Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STUART L. REISE, 87-003955 (1987)
Division of Administrative Hearings, Florida Number: 87-003955 Latest Update: Sep. 19, 1988

The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.

Florida Laws (4) 120.57489.105489.119489.129
# 1
JOHN MORRIS vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 80-001562 (1980)
Division of Administrative Hearings, Florida Number: 80-001562 Latest Update: Nov. 11, 1980

Findings Of Fact In 1975 and 1976 John Morris, d/b/a Morris Pool Service, maintained the swimming pool at the Sunland Center in Miami, Florida under a contract with HRS. The contract for the year commencing July 1, 1976 and expiring June 30, 1977 (Exhibit 1) provided generally for Morris to maintain the Sunland Center pool for which he would be paid $520 per month. This contract further provided that a representative of Morris Pool Service check each day except Saturday and Sunday with Ms. O'Donohue, the Director of Training, or her successor. Recreation personnel at Sunland Center hoped to open the pool on Memorial Day; however, an impeller for the pump needed replacement and the pool was inoperative for some six weeks in May and June awaiting this part. During this time petitioner did little or no maintenance and the pool's condition was bad enough for the Superintendent to become involved and request a report from the Programs and Services Director (Exhibit 4). When the impeller did arrive in mid-June, 1977, the pool was in such bad shape it was necessary to drain the pool, scrub, and acid-wash the walls and floor of the pool to remove the accumulated algae and scum. Even a colony of frogs had taken up residence in the pool during this period. As a result of additional delays the next hoped-for opening date of July 4 was also missed. The pool was finally ready for operation and was opened the week following July 4, 1977. Although opened the water in the pool was not properly maintained by cleaning and chlorinating. In the latter part of July the gas chlorinator became inoperative and the pool's condition deteriorated as no chlorine was being added to the water. Under the contract Petitioner was to provide materials necessary to keep the pool water in a balanced condition. This contract expired on June 30, 1977. Nevertheless, Petitioner purported to continue working under the expired contract, pending the issuance of a new contract for 1977-1978. While the gas chlorinator was inoperative Petitioner did not hand-feed chlorine to the pool to maintain the proper chlorine level and to keep algae from growing. By early August, 1977, the pool had become so bad the supervisory personnel at Sunland Center called the Dade County Health Department to inspect the pool. A report of that inspection showing the pool unfit for use was admitted into evidence as Exhibit 3. Following the Superintendent's inquiry to Ms. Titus about the condition of the pool in June, 1977, she contacted Petitioner, who told her the pool would he hack in operation as soon as the impeller was received. Ms. Titus was the successor to Ms. O'Donohue and she told Petitioner to keep her advised regarding the status of the pool. Although the contract (Exhibit 1) required Petitioner to report to Ms. Titus daily (except Saturday and Sunday) she did not see him again, nor did she receive any report that he came to her office. Petitioner contends that he attempted to report to Ms. Titus but was unable to find her in her office and after a few attempts stopped trying. Ms. Titus and her assistant were both equipped with beepers and could be contacted any time of day by their office if they were out of the office. Following the Health Department's inspection on August 9, 1977, the pool was closed for several days, then reopened around mid-August after the chlorinator was repaired. When the pool was reopened in August its condition was barely satisfactory. Shortly after Labor Day the pool was again closed and remained closed throughout the balance of 1977. By October, the Sunland Center officials decided they should notify Petitioner that his contract would not be renewed for the 1977-1978 year and a letter dated October 27, 1977 (Exhibit 2) was forwarded to him by registered mail. This letter was mailed to an old address for Petitioner, was returned to the sender and remailed to the proper address. As a result, the letter was not received by Petitioner until December 14 or 15, 1977. Petitioner submitted bills to Respondent for services for the period July 1, 1977 through December 15, 1977, the approximate date he received Exhibit 2. Following August 10, 1977 some of Respondent's employees in the maintenance department saw Petitioner in the cafeteria at Sunland Center and on the premises, but none of them reported seeing Petitioner do any work on the pool. Petitioner contends he worked on the pool on a daily basis, however, the condition of the pool casts serious doubts on this testimony.

# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD G. BATTER, D/B/A TROPICANA POOLS, INC., 79-001938 (1979)
Division of Administrative Hearings, Florida Number: 79-001938 Latest Update: Apr. 30, 1980

The Issue The issues posed for decision herein are whether or not the certified pool contractor's license issued to Respondents Licensee, Edward G. Batter, should be revoked or suspended or the Licensee's right to practice thereunder should be withdrawn based on conduct which will be set forth hereinafter in detail as set out in the Administrative Complaint filed herein on August 23, 1979.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Edward G. Batter, d/b/a Tropicana Pools, Inc., (Respondent or Licensee) is a certified pool contractor who holds license No. CPC 012906. Respondent was first licensed on July 28, 1978, as qualifier of Tropicana Pools, Inc., which license was temporarily suspended in June, 1979, and remains in an invalid status to this date. By its Administrative Complaint, Petitioner's Executive Director took action to revoke or otherwise suspend the Respondent's rights to practice pursuant to his referenced license. As a licensed pool contractor, Respondent is subject to the Board's rules and regulations. (See Petitioner's Composite Exhibit 1.) A special meeting of the Board of Adjustment, Appeals and Examiners for general building contractors for Hillsborough County was held on Thursday, July 19, 1979, for the purpose of hearing certain allegations concerning the demise of Tropicana pools, Inc. Jerry Taylor, Petitioner's field investigator, presented the Hillsborough County Board with the results of an investigation of Respondent and presented several cases wherein funds were diverted after being collected for a specific contract to other projects or for other purposes and that projects for which funds had been collected had either been left unstarted or abandoned at the time Tropicana Pools, Inc., ceased doing business. At that meeting, the Respondent's construction activities were suspended by the Board until restitution or settlement was made and verified by affected parties. The temporary suspension by Hillsborough County became final during August of 1979. (Petitioner's Exhibits 2 and 3.) Howard Shaw, Director of Building and Zoning for the City of Tampa, appeared and testified to substantiate the disciplinary action taken against the Respondent by Hillsborough County during the summer of 1979. On June 7, 1979, Mr. and Mrs. James R. Stanton entered into a contract with Respondent to have a pool constructed for a price of $8,182.00. Respondent was paid a 10 percent deposit to commence construction of the Stantons' pool. Respondent absconded with the deposit and never notified the Stantons that their pool would not be built nor did Respondent return their deposit. (See Petitioner's Exhibits 4 and 5.) On April 19, 1979, Mr. and Mrs. Theodore Hillary entered into a contract for the construction of a swimming pool for a contract price of $8,130.00. Approximately $5,690.00 or approximately 70 percent of the contract sum was paid on June 18, 1979, and the work ceased on the Hillary project at a completion stage of approximately 40 percent. Respondent abandoned the Hillary project on approximately June 5, 1979. The Hillarys completed their pool at a price of approximately $5,000.00 over and above the contracted price. (Petitioner's Composite Exhibit 6.) On April 30, 1979, Mr. and Mrs. Leon Tope entered into a contract for the construction of a swimming pool at their residence for the contract price of $8,050.00. On June 18, 1979, the Topes had tendered to Respondent approximately 70 percent of the contract cost while the Respondent abandoned the construction of the Topes' pool after approximately 40 percent of the work was complete. Respondent abandoned the project on June 18, 1979, and the Topes completed the construction of their pool at a price of approximately $2,000.00 by engaging the services of other contractors in the area. (See Petitioner's Exhibits 7, 8, 9, 10, and the testimony of Jim Moran.) Jerry Taylor, Petitioner's field investigator, attended the probable cause hearing during August of 1979 in which the Hillsborough County Board of Examiners suspended the pool license of Respondent. Investigator Taylor briefed the Hillsborough County Board respecting the results of the investigation conducted by Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Respondent's pool contractor's license No. CPC 012906 be REVOKED. ENTERED this 10th day of March, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings 101 Collins Building Tallahassee, Florida 32301 (904) 488-9675

Florida Laws (1) 120.57
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HENRY C. HOLLENBECK, 81-002086 (1981)
Division of Administrative Hearings, Florida Number: 81-002086 Latest Update: Dec. 04, 1990

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times pertinent to this proceeding, respondent Henry C. Hollenbeck was licensed as a swimming pool contractor. In February of 1980, respondent, doing business as Acme Pools, entered into a contract with Loren Bjornson to construct a swimming pool at Bjornson's residence for a total purchase price of $8,300. Construction of this pool was completed on or about June 30, 1980. Respondent did not obtain a building permit for the Bjornson pool until January 5, 1981. Prior to the construction of a swimming pool in Ft. Walton Beach, a building permit is required. No inspections were performed by the City during construction of the Bjornson pool. Many items, such as the plumbing, walls, drain system, etc., cannot be adequately inspected after construction is completed and the pool is filled with water. Almost immediately upon construction of the Bjornson pool, a crack in the wall at the center of the pool appeared. This was repaired by respondent. Then, in July of 1980, the pool started losing one inch of water per day. In August, 1980, the pool started losing two inches of water per day. Mr. Bjornson repeatedly contacted respondent about this problem, but respondent did not respond to the calls because he felt that Mr. Bjornson had not paid his bills. Apparently, the financial dispute concerned work on a neighbor's driveway for which Mr. Bjornson was never billed. On three different occasions, Mr. Bjornson had not paid his bills. Apparently, the financial dispute concerned work on a neighbor's driveway for which Mr. Bjornson was never billed. On three different occasions, Mr. Bjornson retained another pool company to make repairs on his pool to prevent it from leaking. The three repair bills amounted to slightly over $200 and none of the repair jobs could be guaranteed. In order to make a guarantee, the service and sales manager of Aqua Pools estimated that repairs amounting to $11,365 would be necessary. It was his opinion that the repair work would involve a major rebuilding of the pool, including the removal of the pool deck and tiles and the reinforcement of walls. At the time of the hearing, the Bjornson pool was not presently leaking. By contract dated August 10,1979, respondent agreed to install a swimming pool for Mr. and Mrs. Walter Parker. Construction was competed in October of 1979 and leaking problems began almost immediately. Respondent came back on at least four occasions to do the repair work. The corners were patched and other repair work necessitating the complete draining of the pool was performed. Each time, the Parkers were charged for labor and parts. At the time of the hearing, the Parker pool still leaked approximately one inch per day. It was estimated that it would cost about $1,000 to repair the Parker pool adequately so that a one-year warranty against leaking could be given. Respondent testified that he did not respond to Mr. Bjornson's calls for repair work because Mr. Bjornson still owed him money. He believed the Parkers also owed him money. He felt that he could repair both pools adequately for a nominal sum of money.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that petitioner find respondent guilty of violating Sections 489.129(1)(d) and 489.129(1)(m), Florida Statutes, and suspend his pool contractor's license for a period of one (1) year. DONE AND ENTERED this 16th day of December 1981 in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of December 1981. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 Henry C. Hollenbeck Rt. 1, Box 196 F-G, Circle Drive Ft. Walton Beach, Florida 32548 Mr. Samuel Shorestein, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (1) 489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KENNETH R. MARTIN, 87-005044 (1987)
Division of Administrative Hearings, Florida Number: 87-005044 Latest Update: Aug. 02, 1988

The Issue The administrative complaint filed on September 17, 1987 alleges that in a residential pool contracting job Respondent Martin ". . . exhibited financial mismanagement, misconduct, or diversion, in violation of 489.129(1)(h), (m) . . . [and] failed to perform in a reasonably timely manner, and/or abandoned said job, in violation of 489.129(1)(m), (k)." The issue is whether Martin committed those violations, and if so, what disciplinary action is appropriate.

Findings Of Fact At all times relevant, Kenneth Martin was licensed in the State of Florida as a registered commercial pool contractor, holding license number RP 0021608. His license is currently in inactive status. Martin was President of Adair Pools, Inc., the corporation under which he conducted his pool construction business. In early July 1986, Adair Pools contracted to build a residential pool for Paul and Cynthia Pajak at 8304 Helena Drive in Orange County, Florida. The pool was to be kidney-shaped, approximately 14 feet by 30 feet, with a waterfall and a detached spa. The contract amount of $11,571.00 expressly excluded the deck, electrical work and screening, although the written contract included a sheet describing the specifications for the excluded work, recommended contractors, and estimated costs. This sheet and the pool contract itself clearly indicated that these items were not the responsibility of the pool company and were not included in the contract price. Work commenced in July, shortly after the contract was signed. Although the contract did not specify a completion date, Martin concedes that the pool should have taken no more than four to eight weeks to complete. The Pajaks had planned a Labor Day party and were told by Adair's employees there would be no problem getting their pool finished for the party. The pool was not finished by Labor Day. After the pool was dug, shot with concrete and tiled, someone determined that the spa was supposed to have been raised. In attempting to raise the spa and to change the water jets, the workers cracked the shell of the spa and had to replace it. Until the problems with the spa, the Pajaks felt that the construction progress was reasonable and smooth. At this point, sometime around Labor Day, the problems began. Adair delayed in paying Shotcrete Pools, the subcontractor for the concrete shell, because Adair felt it was Shotcrete's fault that the spa was cracked. Shotcrete notified the Pajaks that a lien would be placed on the property if they were not paid. The notice to owner is dated November 3, 1986. Eventually Adair paid Shotcrete and its other subcontractors for the Pajak work and no lien was filed. The evidence does not reflect a clear sequence of events, but between Labor Day and February or March 1987, little progress was made to finish the pool. Martin's supervisor left and Martin's brother took over. The Pajaks kept calling Martin and were always assured that the job would be completed. Martin admits that the company at this time was in serious financial trouble because it was not being paid for a large commercial job that it had undertaken. On December 10, 1986, Mrs. Pajak's brother-in-law, an attorney, sent Martin a demand letter, giving a 10-day deadline for completion of the work. Martin and his brother met with the attorney and assured him the job would be finished. In spite of the problems, the Pajaks continued working with Martin and paid the full contract price, less the $100.00 that was to be paid when the pool was filled. On March 5, 1987, Martin informed the Pajaks that they should have the deck poured so that Adair could finish the pool. The Pajaks were not satisfied that the pool was ready for the deck as there were leaks in the waterfall, debris was all over the yard and the spa tile work looked messy. In Martin's opinion those items were his company's responsibility, but were part of the finishing to be done after the deck was poured and the pool was lined with marblelite. On March 21, 1987, the Pajaks contracted with another pool company for $4450.00 to finish their pool. Martin denies that Adair abandoned the job, but admits that it took an inordinate amount of time. The Pajaks did not allow him to finish the cleanup, the interior coating and the pool start up because they contracted with someone else. Martin did not contest that the waterfall leaked or that extensive cleanup needed to be done, but disputed that this work should be done before the deck was poured. He contended that the leaks in the waterfall would have been fixed when the finish was done. Martin estimates that between 1974 and 1986, his company completed over fourteen hundred residential pools and approximately five hundred large commercial pools. Martin has been active on various local pool construction industry boards and has no record of prior disciplinary action against his license.

Recommendation Based upon the foregoing, it is, hereby, RECOMMENDED: That Kenneth Martin be found guilty of misconduct, in violation of Section 489.129(1)(m), Florida Statutes, not guilty of the other violations with which he is charged, and that he be required to pay an administrative fine of $500.00. DONE and RECOMMENDED this 2nd day of August, 1988, in Tallahassee, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 1988. COPIES FURNISHED: David E. Bryant, Esquire 220 East Madison Street, Suite 530 Tampa, Florida 33602 Kenneth R. Martin 3225 North Glenn Drive Orlando, Florida 32806 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (3) 120.57455.225489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs MICHAEL MEINTS, 90-001629 (1990)
Division of Administrative Hearings, Florida Filed:Panama City, Florida Mar. 15, 1990 Number: 90-001629 Latest Update: Aug. 02, 1990

The Issue The issue at the hearing was whether Respondent's pool contracting license should be disciplined for alleged violations of Chapter 489, Florida Statutes.

Findings Of Fact Respondent is a licensed pool contractor in Panama City, Bay County, Florida, holding license number RP 0053231. Respondent was registered as an individual with the Board. The address given on his pool contractor's license was 3414 Jenks Avenue, Panama City, Florida. National Pools of Panama City, Inc. was not registered or certified as a contractor with the Board. National Pool's address was 3416 Jenks Avenue, Panama City, Florida. No clear and convincing evidence was presented as to whether Respondent had any knowledge of National Pool's unregenerate and incertitude status. On February 16, 1988, Robert D. Hay entered into a contract with National Pools of Panama City, Inc., for the construction of a pool on his property located at 1000 Kimberly Lane, Lynn Haven, Florida. The price of the pool was $9,310.92. The contract established a schedule of payments for the construction of the pool. Each payment was made upon completion of a certain portion of the construction work. The contract also provided that National Pools would pay for all work and materials used in the construction of the pool. A building permit was obtained for the construction of the pool. No evidence was submitted on who actually pulled the construction permit. The contractor listed on the building permit was Respondent and the construction was supervised by Respondent. The pool was completed to Mr. Hay's satisfaction and he paid the last installment payment to National Pools. 1/ Mr. Hay received a release of lien from Vance White. Mr. White was the president of National Pools. However, Mr. Hay later learned That National Pools had not paid for some materials which had been used in the pool's construction. The supplied of the materials filed a lien In the amount of $1,718.49 on Mr. Hay's property. Mr. Hay attempted to get National Pools to pay the lien. However, the lien was never satisfied by National Pools. Eventually, Mr. Hay was forced to pay the lien plus attorney's fees and court costs or else have the lien foreclosed on his property. The amount Mr. Hay was forced to pay in order to clear the title to his property was $2,615.41. There was no substantial evidence submitted which demonstrated Respondent's relationship to National Pools. The fact that Respondent's name appeared on the building permit does not support a finding that Respondent is the primary contracting agent for National Pools. Likewise, the fact that Respondent's address on his license was next door to National Pools does not support a finding that Respondent is the primary contracting agent for National Pools. It is just as likely an inference that Respondent was not the qualifying agent for National Pools, but was its subcontractor and it is National Pools and its officers who are violating the provisions of Chapter 489, Florida Statutes.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order dismissing the Administrative Complaint against Respondent. DONE and ENTERED this 2nd day of August, 1990 in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 1990.

Florida Laws (5) 120.57489.105489.119489.1195489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILLIP WHITAKER, JR., 87-005053 (1987)
Division of Administrative Hearings, Florida Number: 87-005053 Latest Update: Feb. 29, 1988

Findings Of Fact The Petitioner is the Department of Professional Regulation. The Respondent is Phillip Whitaker, Jr., holder of certified pool contractor license number CP-C008325 at all times pertinent to these proceedings. He is the qualifying agent for the business known as Sunshine State Pools pursuant to requirements of Chapter 489, Florida Statutes. He is responsible for actions of that business relating to construction of the swimming pool which is the subject of this proceeding. His address of record is Miami, Florida. The customer, Ken Gibson, signed a contract with Sunshine State Pools on September 15, 1986. The contract called for construction of a residential swimming pool at 15840 S.W. 155th Avenue, Miami, Florida. The total contract price was $12,700. Testimony adduced at hearing establishes that Sunshine State Pools completed the layout of the customer's swimming pool and the excavation of soil from the proposed pool site by October 1, 1986. These tasks were accomplished under the Respondent's supervision. Metropolitan Dade County issued a building permit for construction of the swimming pool in response to a permit application bearing the signature of Phillip E. Whitaker. The permit and application are both dated October 10, 1986. At hearing, the Respondent acknowledged that initiation of construction prior to pulling the permit and termed this action an "oversight." Based on the candor, demeanor and experience of the Respondent, his explanation of the failure to timely obtain the construction permit is not credited. Initiation of construction for a swimming pool prior to obtaining permits constitutes a violation of part 301.1(n), of the South Florida Building Code and, by stipulation of the parties at hearing, the building code of Metropolitan Dade County. The Respondent was responsible for supervision of the actual pool shell construction. After completion and removal of the wood forms used in the process, steel rods or "rebar pins" required as support during the construction process were not removed. These rods extended some distance above the ground and posed a substantial hazard to Respondent's children while playing. Finally, the steel rods were removed by the customer a week after he requested the Respondent to remove them. Respondent admitted some of these reinforcements could have been left by his subordinates. Respondent admits responsibility for the "back fill" process completed on October 25, 1986. This was originally a responsibility of the customer under the contract as the party responsible for deck construction. The "back fill" process consists of compacting loose soil between the outside of the pool walls and surrounding earth by use of special tamping or pounding equipment. Under terms of the contract, the customer was responsible for construction of a sizeable two part deck surrounding at least sixty percent of the pool's circumference. There now exists a substantial height difference between the coping surrounding the perimeter of the pool and the deck or patio surface. The coping is elevated above the top of the patio approximately two to four inches. As adduced from testimony of Ben Sirkus (stipulated by both parties as an expert in swimming pools and swimming pool construction), coping along the top of the pool walls consists of flagstone rock in conformity with the contract terms. Some of the rocks are cracked. The rocky edge of the coping extends over the pool wall and has a dangerously sharp edge. The sharp edge of the coping overhang could have been avoided by cutting the flagstone coping smooth prior to installation, the acceptable practice among pool contractors. The bottom step to one set of the pool steps has a hazardous 19 inch riser as opposed to the 12 inch distance required by the building code. No hand rail is present. Hollow space under some of the coping stones are the result of either improper installation, dirty cement or sinking of the deck as a result of improper "back filling" upon completion of the pool shell. On one occasion, Respondent admitted responsibility for deficiencies in the pool coping to an employee named Rick Miro. The Respondent further stated to this employee that he intended to do nothing about the problem. Respondent was present during some, but not all, of the coping installation. The "skimmer," the apparatus by which debris is cleared from the pool water, is inoperable as a result of faulty construction of the pool. The failure of the Respondent, who admits to successful completion of approximately 2500 pools with only three complaints, to properly supervise job site activities was the major cause of the pool deficiencies identified at hearing.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be placed on probation for a period of two years upon such terms and conditions as may be determined by the Construction Industry Licensing Board and assessed an administrative penalty in the amount of $1500. DONE AND RECOMMENDED this 29th day of February, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5053 The following constitutes my specific ruling on proposed findings of fact submitted by the parties. Petitioner's Proposed Findings Included in finding 2. Included in finding 3. Included in finding 4. Included in findings 5, 6 and 7. Included in findings 5 and 6. Included in finding 8. Included in finding 10 with exception of hearsay statement. Included in finding 11.1 Included in finding 12. Included in finding 11. Included in finding 11. Included in finding 11. Included in finding 11. Rejected as unnecessary. Rejected as unnecessary. Included in finding 11. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark D. Press, Esquire 2250 Southwest Third Avenue 5th Floor Miami, Florida 33129 William O'Neil General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 =================================================================

Florida Laws (3) 120.57489.105489.129
# 7
DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES vs. THE FAIRWAYS, TOWNHOUSES AND VILLAS, 79-001925 (1979)
Division of Administrative Hearings, Florida Number: 79-001925 Latest Update: Mar. 05, 1980

The Issue The legal issues raised and the status of the parties in this cause are seemingly complex due to the manner in which the case was presented on the initial pleadings to the Division of Administrative Hearings. At bearing, it was determined that Fairways was seeking approval of a permit for use of its swimming pool. This application had been denied by the Department of Health and Rehabilitative Services on the grounds that the pool failed to meet the requirements of Rule 100-5.50, Florida Administrative Code. In order to place the parties in their proper positions, the Respondent, Fairways, was determined to be the movant party and its cross-petition considered to be the petition. The ultimate issue presented is whether the subject pool meets the requirements of Rule 100-5.50 and its use should be approved. PRELIMINARY RULINGS Fairways collaterally attacks the manner of application of the rule by the Department to its pool, asserting that the manner of application of the rule constitutes an unpromulgated rule. Fairways also alleges in its proposed findings that Rule 100-5.50 is an invalid exercise of validly delegated legislative authority, and that the Department is estopped to assert the pool fails to comply with Rule 100-5.50 because of a failure to communicate properly the conditional approval of construction of the pool. The allegations that the Department's application of Rule 100-5.50 constitutes an unpromulgated rule and that Rule 100-5.50 is invalid are raised for the first time in Fairways' proposed findings. The original petition (cross-petition) makes no allegation that Rule 100-5.50 is invalid, and makes no allegation that the manner of measurement is an invalidly promulgated rule. These allegations would not be properly raised within the context of a Section 120.57(1), Florida Statutes, proceeding. Although invalidity of the rules on constitutional grounds is preserved in the record for appellate review, the nature of the allegations in this instance are not grounded in a constitutional challenge. Having failed to raise these issues in their pleadings under the appropriate provision of Chapter 120, Florida Statutes, these attacks will not be considered in determining the issue presented in this proceeding.

Findings Of Fact Respondent is a six-building complex containing 13 condominium units, each building being situated on a separate lot circumscribed by property lines outlining the property within the exclusive possession and control of the occupants of the condominiums. The pool in question is located upon jointly held property and is not intended to be and has not been open for use by the public or persons other than the occupants of the condominiums and their guests. On April 2, 1979, Fairways submitted a site plan (Joint Exhibit number 4) to Petitioner at the Manatee County Health Department. The site plan showed the proposed location of the pool in relation to the condominium buildings. Approval of these plans by the Department was necessary in order for a construction permit to be issued for the pool. By a letter dated May 30, 1979 (Joint Exhibit number 2), Mr. O. P. Randle, Jr., Engineer for the Department, granted approval for the pool plans with the condition that "Wet facilities shall be provided within two hundred (200) feet of the pool." Between April 4 and May 30, 1979, Ms. Rosemary Wiley, Engineering Technician with the Department, orally informed Fairways' "project engineer" that several units were more than 200 feet from the proposed pool and that wet facilities would be required. During this period, Wiley also informed Fairways' pool contractor of the same condition and requirements. A construction permit for the pool was secured by Fairways' pool contractor on June 4, 1979. Construction of the pool began during the first week of June, 1979, and was substantially finished by July 5, 1979. Shortly after June 17, 1979, Fairways contacted the Department's local pollution control director, who visited Fairways and measured the distance between the water's edge of the pool and the farthest building. The method of measurement employed by the Health Department was to measure the shortest distance between the edge of the pool and the structure of the building. The method of measurement used by the Department has been in use 16 years and evolved because measurement from the pool to the actual sanitary facility located within a building is impractical. The only building which was not within 200 feet of the water's edge of the pool was Building 6, containing two dwelling units, which was 241 feet from the edge of the pool. Part of Building 5 is more than 200 feet from the edge of the pool; however, its closest edge is within 200 feet of the pool, meeting the requirement for wet facilities. The only toilets and lavatories constructed at this site are those contained in the individual condominium units. These facilities are not open to use by the public or other condominium owners. By letter dated June 23, 1979, the local pollution director, at the request of the Health Officer, requested from the Chief of Public Health Engineering Services an interpretation of the method of measuring the 200 feet provided in Rule 100-5.50. The request of the Health Officer was precipitated by a request for section interpretation by Fairways' agent. The request dealt specifically with what was required to be within the 200-foot radius of the pool. The interpretation of the Chief of Public Health Engineering Services was contained in his letter dated July 5, 1979, addressed to the District VI pollution control director. This interpretation advised that the building's edge must touch or fall within a 200-foot radius of the pool. This letter also advised that the Department had no power to consider or grant variances or exceptions to the rules. The information contained in this interpretation was communicated to Fairways' agent. Other proposed findings of fact presented by the Petitioner and Respondent are specifically rejected.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommends that the Department deny the application of the applicant for a permit of use. DONE and ORDERED this 6th day of February, 1980, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Amelia Park, Esquire Department of HRS W. T. Edwards Facility 4000 West Buffalo Avenue, 4th Floor Tampa, Florida 33614 Janice Sorter, Esquire Department of HRS W. T. Edwards Facility 4000 West Buffalo Avenue, 4th Floor Tampa, Florida 33614 David Paul Montgomery, Esquire 2103 Manatee Avenue, West Bradenton, Florida 33505

Florida Laws (1) 120.57
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CHARLES H. BROMLEY, 81-001753 (1981)
Division of Administrative Hearings, Florida Number: 81-001753 Latest Update: Dec. 04, 1990

The Issue Whether or not the Respondent's activity and conduct in the performance and completion of several construction projects constitute unreasonable or dilatory practices and also whether Respondent's workmanship on such projects was of such an inferior quality that it would indicate proof and continued evidence of gross negligence or misconduct by Respondent in the practice of contracting within the meaning of Chapter 489.129(1)(m), Florida Statutes (1979). 2/ Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel, the memoranda submitted, and the entire record compiled herein, I hereby make the following:

Findings Of Fact By its Administrative Complaint signed April 27, 1981, Petitioner, Florida Construction Industry Licensing Board, seeks to revoke Respondent's license to practice the profession of contracting and to impose a civil penalty based on conduct set forth hereinafter. Respondent, Charles H. Bromley, is a certified pool contractor holding License No. CP-007871 (Petitioner's Composite Exhibit No. 1). During times material to the allegations of the Administrative Complaint herein, Respondent was a qualifying agent, pursuant to Section 489.119, Florida Statutes, for both Wands Construction Company, Inc., and for Magic Wands Pools, Inc. Respondent's testimony established that he was part owner of Wands Construction Company, Inc., was an officer of that company and deemed himself responsible for its activities. Respondent testified that he owned no stock in the predecessor company, Magic Wands Pools, Inc., nor was he an officer of that corporation and was not directly responsible for contracts undertaken by that company. Respondent's position is that at least two of these construction projects (Derfler and Dubovick) were projects undertaken by Magic Wands Pools, Inc., and completed by Respondent, doing business as, Wands Construction Company, Inc., inasmuch as Magic Wands Pools closed its doors in late 1979. Wands Construction Company, Inc., entered into a contract with Mariner Village, Inc., to construct a pool at a condominium site being developed by that corporation. The contract was dated September 6, 1979, and called for completion of the pool within six weeks from the date of issuance of a permit. The permit for pool construction was issued on November 6, 1979. Respondent was unable to complete construction of the pool at Mariner Village, inasmuch as problems developed after the pool was filled which caused the pool walls and decking to crack and leak. Respondent attempted to correct the deficiencies in the pool until approximately August of 1980, at which time he was ordered off the job by Mariner Village, Inc. Robert Hamilton, the developer and president of Mariner Village, was the person with whom Respondent negotiated the contract to build the pool for Mariner Village. During the course of time in which Respondent was attempting to correct the problems at Mariner Village, its president, Robert Hamilton, sent approximately six mailgrams to Petitioner reciting his contention that Mariner Village considered Respondent's actions to be a breach of its contract; that the pool was not completed in a professional-like manner and that Respondent's overall performance, or lack thereof, constituted negligence. (Petitioner's Composite Exhibits 3 and 4.) When Respondent completed the construction phase of the pool, neither the city nor the county would issue a certificate of occupancy to allow the residents of Mariner Village to use the pool. While it was noted that the county initially issued Respondent a certificate of occupancy for its construction of this pool site, that certificate was immediately revoked due to surface cracks in the pool on the north, east and west ends of the pool once it was filled to capacity. Robert Hamilton, president of Mariner Village, testified that at this time (during the hearing) he thought that the issuance of a certificate of occupancy was imminent and that while the price called for in the contract between Respondent and Mariner Village was $20,450.00, it (Mariner Village) had expended or was obligated to expend sums totaling $70,000.00 to complete the pool. Mr. Hamilton ordered two engineering studies to examine and report on performance in the Respondent's construction of the pool. According to Hamilton, the reports revealed that the pool was erected on "good" pilings. Respondent and Leslie Derfler entered into a contract on June 9, 1978, to construct a pool at his residence. The contract price was paid in full and the pool was completed, however, during the spring of 1979, Mr. Derfler detected an opening around the tile grout near the leaf-skimmer. The matter was immediately called to Respondent's attention. Failing to get a prompt response to his complaint, Mr. Derfler contacted the Better Business Bureau after which Mr. Derfler was able to communicate with Respondent during March of 1980. Respondent dispatched a repairman to regrout the tiles in the area around the leaf-skimmer, however, the repairman failed to regrout the tiles which he replaced. As a result, the door of the skimmer became inoperative and separated from the skimmer. Repeated attempts by Mr. Derfler to contact Respondent were unavailing and Mr. Derfler called another company (Boca Pool-Trol Laboratories, Inc.) to finish the necessary work. In this regard, evidence reveals that Respondent reimbursed Mr. Derfler for the monies paid to the Boca Pool-Trol Laboratories, Inc. Respondent and Lindberg Development Company, through its assistant project manager, Taisto Pistkan, entered a contract on January 31, 1980, for the installation of a commercial swimming pool at Shore Heights Condominiums in Lantana, South Palm Beach, Florida. Respondent commenced construction on the pool during August, 1980, and the pool was not completed, such that it could be used, until June, 1981. Mr. Pistkan had to make repeated requests of Respondent to correct numerous problems, including leaks, falling plaster and tiles. When Respondent initially completed construction of the pool and it was filled, during September, 1980, leaks surfaced and approximately nine months later (June, 1981) Respondent completed construction of the pool and a certificate of occupancy was issued. In this regard, Respondent admitted during the hearing that it took an inordinate amount of time to make the necessary repairs to get the Lindberg pool certified. On August 10, 1979, Mr. and Mrs. Melvin Dubovick entered into a contract with Magic Wands Pools to construct a pool at their residence in Delray Beach, Florida. This contract called for the completion of the pool within six weeks from the date that the permit was issued. In October of 1979, an agent of Wands Construction, which agent had previously been an agent of Magic Wands Pools, informed Mr. Dubovick that he would have to enter into a new contract due to a reorganization of the pool company. As a result of that advice, the Dubovicks and Respondent entered into another contract with Wands Construction Company, Inc., on October 25, 1979. (Petitioner's Exhibits 10 and 11.) According to Mr. Dubovick, the second contract was signed to "straighten out the paper work." Mr. Dubovick was advised that all of the material terms of the new contract would remain unchanged and that the work would be completed within approximately eight weeks. However, the contract with Wands Construction Company does not contain a completion date. Excavation for the pool was made during the middle of October, 1979. Thereafter, no further work was done during that year and the wooden deck of the Dubovicks' home, which was adjacent to the hole dug for the pool, collapsed on New Years Eve, 1979. Thereafter, there were a number of problems with the construction of the pool, including the fact that a spa was not built as called for in the plans for the pool which necessitated that the Respondent remove a portion of poured gunite around the pool's deck; the filter was improperly installed and leaks surfaced when the pool was filled, causing Respondent to place numerous patches and filter outlets in the pool. Additionally, the slope of the pool decking was improper and caused a flooding condition around the Dubovicks' patio. The dimensions of the pool were not completed according to plans in that the length of the pool as completed is 30 feet, 3 inches, whereas the plans called for the pool to be 34 feet in length. The contract provides that the pool would have a 15,000 gallon capacity whereas Mr. Dubovick contends that he has never been able to measure more than a 10,000 gallon capacity while he filled the pool. The pool was completed in July of 1980. Kim Parker, a certified pool contractor, testified on behalf of Petitioner concerning two of the projects complained of in the Administrative Complaint. Consultant Parker is a licensed pool contractor and has been certified approximately two years. He is presently the general manager for Almar Pools. Mr. Parker has supervised pool construction in excess of two years. Mr. Parker visited the Mariner Village project on August 28, 1981, and noted hairline cracks in the plaster around the pool. Those cracks indicated to him that the plaster was either improperly applied or cured. He also noted a return fitting protruding into the pool, which he considered to he evidence of "shoddy" workmanship. Mr. Parker also noticed that the pumps in the pump room were not installed in a "professional" manner. During this time period, Mr. Parker also visited the Dubovicks' residence and he noted that an air leak existed at the filter pump, which caused a loud noise and that the pool was situated approximately three inches above the patio which created a drainage problem. In this regard, the Dubovicks testified that two doors were ruined due to water drainage problems around the pool area. Mr. Parker considered the workmanship around the Dubovick pool to be professional in its appearance although he did note that the pool was not constructed to the measurements provided for in the contract. Respondent's Defense Respondent, Charles Bromley, qualified Magic Wands Pools during 1978. He did so, according to him, based on "bad legal advice." Respondent encountered numerous problems completing pools that were under construction for Magic Wands Pools while he also was handling the day-to-day affairs of the successor corporation. Respondent has completed all except two out of forty-two pools that remained incomplete when he took over and Magic Wands Pools ceased operations in late 1979. Respondent contends that the former owner dumped "problem" pools on him which included the Mariner Village pool. William Sheldon, a professional engineer who has acted as a consultant in the design of numerous pools (in excess of 1,000) was called as a witness to testify on behalf of Respondent. Mr. Sheldon visited the Mariner Village pool and studied the design. He concluded that inadequate pilings were the source of the problems with the Mariner Village pool. That is, he considered the pilings failed to give adequate support and that this was of no fault or could not result in any liability on Respondent's part, inasmuch as the pool contractor was not responsible for the pilings erected to provide support for the pool. Mr. Sheldon noted that the pilings were driven to substantially less depth than other short piles in the area which led him to conclude that the developers used "soft" piles which had a low-blow content. He concluded that this caused cracks to radiate out of the east end of the pool creating leaks. Mr. Sheldon's examination of the elevations around the pool indicated that the gutters were level; that the problem was therefore one relating to the pool's substructure and not due to any construction deficiency. Also, Mr. Sheldon noted that, based on his calculations, without the usual allowance in calculations for an approximate ten percent (10 percent) deviation in a pool's volume capacity, his calculations indicated that the pool would hold approximately 11,872 gallons whereas the plans called for an approximate gallonage capacity of 10,500 to 11,000 gallons. Finally, Mr. Sheldon indicated that his review of the pool construction at Mariner Village only indicated that there existed one extrusion which he considered not to be critical in view of the overall construction and the pool's layout. Respondent testified that construction at Mariner Village progressed at a reasonable pace indicating that on May 8, 1980, the pool was marble coated, however, the equipment was not completed in the pool room and therefore work could not proceed as scheduled. According to Respondent, the earliest time that the equipment was in place, by other subcontractors, was approximately August 18, 1980, and work commenced rapidly thereafter by Respondent's employees. Respondent testified that an engineer inspected the gutters on July 16, 1980, at which time the gutters were properly erected and that within four days, i.e., on July 20, 1980, the gutters were "low" and the tiles had sunk. Respondent replaced the gutters without cost, however, he refused to do further work on the pool until the substructure was solidified. During this period, Respondent also testified that Mariner Village failed to timely honor draw payment requests which forced him to stop work until funds were received according to the schedule for draws. Finally, Respondent testified that the pilings and related substructures were obligations contracted for and hired independently by the general contractor. For this reason, the Respondent offers that he was not obligated for the failures surrounding the pool at Mariner Village. Respondent admits that the Dubovick project caused problems in that it was one that was left from the predecessor entity, Magic Wands Pools. He admits to delays in construction, however, he testified that he labored as faithfully as he could under the circumstances and further that all corrections and/or repairs were made that were called to his attention. As to the contention that the pool was constructed smaller than the 15,000 gallon volume capacity as reflected in the plans and specifications, Respondent indicates that the 15,000 gallon capacity was an error and further that the Dubovicks never indicated to him that there was any discrepancy or deviations from requirements in the plans and specifications as he was required to do according to the terms of the contract. Respondent indicates a willingness to negotiate with the Dubovicks respecting this omission. Finally, Respondent testified that he never met the Derflers, although he did dispatch a repairman out to remedy their problem. Respondent considered that the problem had been resolved and was unaware that it had not until the subject complaints were filed. Respondent has, however, refunded the Derflers' monies which were expended to hire an outside contractor. Throughout the time in which Respondent was attempting to complete or correct projects which had been started or initiated by Magic Wands Pools, he labored to do so with as much dispatch as possible under the circumstances. Respondent indicates that money was due and owing Magic Wands Pools by many customers who refused or was slow to pay. Respondent has been in the pool construction business in excess of twenty years and based on the experience gained and the nature of that business he (Respondent) refuses to guarantee a completion date for a pool due to weather and other uncertainties beyond his control. He again acknowledged that the repairs took a great deal of time to complete, however, he stressed that he labored to perform those repairs in as much dispatch as possible under the circumstances. Concluding, Respondent offered that part of his problem with the Dubovick pool had to do with his attempt to stay within the setback lines of the Dubovicks' property which prompted him to make minor deviations from the plans and specifications.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED: That the Respondent, who holds certified pool contractors License No. CP- 007871, be placed on probation by Petitioner for a period of one year. RECOMMENDED this 26th day of January, 1982, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of January, 1982.

Florida Laws (3) 120.57489.119489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOAQUIN VAZQUEZ, 76-002112 (1976)
Division of Administrative Hearings, Florida Number: 76-002112 Latest Update: Aug. 11, 1977

The Issue Whether the state certified pool construction license number CP C008904 and the state certified general contractor's license number CG C002481 of Joaquin Vazquez should be revoked.

Findings Of Fact Division A of the Construction Trade Qualifying Board held a hearing on September 15, 1976, pertaining to ten (10) charges of violating the Dade County building code against Respondent Joaquin Vazquez. At the completion of this formal hearing, Joaquin Vazquez was found guilty of eight (8) of the ten (10) charges. Charles W. Leavitt, Jr., Clerk of the Construction Trades Qualifying Board In Metropolitan Dade County, Florida, identified the minutes of the Board Meeting held on September 15, together with the charges as set forth in letters dated May 10, 1976, and August 19, 1976. Copies of these instruments were introduced into evidence without objection. The Respondent did not deny the charges at the hearing and had not appealed the finding of guilt of eight (8) of the ten (10) charges at the conclusion of the formal hearing on September 15, 1976. Briefly the charges (spanning the term from July 1, 1975 to June 29, 1976), finds and penalties are as follows: Charge 1.: Allowing permit to be applied for and taken out in Respondent's name in order for Angela J. Stevens and/or Sparkle Blue Pools to construct a swimming pool. Found guilty - letter of reprimand. Charge 3.: Similar to Charge 1 - found guilty - certificate to be suspended for one (1) year. Charge 4.: Failure to supervise, direct and control, the construction or installation of a swimming pool taken out in Respondent's name. Found guilty - one (1) year suspension to run concurrent with any other suspensions. Charge 5.: Similar to Charge 1 - found guilty - ninety (90) day concurrent suspension. Charge 6.: Similar to Charge 4 - found guilty - ninety (90) day suspension. Charge 7.: Similar to Charge 1 - found guilty - revo- cation of certificates. Charge 8.: Similar to Charge 4 - found guilty - both certificates be revoked. Charge 10.: Allowing a permit to be applied for and taken out in Respondent's name in order for Jack Goodman and/or Precision Engineering, Inc., to construct a swimming pool. Found guilty - letter of reprimand. An Administrative Complaint was filed by the Petitioner through its executive director on November 12, 1976, citing the hearing and the charges and the finding of guilt of Respondent and stating that the results of said formal hearing show a violation of Florida Statute 468.112(2)(a), willful or deliberate disregard and violation of applicable building codes or laws of the state or any municipality, cities or counties thereof. Therefore, the Board seeks to revoke the state certified pool contractors license number CP C008904 and state certified general contractors license number CG C002481 of Joaquin Vazquez, the Respondent. The Respondent did not deny the charges but presented an attack on the character and veracity of the witness, Angela Stevens, in four (4) of the charges against him. He cited the witness Angela Stevens' failure to abide by probationary requirements imposed for her acting as a contractor without a license. Furthermore, the Respondent offered his own and a witness, Mr. Gonzalez's, testimony to the fact that he was solicitated by Angela Stevens to make false testimony to the effect that Angela Stevens was an employee of his when in fact she had never been. The charges against the Respondent were brought subsequent to the charges brought against the witness Angela Stevens. The Respondent contends that the affidavits and testimony of Angela Stevens were no more than self serving statements made in her own behalf in an attempt to cover up her criminal intentions and that the charges and finding of guilt of the Respondent were based largely on the affidavit and testimony of said witness. Respondent further offered a medical report indicating that he was unable to work in the month of May, 1975, and further his testimony was that he was out of the country in mid June and July, 1975, in order to recuperate from high blood pressure attacks. Petitioner contends: the undisputed evidence presented in the finding of guilt of the charges involved in the prior hearing are sufficient to find Respondent guilty of violating Section 468.112(2)(a), Florida Statutes, and that Respondent's license should be revoked. Respondent contends: the witness against him was self serving and an attempt to cover up her criminal intentions; that he in fact supervised some of the jobs he was found guilty of not supervising; that he was ill some of the time and did not willfully violate the code. The proposed facts and conclusions of the parties submitted after the hearing herein have been considered in this Recommended Order.

Recommendation Suspend the licenses, No. CP C008904 and No. CG C002481, of the Respondent Joaquin Vazquez for a period not to exceed six (6) months. DONE and ORDERED this 31st day of May, 1977, in Tallahassee, Florida. DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: David Linn, Esquire Post Office Box 1386 Tallahassee, Florida 32302 Jerome S. Reisman, Esquire 1515 Northwest 7th Street, #106 Miami Florida 33125 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer