The Issue Whether the certified general contractor's license of W. Bert Jones should be revoked.
Findings Of Fact By an Administrative Complaint filed October 27, 1976, the Florida Construction Industry Licensing Board sought to revoke the general contractor's license of W. Bert Jones alleging that the Respondent contractor entered into a contract with Mrs. Barbara Loewe to renovate her home and to add a room onto the back of the house; that the Respondent contractor was paid in full the contract price but the job was not completed and there were numerous building code violations. Respondent requested an administrative hearing. Pursuant to written agreements entered into between the Respondent and Mrs. Barbara Loewe of Tampa, Florida, Respondent agreed to renovate Mrs. Loewe's home and to add a room onto the back of the house. Mrs. Loewe, either by paying the Respondent directly or paying material suppliers, paid the full contract price. In June or July of 1975 the Respondent left the job contracted for partially or wholly incompleted as follows: the ceiling of the kitchen and drywall were in complete and the kitchen was not painted; the guest bathroom was not trimmed; two back rooms were incomplete. Inasmuch as the ceiling was left undone, it was not trimmed, the drywall was incomplete, the doorways were left uninstalled, and the paneling was incomplete; the bathroom had no toilet, no sink and no trim on the tub; in the master bedroom the ceiling was left sagging, there was no insulation in ceiling or walls, the door was untrimmed, siding was left partially undone and the windows weren't trimmed; holes were left unrepaired around the pipes in the home. The sum of Five Thousand Dollars ($5,000) was paid by St. Paul Fire and Marine Insurance Company in full settlement of the claims arising under the general contractor's bond. Additional money, approximately Thirty-Five Hundred Dollars ($3,500), was spent by Mrs. Loewe in addition to the Five Thousand Dollars ($5,000.00) received from the bonding company in order to complete the jobs contracted for. Although there were minimum changes In the job as originally contracted for, work is still going on to complete the original work contracted for by the Respondent. The building inspector for the City of Tampa Building Bureau, Tom Burgoyme, inspected the job site on several occasions during the progress on the work contracted for between Mrs. Loewe and the Respondent. He found building code violations and submitted a list of corrections to the Respondent, Mr. Jones, which were not remedied. A number of problems arose during the construction work, some of which was not the fault of the Respondent. Another contractor was involved in the work on the project. Funds in excess of the purchase price were paid to the Respondent and funds in excess of Eighty-Five Hundred Dollars ($8,500) were needed or will be needed to complete the project.
Recommendation Revoke the general contractor's license of Respondent, Number C GC007323. DONE and ORDERED this 7th day of April, 1977, in Tallahassee, Florida. DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 Barry Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 W. Bert Jones 2300 Greenlawn Street Brandon, Florida 33511
Findings Of Fact At all times pertinent to the issues in this hearing, Respondent was a licensed building contractor, whose license is No. CBC014467. His certification as an individual by the Florida Construction Industry Licensing Board was initially dated August 16, 1979. In February, 1981, he requested his second license be registered qualifying Jeff Webb Homes, Inc.; and in September, 1982, the license was changed from Jeff Webb Homes, Inc., to Intervest Construction, Inc. On April 23, 1981, Anna Ray McClellan contracted with Regency Central, Inc., for the construction and purchase of a single family residence located at Lot 5, Devonwood Subdivision, Volusia County, Florida. David L. Martin is president of Regency Central, Inc., and neither he nor Regency Central, Inc., are or have ever been registered or certified by the Florida Construction Industry Licensing Board to engage in the business of contracting in the State of Florida. On June 5, 1981, Respondent applied for a residential construction permit for Lot 5, Devonwood Subdivision, listing Regency Central, Inc., as the owner of the property, and himself, with License No. CBC014467, as the contractor. Actual contracting for the construction at Lot 5, Devonwood Subdivision, was accomplished by Regency Central, Inc. Three separate addenda to the construction/purchase contract calling for modifications to the specifications of construction were signed, not by Respondent, but by David L. Martin for Regency Central, Inc. Major subcontracts on the construction including plumbing, electrical, and heating and air conditioning, were entered into between the subcontractors and Regency Central, Inc., and not Respondent. Subcontractors looked to Regency Central for payment, and not to Respondent. A claim of lien filed on ,September 9, 1981, for central air conditioning and heating work on the property in question reflects the work was done under contract with Regency Central, Inc., David L. Martin, President. During construction of the house, Ms. McClellan visited the construction site several times a week at different hours of the day. She recalls seeing Respondent in the area only twice, the first time being the day the contract for purchase was signed, and the second being the day the slab was poured. Her dealings at the site were with the supervisor, Dan Haley, who indicated to her that he worked for Regency Central, Inc. Respondent was interviewed by Philip T. Hundemann, an investigator for the Florida Department of Professional Regulation, in late March, 1982, at Respondent's home. During the course of the interview, Respondent admitted that he met David L. Martin when Martin rented office space in a building that Respondent had constructed and owned. During the course of conversations, Martin suggested to Respondent that he, Martin, had ninety-nine lots available for building and that if Respondent would pull the construction permit for the Lot 5 project, he would get a contract from Martin to build on the other ninety- nine lots. Respondent admitted that he did not supervise the contract, that he did pull the permit, and that he was in violation of the law and had prostituted his license. His defense was, at that time, that he was hungry to get a big construction contract with Martin. Though after he pulled the permits his agreement was to work on the site for the rate of ten dollars per day with the supervisor, Mr. Haley, he was there only infrequently. Respondent now modifies the admissions made previously to Mr. Hundemann. He now states he was heavily involved with the construction project on a daily basis either in his office or on the construction site, not only as a contractor, but also as sales broker. While he admits what he did was in violation of the law and was foolish, he did not intend to break the law. Respondent's involvement with Ms. McClellan's project was not as contractor as indicated in the permit he pulled. He had very little contact with that project until Martin abandoned the project and left the area.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's, Dominic D'Alexander's, license as a certified building contractor be suspended for one year, but that, upon the payment of a $500 administrative fine, the execution of the suspension be deferred for a period of three years, with provision for automatic recission. RECOMMENDED this 21st day of March, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of March, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Dominic D'Alexander Post Office Box 4580 South Daytona, Florida 32021 Mr. James Linnan Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times relevant to this proceeding, respondent Ruben S. Ares was a certified general contractor in the State of Florida holding license number CG CO 14769. Sentinel Building Company of Central Florida, Inc. was engaged in the business of building residential homes for sale. It was the practice of Sentinel Building to buy the land, engage the services of a general contractor to obtain a building permit and help in the supervision and consultation on construction and sell the hones built to others. The contractors were paid a fee of between $250 and $500 per residence for obtaining permits and providing consultation and services. The Vice-President of Sentinel Building was responsible for hiring and paying subcontractors and suppliers. Sentinel Building was not a Florida licensed general contractor, nor was it qualified by respondent or other Florida registered or certified licensee to engage in the business or contracting in Florida. Respondent Ares was not an officer, stockholder, member of the board of directors or employee of Sentinel Building Company. In 1980, respondent entered into an agreement with Sentinel Building to act as the general contractor for the con- struction of at least four residences. His responsibilities were to supervise the construction of the hones and obtain all necessary permits, including the original building permit and the final certificate of occupancy. The responsibility for engaging subcontractors and ordering and purchasing materials and supplies remained with Sentinel Building Company. Respondent was paid a fixed fee of $350 per house. During the period of time in which four residences in Seminole County were constructed, respondent held another full time job with a building company for which he worked 43 to 44 hours per week. His activity with Sentinel Building consisted of obtaining permits and periodic checks on the construction work. According to respondent, his inspections on construction activity occurred once every three to ten days and consumed approximately too to four hours of respondent's time per week. In 1980 and 1981, respondent applied for and obtained building permits for four single-family residences in Delmar Estates, Seminole County. The applications and permits listed Sentinel Building as the owner of the property and respondent Ruben S. Ares as the contractor. At least one of the four homes was under a contract of sale prior to construction. Three of the four purchasers were under the impression that the homes were built by Sentinel Building. None of the three had ever met respondent Ares, nor were they aware that he was the general contractor.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that respondent be found guilty of violating Section 489.129(1)(e) and (f), Florida Statutes, that an administrative fine in the amount of $1500 be imposed against respondent and that the remaining charges of the Administrative Complaint be dismissed. Respectfully submitted and entered this 22nd day of June, 1984, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of June, 1984. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Aldo Icardi, Esquire P.O. Box 879 990 Lewis Drive Winter Park, Florida 32790 James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202
The Issue The issue in this case is whether Respondent committed the acts alleged in the Administrative Complaint and if so, what penalty is appropriate.
Findings Of Fact Based upon the testimony of the witnesses and the evidence presented and the entire record in this proceeding, the following material and relevant facts are found. At no time material hereto was Respondent, Donald Clark, licensed by the State of Florida Construction Industry Licensing Board to engage in construction contracting. At no time material hereto was Cancun Development Company ever qualified or certified by any State of Florida agency as a certified contractor. With knowledge of that he was not licensed by the State of Florida to solicit, engage in, nor contract for construction work, Respondent entered into an oral agreement with homeowner Ms. Eichar to build a second-story addition to her home, located in Indian Rocks Beach, Florida, for a contract price of $30,000.00. Respondent, who was paid by Ms. Eichar a total of $25,000.00, subcontracted with Mr. Erwin, a licensed electrical contractor, to do the electrical work at the Eichar's residence for $2,364.00. Respondent, after notice, failed to attend the formal final hearing regarding this matter. The investigative and prosecution costs to the Department of Business and Professional Regulation, excluding cost associated with attorney time, were $550.00.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that a final order be entered by the Department as follows: Finding Respondent, Donald Clark, guilty of having violated Subsection 489.127(1)(f), Florida Statutes, as alleged in the Administrative Complaint herein filed and imposing as a penalty an administrative fine in the amount of $5,000.00. Assess costs of investigation and prosecution, excluding costs associated with an attorney's time, in the amount of $550.70. DONE AND ENTERED this 23rd day of July, 2002, in Tallahassee, Leon County, Florida. FRED L. BUCKINE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July, 2002. COPIES FURNISHED: Donald Clark 813 East Bloomingdale Avenue Suite 252 Brandon, Florida 32720 Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Hardy L. Roberts, III, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202
Findings Of Fact At all times pertinent to these proceedings, Hamilton held registered residential contractors license number RR0015037. Hamilton agreed to construct a house in Clearmont, Florida, with a completion date no later than May 1, 1977, for Robert J. and Margaret M. Phlepsen. The construction price was $75,000.00. After construction of the house it was discovered that there existed two violations of the Southern Building Code. First, the "step-down" from the kitchen to the garage was an eleven inch riser contrary to the code requirement that the height of a riser shall not exceed seven and three quarters inches. The second violation occurred through the use of 2 X 8 joists where the code would require 2 X 10 joists. The extra high riser between the kitchen and the garage was apparently caused by an oversight. Hamilton merely failed to install an intermediate step at that location. The second violation occurred because the owner and Hamilton agreed to use the smaller joists in order to save money on the contract price. In neither case is there sufficient evidence to establish that Hamilton's violations were willful or deliberate as alleged in the Administrative Complaint. On June 6, 1978, the Lake County Board of Examiners suspended Hamilton's Lake County Certificate of Competency because of violations of building code requirements in the construction of Phlepsen's house.
The Issue Whether disciplinary action should be taken against Respondent, Michael Hill's, contracting license based on the violations as charged in the Administrative Complaint in this proceeding.
Findings Of Fact Based on the evidence and testimony of the witnesses presented and the entire record in this proceeding, the following Findings of Fact are made: Respondent is a certified contractor, having been issued License No. CR C057409 by the Florida Construction Industry Licensing Board. Respondent's license as a certified residential contractor is currently active. Respondent was not certified with the Construction Industry Licensing Board as doing business as "Michael Hill Homes, Inc." On or about April 11, 2005, Kenneth and Aldith Farquharson ("Farquharson") entered into a written contractual agreement with Respondent, d/b/a Michael Hill Homes, Inc., for the construction of a single-family residence at Lot 17, Hattaras Terrace, Palm Bay, Florida. The original contract price of the contract between Respondent and Farquharson was $240,900.00. The original contract price was subsequently increased, via change orders executed by Respondent and Farquharson, by $4,500.00, for a total contract price of $245,400.00, adding the value of the change order for the fill dirt needed for the lot. On June 19, 2005, Farquharson paid a total of $28,590.00 to Respondent. The scope of work under contract required appropriate permits from the City of Palm Bay Building Department before work could commence. Respondent failed to apply for the permits necessary to commence work under the contract. Respondent delivered some sand to the lot on or before October 2005. After delivering the sand, Respondent failed to continue any more of the contracted work. From November 2005 to December 2006, Respondent performed no work on the project under contract. From October 2005 to February 2006, Farquharson made multiple attempts to contact Respondent regarding the lack of work under the contract. Farquharson did not prevent Respondent from commencing and completing the work under contract or agree to delay the project for any reason. Farquharson did not terminate the contract with Respondent. Respondent did not refund any money to Farquharson. The amount of actual damages that Respondent caused Farquharson is calculated as follows: Amount paid: $28,590.00 Amount of work performed by Respondent (dirt fill): _ 4,500.00 $24,090.00 The Petitioner's total investigative cost for the case is $439.79.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered as follows: Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count I of the Administrative Complaint, for violating Subsection 489.119(2), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count II of the Administrative Complaint, for violating Subsection 489.126(2)(a), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(g), Florida Statutes, as alleged in Count III of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(j), Florida Statutes, as alleged in Count IV of the Administrative Complaint, and imposing as a penalty an administrative fine of $5,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(o), Florida Statutes, as alleged in Count V of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Section 489.129(1)(m), Florida Statutes, as alleged in Count VI of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Respondent be ordered to pay financial restitution in the amount of $24,090.00 to Kenneth and Aldith Farquharson; Assessing cumulative cost of investigation and prosecution in the total amount of $439.79, which excludes costs associated with any attorney's fees; and Permanently revoking Respondent's license as a result of the numerous violations and the financial harm sustained by Kenneth and Aldith Farquharson. DONE AND ENTERED this 12th day of October, 2007, in Tallahassee, Leon County, Florida. S JEFF B. CLARK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of October, 2007.
The Issue The Florida Construction Industry Licensing Board, Petitioner, seeks to revoke the registered contractor's license of Stephen J. Borovina, Respondent, based on allegations, which will be set forth in detail hereafter, that he engaged in conduct violative of Chapter 468, Florida Statutes. The issue presented is whether or not the Respondent aided or abetted and/or knowingly combined or conspired with Mr. Howard North, an uncertified or unregistered contractor, to evade the provisions of Chapter 468.112(2)(b), and (c), Florida Statutes, by allowing North to use his certificate of registration without having any active participation in the operations, management, or control of North's operations. Based on the testimony adduced during the hearing and the exhibits received into evidence, I make the following:
Findings Of Fact The Respondent is a certified general contractor who holds license no. CGC007016, which is current and active. On or about July 25, 1976, Mr. and Mrs. Julius Csobor entered into a contract with Mr. and Mrs. Howard North for the construction of a home in Martin County, Florida, for a total price of $35,990. Neither Mr. or Mrs. North are certified or registered contractors in the State of Florida. (Petitioner's Composite Exhibit #2). Respondent applied for and was issued a permit by the Martin County Building Department to construct a residence for the Csobors at the same address stipulated in the contract between the Csobors and the Norths, i.e., Northwest 16th Street, Palm Lake Park, Florida. (Petitioner's Composite Exhibit #1). Howard North, a licensed masonry contractor for approximately nine (9) years was contacted by the Csobors through a sales representative from a local real estate firm. It appears from the evidence that North had previously constructed a "spec" house which the local realtor had sold and thus put the Csobors in contact with Mr. North when they were shown the "spec" house built by North. Evidence reveals that North contacted Borovina who agreed to pull the permit "if he could get some work from the job and could supervise the project". Having reached an agreement on this point, North purchased the lot to build the home for the Csobors and he orally contracted with the Respondent to, among other things, pull the permit, supervise construction, layout the home and do trim and carpentry work. North paid Respondent approximately $200 to layout the home for the Csobors. By the time that North had poured the slab and erected the subfloor, the Csobors became dissatisfied with his (North's) work and demanded that he leave the project. According to North, Respondent checked the progress of construction periodically. Prior to this hearing, the Csobors had never dealt with Respondent in any manner whatsoever. According to Csobor, North held himself out as a reputable building contractor. A contractor is defined in relevant part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. . . . real estate for others. . . Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby recommended that the complaint filed herein be dismissed in its entirety. RECOMMENDED this 4th day of November, 1977, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 Stephen J. Borovina 2347 Southeast Monroe Street Stuart, Florida 33494 J. Hoskinson, Jr. Chief Investigator Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 STEPHEN J. BOROVINA, CG C007016, 2347 S. E. Monroe Street, Stuart, Florida 33494, Respondent. / This cause came before the FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD at its regular meeting on February 10, 1978. Respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did not appear The FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD on February 10, 1978, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded voted to revoke the certified general contractor's license of STEPHEN J. BOROVINA. It is therefore, ORDERED that the certification of respondent STEPHEN J. BOROVINA, Number CG C007016, be and is hereby revoked. Respondent is hereby notified that he has 30 days after the date of this final order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. DATED this 13th day of February, 1978. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President ================================================================= SECOND AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD STEPHEN J. BOROVINA, CG C007016, Respondent/Appellant, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner/Appellee. / This cause came before the Florida Construction Industry Licensing Board at its regular meeting on August 3, 1979. The respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did appear. The Florida Construction Industry Licensing Board, on August 3, 1979, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded, voted to revoke the certified general contractor's license of Stephen J. Borovina, No. CG C007016. On February 13, 1978, the certification of respondent, Stephen J. Borovina, No. CG C007016, was revoked by order of the Florida Construction Industry Licensing Board. On April 25, 1979, the District Court of Appeal of the State of Florida, Fourth District, in Case Number: 78-527, reversed the final order of the Florida Construction Industry Licensing Board. That Court remanded the above captioned case to the Board to further consider the matter and enter such order as it may be advised in conformity with Section 120.57(1)(b)(9), Florida Statutes (1977). In accordance with the decision of the Florida District Court of Appeal, Fourth District, the Board has reconsidered the above captioned matter and finds as follows: The Board rejects the recommended order as the agency's final order. The Board adopts the first paragraph of the hearing officer's finding of fact. The Board, however, rejects the findings of fact found in the second paragraph of the hearing officer's findings. The second paragraph states as follows: A contractor is defined in relevent(sic) part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. real estate for others...Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety. The findings of fact found in the above-quoted paragraph were not based upon competent substantial evidence. The competent substantial evidence supports a finding that the respondent, Stephen J. Borovina, did not supervise the project and that Borovina evaded the provisions of Chapter 468, Florida Statutes. The following evidence supports the Board's position: There was no written agreement entered into between Howard North and the respondent which indicated that the respondent was to supervise the construction of the Csobors' house (T- 14); It was conceded at the hearing that the only subcontractors or draftmen who worked on the Csobors' house were contracted solely by Howard North and they had no contract whatsoever with the respondent (T-19, 25); The respondent never advised or informed Mr. and Mrs. Csobor that he was the contractor on the job. (T-51); At all times during the act of construction of the house, Mr. and Mrs. Csobor were under the impression that Howard North was the contractor (T-44-51). It is, therefore, ORDERED: That the certification of respondent, Stephen J. Borovina, Number CG 0007016, be and is hereby revoked. Respondent is hereby notified that he has thirty (30) days after the date of the Final Order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. Dated this 3rd day of August, 1979. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President
The Issue Whether Respondent violated section 489.129(1)(j), Florida Statutes (2005),1 by abandoning a construction project, and, if so, the appropriate discipline; and Whether Respondent violated section 489.129(1)(i) by virtue of her violation of section 489.127(1)(f), which prohibits engaging in the business or acting in the capacity of a contractor without being licensed, and, if so, the appropriate discipline.
Findings Of Fact Based on the evidence, the following facts were made: Ms. Curbelo is a certified building contractor, doing business as A+ Construction & Management, Inc. The Florida Construction Industry Licensing Board issued Ms. Curbelo License No. CBC 1255321 on March 12, 2007. She is currently licensed as the qualifying agent of A+ Construction & Management, Inc., and she was issued qualified business organization certificate of authority License No. QB53665. Before March 12, 2007, Ms. Curbelo was not licensed pursuant to chapter 489, Part I, to practice construction contracting. In December 2005, Ms. Curbelo purchased A+ Construction & Remodeling, Inc., and became its sole corporate officer. She renamed the entity A+ Construction & Management, Inc. (A+ Construction). Before March 12, 2007, A+ Construction was not duly licensed pursuant to chapter 489, Part I. Further, its predecessor, A+ Construction & Remodeling, Inc., was never duly licensed pursuant to chapter 489, Part I. On January 25, 2006, Mr. Torres was provided a proposal from Ms. Curbelo, doing business as A+ Construction & Remodeling, Inc. The proposal was to remodel, renovate, and repair Mr. Torres' home located at 1031 Hunting Lodge Drive, Miami Springs, Florida 33166. On January 27, 2006, Mr. Torres accepted the proposal, and it formed the agreement between Ms. Curbelo and Mr. Torres. Mr. Torres made an initial payment of $24,900.00 to A+ Construction on February 6, 2006, which was due under the contract upon acceptance. The agreed contract price for the work was $166,000.00. The contract contained a description of the work to be completed and a draw schedule that provided for payment as the work progressed. Mr. Torres made payments to A+ Construction for the time period of February 8, 2006, through April 10, 2007. The payments totaled $157,700.00 and corresponded with a majority of the work contracted to be completed under the contract. The only draw that Mr. Torres did not pay was in the amount of $8,300.00 that was due "upon completion" of the work. Mr. Torres credibly testified that he paid A+ Construction for work that had not been completed in order to move the job along to completion. Furthermore, Mr. Torres credibly testified that when he would question Mr. Luis Curbelo, the job-site foreman, about the status of the work, Mr. Curbelo would threaten to walk off the job. Mr. Torres identified a check, Petitioner's Exhibit 6, that he made payable to First Call Roofing dated August 23, 2007, in the amount of $5,000.00. Mr. Torres explained that he paid First Call Roofing because he was desperate to get his leaking roof repaired. Mr. Torres paid this amount even though he had previously paid A+ Construction for repairs to the roof as part of the contract. The evidence also showed that during the work, Mr. Torres requested change orders which were not part of the original contract. Although these change orders increased the costs above the original contract, it was not disputed that Mr. Torres fully paid A+ Construction for all of the work outside of the contract. Sometime in late August 2007, A+ Construction stopped work on the job and failed to return. Mr. Torres credibly testified that he had an estimate from another contractor that the construction job was left approximately 40 percent completed and that it would cost an estimated amount of $108,000.00 to complete the job. The Department, however, did not introduce any non-hearsay evidence to support the estimate to complete the work or the costs to complete the construction. After A+ Construction stopped work on the job, Mr. Torres testified that he called in a series of inspections and that his home had passed the inspections. He stated that a majority of the inspections had been called in by him. Ms. Curbelo and Mr. Luis Curbelo offered the following three explanations for why A+ Construction stopped work on Mr. Torres' house: first, Mr. Torres failed to approve a payment draw concerning installation of windows; second, Mr. Torres' construction job included work for which Mr. Torres had not paid; and finally, Mr. Torres attempted to undercut A+ Construction by directly dealing with its subcontractors. None of these offered reasons is supported by the evidence. The record clearly showed that Mr. Torres made all of the payments required under the contract, except the final draw of $8,300.00, which was due on completion of the job. Consequently, under the contract, Mr. Torres had fully paid, including amounts for windows, all amounts that were owed under the contract when A+ Construction abandoned the job. The final draw was not due until completion, and A+ Construction had not completed the job. Next, the record clearly shows that Mr. Torres paid for all change orders. Therefore, the record does not support Ms. Curbelo's claim that A+ Construction stopped work because of non-payment. Finally, the record clearly showed that Mr. Torres contracted with the roofing subcontractor to do work that A+ Construction had been paid to do, but had not done. Thus, the evidence did not support the contention that A+ Construction had stopped work because Mr. Torres attempted to undercut them by dealing with the subcontractors. The record clearly shows that Ms. Curbelo, doing business as A+ Construction, abandoned the construction job. Next, the record does not support the claim that the building inspections showed that 85 percent of the remodeling had been completed on the job and that work stopped because of Mr. Torres' non-payment. Considering that Ms. Curbelo stopped work in August 2007, a review of the building inspections shows that many of the inspections occurred after she abandoned the job. None of the inspections shows the percentage of work completed by A+ Construction. Finally, the record does not support Ms. Curbelo's testimony that Mr. Torres was aware that at the time of entering into the contract that she did not have a contractor's license and that the job was under the supervision of Joe Anon (Mr. Anon). Ms. Curbelo testified that Mr. Torres was aware the Mr. Anon would be the general contractor, as his name was on the January 25, 2006, contract. Interestingly, the document that Ms. Curbelo relies upon for her testimony is a proposal dated January 25, 2006, from A+ Construction & Management, Inc. This document is nearly identical to the 11-page proposal from the A+ Construction & Remodeling, Inc., to Mr. Torres on the same date for the repairs to the home. However, two important differences are found on the faces of the two exhibits. On Respondent's Exhibit 2, under the logo of "A+ Construction" are the terms "& Management, Inc. For Joe Anon, GC." In contrast, Petitioner's Exhibit 3 shows the logo of "A+ Construction & Remodeling" with no reference to the later company or Mr. Anon's name. Both of these exhibits purport to be from the same proposal given to Mr. Torres on the same day. Yet, out of the composite exhibit of 12 pages, only Ms. Curbelo's offered document contains Ms. Curbelo's subsequent company's name or reference to Mr. Anon. Moreover, unlike the Department's exhibit, the exhibit offered by Ms. Curbelo is unsigned by Mr. Torres. Consequently, the document offered by Ms. Curbelo is untrustworthy. Thus, the undersigned rejects as unbelievable Ms. Curbelo's claims that Mr. Torres knew that she was not a licensed general contractor and that the construction project was being overseen by a licensed contractor. Mr. Torres credibly testified in rebuttal that he did not meet Mr. Anon until after Ms. Curbelo abandoned the job. Further, Mr. Torres credibly testified that his "biggest mistake was paying ahead" to get work completed. The Department's total investigative costs of this case, excluding attorney's fees, is $414.57. The evidence showed that Ms. Curbelo does not have any prior disciplinary actions against her license.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be issued by Petitioner, Department of Business and Professional Regulation, Construction Industry Licensing Board: Finding Respondent, Chandra Beth Curbelo, guilty of having violated section 489.129(1)(j), Count I of the Administrative Complaint, imposing as a penalty a fine of $7,500.00, and placing Ms. Curbelo's license on probation for a period of four years; Finding Ms. Curbelo guilty of having violated sections 489.127(1)(f) and 489.129(1)(i), as set out in Count II of the Administrative Complaint, imposing a fine of $7,500.00, and placing her license on probation for a period of four years; and Requiring Ms. Curbelo to pay the Department's costs of investigation and prosecution in the amount of $414.57. DONE AND ENTERED this 5th day of January, 2011, in Tallahassee, Leon County, Florida. S THOMAS P. CRAPPS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 2011.
Findings Of Fact At all times material to these proceedings, the Respondent, David R. Knight, held a registered general contractor's license numbered RG 007907 issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board initially in July, 1968. Respondent's license is presently in an inactive status for failure to renew but renewal can be accomplished by Respondent paying the required renewal fee only. On May 13, 1983, Respondent contracted with Joseph Cobb to remodel a house in Milton, Florida. The contract price was $23,800.00. The Respondent began the remodeling and when the project was approximately 50 percent completed, left the site. Joseph Cobb, on numerous occasions, offered to work with the Respondent in any way to finish the project, but the Respondent failed to return. Joseph Cobb paid Respondent $19,100.00 from May 14, 1983 through June 23, 1983. In addition, although the contract required Respondent to pay for all supplies and materials, Cobb paid $2,300.98 for supplies and material used in the remodeling. Respondent failed to pay Gary Rich Plumbing for the plumbing work done on the Cobb residence. Joseph Cobb was forced to pay Gary Rich $1,200.00 in order to avoid a lien being filed on his home. Respondent was not licensed to contract in Milton, Santa Rosa County, Florida, when he contracted with Joseph Cobb to perform remodeling. In June, 1982, Respondent contracted with Pearlie Rutledge to remodel a house at 608 North D Street, Pensacola, Florida, Escambia County. The contract price was $17,000.00. The Respondent began the construction without obtaining a building permit which is in violation of Section 106 Standard Building Code as adopted by the City of Pensacola Ordinance 81-83. Respondent deliberately and in a hurry left the site of construction when the building inspector appeared on the job. The Respondent was not licensed in Escambia County or the City of Pensacola to practice contracting. Pearlie Rutledge paid Respondent $5,000.00 which the Respondent failed to return when the remodeling was stopped by Charles Humphreys, Housing Inspector for the City of Pensacola. Pearlie Rutledge obtained a Final Judgement against the Respondent for $4,557.00 which has not been paid by the Respondent. Respondent's "81-82' and "82-83", Okaloosa County Occupational License was issued to David Knight doing business as "Your Way Construction." However, there was no evidence presented at the hearing that Respondent ever contracted in the name of "Your Way Construction." In fact there is evidence that during the year 1983 he contracted with Cobb as David Knight, General Contractor and not as David Knight, General Contractor, d/b/a Your Way Construction. (See Petitioner's Exhibit No. 1.)
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the Board enter a final order Dismissing Counts II, V and VI of the Administrative Complaint filed against the Respondent. It is further RECOMMENDED that the Board enter a final order finding Respondents guilty of the violation charged in Counts I, III and IV of the Administrative Complaint filed against the Respondent and for such violation it is RECOMMENDED that the Board revoke the Respondent's registered general contractor's license numbered RG 0007907, to practice contracting in the State of Florida Respectfully submitted and entered this 9th day of January, 1986, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 9th day of January, 1986. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 84-3836 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the Petitioner to this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Adopted in Finding of Fact 1. Exhibit 1). 3. Adopted in Finding of Fact 3. 4. Adopted in Finding of Fact 4. 5. Adopted in Finding of Fact 5. 6. Adopted in Finding of Fact 6. 7. Adopted in Finding of Fact 7. 8. Adopted in Finding of Fact 8. 9. Adopted in Finding of Fact 9. 10. Adopted in Finding of Fact 10. 11. Adopted in Finding of Fact 11. 12. Adopted in Finding of Fact 12. Adopted in Finding of Fact 2 except for contract amount which should have been $23,800. (See Petitioner's Respondent Did Not Submit Any Proposed Findings of Fact COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32202 Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee Florida 32301 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. David R. Knight 1215 East Hayes Street Pensacola, Florida 32503
The Issue The issue in this case is whether Respondent violated Section 489.129(1), Florida Statutes (1997) (hereinafter, "Florida Statutes"), by committing mismanagement or misconduct in the practice of contracting, causing financial harm to a customer, abandoning a construction project, and failing to satisfy a judgment against him.
Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a contractor pursuant to license number CB C019811. At all relevant times, Respondent was the qualifying agent for Gulf and Bay Sunrooms, Inc. ("Gulf"). As the qualifying agent, Respondent was responsible for all of Gulf's contracting activities in accordance with Section 489.1195, Florida Statutes. On August 23, 1995, Respondent and Gulf entered into a contract with Mr. H. Edward Dowling ("Dowling") to install a Four Seasons System 330 Sunroom in Dowling's residence at 3016 West 38th Street, Orlando, Florida. The contract price was $31,340. Dowling paid the first draw of $9,402 to Respondent and Gulf by check number 45016644. On October 27, 1995, Gulf deposited the check to its account. Respondent and Gulf never commenced work on the sunroom. Respondent and Gulf did not return the first draw to Dowling. Respondent and Gulf abandoned the project without just cause and without notice to Dowling. On June 19, 1997, the County Court of the Ninth Judicial Circuit entered a Default Final Judgment in Case No. CO97-3800. The default judgment was entered in the amount of $9,402 plus costs of $145. Neither Respondent nor Gulf have satisfied the judgment. Respondent has a discipline history in two other cases. In Petitioner's Case No. 96-7123, Respondent failed to pay a supplier for windows. In DOAH Case No. 96-5914, Respondent contracted to build a sunroom in a residence, accepted payment of $1,540.44 toward the contract price of $4,668.00, never commenced construction, and abandoned the project. In the first case, Respondent was found guilty of failing to satisfy a civil judgment, was fined, and was ordered to pay restitution. In the second case, Respondent was found guilty of abandonment, incompetency or misconduct, was fined, and was ordered to pay restitution, and his license was suspended until Respondent complied with the penalty imposed.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating Section 489.129(1), Florida Statutes, imposing administrative fines in the aggregate amount of $15,000.00, and revoking Respondent's license. DONE AND ENTERED this 10th day of August, 1998, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 1998. COPIES FURNISHED: Rodney Hurst, Executive Director Department of Business and Professional Regulation Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Paul F. Kirsch, Senior Attorney Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 William Leete Stone, IV, pro se 3386 Poinsettia Avenue Naples, Florida 34104