The Issue The issue is whether Respondent Department of Environmental Protection may issue to Respondent Tampa Bay Water a variance from the requirements, in Rules 62-555.520(4)(c) and (d), Florida Administrative Code, that an application for a permit to construct and operate a drinking water system contain drawings of the project with sufficient detail to describe clearly the work to be undertaken and complete specifications of the project to supplement the drawings.
Findings Of Fact Inception of Tampa Bay Water, Consolidated Permit, and Other Documentation for the Production of Drinking Water Respondent Tampa Bay Water (TBW) is a wholesale public water supply utility. TBW is governed by a nine-member board of directors with one member each from the municipalities of Tampa, St. Petersburg, and New Port Richey and two members each from the counties of Hillsborough, Pinellas, and Pasco. The purpose of TBW is to use group resources to find regional solutions to the problems of water supply in the region. Over two million persons in the three-county area rely on TBW for their drinking water. The predecessor of TBW was the West Coast Regional Water Supply Authority (WCRWSA), which was created in 1974. The West Coast Regional Water Supply Authority was also a wholesale public water supply authority. However, the authority operated as a cooperative entity, and TBW operates as a regulatory entity. In 1996, WCRWSA sought to renew its permit from Intervenor Southwest Florida Water Management District (SWFWMD) to allow continued withdrawals from four of its eleven major wellfields. Concerned with the environmental impacts, such as drawdowns of the water levels of wetlands, streams, and lakes, from the environmental, if not regulatory, overpumping of the wellfields, SWFWMD denied the application for the quantities requested. An Administrative Law Judge at the Division of Administrative Hearings conducted a hearing and issued a recommended order finding adverse environmental effects from overpumping, but recommending that SWFWMD issue the requested permits subject to certain conditions. Subsequent negotiations resulted in the parties' entering into a series of agreements covering withdrawals from the four wellfields that had been the subject of the administrative hearing and seven more wellfields that were approaching repermitting (11 Wellfields), as well as a series of other matters. On May 20, 1998, WCRWSA, the three member counties, the three member municipalities, and SWFWMD entered into the Northern Tampa Bay New Water Supply and Ground Water Withdrawal Reduction Agreement (Partnership Agreement). The Partnership Agreement requires WCRWSA to bring one or more projects online, by December 31, 2002, to produce at least 38 million gallons per day (MGD) and, by December 31, 2007, to produce at least 85 MGD of new water supply. The Partnership Agreement requires SWFWMD to provide WCRWSA with $183 million toward eligible water supply projects. The Partnership Agreement notes that the then-current Master Water Plan of WCRWSA recognizes that "an aggressive conservation and demand management program is an integral component of a sustainable water supply." (Joint Exhibit 3, p. 31.) The Partnership Agreement notes that the then-current Master Water Plan states that the conservation program was expected to reduce use by 10 MGD per day by 2000 and 17 MGD by 2005. From the effective date of the agreement through December 31, 2002, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 158 MGD, based on a rolling 36-month average. For the next five years, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 121 MGD, based on an annual average. After that, effective December 31, 2007, the Partnership Agreement requires a reduction in pumping of the 11 Wellfields to 90 MGD, also based on an annual average. Three weeks after the execution of the Partnership Agreement, WCRWSA was reorganized into TBW in June 1998 through the execution of two documents: an Amended and Restated Interlocal Agreement dated June 10, 1998 (Interlocal Agreement), and a Master Water Supply Contract dated June 10, 1998. TBW assumed WCRWSA's rights and responsibilities under the Partnership Agreement. The Interlocal Agreement empowers TBW to produce and supply drinking water "in such manner as will give priority to reducing adverse environmental effects of excessive or improper withdrawals of Water from concentrated areas." (Joint Exhibit 1, pp. 20-21.) The Interlocal Agreement incorporates the phased-in reductions in withdrawals from the 11 Wellfields that are set forth in the Partnership Agreement. The Interlocal Agreement notes that, if the Partnership Agreement provides for extensions of the deadlines, the deadlines contained in the Interlocal Agreement shall likewise be subject to extension. Applying to the 11 Wellfields, SWFWMD issued TBW a Consolidated Permit, which was issued on December 15, 1998, and became effective on January 1, 1999. Complementing the Partnership Agreement, which reflects SWFWMD's resource- development role, is the Consolidated Permit, which reflects SWFWMD's regulatory role. The Consolidated Permit incorporates the phased-in reductions of withdrawals, as set forth above, for the 11 Wellfields. Although the deadlines for phased-in reductions are conditioned on the funding to be provided by SWFWMD, pursuant to the Partnership Agreement, these deadlines are otherwise unconditional and firm. The Consolidated Permit expressly provides for extensions of deadlines, except the deadlines set for the phased-in reductions of withdrawals from the 11 Wellfields. The Consolidated Permit imposes upon TBW extensive responsibilities regarding environmental monitoring, reporting, and mitigation. These responsibilities extend to groundwater, wetlands, and surface waters, as TBW must, among other things, monitor and report levels in the surficial and Floridan aquifers and potentiometric surfaces in the Floridan aquifer in the vicinity of the 11 Wellfields, as well as in the vicinity of selected wetlands and surface waters. The Consolidated Permit sets specific "regulatory levels" for these resources. Present and Future Tampa Bay Water Facilities, Including the Surface Water Treatment Plant A majority of TBW's production facilities consists of the 11 Wellfields. In an effort to supplement these production sources so as to comply with the phased-in reduction deadlines set forth in the Consolidated Permit and other documents, TBW annually adopts a New Water Plan, which describes capital planning for drinking water production facilities. The June 2000 New Water Plan summarizes the requirements of the Partnership Agreement. The June 2000 New Water Plan notes that TBW reaffirmed its Master Water Plan and New Water Plan projects in April 2000. These projects include the Enhanced Surface Water System, which includes the Tampa Bay Regional Surface Water Treatment Plant (SWTP), Tampa Bay Reservoir Project (Reservoir), and projects obtaining water from the Alafia River, Hillsborough River, and Tampa Bypass Canal. Other projects, besides the Enhanced Surface Water System, include Seawater Desalination (Desal Plant). The June 2000 New Water Plan states that the Enhanced Surface Water System is eligible for a maximum of $120 million from SWFWMD, pursuant to its funding obligation under the Partnership Agreement. This case involves the means by which the SWTP will be permitted, and, in consideration of the manner of permitting, this case involves the means by which the SWTP will be designed and constructed. The June 2000 New Water Plan notes that TBW and USFilter Operating Services, Inc. (USFilter) have entered into a contract for the latter to design, build, and operate (DBO) the SWTP (DBO Contract). The June 2000 New Water Plan reports that USFilter is currently constructing an access road to the site. Among current issues, the June 2000 New Water Plan describes this case, noting that TBW obtained a variance from Respondent Department of Environmental Protection (DEP) allowing a design, build (DB) approach to permitting the SWTP. The June 2000 Water Plan states that the present challenge "has the potential to delay the completion of the [SWTP] by an estimated 8 months, subsequently delaying delivery of the initial 22 mgd (dry weather conditions) of new surface water to the regional system until May 2003 and more likely final acceptance of the [SWTP] to September 2003." (Joint Exhibit 5, p. 4.) (The accuracy of this statement is open to debate because SWFWMD granted an environmental resource permit for the SWTP project only on June 27, 2000--before which no significant alteration of the land could have taken place.) In the meantime, the June 2000 New Water Plan predicts a water supply shortfall of 100,000 to 2 million gallons per day in the South-Central service area of Hillsborough County. Addressing the SWTP, the June 2000 New Water Plan states that TBW purchased the site in October 1999 and released a Request for Proposals on July 19, 1999. Four pre-qualified DBO teams responded on October 18, 1999. The June 2000 New Water Plan erroneously states that TBW applied for a public drinking water facility construction permit (Water Treatment Permit) in October 1999. Actually, in September or October, TBW prefiled with the Hillsborough County Health Department (Health Department) its application for a Water Treatment Permit and paid the $7500 filing fee. The purpose of this courtesy filing or prefiling was to allow Health Department representatives to examine the application, including drawings and specifications for the SWTP, and perhaps expedite the approval process, once TBW filed a formal application. The June 2000 New Water Plan reports that the SWTP will have a peak day, surface water treatment capacity of 60 MGD and will be located on a 433-acre site near U.S. Route 301 and Broadway Avenue in central Hillsborough County. The June 2000 New Water Plan states that the SWTP project schedule calls for completion of construction by March 2003 with plant startup and testing in May 2003 and final acceptance testing in September 2003. The June 2000 New Water Plan estimates that detailed design, site permitting, and construction of the SWTP will cost $84.3 million, and the annual operation and maintenance expenses will be $7.9 million. As for the Desal Plant, the June 2000 New Water Plan reports that TBW will pursue a design, build, own, operate, and transfer (DBOOT) approach to acquire a plant to produce, initially, 25 MGD and capable of expansion by an additional 10 MGD. The June 2000 New Water Plan states that this plant will cost a total of about $96 million in capital expenses and about $19 million annually to operate. Procurement of the Surface Water Treatment Plant Design, Build, Operate Contract and Basis of Design TBW issued a Request for Proposals (RFP) that invited base and alternative proposals for the SWTP. TBW hired Parsons Engineering Sciences to prepare a preliminary design of the SWTP, so as to assist in the preparation of the proposals; although offerors could use alternative designs to the Parsons base design, all proposals had to meet the performance standards specified in the RFP. After publishing the RFP in papers and technical journals and on the Internet, TBW was able to prequalify five teams of offerors. Four of the five prequalified offerors submitted proposals. TBW received a total of nine proposals because each offeror submitted a base proposal and one alternative proposal, and one offeror submitted a second alternative proposal. At its January board meeting, TBW selected the USFilter proposal. No party filed a bid protest to the specifications of the RFP or the selection of USFilter and its team. After the selection of USFilter, TBW entered into negotiations with USFilter. During this process, USFilter agreed, at its expense, to add sand to the granulated activated carbon filters to remove fine particles more efficiently, even though it cannot recover the resulting cost of $1.5 million before or after the commencement of operations. TBW and USFilter entered into the DBO Contract on April 10, 2000 (DBO Contract). The DBO Contract identifies "Design Requirements" that "are intended to include the basic design principles, concepts and requirements for the [c]onstruction . . but do not include the detailed design or indicate or describe each and every item required for full performance of the physical [c]onstruction . . .." (Joint Exhibit 23, Section 1.2.6.) The "Design Requirements" are Schedule 6 to the DBO Contract. Schedule 6 contains all of the individual, technical specifications for the SWTP. Schedule 6 occupies two of the four volumes of large, three-ringed binders forming the DBO Contract. The DBO Contract identifies USFilter, Clark, and Camp Dresser & McKee, Inc. (Camp Dresser) as the DBO team for the SWTP project. Camp Dresser is providing design services, Clark is performing the construction, and USFilter is providing the operation and maintenance services for at least 15 years, as well as the financial guarantee, through its corporate parent. The DBO Contract provides TBW with a fixed construction cost, fixed operating costs, and guaranteed finished water quality. Schedule 8 assures that finished water quality will meet all applicable state and federal drinking water quality standards. Two witnesses at the hearing testified that TBW exacted from USFilter assurances of water quality that, as to certain parameters, will exceed applicable state and federal drinking water quality standards. The DBO Contract provides TBW with a firm completion date, subject to design modifications requested by TBW and uncontrollable circumstances, such as acts of God, raw water whose quality exceeds the maximum limits, or the delay caused by this case. A key document in this case is the Basis of Design Report (Basis of Design), which was prepared by the DBO team in April 2000. Acknowledging the phased-in withdrawal limitations and potential for fines for not meeting the deadlines set forth in the Consolidated Permit, the Basis of Design describes the purpose of the DBO process as follows: By utilizing the [DBO] approach for the [SWTP], [TBW] expects to secure substantial benefits . . .[,] includ[ing] costs savings, innovative design, reduced risk of schedule and cost excesses, long-term contracted facility operations, and maintenance efficiencies and guaranties. (Joint Exhibit 8, pp. 1-2.) The Basis of Design reports that the SWTP will be located on a 100-acre parcel within a 435-acre tract that will also accommodate facilities for groundwater treatment and storage of the treated groundwater, treated surface water from the SWTP, and treated saline water from the Desal Plant. The Basis of Design identifies the sources of raw water for the SWTF as the Tampa Bypass Canal, Hillsborough River, and Alafia River. Once online, the reservoir will help normalize quantities of available raw water throughout the dry season. The Basis of Design describes the main treatment process as pretreatment, including pH adjustment with sulfuric acid or caustic soda, powdered activated car feed, and ferric sulfate coagulant addition; coagulation, flocculation, and sedimentation using a high-rate ballasted sedimentation process known by its tradename as ACTIFLO; ozonoation for primary disinfection, taste and odor control, and partial conversion of dissolved organic carbon to an assimilable or biodegradable form; biologically active filtration for turbidity reduction, taste and odor control; reduction of biodegradable organic carbon; and post-treatment, including secondary disinfection using chloramines. The finished water will then be pumped into tanks for storage and blending before release into the distribution facilities. Distinguishing the DB process from the typical design, bid, build (DBB) process, the Basis of Design states: a very significant amount of process studies and pre-engineering was performed by the Project Team in support of its [DBO p]roposal. This work included a set of drawings covering all disciplines and developed to the 25 to 30 percent completion stage at a minimum with some drawings developed to a greater degree. This stage of drawing development is significantly beyond the sketches and diagrams usually provided in Basis of Design or Preliminary Design Reports. For this [Basis of Design,] the referenced drawings are attached and should be examined when reviewing this [Basis of Design]. As such, a relatively small number of figures are contained within this [Basis of Design]. (Joint Exhibit 8, pp. 1-4.) The Basis of Design notes that the Project Team conducted "pilot-scale" studies of the chosen treatment processes using Lake Manatee raw water. The purpose of these studies was to validate the selected treatment processes, provide water quality data, and establish appropriate operating criteria, such as coagulant dosages. The Basis of Design addresses raw water quality issues. One table sets out values for 30 different water quality parameters for each of the three raw water sources. The Basis of Design discloses expected water quality data for 11 water quality parameters. Of particular interest are total nitrogen and total phosphorus because, as noted in the Basis of Design, the algal life-cycle increases dissolved organic carbon and nutrient concentrations in reservoir water, and the "severity of this problem is impossible to predict." (Joint Exhibit 8, pp. 2-4.) The expected water quality values for total nitrogen and total phosphorus, respectively, are, on average, 0.8 and 0.55 mg/L and, at maximum, 1.6 and 2.1 mg/L. Each of the three surface waters approaches the average values, but none approaches the maximum values, for total nitrogen. The same is true for total phosphorus for the Tampa Bypass Canal and Hillsborough River. However, for the Alafia River, total phosphorus is 2.09 mg/L, so the raw water from the Alafia River may present a substantial treatment challenge, as it exceeds even the maximum expected value for total phosphorus. An error in Table 2-4 in reporting the maximum and average values of manganese (either the maximum value should be 0.02 mg/L or the average value should be 0.001 mg/L) and the omission of a turbidity parameter expressed in NTUs precludes analysis of these water quality parameters. However, the other expected parameters appear to reflect the actual water quality of these three surface waters. Section 4 of the Basis of Design describes the facilities and design criteria for the SWTP. This section begins with site grading, roadways, yardpiping, and stormwater management and extends to detailed discussions of the pretreatment and treatment processes, including the ACTIFLO, ozone contactor, and biologically active filtration. Urgency of New Means of Producing Drinking Water The SWTP is the hub of a network of production, storage, transmission, and distribution facilities that TBW plans to bring online in order to meet the requirements and deadlines set forth in the Consolidated Permit and other documents. The urgency for bringing this component of these new facilities online as soon as possible is due to environmental reasons, as well as the financial and legal reasons set forth above. Overpumping of existing wellfields has drawn down water levels in surface waters and wetlands, to the detriment of the overall level of biodiversity supported by these natural resources. Some lakes have been down 10 years, and a few have been down 40 or 50 years. During the recent drought, the City of Tampa, which obtains water from the Hillsborough River, lacked adequate volumes of surface water from which to produce sufficient finished water to meet the demand of its customers. Not surprisingly, these supply problems are accompanied by record withdrawals from the 11 Wellfields. Withdrawals in May and June of this year were the highest monthly withdrawals on record--208 MGD and 175 MGD, respectively. If the drought continues and TBW continues to meet the demands of its customers, TBW's withdrawals from the 11 Wellfields will exceed the permitted 158 MGD, on a rolling 36-month average, by April 2001. Wellfield overpumping has stressed the groundwaters. Although surface waters respond to substantial rains in as little as a day or two, groundwater takes significantly longer to respond. The surficial water table is as much as 20 feet below ground level, and the Floridan Aquifer is even deeper. The surficial aquifer does not begin to respond to substantial rains for one week, and the Floridan Aquifer begins to respond in two to four weeks. The condition of the surficial and Floridan aquifers affects the Hillsborough River and Tampa Bypass Canal, which are significantly recharged by the surficial and, sometimes, the Floridan Aquifer. The Floridan Aquifer is especially important to the Tampa Bypass Canal, whose rock bed has been breached. During dry periods, the two aquifers are the primary sources of recharge for these two surface waters. The Alafia River is more confined, but gets water from the Floridan Aquifer through two springs at the head of the river. TBW has already made substantial gains through conservation and has met the goal of nearly 10 MGD for 2000. Over the next 20 years, maximum potential gains are expected to be no more than 74-94 MGD. Conservation will continue to play an important role in securing adequate drinking water supplies in the Tampa Bay area, but conservation, even in conjunction with reclaimed water, will not suffice, especially when future population growth in the area is considered. TBW also manages wellfield production efficiently. Under its Optimized Regulatory Operations Plan, TBW collects and analyzes wellfield data to determine which wellfield to tap, notwithstanding specific limits set by wellfield, in order to minimize environmental damage. The consumptive use permits issued to TBW for the surface waters that will provide raw water to the SWTP restrict the amounts and timing of the removals. Additionally, a hydrobiological monitoring program requires the collection and analysis of data to safeguard against adverse effects in the rivers and, downstream, in the estuary. The contractual deadline for delivery of the SWTP is September 30, 2002. The timeframe for bringing online the SWTP necessarily relies on acceptance testing in the wet season, during which 60-65 percent of the annual rain occurs. The wet season extends from mid June to the end of September. Acceptance testing of the SWTP is imperative toward the end of this period because this is when the water quality of the surface waters bears the highest levels of the contaminants. Thus, if delays postpone beyond the wet season the point at which acceptance testing can take place, the postponement will effectively be until the next wet season and, possibly, the end of the next wet season. Permitting the Design, Build Process for the Surface Water Treatment Plant General The DB process envisioned by TBW would essentially break into phases the process by which TBW would obtain the necessary Public Drinking Water Treatment Construction Permit (Permit). The Permit initially would be based on "30 percent plans," which reflect about a 30 percent level of effort toward the overall design work or 30 percent completion of all of the design work (30 Percent Plans). Generally, 30 Percent Plans mark the end of the preliminary design phase. Plans reflecting 30, 60 and 90 percent levels of effort are customary in DBB processes, as these are the stages at which owners typically review design work. In 30 Percent Plans, some items are designed to 100 percent and other items are not designed at all. However, 30 Percent Plans provide reasonable assurance that the designed system is constructable. In essence, the Permit initially would be a conceptual permit for the entire SWTP coupled with a construction permit for those components for which the design is already complete on the 30 Percent Plans. Construction of each remaining component of the SWTP would await subsequent permit modifications authorizing construction of that component. As noted above, the May 18, 2000, cover letter anticipates another interim permit, or permit modification, covering specific components, and then the final permit, or permit modification, covering the entire SWTP. The DEP district office in Orlando has substantial experience with permitting DB water treatment projects. From 1996-98, the DEP Orlando office has permitted four such projects for the Orlando Utilities Commission and one such project for the City of Kissimmee. One of the Orlando Utilities Commission projects was to construct a completely new water treatment plant. Based on the experience of the DEP Orlando office, DB permitting, when based initially on 30 Percent Plans, shortens and simplifies the permitting process. DB permitting eliminates, or at least postpones, the presentation of elements, such as electrical and HVAC, that are irrelevant to the permitting process; the elimination of elements irrelevant to permitting from the initial designs helps the regulator find the elements that are relevant to the permitting process. Also, the experience of the DEP Orlando office is that the DB process results in no more permit modifications for change orders than are typical of a conventional DBB process. The DB-approval process used by the DEP Orlando office is modeled after the DEP-permitting process for wastewater treatment plants. DEP rules allow DB permitting of these plants, which are similar in construction to water treatment plants. In fact, DEP is preparing to adopt rules to allow DB permitting of water treatment plants. Because the DEP Orlando office did not issue variances from the rules that arguably preclude DB construction of water treatment plants, there is no precedent for the issuance of the variance sought in this case. However, the experience of the DEP Orlando office is that applicants do not present basic design changes after the initial submission, and DB permitting does not mean that regulatory objectives are sacrificed to the expediency sought by the applicant. The Present Case On April 11, 2000, Camp Dresser, on behalf of TBW, filed with the Health Department an Application for a Public Drinking Water Facility Construction Permit. The April 2000 drawings that accompanied the April 11, 2000, application are described above. The cover letter to the Health Department notes that, "upon conceptual approval of the project, individual components will be permitted through permit modifications based on submittals of complete drawings and specifications for each component." In this case, the availability of the Basis of Design meant that the 30 Percent Plans reflected more than a 30 percent level of effort or completion of the five-stage process of pretreatment, pH adjustment, ozone contactors, filtration, and storage in tanks. The engineer had already sized the facilities and defined all of the processes and elements of the SWTP. The April 2000 drawings, as supplemented by the Basis of Design, therefore presented a relatively detailed description of the scope, elements, and processes of the project. On May 18, 2000, Camp Dresser submitted to the Health Department more advanced drawings, which are dated May 18, 2000. The cover letter explains that the drawings are a complete set of Phase I drawings and specifications. The letter states that Camp Dresser intends to file complete drawings and specifications in three phases. Phase I, which is completed with the May 2000 drawings, consists of sitework, high rate flocculation and sedimentation, and ozone contact tanks. Phase II consists of biologically active granulated active carbon filters, clearwell, and gravity thickeners. Phase III consists of the remainder of the project. As of July 3, 2000, prior to the final hearing, the design for the SWTP had reached the 60 percent level of effort or completion. Although the SWTP described in the DBO Contract, Basis of Design, and May drawings is a relatively large, complex facility, it does not employ unproven technology. The standardization of design and regulatory review is facilitated by the use of the so-called Ten States' Standards, which are standards commonly used by the permitting authorities of numerous states, including Florida, to determine the capabilities of specified treatment processes in achieving specific water quality levels. Although the ACTIFLO technology is relatively new, it has been in use for at least five years. A pretreatment sedimentation barrier that reduces treatment time and thus tankage volume requirements, ACTIFLO is in use in a water treatment plant with a capacity of 60 MGD in Canada, which TBW's selection team members visited. ACTIFLO presently is being incorporated into a surface water treatment plant in Melbourne, Florida, where it must treat the nutrient-rich water of Lake Washington and the St. Johns River. The City of Tampa is adding ACTIFLO basins to its facilities. Also significant is the fact that ACTIFLO easily passed the pilot test on Lake Manatee. At present, 25 facilities using ACTIFLO are under design or construction in North America. As is consistent with the theory, the DBO process for designing, building, and operating the SWTP has demanded greater cooperation among the three entities that operate relatively independently in the DBB process. Pursuant to their obligations under the DBO Contract, Camp Dresser, Clark, and USFilter have coordinated, and likely will continue to coordinate, their efforts closely from design and construction, up to operation, to save time and money from the traditional DBB process, in which the design phase, construction phase, and operation phase are relatively independent of each other. The Variance In general, DEP has the authority to issue public drinking water treatment construction permits. The successful applicant obtains one permit--for construction and operation. There are no conceptual permits or separate operating permits. In Hillsborough County, as well as 10 other counties, DEP has delegated its responsibilities for issuing public drinking water treatment construction permits. In Hillsborough County, DEP has delegated this responsibility by an interagency agreement to the Health Department. Applying DEP rules to determine whether to issue a public drinking water construction permit, the Health Department defers to DEP for the issuance of variances from DEP rules. In typical permitting cases, the Health Department uses its own staff in processing the application and reaching a permitting decision. In a large case, such as this, the Health Department's lone professional engineer, who was hired in September 1999, can obtain considerable assistance from professional engineers within the Tampa Bay area and professional engineers employed by DEP. Perceiving a possible incompatibility between the DB process and the rules from which the variance is sought in this case, TBW initially filed a request for a variance with the Health Department. However, the Health Department declined to issue a variance to DEP rules and informed TBW that it had to file its request with DEP. Thus, on January 10, 2000, TBW filed a petition for a variance with DEP. On March 28, 2000, DEP issued a final order, pursuant to Section 120.542, Florida Statutes, granting the requested variance from Rule 62-555.520(4)(c) and (d), Florida Administrative Code (Variance). The Variance finds that the purpose of the underlying statutes would be met "because no component of the project would be permitted or constructed without review by the permitting authority of the complete plans and specifications for that portion of the project." The Variance finds that the DB approach will protect the public health, safety, and welfare in providing safe drinking water without exacerbating possible negative environmental impacts from the overuse of groundwater. The Variance relieves TBW of the necessity of complying with two subsections of the rule governing the contents of applications for a public drinking water construction permit. Rule 62-555.520(4)(c) and (d), Florida Administrative Code, provides: The permit application form sets forth the minimum information which is to be supplied to the Department or the Approved County Health Department. Additional information may be required by the Department to clarify information submitted in the permit application or to demonstrate that the proposed level of treatment will effectively treat the contaminants present in the raw water. The information required by the application is as follows: * * * Prints of drawings of the work project which contain sufficient detail to clearly apprise the Department of the work to be undertaken. All prints shall be minimum of 18 x 24 inches and a maximum size of 36 x 42 inches. The scale of details contained shall be satisfactory for microfilm reproduction. (Reduced size photographic reproduction of drawings for submission may be authorized.) Complete specifications of the project necessary to supplement the prints submitted. The issuance of the Variance by DEP has met with approval, albeit cautious approval, by the Health Department. One Health Department witness was an Engineer III, who is 19-year employee of the Health Department and supervisor of four Environmental Specialists charged with reviewing construction plans for drinking water plants. He testified that he agreed with DEP's final order granting the Variance. The Engineer III and the other Health Department witness, its professional engineer, testified that the issuance of the initial permit would not influence the Health Department in deciding whether to issue permit modifications, except to ensure compatibility. Allowing TBW not to comply with Rule 62-555.520(4)(c) and (d), Florida Administrative Code, the Variance provides that the initial permit shall not authorize the construction of any component of the SWTP; each component may be constructed only after the submission of complete plans and specifications for that component and the issuance of a permit modification based on those complete plans and specifications. The Variance also provides that the permitting authority shall publish a notice of intent to issue a permit modification "if the permitting authority believes that the modifications are of a controversial nature, or that there is heightened public awareness of the project." Save Our Bays and Canals, Inc. The Verified Amended Petition On May 1, 2000, Petitioner filed a petition challenging the Variance. On June 29, 2000, Petitioner filed an amended petition challenging the Variance, and the Administrative Law Judge granted Petitioner leave to file an amended petition on July 3, 2000. At the start of the hearing, on July 7, 2000, Petitioner filed a verified amended petition, which was identical to the amended petition, except that, on July 6, 2000, Petitioner's president had verified the pleading "to the best of [his] knowledge, information and belief." The verified amended petition states that Petitioner has over 400 members. The verified amended petition alleges that a substantial number of Petitioner's members will consume the finished water produced by the SWTP and will use the surface waters supplying the SWTP for recreation. The verified amended petition states that the purpose of Petitioner is to save the bays, canals, and waterways of the Tampa Bay area and to ensure safe drinking water for its members and residents of the Tampa Bay area. The verified amended petition states that the Variance affects Petitioner because it would allow the issuance of the Permit and construction of initial phases of the SWTP prior to submittal, review, and approval of complete plans for the next and subsequent phases. The verified amended petition alleges that Petitioner incorporated to pool its resources to review applications, so as to ensure safe drinking water. The verified amended petition states that submittal and review of a complete set of drawings and specifications is necessary prior to construction of the SWTP to ensure the ability of the facility to comply with state drinking water standards. The verified amended petition states that review of all individual components of the SWTP is necessary to assure the protection of the public health, safety, and welfare and the compliance with all applicable state and federal laws. Addressing specifically the 30 Percent Plans, the verified amended petition objects to the absence of a list of items to be included in the 30 Percent Plans. The verified amended petition alleges that this piecemeal approach to permitting will require Petitioner to request administrative hearings on each phase of permitting. The verified amended petition states that the Variance may have adverse environmental and safety impacts that cannot be evaluated fully without a submittal and review of the complete drawings and specifications. The verified amended petition states that the DBO approach is "self-created." The verified amended petition objects to the failure of TBW to obtain the Variance before issuing the RFP and instead using the DBO Contract as a basis for claiming hardship so as to qualify for the Variance. The verified amended petition states that the number of variances issued for similar 30 Percent Plans threatens to create a situation in which the variance subsumes the rule requiring complete drawings and specifications. The verified amended petition objects to this form of unwritten policy that has not been published as a rule. The verified amended petition states that the phased permitting of the SWTP may create permitting momentum that discourages a rigorous application of the rules at a later stage. The verified amended petition states that the request for a variance is improper because it is for a variance from statutes, not rules. The verified amended petition states that Section 403.861(10), Florida Statutes, requires DEP or Health Department approval of "complete plans and specifications prior to the installation, operation, alteration, or extension of any public water system." The verified amended petition states that "installation" means construction. The verified amended petition states that Section 403.861(5), Florida Statutes, prohibits the issuance of a public drinking water treatment construction permit "until the water system has been determined to have the required capabilities . . .." The verified amended petition states that the assurances of USFilter are insufficient to satisfy this requirement. The verified amended petition states that Section 120.542, Florida Statutes, which authorizes the variance procedure used in this case, does not authorize variances for compliance with federal law. The verified amended petition states that TBW must obtain a federal variance in order to obtain the Variance. The verified amended petition states that the 30 Percent Plans omit information required for permitting, such as the listing of a certified operator, monitoring and recordkeeping programs, and various financial elements, such as the posting of a bond and creation of reserves to demonstrate financial soundness. The verified amended petition states that TBW's substantial hardship is based on contract deadlines that are entirely self-created and, thus, insufficient to warrant a variance. The verified amended petition notes that the environmental damage cited as a basis for granting the Variance "was caused by years of overpumping by . . . TBW . . .." Also, the verified amended petition states that member governments of TBW continue to approve new development, which increases the demand for drinking water, because TBW and its member governments have failed to exploit fully the potential for conservation and reclaimed water. Similarly, the verified amended petition states that SWFWMD helped create the hardship by renewing the permits for additional withdrawals from the 11 Wellfields. The verified amended petition states that the DBO process will not necessarily save time and money and is not a recognized exception to the general requirement that an applicant must submit complete drawings and specifications prior to permitting. The verified amended petition states that 30 Percent Plans do not provide sufficient detail to know what the contractor is promising to build, and it would be faster to correct any mistakes prior to the start of construction, rather than after the start of construction. Standing Petitioner was an unincorporated association from its formation in early October 1999 through February 3, 2000, when it was incorporated as a Florida not-for-profit corporation. Originally named Save Our Bays and Canals Association, the unincorporated association was formed by members of the Apollo Beach Civic Association who were concerned about the environmental impact upon their bays and canals of intensive utility and industrial land uses in close proximity to their homes. Apollo Beach is an unincorporated area along the southeast shore of Tampa Bay, just south of the mouth of the Alafia River. The land uses with which the unincorporated association has been concerned in its brief existence include a sulfur plant, the TECO Big Bend plant, a proposed National Gypsum plant, a proposed concrete plant, the proposed Desal Plant, and, now the proposed SWTP. The Apollo Beach area is very close to the proposed site of the Desal Plant, but is about 17 miles south southeast from the proposed site of the SWTP. Petitioner and its members are primarily concerned with the Desal Plant, not the SWTP. However, Petitioner and its members express concern with the SWTP. The concerns are that DB permitting of the SWTP will jeopardize the production of safe drinking water and will result in greater costs to TBW customers, who will eventually bear the financial burden of costly reworking of a hastily designed and constructed project. Standing analysis is simplified by the elimination of the issue of whether the verification of the amended petition confers standing. The claims of Petitioner in this case do not rise to the level of an attempt to prevent an activity, conduct, or product to be permitted from impairing, polluting, or otherwise injuring the air, water, or other natural resources of the State. First, finished drinking water is not a natural resource of the State. Although a resource, finished drinking water is not natural. Although of lower water quality, raw water is a natural resource. The potable water leaving the SWTP is a manufactured resource. Second, even if finished drinking water were a natural resource, the issuance of the Variance does not have the effect of impairing, polluting, or otherwise injuring a natural resource. The Variance excuses compliance with two rules requiring complete drawings and specifications. Even assuming that the SWTP would impair, pollute, or otherwise injure natural resources, the Variance would not have such an effect because the act of granting the Variance is distinct from the act of granting the Permit itself. Thus, facts regarding the circumstances under which Petitioner's president verified the amended petition are irrelevant for the purpose of determining standing. Petitioner's standing is a function of the characteristics of the corporation and its members. At the corporate level, the articles of incorporation state that the "specific and primary purposes for which this corporation is formed are to operate for the public education and advancement of the water quality of Tampa Bay, its tributaries, its estuaries and its canals and for other charitable purposes, by the distribution of its funds for such purposes." There is some indication in the record of an attempt, after filing the petition commencing this proceeding, to amend the articles of incorporation to state, among Petitioner's purposes, the protection of drinking water. The record does not contain the written articles of incorporation, as amended, or amended articles of incorporation after February 3, 2000. However, for the purpose of this recommended order, the Administrative Law Judge shall assume that such an amendment was made at some point after the filing of the petition and before the final hearing. At the membership level, the water to be produced by the SWTP will be distributed primarily to customers in Pasco and Pinellas counties, St. Petersburg, and the Northwest Service Area of Hillsborough County, not to Apollo Beach, which is in southern Hillsborough County. Nearly all of Petitioner's members reside in Apollo Beach or other nearby communities, which also will not be served by the SWTP. Although an insubstantial number of Petitioner's members will consume finished water from the SWTP in their homes, a substantial number will consume finished water from the SWTP at their places of work or schools and where they shop or dine out. Drinking water is ubiquitous, and the mixture of functional land uses in Apollo Beach is not, so it is highly probable that members of Petitioner will travel the three-county area in connection with their employment, education, and recreation. Close analysis of the characteristics of Petitioner and its members reveals no basis for finding standing to challenge the Variance. Nothing in the record suggests that Petitioner or any of its members have devoted themselves to the arcane task of resisting a perceived trend of state and local agencies to issue series of permits in response to DB proposals--or, more colorfully, to engage in "piecemeal permitting." About the only interest that Petitioner can legitimately claim in DB permitting is that multiple points of entry, at each permit and permit modification, will result in additional expense. If Petitioner has standing to contest even the permitting of the SWTP, Petitioner must petition each time for an administrative hearing, conduct discovery, and participate in the final hearing. However, this seems, at most, like a tenuous interest, which suffers also from the speculation that later stages of the DB permitting process will continue to present new issues not raised in the challenge of the Permit initially approved. Turning to the members themselves, their consumption of drinking water produced by the SWTP is no basis for standing either because the attenuated relationship between the Variance, which excuses compliance with two rules concerning the contents of applications, and the safety of drinking water or the additional costs that could arise from hasty designing, constructing, or permitting. Although it is conceivable that a record could have been made that the DB permitting proposed in this case would likely result in incomplete, incompetent permitting review, so as to jeopardize the public health if the permit were to issue, the record in this case does not support such a contention. To the contrary, the record establishes that the DB permitting is at least as likely as DBB permitting to provide the regulatory oversight necessary to assure the design and construction of a successful public drinking water treatment plant Lacking a substantial nexus in the record between the DB permitting authorized by the Variance and the quality of the drinking water that, if the Health Department issues the Permit, would likely be produced by the SWTP and likelihood of success of the overall construction project, the members of Petitioner likewise lack standing to challenge the Variance. Ultimate Findings of Fact Petitioner and its members lack standing to challenge the Variance. TBW faces a substantial hardship if not given the Variance. The legal and financial consequences of a failure to meet the phased-in withdrawal reductions are real and substantial. The environmental damage caused by overpumping the 11 Wellfields underscores the urgency of developing alternative sources of raw water for production into finished drinking water. The rule from which TBW seeks the Variance is derived from the statute discussed in the Conclusions of Law. The underlying purpose of this statute is the protection of the public health, safety, and welfare. The Variance serves the underlying purposes in two respects. First, the 30 Percent Plans contain sufficient detail to allow permitting to proceed without jeopardizing the objective of the rules to ensure that the USFilter team designs and constructs a water treatment plant that is in full compliance with all federal and state law. Second, the Variance provides that the USFilter team shall construct no component of the SWTP until it has been permitted, either initially or by a permit modification. Petitioner's Liability for Attorneys' Fees and Costs Petitioner has a Technical Committee on which Petitioner relies for examination of technical aspects of matters that are of general concern to Petitioner. This committee obtained a copy of the Variance and, after examination and discussion, developed a position in opposition to DEP's stated intent to grant the Variance. The Chair of Petitioner's Technical Committee, who has a bachelor of science degree in chemistry and is an industrial hygienist, drafted a letter reflecting the opinion of the committee in opposition to the Variance. Petitioner's attorney then converted this letter into the petition that commenced this proceeding. At all times, the Board of Directors of Petitioner approved the actions of the Technical Committee and Petitioner's attorney, including the filing of the petition. When Petitioner's president verified the amended petition, he reasonably relied on the advice of counsel concerning the substance of the assertions, and the advice of counsel was based on the work of the Technical Committee. Petitioner's president also reasonably relied on the work of the Technical Committee when he verified the amended petition. Although DB permitting has been available for the design and construction of wastewater treatment plants for an undetermined period of time, DB permitting for the design and construction of public drinking water plants is a new concept. The concept is so new that the DEP Orlando office mistakenly issued at least 2 DB permits for public drinking water plants without requiring the applicant to obtain a variance from the two rules that prevent DB permitting for such facilities. The concept is so new that the key Health Department employees have expressed concern over personnel demands from this new means of permitting, although they have also expressed at least lukewarm support for the Variance. The record portrays the employees of the Health Department as hard-working and competent, but over-burdened. The DB permitting obviously places significant responsibilities upon the Health Department, especially as it familiarizes itself with DP permitting. Although the availability of professional support from other sources, including DEP, ultimately resolves this issue, the situation of the Health Department also is relevant in assessing Petitioner's liability for attorneys' fees and costs. Two or three aspects of the drawings were deficient, according to Petitioner's professional engineer, whose testimony has been admitted despite the unreasonably restricted opportunity presented for cross-examination by his contractually driven refusal to identify past clients or jobs. Although none of these items seems likely to jeopardize a successful construction project, these were design points on which well-informed professionals could reasonably differ. Although the issue of "improper purpose" presents a closer question than the substantive issues discussed above, there is inadequate subjective or objective evidence in the record supporting TBW's claim for attorneys' fees and costs on this ground. Ultimately, the novelty of DB permitting of drinking water treatment plants precludes a finding of improper purpose. All available facts drive this determination, and, at this point in time, the relative uniqueness of DB permitting of drinking water treatment plants to DEP, the Health Department, and Petitioner and its members provides the necessary margin to preclude a finding of improper purpose.
Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order granting the Variance and denying the request of Tampa Bay Water for attorneys' fees and costs. DONE AND ENTERED this 24th day of July, 2000, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of July, 2000. COPIES FURNISHED: Kathy C. Carter, Agency Clerk Office of General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Ralf G. Brookes, Attorney 1217 East Cape Coral Parkway Suite 107 Cape Coral, Florida 33904 Donald D. Conn, General Counsel Tampa Bay Water 2535 Landmark Drive, Suite 211 Clearwater, Florida 33761 J. Frazier Carraway Thomas A. Lash Salem, Saxon & Nielson, P.A. 101 East Kennedy Boulevard Suite 3200 Tampa, Florida 33601 Cynthia K. Christen Senior Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 William S. Bilenky General Counsel Jack R. Pepper, Jr. Associate General Counsel Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
The Issue The issue in this case is whether the application of Respondents Falkner to transfer and modify a Water Use Permit should be approved.
Findings Of Fact The Southwest Florida Water Management District (District) is responsible for regulation and protection of water resources in the geographic area involved in this proceeding. Since 1994, John Falkner has owned the property in Hillsborough County which is the subject of this proceeding. The Falkner property is farmed by Christopher Falkner, the owner's brother. Prior to purchasing the land, the Falkners farmed the property, also known as the Rogers farm, through a lease arrangement with the previous owner. Rose Ann DeVito owns property to the south of the Falkner property. In the time since Ms. DeVito purchased the property, the elevation of Sumner Road has been raised and culverts were replaced. A fish farm was constructed in close proximity to her property. The result of this and other development has been to direct all the water flow from the surrounding area into the stream adjacent to the DeVito property. Drainage patterns in the area of Ms. DeVito's property have been altered since she first occupied the property. A ditch along Sumner Road which used to handle runoff from her property has been blocked by a neighbor's driveway. Maintenance on the ditch, allegedly a county responsibility, is described as poor. The ditch at the rear of Ms. DeVito's property handled water flow to Bullfrog Creek until the water flow became blocked, and the water diverted onto her property. The effect is that Ms. DeVito's property often contains a large amount of water. A substantial amount of sand is visible on her property, allegedly deposited by water flow. According to Ms. DeVito, both the county and the District have blamed the Falkner farm for the water-deposited sand. Charles and Diana Booth own property adjacent and to the south of the Falkner property. From 1992 to 1994, the Booths suffered from water running off the Falkner/Rogers farm and flooding the Booth property. A flood of the Booth property in the Fall of 1994 was not caused by irrigation but was related to a ten inch rainfall event at the Falkner farm. A ten inch rainfall exceeds a 25 year storm event and would likely result in widespread flooding. The Booths' pasture, top soil and driveway were eroded by the flooding. During the two years of flooding, Mr. Booth complained on several occasions about the flooding to the Falkners' foreman, "Cleo." The complaints were not relayed to Mr. Falkner. In October 1994, Mr. Booth reported the problem to the Southwest Florida Water Management District. Soon after the complaint was made, a representative of the District inspected the property and determined that a ditch needed maintenance. Shortly thereafter, the ditch was cleaned and a berm was installed to redirect runoff away from the Booth property. There has been no further flooding of the Booth property. In October 1995, Mr. Booth became concerned that a ditch was filling with sand and would not continue to handle the runoff. After voicing his concern, a water diverter was installed in the ditch and appears to have remedied the situation. At the time the Falkners began to lease the Rogers property, an existing water use permit, numbered 206938.01, had been issued and was valid for the farm. The Falkners have applied to transfer the existing water use permit from the previous property owner. The Falkners also seek to modify the permit, increasing the total quantities which can be pumped by transferring previously approved quantities from another permit the Falkners currently hold. All of the relevant wells are within the District's Most Impacted Area (MIA) of the Tampa Bay Water Use Caution Area. The District allows a permit holder within the MIA to increase withdrawals from a well by transferring the quantities from another permitted well within the MIA. The other Falkner farm (the "301 farm") from which the quantities would be transferred is located approximately one-half mile to the south of the Rogers farm and is within the MIA. The District reviewed the application and, on September 29, 1995, issued its Proposed Agency Action to Issue Water Use Permit No. 206938.03. The proposed permit includes special conditions requiring monthly pumping reports, water quality reports, adherence to District irrigation allotments (irrigation levels established by the AGMOD computer model) and crop reporting. In reviewing the application the District utilized the criteria set forth in Florida Administrative Code, and the Basis of Review, incorporated into the code by reference. In order to obtain a Water Use Permit, an applicant must demonstrate that the water use is reasonable and beneficial, is in the public interest, and will not interfere with any existing legal use of water. Additionally, the applicant must provide reasonable assurances that the water use: will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters; will not adversely impact offsite land uses existing at the time of the application; will not cause water to go to waste; and will not otherwise be harmful to the water resources within the District. The uncontroverted evidence establishes that the water use is reasonable, beneficial and is in the public interest. The Falkners irrigate farmland to produce agricultural products. The production of food is in the public interest. The proposed use is reasonable and beneficial. Further, uncontradicted evidence and opinions of expert witnesses establish that the proposed use will not interfere with any existing legal use of water. The applicant must provide reasonable assurances that the water use will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters. The evidence establishes that pumping from the Falkner wells will not adversely affect the quality of water within the aquifers from which the water is drawn. Mr. Booth asserted that he is having water quality problems, specifically with rust in his well. The Booth well is approximately 25 years old. There is no evidence that the rust is related to the Falkner pumping. The DeVito and Booth wells draw from the Intermediate aquifer. Review of the potentiometric surface map of the intermediate aquifer indicates that there is a water level variation of 17 feet between the rainy and dry seasons. The result of the variance can be "dry" wells. There are two wells on the Falkner/Rogers property relevant to this proceeding. The first (District ID number 1) is 770 feet deep, is cased to a depth of 160 feet, and opens to the Floridan aquifer. The second (District ID number 2) is 1100 feet deep, is cased to a depth of 140 feet, and opens to the Intermediate and the Floridan aquifers. A cased well does not withdraw water from the formations through which the casing is placed. For example, a well cased to a depth of 160 feet draws no water from the top of the casing (at approximately ground level) to the bottom of the casing at 160 feet. The Intermediate aquifer releases water at a much slower rate than the Floridan aquifer. Based on the type and location of the Falkner wells, the vast majority of the water pumped by the Falkners comes from the Floridan aquifer. Impacts on existing wells are calculated through computer modeling. The "MOD" flow model demonstrates impacts that will occur after 90 days of pumping at peak month levels with no recharge to the aquifer. The MOD flow model results in a conservative "worst case" projection. The MOD flow model calculation projects the drawdown at Falkner well number 1 to be approximately .9 feet. The MOD flow model calculation projects the drawdown at Falkner well number 2 to be approximately 1.4 feet. The MOD flow model calculation projects the drawdown at the Booth well to be approximately one-half foot. The impact on the DeVito well will not exceed that projected at the Booth well. District permitting criteria allow for projected MOD flow model drawdown impacts of less than five feet at existing wells. The impact possible after approval of this application falls well within the District's guidelines. The impact of pumping if the application at issue in this proceeding is approved will result in a maximum variation of one-half foot at the Booth well. The evidence fails to establish that any problems related to water quantity encountered by the Booths are related to agricultural pumping at the Falkner farms. The evidence also establishes that, based on the existing retention and drainage system, the proposed use will not adversely impact surrounding surface water bodies. A system of swales and ditches is utilized to retain the water on the farm property. The evidence fails to establish that runoff from the Falkner/Rogers farm will adversely impact surrounding surface waters if this application is approved. The applicant has provided reasonable assurances that the water use will not adversely impact offsite land uses existing at the time of the application. The evidence establishes that the runoff from the Falkner farm does not discharge directly to the stream at the rear of the DeVito property. Other agricultural property discharges into the stream adjacent to the DeVito property. There is a steady waterflow through the stream at all times, whether or not the Falkner pumps are operating. Ms. DeVito's property consists of Myakka soil, which has little capacity to absorb rainfall and generates large amounts of runoff. The altered drainage patterns in the area have resulted in substantial water on her property. The evidence in insufficient to establish that the Falkner farm pumping has resulted in flooding on Ms. DeVito's property. The evidence fails to establish that approval of the application at issue in this proceeding will cause adverse impact to the DeVito property or will result in water quality or quantity problems. The Booths are concerned that the existing drainage system will not be maintained and that increased pumping will result in their land being flooded again. The evidence fails to establish a substantial likelihood that the Falkner farm drainage system will not be maintained. The applicant has provided reasonable assurances that the water use will not cause water to go to waste. The Falkners use a semi-enclosed seep irrigation system at the Rogers farm. Irrigation is only used when necessary. Mushroom compost, humates, and plastic mulch retain moisture in the soil. A special condition of the permit requires the Falkners investigate the feasibility of tail water recovery and reuse. The applicant has provided reasonable assurances that the use will not otherwise be harmful to the water resources within the District. The permit application results in no increased withdrawal of water than is allowed under the existing permits for the Rogers and the "301" farms.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Southwest Florida Water Management District enter a Final Order granting the Falkner application and issuing permit number 206938.03. DONE and ENTERED this 26th day of April, 1996 in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1996. APPENDIX TO RECOMMENDED ORDER, CASES NO. 95-5763 and 95-5764 To comply with the requirements of Section 120.59(2), Florida Statutes, the following constitute rulings on proposed findings of facts submitted by the parties. Petitioners Booth The Petitioners Booth proposed findings of fact fail to comply with the requirements of Rule 60Q-2.031(3), Florida Administrative Code, which requires citations to the record of hearing. The proposed findings are rejected as irrelevant or not supported by the greater weight of the evidence except where they are consistent with the Findings of Fact set forth herein. Respondents The Respondents' joint proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 15. Rejected, cumulative. 28-29. Rejected, subordinate. 33. Rejected, subordinate. COPIES FURNISHED: Rose Ann DeVito, pro se 11001 Sumner Road Wimauma, Florida 33598 Diana P. and Charles B. Booth, pro se 10812 Sumner Road Wimauma, Florida 33598 Patricia Petruff, Esquire Dye and Scott, P.A. 1111 Third Avenue West Bradenton, Florida 34206 Martin Hernandez, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Peter G. Hubbell, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
Findings Of Fact The parties stipulated, and it is so found, that Petitioner, DER, has jurisdiction over both the issues and the Respondents Dey and KWC. KWC owns and operates a water system which supplies water to both residential and commercial customers in the City of Keystone Heights, Florida. Virginia Key is the President of KWC, a member of the Board of Directors of the corporation, and one of the five stockholders. The other stockholders are her sisters. The five sisters are the daughters of the late G. E Wiggins, and inherited the company from him at his death in 1969. Mr. Wiggins developed the water company in the 1920's and operated it until his death. KWC came under the jurisdiction of the Florida Public Service Commission (PSC) just prior to Mr. Wiggins' death. At that time, pursuant to a PSC requirement, it was assessed and valued at a sum in excess of $250,000.00 by a consultant firm hired for the purpose. As of late November, 1984, KWC served approximately 752 residential customers which, when multiplied by an average 2.5 persons per family factor, results in a total of approximately 1,880 residential inhabitants served by the water system. In addition, the system serves 105 commercial customers. It is impossible to estimate with any reasonable degree of accuracy the number of individuals involved in the commercial service. The system consists of three wells drilled in 1940, 1946, and 1960 to a depth of 350, 450, and 492 feet respectively. Total yield from the three wells is normally 1,350 gallons per minute. The wells are generally well protected against surface water infusion, are normally not subject to inundation, and have had no salt water infiltration problems in the past. At the present time, well number 2, drilled in 1946, with a 350 gpm yield is out of service. The water, when pumped from the ground, is stored in two tanks-one with a 60,000 gallon capacity and the other with a capacity of 800 gallons. Both tanks are steel. Chlorine is added to the water in each storage situation by a hyper-chlori- nation system before the water is sent to the storage tank. The distribution system is made up of 6" and 2" diameter pipe. In March, 1984, two different inspections of the water system, done by, in one case, an environmental specialist and in the other, an Engineer I with DER, revealed several deficiencies in the maintenance and operation of the system all of which constitute violations of DER rules. Specifically, these include (1) failure to provide an auxiliary power source in the event the main pumping capability of the system is lost, (Rule 17-22.106 (3)(a); (2) failure to utilize for the system an operator certi- fied by the state with a Class C license, (Rule 17-22.107(3)(b); (3) failure to maintain a free chlorine residual in the water of at least 0.2 ppm in the system, (Rule 17-22.106(3)(c); (4) failure to maintain a minimum pressure of 20 ppi in the distribution system, (Rule 17-22.106(3)(f); (5) failure to have a gas chlorination facility, (Rule 17-22.106(3)(d); and (6) failure to obtain proper permits to expand the distribution system, (Rule 17-22.108 (1)(b) Rule 17-22, F.A.C., sets up requirements for safe drinking water and was designed to establish guidelines and standards for facilities and water and to bring water into compliance with the Federal Act. Twenty ppi of pressure in the system was adopted as a standard minimum for residual pressure to protect against outside contaminants getting into the water system. Such contaminants could come from ground water, leaks, and water in storage tanks attached to the system such as toilet tanks, being aspirated into the system. Also a certain amount of pressure is required to operate appliances. Normally minimum pressure is found in areas at the edge of the system and in those areas where inadequate chlorination is located. They interact and both pressure and chlorinization are required. Chlorine can be injected into the system generally in two ways: the first is through gas chlori- nation and the second, through hyper-chlorinization as is used in the instant system. The effectiveness of hyper-chlorinization is limited, however, by the size of the system. Basically, hyper- chlorinization is effective when the demand in the system for pressure is no more than 10 ppi. Above this, gas chlorinization is necessary. As late as January 4, 1985, Mr. Dykes went to Keystone Heights to test the system. His tests showed that 11.9 ppi is the average daily flow per 24 hours for the last 12 months. Since this figure is above 10 ppi, in his opinion, a gas chlorinization system would be needed. Chlorine is used to purify water because it has been shown, through long use, to prevent disease. The requirement for a residual chlorine level in water, therefore, is consistent with that concept to insure chlorine is always in the water in sufficient quantity to prevent disease. Respondent's plant has less than the 0.2 residual that is required under the rule. This insufficiency is caused by the inadequate chlorinization system which has insufficient capacity to provide the appropriate amount of chlorine. At the current level, it is providing only approximately 60 percent of the needed chlorine. To correct this deficiency Mr. Dykes recommends installation of a gas chlorinization system. In addition, the pneumatic tank storing the water from the number 3 well does not give sufficient detention time to allow for appropriate reaction of the chlorine contained in the water before the water is released into the distribution system. Another factor relating to the lack of adequate pressure in the system is the fact that, in Mr. Dykes' opinion, too much of the system is made up of 2" diameter water line. A line of this small diameter prevents the maintenance of adequate pressure especially in light of the fact that there are numerous old lines in the system some with corrosion and scale in them which tends to reduce pressure. This latter factor would be prevalent even in the 6" lines. The current plant manager, Mr. Cross, who has been with Respondent for approximately 4 years is, with the exception of one part time employee, the only operations individual associated with the plant. As such, he repairs the meters and the lines, checks the pumps, the chlorinator, and checks and refills the chlorine reservoir on a seven day a week basis. Be learned the operation of the plant from his precedessor, Mr. Johnson, an unlicensed operator who was with the company for 10 years. Mr. Cross has a "D" license which he secured last year after being notified by DER that a license was required. It was necessary for him to get the "D" license before getting the required "C" license. At the present time, he is enrolled to take courses leading toward the "C" license. At the present time, however, he is not, nor is anyone else associated with KWC, holding a license as required. The rule regarding auxiliary power provides that all community systems serving 350 or more persons shall have standby pumping capability or auxiliary power to allow operation of the water treatment unit and pumping capability of approximately one-half the maximum daily system demand. Respondent has admitted that the system is not equipped with an auxiliary power source and it has already been established that more than 350 persons are served by the system. Respondent also admits that subsequent to November 9, 1977, it constructed main water lines for the system which required the obtaining of a permit from either the Petitioner or the county health unit. Respondent admits that it did not obtain or possess a permit to do the additional construction referenced above from either DER or the Clay County Health Department prior to the construction of the water lines referenced. The inspections referenced above, which identified the problems discussed herein, were accomplished by employees of Petitioner, DER, at a stipulated cost of $898.10. Respondent contends, and there is no evidence to the contrary, that there have been no complaints of contaminated water and that the monthly water samples which Mr. Cross forwards to the Clay County Health Department have been satisfactory. Mr. Cross also indicates that a September, 1983 DER analysis of water samples taken from the system was satisfactory. However, bacteriological analysis reports on water collected from Respondent's system on July 11 and 27, 1983, reflect unsatisfactory levels of either coliform or non-coliform bacteria in the water requiring resubmission of test samples. Respondent also contends that no one has ever gotten sick or died from the water furnished by the system and there is, in fact, no evidence to show this is not true. Even though so far as is known, no one has ever been made sick from the water in the system, in Mr. Dykes' opinion, the risk is there. As a result of the defects identified in this system, insufficient chlorine is going into the system to meet reasonable health standards. Though this does not mean that the water is now bad, it does mean that at any time, given a leak or the infusion of some contaminant, the water could become bad quickly, and the standard established by rule is preventive, designed to insure that even in the case of contamination, the water will remain safe and potable. Respondent does not deny that it is and has been in violation of the rules as set out by the Petitioner. It claims, however, that it does not have sufficient funds available to comply with the rules as promulgated by DER. Respondent has recently filed a request for variance under Section 403.854, Florida Statutes, setting forth as the basis for its request that it does not have the present financial ability to comply with any of the suggested or recommended corrective actions to bring its operation into compliance with the rules. Mr. Protheroe, the consulting engineer who testified for Respondent has not evaluated the system personally. His familiarity with it is a result of his perusal of the records of the company and the Petitioner. Based on his limited familiarity with the system, he cannot say with any certainty if it can be brought into compliance with, for example, the 20 ppi requirement. There are too many unknowns. If, however, the central system was found to be in, reasonably good shape, in his opinion, it would take in excess of $100,000.00 to bring it within pressure standards. To do so would require replacement of the 2" lines, looping the lines, and cleaning and replacing some central system lines as well. In his opinion, it would take three months to do a complete and competent analysis of the system's repair needs. Once that was done, he feels it would take an additional three months to bring the plant into compliance with DER requirements. Other repairs, such as those to the lines outside the plant, would take longer because some are located in the downtown area and have interfaced with other utilities. This could take from three to four months if the money were available to start immediately. Here, however, it has been shown that it is not. Consequently, to do the study and then, if possible, procure the funds required, could take well in excess of six months or so. Mr. Protheroe contends, and there is little if any evidence to indicate to the contrary, that to replace the current system with a new one entirely as it is currently constituted would cost at least $250,000.00. However, in his opinion, no one would ever put in a new system similar to the one currently there. He cannot say how much it would cost to buy the system and make the necessary corrections to it to rectify the deficiencies. His familiarity with the system is not sufficiently complete to do this. He cannot say exactly how much the system is worth in its current state, but he is satisfied that it is worth more than $65,000.00. In that regard, Mrs. Dey indicated that in her opinion, the fair market value of the system is currently at $250,000.00. At the present time, there are current outstanding loans in excess of $9,000.00 at 16 percent interest. This current loan basis has been reduced from a higher figure. In 1977, the company borrowed $15,000.00 at 9 percent. In 1981, it borrowed $5,000.00 more at 18 percent. In 1982, the loans were consolidated at an increased rate of 16 percent and the officers have been advised by their current creditors that they cannot borrow any more money for the system in its current state. They would sell the system if a reasonable price could be realized. However, any inquiries on prospective purchases have been chilled by a low rate base assigned by the PSC. In that regard, the City of Keystone Heights offered to purchase the system for $59,000.00. This offer was declined as being unreasonable. Nonetheless, in light of the low rate base assigned by the PSC in its order issued on December 21, 1981 of slightly over $53,000.00 the offer by the city of $59,000.00 is not completely out of line. A certified public accountant, in KWC's December 31, 1983 financial report assigned a valuation of approximately $62,000.00, again a figure only slightly higher than that offered by the city, but substantially less than the $175,000.00 price asked of the city by Respondent Dey and her sisters. Mrs. Dey indicated that to the best of her knowledge the PSC denied rate increases for the purposes of improvements. In the presentation before the commission, respondents relied exclusively on the services of their attorney and accountant. Evidence from Mr. Lowe, of the PSC, however, indicates that KWC has never requested a rate increase to finance any of the improvements called for here. In the PSC order referred to above, Respondent was awarded a 12.25 percent rate of return on its rate base. This figure was an amalgam of a more than 13 percent rate on equity and a lesser figure for cost of doing business, including debt. At the time of that hearing, however, the debt cost was based on a 9 percent interest figure. The 16 percent interest figure came afterwards and no hearing has been requested based on the higher interest rate and it is so found.
Recommendation Based on the foregoing findings of fact and conclusion of law, it is, therefore: RECOMMENDED that Respondents Virginia W. Day and the Keystone Water Company be ordered to comply with the Orders for Corrective Action previously filed herein to bring the water system in question in compliance with the Florida Safe Water Drinking Act without delay or suffer the penalties for non- compliance called for by statute and, in addition, pay costs of investigation in the amount of $898.16. RECOMMENDED in Tallahassee, Florida this 19th day of February, 1985. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1987. COPIES FURNISHED: Debra A. Swim, Esquire Assistant General Counsel Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 John E Norris, Esquire 10 North Columbia Street Lake City, Florida 32055 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue This is a procurement protest. The ultimate issue is whether the Respondent’s award of the "Agreement for the Construction and Operation of a Seawater Desalination Plant and Water Purchase Agreement" ("WPA") to Intervenor, S & W Water, LLC ("S&W") on July 19, 1999, is contrary to Tampa Bay Water's (TBW’s) governing statutes, its rules or policies, or the proposal specifications, or is clearly erroneous, contrary to competition, arbitrary, or capricious. Additional issues presented for decision are: (1) whether Petitioner has standing to maintain this protest; and (2) whether, by participating in the procurement process, Petitioner has waived or is estopped from claiming irregularities arising out of that process.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that TBW enter a Final Order denying Petitioner's Formal Protest. Jurisdiction is reserved for consideration of S&W's request for a determination of improper purpose under Section 120.595(1), Florida Statutes, if such request is made by motion within 10 days from the issuance of this Recommended Order. DONE AND ENTERED this 25th day of October, 1999, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of October, 1999. COPIES FURNISHED: Charles W. Pittman, Esquire 400 North Tampa Street Suite 1040 Tampa, Florida 33602 Richard A. Harrison, Esquire John W. Wilcox, Esquire Allen, Dell, Frank & Trinkle, P.A. Post Office Box 2111 Barnett Plaza, Suite 1240 101 E. Kennedy Boulevard Tampa, Florida 33601-2111 Donald D. Conn, General Counsel Tampa Bay Water 2535 Landmark Drive Suite 211 Clearwater, Florida 33761-3950 John H. Rains, III, Esquire Annis, Mitchell, Cockey, Edwards & Roehn, P.A. Post Office Box 3433 One Tampa City Center, Suite 2100 Tampa, Florida 33601
Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby, RECOMMENDED: For sixty (60) days from service of the Final Order, the Respondent, Thomas Hearns, shall not have to institute that construction required by paragraph 3 below. However, within the sixty (60) days the Respondent shall obtain a firm purchase commitment from a qualified purchaser. A firm purchase commitment is either a signed contract of purchase or a signed contract to purchase between the Respondent and a qualified purchaser. A qualified purchaser is a person or other legal entity that the Petitioner and Polk County Health Department adjudge to be capable of taking over the water system, bringing it into compliance with Chapter 17-22, Florida Administrative Code, and thereafter keeping the system in compliance with Chapter 17-22, Florida Administrative Code. Upon obtaining a purchase commitment, the Respondent shall send a copy of the purchase commitment to the Department of Environmental Regulation and Polk County Health Department. Within twenty (20) days of receipt the Petitioner and the Polk County Health Department shall review the purchase commitment for its acceptability as a firm purchase commitment by a qualified purchaser. Written notice as to whether the Respondent has obtained a commitment which is a commitment by a qualified purchaser shall be given to the Respondent by the Petitioner. The Respondent, to the extent contained in this paragraph, waives his right and capacity to contract and specifically reserves unto the Petitioner the right to void any purchase commitment that is determined to be other than a firm purchase commitment from a qualified purchaser. Failure of the Respondent to obtain a firm purchase commitment within sixty (60) days of service of the Final Order on the Respondent will cause the times and measures for corrective action, contained in paragraph 3 below, to become effective as of the sixty-first (61st) day from the date of service of the Final Order on the Respondent. The corrective actions and the times for taking them are: Within thirty (30) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall install disinfection equipment into the Respondent's water system. The disinfection equipment must be capable of maintaining the degree of disinfection required by Section 17-22.106(3)(c), Florida Administrative Code. The required degree of disinfection shall thereafter be maintained throughout the water system at all times and the disinfection equipment shall be kept in continual operation. Sections 17- 22.106(3)(c) and 17-22.107(3)(a), Florida Administrative Code. Within fifteen (15) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall, by collecting and submitting two (2) samples for analysis, initiate the collection of water samples of the Respondent's water system and the Submission of the samples for microbiological analysis. Thereafter, the Respondent shall collect and submit for analysis two (2) compliance samples per month. Section 17-22.105(1)(d), Florida Administrative Code. Within fifteen (15) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall notify, by written notice to each customer, all customers of the Respondent's water system of the fact that the Respondent fails to perform microbiological monitoring. Section 17-22.112, Florida Administrative Code. Within fifteen (15) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall retain the services of a certified operator who shall thereafter operate, maintain and supervise the Respondent's water system. Section 17-22.107(3)(b), Florida Administrative Code. Within forty-five (45) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall commence, by the submission of a monthly operation report on the water system, the submission of monthly operation reports to the Department. Thereafter, such reports shall be submitted monthly. Section 17-22.111(2), Florida Administrative Code. Within thirty (30) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall commence, by the submission of the results of the analyses of the samples taken pursuant to subsection 3.B. above, the monthly submission of the results of analyses taken by the Respondent to fulfill his Section 17-22.105(1)(d), Florida Administrative Code, monitoring requirement. Thereafter, the Respondent shall submit monthly the results of compliance monitoring. Sections 17-22.107(3)(c) and 17-22.111(2), Florida Administrative Code. Within forty-five (45) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall submit "as-built" engineering plans of the water system, as well as an application for a construction permit. The construction permit shall contain plans and specifications for proposed construction which shall: (1) install a downopening sampling tap on the discharge side of the well pump, and (2) install a bypass and a drain on the system's pressure tank. Within forty-five (45) days of the sixtieth (60th) day from service of final orders in this case, the Respondent shall submit to the Department's Southwest District Office, Tampa, Florida, the sum of Two Hundred Fifty Dollars and Sixty-nine Cents ($250.69). The Petitioner waives payment of the costs of investigation in this case if the Respondent has a firm purchase commitment from a qualified purchaser within sixty (60) days of service of the Final Order on him, or the Respondent complies with the corrective measures and times stated in paragraph 3, AG, above. The Petitioner will place the Respondent in touch with the Department of Community Affairs and the Federal Farmers Home Administration within ten (10) days of service of the Final Order on the Respondent. Within fifteen (15) days of service of the Final Order, the Petitioner shall contact Imperial Polk County's Sam Robinson to urge the purchase of the water system. The Department shall also investigate whether it has funds which Imperial Polk County might obtain in order to purchase the water system. The Petitioner shall notify the Respondent of its investigation within fifteen (15) days of service of the final orders on the Respondent. Alteration of the Final Order may be accomplished by written amendment of the Final Order, signed by both the Petitioner and Respondent. The Petitioner reserves solely to itself the authority to determine whether the Final Order shall be amended due to good cause shown by the Respondent. Among other things, good cause may be delays caused the Respondent due to actions of others beyond his control. In order that the corrective measures stated in paragraph 3 above be accomplished within the stated times, it shall not be good cause for postponement of any of the corrective measures set forth in paragraph 3 above that the Respondent has filed an application for financing of the corrective measures at a time that does not allow time for processing the application prior to the sixty-first (61st) day from service of the Final Order on the Respondent. RECOMMENDED this 6th day of April, 1979, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Vance W. Kidder, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Mr. Thomas Hearns Post Office Box 1916 Winter Haven, Florida 33880
The Issue Whether Petitioner should take enforcement action against Respondent for alleged violations of Chapter 403, F.S., and Chapter 17, F.A.C., as set forth in Notice of Violation and Orders for Corrective Action, dated September 4, 1978.
Findings Of Fact Respondent Deseret Ranches of Florida, Inc., (Deseret), a wholly owned subsidiary of the Church of Jesus Christ of Latter Day Saints, conducts agricultural and ranching operations on approximately 283,000 acres of land owned by the Church which is located in parts of Orange, Osceola, and Brevard Counties. Over 80 percent of the acreage consists of unimproved and semi- improved pasture or range land, and the remainder is utilized for production of sod, clover, and citrus. Citrus production involves the use of 1800 acres. An average cattle herd of 44,500 head is maintained on the pastureland with an average density of 5.4 acres per head. Some 104,000 acres consists of lowlands which are subjected to periodic flooding. This land is located a short distance to the west of the St. Johns River and over 60,000 acres are channelized with canals, ditches, and dikes to improve drainage in order that the pastureland will remain relatively dry in periods of excessive rainfall. To prevent water in the interior canals from flooding the land, pumping stations are located at a number of points which periodically discharge water from the interior canals into larger canals which flow into the St. Johns River. Both diesel and electrically operated pumps are used for this purpose. There are also canals which discharge by gravity flow to the St. Johns River. Deseret Ranch is divided into north and south areas that are separated by land owned by others. The northern portion is bordered on the east by the North Mormon Outside Canal which parallels the St. Johns River. The southern portion is bordered on the east by the South Mormon Canal which also parallels the St. Johns River. The Bulldozer Canal forms the northern border of the southern portion of the ranch. The latter two canals meet at the northeastern corner of the southern area at the St. Johns River. The ranch has a number of artesian wells which are used primarily for providing water for stock and for agricultural irrigation during dry periods of the year. The St. Johns River Water Management District has authorized an annual allocation of 2522 million gallons of ground water per year for these purposes. (Testimony of Dahl, Petitioner's Exhibits 26, 27, 35, Respondent's Exhibit 1) On January 7, 1976, a Department of Environmental Regulation (DER) biologist observed turbidity at the southern end of Lake Hellen Blazes which is in the St. Johns River near the confluence of the Bulldozer and South Mormon Canals. He determined that a Deseret operating pump discharging into Bulldozer Canal was the cause of the turbid water. Water samples taken at various points upstream and downstream from the discharge were analyzed and showed violations of state water quality standards relating to turbidity. DER thereafter advised Respondent to apply for a temporary operating permit for the discharges from the ranch, but it declined to so. At informal meetings during 1976, Respondent explained that the turbidity problem had arisen during a time when interior canals were being cleaned and it was necessary for the pump to be placed into operation to move out the water in order that a dragline operator could accomplish the cleaning task. Respondent agreed at these meetings not to operate its pumps in the future when cleaning canals and there have been no observable turbidity violations since that time. (Testimony of Cormier, Dahl, Hulbert, Petitioner's Exhibits 1, 2, 31, 32-34, Respondent's Exhibit 6) On July 25, 1978, a fish kill in the vicinity of Camp Holly near U.S. Highway 192 was reported to DER personnel. Camp Holly is a fish camp located approximately eight to ten miles north of Bulldozer Canal on the St. Johns River. About 30 dead fish were observed around Camp Holly and several more between that location and Bulldozer Canal. Investigation disclosed that pumps at two stations on the Bulldozer Canal were in operation on that day, and water samples taken upstream and downstream of the operating pumps showed dissolved oxygen levels ranging from 1.8 mgs to 2.8 mgs per liter. A dragline was observed in an interior canal on the Deseret Ranch, but it is unknown if it was then in operation. The St. Johns River was high in 1978. (Testimony of Hadley, Cataldo, Auth, Petitioner's Exhibits 3, 4, 4A, 25, Respondent's Exhibit 5) The flood plain of the St. Johns River South of Lake Washington has decreased significantly over the years due, in part, to the fact that large areas are now behind dikes in order that the land may be used for various agricultural purposes. To maintain low water levels in these reclaimed areas, extensive canal and pumping systems have been installed to remove excess water. Conversion of an area from natural conditions to agricultural use increases pollutant loading of receiving waters from the use of fertilizer and pesticides. Disturbances of the land surface by removal of natural cover and modifications of natural drainage patterns reduce the detention time of storm water flow to the St. Johns River and the natural assimilative or purification processes of the original system. (Testimony of Sullivan, Cox, Petitioner's Exhibit 24) Water quality parameters that could potentially be influenced by the pumping activities of Respondent include turbidity, dissolved oxygen, biological oxygen demand (BOD) , specific conductance, chlorides, total phosphorus and total nitrogen. Available data concerning water quality in the upper St. Johns River include bimonthly water sampling by personnel of the Florida (came and Fresh Water Fish Commission from 1973 to 1976 at 24 stations, irregular sampling by DER personnel from 1975 to 1978 primarily in the Blue Cypress Lake region, and sampling in the summer of 1978 and in January, 1979 by DER and a consulting firm employed by Respondent. The collective data obtained show that the waters in the upper St. Johns River do not consistently meet state water quality standards in various respects and that the most serious deficiency is low dissolved oxygen concentrations. The data show a general downstream trend of increasing specific conductance with seasonal fluctuations due to dilution during the summer rainfall season. Conductivity increases are generally attributable to inputs of mineralized ground water, some of which occurs from irrigation wells. The specific conductance levels in the upper St. Johns regularly exceed the Class I standard of 500 micromhos per centimeter. Although Respondent has over 170 artesian wells under state permits, the wells are only used when irrigation water is necessary and are capped and controlled by valves at other times. Although specific conductance has been shown to increase beyond state standards in "Respondent's canals, primarily during the dry winter season, it is basically a ground water problem and is not considered by Petitioner and other state monitoring authorities to constitute a serious situation. Chloride levels generally increase in the area of Respondent's exterior canals during the summer, but they are almost always below the Class I water quality standard of 250 mgs per liter. Phosphorus concentrations increase somewhat as the river passes the confluence with the North Mormon Outside Canal, but the average total phosphorus concentration in the canal is essentially the same as that in the river upstream of the canal confluence. As to nitrogen concentrations, the data show that there is no pattern of increased concentrations arising from Respondent's canal discharges. Turbidity has not been shown to be a problem since Respondent discontinued pumping during dragline operations. BOD values have not been shown to be sufficiently high as to constitute a water quality problem. (Testimony of Cox, Shannon, Hulbert, Auth, Petitioner's Exhibits 8, 9, 11, 16, 18, 19, 24, 26, 27-29) It is generally agreed by water quality experts that low dissolved oxygen levels are natural to the upper St. Johns River, particularly during periods of high rainfall during the summer and fall. Agricultural activities in the St. Johns River basin contribute to oxygen depletion by the nutrient load that is pumped into the receiving waters after having remained in interior canals for varied periods of time during the dry season. Highly mineralized artesian well water which has migrated to canals, collected plant debris, fertilizer, and cattle waste all serve to depress oxygen values when discharged into the river system. Aquatic plants, such as hyacinths, tend to proliferate in stagnant canals during the dry season and are released into the river during pumping operations. They accumulate in the river lakes where spraying operations by the St. Johns River Water Management District cause decomposition of the plant material which also serves to reduce the oxygen supply. This, in turn, is detrimental to the fish habitat and has caused fish kills in extreme situations. Studies have shown that the population of fish in the river has decreased over the years due to the degradation of water quality and limited access to spawning and grazing areas. Less dissolved oxygen affects the food supply and growth of fish. However, Respondent's interior canals have been a plentiful source of fish over the years. Another cause of reduced oxygen levels in the upper St. Johns River is the natural loading of nutrients from accumulated detritus from adjacent marshes and wetlands. In particular, the trees and plant life in the area from Lake Washington to south of Lake Winder consist of a swamp forest which produces a larger amount of detrital material than grass marshlands. During the wet season of June through October, average dissolved oxygen levels in the upper St. Johns River range from 2.0 to 4.0 mgs per liter and can, at times, fall as low as 0.0. However, samples from lake areas in the upper St. Johns show average levels ranging from 4.9 mg/1 to 7.9. Although water samples showing dissolved oxygen values of zero were measured in Bulldozer Canal in 1978, a sample from the river upstream of the canal showed the same value. In January 1979, six locations were sampled along Bulldozer Canal and in Respondent's canals located behind the dike. No pumps were operating and the data did not indicate any appreciable water quality problem. Samplings in the North Mormon Outsider Canal consistently show dissolved oxygen concentrations of less than 2.0 mg/1. In most cases, the dissolved oxygen concentration in the canal was less than in the river upstream, and in some cases a drop in dissolved oxygen concentration in the river occurred as it passed the canal. Respondent's pumps normally operate during the rainy season after a two to four inch rainfall. There are some twenty-three potential periods for Pumping during the months July to October, but normally the pumps are operated for only about fourteen days a year. It is estimated that the pumps contribute less than one percent of the river content during such periods. Water samples taken from Respondent's exterior canals in October 1978, both before and after pumping, failed to reveal any significant change in dissolved oxygen levels. Insufficient data exists to show the effect of pumping on dissolved oxygen levels at the present time. The organic material discharged by pumping operations undoubtedly depresses oxygen values to some unknown extent, but seasonal monitoring is necessary to ascertain precise data in this regard. The Florida Game and Fresh Water Fish Commission studies showed that only at one time was there found to be a low dissolved oxygen level when the pumps were operating. Initially, at least, pumping serves to aerate the water to some degree with consequent increase in dissolved oxygen. Other ranching and agricultural operations along the upper St. Johns River, together with organic material flushed from adjacent lands, provide an unknown contribution to the depressed oxygen values of the upper St. Johns River. Temporary operating permits have been issued to a number of ranches and farms adjacent to the river which call for monitoring of water quality from structures and pump discharge for evaluation of the effects of the discharge upon the receiving waters. Respondent is one of several such sources in the upper St. Johns River who has declined to submit an application. Although the term "stormwater discharge" is not defined in Chapter 403 or DER rules, pumped discharges of water that has been dormant for a considerable period of time with accumulated plant debris, nutrients, and other wastes are not considered by DER, as a matter of policy, to be "stormwater discharge" within the meaning of Rule 17-4.248, F.A.C. (Testimony of Parks, Sullivan, Hulbert, Justesen, Cornwell, Shannon, Dahl, Mapes, Pate, Ross, Petitioner's Exhibits 6-7, 10-10A, 12-15, 20-24, 26, Respondent's Exhibit 2) The Deseret Ranch contains pine flatwoods, and numerous cypress domes, strands, and marshes. Approximately 50 percent of the ranch area has been left in a natural system and therefore is one of the most productive areas in Florida for the propagation of wildlife. The ranch creates an excellent environment for such productivity by a mixing of natural and developed environment. A wide variety of animal, bird, aquatic and plant life are found throughout the ranch property. Approximately 30,000 deer are estimated to inhabit the ranch area. (Testimony of Cornwell, Dahl, Sullivan, Mapes, Pate, Justesen, Shannon, Respondent's Exhibits 7-10, Petitioner's Exhibit 26) Three public witnesses testified at the hearing. One witness who operates Camp Holly, a fish camp on the St. Johns River, attested to the importance of the river system for recreational and fishing purposes, and expressed concern as to fish kills and the adverse effects on fishing from recent high water. Another witness who is a professional fisherman expressed similar concerns about recent flooding and consequent detrimental effects on fishing. The third witness testified as to his opinion that Petitioner is a responsible agency that is cautious in development and analysis of data in carrying out its statutory responsibilities. (Testimony of Cataldo, Hunter, Nicolay, Hearing Officer Exhibit 1) At the hearing, Petitioner submitted in evidence a summary of its costs of investigating the activities of Deseret in preparation for this administrative proceeding in the amount of $632.94. However, agency records supporting the expenditures were net made available to Respondent and, consequently, Respondent had no opportunity to determine the accuracy of such costs. It is therefore found that Petitioner's costs are not supported by competent evidence. (Testimony of Kozlev, Petitioner's Exhibit 30)
Recommendation That Petitioner issue a final order for corrective action requiring Respondent to submit an application for an operation permit covering its Pumping stations within sixty (60) days from the date of such final order, under the authority of Section 403.121(2)(b), Florida Statutes. DONE and ENTERED this 29th day of June, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Segundo Fernandez, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Philip N. Watson, Esquire 17th Floor CNA Building Post Office Box 231 Orlando, Florida 32802
The Issue The issue is whether Petitioner's application to sit for the water well contractor examination should be approved.
Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: On January 9, 2004, Petitioner, who resides in Baker County, Florida, filed his application with the District requesting that he be allowed to sit for the water well contractor examination. The requirements for qualification to take the examination are set forth in Florida Administrative Code Rule 62-531.300. Relevant to this controversy is the requirement that an applicant present "satisfactory proof of two years experience in the water well construction business." This requirement is normally met by the applicant providing a list of at least ten water well jobs he has completed during a consecutive 24-month period (together with their locations, major use, and approximate depth and diameter), the name and address of the owner of the well, and the approximate date the activity took place. See Fla. Admin. Code R. 62-531.300(6)(a). If the work has been completed in Florida, the applicant is also required to submit copies of completion reports for each of the ten wells. Id. Completion reports are filed by the contractor with the District within thirty days after the work is completed. See Fla. Admin. Code R. 40C-3.411. Finally, the applicant must submit letters from three persons attesting to the length of time the applicant has been working in the water well construction business as a major activity. See Fla. Admin. Code R. 62-531.600(6)(a). Alternatively, an applicant may present "satisfactory proof of equivalent experience," which may be accepted by the District "on a individual basis." See Fla. Admin. Code R. 62- 531.300(6)(b). While this option has rarely, if ever, been used by any applicant, at hearing the District suggested that this provision would allow an applicant to submit other credible documentary evidence, such as affidavits, attesting to the applicant's equivalent experience. Mr. Julian C. Varnes, Jr., a District water resource representative III, is in charge of reviewing water well contractor applications in four northeast Florida counties, including Baker County. Mr. Varnes reviewed Petitioner's application and concluded that he had failed to submit proof of two years' experience in the water well contracting business or satisfactory proof of equivalent experience, as required by the rule. In this case, Petitioner submitted ten completion reports with his application, but none of the reports indicated that he had been involved on those projects, and Petitioner acknowledged at hearing that he could not recall if he was even present on the job site. This is probably because the reports related to jobs performed between November 10, 1982, and July 31, 1985, by his father, a licensed water well contractor, when Petitioner was less than fifteen years old. In addition, the reports submitted by Petitioner covered work performed over a 32-month period, rather than over a 24-month period, as required by the rule, and some of the reports did not have the complete address of the location of the well. By letter dated February 4, 2004, the District advised Petitioner that his application was deficient because he had failed to submit the information required in Florida Administrative Code Rule 62-531.300(1)(b) and (6) relative to experience. The letter advised Petitioner that he must submit an "acceptable list of ten wells together with their completion reports, for wells that [he had] constructed, repaired, or abandoned, with completion dates distributed over a consecutive 24-month time period." Further telephonic discussions between Petitioner and District personnel concerning the request for additional information occurred on March 25 and 29, 2004, but they did not resolve the District's concerns. On June 15, 2004, the District staff again notified Petitioner in writing that he must submit the requested information within 30 days or his application would be denied. When no response was received from Petitioner, on July 27, 2004, the staff issued a Technical Staff Report recommending that the application be denied because of Petitioner's failure to comply with the requirements of Florida Administrative Code Rule 62- 531.300(1)(b) and (6). On August 23, 2004, a Notice of Staff Intent to Recommend Denial of Water Well Contractor Application No. 7300 and Notice of Rights was issued by the District. Petitioner's request for a hearing was then filed. After his first request for a hearing was dismissed, on November 18, 2004, Petitioner filed an amended request for a hearing. In that request, he alleged that the District was "not capable of locating completion reports filed by [Petitioner] and/or his father"; that the experience of he and his father was well known to two District staffers; that he had purchased a well drilling company from another individual and operated under the seller's license for over a year; that he is entitled to licensure because he has satisfactory equivalent experience; and that his father has paid all outstanding fines previously imposed by the District. As relief, Petitioner has requested that he be allowed to take the contractor's examination. At hearing, Petitioner explained that his father was in the water well contracting business for twenty years, and that beginning in 1983, when he was thirteen years old, he had helped his father on "hundreds of jobs" until his father's retirement in 1994. However, Petitioner cannot recall the names and addresses of customers who were serviced by his father's business, which is necessary in order for the District to retrieve completion reports presumably filed by his father. Because of the large number of completion reports filed by contractors throughout its multi-county jurisdiction, in order to retrieve one, the District must have the following information: the year the job was completed, the county in which the job was performed, and the address (township and range) of the well's owner. Petitioner is unable to provide this information.1 In addition, Petitioner stated that he had purchased a water well contractor's business (from Tim Johnson) shortly after his father retired in 1994 and that he operated the business under Mr. Johnson's license for a little more than a year. Although Petitioner produced no documentation concerning jobs he may have performed under Mr. Johnson's license, even if he had, that work would still constitute less than 24 consecutive months of experience, as required by the rule. Petitioner further asserted that Mr. Varnes, who oversees the water well contractors in Baker County, personally "knows" that he is an experienced well driller (having gained such experience through working for his father for many years) and that he possesses the skills necessary to take the examination. However, Mr. Varnes did not agree with this assertion. Finally, Petitioner asked that he be allowed to take the examination, which would be the best indicator of whether he possesses the necessary knowledge to be a contractor. He also pointed out that each completed project must be inspected by a District employee, and that such inspections would verify and ensure that his work is satisfactory. However, the rules require that before the examination can be taken, certain requirements must be met. Petitioner has not satisfied those requirements.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order denying Petitioner's application to sit for the water well contractor examination. DONE AND ENTERED this 25th day of January, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of January, 2005.
The Issue Whether the Petitioner is entitled to the issuance of a water vending machine permit for a machine located at Herman's Meat Market, Nokomis, Florida, under the provisions of Section 381.295, Florida Statutes.
Findings Of Fact A water vending machine located at Herman's Meat Market, 227 West Albee Road, Nokomis, Florida, operating from a non-community water supply came to the attention of the Department's water vending machine permitting personnel in Tallahassee on March 9, 1987. At that time, Frank Dowdney, on behalf of Bottled Water Vending of Florida, had made application for issuance of a water vending machine permit at that location. Upon request of the Department in June, 1987, Mr. Dowdney had the well water tested to determine whether the water met community public water supply system standards as required in Chapter 10D-22.004(5) Florida Administrative Code. The water failed to meet the minimum standards as determined by the lab report dated July 22, 1987 of Thornton Laboratories Inc. There were four areas of deficiency, specifically, turbidity, radionuclides, iron, and total dissolved solids (T.D.S.). Mr. Dowdney did not provide any additional test results to the Department and did not receive a permit from the Department for this location. Subsequent to Mr. Dowdney's death in the fall of 1987, the water vending machine location at Herman's Meats was operated by Glacier Water Vending. In the summer of 1988, an agent of Glacier Water had notified departmental permitting personnel that the machine at this location was not in operation. Glacier Water Vending never requested a permit for this location. On September 7, 1988, Mr. McKinney, President of the Petitioner Clean Water Systems, Inc., became the operator of a new water vending machine at the Herman's Meats Location. Mr. McKinney submitted an application for a permit on September 6, 1988, which was denied on November 3, 1988. The reason for denial was that the water source at Herman's Meats had not been shown to be in compliance with community public water system standards. Neither Mr. McKinney nor Clean Water Systems, Inc., though aware of the predecessor operators at this location, had any ownership interest and had not been an employee of either Bottled Water Vending of Florida or Glacier Water Vending. A reverse osmosis system which had been installed on the source line from the well to the water vending machine subsequent to the 1987 testing was removed by Robert Miller of Glacier Water Vending. Mr. McKinney installed a new reverse osmosis system on the source line on September 7, 1988. The source water for a vending machine is the water just prior to entering the machine, which includes the well and any treatment processes between the well and the machine. The source water for Petitioner's vending machine has been processed through chlorination and one reverse osmosis system. This source water must meet minimum standards established for community public water supply systems. There are many different types of reverse osmosis systems. In general, a reverse osmosis system is a purification process intended to improve water quality. The degree of improvement in product water is affected by many factors including, but not limited to, feed water mineral concentration, feed pressure, feed water temperatures and Ph. It cannot be assumed that minimum water quality standards are being met just because a reverse osmosis system has been installed. The Department has no obligation to provide and/or pay for the chemical testing that is a prerequisite to the issuance of this water vending machine permit. Department personnel do perform required bacteriological and nitrate testing on the non-community well at Herman's Meats. There has been a pattern of noncompliance for bacteriological and chlorine residual levels at this location. The Department does not perform water vending machine testing at Herman's Meats and would only do so if there was a complaint. At the time of the hearing, there had been no complaints about the vended water there. The Petitioner has provided no test results from a state certified lab to the Department. The Petitioner has provided to the Department only test results from his own testing efforts which relate only to the total dissolved solids (T.D.S.) category. The test results generated by Mr. McKinney are not adequate for departmental permitting purposes. The only state certified chemical test results available to the Department on this location show that the source water did not meet minimum standards for community public water supply systems in 1987.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Petitioner's application for a water vending machine permit be DENIED. DONE AND ENTERED this 3rd day of October, 1989, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of October, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-0668 The following constitutes my specific rulings, in accordance with section 120.59, Florida Statutes, on findings of fact submitted by the parties. Respondent's Findings of Fact Accepted-paragraphs 1-11. Rejected-paragraph 11 is covered in the Preliminary Statement Petitioner's Findings of Fact Accepted-paragraph 7 (in substance) Rejected-paragraph 1 - irrelevant paragraph 2 - against the weight of the evidence or subordinate paragraph 3 - insufficient proof (first subparagraph); uncorroborated hearsay (second subparagraph); subordinate (third, fourth and fifth subparagraphs) paragraph 4 - argumentative and uncorroborated 5,8 (sic) hearsay and 10 paragraph 6 - insufficient proof COPIES FURNISHED: Eugenie G. Rehak, Esquire Health Program Attorney Department of Health and Rehabilitative Services 12381 South Cleveland Avenue Suite 501 Fort Myers, Florida 33907 Lew McKinney, President Clean Water Systems, Inc. 250 Warfield Avenue Venice, Florida 34292 Sam Power Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Gregory L. Coler Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Miller General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: WEST COAST REGIONAL WATER SUPPLY AUTHORITY (STARKEY WELLFIELD) The Authority is a nonprofit five-member interlocal entity created in 1974, pursuant to Section 373.1962, Florida Statutes, for the purpose of planning, designing and operating new sources of water supply to governmental entities in Pasco, Pinellas and Hillsborough Counties. Its members include the Counties of Pasco, Pinellas and Hillsborough and the Cities of St. Petersburg and Tampa. The City of New Port Richey also has a seat on the Authority Board. The Authority's revenues are presently derived entirely from the sale of water to its customers. It owns and/or operates five wellfields, some of which are connected by a water transmission pipeline to each other and to wellfields operated or owned by Pinellas County and the City of St. Petersburg. In 1984, the Authority supplied approximately 74 million gallons per day (mgd) to its customers and held consumptive use permits (CUPs) for a total of 94 mgd average and 144 mgd peak or maximum. The Authority anticipates that it will serve approximately 800,000 people in the year 1985. Its master plan, which was last updated in 1982, projects future water demands through 1995 and identifies alternative sources of supply to satisfy those demands. One of the wellfields presently operated by the Authority is the Starkey Wellfield located in Pasco County. The Starkey Wellfield property, located on some 5,400 or 6,947 acres, was acquired in phases by the Southwest Florida Water Management District (District) over a period of years beginning in the early 1970's. There are two remaining parcels which the District has contracted to acquire in 1985 and 1986. These parcels will be acquired under the "Save Our Rivers" program embodied in Section 373.59, Florida Statutes. The various contracts between the District and the Starkey family contain restrictive covenants which require that "the land remain, as nearly as practicable, in its natural state" and that water withdrawals be restricted so that they "do not substantially and/or permanently damage the lands adjacent to the area." In 1981, the District granted the Authority an exclusive license to operate a wellfield on the Starkey property provided that it maintain the wellfield "as nearly as practicable in its natural state." All cater produced from the property is to be for the water supply needs of the City of New Port Richey and Pasco County, except that those entities can authorize the sale of surplus water. Prior to the Authority's involvement with the Starkey Wellfield, the City of New Port Richey planned and constructed water supply facilities at the extreme western portion of the wellfield. Four wells were originally permitted for 3 mgd average and 4.5 mgd maximum. In 1979, in conjunction with Pasco County as a co-applicant, the permit was modified to provide for increased withdrawals of 8 mgd average and 15 mgd peak. This increase was not implemented due to contractual problems between the City and the County. Then, in December of 1981, the Authority became involved in the Starkey Wellfield. Pursuant to a Water Transfer and Management Agreement and a Water Supply Agreement, the City of New Port Richey's four existing wells were transferred to the Authority and the Authority was authorized to construct additional wells and sell the water to the City and Pasco County. As noted above, any surplus water could be sold to others. These agreements have a term of 35 years, with an option of a 35-year renewal period. If the agreements are terminated, the facilities are to revert back to the City of New Port Richey and Pasco County. In 1982, the Authority, the City of New Port Richey and Pasco County obtained the present CUP authorizing the construction and operation of a total of 14 wells and permitting withdrawals at an average annual rate of 8 mgd and a maximum daily rate of 15 mgd. This CUP expires on February 3, 1986. The ten presently operating wells have the capacity to produce 22 mgd. The financing arrangements for the construction of the Starkey Wellfield are not sufficient to complete construction. There is a shortfall of about $720,000, which the Authority plans to make up in revenues from the facility. On December 20, 1983, the Authority, with the City of New Port Richey and Pasco County as co-applicants, applied to the District for a modification of the 1982 CUP to increase withdrawals from 8 mgd average, 15 mgd maximum to 11 mgd average and 21 mgd maximum. At the time, the Authority believed that the increases were justified by the projected water demands of the City and Pasco County. In preparing its water supply plan submitted to the District on March 1, 1984, the Authority determined that it would be feasible to interconnect the Starkey Wellfield with the Cypress Creek pipeline and other major production facilities. In order to finance this pipeline interconnection and again believing that there was sufficient demand in Pasco County and the City of New Port Richey to justify increased withdrawals, the Authority, along with the City and the County, amended the application to modify their CUP on March 23, 1984. This amendment sought average annual withdrawals of 15 mgd and maximum daily withdrawals of 25 mgd. Also requested was the relocation of 2 wells that have not yet been constructed. Between 1971 and 1982, five pump tests have been performed at the Starkey Wellfield, and monitor wells are installed throughout the property. Except for the northwest corner of the property, existing withdrawals have not changed the natural condition of the property. Utilizing these various tests and monitoring results to predict the hydrologic effects of the Authority's proposed increased withdrawals, the District found that the potentiometric drawdown and the water table drawdown at the requested rates would each increase to almost twice the drawdown at the currently permitted rates. The withdrawal of water will cause the level of the potentiometric surface to be lowered more than five feet outside the northern and southern boundaries of the Starkey Wellfield property. The one-foot water table drawdown anticipated from the increased withdrawals could have an adverse effect upon lands immediately adjacent to the north and west. Likewise, this one foot water table drawdown could cause adverse ecological effects on forests and wetlands within the Starkey Wellfield properties. Approximately 40 percent of the Starkey property is high quality wetlands. In June of 1984, a three-day field validation multi-pump test was performed for the Authority. These test results were not available to the District at the time it performed its evaluation. The June tests showed aquifer characteristics different than those previously thought to exist. A much higher transmissivity level was found and the differing leakance values throughout the property demonstrated that the aquifer beneath the Starkey Wellfield is not homogenous. A higher transmissivity level decreases the extent of potentiometric surface drawdown. After substituting the new aquifer characteristics found from the June pump tests, the Authority's computer modeling demonstrates no violation of District hydrologic rules with respect to potentiometric surface and water table drawdowns at the increased level of withdrawals. The Authority's ecologist did not feel that the increased withdrawals would adversely affect natural conditions on the Starkey property, stating that a one-foot water table drawdown is well within the adaptive range of wetland vegetation. In addition, the Authority will maintain its existing ecological monitoring plan on site. The District has not established regulatory levels for the rate of flow of streams or other water courses, for the potentiometric surface or for the surface water in the vicinity of the Starkey Wellfield. Deep monitor wells on the property indicate that there has been no increase in chloride concentrations. Increased withdrawals are not expected to induce saltwater encroachment. If it is found that the potentiometric surface at the Starkey property boundary is lowered more than five feet, an alternative pumping schedule can be put into effect to prevent that occurrence. The pattern of production can be changed by shifting to different wells during the dry season. Increased withdrawals will not lower off-site water tables, lakes or other impoundments by more than one foot, and the potentiometric surface will not be lowered below sea level. The Authority's proposed consumptive use of 15 mgd average would withdraw 2,777.77 gallons per acre per day if the Starkey Wellfield contains 5,400 acres, and 2,159.13 gallons per acre per day if it contains 6,947 acres. Its present permitted withdrawals average more than 1,000 gallons per acre per day. The Authority's proposed increased withdrawals will not interfere with any presently existing legal use of water. BEXLEY (CENTRAL PASCO WELLFIELD) Bexley owns 14,510 acres of land in Pasco County located immediately east of the Starkey Wellfield. The land contains improved pasture, crops, planted pine and some cypress heads and ponds. He presently holds a CUP authorizing a combined average annual withdrawal of 2,416,000 gallons per day with a maximum withdrawal of 11,520,000 gallons per day. Such withdrawals are permitted for agricultural irrigation purposes and come from five wells. In August of 1983, Bexley entered into a contract with Pasco County. The contract requires Bexley to produce and supply to Pasco County an average of 9 mgd of public supply water and a maximum of 13 mgd. Pasco County is given the exclusive right to purchase these amounts and, indeed, must pay for the water made available, whether it is accepted or not. The term of the agreement between Bexley and the County is 33 years. Pursuant to his contract with Pasco County, Bexley applied to the District on December 21, 1983 to modify his existing CUP. A decrease in agricultural withdrawals was requested, as were five additional wells to produce 10.0 mgd average and 13.5 mgd maximum for Pasco County's public water supply. The five additional wells are to be located on 10,848 acres of land, to be known as the Central Pasco Wellfield, located within the 14,510 acres owned or controlled by Mr. Bexley. The modification would result in total (agricultural irrigation and public water supply use) withdrawals of 11,881,000 gallons per day annual average and 23,580,000 gallons per day maximum. In order to determine the anticipated hydrologic effect of the proposed withdrawals, Bexley's hydrologist reviewed and analyzed previous studies of regional hydrogeology and other wellfields prepared by the District, the United States Geological Survey and private consultants. He also conducted a "slug test" and a single well pump test over a period of six days. The aquifer characteristics of the Bexley property were found to be within the range of values derived from other regional testing. Assuming an homogenous aquifer, these characteristics were used in computer modeling to predict the effect of increased withdrawals on and off the Bexley property. The five-foot potentiometric drawdown is confined to the Bexley property, as is the three-foot water table drawdown. The effects of any potentiometric surface and/or water table drawdowns on agricultural crops in the vicinity of the production wells can be offset by irrigation. No lake or other impoundment off-site will be lowered more than one foot. The proposed withdrawals will not cause the potentiometric surface to be lowered below sea level. Regulatory levels have not been established by the District for potentiometric surface, stream flows or surface water on the Bexley property. Although there was no deep monitor well testing done, salt water encroachment is not anticipated as a result of the proposed withdrawals. After an independent evaluation, the District staff also concluded that the proposed Bexley withdrawals would not violate the District's hydrologic rules. The proposed public water supply use of 10 mgd average from 10,848 acres will average 921.80 gallons per acre per day. The combined public supply and agricultural irrigation use of 11.8 mgd from 14,510 acres will average 818.78 gallons per acre per day. CITY OF ST. PETERSBURG (SOUTH PASCO WELLFIELD) The City of Saint Petersburg owns and operates the South Pasco Wellfield, located on a 589 acre site to the south of the Bexley property. This wellfield has been in operation since 1973, and the City has a CUP to withdraw water at the rate of 16.9 mgd annual average and 24 mgd maximum as part of a public supply system. This CUP expires on September 1, 1992. The CUP requires the City to balance production from its South Pasco Wellfield equally with its two other well fields -- Section 21 and Cosme-Odessa. Among the terms and conditions of the CUP are that three regulatory wells be monitored so as not to cause the cumulative weekly average elevations of the potentiometric surface of the aquifer to be lower than the regulatory level set for each well. One of the regulatory wells is located on State Road 54, about 1.5 miles south of the Bexley southern property boundary. The regulatory level set for that well is that the potentiometric surface not be below 42.0 feet above mean sea level on a cumulative weekly average basis. On a noncumulative weekly average basis, the elevations may be 37.0 feet above mean sea level. Since 1974, average water levels at the State Road 54 regulatory well have fluctuated from 44.8 feet to 49.4 feet. Bexley's proposed combined average withdrawals may cause a potentiometric surface drawdown of between 1.3 and 1.9 feet at the State Road 54 regulatory well. The City of Saint Petersburg presented evidence that if the City pumps at its permitted average of 16.9 mgd and Bexley pumps at its average of 11.8 mgd, the City will only be able to withdraw 14.1 mgd without violating the regulatory level for the State Road 54 well. However, this result was obtained by starting off with the normal water levels in the State Road 54 well as they existed in 1980-81, a particularly dry year, and then comparing them with the results obtained if Bexley were to pump its total combined average of 11.8 mgd. This methodology fails to take into account Bexley's permitted withdrawals of 2.4 mgd as they existed in 1980-81, and in effect, double-counted them by initially ignoring their impact on the 1980-81 water levels and adding them back in as a part of the new combined total. In addition, the exhibits and testimony offered by the City failed to demonstrate that the cumulative weekly average elevations would go below 42.0 feet if Bexley were pumping at its requested average rate. While the City of St. Petersburg did utilize its permitted average capacity in 1975, for the past five years it has averaged only between 10.1 and 12.3 million gallons per day from its South Pasco Wellfield. Even if the regulatory level of the State Road 54 well were in jeopardy of violation, it would be possible to shift the pumpage among the eight production wells to counter such a result. The Bexley property is located approximately 3.5 miles from the center of pumpage at the South Pasco Wellfield. THE OTTO POTTBERG TRUST PROPERTY The Otto Pottberg Trust Property, owned by the Pottberg family since 1936, is comprised of 8,000 acres of land located immediately north of the Starkey Wellfield. The property is used for cattle grazing and a nursery operation, and wildlife on the property is abundant. The intervenor Pottberg has observed that since the operation of the well field began on the Starkey property, the cattle ponds on the Pottberg property dry up and vegetation and grasses are adversely affected during the dry seasons. He has observed a noticeable decline in all lake levels. He fears that increased withdrawals from the Starkey well field would diminish the use of his property for cattle grazing and nursery operations, would create a fire hazard and would adversely affect plant, animal and human life on his property. The Authority's experts found no surface drawdowns which would extend into the Pottberg property. The District determined that the potentiometric surface drawdown resulting from the proposed increased withdrawals from the Starkey Well field would exceed five feet on the northern boundary--thus extending into the property owned by the Otto Pottberg Trust. Likewise, the water table drawdown of one foot extends beyond the property at the northwest corner. However, there was no evidence that there are lakes on the Pottberg property at or near the northwest corner of the Starkey property, or that there is an existing CUP well on the Pottberg property in the area where the potentiometric surface drawdown exceeds five feet. PASCO COUNTY'S WATER DEMANDS AND SUPPLIES Pasco County is legally authorized and required to provide an adequate public water supply for its citizens. Based upon per capita use and estimates of population growth, the quantity of public supply water needed by Pasco County has been estimated by various experts as follows: YEAR AVERAGE MGD MAXIMUM MGD 1985 11.3 20.3 1986 12.3 1988 12.8 28.6 1990 16.4 29.5 1993 18.8 40.8 1995 21.8 39.5 2000 27.2 49.0 In the year 1983, the Pasco County Utility Department actually utilized 8.1 mgd for public water supply purposes. Pasco County has a contract right and obligation to purchase the following amounts of water produced by the Authority at the Starkey Wellfield: YEAR AVERAGE AND MAXIMUM MGD 1985 7 1986 6.7 1987 6.4 1988 6.1 1989 5.8 1990 and thereafter 5.5 The City of New Port Richey also has an allocated entitlement to the remaining amounts of water withdrawn from the Starkey Wellfield under its current permit. The Water Supply Agreement for the Starkey Well field recognizes that the City and County will have increasing water supply needs, and provides that they may, upon giving the Authority two years prior notice, increase their entitlement. The Pasco County Utility Department also has 13 CUPs covering public supply wells located on or near the coast. These CUPs, which were renewed in May of 1984 and expire in May of 1992, authorize a total withdrawal of 4.54 mgd average. The majority of these wells are located in coastal areas along and to the west of the 10-foot potentiometric surface contour near the saltwater- freshwater interface. Wells west of the 10-foot contour line generally have high chloride levels. The County has experienced inefficiency in operating some of these wells, and they are considered suitable mainly for fire control and peaking purposes. A condition of the 13 CUPs requires a proportionate, or gallon by gallon, decrease of average day withdrawals should Pasco County acquire another source of public water supply. Pinellas County is contractually obligated to provide Pasco County with up to 10 mgd upon demand. Pasco County controls how much water it will take from the Pinellas County water system. This water is produced by the Authority from other wellfields located within Pasco County, is purchased by Pinellas County and then is transported to Pinellas County. Upon request by Pasco County, the water is then transported back up north again to Pasco County. The water travels approximately 25 to 40 miles from Pasco County to Pinellas County and back to Pasco County. The Pinellas County water system has sufficient capacity to continue to provide 10 mgd to Pasco County. Pasco County does not currently utilize the full 10 mgd, partially because such use would currently present difficulties in fulfilling its contractual obligation or entitlement from the Starkey Wellfield. The contract between Pinellas and Pasco Counties was not placed into evidence. No evidence was presented as to whether Pasco County is either able to or desires to eliminate or change its contract with Pinellas County. It was the position of the Pasco County Director of Public Works and Utilities that it would be more cost-effective to have an alternative source of public water supply. There was insufficient evidence produced at the hearing to determine if the Pinellas County water provided to Pasco County is more or less expensive than the rates presently charged by the Authority or by the contractual agreement between Bexley and Pasco County.