DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs IAN TUTTLE, 16-003900 (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 13, 2016 Number: 16-003900 Latest Update: Feb. 07, 2017

The Issue The issues determined in this proceeding are whether Respondent engaged in construction contracting without a license as alleged in the Amended Administrative Complaint; and, if so, the appropriate penalty.

Findings Of Fact Parties Petitioner is the state agency responsible for regulating the practice of construction contracting pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. Petitioner has jurisdiction over the unlicensed practice of construction contracting pursuant to sections 455.227, 455.228, and 489.13. At all times material to this matter, Respondent was the owner of Advanced Connections, LLC. Neither he nor his company is licensed, registered, or certified to perform construction contracting services in Florida. Respondent holds only certification to perform backflow preventer testing. At the heart of this case is whether Respondent may perform backflow preventer repair without a license, certification, or registration. Facts Related to Work Performed It is undisputed that Respondent performed repair of backflow preventers for customers in Tallahassee, Florida. On July 25, 2014, Respondent performed a backflow prevention assembly test on two existing backflow preventers at Old Enrichment Center located at 2344 Lake Bradford Road, Tallahassee, Florida 32301. Respondent provided an invoice to Old Enrichment Center following the backflow test, which described the work performed as follows: “I was able to repair both units and they are Functioning [sic] properly. I had to replace one additional part on, AS #10896, the #2 check cage was cracked. Thank you For [sic] your business. Don’t forget to cover the backflows.” The invoice reflected that Respondent was compensated $343.00 for the worked performed and materials. On August 20, 2014, Respondent performed a backflow test on an existing backflow preventer for Li-Ping Zhang at a property located at 2765 West Hannon Hill Drive, Tallahassee, Florida 32309. Respondent provided an invoice to the customer describing the outcome of the test, and he provided an estimate for repair as follows: Invoice: Thank For this opportunity to serve you. The unit is failing. The #1 check valve is leaking across it. That means it is not holding pressure. The Manufacture of flowmatic no longer makes parts for your unit. But my supplier does have a repair kit available. Due to the Fact are no longer made for your device it may be better to have the unit replaced with a Wilkins 975-XL. Please See Quote * * * Quote for repair: Part: Complete Rubber Kit-$30.00 Labor: This unit may not be repairable due to the fact that there is a limited supply of parts. If there is damage to the #1 Check. I will not be able to repair the unit. If that happens I can return the parts but a labor charge would still remain. Please call with any questions. Thank you. (Quoted text from invoice without correction of grammar.) Respondent ultimately performed the repair on August 25, 2014. The invoice issued to Li-Ping Zhang reflected service provided as “[t]he repair was a success. The unit is Passing [sic]. Paid Cash $115.00 8.25.14 — signed Ian.” Both invoices include the Respondent’s company name, Advanced Connections, LLC. There was no evidence presented of financial or property harm caused by Respondent’s actions. On or about February 2, 2015, Petitioner received a complaint from City of Tallahassee filed against Respondent for his repair of backflow preventers in Tallahassee, Florida. Petitioner commenced an investigation into Respondent’s actions through its unlicensed activity investigation unit. At the conclusion of the investigation, Petitioner filed an Administrative Complaint alleging Respondent engaged in construction contracting without a license. Respondent disagrees with Petitioner and argues that he is eligible for an exemption under section 489.103(9), commonly known as the “handyman” exemption. Life-Safety Matter Respondent’s eligibility for the exemption hinges upon whether repair of a backflow preventer is considered a life- safety matter. The Florida Building Code provides minimum standards for building construction to “safeguard the public health, safety and general welfare.” See § 101.3, Florida Building Code, Building. The Florida Building Code, Plumbing, applies to “the installation, alteration, repair and replacement of plumbing systems, including fixtures, fittings and appurtenances where connected to a water or sewage system . . . .” See § 101.4.3, Florida Building Code, Building. The plumbing chapter of the Florida Building Code defines a backflow preventer as a device or means to prevent backflow of water from flowing from one system into the potable water system.2/ A potable water supply system shall be maintained in such a manner so as to prevent contamination from non-potable liquids, solids, or gases being introduced into the potable water supply through cross-connections or any other piping connections to the system. § 608.1 Building Code, Plumbing. To further explain the purpose of backflow preventers, Petitioner offered Frank Hagen as a plumbing expert. Mr. Hagen, who has 42 years of plumbing experience, has been licensed in Florida since 1981 and is also licensed in Georgia. He holds a certification in backflow preventer testing (issued by the University of Florida TREEO Center) and backflow preventer repair. Mr. Hagen has regularly conducted on-the-job plumbing training for 36 years. Mr. Hagen was accepted as a plumbing expert. Mr. Hagen testified that a backflow preventer is a life-safety device. He explained that this reference is accepted throughout the plumbing industry because the backflow preventer protects water systems by preventing chemicals and poisons from entering the public water system. Mr. Hagen provided examples of potential outcomes if a backflow preventer fails (e.g., three children died as a result of drinking water from a water hose where poison in the sprinkler system contaminated the water). Mr. Hagen also testified that only a licensed plumber is authorized to perform backflow repairs. Mr. Hagen’s testimony is credible. John Sowerby, P.E., a licensed professional engineer for 35 years, who previously worked in the Department of Environmental Protection’s (DEP) Source of Drinking and Water Program, also testified regarding the nature of backflow preventers. He testified that backflow preventers protect public health because they prevent contamination of potable water systems (i.e., water that is satisfactory for human consumption). Mr. Sowerby’s testimony is also found to be credible. Respondent’s testimony that a backflow preventer is not a life-safety fixture, is not supported by the evidence. Respondent testified that backflow preventers are “plumbing fixtures” that are installed between the public water supply line and the private water supply line. Respondent also testified that if a backflow preventer fails, it could cause contamination of the public water supply and public health would be at risk. More importantly, the applicable building codes and the testimony of Mr. Hagen and Mr. Sowerby establish that backflow preventers prevent contamination of public water supply and protect public health. Given that backflow preventers safeguard public health by protecting the public water supply, they involve life-safety matters. The Department has incurred investigative costs in the amount of $415.95 related to this matter. Ultimate Findings of Fact Respondent’s repair of a backflow preventer on a water service line is a life-safety matter and as a result, Respondent is not eligible for an exemption under section 489.103(9). The evidence is clear and convincing that Respondent’s repair of a backflow preventer at the two properties referenced herein constituted the practice of construction contracting without a license. As a result, Respondent is guilty of unlicensed contracting, as charged in Counts I and II of the Amended Administrative Complaint.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation issue a final order that: Finds Respondent guilty of unlicensed contracting in violation of section 489.13(1), as alleged in Counts I and II of the Amended Administrative Complaint; Imposes an administrative fine of $6,000 ($3,000 for each count); and Requires Mr. Tuttle to pay the Department’s investigative costs of $415.95. DONE AND ENTERED this 26th day of October, 2016, in Tallahassee, Leon County, Florida. S YOLONDA Y. GREEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 26th day of October, 2016.

Florida Laws (13) 120.565120.569120.57120.68381.0062455.227455.228474.203489.103489.105489.113489.127489.13
# 1
ROSE ANN DE VITO vs JOHN FALKNER, CHRISTOPHER FALKNER, AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 95-005763 (1995)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Nov. 27, 1995 Number: 95-005763 Latest Update: Jun. 03, 1996

The Issue The issue in this case is whether the application of Respondents Falkner to transfer and modify a Water Use Permit should be approved.

Findings Of Fact The Southwest Florida Water Management District (District) is responsible for regulation and protection of water resources in the geographic area involved in this proceeding. Since 1994, John Falkner has owned the property in Hillsborough County which is the subject of this proceeding. The Falkner property is farmed by Christopher Falkner, the owner's brother. Prior to purchasing the land, the Falkners farmed the property, also known as the Rogers farm, through a lease arrangement with the previous owner. Rose Ann DeVito owns property to the south of the Falkner property. In the time since Ms. DeVito purchased the property, the elevation of Sumner Road has been raised and culverts were replaced. A fish farm was constructed in close proximity to her property. The result of this and other development has been to direct all the water flow from the surrounding area into the stream adjacent to the DeVito property. Drainage patterns in the area of Ms. DeVito's property have been altered since she first occupied the property. A ditch along Sumner Road which used to handle runoff from her property has been blocked by a neighbor's driveway. Maintenance on the ditch, allegedly a county responsibility, is described as poor. The ditch at the rear of Ms. DeVito's property handled water flow to Bullfrog Creek until the water flow became blocked, and the water diverted onto her property. The effect is that Ms. DeVito's property often contains a large amount of water. A substantial amount of sand is visible on her property, allegedly deposited by water flow. According to Ms. DeVito, both the county and the District have blamed the Falkner farm for the water-deposited sand. Charles and Diana Booth own property adjacent and to the south of the Falkner property. From 1992 to 1994, the Booths suffered from water running off the Falkner/Rogers farm and flooding the Booth property. A flood of the Booth property in the Fall of 1994 was not caused by irrigation but was related to a ten inch rainfall event at the Falkner farm. A ten inch rainfall exceeds a 25 year storm event and would likely result in widespread flooding. The Booths' pasture, top soil and driveway were eroded by the flooding. During the two years of flooding, Mr. Booth complained on several occasions about the flooding to the Falkners' foreman, "Cleo." The complaints were not relayed to Mr. Falkner. In October 1994, Mr. Booth reported the problem to the Southwest Florida Water Management District. Soon after the complaint was made, a representative of the District inspected the property and determined that a ditch needed maintenance. Shortly thereafter, the ditch was cleaned and a berm was installed to redirect runoff away from the Booth property. There has been no further flooding of the Booth property. In October 1995, Mr. Booth became concerned that a ditch was filling with sand and would not continue to handle the runoff. After voicing his concern, a water diverter was installed in the ditch and appears to have remedied the situation. At the time the Falkners began to lease the Rogers property, an existing water use permit, numbered 206938.01, had been issued and was valid for the farm. The Falkners have applied to transfer the existing water use permit from the previous property owner. The Falkners also seek to modify the permit, increasing the total quantities which can be pumped by transferring previously approved quantities from another permit the Falkners currently hold. All of the relevant wells are within the District's Most Impacted Area (MIA) of the Tampa Bay Water Use Caution Area. The District allows a permit holder within the MIA to increase withdrawals from a well by transferring the quantities from another permitted well within the MIA. The other Falkner farm (the "301 farm") from which the quantities would be transferred is located approximately one-half mile to the south of the Rogers farm and is within the MIA. The District reviewed the application and, on September 29, 1995, issued its Proposed Agency Action to Issue Water Use Permit No. 206938.03. The proposed permit includes special conditions requiring monthly pumping reports, water quality reports, adherence to District irrigation allotments (irrigation levels established by the AGMOD computer model) and crop reporting. In reviewing the application the District utilized the criteria set forth in Florida Administrative Code, and the Basis of Review, incorporated into the code by reference. In order to obtain a Water Use Permit, an applicant must demonstrate that the water use is reasonable and beneficial, is in the public interest, and will not interfere with any existing legal use of water. Additionally, the applicant must provide reasonable assurances that the water use: will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters; will not adversely impact offsite land uses existing at the time of the application; will not cause water to go to waste; and will not otherwise be harmful to the water resources within the District. The uncontroverted evidence establishes that the water use is reasonable, beneficial and is in the public interest. The Falkners irrigate farmland to produce agricultural products. The production of food is in the public interest. The proposed use is reasonable and beneficial. Further, uncontradicted evidence and opinions of expert witnesses establish that the proposed use will not interfere with any existing legal use of water. The applicant must provide reasonable assurances that the water use will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters. The evidence establishes that pumping from the Falkner wells will not adversely affect the quality of water within the aquifers from which the water is drawn. Mr. Booth asserted that he is having water quality problems, specifically with rust in his well. The Booth well is approximately 25 years old. There is no evidence that the rust is related to the Falkner pumping. The DeVito and Booth wells draw from the Intermediate aquifer. Review of the potentiometric surface map of the intermediate aquifer indicates that there is a water level variation of 17 feet between the rainy and dry seasons. The result of the variance can be "dry" wells. There are two wells on the Falkner/Rogers property relevant to this proceeding. The first (District ID number 1) is 770 feet deep, is cased to a depth of 160 feet, and opens to the Floridan aquifer. The second (District ID number 2) is 1100 feet deep, is cased to a depth of 140 feet, and opens to the Intermediate and the Floridan aquifers. A cased well does not withdraw water from the formations through which the casing is placed. For example, a well cased to a depth of 160 feet draws no water from the top of the casing (at approximately ground level) to the bottom of the casing at 160 feet. The Intermediate aquifer releases water at a much slower rate than the Floridan aquifer. Based on the type and location of the Falkner wells, the vast majority of the water pumped by the Falkners comes from the Floridan aquifer. Impacts on existing wells are calculated through computer modeling. The "MOD" flow model demonstrates impacts that will occur after 90 days of pumping at peak month levels with no recharge to the aquifer. The MOD flow model results in a conservative "worst case" projection. The MOD flow model calculation projects the drawdown at Falkner well number 1 to be approximately .9 feet. The MOD flow model calculation projects the drawdown at Falkner well number 2 to be approximately 1.4 feet. The MOD flow model calculation projects the drawdown at the Booth well to be approximately one-half foot. The impact on the DeVito well will not exceed that projected at the Booth well. District permitting criteria allow for projected MOD flow model drawdown impacts of less than five feet at existing wells. The impact possible after approval of this application falls well within the District's guidelines. The impact of pumping if the application at issue in this proceeding is approved will result in a maximum variation of one-half foot at the Booth well. The evidence fails to establish that any problems related to water quantity encountered by the Booths are related to agricultural pumping at the Falkner farms. The evidence also establishes that, based on the existing retention and drainage system, the proposed use will not adversely impact surrounding surface water bodies. A system of swales and ditches is utilized to retain the water on the farm property. The evidence fails to establish that runoff from the Falkner/Rogers farm will adversely impact surrounding surface waters if this application is approved. The applicant has provided reasonable assurances that the water use will not adversely impact offsite land uses existing at the time of the application. The evidence establishes that the runoff from the Falkner farm does not discharge directly to the stream at the rear of the DeVito property. Other agricultural property discharges into the stream adjacent to the DeVito property. There is a steady waterflow through the stream at all times, whether or not the Falkner pumps are operating. Ms. DeVito's property consists of Myakka soil, which has little capacity to absorb rainfall and generates large amounts of runoff. The altered drainage patterns in the area have resulted in substantial water on her property. The evidence in insufficient to establish that the Falkner farm pumping has resulted in flooding on Ms. DeVito's property. The evidence fails to establish that approval of the application at issue in this proceeding will cause adverse impact to the DeVito property or will result in water quality or quantity problems. The Booths are concerned that the existing drainage system will not be maintained and that increased pumping will result in their land being flooded again. The evidence fails to establish a substantial likelihood that the Falkner farm drainage system will not be maintained. The applicant has provided reasonable assurances that the water use will not cause water to go to waste. The Falkners use a semi-enclosed seep irrigation system at the Rogers farm. Irrigation is only used when necessary. Mushroom compost, humates, and plastic mulch retain moisture in the soil. A special condition of the permit requires the Falkners investigate the feasibility of tail water recovery and reuse. The applicant has provided reasonable assurances that the use will not otherwise be harmful to the water resources within the District. The permit application results in no increased withdrawal of water than is allowed under the existing permits for the Rogers and the "301" farms.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Southwest Florida Water Management District enter a Final Order granting the Falkner application and issuing permit number 206938.03. DONE and ENTERED this 26th day of April, 1996 in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1996. APPENDIX TO RECOMMENDED ORDER, CASES NO. 95-5763 and 95-5764 To comply with the requirements of Section 120.59(2), Florida Statutes, the following constitute rulings on proposed findings of facts submitted by the parties. Petitioners Booth The Petitioners Booth proposed findings of fact fail to comply with the requirements of Rule 60Q-2.031(3), Florida Administrative Code, which requires citations to the record of hearing. The proposed findings are rejected as irrelevant or not supported by the greater weight of the evidence except where they are consistent with the Findings of Fact set forth herein. Respondents The Respondents' joint proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 15. Rejected, cumulative. 28-29. Rejected, subordinate. 33. Rejected, subordinate. COPIES FURNISHED: Rose Ann DeVito, pro se 11001 Sumner Road Wimauma, Florida 33598 Diana P. and Charles B. Booth, pro se 10812 Sumner Road Wimauma, Florida 33598 Patricia Petruff, Esquire Dye and Scott, P.A. 1111 Third Avenue West Bradenton, Florida 34206 Martin Hernandez, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Peter G. Hubbell, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (1) 40D-2.301
# 2
DEPARTMENT OF HEALTH vs ROBERT J. GORMAN, 99-000655 (1999)
Division of Administrative Hearings, Florida Filed:Fort Pierce, Florida Feb. 11, 1999 Number: 99-000655 Latest Update: Oct. 01, 1999

The Issue Whether the Respondent committed the violations alleged in the Administrative Complaint dated January 8, 1999, and, if so, the penalty which should be imposed.

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department of Health, including the county health departments such as the St. Lucie County Health Department ("County Health Department"), are responsible for supervising and controlling limited use public water systems. Section 381.0062(3), Florida Statutes (1997). Mr. Gorman is the owner of three duplexes located at 120 and 122 Laidback Way, Fort Pierce, Florida; 140 and 142 Laidback Way, Fort Pierce, Florida; and 160 and 162 Laidback Way, Fort Pierce, Florida. The duplexes were built in 1982 and 1983 and each contains two units which are available for rent. Water is piped into each duplex from a well located on the property. The wells providing water to 120 and 122 Laidback Way and to 140 and 142 Laidback Way were inspected by the Department of Health and Rehabilitative Services in May 1994 and found to be satisfactory pending results of water tests. Two-day bacteriological analyses were conducted on May 2 and 3, 1994, on the wells serving these two properties, and the results were satisfactory. 3/ The 1994 inspection report for the well serving the property at 120 and 122 Laidback Way reflects that it had the following equipment: a one-half horsepower pump; a 30-gallon "p tank"; a 20-gallon water softener filter; and a 30-gallon brine tank. The 1994 inspection report for the well serving the property at 140 and 142 Laidback Way reflects that it had the following equipment: a one-half horsepower pump; a 20-gallon "p. tank"; a 25-gallon water softener filter; and a 40-gallon brine tank. In a letter dated August 21, 1998, the County Health Department notified Mr. Gorman that he needed to submit the application enclosed with the letter and a $140.00 fee to bring the "permit" to current status for the property located at 140 and 142 Laidback Way. The letter was inartfully composed and conveyed incomplete information regarding the nature of the permit. The letter did, however, contain reference to "Chapter" 381.0062, Florida Statutes, and Chapter 64E-8, Florida Administrative Code, and it also provided notification that Chapter 64E-8 required quarterly sampling of limited use public water systems for bacteria and a lead and nitrate test every three years. The County Health Department sent Mr. Gorman an identical notice, dated August 21, 1998, regarding the property located at 160 and 162 Laidback Way. The County Health Department sent Mr. Gorman a somewhat different letter, dated August 31, 1998, regarding the "Limited Use Public Water Systems" for the property located at 120 and 122 Laidback Way. The letter notified Mr. Gorman that his permit to operate the "referenced water system has expired as of September 30, 1998." The letter reiterated the information contained in the August 21 letter and requested in addition that Mr. Gorman submit "a minimum 8.5 x 11 inch site plan of the system, drawn to scale, that accurately identifies the location of the source of water in relation to property boundaries and contaminant sources, i.e., well must be 75 feet from septic system, etc." and an "[e]quipment list: pump, tank, softener, automatic chlorinate, etc., manufacturer, model #, and capacity." Finally, Mr. Gorman was notified of the permitting and testing fees and told that the "[a]pplication with required site and equipment information must be submitted with necessary fees within 30 days receipt of this notification." Mr. Gorman responded with a letter dated October 16, 1998, in which he posed several questions to the County Health Department: Do you understand that these are duplexes? Are all rental properties including single family subject to these regulations? Can you give me a valid reason why rental units of two units or more should be subject to quarterly bacterial testing (I believe the statute only authorizes it annually) and not all other residential properties, public facilities or otherwise that might use well water? Mr. Gorman requested a response to his questions but did not provide the information, applications, and permit fees requested in the letters dated August 21 and August 31. In a letter dated December 14, 1998, sent certified mail with return receipt requested and referenced as a Notice of Violation, the County Health Department notified Mr. Gorman that he was operating limited use community public water systems without a permit at 120 and 122, 140 and 142, and 160 and 162 Laidback Way and that he had not provided the following required information: Signed, dated application form. An operation permit fee of $75.00 for the initial permit. A site plan of the property that accurately identifies the location of the well in relation to property, boundaries and contaminant sources such as septic tank systems. Capacity/size, model and brand information on system components. Well completion report if available or year well was installed if known. Required chemical analysis results (lead and nitrate). Initial satisfactory two-day source (well) water and system water bacteriological tests results. Mr. Gorman was told to contact Bruce McLeod within five days of receipt of the notice. Although Mr. Gorman received the notice on December 16, 1998, he did not respond. The County Health Department had not, as of the final hearing, received any reports of illness attributable to the water from the wells at the subject properties, and it does not have any reason to believe that the wells are contaminated. Mr. Gorman had not, as of the final hearing, submitted the applications, permit fees, or information requested by the County Health Department, and he had no operating permits for the wells providing water to the subject properties. The evidence presented in this case is sufficient to establish that the wells providing water to the three duplexes owned and rented by Mr. Gorman each contains two rental units and are limited use community public water systems. Mr. Gorman must have operating permits for the wells providing water to these properties.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health enter a final order: Finding that Robert J. Gorman is guilty of three violations of Section 381.0062, Florida Statutes (1997), because he failed to obtain operating permits for the limited use community public water systems he maintains at 120 and 122, 140 and 142, and 160 and 162, Laidback Way, Fort Pierce, Florida; and Imposing an administrative fine in the amount of $1500.00, or $500.00 for each of the three violations. DONE AND ENTERED this 25th day of June, 1999, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 1999.

Florida Laws (6) 120.569381.0061381.0062381.0065381.0066381.0072 Florida Administrative Code (2) 64E-8.00464E-8.006
# 3
WYATT S. BISHOP, JR. vs SARASOTA COUNTY PUBLIC HOSPITAL BOARD, D/B/A SARASOTA MEMORIAL HOSPITAL, 91-002704 (1991)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida May 01, 1991 Number: 91-002704 Latest Update: Sep. 30, 1991

The Issue The issue for consideration herein is whether Sarasota County Utilities should be issued a consumptive use permit to draw water from the 14 wells in issue here located in Sarasota County.

Findings Of Fact At all times pertinent to the issues herein, the Respondent, District, was the state agency responsible for themanagement of water resources within its area of geographical jurisdiction. Included therein was the responsibility for the permitting of consumptive water use. The Respondent, Sarasota County, is a political subdivision of the State of Florida and operates a public utilities division which is charged with meeting, among other things, the potable water needs of the residents of the County. Petitioners Wyatt S. Bishop and Joan Jones are both residents of Sarasota County and both draw their potable water from wells which utilize the aquifers pertinent to the wells for which the permit in issue here relate. Mr. Bishop lives approximately 7.5 miles north of the Carlton Reserve, the property on which the wells in issue are located, and Ms. Jones lives approximately 7 miles from the Reserve, but in a different direction. Sarasota County filed an application for a consumptive use permit with the District on January 28, 1987 requesting an average daily withdrawal of 10.71 million gallons per day, (mgd), and a peak monthly withdrawal of 15.55 mgd. This application, assigned number 208836.00, was, over the next three years, amended by the County four separate times. These amendments reflected revised water demand determinations and were submitted to provide additional information requested by the District. The District issued a preliminary staff report and proposed intent on March 26, 1991 reflecting an approved withdrawal in the amount of 7.28 mgd average daily withdrawal and 11.1 mgd peak monthly withdrawal. These figures were revised, however, byan amendment by the District on July 8, 1991, and as amended, authorize 7.303 mgd average daily withdrawal and 9.625 mgd peak monthly withdrawal. The County's application was reviewed by an experienced hydrologist in the District office with extensive permit review experience who utilized, in his evaluation of the permit, the pertinent District rules and policies. By way of background, to more easily understand the circumstances here, Sarasota entered into a contract with Manatee County in 1973 which called for the latter to provide up to 10 mgd of water for a period of 40 years, up to and including the year 2013. However, in 1979, Manatee County's utilities director advised Sarasota County that it, Sarasota County, could not continue to rely on Manatee County's water after the expiration of the current contract, and would, therefore, have to become self sufficient in water. Since the MacArthur tract, now known as the Carlton Reserve, had just recently been identified by, inter alia, the United States Geological Service as a potential long term water source for Sarasota County, after Manatee County advised Sarasota County of its future expectations, Sarasota County and the Manasota Basin Board hired a consulting firm to conduct hydrological testing on the Carlton Reserve. This study concluded that the Reserve had sufficient water resources to satisfy the needs of the unincorporated areas of Sarasota County for an extended time into the future. In 1985, because of its increased water needs and thetime necessary to complete required studies on the utilization of the Myakka River, a surface water resource, Sarasota County concluded that it was suffering a water supply shortage and entered into a supplemental contract with Manatee County to provide 2 million gallons of water per day over a 5 year period which would expire in 1990. Sarasota County had not, however, been idle with regard to the investigation of other water resources. Studies done included not only the Myakka River mentioned above but a reservoir owned by the City of Bradenton, and the Peace River. Nonetheless, it was determined that the Carlton Reserve was the best source available overall, and in 1987, the County filed the application in issue here. The permit was under consideration for approximately 3 1/2 years before the initial decision by the District to grant it. During that time the County experienced a significant deficiency in its water sources and found it necessary, on February 5, 1991, to enter into another contract with Manatee County to supply an addition 5 mgd. Terms of that contract clearly indicate the expectations of both parties that Sarasota County will take reasonable steps to develop its own water resources. It is not as though Sarasota County sat quietly in the interim, however, and allowed the situation to develop. A building moratorium to halt additional construction was proposed and as a result, economic forces in the County indicated a potential loss of jobs to County residents. None of this would be desirable from an economicstandpoint. In the course of the permit application process, 12 test wells were sunk to conduct aquifer pump tests; to assess water quality, amounts and availability, aquifer characteristics and drawdown; and to determine the impact of withdrawal on water quality. Eight of these 12 wells are located on the Carlton Reserve. The other 4 are located on property owned by the MacArthur Foundation which is contiguous to the Carlton Reserve property and from which Sarasota has a right by easement to draw water. The 2 wells yet to be constructed will be on Sarasota County property. Sarasota County currently receives 10 mgd of water under its contract with Manatee County; an additional 5 mgd under the February 5, 1991 contract; 2 mgd from the University wellfield, (with a peak withdrawal rate of 3 mgd); and .9 mgd from the Sorrento wellfield, (with a peak withdrawal rate of 1.1 mgd). This latter source is only producing currently .6 mgd of potable water due to constraints imposed by the water treatment requirements. Taken together, the current Sarasota County supply constitutes 18.6 mgd. The above does not take into account the County's agreement with the City of Sarasota calling for the purchase of up to 2 mgd. Since this source is not reliable, it is not included in the total, and the City is not considered an available water source. In addition, the District and Sarasota County stipulated on July 15, 1991 that within 30 days, the County would apply tophase out routine water production from the Sorrento wellfield, relying on it only in emergency situations with District consent. For this reason, it, too, is not considered an available water supply source. These currently existing sources, with modifications as described, will be the primary sources of potable water provided to 6 major service areas in Sarasota County when the County's water treatment plant and transmission system are complete in 1993. In attempting to define the County's future water requirements, two major criteria were considered. The first was the County's historical water demand, and the second, modifying it, relates to the demand arising as a result of new water users being added to the system as a result of the County's capital improvements and acquisition program. Water resources are not unlimited. Current resources come primarily from Manatee County and there are constraints on this supply as it is made available to Sarasota County. For example, the 10 mgd contract expires in 2013. The 5 mgd contract expires in 2001. Though the latter is subject to renewal, renewal is contingent upon the availability of water supply at that time, and that is not a sure thing. It can, therefore, readily be seen that 15 out of the 18.6 mgd routinely available now comes from Manatee County, and those sources are not perpetual. In addition, it is conceivable that Manatee County may pre-blend the water it delivers to Sarasota County with water of lesser quality, so that the delivered water may exceed the total dissolved solids standard of 500 ppm for potable water. If thewater from Manatee County were reduced to that quality, the University wellfield supply, which currently exceeds standards itself, and which relies on blending with better quality Manatee County water to be potable, would also be removed as a source of potable water to Sarasota County. In order to comply with the provisions of Section 373.171, Florida Statutes, which requires the District to regulate the use of water by apportionment, limitation, or rotating uses, to obtain the most beneficial use of water resources and to protect the public health, safety and welfare, the District analyzed the available water sources and determined that Sarasota County relies upon its 10 mgd supply from Manatee County and the 2 mgd supply from University wellfield to constitute 12 mgd usable water. The 5 mgd from Manatee County would be used only in an emergency situation, and the Sorrento wellfield would be abandoned. Future water demands must be predicted relying in great part upon an historic record of prior water use. Utilizing a statistical procedure called linear regression, a methodology accepted by the District, indicated a water demand figure for the period from 1992 to 1997 based upon six use points extending from 1985 to 1990. These use records reflected a low of 9.733 mgd and a high of 12.808 mgd, the former being in 1985 and the latter in 1990. In addition, the County estimated that its capital improvement program would add between 10 and 12 thousand customers who presently use private wells, whose water use would constitute approximately 2 mgd of additional demand. The County's program toacquire some 42 private franchises now serving customers would add an additional demand of 2 mgd. Taken together, these programs would add in approximately 1.8 mgd per year to the need assessment, and it would therefore appear that by 1997, the County's average daily demand, considering all new users, would be 17.84 mgd. The water to be drawn from the Carlton Reserve is not currently potable and will require some form of treatment to render it so. Sarasota County proposes to use the Electrodialysis Reversal process, (EDR), because, in the County's judgement, it is more efficient than others such as reverse osmosis and ion exchange. Whereas EDR is rated at up to 85% efficient, the others range between 50% to 75% efficient. In that regard, in order to determine the maximum amount of water to be drawn, providing a safety factor for a treatment plant operation that is not working up to peak capacity in computing the water needs, the EDR process was determined to be no more than 80% efficient. Factoring in that efficiency potential, when the 1997 average daily demand is subtracted from the County's projected water capacity, the withdrawal need in 1997 is determined to be 7.303 mgd. However, as a part of its permitting process, the County also calculated its peak month daily demand. This is a figure which represents the maximum amount permitted to be drawn on a daily basis during the peak demand period. This peak period was determined under Section b 3.2 of the District's Basis of Review by taking the 1989 daily flow and using a sliding 31 day calendar to determine the highest historical 31 day flow. Thisresulted in a peak month coefficient of 6.16 which was then multiplied by the 1997 average daily demand of 17.842 mgd which resulted in a peak month daily demand of 20.7 mgd. When existing water supplies are removed and the 80% EDR treatment process factor is applied, the amount of raw water needed from the wellfield in issue on a peak monthly basis would be 9.625 mgd. This peak monthly basis figure is considered because of the intermittent periods of low rainfall and high water demand within the County. Accepting the 1.8 gpd yearly increase; the peak factor of 1.16; and the assumed water supply capacity of 18.6 mgd; Sarasota County's need will exceed its available supplies by 1993. In fact, the County is already experiencing low water pressure in part of its service area during peak demand periods. County experts estimate that without the requested water from the Carlton Tract, Sarasota County can expect to experience dry periods as early as 1993 during the periods of peak water usage, generally between April and June. For the above reason, when the application and its supporting information was reviewed by Mr. Basso, the District hydrologist with extensive experience reviewing more than 300 water use application, he determined that the water supplies requested are necessary to meet the County's certain reasonable demand, and that this meets the criteria set out in Rule 40D - 2.301(1)(a), F.A.C. Turning to the issue of hydrologic and environmental impacts, the District's Basis For Review of Water Permit Applications provides for the use of a "water use model" inevaluating water needs and the appropriateness of a proposed withdrawal. In preparing its submittal to the District, Sarasota County performed certain tests and modeling to derive the statistical and scientific information used in support of its application. Specifically it used the USGS' MODFLOW model utilizing information obtained from the pump tests run on the wells in the pertinent areas. Consistent with the District's rule, the water data and aquifer drawdown were determined by simulated pumping. The tests run also provided the information on water quality in the aquifer and physical characteristics including transmissivity, storage coefficient, specific yield and leakance between aquifers. This data also helped in defining the hydrogeologic framework of the Carlton Reserve. The Carlton Reserve's hydrogeology listed in descending order from the surface, includes a surficial aquifer which varies in depth between 19 and 70 feet across the Reserve; a semi-confining clay unit separating it from the intermediate aquifer; the upper intermediate and lower intermediate aquifer which range in depth from 140 to 180 feet across the Reserve; another confining layer, and the Upper and Lower Floridan aquifers. The hydrology and groundwater modeling expert who constructed the model used in Sarasota County's permit application concluded that the water table drawdown at the Reserve property boundary in the surficial aquifer would be less than .3 of a foot; less than .4 of a foot in the intermediate aquifer; and 2.9 feet in the Upper Florida aquifer. The water to be drawn consistentwith this instant permit, if approved, would come from the Upper Floridan aquifer on the Reserve. The County's experts were conservative in the assumptions used in the groundwater model. It was assumed there would be no lateral water flow into the model area and no recharge. In addition, the model called for all pumps to run simultaneously at a maximum drawdown of 12.65 mgd for 90 days rather than at the requested quantity of 9.625 mgd. Utilization of these assumptions provided a scenario wherein "severe" impacts would be encountered. Based on the testing and the modeling done, expert opinion was that there would be no quantity or quality changes that would adversely effect water resources including ground and surface water. This meets the criteria of Rule 40D-2.301. This opinion was concurred in the District's hydrology expert. Nonetheless, in its proposed approval, the District has imposed special permitting conditions which require the County to monitor, analyze, and report water quality and water table level information to the District on a monthly and annual basis. When it evaluates the information supplied by an applicant relating to ground water monitoring, the District is required to consider certain presumptions set forth in its Basis For Review. For example, the District presumes that if there is a drawdown of more than 1 foot in the surficial aquifer at a wetland, adverse environmental impacts will occur. In the instant case, the County model concluded that the actual drawdown in the surficial aquifer at the Carlton Reserve is less than .6 of onefoot and, therefore, there should be no adverse environmental impact resulting from the withdrawal. Nonetheless, the County has developed several plans designed to provide information on environmental impacts which will continuously monitor such parameters as rainfall and evaporation, wetlands hydroperiod changes and vegetative changes in the wetlands to detect any changes which might be attributed to the water pumping. These plans have been made special conditions to the water use permit, and in the opinion of the County's ecology and hydrology expert, would enable the County to adequately monitor and detect any pertinent changes to the pertinent factors concerned on the Carlton Reserve. If wetland changes are detected, a contingency plan will be in effect which will require an alteration of pumping schedules or other action to minimize any adverse impacts. The District expert in wetlands and wildlife habitat has opined that these measures, with which he is familiar, are adequate to insure that adverse impacts to the wetlands will not occur. This is consistent with the provisions of Rule 40D-2.301(1). As was stated previously, the water to be drawn pursuant to this permit will be drawn from the Upper Floridan aquifer. This water is not potable but is treatable and is the lowest quality water which can be economically used by the County. Water of a lower quality does exist in the Lower Florida aquifer, but it is not economically treatable, and, in addition, use of this Lower Floridan aquifer might cause vertical movement of the poorer quality water into the upper strata. For all practical purposes,then, the lowest quality water available to it will be used by the County and this is consistent with the District's basis for review. Expert testimony indicates that saline water will not be infused into the Upper Floridan aquifer. Salt water intrusion generally occurs when groundwater is brought to a level below sea level. Even at the point of maximum actual drawdown as a result of pumping on the Reserve, the fresh water level will remain at least 20 feet above sea level, and as a result of the difference in water level, no saline water intrusion into the fresh water supply will occur even though salt water intrusion can also occur as a result of upward vertical movement of lower quality water due to withdrawal. The District's hydrologist and reviewing official also concluded that because of the confining layer below the aquifer from which water will be withdrawn, there would not be any significant upward movement of lesser quality water. The District's basis of review also envisions an aquifer pollution if a proposed withdrawal would spread an identified contamination plume. Here no contamination has been identified in the area from which the water will be drawn, and therefore, contamination would not be spread. The Basis for Review also infers there will be adverse impact to off site land if there is a significant drawdown of surface water bodies or if damage to crops or other vegetation can be expected. Here, the water table drawdown at the boundary of the Carlton Reserve is anticipated at less than .3 of one foot and any drawdown further out from the Reserve can be expected tobe even less. As a result, no adverse impact to existing off site land useage is expected. With regard to Rule 40D-2.301(1)(i), relating to an adverse impact on existing legal uses, the District presumes that no adverse impact will exist if the drawdown in the water table is no more than 2 feet at an affected well, or the potentiometric surface at the well is not lowered by more than 5 feet. Here, again applying the County's groundwater modeling demonstrates that the drawdown at its worst, in the Upper Floridan aquifer, would be no more than 2.9 feet at the Reserve boundary and much less at the Petitioners' wells. Both Mr Bishop's and Ms. Jones' wells are approximately 7.5 and 7 miles, respectively, from the closest well on the Reserve property. Ms. Jones' well is drilled into the intermediate aquifer which is above that which the County proposes to use and should not be impacted. Mr. Bishop draws water from the intermediate and surficial aquifers, both of which are above the Upper Florida aquifer identified for use here, and the groundwater modeling would suggest that his well would not be impacted either. Sarasota County's application contains reference to numerous proposals for water conservation measures which it intends to implement or has already implemented. It has adopted ordinances to enforce the District's watering restrictions and is currently implementing a block inverted use rate structure to promote conservation. It has developed programs for use in the schools outlining water conservation efforts and is developing programs topromote the increased use of treated waste water for golf course irrigation. The requirement for a water conservation plan such as is described and envisioned by the County is a condition of the water use permit proposed, and in addition, the County has adopted an Ordinance, (90-38) which modifies its building code to require installation of water conservation devices in new buildings erected in the County. It has developed proposals for conservation measures such as water auditing, meter testing, leak detection, system looping, and pressure reduction, and has selected the EDR process of water purification as the most efficient use of groundwater resources. Petitioner, Bishop, testified to his belief that approval of this permit and the resultant water withdrawal on the Carlton Reserve would necessitate an expansion of the boundaries of the District's Eastern Tampa Bay Water Use Caution Area to a point where his property would be encompassed therein. In support of his position, Mr. Bishop offered a notice to the effect that new ground water withdrawals would not be permitted within a certain "most impacted area" within the caution area. There was, however, no independent evidence from hydrologists, geologists, or other conservationists, or individuals familiar with the water conservation process, to support Mr. Bishop's contention that either the boundaries would be expanded or that withdrawal of the proposed permitted amounts of water from the Carlton Reserve would cause the boundaries to be expanded. By the same token, Mr. Bishop's contention that theproposed withdrawal from the wells here in issue would adversely effect his ability to draw water from his existing well was not supported by any expert testimony or documentary evidence tending to support or confirm his contention. He had no evidence tending to contradict the County's and District's experts, all of whom indicated there would be no adverse impact on the environment or water resources as a result of the instant permit. Similarly, neither Petitioner offered any evidence of a demonstrative nature that would draw any connection between the proposed permitted withdrawals and potential salt water intrusion and water level drawdown in their wells. The County introduced construction permits issued by its own health department covering 8 of the 12 wells which have been drilled on the Carlton Reserve as test wells. These wells were clearly sunk pursuant to an agreement between the District and the County's public health unit which delegates authority for water well construction permitting to the County. Taken together the documentation indicates that these 12 wells on the Reserve were installed and permitted pursuant to and consistent with appropriate permitting processes, and the testimony of Mr. Bassarab, the County's expert who oversaw the installation of the wells, reflects they are appropriately grouted and sealed. Therefore, there will be no mixing of lower quality water from the lower portion of the Floridan aquifer with the better quality water from the upper portion of that aquifer. The County's evidence clearly refutes the allegation by Mr. Bishop that the 12 test wells currently existingon the Carlton Reserve were neither permitted nor inspected as required by the District. County Commissioner Hill, who testified on behalf of the Petitioners, indicated that the wells applied for here are unnecessary and an inappropriate expenditure of County funds. She claimed there are other valid sources of water available to the County, including that extracted from excavated shell pits and seawater from the Gulf of Mexico which could be treated and desalinated. The Commissioner's comments as to alternate sources are not specifically rebutted. However, she is neither an expert in hydrology or hydrogeology, and her testimony is not persuasive. While other water sources may exist, the better evidence clearly indicates that those sources are not sufficient to meet the County's needs or are otherwise inappropriate for use by the County in sufficient quantity to satisfy those needs.

Recommendation Based on the foregoing Findings of fact and Conclusions of Law, it is, therefore: RECOMMENDED that consumptive water use permit No. 208836.00, providing for authorized quantities as outlined in the intent to issue, subject to conditions contained therein, be issued to Sarasota County. RECOMMENDED in Tallahassee, Florida this 5th day of September, 1991. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1991. APPENDIX TO RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONERS: Rejected as not supported by the evidence. Accepted. Accepted. - 8. Resolved against the Petitioners on the basis information presented by Respondents. 9.- 13. Accepted and incorporated herein. 14. - 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. 20. - 23. Accepted. Accepted but not dispositive of any issue. Accepted. & 27. Noted as citation of authority. Rejected. & 30. Accepted as restatements of evidence but not as Findings of Fact. 31. Irrelevant. 32. Rejected 33. & 34. Not a error is, in fact, it is such. 35. - 38. Irrelevant. 39. - 43. Accepted. 44. Accepted. 45. Rejected. 46. Accepted and incorporated herein. 47. & 48. Rejected as a mere citation of testimony. 49. Not understandable. Not a Finding of Fact. 50. Accepted. 51. Evidence is acceptable. 52. Not sufficiently specific to rule upon. 53. Not proven. 54. Not specific. 55. & 56. Rejected. FOR THE RESPONDENTS: 1. - 4. Accepted and incorporated herein. 5. & 6. Accepted and incorporated herein. 7. & 8. Accepted and incorporated herein. 9. - 14. Accepted and incorporated herein. 15. - 17. Accepted and incorporated herein. 18. - 21. Accepted and incorporated herein. 22. & 23. Accepted and incorporated herein. Accepted. - 27. Accepted and incorporated herein. 28. & 29. Accepted and incorporated herein. 30. - 32. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted. - 37. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. - 43. Accepted and incorporated herein. Accepted. Accepted and incorporated herein, - 48. Accepted and incorporated herein. Accepted - not a Finding of Fact. Accepted and incorporated in substance herein. Not correct as stated. Sarasota County will not be withdrawing saline water from the upper Floridan aquifer. The remaining discussion is accepted. Accepted and utilized. & 54. Accepted. Accepted and incorporated herein. Accepted. - 59. Accepted and incorporated herein. 60. Accepted. 61 - 63. Not Findings of Fact but comments on the evidence. Accepted and incorporated herein. & 66. Not Findings of Fact. COPIES FURNISHED: Wyatt S. Bishop, Jr. 5153 Tucumcari Trail Sarasota, Florida 34241 Joan Jones 719 East Baffin Road Venice, Florida 34293 William A. Dooley, Esquire Nelson, Hesse, Cyril, Smith, Widman, Herb, Causey & Dooley 2070 Ringling Blvd. Sarasota, Florida 34237 Cathy Sellers, Esquire Steel, Hector & Davis 215 S. Monroe Street Tallahassee, Florida 32301-1804 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Edward B. Helvenston, Esquire Vivian Arenas, Esquire SWFWMD 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (4) 120.57373.171373.2237.28 Florida Administrative Code (2) 40D-2.04140D-2.301
# 4
OSCEOLA COUNTY vs SOUTH BREVARD WATER AUTHORITY, 91-001779 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Mar. 22, 1991 Number: 91-001779 Latest Update: Jun. 12, 1992

The Issue As reflected in the parties' prehearing stipulation filed on August 28, 1991, the issue in this case is whether the St. Johns River Water Management District (SJRWMD) should approve South Brevard Water Authority's (SBWA) consumptive use permit (CUP) application. The SBWA is seeking permission to withdraw an annual average daily rate of 18.8 million gallons (mgd) and a maximum daily rate of 21.4 mgd. The District proposes to grant the permit with specified conditions. Petitioners challenge the issuance of the permit, alleging that applicable requirements of Chapter 373, F.S. and Chapter 40C-2, F.A.C. and other applicable law are not met. The standing of Petitioners, other than Osceola County, is at issue. Also at issue is whether the relevant criteria include consideration of the adequacy of existing sources of water, and the consideration of costs of utilizing existing sources versus the cost of the proposed new source of water.

Findings Of Fact The Parties The applicant, South Brevard Water Authority (SBWA) was created by special act of the legislature, Chapter 83-375, Laws of Florida. Its principal office is located in Melbourne, Brevard County, Florida. Its general mission is described in Section 1, of Chapter 83-375, Laws of Florida, as amended by Chapter 87-481, Laws of Florida: Section 1. It is hereby declared and determined by the Legislature that a regional water authority is the most responsive, efficient, and effective local government entity to secure, operate, and maintain an adequate, dependable, and safe water supply for the district and customers of the district. It is the intent of the Legislature that such regional water authority possess the full power and authority to implement, finance, and operate a single coordinated program of water supply transmission and distribution to meet the future quantity and quality needs of the district and for customers of the district. There is a paramount public need to develop a safe, reliable, and energy-efficient source of public water for the district residents and to contruct the wellfields, transmission lines, and other facilities necessary to supply such water. The St. Johns River Water Management District (SJRWMD or District) is an agency created pursuant to Chapter 373, F.S. in charge of regulating consumptive uses of water in a 19-county area of the State of Florida, including all of Brevard and part of Osceola County. The geographical boundaries of the District are described in Section 373.069(2)(c), F.S. Osceola County is a political subdivision of the state, west of, and contiguous to, south Brevard County. The Corporation of the President of the Church of Jesus Christ of Latter Day Saints (Deseret) is a Utah corporation authorized to conduct business in the State of Florida. Deseret owns real property in Osceola County to the north and east of the proposed wellfield. Deseret possesses a valid consumptive use permit authorizing the withdrawal of water for this property. East Central Florida Services (ECFS) does not own land or possess a consumptive use permit (CUP). Its purpose is to take over the water management program for the Deseret property. It has applied to the Public Service Commission for certification. Notwithstanding the parties' stipulation that "Triple E Corporation" and "Triple N Corporation" own real property in Osceola County near the proposed wellfield (prehearing stipulation, filed 8/28/91, p. 5), no such corporations are registered in the State of Florida. The lands identified as Triple E and Triple N are owned by multiple parties through trusts, primarily managed by Maury L. Carter, one of the owners. Neither Triple E nor Triple N properties have CUP's. The properties are used for agricultural purposes and the Triple N property has a well and recreational camp. The Site of the Proposed Use The proposed wellfield is located on property owned by the SJRWMD, the Bull Creek Wildlife Management Area (BCWMA), located entirely in eastern Osceola County. The BCWMA is comprised of 22,206 acres within the drainage area of the St. Johns River. The northern third of the management area is drained by Crabgrass Creek, and the southern two-thirds is drained by Bull Creek. The easternmost boundary is located approximately one mile from the Brevard County boundary. Currently all 22,206 acres of the BCWMA are under lease to the Florida Game and Fresh Water Fish Commission, which agency manages the area as a public recreation facility for hunting, fishing, hiking, horseback riding, camping and archeological studies. The sparsely populated area has historically been used for logging and cattle grazing. It was acquired for a detention area and it currently provides nonstructural flood protection. Its surface topography is relatively flat, with uplands and wetlands separated by only inches in vertical elevation. Upland communities include pine flatwoods, saw palmetto prairies, pine savannahs and sand oaks. Wetland communities include cypress domes, mixed shallow marshes, sawgrass marsh, wet prairies and transitional prairies. The BCWMA is classified as a "conservation area" in the District's current adopted Five Year Land Plan which summarizes the agency's land acquisition and management policies. A "conservation area" is defined as "...an area acquired for water resource conservation and protection in an environmentally-acceptable manner". The term includes water supply areas, including areas for public wellfield location. (Osceola Co. exhibit #33, p. 15) Facilities Associated with the Proposed Consumptive Use Although the precise siting of the wells has not been established, the wellfield will be located at the northern end of the BCWMA, east-west into a "panhandle" area, and extending south, for an inverted "L" shape. The wellfield will consist of 12 production wells in 2000 ft. intervals. Wells 1-9 will lie along an east-west axis adjacent to Crabgrass Creek, while wells 10-12 will lie along a north-south axis below well 9, the eastern-most well. The capacity of each well is designed at 3,000 gallons per minute or approximately 4.30 million gallons a day (mgd). Each well consists of 20" diameter casing pipe extending 700' below the ground surface. From there, an open hole for production will extend another 250 feet in depth. A small, 20 ft. by 30 ft., concrete building will enclose the motor and other equipment associated with each well, in order to eliminate vandalism and to baffle the noise. The wells will be sited to avoid jurisdictional wetlands. In addition to the production wells, monitoring wells will be constructed to comply with permit conditions. Because the water drawn from the proposed wellfield will exceed potable standards, reverse osmosis (RO) desalinization treatment is required. A below ground header pipeline will carry raw water from the wellfield to an RO treatment facility in Brevard County. The RO treatment facility will process 75 percent of water coming from the wellfield, 85 percent of which is recovered as finished water, and 15 percent of which is disposed of as brine by deep well injection. The 25 percent of raw water which bypasses the treatment process will be blended with the finished water to yield water which meets drinking water standards for chloride levels. The yield is anticipated to be 16.67 mgd on an average day and 18.9 mgd on a maximum day. However, the finished water yield could be higher if raw water quality permits greater blending and less reject water. On the finished water side, the water will need to be treated again to assure that it will be compatible with water from the City of Melbourne plant. Failure to balance the blended waters chemically could result in corrosion of pipes, leaching of pipes, discoloration, rusty water, and odorous water. A proper process, therefore, is essential and is highly sophisticated. From the treatment facility the water will travel in underground pipes, beneath the St. Johns River, beneath I-95 and east to the Melbourne distribution system. From there some water is anticipated to travel south to connect to the General Development Utilities (GDU) system. Hydrogeologic Characteristics of the Site For modelling purposes, the aquifer system in the region is represented by sequential layers of differing characteristics in the flow and movement of water. The SBWA model contains 6 layers; the Osceola model contains 7 layers. In both models, layer 1 corresponds to the surficial (water table) aquifer; layer 2 corresponds to the Hawthorn formation (the upper confirming layer); layer 3 is the Upper Floridan aquifer; layer 4 describes the 200 ft. thick portion of the Upper Floridan called the "production zone"; layer 5 in the SBWA model is approximately 450 ft. thick and is called a confining unit; Osceola's consultants consider this layer less permeable or semi-confirming; layer 6 is the lower Floridan; and layer 7 in the Osceola model is the bottom reaches of the lower Floridan. The surficial aquifer consists of sand and shell deposits and extends to a depth of approximately 100 feet below land surface. The surficial aquifer is capable of producing small to moderate amounts of water for domestic uses. The Hawthorn is an interbedded formation consisting of clay, limestone and phosphate. Due to its extremely low permeability, this layer restricts both the vertical and horizontal movement of water. The Hawthorn is thicker in Central Florida than in other portions of the state. At the BCWMA the thickness of the Hawthorn ranges from 240 feet in the area northwest of the management area to 80 feet in the southeastern portion of the management area. The upper Floridan Aquifer at the BCWMA, as characterized by the SBWA's consultant and based on site specific data, extends from the base of the Hawthorn to a depth of approximately 900 feet below land surface. That portion of the upper Floridan Aquifer between the bottom of the Hawthorn and 700 feet below land surface consists of fine grained limestone with relatively low permeability. This zone corresponds with layer 3 in the groundwater modeling done by the SBWA. The portion of the upper Floridan between the bottom of the Hawthorn and 700 feet below land surface is less capable of producing water than the portions below this level. That portion of the upper Floridan Aquifer between 700 feet and 900 feet of depth consists of hard dolomites. Dolomitic zones are the most productive zones of water within the Floridan in this part of the state because these formations contain solution fractures and cavities. This zone corresponds with layer 4 in the groundwater modeling done by the SBWA. Several researchers and modelers have suggested the existence of a zone, variously referred to as a semi-confining unit, a zone of lower permeability or a middle semi-confining unit, located between the upper and lower Floridan Aquifer. This area between 900 feet and 1350 feet below land surface consists largely of hard dolomites similar in nature to those in the zone immediately above it. This zone corresponds to layer 5 in the groundwater modeling done by SBWA. Previous regional modeling efforts have utilized model derived values to describe the middle semi-confining unit rather than site specific information showing the location, thickness or hydrogeological characteristics of the zone. Site specific data tends to confirm the lower permeability of this zone relative to the layers above and below it. Site specific data consists of a core sample, mineral content observed during the drilling of the test monitor well, and a Neumann-Witherspoon ratio analysis conducted during the aquifer performance test. The area between 1350 feet and 1450 feet below land surface also consists of dolomites but with greater permeability and greater transmissivity (the measure of an aquifer's ability to transmit water in a horizontal direction). This area corresponds to layer 6 in the groundwater modeling done by the SBWA. No site specific data exists beneath 1483 feet, representing the total depth of test well TM. Regional data does exist which characterizes the areas from 1500 feet below land surface to the bottom of the lower Floridan Aquifer as consisting of zones of varying lithology, and varying permeabilities. This zone which corresponds to layer 7 in the groundwater modeling done by Osceola County is not homogeneous or uniform over its entire thickness according to available regional data, consisting of geologic reports of deep wells in the east-central Florida area. All parties agree that in the area of the proposed wellfield, horizontal movement of water in the Floridan aquifer is from west, where the greatest recharge occurs along the Lake Wales Ridge, to east, where there is little or no recharge. Water quality in the upper Floridan as measured by chloride concentrations deteriorates as one moves from west to east. The Floridan aquifer beneath the BCWMA represents a transition zone between the recharge area to the west and high saline formation waters in the east. The dominant geochemical components in water beneath the BCWMA are biocarbonates. Water quality, as measured by chloride concentrations, also deteriorates with depth. Chloride concentrations, based on data derived from the drilling of well TM at the BCWMA, increase gradually from 306 milligrams per liter (mgl) at 410 feet, to 658 mgl at 1473 feet below land surface. Chloride concentrations increase abruptly to 1980 mgl in well TM at 1483 feet of depth. Evidence is inconclusive as to whether all of the proposed production wells will draw water exceeding 250 mgl in chloride concentrations. It is undisputed that most will, but chloride contours initially provided by SBWA's consultant indicate that the southernmost wells may produce water between 150 and 250 mgl. A comprehensive aquifer performance test (APT) was conducted at the BCWMA by the SBWA's consultant, Post, Buckley Schuh, and Jernigan, Inc. (PBSJ). The test was designed by the staff of the SJRWMD in consultation with the U.S. Geological Survey (USGS). This test yielded data which enabled PBSJ to calculate several aquifer characteristics for use in the groundwater modeling which was later done by SBWA's modeling consultant, Environmental Science and Engineering, Inc. (ESE). Eight wells were utilized in connection with the APT conducted at the BCWMA in January and February 1990. Three of the wells were dual zone monitoring wells capable of monitoring events in two different geologic units simultaneously. Three wells, including the test production well (TP) were open to the interval between 700 and 900 feet below land surface which was identified by the SBWA as the production zone. Typically APT's are run for 12 to 72 hours in Florida. Well TP was pumped for approximately 10 days at a rate equivalent to that expected during actual production while observations were made of water levels in all wells, including three off-site wells (the Holopaw test well, the Kempfer well and the Bruner well). All of the information the SBWA needed from the APT was obtained in the first hours of the test. Water levels in the area monitored during the APT ceased dropping due to pumpage within 1 hour after the pumping started. Three different analytical models were used to calculate a transmissivity value for the production zone, utilizing data derived during the APT. The result showed transmissivity in this zone to be approximately 2 million gallons per foot per day. This is a very high transmissivity value indicating a comparatively prolific aquifer, capable of producing the volumes of water requested in the application. As transmissivity increases, the cone of depression associated with pumpage tends to flatten out and be less steep. The cone of depression extends further out, creating a wider area of drawdown. Hydraulic conductivity is the measure of an aquifer's resistance to flow either in a vertical (KV) or horizontal (KH) direction. Two methods were used to calculate the hydraulic conductivity of the Hawthon Formation by PBSJ: laboratory analysis of a core sample taken from this unit, and a bail test (measuring an increase in water level over time) conducted on a well on site by the SJRWMD. Two different methods were used by PBSJ to calculate the hydraulic conductivity of layer 5: laboratory analysis of a core sample taken from that zone, and the Neuman-Witherspoon ratio analysis method. Porosity is the void space in porous media through which transport of particles, such as chlorides, can occur. Effective porosity has an impact on the ability of saline or dense water to move upward from depth toward a pumping well. The lower the effective porosity within an aquifer, the greater the potential for upconing of saline water within that aquifer. Effective porosity for layers 4 and 5 was calculated using two different methods, those being laboratory analysis of core samples taken from these zones, and analysis of acoustic logs generated during the APT. Each of these methods is accepted in the field of hydrogeology. Anticipated Impacts to Groundwater Levels and Flows as a Result of the Proposed Consumptive Use A numeric groundwater flow model is a computer code representing the groundwater flow process. Both SBWA and Osceola used numeric groundwater flow models developed by their consultants to predict and simulate the impacts associated with withdrawals proposed in the application. The SBWA used a finite difference model called INTERSAT for its simulations. INTERSAT is a widely used and accepted groundwater flow model. The model was run by ESE for the SBWA in the impact or drawdown mode. Drawdown or impact models simulate changes in water levels in response to a stress such as a pumping well. Drawdown models are an accepted and frequently used method to evaluate wellfield stress, particularly in association with a CUP application. ESE and PBSJ utilized several analytical models to first determine and later to verify the area to which the boundaries of their model would extend. The radius of influence of a well or wellfield is the distance from the center of pumpage extending out to where drawdowns caused by that pumpage reach zero. The boundary for a numeric groundwater model should be set at, or beyond, the radius of influence of the pumpage being simulated by the model. Based on the analytical models run by ESE and PBSJ the radius of influence of the wellfield proposed in the application is 43,000 to 45,000 feet. The approximate distances of the boundaries set in INTERSAT model from well TP were 50,000 feet to the east, 40,000 feet to the west, 40,000 feet to the north and 50,000 feet to the south. The INTERSAT model covers a total area of 320 square miles. This size falls somewhere between a regional model and a local model, and is adequate in size to address the impacts associated with the proposed withdrawals. The vertical boundary of SBWA's model extends to 1450 feet below land surface and, as stated above, is divided into 6 layers. The 1450 feet depth generally coincides with the limits of site specific data generated during the APT. The six layers in the SBWA flow model coincide with the six distinct geologic units identified by PBSJ in their APT report. The site specific data generated by the APT was utilized, along with other regional modeling studies, to arrive at a set of "conservative" aquifer parameters to be utilized in the INTERSAT model. "Conservative" parameters for purposes of this application are those which would tend to overpredict drawdown in the surficial aquifer and the production zone, while allowing for more upconing of dense water from the bottom of the model. The selection of "conservative" aquifer parameters by SBWA involved taking site specific values, comparing them with the ranges of values reported in the other available regional models and selecting values which, while still within the range of reported values used in other studies, would tend to show greater impacts for the areas of primary concern than the site specific values. Every aquifer parameter utilized in SBWA's groundwater flow model falls within the range of values reported in at least one of the groundwater modeling studies previously done in this region. The size of the grids utilized in the SBWA model were 500 feet by 500 feet within the vicinity of the wellfield. Grid sizes expand as one moves toward the outer boundaries of the model. The fineness of the grids used by ESE, particularly in the wellfield area, allows for accurate representation and resolution of surface water features, impacts in the production zone and for evaluating the effects of saltwater upcoming in the transport model also done by ESE. Within the radius of influence of the proposed wellfield, there are no existing wells in layers 5 or 6. The ESE model simulations for 18.8 mgd pumpage predict a maximum drawdown in the surficial aquifer (layer 1) of 0.14 feet centered primarily within the BCWMA. At a distance of 1 mile from the wellfield the impact drops to 0.12 feet. None of the existing legal users of water in layer 1 within the radius of influence of the proposed wellfield will suffer a ten percent or greater reduction in withdrawal capacity from their wells solely as a result of the proposed withdrawals, since 10 percent reduction would require at least 3 feet of drawdown. The ESE model simulations predict a maximum drawdown caused by the proposed pumpage of 4.5 feet in layer 3 centered along the alignment of wells and primarily within the BCWMA. At a distance of 2 miles, the drawdown drops to 2 feet. At the Brevard-Osceola County line the drawdown in layer 3 is approximately .5 feet. Petitioner Deseret's flowing wells are drilled in layer 3 and are located within the area where a drawdown of 1 foot is predicted in layer 3 by the ESE model. Deseret uses its property for a cow/calf ranching operation and has approximately 32,000 head of cows. Deseret uses 39 flowing wells east of state road 192 to irrigate pasture, water cattle and supply drinking water. Deseret possesses a valid CUP for a portion of the total flow capacity from those wells. Seasonally, the wells flow at different rates, but they are most relied upon in dry conditions when the natural flow would be decreased. It is unlikely that the proposed SBWA withdrawals will stop the flow of any of Deseret's wells; and it is unlikely that the flow will be reduced by more than 10 percent. Deseret and Osceola's consultants do predict a greater drawdown and opine that approximately 12 of Deseret's wells will cease flowing as a result of the SBWA withdraw As addressed below, the modelling by Petitioner's consultants, upon which those predictions are based, is less reliable than that of SBWA's consultants. If the effects are greater than predicted, mitigation in the form of installation of pumps is possible, albeit inconvenient and expensive. Mitigation would have to be provided by the applicant, SBWA. The drawdowns predicted by the ESE model for layer 4 are not significantly different from those for layer 3. It is anticipated that no legal user of water within the radius of influence of the proposed wellfield will suffer a 10 percent or greater reduction in withdrawal capacity for its wells, as a result of SBWA's proposed withdrawals. Petitioners' consultants, Hartman and Associates, (Hartman) modeled a significantly larger (4900 square miles) and deeper (3000 feet) area than did SBWA. The model makes its predictions based on one data point for every 49 square miles within the modeled area. Petitioners utilized much larger model grids in the wellfield area (2000 feet by 2000 feet) than did the SBWA. Grid of this size lacks the resolution necessary to evaluate wellfield impacts. Petitioners selected their aquifer parameters from another regional modeling study done in 1985 rather than using site specific data. Those parameters were then adjusted or calibrated until a match was obtained to a computer created potentiometric surface which was supposed to reflect the potentiometric surface for May 1990, an uncharacteristically dry period. The created potentiometric surface to which Hartman calibrated its model varies greatly from the potentiometric surface as reflected in the actual data points from which USGS derives its potentiometric surface maps. While no model is perfect, and actual data is preferable, in the absence of all the actual data that is needed, the ESE model is a more credible predictor of drawdowns. Anticipated Impacts to Groundwater Quality as a Result of the Proposed Consumptive Use Solute transport models are computer models designed to simulate the movement of mass, in this case -- chlorides -- through a groundwater flow system. These models are linked to, and are dependent on flow fields generated by groundwater flow models. In order to predict changes in water quality anticipated to occur as a result of its proposed withdrawals, SBWA's consultants used a solute transport model called HST3D. Developed by the USGS, this model is widely used and accepted. For simulations using the HST3D model, SBWA used the flow field and a portion of the grid generated by its INTERSAT groundwater flow model. The HST3D simulations run by ESE utilized a cross section of the INTERSAT model grid extending through row 26 of that grid, which is the row containing the line of 9 proposed wells running on an east-west axis. Use of a cross sectional grid is an appropriate method by which to examine salt water intrusion. Upconing, to the extent that it will occur as a result of the proposed pumpage, would be greatest within the cross section containing the 9 wells. The cross section extends two miles through the wellfield to the west. As chloride concentrations in water increase, the density of the water increases. Density can retard the degree of upconing when chloride concentrations are as low as 1000-2000 parts per million and becomes significant at 3000-5000 parts per million. Failure of a model to consider density effects, when appropriate, would tend to overstate upconing. HST3D does consider density effects. SBWA's consultant ran several simulations with the HST3D model to predict changes that would occur as a result of the proposed pumpage in chloride concentrations over 7, 14 and 30 year time periods. These simulations utilized the same aquifer parameters as the INTERSAT model together with the effective porosity values derived from site specific data. Assuming a starting chloride concentration of 1000 mgl at the bottom of layer 5, the measured concentration at that level in well TM on the BCWMA site, after 30 years of pumpage at 18.8 mgd, the chloride concentrations in layer 4 would increase by only 100 mgl. The simulations for 7 years of pumpage which is the duration of the proposed permit, show that the predicted increase in chloride levels would be substantially less than 100 mgl. Other HST3D simulations were run by SBWA for a pumpage rate of 35 mgd utilizing beginning chloride concentrations of 5,000 mgl and 10,000 mgl, respectively at the bottom of layers. The results did not show any significant changes in chloride concentrations in layer 4 over and above those shown when a lower starting chloride concentration was assumed. In a circumstance where, as here, the chloride concentrations in the zone from which water is proposed to be withdrawn exceeds secondary drinking water standards (250 mgl), the SJRWMD evaluates the existing legal water uses within the area that would be impacted by the proposed use. If it is determined that the increase in chloride concentrations caused by a proposed use would detrimentally affect other existing legal users or the applicant, only then is the increase deemed to be "significant". Within the layers of the aquifer which would experience increases in chloride concentrations as a result of the proposed withdrawal, layers 4, 5 and 6, no existing users of water would be detrimentally affected. Petitioner Deseret's closest wells to the proposed wellfield are in layer 3 where chloride levels will not be affected by the proposed wellfield within the 7 year duration of the proposed permit or even beyond that period. Further, the use Deseret makes of the water from the wells in closest proximity to the proposed wellfield, pasture irrigation, can tolerate significantly higher chloride concentrations than will exist even directly beneath the wellfield in level 4 after 30 years of pumping. Use of water for public supply purposes is considered by SJRWMD to be in the public interest. Utilization of the water beneath BCWMA for public supply purposes, even with some increase in chloride concentrations in the source of the water over the life of the permit, does not on balance detrimentally affect the public interest. Two different solute transport models were done by Petitioners' consultants, one a numeric model and the other an analytical model. The numeric model done by Hartman, RANDOMWALK, does not predict changes in chloride concentrations within an aquifer, but rather tracks movement of particles. RANDOMWALK does not account for density effects. The analytical model done by Prickett for the Petitioners relies on assumptions, many of which are not met in the aquifer system at BCWMA. Those assumptions relate to uniformity of the system, for example: porosity and permeabilities, and lack of regional gradients. The solute transport models utilized by the Petitioners are less reliable for predicting water quality changes resulting from the proposed pumpage than the model utilized by the SBWA. Salt water intrusion is a dramatic increase of chloride levels in an aquifer layer. The saline water encroachment which occurs from the wellfield stress will be in the lower confining unit. There will be limited degradation in the lower part of the production zone. The wellfield will not induce significant lateral intrusion from the east. There will not be any dramatic changes in chlorides. The movement of the chlorides is confined to the locality of the wellfield. Most of the movement is vertical and is of limited increase. The proposed Bull Creek withdrawals will not aggravate any currently existing salt water intrusion problems. The reject brine water from the RO treatment plant will be disposed of in deep injection wells in Brevard County. These injection wells would deposit the brine into a receiving body of water in the Oldsmar geologic formation. The brine reject will have a total dissolved solids (TDS) concentration of approximately 7,000 mgl. The receiving water into which the brine will be injected approximates sea water, with TDS concentrations in the range of 36,000 mgl. The receiving body will obviously not be further degraded. Environmental Impacts of the Proposed Consumptive Use District staff, SBWA consultants and Osceola's consultants independently conducted onsite field investigations of the BCWMA to evaluate the vegetative communities and land uses which exist on site. Each consultant prepared a habitat map identifying the various vegetative communities found at the site. While relatively pristine, the BCWMA has been logged and grazed by cattle in the past. The impacts of man's activities have been remediated by ceasing the activity. There are few permanent incursions, such as roads, canals and buildings. The area is a very diverse landscape, with a mosaic of different types of plant communities. There are various upland and wetland habitats. The variety of wetlands are forested and non-forested, deep and shallow, open and closed. These wetlands perform important functions, including water storage and purification, aquifer recharge, flood control, and provision of food sources and habitat for wildlife, and they are "factories" for producing the materials needed by many higher organisms. The wetlands on site are structurally complex and are good habitat for macro- invertebrates and the fish and higher organisms that feed on them. A number of these wetlands are shallow, isolated wetlands. During periods of inundation, when the wetlands fill up with water and interconnect with the Bull Creek drainage system, the system exports various organisms to the wetlands. Fish that are live bearers move into isolated wetlands during periods of inundation, and they and their offspring become a source of food for birds. Fish species that lay eggs can withstand desiccation (total drying out) can survive the temporary drying of wetlands, but live bearers must repopulate during periods of inundation. The mixed wetland hardwoods on site contain a diversity of bugs, crawfish, mayflies, damsel flies, midges, and snails. Some of these are important food sources for higher organisms. The apple snail, for example, is an important food source for such birds as the limpkin and the endangered snail kite, and its eggs are food for crawfish and other organisms. The biological communities that exist in the wetlands and uplands at the site are determined by a number of factors, including the depth and duration of the hydroperiod, soils, climate, temperature, and availability of sunlight. These communities and their habitats will react to changes in light, water, temperature, and many other subtle effects, causing changes in plant diversity and structure, the areal extent of certain types of habitats and wetlands, and utilization by wildlife. Natural fluctuations in the hydroperiod also cause these changes, generally from the exterior edges of a wetland to the interior. The wetlands in the BCWMA have been able to withstand the natural drought and flood periods, or they wouldn't be there today. Periodic burning is essential to the health of ecosystems such as in the Bull Creek area. Fires reduce the prevalence of species less tolerant to fire, allow other species to strengthen their presence, return organic material to the soil, and reduce the fuel available for wild fires. Originally occurring naturally as a result of lightening strikes, prescribed burns are now undertaken by agencies such as the Division of Forestry and the Game and Fresh Water Fish Commission to replicate the beneficial functions of natural periodic burning. Fire management is used as a land management technique at BCWMA and continued fire management at the BCWMA will maintain a natural ecological setting typical of Florida. Slight variations in elevation which mark the difference between wetlands and uplands can result in utilization of the areas by different animal communities. Where different types of plant communities meet, an "ecotone" is created. Where an ecotone exists, the "edge effect" of the competition between the two communities occurs. The result of the edge effect is higher plant and animal species diversity, which is extremely important to the natural community. Some animals make specific use of the ecotone for habitat and food resources. Many amphibians, frogs in particular, live in the ecotone. Some birds will not roost in the upland forests but will roost in the edge of the forest adjacent to wetlands. Wetlands in the BCWMA are connected to the remainder of the Bull Creek system through groundwater resources. Their biological and ecological communities are also connected as the same organisms move throughout the system. Isolated wetlands also exhibit a "moving edge" effect, where changes in the surface water and water table levels cause different plants, or plants at different levels of maturity, to exist in the wetland and its perimeter. This increases the productivity of the wetland by making it attractive to a wider variety of plant and animal species. If the expansion and contraction of isolated wetlands is reduced by lowered water levels, the smaller wetlands would exhibit a reduced edge effect, and the cumulative effect of this reduction over time would disrupt the functioning of the wetland-upland system. Isolated wetland systems are more sensitive to drawdowns in the surficial aquifer than connected wetland systems because the drainage area contributing water to the wetland system is smaller. Isolated herbaceous wetland communities are the most sensitive of the vegetative communities on BCWMA to drawdowns in the surficial aquifer. The surficial aquifer fluctuates naturally as much as five feet annually. Rainfall is the primary source of water for the surficial aquifer. Water levels in the surficial aquifer respond very quickly to rainfall events. Hydroperiods of the wetland systems in the BCWMA respond to rainfall and surficial aquifer levels. The wetland hydroperiods vary from year to year, and wetland ecosystems have adopted to those annual changes. But a groundwater withdrawal from the surficial aquifer in the Bull Creek area would cause a corresponding lowering of the surface water level, since the wetlands are not "perched", or separated from the aquifer by a confining layer. A drawdown would lower water levels throughout the hydroperiod, under both high water and low water conditions, with a more pronounced effect during the dry season and drought periods. Some of the over twenty threatened and endangered plant species present at Bull Creek grow in shallow, marginally wet areas. Changes in even a few inches of groundwater would cause these plant species to be retarded in growth, and their abundance would decrease or they would die out at the site. Many of the wetlands are shallow, broad, sloping areas, and groundwater elevation changes of just a few inches will cause changes in the areal extent of these wetlands. Even the .14 foot drawdown predicted by SBWA's modeling would affect shallow inundated or saturated systems by changing the moisture level at the surface, particularly by affecting the lowest water levels. Changes in the vegetative composition of wetlands will affect the macro-invertebrate characteristics of a site. For example, as water levels change, the density of the vegetation (in terms of number of plant stems per acre) can decrease, leaving fewer places for the macro-invertebrates to hide, and the populations of macro-invertebrates will decrease through predation. As food sources, habitat and breeding grounds decrease, those animal species that can relocate will attempt to do so. Relocation can adversely affect the survival of the species; for example, a wood stork unable to find a particular food upon which it is dependent at a particular interval in its life cycle may abandon its nest and its young. Animals that attempt to relocate may find that there is not a suitable similar habitat available, making their attempt to adjust to the change in their environment unsuccessful. The proposed use will not significantly affect the stages or vegetation of the upland communities at the BCWMA because they are not as dependent on saturation or inundation as a wetland community. Forested wetland systems, be they isolated or connected, will not be influenced by a drawdown of the magnitude predicted by SBWA for the surficial aquifer. Forested systems have deep root zones and the canopy provides shading to the strata below. Forested systems are able to tolerate natural changes in hydrology. The SBWA assessment does not offer any detailed cataloguing of the plant and animal communities on site, or a description of how the systems operate or interface with each other. It does not provide sufficient information to be able to assess the impacts of the proposed wellfield on these systems. There was insufficient information presented by the applicant to conclude that the environmental harm to be caused by operation of a wellfield at the BCWMA has been reduced to an acceptable level. The applicant relied on the fact that drawdowns in the surficial aquifer will be minimal, without fully considering the impact of those minimal drawdowns on a fragile wetland ecosystem during a dry period. Water Demand The SBWA was created by special act in 1983 as a dependent special district for the purpose of developing regional water supplies and transmission of water to water distribution systems. In its existence so far, its labors have been in the former, and none in the latter category. Efforts to develop a regional water supply have been frustrated by litigation, by reluctance of local public systems to give up their authority and by delays in pursuing and processing CUP applications, two of which are still pending, in addition to the instant application. The City of Melbourne's public water system provides water to Melbourne, Palm Bay and West Melbourne, and to some unincorporated areas surrounding Melbourne. It also supplies water to the area called south beaches, comprised of the Brevard County area south of Patrick Air Force Base, including Satellite Beach, Melbourne Beach, Indiatlantic and Indian Harbor Beach. The current water supply is Lake Washington, which is part of the chain of lakes on the St. Johns River. The city of Melbourne was granted a CUP on January 15, 1991, for withdrawals from Lake Washington, ranging from 27.15 million gallons maximum daily withdrawals in 1991 to 21.7 million gallons maximum daily withdrawals in 1998. In addition, Melbourne has planned a new facility and has the CUP to withdraw 8.13 million gallons a day from the Floridan Aquifer commencing in 1993. After reverse osmosis treatment, the groundwater withdrawal will yield 6.5 million gallons a day finished water, making up the difference from reduced withdrawals from Lake Washington. Approximately 56 potable water systems have been identified by SBWA in South Brevard, south of the Pineda Causeway. Almost all are small private systems. Besides Melbourne, the other major water supplier in the area is General Development Utilities (GDU), serving the City of Palm Bay. GDU's CUP expires in 1993 with an average daily withdrawal of 6.5 mgd and maximum daily withdrawal of 8.5 mgd. It has ample capacity until 1996, and beyond to the year 2000, if an additional Department of Environmental Regulation capacity rating is obtained. The total capacity of the two major existing facilities is approximately 30 mgd and total existing consumptive use quantities (including existing CUPs with expiration dates varying from 1993 to 1998) approach 40 mgd. The current SBWA water master plan assumes that existing sources need replacing. More specifically, SBWA, if this CUP is granted, seeks to replace Lake Washington as the primary source of water in the area with the groundwater obtained from the BCWMA wellfield. An agreement between the City of Melbourne and SBWA provides that the City will initially purchase 8 mgd, plus all future needs of water from the SBWA. This 8 mgd would be used by Melbourne prior to using its 6.5 mgd finished water from the RO facility, and the RO water would be used prior to withdrawals from Lake Washington. The agreement, dated January 9, 1991, acknowledges the need for, and specifically authorizes improvements to Melbourne's Lake Washington Water Treatment Plant, including the conversion of the existing high service pumping station to a low service pumping station with average daily capacity of 20 mgd and maximum capacity of 25 mgd. (SBWA Ex. 49) GDU is a private utility and currently is outside the jurisdiction of the SBWA. General Development Corporation is in receivership and the City of Palm Bay is negotiating for purchase of the utility. If the purchase is successful, the supply will become publicly owned and subject to the jurisdiction of the SBWA. The City of Palm Bay is not bound to purchase GDU at any price, and the requirement that it would shut down its newly purchased facility to receive water from SBWA is a disincentive to the acquisition. In the meantime, GDU has no incentive to reduce CUP capacity and devalue its facility. GDU's service has been uninterrupted and reliable. Contamination to the surface aquifer utilized by GDU has been successfully treated. Although septic tanks proliferate in Palm Bay, their location, as well as the presence of confining layers in the surficial aquifer, reduce the susceptibility of GDU wells to contamination from septic tanks. The applicant's concerns about unreliability and safety of Lake Washington as a continued water source are unsubstantiated by the weight of evidence in this proceeding. Surface water facilities have been used in Florida since before the turn of the century and no major facility has ever been off-line one day due to raw water contamination. Nor has any major Florida surface water plant ever been sabotaged. There is a greater chance in Florida of problems with pipeline failures, and the miles of pipes planned to transmit ground water from Bull Creek east to SBWA consumers increase the chances of those problems. Recently, the SJRWMD Upper Basin Project has significantly improved the water quality and quantity in Lake Washington through restoration of marshlands in the upper basin and capping flowing wells. Restored marsh areas will allow for additional removal of nutrients and provide an additional storage to the Lake Washington/Upper Basin system, significantly improving safe yield quantities. Comparisons of concentrations of raw water chlorides and total dissolved solids for the drought years of 1989 and 1990, show significant reductions for the latter time frame. Recent evaluations indicate that Lake Washington would be acceptable in terms of chlorides and TDS concentrations for a 35 mgd withdrawal, even during 50 and 100 year droughts. Water quality improvements to Lake Washington can be directly related to the Upper Basin project. Trihalomethanes are regulated by the Safe Drinking Water Act. They are produced by the disinfection process of treating raw water with chlorines, and they are carcinogenic. A previously experienced problem at the Melbourne plant has been corrected with operational changes. As recently as 1988, an internal staff report by SJRWMD staff provided: Lake Washington has been a reliable source of public water supply since 1960 and can remain so in the future with the continuation of sound basin planning and watershed management by the St. John's river Water Management District. The quality of the raw water from Lake Washington is subject to annual and seasonal variations that make the treatment process more difficult, and the quality of the delivered water less consistent, than would be the case with a groundwater supply. A supplemental water source near Lake Washington would improve the quality of the water delivered to the users, would increase the total volume that could be taken from the lake in times of stress, and would provide a reliable alternative in case of emergency. The upper zone of the Floridan Aquifer within south Brevard County has the potential to supply a significant portion of the area's future water needs with existing low-pressure, reverse osmosis technology at a cost that is comparable to current supplies.

Recommendation Based on the foregoing, it is hereby, recommended that the SBWA application for CUP be denied. RECOMMENDED this 12th day of March, 1992, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of March, 1992. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 91-1779, 91-1780, & 91-1781 The following constitute disposition of the findings of fact proposed by each party. Petitioner, Osceola County These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-5, 7-8, 14, 21-22, 24-25, 27-28, 30, 32, 35, 62-65, 73, 104, 113, 116-125, 127, 129-130, 132-138, 140, 154, 157-158, 164, 167-168, 183, 186, 189, 191-195, 197-200, 202-204, 209, 212. These findings are rejected as contrary to or unsupported by the weight of evidence: 37-38, 48, 51, 53, 56, 66, 79-81, 84-90, 92-94, 102-103, 105-107, 110-112, 115, 128, 171-172, 212(d), (f) and (g), 213-214. These findings are rejected as cumulative, unnecessary or irrelevant: 6, 9- 13, 15-20, 23, 26, 29, 31, 33-34, 36, 39-47, 49-50, 52, 54-55, 57-61, 67-72, 74- 78, 82-83, 91, 95-101, 108-109, 114, 126, 131, 139, 141-153, 155-156, 159-163, 165-166, 169-170, 173-182, 184-185, 190, 196, 201, 205-208, 210-211, 212(e), 215. Petitioners, Triple E, Triple N, East Central Florida Services, Inc., and Deseret These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-6, 8-9, 16-20, 22-25, 27-28, 30-31, 50- 56, 59-60. These findings are rejected as contrary to or unsupported by the weight of evidence: 7, 12, 32, 34-37, 40, 42, 44, 48, 49, 58. These findings are rejected as cumulative, unnecessary or irrelevant: 10- 11, 13-15, 21, 26, 29, 33, 38-39, 41, 43, 45-47, 57, 61-63. Respondent, South Brevard Water Authority These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-6, 9-11, 13, 16-24, 28, 30-34, 36, 38, 46-48, 61, 64, 70, 72-74, 90-91, 94-98, 105-108, 110-111, 113, 115-116, 121, 126-129, 133, 149, 152, 157, 169, 179, 181-190, 192-194. These findings are rejected as contrary to or unsupported by the weight of evidence: 41, 130-132, 156, 158, 167, 174, 177. These findings are rejected as cumulative, unnecessary or irrelevant: 7-8, 12, 14-15, 25-27, 29, 35, 37, 39-40, 42-45, 49-60, 62-63, 65-69, 71, 75-89, 92- 93, 100-104, 109, 112, 114, 117-120, 122-125, 134-148, 150-151, 153-155, 159- 166, 168, 170-173, 175-176, 178, 180, 191. Respondent, St. Johns River Water Management District These findings have been adopted in full or in substantial part in the recommended order submitted herewith: 1-8, 10-22, 24-36, 38-44, 47-62, 64-88, 90, 92-116, 118-122, 124-130, 132-142, 144-151, 159-160, 164, 166-167, 169, 171, 174-175, 177, 193-196, 198, 202, 206. These findings are rejected as contrary to or unsupported by the weight of evidence: 131 (the conclusion), 153-154, 156-157, 161-162, 197, 204, 207. These findings are rejected as cumulative, unnecessary or irrelevant: 9, 23, 37, 45-46, 63, 89, 91, 117, 123, 143, 150, 152, 155, 158, 163, 165, 168, 170, 172-173, 176, 178-192, 199-201, 203, 208-210. COPIES FURNISHED: Segundo J. Fernandez, Esquire Scott Shirley, Esquire OERTEL, HOFFMAN, FERNANDEZ & COLE, P.A. Post Office Box 6507 Tallahassee, FL 32314-6507 Douglas P. Manson, Esquire BLAIN & CONE, P.A. 202 Madison Street Tampa, FL 33602 Clifton A. McClelland, Esquire POTTER, McCLELLAND, MARKS & HEALY, P.A. Post Office Box 2523 Melbourne, FL 32902-2523 Wayne Flowers, Esquire Nancy B. Barnard, Esquire St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429 Neal D. Bowen, County Attorney Osceola County Room 117 17 South Vernon Avenue Kissimmee, FL 32741 Carol Browner, Secretary Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Dept. of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (7) 120.52120.5727.15373.019373.042373.069373.223 Florida Administrative Code (1) 40C-2.301
# 5
CHARLES P. PAGE vs SARASOTA COMPANY UTILITIES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-002002 (1992)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida Mar. 27, 1992 Number: 92-002002 Latest Update: Jan. 15, 1993

The Issue Whether Respondent Sarasota County Public Utilities Department (Sarasota County) has provided reasonable assurances pursuant to Rule 17- 555.530(1)(a), Florida Administrative Code, that its proposed water treatment plant will comply with each applicable water quality standard contained in Part III, Chapter 17-550, Florida Administrative Code. Whether Respondent Sarasota County has provided reasonable assurance pursuant to Rule 17-555.530(1)(b), Florida Administrative Code, that its proposed water treatment plant meets adequate engineering design complying with the applicable engineering principles established in Rules 17-555.310 through 17-555.160, Florida Administrative Code.

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: STIPULATED FACTS Sarasota County Utilities Department is a department established by Sarasota County, a political subdivision of the State of Florida and operates a public utility department which is charged with meeting, among other things, potable water needs of the residents of Sarasota County. At all times pertinent to the issues herein, HRS was responsible for receiving applications and issuing permits for the construction of water treatment plants and the accompanying well field. Petitioner, Charles P. Page, is a resident of Sarasota County and resides at 259 Glen Oak Road, Venice, Florida. Sarasota County filed an Application for a Water Treatment Plant Construction Permit with HRS seeking to construct a well water collection system and a 12 mgd - electrodialysis treatment plant having an auxiliary power system to provide power for the well field and water treatment plant. Sarasota County has previously obtained a water use permit from the Southwest Florida Water Management District (SWFWMD) #208836.00, restricting Sarasota County to feed water for the water treatment plant to 7,303,000.00 gallons average daily withdrawal and 9,625,000.00 gallons peak monthly withdrawal. Sarasota County has received permits for the eleven (11) production wells from HRS. It was the duty of HRS to review the plans and specifications and all supporting documentation to assure that they address and meet every requirement listed in Rule 17-555, Florida Administrative Code, for the issuance of a construction permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, accordingly, RECOMMENDED: That a final order be entered issuing permit No. PATS No. 204307 & WC No. 1591-91-036 to Respondent Sarasota County, as set forth in the Notice of Intent To Issue dated February 20, 1992, provided that the grant of the subject permit shall include the general and specific conditions in the Intent To Issue with the further recommendation that the third required specific condition found on page 1 of the Specific Conditions be modified as follows: Construction of the electrodialysis reversal water treatment plant covered by this permit shall not begin prior to the issuance of a permit as required by State of Florida Department of Environmental Regulation for the EDR concentrate discharge facility. DONE and ENTERED this 21st day of October, 1992, at Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of October, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-2002 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statute, on all of the Proposed Findings of Fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner 1. The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(1); 22(47); 23(48); 24(19-20) 29(49); 38(5); 39(19); 42-43(19,20); and 51(49). 2. Proposed finding(s) of fact 2,3,5,6,7,11,14,15,16,18, 19,20,21,25,26,30,31,35,40,45,46,47,49,and 50 are neither material nor relevant to this proceeding or the conclusion reached in the Recommended Order. Proposed finding(s) of fact 4,8,9,10,12,13,17,27,28,and 41 are rejected as not being supported by competent substantial evidence in the record. Proposed finding(s) of fact 32,33,34,36,37, and 48 are unnecessary. Proposed finding of fact 44 is rejected as not being the "opinion" of the Hearing Officer. The transcript will show that the Hearing Officer was only restating the testimony of Judith Richtar. But see Finding of Fact 49. Rulings on Proposed Findings of Fact Submitted by the Respondent Sarasota County The following proposed findings of fact are adopted in substance as modified if the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 20(1) - 20, respectively); 21(27); 22 - 26(22 - 26, respectively); 27(28); 28(29); 29(31); and 30 - 44(32 - 46, respectively). For proposed findings of fact 45 through 65 see Findings of Fact 51 and 52. Proposed findings of fact 66 through 68 are unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent Department of Environmental Regulation The Respondent Department of Environmental Regulation adopted Sarasota County's proposed findings of fact 1 through 44, 63 and 64, and 66 with modification. Therefore, the rulings on the Department's proposed findings of fact would be the same as the previous rulings on Sarasota County's proposed findings of fact adopted by the Department. COPIES FURNISHED: Bruce Wheeler Pitzer, Esquire 546 47th Street Sarasota, FL 34234 William A. Dooley, Esquire Nelson, Hesse, Cyril, et al. 2070 Ringling Blvd. Sarasota, FL 33237 Joseph W. Landers, Esquire Landers & Parsons 310 W. College Avenue, 3rd Floor Tallahassee, FL 32301 W. Douglas Beason, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57403.861403.862
# 6
RAYMOND VAN LOON vs DEPARTMENT OF HEALTH, 03-004285SED (2003)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Nov. 18, 2003 Number: 03-004285SED Latest Update: Jun. 03, 2004

The Issue The issue in the case is whether the Petitioner's employment position was properly reclassified from Career Service to Selected Exempt Service pursuant to Section 110.205(2)(x), Florida Statutes (2001).

Findings Of Fact Beginning on April 23, 2001, and at all times material to this case, the Petitioner was employed by the Hillsborough County Health Department as a Professional Engineer III, a position requiring state registration in accordance with Chapter 471, Florida Statutes (2001). The job announcement related to the Petitioner's employment states that the position "oversees" the drinking water program and engineering-related activities. The position was responsible for management of "Safe Drinking Water" permitting and compliance enforcement program entailing a variety of duties, including planning, organizing, and coordinating work assignments. According to organizational charts before and after the date of the reclassification of the position, the Professional Engineer III position had direct supervision of four employment positions, and indirect supervision of eight additional positions that reported to one of the Petitioner's direct employees. The position of Professional Engineer III includes a substantial amount of engineering review responsibilities, and is charged with direct supervision of the Safe Drinking Water Act program staff and Limited Use Drinking Water program staff. The position description categorized the job responsibilities as "regulatory," "supervising/training," "enforcement," "policies and procedures," "record keeping," "education," and "committees/other duties." Review of the specific duties indicates that the Petitioner's supervisory responsibilities were included within several of the categories. Included within the "regulatory" category was "[e]nsures staff conduct field inspections of public water systems. . . . Supervisor is responsible and accountable for field staff." Included within the "supervising/training" category were the following duties: Supervises Engineers to ensure all programs in the Safe Drinking Water Program are completed according to the agreement with DEP and the policies and procedures of the Department of Health. Supervises an Environmental Supervisor II to ensure that all programs in the Limited Use Drinking Water Program and Private Drinking Water Program are completed according to the F.S., F.A.C. and county regulations. Supervises staff review of engineer's plans. Supervises and reviews the preparation of non-compliance letters written by staff regarding enforcement actions. Provide training to new Health Department staff in all aspects of EHS at least once a year (standardized presentation). Perform field inspections (documented) with personnel on a quarterly basis to evaluate staff performance and for Quality Improvement (QI) in accordance with office policy. Telephone regulated facilities each quarter to determine customer satisfaction . . . in accordance with office policy. Develop training modules for specific program areas (public drinking water systems) and maintain them accurate and current. Provide those training modules to new EH staff and twice a year to existing EH staff. Assign staff to special work areas as necessary and perform field inspections (staff shortages, vacation/leave time, and natural disaster). Evaluate personnel's work, plan work load, special tasks to include efficiency. Included within the "enforcement" category were the following duties: Reviews appropriate enforcement activities generated by staff and assure timely progress of formal enforcement from compliance to enforcement. Ensures the time progress of enforcement cases by working closely with the compliance section of the Public Drinking Water Program in bringing non-compliant clients into enforcement. Follow up on violations of FAC and/or FS and ensure compliance is achieved or enforcement action is taken. Included within the "policies and procedures" category was the responsibility to "[r]eview daily activity reports and corresponding paperwork each day." The Petitioner was responsible for managing the daily workflow of the office. He planned, directed, and reviewed the work performed by his employees. The Petitioner was responsible for the evaluation of all employees under his direct supervision, including newly hired probationary employees. The Petitioner was responsible for review of the evaluations for employees for whom he had indirect supervisory duties, and he also provided his own independent evaluation of their performance. The Petitioner was responsible for the discipline of employees. At one point he had to counsel an employee who was consistently late to arrive for work. The Petitioner was also responsible for seeking qualified applicants for position openings. He was responsible for initiating the employment process. He chose the panel that interviewed applicants, designed the interview questions, participated in interviews, and made the final recommendation as to the person hired. He had the authority to decline to fill an open position if he deemed that the applicants lacked sufficient qualification. The Petitioner claims that the majority of his time was spent in review of permit applications and related engineering tasks. The evidence fails to support the assertion. The Petitioner's claim appears to essentially relate to a period of time subsequent to the July 1, 2001, reclassification of the position. During the time between his initial employment and the date of the position reclassification, the Petitioner was primarily a supervisory employee and had little, if any, permit review responsibilities. The office was fully staffed with other employees who were directly responsible for review of permit applications and related field reviews. In autumn of 2001, after the position was reclassified, the office began to lose employees, resulting in an increased workload for the remaining workers. At this point, the Petitioner began to undertake a substantial role in the actual review of permit applications in addition to his supervisory duties. Nonetheless, the Petitioner remained responsible for supervision of remaining employees. The Petitioner was also responsible for filling the vacant positions.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Education enter a Final Order finding that the "Professional Engineer III" position held by Raymond Van Loon on July 1, 2001, was properly classified into the Selected Exempt Service. DONE AND ENTERED this 21st day of April, 2004, in Tallahassee, Leon County, Florida. S WILLIAM F. QUATTLEBAUM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 2004. COPIES FURNISHED: Stephen W. Foxwell, Esquire Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1703 Aaron J. Hilligas, Esquire AFSCME Council 79 3064 Highland Oaks Terrace Tallahassee, Florida 32301 Maria N. Sorolis, Esquire Allen, Norton & Blue, P.A. 324 South Hyde Park Boulevard Hyde Park Plaza, Suite 350 Tampa, Florida 33606 Jerry G. Traynham, Esquire Patterson & Traynham Post Office Box 4289 315 Beard Street Tallahassee, Florida 32315 William E. Large, General Counsel Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701 R. S. Power, Agency Clerk Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701

Florida Laws (5) 110.205110.602110.604120.57447.203
# 7
ELSBERRY AND ELSBERRY vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-002095 (1975)
Division of Administrative Hearings, Florida Number: 75-002095 Latest Update: Mar. 21, 1977

Findings Of Fact Application 7500165 requested average withdrawal of water of 1,804,750 gallons per day from 4 wells located about a mile east of Highway 41 and a mile north of Apollo Beach. The four wells would be for irrigation of tomato crops on total acreage of 4 acres located in Hillsborough County (Exhibit 1, Testimony of Elsberry and Boatwright). Notice of hearing as to the application was published in a newspaper of general circulation in accordance with statute and rule (Exhibit 3). A letter of objection from Joseph S. Benham, Apollo Beach, Florida, dated November 19, 1975 was submitted to the Water Management District, wherein he expressed concern regarding water shortages and, although he does not seek to totally deny the application, is of the belief that the district must insure sufficient controls and management of irrigation activities so that resources are not wasted, water runoff to drainage ditches is eliminated and renewed justification is given each year for the withdrawal (Exhibit 2). A representative of the District staff established that there would be no violation of statutory or regulatory requirement for issuance of a consumptive water use permit in this case except as to the fact that potentiometric level of the applicant's property would be lowered below sea level as a result of withdrawal. It was agreed at the hearing that a period of thirty days should be granted both parties to formulate a stipulation as to control of runoff. An unsigned stipulation was received from the Water Management District by the hearing officer on March 1, 1976, which provided that the permit would be granted with the following stipulations: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expense install metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. (Testimony of Boatwright, Exhibit 4).

Recommendation That application 8500165 submitted by Elsberry and Elsberry, Inc. Route 2, Box 70 Ruskin, Florida, for a consumptive water use permit be granted with the conditions as follow: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expenseinstall metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. That the Board grant an exception to the provision of Rule 16J- 2.11(4)(e), F.A.C., for good cause shown. DONE and ENTERED this 15th day of March, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Elsberry & Elsberry, Inc. Route 2, Box 70 Ruskin, Florida

# 8
SAVE OUR BAYS AND CANALS ASSOCIATION vs TAMPA BAY WATER AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 00-002010 (2000)
Division of Administrative Hearings, Florida Filed:Tampa, Florida May 11, 2000 Number: 00-002010 Latest Update: Aug. 18, 2000

The Issue The issue is whether Respondent Department of Environmental Protection may issue to Respondent Tampa Bay Water a variance from the requirements, in Rules 62-555.520(4)(c) and (d), Florida Administrative Code, that an application for a permit to construct and operate a drinking water system contain drawings of the project with sufficient detail to describe clearly the work to be undertaken and complete specifications of the project to supplement the drawings.

Findings Of Fact Inception of Tampa Bay Water, Consolidated Permit, and Other Documentation for the Production of Drinking Water Respondent Tampa Bay Water (TBW) is a wholesale public water supply utility. TBW is governed by a nine-member board of directors with one member each from the municipalities of Tampa, St. Petersburg, and New Port Richey and two members each from the counties of Hillsborough, Pinellas, and Pasco. The purpose of TBW is to use group resources to find regional solutions to the problems of water supply in the region. Over two million persons in the three-county area rely on TBW for their drinking water. The predecessor of TBW was the West Coast Regional Water Supply Authority (WCRWSA), which was created in 1974. The West Coast Regional Water Supply Authority was also a wholesale public water supply authority. However, the authority operated as a cooperative entity, and TBW operates as a regulatory entity. In 1996, WCRWSA sought to renew its permit from Intervenor Southwest Florida Water Management District (SWFWMD) to allow continued withdrawals from four of its eleven major wellfields. Concerned with the environmental impacts, such as drawdowns of the water levels of wetlands, streams, and lakes, from the environmental, if not regulatory, overpumping of the wellfields, SWFWMD denied the application for the quantities requested. An Administrative Law Judge at the Division of Administrative Hearings conducted a hearing and issued a recommended order finding adverse environmental effects from overpumping, but recommending that SWFWMD issue the requested permits subject to certain conditions. Subsequent negotiations resulted in the parties' entering into a series of agreements covering withdrawals from the four wellfields that had been the subject of the administrative hearing and seven more wellfields that were approaching repermitting (11 Wellfields), as well as a series of other matters. On May 20, 1998, WCRWSA, the three member counties, the three member municipalities, and SWFWMD entered into the Northern Tampa Bay New Water Supply and Ground Water Withdrawal Reduction Agreement (Partnership Agreement). The Partnership Agreement requires WCRWSA to bring one or more projects online, by December 31, 2002, to produce at least 38 million gallons per day (MGD) and, by December 31, 2007, to produce at least 85 MGD of new water supply. The Partnership Agreement requires SWFWMD to provide WCRWSA with $183 million toward eligible water supply projects. The Partnership Agreement notes that the then-current Master Water Plan of WCRWSA recognizes that "an aggressive conservation and demand management program is an integral component of a sustainable water supply." (Joint Exhibit 3, p. 31.) The Partnership Agreement notes that the then-current Master Water Plan states that the conservation program was expected to reduce use by 10 MGD per day by 2000 and 17 MGD by 2005. From the effective date of the agreement through December 31, 2002, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 158 MGD, based on a rolling 36-month average. For the next five years, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 121 MGD, based on an annual average. After that, effective December 31, 2007, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 90 MGD, also based on an annual average. Three weeks after the execution of the Partnership Agreement, WCRWSA was reorganized into TBW in June 1998 through the execution of two documents: an Amended and Restated Interlocal Agreement dated June 10, 1998 (Interlocal Agreement), and a Master Water Supply Contract dated June 10, 1998. TBW assumed WCRWSA's rights and responsibilities under the Partnership Agreement. The Interlocal Agreement empowers TBW to produce and supply drinking water "in such manner as will give priority to reducing adverse environmental effects of excessive or improper withdrawals of Water from concentrated areas." (Joint Exhibit 1, pp. 20-21.) The Interlocal Agreement incorporates the phased-in reductions in withdrawals from the 11 Wellfields that are set forth in the Partnership Agreement. The Interlocal Agreement notes that, if the Partnership Agreement provides for extensions of the deadlines, the deadlines contained in the Interlocal Agreement shall likewise be subject to extension. Applying to the 11 Wellfields, SWFWMD issued TBW a Consolidated Permit, which was issued on December 15, 1998, and became effective on January 1, 1999. Complementing the Partnership Agreement, which reflects SWFWMD's resource- development role, is the Consolidated Permit, which reflects SWFWMD's regulatory role. The Consolidated Permit incorporates the phased-in reductions of withdrawals, as set forth above, for the 11 Wellfields. Although the deadlines for phased-in reductions are conditioned on the funding to be provided by SWFWMD, pursuant to the Partnership Agreement, these deadlines are otherwise unconditional and firm. The Consolidated Permit expressly provides for extensions of deadlines, except the deadlines set for the phased-in reductions of withdrawals from the 11 Wellfields. The Consolidated Permit imposes upon TBW extensive responsibilities regarding environmental monitoring, reporting, and mitigation. These responsibilities extend to groundwater, wetlands, and surface waters, as TBW must, among other things, monitor and report levels in the surficial and Floridan aquifers and potentiometric surfaces in the Floridan aquifer in the vicinity of the 11 Wellfields, as well as in the vicinity of selected wetlands and surface waters. The Consolidated Permit sets specific "regulatory levels" for these resources. Present and Future Tampa Bay Water Facilities, Including the Surface Water Treatment Plant A majority of TBW's production facilities consists of the 11 Wellfields. In an effort to supplement these production sources so as to comply with the phased-in reduction deadlines set forth in the Consolidated Permit and other documents, TBW annually adopts a New Water Plan, which describes capital planning for drinking water production facilities. The June 2000 New Water Plan summarizes the requirements of the Partnership Agreement. The June 2000 New Water Plan notes that TBW reaffirmed its Master Water Plan and New Water Plan projects in April 2000. These projects include the Enhanced Surface Water System, which includes the Tampa Bay Regional Surface Water Treatment Plant (SWTP), Tampa Bay Reservoir Project (Reservoir), and projects obtaining water from the Alafia River, Hillsborough River, and Tampa Bypass Canal. Other projects, besides the Enhanced Surface Water System, include Seawater Desalination (Desal Plant). The June 2000 New Water Plan states that the Enhanced Surface Water System is eligible for a maximum of $120 million from SWFWMD, pursuant to its funding obligation under the Partnership Agreement. This case involves the means by which the SWTP will be permitted, and, in consideration of the manner of permitting, this case involves the means by which the SWTP will be designed and constructed. The June 2000 New Water Plan notes that TBW and USFilter Operating Services, Inc. (USFilter) have entered into a contract for the latter to design, build, and operate (DBO) the SWTP (DBO Contract). The June 2000 New Water Plan reports that USFilter is currently constructing an access road to the site. Among current issues, the June 2000 New Water Plan describes this case, noting that TBW obtained a variance from Respondent Department of Environmental Protection (DEP) allowing a design, build (DB) approach to permitting the SWTP. The June 2000 Water Plan states that the present challenge "has the potential to delay the completion of the [SWTP] by an estimated 8 months, subsequently delaying delivery of the initial 22 mgd (dry weather conditions) of new surface water to the regional system until May 2003 and more likely final acceptance of the [SWTP] to September 2003." (Joint Exhibit 5, p. 4.) (The accuracy of this statement is open to debate because SWFWMD granted an environmental resource permit for the SWTP project only on June 27, 2000--before which no significant alteration of the land could have taken place.) In the meantime, the June 2000 New Water Plan predicts a water supply shortfall of 100,000 to 2 million gallons per day in the South-Central service area of Hillsborough County. Addressing the SWTP, the June 2000 New Water Plan states that TBW purchased the site in October 1999 and released a Request for Proposals on July 19, 1999. Four pre-qualified DBO teams responded on October 18, 1999. The June 2000 New Water Plan erroneously states that TBW applied for a public drinking water facility construction permit (Water Treatment Permit) in October 1999. Actually, in September or October, TBW prefiled with the Hillsborough County Health Department (Health Department) its application for a Water Treatment Permit and paid the $7500 filing fee. The purpose of this courtesy filing or prefiling was to allow Health Department representatives to examine the application, including drawings and specifications for the SWTP, and perhaps expedite the approval process, once TBW filed a formal application. The June 2000 New Water Plan reports that the SWTP will have a peak day, surface water treatment capacity of 60 MGD and will be located on a 433-acre site near U.S. Route 301 and Broadway Avenue in central Hillsborough County. The June 2000 New Water Plan states that the SWTP project schedule calls for completion of construction by March 2003 with plant startup and testing in May 2003 and final acceptance testing in September 2003. The June 2000 New Water Plan estimates that detailed design, site permitting, and construction of the SWTP will cost $84.3 million, and the annual operation and maintenance expenses will be $7.9 million. As for the Desal Plant, the June 2000 New Water Plan reports that TBW will pursue a design, build, own, operate, and transfer (DBOOT) approach to acquire a plant to produce, initially, 25 MGD and capable of expansion by an additional 10 MGD. The June 2000 New Water Plan states that this plant will cost a total of about $96 million in capital expenses and about $19 million annually to operate. Procurement of the Surface Water Treatment Plant Design, Build, Operate Contract and Basis of Design TBW issued a Request for Proposals (RFP) that invited base and alternative proposals for the SWTP. TBW hired Parsons Engineering Sciences to prepare a preliminary design of the SWTP, so as to assist in the preparation of the proposals; although offerors could use alternative designs to the Parsons base design, all proposals had to meet the performance standards specified in the RFP. After publishing the RFP in papers and technical journals and on the Internet, TBW was able to prequalify five teams of offerors. Four of the five prequalified offerors submitted proposals. TBW received a total of nine proposals because each offeror submitted a base proposal and one alternative proposal, and one offeror submitted a second alternative proposal. At its January board meeting, TBW selected the USFilter proposal. No party filed a bid protest to the specifications of the RFP or the selection of USFilter and its team. After the selection of USFilter, TBW entered into negotiations with USFilter. During this process, USFilter agreed, at its expense, to add sand to the granulated activated carbon filters to remove fine particles more efficiently, even though it cannot recover the resulting cost of $1.5 million before or after the commencement of operations. TBW and USFilter entered into the DBO Contract on April 10, 2000 (DBO Contract). The DBO Contract identifies "Design Requirements" that "are intended to include the basic design principles, concepts and requirements for the [c]onstruction . . but do not include the detailed design or indicate or describe each and every item required for full performance of the physical [c]onstruction . . .." (Joint Exhibit 23, Section 1.2.6.) The "Design Requirements" are Schedule 6 to the DBO Contract. Schedule 6 contains all of the individual, technical specifications for the SWTP. Schedule 6 occupies two of the four volumes of large, three-ringed binders forming the DBO Contract. The DBO Contract identifies USFilter, Clark, and Camp Dresser & McKee, Inc. (Camp Dresser) as the DBO team for the SWTP project. Camp Dresser is providing design services, Clark is performing the construction, and USFilter is providing the operation and maintenance services for at least 15 years, as well as the financial guarantee, through its corporate parent. The DBO Contract provides TBW with a fixed construction cost, fixed operating costs, and guaranteed finished water quality. Schedule 8 assures that finished water quality will meet all applicable state and federal drinking water quality standards. Two witnesses at the hearing testified that TBW exacted from USFilter assurances of water quality that, as to certain parameters, will exceed applicable state and federal drinking water quality standards. The DBO Contract provides TBW with a firm completion date, subject to design modifications requested by TBW and uncontrollable circumstances, such as acts of God, raw water whose quality exceeds the maximum limits, or the delay caused by this case. A key document in this case is the Basis of Design Report (Basis of Design), which was prepared by the DBO team in April 2000. Acknowledging the phased-in withdrawal limitations and potential for fines for not meeting the deadlines set forth in the Consolidated Permit, the Basis of Design describes the purpose of the DBO process as follows: By utilizing the [DBO] approach for the [SWTP], [TBW] expects to secure substantial benefits . . .[,] includ[ing] costs savings, innovative design, reduced risk of schedule and cost excesses, long-term contracted facility operations, and maintenance efficiencies and guaranties. (Joint Exhibit 8, pp. 1-2.) The Basis of Design reports that the SWTP will be located on a 100-acre parcel within a 435-acre tract that will also accommodate facilities for groundwater treatment and storage of the treated groundwater, treated surface water from the SWTP, and treated saline water from the Desal Plant. The Basis of Design identifies the sources of raw water for the SWTF as the Tampa Bypass Canal, Hillsborough River, and Alafia River. Once online, the reservoir will help normalize quantities of available raw water throughout the dry season. The Basis of Design describes the main treatment process as pretreatment, including pH adjustment with sulfuric acid or caustic soda, powdered activated car feed, and ferric sulfate coagulant addition; coagulation, flocculation, and sedimentation using a high-rate ballasted sedimentation process known by its tradename as ACTIFLO; ozonoation for primary disinfection, taste and odor control, and partial conversion of dissolved organic carbon to an assimilable or biodegradable form; biologically active filtration for turbidity reduction, taste and odor control; reduction of biodegradable organic carbon; and post-treatment, including secondary disinfection using chloramines. The finished water will then be pumped into tanks for storage and blending before release into the distribution facilities. Distinguishing the DB process from the typical design, bid, build (DBB) process, the Basis of Design states: a very significant amount of process studies and pre-engineering was performed by the Project Team in support of its [DBO p]roposal. This work included a set of drawings covering all disciplines and developed to the 25 to 30 percent completion stage at a minimum with some drawings developed to a greater degree. This stage of drawing development is significantly beyond the sketches and diagrams usually provided in Basis of Design or Preliminary Design Reports. For this [Basis of Design,] the referenced drawings are attached and should be examined when reviewing this [Basis of Design]. As such, a relatively small number of figures are contained within this [Basis of Design]. (Joint Exhibit 8, pp. 1-4.) The Basis of Design notes that the Project Team conducted "pilot-scale" studies of the chosen treatment processes using Lake Manatee raw water. The purpose of these studies was to validate the selected treatment processes, provide water quality data, and establish appropriate operating criteria, such as coagulant dosages. The Basis of Design addresses raw water quality issues. One table sets out values for 30 different water quality parameters for each of the three raw water sources. The Basis of Design discloses expected water quality data for 11 water quality parameters. Of particular interest are total nitrogen and total phosphorus because, as noted in the Basis of Design, the algal life-cycle increases dissolved organic carbon and nutrient concentrations in reservoir water, and the "severity of this problem is impossible to predict." (Joint Exhibit 8, pp. 2-4.) The expected water quality values for total nitrogen and total phosphorus, respectively, are, on average, 0.8 and 0.55 mg/L and, at maximum, 1.6 and 2.1 mg/L. Each of the three surface waters approaches the average values, but none approaches the maximum values, for total nitrogen. The same is true for total phosphorus for the Tampa Bypass Canal and Hillsborough River. However, for the Alafia River, total phosphorus is 2.09 mg/L, so the raw water from the Alafia River may present a substantial treatment challenge, as it exceeds even the maximum expected value for total phosphorus. An error in Table 2-4 in reporting the maximum and average values of manganese (either the maximum value should be 0.02 mg/L or the average value should be 0.001 mg/L) and the omission of a turbidity parameter expressed in NTUs precludes analysis of these water quality parameters. However, the other expected parameters appear to reflect the actual water quality of these three surface waters. Section 4 of the Basis of Design describes the facilities and design criteria for the SWTP. This section begins with site grading, roadways, yardpiping, and stormwater management and extends to detailed discussions of the pretreatment and treatment processes, including the ACTIFLO, ozone contactor, and biologically active filtration. Urgency of New Means of Producing Drinking Water The SWTP is the hub of a network of production, storage, transmission, and distribution facilities that TBW plans to bring online in order to meet the requirements and deadlines set forth in the Consolidated Permit and other documents. The urgency for bringing this component of these new facilities online as soon as possible is due to environmental reasons, as well as the financial and legal reasons set forth above. Overpumping of existing wellfields has drawn down water levels in surface waters and wetlands, to the detriment of the overall level of biodiversity supported by these natural resources. Some lakes have been down 10 years, and a few have been down 40 or 50 years. During the recent drought, the City of Tampa, which obtains water from the Hillsborough River, lacked adequate volumes of surface water from which to produce sufficient finished water to meet the demand of its customers. Not surprisingly, these supply problems are accompanied by record withdrawals from the 11 Wellfields. Withdrawals in May and June of this year were the highest monthly withdrawals on record--208 MGD and 175 MGD, respectively. If the drought continues and TBW continues to meet the demands of its customers, TBW's withdrawals from the 11 Wellfields will exceed the permitted 158 MGD, on a rolling 36-month average, by April 2001. Wellfield overpumping has stressed the groundwaters. Although surface waters respond to substantial rains in as little as a day or two, groundwater takes significantly longer to respond. The surficial water table is as much as 20 feet below ground level, and the Floridan Aquifer is even deeper. The surficial aquifer does not begin to respond to substantial rains for one week, and the Floridan Aquifer begins to respond in two to four weeks. The condition of the surficial and Floridan aquifers affects the Hillsborough River and Tampa Bypass Canal, which are significantly recharged by the surficial and, sometimes, the Floridan Aquifer. The Floridan Aquifer is especially important to the Tampa Bypass Canal, whose rock bed has been breached. During dry periods, the two aquifers are the primary sources of recharge for these two surface waters. The Alafia River is more confined, but gets water from the Floridan Aquifer through two springs at the head of the river. TBW has already made substantial gains through conservation and has met the goal of nearly 10 MGD for 2000. Over the next 20 years, maximum potential gains are expected to be no more than 74-94 MGD. Conservation will continue to play an important role in securing adequate drinking water supplies in the Tampa Bay area, but conservation, even in conjunction with reclaimed water, will not suffice, especially when future population growth in the area is considered. TBW also manages wellfield production efficiently. Under its Optimized Regulatory Operations Plan, TBW collects and analyzes wellfield data to determine which wellfield to tap, notwithstanding specific limits set by wellfield, in order to minimize environmental damage. The consumptive use permits issued to TBW for the surface waters that will provide raw water to the SWTP restrict the amounts and timing of the removals. Additionally, a hydrobiological monitoring program requires the collection and analysis of data to safeguard against adverse effects in the rivers and, downstream, in the estuary. The contractual deadline for delivery of the SWTP is September 30, 2002. The timeframe for bringing online the SWTP necessarily relies on acceptance testing in the wet season, during which 60-65 percent of the annual rain occurs. The wet season extends from mid June to the end of September. Acceptance testing of the SWTP is imperative toward the end of this period because this is when the water quality of the surface waters bears the highest levels of the contaminants. Thus, if delays postpone beyond the wet season the point at which acceptance testing can take place, the postponement will effectively be until the next wet season and, possibly, the end of the next wet season. Permitting the Design, Build Process for the Surface Water Treatment Plant General The DB process envisioned by TBW would essentially break into phases the process by which TBW would obtain the necessary Public Drinking Water Treatment Construction Permit (Permit). The Permit initially would be based on "30 percent plans," which reflect about a 30 percent level of effort toward the overall design work or 30 percent completion of all of the design work (30 Percent Plans). Generally, 30 Percent Plans mark the end of the preliminary design phase. Plans reflecting 30, 60 and 90 percent levels of effort are customary in DBB processes, as these are the stages at which owners typically review design work. In 30 Percent Plans, some items are designed to 100 percent and other items are not designed at all. However, 30 Percent Plans provide reasonable assurance that the designed system is constructable. In essence, the Permit initially would be a conceptual permit for the entire SWTP coupled with a construction permit for those components for which the design is already complete on the 30 Percent Plans. Construction of each remaining component of the SWTP would await subsequent permit modifications authorizing construction of that component. As noted above, the May 18, 2000, cover letter anticipates another interim permit, or permit modification, covering specific components, and then the final permit, or permit modification, covering the entire SWTP. The DEP district office in Orlando has substantial experience with permitting DB water treatment projects. From 1996-98, the DEP Orlando office has permitted four such projects for the Orlando Utilities Commission and one such project for the City of Kissimmee. One of the Orlando Utilities Commission projects was to construct a completely new water treatment plant. Based on the experience of the DEP Orlando office, DB permitting, when based initially on 30 Percent Plans, shortens and simplifies the permitting process. DB permitting eliminates, or at least postpones, the presentation of elements, such as electrical and HVAC, that are irrelevant to the permitting process; the elimination of elements irrelevant to permitting from the initial designs helps the regulator find the elements that are relevant to the permitting process. Also, the experience of the DEP Orlando office is that the DB process results in no more permit modifications for change orders than are typical of a conventional DBB process. The DB-approval process used by the DEP Orlando office is modeled after the DEP-permitting process for wastewater treatment plants. DEP rules allow DB permitting of these plants, which are similar in construction to water treatment plants. In fact, DEP is preparing to adopt rules to allow DB permitting of water treatment plants. Because the DEP Orlando office did not issue variances from the rules that arguably preclude DB construction of water treatment plants, there is no precedent for the issuance of the variance sought in this case. However, the experience of the DEP Orlando office is that applicants do not present basic design changes after the initial submission, and DB permitting does not mean that regulatory objectives are sacrificed to the expediency sought by the applicant. The Present Case On April 11, 2000, Camp Dresser, on behalf of TBW, filed with the Health Department an Application for a Public Drinking Water Facility Construction Permit. The April 2000 drawings that accompanied the April 11, 2000, application are described above. The cover letter to the Health Department notes that, "upon conceptual approval of the project, individual components will be permitted through permit modifications based on submittals of complete drawings and specifications for each component." In this case, the availability of the Basis of Design meant that the 30 Percent Plans reflected more than a 30 percent level of effort or completion of the five-stage process of pretreatment, pH adjustment, ozone contactors, filtration, and storage in tanks. The engineer had already sized the facilities and defined all of the processes and elements of the SWTP. The April 2000 drawings, as supplemented by the Basis of Design, therefore presented a relatively detailed description of the scope, elements, and processes of the project. On May 18, 2000, Camp Dresser submitted to the Health Department more advanced drawings, which are dated May 18, 2000. The cover letter explains that the drawings are a complete set of Phase I drawings and specifications. The letter states that Camp Dresser intends to file complete drawings and specifications in three phases. Phase I, which is completed with the May 2000 drawings, consists of sitework, high rate flocculation and sedimentation, and ozone contact tanks. Phase II consists of biologically active granulated active carbon filters, clearwell, and gravity thickeners. Phase III consists of the remainder of the project. As of July 3, 2000, prior to the final hearing, the design for the SWTP had reached the 60 percent level of effort or completion. Although the SWTP described in the DBO Contract, Basis of Design, and May drawings is a relatively large, complex facility, it does not employ unproven technology. The standardization of design and regulatory review is facilitated by the use of the so-called Ten States' Standards, which are standards commonly used by the permitting authorities of numerous states, including Florida, to determine the capabilities of specified treatment processes in achieving specific water quality levels. Although the ACTIFLO technology is relatively new, it has been in use for at least five years. A pretreatment sedimentation barrier that reduces treatment time and thus tankage volume requirements, ACTIFLO is in use in a water treatment plant with a capacity of 60 MGD in Canada, which TBW's selection team members visited. ACTIFLO presently is being incorporated into a surface water treatment plant in Melbourne, Florida, where it must treat the nutrient-rich water of Lake Washington and the St. Johns River. The City of Tampa is adding ACTIFLO basins to its facilities. Also significant is the fact that ACTIFLO easily passed the pilot test on Lake Manatee. At present, 25 facilities using ACTIFLO are under design or construction in North America. As is consistent with the theory, the DBO process for designing, building, and operating the SWTP has demanded greater cooperation among the three entities that operate relatively independently in the DBB process. Pursuant to their obligations under the DBO Contract, Camp Dresser, Clark, and USFilter have coordinated, and likely will continue to coordinate, their efforts closely from design and construction, up to operation, to save time and money from the traditional DBB process, in which the design phase, construction phase, and operation phase are relatively independent of each other. The Variance In general, DEP has the authority to issue public drinking water treatment construction permits. The successful applicant obtains one permit--for construction and operation. There are no conceptual permits or separate operating permits. In Hillsborough County, as well as 10 other counties, DEP has delegated its responsibilities for issuing public drinking water treatment construction permits. In Hillsborough County, DEP has delegated this responsibility by an interagency agreement to the Health Department. Applying DEP rules to determine whether to issue a public drinking water construction permit, the Health Department defers to DEP for the issuance of variances from DEP rules. In typical permitting cases, the Health Department uses its own staff in processing the application and reaching a permitting decision. In a large case, such as this, the Health Department's lone professional engineer, who was hired in September 1999, can obtain considerable assistance from professional engineers within the Tampa Bay area and professional engineers employed by DEP. Perceiving a possible incompatibility between the DB process and the rules from which the variance is sought in this case, TBW initially filed a request for a variance with the Health Department. However, the Health Department declined to issue a variance to DEP rules and informed TBW that it had to file its request with DEP. Thus, on January 10, 2000, TBW filed a petition for a variance with DEP. On March 28, 2000, DEP issued a final order, pursuant to Section 120.542, Florida Statutes, granting the requested variance from Rule 62-555.520(4)(c) and (d), Florida Administrative Code (Variance). The Variance finds that the purpose of the underlying statutes would be met "because no component of the project would be permitted or constructed without review by the permitting authority of the complete plans and specifications for that portion of the project." The Variance finds that the DB approach will protect the public health, safety, and welfare in providing safe drinking water without exacerbating possible negative environmental impacts from the overuse of groundwater. The Variance relieves TBW of the necessity of complying with two subsections of the rule governing the contents of applications for a public drinking water construction permit. Rule 62-555.520(4)(c) and (d), Florida Administrative Code, provides: The permit application form sets forth the minimum information which is to be supplied to the Department or the Approved County Health Department. Additional information may be required by the Department to clarify information submitted in the permit application or to demonstrate that the proposed level of treatment will effectively treat the contaminants present in the raw water. The information required by the application is as follows: * * * Prints of drawings of the work project which contain sufficient detail to clearly apprise the Department of the work to be undertaken. All prints shall be minimum of 18 x 24 inches and a maximum size of 36 x 42 inches. The scale of details contained shall be satisfactory for microfilm reproduction. (Reduced size photographic reproduction of drawings for submission may be authorized.) Complete specifications of the project necessary to supplement the prints submitted. The issuance of the Variance by DEP has met with approval, albeit cautious approval, by the Health Department. One Health Department witness was an Engineer III, who is 19-year employee of the Health Department and supervisor of four Environmental Specialists charged with reviewing construction plans for drinking water plants. He testified that he agreed with DEP's final order granting the Variance. The Engineer III and the other Health Department witness, its professional engineer, testified that the issuance of the initial permit would not influence the Health Department in deciding whether to issue permit modifications, except to ensure compatibility. Allowing TBW not to comply with Rule 62-555.520(4)(c) and (d), Florida Administrative Code, the Variance provides that the initial permit shall not authorize the construction of any component of the SWTP; each component may be constructed only after the submission of complete plans and specifications for that component and the issuance of a permit modification based on those complete plans and specifications. The Variance also provides that the permitting authority shall publish a notice of intent to issue a permit modification "if the permitting authority believes that the modifications are of a controversial nature, or that there is heightened public awareness of the project." Save Our Bays and Canals, Inc. The Verified Amended Petition On May 1, 2000, Petitioner filed a petition challenging the Variance. On June 29, 2000, Petitioner filed an amended petition challenging the Variance, and the Administrative Law Judge granted Petitioner leave to file an amended petition on July 3, 2000. At the start of the hearing, on July 7, 2000, Petitioner filed a verified amended petition, which was identical to the amended petition, except that, on July 6, 2000, Petitioner's president had verified the pleading "to the best of [his] knowledge, information and belief." The verified amended petition states that Petitioner has over 400 members. The verified amended petition alleges that a substantial number of Petitioner's members will consume the finished water produced by the SWTP and will use the surface waters supplying the SWTP for recreation. The verified amended petition states that the purpose of Petitioner is to save the bays, canals, and waterways of the Tampa Bay area and to ensure safe drinking water for its members and residents of the Tampa Bay area. The verified amended petition states that the Variance affects Petitioner because it would allow the issuance of the Permit and construction of initial phases of the SWTP prior to submittal, review, and approval of complete plans for the next and subsequent phases. The verified amended petition alleges that Petitioner incorporated to pool its resources to review applications, so as to ensure safe drinking water. The verified amended petition states that submittal and review of a complete set of drawings and specifications is necessary prior to construction of the SWTP to ensure the ability of the facility to comply with state drinking water standards. The verified amended petition states that review of all individual components of the SWTP is necessary to assure the protection of the public health, safety, and welfare and the compliance with all applicable state and federal laws. Addressing specifically the 30 Percent Plans, the verified amended petition objects to the absence of a list of items to be included in the 30 Percent Plans. The verified amended petition alleges that this piecemeal approach to permitting will require Petitioner to request administrative hearings on each phase of permitting. The verified amended petition states that the Variance may have adverse environmental and safety impacts that cannot be evaluated fully without a submittal and review of the complete drawings and specifications. The verified amended petition states that the DBO approach is "self-created." The verified amended petition objects to the failure of TBW to obtain the Variance before issuing the RFP and instead using the DBO Contract as a basis for claiming hardship so as to qualify for the Variance. The verified amended petition states that the number of variances issued for similar 30 Percent Plans threatens to create a situation in which the variance subsumes the rule requiring complete drawings and specifications. The verified amended petition objects to this form of unwritten policy that has not been published as a rule. The verified amended petition states that the phased permitting of the SWTP may create permitting momentum that discourages a rigorous application of the rules at a later stage. The verified amended petition states that the request for a variance is improper because it is for a variance from statutes, not rules. The verified amended petition states that Section 403.861(10), Florida Statutes, requires DEP or Health Department approval of "complete plans and specifications prior to the installation, operation, alteration, or extension of any public water system." The verified amended petition states that "installation" means construction. The verified amended petition states that Section 403.861(5), Florida Statutes, prohibits the issuance of a public drinking water treatment construction permit "until the water system has been determined to have the required capabilities . . .." The verified amended petition states that the assurances of USFilter are insufficient to satisfy this requirement. The verified amended petition states that Section 120.542, Florida Statutes, which authorizes the variance procedure used in this case, does not authorize variances for compliance with federal law. The verified amended petition states that TBW must obtain a federal variance in order to obtain the Variance. The verified amended petition states that the 30 Percent Plans omit information required for permitting, such as the listing of a certified operator, monitoring and recordkeeping programs, and various financial elements, such as the posting of a bond and creation of reserves to demonstrate financial soundness. The verified amended petition states that TBW's substantial hardship is based on contract deadlines that are entirely self-created and, thus, insufficient to warrant a variance. The verified amended petition notes that the environmental damage cited as a basis for granting the Variance "was caused by years of overpumping by . . . TBW . . .." Also, the verified amended petition states that member governments of TBW continue to approve new development, which increases the demand for drinking water, because TBW and its member governments have failed to exploit fully the potential for conservation and reclaimed water. Similarly, the verified amended petition states that SWFWMD helped create the hardship by renewing the permits for additional withdrawals from the 11 Wellfields. The verified amended petition states that the DBO process will not necessarily save time and money and is not a recognized exception to the general requirement that an applicant must submit complete drawings and specifications prior to permitting. The verified amended petition states that 30 Percent Plans do not provide sufficient detail to know what the contractor is promising to build, and it would be faster to correct any mistakes prior to the start of construction, rather than after the start of construction. Standing Petitioner was an unincorporated association from its formation in early October 1999 through February 3, 2000, when it was incorporated as a Florida not-for-profit corporation. Originally named Save Our Bays and Canals Association, the unincorporated association was formed by members of the Apollo Beach Civic Association who were concerned about the environmental impact upon their bays and canals of intensive utility and industrial land uses in close proximity to their homes. Apollo Beach is an unincorporated area along the southeast shore of Tampa Bay, just south of the mouth of the Alafia River. The land uses with which the unincorporated association has been concerned in its brief existence include a sulfur plant, the TECO Big Bend plant, a proposed National Gypsum plant, a proposed concrete plant, the proposed Desal Plant, and, now the proposed SWTP. The Apollo Beach area is very close to the proposed site of the Desal Plant, but is about 17 miles south southeast from the proposed site of the SWTP. Petitioner and its members are primarily concerned with the Desal Plant, not the SWTP. However, Petitioner and its members express concern with the SWTP. The concerns are that DB permitting of the SWTP will jeopardize the production of safe drinking water and will result in greater costs to TBW customers, who will eventually bear the financial burden of costly reworking of a hastily designed and constructed project. Standing analysis is simplified by the elimination of the issue of whether the verification of the amended petition confers standing. The claims of Petitioner in this case do not rise to the level of an attempt to prevent an activity, conduct, or product to be permitted from impairing, polluting, or otherwise injuring the air, water, or other natural resources of the State. First, finished drinking water is not a natural resource of the State. Although a resource, finished drinking water is not natural. Although of lower water quality, raw water is a natural resource. The potable water leaving the SWTP is a manufactured resource. Second, even if finished drinking water were a natural resource, the issuance of the Variance does not have the effect of impairing, polluting, or otherwise injuring a natural resource. The Variance excuses compliance with two rules requiring complete drawings and specifications. Even assuming that the SWTP would impair, pollute, or otherwise injure natural resources, the Variance would not have such an effect because the act of granting the Variance is distinct from the act of granting the Permit itself. Thus, facts regarding the circumstances under which Petitioner's president verified the amended petition are irrelevant for the purpose of determining standing. Petitioner's standing is a function of the characteristics of the corporation and its members. At the corporate level, the articles of incorporation state that the "specific and primary purposes for which this corporation is formed are to operate for the public education and advancement of the water quality of Tampa Bay, its tributaries, its estuaries and its canals and for other charitable purposes, by the distribution of its funds for such purposes." There is some indication in the record of an attempt, after filing the petition commencing this proceeding, to amend the articles of incorporation to state, among Petitioner's purposes, the protection of drinking water. The record does not contain the written articles of incorporation, as amended, or amended articles of incorporation after February 3, 2000. However, for the purpose of this recommended order, the Administrative Law Judge shall assume that such an amendment was made at some point after the filing of the petition and before the final hearing. At the membership level, the water to be produced by the SWTP will be distributed primarily to customers in Pasco and Pinellas counties, St. Petersburg, and the Northwest Service Area of Hillsborough County, not to Apollo Beach, which is in southern Hillsborough County. Nearly all of Petitioner's members reside in Apollo Beach or other nearby communities, which also will not be served by the SWTP. Although an insubstantial number of Petitioner's members will consume finished water from the SWTP in their homes, a substantial number will consume finished water from the SWTP at their places of work or schools and where they shop or dine out. Drinking water is ubiquitous, and the mixture of functional land uses in Apollo Beach is not, so it is highly probable that members of Petitioner will travel the three-county area in connection with their employment, education, and recreation. Close analysis of the characteristics of Petitioner and its members reveals no basis for finding standing to challenge the Variance. Nothing in the record suggests that Petitioner or any of its members have devoted themselves to the arcane task of resisting a perceived trend of state and local agencies to issue series of permits in response to DB proposals--or, more colorfully, to engage in "piecemeal permitting." About the only interest that Petitioner can legitimately claim in DB permitting is that multiple points of entry, at each permit and permit modification, will result in additional expense. If Petitioner has standing to contest even the permitting of the SWTP, Petitioner must petition each time for an administrative hearing, conduct discovery, and participate in the final hearing. However, this seems, at most, like a tenuous interest, which suffers also from the speculation that later stages of the DB permitting process will continue to present new issues not raised in the challenge of the Permit initially approved. Turning to the members themselves, their consumption of drinking water produced by the SWTP is no basis for standing either because the attenuated relationship between the Variance, which excuses compliance with two rules concerning the contents of applications, and the safety of drinking water or the additional costs that could arise from hasty designing, constructing, or permitting. Although it is conceivable that a record could have been made that the DB permitting proposed in this case would likely result in incomplete, incompetent permitting review, so as to jeopardize the public health if the permit were to issue, the record in this case does not support such a contention. To the contrary, the record establishes that the DB permitting is at least as likely as DBB permitting to provide the regulatory oversight necessary to assure the design and construction of a successful public drinking water treatment plant Lacking a substantial nexus in the record between the DB permitting authorized by the Variance and the quality of the drinking water that, if the Health Department issues the Permit, would likely be produced by the SWTP and likelihood of success of the overall construction project, the members of Petitioner likewise lack standing to challenge the Variance. Ultimate Findings of Fact Petitioner and its members lack standing to challenge the Variance. TBW faces a substantial hardship if not given the Variance. The legal and financial consequences of a failure to meet the phased-in withdrawal reductions are real and substantial. The environmental damage caused by overpumping the 11 Wellfields underscores the urgency of developing alternative sources of raw water for production into finished drinking water. The rule from which TBW seeks the Variance is derived from the statute discussed in the Conclusions of Law. The underlying purpose of this statute is the protection of the public health, safety, and welfare. The Variance serves the underlying purposes in two respects. First, the 30 Percent Plans contain sufficient detail to allow permitting to proceed without jeopardizing the objective of the rules to ensure that the USFilter team designs and constructs a water treatment plant that is in full compliance with all federal and state law. Second, the Variance provides that the USFilter team shall construct no component of the SWTP until it has been permitted, either initially or by a permit modification. Petitioner's Liability for Attorneys' Fees and Costs Petitioner has a Technical Committee on which Petitioner relies for examination of technical aspects of matters that are of general concern to Petitioner. This committee obtained a copy of the Variance and, after examination and discussion, developed a position in opposition to DEP's stated intent to grant the Variance. The Chair of Petitioner's Technical Committee, who has a bachelor of science degree in chemistry and is an industrial hygienist, drafted a letter reflecting the opinion of the committee in opposition to the Variance. Petitioner's attorney then converted this letter into the petition that commenced this proceeding. At all times, the Board of Directors of Petitioner approved the actions of the Technical Committee and Petitioner's attorney, including the filing of the petition. When Petitioner's president verified the amended petition, he reasonably relied on the advice of counsel concerning the substance of the assertions, and the advice of counsel was based on the work of the Technical Committee. Petitioner's president also reasonably relied on the work of the Technical Committee when he verified the amended petition. Although DB permitting has been available for the design and construction of wastewater treatment plants for an undetermined period of time, DB permitting for the design and construction of public drinking water plants is a new concept. The concept is so new that the DEP Orlando office mistakenly issued at least 2 DB permits for public drinking water plants without requiring the applicant to obtain a variance from the two rules that prevent DB permitting for such facilities. The concept is so new that the key Health Department employees have expressed concern over personnel demands from this new means of permitting, although they have also expressed at least lukewarm support for the Variance. The record portrays the employees of the Health Department as hard-working and competent, but over-burdened. The DB permitting obviously places significant responsibilities upon the Health Department, especially as it familiarizes itself with DP permitting. Although the availability of professional support from other sources, including DEP, ultimately resolves this issue, the situation of the Health Department also is relevant in assessing Petitioner's liability for attorneys' fees and costs. Two or three aspects of the drawings were deficient, according to Petitioner's professional engineer, whose testimony has been admitted despite the unreasonably restricted opportunity presented for cross-examination by his contractually driven refusal to identify past clients or jobs. Although none of these items seems likely to jeopardize a successful construction project, these were design points on which well-informed professionals could reasonably differ. Although the issue of "improper purpose" presents a closer question than the substantive issues discussed above, there is inadequate subjective or objective evidence in the record supporting TBW's claim for attorneys' fees and costs on this ground. Ultimately, the novelty of DB permitting of drinking water treatment plants precludes a finding of improper purpose. All available facts drive this determination, and, at this point in time, the relative uniqueness of DB permitting of drinking water treatment plants to DEP, the Health Department, and Petitioner and its members provides the necessary margin to preclude a finding of improper purpose.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order granting the Variance and denying the request of Tampa Bay Water for attorneys' fees and costs. DONE AND ENTERED this 24th day of July, 2000, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of July, 2000. COPIES FURNISHED: Kathy C. Carter, Agency Clerk Office of General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Ralf G. Brookes, Attorney 1217 East Cape Coral Parkway Suite 107 Cape Coral, Florida 33904 Donald D. Conn, General Counsel Tampa Bay Water 2535 Landmark Drive, Suite 211 Clearwater, Florida 33761 J. Frazier Carraway Thomas A. Lash Salem, Saxon & Nielson, P.A. 101 East Kennedy Boulevard Suite 3200 Tampa, Florida 33601 Cynthia K. Christen Senior Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 William S. Bilenky General Counsel Jack R. Pepper, Jr. Associate General Counsel Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (6) 120.542120.569120.57120.595403.412403.861 Florida Administrative Code (2) 62 -555.52062-555.520
# 9
ESTERO FIRE PROTECTION AND RESCUE SERVICES vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 96-002752RX (1996)
Division of Administrative Hearings, Florida Filed:Fort Myers Beach, Florida Jun. 10, 1996 Number: 96-002752RX Latest Update: Aug. 14, 1996

Findings Of Fact Petitioner is a special taxing district providing fire protection and rescue services to the residents of the Estero area of Lee County. The fire station is located at 20241 Tamiami Trail, Estero, Florida. Petitioner employs 14 employees, including administrative staff and firefighters. The firefighters work 24 hours straight and then are off-duty for 48 hours. Two to four employees work each shift. Firefighting requires a fast response. Thus, Petitioner requires that on-duty firefighters remain at the station for their entire 24-hour shift, unless they are out fighting fires or performing rescue duties. The fire station contains an 8' x 13' bedroom with six mattresses located on three bunk beds. On-duty firefighters are allowed to bring pillows and sheets so they can sleep at the station while on duty. There are no dressers in the room, which contains small lockers that the firefighters may use to store a change of clothes. Petitioner provides kitchen facilities at the fire station and well water. The well water is used for washing equipment, taking showers, and flushing the toilet. The well water is not used for any other purposes, nor is it used by any other persons. Petitioner provides bottled water for drinking and cooking. All of the firefighters have residences apart from the fire station and within a reasonable commuting distance from the fire station. No firefighter has ever lived at the station. Petitioner does not charge, or reduce the pay of, the firefighters for their use of the limited sleeping facilities. Petitioner lawfully does not treat the use of the limited sleeping facilities by firefighters as gross income for the purposes of withholding federal income tax or making social security contributions. By letter dated July 18, 1995, Respondent informed Petitioner that the fire station's water system is a limited use community water system because the sleeping facilities constituted rental residences, as defined by Rule 10D- 4.024(21), Florida Administrative Code. Respondent advised Petitioner that it was therefore required to obtain a permit. As noted in the following section, the statute authorizes Respondent to regulate as limited use community public water systems those systems serving a certain number of "rental residences." The statute does not define "rental residence." In Rule 10D-4.024(21), Respondent defines a "rental residence" as follows: a dwelling unit, a structure or part of a structure that is rented for use, or furnished with or without rent as an incident of employ- ment, for use as a home, residence, sleeping place by one or more persons, a mobile home rented by a tenant. This term does not apply to facilities offering transient residency such as public lodging establishments. This term includes other facilities where residency or detention is incidental to the provision of medical, geriatric, educational, counseling, religious, or similar services. Respondent equated a "rental residence" with a "dwelling unit" when it based its definition of "rental residence" on the statutory definition of "dwelling unit" in Chapter 83, Part II, Florida Statutes, which is the Florida Residential Landlord and Tenant Act. A "dwelling unit" is a "residence." The American Heritage dictionary defines a "dwelling" as "a place to live in; residence; abode." Similarly, the same dictionary's first definition of "residence" is "the place in which one lives; a dwelling; an abode." But the statutory definition qualifies "residential" with "rental." The word "rental" requires consideration of the nature of the relationship of the occupant to the dwelling and its owner. Obviously, the Florida Residential Landlord and Tenant Act addresses rental transactions, but it does not do so in the definition of "dwelling unit." Other provisions of the Act describe the kind of activity that must take place for a person to be considered a tenant renting a dwelling unit. Most importantly, Section 83.43(6) defines "rent" as "periodic payments due the landlord from the tenant for occupancy under a rental agreement " The facts of this case present a revealing illustration of the distinction between a "residence" or "dwelling unit," on the one hand, and a "rental residence," on the other hand. There is no rental relationship between the occupants of the sleeping quarters at the fire station and the residence or dwelling itself. The firefighters do not pay, directly or indirectly, for these beds or the rooms in which the beds are located. Their employer legitimately does not include the value of the use of these sleeping quarters in the compensation paid to the firefighters. The firefighters have residences within commuting distance of the fire station and use the meager sleeping quarters and kitchen facilities only because they are required to spend long hours continuously at the fire station.

Florida Laws (6) 120.52120.56120.57120.68381.006283.43
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer