Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 48 similar cases
IN RE: DADE COUNTY APPLICATION FOR CERTIFICATE vs. *, 77-000607 (1977)
Division of Administrative Hearings, Florida Number: 77-000607 Latest Update: Jan. 13, 1978

Findings Of Fact The proposed site for the resource recovery unit is located on 160 acres of the northeast quarter of Section 17, Township 53 South, and Range 40 East in Dade County. This site is presently undeveloped and bordered on the east by the Dade County Northwest 58th Street landfill. The resource recovery facility as proposed consists of a three thousand (3,000) tons per day solid waste resource recovery facility and two 38.5 meggawatt steam electric generating turbines, and one 80 acre landfill. The proposed operations call for the separation of ferrous and aluminum metals and glass from combustible material. The combustible material is to be pulped, dried, and burned in four (4) boilers to produce steam for the generation of electricity. On a daily basis the resource recovery boilers will require 1.76 million gallons of water to operate the cooling towers. Cooling tower blow- down, boiler blow-down, and landfill leachate will be utilized in a hydro- pulping process to process the solid wastes prior to combustion. As a result of this waste water usage, no industrial waste water will be discharged from the site. Potable water will be supplied by the Miami Dade Water and Sewer Authority. Sanitary wastes will be treated in a sewage treatment plant on the site. The cooling water will be withdrawn from a portion of the Biscayne Aquifer contaminated by leachate from the Northwest 58th Street landfill. The South Florida Water Management District has concluded that the Biscayne Aquifer would be capable of supplying the non-potable water requirements of the proposed facility. In addition, the withdrawal of water for the facility would alleviate the impact of the leachate plume from the 58th Street landfIll, which plume of contaminated water is moving eastward to the Miami Springs wellfield. The construction of the resource recovery facility would allow the closing of the 58th Street landfill and would thereby prevent the continued production of contaminated leachate and would reduce problems of flies, rodents, and odors. The construction of the resource recovery facility will involve extensive grading, filling, and removal of vegetation on the proposed site. Due to previous drainage and development of the surrounding area, however, the site is situated in a degraded everglades habitat the hydrologic regime of which has been drastically altered and now supports relatively little wildlife. Surrounding land uses would make future restoration difficult. The destruction of the grasses, and other vegetation on the site would have little environmental impact. The resource recovery facility site is owned by Dade County and will be operated by Dade County Resource Recovery, Inc. Steam produced at the resource recovery facility will be sold to Florida Power and Light Company for the generation of electricity. Some 61 meggawatts of electricity will be generated and distributed throughout the Florida Power and Light transmission system. The electricity generated by this facility will eliminate the need for over one million barrels of imported fuel oil each year and will produce a net savings to the customers of Florida Power and Light. The resource recovery facility will utilize cyclonic collectors and high efficiency electrostatic precipitators to remove fly ash from the burning of processed refuge. Plant air will be injected into the boiler or will be passed through activated carbon filters to eliminate odors. As a result of these control measures, the resource recovery facility will comply with state and federal emission limitations and ambient air quality standards. Although the facility may contribute slightly to a violation of the Dade County Ambient Air Quality Standards, the Director of the Dade County Environmental Resources Management Board did not feel that the facility would cause a problem. The resource recovery facility would utilize the latest reasonably available control technology for the control of emissions to the atmosphere. The use of the proposed equipment will result in a very small incremental increase of sulphur dioxide and particulate matter into the ambient air. These emissions are less than the federal significant deterioration limits and the increases in air pollution levels are not expected to significantly degrade air quality in the area. The Florida Public Service Commission report of October 7, 1977, states that 62 meggawatts of electricity would enhance the reliability of Florida Power and Light's system and would displace residual fuel oil so that some benefit would be derived from construction of the facility. The Division of State Planning did not submit a report as required by Section 403.507(1)(a), Florida Statutes. The Department of Natural Resources, Game and Fresh Water Fish Commission, Department of Commerce, and South Florida Regional Planning Counsel offered comments on the facility supportive of its construction and operation. Comments and objections from the Department of Health and Rehabilitative Services, South Florida Water Management District, the Division of Archives, History and Records Management, were resolved by the provision of additional information and proposed conditions of certification. No opposition from these agencies was presented at the conclusion of the hearing. The Department of Environmental Regulation recommended certification of the Dade County Resource Recovery facility in accordance with the proposed general and special conditions of certification. The applicant has stipulated and agreed that the general and special conditions of certification, as proposed at the hearing, should be imposed if certification is granted. At the conclusion of the presentations by the parties to this proceeding, opportunity was given to the general public to comment on the application for site certification. No such individuals appeared and no comments were offered. After examining the sum and substance of the testimony and evidence offered, it appears that the construction of the resource recovery facility would provide for the closing of inadequate sanitary landfills and inadequate air polluting incinerators. Further, the operational safe guards of the proposed facility are sufficient to protect human health, wildlife and aquatic life. Finally, the construction and operation of the proposed facility will not violate state air or water pollution standards.

Recommendation It is therefore recommended that the proposed site be found and held to be in conformity with existing land use plans and zoning ordinances in effect as of this date, and it is further recommended that the responsible zoning or planning authorities be restrained from hereafter changing such land use plans or zoning ordinances so as to affect the proposed site. DONE AND ENTERED this 22nd day of November, 1977, in Tallahassee, Florida. KENNETH G. OERTEL, Director Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32304 (904) 488-9675 Copies furnished to all parties

Florida Laws (2) 403.507403.508
# 1
DEPARTMENT OF ENVIRONMENTAL REGULATION vs. B. D. TAYLOR AND LANE MOBILE ESTATES, 83-001208 (1983)
Division of Administrative Hearings, Florida Number: 83-001208 Latest Update: Oct. 21, 1983

Findings Of Fact B. D. Taylor, Respondent, is the owner of a wastewater treatment facility near Panama City, Florida, which serves a community of some 125-150 mobile homes at Lane Mobile Home Estates. The facility has a 24,000 gallons per day capacity to provide secondary treatment of wastewater with percolating ponds. It was first permitted in 1971 upon construction and has been in continuous operation since that time. In 1980 Respondent employed the services of a consultant to apply for a renewal of its temporary Permit to operate a wastewater treatment facility. This application stated the temporary operating permit (TOP) was needed to give Respondent time to connect to the regional wastewater treatment facility. The schedule contained in the following paragraph was submitted by Respondent at the time needed to accomplish this objective, Following inspection of the facility, a TOP was issued December 5, 1980 (Exhibit 1), and expired January 1, 1983. TOPs are issued to facilities which do not comply with the requirements for Wastewater treatment. Exhibit 1 contained a schedule of compliance to which Respondent was directed to strictly comply to stop the discharge of pollutants from the property on which the facility is located. These conditions are: Date when preliminary engineering to tie into regional will be complete and notification to DER. July 1, 1981; Date when engineering to tie into regional system will be complete and notification to DER - June 1, 1982; Date construction application will be submitted to phase out present facility - March 1, 1982; Date construction will commence - June 1, 1982; Date construction is to be complete and so certified - October 1, 1982; and Date that wastewater effluent disposal system will be certified "in compliance" to permit - January 1, 1903. None of these conditions or schedules has been met by Respondent. The regional wastewater treatment facility was completed in 1982 and Respondent could have connected to this system in the summer of 1982. This wastewater treatment facility is a potential source of pollution. The holding ponds are bordered by a ditch which is connected to Game Farm Greek, which is classified as Class III waters. The size of Game Farm Creek is such that any discharge of pollution to this body of water would reduce its classification below Class III. On several occasions in the past there have been breaks in the berm surrounding the holding ponds which allow the wastewater in the holding ponds to flow into the ditch and into Game Farm Creek. Even without a break in the berm, wastewater from these holding ponds will enter Game Farm Creek either by percolation or overflow of the holding ponds caused by the inability of the soil to absorb the effluent. On January 28, 1983, this facility was inspected and the results of the inspection were discussed with the operators of the facility. The plant was again inspected on February 8 and February 18, 1983. These inspections disclosed solids were not settling out of the wastewater in the settling tanks; inadequate chlorination of the wastewater was being obtained in the chlorination tanks; samples taken from various points in the system, the ditch along side the holding tanks and in Game Farm Creek, disclosed excess fecal coliform counts; and that very poor treatment was being afforded the wastewater received at the plant as evidence by high levels of total Kejhdal nitrogen and ammonia, high levels of phosphates, high biochemical oxygen demand, and low levels of nitrates and nitrites. In July, 1983, in response to a complaint about odors emanating from the plant, the facility was again inspected. This inspector found the aeration tanks anaerobic, effluent had a strong septic odor, the clarifier was cloudy, the chlorine feeder was empty, no chlorine residual in contact tank, final effluent was cloudy, both ponds were covered with duckweed and small pond was discharging in the roadside ditch (Exhibit 14) Expenses to Petitioner resulting from the inspections intended to bring Respondent in compliance with the requirements for wastewater treatment facilities are $280.32 (Exhibit 9)

Florida Laws (2) 403.087403.088
# 2
FREDERICK A. BRADY AND JANET B. BRADY vs KENNETH ACRE AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 91-002608 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Apr. 25, 1991 Number: 91-002608 Latest Update: Jul. 22, 1992

The Issue The issues are whether the Consent Order entered into between the Department of Environmental Regulation (DER) and Kenneth Acre (Acre) is an appropriate settlement of the violations addressed therein and whether Acre is entitled to construction permit number IC35-190005 for an Industrial Waste Disposal Facility. The Bradys assert that the Consent Order is not a reasonable exercise of DER's enforcement discretion and that the permit should be denied.

Findings Of Fact Background Acre owns and operates an animal research facility in Eustis, Florida. Acre performs research trials on dogs using a USDA approved heartworm medication sold under the brand name of Heartguard, the chemical name of which is ivermectin. Acre is not in the business of testing or manufacturing new drugs. The Consent Order To handle the waste generated by the animals at the facility, Acre initially constructed a conventional septic tank system. Prior to construction, Acre contacted the Lake County health department to inquire about permitting and was told that he did not need a permit for his facility. With that information, he continued with the project. Subsequently, DER became aware of the facility and notified Acre that a DER industrial waste permit was required and that he should cease the discharge into the septic tank until such a permit was obtained. Acre complied with DER's instructions and plugged the septic tanks. Since the time the septic tanks were plugged, the waste has been collected by Roto Rooter on a periodic basis and disposed of offsite. Acre entered into a Consent Order with DER to resolve the alleged past violation for not obtaining a permit and paid of penalty of $600 as required by DER. The Consent Order is a reasonable and appropriate settlement of the violations alleged therein. The Disposal System Acre has applied for a permit to construct and operate an evapotranspiration disposal system to dispose of the waste from his facility on site. The proposed system is essentially a modified septic tank system using a lined drainfield to capture and hold the liquid waste, allowing it to transpire from the grass or otherwise evaporate into the atmosphere and preventing any discharge to groundwater. The waste will be discharged to a series of modified septic tanks which will provide treatment beyond that of a traditional septic tank system and will reduce the amount of total suspended solids. The first septic tank accepts the waste and provides initial treatment through natural settling of solids. The waste then passes through a filter device and travels by gravity flow to the second septic tank. From the second tank it flows through a second filter device and into a dosing tank. The dosing tank is basically a small holding basin with a pump that disperses the waste to the drainfield in incremental amounts. The dosing tank contains several float mechanisms which monitor the level of liquid in the tank. When the water level in the dosing tank reaches a certain level, one such float mechanism turns on the pump to transport the liquid to the drainfield. The waste is then pumped from the dosing tank through a closed pipe to one of two evapotranspiration cells where it is distributed through a number of perforated pipes. The Evapotranspiration Cells The perforated pipes are situated in a gravel bed approximately 24 inches in depth. On top of the gravel bed is a clay soil mix approximately 15 inches deep. The clay soil mix absorbs the liquid waste in the gravel bed by drawing it up through the process of capillarity. Once the liquid is in the upper clay soil layer, it is evaporated. Grass is planted on top of the soil mix as an additional method for dissipation of the waste. The liquid waste is absorbed by the roots of the grass and transpired through the grass leaves. The clay soil mix in the top layer of the system is relatively impervious. The impervious nature of the soil mix along with a three percent surface slope will prevent rain water from entering the evapotranspiration cells and impacting the effective operation of the system. The entire drainfield has a double liner: one PVC plastic liner and a 6" clay layer. These two liners will ensure that no discharge to groundwater will occur from the system. System Capacity It is estimated that the Acre facility will produce approximately 520 gallons per day (GPD) of waste to be handled by the system. The drainfield is designed to handle twice the volume that will be discharged by the Acre facility and is therefore more than adequate to assimilate the waste received into the system. The drainfield is composed of two independent cells so that loading of each cell will be rotated. Once one cell receives its maximum capacity, the loading of that cell will cease in order to allow that cell to assimilate the waste through evapotranspiration. In this manner, the first cell is permitted to "rest" while the second cell receives further loading from the dosing tank. Safety Features Although the proposed disposal system is innovative in design, it incorporates several safety features which will ensure that no overflow of waste will occur. First, a float mechanism in the dosing tank is designed to trigger an alarm in the event the water level in the dosing tank gets too high. If that occurs, the alarm provides a flashing light as well as a horn which will notify the operator of a problem. Once the float reaches this warning level, the system will automatically shut down, thus preventing further waste from entering the system. Second, each evapotranspiration cell is equipped with a similar device which will automatically close off the dosing tanks and prevent further discharge into the cells in the unlikely event the system were to become too saturated to accept further loading. Finally, the double lined drainfield provides an additional safety measure which will prevent any discharge to groundwater. The numerous permit conditions requiring periodic monitoring of water quantity and quality in the system itself as well as the groundwater in the vicinity of the system provide ample assurance that the system will not pose a threat to the state's water resources. Ivermectin Although the proposed system will not discharge to groundwater, DER required the applicant to determine the amount of ivermectin in the wastestream. Ivermectin binds tightly to soil and does not dissolve in water. A sample of the wastestream from the Acre facility was collected by Bionomics Laboratory, Inc., and analyzed by Analytical Development Corporation using the analytical procedure designed by Merck scientists. The results of this analysis show that the concentration of ivermectin in the Acre wastestream ranges from .6 to 6.1 parts per trillion (ppt). The publication submitted to the Department by Acre entitled, Chapter 11, "Environmental Aspects of Ivermectin Usage in Livestock: General Considerations" by Halley, Nessel and Lu, from William C. Campbell, Ivermectin and Abamectin, documents the results of studies designed to determine whether using ivermectin in animals would result in any harmful or undesirable effects on the environment through excretion in the feces. This publication indicates that: Ivermectin is relatively immobile in soil and will not readily translocate into groundwater. Ivermectin is rapidly decomposed by sunlight and therefore will not accumulate in soil when administered to livestock. Ivermectin has no effect on earthworms at a concentration in soil of 12 parts per million (ppm). (This concentration is approximately two million times higher than that of the Acre waste stream.) Aquatic organisms such as water fleas and fish are highly sensitive to ivermectin toxicity. However, ivermectin is not toxic to the most sensitive species, the Daphnia magna, at a concentration of 0.01 parts per billion (ppb). Ivermectin concentrations in cattle feedlot runoff was less than the no-effect level of 0.01 ppb for Daphnia magna and therefore should cause no adverse environmental effects in surface or subsurface waters. The highest concentration of ivermectin found in the Acre waste stream is 6.1 ppt (or .006 ppb), which is less than the 0.01 ppb non-toxic level for the most sensitive aquatic species. Based on the concentration of ivermectin found in the Acre waste stream and the fact that ivermectin binds tightly to soil, the discharge from the Acre facility would not cause any adverse environmental impact, even if it were discharged to groundwater. Bradys' case Bradys submitted no evidence to show that the Consent Order is not an appropriate settlement of the violations alleged therein. They submitted no evidence that the septic tanks were improperly plugged. Brady offered no expert testimony in support of their claim that the facility had caused an adverse impact to groundwater or that the proposed system would cause any threat to groundwater quality. Bradys apparent concern about standing surface water on their property during heavy rainfalls is not relevant to this proceeding. Their concern that the lining of the drainfield could leak is unsupported by competent evidence. Bradys learned immediately prior to hearing that DER had changed its position and intended to issue the permit. Their failure to present any relevant evidence that the Consent Order was insufficient or that the proposed facility would violate any applicable DER rules or criteria and their ill- prepared participation in the hearing was in part the result of DER's late change in position. Bradys' participation in this proceeding was not shown to be frivolous.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Environmental Regulation enter a Final Order and therein: Ratify the terms of the Consent Order as reasonable. Grant Acre construction permit number IC35-190005 for an Industrial Waste Disposal Facility, subject to the special conditions set forth in DER Exhibit 1. RECOMMENDED this 22nd day of July, 1992, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of July, 1992. APPENDIX TO RECOMMENDED ORDER CASE NOS. 91-2608, 92-0958 AND 92-0959 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioners, Bradys 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 6 & 7(8) and 15(10). 2. Proposed findings of fact 1-5, 16, 27, 28, 31, 36-42, 44, 46-49, 51, 52, 54, 57-59, 61, and 62 are subordinate to the facts actually found in the Recommended Order. 3. Proposed findings of fact 8, 10-14, 17, 19-21, 26, 29, 30, 32, 33, 35, 43, 53, 55, and 56 are irrelevant. Proposed findings of fact 9, 18, 22-25, 45, and 50 are unnecessary. Proposed findings of fact 34 and 60 are unsupported by the competent and substantial evidence. Specific Rulings on Proposed Findings of Fact Submitted by Respondents, Acre and DER Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-44(1-44). Proposed findings of fact 45 and 46 are unsupported by the competent and substantial evidence. COPIES FURNISHED: Carlyn H. Kowalsky, Attorney at Law Bogin, Munns & Munns 250 North Orange Avenue 11th Floor-P.O. Box 2807 Orlando, FL 32802 Douglas MacLaughlin, Attorney at Law Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Martha Hunter Formella Attorney at Law FOLEY & LARDNER Post Office Box 2193 Orlando, FL 32802-2193 Carol Browner, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57403.087403.412
# 3
DEPARTMENT OF COMMUNITY AFFAIRS vs. FLORIDA EAST COAST RAILWAY COMPANY, ET AL., 83-003271 (1983)
Division of Administrative Hearings, Florida Number: 83-003271 Latest Update: Sep. 28, 1984

Findings Of Fact FEC is the owner and developer of the project at issue in this proceeding, an industrial park to be located on 322.1 acres in Section 32, in the Town of Medley, in northwestern Dade County, Florida. Not at issue in this proceeding is the related but separate project planned by FEC for construction in Section 6, an unincorporated area of Dade County, lying immediately southwest of the property at issue. FEC proposes 5,193,570 gross feet of floor space for the project, to be constructed in six phases. Seventy-four percent of the floor area is to be completed or under construction within the first five years of the park's operation. Expected uses of the park, when completed, are expected to fall into four general categories: Distribution, comprising 792,516 square feet; wholesale trade, 2,509,018 square feet; manufacturing, 873,520 square feet; and offices and services of 1,017,515 square feet. There is no specification of what types of industries will be located in the project, or what types of chemicals or materials each may handle. FEC has applied for and received various approvals of the proposed industrial park. On June 6, 1983, the South Florida Regional Planning Council ("RPC") recommended approval of the FEC proposal, with conditions. On August 1, 1983, the town council of Medley adopted Resolution No. C-426, which approved and issued a development order for a development of regional impact for the project. Before the issuance of the Medley development order, Metropolitan Dade County adopted its own development order, Resolution No. Z-114-83, on June 23, 1983, approving the development proposed for Section 6 in the unincorporated area of the county. In September, 1983, DCA appealed the Medley development order. On October 3, 1983, the RPC voted not to appeal that order. The proposed project is located in an industrialized and largely unsewered area. The FEC property surrounds or abuts numerous out parcels within Section No. 32, which are served only by septic tank disposal systems, unlike the sewer system planned for the FEC development. The Northwest Wellfield is located about three miles to the southwest of the proposed FEC industrial park at its closest point to Section 32, and about four miles from the furtherest reach of the park. The wells of the Northwest Wellfield form a line about two miles west of the Florida Turnpike, and four miles southwest of Medley. The wellfield presently comprises 15 wells, each 42 inches in diameter, fully penetrating the Biscayne Aquifer to a depth of about 70 feet. The county has equipped each well with a two-speed pump capable of producing ten million gallons per day (MGD) at low speed, and about 15 MGD at high speed. Current maximum capacity of the wellfield is about 225 MGD. The county holds a valid consumptive use permit from the South Florida Water Management District authorizing an average pumpage of 50 MGD. The county has applied for a permit to increase the pumpage to 180 MGD. The county is presently pumping the wellfield at the rate of 140 MGD to offset the reduction in pumpage from the Hialeah and Miami Springs wellfields as a consequence of the discovery of contamination in those fields. The Hialeah and Miami Springs wellfields are currently pumping at a rate varying from three to ten MGD. The Northwest Wellfield, completed in 1983, at a cost to the public of $38,000,000, is located within the Biscayne Aquifer, which underlies all of southeastern Florida, including all of Dade County, from north of Boca Raton to the northwest area of Monroe County. The Biscayne Aquifer is a highly permeable, unconfined shallow aquifer composed of limestone and sandstone. The aquifer is a regional resource, serving as a sole source of potable water for the approximately 1.8 million residents of Dade County. Because of its cavernous nature, the aquifer has high vertical and horizontal permeabilities, permitting both rapid infiltration of rainfall as recharge to the aquifer, and rapid drainage through canals. Recharge to the aquifer is primarily from rainfall. In the latter part of the dry season, however, the main recharge to the aquifer results from infiltration from canals fed from water conservation areas. Net recharge from rainfall to the aquifer ranges from 8 to 20 inches per year. Because of wide fluctuations in annual rainfall amounts in South Florida, recharge from canals to the wellfield is important. The South Florida Water Management District operates an intricate system of canals, levees, control structures, and large water conservation areas for flood control, water conservation, and salinity control. These systems significantly affect water levels in the Biscayne Aquifer, including the area around the Northwest Wellfield. The levees impound fresh water and prevent overland sheet flow from the Everglades eastward through agricultural and urban areas. The complex system of interconnected canals provides necessary drains for the urban coastal areas in the wet season and transfers water from the conservation areas during the dry season to replenish water in the aquifer removed by various municipal and county wellfields. Water levels in the canals are controlled by opening or closing control structures during the wet season to prevent flooding in urban agricultural areas, and leaving the structures closed during the dry season to conserve fresh water and limit saltwater intrusion. Canal levels usually reach their seasonal lows in May. In the vicinity of the Northwest Wellfield, the system of levees and canals provides a substantial amount of recharge to the wellfield. The canal most significantly affecting water levels in the Northwest Wellfield is the Snapper Creek Canal, a borrow canal running immediately east of and parallel to the Turnpike, about two miles east of the wellfield. The Snapper Creek Canal borders the western line of the FEC property in Section No. 6 and lies about one mile west of Section No. 32. The terms "cone of influence" or "cone of depression" are terms applied to the area around a well from which the well draws water. Before a well commences pumping, ground water fills the pores and fractures in underground rock formations to a water level at which the fluid pressure of the ground water equals the atmospheric pressure exerted from above. Pumping the well reduces the fluid pressure of the ground water in the vicinity of the well, and results in a cone of depression or influence. Viewed from above, a drawing of a hydrologic cone of depression appears roughly circular, centered on the pumping well. A cross section of the cone would show an inverted shallow cone in the upper aquifer, whose lowest point coincides with the intersection of the cone where it enters the well. Pumping the well creates a down gradient for water below the area of the cone to flow toward the well. A "hydrologic cone of influence" is that point marking the outer bounds of the influence of a pumping well at a given point in time. A "regulatory cone of influence" arbitrarily fixes the location of the cone as a zone in which activity is regulated. The extent of a regulatory cone depends upon policy decisions taking into account the margin of safety deemed necessary for the protection of a well, regardless of the actual location of the hydrologic cone and technology available to protect ground water. The generally accepted value adapted by most regulatory agencies for the "regulated cone of influence" of a wellfield is the 0.25 foot draw-down line. This is so because it is also generally accepted that, with proper engineering practices and proper annual inspections, potential contaminants be generated and stored within this regulated cone of influence without inordinate risks of contamination to the underlying aquifer. The extent of a hydrologic cone of influence varies continuously, and is dependent upon the characteristics of the involved aquifer, such as its ability to transmit and to retain water, as well as the pattern and the amount of rainfall in the area, and the effect of nearby streams or canals. In addition, the rate of pumping of a well controls the extent of the cone of influence under any given set of aquifer conditions. Dade County regulates land uses in the area of the Northwest Well field according to whether property falls within the projected cone of influence of the field. In March, 1981, Dade County adopted an ordinance prohibiting the handling, use, transportation, disposal, storage, discharge, or the generation of hazardous materials in an area west of the Florida Turnpike, defined as being within 210 days travel time for a hypothetical particle of contamination to the Northwest Wellfield. That initial protective zone lay entirely to the west of the Turnpike, and included neither Section 6 nor Section 32. As a result of further study and computer modeling, the county subsequently adopted Ordinance No. 83-82 on September 20, 1983, amending the map of the cone of influence for the Northwest Wellfield, and adopting new regulations requiring the use of sewers instead of septic tanks in industrial areas. The amended map projected a cone of influence that greatly expanded the protective zone around the wellfield, and included both Section 6 and Section 32. The regulatory cone of influence selected by Dade County does not conform to the hydrological cone of influence, but excepts instead the area around the well depressed by 0.25 feet or more from the original unpumped surface. The county based its modeling of the regulatory line on an assumed pumpage of 150 MGD for the Northwest Wellfield, which is approximately equal to its present pumpage, and 75 MGD from the Miami Springs, Hialeah, and Preston wellfields, which is approximately ten times the current combined rate of pumpage for those fields. In addition, in running its computer model, the county conservatively assumed the highly unlikely condition for the aquifer--a 210-day period during which the aquifer would receive no recharge from rainfall. This "worst case" condition has never occurred during this century. In addition to this assumption, the county's computer modeling also ignored the substantial contraction of the cone during every wet season because of rainfall recharge, and omitted consideration of recharge to the wellfield from canal systems in the area. Within the line defined by its regulated cone of influence, Dade County currently bans all use, handling, generation, and transportation of hazardous materials. The cone of influence currently contained in the county's ordinances includes all of Section 32, including FEC's proposed project. Dade County Ordinance No. 83-82 is considered an interim regulation, intended to remain in force while Dade County continues to gather information concerning the aquifer in the vicinity of the Northwest Wellfield under pumping conditions. Since the enactment of the wellfield protection ordinance, Dade County has initiated a study to formulate a more detailed management plan for the wellfield. Dade County is conducting the study and generally implementing its environmental regulation and wellfield protection through its Department of Environmental Resources Management (DERM). DERM's powers extend into municipal areas, such as Medley, as well as throughout the unincorporated area of Dade County. The agency has a budget in excess of $5 million annually. Both within the municipalities and throughout the unincorporated areas of Dade County, DERM reviews building permit applications of all industries expected to potentially discharge chemicals into sewer systems. DERM requires all such industries to obtain an annual permit under Section 24-35.1 of the Dade County Code, and to install pretreatment facilities to ensure that no unsafe chemicals are discharged directly into sewers. In addition, DERM requires that all users or generators of hazardous materials throughout Dade County follow best management practices, including ground water monitoring, when appropriate. A special section of the agency focuses on the enforcement of hazardous materials regulation. In addition, Dade County has initiated a hazardous waste cleanup fund, a liquid waste transporter's permit ordinance, and regulation for underground storage facilities for hazardous materials. Further, Dade County has adopted Resolution No. R-114-84, which incorporates a non-exclusive list of numerous hazardous materials subject to regulation under the wellfield protection ordinance and other regulations. The more credible evidence of record in this cause establishes that even should Dade County remove the current ban on hazardous materials in Section 32, the proposed industrial park, as restricted by the Medley development order, would pose no significant threat of contamination to the Northwest Wellfield. As modeled under realistically conservative assumptions, including pumpage rated far exceeding the presently permitted legal rate of 50 MGD, the Northwest Wellfield hydrological cone of influence would reach into Section 32 for no more than one or two months per year, at the end of the dry season. For most of the year, the Snapper Creek Canal will act as a natural recharge boundary for the Northwest Wellfield. The canal would normally carry sufficient water northward from the Tamiami Canal to maintain a pressure head in the canal, driving water into the aquifer on both sides, replenishing the water drawn by the wellfield in the area west to the canal, and holding the cone of influence at the west side of the canal. On the east side of the canal, ground water would resume its natural flow to the southeast or east, unaffected by pumping in the Northwest Wellfield. During the dry season, the recharge mound in the Snapper Creek Canal would diminish, and the cone of influence could gradually expand, possibly recharging Section 32 for a month or two at the end of the dry season. As soon as the rainy season commenced again, however, the canal would fill up rapidly and resume its function as a recharge boundary. The more credible evidence establishes that it is highly unlikely that ground water contaminants originating from Section 32 would ever reach the Northwest Wellfield. Ground water moves only a few feet or even inches per day in the Biscayne Aquifer. Because Section 32 is located three to four miles from the Northwest Wellfield, the gradient to the wells in the cone of influence in Section 32 is extremely slack. In the driest of droughts, a hypothetical plume of contaminants beneath Section 32 would move only slightly towards the wellfield. At the return of the wet season, the gradient draining ground water from Section 32 eastward to the Miami Canal would be very steep and would rapidly flush any contaminants away from the wellfield and its cone of influence. The Medley development order imposes several restrictions on the development which protect the Northwest Wellfield from any threat of potential contamination from the proposed industrial park. The development order requires the removal of all exotic vegetation and the planting of native species to reduce the demand for water and the use of fertilizer, a potential contaminant; restricts irrigation in the project to the use of non-potable water from onsite lakes and wells; obligates FEC to construct, or provide $600,000 to the Dade County Fire Department for construction of, a fire station according to county specifications within the primary response district for Section 32, to improve the fire department's capability to respond quickly to any spill of hazardous materials; requires FEC to submit to the RPC, Dade County and Medley a detailed management operation plan within six months of the date of issuance of the development order; and further requires that FEC submit a hazardous material spill contingent fee and response plan to the RPC, Dade County, and Medley within one year of the date of the development order. The development order contains detailed criteria for the management/operation plan, including inspections, monitoring, and the use of best management practices designed to minimize the risk of contaminating ground water. Further, these requirements include approval of specific standards for hazardous materials accident prevention, mitigation, and response; adequate pre-treatment facilities to assure segregated retention of hazardous waste and their removal and disposal in accordance with local, state, and federal requirements; that all facilities be readily open for inspection by Medley and DERM; and appropriate storage and accurate labeling of hazardous materials. The order also requires that FEC receive review and approval of its plans by the RPC, Medley, and Dade County. The RPC will, if deemed appropriate, in the course of review, impose its customary policy of ground water monitoring for a project using or generating hazardous materials. The development order provides that whatever wellfield protection regulations Dade County might adopt after further monitoring of the Northwest Wellfield will apply to the FEC project in Section 32. The RPC compiled, and Medley adopted, in the development order, "Table 22" as a tool for determining the types of land uses that should be excluded from locating in the proposed industrial park. In the event Dade County were to remove the present ban on hazardous materials in Section 32, the Medley development order requires that every firm and industry listed in Table 22 desiring to locate in the development to apply to RPC, Dade County, and Medley for a waiver of restriction on hazardous materials, based upon the tenant's demonstration that its use of appropriate best management practices or other measures will adequately protect the environment. These applications would be reviewed on a case-by-case basis to determine the adequacy of proposed protected measures. This condition is imposed in the development order in addition to existing local, state, and federal permitting requirements. Further, Dade County also independently requires the use of best management practices, including monitoring when appropriate, by any industry using hazardous materials in Dade County. In summary, the evidence in this cause establishes that the current ban imposed by Dade County on the use, handling, generation, and transportation of hazardous materials in Section 32, when viewed in the context of the existing hydrological system in the area and the conditions imposed upon FEC in the Medley development order, combine to demonstrate the lack of a permanent ban on hazardous materials in Section 32 will pose no significant threat to the Northwest Wellfield. There is no evidence of record in this proceeding to demonstrate that the proposed project is in any way inconsistent with an existing state land development plan, any local land development regulation, or the regional planning council report.

Florida Laws (5) 120.54120.57380.06380.07380.08
# 4
THOMAS H. ADAMS vs RESORT VILLAGE UTILITY, INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 01-003172 (2001)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 14, 2001 Number: 01-003172 Latest Update: Apr. 16, 2002

The Issue The issue is whether Resort Village Utility, Inc., and SGI Utility, LLC, are entitled to a renewal of a permit for the construction and operation of a wastewater treatment facility with effluent disposal to a rapid-rate absorption field land application system consisting of three absorption beds on St. George Island in Franklin County, Florida.

Findings Of Fact In 1996, DEP issued Permit No. 235845 (subsequently renumbered Permit No. FLA010069-001) to RVU. The permit was issued pursuant to Adams v. Resort Village Utility, Inc. and Department of Environmental Protection, DOAH Case No. 95-0863 (Final Order February 23, 1996). Petitioner, in the instant case, was the petitioner in the prior case. RVU and DEP, Respondents in the instant case, were respondents in the prior case. The original permit authorized RVU to construct and operate an advance wastewater treatment facility with associated reuse/land application system (AWT facility) in a proposed mixed-use development on St. George Island in Franklin County, Florida. Mr. Ben Johnson was the owner of the proposed development and the principal of RVU when DEP issued the original permit. DEP issued the original permit for five years with an expiration date of March 1, 2001. The instant case involves a renewal of the original permit, currently designated as Permit No. FLA010069-002 (the Permit). Since the issuance of the original permit, the AWT facility has been constructed in accordance with its plans and specifications. However, at the time of the final hearing in the instant case, the AWT facility was not operational. The original permit contained certain groundwater monitoring requirements. These requirements included baseline monitoring to collect data on certain contaminants or pollutants before the AWT facility becomes operational for comparison to groundwater monitoring after the AWT facility becomes operational. The original permit did not specify the time frame for beginning and ending the monitoring. RVU furnished DEP with a baseline groundwater monitoring report in December 1997 and June 1998. By letter dated June 15, 1998, Garlick Environmental Associates, Inc., on behalf of RVU, advised DEP that further baseline groundwater monitoring would be suspended until February 1999. RVU properly suspended the baseline groundwater monitoring because of a delay in the construction and operation of the AWT facility. At the time of the final hearing, RVU had not resumed the monitoring. The AWT facility is scheduled to become operational in incremental stages beginning with 30,000 gallons of effluent per day and increasing to 90,000 gallons of effluent per day. The monitoring requirements in the original permit and the instant Permit are sufficient to show at each stage of operation whether the AWT facility will cause an increase in contaminants in Apalachicola Bay. Because the AWT facility is not currently operational, it is not responsible for causing any pollution. In October 1999, Mr. Johnson sold the subject property to SGI Limited Partnership, a Florida limited partnership. Mr. David Wilder is a principal in SGI Limited Partnership and vice-president of SGI Utility, LLC. On February 10, 2000, RVU filed an application with DEP to transfer the original permit to SGI Utility, LLC. By letter dated February 18, 2000, DEP granted the request to transfer the permit contingent upon approval of the sale of the AWT facility by the Florida Public Service Commission (PSC). The February 18, 2000, letter states that DEP would change its records to show SGI Utility, LLC, as owner of St. George Island Resort Village domestic wastewater treatment facility. DEP's letter states that it shall be attached to and become part of domestic wastewater Permit No. FLA010069. On September 1, 2000, SGI Utility, LLC, filed an application with DEP to renew the original permit. The application indicates that SGI Utility, LLC, is the applicant/owner/operator of the AWT facility. Mr. Wilder signed the application as the authorized representative of SGI Utility, LLC. A professional engineer signed the application in his professional capacity, as well as agent for SGI Utility, LLC. The application for permit renewal contains a copy of RVU's PSC certificate. The certificate grants RVU authority to provide wastewater service in Franklin County. The application included the following implementation schedule and completion dates: (a) Begin Construction, September 2000; (b) End Construction, March 2001; (c) Begin Reuse or Disposal, March 2001; and (d) Operational Level Attained, August 2001. SGI Utility, LLC, enclosed a check payable to DEP in the amount of $1,000 with the permit renewal application. The purpose of the check was to cover review fees. By letter dated September 28, 2000, DEP requested additional information. On or about October 5, 2000, the professional engineer for SGI Utility, LLC, sent DEP copies of the signed and sealed cover page for the permit renewal application. DEP subsequently sent SGI Utility, LLC, a copy of a Notice of Application. The notice stated that DEP had received the permit renewal application from SGI Utility, LLC. DEP expected SGI Utility, LLC, to publish the notice in a newspaper of general circulation. For the reasons set forth below, SGI Utility, LLC, never published this notice. After SGI Utility, LLC, received the Notice of Application, Mr. Wilder wrote a letter dated October 11, 2000, to DEP. The letter states that SGI Utility, LLC, as the proposed transferee of the Permit, had filed the application to renew the Permit on behalf of RVU, the current holder of the Permit. Mr. Wilder advised DEP that PSC approval was still pending. The letter states as follows in relevant part: Technically, therefore, SGI Utility, LLC is not yet the holder of the permit, although it is acting with the approval of and as the agent for Resort Village Utility, Inc. Additionally, should the publication Notice be amended to show Resort Village Utility, Inc. and SGI Utility, LLC as the applicant? By letter dated November 2, 2000, Mr. Johnson confirmed that Mr. Wilder was authorized to act on behalf of RVU with respect to all matters relating to the renewal and transfer of the Permit, including without limitation, signing all applications, documents, certificates and publication notices. Mr. Johnson's letter also states as follows in relevant part: This letter will also confirm your statement to Gary Volenac, P.E., that the form of the Notice of Application for the renewal of the permit previously submitted by the Department to Mr. Wilder by letter dated October 11, 2000, is acceptable with the exception of substituting Resort Village Utility, Inc. for SGI Utility, Inc. On November 23, 2000, the Notice of Application was published in the Apalachicola Times. The notice stated that DEP announced receipt of an application from David E. Wilder for RVU to obtain a renewal of the Permit. In a letter dated December 1, 2000, DEP advised SGI Utility, LLC, that it had been 52 days since SGI Utility, LLC, had been notified of deficiencies in the Permit renewal application. DEP reminded SGI Utility, LLC, that failure to supply the requested information might result in permit denial. Petitioner wrote DEP a letter dated December 4, 2000. Petitioner was concerned that the newspaper announcement named RVU as the applicant for renewal of the Permit instead of SGI Utility, LLC. Petitioner also noted that RVU had created a small lake on the property close to the AWT facility's largest absorption bed. Petitioner was concerned that flooding after heavy rains in the absorption bed area, together with the addition of the small lake, would present a threat of pollution to Apalachicola Bay. By letter dated December 6, 2000, SGI Utility, LLC, furnished DEP with a copy of the Notice of Application that was published in the Apalachicola Times on November 23, 2000. On January 18, 2001, DEP representatives (Joe May and Dave Krieger) met with Petitioner and an employee of SGI Utility, LLC (Morris Palmer), at the site of the AWT facility. The purpose of the visit was to conduct a routine inspection in response to the Permit renewal application and to address Petitioner's concerns. At the time of the inspection, construction of the wastewater treatment plant had not commenced. Two of the absorption beds had been installed. The third absorption bed had been flagged for construction. During the meeting on January 18, 2001, Mr. May noted that there could be a concern with rainfall run-on for one of the absorption beds. Mr. May suggested the creation of a berm at the entrance to the bed along the adjacent road to prevent rainfall run-on. Mr. May concluded that implementation of the approved stormwater plan would redirect rainfall run-off from the road. Mr. May also suggested the creation of a berm for another absorption bed. A berm between dunes adjacent to that bed would prevent run-on to the bed from high tide. During the meeting, Mr. May and Petitioner discussed the impact of heavy rainfall from a tropical storm in October 1996. The storm flooded isolated areas on St. George Island, including areas in the subject development. The isolated flooding lasted for several days. However, persuasive evidence received at final hearing indicates that the 1996 storm did not cause prolonged flooding, if any, in the absorption cells. Similar concerns about flooding in the absorption cells were addressed in the original permit. The absorption cells have been designed to ensure protection to the facility in the event of a large storm. The creation of the berms recommended by Mr. May will provide additional protection from run-on resulting from heavy rainfall. After the meeting on January 18, 2001, Morris Palmer constructed all of the berms as suggested by Mr. May. During the site visit on January 18, 2001, Mr. May and Petitioner discussed the impact of a small lake or pond created by RVU in the development after issuance of the original permit. The pond is the only change to the 58-acre development that was not contemplated prior to the issuance of the original permit. The pond is more like an isolated ditch that RVU excavated below groundwater level. RVU used the sand from the ditch to elevate the ground surface in the absorption beds and for other purposes. The pond is located approximately 527 feet from the AWT plant and 478 feet from the nearest absorption bed associated with the plant. Surface water drainage, if any, from the three absorption beds is away from the pond. Persuasive evidence indicates that the pond will not interfere with the AWT facility once it begins operation. Additionally, there is no credible evidence that possible flooding in the absorption beds will cause contaminates to collect in the pond and eventually result in a discharge of pollutants to Apalachicola Bay. Petitioner presented some evidence that the pond might act as a collection point for pollution from sources such as cars, animals, and other above-ground sources. However, the greater weight of the evidence indicates that excavation of the pond will have no impact on the results of groundwater flow modeling and contaminants transport modeling introduced at the prior hearing in DOAH Case No. 95-0863. DEP appropriately referred Petitioner's other concerns about the pond to DEP's Submerged Lands and Environmental Resources Program. Neither the original permit nor the instant Permit requires an anti-degradation study. Such studies are required only in cases involving a direct discharge to surface waters. In this case, the AWT facility will not result in a surface water discharge. During the meeting on January 18, 2001, Mr. May acknowledged that ambient monitoring data showed elevated levels of hydrocarbons and nutrients. The elevated hydrocarbons may be caused by traffic on the road and at the airport located near the absorption beds. The elevated nutrient levels can only be attributed to animals. As stated above, the AWT facility is not operational; therefore, the elevated levels of hydrocarbons and nutrients are not the result of the AWT facility. On March 30, 2001, DEP issued its Notice of Intent to Issue the Permit to RVU. The Intent to Issue indicates that RVU is the applicant for an application filed by SGI Utility, LLC, and RVU. The Permit lists RVU and SGI Utility, LLC, as co- permittees. If PSC approves the transfer of RVU's certificate to SGI Utility, LLC, DEP will transfer the Permit to SGI Utility, LLC. Until then, DEP will issue the Permit in the name of both entities. The Permit sets forth requirements for continued ambient and groundwater monitoring. These requirements, like the ones in the original permit, are sufficient to provide reasonable assurances that operation of the AWT facility will comply with Chapter 62-620, Florida Administrative Code. Under cover of a letter dated May 22, 2001, Mr. Wilder provided DEP with proof that the Notice of Intent to Issue had been published in the Apalachicola Times on April 12, 2001. Mr. Wilder signed the letter as treasurer of RVU. The published notice indicates that DEP intends to issue the Permit to RVU.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That DEP enter a final order granting RVU and SGI Utility, LLC, a renewal of Permit No. FLA010069-002. DONE AND ENTERED this 28th day of February, 2002, in Tallahassee, Leon County, Florida. SUZANNE F. HOOD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of February, 2002. COPIES FURNISHED: Thomas H. Adams Post Office Box 791 Eastpoint, Florida 32328 Craig D. Varn, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 L. Lee Williams, Jr., Esquire Williams, Gautier, Gwynn & DeLoach, P.A. 2010 Delta Boulevard Post Office Box 4128 Tallahassee, Florida 32315-4128 Kathy C. Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

Florida Laws (2) 120.569120.57
# 6
PELICAN ISLAND AUDUBON SOCIETY, GARRETT BEWKES, NED SHERWOOD, ORIN R. SMITH, STEPHANIE SMITH, AND CAROLYN STUTT vs OCULINA BANK CORPORATION AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 15-000576 (2015)
Division of Administrative Hearings, Florida Filed:Vero Beach, Florida Feb. 03, 2015 Number: 15-000576 Latest Update: Jul. 15, 2016

The Issue The issue to be determined in this case is whether Respondent Oculina Bank is entitled to a Consolidated Environmental Resource Permit and Sovereign Submerged Lands Authorization to construct three single-family homes, an access drive, surface water management system, and three single-family docks in Indian River County.

Findings Of Fact Parties Petitioner Pelican Island Audubon Society has more than 25 members residing in Indian River County, was in existence for more than a year before Oculina Bank filed its application for the Permit, and was formed for the purpose of protecting the environment, fish, and wildlife resources. Petitioners Carolyn Stutt and Garrett Bewkes live approximately one mile north of the proposed project site, on John's Island, which is on the opposite side of the Indian River Lagoon from the proposed project site. Petitioner Carolyn Stutt uses the Lagoon for boating, nature observation, nature photography, and sketching. Petitioner Garrett Bewkes uses the Lagoon for boating and fishing. Petitioners Orin Smith and Stephanie Smith did not testify at the final hearing nor present other evidence to show they have substantial interests that could be affected by the proposed project. Respondents did not stipulate to any facts that would establish the Smiths’ substantial interests. Respondent Oculina Bank has an undivided ownership interest in the project site and is the applicant for the Permit that is the subject of this proceeding. DEP is the state agency responsible for regulating construction activities in waters of the State. DEP also has authority to process applications for authorization from the Board of Trustees of the Internal Improvement Trust Fund ("Board of Trustees") to use sovereignty submerged lands for structures and activities that will preempt their use by the general public. The Project Site The project site is 15.47 acres and located along 45th Street/Gifford Dock Road in Vero Beach. It is on the western shoreline of the Indian River Lagoon. The Lagoon in this area is part of the Indian River- Malabar to Vero Beach Aquatic Preserve. It is an Outstanding Florida Water. The Lagoon is an estuary, but it is almost non-tidal in this area. There is a seasonal rise in sea level that occurs from August to November and it is during this season that waters of the Lagoon flood into adjacent wetlands. The wetlands may be inundated at other times as a result of large storms. The wetlands along the western shore of the Lagoon play a role in regional tarpon and snook fisheries. Wetlands provide essential refuges for early-stage tarpon and snook. When the wetlands are inundated, larval tarpon and snook can move into the wetlands and seek out shallow areas to avoid predation by larger fish. The project site is dominated by salt marsh wetlands. In order to control salt marsh mosquitoes, the site was impounded by the Indian River Mosquito Control District sometime in the 1950s by excavating ditches and building earthen berms or dikes along the boundaries of the site. The mean high water line of the Lagoon in this area is 0.78 feet. The berms were constructed to an elevation of about five feet, but there are now lower elevations in some places. The wetlands on the site are isolated for much of the year because the waters of the Lagoon cannot enter the wetlands unless the waters rise above the lowest berm elevations. This connection only occurs in unusually high water conditions. The impoundment berms have decreased the frequency and duration of the project site’s inundation by waters from the Lagoon. There are almost 14 acres of wetlands impounded by the berms. The impounded wetlands are dominated by salt grass. There are also mangroves, mostly white mangroves, along the side slopes of the berms. Most of the upland areas are dominated by Brazilian pepper trees and Australian pine trees, which are non- native, invasive vegetation. Within the wetlands are three ponds. Before the project site was impounded for mosquito control, it had "high marsh" vegetation such as saltwort and glasswort, as well as black and red mangroves. The impoundment resulted in the reduction of these species. There is now reduced nutrient export from the impounded wetlands to the Lagoon. The project site still provides nesting, denning, and foraging habitat for birds and other wildlife. However, the environmental health and productivity of the wetlands on the site have been reduced by the impoundment berms. The adverse effects of impounding wetlands for mosquito control are widely understood by environmental scientists. Therefore, reconnecting impounded wetlands along the Indian River Lagoon has been a local and state governmental objective. North and south of the project site are salt marsh wetlands that have been restored. To the north is a portion of the mitigation area for a development called Grand Harbor. To the south is the CGW Mitigation Bank. Both adjacent wetland areas were restored by reconnecting them to the Lagoon and removing exotic vegetation. The restored wetlands to the north and south now contain a dominance of saltwort and glasswort. They also have more black and red mangroves. These environmental improvements, as well as an increase in species diversity, are typical for former mosquito control impoundments that have been restored. In the offshore area where the three proposed docks would be constructed, there are scattered seagrasses which are found as close as 25 feet offshore and far as 100 feet offshore. They include Manatee grass, Cuban shoal grass, and Johnson’s seagrass. The Proposed Project The proposed home sites are on separate, recorded lots ranging in size from 4.5 acres to 6.5 acres. The home sites would have 6,000 square feet of "footprint." The houses would be constructed on stilts. There would be a single access driveway to the home sites, ending in a cul-de-sac. The displacement of wetlands that would have been required for the side slopes of the access drive and cul-de-sac was reduced by proposing a vertical retaining wall on the western or interior side of the drive. Each home site has a dry retention pond to store and treat stormwater runoff. The ability of these retention ponds to protect water quality is not disputed by Petitioners. The home sites and access drive would be constructed on the frontal berm that runs parallel to the shoreline. However, these project elements would require a broader and higher base than the existing berm. The total developed area would be about three acres, 1.85 acres of which is now mangrove swamp and salt marsh and 0.87 acres is ditches. One of the onsite ponds would be eliminated by the construction. The houses would be connected to public water and sewer lines. Oculina Bank would grant a perpetual conservation easement over 11.69 acres of onsite salt marsh wetlands. It would remove Brazilian Pepper trees, a non-native plant, from the site. Petitioners' original objection to the proposed project and their decision to file a petition for hearing appears to have been caused by Oculina Bank's proposal to build docks over 500 feet in length. The dock lengths in the final revision to the project vary in length from 212 to 286 feet. The docks do not extend out more than 20 percent of the width of the waterbody. The docks do not extend into the publicly maintained navigation channel of the Lagoon. Because the docks meet the length limit specified in Florida Administrative Code Chapter 18-21, they are presumed not to create a navigation hazard. To reduce shading of sea grasses, the decking material for the docks would be grated to allow sunlight to pass through the decking. There are no seagrasses at the waterward end of the docks where the terminal platforms would be located and where boats would usually be moored. The dock pilings will be wrapped with an impervious membrane to prevent the treatment chemicals from leaching into the water. In Oculina I, the Administrative Law Judge determined that the condition for vessels moored at the proposed docks should be stated as a maximum permissible draft. The Permit imposes a maximum draft for boats using the docks. Fish Survey Oculina Bank conducted a fish sampling survey in 2014 to obtain additional information about the presence of tarpon, snook, rivulus, and other fish on the project site. Twenty-three sampling stations were established and sampled from January 16, 2014 to February 16, 2014. The survey was conducted during a period of seasonal high water in order to catalog the highest number of fish that might migrate in and out of the site during high water. Oculina Bank collected five species of fish that are typically found in impounded areas. No tarpon or snook were found. Oculina Bank did not find Florida Gar or Least Killifish during the fish survey, but Dr. Taylor observed these two species on his site inspection in 2015. He also saw three to five juvenile tarpon. No testimony about snook was presented at the final hearing nor was this fish mentioned in Petitioners’ Proposed Recommended Order. Mangrove Rivulus Rivulus marmoratus, or mangrove rivulus, is designated a species of special concern by the FWC. See Fla. Admin. Code R. 68A-27.005(2)(b). Species of special concern are those species for which there are concerns regarding status and threats, but for which insufficient information is available to list the species as endangered or threatened. Some research indicates rivulus are more common than originally believed. Certain populations of rivulus in Florida are healthy and thriving. A team of scientists who participated in a biological status review of the rivulus for the FWC recommended that the rivulus be delisted. The team included Dr. Taylor and Dr. Wilcox. In Oculina I, Dr. Gilmore did not find any rivulus on the project site, but he expressed the opinion that the site had rivulus habitat and they were probably on the site. In his more recent visits to the project site in conjunction with the current proceeding, Dr. Gilmore did not observe any rivulus. Oculina Bank did not find any rivulus during its fish survey. Dr. Taylor sampled for rivulus on the site on five different days in 2015 and found five rivulus in a ditch outside (waterward) of the impoundment berm. Dr. Taylor sampled “extensively” for rivulus in the interior of the project site, but found none there. Still, he believes there are probably some in the interior. The area where the rivulus were found outside the impoundment berm would not be changed by the proposed project. However, Oculina Bank’s proposal to scrape down the impoundment berm would eliminate many crab burrows, which are habitat for the rivulus. Dr. Taylor and Dr. Wilcox agreed that rivulus are more likely to be found in areas that are tidally connected. The preponderance of the evidence does not support Petitioners’ claim that the proposed project would, on balance, adversely affect the mangrove rivulus. However, the recommended permit modifications should benefit the species. Tarpon In Oculina I, Dr. Gilmore testified that the project site was “one of the critical habitats maintaining regional tarpon fisheries.” However, he only observed one “post larval” tarpon in 2012 and none in 2014. Dr. Gilmore stated that a small mesh seine is the best method to sample for these nursery phase tarpon, but he never used such a seine to sample for them on the project site, nor did anyone else. Extensive evidence regarding on-site investigations and literature related to tarpon was presented at the final hearing. Sometimes the testimony failed to distinguish between early stage (larval) tarpon and later stage (juvenile) tarpon, whose habitat needs are not the same. The nursery and refuge functions of the wetlands on the project site relate primarily to larval tarpon, not juvenile tarpon. The shallow ponds on the project site are an important habitat type that can be used by larval tarpon when related hydrologic conditions are compatible. The preponderance of the evidence does not support the characterization of the wetlands on the project site as “critical habitat” for tarpon in the region. The current hydrologic conditions diminish the value of the nursery and refuge functions provided by the wetlands. Improving the connection between the wetlands and the Lagoon can enhance the tarpon nursery function if the improved connection is made without giving predators of larval tarpon access to the interior ponds. Dr. Gilmore stated, “you don’t have to take down the entire dike, you can create low spots.” By low spots, he means areas like the one that currently exists in the southern impoundment berm that is at about elevation 2.0 feet. The preponderance of the evidence shows the proposed project would not adversely affect the nursery function of the wetlands for tarpon if the recommended modifications are made to the Permit to improve the connection to the Lagoon while keeping the interior ponds isolated from the Lagoon for most of the year. Mitigation DEP conducted a Uniform Mitigation Assessment Methodology (“UMAM”) analysis for the proposed project that assumed direct impacts to 2.72 acres of mangrove swamp. It did not account for secondary impacts that could be caused by the proposed project. DEP’s UMAM analysis determined there would be a functional loss of 1.269 units. It further determined that these losses would be offset by the creation of 0.88 acres of salt marsh and the enhancement of 10.81 acres of mangrove swamp, resulting in a net functional gain of 2.342 units. DEP concluded that, if functional losses caused by secondary impacts were included, there would be a functional loss of 2.350 units, which still results in a net gain of 3.056 units. Because DEP determined there would be a net gain in functional value, it did not require Oculina Bank to provide additional on-site mitigation or to purchase mitigation credits from an off-site mitigation bank. The UMAM analysis performed by DEP did not adequately account for the lost tarpon nursery function and the proposed mitigation could further diminish the nursery function. The purchase of mitigation bank credits would not offset the lost nursery function because the mitigation bank was not shown to provide a nursery function.

Recommendation Based upon the foregoing Findings of Fact and Conclusion of Law, it is RECOMMENDED that the Department of Environmental Protection issue Permit No. 31-0294393-003-EI, with the following modifications: The impoundment berm will not be scraped down to mean sea level, but, instead, two new low spots will be created in the impoundment berm at an elevation of approximately 2.0 feet. A new isolated pond will be created to replace the one that will be eliminated by the construction, similar in size to the one that will be eliminated. Internal ditches and other channels will be filled as needed to eliminate predator access to the ponds. If these modifications are not made, it is recommended that the Permit be denied. DONE AND ENTERED this 1st day of June, 2016, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 1st day of June, 2016. COPIES FURNISHED: Marcy I. LaHart, Esquire Marcy I. LaHart, P.A. 4804 Southwest 45th Street Gainesville, Florida 32608-4922 (eServed) Glenn Wallace Rininger, Esquire Department of Environmental Protection Douglas Building, Mail Stop 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) Nicholas M. Gieseler, Esquire Steven Gieseler, Esquire Gieseler and Gieseler, P.A. 789 South Federal Highway, Suite 301 Stuart, Florida 34994 (eServed) Jonathan P. Steverson, Secretary Department of Environmental Protection Douglas Building, Mail Stop 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) Craig Varn, General Counsel Department of Environmental Protection Douglas Building, Mail Stop 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Stop 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed)

Florida Laws (7) 120.52120.569120.68267.061373.414403.412607.0501
# 7
ORANGE BLOSSOM BAPTIST ASSOCIATION vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-000944 (1992)
Division of Administrative Hearings, Florida Filed:Lake Wales, Florida Feb. 12, 1992 Number: 92-000944 Latest Update: Jun. 01, 1992

The Issue Whether Petitioner was wrongfully denied general permits to construct an extension to a public water supply distribution system and to construct a waste water treatment system at a camp being constructed by Petitioner.

Findings Of Fact On December 11, 1991, the Department of Environmental Regulation (DER), Ft. Myers office, received applications from the Orange Blossom Baptist Association, Petitioner, submitted by its project engineer, for general permits to install an extension to provide water to, and construct a waste water treatment facility for, a camp being built by Petitioner. These applications were reviewed by the Respondent, and on January 2, 1992, James Oni telephoned Petitioner's engineer to tell him the applications were incomplete and additional information was required. Some of this additional information was submitted by Petitioner on January 7, 1992, but the word "vertical" was left out of the application to indicate what the 18 inch separation of the water and sewer lines represented; no pump out was provided for the lift station; the flotation formula as submitted contained a typographical error where an "s" was substituted for a "5", leaving the calculation of storage capacity of the system indeterminable; the lift station was only 4.5 feet deep and should normally be 10 feet; the configuration of the sump to insure solids would settle to the bottom was not provided, nor was the amount of concrete to be used to obtain this configuration shown; and the type of equipment to be used was not clearly shown. In summary, when submitted the application was not technically correct, and it remained technically incorrect after the additional information was submitted by the applicant. General permits are required to be processed by DER within 30 days of their receipt, and if not denied within that 30 day period they must be approved regardless of their compliance with the statutes and regulations.

Recommendation It is recommended that a Final Order be entered denying Orange Blossom Baptist Association general permits to install a waste water treatment facility and to construct an extension to a public water supply distribution system in Highlands County, Florida. ORDERED this 6th day of May, 1992, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of May, 1992. COPIES FURNISHED: William N. Clark, P.E. 233 E. Park Avenue Lake Wales, FL 33853 Francine M. Ffolkes, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

# 8
ARNOLD G. AND MAUDE D. PARKER vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 90-003695 (1990)
Division of Administrative Hearings, Florida Filed:Cross City, Florida May 17, 1990 Number: 90-003695 Latest Update: Dec. 19, 1990

The Issue The issue to be resolved in this proceeding concerns whether the Petitioners are entitled to an on-site sewage disposal system ("OSDS") permit in consideration of the statutes and rules relating to approval of permits cited and discussed herein, or whether they are entitled to a variance from the strict requirements of those statutes and rules so as to allow the installation of the OSDS on their property near the Suwannee River. See Section 381.272, Florida Statutes, and Chapter 10D-6, Florida Administrative Code.

Findings Of Fact The Petitioners purchased real property located in Levy County, Florida, in 1967. That property is located in the unincorporated community of "Fowlers Bluff" on the east bank of the Suwannee River. The property is more particularly described as the west one-half of Lot 13, and the east three- quarters of Lot 14, Treasure Camp Addition, Unit 3. The lot in question is approximately 100 feet by 125 feet by 197 feet in size. There is adequate unobstructed area available for the subject system's installation, according to Respondent's Exhibit NO. 1 in evidence. The lot is part of a subdivision which was platted prior to 1956. The subject lot has available a potable water source from the public water system. Consequently, the lot is of sufficient size to meet the quarter-acre minimum requirement for the installation of septic tank and drain-field systems in situations where lots have potable water available from a public water system, which is the case in this circumstance. The effective soil depth at the drain-field installation site is greater than 42 inches below the bottom surface of the proposed drain-field trench or absorption bed location. That is, 72 inches of sand, which is a "slight limited soil" and appropriate for such installations, exist at the site. The wet season water table was shown to exist at 26 inches below the grade level. The wet season water table, pursuant to Rule 10D-6.047(2) Florida Administrative Code, must be at least 24 inches below the bottom surface of the drain-field trench or absorption bed. Consequently, the wet season water table in this situation is not sufficient in depth for the proposed installation to meet this provision of the Respondent's rules. The Petitioners seek to gain approval for a system to serve a single- family residence of approximately 2,000 heated and cooled square feet, with a "standard" 350 gallons per day sewage flow. The residence would contain three bedrooms, as presently envisioned. The Petitioners' Exhibit NO. 1 establishes a benchmark elevation for the grade level of the proposed OSDS installation site of 7.48 feet above mean sea level ("MSL"). The actual grade elevation is 0.8 feet below that benchmark elevation. That is, the elevation of the grade of the property is 6.72 feet above MSL at the proposed installation site., The ten-year flood elevation for the proposed installation site, however, is 9 feet above MSL, as verified by a report prepared by the Suwannee River Water Management District, admitted into evidence and which was submitted to the Respondent by the Petitioners in the application process. The property also lies within the regulatory floodway of the Suwannee R for purposes of Rule 10D-6.047(6), Florida Administrative Code. Testimony by Mr. Parker, as well as the Respondent's evidence through Mr. May, establishes that the property in the past has had approximately 30 inches of fill placed on it. Because of this, the grade level elevation is in fairly-close proximity to the ten-year flood elevation and because of the prevailing slight limited soil type down to a depth of six feet, the property was shown to be generally amenable to installation of a mounded septic tank and drain-field disposal system, which mounding could raise the property so that the bottom of the drain-field trench or absorption bed would not be within the ten- year flood elevation. As Mr. May indicated by letter dated March 1, 1990 to Mr. Parker, the lot could be filled utilizing slight limited soil so that a mound to contain the septic tank and drain field of no more than the required 36 inches, pursuant to Rule 10D-06.0493(b), Florida Administrative Code, might be utilized. That letter, in evidence, also indicates that if the lot, or a portion of it, is filled, the fill shall extend a minimum of 20 feet in all directions beyond the perimeter of the mound base. The lot was shown to be of sufficient size to accommodate such a perimeter area of fill. In that same letter, Mr. May advised Mr. Parker that he had the right to request a variance from the provisions of Chapter 10D-6 Florida Administrative Code, since his property, in Mr. May's view, did not meet the criteria in that regulatory chapter for the issuance of an actual permit. The record does not reflect that an actual variance application had been filed, however. It would thus seem that this property is amenable to a reasonable alternative solution to a conventional, subterranean septic tank and drain-field system by the use of the "mounding process". That alternative, however, pursuant to Rule 10D-6.047(6), Florida Administrative Code, would require the certification of a registered professional engineer to the effect that the installation of such a mound could be done ,in such a way as not to raise the "base flood" level. This is because the property lies within the regulatory floodway of the ,Suwannee River; and under the rule section cited last above, a `certification must be made that the base flood level will not be raised by such a mounded system installation for property lying in the regulatory floodway. The Petitioners adduced no such engineering testimony or evidence to establish that if the system were installed with the mounding process, the base flood level would not be raised. In addition to the evidence culminating in the above Findings of Fact, the Petitioners offered general testimony to the effect that they had purchased the property in question for purposes of both having a "retirement rest egg" and a place to live should they choose to live on the property. The Petitioners established that they, like numerous other OSDS permit applicants in similar proceedings, are undergoing a hardship because they purchased the property for residential purposes or for re-sale for residential purposes and cannot construct a residence and live on the property or sell it for that purpose because of the inability to obtain a permit. The Petitioners' proof, in terms of the variance criteria noted below, is inadequate to show that there are no alternative systems available which will adequately dispose of and treat the sewage to be expected, nor did the Petitioners establish that installation of the system presently proposed would only constitute a minor deviation from the requirements of the Respondent's OSDS permitting rules, in terms of having no adverse effect on the health of the Petitioners, the general public, or upon the surface or ground waters involved in the vicinity of the site. Although the Petitioners did not formally apply for a variance, no adequate proof in these two particulars was offered so as to justify the grant of a variance; however, it was established that the property was platted prior to 1972 for purposes of the relaxed consideration embodied in the variance rule and statute for this circumstance. The Respondent now asserts, however, that the Petitioners should not be accorded the opportunity to avail themselves of the variance procedure because of the Respondent's interpretation of the Governor's Executive Order 90-14, which it opines precludes it from granting any variances or permits for OSDS's within the ten-year flood elevation. The Governor's Executive Order, which incorporated the "Suwannee River Task Force" recommendation to preclude such systems beneath the ten- year flood elevation, was entered on January 17, 1990. The Respondent has, in effect, interpreted that Executive Order as precluding it from exercising its discretion to entertain and grant or deny variance applications.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is therefore, RECOMMENDED that a Final Order be entered denying the application for the subject permit, without prejudice to a later application for a variance or a later application for an OSDS permit based upon additional and changed facts and circumstances. DONE AND ENTERED this 19th day of December, 1990, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of December, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 90-3695 The Petitioners submitted no proposed findings of fact. Respondent's Proposed Findings of Fact: 1-8. Accepted. 9. Rejected, as immaterial. 10-11. Accepted. COPIES FURNISHED: Sam Power, Agency Clerk Department of HRS 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Linda K. Harris, Esquire General Counsel Department of HRS 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Arnold G. Parker P.O. Box 467 Chiefland, Florida 32626 Frances S. Childers, Esquire Assistant District III Legal Counsel Department of HRS 1000 Northeast 16th Avenue Gainesville, Florida 32609

Florida Laws (2) 120.577.48
# 9
WILLIAM H. AND BETSY K. LANIER vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 90-003112 (1990)
Division of Administrative Hearings, Florida Filed:Cross City, Florida May 17, 1990 Number: 90-003112 Latest Update: Dec. 21, 1990

The Issue The issue for consideration in this case concerns whether the Petitioners are entitled to an on-site sewage disposal system ("OSDS") permit authorizing the installation of an OSDS on property which they own near the Suwannee River in Dixie County, Florida, in accordance with the permitting requirements of Section 381.272, Florida Statutes, and Chapter 10D-6, Florida Administrative Code.

Findings Of Fact The Petitioners are the owners of certain real property located in Dixie County, Florida, in the proximity of the Suwannee River. The property is described as Lot 38, Highpoint Suwannee Riverfront Estates. The lot in question is 82 feet by 141 feet in size and was purchased in April, 1988 for approximately $5000.00. The lot, and the subdivision it is in, was platted in 1983. On February 21, 1990, the Petitioners made application for an on-site sewage disposal system ("OSDS") permit, seeking to install such a system on this lot in order to be able to construct a vacation cottage on the lot The proposed cottage would contain one bedroom and would have a heated and cooled area of approximately 500 square feet. Upon reviewing the application, the, Respondent informed the Petitioners that they would need to have a surveyor establish the elevation of their lot, and particularly the site of the proposed OSDS installation, as well as to establish, through contact with the Suwannee River Water Management District, the ten-year flood elevation for the property. Accordingly, the Petitioners obtained a survey by `Mr. Herbert Raker, a registered land surveyor of Cross City, Florida. That survey shows a benchmark elevation of 13.09 feet above mean sea level ("MSL") That benchmark elevation is six inches above the actual grade surface of the lot so that the elevation at the proposed OSDS installation site is 12.59 feet above MSL. The ten-year flood elevation for the property is 15 feet above MSL, as established by data from the Suwannee River Water Management District contained in a report which is in evidence as Respondent's Exhibit 1. That flood elevation data was submitted to the Respondent by the Petitioners with the application for the OSDS permit. The property in question is located within the ten- year flood plain of the Suwannee River, and it is also located within the regulatory floodway of the River. On April 24, 1990, after advising the Petitioners of the denial of the OSDS permit application, the Respondent, by letter, advised the Petitioners that they should pursue a formal administrative proceeding rather than file an informal variance application before the Respondent's own Variance Board. The Respondent took the position that a variance could not be granted from the requirements of Rule 10D- 6.47(6), Florida Administrative Code, because the subject property was located within the ten-year flood plain of the Suwannee River and because of the Respondent's interpretation of the affect of the Governor's Executive Order 90- 14, which adopted by reference the Suwannee River Task Force recommendation that all such systems be prohibited within the ten-year flood plain. The Respondent thus declined to exercise its discretion, accorded it in the statute and rule cited hereinbelow, to entertain and consider a variance application. Finally, it is established that the lot in question is not subject to frequent flooding; but because the surface grade is beneath the ten-year flood elevation, the bottom of the drain field trenches absorption bed to be installed would also be beneath the ten-year flood elevation. In other respects, the property is a amenable to the installation of an effective OSDS because the wet season water table is 48 inches beneath the surface grade and would be more than 24 inches beneath the proposed drain field. The normal water table is approximately 60 inches beneath the surface grade. Appropriate limited soils are present beneath the first six inches of soil below the surface and consist of fine sand, light brown and brown fine sand, down to 60 inches, which is appropriate for effective subterranean treatment and disposal of sewage effluent. The Petitioners established a definite hardship on their part by the fact that they have paid a substantial sum for the lot and are now unable to develop it unless they receive entitlement to an OSDS or some reasonable alternative. In that regard, no sufficient proof of truly effective, reasonable alternatives was established by the Petitioners. However, they did establish that an anaerobic septic tank and drain field disposal system might be an effective alternative treatment and disposal method for the property in question. An aerobic system involves the injection of air into the attendant septic tank to support aerobic bacteria which break down and treat sewage at a faster, more effective rate than does the normal anaerobic bacteria-based system. The resulting effluent is substantially lower in BOD and suspended solids than is the effluent from the normal subterranean and anaerobic septic tank and drain field disposal system. The problem with such an aerobic system is that it involves mechanical equipment, especially, an external electric motor and pump to force air into the system. This is disadvantageous in that, if the equipment suffers a breakdown, then treatment and appropriate disposal of the effluent stops. The untreated sewage can then rise to the surface of the property or otherwise pollute ground or surface waters and potentially cause a public health hazard. Thus, such systems would require inspection periodically to insure that they are in adequate working order because if the mechanical system malfunctions, the system will continue to put effluent through its drain field without adequate treatment. In this circumstance, the occupants of the dwelling served by the system might not notice for long periods of time that it is inoperative because the system will continue to dispose of effluent, but just of an untreated nature. Accordingly, when the motor and air pump system becomes inoperative, there is less incentive for the owner to repair it. Thus, it is likely that if such a system were installed, some means would have to be found to insure that the owner keeps the system in good repair and working order. The means by which such an arrangement for insuring that such an aerobic system works properly at all times was not established in this record, however. Consequently, the Petitioners failed to establish that reasonable alternatives to the proposed conventional system exist and what they might consist of.

Recommendation Having considered the foregoing findings of Fact, Conclusions of Law, the evidence of record, the carndor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is therefore, RECOMMENDED that a Final Order be entered denying the Petitioners' application for an OSDS permit. DONE AND ENTERED this 21st day of December, 1990, in Tallahassee, Leon County, Florida P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of December, 1990. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 90-3112 The Petitioners filed no proposed findings of fact. Respondent's Proposed Findings of Fact: 1-9. Accepted. COPIES FURNISHED: Sam Power, Agency Clerk Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Linda K. Harris, Esquire General Counsel Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Betsy K. Lanier, pro se P.O. Box 238 Old Town, FL 32680 Frances S. Childers, Esq. Assistant District III Legal Counsel Department of HRS 1000 N.E. 16th Avenue Gainesville, FL 32609

Florida Laws (1) 120.57
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer