Findings Of Fact In June 1984, Clark Vargas applied for a permit with the Department of Environmental Regulation for activities in the waters of the state. The application stated that the proposed activity was to construct a soil road 700 feet long and constructed of 2,000 cubic yards of fill to be deposited landward of the mean high water line. The roadway proposed was to have Geotextile Fabric placed over it, and would have fifteen inch culverts for cross flow. The purpose of the road was to allow 8 property owners to have automobile access to their lots. Attached to the application was a copy of a larger engineering drawing of the project, reduced to letter size paper. The larger drawing C in evidence as Responder's Exhibit 1, and the original application is in evidence as Respondent's Exhibit 2. The drawing depicts the construction that is proposed, and in the notes states that the mean high water line is 1.1 feet above mean sea level. The drawing (Respondent's Exhibit 2) shows a number of elevation readings along the road. The elevation readings on the land upon which approximately one half of the road is to be located, the southerly portion closest to Julington Creek, and adjacent to lots 19 through 26, are all below the elevation of mean high water. The data as to the mean high water elevation for the note on the drawing was obtained by Mr. Vargas from the Corps of Engineers. The elevations on the road were the elevations measured by a survey caused to be conducted by Mr. Vargas starting from a U.S.G.S. benchmark three quarters of a mile away. The survey was conducted by a registered land surveyor. Mr. Vargas stated that the survey was not meant to be a survey to establish mean high water, and that it was intended to determine a price and plan for construction. In Mr. Vargas's professional opinion, the survey was not adequate to establish the mean high water line. Timothy J. Deuerling, an Environmental Supervisor I for the Northeast District, visited the site of the project in the summer of 1984. He saw water throughout the area. He developed the initial opinion that the project was landward of the mean high water line. When he returned to the office, he looked at the small attached drawing and decided that the project appeared to be mostly landward of the mean high water line. The elevations are very unclear on the reduced size version attached to the application. Mr. Deuerling's statement as to the mean high water line is contained in Respondent's Exhibit 4. It is the finding of the Hearing Officer that the drawing was so small and the elevations so unclear that Mr. Deuerling's opinion as to the mean high water line in Exhibit 4 is not reliable, and is rejected. Jeremy G. Tyler, Environmental Supervisor of the Dredge and Fill Section, North East District, said that the conclusions contained in the Intent to Deny and Final Order of Denial, Respondent's Exhibits 7 and 6, that one-third of the fill was to be placed waterward of the mean high water line, was based upon the data provided to DER by Mr. Vargas, Respondent's Exhibit 2. Mr. Tyler said that it is very hard to determine mean high water line by site inspection, and that he credited the survey as better evidence. It is she finding of the Hearing Officer that the location of the mean high water line has not been established by the evidence. This finding is not based upon the testimony of Mr. Vargas, however. Mr. Vargas did not present any evidence that the standard for mean high water, which was obtained from the Corps of Engineers, was inaccurate, and he did not present any evidence that the survey elevations on the drawing were inaccurate. There is good reason to believe that the proposed road in this case may be, at least with respect to the one half from lots 19 through 26, waterward of the mean high water line. The evidence shows there is an elevated ridge along the edge of the canal, that this ridge was caused by deposit of dredged material when the canal was dredged in the 1950's or 1960's, and that the ridge has eroded in places, and the water from the canal and Julington Creek floods much of the area from time to time through low places in the ridge. The engineering drawing, however, runs a series of elevation readings across only two places on the ridge, and in both cases there is at least one reading above mean high water level. Further, the only reading at a spot directly on the open water is at the southerly end of the proposed road, and it also is above mean high water. It is possible, therefore, that although portions of the road are below mean high water elevation, these portions may be completely surrounded by higher ground. It is also possible that the several low spots on the canal ridge bring the mean high water line to the road itself. On this record, it is not possible to conclude where the mean high water line is. The site of the proposed road and surrounding lots are located in a hardwood swamp associated with Julington Creek in Duval County. The land upon which the road would be built is heavily wooded. Julington Creek is Class III waters of the state. The land upon which the road is to be built is the landward extent of the waters of the state. All of the Petitioners stipulated at the hearing that the Department of Environmental Regulation has jurisdiction to require a permit for fill pursuant to Chapter 403, Florida Statutes. The proposed project would result in the placement of silica fill upon a strip of wetlands described above measuring 25' by 702.5', which is 17,562.5 square feet, plus four driveway pads to lots measuring 25' by 30', for an additional 3900 square feet, for a total of 20,562.5 square feet, which is 0.47 of an acre. (An acre is 43,560 square feet.) The sand of the roadway and driveway pads will not pollute the waters of the state. The sand of the road will not increase biological oxygen demand or nutrients. During construction, turbidity could be increased if high waters are experienced and the area is not properly stabilized, but turbidity could be monitored and controlled. The materials of the roadway further will not depress the oxygen levels in Julington Creek. The project originally proposed that seed and fertilizer be used to stabilize the banks of the road, and fertilizer would contribute to nutrients in the waters of the state, but Petitioners at the hearing gave reasonable assurances that seeding could be accomplished without fertilizer by using burlap and seed. The roadway itself will also not generate unlawful bacteria that could make its way to the waters of the state. The road will disturb the biological integrity of the organisms living in the soil beneath the roadway and driveway pads. The proposed project will permanently destroy 0.47 of an acre of the wetlands associated with Julington Creek. These and adjacent wetlands function as a natural kidney, cleansing the water of pollutants, in a continuous cycle. Wetlands contain soil and living organisms that, in balance, filter out pollutants, assimilate nutrients, and provide habitat for organisms. The silica road proposed by Petitioners will not perform these functions. Petitioners presented no evidence to rebut these findings, except to argue that the loss of wetland was insignificant and to argue that wetlands, at times, will also cause pollution. Petitioners gave no other reasonable assurances that the long-term effects of the road would not degrade water quality. The exchange of water, which results in the natural filtration and cleansing described above, occurs from waters coming from the uplands, from the wetlands, and from open waters such as Julington Creek. Julington Creek is tidal, and the testimony indicated that with significant regularity the wetlands associated with this proposed road were inundated with water. In a natural state, wetlands will experience dry conditions. During such periods, which are natural and cyclical, water will drain from the swamp and there can be a natural depression of oxygen levels in the open waters, increasing suspended solids. While these facts are true, Petitioners did not present evidence to show with particularity whether this had occurred or to what extent this had occurred with respect to the wetland area where the road is to be located, and did not show with particularity how removal of these wetlands by constructing this road would prevent natural degradation of the water in the future. Moreover, whether or not the natural filtration system of a wetland becomes less efficient due to natural cycles is not relevant in this case. Petitioners here do not propose to replace nature's cyclical inefficiencies with a better, manmade system, but propose, rather, to remove a significant portion of the only filter now operating, without replacement. The entire Julington Creek drainage basis is 30 or 40 square miles. The relevance of this figure was not established, since from the map which is Respondent's Exhibit 9 it is clear that the drainage basis of Julington Creek, with its associated wetlands, serves to filter pollutants from an equally large, if not larger, upland area. Petitioners argue that removal of 0.47 acre is insignificant if the entire area is 30 to 40 square miles, but from Respondent's Exhibit 9 it is evident that much of that other part of the wetland is not available to function as a filter for the waters currently filtered by the wetlands in the vicinity of the pro- posed roadway. The proposed road is near the conjunction of Julington and Durbin Creeks, and near the place where the open waters enlarge. The wetlands of the proposed road would be expected to serve the filtration function for those open waters and the uplands immediately above the wetlands, and not some other part of the 30 or 40 square miles. The land at the headwaters of Julington Creek is now being developed for multifamily housing and industrial uses, and the whole watershed of the Creek is being developed. The waters of Julington Creek have already been stressed in a general way by this development. Petitioners Vargas, Mrs. M. E McCullough, Dr. Robert L. Barksdale, and Mr. Steve Scecere, all testified at the hearing, and own, respectively, lots 22, 21, 19, and 24. All testified that they intend to build houses on their lots, but have not yet applied for permits. Since 1977, the Department of Environmental Regulation has consistently taken the position that deposit of fill on the wetlands which are the landward extent of Julington Creek will degrade the quality of the waters of the state, and have consistently acted to prohibit such fill. See Respondent's Exhibits 8, 10, and 11. The Department further has consistently told prospective buyers of this position with regard to these wetlands. Of particular relevance to this application, in 1977 the Respondent denied a fill permit to place 2,500 cubic yards of fill on lot 20 as depicted on Respondent's Exhibit 1. This lot is now owned by Debra H. Prevatt, and is contiguous to lot 19 owned by Petitioner, Dr. Robert L. Barksdale. The fill proposed in 1977 would have eliminated 20,000 square feet of wetlands, approximately the same as the proposed project in this case. Petitioner proposes the finding that the Corps of Engineers stands ready to issue their permit pending resolution of their application by the Department of Environmental Regulation. This finding is based solely upon the testimony of Mr. Vargas as to the intentions of unnamed officials in the Corps of Engineers, and as such, is hearsay. Therefore, absent direct evidence on the point, the proposed finding is rejected. Petitioners propose a finding that the permitting process progressed "without negative feedback" until objections were raised by adjacent property owners. This finding was not supported by any evidence other than the opinion of Mr. Vargas, and will be rejected as unsupported and possibly hearsay. It is also rejected as irrelevant since there was no evidence that the Respondent denied the permit for reasons other than those provided by statute and regulation. The Petitioners have paid taxes on their property, are of the opinion that they cannot build on their land if the permit is denied, and would be willing to sell their land to the state for a reasonable amount if the permit is denied. Respondent has not placed a monetary value on the wetlands which Petitioners propose to fill. If Petitioners proposed to build the road on pilings, elevated above the wetlands so that most of the wetlands would continue to function, the application would be approved.
Recommendation It is therefore recommended that the application for a dredge and fill permit to construct the road and driveway pads as proposed by Petitioners be DENIED. DONE and ORDERED this 1st day of March, 1985, in Tallahassee, Florida. WILLIAM C. SHERRILL, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of March, 1985. COPIES FURNISHED: Clark Vargas, P.E. President C. Vargas & Associates 8596 Arlington Expressway Jacksonville, Florida 32211 M. E McCullough 9139 Warwickshire Jacksonville, Florida 32217 Steve Scecere 9058 Kentism Court Jacksonville, Florida 32217 Dr. Robert L. Barksdale 2423 Acadie Jacksonville, Florida 32205 Ross Burnaman, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinke, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact Petitioner SFWMD is a public corporation of Florida. It is charged with the responsibility of issuing permits and enforcing orders relating to surface water management within its jurisdictional boundaries. Respondents Hubschman, as trustees, have full rights of ownership in 1,280 contiguous acres located in Sections 17 and 20, Township 47 South, Range 26 East, Lee County, Florida. These lands are known as Bonita Farms I and II. They are located within the jurisdictional boundaries of SFWMD. In their pre- developed state, these lands could generally be categorized as marsh and wetlands with cypress forest and some uplands in the northern half of the project area. After deciding to develop the acreage for use as pasture and farmland for small vegetable crops, Respondents Hubschman applied for a surface water management permit from SFWMD. The purpose of the permit was to allow the construction and operation of a water management system that would serve both farms. A system was designed to drain water off both parcels through a 62-acre retention area into a natural slough system which runs water into Kehl Canal. In order to create the system, the Respondents Hubschman had the following facilities designed for the site: internal ditches, dikes, pumps, a retention area and control structures. On April 15, 1982, SFWMD issued Surface Water Management Permit No. 36- 00315-S, and Respondents Hubschman were allowed to proceed with their proposed construction plan. A modification to the permit was issued on April 14, 1983. The retention area was enlarged from 62 acres to 88 acres by relocating the perimeter dike. The outfall structure was revised in that the two pumps and the weir were to be replaced by three 18" CMP culverts that would discharge the drained water by gravity flow from the retention area through the slough into Kehl Canal. The duration of the construction phase of its permit was a three-year period, unless the construction of the permitted project discharge structure or equivalent had been completed prior to that date. After the close of the three-year period, there was a dispute between the Respondents and SFWMD as to whether the permit had expired. The controversy was resolved through a compromise agreement. An application for the reissuance of Permit No. 36-00315-S was filed on October 13, 1986. Instead of reissuing Permit No. 36-00315-S, as requested by Respondents Hubschman, SFWMD decided to issue a new permit on May 14, 1987. As part of the processing procedures, SFWMD again reviewed and approved the entire surface water management system designed to serve the 1,280 acres of land proposed by Respondents. Because the additional work proposed for Section 17, the northern section was limited at this stage of development to the selective clearing of additional upland areas to create more improved pasture, the new permit directed attention to Section 20, the southern section of the land. The new permit advised the Respondents that if they wanted to propose additional development to Section 17, they were required to seek a modification of this new permit, Surface Water Management Permit No. 36-00764-S, to include those changes. The Respondents applied for a modification of Permit No. 36-00764-S on July 30, 1987. The proposed modification sought to change the status of the development of Section 17 from improved pasture to small vegetable farmland on 639 acres. The surface water management system plan was modified to drain water in Section 17 to the reservoir on Section 20. The water would be directed via a series of lateral ditches and swales. A six foot high dike and one 27,000 GPM pump were also required. Two additional 18" CMP culverts were required at the discharge facilities to accommodate the increased outflow. The Modification of Permit No. 36-00764-S was approved and issued on June 16, 1988. The original Permit NO. 36-00764-S and its modification are similar to a contract novation because the new permits substituted new obligations between the parties for the old ones under Permit No. 36-00315-S. Based upon this approach to the situation, SFWMD allowed the construction work completed under Permit No. 36-00315-S prior to the Stop Work Order of August 27, 1986, to vest. The completion of the berm around the reservoir in Section 20, as set forth in the letter from Elizabeth D. Ross, attorney for SFWMD, on September 19, 1986, was also allowed to vest. However, if the vested matters were changed in the subsequent permits, they became revisions. The revisions take precedence over the vested matters. Otherwise, completed construction under Permit No. 36- 00764-S as modified, and post Stop Work Order construction remains in effect perpetually for the operation portion of the permit. In order to determine with certainty what was permitted when the Notice of Violation was issued on December 20, 1988, the parties would have to look to the project work actually completed on August 27, 1986, the specific construction approved by SFWMD after that date, the subsequent Surface Water Management Permit No. 36-00764-S issued May 14, 1987, and its Modification issued June 16, 1988. The substantial compliance determination issued by Richard A. Rogers, P.E., Resource Control Department dated September 24, 1987, should also be considered as authorized activity. The Notice of Violation dated December 20, 1988, was issued to Respondent Samuel Hubschman, Trustee. He was advised that recent routine inspections indicate that current on-site activity was in violation of Special Conditions 2,3,4,7,14, 17 & 23 of Permit No. 36-00764-S (issued 5/14/87) and Special Conditions 5,16 & 22 of 36-00315-S (modified 6/16/88). A meeting to resolve these issued was suggested by SFWMD. Respondent Hubschman agreed to attend the meeting through his consultants. Both parties elected to attempt resolution of the Notice of Violation controversy through negotiations in a meeting scheduled for January 5, 1989. To demonstrate their sincerity, the parties agreed not to bring attorneys to the meeting. During the meeting, the parties resolved the controversy by agreeing to the following: SFWMD would no longer consider the project to be in violation of Florida law if the Respondents submitted certain items that would cause SFWMD to issue certain permits and modify others. The Respondents would promptly file an application for a dewatering permit so that the governing board could issue the permit at its March 9, 1989 meeting. The Respondent's contractor would make no field changes in the mitigation or excavation areas without first obtaining appropriate permit modification from SFWMD. Small jockey pumps were to be installed to pump water from the internal water management system into certain cypress and/or mitigation areas for the sole purpose of establishing wetland vegetation within the areas. Respondents were to apply for a modification of Permit No. 36-00764-S, as currently modified, to allow a single phase of mining for the entire affected area. The perimeter dike was to be made structurally adequate. Respondents were to submit an alternative proposal for the disposal of cap rock within ninety days. In the meantime, the contractor could continue to bury the cap rock within the mitigation areas. Both parties demonstrated their reliance on the settlement reached in the meeting by their subsequent actions towards completing and processing the applications for permit modifications and additional permits. Although the noted violations were not cured by these actions, the parties intended to reach a cure or to mitigate for present permit violations through new permit conditions. The preliminary staff review of the Respondents' application for modification of Permit No. 36-00764-S, as currently modified, was completed by March 31, 1989. The following information was requested by SFWMD staff: Revised engineering calculations which reflect that the permitted discharge structure is five 18" CMP culverts. An explanation as to why the 6.3 acre maidencane/juncus marsh designated as a preserve area and the adjacent western preserve area were excavated and otherwise disturbed by project activities. The scrapedown methodology for the replanting of mitigation areas. The Respondents' plans for the area delineated on the plans as pine, which is currently permitted as part of a cypress preservation area. Dike certification and reservoir certification. The above-listed information was required to be returned to the SFWMD within ninety days from the date of the written request. At the close of the ninety days, the information was not received. A second request for a response within thirty days was submitted by SFWMD on August 4, 1989. In September 1989, the Respondents attempted to comply with SFWMD's second request for information. Communications continued in regard to the filed application for modification of Permit No. 36-00764-S, as currently modified, into December 1989. After the thirty days expired for the response to the second request for information dated August 4, 1989, SFWMD filed the Administrative Complaint in these proceedings. After the second request for information, a partial response was received from Respondent Hubschman's consultants. The application continues to go through the review process. It has not yet been deemed complete by SFWMD. As part of the resolution of the Notice of Violation dated December 20, 1988, SFWMD issued permit No. 36-01023-W to Respondent Hubschman for construction dewatering, excavation of an irrigation pond, and water storage at the site. The permit was issued on March 9, 1989. Special condition No. 20 of this permit requires a 200-feet setback from the cypress mitigation area and the irrigation pond being dewatered. The setback is shown on Exhibit 10 of the Bonita Farms Dewatering Application which was made part of the permit. A copy of the permit was attached to the Administrative Complaint. No evidence was submitted by SFWMD regarding alleged violations of Special condition No. 20 which were allegedly observed and documented after the permit was issued, before the filing of the Administrative Complaint Respondent Bob Cadenhead is the contractor hired by Respondents Hubschman to construct the surface water management system. There was no evidence presented to show the connection of another party, Respondent, Cadenhead & Sons Construction, to the project.
Recommendation Based upon the foregoing, it is RECOMMENDED: That Surface Water Management Permit No. 36-00315-S be deemed to have vested as to all construction activity completed under the permit which was not addressed in the subsequent permit issued by SFWMD. The completion of the berm, as set forth in Attorney Ross' September 19, 1986 letter, should also be allowed to vest. That Permit No. 36-00764-S and its later modification be ordered to supercede the prior permit in all matters specifically addressed. That the parties be held to their prior agreements to resolve pending permit violations through the permit modification process. That the alleged dewatering violation in paragraph 19 of the Administrative Complaint be dismissed for lack of evidence. That a specific deadline be set to reasonably complete pending application modifications. That all future enforcement action specifically comply with Rule 40E- 1.612, Florida Administrative Code, and remain separate from any permit or permit modification applications. That the parties create a new, active permit file with current drawings and a specific construction schedule. That the Administrative Complaint and Order filed in these proceedings be dismissed. That future agreements be reduced to writing and signed by the proper parties before they are relied upon by either party. DONE and ENTERED this 9th day of November, 1990, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of November, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 89-5737 Petitioner's Proposed Findings of Fact are addressed as follows: Rejected. Irrelevant. Accepted. See HO number 4. Accepted. See HO number 3. Accepted. Rejected. Improper summary. Accepted. See HO number 6. Rejected. Improper opinion testimony. Rejected. Irrelevant. Argumentative. Rejected. Legal argument. Accepted. See HO number 5. Rejected. Legal argument. Rejected. Contrary to fact. See HO number 15. Rejected. Contrary to fact. See HO number 15. The argument presented in this paragraph is overly punctilious. It ignores the detrimental reliance of opposing parties to the agreement. Rejected. Contrary to fact. See HO number 15 and number 16. Rejected. Legal argument and improper opinion. Rejected. Contrary to fact. See HO number 15 and number 16. Rejected. Matters presented were either not ripe for these proceedings or not proved at hearing. See HO number 16-number 20 and HO number 23. Rejected. Contrary to fact and law. Rejected. Not set forth in pleadings. Irrelevant. Rejected. Not set forth in pleadings. Irrelevant. Rejected. Not set forth in pleadings as separate from the Notice of Violation. Irrelevant. Accepted as fact, resolved by agreement. Rejected. Improper opinion testimony. Rejected. Improper opinion testimony. Rejected. Irrelevant. Rejected. Irrelevant. See HO number 15. Rejected. Irrelevant. See HO number 15. Rejected. Irrelevant. Accepted. Rejected. See HO number 15. Rejected. Cumulative. Rejected. See HO number 11-number 12. Contrary to fact. Accepted. See HO number 9. Accepted. Accepted. See HO number 16-number 20. Rejected. Matter is still pending. See HO number 16-number 20. Rejected. Resolved through agreement. See HO number 15. Rejected. Matter is still pending. See HO number 16- number 20. Rejected. Legal argument. Rejected. Not in pleadings. Irrelevant. Rejected. Irrelevant. Accepted. See HO number 21. Accepted. Accepted. Rejected. Speculative. Respondent's Proposed Findings of Fact are addressed as follows: Accepted. See HO number 13. Rejected. See HO number 23. Contrary to fact and pleadings. Accepted. See HO number 14. Accepted. See HO number 15. Accepted. See HO number 15. Accepted. See HO number 20. Accepted. Rejected. Argumentative. See HO number 20. Accepted. See HO number 4-number 7. Rejected. Contrary to fact. The permit modifica- tion specifically required replacement of a pump with 3 culverts. See HO number 5. Accepted. See HO number 5. Accepted. Rejected. Irrelevant. See HO number 7. Rejected. Irrelevant. See HO number 7. Rejected. Irrelevant. Rejected. Contrary to fact. See HO number 7 and number 11. Rejected. Contrary to fact. See HO number 11. Accepted. Accepted. Rejected. See HO number 15. Additional matters were agreed upon which were not reflected in the letter. This is an incomplete summary. Rejected. Irrelevant. Rejected. Irrelevant to these proceedings. Rejected. Contrary to fact. Accepted. Accepted. Rejected. Contrary to fact. See HO number 8 and number 9. Rejected. See HO number 8 and number 9. Contrary to fact. Accepted. Accepted. Accepted. Rejected. Contrary to fact. Accepted. See HO number 23. Rejected. Contrary to fact. Accepted. COPIES FURNISHED: John J. Fumero, Esquire Office of General Counsel South Florida Water Management District Post Office Box 24680 West Palm Beach, FL 33416-4680 Kenneth G. Oertel, Esquire OERTEL HOFFMAN FERNANDEZ & COLE, P.A. Post Office Box 6507 Tallahassee, FL 32314-6507 Russell Schropp, Esquire HENDERSON FRANKLIN STARNES & HOLT, P.A. 1715 Monroe Street Fort Myers, Florida 33902 John R. Wodraska, Executive Director South Florida Water Management District 3301 Gun Club Road Post Office Box 24680 West Palm Beach, Florida 33416-4680
Findings Of Fact Background Petitioner, David E. Musselman, is the owner of Lot 23, Block 22, Cudjoe Gardens Eighth Addition, Cudjoe Key, Monroe County, Florida. The lot measures 127 feet along its front and rear property line, 135 feet along its side property lines and, similar to adjacent lots, its rear property line abuts an artificially created waterway. Currently, most of petitioner's lot enjoys an elevation of six feet; however, from the edge of the waterway landward a distance of approximately 20 feet [to what has been referred to as the "toe of the existing slope" in these proceedings] the surface consists of exposed caprock at an elevation of approximately four inches above mean high water. It is petitioner's desire to construct a single family residence upon such lot and, incident to such construction, to erect a seawall along the edge of the waterway such that the elevation at the waterway will be increased by two feet, and to backfill from the seawall to his home. Such backfilling would require the deposition of approximately 3,540 square feet of fill within the Department's jurisdiction, which was shown to extend from the edge of the waterway to the toe of the existing slope, and would raise the elevation in such area two feet above existing grade. On December 16, 1991, petitioner filed an application with respondent, Department of Environmental Regulation (Department), for an exemption from the Department's wetland permitting requirements. If approved, such exemption would allow petitioner to construct the vertical seawall along the waterway, and backfill from the seawall to his proposed home. By notice of agency action dated February 14, 1992, the Department proposed to deny petitioner's application predicated on its conclusion that his proposal did not meet the exemption criteria established by Rule 17- 312.050(1)(g), Florida Administrative Code. Petitioner filed a timely protest to contest the Department's conclusion. The exemption Pertinent to this case, Rule 17-312.050(1)(g), Florida Administrative Code, exempts from permitting the following activities: (g) Construction of seawalls or riprap, including only that backfilling needed to level the land behind the seawalls or riprap, in artificially created waterways where such construction will not violate existing water quality standards, impede navigation or adversely affect flood control. An artificially created waterway shall be defined as a body of water that has been totally dredged or excavated and which does not overlap natural surface waters of the state. For the purpose of this exemption, artificially created waterways shall also include existing residential canal systems . . . . At hearing, the parties stipulated that the waterway which abuts the rear property line of petitioner's lot is an artificially created waterway, as well as an existing residential canal, and that the proposed project will not violate existing water quality standards, impede navigation, or adversely affect flood control. Notwithstanding, the Department contends that petitioner's application should be denied because no need has been demonstrated that would support the construction of the seawall along the edge of the waterway, as opposed to locating it further inland, and therefore the amount of backfill, with its attendant loss of wetlands, is excessive. For the reasons set forth in the conclusions of law, the Department's position is untenable as a matter of law. 1/
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department enter a final order approving petitioner's application for an exemption to construct a seawall, and to backfill from such seawall to his proposed home, as applied for. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 4th day of June 1992. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of June 1992.
Findings Of Fact At all times material, Edward G. Thompson was licensed as a real estate broker in the State of Florida, having been issued license number 0190143 in accordance with Chapter 475, Florida Statutes. (Respondent's answer, Petitioner's Exhibit #1) His place of business is Red Thompson Realty Inc., State Road 20, Post Office Box 260, Interlachen, Florida 32408. (Respondent's Answer) In July 1983, Phillip and Dorothy White from Jacksonville, Florida, contracted to purchase a lot on Mirror Lake in Putnam County for a vacation residence. Edward Thompson was the broker for the sale. He and his partner, James Meyer, owned the lot and property surrounding it and they were in the process of creating a subdivision on the lake. (tr-73, 93, Petitioner's Exhibit #4) The configuration of the White's lot, lot 3-A, Mirror Lake, is elongated and stretches from a roadway. Tapering down into the lake in a modified pie-slice shape. That is, there is less frontage on the water than along the roadway. (Petitioner's Exhibit #2, Respondent's Exhibits #3 and #4) On the day that Respondent showed the lot to the Whites, he and Mr. White paced the water frontage as close as they could get to the water, given the thick vegetation; the distance was approximately 84 feet. (tr-32, 52-53, 110) Back at the real estate office, Mr. Thompson gave the Whites a drawing of the lot prepared by Terry Short, a draftsman who did the initial design concept and layout of the subdivision. This drawing clearly indicates 84 feet of water frontage. (tr-32-33, 72-73, Petitioner's Exhibit #3) The White's relied on the fact that the property had this much frontage in deciding to purchase the lot. (tr-36,56,65) The sale to the Whites closed on August 1, 1983, at which time the White executed a Contract for Deed. (Petitioner's Exhibit #9, Respondent's Answer) Sometime in January 1985, when the Whites were clearing an area near the water, the adjacent lot owner came over to explain that they were on her property and showed them the survey markers. (tr-33, 48) The Whites hired a surveyor, Earl Wallace, who completed his survey on June 10, 1985. The Wallace survey of the White's lot shows 33 feet of water frontage at the ordinary high water line. (Petitioner's Exhibit #2) Sometime after the closing on the Whites property, the survey of the entire subdivision was completed. (tr-94) Mr. Thompson claims that it was mailed to Mr. White; Mr. White denies that he received it. (tr-33,82,113,119- 120) The survey obtained by the Whites and the subdivision survey are consistent in their depiction of the White's lot. Both indicate approximately 84 feet between the two survey markers that arc closest to the water front; they both show the water line a distance from those markers with less than 84 feet of lake frontage. (Petitioner's Exhibit #2, Respondent's Exhibits #1 and #3, Tr-24) The difference between the water frontage depicted on the drawing given to the Whites and the subsequent surveys is substantially due to a fluctuation in the Mirror Lake water level. When the adjacent lot owner bought her lot in early 1983, the concrete marker was in soggy ground, near the water. Now the water has receded considerably. (tr-104,105) The lakes in that area fluctuate widely in response to rain or drought. (tr-15,16,89,108) Because of its wedge shape, the water frontage of the White's lot increases or decreases with the level of the lake. Edward Thompson is not an engineer or surveyor and relied on Terry Short to draw an accurate depiction of the property. Short held himself out as an engineer and maintained an office in the same building as Thompson Realty. (tr-72,73) Mr. Thompson saw him designing other plats and houses and after paying him for his services, relied on his professionalism. (tr- 116, 117)
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, as well as the Hearing Officer's personal view of the subject premises, the following relevant facts are found: In April or May of 1974, William M. Lyons, as president of Central Development Company, submitted an application for a permit to construct a 20 foot wide, 172 foot long concrete bridge across sovereign land connecting Parker Island in King's Bay with a mainland lot. Both the mainland lot, known as Lot 20, Parker Haven, and Parker Island are owned by Central Development Company. The application contains specific plans for run-off control. In 1975, various studies were performed by representatives of different environmental agencies concerning the proposed project. Representatives from the respondent Department of Environmental Regulation concluded that the bridge should cause no significant direct degradation of or adverse effect upon the water quality of King's Bay. The Director of the Division of Environmental Permitting therefore recommended the issuance of a permit and water quality certification following public notice of the project. In February of 1975, the Chief of Survey and Management of the Department of Natural Resources conducted a biological and hydrographic assessment and found that "the proposed bridge construction would eliminate a limited area of vegetated bottoms but would not, in itself, significantly affect aquatic biological resources," and that "it is improbable that the proposed bridge construction . . . would have significantly adverse hydrographic effects." The Game and Fresh Water Fish Commission had no objection to the bridge itself, but did express concern over the future development of Parker Island. The petitioners herein are citizens and property owners in the area and have requested a hearing on the permit application. The Department of Environmental Regulation forwarded the petition to the Division of Administrative Hearings, and the undersigned Hearing Officer was duly designated to conduct the hearing. Upon the agreement of all parties, the hearing was consolidated with other cases involving permits for projects in the King's Bay area of Crystal River. The prime issue upon which testimony was adduced at the hearing was the effect of the proposed bridge upon navigation. The waters of King's Bay are affected by the ebb and flow of the tide. The bridge is to be approximately four and one-half feet above the mean high water level. The pass between Parker Island and the mainland Lot 20 is approximately 250 feet wide and is relatively shallow, ranging from a low of one foot to a high of approximately four and one- half feet deep, depending upon the tide. Net fishing and gigging in that area are prohibited. Power boats, air boats and small sailboats presently utilize the pass, but large sailboats would not prudently use this pass for safety reasons. Small power boats with windshields and/or covered tops would probably not be able to use the pass during high tide if the proposed bridge at a height of four and one-half feet is constructed. A mean high water survey, per se, was not conducted by or on behalf of the applicant. Rather, the applicant relied upon a bulkhead map which establishes a bulkhead line around Parker Island (Exhibit 9). This document describes mean high water as +1.2 elevation and the metes and bounds description of the bulkhead line is followed by the words "all being along the mean high water line." The King's Bay area and the springs located therein provide a winter home for manatee, an endangered species. During high tides, manatees have occasionally been observed in the pass between Parker Island and Lot 20 on the mainland. While further development and degradation of the area could affect the manatee population, the placement of the bridge itself would not affect the navigation of the manatee travelling in that area, though some would balk or be hesitant around the bridge. One of the greatest hazards to the manatee is injury or even fatality from boat propellers and collisions with fast moving power boats. A boat travelling at five miles per hour should present no problem to the manatee. Several residents owning waterfront lots on King's Bay testified that their view of the open water would be obstructed by the existence of the proposed bridge. The purpose of constructing the bridge is obviously to provide a means of access from the mainland to Parker Island. Parker Island is about five and one-half acres in size and is owned by Central Development Company. Preliminary land use plans have been developed for an environmentally oriented low density subdivision on Parker Island. The conceptual plans include the sale of eleven lots, one-third acre each, for residential purposes. Each lot owner would only be permitted to develop 5,000 square feet of the lot, with the remainder of the lot to be retained in an undisturbed state. The preliminary plans call for underground utilities, no seawalls and a centralized dock. It must be emphasized that these are preliminary or conceptual plans for development of the Island, and Central is in no way bound by said plans. On or about April 5, 1977, the Board of County Commissioners of Citrus County passed a resolution declaring that the area known as King's Bay and the islands located therein was an area of critical habitat, and that any man-made changes in the area be subject to public hearings and comply with all Citrus County ordinances, resolutions and regulations. Lot 20 on the mainland is zoned R-1AA which permits single family dwellings, municipally owned or operated parks and playgrounds, golf courses, certain temporary signs and certain conditioned accessory uses. Central Development Company has not appeared before the zoning board to seek a zoning change or exception for Lot 20. Central Development Company has submitted to the Department of Natural Resources an application for an easement for its bridge construction. This is the subject matter of Case No. 77-960, for which a separate recommended order is being entered.
Recommendation Based upon the findings of fact and conclusions of law recited above, it is recommended that the Department of Environmental Regulation issue to Central Development Corporation a permit to construct a concrete bridge between Lot 20, Parkers Haven, and Parker Island subject to the following conditions: The height of the structure above mean high water level be increased from four and one-half (4 1/2) feet to six and one-half (6 1/2) feet; and Receipt by the applicant and exhibition to the Department of Environmental Regulation of the required easement or other form of consent from the Board of Trustees of the Internal Improvement Trust Fund authorizing the proposed use of sovereignty lands, as required by Florida Statutes 253.77 (1976). Respectfully submitted and entered this 16th day of September, 1977, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Kenneth F. Hoffman, Esquire Post Office Box 1872 Tallahassee, Florida 32302 Alfred W. Clark, Esquire Assistant General Counsel Department of Environmental Regulation 2562 Executive Center Circle, E. Montgomery Building Tallahassee, Florida 32301 Baya M. Harrison, III, Esquire Post Office Box 391 Tallahassee, Florida 32302 David Gluckman, Esquire 3348 Mahan Drive Tallahassee, Florida 32303 Mr. H. A. Evertz, III Florida Power Corporation Post Office Box 14042 St. Petersburg, Florida 33733 Kent A. Zaiser, Esquire Assistant Department Attorney Department of Natural Resources Crown Building 202 Blount Street Tallahassee, Florida
Findings Of Fact On June 27, 1979, Respondent Department of Environmental Regulation's St. Johns River District office received an application from Petitioner John W. McPhail, Deland, Florida, for a permit to conduct dredge and fill activities on his property at Lake Johnson, DeLeon Springs, Florida. The application reflected that Petitioner desired to dredge 100 cubic yards of material Waterward of the lake mean high Water line and 100 cubic yards landward of the mean high water line, and then fill an adjacent cove area on his Property with the 200 cubic yards of material. (Respondent's Exhibit 1) Lake Johnson is a small privately owned lake about fifteen acres in area. There are two distinct "lobes" of the lake which are joined by a narrow band of water. Each of these lobes is approximately seven acres in area. Some four or five houses, including, Petitioner's, are located around the lake. In the early Seventies, Petitioner dredged part of his shoreline and, in the process, too much material was inadvertently removed from the present cove area and placed in the middle of the property, which left a hump of land in the middle. The shoreline now is irregular with steep ungraded banks, and the cove area is somewhat stagnant. Petitioner wishes to restore the property by dredging the "hump" created by prior filling, and return the material to its Original location by filling the cove area. This will produce an even, sloped shoreline extending some 200 feet and improve the appearance of the lakefront. It will also reduce present maintenance Problems. (Testimony of Petitioner, Vause, Petitioner's Exhibits 1-3) A field biologist in Respondent's District Dredge and Fill Permitting Section conducted an on-site inspection on August 28, 1979, and rendered a report of the inspection on October 2, 1979. He found that the dominant plant community along the banks of the shoreline consisted primarily of upland weeds and grasses such as broomsedge and bahaia grass. Additionally, primrose willow was found in that location. The vegetation along the shoreline includes maidencane and a small amount of bullrush while the open water area is predominately vegetated with water lilies. Primrose willow is a species of vegetation found in the transitional zone of a submerged land, and bullrush, maidencane, and water lily are also fresh water species of vegetation found in submerged lands, as defined in Chapter 17-4, Florida Administrative &ode. The water depth in the lake is approximately eight feet and the depth the water at the steep banks of the Petitioner's property is approximately three feet. Wetlands vegetation of the above types are conducive to the improvement of water quality by increasing dissolved oxygen levels after removal of polluting nutrients from the water. The removal of a significant amount of such vegetation may have a measurable adverse effect on water quality. Although Lake Johnson, a Class III body of water, presently has excellent Water quality, the vegetation along the shoreline has been removed to a degree of about ten to fifteen percent. The removal of fifteen to twenty percent or more of a shoreline in such a lake normally produces a measurable adverse effect on water quality. The dredging of material along a shoreline can produce short-term turbidity of the water. (Testimony of Vause, Respondent's Exhibits 2-3) Respondent's inspector found that although filling the cove would remove some beneficial aquatic and land vegetation, would most likely reestablish if proper sloping was maintained on the shoreline. He also noted in his report that the proposed project would restore approximately one-half acre of open water to the lake. He therefore interposed no objection to the filling aspect of the project, but believed that dredging should not be undertaken waterward of the ordinary high water line, and that the shoreline should be merely contoured without dredging. By letter of October 4, 1979, Respondent's district manager advised Petitioner of its intent to deny his application for permit for the reason that the proposed work would eliminate approximately .5 acres of wetland community and thereby degrade water quality in the areas of BOD, turbidity, and dissolved oxygen. (Testimony of Vause, Respondent's Exhibits 2-4)
Recommendation That Petitioner be issued the requested permit, subject to standard conditions. DONE and ENTERED this 13th day of February, 1980, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Segundo J. Fernandez Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 John W. McPhail Route 1, Box 692H Deland, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION JOHN W. MCPHAIL, Petitioner, vs. CASE NO. 79-2174 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION Respondent. /
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Respondent owns real property located in Township 2 North, Range 7 East, Section 32, in Madison County, Florida, that has surface water flowing through it and is encompassed within what is defined as "wetlands." Respondent is in control and possession of the property in question and all work on the property that is material to this proceeding is under the control or direction of the Respondent. There were access roads on the property as early as 1973 as reflected by Respondent's exhibit 2, a 1973 aerial photograph, but the width of the roads or the existence of ditches or culverts cannot be determined from the photograph. Petitioner's exhibit 2, a 1981 aerial photograph, shows the roads still in existence in 1981 but the width of the roads or existence of ditches or culverts cannot be determined from the photograph. Sometime before the Respondent purchased the property and began construction to expand the roads, ditches and culverts were in place; however, there was no evidence as to when the ditches and culverts came to be in place. A 1976 survey of the property reflects 60 foot roads which were to provide access to platted but unrecorded lots. These roads had not been constructed when Respondent purchased the property or began construction to expand the roads. The newly constructed portions of the road indicates an attempt to build the roads in accordance with the 1976 survey. The previously existing roads attempted to follow the natural contour of the land and as a result were not always straight, and only had a negligible effect on the flow or storage of surface water in regard to the property. Sometime around October 1987, Respondent began to rebuild and construct roads on the property by straightening existing curves, removing fill material from adjacent wetlands to widen and heighten the existing roadbed or construct a new roadbed, and to increase the depth and width of existing ditches or dig new ditches. The initial portion of the existing road providing access to the property from the county graded road has been substantially rebuilt with portion of the roadbed being 40 to 43 feet wide. Ditches along this portion of the roadbed have had their width increased up to 14 feet and their depth increased up to 6 and 8 feet. Other portions of the road has been expanded beyond the previously existing roadbed by increasing the width and height of the roadbed. The increased size of the ditches and the expanded roadbed has increased the interception of surface water above that already being intercepted by the previous roadbed and ditches and, as a result, there is an increased amount of surface water impounded or obstructed. The effect is that surface water is removed from Respondent's property at a faster rate than before road construction began and, as a result, sheet flow of surface water is decreased which diminishes the storage of surface water on the property. Although new culverts were installed during road construction, there was insufficient evidence to show that these new culverts were in addition to the culverts already in place or if they replaced old culverts. There was insufficient evidence to show that the new culverts allowed water to flow in a different direction or be removed from the property at a faster rate than before or if they impounded or obstructed surface water more so than before. The previously existing roads had sufficiently served an earlier timber harvest on the property and, by Respondent's own testimony, were sufficient for his ongoing hog and goat operation. The extensive rebuilding and constructing of roads in this case was neither necessary nor a customary practice for construction of farm access roads in this area. Respondent is engaged in the occupation of agriculture in that he has a bona fide hog and goat operation. However, Respondent's silviculture occupation is somewhat limited in that he is presently harvesting the timber but shows no indication of replanting or continuing the forestry operation upon completing the present harvesting operation. The extensive rebuilding and constructing of roads in this case goes beyond what is necessary or is the customary practice in the area for a hog or goat operation or forestry operation such as Respondent's and is inconsistent with this type of agriculture or silviculture occupation. Respondent has never applied for nor received a surface water management permit from the Petitioner even though the Petitioner has informed Respondent that a permit was required for the work being done on his property. The present alteration of the topography of the land by Respondent has obstructed and impounded surface water in such a fashion that the interruption of the sheet flow of surface water has been increased, causing the storage of surface water on the property to be diminished. At the present time, Respondent has been enjoined by the Circuit Court of Madison County, Florida, from any further activity on this project. However, should Respondent be allowed to complete this project, it is evident that the sole and predominant purpose would be to impound and obstruct the sheet flow of surface water and diminish the storage of surface water on the property in question.
Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore, RECOMMENDED that the Petitioner, Suwannee River Management District, enter a Final Order requiring Respondent, Norman Leonard, to: (a) remove all unauthorized fill material placed within jurisdictional wetlands and return those areas to predevelopment grades and revegetate with naturally occurring local wetlands species to prevent erosion; (b) back fill excavated swale ditches, return road beds and excavated ditches to predevelopment condition and grades and seed disturbed non-wetland areas with a 50:50 mix of bahia and rye grass and; (c) refrain from any other development until and unless a required permit is obtained for such development. Respectfully submitted and entered this 13th day of February, 1989, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 1989. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 88-1445 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner 1. Adopted in Finding of Fact 1. 2.-3. Adopted in Finding of Fact 2. 4.-7. Are unnecessary findings for this Recommended Order. Adopted in Finding of Fact 18. Adopted in Finding of Fact 19. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Subordinate to the facts actually found in this Recommended Order. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12. Rejected as conclusions of law. Adopted in Findings of Fact 3 and 4. Adopted in Finding of Fact 8. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 8. Adopted in Finding of Fact 6. Adopted in Finding of Fact 7. Adopted in Finding of Fact 6. Adopted in Finding of Fact 10. Adopted in Findings of Fact 15 and 17. 26.-29. Adopted in Finding of Fact 12. 30. Adopted in Finding of Fact 13. 31.-32. Subordinate to facts actually found in this Recommended Order. Adopted in Finding of Fact 12. Adopted in Finding of Fact 16. 35.-38. Subordinate to facts actually found in this Recommended Order. 39.-42. Rejected as not being relevant or material. Specific Rulings on Proposed Findings of Fact Submitted by Respondent 1. The first paragraph adopted in Finding of Fact 16. The balance is rejected as a conclusion of law. 2.-3. Rejected as not being relevant or material. Not a finding of fact but a statement of testimony. However, it is subordinate to facts actually found in this Recommended Order. Rejected as not supported by substantial competent evidence in the record. The more credible evidence is contrary to this finding. COPIES FURNISHED: Janice F. Baker, Esquire Post Office Box 1029 Lake City, Florida 32056-1029 Norman Leonard, Pro Se Route 2, Box 172-D Live Oak, Florida 32060 Donald O. Morgan Executive Director Suwannee River Water Management District Route 3, Box 64 Live Oak, Florida Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Findings Of Fact On June 26, 1986, the Department of Environmental Regulation (DER) issued a permit, No. 661168901, to Elizabeth R. McSheehy authorizing construction on the shore of Choctawhatchee Bay of a seawall 165 feet long and eight feet high "faced with rip-rap . . . and backfilled with 18 cubic yards of sand fill . . . in accordance with [an] attached map and drawing." Joint Exhibit No. 1. The permit application had proposed that the seawall "TIE INTO MR. HEATH['S] SEAWALL," and the attached drawing indicated a point of beginning along the seawall already protecting the lot to the east, then owned by Mr. Heath, now owned by Prentice M. Thomas. The drawing has no compass rose and does not specify the angle of either leg of the permitted seawall. The construction permit expired December 30, 1987 (well beyond the 120 days within which the application indicated it would be necessary to complete construction, once begun.) At hearing, the parties stipulated that Ms. McSheehy had erected or caused to be erected a seawall at the location permitted on or before December 30, 1987. DER does not dispute that the seawall functioned as such when built. Seawall Fails Ms. McSheehy received a letter from Mr. Thomas dated June 6, 1990 (in an envelope postmarked June 22, 1990) stating, "I recently visited my lot at Four Mile Post and regret to inform you that the seawall you installed on your property has been demolished by the winter and spring storms." Petitioner's Exhibit No. 2. The letter reported that her "lot was eroding at a rapid pace." Id. Afraid that his own lot would be affected, despite its well-maintained seawall and rip-rap he had added, Mr. Thomas "beseech[ed her]. . . to take action to arrest the erosion of [he]r shoreline." Petitioner's Exhibit No. 2. The lot west of Ms. McSheehy's has no seawall. T. 48. Its shoreline had also eroded, judging from photographs in evidence. Soon after receiving the letter, Ms. McSheehy inspected the property for the first time since the summer before. She found the piles on which the seawall had been constructed in 1986 or 1987, now standing as far as 30 feet out in the bay. Only the eastern 20 or 30 feet of the seawall remained intact. Remnants, including individual boards and wall fragments comprised of as many as four boards had washed up on the receded shoreline. When DER's James Eric Buckelew happened on the site on July 26, 1990, he concluded from the erosion that the seawall had ceased to function as such some months before. Bay waters reached 20 or 30 feet further inland, covering about a tenth of an acre landward of what remained of the seawall. Mr. Buckelew took photographs of the site. Petitioner's Exhibit No. 1. Seawall Now in Bay Before the month ended and apparently before anybody from DER communicated with Ms. McSheehy, the seawall was rebuilt in its original location. No additional fill has been placed landward of the seawall, which now has water on both sides. In various trips to the site and otherwise in responding to this turn of events, DER has expended at least $245.37. DER advised Ms. McSheehy that a permit could be issued for construction of another seawall along what seems to be the new mean high water line, but that she had acted illegally in having the seawall restored at a location now some 20 or 30 feet out in the Bay. (T. 115). After first applying for and receiving a permit to remove the existing seawall and construct a new one further landward, she took the position that restoration of the original seawall had been lawful, and these proceedings ensued.
Recommendation It is, accordingly, RECOMMENDED: That DER make final its proposed orders for corrective action, unless within a reasonable time DNR conveys or leases to respondent the property lying between the seawall and the mean high water line. DONE AND ENTERED this 24th day of February, 1993, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of February, 1993. APPENDIX TO RECOMMENDED ORDER CASE NO. 91-7281 Petitioner's proposed findings of fact numbers 2, 3, 5, 6 and 12 have been adopted, in substance, insofar as material. With regard to petitioner's proposed finding of fact number 1, the permit issued in 1986, but it is not clear that construction was accomplished in 1986. With regard to petitioner's proposed finding of fact number 4, the seawall failed sometime between the summer of 1989 and the spring of 1990. With regard to petitioner's proposed findings of fact numbers 7, 8, 9, 10 and 11, use of the word "unauthorized" renders these proposed conclusions of law. Respondent's "proposal for the ruling of the hearing officer" did not contain separately numbered proposed findings of fact. COPIES FURNISHED TO: Virginia B. Wetherell, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Richard L. Windsor, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Elizabeth R. McSheehy 516 Mooney Road Fort Walton Beach, Florida 32547
The Issue The issue is whether Petitioner is entitled to an environmental resource permit for a surface water management system and the alteration of a wetland in connection with the construction of two warehouses, paved parking and loading areas, a detention pond, and enhancement of the remainder of the existing wetland. If not otherwise entitled to the permit, an additional issue is whether Petitioner is entitled to the permit through an exemption, waiver, or variance from the standard requirements for mitigation.
Findings Of Fact Background Petitioner Carlos M. Beruff, as Trustee under Florida Land Trust No. 22 dated March 30, 1989 (Petitioner), purchased 85 acres of land in Manatee County for $1.2 million in May 1989. (All acreages are approximate.) The east boundary of the 85-acre parcel consists of about 1700 feet of frontage along U.S. Route 301. One month after the purchase, Petitioner sold 70 of the 85 acres for $1.6 million. In the intervening month, Petitioner incurred no significant expenses for development or marketing, although the development and marketing expertise of Carlos Beruff facilitated the $1.6 million sale. The 70 acres that were sold included the frontage on U.S. Route 301. The 15 acres remaining after the sale comprise two tracts of 9 and 5.88 acres. In these cases, Petitioner seeks an environmental resource permit (ERP) for activities involving the 5.88-acre parcel (Site). The 9-acre parcel occupies the northwest corner of the 85-acre parcel. The Site, which was platted in 1911, is the only noncontiguous land constituting the 85-acre parcel; it is 450 feet south of the remainder of the 85-acre parcel. The sole parcel between the Site and the remainder of the 85- acre parcel was originally owned by Lowe's and is now owned by Cheetah Technologies (Cheetah Parcel). The 5.88-acre Site is subject to a road right-of-way of 0.32 acres in favor of the Cheetah Parcel. Of the remaining 5.56 acres, 4.66 acres are wetland and 0.9 acres are upland. The 0.9 acres of upland are subject to an access easement of 0.42 acres, also in favor of the Cheetah Parcel, so the net available upland acreage is only 0.48 acres. The Cheetah Parcel occupies the northwest corner of U.S. Route 301 and Saunders Road (also known as 63rd Avenue East). The Site is immediately west and south of the Cheetah Parcel and occupies the northeast corner of Saunders Road and 24th Street East (also known as Arlin Road). The Site is about 530 feet west of the intersection of U.S. Route 301 and Saunders Road. U.S. Route 301 is a major arterial, and Saunders Road is at least a major collector road. The Site contains about 600 feet of frontage along Saunders Road and 465 feet of frontage along 24th Street East. The Site is in unincorporated Manatee County roughly midway between downtown Bradenton and downtown Sarasota. Saunders Road crosses a north-south railroad line approximately one-half mile west of the Site and Bowlees Creek about 650 feet west of the railroad track. The 9-acre parcel still owned by Petitioner is about 350 feet north-south by 1250 feet east-west. The western boundary of the 9-acre parcel runs along the east side of the railroad line. Like the other parcels involved in this case, the 9-acre parcel drains into Bowlees Creek. The Site is in an area characterized by industrial land uses, including warehouses, a junkyard, an industrial center, and a bakery. A halfway house for persons recently released from prison is located one-quarter mile to the west of the Site. The Site is zoned HM (heavy manufacturing), which is a limited, and thus valuable, zoning category in Manatee County. Respondent has issued three relatively recent surface water management permits that are relevant to these cases: a 1986 permit for the development of the Cheetah Parcel (Cheetah Permit), a 1988 permit for the widening of Saunders Road from two to four lanes (Saunders Road Permit), and a 1989 permit for the construction of a commercial park north of the Site known as 301 Park of Commerce (301 Permit). Bowlees Creek runs from north to south, emptying into Sarasota Bay across from Longboat Key. Sarasota Bay is an Outstanding Florida Water. Bowlees Creek drains a nine square-mile basin, which is about 21-25 percent developed. The Bowlees Creek basin is an open drainage basin. Due to flooding problems, Manatee County has imposed special limitations upon development within the Bowlees Creek basin. Among these limitations is that the rate of post- development runoff must be less than the rate of pre- development runoff--up to 50 percent less, according to expert witnesses for both sides (Lawrence Weber, Tr. Vol. III, pp. 118-19; and Daryl Flatt, Tr. Vol. IV, p. 230). By stipulation, the Site is at the extreme eastern end of the Bowlees Creek basin. In fact, the Site may have historically drained into Bowlees Creek and will drain into Bowlees Creek after, as described below, the northwest window is added to the surface water management system. In 1993 or 1994, Petitioner began the process of developing the Site following the sale five years earlier of the larger 70-acre parcel. Mr. Beruff has been in the development business for 20 years. His career began in 1980 when Mr. Beruff became an employee for U.S. Homes and Modern Builders; he became self-employed in 1984. Mr. Beruff has developed seven commercial and ten residential developments. Application Process Deciding to pursue warehouse development for the Site, Petitioner initiated the development process by hiring an engineer and environmental consultant. With the assistance of these consultants, Petitioner prepared its application for an ERP. By application dated October 9, 1998, and filed November 13, 1998, Petitioner requested that Respondent issue an individual ERP for the construction on the Site of a surface water management system in connection with the construction of two warehouse buildings, paved parking and loading areas, and a detention pond, as well as the enhancement of the remainder of the existing wetland (Application). The Application states that the total building, parking, and loading areas would be 58,026 square feet and that wetlands constitute 3.37 acres of the 5.88-acre Site. The site plan attached to the Application shows a "wetland preservation & enhancement" area of 1.592 acres at the north end of the Site. To the south, toward Saunders Road, are two buildings with paved parking and loading areas. On the southwest corner is a "stormwater treatment & attenuation" area. After several discussions with Respondent's staff, Petitioner modified the proposed development. In its latest revision, the footprint of the proposed development would occupy 2.834 acres of wetland, leaving 1.826 acres of wetland. On November 13, 1998, Petitioner filed a Petition for Exemption, Waiver or Variance as to Mitigation Requirements, seeking an exemption, waiver, or variance from all laws requiring offsite mitigation or additional onsite mitigation for the portion of the wetland that would be destroyed by the proposed development. Drainage At present, the Site receives runoff from a total of 27 acres. The offsite contributors of runoff are the Cheetah Parcel and a segment of Saunders Road east of 21st Street East. These locations have drained into the Site for hundreds of years. In general, drainage raises two distinct issues: water quality and water quantity. For an open drainage basin, the issue of water quantity expresses itself primarily in runoff discharge rate, although historic basin storage is also an issue. As discussed in the Conclusions of Law, the Respondent's Basis of Review identifies different storm events to which applicants must design different components of surface water management systems. For water quantity, the system may release no more than the permitted discharge rate in the design storm, which is the 25-year, 24-hour storm event. At present, the design storm would produce about eight inches of rain, although the same design storm, due to a different model or modeling assumptions, produced 9.5 inches of rain at the time of the issuance of the permit for the Cheetah Parcel. (The practical effect of this change in the calculation of the design storm is that the quantitative capacity of the surface water management system of the Cheetah Parcel is nearly 20 percent greater than would be required today.) For water quality, the system must capture the first inch of runoff (sometimes only the first half-inch of runoff, depending on the type of system and receiving waterbody). In contrast to the relatively infrequent 25-year storm, approximately 90 percent of the storms in Respondent's jurisdiction produce no more than one inch of runoff. The underlying premise is that the first inch of runoff contains nearly all of the contaminants that will be flushed from impervious surfaces. The Cheetah surface water management system features a wetland and a retention pond along the north property line of the Site. The Cheetah pond and wetland attenuate runoff before allowing it to drain south onto the Site. The Cheetah surface water management system also includes a swale running north along 24th Street East to take runoff eventually to Bowlees Creek. The Saunders Road surface water management system discharging onto the Site consists largely of an underground, offline storage and attenuation system that stores excess runoff, as compared to pre-development rates, in lateral pipes off a weir. Nothing in the record suggests that the surface water management systems authorized by the Cheetah Permit or the Saunders Road Permit fail to provide reasonable assurance that the discharged runoff is of satisfactory water quality. Following their respective permits in 1986 and 1988, respectively, the rates of discharge of runoff from the Cheetah Parcel and Saunders Road were no greater post- development than they had been pre-development. The Cheetah Parcel post-development and pre-development discharge rates were both 10.6 cubic feet per second (cfs). The Saunders Road post-development and pre-development discharge rates were both 32.4 cfs. In issuing the 301 Permit, Respondent authorized the construction of a drainage system that would take runoff north along 24th Street East and then west, eventually emptying into Bowlees Creek. Conforming to the previous drainage system, the new system replaced an open ditch with underground stormwater pipes. Of particular relevance to the Site, two prominent features of the system authorized by the 301 Permit were windows in the vicinity of the southwest and northwest corners of the Site (Southwest Window and Northwest Window). A window is an opening in the wall of a hardened structure whose purpose includes drainage. The opening is constructed at a certain elevation and a certain size to allow specified volumes or rates of water to pass into the structure and then offsite. The 301 Permit authorized the construction of a swale along the southwest corner of the Site to direct runoff discharging from the Saunders Road system into the Southwest Window. This swale has been construed. However, several problems have precluded the construction of the Southwest Window, probably permanently. The most serious problem, from an engineering perspective, is the failure to lay the stormwater pipe along 24th Street East at the proper depth. The stormwater pipe was erroneously installed at an elevation of 15.32 feet National Geodetic Vertical Datum (NGVD), and the Southwest Window was to have been cut at a control elevation of 14.75 feet NGVD. The discharge elevation of the Saunders Road outlet precludes raising the control elevation of the Southwest Window sufficiently to allow gravity drainage into the stormwater pipe. Exacerbating the discrepancy among the as-built elevations of the three structures is what appears to be a design problem belatedly recognized by Respondent. Respondent is justifiably concerned that the Southwest Window, at a control elevation of 14.75 feet NGVD, would draw down the water elevation of the Site's wetland, which is at a wet season elevation of 16.5 feet NGVD (now actually 17 feet NGVD, possibly due to the absence of the Southwest Window). A third problem with the Southwest Window is that the southwest corner of the Site was not historically a point of discharge, so the Southwest Window would deprive the Site's wetland of runoff. Fortunately, neither the Southwest nor the Northwest Window is essential for the proper operation of the surface water management system of 301 Park of Commerce, which largely depends on a series of lakes for treatment and attenuation. The Northwest Window was to be at elevation 16.5 feet NGVD, and its construction would provide needed drainage for the Site. In general, the Northwest Window does not raise the same concerns as does the Southwest Window. The Northwest Window is in the vicinity of the historic point of discharge for the Site and replaces a ditch permitted for the Cheetah Parcel to take runoff north along 24th Street East. The Northwest Window would also alleviate a standing-water problem at the northwest corner of the Site. However, Manatee County, which controls the right- of-way on which the Northwest Window is located and is responsible for its construction and maintenance, has discovered that it lacks a sufficient property interest to access the Northwest Window. The County has since initiated the process by which it can obtain the necessary interest, and, once completed, the County will cut the Northwest Window into the existing structure. Due to the role of the Northwest Window in draining the runoff in the area, including the Site, the Application reincorporates the Northwest Window, as it should have been constructed pursuant to the 301 Permit. Although the Cheetah and Saunders Road permits resulted in greater runoff volume entering the Site, more importantly to area drainage, these permits did not result in greater runoff rates and or in a deterioration in runoff water quality. Likewise, the failure to construct the Southwest Window and Northwest Window is not especially relevant to area drainage, nor is the likely inability ever to construct the Southwest Window. Far more important to area drainage is the fact that Petitioner proposes that the Site, post-development, would produce a runoff rate of 10.6 cfs, as compared to a pre-development runoff rate of 7 cfs. A serious adverse impact to area drainage, the proposed activity increases the runoff rate by 50 percent in a floodprone, 80-percent builtout basin--a basin of such sensitivity that Manatee County is imposing a post-development requirement of substantially reduced runoff rates. The cumulative impacts of the proposed development, together with existing developments, would be to cause substantial flooding of the Bowlees Creek basin. Petitioner's expert attempted to show that the runoff from the Site, which is at the extreme eastern end of the Bowlees Creek basin, would be delayed sufficiently so as not to exacerbate flooding. Respondent's expert thoroughly discredited this testimony due, among other things, to its reliance upon obsolete data and an unrealistic limitation upon the assumption of the direction of travel of storms. Similarly, Petitioner failed to prove that the authorized discharge rate for the 301 Permit is 42 cfs. This assertion is most succinctly, though not exclusively, rebutted by the fact that the 42-inch pipe can only accommodate 18 cfs. Even if the 42-inch pipe could accommodate a substantially greater runoff rate, Petitioner's expert would have erroneously inferred a permitted discharge rate from this increased capacity without negating the possibility that other structures in the 301 surface water management system effectively reduced the rate or that oversized structures existed to accommodate higher runoff rates in storms greater than the design storm. In addition to increasing the runoff rate by 50 percent, Petitioner's proposal would also reduce the historic basin storage by over 40 percent. Displaced basin storage moves downstream, increasing flood levels from fixed storm events. At present, the Site provides 8.68 acre-feet of historic basin storage. The Application proposes to replace this storage with storage in the wetland and retention pond totaling only 4.9 acre-feet. The loss of 3.8 acre-feet of basin storage means that this additional volume of water would, post-development, travel down Bowlees Creek. A final drainage deficiency in Petitioner's proposal arises out of a berm's proposed outside of the Northwest Window. A one-foot bust in the survey of Petitioner's expert would have resulted in this berm preventing runoff from entering the Site from the Cheetah Parcel, as runoff presently does. Respondent's expert suggested several possible alternatives that might result in a permittable project with respect to post-development runoff rates (the record is silent as to the effect of these alternatives upon historic basin storage, although it would seem that they would add storage). Reducing the area of destroyed wetlands to one acre would probably reduce the excess of post-development runoff rate to 1-2 cfs. Petitioner could then obtain offsetting attenuation through a variety of means, such as by obtaining an easement to use the wetland on the Cheetah Parcel, constructing an attenuation pond on the 9-acre parcel, or constructing underground vaults in the filled area of the wetland on the Site. Wetlands Except for the road right-of-way, the Site is undeveloped and forested. The presence of 25-year-old red maples militates against attributing the transition from an herbaceous to a forested wetland to the failure to install the Northwest and Southwest windows. More likely, this transition to the sub-climax species of red maple and willow (in the absence of a cypress source) is due to the repression of fire on the Site. Experts for the opposing sides differed sharply in their biological assessments of the wetland. Petitioner's expert described a stressed wetland whose impenetrable thicket provided habitat only to a lone rat and swarm of mosquitoes. Respondent's expert described a robust wetland featuring a luxuriant overstory of red maple and Carolina willow; an rich understory of ferns, and diverse wildlife ranging from birds in the air (direct evidence); fish, snails, and tadpoles in a small pond (direct evidence); and squirrel and opossum (indirect evidence) scampering (indirect evidence) among the buttonbush, elderberry, and wax myrtle (direct evidence). Undoubtedly, the wetland has been stressed; approximately 30 percent of the wetland vegetation is Brazilian pepper, which is a nuisance exotic. However, the wetland is well hydrated. Issuance of the Cheetah Permit was predicated, in part, upon the rehydration of the wetland on the Site. With the issuance of the Cheetah Permit and especially the Saunders Road Permit, the quality of water entering the wetland has improved by a considerable amount. As already noted, added volumes of runoff are entering the wetland since the issuance of these two permits, although post-development runoff rates are the same as pre-development runoff rates. On balance, the wetland is functioning well in providing habitat and natural drainage functions. Giving due weight to the current condition of the wetland, the enhancement offered by Petitioner does not approach offsetting the loss of wetland area. In return for destroying 2.83 acres of the wetland, Petitioner proposed the enhancement of the remaining 1.83 acres by removing exotic species to no more than 10 percent of the total vegetation. The mitigation is plainly insufficient because of the level of functioning of the entire wetland at present. Additionally, Petitioner has failed to demonstrate that the Brazilian pepper, which is the major nuisance exotic occupying the Site, is evenly distributed; to the contrary, it is present mostly outside the wetland, along a berm just outside of the wetland. The lack of seedlings and old specimens suggests that the Brazilian pepper population may not be stable and may itself be stressed. Petitioner's failure to show that the remaining wetland area has more than 10 percent infestation or is likely to suffer additional infestation further undermines the effectiveness of the proposed mitigation. Respondent has never issued an ERP for a proposed activity involving the alteration of wetlands when the enhancement mitigation ratio is as low as .65:1, as Petitioner proposes. In general, Respondent requires higher mitigation ratios when proposals involve wetlands enhancement, rather than wetlands creation, because the wetlands to be enhanced are already functioning--in these cases, at a relatively high level. Although Petitioner has been unwilling to consider such alternatives, numerous alternatives exist for offsite mitigation or mitigation banking, if insufficient area exists for adequate onsite mitigation. Lastly, Petitioner devoted considerable effort at hearing to portraying Respondent's handling of the Application as flawed and unfair. However, the evidence does not support these assertions. Most strikingly, Respondent's staff treated the drainage windows inconsistently, to the benefit of Petitioner. They treated the Northwest Window as installed for the purpose of calculating the pre-development runoff discharge rate to Bowlees Creek. Until the Northwest Window is installed, the actual rate is even lower. This approach is justifiable because the Northwest Window will be installed at some point. On the other hand, Respondent's staff ignored the higher wetland elevation on the Site, presumably resulting from the absence of the Southwest Window. However, this approach, which benefits Petitioner in calculating wetland drawdown effects, is unjustifiable because the Southwest Window probably will never be installed. Petitioner's specific complaints of unfair treatment are unfounded. For example, Petitioner suggested that Respondent credited Lowe's with wetland acreage for the littoral shelf of its wetland, but did not do so with the wetland on the Site. However, Petitioner produced no evidence of similar slopes between the two shelves, without which comparability of biological function is impossible. Additionally, Petitioner ignored the possibility that, in the intervening 14 years, Respondent may have refined its approach to wetland mitigation. Although occurring at hearing, rather than in the application-review process, Respondent's willingness to enter into the stipulation that the Site presently drains into Bowlees Creek, despite recent data stating otherwise, was eminently fair to Petitioner. Absent this stipulation, Respondent would have been left with the formidable prospect of providing reasonable assurance concerning drainage into the floodprone Bowlees Creek when the post-development rate was 10.6 cfs and the pre-development rate was 0 cfs.
Recommendation Based on the foregoing, it is RECOMMENDED that Respondent deny Petitioner's application for an environmental resource permit and for an exemption, variance, or waiver. DONE AND ENTERED this 29th day of February, 2000, in Tallahassee, Leon County, Florida. ___________________________________ ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of February, 2000. COPIES FURNISHED: S. W. Moore Tracey B. Starrett Brigham. Moore, Gaylord, Schuster, Merlin & Tobin, LLP 100 Wallace Avenue, Suite 310 Sarasota, Florida 34237-6043 Mark F. Lapp Jack R. Pepper Assistant General Counsel Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609 E. D. "Sonny" Vergara Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
The Issue As to Case 92-1751DRI whether Building Permit No. 9110002865 issued by Monroe County, Florida, to Ronald and Patricia LaCroix as owners and Pierce Construction and Builders as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations. As to Case 92-3949DRI whether Building Permit No. 9110003422 issued by Monroe County, Florida, to David Goodridge as owner and Pierce Construction and Builders as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations. As to Case 92-5582DRI whether Building Permit No. 9210004503 issued by Monroe County, Florida, to Dick and Jean Madson as owners and Mark W. Milnes Construction as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations.
Findings Of Fact Petitioner is the state land planning agency charged with the responsibility to administer the provisions of Chapter 380, Florida Statutes, and the regulations promulgated thereunder. Petitioner has the authority to appeal to the Florida Land and Water Adjudicatory Commission any development order issued in an area of critical state concern. Each appeal in this consolidated proceeding was timely and each involved a development within the Florida Keys Area of Critical State Concern as designated under Sections 380.05 and 380.0552, Florida Statutes. Monroe County is a political subdivision of the State of Florida and is responsible for issuing development orders for development in unincorporated Monroe County. Monroe County issued the development orders that are the subject of this appeal. Respondents, Ronald and Patricia LaCroix, are the owners of real property known as Lot 43 Saddlebunch RV Park on Saddlebunch Key in unincorporated Monroe County. On December 12, 1991, Monroe County issued building permit 9110002865 to Mr. and Mrs. LaCroix as owners and to Pierce Construction and Builders as general contractors, to build a boat dock on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout the Saddlebunch RV Park. Respondent, David Goodridge is the owner of real property known as Lots 38 and 39 Saddlebunch RV Park on Saddlebunch Key in unincorporated Monroe County. On March 20, 1992, Monroe County issued building permit 9110003422 to Mr. Goodridge as owner and to Pierce Construction and Builders as general contractors, to build a seawall and boat dock on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout the Saddlebunch RV Park. Respondents, Dick and Jean Madson are the owners of real property known as Lot 38, Section D, Sugarloaf Shores subdivision, Sugarloaf Key in unincorporated Monroe County. On May 13, 1992, Monroe County issued building permit 9210004503 to Mr. and Mrs. Madson as owners and to Mark W. Milnes Construction as general contractors, to build a dock and davits on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout Sugarloaf Shores subdivision. Monroe County's comprehensive plan, which has been approved by the Petitioner and by the Administration Commission, is implemented through its adopted land development regulations, codified in Chapter 9.5, Monroe County Code. Section 9.5-345(m)(2), Monroe County Code, referred to as the four foot rule, provides as follows: (2) All structures on any submerged lands and mangroves shall be designed, located and constructed such that: * * * No structure shall be located on submerged land which is vegetated with sea grasses except as is necessary to reach waters at least four (4) feet below mean low level for docking facilities; No docking facility shall be developed at any site unless a minimum channel of twenty (20) feet in width where a mean low water depth of at least minus four (4) feet exists; Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, provides, in pertinent part, as follows: The Florida Keys are dependent on nearshore water quality for their environmental and economic integrity. The heart of the Florida Keys economy, the means by which Monroe County exists as a civil and social institution, is based on its unique oceanic character. If nearshore water quality is not maintained, then quality of life and the economy of Monroe County will be directly and immediately impacted. OBJECTIVES 1. To protect, maintain and, where appropriate, to improve the quality of nearshore waters in Monroe County. * * * POLICIES 1. To prohibit land use that directly or indirectly degrade nearshore water quality. * * * To prohibit the development of water dependent facilities, including marinas, at locations that would involve significant degradation of the biological character of submerged lands. To limit the location of water-dependent facilities at locations that will not have a significant adverse impact on off-shore resources of particular importance. For the purposes of this policy, off-shore resources of particular importance shall mean hard coral bottoms, habitat of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of less than four (4) feet, and all designated aquatic preserves under Florida Statutes section 258.39 et seq. Section 9.5-4(W-1), Monroe County Code, provides as follows: (W-1) "Water at least four (4) feet below mean sea level at mean low tide" means locations that will not have a significant adverse impact on off- shore resources of particular importance. For the purposes of this definition, "off-shore resources of particular importance" shall mean hard coral bottoms, habitat of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of less than four (4) feet, and all designated aquatic preserves under Florida Statutes section 258.39 et seq. Benthic communities exist in the waters between the two canals and deep water, such as rock-hard bottom, sea grasses, algae, and hard coral. Turtles, manatees, sharks, stingrays, eagle rays, snapper, pink shrimp, mullet, and other marine animals populate the Sound. Sea grass beds play an important role in water quality maintenance in the Keys through filtration, nutrient uptake, stabilization of the bottom, and as a habitat for commercially important species. Neither the canal system for Saddlebunch RV Park nor the canal system for Sugarloaf Shores subdivision has access to deep water without crossing areas of water in Sugarloaf Sound with depths of less than four feet at mean low water. Many of these shallow areas contain sea grass beds. The operation of motor driven boats may result in damage to sea grass beds and shallow water marine communities through prop dredging if boats were to attempt to cross these shallow areas. Although there is evidence of prop dredging in parts of these shallow waters, it was not shown that the damage was done by boats traveling from these canal systems and deep water. Whether boats that may be docked at these sites if these permits are granted will cause damage at some future time to some portion of the shallow waters of Sugarloaf Sound between the canal systems and deep water is speculation. Since 1986, Monroe County has adopted an interpretation of Section 9.5-345(m)(2), Monroe County Code, and of Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, that would permit the construction of each of the subject projects. That interpretation permits the development of marginal seawalls, vertical bulkheads and docks in subdivisions that were under development in 1986 if the proposed structure would terminate in a channel more than 20 feet wide with water more than four feet deep at mean low tide. The structures that are the subject of this proceeding meet that permitting criteria. Monroe County's interpretation of the so-called "four foot rule" is that the rule was intended to restrict the development of boating access facilities in new, undeveloped subdivisions and to regulate proposed expansion of existing marinas and the development of new marinas. Monroe County's interpretation of its rules is that the type development at issue in this proceeding, constructed on an individual family home-site, would have minimal effect on the nearshore water environment of critical state concern. Monroe County considers the subject applications to meet all of its permitting criteria. Respondents presented evidence that several similar projects were permitted at approximately the same time as the subject permits were issued without Petitioner filing an appeal. This evidence was insufficient to establish that Petitioner should be estopped to appeal the subject permits, that Petitioner engaged in selective enforcement of its regulatory power, or that Petitioner otherwise brought the subject appeals for an inappropriate purpose.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9110002865, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case 92-1751DRI. It is further recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9110003422, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case No. 92-3949DRI. It is further recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9210004503, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case No. 92-5582DRI. DONE AND ORDERED this 26th day of January, 1993, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of January, 1993. APPENDIX TO RECOMMENDED ORDER TO CASE NO. 92-1751DRI, CASE NO. 92-3949DRI, AND CASE NO. 92-5582DRI The following rulings are made on the proposed findings of fact submitted by Petitioner. The proposed findings of fact in paragraphs 1, 2, 3, 4, 5, 6, 8, 10, 11, and 14 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 7 are rejected as being unnecessary to the conclusions reached. The proposed findings of fact in the first two sentences of paragraph 9 are adopted in material part by the Recommended Order. The proposed findings of fact in the last sentence of Paragraph 9 are rejected as being unsupported by the evidence. While the evidence established that damage may result, the evidence did not establish that damage would result. The proposed findings of fact in the first sentence of paragraph 12 are rejected as being unsubstantiated by the evidence since the water in the canals is deeper than four feet. The proposed findings in the second sentence of paragraph 12 are subordinate to the findings made. The proposed findings of fact in the last sentence of Paragraph 12 are rejected as being unsupported by the evidence. While the evidence established that damage may result, the evidence did not establish that damage would result. The proposed findings of fact in paragraph 13 are rejected as being subordinate to the findings made. The proposed findings of fact in the first sentence of paragraph 15 are rejected since the evidence established that Monroe County's interpretation of the four foot rule dates to 1986. The proposed findings of fact in the second sentence of paragraph 15 are rejected as being unnecessary to the conclusions reached. The remaining proposed findings of fact in paragraph 15 are adopted in material part by the Recommended Order. The proposed findings of fact in the first sentence of paragraph 16 are subordinate to the findings made. The proposed findings of fact in the second sentence of paragraph 16 are rejected as being argument. The proposed findings of fact in the final sentence of paragraph 17 (there are two paragraphs 16, the second of which is being referred to as paragraph 17) are adopted in material part by the Recommended Order. The remaining proposed findings of fact in paragraph 17 are rejected as being unnecessary to the conclusions reached. The following rulings are made on the proposed findings of fact submitted by Respondents. The proposed findings of fact in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 16, and 17 are rejected as being the recitation of testimony that is subordinate to the findings made. The proposed findings of fact in paragraph 12 are rejected as being contrary to the record of the proceedings. The proposed findings of fact in paragraph 13 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 14 are adopted in part by the Recommended Order are rejected in part as being subordinate to the findings made. The proposed findings of fact in paragraph 15 are rejected as being unnecessary to the conclusions reached. COPIES FURNISHED: Lucky T. Osho, Esquire Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Randy Ludacer, Esquire Monroe County Attorney 310 Fleming Street Key West, Florida 33040 James T. Hendrick, Esquire Morgan & Hendrick 317 Whitehead Street Key West, Florida 33040 William R. Kynoch, Deputy Director Florida Land and Water Adjudicatory Commission Executive Office of the Governor 311 Carlton Building Tallahassee, Florida 32301 Carolyn Dekle, Director South Florida Regional Planning Council Suite 140 3400 Hollywood Boulevard Hollywood, Florida 33021 Robert Herman Monroe County Growth Management Division Public Service Building, Wing III 5825 Jr. College Road Stock Island Key West, Florida 33040 Charles M. Milligan, Esquire Post Office Box 1367 Key West, Florida 33041 David and Florence Clark 4606 Wayne Road Corona Del Mar, California 92625 Edward Warren Werling Post Office Box 1042 Summerland Key, Florida 33042 Theodore W. Herzog, Esquire 209 Duval Street Key West, Florida 33040 Pierce Construction & Builders Route 4, Box 319 Summerland Key, Florida 33042 Dick and Jean Madson Post Office Box 276 Summerland Key, Florida 33402 Mark W. Milnes Route 5, Box 775-G Big Pine Key, Florida 33043 David M. Maloney, Esquire Office of the Governor The Capitol, Room 209 Tallahassee, Florida 32399-0001