Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL LOZEAU, 87-000445 (1987)
Division of Administrative Hearings, Florida Number: 87-000445 Latest Update: Sep. 17, 1987

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material hereto, Respondent was a certified pool contractor, holding license no. CP-C033753, issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board. At all times material hereto, Respondent's certified pool contractor's license qualified Artistic Pools and Spas, Inc. with the Florida Construction Industry Licensing Board. On or about May 19, 1986, Respondent, d/b/a Artistic Pools and Spas, Inc. entered into a contract with Joseph and Joyce Malinoski for the construction of a swimming pool at 31 Sea Harbour Drive, Ormond Beach, Florida for a contract price of $9,737.75. The contract required a down payment of ten per cent (10 percent) of the contract amount ($973.78) which was paid by the Malinoskis on May 19, 1986. The Malinoskis resided in Massachusetts at the time they contracted for the swimming pool with Respondent and had contracted for the construction of a home in Ormond Beach, Florida to begin upon the pool shell being in place. The Malinsokis returned to Massachusetts upon execution of the contract expecting Respondent to commence work on the pool two weeks after he was notified by the builder that the survey was completed and the benchmark in place. On or before June 18, 1986, Respondent contacted the Malinoskis by phone to advise them that the pool was under construction, that Respondent was ready to start pouring concrete, and that he needed the next two (2) installments (20 percent due on day of excavation and 35 percent due on day of concrete shell installation) in the amount of $5,355.76. On or about June 18, 1986, the Malinoskis forwarded a cashier's check in the amount of $5,355.76 made payable to Respondent with the understanding from Respondent that the pool was under construction. On or about June 25, 1986, the Malinoskis were advised by their building contractor that the pool was not under construction. On or about July 5, 1986, the Malinoskis returned to Ormond Beach and found that the pool was not under construction. Although the business phone at Artistic Pools and Spas, Inc. had been disconnected, the Malinoskis ultimately located the Respondent but were unable to resolve the problem until after a complaint had been filed. In early August, 1986, an agreement was reached with the Malinoskis, Respondent and David Larsen whereby Respondent would furnish the labor to build the pool, Larsen would pay the bills and the Malinoskis would pay the balance owed on the contract to Larsen and at end of construction Larsen would give the Malinoskis release of liens. The pool was constructed without the Malinoskis having to pay any additional money on the contract. The money used by Larsen to purchase materials above the amount paid to Larsen by the Malinoskis was repaid to Larsen by Respondent. Respondent supplied all the labor to construct the pool. The testimony of Respondent, which I find credible, was that the funds received by Respondent were frozen due to an Internal Revenue Service levy on the Respondent's business account which resulted in the IRS taking all the funds in the bank account, including the money from the Malinoskis. There was insufficient evidence to show that Respondent diverted the Malinoskis' funds or that the Respondent was unable to fulfill the terms of the contract. On or about November 15, 1985 Respondent, d/b/a Artistic Pools and Spas, Inc. contracted with John and Louise McGowan for the construction of a swimming pool and spa at 1266 Robbin Drive, Port Orange, Florida for an original contract price of $11,500. These were 2 addendums to the original contract bringing the total contract price to $13,005.75. The contract provided for the spa to be 7 feet long by 5 feet wide with a depth ranging from 18 inches to 36 inches. As constructed, the spa was 5 feet long by 5 feet wide with a depth of 44 inches. The spa was also unlevel resulting in water spilling on to the deck rather than into the spillway to the pool. The therapy jets were located too deep in the spa to allow them to function properly. The spa has never been operational. Respondent was aware of the deficiencies in the construction of the spa but failed to correct them. The deck around the pool was not properly finished in that it is uneven and rough in several locations and is pitched toward the pool rather than away from the pool. The deck also has several facial cracks (not structural) which indicate a nonuniform thickness. As contracted, the pool was to have 3 return fittings of which only 2 were installed. The contract called for the installation of a heater by the Respondent. Although the heater was installed, it was improperly placed resulting in the inspector putting a "red tag" on the heater and having the gas company disconnect it. The McGowans have paid all but $575 of the contract price but refuse to pay the balance until corrections are completed. Respondent was aware of the deficiencies in the construction of the pool but failed to correct them. The evidence is clear that Respondent failed to properly supervise the construction of the McGowans' pool and spa, thereby resulting in poor workmanship in the construction of the pool and spa.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED that the Florida Construction Industry Licensing Board (Board) enter a final order finding Respondent guilty of violating Section 489.129(1)(j) and (m), Florida Statutes and for such violation it is Recommended that the Board assess the respondent with an administrative fine of $500.00 and suspend the Respondent's pool contracting license for a period of two (2) years, stay the suspension, and place Respondent on probation for a period of two (2) years, provided the Respondent pays the administrative fine of $500.00 within sixty days of the date of the Final Order. It is further Recommended that the charges of violating Section 489.129(1)(h) and (k), Florida Statutes be DISMISSED. Respectfully submitted and entered this 17th day of September, 1987, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of September, 1987.

Florida Laws (3) 120.57489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DARELL L. TREADWAY, 81-000329 (1981)
Division of Administrative Hearings, Florida Number: 81-000329 Latest Update: Aug. 27, 1981

Findings Of Fact The Respondent, Darell L. Treadway currently holds contractor's license number RP 0027269 and serves as qualifying agent for Treadway Pools and Concrete, 415 South Palmetto Avenue, Daytona Beach, Florida. (Petitioner's Exhibit II) On June 6, 1979, Chester Webb, 1548 Culverhouse Drive, Holly Hill, Florida, entered into a contract with Almo Pools of Florida, Inc., 609 Turnbull Bay Road, New Smyrna Beach, Florida, for Almo to construct a 13' x 27' kidney shaped fiberglass pool for $4,840.00. (Petitioner's Exhibit I) A $484.00 deposit was paid to Respondent Treadway on June 21, 1979, and on June 26, 1979, a building permit for the pool was obtained by Treadway Pools. (Petitioner's Exhibits I and II) Mr. Webb paid Respondent Treadway $4,684.00 toward completion of the pool. He refused to pay the $242.00 due on completion under the terms of the contract because of numerous problems with the pool including a broken drain, malfunctioning switch box timer, leaking pipes, defective filter and debris left at the site by workmen. (Testimony of Webb; Petitioner's Exhibit III) On August 23, 1979, Clyde Pirtle, Investigator, Department of Professional Regulation discussed the Webb pool with the Respondent who was informed by Pirtle that Almo Pools of Florida, Inc. was not licensed with the Board. (Petitioner's Exhibit III) Investigator Pirtle mailed change of status forms to the Respondent to qualify Almo Pool's but the forms were never completed and returned. (Petitioner's Exhibit III) At Investigator Pirtle's request, the Respondent agreed on August 23, 1979, to correct the problems with Mr. Webb's pool but thus far has failed to do so. In addition to repairing minor problems, Mr. Webb found it necessary to replace the pool filter. (Testimony of Webb) On August 29, 1979, the Respondent Treadway acting as agent for Almo Pools of Florida, Inc. entered into a contract with Donald Bird, 227 East Burn Drive, Orange City, Florida, to construct a 14' x 36' fiberglass pool with a 47' x 32' screen enclosure for $9,425.00. (Petitioner's Exhibit IV) The Respondent was paid $5,642.00 and on September 10, 1979, began installation of a fiberglass shell. (Testimony of Bird) While installing the pool, workmen who were attempting to level its bottom and sides cracked one side of the pool. (Testimony of Bird) The Respondent agreed to repair the crack and in October, 1979, returned to the site, repaired the crack and back-filled around the pool. (Id) No other work was done on the filter system or screen enclosure. Mr. Bird spent approximately $12,500.00 to finish the construction of his pool and patio. (Id) Mr. Bird's pool still has problems including discoloring, cracking and leaking. (Id) The Respondent Treadway failed to obtain a permit for the construction of the Bird's pool from the Volusia County Building Department and, accordingly, no permit for this project was ever obtained. (Testimony of Barrett) The Respondent failed to place his state registration number on the face of his contracts with Webb and Bird. (Petitioner's Exhibits I and IV)

Recommendation Upon consideration of the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Florida Construction Industry Licensing Board enter a final order revoking the registration of Darell L. Treadway as a state registered contractor. DONE and ORDERED this 21st day of July, 1981, in Tallahassee, Florida. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of July, 1981. COPIES FURNISHED: Drucilla Bell, Esquire Assistant General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Nancy Kelley Wittenberg, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Darell L. Treadway 415 South Palmetto Avenue Apartment Number 5 Daytona Beach, Florida 32015

Florida Laws (2) 489.119489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD W. ANDREWS, 87-004395 (1987)
Division of Administrative Hearings, Florida Number: 87-004395 Latest Update: Feb. 29, 1988

Findings Of Fact At all times material hereto, Respondent has been a certified pool contractor in the state of Florida, having been issued License No. CP C029646. At all tines material hereto, Respondent has been the qualifying agent for Pools by Andrews, Inc., and the owner of that company. On August 21, 1986, George Silvers, a building inspector for the Village of Tequesta, saw people working at a pool site with no identification on the truck parked nearby. When he stopped, he discovered a crew installing- plumbing pipes for a swimming pool. When he asked for identification, Roland R. Androy identified himself as an employee of Pools by Andrews, Inc. Although "piping a pool" does not itself require specialized licensure, Silvers asked Androy if he were a licensed contractor, and Androy said that he was not. By way of further identification, Androy produced a personal card which read "Andy's Elite Pools." Silvers "red flagged" the job stopping construction and filed a complaint with the Department of Professional Regulation. Androy was an employee of Pools by Andrews, Inc., for approximately one year in 1974. He returned to Florida and again became an employee of Pools by Andrews, Inc. in February, 1985. During the remainder of that calendar year Androy drew a regular weekly salary from that company, received holiday pay, and drove a company vehicle. Taxes were deducted from his salary check, and the company provided him with health insurance. Androy was a fast worker and frequently finished piping pools early in the day at which time he was given odd jobs to perform for the company such as building shelves in the warehouse. Androy decided that he could make the same amount of money and substantially shorten his work day if he were paid on a piecework basis rather than for an eight hour work day. That way he would also be able to 'moonlight' by using his free time performing maintenance and repair work for swimming pool owners. Respondent agreed to pay Androy on the basis of piecework rather than a 40-hour work week. Since January 1, 1986, Androy appears at Pools by Andrews, Inc., at 6:00 a.m. six days a week at which time he is given a list of pools to plumb that day. All materials and equipment necessary to perform the work are supplied by the Respondent. When Androy finishes, he goes home. Every Friday he gives Respondent a list of pools that he piped that week, and Respondent pays Androy by check. Because Androy wanted to be free to leave when he finishes that day's work, he no longer drives a company truck but rather drives his own truck so he does not have to return the truck before he can go home. Under the new salary arrangement, he is paid by the job and no longer receives a regular weekly salary or holiday pay or health insurance. Further, Respondent has ceased deducting withholding tax and social security taxes from Androy's paycheck. The card which Androy gave to Inspector Silver is a card that he used prior to moving to Florida. He had new cards printed with his Florida address and telephone number. He uses them when persons ask how they can get in touch with him. Respondent had no knowledge of Androy having or using such a card. As a certified pool contractor, Respondent is aware of the requirements for licensure, that is, installation of a swimming pool must be done by a licensed contractor. However, there is no requirement for licensure for that portion of the installation known as piping a pool. Rather, that work can be performed by anyone under the supervision of a licensed contractor. Further, no separate permit is required for that "plumbing" portion of pool installation. All permits for the job in question were obtained by Pools by Andrews, Inc., pursuant to Respondent's state licensure. No other permits were necessary for the job, including the work done for Respondent by Androy. Respondent (like Androy) believes that Androy is an employee of his and not an independent contractor or a subcontractor. There is no intent on Respondent's part to evade he state licensure requirements. Respondent has had no other disciplinary actions filed against him.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that a Final Order be entered finding Respondent not guilty and dismissing the Administrative Complaint filed against him in this cause. DONE and RECOMMENDED this 29th day of February, 1988, at Tallahassee, Florida. LINDA M. RIGOT, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-4395 Petitioner's proposed findings of fact numbered 1, 2, and 4-6 have been adopted either verbatim or in substance in this Recommended Order. Petitioner's proposed finding of tact numbered 2 has been rejected as not being supported by any evidence in this cause. Petitioner's proposed finding of fact numbered 7 has been rejected as being contrary to the evidence in this cause. Respondent's proposed findings of fact numbered 1, 2, 6, 8, 9, and 12 have been adopted either verbatim or in substance in this Recommended Order. Respondent's proposed findings of fact numbered 3, 7, and 10 have been rejected as being irrelevant to the issues under consideration herein. Respondent's proposed findings of fact numbered 4, 5, and 11 have been rejected as not constituting findings of fact but rather as constituting argument of counsel or conclusions of law. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Edward W. Andrews 8300 Resource Drive Riviera Beach, Florida 33404 William O'Neil, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (2) 120.57489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. NORMAN RIVERS, 77-000474 (1977)
Division of Administrative Hearings, Florida Number: 77-000474 Latest Update: Nov. 09, 1977

The Issue The basic allegations of the complaint having been proven or admitted, the sole question at hearing was one of mitigation.

Findings Of Fact Rivers is a licensed general and a licensed pool contractor. All the complaints against Rivers arose in relationship to his pool contracting activities. Rivers did begin construction of two pools in Levy County without first obtaining a building permit as required by the Levy County Building Code, a certified copy of which was identified by the Levy County Building official. Rivers paid a late fee in both instances. Although in one instance all inspections were made, in the second instance no inspections were possible because construction was essentially complete when the construction was discovered by the Levy County Building official. Rivers did fail to pay materialmen on two pools although he received payment in full for the jobs. His failure resulted in materialmen's liens being placed on the property, although Rivers provided each owner a written statement that all bills had been paid. Rivers admitted that he had not paid the materialmen because he lacked funds to do so. His contract with both parties for construction of a specified pool contained a provision stating that he would provide them an affidavit that all labor and material had been paid prior to receipt of final payment on the contract.

Recommendation Based upon the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Residential Pool Contractor's License and General Contractor's License of Norman Rivers be suspended for a minimum of ninety (90) days and that thereafter be reinstated upon his satisfying the Board of his ability to meet his financial obligations. DONE and ORDERED this 15th day of September, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488 9675 COPIES FURNISHED: Mr. J.K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 Mr. Norman Rivers 1710 South East 19th Street Ocala, Florida 32670

# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD G. BATTER, D/B/A TROPICANA POOLS, INC., 79-001938 (1979)
Division of Administrative Hearings, Florida Number: 79-001938 Latest Update: Apr. 30, 1980

The Issue The issues posed for decision herein are whether or not the certified pool contractor's license issued to Respondents Licensee, Edward G. Batter, should be revoked or suspended or the Licensee's right to practice thereunder should be withdrawn based on conduct which will be set forth hereinafter in detail as set out in the Administrative Complaint filed herein on August 23, 1979.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Edward G. Batter, d/b/a Tropicana Pools, Inc., (Respondent or Licensee) is a certified pool contractor who holds license No. CPC 012906. Respondent was first licensed on July 28, 1978, as qualifier of Tropicana Pools, Inc., which license was temporarily suspended in June, 1979, and remains in an invalid status to this date. By its Administrative Complaint, Petitioner's Executive Director took action to revoke or otherwise suspend the Respondent's rights to practice pursuant to his referenced license. As a licensed pool contractor, Respondent is subject to the Board's rules and regulations. (See Petitioner's Composite Exhibit 1.) A special meeting of the Board of Adjustment, Appeals and Examiners for general building contractors for Hillsborough County was held on Thursday, July 19, 1979, for the purpose of hearing certain allegations concerning the demise of Tropicana pools, Inc. Jerry Taylor, Petitioner's field investigator, presented the Hillsborough County Board with the results of an investigation of Respondent and presented several cases wherein funds were diverted after being collected for a specific contract to other projects or for other purposes and that projects for which funds had been collected had either been left unstarted or abandoned at the time Tropicana Pools, Inc., ceased doing business. At that meeting, the Respondent's construction activities were suspended by the Board until restitution or settlement was made and verified by affected parties. The temporary suspension by Hillsborough County became final during August of 1979. (Petitioner's Exhibits 2 and 3.) Howard Shaw, Director of Building and Zoning for the City of Tampa, appeared and testified to substantiate the disciplinary action taken against the Respondent by Hillsborough County during the summer of 1979. On June 7, 1979, Mr. and Mrs. James R. Stanton entered into a contract with Respondent to have a pool constructed for a price of $8,182.00. Respondent was paid a 10 percent deposit to commence construction of the Stantons' pool. Respondent absconded with the deposit and never notified the Stantons that their pool would not be built nor did Respondent return their deposit. (See Petitioner's Exhibits 4 and 5.) On April 19, 1979, Mr. and Mrs. Theodore Hillary entered into a contract for the construction of a swimming pool for a contract price of $8,130.00. Approximately $5,690.00 or approximately 70 percent of the contract sum was paid on June 18, 1979, and the work ceased on the Hillary project at a completion stage of approximately 40 percent. Respondent abandoned the Hillary project on approximately June 5, 1979. The Hillarys completed their pool at a price of approximately $5,000.00 over and above the contracted price. (Petitioner's Composite Exhibit 6.) On April 30, 1979, Mr. and Mrs. Leon Tope entered into a contract for the construction of a swimming pool at their residence for the contract price of $8,050.00. On June 18, 1979, the Topes had tendered to Respondent approximately 70 percent of the contract cost while the Respondent abandoned the construction of the Topes' pool after approximately 40 percent of the work was complete. Respondent abandoned the project on June 18, 1979, and the Topes completed the construction of their pool at a price of approximately $2,000.00 by engaging the services of other contractors in the area. (See Petitioner's Exhibits 7, 8, 9, 10, and the testimony of Jim Moran.) Jerry Taylor, Petitioner's field investigator, attended the probable cause hearing during August of 1979 in which the Hillsborough County Board of Examiners suspended the pool license of Respondent. Investigator Taylor briefed the Hillsborough County Board respecting the results of the investigation conducted by Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Respondent's pool contractor's license No. CPC 012906 be REVOKED. ENTERED this 10th day of March, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings 101 Collins Building Tallahassee, Florida 32301 (904) 488-9675

Florida Laws (1) 120.57
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs WILMON RAY STEVENSON, 90-001637 (1990)
Division of Administrative Hearings, Florida Filed:Inverness, Florida Mar. 15, 1990 Number: 90-001637 Latest Update: Oct. 24, 1990

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are made: At all times material to this proceeding, Respondent Wilmon Ray Stevenson was licensed as a registered building contractor in the state of Florida, holding license numbers RB 0035005 and RB A035005. License number RB 0035005 was issued on an active status qualifying an Individual in March 1987 and is still in effect. License number RB 0035005 replaced license number RR 0035005 issued in December, 1980. License number RB A035005 was issued on an active status qualifying Yankee Construction, Inc. d/b/a Olympic Homes of Citrus County (Olympic) in June 1987 and replacing license number RR A035005 issued in August 1981. In October, 1988 Respondent submitted a change of status application which was not acted upon by Petitioner until February, 1989 when it was deleted. However, Petitioner's file (Petitioner's Exhibit 1, page 2) indicates the license was in effect only until October, 1988. The Marion County Building Department was advised of this status change in September, 1988. Findings As To Case No. 90-1637 On April 16, 1988, Frank and Margaret Orkwis entered into a contract with Olympic to construct a home for $37,900 which was later modified, increasing the contract price to $39,363.00. On July 26, 1988 a permit for the Orkwis job was obtained from the Marion County Building Department in accordance with the Respondent's letter dated January 25, 1985 authorizing certain individuals to "pull" permits on his license. There was a total of $27,583.20 paid to Olympic on the Orkwis contract which included $27,483.20 paid by draw schedules and $100.00 as a down payment. Olympic stopped work on the Orkwis home sometime around November 27, 1988 and failed to complete the work under the contract. Olympic gave no notice to Orkwis that it intended to terminate the work on the Orkwis job. In fact, Olympic kept putting Mrs. Orkwis off about completing the job until sometime in late January, 1989 or early February, 1989 when she decided to get a permit and complete construction. Olympic terminated the Orkwis job without just cause. The following liens were recorded against the Orkwis property for the failure of Olympic to timely pay for materials and labor furnished to Olympic for the Orkwis's job in accordance with Orkwis contract: (a) Florida A/C Sales and Services, Inc., filed December 13, 1988 and; (b) Florida Forest Products, Inc. filed December 15, 1988. The labor and materials had been furnished between October 24, 1988 and November 22, 1988. Olympic was contacted by Mrs. Orkwis concerning the liens, with no response. However there was insufficient evidence to establish that the liens had not been removed from the property, by payment or bond, within 30 days after the date of such liens. Sometime in early 1989, Mrs. Orkwis obtained a permit and she and her husband completed the home. Although Mr. Orkwis had obtained an estimate of $27,050.00 from a contractor to complete the home, she and her husband invested 466.5 hours of their time and $10,340.00 for materials to complete the home. In addition to the material, a reasonable amount for labor to complete the home would be $10,000.00. Findings As To Case No. 90-1889 John J. and Josephine Grillo and Madeline Chapman entered into a contract with Olympic for construction of a home on June 11, 1987. A permit was obtained for the Grillo/Chapman home under Respondent's license. The Grillo/Chapman home was completed and a certificate of occupancy issued January 13, 1989. Olympic was paid in full under the contract. Before the expiration of the one-year warranty under the contract, Olympic was advised of certain problems with the construction which Olympic attempted to correct. It is unclear whether the problems were satisfactorily corrected by Olympic but it appears that the only complaint not resolved was a water stain on the carpet that was the result of water seeping in under a door. Respondent was not aware of these problems until after the expiration of the one-year warranty and upon learning of the problems, commented that he was not obligated since the warranty had expired. There was insufficient evidence to establish that the problems were not corrected in accordance with contract. Findings As To Case No. 90-1890 Veronica McPherson entered into a contract with Olympic on March 1, 1989 to construct a home for the contract price of $36,450.00 which was later modified increasing the contract price to $37,775.00. All permits were obtained under the Respondent's license pursuant to a letter dated January 15, 1985 authorizing certain individuals to "pull" permits under Respondent's license. McPherson paid $26,442.50 to Olympic pursuant to a draw schedule in the contract as the home was being constructed. Additionally, McPherson paid a $100.00 down payment. All work performed by Olympic pursuant to the McPherson contract was prior to November 22, 1988. The exact date of termination of work is uncertain. Olympic notified McPherson that it had terminated work and would not complete construction of the home. The exact date of this notification is uncertain. There is no evidence that notice was not given within 90 after termination of work. Olympic terminated work without just cause. McPherson paid a roofing contractor $998.00 to complete the roof on her unfinished home in order to protect the interior. McPherson was financially unable to complete construction of the home. A reasonable estimate to complete construction of the McPherson home at the time work ceased would be $20,000.00. On December 15, 1988 Florida Forest Products, Inc. recorded a lien on December 15, 1988 against the McPherson property for building materials furnished to the McPherson job on order of Olympic on October 24, 1988 for construction of the home pursuant to the McPherson contract in the amount of $1,450.08. There was insufficient evidence to establish that this lien had not been removed from the McPherson property, by payment or bond, within 30 days after the date of such lien. There were three other claims of liens for labor and materials furnished to the McPherson job on order of Olympic between October 19, 1988 and December 2, 1988 for construction for the home pursuant to the McPherson contract as follows: (a) Florida A/C Sales and Services, Inc. dated December 8, 1988 for $1,059.00; (b) Masons Concrete of Crystal River dated December 14, 1988 for $354.97 and (c) Panning Lumber Company, a Division of Wheeler Consolidated, Inc. for $2,284.13. There is no evidence that any of the above liens were ever recorded against the McPherson property. Likewise, there is no evidence to establish that these liens had not been removed from the McPherson property, by payment or bond, within 30 days after the date of such lien, if in fact they were recorded. General Findings Respondent was advised by Larry Vitt in February, 1988 that Olympic was having financial problems. Respondent never supervised the financial aspects of Olympic. Respondent did not participate in the contract process or supervision of the construction of homes contracted to be built by Olympic. More specifically, he did not participate in the contract process or the supervision of the construction of the Orkwis, McPherson or Grillo/Chapman homes. Respondent's main purpose in being involved with Olympic was to use his license to qualify Olympic and to contract all of Olympic's concrete block work. In March, 1989 Respondent advised the Marion County Building Department that no one was authorized to "pull" permits under his license. However, at no time did Respondent withdraw the permits for the Orkwis and McPherson jobs that had been issued under his license. The record is clear that Respondent did not understand his relationship with Olympic nor did he understand the responsibility he incurred when he used his license to qualify Olympic. However, his inexperience or ignorance in this regard does not relieve him of his responsibility to those whose homes were built or not completely built pursuant to a permit issued under his license.

Recommendation Having considered the foregoing Findings of Facts and Conclusions of Law, the evidence of record, the demeanor of the witnesses and the disciplinary guidelines set out in Chapter 21E-17, Florida Administrative Code, it is RECOMMENDED: That the Board enter a final order finding Respondent guilty of violating Section 489.129(1)(k) and (m), Florida Statutes, and for such violations it is Recommended that the Board assess the Respondent with an administrative fine of $2,500.00. It is further Recommended that Counts I and II for the Administrative Complaint in Case Nos. 90-1637, 90-1889, and 90-1890 be Dismissed. DONE and ORDERED this 24th day of October, 1990, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of October, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 90-1637 The following constitute my specific rulings pursuant to Section 120.59(20, Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings of Proposed Findings of Fact Submitted by the Petitioner 1. Covered in Conclusions of Law. 2.-8. Adopted in Findings of Fact 1, 2, and 3. 4.-6. Adopted in Findings of Fact 15, 16, and 17, respectively. 7. Adopted in Findings of Fact 19 and 20, but modified. 8.-12. Adopted in Findings of Fact 18, 4, 5, 6, and 8, respectively. 13.-14. Adopted in Findings of Fact 9 and 10, respectively, but modified. Adopted in Findings of Fact 21 through 25. Restatement of testimony; not stated as a Finding of Fact but see Findings of Fact 10 and 14. Adopted in Findings of Fact 13 through 15. Adopted in Findings of Fact 16, but modified. Rulings of Proposed Findings of Fact Submitted by Respondent 1. Covered in Preliminary Statement. 2.-8. Adopted in Findings of Fact 1, 2, 3, 3, 15, 15, and 16, respectively. 9. Adopted in Findings of Fact 19 and 20. 10.-11. Adopted in Findings of Fact 18 but modified. Adopted in Finding of Fact 4. Adopted in Findings of Fact 4 and 6. Adopted in Finding of Fact 5. Adopted in Findings of Fact 8 and 9. 16.-20. Adopted in Findings of Fact 7, 7, 11, 13 and 14, respectively, but modified. Not material. Adopted in Finding of Fact 3, but modified. Not material. Copies furnished to: Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth E. Easley, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 G. W. Harrell, Esquire Department of Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Fred A. Ohlinger, Esquire P.O. Box 1007 Beverly Hills, FL 32665

Florida Laws (4) 120.57489.105489.129583.20
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES J. HASTINGS, 87-005328 (1987)
Division of Administrative Hearings, Florida Number: 87-005328 Latest Update: Mar. 18, 1988

Findings Of Fact Petitioner is the Department of Professional Regulation. Respondent is James J. Hastings, the holder, at all times pertinent to these proceedings, of general contractor license number CG C009847. He is also the qualifying agent for Hastings Construction Co., Inc. James and Susan Cesiro, owners of a residence in Palm Bay, Florida, entered into a contract on June 13, 1985, with Mike Boyer, proprietor of a business known as American Fiberglass Pools, to furnish and install a swimming pool. The total contract price was $8500. The owners gave Boyer a $1,500 check at the time the contract was executed. On July 9, 1985, Boyer's employee obtained a second check from the owners for an additional $1,500 allegedly to complete the $3,000 required down payment. Unfortunately, the employee persuaded the owners to make this check payable to the employee personally. The employee subsequently disappeared after cashing the check. This complication resulted in some delay in the initiation of construction activities. On August 12, 1985, the owners were informed by Boyer that a contractor had been retained to install the fiberglass pool. On August 28, 1985, Respondent obtained a building permit from the City of Palm Bay authorizing the pool construction. The permit identified Respondent's company, Hastings Construction Co., Inc., as the contractor. The owners issued a check in the amount of $2,500 on September 6, 1985. Delivery of the check was made to Boyer, but was made payable to Respondent. In view of their past experience with furnishing a check payable to a party other than Boyer or his company, the owners obtained a receipt for the check from Boyer. The owners gave another check in the amount of $500 to Boyer on September 9, 1985. This check was also made payable to Respondent. Again, a receipt was obtained from Boyer by the owners. On September 23, 1985, Respondent personally received another check from the owners in the amount of $2,500. In September, 1985, after receipt of funds from the owners, Respondent and Boyer proceeded with the pool installation. While Boyer was present at the site more than Respondent, the Respondent was present every day at periodic intervals. The owners had the impression that Respondent was new at the installation of this type of pool. Boyer seemed to be more in charge of the construction and Respondent appeared to defer to him on questions asked by the owners during the installation process. This impression was confirmed at hearing by Respondent's admission that this was his first experience with this kind of pool. He had never "lifted pools over houses" and viewed the entire job as a "learning experience." Because of the tutorial nature of the situation, Respondent said he didn't enter into a formal contract with the owners. In May 1986, cracks appeared in the bottom of a portion of the pool. Respondent took the position that the pool should be repaired by Boyer under terms of the owners agreement with that individual. Respondent never prepared or accepted an assignment of the contract made by Boyer with the owners. Respondent is not an officer or employee of Boyer's business. Respondent is not a qualifying agent for Boyer or American Fiberglass Pools and those names do not appear on his license. The owners were never apprised that Respondent was "their" contractor. Respondent's testimony that a letter was sent from him to the owners on August 30, 1985, informing them of this fact is not credited in view of the Respondent's candor and demeanor while testifying on this point, the fact that he had obtained the building permit on August 28, 1985, and the owners denial that such letter was ever received. Respondent's credibility on this point was further undermined at one point in the hearing when he stated he was given this job by Boyer. Mike Boyer is not, and has never been, licensed by the Florida Construction Industry Licensing Board in accordance with Chapter 489, Florida Statutes. Respondent was aware that Boyer was not a licensed contractor. Respondent was previously disciplined by the Florida Construction Industry Licensing Board in Petitioner's case numbers 430077 and 50057, on or about October 29, 1984 and February 4, 1985, respectively. Discipline in the form of a $250 fine was imposed in the former case for Respondent's failure to qualify a company through which he was doing business and for deceptive representations in the practice of contracting. The latter disciplinary action resulted in the imposition of a $250 fine upon Respondent or suspension of his license for 60 days due to aiding and abetting an unlicensed individual and failing to qualify a business with the Board.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered suspending Respondent's licensure to practice contracting for one year and assessing an administrative fine in the amount of $2000. DONE AND RECOMMENDED this 18th day of March, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of March, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5328 The following constitutes my specific rulings on findings of fact submitted by the Petitioner. Included in finding number 2. Included in findings numbered 3 and 15. The last sentence is rejected as noncorroborative hearsay. Included in part in finding number 4. Included in part in finding number 5. Included in finding number 6. Included in findings numbered 7, 8, and 9. Included in finding number 10. Included in finding number 12. Included in finding number 13. Included in finding number 16. The Respondent submitted a document entitled Proposed Findings of Fact. The document consists of five unnumbered paragraphs in the nature of a closing argument as opposed to proposed findings of specific facts. This document of the Respondent has been reviewed by the Hearing Officer and numbers 1-5 applied to the paragraphs therein. Rulings on those paragraphs are as follows: Rejected as unnecessary. Rejected as unnecessary with the exception of the proffered August 30, 1985 letter. In this regard see finding number 14. Rejected as not supported by the evidence. Rejected as a conclusion of law not supported by the evidence. Rejected as unnecessary. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mr. James J. Hastings 836 19th Place Vero Beach, Florida 32962 William O'Neil Department of Professional Regulation General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seeley, Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (3) 120.57489.119489.129
# 9
FLORIDA BOARD OF PROFESSIONAL ENGINEERS vs THOMAS PLOTTS, P.E., 12-002523PL (2012)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Jul. 24, 2012 Number: 12-002523PL Latest Update: Dec. 25, 2024
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer