The Issue Whether disciplinary action should be taken against Respondent, Michael Hill's, contracting license based on the violations as charged in the Administrative Complaint in this proceeding.
Findings Of Fact Based on the evidence and testimony of the witnesses presented and the entire record in this proceeding, the following Findings of Fact are made: Respondent is a certified contractor, having been issued License No. CR C057409 by the Florida Construction Industry Licensing Board. Respondent's license as a certified residential contractor is currently active. Respondent was not certified with the Construction Industry Licensing Board as doing business as "Michael Hill Homes, Inc." On or about April 11, 2005, Kenneth and Aldith Farquharson ("Farquharson") entered into a written contractual agreement with Respondent, d/b/a Michael Hill Homes, Inc., for the construction of a single-family residence at Lot 17, Hattaras Terrace, Palm Bay, Florida. The original contract price of the contract between Respondent and Farquharson was $240,900.00. The original contract price was subsequently increased, via change orders executed by Respondent and Farquharson, by $4,500.00, for a total contract price of $245,400.00, adding the value of the change order for the fill dirt needed for the lot. On June 19, 2005, Farquharson paid a total of $28,590.00 to Respondent. The scope of work under contract required appropriate permits from the City of Palm Bay Building Department before work could commence. Respondent failed to apply for the permits necessary to commence work under the contract. Respondent delivered some sand to the lot on or before October 2005. After delivering the sand, Respondent failed to continue any more of the contracted work. From November 2005 to December 2006, Respondent performed no work on the project under contract. From October 2005 to February 2006, Farquharson made multiple attempts to contact Respondent regarding the lack of work under the contract. Farquharson did not prevent Respondent from commencing and completing the work under contract or agree to delay the project for any reason. Farquharson did not terminate the contract with Respondent. Respondent did not refund any money to Farquharson. The amount of actual damages that Respondent caused Farquharson is calculated as follows: Amount paid: $28,590.00 Amount of work performed by Respondent (dirt fill): _ 4,500.00 $24,090.00 The Petitioner's total investigative cost for the case is $439.79.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered as follows: Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count I of the Administrative Complaint, for violating Subsection 489.119(2), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(i), Florida Statutes, as alleged in Count II of the Administrative Complaint, for violating Subsection 489.126(2)(a), Florida Statutes, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(g), Florida Statutes, as alleged in Count III of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(j), Florida Statutes, as alleged in Count IV of the Administrative Complaint, and imposing as a penalty an administrative fine of $5,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(o), Florida Statutes, as alleged in Count V of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $1,000.00; Finding Respondent guilty of having committed one violation of Section 489.129(1)(m), Florida Statutes, as alleged in Count VI of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $2,500.00; Respondent be ordered to pay financial restitution in the amount of $24,090.00 to Kenneth and Aldith Farquharson; Assessing cumulative cost of investigation and prosecution in the total amount of $439.79, which excludes costs associated with any attorney's fees; and Permanently revoking Respondent's license as a result of the numerous violations and the financial harm sustained by Kenneth and Aldith Farquharson. DONE AND ENTERED this 12th day of October, 2007, in Tallahassee, Leon County, Florida. S JEFF B. CLARK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of October, 2007.
The Issue Whether disciplinary action should be taken against Respondent's license to practice contracting number RC 0054458, based on the violations of Section 489.129(1)(j), (k), (h), (p) and (m), F.S., alleged in the five count Administrative Complaint.
Findings Of Fact Since July 1968 and at all times material, Respondent Ronnie Boles, was licensed as a registered roofing contractor in the State of Florida, having been issued license number RC 0054458, and was registered to do business as "Ronnie Boles Roofing Company." On January 8, 1990 Ronnie Boles, doing business as Ronnie Boles Roofing and Construction, contracted with William C. Martin to construct two pole barns at 10550 N.W. 36th Lane, Gainesville, Alachua County, Florida. The contract price was $21,000.00. There is no evidence that "Ronnie Boles Roofing and Construction" was authorized through a valid contractor to construct pole barns. Respondent's roofing contractor license also did not permit the construction of pole barns. On January 12, 1990, Ms. Jean H. Martin, wife of William C. Martin, issued a personal check to the Respondent for $10,000 as partial payment on the January 8, 1990 contract. The Respondent delivered some materials to the site for use in the construction of the aforementioned pole barns, but never began construction. Mr. Martin attempted to have the Respondent construct the pole barns for over three months without success. The value of the materials provided by the Respondent was approximately $2,000.00, Mr. Martin attempted to have the Respondent refund the $8,000.00 balance of the money Ms. Martin previously paid Respondent on the uncompleted contract. Eventually, Mr. Martin retained attorney Ron Holmes who filed a civil suit against the Respondent based on the aforementioned contract. A judgment for Mr. Martin was obtained in the amount of $9,374.36 on October 1, 1991. Mr. Holmes has attempted to collect the judgment for Mr. Martin on several occasions without success. The Respondent has been actively uncooperative. As of the date of the formal administrative hearing, Respondent had paid no portion of the aforementioned judgment. Mr. Martin filed a complaint against the Respondent with the Department of Business and Professional Regulation. Tom Bishop, Department of Business and Professional Regulation Investigator, investigated the case and mailed the Respondent a notification letter on April 20, 1992. In addition, Mr. Bishop left two messages on the Respondent's answering machine. The Respondent did not respond to the notification letter or the phone messages left by Mr. Bishop. The Department of Business and Professional Regulation has accumulated $22.40 in initial investigative costs, $267.50 in investigative costs, and $605.90 in legal costs associated with prosecution of this cause as of the date of Petitioner's Proposed Recommended Order, totalling $895.80.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a final order which provides as follows: Finds Respondent guilty of all violations as set out above. Requires Respondent to pay a collective fine of $5,000.00; Requires Respondent to pay restitution to Mr. Martin of $9,374.36; Requires Respondent to pay costs of investigation and legal fees in the amount of $895.80; and Suspends Respondent's license for three years, thereafter renewal of his license to be subject to proof of Respondent's compliance with requirements (2) - (4) inclusive. RECOMMENDED this 1st day of February, 1994, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The De Soto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of February, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 93-1497 The following constitute specific rulings, pursuant to S120.59(2), F.S., upon the parties' respective proposed findings of fact (PFOF). Petitioner's PFOF: 1 Rejected as unnecessary. 2-9 Accepted as modified to remove rhetoric and cumulative material. Respondent's PFOF: None Filed. COPIES FURNISHED: G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Ron Boles Route 2 Box 417 Alachua, Florida 32615 Richard Hickok, Executive Director Construction Industry Licensing 7960 Arlington Expressway Jacksonville, Florida 32211-7467 Jack McRay, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
The Issue Whether Respondent aided and abetted an unlicensed contractor to engage in contracting by pulling permits for the unlicensed contractor; whether Respondent failed to qualify a firm for whom he was acting as licensed contractor; whether Respondent acted in the capacity of a contractor other than in his own name; and, whether Respondent violated local building codes as alleged in Second Amended Administrative Complaint filed 6-30-89, and Administrative Complaint filed 7-26-89.
Findings Of Fact At all times relevant hereto, Fred S. Petersen was licensed as a general contractor by the Florida Construction Industry Licensing Board (FCILB) and issued License Nos. CG C023928 and CB CA23929 (Exhibit 1). Neither American Weatherall Industries Inc. (AWI), Mel C. Wyatt, nor Steven C. Wyatt were licensed as contractors by the FCILB (Exhibit 2). Prior to mid-August 1987, Kirk Evenstad was the qualifying general contractor for AWI. By letter dated August 20, 1987, AWI proclaimed Kirk Evenstad to be no longer working for AWI because of mismanagement (Exhibit 3). Mel Wyatt, President of AWI, testified that Everstad had stolen between $30,000 and $50,000 of materials from AWI, leaving AWI in a precarious financial situation. In order to continue in business to work out of the financial hole created by Everstad, AWI, through one of its employees, Danny O'Brien, introduced Mel Wyatt to Respondent. Respondent had known O'Brien for some 20 years and, for the proposed reason of helping O'Brien, Respondent agreed to act as qualifying contractor for AWI. To carry out this project, Respondent entered into a contract (Exhibit 4) or Employment Agreement dated July 31, 1987, in which Respondent agreed to supervise construction of projects contracted for by AWI, but the latter was to provide all material and handle all financial aspects of the contracts. Respondent received $1000 for signing this agreement and was to receive a percentage of the gross proceeds of future contracts entered into by AWI. Respondent authorized O'Brien to pull permits for AWI pursuant to Respondent's contractor's license. Although Respondent testified he gave O'Brien authorization for each specific permit pulled and did not believe he signed Exhibit 11, dated August 11, 1987, a copy of General Authorization for O'Brien to pull permits for AWI under Respondent's license, it is found as a fact that Respondent signed the original of Exhibit 11 which is a copy. Within a short period of time after executing Exhibit 4, Respondent became aware of the financial difficulties facing AWI and ceased his efforts to qualify AWI. In the latter part of 1987 (believed to be November-December), AWI reached the point that it could no longer remain solvent and filed for bankruptcy leaving several contracts unfinished for which AWI had received partial payment. Of the four contracts entered into between AWI and homeowners for additions to their houses (Exhibits 7-9 and 14), all were entered into under a printed document showing Everstad's license number; however, the building permits for Exhibits 7-9 were pulled under Respondent's license. By agreement dated August 10, 1987 (Exhibit 7), Alfred and Marjory Hauk contracted with AWI to convert a garage at their home into an office. Hauk made payments of $1000 and $2300 to AWI, the permit for the work was pulled by O'Brien under Respondent's license, but no work was ever done under this contract. AMI subsequently went out of business, and Hauk received no refund of the monies he had paid to AMI. Hauk never met Respondent. On June 12, 1987, John Davis contracted with AWI to convert an existing garage to bedroom and bath and add a garage to his home. The initial permit for this work was pulled by Kenn Covicc as contractor on June 21, 1987, and a subsequent permit was pulled by O'Brien using Respondent's license. Although Davis paid over $6000 to AWI for this work, the work stopped after the footing for the garage addition was poured. On June 2, 1987, Albert Charette entered into a contract with AWI to add a room to his house. Charette paid some $9300 of the $34,400 contract amount during the progress of the work. Differences arose between Charette and AWI involving whether the construction was being done in accordance with the plans and specifications. In September, 1987, Respondent met with Charette and submitted a proposal (Exhibit 15) to Charette to complete the project in accordance with the plans and specifications. About one week after Exhibit 15 was signed, all work stopped on the project, and Respondent never received compensation or commenced work on this contract, which he had entered into in his own name and not as a representative of AWI.
Recommendation It is recommended that Fred S. Petersen be found guilty of violating Sections 489.129(1)(e), (f) and (g), Florida Statutes, and assessed a monetary fine of $3000. ENTERED this 11th day of June, 1990, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of June, 1990. APPENDIX Proposed findings submitted by Petitioner are accepted, except: Finding #7, penultimate sentence which is rejected as uncorroborated hearsay. Finding #11, that portion stating the purpose of Petersen's visit to Charette was to change the licensure on the permit to Petersen is rejected. See HO #13. Proposed findings submitted by Respondent are accepted, except: Finding #4, Accepted, except with regard to Respondent's notification of termination of his association with AWI. No documentation of this act was submitted and, even though Respondent may have ultimately revoked O'Brien's authority to pull permits, this was done well after the permits were pulled. COPIES FURNISHED: Robert B. Jurand, Esquire G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Brian A. Burden, Esquire Post Office Box 2893 Tampa, FL 33601 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth E. Easley General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792
Findings Of Fact Harry L. Wilson is the holder of a registered roofing contractor's license from the Florida Construction Industry Licensing Board. The license, Number RC 0041328, was first issued in March of 1982. The license was issued in the name of Harry L. Wilson Roofing, 1943 Hardy Street, Jacksonville, Florida, with the Respondent as qualifier. The Respondent has been the qualifier of Harry L. Wilson Roofing at all times relevant to this proceeding. On December 6, 1984, the Respondent and Robbie L. Hicks, entered into a written contract (Petitioner'S Exhibit 2). Pursuant to this written contract (hereinafter referred to as the "Contract"), the Respondent agreed to perform the repair work specified in the Contract in a "professional manner" and Ms. Hicks agreed to pay the Respondent $2,395.00. The property to be repaired is rental property owned by Ms. Hicks. The property is located at 1508 Eaverson Street, Jacksonville, Florida. The Respondent commenced work sometime during the early part of 1983. Shortly after commencing work, however, the Respondent and Ms. Hicks began having disagreements as to the work to be performed and the quality of the Respondent's work. These disagreements continued after the Respondent completed the work in November of 1983. Ms. Hicks testified that the work that the Respondent completed was done in an unprofessional manner and that the Respondent had not completed all of the work that he had agreed to perform. In particular, Ms. Hicks testified that the Respondent had failed to paint the interior of the house beige as required by the Contract, had failed to remove saw dust and other debris from the house following completion of the work, had failed to finish cabinets installed in the house, had failed to repair screens and generally had not performed in the manner he had agreed to perform. Ms. Hicks paid the Respondent all but $410.00 of the contract price. The Respondent testified that all off the work called for pursuant to the Contract had been performed. According to the Respondent, he had performed some work not required by the Contract and had not performed other work requested by Ms. Hicks because the work was beyond the scope of the Contract. The Respondent also stated that the work which Ms. Hicks expected would have cost considerably more than the price agreed upon in the Contract. The Respondent did not perform all of the work specified in the Contract in a "professional manner" as required by the Contract. Based upon the testimony of Mr. Claude Bagwell, Deputy Chief, Building and Zoning, Inspection Division of the City of Jacksonville, it is clear that no permit was issued by the City of Jacksonville to perform the work required by the Contract. The only permits issued with regard to Ms. Hicks' rental property was a permit issued in 1961 and the original building permit issued in 1949. Additionally, due to the fact that no Florida registered roofing contractor's license in the name of "Harry L. Wilson Roofing" had been filed with the City of Jacksonville, no permit could be issued to Harry L. Wilson Roofing with regard to the Contract. The Respondent admitted that he had not obtained a permit to perform the work required by the Contract. The Respondent indicated that he had not obtained a permit because he was not aware that one was required in order to perform the work. He did indicate that he had obtained permits to perform other jobs. The Respondent could not, however, have obtained permits for other jobs because no license issued in the name of Harry L. Wilson Roofing had been filed with the City of Jacksonville. The Respondent did take the examination required in order to obtain a registered roofing contractor's license. The Petitioner suggested in its Proposed Findings that the "permit requirement was explained" when the Respondent took the exam. No evidence to support such a finding was presented at the hearing. The Respondent in entering into the Contract clearly used the name "Wilson Recycling". Nowhere on the Contract is the name "Harry L. Wilson Roofing" used. The Respondent ultimately admitted that no Florida license authorizing the use of the name "Wilson Recycling" had been obtained by him. The Respondent, however, when initially asked whether a Florida license in the name of "Wilson Recycling" had been obtained indicated that such a license had been issued. On further examination, however, the Respondent testified that an occupational license in the name of "Wilson Recycling' had been obtained by him and not a Florida license. The work to be performed pursuant to the Contract was beyond the scope off the Respondent's license. As pointed out by Mr. Bagwell the work to be performed pursuant to the Contract would require licensure as a registered residential contractor or more.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That count I of the Administrative Complaint filed against the Respondent be dismissed. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129 (1)(g), Florida Statutes (1983), by contracting in a name other than the name as set forth on the Respondent's license. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129(1)(j), Florida Statutes (1983), by failing in a material respect to comply with the provisions of Section 489.119(2) and(3), Florida Statutes (1983), in that the Respondent failed to qualify the business name "Wilson Recycling" with the Construction Industry Licensing Board. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129(1)(j), Florida Statutes (1983), when he failed in a material respect to comply with the provisions of Section 489.117(2), Florida Statutes (1983), by contracting to perform and actually performing work beyond the scope of his Florida contracting license. It is further RECOMMENDED: That Petitioner suspend Respondent's roofing contractor's license for a period of three (3) months. DONE and ENTERED this17th day of December, 1984, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of December, 1984. COPIES FURNISHED: H. Reynolds Sampson, Esquire Staff Attorney Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Harry L. Wilson 1943 Hardee Street Jacksonville, Florida 32209 Mr. Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
Findings Of Fact Leroy Alvin Colts was qualifier for Berkley Home Service, which held License #RC0029635. Colts held such license from 1977 - 81. In December 28, 1978, Leroy Alvin Colts' local certificate of competency was revoked by the Pinellas County authorities. This action was reviewed by the Florida Construction Industry Licensing Board prior to these charges being filed. On January 4, 1979, Leroy Alvin Colts was adjudged guilty of violating Section 812.021 (Grand Theft) and Section 812.014 (Grand Larceny) and sentenced to 45 years in the State Penitentiary. These offenses arose directly from Colts' activities as a licensed contractor. The court's judgment was affirmed by the appellate court. Notice of this proceeding was provided Colts in the manner prescribed by law, and inquiry of Counsel for the Petitioner Board and representatives of the St. Petersburg Police Department showed that Colts was free on bond and available to attend the hearing.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommended that the Florida Construction Industry Licensing Board revoke Leroy Alvin Colts' license. DONE and ORDERED this 21st day of September, 1979, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Michael E. Egan, Esquire 247 South Adams Street Post Office Box 1386 Tallahassee, Florida 32302 Joseph F. McDermott, Esquire 544 First Avenue, North St. Petersburg, Florida 33701 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner,
Findings Of Fact Respondent, Frank D. Gutc, holds registered building contractor license number R80027543 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. When the events herein occurred, Gutc resided in Flagler Beach, Florida where he was engaged in the business of constructing residential homes. Simon and Doris Lutterbach were aware of Gutc's construction activities and approached him concerning the possibility of him building a house. The Lutterbachs had only 50,000 with which to buy a home and they conveyed this information to Gutc. Gutc showed them the plans for a three bedroom house which cost in excess of 550,000, but agreed to "downsize" the house to two bedrooms for a price of 550,000, including the lot. Thereafter, on December 11, 1982, Gutc entered into a contract with the Lutterbachs to construct a two bedroom, two bath home at 16 Prince Patric Lane in Palm Coast, Florida at a cost of 550,000. The parties later agreed that Gutc would enclose the porch for an additional 51,700, or a total contract price of $51,700. The contract called for a closing date of March 1, 1983. After the Lutterbachs gave an initial down payment of $10,000 to Gutc, Gutc obtained a $37,500 construction loan from Stockton Whatley Davin & Company. He later received an additional $1,314 from the Lutterbachs for minor changes in the plans. Construction commenced in early January, 1983, but the house was not completed by March 1. The closing date was accordingly reset to April 26, 1983. However, by that date a number of suppliers and subcontractors had filed liens totaling $28,005.37 on the house. The liens were filed even though Gutc had drawn the full amount of the construction loan from the lending institution, and had received almost $11,400 in cash from the Lutterbachs. The Lutterbachs were unable to pay off the additional liens incurred by Gutc and were consequently unable to close on the house. They have never been reimbursed the $11,314 which they advanced to Gutc to construct the home. Since that time Gutc's financial condition has deteriorated, and he has been forced to file for bankruptcy. An expert witness retained by petitioner established that the house constructed by Gutc was substantially underpriced, and that a competent contractor would have charged at least $53,800 for the house itself, exclusive of the cost of land. It was also established that a competent contractor normally prepares an itemized cost sheet whereby all costs are broken out in detail. By doing this, and using sound financial management procedures, a contractor could avoid the predicament which befell Gutc on this project. Gutc himself acknowledged that he should have asked around $70,000 for the house instead of $50,000, that he never priced out construction costs on any of his projects including the Lutterbach project, and did not know if he had made a profit on a job until the proceeds were distributed at closing. Further, he had no one keeping his books, kept no financial records, and did not seek competitive bids on his jobs. In short, while Gutc's on-site competency is not questioned, his planning and financial practices are in contravention of competency standards for the construction industry.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that respondent be found guilty of violating Subsection 489.129(1)(m), Florida Statutes, as set forth in Count III of the administrative complaint. All other charges should be dismissed. It is further RECOMMENDED that respondent pay a $1,500 administrative fine, that his registered general contractor's license be suspended for two years, and that reinstatement of said license thereafter be conditioned on respondent demonstrating that he has received adequate training or study in cost estimating and in the financial management of a construction business. DONE and ORDERED this 25th day of January, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of January, 1981. COPIES FURNISHED: Douglas A. Shropshire, Esquire 130 North Monroe Street Tallahassee, Florida 32301 Frank D. Gutc P.O. Box 1658 Flagler Beach, Florida 32036
Findings Of Fact Based upon the record evidence, the Hearing Officer makes the following findings of fact: Martin Gold is now, and has been since July, 1986, licensed by Petitioner as a Registered Specialty Contractor authorized to do painting and waterproofing work in Dade County. He holds license number RX 0051718, which expires June 30, 1989. Since receiving his license he has been disciplined twice by the Florida Construction Industry Licensing Board. Gold is the President of Team Leisure Corp., a construction company, and is also its "qualifying agent." On August 14, 1986, Team Leisure Corp. entered into a written contract with Terry Dudley and his wife, Patricia, in which it agreed, for $12,000, to build a two-room, 27-foot by 13- foot addition to the Dudley home located at 15510 Leisure Drive in Dade County and to install new windows in the existing structure. According to the terms of the agreement, Team Leisure was to do "no painting." In his capacity as President of Team Leisure Corp., Gold hired William Sernaker to directly oversee the completion of the construction work specified in the Dudley contract. At the time, Sernaker was licensed as a general contractor in Dade County. As part of his arrangement with Gold, Sernaker assumed responsibility for ensuring that all work permits and inspections necessary to complete the Dudley project were obtained. On September 4, 1986, Sernaker obtained a building permit for the Dudley project. Thereafter, work on the project commenced. The foundation for the addition was laid and, on September 10, 1989, it passed the inspection of James Tucker, a Dade County building inspector. Fifteen days later, Tucker conducted a tie beam inspection. This phase of the project also received his formal approval. Sernaker obtained a roofing permit on October 14, 1986. The exterior of the roof was inspected by Russell Bergsma, another Dade County building inspector, on October 21, 1986. It too passed inspection. An electrical permit was obtained for the Dudley project on November 17, 1986, by Robins Electric, a subcontractor. When the electrical work was initially inspected by Grant Morse, another Dade County building inspector, it was rejected because there were a "few outlets missing." The record is unclear as to the results of any subsequent electrical inspections. Morse also conducted an inspection of the framing work done on the Dudley project. He did so on or around November 21, 1986. In his view, the framing was "not to code." Accordingly, he left a "tag" at the job site on which he gave the following written explanation for his rejection of the framing work: All window bucks must be tight with caulking, no gaps. When the stucco meets the window frame, it should be set back at approximately a 45-degree angle at a width of one quarter to provide a groove to be filled with caulking. Continuous back bed of caulking must be maintained. A follow-up inspection of the framing work was performed by Bergsma on December 1, 1986. In Bergsma's opinion, while some corrections had been made, deficiencies remained. He therefore issued another rejection. A third framing inspection was conducted on December 3, 1986. Tucker was the inspector who performed this inspection. He approved the work that had been done. Prior to this inspection, Gold had paid another contractor $600 to "redo" the framing. This additional expense was not passed on to the Dudleys. Morse attempted to conduct a final building inspection on December 22, 1989. He was unable to do so, however, because "[n]o one was home." From the outset, Gold kept abreast of the progress that was being made on the Dudley project by communicating with Sernaker. He also visited the job site on at least a weekly basis. Gold also heard from the Dudleys concerning the status of the project. The Dudleys closely monitored the work of Sernaker and his crew. If the work was not done to their satisfaction, they expressed their disapproval to Sernaker and, if he did not rectify the matter, they complained to Gold over the telephone. The following were among the complaints made by the Dudleys: the foundation was not level; the roof did not contain any fiberglass material; the window frames did not fit properly; the wood used for the open beam ceilings had cracks in it and was unsightly; the walls in the den were not level and had cracks in them; the linoleum on the Dudleys' screened-in porch was ripped by workers putting up a wall; the outside stucco was cracking and peeling; and trash was left on the property. An effort was made to address the Dudleys' concerns. For instance, in response to the Dudleys' complaints, a "thin cap" was placed over the foundation to make it level. The roof was redone with fiberglass material. The Dudleys were reimbursed for the linoleum they needed to replace on their porch. A contractor was hired to correct the framing problem. Nonetheless, the Dudleys became increasingly dissatisfied with Team Leisure Corp.. Sometime shortly before January 6, 1987, they became so dissatisfied that they ordered Sernaker and his crew off their property and refused to make any additional payments. Following this incident, Gold met with the Dudleys and attempted to mollify them. This was his first face-to-face meeting with them. He offered to send another contractor to the Dudleys' home to perform the work the Dudleys believed needed to be done to satisfactorily complete the project. The Dudleys accepted this offer. On January 6, 1987, Gold sent the Dudleys a letter which read as follows: As per our mutual agreement, these are the items you requested be taken care of. Once taken care of, you agree to sign completion certificate so we can be funded. COMPLETED (please check upon satisfaction) 1.) Touch up outside windows. 2.) Windows to be locked in. 3.) Walls in den to be taken down and leveled out. 4.) Frame around closet door. 5.) Fix two windows; replace concrete in doors and windows. 6.) Clean up. 7.) Replace vinyl, in rear den. 8.) $100.00 dollars to Mrs. Dudley, for clean-up. 9.) 10 year guarantee- roof and release of lien [sic]. 10.) Concrete over build. 11.) Crack under window sill. 12.) Nail in door frame. 13.) Gaps in drywall bedroom. 14.) Stucco cracking outside. 15.) Electrical inspection. (not to be Mike Charles.) Accepted and Approved: x x After receiving this letter, Mr. Dudley checked all but items 2, 5, 6, 8, and 9 on the letter's "completion certificate." Neither he nor his wife, however, signed this "completion certificate." Although the cracks in the outside stucco had been repaired at the time Dudley checked item 14, the stucco subsequently started cracking again. A final building inspection of the Dudley project was conducted by Tucker on January 13, 1989. The project was "turned down" by Inspector Tucker because it was unpainted. Under their contractual agreement, the Dudleys, not Team Leisure Corp., were responsible for the painting of the project. The painting was not done because the Dudleys noticed cracks reappearing in the outside stucco. On or around March 4, 1987, Mr. Dudley telephoned Inspector Bergsma and asked him to conduct an informal field inspection of the project. Bergsma complied with Dudley's request. When he arrived at the Dudley home, Dudley showed him a "gap on the rear of the house ... where the two roofs are at different levels and come together." Bergsma told Dudley that "[i]t didn't belong there" and that it would have to be eliminated if the structure was to pass a final building inspection. As of the date of the hearing, the structure had not passed such an inspection. Team Leisure Corp. received $10,200 for the work done in connection with the Dudley project. The remaining $1,800 of the $12,000 that the Dudleys were to pay pursuant to the contract was held in escrow by a bank. Ultimately, this $1,800, along with approximately an additional $500 from Team Leisure Corp., was given to the Dudleys as part of a settlement between them and Team Leisure Corp.. The money was to be used by the Dudleys to pay another contractor to complete the project to their satisfaction.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order (1) finding Respondent guilty of contracting outside the scope of his license in violation of Section 489.129(1) (j) , Florida Statutes; (2) imposing a $750 administrative fine upon Respondent for said violation, and (3) dismissing the remaining charges against Respondent set forth in the instant administrative complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 30th day of May, 1989. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of May, 1989. COPIES FURNISHED: Elizabeth Alsobrook, Esquire Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, Florida 323399-0792 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Carlos Garcia, Esquire 8603 Dixie Highway Suite 400 Miami, Florida 33143 =================================================================
Findings Of Fact At the final hearing the following factual allegations contained in the Administrative Complaint were either stipulated to by the parties or not disputed by the Petitioner: The Respondent John W. Rohrback is a certified general contractor having been issued license numbers CC C002372, CG CA 02372, PM 0015083 and RF 0036563. The last known address of the Respondent Rohrback is 10282 N.W. 31st Street, Coral Springs, Florida 33065. The Respondent Rohrback, while doing business as Statewide Insulation and Solar Systems, Inc., failed to initially obtain building permits which are required by ordinance on the following job sites: Mrs. Blanche Nelson, 454 N.E. 4th Street, Boca Raton. Mrs. Dorothy Menzel, 784 N.E. 71st, Lot 27, Block C, Boca Harbor. Work started May 17, 1980. Permit taken out on May 19, 1980. Mrs. Meinhard, 1230 S.W. 7th Street, Lot 6, Block 29, Boca Raton Square. Work started on May 7, 1980. Permit taken out on May 19, 1980. Ms. Mary Greenhauer, 986 S.W. 14th Street, Lot 20, Block 63, Boca Raton Square. Work started on May 3, 1980. Permit issued on May 19, 1980. Although the Respondent Rohrback eventually received the permits for these projects, he also initially failed to obtain a license to do contracting in the City of Boca Raton as required by ordinance. On or about August 11, 1980, the City of Boca Raton Contractor's Board suspended the Respondent Rohrback indefinitely from doing business in the city for: using alternate materials and methods without clearance; not obtaining building permit; not filing a proper permit; and not filing proper proof of a certificate of competency. At the time of the hearing before the local contractor's board, the Respondent Rohrback had settled and obtained releases with two of the listed individuals. He was told to settle the remaining two cases, obtain releases and appear before the local Board at a later date. The Respondent appeared on the designated date and discovered that the Board had met the previous day and suspended his license. The Respondent Rohrback contacted the Boca Raton city attorney and a representative of the Department to present the signed releases and cancelled checks he eventually obtained from the four listed individuals in order to obtain a reversal of the local Board's action suspending his license. At the time of hearing, the Respondent had been unsuccessful in obtaining a reversal of the Board's decision. Additionally, the Respondent Rohrback acted as qualifying agent for D.R.K. Company from July 1, 1979 through February 1981. During this period of time, D.R.K. utilized deceptive practices in order to obtain contracts from various individuals. By certified letter dated June 12, 1980, the Respondent informed D.R.K. and pertinent licensing boards that he was withdrawing as qualifying agent for D.R.K. and Statewide Insulation and Solar Systems, Inc., and revoking any presigned permits or letters of authorization that may have been signed by John W. Rohrback. However, the Respondent did not actually attempt to revoke his authorization until October 28, 1980, when a letter was sent to Milton Rubin, administrative assistant to the Florida Construction Industry Licensing Board, outlining the problems he had encountered with D.R.K. and Statewide. On or about February 19, 1981, the Lee County Board of County Commissioners suspended the Respondent Rohrback's privilege to pull building permits.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a Final Order be entered dismissing the Administrative Complaint filed against the Respondent John W. Rohrback in Case No. 82-2616. DONE and ORDERED this 28th day of March, 1983, in Tallahassee, Florida. SHARYN L. SMITH, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March, 1983. COPIES FURNISHED: Michael J. Cohen, Esquire Suite 101 Kristin Building 2715 East Oakland Park Blvd. Fort Lauderdale, Florida 33306 John W. Rohrback 10282 Northwest 31st Street Coral Springs, Florida 33065 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
Findings Of Fact At all times material to these proceedings, Respondent Farrall was licensed as a certified general contractor in Florida, and held license number CG C040234. In addition, the Respondent was licensed as a certified roofing contractor and held license number CC C024398. Mr. Farrall was the qualifying agent for Sunmaster Roofing Company. On May 25, 1987, Sunmaster Roofing Company entered into a contract with Clarence A. Miller and Emily Miller to reroof their residence in Naples, Florida. After the project was completed, Mr. and Mr. Miller filed a complaint with the Collier County Contractors' Licensing Board on December 7, 1987. Essentially, the complaint alleged as follows: 1) that the contractor abandoned the job without adequately completing construction; 2) that the roof materials were incorrectly installed; 3) that the contractor failed to obtain a building permit; and 4) that the contractor failed to adequately perform the contract due to his failure to correct faulty workmanship on the job. On December 11, 1987, copies of the complaint and a notice of hearing was sent to Respondent Farrall by certified mail to two different addresses. The items were promptly received at both locations. On January 15, 1988, the Respondent acknowledged that he was personally aware of the hearing scheduled for January 20, 1988. The Respondent requested a continuance until after January 29, 1988, because he had to attend to urgent family matters which required his presence in Canada. A continuance was not granted, and the hearing proceeded as scheduled. The Respondent was aware that the hearing was not continued prior to his departure for Canada. On January 20, 1988, a hearing was held, and the local board received evidence regarding the Miller complaint. As a result of the hearing, the local board found that the Respondent violated specific county ordinances in the following manner: by abandoning the job without legal excuse; disregarding or violating the building code by failing to obtain a building permit; and by failing to make good, faulty workmanship obviously performed in evasion of performance of the contract. The Respondent was disciplined by the Collier County Contractors' Licensing Board on January 20, 1988. His permit privileges were suspended in Collier County until the contractor makes restitution and appears before the Board for reinstatement. The Respondent was given fifteen days to appeal the decision. The Respondent personally received a copy of the disposition of the hearing by certified mail on January 28, 1988. An appeal was not taken of the decision.
Recommendation Based upon the foregoing, it is recommended that the charges set forth in the Administrative Complaint against the Respondent, John W. Farrall, in Case No. 89-3291 be DISMISSED. RECOMMENDED this 15th day of February, 1990, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1990. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-3291 The proposed findings of fact set forth in Petitioner's proposed recommended order are addressed as follows: 1. Accepted. See HO #1. 2. Accepted. See HO #2. 3. Accepted. See HO #1 and #2 4. Accepted. See HO #8 and #9. 5. Accepted. See HO #8. Rejected. Irrelevant to the charges filed. Rejected. Irrelevant to the charges filed. The proposed findings of fact filed by the Respondent are addressed as follows: Accept the first two sentences. See HO #1. The rest of paragraph 1 is rejected as improper argument which is not based upon material evidence presented at hearing. Accepted. See HO #2. Rejected. The issue in this proceeding involves the discipline by the local government board and not the underlying facts upon which the board based its findings. Immaterial. 4. Rejected. Immaterial. See above. Rejected. Rejected. Rejected. Irrelevant. Irrelevant. Irrelevant. Rejected. Rejected. Irrelevant. Irrelevant. Rejected. Rejected. Rejected. Irrelevant. Irrelevant. Contrary to fact. See HO #6. Rejected. Rejected. Contrary to Irrelevant. fact. See HO #9. COPIES FURNISHED: Jack M. Larkin, Esquire 806 Jackson Street Tampa, Florida 33602 John W. Farrall 316-2 Tudor Drive Cape Coral, Florida 33904 Fred Seely, Executive Director Construction Industry Licensing Board 111 East Coastline Drive, Room 504 Jacksonville, Florida 32202 Kenneth E. Easley, Esquire General Counsel Department of Professional Regulation 1940 North Monroe, Suite 60 Tallahassee, Florida 32399-0792
The Issue The issue in this case is whether the Pinellas County Construction Licensing Board should discipline the Respondent for alleged failure or refusal to satisfy a civil judgment in a reasonable period of time.
Findings Of Fact The Respondent, Bradley T. Barbour, has not disputed that he is a certified tile and marble specialty contractor, holding Pinellas County Construction Licensing Board license number C-5778. The Respondent entered into a contract with Cameron Vale to tile the floor of his house. The tile job was unsatisfactory to Vale, who sued in the County Court, Pinellas County, Small Claims Division, Case No. 93-5287 SC-NCD. On February 14, 1994, Vale and the Respondent entered into a Pretrial Conference Agreement. Under the Agreement, the Respondent agreed, among other things, to pay Vale $2,500, payable $200 a month beginning February 18, 1994, until paid in full. Based on the Agreement, Vale and the Respondent filed a Stipulation to Stay Entry of Judgment on February 14, 1995, and two days later the court entered an Order staying entry of final judgment. Contrary to the terms of the Agreement and Stipulation, the Respondent only made one payment of $100. On June 7, 1994, the court entered a Judgment against the Respondent in the amount of $2,400, together with 12 percent interest on the Judgment. The Respondent has made no payments to Vale on the Judgment and has not satisfied the Judgment either in full or in part. The Board has published "Guidelines for Disciplinary Action" which provide for a $300 fine as the "typical" penalty for the first "minor" infraction and a $750 fine as the "typical" penalty for the first "major" infraction. The Guidelines give no guidance in distinguishing between "minor" and "major" infractions. The Guidelines also list aggravating and mitigating circumstances which focus on the harm done by the offense, the licensee's efforts to rectify the situation, and whether there is a history of similar offenses by the licensee. They also authorize suspension or revocation and fines "not to exceed $1,000 per count."
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County Construction Licensing Board enter a final order: (1) finding the Respondent guilty of violating Section 24(2)(c) of Chapter 75-489, Laws of Florida (1975), as amended; (2) fining him $750; (3) revoking his license; and (4) conditioning relicensure upon both full restitution to Cameron Vale under the terms of the outstanding Judgment and full payment of the fine imposed in this case. RECOMMENDED this 23rd day of June, 1995, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of June, 1995. COPIES FURNISHED: William J. Owens Executive Director Pinellas County Construction Licensing Board Suite 102 11701 Belcher Road Largo, Florida 34643-5116 Bradley T. Barbour B & B Tile 2035 Philippe Parkway Safety Harbor, Florida 34695