Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES L. WASHINGTON, 87-002958 (1987)
Division of Administrative Hearings, Florida Number: 87-002958 Latest Update: Dec. 23, 1987

Findings Of Fact The Respondent, at all times material hereto, was a licensed registered "residential contractor." He was not registered or licensed as a general or building contractor, however, as Respondent himself acknowledged. See also, Petitioner's Exhibit 1 in evidence. The Petitioner is an agency of the State of Florida charged pursuant to the provisions of Chapter 489, Florida Statutes, with establishing licensure standards for building contractors of all types in the State of Florida, and with enforcing the various limitations on practice as a contractor embodied in that chapter. On or about January 28, 1986, the Respondent contracted with one Harold Martin, M.D., to build Dr. Martin a commercial office building in Leon County, Florida. The contract specified construction of all phases of the building project except the parking lot and the landscaping. The Respondent submitted a budget for the construction work to Dr. Martin depicting a total proposed cost for the project of $134,882. The Respondent performed substantial work on the office building in January and February of 1986. In March of 1986, due to a dispute which arose between the Respondent and Dr. Martin concerning the cost and progress of the construction project, Dr. Martin terminated the Respondent's service and contract and retained another contractor to finish the job, which was done. The Respondent established that when the contract was terminated, the building was approximately 65 percent complete. It is undisputed that the Respondent did perform a substantial amount of work on the office building pursuant to the contract with Dr. Martin. On March 27, 1986, the Respondent filed a claim of lien against the owner, Harold Martin, in which the Respondent stated that he had managed the construction of the office building in question and had performed $23,300 worth of work thereon. The Respondent also provided Dr. Martin with a Contractor's Affidavit, in which he certified to the owner that all lienors, except one, had been paid. The Respondent had contracted to perform the work after it had been started by another contractor retained by Dr. Martin, whom Dr. Martin had also terminated because he was not pleased with the progress and the quality of work of that first contractor. The Respondent established that one of the members of the Board of Directors of his corporation was a licensed general contractor, but admitted that that general contractor and board member had performed no work with regard to Dr. Martin's office building. The Respondent testified that another general contractor came to the job site from time to time to supposedly oversee the job. However, it was not established that any other general contractor, in the course of his practice, had any nexus with the Martin contract nor the performance of any construction on the building at times when the Respondent was performing construction thereon in January and February of 1986. This is demonstrated especially because of the fact that the Respondent never paid any other general contractor any money for any work or supervision performed with regard to this job, nor had Dr. Martin paid any other general contractor for such duties during the time that the Respondent was performing work on the building in question.

Recommendation Having considered the foregoing findings of fact conclusions of law, the evidence of record, and the candor and demeanor of the witnesses, it is therefore RECOMMENDED that a Final Order be entered by the Construction Industry Licensing Board, in accordance with disciplinary guideline Rule 21E-17.001(3), Florida Administrative Code, according the Respondent the penalty of a Letter of Guidance. DONE and ENTERED this 23rd day of December, 1987, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of December, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-2958 Petitioner's Proposed Findings of Fact: Accepted. Accepted. Accepted. Accepted. Accepted. Accepted. COPIES FURNISHED: William O'Neil, III, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mr. James L. Washington 320 West Pershing Street Tallahassee, Florida 32301 Mr. Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (4) 120.57489.105489.117489.129
# 2
JACK M. KEELS vs. BLACK AND VEATCH ENGINEERING, 86-004446 (1986)
Division of Administrative Hearings, Florida Number: 86-004446 Latest Update: Oct. 12, 1987

The Issue Whether petitioner suffered age discrimination for which Black & Veatch is answerable, when an employee of Black & Veatch objected to petitioner's becoming the safety engineer for M. A. Mortenson Company, the general contractor on a project for the Orlando Utilities Commission for which Black & Veatch was construction manager?

Findings Of Fact Since 1940, petitioner Jack Keels has been in the construction business, "95 percent of it would be . hydroelectric dams along the Columbia and Snake Rivers." (T.13) He has worked as a laborer, carpenter, an iron worker, a craft superintendent, a shift superintendent, a general superintendent, a craft foreman, a shift foreman and a general foreman. Aside from a wealth of practical experience, he has taken "probably 200 or 250 hours of classes on safety and first aid." (T. 13, 14) He has "been acting safety director on five or six jobs" (T.14) and once was responsible for the safety of 300 men. When he began work for M.A. Mortenson Company (Mortenson), however, on the Curtis H. Stanton Energy Center job (Stanton) , a coal-fired plant Mortenson was building for the Orlando Utilities Commission (OUC), Mr. Keels was a crane Coordinator without "assigned responsibility for safety." (T.93) But Mr. Keels offered suggestions about how to improve safety and spoke to Mortenson's Bill King regularly on such topics as safety latches for the hooks, proper nets, electrical splices, man baskets that were not regulation, and the like. When a new crane arrived on the site, Mr. Keels asked the general superintendent where the blocks were to test the crane and was told there were none and they had not been testing the cranes. There were other "flagrant violations" of safety regulations including widespread disregard for the rules requiring workmen to wear hard hats and forbidding them to bring glass containers onto the construction site. Although another contractor at Stanton, Babcock & Willcox, seemed to be doing worse as far as safety, Mortenson's practices were below average in Mr. Keels' opinion. This was also the impression key personnel at Black & Veatch had of Mortenson's performance. As the owner's representative at Stanton, Black & Veatch had invoked OUC's right under "option BC. 4. 1. of the . . . contract," Respondent's Exhibit No. 6, to require Mortenson to appoint a full-time safety engineer, in May of 1984. Bill King was Mortenson's safety director or designated safety engineer, when Mr. Keels started. Bill King left the job in February of 1985, and Mortenson's Mr. Barbato suggested replacing him with petitioner Keels. Mortenson did not propose this formally in writing, but Mr. Barbato explained to Richard F. King, Black & Veatch's project loss control manager at Stanton, that the work had reached a point that Mr. Keels' services as crane coordinator were no longer needed and that naming him safety engineer would make it possible to keep him on. He never told anybody at Black & Veatch about Mr. Keels' considerable background in construction safety. Petitioner and Black & Veatch's Paul William Weida had twice differed with each other on issues of safety: Once Mr. Weida objected to work on a generator pedestal going forward without a handrail in place. At the time, carpenters working for Mortenson were installing concrete forms on top of the pedestal, some distance above ground. Mr. Keels pointed out that they were wearing safety belts, and argued that a handrail could constitute a hazard as they moved around bolting and nailing the forms. The other dispute about which both men testified had to do with a bent crane lattice. The lessor of the crane told petitioner there was no need to replace that section of the lattice, but a representative of the manufacturer told Mr. Weida replacement would be best. Over petitioner's strenuous objection, Mr. Weida insisted that the damaged lattice be replaced. These confrontations left Mr. Weida with the impression that petitioner would be difficult to work with and also made him skeptical about petitioner's commitment to safety, a skepticism to which petitioner vehemently and perhaps justifiably objects. Under the contract between OUC and Mortenson, Black & Veatch had the right, as OUC's representative, to veto any candidate for safety engineer. The agreement provided, "During the life of the contract, replacement personnel will also be subject to interview and approval by the Owner." Respondent's Exhibit No. 7. Mr. Weida objected to Mr. Keels, and Richard F. King backed him up. Neither Mr. Weida's nor Mr. Richard King's opposition to Mr. Keels' being named safety engineer was in any way related to Mr. Keels' age, which, incidentally, was not proven with any specificity. After receiving indications from Black & Veatch that Mr. Keels would not be an acceptable safety engineer at Stanton, Mortenson laid him off, in February of 1985. By November of 1985, Mortenson had finished its work at Stanton.

Florida Laws (2) 760.02760.10
# 3
# 8
FLORIDA BOARD OF PROFESSIONAL ENGINEERS vs OLIVER TURZAK, P.E., 13-004046PL (2013)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Oct. 17, 2013 Number: 13-004046PL Latest Update: Jul. 01, 2014

The Issue The issue is whether Oliver J. Turzak violated statutes and rules governing the practice of engineering as charged in the Amended Administrative Complaint filed with the Clerk of the Florida Board of Professional Engineers (the “Board”) on October 4, 2012.

Findings Of Fact Petitioner is charged with regulating the practice of engineering pursuant to chapter 455, Florida Statutes. The Administrative Complaint at issue was filed by the Florida Engineers Management Corporation (“FEMC”) on behalf of Petitioner. FEMC is charged with providing administrative, investigative, and prosecutorial services to the Florida Board of Professional Engineers pursuant to section 471.038, Florida Statutes. Respondent is, and at all times material to these proceedings has been, a licensed professional engineer in the State of Florida, having been issued license number PE 18230. Respondent’s last known address is 5405 Water Street, New Port Richey, Florida 34652. On April 20, 2008, Respondent signed, sealed, and dated a Settlement Stabilization Plan for the Fish Residence located at 11251 Knotty Pine Drive, New Port Richey, Florida (“Fish Residence Project”). On June 10, 2008, Respondent signed, sealed, and dated an engineering opinion letter (“Letter”) which was addressed and sent to Champion Foundation Repair, the entity which was Respondent’s client for the Fish Residence Project. The Letter stated in material part: [Respondent], whose signature appears below, has verified placement of twenty-seven (27) exterior piers and twenty-five (25) interior jack pins as located on the drawings by the same job number. The piers all achieved sufficient load bearing characteristics to transfer the house weight to the piers and to close cracks substantially and stabilize the foundation. The remediation program was developed according to geological data supplied by Central Florida Testing Laboratories, Inc., dated November 2007. Similar pier reports on numerous structures with similar problems have demonstrated long term success without additional settlement. Therefore, it is the opinion of the [Respondent] that the location has been repaired and stabilized and, further, that there is no evidence of new sinkhole activity at the location. In compliance with Florida Statute 627.707, the report and remediation program was prepared under the supervision of a Registered Professional, whose field of expertise is a Geo-Technical Engineer. The Board has adopted Responsibility Rules of Professional Engineers (“Responsibility Rules”). These rules are contained in Florida Administrative Code Chapters 61G15-30 through 61G15-35. Professional engineers, who perform services covered by the Responsibility Rules, are required to comply with those rules. Rule 61G15-30.002(1) mandates that Respondent, as the structural engineer of record, is professionally responsible for the documents prepared for the Fish Residence Project. As such, Respondent is responsible for producing a document that complies with the applicable portions of the Responsibility Rules. Respondent acted as Engineer of Record of the Structure for the Fish Residence Project as that term is defined in rules 61G15-31.002(1) and 61G15-31.003(1). As such, all structural documents prepared, signed, sealed, and dated by Respondent must contain the information set out in rule 61G15-31.002(5), as mandated by rule 61G15-31.001, setting out the General Responsibility standards for engineers designing structures. Section 471.033(1)(g), Florida Statutes, provides that an engineer is subject to discipline for engaging in negligence in the practice of engineering. Florida Administrative Code Rule 61G15-19.001(4) provides that negligence constitutes “failure by a professional engineer to utilize due care in performing in an engineering capacity or failing to have due regard for acceptable standards of engineering principles.” Rule 61G15-19.001(4) also provides that: [F]ailure to comply with the procedures set forth in the Responsibility Rules as adopted by the Board of Professional Engineers shall be considered as non-compliance with this section unless the deviation or departures therefrom are justified by the specific circumstances of the project in question and the sound professional judgment of the professional engineer. Respondent’s June 10, 2008, Letter is an engineering “certification” as that term is defined in Florida Administrative Code Rule 61G15-18.011(4): statement signed and sealed by a professional engineer representing that the engineering services addressed therein, as defined in section 471.005(6), F.S., have been performed by the professional engineer, and based upon the professional engineer’s knowledge, information and belief, and in accordance with commonly accepted procedures consistent with applicable standards of practice, . . . . “Certifications” are subject to the standards set out in Florida Administrative Code Rule 61G15-29.001, which require that if an engineer is presented with a “certification” that “involve[s] matters which are beyond the engineer’s scope of services actually provided” that the engineer must “decline to sign . . . such certification.” Section 471.033(1)(a) provides that an engineer is subject to discipline for “[v]iolating . . . [a] rule of the [B]oard.” Section 471.033(1)(e) provides, in material part, that a professional engineer is subject to discipline for “[m]aking or filing a report or record that the licensee knows to be false” when the report is “signed in the capacity of a licensed engineer.” Rule 61G15-19.001(6) provides that: A professional engineer shall not commit misconduct in the practice of engineering. Misconduct in the practice of engineering as set forth in Section 471.033(1)(g), F.S., shall include, but not be limited to: * * * (b) Being untruthful, deceptive, or misleading in any professional report, statement, or testimony whether or not under oath or omitting relevant and pertinent information from such report, statement or testimony when the result of such omission would or reasonably could lead to a fallacious conclusion on the part of the client, employer or the general public; . . . . The Fish Residence In 2007, the residence located at 11251 Knotty Pine Drive in New Port Richey, Florida (the “Fish Residence”), experienced structural damage from subsidence in the ground underlying the home. As a result, a claim was made to Fish’s insurance company, and an investigation was commenced. Central Florida Testing Laboratories, Inc. (“CFTL”), a geotechnical engineering firm, performed an in-depth analysis and found, in a signed, sealed, and dated engineering report issued on November 20, 2007, that the subsidence was likely caused by a number of factors, including sinkhole activity. As a result, the Fishes hired a contractor, Champion Foundation Repair (“Champion”) to remediate the damage. Champion hired Respondent to perform the engineering services necessary to obtain a permit for the remediation, inspect the construction, and complete a report certifying the adequate completion of the work. Respondent had a long history of providing similar services to Champion in the past, having performed engineering services in over 200 projects for Champion. Respondent created, signed, sealed, and dated on April 20, 2008, a Settlement Stabilization Plan (“Plan”), which formed the design basis for the work Champion carried out. Well into the project, the Fishes became dissatisfied with the work done by Champion. Champion was terminated as the contractor before the work was finalized and before Respondent was able to perform a final inspection of the property. Litigation was commenced and Bracken Engineering (“Bracken”), a forensic structural/civil engineering firm was engaged to perform an investigation of the work performed by Champion and Respondent for the pending litigation. Bracken issued a lengthy engineering report (“Bracken Report”), under engineering seal, on June 20, 2011. The Bracken Report found Respondent’s Plan deficient, that Respondent was not adequately knowledgeable about the site, that Champion’s implementation of the Plan, and Champion’s construction work as a whole was flawed and inadequate. Subsequent to the issuance of the Bracken Report, a complaint was filed with the Board, and these proceedings were initiated. Settlement Stabilization Plan for the Fish Residence Roger Jeffery opined that the Plan failed to meet required engineering standards. The parties agree that when a structure, such as the Fish Residence Project, is initially built, the loads are directly transferred to the foundation, which then transfers the loads directly and uniformly as a continuously supported structure to the underlying soil. However, when, as occurred in this case, the structure’s loads are no longer transferred directly and uniformly to the ground through the foundation, but are transferred through pins which underlie the foundation, the foundation itself now acts as a beam or beams and is subject to the stresses applied to the beams. Respondent asserted that the foundation load would remain continuous, and therefore stable, since grouting had been poured under the Fish Residence to consolidate and stabilize the soils. However, Respondent’s plan did not call for grouting to be used. Moreover, according to the Bracken Report, no grouting was ever placed under the Fish Residence, even though it was called for in the CFTL Report to stabilize the structure. Respondent’s failure to perform a final inspection resulted in an inaccurate assumption and opinion. Respondent’s claim that grouting placed in the void under the structure reconstituted the original soil conditions is rejected, especially in light of the fact that Respondent also analyzed the pins and foundation in a beam configuration--a simple span beam. Further, Respondent’s analysis must be discounted because the calculations justifying his conclusion that the structure was adequately supported was performed in December 2013, well after these proceedings commenced and more than five years after the Plan had been created by Respondent. As a result of the changed structural support system (from ground support to pins), the position of the pins is critical to the stability of the structure. If the pins are too far apart for the strength of the foundation’s materials to accommodate the foundation, now acting as a beam or beams, the foundation will be overstressed. Cracking, at a minimum, or collapse, at a maximum, can occur. Cracking or collapse can occur because the concrete slab foundation used at the Fish Residence does not have any existing top reinforcing steel in it. When asked if perhaps reinforcing steel might have been placed within the slab itself, Mr. Jeffery stated he had never seen such use of steel in over 40 years. No evidence to support the steel within the slab theory was presented. When the newly installed pins become the structural support, a negative bending moment is introduced to the top of the foundation, now acting as a beam. The top of the foundation is made only of concrete, which has little ability to resist the induced negative moment. As a result, deflection, racking, and ultimate failure will be the result if the pin placement and the spans created by the placement are inadequately designed. Respondent’s after-the-fact calculations do not address this issue. Using a continuous beam analysis, the preferred method to evaluate the beam/pin assemblage design in structures like the Fish Residence, the spacing of the pins (usually ten feet apart) designed by Respondent coupled with the loads generated by the foundation and the lack of reinforcing steel in the top portion of the foundation would result in stress that would exceed the strength of the concrete and, at a minimum, the concrete would eventually crack. Dr. Ahmed Said, Respondent’s expert, agreed with this conclusion. Even using a simple beam analysis, the design method Respondent testified he used and that Dr. Said agreed was commonly used, movement, resulting in cracks at the foundation slab, would occur. Again, since no reinforcing steel exists at the top of the slab, as a matter of simple physics, the concrete would have to respond to the deflection that would occur at the bottom of the foundation and, concrete being weak, would likely crack or worse at the top. Respondent provided no persuasive rebuttal to Mr. Jeffery’s analysis. First, Respondent claimed that elevations taken at the site in 2013 showed minimal deflective movement, proving the Plan design was sufficient. However, Mr. Jeffery noted that subsequent elevations taken at the completed structure would have little meaning regarding the adequacy of the design since: the design stands alone and is not affected by how the contractor implemented it; and no one could know whether the design, as constructed, would withstand the required stresses until it was subjected to full design loading, which would have to include the full wind loads to which the structure was designed. There is no evidence the structure was ever subjected to such stress in the period between its construction in 2008 and the later recorded elevations. Next, Respondent claimed the 3-foot “spreaders” attached to the pins would reduce the span of the foundation acting as a beam and thus would overcome the lack of reinforcing steel in the top of the foundation and the resulting overstress. The problem with this assertion is that the Plan does not call for “spreaders” to be placed in the design by any notations that are readily and universally cognizable. Respondent admitted that the symbol regarding the use of the spreaders was agreed to only between Champion and him, and was not included in the Plan. However, even if the notations used by Respondent could be interpreted as calling for the use of the “spreaders,” the “spreaders” would not materially impact the fact that the foundation, acting as a beam, would be overstressed, since a negative moment would still exist due to the lack of reinforcing steel at the top of the foundation. Finally, Respondent asserted that Mr. Jeffery’s analysis was flawed since Mr. Jeffery had assumed the Fish Residence was a masonry structure whereas Respondent claimed the structure was a wood frame covered with a stucco exterior. This issue is confused by the fact that both the CFTL and Bracken Reports, upon which Mr. Jeffery relied, both stated the Fish Residence was a masonry structure, although the CFTL Report notes the structure was initially constructed as wood frame. In any event, Mr. Jeffery testified that regardless of the masonry versus wood frame question, the structure would still be overstressed. Changing the construction from masonry to wood frame/stucco veneer might lessen the overstress, but not materially. In addition to the overstress created by failing to address the induced negative moment at the top of the foundation, Respondent’s design also resulted in a shear load which exceeded the maximum allowable under the American Concrete Institute 318 Concrete Code; and, since that code is incorporated into the Florida Building Code (“FBC”), the requirements of the FBC as well. The shear load factor is especially relevant since Respondent did not assure that the pins would not be placed under windows and doors where this issue is critical. Respondent did not address the shear issue as it applied to windows and doors in his after-the-fact calculations. The Plan is also deficient since it did not indicate the placement of windows and doors in the Fish Residence Project. By not doing so, the pins, when put in the ground, could be placed underneath these internal spaces which do not then form a continuous roof/wall/foundation assembly. If that occurred, and it apparently did in the Fish Residence on four occasions, the shear problem described above is exacerbated, since at either side of a door or window a point load is created and the shear stress increased. The Plan also fails to include required information. While the Plan calls for the use of a “FastSteel” product, the Plan does not include any product specification number or the strength of the material to be used. Although Respondent stated that the contractor, based upon its experience, knew what was intended, ultimately Respondent admitted that the required information was not in the Plan. Similarly, the Plan did not include the design loads and criteria used in the design and provided no building codes and standards. Respondent admitted the Plan lacked this required information. The missing information is important. Only by including such information on design documents can the engineer adequately communicate to the reviewing building code plans examiner or a contractor what the design engineer intended. By not including this required information, the reviewer can be uncertain as to whether the engineer used the correct loadings or designed the structure in accordance with the correct edition of the building code. Similarly, failing to provide sufficient information concerning the products to be used may lead a contractor to utilize the wrong product during construction. The Plan was submitted to Pasco County for issuance of a permit. The county building department issued a permit for the work to be performed. Mike Mosher of Champion believed the Plan included all the specifications he needed to identify the components to be used and the manner in which the work was to be performed. He also testified the work was completed consistent with the Plan. The June 10, 2008, Certification Letter Respondent issued the June 10, 2008 Certification Letter (“Letter”) under seal to his client before he completed the inspections necessary for the conclusions in the Letter to accurately reflect the opinions contained in it. Both Respondent and his client, Champion, agree that since the client had been denied access to the Fish Residence Project, no final inspection of the site by Respondent ever occurred. As a result, Respondent admitted that, when he signed, sealed, and issued the Letter, the engineering services, upon which the certification in the Letter was based, had not yet occurred. The evidence proved that Respondent’s last appearance at the Fish Residence Project occurred on or about May 5, 2008, and that most of the work done at the site occurred after that date with the final construction finishing on or about May 30, 2008. As a result, the conclusions and opinions contained in the Letter were not based upon accurate and contemporaneous engineering analysis. Since the Letter purports to be grounded in engineering inspections, the statements in the Letter were not fully based upon the services Respondent actually provided. While not entirely clear from the evidence and testimony, had Respondent had the ability to perform a final inspection, he would have had the opportunity to discover several deficiencies in the construction. The Bracken Report detailed several deficiencies and non-conformances with the Remediation Plan. These deficiencies included: 1) failure to drive 5/6ths of the pilings to the depth prescribed by the notes to the Plan; a large number of pins found beneath door and window openings; mis-installation of pins and pin assemblages; and 4) no grouting placed in the ground although Respondent intended that grouting be used. Respondent agreed that at least some of the Bracken Report conclusions were warranted. Respondent asserts that, although the Letter was issued prematurely, Respondent should not be held accountable since the Letter “never went public.” This contention is rejected. The Letter was a final engineering report/certification and, upon issuance to Respondent’s client, Champion, was fully subject to all engineering standards, rules, and statutes. Since the Letter contained conclusions that were inaccurate and based upon information that was not collected under Respondent’s direct supervision, issuance of the Letter constituted negligence and misconduct in the practice of engineering. Respondent’s Prior History of Discipline Respondent has previously had discipline imposed. The instant case is the first in more than 40 years of Respondent practicing engineering that involved a subsidence remediation plan. Respondent’s first prior discipline was in FEMC Case No. 00-0086. In that case, Respondent was hired to correct building code issues identified by a county building department. The drawings he made violated the building code requirements, contained deficiencies, and were not in compliance with the standard practice of engineering. Respondent proceeded to hearing without benefit of legal counsel. A final order was entered by the Board reprimanding his license, fining him $1,000, plus costs of $302.93, placing him on probation for one year, and requiring he complete a course in professionalism and ethics while on probation. Respondent’s second prior discipline was in FEMC Case No. 01-0079. That matter was based upon drawings that were dated February 16, 2001. Respondent was not represented by counsel in that proceeding. In that proceeding, no proof was presented that the structure depicted in the plans by Respondent was ever built. Therefore, no direct risk of harm to the public was proven. Respondent entered into a Settlement Stipulation in that matter which was approved by the Board of Professional Engineers. He agreed to pay a total administrative fine of $7,000, plus $316.67 in costs and receive a reprimand on his license. He also received a one-year suspension of his license, followed by two years’ probation, and continuing education requirements. The other instance of discipline imposed against Respondent was in FEMC Case No. 2004037005. That complaint arose from plans that were signed by Respondent in June 2004. He was charged with signing plans he had not personally prepared or were not prepared under his supervision. Respondent entered into a Settlement Stipulation in that case that was approved by the Board. He paid a $5,000 administrative fine and costs of $750; received a reprimand on his license; received two years of probation; and was required to make detailed reporting to the FEMC during the probationary period. No additional evidence of prior disciplinary matters was offered other than the three cases described above.

Recommendation Based on the Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent Oliver Turzak’s Professional Engineer license be reprimanded, and that the license shall be suspended for a period of one year. Upon termination of the suspension, Respondent shall be reinstated under terms and conditions of reinstatement as the Board determines are appropriate, including two years of probation with terms the Board deems appropriate. Respondent shall also be fined $1,000 per count ($2,000 total fine). Finally, Petitioner shall be entitled to assess costs which are related to the investigation and prosecution of this case, other than costs or fees associated with an attorney’s time, as provided in section 455.227(3), Florida Statutes. DONE AND ENTERED this 6th day of May, 2014, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 6th day of May, 2014. COPIES FURNISHED: Zana Raybon, Executive Director Board of Professional Engineers Department of Business and Professional Regulation 2639 North Monroe Street, Suite B-112 Tallahassee, Florida 32303 Michael Flury, Esquire Office of the Attorney General The Capitol, Plaza Level 01 Tallahassee, Florida 32399-1050 J. Layne Smith, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 David P. Rankin, Esquire Law Office of David P. Rankin, P.A. 18540 North Dale Mabry Highway Lutz, Florida 33548 John Jefferson Rimes, III, Esquire Florida Engineers Management Corporation 2639 North Monroe Street, Suite B-112 Tallahassee, Florida 32303

Florida Laws (11) 120.569120.5729.001455.227471.005471.025471.031471.033471.038553.73627.707
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer