ELECTRICAL CONTRACTORS LICENSING BOARD vs. WILLIAM COOPER, 89-000738 (1989)
Division of Administrative Hearings, Florida Number: 89-000738 Latest Update: May 22, 1989

Findings Of Fact Based on the evidence received at the final hearing, the following findings of fact are made: At all times material to this case, the Respondent, William Cooper, was licensed as an electrical contractor in the State of Florida, holding license number ER 0007444. In October 1986, Dr. and Mrs. Gadi Gichon contracted with a general contractor named Construction Pros in connection with the remodeling of the Gichon residence in Fort Lauderdale, Florida. Respondent was hired by Construction Pros as the subcontractor for the electrical work on the residence. Respondent completed a portion of the electrical work pursuant to his subcontract. Prior to July 16, 1987, the Gichons fired Construction Pros as their general contractor. On July 16, 1987, the Respondent contracted in writing with the Gichons to complete the work he had started as the electrical subcontractor for Construction Pros and to do certain additional work specified by the contract. The Gichons agreed to pay Respondent the sum of $5,345.54 to complete the work he had started as a subcontractor and to do the additional work. The contract price included labor and materials. The Gichons paid Respondent $4,500.00 on July 16, 1987, and agreed to pay Respondent the balance of the contract price upon completion of the job. Respondent's work on the Gichon residence progressed very slowly after July 16, 1987, despite repeated telephone calls to Respondent by the Gichons. In response to the telephone calls Respondent would send one or two men to placate the Gichons by making a brief appearance at the Gichon residence. These men did not do any meaningful work on the project. On October 1, 1987, the Gichons sent Respondent a certified letter demanding that Respondent complete the work in 10 days. Respondent telephoned Dr. Gadi Gichon at his office in response to the letter of October 1, 1987. Respondent told Dr. Gichon that he had not returned to complete the project because he had not been paid for certain fixtures by the fired general contractor. Respondent made no further effort to complete the work. The Gichons hired another electrical contractor to complete the work started by Respondent and to do additional work. The second electrical contractor found Respondent's work incomplete but ready for a punchlist inspection. The second electrical contractor received its takeover permit on November 24, 1987, and completed the work started by Respondent in less than a week. Palm Coast Electrical charged the Gichons approximately $200.00 more than the Gichons would have paid had Respondent completed his contract.

Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered which finds Respondent guilty of having violated Section 489.533(1)(f) and (p), Florida Statutes, and which imposes an administrative fine of $1,000.00 against Respondent and which further issues a reprimand to Respondent for his violations of Section 489.533(1)(f) and (p), Florida Statutes. DONE and ORDERED this 22nd day of May, 1989, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed With the Clerk of the Division of Administrative Hearings this 22nd day of May, 1989. APPENDIX TO RECOMMENDED ORDER DOAH CASE NO. 89-738 The findings of fact contained in Paragraphs 1, 2, 3, 4, 6, 7, 10, 11, 14, and 16 of Petitioner's proposed findings are adopted in substance, insofar as material. The findings of fact contained in Paragraphs 5, 13, 15, 17, and 18 of Petitioner's proposed findings are immaterial. The finding of fact contained in Paragraph 8 of Petitioner's proposed findings is unsubstantiated by the evidence. The finding of fact contained in Paragraph 9 of Petitioner's proposes findings that the Gichons had live electrical wires in their home is unsubstantiated by the evidence. The finding of fact contained in Paragraph 9 of Petitioner's proposed findings that the Gichons had incomplete work in their home is adopted in substance. The finding of fact contained in paragraph 12 of Petitioner's proposed finding that Respondent did not complete the Gichon's job is adopted. The finding of fact contained in Paragraph 12 of Petitioner's proposed findings that Respondent did not respond to the letter of October 1, 1989, is rejected as being contrary to the evidence. The finding of fact contained in Paragraph 19 of Petitioner's proposed findings is subordinate. Respondent's statement in his letter filed May 8, 1989, is rejected as being contrary to the weight of the evidence. COPIES FURNISHED: Elizabeth R. Alsobrook, Esquire Department of Professional Regulation 1940 North Monroe, Suite 60 Tallahassee, Florida 32399-0729 William Cooper 4400 Northwest 15th Street Lauderhill, Florida 33313 Kenneth E. Easley, Esquire General Counsel Department of Professional Regulation 1940 North Monroe, Suite 60 Tallahassee, Florida 32399-0729 Pat Ard, Executive Director Electrical Contractors Licensing Board Department of Professional Regulation 1940 North Monroe, Suite 60 Tallahassee, Florida 32399-0729

Florida Laws (2) 120.57489.533
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs LAMAR CAMPBELL, A/K/A MARTY CAMPBELL, D/B/A JOHNSTON HANDYMAN SERVICES, 06-003171 (2006)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida Aug. 23, 2006 Number: 06-003171 Latest Update: Nov. 07, 2019

The Issue At issue is whether Respondent committed the offenses set forth in the Administrative Complaints and, if so, what penalty should be imposed.

Findings Of Fact Petitioner, the Department of Business and Professional Regulation (Department), is the state agency charged with the duty and responsibility of regulating the practice of contracting and electrical contracting pursuant to Chapters 20, 455, and 489, Florida Statutes. At all times material to the allegations of the Administrative Complaints, Lamar "Marty" Campbell was not licensed nor had he ever been licensed to engage in contracting as a State Registered or State Certified Contractor in the State of Florida and was not licensed, registered, or certified to practice electrical contracting. Mr. Campbell readily acknowledges that he has not had training or education in construction or contracting and has never held any licenses related to any type of construction or contracting. At all times material to the allegations of the Administrative Complaints, Johnston Handyman Services did not hold a Certificate of Authority as a Contractor Qualified Business in the State of Florida and was not licensed, registered, or certified to practice electrical contracting. Respondent, Lamar Campbell, resides in Gulf Breeze, Florida. After Hurricane Ivan, he and his roommate took in Jeff Johnston, who then resided in Mr. Campbell's home at all times material to this case. Mr. Johnston performed some handywork in Respondent's home. Mr. Johnston did not have a car, a bank account, or an ID. Mr. Campbell drove Mr. Johnston wherever he needed to go. At some point in time, Mr. Campbell drove Mr. Johnston to obtain a handyman's license in Santa Rosa County. Mr. Campbell did not apply for the license with Mr. Johnston and Mr. Campbell's name does not appear on this license. The license is in the name of Johnston's Handyman Services. Mr. Campbell is a neighbor of Kenneth and Tracy Cauley. In the summer of 2005, which was during the period of time when Mr. Johnston resided in Mr. Campbell's home, the Cauleys desired to have repairs done on their home to their hall bathroom, master bathroom, kitchen and laundry room. With the help of Mr. Campbell and others, Mr. Johnston prepared various lists of repairs that the Cauleys wanted performed on their home. In August 2005, Mr. Johnson and Mr. Campbell went to the Cauley's home and the proposed repairs were discussed with the Cauleys. There are documents in evidence dated August and October, 2005, which the Cauleys perceive to be contracts for the repairs to be done in their home. However, these documents are not contracts but are estimates, itemizing both materials and labor. The documents have the word "Estimate" in large bold type at the top and "Johnston Handyman Services" also at the top of the pages. The list of itemized materials includes electrical items, e.g., light fixtures and wiring. Also in evidence are documents dated August and October, 2005, with the word "Invoice" in large bold letters and "Johnston Handyman Services" at the top of the pages. Both Mr. and Mrs. Cauley acknowledge that Mr. Johnston performed the vast majority of the work on their home. However, at Mr. Johnston's request, Mr. Campbell did assist Mr. Johnston in working on the Cauley residence. Between August 5, 2005, and October 11, 2005, Mrs. Cauley wrote several checks totaling $24,861.53. Each check was written out to Marty Campbell or Lamar Campbell.1/ Mr. Campbell acknowledges endorsing these checks but asserts that he cashed them on behalf of Mr. Johnston, who did not have a bank account or identification, and turned the cash proceeds over to Mr. Johnston. Further, Mr. Campbell insists that he did not keep any of these proceeds. The undersigned finds Mr. Campbell's testimony in this regard to be credible. Work on the project ceased before it was finished and Mr. Johnston left the area. Apparently, he cannot be located. The total investigative costs, excluding costs associated with any attorney's time, was $419.55 regarding the allegations relating to Case No. 06-2764, and $151.25 regarding the allegations relating to case No. 06-3171, for a total of $570.80.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is, RECOMMENDED: That the Department of Business and Professional Regulation enter a final order imposing a fine of $1,000 for a violation of Section 489.127(1), Florida Statutes; imposing a fine of $500 for a violation of Section 489.531(1), Florida Statutes, and requiring Respondent, Lamar Campbell, to pay $570.80 in costs of investigation and prosecution. DONE AND ENTERED this 9th day of March, 2007, in Tallahassee, Leon County, Florida. S BARBARA J. STAROS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of March, 2006.

Florida Laws (11) 120.56120.569120.57120.68455.2273455.228489.105489.127489.13489.505489.531
# 3
RILEY N. BRACK vs. ELECTRICAL CONTRACTORS LICENSING BOARD, 84-001292 (1984)
Division of Administrative Hearings, Florida Number: 84-001292 Latest Update: May 22, 1984

Findings Of Fact Petitioner was a candidate for licensure as an electrical contractor and took the electrical contractor examination given July 26, 1983. Petitioner's initial grade was 70 percent. Additional credit was given based on certain objections and Petitioner's grade was raised to 73.5 percent. The minimum passing score on this examination is 75 percent. See Rule 21GG- 6.01(4), F.A.C. Respondent concedes that Petitioner's answer to question #11 should be credited since the .80 multiplier utilized by the Board in its calculation was not correct pursuant to note 10A of Table 310-16 of the National Electrical Code. Petitioner's grade is thereby further raised to 74.5 percent. Question #13 involves the calculation of electrical service for a lobby room of an apartment house. There was no listing for a lobby on the Table 220- 25 of the National Electrical Code and since this lobby is found in an apartment building, the service should be the same as a residence which is three watts. Furthermore, Petitioner made mistakes on the percentage he utilized on both motor loads and incorrectly multiplied the fire alarm service by 1.25. Petitioner incorrectly answered question #16, in part because he utilized two watts instead of three watts for the lobby computation. As noted above, the lobby was in an apartment house and should have been assigned the residential rate. Question #23 reads as follows: The owner is thinking of taking 2400 square feet of the lobby and adding a barber shop with 120/208 single phase panel. There would be a 9 KW hot water heater (at 125 percent) and 15 other receptacles, a reverse cycle air conditioner, 3 HP, 208 volt. How many amps would this add to the service? The accepted answer to the above question is computed by adding the additional current requirements to the existing lobby area. Petitioner followed this procedure but went one step further. He deducted the current required for the 2400 feet of lobby space which would no longer exist if the barber shop were added. Question #23 clearly contemplates removal of 2400 feet of lobby space. Therefore, the best answer to the question is derived by following Petitioner's procedure rather than Respondent's. Petitioner should be given credit for his answer to this question, thus raising his grade to 75.5 percent. Petitioner marked the wrong answers on his answer sheet for questions 49 and 60. He was not given credit for his correct calculations on his work sheet since the Board does not grant credit for any information which is not reflected on the answer sheet. This has been a consistent Board policy.

Recommendation From the foregoing, it is RECOMMENDED that Respondent enter a Final Order assigning Petitioner a grade of 75.5 percent on the July, 1983 electrical contractor examination. DONE and ORDERED this 22nd day of May, 1984 in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1984. COPIES FURNISHED: David G. Budd, Esquire 660 Ninth Street, North Naples, Florida 33940 Drucilla E. Bell, Esquire Deputy General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Jerry W. Hendry, Executive Director Electrical Contractors Licensing Hoard 130 North Monroe Street Tallahassee, Florida 32301 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (2) 455.2176.01
# 4
JOHN R. MARONEY vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, ELECTRICAL CONTRACTORS LICENSING BOARD, 99-002628 (1999)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 02, 1999 Number: 99-002628 Latest Update: Jul. 15, 2004

The Issue Whether Petitioner is entitled to additional credit on the challenged examination for licensure.

Findings Of Fact Petitioner, John R. Maroney, is a candidate for licensure as an electrical contractor low voltage applicant. He sat for examination in January 1999. His candidate number is 240024. Respondent, Department of Business and Professional Regulation, Board of Electrical Contractors, is the state agency charged with the responsibility of licensing applicants such as Petitioner. On the examination challenged, Petitioner received a score of 73.00, which was designated a failed status. In order to achieve a pass status Petitioner was required to obtain a score of 75.00. Petitioner timely challenged the results of two questions on the January 1999 examination. First, as to question 49, Petitioner maintained that his answer was reasonable as none of the answers given were correct. Question 49 required applicants to perform a mathematical computation and to select the best answer from those offered. The answer selected by Petitioner was $6.59 from the correct answer. The answer, the one that was given credit, was $4.77 or $1.47 from the correct answer, depending on whether the individual was paid for over-time at a higher rate. In either case the Department’s "correct" answer while not being mathematically accurate was the closer answer to a properly computed answer. The instructions on the examination directed applicants to choose the best answer to each question posed. Thus, while not mathematically accurate, Respondent’s answer to question 49 was the best from those offered. Choosing the best answer was also the issue in question 84 as none of the answers given on the examination accurately describes the cause of the problem. In making his selection, Petitioner admitted he had guessed, as he could not determine how any of the provided answers could decipher the problem he was to solve. Petitioner’s argument in this regard is well made since none of the answers given are attributable to the conditions described. Nevertheless, by process of elimination, an applicant could rule out the options offered by recognizing that two choices related to relay 1 could not contribute to the problem described. As Petitioner selected one of these clearly erroneous options, he cannot be given credit for the choice. As to the two remaining options, while inaccurate, the option that received credit was more likely related to the problem as the stop switch (stop 3) being faulty could cause the described problem if the circuit were to continue to be closed. Petitioner’s answer that described the problem on a relay unrelated to stop 3 would not be the best answer.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Electrical Contractors’ Licensing Board, enter a final order dismissing Petitioner’s challenge to the examination for licensure. DONE AND ENTERED this 15th day of December, 1999, in Tallahassee, Leon County, Florida. J. D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of December, 1999. COPIES FURNISHED: Lynne A. Quimby-Pennock Assistant General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-1007 John R. Maroney 9641 Northwest 39th Court Cooper City, Florida 33024 Ila Jones, Executive Director Board of Electrical Contractors Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399 William Woodyard, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399

Florida Laws (1) 489.516
# 6
PAUL A. MEIER vs ALARM SYSTEMS CONTRACTOR, 89-005209 (1989)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Sep. 20, 1989 Number: 89-005209 Latest Update: Feb. 26, 1990

The Issue The issue in this case is whether Petitioner is entitled to a passing grade on his examination for certification as an electrical contractor.

Findings Of Fact Petitioner took the electrical and alarm system contractor examination in January, 1989. Petitioner failed the examination. Petitioner timely challenged one question of relevance. The question that Petitioner challenges is question 34. If he were to receive a passing grade on this question or if the question were discarded, Petitioner would pass the examination. The challenged question is: All cut ends of rigid nonmetallic conduits shall be inside and outside to remove rough edges. trimmed reamed shaped sanded Petitioner answered "(B)." The answer for which Respondent gave credit is "(A)." The National Electrical Code describes the finishing processes for rigid nonmetallic conduit and rigid metal conduit as follows: Section 347-5. Trimming. All cut ends shall be trimmed inside and outside to remove rough edges. Section 346-7(a). Reamed. All cut ends of conduits shall be reamed or otherwise finished to remove rough edges. The National Electrical Code also uses the phrase "reamed or otherwise finished" with respect to intermediate metal conduit and electrical metallic tubing. Sections 345-8 and 348- 11. The first article of the National Electrical Code is devoted to definitions. Under Article 100, the scope of the definitions article is explained as follows: Scope. Only definitions of terms peculiar to and essential to the proper use of this Code are included. In general, only those terms used in two or more articles are defined in Article 100. . . . Part A of this article contains definitions intended to apply wherever the terms are used throughout this Coded. . . Article 100 contains no definition of "trim" or "ream," although the term "ream" is used in two or more articles: namely, Articles 345, 346, and 348. The term "ream" is the word commonly used in the relevant industry to describe the process by which a person eliminates the rough edges on the cut end of a rigid; nonmetallic conduit. The term "ream" is so used by, among others, practicing professional electrical and alarm system contractors. The term "ream" is also so used by manufacturers of "conduit reamers," which are packaged and labelled under that name. These "conduit reamers" are obviously designed for use with PVC and other rigid nonmetallic conduit. By contrast, the term "trim" is rarely used to describe this deburring process.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Department of Professional Regulation enter a Final Order assigning Petitioner a passing grade on the January, 1989, electrical and alarm systems contractor' s examination. ENTERED this 26th day of February, 1990, in Tallahassee, Florida. ROBERT E. MEALE, Hearing Officer Division of Administrative Hearings The DeSoto 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26 day of February, 1990. COPIES FURNISHED: Kenneth E. Easley General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Robert S. Hayes 437 W. Vine Street Kissimmee, FL 34741 Jack L. McRay, Senior Attorney Department of Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, FL 32399-0792 Pat Ard, Executive Director Electrical Contractors Licensing Board Northwood Centre 1940 North Monroe Street Tallahassee, FL 32399-0792

Florida Laws (3) 120.57455.217489.511
# 7
BOARD OF PROFESSIONAL ENGINEERS vs. WILLIAM E. OVERSTREET, 86-000543 (1986)
Division of Administrative Hearings, Florida Number: 86-000543 Latest Update: Jun. 17, 1988

Findings Of Fact Based on the stipulations of the parties, on the exhibits received in evidence, and on the testimony of the witnesses at the hearing, I make the following findings of fact. The Respondent has been licensed as a professional engineer in the State of Florida since 1964 (license number PE 0010812), having become licensed by examination in the field of mechanical engineering. He has practiced professional engineering since 1964 in and around Fort Walton Beach and Okaloosa County, Florida, as an individual practitioner and as an officer of the Royster Construction Company. The Respondent's formal education and professional experience are in the fields of civil, structural, and mechanical engineering. Although testimony indicates that the Respondent has had some contact with the field of electrical engineering, he lacks significant formal education or professional experience in that specialty. Findings regarding Count I In July 1984 plans for a proposed project to be known as the White Sands Bowling Center were prepared, signed, and sealed by the Respondent in his capacity as a professional engineer. The plans included sheets numbered 1 through 9, of which sheet number 6 and sheet number 9 depict electrical components of the proposed structure. Findings regarding Count II The electrical engineering plans (sheet number 6 and sheet number 9) contain errors and omissions including the following: The "symbol legend" necessary to define components depicted on the plans has been omitted. Fixture types and wattage specifications necessary to determine adequate and appropriate loading of circuits have been omitted. Electrical component and fixture circuit identification numbers necessary to identify such components and fixtures have been omitted. Specifications necessary to determine air conditioning connections have been omitted. Details of fire alarm circuitry required by applicable building codes in force at the time of design have been omitted. Emergency exit fixtures and circuitry required by applicable building codes in force at the time of design have been omitted. Electrical panel details necessary to complete construction have been omitted. Details of connections necessary for installation of indicated aluminum wiring have been omitted. The specification depicted for grounding of the electrical system is not in compliance with applicable building codes in force at the time of design. The electrical riser depicted on the plans is incomplete and does not provide sufficient information to complete construction. The Respondent failed to meet a standard of due care in the preparation of the plans depicting electrical engineering for the White Sands Bowling Center and was negligent in his preparation of those plans. Findings regarding Count III The mechanical engineering plans (sheet number 7, air conditioning, and sheet number 8, plumbing) contain errors and omissions including the following: Specifications of air conditioning units and associated ducting are in conflict and do not provide details necessary to complete construction. Details showing "returns" from outside air are in conflict with known standards of design and do not provide details sufficient to complete construction. Specifications of condensation features do not provide sufficient detail to complete construction and are not in compliance with applicable building codes in force at the time of design. Toilet exhaust system details are not sufficient to complete construction and are not in compliance with applicable building codes in force at the time of design. Details of water supply system source and sanitary collection and disposal required by applicable building codes in force at the time of design have been omitted. The Respondent failed to meet a standard of due care in the preparation of the plans depicting mechanical engineering for the white Sands Bowling Center and was negligent in his preparation of those plans. Findings regarding Count IV The structural engineering plans (sheet number 3) do not contain details sufficient to complete construction, and if built as designed, there is no reasonable assurance that the structure would comply with applicable building codes in force at the time of design. The Respondent failed to meet a standard of due care in the preparation of the plans depicting structural engineering for the White Sands Bowling Center and was negligent in his preparation of those plans.

Florida Laws (5) 120.57455.227471.025471.031471.033
# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs ANTONEY MANNING, D/B/A MANNING BUILDERS, 06-000601 (2006)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 16, 2006 Number: 06-000601 Latest Update: Nov. 07, 2019

The Issue At issue is whether Respondent committed the offenses set forth in the Administrative Complaints and, if so, what penalty should be imposed.

Findings Of Fact Petitioner, the Department of Business and Professional Regulation (Department), is the state agency charged with the duty and responsibility of regulating the practice of contracting and electrical contracting pursuant to Chapters 20, 455 and 489, Florida Statutes. At all times material to the allegations of the Administrative Complaints, Antoney Manning was not licensed nor had he ever been licensed to engage in contracting as a State Registered or State Certified Contractor in the State of Florida and was not licensed, registered, or certified to practice electrical contracting. At all times material to the allegations of the Administrative Complaints, Manning Builders did not hold a Certificate of Authority as a Contractor Qualified Business in the State of Florida and was not licensed, registered, or certified to practice electrical contracting. Respondent, Antoney Manning, was at all times material to this proceeding, the owner/operator of Manning Builders. Respondent is in the business of framing which includes framing, drywall, tile, trim work, and painting. A document which is in evidence purports to be a contract dated September 5, 2004, between Manning Builders and Ms. Gwendolyn Parker, for the construction of a 14-foot by 14- foot addition in the rear corner of Ms. Parker's house located at 8496 Southern Park Drive in Tallahassee, Florida. The contract identifies Manning Builders as the "contractor." The contract price is $15,000. Unfortunately, only the first page of the contract is in evidence. However, Respondent acknowledges that he and Ms. Parker entered into a contract regarding the 14-foot by 14-foot addition to Ms. Parker's home. Respondent insists that he informed Ms. Parker that he was not a certified general contractor, but that he could find a general contractor for her. When that did not work out, Respondent told Ms. Parker that she would have to "pull" her own permits and that he could do the framing. He also told her that he would assist her in finding the appropriate contractors to do the electrical work, plumbing, and roofing. Ms. Parker did not testify at the hearing. On September 7, 2005, Respondent signed a receipt for $7,500 for a "deposit on addition (14 x 14)." The receipt identifies Ms. Gwendolyn Parker as the person from whom the money was received by Respondent. Respondent acknowledges finding an electrical contractor to perform the electrical work on the addition. However, he insists that he did not hire the electrical contractor but found one for Ms. Parker to hire. He gave the name to Ms. Parker but she apparently did not contact him. In any event, the electrical work was never done on the addition. Respondent completed the framework on the addition. Respondent did not build the roof, as he was aware that would require a roofing contractor. Work on the project ceased before the addition was finished. Ms. Parker's home suffered rain damage as a result of the roof not being completed. There is nothing in the record establishing the dollar amount of damage to her home. The total investigative costs to the Department, excluding costs associated with any attorney's time, was $360.59 regarding the allegations relating to Case No. 06- 0601, which charged Respondent with the unlicensed practice of contracting. The total investigative costs, excluding costs associated with any attorney's time, was $140.63 regarding the allegations relating to Case No. 06-0602, which charged Respondent with the unlicensed practice of electrical contracting.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the Department of Business and Professional Regulation enter a final order imposing a fine of $1,000 for a violation of Section 489.127(1); requiring Respondent to pay $360.59 in costs of investigation and prosecution of DOAH Case No. 06-0601, and dismissing DOAH Case No. 06-0602. DONE AND ENTERED this 28th day of June, 2006, in Tallahassee, Leon County, Florida. S ___________________________________ BARBARA J. STAROS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of June, 2006. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Antoney Manning 11865 Register Farm Road Tallahassee, Florida 32305 G. W. Harrell, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Josefina Tamayo, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202

Florida Laws (10) 120.56120.569120.60455.2273455.228489.105489.127489.13489.505489.531
# 9
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs WILLIS WITTMER, JR., AND JR WITTMER`S REMODELING, INC., 07-000074 (2007)
Division of Administrative Hearings, Florida Filed:Daytona Beach, Florida Jan. 05, 2007 Number: 07-000074 Latest Update: Nov. 07, 2019

The Issue The issues to be resolved in this proceeding concern whether the Respondent committed the charged violations of Section 489.127(1)(f), Florida Statutes (2006), and Section 489.531(1)(a), Florida Statutes (2006), and if so, what penalty, if any, is warranted.

Findings Of Fact The Petitioner is an Agency of the State of Florida charged with regulating the practice of contracting and the licensure of those engaged in the practice of contracting of all types, in accordance with Section 20.165, Florida Statutes, as well as Chapters 455 and 489, Florida Statutes. The Respondent engages in re-modeling and other construction-related work both as his own business and employment by a certified general contractor. This case arose upon a Complaint filed with the Petitioner Agency by Mr. Kenneth Hatin. The Complaint asserted his belief that the Respondent had engaged in a contract to construct an addition on his home, and after being paid substantial sums of money, had wrongfully left the job and never finished it. The residence in question is co-owned by Mr. Hatin and his fiancée, Ms. Beverly White. Ms. White's first cousin is Ms. Julie Crawley. Ms. Crawley is the Respondent's fiancée. Mr. Hatin and the Respondent were introduced by Ms. Crawley and Ms. White. Mr. Hatin and the Respondent thus met socially and as they got to know each other discussed Mr. Hatin's desire to have an addition placed on his home. The addition consisted of a pool enclosure to be constructed on his property located at 33 Botany Lane, Palm Coast, Florida. Mr. Hatin expressed the desire to have the Respondent assist him in constructing the pool enclosure. The Respondent agreed to do so. The Respondent is employed by his brother, who is a Florida-Licensed General Contractor, but neither the Respondent nor his business, JR. Wittmer's Remodeling, Inc., are licensed or certified to engage in contracting or electrical contracting. In accordance with his agreement with Mr. Hatin, the Respondent provided labor and assistance with the renovation project, including digging ditches, picking-up supplies and being present at the work site. In addition to the Respondent, other friends and family members of the protagonists assisted with the project, including the Respondent's son, Ms. Crawley's son, Mr. Hatin's employer, Ms. White's brother-in-law, and Mr. Hatin himself. This was, in essence, a joint family/friends cooperative construction project. Over the course of approximately five months during the construction effort, Mr. Hatin wrote checks to the Respondent in the total amount of $30,800.00. All contractors or workmen on the job were paid and no liens were placed on Mr. Hatin's property. The checks written were for the materials purchased and labor performed by tradesmen or sub-contractors engaged by the Respondent and Mr. Hatin for various aspects of the job such as roofing, tile or block laying, etc. The Respondent received no fee or profit in addition to the amounts paid to the material suppliers, contractors, and laborers on the job. It is not entirely clear from the record who prepared the contract in evidence as Petitioner's Exhibit four, or the document that the parties treated as a contract. It is not entirely clear who actually signed it, but the document was drafted relating to the work to be done on Mr. Hatin's home (the contract). Mr. Hatin maintained that the Respondent prepared and signed the contract. Ms. Crawley testified that the contract was actually prepared by herself and Ms. White (for "tax purposes"). It is inferred that this means that the contract was prepared to provide some written evidence of the amount expended on the addition to the home, probably in order to raise the cost basis in the home to reduce capital gains tax liability potential at such time as the home might be sold. The term "tax purposes" might mean other issues or consequences not of record in this case, although it has not been proven that the contract was prepared for a fraudulent purpose. Ms. Crawley testified that the Respondent did not actually sign the document himself but that she signed it for him. What was undisputed was that there were hand-written changes made to the contract so as to include exhaust fans, ceiling fans, sun tunnels, a bathroom door and outside electrical lighting. Although there was a change to the contract for this additional scope of work, there was no increase in the amounts to be paid by Mr. Hatin for such work. After the project was commenced and the addition was partially built, Mr. Hatin and Ms. White were involved in a serious motorcycle accident. Work was stopped on the project for a period of approximately seven weeks, with Mr. Hatin's acquiescence, while Ms. White convalesced. The Respondent, during this time, dedicated all of his time to his regular job and other work commitments. It was apparently his understanding, expressed in Ms. Crawley's testimony, that, due to injuries he received in the accident and more particularly the more serious injuries received by his fiancée, that Mr. Hatin was not focused on the project at that time, but let it lapse until the medical emergency was past. After approximately seven weeks of inactivity Mr. Hatin contacted the Respondent requesting that he begin work on the project again. A meeting was set up between Mr. Hatin and the Respondent. The Respondent however, was unable to attend the meeting with Mr. Hatin that day, tried to re-schedule and a dispute arose between the two. Additionally, family disputes over money and interpersonal relationships were on- going at this time leading to a lack of communication and a further dispute between Mr. Hatin, Ms. White, the Respondent, and Ms. Crawley. A threat of physical harm was directed at the Respondent by Mr. Hatin (he threatened to put out the Respondent's "one good eye" if he came on the subject property again). Because of this, the Respondent elected not to return to the project. Inferentially, at that point the process of filing the subject complaint soon ensued.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED that the Administrative Complaint filed herein be dismissed. DONE AND ENTERED this 12th day of June, 2007, in Tallahassee, Leon County, Florida. S P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with Clerk of the Division of Administrative Hearings this 12th day of June, 2007. COPIES FURNISHED: Ned Luczynski, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 E. Renee Alsobrook, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-1007 Garvin B. Bowden, Esquire Gardner, Wadsworth, Duggar, Bist & Wiener, P.A. 1300 Thomaswood Drive Tallahassee, Florida 32308 Nancy S. Terrel, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (8) 120.569120.57120.6820.165489.105489.127489.505489.531
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer