Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs GONZALO VEGA, 96-004148 (1996)
Division of Administrative Hearings, Florida Filed:Miami, Florida Sep. 03, 1996 Number: 96-004148 Latest Update: Jul. 15, 2004

The Issue Whether the Respondent committed the violations alleged in the Administrative Complaint, and, if so, the penalty that should be imposed.

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department of Business and Professional Regulation is the state agency responsible for investigating and prosecuting complaints involving violations of the requirements of Chapter 489, Part I, Florida Statutes. Sections 489.131(7)(e) and 455.225, Florida Statutes. Pursuant to Section 489.129(1), the Construction Industry Licensing Board ("Board") is the entity responsible for imposing discipline for any of the violations set out in that section. At all times material to this case, Mr. Vega was a certified general contractor operating under a license issued by the Construction Industry Licensing Board, numbered CG C046448. Mr. Vega has been a licensed general contractor in Florida since 1989, and since 1994, he has been the licensed qualifying agent for Group Construction South Florida, Inc. The residence of David M. Hudson, located at 19801 Southwest 84th Avenue, Miami, Dade County, Florida, was severely damaged in August, 1992, by Hurricane Andrew. In a letter dated October 13, 1992, Mr. Hudson, who holds a doctorate in biology and is the laboratory manager for the University of Miami Chemistry Department, proposed to Mr. Vega that he prepare plans for reconstructing the Hudson residence. On December 23, 1992, Mr. Hudson and Mr. Vega executed a contract for construction work to be performed on the Hudson residence. The parties contemplated that Mr. Vega would complete the work in accordance with the drawings and original blueprints prepared by Jose A. Sanchez, a structural engineer, at Mr. Vega's direction and based on preliminary plans approved by Mr. Hudson. Specifically, Mr. Hudson understood that the major elements of construction included in the December 23 contract were elevation of the house from one story to two stories, construction of a new living area on the second floor, and construction of a basement on the first floor to serve as a "bare bones storage area." The contract price specified in the December 23 contract was $146,338.33, with ten percent due upon acceptance of the proposal, ten percent due at completion of each of eight items of construction specified in the contract, and ten percent due upon completion of the project. The eight items of construction specified in the contract were "demolition work, rising work, tie beams, roof, doors & windows, plaster & tile, pool & fence, finish work and paint." On February 1, 1993, Metropolitan Dade County Building and Zoning Information Department issued Permit Number 93119957 to Mr. Vega for the Hudson project. The building permit was based on the original plans for the project submitted by Mr. Vega on January 19, 1993, together with some items that were added to the plans at the county's request. Mr. Vega began work on the project on February 1, 1993, the day the permit was issued. Mr. Vega hired Ruben Armas to act as foreman for the project, and his duties included hiring and supervising day laborers and procuring materials needed for construction. At the time, Mr. Armas was not licensed, registered, or certified by either Dade County or the State of Florida. Mr. Vega had an arrangement with Mr. Armas whereby he paid Mr. Armas periodic advances on a lump sum payment that Mr. Armas was to receive when the Hudson project was complete. Mr. Vega did not deduct FICA or withholding tax from the payments made to Mr. Armas under this arrangement. Mr. Vega dealt directly with Mr. and/or Mrs. Hudson regarding the project, although they would occasionally leave messages for him with Mr. Armas. Mr. Vega directly supervised Mr. Armas and gave him instructions on the work that was to be performed and the way it was to be done. Mr. Vega was routinely at the job site at least two or three times a day to inspect the work that had been done. Mr. Vega was present at the site during the entire time that cement was poured for footings or other structural elements. Mr. Vega arranged for various subcontractors to work on the project, including electricians, plumbers, air conditioning workers, roofers, carpenters, and drywall hangers. On April 14, 1993, a Department investigator conducted an inspection of the Hudson project during a "hurricane task force sweep." When she and the other members of the task force arrived on the job site, she observed Mr. Armas and two other men "inside working," but she did not observe them working or see the type of work they were doing. Mr. Armas walked out to meet the inspector and gave her a card that contained his name and phone numbers and the words "General construction & roof repair." Mr. Armas told the Department investigator that, when she arrived, he was "working on the footing for the elevation of the house." On April 21, 1993, Mr. Vega signed a Cease and Desist Agreement in which he acknowledged that the Department was investigating allegations that he had "engaged in the practice of aiding and abetting unlicensed contractor Ruben Armas." By signing the agreement, Mr. Vega agreed to cease "engaging in this activity," but he did not admit that the Department's allegations were true. The Department investigator was at the Hudson job site on April 14, 1993, for thirty minutes to an hour, during which time Mr. Vega did not appear at the site. This was the only time she was at the job site while work was being done. As the work progressed on the project, everything appeared to be going well, and Mr. Vega felt that he enjoyed a very good working relationship with Mr. and Mrs. Hudson. Mr. Hudson paid Mr. Vega a total of $116,400.00, or eighty percent, of the original contract price of $146,338.33, in ten percent increments as provided in the contract. By check dated December 23, 1992, Mr. Hudson paid the down payment of $14,633.38. By check dated February 5, 1993, Mr. Hudson paid $14,600.00 upon completion of the demolition work. By check dated March 5, 1993, Mr. Hudson paid $14,633.00 upon completion of raising the structure to two stories. By check dated March 24, 1993, Mr. Hudson paid $14,633.00 upon completion of the tie beams. By check dated April 19, 1997, Mr. Hudson paid $14,633.00 upon completion of the roof. By check dated May 13, 1993, Mr. Hudson paid $14,633.00 which should have been paid upon completion of the doors and windows but which he paid even though the installation of the doors and windows was not complete. By check dated June 23,1993, Mr. Hudson paid $12,000.00 of the $14,633.00 draw because, in his opinion, the project was not being completed on schedule. Finally, by check dated July 2, 1993, Mr. Hudson paid $17,000.00 to bring the payments up to the amount consistent with the contract schedule for completion of the pool and fence. In a letter to Mr. Vega dated June 7, 1993, Mr. Hudson stated that he wanted to make "a major change" in the plans. Specifically, Mr. Hudson wanted to eliminate the swimming pool, which he estimated would save $20,000.00 of the $146,633.00 contract price, and use the money saved "to completely finish the downstairs to be a nice guest area," to "install the better quality carpet we want, complete wooden fence, air conditioning in 1st floor, plumbing ~ electric in 1st floor, [and] indoor wooden shutters for all windows." Mr. Hudson went on to state that he wanted certain enumerated appliances, which would cost $4,108.00, and new furniture, which he estimated would cost $6,000.00, for a total of $10,108.00. According to Mr. Hudson's proposal, Mr. Vega should be able to "finish off the 1st floor the way we want it, install the nice carpet and tile, and do all the other jobs previously listed (fence, plumbing, etc., for 1st floor) for about $10,000.00." The basement area which Mr. Hudson wanted to finish as a "nice" living area consisted of approximately 2,000 square feet and had originally been designed as a storage area, with concrete floor and walls. Mr. Vega and Mr. Hudson discussed the proposal and the costs of the changes, but they did not reach an agreement on the cost of the additional work. 3/ Mr. Hudson asked Mr. Vega to leave the job site and cease work on the project on or about July 3, 1993, and Mr. Vega did not perform any work on the Hudson residence after this time. Mr. Hudson terminated Mr. Vega from the project solely because of the dispute with Mr. Vega over the cost of the changes he had requested in his June 7 letter. Mr. Hudson did not complain to Mr. Vega about the quality of the work that had been completed, and, although he thought that the project was getting behind schedule, Mr. Hudson issued a check dated July 2, 1993, which brought the total payments to eighty percent of the original contract price. When Mr. Vega stopped work on the project, the structure contained deviations from the original plans. 4/ Some of the deviations were items shown in the original blueprints which had not been incorporated into the structure; some were items that were not shown in the original blueprints but were incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson; some were deviations in the size of openings to accommodate doors and in the location and size of windows; most were minor deviations in the placement of electrical switches and receptacles or other similar deviations. The construction was, however, generally consistent with the original plans. 5/ There were three items that were significant deviations from the original plans. The most serious deviation concerned the changes made in the dimensions of the structural slab that formed the floor of the second floor balcony off the family room, kitchen, and dining room and the roof of the first floor terrace. The original plans included a second floor balcony with a width of six feet. The Hudsons asked Mr. Vega to increase the width of the balcony, and Mr. Vega called Mr. Sanchez, the structural engineer who had prepared the original plans, and asked if the width of the slab could be increased. Mr. Sanchez approved an extension from the original six feet to eight feet, eight inches, and he advised Mr. Vega of the additional reinforcement that would be needed to accommodate the increased width. On the basis of Mr. Sanchez's approval, Mr. Vega incorporated the additional reinforcement specified by Mr. Sanchez and poured the slab to the requested width of eight feet, eight inches. Even though Mr. Vega consulted a structural engineer, he did not submit revised blueprints to the building department and obtain approval for the structural change before doing the alteration. He was aware that the building code required approval before such a change could be incorporated into a structure and that his actions violated the code. 6/ The second significant deviation from the original plans was Mr. Vega's failure to construct the fireplace shown in the original plans. According to the plans, a fireplace was to be constructed in the living room, on the second floor. Although the roof was completed and the drywall installed, no accommodation had been made for the fireplace in either the wall or the roof. Mr. Vega intended to construct the fireplace and would have done so had he not been told to cease work on the project. The third significant deviation from the original plans concerns the windows installed in the structure. No window permits or product approvals were contained in the permit file for the Hudson project. In addition, some of the windows were not the size specified in the original plans, some were too deep, and some were placed lower than the thirty inch sill height specified in the original plans. Many of the items identified as "deviations" were actually items not shown on the original plans but incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson. Neither the requests for the additional items nor the costs of the items were reduced to writing by Mr. Hudson or Mr. Vega. At the time Mr. Hudson directed him to cease work on the project, Mr. Vega had contracts with subcontractors to provide the labor and materials specified in the original contract. He was prepared to complete the project in accordance with the original plans and for the original contract amount, with adjustments for the extras that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. He was also prepared to correct all deficiencies and code violations in the structure. After he was terminated from the project, Mr. Vega continued to negotiate with Mr. Hudson's attorney to arrive at an agreement for completion of the project that would be satisfactory to Mr. Hudson. In a proposal submitted to Mr. Hudson's attorney in the fall of 1993, Mr. Vega offered to complete the project in seven weeks in accordance with the original plans, as modified to incorporate the changes and upgrades Mr. Hudson had requested in the June 7 letter and the changes and upgrades that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. The total price for completion proposed by Mr. Vega was $56,750.00, which included the cost of the upgrades and extras and the $29,572.00 balance owing under the original contract. Mr. Hudson did not accept this proposal. Instead, he eventually hired a contractor named Robert Krieff, who did some work on the project. In February, 1994, Mr. Hudson took over the building permit himself and hired various subcontractors to work on the project. According to Mr. Hudson, in addition to the $116,400.00 he paid Mr. Vega, he has paid approximately $50,000.00 for work done after he terminated Mr. Vega, and he anticipates spending another $35,000.00 before a Certificate of Occupancy is issued. Mr. Hudson paid off a lien on his property for work done pursuant to his contract with Mr. Vega. A Claim of Lien in the amount of $4,712.00 was filed by Luis A. Roman on October 5, 1993, for drywall hung and finished at the Hudson residence under an arrangement with Mr. Vega. Summary of the evidence. The evidence presented by the Department is sufficient to establish that Mr. Vega willfully violated the building code with respect to the alteration of the width of the second floor balcony. Mr. Vega admitted that he knew he was violating the building code when he extended the width of the second floor balcony beyond the width specified in the original blueprints before submitting revised engineering plans to the county and receiving approval to make the alteration. This violation is one of procedure only, however, and there was no competent evidence presented to establish that Mr. Vega failed to include adequate reinforcement to compensate for the additional width prior to pouring the slab or that there were structural problems with the slab. 7/ The evidence presented by the Department is sufficient to establish that Mr. Vega violated the building code because the work completed by Mr. Vega on the Hudson project contained deviations from the original approved plans. 8/ On the other hand, the evidence presented by the Department is sufficient to establish that this violation is a minor one. The Department's experts testified that the construction done on the Hudson residence by Mr. Vega was generally consistent with the approved plans and that it was commonplace for contractors in Dade County to deviate from the approved plans and later submit revised plans for approval. The evidence presented by the Department is sufficient to establish that Mr. Vega did not file product approvals or obtain window permits prior to windows being installed in the Hudson project. The evidence presented by the Department is not sufficient, however, to establish that these omissions on Mr. Vega's part constituted a violation of section 204.2 of the South Florida Building Code, as alleged in the Administrative Complaint. Although there was some testimony that the building code requires that product approvals be filed and window permits obtained before windows are installed, the applicable code and section were not identified by the Department's witnesses or otherwise made a part of the record. Thus, there is no evidence of the precise obligations imposed on Mr. Vega by the code that was applicable at the time of the Hudson project. As a result, it is not possible to determine whether Mr. Vega fulfilled his obligations under the code. The evidence presented by the Department is not sufficient to establish that Mr. Vega assisted Mr. Armas in engaging in the unregistered or uncertified practice of contracting. There is no evidence in the record that Mr. Armas performed any work on the Hudson project that could be performed only by a licensed contractor. 9/ Notwithstanding the opinions stated by the Department's experts, the evidence presented by the Department is not sufficient to establish that Mr. Vega is guilty of incompetence or misconduct in the practice of contracting as a result of the work done on the Hudson project. The evidence presented by the Department is sufficient to establish that Mr. Hudson suffered financial loss in the amount of $4,712.00, which is the amount Mr. Hudson paid to clear the lien placed on his property by Luis A. Roman. Although this loss is attributable to Mr. Vega's failure to pay Mr. Roman for hanging and finishing drywall in the Hudson residence, the evidence presented by the Department is not sufficient to establish that Mr. Hudson suffered financial loss as a result of the violation with which Mr. Vega was charged and of which he was proven guilty.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board issue a Final Order dismissing Counts I and III of its Administrative Complaint, finding that Gonzalo Vega is guilty of violating section 489.129(1)(d), Florida Statutes (1993), and imposing an administrative fine in the amount of $1,000.00. DONE AND ENTERED this 3rd day of July, 1997, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of July, 1997.

Florida Laws (8) 120.569120.5717.001455.225489.105489.113489.129489.131 Florida Administrative Code (1) 61G4-17.003
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PAUL MCALLISTER, D/B/A GARNETT-MCALLISTER, 78-001552 (1978)
Division of Administrative Hearings, Florida Number: 78-001552 Latest Update: Jun. 29, 1979

Findings Of Fact Respondent Paul McAllister is a certified general contractor and was the qualifying individual for the firm of Garnett-McAllister Associates, Inc., Fort Lauderdale, Florida, in 1977 and until July, 1978. (Stipulation) On April 8, 1977, Respondent's firm entered into a contract with Ray Borchardt, Westchester, Illinois, for the construction of a four-unit apartment building at Lighthouse Point, Florida. The contract provided for a total price of $139,110.00, payable in five payments or "draws" in various percentages of the contract price at specified stages of construction. However, the contract did not specify a time for performance or completion of the building. It contained a clause stating "Any alteration or deviation from above specifications involving extra costs - will be executed only upon written orders, and will become an extra charge over and above the estimate." Respondent obtained a building permit for the construction of the building from the building official, City of Lighthouse Point, Florida, on May 8, 1977. (Petitioner's Exhibits 1, 2) Prior to the commencement of construction, it was determined that foundation pilings for the building were required and therefore Borchardt sent Respondent the sum of $13,519.65 on June 9, 1977, as an additional sum over and above the contract price. At this time, he also sent the first draw in the amount of $20,866.00 even though such payment was not called for until completion of the foundation and "rough in" of plumbing and electric connections. On August 1, 1977, Borchardt paid the second draw of $20,866.00 although the roof was not on, nor had the beam been poured at the time as called for under the contract. Respondent was delayed approximately three weeks by failure of a supplier to provide the second floor concrete planking. On October 24, 1977, Borchardt paid the third draw in the amount of $34,777.00 although construction was not at the stage called for under the contract. On November 22, 1977, Borchardt paid $18,000.00 of the fourth draw and on January 23, 1978, paid the remaining portion of $16,777.00. At that time, the roof was not completed, tile work had not been started, woodwork was incomplete, and kitchen cabinets and vanities had not been installed pursuant to the terms of the contract. Borchardt had made a number of trips from Illinois to Florida during the construction period and was aware that his various partial payments were made in advance of completion of the several construction phases. He had dealt primarily with Edward J. Garnett, president of Garnett-McAllister Associates, Inc., as to the financial aspects of the project. Respondent primarily was a "field" man in charge of supervising construction. Also, Borchardt's son-in- law, Vincent A. Svegel, had moved to Florida in September, 1977, and acted as Borchardt's contact with Respondent's firm after that time. Both Respondent and Garnett informed Svegel in the fall of 1977 that the building would be completed by December 15. (Testimony of Borchardt, Svegel, Petitioner's Exhibit 1) Although during the early part of 1978, five subcontractor liens were filed against the property for work and materials supplied on the project, three of these liens were eventually paid by Garnett-McAllister and the remaining two totaling over $7,000.00 were eventually paid by Borchardt. One of the latter liens was filed by Pompano Roofing Company, Inc. That firm refused to install the roofing tile until paid and the tile therefore "sat on the roof" for approximately five months. On March 13, 1978, Borchardt filed a complaint with Petitioner based on the fact that the work had not been performed according to the draw schedule and liens had been placed on the property. Borchardt also complained to James P. Simmons, the building official of Lighthouse Point about the project delays and claims of lien. As a result, on March 14, 1978, Simmons referred the complaint to Petitioner because Respondent was certified by the state. Petitioner's local inspector, Wallace Norman, issued a Notice of Violation of Section 468.112(2)(e), F.S., to Respondent on March 15, 1978, for diversion of funds based on the filing of liens by suppliers. In a meeting with Respondent and Garnett, Norman asked for an explanation of the situation. They told him that they had been building a house in Davies, Florida, and had used some of the money that Borchardt had paid them to pay suppliers on that house and they had expected to be able to put the money back into the Borchardt project when they sold and realized a profit on the other house. (Testimony of Borchardt, Svegel, Simmons, Norman, Petitioner's Exhibits 7, 9, 10; Respondent's Exhibit 3) During the period between January and March, 1978, some progress was made toward completing the building, including the rough in of the plumbing and electrical systems, installation of inside lath work, installation of tub and shower stalls, and extension of a kitchen area. As late as April 19, 1978, Respondent accompanied Borchardt to a supplier to purchase windows for the building. (Testimony of Svegel, Respondent, Pet. Ex. 3) On May 29, 1978, Svegel, in behalf of Borchardt, notified building official Simmons that Garnett-McAllister Associates, Inc. had been terminated from any further work on the building due to the fact that the building permit had expired and would not be reissued, and requested authorization to finish the building. Simmons thereafter issued a building permit to complete the building to Borchardt on June 21, 1978. He also instructed his staff not to issue any more permits to Respondent due to his "poor track record" and liens which had been filed against the building under construction. Simmons issued the completion permit under the authority of Section 304.3 of the South Florida Building Code, Broward County Edition, which provided that a building permit expires and becomes null and void if work is abandoned at any time for a period of ninety days. Although Simmons considered that the time limit had elapsed because an inspection had not been called for by the builder for ninety days, he erroneously believed that the last inspection had been on January 4, 1978, when, in fact, the city's inspection records show that the plumbing department had made an inspection of rough plumbing on March 27, 1978. Simmons did not notify Respondent of the issuance of the second permit. He considered that he had inherent authority in his position to prohibit issuance of additional permits to Respondent, but didn't consider his action in this regard to be disciplinary in nature because the City of Lighthouse point does not issue contractor's licenses. Therefore, the matter was referred to Petitioner for any action against Respondent's state certification. (Testimony of Simmons, Svegel, Petitioner's Exhibit 3, 4, 11, Respondent's Exhibit 1) At some time prior to obtaining the permit to complete the building, Borchardt had refused to pay the final draw of $27,824.00 to Garnett-McAllister Associates, Inc. because the firm was so far behind on the job. Garnett had told Borchardt that be was selling another home for $80,000.00 and was going to put some of the money he realized from that sale into the Borchardt project. He wanted Borchardt to loan him $20,000.00 and take back a lien on a boat in order to have money in the interim to work on the building. When Borchardt declined to do so, Garnett told him that he could not complete the job. Borchardt also received a call from Respondent to the effect that he would finish the job on his own for $150.00 a week if Borchardt would pay the remaining costs. Borchardt informed him that he would pay nothing further until the job was completed. Garnett had also told Svegel that he had used some $25,000 to $30,000 of the Borchardt funds to construct the house in Davies and that he would put that money back into the firm's business account to use for the Borchardt building when the house was sold. (Testimony of Borchardt, Svegel, Respondent) At the time Borchardt took over completion of construction, the building was approximately 70-75 percent completed. Borchardt paid an additional sum of about $82,000.00 to complete the building which was some $54,000.00 more than the original contract price. However, about $12,000.00 of this sum constituted changes to the original specifications that had been agreed to by Borchardt during the course of construction. Some of these involved changes due to building code requirements, such as the addition of a ramp for the handicapped. Other changes were made on the recommendation of subcontractors or resulted from requests by Borchardt's daughter and son-in-law who were intending to occupy one of the apartments in the building. None of these changes was reflected in a written change order or supplemental agreement to the contract because Borchardt had agreed to the changes and neither party to the contract apparently considered it necessary to formalize these matters. Additional changes in the sum of some $12,000 were made to the building after Borchardt took over construction. These primarily dealt with carpeting, appliances and the like. (Testimony of Borchardt, Svegel, Simmons, Respondent, Stipulation, Petitioner's Exhibits 5, 8) Respondent testified at the hearing and disclaimed knowledge of the financial affairs of the corporation which he claimed were handled exclusively by Garnett. He denied ever abandoning the project and stated that he was unaware, until June 7, 1978, that Borchardt was taking over the construction project to complete. He acknowledged that funds became a problem about mid- January, 1978, and that he then recognized that the contract price had been set at too low a figure because cost overruns were being experienced. He denied diversion of Borchardt's funds to the Davies house, and claimed that his firm did not purchase supplies for that project. He conceded, however, that the firm had one corporate business account from which suppliers on all jobs were paid. Respondent further testified that when funds for the Borchardt building became scarce, profits from other jobs were used in meeting construction costs on the building. He acknowledged receiving a salary of $8,420.00 during the course of construction and said that Garnett had also drawn a sum of approximately $11,000.00 for himself. (Testimony of Respondent) A review of the books of Garnett-McAllister Associates, Inc. by a certified public accountant indicated that they were not well kept and were frequently in error. The auditor's report reflected that the firm had expended at least $80,675.00 in direct construction costs on the project. Certain cost items could not be verified due to the failure of suppliers to respond to the auditor's inquiry. These accounts were reflected on the books of the firm at a total of approximately $1,000.00. (Testimony of Webb, Respondent's Exhibit 4)

Recommendation That Respondent's certification as a general contractor be suspended for a period of 90 days, but that he be permitted to complete any contracts which are uncompleted at the time suspension is effected. DONE and ENTERED this 25th day of April, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32302 Alan C. Brandt, Jr., Esquire 1040 Bayview Drive Fort Lauderdale, Florida 33304 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 2
BOARD OF PROFESSIONAL ENGINEERS vs MICHAEL V. CARR, 90-002420 (1990)
Division of Administrative Hearings, Florida Filed:Panama City, Florida Apr. 24, 1990 Number: 90-002420 Latest Update: Feb. 22, 1991

The Issue The issue in this proceeding is whether Respondent's engineering license should be disciplined for alleged violations of Chapter 471, Florida Statutes.

Findings Of Fact Michael V. Carr, P.E. is a licensed professional engineer in the State of Florida, holding license number PE0026675. He has been engaged in the practice of engineering for more than 15 years. Mr. Carr's area of expertise is in civil and structural engineering. He is not experienced in electrical or mechanical engineering. In 1989, Mr. Carr was employed as a full-time engineer and construction project manager by a local development and construction company. He also operated, on a part-time basis, an engineering business. The purpose of his part-time business was to offer engineering services to people who are experienced in the construction industry or are working with someone who is experienced in the construction industry and have to varying degrees developed their own plans. Respondent also would serve as the construction manager on those projects. During 1989, Respondent performed engineering services on four buildings owned by four different owners. All four buildings, involved relatively simple construction. Three of the buildings, Dr. Zummarraga's office, the Raulerson/Liberty National building, and Bay Podiatry Center, were designs comparable to residential structures. The Eleventh Street Office Park, while a larger structure, was a shell building and a simple structure, as well. Respondent was not retained to provide engineering for the construction of the interior of the Eleventh Street Office Park. In regards to all four buildings, the Respondent was not retained to provide plumbing, electrical or mechanical engineering services. Those items were left to the respective trades involved in the construction of the project. The limited plans submitted for the plumbing, electrical and mechanical aspects of the four buildings met the standard of practice in the Bay County area and were sufficiently complete for the various trades to perform its respective part of each project. Moreover, the simplicity of the construction plans for these four buildings meant that standard construction methods are provided in the Standard Building Code and/or are known in the industry. Such standard construction methods include detail on roof systems, spacing and connections, as well as live load requirements. Therefore, not as much detail needed to be provided on the plans for these projects. It was standard engineering practice in the Bay County area not to include such detail if it was adequately covered in the building code. In each instance, the owners of the buildings contacted Respondent to perform limited engineering services and to act as the construction manager on each project. Except for Mr. Raulerson, each owner had, prior to the time Respondent was hired, worked out some rough plans with a person qualified to create such plans and had a general idea of what type of building they wanted. Mr. Raulerson had drafted a fairly complete set of building plans. The goal of each owner of the four projects was to obtain a set of plans from what the owner already had developed which would at least minimally meet the local building code requirements sufficiently to allow a building permit to be issued for the construction project. In each instance, the Respondent's plans were submitted to the local building code enforcement agency which reviewed and accepted the plans. A building permit was issued for each building project. During the construction of each building, Respondent provided engineering inspections on each project. The plans submitted to the Bay County building department were not as-built plans and were never intended to be 100% complete plans since several of the owners had not made final decisions on a number of details such as roof line or plumbing facilities. 1/ Such open-ended plans were justified by the specific circumstances of each case and the professional judgment of Respondent, especially since Respondent acted as the project manager of the construction project. For purposes of clarity the facts and circumstances surrounding each building and any violations of Chapter 471, Florida Statutes, in regards to each building will be outlined individually. No alleged violations of Chapter 471, Florida Statutes, were established by the evidence unless it is specifically noted below. Zummarraga Building The plans for the Zummarraga building were signed and sealed by Respondent on October 24, 1989. Dr. Zummarraga had contacted Rich Koehnemann of Koehnemann Construction Company to build an office building for him. Mr. Koehnemann sent the doctor to Jeff Robinson, a draftsman in the Bay County area, to work up a draft of the office plans the doctor desired. The doctor or Mr. Koehnemann gave Mr. Robinson a rough sketch of the office building. Mr. Robinson informed the doctor that a structural engineer would have to be involved since the County would require the plans to have the signature and seal of an architect or engineer in order to obtain a building permit. At that point, Respondent was retained to help develop a set of plans for Dr. Zummarraga. Mr. Carr was hired to draft plans for an office building. He was not hired by Dr. Zummarraga to design a building for a specific site. Therefore, no substantial site information, site work, grading or contouring details were provided on the plans for the Zummarraga project. By passing drafts of plans back and fort, a set of plans was devised by Mr. Robinson under the direct supervision and control of Respondent. Therefore, Respondent is not guilty of improperly affixing his seal to the plans for the Zummarraga project. Later, after the structure's plans were finalized, the contractor determined that a detention pond would have to be designed for the site and a DER permit obtained for the pond. Respondent was retained to design a detention pond for the site and worked with DER to meet its extensive permitting requirements for such a pond. See Chapter 17-4, 17-25 and 17-512, Florida Administrative Code. That design was submitted to DER and a permit was issued for the detention pond. The original unsealed set of plans was amended for the building department. The specific details of the more rigid DER requirements, such as site work, grading and contouring, were not included on the plans filed with the building department and the owner did not contract with Respondent to include redundant detail on the building department's plans. Essentially, the building department's plans reflected the location of the detention pond and the area of the wetlands on the property which were subject to DER jurisdiction. Additionally, the plans contained some specifications which guided the contractor on pond requirements and in grading and contouring the site. These notes in conjunction with the DER permit requirements were sufficient to accomplish the building of the detention pond. Therefore, the desire of the owner and the avoidance of unnecessarily redundant detail between the DER permit and the building department's plans justified the lack of any extensive site work detail on the building department's set of plans for the Zummarraga project. The plans devised by Mr. Carr did not contain any architectural work which was not incidental to the engineering work he performed. 2/ Therefore, Respondent is not guilty of improperly affixing his seal to plans depicting work outside his field or of practicing outside of his field. In every instance, the plans of Dr. Zummarraga's office building were of sufficient detail to meet the building department's requirements for the issuance of a building permit, to allow the contractor to construct the project according to the Standard Building Code and to obtain a certificate of occupancy from the building department. Obviously, on these facts, the plans met the standard of practice in the community for the engineering services Respondent was hired to perform. Moreover, the lack of code related, electrical or mechanical details was justified under the facts and circumstances of the Zummarraga project and it was well within the professional judgment of the Respondent to omit such details given the standards of practice in the Bay County area. Raulerson/Liberty National Building The plans for the Raulerson/Liberty National building were signed and sealed by Respondent on July 31, 1989. Mr. Raulerson is an experienced developer in the Bay County area and acts as a general contractor on his own projects. Prior to hiring Respondent, Mr. Raulerson had been working with a local draftsman and Liberty National's architect to create a set of plans for the construction of Liberty National's office building in Bay County. Mr. Raulerson contacted Respondent on the advice of Bayne Collins, a local architect. Mr. Collins advised Mr. Raulerson that his plans were complete and all he needed was an engineer to check the wind loads. 3/ Mr. Raulerson gave Respondent the plans he had developed in conjunction with Liberty National's architect. Mr. Raulerson asked Mr. Carr to go through the plans and do a structural analysis to make sure that wind load requirements were met, that the building was structurally sound and that the building met the requirements for issuance of a building permit. Mr. Carr reviewed the plans and determined that they were an excellent set of plans for a very simple, sound and over-designed structure. He calculated the wind loads for the building and completed a structural analysis of the building. He also made one minor correction to the plans. Mr. Carr thought it ridiculous to put Mr. Raulerson to the expense of copying the Liberty National plans and essentially adopted the plans as his own. In this case, the fact that the plans were not drawn under Respondent's supervision is immaterial since the specific circumstances of the project did not call for such supervision in that the plans were drafted by experienced individuals. The plans were under Respondent's control at the point in time he was hired by Mr. Raulerson and the plans submitted to him for his review and approval, disapproval or amendment. Since copying the plans would be an unnecessary duplication of effort and Respondent did in fact exercise control over the plans by reviewing them before he affixed his seal to them, Respondent is not guilty of improperly affixing his seal to construction plans. The Raulerson/Liberty National plans did not contain any architectural work which was not incidental to the engineering services he performed. Anything in the plans which may be construed as "architectural work" was requested and specified by the owner to be in the plans. Therefore, Respondent is not guilty of improperly affixing his seal to plans depicting work outside his field or of practicing outside his field. The plans did contain a roofing plan which called for pre-engineered trusses. The detail on the plan simply read "pre-engineered trusses." The plans did not contain any requirements relating to who was to design the pre- engineered trusses or requirements for structural submittals on the trusses. In the Bay county area "pre-engineered trusses" means trusses from Fagans, the local truss manufacturer. It is common knowledge, that Fagan's has a licensed engineer on staff who designs all of its pre-engineered trusses from the plans submitted to him. The pre-engineered trusses all have pre-construction documentation available. Also, submittals for the trusses accompany the trusses at the time of their delivery. With such knowledge, it is unnecessary to specify any more information or requirements regarding the truss manufacture on the Liberty National plans. Similarly it was unnecessary to detail that submittals be given to the engineer since such submittals accompanied the trusses. The absence of any more detail was justified by the specific circumstances of the Liberty National project and well within the professional judgment of the Respondent given the nature of the pre-engineered truss market in the Bay County area and the fact that Respondent was the construction manager on the project. As indicated, Respondent also acted as the construction project manager and would visit the construction site about once a week. At the point in time Mr. Raulerson was going to order the trusses, he decided to change the pitch of the roof, Mr. Raulerson did not advise Mr. Carr of his decision. Mr. Carr discovered Mr. Raulerson's change when he visited the construction site. Fortunately, Respondent had the project file with him. With the project file information and the submittals from the truss manufacturer, Respondent checked the load conditions for the changed pitch. No structural concerns were presented due to the change in pitch of the roof. The Liberty National plans were not amended because Mr. Raulerson did not contract for them to be amended. The plans were not required to be amended under Chapter 471, Florida Statutes. Respondent did not commit any violations of Chapter 471, Florida Statutes, in regards to his actions outlined above. Bay Podiatry Center The plans for the Bay Podiatry Center were signed and sealed by Respondent. However, the date the plans were signed and sealed was not included on the plans. It was inadvertently omitted by Respondent. The absence of the date is a de-minimis violation of Chapter 471, Florida Statues, and does not justify the imposition of any formal penalties. However, Respondent should be given a letter of guidance for the violation. Respondent was not brought into the Bay Podiatry Center project until the final draft of the plans was to be done. Up until that time, Dr. Wilkerson, the owner of the project, had worked up preliminary drafts of the project in conjunction with his contractor and a local draftsman. They had developed a building with an attached carport. Mr. Carr did work directly with the draftsman on the final plan. Therefore, the plans were created under the direct supervision and control of Respondent. Since Respondent supervised and controlled the finalization of the project's plans at the crucial time and since the people involved in drafting the plans did not need more supervision and control, Respondent is not guilty of improperly using his seal. There was no clear and convincing evidence which demonstrated that Respondent performed any architectural work which was not incidental to the engineering services he performed. At the time Dr. Wilkerson desired to begin construction and obtain a building permit, he had not decided on a final roofing system. Therefore, the final plans called for the use of pre-engineered trusses and did not have a great amount of detail on a roof framing plan. There was some detail provided on the page of the plans detailing the wall section of the building. This page provided sufficient detail for a competent contractor to construct the building according to code. In fact, the building was so constructed and a certificate of occupancy was issued for the building upon its completion. Again the trusses would come from Fagans. Petitioner did in fact review submittals from Fagan's truss engineer for the pre-engineered trusses used on the Bay Podiatry Center. Included in those submittals was a roofing plan in which the trusses were numbered to fit the sequence shown in the roofing plan. Respondent made sure the trusses and roof system were structurally sound. However, the owner did not contract with Respondent to amend the building department's plans. Chapter 471, Florida Statutes does not require such an amendment. Given the truss market in the Bay County area, the knowledge of Respondent regarding that market, the fact that a decision regarding a roof line had not been made when the plans were sealed, and that it was appropriate to leave such a decision for later in the construction process, no further detail was required in specifying the roof system for this project. No clear and convincing evidence was presented that demonstrated Respondent was negligent in his specifications on the roof system. The only exception to the above was that Respondent did not specify the material of the trusses over the carport. Such information is not supplied by the Code and therefore must be supplied by the engineer. The oversight was caught by the contractor when he was preparing to order the trusses. The contractor contacted Mr. Carr. Mr. Carr determined what the appropriate truss material should be and informed the contractor. The inadequacy of the plans was resolved in less than ten minutes. The omission of such a detail is negligent on the part of Respondent and is a violation of Chapter 471, Florida Statutes. However, on these facts, the omission of the detail is minor. Most of the light, plumbing and mechanical fixtures were prelocated by the owner prior to the time Respondent was hired. Respondent did not purport to draft plumbing, electrical or mechanical plans in detail in the final plan. Except in one respect, the detail was sufficient to guide the respective trades in the performance of their work and no more detail was required. The only exception was that Respondent approved a special detail of the hub drain/trap primer which was not in accordance to code. Since Respondent provided a special detail which did not meet the code requirements and which was not demonstrated to be justified by the circumstances of the Bay Podiatry project, he is guilty of negligence in the drawing of the Bay Podiatry plans in that aspect. Given the fact that this is a very small error in a larger project and that the drain was put in according to code during the construction of the building, Respondent's violation is a minor one. Finally, the draftsman, without instructions from Respondent, put some plumbing and mechanical notes in the plans which clearly did not relate to the project. Respondent did not catch the inclusion of the notes and sealed the plans with the superfluous notes in them. However, it was obvious that the notes did not relate to the project and the trades involved ignored them. The notes did not cause any problems during the construction and were not shown to be inimical to the public health and safety. Therefore, while the inclusion of the notes was sloppy work, there was no negligence shown on the part of Respondent. Eleventh Street Office Park The plans for the Eleventh Street Office Park were signed and sealed by Respondent on January 31, 1989 The Eleventh Street Office Park project demonstrates best the dynamism involved in an evolving construction project. Often, as with the Eleventh Street project, an owner is not sure of the best method or design (usually determined by lowest cost) to utilize prior to construction or whether he wants to go forward with the expense of construction of a building given certain designs. On the Eleventh Street project three plans were developed, beginning with a three story structure with structural steel and precast walls, and ending with a large, one story, cement block structure on a cement slab. All the plans were for a shell building and did not include any floor plan. Preliminary rough drawings were completed by a draftsman who was hired by the project's owner. Respondent reviewed these rough drafts and over the course of several weeks made numerous structural changes. After the plans were re-drawn to Respondent's satisfaction, he submitted them to the building department in order to obtain a building permit. There is no question that the plans for the Eleventh Street project were drawn under Respondent's direct supervision and control. Therefore, Respondent is not guilty of improperly using his seal. The plans submitted to the building department were not intended to be complete. For instance, the owner had not decided where to locate the restrooms in the building. However, the owner, for unspecified reasons, wanted to proceed with obtaining a building permit. With that decision open, the detail for the plumbing aspects of the plan were not intended to be complete or to match as to specifics. Such limited detail was intended only to place the building department and the contractor on notice that some consideration had to be given to the upcoming plumbing. The same considerations applied to the electrical and mechanical aspects of the plans. All of the evidence concerning deficiencies in the electrical design of the Eleventh Street Office Park was based on Petitioner's expert's review of a single sheet of plans obtained from the building Department. This sheet is mysterious as to its origins and relationship to the Eleventh Street project. The sheet was not prepared by Respondent, did not bear his seal, lacked the fire department's approval which was present on other pages of the project's plans, and was a different size paper than those sealed by Respondent. There was no substantial evidence which demonstrated Respondent had prepared this sheet or that the sheet reflected the electrical plans used in the Eleventh Street project. The absence of extensive detail or the provision of extraneous notes on the electrical, mechanical and plumbing aspects of the plans were justified by the fact that the owner of the project had not made up his mind in regards to those details, such decisions could be determined later in the construction process, the Eleventh Street project was a shell building and there was sufficient detail for the licensed trades to perform their tasks when the time came and the decisions were made. The incompleteness of these plans in that regard was clearly justified by the specific circumstances of the Eleventh Street project. Therefore, Respondent is not guilty of violating Chapter 471, Florida Statutes. As with the Bay Podiatry project, the only exception to the above was that the hub drain/trap primer detail was not in accordance with the building code. For the reasons stated in regards to the Bay Podiatry project, the provision of the hub drain detail constitutes negligence in the practice of engineering in violation of Section 471.033(1)(g), Florida Statutes. Again the violation is a minor one. Similarly, as with the other three projects, no substantial evidence was presented that Respondent performed any architectural services in relation to the Eleventh Street project which were not incidental to the engineering services he performed. There was a great deal of debate among the experts as to the adequacy of the structural aspects of the Eleventh Street Office Park and whether they met the standards of practice for engineers. Most of the debate centered on how much detail needed to be placed on the plans and whether the detail provided was sufficient for a contractor to build a safe building. The better evidence demonstrated that the amount of detail on the plans was sufficient to enable a contractor to build a safe building. The detail which was not contained on the plans was contained in the building code and did not need to be included on the plans. Such a practice comports with the standard of practice in the Bay County area and is a specific circumstance of a project which would enable a professional engineer to exercise his judgment and not include such detail. 4/ Moreover, although the calculations were not contained on the plans, Respondent did, in fact, determine the structural soundness of the Eleventh Street project. Therefore, Respondent is not guilty of violating Section 471.033(1)(g), Florida Statutes. The only exception to the above is that Respondent was negligent in specifying the type of mortar to be used in the concrete walls. In essence Respondent specified three different types of mortars. These mortars significantly differed as to each mortar's respective strength. Use of an improper mortar in the concrete walls can effect the strength of the wall and cause them to be unsafe. This inconsistency in detail or specifications differs from the inconsistency in details or specifications where such details or specifications obviously do not apply to the project or where such details or specifications have no contrary reference in the plans. The latter two cases while showing sloppy work are not necessarily indicative of negligence and depend greatly on the surrounding facts and circumstances before a finding of negligence can be made. The inconsistency with the mortar is indicative of negligence since a contractor may very well use the wrong mortar on a project. In this case, the inconsistency did not become a problem and Respondent was present as the project manager to handle any problem which may have arisen. Therefore, the violation of Chapter 471, Florida Statutes, is moderate to minor.

Recommendation That the Department enter a Final Order finding Respondent guilty of five violations of Chapter 471, Florida Statutes, assessing a total fine of $750.00 and placing the Respondent's license on probation for a period of one year, during which Respondent should be required to take and pass a course or courses on the proper methods of plan drafting for the four violations involving negligence; and issuing a letter of guidance for the violation involving the date. DONE and ENTERED this 22nd day of February, 1991, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of February, 1991.

Florida Laws (8) 10.001120.57455.227471.003471.005471.025471.031471.033
# 3
FLORIDA REAL ESTATE COMMISSION vs. VICTOR L. CONTESSA, 84-002805 (1984)
Division of Administrative Hearings, Florida Number: 84-002805 Latest Update: Aug. 13, 1985

Findings Of Fact At all times relevant hereto, Respondent, Victor L. Contessa, (Contessa) was licensed as a real estate broker in the State of Florida, having been issued license Number 0016808. The last license issued to Respondent was as a broker, c/o Cavalier Southern Realty, Inc., 4343 Ridgewood Avenue, Port Orange Florida, 32019. At all times material hereto, Contessa was owner and president of Cavalier Development and Building Corporation. In 1983, Charles Hill purchased a lot in Port Orange, Florida, more particularly described as Lot 29, Phase One, Cypress Grove. In June of 1983, Charles Hill wished to have a house constructed on his lot. Mr. Hill spoke with Contessa regarding the construction of the house. After reviewing plans with Contessa, Hill entered into a written Building Agreement with Contessa whereby Contessa agreed to construct a house for Hill for $50,000.00, plus extras. At the time he signed the Building Agreement, Hill believed that Contessa was a licensed building contractor. He based this belief upon representations made by Contessa to Hill that Contessa was a licensed building contractor. The Building Agreement, dated June 4, 1983, listed Cavalier Development and Building Corporation as the contractor and was signed by Contessa as president of Cavalier Development and Building Corporation. Contessa was not a licensed building contractor when he signed the Building Agreement. In order to have the house constructed as set forth in the Building Agreement, it was necessary for Contessa to hire a licensed building contractor. Contessa contacted Donald E. Welch, a licensed residential contractor. Contessa represented to Welch that Contessa's company, Cavalier Development and Building Corporation, was the owner of Hill's lot. Based on that representation, Contessa entered into a Building Agreement with Welch to have Welch construct the house for $42,500.00. Welch did not become aware that the lot in question was owned by Hill and not by Contessa or Cavalier Development and Building Corporation until October 25, 1983, when Welch attempted to pull a building permit. At that time, Contessa advised Welch that the owner's name was Charles B. Hill. Hill paid Contessa a total of $45,000.00 for construction of the house. In January 1984, Welch slowed construction on the house because Contessa did not pay him his construction draws when they were due. Until this time, Contessa had instructed Hill not to discuss construction with any of the workmen on the site, but to bring any concerns directly to Contessa. Additionally, Contessa had instructed Welch not to deal directly with Mr. Hill, but instead to discuss all construction matters directly with Contessa. Because of the slowdown in construction, Hill and Welch discussed the matter between themselves. It was at this time that Hill learned that Welch was the licensed contractor, and not Contessa. Hill then began dealing directly with Welch. Welch completed the construction upon payment of $8,842.00 paid directly by Hill to Welch. Contessa, in the name of Cavalier Development and Building Corporation filed a mechanics lien as a contractor against the Hill property on May 16, 1984.

Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Professional Regulation, Division of Real Estate, enter a final order suspending the license of Victor L. Contessa for a period of five (5) years and assessing an administrative fine against Victor L. Contessa in the amount of $1,000.00. DONE AND ENTERED this 13th day of August, 1985, at Tallahassee Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of August, 1985. COPIES FURNISHED: James H. Gillis, Esquire Staff Attorney Department of professional Regulation Division of Real Estate 400 West Robinson Street Orlando, Florida 32801 Victor L. Contessa Box 566 Port Salerno, Florida 33492 Victor L. Contessa 101 Santa Lucia Avenue West Palm Beach, Florida 33492 Salvatore A. Carpino, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Harold Huff, Director Division of Real Estate 400 West Robinson Street Orlando, Florida 32801

Florida Laws (2) 120.57475.25
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOSE R. GARCIA, D/B/A GABROS CONSTRUCTION, 76-000410 (1976)
Division of Administrative Hearings, Florida Number: 76-000410 Latest Update: Jun. 03, 1977

The Issue Whether Jose Ramone Garcia obtained a building permit for the purpose of aiding an uncertified or unregistered person to evade the provisions of Part 2, Chapter 468, Florida Statutes.

Findings Of Fact Jose Ramone Garcia holds a license as a general contractor issued by the Florida Construction Industry Licensing Board and is licensed as doing business as Gabros Construction. Jose Ramone Garcia, on or about April 26, 1974, obtained a building permit No. 74-1006 issued by Collier County Building Department to build a home at 378 Seabee Avenue, Vanderbilt Beach, Florida. The home at 378 Seabee Avenue, Vanderbilt Beach, Florida, was built by Roger Dulaney, an unlicensed person, who had contracted verbally to build said home with Mr. William E. Young, the owner of the real property. Jose Ramone Garcia obtained the building permit No. 74-1006 with money given to him by Roger Dulaney, but Jose Ramone Garcia did not receive any compensation for his assistance to Roger Dulaney. Jose Ramone Garcia did not contract with William E. Young to build the home at 378 Seabee Avenue, Vanderbilt Beach, Florida. Jose Ramone Garcia did not contract with any of the subcontractors or materialmen for services or goods used in the construction of the home at 378 Seabee Avenue, Vanderbilt Beach, Florida. Jose Ramone Garcia was frequently at the construction site at 378 Seabee Avenue and did oversee the construction which Dulaney directed. Garcia did insure that all construction work done was in accordance with the specifications and plans and the building code of Collier County. All work on the home at 378 Seabee Avenue was inspected and approved by the building authorities of Collier County. With several minor adjustments, the construction was acceptable to the owners. The major problem involved with the house constructed at 378 Seabee Avenue involved the contract price of the home arrived at between Dulaney and Young. Garcia did not negotiate the contract of the construction of the house at 378 Seabee Avenue and had no knowledge of the contract price. The dispute between Dulaney and Young resulted in court action between these parties which resulted in a judgment by the court in the favor of Dulaney. Jose Ramone Garcia has been unable to obtain a building permit as a contractor in Collier County since the filing of the Administrative Complaint in January, 1976. Garcia currently resides in Collier County.

Recommendation Because the licensing privilege of Garcia has already been effectively suspended for 14 months, which is a substantial period of suspension, the Hearing Officer does not feel that a further suspension would be of any benefit. The Hearing Officer would recommend that a civil penalty of $500 be assessed against Garcia based upon the foregoing findings of fact and conclusions of law. DONE and ORDERED this 29th day of March, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire Jacobs, Sinoff, Edwards, Alford & Burgess Post Office Drawer I Fernandina Beach, Florida 32034 Jose Ramone Garcia 9341 S. W. 38th Street Miami, Florida J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DOMINIC D`ALEXANDER, 82-002858 (1982)
Division of Administrative Hearings, Florida Number: 82-002858 Latest Update: Apr. 24, 1984

Findings Of Fact At all times pertinent to the issues in this hearing, Respondent was a licensed building contractor, whose license is No. CBC014467. His certification as an individual by the Florida Construction Industry Licensing Board was initially dated August 16, 1979. In February, 1981, he requested his second license be registered qualifying Jeff Webb Homes, Inc.; and in September, 1982, the license was changed from Jeff Webb Homes, Inc., to Intervest Construction, Inc. On April 23, 1981, Anna Ray McClellan contracted with Regency Central, Inc., for the construction and purchase of a single family residence located at Lot 5, Devonwood Subdivision, Volusia County, Florida. David L. Martin is president of Regency Central, Inc., and neither he nor Regency Central, Inc., are or have ever been registered or certified by the Florida Construction Industry Licensing Board to engage in the business of contracting in the State of Florida. On June 5, 1981, Respondent applied for a residential construction permit for Lot 5, Devonwood Subdivision, listing Regency Central, Inc., as the owner of the property, and himself, with License No. CBC014467, as the contractor. Actual contracting for the construction at Lot 5, Devonwood Subdivision, was accomplished by Regency Central, Inc. Three separate addenda to the construction/purchase contract calling for modifications to the specifications of construction were signed, not by Respondent, but by David L. Martin for Regency Central, Inc. Major subcontracts on the construction including plumbing, electrical, and heating and air conditioning, were entered into between the subcontractors and Regency Central, Inc., and not Respondent. Subcontractors looked to Regency Central for payment, and not to Respondent. A claim of lien filed on ,September 9, 1981, for central air conditioning and heating work on the property in question reflects the work was done under contract with Regency Central, Inc., David L. Martin, President. During construction of the house, Ms. McClellan visited the construction site several times a week at different hours of the day. She recalls seeing Respondent in the area only twice, the first time being the day the contract for purchase was signed, and the second being the day the slab was poured. Her dealings at the site were with the supervisor, Dan Haley, who indicated to her that he worked for Regency Central, Inc. Respondent was interviewed by Philip T. Hundemann, an investigator for the Florida Department of Professional Regulation, in late March, 1982, at Respondent's home. During the course of the interview, Respondent admitted that he met David L. Martin when Martin rented office space in a building that Respondent had constructed and owned. During the course of conversations, Martin suggested to Respondent that he, Martin, had ninety-nine lots available for building and that if Respondent would pull the construction permit for the Lot 5 project, he would get a contract from Martin to build on the other ninety- nine lots. Respondent admitted that he did not supervise the contract, that he did pull the permit, and that he was in violation of the law and had prostituted his license. His defense was, at that time, that he was hungry to get a big construction contract with Martin. Though after he pulled the permits his agreement was to work on the site for the rate of ten dollars per day with the supervisor, Mr. Haley, he was there only infrequently. Respondent now modifies the admissions made previously to Mr. Hundemann. He now states he was heavily involved with the construction project on a daily basis either in his office or on the construction site, not only as a contractor, but also as sales broker. While he admits what he did was in violation of the law and was foolish, he did not intend to break the law. Respondent's involvement with Ms. McClellan's project was not as contractor as indicated in the permit he pulled. He had very little contact with that project until Martin abandoned the project and left the area.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's, Dominic D'Alexander's, license as a certified building contractor be suspended for one year, but that, upon the payment of a $500 administrative fine, the execution of the suspension be deferred for a period of three years, with provision for automatic recission. RECOMMENDED this 21st day of March, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of March, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Dominic D'Alexander Post Office Box 4580 South Daytona, Florida 32021 Mr. James Linnan Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (7) 120.57489.101489.111489.117489.119489.129489.131
# 6
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs CLIFFORD GRANDMONT, 06-003278 (2006)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 31, 2006 Number: 06-003278 Latest Update: Feb. 27, 2007

The Issue The issue is whether Respondent undertook to act as a contractor without a license as charged in the Administrative Complaints, and if so, what disciplinary action should be taken.

Findings Of Fact Pursuant to Section 20.165, the Division of Professions is a subordinate unit of the Department of Business and Professional Regulation (the Department). The Department provides administrative support, including prosecutorial support to the Construction Industry Licensing Board (the Board), which is also located within the Department. Mr. Grandmont is not currently licensed as a State Registered or State Certified Contractor in this state, nor has he ever been licensed by the Board. Mr. Grandmont's last known address is 355 China Berry Circle, Davenport, Florida. He was provided notice of the hearing at that address, and at 7733 Park Road, Charlotte, North Carolina 28210, which is the address he used when demanding a hearing on disputed facts in two of these cases. In DOAH Case No. 06-3279, he provided no address in his demand for a hearing. All attempts by U. S. Mail to notify Mr. Grandmont of the hearing, were returned. Mr. Grandmont is deemed to have known of the time, date, and place of the hearing, and is deemed to have waived his appearance at the hearing. On November 11, 2005, subsequent to Hurricane Wilma, Robert L. Coe, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged mobile home. He provided a written estimate of $10,500. The estimate contained a list of 11 items requiring repair, and stated that he would accomplish the repair of them. He demanded a $4,200 down payment, which Mr. Coe provided in a draft drawn on Fidelity Cash Reserves, and dated November 11, 2005. Mr. Coe never saw Mr. Grandmont again. The repairs set forth in the written estimate were not accomplished. The draft, however, was negotiated by Mr. Grandmont. On November 12, 2005, subsequent to Hurricane Wilma, Joseph Webster, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged residence. Mr. Grandmont discussed charging $13,500 in return for repairing Mr. Webster's residence. After negotiations, Mr. Grandmont agreed to do it for $11,500. No written estimate or contract was prepared. Mr. Grandmont demanded $5,750 payment in advance. Mr. Webster rounded off the down payment to $6,000 and presented Mr. Grandmont an official check of the Taunton Federal Credit Union, of Taunton, Massachusetts, for that amount. The check was negotiated by Mr. Grandmont, but the promised repairs were not accomplished. On November 4, 2005, subsequent to Hurricane Wilma, Ella Arseneau, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to replace her roof. He provided an estimate of $5,500 in return for repairing Ms. Arseneau's residence. He demanded that she pay $3,500 in advance, which Ms. Arseneau provided by presenting Mr. Grandmont a check for $3,500, drawn on an account in Wachovia Bank. The check was negotiated by Mr. Grandmont, but the roof was not repaired as promised. Mr. Coe is 78 years of age, Mr. Webster is 85, and Ms. Arseneau is 77.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation impose a fine upon Clifford Grandmont in the amount of $30,000. DONE AND ENTERED this 28th day of November, 2006, in Tallahassee, Leon County, Florida. S HARRY L. HOOPER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th of November, 2006. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Clifford Grandmont 7733 Park Road Charlotte, North Carolina 28210 Nancy S. Terrel, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Simone Marstiller, Secretary Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (6) 120.5720.165489.105489.113489.127489.13
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs MARK P. STANISH, 95-004534 (1995)
Division of Administrative Hearings, Florida Filed:Crystal River, Florida Sep. 13, 1995 Number: 95-004534 Latest Update: Jul. 17, 2013

Findings Of Fact The Petitioner is an agency of the State of Florida charged with regulating the licensing of contractors in Florida and regulating the practice of contracting of all types. Specifically, the Petitioner is responsible for enforcing law which prohibits unlicensed persons from engaging in the business of contracting, or advertising themselves or business organizations as available to engage in contracting, without proper licensure. The Respondent is a citizen of the State of Florida, who has embarked on a business of representing owners who desire to construct residences, acting as the agent of those owners in arranging for materials, labor, subcontractors, and the financing of construction. Upon the decision by the owner to construct a residence, the Respondent engages in drafting plans, to some extent, arranging for subcontractors, overseeing the details of the work and any changes or alterations in the work and plans as the project proceeds. The owner in this arrangement does not obtain workers' compensation coverage for the Respondent, as would be the case if the Respondent was an employee of the owner, nor does the owner withhold F.I.C.A. taxes from monies due the Respondent for his services. The Respondent is not licensed as a contractor in the State of Florida. On May 11, 1995, the Respondent signed a contract (hereinafter the "Kassiris Contract") with owner Gus Kassiris, to oversee the erection and construction of a new residence for Mr. Kassiris. The Respondent was to perform the following duties, pursuant to the Kassiris Contract: to make recommendations as to which subcontractor to hire; to inspect progress and review payments; consultations and solutions on construc- tion project; to engage in manpower tracking and coor- dination of resources; monitoring of contract compliance; to provide punch list services; and to engage in the preparation and de- fense of change orders, as well as cost accounting. The "punch list services" mean that the Respondent was to engage in insuring that no work was left undone or done incorrectly at the end of the project. The Respondent admitted that he conducted all inspections on the project and reviewed all requisitions for payment from the subcontractors. The amount he charged for his services was roughly equivalent to the amount a licensed contractor would charge for similar services. The Kassiris Contract did not meet the conditions for a homeowner's exemption, found in Section 489.103(7), Florida Statutes. Specifically, the Kassiris Contract did not provide that the Respondent would work under the supervision of the homeowner. In fact, the Kassiris Contract provided that if the homeowner wanted changes made in the specifications, he could request a change order. The Kassiris Contract also did not provide that the homeowner would deduct F.I.C.A. and withholding taxes from the Respondent's fees or wages, as required in the homeowner's exemption standards. There was no provision requiring that the homeowner provide workers' compensation, as required by the statute, in order to make out the elements of the homeowner's exemption (from the requirement of having a contractor's license). The conditions for exemption from licensure were also not met in the implementation of the Kassiris Contract. Specifically, the homeowner did not act as his own contractor and provide all of the material supervision himself. Although he denies it, in fact, the Respondent negotiated the contracts with the subcontractors and, during the course of performance of the Kassiris Contract, the Respondent approved plan changes for the project, without the involvement or consultation of the owner. The Respondent acted in the capacity of a contractor in the implementation of the contract by overseeing most details of construction of the residence. He performed the on-site inspections, dealt with subcontractors, approved the manner in which work was being performed, approved payment of subcontractors, and, in general, closely managed all details of the contracting effort. Practically, the only involvement the owner had, other than being present on the site frequently, was that the owner actually wrote the checks to pay the subcontractors and delivered them to the Respondent, who, in turn, delivered them to the subcontractors. The owner obtained the building permit at the commencement of the project. The Respondent advertised in the Citrus County Chronicle, a newspaper of general circulation, on or about June 25, 1995, that he offered services for hire as a construction consultant and for project management. On or about June 27, 1995, he entered into a contract with Paul and Valerie Stamper (hereinafter the "Stamper Contract"). The Respondent was thus charged with overseeing the erection and construction of a residence located at Lot 15 of Laurel Oak Estates Subdivision in Citrus County, Florida. He acted in the capacity of a contractor in the negotiation and formulation of this contract. According to the Stamper Contract, the Respondent's responsibilities were to include the following: make recommendations as to which subcon- tractor to hire; conduct progress inspections and payment reviews; consult concerning construction problems and arrive at solutions; engage in manpower and tracking and coor- dination of resources; monitor contract compliance; provide "punch list" services; prepare and defend any change orders; engage in cost accounting. The terms of the Stamper Contract indicate that the residence to be constructed was to be purveyed to the owner, rather than a case of the owner being the contractor actually creating the product. In order for the above- referenced exemption to apply, the homeowner must be the party functioning as a contractor on his own behalf. It is noteworthy in this regard that the Stampers gave the Respondent a $3,000.00 deposit. The Stampers later decided that they did not wish to proceed with the contract and requested return of that deposit. The Respondent refused to return the deposit money, although acknowledging that the Stamper Contract was no longer in effect. In his letter to the Stampers, responding to their request for return of the deposit, he proposed, instead, that they continue to proceed with the contract and the construction of the residence, which the Stampers no longer wished to own and occupy, in order that they could sell it. The intention to construct a residence for sale to another party directly belies the possibility that the homeowner can be his own contractor, constructing a residence for his own use in compliance with the homeowner-exemption law. It shows an intention to engage in contracting by the Respondent. The existence of facts supporting this exemption is also belied because the Respondent, in his contract with the Stampers, did not contract to have F.I.C.A. or income taxes withheld from any paychecks due him from the Stampers, nor did the Stampers contract to provide workers' compensation coverage for the Respondent. The contract also did not provide that the owners, the Stampers, would act as their own contractors and provide all material supervision themselves. In fact, the Respondent was to provide supervision. The Petitioner is responsible for enforcing the prohibition against unlicensed contracting in order to protect the public. There are frequent problems with unlicensed contractors in Florida in terms of their competence to provide quality work and their willingness to do so, as well as outright fraud and harm to the public. The contracts which unlicensed contractors enter into are illegal and unenforceable. Homeowners who contract with unlicensed contractors are not eligible for recovery under the Construction Industry Licensing Recovery Fund. On July 2, 1995, the Respondent again advertised in the Citrus County Chronicle, advertising himself as available to manage the construction of residences. Based upon this notice and other information, the Petitioner issued a Notice to Cease and Desist to the Respondent, ordering him to cease and desist the unlicensed practice of contracting. The Respondent contends that he is not a contractor and that he is, instead, a project manager or consultant and, therefore, not governed by the statutory provision authorizing the Notice to Cease and Desist.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is RECOMMENDED that a Final Order be entered imposing an administrative fine in the amount of $5,000.00 against the Respondent. DONE AND ENTERED this 23rd day of February, 1996, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of February, 1996. APPENDIX TO RECOMMENDED ORDER CASE NO. 95-4534 Petitioner's Proposed Findings of Fact 1-9. Accepted. 10. Rejected, as constituting a conclusion of law. 11-14. Accepted. 15. Rejected, as being irrelevant. 16-17. Accepted. 18. Accepted, except for the next to the last sentence, which constitutes a conclusion of law. 19-20. Accepted. 21. Rejected, as constituting a conclusion of law. 22-31. Accepted. Respondent's Proposed Findings of Fact 1-2. Accepted. Rejected, as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected, as contrary to the unrefuted evidence and as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected, as not in accordance with the greater weight of the evidence and as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected, as constituting a conclusion of law, but to the extent it might be a proposed finding of fact, as not in accord with unrefuted evidence of record and as subordinate to the Hearing Officer's findings of fact on this subject matter. Rejected, as not representative of the unrefuted evidence of record and as subordinate to the Hearing Officer's findings of fact on this subject matter and as not itself being dispositive of material issues. Rejected, as contrary to the greater weight of the evidence and as not being materially dispositive. Rejected, as contrary to the greater weight of the evidence and as subordinate to the Hearing Officer's findings of fact on this subject matter and as, in part, being a conclusion of law and not a proposed finding of fact. 10-12. Rejected, as constituting a conclusion of law. COPIES FURNISHED: Donna Bass, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0750 Mr. Mark P. Stanish 6041 Town Court Springhill, FL 34606 Richard Hickok, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, FL 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792

Florida Laws (9) 120.57455.228489.103489.105489.127489.128489.141775.082775.083
# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs CLIFFORD GRANDMONT, 06-003279 (2006)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 31, 2006 Number: 06-003279 Latest Update: Feb. 27, 2007

The Issue The issue is whether Respondent undertook to act as a contractor without a license as charged in the Administrative Complaints, and if so, what disciplinary action should be taken.

Findings Of Fact Pursuant to Section 20.165, the Division of Professions is a subordinate unit of the Department of Business and Professional Regulation (the Department). The Department provides administrative support, including prosecutorial support to the Construction Industry Licensing Board (the Board), which is also located within the Department. Mr. Grandmont is not currently licensed as a State Registered or State Certified Contractor in this state, nor has he ever been licensed by the Board. Mr. Grandmont's last known address is 355 China Berry Circle, Davenport, Florida. He was provided notice of the hearing at that address, and at 7733 Park Road, Charlotte, North Carolina 28210, which is the address he used when demanding a hearing on disputed facts in two of these cases. In DOAH Case No. 06-3279, he provided no address in his demand for a hearing. All attempts by U. S. Mail to notify Mr. Grandmont of the hearing, were returned. Mr. Grandmont is deemed to have known of the time, date, and place of the hearing, and is deemed to have waived his appearance at the hearing. On November 11, 2005, subsequent to Hurricane Wilma, Robert L. Coe, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged mobile home. He provided a written estimate of $10,500. The estimate contained a list of 11 items requiring repair, and stated that he would accomplish the repair of them. He demanded a $4,200 down payment, which Mr. Coe provided in a draft drawn on Fidelity Cash Reserves, and dated November 11, 2005. Mr. Coe never saw Mr. Grandmont again. The repairs set forth in the written estimate were not accomplished. The draft, however, was negotiated by Mr. Grandmont. On November 12, 2005, subsequent to Hurricane Wilma, Joseph Webster, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to repair his damaged residence. Mr. Grandmont discussed charging $13,500 in return for repairing Mr. Webster's residence. After negotiations, Mr. Grandmont agreed to do it for $11,500. No written estimate or contract was prepared. Mr. Grandmont demanded $5,750 payment in advance. Mr. Webster rounded off the down payment to $6,000 and presented Mr. Grandmont an official check of the Taunton Federal Credit Union, of Taunton, Massachusetts, for that amount. The check was negotiated by Mr. Grandmont, but the promised repairs were not accomplished. On November 4, 2005, subsequent to Hurricane Wilma, Ella Arseneau, of Lake Worth, Florida, was contacted by Mr. Grandmont, who offered to replace her roof. He provided an estimate of $5,500 in return for repairing Ms. Arseneau's residence. He demanded that she pay $3,500 in advance, which Ms. Arseneau provided by presenting Mr. Grandmont a check for $3,500, drawn on an account in Wachovia Bank. The check was negotiated by Mr. Grandmont, but the roof was not repaired as promised. Mr. Coe is 78 years of age, Mr. Webster is 85, and Ms. Arseneau is 77.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation impose a fine upon Clifford Grandmont in the amount of $30,000. DONE AND ENTERED this 28th day of November, 2006, in Tallahassee, Leon County, Florida. S HARRY L. HOOPER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th of November, 2006. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Clifford Grandmont 7733 Park Road Charlotte, North Carolina 28210 Nancy S. Terrel, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Simone Marstiller, Secretary Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (6) 120.5720.165489.105489.113489.127489.13
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILLIE F. DANIELS, 86-005031 (1986)
Division of Administrative Hearings, Florida Number: 86-005031 Latest Update: Apr. 30, 1987

The Issue The issue in this proceeding is whether Willie Daniels violated sections 489.129(1)(d) and (e) F.S., as alleged in the administrative complaint, by willful violation of a local building code and aiding and abetting an unlicensed person to evade any provision of Chapter 489. At the hearing the material facts were uncontroverted.

Findings Of Fact Willie F. Daniels is now, and was at all times relevant, licensed as a roofing contractor by the Florida Construction Industry Licensing Board. He holds license #RC 0027954 and does business as "Daniels Roofing', a sole proprietorship. He has been doing roofing in the Orlando, Florida area since 1954. Willie Daniels first met Thomas Dahlman when Dahlman came to his house trying to sell windows. Dahlman told him that he did all kinds of work, including windows, roofing and painting. Later Dahlman called him and said he had a roofing job that he wanted Daniels to do and that he would take him out to the house. The house belonged to Chris Correa and was located at 4421 Sebastian Way, in Orlando. Dahlman bought the materials for the job and Willie Daniels provided a day and a half labor on the roof. He was paid approximately $600.00 by Dahlman. Chris Correa was initially contacted by an agent for Thomas Dahlman who was trying to sell solar heating devices. When she told him she really needed a new roof, he said his boss could arrange that. Dahlman arranged for her loan to pay for the roof and arranged for the labor to be done by Willie Daniels. Chris Correa paid Thomas Dahlman $3,000 for the roof. About three days after the roof was completed, on February 18, 1986, she signed a contract for the roof work with Dahlman Enterprises, Inc. The contract is signed Thomas Dahlman and by Ms. Correa. Willie Daniels was not a party to the contract. The City of Orlando has adopted the Standard Building Code, including the following provision relating to permit applications: Section 105 - Application for Permit - When Required Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, ... or to cause any such work to be done, shall first make application to the Building Official and obtain the required permit therefor. * * * No permit was applied for or obtained for the roofing job on Chris Correa's house. Willie Daniels assumed Thomas Dahlman was a licensed contractor because Dahlman told him he was in the business of doing roofing, painting, installing windows and similar work. He did not ask Dahlman if he was licensed. Dalhman was, in fact, not a licensed contractor.

Florida Laws (3) 120.57455.225489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer