Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL A. ARGUELLES, 85-001293 (1985)
Division of Administrative Hearings, Florida Number: 85-001293 Latest Update: Oct. 01, 1985

Findings Of Fact At all times relevant hereto, Respondent, Daniel A. Arguelles, held certified general contractor license number CG C004252 issued by Petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. When the events herein occurred, he was qualified as an individual. He presently resides at 9455 Southwest 78th Street, Miami, Florida. Respondent's brother is J. Alejandro Arguelles. Alejandro holds an inactive contractor's license which has been delinquent since July, 1979. In June, 1984, Alejandro was contacted by an individual named Louis Taylor. Taylor told Alejandro that David Reynolds, who resided at 753 Northwest 116th Street, Miami, Florida, wished to add a room to his house. After meeting with Reynolds, Alejandro had plans for the addition prepared, provided an estimate for the job, and gave Reynolds a business card reflecting that he was a licensed general contractor. Reynolds and Alejandro then jointly executed a contract on July 26, 1985, wherein it was provided that A. Arguelles & Associates would construct the room addition for $19,000. The letterhead on which the contract was executed indicated that Alejandro was a general contractor. However, the entity "A. Arguelles & Associates" has never been qualified by any licensee to do construction work in the state. During all negotiations with Reynolds, Alejandro never mentioned that Daniel would be the contractor on the project although Alejandro did advise him that a general contractor would be required. All checks were made out to Alejandro, and Alejandro ordered all supplies and materials used on the project. In addition, Alejandro was at the job site on a regular basis. Prior to signing the contract on July 26, Daniel was approached by Alejandro and asked if he would be willing to act as contractor on the project. Daniel agreed, and thereafter pulled a job permit and used his license number on all pertinent documentation. Other than visiting the job site on a "couple" of occasions, he had no other contact with the project. He never met or had any contact with Reynolds. The actual amount of work done on the project by Alejandro and Daniel amounted to only $5,000.00 and consisted of constructing the foundation up to the tie beam. There is no evidence that this phase of the work was performed in a negligent or incompetent manner.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as set forth in the Conclusions of Law portion of this order, and that he be fined $500.00. DONE and ORDERED this 1st day of October, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of October, 1985. COPIES FURNISHED: Salvatore A. Carpino, Esquire 130 N. Monroe St. Tallahassee, FL 32301 Fred Roche, Secretary Dept. of Professional Regulation 130 N. Monroe St. Tallahassee, FL 32301 Nancy M. Snurkowski, Esquire 130 N. Monroe St. Tallahassee, FL 32301 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board P. O. Box 2 Jacksonville, FL 32201 Mr. Daniel A. Arguelles 9455 S.W. 78th Street Miami, FL 33173

Florida Laws (3) 120.57489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs LAWRENCE I. PAUL, III, 92-000193 (1992)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Jan. 13, 1992 Number: 92-000193 Latest Update: Apr. 09, 1993

The Issue Whether the Petitioner violated Section 489.129(1)(a), Florida Statutes, by obtaining licensure by fraud or misrepresentation.

Findings Of Fact The Petitioner is the state agency responsible for licensure of certified general contractors. The Respondent Lawrence I. Paul, III, ("Respondent") is a licensed general contractor, holding State of Florida licenses GC C046485 and CG CA46485. On or about December 12, 1988, the Respondent submitted his application to the Department of Professional Regulation seeking leave to take the examination for certification as a general contractor. The Respondent subsequently took and passed the certified general contractors examination. In his application, the Respondent states that he is qualified to take the examination by virtue of having four years of proven experience as a workman or foreman of which at least one year was as a foreman. On the experience verification form submitted to the DPR as part of his application the Respondent states that from January, 1977 to January, 1980, he had been employed as a construction workman and that from January 1980 to January 1981 he had been employed as a construction foreman. The application includes an experience verification form executed by the Respondent and Paula Wisnik, a New York licensed architect. The form indicates that the Respondent had experience in steel erection form work, masonry walls, concrete slabs, footings, site work, excavation, rebar, trusses, and floor and ceiling joists, in single family residences, strip stores and high rise condominiums ten stories and higher. The experience verification form executed by Ms. Wisnik and the Respondent states as follows: I have read the CANDIDATE INFORMATION BOOKLET and reviewed the experience requirements and understand that any false information provided on this form may subject the person(s) signing below to disciplinary action and possible loss of license. I understand that DIRECT KNOWLEDGE does NOT mean that I am relying on a statement from the applicant that he has met the requirements. Ms. Wisnik has no direct knowledge of the Applicant's experience or of the applicant personally. Her knowledge was based upon information provided to her by Peter Wendt, another licensed architect. The Respondent originally sought to have Mr. Wendt complete the experience verification form. Mr. Wendt forwarded the form to Ms. Wisnik and she subsequently signed the document. Mr. Wendt has no direct personal knowledge of the Respondent's experience as set forth on the experience verification form. Mr. Wendt did not meet the Respondent until the Respondent's move to Florida, which occurred subsequent to the period of employment identified in the application. The greater weight of the evidence establishes that at the time the application was completed, the Respondent did not have the claimed four years of proven experience as construction worker or foreman. The Respondent's application states that first he became employed in the construction trade in January, 1977. In fact, he became employed full time in late December, 1978, with Paul Brothers, Inc., a family owned fire restoration business in Philadelphia. He worked primarily as a salesman and estimator with Paul Brothers until June, 1982, a period of approximately three and one-half years. Although there were periods when the Respondent worked on- site, it was not his primary responsibility throughout the employment period.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order revoking the licensure of Lawrence I. Paul, III, as a certified general contractor, license numbers GC C046485 and CG CA46485. DONE and RECOMMENDED this 19th day of October, 1992, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October, 1992. APPENDIX TO CASE NO. 92-0193 The following constitute rulings on proposed findings of facts submitted by the parties. Petitioner The Petitioner's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 1. The proposed finding is modified to reflect that the Respondent did not hold the licenses prior to examination. Respondent The Respondent's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 5. Rejected, illogical and unsupported by evidence. 6-7. Rejected, not supported by credible and persuasive evidence. COPIES FURNISHED: Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Jack McRay, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Robert G. Harris, Esq. Senior Attorney Dept. of Professional Regulation 2295 Victoria Avenue #263 Fort Myers, Florida 33901 Timothy J. Murty, Esq. 1633 Periwinkle Way, Suite A Sanibel, Florida 33957 Wellington H. Meffert, II Chief Construction Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0750

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MICHAEL RADA, 89-000187 (1989)
Division of Administrative Hearings, Florida Number: 89-000187 Latest Update: Jul. 28, 1989

The Issue Whether the Respondent committed the offenses set forth in the administrative complaint filed in this case and, if so, what disciplinary action should be taken.

Findings Of Fact At all times material hereto, Respondent, Michael Rada was a certified general contractor, the qualifying agent for A-Team Remodeling and Design, Inc. and held license number CG C026705 of the Florida Construction Industry Licensing Board. On or around December 10, 1987, Mrs. Katherine Hill contracted with A- Team Plumbing, Inc. to renovate a bathroom in her home. A-Team Plumbing, Inc. is an entity separate and distinct from A-Team Remodeling and Design, Inc. and Mr. Rada was not associated with A-Team Plumbing, Inc. Following A-Team Plumbing, Inc.'s failure to complete the job, Mr. Rada, on behalf of A-Team Remodeling and Design, Inc. agreed with Mrs. Hill to re-do the job. Mr. Rada, as qualifying agent for A-Team Remodeling and Design, Inc., applied to the City of Plantation for the building permit on January 11, 1988, and it was issued on February 13, 1988. At the instruction of the City of Plantation, the job was gutted, and Mr. Rada began his work sometime in March, 1988. The job should have been completed in two to three weeks, but was not completed until May 6, 1988. During construction, Mr. Rada's work was erratic and at times dilatory. On several occasions, he made appointments to work on the job, necessitating Mrs. Hill's absence from her employment, and, then, he would not keep the appointments or even contact Mrs. Hill about his failure to report. In addition to having failed to complete the job in a timely manner, the proof demonstrated that when completed the work failed to conform to that standard existent in the community for similar work. Even after the final inspection, a hole remained in an adjoining closet wall, the base boards were not flush with the walls and "gop" hung down in one corner of the room. Mrs. Hill refused to pay for the job because of her dissatisfaction. As general contractor, Mr. Rada assumed responsibility for the completion of the job at the time of his initial visit to Mrs. Hill and his application for the building permit. By failing to complete the job in a workmanlike and timely manner, Mr. Rada's performance was incompetent and exemplified misconduct in the practice of contracting.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered imposing on Respondent an administrative fine of $750. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 28th day of July 1989. JANE C. HAYMAN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of July, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-187 Petitioner's proposed findings of fact are addressed as follows: Addressed in paragraph 1. Subordinate to the result reached. Addressed in paragraph 2. Subordinate to the result reached. Subordinate to the result reached. Subordinate to the result reached 2. Subordinate to the result reached. In part, subordinate to the result reached; in part, addressed in paragraph 3. Addressed in paragraph 3. Subordinate to the result reached. Addressed in paragraph 4. Addressed in paragraph 5. Addressed in paragraphs 3 and 4. In part, addressed in paragraphs 4 and 5; in part, subordinate to the result; in part, not supported by competent and substantial evidence. In part, subordinate to the result reached; in part, addressed in paragraphs 4 and 5. In part, subordinate to the result reached; in part addressed in paragraph 2. Subordinate to the result reached. COPIES FURNISHED: Elizabeth Alsobrook, Esquire Department of Professional Regulation Suite 60 1940 North Monroe Street Tallahassee, Florida 32399-0729 Michael Rada, pro se 4576 Northwest 16th Terrace Tamarac Lakes, Florida 33304 Fred Seely Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201 Kenneth E. Easley, Esquire Department of Professional Regulation 1940 North Monroe Street Suite 60 Tallahassee, Florida 32399-0792 =================================================================

Florida Laws (4) 120.57489.105489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs WILLIAM LEETE STONE, IV, 98-001922 (1998)
Division of Administrative Hearings, Florida Filed:Naples, Florida Apr. 22, 1998 Number: 98-001922 Latest Update: Nov. 23, 1998

The Issue The issue in this case is whether Respondent violated Section 489.129(1), Florida Statutes (1997) (hereinafter, "Florida Statutes"), by committing mismanagement or misconduct in the practice of contracting, causing financial harm to a customer, abandoning a construction project, and failing to satisfy a judgment against him.

Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a contractor pursuant to license number CB C019811. At all relevant times, Respondent was the qualifying agent for Gulf and Bay Sunrooms, Inc. ("Gulf"). As the qualifying agent, Respondent was responsible for all of Gulf's contracting activities in accordance with Section 489.1195, Florida Statutes. On August 23, 1995, Respondent and Gulf entered into a contract with Mr. H. Edward Dowling ("Dowling") to install a Four Seasons System 330 Sunroom in Dowling's residence at 3016 West 38th Street, Orlando, Florida. The contract price was $31,340. Dowling paid the first draw of $9,402 to Respondent and Gulf by check number 45016644. On October 27, 1995, Gulf deposited the check to its account. Respondent and Gulf never commenced work on the sunroom. Respondent and Gulf did not return the first draw to Dowling. Respondent and Gulf abandoned the project without just cause and without notice to Dowling. On June 19, 1997, the County Court of the Ninth Judicial Circuit entered a Default Final Judgment in Case No. CO97-3800. The default judgment was entered in the amount of $9,402 plus costs of $145. Neither Respondent nor Gulf have satisfied the judgment. Respondent has a discipline history in two other cases. In Petitioner's Case No. 96-7123, Respondent failed to pay a supplier for windows. In DOAH Case No. 96-5914, Respondent contracted to build a sunroom in a residence, accepted payment of $1,540.44 toward the contract price of $4,668.00, never commenced construction, and abandoned the project. In the first case, Respondent was found guilty of failing to satisfy a civil judgment, was fined, and was ordered to pay restitution. In the second case, Respondent was found guilty of abandonment, incompetency or misconduct, was fined, and was ordered to pay restitution, and his license was suspended until Respondent complied with the penalty imposed.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating Section 489.129(1), Florida Statutes, imposing administrative fines in the aggregate amount of $15,000.00, and revoking Respondent's license. DONE AND ENTERED this 10th day of August, 1998, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 1998. COPIES FURNISHED: Rodney Hurst, Executive Director Department of Business and Professional Regulation Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Paul F. Kirsch, Senior Attorney Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 William Leete Stone, IV, pro se 3386 Poinsettia Avenue Naples, Florida 34104

Florida Laws (2) 489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEPHEN J. BOROVINA, 77-001442 (1977)
Division of Administrative Hearings, Florida Number: 77-001442 Latest Update: Feb. 21, 1978

The Issue The Florida Construction Industry Licensing Board, Petitioner, seeks to revoke the registered contractor's license of Stephen J. Borovina, Respondent, based on allegations, which will be set forth in detail hereafter, that he engaged in conduct violative of Chapter 468, Florida Statutes. The issue presented is whether or not the Respondent aided or abetted and/or knowingly combined or conspired with Mr. Howard North, an uncertified or unregistered contractor, to evade the provisions of Chapter 468.112(2)(b), and (c), Florida Statutes, by allowing North to use his certificate of registration without having any active participation in the operations, management, or control of North's operations. Based on the testimony adduced during the hearing and the exhibits received into evidence, I make the following:

Findings Of Fact The Respondent is a certified general contractor who holds license no. CGC007016, which is current and active. On or about July 25, 1976, Mr. and Mrs. Julius Csobor entered into a contract with Mr. and Mrs. Howard North for the construction of a home in Martin County, Florida, for a total price of $35,990. Neither Mr. or Mrs. North are certified or registered contractors in the State of Florida. (Petitioner's Composite Exhibit #2). Respondent applied for and was issued a permit by the Martin County Building Department to construct a residence for the Csobors at the same address stipulated in the contract between the Csobors and the Norths, i.e., Northwest 16th Street, Palm Lake Park, Florida. (Petitioner's Composite Exhibit #1). Howard North, a licensed masonry contractor for approximately nine (9) years was contacted by the Csobors through a sales representative from a local real estate firm. It appears from the evidence that North had previously constructed a "spec" house which the local realtor had sold and thus put the Csobors in contact with Mr. North when they were shown the "spec" house built by North. Evidence reveals that North contacted Borovina who agreed to pull the permit "if he could get some work from the job and could supervise the project". Having reached an agreement on this point, North purchased the lot to build the home for the Csobors and he orally contracted with the Respondent to, among other things, pull the permit, supervise construction, layout the home and do trim and carpentry work. North paid Respondent approximately $200 to layout the home for the Csobors. By the time that North had poured the slab and erected the subfloor, the Csobors became dissatisfied with his (North's) work and demanded that he leave the project. According to North, Respondent checked the progress of construction periodically. Prior to this hearing, the Csobors had never dealt with Respondent in any manner whatsoever. According to Csobor, North held himself out as a reputable building contractor. A contractor is defined in relevant part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. . . . real estate for others. . . Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby recommended that the complaint filed herein be dismissed in its entirety. RECOMMENDED this 4th day of November, 1977, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 Stephen J. Borovina 2347 Southeast Monroe Street Stuart, Florida 33494 J. Hoskinson, Jr. Chief Investigator Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 STEPHEN J. BOROVINA, CG C007016, 2347 S. E. Monroe Street, Stuart, Florida 33494, Respondent. / This cause came before the FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD at its regular meeting on February 10, 1978. Respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did not appear The FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD on February 10, 1978, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded voted to revoke the certified general contractor's license of STEPHEN J. BOROVINA. It is therefore, ORDERED that the certification of respondent STEPHEN J. BOROVINA, Number CG C007016, be and is hereby revoked. Respondent is hereby notified that he has 30 days after the date of this final order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. DATED this 13th day of February, 1978. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President ================================================================= SECOND AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD STEPHEN J. BOROVINA, CG C007016, Respondent/Appellant, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner/Appellee. / This cause came before the Florida Construction Industry Licensing Board at its regular meeting on August 3, 1979. The respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did appear. The Florida Construction Industry Licensing Board, on August 3, 1979, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded, voted to revoke the certified general contractor's license of Stephen J. Borovina, No. CG C007016. On February 13, 1978, the certification of respondent, Stephen J. Borovina, No. CG C007016, was revoked by order of the Florida Construction Industry Licensing Board. On April 25, 1979, the District Court of Appeal of the State of Florida, Fourth District, in Case Number: 78-527, reversed the final order of the Florida Construction Industry Licensing Board. That Court remanded the above captioned case to the Board to further consider the matter and enter such order as it may be advised in conformity with Section 120.57(1)(b)(9), Florida Statutes (1977). In accordance with the decision of the Florida District Court of Appeal, Fourth District, the Board has reconsidered the above captioned matter and finds as follows: The Board rejects the recommended order as the agency's final order. The Board adopts the first paragraph of the hearing officer's finding of fact. The Board, however, rejects the findings of fact found in the second paragraph of the hearing officer's findings. The second paragraph states as follows: A contractor is defined in relevent(sic) part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. real estate for others...Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety. The findings of fact found in the above-quoted paragraph were not based upon competent substantial evidence. The competent substantial evidence supports a finding that the respondent, Stephen J. Borovina, did not supervise the project and that Borovina evaded the provisions of Chapter 468, Florida Statutes. The following evidence supports the Board's position: There was no written agreement entered into between Howard North and the respondent which indicated that the respondent was to supervise the construction of the Csobors' house (T- 14); It was conceded at the hearing that the only subcontractors or draftmen who worked on the Csobors' house were contracted solely by Howard North and they had no contract whatsoever with the respondent (T-19, 25); The respondent never advised or informed Mr. and Mrs. Csobor that he was the contractor on the job. (T-51); At all times during the act of construction of the house, Mr. and Mrs. Csobor were under the impression that Howard North was the contractor (T-44-51). It is, therefore, ORDERED: That the certification of respondent, Stephen J. Borovina, Number CG 0007016, be and is hereby revoked. Respondent is hereby notified that he has thirty (30) days after the date of the Final Order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. Dated this 3rd day of August, 1979. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President

Florida Laws (1) 120.57
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. TOMAS PEREZ, D/B/A LIFETIME CHEMICALS OF AMERICA, 79-002173 (1979)
Division of Administrative Hearings, Florida Number: 79-002173 Latest Update: Aug. 25, 1980

The Issue At issue herein is whether or not the Respondent/Licensee, Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Lifetime), engaged in conduct which will be set forth hereinafter in detail, which warrants the Florida Construction Industry Licensing Board (Board) to take disciplinary action respecting his license and to impose an administrative fine based on said alleged conduct.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Tomas Perez, d/b/a Lifetime Chemicals of America, Inc. (Respondent), is a certified general contractor who holds license No. CGCA 04170, which is active. On September 24, 1975, Mr. Perez used his license to qualify Lifetime Chemicals of America, Inc., as the entity through which he would conduct his business activities (Petitioner's Exhibit 1). On August 15, 1978, Lifetime Chemicals of America, Inc. , entered into an agreement with James Laughery of Fort Myers, Florida, for a franchise agreement to use Lifetime's license in the immediate area of Fort Myers, Florida (Petitioner's Exhibit 5). That agreement provides, among other things, that Respondent Lifetime authorized James Laughery to use its license in the Fort Myers area for a fee of $50.00 per job or $1,500.00. The agreement does not provide, nor was any evidence offered to establish that Respondent Perez played any supervisory or managing role in agent Laughery's contracting activities in the Fort Myers area. During October of 1978, Mr. Andrew Szarfran entered into an agreement with Respondent's agent, Laughery, to perform certain roofing repairs to his residence for the sum of $1,000.00. Mr. Szarfran paid Laughery $500.00 and Laughery abandoned the project prior to completion (Testimony of Szarfran and Petitioner's Composite Exhibit 4). Mr. Szarfran engaged the services of another contractor to complete the project. On May 17, 1979, the Lee County Construction Board reviewed a complaint filed against Respondent by the Szarfrans. Based on that review, the Lee County Construction Board revoked Respondent's licensing privileges in the county at its June, 1979, meeting (Petitioner's Exhibits 3 and 4 and testimony of witnesses Richard M. McDole and Maxine Allred, Administrative Director of Court Enforcement and Permit Clerk, respectively, for Lee County). On or about October 17, 1978, Respondent's agent, Laughery, also entered into an agreement with Mr. and Mrs. Arthur Swanson for the erection of aluminum siding to the exterior walls of their residence for a full price of $5,000.00. The Swansons gave Respondent's agent, Laughery, a downpayment of $2,500.00 and agent Laughery abandoned the project prior to the commencement of any work (Petitioner's Exhibits 7 and 8 and testimony of Mrs. Swanson). Richard Newmes, the chief inspector for building and zoning, Cafe Coral, Florida, testified that the Construction Industry Licensing Board for Cape Coral, Florida, revoked Respondent's contractor license on January 17, 1979, based on his violation of Cape Coral Code Section 5-1/2 - 21(J), to wit: "Failure to make good faulty workmanship or materials performed or installed to evade performance of the contract or specifications as agreed upon." (Petitioner's Exhibit 9.) On or about January 4, 1979, Lifetime Chemicals of America, Inc., became aware of its agent, James Laughery's mismanagement of funds and his failure to honor contractual obligations he had entered in the Fort Myers area. Respondent and its agent Laughery therefore entered into an agreement which rendered the franchise agreement between the parties null and void. Agent Laughery, in said agreement, promised to pay, from his commissions due, monies owed to Lifetime Chemicals, Inc., which apparently was brought about due to the restitution that Lifetime Chemicals had made to customers whom agent Laughery had defaulted. As mitigating evidence, it was noted that the Respondent, Tomas Perez, was not party to or familiar with the activities and/or difficulties that the designated agent for Lifetime Chemicals of America, Inc., James Laughery, was encountering in the Fort Myers vicinity before early January, 1979. As soon as Respondent became aware of Laughery's problems, steps were immediately taken to halt such acts insofar as they related to Respondent (Testimony of Tomas Perez and Michael Arfaras).

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law and the mitigating evidence which revealed that although the Petitioner is authorized and in fact holds the qualifier license of a registered entity responsible for the acts of its agents, in view of the undisputed evidence which reflects that neither Respondent Perez or Respondent Lifetime Chemicals of America, Inc., in any manner benefited from the acts of its agents and in fact attempted to thwart the illegal acts of its agent as soon as such became known, it is hereby RECOMMENDED: l. That the Respondent, Tomas Perez's Certified General Contractor's license, CGCA 04170, be placed on probation for a period of one (1) year. 2. That the Respondents, Tomas Perez and Lifetime Chemicals of America, Inc. , be issued a written letter of reprimand. RECOMMENDED this 24th day of April, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of April, 1980. COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 Tomas Perez 2395 West 12th Avenue Hialeah, Florida 33010 Michael Harold Arfaras 820 S.W. 20th Avenue Miami, Florida 33135 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 79-2173 THOMAS PEREZ, CGCA 04170 Respondent. /

Florida Laws (1) 120.57
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. W. BERT JONES, 76-002111 (1976)
Division of Administrative Hearings, Florida Number: 76-002111 Latest Update: Jun. 03, 1977

The Issue Whether the certified general contractor's license of W. Bert Jones should be revoked.

Findings Of Fact By an Administrative Complaint filed October 27, 1976, the Florida Construction Industry Licensing Board sought to revoke the general contractor's license of W. Bert Jones alleging that the Respondent contractor entered into a contract with Mrs. Barbara Loewe to renovate her home and to add a room onto the back of the house; that the Respondent contractor was paid in full the contract price but the job was not completed and there were numerous building code violations. Respondent requested an administrative hearing. Pursuant to written agreements entered into between the Respondent and Mrs. Barbara Loewe of Tampa, Florida, Respondent agreed to renovate Mrs. Loewe's home and to add a room onto the back of the house. Mrs. Loewe, either by paying the Respondent directly or paying material suppliers, paid the full contract price. In June or July of 1975 the Respondent left the job contracted for partially or wholly incompleted as follows: the ceiling of the kitchen and drywall were in complete and the kitchen was not painted; the guest bathroom was not trimmed; two back rooms were incomplete. Inasmuch as the ceiling was left undone, it was not trimmed, the drywall was incomplete, the doorways were left uninstalled, and the paneling was incomplete; the bathroom had no toilet, no sink and no trim on the tub; in the master bedroom the ceiling was left sagging, there was no insulation in ceiling or walls, the door was untrimmed, siding was left partially undone and the windows weren't trimmed; holes were left unrepaired around the pipes in the home. The sum of Five Thousand Dollars ($5,000) was paid by St. Paul Fire and Marine Insurance Company in full settlement of the claims arising under the general contractor's bond. Additional money, approximately Thirty-Five Hundred Dollars ($3,500), was spent by Mrs. Loewe in addition to the Five Thousand Dollars ($5,000.00) received from the bonding company in order to complete the jobs contracted for. Although there were minimum changes In the job as originally contracted for, work is still going on to complete the original work contracted for by the Respondent. The building inspector for the City of Tampa Building Bureau, Tom Burgoyme, inspected the job site on several occasions during the progress on the work contracted for between Mrs. Loewe and the Respondent. He found building code violations and submitted a list of corrections to the Respondent, Mr. Jones, which were not remedied. A number of problems arose during the construction work, some of which was not the fault of the Respondent. Another contractor was involved in the work on the project. Funds in excess of the purchase price were paid to the Respondent and funds in excess of Eighty-Five Hundred Dollars ($8,500) were needed or will be needed to complete the project.

Recommendation Revoke the general contractor's license of Respondent, Number C GC007323. DONE and ORDERED this 7th day of April, 1977, in Tallahassee, Florida. DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 Barry Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 W. Bert Jones 2300 Greenlawn Street Brandon, Florida 33511

# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD A. VALDES, 79-000956 (1979)
Division of Administrative Hearings, Florida Number: 79-000956 Latest Update: May 19, 1980

The Issue Whether Respondent, a certified general contractor, is guilty of pulling permits for construction projects not supervised by Respondent, and, if so, the appropriate disciplinary action which should be taken by the Board.

Findings Of Fact At all times material hereto, Respondent was the holder of Certified General Contractor's License No. CG C005204 issued by the Board. Although this license was active at the time the Administrative Complaint was filed, Respondent has placed it on an inactive status until June 30, 1981. (Stipulation, Testimony of Respondent) As to Amiguet Construction Project During 1976, Jose Amiguet entered into a contract with San Pedro Construction Inc. for the construction of an addition to his existing residence located at 1409 Granada Boulevard, Coral Gables, Florida. (Stipulation, Petitioner's Exhibit 1) Since San Pedro Construction Inc. was not properly licensed as a building contractor, it was not qualified to apply for and obtain a Coral Gables building permit to undertake this residential addition. Therefore, on January 12, 1977, pursuant to an agreement with Jose San Pedro, representative of San Pedro Construction Inc., the Respondent applied and obtained the required Coral Gables building permit under his on name. (Stipulation, Testimony of Respondent, Charles Kozak, Petitioner's Exhibit 1) The Respondent did not participate in, manage, or supervise, in any manner, the construction of the Amiguet residential addition by San Pedro Construction Inc. Jose Amiguet neither knew the Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) Final inspection of the Amiguet construction project has not been conducted by the Coral Gables building inspection department since the required documentation concerning sidewalk improvements and subcontractors used has not yet been submitted. The actual construction work has, however, been completed, to the satisfaction of Jose Amiguet. (Testimony of Charles Kozak, Respondent) Respondent made an effort to assist Jose Amiguet in obtaining the final inspection and clearance by the city building inspection department. However, since Respondent did not supervise the subcontractors' work, he cannot truthfully complete the required documents. He has, therefore, offered to (1) pay for the additional costs associated with obtaining the necessary final inspection, and (2) transfer to Jose Amiguet the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Respondent) As to the Shaw Construction Project During July, 1977, and on February 8, 1978, James L. Shaw entered into separate contracts with San Pedro Construction Inc. for the construction of residential improvements at 836 Obispo Avenue, Coral Gables, Florida. The final contract was in the amount of $16,700.00. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) Since San Pedro Construction Inc. was an unlicensed contractor, Respondent, on November 15, 1977, pursuant to an agreement with that company, applied for and obtained the required Coral Gables building permit. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) The Respondent did not participate in, manage, or supervise in any manner the construction of the Shaw residential improvements by San Pedro Construction Inc. James Shaw neither knew Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) On or about April, 1978, the lending institution for the Shaw project, and James Shaw stopped making construction payments to San Pedro Construction Inc., due to its failure to proceed on and abandonment of the project. (Testimony of James Shaw, Charles Kozak) On June 20, 1978, James Shaw obtained an "owner-builder" permit from the City of Coral Gables and incurred the following costs in order to complete the construction project as originally planned: $12,000 for labor and materials, and $625.00 for architectural services. Inasmuch as approximately, $10,128.00 had earlier been paid to San Pedro Construction Inc. for the construction project, the total cost of the project to James Shaw was approximately $22,753.00-$6,053.00 in excess of the original contract price. (Testimony of James Shaw and Respondent) San Pedro Construction Inc. is no longer in business, and the whereabouts of its owner, Jose San Pedro, is unknown. (Testimony of Respondent) As with the Amiguet construction project, final inspection of the Shaw project cannot be conducted until missing documentation relative to sidewalk improvements and subcontractors involved is supplied. In an effort to assist James Shaw, the Respondent has offered to transfer to Shaw the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Charles Kozak and Respondent) At all times material hereto, the Respondent was aware that it was unlawful, under both state law and the Code of Metropolitan Dade County, to aide an unlicensed contractor in evading the contractor licensing law, and to use one's license to pull permits for projects not supervised by the licensee. (Stipulation, Testimony of Respondent, Petitioner's Exhibit 1) The Metro Dade Construction Trades Board heard the complaint against the Respondent and found prima facie evidence and probable cause to refer the matter to the Florida Construction Industry Licensing Board (Stipulation) Notwithstanding the evidence presented, the Administrative Complaint and the Board's counsel at hearing limited the amount sought for restitution purposes to $5,300.00, provided both the performance bonds are refunded to the benefit of Jose Amiguet and James Shaw. (Administrative Complaint, statement of Board's Counsel) Respondent regrets having taken the actions complained of in the Board's Administrative Complaint, and now more fully understands the resulting burdens which have been placed on Jose Amiguet and James Shaw. (Testimony of Respondent)

Recommendation Guilty, as charged. Respondent's certified general contractor's license should be suspended until such time as full restitution is made to the persons damaged by his actions.

Florida Laws (2) 120.57489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES D. POSKEY, 82-001236 (1982)
Division of Administrative Hearings, Florida Number: 82-001236 Latest Update: Dec. 04, 1990

The Issue The issues in this proceeding are whether the Respondent has violated provisions of the Florida Construction Industry Licensing Law, and, if so, what disciplinary action should be taken. The administrative complaint specifically charges Respondent with aiding an unlicensed person to evade provisions of the contracting licensing law, conspiring with an unlicensed person to allow his license to be used to evade provisions of the law, acting as a contractor under a name other than as appears on his registration, and failing to properly qualify a company under which he was doing business. Respondent denies the allegations.

Findings Of Fact At all times material to this proceeding, the Respondent has been duly licensed by the Petitioner as a building contractor. On March 23, 1980, Nettie Wilkes entered into a contract with Rado Construction, Inc. The contract was for Rado to enclose a carport at Wilkes' residence and to do other work incident to that renovation. The contract provided that work would commence on April 10, 1980, and be completed approximately 21 to 30 days from the start. The total contract price was $5,700, and Mrs. Wilkes gave Rado a $1,500 down payment. Donald W. Gray negotiated the contract on behalf of Rado with Wilkes. Gray appears to be the principal party in Rado Construction. Gray contacted James Neilan and Jerry Polk about performing the work on the Wilkes project. Gray did not show Polk a copy of the contract with Wilkes, and he led Polk to believe that considerably less work would need to be performed than was required under the contract. Although Polk had a local occupational license as a carpenter, he was not a licensed contractor, and was not able to obtain a building permit for the work. Neilan and Gray were also unlicensed and unable to obtain a permit. Polk assumed that he would be working for Gray in a subcontracting capacity. Polk had performed considerable carpentry work on a subcontracting basis for the Respondent. Polk felt that the Respondent might help him obtain a permit. Polk approached the Respondent about the Wilkes' project. He told the Respondent the scope of the project as it bad been related to Polk by Gray. He did not advise the Respondent of the involvement of Gray or of Rado Construction. Polk initially asked the Respondent if the Respondent would be able to do the job and the Respondent indicated that he could not. Polk and the Respondent discussed the job on a casual basis and the discussion ended. Several days later, Polk returned to the Respondent's office and asked the Respondent if the Respondent could obtain the building permit and allow Polk to perform the work on a subcontractor basis. Respondent drew up some plans about the project. He agreed to Polk's proposal. The Respondent filed an application with the building inspection department of the City of Orlando for a building permit on April 15, 1980. A permit was issued by the city on that same date. Respondent had estimated the cost of the project, based upon his discussion with Polk, as being approximately $2,000. The Respondent delivered the permit to Polk and advised Polk that he would be inspecting the project periodically. Polk posted the permit at the Wilkes' property and worked together with James Neilan on the project. The work did not commence as scheduled in the contract between Rado Construction and Mrs. Wilkes, but it did commence sometime after April 15, 1980. As the project went on, Gray would from time to time visit the site and advise Polk and Neilan of additional work that would need to be performed that Polk had not known about earlier. Polk did not know that considerable masonry work would be required. He was not qualified to do masonry work, but he attempted to perform it. As the work went on, Polk became more and more dissatisfied, and ultimately concluded that what had been described to him as a one and one-half week job for two people was in reality a two-week job for ten men. Polk ultimately removed the permit from the premises and abandoned his work there. Approximately four days after he obtained the building permit for Polk, the Respondent visited the job site. He observed that no work had commenced and he contacted Polk. Polk erroneously advised the Respondent at that time that the project had been abandoned and that the permit would not be utilized. Respondent heard nothing more about the project for approximately four weeks. Mrs. Wilkes eventually became dissatisfied with the nature of the services that were being performed on her property. When Polk abandoned further work, she contacted the building permit officials and was advised that the Respondent, not Rado Construction, had obtained the permit. She contacted the Respondent and advised him of what had occurred. The Respondent promptly visited Mrs. Wilkes at her home. He was surprised and appalled to find that very poor work had been performed in a very sloppy manner. He discussed the matter at length with Mrs. Wilkes and learned for the first time of Gray's involvement in the project. He advised Mrs. Wilkes that he would not be able to do the job, but he gave her a check for $600 which she told him would be sufficient to complete the project. Respondent also provided laborers to perform cleanup work at the site, and hired a subcontractor to pour a driveway. Respondent expended approximately $1,000 to complete the project for Mrs. Wilkes. The Respondent located Gray, and in an unpleasant confrontation, obtained a promissory note from Gray for $1,000 to compensate the Respondent for his expenditures. The Respondent ultimately accompanied Mrs. Wilkes to a first meeting of creditors at Gray's bankruptcy proceedings. The Respondent has not previously or subsequently engaged in business in the manner that he did in this transaction. He is a reputable contractor and is contrite about the role that he played in the transaction.

Florida Laws (3) 120.57489.119489.129
# 9
PINELLAS COUNTY CONSTRUCTION LICENSING BOARD vs DAVID G. BEERS, 00-002434 (2000)
Division of Administrative Hearings, Florida Filed:Largo, Florida Jun. 12, 2000 Number: 00-002434 Latest Update: Jan. 03, 2025
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer