Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
JOHN W. MCPHAIL vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 79-002174 (1979)
Division of Administrative Hearings, Florida Number: 79-002174 Latest Update: Apr. 01, 1980

Findings Of Fact On June 27, 1979, Respondent Department of Environmental Regulation's St. Johns River District office received an application from Petitioner John W. McPhail, Deland, Florida, for a permit to conduct dredge and fill activities on his property at Lake Johnson, DeLeon Springs, Florida. The application reflected that Petitioner desired to dredge 100 cubic yards of material Waterward of the lake mean high Water line and 100 cubic yards landward of the mean high water line, and then fill an adjacent cove area on his Property with the 200 cubic yards of material. (Respondent's Exhibit 1) Lake Johnson is a small privately owned lake about fifteen acres in area. There are two distinct "lobes" of the lake which are joined by a narrow band of water. Each of these lobes is approximately seven acres in area. Some four or five houses, including, Petitioner's, are located around the lake. In the early Seventies, Petitioner dredged part of his shoreline and, in the process, too much material was inadvertently removed from the present cove area and placed in the middle of the property, which left a hump of land in the middle. The shoreline now is irregular with steep ungraded banks, and the cove area is somewhat stagnant. Petitioner wishes to restore the property by dredging the "hump" created by prior filling, and return the material to its Original location by filling the cove area. This will produce an even, sloped shoreline extending some 200 feet and improve the appearance of the lakefront. It will also reduce present maintenance Problems. (Testimony of Petitioner, Vause, Petitioner's Exhibits 1-3) A field biologist in Respondent's District Dredge and Fill Permitting Section conducted an on-site inspection on August 28, 1979, and rendered a report of the inspection on October 2, 1979. He found that the dominant plant community along the banks of the shoreline consisted primarily of upland weeds and grasses such as broomsedge and bahaia grass. Additionally, primrose willow was found in that location. The vegetation along the shoreline includes maidencane and a small amount of bullrush while the open water area is predominately vegetated with water lilies. Primrose willow is a species of vegetation found in the transitional zone of a submerged land, and bullrush, maidencane, and water lily are also fresh water species of vegetation found in submerged lands, as defined in Chapter 17-4, Florida Administrative &ode. The water depth in the lake is approximately eight feet and the depth the water at the steep banks of the Petitioner's property is approximately three feet. Wetlands vegetation of the above types are conducive to the improvement of water quality by increasing dissolved oxygen levels after removal of polluting nutrients from the water. The removal of a significant amount of such vegetation may have a measurable adverse effect on water quality. Although Lake Johnson, a Class III body of water, presently has excellent Water quality, the vegetation along the shoreline has been removed to a degree of about ten to fifteen percent. The removal of fifteen to twenty percent or more of a shoreline in such a lake normally produces a measurable adverse effect on water quality. The dredging of material along a shoreline can produce short-term turbidity of the water. (Testimony of Vause, Respondent's Exhibits 2-3) Respondent's inspector found that although filling the cove would remove some beneficial aquatic and land vegetation, would most likely reestablish if proper sloping was maintained on the shoreline. He also noted in his report that the proposed project would restore approximately one-half acre of open water to the lake. He therefore interposed no objection to the filling aspect of the project, but believed that dredging should not be undertaken waterward of the ordinary high water line, and that the shoreline should be merely contoured without dredging. By letter of October 4, 1979, Respondent's district manager advised Petitioner of its intent to deny his application for permit for the reason that the proposed work would eliminate approximately .5 acres of wetland community and thereby degrade water quality in the areas of BOD, turbidity, and dissolved oxygen. (Testimony of Vause, Respondent's Exhibits 2-4)

Recommendation That Petitioner be issued the requested permit, subject to standard conditions. DONE and ENTERED this 13th day of February, 1980, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Segundo J. Fernandez Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 John W. McPhail Route 1, Box 692H Deland, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION JOHN W. MCPHAIL, Petitioner, vs. CASE NO. 79-2174 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION Respondent. /

Florida Laws (4) 120.52120.57120.60403.087
# 1
BOCA GRANDE CLUB, INC. vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 85-003849 (1985)
Division of Administrative Hearings, Florida Number: 85-003849 Latest Update: Dec. 19, 1986

Findings Of Fact The applicant currently operates a 58 slip marina Village at the proposed site, which was constructed under a modified permit from the Department in 1980 by Sunset Realty. Subsequent to that construction, the Petitioner commenced its Marina Village project on uplands adjacent to the existing dock facility and entered into a lease with Sunset Realty to operate the present marina as part of its "Boca Grande Club." The operative portion of the existing marina, that is, where boats are moored and operate, is in water eight feet or greater in depth. The marina provides fuel service at a separate fuel dock as well as electric and telephone service at the individual slips, thus permitting boats using the slips to hook up to on- shore electrical and telephone service. Sewage pump-out equipment is available at the fuel dock and a portable sewage pumping facility is available to be moved to each slip as necessary. Boca Grande Club employs a full time dock master who lives aboard a boat at the existing facility. The facility presently generally serves larger craft, that is, boats generally larger than 25 feet in length and serves some vessels in excess of 60 feet in length. The marina village portion of Boca Grande Club is a condominium, residential development, which is nearly completed and will consist of 48 residential units. A second portion of the Boca Grande Club is located on the Gulf of Mexico some 2,000 feet away from the marina village. The entire project employs slightly more than 100 people. The Petitioner contends that the existing marina of 58 slips is not sufficient to provide adequate dock space for the residents of the development, as well as members of Boca Grande Club. It also contends that the existing dock elevations are such as to make access from small boats to the dock difficult. The number of residents or club members requiring boat slips was not established, nor was it shown that efforts to modify existing dock elevations have been attempted unsuccessfully. In any event, the Petitioner applied to the Department on February 15, 1985, to construct the approximate 3450 square feet of additional dock facility. This would include a "T" shaped structure with an access ramp or walkway extending approximately 189 feet toward the existing channel from the shore. The waterward "T" portion will be 237 feet ~n length. Additionally,. an "L" shaped structure with two sections, each approximately 75 feet in length, would be constructed which would accommodate six boat slips. The "T" shaped dock will accommodate 19 boat slips at its waterward end. The docks proposed will contain ten 3' X 15' finger piers with regard to the "T" shaped dock and two 3' X 15' finger piers attached to the "L" shaped dock. The applicant would install 42 mooring pilings in the bottom of Gasparilla Sound for the mooring of boats using the docks. Thus, the applicant proposes the addition of approximately 25 boat slips with the proposed docks, all of which will be located within Gasparilla Sound, in the Charlotte Harbor Aquatic Preserve, an Outstanding Florida Water (OFW). This is a Class II water body pursuant to Chapter 17-3, Florida Administrative Code, and has also been designated an outstanding Florida water, pursuant to Rule 17-3.041, Florida Administrative Code. The docking facility will be located in an area vegetated by sea grass, including turtle grass and associated algae. The access ramp for the "T" dock would be through a mangrove fringe including red, white and black mangroves. The Department's appraisal recommended denial of the application unless certain modifications to the "T" shaped dock are accomplished, including omitting the "T" shaped docking structure or relocating it to an area without grass beds; that the pilings should be driven into place rather than placed in augured holes; that turbidity screens should be installed and staked around the proposed piling site and that no boats over 25 feet in length or equipped with heads or toilets should be allowed to moor at the docking facility, nor should boats be permitted with people living aboard them. On September 5, 1985, the Respondent issued its Intent to Deny indicating that the project was expected to violate water quality standards and that the construction of the dock and the presence of the moored boats attendant to use of the dock would lower existing water quality in terms of turbidity, biological integrity, bacteriological quality, especially as to fecal coliform and total coliform bacteria and based upon the DER's position that the "T" shaped dock would not clearly be in the public interest in several respects. The Department has no objection and proposes to issue a permit for construction of the smaller, "L" shaped dock. In response to the Intent to Deny, the Petitioner resurveyed the seagrasses in the area and located a site where the water depths sloped to deeper water and seagrasses were sparser. It modified its application, moving the waterward extension of the dock over the deeper water in the less dense seagrasses, but could not move the dock to a location to avoid seagrass since to do so would not allow maneuvering room for larger boats utilizing the existing dock. The applicant agreed to the other suggestions of modification by the Respondent. Thus, the applicant subsequently modified the application to include "bow-in" mooring of boats so as to place boat propellors over the deepest possible waters at the mooring site, as well as raising the central portion of the access ramp leading waterward from the shore, to provide for greater light penetration and less shading of seagrasses, as well as narrowing the dock to five feet in width where it passes through the mangrove fringe, so as to limit alteration of the mangroves at the site to only three trees. The Department continues to take the position that the permit should be denied, however, on the basis that the construction of the dock and the presence of the boats attendant to the dock will lower existing water quality in terms of the above particulars and based upon the DER's evaluation that the "T" shaped dock will not clearly be in the public interest. AMBIENT WATER QUALITY The Petitioner tendered C. W. Sheffield, professional engineer, and Dr. Martin Roessler as experts in the field of water quality and they were accepted without objection. The respondent tendered the expert testimony of Mr. Doug Frye and William Porter, respectively a dredge and fill specialist and supervisor and an environmental specialist with the Shellfish Monitoring Program for the Department of Natural Resources, who were accepted as expert witnesses in the areas of water quality and, with regard to Mr. Porter, the impacts of water quality on shellfish. It was thus established that the ambient water quality in the cove which contains the present marina and where the proposed docking facilities would be is generally good. The water meets all relevant State regulatory standards with the exception of fecal coliform and total coliform bacteriological standards for Class II waters. In that regard, repetitive samples have shown violations of the fecal coliform and total coliform bacteriological standards for Class II waters on a number of occasions. The data relied upon concerning fecal coliform organism levels at the project site was collected and analyzed over approximately a one year period during which time the samples were shown to contain fecal coliform and total coliform bacteria in violative concentrations a number of times. Marinas are known discharge sources for fecal coliform organisms. This is especially true of moored boats in marinas which often have toilets or heads which are illegally flushed into the State waters within the marina. The presence of moored boats with heads are known discharge sources of fecal coliform organisms and the boats utilizing the present marina and the proposed project do, and likely will, have toilets on board, which can be improperly discharged into the waters of the marina. This marina has been established to be a source of discharge of fecal coliform organisms in violation of the relevant standard for Class II waters of the State. There presently exists relatively high levels of fecal coliform organisms ranging up to 50 organisms per 100 milliliters of water in the area of the existing marina. This level of concentration exceeds the regulatory standard for fecal coliform bacteria in the Class II water quality rules. Although Mr. Porter discussed the possibility that high levels of coliform bacteria could be caused by birds or animals depositing fecal material in the water, he established that the likely source of elevated levels of this bacteria was improper operation of heads aboard boats, as pointed out by the fact that samples taken in other areas of the Gasparilla Sound away from marina sites do not exhibit the high coliform levels found on repeated occasions at the subject site. Thus, it has been established that the ambient water quality is within State standards for all parameters with the exception of fecal and total coliform bacteria for Class II waters. The Petitioner contends that Class III water standards are appropriately applied herein inasmuch as the Department placed the Class III standards rather than the Class II standards at issue in its Intent to Deny, albeit mistakenly. There is no question, however, that there are Class II waters of the State involved at this site and the subject area is within the aquatic preserve and outstanding Florida waters. The Petitioner is charged with knowledge of this inasmuch as the aquatic preserve boundaries are delimited in the Department's above-cited, published rule. In preparing and processing its application and electing to proceed with this project, the Petitioner is charged with knowledge that these are Class II waters and that the water quality criteria and considerations applicable to Class II outstanding Florida waters are the appropriate parameters with which it must comply. In any event, this is a de novo proceeding and the Department's initial position with regard to this application is not binding in favor of or to the prejudice of any party to the Section 120.57(1), Florida Statutes proceeding. IMPACT ON BENTHIC COMMUNITY ·9. There is a moderate stand of seagrass at the proposed site of the "T" portion of the dock or waterward end of the dock, with dense seagrass beds existing toward the shore, over which the narrower walkway portion of the dock will traverse. Seagrass beds are an especially productive marine community which contribute greatly to the biological diversity in surrounding waters because of their important function in the marine food chain. That function is involved with the seagrasses production of detrital matter consisting of seeds and vegetative material which marine organisms feed upon and upon which organisms larger fish, including commercial and sport fish species, feed upon. Potential adverse impacts caused by a project of this type on the Benthic Community at the project site and especially the seagrass beds involve the potential shading of seagrasses caused by the location of the dock over them, as well as the mooring of boats over them which shading retards or eliminates photosynthesis, which ultimately can kill the seagrass and thus reduce marine productivity in the area. The concentration of boats at such a mooring site as the end of this "T" dock will concentrate the effects of prop scouring, washing and prop dredging, which will have a destructive effect on seagrasses as well as the settling out of sediment from propellor wash or disturbance of the bottom on the seagrasses which can ultimately smother them as well as other marine life forms. In discussing these considerations, it should be pointed out that the "T" portion of the dock would be oriented in a general north-south direction which causes the shadow of the dock to move rapidly as the sun passes overhead in a general east to west direction. This would tend to minimize the effect of shading on the seagrass of the dock itself, particularly with regard to the approach ramp portion of the dock which is relatively narrow. That portion of the dock extending toward the shore runs in an east to west direction and would not exhibit the same rapidly moving shadow, but the central portion of the approach walkway has been elevated to such an extent that light reaching under the dock from both sides will be sufficient to allow photosynthesis of the seagrasses under the dock, although not for as long a period of the day nor at the same rate as would be the case if the dock were not present. The Petitioner asserts that its voluntary relocation of the "T" shaped portion of the dock from an area of dense sea grass to a moderately populated sea grass bed plus the proposed bow-in mooring of boats so as to alleviate propellor damage to the seagrass, together with its view concerning the prevailing water depth at the end of the dock, will serve to prevent damage to the seagrass at the end of the "T" dock where the boats will be moored. It has been shown, however, that the mooring of boats whether bow-in or otherwise will still create a significant amount of shading of the bottom which, together with the shading caused by the "T" dock as well as the associated finger piers will retard or prevent photosynthesis to some extent, especially where boats are moored for days at a time without moving. This will significantly reduce the marine productivity attributable to the seagrass by retarding its natural function or, in some cases, killing it with the resultant loss of the detrital production as well as carbon production, the former being crucial to the proper functioning of the marine food chain in the area. If the seagrass is damaged or extinguished by the shading effect, prop scouring and washing, and/or settlement of turbidity on the seagrass, or a combination of these factors, not only will its productivity be lost, but the biological diversity of marine life in the area will be reduced as it relates to those vertebrate and invertebrate marine animals which depend on seagrass as a food source either directly or indirectly. Dr. Roessler, for the Petitioner, opined that the attached biological communities or "fouling" organisms such as barnacles which would form on the dock pilings, if they were installed, would provide habitat for marine life and invertebrates and thus enhance the biological diversity of the area. These fouling organisms which attach to pilings, however, represent a very narrow portion of the potential marine biological diversity of life forms in an area such as this. Their advent on the pilings, should the pilings be installed, would not mitigate for the loss of important marine habitat and resultant species diversity that elimination of this portion of the seagrass beds would pose. Thus, reasonable assurances have not been established that significant adverse impact to the Benthic Community in the form of damage or elimination of the seagrass beds and their dependent biota will not occur due to shading and propellor scouring, dredging and washing occasioned by the installation of the docking facility. Respondent's expert witnesses Sheftal, Barth, and Dentzau uniformly expressed a concern for propellor scarring, dredging and prop washing of the seagrass beds caused by an improper operation of boats in the project area where water is too shallow over the grass beds to protect them from the resultant propellor damage. In this regard, the Petitioner's own experiments with actual boats indicated that approximately one to 1 1/2 feet of water will remain between the bottom of the sound and the boat propellors at the end of the "T" dock for the general type and size of boats which will use the dock, even assuming that the boats are moored bow inward, thus taking maximum advantage of the deepest water possible under the propellors when a boat engine is started. Respondent's witness Dentzau performed a test with a 21 foot boat with an approximately 100 horsepower outboard engine running it in both forward and reverse at the "T" end of the dock. He was able to readily generate a "plume" of turbidity consisting of sand and other bottom material suspended in the water by the scouring action of the propellor. Although it was demonstrated for water quality parameter considerations that this turbidity plume did not violate the water quality standards for turbidity, it obviously shows that over time the turbidity suspended by boat propellors will settle on the seagrasses and other bottom dwelling biota to their detriment and, more immediately important, demonstrates that prop washing and scouring will occur by boats even if moored bow-in at the presently proposed site of the "T" shaped portion of the dock. The Petitioner proposes by the configuration of its "L" shaped dock in conjunction with the IT" shaped dock, as well as with buoy lines, to keep boat traffic away from the dense grass beds surrounding the proposed dock site and over which the walkway will extend. The Petitioner will mark the entrance channel to the marina itself to keep boats from straying over adjacent grass beds. It has not been demonstrated, however, what steps can be taken to effectively prevent boats from approaching the side of the proposed dock around the ends of the buoy lines and over the dense grass beds toward prohibitively shallow water where prop scouring and scarring will occur. Further, although the Petitioner will mark the entrance channel to the marina itself to keep boats from straying over adjacent dense grass beds, the likelihood of propellor damage to the grass beds in the vicinity of the end of the "T" dock has been exacerbated by the concentration of boat traffic which will result by installation of that dock, over waters at the mooring site which are of insufficient depth to protect the grass bed at that location from scouring and washing from boat propellors. In view of these reasons, significant adverse impacts to the Benthic Communities and especially to the grass beds themselves will result by installation of the docking facility at the site proposed, primarily because of insufficient water depth for safe operation of boats in relation to the well-being of the grass beds in the vicinity of the end of the dock and because of the shading which will result by installation of the "T" shaped portion of the dock in conjunction with the boats to be moored to it and the finger piers between the boat slips attached to it. WATER QUALITY The Respondent, through its water quality expert witness, Doug Frye, expressed the concern that the proposed project would violate Rule 17-3.051, Florida Administrative Code, which requires that the State's waters be free from pollutants above a certain level measured by various accepted and codified scientific methods of measurement. In this regard, the primary concern of the Department is bacteriological quality as well as turbidity resulting from boat operation. The turbidity standards contained in the above Rule provides that State waters not exceed 29 nephelometric turbidity units above the natural background level. The Respondent contends that this level will be exceeded as a result of operation of boats in the vicinity of the dock. The Petitioner, however, presented a soils analysis and silt settling study which showed that bottom materials in the area involved consist of sand, with some finely pulverized shell and that this material settles very rapidly after being disturbed with little silt remaining in suspension a significant period of time after the disturbance. This is primarily because the level of organics in the bottom substrate is very low at this site. In this connection, the Petitioner's expert witness, Mr. Sheffield, anchored a 16 foot boat with a 40 horsepower outboard motor in the docking area of the proposed project. He operated the boat at 1,000 RPM for an extended period of time while measuring the resultant turbidity. The results of his measurements showed turbidity to be in the range of 5-11 NTUs. The Respondent's witnesses, however, operated a larger 21 foot boat at the location of the "T" shaped portion of the dock maneuvering it back and forth with a fairly large outboard motor in the 100 horsepower class, which might be presumed to be typical of the boats which will be using the proposed facility. The maneuvering of the boat with the larger engine in this shallow water created a clearly visible plume of turbidity shown by photographs introduced into evidence by the Respondent. In fact, however, although the turbidity plume was clearly visible, the Respondent's own direct measurement of turbidity taken from within the plume immediately after it was generated was 23.8 NTUs, still below the State standards for violations as to turbidity. The existing marina facility has a fuel dock and has adopted a fuel spill contingency plan. There will be no fueling of boats nor fuel kept at the proposed docks. Nevertheless, marinas were established to be a known source of discharge of oils and greases and the presence of more boats utilizing all the dock facilities, especially during fueling and maintenance procedures, will result in additional oils and greases being deposited in the water. Even if there is no fueling facility planned for the proposed docks, the additional boats represented by the 25 additional slips sought to be approved will have to be fueled and likely at the existing facility. This will heighten the risk of fuel, oil and grease spills. In this regard, it must be remembered that the present marina and the proposed docking facilities are in outstanding Florida waters in which no degradation of ambient water quality is permitted. In this context then, the Petitioner/Applicant has, not provided reasonable assurances that pollution levels for oils and greases will not increase as a result of the potential addition of 25 boats to this marina facility. A substantial issue has been raised in this proceeding concerning water quality as it relates to the bacteriological standard. It has been established that this marina is presently a source of discharge of fecal coliform organisms which frequently are present in sufficient concentrations so as to violate the standard for that organism for Class II waters. Fecal coliform bacteria are accumulated in the bodies of shellfish. The shellfish themselves are not harmed, but contaminated shellfish can accumulate concentrations of as much as 100 times the ambient fecal coliform bacterial levels present in the waters they inhabit. Fecal coliform bacteria can cause extreme illness in human beings, sometimes even paralysis and death. Fecal coliform bacteria in State waters results from the deposition therein of human or animal waste. The Petitioner maintains a sewage pumpout station located at its fuel dock with a direct connection to its sanitary upland sewer system, as well as a portable sewage pump that can be moved to each boat slip for pumping out of toilets or "heads" on boats. Upland fish cleaning stations will additionally be provided with the proposed docks so as to prevent refuse from fish cleaning activities being deposited into the waters of the cove. The fact remains, however, that there presently exist high levels of fecal coliform organisms in the waters of the cove at the marina site, in the above noted violative concentrations on repetitive occasions. The presence of boats moored in the marina with "heads" aboard are a known discharge source of fecal coliform organisms. The Petitioner proposes to restrict boats using the facility to those boats without marine heads aboard or requiring those with heads to keep them locked or otherwise not discharge them into the waters of the marina. If boats utilizing the marina have toilets aboard, however, there is a substantial likelihood that at some point those toilets will be discharged into the waters of the cove before any of the Petitioner's monitoring personnel are aware of it. The problem is thus one of enforcement. In this regard, it is established that even with the sewage pumpout station and the portable sewage pumpout device, that there are a number of "live-aboard" boats with marine heads in the marina at the present time and customarily. This has caused the above found violations of fecal coliform, Class II water standards. Although the Petitioner proposes to restrict boats at the proposed docking facility to those less than 25 feet in length and to establish a monitoring program by the marina management personnel to assure that the boats with heads only contain heads approved by Coast Guard regulation, reasonable assurances have still not been established that the enforcement plan proposed can be effective in ensuring that no marine heads or other sources of coliform bacteria will be discharged into the waters of the cove at the project site. The plan proposed by the Petitioner simply did not ensure that boats having marine heads will not use the marina and that those persons using boats so equipped will not, on some occasions, discharge the heads into the waters of the marina at the project site nor that spills will not result in the sewage pumping-out process. The Respondent's expert witness, Mr. Porter, confirmed that most fishing boats of the open "center console" variety of 25 feet length or less do not contain marine heads, nevertheless, he established that in his experience monitoring marinas of this sort, the restrictions against marine heads of the non-approved variety and the attempted restriction against boats discharging the contents of their heads into the waters of the marina cannot be effectively enforced nor was it established that fishing boats without marine heads will be the only type of boat to use the proposed docking facilities. Accordingly, the waters of the cove at the marina site and project site are in frequent violation of the fecal coliform and total coliform parameter for Class II waters and reasonable assurances have not been provided that the fecal coliform bacterial levels will not increase as a result of the installation and operation of the proposed facility with its attendant boats. Because of the likelihood of shellfish contamination by fecal coliform bacterial levels which will likely increase if the proposed project is constructed and operated, together with the loss of marine habitat and productivity posed by the harm likely to result to the seagrass beds in the vicinity of the proposed facility due to attendant boat operation, it has been shown that the water quality parameter for biological integrity in these Outstanding Florida Waters will likely be degraded. The "Diversity Index" of marine microinvertebrates in the area of the affected seagrass beds will likely be reduced below 75 percent of background levels. Therefore, in the context discussed above, the proposed construction and operation of the 25-slip marina facility with the "T" dock will lower ambient water quality in these outstanding Florida waters and will result in violations of State water quality standards for Class II waters in the above particulars. SHELLFISH HARVESTING Mr. William Porter of the Department of Natural Resources Bureau of Shellfish Sanitation established that the cove where the project would be located is closed to the taking of shellfish as a result of the contamination or potential for contamination of shellfish by coliform bacteria contained in fecal material. His Department's water quality sampling confirmed the elevated levels of fecal coliform bacteria in the cove on repetitive occasions. This elevated level of coliform organisms was shown to result from improper operation of marine toilets upon vessels using the marina at the present time. Because of the potential for contamination from vessels discharging fecal material, Mr. Porter established that the Department would likely close an area 50 percent larger than the present shellfish harvest closure area as a result of a 50 percent increase in the number of boats capable of using the marina if the proposed project is built. Mr. Porter acknowledges that if it could be assured that boats using the marina did not contain heads, the increased area of closure might be lessened after this project were built. He also established as pointed out above that such restrictions on boats containing heads from using the proposed boat slip is very difficult to enforce. Even with the present central sewage pumpout facilities and portable pumpout equipment at the existing marina, the marina still has failed to comply with fecal and total coliform standards for Class II waters on a repetitive basis. The management of the present marina has allowed live-aboard boats at the marina even though it has posted warning signs against boat owners discharging toilets in the cove waters. Mr. Porter also acknowledged that the Boca Grande North Marina, owned by Gasparilla Pass, Inc., was recently permitted by the DER and constructed and has not yet resulted in the Department's closing an additional area to the taking of shellfish. The area the marina is situated in, however, is only "conditionally approved" for the taking of shellfish, meaning that it is subject to closer monitoring by the DNR with a view toward the possible necessity of closing waters in the area of that marina. It was not established, however, how the fecal coliform or total coliform levels in the waters adjacent to that marina compare to the existing marina or the site of the proposed docking facilities at the existing marina, nor what conditions might prevail which would render that other marina a comparable site to -be used as a relevant demonstration of what conditions might be expected at the present marina if the proposed project were built and operated. Thus it has been shown that even though the Petitioner proposes limiting the size of boats at the proposed facility and closely inspecting and regulating any marine heads on boats using the facility to make sure they comply with Coast Guard regulations, it has not been demonstrated that the additional deposition of fecal coliform bacteria in the waters often the cove will be adequately prevented by the proposed enforcement measures. It is thus reasonably likely that the construction of the proposed project will lead to the closing of an additional area of water which is presently approved for shellfish harvesting. The closure of shellfish harvesting in waters is contrary to the public interest in terms of recreational values, fishing and marine productivity and others of the seven public interest criteria quoted below. Further, the contamination of shellfish, which can cause severe illness or even death in human beings, is clearly contrary to the public interest and there is a substantial likelihood that shellfish contamination is already occurring in the area due to the characteristic of shellfish by which they accumulate or store fecal coliform organisms to reach injurious levels for human consumption even though the shellfish themselves appear to be healthy. The area of the proposed project is extensively used for commercial and recreational shellfish harvesting at the present time, outside the immediate closed waters of the marina within the cove. PUBLIC INTEREST Section 403.918(2) (a) (1-7) requires that the Petitioner provide reasonable assurances that the proposed project will be clearly in the public interest. The public interest considerations of those seven criteria concern whether the project will adversely affect public health, safety or welfare or property of others: whether it will adversely affect conservation of fish and wildlife or their habitats; whether it will adversely affect the fishing or recreational values or marine productivity in the project vicinity; whether it will be of a temporary or permanent nature; and the effect on the current condition and relative value of functions reformed by areas affected by the project. Although Petitioner's witness, Dr. Roessler, related that the attached fouling communities, such as barnacles, which would form on the proposed docks and pilings would increase the diversity of marine habitat available, that will not offset the loss of marine habitat occasioned by the increasingly detrimental effect imposed by the project and the operation of it on the seagrass beds, in the manner discussed above. The fouling communities expected by Dr. Roessler to occur on the pilings to be installed, will not provide, nor replace the value of, the detritus (seeds and leaves) produced by the seagrass which would be lost, which is an important food source for marine organisms in the upper portion of the food chain in the area, some of which organisms include fish and have a high recreational value and commercial value. The importance of detrital production by the seagrass beds outweigh the value of the addition of the fouling communities on the pilings. In fact, the total diversity of marine species actually might decline even though the fouling organisms would be added with the installation of the pilings, once the harmful effects on the seagrass beds begin to occur after installation and operation of the proposed facility and over the life of the marina. Thus, in this regard, the project is contrary to the public interest and certainly not clearly in the public interest. Additionally, there is a substantial likelihood that shellfish may be contaminated which, in turn, will have an adverse effect on the public health, safety and welfare. The harvesting of shellfish has a substantial recreational and commercial value and is an important aspect of the marine productivity in the vicinity of the project. The heightened coliform bacteria production caused by the resultant expansion of the marina will adversely affect fishing and recreational values and marine productivity and will degrade the current condition and relative values of the functions performed by the marine habitat in the vicinity of the proposed dock. Finally, there is no question that the project will be of a permanent nature. The various detrimental effects on the public interest consideration found herein are rendered more critical by the fact that there is no truly redeeming public purpose or use for this project. This will be essentially a private docking facility designed to serve the residents of the applicant's attendant real estate development. The upland development is a condominium development and the slips will be owned by the condominium owners and not open to the general public, although the Petitioner did make vague reference to an idea that some slips might be rented to members of the public. This was not established to be the case and, in any event, the primary purpose of the boat slips is to enhance the desirability of the upland development. Although the Petitioner emphasizes that the advent of the additional slips might help attract as much as $1,000,000 additional revenue to the Boca Grande area by assisting the applicant in hosting the Annual Tarpon Release Fishing Tournament, it is also true that any development in a coastal area will likely represent some economic benefit to that area, but there is also a substantial economic and recreational benefit to maintaining the outstanding Florida waters involved in an undegraded condition and maintaining the present Class II, approved shellfish harvesting area unimpaired. Thus, although the proposed docks might be used for sponsorship of the subject fishing tournament and it can be said that that would enhance fishing and recreational value to some extent, it was not established that the tournament will not occur and that the extra revenue and enhancement of fishing and recreational value it will generate will not occur in the Boca Grande area anyway. The potential detrimental effects of the proposed project, delineated above, will also decrease fishing and recreational value over many years and for the life of this project in terms of harm to the marine habitat occasioned by the constant deposition of oils, greases and fuel and coliform bacteria in the Class II waters involved, as well as the other detrimental aspects of the project discussed above. It has not been established that the economic benefits of the fishing tournament and the addition of the boat slips will not occur but for the installation of this proposed docking facility. Although it may help relieve a shortage of marina slips in the area, it was not shown that this is the only alternative to relief of that shortage. ALTERATION OF MANGROVES The original site for the access ramp or walkway to the "T" shaped portion of the dock was selected through an on site inspection conducted in part by Respondent's witness, Andrew Barth. The mangrove area is less dense at the site of the walkway's penetration of the mangrove belt than surrounding mangrove areas. Petitioner's witness, Dr. Roessler, has participated in many studies involving mangroves in South Florida. He identified each tree within the proposed dock pathway. Through narrowing of the dock walkway to five feet and the relocation agreed upon by the Petitioner and Mr. Barth, it has been established that only three mangrove trees will be removed by the construction of the dock. Thus, there will be no substantial alteration or degradation of the mangrove fringe area at the project site. DOCK CONSTRUCTION Mr. C. W. Sheffield was accepted as an expert witness in the field of marine engineering. He established that the pilings will be installed using a 6 to 8 inch chisel point driven into the bottom of the sound with an air hammer. There will be no augering or other means of excavation used which would generate a substantial amount of turbidity. The air hammer will result in compaction of sediments by forces radiating out from the piling as it is driven, with the counteracting sheer force caused by the piling installation causing a slight bulging in the bottom around each piling, but nothing more. There will be no significant movement of sediment in the water column. The construction of the dock will take place moving from the land waterward, utilizing equipment mounted on the dock. Thus, construction barges will not be required to come into the shallow grass bed area with the potential for its damage. Small barges would be used in the deeper waterward portions of the project to install the mooring pilings off-shore from the end of the "T" dock. Turbidity curtains will be used during all construction, surrounding all phases of the construction work. In Mr. Sheffield's experience, such measures have resulted in no violation of the State turbidity standards at other similar projects, and are not likely to with this one. CUMULATIVE IMPACT A number of permits have been issued by the Department for docking facilities to the north of this proposal and other facilities are already in existence. Dr. Roessler opined that the geographic location of these, as well as that of this project, in light of the numerous inlets and high degree of tidal flushing and exchange through the inlets, will not result in any adverse cumulative impact occasioned by the addition of the proposed dock with 25 slips to those already existing in the Sound. It is noteworthy that, with regard to the potential this project poses for damage to the seagrass beds and for heightened production of fecal coliform bacteria, with the environmental damage attendant thereto, no proof was offered by either party concerning those considerations or effects to the extent that they might or might not exist at other marinas or docking facilities in the Gasparilla Sound area. There has been no proof to establish any cumulative impact.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the testimony and evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that a Final Order be entered denying the subject permit application, except for that portion seeking authorization for the "L" shaped dock and six boat slips attendant thereto, which should be granted with the agreed-upon conditions and restrictions contained in the above Findings of Fact. DONE and ENTERED this 19th day of December, 1986 in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of December, 1986. APPENDIX Petitioner's Proposed Findings of Fact: The rulings on the Petitioner's Proposed Findings of Fact are numbered below in the order in which they were presented (unnumbered) by the Petitioner. 1-6. Accepted Accepted, excepted for the last two sentences which are immaterial Accepted. Accepted, except as to the proffered material import of the last sentence. Accepted, except the first sentence which is not in accord with the greater weight of the evidence. Accepted, except as to the last three sentences which are not supported by preponderant evidence 12-16. Accepted. Rejected, as not in accordance with the preponderant evidence of record. Rejected as not being in accordance with the greater weight of the evidence. Accepted, but not as dispositive of any material issue presented. Accepted, except as to the last sentence which is rejected as being contrary to the preponderant evidence adduced. Accepted, except as to the third and last sentences which are rejected as being contrary to the preponderant evidence adduced. Accepted, except for the third and last two sentences which are rejected as to their purported import in the resolution of the material issues presented and as being not in accordance with the preponderant evidence adduced. Accepted. Accepted, but not as dispositive of the jurisdictional issue concerning "dredging and filling" for the reasons found in the Recommended Order. Accepted. Accepted. Respondent's Proposed Findings of Fact: 1-18. Accepted 19. Accepted, but not dispositive of any material issue presented. 20-25. Accepted. Rejected as not being a complete finding of fact. Accepted. Accepted, except as to the issue of water dept which would actually be less at the critical location involved. Accepted. Accepted, but not material. 31-31. Accepted. 35. Accepted, but not truly material in this de novo proceeding. COPIES FURNISHED: Robert A. Routa, Esquire 217 South Adams Street Tallahassee, Florida 32302-1386 Bradford L. Thomas, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Mary F. Smallwood, Esquire General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Stephen Fox, Director Division of Environmental Permitting Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 ================================================================ =

Florida Laws (6) 120.57120.68258.392267.061403.061403.087
# 2
R. E. LAUTHAIN vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 76-001960 (1976)
Division of Administrative Hearings, Florida Number: 76-001960 Latest Update: Jun. 08, 1977

Findings Of Fact The Petitioner owns property which fronts on Lake Serena in Putnam County, Florida. Petitioner has submitted an application to the Respondent to dredge an area waterward of the ordinary high water line of Lake Serena and to place the dredged material on another area waterward of the ordinary high water line. Approximately 13,000 square feet of surface area presently dominated by wetlands vegetation would be removed by the dredging activity. The Petitioner proposes to cover the area where the fill is deposited with white sand. Petitioner proposes to use the area as a sandy swimming beach. During the summer of 1976 the Petitioner commenced work on his proposed project without receiving a permit from the Respondent. The Respondent, through its agents, stopped the work, and this permit application proceeding ensued. Lake Serena is a relatively pollution-free lake. Most of the littoral or transitional zone Vegetation surrounding the lake has been replaced by sandy swimming beaches. Only approximately forty percent of the shoreline is an aquatic vegetated littoral zone. Aquatic vegetation in the littoral zone surrounding the lake serves an important and natural function in preserving the water quality of the lake, and the natural resources of the lake including fish and wildlife. The aquatic vegetation serves to filter runoff from uplands areas by assimilating nutrients that are in the runoff. Lake Serena is an oligotrophic lake. It is relatively low in nutrients. Aquatic vegetation in the littoral zone serves in part to maintain this condition. If the condition is not maintained the buildup of nutrients would cause an algae bloom, or buildup of algae plants on top of the lake. A buildup of algae on the lake would drastically decrease the oxygen levels of the lake. The algae itself uses oxygen. The algae also kills oxygen producing plants which thrive on the bottom of the lake because the algae cuts off light to these plants. As the algae dies, it sinks and decomposes and uses up more oxygen. An algae bloom of this sort, and the resulting diminishing of oxygen levels in the lake would constitute pollution. Removal of aquatic plants in the lake's littoral zone will also serve to diminish fish populations in the lake. Small fish use such an area as a nursery ground where they can hide from larger predators. The action of aquatic plants on nutrients also serves as an initial step in the food chain for fish. The littoral zone which the Petitioner proposes to dredge and fill is apparently not in its natural state. There was no direct testimony respecting past dredging activity, but there was hearsay testimony to the effect that a previous land owner had dredged what amounts to a sand bar to serve as a boat slip. The entire area is now dominated by aquatic vegetation. It is a viable part of the littoral zone of the lake, and serves the beneficial purposes set out in Paragraph 2 above. There was no evidence offered at the hearing from which it could be determined with any degree of certainty that the Petitioner's proposed project would have any finitely measurable impact upon water quality or wildlife resources in Lake Serena. Removal of all such littoral zones would, however, drastically change the ecology of the lake, and render it polluted. Sixty percent of the lake's shoreline has already been denuded of vegetation. Although it cannot be determined how much more such action the lake will tolerate, it is clear that there is a limit. If the Petitioner's project were granted, other similar projects would also be justified. Inevitably the lake's oligotrophic nature would be destroyed. While it cannot be concluded from the evidence that the Petitioner's project would have any precisely measurable effect upon water quality and upon the natural resources of Lake Serena, it can be determined that the only effect the project could have would be negative. Petitioner has not established that the project would not have an adverse impact upon water quality and natural resources of Lake Serena. Petitioner has apparently concluded that there is no other means for him to have a swimming beach on his property than through the project as he has proposed it. Other witnesses testified, however, that his property includes a site for a swimming beach on land that is not dominated by aquatic vegetation.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED: That a final order be entered denying the Petitioner's application for dredge and fill permit. RECOMMENDED this 8th day of April, 1977 in Tallahassee, Florida. G. STEVEN PFEIFFER, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: John Mussoline, Esquire CLARK & MUSSOLINE 501 St. Johns Avenue Palatka, Florida 32077 Vance W. Kidder, Esquire Department of Environmental Regulation 2562 Executive Center Circle East Montgomery Building Tallahassee, Florida 32301 Mr. Jay Landers, Secretary Department of Environmental Regulation 2562 Executive Center Circle East Montgomery Building Tallahassee, Florida 32301

Florida Laws (2) 120.57403.031
# 3
JAMES R. BENFIELD vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 88-000117 (1988)
Division of Administrative Hearings, Florida Number: 88-000117 Latest Update: Nov. 02, 1988

Findings Of Fact The Petitioner is the owner of five acres of undeveloped real property in Henderson Creek Basin, Naples, Collier County, Florida. The property is dominated at the tree canopy level by medium-sized cypress. The mid-story plant association is made up of a varying mix of wax myrtle, dahoon holly, seedling cypress, and a lesser amount of slash pine. Hypercium, stillingia, poverty grass, and xyris are the major components of the ground cover. In the vicinity of the proposed homesite, the ordinary mean water depth averages 2-4 inches, as indicated by the water marks on the stems of cypress, stillingia, and cypress knees. Based upon the dominant vegetation, the project site is within the jurisdiction of the Respondent for the regulatory purposes set forth by law. The Petitioner intends to build a house on the property for his personal use. In order to construct the residence, the Petitioner applied to the Respondent for a dredge an fill permit. In the application,, the Petitioner seeks a permit which would allow him to place 1,200 cubic yards of sand fill over a .17 acre area of the submerged land. The proposed location for the housepad, septic tank and drainfield is the center of the five acre parcel. This is the predominant area in which the Petitioner seeks to place the fill. A large portion of this part of the property is low and consists of wetlands. The project, as it is designed in the permit application, does not provide the Respondent with reasonable assurance that the applicable water quality standards for the geographical area will continue to be met. In fact, the proposal demonstrates that a violation of the standards will occur. The Petitioner recently cleared 14,340 square feet of the wetlands in the proposed homesite area. The cypress trees which ware removed acted as a pollution filtration system and aided in the cleansing of the standing waters on site. These waters eventually percolate down to the aquifer to become an important source of fresh water for the state. Without the trees, the water will lose an important aid in the natural purification process. In addition to the adverse impact on water quality, the project will interrupt the natural water flow and filtration which has historically occurred when the water located in the low wetland area on the property has overflowed and eventually run into Henderson Creek. The Respondent is required to consider this natural condition in its determination as to whether or not a permit should be issued. The Respondent has indicated that certain changes should be made to the project in order to make it eligible to receive a permit. The Respondent suggested that the Petitioner relocate the fill area for the house pad eighty- five feet to the west of the proposed site. The septic tank and drainfield should be moved one hundred and ten feet to the west. The drive should be reduced to a single lane which leads directly to the housepad. In addition, three culverts should be placed under the drive. The purpose of these modifications would be to minimize the impact of the project on the wetland site. The movement of the project away from the cypress area would minimize the damage to water quality that would occur if the septic system were placed in the wetlands. If the design for the lane and driveway were modified, the harm to the natural sheet flow of the water through the area on its route to the creek would be greatly reduced. Another suggested modification was to remove exotic vegetation which has been planted or which has begun to dominate in some areas because of the clearing of the property which took place before and after the Petitioner purchased the property. The Respondent also seeks a construction plan from the Petitioner which demonstrates that the fill areas will be adequately stabilized and that turbidity will be controlled during construction. The final modification suggested by the Respondent was for the Petitioner to place a deed restriction on the property which would protect the planting areas and the remainder of the wetlands on the site. The Petitioner's expert, Gary L. Beardsley, has recommended that the proposed circular entrance driveway be eliminated and that a single and straightened lane be substituted its place. He further recommended that one 12" diameter culvert should be installed under the lane near the housepad in order to facilitate or equalize any sheet flow on the downstream side. This recommendation is made to substitute for the agency's proposal that three culverts be placed under the straightened lane. In addition, the Petitioner's expert recommended that the septic drainfield be moved 30 feet westward to reduce the fill slope requirements by abutting the house and septic fill pads. The Petitioner should also be required to replant 5,265 square feet of wetland area that he cleared on site with the approval of the Collier Natural Resource Management Department, but without the approval of the Respondent. The Petitioner has not agreed to any of the proposed modifications, including those proposed by his own expert. The Respondent's request for a deed restriction is not necessary to the agency's regulatory function. There was no reason for the request presented at hearing by the agency.

Florida Laws (2) 120.57408.817
# 4
PALMETTO POINT HOMEOWNERS ASSOCIATION vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-003488 (1983)
Division of Administrative Hearings, Florida Number: 83-003488 Latest Update: Apr. 02, 1984

Findings Of Fact On December 9, 1982, Petitioner filed with Respondent a dredge and fill permit application to remove gates and wing-walls from a double-lock canal system presently installed at the Palmetto Point Subdivision in Lee County, Florida, adjacent to the Caloosahatchee River. On January 6, 1983, Respondent sent a "completeness summary" to Petitioner, along with a letter advising Petitioner that its permit application was incomplete, and requesting additional information. Petitioner responded to the January 6, 1983, completeness summary by submitting additional information to Respondent on or about February 23, 1983. On March 21, 1983, Respondent sent a second completeness summary requesting further additional information from Petitioner. By letter dated May 18, 1983, Petitioner's attorney advised Respondent that submission of additional requested hydrographic information and water quality data was not justified. The letter further advised that Petitioner intended to rely on the information already submitted, and requested, pursuant to Section 403.0876, Florida Statutes, that Respondent begin processing the permit application. The letter further indicated that petitioner was submitting under separate cover a request that Respondent apply the "moderating provisions" of Rule 17-4.244, Florida Administrative Code, to the application. The aforementioned rule is entitled "Mixing Zones: Surface Waters." Also on May 18, 1983, Petitioner's counsel sent another letter to Respondent requesting the aforementioned "Mixing Zone." The letter requested the "maximum mixing zone" allowed under the applicable Provisions of Rule 17- 4.244, Florida Administrative Code. Petitioner had not requested a mixing zone be applied to the permit application prior to the request contained in its May 18, 1983, letter. By letter dated June 17, 1983 Respondent, in response to Petitioner's May 18, 1983, letters, advised that: The additional information [which] was received on May 19, 1983, was reviewed; however, the items listed on the attached sheet remain incomplete. Evaluation of your proposed project will continue to be delayed until we receive all requested information. Respondent's June 17, 1983, letter included a completeness summary, which asked for additional information, including the following requests concerning mixing zones: Your request for a mixing zone is applicable pursuant to F.A.C. Rule 17-4.244(6). Please provide a map indicating the outermost radius of the mixing zone (no more than 150 meters) and the period of time required. The completeness summary acknowledged Petitioner's refusal to supply additional information concerning hydrographic data and water quality information, and indicated that Respondent would evaluate the project accordingly. By letter dated August 29, 1983, Respondent advised Petitioner that it had been 73 days since notification of the incompleteness of the permit application with regard to the mixing zone request. This letter requested Petitioner to advise Respondent if it wished to withdraw the application, request additional time, or discuss questions regarding the application. The Petitioner did not respond to this communication. On September 9, 1983, Petitioner's attorney forwarded a letter to Respondent requesting a default permit pursuant to Sections 120.60(2) and 403.0876, Florida Statutes. Until this letter, other than a prior oral communication on September 2, 1983, notifying Respondent that the default request was forthcoming, Petitioner had not contacted Respondent concerning the permit application since its May 18, 1983, letters. On October 13, 1983, Respondent advised Petitioner by letter that the mixing zone request constituted a revision of the application and that the information received to evaluate the mixing zone request was incomplete. Petitioner was also advised that since the additional information requested had not been received, the application remained incomplete and Petitioner was not entitled to a default permit. Whether or not a mixing zone is applied to a permit application is significant because it determines where state water quality standards must be met, either adjacent to the proposed project, or up to 150 meters away from the project location. Under Rule 17-4.244(6), Florida Administrative Code, the 150 meter radius is measured from the point of generation of turbidity or pollution. Since the two locks to be removed were 80 feet apart, it was unclear whether Petitioner intended the point of generation for measuring the radius of the mixing zone to be the northern lock, the southern lock, or some other point. It is equally unclear whether Petitioner intended the mixing zone to extend south into the canal as well as north into the Caloosahatchee River. Petitioner never contacted Respondent to clarify the dimensions of the mixing zone being sought, even after Respondent requested a map indicating the outermost limits of the mixing zone in the June 17, 1983, completeness summary.

Florida Laws (3) 120.57120.60403.0876
# 5
ST. JOHNS RIVERKEEPER, INC. AND HENRY O. PALMER vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 09-007054RX (2009)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Dec. 29, 2009 Number: 09-007054RX Latest Update: Nov. 16, 2010

The Issue The issues to be determined in this case are: whether Petitioners have standing; and whether Rule 62-302.800(2) is an invalid exercise of delegated legislative authority, as defined by Section 120.52(8)(b) and (c), Florida Statutes.3

Findings Of Fact Petitioner, St. Johns Riverkeeper, Inc. (Riverkeeper), is a nonprofit, membership-based corporation with its principal place of business in Jacksonville, Florida. It is dedicated to the protection, preservation, and restoration of the ecological integrity of the St. Johns River watershed, monitors water quality in the river and its tributaries, and involves citizens in the decisions that affect the health of the river, and organizes regular boat trips for its members and citizens to learn more about the river and how they can participate in its management. Petitioner, Henry O. Palmer (Palmer), uses the lower St. Johns River (LSJR), including its marine portions and tributaries, for kayaking, boating, and observation of wildlife, and a substantial number of Riverkeeper's members use the LSJR, including its marine portions and tributaries, for boating, fishing, crabbing, observing birds and other wildlife, and other water-based recreational activities. Based on undisputed affidavits, Petitioners are substantially affected by algal blooms and decay and vegetation and fish kills in and along the river. These conditions can be caused by excessive nutrients along with other factors. Respondent, Department of Environmental Protection (DEP), has used the procedures in Rule 62-302.800(2) to establish a Type II site-specific alternative criterion (SSAC) for dissolved oxygen (DO) for the LSJR that is lower than the otherwise-applicable, default water quality standard in Rule 62- 302.530(30). See Fla. Admin. Code R. 62-302.800(5)(a). As a result of the SSAC, DEP revised the Total Maximum Daily Load (TMDL) for total phosphorus (TP) and total nitrogen (TN) allowed for the marine portion of the LSJR. Rule 62-302.800 sets out a procedure for establishing a SSAC. Paragraph (1) sets out the procedure for Type I SSACs, which can be established when a "water body, or portion thereof, may not meet a particular ambient water quality criterion specified for its classification, due to natural background conditions or man-induced conditions which cannot be controlled or abated" and "when an affirmative demonstration is made that an alternative criterion is more appropriate for a specified portion of waters of the state." Paragraph (2), which is challenged in this case, sets out the procedure to petition DEP for a Type II SSAC for unspecified "reasons other than those set forth above in subsection 62-302.800(1), F.A.C." Rule 62-302.800(2) provides in part: The Department shall initiate rulemaking for the [Environmental Regulation] Commission to consider approval of the proposed alternative criterion as a rule if the petitioner meets all the requirements of this subparagraph and its subparts. The petitioner must demonstrate that the proposed criterion would fully maintain and protect human health, existing uses, and the level of water quality necessary to protect human health and existing and designated beneficial uses. If the petition fails to meet any of these requirements (including the required demonstration), the Department shall issue an order denying the petition. In deciding whether to initiate rulemaking or deny the petition, the Department shall evaluate the petition and other relevant information according to the following criteria and procedures: The petition shall include all the information required under subparagraphs (1)(a)1.-4. above. In making the demonstration required by this paragraph (c), the petition shall include an assessment of aquatic toxicity, except on a showing that no such assessment is relevant to the particular criterion. The assessment of aquatic toxicity shall show that physical and chemical conditions at the site alter the toxicity or bioavailability of the compound in question and shall meet the requirements and follow the Indicator Species procedure set forth in Water Quality Standards Handbook (December 1983), a publication of the United States Environmental Protection Agency, incorporated here by reference. If, however, the Indicator Species Procedure is not applicable to the proposed site-specific alternative criterion, the petitioner may propose another generally accepted scientific method or procedure to demonstrate with equal assurance that the alternative criterion will protect the aquatic life designated use of the water body. The demonstration shall also include a risk assessment that determines the human exposure and health risk associated with the proposed alternative criterion, except on a showing that no such assessment is relevant to the particular criterion. The risk assessment shall include all factors and follow all procedures required by generally accepted scientific principles for such an assessment, such as analysis of existing water and sediment quality, potential transformation pathways, the chemical form of the compound in question, indigenous species, bioaccumulation and bioconcentration rates, and existing and potential rates of human consumption of fish, shellfish, and water. If the results of the assessments of health risks and aquatic toxicity differ, the more stringent result shall govern. The demonstration shall include information indicating that one or more assumptions used in the risk assessment on which the existing criterion is based are inappropriate at the site in question and that the proposed assumptions are more appropriate or that physical or chemical characteristics of the site alter the toxicity or bioavailability of the compound. Such a variance of assumptions, however, shall not be a ground for a proposed alternative criterion unless the assumptions characterize a factor specific to the site, such as bioaccumulation rates, rather than a generic factor, such as the cancer potency and reference dose of the compound. Man-induced pollution that can be controlled or abated shall not be deemed a ground for a proposed alternative criterion. The petition shall include all information required for the Department to complete its economic impact statement for the proposed criterion. For any alternative criterion more stringent than the existing criterion, the petition shall include an analysis of the attainability of the alternative criterion. No later than 180 days after receipt of a complete petition or after a petitioner requests processing of a petition not found to be complete, the Department shall notify the petitioner of its decision on the petition. The Department shall publish in the Florida Administrative Weekly either a notice of rulemaking for the proposed alternative criterion or a notice of the denial of the petition, as appropriate, within 30 days after notifying the petitioner of the decision. A denial of the petition shall become final within 14 days unless timely challenged under Section 120.57, F.S. The provisions of this subsection do not apply to criteria contained in Rule 62- 302.500, F.A.C., or criteria that apply to: Biological Integrity. B.O.D. Nutrients. Odor. Oils and Greases. Radioactive Substances. Substances in concentrations that injure, are chronically toxic to, or produce adverse physiological or behavioral response in humans, animals, or plants. Substances in concentrations that result in the dominance of nuisance species. Total Dissolved Gases. Any criterion or maximum concentration based on or set forth in paragraph 62-4.244(3)(b), F.A.C. Despite any failure of the Department to meet a deadline set forth in this subsection (2), the grant of an alternative criterion shall not become effective unless approved as a rule by the Commission. Nothing in this rule shall alter the rights afforded to affected persons by Chapter 120, F.S. Rule 62-302.800 cites several statutes as its specific rulemaking authority and specific provisions of law implemented, including Section 403.061, Florida Statutes, which states in pertinent part: The department shall have the power and the duty to control and prohibit pollution of air and water in accordance with the law and rules adopted and promulgated by it and, for this purpose, to: * * * Adopt rules pursuant to ss. 120.536(1) and 120.54 to implement the provisions of this act. . . . . * * * Adopt a comprehensive program for the prevention, control, and abatement of pollution of the air and waters of the state, and from time to time review and modify such program as necessary. Develop a comprehensive program for the prevention, abatement, and control of the pollution of the waters of the state. In order to effect this purpose, a grouping of the waters into classes may be made in accordance with the present and future most beneficial uses. . . . . Establish ambient air quality and water quality standards for the state as a whole or for any part thereof, and also standards for the abatement of excessive and unnecessary noise. . . . . Section 403.201, Florida Statutes, sets out a separate procedure to apply to DEP for a variance from DEP's rules and regulations, including water quality standards, "for any one of the following reasons": There is no practicable means known or available for the adequate control of the pollution involved. Compliance with the particular requirement or requirements from which a variance is sought will necessitate the taking of measures which, because of their extent or cost, must be spread over a considerable period of time. A variance granted for this reason shall prescribe a timetable for the taking of the measures required. To relieve or prevent hardship of a kind other than those provided for in paragraphs (a) and (b). Variances and renewals thereof granted under authority of this paragraph shall each be limited to a period of 24 months, except that variances granted pursuant to part II may extend for the life of the permit or certification. There was no evidence that the revised TMDLs for TP and TN allowed for the marine portion of the LSJR will lead to algal growth and algal blooms, reduced DO, fish kills, or adverse impacts to recreation on the river. To the contrary, the Type II DO SSAC for the marine portion of the LSJR has not been challenged and conclusively establishes that it will "maintain and protect human health, existing uses, and the level of water quality necessary to protect human health and existing and designated beneficial uses" and will "protect the aquatic life designated use of the water body." Fla. Admin. Code R. 62- 302.800(2)(c). See also Affidavit of Douglas J. Durbin, Ph.D., filed June 25, 2010.

CFR (1) 40 CFR 131.11(b)(1) Florida Laws (13) 120.52120.536120.54120.56120.57120.68253.03258.004258.007403.061403.201550.0251550.2415 Florida Administrative Code (7) 18-14.00318-21.00461D-6.00262-302.20062-302.80062-4.24462D-2.014
# 6
STORMY SANDQUIST, MARION C. SNIDER, ET AL. vs. RONALD JANSON AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-001309 (1983)
Division of Administrative Hearings, Florida Number: 83-001309 Latest Update: Feb. 28, 1984

Findings Of Fact On November 1, 1982, Respondent Janson filed a Joint Application for a dredge and fill permit from Respondent, Department of Environmental Regulation, and from the Department of the Army Corps of Engineers. The project described in that application involved the construction of an approximately 1,000-square- foot, pile-supported residence, landward of the mean high water line but within the landward extent of Robinson Creek in St. Johns County, Florida. The proposed project also involved the placement of approximately 35 cubic yards of fill and a 30-foot culvert within a small (approximately 4-foot), tidally- influenced roadside ditch for driveway access and parking. The original application sought permission to place part of a concrete driveway and tool shed within the landward extent of Robinson Creek. The project is to be constructed on Lot 47, J.A. Lew Subdivision. Respondent Janson owns Lot 47, as well as Lots 45 and 46, which lots are north of and adjoining Lot 47 and also adjoining Robinson Creek. The next adjoining property owner to the north is the City of St. Augustine, Florida, which presumably owns the street. The adjoining property owner to the south of Lot 47 is Virginia P. Melichar. Neither Melichar nor the City objected to the Department's approval of the dredge and fill permit application. In support of his application, Janson retained the services of a registered surveyor and civil engineer, who performed a survey on Lot 47 to determine the location of the mean high water line with reference to the proposed project. That expert determined the location of the mean high water line to be at elevation 2.4 feet. Accordingly, all work contemplated by the dredge and fill permit is upland from the mean high water line. T.J. Deuerling, an environmental specialist for Respondent, Department of Environmental Regulation, visited the project site on December 13, 1982 and on December 30, 1982 in order to prepare the Department's Biological and Water Quality Assessment. As a result of those site visits, Deuerling recommended to Respondent Janson that he modify his permit application by moving the concrete slab and tool shed from the marsh area onto the uplands. Janson did so revise his application. In spite of the name of the permit being sought by Respondent Janson, the project involves no dredging. However, the culvert and its attendant fill would be placed in the man-made roadside ditch. That ditch constitutes a very weak transitional marsh. Although the culvert will eliminate some vegetation within that ditch, the effect of the elimination will be insignificant on water quality. The pilings for the pile-supported residence will also eliminate a small area of marsh. The anticipated shading caused by the pile-supported residence may impact somewhat on the vegetation in a small area below the residence; however, due to the fact that the floor of the house will be eight feet above the ground, light will still be able to penetrate. Therefore, the vegetation below the pile-supported residence will continue to act as a filter for pollutants. Janson has mitigated the small loss in wetlands by modifying his project so as to remove the concrete slab and tool shed from the marsh area to the uplands. Due to the project's small size, no storm water impact can be expected. Additionally, no evidence was introduced to show a violation of any water quality standard as a result of the proposed project. On March 16, 1983, Respondent, Department of Environmental Regulation, executed its Intent to Issue the dredge and fill permit in accordance with the revised application and subject to the conditions that: (1) turbidity curtains be employed in the ditch during the placement of fill over the culvert to contain any turbidity generated, and (2) construction on the uplands be confined to periods of normal water level conditions. On July 5, 1983, the Department of the Army Corps of Engineers issued its Permit and Notice of Authorization. The essence of the testimony presented by the Petitioners, including that of the employees of the St. Johns River Water Management District, who testified in opposition to the proposed project, is that even though Janson's proposed project would not impact water quality in a way that was either significant or measurable (although no one even suggested any specific water quality standard that might be violated), approval of Janson's permit might set a precedent for other projects which might then have a cumulative impact in some unspecified way at some unspecified location. No evidence was offered to show that Respondent, Department of Environmental Regulation's review of permit applications is other than site specific. Further, no evidence was introduced to show any proposed project anywhere having any impact with which Janson's project could be cumulative. Petitioners Sandquist and Shuler live in the neighborhood of the proposed project, perhaps as close as two blocks away.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered dismissing with prejudice the petition filed herein as to each individual Petitioner and issuing a dredge and fill permit to Respondent Janson in accordance with his revised application. DONE and RECOMMENDED this 13th day of January, 1984, in Tallahassee, Leon County, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1984. COPIES FURNISHED: Stormy Sandquist 3 Aviles Street St. Augustine, FL 32084 Marion C. Snider Volla F. Snider 79 Fullerwood Drive St. Augustine, FL 32084 Carmen Ashton 51 East Park Avenue St. Augustine, FL 32084 Reuben D. Sitton Gail P.Sitton 35 Seminole Drive St. Augustine, FL 32084 Sandra N. Shuler 22 East Park Avenue St. Augustine, FL 32084 Patty Severt Greg Severt 1 Fern Street St. Augustine, FL 32084 Nancy Moore Paul Moore, Jr. 6 Fern Street St. Augustine, FL 32084 John D. Bailey, Jr., Esq. P.O. Box 170 St. Augustine, FL 32085-0170 Charles G. Stephens, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301

Florida Laws (2) 120.57120.66
# 7
CITY OF PARKER vs. JOHN E. BRAVO AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 86-004410 (1986)
Division of Administrative Hearings, Florida Number: 86-004410 Latest Update: Jul. 29, 1987

Findings Of Fact The Applicant, John E. Bravo, applied for a dredge and fill permit to construct a dockage facility. The proposed facility will consist of a 910 foot pier with a "T"-shaped platform structure extending perpendicular in two directions from the seaward end of the pier, all of which is designed to accommodate 56 boat slips, restricted to the use of pleasure boats only. The proposed project site is located on the southeast side of "Long Point" and would extend into the waters of East Bay, which is a tidally influenced water body in Bay County, Florida. The project site lies in Class II waters of the State. The waters involved are not approved for shellfish harvesting, however, but rather are under a shellfish harvesting prohibition imposed by the Department of Natural Resources. The portion of East Bay involved also lies within the Intracoastal Waterway. The waterway is approximately 6,000 feet wide at the site of the proposed docking facility. The water along the shoreline of the area is shallow for a considerable distance waterward. The bay bottom is characterized by profuse seagrass for approximately 500 feet waterward of mean high water. Beyond that point, the seagrass (Cuban Shoal Grass) dissipates and disappears. The first 400 feet waterward of the mean high water line at the location of the proposed dock, is shallow and not truly navigable. The water then deepens to approximately five feet at mean low water some 525 feet from the shore. This distance from the shore marks the beginning of the area where no significant amount of seagrass exists and where the boat docking slips and mooring pilings would be installed in a waterward direction down the remaining length of the proposed dock. The water depth continues to increase to approximately 20 feet at the proposed location of the end of the dock. The dock would be constructed of pilings driven into the bay bottom supporting the decking of the walkway portion and "T" portion of the dock. The "T" would be installed on the seaward end of the dock, perpendicular to the walkway portion of the dock with most of the boat slips installed and operated at that point. The length of the docking facility is dictated by the fact that the Applicant seeks to locate the boat slips in a manner so that all boats will be moored and operated well beyond existing seagrasses. In fact, the length of the dock is more than absolutely necessary to accomplish this purpose since water depth and avoidance of seagrasses could accomplished with the dock ending approximately 700 feet from the mean high water line. In an abundance of caution, however, in order to avoid the possibility of propeller dredging and prop wash damaging the bottom substrates and grasses, and since the Intracoastal Waterway is over a mile wide here, the Applicant elected to design the dock in the length and configuration proposed. Such will cause no unreasonable impediment to navigation. In this connection, the Applicant has agreed to post Coast Guard- approved safety lights on the dock which will warn boats of its presence in hours of darkness. Further, the dock does not extend far enough into the 6,000 foot wide Intracoastal Waterway to pose a hazard to barge and other boating traffic in the Waterway. Some of the Petitioner's witnesses revealed that shrimp boats pull their nets during shrimping operations closer than 900 feet to the shore line and in the vicinity of the grass beds. While the presence of the dock may alter the trawling pattern of shrimp boats and the operations of other commercial fishermen, as well as water skiing and boating by members of the public, this may in fact have a beneficial effect by promoting the public interest in preserving marine habitat and the conservation of marine resources by preventing some damage to the grass beds. Such marine grass beds are valuable nursery areas for fishes and other marine animals, the effects upon which must be considered in weighing the various statutory indicia of the public interest which must be satisfied before granting a dredge and fill permit. Further, because the dockage facility at issue would be an isolated one with no significant similar docks in the immediate vicinity, the likelihood that it would pose a navigational hazard to water skiiers, fishermen, shrimpers, and other commercial and recreational interests is rather insignificant. Water Quality The water quality issues posed by a project such as this typically involve the water quality parameters of dissolved oxygen, nutrients, bacteriological quality, turbidity, oils, greases, fuel, paint or varnish, solvents and heavy metals, as contemplated by the below-cited rules concerning general surface water quality criteria and the specific rules related to Class II surface waters. The project site is located in Class II surface waters of the State. Those Class II waters are classified by the Department of Natural Resources as "not approved" for shellfish harvesting. The zone of the Class II waters of East Bay in which shellfish harvesting is not approved extends some two miles eastward of the project site. Marinas and dockage facilities such as this one, which will accommodate fairly large boats in significant numbers, typically pose potential pollution problems involving deposition of nutrients in State waters in the form of fish carcasses and offal, garbage and human wastes. Additionally, boats can pose pollution hazards because of attendant dumping of grease, oil and fuel residues in marina waters as well as the deposition of trash in various forms such as paper and plastic items as a result of human use of the boats and the marina facility itself. Perhaps the most severe potential problem is the deposition of human fecal matter into the water as a result of the flushing of marine heads on the larger boats, which the dockage facility will accommodate in the slips as designed. The fecal coliform bacteria which emanate from the deposition of human wastes into the waters around such a dockage facility can be concentrated in oysters and other shellfish to such an extent as to cause severe illness, permanent disability or even death in humans. Consequently, in order to avoid this problem in a magnitude which would violate the water quality parameter in the rule cited below for bacteriological quality, substantial measures must be taken with a project such as this to avoid the deposition of human wastes from the dockage facility itself and from the boats using the slips. In furtherance of this end, the Applicant proposes to allow no live- aboard vessels to be occupied over night while moored at the docking facilities. Live-aboard vessels are deemed to be those with sleeping accommodations and marine heads. The Applicant also proposes to employ a full-time dock master seven days a week, eight hours a day to ensure that all dockage users are familiar with dockage rules, and who would enforce them, especially that prohibiting any discharges from vessels using or docking at the marina. The rules would be incorporated in the dockage lease agreements. The dock master would be responsible for the clean up and correction of all unauthorized discharges. In view of the potential for sewage discharges from marine heads, even with sewage pump-out facilities and the other restrictions on the use of live-aboard type boats, the additional protective measure of requiring a sewage pump-out line and pump-out equipment, including a storage tank and a means to direct sewage pumped from boats into the upland sanitary sewer system, should be imposed as an additional condition. Additionally, the restriction against over night stays aboard boats, the discharge of marine heads into the marina waters and the requirement for use of the sewage pump-out system should be publicized on large, easily legible signs at various points on the pier so that all boat slip renters or users can be on notice of the restrictions and the dock master's and the Department's enforcement of them. Additional potential sources of nutrient and bacteriological degradation of the dissolved oxygen content and bacteriological integrity of the surface waters involved can be posed by the deposition of fish carcasses and parts, as well as food wastes and other garbage in the marina waters. In order to prevent this, the Applicant has proposed to provide fish cleaning stations located on the upland and to require all fish carcasses and other related wastes to be placed in upland containers and not disposed of in the Class II waters at the dock site. Additionally, waste containers will be located along the length and perimeter of the dock facility for garbage, with regular emptying of the containers enforced by the dock master to prevent spillage. In connection with the upland fish cleaning sites to be installed, the drainage waters or waste water from fish cleaning stations should be directed into an upland disposal system so that it may be ensured that the water does not get back into the Class II waters of the bay. In addition to the above measures, pump-out facilities and equipment will be provided by the Applicant for used engine oil removed from boats and oil and water from boat bilges. These wastes, under agreed-upon conditions, would be transported by pipeline to the upland to a storage tank pending proper disposal. Trash, garbage and other refuse will be deposited in dumpsters for removal by municipal garbage disposal services. No fueling facilities or fueling of boats will be allowed. Additionally, oil spill clean up materials will be maintained on the marina site in sufficient quantities to allow clean up of the maximum spill expected from the largest boat typically using the marina pursuant to the leases for the boat slips. In order to further lessen the possibility of spills of oils, greases and fuels, the permit should be conditioned (as should the leases) upon no boat maintenance being performed at the marina site other than minor engine adjustments. In this context, an additional enforcement measure will be in the boat slip rental agreements themselves. The agreements will contain restrictive provisions requiring lessees to properly handle and dispose of fish carcasses and wastes, used engine oil, bilge water and requiring them to comply with sewage pump-out and refuse disposal conditions enumerated above. Upon completion of the facility, the dock master will manage and accomplish maintenance of the various items of equipment, such as the pump-out facility, on an eight hour a day, seven day per week basis and will enforce the restrictive provisions incorporating the above conditions in the boat slip rental agreements. Those restrictive provisions should include putting the lessees on notice that violation of any of the conditions enumerated above and in the boat slip leases will result in a breach of the lease and removal of their vessel from the marina and reporting of the violation to regulatory authorities. The various expert witnesses agreed that the proposed permit conditions enumerated above, if enforced, would adequately protect water quality as to the above parameters at issue. The Class II water quality standards will not be violated by the installation and operation of the project as proposed, provided the above conditions are strictly enforced and adhered to. Mr. Jack Taylor, the expert witness for the Petitioner, agreed that the above measures would reasonably ensure that the marina will not cause pollution and contravention of Class II water quality standards, but feared that enforcement problems would prevent such conditions from prevailing. In view of the measures enumerated above which will be undertaken by the Applicant to ensure that water quality standards are adhered to, including the liberal use of warning signs for marina customers and slip lessees, the use of a full-time dock master to enforce the conditions and including the enforcement measure of putting the conditions as restrictions in the slip rental leases, it has been shown that the enforcement will be reasonably adequate. An additional and important enforcement measure can be incorporated into this project, however, by requiring the Applicant to submit an operation and maintenance plan for the marina and requiring a monitoring program under the auspices of the Department for at least a year of operation in order to ensure that the project operates as it is proposed under the above-delineated conditions. The Department has continuing enforcement power and the monitoring program would, with regular monthly inspections, allow early detection and correction of any water quality violations, to and including the voiding of the permit and the closing of the marina operation should violations prove severe and uncorrectable. 1/ Such a monitoring program and marina operation and maintenance plan should be required as a condition to granting of the permit. 2/ Finally, it should be pointed out that the area of East Bay where the project would be built is Class II shellfish prohibited waters. The proposed project itself will not likely adversely affect shell fishing to the extent of closing additional waters if the above water quality safeguards are imposed as conditions on the permit and on the marina operation. This is especially true because the boundary line of the shellfish approved water to the east is at least two miles away, which distance incorporates a substantial mixing zone in the open waters of East Bay to sufficiently dilute pollutants which might emanate from the marina or other sources to levels such that the shellfish waters presently open will not be subject to any further closures by the Department of Natural Resources, as a result of this installation. The primary reason the shellfish waters in the immediate vicinity of the proposed project are closed to harvesting is the presence of the Military Point Sewage Treatment Plant which discharges its effluent into the waters of East Bay, such that the DNR's dye flow studies reveal that a 5.1 square mile buffer zone around that plant is necessary for closure to shellfish harvesting to ensure that the public health is not adversely affected by consumption of shellfish from the waters in that buffer area. That buffer area includes the proposed marina site. Additional significant pollution sources include fecal coliform bacteria, oils and greases and other contaminants associated with rainfall events and resultant urban runoff from the City of Parker and surrounding areas, including septic tank leachate and petroleum residues. These influences also currently add to the reasons why shellfish harvesting is precluded in the area of the proposed facility. It was not demonstrated that the addition of the marina and the boats operating under the above strict conditions will result in any additional closures to shellfish harvesting in surrounding, presently approved areas as a result of any water quality degradation posed by the subject project. Public Interest The public interest criteria-enumerated at Section 403.918(2)(a), Florida Statutes, which are actually at issue in this proceeding concern: (1) whether the project will adversely affect the public health, safety, welfare or property of others, (2) whether it will adversely affect conservation of fish and wildlife, including their habitats, (3) whether the project will adversely affect navigation, water flow or cause harmful erosion or shoaling, (4) whether it will adversely affect fishing or recreational values or marine productivity in its vicinity, and (5) whether the current condition and relative value of the functions of the natural area involved at the project site will be adversely affected by the proposed activity. There is no issue or dispute raised concerning the permanence of the project for purposes of criteria number 5 under this subsection, nor as to number 6, concerning historical and archaeological resources. Concerning criteria numbered 1-4 and 7, of this subsection, it has been demonstrated that the project will not likely affect the public health, safety, welfare or the property of others if constructed and operated according to the conditions delineated herein. Some members of the public testifying on behalf of the Petitioner objected to the interference they feared the dock would cause with their jogging along the shoreline and feared an impediment to their use of the area for water skiing. This is the only dock in this vicinity, however, and such interference is minor. It will be well lit in order to avoid impeding navigation or posing a danger to the public health or safety during hours of darkness in terms of the public's ability to safely operate boats in the area. There is some potential for the project adversely affecting conservation of fish and wildlife or their habitats in that, if boats are permitted to operate in the vicinity of the dock and use the dock for mooring, loading and unloading purposes, and the like, closer than 500 feet off shore, harmful propeller washing or dredging of the bottom sediments and seagrasses growing therein will result. If such erosion of the bottom and seagrass growth begins occurring, it will adversely affect and gradually destroy the area as a habitat for fish and other marine life, which is of particular importance since such Cuban Shoal Grass stands are quite beneficial as nursery areas for fish and other organisms. Thus, if boating activity were allowed unimpeded around the dock, including in the near shore area within 500 feet from the mean high water line, the resultant erosion and propeller damage to the seagrass beds in the bottom would indicate that, as to criteria 2 and 3 of the above subsection, that the project would not be in the public interest and would be contrary to the public interest. This same consideration is true with regard to the fourth criteria concerning whether the project adversely affects fishing and recreational values or marine productivity for similar reasons. If marine habitat is disrupted or destroyed in whole or in part in the vicinity of the dock due to erosion and other damage caused by boat and propeller contacts with the bottom or prop wash near the bottom, then as to this criteria, concerning marine productivity and recreational value, the project will be contrary to the public interest also. To the extent that nursery areas for fish and other valuable marine organisms are destroyed, the recreational value in terms of quality of fishing will certainly be diminished. The "current condition and relative value of functions" being performed by the area of marine habitat affected by this project must also be considered. In a like vein, this particular area constituting dense growths of seagrasses has a relatively high functional value as a marine habitat and, particularly, a nursery for marine animals. This current condition and value of the area should be accorded a fairly high status in weighing and balancing the various considerations used in determining whether the project is or is not contrary to the public interest. If the boats which are to use the marina upon its construction and operation are permitted inside the grass bed area, roughly within 500 feet of the shore, then clearly the considerations mentioned above will be the subject of adverse effects caused by the boats' operation which in turn is a direct result of the installation of this marina, the dock and the slips. In view of the reasonable likelihood of the project causing some of the adverse effects mentioned above, resulting from contact by boat propellers and boat hulls with the grass beds or erosive prop wash caused by operation of boats in water so shallow that the propellers are too near the bottom, the Applicant has agreed to a condition which will effectively remove boats from the seagrass bed area, provided it is strictly enforced. That condition would provide that boats and the slips in which they would be moored cannot be landward of 600 feet off shore of the mean high water line along the sides of the seaward extending dock. All boat slips are to be located seaward of that point. The Petitioners, however, raised a valid point that, the dock being so long, the natural tendency of boat operators would be to moor their boats along the sides of the dock as close into shore as boat operation is possible in order to more easily load and unload their boats. In order to prevent this problem from occurring, therefore, an additional condition should be imposed on the permit which would provide that the sides of the dock be enclosed by a fence out to the 600 foot mark and of such a configuration and type as to prevent boat operators from mooring boats to the sides of the dock and gaining ingress or egress from their boats on the dock shoreward of the 600 foot point mentioned above. In other words, if it is made impossible to enter or leave a boat from the dock in the area of the seagrass beds, this would substantially reduce the likelihood that the seagrass beds would be damaged by boats using the dock. Additionally, prominent signs should be posted on or in the vicinity of the dock announcing the necessity to avoid operating boats landward of the point mentioned above and the necessity of avoiding contacting the seagrass beds with boats or boat propellors. If this condition is adhered to and strictly enforced, as even Petitioner's expert witness concedes, it will prevent the chief source of adverse effects upon the public interest. An additional consideration in determining whether or not this project is contrary to the public interest concerns its effect upon navigation. This has already been discussed in the above Findings of Fact. Since this would be the only dock in the immediate area, it is found that the presence of the dock, even though it extends a significant distance seaward of the shore line, will still not pose a significant impediment to navigation. Additionally, as has been pointed out above, the public interest might be served in a positive way by the installation of the dock to the extent that it might prevent shrimp boats and other fishing boats pulling nets from using the shallow seagrass area which will help prevent uprooting and other damage to the grass beds caused by the nets and associated fishing gear. Finally, it should be pointed out that to a certain extent the project will positively serve recreational values and the public welfare, in the context of balancing the various public interest considerations, because at least half the boat slips will be reserved for public use and because the addition of such a marina or docking facility will enhance the public's ability to obtain recreational value from the State waters involved in East Bay by improving marine access to those waters for fishing, boating, skiing and other purposes. In short, reasonable assurances have been provided that the project is not contrary to the public interest.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that the application of John E. Bravo for the dredge and fill permit at issue be GRANTED, provided that the terms and conditions enumerated in the above Findings of Fact are incorporated in the permit as mandatory conditions. DONE and ORDERED this 29th day of July, 1987, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of July, 1987.

Florida Laws (2) 120.57267.061
# 8
TERRI SALTIEL vs. SCHOOL BOARD OF LEON COUNTY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-002752 (1989)
Division of Administrative Hearings, Florida Number: 89-002752 Latest Update: Mar. 24, 1993

The Issue The issue for determination is whether Respondent Leon County School Board should be issued a dredge and fill permit to excavate and backfill in connection with the installation of sewage collection system pipes beneath the Alford Arm of Lake Lafayette in Leon County.

Findings Of Fact On April 13, 1989, the Board submitted a permit application to DER for the dredge and fill permit which forms the basis for this proceeding. The project represented in the dredge and fill application consisted of installation of two sewage collection system pipes beneath the Alford Arm of Lake Lafayette. Installation would be accomplished by excavating and backfilling two trenches, each approximately 50 feet long by four feet wide by two feet deep. The pipes to be installed in the trenches adjacent to Buck Lake Road are one 15-inch gravity main and one 14-inch force main. A total of 15 cubic yards of soil was proposed for excavation and replacement. The project area consisted of less than 100 square feet. The Alford Arm in the project's vicinity is a canal dredged in the 1920's and 1930's. Neither the Alford Arm nor Lake Lafayette constitute Outstanding Florida Waters (OFW), instead these water bodies are Class III Waters. On April 14, 1989, DER staff conducted an inspection of the project site, completed a permit application appraisal of the project, and issued permit no. 371633191 for the project. On the same day, the permit was withdrawn when it was discovered that the document had been signed by an unauthorized official. On April 20, 1989, DER again issued permit no. 371633191 to the Board for the project. The dredging, pipe installation, and backfilling were subsequently completed. Water Quality Since the dredging and filling could potentially produce short-term turbidity in the Alford Arm as a result of sediment entering the water, a specific condition of the permit required the placement of a row of staked hay bales downstream from the project site prior to construction and thereafter until re- vegetation of the site had occurred. By compliance with this turbidity control measure, reasonable assurance was provided by the Board that violations of state water quality standards would not result from the project construction. The project did not cause any violations of DER water quality criteria for turbidity or any other water quality criteria. Numerous technological advances and safeguards built into the sewer lines and lift stations make probability of any leakage very remote. Petitioner's concern with regard to potential for leakage from the collection system lines and the lift stations to cause water quality problems in the Alford Arm is not supported by any competent substantial evidence of record regarding statistical frequency and probability of such occurrences. Further, there is no such evidence of infirmities regarding design soundness or the functional history of the pipe used in the project. Public Interest DER evaluated the project in accordance with the criteria of Section 403.918(2), Florida Statutes, prior to issuance of the permit. Another review has now been completed approximately two years after completion of the project. The project has not and will not cause any adverse impacts on public health, safety, welfare, or property of others. Likewise, the project has not caused adverse impacts on significant historical or archaeological resources. Similarly, no adverse impacts on the conservation of fish or wildlife, including endangered or threatened species or their habitats has or will result from the project. Interestingly, woodstorks have been observed feeding in the very vicinity of the project as recently as May 28, 1991, more than two years after completion of the project. No adverse impacts have or will be visited upon navigation or flow of the water. No harmful erosion or shoaling has or will result from the project. The project has not and will not cause any adverse impacts on fishing, recreational values or marine productivity in the vicinity of the project. The impacts of this dredge and fill project were temporary. The dredged and filled area has re-vegetated with the same species, pickerelweed and smartweed. Wetland functions of the site that existed prior to the project were minimal and have been re-established. Cumulative And Secondary Impacts Cumulative impacts from similar projects were not evidenced at the final hearing. There are no projects proposed which are closely linked or causally related to the dredge and fill project. The only non-speculative secondary impact from the project was possible leakage of wastewater from the collection system lines and lift station. The probability of such leakage is very low. Particularly in view of the geographical area, engineering design and manufacture of the pipes and waste collection system, such probability is speculative and minimal or non-existent in the absence of competent substantial evidence regarding statistical frequency of such an event. The construction of the sewage collection system with which the project is associated is a result of growth in the geographic area. While the project has not been established to induce growth in the area, such development would not affect Lake Lafayette since the collection system currently installed has a 400 gallon per minute capability, or the ability to serve 400 residential connections. Prior to issuance of the dredge and fill permit, 800 existing residential lots were platted along Buck Lake Road within two miles east and two miles west of the project site. Since the system could be upgraded to accommodate 1600 residential units, the potential increase that could result from the project in any event is an additional 800 residential units. If these additional residences are built at the very high density of one per quarter acre, these lots would cover only approximately two-thirds of a square mile or less than one percent of the Lake Lafayette drainage basin of approximately 80 square miles. Such development would have no measurable impact on Lake Lafayette.

Recommendation Based on the foregoing, it is hereby recommended that a Final Order be entered approving the issuance of permit number 371633191 to the Board. RECOMMENDED this 9th day of August, 1991, in Tallahassee, Leon County, Florida. DON W.DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Fl 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of August, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-2752 The following constitutes my specific rulings, in accordance with Section 120.59, Florida Statutes, on findings of fact submitted by the parties. Petitioner's Proposed Findings. None Submitted. Respondent Board's Proposed Findings: 1.-17. Adopted in substance. Respondent Department's Proposed Findings: 1.-24. Adopted in substance. COPIES FURNISHED: Terri Saltiel 7769 Deep Wood Trail Tallahassee, FL 32311 Richard A. Lotspeich, Esq. John T. LaVia, III, Esq. P.O. Box 271 Tallahassee, FL 32302 Michael Donaldson, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esq. General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.52120.57120.68
# 9
AUDUBON SOCIETY OF SOUTHWEST FLORIDA vs. LEE COUNTY BOARD OF COUNTY COMMISSIONERS AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-002307 (1981)
Division of Administrative Hearings, Florida Number: 81-002307 Latest Update: Jul. 07, 1982

Findings Of Fact On April 2, 1981, Lee County applied to DER for a permit to construct an extension of Colonial Boulevard east to State Road 82B by dredging 4,600 cubic yards of material landward of the ordinary high water mark, and by depositing 83,000 cubic yards of fill landward of the ordinary high water mark in an area of Lee County known as the Six Mile Cypress Strand or Six Mile Cypress Slough. The permit application was made by Lee County on standard DER forms which would have been appropriate for an application under either or both Chapters 253 or 403, Florida Statutes. Additionally, Lee County tendered a permit application fee to DER sufficient to cover the cost of an application under both statutes. After review of the application, DER determined that it had no jurisdiction under Chapter 253, Florida Statutes, and refunded to Lee County that portion of the permit application fee required for a Chapter 253 permit. As indicated above, Lee County's application, on its face, reflected that no fill material or dredging was proposed waterward of the ordinary high water mark. The Six Mile Cypress Strand is a meandering swamp, approximately 44,000 acres in size, dominated by cypress trees. At periods of high water the waters of the swamp empty into Ten Mile Canal, an artificial water body which connects to Estero Bay by way of Mullock Creek, a natural stream. All water bodies involved in this proceeding are classified as Class III waters. Six Mile Cypress Strand functions as a major aquifer recharge area for the eastern central portion of Lee County. The area drained by the Strand receives approximately 54 inches of rainfall annually. The wetland vegetation and uneven contours of the Strand allow the assimilation of nutrients and reduction in turbidity and erosion which could otherwise adversely affect downstream waters. The drainage area north of the proposed project consists of approximately 5,000 acres, or 11 percent of the total drainage basin served by the Strand. The proposed roadway would cross the Strand through a corridor which contains three cypress heads, or flag ponds. These ponds generally retain water during dry periods and support a more diverse community of aquatic life than those portions of the Strand which become completely dry. At the time of final hearing in this cause, these ponds exhibited dry season characteristics and contained less than one foot of water in their deepest portions. During low water periods the Strand itself may be virtually dry except for standing water in the vicinity of cypress heads and flag ponds. Only during the rainy season, which occurs during approximately four months of the year, does the Strand contain standing water. During high water periods, however, water may flow continuously throughout the length of the Strand. During these latter periods, canoes and other such small water craft may be able to negotiate portions of the Strand. No evidence was presented, however, which would indicate that the Strand is now or has ever been utilized, or is susceptible to utilization, for commercial boat traffic. The lands in the Strand over which Lee County proposes to build the roadway were conveyed by the Trustees of the Internal Improvement Trust Fund to private ownership after having been acquired from the federal government under the Swamp and Overflow Grant Act of 1850. The Strand was not meandered in the original government survey of the area, and, in fact, the surveyor's field notes reflect that the area of the Strand was densely vegetated and crossed by several roads, including one crossing the section line in the same vicinity proposed for the Colonial Boulevard extension. The existence of this last referenced road is corroborated by biological evidence presently existing on the site, and from examinations of full infrared aerial photography of the area. It is approximately nine miles from the Strand to the nearest meander line contained in the original government survey. Further, evidence of record in this proceeding establishes that water craft may not presently be navigated from Estero Bay into the Strand because of man-made barriers, and no record evidence establishes that such navigation would have been possible at the time of Florida's admission to statehood in 1845 when the stream presumably was in its natural condition. The Department of Natural Resources was notified in accordance with DER policy, of the pendency of Lee County's application, and asserted no claim of ownership over sovereignty lands in the area of the proposed project. The design for the proposed roadway includes a system of collector and spreader swales on the upstream and downstream sides of the Strand, respectively, connected by large culverts to be located beneath the roadway. The swales and culverts are intended to minimize interruption of the Strand's hydroperiod, the natural fluctuation and flow of waters within the affected portion of the Strand. A vegetated swale system paralleling the roadway is also included in the proposed roadway design to provide treatment and nutrient uptake from storm water runoff generated from the surface of the roadway. In addition, the toe of the slope of the roadway will be replanted with native vegetation, and the edge of the fill area will be meandered to save some existing vegetation. It is anticipated that the roadway could result in runoff containing from .17 to .18 pounds per day of nitrogen, and from .01 to .07 pounds per day of phosphate. The grassy swales proposed for inclusion in the project design have the capability of assimilating from 1.8 to 3.6 pounds of these nutrients per day, thereby ensuring a significant safety factor. It can also reasonably be anticipated that the swale areas are capable of absorbing any BOD loading from the roadway surface. As a result, it can reasonably be anticipated that the construction of the project will not result in the discharge of nutrients into the Strand, and that any heavy metals will be bound in organic sediments and not result in degradation of existing water quality. Ambient water conditions in the Strand show low dissolved oxygen content together with high biochemical oxygen demand, neither of which should be exacerbated by construction of the project. No violation of water quality criteria relating to herbicides is anticipated in view of Lee County's commitment at final hearing in this cause to control vegetation by way of mowing instead of by the use of herbicides. The proposed construction will, of course, destroy aquatic vegetation in the area lying in the path or "footprint" of the roadway itself, consisting of approximately seven and one-half acres, three acres of which are predominantly cypress. However, because of the design features of the proposed roadway, including grass, collector and spreader swales and the culvert system, the anticipated impact on the hydroperiod upstream and downstream of the project, and thereby the effect on aquatic vegetation and water quality will not be significant. Construction fabric will be used to allow the road surface to be supported without demucking, thus minimizing turbidity during construction periods, although it is intended that construction be conducted during the dry season, thereby further reducing the potential for turbidity violations. Further, the detention swales which are to be equipped with French drains are designed to retain the first inch of rainfall. Culverts to be constructed on the roadway are designed to accommodate a 50-year, 24-hour storm event. The Secretary of DER issued the subject permit on August 18, 1981, without any prior notice of intent. ASSWF received notice of DER's action in the form of a complete copy of the permit on August 27, 1981. On September 2, 1981, ASSWF filed its petition requesting a formal Section 120.57(1), Florida Statutes, hearing. This petition was received by DER on September 8, 1981. ASSWF and Audubon, and the members of these organizations, use the Six Mile Cypress Strand in the vicinity of the proposed project for field trips and environmental education activities which will be impacted should the project be approved. In addition, Audubon owns property within the Strand which may also be affected by the proposed project if permitted. Intervenors, Community Council and Lehigh Acres of Florida, Inc., Ralph Marciano, Claudia Tipton and H. Mark Strong requested to be granted party status in this proceeding in support of the application. Ralph Marciano owns a business allegedly limited because of the present poor highway access to the business center of the city. Claudia Tipton owns an electrical construction business alleged to be seriously hampered because of extended transportation time in emergency trips. H. Mark Strong is a retired fire marshal and contends that paramedics are seriously hampered in transporting emergency patients to the community hospital located in Fort Myers. The Community Council of Lehigh Acres was formed to serve as a council representing the entire community of Lehigh Acres on problems and projects affecting the health, welfare, growth and prosperity of Lehigh Acres. Essentially, these intervenors assert that the general public welfare and, in some cases, their own personal business interests, will be enhanced by building the proposed roadway, thereby enhancing vehicular access to various portions of the community.

Florida Laws (3) 120.57403.087403.412
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer