Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID L. NORRIS, 88-000275 (1988)
Division of Administrative Hearings, Florida Number: 88-000275 Latest Update: Sep. 30, 1988

Findings Of Fact The foregoing findings of fact 1, 2, and 3 are incorporated herein by reference as if fully set forth anew. On January 8, 1987, the Respondent was found guilty of violating Sections 489.129(2), 489.129(3), and 489.129(1)(g) Florida Statutes, by the Construction Industry Licensing Board in DPR Case No. 60987, DOAH Case No. 88- 0002. The Respondent was not present at that Board meeting. He asserted this was due to lack of timely notice of the Board's meeting. Respondent was fined $1,000 by the Final Order of the aforementioned Board filed/served on February 20, 1987. The Respondent has failed to pay the fine. Respondent has not appealed the final order or fine. Respondent expressed himself at formal hearing as intending never to pay the lawfully imposed fine.

Conclusions The foregoing Conclusion of Law 14 is adopted and incorporated herein as if fully set forth anew. Respondent is charged with gross negligence, incompetence or misconduct in the practice of contracting pursuant to Section 489.129(1)(m), Florida Statutes, for failure to pay his $1,000 fine pursuant to the Board's February 20, 1987 final order. However, Petitioner has cited no statutory or rule authority which labels a licensee's refusal to pay a fine or obey a final order of the Construction Industry Licensing Board as gross negligence, incompetence, or misconduct in the practice of contracting. (Emphasis supplied, see definition of "contracting" at Section 489.105, Florida Statutes). Without such authority, the factual allegations of the administrative complaint, although proved, support no conclusion that a statute or rule has been violated. Petitioner's recourse lies not in this forum but in enforcement, execution, and collection actions in Circuit court.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that: The Construction Industry Licensing Board enter its final order dismissing the charge of a violation of Section 489.129(1)(m). DONE and RECOMMENDED this 30th day of September, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of September, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 88-0275, 88-0732 The following constitute rulings pursuant to Section 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of Fact (PFOF). DOAH CASE NO. 88-0275 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is accepted in part in FOF 9. The remainder is rejected as mere argument or as based upon hearsay not properly in the record. DOAH CASE NO. 88-0732 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is mere legal argument addressing the underlying facts of the previous final order finding Respondent guilty of certain violations and assessing a $1,000 fine. Absent a timely appeal, these matters are immaterial and rejected. These proposals are also rejected as mere argument. COPIES FURNISHED: Fred Seely, Executive Director Construction industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 G. W. Harrell, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 David L. Norris 3144 Northwest 39th Court Lauderdale Lakes, Florida 33309 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.105489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HOWARD G. RIENECKER, 82-002261 (1982)
Division of Administrative Hearings, Florida Number: 82-002261 Latest Update: Jan. 31, 1984

The Issue Whether respondent's license as a certified general contractor should he disciplined on charges of abandonment, diversion, violation of applicable building codes, improper qualification of companies under whose name he was conducting business, and continued misconduct in the practice of contracting, in violation of Chapter 489, Part I, Florida Statutes.

Findings Of Fact At all times relevant to the charges, respondent was a certified general contractor holding license no. CG C015937. He now resides at 1210 Old Boynton Road, Apartment 113, Boynton Beach, Florida. (Testimony of respondent; P-1) I. Count I: Abandonment of a Construction Project On or about October 30, 1980, respondent, d/b/a P & R Construction, a subsidiary of New Visions, Inc., entered into a contract with Mr. and Mrs. A. J. Ervin to construct a bathroom addition to their residence located at 1119 Lake Terrace, No. 101, Boynton Beach, Florida, for the sum of $4,500. (Testimony of respondent) Respondent was the contractor of record for this project. He pulled the required building permit, hired the subcontractors, and supervised the project. Robert Popiel, owner of New Vision, Inc., kept the company's books, paid bills, and handled sales. (Testimony of respondent; P-9) In June of 1981, respondent abandoned the construction project, leaving it uncompleted. Neither the bathroom door nor the shower door had been installed; exterior stucco beneath the bathroom window (which had been removed to repair a leak) had not been replaced; and the bathroom floor was unfinished. Final inspections had not been made and a certificate of occupancy had not been obtained. During the next four or five months, Mr. Ervin tried, unsuccessfully, to locate respondent and persuade him to return and complete the project. Eventually, Mr. Ervin hired another contractor and paid him $500 to complete the unfinished work. (Testimony of Ervin, respondent) When respondent abandoned the project, the plumbing (Archie's Plumbing), roofing (Modern Roofing), and electrical (Jerry's Electric) subcontractors, who had performed work and furnished materials for the project, were left unpaid. The improvements were thus subject to the placement of contractors' liens. The subcontractors were owed a total of $2,107.21, although they eventually settled with the owner for a total payment of $1,100. (Testimony of Ervin, Yedvarb, Grummer) Moreover, when respondent abandoned the project, there were leaks in the roof, where the bathroom joined the existing structure, and leaks below the bathroom window. (Testimony of Ervin) During this time, respondent was undergoing a divorce and moving from one motel to another. Mr. Ervin tried repeatedly to contact him, but respondent neither returned his phone calls nor answered his messages. Despite the best efforts of Mr. Ervin, respondent was nowhere to be found. II. Count II: Diversion of Monies Respondent did not receive a fixed salary from New Visions, Inc. Periodically, he would be paid by simply withdrawing funds from the company. During the time in question, New Vision, Inc., had four construction projects underway and respondent withdrew approximately $500. (Testimony of respondent, Popiel) The various New Vision, Inc., projects, including the Ervin project, were apparently underbid. Subcontractors were paid by Mr. Popiel out of incoming funds. But both he and respondent realized that the incoming money under the various contracts would be insufficient to pay all subcontractors for work performed. (Testimony of respondent, Popiel) Respondent was aware that the Ervin project was "running close" and that it "was probably running over" the contract price. (TR-53) It has not been shown that respondent diverted funds received for the completion of the Ervin project and that, as a result of such diversion, he was unable to complete the work. The subcontractors were not paid because the Ervin project incurred costs which exceeded the contract price. And, since New Vision, Inc., was experiencing similar difficulties elsewhere, it had insufficient funds to cover the excess costs of the Ervin project. (Testimony of respondent, Popiel; P-9, p. 32) III. Count III: Deliberate Violation of Building Code The Department alleges that respondent violated the applicable building code (Section 105.1, City of Boynton Beach Code of Ordinances) by covering the roof before the proper city inspection had been made. Pursuant to this code, it was respondent's duty to order the flat roof sheathing inspection; but it was the roofing contractor's responsibility to obtain the "tin tag" inspection before covering the roof. This is an inspection which is required to ensure that the base sheet or black felt is properly installed. Even though it was the roofing contractor's duty to call for such an inspection, the general contractor remained responsible for the entire project. (Testimony of Howell, respondent) In this case, respondent called for the sheathing inspection but the roofing contractor laid the felt and covered the roof without first calling for the requisite tin tag inspection. The building code violation was thus primarily the fault of the roofing contractor and only secondarily, or derivatively, the fault of the respondent. No evidence was presented to show that respondent approved, or knew, in advance, of the roofing contractor's failure to call for the tin tag inspection. Respondent's failure to ensure that the roofing contractor called for the required inspection cannot, without more, support a conclusion that respondent knowingly and deliberately violated an applicable building code. (Testimony of Howell, respondent) IV. Count IV: Acting in a Capacity of a Contractor Under a Name Other Than as Certified Respondent, d/b/a P & R Construction, a subsidiary of New Vision, Inc., contracted for and constructed a bathroom addition to the Ervin residence. However, neither company was qualified with the Construction Industry Licensing Board. V. Count V: Misconduct in the Practice of Contracting In this count, the Department alleges that, by virtue of the misconduct alleged in Counts I through IV, respondent is guilty of "misconduct in the practice of contracting." No additional acts of respondent were complained of or alleged. It follows that respondent can be found guilty of this charge only to the extent he is found guilty of the charges contained in Counts I through IV. VI. Mitigation There is no evidence that respondent has ever before been the subject of a disciplinary proceeding brought by the Construction Industry Licensing Board. He has worked in construction most of his life and this is the only business he knows. It is his livelihood, and, in his words, the only way "I can make a decent living." (TR-134) He is 59 years old. His goals are modest and tempered by experience: I'm just a small, small operator, and I work to make a living. I'm not going to get rich. I'm too old to get rich. Those things, thirty years ago I had that in mind. TR-134. He now realizes, better than before, the value of his contractor's license. His misconduct in connection with the Ervin project occurred when he was in the midst of a divorce and a personal ordeal. In his own words: And I bounced from place to place. I bounced off the bottom. I was living down at a flea bitten motel here. The roaches were so thick that I never thought I'd survive it. So now I guess--now I got married last September and I guess I'm getting to appreciate things which I took for granted before. I'm just getting so I appreciate them now and what-- you know, what I got and what I can do. TR-136 He admits that he did not fulfill his responsibilities from the Ervin project and understands better the hardships which his conduct imposed on Mr. Ervin.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Construction Industry Licensing Board impose a $1,000 fine against respondent for violating Section 489.129(1)(g), (k) , and (m), Florida Statutes. DONE and ENTERED this 7th day of November, 1983, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of November, 1983.

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT D. HUEY, 87-004505 (1987)
Division of Administrative Hearings, Florida Number: 87-004505 Latest Update: Oct. 31, 1988

The Issue Whether Respondent violated Sections 489(1)(d),(j) and (m), Florida Statutes?

Findings Of Fact At all times relevant Respondent was licensed as a registered residential contractor in Florida and held license number RR0046781. Sometime in late April, 1985, Respondent entered into a contract with Mr. Reames. The contract called for Respondent to build a house at 1512 S.E. 24th Avenue, Ocala, Florida. Mr. Reames moved into the house on December 23, 1985, after a certificate of occupancy was issued, even though the house was not fully completed. Mr. Reames completed a "punch list," consisting of an undetermined number of items which needed to be completed, and asked Respondent to complete the items. Most items in the punch list were never completed by Mr. Huey. After the initial attempt by Mr. Reames to get Huey Construction Co. to complete the items in the punch list, Mr. Reames did not contact Huey Construction Co. about the other problems found subsequently. In March or April, 1986, Mr. Reames noticed that the wood floor was buckling and separating. He contacted Mr. Gassett, the person who had installed the floors, who determined that a water leak was causing the problem. In November, 1986, Mr. Reames hired Mr. Clyatt, a licensed general contractor, to inspect the house, to go over the punch list items which needed to be completed, and to correct other items which were discovered to be inadequate. In the first week of January, 1987, Mr. Norton, the chief building inspector for the City of Ocala, was asked by Mr. Reames to inspect the house. Mr. Norton found a number of problems and identified some violations of the City of Ocala Building Code (Code) which was in effect at the time the house was built. The inadequacies, problems and code violations found by Mr. Clyatt and Mr. Norton are set forth below. Ventilation The Code requires 1 sq. ft. of opening for each 150 sq. ft. of crawlspace, in order to provide ventilation. Since the house had 2720 sq. ft. of crawlspace, it needed 18 sq. ft. of openings. The house, however, had only 6 openings of 1 sq. ft. each, or 6 sq. ft. of openings. Additionally, the plans for the house indicated where the openings were to be located and the completed house did not meet the plan specifications in this area. Mr. Clyatt added 15 openings, 8 in. by 12 in. each. In addition to the inadequate openings, one area of the crawlspace was completely enclosed, with no ventilation. The Code requires that attic ventilation for this type of house be 1 sq. ft. of opening for each 300 sq. ft. of space. The plans called for 3 in. by 12 in. vents at 24 in. intervals. The openings in the house were approximately 2 in. in diameter and were placed sporadically. From a visual inspection, without taking actual measurements, the openings for attic ventilation were inadequate and did not provide the ventilation required by the Code. Roof The roof of the house contained exposed nails and staples on the shingles, including some which had rusted. Nails and staples should not be exposed on a shingle roof, since they can lead to leaks. The roof leaked in one area in the back of the house. Mr. Reames contacted H & B Roofing, the subcontractor who had installed the roof, who corrected the problems with the roof. Driveway The Code requires that a driveway permit be obtained prior to the installation of a driveway. Also, the Code requires an inspection of the driveway prior to the concrete being poured. Respondent obtained the required permit, but failed to call for the required inspection prior to pouring the concrete. By letter dated December 10, 1985, Respondent notified the Building Inspection Office of the City of Ocala that the driveway was poured according to the Code. By the time of the inspections by Mr. Norton and Mr. Clyatt, several cracks were present in the driveway. SubFloor Due to the water damage set forth in paragraph 5, supra, the wood floor was removed in late December, 1986 or early January, 1987. The plans originally called for the subfloor to be constructed of one-half inch plywood decking, particle board, and 15 lb. felt paper. However, the Code requires subfloors to be constructed using three-quarter inch plywood, and the plans contained a penciled in notation where the one-half inch was changed to eleven- sixteenths. The subfloor had been constructed using one-half inch CDX plywood decking with particle board on top. No felt paper had been used. Additionally, the subfloor had been nailed in violation of the Code. The Code requires nails to be spaced two and one-half inches on the perimeter of the plywood and four inches in the interior area of the plywood. The subfloor of the house contained boards which had only been nailed on the perimeter and boards which had a large number nails in one area, far in excess of the amount required by the Code. Girders When Mr. Clyatt inspected the house he discovered that approximately 6 of the wood girders supporting the floor appeared to have been cut short and, instead of bearing on the stem wall bearing plate, were supported by posts made of two-by-four and two-by-six non-pressure treated lumber. The posts were resting on soil and the bottom part of the posts had decayed. This construction is a violation of the Code which requires that pressure treated wood be used, and is a violation of construction standards which require that the girders rest on the bearing plate or on concrete. See Petitioner's Exhibit 6. Also, the girders supporting the wood floor were not resting directly on the block piers. Wood shims had been added to fill the space between the girders and the block piers. The wood shims were not pressure treated. The Code requires that pressure treated wood be used in this situation. Additionally, proper construction requires that the girders rest directly on the block piers. Foundation Wall A foundation wall was not bearing on the footing properly. The foundation wall was constructed of 8-inch block and portions of the wall had only one to two inches bearing on the footing; the rest of the wall was resting on the soil. This is a violation of the Code. This problem was corrected by Mr. Clyatt by removing the soil on which the wall rested and pouring concrete under the wall. See Petitioner's Exhibit 7. Cabinets The cabinets in or near the utility room area of the house were loose and separating from the soffit and the wall.

Recommendation Therefore, based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order reprimanding Respondent and imposing a fine of $1500.00. DONE and ORDERED this 31st day of October, 1988, in Tallahassee, Florida. JOSE A. DIEZ-ARGUELLES Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 1988. APPENDIX Case Number 88-5570 The parties submitted proposed findings of fact which are addressed below. Paragraph numbers in the Recommended Order are referred to as "RO ." Petitioner's Proposed Findings of Fact Proposed Finding of Fact Number Ruling and RO Paragraph Accepted. RO1. Accepted. RO2. Accepted. RO3,4. First sentence, Accepted RO7. Second sentence accepted for proposition that Mr. Reames paid Mr. Clyatt $30,000 for work done on the house. However, the evidence fails to establish what portion of this amount was paid for problems caused by Respondent. 5-10. Accepted generally as to what Mr. Clyatt observed. RO19,20. But see discussion in Conclusions of Law portion of this RO. Accepted. RO13. Accepted generally. RO14. Respondent was not asked to repair the shingles when this deficiency was discovered about one year after Respondent had ended work on the house. First sentence rejected. Second sentence, accepted R016, but no competent substantial evidence was presented to show what caused the cracks. Accepted generally as to what was observed. RO22. But see discussion in Conclusions of Law portion of RO. Accepted. RO18. Accepted. RO18. Accepted. RO21. Accepted. RO21. Accepted. RO10,11. Accepted. RO10,11. Accepted. RO17. Accepted. RO12. Accepted. RO12. Accepted. RO15. Accepted. RO15. Accepted. RO8. Respondent's Proposed Findings of Fact Respondent's post-hearing statement consists of a two page letter with attachments. The attachments have been addressed in the Background section of this Recommended Order. The proposed findings of fact contained in the letter are addressed below. References are to paragraphs and sentences within each paragraph. Proposed Finding of Fact Number Ruling and RO Paragraph Par. 2 RO2 establishes that a contract existed; no finding is made as to whether the contract was oral or written, or as to what the contract amount was. Par. 3 First sentence is not supported by the evidence. Second sentence, accepted. Third-Fifth sentences rejected as not supported by competent evidence; however, no finding is made as to who is at fault for this problem. See Conclusions of Law. Fifth sentence is not a finding of fact. Par. 4 Not a finding of fact. Par. 5 (References are to statements after each number in the paragraph) #8 is accepted generally. RO15. #9 rejected as not supported by competent evidence. #10 rejected as not supported by competent evidence; some of the allegations were proven to exist as set forth in this RO. #11 and 12 are not findings of fact. COPIES FURNISHED: David L. Swanson, Esquire Staff Attorney Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Robert D. Huey 3710 Southeast 12th Place Ocala, Florida 32670 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Lawrence A. Gonzalez, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Bruce Lamb General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (6) 120.57120.6017.001489.105489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HODGES J. JEFFERSON, 82-002329 (1982)
Division of Administrative Hearings, Florida Number: 82-002329 Latest Update: Jun. 26, 1984

Findings Of Fact The Respondent, Hodges J. Jefferson, is a registered general contractor having been issued License No. CGC004463. The Petitioner is an agency of the State of Florida charged with regulating the licensure status of contractors in the State of Florida, and with enforcing the requirements of Chapter 489, Florida Statutes, pertaining to licensing and regulation of the practices of general contractors in Florida. On or about March 3, 1979, Respondent, doing business as H. J. Jefferson Brothers Construction, Inc., entered into a contract with Gladston Kemp to construct a room addition on his residence for a total sum of $14,900. The construction loan by which Mr. Kemp was to finance the addition was ultimately approved sometime in April 1979. The Respondent commenced work on the property after the first check was paid him by Mr. Kemp on May 3, 1979. The Respondent worked for two to three days digging the foundation, constructing the foundation and the brick wall involved and then stopped work for a period of four to five weeks. He then came back and worked on the addition, finishing construction of the foundation, the block walls, the tie beam and the bedroom portion of the roof up to the first layer of tar paper on one side of the addition. The other side of the addition to Mr. Kemp's house was left at that point with the roof not being constructed at all. Up to July 20, 1979, Mr. Kemp had paid the Respondent a total of $7,500, inasmuch as the contract called for payments in one-third increments of the total contract price at various stages of construction. At that point the Respondent left the job after being paid $7,500 of the total price. By letter of July 24, 1979, the Respondent demanded an additional $2,900 which would complete approximately the second one-third of the total contract price and on the following day, July 25, Mr. Kemp paid the Respondent the $2,900. Thus, at that point, July 25, 1979, Mr. Kemp had paid the Respondent a total of $10,400. The Respondent did not come back and continue construction of the project. Mr. Kemp tried repeatedly to contact the Respondent, to no avail. After numerous efforts, he contacted him by telephone and the Respondent assured him that he would come by and send "his man" out to commence work, but no one ever appeared to continue the construction. Finally, in October, 1979, Mr. Kemp contacted the Respondent and he once again assured Mr. Kemp that he would come back to finish the job. Additionally, sometime after July 25, 1979, the Respondent demanded $375 from Mr. Kemp to pay for the architectural plans drafted by Edna Mingo, the architect who drafted the plans for the job in January, 1979. Mr. Kemp had already paid the $375 to Edna Mingo in January of 1979. In any event, he relented and gave the Respondent the additional $375 in order to induce him to come back and finish the job. Finally, in the latter part of October 1979, the Respondent returned to the job and began putting rafters on the bedroom portion of the addition. He then asked Mr. Kemp to advance him some more money, over and above the $10,775 Mr. Kemp had already paid him. The roof on one-half of the addition was still not finished, but Mr. Kemp gave the Respondent another $1,700 by check dated November 16, 1979. Approximately two weeks thereafter Mr. Kemp gave the Respondent another $500 in cash. Shortly before Thanksgiving 1979, the Respondent came to the project and asked Mr. Kemp to advance him some more money which Mr. Kemp refused to do. Several days later Mr. Kemp received a "demand letter" from the Respondent asking for more money and reminding him of his obligation to honor the contract. At that point Mr. Kemp contacted the Respondent and met with him at the job site, whereupon Mr. Kemp displayed to him all the checks he had already paid him, informing him of the total amount of money paid and that he did not feel that he owed him any more money. He demanded that the Respondent complete his job. The Respondent, in turn, sent Mr. Kemp a letter on November 21,1979, informing him that he would complete the job if Mr. Kemp gave him the last one- third of the contract price. At that point Mr. Kemp had already given the Respondent $12,975, so, less than one-third of the contract price was still outstanding. The Respondent assured Mr. Kemp in that letter (Petitioner's Exhibit 17, in evidence) that he would complete the job by December 15, 1979. Mr. Kemp gave the Respondent another $2,100 making a total of $15,075 paid to the Respondent (the contract price being $14,900). Respondent did not complete the job in December 1979 and indeed never completed it. He went to Mr. Kemp's house "one night in December" and discussed the job with Mrs. Kemp's wife and assured her that he was going to try and get the job "out of the way" by January. The Respondent never came back to continue working on the job and never communicated with the Kemps after December 1979, except for a fist fight between Mr. Kemp and the Respondent engendered by the bitterness resulting form this dispute which occurred in July 1980. Mr. Kemp and his wife, however, went to the Respondent's home in January 1980 to ask him when he would complete the job. He became abusive and would not give them a copy of the plans so that the Kemps had to get a duplicate copy from the architect so Mr. Kemp could then obtain the appropriate inspections from the building department. There were no extra additions to the contract and the only work ever required of the Respondent was that described on the building plans. The fees fro the electrical, plumbing, and building permits were paid by Mr. Kemp. At the time the Respondent left the job it was approximately 55 percent complete. The roof was incomplete. Mr. Kemp had to do the "rough plumbing," the "finish plumbing," install a half bath, a utility room and a full bath in the bedroom. Mr. Kemp also had to "rough in" the electrical wiring, that is, run the electrical service wiring inside the house for the finish electrical work. Mr. Kemp also had to install drywall and plaster inside and outside the house and completely "finish out" the addition to his home. He supplied some of the labor for this himself and hired various subcontractors to do other portions of the work such that he ultimately spent approximately $9,000 in excess of the amount paid Respondent in order to finish the job in accordance with the building plans. Completion of the work thus cost the Kemps an additional $9.000 above the $15,075 already paid the Respondent, with the use of the monies paid Respondent for the last 45 percent of the work required of him by the contract being unexplained, except for the Respondent's general statement that some of that money was attributable to unaccounted for "overhead" costs. The Respondent left the job in terms of performing any work in October 1979, promised to finish it in December and later in January 1980, and never returned to finish the job or perform any more work such that sometime in the summer of 1980 the Kemps ultimately finished the job through their own labors and that of various subcontractors and materialmen they were forced to hire and pay.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED that the contractor's license of Hodges J. Jefferson be suspended for a period of 5 years, provided however, that if he makes full restitution to the Kemps of all monies they expended for labor, materials and permits to complete the work he was contractually obligated to complete within one year from a Final Order herein that that suspension should be terminated and his license reinstated. DONE AND ENTERED this 14th day of March 1984 in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of March 1984. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Hodges J. Jefferson 2250 Northwest 194th Terrace Miami, Florida 33156 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (3) 120.57489.119489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EUGENE AMRHEIN, 84-002527 (1984)
Division of Administrative Hearings, Florida Number: 84-002527 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent, Eugene Amrhein, is a certified roofing contractor, license number CC C020238, and was the qualifying agent for Knight Roofing, Inc. at all times relevant to these cases. On or about December 16, 1982, Respondent, conducting business through Knight Roofing Inc., contracted with Evelyn Nickerson for reroofing of a home at 707 N.E. 7th Street, Fort Lauderdale, Florida for a contract price of $1,485. She gave Respondent a downpayment of $785, and upon completion of the project paid the balance of $700. Respondent commenced work on the project without obtaining a permit, as required by Section 301.1(k), South Florida Building Code. Respondent also failed to obtain an inspection as required by Section 305.2(a), of this code. On or about March 10, 1981, Respondent conducting business through Knight Roofing, Inc., contracted with Judevilla Geria for the rebuilding of an existing flat tile roof for a contract price of $4,100. Respondent did not obtain the required building permit, in violation of Section 301.1(k), South Florida Building Code. Respondent did not perform the work contracted in that only a coat of paint was applied. He failed to rebuild the existing roof by recementing each tile, replacing rotten lumber, soffitt and fascia, nor did he replace approximately 50 tiles as required by the contract. However, Respondent has honored his warranty to Geria to the extent of repairing four leaks that developed subsequent to the work. On or about June 29, 1982 Respondent contracted with Golda Oxenberg to waterproof a roof at 3253 Foxcroft Road, Miramar, Florida. The contract price was $1,000. The project was completed and Respondent was paid in full. The Respondent violated Section 301.1(k), South Florida Building Code by failing to obtain a permit for this project. On or about August 22, 1983, Knight Roofing Inc., contracted with Joseph Castellano to repair the roof of a home at 1215 1st Street, Indian Rocks Beach, Florida. The contract price was $600, and included a two-year warranty. At no time was a licensed roofer present at the job site. David Ness, then an unlicensed individual, contracted for the work, performed the work, and received the payments. At no time did the Respondent supervise the work on the Castellano home. After completion, the roof began to leak. Respondent has not repaired the leak, despite his warranty. Respondent violated Section 108.2(d), Standard Building Code (adopted by Indian Rocks Beach Ordinance 291) by failing to obtain required inspections. However, no evidence was presented to show that Respondent violated Section 108.2(b), Standard Building Code, since a permit was obtained. Respondent has moved, but failed to notify the Construction Board of his new address as required by Rule 21E- 15.07, F.A.C. On March 7, 1984, Respondent contracted with Ralph Huff for roofing work at 3210 N.E. 9th Avenue, Pompano Beach, Florida. The contract price was $5,725, and the work was completed. Respondent admitted at hearing that he failed to follow up on his warranty agreement. Respondent did not violate Section 305.2(a), South Florida Building Code since a final inspection was obtained on October 25, 1984.

Recommendation Based on the foregoing, it is RECOMMENDED that Petitioner enter a Final Order revoking Respondent's license. DONE and ENTERED this 25th day of June, 1985 in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 FILED with the Clerk of the Division of Administrative Hearings this 25th day of June, 1985. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 William F. Beggs, Esquire BEGGS and VECCHIO 3012 East Commercial Boulevard Fort Lauderdale, Florida 33308 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee Florida 32301 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville Florida 32202

Florida Laws (5) 15.07455.227489.105489.119489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs EDUARDO KIRKSEY, 90-007869 (1990)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 14, 1990 Number: 90-007869 Latest Update: Jun. 05, 1992

Findings Of Fact Eduardo Kirksey is licensed as a certified residential contractor, holding license CR C012717. He qualified a corporation known as Modern Construction Company, Inc. (Modern) to engage in contracting.Modern entered into a contract on about July 28, 1986 with Ira Goldstein of 4440 Southwest 32nd Drive, Hollywood, Florida for construction of two-story room addition which would include a family room, bedroom and bath. Modern was to provide the plan by which the addition would be built. A rough sketch of the addition is included on the contract. More specific plans, which are similar to architectural drawings, were thereafter prepared for submission with the building application, which Modern filed with the Broward County Building and Zoning Enforcement Division. The contract was later amended to add a balcony around the second floor of the addition. The plans which are in evidence as Department Exhibit 4 are the second set of plans. According to these plans, the second floor bedroom had a 6" x 6" sliding glass door. The door opened on to a balcony which was created by cantilevered joists consisting of 2" x 10" pieces of lumber bolted to 2" x 12" rafters between the first and second floor. These 2" x 10" members extended out four feet from the building. According to the plans, 2" x 6" decking was to be placed across these joists, and an appropriate railing would then be placed around the balcony. Mr. Kirksey submitted the amended application for the permit and the plan to the Broward County Plan Review Board for approval, and it was approved. After construction began, Mr. Goldstein determined that he did not wish the floor of the balcony to be pressure treated wooden decking. Instead, he wanted a tile floor on the deck. Mr. Kirksey had already filed two sets of plans with Broward County on the project, the first for the addition without the balcony, and the second for the addition with the balcony. He did not want to file a third building permit application which would also require the submission of new drawings. Mr. Kirksey did agree to change the construction to accommodate Mr. Goldstein's desire to tile the balcony but declined to do the tile work himself as part of his contract with Mr. Goldstein. Mr. Goldstein was to arrange for the tiling of the deck. The original design for the decking would have spaced the 2" x 6" lumber which made up the decking with small spaces between each piece of lumber to allow water to fall through during rain. In order to lay tile down, it was necessary to place plywood across the joists, rather than 2" x 6" pressure treated lumber. Before the plywood could be laid, however, Mr. Kirksey had to remove the 2" x 10" cantilevered joists from between the first and second floor, because the original design called for those joists to be level. They were reinstalled at about a 1/2 inch slant so that the water would then drain from the balcony after it had been tiled. In addition, Mr. Kirksey then had to place soffit under the balcony, and put facia around the bottom of the deck. Neither the soffit nor the facia were required in the plans. Although it was more expensive for Mr. Kirksey to add these items, Mr. Goldstein was not charged any additional money for this work. The plywood that was put down over the 2" x 10" rafters instead of the pressure treated 2" x 6" lumber was 3/4 inch exterior grade plywood. Pressure treated plywood was not used because the plywood was to be covered with tile, and if properly tiled, pressure treated plywood is unnecessary. Moreover, even if tile is put over pressure treated plywood, if tile is not laid properly, the pressure treated plywood will rot as well as exterior plywood will rot. It would not have been possible to place tile over the 2" x 6" pressure treated lumber which the amended plan filed with the Broward Building and Zoning Enforcement Division had called for. The 2" x 6" members would shrink and move, causing the tile to crack. Some type of plywood had to be used instead of decking to permit Mr. Goldstein to tile the deck. The 3/4 inch plywood which Mr. Kirksey used met or exceeded the standards established by the South Florida Building Code. No sealant, or paint, was applied to the plywood, nor was the deck covered with visquine. Preparation of the plywood before the tile was placed over it would be the job of the person doing the tile work. An inspector from the Broward County Building and Zoning Enforcement Division visited the site on a number of occasions. During the course of those inspections some of the work was originally rejected by the inspector. For example, the balcony railing pickets had a spacing greater than 5 inches and the top of the rail was only 36 inches high, not 42 inches high. As a result of this rejection, the picket spacing and railing were changed. Ultimately, the inspector gave final approval after having seen the plywood deck, even though no new plans had been submitted to change the deck to have a plywood floor for tile rather than the originally permitted 2" X 6" pressure treated lumber deck. When the job was completed by Modern it was in the condition a project would normally have been left where the contractor was not responsible for laying the tile over the balcony floor. Because the floor was to be tiled, there was no reason for Mr. Kirksey to have painted the balcony floor. In addition, the contract did not require that any painting be done. Mr. Goldstein did the tile work on the deck himself although he had no prior experience in laying tile. Mr. Goldstein spoke with one of Modern's workmen about how to lay tile. This was an informal conversation, and Mr. Kirksey, the contractor, never advised Mr. Goldstein on how to lay tile. I do not accept the testimony of Mr. Goldstein that the employee of Modern who explained to him how to lay tile was the job foreman. Nothing in the contract with Modern required Modern to lay tile, or to advise Mr. Goldstein how to lay tile, so whether the person who discussed laying tile with Mr. Goldstein was a foreman is not significant. Sometime after all the work had been completed by both Modern and Mr. Goldstein, Mr. Goldstein's daughter Evette stepped out onto the balcony, and her foot and leg went through the balcony. This occurred because the plywood had not been sealed or protected before the tile was laid by Mr. Goldstein. As a consequence, the plywood had rotted under the tile. The rot also extended to the supporting joists. Broward County has adopted and incorporated into the Broward County Charter, Chapter 71-575, Laws of Florida, a Special Act of the Legislature. Both adopt for Broward County the "South Florida Building Code, Dade County 1970 edition, as amended." The Department included with its proposed recommended order portions of the South Florida Building Code, 1986 Broward County edition, for the purpose of demonstrating that the conduct of Mr. Kirksey violated Section 301(a) and 302.1(e) of that 1986 code. As a matter of evidence, the 1986 Broward County edition of the Southern Florida Building Code does not appear to apply. The Department's exhibit 7, which is "a copy of the Broward ordinance which adopts the South Florida Building Code" (Tr. 6) shows that it is the South Florida Building Code, Dade County 1970 edition which applies in Broward County. No portion of that document has been offered in the record of this case. As a consequence, there is no record evidence that Mr. Kirksey has violated a portion of an applicable code. It is true that Mr. Joseph Montagnino testified that Section 301(a) of the South Florida Building Code would not permit a change in a plan once it had been approved (Tr. 22, 104). In a case such as this, however, it is necessary for the Department to produce the text of the applicable building code, which has been adopted either by State statute or local ordinance. It cannot prove a violation through the testimony of a witness who merely characterizes his recollection of the text of an authoritative code. Moreover, other witnesses who are experts in construction trades in Broward County testified that it is common for inspectors to approve changes such as that made by Mr. Kirksey here, at the request of Mr. Goldstein, to substitute plywood flooring for pressure treated decking, without the need for amended plans or permits. (Tr. 75-77, 88- 89). Without evidence of the text of the applicable code, it is not possible to determine whether these experts, or Mr. Montagnino are correct. Since Mr. Goldstein, the homeowner, intended to do the tile work, it would not have been Mr. Kirksey's responsibility to pull additional permits for the tile work. At most, Mr. Kirksey's duty might have been to have obtained approval of amended plans, showing the slight pitch of the joists supporting the balcony floor, and the substitution of plywood and tile for 2" X 6" pressure treated lumber as the flooring for the balcony. Mr. Kirksey is in no way responsible for the inadequate preparation of the plywood surface for the application of the tile. Mr. Kirksey is in no way responsible for informal advice given by an employee of Modern, whose identity cannot be determined from the evidence in this case, to Mr. Goldstein about the proper way to prepare the plywood deck for tiling. Tiling was not part of the construction contract which Mr. Goldstein entered into with Mr. Kirksey's company. Mr. Kirksey is therefore not liable for inadequate supervision of employees on the job. Mr. Kirksey's employees performed the work required under the agreement which Modern had with Mr. Goldstein, as the parties amended it after the construction began.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that a Final Order be entered by the Board finding Eduardo Kirksey not guilty of the violations set out in Counts I, II or III of the Administrative Complaint. RECOMMENDED this 24th day of December, 1991, at Tallahassee, Florida. WILLIAM R. DORSEY, JR. Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of December, 1991.

Florida Laws (3) 120.57489.105489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID COBB, 79-002403 (1979)
Division of Administrative Hearings, Florida Number: 79-002403 Latest Update: May 30, 1980

The Issue Whether the Respondent willfully violated local building codes and abandoned a job.

Findings Of Fact David Cobb is a registered general and registered roofing contractor with the Florida Construction Industry Licensing Board. The job in question was done in Gainesville, Florida. Gainesville has a local building code, having adopted the Southern Standard Building Code, but does not have a local competing board. Cobb entered into a contract with John Larramore for a room addition to Larramore's home. Larramore paid Cobb a total of $2,475.84 on the job which was priced as $4,080.24, an amount which included the price of floor covering which both parties acknowledged would be purchased by Larramore and deducted from the monies paid Cobb. Cobb began work on the project. Larramore was not happy with the craftsmanship on the job, which was overseen by Cobb's foreman. Eventually, Larramore contacted a friend who was a contractor. This friend indicated to Larramore that the job should be inspected by the building inspectors of Gainesville, and Larramore contacted the Building Department of Gainesville. Pending inspection by the Department, Larramore told Cobb to stop work until he was contacted again. The chief building official, Leslie Davis, inspected the Larramore job on May 4, 1979. He found several violations of the local building code. Davis was accompanied by the Board's investigator, Herman Cherry. Davis contacted Cobb and advised him to correct the code violations. Davis sent Cobb a letter on May 10, 1979, outlining the violations and giving Cobb 14 days to correct these violations. See Exhibit 5. Cobb tried to contact Larramore by telephone without success concerning correction and completion of the job. Eventually, Cobb wrote Larramore an undated letter, Exhibit 4, which was written after the inspection by Davis and Cherry on May 4, 1979. Larramore was uncertain of the date he received the letter but did acknowledge it was after the Davis/Cherry inspection. Larramore did not contact Cobb after he received Cobb's letter. Instead, he contracted with another contractor to complete the job. This contractor began work on May 17, 1979.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board take no action against David Cobb. DONE and ORDERED this 9th day of April, 1980, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Michael E. Egan, Esquire 217 South Adams Street Mr. David Cobb Post Office Box 1306 16146 James Couzens Freeway Tallahassee, Florida 32301 Detroit, Michigan 48221

# 7
RAFAEL R. PALACIOS vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD, 99-004163F (1999)
Division of Administrative Hearings, Florida Filed:Miami, Florida Oct. 01, 1999 Number: 99-004163F Latest Update: Jan. 08, 2001

The Issue Whether pursuant to Sections 57.111 or 120.595(1), Florida Statutes, Petitioner Rafael R. Palacios (Palacios) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by the Respondent, Department of Business and Professional Regulation (Department). Whether pursuant to Section 120.595(1), Florida Statutes, Petitioner Steven L. Johns (Johns) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by Respondent.

Findings Of Fact Petitioner, Steven L. Johns, is a Florida Certified General Contractor and the principal qualifier for C. G. Chase Construction Company (Chase Construction). In 1994, Chase Construction entered into a construction contract with Carnival Cruise Lines for an expansion project at the Port of Miami. Chase Construction subcontracted the mechanical work to R. Palacios & Company. Petitioner, Rafael R. Palacios, is the president, primary qualifier, and 100 percent stockholder of R. Palacios & Company. Palacios' principal place of business is located in Miami, Florida. In July and December 1998, Palacios employed less than 25 employees and had a net worth of less than $2,000,000. The contract for the Port of Miami project consisted of two phases. Phase I was to construct an arrival lobby and an enclosed walkway to a terminal. Phase II included the addition of boarding halls, the renovation of an existing elevated area, and the addition of baggage areas. A foundation permit had been pulled for Phase I. The foundation work was quickly completed, and Chase Construction representatives advised both the Port of Miami and Carnival Cruise Lines that they could go no further without a permit. Work stopped for a short period of time. In June 1995, a Representative from the Port of Miami called Chase Construction and told them to go to the Dade County Building and Zoning Department (Building Department) the next day to meet with Port of Miami officials, the architect, and building and zoning officials. Johns sent Dave Whelpley, who was a project manager and officer of Chase Construction. Palacios did not attend the meeting. Dr. Carlos Bonzon (Bonzon) was the director and building official of Dade County's Building Department during the majority of the construction activities at the Port of Miami by Chase Construction. As the building official, Dr. Bonzon gave verbal authorization for the work on the project to proceed above the foundation without a written permit. Inspections were to be done by the chief inspectors for Dade County. After the meeting with the Building Department officials in June 1995, Johns understood that authorization had been given by the building official to proceed with construction without a written permit. Work did proceed and inspections were made on the work completed. The Dade County Building Code Compliance Office (BBCO) had the responsibility to oversee Dade County's Building Department. In early 1996, an officer of the BBCO accompanied a building inspector during an inspection of the Port of Miami project. It came to the attention of the BBCO officer that no written permit had been issued for the project. The BBCO officer notified the chief of code compliance for Dade County. A written permit was issued for Phase II of the Port of Miami Project on February 6, 1996, at which time approximately 80 percent of the work had been completed. On the same date, Chase Construction issued a memorandum to its subcontractors to secure the necessary permits. Shortly after the permits were issued, an article appeared in the Miami Herald concerning the project and the lack of written permits. Respondent, Department of Business and Professional Regulation (Department) became aware of the situation as a result of the newspaper article and began an investigation. Diane Perera (Perera), an attorney employed by the Department since 1993 to prosecute construction-related professional license law violations, played a major role in determining and carrying out the Department's subsequent actions regarding the Port of Miami project and persons licensed by the Department who had been involved in the project. The Department opened investigations against eight Department licensees. Those licensees included two building officials, Bonzon, and Lee Martin; four contractors, Johns, Palacios, Douglas L. Orr, and D. Jack Maxwell; one engineer, Ramon Donnell; and one architect, Willy A. Bermello. By Administrative Complaint prepared by Perera and filed on September 9, 1997, before the Building Code Administrators and Inspectors Board (BCAIB), the Department charged Bonzon with various violations of Part XIII of Chapter 486, Florida Statutes, for having allowed above-grade construction on the project to proceed in the absence of approved plans and building permits. In conjunction with the Bonzon case, Charles Danger (Danger), a licensed professional engineer and Director of BBCO testified in a deposition that above-grade construction of the project had proceeded without a building permit and without approved plans in violation of Chapter 3, Section 301 of the South Florida Building Code. He also testified that Bonzon had exceeded his authority under the South Florida Building Code by authorizing the above-grade construction and that the contractors who performed the work did so in violation of the South Florida Building Code. The Department's charges against Bonzon were resolved through a settlement agreement, whereby Bonzon agreed to relinquish his building code administrator's license. A final order of the BCAIB accepting the settlement agreement was filed on July 2, 1998. In the settlement agreement, Bonzon specifically agreed that his interpretation of the South Florida Building Code provisions, including portions of Section 301, was erroneous. On June 24, 1998, the Department presented the Department's Case Number 97-17322 involving Johns to the Division I Probable Cause Panel (PCP) of the Construction Industry Licensing Board (CILB). The panel members on this date were Gene Simmons and Wayne Beigle. Stuart Wilson-Patton and Leland McCharen, assistant attorneys general, were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the panel was Perera. The Department was requesting a finding of probable cause against Johns for a violation of Section 489.129(1)(d), Florida Statutes, for knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and specifications. Prior to the meeting of the Division I PCP of the CILB, Perera had furnished the two panel members documentary evidence pertaining to the case, copies of which were received in evidence at the final hearing as Respondent's Exhibits 5 and 13, with the exception of a letter dated July 31, 1998, from Petitioners' attorney, Renee Alsobrook. Respondent's Exhibit 5 consisted of materials taken from the Bonzon and Lee Martin cases, including the transcript of the December 22, 1997, deposition of Charles Danger, who was the building officer for the BBCO from 1991 to 1998. Respondent's Exhibit 13 was the investigative file for the Johns' case. The Division I PCP discussed Johns' case and voted to request additional information regarding whether any fast track ordinance existed in Dade County, and if so, how it might have applied to the Port of Miami project. On June 24, 1998, the Division II PCP of the CILB met and discussed the Palacios case, which was designated as the Department's Case No. 97-17313. The members of the panel were James Barge and Richard Cowart. Mr. Wilson-Patton and Mr. McCharen were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the PCP was Perera. The Department was requesting a finding of probable cause against Palacios for violating Section 489.129(1)(d), Florida Statutes, by knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and a building permit. Prior to the Division II PCP meeting, the panel members were provided with materials which were received in evidence at the final hearing as Respondent's Exhibits 5 and 14, with the exception of letters dated July 31 and August 26, 1998, from Renee Alsobrook. Respondent's Exhibit 14 is the Department's investigative file on the Palacios case. Following a discussion of the Palacios case, one of the panel members made a motion not to find probable cause. The motion died for lack of a second, and the panel took no further action on the case that day. Pursuant to Section 455.225(4), Florida Statutes, the case was treated as one in which the PCP failed to make a determination regarding the existence of probable cause and was presented to Hank Osborne, Deputy Secretary of the Department, to make a determination whether probable cause existed. On July 2, 1998, Deputy Secretary Osborne found probable cause, and the Department filed an Administrative Complaint against Palacios, charging a violation of Section 489.129(1)(d), Florida Statutes. The Department never served Palacios with the Administrative Complaint filed on July 2, 1998. The Department did not notify Palacios that the Administrative Complaint had been filed and did not prosecute the Administrative Complaint. At the time the Administrative Complaint was filed, the Department believed that the Legislature was in the process of enacting legislation to repeal Section 489.129(1)(d), Florida Statutes. Chapter 98-419, Laws of Florida, which became law on June 17, 1998, repealed Section 489.129(1)(d), Florida Statutes, effective October 1, 1998. Because of the repeal and the lack of a savings clause for pending cases, the Department determined that as of October 1, 1998, the Department did not have authority to take disciplinary action based on a violation of Section 489.129(1)(d), Florida Statutes. On December 18, 1998, the Department presented the Department's Case Nos. 97-17133 and 97-1732 to the PCPs for a second time with a recommendation to find probable cause that Johns and Palacios had violated Section 489.129(1)(p), Florida Statutes, for proceeding on any job without obtaining applicable local building permits and inspections. Mr. McCharen was present to provide legal advice to the PCPs. Ms. Perera was also present during the meetings of the PCPs. Documentary materials presented to the PCP considering Palacios' case included the materials on the Bonzon and Martin cases which had been previously presented to the PCP panel in June 1998 and the investigative files on Palacios. The investigative file included letters with attachments from Palacios' attorney Rene Alsobrook concerning the materials contained in the Bonzon and Martin cases as they related to Palacios and the investigative file on Palacios. Additionally, the investigative file contained a report from Frank Abbott, a general contractor who had been asked by the Department to review the file on Palacios. Mr. Abbott concluded that Palacios had violated several provisions of Chapters 489 and 455, Florida Statutes, including Section 489.129(p), Florida Statutes. The PCPs found probable cause in the Johns and Palacios cases. On December 23, 1998, the Department filed administrative complaints against Palacios and Johns alleging violations of Section 489.129(1)(p), Florida Statutes. The cases were forwarded to the Division of Administrative Hearings for assignment to an administrative law judge. Palacios and Johns claimed that they were relying on the authorization from Bonzon when they proceeded on the above-grade construction work. No formal administrative hearing was held on the administrative complaints filed on December 23, 1998. On December 18, 1998, a Recommended Order was issued in the related case against Lee Martin, Department Case No. 97-11278, finding that Mr. Martin, the building official who replaced Bonzon and assumed responsibility for the Port of Miami project, had the discretion to allow the remaining construction to proceed while taking action to expedite the plans processsing. A Final Order was entered by the Department dismissing all charges against Mr. Martin. On February 26, 1999, Petitioners Palacios' and Johns' Motions to Dismiss and Respondent's responses were filed. The Motions to Dismiss did not request attorney's fees or costs and did not reference Section 120.595(1), Florida Statutes. The motions did contain the following language: The DBPR has acted in an improper and malicious manner by precluding the Respondent from asserting his response to the second draft Administrative Complaint and requesting the Panel to find probable cause for reasons other than whether there was probable cause to believe the Respondent violated specific disciplinary violations. On March 19, 1999, the cases were consolidated and noticed for hearing on May 12-13, 1999. Section 489.129, Florida Statutes, was amended during the 1999 legislative session to provide: A contractor does not commit a violation of this subsection when the contractor relies on a building code interpretation rendered by a building official or person authorized by s. 553.80 to enforce the building code, absent a finding of fraud or deceit in the practice of contracting, or gross negligence, repeated negligence, or negligence resulting in a significant danger to life or property on the part of the building official, in a proceeding under chapter 120. . . . On April 15, 1999, the Department filed a Motion for Leave to Revisit Probable Cause Panel and to Hold in Abeyance. On April 20, 1999, Petitioners filed a response, stating they did not object to the granting of the motion to hold in abeyance. The final hearing was cancelled, and the cases were placed in abeyance. On May 24, 1999, the Department submitted a Status Report, stating that the cases would be placed on the next regularly scheduled PCP meeting scheduled for June 16, 1999. By order dated May 25, 1999, the cases were continued in abeyance. On July 1, 1999, Palacios and Johns filed a Status Report, indicating that the cases would be presented to the PCPs sometime in July and requesting the cases be continued in abeyance for an additional 30 days in order for the parties to resolve the issues. On July 30, 1999, Palacios and Johns filed a Status Report, stating that the cases were orally dismissed on July 28, 1999, and that a hearing involving issues of disputed facts was no longer required. Based on Johns' and Palacios' status report, the files of the Division of Administrative Hearings were closed by order dated August 3, 1999. No motion for attorney's fees and costs was filed during the pendency of the cases at the Division of Administrative Hearings. On August 3, 1999, orders were entered by Cathleen E. O'Dowd, Lead Attorney, dismissing the cases against Palacios and Johns.

Florida Laws (9) 120.569120.57120.595120.68455.225489.129553.8057.10557.111
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOSEPH F. SCIOLI, JR., 83-003040 (1983)
Division of Administrative Hearings, Florida Number: 83-003040 Latest Update: Jun. 26, 1984

Findings Of Fact At all times material hereto, Respondent has been a registered residential contractor having been issued license number RR 0040275. In approximately 1980, Respondent entered into a contract to erect a screen room for a Mr. Lewis. Under the terms of the contract, Respondent was to obtain the necessary building permit. After the contract had been signed, Respondent's grandfather died, and Respondent therefore went to New Jersey. He left the permit application with his qualifying agent to sign and process through the building department. When Respondent returned from New Jersey approximately 30 to 35 days later, he went to the Lewis job site and found the project almost completed. Respondent did not check to ascertain if the permit had been obtained, but rather completed the screen room himself. Lewis subsequently contacted Respondent to say that he had received a notice of violation from the building department for erecting a screen room without a permit. Respondent contacted the building department and advised that it was not Lewis's fault, but rather that it was Respondent's responsibility to pull the permit. Respondent was charged with unlawfully erecting a screen room without a permit; he appeared in court and pled guilty; and he paid a $250 fine pursuant to the adjudication of guilt entered on April 20, 1981, in the County Court in and for Dade County, Florida, in Case No. 81-50438. On June 24, 1981, Respondent submitted to the Construction Industry Licensing Board a Contractor's Registration application. On that application, Respondent answered in the negative the following question: "Has any person named in (i) below ever been convicted of any offense in this state or elsewhere other than traffic violations?" At the time Respondent gave that answer, he believed it to be true. He understood the question to call for information on criminal acts and did not comprehend the "screen room" charge to have been criminal conduct. Since Respondent answered that question in the negative, his application for registration was processed in accordance with normal procedures. Had Respondent answered that question in the affirmative, his application would not have gone through normal processing but rather would have been presented to the Construction Industry Licensing Board for the Board's determination of whether to approve the application based upon a consideration of the facts. On November 22, 1982, Respondent contracted with Naomi Blanton to construct an addition to Blanton's home located in the City of Miami, in Dade County, Florida, for a contract price of $11,250. When Respondent had first met with Blanton several months earlier, he had told her he could guarantee completion of the project within 45 days. No contract was entered into at that time, however, since Blanton had not obtained the financing she needed in order to construct an addition. When the contract was signed on November 22, Respondent told Blanton he would start the job when he finished the Chamber of Commerce building he was con structing but that he was starting a 12-unit duplex project around Christmas and would not be able to guarantee any 45-day completion deadline. Accordingly, when the contract was signed, no completion date was included in the terms of that written contract, since Respondent did not know when he could guarantee completion. The Blanton contract written by Respondent specifically provided that Respondent would obtain the building permit. On December 22 and 23, 1982, two of Respondent's employees arrived at the Blanton job site, dug a trench, knocked down the utility room, and moved Mrs. Blanton's washing machine. No further work was done until January 1983. Since Respondent knew that he was required to obtain the building permit before commencing any construction work, Respondent submitted his plans and permit application to the City of Miami Building Department. After the plans had been there about a week, he was advised that his plans would not be accepted unless they were drawn by an architect, although that is not required by the South Florida Building Code. After attempting several more times to obtain approval from the City of Miami Building Department, Respondent hired an architect to redraw the plans and secure the building permit. By this time, Respondent found himself unable to concentrate on operating his business efficiently, since he was preoccupied with spending time with his father who was dying of cancer. Also by this time, Blanton had commenced telephone calls to Respondent on an almost daily basis as late as 11:00 p.m. at his office, at his home, at his mother's home, and at his father's home. Respondent offered to return Blanton's deposit, but she refused to cancel the contract and threatened Respondent that she would sue him if he did not comply with that contract. Respondent commenced working on the Blanton job, although no permit had yet been obtained. The contract on the Blanton job called for payments at certain stages of the construction. By January 27, 1983, Respondent had completed a sufficient amount of the work under the contract so that Blanton had paid him a total of $8,270 in accordance with the draw schedule contained in the contract. Respondent ceased working on January 27, 1983, and advised Blanton and her attorney that he would do no further work until he could obtain the building permit, which he had still not been able to obtain. Although he told them his work stoppage was due to his continued inability to obtain the permit, he also stopped work due to his father's illness and his continued inability to get along with Mrs. Blanton. A delay occurred with the plans being redrawn by the architect Respondent hired to obtain the Blanton building permit, since the architect needed information from Blanton and she was out of town. After Blanton returned, the architect made unsuccessful attempts to obtain the building permit. Respondent and his architect were finally able to speak to one of the top personnel in the City of Miami Building Department about the problems they were experiencing in obtaining a building permit, and, at about the same time, Blanton contacted that same individual to complain that Respondent had no permit. On May 4, 1983, the building department finally accepted the second permit application together with the plans drawn by the architect, and the building permit was issued on May 4, 1983. No work was performed on the Blanton job between January 27, 1983, when Blanton paid Respondent the draw to which he was entitled by that date, and May 4, 1983, when the building permit was finally issued by the City of Miami. Respondent immediately resumed work and quickly completed the next stage of construction called for under the Blanton contract. Upon completing that next stage, he requested his next draw payment; however, Blanton decided not to pay Respondent for the work completed and had her attorney advise Respondent not to return to the job site. Blanton then had a friend of her son come to Miami from Wisconsin to complete the addition to her home. At all times material hereto, Respondent held a certificate of competency issued by Metropolitan Dade County.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding Respondent guilty of violating Section 489.129(1)(d), Florida Statutes, by willfully and deliberately violating Section 301(a) of the South Florida Building Code; imposing an administrative fine against Respondent in the amount of $2,000 to be paid by a date certain; and dismissing the remaining charges contained in the Administrative Complaint, as amended, against Respondent. DONE and RECOMMENDED this 13th day of April, 1984, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of April, 1984. COPIES FURNISHED: Douglas A. Shropshire, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Joseph F. Scioli, Jr. 246 North Krome Avenue Florida City, Florida 33034 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (2) 120.57489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer