Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES D. POSKEY, 82-001236 (1982)
Division of Administrative Hearings, Florida Number: 82-001236 Latest Update: Dec. 04, 1990

The Issue The issues in this proceeding are whether the Respondent has violated provisions of the Florida Construction Industry Licensing Law, and, if so, what disciplinary action should be taken. The administrative complaint specifically charges Respondent with aiding an unlicensed person to evade provisions of the contracting licensing law, conspiring with an unlicensed person to allow his license to be used to evade provisions of the law, acting as a contractor under a name other than as appears on his registration, and failing to properly qualify a company under which he was doing business. Respondent denies the allegations.

Findings Of Fact At all times material to this proceeding, the Respondent has been duly licensed by the Petitioner as a building contractor. On March 23, 1980, Nettie Wilkes entered into a contract with Rado Construction, Inc. The contract was for Rado to enclose a carport at Wilkes' residence and to do other work incident to that renovation. The contract provided that work would commence on April 10, 1980, and be completed approximately 21 to 30 days from the start. The total contract price was $5,700, and Mrs. Wilkes gave Rado a $1,500 down payment. Donald W. Gray negotiated the contract on behalf of Rado with Wilkes. Gray appears to be the principal party in Rado Construction. Gray contacted James Neilan and Jerry Polk about performing the work on the Wilkes project. Gray did not show Polk a copy of the contract with Wilkes, and he led Polk to believe that considerably less work would need to be performed than was required under the contract. Although Polk had a local occupational license as a carpenter, he was not a licensed contractor, and was not able to obtain a building permit for the work. Neilan and Gray were also unlicensed and unable to obtain a permit. Polk assumed that he would be working for Gray in a subcontracting capacity. Polk had performed considerable carpentry work on a subcontracting basis for the Respondent. Polk felt that the Respondent might help him obtain a permit. Polk approached the Respondent about the Wilkes' project. He told the Respondent the scope of the project as it bad been related to Polk by Gray. He did not advise the Respondent of the involvement of Gray or of Rado Construction. Polk initially asked the Respondent if the Respondent would be able to do the job and the Respondent indicated that he could not. Polk and the Respondent discussed the job on a casual basis and the discussion ended. Several days later, Polk returned to the Respondent's office and asked the Respondent if the Respondent could obtain the building permit and allow Polk to perform the work on a subcontractor basis. Respondent drew up some plans about the project. He agreed to Polk's proposal. The Respondent filed an application with the building inspection department of the City of Orlando for a building permit on April 15, 1980. A permit was issued by the city on that same date. Respondent had estimated the cost of the project, based upon his discussion with Polk, as being approximately $2,000. The Respondent delivered the permit to Polk and advised Polk that he would be inspecting the project periodically. Polk posted the permit at the Wilkes' property and worked together with James Neilan on the project. The work did not commence as scheduled in the contract between Rado Construction and Mrs. Wilkes, but it did commence sometime after April 15, 1980. As the project went on, Gray would from time to time visit the site and advise Polk and Neilan of additional work that would need to be performed that Polk had not known about earlier. Polk did not know that considerable masonry work would be required. He was not qualified to do masonry work, but he attempted to perform it. As the work went on, Polk became more and more dissatisfied, and ultimately concluded that what had been described to him as a one and one-half week job for two people was in reality a two-week job for ten men. Polk ultimately removed the permit from the premises and abandoned his work there. Approximately four days after he obtained the building permit for Polk, the Respondent visited the job site. He observed that no work had commenced and he contacted Polk. Polk erroneously advised the Respondent at that time that the project had been abandoned and that the permit would not be utilized. Respondent heard nothing more about the project for approximately four weeks. Mrs. Wilkes eventually became dissatisfied with the nature of the services that were being performed on her property. When Polk abandoned further work, she contacted the building permit officials and was advised that the Respondent, not Rado Construction, had obtained the permit. She contacted the Respondent and advised him of what had occurred. The Respondent promptly visited Mrs. Wilkes at her home. He was surprised and appalled to find that very poor work had been performed in a very sloppy manner. He discussed the matter at length with Mrs. Wilkes and learned for the first time of Gray's involvement in the project. He advised Mrs. Wilkes that he would not be able to do the job, but he gave her a check for $600 which she told him would be sufficient to complete the project. Respondent also provided laborers to perform cleanup work at the site, and hired a subcontractor to pour a driveway. Respondent expended approximately $1,000 to complete the project for Mrs. Wilkes. The Respondent located Gray, and in an unpleasant confrontation, obtained a promissory note from Gray for $1,000 to compensate the Respondent for his expenditures. The Respondent ultimately accompanied Mrs. Wilkes to a first meeting of creditors at Gray's bankruptcy proceedings. The Respondent has not previously or subsequently engaged in business in the manner that he did in this transaction. He is a reputable contractor and is contrite about the role that he played in the transaction.

Florida Laws (3) 120.57489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILIP J. MAINS, 80-002231 (1980)
Division of Administrative Hearings, Florida Number: 80-002231 Latest Update: Jul. 08, 1981

Findings Of Fact In early September of 1979, John and Ruth E. Lockwood contracted with P & P Custom Pools, Inc. (P & P), for the construction of a swimming pool at their home, 231 El Dorado Drive, Debary, Florida. Respondent, Philip J. Mains, signed the contract on behalf of P & P and later obtained a building permit. He and his men began excavating on site in mid-September. The Lockwoods paid respondent $700.00 on September 6, 1979. As construction progressed, they paid him $1,706.25 on September 27, 1979; $1,000.00 on October 26, 1979; $1,047.50 on October 29, 1979; and $1,706.25 on November 20, 1979. At the appropriate times, a building inspector was summoned, who inspected the project, including the placement of reinforcing steel, ground wiring, and lights. Neither the "steel inspection" nor the "deck inspection" revealed any problem. The workmanship was excellent, as far as it went, but the Volusia County building inspector's office was never asked to perform a final inspection. As respondent promised there would be, there was water in the swimming pool by Christmas of 1979, but respondent did no further work after December, 1979. He never installed the pump, filter, diving board, or hand bars called for in the Lockwoods' contract. Earlier in 1979, Patrick T. Ryan, the other principal in P & P, left town and abandoned the business which was then $37,000 in debt. In November of 1979, respondent turned the company's books over to an accountant. In January of 1980 the business' financial problems became critical and, at the accountant's suggestion, respondent so advised the eight homeowners for whom he was building swimming pools, including, in January or February, Mr. Lockwood, who reacted angrily. Respondent testified that Mr. Lockwood "cussed him out." Thereafter respondent avoided the Lockwoods until April of 1980 when they found him working on another pool. There was enough money owed on the eight contracts as a group to finish all the pools, according to respondent's uncontroverted testimony, at the time the Internal Revenue Service levied on respondent's bank account and seized his tools and equipment. Even then respondent offered to finish the Lockwoods' pool if they would buy the materials. Respondent's wife asked Mrs. Lockwood to write a check to a supplier for a pump and filter so that respondent could install them and get water in the pool circulating. Instead, during the last week of April, 1980, the Lockwoods contracted with somebody else to finish the job and paid him $1,200. Respondent subcontracted with a Jacksonville cement company to pour concrete for the pool. After the concrete had been poured, the Lockwoods got a registered letter from the subcontractor threatening to place a lien on their property if he were not paid. According to Mr. Lockwood, the problem was that some check [supposedly drawn by respondent in favor of the subcontractor] had been delayed in the mail. In any event, there was no indication in the evidence that the Lockwoods heard anything further from the subcontractor.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration for thirty (30) days. DONE AND ENTERED this 29th day of April, 1981, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1981. COPIES FURNISHED: Charles F. Tunnicliff, Esquire 130 North Monroe Street Tallahassee, Florida 32301 Philip J. Mains c/o Sue Mains Route 2, Box 799A DeLand, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs. CASE NO. 80-2231 PHILIP J. MAINS, RP 0024663, Respondent. /

Florida Laws (1) 489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN W. ROHRBACK, 82-002616 (1982)
Division of Administrative Hearings, Florida Number: 82-002616 Latest Update: Jun. 26, 1984

Findings Of Fact At the final hearing the following factual allegations contained in the Administrative Complaint were either stipulated to by the parties or not disputed by the Petitioner: The Respondent John W. Rohrback is a certified general contractor having been issued license numbers CC C002372, CG CA 02372, PM 0015083 and RF 0036563. The last known address of the Respondent Rohrback is 10282 N.W. 31st Street, Coral Springs, Florida 33065. The Respondent Rohrback, while doing business as Statewide Insulation and Solar Systems, Inc., failed to initially obtain building permits which are required by ordinance on the following job sites: Mrs. Blanche Nelson, 454 N.E. 4th Street, Boca Raton. Mrs. Dorothy Menzel, 784 N.E. 71st, Lot 27, Block C, Boca Harbor. Work started May 17, 1980. Permit taken out on May 19, 1980. Mrs. Meinhard, 1230 S.W. 7th Street, Lot 6, Block 29, Boca Raton Square. Work started on May 7, 1980. Permit taken out on May 19, 1980. Ms. Mary Greenhauer, 986 S.W. 14th Street, Lot 20, Block 63, Boca Raton Square. Work started on May 3, 1980. Permit issued on May 19, 1980. Although the Respondent Rohrback eventually received the permits for these projects, he also initially failed to obtain a license to do contracting in the City of Boca Raton as required by ordinance. On or about August 11, 1980, the City of Boca Raton Contractor's Board suspended the Respondent Rohrback indefinitely from doing business in the city for: using alternate materials and methods without clearance; not obtaining building permit; not filing a proper permit; and not filing proper proof of a certificate of competency. At the time of the hearing before the local contractor's board, the Respondent Rohrback had settled and obtained releases with two of the listed individuals. He was told to settle the remaining two cases, obtain releases and appear before the local Board at a later date. The Respondent appeared on the designated date and discovered that the Board had met the previous day and suspended his license. The Respondent Rohrback contacted the Boca Raton city attorney and a representative of the Department to present the signed releases and cancelled checks he eventually obtained from the four listed individuals in order to obtain a reversal of the local Board's action suspending his license. At the time of hearing, the Respondent had been unsuccessful in obtaining a reversal of the Board's decision. Additionally, the Respondent Rohrback acted as qualifying agent for D.R.K. Company from July 1, 1979 through February 1981. During this period of time, D.R.K. utilized deceptive practices in order to obtain contracts from various individuals. By certified letter dated June 12, 1980, the Respondent informed D.R.K. and pertinent licensing boards that he was withdrawing as qualifying agent for D.R.K. and Statewide Insulation and Solar Systems, Inc., and revoking any presigned permits or letters of authorization that may have been signed by John W. Rohrback. However, the Respondent did not actually attempt to revoke his authorization until October 28, 1980, when a letter was sent to Milton Rubin, administrative assistant to the Florida Construction Industry Licensing Board, outlining the problems he had encountered with D.R.K. and Statewide. On or about February 19, 1981, the Lee County Board of County Commissioners suspended the Respondent Rohrback's privilege to pull building permits.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a Final Order be entered dismissing the Administrative Complaint filed against the Respondent John W. Rohrback in Case No. 82-2616. DONE and ORDERED this 28th day of March, 1983, in Tallahassee, Florida. SHARYN L. SMITH, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March, 1983. COPIES FURNISHED: Michael J. Cohen, Esquire Suite 101 Kristin Building 2715 East Oakland Park Blvd. Fort Lauderdale, Florida 33306 John W. Rohrback 10282 Northwest 31st Street Coral Springs, Florida 33065 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (4) 455.227489.119489.129501.204
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs ROCCO R. SODOMIRE, 99-001683 (1999)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Apr. 12, 1999 Number: 99-001683 Latest Update: Jul. 15, 2004

The Issue Whether Rocco R. Sodomire (Respondent) violated Section 489.129(1)(c) and (r) and Section 455.227(l)(o), Florida Statutes, and if so, what disciplinary action should be taken against his license to practice contracting.

Findings Of Fact Respondent is, and has been at all times material hereto, a Certified Residential Contractor in the State of Florida, having been issued license number CR CO57213. At all times material hereto, Respondent was not licensed to do any swimming pool/spa contracting in the State of Florida. On or about November 1996, Respondent submitted a proposal to Vincent Neglio for the construction of a 28' x 14' in-ground swimming pool, a deck, and a screen enclosure at a cost of $15,000.00. Shortly thereafter, pursuant to the proposal, Respondent began construction of a swimming pool and deck at Mr. Neglio's residence. Prior to completion of the pool project, Mr. Neglio paid Respondent a total of $14,200.00. Although Respondent received $14,200.00 from Vincent Neglio, he never completed the pool project. Respondent presented the proposal for the pool project to Mr. Neglio; accepted money from Mr. Neglio as payment for work on the project; distributed funds to other contractors who worked on the pool project; and performed work on the pool project at Mr. Neglio's home. On August 4, 1997, the County Court of the Twentieth Judicial Circuit in and for Lee County, Florida, Small Claims Division (Case Nos. 97-2569SP-RRS and 97-2570-SP-RRS), entered a Record of Agreement between Respondent and Mr. Neglio whereby Respondent was to pay Mr. Neglio a total of $2,600.00 to settle the dispute involving the aforementioned pool project. On January 13, 1998, the County Court of the Twentieth Judicial Circuit in and for Lee County, Florida, Small Claims Division, in the above-referenced cases entered a Final Judgment by Default against Respondent in favor of Vincent Neglio in the amount of $2,600.00, the payment amount required in the Agreement, as a result of Respondent's failing to pay monies based on the Agreement referenced in paragraph 6. To date, Respondent has failed to make any payments to Vincent Neglio based on the Small Claims Court Record of Agreement, referenced in paragraph 6 or the Final Judgment by Default referenced in paragraph 7.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order that: (1) finds Respondent committed the offenses alleged in Counts I and II of the Administrative Complaint and imposes a $500.00 fine for these violations; (2) requires Respondent to pay restitution to Vincent Neglio in the amount of $2,600.00; and (3) requires Respondent to pay to Petitioner $858.97, the costs incurred by Petitioner in the investigation and prosecution of this proceeding. DONE AND ENTERED this 23rd day of November, 1999, in Tallahassee, Leon County, Florida. CAROLYN S. HOLIFIELD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of November, 1999. COPIES FURNISHED: Paul F. Kirsch, Esquire Leonardo N. Ortiz, Qualified Representative Department of Business and Professional Regulation 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 Rocco R. Sodomire 3520 Southeast 2nd Avenue Cape Coral, Florida 33904 Rodney Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (5) 120.57455.227489.105489.1195489.129 Florida Administrative Code (1) 61G4-12.018
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. HAMILTON, 79-000018 (1979)
Division of Administrative Hearings, Florida Number: 79-000018 Latest Update: Apr. 28, 1980

Findings Of Fact At all times pertinent to these proceedings, Hamilton held registered residential contractors license number RR0015037. Hamilton agreed to construct a house in Clearmont, Florida, with a completion date no later than May 1, 1977, for Robert J. and Margaret M. Phlepsen. The construction price was $75,000.00. After construction of the house it was discovered that there existed two violations of the Southern Building Code. First, the "step-down" from the kitchen to the garage was an eleven inch riser contrary to the code requirement that the height of a riser shall not exceed seven and three quarters inches. The second violation occurred through the use of 2 X 8 joists where the code would require 2 X 10 joists. The extra high riser between the kitchen and the garage was apparently caused by an oversight. Hamilton merely failed to install an intermediate step at that location. The second violation occurred because the owner and Hamilton agreed to use the smaller joists in order to save money on the contract price. In neither case is there sufficient evidence to establish that Hamilton's violations were willful or deliberate as alleged in the Administrative Complaint. On June 6, 1978, the Lake County Board of Examiners suspended Hamilton's Lake County Certificate of Competency because of violations of building code requirements in the construction of Phlepsen's house.

# 5
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs RONALD J. POWELL, 00-002938PL (2000)
Division of Administrative Hearings, Florida Filed:Lakeland, Florida Jul. 18, 2000 Number: 00-002938PL Latest Update: Mar. 12, 2001

The Issue Did Respondent commit the violations alleged in the Administrative Complaint dated April 11, 2000, and if so, what discipline is appropriate?

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: The Department is the agency of the State of Florida charged with the responsibility of regulating the practice of contracting pursuant to Section 20.165, Florida Statutes, and Chapters 455 and 489, Florida Statutes. Respondent is, and has been at all times material hereto, a certified residential contractor in the State of Florida, having been issued license number CR CO13253 by the Florida Construction Industry Licensing Board. At all times material hereto, Respondent was licensed with the Construction Industry Licensing Board as an individual. On or about November 20, 1993, Respondent entered into a written contractual agreement (contract) with Kevin Watkins (Watkins) to construct a single family residence at 126 Meadow Lark Boulevard, Lot 65, Indian Lake Estates, Florida. The contract price was $333,944.00. Between December 7, 1993, and February 1, 1996, Watkins and Respondent executed 102 addenda to the contract which increased the contract price by approximately $241,874.43, for a total amount of approximately $575.818.43. On or about December 9, 1993, Respondent obtained permit number 93-120l850 from the Polk County Building Department and commenced work on the project. The contract provided that the "project shall be substantially completed on or about 195 days from the date all building permits are issued." However, due to the 100-plus addenda to the contract, it was estimated that an additional 190 days would be needed to complete the project. Additionally, construction ceased on the home for approximately 60 days so that Watkins could explore the possibility of a construction loan. However, due to the extent of completion, the lending institutions decided not to make any construction loans. On or about May 27, 1996, Watkins moved to Florida with the expectations that his home would be completed within a short period of time. (Watkins' recollection was that the home was to be completed in a couple of weeks. Respondent's recollection was that the home was to be completed in a couple of months.) In any event, Respondent did not complete the Watkins home within a couple of weeks or a couple of months. After Watkins moved to Florida, Respondent paid for Watkins to live in a Best Western motel for a few weeks. Subsequently, Respondent moved Watkins into a rental home for which Respondent paid the rent through September 1996. Beginning October 1996 through July 1999, Watkins paid $600.00 per month for a total of $20,400.00 as rent on the rental home. In early 1998, Respondent and Watkins went through the home, identified those items which had not been completed and Respondent made a handwritten list of those items. Respondent failed to complete the items identified on the list. In fact, shortly thereafter, Respondent ceased working on the project and was unresponsive to attempts to contact him. At the time Respondent ceased working on Watkins' home, the home was approximately 75 percent complete. While this estimation of completion may not be totally accurate, it is the best that could be derived based on the evidence presented, including Respondent's testimony to which I gave some credence. Watkins paid Respondent $561,617.91, which represents approximately 97.534 percent of the total contract price plus addenda to the contract. Seventy-five percent of the contract price plus addenda to the contract equals $431,863.82 for an overpayment of $129,754.09. To date, Respondent has not returned any of the money he received from Watkins above the amount completed under the contract. From early 1998, until August 1998, when Watkins had Respondent removed as general contractor on the building permit, Respondent failed to perform any work on the home for a period in excess of 90 days. Respondent contracted with Jack Eggleston to install cabinets in Watkins home. Eggleston performed under the contract but Respondent failed to pay Eggleston in full, requiring Watkins to pay Eggleston $1,200.00. After Watkins' home was partially complete, Respondent advised Watkins that he had the home insured when in fact he did not have the home covered with insurance. While Respondent was building Watkins' home, Respondent and Watkins entered into a joint venture called Contractors of Central Florida to build modular homes sometime after January 1, 1995. Respondent contends that some of the checks Watkins claims as payment under the contract for his home, were in fact reimbursement to Respondent for funds he had advanced for the joint venture. There is insufficient evidence to establish facts to show that any of the checks Watkins claims as payment under the contract for his home were in fact reimbursement for funds advanced by Respondent for the joint venture. Up until the time of the final hearing, the Department had incurred costs for the investigation and prosecution of this matter, excluding costs associated with an attorney's time, in the amount of $1,451.28.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, and after careful review of the guidelines set forth in Rule 61G4-17.001(8) and (11), Florida Administrative Code, and the circumstances for purpose of mitigation or aggravation of penalty set forth in Rule 61G4-17.002, Florida Administrative Code, it is recommended that the Department: Enter a final order finding Respondent guilty of violating Section 489.129(1)(h)2., Florida Statutes, and imposing a penalty therefor an administrative fine in the amount of $1,000.00; Enter a final order finding Respondent guilty of violating Section 489.129(1)(k), Florida Statutes, and imposing a penalty therefor an administrative fine in the amount of $1000.00; Assessing costs of investigation and prosecution, excluding costs associated with an attorney's time, in the amount of $1,451.28, plus any such further costs which have or may accrue through the taking of final agency action and; Requiring Respondent to pay restitution to Kevin Watkins in the amount of $129,754.09 which represents the amounts accepted by Respondent for work not performed. DONE AND ENTERED this 23rd of October, 2000, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6947 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 2000. COPIES FURNISHED: Robert A. Crabill, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32388-2202 Ronald J. Powell Post Office Box 7043 Indian Lake Estates, Florida 33855 Rodney Hurst, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (4) 120.5720.165489.1195489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. HAMILTON, 81-001925 (1981)
Division of Administrative Hearings, Florida Number: 81-001925 Latest Update: May 17, 1982

The Issue The issues presented in this case concern certain allegations made by the Petitioner against the Respondent through an Administrative Complaint. In particular, it is alleged that on or about April 23, 1980, the Respondent's contractor's license issued by the Petitioner was suspended and subsequent to that time, the Respondent continued to perform contracting services through a company, David H. Hamilton, Inc., a corporation which was not properly qualified by the Petitioner to provide contracting services. It is further alleged by the Petitioner that the Respondent obtained building permits Nos. S2740-80B 1/ and 3214-80B from the Osceola County Building Department with the use of another contractor's license, namely: Louie S. Winchester, license #RR003839. For the reason of these facts, the Petitioner alleges that the Respondent has violated Subsection 489.127(1)(e), Florida Statutes, in that he attempted to use a suspended registration. It is further alleged, based upon the facts as reported in this Issues statement, that the Respondent has violated Subsection 489.129(1)(g), Florida Statutes, by acting in a capacity as a contractor under a certificate of registration not in his name. Finally, it is alleged, based upon the facts as reported hereinabove, that the Respondent has violated Subsection 489.129(1)(j), Florida Statutes, by failing to comply with Subsection 489.119(2), Florida Statutes, by not properly qualifying a corporation under which he performed contracting services.

Findings Of Fact The case presented concerns license disciplinary action by the Petitioner, State of Florida, Department of Professional Regulation, Florida Construction Industry Licensing Board, against the Respondent, David H. Hamilton, who holds a residential contractor's license issued by the Petitioner, #RR0014037. The prosecution of this action is through the offices of the Department of Professional Regulation and the outcome of the matter could lead to the revocation, suspension or other disciplinary action against the Respondent, in keeping with the provisions of Chapter 489, Florida Statutes. This case was presented before the Division of Administrative Hearings following a decision on the part of the Respondent to request a formal hearing pursuant to Subsection 120.57(1), Florida Statutes. The facts reveal that a Final Order of the Florida Construction Industry Licensing Board was issued on April 23, 1980, and this order established disciplinary action against the current license of David H. Hamilton. (A copy of this Final Order may be found as a part of the record in this proceeding and official recognition of that Final Order is made by the Recommended Order process.) This Final Order was entered after review of a Recommended Order of a Division of Administrative Hearings' Hearing Officer. By the terms of the Final Order, Hamilton's license was suspended "until such time as his Lake County Certificate of Competency is reinstated by the Lake County Board of Examiners." This contingency referred to the fact that the Respondent had his Lake County Certificate of Competency Card removed prior to the entry of the April 23, 1980, order of the Construction Industry Licensing Board. On September 2, 1980, at a time when the Respondent's residential contractor's license was under suspension by the State of Florida, the Respondent through a corporation applied to the Osceola County Building Department for a building permit to construct a residence in Osceola County, Florida. This permit number was #2740-80B. The permit was issued on September 4, 1980, and was granted in the name of David Hamilton, Inc., a corporation in which the Respondent was a principal. To obtain the permit in the sense of an effort to meet the requirements that the permit be applied for by a licensed Florida contractor, the Respondent used the registered residential contractor's license of one Louie Stevens Winchester who held license #RR003839 issued by the Florida Construction Industry Licensing Board. On the occasion of the issuance of the permit by Osceola County, Winchester was an officer of David Hamilton, Inc. Through the action of "pulling" this permit and the utilization of the permit in his construction of the residence, the Respondent was acting in the capacity of contractor under Winchester's license and the offices of the corporation, as opposed to the Respondent's suspended license. Prior to the request for permit, neither Hamilton nor Winchester had attempted to properly qualify David Hamilton, Inc., as a contracting corporation with the Florida Construction Industry Licensing Board. In this case, to properly qualify the corporation, it would have entailed the use of Winchester as the qualifying agent, in view of the fact that Winchester still held a valid contractor's license from the Florida Construction Industry Licensing Board. No effort was made to qualify David Hamilton, Inc., in its own right, through the agency of Winchester, until some time shortly beyond December 1, 1980. On October 28, 1980, the Respondent in his individual capacity, that is to say unconnected with his business pursuits as David Hamilton, Inc., went to the Osceola Building Department and applied for the issuance of a building permit for a home remodeling project for a customer of his. The permit in question on this occasion was #3214-80B. That permit was issued on October 29, 1930, and was used by the Respondent in his building project. An official in the Osceola County Building Department had checked with an employee in the Lake County Building Department on the status of Hamilton's rights to be employed as a building contractor in Lake County, Florida, and was informed that Hamilton's status in Lake County was acceptable. Based upon these representations, the Osceola County employee issued the permit discussed in this paragraph to Hamilton. The Osceola County employee also asked that the Lake County employee formally confirm Hamilton's status. The correspondence in response to Osceola County employee, John Pate, Assistant Building Director, as issued by an official in Lake County, one Herb Dudgeon, may be found as Petitioner's Exhibit No. 3. This letter was received by Pate after the permit was issued. That correspondence indicates that Hamilton had been given the privilege of reinstating his Lake County Competence Card, contingent upon "providing bond, insurances, occupational license, etc.," which had not been received by Lake County as of the date of the correspondence. The correspondence goes on to mention that the State, meaning the Florida Construction Industry Licensing Board, was waiting for confirmation of the completion of the contingencies referred to. Subsequent to this correspondence, the Respondent having completed all the necessary steps for reinstatement of the Lake County Competency Card, had his license suspension removed and was reinstated by the Florida Construction Industry Licensing Board, as verified by that body.

Recommendation Based upon a full consideration of the findings of fact and conclusions of law reached herein, it is RECOMMENDED: That the Florida Construction Industry Licensing Board issue a Final Order which absolves the Respondent of any responsibility for a violation of Subsection 489.127(1)(e), Florida Statutes (1980); that finds the Respondent in violation of Subsection 489.129(1)(g), Florida Statutes (1979), and imposes a penalty of a 60-day suspension; and that finds the Respondent in violation of Subsection 489.129(1)(j), Florida Statutes (1979), and imposes a suspension of 60 days to run concurrently with the other suspension in this paragraph of recommendation. 2/ DONE and ENTERED this 13th day of November, 1981, in Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of November, 1981.

Florida Laws (4) 120.57489.119489.127489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEVEN E. SHIELDS, 82-001342 (1982)
Division of Administrative Hearings, Florida Number: 82-001342 Latest Update: Dec. 02, 1983

Findings Of Fact The Respondent is licensed as a general contractor in the State of Florida and registered with the Florida Construction Industry Licensing Board. That agency is the agency charged with regulating the practice of contracting in the State of Florida and with monitoring the compliance of licensees with the various provisions of Chapter 489, Florida Statutes, and pertinent rules relating to licensure standards and practice standards of contractors. On April 23, 1980, one Terry Burch and Jim Goodman were operating a construction business under the fictitious name of "T. J. Associates." Neither Terry Burch or Jim Goodman, nor the entity known as T. J. Associates, was qualified or licensed with the Florida Construction Industry Licensing Board at that time, nor at times subsequent thereto which are pertinent to this proceeding. On April 23, 1980, T. J. Associates entered into a written contract with homeowners Florence Martin and her husband to remodel their home at 120 Broadview Avenue, Winter Park, Florida. The original contract was for $26,615.00 with various addenda to that contract, such that the total net contract price, with modifications, ultimately reached $40,597.00. Both the contract and the modification agreements were signed by the Martins and Terry Burch of T. J. Associates. The Respondent, Steven Shields, was not a party to any of these agreements. Mr. Burch and Mr. Goodman of T. J. Associates, obtained the Martin contract entirely through their own efforts and after obtaining the signed contract, approached the Respondent, Steven Shields, to ask him to draft blueprints for the job, also proposing that the three of them enter into some sort of partnership or other business arrangement. During the meeting at which this business was discussed, it was revealed to the Respondent that T. J. Associates was unlicensed with the Florida Construction Industry Licensing Board and the three men agreed that they would obtain proper application documents from the Board's office in Orlando for filing so as to properly qualify the company. In the meantime, the Respondent agreed to obtain from the City of Winter Park Building Department, the necessary building permits and did so. The Respondent was ultimately paid $600.00 by T. J. Associates for labor he performed on the subject project and for obtaining a building permit in his own name. The Respondent ultimately decided not to enter into a business relationship with T. J. Associates, Burch and Goodman. He did, however, work on the "Martin project" as a sort of job supervisor or foreman, performing some labor on the job and going to the job site on possibly two or three occasions during the course of the construction effort of T. J. Associates. The Respondent initially intended to use his contractor's license to properly qualify T. J. Associates with the Board and obtain the papers to do so, but after he did not enter the formal business relationship with T. J. Associates, neglected to do so, nor did T. J. Associates make any further effort to qualify itself as a contracting entity with the Florida Construction Industry Licensing Board. The Respondent did obtain the building permit for T. J. Associates for the Martin job on May 13, 1980, and obtained it under his individual name and contractor license number. T. J. Associates worked on the Martin job from May 6, 1980, to July 16, 1980. On July 16, 1980, after a dispute regarding the quality of the paint work and other matters, T. J. Associates and the Respondent stopped all work. At the time of the stoppage, the work was 90 percent complete. At the time the work was stopped, no more money was due to T. J. Associates for work already performed. The Martins, at that point, had paid T. J. Associates $35,900.00. The Martins had however, upon advice of their attorney, withheld sufficient funds at the point of cessation of work by T. J. Associates, to enable them to pay for the completion of the job by other labor and materialmen. Three subcontractors had been hired or contracted with by T. J. Associates for work which was performed by them on the Martin job. Those three subcontractors, Mr. Anthony Costa, Mr. Clyde Ray and Mr. Michael Ellis, had performed work for which they were owed, respectively, $531.00, $550.00 and $130.00. None of those three subcontractors have, as yet, been paid for these amounts. They repeatedly attempted to obtain payment from T. J. Associates, but were given no satisfaction in that regard. The Respondent never entered into any agreement or hiring arrangement with the three subcontractors involved, nor did the Respondent ever have possession or control of any funds paid from the Martins to T. J. Associates from which the subcontractors should have been paid. The Respondent only received the above- mentioned $600.00 from T. J. Associates for his services.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that the Respondent be found guilty of a violation of Section 489.129(1)(e) and (k), in that he aided and abetted an uncertified, unregistered person to evade the act and violated Subsection (k) by abandoning the project without just cause. The remaining charges in the Administrative Complaint should, however, be dismissed. In view of the violations proven, an administrative fine of $500.00 and a three (3) month suspension of his license, followed by a one (1) year period of probation is warranted. DONE and ENTERED this 22nd day of August, 1983, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1983. COPIES FURNISHED: Douglas A. Shropshire, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Charles E. Hoequist, Esquire 301 North Ferncreek Orlando, Florida 32803 James Linnan, Executive Director Florida Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (5) 120.57489.105489.113489.119489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PRESTON MADDOX, 87-000213 (1987)
Division of Administrative Hearings, Florida Number: 87-000213 Latest Update: Jun. 19, 1987

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material to this proceeding, Respondent was licensed as a registered general contractor by the State of Florida, Construction Industry Licensing Board, having been issued license number RG 0014645. Respondent's address is 2533 Green Road, Tallahassee, Florida 32308. On or about October 30, 1985, Willie McFarland (McFarland) contracted with Virgil Fleming (Fleming) to perform certain improvements to Fleming's home located at 9008 Broken Lance, Tallahassee, Florida. The contract price was $24,600.00. There was no contract between Fleming and Respondent. Fleming paid McFarland $16,500.00 of the contract price. Most of this money was paid in advance of work being performed. MoFarland was not, at any time material to this proceeding, a licensed contractor in the State of Florida and both Fleming and Respondent knew that he was not a licensed contractor. McFarland was not authorized to pull a permit to complete the work and Fleming, upon finding this out, started to pull the permit as a homeowner but changed his mind. Respondent agreed to pull, and did pull, the permit for this job, after checking on McFarland and with the understanding that he would have to be involved with McFarland on the job. Without the permit, McFarland could not have continued with the job. Fleming did not pay any money to Respondent for pulling the permit or for anything else and there was no evidence that McFarland paid any money to Respondent for pulling the permit or anything else. McFarland partially completed the work contracted for with Fleming. The Respondent went to the job site on several occasions but was unable to make contact with McFarland. Respondent did make contact with McFarland on one (1) occasion after he had pulled the permit and obtained some promises from McFarland concerning the job but McFarland did not "live up" to those promises. There was credible testimony from Respondent that McFarland was not an employee of Respondent's business but that one of the conditions for pulling the permit required McFarland to be an employee of Respondent only on this job. Respondent had no knowledge of the financial arrangements between McFarland and Fleming until after the permit was pulled and McFarland had "skipped." The parties have been unable to locate McFarland.

Florida Laws (2) 120.57489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES RASKIN, 77-000624 (1977)
Division of Administrative Hearings, Florida Number: 77-000624 Latest Update: Aug. 10, 1977

Findings Of Fact The parties stipulated to the fact that James Baskin holds registered contractor's license number BC 0011300. Raskin's registered general contractor's license was issued by the Florida Construction Industry Licensing Board. Prior to the commencement of the hearing, the Hearing Officer held that the record of the proceedings for the Cape Coral Board could be filed as a late filed exhibit in this cause in order that the Florida Construction Industry Licensing Board could review the Cape Coral Board's action pursuant to its authority under Section 468.112(2)(f), Florida Statutes. Ambassador Homes contracted with Sam and Marie Franzella for the construction of a single family residence to be constructed on the property located on Lots 41-42, Block 1224, Cape Coral Unit 19, Section 32-33, Township 44 South, Range 24 East. Stucky Well Drilling was initially contacted by an unknown agent of Ambassador Homes on January 1, 1975, and directed to drill a well, and install a deep well jet pump and tank at the location stated above. On January 20, 1975, Marion, a secretary for Ambassador Homes, called Stucky Well Drilling and directed that Stucky Well Drilling install the well and equipment as soon as possible. On January 21, 1975, a 210 foot well was drilled on the property described above and on January 23, 1975, a Mr. Green from Ambassador Homes called and requested that the tank and equipment be installed immediately. Mr. Hall, an employee of Stucky Well Drilling, installed all the equipment as ordered on January 23, 1975. On January 24, 1975, a bill in the amount of Six Fifty Dollars ($650.00) was sent to Ambassador Homes for the work performed on the property described above. Ambassador Homes was a corporation engaging in residential contracting and operating under the license of James Raskin. Ambassador Homes did not pay Stucky Well Drilling the bill for the drilling of the well and installation of the equipment on the property described in paragraph 3 above. Subsequently Stucky Well Drilling brought suit against Ambassador Homes, Inc., in the County Court of Lee County and obtained final judgment in the amount of Six Hundred Fifty Dollars ($650.00) plus costs. This judgment was entered on December 2, 1975.

Recommendation Based on the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board suspend the license of James Raskin as a registered general contractor until he presents satisfactory proof to the Board of his financial qualifications to engage in the contracting business. DONE and ORDERED this 27th day of May, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blacks tone Building Jacksonville, Florida 32202 James Raskin 1810 S. E. 44th Street Cape Coral, Florida 33904 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer