Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN H. HOLLAND, 79-002059 (1979)
Division of Administrative Hearings, Florida Number: 79-002059 Latest Update: Aug. 28, 1980

Findings Of Fact Respondent is the holder of currently active General Contractor's license No. RG-0023888. On January 18, 1977, Norwood W. Hope (hereinafter "Developer") entered into a contract with Respondent for the construction of a commercial swimming pool. Respondent was to have been paid the amount of $43,346.40 under the contract for construction of the pool. The contract amount was to be paid pursuant to a five-stage draw schedule as follows: 1. Framing and steel draw paid $10,836.60 2. Gunite draw paid 10,836.60 3. Mancite draw 7,224.40 4. Equipment set draw 7,224.40 5. Final approval draw 7,224.40 Respondent made application for an Alachua County building permit for the swimming pool project on February 23, 1977. The permit application was approved on February 25, 1977, and a building permit was issued. Thereafter, the project received Alachua County approval on a temporary power pole inspection on June 1, 1977. An interim inspection of the property was made by Alachua County officials on November 7, 1977, with no deficiencies noted. A final inspection on the electrical work on the project was made, with satisfactory results, on November 8, 1977. The Alachua County Building Code, by incorporation of the 1973 Southern Standard Building Code, 1974 Revision, provides, in part, as follows: 108.2--INSPECTIONS REQUIRED The Building Official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building or structure upon completion, prior to the issuance of the Certificate of Occupancy, as required in Section 109. * * * (c) The Building Official upon notifica- tion from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit bolder or his agent wherein the same fails to comply with the law: * * * Final Inspection: To be made after the building is completed and ready for occupancy. (Emphasis added). The contract entered into on January 18, 1977 between the Developer and Respondent called for Respondent to construct the swimming pool according to the plans and specifications admitted into evidence as Petitioner's Exhibit No. 1. Associated construction, including construction of concrete pool decking, a pumphouse and a fence surrounding the swimming pool site were either completed by the Developer or by other sub contractors. By invoice dated October 12, 1977, Respondent requested a final draw on the project in the amount of 87,000, which, if paid, would have left only $224.40 unpaid under the contract. This draw request indicated that a balance due for extra time and materials would be billed ". . . upon acceptance of total pool." (Respondent's Exhibit No. 4). On October 25, 1977, the Developer paid $6,000 of the $7,000 requested to be paid by Respondent's invoice of October 12, 1977. The Developer contested Respondent's expressed intention to bill for additional time and material, asserting that the Developer had not approved any additional sums for extras. In remitting the $6,000 payment to Respondent, the Developer indicated that "[t]his leaves a balance on our account of $1,224.40, which will be paid upon checking out the pool." (Respondent's Exhibit No. 2). (Emphasis added.) An invoice for back charges on the swimming pool project in the amount of $274 was forwarded to the Developer by Respondent by invoice dated November 8, 1977. In addition, on November 8, 1977, Respondent also invoiced the Developer for a final draw on the project in the amount of $1,224.40. At some time after notification from the Developer's representatives that tile targets in the racing lanes of the pool were improperly located, Respondent returned to the job site after November 9, 1977 to relocate the targets. Respondent performed this work as a result of a written request from the Developer dated November 9, 1977. Respondent completed primary construction of the pool prior to submission of the final draw request of October 12, 1977. At that time, back- filling around the exterior of the pool structure preparatory to the pouring of the concrete pool decking had not been completed. Although by October 12, 1977, Respondent had removed much of the excess dirt and debris from around the edges of the pool. There were still areas of exposed piping which would, in due course, be covered with back-fill and tamped by the decking subcontractor. Respondent did not attempt to back-fill or tamp any areas around the pool's piping system. At some time subsequent to October 12, 1977, which date is not clearly reflected in this record, a separate sub- contractor completed back-filling work around the pool, and poured the concrete decking. Neither the Developer nor his subcontractor advised Respondent that the back-filling had been accomplished and that the deck was to be poured. Prior to October 12, 1977, Respondent "pressure tested" the pool's piping system, and determined that the pool would hold water at a level above its scum gutters. The results of this testing indicated that, at least as of October 12, 1977, there was no leakage from the pool. Standard practice in the pool construction industry dictates that a minimum of three pressure tests be made of a pool's piping system during the course of construction. The first of these tests should occur immediately after installation of the pipes, and a second test should be performed immediately before final back-filling to cover the pipe system. A final pressure test should be conducted after tamping of the fill and prior to the pouring of concrete for the pool deck. The obvious purpose of this system of pressure testing is to discover any water leaks before concrete pool decking is poured to avoid having to cut out sections of the concrete in order to locate leaks. Because the Developer and his subcontractor failed to notify Respondent of further work being done on the pool. Respondent was unable to perform a pressure test either after back-filling was completed, after the back- fill had been tamped and before the concrete deck was poured. By letter dated January 17, 1978, Respondent was furnished by the Developer with a "punch list" indicating several areas of deficiency that needed to be corrected in the pool. In that letter the Developer requested that Respondent complete the necessary work within seven days. The Developer forwarded a second letter to Respondent dated February 23, 1978 advising Respondent that the punch list items had not been corrected, and urging Respondent to complete the work described in the punch list as soon as possible. From receipt of the punch list in January of 1978 through the middle of March, 1978 Respondent had workers on the job intermittently making the corrections indicated in the punch list. Respondent satisfactorily corrected fifteen of the eighteen items listed as defective n the punch list. Some of the items were repaired by other subcontractors. Respondent had difficulty obtaining some items of equipment, which he was required to back-order. When the back-ordered equipment was slow in arriving, the Developer opted to obtain these items from a source other than Respondent. Respondent replaced a defective pump associated with the pool construction at some time subsequent to January 18, 1977. The last work performed by Respondent on the pool project occurred some time between March 10 and March 16, 1978. At no time thereafter was Respondent ever advised by the Developer that any work performed under the contract was either unsatisfactory or incomplete. The pool received a final State of Florida, Department of Health and Rehabilitative Services inspection on July 13, 1978, at which time all necessary permits for operation of the pool under applicable regulations were issued. Respondent at no time requested that Alachua County officials come to the job site to conduct the necessary final inspection of the project, nor did he advise the Developer of the necessity to do so. At some time during 1979, subsequent to the completion of the swimming pool project, the Developer discovered that the pool was losing water at a rate of approximately 2,100 gallons per day. During this period, the water level inside the pool would drop to a level equal to the piping running around the exterior of the pool shell and under the pool decking. When the Developer was unable to ascertain the cause of the leak, an outside subcontractor was hired to check the pool. This sub- contractor performed pressure tests on the pool's piping system in an attempt to determine whether the leakage was occurring through the pipes. These tests apparently showed no leakage through the piping system. The Developer then caused the concrete decking around the edge of the pool to be removed in order to more closely inspect the interior piping. At this point it was discovered that there existed flaws and breaks in the neoprene piping surrounding the exterior shell of the pool. After repairs to the damaged piping, the pool decking was repoured and there has been no subsequent leakage problem in the pool. The Developer incurred expenses in the amount of $2,288 in removing the decking around the pool and repairing the neoprene piping. Because of the fact that several subcontractors in addition to Respondent worked in the pool area during construction of the pool project, it is impossible on the basis of this record to determine the cause of the damage to the neoprene piping. Respondent's testimony is uncontroverted that pressure testing performed prior to the conclusion of primary work on the pool in October of 1977 showed no leakage through the pool's piping system. Further, at the conclusion of the primary work in October, 1977, much of the pool's piping system was left exposed and could have been damaged either by the Developer's own workers or by employees of other subcontractors in the course of back- filling and tamping fill material preparatory to pouring concrete decking. The Developer's failure to advise Respondent of the schedule for back-filling, tamping and pouring of concrete deprived Respondent of an opportunity to properly pressure test the piping system at appropriate stages of construction. Respondent has submitted proposed findings of fact for consideration by the Hearing Officer. To the extent that those proposed findings of fact are not incorporated in this Recommended Order, they have been rejected as being either irrelevant to the subject matter of this proceeding or as not having been supported by the evidence.

Florida Laws (1) 120.57
# 1
CHRISTOPHER P. KISELIUS vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD, 99-001666 (1999)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 07, 1999 Number: 99-001666 Latest Update: Jul. 15, 2004

The Issue Whether the claimants herein are entitled to payment from the Construction Industries Recovery Fund and, if so, the amount of the payment to which each claimant is entitled. Whether the license of the Petitioner is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998).

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Fund is established by Section 489.140, Florida Statutes, for the purpose of reimbursing those persons who meet the eligibility requirements set forth in Section 489.141, Florida Statutes. The Board is the entity responsible for reviewing applications for payment from the Fund and entering orders approving or disapproving the applications. Sections 489.140(1) and 489.143(1), Florida Statutes. Mr. Kiselius is a licensed residential pool/spa contractor, having been first issued such a license in 1984. Mr. Kiselius's license is currently on inactive status, but at the times material to this action, Mr. Kiselius's license was active. Pool Masters was a Florida corporation incorporated on August 10, 1995. Frederick H. Martin and Abraham Zafrani were the sole shareholders of the corporation, and Mr. Martin was the President and Secretary of the corporation, and Mr. Zafrani was the Vice-President and Treasurer. From on or about October 24, 1995, until November 14, 1997, Mr. Kiselius was the qualifying agent for Pool Masters. The record does not reflect the date on which Pool Masters was issued its certificate of authority allowing it to engage in contracting as a business organization, but it was assigned Qualified Business Organization License Number QB0002327 on or about November 6, 1996. Pool Masters filed for bankruptcy pursuant to Chapter 7 of the United States Bankruptcy Code on January 1, 1998, and the corporation was administratively dissolved on October 16, 1998. DOAH Case No. 99-1665: Santibanez and Pappas Eugene Santibanez and Alexander Pappas entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 25, 1997. The total price stated in the contract was $21,000.00; a change order was executed on November 4, 1997, for an additional price of $2,890.00. Pool Masters represented to Mr. Santibanez and Mr. Pappas that it was a licensed swimming pool contractor. Pool Masters began work on the pool on or about May 17, 1997. Mr. Santibanez and Mr. Pappas made payments to Pool Masters pursuant to the contract, and Pool Masters excavated the hole for the pool, put in the foundation, and poured the concrete. Pool Masters ceased work on the swimming pool in late November 1997, after the concrete was poured. A week later, Mr. Santibanez heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. Santibanez and Mr. Pappas had paid Pool Masters a total of $19,690.00 for work done pursuant to the contract and change order. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. At least one lien was filed against Mr. Santibanez's and Mr. Pappas's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Santibanez and Mr. Pappas submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Santibanez and Mr. Pappas to file suit against Pool Masters. Mr. Santibanez and Mr. Pappas filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Santibanez and Mr. Pappas alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 3/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 4/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 5/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 6/ ] Mr. Santibanez and Mr. Pappas further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $17,975.50, and they included in the complaint an itemized list of expenditures to support their claim. The circuit court entered a Default Final Judgment on August 4, 1998, awarding Mr. Santibanez and Mr. Pappas $17,675.50, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Santibanez and Mr. Pappas submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Santibanez and Mr. Pappas did not receive any funds from the bankruptcy estate or any other source to satisfy the judgment against Pool Masters. Mr. Santibanez and Mr. Pappas satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $17,675.50. DOAH Case No. 99-1666: Klaus and Lucrecia Mueller Klaus and Lucrecia Mueller entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about February 24, 1997. The total price stated in the contract was $16,400.00. Pool Masters represented to Mr. and Mrs. Mueller that it was a licensed swimming pool contractor. Pool Masters began work on the pool in Spring 1997, and Mr. and Mrs. Mueller made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool, installed the steel frame, poured gunnite at the shallow end of the pool, and installed the brick and tile around the pool. Pool Masters last worked on the swimming pool in late November 1997. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Mueller had paid Pool Masters approximately $12,900.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Mueller's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Mueller submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Mueller to file suit against Pool Masters. Mr. and Mrs. Mueller filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Mueller alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 7/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 8/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 9/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 10/ ] Mr. and Mrs. Mueller further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,299.51. The matter was presented to the circuit court, ex parte, upon Mr. and Mrs. Mueller's Motion for Default Final Judgment. The court entered a Default Final Judgment in June 1998, awarding Mr. and Mrs. Mueller $13,299.51, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated June 23, 1998, Mr. and Mrs. Mueller submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Mueller did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Mueller satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $13,299.51. DOAH Case No. 99-1667: Mario and Martha Alboniga Mario and Martha Alboniga entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 17, 1997. The total price stated in the contract was $24,000.00. Pool Masters represented to Mr. and Mrs. Alboniga that it was a licensed swimming pool contractor. Pool Masters began work on the pool on November 10, 1997, and Mr. and Mrs. Alboniga made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and poured the concrete form of the pool. The last day Pool Masters worked on the swimming pool was November 19, 1997. Mr. and Mrs. Alboniga later heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Alboniga had paid Pool Masters a total of $15,200.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Alboniga’s property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Alboniga submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Alboniga to file suit against Pool Masters. Mr. and Mrs. Alboniga filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Alboniga alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 11/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 12/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 13/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 14/ ] Mr. and Mrs. Alboniga further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $10,541.77. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. and Mrs. Alboniga $10,541.77, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. and Mrs. Alboniga submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Alboniga did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Alboniga satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $10,541.77. DOAH Case No. 99-1668: Salvator Militello and Sharon Sidorski Salvator Militello and Sharon Sidorski entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about April 6, 1997. The total price stated in the contract was $24,295.00. Pool Masters represented to Mr. Militello and Ms. Sidorski that it was a licensed swimming pool contractor. Mr. Militello and Ms. Sidorski made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and spa, installed basic plumbing, and poured the concrete for the pool. Pool Masters last worked on the swimming pool in October 1997. At the time Pool Masters ceased work on the pool, Mr. Militello and Ms. Sidorski had paid Pool Masters $19,389.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. Militello's and Ms. Sidorski's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Militello and Ms. Sidorski submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Militello and Ms. Sidorski to file suit against Pool Masters. Mr. Militello and Ms. Sidorski filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Militello and Ms. Sidorski alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 15/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 16/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 17/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 18/ ] Mr. Militello and Ms. Sidorski further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,544.00 and that they paid $1,641.68 to satisfy liens and unpaid subcontractors and materialmen, for total damages of $15,185.68. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. Militello and Ms. Sidorski $15,185.68, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Militello and Ms. Sidorski submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Militello and Ms. Sidorski did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. Militello and Ms. Sidorski satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $15,185.68. DOAH Case No. 00-0024: Jack and Paula Tieger Jack and Paula Tieger entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about December 17, 1995. The total price stated in the contract was $28,200.00. Pursuant to the contract, Pool Masters built a pool and screen enclosure, and Mr. and Mrs. Tieger paid Pool Masters the price specified in the contract. Mr. and Mrs. Tieger were not, however, satisfied with the work done by Pool Masters, and, in or around 1997, they filed a complaint for breach of contract against Pool Masters in the Circuit Court of the Seventeenth Judicial Circuit, in Broward County, Florida. In the complaint, Mr. and Mrs. Tieger alleged that Pool Masters had breached the contract: By failing to adequately explain the technical terms used in the Agreement to the TIEGERS; By failing to install a vacuum line with valve as specified in the Agreement; By failing to install anti-corrosive handrails in the swimming pool; By failing to properly install and/or provide a properly functioning waterfall as specified in the Agreement; By failing to properly fill the area behind the waterfall; By unilaterally, and or the TIEGERS' [sic] objection, placing a tile with the "Pool Masters" logo on the steps heading into the pool: By failing to re-route the TIEGERS' [sic] sprinkler system in a timely manner; By failing to advise the TIEGERS that they were going to need to pay for and install a separate circuit breaker box as part of the installation of the swimming pool; and By failing to install the second screen door as specified in the Agreement. Mr. and Mrs. Tieger did not identify the amount of damages they allegedly suffered as a result of Pool Masters's alleged breach of contract. Mr. and Mrs. Tieger were not aware that Pool Masters had declared bankruptcy until January 1998, when Mrs. Tieger went to Pool Masters' office and found the notice on the door. A non-jury trial was held before the circuit court on March 5, 1998; Pool Masters did not attend the trial. In a Final Judgment entered on March 25, 1998, the court awarded Mr. and Mrs. Tieger $4,200 as compensatory damages to be recovered from Pool Masters. In a Proof of Claim dated May 13, 1998, and filed with the United States Bankruptcy Court of the Southern District of Florida, Mr. and Mrs. Tieger submitted an unsecured claim against Pool Masters' bankruptcy estate in the amount of $7,300.00, which represented the compensatory damages awarded in the final judgment, together with attorney's fees and costs. Mr. and Mrs. Tieger have not collected any portion of their judgment against Pool Masters. Mr. and Mrs. Tieger submitted to the Board a Construction Industries Recovery Fund Claim Form dated December 5, 1998, and the Board awarded Mr. and Mrs. Tieger $800.00, representing the cost of the vacuum line with valve and the second screen door which Pool Masters had not installed. Mr. and Mrs. Tieger do not satisfy the statutory criteria for eligibility for payment from the Fund. Mr. and Mrs. Tieger failed to establish that they filed their claim with the Board within two years of the date they discovered the alleged deficiencies in the pool, and they failed to establish that the final judgment against Pool Masters was based on a violation of Section 489.129(1)(g), (j), or (k), Florida Statutes (Supp. 1998). The evidence presented herein is not sufficient to establish that Mr. Kiselius is the licensee against whom the claimants obtained final judgments.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, 25/ it is RECOMMENDED that the Construction Industry Licensing Board: Enter final orders as follows: In DOAH Case No. 99-1665, finding Eugene Santibanez and Alexander Pappas eligible for payment from the Fund in the amount of $17,675.00, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1666, finding Klaus and Lucrecia Mueller eligible for payment from the Fund in the amount of $13,299.51, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1667, finding Mario and Martha Alboniga eligible for payment from the Fund in the amount of $10,541.77, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1668, finding Salvator Militello and Sharon Sidorski eligible for payment from the Fund in the amount of $15,185.68, in satisfaction of a final judgment against Pool Masters, Inc.; and In DOAH Case No. 00-0024, dismissing the claim of Jack and Linda Tieger for payment from the Fund. Determine that Christopher P. Kiselius is not the "licensee" whose license is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998), as a result of payments to the claimants in DOAH Case Nos. 99- 1665, 99-1666, 99-1667, and 99-1668. DONE AND ENTERED this 31st day of August, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2000.

Florida Laws (11) 120.569120.57455.225489.105489.119489.1195489.129489.140489.141489.143641.68
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STUART L. REISE, 87-003955 (1987)
Division of Administrative Hearings, Florida Number: 87-003955 Latest Update: Sep. 19, 1988

The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.

Florida Laws (4) 120.57489.105489.119489.129
# 3
JOHN MORRIS vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 80-001562 (1980)
Division of Administrative Hearings, Florida Number: 80-001562 Latest Update: Nov. 11, 1980

Findings Of Fact In 1975 and 1976 John Morris, d/b/a Morris Pool Service, maintained the swimming pool at the Sunland Center in Miami, Florida under a contract with HRS. The contract for the year commencing July 1, 1976 and expiring June 30, 1977 (Exhibit 1) provided generally for Morris to maintain the Sunland Center pool for which he would be paid $520 per month. This contract further provided that a representative of Morris Pool Service check each day except Saturday and Sunday with Ms. O'Donohue, the Director of Training, or her successor. Recreation personnel at Sunland Center hoped to open the pool on Memorial Day; however, an impeller for the pump needed replacement and the pool was inoperative for some six weeks in May and June awaiting this part. During this time petitioner did little or no maintenance and the pool's condition was bad enough for the Superintendent to become involved and request a report from the Programs and Services Director (Exhibit 4). When the impeller did arrive in mid-June, 1977, the pool was in such bad shape it was necessary to drain the pool, scrub, and acid-wash the walls and floor of the pool to remove the accumulated algae and scum. Even a colony of frogs had taken up residence in the pool during this period. As a result of additional delays the next hoped-for opening date of July 4 was also missed. The pool was finally ready for operation and was opened the week following July 4, 1977. Although opened the water in the pool was not properly maintained by cleaning and chlorinating. In the latter part of July the gas chlorinator became inoperative and the pool's condition deteriorated as no chlorine was being added to the water. Under the contract Petitioner was to provide materials necessary to keep the pool water in a balanced condition. This contract expired on June 30, 1977. Nevertheless, Petitioner purported to continue working under the expired contract, pending the issuance of a new contract for 1977-1978. While the gas chlorinator was inoperative Petitioner did not hand-feed chlorine to the pool to maintain the proper chlorine level and to keep algae from growing. By early August, 1977, the pool had become so bad the supervisory personnel at Sunland Center called the Dade County Health Department to inspect the pool. A report of that inspection showing the pool unfit for use was admitted into evidence as Exhibit 3. Following the Superintendent's inquiry to Ms. Titus about the condition of the pool in June, 1977, she contacted Petitioner, who told her the pool would he hack in operation as soon as the impeller was received. Ms. Titus was the successor to Ms. O'Donohue and she told Petitioner to keep her advised regarding the status of the pool. Although the contract (Exhibit 1) required Petitioner to report to Ms. Titus daily (except Saturday and Sunday) she did not see him again, nor did she receive any report that he came to her office. Petitioner contends that he attempted to report to Ms. Titus but was unable to find her in her office and after a few attempts stopped trying. Ms. Titus and her assistant were both equipped with beepers and could be contacted any time of day by their office if they were out of the office. Following the Health Department's inspection on August 9, 1977, the pool was closed for several days, then reopened around mid-August after the chlorinator was repaired. When the pool was reopened in August its condition was barely satisfactory. Shortly after Labor Day the pool was again closed and remained closed throughout the balance of 1977. By October, the Sunland Center officials decided they should notify Petitioner that his contract would not be renewed for the 1977-1978 year and a letter dated October 27, 1977 (Exhibit 2) was forwarded to him by registered mail. This letter was mailed to an old address for Petitioner, was returned to the sender and remailed to the proper address. As a result, the letter was not received by Petitioner until December 14 or 15, 1977. Petitioner submitted bills to Respondent for services for the period July 1, 1977 through December 15, 1977, the approximate date he received Exhibit 2. Following August 10, 1977 some of Respondent's employees in the maintenance department saw Petitioner in the cafeteria at Sunland Center and on the premises, but none of them reported seeing Petitioner do any work on the pool. Petitioner contends he worked on the pool on a daily basis, however, the condition of the pool casts serious doubts on this testimony.

# 4
CHRISTOPHER P. KISELIUS vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD, 99-001665 (1999)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 07, 1999 Number: 99-001665 Latest Update: Jul. 15, 2004

The Issue Whether the claimants herein are entitled to payment from the Construction Industries Recovery Fund and, if so, the amount of the payment to which each claimant is entitled. Whether the license of the Petitioner is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998).

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Fund is established by Section 489.140, Florida Statutes, for the purpose of reimbursing those persons who meet the eligibility requirements set forth in Section 489.141, Florida Statutes. The Board is the entity responsible for reviewing applications for payment from the Fund and entering orders approving or disapproving the applications. Sections 489.140(1) and 489.143(1), Florida Statutes. Mr. Kiselius is a licensed residential pool/spa contractor, having been first issued such a license in 1984. Mr. Kiselius's license is currently on inactive status, but at the times material to this action, Mr. Kiselius's license was active. Pool Masters was a Florida corporation incorporated on August 10, 1995. Frederick H. Martin and Abraham Zafrani were the sole shareholders of the corporation, and Mr. Martin was the President and Secretary of the corporation, and Mr. Zafrani was the Vice-President and Treasurer. From on or about October 24, 1995, until November 14, 1997, Mr. Kiselius was the qualifying agent for Pool Masters. The record does not reflect the date on which Pool Masters was issued its certificate of authority allowing it to engage in contracting as a business organization, but it was assigned Qualified Business Organization License Number QB0002327 on or about November 6, 1996. Pool Masters filed for bankruptcy pursuant to Chapter 7 of the United States Bankruptcy Code on January 1, 1998, and the corporation was administratively dissolved on October 16, 1998. DOAH Case No. 99-1665: Santibanez and Pappas Eugene Santibanez and Alexander Pappas entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 25, 1997. The total price stated in the contract was $21,000.00; a change order was executed on November 4, 1997, for an additional price of $2,890.00. Pool Masters represented to Mr. Santibanez and Mr. Pappas that it was a licensed swimming pool contractor. Pool Masters began work on the pool on or about May 17, 1997. Mr. Santibanez and Mr. Pappas made payments to Pool Masters pursuant to the contract, and Pool Masters excavated the hole for the pool, put in the foundation, and poured the concrete. Pool Masters ceased work on the swimming pool in late November 1997, after the concrete was poured. A week later, Mr. Santibanez heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. Santibanez and Mr. Pappas had paid Pool Masters a total of $19,690.00 for work done pursuant to the contract and change order. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. At least one lien was filed against Mr. Santibanez's and Mr. Pappas's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Santibanez and Mr. Pappas submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Santibanez and Mr. Pappas to file suit against Pool Masters. Mr. Santibanez and Mr. Pappas filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Santibanez and Mr. Pappas alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 3/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 4/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 5/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 6/ ] Mr. Santibanez and Mr. Pappas further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $17,975.50, and they included in the complaint an itemized list of expenditures to support their claim. The circuit court entered a Default Final Judgment on August 4, 1998, awarding Mr. Santibanez and Mr. Pappas $17,675.50, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Santibanez and Mr. Pappas submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Santibanez and Mr. Pappas did not receive any funds from the bankruptcy estate or any other source to satisfy the judgment against Pool Masters. Mr. Santibanez and Mr. Pappas satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $17,675.50. DOAH Case No. 99-1666: Klaus and Lucrecia Mueller Klaus and Lucrecia Mueller entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about February 24, 1997. The total price stated in the contract was $16,400.00. Pool Masters represented to Mr. and Mrs. Mueller that it was a licensed swimming pool contractor. Pool Masters began work on the pool in Spring 1997, and Mr. and Mrs. Mueller made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool, installed the steel frame, poured gunnite at the shallow end of the pool, and installed the brick and tile around the pool. Pool Masters last worked on the swimming pool in late November 1997. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Mueller had paid Pool Masters approximately $12,900.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Mueller's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Mueller submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Mueller to file suit against Pool Masters. Mr. and Mrs. Mueller filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Mueller alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 7/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 8/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 9/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 10/ ] Mr. and Mrs. Mueller further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,299.51. The matter was presented to the circuit court, ex parte, upon Mr. and Mrs. Mueller's Motion for Default Final Judgment. The court entered a Default Final Judgment in June 1998, awarding Mr. and Mrs. Mueller $13,299.51, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated June 23, 1998, Mr. and Mrs. Mueller submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Mueller did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Mueller satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $13,299.51. DOAH Case No. 99-1667: Mario and Martha Alboniga Mario and Martha Alboniga entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 17, 1997. The total price stated in the contract was $24,000.00. Pool Masters represented to Mr. and Mrs. Alboniga that it was a licensed swimming pool contractor. Pool Masters began work on the pool on November 10, 1997, and Mr. and Mrs. Alboniga made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and poured the concrete form of the pool. The last day Pool Masters worked on the swimming pool was November 19, 1997. Mr. and Mrs. Alboniga later heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Alboniga had paid Pool Masters a total of $15,200.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Alboniga’s property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Alboniga submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Alboniga to file suit against Pool Masters. Mr. and Mrs. Alboniga filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Alboniga alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 11/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 12/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 13/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 14/ ] Mr. and Mrs. Alboniga further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $10,541.77. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. and Mrs. Alboniga $10,541.77, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. and Mrs. Alboniga submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Alboniga did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Alboniga satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $10,541.77. DOAH Case No. 99-1668: Salvator Militello and Sharon Sidorski Salvator Militello and Sharon Sidorski entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about April 6, 1997. The total price stated in the contract was $24,295.00. Pool Masters represented to Mr. Militello and Ms. Sidorski that it was a licensed swimming pool contractor. Mr. Militello and Ms. Sidorski made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and spa, installed basic plumbing, and poured the concrete for the pool. Pool Masters last worked on the swimming pool in October 1997. At the time Pool Masters ceased work on the pool, Mr. Militello and Ms. Sidorski had paid Pool Masters $19,389.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. Militello's and Ms. Sidorski's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Militello and Ms. Sidorski submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Militello and Ms. Sidorski to file suit against Pool Masters. Mr. Militello and Ms. Sidorski filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Militello and Ms. Sidorski alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 15/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 16/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 17/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 18/ ] Mr. Militello and Ms. Sidorski further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,544.00 and that they paid $1,641.68 to satisfy liens and unpaid subcontractors and materialmen, for total damages of $15,185.68. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. Militello and Ms. Sidorski $15,185.68, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Militello and Ms. Sidorski submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Militello and Ms. Sidorski did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. Militello and Ms. Sidorski satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $15,185.68. DOAH Case No. 00-0024: Jack and Paula Tieger Jack and Paula Tieger entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about December 17, 1995. The total price stated in the contract was $28,200.00. Pursuant to the contract, Pool Masters built a pool and screen enclosure, and Mr. and Mrs. Tieger paid Pool Masters the price specified in the contract. Mr. and Mrs. Tieger were not, however, satisfied with the work done by Pool Masters, and, in or around 1997, they filed a complaint for breach of contract against Pool Masters in the Circuit Court of the Seventeenth Judicial Circuit, in Broward County, Florida. In the complaint, Mr. and Mrs. Tieger alleged that Pool Masters had breached the contract: By failing to adequately explain the technical terms used in the Agreement to the TIEGERS; By failing to install a vacuum line with valve as specified in the Agreement; By failing to install anti-corrosive handrails in the swimming pool; By failing to properly install and/or provide a properly functioning waterfall as specified in the Agreement; By failing to properly fill the area behind the waterfall; By unilaterally, and or the TIEGERS' [sic] objection, placing a tile with the "Pool Masters" logo on the steps heading into the pool: By failing to re-route the TIEGERS' [sic] sprinkler system in a timely manner; By failing to advise the TIEGERS that they were going to need to pay for and install a separate circuit breaker box as part of the installation of the swimming pool; and By failing to install the second screen door as specified in the Agreement. Mr. and Mrs. Tieger did not identify the amount of damages they allegedly suffered as a result of Pool Masters's alleged breach of contract. Mr. and Mrs. Tieger were not aware that Pool Masters had declared bankruptcy until January 1998, when Mrs. Tieger went to Pool Masters' office and found the notice on the door. A non-jury trial was held before the circuit court on March 5, 1998; Pool Masters did not attend the trial. In a Final Judgment entered on March 25, 1998, the court awarded Mr. and Mrs. Tieger $4,200 as compensatory damages to be recovered from Pool Masters. In a Proof of Claim dated May 13, 1998, and filed with the United States Bankruptcy Court of the Southern District of Florida, Mr. and Mrs. Tieger submitted an unsecured claim against Pool Masters' bankruptcy estate in the amount of $7,300.00, which represented the compensatory damages awarded in the final judgment, together with attorney's fees and costs. Mr. and Mrs. Tieger have not collected any portion of their judgment against Pool Masters. Mr. and Mrs. Tieger submitted to the Board a Construction Industries Recovery Fund Claim Form dated December 5, 1998, and the Board awarded Mr. and Mrs. Tieger $800.00, representing the cost of the vacuum line with valve and the second screen door which Pool Masters had not installed. Mr. and Mrs. Tieger do not satisfy the statutory criteria for eligibility for payment from the Fund. Mr. and Mrs. Tieger failed to establish that they filed their claim with the Board within two years of the date they discovered the alleged deficiencies in the pool, and they failed to establish that the final judgment against Pool Masters was based on a violation of Section 489.129(1)(g), (j), or (k), Florida Statutes (Supp. 1998). The evidence presented herein is not sufficient to establish that Mr. Kiselius is the licensee against whom the claimants obtained final judgments.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, 25/ it is RECOMMENDED that the Construction Industry Licensing Board: Enter final orders as follows: In DOAH Case No. 99-1665, finding Eugene Santibanez and Alexander Pappas eligible for payment from the Fund in the amount of $17,675.00, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1666, finding Klaus and Lucrecia Mueller eligible for payment from the Fund in the amount of $13,299.51, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1667, finding Mario and Martha Alboniga eligible for payment from the Fund in the amount of $10,541.77, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1668, finding Salvator Militello and Sharon Sidorski eligible for payment from the Fund in the amount of $15,185.68, in satisfaction of a final judgment against Pool Masters, Inc.; and In DOAH Case No. 00-0024, dismissing the claim of Jack and Linda Tieger for payment from the Fund. Determine that Christopher P. Kiselius is not the "licensee" whose license is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998), as a result of payments to the claimants in DOAH Case Nos. 99- 1665, 99-1666, 99-1667, and 99-1668. DONE AND ENTERED this 31st day of August, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2000.

Florida Laws (11) 120.569120.57455.225489.105489.119489.1195489.129489.140489.141489.143641.68
# 5
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs MICHAEL E. SEAMON, 16-002845PL (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 23, 2016 Number: 16-002845PL Latest Update: Mar. 29, 2017

The Issue Whether Respondent practiced beyond the scope of his certified commercial pool/spa contractor’s license and proceeded on a job without obtaining applicable local building department permits and inspections, as alleged in the Amended Administrative Complaint and, if so, the nature of the sanctions to be imposed.

Findings Of Fact Petitioner is the state agency charged with the licensing and regulation of the construction industry, including pool and spa contractors and electrical contractors, pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. At all times material to the allegations in the Administrative Complaint, Respondent was licensed as a commercial pool/spa contractor in the State of Florida, having been issued license numbers CPC 05661, 1457406, and 1458031. Respondent was the primary qualifying agent of Cox Building Corporation, d/b/a Cox Pools (Cox Pools). Respondent has been registered, certified, or licensed as a swimming pool contractor since 1978. Over the course of his almost 40 years as a swimming pool contractor, Respondent has replaced thousands of pool lights and pool pumps. He believed that the replacement of pool equipment, which he understood to include pool lights, was within the allowable scope of work as a swimming pool contractor. On or about September 12, 2014, Cox Pools entered into a contract with John Patronis to replace four pool light fixtures, a booster pump, and other miscellaneous services for $4,681.17 at the Subject Property. The Subject Property falls within the jurisdiction of the Bay County Building Department. Respondent did not obtain an electrical permit for replacing the pool light fixtures at Subject Property. Mr. Carnley testified that the Bay County Building Department requires that pool light replacement be performed by a licensed electrician, and with a county-issued electrical permit. The permit must be obtained by an electrical contractor or a homeowner. Bay County would not have issued a permit to Respondent, because he was not an electrical contractor. The Bay County Building Department also requires an electrical permit for the replacement of a circuit breaker in the electrical box serving a swimming pool. A pool contractor is not authorized to replace circuit breakers. No permits were obtained to replace circuit breakers at the Subject Property. On September 15, 2014, during the course of replacing the pool light fixtures, an employee of Cox Pools, Joshua Cook, was electrocuted. The precise cause of the electrocution was not established, though no plausible basis exists for it being related to anything other than the replacement of the pool lights. After a period of several days following the accident involving Mr. Cook, Respondent returned to the Subject Property to complete the job. He personally went into the pool, put the light in the fixture and screwed it in, and left. The light was thereafter wired and energized by a Cox Pool service technician. Given the circumstances, Mr. Patronis was not asked to complete payment for the services performed. Nonetheless, it is clear that, but for the accident, Mr. Patronis would have been expected to pay for the services for which he contracted. The photographic evidence in this case demonstrates that between September 15, 2014, and some indeterminate time in 2016, a circuit breaker was replaced in the electrical box serving the Subject Property’s pool. The circuit breaker that existed on September 15, 2014, was a ground-fault circuit interrupter (GFCI). By 2016, the GFCI has been replaced with an arc-fault circuit interrupter (AFCI). Had Bay County performed an inspection of the electrical box with the AFCI, it would not have passed inspection. Respondent testified that he did not change the circuit breaker, that Cox Pools keeps no inventory of circuit breakers, and that service technicians do not carry circuit breakers on the trucks. Respondent acknowledged his understanding that replacing a circuit breaker is a job for an electrical contractor. At some time “recently,” Williams Electric was called to the Subject Property, at which time Mr. Williams “swapped out a breaker or two that was an incorrect type of breaker for the application.” Mr. Patronis was not clear whether an arc breaker was replaced with a ground breaker, or vice versa. Pool lights are sealed units. The light and its power cord come as a single unit. To replace a pool light, the main circuit breaker at the swimming pool sub-panel is turned off. The wires to the existing light are disconnected (unscrewed) from the circuit breaker. A lead is tied to the end of the wire. The light fixture is removed from the pool opening, and the wire is pulled through the existing conduit from the pool side. When the old fixture and wiring unit has been removed, the lead is removed from the end of the old unit’s wire, tied to the wiring of the new light, and drawn back through the conduit to the circuit breaker box. The new light is screwed into the fixture, and then energized by connecting the wires back into the existing circuit breaker. The point of connection of the light to the circuit breaker is the “load side” of the circuit. The experts who testified in this proceeding were all competent and qualified in their fields, and had served in leadership positions with the CILB (Mr. Weller, Mr. Del Vecchio, and Mr. Lenois), the Electrical Contracting Licensing Board (Mr. Tibbs), or the Florida Swimming Pool Association (Mr. Garner and Mr. Pruette). However, despite the relative simplicity of the statutes at issue, their opinions as to the allowable scope of work under a swimming pool contractor license were at odds. Respondent acknowledged, and the evidence in this case establishes, that electrical work associated with new pool construction is a task that is within the scope of work of an electrical contractor. Initial construction involves substantial work in bringing power from the main residential panel to the new pool panel, installing a junction box and circuit breakers, installing the wiring, and performing other electrical work of significantly greater complexity than that involved in the installation of equipment into a pre-constructed electrical system, which involves only the disconnect and reconnect of wires to the load side of a circuit breaker. As discussed by Mr. Lenois, a pool contractor can contract for the entire pool, but cannot self-perform the electrical components pursuant to section 489.113. As to the replacement of existing equipment, Petitioner’s experts testified that pool light fixtures differ from other pool-related equipment, e.g., pool pumps, in that the light fixtures have direct contact with the water, whereas other components do not. Lights are changed out in a submerged condition, which makes them extremely dangerous. As stated by Mr. Weller, “the whole area of electricity around pools gets complicated, between the bonding, the grounding, and all the other stuff.” It was Mr. Weller’s opinion that, although pool contractors can contract for pool light replacement, they cannot self-perform the work. Rather, the electrical work involved in replacing pool light fixtures should be subcontracted to an electrical contractor because “you can make mistakes in plumbing, and you can make mistakes in other areas, but with electricity, it's pretty non-forgiving, especially if you're around water.” Mr. Lenois distinguished pool lights, which he characterized as accessories since all pools do not have them, from pool equipment, which includes pumps and filters, heaters, specialty filters, and salt generators, which are mounted at the pump and filter area. Respondent’s experts were uniform in their opinions that the act of disconnecting and reconnecting pool lights, as well as other pool equipment, at the load side of a breaker does not constitute electrical contracting. Mr. Pruette testified that disconnecting and connecting a pool light at a circuit breaker is not a difficult or complex task, and can be easily performed with a little training. Mr. Del Vecchio testified that the disconnection and connection of pool lights at the circuit breaker is no different than that performed by a plumber in replacing a hot water heater, or an air-conditioning contractor in replacing a piece of air-conditioning equipment. Almost all of the experts either replaced pool lights as part of their routine scope of work or knew of pool contractors who did so, a practice that appears to be commonplace. Furthermore, several of the witnesses worked in areas of the state in which county building officials did not require permits, electrical or otherwise, for the replacement of pool lights, though the evidence in that regard was generally hearsay. Mr. Lenois, who testified on Petitioner’s behalf, stated his opinion that reasonable people could differ as to the meaning of the statutory language placing the “installation, repair, or replacement of existing equipment” within the scope of work of a pool/spa contractor. The issue of the extent to which electrical work is subsumed within the statutory scope of work of a pool/spa contractor of “installation, repair, or replacement of existing equipment” has been the topic of considerable discussion in the industry. In that regard, the Florida Pool and Spa Association has filed a Petition to Initiate Rulemaking with the CILB seeking, among other things, to “clarify[] the scope of a certified pool contractor’s license to include the installation, repair, and replacement of pool equipment, up to and including the electrical connection on the demand side of the power source.” There was no evidence as to the disposition of the petition. Respondent argued that Florida Administrative Code Rule 61G4-16.001(9), which establishes that five percent of the written certification exam for commercial pool/spa contractors is to cover “electrical work,” is evidence that electrical work is within the scope of work for a pool contractor. Electrical work associated with pool construction includes grounding for the pool shell itself. Thus, a degree of knowledge of basic electrical work and codes would be warranted, regardless of whether equipment electrical connections are within the scope of work for a pool/spa contractor. The parties introduced a series of DBPR-approved course outlines and instructor applications for a three-hour class, sponsored by the Florida Pool and Spa Association, entitled “Basic Electricity and the NEC [National Electric Code] for Swimming Pools,” and a one-hour class, sponsored by the Florida Pool and Spa Association, entitled “Basic Electrical Requirements for Pools.” The course outline prepared by the Florida Pool and Spa Association for each of the approved courses provides, in bold font, that: Instructor is aware that electrical work does not fall within the scope of work of licensed pool/spa contractors. No instruction on how to perform electrical work will take place. Course will provide much needed understanding of the basics of electricity as well as those aspects of the NEC as they pertain to pools and spas. Instructor will also emphasize the importance of using a licensed electrical contractor to perform required work.

Recommendation Upon consideration of the facts found and conclusions of law reached, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order finding that Respondent violated section 489.129(1)(o), Florida Statutes, as alleged in Count One; and sections 455.227(1)(o) and 489.129(1)(c), Florida Statutes, as alleged in Count Two, but only as that count pertains to the replacement of pool lights. It is further recommended that: Respondent be subject to a fine of $1,000 for a first violation of section 489.129(1)(o); Respondent be subject to a fine of $4,000, and that Respondent’s commercial pool/spa contractor licenses be subject to a period of probation for two years for a first violation of section 455.227(1)(o) and section 489.129(1)(c); and Respondent be required to complete an approved, live seven-hour continuing education course, in addition to any otherwise required continuing education, with an emphasis on chapter 489 and the rules enacted pursuant thereto. DONE AND ENTERED this 5th day of October, 2016, in Tallahassee, Leon County, Florida. S E. GARY EARLY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of October, 2016.

Florida Laws (15) 120.52120.56120.565120.569120.57120.6817.00120.165455.227455.2273489.105489.113489.117489.1195489.129 Florida Administrative Code (1) 61G4-18.001
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CRAWFORD L. GROVE, D/B/A ATLAS POOLS, INC., 79-002058 (1979)
Division of Administrative Hearings, Florida Number: 79-002058 Latest Update: Mar. 17, 1981

Findings Of Fact Atlas Pools, Inc., contracted with Mr. and Mrs. Jerry Thompson in May, 1978, to construct a swimming pool on the Thompson property for a completed price of $5,940. Work ceased in mid-July, 1978, by which time the Thompsons had paid Atlas Pools $5,643. The Thompsons hired another pool contractor to complete the project at additional cost in excess of $2,000. Atlas Pools contracted with Mr. and Mrs. Dennis Perry in June, 1978, to construct a swimming pool on the Perry property for a completed cost of $5,770. Work ceased in late July, 1978, after the Perrys had paid Atlas Pools $5,474.50. The Perrys completed the project through self-help and use of another pool contractor at a further cost of $1,566. Atlas Pools contracted with Mr. and Mrs. Thomas Wolters in June, 1978, to construct a swimming pool on the Wolters' property for a completed cost of $6,980. Work ceased in mid-July, 1978, after the Wolters had paid Atlas Pools $6,631. The Wolters completed the pool through self help at an additional cost in excess of $1,300. Atlas Pools contracted with Mr. and Mrs. Albert Sentman in June, 1978, to construct a spa on the Sentman property for a completed cost of $5,500. The Sentmans paid Atlas Pools a $550 deposit after which the spa was delivered but not installed. The Sentmans completed the project by other means at an additional cost of $6,137. Respondent abandoned each of the above projects without notice to the customer, who ultimately learned of the company's bankruptcy from a third party source. Each of the four projects described above was completed at a final cost to the purchaser in excess of $900 over the contract price. The company filed a Voluntary Petition of Bankruptcy with the U.S. District Court, Middle District of Florida, on August 1, 1978. Thereafter, on March 7, 1979, the Brevard County Contractors Licensing Board revoked the certificate held by Atlas Pools for a minimum period of one year, with the requirement that financial rehabilitation be demonstrated as a condition of reinstatement. At the time of bankruptcy, Respondent was president of Atlas Pools, Inc., and owned one-third of the stock. He was, at all times relevant to this proceeding, the company's only licensed pool contractor. He is currently employed in pool construction work by a licensed contractor. Proposed findings of fact were submitted by the parties. To the extent these proposed findings have not been adopted herein or are inconsistent with the above findings, they have been specifically rejected as irrelevant or not supported by the evidence.

Recommendation Based on the foregoing, it is RECOMMENDED: That Pool Contractor's License No. RP 0018040 issued to Crawford L. Grove, be suspended until Respondent demonstrates compliance with the financial responsibility standards established by Section 489.115, Florida Statutes (1979). DONE AND ENTERED this 29th day of October, 1980, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 29th day of October, 1980.

Florida Laws (4) 120.57489.101489.115489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs DONALD F. COLOMBO, 90-005357 (1990)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Aug. 29, 1990 Number: 90-005357 Latest Update: Mar. 07, 1991

Findings Of Fact Petitioner, in conjunction with the Construction Industry Licensing Board, is the state agency charged with the responsibility to prosecute administrative complaints pursuant to Chapters 120, 455 and 489, Florida Statutes and rules and regulations promulgated thereunder. During times material, Respondent, Donald F. Colombo, was licensed as a certified pool contractor in Florida, having been issued license number CP 15343. During times material, Respondent's license was registered with Petitioner as the qualifying agent for National and Spa Builders, Inc. (National). On or about May 27, 1988, National, the entity which Respondent was the qualifying agent, contracted with Diane and Leonard Cline to construct a pool at the Cline's residence in Tarpon Springs, Florida, for the contract price of $9825.00. The Clines financed the construction of the pool by placing a security interest against their property for the full purchase price of the pool. The full contract price of $9825.00 was paid to National and after National completed approximately 40% of the pool construction, National abandoned the project without notice or just cause. National never completed construction of the pool and the Clines obtained a homeowner's building permit and completed the pool project at an additional cost of approximately $5,000.00. Additionally, liens were filed against the property of the Clines by Florida Mining and Materials Concrete Corporation in the amount of $682.00 and Jim's Custom Pool Work in the amount of $135.00. The above-referred liens were for work performed and/or materials supplied in the construction of the Cline pool project by National. On or about May 20, 1988, National entered into a contract with Ben and Linda Thomas to construct a pool at their residence in Lutz, Florida, for the contract price of $9000.00. Following commencement of construction, National received approximately 60% of the contract price ($5,400.00) and later abandoned the project without notification or just cause to the Thomas's. The Thomas's subsequently completed their pool at an additional cost of approximately $1,000.00 over and above National's original contract price. On or about January 11, 1989, Respondent was disciplined by the Hillsborough County Building Department, Building Board of Adjustments, Appeals and Examiners for alleged violation of local laws including abandoning a construction project; alleged willful and deliberate disregard of applicable building codes; allegedly allowing liens to be filed against a project for which he was the contractor and for allegedly diverting funds from a construction project. Respondent was assessed an administrative penalty of a 30-day suspension of his permitting privileges by the Hillsborough County Building Department. Respondent was the qualifying agent for National during the 90-day period commencing April 1 through June 30,1988. Respondent formally terminated his status as qualifying agent for National and also tendered his resignation from that entity based on difficulties that he ecountered respecting his attempts to serve as qualifier to include his inability to control the finances, to be kept apprised of accounts receivable, accounts payable, an inability to select contractors and material suppliers and to assure that the payments for such services were timely remitted. Prior to Respondent's engagement with National as a pool salesman and later as qualifier, National was a well reputed pool company, having been in existence in excess of twelve years. National annually constructed approximately 750 pools with accounts receivable in the $10 to $12 million dollar range. Prior to April 1988, National was a secure and stable company that regularly paid its bills and grew at a rapid pace. While engaged with National, Respondent was unaware that there was internal collusion among its owners respecting diversion of funds. Respondent repeatedly attempted to gather a handle on the internal financial operations of the company and on each occasion he was rebuffed. within the first month that Respondent qualified National, he began to seek advice as to the proper means of salvaging his license by contacting a local attorney, the local office of Petitioner, and Petitioner's headquarters in Tallahassee seeking the proper procedures for ending his relationship with National. This came about once it became apparent that he was unable to effectively manage or otherwise perform the functions of a qualifying agent. Respondent formally severed his relationship as qualifying agent for National on June 30, 1988. Subsequent to ending his status as qualifying agent for National, Respondent assisted the Clines in the completion of their pool. Mr. Cline specifically recalled that Respondent assisted him in locating other subcontractors and with the purchase of plumbing supplies for his pool without remuneration from the Clines. (Petitioner's Exhibit 1F; Tr. 30-32.) Likewise, Respondent also assisted the Thomas's in completing their pool. (Tr. 45, lines 23-24.) Respondent demonstrated compassion and a proper concern which was evident based on the testimony of the complaining witnesses who appeared at the formal hearing. Significantly, Petitioner's investigator, H. Dennis Force, related that Respondent assisted him in his investigation of the subject charges. To this end, Respondent supplied him with the names of all customers with which National had contracts with during the period that he was National's qualifying agent. It is unfortunate that Respondent was not able to control the fiscal policies of National during the period that he was the qualifying agent, although from a review of the evidence herein, it is apparent that this was not based on his failure to attempt to gain control over the situation as a qualifying agent, but was rather based on the collusion of National's higher-ups who was determined to keep Respondent in the dark. Noteworthy was the fact that within a three-month period, National changed banks at least eight times. It would have been, at best, difficult if not impossible for Respondent to have gained a handle on National's financial condition and to do the things with which a qualifying agent is charged with during the short period during which Respondent was National's qualifying agent.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Petitioner enter a Final Order imposing an administrative fine against Respondent in the amount of $1,000.00 and placing his certified pool contractor's license on probation for a period of six (6) months. 1/ DONE and ENTERED this 7th day of March, 1991, in Tallahassee, Leon County, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of March, 1991.

Florida Laws (2) 120.57489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD COBB, 78-001553 (1978)
Division of Administrative Hearings, Florida Number: 78-001553 Latest Update: Feb. 13, 1979

Findings Of Fact When the third vinyl liner Brenda Hanna had installed in her swimming pool also ripped, she decided concrete would serve better. A friend referred her to respondent Richard Cobb. Mrs. Hanna and Mr. Cobb entered into a written agreement on March 10, 1977, by which Mr. Cobb undertook, among other things, to cement the pool walls and bottom, in exchange for eighteen hundred eighty dollars ($1,880,00). Plumbing was not covered by this agreement. Approximately one month later two workmen began on the project. Work progressed sporadically. Mr. Cobb himself helped remove the vinyl wall, remove aluminum plates, widen the existing excavation and replace the aluminum plates with the intention of using them as part of the forms for pouring the concrete swimming pool walls. Mr. Cobb also put some steel bars in place, After several telephone calls, on October 17, 1977, Mrs. Hanna wrote respondent saying he had 15 days in which to resume work and 45 days thereafter to finish. On or about November 1, 1977, respondent appeared at the job site. The last day he worked on the project Mrs. Hanna told Mr. Cobb she would call him when she had gotten the plumbing finished. Mrs. Hanna never told Mr. Cobb not to finish the work he began for her. On or about March 10, 1977, Mrs. Hanna wrote a check in favor of DLC, a contracting company, in the amount of five hundred dollars ($500.00), which she intended as partial payment under the contract she entered into on March 10, 1977. Two weeks after work began, Mr. Cobb asked Mrs. Hanna for more money, saying that DLC had charged him five hundred dollars ($500.00) for getting the job for him. Mrs. Hanna gave him one hundred dollars ($100.00) at that time, After Mrs. Hanna investigated, she again discussed what had happened to the first five hundred dollars ($500.00) with Mr. Cobb who conceded that some bills were paid with the money. On another occasion, Mrs. Hanna advanced one hundred fifteen dollars ($115.00) which Mr. Cobb used to buy steel. Before beginning work Mr. Cobb, who held individual swimming pool servicing contractor's license No. RP 2997 from March 17, 1977, till June 30, 1977, secured building permit No. 77-338 to repair Mrs. Hanna's swimming pool. John F. Viking, an investigator in petitioner's employ since February 15, 1971, issued a notice of violation to Mr. Cobb in 1971 or 1972, when he was told that Mr. Cobb had been contracting without a license. In 1973, on the basis of similar information, he filed a complaint with the state attorney's office which he understood resulted in Mr. Cobb's conviction and probation. Lester A. Davis, a long time employee of the City of Gainesville and presently its acting building official, visited Mrs. Hanna's residence after Mr. Cobb had begun work and asked Mr. Cobb to show him engineering plans. In Mr. Davis' opinion, the plans Mr. Cobb showed him were not being followed. Mr. Davis told Mr. Cobb that he could finish the job only if he associated a contractor licensed to build swimming pools. Mr. Davis inspected and discovered that the bottom drain had been installed. No other plumbing was required to be done before cementing the pool walls and bottom.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's license for one year. DONE and ENTERED this 28th day of November, 1978, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Michael Egan, Esquire Post Office Box 1386 Tallahassee, Florida 32302 Richard Cobb, Esquire 1238 Southest 18th Terrace Gainesville, Florida 32601 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO.: 78-1553 RICHARD COBB, RP 0029977, 1238 S. E. 18th Terrace, Gainesville, Florida 32601, Respondent. /

# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD G. BATTER, D/B/A TROPICANA POOLS, INC., 79-001938 (1979)
Division of Administrative Hearings, Florida Number: 79-001938 Latest Update: Apr. 30, 1980

The Issue The issues posed for decision herein are whether or not the certified pool contractor's license issued to Respondents Licensee, Edward G. Batter, should be revoked or suspended or the Licensee's right to practice thereunder should be withdrawn based on conduct which will be set forth hereinafter in detail as set out in the Administrative Complaint filed herein on August 23, 1979.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Edward G. Batter, d/b/a Tropicana Pools, Inc., (Respondent or Licensee) is a certified pool contractor who holds license No. CPC 012906. Respondent was first licensed on July 28, 1978, as qualifier of Tropicana Pools, Inc., which license was temporarily suspended in June, 1979, and remains in an invalid status to this date. By its Administrative Complaint, Petitioner's Executive Director took action to revoke or otherwise suspend the Respondent's rights to practice pursuant to his referenced license. As a licensed pool contractor, Respondent is subject to the Board's rules and regulations. (See Petitioner's Composite Exhibit 1.) A special meeting of the Board of Adjustment, Appeals and Examiners for general building contractors for Hillsborough County was held on Thursday, July 19, 1979, for the purpose of hearing certain allegations concerning the demise of Tropicana pools, Inc. Jerry Taylor, Petitioner's field investigator, presented the Hillsborough County Board with the results of an investigation of Respondent and presented several cases wherein funds were diverted after being collected for a specific contract to other projects or for other purposes and that projects for which funds had been collected had either been left unstarted or abandoned at the time Tropicana Pools, Inc., ceased doing business. At that meeting, the Respondent's construction activities were suspended by the Board until restitution or settlement was made and verified by affected parties. The temporary suspension by Hillsborough County became final during August of 1979. (Petitioner's Exhibits 2 and 3.) Howard Shaw, Director of Building and Zoning for the City of Tampa, appeared and testified to substantiate the disciplinary action taken against the Respondent by Hillsborough County during the summer of 1979. On June 7, 1979, Mr. and Mrs. James R. Stanton entered into a contract with Respondent to have a pool constructed for a price of $8,182.00. Respondent was paid a 10 percent deposit to commence construction of the Stantons' pool. Respondent absconded with the deposit and never notified the Stantons that their pool would not be built nor did Respondent return their deposit. (See Petitioner's Exhibits 4 and 5.) On April 19, 1979, Mr. and Mrs. Theodore Hillary entered into a contract for the construction of a swimming pool for a contract price of $8,130.00. Approximately $5,690.00 or approximately 70 percent of the contract sum was paid on June 18, 1979, and the work ceased on the Hillary project at a completion stage of approximately 40 percent. Respondent abandoned the Hillary project on approximately June 5, 1979. The Hillarys completed their pool at a price of approximately $5,000.00 over and above the contracted price. (Petitioner's Composite Exhibit 6.) On April 30, 1979, Mr. and Mrs. Leon Tope entered into a contract for the construction of a swimming pool at their residence for the contract price of $8,050.00. On June 18, 1979, the Topes had tendered to Respondent approximately 70 percent of the contract cost while the Respondent abandoned the construction of the Topes' pool after approximately 40 percent of the work was complete. Respondent abandoned the project on June 18, 1979, and the Topes completed the construction of their pool at a price of approximately $2,000.00 by engaging the services of other contractors in the area. (See Petitioner's Exhibits 7, 8, 9, 10, and the testimony of Jim Moran.) Jerry Taylor, Petitioner's field investigator, attended the probable cause hearing during August of 1979 in which the Hillsborough County Board of Examiners suspended the pool license of Respondent. Investigator Taylor briefed the Hillsborough County Board respecting the results of the investigation conducted by Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Respondent's pool contractor's license No. CPC 012906 be REVOKED. ENTERED this 10th day of March, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings 101 Collins Building Tallahassee, Florida 32301 (904) 488-9675

Florida Laws (1) 120.57
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer