Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
ROGER E. NEWBOLD vs. ALLEN ELECTRIC CO., 77-001207 (1977)
Division of Administrative Hearings, Florida Number: 77-001207 Latest Update: Oct. 05, 1977

Findings Of Fact Roger Newbold was employed by Allen Electric Company, Inc., as a laborer working on its contract with the State. Newbold was employed during two different periods. The first time was prior to January 1, 1977, and the second, from March 13, 1977, to May 22, 1977. The addition to the Polk County Correctional Institution was bid in two phases; the first for heavy construction for site preparation, and the second, the actual building construction. Allen Electric Company, - Inc., had a contract from the general contractor during the first phase to install the main electrical distribution facilities on the site. All of this work was not associated with and carried on prior to the commencement of building construction. The heavy construction was in progress during Newbold's first period of employment with Allen Electric Company, Inc. Allen Electric Company was also a subcontractor with Delta Electric Company on the second phase of construction; however, Allen Electric Company did not do any building construction. They subcontracted with Delta to install secondary distribution lines and perimeter fence lighting on the site. See Delta Electric Company contract, late filed exhibit No. 7. Allen Electric Company did not go into the building with their workmen because their contract called for them to stop five (5) feet outside the building with the secondary distribution lines. All work and wiring done from this point into the building was carried on by Delta Electric. Newbold's job during his entire employment with Allen electric was to dig ditches and lay conduit. The conduit runs then were reinforced with concrete poured over reinforcing steel. During his entire employment, he was involved in digging the necessary ditches, setting the reinforcing rods, and pouring the concrete. The rate for heavy construction laborers under wage rate 398-W filed as a portion of late filed exhibit No. 7 was three dollars and thirty-six cents ($3.36) per hour. The wage rate for laborers working on building construction pursuant to wage rate 397-W also filed as a portion of late filed exhibit No. 7 was six dollars and fifteen cents ($6.15) per hour. Wage scale 397-W specifically states that it is applicable to nonresident building construction. All of the skills listed on the wage rate apply specifically to building construction except the general term "laborer." The record shows that the work done by Allen Electric Company, Inc., in the building construction phase was the same type of work undertaken by Allen Electric in the heavy construction phase. In both phases, Newbold was engaged in exactly the same duties. Newbold did not work on building construction but on laying conduit for secondary distribution systems and perimeter lighting systems during the second phase. All of this work took place outside of the building.

Recommendation The Hearing Officer recommends that the claim of Roger Newbold be dismissed by the agency. DONE and ENTERED this 5th day of 1977, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Marvin Woods, Esquire 440 S. Florida Avenue Post Office Box AR Lakeland, Florida 33801 David A. Perry, Esquire Corporate Officer Allen Electric Company, Inc. 1271 LaQuinta Drive Orlando, Florida 32809 Mr. Luther J. Moore Administrator of Prevailing Wage Department of Commerce Division of Labor 1321 Executive Center Drive Fast Tallahassee, Florida 32301

# 2
GEORGE SOLAR vs CONSTRUCTION INDUSTRY LICENSING BOARD, 90-006607 (1990)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Oct. 18, 1990 Number: 90-006607 Latest Update: Mar. 28, 1991

The Issue Whether Petitioner should be granted additional credit for one or more examination questions answered by him during the June 1990 Certified Building Contractor Examination.

Findings Of Fact Petitioner sat for the June 1990 certified building contractor examination. On Part II, he received a score of 68.0. A minimum passing score is 69.01. On Part III, he received a score of 71.00. Minimum passing score is 69.01. Petitioner had previously passed Part I of the exam. Petitioner initially challenged question numbers 6, 13 and 14. Upon completion of the testimony, Petitioner withdrew his challenges to question numbers 13 and 14. The National Assessment Institute prepares licensure examinations for building contractors in the State of Florida under authority of the Office of Examination Services, Department of Professional Regulation. The Institute prepared question number 6 for the certified building contractor examination administered on June 26 and 27, 1990. Question number 6 tested the candidate's ability to calculate the time necessary for a crew to excavate, form and pour concrete for a reinforced concrete curb and gutter in a parking area and have it inspected. The candidate was asked to select the earliest date that concrete can be scheduled to be poured. Four dates were given: (A) June 11, (B) June 13, (C) June 15, and (D) June 18, 1990. The Institute determined that the only correct answer was: (D) June 18, 1990. The Petitioner selected: (C) June 15, 1990. Part of the instructions to the examination candidates stated: "The inspection request will NOT be called in the day the work is completed." The evidence was undisputed that preliminary calculations indicate with regard to question 6 the mathematical approach to the solution demonstrates that the work will take nine days (rounded up), starting June 1 and completed on June 13, and, therefore, the inspection is to be called in on Thursday, June 14, 1990. The third paragraph of the question states: Inspections have been taking one day from the time the inspection is called in until the time the inspection is completed. Inspections can NOT be called in or performed on Saturdays or Sundays." The first sentence of the fourth paragraph states: "The concrete is to be placed the day after the inspection is completed." (Emphasis supplied) The Department's position is that the plain language of the question indicates that it would take one day or 24 hours from the date the request for inspection was called in (June 14) until the inspection was completed which would be June 15. Since the instructions were clear that the concrete cannot be poured on the same day the inspection is completed or on Saturdays or Sundays, then the earliest date that the concrete can be scheduled is Monday, June 18, 1990, or answer (D). The Petitioner argues that it is not uncommon in the construction industry to "call in" an inspection in the morning and have it completed on the same date (in one day). Therefore, since it is undisputed that the inspection is to be "called in" on Thursday, June 14, that it was reasonable and logical for him to conclude that the inspection would also be completed the same date. Since the question instructed that the concrete is to be placed the day after the inspection is completed, he selected answer (C), June 15, 1990 (a Friday) as the correct answer. The Department does not dispute that it is common practice in the construction industry for an inspection to be called for and completed in one day. The Department's determination that answer (D) was the only appropriate answer was arbitrary and unreasonable.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that: Petitioner be awarded four points for his answer to question number 6 of Part II of the Certified Building Contractor examination for June, 1990. Petitioner be awarded a passing grade for Parts II and III of the examination. DONE AND ENTERED this 28th day of March, 1991, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March, 1991. APPENDIX The following constitutes my specific rulings, in accordance with section 120.59, Florida Statutes, on findings of fact submitted by the parties. Petitioner's proposed findings of fact. Accepted in substance: paragraphs 1,2,3,4,5,6,7,10 Rejected as argument: paragraphs 8,9 Respondent's proposed findings of fact. Accepted in substance: paragraphs 1,2,3(included in Preliminary Statement), 4(in part),5. Rejected: paragraph 4(in part, as against the greater weight of the evidence and argument), 5 and 6(challenge withdrawn) Copies furnished: George Solar 1302 West Adalee Street Tampa, Florida Vytas J. Urba, Esquire Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Jack McRay, Esquire General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.111
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DOUGLAS R. MCINTEE, 82-002843 (1982)
Division of Administrative Hearings, Florida Number: 82-002843 Latest Update: Jun. 01, 1984

Findings Of Fact These proceedings were set for final hearing by a Notice of Hearing dated July 8, 1983 addressed to the parties, including Respondent at 488 Esther Lane, Altamonte Springs, Florida, 33596. 2/ The Notice of Hearing was not returned to the Division of Administrative Hearings as undelivered. At the time and place noticed for the final hearing the Hearing Officer waited until 9:16 a.m., to commence the proceedings, which concluded at 11:08 a.m. At no time has the Respondent contacted the Hearing Officer concerning a continuance or explained his failure to appear as noticed. At all times material to this proceeding Mr. McIntee has been licensed as a certified building contractor under license number CB C015923. He was also the qualifying agent pursuant to Section 489.119, Florida Statutes, for Delco, Incorporated. At no time has he ever attempted to qualify or otherwise notify the Construction Industry Licensing Board that he intended to affiliate with or do business as Earth Shelter Corporation of Florida, Inc. On July 30, 1980 Earth Shelter Corporation of Florida, Inc. (Earth Shelter) entered into a contract with Mr. and Mrs. William Sweet to construct an earth shelter single family residence in Lake County, Florida. The estimated cost of the project was to be $57,000 and was guaranteed not to exceed $60,000. The contract was negotiated by Respondent acting as president of Earth Shelter. Mr. McIntee was the contractor who pulled the building permit on behalf of Earth Shelter. The project was financed by First Family Federal Savings and Loan Association of Eustis, Florida. In order to obtain payments from the Association, Respondent periodically executed affidavits which stated in part: Affiant says further that all the subcon- tractors, materialmen or any other persons performing labor and furnishing materials used in the construction of the building, or improvements to the premises or appur- tenances thereof, have been fully paid in- cluding all extras. As the result of executing these affidavits Respondent received draws totaling $49,079.26 on the dates of September 30, 1980, October 31, 1980, December 3, 1980, February 4, 1981 and July 10, 1981. These affidavits were false. At the time the affidavits were executed all the subcontractors had not been paid by Respondent. As an example, Frank Wagner Excavating, Inc. performed subcontracting services at the Sweet project on June 4 and 5, 1981 at a cost of $1,451. This was billed to Respondent on June 6, 1981. He sent Wagner Excavating a check dated June 6, 1981, in the amount of the invoice, but the check was returned to Wagner for lack of sufficient funds at Respondent's bank. Before Respondent's check bounced, but subsequent to invoicing the work done on June 4 and 5, 1981, Mr. Wagner performed additional earth moving work at the Sweet project on July 3, 8, 9 and 10, 1981. That work was invoiced on July 10, 1981 for $1,378.75. No attempt was made by Respondent to pay for the second invoice. Eventually Wagner Excavating was paid by Mr. Sweet personally and by an additional payment directly to Wagner Excavating by First Family Federal Savings and Loan Association in order to satisfy Wagner's lien. In order to protect himself, Wagner had filed a lien against the Sweet property on August 17, 1981. Because of structural defects in the construction of Mr. Sweet's home performed by Respondent, Mr. Sweet filed a complaint with the Lake County Board of Examiners against Respondent. Notice of that complaint was given to Respondent on August 18, 1981. He was informed that on September 1, 1981 the Lake County Board of Building Examiners would take testimony concerning the allegations contained in the complaint. Respondent was urged to attend the meeting and to be represented by counsel if he so desired. Mr. McIntee did appear at that meeting. An investigation of the complaint followed. Respondent was subsequently noticed for a second meeting of the Board of Examiners to be held on October 6, 1981 concerning the Sweet complaint, but he failed to appear. At that time the results of the investigation were reviewed and the Lake County Board of Examiners revoked Respondent's license as a contractor in Lake County for abandonment and code violations related to his work on Mr. Sweet's residence. On September 19, 1980 Earth Shelter through Respondent entered into a contract with James V. Migliorato to construct a residence in Seminole County, Florida. The contract price was $48,500. During the course of the work performed by Mr. McIntee, liens in the amount of approximately $9,500 were filed by third parties who provided materials and services under subcontract to Earth Shelter in the construction of Mr. Migliorato's residence. By March of 1981 Respondent had abandoned the project without cause. Mr. Migliorato later met with him at which time Respondent explained that he had run out of money and was not going to finish the job. In August of 1981 Mr. Migliorato and his counsel met with Respondent and his counsel. During their discussions Respondent stated that the money which he had been paid for work on the Migliorato home had been diverted by him for use on the Sweet residence mentioned above. The liens outstanding against Mr. Migliorato's property were never satisfied by Respondent and had to be paid by the homeowner. An example of the outstanding liens was that filed by Superior Distributors, Inc. which supplied and installed a kitchen and bathroom cabinet at the Migliorato residence. The work was completed on June 30, 1981 and invoiced on the same date for $2,128. This invoice has never been paid by Respondent.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Construction Industry Licensing Board enter a Final Order revoking Respondent's license as a certified building contractor in the State of Florida. DONE and RECOMMENDED this 14th day of October, 1983, in Tallahassee, Florida. MICHAEL P. DODSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of October, 1983.

Florida Laws (4) 120.57455.225489.119489.129
# 4
FLORIDA ENGINEERS MANAGEMENT CORPORATION vs FRED C. JONES, P.E., 05-003216PL (2005)
Division of Administrative Hearings, Florida Filed:Bradenton, Florida Sep. 06, 2005 Number: 05-003216PL Latest Update: Sep. 15, 2006

The Issue The issues presented are whether Respondent signed and sealed negligent drawings for one single-family residence and provided plan review certification for two other projects designed by Respondent in violation of Subsections 471.033(1)(g) and 553.791(3), Florida Statutes (2002), and Florida Administrative Code Rule 61G15-19.001(6)(n).1

Findings Of Fact The Board of Professional Engineers (Board) is charged with regulating the practice of engineering pursuant to Chapter 455, Florida Statutes. Section 471.038, Florida Statutes, authorizes Petitioner to provide the Board with administrative, investigative, and prosecutorial services. Respondent is licensed in the state as a professional engineer pursuant to license number PE 54476. It is undisputed that Respondent is a private provider within the meaning of Subsection 553.791(1)(g), Florida Statues. On October 29, 2002, Respondent signed and sealed drawings for a single-family residence identified in the record as the Barnes residence. It is less than clear and convincing that the drawings for the Barnes residence are deficient. The testimony of Respondent's expert witness was credible and persuasive. The applicable standard of care does not require the relevant drawings to include multiple ridge heights in order to describe the nature and character of the work to be performed with sufficient clarity. It is less than clear and convincing that the ridge heights in the drawings are unequal. Additional ridge height information would have been non-critical information that may have been interpreted as specific construction requirements and lead to confusion, added costs, conflicting interpretations, and potential hazards in buildings. It is less than clear and convincing that the drawings for the Barnes residence insufficiently show heights of the eaves or lintels and sills. The plans can be easily understood by tradesmen and inspectors. The typical wall section at page 4 of the plans addresses eaves, lintels, and sills. The ridge height requirements in Manatee County, Florida (the County), are intended to ensure compliance with maximum height restrictions. The mean heights in the drawings adequately address the maximum local height ordinances. It is less than clear and convincing that the roof entry plan provided insufficient clarity. The roof was constructed according to the local code requirements without apparent exception. The evidence does not support a finding that the roof entry plan, the ridge heights, lintels, eaves, and sills were insufficiently clear to describe the nature and character of the work to be performed. Clear and convincing evidence does not support a finding that the wind uplift for roof trusses in the plans was incorrect or unclear. If the wind load calculations were found to be deficient, the specified fittings were sufficient to withstand wind loads that exceeded the calculations of Petitioner's expert by approximately 70 percent. Wind load calculations are intended to ensure a roof will sustain the load and will not blow off of the house. The fittings were sufficient to secure the roof against the projected wind load. Clear and convincing evidence does not support a finding that the drawings failed to specify the applicable masonry inspection requirements. The evidence is less than clear and convincing that special masonry inspections are required for single-family residences of two stories or less. A masonry inspection is required for such structures when a building inspector finds a need for such an inspection. It is less than clear and convincing that the drawings fail to adequately specify the splice lengths of the bond beam reinforcement for tension, compression, intersections, and corners. The requisite evidence does not support a finding that the plans deviate from the standard of care in the community. Clear and convincing evidence does not support a finding that Respondent failed to comply with applicable soil condition requirements. The County did not require soil conditions on plans at the time Respondent drew the plans. From sometime in the 1940s through November 2003, the County permitted engineers to assume soil conditions with a ground load of 2000 pounds per square foot. Respondent drew the plans for the Barnes project in 2002. The testimony of Petitioner's expert does not relate to facts in evidence. The expert did not know County allowances for soil conditions at the time Respondent drew the plans. The evidence is less than clear and convincing that the design of the concrete footings cannot be verified from the plans. Nor does the requisite evidence support a finding that the plans do not specify reinforcement of the thickened edge under a load bearing wood stud wall at the garage. The plans include two reinforcement specifications for the thickened edge under the load bearing wood stud wall at the garage. The specifications include welded wire mesh and reinforced steel bars. Clear and convincing evidence does not support a finding that Respondent supplied or submitted the Barnes plans for permit. Without such a finding, Respondent was not required to prepare, submit, or seal a site plan. A site plan for the Barnes residence exists in the file of the County Building Department (Department). A Department representative confirmed that the site plan is sufficient and that an engineer of record is not required to prepare, submit, or seal a site plan unless the engineer of record actually submits the plans for a permit. On February 24 and March 7, 2003, Respondent signed and sealed drawings for respective projects at 14815 Coker Gully Road, Myakka, Florida (the Coker project), and 705 50th Avenue, Plaza West, Bradenton, Florida (the Yonkers project). Pursuant to Section 553.791, Florida Statutes, Respondent entered into a contract with an entity identified in the record as Griffis Custom Homes (Griffis) to provide either building code plans or inspection services, or both. Prior to the commencement of the two projects in question, the Department expressly permitted an engineer to provide building code inspection services involving buildings designed or constructed by the engineer. Respondent prepared private provider affidavits, obtained additional insurance, had forms made, and prepared to provide inspections services. Respondent immediately ceased his activities when Department officials objected to Respondent's stated intention of providing "private provider" building code inspection services for the Coker and Yonkers projects. The separate owners of the two projects withdrew their applications as "private provider" projects. The Department processed the projects, performed all inspections, and issued a certificate of occupancy for each project. Neither the Department, Petitioner, nor the Board, ever served Respondent with a Notice of Non-compliance. If it were found that Respondent committed the alleged violation, the violation was minor. There is no evidence of any economic or physical harm, or significant threat of harm, to a person or to the health, safety, or welfare of the public. There is no evidence that Respondent has any prior discipline against his license.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a final order finding Respondent not guilty of the alleged violations. DONE AND ENTERED this 2nd day of May, 2006, in Tallahassee, Leon County, Florida. S DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of May, 2006.

Florida Laws (8) 120.52120.569120.57468.603471.033471.038553.79190.803
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT TUCKER, 85-004329 (1985)
Division of Administrative Hearings, Florida Number: 85-004329 Latest Update: Apr. 04, 1986

The Issue The issue is whether Respondent's license as a registered building contractor should be disciplined for the acts alleged in the Administrative Complaint, as amended?

Findings Of Fact Respondent, Robert Tucker, is a registered building contractor holding State of Florida license number RB 0033063 (Ex. 7). Respondent was licensed as a building contractor by the State of Florida in September 1978, and has remained licensed at all times material hereto (Ex. 7). Since September 20, 1978, Respondent has held a local Building Contractor's License issued by the Leon County Contractor Licensing and Examination Board (Ex. 7). Respondent's license with the Department has been delinquent since July 1, 1985 (Ex. 7). In July 1983, Respondent made an oral agreement with Violet Gladieux to erect a carport for her at a cost of $1,350 (Ex. 3). Ms. Gladieux's residence is located at 2321 Belle Vue Way, within the city limits of Tallahassee. Jay Gladieux, Jr. became acquainted with Mr. Tucker from his position as an employee of Mr. Tucker on a prior construction project. Mr. Gladieux introduced his mother, Ms. Gladieux, to Mr. Tucker for the carport construction. It was orally agreed that Ms. Gladieux would pay Mr. Tucker for supplies as they were needed. Mr. Tucker began erection of the carport approximately one week after July 11, 1983, when he received the first payment of $300. On July 29, 1983, Mr. Tucker received final payment of $350 so that he could complete the carport (Ex. 3). Approximately two weeks after July 29, 1983, Respondent completed the carport. A permit for the erection of the carport was required by Section 7-63, Buildings and Construction Regulations (The Building Code) of the City of Tallahassee. The language of that ordinance has not changed since 1957 (Ex. 1). No building permit was ever obtained by Mr. Tucker for erection of the carport. Approximately two weeks after completion of the carport, it collapsed after a heavy rainfall (Ex. 4 and 5). Mr. Tucker returned to repair the damaged carport. He erected center studs and was to return later to complete the damage repair. Mr. Tucker has failed to return to complete the damage repair after requested to do so by Jay Gladieux. When an administrative complaint has been filed against a contractor, personal service of the complaint is attempted upon the contractor at his last address of record. If personal service cannot be effectuated at the contractor's last address of record, further attempts are made to locate the contractor. The building departments, both City and County, the telephone company, utility company and post office are contacted. The building departments are contacted to determine if the contractor has obtained any permits, for the permits would list the contractor's address. The telephone company is contacted for prior and new telephone listing(s) with address(es). The post office is contacted for forwarding address(es). The utility company is contacted for new utility service which would contain a new address (es). If the contractor cannot be located after using these avenues, a diligent search affidavit is executed by the investigator who is attempting to serve the contractor. In September 1978 and at all times pertaining to the construction of the carport, Respondent's address of record with the Department was 1515-21 Paul Russell Road and P.O. Box 20234, Tallahassee, Florida. Respondent had not notified the Department of Professional Regulation, Construction Industry Licensing Board of any change in his address (Ex. 7), other than by the new address revealed on the Election of Rights form he filed in response to the administrative complaint. The Department attempted to personally serve Mr. Tucker at his listed address and could not locate him there. On May 21, 1984, Robert E. Connell, an investigator for the Department of Professional Regulation, executed a diligent search affidavit concerning service of the Administrative Complaint upon Mr. Tucker in this proceeding (Ex. 8).

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that Respondent be found guilty of the charges in count one of the Administrative Complaint, as amended; that counts two and three be dismissed; and that he be fined $250.00. DONE AND ORDERED this 4th day of April 1986 in Tallahassee, Leon County, Florida. WILLIAM R. DORSEY,JR., Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of April 1986. COPIES FURNISHED: Mr. James Linnan Executive Director Construction Industry Licensing Board P.O. Box 2 Jacksonville, Florida 32202 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Errol H. Powell, Esq. Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Robert Tucker P.O. Box 10218 Tallahassee, Florida 32302

Florida Laws (6) 120.57455.227489.105489.115489.117489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs DAVID P. MILLER, D/B/A GREAT SOUTHERN CONSTRUCTION AND DEVELOPMENT, INC., 92-007413 (1992)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Dec. 15, 1992 Number: 92-007413 Latest Update: Aug. 08, 1994

The Issue The issue for consideration in this hearing is whether Respondent's license as a certified building contractor should be disciplined because of the matters set out in the Administrative Complaint.

Findings Of Fact At all times pertinent to the allegations herein, Petitioner was the state agency responsible for the regulation of the construction industry in Florida. Respondent, David P. Miller, was licensed as a certified building contractor under license number CB C039127 and was doing business as Great Southern Construction and Development, Inc. On March 14, 1988, Robert Crowley, a semi-retired real estate broker and promoter, and Treasurer of Enterprise Industrial Park, Inc., (EIP), entered into contracts with the Respondent to construct three buildings, A, B, and H, for it within the park boundaries. Building A was to house offices and retail space; building B was to house warehouse and offices; and building C was to house garage space. The construction was to be financed by an infusion of shareholders' money and by a construction loan from the Southland bank in the amount of $375,000.00. The loan was ultimately increased to $614,000.00 so that EIP could begin development of phase II of the park. The contracts provided for Respondent to be paid $110,000.00 for Building A, $67,000.00 for Building B, and $52,807.00 for Building H. The loan was obtained in phases. The developers had outlined the project to bank officials who approved it, initially, for development of the park and construction of four buildings. Phase one was to include the roadway and one building. When that was completed, the other buildings were to be erected. Site preparation was accomplished by John T. Day. Most of the site preparation was completed before Respondent started construction. Thereafter, as work progressed, Respondent periodically certified to the bank what work had been done and that suppliers had been paid. Upon receipt of that certification, the bank would issue a check for the appropriate amount to EIP which would, thereafter, issue its own check to Respondent. There was an exception, however, in the case of payments to Ludwig Steel. Whereas that supplier would bill Respondent for small items delivered, it demanded payment by cashiers' check upon delivery for major structural steel fabrications. These checks, for steel for Buildings A and B, were for $18,511.84 and $17,716.84, were issued by Southland Bank, at the request of EIP. During the course of his performance of the contracts for the construction of Buildings A, B, & H, Respondent executed several of the above mentioned certification forms. For Building H: These included: a. August 30, 1988 $ 9,505.00 b. October 4, 1988 9,505.00 c. October 17, 1988 9,505.00 d. December 28, 1988 11,881.50 e. January 31, 1989 9,437.50 TOTAL $49,834.00 Prior to these certificates, the bank also released $90,000 in advances for start up costs and the loan in March, April and May, 1988. In addition to the certificates listed above, Respondent also signed certificates for Building A totalling $91,446.00 as follows: a. August 30, 1988 $ 19,800.00 b. October 4, 1988 19,800.00 c. October 17, 1988 19,800.00 d. December 28, 1988 24,750.00 e. January 31, 1989 7,296.00 TOTAL $ 91,446.00 Respondent also signed additional certificates for Buildings B as follows: a. December 28, 1988 $ 46,642.00 b. January 31, 1989 28,031.00 c. March 1, 1989 28,031.00 TOTAL $102,704.00 These certificates were also signed by the architect, Mr. Wilcockson. In fact, they were not correct in that not all the work had been done and not all suppliers had been paid. Respondent admits to falsely signing the certificates but claims he was urged to do so by representatives of EIP who indicated to him it was just a routine procedure. Consequently, even knowing the certificates were not accurate, he signed them because he wanted to get paid. It is found, however, that Respondent has been a licensed contractor for a number of years and knew the implications of his actions. His attempts at justification for his actions are neither credible nor impressive. Construction progressed satisfactorily and without major problems up to the time for the last draw. At that point, the bank declined to issue a check to EIP for the construction of Building C, also to be erected on the site, when it became aware that numerous liens had been filed by subcontractors and materialmen indicating Respondent's failure to make satisfactory payment for buildings A, B, and H. These liens included claims by: American Roll-Up Door Co. $ 3,630.00 B & B Painting Contractors 3,020.00 Blackton, Inc., 5,820.73 Brownie Septic Tank Contractors #1 1,025.00 Brownie Septic Tank Contractors #2 1,025.00 Brownie Septic Tank Contractors #3 1,635.00 Don Alan Dinora 930.00 Energy Savings Systems, Inc. 10,750.00 Florida Mining & Materials 2,388.31 Mid Florida Air Conditioning, Inc. 3,982.00 Neeley-Built Structures, Inc., 4,995.78 Residential Building Supply 7,857.11 Total $47,058.93 Mr. Crowley claims the above liens were satisfied by EIP, and it is so found. He claims EIP also paid some subcontractors who did not file liens because of a desire to help small contractors who otherwise would not have been paid. No figures were available to support that latter claim, however, and it is not considered to be probative of any issue. It is found, however, that Respondent paid Neeley-Built the amount of $4,995.78 and the claim of lien form included within Petitioner's exhibit of filed liens refers to property other than that in issue here. In addition, the $10,750.00 lien of Energy Savings Systems is not totally attributable to services or materials for the instant project. It is estimated that 60 percent of that amount relates to work done outside the three contracts in issue here. Further, only $1,700.00 of the lien of Residential Building Supply relates to material provided for the work done by Respondent under these contracts. The balance relates to work done outside the original contract limits. Over the course of the contracts, EIP paid Respondent, in addition to a deposit of $25,786,99 for Bldgs. A & H, the sums below, for a total of $259,006.72 for Bldgs. A, B, & H: a. Aug. 31, 1988 $19,800.00 for Bldg. A b. Aug. 31, 1988 9,505.00 for Bldg. H c. Oct. 05, 1988 10,793.16 for Bldg. H & A d. Oct. 17, 1988 29,305.99 for Bldg. A & H e. Dec. 14, 1988 19,000.00 f. Dec. 29, 1988 49,417.06 g. Feb. 06, 1989 7,296.00 for Bldg. A h. Feb. 06, 1989 28,310.00 for Bldg. B i. Feb. 06, 1989 9,473.50 for Bldg. H j. Feb. 10, 1989 2,350.00 for misc. k. Feb. 15, 1989 20,000.00 l. Mar. 03, 1989 28,031.00 for Bldg. B In addition to those payments, EIP also paid $16,000.00 to Benson Drywall on December 12, 1988 at the request of Respondent. The total paid by EIP, either to or on behalf of the Respondent, was: $ 25,786.00 deposit 233,280.72 to Great Southern 16,000.00 Benson Drywall 36,228.68 Ludwig Steel $311,295.40 TOTAL Mr. Crowley was not the main source of corporate funds. The President of the company is a Mr. Nelson who was the "money man." Contractor selection was by agreement between Nelson and Crowley, but Crowley was the supervisor of the contracts and did most of the negotiating with Respondent. The work stipulated in the contracts between EIP and Respondent was not the only work called for in their relationship. The contracts provided for the basic construction but Mr. Crowley requested Respondent to perform additional work in or around buildings A, B, and H, which included: Tenant improvements in buildings A and B valued at $23,000 excluding labor; Additional site work including electrical, telephone, grading and filling, berm modification, concrete sidewalks and parking buffers, and repair of damaged concrete (all but the repair of concrete was the result of the failure of the original site preparation contractor to properly complete his work); Negotiations and discussions with Volusia County regarding the sewer/septic system necessary for the project. In addition to the $23,000.00 for tenant improvements mentioned in the paragraph next above, Respondent also paid out of pocket to the following contractors and suppliers for work outside the scope of the original contracts: a. Ludwig Metal Buildings $ 3,000.00 b. Concrete 3,840.00 c. John Bates & family 6,497.73 d. Four Seasons 1,190.00 e. Will Cox 975.00 f. Riley 3,100.00 All Star Electric 4,705.32 Jerry's Concrete Service 1,350.00 TOTAL $24,658.05 Though the contracts referenced in this proceeding pertain to construction of Buildings A, B, & H, Respondent was also retained to erect a metal building to be designated C. Respondent received a total of $253,000.00 from EIP to construct those buildings for which he had the initial contracts and also to put up the metal building, C. The cost to complete Building C was $45,500.00 but EIP had remaining only slightly over $6,000.00 to pay for that work. Respondent did substantial work for EIP which was over and above the services called for under the contracts for Buildings A, B, & H as amended by the change orders for which he was not paid because Mr. Crowley advised him no additional monies were available. For example, he and his brother, Thomas, did additional site work valued by him at $24,260.00; and additional labor and services on the septic and sewer system problems valued by him at $5,600.00 and for tenant improvement, valued by him at $5,000.00. Here, however, it must be noted that the figures cited are not documented by any supporting material and contain significant amounts for his labor which he priced at $90.00 per hour. Mr. Miller, during his relationship with EIP, purchased a 10 percent interest in the firm. He originally filed his own lien on the property for $80,364.00 based on the contracts he had in hand and the site work which he valued at $18,000.00. He claims he subsequently withdrew his lien without being paid so that the limited funds available could be used to pay the subcontractors. No corroborating evidence on this point was introduced, however. Mr. Miller's contracting license was, subsequent to the incidents herein, placed in inactive status and currently remains so. He is not now engaged in contracting and claims he does not intend to do so in the future. His motivation in contesting the allegations against him is, he claims, solely to clear his good name and reputation.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED THAT the Respondent, David P. Miller, d/b/a Great Southern Construction and Development, Inc. pay an administrative fine of $3,750.00 and be reprimanded. RECOMMENDED this 9th day of November, 1993, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of November, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-7413 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: 1. & 2. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. & 6. Accepted and incorporated herein. 7. - 14. Accepted and incorporated herein. 15. - 17. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. & 21. Accepted and incorporated herein. 22. - 24. Accepted and incorporated herein. 25. & 26. Accepted. FOR THE RESPONDENT: Accepted and incorporated herein. & 3. Accepted and incorporated herein. Rejected as the total amount paid by EIP for the buildings constructed by Respondent. The figure is somewhat higher due to deposit and amounts paid to suppliers by EIP. Accepted and incorporated herein. * At this point, Respondent's proposed Findings of Fact become misnumbered. There are two numbers 5. The subsequent numbers are as reflected in Respondent's submittal. 5. - 9. Accepted and incorporated herein. 10. - 12. Accepted and incorporated herein. 13. - 15. Accepted and incorporated herein. 16. Accepted. 17 & 18. Accepted. Alleged but not proven. Accepted. Rejected as contra to the weight of the evidence. Accepted and incorporated herein. COPIES FURNISHED: Tracy Sumner, Esquire William S. Cummins, Esquire Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Kurt R. Borglum, Esquire 366 East Graves Avenue, Suite B Orange City, Florida 32763 Jack McRay General Counsel Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (2) 120.57489.129
# 9

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer