Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. HAMILTON, 79-000018 (1979)
Division of Administrative Hearings, Florida Number: 79-000018 Latest Update: Apr. 28, 1980

Findings Of Fact At all times pertinent to these proceedings, Hamilton held registered residential contractors license number RR0015037. Hamilton agreed to construct a house in Clearmont, Florida, with a completion date no later than May 1, 1977, for Robert J. and Margaret M. Phlepsen. The construction price was $75,000.00. After construction of the house it was discovered that there existed two violations of the Southern Building Code. First, the "step-down" from the kitchen to the garage was an eleven inch riser contrary to the code requirement that the height of a riser shall not exceed seven and three quarters inches. The second violation occurred through the use of 2 X 8 joists where the code would require 2 X 10 joists. The extra high riser between the kitchen and the garage was apparently caused by an oversight. Hamilton merely failed to install an intermediate step at that location. The second violation occurred because the owner and Hamilton agreed to use the smaller joists in order to save money on the contract price. In neither case is there sufficient evidence to establish that Hamilton's violations were willful or deliberate as alleged in the Administrative Complaint. On June 6, 1978, the Lake County Board of Examiners suspended Hamilton's Lake County Certificate of Competency because of violations of building code requirements in the construction of Phlepsen's house.

# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs DANIEL FRANK MOLINARI, 94-005259 (1994)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 22, 1994 Number: 94-005259 Latest Update: Mar. 20, 1997

Findings Of Fact At all times material hereto, Daniel Frank Molinari (Respondent) was a certified plumbing contractor, being licensed by the Florida Construction Industry Licensing Board (CILB) and having been issued license numbers CF C021437 and CF C041671. On or about March 20, 1990, the State Attorney of Dade County, Florida charged Respondent by Information with an attempted offense against intellectual property in violation of Sections 815.04(3) and 777.04, Florida Statutes, a misdemeanor: "[Respondent] on the 19th day of February 1990 . . . willfully, knowingly, without authorization, attempt to disclose or take data, programs, or supporting documentation, to wit: The CONTENTS of a CONTRACTOR'S LICENSING EXAMINATION, which is confidential as provided by law, residing or existing internal or external to a computer, computer system, or computer network. . ." On or about July 30, 1990, Respondent pled nolo contendere to the misdemeanor charge. Based upon Respondent's plea of nolo contendere, the Dade County Judge entered a judgement finding Respondent guilty as charged, withholding adjudication and imposing costs in the amount of $300.00. In the Dade County judicial circuit, a judge usually makes a finding of guilt when a defendant pleads nolo contendere even if adjudication is withheld. Typically, items in a CILB examination are reused on subsequent exams. However, each examination must contain a certain percentage of new items. Because of Respondent's attempted act, the CILB considered the items on the contractors examination in 1990 to be compromised and, therefore, unusable for subsequent examinations. The 1990 CILB examination consisted of two hundred and twenty-one (221) items. Consequently, 221 new items had to be developed at a cost of approximately $100.00 per item. On or about June 10, 1993, Respondent submitted to the CILB a Certification Change of Status Application (Application) to activate his inactive certified plumbing contractor license (license number CF C041671). Question 7(H) of the Application inquired whether Respondent had ever "Been found guilty of any crime other than a traffic violation". He responded "no" to the question. The Application required an affirmation, and Respondent so affirmed, that "these statements are true and correct and I recognize that providing false information may result in a fine, suspension, or revocation of my contractor's license." Respondent's request for activation could have been denied if he had responded "yes" to question 7(H) of the Application.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order: Dismissing Count II of the administrative complaint in DOAH Case No. 94-5259; Dismissing all counts of the administrative complaint in DOAH Case No. 95-0199; Revoking Respondent's licenses; Imposing costs for the investigation and prosecution to be determined by the construction Industry Licensing Board. DONE AND ENTERED this 29th day of August, 1995, in Tallahassee, Leon County, Florida. ERROL H. POWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 1995.

Florida Laws (4) 120.57489.129777.04815.04
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES RASKIN, 77-000624 (1977)
Division of Administrative Hearings, Florida Number: 77-000624 Latest Update: Aug. 10, 1977

Findings Of Fact The parties stipulated to the fact that James Baskin holds registered contractor's license number BC 0011300. Raskin's registered general contractor's license was issued by the Florida Construction Industry Licensing Board. Prior to the commencement of the hearing, the Hearing Officer held that the record of the proceedings for the Cape Coral Board could be filed as a late filed exhibit in this cause in order that the Florida Construction Industry Licensing Board could review the Cape Coral Board's action pursuant to its authority under Section 468.112(2)(f), Florida Statutes. Ambassador Homes contracted with Sam and Marie Franzella for the construction of a single family residence to be constructed on the property located on Lots 41-42, Block 1224, Cape Coral Unit 19, Section 32-33, Township 44 South, Range 24 East. Stucky Well Drilling was initially contacted by an unknown agent of Ambassador Homes on January 1, 1975, and directed to drill a well, and install a deep well jet pump and tank at the location stated above. On January 20, 1975, Marion, a secretary for Ambassador Homes, called Stucky Well Drilling and directed that Stucky Well Drilling install the well and equipment as soon as possible. On January 21, 1975, a 210 foot well was drilled on the property described above and on January 23, 1975, a Mr. Green from Ambassador Homes called and requested that the tank and equipment be installed immediately. Mr. Hall, an employee of Stucky Well Drilling, installed all the equipment as ordered on January 23, 1975. On January 24, 1975, a bill in the amount of Six Fifty Dollars ($650.00) was sent to Ambassador Homes for the work performed on the property described above. Ambassador Homes was a corporation engaging in residential contracting and operating under the license of James Raskin. Ambassador Homes did not pay Stucky Well Drilling the bill for the drilling of the well and installation of the equipment on the property described in paragraph 3 above. Subsequently Stucky Well Drilling brought suit against Ambassador Homes, Inc., in the County Court of Lee County and obtained final judgment in the amount of Six Hundred Fifty Dollars ($650.00) plus costs. This judgment was entered on December 2, 1975.

Recommendation Based on the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board suspend the license of James Raskin as a registered general contractor until he presents satisfactory proof to the Board of his financial qualifications to engage in the contracting business. DONE and ORDERED this 27th day of May, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blacks tone Building Jacksonville, Florida 32202 James Raskin 1810 S. E. 44th Street Cape Coral, Florida 33904 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs BRET JAYSON BOREK, 05-001686PL (2005)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida May 12, 2005 Number: 05-001686PL Latest Update: Jun. 02, 2006

The Issue The issue for determination is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what action should be taken.

Findings Of Fact At all times material hereto, Mr. Borek was licensed by the Department as a certified general contractor, having been issued license number CG C 58817. He was licensed on November 18, 1996. At all times material hereto, Mr. Borek was the qualifying agent of Atlantic Coast General Contractors, Inc. (ACGC), a Florida corporation, and has been its president. ACGC was issued a certificate of authority as a contractor qualified business on June 2, 1977, having been issued license number QB 07357. ACGC's license expired on September 1, 2001 and became null and void on September 1, 2003. The State of Florida, Department of State, administratively dissolved ACGC, as a corporation, on October 1, 2004, for its failure to file its annual report, as required by law; and, as a result, ACGC's authority to transact business, as a corporation, in the State of Florida was revoked on the same date. At all times material hereto, Tracey Meredith (Ms. T. Meredith) resided in and owned a home located at 7690 Northwest 16th Court, Pembroke Pines, Florida. Ms. T. Meredith wanted her mother, Jane Meredith1 (Ms. J. Meredith), to live with her so Ms. T. Meredith decided to have an addition built to her home, consisting of a bedroom, bathroom, and closet. Ms. T. Meredith obtained a proposal from ACGC and five other contractors for the addition. Each contractor was aware of the purpose of the addition. Ms. T. Meredith decided to contract with ACGC, which was not the lowest or the highest bidder, but was somewhat in the middle. On June 28, 2002, a Proposal/Contract (Contract) was executed with ACGC for the addition at a cost of $32,925.00. Even though the Contract showed Ms. T. Meredith as the contracting party, it was signed by Ms. J. Meredith because she (Ms. J. Meredith) was actually paying for the addition and signing the checks. Both Mses. T. Meredith and J. Meredith were in agreement with the Contract. The Contract provided, among other things, that the addition was 15 x 21; and that the payments would be as follows: 20% at acceptance of the Contract, 20% at permit issuance, 10% at slab, 20% at wall and roof framing, 10% at roof completion, 10% at finished walls and flooring, and 10% at final completion. No dispute exists that the cost of the Contract was reasonable. No dispute exists that the Contract failed to contain a provision explaining the consumer's rights under the Florida Homeowners' Construction Recovery Fund, formerly known as the Construction Industries Recovery Fund. No dispute exists that the Contract did not provide a date for completion of the addition. Regarding a completion date for the addition, Ms. T. Meredith testified that all the other proposals provided that the addition would be completed within six to eight weeks and that, at the beginning, Mr. Borek orally communicated to her that the addition would be completed by ACGC within six to eight weeks. To the contrary, Mr. Borek testified that, at the beginning, no completion date was given to her, either orally or in writing. None of the other proposals were submitted into evidence, only the Contract with Mr. Borek, which did not provide a completion date. It would not be reasonable for Ms. T. Meredith to accept Mr. Borek's proposal without it’s being within the time period of completion of the other proposals. The undersigned finds Ms. T. Meredith's testimony more credible and makes a finding of fact that, at the time of the signing of the Contract, Mr. Borek made an oral representation that the addition would be completed by ACGC within six to eight weeks. An expert in the field of general contracting, John Yanoviak (Mr. Yanoviak), testified on behalf of the Department. The undersigned finds his testimony credible, except as specifically indicated. A reasonable amount of time to complete the addition was a maximum of three months. Mr. Borek, as the contractor, was responsible for keeping the project timely and for quality control. On June 30, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,585.00. This amount was 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. Paying this amount was in accordance with the Contract. Mr. Borek filed an application for a building permit with the City of Pembroke Pines (CPP) on or about July 3, 2002. The building permit was issued by CPP on or about October 25, 2002. Work on the addition was commenced before the issuance of the building permit. Ms. T. Meredith was aware of the date that the building permit was issued. Prior to the issuance of the building permit, Ms. T. Meredith complained to Mr. Borek regarding the addition’s not being completed. No evidence was presented to show that Ms. T. Meredith indicated to Mr. Borek that, by his failure to complete the addition within a six-to- eight-week period, he was not abiding by the Contract. No evidence was presented to show that she indicated her dissatisfaction to the degree of possibly terminating the Contract with ACGC. On November 12, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,585.00. This amount was paid after Mr. Borek obtained the building permit and was 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. Paying this amount was in accordance with the Contract. On December 11, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,885.00. This amount was $300.00 more than 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. An inference is drawn and a finding is made that this check was written in advancing of the addition. According to the records of the CPP's building department2 (Records), a CPP form for a revision to the addition was submitted on January 6, 2003, providing for an electrical change to the addition. Further, the Records indicate that, on March 20, 2003, an application for an electrical permit was submitted and that, on March 24, 2003, the permit was approved. Also, a revision to the plans of the addition was submitted to the CPP by the architect to the addition, Hernando Acosta, according to the Records. The Records indicate that the revision to the plans was dated January 30, 2003 by Mr. Acosta, that the revision was submitted on February 7, 2003, and that the revision was approved on February 11, 2003 by the CPP. In addition, in February 2003, Ms. T. Meredith received written communication from the CPP regarding a problem with the addition. Ms. T. Meredith received a copy of a letter from the CPP to Mr. Borek, dated February 18, 2003. The letter indicated, among other things, that the CPP had issued a "stop work status" on the addition due to Mr. Borek’s having issued a check, payable to the CPP, in the amount of $135.80, which was dishonored. Another revision, according to the Records, was submitted on March 27, 2003, regarding the trusses. The Records indicate that the revision was approved on April 17, 2003. Ms. T. Meredith became more dissatisfied with the progress toward completion on the addition by Mr. Borek to the point that she filed a complaint with the Department on May 21, 2003. In May 2003, Ms. T. Meredith received written communication from the CPP regarding a problem with the addition. By letter dated May 22, 2003, she received notification from the CPP, as information only, that a code violation had not been corrected within the allowable ten-day period, together with a copy of CPP's letter to Mr. Borek, dated May 22, 2003, of his failure to correct the code violation. The letter to Mr. Borek indicated, among other things, that Mr. Borek had until June 11, 2003 to correct the violation, identifying the inspection date and the violation. By a letter dated May 28, 2003, Ms. T. Meredith advised Mr. Borek, among other things, that he had seven days to continue with the work on the addition in accordance with the Contract or else the Contract would be considered by her to be "null and void"; that, if he did not do so, she would be "forced" to hire another contractor, with Mr. Borek being held financially responsible for completion of the addition; and that the Contract was to be completed within six to eight weeks. On June 12, 2003, Mr. Borek contacted the investigator for the Department regarding the complaint filed by Ms. T. Meredith. Among other things, Mr. Borek informed the investigator that he (Mr. Borek) was willing to complete the addition in 30 days. By his representation, Mr. Borek indicated that he would complete the addition on or about July 12, 2003. By a letter dated June 18, 2003, Mr. Borek notified the investigator, among other things, that he was working "diligently" to complete the addition. Mr. Borek failed to complete the addition within the 30-day period, as he had represented to the Department's investigator. The Records indicate that an application for a building permit, involving the roof to the addition, was submitted on June 25, 2003. The permit was issued, according to the Records, on July 30, 2003. Further, the Records indicate that a revision, regarding the size of a window and the elimination of a door, was submitted on July 8, 2003, and approved on July 9, 2003. In July 2003, Ms. T. Meredith received another written communication from the CPP regarding a problem with the addition. By letter dated July 9, 2003, she received notification from the CPP, as information only, that a code violation had not been corrected within the allowable ten-day period, together with a copy of CPP's letter to Mr. Borek, dated July 9, 2003, of his failure to correct the code violation. The letter to Mr. Borek indicated, among other things, that Mr. Borek had until July 28, 2003, to correct the violation, identifying the inspection date and the violation. In addition, in July 2003, Ms. T. Meredith received written communication from the CPP regarding another problem with the addition. She received a copy of a letter from the CPP to Mr. Borek, dated July 18, 2003, which indicated, among other things, that the CPP had issued a "stop work status" on the addition due to Mr. Borek having issued a check, payable to the CPP, in amount of $76.23, which was dishonored. Even though Mr. Borek failed to complete the addition within the 30-day period that he had represented to the Department's investigator and even though Ms. T. Meredith had received notification of the problems at the jobsite from the CPP, on September 10, 2003, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $4,000.00. No dispute exists that this check was written and presented to Mr. Borek. An inference is drawn and a finding is made that this check was written in furtherance of the addition. ACGC had been paid a total of $24,055.00 of the Contract cost of $32,925.00, which was approximately 73 percent of the Contract cost. The balance of the Contract cost was $8,870.00. Mr. Borek testified that, at the time of the writing of the check for $4,000.00, he and Ms. T. Meredith agreed that he would have until on or about November 15, 2003 to complete the project. Ms. T. Meredith testified that no such agreement was made. At the time of the check for $4,000, ACGC was almost 60 days beyond the completion date represented to the Department's investigator. No testimony was presented as to why the $4,000.00 was paid to ACGC in light of such a considerable delay in completing the job by ACGC and in light of the complaint being filed with the Department. Due to the lack of an explanation for the payment of the $4,000.00 to ACGC in furtherance of the project, Mr. Borek's testimony presents a reasonable explanation. Therefore, Mr. Borek's testimony is found to be credible. Hence, a finding is made that, on or about September 10, 2003, Mr. Borek and Ms. T. Meredith orally agreed that ACGC would have until on or about November 15, 2003, to complete the addition. Ms. T. Meredith continued to be dissatisfied with the progress on the addition by ACGC. Sometime after September 10, 2003, an incident occurred which caused her to reach the conclusion that she could not allow ACGC to continue working on the project. One day when she left for work, one of ACGC's workers was painting the exterior walls. When she returned from work later that same day, the same worker for ACGC was painting the exterior walls. Ms. T. Meredith immediately directed the worker to leave and to take all of his equipment with him; the worker did so. Ms. T. Meredith contacted Mr. Borek and informed him that she would not allow him to continue with the project. Mr. Borek repeatedly requested Ms. T. Meredith to allow him to continue with the project, but she refused. By letter dated October 9, 2003, Ms. T. Meredith terminated the Contract with ACGC. She mailed the letter on the same date and faxed it on October 14, 2003. Her mother was in agreement with terminating the Contract. Ms. T. Meredith indicated, among other things, in her letter to ACGC that its failure to complete the addition as of the date of the letter, when the oral agreement was completion within six to eight weeks, left her no choice but to terminate the Contract. Ms. T. Meredith included in the letter, among other things, what remained to be completed on the project and a cost of $539.55 for damaged items at her home caused by ACGC, with an itemized list. At the time of the termination, the following work remained to be completed: purchase and installation of plumbing fixtures; sewer hookup; molding; tile work in the bathroom; installation of storm panels and flooring; some painting; installation of an air conditioner; some electrical connections; and installation of an electrical panel, electric wall plates, and an electric light fixture. Ms. T. Meredith obtained a homeowner's permit and hired someone, Adam Friedman, to assist her in completing the addition. On December 15, 2003, the CPP issued a certificate of occupancy to her. As to expenditures by Mses. T. and J. Meredith in order to complete the addition, the undersigned finds the testimony of Mr. Yanoviak credible. Mses. T. and J. Meredith expended $19,170.52 to complete the addition. The expenditures for completion were reasonable and necessary. Not included in the expenditures for completion are the following: $3,941.31 for items not included in the Contract--a fence, pavers, wood floor, upgraded bathroom fixtures or accessories, closet woodwork and various Home Depot items (totaling $238.21); $250.00 for mill work associated with chair rails; and $2,400.00 for an exterior concrete slab. Included in the expenditures for completion is the following: $1,360.00 for a split-system air conditioning unit which was not installed by ACGC. Further, included in the cost of expenditures is an adjustment in favor of Ms. T. Meredith in the amount of $1,000.00 for the elimination of a window on the west elevation of the addition, which was orally agreed to by Ms. T. Meredith and Mr. Borek after the signing of the Contract and which would have been subtracted from the cost of the Contract. After Ms. T. Meredith terminated the Contract, she filed a claim under the Construction Industries Recovery Fund. The claim was dated October 10, 2003, one day after she terminated the Contract. Ms. T. Meredith set forth in the claim that she was requesting $12,000.00, which she indicated was the amount to pay another contractor to complete the project. The undersigned places very little weight upon the amount requested because the claim is prior to completing the project and fails to reflect the actual costs involved in completing the project, which were realized only after completion. Damage to items at Ms. T. Meredith's home occurred, during the work being performed by ACGC, for which ACGC was responsible. The following items were affected: damaged a window magnet that was part of the home's security system at $80.00; destroyed, broken, or thrown away one large planter pot, one archway, and two large stepping stones--all at an estimate of $440.34; and broken tiles in the front of the house at $13.57. The damages totaled $533.91. At the time of the hearing, Mr. Borek had not made any payments to Ms. T. Meredith or Ms. J. Meredith for their expenditures to complete the addition or for the damages. At the time of the termination, in accordance with the oral agreement of completion by on or about November 15, 2003, ACGC had a little over 30 days to complete the addition. In light of the finding that an oral agreement had been reached to allow ACGC until on or about November 15, 2003, to complete the addition and in light of the only incident since that agreement, presented by the evidence, was the situation involving ACGC's painter, the undersigned finds that the painting situation was not substantial and that, therefore, the termination on October 9, 2003, prior to the new agreed- upon termination date, was unreasonable. Ms. T. Meredith testified that, sometime during the middle of the year 2003, for a period of "exactly" 60 days, ACGC failed to perform any work at the project. Mr. Borek denies her assertion. Ms. T. Meredith testified that she kept records on everything. When she testified as to an exact 60- day period in the middle of 2003 during which no work was being done at the project, Ms. T. Meredith did not point to any of her records to verify the assertion or provide certain beginning and ending dates. Taking into consideration the standard of proof and the burden of proof, the evidence failed to show clearly and convincingly that no work was done at the jobsite by ACGC for a period of 60 days in the middle of the year 2003. Nothing was done by Ms. T. Meredith, the architect, or CPP to delay the completion of the project. Mr. Borek admits that he had other jobs in progress when he was working on the addition. He further admits that when changes had to be made to the project, whether by the CPP or the architect or Ms. T. Meredith or himself, he had to re- arrange his schedule to accommodate the other jobs, which included re-deploying his workers and subcontractors, which in turn caused delays. Further, Mr. Borek admits that the turnaround time for any changes given to the architect for the plans to the addition was reasonable and that the turnaround time for the CPP to review the changes to the plans submitted by the architect was reasonable. Consequently, no unreasonable or inordinate delays were caused by the architect or the CPP when changes were made to the plans of the addition. Mr. Borek performed some work for Ms. T. Meredith at no cost that was not required by the Contract. The extra work at no cost included the following: the removal of trees; pouring of an exterior concrete slab; and plastering of drywall. The slow progress in completing the Contract was significant and material and resulted in the Contract’s not being performed in a reasonable time. The delays in completion of the addition were significant and were the fault of Mr. Borek. In addition to re-deploying workers for other jobs on which ACGC was working, ACGC failed to properly perform work, which resulted in failed inspections by the CPP, which resulted in numerous delays, and failed to timely obtain an electrical permit. As to the failure to timely obtain an electrical permit, the electrical permit was obtained almost five months subsequent to the issuance of the building permit by the CPP. The electrical permit was applied for on March 20, 2003 and approved on March 24, 2003. CPP's turnaround time in approving the permit was short and inconsequential. As to the failure to properly perform work, the Records indicate construction defects, which were under Mr. Borek's, the contractor's, control and which resulted in failed inspections. Furthermore, the Records indicate prior construction faults, identified in inspections, not being timely corrected, which was under Mr. Borek's control and which resulted in delays until the faults were corrected. Mr. Yanoviak testified that failure to perform the Contract within a reasonable time constituted misconduct. The undersigned finds his testimony credible. A finding of fact is made that the failure to perform the Contract within a reasonable time constituted misconduct. Additionally, Mr. Yanoviak testified that the failure to perform the Contract within a reasonable time constituted a material breach of the Contract. The undersigned finds his testimony credible, and a finding of fact is made that the failure to perform the Contract within a reasonable time constituted a material breach of the Contract. Further, Mr. Yanoviak testified that, such material breach, justified terminating the Contract. The undersigned finds his testimony credible only as to a general application and, therefore, a finding of fact is made that, generally, the failure to perform a construction contract within a reasonable time would justify terminating the construction contract but does not justify terminating the Contract under the circumstances presented in the instant case. Both Mr. Borek and Ms. T. Meredith orally agreed to a new date for completion of the addition, i.e., on or about November 15, 2003. To disregard the new date of completion would be manifestly unjust. Furthermore, at the time of the termination of the Contract by Ms. T. Meredith, i.e., on October 9, 2003, the termination was unreasonable and not for just cause. Hence, a finding of fact is made that termination of the Contract by Ms. T. Meredith, prior to the new completion date, was not justified. Mr. Yanoviak also testified that failure to perform the Contract within a reasonable time constituted abandonment of the project. The undersigned finds his testimony credible only as to general application and, therefore, a finding of fact is made that, generally, the failure to perform a construction contract within a reasonable time would constitute abandonment of a project. However, as found above, a new date for completion of the project was orally agreed upon and the new date had not expired at the time of the termination of the Contract by Ms. T. Meredith. Hence, a finding of fact is made that, under the circumstances of the instant case, abandonment did not exist. The Department presented evidence of costs for the investigation and prosecution of this matter, excluding costs associated with attorney time. As of July 5, 2005, the costs for the investigation and prosecution totaled $880.18. As to prior disciplinary action, on September 9, 2004, the Department filed a Final Order in Department of Business and Professional Regulation vs. Bret Jayson Borek, Case No. 2003-069533, License No. CG Co58817 before the Construction Industry Licensing Board. In that case, an administrative complaint was filed against Mr. Borek for violating Section 489.129(1)(i), Florida Statutes (2001), by failing to comply in a material respect with a provision of Chapter 489, Florida Statutes, through the failure to obtain a certificate of authority for ACGC; and for violating Section 489.129(1)(q), Florida Statutes (2001), by failing to satisfy a civil judgment, related to the practice of construction, within a reasonable time. Mr. Borek waived his rights to an informal hearing, and no material fact was disputed. Among other things, the Final Order imposed an administrative fine of $1,000.00, required restitution of $15,218.94 to a roofing and sheet metal company and required payment of $506.92 for investigative costs.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order: Finding that Bret Jayson Borek committed the violations set forth in Counts I, II, and III; Dismissing Count IV; and Imposing the following penalties: As to Count I, an administrative fine in the amount of $1,000.00 and revocation of the license of Bret Jayson Borek. As to Count II, an administrative fine in the amount of $500.00. As to Count III, an administrative fine in the amount of $5,000.00 and revocation of the license of Bret Jayson Borek. S DONE AND ENTERED this 9th day of January, 2006, in Tallahassee, Leon County, Florida. _______________________________ ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2006.

Florida Laws (10) 120.569120.5717.00117.002455.227489.119489.1195489.129489.1425941.31
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIAM LOSCIALE, 89-003297 (1989)
Division of Administrative Hearings, Florida Number: 89-003297 Latest Update: Oct. 19, 1989

Findings Of Fact At all times material hereto, Respondent, William Losciale, was a licensed registered pool contractor in the State of Florida, having been issued license number RP-0032951, by the State of Florida, and was the qualifier of Lynn Pools. On June 9, 1987, Respondent entered into a contract with Kevin D. Foy for the construction of a pool with a screen enclosure on Mr. Foy's property for the sum of $12,000.00. On August 12, 1987, Mr. Foy made his final payment to the Respondent for the pool and enclosure and all related work. On June 9, 1987, Respondent entered into a contract with Harold Orcutt for the construction of a pool with a screen enclosure on Mr. Orcutt's property for the sum of $18,015.00. On August 1, 1987, Mr. Orcutt made his final payment to the Respondent for the pool and enclosure and all related work. On May 12, 1987, Respondent entered into a contract with Ann McAuley for the construction of a pool with a screen enclosure on Ms. McAuley's property for the sum of $14,204.08. On September 18, 1987, Ms. McAuley made her final payment to the Respondent for the pool and enclosure and all related work. At the end of September, 1987, the Respondent entered into an oral contract with Paragon Aluminum Products, Inc. to have Paragon Aluminum Products, Inc., install the pool enclosure at the Foy residence, pursuance to the Respondent's contract with the Foys. The total Paragon contract price was $3,975.00 which was to be paid by the Respondent to Paragon within two weeks of October 6, 1987, which was the completion date. The Respondent failed to pay that amount in a timely manner. On or about July 16, 1987, the Respondent entered into an oral contract with Paragon Aluminum Products, Inc. to have Paragon Aluminum Products, Inc., install the pool enclosure at the Orcutt residence pursuant to the Respondent's contract with the Orcutts. The total Paragon contract price was $4,910.00, which was to be paid by the Respondent to Paragon within two weeks of the first part of August, 1987, which was the completion date. The Respondent made a partial payment on August 17, 1987, of $3,015.00 and the balance of $895.00 was not paid in a timely manner. On or about July 20, 1987, the Respondent entered into an oral contract with Paragon Aluminum Products, Inc. to have Paragon Aluminum Products, Inc., install a pool enclosure at the McAuley residence pursuant to the Respondent's contract with Ms. McAuley. The total Paragon contract price was $4,321.00 which was to be paid by the Respondent to Paragon within two weeks of August 5, 1987, which was the completion date. The Respondent made a partial payment on September 12, 1987, of $2,704.08 which left a balance of $1,616.92 which was not paid in a timely manner. When the Respondent failed to timely pay Paragon Aluminum Products, Inc., at the end of the foregoing jobs, an officer of Paragon contacted the Citrus County Building Department in an effort to have that department aid her in collection of the monies owed. The Respondent admitted to an investigator of the Department of Professional Regulation on June 7, 1988, that he was having cash problems in relation to the three jobs, that all work had been completed, but due to those cash flow problems, Paragon had not been paid in full. The Respondent signed a personal promissory note for the full amount due to Paragon. No liens were ever filed by Paragon. The Respondent's county license was suspended the Citrus County Licensing Board on May 11, 1988, until he was able to show financial responsibility to that board. That suspension was lifted by the Citrus County Licensing Board on October 12, 1988. Respondent has previously been disciplined by the Florida Construction Industry Licensing Board.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order and therein penalize the Respondent, William Losciale, as follows: Assess a fine of $1500 for the violation of Section 489.129(1)(i) Dismiss the remaining charges made in the Administrative Complaint. DONE and ENTERED this 19th day of October, 1989, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October, 1989.

Florida Laws (3) 120.57489.129704.08
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. FRED S. PETERSON, 89-000752 (1989)
Division of Administrative Hearings, Florida Number: 89-000752 Latest Update: Jun. 11, 1990

The Issue Whether Respondent aided and abetted an unlicensed contractor to engage in contracting by pulling permits for the unlicensed contractor; whether Respondent failed to qualify a firm for whom he was acting as licensed contractor; whether Respondent acted in the capacity of a contractor other than in his own name; and, whether Respondent violated local building codes as alleged in Second Amended Administrative Complaint filed 6-30-89, and Administrative Complaint filed 7-26-89.

Findings Of Fact At all times relevant hereto, Fred S. Petersen was licensed as a general contractor by the Florida Construction Industry Licensing Board (FCILB) and issued License Nos. CG C023928 and CB CA23929 (Exhibit 1). Neither American Weatherall Industries Inc. (AWI), Mel C. Wyatt, nor Steven C. Wyatt were licensed as contractors by the FCILB (Exhibit 2). Prior to mid-August 1987, Kirk Evenstad was the qualifying general contractor for AWI. By letter dated August 20, 1987, AWI proclaimed Kirk Evenstad to be no longer working for AWI because of mismanagement (Exhibit 3). Mel Wyatt, President of AWI, testified that Everstad had stolen between $30,000 and $50,000 of materials from AWI, leaving AWI in a precarious financial situation. In order to continue in business to work out of the financial hole created by Everstad, AWI, through one of its employees, Danny O'Brien, introduced Mel Wyatt to Respondent. Respondent had known O'Brien for some 20 years and, for the proposed reason of helping O'Brien, Respondent agreed to act as qualifying contractor for AWI. To carry out this project, Respondent entered into a contract (Exhibit 4) or Employment Agreement dated July 31, 1987, in which Respondent agreed to supervise construction of projects contracted for by AWI, but the latter was to provide all material and handle all financial aspects of the contracts. Respondent received $1000 for signing this agreement and was to receive a percentage of the gross proceeds of future contracts entered into by AWI. Respondent authorized O'Brien to pull permits for AWI pursuant to Respondent's contractor's license. Although Respondent testified he gave O'Brien authorization for each specific permit pulled and did not believe he signed Exhibit 11, dated August 11, 1987, a copy of General Authorization for O'Brien to pull permits for AWI under Respondent's license, it is found as a fact that Respondent signed the original of Exhibit 11 which is a copy. Within a short period of time after executing Exhibit 4, Respondent became aware of the financial difficulties facing AWI and ceased his efforts to qualify AWI. In the latter part of 1987 (believed to be November-December), AWI reached the point that it could no longer remain solvent and filed for bankruptcy leaving several contracts unfinished for which AWI had received partial payment. Of the four contracts entered into between AWI and homeowners for additions to their houses (Exhibits 7-9 and 14), all were entered into under a printed document showing Everstad's license number; however, the building permits for Exhibits 7-9 were pulled under Respondent's license. By agreement dated August 10, 1987 (Exhibit 7), Alfred and Marjory Hauk contracted with AWI to convert a garage at their home into an office. Hauk made payments of $1000 and $2300 to AWI, the permit for the work was pulled by O'Brien under Respondent's license, but no work was ever done under this contract. AMI subsequently went out of business, and Hauk received no refund of the monies he had paid to AMI. Hauk never met Respondent. On June 12, 1987, John Davis contracted with AWI to convert an existing garage to bedroom and bath and add a garage to his home. The initial permit for this work was pulled by Kenn Covicc as contractor on June 21, 1987, and a subsequent permit was pulled by O'Brien using Respondent's license. Although Davis paid over $6000 to AWI for this work, the work stopped after the footing for the garage addition was poured. On June 2, 1987, Albert Charette entered into a contract with AWI to add a room to his house. Charette paid some $9300 of the $34,400 contract amount during the progress of the work. Differences arose between Charette and AWI involving whether the construction was being done in accordance with the plans and specifications. In September, 1987, Respondent met with Charette and submitted a proposal (Exhibit 15) to Charette to complete the project in accordance with the plans and specifications. About one week after Exhibit 15 was signed, all work stopped on the project, and Respondent never received compensation or commenced work on this contract, which he had entered into in his own name and not as a representative of AWI.

Recommendation It is recommended that Fred S. Petersen be found guilty of violating Sections 489.129(1)(e), (f) and (g), Florida Statutes, and assessed a monetary fine of $3000. ENTERED this 11th day of June, 1990, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of June, 1990. APPENDIX Proposed findings submitted by Petitioner are accepted, except: Finding #7, penultimate sentence which is rejected as uncorroborated hearsay. Finding #11, that portion stating the purpose of Petersen's visit to Charette was to change the licensure on the permit to Petersen is rejected. See HO #13. Proposed findings submitted by Respondent are accepted, except: Finding #4, Accepted, except with regard to Respondent's notification of termination of his association with AWI. No documentation of this act was submitted and, even though Respondent may have ultimately revoked O'Brien's authority to pull permits, this was done well after the permits were pulled. COPIES FURNISHED: Robert B. Jurand, Esquire G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Brian A. Burden, Esquire Post Office Box 2893 Tampa, FL 33601 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth E. Easley General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792

Florida Laws (1) 489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. HAMILTON, 81-001925 (1981)
Division of Administrative Hearings, Florida Number: 81-001925 Latest Update: May 17, 1982

The Issue The issues presented in this case concern certain allegations made by the Petitioner against the Respondent through an Administrative Complaint. In particular, it is alleged that on or about April 23, 1980, the Respondent's contractor's license issued by the Petitioner was suspended and subsequent to that time, the Respondent continued to perform contracting services through a company, David H. Hamilton, Inc., a corporation which was not properly qualified by the Petitioner to provide contracting services. It is further alleged by the Petitioner that the Respondent obtained building permits Nos. S2740-80B 1/ and 3214-80B from the Osceola County Building Department with the use of another contractor's license, namely: Louie S. Winchester, license #RR003839. For the reason of these facts, the Petitioner alleges that the Respondent has violated Subsection 489.127(1)(e), Florida Statutes, in that he attempted to use a suspended registration. It is further alleged, based upon the facts as reported in this Issues statement, that the Respondent has violated Subsection 489.129(1)(g), Florida Statutes, by acting in a capacity as a contractor under a certificate of registration not in his name. Finally, it is alleged, based upon the facts as reported hereinabove, that the Respondent has violated Subsection 489.129(1)(j), Florida Statutes, by failing to comply with Subsection 489.119(2), Florida Statutes, by not properly qualifying a corporation under which he performed contracting services.

Findings Of Fact The case presented concerns license disciplinary action by the Petitioner, State of Florida, Department of Professional Regulation, Florida Construction Industry Licensing Board, against the Respondent, David H. Hamilton, who holds a residential contractor's license issued by the Petitioner, #RR0014037. The prosecution of this action is through the offices of the Department of Professional Regulation and the outcome of the matter could lead to the revocation, suspension or other disciplinary action against the Respondent, in keeping with the provisions of Chapter 489, Florida Statutes. This case was presented before the Division of Administrative Hearings following a decision on the part of the Respondent to request a formal hearing pursuant to Subsection 120.57(1), Florida Statutes. The facts reveal that a Final Order of the Florida Construction Industry Licensing Board was issued on April 23, 1980, and this order established disciplinary action against the current license of David H. Hamilton. (A copy of this Final Order may be found as a part of the record in this proceeding and official recognition of that Final Order is made by the Recommended Order process.) This Final Order was entered after review of a Recommended Order of a Division of Administrative Hearings' Hearing Officer. By the terms of the Final Order, Hamilton's license was suspended "until such time as his Lake County Certificate of Competency is reinstated by the Lake County Board of Examiners." This contingency referred to the fact that the Respondent had his Lake County Certificate of Competency Card removed prior to the entry of the April 23, 1980, order of the Construction Industry Licensing Board. On September 2, 1980, at a time when the Respondent's residential contractor's license was under suspension by the State of Florida, the Respondent through a corporation applied to the Osceola County Building Department for a building permit to construct a residence in Osceola County, Florida. This permit number was #2740-80B. The permit was issued on September 4, 1980, and was granted in the name of David Hamilton, Inc., a corporation in which the Respondent was a principal. To obtain the permit in the sense of an effort to meet the requirements that the permit be applied for by a licensed Florida contractor, the Respondent used the registered residential contractor's license of one Louie Stevens Winchester who held license #RR003839 issued by the Florida Construction Industry Licensing Board. On the occasion of the issuance of the permit by Osceola County, Winchester was an officer of David Hamilton, Inc. Through the action of "pulling" this permit and the utilization of the permit in his construction of the residence, the Respondent was acting in the capacity of contractor under Winchester's license and the offices of the corporation, as opposed to the Respondent's suspended license. Prior to the request for permit, neither Hamilton nor Winchester had attempted to properly qualify David Hamilton, Inc., as a contracting corporation with the Florida Construction Industry Licensing Board. In this case, to properly qualify the corporation, it would have entailed the use of Winchester as the qualifying agent, in view of the fact that Winchester still held a valid contractor's license from the Florida Construction Industry Licensing Board. No effort was made to qualify David Hamilton, Inc., in its own right, through the agency of Winchester, until some time shortly beyond December 1, 1980. On October 28, 1980, the Respondent in his individual capacity, that is to say unconnected with his business pursuits as David Hamilton, Inc., went to the Osceola Building Department and applied for the issuance of a building permit for a home remodeling project for a customer of his. The permit in question on this occasion was #3214-80B. That permit was issued on October 29, 1930, and was used by the Respondent in his building project. An official in the Osceola County Building Department had checked with an employee in the Lake County Building Department on the status of Hamilton's rights to be employed as a building contractor in Lake County, Florida, and was informed that Hamilton's status in Lake County was acceptable. Based upon these representations, the Osceola County employee issued the permit discussed in this paragraph to Hamilton. The Osceola County employee also asked that the Lake County employee formally confirm Hamilton's status. The correspondence in response to Osceola County employee, John Pate, Assistant Building Director, as issued by an official in Lake County, one Herb Dudgeon, may be found as Petitioner's Exhibit No. 3. This letter was received by Pate after the permit was issued. That correspondence indicates that Hamilton had been given the privilege of reinstating his Lake County Competence Card, contingent upon "providing bond, insurances, occupational license, etc.," which had not been received by Lake County as of the date of the correspondence. The correspondence goes on to mention that the State, meaning the Florida Construction Industry Licensing Board, was waiting for confirmation of the completion of the contingencies referred to. Subsequent to this correspondence, the Respondent having completed all the necessary steps for reinstatement of the Lake County Competency Card, had his license suspension removed and was reinstated by the Florida Construction Industry Licensing Board, as verified by that body.

Recommendation Based upon a full consideration of the findings of fact and conclusions of law reached herein, it is RECOMMENDED: That the Florida Construction Industry Licensing Board issue a Final Order which absolves the Respondent of any responsibility for a violation of Subsection 489.127(1)(e), Florida Statutes (1980); that finds the Respondent in violation of Subsection 489.129(1)(g), Florida Statutes (1979), and imposes a penalty of a 60-day suspension; and that finds the Respondent in violation of Subsection 489.129(1)(j), Florida Statutes (1979), and imposes a suspension of 60 days to run concurrently with the other suspension in this paragraph of recommendation. 2/ DONE and ENTERED this 13th day of November, 1981, in Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of November, 1981.

Florida Laws (4) 120.57489.119489.127489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs JULIUS S. BAKER, 92-000591 (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jan. 31, 1992 Number: 92-000591 Latest Update: Aug. 08, 1994

The Issue The issue to be resolved in this proceeding involves whether the Respondent's certification to practice contracting should be subjected to disciplinary action for alleged violations of Section 489.129(1), Florida Statutes, and, if the violations are proven, what, if any, penalty is warranted.

Findings Of Fact The Petitioner is an agency of the State of Florida charged, as pertinent hereto, with enforcing, administering, and regulating the practice standards and licensure standards for the construction industry in Florida. This authority is embodied in the various provisions of Chapters 489, 455, and 120, Florida Statutes, and rules promulgated pursuant thereto. The Respondent is a licensed general contractor in the State of Florida having been issued license number RG0060516 and is registered to conduct contracting business in his individual capacity. On July 2, 1990, a contractor, Lonnie J. Walker, notified the Building Department of the City of Tallahassee that he had withdrawn as contractor for a job located at 722 Dunn Street, in Tallahassee, Florida. He thereupon withdrew the building permit he had obtained for the work being performed at those premises. On August 8, 1990, the Respondent contracted with Mary N. Spencer, the owner, to make certain repairs at the two-unit apartment building located at 722 Dunn Street, Tallahassee, Leon County, Florida. The contract price agreed upon between the Respondent and Ms. Spencer was $867.00. The Respondent thereupon performed some of the aforementioned contracting work, consisting of repairs of various types. He was not registered to contract in Leon County, Florida, however. The Department of Growth and Environmental Management of Leon County, Florida, is responsible for issuing construction contractor licenses for the County, including for the City of Tallahassee. There was no proper building permit issued for the job and job site when the Respondent entered into the contracting work at those premises. The Respondent failed to obtain a permit for the repairs and this ultimately came to the attention of the City of Tallahassee Building Department. That agency issued a stop work order on September 5, 1990. The Respondent was not performing work pursuant to Mr. Walker's previous permit, which had been withdrawn. The Respondent was not an employee of Lonnie J. Walker, the previous general contractor for the job. The Petitioner agency submitted an affidavit after the hearing and close of the evidence, with its Proposed Recommended Order. That affidavit asserts that the Petitioner accumulated $458.10 in investigative costs and $2,491.30 in legal costs associated with the prosecution of this case, for a total alleged cost of prosecution of $2,949.40. It moves, in its Proposed Recommended Order, that payment of the costs should be made in accordance with Section 61G4-12.008, Florida Administrative Code. The request for costs was first raised as an issue in the Proposed Recommended Order submitted by the Petitioner and is advanced only in the form of a hearsay affidavit. No prior motion for costs served upon the Respondent is of record in this proceeding.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered by the Construction Industry Licensing Board finding the Respondent guilty of the violations charged in the Administrative Complaint and assessing a penalty in the form of a letter of guidance and an aggregate fine of $600.00, as described with more particularity hereinabove. DONE AND ENTERED this 9th day of March, 1994, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of March, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-591 Petitioner's Proposed Findings of Fact 1-8. Accepted. Respondent's Proposed Findings of Fact Respondent submitted no post-hearing pleading. COPIES FURNISHED: G.W. Harrell, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Julius S. Baker, Sr. Box 253 Morrow, GA 30260 Mr. Richard Hickok Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway Suite 300 Jacksonville, FL 32211-7467 Jack McRay, Esq. General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792

Florida Laws (4) 120.5717.001489.117489.129 Florida Administrative Code (1) 61G4-12.008
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ALVIN C. SMITH, 82-000705 (1982)
Division of Administrative Hearings, Florida Number: 82-000705 Latest Update: Jan. 31, 1983

Findings Of Fact Respondent is a certified general contractor holding license number CG C008351. Respondent obtained Osceola County Building Permits and agreed to help property owners construct improvements or additions to four motels located in Osceola County, Florida. (Testimony of Record, Popesco, Matay, Solms, respondent.) Specifically, on January 29, 1980, respondent pulled Osceola County Building Permit ("building permit") No. 364-80B to construct the Record Motel, an 11-unit motel owned by Frank B. Record. On March 17, 1981, respondent pulled building permit No. 694-81B to construct a five-unit addition to the Record Motel; on January 30, 1980, he pulled building permit No. 2613-80B to add eight units to the Lakeview Motel owned by Michael Popesco; on February 2, 1980, he pulled building permit No. 2996-81B to construct a 20-unit motel known as The Key Motel, owned by Reinhold Matay; on April 8, 1981, he pulled building permit No. 3087-81B to construct a second floor addition to The Key Motel; and on March 2, 1981, he pulled building permit No. 3038-81B to construct a 20-unit motel known as the Siesta Motel, owned by Herbert Solms. (Stipulation dated June 30, 1982.) II. Respondent had a similar working arrangement with each motel owner, none of whom were licensed contractors. As the general contractor, he pulled the necessary building permits. He would perform the carpentry work on each project. The owners actively supervised and participated in their building projects. After consulting with respondent, they solicited, selected, and awarded bids to electrical, masonry plumbing, paving, and drywall subcontractors. They paid subcontractors directly and supervised their work daily. Respondent, however, would inspect the job sites intermittently, usually on weekends, sometimes during the week. But he did not directly and actively supervise the subcontractors; some were even unaware that he was the general contractor for the job. (Testimony of Record, Popesco, Matay, Solms; P-3, P- 10.) No evidence was presented to establish that the owners, for compensation, constructed these improvements for others or for resale to others. All the buildings were constructed in a satisfactory manner. The buildings passed all inspections, and the owners are entirely satisfied. (Testimony of Record, Popesco, Matay, Solms, respondent.) The owners of the various motels did not act as "contractors" within the meaning of Section 489.105(3), Florida Statutes (1981).

Recommendation Based on the foregoing, it is RECOMMENDED: That the charges against respondent be dismissed. DONE and RECOMMENDED this 14th day of October, 1982, in Tallahassee, Leon County, Florida. R. L. CALEEN, JR., Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of October, 1982.

Florida Laws (7) 120.57489.103489.105489.113489.119489.127489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer