The Issue The issue for consideration in this case is whether the Department should impose administrative penalties in the form of fines, costs and points assessment because of the matters alleged in the Administrative Complaint and Order entered herein.
Findings Of Fact At All times pertinent to the issued herein, the Petitioner, SWFWMD, was the governmental agency responsible for the licensing of well contractors and the permitting of well drilling and abandonment within its jurisdictional area. Respondent, Edward Tanner, was a licensed water well contractor, holding license Number 2276 issued on July 21, 1982. On January 16, 1996, SWFWMD issued Well Construction permit 575267.01 to Respondent for the abandonment of a four-inch diameter water well on property owned by Mr. McCrimmon located at Five Tera Lane in Winter Haven. The well, a domestic water well, had failed and Respondent applied for a permit to construct a new well at the site and abandon the failed well. Stipulation Number Four of the permit issued to the Respondent provided that the well must be examined for debris or obstructions from the land surface to the original depth of construction, and further required that any debris or obstruction discovered be removed from the well prior to the commencement of abandonment. In addition, the stipulation called for the well to be plugged from bottom to top by an approved method of grouting. According to the permit, if any other method of abandonment was to be used, it must be approved in advance by specifically denoted District personnel. Though Respondent did not utilize the approved method of abandonment in this project, he did not apply for a variance from the District. Had he done so, he would have been required to show some emergency or hardship which would have prevented him from properly filling the abandoned well with cement from top to bottom and justified an alternative method of abandonment. In this case, Respondent plugged the well in issue, which was 210 feet in depth, from the land surface down to fifty five feet, utilizing six bags of portland cement. Deviation from the 210 foot plug required a variance to be granted by the District. Respondent did not seek this variance. Well abandonment is a regulated practice because, inter alia, improper abandonment may result in contamination of the aquifer. The well in question here is located in an area susceptible to contamination by ethylene dibromide, (EDB), recognized as a human carcinogen, which is known to be present in the area. In addition to failing to properly abandon the well, Respondent also failed to file a well completion report within thirty days of completion of his abandonment effort. The required report was submitted on June 10, 1996, nearly four months after it was due. Respondent relates that in January 1996, after he had worked on a well “commonly known” to be the subject of litigation, he was asked to try to fix the well in issue. When he saw the problem, he contends he repeatedly advised the authorities that the well was leaking sand and could not be cleaned out to the bottom as the District required. Therefore, to preserve the integrity of the well, he plugged it at a point below the break in the well lining. At that time, he told Mr. McCrimmon what the situation was and advised him the well needed to be abandoned, but he, Tanner, did not do that type of work. Respondent contends, supported by his son, that on January 16, 1996, while he was at Mr. McCrimmon’s property, he was told by Mr. Wheelus and Mr. Lee, both District officials, that Mr. Calandra, also a District official had said he, Tanner, had to pull a well abandonment permit or Calandra would not sign off on the new well. At that point, Respondent claims, he went to the District’s Bartow office to argue with Mr. Calandra, and asked Mr. Calandra to show him the law which supported Calandra’s position. Calandra persisted in his position and even, according to Respondent, bet with another District employees that Respondent had to do what he was told. This other employee does not recall any such bet. Therefore, under protest and only so he could get paid for the work he had done on the new well, Respondent agreed to pull the abandonment permit. At that time, he claims, he asked the District personnel in charge how many bags of concrete would be required to abandon the well and was told, “six”. When the time came to do the actual work, Respondent called for the required observer to be present from the District office, but because no one was available at the time, he was granted permission to do it without observation. He did the job as he felt it had to be done, and thirty days to the day after that, was served with the notice of violation. Respondent contends either that the witnesses for the District are lying in their denials of the coercive statements he alleges, or the situation is a conspiracy to deprive him of his civil rights. He does not believe a well contractor should be required to stay current regarding all the District rules regarding well construction and abandonment because the rules change so often. Respondent admits, however, that the rules in existence at the time in question required the filling of a well all the way down and that he did not do that nor did he seek a variance., He knew he was required to comply with the conditions of a permit. He also admits that a completion report was due within thirty days of work completion. In that regard, however, he contends that when the issue went into litigation, he felt the district would advise him of what he had to do. In this he was mistaken, but he was not misled into believing so by anything done or said by District personnel. Taken together, the evidence does not demonstrate that anyone from the District staff coerced Respondent into abandoning the well. He was issued a permit to drill the new well for Mr. McCrimmon with no conditions thereon. By the same token, the abandonment permit he obtained did require the complete clearing and total plugging of the abandoned well, and this was not done. The costs incurred by the District in the investigation and enforcement of this alleged violation totaled in excess of $500.00.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Southwest Florida Water Management District enter a final order finding Respondent, Edward Tanner, guilty of improperly abandoning the well in issue and failing to file the required report in a timely manner, and assessing enforcement costs in the amount of $500.00 in addition to an administrative fine of $250.00. DONE and ENTERED this 29th day of January, 1997, in Tallahassee, Florida. ARNOLD H. POLLOCK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6947 Filed with the Clerk of the Division of Administrative Hearings this 29th day of January, 1997. COPIES FURNISHED: Margaret M. Lytle, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Edward Tanner 1137 Saint Anne Shrine Road Lake Wales, Florida 33853 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
The Issue Whether Rule 27G-1.06(2) and Rule 27G-1.08(4), Florida Administrative Code, or either of them, is an invalid exercise of delegated legislative authority?
Findings Of Fact The parties have stipulated that Fairfield Communities, Inc. (Fairfield) has the requisite standing to challenge the rule provisions at issue and that Friends of Fort George, Inc., (Friends), Florida Wildlife Federation (FWF) and Florida Audubon Society (Audubon) have standing to participate as intervenors in support of these rule provisions. The Florida Land and Water Adjudicatory Commission (FLWAC) is the state agency that promulgated the challenged rules. The Fort George DRI case, No. 86-4127, began on August 1, 1986, when the Department of Community Affairs took an appeal of the development order entered by the City of Jacksonville on June 12, 1986 on grounds The MLUP does not accurately show or locate the DER jurisdictional line on the western side of the island from which buffer areas required by the ADO are to be measured . . . The MLUP does not properly or accurately depict or locate buffer areas surrounding the sloughs on the western side of Fort George Island. Exhibit B to the Prehearing Stipulation. Together with others, the Intervenors in the present case filed, in the Fort George DRI case, No. 86-4127, a motion to intervene as of right and request for consideration of additional issues on August 7, 1986. The intervenors in No. 86-4127 sought consideration of a wide range of issues in the Fort George DRI case, including questions concerning Blue Pond, the perimeter buffer zone, the interior habitat, weirs, berms, dikes and hydraulic connections, the adequacy of the water supply, the effect of the Game and Fresh Water Fish Commission's disapproval, the placement of various boundaries, and whether "Fairfield has failed to provide adequate protection of the microclimate and ecology of the Rollins Bird and Plant Sanctuary as mandated by the ADO . . ." Exhibit C to the Prehearing Stipulation. In filing their motion to intervene as of right and request for consideration of additional issues in No. 86-4127, Friends, Audubon and FWF expressly relied on Rule 27G-1.06, Florida Administrative Code. The portion under challenge here provides: (2) Motions to intervene filed with the Commission within 30 days of the filing of a notice of appeal may request the Commission to consider issues raised in the record below but not raised by the parties to the appeal. Rule 27G-1.06, Florida Administrative Code. In the order of transmittal, entered in No. 86-4127 on October 15, 1986, FLWAC denied consideration of every issue raised by the intervenors, except for the issue concerning the Rollins Bird and Plant Sanctuary, and added a related issue, also concerning the Rollins Bird and Plant Sanctuary, citing Rule 27G- 1.08, Florida Administrative Code. The portion of that rule under challenge here provides: Within 60 days of receipt of a notice of appeal, the Commission shall meet to review the issues raised by the parties. If the Commission determines that an issue of statewide or regional importance was not raised by the parties but is necessary to its disposition of the appeal, the Commission shall specify said issue and shall specify whether the issue shall be the subject of review based on the record made below, additional evidence or a combination thereof. New issues shall not be raised by the parties or other persons after this Commission meeting. At this meeting, the Commission may also dispose of procedural motions, including motions to intervene, which have been filed within 30 days of the filing of the notice of appeal. Rule 27G-1.08, Florida Administrative Code. Fairfield, as the applicant for the development order in No. 86- 4127, questions FLWAC's authority to promulgate rules that allow FLWAC to consider issues not raised by the party who took the DRI appeal, whether sua sponte or on motion of an intervenor.
Findings Of Fact By application number 21312, the applicant seeks a ten year water use permit for a total annual diversion of 3,831 million gallons to provide water and sewer services to an area containing approximately 7,300 acres. In September of 1969, the Florida Public Service Commission granted the applicant certificates of convenience and necessity. The existing facilities of the applicant include nine wells and an average capacity of 700 gallons per minute each. Based upon historical data and taking into accourt the reduction of construction in the service area, the projected 1984 water demand is 375 gallons per day per unit. This is equivalent to an average of 150 gallons per day per person, using a figure of 2.5 persons per living unit. The ultimate estimated population is to be 70,000 to 80,000 people with 28,000 to 32,000 living units. Based upon the average capacities of the wells, in order to meet the projected demand a total number of 22 or 23 wells will be required. This includes the nine existing wells, eleven proposed wells with the same 700 gallon per minute average and a fifteen percent standby capability of two or three additional wells. Rather than the total number of wells utilized -- 22 or 23, -- what is important is the total gallon per minute capacity of 15,400. An allocation based on this data would be equal to the applicant's requested annual maximum diversion of 3,831 million gallons and a daily maximum diversion of 18.37 million gallons. The requested diversion presents no threat of salt water intrusion. The proposed well sites will create no adverse impact upon the Fort Lauderdale well fields. While there is evidence of recharge to the aquifer from runoff waters, there is insufficient data to determine the exact amount which will be returned. For this reason, the staff report's water budget calculations are conservative.
Recommendation Based upon the above findings of fact and conclusions of law, it is recommended that a ten year permit be issued to the applicant for a maximum annual diversion of 3,831 million gallons; a maximum daily diversion of 18.37 million gallons and a maximum installed field capacity of 15,400 gallons per minute, utilizing 22 or 23 wells with a capacity of 700 gallons per minute each. It is further recommended that the applicant be subject to the conditions set forth on page 5 of the staff report (Exhibit 8) concerning the submission of monthly reports of daily pumpage and actual connections or population served, conformance with health department standards of the water quality of all wells, and the installation and maintenance of an observation well and monthly reports of the data obtained therefrom. Respectively submitted and entered this 10th day of May, 1976, in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 COPIES FURNISHED: Mr. John R. Maloy Executive Director Central and Southern Florida Flood Control District P.O. Box V West Palm Beach, Florida 33402 Mr. Edward B. Deutsch 350 Southern Federal Building 400 North State Road 7 Margate, Florida 33063 Mr. John Wheeler P.O. Box V West Palm Beach, Florida 33402 Attorney for the Central and Southern Florida Flood Control District
The Issue The issue in this case is whether Respondent, the Southwest Florida Water Management District (District), should grant Environmental Resource Permit (ERP) No. 43023532.000 authorizing Respondent, Florida Department of Transportation (DOT or Department), to construct the Pinellas Bayway Bridge Replacement and associated surface water management system.
Findings Of Fact The Florida Department of Transportation is a state agency charged by statute with the construction, maintenance, and operation of the State Highway System. The Pinellas Bayway Bridge in Pinellas County, Florida, is part of the State Highway System. The Southwest Florida Water Management District is a political subdivision created pursuant to Chapter 61-691, Laws of Florida (1961), which exists and operates under the Water Resources Act, Chapter 373, Florida Statutes. The District has the regulatory authority to implement the ERP program in Pinellas County, Florida. The existing Pinellas Bayway Bridge (the Existing Bridge) is a two-lane bascule structure located within and spanning Boca Ciega Bay, an Outstanding Florida Water. It has three-foot wide walkways on both sides, with no shoulders for the travel lanes. The Existing Bridge connects the cities of St. Petersburg and St. Pete Beach, and was built approximately 40 years ago upon perpetual easements "for public State Road right of way purposes" conveyed in 1960 and 1961 from BOT/IITF to the State Road Department, the predecessor of the Department. The perpetual easements do not contain any restrictions on the perpetual right to construct and maintain a "public state road upon and/or over said land," other than conditions that recognize prior rights of the United States of America and prior grants by the Board of Trustees. The proposed replacement of the Existing Bridge will be located entirely within the boundaries of those perpetual easements. The practice and policy of the Board of Trustees of the Internal Improvement Trust Fund (BOT/IITF), and the Department of Environmental Protection (DEP), has been that, under Section 253.002(1), Florida Statutes, perpetual easements such as those conveyed for the Bayway Bridge are sufficient authorization for expansion of bridges within the boundaries of the perpetual easements. Since the time of construction of the Existing Bridge, the area served by it has transformed from a largely uninhabited barrier island to a densely developed area. The Department has been studying and preparing for replacement of the Pinellas Bayway Bridge since the early 1980's, and studying alternatives since the early 1990's. In the year 2000, with the concurrence of the Pinellas County Metropolitan Planning Organization, the cities of St. Petersburg and St. Pete Beach, and the United States Coast Guard, the Department determined that the best alternative for replacing the Existing Bridge was a fixed-span, high level bridge with four travel lanes and a pedestrian walkway along the southern side of the bridge (the Replacement Bridge or Project). The fixed-span alternative was selected as superior to low-level and mid-level bascule options for superior traffic efficiency, superior access for emergency vehicles, superior emergency evacuation, and improved boat traffic. As part of the design process of the Replacement Bridge, the Bayway Bridge Beautification Committee was formed to provide the Department with input from the residents as to the aesthetics of the Replacement Bridge. The Bayway Bridge Beautification Committee was made up of representatives from the neighborhood and homeowners associations in the area, and submitted a report containing suggested improvements that were incorporated into the ultimate design of the bridge, including lighting, hardscape, and landscape features. Each of the three replacement alternatives (low-level, mid-level, or high-level) would result in the elimination of parking spaces within existing Department right-of-way adjacent to the east and west ends of the Existing Bridge. These parking spaces are intended for the use of drawbridge tenders and Department maintenance vehicles; currently, they also are utilized by fishermen and others recreating on the Existing Bridge. Neither the cities of St. Petersburg nor St. Pete Beach provides public parking in the vicinity of the Existing Bridge. Navigation and Shoaling The height of the Replacement Bridge will allow all boats using the Intracoastal Waterway (ICW) with mast heights of less than 65 feet to freely go under the bridge. Large boats currently must wait for the Existing Bridge to open and have to either circle or move forward and backward while waiting for the drawbridge to open. This will not be the case with the proposed bridge. The fenders lining the channel crossing under the proposed bridge will also be widened to 100 feet from the existing 90 feet. The Replacement Bridge also will be higher in places other than the ICW crossing, including 39 feet high near the west end where Mud Key Channel crosses (versus 9 feet under the Existing Bridge). As a result, more boats will be able to pass under the Replacement Bridge in Mud Key Channel than with the Existing Bridge, and fewer will have to use the so-called Entrance Channel paralleling the south side of the bridge between the ICW and Mud Key Channel. In this respect, the Replacement Bridge will improve navigation. Petitioners contend that additional use of Mud Key Channel, coupled with changes in the ability of boaters to see other boats on the opposite side of the bridge will change, will create a navigation hazard and safety concern for boaters, wading fishermen, and occasional swimmers using Mud Key Channel and the Entrance Channel. As for wading fishermen and occasional swimmers, their activities occur mostly to the south of the extreme western end of the bridge, and boats using Mud Key Channel would pass them whether they pass under bridge at Mud Key Channel or pass under at the ICW and use the Entrance Channel to or from Mud Key Channel. The Replacement Bridge will not increase the number of boats passing by them. As for boaters' ability to see, the Existing Bridge is lower, has more but narrower pilings. The higher Replacement Bridge will have fewer pilings but they will be wider, including 22 feet square pile caps 7 feet high at the water line. In terms of boaters' ability to see through the bridge, the Existing Bridge and Replacement Bride have advantages and disadvantages, depending on the particular circumstances and location of the boats, wading fishermen and occasional swimmers in question. It was not proven that the Replacement Bridge, compared to the Existing Bridge, will create navigation hazards and safety concerns. The Replacement Bridge will extend some 70 feet into the Entrance Channel to Mud Key Channel. Currently, the width of the Entrance Channel is 215 feet, narrowing to 130 feet at the junction with Mud Key Channel. The width of Mud Key Channel at some points is only 100 feet. The Replacement Bridge will narrow the Entrance Channel to a minimum width of 145 feet, will not affect the width at the junction with Mud Key Channel, and will not affect the width of Mud Key Channel itself. The currents in this area are felt least within the Entrance Channel. Boats are currently able to pass each other safely in the Intercoastal Waterway and the narrow confines of Mud Key Channel, which are both narrower than the Entrance Channel will be upon completion of the Project. Boats with masts higher than 65 feet will not be able to go under the Replacement Bridge. Petitioner, Michael T. (Ted) Irwin, has a boat with a 90-foot mast (with radio antenna), which he keeps at his residence north of the bridge site. Once the Replacement Bridge is constructed, he will have to either access the Gulf of Mexico by heading north through Johns Pass, or move his boat to another mooring location. Mr. Irwin testified that Johns Pass, while navigable in his boat, is much more difficult and much less desirable for him than going through the drawbridge at the Existing Bridge. There are over 11,000 boat crossings per year by boats with masts too tall to pass under the Existing Bridge. Of these 11,000, Mr. Irwin's boat accounts for 20 to 60 of those crossings. Mr. Irwin testified that there are three or four other boats in the area with masts taller than 65 feet. Even assuming that those boats are kept north of the bridge site, which was not clear from the evidence, there was no evidence as to the extent to which those boat owners would be inconvenienced by having to use Johns Pass, or as to whether they could make suitable alternate arrangements. Clearly, the Replacement Bridge will have some impact on navigation. While the Replacement Bridge will require Mr. Irwin to change his current boating practices, and while the Entrance Channel will be narrower, the impact on navigation in the area will generally be positive. For the vast majority of boaters, boat traffic will move more freely through the area and, at least in some circumstances, with better visibility. With respect to sediment transport or shoaling, the Department introduced evidence in a bridge hydraulics report showing that the Replacement Bridge would not experience scour around the pilings during either a 100- or 500-year storm event. In addition, there was expert testimony that harmful erosion or shoaling would not occur as a result of the Project. Petitioners offered only speculation on the likelihood of erosion or shoaling, candidly admitting that their concern was that such conditions "might" occur. There is an undisputed evidentiary basis to conclude that sediment transport or shoaling will not occur around the Replacement Bridge. Fishing and Recreation People currently fish from the Existing Bridge using the two three-foot wide catwalks. Although not designated for public parking, people who do not live within walking distance of the bridge site currently park on either end of the Existing Bridge within the Department's right-of-way. All of these parking spaces will be eliminated by the Replacement Bridge; but they would be eliminated under all designs considered, including a low level drawbridge. Other bridges in immediate vicinity are not used for fishing due to lack of nearby parking. Fishing will be allowed from the Replacement Bridge from the single 11-foot wide multi-use path along the south side of the Replacement Bridge. While the multi-use path will allow fishermen and other users to get farther away from passing car traffic, fishing on strong incoming (south-to- north) tides will be less desirable from the south side of the Replacement Bridge, and the higher bridge elevations also will make fishing generally less desirable. There are several other locations within 20 minutes of the Existing Bridge that are available for fishing by the public. In particular, the fishing pier at the old Skyway Bridge in southern Pinellas County is specifically designated for public fishing, as are several other locations. The Replacement Bridge's multi-use path also will be more user-friendly for people who want to walk or bike across. Also, the path will continue from the bridge site to the intersection of State Roads 679 and 652, providing a safe sidewalk where none currently exists. The path will ultimately tie into a trail system linking the area to Fort DeSoto Park. The Replacement Bridge will also be more wheelchair accessible than the Existing Bridge. Water Quality Boca Ciega Bay is an Outstanding Florida Water. The ambient existing water quality in Boca Ciega Bay meets the standards which are applicable to that waterbody in the location of the Replacement Bridge, as demonstrated by the water quality data gathered from Pinellas County and by the Department. Such data were comprised of dissolved oxygen readings from the County and the analysis of water samples provided by the Department. Petitioners questioned whether such water quality data were sufficient, but testimony from District experts demonstrated the sufficiency of these data. Petitioners introduced no evidence to indicate that water quality does not meet standards in the vicinity of the Project. Within the limits of the Project, including the bridge site, the western approach to the bridge, and State Road 679 to the intersection of State Road 652 of the eastern side of the bridge site, there currently is a very limited amount of surface water runoff treatment. Although the project will involve adding several acres of impervious surface, after construction there will be less untreated surface water runoff than exists currently. The proposed treatment system will primarily involve three ponds: two lined effluent filtration ponds along State Road 679; and a wet detention pond located adjacent to the Sunshine Skyway Bridge, known as the compensation pond. The compensation pond is proposed because there is not enough right-of-way in the project area to build ponds or other treatment systems to treat the runoff from the Replacement Bridge. The compensation pond will treat surface water runoff from the Skyway Bridge that today is discharged untreated into the same Outstanding Florida Water, Boca Ciega Bay. The two effluent filtration ponds will be lined with an impermeable material up to the level of seasonal high ground water elevations within the vicinity of those pond sites to prevent groundwater drawdown and prevent interaction between water in the pond and groundwater. DOT introduced detailed site plans, engineering studies and credible expert engineering testimony that the three stormwater treatment ponds will detain stormwater runoff in a manner that complies with the presumptive criteria in the District's Basis of Review. In addition, the two effluent filtration ponds have been oversized so as to treat 100 percent more volume than is required for treatment systems discharging into Outstanding Florida Waters. Less untreated surface water runoff will be discharging into Boca Ciega Bay after construction than is today. Further, much of the impervious area to be added will not be automobile travel lanes, and these areas will not generate the heavy pollutant loadings associated with the travel lanes. In addition, the pollutant loading from the travel lanes on Replacement Bridge will be less than from the Existing Bridge. At the Existing Bridge, pollutant discharge into Boca Ciega Bay occurs in several ways. First, oils and greases from the actual drawbridge mechanism itself drip straight down into the Bay. With the elimination of the drawbridge, this discharge will stop. Second, stopped cars and trucks waiting for the drawbridge to open and close drip oils and greases onto the roadway in greater concentrations than traffic which is moving. This was evident by examining photographs of the travel lanes on either side of the drawbridge, and the dark staining of the roadway where traffic is stopped. With no drawbridge to stop traffic, less oil and grease will be discharged. Third, boats waiting for the existing drawbridge to open also discharge undetermined amounts of uncombusted gasoline and oil into the water. (Generally, their engines are kept running and in and out of gear to maintain steerage while waiting for the bridge to open.) Those boat engines will have to run for less time in the vicinity of the Project if the boats do not have to wait for the existing drawbridge, thus reducing the discharge of uncombusted gasoline and oil into the Bay. Another boost to water quality will occur as a result of the mitigation for the Project. District rules allow impacts to wetlands and other surface waters to be mitigated, and the Department does so in accordance with the program set forth in Section 373.4137, Florida Statutes. That program calls for the Department to contribute a dollar amount to the District based upon the expected acres of wetlands and other surface waters impacted by the project. Mitigation provided for this purpose in accordance with Section 373.4137, Florida Statutes, and approved by the Secretary of DEP, is deemed to satisfy mitigation requirements. In this case, the mitigation project to compensate for impacts by the Replacement Bridge to sea grass beds within the affected surface waters is a water circulation project at Fort DeSoto Park, located at the southern end of Boca Ciega Bay, in the same receiving waters where the impacts will occur. The project consists of opening a dead-end section of the Bay created by the SR 679 causeway to Fort DeSoto Park to improve water flow. Improved water flow will improve dissolved oxygen levels, which in turn will improve conditions for sea grasses, which will in turn lead to more dissolved oxygen. This Project has been approved by separate final order by DEP, satisfying the mitigation requirement. In addition, the Department and the District demonstrated that the mitigation project will improve water quality in the receiving waters. The Project will not degrade water quality in Boca Ciega Bay, and the record is also clear that the Project will actually improve water quality in the Bay. This means that the Project is consistent with the Surface Water Improvement Management Plan adopted by the District, which calls for improved water quality and increased sea grasses. Petitioners called no witnesses with respect to the water quality issue. Although Petitioners listed a water quality expert, James Shirk, as a witness in answers to interrogatories, and even though Respondents deposed Mr. Shirk; Petitioners not only decided not to call Mr. Shirk as a witness, they objected to introduction of Mr. Shirk's deposition into the record of the case. In their PRO, Petitioners criticized a lack of studies to determine the efficacy of proposed Ponds 1 and 2 and the Compensation Pond. They also criticized a lack of studies of water quality impacts of untreated discharges from a 18-inch pipe to be constructed at the western end of the bridge. They argue that, due to the asserted lack of studies, reasonable assurances were not given either that the Project will not degrade water quality or that it will result in a net improvement in water quality. But, based on the evidence in this case, studies of the kind Petitioners want to require were not necessary to prove that the Project will not degrade water quality but rather will result in a net improvement in water quality. In their PRO, Petitioners also cited the deposition testimony of Jeremy Craft that Ponds 1 and 2 discharge into Class III waters "in the vicinity of a Class II water body" and criticized the lack of a "plan or procedure with respect to protection of the Class II waterbody that demonstrates that the regulated activity will not have a negative impact and will [not] result in violations of water quality standards in such Class II waters, as required in the District's Basis of Review [BOR] Section 3.2.5(b)." But there was no other evidence that Ponds 1 and 2 will be a "regulated activity" or "system" that is "adjacent or in close proximity to Class II waters." To the contrary, the evidence that the nearest Class II waters were over a mile away from the Project site and would not be affected negatively by the Project. Similarly, Petitioners in their PRO contend that the Compensation Pond "discharges to Class II waters and waters that are prohibited for shellfish harvesting" and that "[t]here has been no plan or procedure provided with respect to protection of that Class II waterbody that demonstrates that the regulated activity will not have a negative impact on Class II waters and will not result in violations of water quality standards in such Class II waters, as required in the BOR Section 3.2.5(a) and (b)." The basis cited for this criticism was reference to "Shellfish Harvesting Area Classification Map #42 (Effective: June 18, 1997)," that appears to show the Compensation Pond adjacent to or in close proximity to an area where shell fishing is prohibited. There was no testimony explaining the map, which did not purport to map Class II waters. In any event, if the Compensation Pond is "adjacent or in close proximity" to Class II waters which are not approved for shellfish harvesting, and if it is considered to be the "regulated activity" or "system," creation of the Compensation Pond to treat previously untreated discharges will not have a negative effect on Class II waters or result in violations of water quality standards in the Class II waters. Petitioners in their PRO also cite the Final Roadway Soil Survey and Stormwater Pond Report (Report) prepared by the Department's consultants for the purpose of establishing the fact: "Groundwater data beneath the roadway near the east end of Pond 2 indicate that the seasonal high groundwater table is between 4.0 and 4.5 feet, NGVD." Although never made explicit, Petitioners' PRO seems to raise the specter that the liner for this pond was deficient because it only came up to 2.5 feet, NGVD. No witness explained where the Report establishes the "seasonal high groundwater table" "beneath the roadway near the east end of Pond 2," or if it even does. It appears that Sheet 9 of Appendix B of the Report indicates a single datum point of groundwater at approximately 4.0 feet, NGVD, on June 1, 2002; meanwhile, Table 4 of Appendix A of the Report also states that the "Estimated Seasonal High Groundwater Table" at the same location is at the "Approximate Elevation" of 1.2 feet, NGVD. In any event, even assuming that the "seasonal high groundwater table" "beneath the roadway near the east end of Pond 2" were 4.5 feet, NGVD, all of the expert testimony on the subject of the liner was that it came up high enough to function properly in the location of Pond 2. The last water quality issue raised in Petitioners' PRO addresses the amount of impervious surface runoff treated under the Replacement Bridge Project. Specifically, Petitioners seem to contend that BOR 5.8(b) was interpreted to only require treatment of the runoff contributed by the two additional automobile travel lanes provided by the Replacement Bridge Project; the area of the existing travel lanes and the multi-use path was not figured in the calculation. While not clearly explained, the expert testimony was that the Project met the requirements for water quality treatment under both BOR 5.2.e. and BOR 5.8(b) and (c). BOR 5.2.e. requires projects discharging into Outstanding Florida Waters to provide treatment for a volume 50 percent more than otherwise required for the selected treatment system. BOR 5.8(b)1. requires that, for "off-line treatment systems and on-line treatment systems . . . which provide storage of the treatment volume off-line from the primary conveyance path of flood discharges," the contributing area to be used in calculating the required treatment volume is the area of new pavement. It appears that BOR 5.8(b)1. was used for the parts of the Project not treated by Ponds 1 and 2. The "area of new pavement" was considered, for purposes of BOR 5.8(b)1. to be just the new travel lanes; the area of the multi-use path apparently was not added for purposes of BOR 5.8(b)1. because it would not be expected to add much, if any, pollutant loading. In addition, BOR 5.8(c) provides: When alterations involve extreme hardship, in order to provide direct treatment of new project area, the District will consider proposals to satisfy the overall public interest that shall include equivalent treatment of alternate existing pavement areas to achieve the required pollution abatement. While also not clearly explained, the expert testimony was that BOR 5.8(c) also applied and was met by the Project.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Southwest Florida Water Management District enter a final order approving the application of the Florida Department of Transportation for Individual Environmental Resource Permit No. 43023532.000. DONE AND ENTERED this 25th day of November, 2003, in Tallahassee, Leon County, Florida. S ___________________________________ J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of November, 2003. COPIES FURNISHED: Robert C. Downie II, Esquire Assistant General Counsel Department of Transportation 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 William D. Preston, Esquire 2937 Kerry Forest Parkway Suite B-1 Tallahassee, Florida 32309-6825 Steve Rushing, Esquire David C. Ryder, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899 E.D. "Sonny" Vergara, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
The Issue Whether Southern Hy Power Corporation (Hy Power) has provided reasonable assurance, based on plans, test results, or other information, that its proposed hydroelectric facility will comply with the Management and Storage of Surface Water (MSSW) statutes and rules of Southwest Florida Water Management District (SWFWMD) and the Wetland Resource Management permit (WRM)/water quality certification statutes and rules of the Florida Department of Environmental Protection (DEP).
Findings Of Fact By Joint Prehearing Stipulation the parties agreed to the following description of the parties and the project: PARTIES: The Department of Environmental Protection (the Department) is a government agency in the State of Florida existing by virtue of Section 20.255, Florida Statutes, and operating pursuant to Chapters 253, 373, 376, and 403, Florida Statutes, and Title 62, Florida Administrative Code. Under an interagency agreement with SWFWMD, the Department also implements Title 40D, Florida Administrative Code. The Department is located in Tallahassee, Florida, and it has a district office in Tampa, Florida, which district includes Levy County. Southern Hy Power Corporation is a Florida Corporation whose principal offices are located at 7008 Southwest 30th Way in Gainesville, Florida. Betty Berger is an interested party with a mailing address of Post Office Box 83, Inglis, Florida. The Campbells are an interested party with a mailing address of 245 Palm Street, Inglis, Florida. Hy Power applied on August 31, 1993, to the Department for a WRM permit/water quality certification to construct a hydroelectric facility on the Inglis By-Pass Channel. The project is located in Section 12, Township 17 South, Range 16 East, within the town of Inglis in Levy County. The facility consists of a powerhouse located on the south side of the channel measuring about 28 feet wide by 115 feet long, drawing water from the Inglis By-Pass Channel, passing it through a single-pit type turbine and discharging downstream of the Inglis By-Pass Spillway Dam. Hy Power applied on August 4, 1998, to the Department for a MSSW permit for the same proposed hydroelectric facility on the Inglis By-Pass Channel. DESCRIPTION OF PROPOSED PROJECT The project involves the construction of an intake structure, powerhouse, and tailrace on a 0.61-acre area located on the south side of the existing Inglis By-Pass Spillway. The facility will take advantage of the existing hydrostatic head that exists on either side of the Spillway Dam, to generate electricity. The powerhouse will be constructed below grade and will contain a single megawatt turbine and generating unit. The intake structure will divert flows from the upstream side of the Spillway Dam through the powerhouse and back into the By-Pass Channel. A small one-story control building and low profile substation will be constructed above grade within the boundaries of the project area. The hydroelectric project is considered to be a "Run of the River" type of facility because it can only use that water which flows down the existing channel. The geometry of the channel restricts flow to a certain amount, therefore the project cannot create or use flows above those that the By-Pass Channel can provide. The overall authority for control of water levels in Lake Rousseau and flow to the lower Withlacoochee River will remain with the DEP. Lake Rousseau was created in 1909 when the Inglis Dam was constructed across the Withlachoochee River for the purposes of hydroelectric generation. The dam impounds over 11 miles of the Withlachoochee River and forms a lake approximately 3,000 to 4,000 acres in size. Prior to construction of the Barge Canal, water released from the Inglis Dam would flow down the lower portion of the Withlachoochee River about 10 miles before entering into the Gulf of Mexico. In the mid to late 1960's the Army Corps of Engineers (ACOE) built a portion of the Cross Florida Barge Canal between the Gulf of Mexico and Lake Rousseau. The canal severed the Withlachoochee River downstream of the Inglis Dam causing its flow to be diverted into the Barge Canal and then into the Gulf. In order to maintain the flow of freshwater from Lake Rousseau to the lower segment of the River, the 8,900-foot long Inglis By- Pass Channel and Spillway were constructed. The resulting downstream flow ensures navigation in the lower portion of the River and sustains its freshwater and estuarine environment. The water level in Lake Rousseau is generally maintained at an elevation of 27.5 feet above mean sea level (msl) by a combination of the Inglis Dam, the Inglis Lock, which is located in the Barge Canal, and the By-Pass Channel Spillway. These water control features are known collectively as the Inglis Project Works. The water levels in the lower Withlachoochee River immediately to the west of the By-Pass spillway are close to sea level. The resulting head provides the potential energy needed to drive the proposed generator turbine. Under normal conditions the majority of water released from Lake Rousseau flows over the Spillway Dam into the lower segment of the River. According to the DEP Office of Greenways and Trails (OGT), the maximum capacity of the existing By-Pass Channel Spillway is 1,540 cubic feet per second. The hydroelectric project will divert whatever flow is allowed around the existing spillway through the turbine and back into the channel. When the Cross Florida Barge Canal project was cancelled in the 1990's, the ACOE transferred ownership of the property to the State of Florida Board of Trustees, who in turn has leased the property to the DEP for use as the Cross Florida Greenbelt State Recreation and Conservation Area. Management of this property, the control of river flow and lake levels, and operation of the Inglis Project Works are exercised by the DEP's OGT. The OGT utilizes a document entitled "Water Control Plan for Inglis Project Works," dated September 1994, as a guide to operating the structures. The Water Control Plan is incorporated as part of the MSSW intent to issue. On or about April 25, 1995, the Governor and Cabinet, sitting as the Board of Trustees of the Internal Improvement Trust Fund ("Trustees"), approved a request from Hy Power to sublease 0.61 acres of Greenway property at the project site for the purpose of providing electric power. The request was challenged by Berger and the Campbells, and resulted in an administrative hearing held on November 3, 1995. As a result of the hearing, Administrative Law Judge Larry Sartin entered a Recommended Order on July 12, 1996, that the Board enter an order approving execution by the DEP of the proposed sublease and dismissing the petition of Berger and the Campbells. The Recommended Order was approved by the Trustees in its entirety in a Final Order dated April 12, 1996 ("Final Order"). Berger v. Southern Hy Power Corporation et al., Case No. 95-3589. A copy of the Final Order is listed as an exhibit to this Stipulation, and the Findings of Fact and Conclusions of Law contained therein are adopted herein. As previously ruled by the undersigned, the previous Final Order is res judicata as to Petitioners in this case, who are collaterally estopped from challenging any of the findings of fact or conclusions of law contained in the previous Final Order. Petitioners reserve the right to litigate issues of fact and law not addressed in the Findings of Fact or Conclusions of Law contained in that Final Order with regard to the permittability of this project under the WRM and MSSW permitting proposals, and to raise objections as to relevance to this proceedings of any of the Findings of Fact or Conclusions of Law in the Final Order. On February 21, 1995, Hy Power filed application with the Federal Energy Regulatory Commission (FERC) for a conduit exemption from the licensing requirements of Part I of the Federal Powers Act (FPA) for the proposed project. Petitioners and various other persons filed protests with FERC in opposition to the project. On April 21, 1997, FERC issued an Order Granting Conduit Exemption, a copy of which is listed as an exhibit to this Stipulation. Petitioners in this case are collaterally estopped from challenging any of the findings or conclusions contained in that Order Granting Conduit Exemption. Petitioners reserve the right to litigate issues of fact and law not addressed in the Findings of Fact or Conclusions of Law contained in that Order Granting Conduit Exemption with regard to the permittability of this project under the WRM and MSSW permitting proposals, and to raise objections as to relevance to this proceedings of any of the findings or conclusions in the Order Granting Conduit Exemption. FACTS ADDUCED AT HEARING OUTLINE OF PROJECT The proposed project calls for the construction of a water retention structure along the existing By-Pass spillway, the excavation of a large hole in which the powerhouse and turbine would be constructed "in-the-dry" south of the existing dam, and a millrace below the proposed project to return the water back into the existing water course. Conflicting testimony was received regarding the facts surrounding the construction of the project. These included: whether the proposed project will touch the existing wing walls of the existing dam; whether the water retention structure is a coffer dam; whether the proposed water retention structure will safely retain the water; whether the powerhouse and turbine have sufficient negative buoyancy to stay in the ground; whether the proposed excavation will weaken the existing dam; and whether the de-watering of the excavation site will adversely impact ground and surface water. PROJECT DESIGN AND ENGINEERING Engineering for the project was directed by witness Richard A. Volkin, a professional engineer and president and CEO of Engineering Company, Inc., based in Canton, Massachusetts. Mr. Volkin has extensive national and international experience in the design, management, and operation of hydroelectric facilities. Other engineers in Mr. Volkin’s firm worked on the project under Mr. Volkin’s direct supervision, including John May, who became registered as a professional engineer in Florida in order to sign and seal the engineering drawings for the project, which he initially did around 1994. Mr. May became ill and retired in 1998. Because of the length of time the application process has taken and the fact that Mr. May retired, there was a time while the application was pending, when Hy Power's design team was without a registered Florida engineer. When this was brought to the attention of Hy Power, Hy Power substituted Steven Crockett for Mr. May as the Florida-registered professional engineer of record for the project. DEP routinely accepts an applicant’s changing its engineer of record during the course of permit application or construction. Mr. Crockett is a civil and structural engineer who has considerable experience in preparing dam structural designs. Mr. Crockett independently reviewed and evaluated the engineering drawings for the project. Mr. Crockett resealed the drawings by using his drawn seal and signing the plans because his embossed seal was not readily available and time was of the essence. Mr. Crockett has advised DEP that he is now engineer of record for the project, using the appropriate DEP forms. Mr. Volkin’s firm performed all of the studies required by the various agencies, including a geotechnical study of the area, a 50-year analysis of water flow in and out of the Lake Rousseau regime, and water quality evaluations of water in the By-Pass Channel. The ACOE performed deep hole borings of the soils (approximately 36-40 feet below sea level) in the area of the project site to determine soil stabilization conditions at the site when they were constructing the Inglis Project Works. The soil conditions found can reasonably be expected to be similar today. Mr. Volkin’s company also took its own eight-foot deep surface core samples. The purpose of those samples was to verify the ACOE data. The new core samples verified the original core samples. Mr. Volkin also reviewed the ACOE’s engineering drawings developed from construction of the Spillway Dam. These show that the dam is founded on limestone bedding that has been stabilized with concrete. The hydroelectric facility will be constructed adjacent to and south of the dam structure and adjacent to and north of the barge canal. The same type of limestone bedrock is found in the area of the proposed construction. The facility design includes an intake channel on the upstream channel and a tailrace downstream. Those are the only structures that will be constructed next to the By-Pass Channel. The construction of the facility itself will be "in the dry." Hy Power will use coffer dams to seal off the construction site from the By-Pass Channel, so that there will not be water leakage from the Channel into the construction site. Water from the By-Pass Channel will enter the power plant when the coffer dams are lifted and the water is allowed to flow into the facility. The Petitioners presented the testimony of Bill Edwards, an individual with considerable experience in the construction of bridges, cofferdams, and similar concrete structures in aquatic and semi-aquatic conditions. Mr. Edwards is a former hard-hat diver who worked all over the world and worked in Florida for many years prior to his retirement. Based upon his experience and expertise in construction related to projects of this type, his testimony is credible and worthy of consideration. Mr. Edwards pointed out that if the proposed water retention structure did not touch the wing wall of the existing dam, it could not keep the water out and would not have the strength that it needed to retain the water. Hy Power’s witnesses explained that the retention structure would be set close enough to the existing wing wall that waterproofing materials could be placed between the two structures to keep the water out. Further, that the existing plans did not show interior bracing which would be included for structural strength and integrity. In sum, the retention structure will be in contact with existing dam’s wing wall, but will be free standing and not dependent upon the strength of the wing wall for its strength. Mr. Edwards pointed out that a cofferdam by definition has walls on all sides of the structure. The structure proposed by Hy Power did not have walls all the way around the proposed excavation. In rebuttal, Hy Power presented evidence that its plans were conceptual, design drawing and not construction plans. Hy Power represented that in actuality it would put as many walls as were necessary to keep the water out of the hole it intended to excavate. Trash racks will be constructed at the intake structures to protect aquatic life and make sure that trash and vegetation do not enter the intake structure or go down river. The trash rack bars will be two inches on center, which the U.S. Fish and Wildlife Service has determined as the appropriate size for the protection of fish. The turbine blades are "double regulated," and operate generally between 60 and 90 revolutions per minute. The design enables the turbine to operate at a constant speed to generate a consistent flow of electricity, notwithstanding the fact that the flow of the water may vary. The blade speed is not very fast, and the 2.5-meter blades provide a two to three-foot opening. This design acts to prevent fish mortality. There are four ways to shut off the flow of water through the proposed structure: close the pitch of the blades, close the wicket gates, allow the counter balance to the wicket gates to kick in and automatically close the gates, and close off the main gates. This is a fail safe system ("four level redundancy") designed to work upon any failure. Once water goes through the generator, its velocity is reduced to no greater than its intake rate which is a maximum of three feet per second. This prevents the water being discharged from the tailrace from causing erosion. If the head of water in the dam produces a flow exceeding three feet per second, it can be diverted over the other dams which will be functional. The power plant will be encased in concrete, except for a small access way that enables a person to go down a set of stairs to the plant. It will be a sealed, waterproof structure, as required by FERC and the ACOE. This will prevent penetration of groundwater, or flood waters in the event a massive flood overtops the plant. The only water entering the powerhouse will be through the turbine tunnel for power generation purposes. Mr. Edwards pointed out that the powerhouse was a closed structure and as such would have positive buoyancy, that is, it would float. Mr. Edwards pointed out that the proposed site is between the barge canal and By-Pass spillway and there is a great deal of groundwater and potentiometric pressure in the existing water table. In sum, there is a unlimited supply of groundwater at the site, and powerhouse could float out of the ground just like an empty swimming pool. Hy Power presented rebuttal evidence that the weight of the building, the turbine, and the water flowing through the turbine would be close to negative buoyancy, and they would add additional weight to the structure as necessary to keep it in place. The project is designed to generate three megawatts of electric power which is enough electricity to serve between 300 and 3000 homes, depending on usage. The project is designed to be unmanned. This is common for facilities such as this. The plant can be operated by remote control, unlike the existing controls at the By-Pass Dam, which are operated manually. DEP can access, monitor, and control remotely the generator's operation to include shutting the facility down at any time. There will be remote sensors to monitor water elevations. Flood protection will improve because of the ability of DEP to manage water flow from a remote location. If there is any major disruption, the plant will shut itself down. The project is classified as "green power." In other words, it generates natural energy without any disruption to the environment. The project will have minimal to no impact on the environment. There will be no significant changes in water quality compared to existing conditions as a result of either construction or operation of the facility. WRM Permit Criteria Hy Power has provided reasonable assurances that the proposed project will not cause a violation of state water quality standards of Section 403.918(a), Florida Statutes (1991). The parties stipulated that turbidity and dissolved oxygen were the two surface water quality issues of concern in this proceeding. The receiving water body is the Inglis By-Pass Channel. The Inglis By-Pass Channel is a Class III surface water. The project is not located in a OFW. While the lower Withlacoochee River is an OFW, the OFW designation runs up the natural river itself, and does not include the Spillway Dam, tailrace, or the remainder of the By-Pass Channel. There would be no degradation of water quality at the point of contact with the Withlacoochee River OFW. The DEP and FERC looked specifically at potential for turbidity and dissolved oxygen in determining whether the project would violate state water quality standards. The standards for turbidity and dissolved oxygen will not be violated. Because the By-Pass Dam is an under flow structure, a minimum of oxygenation currently occurs as water flows through the existing dam. The proposed project runs the water underground through the generator; however, Hy Power will measure the dissolved oxygen below the dam in the Lower Withlacoochee River. In the event there is any lowering of dissolved oxygen, Hy Power can install a "sparge ring" to reoxygenate the water going through the turbine so that dissolved oxygen remains at current levels. No turbidity will be added to the receiving water as a result of the project, because water velocity is low and the structure is encased in concrete and rip-rap. The only other potential for turbidity would occur when the coffer dams are removed after construction is complete. The coffer dams can be removed with the generator closed to permit any turbidity to settle. The amount of siltation that might occur when the generator is opened would be insignificant. Where a project is not in a OFW, an applicant must provide reasonable assurance that the project will not be contrary to public interest. See Section 403.918(2), Florida Statutes (1991). Hy Power has provided such assurances. The project will not directly affect public health, safety or welfare, or the property of others. See Section 403.918 (2)(a)1., Florida Statutes. There are concerns relating to the structural integrity of the proposed facility and adjacent structures which are discussed extensively below. The project will have no adverse impact upon the conservation of fish and wildlife, including threatened and endangered species and their habitat. See Section 403.918 (2)(a)2., Florida Statutes. While manatees are not likely to be found at the project site, the installation of the trash racks will eliminate any potential adverse impact on manatees. In fact, the racks will be an improvement over the current unprotected Spillway Dam. DEP procedures require a specific manatee control plan be implemented to deal with site specific concerns. The project will not adversely affect navigation or the flow of the water or cause harmful erosion or shoaling. See Section 403.918(2)(a)3., Florida Statutes. The project will not adversely affect fishing or recreation values or marine productivity in the vicinity of the project. See Section 403.918(2)(a)4., Florida Statutes. The permanent project and its construction will cause no significant environmental impacts. See Section 403.918(2)(a)5., Florida Statutes. There will be no adverse impacts to significant historical and archeological resources. Section 403.918(2)(a)6., Florida Statutes. With regard to the impact on current conditions and relative value of functions being performed by the areas affected by the proposed activity, there will be no negative impacts. See Section 403.918(2)(a)7., Florida Statutes. Improvement will result from better control of water flow at the project site, installation of trash racks and implementation of green power. THE FORESEEABLE ADVERSE SECONDARY OR CUMULATIVE IMPACTS Potential adverse secondary impacts related to power transmission are addressed through the fact that there is an existing power line corridor that can be used to transmit the electricity. Any need to change the corridor could be addressed by subsequent DEP permitting. Cumulative impacts are not at issue. Mr. Gammon, with Florida Power, acknowledged that the current electric company, presumably Florida Power, would be required by FERC to transport the electricity generated by Hy Power over its existing corridor and poles. No final decision has been made regarding how to access the site with equipment during construction. Several feasible construction options exist, and there are several ways of accessing the site with heavy equipment vehicles and without impacting wetlands. Any final decision would be subject to DEP approval. Since the project meets the public interest criteria of Section 403.918(2)(a), Florida Statutes, and wetland impacts are minimal, the project is permittable without the need for mitigation. See Section 403.918(2)(b), Florida Statutes. The ACOE has issued a permit for the facility. The permit varies slightly from the DEP intent to issue in the use of reinforced concrete rather than rip-rap on the bottom half of the intake channel. This is to comply with ACOE preference, but the variation has only an environmental benefit. Counsel for Petitioners sought to elicit testimony from Linda Sloan, Executive Director of the Withlacoochee Regional Planning Council, with regard to compliance of the proposed project with the Town of Inglis Comprehensive Plan and Land Development Code. Such compliance is not relevant to this proceeding. At any rate, Ms. Sloan conceded that any prohibition that might apply in the Land Development Code to construction of the proposed facility could potentially be alleviated by exemption or variance provisions in the Code. MSSW PERMIT CRITERIA The project will provide adequate flood protection and drainage in the conventional sense. See Rule 40D-4.301(1)(a), Florida Administrative Code. Because the amount of impervious area is minimal, runoff from the project will not in any way contribute to increased flooding or adversely impact drainage patterns. The total amount of impervious area of the facility is less than that of a single-family residence. SWFWMD rules do not even require MSSW permits for single-family residences because the impact is not significant. The only purpose for requiring a MSSW permit for the project is to review the project’s potential downstream impacts to the watershed, not stormwater runoff from the facility itself. The project will not cause adverse water quality or water quantity impacts on adjacent lands in violation of Chapter 373, Florida Statutes, or cause a discharge that violates state water quality standards. See Rule 40 D-4.301(1)(b), Florida Administrative Code. As indicated by the WRM water quality findings above, the project will not generally violate state surface water quality standards. See Rule 40 D-4.301(1)( c), Florida Administrative Code. The project will not generally cause adverse impact on surface or groundwater levels or flows. See Rule 40 D- 4.301(1)(d), Florida Administrative Code. Since the project is a run-of-the-river, it will not diminish the capability of a lake or other impoundment to fluctuate through the full range established for it under Chapter 40D-8, Florida Administrative Code. The project will not cause adverse environmental impacts, or adverse impacts to wetlands, fish, and wildlife or other natural resources. The project can be effectively operated and maintained. See Rule 40D-4.301(1)(g), Florida Administrative Code. The project is a slow speed, low maintenance facility. The design concept is well established and has been successfully used for many years. Possible adverse affects to public safety are discussed below. The project is consistent with the requirements of other public agencies. See Rule 40D-4.301(1)(i), Florida Administrative Code. Potential harm to water resources within the SWFWMD are discussed below. See Rule 40D-4.301(1)(j), Florida Administrative Code. The proposed project generally will not interfere with the legal rights of others. See Rule 40D-4.301(1)(k), Florida Administrative Code. The proposed project is not against public policy. See Rule 40D-4.301(1)(l), Florida Administrative Code. The project complies with the requirements contained in the Basis of Review. See Rule 40D-4.301(2), Florida Administrative Code. There is a dispute as to whether the project was within or at the edge of the 100-year flood plain. This dispute is related to how one interprets the rule as it relates to the millrace and the location of the facility which is under ground. In the conventional sense, the project is not in the flood plain. Further, the project is designed in such a way, that it is waterproof if it were topped with water. While in the past SWFWMD may have had concerns that the project might cause downstream flooding, SWFWMD currently has no such concerns, given the run-of-the-river status of the proposed project. The operation of the project will not cause downstream flooding. The DEP included in its intent to issue, conditions contained in the sublease between Hy Power and the DEP in order to ensure that the facility would remain run-of-the-river, would comply with the water control plan, and would otherwise comply with the terms of the sublease. The DEP has final control over water flow and can revoke the permit or otherwise take enforcement action against Hy Power if Hy Power fails to comply with the water control plan. GROUNDWATER IMPACTS Operation of the project will not cause groundwater contamination or otherwise have adverse groundwater impacts. Some concerns about groundwater during excavation of the construction site were raised. The conflicting evidence received regarding them is discussed below. An area of concern was the de-watering plan for the project. Everyone agrees there will be some water seepage into the construction site that will have to be pumped out. The parties disagree regarding the amount of water that will have to be removed. Their estimates of amount of water to be removed vary because their estimates of size and over-all depth of the site vary. Petitioners presented credible evidence that a potential exists for the construction site to have a large quantity of water because of its location between two sources of surface water (the By-Pass Channel and Barge Canal), because of the makeup of the subsurface, and because of the depth of the construction. Hy Power credibly represents that if excessive groundwater is found, it can address the adverse impacts through its de-watering plan that would have to be filed with FERC and DEP. The technology exists to address the de-watering of the project. Such plans are routinely considered by DEP after a construction permit is issued and before de-watering occurs. There is very little evidence of sinkhole activity in the project area, and the construction activities are not expected to cause any sinkhole activity. NOISE POLLUTION Mr. Bitter expressed concerns that FERC would require the facility to install a very loud siren that would result in sudden noise adverse to the well-being of neighbors. Mr. Bitter is unfamiliar with FERC siren requirements at run-of the-river hydroelectric facilities. In contrast, Mr. Volkin, who has substantial experience in this area, testified that the only alarm device that would be required would be for the protection of the workers during construction. The purpose of the alarm is to warn persons below a dam spillway of a change in the volume of water being let out of the impoundment. In the case of a run-of-the-river facility, the volume is near constant, changing only gradually. Therefore, even if a warning siren had to be installed its use would be limited to significant changes in flow or testing. This would not constitute a nuisance. Further, the facility is located in the vicinity of the Crystal River Nuclear Power Plant which has its own warning sirens. It would be prudent to make any warning devices required for this structure significantly different from those at the nuclear plant and to limit their use. DAM SAFETY AND FERC REVIEW In reviewing whether Hy Power’s applications complied with the relevant permitting criteria, the DEP took into consideration the review of the facility already performed by FERC. FERC will also be responsible for reviewing the project as it is being constructed. Mr. Edwards also raised concerns about the structural stability of the By-Pass Dam itself. This has been a subject of concern by those responsible for the dam, and a survey of the structure was conducted in 1993, referred to as the Greiner Report. The Greiner Report identified specific maintenance problems that have been and are being addressed by the DEP. However, DEP’s maintenance plan does not address specifically the possibility that the weight of the dam over time has caused some shifting in the dam. Hy Power has only a few core borings and only one at the location of the generator. Hy Power is using the ACOE’s original borings, as confirmed by several new ones, to develop its preliminary plans. The DEP considered FERC and the ACOE as responsible agencies for determining the structural integrity of the dam. DEP has taken FERC’s review of this facility into consideration as part of DEP’s own permitting review. It is normal for DEP to rely on outside sources and agencies for assistance in determining compliance with DEP permitting criteria such as public health and safety, and it is reasonable for DEP to do so in this instance. Most states do not have the full capability to evaluate dam safety, and so they rely on FERC and ACOE. On April 21, 1997, the project received a conduit exemption from FERC. The application process is illustrated in Hy Power Exhibit 11. Hy Power submitted to DEP detailed information about the dam, the associated structures and the proposed project which had been reviewed by FERC and the ACOE, the two agencies in the United States who are responsible for dam structure design, control, and administration. Included in the package was the Greiner Report and Hy Power’s review of it. FERC evaluated the project, the Inglis By-Pass Dam structure, and the proximity of the project to the Dam in relation to structural impact, upstream and downstream impacts, water quality, and environmental issues. Mr. Edwards raised concerns regarding the ability of the limestone bedrock to sustain additional construction in the area of proposed construction. This is a material issue in the controversy which impacts several aspects of the proposed construction. Mr. Edwards pointed out that the barge canal channel was constructed with the use of explosives that caused a fracturing of limestone bedrock. He pointed out that the steel panels, which Hy Power proposes to drive into the bedrock to construct the water retention structure necessary to excavate the hole into which the turbine and powerhouse would be placed, will further fracture this bedrock. This creates two potential dangers. It could permit water to move under and around the bottoms of the panels, potentially scouring the loosened material from the base of the panels and making them unstable and subject to failure. It could weaken the entire southern wing of the existing spillway dam. Mr. Edwards opined that this could result in catastrophic failure of the dam or the coffer dam. Such a failure would cause major destruction and loss of life to those persons living and working in and along the lower Withlacoochee River. Hy Power presented rebuttal evidence that it could and would, if necessary, inject concrete into the limestone to stabilize it and avoid the concerns raised by Mr. Edwards. FERC specifically evaluated concerns raised by project opponents over the poor physical condition of the By-Pass Channel Spillway structures, relying particularly on the 1993 Greiner Report. FERC noted that the DEP had entered into a contract to correct any deficiencies listed in the Greiner Report, which "did not conclude that the deficiencies at the By-Pass Spillway threaten downstream life and property." The FERC review concluded that the dam was safe. To ensure safety, FERC is requiring that Hy Power do a complete stability analysis of the dam prior to any construction. Articles 301 and 302 of the FERC exemption ensure that all final drawings and specifications be submitted to FERC prior to construction, along with a supporting design report consistent with FERC’s Engineering Guidelines; that FERC can require changes to assure a safe and adequate project; and that Hy Power must also submit approved coffer dam construction drawings and specifications at least 30 days prior to starting construction. FERC has its own engineering staff who will go to the site and do their own analysis, along with the ACOE, of the dam and structures, prior to any construction commencing. This is a detailed design review evaluation so that the latest information on the dam will be made known immediately prior to construction, and will prevent any catastrophic event from happening. Under FERC procedures, FERC requires the applicant to obtain the DEP permits prior to requiring applicant to submit more detailed construction designs for FERC's consideration. These more detailed designs in turn will be subject to further review by DEP and FERC. It is assumed that Hy Power will comply with the post- permitting procedures and requirements, and will present complete, detailed construction drawings for FREC and DEP approval. Hy Power’s failure to complete the process would result in denial of a construction permit.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the DEP enter a Final Order that issues the two permits challenged in this proceedings, WRM Permit No. 38-237096-3.001 and MSSW Permit No. 38-0129249-002, subject to the conditions contained in the Intents to Issue in the respective WRM and MSSW Permits and as described in the Recommended Order. DONE AND ENTERED this 2nd day of March, 2000, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 2000. COPIES FURNISHED: Daniel H. Thompson, Esquire Berger Davis & Singerman 215 South Monroe Street, Suite 705 Tallahassee, Florida 32301 Andrew Zodrow, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 John S. Clardy, III, Esquire Crider Law Firm Plantation Point 521 West Fort Island Trail, Suite A Crystal River, Florida 34429 Teri Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Kathy Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Bernard M. Campbell Bessie H. Campbell 245 Palm Street Post Office Box 159 Inglis, Florida 34449 Sarah E. Berger Post Office Box 83 Inglis, Florida 34449
The Issue Whether the South Florida Water Management District’s (“District”) intended award of a contract for aerial spraying services, granular application services, and aerial transport services, to Coastal Air Services, Inc. (“Coastal”), is contrary to the District’s governing statutes, rules, policies, or the bid specifications; and, if so, whether the decision was clearly erroneous, contrary to competition, arbitrary, or capricious.
Findings Of Fact The Parties The District is an independent taxing authority created pursuant to section 373.069, Florida Statutes, with the authority to contract with private entities to maintain real property controlled by the District. See § 373.1401, Fla. Stat. HAI is a Florida corporation duly authorized to do business in the State of Florida with a business address of 1090 Airglades Boulevard in Clewiston, Florida. Coastal is a Florida corporation duly authorized to do business in the State of Florida with a business address of 7424 Coastal Drive in Panama City, Florida. The RFB On February 7, 2018, the District issued the RFB, soliciting bids for qualified respondents to provide the following: [F]urnish all labor, equipment, perform data entry and perform all operations for spraying of aquatic, ditchbank and invasive vegetation by helicopter and provide aerial flight services for site inspection and plant surveys. Both HAI and Coastal submitted timely bids, which the District deemed responsive and responsible under the terms of the RFB. The District deemed Coastal the lowest responsive and responsible bidder for aerial spraying, granular application, and aerial transport services. The District deemed HAI the lowest responsive and responsible bidder for spot spraying services. On May 11, 2018, the District posted its Notice of Intent to Award the respective contracts to Coastal and HAI. HAI challenges the award to Coastal because it is not a responsible bidder under the terms of the RFB. HAI’s challenge focuses on two items required to document the bidder’s responsibility to perform the requested services. First, the RFB requires the bidder to provide at least two helicopters certified pursuant to 14 CFR Part 133, Rotocraft External-Load Operations; and 14 CFR Part 137, Agricultural Aircraft Operations (Part 137 Certificate). Second, the RFB requires the bidder to demonstrate its ability to obtain required insurance coverage. Part 137 Certificate HAI contends that Coastal’s bid does not meet the responsibility provisions of the RFB because it did not include sufficient Part 137 Certificates for its subcontractor, HMC Helicopters (“HMC”). HAI contends the Part 137 Certificates are required to expressly state that aircraft are certified to dispense economic poisons. Petitioner’s argument fails for three reasons. First, the RFB does not require the bidder’s Part 137 Certificate to expressly endorse aircraft to dispense economic poisons.3/ Second, assuming the express endorsement was required, the requirement does not apply to HMC. The RFB defines the term “Bidder” and “Respondent” as “[a]ll contractors, consultants, organizations, firms or other entities submitting a Response to this RFB as a prime contractor.” (emphasis added). In its bid, Coastal is listed as the prime contractor, and HMC as a subcontractor. The RFB requires each Respondent to list at least two aircraft which are Part 133 and 137 certified. The requirement applies to Coastal as the primary contractor, not to its subcontractor. Coastal’s bid listed five aircraft with both Part 133 and 137 Certificates, actually exceeding the requirement for two such certified aircraft. Third, assuming an express endorsement for dispensing economic poisons was required, and that the requirement applied to HMC, HMC’s Part 137 Certificate documents HMC’s authority to dispense economic poisons. Pursuant to 14 CFR 137.3, “Agricultural aircraft operation” is defined as follows: [T]he operation of an aircraft for the purpose of (1) dispensing any economic poison, (2) dispensing any other substance intended for plant nourishment, soil treatment, propagation of plant life, or pest control, or (3) engaging in dispending activities directly affecting agriculture, horticulture, or forest preservation, but not including the dispensing of live insects. To obtain a Part 137 Certificate, the operator must pass a knowledge and skills test, which includes the safe handling of economic poisons and disposal of used containers for those poisons; the general effects of those poisons on plants, animals, and persons and precautions to be observed in using those poisons; as well as the primary symptoms of poisoning in persons, appropriate emergency measures in the case of poisoning, and the location of poison control centers. See 14 CFR § 137.19. However, if the operator applies for a Part 137 Certificate which prohibits dispensing of economic poisons, the applicant is not required to demonstrate the knowledge and skills listed above. See Id. HMCs’ certificates do not contain an express prohibition against dispensing economic poisons. The authorization for HMC’s aircraft to dispense economic poisons is inherent in its Part 137 Certificate. Coastal’s bid meets the solicitation requirement for at least two aircraft with Part 137 Certificates. Insurance Requirements The RFB requires each Respondent to “provide evidence of the ability to obtain appropriate insurance coverage.” Respondents may meet the insurability requirement by having their insurance agent either (1) complete and sign an insurance certificate which meets all of the requirements of Exhibit H to the RFB; or (2) issue a letter on the insurance agency’s letterhead stating that the Respondent qualifies for the required insurance coverage levels and that an insurance certificate meeting the District’s requirements will be submitted prior to the execution of the contract. In response to this requirement, Coastal submitted a letter from Sterlingrisk Aviation, dated March 6, 2018, stating, “All required coverage amounts are available to Coastal Air Service, Inc. to fulfill the requirements of this contract.” In the Re: line, the letter refers to the specific RFB at issue in this case. Coastal also submitted a certificate of insurance from Sterlingrisk Aviation demonstrating the levels of insurance coverage in effect at the time the bid was submitted, although the coverages are less than the amounts required under the RFB.4/ HAI takes issue with Coastal’s evidence of ability to obtain the required coverage because the letter from Sterlingrisk does not state “an insurance certificate reflecting the required coverage will be provided prior to the contract execution.” Based on the totality of the evidence, the undersigned infers that Sterlingrisk’s letter omits the language that a certificate “will be provided” prior to contract execution, because Sterlingrisk will issue an insurance certificate only when Coastal applies, and pays the premium, for the increased coverage limitations. The letter from Sterlingrisk substantially complies with the insurance requirements of the RFB, and constitutes competent, substantial evidence of Coastal’s ability to obtain the required insurance coverage. HAI introduced no evidence that Coastal obtained an economic advantage over HAI by failing to include language from its insurance agent that “an insurance certificate reflecting the required coverage will be provided prior to the contract execution.” Instead, HAI argued that by failing to enforce that provision of the RFB, the District cannot ensure the winning bidder will be responsible to undertake the contract. HAI argued that the District’s failure to adhere to this RFB requirement may create inefficiencies that “would result in the event that Coastal were unable to obtain the required insurance coverage” before execution of the contract. Coastal’s bid documents its eligibility for insurance coverage in the amounts required by the RFB. If Coastal does not provide said certificates, it will not be qualified for final execution or issuance of the contract.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Southwest Florida Water Management District enter a final order dismissing Helicopter Applicator, Inc.’s Petition. DONE AND ENTERED this 15th day of November, 2018, in Tallahassee, Leon County, Florida. S SUZANNE VAN WYK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of November, 2018.