Findings Of Fact During the month of March 1996, the Pinellas County School Board, pursuant to an advertised invitation for bids, (IFB), solicited bids for the construction of a new facility for John H. Sexton Elementary School (Sexton school). Each party submitting a bid was required to do so on a bid proposal form which was contained in the bid documents prepared by the project architect, Mr. Hoffman, and furnished to each prospective bidder who requested the bid package. One section of the bid proposal form related to "dewatering" potentially required at the construction site, and consistent with that potential two sentences were contained on the bid proposal form relating to dewatering of footings and of utilities, both of which provided for election by checking of an affirmative or a negative, and both of which had been pre-checked in the affirmative by the Board. It was the position of the Board that the pre- checked sentences as to dewatering on the bid proposal form constituted an acknowledgment by each bidder that that bidder's submittal included dewatering in the base bid. In addition to the check, the dewatering section also included blanks for the insertion by the bidder of figures representing lineal feet of header pipe and unit price per foot which figure would constitute a credit given by the bidder to the Board against the total bid price if dewatering were found not to be necessary, both as to footings and to utilities. Even further, the form also contained blanks to be filled in by the bidder for unit prices to be charged the Board in the event additional dewatering was required by virtue of the Board's later inclusion in the project of additional footings or utilities. Prior to the time for bid submittal, the Board conducted a meeting of all prospective bidders at which the project was explained and bidders given an opportunity to ask questions raised by the bid package. Johnson did not ask any questions regarding dewatering or that portion of the package relating thereto. Numerous bids were submitted in response to the proposal, including those from Johnson and Ellis. By stipulation at the hearing, the parties agreed that in all ways other than in that section of the bid proposal form for this project relating to dewatering, Johnson was and is a responsive and responsible bidder, as is Ellis. The bid proposals were opened by the Board at 2:00 PM on April 11, 1996 and the base bid prices on each proposal were read aloud to all in attendance by a Board representative. The project architect was present at the opening and tabulated and reviewed the bid proposals as opened. Johnson submitted the lowest base bid with a price of $7,965,000. The next lowest bid was that of Ellis, whose base bid price was $7,945,200. At the time of opening, no Board representative indicated anything was wrong with Johnson's bid Mr. Hoffman, the project architect, immediately noticed that Johnson had altered the Board's pre-checked bid proposal form by striking out the pre- checked "is" space regarding inclusion of dewatering in the base price of the two dewaterings, and making an X in each of the "is not" spaces. Mr. Hoffman considered that alteration by Johnson as a material alteration of the Board's solicitation which rendered Johnson's bid non-responsive. It must be noted that each change bears the initials, R. Y. Reza Yazdani is Johnson's president who initialed the changes and signed the bid proposal form for the company. In addition, Johnson also inserted a "0" in those spaces which dealt with amount of credit and cost of additional dewatering in the event additional work is required by the Board. In that regard, Hoffman opined that had Johnson not changed the check marks, but inserted the "0" figures as it did, the bid would have been responsive and Johnson would still have been lowest responsive bidder. The reason for this is that the bid form specifically notes that "the unit costs described in A & B above shall in no manner influence the School Board's selection of a firm to whom to award the Contract." The Board now recognizes that there is no part "B", as referenced in the proposal form. Since the "0's" would not influence the selection, use of an unmodified Board form, along with the lowest submitted base price would, in Hoffman's opinion, probably have meant that Johnson would have been awarded the contract. Johnson's representative, Mr. Mohme, who drafted the company proposal, specifically indicated he did not believe dewatering was a potential in this project. He recognized that such dewatering as was necessary was required by other provisions in the project specifications and he could not figure any way to recognize this and yet accurately reflect his belief that dewatering would not be necessary, other than to strike the pre-checked block and insert the check in the alternative block. He felt that by doing so, he was more accurately reflecting Johnson's bid. This reasoning is rather obscure. By letter dated April 12, 1996, written to the Board after the bids were opened, Mr. Mohme reiterated Johnson's position that dewatering is not necessary on this project, but further stated that if dewatering were to be necessary, Johnson would do so solely at its own risk and without any risk of additional cost to the Board. Bids may be clarified by a bidder, but such clarification must take place before the bids are opened. Bids may not be modified after bid opening. Before that letter was written, however, when the bids were opened and Mr. Hoffman observed what he considered was Johnson's alteration of the bid form, Hoffman consulted with a representative of the Board's purchasing department, Ms. Maas, who also reviewed Johnson's bid. Ms. Mass was of the opinion that Johnson may have attempted to qualify its bid, and she and Mr. Hoffman thereafter met with Mr. Rivas, the Board's director of facilities design and construction, to explain the problem. Mr. Rivas took the problem to two other Board personnel to see if there were some way Johnson's bid could be deemed responsive so that the Board could benefit by Johnson's low bid price. Within the context of those aforementioned discussions, Hoffman took the position that the alteration might leave the Board open to a possible change order and additional liability if dewatering were to be required and the Board had accepted Johnson's bid indicating that process was not included in the base price. Mr. Rivas, after consulting with the Board's attorney, also concluded that Johnson's alteration expressly excluded dewatering as an included factor and its exclusion constituted a serious and material deviation from the Board's solicitation. It was deemed material in that the deviation apparently gave Johnson a competitive advantage over other bidders who did not amend the form. This appears to be a valid conclusion and is adopted herein. The decision to recommend rejection of Johnson's bid and acceptance of Ellis's as the lowest responsive bid was ultimately reached by the Board's administrative staff. The Ellis bid was responsive to the solicitation whereas the determination was made that Johnson's was not responsive because of the alteration. It was not the actual act of alteration that caused that determination but rather the potential effect of the alteration. This was consistent with long standing Board policy not to accept a bid which does not conform to a bid solicitation and not to accept bids from bidders who alter the Board's bid proposal form or otherwise attempt to qualify their bids. It is the opinion of the Board personnel that such consistency in bidding procedure has resulted over time in more qualified bidders submitting bids for Board work which, in turn, has resulted in more competitive prices for the work let for bid. This is a reasonable policy. Mr. Gottschalk, Johnson's expert architect, who has designed schools for the Board, offered an alternative disposition to this dilemma. While admitting that Johnson's shifting of the risk of loss as a result of possible dewatering was a material matter, he suggested the Board could have disregarded the dewatering clause on every submittal and thereafter awarded the contract to Johnson, the lowest bidder, whose bid was responsive to the solicitation except for the dewatering provision. Recognizing this solution would have placed each bidder on an equal footing and allowed award to the lowest bidder at a substantial savings to the Board, he nonetheless also understood the decision made by Mr. Hoffman and the Board staff here and could not fault it. He agreed that reasonable men could differ on the issue of responsiveness here and how to deal with it. It is so found. After a review of the evidence submitted, including the testimony indicating the remoteness of the likelihood that extensive dewatering would be required, there appears to be no evidence that the Board, or its staff, acted dishonestly, fraudulently, illegally or arbitrarily in rejecting Johnson's bid on this project and recommending award to Ellis.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County School Board enter a final order denying and dismissing G. H. Johnson Construction Company's protest and awarding a contract for the construction of Sexton Elementary School to Ellis Construction Company, Inc. DONE and ENTERED this 8th day of May, 1996, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 96-1942BID To comply with the requirements of Section 120.59(2), Florida Statutes (1993), the following rulings are made on the parties' proposed findings of fact: Johnson's Proposed Findings of Fact. 1.-5. Accepted and incorporated herein. Accepted. Accepted but not a proper Finding of Fact. More a restatement of and comment on testimony. Rejected. Accepted but not a proper Findings of Fact. More a restatement of and comment on testimony. &11. Accepted. Accepted and incorporated herein. First sentence accepted as a literal statement of what appears in the specifications. Second and third sentences accepted but not probative of any material issue of fact. Accepted and incorporated herein. First sentence accepted. Balance not Finding of fact but argument. Ellis' Proposed Findings of Fact. 1.&2. Accepted and incorporated herein. 3.-6. Accepted. 7.-10. Accepted and incorporated herein. 11.-15. Accepted and incorporated herein. 16. Accepted but word "certain" is changed to read "likely." 17.-21. Accepted and incorporated herein. 22. Accepted and incorporated herein. 23.&24. Accepted. 25.&26. Accepted and incorporated herein. 27.-29. Accepted. Accepted and incorporated herein. Not relevant to any material issue of fact. COPIES FURNISHED: Jawdet I. Rubaii, Esquire Clearwater Executive Suites, No. 213 1345 South Missouri Avenue Clearwater, Florida 34616 John W. Bowen, Esquire Pinellas County School Board 301 4th Street S.W. Largo, Florida 34649-2942 E. A. Mills, Jr. Esquire Dale W. Vash, Esquire Fowler, White, Gillen, Boggs, Villareal and Banker, P.A. 501 East Kennedy Boulevard Post Office Box 1438 Tampa, Florida 33601 Pinellas County School Board 301 4th Avenue, S.W. Largo, Florida 34649-2942
Findings Of Fact This case concerns what is called a "turnkey lease." The program was developed by the State of Florida in 1971. It encompasses a situation whereby agencies seeking space for their operation may, after a specific need is determined that cannot be filled by existing adequate space, solicit competitive bids from developers for the provision of land and the construction of a building there sufficient to meet the agency's needs, for lease specifically to the agency requesting it. The Bureau of Property Management within DGS was given the initial responsibility to develop the guidelines, promulgate the rules, and seek statutory authority for such a program. The Bureau's current role is to work with agencies requesting this program. The agency certifies the need to the Bureau, in addition to the fact that there is no available existing space present. The Bureau then determines agency needs and gives the agency the authority to solicit the bids for the turnkey project. Once the bids have been solicited and the preproposal conferences have been held, the bids are then received, evaluated, and a recommendation for an award is forwarded by the agency to the Department of General Services. DGS reviews the supporting documents required by the provisions of the Florida Administrative Code and either concurs or does not concur in the recommendation. If DGS concurs, the submitting agency is notified and is permitted to then secure the lease. Once the lease has been entered into, it is then sent back to DGS for review and approval, as to the conditions, and thereafter the plans and specifications for the building are also referred to DGS for review and approval as to the quality and adequacy of the plans and specifications and code compliance. Section 255.249 and Section 255.25, Florida Statutes, sets forth the requirement for soliciting and awarding bids for lease space in an amount in excess of 2500 square feet. This provision requires that an award of this nature be made to the lowest and best bidder, and DGS subscribes to that standard in evaluating and determining whether or not it will concur with an agency's recommendation. In the instant case, DHRS advertised for bids for the construction of office space in Palatka, Florida for its District III facilities. Before seeking to solicit bids, District III staff conducted a search for other possible existing space within a five mile radius of the downtown area and located no adequate facilities. Thereafter, a certification of need was processed for a solicitation of proposals and approval was granted by DGS to follow through with the solicitation. A preproposal conference was advertised and held on October 14, 1983 and after review by those present at the conference, bid opening date was set for November 22, 1983. Thirty-two bid packages were distributed and twelve bidders submitted proposals. The public bid opening was held as scheduled at 2:00 P.M. on November 22, 1983, in Palatka, Florida by Robert E. Litza, Facilities Service Coordinator for DHRS District III. Of the bids submitted by the twelve bidders, the lowest bid was rejected because of the failure of the bidder to comply with the requirements of the bid package. Of the remaining eleven bids, the four lowest were evaluated with the understanding that additional high bids would be evaluated if the four lowest were found to be unacceptable. Among the four bids considered were bids of Chuck Bundschu, Inc.; Kenneth McGunn, the Intervenor (Mr. McGunn submitted five price schedules for his bid and of these only one was considered); Elizabethan Development, Inc.; and TSU. A recommendation by the evaluation committee which met at DHRS District III that Intervenor's bid be selected was forwarded to DGS in Tallahassee through the Director of DHRS's General Services in Tallahassee on December 22, 1983. The terms of the successful bid and the reasons for its being considered lowest and best are discussed below. The successful bid for the lease in question, lease number 590:8030, was, upon completion of the committee's evaluation, also evaluated by Mrs. Goodman in the Bureau of Property Management of DGS. She also considered the McGunn bid as the lowest and best of the eleven non-disqualified bids. In that regard, not only Mr. McGunn's bid but all of the twelve bids received were considered and reviewed not only at the local level but at DHRS and DGS Headquarters as well. In her evaluation of the proposal and the bids, Mrs. Goodman considered the documentation submitted by DHRS. This included a letter of recommendation supported by a synopsis of all proposals, the advertisements for bids, and any information pertinent to the site selection process. The letter from DHRS dated December 22, 1983, which recommended award of the lease to Mr. McGunn, included Mr. Litza's December 21, 1983 analysis and recommendation letter which, itself, was attached to McGunn's primary bid documents. Her analysis did not include a prior award recommendation and analysis from Mr. Litza, dated December 8, 1983. It also did not include the site plan, the floor plan for the proposed building, or a survey of the site, but these areas are considered to be within the discretion of the leasing agency. Their absence is not considered to be particularly significant. In her analysis, Mrs. Goodman found that Petitioner's bid was also responsive. However, comparing it with Mr. McGunn's bid, she and her staff found that the latter was the lowest bid submitted. The determing factor in her decision was cost. In determining that McGunn's bid was the lowest as to cost of all bids, Mrs. Goodman compared the average rate per square foot per year for each. This did not take into consideration proration of costs per year, but strictly the average over the fifteen years of the term of the lease (10 year basic plus 5 year option) . According to Mrs. Goodman, this same method of calculating cost has been used in every lease involving a turnkey situation and in fact in every lease since 1958 - as long as she has been with DGS. This particular method, admittedly, is not set forth in any rule promulgated by DGS. However, the agencies are instructed by DGS to advertise and bidders to bid on an average square foot basis, the basis utilized by Mrs. Goodman and her staff in analyzing the bids submitted. In that regard, the request for proposals does not, itself, indicate how the calculation of lowest cost would be made by DHRS and DGS but it does tell prospective bidders what information to submit. This procedure has been followed exclusively in situations like this for many years and many of the bidders have bid before using this same system. While Mrs. Goodman is not certain whether TSU has ever bid before, using this system, she does not consider it to be unfair because all bidders are considered on the same footing in an evaluation. They are notified of what information to submit and if they do so, their information will be considered along with all other bidders. Further, anyone who inquires as to the basis for evaluation will be given a straight and complete answer as to the method to be used. In the instant case, DHRS followed procedure for solicitation and evaluation utilized in the past and DGS followed its own policy in evaluating the submissions. In short, the primary consideration for DGS is the price factor and all other factors are considered to be within the expertise of the requesting agency. In Mrs. Goodman's opinion, based on the fact that she worked with the Florida Legislature on the development of the controlling statute, and helped develop the existing rule within DGS, that was the intent of the Legislature. Consequently since the statute requires award to the lowest and best bidder, it can be said that in this case the term "lowest" falls within the purview of both DHRS and DGS but "best" is solely within the purview of DHRS. Therefore, utilizing the lowest and best criteria and accepting the fact that the lowest bid may not be the best bid, the determination of "non-best" should be based on the reasonable "end objective" of the agency and need not be based on a criterion which is set forth in the bid proposal. In other words, it is not necessary for the agency to set forth the manner of evaluation it will use or the factors it will consider, according to Mrs. Goodman. With regard to the bid and evaluation committee process, Mr. Litza, the facilities manager for DHRS in Gainesville, was involved in putting together the bid package along with Mr. George Smith from Tallahassee, Litza's predecessor in the job in Gainesville. He worked with Mr. Smith in order to take advantage of Smith's experience in evaluating bids for leases. So far as he knew, the bid package contained minimum standards for all parts of the bid, and the package was, in fact, approved by officials in Tallahassee before being released. While no particular factors were identified to prospective bidders as being significant, Mr. Litza did conduct a bid conference for them prior to the date the bid was due and was available to answer any questions that prospective bidders might have. He did not receive any questions regarding the significance of any particular factor from any bidder. The bids were advertised and when received, were opened and read properly in accordance with the terms of the solicitation. When the bids were received and opened, it was seen that Mr. McGunn had submitted five different bids for the same project. Litza had not been confronted with this situation before and asked Mr. Smith what to do about it. Mr. Smith's reply was to put all five McGunn bids in with the rest and extract the lowest five of all bids. When this was done, Mr. McGunn was shown to have submitted two of the lowest five bids. In determining which were the lowest five bids, Mr. Litza utilized the average cost per square foot formula utilizing therein the entire 15,772 square feet authorized for the project. Once the five lowest bids were determined, Mr. Litza selected an evaluation committee made up of local Palatka DHRS supervisors except for the fiscal member, Mr. Foust, Mrs. Shinholster, Litza's secretary and Litza himself. He gave each of the members a score sheet with point values for each area. Each member filled out the form independently. Though he gave very little briefing to the evaluation committee, he admits that he did, in advance, tell each member that Mr. McGunn was the lowest bidder and should be awarded the highest points for criteria number 1, which related to cost. There were several irregularities in Mr. Litza's processing of the evaluation committee's results. For example, on the evaluation of the file conducted by member Sheryl Dollar, regarding criteria number 2, which relates to the conformity of space offered to the specific requirements contained in the invitation to bid (with a weight of 25 points), Mr. Litza admitted he lowered Mrs. Dollar's point award in that area from 35 to 25 without first checking with her to insure that his action would meet with her approval. While this is irregular, it is of little or no consequence since - the maximum number of points that could be given for that particular item was 25 and Mr. Litza's actions did not reduce that member's award to less than the maximum allowable. He contends that his action was based on what he considered to be a mistake on her part. In another apparent irregularity, Mr. Litza prepared a recommendation letter based on his and the other committee members' evaluation of the files to DHRS Headquarters in Tallahassee on December 8, 1983. In that letter, be indicated that McGunn would provide gas heat for the proposed building for free. Though McGunn had not specifically stated this, he implied it from the energy features paragraph in the Intervenor's bid. On the other hand, the bid by TSU contained an express comment offering to pay the utility charges. This specific provision was overlooked and omitted from the evaluation and report to Tallahassee by Litza, who contends that this omission was merely an oversight. There are other discrepancies as well. In his testimony, Mr. Litza indicated Mr. McGunn proposed to build one building but his letter of December 8th and that of December 21, 1984, both reflect two buildings. Here again, Mr. Litza explains this as the result of his being confused. Nonetheless, this erroneous information was referred to Mrs. Goodman at DGS. This is significant in that at the evaluation committee meeting, when the forms were given out, several of the members expressed a preference for a two-building complex. After the award, Mr. Litza secured agreement from McGunn to build two buildings. Mr. Litza admits that much of this was done in an attempt to insure that McGunn, as the low bidder, got the award. Mr. Litza equated the lowest bid with the best and had Petitioner been the low bidder, he contends he would have done the same thing. In most areas, he would not, however, have given Petitioner's four-building concept a high score because of the increased heat and air requirements of four buildings. Mr. Litza also downgraded Petitioner on that bid criteria which relates to the proximity of offered space to the clients to be served because Petitioner's site, he contends, was too close to the clients to be served. In this case, a housing project for low income families which make up much of the clientele to be served by DHRS, was located across the street from the proposed site offered by the Petitioner. Mr. Litza contends that he was thinking of the potential damage to the building because of increased activity by virtue of the facility being so close. There were other questionable areas in Mr. Litza's testimony. For example, he testified that though Petitioner provided 15 more parking spaces than Intervenor, this would result in mud being tracked in from the adjacent dirt road 200 feet away in greater quantities than in Intervenor's proposal. He also considered positively that the Intervenor's proposed site was closer to a restaurant than that of the Petitioner. Though it was recommended by DHRS Headquarters in Tallahassee that only two of the committee members be from the Palatka office, Mr. Litza disregarded that advice because, he contends, there was a morale factor in that office and the people assigned there wanted to have a part in this decision. Because of this, he allowed Ms. Stouffenberg to put five extra members of her staff on the committee. Nonetheless, the evaluation committee serves only in an advisory capacity. Its recommendation is no more than an advisory opinion. The ultimate decision as to which of the bidders should be awarded the contract is made at DHRS Headquarters in Tallahassee. Ms. Shinholster, a Clerk IV in the DHRS Gainesville office, who works as a secretary to Mr. Litza and several others, was advised she would be on the committee for the evaluation at the same time she was given the bid file. She did not get an opportunity to meet with other committee members to talk about the standards to be used, nor was she given any standards by which to evaluate the files. All she was told by Mr. Litza was that McGunn was the lowest bidder. She cannot explain how she accorded points on her evaluation sheets except that she gave the low bidder the highest number of points. Mr. George Smith, a Senior Analyst with DHRS in Tallahassee, relied on Mr. Litza's input when he made his recommendation to his superiors that the award should be made to McGunn. He also formulated his own opinion, based on his own analysis of the bids. He resolved any dispute regarding cost in favor of Mr. McGunn on the basis of the average rental, and regarding space, in favor of McGunn on the basis of the number of buildings. Dr. Perry, an economist with the University of North Florida, testified to the Federal Government's policy regarding the desirability of using the present value of money methodology and the determination of an acceptable discount rate or index in calculating the actual cost of the bids. Both experts, Dr. Perry and Dr. Scott, who testified for DGS, agree that the present value methodology is valid and presents a more accurate analysis of cost than the average rental cost methodology which does not utilize this theory. The major difference between the two was primarily in the percentage to be utilized in applying the discount rate. Whereas Dr. Perry adopted the Federal policy and suggested a 10 percent discount rate, Dr. Scott testified that a more viable percentage rate in November, 1983, at the time the award was to be made, would have been 3.3 percent. If the 10 percent rate were used, then the Petitioner's bid would be the lowest of all submitted. On the other hand, if the 3.3 percent rate were used, Intervenor's bid would be the lowest. If a different discount rate, that of 5.7 percent were to he used, the bid of Elizabethan Development Corporation would be low. It is at about the 6 percent point and above that Petitioner's bid becomes the lowest. Nonetheless, the State has not adopted the present value of money theory and the policy followed by the State is not to consider that methodology in analyzing costs. State policy is to use only the average rental methodology. There are no written instructions (rules) on evaluating bids for leases of this nature. Oral instructions given by DGS to each agency are that the average rate per square foot is to be computed using, if the square footage is constant, for each year of the lease, the basic square footage requested, multiplied by the rental rate proposed for each year of the basic lease, divided by the number of years. If the square footage is not constant in every year of the lease, evaluators are directed to apply the rate per square foot proposed in each year to the square footage to be utilized in that year, total up the annual rentals, total up the square footage involved, and divide to arrive at the average rate per square foot per year. Utilizing one or the other of those two methods in evaluating both the McGunn and the TSU bids, it becomes clear that the McGunn bid results in an average of $8.86 cost per square foot per year and the TSU bid an average of $9.58 per square foot per year. Recalculation of DHRS' evaluation by DGS showed the DHRS' figures as stated above were correctly arrived at. This procedure is followed on all turnkey and non-turnkey leases in the State of Florida. The reason the State uses this process instead of the present value of money process is because it is easy. DGS statistics indicate that most landlords in the approximately $32,000,000 worth of leases presently existing with the State are "Mom and Pop" landlords. These people are not normally trained lease evaluators. By using the straight average rental rate method, there are no arbitrary variables. It has always worked because people can understand it and all agencies which lease property in the State of Florida follow this procedure. Also, this procedure does not require computer-based calculations, and it does not require economists to work with it. Both latter reasons are amplifications of the first. In Mrs. Goodman's estimation, if the present value of money system were to be adopted, her division would have to hire at least two $30,000 per year economists and buy an in-house computer to operate the system. This additional cost, she believes, would far outweigh the paper savings to be realized by utilizing the present value of money system. As of the hearing date, considering all the factors, in Mrs. Goodman's opinion, DGS would nonetheless still recommend Mr. McGunn's bid as the lowest and best bid.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore RECOMMENDED that DHRS lease Number 590:8030 be awarded to Kenneth R. McGunn. RECOMMENDED this 5th day of September, 1984, in Tallahassee, Leon County, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1984. COPIES FURNISHED: Donald E. Holmes, Esquire William E. Townsend, Jr., Esquire Post Office Drawer D Palatka, Florida 32078-0019 James A. Sawyer, Jr., Esquire District III Legal Counsel Department of Health and Rehabilitative Services 1000 Northeast 16th Avenue Gainesville, Florida 32609 Stephen J. Kubik, Esquire Department of General Services Room 452, Larson Building Tallahassee, Florida 32301 H. Allen Poll, Esquire 112 South Main Street Gainesville, Florida 32601 Linda C. McGurn, Esquire 1717 Northeast 9th Avenue Gainesville, Florida 32301 David H. Pingree, Secretary Department of Health and Rehabilitative Services 1321 Winewood Boulevard Tallahassee, Florida 32301 Ronald W. Thomas, Executive Director Department of General Services 115 Larson Building Tallahassee, Florida 32301
The Issue At issue in this proceeding is whether the decision of respondent, Department of Transportation (Department), to award the subject bid to intervenor, The Walsh Group, Ltd., Inc. and Subsidiaries d/b/a Archer-Western Contractors, Ltd. (Archer-Western), comported with the essential requirements of law.
Findings Of Fact The bid process In June 1995, the Department of Transportation (Department) issued an invitation to bid (ITB), State Project Number 93280-3504, Contract Number E- 4866, for the repair and rehabilitation of the Royal Park Bridge, a two span, four leaf bascule bridge, which spans the Intercoastal Waterway and connects the town of Palm Beach to West Palm Beach, Palm Beach County, Florida. Prospective bidders were contacted through a bid solicitation notice, which was sent to prequalified contractors, and interested firms ordered bid packages, which included plans and specifications. The subject project was experimental, and was an effort to identify the most cost-effective means of repainting bridges that contained, inter alia, lead-based paint, a hazardous material, while minimizing exposure of workers and the public as well as the environment (the Intercoastal Waterway), to the hazardous materials. The technical specifications or capabilities of the equipment to be used to abrade and prepare the bridge surfaces for repainting, keeping in mind the objective of the project, were developed by the Department's consultant, Kenneth C. Clear, and are noted in section 560, subsection 1.01.1, of the specifications, discussed infra. At the time, Mr. Clear was aware of one system, the "Cavi-Tech" or "Cavi-Blast" method, a proprietary system devised by Cavi-Tech, Inc., that could comply with the technical specifications, but did not know of any other company that had a similar process. Consequently, in drafting the technical requirements at issue in this bid challenge, discussed more fully infra, he identified the "Cavi-Blast" system of Cavi-Tech, Inc., as capable of satisfying the technical requirements, and further provided, at the bidder's election, for the use of alternative equipment if it could be shown to meet the surface preparations standards described in the ITB. Pertinent to this case, Section 560 of the specifications, entitled Repainting Exposed Steel, at page 560-1 of the ITB, specified the following technical requirements for surface preparation equipment: Surface Preparation Equipment Surfaces shall be abraded and prepared for recoating using an energy enhanced water jet generated by equipment capable of sustained operation at pressures in excess of 17,000 psi. Nozzles shall operate using resonation and cavitation technology. Production rates shall be at least 600 square feet per machine and production shift in the case of full coating removal (CB-4 per section 1.2), and 1,500 square feet per machine and production shift for sweep- off blasts which remove all oil, grease, dirt, loose paint, loose rust, rust scale and loose mill scale, and profile the remaining paint (CB-1 per section 1.2). The equipment shall include closed-loop water handling and filtration systems capable of repeated reuse of blast water and on-site treatment of the water upon completion such that it is rendered non-hazardous. Abrasives, steel shot and/or chemical strippers shall NOT be used. The surface preparation equipment shall be capable of achieving the surface preparation standards described in section 1.2, and document ation of its successful use on at lest 10 similar bridge or industrial structures totaling at least 250,000 square feet shall be submitted with the bid. Additionally, detailed project documentation and air monitoring historical data from at least 5 projects in which paint containing a lead primer was completely removed without the use of negative pressure enclosures, shall be submitted with the bid. These data shall show conclusively that, on each of the projects, the lead exposure to individuals WITHOUT breathing apparatus located 5-feet and further from the water jet nozzle was less than the OSHA action level (i.e. the air qualified as non-hazardous, breathable air in accordance with Code of Federal Regulations 29 CFR 1926.62 "Lead") when the equipment was operated at full capacity for at least 8-hours. The Cavi-Tech, Inc., Inc. (2108 Moon Station Drive, Kennesaw, Georgia 30144; phone Number 404-424-4015; fax Number : 404-424-4009) "Cavi-Blast" system meets the above requirements. The ITB package did not require, apart from any implications that may be drawn from the foregoing provisions, that the bidder specify the type of surface preparation equipment it proposed to use, and no form was included with the bid package on which such election could be denoted. The bid package did include, however, a standard proposal to be executed by the bidder, which bound the bidder "to perform all necessary work, as provided for in the contract, and if awarded the Contractor [Bidder] to execute the contract within 20 calendar days after the date on which the notice of award has been given." The ITB further required a proposal guarantee, payable to the Department, of not less than five percent of the total actual bid, "which guarantee is to be forfeited as liquidated damages if . . . the Proposal is accepted [and] the Bidder . . . fail[s] to execute the attached Contract under the conditions of this proposal. " On August 17, 1995, after the pre-bid conference, the Department issued Addendum Number 1 to the ITB, which included the following clarification as to the painting specifications for the project: Surface preparation equipment requirements are specified in Section 1.01 of the painting specifications. Cavi-Tech, Inc. is indicated as a company having equipment and experience meeting the requirements of this specification section. Other companies meeting the requirements of Section 1.01 can bid on this project. In response to the ITB, the Department received five bids for the project. The lowest bid was submitted by Archer-Western, $2,868,816.35, and the second lowest bid was submitted by Coastal, $2,930,461.68. The three other firms that bid on the project were PCL Civil Contracts, Inc. (PLC), with a bid of $2,943,370.20, Gilbert Southern Corp. (Gilbert), with a bid of $2,967,928.10, and M & J Construction Co. of Pinellas County (M & J), with a bid of $3,274,867.17. The bid price proposal submitted by each bidder contained various items which were tallied to derive the total amount bid. Item Number A560 1 was for painting structural steel, and Archer-Western listed a price of $425,300, Coastal a price of $500,000, PCL a price of $350,000, Gilbert a price of $450,000, and M & J a price of $575,348.45. Pertinent to this case, while Archer-Western did secure a quotation from Cavi-Tech, Inc., for Cavi-Blast and coating services, as well as historical data regarding its use, it did not include such documentation with its bid. Consequently, the bid submitted by Archer-Western, as well as the bid of PCL, contained no information in response to subsection 1.01.3, regarding surface preparation equipment. Contrasted with those bids, Coastal, in what it perceived as the appropriate response to subsection 1.01.3, included information from Cavi-Tech, Inc., on the Cavi-Blast system. Gilbert and M & J likewise included documentation on the Cavi-Blast system. The Department, following its evaluation, deemed the five bids responsive, and on October 4, 1995, posted notice of its intent to award the contract to Archer-Western. Coastal timely protested the proposed award (DOAH Case No. 95-5702BID). On October 9, 1995, the Department notified all bidders that it was rescinding its notice of intended award and proposed to reject all bids. Coastal timely protested such decision (DOAH Case No. 95-5703BID).3 Finally, on October 24, 1995, the Department, following reconsideration of its position, resolved to rescind its rejection of all bids and, consistent with its initial decision, award the contract to Archer-Western. Coastal timely protested such award (DOAH Case No. 95-5701BID). The bid protest Here, Coastal contends that Archer-Western's proposal (bid) was not responsive to the ITB because it did not include documentation in response to subsection 1.01.3 of the ITB. By such failure, Coastal suggests Archer-Western failed to commit to using the Cavi-Blast system or identify an alternative system it would use and, therefore, its bid was at material variance from the ITB. That variance, Coastal avers, accorded Archer-Western the opportunity to reevaluate its bid, after bid opening, and then decide whether to adhere to is bid or refuse to abide its bid without penalty due to its non-responsiveness. Contrasted with Coastal's perception of subsection 1.01.3, the Department views that subsection, when read in pari materia with subsections 1.01.1 through 1.01.4, as only requiring documentations when the bidder proposes to use surface preparation equipment other than the Cavi-Blast system. Indeed, the Department observes, it would be superfluous to include documentation demonstrating that the Cavi-Blast system was capable of achieving the surface preparation standards when subsection 1.01.4 specifically states that the Cavi- Blast system meets requirements. Accordingly, where, as here, the bidder does not provide any documentation in response to subsection 1.01.3, the Department contends it may be fairly implied, based on the bidder's agreement in the proposal "to perform all necessary work, as provided for in the contract," that it has proposed to use, and is bound to use, the Cavi-Blast system. Consequently, the Archer-Western bid was, in the Department's opinion, responsive to the ITB. Reading the provisions of subsections 1.01.1 through 1.01.4 in para materia, it must be concluded that the Department's conclusion in this case is supported by logic, and that its decision to award the contract to Archer- Western did not depart from the essential requirements of law.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered dismissing Coastal's protests and, more particularly, its protest of the award of the subject bid to Archer- Western. DONE AND ENTERED this 26th day of February 1996 in Tallahassee, Leon County, Florida. WILLIAM J. KENDRICK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of February 1996.
The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.
The Issue Whether the Respondent, School Board of Broward County, Florida (Respondent or Board), may reject all bids as proposed for Bid No. 2002-02-FC, Group A1, or whether such action is illegal, arbitrary, dishonest, or fraudulent.
Findings Of Fact The Respondent is the entity charged with the responsibility of governing the public schools within the Broward County School District. As such, the acquisition of school properties and attendant improvements fall within the Board's legal authority. These cases involve the procurement of relocatable buildings suitable for classroom purposes. Pursuant to its authority, on or about December 27, 2002, the Respondent issued a bid that is the subject matter of the instant challenge. The bid, identified in this record as Bid 2002-02-FC, sought proposals for the procurement of district-wide relocatable buildings. In a prior time these buildings were known as "portable classrooms" or "portables." In the post-Hurricane Andrew world, these structures are now pre-engineered and constructed of concrete or steel (or a hybrid of both) and must be, by design, capable of being relocated to various sites. The Petitioners, Royal and Padula jointly, and the Intervenor, James B. Pirtle Construction Company, Inc. (Pirtle or Intervenor), design, construct, and install such structures. In these cases the bid sought several distinct proposals. First, the project sought vendors who would provide and deliver concrete relocatable buildings (Group A1). Group A2 (not at issue in this proceeding) sought steel relocatable buildings. Group B (also not at issue in the instant case) sought site adaptation prices for landscaping, lighted covered walkways, steps, ramps, and other engineering incidental to the installation of the buildings. The advertisement for the bid carried the same generic information as to all groups. The bid documents also contained many terms that were applicable to all groups. Pertinent to the issues of these cases are the following excerpts from the bid document (Joint Exhibit 2). The order of the excerpts should not suggest any significance. The excerpts are listed in this manner solely for convenience sake: BASIS OF AWARD In order to meet the needs of the school system . . . each Award will be . . . up to three responsive and responsible bidders meeting specifications, terms and conditions. Individual projects will be issued . . . based upon lowest cost among one or more bidders per project as determined by the project manager. Therefore, it is necessary to bid on every item in the group, and all items in the group must meet specifications in order to have the bid considered for award. Unit prices must be stated in the space provided on Document 00410 Bid Form. SBBC [the Respondent] reserves the right to procure goods from the second and third lowest bidders if: a) the lowest bidder cannot comply with delivery requirements or specifications; b) the lowest bidder is not in compliance with delivery requirements or specifications on current or previous orders; c) in cases of emergency; d) work may be issued to multiple contractors if in the opinion of The School Board of Broward County, Florida or its staff the work cannot be completed by a single contractor in the specified time such as a Summer, Winter or Spring Break or if it is in the best interest of SBBC to do so regardless of reason. ARTICLE 4 BIDDING PROCEDURES 4.01 FORM AND STYLE OF BIDS A. Bids shall be submitted on forms identical to Document 00410, Bid Form, and other standard forms included with the Bidding Documents. The following documents are required to be submitted with the Bid: * * * SIGNED SEALED ARCHITECTURAL AND ENGINEERING DESIGN DRAWINGS OF THE STRUCTURES TO BE PROVIDED (FOR RELOCATABLE BUILDINGS BID ONLY) 5.03 REJECTION OF BIDS AND IRREGULAR PROPOSALS * * * The Owner shall have the right to reject any or all Bids, reject a Bid not accompanied by a required bid security, good faith deposit, or by other data required by the Bid Documents, or reject a Bid which is in any way incomplete, irregular or otherwise not Responsive. The Owner may waive any formality in the bid requirements and award or not award the contract in the best interests of The School Board of Broward County, Florida. (Emphasis in original not shown) In addition to the foregoing, the bid documents contained detailed and specific design criteria that set forth information such as the slope of roofs, the roof spans, the mechanical systems, ventilation, plumbing, windows, and stoops. These design criteria covered hundreds of topics and encompassed virtually every facet of the structures. To review each bid proposal as to whether each design specification was met would require countless man-hours. The issue of how to review the bid proposals was not adequately anticipated by the Respondent. From the outset the bid document evolved from unusual circumstances. Whether the bid document was intended to be a request for proposals (RFP) or an invitation to bid (ITB) was a primary confusion among the Board's staff. If the proposals were to be deemed responsive or not and then ranked solely on price (thus making the bid process more like an ITB) how could staff effectively determine the threshold question of responsiveness? If the proposals were to be ranked based upon a point or qualitative approach (more like an RFP) where were the criteria by which to score the proposals? In fact, there were no objective criteria disclosed in the bid document by which a proposal could be evaluated. More curious is that no bidder brought this lack of evaluation criteria to the Board's attention during the mandatory bidder's conference. Moreover, no one challenged the bid specifications. Presumably, the bidders believed it was an "all or nothing" award. That is, if they were the lowest responsive bidder, they would receive the award. The question of who would be responsive and how that decision would be resolved did not come to light until after the bids had been opened. At the mandatory bidders' conference conducted on January 14, 2003, the bidders posed questions in the form of requests for information. In response, the Respondent issued six addenda intended to cover the questions posed. None of the responses addressed how the bid proposals would be evaluated. If anything, Addendum No. 3 added to confusion related to what documents must be submitted with the bid proposal. More specifically, Addendum No. 3 provided, in pertinent part: [Addendum 3, question and response to inquiry] 9. Can schematics be submitted with the bid instead of the signed and sealed architectural and engineering design drawings of the structures that are requested in Document Article 4.01.A.6? Response: Signed and Sealed Architectural/Structural Drawings are required to be submitted with the Bid. The Requirement for Mechanical and Electrical signed and sealed drawing is waived, however all engineering associated with the Relocatable Buildings will require engineer of record signed and sealed drawings and calculations prior to issuance of building permit DRC review. Nevertheless, when the bid proposals were opened on March 4, 2003, the Petitioners and the Intervenor were found to be the three lowest bidders. If responsive, the Intervenor would be considered the lowest bidder with the Petitioners being considered alternate vendors for the procurement. Unsatisfied with the preliminary determination that the Intervenor was the lowest bidder, the Petitioners timely challenged the bid award. The Petitioners maintained that the Intervenor had not timely provided sealed design drawings as required by the bid document. Petitioners argued that the Intervenor had attempted to impermissibly amend their proposal by late-filing a set of structural drawings for the bid. Thus the initial bid protest sought to determine what design drawings were required by the bid and whether the Intervenor had timely supplied such drawings. The Petitioners contended that the Intervenor's submittal should be rejected as non-responsive to the bid. Whether they had complied with the full dictates of the bid requirements was potentially at issue as well. While the initial bid protest was referred to the Division of Administrative Hearings and scheduled for formal hearing, the parties continued to attempt to resolve the issues. It was apparent that the bidders had not submitted identical proposals. How the proposed products had been compared and evaluated was difficult to determine. From the Respondent's committee members came the disclosure that the decision of determining whether the bidders had complied with the bid ultimately came from three fashioned questions. If the structure proposed was pre- engineered, relocatable to various sites, and suitable for educational purposes, the entry was deemed responsive. Based upon this assessment the Petitioners and the Intervenor were deemed responsive and their bids ranked based upon price. This approach did nothing to discern if the designs were comparable in quality, if they met the bid design criteria, or if the drawings were even sufficient to comply with the dictates of the bid. The first posting of the bid award for Group A1 was entered March 18, 2003. On March 21, 2003, the Petitioners timely filed their notices of intent to protest the award of Group A1 to the Intervenor. Thereafter they timely filed the petitions to protest the award and the initial protest was forwarded to the Division of Administrative Hearings. The protests did not encompass Group A2 or Group B. No bidder protested the proposed awards for Group A2 or Group B. In fact, the Respondent went forward on those procurements and awarded contracts for those groups on April 1, 2003. The Respondent did not award the contract award for the Group at issue in this proceeding. It must be noted that the instant procurement is not the Board's first experience with the procurement of concrete relocatable classrooms. In fact, the Board has purchased similar structures through a procurement contract that the Palm Beach County School Board holds with its vendors. One of the Respondent's concerns when the instant bids were reviewed was why the cost per unit for the bids in this case was higher than the Palm Beach County amount. As it turned out, the installation economy of multiple units at one site directly impacts the cost of the relocatable structures. Royal confirmed this information after the bids had been opened. When the Respondent's staff met with its counsel in preparation for the initial bid dispute (before the Board elected to reject all bids) the cost of the bid, the lack of full evaluation of the bidders' proposals, and the issues of the first protest were openly discussed. By that time any irregularities with the bid documents could not be repaired as to the contracts already awarded, but as to the instant matter the Respondent could revisit the circumstances and determine its best course. As a result of that reassessment, the Respondent elected to reject all bids regarding this group and attempt to re-bid the procurement with more certain terms. To that end on May 9, 2003, the Respondent issued a revised bid decision that provided in pertinent part: The Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on June 3, 2003, reject all bids received for Group A1 and authorize revising the bidding documents and re-bidding. The rejection of all bids received for Group A1 is made due to serious flaws and ambiguities contained in Document 00200 4.01.A-6 as modified by Addendum No. 3. The Division intends to revise the bidding documents to delete the requirements that bidders submit plans with the bids; include ranges of unit quantities within the bid form; include one or more additional types of construction of the classroom buildings including a composite concrete/steel structure; and incorporate within the new Invitation to Bid all revised terms and conditions that were released through addenda in this procurement. The Petitioners timely filed protests regarding this new decision by the Board and the instant action ensued. By issuing the revised decision to reject all bids the Respondent intended to resolve all issues and to cure the perceived problem with the lack of consistent evaluation of the bidders' proposals. More specifically, the Respondent would be able to assure that the project design could comport with the specifications sought; specify whether architectural or engineering drawings were required and when (it was hoped that the confusion over "architect" vs. "engineer" could be eliminated); and obtain a substantial discount based upon economies from multi-unit purchases for a single site. None of the objectives sought were pre-textual or contrived. Additionally, by avoiding any process that would require a detailed reviewed of the bidders' proposals, countless man- hours could be saved.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a Final Order affirming the decision to reject all bids in this matter. DONE AND ENTERED this 20th day of November 2003 in Tallahassee, Leon County, Florida. S ___________________________________ D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of November 2003. COPIES FURNISHED: Dr. Franklin L. Till, Jr. Superintendent Broward County School Board 600 Southeast Third Avenue Fort Lauderdale, Florida 33301-3125 Daniel J. Woodring, General Counsel Department of Education 325 West Gaines Street 1244 Turlington Building Tallahassee, Florida 32399-0400 Usher Larry Brown, Esquire Brown, Salzman, Weiss & Garganese, P.A. 225 East Robinson Street, Suite 660 Orlando, Florida 32801 Steven L. Schwarzberg, Esquire Schwarzberg & Associates Esperante, Suite 210 222 Lakeview Avenue West Palm Beach, Florida 33401 Thomas R. Shahady, Esquire Adorno & Yoss, P.A. 350 East Las Olas Boulevard, Suite 1700 Fort Lauderdale, Florida 33301 Robert Paul Vignola, Esquire Broward County School Board C. Wright Administrative Building 600 Southeast Third Avenue, 11th Floor Fort Lauderdale, Florida 33301
The Issue The issue in this case is whether the bid specifications, together with other applicable authority, require that a bid, in order to be responsive, contain any written list of subcontractors.
Findings Of Fact On September 26, 1989, Respondent issued a document entitled, Specifications for Replacement of Air Conditioning, West Orange High School, Winter Garden, Florida, Engineers Project No. 89-016. As amended by three addenda, the above-described specifications shall be referred to as the "ITB." Respondent duly advertised for bids ore September 26, October 3, and October 10, 1989. The advertisement did not state that Respondent reserved the right to waive minor irregularities. In response to the ITB, Florida Mechanical, Inc. ("FMI") and B & I Contractors, Inc. ("B & I") timely submitted bids. For the base work and alternate 1, which Respondent ultimately decided to select, FMI bid $1,439,000, B & I bid $1,438,000, and a third bidder, S. I. Goldman, Company bid $1,621,000. These bids are recorded on a Bid Tabulation Sheet prepared by the engineer retained by Respondent for the project. The Bid Tabulation Sheet contains eight columns. Four columns record bid amounts for the base work and various alternates. The remaining columns are entitled, "Bidder," "Bid Bond," "Addenda," and "Subs." Each of the three bidders were named in one of the rows beneath the "Bidder," column. Each bidder had one "X" in its "Bid Bond" column and three "X"s in its "Addenda" column. However, only FMI and S. I. Goldman Company had "X"'s in their "Subs" columns. By resolution adopted on November 29, 1989, Respondent directed that all bids were rejected and that the Superintendent would correct any ambiguities and uncertainties in the ITB and solicit new bids. The resolution noted that Respondents staff had recommended that, if any bid were accepted, it should be that of B & I. However, [FMI] submitted with its bid a list of Major Sub-contractors of the form displayed in the [ITB], and B & I did not submit wish its aid a list of Major Sub-contractors[.] The resolution concluded that Respondent based on advice of staff and counsel, found that the [ITB is) ambiguous and/or uncertain as to whether or not a bidder must submit along with his bid a list of Major Sub-contractors, (b) that because of such ambiguity and/or uncertainty, it would be unfair and/or improper for [Respondent] to accept either of the bids received by it, and (c) that as a result thereof [Respondent] should reject all bids received by it for ,the Project and should solicit new bids for the Project as soon as is reasonably feasible after correction by [Respondents] staff of any ambiguity and uncertainty as aforesaid in the [ITB]. FMI and B & I each timely filed a notice of intent to protest and formal written protest of Respondent's decision to reject each company's respective bid. S. I. Goldman did not protest the decision and is not a party to the subject case. At a meeting on December 12, 1989, Respondent elected to refer the bid protests to the Division of Administrative Hearings for a formal hearing., At the beginning of the hearing, the parties filed a written stipulation, which stated that the only issue for determination was which Petitioner should be awarded the contract and not whether Respondent should seek further bids or award the contract to another bidder. The stipulation also stated that the Petitioners and Respondent agreed to abide by the recommendation of the hearing officer. At the hearing, the parties further stipulated that the sole issue for determination is whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. In addition, the parties stipulated that both Petitioners had standing and the protests were timely and sufficient. The ITB requires that each bidder familiarize itself with all federal, state, and "Local Laws, ordinances, rules, and regulations that in any manner affect the work." Under the section entitled, "Preparation and Submission of Bids," the ITB states: "Each bidder shall use the Bid Form that is inserted herein, and may copy or reproduce the form on this own letterhead." Among other requirements, the ITB requires two bonds. The first is a "bid guarantee" of at, least five percent of the amount of the bid. The form of this guarantee may be cash or a Bid Bond." The other bond described in the ITB a 100% public construction bond. The surety on this bond must have been admitted to do business in Florida, must have been in business and have a record of successful continuous operation for at least five years, and must have at least a Bests Financial Rating of "Class VI" and a Bests Policyholder Ration of "A." The Bid Form contained in the ITB is two pages. Among other things, the Bid Form requires that the bidder receiving written notice of acceptance of its bid must provide the prescribed payment and performance bond and execute the contract within ten days after notification. The next document in the ITB is a single page entitled, "Form of Bid Bond." The provisions on this page identify the A.I.A. document to use and state that the Bid Bond "shall be submitted with the Bid Proposal Form." The next document in the ITB is a single page entitled, "List of Major Subcontractors." The List of Major Subcontractors states: Bidders shall list all major subcontractors that will be used if a contract is awarded. Additionally, bidders shall identify in the appropriate box whether or not that trade specialty is minority owned. Another paragraph defines minority ownership. The remainder of the form consists of ten rows for the "bidder" and nine major subcontractors, such as concrete, electrical, HVAC, and controls, and blanks where the bidder can indicate which of these entities are minority owned. The next document in the ITB is the Owner-Contractor Agreement, which is followed by tie Form of Construction Bond, General Conditions, and Supplementary General Conditions. Section 7.11 of the Supplementary General Conditions establishes certain requirements to be performed after the submission of bids. This section provides: Pre-Award Submittals: Before the Contract is awarded the apparent low bidder shall provide the following information to the owner. A copy of the Contractors current State of Florida General Contractor's or Mechanical Contractors License. Pre-Construction Meeting. After the Notice to Proceed and within eight (8) business days of the Owner [sic], the Contractor shall meet with the Owner, Engineer and Subcontractors that the Owner may designate... The Contractor shall provide the following to the Owner. * * * 2. A written list of all Subcontractors, material men and suppliers with such information as requested by the Owner or Engineer. * * * The remaining documents in the ITB are the technical specifications for the job. The three addenda supply additional technical information not relevant to this case. Respondent has promulgated rules with respect to the bidding process ("Rules"). The ITB does not refer to the Rules, which define and use many terms that are found in the ITB. For instance, Rule 1.1.25 defines the phrases, "Performance and Payment Bond," which is the same phrase used in the Bid Form in the ITB. The Rules define several other capitalized terms that are also used in the ITB, such as Bid Bond, Bid Guarantee, Bidder, and Contractor. Rule 4.1 similarly states that the bidder is familiar with federal, state, and "Local Laws, Ordinances, Rules and Regulations that in any manner affect the Work." Rule 6.1 describes the process by which a bidder is to prepare and submit bids and the Bid Guarantee in language similar to that contained in the ITB. Rule 6.2 discusses the listing of subcontractors. Rules 6.2.1 and 6.2.2 state: General Contractor shall include as an integral part of his bid a List of Subcontractors he proposes to use. The Bidder shall enclose this list in a 4" x 9" envelope, sealed and marked "List of Subcontractors" and identified ... The Bidder shall enclose said envelope with his bid proposal in the mailing envelope. The List of Subcontractors enclosed with tee Proposal of each Bidder will be examined by the ... Engineer before the Proposal is opened and read. In the event that the form is not properly executed and signed, the Proposal of that Bidder will be returned to him unopened... Rule 6.3 requires a Statement of Surety as another "integral part" of each bid. Rule 6.3.3 states: The Statement of Surety will be opened examined by the ... Engineer prior to the opening of the Proposal.... Although similar to Rule 6.2, Rule 6.3 lacks the warming that if the Statement of Surety is not "properly executed and signed, the Proposal of that Bidder will be returned to him unopened." Rule 19.1 sets forth the requirements, for the surety. These requirements are different than those set forth in the ITB. Rules 19.1.1 and 19.1.2 require, as does the ITB, that the surety be admitted to do business in the State of Florida and shall have been in business and have a record of successful continuous operations for at least five years. However, Rule 19.1.1 requires that the surety be represented by a reputable and responsible surety bond agency licensed to do, business in the State of Florida and have a local representative in the Orlando area. Rule 19.1.3 requires minimum Bests ratings of "A" in "management," and, as to "strength and surplus," "AAA+" in financial rating and $12,500,000 minimum surplus. Rule 19.1.3.3 also requires that the surety be listed on the U.S. Treasury Departments Circular 570. The bids of FMI and S. I. Goldman Company contained a completed List of Major Subcontractors. The bid of B & I did not. No bidder included a Statement of Surety with its bid.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the School Board of Orange County enter a Final Order awarding the subject contract to Florida Mechanical, Inc. ENTERED this 15th day of February, 1990, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1990. APPENDIX Treatment Accorded Proposed Findings of FMI All of FMI's proposed findings have been adopted or adopted in substance. Treatment Accorded Proposed Findings of B & I 1-4: adopted or adopted in substance. 5: adopted, except that the staff recommended that, if the bid was to be awarded, that it be awarded to B & I. 6: adopted in substance. 7: rejected as conclusion of law and, to the extent fact, subordinate. 8-12: rejected as subordinate. 13-16: adopted or adopted in substance. 17: rejected as subordinate. 18: rejected as unsupported by the greater height of the evidence. 19-21: rejected as subordinate. 22: rejected as beyond the scope of the issues and irrelevant in view of the stipulation. In the stipulation, the parties agreed that the issue to be addressed would not be whether the intended agency action of Respondent was lawful (i.e., not arbitrary, fraudulent, dishonest, or otherwise improper), but rather whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. COPIES FURNISHED: James L. Schott, Superintendent The School Board of Orange County, Florida P.O. Box 271 Orlando, FL 32802 Charles Robinson Fawsett, P. A. Shutts & Bowen 20 North Orange Avenue Suite 1000 Orlando, FL 32801 James F. Butler, III Smith, Currie & Hancock 2600 Peachtree Center Harris Tower 233 Peachtree Street, N.E. Atlanta, GA 30043-6601 William M. Rowland, Jr., Esq. Rowland, Thomas & Jacobs, P.A. 1786 North Mills Avenue P.O. Box 305 Orlando, FL 32803
Findings Of Fact The Department of Community Affairs has its headquarters in the Rhyne Building on Centerview Drive in the City of Tallahassee. The Rhyne Building is one of a cluster of office buildings in the Koger Center which is owned by Koger Properties, Inc. One of the organizational units in the Department is the Energy Office, which was organizationally located within the Office of the Governor until 1991. At that time, the Energy Office was transferred by the Legislature to the Department, and the Department temporarily located the Energy Office organizationally as one of the components in the Office of the Secretary. The Secretary of the Department has decided to organizationally and physically integrate the Energy Office into the Department's Division of Housing and Community Development, having determined that the Energy Office programs are functionally related to that Division's programs. The Energy Office was physically housed in a building owned by Petitioner on Bronough Street in the City of Tallahassee. After the Energy Office was merged with the Department, the Department decided to move the Energy Office to the Rhyne Building. Officials of the Department responsible for supervision of the Energy Office had found it inconvenient to travel the distance between the Bronough Street and Centerview Drive locations and were experiencing difficulty in getting Energy Office personnel and other Department personnel to meet with each other and coordinate related duties. Accordingly, on January 31, 1993, the Department moved the Energy Office out of the Bronough Street building and into the Rhyne Building. As a result of that move, Petitioner has filed a lawsuit against the Department, alleging, inter alia, that the Department breached its lease with Petitioner. That litigation is still pending. Another organizational component of the Department is the Florida Housing Finance Agency. That Agency is physically located in the Marathon Building on Seagate Drive in the City of Tallahassee, part of the Koger Center. That Agency is in need of additional office space caused by new programs and by additional employees. The Agency does not have adequate space for its employees in its current location. The Agency and senior Department officials desire that the Agency remain in close physical proximity to the Rhyne Building since the Agency, like the other components of the Department, receives its administrative and other support services, including fiscal, legal, personnel, and procurement, from the Department. Further, the Agency, like the other divisions of the Department, have a number of interrelated programs which require a close working relationship. Although there were a number of possible solutions to the overcrowding faced by the Agency, splitting its different components into different locations was determined to be impracticable. Accordingly, several proposals to relocate other components of the Department were considered. Ultimately, the Department decided to lease additional office space for the Agency and locate the Energy Office in the Rhyne Building. A state agency which needs private office space of 3,000 square feet or more is required to engage in competitive bidding procedures. A state agency initiates such a process by submitting a Request For Prior Approval of Space Need ("RSN") to the Department of Management Services ("DMS") to show its need for additional space. Attached to the RSN is a Letter of Agency Staffing, which is used to determine the additional space needed based on the number and pay grade of agency employees and other variables. When an RSN is submitted, DMS first determines whether there is suitable state office space to meet the needs of the agency. If state-owned space is not available, the agency may solicit competitive bids from private lessors for the proposed lease by using a Request For Proposal ("RFP"). The state agency prepares the specifications used in the RFP, using the guidelines of DMS. Such specifications include a functional description of the type of space needed, the square footage, and the area of acceptable locations. The area of location of the premises is outlined by geographic boundaries on a map of the city or county where the space is needed, and the map is attached to the RSN and the RFP. The RFP also contains the evaluation criteria created by the agency soliciting bids for determining the score for each bidder's proposal. Each criterion is assigned a specific score, and the total possible score for all criteria is 100. The Department's interest in keeping its component programs in close proximity to each other and to the Office of the Secretary in the Rhyne Building at the Koger Center for supervisory, management, and operational effectiveness is strong. The amount of additional space needed, however, made the Department's acquisition of additional space subject to competitive bidding. The Department employee responsible for obtaining the additional space, Kirby Bass, advised senior management officials that in order for the Department to realize its desire to locate all of its components in proximity to the Office of the Secretary in the Koger Center, the Department could simply expand its current leases in the Koger Center in yearly increments below 3,000 square feet, thereby avoiding the requirement that the Department engage in the competitive bidding process. Rather than following the incremental approach, Bass' supervisor, Lynn Ekholm, directed him to prepare appropriate specifications for a new lease to accommodate 55 new and transferred employees needing approximately 14,000 square feet of additional space. Bass began gathering the information and preparing the paperwork to obtain the additional office space under the direction and supervision of Ekholm, the Department's Director of Administrative Services, and Mary Anne McMullen, the Department's Assistant Secretary, who had been charged with resolving the Department's office space problems. Bass contacted Randall Baker at DMS and discussed with him that Department's requirements for procuring additional office space. He also contacted the purchasing agents at the Department of Revenue and at the Department of Labor and Employment Security ("DLES") to determine how best to prepare the requisite documentation to meet the lease parameters desired by his Department. He discussed his Department's desire to obtain office space in an existing building in or near the Koger Center. Bass discovered that DLES had two leases obtained through competitive bidding within a small geographic area encompassing the Koger Center. One lease encompasses in excess of 15,000 square feet and is dated December 13, 1990; the other lease encompasses in excess of 16,000 square feet and is dated November 19, 1992. In both of those bid solicitations, DLES had received bid proposals from only two bidders located within that boundary -- Koger Properties, Inc., and Parkway-Oakland General Partnership. Each of those bidders received one of those two bid awards. Bass also made telephone inquiries to owners of buildings within the geographic area utilized by DLES to obtain those two leases and drove through the area. Bass did not go into any of the buildings that he drove past to inquire of the rental agents whether they in fact had any space available. He did notice a sign located at or near the complex east of the Oakland Complex advertising space available for up to 18,000 square feet. The evidence is unclear as to the exact buildings with the sign. If the sign related to the buildings known as the Parkway-Oakland Complex, no space was available, according to the testimony of one of the Department's witnesses. If that sign related to the Parkway Terrace Building, that building is owned by one of Petitioner's related companies, and that building is full. As a result of Bass' driving in the area, the Department did not discover any vacant space in any existing building within the geographic boundaries utilized by DLES. As a result of Bass' telephone contacts to owners of existing buildings within the geographic boundaries utilized by DLES, the only rental agent who represented that he had sufficient space available at that time was the rental agent for the Koger Center. That rental agent further advised Bass that although he had sufficient space available in the Koger Center, the rental rate would not be competitive with rates charged by other landlords. Accordingly, at the time that the Department drafted the geographic boundaries and evaluation criteria which are the subject of this proceeding, it knew that the Koger Center had sufficient space available although the Koger Center's rental agent did not consider his rates to be competitive, and the Department knew of no other available space within the boundaries. The Department prepared its RSN, utilizing the geographic boundaries which DLES had used. As stated in the RSN and in the subsequent RFP, the geographic boundaries selected by the Department are as follows: Beginning at the intersection of Capital Circle and Governor's Court Road, proceed west on Governor's Court Road until it ends. Continue on a projection, due west, to the intersection with Blair Stone Road. Proceed south on Blair Stone Road to Paul Russell Road. Proceed east on Paul Russell Road to Monday Street. Continue east on Monday Street to Capital Circle. Go north on Capital Circle to Governor's Court Road, the point of beginning. The RSN also represented that the Department was seeking a new lease for 14,193 square feet, more or less, to house 55 employees from June 1, 1993, through March 31, 1997. The Department submitted its RSN to DMS where it was reviewed by Randall Baker. DMS is authorized to approve an RSN submitted by a state agency seeking to lease private office space. DMS checks to determine if there is space available in a state-owned building, and, if there is not, approves the request of an agency to lease private space. DMS also checks to verify that the amount of space being requested is appropriate for the number and types of employees who will occupy the desired space. DMS does not have the authority to approve or disapprove other components of the RSN; for example, DMS can only make recommendations regarding such items as geographic boundaries. Baker reviewed the RSN, determined that there was no space available in a state-owned building, determined that the amount of space requested was appropriate for the number and types of employees to be housed in the additional space, and determined that the RSN form was properly completed. Baker was concerned about the small geographic area from which the Department would accept bids. He noted, for example, that the northern boundary cuts through a residential area and is not a commercial thoroughfare. He checked the vendor list maintained by DMS and found that there were other properties which were available but which were outside the boundaries to be utilized by the Department. Based upon his experience, he knew that an expanded radius for bid submittal would be likely to obtain a better rental rate for the Department. Baker sent the Department a letter, dated December 30, 1992, which states as follows: While we are approving your Request for Space Needs, it should be noted that the boundaries are rather restricted and may eliminate bidders who have quality space available. The Department employees who received and/or reviewed that letter did not consider Baker's letter to be a criticism of the Department's desired geographic boundaries. Accepting the first half of the sentence and ignoring the second half of the sentence, the Department determined that Baker's letter represented approval of its RSN and the geographic boundaries set forth therein. Accordingly, on January 26, 1993, the Department issued its RFP for its proposed Lease No. 520:0062. The bid specifications contained in that RFP called for 14,193 square feet of office space, more or less, to be available for occupancy not later than June 1, 1993. In addition, the RFP specified that the office space must be located in the City of Tallahassee inside the same geographic boundaries described in the Department's RSN. The RFP also contained the criteria by which bid submittals would be evaluated. Those criteria are as follows: C. EVALUATION CRITERIA (AWARD FACTORS) The successful bid will be that one determined to be the lowest and best. All bids will be evaluated based on the award factors enumerated below. Rental, using Total Present Value methodology for basic term of lease (see #D, General Provisions Items 3 and 4) applying the present value discount rate of 5.38 percent. (Weighing: 30) The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of Departmental operations planned for the requested space. (Weighing: 15) Conformance of and susceptibility of the design of the space offered to efficient layout and good utilization and to the specific requirements contained in the Invitation to Bid. (Weighing: 15) Frequency and availability of satisfactory public transportation within one block of the offered space. (Not to exceed a weight of 10 award factors) (Weighing: 4) Availability of adequate dining facilities within one mile of the offered space. (Weighing: 5) Proximity of offered space to Department of Community Affairs, Secretary's Office, Rhyne Building, Koger Center. (Weighing: 25) Moving cost (furniture, equipment, etc.) (Weighing: 1) Aggregate square footage in street level space. (Weighing: 5) Total award factors = 100 The bid specifications contain no other guidelines or information on how each criterion will be evaluated or how points will be awarded within the point spread for each criterion. Other state agencies have utilized proximity as an evaluation criterion, and DMS considers proximity a legitimate and potentially important criterion. However, the proximity that is usually referred to is proximity to the clients being served, not, as in this case, proximity to the Office of the Secretary. At first blush, the bid specifications allocate the highest score to cost and the second highest score to the proximity of the leased space to the Rhyne Building. The evaluation criteria in the RFP place almost as much weight on proximity to the Office of the Secretary (criterion 6), assigning 25 points, as on the rental amount bid (criterion 1), assigning 30 points. Yet, criterion 2 with its weight of 15 points may also relate to proximity to the Office of the Secretary by its use of vague terms about the area surrounding the building and the efficient and economical conduct of the Department's operations. It may well be, therefore, that the proximity to the Office of the Secretary offers a maximum score of 40 points, while the amount of rent only offers 30 points. Some state agencies awarding points for proximity include in their bid specifications a grid showing how many points are to be awarded for each incremental distance that a space being offered is from the target. Such a grid discloses to potential bidders in advance the number of points a bidder could expect to receive, for example, for a building located ten miles from the target as compared with how many points a bidder would receive for a building located one mile away. The Department's RFP contains no such grid system. In the RFP under consideration herein, it is certain that Koger Center would receive the maximum number of points allowable for proximity since the Office of the Secretary is located there. There is no requirement that any other bidder receive any points for the proximity criterion. Upon reviewing the bid specifications under consideration herein, Anagram Corporation timely filed its notice of protest and its formal protest challenging those bid specifications. By operation of law, the timely filing of the formal protest has caused the bidding process to be stayed until the resolution of this proceeding. Leonard Pepper is an officer and shareholder in Anagram Corporation. He is also an officer, shareholder or partner in other business entities which offer commercial space for rent in Tallahassee. Pepper and his companies have been leasing buildings to the State for the last 25 years. During that period, Pepper and his companies have won bid awards approximately 18 to 20 times. Neither Pepper nor Anagram has available office space within the geographic boundaries contained within the RFP. The Anagram building recently vacated by the Energy Office is still available. It, together with two other small buildings on adjacent parcels also owned by Anagram, would have sufficient space to respond to the RFP, but they are outside the geographic area specified. Gemini Associates, one of Pepper's related businesses, owns two buildings in what is known as the old FDLE Complex on Adams Street midway between the Capitol and the Governor's Mansion. One of those buildings has 27,000 square feet available and the other has 32,000 square feet available. Those buildings are also outside the geographic boundary specified in the RFP. Pepper has already made arrangements, however, for Gemini Associates to transfer title to those buildings to Anagram if Anagram so desires. Accordingly, Petitioner owns or controls property which meets the bid specifications but for the geographic boundaries contained in the RFP. The more potential bidders there are in a bid solicitation process, the more competitive the bidders will be. Accordingly, expanding the radius from the restrictive boundaries contained in the Department's RFP is likely to result in obtaining a better rental rate. The Department's choice of geographic boundaries after ascertaining that only Koger Center was known to have available space although not at competitive rates, after learning that those boundaries on two different occasions had produced only two bids, and after being cautioned by DMS that the boundaries were restrictive enough to preclude available quality space, leads to only one reasonable conclusion: that the Department intended to award the bid to the Koger Center if Koger submitted a bid. The bid specifications drawn by the Department were likely to achieve the Department's intended goal to have all of its organizational components physically housed in close proximity to the Office of the Secretary in the Koger Center, despite the requirement that the Department solicit competitive bids.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered sustaining Petitioner's protest to the bid specifications of proposed Lease No. 520:0062, declaring those bid specifications to be void, and terminating any bid solicitation process based upon those bid specifications. DONE and ENTERED this 12th day of May, 1993, at Tallahassee, Florida. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of May, 1993. APPENDIX TO RECOMMENDED ORDER DOAH CASE NO. 93-0854BID Petitioner's proposed findings of fact numbered 1-6 and 9-11 have been adopted either verbatim or in substance in this Recommended Order. Petitioner's proposed finding of fact numbered 7 has been rejected as not being supported by the weight of the competent, credible evidence in this cause. Petitioner's proposed finding of fact numbered 8 has been rejected as being subordinate to the issues involved herein. Petitioner's proposed findings of fact numbered 12-14 have been rejected as not constituting findings of fact but rather as constituting conclusions of law, argument of counsel, or recitation of the testimony. Respondent's proposed findings of fact numbered 1-7, 9-11, 14-17, 22, and 23 have been adopted either verbatim or in substance in this Recommended Order. Respondent's proposed findings of fact numbered 12 and 13 have been rejected as not being supported by the weight of the competent, credible evidence in this cause. Respondent's proposed finding of fact numbered 18 has been rejected as being subordinate to the issues involved herein. Respondent's proposed findings of fact numbered 19-21 and 24-28 have been rejected as not constituting findings of fact but rather as constituting conclusions of law, argument of counsel, or recitation of the testimony. Respondent's proposed finding of fact numbered 8 has been rejected as been irrelevant to the issues herein. COPIES FURNISHED: A. Eugene Lewis, Esquire Marlow V. White, Esquire Lewis & White Post Office Box 1050 Tallahassee, Florida 32302 Alfred O. Bragg, III, Esquire Robert C. Byerts, Esquire Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 William A. Friedlander, Esquire Friedlander & Mattox 3045 Tower Court Tallahassee, Florida 32303 Linda Loomis Shelley, Secretary Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 G. Steven Pfeiffer, General Counsel Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100
The Issue The central issue in this case is whether the bid for the Department of Health and Rehabilitative Services Lease No. 590:1871 to provide office space in Dade County, Florida, should be awarded to either Petitioner or Intervenor.
Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received at the hearing, I make the following findings of fact: The Petitioner, Robert Litowitz (hereinafter "Litowitz"), in response to an invitation to bid advertised by the Department of Health and Rehabilitative Services (hereinafter "HRS"), timely filed a bid submittal form offering to lease real property located at 11401 SW 40th Street (also known as Bird Road), Miami, Florida. This lease was to be for a five-year term with two one-year renewal options. The net square footage for the lease required by HRS was 14,781 + 3 percent with the geographical boundary designated by the invitation to bid being described as follows: All bid should be for existing office space located within the following boundaries: On the North, S.W., 48th Street. On the South, S. W., 88th Street. On the East, Palmetto Expressway, and on the West, S.W., 117th Street. This description contained an error in that the western boundary line should have been 117th Avenue not 117th Street. This minor discrepancy was noted at both of two pre-bid conferences conducted by HRS. The Intervenor, James C. Colross (hereinafter "Colross"), also timely filed a bid submittal form offering to lease real property described as Building "B," 9495 Sunset Drive (Southwest 72nd Street), Miami, Florida. Prior to the bid opening date, February 17, 1987, employees of HRS conducted two pre-bid conferences. At these conferences the bid package was reviewed and explained to all potential bidders present. Litowitz attended the pre-bid conference held the last week in January 1987. At this pre-bid conference Litowitz received the bid package and advised employees of HRS that he would be submitting property located on Bird Road for consideration for lease No. 590:1871. Linda Treml was the HRS employee who served as the contact person for the bid for Lease No. 590:1871. Ms. Treml conducted the pre-bid conferences and answered questions from potential bidders regarding the bid submittal forms. Several months earlier, perhaps during the summer 1986, Litowitz had met with Linda Treml regarding the possible lease of the Bird Road site, Ms. Treml had advised Litowitz that, at that time, HRS was not looking for space but that Litowitz would be added to their mailing list for future bid opportunities. Ms. Treml toured the Bird Road property with Litowitz as a courtesy visit for his inquiry. The bid submittal form for Lease No. 590:1871 required the proposed space be in an existing building. "Existing" was defined to specify the entire space to be dry and capable of being physically measured to determine net rentable square footage. Both the Colross and the Litowitz properties met this definition for an existing building at the time of the bid submittals. The bid submittal form for Lease No. 590:1871 required a minimum of 90 parking spaces to include a minimum of 80 full size spaces and 4 spaces meeting the Standards For Special Facilities For Physically Disabled found in Chapter 130-1, Florida Administrative Code. The required parking spaces did not have to be reserved for the exclusive use of HRS. Colross offered 62 exclusive spaces on site with 50 additional exclusive parking spaces located one block from the proposed facility. The Colross site plan for Building B (the bid property) established over 90 non-exclusive parking spaces available on site. The Litowitz property also had 90-plus non-exclusive parking spaces on site. HRS requested a clarification for the 50 exclusive spaces offered off-site by Colross. The verbal clarification was reduced to writing to confirm such spaces, if needed, would be at no cost to HRS. This written confirmation was not issued until March 31, 1987. HRS established a bid evaluation team to review the bids submitted for Lease No. 590:1871. This team, comprised of Janet Robinson, Dorea Sowinski, and Grace 0abolish, visited both the Litowitz and Colross properties. Subsequent to the site tours, they met in a conference room at Janet Robinson's office to discuss the bid evaluation process. This team was to make a recommendation as to which bid was the lowest and best. The recommendation was to be made based upon the evaluation criteria set forth in the bid submittal form. No other criteria were to be employed by the evaluation team. HRS has no guidelines which specified how each team member is to apply the evaluation criteria. The team recommendation would then be reviewed by George Smith and his superiors. Linda Treml advised the evaluation team not to consider the Litowitz property because it was outside the geographical boundary established by the invitation to-bid. The Litowitz property located on Bird Road is, in fact, outside of the advertised boundaries. The bid advertisement required the property to be considered for Lease No. 590:1871 to be within the stated geographical area. HRS did not, by act or omission, encourage Litowitz to prepare and submit a bid for a property known to be outside the defined boundary. HRS did not advise Litowitz that a property outside of the defined boundary would be disqualified. The bid evaluation criteria assigned a weighing value of 10 percent to the proximity of the offered space in the central or preferred area of the map boundaries. Litowitz mistakenly concluded that even though his property was not within the boundaries that he would lose only the 10 percent weighing factor when his property would be evaluated. HRS did not, by act or omission, affirm this erroneous interpretation. Because the Litowitz property was not within the defined geographical boundary, HRS disqualified the Litowitz bid. Accordingly, the Colross bid was the only bid left for consideration and was selected for Lease No. 590:1871. The interested parties were notified of this selection on or about March 19, 1987. The Colross bid included a higher rental fee than the Litowitz bid. HRS rejected a third bid for Lease No. 590:1871 submitted by Brookhill Capital Resources (hereinafter "Brookhill") since it was missing certain documents which had to be submitted by the time of the bid opening. The Brookhill bid included a lower rental fee than the Litowitz bid. The Brookhill property was within the advertised boundary. HRS selected the Colross property and deemed it the lowest and best bid since the Litowitz and Brookhill properties had to be disqualified. Members of the bid evaluation team preferred the Colross property for Lease No. 590:1871. HRS did not waive the boundary requirement for Lease No. 590:1871. Employees of HRS completed a bid synopsis which listed data on all three bidders for lease no. 590:1871 even though two of the bidders, Litowitz and Brookhill, had been disqualified, HRS reserved the right to reject any and all bids when such rejection would be in the interest of the State of Florida. Janet Robinson as the managing administrator of the disability determination office set the geographical boundaries for the invitation to bid. The boundaries were established in consideration of the needs and desires of the employees of the disability determination office.
Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received at the hearing, I make the following findings of fact: The School Board of Palm Beach County advertised for sealed bids for a project consisting of structural modifications and reroofing at Atlantic Community High School, project no. 000881600. All bidders were required to be prequalified by the School Board prior to the bid opening and had to exhibit evidence that similar work of equivalent magnitude had been accomplished prior to this bid. Language in the bid advertisement notified potential bidders that the School Board reserved the right to waive minor informalities in the bids, or to reject all bids. On April 5, 1989, the bids for the Atlantic Community High School (Atlantic) project were opened and a tabulation performed. All bidders had been prequalified by the School Board and had properly submitted the required bid bond. The results of the bid tabulation established GRI as the lowest bidder, Anderson second, and Milne & Nicholls third. Only three bids were timely received. The amount indicated on the GRI bid was stated only in numbers, not written in words. The written numbers, however, were clearly noted and GRI has, at all times, stated it intends to be bound by the figures listed. No error in the amount has been suggested. On April 5, 1989, Dr. Louwers, as contract administrator for the School Board, notified GRI that its bid for the Atlantic project had been deemed nonresponsive. The basis for this determination was GRI's failure to submit the bid book intact, failure to submit bid Form 00420 at the time of the bid opening, the lack of a warranty letter at the time of the bib opening, and the failure to state the price of the bids in words. GRI sought review of the determination that it had been nonresponsive and an informal hearing was conducted on April 11, 1989. As a result of that hearing, GRI'S bid was deemed responsive and all bidders were notified. Thereafter, Anderson timely challenged the intended bid award to GRI. At the time of the bid opening, GRI did not submit its bid book intact. Instead, GRI submitted the proposal form with the amounts indicated for each section together with the bid bond. The bid proposal form required the bidders to indicate an amount in several categories. These categories included a base bid and six alternates numbered 1 through 6. The amounts listed by all bidders were tallied and are specified on joint exhibit no. 10. GRI's bid was the lowest of the three bids received. Once the bids were opened, and it was determined who the three low bidders were, GRI immediately submitted its list of major subcontractors on Form 00420. Within 24 hours of the bid opening, GRI submitted its list of subcontractors and suppliers, Form 00430. Pertinent to this case are the following provisions found in the Instructions to Bidders, section 00100 of the bid package: BIDDING PROCEDURES: 3.01 All bids must be prepared using the forms contained in these specifications and submitted in accordance with the Instructions to Bidders. * * * 3.05 Preparation and Submission of Bid Proposal Form: Each bidder shall use Proposal Form contained in these specifications, indicate his bid prices thereon in proper spaces, for the entire work and for the alternates. Proposal Forms shall remain attached to the specifications.... Each proposal shall specify a unit price written in ink in both words and figures, * * * (d) The specification book is to be left INTACT, the cover signed by the Contractor, the proposal bid guarantee (Certified Check or Bid Bond) to be signed and filled out in the specification book which will be enclosed in a sealed envelope which shall be marked: * * 3.10 Subcontractors: At the time of the bid opening each bidder submitting a bid shall have in his possession a written list of the major subcontractors; namely, structural metal work and metal covering, structural manufacturer, lightweight insulating concrete, plumbing, HVAC, and electrical, whom he proposes to use on this work. The three (3) apparent low bidders will be required to submit Form 00420 (list of major subcontractors) to the Owner at the time of the opening of the bids.... Within 24 hours of the bid opening, the apparent low bidder shall submit Form 00430 (list of subcontractors and suppliers), completed in full to the Owner. Failure to submit these lists within the time period specified herein shall result in a non- responsive bid. * * * 6. REJECTION OF BIDS: 6.01 The bidder acknowledges the right of the Owner to reject any or all bids and to waive any informality or irregularity in any bid received. In addition, the bidder recognizes the right of the Owner to reject a bid if the bidder failed to furnish any required bid security, or to submit the data required by the bidding documents, or if the bid is any way incomplete or irregular; to reject the bid of a bidder who is not in a position to perform the contract; and to re- advertise for other or further bid proposals. In addition to the foregoing, the apparent three lowest bidders were required to submit certifications to verify information regarding the roofing system included in their proposals. These certifications included: a certification verifying that the pre-engineered metal roofing system had been tested and approved by Underwriter's Laboratory as Class 90; a dealer certification verifying the supplier is a manufacturer's authorized and franchised dealer of the roofing system to be furnished including the date on which authorization was granted; an installer certification specifying that the installer had been regularly engaged in the installation of pre-engirieered metal buildings of same or equal construction to the system proposed including a list of successful installations performed within 200 miles of West Palm Beach, Florida; and a manufacturer's certification verifying that the manufacturer will provide warranties in accordance with the bid specifications. These certifications were to be provided with Form 00430, within 24 hours of being determined an apparent low bidder. GRI did not provide the certifications identified in paragraph 8 within 24 hours of April 5, 1989; however, all certifications were submitted prior to the final hearing in this cause. GRI was not deemed responsive by School Board personnel until after the informal hearing conducted on April 11, 1989. The letter to GRI notifying it of the results of the informal hearing was dated April 19, 1989. The issue of the certifications, therefore, did not arise until Anderson sought to challenge the decision reached by the informal hearing (that GRI was responsive). Anderson submitted all data required by the bid package at the time of the bid opening or within 24 hours of being determined an apparent low bidder. Anderson submitted the bid package intact and complete. According to bark Lottes, the project architect for the Atlantic bid, the manufacturer's certification required to be submitted within 24 hours of the the bid package was to assure the School Board that it would obtain the warranty designated in the bid specifications. Typically, a warranty is not issued until the work is completed. The purpose of the manufacturer's certication is to verify that the warranty, when issued, will be of the type and terms designated by the bid package. No structural deck replacement will be required for the Atlantic job. A general contractor would be required to perform structural deck replacement. GRI listed a general contractor, Mancini Building, among its list of subcontractors and suppliers. The roofing system proposed by GRI is to be manufactured by Varco- Pruden. The installer to perform the structural metal work for the roofing system proposed by GRI is Bretsnyder Netals, Incorporated (Bretsnyder). Bretsnyder has prior experience with metal roofs of the type designated by this bid project. Varco-Pruden has acknowledged Bretsnyder to be an authorized installer of the Varco-Pruden roofing system proposed by GRI. Varco-Pruden has provided a certification that it will warranty the roofing system pursuant to the bid specifications. GPI is registered as a roofing contractor with Gregg Wallick as its licensed roofing contractor. Anderson is a registered general contractor.
Recommendation Based on the foregoing, it is RECOMMENDED: That the School Board of Palm Beach County enter a final order awarding the bid for the Atlantic project, project no. 000881600, to GRI, Inc. as the lowest responsive bidder. DONE and ENTERED this 23rd day of June, 1989, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division ofAdministrative Hearings this 23rd day of June, 1989. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 89-2175BID Rulings on the proposed findings of fact submitted by Anderson: Paragraphs 1 through 3, 5, 6, 7, and 8 are accepted. Paragraph 4 is rejected as irrelevant or immaterial. Whether or not a general contractor is required to perform portions of the work for the Atlantic project is irrelevant to the resolution of the issue in this case. First, because a general cortractor was listed among GRI's subcontractors (the list of which was timely filed) and second, because the weight of the testimony established the project to be roofing in nature with no structural work required. Paragraph 9 is rejected as argument or unsupported by the weight of the evidence in this cause. Rulings on the proposed findings of fact submitted by the School Board: Paragraphs 1 through 15 are accepted. Paragraph 16 is rejected as irrelevant. Rulings on the proposed findings of fact submitted by GRI: Paragraphs 1 through 4 are accepted. Paragraph 5 is accepted to the extent that it states the GPI bid to be lowest; however, as to the exact amount of the difference, it is rejected as contrary to the weight of the evidence. Paragraphs 6 through 8 are accepted. Paragraph 9 is rejected as argument. To the extent that the paragraph is addressed in findings of fact paragraphs 4 and 5, it is accepted. Paragraph 10 is accepted. Paragraph 11 is rejected as conclusion of law or argument except as provided in paragraphs of the preliminary statement, together with paragraphs 6, 8, 9, 12, and 13. COPIES FURNISHED: Jack S. Cox Merola, McCarthy & Cox, P.A. 4114 Northlake Boulevard Suite 301 Palm Beach Gardens, Florida 33410 Robert A. Rosillo Associate Counsel School Board of Palm Beach County 3323 Belvedere Road P.O. Box 24690 West Palm Beach, Florida 33416-4690 Nathan E Nason Gary N. Gerson Nason, Gildan, Yeager & Gerson, P.A. Post Office Box 3704 West Palm Beach, Florida 33402 Thomas J. Mills Superintendent of Schools School Board of Palm Beach County 3323 Belvedere Road P.O. Box 24690 West Palm Beach, Florida 33416-4690