The Issue The issue for determination is whether Respondent Leon County School Board should be issued a dredge and fill permit to excavate and backfill in connection with the installation of sewage collection system pipes beneath the Alford Arm of Lake Lafayette in Leon County.
Findings Of Fact On April 13, 1989, the Board submitted a permit application to DER for the dredge and fill permit which forms the basis for this proceeding. The project represented in the dredge and fill application consisted of installation of two sewage collection system pipes beneath the Alford Arm of Lake Lafayette. Installation would be accomplished by excavating and backfilling two trenches, each approximately 50 feet long by four feet wide by two feet deep. The pipes to be installed in the trenches adjacent to Buck Lake Road are one 15-inch gravity main and one 14-inch force main. A total of 15 cubic yards of soil was proposed for excavation and replacement. The project area consisted of less than 100 square feet. The Alford Arm in the project's vicinity is a canal dredged in the 1920's and 1930's. Neither the Alford Arm nor Lake Lafayette constitute Outstanding Florida Waters (OFW), instead these water bodies are Class III Waters. On April 14, 1989, DER staff conducted an inspection of the project site, completed a permit application appraisal of the project, and issued permit no. 371633191 for the project. On the same day, the permit was withdrawn when it was discovered that the document had been signed by an unauthorized official. On April 20, 1989, DER again issued permit no. 371633191 to the Board for the project. The dredging, pipe installation, and backfilling were subsequently completed. Water Quality Since the dredging and filling could potentially produce short-term turbidity in the Alford Arm as a result of sediment entering the water, a specific condition of the permit required the placement of a row of staked hay bales downstream from the project site prior to construction and thereafter until re- vegetation of the site had occurred. By compliance with this turbidity control measure, reasonable assurance was provided by the Board that violations of state water quality standards would not result from the project construction. The project did not cause any violations of DER water quality criteria for turbidity or any other water quality criteria. Numerous technological advances and safeguards built into the sewer lines and lift stations make probability of any leakage very remote. Petitioner's concern with regard to potential for leakage from the collection system lines and the lift stations to cause water quality problems in the Alford Arm is not supported by any competent substantial evidence of record regarding statistical frequency and probability of such occurrences. Further, there is no such evidence of infirmities regarding design soundness or the functional history of the pipe used in the project. Public Interest DER evaluated the project in accordance with the criteria of Section 403.918(2), Florida Statutes, prior to issuance of the permit. Another review has now been completed approximately two years after completion of the project. The project has not and will not cause any adverse impacts on public health, safety, welfare, or property of others. Likewise, the project has not caused adverse impacts on significant historical or archaeological resources. Similarly, no adverse impacts on the conservation of fish or wildlife, including endangered or threatened species or their habitats has or will result from the project. Interestingly, woodstorks have been observed feeding in the very vicinity of the project as recently as May 28, 1991, more than two years after completion of the project. No adverse impacts have or will be visited upon navigation or flow of the water. No harmful erosion or shoaling has or will result from the project. The project has not and will not cause any adverse impacts on fishing, recreational values or marine productivity in the vicinity of the project. The impacts of this dredge and fill project were temporary. The dredged and filled area has re-vegetated with the same species, pickerelweed and smartweed. Wetland functions of the site that existed prior to the project were minimal and have been re-established. Cumulative And Secondary Impacts Cumulative impacts from similar projects were not evidenced at the final hearing. There are no projects proposed which are closely linked or causally related to the dredge and fill project. The only non-speculative secondary impact from the project was possible leakage of wastewater from the collection system lines and lift station. The probability of such leakage is very low. Particularly in view of the geographical area, engineering design and manufacture of the pipes and waste collection system, such probability is speculative and minimal or non-existent in the absence of competent substantial evidence regarding statistical frequency of such an event. The construction of the sewage collection system with which the project is associated is a result of growth in the geographic area. While the project has not been established to induce growth in the area, such development would not affect Lake Lafayette since the collection system currently installed has a 400 gallon per minute capability, or the ability to serve 400 residential connections. Prior to issuance of the dredge and fill permit, 800 existing residential lots were platted along Buck Lake Road within two miles east and two miles west of the project site. Since the system could be upgraded to accommodate 1600 residential units, the potential increase that could result from the project in any event is an additional 800 residential units. If these additional residences are built at the very high density of one per quarter acre, these lots would cover only approximately two-thirds of a square mile or less than one percent of the Lake Lafayette drainage basin of approximately 80 square miles. Such development would have no measurable impact on Lake Lafayette.
Recommendation Based on the foregoing, it is hereby recommended that a Final Order be entered approving the issuance of permit number 371633191 to the Board. RECOMMENDED this 9th day of August, 1991, in Tallahassee, Leon County, Florida. DON W.DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Fl 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of August, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-2752 The following constitutes my specific rulings, in accordance with Section 120.59, Florida Statutes, on findings of fact submitted by the parties. Petitioner's Proposed Findings. None Submitted. Respondent Board's Proposed Findings: 1.-17. Adopted in substance. Respondent Department's Proposed Findings: 1.-24. Adopted in substance. COPIES FURNISHED: Terri Saltiel 7769 Deep Wood Trail Tallahassee, FL 32311 Richard A. Lotspeich, Esq. John T. LaVia, III, Esq. P.O. Box 271 Tallahassee, FL 32302 Michael Donaldson, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esq. General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400
The Issue The issue in this case is whether the Department of Environmental Protection (DEP) should issue a permit to Out of Bounds, Inc. (Out of Bounds, or applicant), to construct, operate, and close a construction and demolition debris disposal facility (C&D facility) in Hernando County.
Findings Of Fact On September 8, 2008, Out of Bounds applied to DEP for a permit to construct, operate, and close an unlined C&D facility on 26 acres located at 29251 Wildlife Lane, Brooksville, Hernando County, Florida, to be known as the Croom C&D Debris Landfill and Recycling Facility. There were four requests by DEP for additional information, which was provided, and the application was complete on September 3, 2009. In 1994, a previous owner of the property was issued a permit to construct, operate, and close an unlined C&D facility on the property. That owner did not proceed with construction, and the permit expired in 1999. The Out of Bounds application was for a new permit, not for the renewal of an existing permit. Robert McCune owns property adjacent to the proposed C&D facility. He and his wife reside on the property, keep horses in stables on the property, and use the property for horseback riding business, which includes hosting public horseback riding events. Hernando SSK was formed by David Belcher and one or more others to continue the business being operated by Paige Cool when she died during this proceeding. The business is conducted on ten acres of property Cool owned approximately one mile west of the proposed C&D facility. Belcher is one of two co-personal representatives of Cool’s estate. Belcher and his wife hold a mortgage on the property. When the estate is finalized, the Belchers plan to assign their mortgage to Hernando SSK. It is not clear who will own the property after the estate is finalized, or how Hernando SSK will be authorized to continue the business on the property. Western pleasure and trail-riding horses are boarded on the Cool property, which is known as At Home Acres. The business also has access to 20 adjoining acres to the east, which are used for grazing. Access to the horseback riding trails in the Withlacoochee State Forest is conveniently located just across Wildlife Lane from the property, to the north. A manager resides in a double-wide trailer on the property, and another trailer and a barn to the east of it are leased out. There is a potable water well on the property, which is the source of drinking water for the manager and lessees. Well Setback In the application process, Out of Bounds disclosed two potable water wells within 500 feet of the proposed landfill disposal area. The application provided that those wells would be converted to non-potable use. Out of Bounds did not disclose the existence of a third potable water well, on property owned by Daniel Knox, which is within 500 feet of the proposed landfill disposal area. When the Knox well was brought to the attention of DEP, Out of Bounds admitted that the well was permitted for potable use but took the position that it was not for potable use because it was not in use, was not connected to a source of electricity, and appeared to be abandoned. Daniel Knox and his brother, Robert Knox, had the Knox well dug and permitted in 1979 in anticipation of using it as the source of potable water for a residence to be built on the property for their parents and sister. The Knoxes have not yet built a residence on the property, but it still is their intention to do so and to use the well as the source of potable water. Since its construction, the well had been maintained and operated periodically using a gasoline-powered generator so that it will be ready for use when needed. During the application process, Out of Bounds also did not disclose the existence of a fourth potable water well within 500 feet of the proposed landfill disposal area on property once owned by Larry Fannin and now owned by his daughter and son-in- law, Robert McCune. The McCune well was permitted and installed in mid-2005 while the sale of the land from Fannin to the McCunes was pending. The intended purpose of the well was to provide potable water for the use of the McCunes when they started to reside on the property. Despite this intent, and unbeknownst to the McCunes, Fannin had the well permitted as an irrigation well. In mid-2008, the McCunes began to reside on their property. At first, they resided in a mobile home. They ran pipes from the well to the mobile home to provide drinking water. Eventually, later in 2008, they began construction of a residence on the property and ran pipes from the well to the house to provide drinking water to the house. The well was being used for drinking water before the Out of Bounds application was complete. (They also use water from the well from time to time for irrigation purposes--i.e., when they host horseback-riding events on weekends, they truck water from the well to their horseback-riding arena to apply to the ground to control dust.) Groundwater flows from the disposal area of the proposed landfill to the west and southwest. The Knox and McCune wells are down-gradient of the groundwater flow from the proposed disposal area. Out of Bounds represented at the hearing that it would accept a permit condition that no C&D debris, but only clean debris, would be disposed within 500 feet of the Knox and McCune wells. See Fla. Admin. Code R. 62-701.200(15)-(16) and (24). However, there was no evidence of new designs, plans, or operations that would be used to meet such a permit condition. Liner and Leachate Collection Existing unlined C&D facilities in the Southwest District report various parameters that exceed groundwater quality standards and criteria. These include arsenic, benzene, iron, aluminum, nitrate, ammonia, vinyl chloride, methylene chloride, 3- and 4-methyl phenols, sulfate, and total dissolved solids (TDS). Arsenic and benzene are primary (health-based) groundwater quality standards. The others are secondary standards that relate to taste, odor, and aesthetics. The likely source of the reported arsenic violations in the Southwest District is wood treated with chromate copper arsenate (CCA). See Fla. Admin. Code R. 62-701.200(11). Out of Bounds proposes to not accept CCA-treated wood and to use a trained “spotter” to exclude CCA-treated wood from the landfill. This is an appropriate measure to prevent arsenic violations, and is now required for C&D facilities. See Fla. Admin. Code R. 62-701.730(7)(d), (8), and (20). It was not clear from the evidence whether the C&D facilities in the Southwest District with arsenic violations accepted CCA-treated wood. Even if they did, the operational plan proposed by Out of Bounds to exclude CCA-treated wood and to use a trained spotter is not a guarantee that no CCA-treated wood will enter the landfill. A C&D facility would not be expected to dispose of material that would result in benzene contamination. The reported benzene violations suggest that unauthorized material contaminated with benzene nonetheless makes its way into C&D facilities in the Southwest District. The evidence was not clear whether a trained spotter was used at those facilities. Whether or not a spotter was used at those facilities, having a trained spotter would not guarantee that no benzene-contaminated material will enter the landfill proposed by Out of Bounds. Out of Bounds suggested that ammonia violations result from C&D facilities accepting yard trash. However, there was no evidence of a connection between acceptance of yard trash and ammonia violations. The operational plan proposed by Out of Bounds to “cover as you go” is the accepted best practice to control hydrogen sulfide odor, which comes from wet drywall. Out of Bounds suggested that its cover plan would prevent any sulfate violations, but there was no evidence to prove it. There was no evidence as to whether the C&D facility proposed by Out of Bounds would be substantially different from the other existing C&D facilities in DEP’s Southwest District. Absent such evidence, Out of Bounds did not provide reasonable assurances that its proposed facility would not cause groundwater quality violations. The site for the C&D facility proposed by Out of Bounds is internally drained. There are no surface waters onsite or within a mile of the site. There was no evidence of a surficial aquifer above the Floridan aquifer. Rainfall entering the Out of Bounds property migrates downward into the Floridan aquifer. Once in the aquifer, there is a horizontal component of groundwater water flow in a generally southwest direction, towards the Knox and McCune wells. Contaminated leachate from the proposed C&D facility would migrate with the groundwater. Out of Bounds suggests that a thick clay layer under the site of its proposed facility would prevent the downward migration of groundwater into the Floridan aquifer. There are several reasons why the clay layer does not provide the reasonable assurance of a liner that contamination from the proposed landfill would not reach the Floridan aquifer. Clay is much more permeable than a geomembrane meeting DEP’s specifications for use as a liner. The clay on the proposed site is on the order of at least a thousand times more permeable. (Out of Bounds appeared to confuse the permeability of such a geomembrane with the allowable permeability of the geosynthetic clay layer or compacted clay layer underlying the geomembrane. Cf. Fla. Admin. Code R. 62-701.730(4)(f).) In the application process, Out of Bounds relied on the clay layer for purposes of sinkhole prevention and mitigation, not for reasonable assurance that no liner was needed. The limestone formation underlying the site is highly variable, with numerous pinnacles; for that reason, the thickness of the clay layer also is highly variable, making it difficult to excavate the proposed landfill with complete assurance that the clay layer would not be penetrated. To provide reasonable assurance for purposes of sinkhole prevention and mitigation, Out of Bounds proposed to leave or create a clay layer at least six feet thick underlying the bottom of the proposed landfill. Because the site is in an area of high recharge to the Floridan aquifer and drains entirely internally, the clay layer alone does not provide reasonable assurance that there will be no downward migration of contaminated groundwater to the Floridan aquifer. Reasonable assurance requires a liner and leachate collection system.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that DEP deny the application for a C&D facility made by Out of Bounds. DONE AND ENTERED this 8th day of December, 2011, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of December, 2011. COPIES FURNISHED: Ronda L. Moore, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 John R. Thomas, Esquire Law Office of John R. Thomas, P.A. 233 Third Street North, Suite 101 St. Petersburg, Florida 33701-3818 Timothy W. Weber, Esquire Battaglia, Ross, Dicus & Wein, P.A. Post Office Box 41100 St. Petersburg, Florida 33743-1100 Herschel T. Vinyard, Jr., Secretary Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 Thomas Beason, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 Lea Crandall, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000
The Issue The issue in this case is whether Niagara Bottling Company, LLC (Niagara), is entitled to Consumptive Use Permit (CUP) No. 114010 issued by the St. Johns River Water Management District (District), which authorizes Niagara to withdraw and use 484,000 gallons per day (gpd) of groundwater to produce bottled water at a facility in Lake County.
Findings Of Fact The Parties Groveland is a municipal corporation located in Lake County. Niagara is a water bottling company registered to do business in Florida. Niagara currently owns and operates six water bottling facilities in the United States, including a bottling facility in unincorporated Lake County, northwest of Groveland. Niagara currently operates one bottling line at its Groveland facility, which can be used to bottle either spring water or purified water. The District is a special taxing district created by the Florida Water Resources Act of 1972, with jurisdiction over a sixteen-county area that includes Groveland and the site of Niagara’s proposed water withdrawal. The District administers a permitting program for the consumptive use of water. The Proposed Permit The top geologic layer in the region is the surficial aquifer, which starts at the ground surface and extends down about 50 feet to the Intermediate Confining Unit. Below the Intermediate Confining Unit is the Upper Floridan Aquifer, which starts at a depth of about 150 feet and extends downward to about 550 feet below the ground surface. Below the Upper Floridan Aquifer is the Middle Semi-Confining Unit, which extends down another 450 feet. Below the Middle Semi-Confining Unit is the Lower Florida Aquifer, which extends down to about 2,200 feet below sea level. Nearly all of the groundwater withdrawn for consumptive uses in central Florida comes from the Upper Floridan Aquifer. Groveland’s public water supply wells, for example, withdraw water from the Upper Floridan Aquifer. The proposed CUP authorizes Niagara to withdraw 484,000 gpd from the Upper Floridan Aquifer to produce bottled water. The CUP authorizes the installation of three water supply wells for the facility: a 16-inch production well, a 16-inch backup well, and a 4-inch supply well for domestic uses at Niagara’s facility. Of the 484,000 gpd that Niagara would withdraw, approximately 454,000 gpd would be treated and bottled as “purified water” and approximately 30,000 gpd would be used for cooling some of the equipment used in the bottling process. Under federal regulations, bottled water sold as purified water must meet certain maximum contaminant levels, including a total dissolved solids (TDS) level of less than 10 parts per million. By regulation, purified water is distinct from tap water and from bottled spring water. Niagara would treat the groundwater by filtration and reverse osmosis (RO), primarily to remove TDS. At a customer’s request, minerals can be added to the water to enhance taste. Also before the water is bottled, it disinfected with ozone. The RO process at the Niagara facility is projected to turn 454,000 gpd of groundwater into about 363,000 gpd of purified drinking water for bottling and 91,000 gpd of RO concentrate/wastewater. Reject water from the cooling water system would add some additional wastewater. Niagara has arranged to send its RO concentrate to the Frozen Grove Wastewater Treatment Facility to be blended and used for irrigation at the Mission Inn Golf and Tennis Resort in Howey-in-the-Hills. The City of Minneola has also agreed to take Niagara’s RO concentrate. Niagara and the District requested that the proposed CUP be modified to add the City of Minneola wastewater treatment facility as an alternative recipient for Niagara’s RO concentrate. Niagara and the District propose the following change to Condition 10 of the Technical Staff Report: Withdrawals of groundwater from Well Nos. 1 (GRS Id No 145009) and 2 (GRS Id No 145010 for commercial/industrial type use shall not be initiated until Niagara Bottling LLC and the Frozen Grove WWTF or alternatively Niagara Bottling LLC and the City of Minneola WWTF have obtained all necessary permits to create and use the blend of process waste water (R/O concentrate) and reclaimed water for irrigation, as described in Attachment 4 of the application materials submitted to the District on May 9, 2008 for the Frozen Grove WWTF and the material submitted to the District on March 4, 2009 for the City of Minneola WWTF. The permittee shall provide documentation to the District that the necessary permits have been obtained within 30 days of initiating withdrawals of groundwater for commercial/industrial type use from Well Nos. 1 (GRS Id No 145009) and 2 (GRS Id No 145010). The proposed CUP includes a conservation plan with provisions for monitoring water use, repairing leaks, conducting quality assurance inspections, using totalizing flow meters, and minimizing spillage. Niagara’s proposed CUP contains conditions for environmental monitoring. Niagara would be required to collect water level and rainfall data, and basic vegetation and soils conditions at Lake Arthur. Lake Arthur was selected for monitoring because hydrologic modeling indicated that Niagara’s greatest potential impact to the water table was near Lake Arthur. The monitoring is intended to detect any unexpected adverse environmental impacts caused by Niagara’s proposed withdrawal so that they can be addressed. The proposed permit has an expiration date of December 31, 2013. Stipulations and Withdrawn Claims Before the final hearing, Groveland withdrew a number of allegations made in its Second Amended Petition for Hearing. Groveland stated that its intent was to withdraw the claims that its substantial interests were affected by Niagara’s proposed groundwater withdrawal. Groveland no longer contends that it would be specially injured by the proposed water use. In the parties’ Joint Pre-Hearing Stipulation, Groveland stipulated that Niagara’s proposed water use would not interfere with any legal uses of water. Groveland also stipulated that Niagara’s proposed use would not cause adverse or significant impacts to lake stages or vegetation, would not impact adjacent land uses, would not cause significant saline water intrusion, would not cause or contribute to flood damage, would not harm the quality of the water source, would not cause or contribute to a violation of state water quality standards, would not impact minimum flows and levels established by the District, would not cause the water table or aquifer potentiometric surface to be lowered so that lake stages or vegetation would be adversely and significantly affected, would not affect spring flows or water levels, and would not use water reserved by the District from consumptive use. The record evidence supports the stipulations identified above. Economic and Efficient Utilization The Upper Floridan Aquifer is capable of producing the requested amount of water. Florida Administrative Code Rule 40C-2.301(4)(a) and Section 10.3(a) of the Applicant’s Handbook require that a water use be in such quantity as is necessary for economic and efficient utilization. The District’s determination of economic necessity focuses on preventing “water banking,” which is securing rights to water in excess of an applicant’s actual needs, for possible future use. Niagara’s 484,000 gpd allocation is based on the peak maximum daily output of the processing equipment operating at 74 percent capacity, which is the average capacity that Niagara achieves at its bottling facilities. Groveland contends that the consumer demand for bottled water could be met by other water bottlers and, therefore, there is no need for Niagara’s proposed withdrawal. However, no statute or rule requires Niagara to demonstrate that this particular CUP is the only means to meet the consumer demand for bottled water. The District’s evaluation of need focuses on the applicant’s need for the requested volume of water. In determining whether a requested use of water is necessary, the District does not evaluate the appropriateness of the associated business or activity, but only whether the applicant can reasonably be expected to use the requested volume of water, and do so efficiently based on industry standards. The evidence presented regarding the bottled water market and Niagara’s position in the market was sufficient to demonstrate that the requested volume of water is necessary through the duration of the CUP. The 30,000 gpd that Niagara would use for its cooling system is a reasonable amount of the water for that purpose. The technology to be used at Niagara’s facility is state-of-the- art, using constant online monitoring to reduce reject water. The cooling equipment and its operation have been designed to minimize water use. RO is the industry treatment standard for production of purified bottled water. It is the most cost-efficient treatment method in terms of energy use and water consumption. The proposed RO equipment and its operational parameters are designed to optimize treatment efficiencies. The volume of RO concentrate that would be produced depends on the TDS levels in the groundwater. The estimate of 91,000 gpd of RO concentrate is conservatively high, based on the TDS levels in groundwater samples. The actual volume of RO concentrate produced by Niagara could be smaller. Groveland was critical of Niagara’s wastewater volume, contending that the conversion of 91,000 gpd of groundwater to wastewater is inefficient and contrary to the public interest. The fact that Niagara’s bottling process would produce 91,000 gpd of wastewater does not make it inefficient. Nearly every commercial and industrial water use has a wastewater component. In the context of water bottling processes and water treatment systems, Niagara’s operation is efficient. Groveland asserts that sending Niagara’s RO concentrate to the Mission Inn golf course or the City of Minneola for irrigation purposes is inefficient because a large portion of irrigation water is usually lost to evaporation and does not recharge the aquifer. This assertion fails to account for the fact that every gallon of RO concentrate used for irrigation reduces by one gallon the volume of groundwater that would otherwise be withdrawn for irrigation. Using Niagara’s wastewater for irrigation contributes to the efficiency of Niagara’s proposed use. There is typically a deficit of reclaimed water from public wastewater treatment systems in the summer when the demand for reclaimed water for irrigation and other purposes increases. Niagara’s supply of RO concentrate, however, would remain constant throughout the year. Mission Inn and Minneola would benefit if they were able to use Niagara’s RO concentrate. Niagara’s conservation plan for water use at its facility is equal to or better than the conservation plans incorporated into the CUPs that the District has issued to other beverage bottlers. Niagara’s proposed use was shown to be of such a quantity as is necessary for economic and efficient utilization. Sources of Lower Quality Water Florida Administrative Rule 40C-2.301(4)(f) states that reclaimed water must be used if it is “readily available.” Section 10.3(g) of the Applicant’s Handbook requires that the “lowest acceptable quality water source, including reclaimed water or surface water” must be used for a consumptive use, unless the applicant demonstrates that the use of a lower quality water source is not economically, environmentally, or technologically feasible. The requirement to use a lower water quality source, however, is not applicable when the water is for “direct human consumption” or human food preparation. § 10.3(g), Applicant’s Handbook. Groveland argues that the word “direct” should mean unaltered and, therefore, Niagara’s bottled water is not intended for direct human consumption because the water is treated before it is bottled. The District, however, does not interpret or apply the term “direct human consumption” to mean drinking water directly from the source without treatment. In the case of the water delivered to households and businesses by public water suppliers, which also must be treated before it is delivered, the District regulates the water as being for direct human consumption. The fact that Niagara would filter the groundwater, apply RO treatment, add acid to prevent mineral buildup in the RO equipment, and add minerals for taste if requested by customers, does not disqualify Niagara’s bottled water as being for direct human consumption. Because 454,000 gpd of Niagara’s proposed water withdrawal would be processed for direct human consumption, Niagara did not have to seek to use a source of lower water quality for that volume. The requirement to use available sources of lower quality water would apply to the 30,000 gpd that Niagara intends to use for cooling. There are technical and economic problems associated with using water of lower quality for the cooling process at the Niagara facility because higher TDS levels would damage the cooling equipment. Using water with higher TDS levels would also require greater volumes of water to achieve cooling. Niagara’s cooling system is designed to reject water when the dissolved solids reach a certain high level, and to replace the reject water with fresh water. Operating at higher dissolved solid levels would cause the system to reject water more frequently, so greater volumes of water would be needed for cooling and greater volumes of wastewater would be generated. Using surface water from the St. Johns River, which has TDS levels much higher than in the groundwater, would require twice as much water to operate Niagara’s cooling system. In addition, a 44-mile pipeline would be needed to convey water from the St. Johns River to the Groveland facility, which would involve much higher costs. Seawater has even higher TDS levels and would require desalinization and a different cooling system. Using seawater would require much greater volumes of water for treatment and cooling. Disposal of the brine concentrate generated by the treatment process would create additional costs. The use of seawater would require the construction of a 120-mile pipeline, which would involve large capital and operating costs. Groveland insists that the much higher costs associated with these sources of lower quality water are still economically feasible for Niagara based on Niagara’s projected income from its bottling operations. The District does not determine feasibility based on the balance sheet of the individual permit applicant. The District evaluates relative costs of alternative sources in the context of normal practices and expected benefits. Reliable volumes of reclaimed water to use in Niagara’s cooling system are not readily available to Niagara from domestic wastewater treatment facilities in the area. The spring water sources that Niagara is currently using are not sources of lower quality water. These sources are of equivalent quality to the groundwater that Niagara proposes to withdraw. Groveland contends that Niagara did not investigate the quality of the Lower Floridan Aquifer as a potential source of lower water quality water for Niagara’s proposed use. Groveland believes, but did not prove, that the Lower Floridan has lower quality water. Studies conducted by the U.S. Geological Survey indicate that the water quality of the Lower Floridan Aquifer is about the same or better quality than the quality of the water in the Upper Floridan Aquifer. Water quality data from a Lower Floridan well in the vicinity also indicates that the quality of the water in the Lower Floridan is as good as, or better than, the water quality in the Upper Floridan in this area. Withdrawals from the Lower Floridan create a risk of saline water intrusion into the fresh portion of the Lower Floridan or Upper Floridan. Niagara demonstrated that it is not technically nor economically feasible to use a source of lower quality water for its cooling water. Individual Effect on Wetlands and Lakes To identify the “zone of influence” of Niagara’s proposed withdrawal of water and to assess the individual and cumulative effects of the drawdown associated with the withdrawal, Niagara’s consulting hydrogeologist used a steady- state numerical groundwater model developed by the District, known as the East Central Florida (ECF) groundwater model. It is a steady-state model, which produces a value that represents a long-term average effect. The ECF model predicts the level of drawdown in the surficial aquifer. The model assumes that wetlands and other surface waters are directly connected to the surficial aquifer so that a given drawdown of the surficial aquifer causes the same drawdown of the water levels in wetlands and other surface waters. The ECF model is calibrated to water level data from 1995. A drawdown predicted by the model is a drawdown from 1995 water levels. The ECF model results are graphically depicted as drawdown contours that are overlaid on aerial photography. The District considers the condition and functions of the surface waters in and around the withdrawal site to determine how they might be affected by a predicted drawdown. The dominant surface waters in the area of the proposed withdrawal are sand hill lakes. There are few wetlands. In sand hill lake systems, water table levels fluctuate widely, as much as eight or ten feet. Consequently, these systems are colonized by herbaceous plants that are adapted to widely fluctuating water levels. The wetlands and lakes in the area are not currently showing signs of environmental harm as a result of existing groundwater withdrawals. Niagara’s modeling predicted that the proposed water withdrawal, by itself, would cause a maximum drawdown in the surficial aquifer of 0.1 feet, except for one small area where the predicted drawdown was 0.2 feet. All the expert witnesses were in agreement that Niagara’s drawdown, by itself, is unlikely to cause environmental harm. In fact, the impacts of such a small drawdown on the physical conditions or functions of wetlands or lakes in the area would probably be impossible to detect. Cumulative Effect on Wetlands and Lakes For the analysis of cumulative impacts, the ECF model takes into account all permitted withdrawals for the year 2013, because that is the key year for the regulation of water uses in the Central Florida Coordination Area (CFCA), which includes the site of Niagara’s bottling facility. The CFCA is discussed in greater detail later in this Recommended Order. The ECF model predicated that the cumulative surficial aquifer drawdown within the area of influence of Niagara’s proposed withdrawal would be less than one foot except for one small area where the drawdown is predicted to be 1.1 feet. Niagara submitted an environmental assessment report, the Lotspeich report, with its permit application. The Lotspeich report concluded that no ecological harm would be caused by Niagara’s proposed withdrawal. Subsequently, Niagara’s consulting ecologist, Dr. Shirley Denton, who has extensive experience with the effects of drawdowns on wetlands and other surface waters, reevaluated the potential effects of Niagara’s proposed withdrawal. Dr. Denton visited all of the natural systems in the field. It was her opinion that the cumulative drawdown would not cause unacceptable harm to these natural systems. The District’s environmental expert agreed with Dr. Denton. In the Central Florida sand hill lakes area, a drawdown of this magnitude is not an uncommon cumulative impact from groundwater withdrawals that the District has determined to be acceptable. Groveland presented the testimony of Dr. Jay Exum who opined that the cumulative drawdown in the area of Niagara’s proposed withdrawal would adversely impact wetlands. Dr. Exum’s opinion was based on his prediction that the cumulative drawdown would result in a substantial reduction in the size of the wetlands in the area. However, his opinion about the loss of wetland acreage is not persuasive because of the unconventional methodology2/ that he used and the unreasonable assumptions upon which his opinion was based. Dr. Exum reviewed land cover maps of Lake County, calculated the size and topography of eight wetlands in the area (only one was within Niagara’s zone of influence), came up with an estimated reduction in wetland acreage for these wetlands, and then extrapolated from that number a prediction of the total area of wetlands within Niagara’s area of influence that would be lost as a result of the cumulative drawdown. Dr. Exum did not account for the fact that the wetlands and lakes in the area already reflect most of the cumulative drawdown. The cumulative drawdown predicted by the modeling is not a drawdown below today’s average water levels; it is a drawdown below 1995 levels. In addition, Dr. Exum assumed that a drawdown in the surficial aquifer of .5 foot will cause the future loss of the vegetation at the outer edges of a wetland in an amount that can be calculated simply by determining how much area .5 feet of water would occupy. That assumption would only apply in a hypothetical, unnatural situation where water levels are constant and the wetland vegetation will not survive if the water table drops .5 feet. However, the actual situation is that the water table fluctuates widely in these natural systems and the vegetation is adapted to the fluctuations. The area “formerly” occupied by the .5 feet of water could still be inundated frequently enough to sustain the vegetation. Dr. Exum’s opinion about the environmental effects that would be caused by the cumulative drawdown of the surficial aquifer was given less weight than the opinions offered by Niagara’s and the District’s ecologists because Dr. Exum has little or no prior experience with the effects of drawdowns on natural systems. Dr. Exum’s professional experience is almost entirely with the impacts associated with construction activities in or near wetlands, which would not acquaint him with the unique, long-term responses of natural systems to water table drawdowns caused by groundwater withdrawals. Dr. Denton, who has over 25 years of experience with monitoring wetlands affected by groundwater withdrawals, stated that drawdowns in the surficial aquifer do not usually cause reductions in the size of a wetlands. The more persuasive evidence in the record demonstrates that Niagara’s proposed withdrawal would not cause adverse impacts to wetlands on an individual or a cumulative basis. Niagara provided reasonable assurance that any environmental harm caused by the proposed use has been reduced to an acceptable amount. The five-year duration of the permit is reasonable and appropriate. Public Interest Section 9.3 of the Applicant’s Handbook defines “public interest” as: those rights and claims on behalf of the people in general. In examining whether an application is consistent with the public interest, the District considers whether a particular use of water is going to be beneficial or detrimental to the overall collective well-being of the people or to the water resource in the area, the District and the State. The policy and practice of the District has been to limit its public interest analysis to matters directly related to water resources and the management of those resources. Other matters, such as vehicle traffic generated by the applicant, are not considered by the District. Groveland suggests that Niagara’s proposed use, and perhaps all commercial/industrials uses, are less important and worthy than public water supply uses like its own, and should not be allowed to take water that a public water supplier might need in the future. As discussed in the Conclusions of Law, all reasonable beneficial uses of water are equal under Chapter 373, except in certain contexts which are not applicable here. Commercial and industrial activities that make consumptive uses of water, when conducted in conformance with regulations established to efficiently use and protect the water resources, are generally beneficial to the collective well-being of the people. Groveland also claims that Niagara’s CUP is not in the public interest because a portion of Niagara’s bottled water will be shipped out of Florida. Although Niagara cannot project precisely the amount of bottled water that would end in the hands of consumers residing out-of-state, an estimate of 20 percent was given. For beverage bottlers or any other commercial or industrial water users that incorporate water into their products, the District deems the location of the water use to be where the water is bottled or incorporated into the products. The District does not look to where products are ultimately purchased by a retail consumer. Therefore, the District did not consider the fact that a portion of Niagara’s bottled water would be consumed outside of Florida as a factor in the District’s determination of whether the proposed water use is in the public interest. Niagara’s withdrawal is within the Central Florida Coordination Area (CFCA), an area covering parts of the jurisdiction of three water management districts and which includes the City of Groveland and the site of Niagara’s proposed water withdrawal. The CFCA is a highly productive area for groundwater withdrawals, but the water management districts have determined that it does not have sufficient water to serve water needs above the levels that have been allocated through the year 2013. To protect the water resources of the CFCA, rules were adopted to require public water suppliers and other water users within the CFCA to use “supplemental water supplies” to meet their increases in demand after 2013. Supplemental water supplies are identified in the CFCA rules as reclaimed water, stormwater, surface water, and seawater desalinization. Niagara is not requesting additional water above its 2013 demand and, therefore, is not subject to the restrictions imposed by the various CFCA rules. Nevertheless, the District treated Niagara’s location within the CFCA as a matter affecting the public interest. The District determined that it was inconsistent with the public interest to allow Niagara to withdraw groundwater in the CFCA unless Niagara was required to participate in the development of supplemental water supplies. Therefore, Niagara is required by “Other Condition” 14 in the District’s Technical Staff Report, to identify potential partners for the development of supplemental water supply projects, determine the viability of developing the partnerships, evaluate potential supplemental water supply projects available, and submit a comprehensive written report evaluating whether identified projects are feasible future water supply sources for Niagara. The District imposed a permit expiration date of December 31, 2013, to enable the District and Niagara to reevaluate Niagara’s ability to use a lower quality water source after that date. Groveland does not believe the conditions imposed by the District go far enough and asserts that Niagara’s water withdrawal from the CFCA is still contrary to the public interest. Niagara’s proposed withdrawal is also within a Priority Water Resource Caution Area (PWRCA) designated by the District. The District designates priority water resource caution areas as part of its water supply 20-year planning process. In the PWRCA, the District has determined that there is inadequate groundwater in the Floridan Aquifer to meet all existing and future water needs, without having unacceptable impacts on the water resources. The District stated that the designation of a priority water resource caution area is strictly a planning tool and does not preclude the issuance of permits. CUPs are commonly issued for proposed withdrawals in priority water resource caution areas in the District.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the District enter a final order granting Consumptive Use Permit No. 114010 with the conditions specified in the Technical Staff Report and the additional condition proposed by the District and Niagara and set forth in paragraph 12, above. DONE AND ENTERED this 7th day of August, 2009, in Tallahassee, Leon County, Florida. BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of August, 2009.
Findings Of Fact Respondent is an individual who owns or operates a water system that provides piped water for human consumption to the Hardy House Diner in Washington county, Florida. The water system serves at least 35 persons daily at least 60 days out of the year. Respondent has owned or operated the water system since at least October 28, 1976. Respondent does not continually apply effective disinfectant measure to the water distributed to the customer of the Hardy House Diner, nor is Respondent's water system equipped with any disinfection equipment. Respondent's water system has a daily flow greater than 2,500 gallons per day, but less than 100,000 gallons per day. The operation, maintenance and supervision of the water system is not performed by a person who has passed an examination that entitles such a person to be a certified operator. Neither the Department nor the Washington County, Florida Health Department has received from Respondent reports which contained information about the operation and maintenance of the Respondent's water system. The water system's lack of disinfectant equipment and the absence of a certified operator for the system and Respondent's failure to file operation reports have existed continuously since "October, 1976. Representatives of the Department conducted a public water systems inspection of Respondent's water system on October 26, 1976. At that time, the system was found to be unsatisfactory in several categories, including general plant condition, existence of safety hazards, lack of chlorination, failure to submit regular reports, failure to submit monthly bacteriological samples, failure to perform chemical analysis of drinking water and failure to install a raw water tap between the pump and point of chlorination. A second inspection was performed on April 7, 1977, in which it was determined that Respondent still had not installed a chlorinations system, had failed to submit monthly operating reports had failed to employ a certified operator, had failed to submit monthly bacteriological samples, and had failed to perform annual chemical analysis of water disposed from the system. On December 7, 1977, a representative of the Department whose job responsibilities included inspecting public water systems was refused permission to enter and inspect the water system serving the Hardy house diner and its customer. The Department representative was refused entry after he had identified himself and made his purpose known to Respondent. The Department has incurred expenses of $117.58, including personnel time and travel expense, in the course of investigating Respondent's alleged violations.
Recommendation RECOMMENDED: That a final order be entered by the State of Florida, Department of Environmental Regulation, finding the Respondent to be in violation of the above-referenced statutes and regulations, and requiring Respondent to pay the state its reasonable costs and expenses, in the amount of $117.58 incurred in investigating and prosecuting this administrative proceeding. RECOMMENDED this 26th day of February, 1979, at Tallahassee, Florida. WILLIAM E. WILLIAMS, Hearing Officer Division of Administrative Hearings The DeSoto Building 2230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of February, 1979. COPIES FURNISHED: Vance W. Kidder, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Mr. Eugene Hardy 1005 Highway 90 West Chipley, Florida 32428 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION, Petitioner, vs. CASE NO. 78-1209 DER Case No. WC-10-78 EUGENE HARDY, Respondent. /
Findings Of Fact On May 4, 1979, the Department received from Hudson an Application for Variance from Rules 1704.244(1)(f), 1704.244(1)(h)(1), 1704.244(1)(i)(1) and 1704.4244(4), Florida Administrative Code. The request was for a period of twenty four months and was prompted by Hudsons alleged inability to meet the standards set forth in the rules at a secondary waste water treatment facility which is operated in conjunction with a pulp and paper plant in Palatka, Florida. The wastewater is discharged from the plant into Rice Creek and from the creek into the St. Johns River. Hudson stated in its request for a variance that no technology exists, now or in the foreseeable future, which would enable Hudson to meet the rule standards. Hudson further stated that it is presently utilizing the best available technology economically feasible at its Palatka plant. After reviewing the Application for Variance, the Department requested additional information concerning Hudson's application which involved: Hudson's inability to meet applicable water quality standards within the 800 meter mixing zone set forth in Rule 1704.244(1)(f), Florida Administrative Code. Hudson's inability to meet water quality standards within 10 percent of the total length of Rice Creek as required by Rule 1704.244(1)(h)(1), Florida Administrative Code. Hudson's inability to meet a dissolved oxygen level of not less than 4 mg/1 as required by Rule 17-4.244(1)(i)(1), Florida Administrative Code. and Hudson's inability to meet a minimum dissolved oxygen level of 1.5 mg/1 at any time or place. Due to its alleged inability to meet the applicable standards, Hudson proposed that the zone of mixing be extended into the St. Johns River and that average and minimum dissolved oxygen levels be inapplicable in the extended mixing zone. Hudson clarified its request on July 11, 1979, to include in the mixing zone that portion of Rice Creek between Hudson's point of discharge and Rice Creek's confluence with the St. Johns River and 2000 feet beyond the confluence into the river. Additionally, Hudson clarified its request for average and minimum dissolved oxygen levels 0.0 mg/1, respectively, within the modified mixing zone. On August 24, 1979, the Department issued a Notice of Intent to approve the variance subject to the following conditions: That the variance be in effect for a period of not ore than 24 months. That Hudson study alternative discharge and monitoring systems with details and scope of the studies to be approved prior to the effective date of the variance. That Hudson utilize its treatment facilities to the maximum extent to minimize BOD5 loading into Rice Creek and maximize dissolved oxygen levels. Within two months of the effective date of the variance, Hudson is to provide the Department a report outlining how the company will meet this requirement. That Hudson continue to apply new technology as it becomes available and conduct ongoing studies in this area and submit the same to the Department upon completion and That Hudson continue to study, stress and utilize water reuse conservation techniques to reduce the amount of water consumed per ton of product produced. Subsequently, the Department received from Hudson a technical program for continued water quality studies at Rice Creek. Following further communications and discussions, Hudson and the Department agreed on a six month study to replace the two month requirement concerning dissolved oxygen levels in the effluent. Eventually, the Respondents agreed on a study to encompass conditions 5(b) and (c) set forth, supra. Following receipt of a letter to the Department from the Florida Game and Fresh Water Fish Commission, Hudson agreed to incorporate into its study the issues raised by that agency. At the formal hearing the Petitioner and Intervenor, an adjoining property owner, pressed their objections to the Department's intent to issue a variance to Hudson. Hudson demonstrated that its wastewater treatment system at its Palatka facility utilizes the most effective and technologically advanced treatment system available. Hudson has made a major commitment towards upgrading its treatment facilities as new and practicable treatment technologies become available. Hudson's Palatka plant has the highest quality of effluent of any paper mill operating in the state. Hudson is unable to meet the present standards for discharge due primarily to the classification of Rice Creek as a Class III water body. Although classified as a Class III water, Rice Creek, even in the absence of the Hudson discharge, would be unable to meet the standards of the Florida Administrative Code for such waters at all places and times. There is no practicable technology currently available which would enable Hudson to meet Class III water standards. Hudson's annual average for discharge of Biochemical Oxygen Demand ("BOD") and Total Suspended Solids ("TSS") exceeded the Best Available Technology ("BAT") standard proposed by the Federal Environmental Protection Agency by 47% and 22% respectively. Hudson's permit levels only require the standards to be exceeded by 20% and 19%, respectively. Despite Hudson's good faith efforts to meet water quality standards, it is not presently possible to meet Class III criteria for discharge into the St. Johns River. Accordingly, a variance is required from the mixing zone and dissolved oxygen provisions of Chapter 17-4 Florida Administrative Code, if Hudson is to continue in operation. In the intended mixing zone proposed by Hudson, dissolved oxygen levels of 0.0 mg/1 could be expected at certain times of the year and under certain conditions. The variance does not authorize Hudson to discharge at levels in excess of its present permits. If the Palatka plant were to close, Putnam County and a surrounding area would experience severe economic harm due to the tremendous impact the plant has on the local economy. The water quality of the St. Johns River is not significantly affected by the discharge into Rice Creek.
The Issue The issue in this case was whether the Respondent, City of Cape Coral (City), was entitled to an Individual Environmental Resource Permit (Permit) that would allow removal of the Chiquita Boat Lock (Lock) and associated uplands, and installation of a 165-foot linear seawall in the South Spreader Waterway in Cape Coral, Florida.
Findings Of Fact Based on the parties' stipulations and the evidence adduced at the final hearing, the following findings of fact are made: The Parties The Department is the administrative agency of the State of Florida statutorily charged with, among other things, protecting Florida's water resources. As part of the Department's performance of these duties, it administers and enforces the provisions of chapter 373, part IV, Florida Statutes, and the rules promulgated thereunder in the Florida Administrative Code. Pursuant to that authority, the Department determines whether to issue or deny applications for environmental resource permits. The City is a Florida municipality in Lee County. The City is the applicant for the Permit allowing the removal of the Lock and installation of a seawall (Project). The Project is located within the geographic boundary of the City. The South Spreader Waterway is a perimeter canal separating the City's canal system from shoreline wetlands to the west and south, which run the length of Matlacha Pass to the mouth of the Caloosahatchee River at San Carlos Bay.1/ The Association is a Florida non-profit corporation that was created in 1981. The Association was created to safeguard the interests of its members. The Association has approximately 150 members who reside in Matlacha and Matlacha Isles, Florida. A substantial number of its members have substantial interests in the use and enjoyment of waters adjacent to and surrounding Matlacha. The Association's members were particularly interested in protecting the water quality of the surface waters in the area. Matlacha is an island community located to the northwest of Cape Coral, the South Spreader Waterway, and the Lock. Matlacha is located within Matlacha Pass Aquatic Preserve. Matlacha Pass is classified as a Class II waterbody designated for shellfish propagation or harvesting, and is an Outstanding Florida Water (OFW). See Fla. Admin. Code R. 62-02.400(17)(b)36; 62-302.700(9)(h). Petitioner, Karl Deigert, is a resident and property owner in Matlacha. Mr. Deigert is the president of the Association. Mr. Deigert’s house in Matlacha is waterfront. He holds a captain’s license and has a business in which he gives sightseeing and ecological tours by boat of the waters around Matlacha. He fishes in the waters around his property and enjoys the current water quality in the area. He is concerned that removal of the Lock would have negative effects on water quality and would negatively impact the viability of his business and his enjoyment of the waters surrounding Matlacha. Petitioner, Melanie Hoff, is a resident and property owner in St. James City. St. James City is located to the southwest of Cape Coral. Ms. Hoff’s property is located within five nautical miles of the Lock. Ms. Hoff engages in various water sports and fishes in the waters around her property. She moved to the area, in part, for the favorable water quality. She is concerned that removal of the Lock would negatively impact water quality and her ability to use and enjoy waters in the area. Petitioner, Robert S. Zarranz, is a resident and property owner in Cape Coral. Mr. Zarranz’s house in Cape Coral is waterfront. He is an avid fisherman and boater. He is concerned that removal of the Lock would negatively impact water quality, and that the quality of fishing in the area would decline as a result. Petitioner, Yolanda Olsen, is a resident and property owner in Cape Coral. Ms. Olsen’s house in Cape Coral is waterfront. She enjoys watersports and birdwatching in the areas around her property. She is concerned that removal of the Lock would negatively impact water quality, and that her ability to enjoy her property and the surrounding waters would suffer as a result. Petitioner, Jessica Blanks, is a resident and property owner in Cape Coral. Ms. Blanks’ house in Cape Coral is waterfront. She is concerned that removal of the Lock would negatively impact water quality, and that her ability to enjoy her property and the surrounding waters would suffer as a result. Petitioner, Joseph Michael Hannon, is a resident and property owner in Matlacha. Mr. Hannon is a member of the Association. He enjoys boating, fishing, and kayaking in the waters surrounding Matlacha. He is concerned that removal of the Lock would negatively impact water quality, and that his ability to enjoy his property and the surrounding waters would suffer as a result. Petitioner, Debra Hall, did not appear at the final hearing and no testimony was offered regarding her standing. The Project and Vicinity The Project site is 0.47 acres. At the Lock location, the South Spreader Waterway is 200 feet wide, and includes a 125-foot wide upland area secured by two seawalls, the 20-foot wide Lock, a 32-foot wide upland area secured by one seawall, and 23 feet of mangrove wetlands. The Lock is bordered to the north by property owned by Cape Harbour Marina, LLC, and bordered to the south by mangrove wetlands owned by the state of Florida. The 125-foot wide upland area and the 20-foot wide Lock form a barrier separating the South Spreader Waterway from the Caloosahatchee River. The preponderance of the competent substantial evidence established that the South Spreader Waterway behind the Lock is not tidally influenced, but would become tidally influenced upon removal of the Lock. Joint Exhibit 1 at p. 46. The City proposes to remove the Lock and one of the seawalls, reducing the 125-foot upland area to 20 feet. The proposed future condition of the area would include 125 feet of open canal directly connecting the South Spreader Waterway with the Caloosahatchee River. Joint Exhibit 1 at p. 47. The primary purpose of the Lock's removal is to alleviate safety concerns related to boater navigation. The Project's in-water construction includes demolition and removal of the existing Lock, removal of existing fill in the 125-foot upland area, removal of existing seawalls, and construction of replacement seawalls. The City would employ Best Management Practices (BMPs) throughout the course of the Project, including sediment and erosion controls such as turbidity barriers. The turbidity barriers would be made of a material in which manatees could not become entangled. All personnel involved with the Project would be instructed about the presence of manatees. Also, temporary signs concerning manatees would be posted prior to and during all in-water project activities. History of the South Spreader Waterway In the mid-1970's, the co-trustees of Gulf American Corporation, GAC Properties Credit, Inc., and GAC Properties, Inc., (collectively GAC) filed for after-the-fact permits from the Department's predecessor agency (DER), for the large dredge and fill work project that created the canal system in Cape Coral. In 1977, DER entered into CO 15 with GAC to create the North and South Spreader Waterways and retention control systems, including barriers. The Lock was one of the barriers created in response to CO 15. The Spreader Waterways were created to restore the natural hydrology of the area affected by GAC's unauthorized dredging and filling activity. The Spreader Waterways collected and retained surface runoff waters originating from the interior of Cape Coral's canal system. The South Spreader Waterway was not designed to meet water quality standards, but instead to collect surface runoff, then allow discharge of the excess waters collected over and through the mangrove wetlands located on the western and southern borders of the South Spreader Waterway. This fresh water flow was designed to mimic the historic sheet flow through the coastal fringe of mangroves and salt marshes of the Caloosahatchee River and Matlacha Pass estuaries. The fresh water slowly discharged over the coastal fringe until it finally mixed with the more saline waters of the estuaries. The estuarine environments located west and south of the Lock require certain levels of salinity to remain healthy ecosystems. Restoring and achieving certain salinity ranges was important to restoring and preserving the coastal fringe. In 1977 GAC finalized bankruptcy proceedings and executed CO 15. CO 15 required GAC to relinquish to the state of Florida the mangrove wetlands it owned on the western and southern borders of the South Spreader Waterway. This land grant was dedicated by a warranty deed executed in 1977 between GAC and the state of Florida. The Petitioners' expert, Kevin Erwin, worked as an environmental specialist for DER prior to and during the construction of the Spreader Waterways. Mr. Erwin was DER's main representative who worked with the GAC co-trustees to resolve the massive dredge and fill violation and design a system to restore the natural hydrology of the area. Mr. Erwin testified that the Lock was designed to assist in retention of fresh water in the South Spreader Waterway. The fresh water would be retained, slowed down, and allowed to slowly sheet flow over and through the coastal fringe. Mr. Erwin also testified that the South Spreader Waterway was not designed to allow direct tidal exchange with the Caloosahatchee River. In Mr. Erwin's opinion, the South Spreader Waterway appeared to be functioning today in the same manner as originally intended. Breaches and Exchange of Waters The Department's second amended notice of intent for the Project, stated that the Project was not expected to contribute to current water quality violations, because water in the South Spreader Waterway was already being exchanged with Matlacha Pass and the Caloosahatchee River through breaches and direct tidal flow. This second amended notice of intent removed all references to mitigation projects that would provide a net improvement in water quality as part of the regulatory basis for issuance of the permit. See Joint Exhibit 1 at pp. 326-333. The Department's witnesses testified that waters within the South Spreader Waterway currently mix with waters of the Caloosahatchee River when the Lock remains open during incoming and slack tides. A Department permit allowed the Lock to remain open during incoming and slack tides. Department witness, Megan Mills, the permitting program administrator, testified that she could not remember the exact date that permit was issued, but that it had been "a couple years." The location of breaches in the western and southern banks of the South Spreader Waterway was documented on another permit's drawings and pictures for a project titled "Cape Coral Spreader Waterway Restoration." See Cape Coral Ex. 9. Those documents located three breaches for repair and restoration identified as Breach 16A, Breach 16B, and Breach 20. The modeling reports and discussion that support the City's application showed these three breaches connect to Matlacha Pass Aquatic Preserve. Breach 20 was described as a connected tidal creek. Breach 16A and 16B were described as allowing water movement between Matlacha Pass and the South Spreader Waterway only when relatively high water elevations occurred in Matlacha Pass or in the South Spreader Waterway. The Department's water quality explanation of "mixing," was rather simplistic, and did not consider that the waterbody in which the Project would occur has three direct connections with an OFW that is a Class II waters designated for shellfish propagation or harvesting. Such a consideration would require the Department to determine whether to apply the OFW permitting standards, and the Class II waters permitting criteria in section 10.2.5 of the Environmental Resource Permit Applicant's Handbook, Volume I. See Fla. Admin Code R. 62-330.302(1)(a); 62-4.242(2); and 62-302.400(17)(b)36. The Caloosahatchee River, at its entrance to the South Spreader Waterway, is a Class III waters restricted for shellfish harvesting. The mouth of the Caloosahatchee River is San Carlos Bay, which is a Class II waters restricted for shellfish harvesting. There was no evidence that the Department's regulatory analysis considered that the waterbody in which the Project would occur directly connects to Class III waters that are restricted for shellfish harvesting, and is in close proximity to Class II waters that are restricted for shellfish harvesting. See Fla. Admin. Code R. 62-302.400(17)(b)36. and 62-330.302(1)(c).2/ Total Nitrogen The City's expert, Anthony Janicki, Ph.D., testified that nitrogen concentrations in the Caloosahatchee River were higher than in the South Spreader Waterway in the years 2017 and 2018. Thus, he opined that if the Lock is removed, water from the South Spreader Waterway would not negatively impact the Caloosahatchee River. However, the City's application was supported by an analysis, with more than a decade of monitoring data, which showed nitrogen concentration values were comparable inside the South Spreader Waterway and in the Caloosahatchee River. Dr. Janicki also used the Department's Hydrologic Simulation Program – FORTRAN (HSPF) watershed model to estimate the Total Nitrogen (TN) loading that would enter the Caloosahatchee River through the Chiquita Lock. Dr. Janicki estimated that TN loading to the Caloosahatchee River, after removal of the Chiquita Lock, would amount to 30,746 pounds per year. The Caloosahatchee River is listed as impaired for nutrients and has a TN Total Maximum Daily Load (TMDL) that was set by the Department in 2009. Dr. Janicki opined that removing the Lock would not result in adverse impacts to the surrounding environment. But the Petitioners obtained his concession that his opinion was dependent on the City's completion of additional water quality enhancement projects in the future as part of its obligations under the Caloosahatchee Estuary Basin Management Action Plan (BMAP) for achieving the TN TMDL. Dr. Janicki additionally testified that the potential TN loading to the Caloosahatchee River did not anticipate an actual impact to the River's water quality because the TN loads from the South Spreader Waterway were already factored into the 2009 TMDL. He essentially testified that the Lock's removal was anticipated and was factored into the model when the TMDL was established in 2009. Thus, the Petitioners proved by a preponderance of the competent and substantial evidence that the Department and the City were not aligned regarding how the City's application would provide reasonable assurances of meeting applicable water quality standards. The Petitioners proved by a preponderance of the competent and substantial evidence that the City relied on future projects to provide reasonable assurance that the removal of the Lock would not cause or contribute to violations of water quality standards in the Caloosahatchee River and the Matlacha Pass Aquatic Preserve. The Petitioners proved by a preponderance of the competent and substantial evidence that the Department relied on a simplistic exchange of waters to determine that removal of the Lock would not cause or contribute to violations of water quality standards in the Caloosahatchee River and the Matlacha Pass Aquatic Preserve. Water Quantity and Salinity The engineering report that supports the City's application stated that when the Lock is removed, the South Spreader Waterway behind the Lock will become tidally influenced. With the Lock removed, the volume of daily water fluxes for the South Spreader Waterway would increase from zero cubic meters per day to 63,645 cubic meters per day. At the location of Breach 20, with the Lock removed, the volume of daily water fluxes would drastically decrease from 49,644 cubic meters per day to eight cubic meters per day. Dr. Janicki testified that Breach 20 was connected to a remnant tidal creek that meanders and eventually empties into an embayment. The evidence demonstrated that the embayment is Punta Blanca Bay, which is part of the Matlacha Pass Aquatic Preserve. Dr. Janicki opined that Breach 20 was an area of erosion risk and sediment transport into downstream mangroves that would be significantly reduced by removing the Lock. He explained that the reductions in flow would result in reductions in velocities through Breach 20 and in the South Spreader Waterway itself. Mr. Erwin testified that Breach 20 was not a "breach."3/ He described it as the location of a perpendicular intersection of the South Spreader Waterway with a small tidal creek, which connected to a tidal pond further back in the mangroves. Mr. Erwin testified that an "engineered sandbag concrete structure" was built at the shallow opening to limit the amount of flow into and out of this tidal creek system. But it was also designed to make sure that the tidal creek system "continued to get some amount of water." As found above, Lock removal would drastically reduce the volume of daily water fluxes into and out of Breach 20's tidal creek system. Mr. Erwin also testified that any issues with velocities or erosion would be exemplified by bed lowering, siltation, and stressed mangroves. He persuasively testified, however, that there was no such evidence of erosion and there were "a lot of real healthy mangroves." Mr. Erwin opined that removal of the Lock would cause the South Spreader Waterway to go from a closed, mostly fresh water system, to a tidal saline system. He described the current salinity level in the South Spreader Waterway to be low enough to support low salinity vegetation and not high enough to support marine organisms like barnacles and oysters. The City's application actually supports this opinion. Using the Environmental Fluid Dynamics Code (EFDC) model developed by Dr. Janicki for this Lock removal project, comparisons were made describing the salinity distribution within the South Spreader Waterway. The model was run with and without the Lock, for both a wet and dry year. Dr. Janicki testified, and the model showed, that removal of the Lock would result in increased salinity above the Lock and decreased salinity downstream of the Lock. However, he generally opined that the distribution of salinities was well within the normal ranges seen in this area. The City's application also concluded that the resultant salinities did not fall outside the preferred salinity ranges for seagrasses, oysters, and a wide variety of fish taxa. However, Dr. Janicki did not address specific changes in vegetation and encroachment of marine organisms that would occur with the increase in salinity within the South Spreader Waterway. Secondary Impacts to the Mangrove Wetlands Mr. Erwin testified that the mangroves located on the western and southern borders of the South Spreader Waterway are currently in very good health. He additionally testified that loss of the current fresh water hydraulic head and an increase in salinity within the South Spreader Waterway would negatively impact the health of the mangrove wetlands. In addition, the City's application stated that removing the Lock would result in a drop in the water level of one to one and a half feet within the South Spreader Waterway. Mr. Erwin credibly and persuasively testified that a drop in water level of only a few inches would have negative effects on the health of mangroves, and that a drop of a foot could result in substantial mangrove die-off. Mr. Erwin testified that the mangrove wetlands adjacent to the South Spreader Waterway consist of a variety of plants and algae in addition to mangroves. He described the wetlands as a mangrove community made up of different types of mangroves, and epiphytic vegetation such as marine algae. This mangrove community provides habitat for a "wide range of invertebrates." He further testified that these plants and algae uptake and transform the nutrients that flow over and through the mangrove wetlands before they reach the receiving waters. Thus, the mangrove wetlands on the western and southern borders of the South Spreader Waterway serve to filter nutrients out of the water discharged from the Waterway before it reaches Matlacha Pass and the Caloosahatchee River. Mr. Erwin's credible and persuasive testimony was contrary to the City's contention that Lock removal would not result in adverse impacts to the mangrove wetlands adjacent to the South Spreader Waterway. The City and the Department failed to provide reasonable assurances that removing the Lock would not have adverse secondary impacts to the health of the mangrove wetlands community adjacent to the South Spreader Waterway. Impacts to Fish and Wildlife, Including Endangered and Threatened Species The Florida Fish and Wildlife Conservation Commission (FWC) reviewed the City's application and determined that if BMPs for in-water work were employed during construction, no significant adverse impacts on fish and wildlife were expected. For example, temporary signs concerning manatees would be posted prior to and during all in-water project activities, and all personnel would be instructed about the presence of manatees. The FWC determination only addressed direct impacts during in-water construction work. The City's application contained supporting material that identified the major change resulting from removal of the Lock that may influence fish and wildlife in the vicinity of the Project, was the opportunity for movement to or from the South Spreader Waterway canal system. Threatened and endangered species of concern in the area included the Florida manatee and the smalltooth sawfish. The City's application stated that literature review showed the smalltooth sawfish and the Florida manatee utilized non-main-stem habitats, such as sea-wall lined canals, off the Caloosahatchee River. The City cited studies from 2011 and 2013, which showed that non-main-stem habitats were important thermal refuges during the winter, and part of the overall nursery area for smalltooth sawfish. The City concluded that removal of the Lock "would not be adverse, and would instead result in increased areas of useable habitat by the species." However, the Petitioner's expert witness, John Cassani, who is the Calusa Waterkeeper, testified that there is a smalltooth sawfish exclusion zone downstream of the Lock. He testified that the exclusion zone is a pupping area for smalltooth sawfish, and that rapid salinity fluctuations could negatively impact their habitat. The City also concluded that any impacts to the Florida manatee would not be adverse, "and would instead result in increased areas of useable habitat by the species, as well as a reduction in risk of entrapment or crushing in a canal lock system." At the same time, the City acknowledged that "watercraft collision is a primary anthropogenic threat to manatees." The City's literature review included a regional assessment by FWC's Fish and Wildlife Research Institute (FWRI) from 2006. Overall, the FWRI report concluded that the mouth of the Caloosahatchee River, at San Carlos Bay, was a "hot spot" for boat traffic coinciding with the shift and dispersal of manatees from winter refugia. The result was a "high risk of manatee- motorboat collisions." In addition, testimony adduced at the hearing from an 18-year employee of Cape Harbour Marina, Mr. Frank Muto, was that Lock removal would result in novice boaters increasing their speed, ignoring the no-wake and slow-speed zones, and presenting "a bigger hazard than the [L]ock ever has." Boater Navigation Concerns Oliver Clarke was the City’s principal engineer during the application process, and signed the application as the City's authorized agent. Mr. Clarke testified that he has witnessed boater congestion at the Lock. He also testified that lack of boating experience and weather concerns can exacerbate the boater congestion issues at the Lock. Petitioners presented the testimony of Mr. Frank Muto, the general manager of Cape Harbour Marina. Mr. Muto has been at the Cape Harbour Marina for 18 years. The marina has 78 docks on three finger piers along with transient spots. The marina is not currently subject to tidal flows and its water depth is between six and a half and seven and a half feet. He testified that they currently have at least 28 boats that maintain a draft of between four and a half and six feet of water. If the water depth got below four feet, those customers would not want to remain at the marina. Mr. Muto further testified that the Lock was in place when the marina was built, and the marina and docks were designed for an area with no tidal flow. Mr. Muto also testified that he has witnessed several boating safety incidents in and around the Lock. He testified that he would attribute almost all of those incidents to novice boaters who lack knowledge of proper boating operations and locking procedures. Mr. Muto additionally testified that there is law enforcement presence at the Lock twenty-four hours a day, including FWC marine patrol and the City's marine patrol.
Conclusions For Petitioners: J. Michael Hannon, Qualified Representative 2721 Clyde Street Matlacha, Florida 33993 John S. Turner, Esquire Peterson Law Group Post Office Box 670 Fort Myers, Florida 33902 For Respondent City of Cape Coral: Craig D. Varn, Esquire Amy Wells Brennan, Esquire Manson Bolves Donaldson Varn, P.A. 106 East College Avenue, Suite 820 Tallahassee, Florida 32301 Steven D. Griffin City of Cape Coral Assistant City Attorney Post Office Box 150027 Cape Coral, Florida 33915-0027 For Respondent Department of Environmental Protection: Kirk Sanders White, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-3000
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that: The Department of Environmental Protection enter a final order denying Individual Environmental Resource Permit Number 244816-005 to the City of Cape Coral for removal of the Chiquita Boat Lock. The final order deny Petitioners' request for an award of attorney's fees and costs. DONE AND ENTERED this 12th day of December, 2019, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of December, 2019.
The Issue The issues in this case are whether International Paper Company (IP) is entitled to National Pollutant Discharge Elimination System (NPDES) Permit No. FL0002526 issued by Department of Environmental Protection (Department) and whether the Department should approve Consent Order No. 08-0358, for the operation of IP’s paper mill in Cantonment, Escambia County, Florida.
Findings Of Fact The Department is the state agency authorized under Chapter 403, Florida Statutes (2008), to regulate discharges of industrial wastewater to waters of the state. Under a delegation from the United States Environmental Protection Agency, the Department administers the NPDES permitting program in Florida. IP owns and operates the integrated bleached kraft paper mill in Cantonment. FOPB is a non-profit Alabama corporation established in 1988 whose members are interested in protecting the water quality and natural resources of Perdido Bay. FOPB has approximately 450 members. About 90 percent of the members own property adjacent to Perdido Bay. James Lane is the president of FOPB. Jacqueline Lane and James Lane live on property adjacent to Perdido Bay. The mill's wastewater effluent is discharged into Elevenmile Creek, which is a tributary of Perdido Bay. Perdido Bay is approximately 28 square miles in area. U.S. Highway 90 crosses the Bay, going east and west, and forms the boundary between what is often referred to as the "Upper Bay" and "Lower Bay." The Bay is relatively shallow, especially in the Upper Bay, ranging in depth between five and ten feet. At the north end of Perdido Bay is a large tract of land owned by IP, known as the Rainwater Tract. The northern part of the tract is primarily fresh water wetlands. The southern part is a tidally-affected marsh. The natural features and hydrology of the fresh water wetlands have been substantially altered by agriculture, silviculture, clearing, ditching, and draining. Tee Lake and Wicker Lake are small lakes (approximately 50 acres in total surface area) within the tidal marsh of the Rainwater Tract. Depending on the tides, the lakes can be as shallow as one foot, or several feet deep. A channel through the marsh allows boaters to gain access to the lakes from Perdido Bay. Florida Pulp and Paper Company first began operating the Cantonment paper mill in 1941. St. Regis Paper Company acquired the mill in 1946. In 1984, Champion International Corporation (Champion) acquired the mill. Champion changed the product mix in 1986 from unbleached packaging paper to bleached products such as printing and writing grades of paper. The mill is integrated, meaning that it brings in logs and wood chips, makes pulp, and produces paper. The wood is chemically treated in cookers called digesters to separate the cellulose from the lignin in the wood because only the cellulose is used to make paper. Then the "brown stock" from the digesters goes through the oxygen delignification process, is mixed with water, and is pumped to paper machines that make the paper products. In 1989, the Department and Champion signed a Consent Order to address water quality violations in Elevenmile Creek. Pursuant to the Consent Order, Champion commissioned a comprehensive study of the Perdido Bay system that was undertaken by a team of scientists led by Dr. Robert Livingston, an aquatic ecologist and professor at Florida State University. The initial three-year study by Dr. Livingston's team of scientists was followed by a series of related scientific studies (“the Livingston studies"). Champion was granted variances from the water quality standards in Elevenmile Creek for iron, specific conductance, zinc, biological integrity, un-ionized ammonia, and dissolved oxygen (DO). In 2001, IP and Champion merged and Champion’s industrial wastewater permit and related authorizations were transferred to IP. In 2002, IP submitted a permit application to upgrade its wastewater treatment plant (WWTP) and relocate its discharge. The WWTP upgrades consist of converting to a modified activated sludge treatment process, increasing aeration, constructing storm surge ponds, and adding a process for pH adjustment. The new WWTP would have an average daily effluent discharge of 23.8 million gallons per day (mgd). IP proposes to convey the treated effluent by pipeline 10.7 miles to the Rainwater Tract, where the effluent would be distributed over the wetlands as it flows to lower Elevenmile Creek and upper Perdido Bay. IP's primary objective in upgrading the WWTP was to reduce the nitrogen and phosphorus in the mill's effluent discharge. The upgrades are designed to reduce un-ionized ammonia, total soluble nitrogen, and phosphorus. They are also expected to achieve a reduction of biological oxygen demand (BOD) and TSS. IP plans to obtain up to 5 mgd of treated municipal wastewater from a new treatment facility planned by the Emerald Coast Utility Authority (ECUA), which would be used in the paper production process and would reduce the need for groundwater withdrawals by IP for this purpose. The treated wastewater would enter the WWTP, along with other process wastewater and become part of the effluent conveyed through the pipeline to the wetland tract. The effluent limits required by the proposed permit include technology-based effluent limits (TBELs) that apply to the entire pulp and paper industry. TBELs are predominantly production-based, limiting the amount of pollutants that may be discharged for each ton of product that is produced. The proposed permit also imposes water quality-based effluent limits (WQBELs) that are specific to the Cantonment mill and the waters affected by its effluent discharge. The WQBELs for the mill are necessary for certain constituents of the mill's effluent because the TBELs, alone, would not be sufficient to prevent water quality criteria in the receiving waters from being violated. The Livingston studies represent perhaps the most complete scientific evaluation ever made of a coastal ecosystem. Dr. Livingston developed an extensive biological and chemical history of Perdido Bay and then evaluated the nutrient loadings from Elevenmile Creek over a 12-year period to correlate mill loadings with the biological health of the Bay. The Livingston studies confirmed that when nutrient loadings from the mill were high, they caused toxic algae blooms and reduced biological productivity in Perdido Bay. Some of the adverse effects attributable to the mill effluent were most acute in the area of the Bay near the Lanes' home on the northeastern shore of the Bay because the flow from the Perdido River tends to push the flow from Elevenmile Creek toward the northeastern shore. Because Dr. Livingston determined that the nutrient loadings from the mill that occurred in 1988 and 1989 did not adversely impact the food web of Perdido Bay, he recommended effluent limits for ammonia nitrogen, orthophosphate, and total phosphorous that were correlated with mill loadings of these nutrients in those years. The Department used Dr. Livingston’s data, and did its own analyses, to establish WQBELs for orthophosphate for drought conditions and for nitrate-nitrite. WQBELs were ultimately developed for total ammonia, orthophosphate, nitrate-nitrite, total phosphorus, BOD, color, and soluble inorganic nitrogen. The WQBELs in the proposed permit were developed to assure compliance with water quality standards under conditions of pollutant loadings at the daily limit (based on a monthly average) during low flow in the receiving waters. Petitioners did not dispute that the proposed WWTP is capable of achieving the TBELs and WQBELs. Their main complaint is that the WQBELs are not adequate to protect the receiving waters. A wetland pilot project was constructed in 1990 at the Cantonment mill into which effluent from the mill has been discharged. The flora and fauna of the pilot wetland project have been monitored to evaluate how they are affected by IP’s effluent. An effluent distribution system is proposed for the wetland tract to spread the effluent out over the full width of the wetlands. This would be accomplished by a system of berms running perpendicular to the flow of water through the wetlands, and gates and other structures in and along the berms to gather and redistribute the flow as it moves in a southerly direction toward Perdido Bay. The design incorporates four existing tram roads that were constructed on the wetland tract to serve the past and present silvicultural activities there. The tram roads, with modifications, would serve as the berms in the wetland distribution system. As the effluent is discharged from the pipeline, it would be re-aerated and distributed across Berm 1 through a series of adjustable, gated openings. Mixing with naturally occurring waters, the effluent would move by gravity to the next lower berm. The water will re-collect behind each of the vegetated berms and be distributed again through each berm. The distance between the berms varies from a quarter to a half mile. Approximately 70 percent of the effluent discharged into the wetland would flow a distance of approximately 2.3 miles to Perdido Bay. The remaining 30 percent of the effluent would flow a somewhat shorter distance to lower Elevenmile Creek. A computer simulation performed by Dr. Wade Nutter indicated that the effluent would move through the wetland tract at a velocity of approximately a quarter-of-a-foot per second and the depth of flow across the wetland tract will be 0.6 inches. It would take four or five days for the effluent to reach lower Elevenmile Creek and Perdido Bay. As the treated effluent flows through the wetland tract, there will be some removal of nutrients by plants and soil. Nitrogen and phosphorous are expected to be reduced approximately ten percent. BOD in the effluent is expected to be reduced approximately 90 percent. Construction activities associated with the effluent pipeline, berm, and control structures in the wetland tract, as originally proposed, were permitted by the Department through issuance of a Wetland Resource Permit to IP. The United States Army Corps of Engineers has also permitted this work. Petitioners did not challenge those permits. A wetland monitoring program is required by the proposed permit. The stated purpose of the monitoring program is to assure that there are no significant adverse impacts to the wetland tract, including Tee and Wicker Lakes. After the discharge to the wetland tract commences, the proposed permit requires IP to submit wetland monitoring reports annually to the Department. A monitoring program was also developed by Dr. Livingston and other IP consultants to monitor the impacts of the proposed discharge on Elevenmile Creek and Perdido Bay. It was made a part of the proposed permit. The proposed Consent Order establishes a schedule for the construction activities associated with the proposed WWTP upgrades and the effluent pipeline and for incremental relocation of the mill's discharge from Elevenmile Creek to the wetland tract. IP is given two years to complete construction activities and begin operation of the new facilities. At the end of the construction phase, least 25 percent of the effluent is to be diverted to the wetland tract. The volume of effluent diverted to the wetlands is to be increased another 25 percent every three months thereafter. Three years after issuance of the permit, 100 percent of the effluent would be discharged into the wetland tract and there would no longer be a discharge into Elevenmile Creek. The proposed Consent Order establishes interim effluent limits that would apply immediately upon the effective date of the Consent Order and continue during the two-year construction phase when the mill would continue to discharge into Elevenmile Creek. Other interim effluent limits would apply during the 12- month period following construction when the upgraded WWTP would be operating and the effluent would be incrementally diverted from Elevenmile Creek to the wetland tract. A third set of interim effluent limits would apply when 100 percent of the effluent is discharged into the wetland tract. IP is required by the Consent Order to submit quarterly reports of its progress toward compliance with the required corrective actions and deadlines. Project Changes After the issuance of the Final Order in 05-1609, IP modified its manufacturing process to eliminate the production of white paper. IP now produces brown paper for packaging material and “fluff” pulp used in such products as filters and diapers. IP’s new manufacturing processes uses substantially smaller amounts of bleach and other chemicals that must be treated and discharged. IP reduced its discharge of BOD components, salts that increase the specific conductance of the effluent, adsorbable organic halides, and ammonia. IP also reduced the odor associated with its discharge. In the findings that follow, the portion of the Rainwater Tract into which IP proposes to discharge and distribute its effluent will be referred to as the “effluent distribution system,” which is the term used by Dr. Nutter in his 2008 “White Paper” (IP Exhibit 23). The effluent distribution system includes the berms and other water control structures as well as all of the natural areas over which IP’s effluent will flow to Perdido Bay. Most of the existing ditches, sloughs, and depressions in the effluent distribution system are ephemeral, holding water only after heavy rainfall or during the wet season. Even the more frequently wetted features, other than Tee and Wicker Lakes, intermittently dry out. There is currently little connectivity among the small water bodies that would allow fish and other organisms to move across the site. Fish and other organisms within these water bodies are exposed to wide fluctuations in specific conductivity, pH, and DO. When the water bodies dry out, the minnows and other small fish die. New populations of fish enter these water bodies from Elevenmile Creek during high water conditions, or on the feet of water birds. IP's consultants conducted an extensive investigation and evaluation of animal and plant communities in the Rainwater Tract in coordination with scientists from the Department and the Florida Fish and Wildlife Conservation Commission. Among the habitats that were identified and mapped were some wet prairies, which are designated “S-2," or imperiled, in the Florida Natural Area Inventory. In these wet prairies are rare and endangered pitcher plants. IP modified the design of the proposed effluent distribution system to shorten the upper berms and remove 72.3 acres of S-2 habitat. The total area of the system was reduced from 1,484 acres to 1,381 acres. The proposed land management activities within the effluent distribution system are intended to achieve restoration of historic ecosystems, including the establishment and maintenance of tree species appropriate to the various water depths in the system, and the removal of exotic and invasive plant species. A functional assessment of the existing and projected habitats in the effluent distribution system was performed. The Department concluded that IP’s project would result in a six percent increase in overall wetland functional value within the system. That estimate accounts for the loss of some S-2 habitat, but does not include the benefits associated with IP’s conservation of S-2 habitat and other land forms outside of the effluent distribution system. IP proposes to place in protected conservation status 147 acres of wet prairie, 115 acres of seepage slope, and 72 acres of sand hill lands outside the effluent distribution system. The total area outside of the wetland distribution system that the Consent Order requires IP to perpetually protect and manage as conservation area is 1,188 acres. The Consent Order was modified to incorporate many of the wetland monitoring provisions that had previously been a part of the former experimental use of wetlands authorization. IP proposes to achieve compliance with all proposed water quality standards and permit limits by the end of the schedule established in the Consent Order, including the water quality standards for specific conductance, pH, turbidity, and DO, which IP had previously sought exceptions for pursuant to Florida Administrative Code Rule 62-660.300(1). Limitation of Factual Issues As explained in the Conclusions of Law, the doctrine of collateral estoppel bars the parties in these consolidated cases from re-litigating factual issues that were previously litigated by them in DOAH Case No. 05-1609. The Department’s Final Order of August 8, 2007, determined that IP had provided reasonable assurance that the NPDES permit, Consent Order, exception for the experimental use of wetlands, and variance were in compliance with all applicable statutes and rules, except for the following area: the evidence presented by IP was insufficient to demonstrate that IP’s wastewater effluent would not cause significant adverse impact to the biological community of the wetland tract, including Tee and Wicker Lakes. Following a number of motions and extensive argument on the subject of what factual issues raised by Petitioners are proper for litigation in this new proceeding, an Order was issued on June 2, 2009, that limited the case to two general factual issues: Whether the revised Consent Order and proposed permit are valid with respect to the effects of the proposed discharge on the wetland system, including Tee and Wicker Lakes, and with respect to any modifications to the effluent distribution and treatment functions of the wetland system following the Final Order issued in DOAH Case No. 05- 1609; and Whether the December 2007 report of the Livingston team demonstrates that the WQBELS are inadequate to prevent water quality violations in Perdido Bay. Petitioners’ Disputes Petitioners’ proposed recommended orders include arguments that are barred by collateral estoppel. For example, Jacqueline Lane restates her opinions about physical and chemical processes that would occur if IP’s effluent is discharged into the wetlands, despite the fact that some of these opinions were rejected in DOAH Case No. 05-1609. Dr. Lane believes that IP’s effluent would cause adverse impacts from high water temperatures resulting from color in IP’s effluent. There is already color in the waters of the effluent distribution system under background conditions. The increased amount of shading from the trees that IP is planting in the effluent distribution system would tend to lower water temperatures. Peak summer water temperatures would probably be lowered by the effluent. Petitioners evidence was insufficient to show that the organisms that comprise the biological community of the effluent distribution system cannot tolerate the expected range of temperatures. Dr. Lane also contends that the BOD in IP's effluent would deplete DO in the wetlands and Tee and Wicker Lakes. Her contention, however, is not based on new data about the effluent or changes in the design of the effluent distribution system. There is a natural, wide fluctuation in DO in the wetlands of the effluent distribution system because DO is affected by numerous factors, including temperature, salinity, atmospheric pressure, turbulence, and surface water aeration. There are seasonal changes in DO levels, with higher levels in colder temperatures. There is also a daily cycle of DO, with higher levels occurring during the day and lower levels at night. It is typical for DO levels in wetlands to fall below the Class III water quality standard for DO, which is five milligrams per liter (mg/l). An anaerobic zone in the water column is beneficial for wetland functions. DO levels in the water bodies of the effluent distribution system currently range from a high of 11 to 12 mg/l to a low approaching zero. The principal factor that determines DO concentrations within a wetland is sediment oxygen demand (SOD). SOD refers to the depletion of oxygen from biological responses (respiration) as well as oxidation-reduction reactions within the sediment. The naturally occurring BOD in a wetland is large because of the amount of organic material. The BOD associated with IP’s effluent would be a tiny fraction of the naturally occurring BOD in the effluent distribution system and would be masked by the effect of the SOD. It was estimated that the BOD associated with IP's effluent would represent only about .00000000001 percent of the background BOD, and would have an immeasurable effect. Dr. Pruitt’s testimony about oxygen dynamics in a wetland showed that IP’s effluent should not cause a measurable decrease in DO levels within the effluent distribution system, including Tee and Wicker Lakes. FOPB and James Lane assert that only 200 acres of the effluent distribution system would be inundated by IP’s effluent, so that the alleged assimilation or buffering of the chemical constituents of the effluent would not occur. That assertion misconstrues the record evidence. About 200 acres of the effluent distribution system would be permanently inundated behind the four berms. However, IP proposes to use the entire 1,381-acre system for effluent distribution. The modifications to the berms and the 72-acre reduction in the size of the effluent distribution system would not have a material effect on the assimilative capacity of system. The residence time and travel time of the effluent in the system, for example, would not be materially affected. Variability in topography within the effluent distribution system and in rainfall would affect water depths in the system. The variability in topography, including the creation of some deeper pools, would contribute to plant and animal diversity and overall biological productivity within the system. The pH of the effluent is not expected to change the pH in the effluent distribution system because of natural buffering in the soils. The specific conductance (saltiness) of IP’s effluent is not high enough to adversely affect the biological community in the fresh water wetlands of the effluent distribution system. IP is already close to maintaining compliance with the water quality standard for specific conductance and would be in full compliance by the end of the compliance schedule established in the proposed Consent Order. After the 2007 conversion to brown paper manufacturing, IP’s effluent has shown no toxicity. The effluent has passed the chronic toxicity test, which analyzes the potential for toxicity from the whole effluent, including any toxicity arising from additive or synergistic effects, on sensitive test organisms. Dr. Lane points out that the limits for BOD and TSS in the proposed NPDES permit exceed the limits established by Department rule for discharges of municipal wastewater into wetlands. However, paper mill BOD is more recalcitrant in the environment than municipal wastewater BOD and less “bio- available” in the processes that can lower DO. In addition, the regulatory limits for municipal wastewater are technology-based, representing “secondary treatment.” The secondary treatment technology is not applicable to IP’s wastewater. Sampling in the pilot wetland at the paper mill revealed a diversity of macroinvertebrates, including predator species, and other aquatic organisms. Macroinvertebrates are a good measure of the health of a water body because of their fundamental role in the food web and because they are generally sensitive to pollutants. Petitioners contend that the pilot wetland at the paper mill is not a good model for the effect of the IP’s effluent in the wetland distribution system, primarily because of the small amount of effluent that has been applied to the pilot wetland. Although the utility of the pilot wetland data is diminished in this respect, it is not eliminated. The health of the biological community in the pilot wetland contributes to IP’s demonstration of reasonable assurance that the biological community in the effluent distribution system would not be adversely affected. The effluent would not have a significant effect on the salinity of Tee and Wicker Lakes. Under current conditions, the lakes have a salinity of less than one part per thousand 25 percent of the time, less than 10 parts per thousand 53 percent of the time, and greater than 10 parts per thousand 22 percent of the time. In comparison, marine waters have a salinity of 2.7 parts per thousand. IP’s effluent would not affect the lower end of the salinity range for Tee and Wicker Lakes, and would cause only a minor decrease in the higher range. That minor decrease should not adversely affect the biota in Tee and Wicker Lakes or interfere with their nursery functions. The proposed hydrologic loading rate of the effluent amounts to an average of six-tenths of an inch over the area of effluent distribution system. The addition of IP’s effluent to the wetlands of the effluent distribution system and the creation of permanent pools would allow for permanent fish populations and would increase the opportunity for fish and other organisms to move across the effluent distribution system. Biological diversity and productivity is likely to be increased in the effluent distribution system. By improving fish habitat, the site would attract wading birds and other predatory birds. Although the site would not be open to public use (with the exception of Tee and Wicker Lakes), recreational opportunities could be provided by special permission for guided tours, educational programs, and university research. Even if public access were confined to Tee and Wicker Lakes, that would not be a reduction in public use as compared to the existing situation. IP’s discharge, including its discharges subject to the interim limits established in the Consent Order, would not interfere with the designated uses of the Class III receiving waters, which are the propagation and maintenance of a healthy, well-balanced population of fish and wildlife. The wetlands of the effluent distribution system are the “receiving waters” for IP’s discharge. The proposed project would not be unreasonably destructive to the receiving waters, which would involve a substantial alteration in community structure and function, including the loss of sensitive taxa and their replacement with pollution-tolerant taxa. The proposed WQBELs would maintain the productivity in Tee and Wicker Lakes. There would be no loss of the habitat values or nursery functions of the lakes which are important to recreational and commercial fish species. IP has no reasonable, alternative means of disposing of its wastewater other than by discharging it into waters of the state. IP has demonstrated a need to meet interim limits for a period of time necessary to complete the construction of its alternative waste disposal system. The interim limits and schedule for coming into full compliance with all water quality standards, established in the proposed Consent Order, are reasonable. The proposed project is important and beneficial to the public health, safety, and welfare because (1) economic benefits would accrue to the local and regional economy from the operation of IP’s paper mill, (2) Elevenmile Creek would be set on a course of recovery, (3) the wetlands of the effluent distribution system would become a site of greater biological diversity and productivity, (4) the environmental health of Perdido Bay would be improved, (5) the Department’s decades-long enforcement action against IP would be concluded, (6) substantial areas of important habitat would be set aside for permanent protection, and (7) the effluent distribution system would yield important information on a multitude of scientific topics that were debated by these parties. The proposed project would not adversely affect the conservation of fish or wildlife or their habitats. The proposed project would not adversely affect fishing or water-based recreational values or marine productivity in the vicinity of the proposed discharge. There is no Surface Water Improvement and Management Plan applicable to IP’s proposed discharge. The preponderance of the record evidence establishes reasonable assurance that IP’s proposed project would comply with all applicable laws and that the Consent Order establishes reasonable terms and conditions to resolve the Department’s enforcement action against IP for past violations.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is: RECOMMENDED that the Department enter a final order granting NPDES Permit No. FL0002526 and approving Consent Order No. 08-0358. DONE AND ENTERED this 27th day of January, 2010, in Tallahassee, Leon County, Florida. BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of January, 2010.
The Issue The issue to be determined in this case is whether Florida Power & Light Company (“FPL”), is entitled to a water use permit issued by the South Florida Water Management District (“District”) to withdraw water for use at FPL’s Turkey Point Power Plant in Miami-Dade County.
Findings Of Fact The Parties Tropical Audubon is a Florida not-for-profit corporation incorporated more than one year prior to the date FPL filed its permit application. Tropical Audubon was formed for the purpose of protecting the environment, fish and wildlife resources, and air and water quality. Its mission is to “conserve and restore South Florida’s ecosystems, focusing on birds, other wildlife and their habitats for the benefit of humanity and the earth’s biological diversity.” Tropical Audubon has approximately 465 members. More than 25 reside in Miami-Dade County. A substantial number of Tropical Audubon’s members use the area near Turkey Point for recreational activities, including wildlife observation. The District is a multi-purpose water management district with powers and duties set forth in chapter 373, Florida Statutes, and Florida Administrative Code Chapters 40E and 62- 40.410, including powers and duties related to the regulation of consumptive uses of water. Its principal office is located at 3301 Gun Club Road, West Palm Beach, Florida. FPL is a regulated public utility which provides electric service to its customers in 35 Florida counties. FPL owns and operates the Turkey Point Power Plant, an electric power generating facility located in unincorporated southeastern Miami- Dade County and within the boundaries of the District. Background FPL’s Turkey Point property is located 25 miles south of Miami and is situated on the coastline adjacent to Biscayne Bay. The property covers about 9,400 acres. The Turkey Point Power Plant consists of five electric generating units. Units 1 and 2 are gas and oil-fired boilers. Unit 2 has been decommissioned. Units 3 and 4 are nuclear units. Unit 5 is a combined cycle gas turbine unit. Construction of Units 1, 2, 3, and 4, as well as the Turkey Point Cooling Canal System (“CCS”), predated the enactment of the PPSA. However, Units 3 and 4 were certified under the PPSA in 2008 when they were uprated to increase their steam- electric generating capacity. Unit 5 was certified under the PPSA in 2005. Units 1 and 2 originally used once-through cooling, which involved taking water from Biscayne Bay and discharging it back into the Bay. In 1971, following a lawsuit brought by the U.S. Department of Justice, FPL signed a Consent Decree that required FPL to construct the CCS, a closed-loop cooling canal system, to eliminate heated, surface water discharges to Biscayne Bay and Card Sound. The CCS is a 5,900-acre network of canals which dissipate heat from the water used in the operation of Units 3 and 4, as well as Unit 1 when in operation. The CCS functions like a large radiator, which uses evaporation, convective heat transfer, and radiated heat loss to lower the water temperature. Circulating water pumps provide for counter-clockwise flow of water from the discharge canal, down through the western side of the CCS, and then back up the eastern side of the CCS to the power plant. The full circuit from discharge to intake takes about 48 hours. The CCS does not directly discharge to surface water, but water can enter or leave the CCS by groundwater seepage because the canals are not lined. Additions of water into the CCS include plant process water, rainfall, stormwater runoff, and groundwater seepage. In addition to the Consent Decree, FPL entered into an agreement with the District’s predecessor agency in 1972 to address the operation of the CCS. The agreement has been updated, with the most recent version being the Fifth Supplemental Agreement, executed in 2009. Pursuant to the Fifth Supplemental Agreement, FPL implemented an extensive surface water and groundwater monitoring program in and around the CCS. Since 2010, FPL has collected monitoring data for water levels, fluid density, salt concentrations, and conductivity from 42 groundwater monitoring wells. FPL also collects water level data at seven locations within the CCS on an hourly basis. In 2013 and 2014, monitoring data showed water quality decreased in the CCS, with increased salinity, algae blooms, and suspended solids in the water. Decreased water quality reduced heat dissipation, so water temperatures increased. FPL was authorized by the Nuclear Regulatory Commission (NRC) to operate the CCS with water temperatures as high as 100 degrees Fahrenheit (F). In 2014, water temperatures exceeding 100 degrees caused plant shutdowns. As a result, FPL requested and the NRC allowed the maximum operating temperature of CCS water to be raised to 104 degrees. Higher water temperatures cause more evaporation and because the evaporation of water leaves its salt content behind, the salinity of the water in the CCS increased. Water in the CCS became “hypersaline,” having chloride concentrations greater than 35 Practical Salinity Units (PSU), which is the average salinity of seawater. Because hypersaline water is denser and heavier than the naturally occurring groundwater, it sinks down through the CCS canals into the Biscayne Aquifer and down through the aquifer to a confining layer that separates the Biscayne Aquifer from the Floridan Aquifer, about 80 feet below the CCS. When the hypersaline water reaches the bottom of the Biscayne Aquifer, it moves laterally in all directions. However, the primary focus of the District and the DEP has been on the western movement of the hypersaline water because of the potential harm to existing legal uses of water and offsite land uses to the west. The hypersaline “plume” has migrated two to three miles west of the CCS. In August 2014, FPL requested and the District issued an emergency order to withdraw water from the L-31E Canal and discharge it to the CCS to reduce salinity and temperature. FPL withdrew water over a 21-day period in September and October, an average of 43 mgd, and observed reductions in salinity, algae blooms, and temperatures within the CCS. With the combination of rainfall and water from the L-31E Canal, CCS salinity levels were reduced by about 20 practical salinity units (PSU). When the proposed permit that is the subject of this case was challenged, FPL sought and obtained another emergency order to use water from the L-31E Canal during the 2015 rainy season (June 1 to November 30). Use of water from the L-31E Canal in 2015 reduced temperature and salinity levels in the CCS. Salinity declined from 95 PSU to 60 PSU. On December 23, 2014, the DEP issued an Administrative Order (“AO”) which, among other things, directs FPL to submit a Salinity Management Plan with the primary goal of “reduc[ing] the hypersalinity of the CCS to abate westward movement of CCS groundwater into class G-II groundwaters of the State.” The Proposed Permit FPL applied for the water use permit at issue in this case so it could continue to use water from the L-31E Canal for reducing temperature and salinity in the CCS. The proposed water use permit would authorize FPL to pump up to 100 million gallons per day during the period June 1 through November 30 in 2015 and 2016.1/ The permit prohibits withdrawals during the June through November period if they would interfere with the water reservation for Nearshore Central Biscayne Bay, which was established by Florida Administrative Code Rule 40E-10.061. The proposed project involves installation of three pumps and pipes to transfer water from the L-31E North Canal to the L-31E Canal where it would flow south to a point where two pumps would withdraw the water and discharge it through two pipes into the CCS. The permit would allow FPL to withdraw up to 100 million gallons per day (“mgd”). The proposed permit does not identify temperature or salinity objectives, but FPL would be required to submit weekly water temperature and salinity data to demonstrate that the water use is reducing the temperature and salinity of the water within the CCS. Tropical Audubon contends the proposed project is not entitled to a permit because it would harm the natural resources of Biscayne Bay, would increase saltwater intrusion, is not limited to the amount of water needed, and is inconsistent with the 2008 Certification Order and the 2014 AO. Biscayne Bay Biscayne Bay was a tidal estuary before human changes, as described above, reduced freshwater inflows to the Bay. Now the Bay has salinity levels characteristic of a marine lagoon. Salinity levels historically varied across Biscayne Bay, but now the salinity levels are higher. The species richness of Biscayne Bay has been reduced by the reduction of freshwater inflows; that is, the observed numbers of some animals and the areal extent of some plants have been reduced. The reservation of water for Nearshore Central Biscayne Bay is for a geographic area which generally follows the shoreline along Biscayne Bay and extends 500 meters from the shoreline. It is a small fraction of the total area of the Bay. Tropical Audubon stipulated that FPL’s proposed water use would not interfere with the water reservation for Nearshore Central Biscayne Bay, but it contends the reservation does not account for all of the freshwater needs of the Bay. Tropical Audubon’s expert, Dr. Lodge, suggested that the areal extent of “lower salinity grass beds” would increase with fresh water inputs exceeding the water reservation, which would benefit the species that use these grass beds. Neither the reservation rule nor the evidence presented by Tropical Audubon indicates what amount of freshwater is needed for all of Biscayne Bay. Tropical Audubon’s position is simply that more freshwater flow into Biscayne Bay is better than less and FPL’s proposed water withdrawal from the L-31E Canal will result in less freshwater reaching Biscayne Bay. Respondents stipulated that a substantial number of Tropical Audubon’s members have substantial interests in recreational uses in and near Biscayne Bay, but Respondents did not stipulate that the proposed project affected those interests. Tropical Audubon presented little evidence to demonstrate the proposed water use could affect its members’ substantial interests. Instead, it devoted almost all of its efforts at the final hearing and in its proposed recommended order to addressing matters that would not affect Tropical Audubon’s members, such as saltwater intrusion or inconsistency with the Certification Order. Tropical Audubon’s three-part proposition for harm to the substantial interests of its members is that (1) taking fresh water out of the L-31E Canal will deprive Biscayne Bay of fresh water that would otherwise flow to the Bay; (2) there will be a resulting reduction in the biological health of the Bay; and (3) the reduction in biological health will be noticed by Tropical Audubon’s members and will materially diminish their recreational enjoyment of the Bay. However, Dr. Lodge, was unable to say what effect FPL’s proposed water use (in two wet seasons) would have on the Bay. The effect could be de minimis. It could be undiscernible to a member of Tropical Audubon who is recreating on or near the Bay. Tropical Audubon failed to prove the proposed water use would have more than a de minimis effect on the environmental resources of Biscayne Bay. Therefore, it failed to prove non- compliance with any District permit requirement applicable to protection of Biscayne Bay and its natural resources. Saline Water Intrusion Section 3.4 of the Applicant’s Handbook requires that a water withdrawal must not cause harmful saline water intrusion. The saline water interface is generally where groundwater with greater than 10,000 milligrams per liter total dissolved solids (“mg/L TDS”) meets groundwater with less than 10,000 mg/L TDS. Because DEP classifies groundwater with less than 10,000 mg/L TDS as G-II groundwater and groundwater with greater than 10,000 mg/L TDS as G-III groundwater, the saline water interface can also be described as the interface between G-II and G-III groundwater. The location of the saltwater interface is affected by many factors, such as rainfall. “Saltwater intrusion” usually describes the human-induced landward movement of the saline water interface that has resulted from drainage structures, fresh water withdrawals, and other activities that have reduced the volume and, therefore, reduced the “push” of fresh groundwater toward the coast. Saltwater intrusion is considered harmful to water resources in large part because of its effect on land uses. Saltwater intrusion prevents or makes significantly more difficult future land uses that typically require withdraw and use of fresh groundwater, such as agriculture. For existing land uses that rely on withdraw of fresh groundwater, saltwater intrusion “contaminates” the water supply and can make the land uses no longer practicable. The hypersaline plume extends two or three miles west of the CCS and continues to move westward. It is pushing the saline water interface, which is now four or five miles west of the CCS, futher west. The saline water interface is moving westward at the rate of 400 to 600 feet per year. The CCS is causing harmful saline water intrusion. The factual dispute in this proceeding is whether the proposed use of water from the L-31E Canal increases the current intrusion problem. The parties also have a legal dispute about the scope of the District’s review regarding saline water intrusion: whether the District’s review is confined to the impacts of the withdrawal, itself, or whether the District must also consider the impacts of the use of the water after the withdrawal (discharging it into the CCS). The criteria in the Applicant’s Handbook focus the District’s review on the effects of a proposed withdrawal. With regard to saline water intrusion, the District evaluates whether the withdrawal will cause lateral or vertical migration of saline water. The District determined that FPL’s withdrawal from the L- 31E Canal would not cause the migration of saline water. That determination was not disputed by Tropical Audubon. Tropical Audubon contends the District must also determine whether FPL’s use of the water--discharging it into the CCS--would cause harmful saline water intrusion by pushing the saline water interface more landward. The District permit reviewer testified that, in determining whether FPL’s proposed project was consistent with the public interest, he considered the expected benefits of lowering salinity and temperature in the CCS, as well as reducing the hypersaline plume and its impacts on saline water intrusion.2/ As explained in the Conclusions of Law, this analyses is required to determine whether FPL’s proposed water use is consistent with the public interest. FPL used a water/salt budget model for the CCS to quantify the volume of water and mass of salt entering and exiting the CCS over time. The water/salt budget model was run for dry and average weather conditions and multiple withdrawal rates. In each scenario, the model results showed that the greater the volume of water pumped into the CCS, the greater the reduction of salinity in the CCS. The District performed groundwater modeling which showed that freshening of the groundwater would occur rapidly in the upper portion of the Biscayne aquifer near the CCS. The model showed no adverse impacts and some slight improvements in water quality in all areas except for one temporary effect at one monitor well. Based on modeling results and monitoring well data, it was the opinion of the District’s principal scientist, Mr. Giddings, that the addition of water from the L-31E Canal would not increase the western movement of the saline interface. FPL’s expert hydrologist, Mr. Burns, agreed. Tropical Audubon’s expert hydrogeologist, Mr. Martin, opined that the addition of L-31E water into the CCS would increase the westward migration of the hypersaline water in the Biscayne Aquifer and the saline water interface. It was his opinion that the addition of freshwater into the CCS would increase the water levels and the “driving head” within the CCS and thereby increase the downward push against the hypersaline plume, pushing it westward at a greater rate. Mr. Martin did not know what the increase in the rate of western movement would be. Mr. Martin conducted no modeling or other analysis to substantiate his opinion about the increase in driving head, and it appeared he did not take into account how the driving head would be affected by reducing the density of the water in the CCS. Reducing the density of the water would offset the effects of raising the water level. Mr. Martin’s opinion that adding water from the L-31E Canal would push the saline water interface westward was also based on his assumption that the fresher water moving downward from the CCS would not mix with the hypersaline water. However, this opinion was not supported by modeling as was the contrary opinions of Mr. Giddings and Mr. Burns. Monitoring data collected during the period in which FPL has added fresher water to the CCS indicates that mixing is occurring and that head differences in the CCS do not appear to affect chloride levels at distance. FPL provided reasonable assurance that the proposed water use would not increase the rate of saline water intrusion. Existing Legal Uses, Offsite Land Uses, and Pollution Tropical Audubon does not contend the withdrawal of water from the L-31E Canal would interfere with existing legal uses of water, adversely affect off-site land uses, or cause pollution. However, similar to its claim regarding harmful saline water intrusion, Tropical Audubon claims the proposed discharge of the water into the CCS would interfere with existing legal uses of water, harm offsite land uses, and cause pollution. These claims are derived from Tropical Audubon’s belief that discharging freshwater into the CCS would increase the rate of saline water intrusion. Because Tropical Audubon failed to prove the proposed water would increase saline water intrusion, there is no need to address the derivative claims. Conflict with the Conditions of Certification Tropical Audubon asserts that the proposed water use is inconsistent with the DEP National Pollution Discharge Elimination System (“NPDES”) permit for the Turkey Point Plant and with the Fifth Supplemental Agreement between FPL and the District. As explained in the Conclusions of Law, it is normally beyond the scope of a permit proceeding to claim the conditions of another permit would be violated. However, because the NPDES permit and the Fifth Supplemental Agreement are incorporated into or addressed in the 2008 Certification Order for Turkey Point, and the PPSA preempts all other environmental permitting associated with an electric power plant, it is relevant in this proceeding to determine whether the proposed water use would conflict with the conditions of certification for the Turkey Point Power Plant. It is also explained in the Conclusions of Law that the Administrative Law Judge’s consideration of potential conflict must be based on a conflict ascertainable from the plain meaning of the Certification Order, NPDES permit, and Fifth Supplemental Agreement. There has been no determination of conflict by the Siting Board or DEP. In fact, DEP has determined there is no conflict between the proposed water use permit and the NPDES permit. The fact that the NPDES permit describes the CCS as a closed-loop system does not create an irreconcilable conflict. The requirement for a closed-loop system was to terminate a system that had surface discharges of heated water to Biscayne Bay and replace it with a system that circulates water through the power plant with no surface discharges to the Bay. The CCS would still be a closed-loop system with the additions of water from the L-31E Canal because it would still have no surface discharges to Biscayne Bay. The fact that the NPDES permit does not mention the discharge of water from the L-31E Canal into the CCS does not create an irreconcilable conflict. The NPDES permit also does not address rainfall inputs to the CCS. The NPDES permit addresses industrial waste inputs. Water from the L-31E Canal, like rainwater, is not a waste input. The fact that the CCS will operate differently with the addition of L-31E water does not create an irreconcilable conflict. The manner in which water from the L-31E Canal would change the operation of the CCS is not different from the way variable rainfall constantly changes the operation of the CCS. The NPDES permit does not specifically prohibit the introduction of other water into the CCS. DEP determined that the addition of L-31E water would not require a modification of the NPDES permit because it would not change the effluent limits or monitoring requirements of the permit. Tropical Audubon asserts that the proposed permit is inconsistent with the Fifth Supplemental Agreement between the District and FPL. It points to a requirement in the agreement to “operate the interceptor ditch system to restrict movement of the water from the cooling water system westward of Levee 31 E adjacent to the cooling water system to those amounts which would occur without the existence of the cooling canal system.” The interceptor ditch is a ditch running along the western border of CCS, which was intended to intercept hypersaline groundwater and prevent it from moving further westward. It has failed to prevent the western movement of hypersaline water. Tropical Audubon did not show the proposed water use would affect the operation of the interceptor ditch. Therefore, Tropical Audubon failed to prove there is an irreconcilable conflict between the proposed water use permit and the Fifth Supplemental Agreement. Conflict with the DEP Administrative Order Tropical Audubon asserts that the proposed permit is inconsistent with an AO issued by DEP in December 2014 to address CCS salinity issues. However, the AO is not yet in effect and is not a part of the 2008 Certification Order. As explained in the Conclusions of Law, FPL’s compliance with the AO cannot be made a condition of compliance with the proposed water use permit. Furthermore, Tropical Audubon failed to demonstrate there is a conflict between the AO and the proposed water use. Summary In summary, FPL provided reasonable assurance that the proposed water use would comply with all applicable permit criteria. Tropical Audubon did not meet its burden to prove otherwise.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law it is RECOMMENDED that South Florida Water Management District issue a final order that grants the proposed Individual Water Use Permit (No. 13-05856-W) to Florida Power & Light Company. DONE AND ENTERED this 31st day of December, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of December, 2015.
The Issue The issue for consideration in this hearing is whether the Respondent, W. B. Persico, should be issued a permit to construct a commercial marina as described in the Department's Intent to Issue, in Class III waters of the state in Charlotte County, Florida.
Findings Of Fact At all times pertinent to the issues herein, the Petitioner, Burnt Store Isles Association, Inc., was an association of property owners whose property is located in the Burnt Store Isles subdivision located in Charlotte County, Florida. The applicant, W. B. Persico, is the owner of a piece of property located adjacent to the subdivision and applicant for a permit to construct a marina on his property. The Department of Environmental Regulation is the state agency responsible for the regulation and permitting of dredge and fill activities in the waters of the state. Mr. Persico's property is located on a dead end basin canal in Charlotte County, Florida. The canal is a Class III water but is not classified as an Outstanding Florida Water. On July 31, 1989, Mr. Persico applied to the Department for a permit to construct a 75 slip, 5660 square foot commercial marina on his property within this artificial, dead end basin. Because of objections by the Department to several aspects of the proposed project, on February 27, 1990, Mr. Persico submitted a modification proposal in which he eliminated the use of pressure treated lumber for pilings, substituting concrete pilings; incorporated boat lifts in each slip; reduced the number of slips from 75 to 65; committed himself to installing a sewage pump-out facility at the site; committed to creating an inter-tidal littoral shelf planted with mangroves; agreed to face the existing vertical bulkhead seawall in the basin with rip-rap; and incorporated a commitment to include, as a part of his rental contract, long term agreements prohibiting vessel maintenance and liveaboards on boats at the site, and insuring the perpetual use of boat lifts and pump out facilities provided. He now proposes to market the marina as a condominium ownership operation. The basin in which the Persico project is proposed is 136 feet across at the entrance, (the narrowest point), and 326 feet across at the widest point. The length of the basin is more than 900 feet. The docking structure to be created will have fingers extending no more than 39 feet into the water from the existing vertical seawall. It will have a 4 foot wide walkway parallel to and 10 feet from the existing seawall from which the arms will extend 25 feet into the basin. The basin which is the proposed location for the marina is at the end of the easternmost canal in the Burnt Store Isles subdivision. It is located just west of and parallel to US Route 41, and at the entrance point, joins a perimeter waterway which meanders approximately 1 mile seaward toward a lock which joins that waterway to Alligator Creek which is an Outstanding Florida Water. The waterway from the basin through the lock into Alligator Creek and thereafter to the Gulf provides the only navigable access for most vessels moored in the Burnt Store canals and which would be moored in the proposed marina between Charlotte Harbor and the Gulf of Mexico. The lock which joints the Burnt Store canals to Alligator Creek consists of two hydraulically operated swinging gates which are operated by a boater entering or exiting the canal system. This lock was constructed as a part of a 1973 agreement between Punta Gorda Isles, Inc., a developer, and the state to prevent the construction and runoff polluted waters of the canal from freely mingling with the Outstanding Florida Water in Alligator Creek. The lock is now maintained in an open position from November 15 to May 15 because boaters complained of the inconvenience of having to operate the lock system. Available evidence indicates that a complete passage through the lock, one way when closed, takes 15 minutes. No more than 24 boats can complete a round trip in a 12 hour boating day. When the lock is open there is no appreciable delay. The residential lots which abut the Burnt Store canals are still mostly vacant. The City of Punta Gorda has assumed the responsibility of conducting a 5 year water quality monitoring program which was previously agreed to by Punt Gorda Isles, Inc. when the lock was built. The 1973 agreement was amended in 1984 to permit the operation of the lock in a closed position for an entire year if water quality monitoring should indicate a degradation of water quality in either Alligator Creek of the Burnt Store Isles canals. This has not been necessary. The Petitioners fear that pollution generated by the addition of 65 additional boats moored at and operating from the proposed marina will cause the Department to implement that clause and order the lock to operate from a closed position year round. This does not mean that the lock would not be opened for boats, but that it would be closed when not being used. Petitioners contend that the increased usage would create an intolerable traffic jam at the lock which would, for the most part, make their use of the waterway to the Gulf intolerable. Mr. Persico is a former road and bridge contractor. Though he has never owned a marina, at one time he rehabilitated one in the Chicago area. He has owned the property in question here for four years and now plans to develop a condominium ownership marina. When he decided to do so, he hired Mr. James M. Stilwell, an environmental consultant, to prepare and submit to the Department the application for the required dredge and fill permit. Initial discussions between Mr. Stilwell and the Department dealt with many environmental issues. Mr. Stilwell pointed out that the water in the canal might already be stale and avenues were explored to mitigate that problem. They did not discuss the type of docks to be installed or the potential for destruction of mangrove stands along the seawall, but even though the original plan called for the docks to be placed against the seawall, it was to be done in such a way as not to disturb the mangroves. The modified plan removing the docks to a point 10 feet off from the wall will obviate any damage to the mangroves. Admittedly, the original submittal prepared by Mr. Stilwell contained factors which were considered unacceptable to the Department. These included construction of the finger piers with pressure treated wood. To eliminate possible pollution from leaching, the pressure treated wood was replaced with a floating dock using concrete pilings. Liveaboards, and the potential contamination from that activity, have been prohibited. The provision and required use of a sewage pump-out facility should prevent any escape of polluting sewage into the waters of the basin. The use of power hoists at each slip should prevent pollution from bottom paint leaching, and boat maintenance at the marina is to be prohibited. Fueling of the vessels will not be permitted at the site thereby obviating the potential of polluting fuel spills. The construction of a 10 foot wide littoral shelf, planted with mangroves, between the dock and the sea wall will provide increased water filtration and improve water quality. It would also help the development of the fish and wildlife population and would reduce the flushing time. Air released into the water from the use of the boat lifts should add oxygen and contribute to improved water quality. At the present time, the ambient water quality in the basin, as it pertains to dissolved oxygen, is probably below standards in the lower depths of the basin, and of the outside channels as well, due to poor light penetration. The channel depth is anywhere from 20 to 25 feet. The oxygen level at the bottom is undoubtedly depleted. Mangroves are currently located along 300 feet of the 1,300 foot seawall. Mr. Stilwell's proposal, and that approved by the Department, does not call for removal of the mangroves, but they would be built around or possibly trimmed. Mr. Stilwell is of the opinion that provision for trimming of the mangroves is inherent in the granting of the permit though such permission was not specifically sought. There is no evidence to contradict this thesis. Water quality issues were raised subsequent to the filing of the original application, and the facility as now planned is designed to minimize impacts on the environment as best as can be done. Water quality would be improved, or at worst not adversely affected, by the prohibitions against liveaboards and fueling, the provision of boat lifts and a pump station, and the prohibition against other structures beyond the dock and slips. Flushing of the water is important considering the fact that the dissolved oxygen content in the water is already low. However, Mr. Stilwell is satisfied, and it would so appear, that water quality would be improved by the implementation of the proposals as included in the conditions to the permit. Mr. Stilwell, admittedly, did no dissolved oxygen tests because they were not considered as a part of the permit application. If the Department requests them, they are done, but they were not requested in this case. It is clear that the original application did not address all the environmental concerns that Petitioners feel are pertinent. Nonetheless, those items already discussed were treated, as were turbidity control during construction. As to others of concern to Petitioners, many are included in the state standards and need not be specifically addressed in the application. The Department considered the application in light of the state standards, and by the use of the conditions appended to the Intent to Issue, provided for the water quality and other environmental standards to be sufficiently addressed and met. In his February 22, 1990 letter to the Department, Mr. Stilwell directly addressed the public interest concerns including the mangroves and the construction of the littoral shelf. The Department was satisfied that the public interest criteria were met, and considered the plans to be environmentally sound. They appear to be so. Petitioners have raised some question as to the effect of the 39 foot long dock fingers interfering with navigation within the basin. Mr. Stilwell does not feel that the facility would create this problem, even at the narrowest point, and it is so found. The width of the canal there is 136 feet. The portion of the slip designed to accommodate vessels is no more than 25 feet long, and presumably, vessels of a length much greater than that would not visit the basin. Even subtracting 39 feet from the 136 feet narrow point, 97 feet of turning space remains, and this is almost four times the length of the normal vessel anticipated in the basin. Mr. Stilwell did not address the subject of the lock as it relates to navigation, but primarily as it relates to the impact on water quality and the environment. Nonetheless, he is of the opinion, and there is no evidence to the contrary, that keeping the lock open on a year round basis would not trigger a change to the ongoing program under the agreement between the state and Punta Gorda Isles and result in the lock being closed year round. Mr. Shultz, the environmental specialist with the Department, reviewed the application here initially for file completeness, and when all required information was in, made a site visit. He evaluated the application and the attachments for permitability. For Class III waters, the project must meet water quality standards outlined in the Department's rules. Only one of the water quality criteria, that of dissolved oxygen, was shown to be not met. Since the water was already below that standard, the test to be applied then is whether the project will create some improvement." In Mr. Shultz' opinion, planting the mangroves, as proposed by the applicant, does this, as does the use of the lifts. The existing mangroves will not be impacted by the project as it is proposed, and the use of rip-rap, as proposed, will provide additional surface area for organisms which will improve the water quality. When first reviewed, the Department had some concern about on-water storage of boats. These concerns were treated by the use of hoists to hold the boats out of the water when not in use, and as a result, pollutants will not be introduced by bottom paint leaching and, presumably, bilge pumping. Standard conditions included in all Department Intents to Issue, require the project to comply with applicable state water quality standards or to give assurances that such general standards for surface waters and Class III waters will be met. In this case, Mr. Shultz is satisfied that the applicant has demonstrated that water quality standards will be maintained, and there was no evidence presented by the Petitioners to contradict this. Once water quality standards are shown to be protected, then the project is balanced against the public interest criteria outlined in the statute. Here, the requirement is for a showing that the project is not contra to the public interest. It does not, because of its nature, require a positive showing that the project is in the public interest. In his opinion this project, as modified, will not adversely affect the health, safety and welfare of the public, (it will have no environmental effect on other property). It will not adversely affect the conservation of fish or wildlife in their habitats, (the planting of mangroves will provide a net improvement to species habitat in the area). The project will not adversely affect navigation, flow of water, or erosion, (the width and length of the dock system appear to pose no threat to navigation in the basin and there would appear to be no obstruction or potential therefor as a result of this project; the project is within a no-wake zone; and the size of vessels is limited by the slip size). The permit will not adversely affect marine productivity, (there is currently very little productivity in the area now since waters below 0 depth of 6 feet are already low in oxygen, and the project would, at least minimally, improve this condition). The project is permanent and would not adversely affect historical or archeological resources in the area, (there are no objects or known resources in the area, but a standard condition in the permit requires immediate notification if known resources or objects are found). The project would not adversely affect the current condition and relative value of functions being performed in the area since the area is currently a real estate development which is far from completely built. Based on his consideration of these criteria, Mr. Shultz concludes that the project is not contrary to the public interest and this appears to be a valid conclusion. There appears to be no evidence of sufficient weight, presented by the Petitioners, either through direct evidence or through cross examination of the applicant and Department witnesses that would tend to diminish the credibility of Mr. Shultz' analysis. If there are subsequent violations, the Department has enforcement action available. There is, consistent with the multiple use zoning category applied to the area across the basin from the marina, the potential for up to an additional 100 docks to be constructed in the basin beyond those treated here. Nonetheless, the Department does not consider 165 boats to be a problem either in the basin or at the lock. This is not necessarily a supportable conclusion, however. Those 100 additional docks do not currently exist and their potential should not be considered in determining whether to approve the permit under consideration here. In opposition to the applicant, Mr. Konover and Mr. Forsyth both indicated that the addition of 65 more boats would seriously overtax the operation of the lock and make it difficult, if not hazardous, to operate boats in that area between the Burnt Store Isles subdivision and Alligator Creek. Both individuals agree, and it is so found, that in general, motor boats pollute to some degree the waters on which that are operated as a result of oil leaks from engine operation, leakage of bilge oil, escape of sewage, and leaching of copper paint and other solvents. In addition, manatee have been seen in the area, and the increase of boating operations could present some hazard to the manatee population. There is, however, no indication that a manatee population is permanently in residence there or is even there frequently. It is also accepted that boat wake has an adverse effect on sea walls, and all of these factors should have been and, in fact were, considered in the analysis of the permitability of the project. The concerns of Mr. Konover and Mr. Forsyth were echoed by Mr. Gunderson who, over 30 years operating boats, has seen what he considers to be a definite lack of concern for the environment by many boaters who pump bilges directly into the water, throw debris overboard, and use detergents to wash their boats at marinas. He is of the opinion that renters of slips are generally less concerned about water quality than those who live on the water, and take a more cavalier approach to water quality standards. These sentiments are also held by Mr. Young who, over the years, has owned marinas in Connecticut and has observed the approach of nonowning slip users to the water at their disposal. His concerns could be met by the strict enforcement of standards at the marina. Mr. Powell, a nurseryman who owns the lot across the basin from the site of the proposed marina, fishes from his lot and has observed the an increase of pollution in the canal. He routinely sees floating dead fish, palm leaves, cocoanuts, bottles, slicks and other debris, and though he owns a multifamily lot, would have a difficult time putting in many slips since his lot, at the entrance to the basin at the narrow point, would be across from the slips proposed by applicant and their proximity would, he feels, hinder his ability to build out into the basin as well.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of Environmental Regulation enter a Final Order issuing Permit No. 081679445, to W. B. Persico as modified and outlined in the Intent to Issue dated March 16, 1990. RECOMMENDED this 9 day of November, 1990, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9 day of November, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 90-3093 The following constitutes my specific rulings pursuant to S 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: 1. & 2. Accepted and incorporated herein. 3. & 4. Accepted. Accepted but applicable only when the locks are closed. Accepted. - 9. Accepted and incorporated herein. Accepted. & 12. Accepted and incorporated in substance herein. 13. & 14. Accepted and incorporated herein. Accepted and incorporated herein. Rejected as contrary to the weight of the evidence. Accepted and incorporated herein. & 19. Accepted and incorporated herein. 20. & 21. Unsupported by convincing evidence of record. Accepted as valid when the lock is operated from a closed position. However, the evidence indicates that currently the lock is left open from November 15 to May 15 of each year and this does not cause delay. Accepted if the lock is operated from a closed position. Unsupported by convincing evidence of record. FOR THE APPLICANT: 1. - 6. Accepted and incorporated herein. 7. - 15. Accepted and incorporated herein. Accepted and incorporated herein. & 18. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. Accepted. - 32. Accepted and incorporated herein. FOR THE DEPARTMENT: Accepted. and incorporated herein. - 4. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. & 9. Accepted and incorporated herein. 10. - 14. Accepted and incorporated herein. 15. - 18. Accepted and incorporated herein. COPIES FURNISHED: Joseph F. Lynch Burnt Store Isles Association, Inc. P.O. Box 956 Punta Gorda, Florida 33951-0956 Michael P. Haymans, Esquire P.O. Box 2159 Port Charlotte, Florida 33949 Cecile I. Ross, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Dale H. Twachtmann Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400
Findings Of Fact This cause commenced upon the filing of an application (#440816855) by William O. Reynolds to construct a weedgate and fence in front of a dead-end canal in Bogie Channel serving the Atlantis Estates Subdivision on Big Pine Key, Monroe County, Florida. The proposed project would be constructed in Class III waters of the State of Florida. An existing unpermitted weedgate exists in this location and the applicants for the proposed project are attempting to obtain a proper permit for a modified version of the existing gate. Applicants for the proposed project are property owners in the Atlantis Estates Subdivision, whose properties are adjacent to the canal in front of which the proposed weedgate and fence are to be located. An ad hoc committee of certain of the Atlantis Estates Subdivision owners had met and decided to proceed with an application for the proposed project. However, not all subdivision landowners agreed with the proposed project, most specifically the Petitioners Margaret and J. A. Abbanat. William Reynolds signed and submitted the application for the project, and indicated in a notarized affidavit in tie application that he was acting as agent for property owners in the Atlantis Estates Subdivision. Reynolds is one of those property owners, specifically lot #17. There are 26 lots adjoining the dead-end canal. At hearing, twenty (20) of the property owners indicated their support for the project by submission of notarized statements. The members of the ad hoc committee and the vast majority of property owners authorized and supported the project and the filing of the application by Reynolds. The permit application for the proposed weedgate and fence was submitted due to the problems caused by dead floating sea grasses and weeds (wrack) collecting in the Atlantis Estates Subdivision canal. Wrack has collected in large quantities in the canal in the past, and at such times problems such as stench, difficulty in navigation, and fish kills have occurred. Accumulated wrack in dead-end canals can cause water quality problems, including fish kills, and may also negatively affect navigation in the canal. Wrack is likely to collect in the Atlantis Estates Subdivision canal due to its dead-end configuration and due to its location, since the open end of the canal faces the east and the prevailing winds in this area are from the east. The weedgate and fence should cause no state water quality violations, should not unreasonably interfere with navigation where it is located at the mouth of the canal, and should actually improve water quality and navigation within the canal. Water quality outside of the weedgate and fence should not be significantly decreased since the winds, tides, and currents should allow the wrack to drift away into open water and not accumulate, especially not to the extent the wrack would accumulate in the canal. According to a proposed DER permit condition, the weedgate and fence must not cause a state water quality violation, and therefore if a water quality violation were caused by the project in waters outside the weedgate and fence, enforcement action would be required to correct the problem. If the weedgate and fence becomes a navigational hazard, it is to be removed according to a proposed DER permit condition. The application was not certified by a Professional Engineer. The Department's South Florida District Office did not seek such a certification from the applicant. The proposed project consists of a stainless steel framework with vinyl covered wire fence to prevent wreck from drifting into the canal and a gate through the fence constructed of the same type of materials with a cable and counter weight system for opening and closing the gate. As proposed, the weedgate and fence should not create a navigational hazard, but should that occur, the proposed DER permit condition would require removal.
Recommendation Based upon the foregoing Findings of Fact, and Conclusions of Law, it is, therefore, RECOMMENDED that the State of Florida Department of Environmental Regulation grant the application and issue the permit subject to the following conditions: That the weedgate and fence be removed if at anytime a navigational hazard develops or the structure fall into disrepair. That the weedgate and fence must not cause a state water quality violation outside of the fence and if such water quality violations were caused by the project in water outside the weedgate and fence, enforcement action would follow. DONE and ENTERED this 8th day of March, 1985, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of March, 1985. COPIES FURNISHED: J. A. and Margaret M. Abbanat 5561 SW Third Court Plantation, Florida 33317 William O. Reynolds Route 1, Box 661-E Big Pine Key, Florida 33043 Douglas H. MacLaughlin, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301