Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CAPITAL CITY BANK vs FRANKLIN COUNTY AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 14-000517 (2014)
Division of Administrative Hearings, Florida Filed:Apalachicola, Florida Jan. 31, 2014 Number: 14-000517 Latest Update: Sep. 08, 2014

The Issue The issue is whether Franklin County (County) has given reasonable assurance that it satisfies all requirements for an after-the-fact permit authorizing the construction of a rock revetment seaward of the coastal construction control line (CCCL) on Alligator Drive, also known as County Road 370.

Findings Of Fact The Nature of the Dispute The origins of this dispute date back a number of years. In short, the County currently has two adjoining revetments seaward of the CCCL on County Road 370 (Alligator Drive) located on Alligator Point in the southeastern corner of the County.1 County Road 370, situated immediately adjacent to the Gulf of Mexico, is a vulnerable structure and eligible for armoring. See Fla. Admin. Code R. 62B-33.002(64). The old revetment is permitted; the new revetment is not. Pursuant to a Department enforcement action directed at both revetments, the County applied for an after-the-fact permit to authorize the construction of the new revetment. See Case No. 12-3276EF. The two revetments, totaling around 2,800 feet in length, abut County Road 370 and join near the intersection of Alligator Drive and Tom Roberts Road. The road itself is around 50 or 60 feet from the edge of the revetments. The old revetment extends around 2,000 feet west of the intersection while the new revetment extends 800 feet east of the intersection. There is a curve in the road at the intersection, and at that point the road elevation drops two or three feet for an undisclosed distance. The revetments, however, run in a straight line. There is no beach and dune system in front of the old revetment, while a small amount of exposed sand is located on the far eastern end of the new revetment. Due to storm events over the years, unauthorized debris has been placed on top of the old revetment by the County. Under the terms of the enforcement action, the County is required to remove the debris. This will reduce the height of the old revetment by several feet below its original height of nine feet National Geodetic Vertical Datum (NGVD).2 Where the two revetments join, however, the height differs by only around a foot. The Bank owns property across the street from the old revetment and alleges that, for several reasons, the site and design of the new revetment, coupled with the reduction in height of the old revetment, will cause erosion of the shoreline around the old revetment and expose County Road 370 and the adjacent upland Bank property to erosion. Although the current design and location of the old revetment have been finalized through prior agency action, the Bank has asked that the permit be denied unless the County relocates rock boulders from the new to the old revetment and raises its height back to nine feet NGVD. The County asserts that the Bank's real aim here is to require the County, at taxpayer expense, to reconstruct the old revetment to its original height. Otherwise, the Department will not waive the 30-year erosion control line restriction and allow the Bank to fully develop its property that is seaward of the CCCL. See § 161.053(5)(b), Fla. Stat. The Old Revetment Since the late 1970s, the County has owned and maintained that portion of County Road 370 that is the subject of this dispute. In May 1986, the Department of Natural Resources, which was later merged with the Department, issued to the County CCCL Permit No. FR-204 for the construction of the old revetment, then 1,500 feet long. The revetment was located approximately 350 feet east of Department Reference Monument R-211 to approximately 150 feet west of the Department Reference Monument R-213. In November 1994, the Department issued to the County CCCL Permit No. FR-446 for the re-construction of the old revetment, as well as a 500-foot extension of the eastern limits of the structure with granite boulders. The revetment, as extended, is located approximately 540 feet west of Department Reference Monument R-212 to approximately 140 feet east of Department Reference Monument R-213. The permit did not authorize placement of any construction debris within the revetment. With the extension, the total length of the old revetment is now approximately 2,000 feet. After an application for a joint coastal permit to conduct a beach and dune restoration project was filed by the County in September 2006, a Department site inspection revealed the presence of concrete debris and other debris material stacked on top of the old revetment. A debris removal plan was formulated by the Department, which was intended to be incorporated as a special condition in the joint coastal permit. In May 2011, the joint coastal permit was approved and included a debris removal plan. Because of financial constraints, however, the County did not undertake and complete the work relating to the beach and dune restoration plan or the debris removal plan. In January 2012, another inspection was conducted by the Department to document how much debris was in the old revetment and where it was located. The inspection revealed the presence of a significant amount of concrete debris and other debris material scattered throughout the revetment and continuing eastward. That same month, largely at the urging of the Bank, the Department issued a one-count Notice of Violation (NOV) alleging that after a storm event in July 2005, the County placed unauthorized construction debris and other debris material in the old revetment seaward of the CCCL, and that the debris still remained within the footprint of the revetment. See Case No. 12- 3276EF. (The Bank unsuccessfully attempted to intervene in the enforcement action.) As corrective action, the County was required to remove all debris, seaward of the CCCL, from and adjacent to the footprint of the old revetment no later than 60 days after the end of the hurricane season. That work has not yet been performed, probably because the work on both revetments will take place at the same time. After the debris is removed, the height of the old revetment will vary from between five and eight feet NGVD rather than the original nine-foot height. This was not the relief that the non-party Bank desired in the enforcement action. Instead, the Bank has always wanted the old revetment to be reconstructed to the nine-foot NGVD standard authorized in the original construction permit. Even so, the enforcement action is now final, as no appeal was taken by the County. Except for the unauthorized debris, the old revetment meets all Department standards. The New Revetment Under emergency circumstances, between September 2000 and July 2005 the County placed material, including granite rock boulders and debris material, in a location east of the old revetment, seaward of the CCCL. The construction activity is located approximately 140 feet east of Department Reference Monument R-213 to approximately 80 feet east of Department Reference Monument R-214 and is around 800 feet in length. However, the County did not obtain a permit for the temporary structure within 60 days after its construction, as required by section 161.085(3), Florida Statutes. In July 2005, Hurricane Dennis made landfall in the Florida Panhandle causing damage to the shoreline along Alligator Drive. As an emergency measure after the storm event, the County placed rock boulders that had been displaced back into the new revetment seaward of the CCCL. The County also placed other unauthorized concrete debris and debris material within the footprint of the rock revetment seaward of the CCCL. Again, no timely authorization for this work was obtained by the County. In August 2012, the Department issued an Amended NOV in Case No. 12-3276EF adding a second count, which alleged that the County had failed to obtain a permit for the placement of the rock boulders and unauthorized debris. On April 18, 2013, the Department issued a Final Order in Case No. 12-3276EF. As to Count II, it gave the County two options for corrective action: (a) that the County submit "a complete permit application for a rigid coastal armoring structure located between Department reference monuments R-213 and R-214 that complies with all applicable Department permitting rules and statutes"; or (b) that "the County remove all material placed seaward of the CCCL pursuant to a Department approved debris removal plan[,]" leaving that portion of County Road 370 without a revetment. 2013 Fla. ENV LEXIS 16 at *16. Desiring to protect its infrastructure, the County opted to apply for an after-the-fact permit. The Permit Application In March 2013, the County filed an application for an after-the-fact permit for the construction of the new revetment. As directed by the Department, the County proposes to construct a new revetment located between Department Reference Monuments R- 213 and R-214. The height of the new revetment will be around nine feet NGVD, while its slope will be one vertical to three horizontal. The old revetment is not quite as steep, having a slope of one vertical to two horizontal. The application includes a debris removal plan for the removal of construction debris as well as other debris scattered through the new revetment. Construction debris occupies a large portion of the new revetment and largely appears to be associated with storm damaged concrete sidewalk. All derelict concrete and asphalt material that is located water ward of Alligator Drive and landward of the mean high water line is to be removed. Both the County and its engineering consultant will monitor the work at the project. After reviewing the application, the Department proposed to issue after-the-fact CCCL Permit FR-897. The Bank then filed its Petition, as later amended. Petitioner's Objections As summarized in its PRO, the Bank alleges that the County did not give reasonable assurance that the following statutory and rule provisions have been satisfied: section 161.053(1)(a), which provides that special siting and design considerations shall be necessary seaward of the CCCL "to ensure protection of . . . adjacent properties"; rule 62B-33.005(2), which requires that the applicant provide the Department with sufficient information to show that adverse impacts associated with the construction have been minimized and that construction will not result in a significant adverse impact"; rule 62B-33.005(3)(a), which requires that the Department "[d]eny any application for an activity which either individually or cumulatively would result in a significant adverse impact including potential cumulative effects"; rule 62B-33.0051(2), which provides that armoring "shall be sited and designed to minimize adverse impacts to the beach and dune system, marine turtles, native salt-tolerant vegetation, and existing upland and adjacent structures"; and rule 62B-33.0051(2)(a), which requires armoring to "be sited as far landward as practicable to minimize adverse impacts . . . on existing upland and adjacent structures." See PRO, pp. 16-17. A common thread in these regulatory citations is that a revetment should be constructed in a manner that does not cause adverse impacts on "adjacent property." Except for the above cited provisions, no other permit requirements are contested, and the County's prima facie case satisfied those other requirements. The Bank's odd-shaped property, acquired in a foreclosure proceeding, abuts that portion of Alligator Drive immediately adjacent to the old revetment. The eastern boundary of the Bank's property is at least 300 feet west of the new revetment and extends westward along County Road 370 until it intersects with Harbor Circle. The entire tract is separated from the old revetment by County Road 370, a two-lane paved road. The property was once used as a KOA campground; however, the predecessor owner acquired development rights for a Planned Unit Development, which apparently cannot be fully developed unless the old revetment is raised back to its original height by the County or some other acceptable form of erosion protection is provided by the Bank at its own expense. The essence of the Bank's complaint is that the new revetment, as now sited and designed, will expose the old revetment to a higher rate of erosion, and ultimately accelerate the erosion of its property across the street. The Bank asserts that this will occur for three reasons. First, the removal of construction debris from the old revetment will lower its height, weaken the structure, and create a "discontinuity in height and composition between the revetments," resulting in increased exposure to erosion. Second, the toe of the new revetment (at the western end of the structure) will extend ten feet further seaward than the old revetment, creating a discontinuity and placing the old revetment at higher exposure to erosion. Finally, the Bank contends a discontinuity already exists between the two revetments due to the curved shape of the road at the intersection, causing the western end of the new revetment to extend further seaward than the old revetment. The Bank argues that the discontinuity will amplify the wave action on the shoreline during a severe storm event and eventually cause a breach of the old revetment. In sum, the Bank is essentially arguing that unless the two revetments mirror each other in height and slope, and consist of the same construction materials, the after-the-fact permit must be denied. The Bank's expert, Mr. Chou, a coastal engineer, was employed shortly before the final hearing and made one visit to the site. Regarding the removal of unauthorized construction debris from the old revetment, Mr. Chou was concerned that, while not ideal, the debris offers a degree of shoreline protection. He recommended that if removed, the debris be replaced with boulders comparable to the design standard of the new revetment. However, the record shows that when the loose and uneven debris is removed from the old revetment, the existing rocks will be moved to an interlocking or "chinking" configuration that actually enhances the stability and integrity of the structure.3 The Bank is also concerned that the height and slope of the two revetments differ. Mr. Chou testified that there exists the increased potential for erosion as a result of what he described as a discontinuity, or a difference of characteristics, between the two revetments. He opined that the protective function of the old revetment will be compromised by the removal of the granite boulders, which will lower the overall height of the revetment between two and four feet. According to Mr. Chou, if the new revetment suffers a direct hit by a major storm, i.e., one capable of dislodging the armor, he would "expect damage, significant damage, right next to it." Mr. Chou conceded, however, that if a permit is not approved, and the County elects to remove the new revetment, it could result in a significant adverse impact to property located along Alligator Drive. Mr. Chou further acknowledged that there will be no significant adverse effect on the old revetment during "everyday" winds, waves, and currents. Finally, he agreed that if the toes of the new and old revetments are essentially the same, as the certified engineering plans demonstrate they are, it will "minimize" the discontinuity that he describes. Notably, in 2005, Hurricane Dennis actually caused accretion (an increase in sand) on the Bank property, rather than erosion. While there are some differences in height and slope between the two revetments, no meaningful differences from an engineering perspective were shown. Through the County's coastal engineer, Mr. Dombrowski, who over the years has visited the site dozens of times and worked on a number of major projects in the area, it was credibly demonstrated that the old and new revetments will, in effect, form one continuous armoring structure that will provide shoreline protection along Alligator Drive. In terms of toe, slope, height, and construction material, there will be one continuous and straight revetment along the road, with a "fairly consistent elevation and slope going from one end to the other." If a major storm event occurs, the impacts to both revetments will likely be the same. In any event, there is no requirement that the County construct a revetment that is storm proof or prevents severe storm damage. The preponderance of the evidence demonstrates that the new revetment is consistent with the siting and design criteria in rule 62B-33.0051(2). The design of the new revetment is consistent with generally accepted engineering practice. The new revetment is sited and designed so that there will be no significant adverse impacts, individually or cumulatively, to the adjacent shoreline. See Fla. Admin. Code R. 62B-33.005(3). The County has provided the Department with sufficient information to show that adverse and other impacts associated with the construction are minimized, and the new revetment will not result in a significant adverse impact to the Bank's property. See Fla. Admin. Code R. 62B-33.005(2). The new revetment should toll erosion – which now occurs on Alligator Point at the rate of five feet per year -- and provide shoreline protection. Finally, the construction of the new revetment will not cause an adverse impact to the old revetment. For all practical purposes, the two revetments have existed side-by-side since 2005. The Bank failed to offer any credible evidence that the new revetment has had a significant adverse impact on the old revetment over the last nine years.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order approving the County's application for after- the-fact permit number FR-897. DONE AND ENTERED this 23rd day of July, 2014, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July, 2014.

Florida Laws (6) 120.52120.569120.57120.68161.053403.412
# 1
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ARGADYS T. IGLESIAS, 97-001370 (1997)
Division of Administrative Hearings, Florida Filed:Miami, Florida Mar. 17, 1997 Number: 97-001370 Latest Update: Jul. 15, 2004

The Issue The issue for determination is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what action should be taken.

Findings Of Fact At all times material hereto, Argadys T. Iglesias, hereinafter Respondent, was licensed as a certified general contractor by the Department of Business and Professional Regulation, Construction Industry Licensing Board, hereinafter Petitioner. In February 1991, Petitioner issued Respondent license number CG C052822 and placed the license on an inactive status. Effective February 23, 1993, Respondent's license status was changed to active; and Petitioner became the qualifying agent for Miami Construction Enterprises, Inc., hereinafter Miami Construction. Since in or around August 1994, Respondent's license has been on a delinquent status. As qualifier, Miami Construction authorized Respondent to act for it in matters concerning contracting and to supervise construction undertaken by it. At all times material hereto, Respondent was the primary qualifying agent for Miami Construction. At no time material hereto did Respondent have ownership interest in Miami Construction. Juan Carlos Rodriguez was the sole owner, having 100 per cent interest in Miami Construction, and was its president. At no time material hereto was Respondent a signatory on any bank account maintained by Miami Construction. At all times material hereto, Respondent was employed full-time with Dade County, Florida, as a housing inspector. On or about May 28, 1993, Miami Construction entered into a written contract with Juan Marulanda for repair work on a home at a cost of $14,520. The home, located at 8951 Hawthorne Avenue, Surfside, Dade County, Florida, was owned by Mr. Marulanda and his wife, Mildred Marulanda, and had been damaged by Hurricane Andrew. Juan Carlos Rodriguez entered into the contract on behalf of Miami Construction. Mr. Rodriguez represented to Mr. Marulanda that Miami Construction was licensed and insured. On or about July 20, 1993, after demolition of the existing damage to the home, building permit no. 24326 was issued by the Town of Surfside for the repair work. On or about August 20, 1993, Mr. Marulanda entered into a second written contract with Miami Construction for work on his home at a cost of $51,080. This second contract included change orders, some of which Respondent was unaware of. It is inferred and a finding is made that the contract dated August 20, 1993, hereinafter the second contract, superseded the contract dated May 28, 1993. No subsequent building permit was issued for the work under the second contract. It is inferred and a finding is made that building permit no. 24326 also covered work performed in accordance with the second contract. Miami Construction performed the work on Mr. Marulanda's home under Respondent's supervision. At three different times during the construction on his home, Mr. Marulanda observed Respondent examining the work being performed. During one of Respondent's visits, Mr. Rodriguez introduced Mr. Marulanda to Respondent, as the person who was in charge of the construction. The Marulandas paid for part of the construction being performed on their home.3 In addition to performing work on the Marulandas' home, Miami Construction performed work on Mr. Marulanda's business without the knowledge of Respondent. At some point during the construction on his home, Mr. Marulanda became dissatisfied with the work being performed. On December 2, 1993, Mr. Marulanda informed the Town of Surfside that he wanted to cancel building permit no. 24326 based upon "Irreconcilible [sic] differences" and that he wanted an owner's building permit. On December 2, 1993, the Town of Surfside issued Mr. Marulanda an owner's building permit for "nonstructural" work. Respondent did not receive notification of Mr. Marulanda's cancellation of the building permit even though Mr. Marulanda notified Miami Construction. When Respondent eventually became aware of the building permit's cancellation, he considered Mr. Marulanda's action as firing him and Miami Construction from the job. Mr. Marulanda obtained the services of an attorney and in 1994 filed a civil complaint in the Eleventh Judicial Circuit, Dade County, Florida, Case No. 94-3201-CA-01, against Miami Construction and Mr. Rodriguez for alleged violations of the second contract. Respondent was not named as a defendant. The complaint alleged, among other things, breach of agreement, unjust enrichment, fraud, and conversion. In or around February 1994, after operating for approximately one year, Miami Construction ceased doing business. On February 25, 1994, a copy of the complaint was served upon Respondent, through service of process, as a director of Miami Construction. No direct evidence was presented at hearing to show that Respondent was a director of Miami Construction.4 Respondent did not defend the lawsuit. Respondent believed that, since he was not named in the lawsuit, he could not defend it without the cooperation of Mr. Rodriguez, which he did not have. Additionally, after having communicated with the attorney representing Mr. Marulanda in the court action, Respondent believed erroneously that only Miami Construction and Mr. Rodriguez would be affected by the outcome of the court case. On October 12, 1994, Mr. Marulanda obtained a default final judgment against Mr. Rodriguez and Miami Construction from the Circuit Court.5 The default final judgment ordered the following: That a final judgment be and the same is hereby entered in favor of PLAINTIFF and against the DEFENDANTS, jointly and severally, in the amount of $43,304.06. That PLAINTIFF additionally recover from said DEFENDANT [sic] costs herein taxed in the sum of $197.00. That PLAINTIFF recover from said DEFENDANT [sic] attorney's fees herein taxed in the sum of $3,012.50. for all of which let execution issue. The default final judgment does not show that a copy of it was furnished to Respondent, but does show that a copy was furnished to the named defendants, Mr. Rodriguez and Miami Construction. The default final judgment has not been set-aside, vacated, appealed, satisfied, or discharged in bankruptcy in whole or in part. Respondent has not made a single payment toward satisfaction of the default final judgment or offered to negotiate a payment plan.6 Since in or around August 1994, Respondent's license has been on a delinquent status. Respondent is no longer a housing inspector with Dade County; however, he remains employed with Dade County. Respondent is required to have his license to continue his employment with Dade County in his present position.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order: Finding that Argadys T. Iglesias violated Subsection 489.129(1)(r), Florida Statutes.; Imposing a $1,000 administrative fine; Requiring Argadys T. Iglesias to pay restitution to Juan Marulanda for the monetary damages awarded in the default final judgment entered in the Eleventh Judicial Circuit, Dade County, Florida, Case No. 94-3201-CA-01 on October 12, 1994, or, in the alternative, to provide proof of satisfaction of the said default final judgment; and Requiring Argadys T. Iglesias to pay all reasonable costs of investigation and prosecution associated with the Department of Business and Professional Regulation's investigation and prosecution of the charges set forth in the Administrative Complaint.9 DONE AND ENTERED this 5th day of November, 1997, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 5th day of November, 1997.

Florida Laws (7) 120.569120.5717.00117.002489.105489.1195489.129 Florida Administrative Code (3) 61G4-12.01861G4-17.00161G4-17.002
# 2
DEPARTMENT OF ENVIRONMENTAL PROTECTION vs SOUTH PALAFOX PROPERTIES, LLC, 14-003674 (2014)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida Aug. 12, 2014 Number: 14-003674 Latest Update: Jan. 15, 2016

The Issue The issue is whether Respondent's Construction and Demolition Debris Disposal Facility Permit No. 003397-013-SO (the Permit) should be revoked and the facility closed for the reasons stated in the Department of Environmental Protection's (Department's) Notice of Revocation (Notice) issued on July 31, 2014.

Findings Of Fact A. The Parties, the Property, and the Dispute The Department administers and enforces the provisions of chapter 403 and the rules promulgated thereunder, including those applicable to construction and demolition debris (C & D) disposal facilities. Respondent is a Florida limited liability corporation that owns real property located at 6990 Rolling Hills Road, Pensacola, Escambia County (County), Florida. The large, odd- shaped parcel (whose exact size is unknown) is south-southwest of the intersection of Interstate 10 and Pensacola Boulevard (U.S. Highway 29) and has Class III fresh surface waters running in a northeast-southwest direction through the middle of the property. See Resp. Ex. 28. The entire site is surrounded by a six-foot tall fence or is separated from adjoining properties by natural barriers. A railroad track borders on the eastern side of the parcel; the western boundary fronts on Rolling Hills Road; and the northern boundary appears to be just south of West Pinestead Road. Id. The area immediately south of the parcel appears to be largely undeveloped. See Dept. Ex. 40. The Emerald Coast Utilities Authority (ECUA), a local government body, has an easement that runs along the eastern side of the property adjacent to the railroad track on which a 48-inch sewer pipe is located. An older residential area, known as Wedgewood, is located northeast of the facility on the north side of West Pinestead Road. Id. The closest Wedgewood homes appear to be around 400 or 500 feet from the edge of Respondent's property. A community and recreational center, the Marie K. Young Center, also known as the Wedgewood Center, serves the Wedgewood community, is northwest of the facility, and lies around 500 feet from the edge of the property. Established in 2012 where a school once stood, it has more than 200 members. Although non- parties, it is fair to say that the Wedgewood community and County strongly support the Department's efforts to revoke Respondent's permit. Respondent acquired the property in 2007. At that time, an existing C & D disposal facility (the facility) was located on the property operating under a permit issued by the Department. The Permit was renewed in February 2013 and will expire in early 2018. Besides the general and specific conditions, the renewed Permit incorporates the terms and conditions of a Consent Order executed in November 2012, as well as detailed requirements relating to the operation of the facility, water quality monitoring, an odor remediation plan, financial assurance and cost estimates, and closure of the facility. The latter requirements are found in four Appendices attached to the Permit. The facility operates under the name of Rolling Hills Construction and Demolition Recycling Center. All material received by the facility is disposed of in an active disposal pile known as cell 2, located in the middle of the northern section of the parcel. Cell 1, southwest of cell 2 and just east of Rolling Hills Road, was closed a number of years ago by the prior operator. Respondent operates the only C & D facility in the County.1/ It currently serves around 50 to 60 active customers, employs 16 persons, and operates between the hours of 7:00 a.m. and 5:00 p.m. The former manager, Charles Davidson, who had overseen operations since 2010, was replaced in June 2014, and Respondent blames him for ignoring or failing to address most of the problems encountered during the last three years. Since June, the managing partner of the LLC, Scott C. Miller, has overseen the operations. Unlike Class I or III landfills, a C & D landfill may accept only construction and demolition debris. Construction and demolition debris is defined as "discarded materials generally considered to be not water soluble and non-hazardous in nature." § 403.703(6), Fla. Stat.; Fla. Admin. Code R. 62- 701.200(24). Debris includes not only items such as steel, glass, brick, concrete, asphalt material, pipe, gypsum wallboard, and lumber that are typically associated with construction or demolition projects, but also rocks, soils, tree remains, trees, and other vegetative matter that normally result from land clearing or land development operations. Id. No solid waste other than construction and demolition debris may be disposed of at the facility. See Fla. Admin. Code R. 62- 701.730(4)(d). To address and resolve certain violations that predated the renewal of the Permit, the Department and Respondent entered into a Consent Order on November 14, 2012. See Dept. Ex. 2. These violations occurred in 2011 and included the storage and/or disposal of non-C & D debris, and a failure to timely submit an appropriate Remedial Action Plan (RAP). Id. Among other things, the Consent Order required that within a time certain Respondent submit for Department review and approval an RAP; and after its approval to "continue to follow the time frames and requirements of Chapter 62-780, F.A.C." Id. Those requirements included the initiation of an active remediation system and site rehabilitation within a time certain, and the continued monitoring and related corrective action for any water quality violations or impacts. Id. To ensure that it has the financial ability to undertake any required corrective action, the Permit requires Respondent to provide proof of financial assurance for the corrective action program cost estimates. See Fla. Admin. Code 62-701.730(11)(d); § 2, Spec. Cond. F.1. This can be done through a number of mechanisms, such as a performance bond, letter of credit, or cash escrow. The Permit also requires Respondent to provide proof of financial assurance to demonstrate that it has the financial ability to close the facility and otherwise provide for the long-term care cost estimates of the facility. See Fla. Admin. Code R. 62-701.630; § 2, Spec. Cond. F.2. Rather than using a cash escrow or letter of credit, Respondent has chosen to use a performance bond for both requirements. These bonds must be updated annually to include an inflation adjustment. Given the many requirements imposed by the Permit and Consent Order, in 2013 and 2014 several follow-up site inspections of the facility were conducted by the Department, and a review of the operations was made to determine if the various deadlines had been met. Also, in 2014, the Department received complaints from the County and neighboring property owners, almost exclusively by those residing in the Wedgewood community, regarding offensive odors emanating from the facility. Based on field observations, the review of operations, and odor complaints, on July 31, 2014, the Department issued a Notice containing eight counts of wrongdoing. The Notice was issued under section 403.087(7)(b), which authorizes the Department to revoke a permit when it finds the permit holder has "[v]iolated law, department orders, rules, or regulations, or permit conditions." To Respondent's consternation, the Department opted to use that enforcement mechanism rather than initiating an enforcement action under section 403.121 or executing another consent order, both of which would likely result in a sanction less severe than permit revocation.2/ The Notice contains the following charges: exceeding surface water quality standards in rules 62-302.500 and 62- 302.530 (Count I); failing to implement an RAP as required by the Consent Order and Permit (Count II); failing to provide adequate financial assurances for facility closure costs (Count III); failing to provide financial assurances for the corrective action required by the RAP (Count IV); failing to reduce on-site and off-site objectionable odors and to implement a routine odor monitoring program (Count V); disposing non-C & D waste on site (Count VI); failing to remove unauthorized waste (Count VII); and disposing solid waste outside of its permitted (vertical) dimension of 130 feet National Geodetic Vertical Datum (NGVD) (Count VIII). These allegations are discussed separately below. Although the Notice is based on violations that occurred on or before July 31, 2014, the undersigned denied the Department's motion in limine that would preclude Respondent from presenting mitigating evidence concerning circumstances surrounding the violations and efforts to remediate them after July 31, 2014. Given that ruling, the Department was allowed to present evidence to show that Respondent's remediation efforts have not been successful and that some violations still existed as of the date of final hearing. Respondent disputes the allegations and contends that most, if not all, are either untrue, inaccurate, have been remedied, or are in the process of being remedied. As noted above, Respondent considers the revocation of its permit too harsh a penalty in light of its continued efforts to comply with Department rules and enforcement guidelines. It contends that the Department is acting at the behest of the County, which desires to close the facility to satisfy the odor complaints of the Wedgewood residents, and to ultimately use the property for a new road that it intends to build in the future. Count I - Water Quality Violations The Notice alleges that two water quality monitoring reports filed by Respondent reflect that it exceeded surface water quality standards at two monitoring locations (MW-2 and SW-6) sampled on August 26, 2013, and at one monitoring location (MW-2) sampled on March 4, 2014. The Notice alleges that these exceedances constitute a failure to comply with Class III fresh surface water quality standards in rules 62-302.500 and 62- 302.530 and therefore violate conditions in the Permit. These standards apply in areas beyond the edge of the discharge area (or zone of discharge) established by the Permit. To ensure compliance with water quality standards, when the Permit was renewed in 2013, a Water Quality Monitoring Report (Appendix 3) was attached to the Permit. It required Respondent to monitor surface water for contamination, identify the locations at which samples must be collected, and specify the testing parameters. All of these conditions were accepted by Respondent and its consultant(s). The monitoring network, already in place when Respondent purchased the facility, consists of six ground water monitoring wells and three surface water monitoring stations. The surface water stations, which must be sampled to determine compliance with water quality criteria, are SW-5, a background location, and SW-6 and MW-2, both compliance locations located outside the zone of discharge. A background location is placed upstream of an activity in order to determine the quality of the water before any impacts by the activity. A compliance location is placed downstream of an activity to determine any impacts of the facility on surface water. The Water Quality Monitoring Plan and Permit require Respondent to submit semi-annual water quality reports. To conduct the preparation and filing of the reports, Respondent used an outside consulting firm, Enviro Pro Tech, Inc. (EPT). On November 5, 2013, EPT submitted a Second Semi-Annual 2013 report. See Dept. Ex. 5. According to Mr. Miller, who now oversees operations at the facility, EPT did not provide Respondent a copy of the report, or even discuss its findings, before filing it with the Department. A Department engineer reviewed the report and noted that surface water samples exceeded the Class III Fresh Water Quality Standards for iron, copper, lead, zinc, nickel, and mercury at SW-6 and for iron at MW-2. See Dept. Ex. 6. A copy of the Department's report was provided to Respondent and EPT. Notably, the report indicated that background levels were lower than the down-gradient results. Under Department protocol, if the samples at the compliance locations exceed both the regulatory levels and the background, there is a violation of water quality standards. This accepted protocol differs from Respondent's suggested protocol that the background level should be added to the regulatory standard before a comparison with the sample results is made. In sum, except for the reported nickel value at SW-6, a violation which the Department now says it will not pursue, all exceedances shown on Department Exhibits 5 and 6 are violations of the standards. On April 1, 2014, EPT submitted a First Semi-Annual 2014 report. See Dept. Ex. 7. A Department engineer reviewed the report and noted that the surface water samples at one monitoring location, MW-2, did not meet water quality standards for iron; however, background levels for iron were much higher than downstream. See Dept. Ex. 8. No other exceedances were shown. Although the Department engineer considered the higher background level for iron to be an "inconsistency" since it varied from the prior reports, the reported iron value was treated as a violation when the Notice was drafted. In its PRO, however, the Department concedes that it did not establish a violation of standards for iron, as alleged in paragraph 7 of the Notice. While having no concerns with sampling taken at MW-2, Respondent's expert contends that the reported values for SW-6 are unreliable because the samples taken from that location were turbid and filled with large amounts of suspended solid matter. He noted that the well is located in a wetland area that is "clogged with vegetation." The expert estimated the turbidity at the site to be in the range of 480 to 500 Nephelometric Turbidity Units (NTUs) and believes the sample was taken in a "high turbid sediment laden area," thus rendering it unreliable. However, at the time of the sample collection, turbidity was measured at 164 NTUs, or much less than the amount estimated by the expert. See Dept. Ex. 5, p. 147. There is no rule or procedure that disallows the use of turbid samples. In fact, they can be representative of actual water quality. Also, rule 62-302.500(2)(d) provides that if an applicant for a C & D permit believes that turbid samples are not representative of water quality, it may use filtered samples by establishing a "translator" during the permitting process. Respondent did not request a translator during the permitting process, nor is any such translator provision found in the Permit. The expert also criticized EPT for holding the 2013 sample for iron for 22 days after collection before reanalyzing it without providing any explanation for this delay. A reasonable inference to draw from the data, however, is that iron was present in the original sample at levels that required dilution and reanalysis. Respondent's expert testified that even though off- site stormwater is discharged onto the property, no offsite monitoring locations exist, and therefore any offsite exceedances would not be reported. He also criticized the sampling locations that were selected by EPT. In fairness to Respondent, a repositioning of the monitoring network and retesting of the samples might have produced more favorable results. But these are measures that should have been addressed long before this proceeding was initiated. Finally, Respondent's expert testified that the implementation of its RAP, now partially completed, will cure all of the reported exceedances. Assuming this unrefuted testimony is true, it should be taken into account in determining an appropriate penalty. Count II - Failure to Implement an RAP In this Count, the Department alleges that after the issuance of an RAP Approval Order on July 3, 2013, Respondent was required to implement the RAP within 120 days. The Notice alleges that as of July 31, 2014, the RAP had not been implemented. An RAP was first filed by Respondent on November 15, 2010. See Dept. Ex. 3. When the Department determined that changes to the RAP were necessary, the Consent Order imposed a requirement that an RAP addendum be filed within 150 days. The date on which the addendum was filed is not known. However, an RAP Approval Order was issued on July 3, 2013. See Dept. Ex. 4. The terms and conditions in the RAP were incorporated into the renewed Permit. The work required by the RAP consists of two phases, with all work to be completed within 365 days, or by early July 2014. Phase I related to the initiation of an active remediation system within 120 days, or by October 31, 2013. This phase requires Respondent to install a pump and treat system at the facility, which will withdraw contaminated groundwater through recovery wells, pump the water to aeration basins to treat the water, and then re-infiltrate the treated water back into the ground. As noted below, the system was not operational until the second week in December 2014. Respondent's failure to implement the approved RAP by the established deadline constitutes a violation of rules 62- 780.700(11) and 62-780.790 and Permit conditions, as charged in the Notice. While Respondent concedes that it did not comply with the deadline for implementing the RAP, it points out that work on Phase I was begun in a timely manner. However, on October 16, 2013, or just before the 120 days had run, a Notice of Violation was issued by the County. See Resp. Ex. 2. The effect of the Notice of Violation was to halt much of the work on Phase I until Respondent obtained a County stormwater permit. Respondent asserts that this was responsible for all, or most, of the delay. The record shows that the EPT consultant did not apply for the County permit until September 10, 2014, or almost one year after the Notice of Violation was issued. Additional information was required by the County, which was supplied on October 23, 2014, but final sealed documents were not filed by the consultant until around Thanksgiving. The permit was issued by the County "a week or so" before the final hearing. Respondent attributes the delay in applying for a County permit to its former manager and his failure to coordinate with the EPT engineers assigned to the project. It also claims that the County failed to process the application in an expeditious fashion. However, the facts suggest otherwise. Once the permit was issued, Phase I was completed on December 8, 2014, and it was operational at the time of the final hearing. Respondent's expert, hired in August 2014, has proposed a modification to the RAP that would avoid impacting the existing stormwater pond. However, the modification must be reviewed and approved by the Department, and as of the date of the hearing, it had not been formally submitted. The Department asserts that the only reason the modification is being sought is to reduce the cost of a performance bond. In any event, in its PRO, Respondent does not argue that the proposed modification excuses its 13-month delay in completing the requirements of Phase I, or the second phase of the project, which should have been completed by early July 2014. Count III - Failure to Provide Financial Assurance This Count alleges that Respondent failed to provide the required annual 2014 financial assurance mechanism that demonstrates proof of financial assurance for closure and long- term cost estimates of the facility. At the beginning of 2014, Respondent had an $836,000.00 financial performance bond in place for closure and long-term costs. The Permit requires that on or before March 1 of each year Respondent revise the closure cost estimates to account for inflation in accordance with rule 62-701.630(4). See § 2, Spec. Cond. F.2. Once the estimates are approved, the performance bond must be updated within 60 days. In this case, an increase of around $18,000.00 was required. The annual inflation adjustment estimate was not submitted until April 15, 2014. The Department approved the cost estimates the following day and established a due date of June 16, 2014, for submitting a revised financial assurance. Respondent did not have a revised performance bond in place until a "week or two" before the hearing. Other than Respondent's manager indicating that he had a new bonding agent, no evidence was presented to mitigate this violation. The failure to timely update its financial assurance for closure and long-term costs constitutes a violation of rule 62-701.630, as charged in the Notice. Count IV - Financial Assurances for Corrective Action In the same vein as Count III, the Notice alleges that Respondent failed to maintain a financial assurance mechanism to demonstrate proof that it can undertake the corrective action program required under the RAP. Respondent was required to submit proof of financial assurance for corrective actions within 120 days after the corrective action remedy was selected. On July 3, 2013, the RAP Approval Order selected the appropriate remedy. On August 8, 2013, the Department approved Respondent's corrective action program cost estimates of $566,325.85 and established a deadline of October 31, 2013, for Respondent to submit this proof. When the Notice was issued, a corrective action bond had not been secured, and none was in place at the time of the final hearing. This constitutes a violation of rule 62-701.730(11)(d) and applicable Permit conditions. Respondent's manager, Mr. Miller, concedes that this requirement has not been met. He testified that he was not aware a new bond was required until he took over management of the facility and met with Department staff on June 17, 2014. Due to the Notice, Mr. Miller says he has had significant difficulty in securing a bond. He explained that the bonding company is extremely reluctant to issue a bond to an entity faced with possible revocation of its permit, especially if such revocation might occur within a matter of months. Mr. Miller says the bonding company wants 100 percent collateralization to put a bond in place. Nonetheless, he is confident that a bond can be secured if only because its cost will dramatically drop when the RAP project is completed. However, even at hearing, he gave no timeline on when this requirement will be fulfilled. Count V - Objectionable Odors One of the driving forces behind the issuance of the Notice is the complaint about off-site objectionable odors. A considerable amount of testimony was devoted to this issue by witnesses representing the Department, County, Wedgewood community, and Respondent. The Notice alleges that during routine inspections in April, May, and July 2014, mainly in response to citizen complaints, Department inspectors detected objectionable odors both at the facility and off-site. The Notice further alleges that Respondent failed to immediately take steps to reduce the odors, submit an odor remediation plan, and implement that plan in violation of rules 62-296.320(2) and 62-701.730(7)(e) and section 2, Specific Condition E of the Permit. Notably, the Department has never revoked a landfill permit due solely to objectionable odors. Several Department rules apply to this Count. First, objectionable odors are defined in rule 62-210.200(200). Second, a C & D facility must control objectionable odors in accordance with rule 62-296.320(2). Finally, if odors are detected off-site, the facility must comply with the requirements of rule 62-701.530(3)(b). That rule provides that once off-site odors have been confirmed, as they were here, the facility must "immediately take steps to reduce the objectionable odors," "submit to the Department for approval an odor remediation plan," and "implement a routine odor monitoring program to determine the timing and extent of any off-site odors, and to evaluate the effectiveness of the odor remediation plan." These same regulatory requirements are embodied in the Permit conditions. See § 2, Spec. Cond. E. At least occasionally, every landfill has objectionable odors emanating from the facility. As one expert noted, "The trick is, how can you treat it." The technical witnesses who addressed this issue agree that the breakdown of drywall, wall board, and gypsum board, all commonly recycled at C & D facilities, will produce hydrogen sulfide, which has a very strong "rotten egg" type smell. The most effective techniques for reducing or eliminating these odors are to spray reactant on the affected areas, place more cover, such as dirt or hydrated lime, on the pile, and have employees routinely patrol the perimeters of the property and the active cell to report any odors that they smell. Although the facility has been accepting waste products for a number of years, the last seven by Respondent, there is no evidence that the Department was aware of any odor complaints before April 2014. While not an active participant in the operations until recently, Mr. Miller also testified that he was unaware of any citizen complaints being reported to the facility prior to that date. However, in response to citizen complaints that more than likely were directed initially to the County, on April 14, 21, and 24, 2014, the Department conducted routine inspections of the facility. During at least one of the visits, objectionable odors were detected both on-site, emanating from cell 2, and off-site on West Pinestead Road, just north of the facility. See Dept. Ex. 14. Because the inspector created a single report for all three visits, he was unsure whether odors were detected on more than one visit. After the inspection report was generated, Department practice was to send a copy by email to the facility's former manager, Mr. Davidson. A Department engineer who accompanied the inspector on at least one visit in April 2014 testified that she has visited the site on several occasions, and on two of those visits, the odor was strong enough to make her physically ill. On a follow-up inspection by the Department on May 22, 2014, the inspector did not detect any objectionable odors. See Dept. Ex. 17. In June 2014, however, a County inspector visited the Wedgewood Center area in response to a complaint that dust was coming from the facility. He testified that he detected a rotten egg type smell on the Wedgewood Center property. At a meeting attended by Mr. Miller and County and Department representatives on June 17, 2014, the Department advised Respondent of its findings and provided Mr. Miller with copies of the inspection reports. On July 1, 2014, the Department conducted a follow-up inspection of the facility. The inspector noted a hydrogen sulfide odor on the north, south, and west sides of the disposal area of the facility, and on the top of the disposal pile at the facility. See Dept. Ex. 18. Another inspection conducted on July 9, 2014, did not find any objectionable odors. See Dept. Ex. 19. On July 18, 2014, the Department conducted a follow-up inspection of the facility. The inspector again noted objectionable odors at the facility but none off-site. Id. On July 24, 2014, Department inspectors noted objectionable odors on top of the pile, the toe of the north slopes, and off-site on West Pinestead Road. See Dept. Ex. 20. An inspection performed the following day noted objectionable odors on top of the pile and the toe of the north slopes, but none off-site. Id. The Notice, which was already being drafted in mid-July, was issued a week later. In response to the meeting on June 17, 2014, Respondent prepared a draft odor remediation plan, made certain changes suggested by the Department, and then submitted a revised odor remediation plan prior to July 31, 2014. A Department engineer agrees that "in the strict sense it meets the requirements of the rule" and "could work," but there are "two or three things that still needed . . . to be submitted in order for it to be completely approvable." For example, she was uncertain as to how and when dirt cover would be applied, and how erosion would be controlled. Although the plan was filed, it was never formally approved or rejected, and the "two or three things" that the witness says still needed to be done were never disclosed to Respondent. Under these circumstances, it is reasonable to accept Respondent's assertion that it assumed the plan was satisfactory and complied with the rule. After the Notice was issued, Respondent set up a hotline for community members to call and report odors. A sign on the property gives a telephone number to call in the event of odors. At an undisclosed point in time, Respondent began requiring employees to walk the perimeter of the facility each day to monitor for odors; spreading and mixing hydrated lime to reduce the odors around the facility; and increasing the amount of cover applied to the working face of the facility. The parties agree that these measures are the best available practices to monitor and eliminate objectionable odors at a C & D facility. Despite these good faith measures, Mr. Miller acknowledged that he visited the facility during the evening a few days before the final hearing in December 2014 and smelled hydrogen sulfide around the ECUA sewer pipe and "a very mild level" by the debris pile. Respondent does not deny that odors were emanating from the facility during the months leading up to the issuance of the Notice. But in April 2014, the County experienced a 500- year storm event which caused significant flooding and damaged a number of homes. Because Respondent operates the only C & D facility in the County and charges less than the County landfill, it received an abnormal amount of soaked and damaged C & D debris, which it contends could have generated some, if not all, of the odors that month. Given the magnitude of the storm, this is a reasonable explanation for the source of the odors at that time. Respondent also presented evidence that an underground ECUA sewer pipe that runs on the eastern side of the property was damaged during the storm, causing it to rupture and be exposed. Although ECUA eventually repaired the damaged pipe at a later date, the pipe is still exposed above ground. Until the pipe was repaired, Respondent's assumption that it likely contributed to some of the odors detected by the Department appears to be valid. Finally, Respondent's expert attributes some of the odors to biological degradation from other sources both on-site and off-site, including a large wetland area running through the middle of the property. To a small degree, County testing later that fall confirms this assertion. The County has also been an active participant in the odor complaint issue. In response to complaints received from residents of Wedgewood, in July 2014 it began collecting hydrogen sulfide data using a device known as the Jerome 631X Hydrogen Sulfur Detector. This equipment is used to monitor for the presence of hydrogen sulfur. On July 21 and 22, 2014, samples were taken documenting that hydrogen sulfide was coming from the facility. In early September the County set up a fixed station at the Wedgewood Center, around 500 feet from the edge of Respondent's property, to continuously and automatically collect the data. During September and October 2014 the detector reported the presence of hydrogen sulfide at that location 64 percent of the days in those months, and this continued into the month of November. Seventy-five percent of the exceedances occurred when wind was blowing from the south, or when winds were calm. The data also reflected that when the wind was blowing from the meter to the facility, or to the south, hydrogen sulfide was still detected on some occasions. A resident of the Wedgewood community testified that on multiple occasions she has smelled objectionable odors in her home and yard and at the Wedgewood Center, and that these odors have been emanating from the facility for a number of years. Because of the odors, she says fewer citizens are participating in programs hosted by the Wedgewood Center.3/ The evidence establishes that before the Notice was issued, Respondent filed an odor remediation plan that was never rejected; therefore, the allegation that a plan was not submitted has not been proven. However, objectionable odors were detected off-site in June and July 2014, or after the April inspection reports were provided to the facility, and they continued throughout much of the fall. Therefore, the Department has established that the plan was not properly implemented. These same findings sustain the allegation that steps were not immediately taken to reduce the objectionable odors. Counts VI and VII - Disposal and Failure to Remove Unauthorized Waste Counts VI and VII allege that on April 14, 2014, the Department documented the disposal of prohibited or unauthorized waste, including waste tires; and that on July 18, 2014, the Department conducted a follow-up inspection that documented the disposal of unauthorized waste, including waste tires, clothing, shoes, and Class I waste, including one electronic item and a grill, in violation of rule 62-701.730(4)(d). The Permit specifies that the facility can only accept for disposal C & D debris. See § 2, Spec. Cond. C.2. Another condition provides that if unauthorized debris is spotted after a load is received, the unpermitted waste should be removed and placed in temporary storage in a bin at the sorting area. See § 2, Spec. Cond. C.3. The Operations Plan spells out these procedures in great detail. Photographs received in evidence show that during the inspection on April 14, 2014, the following unauthorized items were observed at the facility: tires, a basketball goal, Quiklube material, chromated copper arsenate treated wood, a toy, and a crushed electronic item. See Dept. Ex. 22. Photographs received in evidence show that during an inspection on July 18, 2014, the following unauthorized items were observed at the facility: blanket or clothing, a shoe, a bag of Class I garbage, several bags of household garbage, furniture, an electronic item and garbage, drilling mud, a suitcase, and tires. See Dept. Ex. 23. Respondent's expert, who has trained numerous spotters, including a current Department inspector, established that a de minimis amount of unpermitted waste, which is easily hidden in the debris, is not unusual and would not constitute a violation of the rule. For example, when a building is torn down, numerous thermostats containing mercury vile will be in a C & D container but very difficult to see. Also, workers at construction sites may throw small amounts of leftover food in the pile of debris that goes to the facility. However, he agrees that most, if not all, of the items observed during the two inspections would not be considered de minimis. Respondent does not deny that the unauthorized waste was present on two occasions. However, it contends that one would expect to find some of the items in a C & D dumpster. It also argues that the amount of unauthorized waste was minimal and not so serious as to warrant revocation of its Permit. The evidence supports a finding that on two occasions Respondent violated two conditions in its Permit by accepting non-C & D waste and failing to remove it. Therefore, the charges in Counts VI and VII have been proven. Count VIII - Facility Outside of Permitted Dimensions This Count alleges that on May 22, 2014, the Department conducted an inspection of the facility in response to a complaint that Respondent had disposed of solid waste outside its permitted (vertical) limit of 130 NGVD; that on July 25, 2014, the Department had a survey performed at the facility that confirmed this violation; and that this activity violated section 2.3 of the facility's Operation Plan and Specific Condition C.10 in the Permit. Section 2.3 provides that "the proposed upper elevation of waste at the [facility] will range up to 130-feet, NGVD, which is slightly above original grade[,]" while Specific Condition C.10 provides that "[t]he final (maximum) elevation of the disposal facility shall not exceed 130 feet NGVD as shown on Attachment 3 - Cell 2 Closure Grading Plan." Respondent admits that on July 25, 2014, the maximum height of the disposal pile exceeded 130 feet NGVD. However, it argues that, pursuant to Specific Condition C.10, which in turn refers to the Permit's Cell 2 Closure Grading Plan, the 130-foot height limitation comes into play only when cell 2 is being closed and is no longer active. This interpretation of the conditions is rejected for at least two reasons. First, a disposal pile in excess of the established height would trigger concerns about the integrity of the foundation of the facility. When the 130-foot ceiling was established by the Department at the permitting stage, it was based on calculations that the ground could support the weight of the waste. Second, the facility's financial assurance calculations are based on a set dimension of the site; these calculations would likely be impacted if there were no height restrictions. The Department's interpretation is more reasonable and limits the height of the pile to no more than 130 feet NVGD at any time when the cell is active. The Department has established that Respondent violated Permit conditions by disposing of waste outside its maximum permitted height of 130 feet NVGD. To Respondent's credit, its new consultant, Charles Miller, completed preparation of a height reduction plan on September 3, 2014. See Resp. Ex. 4. Although Mr. Miller says the plan was being implemented at the time of final hearing, it has never been formally submitted to the Department for approval. Under the plan, Respondent proposes to extract all of the existing waste from the pile in the next two years. To reduce the volume of new waste being accepted, Respondent recently purchased a Caterpillar bulldozer, low-speed grinder, and Trommel screener. New waste will be shredded, screened to separate sand and dirt from the material, and then ground and compacted. Mr. Miller anticipates that the facility can achieve up to an eight to one (or at a minimum a five to one) reduction in the size of the waste. This will dramatically reduce the height of the pile and bring it well below 130 feet at closure. But whether cell 2 is now below 130 feet NGVD is unknown. In any event, these proposed remediation steps should be taken into account in assessing an appropriate penalty.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order revoking Respondent's C & D Permit. DONE AND ENTERED this 2nd day of March, 2015, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 2015.

CFR (1) 40 CFR 264 Florida Laws (10) 120.52120.57161.054403.021403.061403.087403.121403.703403.704403.865 Florida Administrative Code (1) 62-602.870
# 3
NORMAN ALEXANDER vs. CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 82-003347RX (1982)
Division of Administrative Hearings, Florida Number: 82-003347RX Latest Update: Feb. 25, 1983

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: By Warranty Deed dated July 2, 1982, petitioner was conveyed "Lot 151, Less the South 1/2 thereof" in Glenwood Subdivision. Lot 151 is presently zoned RS-50. The minimum lot area per dwelling unit in an RS-50 district is 5,000 square feet. Section 131.044, Code of Ordinances of the City of Clearwater. According to the subdivision plat, Glenwood Subdivision contains 154 platted lots, with an average lot size of 8,844 square feet. The smallest platted lot in the subdivision is 6,000 square feet. Lot 151 contains approximately 12,000 square feet. There is an existing single-family dwelling on the southern portion of Lot 151 which portion contains 7,700 square feet. Computations performed from a metes and bounds description of the northern part of Lot 151 which was conveyed to petitioner illustrates that petitioner's portion of Lot 151 contains 4,320 square feet. Section 20-2 of Ordinance No. 1449 provides, in part, that: ". . .Building permits shall not be issued for structures located on subdivided property created subsequent to the adoption of this Ordinance unless such plat of record is recorded in the Public Records of Pinellas County. The City Commission may permit lots of record to be cut in size to not less than the zone permits, without requiring a replat." No request was made to and no approval was given by the Clearwater City Commission to divide Lot 151, a platted lot. The restrictions for Glenwood Subdivision require that only one single- family dwelling house be erected on any single lot or plot. In August of 1982, petitioner applied to the Building Inspection Department of the City of Clearwater for a building permit to erect a single- family residence on his property. Apparently, a survey of the property did accompany the application, but no one in the Building Inspection Department verified the lot size. Petitioner was issued a building permit. Prior to October 27, 1982, petitioner had the land cleared, made soil boring tests, paid water meter fees, laid pilings and had the foundation and walls in place for the lower level of his new residence. The costs of this work, and other expenses related thereto, amounted to some $18,350.00. On or about October 27, 1982, the City issued a "red tag" on the project because it was discovered that petitioner's lot size was substandard. This was the first notification petitioner had of any problem with his lot size. He had never made inquiry concerning the zoning requirements for his lot. Petitioner continued construction on his residence. Two more "red tags" were issued on or about November 2 and November 25, 1982. On the latter date, petitioner was ordered to stop work on the project. Petitioner estimates that between August, 1982, and the date of his hearing (January 26, 1983), he expended approximately $40,710.00 on the purchase of his land and the partial construction of his residence. As noted in the Introduction, petitioner's application for a variance from the lot size requirements was denied by the City's Zoning Enforcement Officer, his appeal to the Board of Adjustment and Appeal on Zoning was denied and the instant proceeding resulted.

Florida Laws (1) 120.65
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HENRY BOTWINICK, 76-000006 (1976)
Division of Administrative Hearings, Florida Number: 76-000006 Latest Update: Jun. 03, 1977

Findings Of Fact On December 17, 1973, Henry Botwinick acknowledged having received from Mrs. Kane $4,000 on account for addition on the house at Northeast 11th Place, North Miami, Florida (Exhibit 8). Exhibit 3 is an application for building permit and building permit issued by the City of North Miami for the construction at the Kane residence. Attached thereto are the plans for the construction. Exhibits 4, 5, and 6 show pollution control authority for the construction, the plumbing permit, and electrical inspection permit. Subsequent thereto construction was commenced on this project. Mrs. Kane was advised that the project would be completed in 4 to 6 weeks, however, the contract was never completed. In April Mr. Botwinick came to Mrs. Kane and asked for an additional $500 to get the electrical work started and the cement foundation poured. Approximately two weeks later he again obtained from Mrs. Kane $1500 with which to pay the roofer. He advised Mrs. Kane that he had used the money, previously advanced by her for materials, on another job. Exhibit 8 indicates that payments of $500 were made on April 1, another $500 was made on April 12, and $1,500 was made on April 25, 1974. Subsequent inaction by the contractor on this project resulted in a letter (Exhibit 7) dated May 6, 1975 from Bertil Lindblad, a building official for the City of North Miami, in which he advised Mr. Botwinick that the building permit issued to him had expired for lack of progress or abandonment of the work for a period exceeding ninety days. Mrs. Kane last saw work performed by Botwinick on February 25, 1975. She made numerous telephone calls, but was unable to contact him. Subsequent to the payments made to Botwinick, Mrs. Kane has had to pay nearly $3,000 to another contractor to perform work and the project is still not completed. As of the date of hearing she requires approximately $3,000 additional work to complete this project.

Recommendation RECOMMENDED that Building Contractor's License #CBC001839 issued to Henry Botwinick, 11321 Rexmere Boulevard, Ft. Lauderdale, Florida, be revoked. DONE AND ENTERED this 18th day of March 1976 in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida

# 5
BARBARA ANN BUTLER vs. HARRY B. WILLIAMS AND DEPARTMENT OF NATURAL RESOURCES, 88-005439 (1988)
Division of Administrative Hearings, Florida Number: 88-005439 Latest Update: Apr. 27, 1989

Findings Of Fact On February 10, 1988 Harry B. Williams made application to the Department of Natural Resources for permission to construct a single-family dwelling with appurtenant structures at 2831 Ponte Verda Boulevard South, South Ponte Verda Beach, Florida. The permit sought was a coastal construction control line permit which would allow construction seaward of that line in the direction of the Atlantic Ocean. A copy of that permit application may be found as Department's Exhibit Number 2. Associated with the permit application was a description of the plans related to the dwelling and other structures. This application was received by the Department February 11, 1988. Following a review of the permit application the Department deemed it complete as of February 22, 1988. A site inspection was made of the property and a report was prepared by an employee with the Department, a Mr. Partel. The report may be found as Department's Exhibit Number 4, which includes photographs of the prospective building site, together with the surrounding property to include dwellings to the north and south of the lot where the Williams home would be built. As commented on by Mr. Partel the applicant had intended at that time to construct a single-family dwelling a maximum of 75 feet seaward of the coastal construction control line. Although this evaluator, Mr. Partel, felt that the applicant had requested the right to construct a dwelling which was in line with existing construction, he felt that it could be moved further landward and that it could be limited in deck size and that a cantilevened form of construction was preferable to the concrete called for in the plans set out in the application information. It was also suggested that the sea oats that were in the way of the construction should be relocated seaward on a dune face slope where a denuded area is found. In this connection, the Department is empowered to make suggestions to the applicant concerning the minimization of the adverse impacts on the beach-dune system. Following the site visit of February 26, 1988 the Department wrote the applicant on March 11, 1988 and indicated concerns about the proximity of the dwelling to the crest of the dune. A copy of this correspondence may be found as Department's Exhibit Number 5. In the correspondence the Department asked the applicant to move the proposed dwelling 10 feet landward and that the 10 foot wide concrete patio, on the seaward side, be modified to a 10 foot wide wooden deck. The letter told the applicant that the approval would be conditioned on the sea oats and other dune grasses that would be disturbed by the proposed structures being replanted seaward of the project in the denuded areas of the dune. The applicant agreed to these changes. The relocation of the structure 10 feet landward took it away from the beach- dune system. The modified site plan that was brought about by the suggested changes is found Department's Exhibit Number 6, a copy of that amended site plan. With the relocation the construction would be 66 feet seaward of the coastal construction control line. An aerial photograph of the site location reference the basic design of the dwelling and the proximity to the relevant or existing coastal construction control line is found as Department's Exhibit Number 3. In responding to the suggestions to the change in location the modified site plan which moved the dwelling 10 feet landward was received by the Department on August 1, 1988. Under this arrangement the applicant had agreed to waive the requirements of Section 120.60, Florida Statutes pertaining to the obligation by the Department to review and decide its action of grant or denial within 90 days of date of receipt of the application. With the changes being made to the location of the proposed dwelling and associated structures and the type of construction materials used in the patio on the seaward side, together with the relocation of the plant life, the impact on the beach-dune system and adjacent property is acceptable. There is no adverse impact on the beach-dune system or on the adjacent properties. The location of the proposed dwelling and its associated structures as it relates to the 30-year erosion projection under the terms of Section 161.053, Florida Statutes, in this instance, shows that the dwelling would be approximately 55 feet landward of the 30-year erosion projection and not at risk. Calculations related to this finding may be found within Department's Exhibit Number 7. The existing coastal construction control line dates from January 28, 1988. Although the original application referred to the previous line of 1978 in describing the site plan and survey, the reason for this was that the site plan and survey were prepared prior to the establishment of the January 28, 1988 line, as allowed. In the course of the hearing appropriate reference was made to the January 28, 1988 line as it relates to the anticipated location of the dwelling and other structures as modified at the instigation of the Department. As contemplated by Section 161.053(5)(f), the Department required the applicant to provide mitigation of the- effects of the construction as a condition to a grant of the permit. Those permit conditions may be found in the Department's Exhibit Number 8, a copy of a proposed final order. Included within those would be the requirements for erection of a temporary construction fence on the site to protect existing native dune vegetation from the impacts of that construction, in addition to the requirement of the dune vegetation relocation. This would involve the irrigation and application of fertilizer to those plants with the expectation that a certain percentage would survive over time as described in this special condition. This project will not pose a hazard to the sea turtle and its hatchlings and habitat for the sea turtles and hatchlings. Ms. Butler, Petitioner in this cause, has a beach home which is north of the Williams property separated by a 10 foot easement between those properties. In mid July, 1988 Ms. Butler offered a written statement in opposition to the placement and size of the proposed dwelling together with other remarks and asked that the Department provide her information and documents pertaining to the application under the authority of Chapter 119, Florida Statutes. On August 10, 1988 the Department dispatched a letter of inquiry to surrounding property owners to include Ms. Butler and solicited remarks concerning the Williams application to be provided on or about August 20, 1988. Ms. Butler had received certain documents from the Department concerning the application sometime in the middle of August 1988. On August 18, 1988 Butler made known her objection to the project on the grounds that the concerns about the 30-year erosion line and the size and placement of the dwelling. On September 2, 1988 the Department informed Ms. Butler of the intent to grant the permit to Mr. Williams. A copy of that correspondence may be found as Petitioner's Exhibit Number 5. This led to a timely request for hearing by Ms. Butler stating her opposition to this project. The request was received in accordance with the Department's advice that the request must be filed by September 26, 1988. Based upon the prehearing conference and the discussion of those issues which would be allowed for consideration as stated in the request for hearing and the statement of particulars that attend the request for hearing, commented on by the hearing officer at the commencement of the final hearing, and found within the transcript and further stated in the issues portion to this Recommended Order, this case has been carried forward. The presentation made by the Petitioner, after the Department and applicant had offered their cases, was through her testimony and that of employees of the Department together with exhibits she offered. The testimony of the Department employees concerned the procedural techniques that the agency pursued in reviewing the application at issue. Ms. Butler described her concern for her property, and the area between her property and the Williams property. This is the 10 foot easement area which is sparsely vegetated and low. As a consequence she was concerned that her property might be destroyed with the advent of the Williams construction. She has no expertise in her own right nor did she present expert opinion from other witnesses which would tend to bear out her concern. She also expressed the concern that the Williams home, in its dimensions, was too large and that it should be relocated an additional 10 feet back from the adjusted placement following the Department's criticism of the original application. In effect, she would have the house placed 20 feet away from the sea as compared to the original site plan submitted with the application on February 10, 1988. Again, there is no competent evidence presented which would support her theory that this further relocation was needed. Her expression of concern for the sea turtles and their hatchlings and habitat was not well founded. Turtles are known to nest on the sandy flat beach area and the construction of the Williams property will not interfere with that area adjacent to the ocean.

Recommendation Based upon a consideration of the facts and the conclusions of law reached, it is RECOMMENDED: That the Department enter a Final Order which grants a coastal construction control line permit to Harry B. Williams, Jr., based upon his modified plan required by the Department and upon the special permit conditions announced in the proposed final order, a copy of which is found as Department's Exhibit Number 8. DONE and ENTERED this 27th day of April, 1989, in Tallahassee, Leon County, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1989.

Florida Laws (3) 120.57120.60161.053
# 8
FRANK STROUT vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 95-003760 (1995)
Division of Administrative Hearings, Florida Filed:Arcadia, Florida Jul. 28, 1995 Number: 95-003760 Latest Update: Feb. 22, 1996

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: l. At all times pertinent to this proceeding, the Department was the state agency responsible for receiving applications for, and the issuance of, general permits for the construction and operation of a construction and demolition debris disposal facility in the State of Florida. Petitioner Frank Strout, submitted an application for a General Permit for the construction and operation of a Construction and Demolition Debris Disposal Facility with the Department dated April 26, 1995, which was received by the Department on May 2, 1995. On May 16, 1995, the Department issued a Notice of Denial to Use a General Permit advising the Petitioner that his request for operation of a construction and demolition debris disposal facility did not qualify for a general permit based on the information submitted by Petitioner in his application dated April 26, 1995, and received by the Department on May 2, 1995. The property upon which the proposed construction and debris disposal facility was to be placed is located at 11163 Agnes Avenue, Southwest, Arcadia, DeSoto County, Florida, and is owned by Petitioner Frank Strout. This location is the same as the location of the construction and demolition debris facility owned by Petitioner that previously operated under a permit issued to Petitioner in April, 1990, which expired due to Petitioner's failure to timely file for an extension of that permit with the Department. However, the disposal area will not cover the entire area of the disposal area of the previous permitted facility. The Notice advised Petitioner that he had not provided the Department with supporting information demonstrating compliance with the construction demolition debris disposal requirements of Chapter 62-701, Florida Administrative Code, as follows: The prohibitions of Rule 62-701.300(2), Florida Administrative Code, have not been addressed. Documentation indicating that the site does not violate these prohibitions was not provided. The airport requirement of Rule 62- 701(12), Florida Administrative Code, was not addressed. Information indicating the location of airports within a 5 mile radius of the site was not provided. A site plan which meets the requirements of Rule 62-701.803(1)(a), Florida Administrative Code, was not submitted. A geotechnical investigation which meets the requirements of Rule 62-701.420, Florida Administrative Code, was not submitted as required by Rule 62-701.803(1)(b), Florida Administrative Code. A description of facility operations (operations plan) was not submitted as required by Rule 62-701.803(1)(c), Florida Administrative Code. A boundary survey was not submitted as required by Rule 62-701.803(1)(d), Florida Administrative Code. Closure plans and cross section details of the final cover which meets the requirements of Rule 62-701.320(7)(f), Florida Administrative Code, were not submitted as required by Rule 62- 701.803(1)(f), Florida Administrative Code. The Department has received a copy of a letter from Southwest Florida Water Management District (District) to the applicant, dated May 23, 1995, which indicates that the District is concerned about the proximity of the C&D debris to on- site wetlands. The letter from District, dated March 13, 1990, provided an exemption from surface water permitting requirements based on the District's understanding that the proposed operation would not change surface water drainage patterns, stormwater runoff quantities or quality. However, site inspections by the Department and District staff have indicated that surface water drainage patterns have been changed by the operation at the site. Therefore, a copy of a permit for stormwater control issued by the Department or the District shall be required pursuant to Rule 62-701.803(4), Florida Administrative Code. Information indicating the availability of equipment for the temporary storage of unacceptable wastes at the site, and segregation methods were not submitted as required by Rule 62-701.803(5), Florida Administrative Code. Compaction procedures and equipment were not described as required by Rule 62- 701.803(6), Florida Administrative Code. A description of access control methods and devices was not submitted as required by Rule 62-701,803(7), Florida Administrative Code. A description of waste inspection procedures was not submitted as required by Rule 62-701.803(8), Florida Administrative Code. The facility's operating hours were not provided to ensure compliance with Rule 62- 701.803(9), Florida Administrative Code. The closure plan submitted as required by Rule 62-701.803(10), Florida Administrative Code, is insufficient. Pursuant to Rule 62-4.070(5), Florida Administrative Code, the Department shall take into consideration a permit applicant's violation of any Department rules at any installation when determining whether the applicant has provided reasonable assurances that Department standards will be met. Reasonable assurance that Department standards will be met has not been provided. Pursuant to Rule 62-701.803(10), Florida Administrative Code, final cover and vegetation shall be established on each disposal unit within 180 days of final receipt of wastes for that unit. Since waste has not been disposed at the site since approximately March, 1993, and the area has not been closed, the requirements of Rule 62- 701.803(10), Florida Administrative Code, has not been met. There is pond on the Petitioner's property which is located to the north of both the existing and proposed disposal areas. The pond is located within 200 feet of the proposed disposal area. The pond is contained completely within the boundaries of the disposal site and on at least one occasion has discharged to surface waters. However, there is no evidence to show that there was at least a 25 year/24 hour storm event on the occasion when the pond discharged to surface waters. Petitioner has failed to furnish the Department with the necessary information for the Department to determine if the pond discharges from the site to surface waters in a 25 year/24 hour storm event. Likewise, Petitioner has failed to provide the Department with either a copy of a storm water permit or documentation that a storm water permit was not necessary Wetlands are located along the southern boundary of Petitioner's property upon which the proposed construction and debris disposal facility will be located. These wetlands are located within 200 feet of the proposed disposal area. Petitioner has offered to reconfigure the disposal area to meet the 200 feet setback. However, Petitioner has not submitted a site plan to demonstrate the manner in which compliance with the 200 feet setback would be achieved. There is a potable water well located on Petitioner's property upon which the proposed facility is to be located which is located within 500 feet of the proposed disposal area. The permit application proposes a maximum elevation of 84 feet for the disposal area with a 3:1 slope for the entire disposal area. Petitioner has not furnished the Department with the existing elevations within the proposed disposal area. Without these elevations the Petitioner cannot show how he would comply with the proposed maximum elevation while maintaining the required 3:1 slope. Likewise, without these elevations, the Department would be unable to determine if Petitioner is complying with the proposed maximum elevation while maintaining the required 3:1 slope. Petitioner has not provided the Department with a geotechnical investigation so as to allow the Department to determine if the site's subsurface features would adequately support the proposed disposal area. The evidence in the record shows that Petitioner has not addressed all of the Department's concerns set out in Finding of Fact 4 (a) through (o). However, based on the testimony of Petitioner and Robert Butera, the Department's witness, it appears that the Department would consider the concerns set out in Finding of Fact 4 (b), (e), (f), (k), and (m) to have been adequately addressed by Petitioner. Petitioner has failed to provide the Department with reasonable assurance that the construction or operation of the facility would be in accord with applicable laws or rules.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Environmental Protection enter a final order denying Petitioner's application for a permit for the construction and operation of a demolition and debris disposal facility. DONE and ENTERED this 19th day of January, 1996, at Tallahassee, Florida. WILLIAM R. CAVE, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of January, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 95-3760 The following constitutes my specific rulings, pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the Petitioner and the Department in this case. Petitioner's Proposed Findings of Fact. Petitioner's proposed findings of fact are set out in three unnumbered paragraphs which shall be considered as proposed findings of fact 1 through 3. Proposed findings of fact 1-2 are not supported by evidence in the record. Adopted in substance as modified in Finding of Fact 14. Department's Proposed Findings of Fact. 1. Proposed findings of fact 1 through 12 are adopted in substance as modified in Findings of Fact 1 through 15. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kenneth Plante, Esquire Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Frank Strout, Pro se 11163 Agnes Street, Southwest Arcadia, Florida 33821 W. Douglas Beason, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (1) 120.57 Florida Administrative Code (6) 62-4.07062-701.30062-701.32062-701.42062-701.80362-701.900
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. NEIL WAYNE SMITH, 80-002079 (1980)
Division of Administrative Hearings, Florida Number: 80-002079 Latest Update: Jul. 07, 1981

Findings Of Fact The Respondent, Neil Wayne Smith, is a certified general contractor holding license number CG C003076. This license was suspended on March 4, 1977, for three years, and was reinstated in March of 1980. On March 21, 1980, the Respondent became the qualifier for WWRS Enterprises, Inc. This corporation had been formed in 1978 by the Respondent and his partner, William Rymers, for the purpose of engaging in the general contracting business. Mr. Rymers became president of WWRS Enterprises, Inc., and the Respondent acted as secretary, supervisor of construction, and manager of financial matters. Although the Respondent did not hold any direct stock ownership, his share of the corporate stock was registered in his wife's name. The Respondent knew that under the law WWRS Enterprises, Inc., needed to have a qualifying agent registered with the Construction Industry Licensing Board, and the Respondent and his partner discussed this subject. Since the Respondent's license was under suspension during 1978 and 1979, it was proposed that a Max Dunaway would become the qualifying agent for WWRS Enterprises, Inc., but the necessary paperwork to register him as qualifying agent for the company was never filed. Thus, until March of 1980, the company was not qualified to engage in general contracting. In November, 1979, the Respondent negotiated a contract on behalf of WWRS Enterprises, Inc., with Wilhelm Hackenberg and his wife, for the construction of an addition to their home in Ormond Beach, Florida. Since the Respondent's license was suspended, Max Dunaway pulled the building permit for the company, but the job was supervised by the Respondent, not Max Dunaway. WWRS Enterprises, Inc., was the contracting company to which at least one subcontractor submitted invoices, Mr. Dunaway's company, Southwide Builders, Inc., was not involved in this transaction. At least four construction jobs were performed by WWRS Enterprises, Inc., but only the Hackenberg job was identified by a precise time-frame during which the company had no qualifying agent. The Respondent does not challenge many of these facts. Instead, he contends that he never held any stock in WWRS Enterprises, Inc., and was only a managing employee of the company, not responsible for its policies. These contentions, however, are not consistent with the weight of the credible evidence, and have been discounted.

Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that license number CG C003076 held by the Respondent, Neil Wayne Smith, be revoked. THIS RECOMMENDED ORDER entered on this 21 day of May, 1981. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of May, 1981. COPIES FURNISHED: Michael Egan, Esquire May, 1981. Post Office Box 1386 Tallahassee, Florida 32302 Neil Wayne Smith 14 Rain Tree Drive Port Orange, Florida 32019

Florida Laws (3) 489.113489.119489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer