The Issue The issues in this case are whether Respondent violated certain rules of the Department of Environmental Protection (Department) related to petroleum contamination site cleanup criteria as alleged in the Department’s Notice of Violation, Orders for Corrective Action, and Administrative Penalty Assessment (NOV); whether Respondent is liable for the administrative fines and investigative costs assessed by the Department; whether mitigation of the administrative fine is appropriate; and whether Respondent should be required to take the corrective action described in the NOV.
Findings Of Fact The Parties The Department is the state agency charged with the power and duty to administer and enforce the provisions of Chapters 376 and 403, Florida Statutes (2008),1 and the rules promulgated in Florida Administrative Code Title 62, pertaining to petroleum contamination. Respondent Z.K. Mart, Inc., is a Florida corporation, and owns and operates a retail fueling facility (DEP Facility No. 8507091) located at 5077 Normand Boulevard, Jacksonville, Florida (“the facility”). In January 2004, soil sampling in conjunction with the removal of an underground petroleum storage tank at the facility showed petroleum contamination. Respondent reported the contamination to the Department in a Discharge Report Form on January 29, 2004. Respondent removed the tank that was the source of the contamination, conducted source removal activities, and submitted various reports to the Department, including a Site Assessment Report (SAR), submitted in February 2006. In March 2006, the Department determined the SAR was incomplete and requested that Respondent submit a SAR addendum. To date, Respondent has not submitted the SAR addendum. Respondent’s insurer, Mid-Continent Casualty Company, refused coverage for the assessment and cleanup costs associated with the reported discharge, asserting that the contamination “arose out of” the tank removal. Respondent contends that the contamination occurred before the tank removal. In October 2004, Respondent sued Mid-Continent in the circuit court for Duval County for wrongful denial of coverage. Respondent requested that the Department also file suit against Mid-Continent, pursuant to Section 376.309(2), Florida Statutes, for violating financial responsibility requirements. In December 2008, the Department sued Mid-Continent. The litigation is ongoing. Respondent spent over $300,000 to remove 2,503 tons of contaminated soil and to conduct site assessment activities associated with the reported contamination. In August, September, and October 2006, Respondent filed financial affidavits and additional materials with the Department in support of Respondent’s claim that it was unable to pay for additional assessment work. By letter dated November 3, 2008, the Department rejected Respondent’s claim that it was financially unable to undertake the requested site assessment. Respondent submitted a financial affidavit prepared by Abdul Khan, the vice president and secretary of Z.K. Mart, Inc., which states that the net income of Respondent was $36,479 at the end of 2005. Financial information for later years, including 2008, was also submitted by Respondent. However, no financial analysis was included. No evidence was submitted to establish the estimated costs of future site assessment activities. It cannot be determined from the financial information in the record whether Respondent is currently financially able to conduct additional site assessment activities. The Department states in the NOV that Count I constitutes a violation of Florida Administrative Code Rule 62- 770.800(5). That rule provides that it is a violation of Chapters 376 and 403, Florida Statutes, for a responsible party to fail to submit additional information or meet any time frame “herein.” The Department explained that Count I was intended to charge Respondent with failing to complete site assessment. The only applicable time frame in Florida Administrative Code Rule 62-770.800, entitled “Time Schedules,” is in subsection (3), which requires a responsible party to submit additional information within 60 days of the Department’s request for the information. That violation, however, is more specifically charged in Count II. Count II of the NOV charges Respondent with violating Florida Administrative Code Rule 62-770.600(11), which states that, if a SAR is incomplete, the Department shall inform the responsible party and the responsible party shall submit a SAR addendum within 60 days. Counts I and II charge Respondent with the same offense, failing to submit requested information within 60 days of the request. As stated in the Conclusions of Law, Respondent cannot be made to pay administrative fines under a duplicate charge. Count III of the NOV charges Respondent with liability for the Department’s investigative costs of $500 incurred in conjunction with this enforcement matter. These are nominal costs and were never disputed by Respondent.
The Issue The issue is whether Florida Petroleum Markers and Convenience Store Association (Florida Petroleum) is entitled to reasonable attorney’s fees and costs pursuant to Section 120.595(2), Florida Statutes, and if so, in what amount.1
Findings Of Fact Introduction Florida Petroleum is the prevailing party in the underlying rule challenge and requests an award of reasonable attorney's fees pursuant to Section 120.595(2), Florida Statutes.2 Florida Petroleum prevailed in DOAH Case No. 05-0529RP on one of two challenged proposed rule revisions to Florida Administrative Code Chapter 62-770, which governs cleanup of petroleum contamination. Proposed rule 62-770.220(3)(b) was held to be an "invalid exercise of delegated legislative authority." Proposed rule 62-770.220(4), was "not an invalid exercise of delegated legislative authority, except insofar as notice must be given every five years to persons other than 'local governments and owners of any property into which the point of compliance is allowed to extend,' as provided in Section 376.3071(5)(b)2., Florida Statutes."3 The Department argues that its actions were "substantially justified" because there was a reasonable basis in law and fact at the time its actions were taken. The proposed rules were approved by the Environmental Regulation Commission (ERC) on February 2, 2005, which is the time when the Department's "actions were taken." The Department does not argue that special circumstances exist that would make the award of fees unjust. Department Contamination Programs The Department's Division of Waste Management is comprised of the Bureau of Petroleum Storage Systems, the Bureau of Waste Cleanup, and the Bureau of Solid and Hazardous Waste. The Bureau of Petroleum Storage Systems administers the state's petroleum contamination cleanup program. This cleanup program encompasses the technical oversight, management, and administrative activities necessary to prioritize, assess, and cleanup sites contaminated by discharges of petroleum and petroleum products from petroleum storage systems. There are approximately 23,000 petroleum-contaminated sites statewide. Florida Administrative Code Chapter 62-770 establishes petroleum contamination site cleanup criteria. These criteria are established for the purposes of protecting the public health and the environment and for determining, on a site-specific basis, the rehabilitation program tasks that comprise a site rehabilitation program and the levels at which a rehabilitation program task and site rehabilitation program may be deemed complete. Fla. Admin. Code R. 62-770.160(8). The petroleum contamination cleanup program incorporates risk-based corrective action (RBCA) principles to achieve protection of human health, public safety, and the environment in a cost-effective manner. The phased RBCA process is iterative and tailors site rehabilitation tasks to site-specific conditions and risks. Fla. Admin. Code R. 62-770.160(8). The Bureau of Waste Cleanup administers the state's drycleaning solvent cleanup program. This program is for the cleanup of property that is contaminated with drycleaning solvents as a result of the operations of a drycleaning facility or wholesale supply facility. Florida Administrative Code Chapter 62-782 establishes drycleaning solvent cleanup criteria, established for the purposes of protecting the human health, public safety and the environment under actual circumstances of exposure and for determining, on a site-specific basis, the rehabilitation program tasks that comprise a site rehabilitation program and the levels at which a rehabilitation program task and site rehabilitation program may be deemed complete. Fla. Admin. Code R. 62-782.150(1). The drycleaning solvent cleanup program, like the petroleum contamination cleanup program, the brownfield site rehabilitation program, and the global RBCA contamination cleanup program mentioned below, incorporates RBCA principles to achieve protection of human health and the environment in a cost-effective manner. Fla. Admin. Code R. 62-782.150(1) and 62-785.150(1). In 2003, the Legislature adopted Section 376.30701, Florida Statutes, which authorizes the Department to adopt rule criteria for the implementation of what is referred to as "global RBCA," which extends the RBCA process to contaminated sites where legal responsibility for site rehabilitation exists pursuant to Chapter 376 or Chapter 403, Florida Statutes. Global RBCA is a cleanup program for contaminated sites that do not fall within one of the Department's other contamination cleanup programs. Department Rulemaking Efforts After the passage of Section 376.30701(2), Florida Statutes, the Department initiated rulemaking to develop Florida Administrative Code Chapter 62-780 (global RBCA). Section 376.30701(2) established July 1, 2004, as the date the Department was to adopt rule criteria to implement the global RBCA contamination cleanup program. At the same time, the Department initiated rulemaking with respect to revisions to Florida Administrative Code Chapters 62-770 (petroleum), Chapter 62-782 (drycleaning solvents), and Chapter 62-785 (brownfields). This decision was predicated on the similarities among the four waste cleanup programs and the Department's desire to ensure a consistent approach across the four programs and pursuant to one large rulemaking effort. As such, the Department sought to include the same notification provisions in each rule for consistency purposes. (T 33-34, 55). However, the Department also recognized at the time that the notice provision for RBCA for petroleum contamination cleanups, i.e., Section 376.3071(5)(b)2., was different from the notice provisions for RBCA cleanups for the drycleaning solvent (Section 376.3078(4)(b)), brownfields (Section 376.81(1)(b)), and global RBCA (Section 376.30701(2)(b)) programs. (T 69, 115, 126-129). In each of these three statutes, the Legislature expressly expanded the class of persons to whom notice is required to be given and expressly referred to a specific type of notice to be given (actual or constructive) depending on the class of persons designated to receive notice. Each of the latter statutes was enacted after, and presumably with knowledge of Section 376.3071(5)(b)2., which was materially amended in material part in 1996 to add, in part, the notice provision. See Ch. 96-277, § 5, at 1131, 1135-1136, Laws of Fla. In May 2004, the Department became aware of concerns with regard to on-going efforts to assess the groundwater contamination at the former American Beryllium plant in Tallevast, Manatee County, Florida. (The party's refer to the city as Tallavast, whereas the Transcript (T 36) and DEP Exhibit 1 refer to the city as Tallevast.) For approximately two years, the owner of the plant, Lockheed Martin, had been conducting an on-going assessment of the extent of the solvent (trichloroethylene) contamination. The Department was concerned that there were residential areas located adjacent to and in the immediate vicinity of the former industrial plant. In May 2004, it became apparent that there were problems with certain assumptions concerning the assessment of the groundwater contamination. First, there had been an erroneous assumption that the contamination plume was small and located predominantly on-site. Second, based on well surveys, there was an assumption that there were no human health exposure points in the form of contaminated off-site potable water wells. Significant concerns arose when it became apparent the contamination plume was more extensive than anticipated and had migrated off-site. These concerns were exacerbated when it became apparent that groundwater contamination was impacting off-site potable water wells. Tallevast residents raised concerns that they were being exposed to contamination and that they were never properly notified by the Department, upon the initial discovery of the groundwater contamination. Tallevast residents were also concerned about whether the Department had failed to properly notify then once it was discovered the groundwater contamination had migrated off-site. The problems experienced at Tallevast emphasized to the Department the need to explore available avenues to enhance public notification procedures as a whole.4, 5 The Department asserted as to a reasonable basis in fact for the proposed rules, that contamination affecting Tallevast residents provided an impetus for the Department in May 2004 to address notification of contamination to affected off-site property owners. The situation in Tallevast arose because well surveys failed to indicate the extent of the contamination plume and that residents were using private wells for potable water. The Department's objective was to make sure that if there was exposure potential, the potentially affected parties should be notified. The Department seems to agree that the failure to discover the contamination of the potable wells in Tallevast occurred during the assessment phase of the cleanup and that it had not yet gotten to the stage of determining the remediation strategy. (T 45-46). The Department's stated concerns regarding Tallevast are not specifically addressed by proposed rule 62-770.220(3)(b) and (4). (T 74-75, 95-96). The Department’s procedure for granting a temporary extension of the point of compliance is that the responsible party will propose such an extension in its remedial action plan. (The four cleanup programs provide for the establishment of a TPOC.) The Department will then issue its notice of intended agency action, notice of the agency action will be provided to the enumerated persons, and the persons receiving notice will have a 30-day comment period. (T 149-155). (Pursuant to proposed rule 62-770.220(3)(a), the person responsible for site rehabilitation (PRSR) "shall provide" actual notice "to the appropriate County Health Department and all record owners of any real property into which the point of compliance is allowed to extend . . . ." In this regard, as Mr. Chisolm testified, the process is "similar to a permit.") Mr. Sole testified that, in the course of rulemaking, Florida Petroleum argued to the Department that the "petroleum statute under 376.3071 is different as it addresses the temporary point of compliance. It's not as prescriptive as the other statutory provisions for Risk-Based Corrective Action and the dry-cleaning, the Brownfields, and now the Global RBCA [statutes]. And their concern was that because it's not as prescriptive, [the Department] should not be establishing these additional notice provisions, such as constructive notice . . . But their fear was or concerns . . . were that you're going to engender a lot of litigation that's unnecessary because, as soon as you say the word 'contamination,' somebody is going to want to sue me . . . . And I understood that position. But at the same time, the lessons that we learned were that failure to provide that notice, unfortunately, can cause exposure and can cause a public health concern; and [the Department] needed to balance the two." (T 63-64, 122). Mr. Chisolm testified, in part, about the development of the constructive notice provision in proposed rule 62- 770.220(3)(b) and explained that the global RBCA, brownfields, and drycleaning solvent statutes required constructive notice to residents and business tenants of impacted properties.6 Mr. Chisolm further explained: So, if you're going to give notice to the legal owners of a piece of property, many cases there are tenants there. And they may not get the word, and they may be the ones that are drinking the water. The same with business tenants. So the idea was let's give notice to the people who are going to be or potentially going to be affected by this contamination, which is, after all, under the property which they may be inhabiting and using. So that was the purpose for the rule change in this case. Let's give notice to everybody who could potentially be affected by the rule, by the contamination beyond the property boundaries . . . . The whole idea behind RBCA, Risk- Based Corrective Actions, is that, if there's no exposure, there's no risk. There's no danger to the individual, to any individual. (T 116-117).
The Issue The issue for determination is whether Redd’s Cleaners, DEP Facility No. 139502588 is eligible for state-administered cleanup under the Drycleaning Solvent Cleanup Program pursuant to Section 376.3078, Florida Statutes.
Findings Of Fact Metropolitan Dade County (Petitioner) is a political subdivision of the State of Florida. Pursuant to Chapter 24, Metropolitan Dade County Code, Petitioner regulates, among other things, the use, storage, and disposal of industrial wastes and hazardous substances in Dade County. Sekoff Investments, Inc. (Intervenor) is a Florida corporation and is the owner of commercial real property located at 5821 Ponce de Leon Boulevard, Coral Gables, Florida. Intervenor is a "real property owner" as defined by Section 376.301(25), Florida Statutes (1995). Florida Department of Environmental Protection (Respondent DEP) is an agency of the State of Florida. Pursuant to Chapters 20, 376, and 403, Florida Statutes, Respondent DEP has jurisdiction, among other things, over the regulation and protection of the State's surface waters, groundwater, and other natural resources. From 1956 to December 1994, Intervenor leased its property to "drycleaning facilities," as that term is defined by Section 376.301(8), Florida Statutes (1995), which operated under the name "Redd's Cleaners" (Respondent Cleaners). Intervenor was not an owner of the drycleaning facilities, nor did it participate in their management or operation. Intervenor's property has never been served by sewers and has a septic tank. Intervenor's property is not in an area served by private drinking water wells or in a cone of influence of a County wellfield. Starting in 1988, Petitioner began inspecting drycleaning facilities and requiring them to obtain operating permits pursuant to Section 24, Metropolitan Dade County Code. On February 28, 1989, Petitioner issued Operating Permit No. IW5-3387-88 to Jen-Dan, Inc., d/b/a Respondent Cleaners. Operating Permit Nos. IW5-3387-89, IW5-3387-90, IW5-3387-91, IW5-3387-92, and IW5-3387-94 were subsequently issued for the period between April, 1989 through April, 1995. On October 14, 1993, Petitioner collected soil and groundwater samples from the septic tank and storm drain/soakage pit at Intervenor's property and discovered elevated levels of perchloroethylene, a "drycleaning solvent," as that term is defined by Section 376.301(9), Florida Statutes (1995). On March 15, 1994, Petitioner issued Respondent Cleaners and Intervenor a Notice of Violation and Orders for Corrective Action (NOV). The NOV provided that the presence of drycleaning solvents in the septic tank and storm drain/soakage pit violated Sections 24-11, 24-13, 24-14, 24-26, and 24-55, Metropolitan Dade County Code, and ordered Respondent Cleaners and Intervenor to submit a formal plan for the assessment and cleanup of the drycleaning solvent contamination. The cited provisions of the Dade County Code generally provide that it is unlawful to throw, drain, run, seep, or otherwise discharge industrial or liquid wastes into septic tanks, sewers, or waters of the County; to cause or maintain a nuisance or sanitary nuisance as defined by the Metropolitan Dade County Code; or to violate any provision or condition of an operating permit. Intervenor hired the environmental consulting firm, REP Associates, Inc., which prepared and submitted to Petitioner a Contamination Assessment Plan (CAP) dated April 21, 1994. By letter dated May 5, 1994, Petitioner approved the CAP with modifications, and required the immediate pump out and disposal of the contaminated contents of the septic tank and storm drain/soakage pit. In May and June, 1994, Intervenor began collecting soil, groundwater, and sediment samples from the septic tank and storm drain, and installed a groundwater monitoring well, as required by the CAP. The test results disclosed the presence of drycleaning solvents in the soils and groundwater at Intervenor's property. The contaminants in the septic tank and storm drain/soakage pit were a source or a likely source of soil and groundwater contamination at the facility. On May 8, 1994, Respondent DEP announced that it was suspending all enforcement actions against drycleaning facilities based on the Florida Legislature's anticipated passage of the Florida Drycleaning Solvent Contamination Cleanup Act (Drycleaning Act). On June 3, 1994, the Drycleaning Act became effective. On August 23, 1994, Petitioner mailed Intervenor and Respondent Cleaners a Final Notice Prior to Court Action stating that they were not in strict compliance with the deadlines set forth in the NOV. On September 22, 1994, Intervenor submitted to Petitioner a Report of Sampling and Analysis summarizing the results of the work performed in May and June, 1994. By letter dated September 23, 1994, Intervenor further advised Petitioner that it would be applying for participation in the Drycleaning Solvent Contamination Cleanup Program (Drycleaning Cleanup Program) as soon as Respondent DEP promulgated the necessary implementation rules. Intervenor proposed that Petitioner approve a no further action plan pending its notice of eligibility under the Drycleaning Act. By letter dated September 30, 1994, Petitioner disapproved Intervenor's no further action plan. Petitioner again notified Intervenor and Respondent Cleaners that they must immediately remove and dispose of the contents of the septic tank and storm drain. In December, 1994, Intervenor evicted Respondent Cleaners. Since that date, the former drycleaning facility has remained vacant. On July 18, 1995, Intervenor's environmental consultants removed and properly disposed of the contents of the septic tank and storm drain. 18.1 On October 3, 1995, Intervenor's consultants advanced new soil borings and installed a new groundwater monitoring well. Groundwater samples were collected on October 24, 1995. 19.2 On February 21, 1996, Intervenor submitted its Contamination Assessment Report Addendum to Petitioner, summarizing the results of the work performed in July and October, 1995, and requesting a monitoring only plan (MOP). By letter dated February 29, 1996, Petitioner disapproved Intervenor's proposed MOP. 20. In March 1996, Respondent DEP began to accept applications for the Drycleaning Cleanup Program. Intervenor submitted its application for Respondent Cleaners on March 8, 1996. 21.3 By letter dated June 11, 1996, Respondent DEP approved Intervenor's application and determined that Respondent Cleaners' drycleaning facility was eligible to participate in the Drycleaning Cleanup Program. By Petition for Formal Administrative Hearing served July 11, 1996, Petitioner appealed Respondent DEP's eligibility determination. According to Petitioner, Intervenor's failure to timely comply with Petitioner's order to assess and remediate Respondent Cleaners constitutes gross negligence in the operation of the cleaner, thereby precluding its eligibility in the Drycleaning Cleanup Program.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order finding Redd's Cleaners, DEP Facility No. 139502588 eligible to participate in the Drycleaning Solvent Contamination Cleanup Program.DONE AND ENTERED this 14th day of May, 1997, in Tallahassee, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of May, 1997.
The Issue The issue in this case is whether Petitioner's site located at 13292 N.W. 118th Avenue in Miami, Florida is eligible for reimbursement of the costs of petroleum contamination cleanup pursuant to Section 376.3071(12), Florida Statutes.
Findings Of Fact Petitioner Rinker Material Corporation ("Rinker") owns and operates a site known as the Rinker FEC Quarry located at 13292 N.W. 118th Avenue, Miami, Florida 33127 (the "site"). At the Site, Rinker operated three (3) one thousand (1,000) gallon tanks which stored waste oil, virgin oil and hydraulic fluid. The DER Facility ID Number for the Site is 138628827. On December 2, 1988, Petitioner, as part of a tank replacement program that it was attempting to conduct in compliance with the applicable state and county regulations, began excavating the three underground storage tanks at the Site. During the excavation, a visible sheen was discovered. At the time of the excavation on December 2, 1988, Alan Gillespie of the Dade County Environmental Resource Management (DERM) was present to conduct a closure inspection of the Site. The December 2, 1988 closure inspection was conducted for Dade County DERM in its own capacity and not as an agent for DER. The purpose of the December 2, 1988 visit by Alan Gillespie was to inspect the removal and closure of the three 1,000 gallon tanks containing, respectively, waste oil, new oil and hydraulic fluid. Mr. Gillespie's inspection indicated that, while there appeared to be no holes in the tanks, free product was visible. Mr. Gillespie noted in his inspection report, dated December 2, 1988, that the contamination was not caused by a tank leak, but, instead, by overspills caused by the pouring of waste oil into the tank, spilling locally around the riser and then contaminating the soil around the tank. Rinker took samples at the Site and submitted them to a laboratory for analysis. It is not clear when the laboratory report was returned, but it generally takes two (2) weeks to obtain the laboratory analysis. Upon receipt of the laboratory report, Rinker initiated its efforts to apply for participation in the Inland Protection Trust Fund for reimbursement or site rehabilitation. In order to participate in the Inland Protection Trust Fund, an applicant was required to submit an Early Detection Incentive Program Notice (the "EDI Form") to DER prior to midnight on December 31,. 1988. The back of the EDI Form states that the form must be filed with and received by DER during the 15 month grace period beginning July 1, 1986 and ending October 1, 1987. The EDI program was; originally scheduled to end on September 30, 1987. However, the deadline for filing was extended by the legislature to December 31, 1988. The EDI Notification Form was not amended to change the dates to reflect subsequent amendments to the reporting date made by the legislature. While the back of the EDI Application Form indicates that the notification form must be filed with and received by DER on or prior to the initial deadline, DER considered as timely all applications with a postmark on or before the extended deadline of December 31, 1988. Petitioner's EDI Form for the Site was prepared by William Voshell, environmental manager for Rinker. Mr. Voshell was out of the state during the last few days of December, 1988. Petitioner's EDI Form was reviewed and signed by William Payne as Vice President of Real Estate for Rinker, on Friday, December 30, 1988. William Payne was informed by Mr. Voshell that the EDI Forms needed to be sent out before the end of the year. A cover letter accompanying the EDI Form for the Site was signed for Mr. Voshell by his secretary, Linda Vasquez on December 30, 1988. After signing the EDI Form, William Payne returned the application to Linda Vasquez to "process to mail". He reminded her that it had to be mailed that day. Ms. Vasquez placed the EDI Form and the cover letter in the Petitioner's mail system on December 30, 1988. The Certified Mail Number P 533059801 appears on the envelope containing Petitioner's EDI Form. January 3, 1989 was the first business day of 1989. The envelope containing the EDI Form was postmarked January 3, 1989. A certified mail return receipt attached to the envelope containing the EDI Form and cover letter shows that the return was stamped by the post office on January 3, 1989. The postal receipt for the EDI Form and cover letter was returned to Rinker from the post office on January 3, 1989. DER received Petitioner's EDI Form for the Site on January 9, 1989. Petitioner's normal procedure is to internally meter regular mail and affix a postmark date. However, certified or registered mail is metered and taken to the post office for processing. Registered mail received in the Petitioner's mailroom on December 30, 1988 should have been metered and taken to the post office for processing the same day or at the latest the next business day (December 31st, a Saturday). After the EDI Form was filed but prior to the eligibility determination, Petitioner was required to submit Site characterization information and documentation of the Site conditions before the initiation of cleanup. The evidence did not establish the expense or costs incurred by Rinker in gathering this information. Prior to ruling on Petitioner's EDI application, DER, through DERM, conducted an eligibility inspection at the Site. Alan Gillespie of DERM conducted the EDI eligibility inspection on April 20, 1989. During an EDI inspection, the inspector examines and reports on the existing conditions of a facility including: recordkeeping, the age of the tanks and the conditions of the monitoring wells and whether there is any negligence involved with the contamination that has occurred. During the April 20, 1989 inspection, Alan Gillespie reported that the three 1,000 gallon underground tanks had been removed and replaced with a new aboveground petroleum storage system. On the EDI inspection report, Mr. Gillespie reported evidence of soil contamination and/or recent product loss and noted that such contamination was discovered at the time of tank removal. After completion of the April 20, 1989 inspection report, Mr. Gillespie's supervisor at DERM sent the report to DER in Tallahassee. In 1989, final Early Detection Incentive Program or Reimbursement Program eligibility determinations were made in Tallahassee by DER. At the time of the EDI eligibility inspection of the Site on April 20, 1989, the role of Dade County DERM was only to conduct an EDI inspection at the site and to forward the information to Tallahassee. Prior to making an eligibility determination on the Site, Patricia Dugan, Environmental Administrator of the DER Petroleum Cleanup Reimbursement Section, reviewed the EDI application, the inspections from DERM, documentation of the site conditions prior to initiation of cleanup and the envelope that the application came in. On November 23, 1989, DER issued an order finding the Site to be ineligible for participation in the Reimbursement Program. Initially, Petitioner's reimbursement application was deemed ineligible because of mixed contamination (i.e., the Site contained used oil) and because the application was deemed untimely. Subsequent to the date of the denial, certain legal decisions made it clear that, contrary to DER's position, sites containing used oil were eligible for participation in the Reimbursement Program. Thus, the only remaining predicate for DER's denial of Rinker's application is that the application was not timely filed. Because Petitioner's EDI application was postmarked on January 3, 1989, after the December 31, 1988 statutory deadline, the Petitioner's application was deemed untimely by DER. DER's policy of relying on the postmark date for purposes of determining timeliness was informally arrived at in 1987. DER has never promulgated a rule on this matter nor conveyed its interpretation to affected parties. Petitioner could have and would have internally placed a postmark date of December 30, 1988 on the envelope containing the EDI Form had it been aware of DER's policy.
Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order approving Petitioner's application for eligibility under the state's reimbursement program. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 23rd day of July, 1990. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July, 1990. APPENDIX Both parties have submitted Proposed Recommended Orders. The following constitutes my rulings on the proposed findings of fact submitted by the parties. The Petitioner's Proposed Findings of Fact: Proposed Finding Paragraph Number in the Findings of Fact of Fact Number in the Recommended Order Where Accepted or Reason for Rejection. Adopted in substance in Findings of Fact 1. Adopted in substance in Findings of Fact 3, 9 and 10. Adopted in substance in Findings of Fact 17 and 20. Adopted in substance in Findings of Fact 20. Adopted in substance in Findings of Fact 26. Adopted in substance in Findings of Fact 22, 36, 37 and 38. Adopted in substance in Findings of Fact 37 and 38. Adopted in substance in Findings of Fact 40. Adopted in substance in Findings of Fact 41. Rejected as constituting argument rather than a finding of fact. Rejected as argument rather than a finding of fact. The Respondent's Proposed Findings of Fact: Proposed Finding Paragraph Number in the Findings of Fact of Fact Number in the Recommended Order Where Accepted or Reason for Rejection. Adopted in substance in Findings of Fact Adopted in substance in Findings of Fact 2. Adopted in substance in Findings of Fact 25. Adopted in substance in Findings of Fact 22. Adopted in substance in Findings of Fact 21. Adopted in substance in Findings of Fact 17. Adopted in substance in Findings of Fact 16. Adopted in substance in Findings of Fact 18. Adopted in substance in Findings of Fact 19. Adopted in substance in Findings of Fact 20. Adopted in substance in Findings of Fact 23. Adopted in substance in Findings of Fact 24. Rejected as constituting argument rather than a finding of fact. Adopted in substance in Findings of Fact 22. Rejected as unnecessary and irrelevant. Adopted in substance in Findings of Fact 15. 17. Adopted in substance in Findings of Fact 15. 18. Adopted in substance in Findings of Fact 37, 38 and 39. 19. Adopted in substance in Findings of Fact 4. 20. Adopted in substance in Findings of Fact 5. 21. Adopted in substance in Findings of Fact 6. 22. Adopted in substance in Findings of Fact 7. 23. Adopted in substance in Findings of Fact 8. 24. Adopted in substance in Findings of Fact 28. 25. Adopted in substance in Findings of Fact 29. 26. Adopted in substance in Findings of Fact 30. 27. Adopted in substance in Findings of Fact 31. 28. Adopted in substance in Findings of Fact 32. 29. Adopted in substance in Findings of Fact 33. 30. Adopted in substance in Findings of Fact 34. 31. Adopted in substance in Findings of Fact 36. 32. Adopted in substance in Findings of Fact 35. 33. Adopted in substance in Findings of Fact 37. 34. Adopted in substance in Findings of Fact 39. 35. Adopted in substance in Findings of Fact 15. 36. Adopted in substance in Findings of Fact 12. 37. Adopted in substance in Findings of Fact 14. 38. Adopted in substance in Findings of Fact 15. 39. Adopted in substance in Findings of Fact 36, 37 and 38. COPIES FURNISHED: Richard A. Pettigrew, Esquire Morgan, Lewis & Bockius 200 South Biscayne Boulevard Miami, Florida 33181 Janet E. Bowman Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Dale W. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 =================================================================
The Issue There are three issues to be determined in this case: (1) whether the Petitioner, Arlington Ridge Community Association, Inc. (Arlington Ridge), demonstrated standing to challenge the proposed agency actions; (2) whether the terms of Consent Order OGC No. 18-0077 (proposed Consent Order) constituted a reasonable exercise of the Respondent, Department of Environmental Protection's (Department), enforcement discretion; and (3) whether the Department's notice of intent to issue minor source air construction permit 0694866-009-AC (009 Permit) to the Respondent, GI Shavings, LLC (GI Shavings), met the applicable rule and statutory criteria for issuance.
Findings Of Fact The Parties The Arlington Ridge community is located in Lake County comprising approximately 500 acres. The community is a 55-year- old plus active adult community with approximately 730 homes. The community includes an 18-hole golf course, swimming pool, tennis courts, pickle ball courts, walking trails, conservation areas, and common areas. Arlington Ridge is a Florida not-for-profit community association governed by its Declaration of Restrictive Covenants for Arlington Ridge, recorded on April 15, 2005, at Official Records Book 2809, Page 1622, of the Public Records of Lake County, Florida, as amended. Arlington Ridge's Articles of Incorporation demonstrate that it was formed, in part, to promote the health, safety, and welfare of the owners within its community and to provide for the ownership, operation, maintenance, and preservation of the common areas. Arlington Ridge is made up of the Declarant, CB Arlington Ridge Landco, LLC, as long as the Declarant still owns lots and the residents who own lots. Robert Salzman is vice president of the Declarant. He serves as president and is a member of the board of directors of the community association. The Declarant still owns 170 undeveloped lots and 91 lots that are under development. There are 730 existing homes that are owned by individual residents who are members of the community association along with the Declarant. The community association owns a section of the roadway and land around the rear gate of the subdivision. GI Shavings is a Florida limited liability company and is the applicant for the minor source air construction permit at issue in this proceeding. The GI Shavings property is located adjacent to the Arlington Ridge community. The address is 26444 County Road 33, Okahumpka, Lake County, Florida 34736. GI Shavings also signed the proposed Consent Order at issue in this proceeding. The Department is the administrative agency of the state having the power and duty to protect Florida's air and water resources and to administer and enforce the provisions of chapter 403, Florida Statutes, and rules promulgated thereunder in Florida Administrative Code Title 62 regarding activities which have the potential to cause air pollution. Facility History of Permitting and Operations On February 7, 2014, GI Shavings' predecessor, Quality Shavings of South Florida, LLC, applied to the Department for an initial air construction permit. The application described the proposed project as a wood chip dryer that included a 30 million British thermal unit per hour (mmBtu/hr) burner fueled by wood chips and sawdust. The burner provided heat to the rotary kiln chip dryer and exhausted to a cyclone dust separator prior to venting to the atmosphere through an exhaust stack. The application materials contained information about the United States Environmental Protection Agency's (USEPA) AP-42 emissions factors for combustion of wood products, with estimations of regulated air pollutant potential and estimated actual emissions from the wood chip drying process. The potential emissions for each pollutant and group of pollutants were listed in tons per year (TPY), and were based on a 30 mmBtu/hr facility running 8,760 hours per year, i.e., no hourly limit. The estimated actual emissions were based on the facility running a typical production schedule of 3,600 hours per year. The listed air pollutants were carbon monoxide (CO), nitrous oxides (NOX), particulate matter (PM), volatile organic compounds (VOCs), sulphur dioxide (SO2), carbon dioxide (CO2), and hazardous air pollutants (HAPs). Although there were potential emissions and estimated actual emissions for each pollutant and group of pollutants, the major source thresholds were not triggered. Therefore, the facility would be classified, from a regulatory standpoint, as a minor source of air pollution. The only air pollution control device was the cyclone dust separator that was rated at 99 percent removal efficiency for PM10, i.e., particulate matter of grain size 10 microns or less, from the exhaust airstream. The application reflected that there were no controls proposed for CO, NOX, VOCs, SO2, CO2, or HAPs. The application was silent as to control of fine particulates or PM2.5, i.e., particulate matter of grain size 2.5 microns or less. The application contained a site location map based on an aerial map. The proposed location of the facility was on a parcel adjacent to the Arlington Ridge community's golf course, and further east a road labeled as Arlington Ridge Boulevard. Other roads, in what appeared to be a not fully built-out subdivision, were White Plains Way and Manassas Drive. The facility plot plan in the application located the wood drip dryer, rotary kiln, cyclone dust separator and exhaust stack on the eastern end of the parcel closest to the boundary with the Arlington Ridge community's golf course. On April 4, 2014, the Department issued minor source air construction permit 0694866-001-AC (001 Permit). The 001 Permit established a visible emissions (VE) limit of five percent opacity, which is the limit specified under the materials handling rules. Like all air permits issued under the Department's rules, the 001 Permit was also subject to certain general conditions. These included the prohibition against "objectionable odor" as defined in the Department's air pollution rules. At the time the 001 Permit was issued, neither GI Shavings nor the Department recognized that the rules for carbonaceous fuel burning equipment were applicable to GI Shavings and that there should also have been a limit for PM in the 001 Permit. Instead, the rules for a materials handling operation were applied to the facility, which required a VE limit of five percent opacity. The 001 Permit required GI Shavings to demonstrate initial compliance and apply for an operating permit no later than 60 days before it expired on June 30, 2015. On December 18, 2014, the Department issued an amendment of the 001 Permit to grant a transfer of ownership from Quality Shavings of South Florida, LLC, to GI Shavings (002 Permit). On May 11, 2015, GI Shavings submitted a request for additional time to demonstrate initial compliance. The reason given for the request was that operations had not started because GI Shavings was waiting on a certificate of occupancy from Lake County, which was expected within the next 60 days. On May 28, 2015, DEP granted the request and issued a permit amendment (003 Permit), which extended the expiration date from June 30, 2015, to December 31, 2015. On November 24, 2015, GI Shavings submitted a second request for additional time to demonstrate initial compliance. The reason given for the request was coding issues at the new warehouse. The request noted that "[a]ll the equipment has been up and runs." On December 7, 2015, the Department granted the request and issued a permit extension (004 Permit), which extended the expiration date from December 30, 2015, to June 30, 2016. In the 004 Permit extension, the Department reminded GI Shavings that there must be notification to the Department within five days of commencing operations, compliance testing within 30 days of commencing operations, 15 days notification to the Department prior to compliance testing, and application for an initial air operation permit no later than 60 days prior to the new expiration date. On April 27, 2016, GI Shavings submitted a third request for additional time to demonstrate initial compliance. There was not any reason given for this 120-day extension request. On May 11, 2016, the Department granted the request and extended the permit's expiration date to October 31, 2016 (005 Permit). The Department reiterated the same reminders as in the 004 Permit extension. On October 24, 2016, the Department conducted its first formal site inspection of GI Shavings in response to complaints from Arlington Ridge residents about smoke, airborne PM, and odor. The Inspection Report confirmed it was a complaint inspection. The Inspection Report also stated that the Department's permitting engineer, Jeff Rustin, had made a previous site visit at which time he had requested to review facility records. The inspection revealed that GI Shavings had commenced operations without notifying the Department, and had not scheduled or submitted a VE compliance test to demonstrate compliance with the permit's five percent opacity limit. During the site inspection, Jeff Rustin and his supervisor, Tom Lubozynski, also a professional engineer, noted that GI Shavings was emitting white smoke from the exhaust stack that did not dissipate quickly and that the smoke may have both moisture and particulates. As they stood 60 feet from the burner and the burner's smoke stack, there was the odor of burning smoke, and particles fell onto Mr. Lubozynski's notepad. Based on their observations, the Department's engineers concluded that the cyclone dust separator was not adequately controlling PM emissions, that the method of operations was unlikely to keep emissions below the five percent opacity VE limitation, and that the equipment should not be operated, except for test purposes. On October 26, 2016, GI Shavings submitted a fourth request for additional time to demonstrate initial compliance. The request was for a 180-day extension with no reason given for the request. On November 23, 2016, the Department granted the request and extended the expiration date from October 31, 2016, to April 4, 2017 (006 Permit). The Department specifically stated in the 006 Permit that the facility was not authorized for normal operations and suggested the alternatives of adding another pollution control device in the form of a bag house, or replacing the cyclone dust separator. Despite the Department's limitations on operations stated in writing at the times of issuing the 004 and 005 Permit extensions, the credible and persuasive evidence was that GI Shavings operated throughout 2016 up until it hired Bruno Ferraro in late November 2016. Actions Taken Before Rerating the Burner Mr. Ferraro is the president of Grove Scientific and Engineering Company, and an expert in air emissions, combustion and visible emissions testing, and air permitting. Mr. Ferraro contacted the Department in early December 2016, stating that he was hired by GI Shavings to evaluate emissions and hoped to visit the facility that month. He requested the original emissions calculations and was provided the original air construction permit application, which contained that information. On December 22, 2016, Mr. Ferraro provided to the Department a report of his initial investigation of the GI Shavings facility. He conducted a site visit on December 20, 2016, accompanied by three representatives from the Department that included Jeff Rustin, Brianna Gowan, and Wanda Parker- Garvin. Ms. Parker-Garvin was the environmental manager for the Central District Office's compliance assurance program. Of particular relevance in the report was the following statement: The cyclone works as designed by separating the dry wood shavings and sawdust from the hot combustion air. However, the cyclone is not designed to remove fine particulates from the combustion of wood. The particulate matter (PM) emitted from the combustion of wood is unburned carbon and too small a particle size to be removed by the cyclone. This carbonaceous PM is best controlled by increasing the efficiency of combustion or through the use of post combustion control equipment. (Emphasis added). J. Ex. 1 at DEP 1-360. Mr. Ferraro recommended certain actions to increase the efficiency of combustion, such as changing the starter fuel to wood logs and varying the sawdust feed rate. He also recommended that GI Shavings seek a permit modification to allow excess emissions during startup, shutdown, and malfunction. He also recommended seeking a permit modification to allow a higher VE limit, such as 20 percent opacity, for normal operating conditions. He recommended, as a last resort, the use of post combustion control equipment. This would involve the installation of a bag house, which he described as a "very costly alternative and an excessive measure for controlling carbonaceous PM from the combustion of clean wood." The Department responded to Mr. Ferraro's report on January 5, 2017. Ms. Parker-Garvin provided the Department's comments and response in a lengthy email that also approved a two-week experimental testing phase. The email specifically limited opacity to no more than 20 percent for a smoke plume that would be carried by a west wind in an easterly direction toward the adjacent residents and golf course in a 90-degree quadrant designated on an aerial map as the area of concern or "AOC." The email summarized an expectation that a future air operation permit would require a showing of reasonable assurance that the relevant carbonaceous fuel burning rules for a 30 mmBtu/hr burner could be met. This would include a VE limit of 30 percent opacity and a PM limit of 0.2 pounds per mmBtu of heat input of carbonaceous fuel. Both limitations would need to be initially demonstrated before an air operation permit could be issued. On January 8, 2017, Mr. Ferraro provided a draft startup, shutdown, and malfunction operation plan (SSMOP) to the Department. In his email, Mr. Ferraro stated that the facility would start the two-week experimental testing phase the next day, on January 9, and keep the Department updated. He also stated that they would submit an application to modify the air construction permit. On January 17, 2019, GI Shavings applied for a permit modification, specifying only a change in VE limit from five percent opacity to 30 percent opacity. On March 8, 2017, the Department met with Mr. Ferraro, and an attorney for GI Shavings who attended by telephone. The meeting summary documented a discussion of issues that included requirements for annual PM testing, annual VE testing, and the SSMOP's restrictions on hours of operation and wind direction. The Department's response referred to "health concerns of the complainants," "adverse impacts off property," "numerous complaints," and "proximity to a retirement-age community" as reasons for the SSMOP's restrictions. On March 31, 2017, the Department's intent to modify GI Shavings' air construction permit was published. Arlington Ridge residents made verbal comments and filed complaints with the Central District Office regarding the draft air construction permit. The residents also filed a petition for administrative hearing that was eventually resolved in some manner, because the evidence showed that the final permit was issued on June 26, 2017. On June 26, 2017, the Department modified the air construction permit (007 Permit). The 007 Permit authorized a change in the VE limit, added a PM limit, added a SSMOP, added initial compliance requirements, and extended the expiration date to November 30, 2017. The 007 Permit also included a separate hours of operation agreement (HOA) between the Department and GI Shavings. The HOA initially provided for "[t]wo consecutive 8-hour shifts per day, between the hours of 6:00am and 10:00pm, Sunday thru Friday." These hours could be increased based on lack of compliance issues and lack of complaints over a 90-day period after the 007 Permit was issued. Mr. Ferraro testified that one of the permit requirements was to do a PM compliance test using EPA Method 5. This involved establishing a protocol that would be approved by the Department prior to conducting the compliance test. He testified that during June and July of 2017, the facility started having operational problems that made it difficult to calibrate the fuel feed system to establish the maximum fuel rate and the maximum shavings production rate. During calibration, the sawdust feed system motor kept burning out. Finally, he was able to schedule and conduct the PM compliance test on August 25, 2017. Mr. Ferraro testified that he ran the burner at maximum capacity during the test, which turned out to be an average of 18.252 mmBtu/hr. That is when he observed that this burner's maximum capacity was not 30 mmBtu/hr. The facility failed the PM compliance test with a three-run average PM of 0.531 pounds per mmBtu of heat input of carbonaceous fuel. The facility complied with the VE limit using the EPA Method 9 test, with the highest six-minute average of 13.33 percent opacity. The compliance test results were reported to the Department on September 8, 2017. In his report, Mr. Ferraro concluded "[i]t is our opinion that the PM caused by the burning of carbonaceous fuel, plus the process emission from the wood shavings dust combined in the method 5 sample filter to cause the observed PM emission rate." He stated that GI Shavings wanted to resolve the situation by exploring a change to the PM limit in the permit. Mr. Ferraro testified that there continued to be startup and operational difficulties at the facility. At maximum operation, the facility was not able to get the burner to the specified heat output of 30 mmBtu/hr. After multiple calibrations and tests, the facility was still unable to function as originally specified by the manufacturer. After consulting with the Department, Mr. Ferraro designed a demonstration test in which the sawdust fuel was fed into the burner without the drying of wood shavings. The demonstration test's purpose was to address the PM and VE from the combustion of sawdust. The test was conducted on October 11, 2017, and reported to the Department on October 30, 2017. The facility failed the PM test with a three-run average PM of 0.824 pounds per mmBtu of heat input of carbonaceous fuel. The facility complied with the VE limit using the EPA Method 9 test, with the highest six-minute average of 5.6 percent opacity. Mr. Ferraro concluded that the October test confirmed the PM measured was a result of unburned carbon or incomplete combustion of the carbonaceous fuel, i.e., sawdust. He stated that the cyclone dust separator appears to do a good job of removing all large PM. However, the burner was not designed for complete combustion, i.e., did not burn hot enough for long enough. This resulted in the black soot deposited on the method 5 filters during the compliance tests. Meanwhile, on October 10, 2017, Mr. Ferraro forwarded an email to the Department with a request from GI Shavings to increase its hours of operation since it was "commencing our six months busy season," and was negotiating with additional clients. After receiving the initial October 10, 2017, test results from Mr. Ferraro, the Department's permitting program administrator at the time, Kimberly Rush, responded that "[b]ased upon the requirements outlined in the [HOA], the Department cannot approve the request[ed] hours of operation change at this time due to the pending compliance test and the complaint received on 8/16/17." Mr. Ferraro testified that GI Shavings decided to bring in Energy Unlimited Inc., the equipment manufacturer, to commission the facility. At this time, GI Shavings, through Mr. Ferraro, also requested an extension of the air construction permit that was set to expire in December of 2017. The reason given was that more time was needed to conduct and complete the commissioning process and continue working on facility compliance. On November 20, 2017, the Department extended the expiration date of the air construction permit to November 30, 2018 (008 Permit). The 008 Permit did not make any other changes to the provisions and requirements of the 007 Permit. In January 2018, the manufacturer did significant work to the facility's systems including reworking the fuel feed system, installing a new programmable logic controller and temperature controllers, as well as mechanical and programmatic changes. Upon completion of the commissioning process, Energy Unlimited, Inc., certified and rerated the equipment at a design rate maximum of 26 mmBtu/hr and an actual rate of 21 mmBtu/hr. Mr. Ferraro testified that typical operation was between 15 and 18 mmBtu/hr depending on the temperature outside and the amount of moisture in the air. Impacts to Arlington Ridge Residents Dennis Hartman lives on Arlington Ridge Boulevard and has been a member of the community association since early 2018. Mr. Hartman testified that GI Shavings is located on a diagonal from his home adjacent to the 11th fairway of the golf course. He testified that the smoke and smell from GI Shavings irritates his lungs, throat, and nasal passages. Mr. Hartman testified that he is impacted by the facility, in this manner, at least twice a week. Notably, he does not experience these impacts when he is away from Arlington Ridge. James Piersall has been a member of the community association since July 6, 2018, when he closed on his home in Arlington Ridge. Mr. Piersall testified that on November 27, 2018, while playing golf on the 11th hole, a dark blue wave of smoke came across and covered the green. The smell was prevalent, which he equated to burning wood. Mr. Piersall captured the smoke on video with his cell phone. He testified that it was common knowledge that GI Shavings was located on the other side of the 11th hole. The 150-yard marker and a cell tower serve as landmarks that help the residents locate the GI Shavings facility. Mr. Piersall also testified that this was the time of year to open the windows and doors, and let the breeze blow through the house. However, it was not possible to do so, as there was "sediment and soot that comes out on the patio." Rhonda Lugo has lived in Arlington Ridge since August of 2014, and has been a member of the community association. She testified that GI Shavings began operating two years after she moved to Arlington Ridge. She lives on Arlington Ridge Boulevard, where her home is directly behind GI Shavings and her backyard is approximately 300 yards from the facility. Ms. Lugo testified that her first two years in her home were great. She used her lanai and enjoyed her home. She now describes her home as "unlivable." She does not open any doors or windows, and has not used the lanai for almost two years. The soot and ash covers her lanai furniture. She testified that her eyes burn, and described the odor as more than "just a wood burning smell." Ms. Lugo testified that over the last two years, the residents as a group, have gone to the City of Leesburg and to Lake County, have written senators and state representatives, and have contacted the Department many times. Cheryl Thomack has lived on Arlington Ridge Boulevard since August 2017, and has been a member of the community association. She experiences headaches and breathing difficulties, and uses an inhaler, which she attributes to smoke and soot from the GI Shavings facility. She testified that she went on vacation for a week away from her home and did not experience any headaches or breathing problems while away from Arlington Ridge. She also testified that the GI Shavings facility has operated when the wind is blowing in the direction of the community. Michael Becker has lived on Manassas Drive in the Arlington Ridge community since August 4, 2017. Mr. Becker enjoys the outdoor activities at the Arlington Ridge community and is a member of the softball team. He testified that the operations of the GI Shavings facility are disruptive to himself and his wife, and that they stay indoors with all windows and doors closed. He testified that they only enjoy their lanai in the late hours of the night, when GI Shavings is not operating. He described the smoke fumes as "pretty toxic" when the wind is blowing their way, with a scorched wood type of smell. Mr. Becker testified that he and his wife have taken several videos of dark smoke billowing from the GI Shavings facility, and provided them to the community association representatives. Mr. Becker also testified that he was aware of the location of at least two industrial facilities near the Arlington Ridge subdivision. He testified that Covanta, a clean waste facility, was located outside the subdivision's gate, and, what he believed was a cement plant, was located off Rogers Industrial Park Road. Douglas Deforge has lived on Manassas Drive since December 2017. He testified that when he first moved in, there was "a lot of noise and I saw a lot of smoke coming out of the trees that are behind us." Eventually, he figured out that it was the location of the GI Shavings facility. Mr. Deforge testified that his wife likes to go out on the lanai to drink her coffee and read the paper, but she is not able to do so on certain days when the machinery is running. Particles on the lanai have to be removed frequently. Mr. Deforge testified that the smoke has a pungent odor like a paper mill. He expressed concern that he may eventually have respiratory issues because of the particles he inhales when out on his lanai. Mr. Deforge testified that since late November 2018, up until the morning of the final hearing, "[i]t seems more frequently that I'm seeing plumes coming out of GI Shavings." Sherry O'Brien lives on Arlington Ridge Boulevard and has been a member of the community association since October 2014. The GI Shavings facility is directly behind her home across the 11th fairway of the golf course. She has even walked the fence line at the 11th fairway to locate GI Shavings' smoke stack. Ms. O'Brien testified that the dark smoke and odor from the GI Shavings facility prevents her from enjoying the lanai and from golfing. She experiences a more hoarse and raspy voice and sinus problems. Ms. O'Brien testified that even with the windows closed, inside her home smells like burning wood. She testified that she observed the smoke directly behind the 11th green, which is directly behind her home. In her testimony, Ms. O'Brien distinguished between the location of smoke from the GI Shavings facility and the Covanta facility. Robert Salzman has been at Arlington Ridge for several years, four to five days per week, 10 to 12 hours per day. He is involved with the day-to-day activities of the sales office, community association management; and he is on the architectural control committee. He testified that GI Shavings' operations impact the 11th and 12th holes of the golf course, which is still owned by the Declarant. Mr. Salzman testified that resident complaints about GI Shavings have increased over the years, particularly in the months of October and November when the operations increase from five to seven days per week and into the night. He testified that while GI Shavings is operating, the residents are not active outdoors, they do not seem to leave their homes, and golfers skip the 11th and 12th holes. Mr. Salzman testified that he was familiar with the industrial facilities around Arlington Ridge. He testified to the locations of an adjacent peat facility, an aggregate company, and the Covanta waste-to-energy facility. He testified that there was not a cement plant nearby, but that it was a concrete mixing company. Mr. Salzman also testified that Covanta has a giant stack that puts out steam, but it is not located in the same direction as the GI Shavings facility. All the residents who testified stated that they get "black stuff" on their lanais when there is smoke coming from GI Shavings. The residents also testified that they cannot open their windows and cannot enjoy their lanais. All the residents believed that an increase in hours of operation and no restriction on wind direction for GI Shavings would negatively impact their quality of life. Complaints to the Department The preponderance of the competent and substantial evidence showed that the residents lodged complaints with the community association, the Department, and the local governments about GI Shavings' operation for most of 2016, 2017, and 2018. The complaints increased in October of each year when GI Shavings increased operations to meet business demands. The complaints varied from the operations being a nuisance and affecting their quality of life in their retirement community, to genuine concerns for their health and well-being. During the hearing, GI Shavings tried to suggest that its facility was not the source of the smoke seen and videoed by the residents. Although the Arlington Ridge subdivision is adjacent to an industrial park, the residents' description and observation of GI Shavings' location behind the tree line at the 11th hole of the golf course was consistent and was supported by the preponderance of the competent and substantial evidence. Arlington Ridges' expert witness, Mitchell J. Hait, Ph.D., and GI Shavings' expert witness, Mr. Ferraro, both provided similar descriptions of the atmospheric conditions during the summer and winter months. They explained that during the winter months, when the atmospheric conditions are cooler, the plume from the exhaust stack does not dissipate as quickly as during the warmer summer months. Thus, the plume would tend to remain visible and be carried by the wind. The increase in residents' complaints starting in October of each year could be explained by a combination of the cooler atmospheric conditions and GI Shavings' increased operations to meet business demands. GI Shavings tried to suggest that the plumes were only comprised of steam from the drying process and that PM was removed at 99 percent efficiency by the cyclone dust separator. However, the preponderance of the competent and substantial evidence established that the cyclone dust separator did not remove fine PM identified as "unburned carbon . . . too small a particle size to be removed by the cyclone." In other words, the "black stuff" that the residents found on their lanais, and the odor that irritated their noses, throats, and lungs. Enforcement and Consent Order Despite overwhelming lay and expert evidence of ongoing objectionable odor violations, the Department sought only to resolve the August and October 2017 PM emission limit exceedances with the proposed Consent Order. Even though both Mr. Ferraro and Ms. Rush agreed that the October 2017 test was not run under normal operating and compliance conditions, the Department decided to label it as a violation in the proposed Consent Order. The proposed Consent Order gave GI Shavings a choice of corrective actions, and did not impose any monetary penalty. The choice given was to either install a pollution control device, such as a bag house, or perform a rerating of the burner. The preponderance of the competent and substantial evidence established that the cyclone dust separator did not remove the fine PM that was the source of the residents' objectionable odor complaints. The adequate and reasonable course of action would be to order GI Shavings to both install a bag house and perform the rerating of the burner. Instead, GI Shavings was allowed to rerate the unit and apply for the associated permit that would remove the requirement of a PM emission limit. Notably, the proposed Consent Order was not finally executed until April 20, 2018, at which time GI Shavings had already rerated the facility, applied for a permit, and received a notice of intent to issue with the draft 009 Permit. These completed actions were even stated in the proposed Consent Order. The Department's expert witness, Ms. Rush, testified that considering the difficulties with the facility's operations at its original specifications, rerating the burner was a viable option for obtaining compliance. However, giving GI Shavings a choice of corrective actions, which allowed it to avoid addressing the objectionable odor complaints, was not an adequate and reasonable exercise of the Department's enforcement discretion under the facts and circumstances described above. 009 Permit Application On January 31, 2018, Mr. Ferraro, on behalf of GI Shavings, submitted the 009 Permit application to the Department. Mr. Ferraro testified that the purpose of the application was to apply the correct part of the carbonaceous fuel burning equipment rule to the facility. The switch would be from the standards applicable to a 30 mmBtu/hr burner to the standards applicable to a less than 30 mmBtu/hr burner. This switch would entirely remove the PM limit and change the VE limit to 20 percent opacity. Mr. Ferraro testified that the application did not request any other change, and the Department did not request any additional information. The application described its purpose as "to update emission limiting standard for carbonaceous [fuel] burning equipment with a rating of less than 30 mmBtu/hr." The emissions unit control equipment was described as a single cyclone device that "separates wood shavings and sawdust from airstream, but does not control products of combustion." Although the inability of the cyclone dust separator to "control products of combustion" was acknowledged, the application indicated that PM would not be synthetically limited, and that a PM limit would not apply to the facility. The application did not propose a pollutant control device for the continuously acknowledged unburned carbon described as "too small a particle size to be removed by the cyclone." Ms. Rush testified that the only PM expected from the facility was PM10. However, as Mr. Ferraro pointed out in his testimony, actual site specific information and data should be considered whenever it is available, instead of simply relying on what is expected based on the literature from the USEPA. The 009 Permit's notice of intent to issue also stated that "the operational hours agreement has been removed from the permit," although GI Shavings did not apply for any change to the 008 Permit beyond the rule switch. Ms. Rush testified that the HOA was voluntary and the Department did not have the authority to require GI Shavings to incorporate these terms into future permits. However, the HOA continues to be a condition of GI Shavings' current 008 Permit. The Department and GI Shavings did not present any persuasive evidence to show that this condition was now obsolete and should not be carried forward into the 009 Permit. The 009 Application did not request any revision to the current SSMOP. Ms. Rush testified that any minor source air permittee may request to revise its SSMOP at any time. However, such a request would be subject to Department approval as specified in condition A.15. of the draft 009 Permit. Although Dr. Hait testified that the facility should be reviewed as a 30 mmBtu/hr burner, the more persuasive evidence was that the rerating by the manufacturer established a design fire rating of 26 mmBtu/hr and an actual rating of 21 mmBtu/hr. Ms. Rush testified that the draft 009 Permit would contain a feed rate limitation that would restrict the facility to a maximum firing rate of 21 mmBtu/hr. Thus, the carbonaceous fuel equipment burning rule was the most appropriate category for this facility, and it was appropriately regulated as a minor source of air pollution. The preponderance of the competent and substantial evidence proved that GI Shavings did not provide reasonable assurance that the facility would control the cause of the objectionable odor violations, i.e., fine PM identified as "unburned carbon . . . too small a particle size to be removed by the cyclone." In other words, the "black stuff" that the residents had constantly and consistently complained about. Ultimate Findings The preponderance of the competent and substantial evidence established that the GI Shavings facility emits fine PM or "black soot" into the outdoor atmosphere, which by itself or in combination with other odors, unreasonably interferes with the comfortable use and enjoyment of life or property at the Arlington Ridge community, and which creates a nuisance. The preponderance of the competent and substantial evidence established that the cyclone dust separator did not remove the fine PM that was the source of the residents' objectionable odor complaints. Therefore, it was an unreasonable exercise of enforcement discretion for the Department to not require that GI Shavings directly address the objectionable odor issue. In addition, the utility of entering the proposed Consent Order was diminished by the fact that the October 2017 alleged violation was not an appropriate compliance test. Also, by the fact that the proposed Consent Order was not finally executed until April 20, 2018, at which time GI Shavings had already rerated the facility, applied for a permit, and received a notice of intent to issue with the draft 009 Permit. The preponderance of the competent and substantial evidence proved that GI Shavings did not provide reasonable assurance that the facility would control fine PM, which the evidence established was the source of the residents' objectionable odor complaints. All other contentions that Arlington Ridge raised in this proceeding that were not specifically discussed above have been considered and rejected.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order denying GI Shavings' application for minor source air construction permit 0694866-009-AC, and disapproving Consent Order OGC No. 18-0077. DONE AND ENTERED this 19th day of June, 2019, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of June, 2019. COPIES FURNISHED: Stephen "Toby" Tobias Snively, Esquire Law Offices of John L. Di Masi, P.A. 801 North Orange Avenue, Suite 500 Orlando, Florida 32801 (eServed) John L. Di Masi, Esquire Law Offices of John L. Di Masi, P.A. 801 North Orange Avenue, Suite 500 Orlando, Florida 32801 Dorothy E. Watson, Esquire Foley & Lardner, LLP 111 North Orange Avenue, Suite 1800 Orlando, Florida 32801 (eServed) Matthew J. Knoll, Esquire Department of Environmental Protection Office of the General Counsel Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 (eServed) Peter A. Tomasi, Esquire Foley & Lardner, LLP 777 East Wisconsin Avenue Milwaukee, Wisconsin 53202-5306 Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 (eServed) Justin G. Wolfe, General Counsel Department of Environmental Protection Legal Department, Suite 1051-J Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 (eServed) Noah Valenstein, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 (eServed)
The Issue The issue in this case is whether Respondent Laniger Enterprises of America, Inc. (Laniger), is entitled to the renewal of its domestic wastewater facility permit that was denied by Petitioner Department of Environmental Protection (Department).
Findings Of Fact The Parties The Department is the administrative agency of the State of Florida having the power and duty to protect Florida's air and water resources and to administer and enforce the provisions of Chapter 403, Florida Statutes (2005),1 and the rules promulgated in Florida Administrative Code Title 62. Laniger is a Florida corporation that owns and operates the WWTP that is the subject of this case, located at 1662 Northeast Dixie Highway, Jensen Beach, Martin County, Florida. The WWTP is referred to in the Department permit documents as the Beacon 21 WWTP. The WWTP Laniger acquired the WWTP in 1988 in a foreclosure action. At that time, the WWTP was in a "dilapidated" condition and was operating under a consent order with the Department. After acquiring the WWTP, Laniger brought it into compliance with the Department's requirements. Laniger's WWTP is commonly referred to as a "package plant."2 The WWTP's treatment processes are extended aeration, chlorination, and effluent disposal to percolation ponds. The WWTP does not have a direct discharge to surface water. It was permitted to treat 99,000 gallons per day (gpd) of wastewater. Its average daily flow during the past year was about 56,000 gallons. The east side of the WWTP site is adjacent to Warner Creek. On the north side of the WWTP site, an earthen berm separates the WWTP's percolation ponds from a drainage ditch that connects to Warner Creek. Warner Creek is a tributary to the St. Lucie River. The St. Lucie River is part of the Indian River Lagoon System. The Indian River Lagoon Act In 1989, the St. Johns River Water Management District and the South Florida Water Management District jointly produced a Surface Water Improvement and Management (SWIM) Plan for the Indian River Lagoon System ("the lagoon system"). For the purpose of the planning effort, the lagoon system was defined as composed of Mosquito Lagoon, Indian River Lagoon, and Banana River Lagoon. It extends from Ponce de Leon Inlet in Volusia County to Jupiter Inlet in Palm Beach County, a distance of 155 miles. The SWIM Plan identified high levels of nutrients as a major problem affecting water quality in the lagoon system. Domestic wastewater was identified as the major source of the nutrients. The SWIM Plan designated 12 problem areas within the lagoon system and targeted these areas for "research, restoration and conservation projects under the SWIM programs." Department Exhibit 2 at 11-13. Neither Warner Creek nor the area of the St. Lucie River that Warner Creeks flows into is within any of the 12 problem areas identified in the SWIM Plan. With regard to package plants, the SWIM Plan stated: There are numerous, privately operated, "package" domestic WWTPs which discharge indirectly or directly to the lagoon. These facilities are a continual threat to water quality because of intermittent treatment process failure, seepage to the lagoon from effluent containment areas, or overflow to the lagoon during storm events. Additionally, because of the large number of "package" plants and the lack of enforcement staff, these facilities are not inspected or monitored as regularly as they should be. Where possible, such plants should be phased out and replaced with centralized sewage collection and treatment facilities. Department Exhibit 2 at 64. In 1990, the Legislature passed the Indian River Lagoon Act, Chapter 90-262, Laws of Florida. Section 1 of the Act defined the Indian River Lagoon System as including the same water bodies as described in the SWIM Plan, and their tributaries. Section 4 of the Act provided: Before July 1, 1991, the Department of Environmental Regulation shall identify areas served by package sewage treatment plants which are considered a threat to the water quality of the Indian River Lagoon System. In response to this legislative directive, the Department issued a report in July 1991, entitled "Indian River Lagoon System: Water Quality Threats from Package Wastewater Treatment Plants." The 1991 report found 322 package plants operating within the lagoon system and identified 155 plants as threats to water quality. The 1991 report described the criteria the Department used to determine which package plants were threats: Facilities that have direct discharges to the system were considered threats. Facilities with percolation ponds, absorption fields, or other sub-surface disposal; systems located within 100 feet of the shoreline or within 100 feet of any canal or drainage ditch that discharges or may discharge to the lagoon system during wet periods were considered threats. * * * Facilities with percolation ponds, absorption fields, or other sub-surface disposal systems located more than 100 feet from surface water bodies in the system were evaluated case-by-case based on [operating history, inspection reports, level of treatment, and facility reliability]. Laniger's package plant was listed in the 1991 report as a threat to the water quality of the lagoon system because it was within 100 feet of Warner Creek and the drainage ditch that connects to Warner Creek. Laniger's WWTP was not determined to be a threat based on its wastewater treatment performance. There was no evidence presented that Laniger's WWTP had ever had intermittent treatment process failure, seepage to the lagoon system from effluent containment areas, or overflow during storm events. Those were the concerns related to package plants that were described in the SWIM Plan and the Department's 1991 report. Laniger's WWTP was not determined to be a threat based on evidence that it was causing or contributing to excess nutrients in Warner Creek or in that part of the St. Lucie River nearest to Laniger's WWTP. No evidence was presented that there are excess nutrients in Warner Creek or in that part of the St. Lucie River nearest to Laniger's WWTP. The Department's 1991 report concluded that the solution for package plants threats was to eliminate the package plants and connect their wastewater flow to centralized sewage collection and treatment facilities. To date, over 90 of the 155 package plants identified in the Department's 1991 report as threats to the water quality of the lagoon system have been connected to centralized sewage collection and treatment systems. The 1999 Permit and Administrative Order On August 26, 1999, the Department issued Domestic Wastewater Facility Permit No. FLA013879 to Laniger for the operation of its WWTP. Attached to and incorporated into Laniger's 1999 permit was Administrative Order No. AO 99-008- DW43SED. The administrative order indicates it was issued pursuant to Section 403.088(2)(f), Florida Statutes. That statute pertains to discharges that "will not meet permit conditions or applicable statutes and rules" and requires that the permit for such a discharge be accompanied by an order establishing a schedule for achieving compliance. The administrative order contains a finding that the Beacon 21 WWTP is a threat to the water quality of the lagoon system and that the WWTP "has not provided reasonable assurance . . . that operation of the facility will not cause pollution in contravention of chapter 403, F.S., and Chapter 62-610.850 of the Florida Administrative Code." The cited rule provides that "land application projects shall not cause or contribute to violations of water quality standards in surface waters." The administrative order required Laniger to connect its WWTP to a centralized wastewater collection and treatment [facility] "within 150 days of its availability . . . or provide reasonable assurance in accordance with Chapter 620.320(1) of the Florida Administrative Code that continued operation of the wastewater facility is not a threat to the water quality of the Indian River Lagoon System." As a result of an unrelated enforcement action taken by the Department against Martin County, and in lieu of a monetary penalty, Martin County agreed to extend a force main from its centralized sewage collection and treatment facility so that the Laniger WWTP could be connected. The extension of the force main was completed in April 2003. On April 10, 2003, the Department notified Laniger by letter that a centralized wastewater collection and treatment system "is now available for the connection of Beacon 21." In the notification letter, the Department reminded Laniger of the requirement of the administrative order to connect within 150 days of availability. On May 9, 2003, Laniger's attorney responded, stating that the administrative order allowed Laniger, as an alternative to connecting to the centralized wastewater collection and treatment system, to provide reasonable assurance that the WWTP was not a threat to the water quality of the lagoon system, and Laniger had provided such reasonable assurance. Laniger's attorney also stated, "due to the location of Martin County's wastewater facilities, such facilities are not available as that term is defined in the [administrative] order." On September 29, 2003, the Department issued a warning letter to Laniger for failure to connect to the Martin County force main and for not providing reasonable assurance that the WWTP will not cause pollution in contravention of Chapter 403, Florida Statutes. The Department took no further formal action until it issued the NOV in August 2005. Laniger's challenge of the NOV was consolidated with this permit case. The Permit Renewal Application In an "enforcement meeting" between Laniger and the Department prior to the expiration of 1999 permit, the Department told Laniger that it would not renew Laniger's WWTP permit. Later, when Laniger filed its permit renewal application, the Department offered to send the application back so Laniger would not "waste" the filing fee, because the Department knew it was not going to approve the application. Laniger submitted its permit renewal application to the Department on February 15, 2005. The Department considered Laniger's permit application to be complete, but proceeded to prepare the Notice of Denial without any technical review of the application. The Department denied the application on April 6, 2005. The Department's Notice of Permit Denial stated that the permit was denied because Laniger had not connected to the available centralized wastewater collection and treatment system nor provided reasonable assurance that the WWTP "is not impacting water quality within the Indian River Lagoon System." The record evidence showed that the "reasonable assurance" that would have been necessary to satisfy the Department was more than the reasonable assurance the Department usually requires for package plants, and more than the Department would have required if Laniger's WWTP was 100 feet from Warner Creek. Competent substantial evidence was presented that Laniger's WWTP is capable of being operated in accordance with the statutes and rules of Department generally applicable to package wastewater treatment plants. Laniger's 1999 permit expired on August 25, 2004. Laniger has operated the plant continuously since the permit expired. Whether the Martin County Facility is Available As discussed below in the Conclusions of Law, it is concluded that the Department did not have authority to require Laniger to connect the WWTP to the Martin County force main or to require assurance beyond the reasonable assurance generally required for package treatment plants in order to obtain a permit. However, because considerable evidence and argument was directed to whether the force main was available, that issue will be addressed here. The Martin County force main was not extended to the boundary of the Laniger WWTP site. The force main terminates approximately 150 feet north of the Laniger WWTP site and is separated from the WWTP site by a railroad and railroad right-of-way. Laniger presented undisputed evidence that the cost to connect to the Martin County force main would be approximately $490,000 and that cost was prohibitively high, given the relatively small number of households served by the WWTP. The Laniger WWTP is subject to rate regulation by the Public Service Commission (PSC). Laniger presented evidence suggesting that connection to the Martin County force main would result in rates that would not be approved by the PSC. The evidence was speculative and not competent to support a finding regarding PSC action. The evidence does show, however, that PSC rate regulation was not a factor that the Department considered when it determined that the Martin County force main was available. There is no Department rule that defines when a centralized sewage collection and treatment facility is "available." The determination that the Martin County force main was available to Laniger was made informally by members of the Department's compliance staff in the Department's St. Lucie office. Mr. Thiel testified that he considered the force main to be available because it was "in close proximity" to Laniger's WWTP. However, Mr. Thiel admitted that there is a difference of opinion within DEP as to when a facility is available and reasonable persons could disagree about whether a facility was available. Mr. Thiel thought that the cost to connect is a factor to be considered in determining whether a facility is available, but another Department employee did not think cost should be considered. There was no evidence that the Department took into account Laniger's cost to connect in determining that the Martin County force main was available. The Department simply assumed that the Martin County force main was close enough to the Laniger WWTP site that the cost to Laniger would not be prohibitive. In addition, the Department was aware of other package plants that had connected to centralized sewage collection and treatment facilities that were the same distance or a greater from the package plant, and the Department did not hear from the owners of the package plants that the costs were prohibitive. Timothy Powell of the Department stated that force mains are usually made available by extending the force main so that it is "abutting the property as much as possible." He also stated that he assumed that Martin County would extend its force main under the railroad and to the boundary of the Laniger WWTP site after Laniger agreed to connect. However, there was no evidence to show that this is Martin County's intent, and the Department did not tell Laniger that Laniger did not have to connect to the force main unless Martin County brought the line to the boundary of the WWTP site. If the Department had authority to require Laniger to connect to the Martin County force main when it became available, and in the absence of any rule criteria to determine when a centralized sewage collection and treatment facility is available, the determination would have to be based on reasonableness. Reasonableness in this context must take into account the cost of the connection. Cost is the inherent reason that Laniger was not required to connect to the Martin County centralized sewage collection and treatment facility without regard to whether the facility was available. Laniger showed that the cost of connecting to the force main is unreasonably high due to the need to construct a line beneath the railroad. Therefore, Laniger proved by a preponderance of the evidence that the Martin County force main is not available.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting Laniger Enterprises of America, Inc., a renewal of its wastewater treatment plant operating permit. The permit should contain the same conditions as were contained in the 1999 permit, with the exception of those conditions derived from Administrative Order No. AO 99-008- DW43SED. DONE AND ENTERED this 19th day of September, 2006, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 2006.
The Issue The issue is whether Petitioner is eligible to continue participating in the Drycleaning Solvent Cleanup Program.
Findings Of Fact Petitioner, Sunset Square General Partnership, is the owner of Sunset Square Shopping Center located in Clearwater, Florida, and in which Tux Cleaners, Department of Environmental Protection Identification No. 529501419, was a tenant conducting a drycleaning business. At all times relevant hereto, the Sunset Square Shopping Center was managed by the Stuart S. Golding Company on behalf of Sunset Square General Partnership. At all times relevant to this proceeding, Tux Cleaners was owned and operated by Angelo Guarnieri. In June 1996, Petitioner submitted an application to participate in the Drycleaning Solvent Cleanup Program (Program/ Drycleaning Solvent Cleanup Program). The application was signed by a representative of Petitioner and by Guarnieri. David Scher, an employee of the Stuart S. Golding Company, was listed on the application as the contact person for Petitioner. All applications to the Drycleaning Solvent Cleanup Program are joint applications that include the real property owner, the operator of the drycleaning facility, and the owner of the drycleaning facility. Thus, in this instance, the applicant was Petitioner, the owner of the real property on which the drycleaning facility was located, and Guarnieri, the owner and operator of the facility. Petitioner was listed as the "designated applicant" on the aforementioned application filed with the Department. The "designated applicant" served to advise and provide the Department with a single point of contact. Upon review of Petitioner's application, the Department determined that Petitioner met the prescribed eligibility requirements for participation in the Drycleaning Solvent Cleanup Program. Thereafter, by letter dated September 27, 1996, the Department notified Petitioner that its site, Tux Cleaners, was eligible for participation in the Drycleaning Solvent Cleanup Program. The letter advised Petitioner that its "participation in the Program is contingent upon continual compliance with the conditions of eligibility set forth in Section 376.3078(3), F.S." At the time Petitioner's letter of eligibility was issued, Section 376.3078(7), Florida Statutes (1995), required that owners and operators of drycleaning facilities install secondary containment by January 1, 1997. This statute was enacted in 1995, the year before Petitioner was determined eligible for participation in the Drycleaning Solvent Cleanup Program. To maintain its eligibility in the Drycleaning Solvent Cleanup Program, Petitioner was required to install secondary containment at Tux Cleaners by January 1, 1997. As of January 1, 1997, secondary containment had not been installed at Tux Cleaners. Consequently, on January 2, 1997, Petitioner and Tux Cleaners were no longer in compliance with the eligibility requirements for participation in the Drycleaning Solvent Cleanup Program. On January 21, 1998, Margaret Hennis, a Pinellas County environmental inspector, conducted an inspection of Tux Cleaners as part of a Title V compliance inspection. During the inspection, Hennis discovered that Tux Cleaners did not have the required secondary containment and advised Guarnieri that secondary containment needed to be installed. Guarnieri then informed Hennis that the equipment had been ordered in late 1997. Guarnieri initially ordered secondary containment for Tux Cleaners in June 1997 but cancelled the order because he thought the business had been sold. When the business was not sold, Guarnieri reordered the secondary containment in late 1997, almost one year after it should have been installed. There is no evidence that the secondary containment was ever delivered to Tux Cleaners; and it clearly was never installed at Tux Cleaners. Prior to becoming eligible for the Drycleaning Solvent Cleanup Program, Petitioner hired an environmental consultant, who subsequently advised Petitioner to apply for participation in the Program. After the application of Petitioner and Tux Cleaners was approved, Petitioner believed that the environmental consultant would monitor the drycleaning facility to ensure that the site was in continual compliance with Program eligibility requirements. Although Petitioner and Guarnieri submitted a joint application to the Department, they never discussed the need to install secondary containment at Tux Cleaners. It was only after receiving the February 26, 1998, letter described below that Petitioner had actual knowledge of the secondary containment requirement. Accordingly, Petitioner never asked Guarnieri whether the secondary containment had been installed or directed Guarnieri to install the required secondary containment. Furthermore, Guarnieri never discussed with Petitioner the January 1997 inspection of Tux Cleaners, Hennis' notification that secondary containment needed to be installed, or any matters relative to Guarnieri's ordering and reordering of the secondary containment. By letter dated February 26, 1998 (notice of cancellation), the Department notified Petitioner of its intent to cancel Petitioner's eligibility for participation in the Drycleaning Solvent Cleanup Program and of the reason for the cancellation. According to the notice of cancellation, the reason for the cancellation was that Tux Cleaners had "fail[ed] to continuously comply with the conditions of eligibility set forth in s. 376.3078(3), F.S." The February 26, 1998, letter stated, in pertinent part, the following: The Department has determined that the referenced site is no longer eligible to participate in the Drycleaning Solvent Cleanup Program for the following reason: Pursuant to s. 376.3078(7)(a), Florida Statutes (F.S.), owners or operators of drycleaning facilities shall by January 1, 1997, install dikes or other containment structures around each machine or item of equipment in which drycleaning solvents are used and around any area in which solvents or waste- containing solvents are stored. As of January 21, 1998, secondary containment had not been installed at the referenced facility. Failure to meet this requirement constitutes gross negligence (s. 376.3078(7)(d), F.S.). Also, failure to meet this requirement constitutes a failure to continuously comply with the conditions of eligibility set forth in s. 376.3078(3). Pursuant to s. 376.3078(3)(n)1., F.S., the Department shall have the authority to cancel the eligibility of any drycleaning facility or wholesale supply facility that fails to continuously comply with the conditions of eligibility set forth in s. 376.3078(3), F.S. Persons whose substantial interests are affected by this Order of Eligibility Cancellation have a right, pursuant to Sections 120.569 and 120.57, F.S., to petition for an administrative determination (hearing). The Petition must conform to the requirements of Chapters 62-103 and 28-5, F.A.C., and must be filed (received) with the Department's Office of General Counsel, 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-3000, within forty-five (45) calendar days of receipt of this Notice. Failure to file a petition within the forty-five (45) calendar days constitutes a waiver or any right such persons have to an administrative determination (hearing) pursuant to Sections 120.569 and 120.57, F.S. * * * If a petition is filed, the administrative hearing process is designed to formulate agency action. Accordingly, the Department's final action may be different from the position taken by it in this Notice. * * * This Order of Eligibility Cancellation is final and effective forty-five (45) calendar days after the date of receipt of this Order unless the attached site access form is signed and returned to the Department or unless a petition is filed in accordance with the preceding paragraph. Upon the timely filing of such petition, this Order will not be effective until further order of the Department. Please be advised that mediation of administrative disputes arising from or relating to this Order of Eligibility Cancellation is not available [s.] 120.573, F.S.; when requested the Department will continue to meet and discuss disputed issues with parties adversely affected by this order. The February 26, 1998, notice of cancellation contained a typographical error in that it referenced an "attached site access form." That reference was as follows: "This Order of eligibility cancellation is final and effective forty-five (45) calendar days after the date of receipt of this Order unless the site access form is signed and returned to the Department or unless a petition is filed in accordance with the preceding paragraph." The reference in the notice of cancellation to the site access form was irrelevant to the notice and improperly and inadvertently included in the notice. That reference should have been omitted from the notice of cancellation and the sentence which mistakenly referred to the site access form should have stated: This Order of Eligibility Cancellation is final and effective forty-five (45) calendar days after receipt of this Order unless a petition is filed in accordance with the preceding paragraph. The February 26, 1998, notice of cancellation complies with the requirements of Section 376.3078(3)(n)2., Florida Statutes, notwithstanding the aforementioned typographical error contained therein. Consistent with the statutory requirements, the letter gives written notice to the applicant of the Department's intent to cancel Petitioner's program eligibility and also states the reason for the cancellation. Section 376.3078(3)(n)2., Florida Statutes, provides that the "applicant shall have 45 days to resolve the reason for the cancellation to the satisfaction of the Department." Typically, the Department's cancellation notices do not state that applicants or participants have 45 days to resolve the reason or reasons for cancellation of their eligibility. Nevertheless, the Department affords this opportunity to adversely affected parties. To facilitate this process, the Department's cancellation notices advise these parties that, when requested, the Department will "continue to meet and discuss disputed issues with parties adversely affected by this Order." Petitioner availed itself of the opportunity to discuss the disputed issues with the Department. In fact, shortly after receiving the notice of cancellation, Petitioner contacted the Department officials to determine what steps it could take to remain eligible for participation in the Drycleaning Solvent Cleaning Program. Thereafter, Petitioner took immediate steps in an attempt to resolve the reasons for cancellation of its eligibility. After extensive discussions between Petitioner and Department officials, the Department concluded that the notice of cancellation had been properly issued. The Department reached this conclusion after Petitioner acknowledged that Tux Cleaners did not have secondary containment installed by the January 1, 1997, the statutorily prescribed deadline for such installation. Having determined that the secondary containment had not been installed by the January 1997 deadline, the Department concluded that the reason for the cancellation of Petitioner's eligibility could not be resolved or corrected. The Department has interpreted the 45-day language in Section 376.3078(3)(n)2., Florida Statutes, to allow Program applicants or participants the opportunity to resolve items that do not constitute gross negligence within the meaning of the statute. In an attempt to bring the facility into compliance, Petitioner insisted that Guarnieri shut down all drycleaning operations at Tux Cleaners and remove all machines and solvents from the property. By mid-March 1998, Tux Cleaners had shut down all drycleaning operations and by the end of March 1998, all drycleaning machines were removed from the facility. Moreover, in mid-March 1998, after the drycleaning operations ceased, Tux Cleaners continued only as a dry drop-off facility. Any store operating solely as a dry drop-off facility is not required to have secondary containment. Secondary containment was not installed at Tux Cleaners by January 1, 1997, the statutorily prescribed deadline, even though it operated as a drycleaning facility from January 1, 1997, until mid-March 1998. Consequently, beginning in January 1, 1997, and through March 1998, Petitioner and Tux Cleaners were not in compliance with the eligibility requirements of the Drycleaning Solvent Cleanup Program.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby: RECOMMENDED that the Department issue a final order finding that Petitioner's facility is not eligible to participate in the Drycleaning Solvent Cleanup Program. DONE AND ENTERED this 10th day of January, 2000, in Tallahassee, Leon County, Florida. CAROLYN S. HOLIFIELD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of January, 2000. COPIES FURNISHED: Martha L. Nebelsiek, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Richard M. Hanchett, Esquire Trenam, Kemker, Scharf, Barkin, Frye, O'Neill & Mullis, P.A. 2700 Barnett Plaza 101 East Kennedy Boulevard Post Office Box 1102 Tampa, Florida 33601-1102 Kathy Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000