Findings Of Fact At all times relevant hereto, Respondent, Daniel A. Arguelles, held certified general contractor license number CG C004252 issued by Petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. When the events herein occurred, he was qualified as an individual. He presently resides at 9455 Southwest 78th Street, Miami, Florida. Respondent's brother is J. Alejandro Arguelles. Alejandro holds an inactive contractor's license which has been delinquent since July, 1979. In June, 1984, Alejandro was contacted by an individual named Louis Taylor. Taylor told Alejandro that David Reynolds, who resided at 753 Northwest 116th Street, Miami, Florida, wished to add a room to his house. After meeting with Reynolds, Alejandro had plans for the addition prepared, provided an estimate for the job, and gave Reynolds a business card reflecting that he was a licensed general contractor. Reynolds and Alejandro then jointly executed a contract on July 26, 1985, wherein it was provided that A. Arguelles & Associates would construct the room addition for $19,000. The letterhead on which the contract was executed indicated that Alejandro was a general contractor. However, the entity "A. Arguelles & Associates" has never been qualified by any licensee to do construction work in the state. During all negotiations with Reynolds, Alejandro never mentioned that Daniel would be the contractor on the project although Alejandro did advise him that a general contractor would be required. All checks were made out to Alejandro, and Alejandro ordered all supplies and materials used on the project. In addition, Alejandro was at the job site on a regular basis. Prior to signing the contract on July 26, Daniel was approached by Alejandro and asked if he would be willing to act as contractor on the project. Daniel agreed, and thereafter pulled a job permit and used his license number on all pertinent documentation. Other than visiting the job site on a "couple" of occasions, he had no other contact with the project. He never met or had any contact with Reynolds. The actual amount of work done on the project by Alejandro and Daniel amounted to only $5,000.00 and consisted of constructing the foundation up to the tie beam. There is no evidence that this phase of the work was performed in a negligent or incompetent manner.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as set forth in the Conclusions of Law portion of this order, and that he be fined $500.00. DONE and ORDERED this 1st day of October, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of October, 1985. COPIES FURNISHED: Salvatore A. Carpino, Esquire 130 N. Monroe St. Tallahassee, FL 32301 Fred Roche, Secretary Dept. of Professional Regulation 130 N. Monroe St. Tallahassee, FL 32301 Nancy M. Snurkowski, Esquire 130 N. Monroe St. Tallahassee, FL 32301 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board P. O. Box 2 Jacksonville, FL 32201 Mr. Daniel A. Arguelles 9455 S.W. 78th Street Miami, FL 33173
Findings Of Fact At all times material to this proceeding Respondent was a registered building contractor in the State of Florida having been issued license number RB 0009164. At no time material to this proceeding was Domingo Alonzo (a/k/a Domingo Alonzo) registered, certified or otherwise licensed by the Florida Construction Industry Licensing Board. Respondent and Alonzo signed and submitted a proposal to Myron M. Gold and Roberta Fox for remodeling and additions to their residence located at 1550 Zuleta Avenue, Coral Gables, Florida in accordance with plans prepared by Frese - Camner Associates on file with the City of Coral Gables, Florida, File No. 2897 for a contract price of $65,940.00 with draw schedules attached. On December 6, 1982, Myron M. Gold and Roberta Fox (Homeowners) accepted the Proposal (Contract). On December 6, 1982, the Homeowners paid Respondent and Alonzo jointly $3,297.00 in accordance with the contract whereby they were to receive 5 percent of the contract amount as a down payment upon signing. The draw schedule provided for a 10 percent retainage from each draw which was to be paid to Respondent and Alonzo upon completion and the issuance of a certificate of occupancy. On December 21, 1982 the Homeowners paid Respondent and Alonzo jointly $2,025.00 which represented a draw on Schedule I - Item 3 for $1,350.00, Schedule II - Item 2 for $360.00 and Item 5 for $315.00. On December 17, 1982 the Homeowners and Respondent filed the affidavit required by ordinance with the City of Coral Gables for the purpose of having a building permit issued covering the work under the contract. 9. On January 19, 1983 Respondent using his building contractors license applied for building permit to cover the work anticipated under the contract and on the same day was issued building permit, No. 28214. Under the contract the Homeowners were to pay for the building permit and the bond required by the city. On January 26, 1983 the Homeowners paid Respondent and Alonzo jointly $3,000.00 which along with a payment on January 27, 1983 of $500.00 and January 31, 1983 of $544.60 represented a draw on Schedule I - Item 2 for $405.00, Item 5 for $1,260.00, Item 6 for $1,547.10 and Item 13 for $832.50. All payments from December 6, 1982 through January 31, 1983 under the contract by the Homeowners totaled $9,366.50 and were paid jointly to Respondent and Alonzo. On February 4, 1983 Respondent and Alonzo entered into an agreement, prepared by Myron Gold in the law office of Gold and Fox, whereby the Homeowners were to pay the balance of the funds remaining under the contract to Alonzo individually. After this date all payments were made to Alonzo. It was the Homeowners understanding after the February 3, 1983 agreement that Respondent would still be responsible for the supervision of the construction although they never saw Respondent again until October 1983. Edward Borysiewicz testified that he dealt with Respondent during March 1983 when he made the floor slab inspection on March 3, 1983 and the columns inspection on March 14, 1983. The record is clear that shortly after the agreement on February 3, 1983 Respondent no longer came to the construction site and supervised the work of Alonzo. On February 8, 1983 the Homeowners paid Alonzo $3,060.00 which represented a draw on Schedule I - Item 1 for $810.00, Item 5 for $1,417.50 and Item 13 for $832.50. On February 28, 1983 the Homeowners paid Alonzo $3,155.40 which represented a draw on Schedule I - Item 4 for $1,705.50 and $729.90 for extras apparently not covered by the contract but whether the balance of check No. 1161 (Pet. Ex. 13) of $720.00 was for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 18, 1983 the Homeowners paid Alonzo $1,000 which represented a draw on Schedule I - Item 9 for $819.00. Again whether the balance of check No. 1206 (Petitioner's Exhibit No. 13) of $181.00 is for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 21, 1983, the Homeowners paid Alonzo $6,400.00 which represented a draw on Schedule I - Items 10, 11, 12, 14 and 15. On March 21, 1983 the Homeowners paid Alonzo $2,166.90 but Petitioner's Exhibit No. 15 does not list check No. 1210 as being a payment under the contract or for extras. On March 31, 1983 the Homeowners paid Alonzo $4,230.00 which represents a draw under Schedule I - Item 7 for $2,520.00 and a payment for extras not covered under the contract in the amount of $1,710.00. On April 21, 1983 the Homeowners paid Alonzo $5,207.40 which represented a draw Schedule I - Items 1, 5, 6, 9 and 14. On June 24, 1983 the Homeowners paid Alonzo $5,788.00 which represented a draw on Schedule I - Item 12 for $667.00, Item 14 for $3,024.00 and payment for extras not under contract for $2,097.00. After March 14, 1983 Respondent was not seen on the job site and there was no longer any apparent supervision of Alonzo by Respondent. After Respondent left the job site there was no licensed building contractor involved in the construction. After Respondent left the construction site the Homeowners soon realized that Alonzo did not know how to proceed with the work and experienced problems with the pace and manner in which the work was being accomplished. On July, 1983, Alonzo stopped working altogether. Although the Homeowners were aware of the problems that Alonzo was having with the construction and that Respondent was not on the job, the record does not reflect that they ever attempted to contact Respondent after the meeting on February 3, 1983. On August 1, 1983 the Homeowners notified Respondent and Alonzo that the contract had been terminated. The Homeowners paid Respondent and Alonzo $42,174.20 total under the contract (pages 1-5, Petitioner's Exhibit No. 15) and paid Alonzo $10,766.37 for extras (Pages 6- 10, Petitioner's Exhibit No. 15). On August 31, 1983 the Homeowners paid Edward Bryant, plastering contractor the sum of $3,100.00 for plastering performed by Edward Bryant. This was for work under the contract that had not been completed or work necessary to correct problems that were already completed. Roberta Fox testified that there were no extras on plaster, however, page 7, line 11 and page 9, line 21 of Petitioner's Exhibit 15 indicates that there was extra plastering. On August 29, 1983 and September 29, 1983 the Homeowners paid Southwest Plumbing Services, Inc. the total amount of $4,875.00 for work contemplated under the contract that had not been completed or needed correction. Homeowners had paid Alonzo $3,591.00 for plumbing under the contract. Both Alonzo and Southwest Plumbing, Inc. were paid for extra plumbing not covered by the contract in the amount of $567.00 and $391.50, respectively by the Homeowners. From September 13, 1983 through June 13, 1984 the Homeowners paid Charles Brueg, Jim Brueg, Charles Buffington and Dan, Inc. the total amount of $4,192.91 for electrical work contemplated under the contract that was not completed or required correction after Alonzo left the construction site. Page 6 lines 6 and 11 of Petitioner's Exhibit No. 15 indicate that there were extras not covered by the contract. The total amount for electricity contemplated by the contract was $3,649.00. Alonzo was paid $2,627.10 under the contract and $1,710.00 for extras. The Homeowners were required to obtain the services of an air conditioning contractor to complete the work contemplated under the contract after Alonzo left the job site and as a result were required to pay Cameron, Inc., the air conditioning contract the amount of $5,181.60 between August 16, 1983 and January 24, 1984. The total amount contemplated under the contract was $3,600.00 of which $1,134.00 had been paid to Alonzo. Debris was dumped in the swimming pool requiring the Homeowners to pay $7,000 to refurbish the swimming pool. This amount included the repair contemplated under the contract and the extra work caused by Alonzo. The contract contemplated $2,300.00 for repairs of which none had been paid to Respondent or Alonzo. The Homeowners paid $1,150.00 to a painting contractor to finish the painting contemplated under the contract. Alonzo had been paid $1,125.00 for painting. (Petitioner's Exhibit No. 15) The contract provided $2,500.00 for all painting required under the contract. Respondent failed to notify the building department that he was no longer responsible for the construction. After the Homeowners terminated the contract due to Respondent's and Alonzo's nonperformance, the Homeowners had to expend a substantial amount of extra money to complete the construction. The evidence is insufficient to determine an exact or approximate amount. Roberta Fox's testimony was conflicting with regard to her understanding as to whether or not the Respondent would continue to supervise the construction after the meeting in the Homeowners' law office on February 3, 1983 when Respondent and Alonzo entered into this agreement. Myron Gold testified that it was his understanding that Respondent would continue to supervise Alonzo after the agreement. However, the Homeowners action in this regard subsequent to February 3, 1983, in making no effort to bring the matter to a "head" and requiring Respondent to supervise the work or terminate the contract and in continuing to deal with Alonzo although Homeowners were aware shortly after February 3, 1983 that Alonzo could not perform without Respondent's supervision and that they knew Respondent was not on the job, tends to show that they were aware or should have been aware that Respondent was no longer involved in the day to day supervision of the construction. Alonzo installed a fireplace pursuant to the contract that the building department determined to be a fire hazard and recommended against its use. The Homeowners applied for and were granted a "owner/builder" permit on September 1, 1983 and requested cancellation of the building permit issued to Respondent which was cancelled on September 6, 1983. They have not received a certificate of occupancy because the building department has not performed the following inspection: electrical final; plumbing final; air conditioning final; roofing final and public works final. The building department would have issued a "stop-work order" had it been aware that Respondent was not supervising the construction and would have required the Homeowners to obtain another licensed building contractor or proceed as a owner/builder. The plans prepared by Frese-Camner Associates that were made a part of the contract by reference were not introduced into evidence with the contract and thus the record is insufficient to determine what was required to meet the specifications of the plans and thereby determine if the specifications had been met. There was a permit issued for the septic tank and drain field which work was started in December, 1982. The construction of the house itself was started in January 1983. The first inspection (foundation) on the house was made by the building department of January 21, 1983.
Recommendation Based on the findings of fact and conclusions of law recited herein, it is Recommended that the Board enter a final order finding Respondent guilty of violating Section 489.129(1)(h)(k)(m), Florida Statutes (1981) and for such violations it is Recommended that the Board assess the Respondent with an administrative fine of $500.00 and suspend the Respondent's contracting license for a period of three (3) years, provided, however, that if Respondent submits to the Board competent and substantial evidence of restitution to Myron Gold and Roberta Fox within one (1) year from the date of the final order herein, then the suspension shall be stayed and Respondent placed on probation for the balance of the suspension. Respectfully submitted and entered this 6th day of February, 1986, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of February, 1986. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 84-2529 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties to this case. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY THE PETITIONER: Adopted in Finding of Fact 1. Adopted in Finding of Fact 2. Adopted in Finding of Fact 3 but clarified. Adopted in Findings of Fact 4 and 5. Adopted in Finding of Fact 4. Adopted in Finding of Fact 6. Adopted in Finding of Fact 5. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12 except clarified as to the last date on construction site. Adopted in Finding of Fact 13. Adopted in Finding of Fact 14 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 16. Adopted in Finding of Fact 17 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 19. Adopted in Finding of Fact 20 but clarified. Adopted in Finding of Fact 21. Adopted in Finding of Fact 11. Adopted in Finding of Fact 21. Adopted in Finding of Fact 22. Adopted in Findings of Fact 22 and 23. Adopted in Finding of Fact24 but clarified to show correct amount paid under contract as indicated by Petitioner's Exhibit 15. Adopted in Finding of Fact 25 but clarified to show that extra plastering not under contract was required. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 29 but clarified. Adopted in Finding of Fact 30 but clarified. Rejected as immaterial. Rejected as not supported by competent substantial evidence. Rejected as not supported by substantial competent evidence. Adopted in Finding of Fact 31. Rejected as immaterial. Adopted in Finding of Fact 32 but clarified to show that the record does not support a figure that approximate $32,000.00. Rejected as not supported by substantial competent evidence even though the Homeowners' testimony supported this fact because the Homeowners' actions with regard to Respondent after February 3, 1983, was to the contrary. Adopted in Finding of Fact 33. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 35. Adopted in Finding of Fact 36. Adopted in Finding of Fact 36. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY RESPONDENT: No Findings of Fact was submitted by the Respondent. COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 W. Douglas Beason Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. George J. Soler, Pro Se 3315 S.W. 96th Avenue Miami, Florida 33165
Recommendation Based on the foregoing findings of facts and conclusions of law, it is RECOMMENDED that Respondent be found guilty of violating Subsection 489.129(1)(k), Florida Statutes, and that he be given a public reprimand and fined $1,000. DONE and ORDERED this 30th day of November, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of November, 1982. COPIES FURNISHED: Xavier J. Fernandez, Esquire P. O. Box 729 Fort Myers, Florida 33902 Michael H. Merrill, Esquire Suite 10 - 2502 Second Street Fort Myers, Florida 33901 Samuel R. Shorstein, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue The issues are whether Respondent committed the several violations of Sections 489.129(1)(h)2.,(h)3.,(j),(k), and (n), Florida Statutes (1997), for the reasons stated in the respective Administrative Complaints and, if so, what, if any, penalties should be imposed. (All chapter and section references are to Florida Statutes (1997) unless otherwise stated.)
Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a certified general contractor pursuant to license number CG C059414. At all relevant times, Respondent was the qualifying agent for Fred T. Garrett Construction, Inc. ("FTG"). As the qualifying agent, Respondent was responsible for all of FTG's contracting activities in accordance with Section 489.1195, Florida Statutes. Respondent failed to obtain a certificate of authority for Fred T. Garrett Construction, Inc., as required by Section 489.119(2), Florida Statutes. The St. Cyr Case On or about August 21, 1998, Respondent entered into a contract with Louis L. St. Cyr to construct an addition to the residence located at 201 South Bel Air Drive, Plantation, Florida. The contract price was $50,000. Although Mr. St. Cyr paid $2,500 to Respondent, Respondent failed to commence work and canceled the project, thereby abandoning it without just cause and without proper notification to Mr. St. Cyr. The contract did not permit Respondent to keep the $2,500 paid by Mr. St. Cyr, and Respondent failed to refund the payment within 30 days after abandonment. Out of the $2,500 he received from Mr. St. Cyr, however, Respondent paid $1,600.00 to the architect before abandoning the project. Thus, the net amount that Respondent owes to Mr. St. Cyr is $900. Petitioner incurred a total of $1,092.28 in investigative costs relating to the St. Cyr case. The Forney Case On May 22, 1998, Respondent, who was doing business as FTG, entered into a contract with Mr. Warren Forney for the construction of a two-bedroom, one-bath addition to the residence located at 1698 Northeast 33rd Street, Oakland Park, Florida. The contract price was $32,500. The contract with Mr. Forney did not contain a written statement explaining the customer’s rights under the Construction Industries Recovery Fund, as required by Section 489.1425(1), Florida Statutes. On July 7, 1998, Respondent obtained permit number 98-050297 from the Oakland Park Building Department. Construction commenced on or about July 7, 1998, and continued sporadically until October 29, 1998, when Mr. Forney dismissed Respondent for failure to timely complete the project. The Oakland Park Building Department issued notices of violation against the project on August 3, September 11, and October 14, 1998, for various building code violations. Mr. Forney was forced to obtain a homeowner’s permit and subsequently hired a subcontractor to complete the work. Mr. Forney paid Respondent approximately $29,250 before relieving Respondent of his duties. To complete the project, Mr. Forney paid a total of $48,746.52, which was $15,396.52 over and above the original contract price. Petitioner incurred a total of $2,190.78 in investigative costs relating to the Forney case. The Kong Case In or around January 1998, a contractor named Lakeview Concepts hired Respondent to perform demolition work for the Kong dry cleaning store project on the property located at 5171 South University Drive, Davie, Florida. On or about June 17, 1998, permit 98-00002349 was issued to Respondent to perform alterations on commercial property located at 5171 South University Drive, Davie, Florida. Respondent, however, did not yet have a contract with the owner for this work. The next month, on or about July 30, 1998, Respondent, who was doing business as FTG, entered into a contract with Shek Kong to complete the dry cleaning store project at 5171 South University Drive, Davie, Florida, for the contract price of $22,300. Shek Kong made payments to Respondent totaling $16,000. Respondent’s work was of poor quality, however, and on or about November 6, 1998, he ceased work, though the project had not been completed. On or about November 14, 1998, Douglas Frankow, license number CB C052960, gave Mr. Kong an estimate of $20,562 to complete the project. Thereafter, on or about June 30, 1999, Mr. Kong contracted with George Settergren, another licensed contractor, to complete the project for a contract price of $27,956. On December 9, 1999, in Case No. 98-020065 08, the Circuit Court, Seventeenth Judicial Circuit, Broward County, Florida, rendered a Final Judgment against Respondent and in favor of Mr. Kong. This judgment awarded Mr. Kong the total amount of $28,693.30, plus 10 percent interest per annum. Petitioner incurred a total of $2,502.78 in investigative costs relating to the Kong case.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Florida Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating Sections 489.129(1)(h)2., (h)3., (j), (k), and (n), Florida Statutes, imposing administrative fines in the aggregate amount of $3,700, assessing investigative costs in the aggregate amount of $5,785.84, placing Respondent's license on probation for a period of four years from the date the Final Order is entered by the Board, and awarding payment of restitution to each customer as follows: (1) to Warren Forney, the amount of $15,396.52; (2) to Shek Kong, satisfaction of the unpaid civil judgment in the amount $28,693.30, plus 10 percent interest accrued thereon; and (3) to Louis L. St. Cyr, the amount of $900. DONE AND ENTERED this 15th day of February, 2002, in Tallahassee, Leon County, Florida. _________________________________ JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 2002.
Findings Of Fact The Respondent, Marlene E. Lutman, is a vice president of American Custom Builders, Inc. and was a vice president in 1977. Respondent holds licenses Number CR C012570 end Number CR CA12570 issued by the Petitioner Board. On September 11, 1978, Respondent submitted a certification change of status application to the Florida Construction Industry Licensing Board. This application, completed by Respondent under oath on September 7, 1978, was filed for the purpose of changing the contractor's licenses held by Respondent to add the name of American Custom Builders, Inc. to said licenses. On July 6, 1979, an Administrative Complaint was filed against Respondent, doing business as American Custom Builders, Inc., seeking to permanently revoke her licenses and her right to practice under said licenses and to impose an administrative fine in the amount of $500.00. Respondent Lutman requested an administrative hearing, which was scheduled for September 6, 1979, continued on Motion of Respondent, and held November 29, 1979. On the application completed by Respondent, Question 12(b) asked: Are there now any unpaid past-due bills or claims for labor, materials, or services, as a result of the construction operations of any person named in (i) below or any organization in which such person was a member of the personnel? Question 12(c) of the application asked: Are there now any liens, suits, or judgments of record or pending as a result of the construction operations of any person named in "(i) below" or any organization in which any such person was a member of the personnel? Respondent, as a vice president of American Custom Builders, Inc., was designated in "(i) below." She answered "no" on the application to both of the above stated questions. Respondent completed the application while she was in Florida. Prior to completing the application, Respondent spoke by telephone with John D. Cannell, an attorney in Ohio, in reference to Questions 12(b) and 12(c), supra. Cannell told Respondent that there were no unpaid bills outstanding. He said that there had been liens filed involving American Custom Builders, Inc., but that these liens had been cancelled. Cannell based his statements to Respondent upon oral assurances from personnel at the bank involved in financing the construction project associated with the liens that all liens had been paid. It was later learned that on September 7, 1978, the date Cannell told Respondent the liens had been cancelled, the liens had not been cancelled and were of record in the Recorder's Office of Geauga County, Ohio. Liens had been filed on January 6, 1978, January 23, 1978, and January 3l, 1978, by various subcontractors involved in the construction of a house owned by Winford and Sally Ferrentina. The liens were based on claims against American Custom Builders, Inc. as general contractor and the Ferrentinas as owners for unpaid labor and materials and were not satisfied of record until September 20, 1978, on which date the January 6, 1978 lien was satisfied, and March 22, 1979, on which date the other two (2) liens were satisfied. The Hearing Officer finds that Respondent Lutman did not intend to make a material false statement but negligently relied on oral representations that there were no past-due bills and no liens of record pending as a result of her construction operations. Both parties submitted proposed findings of fact, memoranda of law and proposed recommended orders, and the Petitioner Board submitted a reply memorandum. These instruments were considered in the writing of this order. To the extent the proposed findings of fact have not been adopted in, or are inconsistent with, factual findings in this order they have been specifically rejected as being irrelevant or not having been supported by the evidence.
Recommendation Based upon the foregoing Findings and Conclusions of Law, the Hearing Officer recommends that the Respondent, Marlene Lutman, be reprimanded. DONE and ORDERED this 1st day of February, 1980, in Tallahassee, Leon County, Florida. COPIES FURNISHED: Jeffery B. Morris, Esquire 2400 Independent Square One Independent Drive Jacksonville, Florida 32202 Jeffrey R. Garvin, Esquire 2532 East First Street Post Office Box 2040 Fort Myers, Florida 33902 DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DOAH CASE NO. 79-1546 Marlene Lutman, CR C012570, CR CA 12570 Respondent, /
The Issue Did Respondent commit the violations alleged in the Administrative Complaint dated April 11, 2000, and if so, what discipline is appropriate?
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: The Department is the agency of the State of Florida charged with the responsibility of regulating the practice of contracting pursuant to Section 20.165, Florida Statutes, and Chapters 455 and 489, Florida Statutes. Respondent is, and has been at all times material hereto, a certified residential contractor in the State of Florida, having been issued license number CR CO13253 by the Florida Construction Industry Licensing Board. At all times material hereto, Respondent was licensed with the Construction Industry Licensing Board as an individual. On or about November 20, 1993, Respondent entered into a written contractual agreement (contract) with Kevin Watkins (Watkins) to construct a single family residence at 126 Meadow Lark Boulevard, Lot 65, Indian Lake Estates, Florida. The contract price was $333,944.00. Between December 7, 1993, and February 1, 1996, Watkins and Respondent executed 102 addenda to the contract which increased the contract price by approximately $241,874.43, for a total amount of approximately $575.818.43. On or about December 9, 1993, Respondent obtained permit number 93-120l850 from the Polk County Building Department and commenced work on the project. The contract provided that the "project shall be substantially completed on or about 195 days from the date all building permits are issued." However, due to the 100-plus addenda to the contract, it was estimated that an additional 190 days would be needed to complete the project. Additionally, construction ceased on the home for approximately 60 days so that Watkins could explore the possibility of a construction loan. However, due to the extent of completion, the lending institutions decided not to make any construction loans. On or about May 27, 1996, Watkins moved to Florida with the expectations that his home would be completed within a short period of time. (Watkins' recollection was that the home was to be completed in a couple of weeks. Respondent's recollection was that the home was to be completed in a couple of months.) In any event, Respondent did not complete the Watkins home within a couple of weeks or a couple of months. After Watkins moved to Florida, Respondent paid for Watkins to live in a Best Western motel for a few weeks. Subsequently, Respondent moved Watkins into a rental home for which Respondent paid the rent through September 1996. Beginning October 1996 through July 1999, Watkins paid $600.00 per month for a total of $20,400.00 as rent on the rental home. In early 1998, Respondent and Watkins went through the home, identified those items which had not been completed and Respondent made a handwritten list of those items. Respondent failed to complete the items identified on the list. In fact, shortly thereafter, Respondent ceased working on the project and was unresponsive to attempts to contact him. At the time Respondent ceased working on Watkins' home, the home was approximately 75 percent complete. While this estimation of completion may not be totally accurate, it is the best that could be derived based on the evidence presented, including Respondent's testimony to which I gave some credence. Watkins paid Respondent $561,617.91, which represents approximately 97.534 percent of the total contract price plus addenda to the contract. Seventy-five percent of the contract price plus addenda to the contract equals $431,863.82 for an overpayment of $129,754.09. To date, Respondent has not returned any of the money he received from Watkins above the amount completed under the contract. From early 1998, until August 1998, when Watkins had Respondent removed as general contractor on the building permit, Respondent failed to perform any work on the home for a period in excess of 90 days. Respondent contracted with Jack Eggleston to install cabinets in Watkins home. Eggleston performed under the contract but Respondent failed to pay Eggleston in full, requiring Watkins to pay Eggleston $1,200.00. After Watkins' home was partially complete, Respondent advised Watkins that he had the home insured when in fact he did not have the home covered with insurance. While Respondent was building Watkins' home, Respondent and Watkins entered into a joint venture called Contractors of Central Florida to build modular homes sometime after January 1, 1995. Respondent contends that some of the checks Watkins claims as payment under the contract for his home, were in fact reimbursement to Respondent for funds he had advanced for the joint venture. There is insufficient evidence to establish facts to show that any of the checks Watkins claims as payment under the contract for his home were in fact reimbursement for funds advanced by Respondent for the joint venture. Up until the time of the final hearing, the Department had incurred costs for the investigation and prosecution of this matter, excluding costs associated with an attorney's time, in the amount of $1,451.28.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, and after careful review of the guidelines set forth in Rule 61G4-17.001(8) and (11), Florida Administrative Code, and the circumstances for purpose of mitigation or aggravation of penalty set forth in Rule 61G4-17.002, Florida Administrative Code, it is recommended that the Department: Enter a final order finding Respondent guilty of violating Section 489.129(1)(h)2., Florida Statutes, and imposing a penalty therefor an administrative fine in the amount of $1,000.00; Enter a final order finding Respondent guilty of violating Section 489.129(1)(k), Florida Statutes, and imposing a penalty therefor an administrative fine in the amount of $1000.00; Assessing costs of investigation and prosecution, excluding costs associated with an attorney's time, in the amount of $1,451.28, plus any such further costs which have or may accrue through the taking of final agency action and; Requiring Respondent to pay restitution to Kevin Watkins in the amount of $129,754.09 which represents the amounts accepted by Respondent for work not performed. DONE AND ENTERED this 23rd of October, 2000, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6947 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 2000. COPIES FURNISHED: Robert A. Crabill, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32388-2202 Ronald J. Powell Post Office Box 7043 Indian Lake Estates, Florida 33855 Rodney Hurst, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer would recommend that no action be taken against the licenses of K. C. Moore as a registered builder contractor. In addition, the testimony at the hearing revealed that subsequent to the institution of this complaint that Dr. 0. Rao, M.D., did make application to the Florida Construction Industry Licensing Board for licensure as a contractor, that his application was approved, and that upon successful completion of the Board's examination he was licensed. If K. C. Moore is in fact guilty of aiding or abetting or knowingly combining or conspiring with a person to violate Part II, Chapter 468, the person with whom he combined or conspired or who he aided or abetted was Dr. John 0. Rao. Although the Board may be limited under the statutory provisions in denying Dr. Rao the license, assuming the Board rejects the Hearing Officer's Conclusions of Law and finds the facts constitute a violation of the statutory provisions, there is an absence of essential fairness to proceed against the licenses of K. C. Moore while licensing the individual with whom he contracted. The disparity in treatment of K. C. Moore and Dr. John 0. Rao is a factor which must be considered by the Board. DONE and ORDERED this 20th day of July, 1977, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 R. Stephen Miles, Jr., Esquire Mile and Cumbie Post Office Box 517 Kissimmee, Florida 32741 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner,
The Issue At issue herein is whether or not the Respondent/Licensee, Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Lifetime), engaged in conduct which will be set forth hereinafter in detail, which warrants the Florida Construction Industry Licensing Board (Board) to take disciplinary action respecting his license and to impose an administrative fine based on said alleged conduct.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Respondent), is a certified general contractor who holds license No. CGCA 04170, which is active. On September 24, 1975, Mr. Perez used his license to qualify Lifetime Chemicals of America, Inc., as the entity through which he would conduct his business activities (Petitioner's Exhibit 1). On August 15, 1978, Lifetime Chemicals of America, Inc. , entered into an agreement with James Laughery of Fort Myers, Florida, for a franchise agreement to use Lifetime's license in the immediate area of Fort Myers, Florida (Petitioner's Exhibit 5). That agreement provides, among other things, that Respondent Lifetime authorized James Laughery to use its license in the Fort Myers area for a fee of $50.00 per job or $1,500.00. The agreement does not provide, nor was any evidence offered to establish that Respondent Perez played any supervisory or managing role in agent Laughery's contracting activities in the Fort Myers area. During October of 1978, Mr. Andrew Szarfran entered into an agreement with Respondent's agent, Laughery, to perform certain roofing repairs to his residence for the sum of $1,000.00. Mr. Szarfran paid Laughery $500.00 and Laughery abandoned the project prior to completion (Testimony of Szarfran and Petitioner's Composite Exhibit 4). Mr. Szarfran engaged the services of another contractor to complete the project. On May 17, 1979, the Lee County Construction Board reviewed a complaint filed against Respondent by the Szarfrans. Based on that review, the Lee County Construction Board revoked Respondent's licensing privileges in the county at its June, 1979, meeting (Petitioner's Exhibits 3 and 4 and testimony of witnesses Richard M. McDole and Maxine Allred, Administrative Director of Court Enforcement and Permit Clerk, respectively, for Lee County). On or about October 17, 1978, Respondent's agent, Laughery, also entered into an agreement with Mr. and Mrs. Arthur Swanson for the erection of aluminum siding to the exterior walls of their residence for a full price of $5,000.00. The Swansons gave Respondent's agent, Laughery, a downpayment of $2,500.00 and agent Laughery abandoned the project prior to the commencement of any work (Petitioner's Exhibits 7 and 8 and testimony of Mrs. Swanson). Richard Newmes, the chief inspector for building and zoning, Cafe Coral, Florida, testified that the Construction Industry Licensing Board for Cape Coral, Florida, revoked Respondent's contractor license on January 17, 1979, based on his violation of Cape Coral Code Section 5-1/2 - 21(J), to wit: "Failure to make good faulty workmanship or materials performed or installed to evade performance of the contract or specifications as agreed upon." (Petitioner's Exhibit 9.) On or about January 4, 1979, Lifetime Chemicals of America, Inc., became aware of its agent, James Laughery's mismanagement of funds and his failure to honor contractual obligations he had entered in the Fort Myers area. Respondent and its agent Laughery therefore entered into an agreement which rendered the franchise agreement between the parties null and void. Agent Laughery, in said agreement, promised to pay, from his commissions due, monies owed to Lifetime Chemicals, Inc., which apparently was brought about due to the restitution that Lifetime Chemicals had made to customers whom agent Laughery had defaulted. As mitigating evidence, it was noted that the Respondent, Tomas Perez, was not party to or familiar with the activities and/or difficulties that the designated agent for Lifetime Chemicals of America, Inc., James Laughery, was encountering in the Fort Myers vicinity before early January, 1979. As soon as Respondent became aware of Laughery's problems, steps were immediately taken to halt such acts insofar as they related to Respondent (Testimony of Tomas Perez and Michael Arfaras).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law and the mitigating evidence which revealed that although the Petitioner is authorized and in fact holds the qualifier license of a registered entity responsible for the acts of its agents, in view of the undisputed evidence which reflects that neither Respondent Perez or Respondent Lifetime Chemicals of America, Inc., in any manner benefited from the acts of its agents and in fact attempted to thwart the illegal acts of its agent as soon as such became known, it is hereby RECOMMENDED: l. That the Respondent, Tomas Perez's Certified General Contractor's license, CGCA 04170, be placed on probation for a period of one (1) year. 2. That the Respondents, Tomas Perez and Lifetime Chemicals of America, Inc. , be issued a written letter of reprimand. RECOMMENDED this 24th day of April, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of April, 1980. COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 Tomas Perez 2395 West 12th Avenue Hialeah, Florida 33010 Michael Harold Arfaras 820 S.W. 20th Avenue Miami, Florida 33135 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 79-2173 THOMAS PEREZ, CGCA 04170 Respondent. /
Findings Of Fact The parties stipulated to the fact that James Baskin holds registered contractor's license number BC 0011300. Raskin's registered general contractor's license was issued by the Florida Construction Industry Licensing Board. Prior to the commencement of the hearing, the Hearing Officer held that the record of the proceedings for the Cape Coral Board could be filed as a late filed exhibit in this cause in order that the Florida Construction Industry Licensing Board could review the Cape Coral Board's action pursuant to its authority under Section 468.112(2)(f), Florida Statutes. Ambassador Homes contracted with Sam and Marie Franzella for the construction of a single family residence to be constructed on the property located on Lots 41-42, Block 1224, Cape Coral Unit 19, Section 32-33, Township 44 South, Range 24 East. Stucky Well Drilling was initially contacted by an unknown agent of Ambassador Homes on January 1, 1975, and directed to drill a well, and install a deep well jet pump and tank at the location stated above. On January 20, 1975, Marion, a secretary for Ambassador Homes, called Stucky Well Drilling and directed that Stucky Well Drilling install the well and equipment as soon as possible. On January 21, 1975, a 210 foot well was drilled on the property described above and on January 23, 1975, a Mr. Green from Ambassador Homes called and requested that the tank and equipment be installed immediately. Mr. Hall, an employee of Stucky Well Drilling, installed all the equipment as ordered on January 23, 1975. On January 24, 1975, a bill in the amount of Six Fifty Dollars ($650.00) was sent to Ambassador Homes for the work performed on the property described above. Ambassador Homes was a corporation engaging in residential contracting and operating under the license of James Raskin. Ambassador Homes did not pay Stucky Well Drilling the bill for the drilling of the well and installation of the equipment on the property described in paragraph 3 above. Subsequently Stucky Well Drilling brought suit against Ambassador Homes, Inc., in the County Court of Lee County and obtained final judgment in the amount of Six Hundred Fifty Dollars ($650.00) plus costs. This judgment was entered on December 2, 1975.
Recommendation Based on the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board suspend the license of James Raskin as a registered general contractor until he presents satisfactory proof to the Board of his financial qualifications to engage in the contracting business. DONE and ORDERED this 27th day of May, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blacks tone Building Jacksonville, Florida 32202 James Raskin 1810 S. E. 44th Street Cape Coral, Florida 33904 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211
The Issue The issue for determination is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what action should be taken.
Findings Of Fact At all times material hereto, Mr. Borek was licensed by the Department as a certified general contractor, having been issued license number CG C 58817. He was licensed on November 18, 1996. At all times material hereto, Mr. Borek was the qualifying agent of Atlantic Coast General Contractors, Inc. (ACGC), a Florida corporation, and has been its president. ACGC was issued a certificate of authority as a contractor qualified business on June 2, 1977, having been issued license number QB 07357. ACGC's license expired on September 1, 2001 and became null and void on September 1, 2003. The State of Florida, Department of State, administratively dissolved ACGC, as a corporation, on October 1, 2004, for its failure to file its annual report, as required by law; and, as a result, ACGC's authority to transact business, as a corporation, in the State of Florida was revoked on the same date. At all times material hereto, Tracey Meredith (Ms. T. Meredith) resided in and owned a home located at 7690 Northwest 16th Court, Pembroke Pines, Florida. Ms. T. Meredith wanted her mother, Jane Meredith1 (Ms. J. Meredith), to live with her so Ms. T. Meredith decided to have an addition built to her home, consisting of a bedroom, bathroom, and closet. Ms. T. Meredith obtained a proposal from ACGC and five other contractors for the addition. Each contractor was aware of the purpose of the addition. Ms. T. Meredith decided to contract with ACGC, which was not the lowest or the highest bidder, but was somewhat in the middle. On June 28, 2002, a Proposal/Contract (Contract) was executed with ACGC for the addition at a cost of $32,925.00. Even though the Contract showed Ms. T. Meredith as the contracting party, it was signed by Ms. J. Meredith because she (Ms. J. Meredith) was actually paying for the addition and signing the checks. Both Mses. T. Meredith and J. Meredith were in agreement with the Contract. The Contract provided, among other things, that the addition was 15 x 21; and that the payments would be as follows: 20% at acceptance of the Contract, 20% at permit issuance, 10% at slab, 20% at wall and roof framing, 10% at roof completion, 10% at finished walls and flooring, and 10% at final completion. No dispute exists that the cost of the Contract was reasonable. No dispute exists that the Contract failed to contain a provision explaining the consumer's rights under the Florida Homeowners' Construction Recovery Fund, formerly known as the Construction Industries Recovery Fund. No dispute exists that the Contract did not provide a date for completion of the addition. Regarding a completion date for the addition, Ms. T. Meredith testified that all the other proposals provided that the addition would be completed within six to eight weeks and that, at the beginning, Mr. Borek orally communicated to her that the addition would be completed by ACGC within six to eight weeks. To the contrary, Mr. Borek testified that, at the beginning, no completion date was given to her, either orally or in writing. None of the other proposals were submitted into evidence, only the Contract with Mr. Borek, which did not provide a completion date. It would not be reasonable for Ms. T. Meredith to accept Mr. Borek's proposal without it’s being within the time period of completion of the other proposals. The undersigned finds Ms. T. Meredith's testimony more credible and makes a finding of fact that, at the time of the signing of the Contract, Mr. Borek made an oral representation that the addition would be completed by ACGC within six to eight weeks. An expert in the field of general contracting, John Yanoviak (Mr. Yanoviak), testified on behalf of the Department. The undersigned finds his testimony credible, except as specifically indicated. A reasonable amount of time to complete the addition was a maximum of three months. Mr. Borek, as the contractor, was responsible for keeping the project timely and for quality control. On June 30, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,585.00. This amount was 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. Paying this amount was in accordance with the Contract. Mr. Borek filed an application for a building permit with the City of Pembroke Pines (CPP) on or about July 3, 2002. The building permit was issued by CPP on or about October 25, 2002. Work on the addition was commenced before the issuance of the building permit. Ms. T. Meredith was aware of the date that the building permit was issued. Prior to the issuance of the building permit, Ms. T. Meredith complained to Mr. Borek regarding the addition’s not being completed. No evidence was presented to show that Ms. T. Meredith indicated to Mr. Borek that, by his failure to complete the addition within a six-to- eight-week period, he was not abiding by the Contract. No evidence was presented to show that she indicated her dissatisfaction to the degree of possibly terminating the Contract with ACGC. On November 12, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,585.00. This amount was paid after Mr. Borek obtained the building permit and was 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. Paying this amount was in accordance with the Contract. On December 11, 2002, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $6,885.00. This amount was $300.00 more than 20 percent of the contracted cost for the addition. No dispute exists that this check was written and presented to Mr. Borek. An inference is drawn and a finding is made that this check was written in advancing of the addition. According to the records of the CPP's building department2 (Records), a CPP form for a revision to the addition was submitted on January 6, 2003, providing for an electrical change to the addition. Further, the Records indicate that, on March 20, 2003, an application for an electrical permit was submitted and that, on March 24, 2003, the permit was approved. Also, a revision to the plans of the addition was submitted to the CPP by the architect to the addition, Hernando Acosta, according to the Records. The Records indicate that the revision to the plans was dated January 30, 2003 by Mr. Acosta, that the revision was submitted on February 7, 2003, and that the revision was approved on February 11, 2003 by the CPP. In addition, in February 2003, Ms. T. Meredith received written communication from the CPP regarding a problem with the addition. Ms. T. Meredith received a copy of a letter from the CPP to Mr. Borek, dated February 18, 2003. The letter indicated, among other things, that the CPP had issued a "stop work status" on the addition due to Mr. Borek’s having issued a check, payable to the CPP, in the amount of $135.80, which was dishonored. Another revision, according to the Records, was submitted on March 27, 2003, regarding the trusses. The Records indicate that the revision was approved on April 17, 2003. Ms. T. Meredith became more dissatisfied with the progress toward completion on the addition by Mr. Borek to the point that she filed a complaint with the Department on May 21, 2003. In May 2003, Ms. T. Meredith received written communication from the CPP regarding a problem with the addition. By letter dated May 22, 2003, she received notification from the CPP, as information only, that a code violation had not been corrected within the allowable ten-day period, together with a copy of CPP's letter to Mr. Borek, dated May 22, 2003, of his failure to correct the code violation. The letter to Mr. Borek indicated, among other things, that Mr. Borek had until June 11, 2003 to correct the violation, identifying the inspection date and the violation. By a letter dated May 28, 2003, Ms. T. Meredith advised Mr. Borek, among other things, that he had seven days to continue with the work on the addition in accordance with the Contract or else the Contract would be considered by her to be "null and void"; that, if he did not do so, she would be "forced" to hire another contractor, with Mr. Borek being held financially responsible for completion of the addition; and that the Contract was to be completed within six to eight weeks. On June 12, 2003, Mr. Borek contacted the investigator for the Department regarding the complaint filed by Ms. T. Meredith. Among other things, Mr. Borek informed the investigator that he (Mr. Borek) was willing to complete the addition in 30 days. By his representation, Mr. Borek indicated that he would complete the addition on or about July 12, 2003. By a letter dated June 18, 2003, Mr. Borek notified the investigator, among other things, that he was working "diligently" to complete the addition. Mr. Borek failed to complete the addition within the 30-day period, as he had represented to the Department's investigator. The Records indicate that an application for a building permit, involving the roof to the addition, was submitted on June 25, 2003. The permit was issued, according to the Records, on July 30, 2003. Further, the Records indicate that a revision, regarding the size of a window and the elimination of a door, was submitted on July 8, 2003, and approved on July 9, 2003. In July 2003, Ms. T. Meredith received another written communication from the CPP regarding a problem with the addition. By letter dated July 9, 2003, she received notification from the CPP, as information only, that a code violation had not been corrected within the allowable ten-day period, together with a copy of CPP's letter to Mr. Borek, dated July 9, 2003, of his failure to correct the code violation. The letter to Mr. Borek indicated, among other things, that Mr. Borek had until July 28, 2003, to correct the violation, identifying the inspection date and the violation. In addition, in July 2003, Ms. T. Meredith received written communication from the CPP regarding another problem with the addition. She received a copy of a letter from the CPP to Mr. Borek, dated July 18, 2003, which indicated, among other things, that the CPP had issued a "stop work status" on the addition due to Mr. Borek having issued a check, payable to the CPP, in amount of $76.23, which was dishonored. Even though Mr. Borek failed to complete the addition within the 30-day period that he had represented to the Department's investigator and even though Ms. T. Meredith had received notification of the problems at the jobsite from the CPP, on September 10, 2003, Ms. J. Meredith wrote a check, payable to ACGC, in the amount of $4,000.00. No dispute exists that this check was written and presented to Mr. Borek. An inference is drawn and a finding is made that this check was written in furtherance of the addition. ACGC had been paid a total of $24,055.00 of the Contract cost of $32,925.00, which was approximately 73 percent of the Contract cost. The balance of the Contract cost was $8,870.00. Mr. Borek testified that, at the time of the writing of the check for $4,000.00, he and Ms. T. Meredith agreed that he would have until on or about November 15, 2003 to complete the project. Ms. T. Meredith testified that no such agreement was made. At the time of the check for $4,000, ACGC was almost 60 days beyond the completion date represented to the Department's investigator. No testimony was presented as to why the $4,000.00 was paid to ACGC in light of such a considerable delay in completing the job by ACGC and in light of the complaint being filed with the Department. Due to the lack of an explanation for the payment of the $4,000.00 to ACGC in furtherance of the project, Mr. Borek's testimony presents a reasonable explanation. Therefore, Mr. Borek's testimony is found to be credible. Hence, a finding is made that, on or about September 10, 2003, Mr. Borek and Ms. T. Meredith orally agreed that ACGC would have until on or about November 15, 2003, to complete the addition. Ms. T. Meredith continued to be dissatisfied with the progress on the addition by ACGC. Sometime after September 10, 2003, an incident occurred which caused her to reach the conclusion that she could not allow ACGC to continue working on the project. One day when she left for work, one of ACGC's workers was painting the exterior walls. When she returned from work later that same day, the same worker for ACGC was painting the exterior walls. Ms. T. Meredith immediately directed the worker to leave and to take all of his equipment with him; the worker did so. Ms. T. Meredith contacted Mr. Borek and informed him that she would not allow him to continue with the project. Mr. Borek repeatedly requested Ms. T. Meredith to allow him to continue with the project, but she refused. By letter dated October 9, 2003, Ms. T. Meredith terminated the Contract with ACGC. She mailed the letter on the same date and faxed it on October 14, 2003. Her mother was in agreement with terminating the Contract. Ms. T. Meredith indicated, among other things, in her letter to ACGC that its failure to complete the addition as of the date of the letter, when the oral agreement was completion within six to eight weeks, left her no choice but to terminate the Contract. Ms. T. Meredith included in the letter, among other things, what remained to be completed on the project and a cost of $539.55 for damaged items at her home caused by ACGC, with an itemized list. At the time of the termination, the following work remained to be completed: purchase and installation of plumbing fixtures; sewer hookup; molding; tile work in the bathroom; installation of storm panels and flooring; some painting; installation of an air conditioner; some electrical connections; and installation of an electrical panel, electric wall plates, and an electric light fixture. Ms. T. Meredith obtained a homeowner's permit and hired someone, Adam Friedman, to assist her in completing the addition. On December 15, 2003, the CPP issued a certificate of occupancy to her. As to expenditures by Mses. T. and J. Meredith in order to complete the addition, the undersigned finds the testimony of Mr. Yanoviak credible. Mses. T. and J. Meredith expended $19,170.52 to complete the addition. The expenditures for completion were reasonable and necessary. Not included in the expenditures for completion are the following: $3,941.31 for items not included in the Contract--a fence, pavers, wood floor, upgraded bathroom fixtures or accessories, closet woodwork and various Home Depot items (totaling $238.21); $250.00 for mill work associated with chair rails; and $2,400.00 for an exterior concrete slab. Included in the expenditures for completion is the following: $1,360.00 for a split-system air conditioning unit which was not installed by ACGC. Further, included in the cost of expenditures is an adjustment in favor of Ms. T. Meredith in the amount of $1,000.00 for the elimination of a window on the west elevation of the addition, which was orally agreed to by Ms. T. Meredith and Mr. Borek after the signing of the Contract and which would have been subtracted from the cost of the Contract. After Ms. T. Meredith terminated the Contract, she filed a claim under the Construction Industries Recovery Fund. The claim was dated October 10, 2003, one day after she terminated the Contract. Ms. T. Meredith set forth in the claim that she was requesting $12,000.00, which she indicated was the amount to pay another contractor to complete the project. The undersigned places very little weight upon the amount requested because the claim is prior to completing the project and fails to reflect the actual costs involved in completing the project, which were realized only after completion. Damage to items at Ms. T. Meredith's home occurred, during the work being performed by ACGC, for which ACGC was responsible. The following items were affected: damaged a window magnet that was part of the home's security system at $80.00; destroyed, broken, or thrown away one large planter pot, one archway, and two large stepping stones--all at an estimate of $440.34; and broken tiles in the front of the house at $13.57. The damages totaled $533.91. At the time of the hearing, Mr. Borek had not made any payments to Ms. T. Meredith or Ms. J. Meredith for their expenditures to complete the addition or for the damages. At the time of the termination, in accordance with the oral agreement of completion by on or about November 15, 2003, ACGC had a little over 30 days to complete the addition. In light of the finding that an oral agreement had been reached to allow ACGC until on or about November 15, 2003, to complete the addition and in light of the only incident since that agreement, presented by the evidence, was the situation involving ACGC's painter, the undersigned finds that the painting situation was not substantial and that, therefore, the termination on October 9, 2003, prior to the new agreed- upon termination date, was unreasonable. Ms. T. Meredith testified that, sometime during the middle of the year 2003, for a period of "exactly" 60 days, ACGC failed to perform any work at the project. Mr. Borek denies her assertion. Ms. T. Meredith testified that she kept records on everything. When she testified as to an exact 60- day period in the middle of 2003 during which no work was being done at the project, Ms. T. Meredith did not point to any of her records to verify the assertion or provide certain beginning and ending dates. Taking into consideration the standard of proof and the burden of proof, the evidence failed to show clearly and convincingly that no work was done at the jobsite by ACGC for a period of 60 days in the middle of the year 2003. Nothing was done by Ms. T. Meredith, the architect, or CPP to delay the completion of the project. Mr. Borek admits that he had other jobs in progress when he was working on the addition. He further admits that when changes had to be made to the project, whether by the CPP or the architect or Ms. T. Meredith or himself, he had to re- arrange his schedule to accommodate the other jobs, which included re-deploying his workers and subcontractors, which in turn caused delays. Further, Mr. Borek admits that the turnaround time for any changes given to the architect for the plans to the addition was reasonable and that the turnaround time for the CPP to review the changes to the plans submitted by the architect was reasonable. Consequently, no unreasonable or inordinate delays were caused by the architect or the CPP when changes were made to the plans of the addition. Mr. Borek performed some work for Ms. T. Meredith at no cost that was not required by the Contract. The extra work at no cost included the following: the removal of trees; pouring of an exterior concrete slab; and plastering of drywall. The slow progress in completing the Contract was significant and material and resulted in the Contract’s not being performed in a reasonable time. The delays in completion of the addition were significant and were the fault of Mr. Borek. In addition to re-deploying workers for other jobs on which ACGC was working, ACGC failed to properly perform work, which resulted in failed inspections by the CPP, which resulted in numerous delays, and failed to timely obtain an electrical permit. As to the failure to timely obtain an electrical permit, the electrical permit was obtained almost five months subsequent to the issuance of the building permit by the CPP. The electrical permit was applied for on March 20, 2003 and approved on March 24, 2003. CPP's turnaround time in approving the permit was short and inconsequential. As to the failure to properly perform work, the Records indicate construction defects, which were under Mr. Borek's, the contractor's, control and which resulted in failed inspections. Furthermore, the Records indicate prior construction faults, identified in inspections, not being timely corrected, which was under Mr. Borek's control and which resulted in delays until the faults were corrected. Mr. Yanoviak testified that failure to perform the Contract within a reasonable time constituted misconduct. The undersigned finds his testimony credible. A finding of fact is made that the failure to perform the Contract within a reasonable time constituted misconduct. Additionally, Mr. Yanoviak testified that the failure to perform the Contract within a reasonable time constituted a material breach of the Contract. The undersigned finds his testimony credible, and a finding of fact is made that the failure to perform the Contract within a reasonable time constituted a material breach of the Contract. Further, Mr. Yanoviak testified that, such material breach, justified terminating the Contract. The undersigned finds his testimony credible only as to a general application and, therefore, a finding of fact is made that, generally, the failure to perform a construction contract within a reasonable time would justify terminating the construction contract but does not justify terminating the Contract under the circumstances presented in the instant case. Both Mr. Borek and Ms. T. Meredith orally agreed to a new date for completion of the addition, i.e., on or about November 15, 2003. To disregard the new date of completion would be manifestly unjust. Furthermore, at the time of the termination of the Contract by Ms. T. Meredith, i.e., on October 9, 2003, the termination was unreasonable and not for just cause. Hence, a finding of fact is made that termination of the Contract by Ms. T. Meredith, prior to the new completion date, was not justified. Mr. Yanoviak also testified that failure to perform the Contract within a reasonable time constituted abandonment of the project. The undersigned finds his testimony credible only as to general application and, therefore, a finding of fact is made that, generally, the failure to perform a construction contract within a reasonable time would constitute abandonment of a project. However, as found above, a new date for completion of the project was orally agreed upon and the new date had not expired at the time of the termination of the Contract by Ms. T. Meredith. Hence, a finding of fact is made that, under the circumstances of the instant case, abandonment did not exist. The Department presented evidence of costs for the investigation and prosecution of this matter, excluding costs associated with attorney time. As of July 5, 2005, the costs for the investigation and prosecution totaled $880.18. As to prior disciplinary action, on September 9, 2004, the Department filed a Final Order in Department of Business and Professional Regulation vs. Bret Jayson Borek, Case No. 2003-069533, License No. CG Co58817 before the Construction Industry Licensing Board. In that case, an administrative complaint was filed against Mr. Borek for violating Section 489.129(1)(i), Florida Statutes (2001), by failing to comply in a material respect with a provision of Chapter 489, Florida Statutes, through the failure to obtain a certificate of authority for ACGC; and for violating Section 489.129(1)(q), Florida Statutes (2001), by failing to satisfy a civil judgment, related to the practice of construction, within a reasonable time. Mr. Borek waived his rights to an informal hearing, and no material fact was disputed. Among other things, the Final Order imposed an administrative fine of $1,000.00, required restitution of $15,218.94 to a roofing and sheet metal company and required payment of $506.92 for investigative costs.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order: Finding that Bret Jayson Borek committed the violations set forth in Counts I, II, and III; Dismissing Count IV; and Imposing the following penalties: As to Count I, an administrative fine in the amount of $1,000.00 and revocation of the license of Bret Jayson Borek. As to Count II, an administrative fine in the amount of $500.00. As to Count III, an administrative fine in the amount of $5,000.00 and revocation of the license of Bret Jayson Borek. S DONE AND ENTERED this 9th day of January, 2006, in Tallahassee, Leon County, Florida. _______________________________ ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2006.