Findings Of Fact Petitioner, in conjunction with the Construction Industry Licensing Board, is the state agency charged with the responsibility to prosecute administrative complaints pursuant to Chapters 120, 455 and 489, Florida Statutes and rules and regulations promulgated thereunder. During times material, Respondent, Donald F. Colombo, was licensed as a certified pool contractor in Florida, having been issued license number CP 15343. During times material, Respondent's license was registered with Petitioner as the qualifying agent for National and Spa Builders, Inc. (National). On or about May 27, 1988, National, the entity which Respondent was the qualifying agent, contracted with Diane and Leonard Cline to construct a pool at the Cline's residence in Tarpon Springs, Florida, for the contract price of $9825.00. The Clines financed the construction of the pool by placing a security interest against their property for the full purchase price of the pool. The full contract price of $9825.00 was paid to National and after National completed approximately 40% of the pool construction, National abandoned the project without notice or just cause. National never completed construction of the pool and the Clines obtained a homeowner's building permit and completed the pool project at an additional cost of approximately $5,000.00. Additionally, liens were filed against the property of the Clines by Florida Mining and Materials Concrete Corporation in the amount of $682.00 and Jim's Custom Pool Work in the amount of $135.00. The above-referred liens were for work performed and/or materials supplied in the construction of the Cline pool project by National. On or about May 20, 1988, National entered into a contract with Ben and Linda Thomas to construct a pool at their residence in Lutz, Florida, for the contract price of $9000.00. Following commencement of construction, National received approximately 60% of the contract price ($5,400.00) and later abandoned the project without notification or just cause to the Thomas's. The Thomas's subsequently completed their pool at an additional cost of approximately $1,000.00 over and above National's original contract price. On or about January 11, 1989, Respondent was disciplined by the Hillsborough County Building Department, Building Board of Adjustments, Appeals and Examiners for alleged violation of local laws including abandoning a construction project; alleged willful and deliberate disregard of applicable building codes; allegedly allowing liens to be filed against a project for which he was the contractor and for allegedly diverting funds from a construction project. Respondent was assessed an administrative penalty of a 30-day suspension of his permitting privileges by the Hillsborough County Building Department. Respondent was the qualifying agent for National during the 90-day period commencing April 1 through June 30,1988. Respondent formally terminated his status as qualifying agent for National and also tendered his resignation from that entity based on difficulties that he ecountered respecting his attempts to serve as qualifier to include his inability to control the finances, to be kept apprised of accounts receivable, accounts payable, an inability to select contractors and material suppliers and to assure that the payments for such services were timely remitted. Prior to Respondent's engagement with National as a pool salesman and later as qualifier, National was a well reputed pool company, having been in existence in excess of twelve years. National annually constructed approximately 750 pools with accounts receivable in the $10 to $12 million dollar range. Prior to April 1988, National was a secure and stable company that regularly paid its bills and grew at a rapid pace. While engaged with National, Respondent was unaware that there was internal collusion among its owners respecting diversion of funds. Respondent repeatedly attempted to gather a handle on the internal financial operations of the company and on each occasion he was rebuffed. within the first month that Respondent qualified National, he began to seek advice as to the proper means of salvaging his license by contacting a local attorney, the local office of Petitioner, and Petitioner's headquarters in Tallahassee seeking the proper procedures for ending his relationship with National. This came about once it became apparent that he was unable to effectively manage or otherwise perform the functions of a qualifying agent. Respondent formally severed his relationship as qualifying agent for National on June 30, 1988. Subsequent to ending his status as qualifying agent for National, Respondent assisted the Clines in the completion of their pool. Mr. Cline specifically recalled that Respondent assisted him in locating other subcontractors and with the purchase of plumbing supplies for his pool without remuneration from the Clines. (Petitioner's Exhibit 1F; Tr. 30-32.) Likewise, Respondent also assisted the Thomas's in completing their pool. (Tr. 45, lines 23-24.) Respondent demonstrated compassion and a proper concern which was evident based on the testimony of the complaining witnesses who appeared at the formal hearing. Significantly, Petitioner's investigator, H. Dennis Force, related that Respondent assisted him in his investigation of the subject charges. To this end, Respondent supplied him with the names of all customers with which National had contracts with during the period that he was National's qualifying agent. It is unfortunate that Respondent was not able to control the fiscal policies of National during the period that he was the qualifying agent, although from a review of the evidence herein, it is apparent that this was not based on his failure to attempt to gain control over the situation as a qualifying agent, but was rather based on the collusion of National's higher-ups who was determined to keep Respondent in the dark. Noteworthy was the fact that within a three-month period, National changed banks at least eight times. It would have been, at best, difficult if not impossible for Respondent to have gained a handle on National's financial condition and to do the things with which a qualifying agent is charged with during the short period during which Respondent was National's qualifying agent.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner enter a Final Order imposing an administrative fine against Respondent in the amount of $1,000.00 and placing his certified pool contractor's license on probation for a period of six (6) months. 1/ DONE and ENTERED this 7th day of March, 1991, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of March, 1991.
The Issue Whether the claimants herein are entitled to payment from the Construction Industries Recovery Fund and, if so, the amount of the payment to which each claimant is entitled. Whether the license of the Petitioner is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998).
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Fund is established by Section 489.140, Florida Statutes, for the purpose of reimbursing those persons who meet the eligibility requirements set forth in Section 489.141, Florida Statutes. The Board is the entity responsible for reviewing applications for payment from the Fund and entering orders approving or disapproving the applications. Sections 489.140(1) and 489.143(1), Florida Statutes. Mr. Kiselius is a licensed residential pool/spa contractor, having been first issued such a license in 1984. Mr. Kiselius's license is currently on inactive status, but at the times material to this action, Mr. Kiselius's license was active. Pool Masters was a Florida corporation incorporated on August 10, 1995. Frederick H. Martin and Abraham Zafrani were the sole shareholders of the corporation, and Mr. Martin was the President and Secretary of the corporation, and Mr. Zafrani was the Vice-President and Treasurer. From on or about October 24, 1995, until November 14, 1997, Mr. Kiselius was the qualifying agent for Pool Masters. The record does not reflect the date on which Pool Masters was issued its certificate of authority allowing it to engage in contracting as a business organization, but it was assigned Qualified Business Organization License Number QB0002327 on or about November 6, 1996. Pool Masters filed for bankruptcy pursuant to Chapter 7 of the United States Bankruptcy Code on January 1, 1998, and the corporation was administratively dissolved on October 16, 1998. DOAH Case No. 99-1665: Santibanez and Pappas Eugene Santibanez and Alexander Pappas entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 25, 1997. The total price stated in the contract was $21,000.00; a change order was executed on November 4, 1997, for an additional price of $2,890.00. Pool Masters represented to Mr. Santibanez and Mr. Pappas that it was a licensed swimming pool contractor. Pool Masters began work on the pool on or about May 17, 1997. Mr. Santibanez and Mr. Pappas made payments to Pool Masters pursuant to the contract, and Pool Masters excavated the hole for the pool, put in the foundation, and poured the concrete. Pool Masters ceased work on the swimming pool in late November 1997, after the concrete was poured. A week later, Mr. Santibanez heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. Santibanez and Mr. Pappas had paid Pool Masters a total of $19,690.00 for work done pursuant to the contract and change order. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. At least one lien was filed against Mr. Santibanez's and Mr. Pappas's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Santibanez and Mr. Pappas submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Santibanez and Mr. Pappas to file suit against Pool Masters. Mr. Santibanez and Mr. Pappas filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Santibanez and Mr. Pappas alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 3/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 4/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 5/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 6/ ] Mr. Santibanez and Mr. Pappas further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $17,975.50, and they included in the complaint an itemized list of expenditures to support their claim. The circuit court entered a Default Final Judgment on August 4, 1998, awarding Mr. Santibanez and Mr. Pappas $17,675.50, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Santibanez and Mr. Pappas submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Santibanez and Mr. Pappas did not receive any funds from the bankruptcy estate or any other source to satisfy the judgment against Pool Masters. Mr. Santibanez and Mr. Pappas satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $17,675.50. DOAH Case No. 99-1666: Klaus and Lucrecia Mueller Klaus and Lucrecia Mueller entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about February 24, 1997. The total price stated in the contract was $16,400.00. Pool Masters represented to Mr. and Mrs. Mueller that it was a licensed swimming pool contractor. Pool Masters began work on the pool in Spring 1997, and Mr. and Mrs. Mueller made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool, installed the steel frame, poured gunnite at the shallow end of the pool, and installed the brick and tile around the pool. Pool Masters last worked on the swimming pool in late November 1997. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Mueller had paid Pool Masters approximately $12,900.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Mueller's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Mueller submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Mueller to file suit against Pool Masters. Mr. and Mrs. Mueller filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Mueller alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 7/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 8/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 9/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 10/ ] Mr. and Mrs. Mueller further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,299.51. The matter was presented to the circuit court, ex parte, upon Mr. and Mrs. Mueller's Motion for Default Final Judgment. The court entered a Default Final Judgment in June 1998, awarding Mr. and Mrs. Mueller $13,299.51, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated June 23, 1998, Mr. and Mrs. Mueller submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Mueller did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Mueller satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $13,299.51. DOAH Case No. 99-1667: Mario and Martha Alboniga Mario and Martha Alboniga entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 17, 1997. The total price stated in the contract was $24,000.00. Pool Masters represented to Mr. and Mrs. Alboniga that it was a licensed swimming pool contractor. Pool Masters began work on the pool on November 10, 1997, and Mr. and Mrs. Alboniga made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and poured the concrete form of the pool. The last day Pool Masters worked on the swimming pool was November 19, 1997. Mr. and Mrs. Alboniga later heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Alboniga had paid Pool Masters a total of $15,200.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Alboniga’s property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Alboniga submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Alboniga to file suit against Pool Masters. Mr. and Mrs. Alboniga filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Alboniga alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 11/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 12/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 13/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 14/ ] Mr. and Mrs. Alboniga further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $10,541.77. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. and Mrs. Alboniga $10,541.77, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. and Mrs. Alboniga submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Alboniga did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Alboniga satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $10,541.77. DOAH Case No. 99-1668: Salvator Militello and Sharon Sidorski Salvator Militello and Sharon Sidorski entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about April 6, 1997. The total price stated in the contract was $24,295.00. Pool Masters represented to Mr. Militello and Ms. Sidorski that it was a licensed swimming pool contractor. Mr. Militello and Ms. Sidorski made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and spa, installed basic plumbing, and poured the concrete for the pool. Pool Masters last worked on the swimming pool in October 1997. At the time Pool Masters ceased work on the pool, Mr. Militello and Ms. Sidorski had paid Pool Masters $19,389.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. Militello's and Ms. Sidorski's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Militello and Ms. Sidorski submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Militello and Ms. Sidorski to file suit against Pool Masters. Mr. Militello and Ms. Sidorski filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Militello and Ms. Sidorski alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 15/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 16/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 17/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 18/ ] Mr. Militello and Ms. Sidorski further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,544.00 and that they paid $1,641.68 to satisfy liens and unpaid subcontractors and materialmen, for total damages of $15,185.68. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. Militello and Ms. Sidorski $15,185.68, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Militello and Ms. Sidorski submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Militello and Ms. Sidorski did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. Militello and Ms. Sidorski satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $15,185.68. DOAH Case No. 00-0024: Jack and Paula Tieger Jack and Paula Tieger entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about December 17, 1995. The total price stated in the contract was $28,200.00. Pursuant to the contract, Pool Masters built a pool and screen enclosure, and Mr. and Mrs. Tieger paid Pool Masters the price specified in the contract. Mr. and Mrs. Tieger were not, however, satisfied with the work done by Pool Masters, and, in or around 1997, they filed a complaint for breach of contract against Pool Masters in the Circuit Court of the Seventeenth Judicial Circuit, in Broward County, Florida. In the complaint, Mr. and Mrs. Tieger alleged that Pool Masters had breached the contract: By failing to adequately explain the technical terms used in the Agreement to the TIEGERS; By failing to install a vacuum line with valve as specified in the Agreement; By failing to install anti-corrosive handrails in the swimming pool; By failing to properly install and/or provide a properly functioning waterfall as specified in the Agreement; By failing to properly fill the area behind the waterfall; By unilaterally, and or the TIEGERS' [sic] objection, placing a tile with the "Pool Masters" logo on the steps heading into the pool: By failing to re-route the TIEGERS' [sic] sprinkler system in a timely manner; By failing to advise the TIEGERS that they were going to need to pay for and install a separate circuit breaker box as part of the installation of the swimming pool; and By failing to install the second screen door as specified in the Agreement. Mr. and Mrs. Tieger did not identify the amount of damages they allegedly suffered as a result of Pool Masters's alleged breach of contract. Mr. and Mrs. Tieger were not aware that Pool Masters had declared bankruptcy until January 1998, when Mrs. Tieger went to Pool Masters' office and found the notice on the door. A non-jury trial was held before the circuit court on March 5, 1998; Pool Masters did not attend the trial. In a Final Judgment entered on March 25, 1998, the court awarded Mr. and Mrs. Tieger $4,200 as compensatory damages to be recovered from Pool Masters. In a Proof of Claim dated May 13, 1998, and filed with the United States Bankruptcy Court of the Southern District of Florida, Mr. and Mrs. Tieger submitted an unsecured claim against Pool Masters' bankruptcy estate in the amount of $7,300.00, which represented the compensatory damages awarded in the final judgment, together with attorney's fees and costs. Mr. and Mrs. Tieger have not collected any portion of their judgment against Pool Masters. Mr. and Mrs. Tieger submitted to the Board a Construction Industries Recovery Fund Claim Form dated December 5, 1998, and the Board awarded Mr. and Mrs. Tieger $800.00, representing the cost of the vacuum line with valve and the second screen door which Pool Masters had not installed. Mr. and Mrs. Tieger do not satisfy the statutory criteria for eligibility for payment from the Fund. Mr. and Mrs. Tieger failed to establish that they filed their claim with the Board within two years of the date they discovered the alleged deficiencies in the pool, and they failed to establish that the final judgment against Pool Masters was based on a violation of Section 489.129(1)(g), (j), or (k), Florida Statutes (Supp. 1998). The evidence presented herein is not sufficient to establish that Mr. Kiselius is the licensee against whom the claimants obtained final judgments.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, 25/ it is RECOMMENDED that the Construction Industry Licensing Board: Enter final orders as follows: In DOAH Case No. 99-1665, finding Eugene Santibanez and Alexander Pappas eligible for payment from the Fund in the amount of $17,675.00, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1666, finding Klaus and Lucrecia Mueller eligible for payment from the Fund in the amount of $13,299.51, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1667, finding Mario and Martha Alboniga eligible for payment from the Fund in the amount of $10,541.77, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1668, finding Salvator Militello and Sharon Sidorski eligible for payment from the Fund in the amount of $15,185.68, in satisfaction of a final judgment against Pool Masters, Inc.; and In DOAH Case No. 00-0024, dismissing the claim of Jack and Linda Tieger for payment from the Fund. Determine that Christopher P. Kiselius is not the "licensee" whose license is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998), as a result of payments to the claimants in DOAH Case Nos. 99- 1665, 99-1666, 99-1667, and 99-1668. DONE AND ENTERED this 31st day of August, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2000.
The Issue At issue is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what penalty should be imposed.
Findings Of Fact Petitioner, the Department, is the state agency charged with the duty and responsibility of regulating the practice of contracting pursuant to Chapters 20, 455 and 489. At all times material to the allegations of the Administrative Complaint, Mike H. Kargar, d/b/a Kargar Construction, Inc., was licensed as a Florida State Certified Building Contractor and a Florida State Certified Pool/Spa Contractor, having been issued license numbers CBC 37867 and CPC 52530 respectively. His licensure status for each license is designated as "Current, Active." The Department's records establish that at no time material hereto did Kargar Construction apply for or obtain a Certificate of Authority as a Contractor Qualified Business in the State of Florida. On or about July 14, 1999, Respondent, doing business as Premier Pools, entered into a contract with Ronald and Gina Steger (the Stegers) for construction of a residential swimming pool to be located at 466 Champagne Circle, Port Orange, Florida. The contract price was $26,469.00. Respondent was paid in full by the Stegers for the construction of the swimming pool at their residence. While Respondent verbally informed Mr. Steger about the Construction Industries Recovery Fund, the contract does not contain a written statement explaining the consumer's rights under the Construction Industries Recovery Fund. Respondent has constructed thousands of residential pools during his career. Respondent proceeded with the construction of the Stegers' pool in the same manner as with all other pools he constructed. That is, he reviewed the contract documents, visited the job site to inspect the site during the various stages of construction, and was in charge of scheduling. As is his typical practice, Respondent also had superintendents who oversaw the project and subcontractors who performed most of the actual work on the excavation and construction of the pool. Respondent visited the Stegers' job site at least twice. He went to the pool site before the pool was "shot." During that visit, he did not observe anything that raised concerns regarding the soil conditions that existed at the Steger residence. He inspected the Stegers' job site after the shell was poured and did not observe any problems. He also observed the control joints for the concrete for the pool deck. The spacing of the control joints at the Stegers' job site was the same as his company usually utilizes in constructing pool decks. Robert Fleming is the owner/operator of Fleming Excavating, which is in the business of excavating for swimming pools. He has been in the business of excavating pools for about ten years and has excavated between 5,000 and 6,000 pools. He and persons who work for him performed the excavation of the Stegers' pool. As is typical on a pool excavation job, Mr. Fleming performed what he refers to as "LDS" on the Stegers' pool. That is, layout, dig, steel, and be ready for inspection. He staked out the pool, determining its shape, then excavated the dirt. After the dirt was excavated, he and his workers put in the steel for inspection. In digging the Stegers' pool, Mr. Fleming did not encounter any unusual subsurface soil conditions to give him any indication that there would be problems for the pool in the future. About two weeks after the project was completed, Mr. Steger observed what he perceived to be a half inch rotation of the pool shell in the ground. When the pool was initially filled with water, the water level followed the grout line of the tile around the pool. After a couple of weeks, the water level against the pool tile furthest from the home was at a different level than the tile toward the area of the pool closest to the home. This was reported to Respondent. Mr. Steger then noticed a crack in the pool deck on the backside of the pool. He described the shape of the initial crack to be the same shape as the backside of the pool shell in the decking. Other cracks formed. One is evident where pieces of tile around the pool shell have come off at the place where the crack in the pool deck meets the pool shell. The cracking is all on the deck, not in the pool itself. A representative of Respondent's company went to the Stegers' home in March of 2000 and documented on a warranty form as follows: Southwest deck, [less than] 1/32 separation around the perimeter south of beam. Northwest near expansion tile needs to be regrout. Watch for further expansion northeast. Near expansion tile needs to be regrout. Watch for further expansion. Between December 1999 and March 2000, Mr. Steger made two other requests for warranty work. These conditions were corrected by Respondent and signed off as satisfactorily completed by Mr. Steger. Sometime in the year 2000, Respondent became aware of the cracking problems in the Stegers' deck. He went to the Stegers' home and met with Mr. Steger. He observed that the cracks were in a circular type of pattern following the pool shape. Respondent offered to repair the deck cracks by "v- ing" out the cracks and inserting a urethane 500 product to stop the cracks from coming through. Once that process was completed, Respondent proposed that he would then "respray and re-acrylic the affected area of the deck." Respondent has used this process numerous times to cover cracks in decks, and once it is used, the cracks do not show. Mr. Steger did not agree to Respondent's proposal to repair the cracking of the deck area as illustrated by his testimony at hearing: Mr. Kargar came out and told me that he would, in fact, grind out the concrete in the cracks themselves, fill them in with some sort of epoxy substance in order to mask the cracking. However, that does not address the original problem of the pool shell shifting and the deck moving away from the pool. So, no, I did not accept that as a solution to the problem. Richard Kushner is a civil engineer with a concentration in geotechnical engineering and construction engineering. He works for Universal Engineering Science (Universal). Mr. Steger called Universal which conducted an investigation as to why the pool deck was cracking. A field representative from Universal went to the Stegers' home and performed four manual auger borings into the soil to test the type and condition of the soil under the pool deck, ran density and compaction tests to see how tight the soils were underneath the pool deck, and observed the cracking and the cracking patterns in the concrete. Mr. Kushner did not personally go to the Stegers' as it is customary in the field of geotechnical and construction engineering to review data, do whatever analysis is necessary, and come to a conclusion using an investigative report. Regarding the cause of the pool deck cracking, Mr. Kushner had three concerns: the compaction of the soil underneath the concrete slab was less than 90 percent, whereas the industry standard is 95 percent; evidence of wood rot was found at one of the auger borings, indicating that the original soils were not well stripped and cleared of debris, such as sticks and roots; and insufficient spacing of control joints in the concrete. Mr. Kushner concluded that the contractor and subcontractors who constructed the pool deck were responsible for the cracking in the pool deck. Mr. Kushner acknowledged that two of the three concerns, i.e., the soil compaction and the evidence of organic debris, are circumstances that may cause future problems but were not the cause of the current problems with the deck cracking. Mr. Kushner also acknowledged that the pool cracking is a problem which is cosmetic or aesthetic in nature and that the cracks in the pool deck are not structural problems. Universal's investigation and Mr. Kushner's report relate exclusively to the pool deck, not to the pool shell or the subsoil conditions under the pool shell. Mr. Kushner was not aware when he wrote the report relied upon by Petitioner that there was an issue regarding whether the pool shell was shifting; was not involved in any discussions about the pool shell; and was not aware that the cracks in the pool deck follow the shape of the pool. Mr. Kushner acknowledged that any shifting of the pool shell could be caused by soil conditions underneath the pool shell and could be the cause of deck cracking that followed the shape of the pool. However, the investigation conducted by Universal and his report were exclusively related to the cracking of the pool deck and did not examine anything regarding the pool shell itself. As of July 18, 2003, the Department's costs of investigation and prosecution, excluding legal costs, totaled $384.63.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the Construction Industry Licensing Board enter a final order imposing a $100.00 fine to be deposited in the Construction Industries Recovery Fund for a violation of Section 489.1425, issue a notice of noncompliance pursuant to Section 489.119(6)(e), and require Respondent to pay $384.63 in costs of investigation and prosecution. DONE AND ENTERED this 22nd day of August, 2003, in Tallahassee, Leon County, Florida. S ___________________________________ BARBARA J. STAROS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 2003.
The Issue Whether the Respondent committed the violations alleged in the Administrative Complaints dated June 3, 1998, and December 23, 1998, and, if so, the penalty that should be imposed.
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department is the state agency responsible for investigating and prosecuting complaints made to the Department for violations of Chapter 489, Part I, Florida Statutes. Sections 489.131(7)(e) and 455.225, Florida Statutes (1997). Pursuant to Section 489.129(1), Florida Statutes (1997), the Construction Industry Licensing Board ("Board") is the entity responsible for imposing discipline for any of the violations set forth in that section. At all times material to these proceedings, Mr. Esquinaldo was a licensed swimming pool contractor, having been issued license number CPCO50527 by the Board, and he was the qualifying contractor for Challenger Pools, Inc. ("Challenger Pools"). Mr. Esquinaldo has been a licensed swimming pool contractor since 1987. In that time, Mr. Esquinaldo has been cited by the Department once, in June 1992, and Mr. Esquinaldo paid an administrative fine of $50.00 for the violation, which was failure to obtain a final inspection after completing a swimming pool. At the times material to these proceedings, Challenger Pools had several offices in south and central Florida, and built approximately 1,500 pools each year. Mr. Esquinaldo was the only qualifier for the company. The building code that governed each of the projects at issue herein was the South Florida Building Code, 1996 Edition. This Code required a number of inspections: For the structural portion of the pool, three inspections were required: the pool steel, the pool deck, and the final inspection. For the plumbing portion of the pool, three inspections were required: the main drain, pool piping, and the final inspection. For the electrical portion of the pool, three inspections were required: the electrical grounding of the steel structure, the pool deck grounding, and the final inspection. In addition, a final inspection was required for any fencing to be installed. It is the responsibility of the pool contractor to call for the required inspections for work over which it has responsibility. The South Florida Building Code, 1996 Edition, also provided that building permits, including permits for the construction of swimming pools, would expire if 180 days elapsed without the contractor calling for an inspection. It is not unusual in the pool contracting industry for inspections to reveal code violations. The contractor is, however, expected to correct the violations and any other deficiencies noted in the inspection reports. During the times material to these proceedings, it was the policy of Challenger Pools that, whenever a customer threatened a lawsuit or filed a lawsuit, it would stop work immediately on the customer's pool and it would cease all direct communications with the customer. Work would recommence at the direction of Challenger Pools' attorney. This policy was adopted on the advice of Challenger Pools' attorney. DOAH Case No. 98-3713 - Irving Jovellar On May 7, 1996, Challenger Pools, Inc., and Irving Jovellar entered into a Swimming Pool Construction Agreement for the construction of a swimming pool and spa at 188 Truxton Drive, Miami Springs, Florida. Addenda to the agreement were executed on June 6 and 22, 1996, and on September 6, 1996. The contract price was $14,000.00, with $1,600.00 added pursuant to the September 6, 1996, addendum. The full contract price of $15,600.00 was paid by Mr. Jovellar, and the check for the final payment was processed by the bank on October 2, 1996. 2/ On June 11, 1996, Challenger Pools applied to the City of Miami Springs, Florida, for a building permit for the pool. Challenger Pools began work on Mr. Jovellar's pool on June 13, 1996, and the swimming pool, plumbing, and electric permits were issued on July 12, 1996. Challenger Pools worked on Mr. Jovellar's pool throughout the summer of 1996. The steel installation was approved on July 19, 1996, and the slab was approved September 12, 1996. The pool was plastered on September 28, 1996, and the pool was filled with water and operating on September 30, 1996. 3/ In a letter dated September 26, 1996, Mr. Jovellar's attorney notified Challenger Pools that the gate to Mr. Jovellar's fence had been damaged during the pool excavation and that Mr. Jovellar expected to be compensated for the damage. Challenger Pools advised Mr. Jovellar that the excavator, Tom Waters, was responsible for the damage and that he should look to Mr. Waters for compensation. Mr. Jovellar filed suit against Mr. Waters in small claims court, served Mr. Waters in early February 1997, and recovered approximately $450.00 in damages from Mr. Waters. Mr. Jovellar's pool did not pass the plumbing final inspection dated November 8, 1996, because the pool heater was not properly installed. Challenger Pools renewed the structural and plumbing permits on July 24, 1997. In a letter dated October 30, 1997, Mr. Jovellar's attorney notified Challenger Pools that, if it did not correct the defects in the swimming pool, suit would be filed against Challenger Pools. Challenger Pools responded in a letter dated November 6, 1997, that it was prepared to correct the problems with the pool. Challenger Pools further advised that, because the pool permits had expired, it would apply to renew the permits so that work could begin. Challenger Pools renewed the structural, plumbing, and electrical permits on January 19, 1998. Challenger Pools went back to work on Mr. Jovellar's pool in January 1998. The next inspections of Mr. Jovellar's pool took place between July 15, 1998, and January 6, 1999, the date on which the pool passed its final inspection. Notwithstanding the plumbing inspection conducted on November 8, 1996, and the permit renewal on July 24, 1997, Mr. Esquinaldo testified that, on the advice of its attorney, Challenger Pools ceased work on Mr. Jovellar's swimming pool in early October 1996, when it received the September 26, 1996, letter from Mr. Jovellar's attorney regarding the broken fence gate. On the basis of Mr. Esquinaldo's testimony, it is established that Challenger Pools ceased work on Mr. Jovellar's pool in early October 1996. The evidence also establishes that work recommenced in early 1998. Accordingly, Challenger Pools failed to work on Mr. Jovellar's pool for a period in excess of 90 consecutive days between October 1996 and January 1998. The evidence further establishes that Challenger Pools ceased work because Mr. Jovellar threatened a lawsuit to recover damages for repair of a fence damaged by the person who excavated the pool. Under the circumstances, the threatened lawsuit did not constitute just cause for Challenger Pools' failure to work on Mr. Jovellar's pool between October 1996 and January 1998 even though Challenger Pools stopped work on the advice of its attorney; Challenger Pools advised Mr. Jovellar to proceed against the excavator to recover for the damages to the fence, which Mr. Jovellar did in early 1997. The Department did not present evidence sufficient to establish that Challenger Pools failed to work on Mr. Jovellar's pool for 90 consecutive days subsequent to January 1998. As of October 6, 1999, the Department had expended $160.52 in investigative costs and $2,433.90 in prosecutorial costs with respect to Mr. Jovellar's complaint. DOAH Case No. 99-2654 - David Casadona On September 30, 1996, Challenger Pools entered into a Swimming Pool Construction Agreement with David Casadona for construction of a residential swimming pool at 14910 Southwest 70th Place, Davie, Florida. The full contract price was $9,000.00, and Mr. Casadona made the final payment on the pool in March 1997. Mr. Casadona was building a house at this address, and, a representative of Challenger Pools advised Mr. Casadona that construction on the swimming pool would begin after construction on the house was completed. Mr. Casadona moved into the new house on November 6, 1996, and Challenger Pools began excavating the pool approximately a week and a half later, in mid-November 1996. Challenger Pools submitted applications to the Town of Davie for the electrical, plumbing, and structural permits for Mr. Casadona's pool on November 19, 1996. The permits to construct the swimming pool were issued on January 2, 1997. Mr. Casadona contracted separately for installation of a fence around the pool, and, pursuant to the agreement between Mr. Casadona and Challenger Pools, Mr. Casadona was responsible for ensuring that the fence met local building codes. Challenger Pools was not licensed to install fences, and the installation of a fence was not included in any of Challenger Pools' swimming pool construction agreements. The permit for the fence was issued January 2, 1997. The Town of Davie conducted a special inspection of Mr. Casadona's property on December 18, 1996, before the permits were issued for construction of the pool, to determine whether a fence existed on the property and the height of the fence, if one existed. At that time, the inspector discovered that the pool had already been excavated and that the rebar was in place. The inspector also noted that part of the footer for the rear patio of the house had been undermined. A permit is required before a pool is excavated, but it is not unusual for a pool contractor to begin excavation before the permit is issued. An inspection of the plumbing pool main drain was conducted on January 3, 1997, and approved without comment. An inspection of the electrical pool grounding was conducted on January 3, 1997, and approved without comment. An inspection of the structural pool steel was conducted on January 6, 1997. The pool steel was approved with an exception. The inspector noted that an area under the existing structure had been undermined, and Challenger Pools was directed to pour the gunnite for the pool as soon as possible and to consult an engineer for directions on how to return the existing structure to its original specifications. The inspector further required that an engineer provide certification that the existing structure had proper support in the area in which it was undermined. The face of the footer under the structure was exposed, and the earth underneath the structure was undermined about three or four inches; the undermining did not threaten the integrity of the existing structure. An inspection of the plumbing pool piping was conducted on January 16, 1997, and approved without comment. An inspection of the electrical pool deck bonding was conducted on January 27, 1997, and disapproved with the comment that all metal within 5 feet of the water must be bonded. An inspection of the structural pool deck steel was conducted on January 27, 1997, and disapproved with the comment that the item was not ready for inspection because the form boards were not completed. The electrical pool deck bonding was inspected on February 3, 1997, and approved without comment. The structural pool deck steel was inspected on February 4, 1997, and approved without comment. Challenger Pools worked on Mr. Casadona's pool from November 1996 through March 1997, when Challenger Pools applied the plaster to the pool and filled the pool with water. Once the pool was filled, Mr. Casadona began using the pool. Because Mr. Casadona had not installed the fence when Challenger Pools plastered the pool and filled it with water, Challenger Pools created a temporary enclosure for the pool by surrounding the pool with an orange plastic barrier. A plumbing pool final inspection was conducted on April 15, 1997, and disapproved because no approved plans or permit cards were available on-site. An electrical pool final inspection was conducted on April 15, 1997, and disapproved with the comment that no approved plans or permit cards were available on the site. Between April 1997 and October 1997, Challenger Pools corrected the violations noted on the inspection reports and made several service calls to work on Mr. Casadona's pool. By October 1997, Mr. Casadona had installed the required fence, but the gate was not in compliance with the South Florida Building Code. Challenger Pools requested a replacement set of plans for Mr. Casadona's pool on October 3, 1997, and they were provided on October 7, 1997. A plumbing pool final inspection was conducted on October 8, 1997. The work was disapproved because the pool's main drain was missing one screw. On October 8, 1997, an electrical pool final inspection was conducted. The electrical work was disapproved with seven comments identifying violations of the National Electric Code, as follows: NEC 110-3B Listed and labeled (insulate unused lead) NEC 680-22(a)-(l) Bond all metal within 5' x 12' (must see bond at handrail) NEC 110-16(a) Working clearance at service and controller NEC 680-20-B-1 Must see potting compound (5) NEC 680-6(A)(2)+(3)+(1), Receptacle (B)-(1), Light (6) NEC 680-10 UG. wiring not permitted within 5' of pool (8) [sic] Speaker wire not approved Item (1) refers to insulating the unused leads on the pool light. Item (2) refers to the lack or apparent lack of bonding on a handrail installed in the pool deck. Item (3) refers to the requirement that there be sufficient working clearance in front of the pump controller, which is a time switch transformer; with respect to this item, a hedge had been planted in front of the pool pump and filter by someone other than Challenger Pools, the shrubs blocked access to the pump controller, and Mr. Casadona refused to move the shrubs. Item (4) refers to the requirement that potting compound be used in the wet light niche in the pool to prevent the chemicals in the water from corroding the ground bonding connection; with respect to this item, Richard Boyette, a licensed professional engineer, certified in a letter to the Town of Davie dated April 3, 1998, that potting compound had been properly placed in the lighting niches in the pool. Item (6) refers to wiring being installed within 5 feet of the pool. Item "(8)" refers to speaker wires that are not allowed in the pool area. With respect to items (6) and "(8)", the violations were not the responsibility of Challenger Pools because they related to wiring for Malibu lights and two speakers installed by someone other than Challenger Pools. A structural pool deck final inspection was conducted on October 8, 1997, and approved without comment. A structural pool steel inspection was conducted on October 8, 1997, and disapproved with the comment that the pool had been completed without a pool steel inspection. In a letter dated April 3, 1998, Richard Boyette, a licensed professional engineer, certified to the Town of Davie that the pool steel had been properly placed according to the permit plans. A structural fence final inspection was conducted on October 8, 1997, and disapproved with the comment that "all fences and gates must be 5' high for yards with pools." The fence contractor was identified in the inspection report as Cercas Isla - Island Fence. Challenger Pools did not call for any inspections on Mr. Casadona's pool after it corrected the deficiencies noted in the October 1997 inspection reports until January 1999 because Mr. Casadona did not correct the violations for which he was responsible, that is, the fence gate height, the shrubs in front of the pool pump, and the electrical wires for the Malibu lights and speakers. Mr. Casadona was aware of these violations as a result of the October 8, 1997, inspection reports. Mr. Casadona and Challenger Pools' personnel were in regular contact during the October 1997 to January 1999 hiatus. Challenger Pools repeatedly asked Mr. Casadona to correct the fence gate height so that a structural pool final inspection could be approved and to remedy the electrical violations for which he was responsible. Challenger Pools let the situation remain unresolved because, on the basis of conversations Challenger Pools' personnel had with Mr. Casadona, there was no reason to believe that Mr. Casadona would not cooperate and correct the deficiencies. As of January 1999, Mr. Casadona had not made the required corrections. He did, however, file a complaint with the Department. At that time, Challenger Pools' attorney advised the company to finish Mr. Casadona's pool and close out the permit. Based on this advice, Challenger Pools renewed the permits and called for the final inspections. A plumbing pool final inspection was conducted on January 25, 1999, and approved without comment. A structural fence final inspection was conducted on January 25, 1999, and disapproved with the comment that "[t]here is no reference to a fence anywhere in the pool plans. The front gate is not self closing, self latching and is about 6" from being the 5' heighth [sic] requirement." An electrical pool final inspection was conducted on March 9, 1999, and disapproved with the comment that "working clearance violated at pump controller." The electrical final inspection was disapproved because Mr. Casadona would not remove the shrubs he had planted in front of the pool pump. An electrical pool final inspection was conducted on March 22, 1999, and approved, but the inspection report contained the comment that "working clearance violated at pump controller." A structural pool deck final was conducted on March 24, 1999, and approved with a comment that it had already been approved by another inspector. A structural fence final inspection was conducted on March 24, 1999, and disapproved with the comment that the fence was "not ready[;] the gate and latch are not 5' high." A structural fence final inspection was conducted on March 26, 1999, and rejected because the gate was not 5 feet high and was not self-closing and self-latching, as required by ordinance. The inspector also noted that no plan or permit for the fence was posted on the property and that no one was at home at the time of the inspection. A structural pool steel inspection was conducted on March 31, 1999, and disapproved because no one was at home and neither the plans nor the permit cards were posted. The inspector noted, however, that the pool was completed. In a letter to the Town of Davie dated February 18, 1999, and received by the Town of Davie on April 12, 1999, Mr. Boyette stated that the "steel and main drain inspection was bypassed due to a lack of communication on the above referenced pool. However, steel and main drain were in per code." An electrical pool final inspection was conducted on April 14, 1999, and disapproved with the comments "disconnect required for pump motor ahead of controller" and "unused transformer tap to be insulated at connection end." These were two items that the electrical inspector did not catch during the March 22, 1999, inspection. A structural pool final inspection was conducted on April 19, 1999, and was approved with the comments that the engineer's letter should be consulted regarding the missed pool steel inspection. A note was made in the report of the structural pool final inspection conducted on April 19, 1999, stating "Fence Final" with the comment that the fence and wall and existing front gate were 5 feet high and self-closing and self-latching. The permit for Mr. Casadona's pool was closed out by the Town of Davie Building Division on April 19, 1999, when the structural pool final inspection was approved. After the inspections conducted in October 1997, Challenger Pools corrected the violations noted in the inspection reports for which it was responsible. Challenger Pools did not do any work on Mr. Casadona's pool after it corrected the violations noted in the October 1997 inspection reports because it considered its work on the pool complete. The violations noted in the inspection reports for Mr. Casadona's pool were not unusual for the industry and were relatively minor. Challenger Pools corrected all of the violations and deficiencies noted in the inspection reports for Mr. Casadona's pool. The evidence presented by the Department is not sufficient to establish with the requisite degree of certainty that Challenger Pools failed to work on Mr. Casadona's pool for 90 consecutive days during the period from March 1997 until October 1997. However, the evidence presented is sufficient to establish with the requisite degree of certainty that Challenger Pools failed to work on Mr. Casadona's pool for 90 consecutive days during the period from October 1997 until January 1999. Challenger Pools could have done more to encourage Mr. Casadona to correct the height of his fence gate, remove the shrubs from around the pump controller, and remove the prohibited electrical wiring around the pool. Nonetheless, Challenger Pools had just cause to cease work on Mr. Casadona's pool because Challenger Pools could have reasonably concluded that its work on the pool was completed and that the only things remaining to be corrected were items for which Mr. Casadona was responsible. All of the violations noted on the inspection reports from January 1999 through April 1999 were the responsibility of Mr. Casadona with the exception of two minor code violations noted in the electrical pool final inspection conducted April 14, 1999, which violations were corrected by Challenger Pools prior to April 19, 1999. The evidence presented by the Department is not sufficient to establish with the requisite degree of certainty that the work Challenger Pools did on Mr. Casadona's pool was below industry standards. 4/ The evidence presented by the Department is sufficient to establish with the requisite degree of certainty that Challenger Pools commenced construction on Mr. Casadona's pool before the Town of Davie issued a building permit. The evidence presented by the Department is not sufficient, however, to establish with the requisite degree of certainty that Challenger Pools worked on Mr. Casadona's pool without having obtained the proper inspections. The inspection history establishes that, notwithstanding the notations on subsequent inspection reports, both the pool main drain and the pool steel were approved on January 3, 1997, and January 6, 1997, respectively. In addition, Challenger Pools called for final inspections of the plumbing, electric, and structural components of the pool on October 8, 1997, and again in January 1999, and closed out the permit on April 19, 1999. DOAH Case No. 99-2655 - Jameel Quadri On August 15, 1995, Challenger Pools entered into a Swimming Pool Construction Agreement with Jameel Quadri for construction of a residential swimming pool and spa at 239 Landings Boulevard, Fort Lauderdale, Florida. The full contract price was $12,240.00. Mr. Quadri was building a house on the property, and the agreement between Challenger Pools and Mr. Quadri provided that construction of the pool would not start until construction on the new house was completed. On October 3, 1996, Challenger Pools and Mr. Quadri entered into a contract addendum to the agreement that provided for the addition of brick pavers, a screen enclosure, and electrical work for the screen enclosure. The price of the additional items was $7,860.00. Mr. Quadri made the final payment on the pool agreement and addendum in April 1997. The applications for the building, screen enclosure, plumbing, and electrical permits for Mr. Quadri's swimming pool and spa were received by the Broward County Building and Permitting Department on October 15, 1996, and the permits were issued on October 29, 1996. The building, screen enclosure, and plumbing permits were issued to Challenger Pools as the contractor; and the electrical permit was issued to Specialty Device Installers. Even so, Challenger Pools remained responsible for the electrical work on the pool because it was included in the agreement. The permits were based on the plans for construction submitted with the permit applications, including the plans for the spa and the pool deck. Challenger Pools began construction on Mr. Quadri's pool on October 25, 1996, when the pool was excavated. A plumbing pool and spa main drain inspection was conducted on October 31, 1996, and was disapproved because the work was not ready for inspection and no safety railing had been installed around the excavation. An electrical pool grounding inspection was conducted on October 31, 1996, and disapproved for several reasons. A structural pool steel inspection was conducted on October 31, 1996, and disapproved for several reasons. The plumbing pool main drain was inspected on November 15, 1996, and disapproved because no Notice of Commencement had been recorded and because the safety fence was not completely around the pool. The electrical pool grounding was inspected and approved on November 15, 1996. The structural pool steel was inspected on November 15, 1996, and disapproved because of unsafe conditions, with the comment that safeguards were required. The plumbing pool and spa main drains were inspected on November 20 1996, and disapproved because the pool and spa main drains had only 38 and 33 pounds of pressure, respectively, when the code requires 40 pounds. The plumbing pool and spa main drains were inspected and approved on November 26, 1996. The structural pool steel was inspected on November 26, 1996, and approved. A plumbing pool piping inspection was conducted on December 9, 1996, and disapproved because the piping was not properly bedded, the dirt on the job site was not proper clean fill, and the piping was "within the angle of repose." The plumbing pool piping was inspected on December 20, 1996, and disapproved because the piping was not properly bedded. The plumbing pool piping was inspected and approved on December 24, 1996. An electrical pool deck grounding inspection was conducted on February 20, 1997, and disapproved for several reasons. A structural pool deck inspection was conducted on February 20, 1997, and disapproved for several reasons. The electrical pool deck grounding was inspected and approved on February 28, 1997. The structural pool deck was inspected and approved on February 28, 1997. Challenger Pools worked steadily on the pool until it was plastered on April 21, 1997, and filled with water. In April and May 1997, Challenger Pools received several telephone calls from Mr. Quadri regarding problems with his pool. In May 1997, Mr. Quadri called an attorney and asked that the attorney write a letter to Challenger Pools regarding what Mr. Quadri perceived were problems with the pool construction. In a letter dated May 22, 1997, Mr. Quadri's attorney identified the problems as follows: The deck area is not level, causing the pavers to break. The vacuum system has never been delivered or installed. The underwater pool light is dangling from its fixture and has exposed wires sitting in the water. The spa and jets do not work. The waterfall does not work. There are open and exposed wires at the pump. One of your trucks damaged the right side corner of Mr. Quadri's house and that condition has not been repaired. The ceramic underwater handles on the exterior of the spa are the wrong color. Mr. Quadri was promised white handles and you installed grey ones. The "exposed wires" mentioned in reference to the pool light were designed to be submerged in water, and the "exposed wires" at the pump were bonding wires running from the timer to the pump. Mr. Quadri's attorney notified Challenger Pools in the May 22, 1997, letter that, unless the defects identified in the letter were corrected within ten days of the date of the letter, Mr. Quadri would file suit against Challenger Pools for breach of contract. Challenger Pools did not respond to the letter of May 22, 1997, and no one from Challenger Pools came to the property to work on the pool and spa in response to that letter. In accordance with company policy, Challenger Pools ceased working on Mr. Quadri's pool and spa when it received the May 22, 1997, letter from Mr. Quadri's attorney threatening a lawsuit. In a letter dated August 14, 1997, Mr. Quadri's attorney sent Challenger Pools a letter demanding treble damages for theft arising out of the failure of Challenger Pools to complete Mr. Quadri's pool and spa after having been paid in full. In August 1997, at the request of Challenger Pools' attorney, Challenger Pools' vice president, Tom Camburn, and Challenger Pools' Fort Lauderdale field supervisor visited Mr. Quadri's property to view the pool and spa. Mr. Camburn and the field supervisor were in the vicinity of Mr. Quadri's pool for only 10 to 15 seconds before Mr. Quadri came out of the house and told them to leave the property, asserting that he was going to sue Challenger Pools. During those few seconds, Mr. Camburn observed that there was water in the pool and that some of the pavers forming the pool deck were sunken. He did not measure the pool and spa to determine if they were larger than represented in the original plans, although he did note that the pool and deck were larger than Challenger Pools usually builds. Challenger Pools' attorney responded to the August 14, 1997, letter with a letter dated August 20, 1997, advising Mr. Quadri's attorney of the outcome of the visit to Mr. Quadri's property and advising him that Challenger Pools would not go back to Mr. Quadri's property to inspect and repair any legitimate warranty complaints unless Mr. Quadri paid Challenger Pools a reasonable amount for the larger pool and spa. Challenger Pools based its contention that Mr. Quadri received a larger pool and spa than that specified in his contract on the fact that the invoice received for the pavers used in the pool deck was much higher than expected and showed that many more pavers were delivered to Mr. Quadri's property than were included in the original plans for Mr. Quadri's pool deck. The pavers were added to the contract in the addendum executed October 3, 1996, but neither the size of the deck nor the number of pavers was shown in the contract or in the addendum. 5/ In addition, no Change of Plans form was filed with the Broward County Building and Permitting Department indicating that there were any deviations from the original construction plans in the construction of Mr. Quadri's pool and spa, and no deviations from the original construction plans were noted by any of the building inspectors who conducted inspections of Mr. Quadri's pool and spa. In a notice dated August 27, 1997, Mr. Quadri was advised by the Broward County Building and Permitting Department that the permit for his pool and spa had expired. These notices are routinely sent by the Broward County Building and Permitting Department to both the property owner and the contractor when 150 days have elapsed without an inspection having been requested. The notice advises the property owner and the contractor that the permit will expire 30 days from the date of the notice. Challenger Pools did not receive a copy of the notice. Mr. Quadri renewed the permits on September 12, 1997, to avoid the penalties set forth in the notice; Challenger Pools continued to be named as contractor on the permits. A plumbing pool final inspection was conducted on September 15, 1997, and disapproved, with the comments that the main drain grid required two screws; 6/ the spa water level was low, possibly because of a leak; and the pavers were sinking around the spa. An electrical pool final inspection was conducted on September 15, 1997, which was disapproved, with comments that the pool screen was not bonded; the pool light was not in place; a bonding wire on the pool pump needed to be covered; and "[s]ealtite to pump motor in grass," meaning that the flexible electric conduit running from the timer/transformer subpanel to the pool pump was lying in the grass. No unsafe conditions were noted on the inspection report. A structural pool final inspection was conducted on September 15, 1997, and rejected, with the comments that there had been no final approval of the pool plumbing and electrical; that the paver deck was washed out in numerous places and needed to be repaired; that the riser at the rear steps was not to code; that the handholds were missing; and that the exterior wall of the raised spa needed finishing. Challenger Pools had installed ceramic underwater handholds on the pool, but Mr. Quadri was not satisfied with them because they were gray in color rather than white, the color he had selected. Challenger Pools did not remove the handholds. Neither Mr. Quadri nor Challenger Pools called for the inspections of Mr. Quadri's pool conducted on September 15, 1997. Rather, those inspections were apparently triggered by the renewal of the permits. Mr. Quadri did not file suit against Challenger Pools, but, by letter dated December 12, 1997, Mr. Quadri notified the Department that Challenger Pools had abandoned construction on his pool and spa and that the pool and spa still had numerous defects. After Challenger Pools received notice of the complaint filed by Mr. Quadri with the Department, Challenger Pools was advised by its attorney to obtain final inspections on Mr. Quadri's pool. An electrical pool final inspection was conducted on March 17, 1998, and disapproved because the screen enclosure needed to be bonded on both sides of the column. An electrical pool final inspection was conducted on March 27, 1998, and approved. A plumbing pool final inspection was conducted on October 9, 1998, and disapproved because the building permit had expired, the equipment was defective in that there was a cracked filter, and the equipment needed to be anchored. 7/ A structural pool final inspection was conducted on October 9, 1998, and disapproved because the permit had expired, and because of damaged sidewalks, no handholds, and a problem with a stairway. A plumbing pool final inspection was conducted on November 6, 1998, and disapproved because the permit card was not displayed on the site. Challenger Pools renewed the permits for Mr. Quadri's pool on November 16, 1998. A structural pool final inspection was conducted on November 20, 1998, and disapproved because the permit card was not at the site. A structural pool final inspection was conducted on November 30, 1998, and disapproved because of "previous inspections" and because the marcite was coming off and stucco was needed around the steps. A structural pool final inspection was conducted on December 3, 1998, and approved. A plumbing pool final inspection was conducted and approved on December 7, 1998. The Certificate of Occupancy for Mr. Quadri's swimming pool and spa was issued by the Broward County Building and Permitting Department on December 8, 1998. At the time of the final hearing, the pavers around Mr. Quadri's pool were uneven and sinking. Pavers are used for pool decks instead of concrete because concrete cracks as the earth beneath the deck settles. They are set on sand and are not grouted but, rather, are locked in with fine sand. It is not uncommon for paver decks to settle because strong rains can wash out the sand under the deck and cause erosion. As a result, pavers will sink or lift as the earth underneath shifts. The degree to which a paver deck shifts varies. Pressure washing a paver deck can cause the sand beneath the pavers to erode and shift, which causes the pavers to sink and lift. Mr. Quadri has cleaned the pavers around his pool and spa with a pressure cleaner at least every six months since it was installed. The evidence presented by the Department is sufficient to establish that Challenger Pools did not work on Mr. Quadri's pool between the end of April 1997 and March 1998 and between the end of March 1998 and October 1998. Challenger Pools may have been justified when it ceased work on Mr. Quadri's pool after the May 22, 1997, letter from Mr. Quadri's attorney threatening a lawsuit if the enumerated defects with the pool were not corrected. It was not justified, however, in failing to perform work on Mr. Quadri's pool after August 20, 1997; the evidence presented by Challenger Pool to justify the statement in the August 20, 1997, letter that it would not correct the problems with Mr. Quadri's pool until Mr. Quadri paid a "reasonable amount for the larger pool and spa he received" is not sufficient to establish that the pool and spa was, indeed, larger than the one for which Mr. Quadri contracted. In addition, Challenger Pools was not justified in failing to perform work on Mr. Quadri's pool between March 27, 1998, when the electrical pool final inspection was approved, and October 1998, because its attorney, in response to the December 1997 complaint to the Department, advised it to obtain final inspections and close out the permit. Accordingly, the evidence presented is sufficient to establish with the requisite degree of certainty that Challenger Pools failed to perform work on Mr. Quadri's pool for a period of 90 consecutive days without just cause. The evidence presented by the Department is not sufficient to establish with the requisite degree of certainty that the work Challenger Pools did on Mr. Quadri's pool was below minimum industry standards. 8/ The evidence presented by the Department is sufficient to establish with the requisite degree of certainty that Challenger Pools began excavating Mr. Quadri's pool after it applied for the necessary permits but before they were issued. The Department presented no evidence to establish that Challenger Pools proceeded with work on Mr. Quadri's pool without receiving the required inspections. In addition, Challenger Pools called for final inspections of the plumbing, electric, and structural components of the pool and closed out the permit on April 19, 1999. As of October 6, 1999, the Department had expended $1,088.47 in investigative costs and $1,307.47 in prosecutorial costs with respect to Mr. Quadri's complaint.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED the Construction Industry Licensing Board enter a final order: Finding that Challenger Pools violated Section 489.129(1)(k), Florida Statutes (1997), in DOAH Case No. 98-3713 and DOAH Case No. 99-2655; Dismissing Count II of the Administrative Complaint in DOAH Case No. 98-3713; Dismissing the Administrative Complaint in DOAH Case No. 99-2654; Dismissing Counts II and III of the Administrative Complaint in DOAH Case No. 99-2655; and Imposing the following penalties on Bruce E. Esquinaldo, Jr., as qualifier of Challenger Pools: Assessing an administrative fine in the amount of $2,500.00 in DOAH Case No. 98-3713 and in DOAH Case No. 99-2655 for the violations of Section 489.129(1)(k), Florida Statutes (1997), for a total administrative fine of $5,000.00; Placing Mr. Esquinaldo's license on probation for a period of one year, subject to such terms and conditions as the Board may impose; and Assessing the costs of investigation and prosecution attributable to the violations of Section 489.129(1)(k), Florida Statutes (1997), in DOAH Case No. 98-3713 and DOAH Case No. 99- 2655. DONE AND ENTERED this 27th day of June, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of June, 2000.
Findings Of Fact The parties stipulated that Petitioner's Exhibit number 1, which is the Florida Construction Industry Licensing Board official records as they relate to Millard P. Hill, Jr., should be received into evidence. The parties noted further that there is little dispute as to facts, however, the Respondent contends that there is no diversion of funds based on the facts of this case. On June 10, Respondent advised Petitioner that he wished to qualify Master Pools, a corporation which he had applied to Petitioner to qualify as the name under which his pool contracting would be done to reflect the name H. B. Patten, Inc. as the name under which said contracting would be done. Petitioner changed its records to show this change. On July 12, Respondent entered into a contract with Manuel and Anna Bueno for a pool to be built at 6960 Northwest 4th Place, Margate, Florida, for a sum of $5,665. See Petitioner's Exhibit number 2 received into evidence and made a part hereof by reference. Anna Bueno testified that a hole was dug and tar paper and steel bars were erected in the hole and the work was abandoned thereafter. Prior to abandonment, the Bueno's paid approximately $4,100 to Patten Pools. To complete the construction, the Bueno's used Hallmark Pools to finish the pool which required an additional sum of approximately $5,000. As can be seen, this is approximately $3,300 over and above the contract price. The evidence also reveals that Patten Pools, Inc., through Millard P. Hill, applied for and obtained a permit for the construction of the pool for the Bueno's on August 5. See Petitioner's Exhibit number 3, received into evidence and made a part hereof by reference. On April 24, Mr. and Mrs. Edward Eskie entered a contract with Respondent for the erection of a swimming pool on their property located at 1525 Southeast 14th Court, Deerfield Beach, Florida for $6,786.00. See Petitioner's Exhibit number 4 received in evidence and made a part hereof by reference. Mr. Eskie testified that the excavation for the pool began on May 20, and on June 2 gunite services were complete. On July 9, he received a letter from Crockett- Bradley, Inc. a gunite subcontractor, indicating that it was filing a lien for $1,312 against the Eskie's property for services performed. The building permit for the Eskie project was obtained by Respondent on June 10. See Petitioner's Exhibit number 7 incorporated herein by reference. Edward Eskie paid Respondent approximately $4,778 and $1,312 was paid to Crockett-Bradley, Inc. to satisfy the lien which was placed against their property. The Eskie's completed their pool by payment of an amount in excess of $4,000 to another pool contracting firm. Prior to completing the pool and after the Respondent abandoned the project, Edward Eskie made numerous attempts to contract Respondent by phone to no avail. On June 27, Respondent entered a contract with Orlando Gonzalez for a pool to be built at his residence located at 353 Northwest 22nd Street, Boca Raton, Florida for $9,000.00. See Petitioner's Exhibit number 8 which was received and made a part hereof by reference. Orlando Gonzalez paid Respondent $3,600 through his bank toward the contract price. For that payment, Respondent dug a hole and the project was abandoned. After work was abandoned, Gonzalez made repeated attempts to contact Respondent to no avail. To complete the project, he paid another contractor approximately $6,000. On April 18, Respondent entered into a contract with Howard and Sheila Siclari for a pool to be built at their home located at 7812 Northwest 67th Avenue, Tamarac, Florida, for the sum of $4,280. To commence the construction, Respondent obtained a building permit on June 18, 1975. See Petitioner's Exhibits number 9 and number 10 received in evidence and made a part hereof by reference. The Siclari's paid Respondent $3,456.75. Thereafter they completed the work which cost them an additional $2,500 and they did most of the work themselves. James T. Anglen, a pool salesman for Patten Pools testified that he was initially employed by Master Pools until June, 1975. A reference to Petitioner's Exhibit number 1 indicates that Master Pools registered as Brian Sales Corporation as the first entity that Respondent registered with Petitioner on January 1, 1974. He was a superintendent of Patten Pools in June, 1975 when he commenced employment with Patten. He acknowledged that he received money from the Bueno's which was transmitted to Patten Pools. He also acknowledged that the Bueno's were probably hurt most of all the complaining parties in this case. Respondent discovered that its cash flow was short approximately $40,000 to $50,000 and that that amount in checks were floating with insufficient funds to cover them. He commenced efforts to try to straighten out the firms cash flow and that for a while the bank worked along with him. Anglen also acknowledged the abandonment of the Gonzalez project. He further acknowledged that monies received from projects were used to cover deficiencies on other projects to continue Respondent's operations.
Findings Of Fact Based on the evidence presented, the following facts were found: At all times pertinent to this case, Respondent held two active contractor's licenses issued by the State of Florida, RP 0033354 and CP 015029. Respondent's current address is 1316 Hoffner Avenue, Orlando, Florida 32809. At all times pertinent to this case, Respondent owned the firm Family Pools and did business as a pool contractor under that name. At no time did Respondent ever qualify his firm, under whose name he did business, with the Florida Construction Industry Licensing Board (CILB). On some date not specified, in June, 1980, Alphonse J. and Pauline L. Rodier contracted with Family Pools to build a pool at their residence at 601 Michigan Avenue, Englewood, Sarasota County, Florida for a price of 6,700. The contract was signed by Respondent for Family Pools. The pool price was to include a screened enclosure and deck, and the entire package was to be completed by July 4, 1980. The pool was paid for by two checks from Coast Federal Sayings and Loan Association in Sarasota from the proceeds of a home improvement loan and by a final check in the amount of $900 from the Rodiers, direct, on October 13, 1980. Respondent subcontracted the pool enclosure to Climatrol Screen Company of Enqlewood, Florida, for $2,065 but failed to pay this subcontractor. As a result, on November 26, 1980, Climatrol filed a lien against Rodier's property which was released only when the Rodiers paid an additional $790 which had not been satisfied by the Respondent. Respondent had satisfied part of the debt to Climatrol by relinquishing title to a truck he owned. On July 3, 1980, Family Pools contracted with Elmer J. and Carla T. Taylor, of Bunnell, Florida, to build an above-ground pool on their property for $4,800.00. The pool was to have a one year warranty against defective parts and a 20-year prorated replacement policy. According to the contract, the pool price included the pump, liner, filter, and walls, along with all other parts. The pool was constructed by employees of Family Pools about three or four weeks after the contract was signed. Not long after the pool was completed and filled, Mr. Taylor noticed that the vinyl liner was protruding out beneath the bottom of the metal retaining wall. His calls to Family Pools were never answered by Respondent with whom he asked to talk and repair work on this problem was not accomplished by the Respondent or Family Pools. Mr. Taylor had to do the work himself and Family Pools would not honor the warranty. Respondent offers the completion certificate executed by the Taylors on August 21, 1980,as evidence the pool was installed properly and the Taylors were satisfied. Mr. Taylor indicates he signed that certificate in blank under pressure from Respondent's agent, who cajoled him into doing it on the basis that if he did not, Family Pools could not be paid by the finance company under the installment sales contract. Also, during the period of the one year warranty, the pool pump burned out. Mr. Taylor had to replace that and pay for it himself, as the warranty was not honored. Respondent contends only a 90-day warranty on the pump, but that appears nowhere in the contract, which, in its description of the pool covered by the one year warranty, includes the pump. On August 29, 1980, Family Pools contracted with Janice Conover to build a swimming pool at her home in Venice, Florida for $4,780. The pool was to be completed approximately 30 days after excavation at the site. Between August 29, 1980, and December, 1980, Ms. Conover paid Family Pools a total of $4,741 by checks which were endorsed by "P. Vescera d/b/a Family Pools" or "Pasquale M. Vescera." On October 2, 1980, Respondent pulled a permit No. 7330- N from the Sarasota County Building Department, in his own name, to construct Ms. Conover's pool. In February, 1981, when the pool was only about fifty percent complete, Respondent ceased work on Ms. Conover's pool without giving her any notice or reason therefor. When Respondent stopped work, he had only dug the hole for the pool. The liner had been delivered but was not installed. The braces were there but not affixed, notwithstanding Ms. Conover had paid almost in full for the pool. As a result, she contracted with Richard Thompson, Respondent's former employee, to finish the work Respondent had started because at this point she could not find the Respondent. Thompson installed the brackets, the liner, and the deck. She had to pay extra for the pump, the chemicals, and the sweep--all of which, except for the sweep, she had paid for when she paid Respondent's price. Respondent never returned to complete Ms. Conover's pool. On July 7, 1980, Family Pools contracted with Robert A. and Florence L. Peipher to build a pool at their property in Port Charlotte, Florida, for a price of $6,900. Between July 7 and November 28, 1980, the Peiphers paid Family Pools, by checks, the sum of $6,905. All checks-were endorsed for deposit, "P. Vescera d/b/a Family Pools." The pool price was to include a screened pool enclosure and in September 1980, Family Pools contracted with Climatrol to build the screened enclosure for Peipher's pool for $1,807. Respondent and Family Pools failed to pay Climatrol for the enclosure and as a result, Climatrol filed a lien against the Peipher's property for $1,807 which was satisfied on March 9, 1981, by the Peiphers who paid Climatrol the amount owed. On March 2, 1981, the Peiphers filed a complaint against Respondent with the Contractor License Division of the Charlotte County Building Department because of Respondent's failure to pay Climatrol and the resultant cost to them. As a result of this complaint and the subsequent investigation into the allegations, the matter was referred to the Charlotte County Building Board which, at its meeting on May 7, 1981, after notice to Respondent, voted to revoke Respondent's permit privileges in Charlotte County until he made restitution to the Peiphers and to notify the State of Respondent's actions requesting state action against his license. Respondent suffered severe financial setbacks just about the time of these incidents. He was hospitalized for a period of five or six weeks and upon his return to his business found that he had been "robbed" of approximately $50,000 worth of fully paid for inventory. When he reported the shortage to the local law enforcement officials, they told him that since there was no evidence of a breaking in, they could do nothing about it. In addition, he could not recover from his insurance company for the same reason. There was no evidence other than Respondent's sworn testimony that there was a shortage or that he reported the loss to either agency. Respondent has been in the pool business in Florida for five years and in New Jersey for 32 years before that. He feels the cause of his problem is the fact that he trusted the people who worked for him who took advantage of him. During the entire period of time he was in business in Florida he took no money from the company for his personal use, living instead on income from a mortgage he owned in New Jersey. He subsequently filed for bankruptcy on March 9, 1981. The $15,000 in current accounts receivable he had on the books at that time was utilized in the bankruptcy proceeding to pay creditors. He got-none of it. He is now working in Orlando, Florida, for a pool rehabilitation company owned by his wife and her father. Respondent alleges that on July 15, 1980, he paid Richard Thompson $1,100 to complete work started on several pools, including that of Ms. Conover. Review of the prior findings of fact, however, shows that the contract with Ms. Conover was not entered into until approximately 45 days after Respondent supposedly made this payment to cover the work left undone on her pool. In light of that development, I find his contention completely without merit or basis in fact. Respondent admits that people were hurt as a result of his actions and he regrets this. However, he claims these few incidents are insignificant when compared with the over 500 satisfied customers he alleges he has served over the years. Finally, Respondent contends that early in 1980, after being advised that he had passed the test to be a certified pool contractor, he wrote to Petitioner and, after advising how he was registered and doing business, asked if he needed to make any changes in license registration. He did in fact do this and received no reply. He thereafter assumed he was acting correctly in that regard and that appears to be a justified assumption.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's license as a contractor be suspended for two years and that he be assessed an administrative fine of $500. RECOMMENDED this 16th day of May, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Pasquale M. Vescera 1316 Hoffner Avenue Orlando, Florida 32809 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue Whether the state certified pool construction license number CP C008904 and the state certified general contractor's license number CG C002481 of Joaquin Vazquez should be revoked.
Findings Of Fact Division A of the Construction Trade Qualifying Board held a hearing on September 15, 1976, pertaining to ten (10) charges of violating the Dade County building code against Respondent Joaquin Vazquez. At the completion of this formal hearing, Joaquin Vazquez was found guilty of eight (8) of the ten (10) charges. Charles W. Leavitt, Jr., Clerk of the Construction Trades Qualifying Board In Metropolitan Dade County, Florida, identified the minutes of the Board Meeting held on September 15, together with the charges as set forth in letters dated May 10, 1976, and August 19, 1976. Copies of these instruments were introduced into evidence without objection. The Respondent did not deny the charges at the hearing and had not appealed the finding of guilt of eight (8) of the ten (10) charges at the conclusion of the formal hearing on September 15, 1976. Briefly the charges (spanning the term from July 1, 1975 to June 29, 1976), finds and penalties are as follows: Charge 1.: Allowing permit to be applied for and taken out in Respondent's name in order for Angela J. Stevens and/or Sparkle Blue Pools to construct a swimming pool. Found guilty - letter of reprimand. Charge 3.: Similar to Charge 1 - found guilty - certificate to be suspended for one (1) year. Charge 4.: Failure to supervise, direct and control, the construction or installation of a swimming pool taken out in Respondent's name. Found guilty - one (1) year suspension to run concurrent with any other suspensions. Charge 5.: Similar to Charge 1 - found guilty - ninety (90) day concurrent suspension. Charge 6.: Similar to Charge 4 - found guilty - ninety (90) day suspension. Charge 7.: Similar to Charge 1 - found guilty - revo- cation of certificates. Charge 8.: Similar to Charge 4 - found guilty - both certificates be revoked. Charge 10.: Allowing a permit to be applied for and taken out in Respondent's name in order for Jack Goodman and/or Precision Engineering, Inc., to construct a swimming pool. Found guilty - letter of reprimand. An Administrative Complaint was filed by the Petitioner through its executive director on November 12, 1976, citing the hearing and the charges and the finding of guilt of Respondent and stating that the results of said formal hearing show a violation of Florida Statute 468.112(2)(a), willful or deliberate disregard and violation of applicable building codes or laws of the state or any municipality, cities or counties thereof. Therefore, the Board seeks to revoke the state certified pool contractors license number CP C008904 and state certified general contractors license number CG C002481 of Joaquin Vazquez, the Respondent. The Respondent did not deny the charges but presented an attack on the character and veracity of the witness, Angela Stevens, in four (4) of the charges against him. He cited the witness Angela Stevens' failure to abide by probationary requirements imposed for her acting as a contractor without a license. Furthermore, the Respondent offered his own and a witness, Mr. Gonzalez's, testimony to the fact that he was solicitated by Angela Stevens to make false testimony to the effect that Angela Stevens was an employee of his when in fact she had never been. The charges against the Respondent were brought subsequent to the charges brought against the witness Angela Stevens. The Respondent contends that the affidavits and testimony of Angela Stevens were no more than self serving statements made in her own behalf in an attempt to cover up her criminal intentions and that the charges and finding of guilt of the Respondent were based largely on the affidavit and testimony of said witness. Respondent further offered a medical report indicating that he was unable to work in the month of May, 1975, and further his testimony was that he was out of the country in mid June and July, 1975, in order to recuperate from high blood pressure attacks. Petitioner contends: the undisputed evidence presented in the finding of guilt of the charges involved in the prior hearing are sufficient to find Respondent guilty of violating Section 468.112(2)(a), Florida Statutes, and that Respondent's license should be revoked. Respondent contends: the witness against him was self serving and an attempt to cover up her criminal intentions; that he in fact supervised some of the jobs he was found guilty of not supervising; that he was ill some of the time and did not willfully violate the code. The proposed facts and conclusions of the parties submitted after the hearing herein have been considered in this Recommended Order.
Recommendation Suspend the licenses, No. CP C008904 and No. CG C002481, of the Respondent Joaquin Vazquez for a period not to exceed six (6) months. DONE and ORDERED this 31st day of May, 1977, in Tallahassee, Florida. DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: David Linn, Esquire Post Office Box 1386 Tallahassee, Florida 32302 Jerome S. Reisman, Esquire 1515 Northwest 7th Street, #106 Miami Florida 33125 J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211
Findings Of Fact On December 30, 1975, Collier County adopted Ordinance No. 75-57 which required, among other things, swimming pool contractors to be licensed by the county or state after establishing their competency. Prior to this time swimming pool contractors did not need certificates of competency to construct swimming pools. Anthony Schmidt had been engaged in the manufacture and installation of swimming pools for several years before opening a swimming pool business in Collier County. On April 22, 1976 Schmidt entered into a contract (Exhibit 1) to construct a swimming pool for John Dottore in Naples, Florida. Shortly thereafter Schmidt was issued a violation by an investigator of the FCILB for starting a different pool without a license. Schmidt contacted friends to ascertain who he could get to "pull" the permit needed to construct Dottore's pool, and was subsequently introduced to George C. Moyant, Respondent, a resident of Hollywood, Florida. He was introduced to Moyant at Moyant's house at a meeting arranged by mutual friends. The alleged purpose of this meeting was special tutoring of Schmidt by Moyant to prepare Schmidt for the pool contractor's exam and no other subject was discussed at this meeting. No final arrangements for such tutoring were made. Respondent holds Pool Contractor's License # CP C009205 and General Contractor's License #CG C001828 issued by the FCILB. He is president of Allstate Construction College, Inc. and prepares applicants for the various examinations required for registration with the FCILB. Subsequent to the meeting at Moyant's house Schmidt contacted Moyant regarding Moyant pulling a permit for Schmidt to construct Dottore's pool, and on a subsequent visit by Moyant to Naples Moyant, in company with Schmidt, submitted an Application for Building Permit (Exhibit 4) prepared and signed by Schmidt, showing the contractor to be George C. Moyant, License #CP C009205. At the same time Collier County Permit (Exhibit 5) was issued to Moyant as contractor for the construction of a swimming pool for Dottore. Immediately thereafter, at the Collier County Courthouse parking lot Schmidt gave Moyant a check dated May 4, 1976 in the amount of $500. Moyant's testimony that the payment was an advance for tuition is not credible. Moyant admits that Schmidt called him around the first of May for help in getting a permit for the swimming pool for Dottore and that he, Moyant, was "very reluctant" but assented to come to Naples to help Schmidt out and in fact, pulled the permit. Moyant recognized that his actions were in violation of the laws unless "one does things correctly." He advised Schmidt that his brother or the mutual friend, both of whom have general contractor's licenses would act as his, Moyant's, agent "if any problems come up". Before Schmidt completed the pool an investigator for the FCILB became aware of the circumstances surrounding the issuance of the permit and the investigation and administrative complaint followed.