Findings Of Fact Based on the evidence received at the final hearing, the following findings of fact are made. At all times material to this case, the Respondent, Steven Ary, was a licensed air conditioning contractor in the State of Florida, holding license number CA CO36888. On October 20, 1987, a company named Jenni Temp Refrigeration Company, Inc., entered into a contract with Lauderhill Mall, Lauderhill, Florida, to install three 3 1/2 ton air conditioning units for the sum of $7,875. Jenni Temp was to provide the three separate permits required by the City of Lauderhill, Florida, for the installation. Joseph Roturra, the owner of Jenni Temp Refrigeration Company, Inc., and Respondent had, prior to October 20, 1987, entered into negotiations whereby Respondent would become employed by Jenni Temp as its qualifying agent so that Jenni Temp could engage in air conditioning contracting. Those negotiations ended before any formal efforts were made to have Jenni Temp licensed with Respondent as the qualifying agent. In late 1987, before his negotiations with Jenni Temp broke down, Respondent signed three blank application forms for electrical and air conditioning permits. Respondent then gave the three signed application forms to Joseph Roturra. Respondent knew that neither Joseph Roturra nor his company was licensed for air conditioning work. Joseph Roturra completed the signed blank application forms he received from Respondent and made application with the City of Lauderhill, Florida, for the three permits required for the job at Lauderhill Mall. The name of the applicant on the applications as completed by Joseph Roturra was All Star Service, Inc. Respondent served as the qualifying agent for All Star Service, Inc. The City of Lauderhill did not issue the permits for which Roturra applied using the forms signed by Respondent because permits had been previously issued to another company for the same job. Jenni Temp completed the Lauderhill Mall job without the permits required by local law and without further assistance from Respondent. Respondent did not supervise the job at Lauderhill Mall. There was no final inspection of the work as required by local law.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered finding Respondent guilty of having violated Sections 489.129(1)(e) and (m), Florida Statutes and which imposes an administrative fine on Respondent in the amount of $500 for the violation of Section 489.129(1)(e), Florida Statutes. It is further recommended that there not be a separate fine for the violation of Section 489.129(1) (m), Florida Statutes, because the conduct that establishes that violation is the same conduct which constitutes the violation for which the administrative fine is recommended. DONE and ENTERED this 22nd day of May, 1989, in Tallahassee, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1989. APPENDIX The findings of fact contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, l0, 13, 14, 15, 19 and 20 of Petitioner's proposed findings of fact are adopted in substance, insofar as material. The findings of fact contained in paragraphs 11, 12, 16, 17 and 18 of Petitioner's proposed findings of fact are immaterial. COPIES FURNISHED: Kenneth E Easley, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0729 Fred Seely, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Elizabeth R. Alsobrook, Esquire Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0729 Steven Ary 1217 N. E 4th Street Pompano Beach, Florida 33306
The Issue Whether Respondent's license as a certified general contractor should be suspended or revoked or the licensee otherwise disciplined for alleged violations of Chapter 489, Florida Statutes as set out in the January 18, 1984 Administrative Complaint. Petitioner presented the oral testimony of Louis P. Gilner, Peter Max Christianson, Jr., Catherine M. Edwards, John Owen Thompson, Jack W. Rainford, and Annie Gilner and had admitted in evidence Petitioner's exhibits 1, 3, 4, 5, 6, 7, 7A, 7B, 8, 9, 10, 11, 12 and 13. Exhibit 2 is clearly hearsay and inadmissible but has be considered as a stipulation of counsel and is discussed under the Conclusions of Law as a jurisdictional argument of counsel. Neither Respondent nor Chester A. Trow, Esquire appeared for formal hearing. Petitioner filed transcript of the proceedings November 14, 1985 and proposed findings of Fact and Conclusions of Law on November 18, 1985, and waived time for entry of this recommended Order. These proposals have been considered in this recommended Order and are ruled upon in the Appendix hereto.
Findings Of Fact Respondent, Patton N. Roberts, is a certified general contractor, license number CG C015023 and qualifying agent for Roberts Construction and Development, Inc. Although Respondent failed to renew his license in June, 1985, and his license is now on inactive status, it can be renewed at any time before June 1988 by payment of late renewal fee. In June 1982, Respondent entered into a contract for $68,242.00 with Louis Gilner to construct home in Putnam County, Florida. The charges against Respondent arise out of the use of the funds associated with construction of this home pursuant to contract. On June 30, 1982, Respondent obtained Putnam County building permit #6107 for the construction. Respondent commenced construction and completed the home to the dry-in stage by approximately early August 1982. Mr. Gilner paid Respondent a $50.00 deposit and two "draw" payments of $20,472.00 each, making total payments to Respondent of $40,995.00. These "draws" against the total amount of $62,242.00 which was contracted-for were paid on July 20, 1982 and August 5, 1982, respectively. Approximately July 15, 1982, Respondent ordered trusses for the Gilner residence from Landmark Truss, Inc. The trusses were delivered on July 23, 1982. Respondent failed to pay for the trusses, although he had received the draw payment for the trusses. Landmark Trusses, Inc. filed a lien on the Gilner residence for $2,490.00. On July 9, 1982, Respondent ordered 16 loads of fill dirt for the Gilner residence from Chesser & Strickland Sand Co., Inc. The Respondent's failure to pay $950.00 for the dirt and the labor in spreading it resulted in a lien being filed against the Gilner property for that amount. Mr. Jack Rainford testified that Respondent subcontracted the heating and air conditioning work to A-1 Air and A-1 plumbing for $5,806.00 ($3,550 plumbing and $2,556 air conditioning); that Respondent paid A-1 Air and A-1 Plumbing the first draw on the plumbing in the amount of $1,128.00 on August 17, 1982; that the Gilners had, on January 3, 1983, paid A-1 Air and A-1 Plumbing $1,128.00 on the air and $1,183.34 on the plumbing, and that Respondent has failed to pay $1,183.34 on the plumbing and $1,128.00 on the air conditioning. No matter how these figures are worked, they do not fairly support Mr. Rainford's conclusion that Respondent only owes A-1 $1,183.34 plus $1,12800. It is more mathematically logical that the original total owed was $6,106.00; the Respondent paid $1,128.00 on August 17, 1982 reducing the remaining amount to $5,806.00; thereafter Mr. and Mrs. Gilner, on January 3, 1983, paid A-1 $1,128.00 for the air conditioning work and $1,183.34 for the plumbing package and that Respondent actually owes the Gilners $2,311.34 for their having to pay twice, and owes A-1 $3,464.66; which is the balance of A-1's bill after all payments the Respondent and the Gilners have been deducted. However, the undersigned will accept Mr. Rainford's unrefuted testimony that Respondent owes A-1 only $1,128.00 plus $1,183.34 for a total of only $2,311.34. On or about September 6, 1982, Gilner terminated Respondent for lack of progress toward completion. At that date of termination the Respondent and his crew had been absent from the premises for five to six weeks. At the time of the Respondent's termination, the project was, by Mr. Gilner's estimation, only 40 percent completed. Although the predicate for Mr. Gilner's knowledge in this regard is less than might normally be characterized as "expert" testimony, it is still credible and based on Mr. Gilner's testimony concerning his usual employment as an installer of traffic controls involving other construction projects, and in conjunction with the testimony of Mrs. Gilner, his estimation that the extent of the household construction total led only 40 percent is accepted for purposes of this finding of fact. At this stage, based on the draws paid. 60 percent of the construction should have been completed by Respondent. The Gilners both testified that they completed the home after Respondent's termination at a total cost of $82,000, or $14,000 over the contract price. There is no evidence to support the actual amount paid or what it was paid for, nor is there any evidence to establish what relationship there may have been between Respondent's behavior and the increased cost. Although Mrs. Gilner testified that there was some misinstallation of the trusswork and that rain had damaged the roof prior to Respondent's final termination, this information, without more, will not support the $14,000 figure. Approximately August 25, 1982, in a conversation with Catherine Edwards, an employee of Landmark Truss, Respondent had explained that the reason he had not paid the Landmark Truss bill was because he had elected to use the draws he had received from the Gilners to buy some lots upon which to build ""spec" (speculation) Respondent stated to Ms. Edwards that he originally intended to get the lots "subordinated" but due to the early death of an elderly man up north, he had had to use the (5) Gilner draws to buy his lots and was awaiting profit from the speculation homes to pay landmark Trusses bill. Because this conversation occurred after Landmark Trusses had served its Notice of Claim on Mrs. Gilner, the undersigned construes this conversation to be an admission against interest by Respondent and draws the inference there from that failure of Respondent to pay the other necessary owed costs from the draws received from the Gilners resulted from the same misapplication of draw funds as Respondent described to Ms. Edwards.
Recommendation That the Construction Industry Licensing Board enter a final order providing that Respondent's certified general contractor's license shall be suspended for a five year period with the provision that the suspension shall be lifted after one year upon the Respondent providing proof to the Construction Industry Licensing Board that he has made restitution of $2,311.34 to the Gilners, $2,490.00 to Landmark Trusses, Inc., $950.00 to Chesser & Strickland Sand Co., and $2,311.34 to A-1 Air and A-1 Plumbing. DONE and ORDERED this 20th day of December 1985 in Tallahassee Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of December, 1985. APPENDIX TO RECOMMENDED ORDER, CASE NO. 84-2857 Petitioner's Proposed Findings of Fact: Accepted. Accepted Accepted. Accepted. Accepted. Accepted. Accepted Accepted. Accepted. Accepted. Accepted but expanded to conform to the evidence as a whole. Accepted but expanded to conform to the evidence as a whole. Rejected as not supported by the competent substantial evidence in the record as a whole. Accepted but rephrased to reflect the competent substantal evidence in the record as a whole. COPIES FURNISHED: Mr. James Linnan Executive Director Construction Industry Licensing Board P. O. Box 2 Jacksonville, Florida 32202 Mr. Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Salvatore A. Carpino General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Chester A. Trow, Esquire P. O. Box 1450 Ocala, Florida 32678 Patton N. Roberts 2442 Jackson Street Hollywood, Florida 33202
Findings Of Fact At all times pertinent to the issues herein discussed, Respondent Wallace W. Stewart was licensed as a registered air conditioning contractor by the Florida Construction Industry Licensing Board under License No. RA 0022169. Since at least October 1979, Respondent has been qualifying agent for the contracting firm "Stewart's Solar Energy, Inc.," with the Florida Construction Industry Licensing Board. In September 1979, Fred Johnson was acting as real estate agent for his son, Don F. Johnson of Ponte Vedra, Florida, a licensed general contractor who at the time had several residences for sale in the area. During that period, Mr. Fred Johnson engaged in a discussion with the Respondent concerning the possibility of installing a solar cooling, heating and hot water system in the house that Mr. Johnson proposed to have his son, Don, build for him in St. Johns County, Florida. Pursuant to these discussions, on September 10, 1979, Respondent prepared a proposal for Mr. and Mrs. Fred Johnson for the installation of a complete cooling and heating system and solar collectors for the purpose of domestic hot water in the said residence. Before this proposal was accepted, Mr. Fred Johnson's son, Don, discussed the terms of the proposal with the Respondent. Specifically discussed was that portion of the proposal wherein Respondent proposed to include the following: Necessary piping for circulating chilled and hot water system, perimeter heat, storage tanks for hot and cold water, necessary heat exchangers, refrigeration equipment, circulating pumps, duct system, thermostats, heat exchanger (fireplace), also piping and controls for the hot water heater. Before allowing his father to sign this proposal and accept it, Don Johnson asked Respondent exactly what he proposed to provide regarding the fireplace and was told that Mr. Stewart would provide a firebox interior, which consisted of a steel box shaped like a fireplace, to protect the heat exchanger that was to go with it. At that time, Mr. Stewart took Don Johnson into his workshop and showed him an outfit which he indicated would be similar to, if not identical to, that which he intended to install in the senior Johnson's home. It was understood that Respondent would supply the firebox and heat exchanger, but the builder was to do the masonry work and the chimney. Thereafter, based upon that understanding, Don Johnson recommended to his father that he accept the proposal, which was accomplished on or about the September 10, 1979, date; and both Fred Johnson and his wife, Christine, did so, agreeing to pay, for the complete system, the sum of $5,483 in accordance with a schedule set forth in the proposal sheet. Construction was begun and progressed to the time it was appropriate to install the firebox. At that point, Respondent told Don Johnson, the builder, he was unable to provide the firebox at that time. Since the state of construction was such that a delay in providing the firebox would hold up the continuance of construction, Respondent asked Don Johnson if he, Don, could provide the standard firebox into which Respondent would put his heat exchanger and thereafter give a credit against the purchase price. In response to this suggestion, Don Johnson told Respondent the cost would be between $400 and $500, to which sum Respondent agreed. As a result, Don Johnson put in the firebox that he procured, and Respondent thereafter put in the heat exchanger unit. Construction on the house continued until such time as, in April 1980, the house was considered sufficiently complete for Mr. and Mrs. Fred Johnson to move in. In the interim, however, in order to get the duct work done for the air conditioning and heating system he installed, Respondent, who was not licensed to perform heating and air conditioning installation in St. Johns County, Florida, arranged with Mr. Everett Masters, owner of Masters Heating and Air Service of St. Augustine, Florida, to do the duct work for the Johnson home. A building mechanical permit is not required to do duct work, and Mr. Masters did the duct work without a permit, even though he was not satisfied that the installation called for in the drawings was sufficient to accomplish the purpose of heating and cooling for a house that size. According to Mr. Masters, he did the work according to the specifications given to him, but protested to a representative of Mr. Stewart, Respondent, that the ducts were too small. In response, he was told to put the ducts in as called for in the specifications, which he did, but was never paid for the work he provided. St. Johns County Ordinance No. 76-20, an ordinance regulating contractors and the business of contracting within that county, at Section 4 thereof requires that air conditioning contractors be certified in order to conduct that business within the county. The contract involved here for the construction of Mr. Johnson's house would have required the contractor, Respondent, to have a local license to complete the air conditioning work. Respondent does not have a license in St. Johns County and never has had one. As a matter of fact, before the work was done, Mr. Don Germain, an assistant building official for St. Johns County, told Respondent in 4Z. Germain's office that he, Respondent, would need a county license at the time Respondent had come to the office prior to installing the air conditioning unit in the Johnson house. At this point, Mr. Germain discussed the project, including the rough drawing Respondent had with him, and advised Respondent at that time what permits and what licensing provisions must be fulfilled. At that time, solar heating and hot water systems did not require the license. However, the other work called for in this contract, such as the installation of the air conditioning system, would require a type of license which Respondent did not have. Germain and the Respondent had an extensive discussion on this. As it appeared to Mr. Germain, Respondent could not seem to understand why a license would be needed. A mechanical permit was issued on April 23, 1950, to Masters Heating and Air for a part of the system. A part did not include the entire installation permit. This permit applied for by Mr. Masters was acquired at the request of Don Johnson, the contractor, who pleaded with him to do so because, according to Mr. Johnson, the only way he could get final approval of the construction in order to get the elec- tricity turned on in the house was if this permit was applied for and issued. The permit in question was issued for something other than the duct work accomplished by Mr. Masters. Mr. Masters did not install the air conditioning equipment, only the ducting. The permit, if legitimate, would allow final approval of the installation of the entire air conditioning system. The information contained on the permit was provided to Mr. Masters by Respondent. According to Mr. Germain, Respondent never did get final approval of the building inspector on the total installation. The equipment was not initially accepted by the building department, since it was not a unitary unit-- in which all segments are designed to work together as a unit. However, even though the unit was rejected by the building authorities, they let the work continue based on a letter from the engineer who approved the purchase of the system, which indicated the engineer would be responsible for the working of the unit. In addition, the building officials allowed the work on Mr. Johnson's home to continue even after the discussions regarding the lack of a proper licensee because Respondent assured Mr. Germain of the building office that Mr. Masters, who was in fact a registered and licensed air conditioning contractor in St. Johns County, was going to do the work. Though the unit was basically installed in April 1980, it was not working property even up to July 3, 1980 It did not cool properly. At that point, Respondent contends he was still owed some money by Mr. Johnson. In November 1980, when it became obvious that the initially installed compressor was insufficient in size to cool a house the size of Mr. Johnson's, Respondent replaced the compressor, installing one a half ton larger than that initially installed. At that point, Don Johnson paid Respondent the sum of $800, which, according to Mr. Johnson, was the entire sum owed on the complete installation after deduction of the credit of $483 for the firebox which Mr. Johnson fabricated in lieu of that initially proposed by Respondent and which Respondent could not provide. After Respondent was paid the $800, he stopped responding to calls to service the cooling system and the heating system, even though neither worked properly at that time. Respondent admits that at some point in time he refused to continue servicing Mr. Johnson's unit and did not honor the warranty. He contends, however, that he stopped servicing because Mr. Johnson still owed him $453. The weight of the evidence indicates otherwise. Mr. Johnson ultimately hired another craftsman to repair his system, and the system was repaired without any further assistance by Respondent.
Recommendation That Respondent pay a fine of $1,000, and that Respondent's license be placed on probation for a period of two years.
The Issue Whether Respondent, a certified air conditioning contractor, committed the offenses alleged in the Administrative Complaint and the penalties, if any, that should be imposed.
Findings Of Fact At all times material to this proceeding, Respondent has been a certified air conditioning contractor, having been issued license number 1133613 on December 27, 1985. Petitioner's licensure file reflects that Respondent's license is held as follows: "Michael J. Morrow d/b/a ATM A/C & Refrigeration, Inc." (ATM). Respondent has never applied for a certificate of authority for ATM pursuant to the provisions of Section 489.119, Florida Statutes. On December 12, 1998, Carmen Schneider contracted with Sun Coast to install an air conditioning and heating unit at her residence located in Miramar, Florida. At no time has Sun Coast been a licensed air conditioning contractor. Respondent had no agreement to do any work for Ms. Schneider, and he had no agreement to subcontract the work for Sun Coast. The City of Miramar issued permit 98121104 for the Schneider job. According to its computer records, Respondent, d/b/a ATM pulled the permit for the Schneider job. The greater weight of the credible evidence established that neither Respondent nor his corporation pulled the permit for the Schneider job1 as alleged in Count II of the Administrative Complaint. Petitioner failed to establish that Respondent enabled Sun Coast to engage in uncertified or unregistered contracting in violation of Section 489.129(1)(d), Florida Statutes, as alleged in Count III. Petitioner presented an affidavit establishing that its costs of investigation of Respondent (absent attorney time) totaled $705.03. That affidavit does not state the cost of investigation for each count. On February 2, 1998, Petitioner entered a Final Order in Case Number 98-12100 that disciplined Respondent's license because he assisted an unlicensed person or entity engage in the uncertified and unregistered practice of contracting and because he proceeded on a job without a permit.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a final order that adopts the Findings of Fact and Conclusions of Law contained in the Recommended Order. It is further recommended that for the violation found for Count I, Respondent be assessed an administrative fine in the amount of $500.00 and that his license be suspended until such times he pays the administrative fine and complies with the requirements of Section 489.119, Florida Statutes. It is further recommended that Counts II and III of the Administrative Complaint be dismissed. DONE AND ENTERED this 17th day of June, 2002, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of June, 2002.
The Issue The issue is whether Respondent violated Subsection 489.129(1)(q), Florida Statutes (2008),1 by allegedly failing to satisfy within a reasonable time the terms of a civil judgment relating to the practice of the licensee's profession.
Findings Of Fact Petitioner is the agency charged with regulating building contractors in Pinellas County, Florida. Respondent is a building contractor, pursuant to license number C-6811 (RB0042337).2 Respondent is the primary qualifying agent for Timberlore Construction, Inc. (Timberlore). The business address of Timberlore is 2142 B Palm Harbor Boulevard, Palm Harbor, Florida 34683. On February 14, 2002, Timberlore contracted with Cox Air Conditioning and Heating, Inc. (Cox), for the installation of an air-conditioning system at a construction site at 19636 Gulf Boulevard, Indian Shores, Florida 33785. A dispute arose between Timberlore, as the general contractor, and Cox, as the subcontractor. As a result of the dispute, Timberlore sued Cox for breach of contract and negligence and for attorney’s fees and costs. After a non-jury trial, the court entered two final judgments. The first final judgment, entered on December 4, 2008, was a determination of liability. The court found that Cox was not liable for the failure of the air-conditioning unit that Cox had installed. Rather, the court found that excessive humidity caused the failure of the air-conditioning unit and damage to the premises and that the condition was aggravated by Timberlore. The court found that Cox was the prevailing party entitled to attorney’s fees and costs from Timberlore. The second final judgment against Timberlore determined the amount of attorney’s fees and costs. The court ordered Timberlore to pay attorney’s fees of $80,775.00 and costs of $30,423.79 plus annual interest of eight percent. Timberlore repaired the damaged air-conditioning system at the construction site. There is no harm to the consumer. Respondent disputes whether attorney’s fees and costs awarded by a court in a dispute between a contractor and a subcontractor relate to the practice of the licensee's profession within the meaning of Subsection 489.129(1)(q). The only evidence relevant to this issue was the testimony of Petitioner's witness.3 The fact-finder finds the testimony of Petitioner's witness after cross-examination to be credible and persuasive and agrees that the judgment for attorney’s fees and costs, under the facts and circumstances in this case, relates to the practice of the licensee's profession. Respondent has failed to satisfy a civil judgment obtained against the business organization qualified by the licensee within a reasonable time in violation of Subsection 489.129(1)(q).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Pinellas County Construction Licensing Board enter a final order finding Paul W. Bourdon guilty of violating Subsection 489.129(1)(q) and suspending Paul W. Bourdon's license until the judgment is satisfied. DONE AND ENTERED this 27th day of April, 2010, in Tallahassee, Leon County, Florida. S DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 2010.
The Issue The issues are (1) whether engaging in air conditioning contracting regulated by the Florida Electrical Contractors Licensing Board pursuant to Section 489.500 et seq. Part II, Florida Statutes, constitutes exceeding the scope of one's license as an electrical contractor, (2) whether performing air conditioning contracting in the name of "Dixon's Heating and Air Conditioning" constitutes operating in a name other than the name his electrical contracting license is issued in, contrary to Subsection 489.533(1)(l), and (3) whether Respondent willfully violated the building codes by venting the heater improperly, failing to get a permit and get work inspected.
Findings Of Fact Notice of hearing was given to Respondent at Route 2, Box 595, Yulee, Florida 32097. Arnold Dixon is and has been at all times material to this case a registered electrical contractor, license number ER0004417. (Pet. Ex. 1 & 2) He has maintained his address of record as Route 2, Box 595, Yulee, Florida 32097. (T-Pg. 6) He has held such license since 1976. (Pet. Ex. 1 & 2) Arnold Dixon does not hold a license, a state registration or certification to engage in contracting as a heating or air conditioning contractor. (Pet. Ex. 4 & 6) Arnold Dixon does hold a Nassau County Occupational License as an electrical contractor and as a heating and air conditioning contractor. No check of local records was conducted to see if he had a local license as an air conditioning contractor. (T-Pg. 22) On or about June 1985, the Respondent's company, Dixon's Heating and Air Conditioning, contracted to install an air conditioning and heating unit at the home of John Williams for a contract price of $1985. (Pet. Ex. 5 and T-Pgs. 10 & 11) The work on this contract was done by David Everett, who negotiated the contract. The Respondent's company, Dixon's Heating and Air Conditioning, did not obtain a permit to perform the work at the Williams' residence. Inspections on the Williams' job were not called for by Dixon's Heating and Air Conditioning. Permits and inspections were required by the applicable building code. (T-Pgs. 25 & 26) Entering into a contract to perform air conditioning and heating work and performing such work is air conditioning contracting, which is regulated under Part I, Chapter 489, Florida Statutes. After installation by Dixon's Hearing and Air Conditioning, the Williams' heating system generated carbon monoxide when operating because there was insufficient fresh air being provided to the unit. Because the air intake was in a closet which restricted the air supply to the hot air handling system, the air handling unit sucked fumes from the exhaust side of the unit back through the unit's combustion chamber and circulated it through the house. The longer the unit ran, the more debris was trapped in the louvered door of the closet and the more combustion gases were pulled through the combustion chamber and distributed through the house by the air handling unit. (T-Pg. 34) According to the manufacturer's representative, the hot air return is required to be ducted into the unit. In this case, the return air was pulled from inside a closet which had louvered doors. No duct was used and this installation was not in accordance with the manufacturer's instructions. Although the unit as installed was unsafe and had the potential to kill, no evidence was received that failure to install the unit in accordance with the manufacturer's instructions was a violation of local building code. (T-Pgs. 34- 38) Dixon's Heating and Air Conditioning did not hold itself out to be and was not engaged in electrical contracting in fulfilling the Williams' contract. Dixon's Heating and Air Conditioning did hold itself out to be an air conditioning contractor and the work performed in fulfilling the Williams' contract was air conditioning contracting.
The Issue The issue for consideration in this case is whether Respondent's license as a real estate salesperson in Florida should be disciplined because of the matters set forth in the Administrative Complaint filed herein.
Findings Of Fact At all times pertinent to the issues herein, Petitioner, Division of Real Estate, was the agency in Florida responsible for the regulation of the real estate profession and the licensing of real estate professionals within this state. Respondent was licensed as a real estate sales person and employed as such in association with Today Real Estate, Inc., a real estate corporation trading as Re/Max Today, located at 2451-1 McMullen Booth Road in Clearwater, Florida. On July 16, 1997, James E. Brown and his wife submitted an offer to purchase a house located at 9813 Palmer Drive in New Port Richey. The offer was submitted by the Browns through their real estate agent, Nancy Riley, to the sellers who were represented by Respondent. As a part of the sales package, a home inspection report was completed on July 21, 1997, which indicated that the "air conditioning does not appear to be cooling enough." Thereafter, Respondent contacted Alvarez/Taylor, a plumbing and air conditioning company, to examine the unit and a representative of that company, William Taylor, went to the property on July 25, 1997, to inspect the unit. When he arrived, he found no one there and the house locked. He contacted his dispatcher who advised him to wait, and within a few minutes, Ms. Riley showed up. She let him in the house to do the inspection. The unit was low on freon, but the big problem with the unit that Taylor found was that it was old -- about 13 years old -- and at that age, he contends, units usually lose freon. He made an oral report to Ms. Riley who authorized him in writing to do whatever work was necessary on the unit to get it working properly. He installed the freon but that did not completely correct the problem. He advised Ms. Riley that he felt the unit should be replaced because of its age. She did not seem concerned about it, but she did not authorize the repairman to replace it. When he had done what he could do, short of replacing the unit, she again signed the work order, indicating the work had been done, and he gave her the pink copy of the form. This form showed his recommendation that the unit be replaced. According to Respondent, Ms. Riley called her after the air conditioner repairman had been at the house. She said the unit was working but was an older unit and somewhere down the line would have to be replaced. Respondent also claims that Ms. Riley told her she, Ms. Riley, had called Mrs. Brown and read her the report, and the Browns "were OK with it." Respondent did not see the repairman's report until July 28, 1997. At that time, she verified the repair charge of $140.00, and when she saw the recommendation for replacement on the form, she was upset by it. Respondent claims she had not been told by Ms. Riley that there was a recommendation for replacement, and she wanted to investigate the matter. She called Ms. Riley and left a message that she wanted to talk about it, and, on the recommendation of her own air conditioning repair firm, also called Alvarez/Taylor to ask for details on the recommendation for replacement. The repairman was not available, and she was unable to speak with anyone who was aware of the problem. All she was told was that the unit was old, would need constant repair, and should be replaced. When she asked to speak with the owner, he refused to speak with her. After several unsuccessful attempts to get information from Alvarez/Taylor, still on July 28, 1997, Respondent called Ms. Riley again and was told, she claims, that the situation was not so bad and the replacement recommendation was not immediate; that the Browns knew of the situation and were OK with it; and that the Browns hoped to get another year use out of the existing unit. Respondent claims she told Ms. Riley at that time she intended to remove the recommendation for replacement from the inspection report if she didn't hear back from Alvarez/Taylor, and that Ms. Riley agreed. Ms. Riley disputes this. Thereafter, she removed the recommendation for replacement from the inspection report, and on July 30, 1997, at the closing, Respondent gave the buyers an altered copy of the report of the air conditioning repairman. On this copy, the notation in the place reserved for recommendations that the unit was 13 years old and should be replaced was not present. The closing went forward and was consummated, and the Browns were given a copy of the altered inspection report. Almost a month later, on August 26, 1997, after the closing, Alvarez/Taylor furnished the Browns with a copy of the inspection report dated July 25, 1997 which reflected, in the space reserved for recommendations, that the unit should be replaced. The unit failed, and on September 3, 1997, Alvarez/Taylor replaced the unit due to its age and condition. The replacement cost the Browns $2,315.00. When the Browns started to look into the matter, and enlisted the aid of their agent, Ms. Riley, they also contacted Respondent who told them that she had altered the inspection report because she believed she had the authority to do that as a realtor. Respondent claims she was not trying to hide anything by altering the inspection report, nor was she trying to limit the Browns "or their representatives" access to the unit. She further contends she did not intend for anyone to reply on the altered inspection report. She says she believed everyone who needed to know, Ms. Riley and the Browns, were aware of the actual recommendation for replacement, and she was merely trying to correct the situation since she could not get what she considered to be appropriate information from Alvarez/Taylor.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Florida Real Estate Commission enter a final order finding Respondent, Margaret L. Page, guilty of concealment and breach of trust, imposing a suspension of her license as a real estate salesperson for six months under such terms and conditions as the Commission deems appropriate, and imposing an administrative fine of $500.00. DONE AND ENTERED this 29th day of September, 1999, in Tallahassee, Leon County, Florida. ARNOLD H. POLLOCK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6947 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 1999. COPIES FURNISHED: Ghunise Coaxum, Esquire Division of Real Estate Department of Business and Professional Development 400 West Robinson Street Suite N-308 Orlando, Florida 32801 David C. Levenreich, Esquire 406 South Prospect Avenue Clearwater, Florida 33756 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Herbert S. Fecker, Division Director Division of Real Estate Department of Business and Professional Regulation 400 West Robinson Street Post Office Box 1900 Orlando, Florida 32802-1900