October, 1983, the Munroes contracted with Orman to correct what Orman had determined to be structural deficiencies and notified Respondent that they no longer wanted him on the job. On September 30, 1983, the final inspection was conducted by the Gulf County Building Department. The Respondent was not present at this inspection having failed to pick up a certified letter from Manuel advising him of the date for the final inspection. By letters dated February 7, 1983 (Petitioner's Exhibit No. 4), October 13, 1983 (Petitioner's Exhibit No. 5) and February 13, 1984 (Respondent's Exhibit No. 1), Manuel expressed his thinking about the Code violations and Orman's report. At the hearing Manuel testified that his thinking had not basically changed from what he had expressed in the letters. Neither the Respondent nor the Gulf County Building Department have had the residence structurally analyzed by a licensed engineer. Respondent deviated from the Plans without first obtaining approval of the Gulf County Building Department when he substituted I-Beams on 24 inch centers for 12 x 12 solid floor joists on 16 inch centers. The only evidence that this change was discussed with the Munroes was in regard to running heating and air conditioning duct work through the I-Beams because Mrs. Munroe did not want to drop the ceiling down to 7 feet to accommodate the duct work. While this change may not have affected the structural integrity of the house had the I-Beams been properly constructed and the strength of the subfloor material adjusted to account for the increased span, the evidence shows that the I-Beams were not properly constructed and that the subfloor material used was not of sufficient strength on account of the increased span. Therefore, this change affected the structural integrity of the house. It was apparent from the testimony that certain other changes in the Plans were made without prior approval of the Gulf County Building Department. However, it was also apparent from the evidence that these changes were at least verbally approved by the Munroes and there was no evidence that these changes affected the structural integrity of the house. Due to a grandfathering provision in the law, William Pitts has never taken an examination for licensure and has never been examined as to the provisions of the Code. Respondent in his testimony exhibited: (1) an awareness of the applicable provisions of the Code but not a complete understanding of them; and (2) an acceptable knowledge of he applicable construction practice.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is Recommended that the Board enter a final order finding Respondent guilty of the violations alleged in Count I and Count II of the Administrative Complaint and for such violations it is Recommended that the Board impose an administrative fine of $1 000.00 and suspend Respondent's residential contractor license for a period of one (1) year, staying the suspension and placing Respondent on probation for that period provided the Respondent: (1) pays the $1,000.00 fine within ninety (90) days; (2) obtains a current copy of the Southern Standard Building Code and agrees to keep it current; and (3) proves to the Board that he has read and is familiar with the applicable Sections of the Code that relate to his license. Respectfully submitted and entered this 2nd day of July, 1985, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of July, 1985. COPIES FURNISHED: Edward C. Hill, Jr. Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Charles S. Isler, III, Esquire Post Office Box 430 Panama City, Florida 32402 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee Florida 32301 Salvatore A. Carpino, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville Florida 32202 =================================================================