Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ARMANDO VICTOR CALLEJA, 08-001432PL (2008)
Division of Administrative Hearings, Florida Filed:Viera, Florida Mar. 21, 2008 Number: 08-001432PL Latest Update: Nov. 12, 2019

The Issue The issues in this case are whether Respondent violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes (2005),1 and, if so, what discipline should be imposed.

Findings Of Fact At all times material to this proceeding, Mr. Calleja had a valid and active license as a commercial certified pool/spa contractor. His license number is CP 1456568. At all times material to this proceeding, Mr. Calleja was the owner of or did business as Nautica Pools & Spa (Nautica). The Board is charged with regulating the practice of contracting in the State of Florida pursuant to Chapters 455 and 489, Florida Statutes. On April 2, 2005, Mr. Calleja, as the representative for Nautica, entered into a contract with Jack Coleman to renovate Mr. Coleman’s existing pool. From April 2005 to July 27, 2005, Nautica installed rebar in the pool and set a new skimmer. Nautica subcontracted with Prestige Gunite of Melbourne, Inc. (Prestige), to put the gunite in the pool. Gunite is concrete that is sprayed out of a hose to form the walls of the pool. Personnel from Prestige arrived on the project site on the afternoon of July 27, 2005, to apply the gunite, but did not do so because the application would have taken longer to do than one afternoon. The following day, July 28, 2005, Mr. Calleja and a crew from Prestige returned to the project. A representative from Prestige told Mr. Calleja that the steel rebar had not been laid properly. Mr. Calleja told Prestige to apply the gunite and do what was necessary to cover the steel. Mr. Calleja left the project site, and Prestige began applying the gunite. During the application of the gunite, it became evident that the first spraying of gunite was not going to cover the steel. Attempts were made to reach Mr. Calleja, but Mr. Calleja was not available to solve the problem. Prestige began applying additional coats of gunite in an attempt to cover the steel. After the gunite was applied, two problems were identified. The first problem was in the fountain area. The gunite had not been applied properly, and there were hollow areas. The second problem was in the wet deck area. The steel rebar was too close to the surface of the floor, and the steel was visible. In order to remedy the problems, the concrete in the areas would have to be jack hammered to remove the concrete, and new gunite would have to be applied. By letter dated August 28, 2005, Nautica requested Mr. Coleman to pay Prestige $954.57. Nautica advised Mr. Coleman that when that amount had been paid, Nautica would pay the balance owed to Prestige and forward a release to Mr. Coleman. Mr. Calleja claimed that Mr. Coleman owed the $954.57 because Mr. Coleman had damaged Mr. Calleja’s saw. In the letter, Nautica acknowledged that there was additional work which had not been completed. The letter was signed by Mr. Calleja’s wife. Mr. Calleja had verbally told Mr. Coleman that he wanted Mr. Coleman to pay him $2,000.00, and he would take care of paying Prestige. The general specifications in the contract required that the contractor was responsible for “[s]tandard structural engineering plans and permits required by code.” Prior to commencing work on the pool renovation, Mr. Calleja did not secure the required building permits for the project. Mr. Coleman called Clifford Stokes, who is the building official with the town of Indialantic, and asked whether a permit had been issued. Mr. Stokes went to the project site. At that time, the gunite had been shot, and there was exposed steel rebar. Since no permit had been pulled, no inspection had been done after the steel was put in place. On September 15, 2005, Mr. Calleja applied for a building permit. Because the steel had been placed, and the gunite shot, it was impossible to do a visual inspection to determine whether the steel had been placed properly. In order to get a permit after the construction had been commenced, certain affidavits had to be submitted to the building official of Indiatlantic. Mr. Calleja had to submit an affidavit stating that the steel had been placed properly. An affidavit stating that the work had been performed properly had to be submitted from an engineer, who had made a site visit to the project and had determined that the work performed had been according to code. Additionally, Mr. Coleman was required to submit an affidavit that stated that he understood that no inspection had been done of the work by the building official. Mr. Calleja also had to pay a fine to Indiatlantic for commencing work without a building permit. On October 19, 2005, Mr. Calleja and Robert Lee from Lee Engineering came to the project site for the purpose of preparing the affidavits necessary to secure a building permit. Mr. Calleja did not return to the project site after October 19, 2005. Mr. Coleman sent a letter to Mr. Calleja dated October 13, 2005, noting that no work had been done on the project since July 28, 2005, and requesting that Mr. Calleja remedy a number of deficiencies with the work performed on the project and complete the job in accordance with the contract. The letter was returned to Mr. Coleman by the postal service because the time for forwarding mail from the address listed in the letter had expired. When Mr. Calleja came to the project site on October 19, 2005, Mr. Coleman requested a current address from Mr. Calleja, but Mr. Calleja refused to give him one. Mr. Coleman wrote another letter to Mr. Calleja dated October 25, 2005, again stating that no work had been done since July 28, 2005, and requesting that Mr. Calleja correct the deficiencies in the work and complete the contract. Mr. Coleman filed an action in small claims court attempting to recover the money for the lien filed by Prestige. However, Nautica had filed for bankruptcy, and Mr. Coleman did not proceed with the small claim action. A building permit for the project was issued in January 2006. The issuance of the building permit did not relieve Mr. Calleja from the responsibility of assuring that the work in the shallow end of the pool area where the rebar was sticking up was redone properly. After the building permit was issued, neither Mr. Calleja nor Mr. Coleman called for inspections by the Indiatlantic building official. The permit expired in June 2006. After the issuance of the building permit, Nautica performed no further work on the project. The total contract price was $9,340.00. Mr. Coleman and Mr. Calleja entered into an addendum to the contract on July 27, 2005, which increased the contract price to $13,000.00. The contract called for a down payment of $934.00, which was ten percent of the contract amount. After completion of excavation and the form and steel work, a payment of $3,736.00 was due, representing 40 percent of the total work. After completion of the pool shell, a payment of $2,802.00 was due, representing 30 percent of the total work. Prior to plastering, which represented 20 percent of the total work, a payment of $1,868.00 was to be paid. The contract addendum of $3,660.00 called for 50 percent of the addendum amount to be paid at the completion of the pool shell, and the remaining 50 percent of the addendum amount was to be paid at the completion of the pool. By check dated April 22, 2005, signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $1,000.00 as down payment on the project. In June 2005, Mr. Coleman gave Mr. Calleja a check for $573.42 for a pool and spa light. Mr. Coleman was to receive a credit of $380.00 toward the contract for the light. Additionally, Mr. Coleman overpaid Mr. Calleja by $166.90. By check dated July 27, 2005, and signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $7,396.00. This payment was to include half of the addendum amount, but Mrs. Coleman inadvertently included the full amount of the addendum. By check dated August 1, 2005, and signed by Mrs. Coleman, Mr. Coleman paid Mr. Calleja $739.10. Thus, by August 1, 2005, Mr. Coleman had paid Mr. Calleja, $9,682.00 on the contract. In December 2005, Mr. Coleman asked a representative of Paradise Pools, Patrick McDonough, to come to the project site and give an estimate to complete the pool. The estimate of $7,800.00 from Paradise Pools was for a cosmetic plaster of the existing pool, and the work was not warranted against leakage. Mr. McDonough would not warrant the work, because he saw a lot of potential liability problems with the work performed by Mr. Calleja. Mr. McDonough did not recommend that a cosmetic plaster be performed because of the potential problems. On October 26, 2005, Prestige filed a Claim of Lien against the property of Mr. Coleman for $4,227.40 plus interest, costs, and attorney’s fees. The lien was for the work which Prestige had performed on the project on July 28, 2005, and for which Mr. Calleja had failed to pay. Mr. Coleman called Mr. Calleja and told him that a lien had been filed. Mr. Calleja assured him that he would pay the lien, but he failed to do so. Mr. Coleman satisfied the lien by check dated April 11, 2006, for the amount of $5,139.58. David Bogenrief, P.E., viewed the project in June 2008 and provided Mr. Coleman with a quote to develop structural plans to repair Mr. Coleman’s pool. There was no testimony on the amount of the quote, and the Department did not request that the written proposal be admitted in evidence. Mr. Bogenrief did not know what it would cost to repair the pool. The Department has incurred $470.49 for costs in the prosecution of this case.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding that Mr. Calleja did not violate Subsection 489.119(2), Florida Statutes, and that Mr. Calleja violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes; for the violation of Subsection 489.129(1)(g)1., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $5,139.58 as restitution for the payment of the lien filed by Prestige; for the violation of Subsection 489.129(1)(g)2., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $9,682.00, which represents the amount that Mr. Coleman paid to Mr. Calleja; for the violation of Subsection 489.129(1)(j), Florida Statutes, imposing a $1,000.00 fine and four years of probation; for the violation of Subsection 489.129(1)(m), Florida Statutes, imposing a $1,000.00 fine and four years of probation, which shall run concurrently with the other probation imposed; and, for the violation of Subsection 489.129(1)(o), Florida Statutes, imposing a $1,000.00 fine and two years of probation to run concurrently with the other probation imposed; and requiring payment of $470.49 as costs for the prosecution of this case. DONE AND ENTERED this 29th day of August, 2008, in Tallahassee, Leon County, Florida. S SUSAN B. HARRELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 2008.

Florida Laws (6) 120.569120.57120.68489.119489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 1
R. SCOTT ROSENBLUM vs WAYNE ZIMMET AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 06-002859 (2006)
Division of Administrative Hearings, Florida Filed:Stuart, Florida Aug. 08, 2006 Number: 06-002859 Latest Update: Dec. 12, 2007

The Issue Whether Wayne Zimmet's proposed single-family boat dock and lift project is exempt from the need to obtain an Environmental Resource Permit (ERP) from the Department of Environmental Protection (Department) under Florida Administrative Code Rule 40E-4.051(3)(c).1

Findings Of Fact Both Wayne Zimmet and Scott Rosenblum own property in Tequesta, Florida, in a community known as North Passage, which has a man-made navigation and drainage easement canal that terminates at its eastern end at Mr. Rosenblum's property, which is Lot 74, at 8738 Riverfront Terrace. Mr. Zimmet's property, which is Lot 75, at 8750 Riverfront Terrace, is south of the eastern terminus of the canal. The Rosenblum and Zimmet properties are adjacent and share a common boundary. There is an existing dock extending from Mr. Rosenblum's property into the canal. The existing dock is perpendicular to, and extends west from the middle of, the shore of the eastern terminus of the canal. There is a wooden walkway leading from the residence on Mr. Rosenblum's property to the existing dock. However, there also has been a wooden walkway leading from Mr. Zimmet's property to the existing dock. As indicated in the Preliminary Statement, there is a dispute between Mr. Zimmet and Mr. Rosenblum as to who is entitled to access and use the existing dock--and in particular the south side of the existing dock. That dispute will be resolved in state circuit court.2 For purposes of this proceeding, it will be assumed that Mr. Rosenblum has the right to use the existing dock. On or about May 25, 2006, Mr. Zimmet filed an application requesting an ERP exemption to install an eight-foot by twenty-foot (160-square feet) marginal dock with a two-pile elevator lift to designed to accommodate his boat, which is approximately 24.5 feet long (22 feet at the waterline) and eight feet wide. According to documentation submitted with the application, the proposed dock would be centered along the waterfront of his property and extend approximately four feet into the canal. The proposed boat lift would be skewed toward the western end of the proposed marginal dock with the intent being to dock his boat with the bow facing the west so that proposed dock could be used to enter and load the boat from the stern. This positioning of the proposed lift and boat at the proposed dock would skew a boat on the lift at the proposed dock about three feet to the west, away from the existing dock. Based on the evidence, it is found that Mr. Zimmet did not prove by a preponderance of the evidence that his proposed boat dock and lift, even if skewed to the west as indicated in the application drawings, would not "impede navigation" to and from the south side of the existing dock. (Otherwise, Mr. Zimmet's proposed dock and lift would not "impede navigation" in the canal.) This impediment to navigation to and from the south side of the existing dock is not a mere inconvenience. Although Mr. Rosenblum now only owns and uses a raft at the existing dock, he testified that he plans on purchasing and using a boat. Boats in the range of approximately 24.5 feet in length with a beam of 8 to 8.5 feet are common in the North Passage canal. A boat of that size docked at the south side of the existing dock would barely fit alongside Mr. Zimmet's boat, whether docked or on the lift, and there would not be a reasonable amount of clearance for navigating a boat of that size commonly to or from the south side of the existing dock if Mr. Zimmet's boat were docked at the proposed dock or on the proposed lift. (Likewise, if a boat of that size were docked on the south side of the existing dock, there would not be a reasonable amount of clearance for Mr. Zimmet to use his proposed dock and lift.) There was no evidence of any impediment to navigation to and from the north side of the existing dock.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order concluding that, absent a circuit court determination that Mr. Rosenblum does not have the right to access and use the south side of the existing dock, Mr. Zimmet's proposed dock and lift project is not exempt from the need to obtain an ERP. DONE AND ENTERED this 23rd day of October, 2007, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 2007.

Florida Laws (2) 120.569120.57 Florida Administrative Code (1) 40E-4.051
# 2
DR. KENNETH LEVY vs BOARD OF TRUSTEES OF THE INTERNAL IMPROVEMENT TRUST FUND, 94-002766RX (1994)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida May 18, 1994 Number: 94-002766RX Latest Update: Aug. 28, 1995

The Issue The issue in this case is whether Rule 18-20.004(5)(a)1, Florida Administrative Code, is an invalid exercise of delegated legislative authority.

Findings Of Fact 1. Rule 18-20.004(5)(a)1 provides: All docking facilities, whether for private residential single-family docks, private residential multi-slip docks, or commercial, industrial, or other revenue generating/income-related docks or public docks or piers, shall be subject to the following standards and criteria: no dock shall extend waterward of the mean or ordinary high water line more than 500 feet or 20 percent of the width of the waterbody at that particular location whichever is less; * * * Pursuant to stipulation, Petitioner has standing, a dock, and upland access to his property. The parties also stipulated that Petitioner's dock is limited by the 500-foot criterion, as the proposed dock extension would not exceed 20 percent of the width of the waterbody. Petitioner's upland property consists of a single family residence and is located adjacent to sovereign submerged lands located in the Gasparilla Island/Charlotte Harbor Aquatic Preserve. He has lawfully constructed a dock extending about 500 feet from the mean high water mark and into the waters of Charlotte Harbor. The consent of use granted Petitioner acknowledges the relative shallowness of the water adjacent to his property and correspondingly limits the draft of vessels to be moored to the dock. At mean low tide, the depth of the water at the end of Petitioner's dock is about two feet. Petitioner requested authorization to extend his dock waterward another 100 feet. On December 15, 1993, Respondents denied the request, in reliance upon the challenged rule and Section 258.42(3)(e)1, which allows the erection in an aquatic preserve of private residential docks for "reasonable ingress and egress of riparian owners." In a separate administrative proceeding, DOAH Case No. 94-2140, Petitioner is contesting the denial of his request to extend the dock. No single family docks in aquatic preserves extend over 500 feet into the water. In Charlotte Harbor, the average length of a single-family residential dock is 200 feet. Nearby Petitioner's dock is a 600-foot long public fishing pier, which was constructed before the subject 500-foot rule was promulgated. From mean high water waterward, the first habitat surrounding Petitioner's dock is an intertidal sand flat that extends about 100-150 waterward from shore. The next habitat is mostly unvegetated submerged bottom with patches of submerged aquatic vegetation that extends from the end of the intertidal sand flat to about 350-400 feet from shore. The vegetation of the latter habitat is mostly Cuban shoal grass, which occurs in no more than four patches of about 50 square feet, in an area measuring 25 feet in both directions from the dock. Last, extending from 350-400 feet waterward to the end of the dock, is a largely unvegetated area with sporadic pieces of attached algae. Unvegetated bottoms play no role in the propagation of fish or wildlife. The biological or scientific value of unvegetated bottoms is unaffected by a dock, although there is some evidence that toxic substances may leach from the construction materials and adversely impact nearby vegetation. However, the dredging caused by boat propellers scouring any form of submerged bottom suspends sediment that can be carried to areas of vegetated bottom, where the increase in turbidity may reduce the penetration of sunlight and thereby harm the aquatic vegetation. In the vicinity of Petitioner's dock, though, there is no evidence of significant prop dredging from recreational boating. The absence of submerged vegetation is more likely a feature of the high-energy shoreline where wave energy disrupts sediments and provides unsuitable habitat. In promulgating the predecessor to Rule 18- 20.004(5)(a)1, the Board of Trustees of the Internal Improvement Trust Fund attempted to balance interests that sometimes are competing, such as environmental, aesthetic, recreational, and private commercial. There was some concern that previously authorized docks in sovereign submerged lands had infringed upon the riparian access of adjacent upland owners. The 500-foot limitation was not in the original rule, which was promulgated in 1981, but was added by an amendment in 1985. The Board of Trustees of the Internal Improvement Trust Fund tried to set thresholds that would not result in the denial of more than a negligible number of dock applications, based on historic dock application data and predominant vessel lengths of under 27 feet. However, the record does not explain how the Board of Trustees of the Internal Improvement Trust Fund analyzed the above-described data so as to arrive at the 500-foot limitation now under challenge. Without providing more detail concerning the data and analysis, it is possible that a limitation of 100 feet or 900 feet would have satisfied the considerations stated in the preceding paragraph. Shallow water predominates in the aquatic preserves, and Board of Trustees of the Internal Improvement Trust Fund realized that a dock extending no more than 500 feet might not reach water depths that are readily navigable. The Board of Trustees of the Internal Improvement Trust Fund could not rationally adopt a rule to ensure minimum water depths for all docks, and chose the 500-foot limitation evidently to provide an easy-to-administer standard.

Florida Laws (7) 120.52120.56120.57120.68258.42258.43258.44
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs DOUGLAS CLAIBORNE, D/B/A CLAIBORNE HOME IMPROVEMENT AND MAINTENANCE SERVICE, 06-001427 (2006)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 20, 2006 Number: 06-001427 Latest Update: Nov. 14, 2006

The Issue Whether Respondent violated Sections 489.127(1)(f) and 455.227(1)(q), Florida Statutes (2004), and what discipline should be imposed.

Findings Of Fact At all times material hereto, Respondent was not licensed to engage in construction in the State of Florida. At all times material hereto, Respondent’s business did not possess a certificate of authority to practice as a contractor-qualified business. On or about October 5, 2004, Respondent contracted with Dyba to repair the roof at Dyba’s residence in Santa Rosa County, Florida. The contracted cost of these repairs was $3600, of which Respondent collected $600 from Dyba by check. On or about October 9, 2004, Respondent placed an advertisement in the Pensacola News Journal asserting that he would make repairs to kitchens, baths, decks, siding, docks, and most any hurricane damage. On June 8, 1994, Petitioner issued a Notice to Cease and Desist to Respondent for engaging in the unlicensed practice of construction contracting. The total investigative cost to the Petitioner was $166.88.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner enter a final order finding Respondent guilty of violating Section 489.127(1)(f), Florida Statutes (2004), imposing an administrative fine in the amount of $5,000, and assessing costs of investigation and prosecution in the amount of $166.88. DONE AND ENTERED this 11th day of August, 2006, in Tallahassee, Leon County, Florida. S SUZANNE F. HOOD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of August, 2006. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Douglas Claiborne DOC No. 203745 Berrydale Forestry Camp 6920 Highway 4 Jay, Florida 32565 John Thomas, Classification Officer Berrydale Forestry Camp 6920 Highway 4 Jay, Florida 32565 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 John Washington, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (6) 120.57455.227455.228489.105489.127489.13
# 4
MIDWEST INDUSTRIAL PAINTING OF FLORIDA, INC. vs. DEPARTMENT OF TRANSPORTATION, 87-003599BID (1987)
Division of Administrative Hearings, Florida Number: 87-003599BID Latest Update: Sep. 15, 1987

Findings Of Fact Introduction On an undisclosed date, respondent, Department of Transportation (DOT), gave notice to qualified and interested contracting firms that it was accepting bids from firms interested in providing various services on State Job No. 90030- 3539. Such bids were due on or before June 24, 1987. In general terms, the project required the successful bidder to perform various maintenance services on the Old Seven Mile Bridge between Pigeon Key and Knight Key just southwest of Marathon in Monroe County, Florida. The parties have stipulated that the project involves the following classes of work: Bridge painting 82 percent Restoration of spalled areas 6 percent Miscellaneous concrete and steel 9 percent Maintenance of traffic 3 percent In response to this offer, three contractors submitted timely bids. These included petitioner, Midwest Industrial Painting of Florida, Inc. (Midwest), intervenor-respondent, Cone Constructors, Inc. (CCI), and J. D. Abrams, Inc. Their respective bids were $1,746,390, $1,122,000 and $2,149,345. The parties have stipulated that the bids of both CCI and Midwest are below the DOT budget estimate and preliminary estimate for the project. On August 3, 1987 DOT posted its intent to award the project to CCI, which submitted the lowest dollar bid. Thereafter, petitioner timely filed a protest challenging the award of the contract to CCI. In its formal protest, Midwest contended that CCI was ineligible to submit a bid since it was not prequalified by DOT to perform bridge painting, a service required for this job. The filing of the protest prompted the instant proceeding. The Project The Old Seven Mile Bridge, once a vital link in the Florida Keys highway network, was replaced in the early 1980s with a new Seven Mile Bridge. Since its replacement, the old bridge has had very little, if any, traffic and is no longer in service as a state highway. Indeed, its center span has been removed, and it is used primarily as two fishing piers by avid anglers and for access to Pigeon Key where a University of Miami research facility is located. The legislature recently mandated that the old bridge be turned over to the Department of Natural Resources (DNR). So that DNR receives the bridge in good condition, DOT intends to perform all necessary maintenance and rehabilitation prior to its turnover. The project has been identified as State Job 90030-3539. The job includes painting the exposed structural steel, doing "corrective measures" to portions of the structural members, and other miscellaneous work. The project will be funded wholly with state funds, and is not considered a critical job. Although at hearing DOT personnel considered the structural work to be the most important aspect of the project, and the painting to be incidental, DOT did not prepare the bid specifications in this manner. Rather, it elected to prepare the specifications listing bridge painting as normal work. By categorizing the work in this manner, DOT did not contravene any statute, rule or standard. Had DOT categorized painting as "specialty" or incidental work on the project, painting would have been considered an incidental aspect of the job, and bidders would not have to be prequalified in bridge painting. However, DOT did not assert its specifications were in "error," or that this might serve as a ground to reject all bids. Indeed, there is no evidence that any bidder was confused or had any doubt as to the services required under the contract. Prequalification Requirements DOT requires that, on projects exceeding a cost of $250,000, bidders obtain a certificate of qualification setting forth the areas (classes) in which they are qualified to perform work. This is commonly known as prequalification. One of these classes of competency is bridge painting, which constituted approximately 82 percent of the work to be done on Old Seven Mile Bridge. The parties have stipulated that CCI's certificate of qualification did not include bridge painting as an area in which it had been qualified. Despite several post-June 24 requests by DOT to furnish additional information, CCI had not yet supplied such data at the time of hearing as would enable it to qualify. On the other hand, Midwest was conditionally qualified in this area, but, because of certain DOT reservations, its certificate was due to expire on June 15, 1987. However, Midwest requested a Section 120.57(1) hearing to contest this expiration date, and Midwest has, with DOT's acquiescence, continued to use its certificate for bidding purposes until an adjudication of the claim is made. Without a certificate of qualification, DOT rules provide that a contractor not be given bid documents that would enable it to submit a bid. Further, DOT witnesses confirmed that no bidder has ever been authorized to become prequalified after it had submitted a bid, nor has a nonqualified bidder been awarded a contract. The agency does have a "policy" of allowing contractors who are qualified in the major work class of minor bridge work (but who are not qualified in bridge painting) to receive bid documents on certain major projects. Even so, this policy, however applied in the past, has never been used on a project such as this, and DOT officials confirmed that this was the first time bid documents had been erroneously sent to a nonqualified bidder. DOT's Reaction to the Bids Through "inadvertence" or "error," DOT furnished bid documents to CCI. Thereafter, CCI, Midwest and a third contractor submitted bid proposals. When the bids were opened, DOT discovered that the lowest dollar bidder (CCI) had not been prequalified on bridge painting. The bids were then routed to the DOT technical review committee, a five person committee that reviews projects where the bids do not conform with award criteria. This committee made no recommendation and was "uncommitted." The matter was then reviewed by the DOT awards committee which unanimously recommended that the contract be awarded to CCI even though it had not prequalified on one segment of the work. In proposing that the contract be awarded to CCI, DOT acknowledges that this is not its normal practice. Indeed, it concedes that this is probably the first occasion that it has proposed to award a contract to a nonqualified bidder. However, it considers the project "unique" in the sense that the bridge will be turned over to DNR immediately after the work is completed. In addition, by using CCI, it can save around $624,000 in state funds which can be used to claim almost another $6 million in matching federal funds for other state work. Finally, DOT is fully satisfied that CCI is capable of performing the work on the project, particularly since it considers the structural repairs the most important aspect of the job. If CCI's bid is rejected, DOT's preference is to reject all bids and relet the project. The agency's nonrule policy is that, for projects valued at more than $250,000, a contract will be awarded if the lowest bid is no more than seven percent above DOT's estimate of the project's value. In this case, both CCI and Midwest submitted bids below DOT's budget and preliminary estimates. The Bidders Midwest, which is located in Tarpon Springs, Florida, has been in the bridge painting business for many years, and has worked on DOT projects since 1974. This is the first occasion the firm has filed a protest. The firm is capable of performing the required work. Although its certificate of qualification was supposed to expire on June 15, or before the June 24 bid opening day, Midwest challenged this action and the certificate continues to be used for bidding purposes. The apparent low bidder (CCI) is located in Tampa, Florida and has been engaged in a number of DOT projects since it was formed approximately five years ago. It is now working on three other DOT bridge projects. The firm was prequalified in the bridge painting class in 1983 and 1984, but for some reason, allowed its qualification to lapse. Its present certificate is valid until April 30, 1988 and qualifies CCI to bid on several types of major bridge projects. CCI stands by its bid proposal, and is fully confident the work can be done for $600,000 less than proposed by Midwest. The firm has access to the necessary equipment and manpower to perform the job.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a Final Order be entered rejecting the bid of Cone Constructors, Inc. on the ground it was unqualified and non-responsive, and instead awarding the contract on State Job 90030-3539 to Midwest Industrial Painting of Florida, Inc., which submitted the lowest responsive bid. DONE AND ORDERED this 15th day of September, 1987, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of September, 1987.

Florida Laws (6) 120.57120.60120.68337.11337.1435.22 Florida Administrative Code (3) 14-22.00214-22.00314-22.008
# 5
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs GERARD ALSIEUX, 18-000375 (2018)
Division of Administrative Hearings, Florida Filed:Brooksville, Florida Jan. 19, 2018 Number: 18-000375 Latest Update: Jul. 02, 2024
# 6
SPIVEY UTILITY CONSTRUCTION COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 02-000286 (2002)
Division of Administrative Hearings, Florida Filed:Odessa, Florida Jan. 18, 2002 Number: 02-000286 Latest Update: May 20, 2002

The Issue Whether Petitioner's application for certification as a minority business enterprise should be granted.

Findings Of Fact Based upon the testimony and evidence received at the hearing, the following findings are made: Spivey Utility is an active for-profit Florida corporation headquartered in Odessa, Florida. The company was formed in August 1986. Sandra Spivey (Mrs. Spivey) provided the initial capital for the company in the amount of $500. Since 1986, the company has grown significantly. Its gross revenues for 2001 were over $11 million. At the time Spivey Utility was formed, Mrs. Spivey was a full-time school bus driver and her husband worked for another excavating company. Between 1986 and 1991 (when she retired from school bus driving), Mrs. Spivey devoted several hours each weekday to running Spivey Utility, and on the weekends she worked as "grunt" (e.g., carrying conduit) for her husband on job sites. Since 1991, Mrs. Spivey has devoted all of her time to running Spivey Utility. The company currently employs 170 people, but it is still a "family business." All of the outstanding stock of Spivey Utility is owned by Mrs. Spivey and her five children. Mrs. Spivey is a white female. She owns 51 percent of the company's outstanding stock. Her daughter Collette Lazar (Ms. Lazar) is also a white female, and she owns ten percent of the company's stock. Thus, white females collectively own 61 percent of the outstanding stock of Spivey Utility. These ownership percentages have not changed since the stock was first issued in October, 1986. Mrs. Spivey's sons, all white males, own the remainder of the stock in the following percentages: Jim Spivey (15 percent); Steve Spivey (ten percent); Daniel Spivey (seven percent); and Tim Spivey (seven percent). Mrs. Spivey's husband, Verlyn Spivey, does not own any of the corporation's stock. The Schedule K-1 tax returns of Mrs. Spivey, Ms. Lazar, and Mrs. Spivey's sons demonstrate that their shares of the company's income is commensurate with their ownership percentages. Mrs. Spivey is the president and chief executive officer of Spivey Utility. She is also a member of the board of directors. Ms. Lazar is secretary of the company. She is also a member of the board of directors. Spivey Utility's bylaws provide that "[t]he business affairs of the corporation shall be managed by its board of directors." Bylaws at Article III, Section 1. Accord Section 607.0802. The bylaws further provide that the president shall supervise and control all of the business affairs of the corporation "subject to the control of the directors." Bylaws at Article IV, Section 5. The board of directors has seven members. In addition to Mrs. Spivey and Ms. Lazar, the board consists of Mrs. Spivey's husband and her sons. Thus, five members of the board are white males and only two members are white females. Five (of seven) directors are required for a quorum of the board of directors. As the holder of more than 51 percent of the company's outstanding stock, Mrs. Spivey has the authority under the bylaws to remove any of the directors and replace them with persons of her choosing. See Bylaws at Article II, Section 9 (stockholders entitled to one vote per share and directors elected by plurality vote); id. at Article III, Section 9 (directors may be removed with cause by the board or stockholders and without cause by the stockholders). However, Mrs. Spivey testified at hearing that she had no intention of removing her children as directors because Spivey Utility was a "family business." Over the years there have been disputes among the board members regarding company policy but, in the end, Mrs. Spivey always made the final decision. She testified that her final decision has never been overruled by the board and testified that she could not conceive of it ever happening. She further testified that, if it ever came down to it, she would overrule the board's decision overruling her through her ownership of the majority of the company's stock. Similarly, Ms. Lazar testified that Mrs. Spivey makes the final decisions, despite what the board might want to do because she owns the most stock. Spivey Utility is in the underground excavating business. Its articles of incorporation describe the nature of its business as "engag[ing] in all activities relating to the installation and maintenance of telephone cable and conduit." Articles of Incorporation, at Article II.a. Similarly, paragraph 8 of the MBE application described the nature of the company's business as "[u]nderground utilities, install manholes, place conduit, pull cable, fiber optic, directional boring, trenching & conventional boring." The largest portion of Spivey Utility's business is installing underground cable and conduit for telecommunications companies and utility providers such as Verizon and Tampa Electric Company. The company also has a water and sewer division which installs water and sewer lines, as well as a site preparation division which clears land for development. The water and sewer and site preparation divisions constitute only ten percent of the company's business. The company does not install or hook up "hot" wires, i.e., wires which are electrically charged. It only installs empty conduit and "cold" wires. The underground excavating work conducted by Spivey Utility does not require extensive technical training. At hearing, it was described as "glorified ditch digging." Mrs. Spivey's sons supervise the field operations of the various divisions within the company, and her husband oversees the bidding and contract work done by the company. Ms. Lazar provides administrative support for the corporation. Mrs. Spivey's sons each have more than 20 years of experience in the underground excavation industry. Her husband has almost 50 years of experience in the industry. Despite the delegation of supervisory authority of the field work to her sons, Mrs. Spivey remains actively involved in the day-to-day operations of the company. She is in direct communication with her sons on a daily basis to ensure that they have all of the equipment and resources they need to perform their work. They come to her when they need additional resources. Mrs. Spivey is 67 years old, but she is still comes to the office on a daily basis. She spends most of her time in the office dealing with financial matters and overseeing work in the shop where equipment is serviced and repaired. She generally does not spend time in the field, although she has done so when necessary. Mrs. Spivey has the authority to hire and fire employees and she has done so when necessary. She has also shifted employees, including her sons, from one division of the company to another to enhance the company's operation. Mrs. Spivey controls all of the financial aspects of the corporation. Her signature is required on all contracts to bind the corporation, including bids prepared by her husband or sons. Neither her sons nor her husband has the authority to bind the corporation. No financial decisions are made without Mrs. Spivey. The company's CPA testified that Mrs. Spivey is the only person in the company that has expertise in financial matters. Mrs. Spivey is the sole personal guarantor for Spivey Utility's lines of credit, indemnity agreements, and bonding line. Mrs. Spivey and Ms. Lazar sign nearly all of the checks written by the corporation out of the company's primary account with Sun Trust Bank. The authorized signatories for that account include, in addition to Mrs. Spivey and Ms. Lazar, Mrs. Spivey's sons: Steve Spivey, Daniel Spivey, Jim Spivey, and Tim Spivey. Only one signature is required on that account; no countersignature is required. The purpose of the sons being signatories on the account was for convenience in the event Mrs. Spivey or Ms. Lazar was unavailable. Although there is no formal limitation with the bank on the authority of Mrs. Spivey's sons to write checks in any amount, the evidence shows that the sons "know better" than to write checks for amounts in excess of $1,000 or so. It was apparent from her testimony that Mrs. Spivey has a keen understanding of the business operations of the company. Although she does not, and has never, performed the excavating work done by the company, she has been in the field to watch the work. She was able to explain and distinguish between the various types of excavating done by the company (e.g., jack and bore, directional boring, etc.) as well as the process and purpose of de-watering soil. She was also able to explain and discuss changes in the industry, including the need for specialized equipment and increased liability insurance when laying fiber optic cable. Mrs. Spivey's testimony also demonstrated her understanding of the company's operations. She is intimately familiar with the various divisions of the company and the services they perform and the clients they serve. Similarly, she demonstrated her familiarity with equipment and inventory of the company, such as the type, number, and cost of trucks, backhoes, and boring equipment owned by the company. Mrs. Spivey gained her knowledge of the excavating business from her husband who has been in the business for almost 50 years. As noted above, in the early years of the company, Mrs. Spivey often accompanied her husband on the job- site and assisted him as a "grunt" on the job. Spivey Utility has a certificate of authority from the CILB. The certificate is not a license to perform work. It only allows the company to do business if it has a qualifier. Spivey Utility has two qualifiers, Robert King in the areas of underground excavating and pollutant storage and Robert Burns in electrical. Neither of those individuals is a member of the Spivey family nor are they owners, officers, or directors of Spivey Utility. Spivey Utility obtained the certificate of authority when its water and sewer division was formed three years ago. Prior to that, Spivey Utility did not hold any state licenses or certificates. Neither Mrs. Spivey nor Ms. Lazar is registered or certified as a contractor by the CILB. Mrs. Spivey does have a commercial driver's license which authorizes her to drive vehicles, which weigh up to 26,000 pounds, including some of the company's dump trucks. The Department did not perform an on-site investigation of Spivey Utility in connection with its review of the company's MBE application. The Department's decision to deny the application was based solely on the information presented by Spivey Utility with its application and the supplemental information it provided on August 2, 2001, pursuant to the Department's request. The résumés included with Spivey Utility's MBE application and the supplemental job descriptions provided in the August 2, 2001, letter are not comprehensive and do not fully reflect Mrs. Spivey's understanding of or control over the management and daily operations of the company.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department issue a final order which grants Spivey Utility's application for certification as a minority business enterprise. DONE AND ENTERED this 18th day of March, 2002, in Tallahassee, Leon County, Florida. T. KENT WETHERELL, II Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of March, 2002.

CFR (1) 47 CFR 68 Florida Laws (15) 119.07120.569120.57120.60287.0943288.703489.105489.113489.119489.503489.505607.0732607.0802607.0808607.0824
# 7
BERGERON LAND DEVELOPMENT, INC., AND CAPELETTI BROTHERS vs. DEPARTMENT OF GENERAL SERVICES, 82-002705 (1982)
Division of Administrative Hearings, Florida Number: 82-002705 Latest Update: Jun. 01, 1990

Findings Of Fact On June 21, 1982, DGS issued specifications and contract documents as a basis for competitive bidding on a building construction project entitled "Rough Site Preparation and Grading for a Reception Center and Correctional Institution, Dade Co., Project No. DC-8037/8135," for the State of Florida, Department of Corrections. The specifications and contract documents were prepared by DGS' consulting architect/engineer ("A/E") Paragraph B-10 of the specifications provided that requests for correction or interpretation of the meaning of drawings and specifications or other bidding documents should be in writing, addressed to the A/E, and that all such interpretations and supplemental instructions would be in the form of written addenda to the bidding documents. In addition, subparagraph B-3 of the specifications for the project provided that each ". . . bidder is required to be familiar with all Federal, State and Local laws, ordinances, rules and regulations that in any manner affect the work. Ignorance on the part of the bidder will in no way relieve him from responsibility." Further, subparagraph B- 11 of the specifications provides as follows: Bidders are required, before submitting their proposals, to visit the site of the proposed work and completely familiarize themselves with the nature and extent of the work and any local conditions that may in any manner affect the work to be performed and the equipment, materials and labor required. They are also required to examine carefully the Drawings, Specifications and other Bidding Documents to inform themselves thoroughly regarding any and all conditions and requirements that may in any manner affect the work. By letter of July 6, 1982, Capeletti, as a prospective bidder, called to the attention of the A/E that an existing road near the north boundary of the property on which the project is to be constructed, which was designated on the site location plan drawing as Northwest 41st Street, was not a public road, but was, instead, a private road on private property. In fact, the road depicted as Northwest 41st Street on the plans and specifications is owned by Florida Power and Light Corporation, and has not been dedicated for public use. Capeletti has been granted an exclusive right-of-way by Florida Power and Light Corporation for use of that road. A fence with a gate installed by Capeletti at some time in the past blocks access to the road, and a sign on the gate advises visitors that the roadway is under private ownership. In its letter to the A/E Capeletti inquired whether another access road would be provided to the bidder ultimately awarded the contract. The A/E did not issue a written addendum in response to Capeletti's letter, nor were any prospective bidders notified in writing by the A/E of the absence of a public access road. Both Bergeron and Capeletti submitted bids on the project. Bids were opened on July 14, 1982, and the apparent low bidder was Bergeron, whose bid totaled $1,985,000. The amount of the second lowest bid was $2,390,000, and Capeletti's bid totaled $2,565,000, or $585,000 more than Bergeron's bid. The estimated DGS project budget for this project was established at $2,400,000 prior to the opening of the bids. Bergeron's bid was, therefore, $415,000 below the DGS estimate of the cost to do the project. By letter dated August 19, 1982, DGS gave notice to all bidders of its intent to award the contract to Bergeron. Within 72 hours after receipt of DGS' notice, Capeletti filed a Notice of Protest pursuant to Section 120.53(5), Florida Statutes, and within ten days thereafter filed its Petition for Formal Hearing. Capeletti's petition requested that the contract be awarded to Capeletti, since it was the only bidder having legal access to the project site, or, alternatively, that all bids be rejected and the project rebid. By letter dated September 22, 1982, DGS notified Bergeron and Capeletti that it was rejecting all bids, and further advised them that: We have determined that the specifications contained a mistake of material fact concerning access to the job site. Although there is no public road adjacent to the site and the state did not otherwise have access, the drawings indicated that a public street, Northwest 41st Street, adjoined the site on our north boundary. This was a misleading representation. When access is obtained, it may be at a different location and may affect the amount of the bid. The Department desires to give bidders an equal opportunity to bid on the project with knowledge of the access location after it is obtained. The Department proposes to rebid the project in the near future, combining the rough site preparation and the buildings into a single project, and you will be notified of the date when' specifications will be available. (Emphasis added.) After receipt of the DGS letter of September 22, 1982, Bergeron timely filed a Notice of Protest and its Petition in this cause, protesting the rejection of bids. The Capeletti and Bergeron petitions were consolidated for hearing purposes and for entry of a Recommended Order in this proceeding. Subparagraph B-22 of the specifications, entitled "Rejection of Bids," provides as follows: The Owner reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the proposal of a bidder who the Owner determines is not in a position to perform the Contract. . . At the time bids for the proposed project were invited, opened and rejected, there was no existing public road that contractors could use to gain access to the building site, and there was no private road adjacent to the state-owned property. That situation remained the same at the time of final hearing in this cause on October 25, 1982. DGS apparently knew, however, prior to the filing of Capeletti's protest that there was no public access to the job site. The DGS Chief of Construction for the Bureau of Construction testified that, prior to the filing of the Capeletti protest: . . . it was my understanding that the Department of Corrections had worked with . . . [Dade] county, and the county was going to provide the access and make arrangements for the access along the road designated as the Florida Power and Light private road and the A. J. Capeletti private road and along Northwest 41st Street. As required by the contract documents, Bergeron, prior to submitting its bid, visited the site of the proposed project and observed the aforementioned gate blocking what was delineated on the project drawings as an extension of Northwest 41st Street. Upon further inquiry, Bergeron determined that the roadway depicted on the project drawings as an extension of North West 41st Street adjacent to the north boundary of the project was in fact not publicly dedicated. As a result, Bergeron, in formulating and submitting its bid, contemplated the construction of a temporary haul road of approximately 4,200 feet in order to access the project site. Bergeron apparently factored into its bid amount approximately $155,000 to $160,000 for the cost of building this temporary haul road. The project specifications did not call for the construction of either a temporary or permanent access road into the project area. Bergeron does not have definitive plans for the location of any such temporary haul road, and has indicated only that it would attempt to obtain permission from adjacent private property owners to use their property for that purpose. There is no evidence of record in this proceeding from which it can in any way be concluded that such an arrangement cannot be accomplished. The State of Florida, Department of Corrections, is under a federal court mandate to have the entire facility, of which this contract is merely a part, available for use in the near future. There is, however, no evidence of record from which the exact date of such required availability can be determined, nor any indication that accepting Bergeron's bid would adversely affect that availability. The contract documents provide for delay damages payable to the contractor in case of a delay for reasons other than changes in the work of 10 percent of the contract price per day, divided by the number of days in the contract period. One of the reasons advanced by DGS for rejecting all bids is that failure to do so could result in claims for damages by Bergeron in the event of any delay in obtaining access to the job site. This fear would seem unfounded for two reasons. First, although the contract is a 150-calendar-day contract, the contract time does not begin to run until DGS issues a Notice to Proceed. No contractual provision sets an exact time in which any such notice should issue. Accordingly, it may well be that either DGS or Bergeron can solve any access problem before issuance of the Notice to Proceed. Secondly, Bergeron submitted its bid with full knowledge that there was no public access available, planning instead to furnish its own method of accessing the site. Indeed, Bergeron still contended in this proceeding that it was willing to perform the obligations of this contract at the price it had bid, including providing its own access to the site. Under these circumstances, it would seem improbable that any claim for delay concerning access could be deemed meritorious. The contract drawings show an entrance road running in a north-south direction from the buildings to be constructed on the project site to the northern boundary of the property. The bid drawings show the length of the entrance road to be built on the site as actually 103 feet less than will be necessary to join that access road to any improved roadway which would run east- west to connect with the current termination point of North West 41st Street. There is no showing in the record that this discrepancy in the plans in any way affected the amount of any bid on the project, and, as such, is not considered to be a "material error. DGS has also contended that re-letting the bids on this project may result in a cost-saving by combining with it certain other portions of the overall project. Only one witness was offered by DGS on this point, and his testimony regarding potential cost-savings is not persuasive, primarily because it appears to be based entirely on speculation, and was offered without any record showing of design criteria for any such revised project upon which to base such a conclusion. The testimony in this case reveals that DGS has been involved in siting and designing this project since 1974. DGS has failed to establish that it is in the best interest of the State of Florida, at this late date, to reject a bid that was directly responsive to the bidding documents, in an amount $415,000 below DGS' own project estimate, on the basis of speculation that some apparently hypothetical change in project plans might possibly result in a cost- saving.

Florida Laws (2) 120.53120.57
# 8
ANNELLE AND JUDSON WEST vs JACK RATKOVIC AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-006363 (1989)
Division of Administrative Hearings, Florida Filed:St. Augustine, Florida Nov. 22, 1989 Number: 89-006363 Latest Update: Jun. 19, 1990

Findings Of Fact Petitioners Kayla and Eric Douglas in DOAH Case No. 89-6367 failed to appear or send a qualified representative on their behalf to formal hearing, and, accordingly, their petition is subject to dismissal, pursuant to Rule 221- 6.022 F.A.C. Applicant Ratkovic owns two adjacent rectangular-shaped pieces of property, Lots #5 and #6, located at 19 Magnolia Drive, within the city limits of St. Augustine, Florida. These lots are bounded on the north by Oceanway Street, a dirt road, and on the east by Magnolia Drive. The Ratkovic house is located on the lot which directly abuts Magnolia Drive (Lot #6). Lot #5 is immediately to the east of Lot.#6 and is separated from it by a ten-foot wide alleyway. Oceanway Street deadends into Salt Run, a Class III Water of the State, which is next to Lot #5. Lot #5 is 55 feet wide in a north-south direction and 82.5 feet long in an east-west direction. Lot #5 is completely within the landward extent of Salt Run. Lot #5 may be cnaracterized as a flat, intertidal sand beach and DER's jurisdiction with respect to it extends to the ordinary mean high water line. Salt Run is an embayment off of the Atlantic Ocean which, with the help of a concrete artificial groin, forms a cove in the vicinity of the proposed project. Water flow in the cove is serene enough to allow a tidal marsh to grow along parts of the shoreline of the cove, but there are still two areas of the cove in which no vegetation grows: waterward of Applicant's property and waterward of the property of Petitioners Steger (DOAH Case No. 89-6366). The Steger property is several lots south of the Applicant's property. Marine vegetation grows in the southeast quadrant of Lot #5 and to the north of Lot #5. The proposed project involves the placement of 19 pilings on 4'8" centers along the northern lot line of Lot #5. The proposed pilings would run on a line in the middle of the unvegetated area, approximately halfway between the two areas of tidal marsh growth, out to the waterward edge of Lot #5. 7. The Applicant desires a dock for Lot #5 and has already availed himself of the general permit provisions of Rule 17-312.808 F.A.C. The dock has not been constructed because he has been unable to obtain local approval for its construction. Respondents assert as a legal proposition that a 1,000 square foot (6 foot wide) piling-supported dock, if built on Lot #5, would be exempt from the requirement of obtaining a DER dredge and fill permit such as the one at issue here, and because of Respondents' assertion, it is one of Petitioners' concerns in this proceeding that the Applicant not be permitted to do by indirection that which he has been prohibited by local government (but not DER) from doing directly. However, that dock permit and those peripheral legal propositions need not be resolved in this proceeding for the reasons set out infra. The Applicant intends that the proposed pilings at issue here will serve as the northern support structure of his proposed dock, if local approval is eventually granted for the dock. However, without such local approval of his proposed dock, the Applicant's proposed pilings would still serve as a barrier to vehicular traffic which presently has unrestricted access across the beach and across his private property, Lot #5. The Applicant represented that he wants to install the pilings with or without the dock approval so as to prevent late night driving of cars on his beachfront property. Salt Run is full of docks, and this vicinity of Salt Run is the only area totally unobstructed by docks. This vicinity also has the only bottom area in Salt Run not encrusted with oyster or other bivalve shells. The only water quality standard to be impacted by the proposed project is turbidity. Turbidity results from the resuspension of bottom material and will occur briefly during the placement of the pilings. At the proposed project site, the bottom material is sand, which when resuspended, rapidly falls to the bottom and therefore has little environmental impact under the circumstances of this application. However, turbidity controls have been required by Specific Condition 4 of the DER Draft Permit. The foregoing factors assure that water quality standards will not be violated by the proposed pilings. The testimony of DER's agency representative, Jeremy Tyler, who was accepted as an expert in oceanography and the impacts of dredge and fill projects to wetlands and water quality, is accepted that because the proposed pilings will be located on a flat, intertidal sand beach, and because installation of the pilings requires appropriate turbidity controls, the placement of the proposed pilings will not generate turbidity sufficient to impact the tidal marsh, and, accordingly, their placement will not adversely affect the conservation of fish, wildlife, or their habitats. Similarly, it is found that fishing, marine productivity,- and the current conditions and relative value of functions being performed by the tidal marsh will not be adversely affected by the proposed project. The proposed project will not have any effects upon the public health, safety, or welfare, the property of others, or significant historical or archaeological resources. It will be permanent. The proposed project will not adversely affect the flow of water at the proposed site and will not cause harmful erosion or shoaling. Depending upon the time of the month, the time of the year, and the height of the tide, water could wash up to the landward side of Lot #5, or could leave the lot high and dry. Oceanway Street, the dirt road adjacent to the Applicant's property on the north, has historically been used by the neighbors and general public to drive down to Salt Run. These persons have used the cleared area between the tidal marsh sections described supra for wading, swimming, throwing of cast nets, and launching of boats and windsurfing boards. Because it is within the city limits, the area is also very attractive to those who just wish to stroll up the beach on a north-south tangent. In gaining access to the water of Salt Run, some persons have not differentiated between Lot #5, which is private property, and Oceanway Street. One reason for this lack of discernment seems to be that nearby Ingram Street, also a public access, is in such disrepair that prudent persons avoid it. Also, Applicant either built on Lot #6 or moved into the house on that lot only within the last few years, and while Lot #6 was formerly unoccupied, the neighbors and the public were free to walk dogs, moor and launch boats, and enjoy virtually all recreational activities in public areas and on Lot #5 with impunity. In essence, Lot #5 has been treated as a public beach. In the recent past, the Applicant's attempts to "run off" persons who have utilized his property in these ways have caused bad feelings in the neighborhood. Also, Lot #5 has been inadvertently used for recreation some of the time that it is covered with water, and this seems to be the source of some persons' confusion over where the Applicant's right to "run off" the public begins and ends; however, the evidence is insufficient to establish a public easement across Lot #5. If the proposed piling project were constructed, beach walkers, swimmers, or waders approaching one of the piles (and if local approval is obtained, ultimately the dock) might have to alter their course to avoid a collision. The 4'8" gap between pilings would allow this, but in the event a dock is installed, it might be more prudent to avoid the area altogether. Cast netters would have to alter their net throws so that their backswing or release would not intersect the position of a proposed piling and so that their nets would land along the line of the proposed pilings instead of on the pilings or dock. This could be done. Boaters and windsurfers, after placement of the proposed pilings, would have a far narrower area within which to launch and land their boats and boards. However, this narrowing would not preclude such launching or landing. Boats often start and end their journeys at docks, which, from a boat hull's perspective, are nothing more than a row of pilings. Windsurfing boards are approximately two feet at their widest. When a windsurfer capsizes in open water, he typically rights his board and starts anew. Here, if windsurfers do not wish to launch in the clear area remaining to the north of the last piling, which they could easily do, they would be able to walk their boards out to the last piling and start as they would in open water. The proposed pilings will make it more difficult to launch or land a windsurfing board, but it would not preclude such use of the water. There is also a public boat ramp at Lighthouse Park, the northern boundary of which is four blocks to the south and three blocks to the west of the proposed project site. Boaters or windsurfers who did not choose to use the end of Oceanway Street to obtain access to Salt Run would be able to use that location.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order Dismissing the Petition in DOAH Case No. 89-6367; Denying the Petitions in DOAH Case Nos. 89-6363, 89-6364, 89-6365, 89-6366, and 89-6368; and Granting the dredge and fill permit application as specifically conditioned by the Department of Environmental Regulation's Intent to Grant. DONE and ENTERED this 19th day of June, 1990, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of June, 1990. APPENDIX TO RECOMMENDED ORDER CASE NOS. 89-6363, 89-6364, 89-6365 89-6366, 89-6367, 89-6368 The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Petitioners Stegers' PFOF filed May 22, 1990: Paragraph 1: Sentences 1, 3, and 4: Accepted as fact, however, the degree of obstruction, the significance of recreational values within the applicable statutory balancing test, and the legal implications of that balance as contained in the Recommended Order more accurately reflect the record as a whole. Sentence 2: Accepted as modified to more accurately reflect the record as a whole. Sentence 5: Rejected as unproved. See what was proved and what was speculated in FOF 9 and 11 and COL 11. Paragraph 2: Rejected as not proved. Respondent DER's PFOF filed May 22, 1990: 1-16 Accepted as modified to more accurately reflect the credible, competent, substantial evidence of record as a whole. To date, no other PFOF have been filed. COPIES FURNISHED: Judson and Annelle West 4 Lighthouse Avenue Anastasia Island St. Augustine, Florida 32084 Virginia Quill Myers Mary Susanna Myers 322 Ponce de Leon Avenue Anastasia Island St. Augustine, Florida 32084 Ronald Asner 37 Magnolia Drive Anastasia Island St. Augustine, Florida 32084 Dan and Sue Steger 25 Magnolia Drive Anastasia Island St. Augustine, Florida 32084 Kayla K. and Eric Douglas 69 Lighthouse Avenue Anastasia Island St. Augustine, Florida Mary H. Acebal 32084 E. V. Acebal 10 Lighthouse Avenue Anastasia Island St. Augustine, Florida 32084 Mr. Jack Ratkovic Post Office Box 4482 St. Augustine, Florida 32085 William H. Congdon Assistant General Counsel, DER Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Florida Laws (2) 120.57267.061
# 9
BARRY ROBERTS AND GLORIA MEREDITH TRUST vs JULIA FONDRIEST AND STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION, 20-002473 (2020)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 26, 2020 Number: 20-002473 Latest Update: Jul. 02, 2024

The Issue The issue in these consolidated proceedings is whether the proposed single-family residential dock meets the requirements for a letter of consent for use of sovereignty submerged lands pursuant to chapters 253 and 258, Florida Statutes, and Florida Administrative Code Chapters 18-20 and 18-21, such that the Consolidated Regulatory Exemption and Letter of Consent for Department of Environmental Protection File No. 0319584-003EE, as amended on September 30, 2020, should be granted.

Findings Of Fact The Parties DEP is the state agency charged with regulating specified activities in state jurisdictional surface waters, pursuant to chapter 373, part IV, Florida Statutes. Additionally, DEP is charged with performing all staff duties and functions for the Board of Trustees of the Internal Improvement Trust Fund ("Trustees" or "Board") related to the administration of state-owned lands pursuant to chapter 253, including sovereignty submerged lands in aquatic preserves, pursuant to chapter 258. In this case, DEP is responsible for reviewing the application for the dock and issuing the Dock Approval that has been challenged in these proceedings. Fondriest owns the upland property riparian to the sovereignty submerged lands on which the Dock is proposed to be, at 1953 Long Beach Drive, Big Pine Key, Florida. She is the applicant for the Dock Approval that has been challenged in these proceedings. The Trust owns the upland property located at 1975 Long Beach Drive, Big Pine Key, Florida. This property is located immediately adjacent to, and west of, Fondriest's property. DeMaria and Appel own the upland property located at 1997 Long Beach Drive, Big Pine Key. This property is located two parcels west of Fondriest's property. Appel owns two other upland properties located on Long Beach Drive, neither of which is located immediately adjacent to Fondriest's property. Crilly is the holder of a marine turtle permit issued by the Florida Fish and Wildlife Conservation Commission ("FFWCC"), and she volunteers as a sea turtle monitor for the Long Beach Drive area of Big Pine Key. History of the Dock Approval and Notice of Agency Action As stated above, on December 10, 2019, DEP issued a regulatory general permit and letter of consent to Fondriest, approving the 2019 Approval, which was then proposed as an 800-square-foot structure for use as a pier for non-motorized vessels. There was no evidence presented that Petitioners received a clear point of entry to challenge DEP's proposed agency action issued on December 10, 2019, either through receipt of written notice by mail, or constructively through publication of notice of the proposed agency action in a newspaper or other publication medium. The Trust filed a Petition for Administrative Hearing on January 30, 2020; DeMaria filed a Verified Petition for Formal Administrative Hearing on January 31, 2020; and Crilly filed a Verified Petition for Formal Administrative Hearing on February 27, 2020. On September 11, 2020, Fondriest filed a revised application with DEP, reducing the size of the Dock to 500 square feet; requesting a verification of exemption from permitting, pursuant to rule 62-330.015(5)(b) and section 403.813(1)(b)2; and requesting authorization, pursuant to chapters 253 and 258, and chapters 18-20 and 18-21, to use sovereignty submerged lands. On September 30, 2020, DEP issued Florida Department of Environmental Protection’s Notice of Proposed Changes to Agency Action—i.e., the "Dock Approval"— 2 Because the Dock will have less than 500 square feet of over-water surface area, it is exempt, pursuant to section 403.813(1)(b). from permitting under chapters 373 or 403. Petitioners have stipulated that the Dock qualifies for the permitting exemption under section 403.813(1)(b). verifying the regulatory exemption and authorizing the use of the sovereignty submerged lands by a letter of consent.3 DEP's agency action proposing to approve the Dock supersedes all prior DEP agency action with respect to the Dock, and constitutes the proposed agency action at issue in these proceedings. Long Beach Drive and the Surrounding Area Fondriest's property is located on Long Beach Drive, Big Pine Key, in Monroe County. Long Beach Drive is located on a spit of land comprising the southern and westernmost part of Big Pine Key. The south side of Long Beach Drive, where Fondriest's, the Trust's, and DeMaria's and Appel's properties are located, borders the Straits of Florida.4 Thus, Fondriest's, the Trust's, and DeMaria's and Appel's properties are riparian to sovereignty submerged lands underlying the Straits of Florida. The land along Long Beach Drive is platted and has been developed for residential and commercial uses. The Long Beach Drive area of Big Pine Key is located within the Coupon Bight Aquatic Preserve ("CBAP"), an Outstanding Florida Water and aquatic preserve consisting of approximately 6,000 acres of bays, mangrove forests, seagrass beds, and offshore patch coral reefs. The Long Beach Drive area, including Fondriest's property, is characterized by a rocky shore, with some narrow sandy beaches. The shore accumulates a significant amount of weed wrack consisting of seaweed, seagrass, and other debris. A beach berm created by wave and tide action 3 The Dock Approval states that the Dock does not qualify for the federal State Programmatic General Permit for section 404 of the Clean Water Act and section 10 of the Rivers and Harbors Act. Separate federal approval for the Dock has been issued by the Army Corps of Engineers, and Monroe County has issued a Building–Floodplain–Development Permit for the Dock. 4 All references to the shore or shoreline along Long Beach Drive refer to the shore or shoreline abutting the Straits of Florida. exists along much of the shore. The berm is frequently overtopped by water during high tides and storms. The beach is disturbed due to frequent use by residents and sea turtle monitors. Among the activities that take place on the beach are kayak launching, beach walking, beach cleaning and restoration, vegetation planting, and sea turtle nest monitoring. Several docks already exist along the shore on Long Beach Drive. The longshore current along the shore at Long Beach Drive flows, and transports sand from, east to west. The existing mangroves, jetties, and points along the Long Beach Drive shoreline trap sand and cause accretion of updrift beaches and starvation of downdrift beaches. The competent, credible evidence establishes that the docks along the shoreline on Long Beach Drive do not significantly contribute to beach accretion, starvation, or erosion in the area. The Proposed Dock The Dock is a private residential single-family dock associated with Fondriest's single-family residence at 1953 Long Beach Drive. It will not be used for commercial purposes or residential habitation, and there are no boat houses, boat lifts, or other enclosures proposed or approved as part of the Dock. As approved, the Dock will occupy 498 square feet, consisting of a 142-foot-long by 3-foot-wide access dock and a 12-foot-long by 6-foot-wide (i.e., 72-square-foot) terminal platform, and extending a total length of 154 feet. The access dock will be constructed with pressure-treated lumber planks spaced half-an-inch apart, to allow light penetration. The supporting pilings are comprised of PVC-encased aluminum, spaced approximately 9 feet, 5 inches apart. The PVC casing will help protect the piles from corrosion, thus helping to protect water quality. The terminal platform, which also will be supported by PVC-encased aluminum pilings, will consist of fiberglass grating, which allows sunlight penetration in order to prevent shading of seagrasses and other benthic resources.5 The top of the terminal platform is designed to be a minimum height of five feet above the mean high water line ("MHWL"). Handrails will be constructed along each side of the dock for its entire length, to prevent vessel mooring in adjacent shallow areas, thus helping protect against damage to benthic resources. The Dock will be used solely for the water-dependent activities of launching vessels and swimming. Only non-motorized vessels, such as kayaks, canoes, and paddleboards, may be launched from the Dock, and then only when there is a minimum depth of 0.5 feet (six inches, or half-a-foot) of water at the terminal platform.6 Additionally, the terminal platform must include signs of at least one-square- foot each placed on each side of the platform, stating "no mooring of motorized vessels allowed." A ladder is proposed to be located on one side of the terminal platform to provide access to the water for swimming or kayak launching, and the Dock Approval imposes a requirement that the ladder cannot be located over seagrass or hard bottom benthic communities. Although some turbidity in the water column may be generated by launching kayaks or other non-motorized watercraft from the terminal platform, the turbidity would be temporary and would not exceed that currently generated by dragging or hauling a kayak or other vessel from the shore across the substrate, to access sufficient water depth for launching. To prevent potential trapping, under the Dock, of sea turtles and other animals, such as Key Deer, an enclosure consisting of barriers one inch apart must be constructed beneath the portion of the Dock's landward access ramp having less than three feet of clearance above grade. 5 This is a standard construction material frequently used for docks in Florida. As further discussed below, the benthic survey performed for the area comprising the footprint of the Dock showed that no seagrass beds or other significant benthic resources are present. 6 The 0.5-foot water depth is keyed to the mean low water datum. At mean high water, the water depth at the terminal platform is approximately 1.2 feet. The competent, credible evidence establishes that the rest of the Dock will be elevated approximately five feet above the MHWL, so will be of sufficient height to allow animals to pass under without being trapped or impeded, and will provide sufficient clearance for sea turtle monitors to pass under as they traverse the beach. The competent, credible evidence also shows that the Dock will not impede the flow of water. The design is such that there are no structures on, or beneath, the Dock that will act as dams to prevent, or otherwise affect, the flow of water under and around the Dock. The water depth at the end of the terminal dock is 0.5 feet at mean low water, and 1.2 feet at mean high water. The Dock does not extend out to a depth of four feet of water. The competent, credible evidence establishes that the Dock will not interfere with navigation. The water depth between the shore and the end of the Dock's terminal platform is too shallow to accommodate motorized watercraft, and the Dock will be of sufficient height to enable persons using non-motorized watercraft to pass under it. The Dock will be constructed to meet the 2017 Southern Building Code, so will be able to resist 180-mile-per-hour, three-second wind gusts. The credible, persuasive evidence establishes that in a storm, the decking and stringers on the Dock will be washed off the pilings and will not become windborne projectiles. The Dock pilings will be imbedded into the substrate to a minimum depth of five feet, using a vibration hammer, rather than drilling and punching the pilings into the substrate. Using a vibration hammer will generate less turbidity in the water column than using the drill-and-punch installation technique, and turbidity curtains must be erected and maintained around the construction footprint to control turbidity and protect water quality. Additionally, the pilings will be installed using a spud barge elevated above the substrate, which also will help reduce turbidity during construction. Any turbidity generated during construction will be temporary. Installing the dock pilings using a vibration hammer also will generate less noise than the drill-and-punch technique. The Jacksonville Office of the National Marine Fisheries Service has issued a biological opinion stating that the vibration hammer installation technique "may affect/is not likely to affect" certain species listed as endangered, threatened, or of special concern. Additionally, because the Dock will be constructed in an open waterbody, the noise generated by piling installation is anticipated to be insignificant. Construction of the Dock may only be conducted outside of sea turtle nesting season, which runs from April 15 to October 31. Dock construction activities also must meet the requirements and standards established by the United States Fish and Wildlife Service to protect manatees, sea turtle species, the Smalltooth Sawfish, and the Eastern Indigo Snake. The 2011 Standard Manatee Construction Conditions for In-Water Work require vessels to navigate at slow speeds; manatee awareness signs to be posted; and construction to stop if a manatee is spotted within 50 feet of the construction site. In any event, manatees are unlikely to be present in the vicinity of the Dock, due to the very shallow water. The sea turtle and Smalltooth Sawfish construction conditions require vessels to operate at idle speeds in the vicinity of the project; turbidity curtains to be erected and maintained; and construction to be stopped if individuals of these species are observed within 50 feet of the construction site. The Eastern Indigo Snake, an upland species, is unlikely to be present at the Dock construction site. To prevent harm to individuals of this species, the letter of consent requires that educational materials be distributed to the construction crew and educational signs be placed at the construction site. No permanent exterior lighting is authorized for the Dock. This will prevent the Dock from attracting sea turtles and other marine species that are drawn to light. No turning basins, access channels, or wave break devices are proposed to be constructed for or used by the Dock. Fondriest's property has approximately 100 linear feet of riparian shoreline. There are no other docks existing on the shoreline along Long Beach Drive for at least 65 linear feet in either direction. The Dock will be constructed perpendicular to the shoreline, and will be located in Fondriest's riparian area, set back more than 40 feet from each riparian line demarcating her riparian area. Thus, the Dock will be located well outside the 25-foot setback from each riparian line. Biological and Other Resources in the Vicinity of the Dock Much of the shoreline along Long Beach Drive below the MHWL, including that along Fondriest's property, consists of bare, hard rock. The water is extremely shallow, and the bare rock is exposed at low tide. Site assessments conducted in 2020 at the location and in the vicinity of the Dock, show that limestone caprock, loose rubble, and some deeper depressions in the rock exist in the footprint of the Dock. The substrate consists of hard, highly uneven rock, with pools of tannin-stained water. Water pooled in the rock depressions is heated at low tide and, due to rotting vegetation, is nutrient-rich. The dissolved oxygen levels are very low, rendering the pools incapable of supporting substantial marine life other than cyanobacteria and filamentous algae, both of which indicate poor water quality. Some algae species are attached to the limestone caprock in the footprint and immediate vicinity of the Dock. However, recent biological resource assessments show that no seagrass beds, corals, or other hard bottom communities exist in the footprint of the Dock. Thus, the competent, credible evidence shows that there are no aquatic resources of any significant value in the footprint, or immediate vicinity, of the Dock. A small seagrass bed is located near the terminal platform. The letter of consent requires avoidance of this seagrass bed during construction and use of the Dock. Additionally, as discussed above, turbidity curtains must be installed to prevent turbidity and siltation of this seagrass bed during construction. The evidence establishes that the area waterward of the MHWL along Long Beach Drive generally supports a rich aquatic community. Fish and aquatic invertebrates inhabit the water in the vicinity, and numerous bird species use the area waterward of the MHWL, including that bordering Fondriest's property, as feeding and foraging habitat. However, no non-speculative evidence was presented to show that the construction, presence, and use of the Dock will result in adverse effects to this aquatic community, or to any plant or animal species in this aquatic community. Additionally, the competent, credible evidence shows that none of these resources exist in the footprint, or immediate vicinity, of the Dock, and conditions have been imposed in the letter of consent to ensure that the construction and use of the Dock will not adversely affect these resources. To the extent that the vibration hammer installation of the pilings will result in noise that may cause fish, birds, and other animals to leave the area, that effect will be temporary and will cease when piling installation is completed. Although some benthic or attached species, such as seahorses, may be unable to leave the area, so may be subjected to noise stress, no persuasive, non-speculative evidence was presented showing that these species inhabit the area in the vicinity of the Dock. Thus, any alleged harm to these species is speculative. Because the Dock may only be used for nonmotorized vessels such as kayaks and canoes, use of the Dock will not generate noise or otherwise adversely affect the aquatic habitat waterward of the MHWL along Long Beach Drive. The Key Deer is listed as an endangered species. Key Deer traverse and forage along the shore at Long Beach Drive. No credible evidence was presented showing that the Dock would adversely affect the ability of Key Deer to traverse and forage on the beach on, or adjacent to, Fondriest's property. As discussed above, the Dock will be elevated waterward of the MHWL to approximately five feet above grade. The evidence showed that this height is sufficient to allow Key Deer to pass underneath without being impeded or trapped. No credible evidence was presented showing that the three-foot wide access ramp would interfere with Key Deer foraging or traversing along the beach. The competent, credible evidence establishes that the Loggerhead Sea Turtle and Green Sea Turtle, both of which are listed as endangered species, use the beach above the MHWL along Long Beach Drive, including the beach on Fondriest's property above the MHWL, for nesting. The FFWCC has determined, through its Florida Sea Turtle Nesting Beach Monitoring Program, that the shore along Long Beach Drive has a relatively low nesting density—i.e., within the lower 25% of nesting density values—for both of these sea turtle species. The evidence establishes that the Hawksbill Sea Turtle, Kemp's Ridley Sea Turtle, and Leatherback Sea Turtle do not use the beach along the Long Beach Drive shoreline for nesting. No competent, credible evidence was presented showing that significant sea turtle food sources are present in the footprint, or immediate vicinity, of the Dock. The competent, credible evidence does not show that the Dock will adversely affect the habitat value of the beach on Fondriest's property for sea turtle nesting, or that it will otherwise adversely affect nesting sea turtles and hatchlings. As previously discussed, an enclosure will be constructed under the access ramp to prevent nesting sea turtles and hatchlings from becoming trapped under the Dock. The competent, credible evidence establishes that the Dock will not adversely affect other protected species, including the Lower Keys Marsh Rabbit, the Keys Rice Rat, or the Mole Skink—none of which inhabit or use the marine/beach habitat present along the shore at Long Beach Drive. To this point, no evidence was presented showing that these species are, or ever have been, present on the beach at Long Beach Drive. Thus, no evidence was presented showing that the Dock adversely affect these species. The Dock will be Located in a Resource Protection Area 3 Areas within aquatic preserves are classified as Resource Protection Area ("RPA") 1, 2, or 3, for purposes of imposing restrictions and conditions on the use of sovereignty submerged lands, to protect discrete areas having high quality and transitioning habitat. The RPA 1 classification applies to areas within an aquatic preserve that have resources of the highest quality and condition. Areas classified as RPA 1 are characterized by the presence of corals, marine grassbeds, mangrove swamps, salt marshes, oyster bars, threatened or endangered species habitat, colonial water bird nesting sites, and archaeological and historical sites. The RPA 3 classification applies to areas within an aquatic preserve that are characterized by the absence of any significant natural resource attributes. The RPA 2 classification applies to areas within an aquatic preserve that are in transition, either having declining RPA 1 resources, or new pioneering resources within an RPA 3. Recent biological resource assessments conducted at the location of, and in the immediate vicinity of, the Dock show that no mangrove swamps, salt marshes, oyster bars, archaeological or historical resources, or colonial water bird nesting sites are present. As discussed above, although sea turtles nest on the beach along Long Beach Drive, this area does not constitute significant sea turtle nesting habitat, and there is no significant food source for adult or juvenile sea turtles in the vicinity of the Dock. Thus, the evidence shows that the Dock will not be located in an RPA 1. The biological resource assessments also showed that no transitioning resources are present at the location, or in the vicinity, of the Dock. The competent, credible evidence showed that current natural resource conditions at the site are the same as those that historically existed before Hurricane Irma struck the Long Beach Drive area in 2013. Thus, the evidence shows that the Dock will not be located in an RPA 2. Because there are no significant natural resource attributes or transitioning resources in the footprint and the immediate vicinity of the Dock, it is determined that the Dock will be located in an RPA 3.7 7 Some portions of the CBAP do contain seagrass beds, offshore coral patch reefs, and mangrove swamp communities, and provide habitat for protected species, including the Key Deer and colonial water birds, and, thus, merit an RPA 1 classification. By contrast, none of these habitats and conditions are present at the location, or in the vicinity, of the Dock. The definitions of RPA 1, 2, and 3 in rules 18-20.003(54), (55), and (56), respectively, refer to "areas within aquatic preserves" which contain specified resources types and quality. Fla. Admin. Code R. 18-20.004(54) through (56)(emphasis added). Additionally, rule 18-20.004(1)(a) provides that in determining whether to approve or deny a request to conduct an activity in an aquatic preserve, the Trustees will evaluate each request on a "case-by-case basis." See Fla. Admin. Code R. 18-20.004(1)(a)(emphasis added). These rules make clear that determining whether an activity will be located in an RPA 1, 2, or 3 necessarily entails a site-specific resource assessment to determine the type and quality of habitat, and the conditions present, at that specific site. As discussed above, the site-specific biological assessments conducted show that the Dock will be located in an RPA 3, and Petitioners did not present any site- specific evidence to rebut that classification. Cumulative Impacts Analysis In determining whether an activity proposed in an aquatic preserve may be approved, an analysis must be performed to determine the projected cumulative impacts of the activity. This analysis focuses on determining the impact of the proposed activity, combined with that of similar existing activities and similar activities currently under consideration for approval. See Fla. Admin. Code R. 18- 20.006. A cumulative impacts analysis performed by Fondriest's expert witness, Sandra Walters, showed that the Dock, in conjunction with similar existing docks and all other applications for docks that could be proposed for approval, will not result in adverse cumulative impacts to the aquatic resources in the CBAP. Walters's cumulative impacts analysis took into account both the acreage and linear footage of parcels within the CBAP for which a dock similar to the one at issue in this proceeding could be approved for construction. In performing a cumulative impacts analysis using linear feet of shoreline, Walters calculated a total of 19,357 feet, or 22.6 miles, of shoreline in the CBAP. Of this linear footage, approximately 7,500 linear feet of shoreline along Long Beach Drive and approximately 1,200 linear feet of shoreline along the ocean side of the Cook's Island portion of the CBAP are developable, for purposes of having the potential to be developed for a minimum-sized single-family residential dock similar to that proposed in this case. Walters's estimate is conservative, in that it included, as developable linear shoreline footage, parcels that likely could not be developed due to rate of growth, conservation easement, or other land use or environmental restrictions. Walters's linear footage analysis showed that approximately 5.7% of the entire CBAP shoreline possibly could be developed for construction of a perpendicular dock. Assuming that each of these docks is four feet wide—which is a valid assumption, using the four-foot maximum access dock width permitted under the aquatic preserves rules—a total of .23% of the shoreline would be impacted if a perpendicular dock was developed on each eligible parcel. Walters opined, credibly and persuasively, that this impact to the resources in the CBAP would be de minimis. In performing a cumulative impacts analysis on an acreage basis, Walters calculated that if a minimum-size single-family residential dock were developed on each of the 68 total developable lots within the CBAP, a total area of approximately 34,000 square feet, or approximately .013% of the acreage in the CBAP, would experience impacts similar to those created by the Dock. Walter credibly and persuasively opined that this impact to the resources in the CBAP would be de minimis. Walters used a conservative approach—i.e., projecting a realistic "worst case" scenario—in performing the cumulative impacts analysis. Specifically, she considered all parcels for which a minimum-size single-family residential dock reasonably could be proposed for approval in the future, rather than limiting her consideration of cumulative impacts to only those currently proposed for approval by the listed agencies. Additionally, she included impacts of similar dock projects for parcels that likely would not qualify for dock approval due to development restrictions. Thus, the cumulative impacts that Walters projected in her analysis are likely greater than the actual cumulative impacts of similar dock projects that reasonably can be anticipated to be developed in the area in the future. Petitioners presented the testimony of Michael Czerwinski regarding the cumulative impacts analysis required under the aquatic preserves rule for approval of an activity in an aquatic preserve. Czerwinski's analysis projected the potential cumulative impacts if every parcel along Long Beach Drive were developed with a minimum-size single-family residential dock, including the parcels on which development restrictions have been imposed such that they would not be eligible to be developed for a single-family residential dock. Based on this assumption, Czerwinski opined that such "buildout" along Long Beach Drive would result in a "cascading" or "nibbling" effect on the resources in the CBAP, and that there would be adverse impacts on sea turtle nesting habitat. Additionally, based on the unsupported assumption of maximum "buildout" of a single-family residential dock on every parcel along Long Beach Drive, Czerwinski projected that the resources within the entire CBAP would be adversely affected as a result of the cumulative impacts from approval of the Dock. Czerwinski's cumulative impacts analysis did not take into account the numerous parcels in the CBAP, including several on Long Beach Drive, that are unable to be developed for single-family residential docks due to conservation easements and local land development restrictions. As such, his analysis considered impacts which could not reasonably be expected to result in the Long Beach Drive area from approval of the Dock. Additionally, based on the unreasonable assumption of maximum dock buildout on every parcel on Long Beach Drive, Czerwinski projected adverse impacts to the entire CBAP as a result of the Dock. This analysis again failed to take into account that numerous parcels within the boundaries of the CBAP that are not located in the Long Beach Drive area also are under development restrictions that will prevent the construction of docks on those parcels. Czerwinski's analysis did not comply with the provisions of rule 18-20.005(1) and (3), which expressly limit the consideration of impacts to only those likely to affect the preserve and which reasonably could be expected to result from the proposed activity. For these reasons, Czerwinski's testimony regarding cumulative impacts as a result of the Dock was not credible or persuasive. As discussed above, Monroe County has issued a permit authorizing the construction of the Dock. This evidences that the Dock is permissible under the Monroe County local comprehensive plan. Additionally, as discussed in detail below, the Dock is an allowable use that is consistent with the CBAP Management Plan ("Management Plan"). As previously discussed, the competent, credible evidence establishes that there are no significant biological resources in the footprint, or in the immediate vicinity, of the Dock. Thus, the Dock will not cause the loss of beneficial biologic functions that would adversely impact the quality or utility of the CBAP. As previously discussed, the competent, credible evidence establishes that the Dock will not cause the loss of the beneficial hydrologic functions, either in the immediate vicinity of the Dock, or in the CBAP. As discussed above, the Dock will be a minimum-size single-family residential dock that will not adversely affect the quantity or flow of water. Accordingly, it is determined that the Dock will not have adverse cumulative impacts on the CBAP. Consistency with the CBAP Management Plan The Management Plan expressly identifies single-family private residential docks as an allowable use within CBAP, and specifies the standards that such docks must meet. Specifically, a dock may not extent waterward of the MHWL more than 500 feet or 20% of the width of the waterbody; must be designed to ensure maximum light penetration; the terminal platform may not be more than 160 square feet in area; and the access dock may not be wider than four feet. As discussed above, the Dock will comply with these standards. The Management Plan also delineates "management areas" within the CBAP, and describes resources and allowable uses within the different management areas. The Management Plan states that final determinations of allowable uses within a particular management plan are made by agency staff on a case-by-case basis. The sovereignty submerged lands along Long Beach Drive, out to a distance of 500 feet from shore, are designated as "Management Area SF/1." The sovereignty submerged lands bordering Fondriest's property are included within the Management Area SF/1. The resources included in Management Area SF/1 generally include grass beds, fringing mangroves, coral banks, coral heads, and hardbottom communities. However, as discussed above, the site-specific biological resource assessment surveys conducted on the sovereignty submerged lands bordering Fondriest's property showed that none of these resources are present at, or in the vicinity of, the Dock site. Furthermore, private single-family residential docks are expressly identified as an allowable use in the Management Area SF/1. Long Beach Drive is not a pristine, undeveloped shoreline. There are residences and some commercial uses along Long Beach Drive, with accessory uses such as seawalls, revetments, and private docks. The Dock is consistent with these existing uses and with the aesthetics of the shoreline on Long Beach Drive. Based on the foregoing, it is determined that the Dock is consistent with the CBAP Management Plan.8 Petitioners' Interests and Timeliness of Crilly's Petition The Trust's Interests The Trust owns a parcel of real property located at 1975 Long Beach Drive, immediately adjacent to, and west of, Fondriest's property. Barry Roberts and Gloria Meredith are the trustees of the Trust. 8 Rule 18-20.004(7) states, in pertinent part: "[t]he aquatic preserve management plans shall be used by [DEP] to preserve and restore the distinctive characteristics identified by the inventories for each aquatic preserve. The management plans for each aquatic preserve are available for guidance purposes only." Fla. Admin. Code R. 18-20.004(7)(emphasis added). Thus, to the extent a rule provision in chapter 18-20 conflicts with an aquatic preserve management plan, the rule controls. See Decarion v. Martinez, 537 So.2d 1083, 1084 (Fla. 1st DCA 1989)(an agency must follow its own rules). Neither Roberts nor Meredith, in their individual capacity, is a petitioner in these proceedings. Meredith testified that she and Roberts purchased the property at 1975 Long Beach Drive because of its location and the natural resources in the area, including the tide pool habitat in the rock depressions along the shore, and the animals that forage along, and inhabit, the shore. Meredith testified that she and Roberts both have a keen personal interest in, and use and enjoy, the natural resources along the shore at Long Beach Drive. They engage in bird watching; nature photography; kayaking; and observing nature, including Key Deer, birds, nesting sea turtles, and fish and invertebrates inhabiting tide pools in the rock depressions along the shore. After Meredith and Roberts purchased the property, they placed it in the Trust in order to preserve it, and its value as a residential property, for their children and grandchildren to enjoy in the future. Meredith and Roberts, as trustees of the Trust, have significant concerns about the aesthetic impact the Dock will have on the Trust property, particularly its impact on the view of the beach and the sunrise over the water. Meredith expressed her personal concern regarding the Dock's impacts on the biological resources at, and in the vicinity of, the Dock, and she also expressed concern that the Dock would interfere with her ability to safely walk along the shoreline. She testified that she was concerned that approval of the Dock would constitute a precedent, resulting in the construction of more docks and piers which would adversely affect the natural resources and the beauty of the beach. Meredith conceded that the Dock will be located within Fondriest's riparian area, will be set back more than 25 feet from the common riparian line, and will not cross the common riparian line into the Trust's riparian area. DeMaria's and Appel's Interests DeMaria is an original Petitioner in Case No. 20-2474, which is part of these consolidated proceedings, and Appel has moved to intervene and become a party to that case. DeMaria and Appel own the Deer Run eco-lodge bed and breakfast ("Deer Run") located at 1997 Long Beach Drive, immediately west of the property owned by the Trust. The Deer Run property is not located immediately adjacent to Fondriest's property. Appel owns two other parcels on Long Beach Drive, neither of which is located immediately adjacent to Fondriest's property. DeMaria testified that she and Appel purchased the Deer Run property because they were attracted to the unspoiled natural environment along Long Beach Drive. Deer Run attracts guests from around the world, who are drawn to the natural environment. These guests engage in nature photography and in-water recreational activities, such as kayaking, paddle boarding, and windsurfing; and they use and enjoy the natural resources and aesthetics of the area. DeMaria and Appel both testified that the presence of a long dock in close proximity to Deer Run would interfere with the view of the water and sunrise from Deer Run, and would significantly detract from the natural beauty and aesthetics of the environment at, and in the immediate vicinity of, Deer Run. Both testified that the presence of the Dock would render Deer Run a less attractive destination for guests. DeMaria testified that the presence of the Dock would interfere with her personal view of the water and the sunrise over the water; her ability to walk along shoreline below the MHWL; and her personal use and enjoyment of the natural beauty and aesthetics of the area. DeMaria also volunteers as a sea turtle nest monitor under the authority of Crilly's marine turtle permit. She expressed concerns similar to those expressed by Crilly—specifically, that the existence of the Dock would interfere with her ability to safely traverse the shoreline below the MHWL on Long Beach Drive to perform her sea turtle monitoring activities. Appel echoed DeMaria's concerns regarding the alleged injury to Deer Run's ecotourism business as a result of the Dock. He also testified that the presence of the Dock on Fondriest's property would injure his personal use and enjoyment of the natural beauty and aesthetics of the Long Beach Drive area. Appel also serves as a volunteer sea turtle monitor, and, in connection with that activity, traverses the shoreline along Long Beach Drive. He testified that the presence of the Dock would interfere with his ability to safely traverse the shoreline below the MHWL to conduct sea turtle monitoring activities. Appel also testified regarding the potential for the Dock to be damaged in storms, resulting in flying and floating debris that may damage his properties and the natural resources in the area. Crilly's Interests and Timeliness of Petition Crilly is the holder of a marine turtle permit issued by FFWCC, authorizing her to monitor sea turtle nesting along the beach at Long Beach Drive. Other volunteer sea turtle nest monitors work with Crilly under the authority of her permit. Crilly and her team of sea turtle monitors walk the beach daily during sea turtle nesting season. Crilly's responsibilities under the marine turtle permit include monitoring sea turtle nesting and false crawls; collecting data on the number of hatchlings that emerge from each sea turtle nest; and collecting data on sea turtle nesting mortality. The data are provided to the FFWCC for use in sea turtle research. Crilly testified that the Dock will impede her ability and that of her team to safely traverse along the shore below the MHWL to perform the sea turtle monitoring duties authorized under her permit. Specifically, Crilly testified that because the property above the MHWL is private, she must walk along the shoreline below the MHWL. The rock is slippery with numerous depressions, and traversing under the Dock would be treacherous. She testified that "I personally would not crawl under a dock and, therefore, I would not ask any of my volunteers on my team to crawl under a dock." According to Crilly, if she and her sea turtle nest monitoring team are unable to traverse the shoreline where the Dock will be located, they will be required to retrace their steps to the roadway on Long Beach Drive, walk down the road to a public access point, walk down to the beach, and walk back to the Dock, significantly increasing the time and effort to conduct their sea turtle monitoring activities. Crilly testified that she "learned of" DEP's approval of the Dock on December 30, 2019. No evidence was presented regarding whether, or how, Crilly received notice of the 2019 Approval sufficient to provide a clear point of entry for purposes of commencing the time for her to challenge that proposed agency action. Crilly filed her Petition challenging the 2019 Approval on February 27, 2020. When DEP issued the Dock Approval on September 30, 2020, superseding the 2019 Approval, Crilly already had filed her Petition at DEP, and the Petition had been referred to DOAH. IX. Findings of Ultimate Fact Regarding Compliance with Applicable Rules The term "dock" is defined in chapters 18-20 and 18-21. Chapter 18-20, applicable to aquatic preserves, defines a dock as "a fixed or floating structure, including moorings, used for the purpose of berthing buoyant vessels either temporarily or indefinitely." Fla. Admin. Code R. 18-20.003(19). Chapter 18-21, which generally governs approvals to use sovereignty submerged lands, defines a dock as "a fixed or floating structure, including access walkways, terminal platforms, catwalks, mooring pilings, lifts, davits and other associated water-dependent structures, used for mooring and accessing vessels." Fla. Admin. Code R. 18-21.003(22). The Dock meets the definition of "dock" in both rules.9 As discussed above, the Dock Approval limits mooring to non-motorized vessels, and Fondriest, a riparian owner, will use the Dock to access the water for the water-dependent activities of kayaking, paddle-boarding, and other water-dependent activities such as swimming, snorkeling, and fishing, consistent with rule 18-20.004(1)(e)5. 9 The Dock is not a "pier," which is defined as "a structure in, or, or over sovereignty lands which is used by the public primarily for fishing or swimming." Fla. Admin. Code R. 18-20.003(41)(emphasis added). As discussed above, the Dock is a private single-family residential dock that will be constructed on sovereignty submerged lands waterward of Fondriest's property. It will not be open to, or used by, the public for fishing or swimming. As previously discussed, the Dock meets the 500-square-foot threshold for purposes of exemption from regulatory permitting, pursuant to section 403.813(1)(b). The evidence also establishes that the Dock is a "minimum-size" dock, as defined in rule 18-21.002(39). Specifically, the Dock's area has been reduced to the smallest size possible that will provide Fondriest reasonable access to the water for kayak launching. The Dock's reduced size also will minimize impacts to resources at, and in the vicinity of, the Dock. Thus, the Dock has been designed to minimize any adverse impacts to fish and wildlife and threatened and endangered species habitat, as required by rules 18-21.004(2)(b) and (i), and 18-21.004(7)(d). Compliance with Aquatic Preserve Management Policies, Standards, and Criteria Rule 18-20.004 establishes the policies, standards, and requirements for approval of uses of sovereignty submerged lands in aquatic preserves. As discussed above, the Dock extends a total of 154 feet waterward from the MHWL. This is substantially less than the allowable 500-foot maximum extent from the MHWL, and also is substantially less than 20% of the width of the Straits of Florida, which spans from the Florida Keys to Cuba. Thus, the Dock is consistent with rule 18-20.004(5)(a)1. The competent, credible evidence establishes that the Dock will not be located in an area of significant biological, scientific, historic, or aesthetic value. However, even if such resources were present, the Dock would not cause adverse impacts due to its specific design features and the use of best management practices during construction. As discussed above, the Dock will minimize shading by reduction of the width of the access dock from four feet to three feet; by elevation of both the access dock and the terminal platform five feet above mean high water; and by the use of light-penetrable grating for the terminal platform. The Dock is designed to ensure that vessel use will not cause harm to site- specific resources, as required by rule 18-20.004(5)(a)3. The types of vessels that may use the Dock are limited to non-motorized vessels, and the letter of consent is conditioned to allow vessel launching only when there is a minimum depth of 0.5 feet of water at the terminal platform. As previously discussed, the evidence establishes that the Dock will be located in an RPA 3. Nonetheless, the Dock will comply with design standards applicable to docks in an RPA 1 or RPA 2. Specifically, the Dock will be constructed of wooden planking less than eight inches wide, spaced half an inch apart after shrinkage; will be elevated five feet above the MHWL; and will have a terminal platform consisting of light-penetrable grating to minimize shading. As previously discussed, the terminal platform will have a total area of 72 square feet—well below the 160-square foot maximum size allowed in aquatic preserves under rule 18-20.004(5)(b)6. The Dock extends out from the shoreline to a depth of approximately -0.5 ft at mean low water. Thus, Dock meets the requirement that it may not extend out from the shoreline further than to a maximum water depth of -4 feet at mean low water. Fla. Admin. Code R. 18-20.004(5)(b)3. Consistency with Coupon Bight Aquatic Preserve Management Plan Rule 18-20.004(7), which addresses management plans for aquatic preserves, states, in pertinent part: "[t]he aquatic preserve management plans shall be used by the Department to preserve and restore the distinctive characteristics identified by the inventories for each aquatic preserve." Rule 18-20.004(3)(a) states, in pertinent part: "all proposed activities in aquatic preserves having management plans adopted by the Board must demonstrate that such activities are consistent with the management plan." For the reasons discussed in detail above, it is determined that the Dock is consistent with the Management Plan, and, thus, complies with rule 18-20.004(3)(a). Public Interest Demonstration Chapters 18-20 and 18-21 both require an analysis to determine whether an activity proposed to be conducted on sovereignty submerged lands meets an applicable public interest test. Rule 18-20.004(1)(b), the aquatic preserve rule's public interest test, states, in pertinent part: "[t]here shall be no further sale, lease or transfer of sovereignty lands except when such sale, lease or transfer is in the public interest (see subsection 18- 20.004(2), F.A.C., Public Interest Assessment Criteria)." However, with respect to private residential single-family docks, rule 18-20.004(4)(c) states, in pertinent part: "[f]or the purpose of this rule, a private, residential single-family docking facility which meets all the requirements of subsection 18-20.004(5), F.A.C., shall be deemed to meet the public interest requirements of paragraph 18-20.004(1)(b), F.A.C." Fla. Admin. Code R. 18-20.004(1)(b)(emphasis added). As discussed herein, the Dock meets all applicable requirements in rule 18- 20.004(5). Accordingly, the Dock meets the aquatic preserves public interest test in chapter 18-20. The Dock also meets the public interest test codified in chapter 18-21. Rule 18-21.003(53) defines "public interest" as "demonstrable environmental, social and economic benefits which would accrue to the public at large as a result of the proposed action, and which would clearly exceed all demonstrable environmental, social, and economic costs of the proposed action." Rule 18-21.004(1) states: "[f]or approval, all activities on sovereignty lands must be not contrary to the public interest, except for sales which must be in the public interest." Fla. Admin. Code R. 18-21.004(1)(emphasis added). In this case, the Dock provides recreational water access to the riparian owner, and, as discussed extensively, will not have any adverse impacts on sovereignty lands, aquatic resources, or listed species. Thus, it is determined that the Dock is not contrary to the public interest, as defined in chapter 18-21. Petitioners assert that the Dock is inconsistent with article X, section 11 of the Florida Constitution, which states: Sovereignty lands. – The title to lands under navigable waters, within the boundaries of the states, which have not been alienated, including beaches below mean high water lines, is held by the state, by virtue of its sovereignty, in trust for all the people. Sale of such lands may be authorized by law, but only when in the public interest. Private use of portions of such lands may be authorized by law, but only when not contrary to the public interest. Fla. Const., art. X, §11 (emphasis added). Chapters 253 and 258, and the implementing rules codified in chapters 18-20 and 18-21, authorize the use of sovereignty submerged lands for private residential single-family docks when not contrary to the public interest. As discussed above, the Dock is not contrary to the public interest under chapters 18-20 and 18-21. Thus, the use of sovereignty submerged lands for the Dock is consistent with article X, section 11 of the Florida Constitution. Petitioners raised, as a public interest concern, their ability to walk below the MHWL along the shoreline on Long Beach Drive. The evidence shows that the Dock will, within its narrow footprint, present a minor hindrance to Petitioners' ability to walk unimpeded along the shoreline below the MHWL. However, the competent, persuasive evidence established that Petitioners will be able to duck under the Dock, or walk around the end of the terminal platform, where the water is relatively shallow. Importantly, Petitioners did not cite any statutory or rule provisions affording completely unencumbered access, by the general public, to all sovereignty submerged lands.10 Cumulative Impacts Rule 18-20.006 requires that an activity proposed in an aquatic preserve be evaluated for its cumulative impact on the aquatic preserve’s natural system. As extensively discussed above, Fondriest's expert, Walters, conducted a comprehensive cumulative impacts analysis that addressed all pertinent considerations in rule 18-20.006, and she concluded that the Dock will not have any 10 A key purpose of chapters 18-20 and 18-21 is to establish standards for approval of private uses of sovereignty submerged lands which may, to a certain extent, hinder the general public's access to those sovereignty lands. See Fla. Admin. Code R. 18-21.004 ("[t]he following management policies, standards, and criteria shall be used in determining whether to approve, approve with conditions or modifications, or deny all requests for activities on sovereignty submerged lands"); and Fla. Admin. Code R. 18-20.004 ([t]he following management policies, standards, and criteria are supplemental to chapter 18-21 . . . and shall be uses in determining whether to approve, approve with conditions or modifications, or deny all requests for activities on sovereignty submerged lands in aquatic preserves.") adverse cumulative impacts on the CBAP as a whole, or on any significant biologic, hydrologic, or other resources within the CBAP. As discussed above, Walters's analysis was comprehensive; her testimony was credible and persuasive; and her conclusion that the Dock will not result in adverse cumulative impacts to the CBAP, or to any resources within the CBAP, was rule- based, and considered all pertinent factual information. Based on the foregoing, it is determined that the Dock will not cause adverse cumulative impacts to the CBAP, or to any resources within the CBAP, as required by rule 18-20.006. Minimization of Adverse Impacts to Sovereignty Submerged Lands and Resources Rule 18-21.004(2)(b) states, in pertinent part, that activities that would result in significant adverse impacts to sovereignty lands and associated resources may not be approved. As discussed above, the evidence establishes that there are no significant natural resources present at the location, or in the vicinity, of the Dock. Thus, the Dock will not have adverse impacts on such resources or on sovereignty submerged lands. Nonetheless, numerous protective measures have been imposed as conditions to the letter of consent, to minimize the potential for adverse water quality impacts and to protect aquatic resources. Based on the foregoing, it is determined that the Dock will meet the resource impact minimization requirements in rules 18-20.004(5)(a)1. and 18-21.004(2). Measures to Avoid and Minimize Adverse Impacts to Listed Species and Habitat 18-21.004(7)(e) requires that "construction, use, or operation of the structure or activity shall not adversely affect any species which is endangered, threatened[,] or of special concern, as listed in rules 68A-27.003, 68A-27.004[,] and 68A-27.005." DEP consulted with FFWCC on the Dock application, to determine its potential impacts to species listed as endangered, threatened, or of special concern. As discussed above, FFWCC provided recommendations to minimize the Dock's potential impacts to several listed species, and those recommendations have been imposed as conditions to the letter of consent. As discussed above, the Dock will implement numerous measures to ensure that construction and use will not adversely affect manatees, sea turtle species, the Smalltooth Sawfish, and the Eastern Indigo Snake. As discussed above, Key Deer forage on and traverse the shore along Long Beach Drive. The competent, credible evidence establishes that the Dock will not impose any substantial barrier to the Key Deer's use of the shore on Fondriest's property, and will not otherwise adversely affect the Key Deer. Also, as discussed above, the competent, credible evidence establishes that due to the lack of suitable habitat, other protected species, such as the Lower Keys Marsh Rabbit, Keys Rice Rat, and Florida Keys Mole Skink are unlikely to inhabit, or otherwise be present at or near, the Dock site. Thus, it is determined that the Dock will not have any adverse impacts on these species. Based on the foregoing, it is determined that the Dock will not have adverse impacts to listed species and their habitat. Riparian Rights Chapters 18-20 and 18-21 require that the riparian rights of owners of upland riparian property adjacent to an activity seeking approval to use sovereignty submerged lands be protected. Rule 18-20.004(4) states, in pertinent part: "[n]one of the provisions of this rule shall be implemented in a manner that would unreasonably infringe upon the traditional, common law and statutory riparian rights of upland property owners adjacent to sovereignty lands." Rule 18-21.004(3) states, in pertinent part: None of the provisions of this rule shall be implemented in a manner that would unreasonably infringe upon the traditional, common law riparian rights, as defined in section 253.141, F.S., of upland riparian property owners adjacent to sovereignty lands. Satisfactory evidence of sufficient upland interest is required for activities on sovereignty submerged lands riparian to the uplands. All structures and other activities must be designed and conducted in a manner that will not unreasonably restrict or infringe upon the riparian rights of adjacent upland riparian owners. [A]ll structures, including mooring pilings, breakwaters, jetties and groins, and activities must be set back a minimum of 25 feet inside the applicant's riparian line. Exceptions to the setbacks are private residential single- family docks associated with a parcel that has a shoreline frontage of less than 65 feet, where portions of such structures are located between riparian less than 65 feet apart. Pursuant to rule 18-21.003(63), "satisfactory upland interest" means owning the riparian uplands or having some other possessory or use interest, as specified in the rule. Section 253.141(1) defines riparian rights as follows: Riparian rights are those incident to land bordering upon navigable waters. They are rights of ingress, egress, boating, bathing, and fishing and such others as may be or have been defined by law. Such rights are not of a proprietary nature. They are rights inuring to the owner of the riparian land but are not owned by him or her. They are appurtenant to and are inseparable from the riparian land. The land to which the owner holds title must extend to the ordinary high watermark of the navigable water in order that riparian rights may attach. Conveyance of title to or lease of the riparian land entitles the grantee to the riparian rights running therewith whether or not mentioned in the deed or lease of the upland. Fondriest owns the upland property riparian to the sovereignty submerged lands on which the Dock is proposed to be located, and Petitioners stipulated that she has a satisfactory upland interest for purposes of rule 18-21.004(3). The Trust owns upland property bordering the Straits of Florida; thus, riparian rights inure to the Trust property, pursuant to section 253.141. As previously discussed, the evidence establishes that the Dock will be set back over 40 feet from the common riparian line between Fondriest's property and the Trust's property. To this point, Meredith acknowledged that the Dock would be set back more than 25 feet from the common riparian line, and will not intrude into the Trust's riparian area. No evidence was presented showing that the Dock would unreasonably interfere with the Trust's traditional riparian rights of navigation, boating, swimming, or fishing within its riparian area. Meredith testified that the Dock would obstruct the view of the waterbody, the shore, and the sunrise over the water, from the Trust property. She appeared to assert these interests on behalf of the Trust and herself. However, as more fully discussed below, under Florida law, the riparian right to an "unobstructed" view does not entail a view completely free of any infringement or restriction by structures or activities appurtenant to neighboring riparian properties. Rather, the right to an "unobstructed" view means that a riparian owner is entitled to a direct, unobstructed view of the channel of the waterbody and a direct means of ingress and egress to the channel. No evidence was presented that the Dock—which will be constructed perpendicular to the shoreline within Fondriest's riparian area—would obstruct the Trust's or Meredith's view of the channel of the Straits of Florida. Additionally, as previously discussed, the Trust presented no evidence to show that the presence of the Dock in Fondriest's riparian area would interfere with the Trust's direct ingress and egress to and from the channel of the Straits of Florida. Accordingly, it is determined that the Dock will not unreasonably infringe on the Trust's riparian rights. Similarly, it is determined that the Dock will not unreasonably infringe on the riparian rights incident to the Deer Run property, or to Appel's properties on Long Beach Drive. To this point, Demaria and Appel did not present any evidence showing that the Dock will obstruct their view of the channel of the Straits of Florida, either from the Deer Run property, or from Appel's properties. DeMaria and Appel also failed to present evidence showing that the Dock would interfere with direct ingress and egress to and from the channel of the Straits of Florida, either from the Deer Run property or from Appel's properties. Accordingly, it is determined that, consistent with section 253.141 and rule 18-21.004(3), the Dock will not unreasonably infringe on the riparian rights of the Trust or of DeMaria and Appel. General Requirements for Authorization to Use Sovereignty Submerged Lands As discussed above, the Dock will be constructed and used in a manner that will avoid and minimize adverse impacts to sovereignty submerged lands and resources, consistent with rule 18-21.004(7)(d). The competent, credible evidence also demonstrates that the construction and use of the Dock will not adversely affect listed species, consistent with rule 18-21.004(7)(e). As discussed above, the Dock will not unreasonably interfere with the riparian rights of the Petitioners, consistent with rule 18-21.004(7)(f). Additionally, the Dock will not constitute a navigational hazard, consistent with rule 18-21.004(7)(g). Due to the shallow water in the footprint and in the vicinity of the Dock, navigation in the area is typically by kayak or canoe. The competent, credible evidence shows that the Dock will not impede navigation of these types of vessels. Because the sandy beach areas on Long Beach Drive are in private ownership, the Dock will not interfere with the public easement for traditional uses of sandy beaches, as provided in section 161.141, Florida Statutes; thus, the Dock is consistent with rule 18-21.004(7)(h). Also, as discussed above, the Dock will be constructed, operated, and maintained solely for the water-dependent uses of launching non-motorized vessels and swimming, consistent with rule 18-21.004(7)(j).

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection issue a Final Order granting Respondent Julia Fondriest's application for a Letter of Consent to Use Sovereignty Submerged Lands and verifying that the Dock is exempt from the requirement to obtain a regulatory permit, pursuant to section 403.813(1)(b). DONE AND ENTERED this 18th day of February, 2021, in Tallahassee, Leon County, Florida. S CATHY M. SELLERS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of February, 2021. COPIES FURNISHED: Julia Fondriest Doug Scheele Lifetime Dock & Lumber, Inc. 24536 Overseas Highway Summerland Key, Florida 33042 Luna E. Phillips, Esquire Gunster, Yoakley & Stewart, P.A. Suite 1400 450 East Las Olas Boulevard Fort Lauderdale, Florida 33301 Deborah K. Madden, Esquire Gunster, Yoakley & Stewart, P.A. Suite 1400 450 East Las Olas Boulevard Fort Lauderdale, Florida 33301 Paul Joseph Polito, Esquire Department of Environmental Protection Mail Stop 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Ralf Gunars Brookes, Esquire Ralf Brookes Attorney Suite 107 1217 East Cape Coral Parkway Cape Coral, Florida 33904 Noah Valenstein, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (14) 120.52120.536120.54120.569120.57120.68161.141163.3161253.03253.141258.36258.42258.43403.813 Florida Administrative Code (15) 18-20.00118-20.00318-20.00418-20.00618-21.00218-21.00318-21.00418-21.00518-21.005128-106.10428-106.20528-106.21762-302.30062-4.24268A-27.003 DOAH Case (9) 04-224017-097217-532819-186520-000420-007120-247320-247420-2535
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer