Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
PALMETTO POINT HOMEOWNERS ASSOCIATION vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-003488 (1983)
Division of Administrative Hearings, Florida Number: 83-003488 Latest Update: Apr. 02, 1984

Findings Of Fact On December 9, 1982, Petitioner filed with Respondent a dredge and fill permit application to remove gates and wing-walls from a double-lock canal system presently installed at the Palmetto Point Subdivision in Lee County, Florida, adjacent to the Caloosahatchee River. On January 6, 1983, Respondent sent a "completeness summary" to Petitioner, along with a letter advising Petitioner that its permit application was incomplete, and requesting additional information. Petitioner responded to the January 6, 1983, completeness summary by submitting additional information to Respondent on or about February 23, 1983. On March 21, 1983, Respondent sent a second completeness summary requesting further additional information from Petitioner. By letter dated May 18, 1983, Petitioner's attorney advised Respondent that submission of additional requested hydrographic information and water quality data was not justified. The letter further advised that Petitioner intended to rely on the information already submitted, and requested, pursuant to Section 403.0876, Florida Statutes, that Respondent begin processing the permit application. The letter further indicated that petitioner was submitting under separate cover a request that Respondent apply the "moderating provisions" of Rule 17-4.244, Florida Administrative Code, to the application. The aforementioned rule is entitled "Mixing Zones: Surface Waters." Also on May 18, 1983, Petitioner's counsel sent another letter to Respondent requesting the aforementioned "Mixing Zone." The letter requested the "maximum mixing zone" allowed under the applicable Provisions of Rule 17- 4.244, Florida Administrative Code. Petitioner had not requested a mixing zone be applied to the permit application prior to the request contained in its May 18, 1983, letter. By letter dated June 17, 1983 Respondent, in response to Petitioner's May 18, 1983, letters, advised that: The additional information [which] was received on May 19, 1983, was reviewed; however, the items listed on the attached sheet remain incomplete. Evaluation of your proposed project will continue to be delayed until we receive all requested information. Respondent's June 17, 1983, letter included a completeness summary, which asked for additional information, including the following requests concerning mixing zones: Your request for a mixing zone is applicable pursuant to F.A.C. Rule 17-4.244(6). Please provide a map indicating the outermost radius of the mixing zone (no more than 150 meters) and the period of time required. The completeness summary acknowledged Petitioner's refusal to supply additional information concerning hydrographic data and water quality information, and indicated that Respondent would evaluate the project accordingly. By letter dated August 29, 1983, Respondent advised Petitioner that it had been 73 days since notification of the incompleteness of the permit application with regard to the mixing zone request. This letter requested Petitioner to advise Respondent if it wished to withdraw the application, request additional time, or discuss questions regarding the application. The Petitioner did not respond to this communication. On September 9, 1983, Petitioner's attorney forwarded a letter to Respondent requesting a default permit pursuant to Sections 120.60(2) and 403.0876, Florida Statutes. Until this letter, other than a prior oral communication on September 2, 1983, notifying Respondent that the default request was forthcoming, Petitioner had not contacted Respondent concerning the permit application since its May 18, 1983, letters. On October 13, 1983, Respondent advised Petitioner by letter that the mixing zone request constituted a revision of the application and that the information received to evaluate the mixing zone request was incomplete. Petitioner was also advised that since the additional information requested had not been received, the application remained incomplete and Petitioner was not entitled to a default permit. Whether or not a mixing zone is applied to a permit application is significant because it determines where state water quality standards must be met, either adjacent to the proposed project, or up to 150 meters away from the project location. Under Rule 17-4.244(6), Florida Administrative Code, the 150 meter radius is measured from the point of generation of turbidity or pollution. Since the two locks to be removed were 80 feet apart, it was unclear whether Petitioner intended the point of generation for measuring the radius of the mixing zone to be the northern lock, the southern lock, or some other point. It is equally unclear whether Petitioner intended the mixing zone to extend south into the canal as well as north into the Caloosahatchee River. Petitioner never contacted Respondent to clarify the dimensions of the mixing zone being sought, even after Respondent requested a map indicating the outermost limits of the mixing zone in the June 17, 1983, completeness summary.

Florida Laws (3) 120.57120.60403.0876
# 1
CITY OF COCONUT CREEK AND MR. AND MRS. W. H. LEE vs. BROWARD COMMUNITY COLLEGE AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-003672 (1983)
Division of Administrative Hearings, Florida Number: 83-003672 Latest Update: Oct. 30, 1984

Findings Of Fact Based on the stipulations of the parties, the exhibits received in evidence, and the testimony of the witnesses at the hearing, I make the following findings of fact: On April 21, 1983, the College filed an application with DER seeking a permit to relocate a drainage ditch that runs through the College property, to fill the existing drainage ditch, and to install a large culvert in the Coconut Creek Waterway which would serve as a road crossing connecting the proposed new College parking lot and N.W. 39th Avenue in Coconut Creek. Upon review of the original application, DER determined that it would not meet the DER's water quality criteria. On September 30, 1983, the College revised its application. It is the revised application which lies at the heart of the present controversy. The revised application no longer contains a proposal to fill in the entire ditch that runs through the College property. Rather, it is new proposed to install two 36-inch culverts in the existing ditch to provide access roads to the proposed new College parking lot. The College also proposed to dredge 832 cubic yards from .5 acres and to install a large structural culvert (measuring 14 feet, 1 inch, by 12 feet, 10 inches) in the Coconut Creek Canal. The existing ditch which runs through the College campus was originally constructed as a drainage ditch. The only water which would flow through that ditch would be provided by run off from the N.W. 11th Street area. At the present time the ditch through the College is plugged in two places. Some time in late July or early August of 1984, contractors employed by the College placed two earthen plugs in the ditch that runs through the College. This was done without benefit of a Department permit and was apparently the result of some confusion on the part of the contractors, the exact nature of which is not explained in the record in this case. The two earthen plugs were not installed in the manner proposed by the subject application, nor were they installed in the locations proposed in the subject application. In their present condition the two earthen plugs effectively prevent the flow of any water through the ditch that runs through the College. The north end of the ditch that runs through the College campus was formerly connected to Coconut Creek Canal. A portion of Coconut Creek Canal runs parallel to N.W. 11th Street. Following the installation of the earthen plugs there was a decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W. 11th Street. The water became cloudier than before and there was some silting. There were fewer base and bluegills and more mudfish. There has also been an occasional unpleasant odor from the area which was not present prior to the installation of the earthen plugs. Also, the residents along N.W. 11th Street complain of an increased mosquito Population since the installation of the earthen plugs. 1/ The proposed 36-inch culverts are substantially larger than is necessary to handle the anticipated flow of water through the College ditch. Calculations made using the methodology approved by the Florida Department of Transportation indicates that 21-inch culverts would have been sufficient to handle any anticipated flow of water through the College ditch. Although the culverts will require some periodic maintenance, they have been designed to minimize the need for maintenance. Properly maintained, the proposed 36-inch culverts will not pose any impediment to the flow of water through the College ditch. There is usually no detectable current or water flow in either Coconut Creek Canal or the College ditch in the area where the College proposes to install the three culverts. Accordingly, inasmuch as there is usually no detectable flow of water, any impediment to water flow which might be caused by the culverts is insignificant. This is particularly true with regard to the issue of weed growth. While it has been contended that the culverts might reduce the rate of water flow to the extent that aquatic weed growth would be promoted because of the stillness of the water, long before this permit was ever applied for and long before the earthen plugs were installed the City of Coconut Creek had serious problems with aquatic weeds growing in all of its canals. As described by one of the City's former mayors, several years ago the hyacinths covered the canals solid from bank to bank and were growing so thick and solid that rabbits could actually run across the canals hopping on the hyacinths. This type of hyacinth growth only occurs in still water. The City has been able to control the hyacinth problem by an ongoing weed control program which consists of spraying chemicals on the plants several times each year. The small amount of water flow which does occur in Coconut Creek Canal is directly related to stormwater runoff, including water generated by the residents along N.W. 11th Street washing their cars and watering their lawns. The portion of Coconut Creek Canal which extends eastward from the College ditch is a dead end system in which the only flushing is due to water runoff from the street. The installation of the proposed large culvert in Coconut Creek Canal would never cause the water to back up in the canal or otherwise impede the flow of water in the canal. A tube 21 inches in diameter would be sufficient to carry away the worst expected rain water conditions and the proposed culvert is, in essence, a tube with an average diameter in excess of 13 feet. The large culvert would cause no change in the volume of water flowing through the canal. It might cause a de minimis headloss, which is a change in the water level from one side of the culvert to the other. Any such headloss would be on a magnitude of approximately 1/1000th of a foot; about 1/3 of a millimeter. The installation of the large culvert in the Coconut Creek Canal would actually increase the velocity of any water flow through the culvert. In conjunction with the installation of the large culvert, the depth of Coconut Creek Canal would be increased to an average of six or six and one-half feet from its present average of approximately five or five and one-half feet. Notwithstanding the decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W 11th Street which apparently resulted from the unauthorized installation of the two earthen plugs, when the water in that portion of the canal was tested by the City's export witness some eight or nine months later, the water quality was within established state standards. And while the construction activity associated with the installation of the two 36-inch culverts in the College ditch effect on the water quality in Coconut Creek Canal, there is no evidence that water quality standards would be violated on either a short or long-term basis. A small amount of habitat would be destroyed, but it is likely that there would be rapid recolonization. No rare or endangered animal species would be affected. The habitat for birds would also recolonize and the birds and fish displaced by construction would return. Any turbidity problems during construction would be controlled by the use of turbidity screens. With regard to navigability, once installed the large culvert would provide a vertical clearance from the surface of the canal of approximately six feet. This clearance would prevent larger boats from passing through the culvert. The vertical clearance of existing canal bridges in the area varies from six and one-half to eight feet. Installation of the larger culvert would not seriously impede navigation. The large culvert would not constitute a navigational hazard nor would it impede the flow of navigable water. As compared to the situation which existed prior to the installation of the two earthen plugs, installation of the two 36-inch culverts would totally stop any boat traffic through the ditch that runs through the College. Nevertheless, curtailment of boat traffic through the College ditch would not seriously impede navigation because any destination which could be reached by traveling through the College ditch could be reached via alternative canal routes which are not affected by this project. As with the larger culvert, the 36-inch culverts would not constitute navigational hazards nor would they impede the flew of navigable water. If the total project envisioned by the College is completed, the culverts will provide a new route for motor vehicle access to an expanded College parking lot. The increased volume of motor vehicle traffic would produce an increased amount of air and noise pollution in the vicinity of N.W. 39th Avenue. A study of the results of the increased motor vehicle traffic based on a "worst case" scenario reveals that even with the additional air and noise pollution generated by the increased motor vehicle traffic, the air and noise pollution levels in the area would be far below the air and noise pollution standards established by the state and federal governments. In the formulation of the foregoing findings of fact I have, of necessity, relied to a large extent on the opinions of expert witnesses who testified in the case. Where there is conflict in the testimony of the expert witnesses, I have generally credited the testimony of the expert witnesses called by the College and the Department because I have found their testimony to be more consistent with other evidence in the case and have found that there is a better factual foundation in the record for their opinions than for the opposing opinions.

Recommendation For the foregoing reasons it is Recommended that the Department issue a Final Order which would GRANT the College's application to install two 36-inch culverts in the College ditch and a 14-foot, 1-inch, by 12-foot, 10-inch, culvert in the Coconut Creek Canal, subject to the conditions set forth in the Department's Notice of Intent to Issue. DONE and ORDERED this 8th day of October, 1984, in Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of October, 1984.

Florida Laws (1) 120.57
# 2
PORT-O-PALMS CONDOMINIUM B., INC.; ET AL. vs. TAVERNIER HARBOR, INC., AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 86-002057 (1986)
Division of Administrative Hearings, Florida Number: 86-002057 Latest Update: Jun. 29, 1987

Findings Of Fact Tavernier Harbor, Inc. (Tavernier, Applicant) has applied for a dredge and fill permit seeking to install seven 40' X 18' boat slips and one 25' X 3' finger pier and to construct a total of 3,024 square feet of perimeter boardwalk, with the eleven six foot wide access walkways over a "mangrove fringe" at a boat basin in an unnamed canal lying at Section 4, Township 63 South, Range 38 East in the municipality of Tavernier, Monroe County, Florida. The site plan and permit application provides that the slips are to accommodate sport fishing boats There would be 564 linial feet of boardwalk waterward of the mangrove fringe surrounding the boat basin and 160 feet of boardwalk landward of that mangrove fringe, with one finger pier of the above dimensions. The landward side of Tavernier's development will contain a restaurant and bar with an adjacent parking area, a storm water drainage system as well as a sewage treatment plant. There will be a six foot high wall screening the parking area from the surrounding non-owned property and public roadways. Tavernier intends to use the property as a sport fishing harbor to moor seven boats as well as to provide transient dockage for users of its upland restaurant or for boat owners or users who travel by car to the upland facilities and parking area. Various environmental impact abatement or mitigation facilities and procedures are proposed to be incorporated in the project in its construction and operation as delineated more fully below. Tavernier owns the entire upland property surrounding and upon which the proposed project will be constructed and operated. Tavernier does not own the submerged land in which the proposed pilings for the boardwalk, slips and pier will be placed, but has received authority from the State of Florida Department of Natural Resources to proceed with the project. The proposed project will be located in a rectangular basin approximately 120 feet wide by 414 feet long, lying at the end of a "dead end" canal which connects with Tavernier Creek, some 2,000 feet away. The canal and basin are box cut (straight sides) into the bedrock with an average depth of approximately 10 feet. The waters of Tavernier Creek and the adjacent Atlantic Ocean lie in the Florida Keys Outstanding Florida Waters as designated in Rule 17-3.041(4)(i), Florida Administrative Code. Artificial water bodies, including canals, within the Florida Keys are excluded from the Outstanding Florida Water (OFW) designation by this rule. Artificial water bodies include canals which have been dredged, as this one has historically, as well as water bodies which existed naturally in whole or in part whose banks or boundaries have been artificially altered by filling. Such is also the case here. In this connection, an aerial photograph in evidence dating from the late 1940s indicates that natural surface waters may have existed at one time in certain portions of the area presently encompassed by the above described boat basin and canal, however, it was not established by competent testimony that the waters depicted in the aerial photograph were actually natural waters or what the depth of those waters might have been as opposed to the above found present average depth of the canal and boat basin at issue. There was credible testimony by persons experienced with the naturally occurring waters of the Florida Keys, which established that the natural waters shown in the 1940s aerial photograph in the vicinity of the boat basin were so-called "floc ponds," which characteristically have a depth of no more than one or two feet. Additionally, the boundaries of the water bodies depicted in the 1940s photograph are not coincidental with the present boundaries of the boat basin or canal system where the project is proposed to be constructed and operated. The basin in which the proposed project is to be placed and the canal connecting it to Tavernier Creek are not natural bodies of water and are instead artificial water bodies created by dredging, excavating and filling of the original boundaries. Therefore, the proposed project is not located in designated Outstanding Florida Waters. The land surrounding the canal and boat basin and owned by Tavernier is historically filled land with a relatively young growth of native vegetation surrounding the basin area. The majority of the boat basin perimeter is vegetated with red, black and white mangroves. White mangroves occur predominately on the upland, near-shore slope of the basin. The surrounding area off the project site is occupied by docks, boats and seawalls owned by non- parties. The boat basin area is non-bulkheaded, although there is a remnant bulkhead which is now largely vegetated. The Tavernier property is surrounded by three roads, the Overseas Highway, the Old Overseas Highway, as well as side streets on the other two sides of the property. The biota present in the basin and canal area involved consists primarily of small fish such as snappers and grunts and occasional small barracuda. Within the mangrove system itself there are algae colonies on the mangrove roots as well as gastropod mollusk systems, with some periwinkus snails on the water bottoms and numerous types of analids, jellyfish, cassipia and tulip snails, as well as various types of minnows and other small fish. Most of the aquatic life in the basin canal system is associated with the vegetative mangrove fringe which provides some structural relief in the water and thus a beneficial marine habitat system for these types of aquatic life. There are no seagrasses associated with the project site or the nearby areas in the artificial canal. There will be no adverse impact on seagrasses. There is presently a healthy biological diversity of life forms in the canal and basin system. Water Quality The Water Quality Rules germane to this proceeding dictate that water quality impact of the proposed project in the basin and canal system must be examined with regard to short term and long term water quality impacts. Short term water quality impacts of the proposed project only involve potential turbidity generated by construction, that is, by the driving of pilings into the bottom substrate to support the finger piers, boardwalks and to create the boat slips. The Applicant agreed at hearing to alleviate such a potential impact by the installation and use of turbidity curtains around the entire construction area during installation of the pilings and decking for the boardwalk, deck and finger pier. In view of the established fact that the driving of the pilings will not cause the suspension of a significant amount of turbidity, reasonable assurances have been provided that this pile driving activity, coupled with the use of turbidity curtains, will result in no violation of state water quality standards as to this pollution parameter. This method of construction and the use of turbidity curtains should be incorporated in the permit as a mandatory condition. The long term water quality impacts which must be examined here are associated with the use of the basin, and to some extent the canal, by boats with the attendant potential for pollution associated with boating activities, as well as the long term pollution effect of storm water runoff from adjacent upland areas into the basin. In this regard, storm water now entering the basin carries with it an indeterminate amount of pollutants associated with surrounding, inhabited upland areas and surrounding automobile roadways. The project as now proposed will alleviate much or all of the present storm water runoff pollutant effect and will prevent any additional such effect occasioned by the installation and operation of the project with regard to upland- originated pollutants. This is because the Applicant has proposed to install, pursuant to its storm water drainage plan, a reverse gradient configuration around the perimeter of the basin on the upland which will divert storm water back on to the upland and prevent it from entering the subject basin. The storm water would be directed into approved storm water filtration basins. Thus, to the extent that storm water may be exerting a pollutant effect on the basin and canal at the present time, the project as proposed represents a marked improvement. The only other potential long-term source of water quality degradation from the proposed project, concerns the pollution that may emanate from the use of boats in the basin, canal and dockage facilities. This potential source will be offset by the diversion of similar type oil, grease and other pollutants already entering the basin from the upland by the storm water diversion and filtration system as well as by the preservation of the present mangrove fringe. The mangrove fringe is quite important to alleviating water quality impacts due to present pollution or due to increased boat traffic as a result of the installation of the project. Mangroves provide an important function in this regard in that their root systems serve to up- take excessive nutrients, heavy metals and other pollutants from the water into the mangroves, thus serving as an important natural filtration system. Additional methods of alleviating the water quality impacts due to pollution from boats and associated activities consist of establishing certain permit conditions, described below, which will prevent boat operation and related activities from lowering ambient water quality and requiring a continuous, long-term operation permit by which those conditions may be enforced, associated with requiring an extensive, water quality monitoring program. That program will require site modification and ultimately even removal of the project if water quality parameters are not met in the long term. Increased boat operation in the basin can result in discharges of hydrocarbons, toxic metals (chiefly from boat bottom paint), organic debris (chiefly associated with disposal in the water of fish cleaning offal) as well as the deposition of detergent material in the waters involved. Additionally and importantly, the presence of boats with heads can result in sewage spills or discharges. It was established, however, that boat use in the canal and associated pollution will not be solely due to the Applicant's proposed project. The canal margin is already almost entirely developed with approximately forty developed lots, most of which have boats associated with them with attendant docking facilities. Many of the same water quality contaminants such as hydrocarbons and greases, heavy metals, nutrients and organic material that would be expected from boat operations and fish cleaning are already present in the canal and in untreated storm water entering the canal and basin system from adjacent roads and parking areas. These contaminants will be reduced somewhat by the installation of the storm water diversion and filtration system at the basin. Additionally, as mentioned above, the proposed project will retain the vast majority of the present mangrove fringe filtration system surrounding the basin. The mangrove fringe will continue to serve its function of filtering and absorbing nutrients and other contaminants related to both storm water runoff and boat operation, which are now or will be entering the system. The Applicant has agreed to the imposition of several permit conditions which will control boat operation pollutants. These include the prohibition of any boat fueling facilities and boat fueling by private owners, the prohibition of "live aboard" boats which require frequent sewage pumpout and pose a substantial risk of illegal sewage discharge, the prohibition of boat hull cleaning and major boat maintenance (other than minor engine adjustments), and the mandatory requirement of an oil spill containment and removal apparatus which must be kept and maintained on the site. An extensive pre-construction and post-construction water quality monitoring plan will be required because of the paucity of background data available concerning existing water quality in the basin and canal. Such monitoring is necessary to determine the effectiveness of the storm water management plan and structures, as well as all the other permit conditions. The applicant has agreed to the implementation of such a long term water quality monitoring plan. Additionally, the Applicant will be required to obtain a long term operating permit in addition to the construction permit, which will allow for continuous Department review of the project and its operation. If water quality standards are not consistently maintained, the permittee will be required to change the marina design, management or operation to correct the problems. These changes can include the reducing of the size and number of boat slips and dockage facilities and ultimately even the physical removal of the proposed project and the non-renewal of the operating permit. In this connection, the evidence of record reveals that the ambient water at the site occasionally is violative of state water quality standards for dissolved oxygen. This is characteristic of such dead end canal and basin systems which are characterized by a very low flushing rate. This canal system flushes such that approximately 90 per cent of the waters therein are exchanged in approximately 5 1/4 days. This is quite a low flushing rate which tends to concentrate pollutants over time. This, however, is an ambient or natural condition in the canal as it presently exists and is not a water quality problem occasioned by the proposed project. The Department has heretofore followed a policy of granting permits where such a parameter is sometimes not in accordance with state water quality standards and indeed, with regard to the instant project, the permit conditions which will be implemented and enforced, especially including the upland sewage and waste disposal system and storm water management and disposal filtration system have been reasonably shown to assure an overall improvement in the water quality in the basin area involved. In addition to prohibiting live aboard boats as a means to protect water quality in the face of boat traffic in the basin area, the Applicant will construct an upland, approved and permitted sewage treatment and disposal facility. Approved and properly maintained pump-out facilities for boat- generated sewage are also proposed and must be required. The Applicant also proposes dockside fish cleaning facilities to help ensure that fish cleaning debris is not deposited in the waters of the basin and canal. In view of the evidence of record which establishes that any other disposal area, such as the open ocean, for fish remains is a substantial distance from the project site, dockside fish cleaning facilities will not ensure that fish debris is not deposited in the waters of the basin because dockside fish cleaning facilities are too proximate to the waters sought to be protected. Accordingly, the evidence of record reveals that, for reasonable assurances to be provided that fish cleaning debris will not be deposited as an organic, nutrient pollutant in the waters of the basin, any fish cleaning facility should be placed a significant, reasonable distance from the dockage facilities on the upland with discharge of the waste into an appropriate waste disposal system, which the Applicant proposes to install. Such should be an additional condition to granting a permit. In addition to the above, there were no other water quality issues presented in this proceeding. In view of the fact that water quality may be enhanced by installation of the project with the above conditions and proposals by the Applicant, the project as presently proposed will reasonably assure that state water quality standards are not violated by the fact of the installation and operation of the proposed project and attendant boating activities. Public Interest Standards Section 403.918(2), Florida Statutes It was not established that the proposed project will adversely affect the public health, safety or welfare or the property of others in a significant way. The main concern regarding the "public welfare" or "property of others" was feared adverse impacts of increased boat usage in the canal with attendant wakes and erosion of shoreline property. These concerns are alleviated by two factors. First, almost all the canal front property involved is presently seawalled, thereby substantially reducing the impact of waves from boats. Secondly, the Applicant has agreed and the Department will require, that the Applicant post "idle speed--no wake" signs at both the entrance to the canal and at the end of the canal at the basin within the Applicant's own property. Additionally, the canal boundaries are largely developed with approximately 40 developed lots with approximately as many attendant boats already using the canal. The relatively small number of additional boats that the proposed project will entail will not significantly add to any erosion problem due to boat wakes, which will be alleviated in any event because of the fortified shorelines already existing and because of the use of the signs with attendant citizen reporting of excessive boat speeds to the Applicant's management as well as to the Department of Natural Resources Marine Patrol. In conjunction with the above-discussed monitoring plan to be imposed as a condition to the permit consideration should be given by the Department and the Applicant to obtaining necessary authority (i.e. from the Department of Natural Resources and the U.S. Army Corps of Engineers) for posting buoys or other similar partial obstruction devices at strategic locations in the canal channel to prevent boats from having the ability to operate on a straight course at high throttle levels when traversing the channel. This, too, should be a condition incorporated in the permit. The project will not adversely affect the conservation of fish and wildlife, including endangered, threatened species or their habitats. The evidence reflects that on rare occasions manatees have been seen in or in the vicinity of the canal, although the evidence does not reveal that this is truly a manatee habitat area. In conjunction with the posting of idle speed--no wake signs, the Applicant should be required to post signs indicating that it is an area frequented by manatees and urging attendant caution in boat operation. Although there will be some net loss of existing mangroves at the basin, at least 90 percent of the extant mangroves will remain. The record reveals that for unknown reasons, and at a time prior to the institution of this proceeding, the Applicant removed or cut some of the existing mangrove growth at the basin site. The permit should be conditioned upon the Applicant replanting or allowing regrowth of the mangroves so removed or altered. Additionally, it having been shown that the walkways between the landward deck and the boardwalk supported by pilings in the water of the basin are for pedestrian use, it was not established as necessary that the walkways should be six feet wide and of the total number depicted in the Applicant's design and plans. The presence of the boardwalks connecting the landward deck and the waterward boardwalk are the direct cause of ten percent removal of the existing mangroves due to the mangroves beneath the walkways being shaded from the sunlight. Accordingly, the Applicant, as a condition to the permit, should be required to either redesign the walkways so that they are significantly narrower than those proposed or reduce the number of these bridges over the mangroves by 50 percent so that only a maximum of approximately five percent of the extant mangroves will be ultimately removed or destroyed. Despite the fact that manatees have been seen in the canal, the habitat in the canal and basin is not favorable for attracting manatees and, additionally placement of the marina away from a pristine natural area as is the situation here will generally tend to have much less of an adverse impact on fish and wildlife than if the marina were placed in a pristine natural area often frequented by manatees and other endangered species. The proposed project will not adversely affect navigation or cause harmful erosion or shoaling. The evidence establishes that the small numbers of additional boats using the canal as a result of the project will not cause additional navigation problems of any significance. The possible erosion caused by boat wakes already is an existing condition and the small number of boats which would be added to present traffic in the canal as a result of the project will not substantially exacerbate any problem that exists, especially in view of the conditions which will be imposed and are discussed above. The proposed project will not adversely affect fishing, recreational values or marine productivity in the vicinity of the project. For the reasons referenced above, there will be no water quality problems occasioned as a result of this project provided the conditions found to be necessary herein are imposed on the permit, the project construction and the project operation. If these are accomplished, there will be no adverse effect on fish and wildlife. Fishing, recreation and marine productivity in the area in turn will not be adversely affected from a water quality standpoint. Additionally, the proposed project will have the positive impact of enhancing the public recreational value of the area since it will offer public facilities for people seeking to navigate the state waters in the vicinity of the project by the provision of a small amount of additional dockage space. Maintenance of the mangroves in the manner depicted above will maintain and indeed, to a small degree, enhance marine productivity. The members of the public presently using the canal and basin area to fish, swim or perform similar activities will be able to continue doing so. In short, the project will not adversely affect marine productivity. There is no evidence of record to indicate that the project will adversely affect historical or archaeological resources. Concerning the "permanence" criteria under the above-cited statutory subsection, the project will indeed be of a permanent nature. The operating permit which the Department will require, will determine, with the conditions incorporated in it, whether or not the project remains a permanent structure. That is, if the various water quality parameters and the various considerations in the above-cited public interest provisions are not complied with, alteration of the project or even ultimate removal of the project may be required. Concerning the public interest criteria regarding current conditions and relative value of the functions being performed by the area involved, the project as proposed to be constructed and operated will not cause any adverse impact on current conditions and relative value of the resources of the project area as a functioning habitat for marine life. The functions and value of the area as a habitat for fish and wildlife and as an area of marine productivity will be unaltered in its post-development state, provided the conditions referenced herein are imposed, especially those related to protecting water quality from the impacts of boat operation, human wastes and waste attendant to fish cleaning operations. Cumulative Impact There have been no similar permit applications submitted to the Department in the past five years for projects in this canal and basin system. In fact, there have been only three or four shoreline dockage facilities permitted by the Department within a four square mile area in the vicinity of the proposed project. There are approximately 40 lots along the canal leading up to the Tavernier Harbor basin. The majority of these lots have already been developed with single family residences and the majority of them already have seawalls with dockage capability. The development of the few remaining undeveloped lots along the canal, coupled with the installation of the proposed project, should not significantly add to the cumulative effect upon water quality and the public interest parameters discussed above. There is only one other pending dock permit application received by the Department for any area near the proposed project. Thus, there will not be any cumulative adverse effect causing violation of any of the water quality or public interest standards at issue if the proposed project is built and operated and exists with other proposed or existing facilities In addition to the above conditions, Tavernier Harbor, Inc. has agreed to devise a contingency plan concerning oil spill containment and removal to be utilized in the event of a spill, which shall be submitted to the Department for review and changes as necessary prior to the commencement of the project's construction. The Applicant has agreed that all perimeter docking areas will be aligned waterward of the mangroves, whereas the restaurant deck will be placed landward of the mangroves. The Applicant has agreed to conduct water quality monitoring of the canal to include a minimum of one year pre- construction data and a minimum of two years of data collected after the project has been constructed and is operating. The Applicant will apply for a long-term operating permit for the mooring facilities and agrees to continue - monitoring and to implement necessary changes to marina design or management as directed by the Department in order to maintain water quality standards on a permanent basis. Tavernier Harbor, Inc. will also institute, prior to issuance of the operation permit, a maintenance program to permanently ensure removal of floating debris from the basin and project site. The Applicant has agreed and should be required to provide sewage pump out and treatment facilities capable of providing upland disposal and treatment of sewage and will provide an upland area well removed from the basin waters and the mangrove fringe for the conducting of fish cleaning operations and disposal of related waste material. The Applicant has agreed, and the permit should be conditioned upon, the allowance of only seven permanently moored sport fishing boats at the site and restriction of the use of the boardwalk waterward of the mangroves to only be used by "transient boats," with no permanently moored boats docked thereto. In summary, it has been established that the project will not degrade state water quality standards or the public interest criteria referenced above. The basin at the project site presently meets state water quality standards with the minor exception of occasional deficient levels of dissolved oxygen which naturally occur at the site.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that the application of Tavernier Harbor, Inc. for the dredge and fill permit sub judice be granted, provided that the terms and conditions enumerated in the above Findings of Fact are incorporated in the permit as mandatory conditions. DONE and ORDERED this 29th of June, 1987, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-2057 Petitioner's Proposed Findings of Fact: 1-3. Accepted. Rejected as contrary to the greater weight of the evidence. Accepted as to the first two sentences but not as dispositive of the material issues presented. Accepted except for the first and last sentences which are contrary to the preponderant evidence. Rejected as to its material import. Rejected as contrary to the preponderant evidence and as subordinate to the Hearing Officer's finding on this subject matter. Rejected as contrary to the greater weight of the evidence. Rejected as not dispositive of the material issues presented. Rejected as contrary to the greater weight of the evidence. Rejected as not dispositive of the material issues presented. Respondent Tavernier Harbor, Inc.'s Proposed Findings of Fact: 1-5. Accepted. 6. Rejected as subordinate to Hearing Officer's findings. 7-13. Accepted. 14. Rejected as subordinate to Hearing Officer's findings. 15-20. Accepted. 21. Rejected as subordinate to Hearing Officer's findings. 22-23. Accepted. Respondent Department's Proposed Findings of Fact: 1. Rejected as subordinate to Hearing Officer's findings. 2-30. Accepted. COPIES FURNISHED: James T. Hendrick, Esquire MORGAN & HENDRICK, P.A. 317 Whitehead Street Key West, Florida 33040 H. Ray Allen, Esquire 618 Whitehead Street Key West, Florida 33040 Douglas H. MacLaughlin, Esquire Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32399-2400 Dale Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, Esquire General Counsel Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32399-2400

Florida Laws (5) 120.56120.57380.0552403.061403.087
# 3
COUNCIL OF CIVIC ASSOCIATION, INC. vs KORESHAN UNITY FOUNDATION, INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 98-000999 (1998)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Mar. 03, 1998 Number: 98-000999 Latest Update: Sep. 17, 1998

The Issue The issue is whether Respondent Koreshan Unity Foundation, Inc., is entitled to a environmental resource permit for the construction of a wooden footbridge over the Estero River east of U.S. Route 41 and authorization to obtain by easement a right to use sovereign submerged lands.

Findings Of Fact Respondent Koreshan Unity Foundation, Inc. (Koreshan) is a not-for-profit corporation dedicated to the preservation of the Koreshan heritage. Koreshan derives its heritage from a largely self-sufficient community that occupied land in south Lee County. For several years, Koreshan has owned a parcel of 14.56 acres at the southeast corner of U.S. Route 41 and the Estero River. This parcel is bounded on the south by Corkscrew Road and contains an amphitheater and historical house, midway between the river and Corkscrew Road. The south end of this parcel contains a museum and parking area with access to Corkscrew Road. The approximate dimensions of the 14.56-acre parcel are 544 feet along the river, 496 feet along Corkscrew Road, and about 1273 feet along the west and the east property lines. The west property line is U.S. Route 41. The right-of-way for U.S. Route 41 is wider at the southern two-thirds of the parcel than the northern one-third of the parcel. A sidewalk runs on the east side of U.S. Route 41 from north of the river, across the U.S. Route 41 bridge, along the west boundary of Koreshan's property, at least to an entrance near the middle of the 14.56-acre parcel. In October 1996, Koreshan acquired 8.5 acres of land at the northeast corner of the U.S. Route 41 and the river. The purpose of the acquisition was to provide parking for persons coming to Koreshan-sponsored events, such as music performances, at the 14.56-acre site. Koreshan rents a small portion of this northerly parcel to a canoe-rental business, which operates where the bridge and river meet. To assist their visitors-some of whom are elderly and disabled--in gaining access to the 14.56-acre site, on November 26, 1996, Koreshan filed an application for a permit and authorization to construct a wooden footbridge across the Estero River about 315 feet east of the U.S. Route 41 bridge. The source of the Estero River is to the east of the U.S. Route 41 bridge and the location of the proposed bridge. After passing under the U.S. Route 41 bridge, the river runs along the Koreshan state park, which is a short distance east of U.S. Route 41, before it empties into the Gulf of Mexico at Estero Bay, which is a state aquatic preserve. The portion of the river at the site of the proposed bridge is an Outstanding Florida Waterway (OFW) and a Class III water. The river is popular with canoeists and kayakers. Persons may rent canoes and kayaks at the canoe rental business operating on the 8.5-acre parcel or the Koreshan state park. Although most canoeists and kayakers proceed downstream toward the bay, a significant number go upstream past the U.S. Route 41 bridge. Upstream of the bridge, the river narrows considerably. Tidal currents reach upstream of the U.S. Route 41 bridge. At certain tides or in strong winds, navigating a canoe or kayak in this area of the river can be moderately difficult. Even experienced canoeists or kayakers may have trouble maintaining a steady course in this part of the river. Less experienced canoeists or kayakers more often have trouble staying on course and avoiding other boats, the shore, vegetation extending from the water or shoreline, or even the relatively widely spaced supports of the U.S. Route 41 bridge pilings, which are about 30 feet apart. Mean high water is at 1.11 feet National Geodetic Vertical Datum. The deck of the proposed footbridge would be 9 feet, 6 inches wide from rail to rail and 16 feet wide in total. The proposed footbridge would extend about 180 feet, spanning 84 feet of water from shore to shore. The bridge- ends would each be about 50 feet and would each slope at a rate of 1:12. The proposed footbridge would rest on nine pilings: four in the uplands and five in the submerged bottom. The elevation of the bottom of the footbridge from the water surface, at mean high water, would be 8 feet, 8 inches. The distance between the centers of the pilings would be 14 feet, and each piling would be of a minimum diameter of 8 inches. According to a special permit condition, the pilings would be treated with chromated copper arsenate, as a preservative, but they would be wrapped in impermeable plastic or PVC sleeves so as, in the words of the proposed permit, "to reduce the leaching of deleterious substances from the pilings." The proposed permit requires that the sleeves shall be installed from at least 6 inches below the level of the substrate to at least 1 foot above the seasonal highwater line and shall be maintained over the life of the facility. The proposed permit also requires that the footbridge be limited to pedestrian traffic only, except for wheelchairs. The permit requires the applicant to install concrete-filled steel posts adjacent to the bridge to prevent vehicles from using the bridge. The proposed permit requires that Koreshan grant a conservation easement for the entire riverbank running along both shorelines of Koreshan's two parcels, except for the dock and boat ramp used by the canoe-rental business. The proposed permit also requires Koreshan to plant leather fern or other wetland species on three-foot centers along the river banks along both banks for a distance of 30 feet. The proposed permit states that the project shall comply with all applicable water quality standards, including the antidegradation permitting requirements of Rule 62-4.242, Florida Administrative Code. Respondents did not raise standing as an affirmative defense. It appears that Petitioners or, in the case of corporate Petitioners, members and officers all live in the area of the Estero River and use the river regularly. For instance, Petitioner Dorothy McNeill resides one mile south of the proposed bridge on a canal leading to the Estero River, which she uses frequently. She is the president and treasurer of Petitioner Estero Conservancy, whose mission is to preserve the Estero River in its natural state. Petitioner Ellen W. Peterson resides on Corkscrew Road, 300-400 feet from the proposed footbridge. For 26 years, she has paddled the river several times weekly, usually upstream because it is prettier. She formerly canoed, but now kayaks. The record is devoid of evidence of the water- quality criteria for the Estero River at the time of its designation as an OFW or 1995, which is the year prior to the subject application. Koreshan has not provided reasonable assurance that the proposed footbridge would not adversely affect the water quality of the Estero River. Although the site of the proposed footbridge is devoid of bottom vegetation and there is no suggestion that this is anything but a natural condition for this part of the riverbottom, there is evidence that the proposed footbridge would adversely affect the water quality in two respects: turbidity caused by the pilings and leaching from the chromated copper arsenate applied to the pilings. The turbidity is probably the greater threat to water quality because it would be a permanent factor commencing with the completion of the installation of the pilings. The leaching of the heavy metals forming the toxic preservative impregnated into the pilings is probable due to two factors: damage to the PVC liner from collisions with inexperienced boaters and high-water conditions that exceed 1 foot over mean high water and, thus, the top of the liner. Both of these factors are exacerbated by flooding, which is addressed below. Koreshan also has failed to provide reasonable assurance that the proposed footbridge is clearly in the public interest under the seven criteria. The proposed footbridge would adversely affect the public health, safety, or welfare and the property of others through exacerbated flooding. South Lee County experienced serious flooding in 1995. In response, Lee County and the South Florida Water Management District have attempted to improve the capacity of natural flowways, in part by clearing rivers of snags and other impediments to flow, including, in the case of the Imperial River, a bridge. One important experience learned from the 1995 floods was to eliminate, where possible, structures in the river, such as snags and pilings, that collect debris in floodwaters and thereby decrease the drainage capacity of the waterway when drainage capacity is most needed. Longer term, the South Florida Water Management District is considering means by which to redirect stormwater from the Imperial River drainage to the Estero River drainage. The addition of five pilings (more as the river rose) would exacerbate flooding. On this basis alone, Koreshan has failed to provide reasonable assurance. Additionally, though, the HEC II model output offered by Koreshan does not consider flooding based on out-of-banks flows, but only on the basis of roadway flows. In other words, any assurances as to flooding in the design storm are assurances only that U.S. Route 41 will not be flooded, not that the lower surrounding land will not be flooded. Koreshan failed to provide reasonable assurance that the proposed activity would not adversely affect the conservation of fish and wildlife, for the reasons already stated with respect to water quality. Koreshan failed to provide reasonable assurance that the proposed activity would not adversely affect navigation or the flow of water. The flow of water is addressed above. Navigation is best addressed together with the next criterion: whether the proposed activity would adversely affect fishing or recreational values or marine productivity in the vicinity of the activity. Despite the presence of only two public launch sites, boating is popular on the Estero River. Reflective of the population growth of Collier County to the south and the area of Lee County to the north, the number of boaters on the Estero River has grown steadily over the years. The canoe- rental business located on the 8.5-acre parcel rented canoes or kayaks to over 10,000 persons in 1996. Many other persons launched their canoes or kayaks for free from this site and the nearby state park. Lee County businesses derive $800,000,000 annually from tourism with ecotourism a growing component of this industry. The Estero River is an important feature of this industry, and the aquatic preserve at the mouth of the river and the state park just downstream from the proposed footbridge provide substantial protection to the scenic and environmental values that drive recreational interest in the river. It is unnecessary to consider the aesthetic effect of a footbridge spanning one of the more attractive segments of the Estero River. The proposed footbridge and its five pilings effectively divide the river into six segments of no more than 14 feet each. This fact alone diminishes the recreational value of the river for the many canoeists and kayakers who cannot reliably navigate the U.S. Route 41 bridge pilings, which are more than twice as far apart. As to the remaining criteria, the proposed footbridge would be permanent and the condition and relative value of functions being performed by areas affected by the proposed activity is high. There is conflicting evidence as to whether the proposed footbridge would adversely affect the remnants of an historic dock, but it is unnecessary to resolve this conflict. The mitigation proposed by Koreshan does not address the deficiencies inherent in the proposed activity.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order dismissing the petition of Petitioner Council of Civic Associations, Inc., and denying the application of Respondent Koreshan Unity Foundation, Inc., for an environmental resource permit and authorization to obtain an easement for the use of sovereign land. DONE AND ENTERED this 3rd day of August, 1998, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of August, 1998. COPIES FURNISHED: Kathy Malone Vice President and Treasurer Council of Civic Associations, Inc. Post Office Box 919 Estero, Florida 33919-0919 Reginald McNeill Dorothy McNeill, President Estero Conservancy, Inc. 26000 Park Place Estero, Florida 33928 Mark E. Ebelini Humphrey & Knott, P.A. 1625 Hendry Street, Suite 301 Fort Myers, Florida 33901 Phyllis Stanley, President 12713-3 McGregor Boulevard Fort Myers, Florida 33919 Cathy S. Reiman Cummings & Lockwood Post Office Box 413032 Naples, Florida 34101-3032 Francine M. Ffolkes Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kathy Carter, Agency Clerk Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 F. Perry Odom, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (9) 120.52120.57120.68253.77267.061373.4136373.414373.421403.031 Florida Administrative Code (8) 18-21.00318-21.00418-21.0040118-21.00518-21.005162-302.20062-302.70062-4.242
# 4
COASTAL ENVIRONMENTAL SOCIETY, INC., AND ST. JOHNS PRESERVATION ASSOCIATION, INC. vs. GATE PETROLEUM COMPANY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-001939 (1989)
Division of Administrative Hearings, Florida Number: 89-001939 Latest Update: Oct. 11, 1989

The Issue The issues to be resolved in this proceeding concern whether the Respondent Gate Petroleum Company (Gate) has provided reasonable assurances that Water Quality Standards will not be violated by the proposed modification of Gate's dredge and fill permit No. 160462149 and whether Gate has provided reasonable assurances that the proposed modification of that permit will not be contrary to the public interest, nor be the occasion of adverse cumulative impacts to water quality or public interest considerations so as to make this project contrary to the public interest.

Findings Of Fact The Respondent Gate Petroleum Company, by and through its wholly-owned subsidiary, Gate Maritime Properties, Inc., proposes to construct a ship- berthing facility for two ships adjacent to Blount Island Channel, along the southeastern portion of Blount Island, in the St. Johns River, in Duval County, Florida. The proposed facility would provide for the berthing of two ships of the United States Navy Military Sea-Lift Command in conjunction with the mission of the Navy's Rapid Deployment Force. The proposed facility would be located along the southeasterly portion of "Cut A" of the Blount Island Channel and will consist of a "T-head Pier", a breasting dolphin and cat walk and two mooring dolphins. The pier would be connected to the land by an approach trestle. The facility involved will be constructed by the insertion of concrete pilings into the bottom of the Blount Island Channel and in the adjacent upland, which would support concrete decks and caps. Removal of dredged material will be necessary to accomplish the project and will be performed by a floating hydraulic dredge with associated "Cutter Head." The resulting dredged material would be disposed of in a diked spoil area on either Blount Island or at the Dayson Spoil Site adjacent to the mouth of Clapboard Creek. The Respondent Gate currently holds a DER dredge and fill permit, No. 160462149, authorizing the removal of approximately 3.4 million cubic yards of dredged spoil and the installation of an associated 5,000 feet of shoreline bulkhead. The proposed installation of the pier and mooring facilities would result in a modification of that permit so that approximately 1,000 feet of shoreline bulkhead and most of the related dredging will be unnecessary and not performed. Instead, approximately 7,100 cubic yards of dredging would be necessary, without the necessity for bulkheading. The remaining shoreline bulkhead and dredging authorized under the above permit would be rendered unnecessary and replaced by the addition of two additional T-head piers and associated dredging at some indefinite time in the future. The additional piers and dredging are not involved in this permit modification application and are not before the Hearing Officer at this time. The Blount Island Channel of the St. Johns River, the St. Johns River and Clapboard Creek are classified as Class III surface waters of the state pursuant to Sections 17-3.081 and 17-3.121, Florida Administrative Code. It has been established by stipulation of the parties that the proposed modification of the dredge and fill permit will not adversely affect navigation nor the flow of water in the Class III state waters involved. It is also stipulated that the proposed modification will not adversely affect historical and archaeological resources pursuant to Section 267.061, Florida Statutes. It is stipulated as well that the discharge of effluent from the Dayson spoil site will not violate water quality standards at the point of discharge in the Fulton-Dames Point Cut. On March 22, 1989, the Florida Department of Environmental Regulation issued its intent to approve the proposed permit modification so as to allow the elimination of the previous requirement in the permit to monitor for copper at the site of the effluent discharge; the relocation of the Blount Island spoil site effluent discharge and the construction of a T-head pier on the southeast side of Blount Island adjacent to the Blount Island Channel. The Department did not initially grant the request to relocate the Dayson spoil site effluent discharge from the Corps of Engineer Channel (Dames Point Cut) to the mouth of Clapboard Creek. On January 31, 1986, Gate was issued permit No. 160462149, pursuant to Chapters 403 and 253, Florida Statutes, with an expiration date of January 31, 1991. It authorizes the dredging and filling on and adjacent to Blount Island referenced above. The permit authorizes those operations in two phases, consisting of new dredging of approximately 300,000 cubic yards in the existing slipway and test area to obtain a project depth of 40.2 feet mean low water. Maintenance dredging was authorized in the amount of approximately 1,850,000 cubic yards in the slipway to maintain the above-noted project depth. New dredging of no more than 3 million cubic yards from the northeastern and southern margins of Blount Island to a depth of 38 feet mean low water (MLW) and 20 feet MLW on the northeastern and southern portions of Blount Island respectively, with attendant maintenance dredging, was authorized. The permit also allowed he construction of shoreline bulkheads along the eastern and southern margins of Blount Island. That 1986 permit also required disposal of dredged material from both phases of the project into diked areas on Blount Island and the existing diked off-site disposal area known as the Dayson Site, near the mouth of Clapboard Creek. Effluent from both sites was to be discharged to the Fulton-Dames Point Cut. Effluent from the Dayson site was to be discharged to the Fulton-Dames Point Cut or routed by pipeline to the Blount Island disposal site for additional treatment prior to discharge. All dredging under the 1986 permit was to be done via a suction, cutter-head dredge apparatus, with the speed of the cutter-head to be controlled so as to prevent excessive turbidity; and with all dredged material to be placed in diked areas, with the effluent discharge being conducted over adjustable weirs. The dredging of the approximately 7,100 cubic yards of material associated with the modification application at issue will be performed with the same type of equipment. Both spoil disposal sites have sufficient capacity for disposal of the material involved with the construction of the T-head pier. The effluent or "de-watering water" generated from the disposal of the dredged material at the Dayson on site will be discharged through a pipe under the St. Johns River to a point near the confluence of the Dames Point Cut and the Old River Channel. That material will consist of approximately 10 percent dredged solid material and 90 percent water. The Dayson disposal site is surrounded by dikes 24 feet high and 120 feet wide at their base. They are so constructed that there will be no discharge of effluent from the Dayson disposal site to Clapboard Creek. Since 1974, over four and one-half million cubic yards of material have been disposed of at the Days on site without any violation of state water quality standards in the creek or the adjacent salt marsh. The entire 7,100 cubic yards of dredged material, together with related water could be placed in the Dayson disposal site without causing any discharge. Gate Maritime Properties, Inc. has a five-year lease agreement with Leadermar, Inc. which will operate the T-head pier as a berthing facility for the two ships. The lease was scheduled to commence July 22, 1989. Under the terms of the contract awarded by the Navy to Leadermar, Inc., Gate, or its lessee, is required to maintain a 110 foot, safe working area surrounding the vessels for operation of tugs, lighterage vessels and fendering operations. The contract with the Navy does not require, however, that the safe working area be maintained at a depth of minus 32 feet "mean lower low water" as shown by Gate Exhibit 6 in evidence. 1/ Given the findings made infra., concerning the lack of adverse water quality or public interest impacts caused by the dredging, and the paucity of any attendant suspension of bottom materials in the operation of the ships to be berthed at the proposed facility, the issue of whether the contract with the Navy requires a depth of minus 32 feet "mean low water" or "mean low low water", a reputed difference of 1.03 inches according to the rebuttal exhibit of Respondent Gate, neither Gate's position nor the Navy's reputed position regarding this apparent contractual dispute item, if carried out, would have any adverse water quality or public interest impact in the context referenced in these findings of fact and conclusions of law. The fact remains that Gate has applied for authority to recede from the massive dredging project presently authorized in the existing permit, to stipulate by this modification application that it only seeks to dredge 7,100 cubic yards of material in the area involved. Based upon the depth established by the marine survey conducted by Bennett, Wattels and Associates, there will be an adequate safe working area for tug boats, fuel barges and lighterage vessels, as well as the ships themselves, for operations involving the berthing facilities. See Gate Exhibit 5 in evidence. If the requested modification is granted, Gate will not dredge more than 7,100 cubic yards of material for construction of the pier and related facilities and in order to provide a safe working area as required under Leadermars contract with the Navy. Indeed the amount of material to be dredged for the construction and operation of the T-head pier was based upon the above- referenced Marine survey, unrefuted evidence in this record. The volume of material was calculated by using the Marine Survey depths and the "average end area method," a widely accepted method of such calculation in the marine engineering and construction field. Further, Gate adduced the only substantial evidence in this record concerning the issue of the amount of dredging involved or the extent of the dredged area, as that relates to the "safe working area" and other issues. Water Quality Gates' consulting experts performed various chemical and sediment analyses in the project area in order to establish a general composition of bottom sediments and to establish the likelihood of suspension of any toxic substances or pollutants in those sediments as a result of the dredging operation or the operation of the ships and berthing facilities. Those analyses, and their results, in evidence in this record, were unrefuted. The bottom sediments in the vicinity of the project area are predominantly fine sand with small fractions of silt. In general, the dredged material is most likely to be free from chemical or biological pollutants where it is composed of sand, gravel or other naturally occurring inert materials, as opposed to large percentages of organic materials, which were not shown to exist in the vicinity of the project site. Based upon the characteristics of the bottom sediments in the project area, there will be no re-entrainment of toxins or pollutants which night presently be sequestered in the sediments due to construction, dredging operations or the operations of the berthing facility and ships involved. An elutriate test was performed to predict the effect on water quality from temporary suspension of the bottom sediments during the dredging operation itself. Elutriate testing is a widely recognized, conservative estimate of contaminant releases, caused by dredging, into a water column. The parameters tested for are those specified in the Department's rules for Class III waters and include cyanide, mercury, silver cadmium, selenium, barium, beryllium, nitrogen, (unionized NH3, NO2, total TKN), fluoride, copper, iron, nickel, zinc, aluminum, pesticides, herbicides and PCBs (polychlorinated biphenyls). The elutriate test results did not reveal any excess ion of any of these parameters in terms of the state water quality standards or as to prevailing natural background levels. There are no PCBs, hydrocarbons, heavy metals or pesticides shown to be sequestered in the bottom sediments of the Blount Island Channel in the vicinity of the proposed project. The chemical analyses was performed on composite elutriate samples of sediments which came from the area of the T- head pier location and the area north of the pier, where the propellers of the ships will be located and operated during test trials, after the ships are berthed at the site. Site specific chemical analyses and core borings were taken and compared with historical data or studies for these sites and found to be consistent with them. There is no likelihood of sequestered contaminants in the bottom sediments which would be released, with deleterious effect on water quality, as a result of the action of the dredge equipment or the operation of the ships after the facility is installed. Cutter-head, hydraulic pipeline dredges are not significant generators of turbidity. They are an efficient means of performing dredging and are designed to loosen and remove material from the bottom substrate, without disturbing or redistributing the dredged material around the dredge apparatus in the water column. The use of the hydraulic pipeline dredge will result in minimal water quality disturbance and any dredge-induced turbidity will be of a transitory, short-term nature. It would be localized in the immediate vicinity of the dredge's cutterhead in any event. Ambient water quality conditions can be expected to return to normal background levels in a matter of hours following cessation of the dredging activity. It is estimated by Gate's consultant witnesses that the dredging activity might be accomplished in approximately one day. It has thus been established that the relevant stage water quality standards will not be violated by the action of the dredging equipment and the dredging operation itself. Water Quality Impacts of Facility Operation The two ships of the military sealift command which are to be berthed at the proposed T-head pier are 948 feet in length and approximately 105 feet in beam. They are equipped with two main engines and two propellers. The propellers are 22 feet, 11 and 9/16 inches in diameter. The ships will be in what is known as "reserved operating status". The ships will go through a dry- docking procedure at a local shipyard approximately every two years for major overhauls, repairs and painting. Such maintenance work will not be performed at the project site. The ships will, however, undergo periodic "dock trials" while berthed at the facility. The dock trials will be conducted on a quarterly basis if the vessels have not been out on a mission in that quarter of the year. The dock trial procedure calls for the main propulsion powerplants of the ships to be put into operation and evaluated. Both main engines are tested under this procedure for approximately one hour, at ten revolutions per minute (rpm) ahead and astern. The tests are to be conducted by civilian personnel retained by the Navy or its contractor, with all appropriate safety precaution being taken. These include, but are not limited to, the manning of the bridge during tests by a master or chief mate and by rotating one engine ahead simultaneously with the other engine being rotated astern. The ships are also equipped with onboard, internal sewage treatment plants so as to prevent the discharge of pollutants to state waters. Only routine maintenance or repair work will be performed on the ships at the lay birth facility. The ships will be refueled at the facility from time to time with "bunker c" or diesel fuel brought in by barges. The barges will be conveyed by tugboats of no more than 16 feet draft. The fueling operation will be governed by the U.S. Coast Guard regulations and are performed by Coast Guard certified and licensed personnel. Dr. Neal Boehnke was accepted as an expert in the field of chemical analysis of water and testified on behalf of the Petitioner. In his opinion, water quality in the facility of the proposed project is poor and may contain elevated hydrocarbon levels. His opinions, however, are based upon 1982 and 1983 reports of sampling results allegedly obtained by the City of Jacksonville Bioenvironmental Services Division and the DER, as well as the study entitled "Survey of Hydrocarbons and the Lower St. Johns River in Jacksonville." These documents were not introduced into evidence. While it is true that an expert may base his opinion on facts and data made known to him in the normal course of his practice at or before trial and that those facts or data may be relied upon by him in formulating his opinions, it must be demonstrated that those facts and data are "of a type reasonably relied upon by experts in the subject to support the opinions expressed." See Section 90.704, Florida Statutes. In this proceeding, it was not established by competent evidence or testimony at hearing that the facts or data derived from these documents were of such a type as to be encompassed by this statutory section and thus they cannot serve as a legitimate basis for Dr. Boehnke's opinion. They otherwise constitute inadmissible hearsay, not sufficient to support a finding of fact on the water quality impacts from the proposed project and they do not constitute corroborative or explanatory hearsay related to any accepted, competent, substantial evidence in this record for purposes of the hearsay admissibility provision in Section 120.58, Florida Statutes. Therefore, Dr. Loehnke's opinion concerning alleged elevated levels of hydrocarbons in the water at the project site is not credited and is rejected. Dr. Allan Niedororda was accepted as an expert in the fields of oceanography, hydrology and hydrologic assessment. He conducted a study on the potential impact to water quality in the Blount Island Channel which might result from the dock trials to be carried out as a part of the routine maintenance and testing of the ships. His study evaluated the degree to which the propeller wash from the dock trials might entrain and transport bottom sediments, any related pollutants and the effect of this entrainment on water quality in the surrounding water column. His study consisted of field sampling and measurements of currents in the area, laboratory analysis and related data analysis. Bottom sediment samples from the project area were analyzed for particle size and grain size distribution according to standard, scientifically accepted procedures. The bottom sediments in the area of the project site are characterized by a sandy sediment of a fine to medium particle size characteristic. The bottom sediments largely consist of clean sand and small gravels, with some silt composition. The propeller wash which will be generated by the testing of the ships engines was computed to have a speed of approximately one half foot per second. Maximum speed will occur about three propeller diameters behind the plane of the propeller itself or about 72 feet behind the propellers. The bottom tip of the propeller with which the ships are equipped will be six feet off the bottom of the channel at low tide. At the point the propeller wash contacts the bottom, its speed will be approximately two tenths of a foot per second. Such a velocity will not be of sufficient force to produce such sheer stress on the bottom sediments as to entrain them or, that is, to displace them upward into the water column. Dr. Niedororda established that, even if the propeller wash is added to the natural velocity of the water currents at the project site, there would be no entrainment of the bottom sediments which he sampled in the project area. It has also been established that the routine, minor maintenance of the ships and dockage facilities involved in the permit application and the fueling and other operations associated with the berthing, testing, entry and egress of the ships from the proposed berthing facility will occasion no water quality violations, so long as appropriate Coast Guard regulations attendant to fueling and the prevention of the deposition of refuse and other wastes into the waters involved are observed. Any grant of the proposed permit modifications should be conditioned upon the strict observance of those regulations and procedures, especially with regard to the potential for spillage during fueling operations. Public Interest Standards Section 403.918(2), Florida Statutes provides that a permit may not be issued unless the applicant provides the department with reasonable assurances that the project is not contrary to the public interest. In determining whether this is the case, the Department must consider and balance the following criteria: Whether the project will adversely affect the public health safety or welfare or the property of others; Whether the project will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the project will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the project will adversely affect the fishing or recreational values or marine productivity in the vicinity of the project; Whether the project will be of a temporary or permanent nature; Whether the project will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061; The current condition and relative value of functions being performed by areas affected by the proposed activity. It has been established by stipulation that the project will not adversely affect navigation or the flow of water and that the project will not adversely affect significant historical or archaeological resources. Unrefuted evidence adduced by Gate and the Department have established that the project will not adversely affect the public, health, safety, welfare or the property of others, if the project is constructed, installed and operated as proposed in the modification application and as proved in this case. The conservation of fish and wildlife, including endangered or threatened species, or their habitats, as well as fishing and recreational values and marine productivity in the project area will not be adversely affected. No harmful erosion or shoaling will be caused by the installation or operation of the project facility. In this connection, Dr. A. Quinton White, a member of the Board of Directors of the Petitioner, C.E.S., acknowledged in his testimony that the Manatee Protection Plan and Manatee Watch Program proposed to be inaugurated by Gate will adequately protect any Manatees frequenting the area. Manatees are an endangered species, but it has been established that the permit modification proposed, if installed and operated, will not adversely affect the conservation of Manatees or their habitat. The Petitioner adduced no evidence on this issue or any of the public interest criteria enumerated above. The area at the project site is characterized by fairly firm consolidated bottom substrata, characterized by very few submerged grasses. Due to the sandy, hard bottom in the project vicinity, there is a paucity of marine grass upon which Manatee could feed. Consequently, Manatees do not and are not likely to frequent the area involved at the project site as that might reflect on the likelihood of their injury or destruction due to operation of the ships and any attendant vessels. Dr. Niedoroda established that the project and the attendant operations of the ships will not cause harmful erosion or shoaling and witness Gary Tourtellotte, testifying for Gate, established that the effects of the construction and operation of the T-head pier on the benthic community and marine productivity in the vicinity of the project will not induce any adverse effect on those elements of the public interest standards involved. The Petitioner offered no credible or credited evidence of equivalent value which could contradict the evidence adduced by Gate on this aspect of the public interest standards. It is true that dredging of the bottom substrata will temporarily eliminate the benthic community within the dredged area itself. It was established by expert testimony, however, that the benthic community will rapidly re-colonize itself with similar organisms to a naturally occurring degree within approximately 6-12 months. The benthic community in the project vicinity is of a low density nature, with a low diversity of organisms. Those organisms occurring in the project site area are estuarine, marine benthic species commonly associated with sandy or silty bottom substrates. Because the area to be dredged is quite small or approximately .25 acres, and the dredging operations will be of short duration, approximately one day, the dredging operations will not have a significant adverse effect on the benthic communities occurring in the project area or in the adjacent St. Johns River. The dredging associated with the project will likewise not have a significant long-term adverse impact on fisheries resources or marine productivity of the Blount Island Channel or the St. Johns River. This is because the area to be dredged is minimal in size and does not contain critical marine benthic habitat. The turbidity generated will be minimal because the sediments are predominantly coarse sands and gravels. Because of this, any turbidity occasioned by the installation and operation of the proposed facility will be very brief and not of a sufficient significance as to violate water quality standards. In view of the hydrologic analysis in evidence concerning propeller wash effects, the bottom sediments at the ship mooring area will not be entrained or suspended in the water column to any significant degree due to propeller operation of the ships. Thus the benthic community in the mooring area for the ships will not be disturbed due to currents created by the operation of the propellers. In a similar vein, it has been shown that the dredging and operation of the T-head pier and mooring facilities, including the attendant conduct of periodic dock trials and the entry and egress of the ships will not violate the water quality criteria for biological integrity. Indeed, the periodic dock trials are shown to have no impact on the benthic community, the fisheries or marine habitat involved at the project site. It was neither shown that the dredging associated with the construction of the pier and berthing facilities will have any adverse impact on fin fish or shellfish in the project area. It has been established that the project will be of a permanent nature, but it has not been established that the current condition and relative value of the functions being performed by the areas affected by the proposed activity in terms of their functions as productive marine habitat, as furnishing fishing or recreational values and the like, will be adversely affected by the proposed project and attendant activity. Deletion of Copper Monitoring Requirement The 1986 permit authorizing the removal of approximately 3.4 million yards of dredged material with attendant extensive bulkheading in the Blount Island Channel requires also that Gate Monitor for copper every two weeks during discharges at the downstream boundary of the mixing zone for each point of a effluent discharge. Effluent from both the Blount Island and Dayson Disposal Sites is discharged into the Fulton Dames Point Cut. The Petitioner has stipulated that the discharge of effluent from the Dayson Spoils Site will not violate any water quality standard at that discharge point. Elutriate testing and other analyses submitted in support of the permit modification request to delete the copper monitoring requirement in the present permit have shown that there will be no violation of water quality standards as to copper, or any of the other water quality parameters involved due to any re-suspenions of bottom sediment during dredging. There will be no violation of water quality standards for copper, caused by the deposition of spoil, consisting of those bottom sediments, and the draining of effluent from the spoils site into the Dames Point Cut. The Department has independently verified the data submitted by Gate as a result of this testing and it has been established that there is no occurrence of any man induced pollutants in the sediments at the project site which will be deposited in the spoil site, (from which the effluent will be disposed of in the Dames Point Cut) which represents any elevation over natural background levels. The sediments to be dredged from the berthing area are not distinguishable from naturally occurring sediments and the copper values in the sediments to be dredged are no higher than those naturally occurring throughout the area. Thus there will be no adverse impact on the water quality occasioned by discharge of the effluent from the spoil site to the Dames Point Cut area due to copper occurring in the sediments or as to any of the other pollutants enumerated above. Thus, there has been no demonstrated necessity to continue monitoring the effluent from the spoil site for copper. In this regard, the Petitioner presented no evidence at hearing concerning the issue of whether copper monitoring should be continued or not. Cumulative Impact Blount Island was created in the 1950's and 1960's by the filling of its area with spoil material during the U.S. Army Corps. of Engineers' construction of the Fulton-Dames Point Cut-Off Channel. Since that time, port facilities and an industrial complex have been constructed on Blount Island. It is one of the principle port facilities for the City of Jacksonville. Under the 1982 DER dredge and fill permit issued to Off-Shore Power Systems, and later transferred to Gate in 1986, the developed area of the island adjacent to the original St. Johns River Channel (the Blount Island Channel) was required to be bulk-headed and the channel dredged to -38 feet MLW. The amount of material to be dredged in the old channel of the St. Johns River for construction of the vertical shoreline bulk head totalled approximately 3.4 cubic yards. The T-head pier involved in this modification proceeding, if constructed, would replace 1,000 linear feet of that shoreline bulkhead authorized by the present permit and would substantially reduce the amount or quantity of material to be dredged. Construction of the T-head pier, instead of the permitted shoreline bulkhead, will minimize dredging and the environmental impact of the facility. Gate has elected to rescind its plans to construct the shoreline bulkhead along the eastern shore of Blount Island, as authorized under the existing dredge and fill permit. Gate instead intends to seek future modification of its existing dredge and fill permit to substitute at least 2 additional T-head piers for all of the shoreline bulk head authorized for the eastern shore of Blount Island. The construction of the additional T-head piers will require substantially less dredging than is authorized under the existing permit. Instead of the 3.4 million cubic yards of dredged material authorized under the existing permit, associated with installation of the shoreline bulkhead, the amount of material to be dredged, if indeed 2 additional T-head piers were applied-for and constructed, would amount to only 269,000 estimated cubic yards, as opposed to the originally authorized 3.4 million. Kevin Pope, the DER witness, established that there are no other projects in the area, or reasonably expected to be located in the project area, which would create impacts in addition to or cumulative with the proposed permit modification project so as to create adverse water quality impacts or which would make this project, because of cumulative impact, contrary to the public interest. There are no other dredge and fill projects in the area of the proposed T-head pier which would adversely impact the waters of the Blount Island Channel and the St. Johns River. The proposed modifications are shown not to likely cause any adverse environmental results and, in fact, will result in an environmental benefit as represented by the agreed-upon recession from the extensive dredging and bulkheading authorized by the present permit. No evidence was adduced by the Petitioner to contravene that adduced by Gate and the Department, which establishes the lack of any adverse cumulative impacts to be occasioned by the proposed project, both as to water quality standards and the public interest standards involved in this proceeding.

Recommendation Having considered the foregoing findings of fact, conclusions of law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is therefore, RECOMMENDED: That a Final Order be entered by the Department of Environmental Regulation approving the proposed modification to permit number 160462149 with the proviso that the conditions contained in the above findings of fact and conclusions of law be incorporated as specific conditions in the modified permit, including the additional condition agreed to at Final Hearing that the Manatee Protection Plan and Manatee Watch Program will be inaugurated and be incorporated as a specific condition in the modified permit. DONE and ENTERED this 11th of October, 1989, at Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of October, 1989.

Florida Laws (3) 120.57267.06190.704
# 6
DR. ROBERT B. TOBER vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 95-000159 (1995)
Division of Administrative Hearings, Florida Filed:Naples, Florida Jan. 13, 1995 Number: 95-000159 Latest Update: Jun. 23, 1995

Findings Of Fact By Joint Application for Works in the Waters of Florida filed June 22, 1994, Petitioner requested a permit to dredge about 500 square feet of uplands for a boatslip and to maintenance dredge 1700-1900 square feet in an adjacent canal, removing 125 cubic yards of material waterward of mean high water. The Application describes the work as including a vertical concrete seawall running 92 feet inside the boatslip, a cat walk from the boatslip to the canal, and a roof over the boatslip. A drawing attached to the Application depicts the proposed boatslip at the east end of the Petitioner's lot and with rounded corners to facilitate flushing. By Notice of Permit Denial executed October 24, 1994, Respondent advised that the permit was denied. The Notice states that water quality in the surrounding canal system is generally poor with low dissolved oxygen (DO) levels. The shoreline vegetation is primarily mangroves, which are tall but not robust. The proposed dredge area consists of a healthy littoral shelf with live oysters and shells. Based on the foregoing site description, the Notice denies the permit because of impacts to the conservation of fish and wildlife and marine productivity and a degradation of the current condition and relative value of the affected area. The Notice relates all of these factors to the loss of the mangroves and dredging of the adjacent canal bottom. The Notice adds that the project would have an adverse cumulative impact on water quality and public resources if similar projects were constructed. In the alternative, the Notice suggests that Petitioner eliminate the dredging into the uplands and canal and instead construct a boat shelter in the canal in an area of existing adequate water depth. By letter dated November 7, 1994, Petitioner challenged the denial. The letter states that Petitioner has maintained an environmentally productive shoreline consisting of mangroves, oysters, and rip rap, rather than concrete seawalls, as are found along the shoreline of most of his neighbors. The letter suggests that, if Petitioner followed Respondent's suggestion and built a slip in the canal, Petitioner would be permitted to do maintenance dredging in the artificial canal. The letter concludes that the maintenance dredging and shading of an over- the-water boathouse would have more impact on the environment than dredging uplands and a small access channel to the slip. Petitioner's residence is located in Aqualane Shores, which is an established residential subdivision located between Naples Bay on the east and the Gulf of Mexico on the west. Petitioner's lot is located about two-thirds of the distance down a long, relatively wide artificial canal known as Jamaica Channel. Jamaica Channel intersects Naples Bay to the east of Petitioner's property. Jamaica Channel is a Class III waterbody. Petitioner owns about 200 feet of shoreline at the corner of Jamaica Channel and a shorter, narrower canal. The entire area is heavily canalized and completely built-out with nearly exclusively single family residences. Most of the shoreline in the area is bulkheaded with concrete seawalls. Jamaica Channel was dredged in the early 1950s. Early riprap revetment crumbled into the water and in some areas became colonized by oysters, which supply food and filter impurities from water. Shoreline owners weary of repairing riprap installed vertical seawalls, thereby destroying the oyster beds and intertidal habitat. But much of the riprap adjacent to unbulkheaded shoreline eventually was stabilized by mangrove roots. The absence of concrete seawalls along Petitioner's shoreline has permitted a significant colony of oysters to populate the 25-foot littoral shelf running along Petitioner's shoreline. The oysters form a hemisphere, thickest at the middle of Petitioner's shoreline and narrowest at the east and west edges, narrowing to a width of as little as 6-10 feet. In recent years, Australian pines were removed from Petitioner's shoreline. As a result, mangrove seedlings have successfully occupied much of the shoreline. The proposed boatslip would be located at the east end of the shoreline where there is a natural gap in the mangroves. As a result, only three mangroves would have to be removed, and a relatively narrow band of oysters would be dredged and, as offered by Petitioner, relocated. The proposed dredging involves uplands and submerged bottom. As to the uplands, Petitioner intends to create a slope in the slip with the rear one to one and one-half feet shallower than the front, although this slope is not reflected on the Application. The purpose of the slope is to facilitate flushing. Petitioner evidently intends to dredge sufficient material to fill the rear of the slip with two feet of water at mean water and the front of the slip with three feet of water at mean water. The dredging in Jamaica Channel would involve an 18-20 foot wide path leading to the slip. Beyond the oysters, the bottom is fine sandy substrate with scattered rock. The relocation of oyster-covered rocks might be successful, if there are sufficient areas suitable for colonization that have not already been colonized. However, the dredged areas would not be recolonized due to their depths. Presently, the Application discloses level dredging down to an elevation of -5 NGVD. Petitioner's intent to slope the boatslip has been discussed above. Although Petitioner did not reveal a similar intent to slope the area dredged in Jamaica Channel, Petitioner's witness, Naples' Natural Resource Manager, testified that he would insist on similar sloping the entire length of the dredged area, so that the deepest area would be most waterward of the boatslip. If the dredged canal bottom were not sloped, Petitioner proposes removing about 4.25 feet of material about ten feet from shore, about 3.4 feet of material about 22 feet from shore, about 1.8 feet of material about 30 feet from shore, and about 0.5 feet of material about 40 feet from shore. Petitioner did reveal that the cross-section indicating a dredged depth of -5 feet applies only to the centerline of the dredge site, which would be tapered off to the east and west. The slope of the taper was not disclosed, but it is evident that the affected areas within 20 feet of the shoreline would be dredged at least two feet deeper and, in most areas, three feet deeper. The deepening of Jamaica Canal in the vicinity of the shoreline would not only eliminate existing oyster habitat, but would also eliminate habitat currently used by small fish. The deepening of Jamaica Channel in the vicinity of the shoreline would also impact water quality in the area. Water quality in Naples Bay and Jamaica Channel is poor and violates water quality standards for DO. Due to poor mixing of freshwater infusions and saltwater, DO levels deteriorate with depth. Where DO levels are probably adequate in the shallows around Petitioner's shoreline, the proposed dredging would likely result in depths at which violations could be expected to occur. Petitioner offers to install an aerator to introduce oxygen into the water. Ignoring the fact that the aerator was to operate only in the boatslip and not in the remainder of the dredged area, Petitioner did not show the effect on DO levels of this proposal. Even if the aerator had been shown to result in a net improvement in area DO levels, Petitioner also failed to show how the operation of the aerator would be guaranteed to extend indefinitely, or at least until the dredged areas were permitted to regain their pre-dredged depths. Petitioner argues that he could construct an over-the- water boathouse and maintenance dredge, and the resulting environmental impact would be greater. Several factors militate against this proposed alternative and thus preclude consideration of this alternative against the proposed project. Most significantly, the oysters have occupied the littoral shelf adjacent to Petitioner's shoreline for a period in excess of 20 years. There is considerable doubt as to whether Petitioner would be permitted to maintenance dredge under these and other circumstances. Respondent argues more persuasively the issue of cumulative impacts. There are about 350 residences in Aqualane Shores, of which only 150 have boatslips similar to that proposed by Petitioner. This raises the prospect of an additional 200 boatslips as a cumulative impact on water and biological resources.

Recommendation It is hereby RECOMMENDED that the Department of Environmental Protection enter a final order denying the application. ENTERED on May 26, 1995, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings on May 26, 1995. APPENDIX Rulings on Petitioner's Proposed Findings 1-2: adopted or adopted in substance. 3: rejected as irrelevant. 4-5 (first sentence): adopted or adopted in substance. 5 (remainder)-6: rejected as irrelevant. 7: rejected as recitation of evidence. 8: adopted or adopted in substance. 9: rejected as unsupported by the appropriate weight of the evidence. 10: rejected as unsupported by the appropriate weight of the evidence, irrelevant, and not findings of fact. 11-12 (first sentence): adopted or adopted in substance. 12 (remainder): rejected as recitation of evidence and as unsupported by the appropriate weight of the evidence. 13: rejected as unsupported by the appropriate weight of the evidence. Rulings on Respondent's Proposed Findings 1-20: adopted or adopted in substance. 21-25: rejected as unnecessary. 26-29: adopted or adopted in substance. 30: rejected as unnecessary. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Kenneth Plante, General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Miles L. Scofield Qualified Representative Turrell & Associates, Inc. 3584 Exchange Ave., Suite B Naples, FL 33942 Christine C. Stretesky Assistant General Counsel Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (2) 120.57373.414 Florida Administrative Code (1) 62-312.030
# 7
CONCERNED CITIZENS OF ORANGE LAKE AREA vs CELEBRITY VILLAGE RESORTS, INC., AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 91-002694 (1991)
Division of Administrative Hearings, Florida Filed:Ocala, Florida May 01, 1991 Number: 91-002694 Latest Update: Jun. 10, 1992

The Issue The ultimate issue is whether Celebrity Resorts, Inc., (Celebrity) is entitled to a Management and Storage of Surface Waters (MSSW) permit for a surface management system to serve its proposed development in Marion County, Florida.

Findings Of Fact PROPOSED PROJECT Celebrity is seeking a District MSSW permit to construct a surface water management system to serve a proposed recreation vehicle (RV) park. The facility is to be located in northern Marion County on the southern border of Orange Lake, an Outstanding Florida Water. The entire site is within the geographic boundaries of the District. The RV park is to be located on 75 acres of land, and is to contain 372 RV and "park model" sites, four bath houses, a clubhouse, and an expanded boathouse. There is a "break" in the watersheds of the Celebrity property caused by a ridge across the approximate center of the project site. The effect of this "break" is that approximately one-half of the property drains toward the lake while the approximate southerly half of the property drains into an independent depression creating a watershed separate from the lake. Parts of Marion County and Alachua county have been designated as Sensitive Karst Area Basin by the District. The project site is located in the designated area. The existing land use is open pasture. The property was previously used for citrus groves. STANDING Concerned Citizens of Orange Lake Area is an unincorporated group of approximately 76 individuals who want to prevent pollution of Orange Lake. Of the 76 members, three members were present and testified at the hearing. The members attending the hearing were an artist (Riley), a photographer (Suto), and a bass guide (Solomon). Ms. Suto testified that she lives about 1 to 1 1/2 miles from the site. Ms. Riley testified that she lives next door to Ms. Suto and determined that to be over two miles away from the site. Mr. Solomon testified that he lives on the southeast side of Orange Lake approximately 1 to 1 1/2 miles from the project site. No witness testified that any member has a property interest in the subject property. Of the members who testified, none use the subject property. There was no testimony that other members use the property. Twenty-six members wrote letters of concern to the District. Ms. Suto testified to the existence of high levels of lead in her well water. WATER QUANTITY The existing land use, pasture, was used to determine the pre- development peak rate and volume of discharge. The existing surface drainage of the 75-acre project site is divided into two basins. On the north side of the property, the surface water flows toward Orange Lake. This basin is designated on the plans, sheet 3 of 16, by a "2." The south portion of the property is contained within the landlocked drainage basin which is designated on the plans, sheet 3 of 16, by a "1." The post-development flow of surface water will be in the same direction as the pre-development flow. There are no proposed development plans or encroachments into the 100- year floodplain. Therefore, there is no increase in potential for damages to off-site property or persons caused by floodplain development or encroachment, retardance, acceleration, displacement, or diversion of surface waters. There is no reduction in natural storage areas and, in fact, the proposed project increases the natural storage on site. Drainage Basin 2 The District's criterion for systems discharging to basins with an outlet is that the post-development peak rate of discharge for the 25-year, 24- hour storm event shall not exceed the pre-development peak rate of discharge for the 25-year, 24-hour storm event. The District's criteria also require that the post-development volume of discharge not exceed the pre-development volume of discharge. The retention system which ultimately discharges to Orange Lake is designed to retain the entire 25-year, 24-hour storm event through the series of basins on site. The pre-development peak rate of discharge for the drainage basin which flows to the lake is 55 cubic feet per second (cfs) during the 25-year, 24-hour storm event. The post-development peak rate of discharge from drainage basin 2 is 4 cfs. The post-development peak rate of discharge is less than the pre- development peak rate of discharge. Runoff from each RV site will be collected in an individual, ten-inch- deep retention basin. Runoff from the road will be collected in roadside swales. Runoff from the clubhouse, country store, and associated parking lots will be conveyed to drainage retention area (DRA) No. 8. The individual retention basins have the capacity to retain the 25- year, 24-hour storm event without discharging. Any surface water discharges from the individual retention basins in Basins 2A, 2B, and 2C as designated on sheet 3 of 16 will flow to DRA Nos. 4, 5, and 7, respectively. In Basin 2D, runoff from the road and RV park model sites will flow to DRA No. 6. The discharge from DRA No. 6 in the 25-year, 24-hour storm will be zero (0) cfs. In larger storms, any discharge from DRA No. 6 will flow to DRA No. 7. In the event DRA No. 7 overflows, the runoff will flow to DRA No. 5. Basins 2G and 2F are located around two existing sinkholes which currently collect stormwater runoff. In the proposed project, Basins 2G and 2F continue to drain the same area as pre-development. However, additional impervious surfaces will be placed in the drainage area. For this reason, an additional three to five feet of clean fill will be placed in the bottom of each sinkhole for filtration purposes. Basins 2H and 2I are less than one acre and currently drain off site. Berms are proposed around the property line at the basin to keep the stormwater on site. Basins 2H and 2I retain 3/4 inch of runoff over the individual basin. The runoff from Basins 2E1 and 2E flows to DRA No. 8 via a drainage swale. DRA No. 8 will retain 3/4 inch of runoff from the drainage area and is an off-line retention basin. The DRA No. 8 is equipped with a diversion box which allows the 3/4 inch of runoff to enter the DRA and then diverts the runoff from larger storms around the DRA so that the treatment volume of runoff (3/4 inch) continues to be treated in DRA No. 8 and does not mix with and discharge from DRA No. 8 during larger storms. Drainage Basin 1 Drainage Basin 1 as designated on plan sheet 3 of 16 is a landlocked basin which does not discharge to Orange Lake. In Drainage Basin 1, as in Basin 2, the runoff from the RV sites flows to the individual retention basins which retain the 25-year, 96-hour storm event. The runoff from the road flows to swales. Overflow from the basins and swales flow to the DRAs. Drainage Basin 1 does not discharge during the 100- year, 24-hour or the 25-year, 24-hour storm event, pre-development or post- development Drainage Basin 1 is designed to retain the 100-year, 24-hour storm, which is an 11 inch storm event. Drainage Basin 1 is also designed to retain the 25-year, 96-hour storm event. The 25-year, 96-hour storm event is 143% of the 25-year, 24-hour storm event. WATER QUALITY Design Criteria The District's design criteria for water quality are set out in Section 40C-42.025, Florida Administrative Code. The District's retention criteria require that a proposed system have a treatment/pollution abatement volume of 1/2 inch of runoff from the site. For discharges to an OFW, the pollution abatement volume is increased by fifty percent. Therefore, the system must have the volume to retain 3/4 inch of runoff from the site. Each retention basin retains a minimum of 3/4 inch of runoff from the site. The District's criteria regarding quantity of water discharged require a larger volume of runoff to be retained than the District's criteria regarding quality. Therefore, the retention system exceeds the District's criteria regarding quality in order to meet the criteria regarding quantity. The District's retention criteria require that the basin recover the treatment volume within 72 hours. Most of the retention basins retain more than the required treatment volume of 3/4 inch, and most will also recover, or become dry, within 72 hours. The retention basins are capable of being effectively maintained in that the side slopes and bottom of the basins can easily accommodate mowing equipment. For erosion control, staked hay bales and silt screens will be utilized on site during construction to prevent the off-site transport of soil material. Following construction, the retention basins will be vegetated with sod to prevent erosion. The District's criteria require that facilities which receive stormwater runoff from areas with greater than fifty percent of impervious surface shall include a baffle or other device for preventing oil and grease from leaving the system. DRA Nos. 1, 4, 5, and 8 are equipped with an oil and grease removal device called a baffle. The baffle is an acceptable engineering design for the removal of oil and grease from stormwater in a retention basin. The facility operation is uncomplicated. If the individual basins did fill due to a storm event greater than the 25-year, 24-hour or the 25-year, 96- hour in the landlocked basin, they would simply overflow into a DRA. No structures are involved to prevent flooding in large storm events. Water Quality Impacts The individual retention basin at each RV site is considered off-line because it does not discharge in the 25-year, 24-hour storm event. DRA Nos. 1, 2, 3, 4, 5, 6, and 7 are considered off-line because they do not discharge during the design storm. DRA No. 8 is considered off-line because of the diversion box which provides for the retention of the treatment volume and diversion of the larger storms. Off-line retention systems generally show greater pollutant treatment efficiencies than other types of stormwater treatment. The first 1/2 inch of runoff or the "first flush" of rainfall contains ninety percent of the pollutants from the site. SURFACE WATER Utilizing information and methodologies generally accepted by experts in the field of water quality, the District analyzed and projected the average surface water and groundwater quality of the discharge from the surface water management system for the proposed project. No data on runoff concentrations currently exists for RV parks. This analysis was based on a review of existing data on untreated runoff concentrations from three multifamily developments and one highway study. Because data from studies of multifamily residential and highway projects was used, the District's estimates of the untreated runoff concentrations for this project are conservative in that the actual concentrations are probably less than estimated. The District's analysis of the average quality of the discharge from the proposed system was also based on projecting the treatment efficiencies associated with the system. This analysis was done by reviewing data from documented studies previously conducted to ascertain the treatment efficiency of retention methods of stormwater treatment. Generally, retention of the first 1/2 inch of runoff removes eighty percent of the pollutants. On this project, a treatment efficiency of ninety-five percent was assumed based on the fact that the system is off-line treatment and a minimum of 3/4 inch of runoff from the site will be retained in the basins prior to discharge. The expected average untreated runoff concentrations were then educed by the expected treatment efficiencies to project post-treatment water quality of the discharge from the proposed system. These numbers were then compared to Chapter 17-302, Florida Administrative Code, water quality standards for Class III water bodies, and ambient water quality in Orange Lake. Orange Lake is classified as an OFW. Therefore, the proposed project cannot be permitted if it will cause degradation of that water body. The background data or ambient water quality data for phosphorous and nitrogen was taken from the Orange Lake Biological Report by the Florida Game and Freshwater Fish Commission in 1986. The ambient water quality for the other parameters in Table 2 of District Exhibit 2 was computed using eight years of data from a District monitoring station on Orange Lake. The projected average concentration for each constituent in the discharge from the system is less than the ambient water quality of Orange Lake. Therefore, the proposed surface water discharge will not violate state water quality standards in waters of the state. The post-development pollutant loading rates should be equal to or better than the pollutant loading rates from the use of the property as citrus or pastureland because the runoff is being retained on site and treated before being discharged. GROUNDWATER Groundwater discharges were reviewed by assessing the type of soil below the retention basin and the distance to the water table. The soil on the site contains some organic matter which is beneficial for treatment purposes. Based on the borings submitted by Celebrity, the water table, if any, is five feet or more below the bottom of any proposed retention basin. Runoff in the basin will percolate through the soil. Nutrients such as nitrogen and phosphorus will be taken up by the vegetation in the bottom of the basins. Metals will bind to the soil material below the basin. Oils and greases will be broken down through microbial degradation into nontoxic material. Groundwater discharges from the proposed system will not violate any applicable state groundwater quality standards. These standards will be met within the first three feet below the treatment basins. The standards will also be met by the time the groundwater discharge moves to the edge of the zone of discharge which is at the property boundary. The discharge from the proposed Celebrity project will not cause or contribute to a violation of state water quality standards in the receiving waters. SINKHOLES Sinkholes may form on the site. Sinkholes that form will probably be "cover subsidence" sinkholes. Cover subsidence sinkholes are those in which a void below the surface fills with the soil from above, causing a depression in the ground surface. There are four relict sinkholes on site. They are cover subsidence sinkholes. The sinkhole nearest the lake has water in the bottom. Stormwater runoff is directed away from the sinkhole. Any water which enters the sinkhole from the land surface or above will enter from the sky. The District has proposed criteria for stormwater systems in designated Sensitive Karst Area Basins. Those criteria are that 1) the water in the basins shall be no deeper than ten feet deep; 2) there should be at least three feet of unconsolidated material between the bottom of the basin and the top of the water table; and 3) the basins should be fully vegetated. The District currently applies these criteria as policy. In this project, the basins are shallow, ranging from ten inches deep at the RV sites to 2 1/2 feet in the DRAs. The basins have at least three feet of unconsolidated material between the bottom of the basin and the top of the water table. In the soil borings performed by Celebrity, the water table was shown to exist between five and fifty feet below land surface. The proposed project design meets or exceeds the proposed criteria for Sensitive Karst Area Basins. The basins will be fully vegetated or sodded with grass. Lineations or lineaments are solution features which may indicate a fracture of the underlying limestone. There may be a lineament on the site. There are other sinkholes in the area. If a cover subsidence sinkhole develops in an individual retention basin or DRA, stormwater, if any, will seep or percolate through the several feet of soil prior to reaching an aquifer. Most of the pollutants in the retention basin will meet groundwater quality standards prior to percolation and further treatment in the soil. OPERATION AND MAINTENANCE Special conditions Nos. 13, 14, and 15 on the permit will require Celebrity to inspect the system monthly for sinkhole development. If a sinkhole develops, Celebrity must notify the District within 48 hours of its discovery. Celebrity must submit a detailed repair plan within 30 days for written approval by the District. Celebrity proposes to repair any sinkholes that develop by a District- approved method. Celebrity Resorts, Inc., is a legally established corporation registered in Delaware and owns the subject property. Celebrity does not intend to subdivide the property but to sell memberships to use the property on a time-share basis. Celebrity will administratively operate the site by employing a park manager who will remain on the property 24 hours a day. If any problems occur with the basins, either he or his designee will be on site to respond quickly to the situation. The park manager will have a full-time maintenance staff which will operate the park. Celebrity will financially operate and maintain the proposed system using funds currently raised and in the future by membership fees. Celebrity is a publicly held corporation. Funds raised from the sale of stock, approximately $3,500,000, have paid for legal and administrative fees as well as the land purchase. Approximately $400,000 has been reserved to operate the facility. It will cost approximately $15,000 per month to run the park. Memberships will be sold for $300 per year. Part of the membership fees will go toward the general maintenance of the site. Maintenance of the proposed system will include regular mowing and monthly inspection for sinkholes and repair if necessary. WETLANDS IMPACTS OF THE PROJECT The property contains waters of the state wetlands and isolated wetlands. The waters of the state wetlands are those along the shore of Orange Lake. One isolated wetland exists on site in the sinkhole which is closest to the lake. The sinkhole has standing water in which lemna, or duckweed, is growing. Duckweed is a listed plant species in Section 16.1.1(2) of the Handbook. No construction is proposed in either the waters of the state wetlands or the isolated wetland. The District criteria require the review of impacts to off-site aquatic and wetland dependent species relative to the functions currently provided by the wetlands to these types of fish and wildlife. Since there will be no construction in the wetlands, there will be no impacts to the habitat, abundance and diversity, or food sources of off-site aquatic and wetland dependent species from this proposed project. No threatened or endangered aquatic and wetland dependent species were observed on site. The proposed permit application will not adversely affect natural resources, fish, or wildlife in a manner which is inconsistent with the District criteria. The proposed permit application will not adversely affect hydrologically-related environmental functions in a manner which is inconsistent with the District criteria.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the petition filed by Concerned Citizens of Orange Lake Area be dismissed for lack of standing and that Celebrity Resorts, Inc., be issued a MSSW permit for its system as designed and proposed. DONE and ENTERED this 19th day of July, 1991, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of July, 1991. APPENDIX TO THE RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Concerned Citizens of Orange Lake Area 1. Proposed findings of fact 1-6 are subordinate to the facts actually found in this Recommended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Celebrity Resorts, Inc. 1. Proposed findings of fact 1-38 are subordinate to the facts actually found in this Recommended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, St. Johns River Water Management District 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1&2(1); 3-7(4-7); 8-20(8- 20); 21(2); 22-31(21-30); 32(16); and 33-107(31-105). COPIES FURNISHED: Crawford Solomon Qualified Representative Concerned Citizens of Orange Lake Post Office Box 481 Citra, FL 32681 William L. Townsend, Jr. Attorney at Law Post Office Box 250 Palatka, FL 32178-0250 Nancy B. Barnard Attorney at Law St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429 Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429

Florida Laws (3) 120.52120.56120.57 Florida Administrative Code (1) 40C-42.025
# 8
MARTIN COUNTY AND ST. LUCIE COUNTY vs ALL ABOARD FLORIDA - OPERATIONS, LLC; FLORIDA EAST COAST RAILWAY, LLC; AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 16-005718 (2016)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 30, 2016 Number: 16-005718 Latest Update: Nov. 16, 2017

The Issue The issues to be determined in these consolidated cases are whether All Aboard Florida – Operations, LLC (“the Applicant”), and Florida East Coast Railway, LLC (“FECR”), are entitled to an Environmental Resource Permit Modification authorizing the construction of a stormwater management system and related activities to serve railway facilities, and a verification of exemption for work to be done at 23 roadway crossings (collectively referred to as “the project”).

Findings Of Fact The Parties Petitioners Martin County and St. Lucie County are political subdivisions of the State of Florida. Petitioners have substantial interests that could be affected by the District’s proposed authorizations. Intervenor Town of St. Lucie Village is a political subdivision of the State of Florida. Intervenor has substantial interests that could be affected by the District’s proposed authorizations. The Applicant, All Aboard Florida – Operations, LLC, is a Delaware limited liability company based in Miami. All Aboard Florida is part of a group of corporate entities formed for the principal purpose of developing and operating express passenger train service in Florida. Co-applicant Florida East Coast Railway, LLC, is a Florida limited liability company based in Jacksonville. FECR owns the existing railway corridor the passenger train service will use between Miami and Cocoa. South Florida Water Management District is a regional agency granted powers and assigned duties under chapter 373, part IV, Florida Statutes, including powers and duties related to the regulation of construction activities in wetlands. The proposed activities are within the boundaries of the District. Background The objective of the All Aboard Florida Project is to establish express passenger train service connecting four large urban areas: Miami, Fort Lauderdale, West Palm Beach, and Orlando. Most of the passenger service route, including the portion which will pass through Martin County and St. Lucie County, will use an existing railroad right-of-way used since the late 1800s. The FECR rail corridor runs along Florida’s east coast from Miami to Jacksonville. It supported passenger and freight operations on shared double mainline tracks from 1895 to 1968. The passenger service was terminated in 1968 and portions of the double track and certain bridge structures were removed. The freight service continued and remains in operation today. The passenger service will use the FECR right-of-way from Miami to Cocoa and then turn west on a new segment to be constructed from Cocoa to Orlando. The railway corridor will be operated as a joint facility, with passenger and freight trains sharing the double mainline tracks. The Applicant is upgrading the portion of the corridor between Miami and Cocoa by, among other things, replacing existing railroad ties and tracks, reinstalling double mainline tracks, and improving grade crossings. The Applicant is also installing Positive Train Control systems which provide integrated command and control of passenger and freight train movements and allow the trains to be directed and stopped remotely or automatically in the event of operator error or disability, or an obstruction on the track. The All Aboard Florida Project is being developed in two phases, Phase I extends from Miami to West Palm Beach, and Phase II from West Palm Beach to Orlando. This proceeding involves a segment within Phase II, known as Segment D09, which runs from just north of West Palm Beach to the northern boundary of St. Lucie County. The railway corridor in Segment D09 passes through Jonathan Dickinson State Park in Martin County and the Savannas Preserve State Park, parts of which are in both Martin County and St. Lucie County. Surface waters within these state parks are Outstanding Florida Waters (“OFWs”). The railway in Segment D09 also passes over the St. Lucie River using a bridge that can be opened to allow boats to pass. The Applicant plans to run 16 round trips per day between Miami and Orlando, which is about one train an hour in each direction, starting early in the morning and continuing to mid-evening. In 2013, the District issued the Applicant an exemption under section 373.406(6), which exempts activities having only minimal or insignificant adverse impacts on water resources. The 2013 exemption covers proposed work in approximately 48 of the 65 miles which make up Segment D09, and includes replacement of existing tracks and re-establishment of a second set of mainline tracks where they were historically located. The 2013 exemption covers all but 24 of the roadway crossings within Segment D09 where work is to be done in connection with the All Aboard Florida Project. In 2015, the District issued the Applicant a general permit under rule 62-330.401, which authorizes activities that are expected to cause minimal adverse impacts to water resources, for the installation of fiber optic cable along the rail bed within Segment D09. The 2013 exemption and 2015 general permit were not challenged and became final agency action. The Proposed Agency Actions The ERP Modification covers work to be done in approximately 17 of the 65 miles which make up Segment D09. The work will consist primarily of replacing existing tracks, installing new tracks, making curve modifications in some locations to accommodate faster trains, culvert modifications, and work on some fixed bridge crossings over non-navigable waters. The 2017 Exemption at issue in this proceeding covers improvements to 23 of the 24 roadway crossings that were not covered by the 2013 exemption. Proposed improvements at Southeast Florida Street in Stuart will be permitted separately. The improvements covered by the 2017 Exemption include upgrading existing safety gates and signals; installing curbs, guardrails, and sidewalks; resurfacing some existing paved surfaces; and adding some new paving. Petitioners argue that, because the District’s staff report for the ERP Modification states that the ERP does not cover work at roadway crossings, track work at roadway crossings has not been authorized. However, the staff report was referring to the roadway improvements that are described in the 2017 Exemption. The proposed track work at the roadway crossings was described in the ERP application and was reviewed and authorized by the District in the ERP Modification. “Segmentation” Petitioners claim it was improper for the District to separately review and authorize the proposed activities covered by the 2013 exemption, the 2015 general permit, the ERP Modification, and the 2017 Exemption. Petitioners contend that, as a consequence of this “segmentation” of the project, the District approved “roads to nowhere,” by which Petitioners mean that these activities do not have independent functionality. Petitioners’ argument is based on section 1.5.2 of the Applicant’s Handbook, Volume 1,1/ which states that applications to construct phases of a project can only be considered when each phase can be constructed, operated, and maintained totally independent of future phases. However, the activities authorized by the four agency actions are not phases of a project. They are all parts of Phase II of the All Aboard Florida Project, which is the passenger railway from West Palm Beach to Orlando. Section 1.5.2 is not interpreted or applied by the District as a prohibition against separate review and approval of related activities when they qualify under the District’s rules for exemptions, general permits, and ERPs. Much of Phase II is outside the District’s geographic boundaries and, therefore, beyond its regulatory jurisdiction. The District can only review and regulate a portion of Phase II. The District is unable to review this portion as a stand-alone railway project that can function independently from other project parts. The Proposed Stormwater Management System Where the Applicant is replacing existing tracks or re- establishing a second set of tracks, it will be laying new ties, ballast, and rail on previously-compacted earth. In those areas, no stormwater management modifications were required by the District. The Applicant’s new proposed stormwater management system will be located in a five-mile area of the corridor where an existing siding will be shifted outward and used as a third track. In this area, swales with hardened weir discharge structures and skimmers will be installed to provide stormwater treatment beyond what currently exists. The weir discharge structures will serve to prevent erosion at discharge points. The skimmers will serve to capture any floating oils or refuse. Because the FECR right-of-way is not wide enough in some three-track areas to also accommodate swales, the proposed stormwater management system was oversized in other locations to provide compensating volume. The District determined that this solution was an accepted engineering practice for linear systems such as railroads. Petitioners argue that the Applicant’s proposed stormwater management system is deficient because some of the proposed swales do not meet the definition of “swale” in section 403.803(14) as having side slopes equal to or greater than three feet horizontal to one foot vertical (3:1). The statute first defines a swale to include a manmade trench which has “a top width-to-depth ratio of the cross-section equal to or greater than 6:1.” The swales used in the proposed stormwater management system meet this description. Petitioners showed that the plans for one of the 46 proposed swales included some construction outside the FECR right-of-way. In response, the Applicant submitted revised plan sheets to remove the swale at issue. The Emergency Access Way The ERP application includes proposed modifications to portions of an existing unpaved emergency access way which runs along the tracks in some areas. The access way is a private dirt road for railroad-related vehicles and is sometimes used for maintenance activities. At the final hearing, Petitioners identified an inconsistency between an application document which summarizes the extent of proposed new access way construction and the individual plan sheets that depict the construction. The Applicant resolved the inconsistency by correcting the construction summary document. Petitioners also identified an individual plan sheet showing proposed access way modifications to occur outside of the FECR right-of-way. This second issue was resolved by eliminating any proposed work outside the right-of-way. Petitioners believe the proposed work on the access way was not fully described and reviewed because Petitioners believe the access way will be made continuous. However, the access way is not continuous currently and the Applicant is not proposing to make it continuous. No District rule requires the access way segments to be connected as a condition for approval of the ERP. Water Quantity Impacts An applicant for an ERP must provide reasonable assurance that the construction, operation, and maintenance of a proposed project will not cause adverse water quantity impacts to receiving waters and adjacent lands, adverse flooding to on-site or off-site property, or adverse impacts to existing surface water storage and conveyance capabilities. The District’s design criterion to meet this requirement for water quantity management is a demonstration that the proposed stormwater system will capture the additional runoff caused during a 25-year/3-day storm event. The Applicant’s proposed stormwater system meets or exceeds this requirement. Petitioners argue that the Applicant failed to provide reasonable assurance because the ERP application materials did not include a calculation of the discharge rates and velocities for water discharging from the swales during the design storm. The ERP application contains the information required to calculate the discharge rates and velocities and the Applicant’s stormwater expert, Bruce McArthur, performed the calculations and testified at the final hearing that in the areas where there will be discharges, the discharge rates and velocities would be “minor” and would not cause adverse impacts. The District’s stormwater expert, Jesse Markle, shared this opinion. Petitioners argue that this information should have been provided to the District in the permit application, but this is a de novo proceeding where new evidence to establish reasonable assurances can be presented. Petitioners did not show that Mr. McArthur is wrong. Petitioners failed to prove that the proposed project will cause adverse water quantity impacts, flooding, or adverse impacts to surface water storage and conveyance capabilities. Water Quality Impacts To obtain an ERP, an applicant must provide reasonable assurance that the construction, operation, and maintenance of a regulated project will not adversely affect the quality of receiving waters, such that state water quality standards would be violated. The District’s design criteria for water quality required the Applicant to show that its proposed stormwater system will capture at least 0.5 inches of runoff over the developed area. To be conservative, the Applicant designed its proposed system to capture 1.0 inch of runoff in most areas. Under District rules, if a stormwater system will directly discharge to impaired waters or OFWs, an additional 50 percent of water quality treatment volume is required. The proposed stormwater system will not directly discharge to either impaired waters or OFWs. In some locations, there is the potential for stormwater discharged from the proposed stormwater system to reach OFWs by overland flow, after the stormwater has been treated for water quality purposes. The Applicant designed its proposed stormwater system to provide at least an additional 50 percent of water quality treatment volume in areas where this potential exists. To ensure that the proposed construction activities do not degrade adjacent wetlands, other surface waters, or off-site areas due to erosion and sedimentation, the Applicant prepared an Erosion and Sediment Control Plan. Temporary silt fences and turbidity barriers will be installed and maintained around the limits of the construction. The District’s design criteria for water quality do not require an analysis of individual contaminants that can be contained in stormwater, except in circumstances that do not apply to this project. Compliance with the design criteria creates a presumption that water quality standards for all potential contaminants are met. See Applicant’s Handbook, V. II, § 4.1.1. Although not required, the Applicant provided a loading analysis for the proposed swales which could potentially discharge overland to impaired waters or OFWs. The analysis compared pre- and post-development conditions and showed there would be a net reduction in pollutant loading. Petitioners believe the pollutant loading analysis was inadequate because it did not specifically test for arsenic and petroleum hydrocarbons. However, the analysis was not required and adequate treatment is presumed. Petitioners did not conduct their own analysis to show that water quality standards would be violated. Petitioners’ expert, Patrick Dayan, believes the compaction of previously undisturbed soils in the emergency access way would increase stormwater runoff. However, he did not calculate the difference between pre- and post-construction infiltration rates at any particular location. His opinion on this point was not persuasive. Petitioners failed to prove that the proposed project will generate stormwater that will adversely affect the quality of receiving waters such that state water quality standards would be violated. The preponderance of the evidence shows the project complies with District design criteria and will not cause water quality violations. Soil and Sediment Contamination Petitioners argue that the ERP Modification does not account for the disturbance of existing contaminants in soils and sediments that could be carried outside of the right-of-way and into OFWs. Petitioners’ argument is based on investigations by their geologist, Janet Peterson, who collected soil, sediment, and surface water samples at 13 sites along the FECR rail corridor in the vicinity of OFWs, or surface waters that eventually flow into OFWs. During her sampling visits, Ms. Peterson saw no visual evidence of an oil spill, fluid leak, or other release of hazardous materials. Ms. Peterson compared her soil sample results to the Residential Direct Exposure Soil Cleanup Target Levels (“SCTLs”) established in rule 62-777. The SCTLs are the levels at which toxicity becomes a human health concern and the residential SCTLs assume soil ingestion of 200 mg/day for children, and 100 mg/day for adults, 350 days a year, for 30 years. Some of the soil sampling results showed exceedances of SCTLs, but the SCTLs are not applicable here because none of the sample sites are locations where children or adults would be expected to ingest soil at such levels for such lengths of time. Petitioners did not show that the contaminants are likely to migrate to locations where such exposure would occur. Ms. Peterson compared her soil sample results to the Marine Surface Water Leachability SCTLs, but she did not develop site-specific leachability-based SCTLs using DEP’s approved methodology. Nor did she show that the proposed project will cause the soils to leach the contaminants. Ms. Peterson collected sediment samples from shorelines, but not where construction activities are proposed. She compared her sediment sample results to the Florida Department of Environmental Protection’s (“DEP”) Sediment Quality Assessment Guidelines (“SQAGs”). These guidelines are not water quality standards. Any exceedance of these guidelines requires further analysis to determine potential water quality impacts. Ms. Peterson did not conduct the analysis. Ms. Peterson acknowledged that there are numerous sources for these pollutants at or near her sample sites, such as high-traffic roads, vehicular bridges, commercial and industrial facilities, boatyards, and golf courses. She did not establish baselines or controls. Ms. Peterson collected surface water samples at seven sites, some of which were located outside the FECR right-of-way. The results showed levels of phosphorous and nitrogen above the criteria for nutrients at some locations. Phosphorous, nitrogen, and the other nutrients are prevalent in the waters of Martin County and St. Lucie County and come from many sources. Petitioners’ evidence focused on existing conditions and not expected impacts of the proposed project. The evidence was insufficient to prove the proposed project will cause or contribute to water quality violations. Functions Provided by Wetlands and Other Surface Waters An applicant for an ERP must provide reasonable assurance that a proposed project will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. Petitioners claim the Applicant and District should not have relied on Florida Land Use Cover and Forms Classification System (“FLUCCS”) maps to identify and characterize wetlands and other habitat areas because the maps are too general and inaccurate. However, the FLUCCS maps were not used by the Applicant or District to evaluate impacts to wetlands or other habitats. The Applicant began its evaluation of impacts to wetlands and other habitat areas by field-flagging and surveying the wetland and surface water boundaries in the project area using a GPS device with sub-meter accuracy. It then digitized the GPS delineations and overlaid them with the limits of construction to evaluate anticipated direct impacts to wetlands and other surface waters. The District then verified the delineations and assessments in the field. The Applicant and District determined that there are a total of 4.71 acres of wetlands within the FECR right-of-way, including tidal mangroves, freshwater marsh, and wet prairie. They also determined the proposed project will directly impact 0.35 acres of wetlands, consisting of 0.09 acres of freshwater marsh and 0.26 acres of mangroves. Petitioners contend that the Applicant failed to account for all of the project’s wetland impacts, based on the wetland delineations made by their wetland expert, Andrew Woodruff. Most of the impacts that Mr. Woodruff believes were not accounted for are small, between 0.01 and 0.05 acres. The largest one is acres. The Applicant’s delineations are more reliable than Mr. Woodruff’s because the methodology employed by the Applicant had greater precision. It is more likely to be accurate. Petitioners argue that the 2013 exemption and the 2015 general permit did not authorize work in wetlands and, therefore, the impacts they cause must be evaluated in this ERP Modification. However, Petitioners did not prove that there are unaccounted-for wetland impacts associated with those authorizations. Any impacts associated with best management practices for erosion control, such as the installation of silt fences, would be temporary. The District does not include such temporary minor impacts in its direct, secondary, or cumulative impacts analyses. Most of the wetlands that would be directly impacted by the ERP Modification are degraded due to past hydrologic alterations and soil disturbances from the original construction and historical use of the FECR railway corridor, and infestation by exotic plant species. Most of these wetlands are also adjacent to disturbed uplands within or near the rail corridor. The functional values of most of the wetlands that would be affected have been reduced by these disturbances. The Applicant provided reasonable assurance that the project will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. Secondary Impacts Section 10.2.7 of the Applicant’s Handbook requires an applicant to provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonably expected uses of a proposed activity (a) will not cause or contribute to violations of water quality standards or adverse impacts to the functions of wetlands or other surface waters; (b) will not adversely impact the ecological value of uplands for bald eagles, and aquatic or wetland-dependent listed animal species for nesting or denning by these species; (c) will not cause impacts to significant historical or archaeological resources; and (d) additional phases for which plans have been submitted, and closely linked projects regulated under chapter 373, part IV, will not cause water quality violations or adverse impacts to the functions of wetlands or other surface waters. The proposed work will be entirely within the limits of the existing railway corridor where secondary impacts to wetlands and other surface waters caused by noise, vibration, fragmentation of habitats, and barriers to wildlife have existed for decades. The preponderance of the evidence shows that any increase in these kinds of impacts would be insignificant and would not reduce the current functions being provided. Because the affected wetlands are not preferred habitat for wetland-dependent, endangered, or threatened wildlife species, or species of special concern, and no such species were observed in the area, no adverse impacts to these species are expected to occur. Petitioners contend that adverse impacts will occur to the gopher tortoise, scrub jay, and prickly apple cactus. These are not aquatic or wetland-dependent species. However, the preponderance of the evidence shows any increase in impacts to these species would be insignificant. When the train bridges are closed, boats with masts or other components that make them too tall to pass under the train bridges must wait for the bridge to open before continuing. Petitioners contend that the current “stacking” of boats waiting for the bridges to open would worsen and would adversely impact seagrass beds and the West Indian Manatee. However, it was not shown that seagrass beds are in the areas where the boats are stacking. The available manatee mortality data does not show a link between boat stacking and boat collisions with manatees. Mr. Woodruff’s opinion about increased injuries to manatees caused by increased boat stacking was speculative and unpersuasive. The preponderance of the evidence shows that the adverse effects on both listed and non-listed wildlife species, caused by faster and more numerous trains would be insignificant. The activities associated with the 2013 exemption and the 2015 general permit for fiber optic cable were based on determinations that the activities would have minimal or insignificant adverse impacts on water resources. These determinations are not subject to challenge in this proceeding. The Applicant provided reasonable assurance that the secondary impacts of the project will not cause or contribute to violations of water quality standards, adversely impact the functions of wetlands or other surface waters, adversely impact the ecological value of uplands for use by listed animal species, or cause impacts to significant historical or archaeological resources. Elimination and Reduction of Impacts Under section 10.2.1.1 of the Applicant’s Handbook, if a proposed activity will result in adverse impacts to wetlands and other surface waters, the applicant for an ERP must implement practicable design modifications to eliminate or reduce the impacts, subject to certain exceptions that will be discussed below. Petitioners argue that this rule requires the Applicant and District to evaluate the practicability of alternative routes through the region, routes other than the existing railway corridor in Segment D09. As explained in the Conclusions of Law, that argument is rejected. The evaluation of project modifications to avoid impacts was appropriately confined to the railway corridor in Segment D09. The Applicant implemented practicable design modifications in the project area to reduce or eliminate impacts to wetlands and other surface waters. Those modifications included the shifting of track alignments, the elimination of certain third-track segments, and the elimination of some proposed access way modifications. However, the project qualified under both “opt out” criteria in section 10.2.1.2 of the Applicant’s Handbook so that design modifications to reduce or eliminate impacts were not required: (1) The ecological value of the functions provided by the area of wetland or surface water to be adversely affected is low, and the proposed mitigation will provide greater long-term ecological value; and (2) the applicant proposes mitigation that implements all or part of a plan that provides regional ecological value and provides greater long-term ecological value. Mitigation The Applicant proposes to mitigate for impacts to wetlands by purchasing mitigation credits from four District- approved mitigation banks: the Bluefield Ranch, Bear Point, Loxahatchee, and F.P.L. Everglades Mitigation Banks. Each is a regional off-site mitigation area which implements a detailed management plan and provides regional long-term ecological value. The number of mitigation credits needed to offset loss of function from impacts to wetlands was calculated using the Modified Wetland Rapid Assessment Procedure (“MWRAP”) or Wetland Assessment Technique for Environmental Review (“WATER”), as prescribed in the state permit for each mitigation bank. Applying these methods, the Applicant is required to purchase mitigation credits. The Applicant proposed to mitigate the adverse impacts to freshwater marsh wetlands by purchasing 0.01 freshwater herbaceous credits from the Bluefield Ranch Mitigation Bank, and 0.06 freshwater herbaceous credits from the Loxahatchee Mitigation Bank. The adverse impacts to tidal mangrove wetlands would be mitigated by purchasing 0.12 saltwater credits from the Bear Point Mitigation Bank, and 0.02 saltwater credits from the F.P.L. Everglades Mitigation Bank. The Applicant committed to purchase an additional 0.29 freshwater herbaceous credits from the Bluefield Ranch Mitigation Bank, for a total of 0.50 mitigation credits. The proposed mitigation implements a plan that will provide greater long-term ecological value than is provided by the wetlands that will be impacted. The Applicant proved by a preponderance of the evidence that the project complies with the District’s mitigation requirements. Cumulative Impacts To obtain an ERP, an applicant must provide reasonable assurance that a regulated activity will not result in unacceptable cumulative impacts to water resources. This assurance can be provided by proposing to fully mitigate the impacts within the same basin. However, when an applicant proposes mitigation in another drainage basin, the applicant must demonstrate that the regulated activity will not cause unacceptable cumulative impacts. The proposed project will adversely impact 0.02 acres of freshwater marsh wetlands and 0.21 acres of tidal mangrove wetlands in the St. Lucie River basin. The impacts to the freshwater marshes must be mitigated out-of-basin because there are no mitigation banks in the basin which offer freshwater herbaceous mitigation credits. The proposed project will adversely impact 0.07 acres of the freshwater marshes and 0.05 acres of the mangrove wetlands in the Loxahatchee River basin. Those impacts must also be mitigated out-of-basin because there are no mitigation banks in the Loxahatchee River basin. Because some of the Applicant’s proposed mitigation must be provided out-of-basin, the ERP application included a cumulative impact analysis. The analysis evaluated whether the proposed project, when considered in conjunction with other possible development within the St. Lucie River and Loxahatchee River drainage basins, would result in unacceptable cumulative impacts considering each basin as a whole. There are approximately 10,068 acres of freshwater marshes within the St. Lucie basin, of which an estimated 4,929 acres are not preserved and would be at risk of potential future development. The proposed project will adversely impact 0.02 of those acres, which is only 0.0004 percent of the total at-risk acreage. There are about 34,000 acres of freshwater marshes within the Loxahatchee River basin, of which an estimated 7,463 acres are at risk of future development, and approximately 564 acres of tidal mangrove wetlands, of which an estimated 75 acres are at risk of future development. The project will adversely impact 0.07 acres of the freshwater marshes (0.0009 percent), and 0.05 acres of the tidal mangrove wetlands (0.0667 percent). Petitioners contend the Applicant’s analysis did not account for impacts from proposed activities authorized in the 2013 and 2015 general permit. However, Petitioners failed to prove there are unaccounted-for wetland impacts. The preponderance of the evidence supports the District’s determination that the proposed project will not cause unacceptable cumulative impacts to wetlands and other surface waters. Public Interest When an applicant seeks authorization for a regulated activity in, on, or over wetlands or surface waters, it must provide reasonable assurance that the activity will not be contrary to the public interest, or if the activity is within or significantly degrades an OFW, is clearly in the public interest, as determined by balancing the following criteria set forth in section 373.414(1)(a): Whether the activities will adversely affect the public health, safety, or welfare or the property of others; Whether the activities will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activities will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activities will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activities will be of a temporary or permanent nature; Whether the activities will adversely affect or will enhance significant historical and archaeological resources; and The current condition and relative value of functions being performed by areas affected by the proposed activities. The proposed work is not within an OFW, but entirely within the FECR corridor. The potential for overland flow and indirect impacts to OFWs is addressed by additional treatment of the stormwater prior to discharge. The proposed project would not significantly degrade an OFW. Therefore, the applicable inquiry is whether the project is contrary to the public interest. Factor 1: Public Safety, Safety, and Welfare Petitioners contend that the proposed project will adversely affect public health, safety, and welfare by impacting water quantity, water quality, and certain non-environmental matters such as emergency response times, traffic congestion, and potential train collisions with pedestrians and vehicles. Potential environmental impacts have been addressed above and, by a preponderance of the evidence, the District and the Applicant showed that such impacts would be insignificant or would be mitigated. As to the potential for non-environmental impacts associated with train operations, it is explained in the Conclusions of Law that the public interest test does not include consideration of non-environmental factors other than those expressly articulated in the statute, such as navigation and preservation of historical or archaeological resources. However, because evidence of non-environmental impacts was admitted at the final hearing, the issues raised by Petitioners will be briefly addressed below. The regulatory agency with specific responsibility for railroad safety is the Federal Railroad Administration (“FRA”). The FRA reviewed the safety features associated with the proposed passenger train operations, and approved them. Public safety will be enhanced at roadway crossings because of the proposed improvements and the use of modern technology in monitoring and managing the movement of trains. Petitioners contend that the addition of the passenger rail service will impede emergency response times in Martin County and St. Lucie County due to more frequent roadway closures. However, freight trains currently impede emergency response times due to their length and slow speed. The passenger trains will be much shorter in length and faster so that roadway crossing closures for passing passenger trains will be much shorter than for freight trains. The ERP Modification and 2017 Exemption do not affect freight train operations. The preponderance of the evidence shows that passenger rail service is unlikely to cause a material increase in the occurrence of circumstances where an emergency responder is impeded by a train. The current problem must be addressed through changes in freight train operations. Petitioners also contend that the passenger rail service will interfere with hurricane evacuation. The persuasive evidence does not support that contention. Train service would cease when a hurricane is approaching. Petitioners contend the trains will have to be “staged” on either side of the two moveable bridges while other trains cross, thereby blocking road intersections. However, this was a matter of speculation. The Applicant does not propose or want to stage trains at the bridges. Petitioners contend that the project will cause hazards to boaters on the St. Lucie River because there will be more times when the train bridge will be closed to allow the passage of passenger trains. Although there were many statistics presented about the number of boats affected, the evidence was largely anecdotal with respect to the current hazard associated with boaters waiting for the passage of freight trains and speculative as to the expected increase in the hazard if shorter and faster passenger trains are added. Factor 2: Conservation of Fish and Wildlife As previously found, the proposed activities will not adversely affect the conservation of fish and wildlife, including threatened or endangered species. The preponderance of the evidence shows the project will have only insignificant adverse impacts on water resources and wildlife. Factor 3: Navigation of the Flow of Water Petitioners claim the project will hinder navigation on the St. Lucie and Loxahatchee Rivers because of the increase in bridge closures if passenger trains are added. The U.S. Coast Guard is the agency with clear authority to regulate the opening and closing of moveable train bridges over navigable waters in the interests of navigation. Petitioners’ insistence that the District address the bridge openings is novel. No instance was identified by the parties where this District, any other water management district, or DEP has attempted through an ERP to dictate how frequently a railroad bridge must open to accommodate boat traffic. The Coast Guard is currently reviewing the project’s potential impacts on navigation and will make a determination about the operation of the moveable bridges. It has already made such a determination for the moveable bridge which crosses the New River in Ft. Lauderdale. Petitioners point to section 10.2.3.3 of the Applicant’s Handbook, which states that the District can consider an applicant’s Coast Guard permit, and suggest that this shows the District is not limited to what the Coast Guard has required. However, Section 10.2.3.3 explains the navigation criterion in terms of preventing encroachments into channels and improving channel markings, neither of which encompasses the regulation of train bridges. The preponderance of the evidence shows the project would not cause harmful erosion or shoaling or adversely affect the flow of water. Factor 4: Fishing, Recreational Values, and Marine Productivity The preponderance of the evidence shows that there would be no adverse impacts or only insignificant impacts to fishing or recreational values and marine productivity. Factor 5: Permanent Impact The proposed project will have both temporary and permanent impacts. The temporary impacts include the installation of silt fences and turbidity barriers designed to reduce water quality impacts and impacts to functions provided by wetlands and surface waters. The impacts due to track installation, construction and rehabilitation of the non-moveable bridges, at-grade crossing improvements, and stormwater system improvements are permanent in nature. The permanent impacts have been minimized and mitigated. Factor 6: Historical or Archaeological Resources Petitioners do not contend that the project will adversely affect significant historical or archaeological resources. Factor 7: Wetland Functions in Areas Affected Because the proposed work is within the limits of an existing railway corridor where impacts have been occurring for decades, and the majority of the wetlands to be affected are of a low to moderate quality, there would be only a small loss of functional values and that loss would be fully mitigated. Public Interest Summary When the seven public interest factors are considered and balanced, the proposed project is not contrary to the public interest. Even if Petitioners’ non-environmental issues are included, the project is not contrary to the public interest. Compliance With Other Permit Conditions The project is capable, based on accepted engineering and scientific principles, of performing and functioning as proposed. The Applicant demonstrated sufficient real property interests over the lands upon which project activities will be conducted. It obtained the required consent for proposed activities relating to bridge crossings over state-owned submerged lands. The Applicant provided reasonable assurance of compliance with all other applicable permit criteria. Exemption Verification for Roadway Crossings The Applicant’s ERP application included a mixture of activities which required an individual permit, as well as activities in roadway crossings which the Applicant claimed were exempt from permitting. Pursuant to section 5.5.3.4 of the Applicant’s Handbook, the Applicant requested a verification of exemption as to certain work to be done within 23 of those 24 roadway crossings. The District determined that the improvements for which an exemption was sought were exempt from permitting under rule 62-330.051(4)(c) for minor roadway safety construction, rule 62-330.051(4)(d) resurfacing of paved roads, and rule 62-330.051(10) for “construction, alteration, maintenance, removal or abandonment of recreational paths for pedestrians, bicycles, and golf carts.” The preponderance of the evidence shows the proposed work qualifies for exemption under these rules.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order that: approves Environmental Resource Permit Modification No. 13-05321-P on the terms and conditions set forth in the District’s Corrected Proposed Amended Staff Report of May 11, 2017; and approves the Verification of Exemption dated March 31, 2017. DONE AND ENTERED this 29th day of September, 2017, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 2017.

Florida Laws (14) 120.52120.569120.57120.573120.60163.3161373.016373.069373.119373.406373.414373.427403.161403.803
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer