Findings Of Fact At all times relevant hereto, Respondent, Roger S. Williams, held registered building contractor license number RB0026339 issued by Petitioner, Department of Professional Regulation, Construction Industry Licensing board, authorizing him to perform contracting under his individual name. Respondent, Frederick S. Schreiner, held certified general contractor's license numbers CG C004811 and CG CA04811 also issued by Petitioner authorizing him to perform contracting under his individual name and under Cape Development Corporation. Williams served as president of Architectural Builders, Inc. (ABI), a development firm located in Palm Bay, Florida. Schreiner was engaged in the contracting business generally in the Brevard County, Florida area. He has done construction work for ABI and Williams for the past eight or nine years. ABI held no licenses from either the state or local governments. On October 31, 1979, ABI entered into a construction contract with Jack and Stella Oleksy to construct a home at 842 South Becker Street, Palm Bay, Florida. The contract was approved by R. S. Williams as president of ABI. At a later undisclosed date, Williams attempted to pull a City of Palm Bay building permit on behalf of ABI. Whether the City gave formal or informal approval at that point is not clear; in any event the construction of the home began shortly thereafter. Several weeks later the City's chief building official told Williams that because he did not have local competency with the City, he could not pull a permit for a job. Williams was also advised that a recent change in state law required ABI to qualify to do business if ABI intended to construct homes within the City. When told that Frederick Schreiner would be constructing the home for ABI and that Schreiner held an appropriate license, the City official told Williams to have a construction contract executed between ABI and Schreiner to build the home. Thereafter, Schreiner pulled a permit for the job and posted it on the building site. He also gave the City a contract executed by he and ABI and which was dated November 29, 1979. During the course of the construction, Schreiner visited the building site approximately six to eight times. The work was done entirely by subcontractors who had been used on other construction jobs by Williams and Schreiner. The subcontractors were paid by ABI but worked under the supervision of Schreiner. When the job was completed Williams signed the final payment affidavit on which it was indicated that Williams was the contractor on the job. Oleksy was on the site daily to inspect the work. He complained periodically about various aspects of the job to Roger Williams. His main complaint concerned the trusses on the roof which he contended were out of alignment causing a wavy and uneven roof line. After the house was essentially completed, Oleksy lodged a complaint with Williams concerning the workmanship on the roof. Williams sent a carpenter to visit the premises who found some "variations" and worked for approximately three hours to correct the problem. He was then told by Oleksy it looked okay. Within the next few days, Oleksy again complained to Williams that the roof was wavy. Williams then sent out a roofing crew to attempt to correct the problem. After they completed their work, Williams received no further indication that the owner was unhappy. Williams later had a local relator familiar with the subdivision and an experienced carpenter who had framed more than 150 homes to view the roof. Both concluded the roof was of good workmanship and of similar quality to other homes in the neighborhood. Oleksy later filed a complaint with the City of Palm Bay concerning his roof. The City sent its chief building official to inspect the home. He described the roof as being of "poor workmanship". The same conclusion was reached by the city building inspector who also inspected the property. Because of this, the City made the notation "Hold problem roof" in its file and did not issue a certificate of occupancy to Oleksy. However, the City did not construe the roof to constitute a violation of the building code. Respondents asserted that a 1979 change in the law as to the qualification of agents caused doubt and confusion as to what was required by ABI and Williams. They also point out that if indeed a violation occurred, it was not intentional. Rather, Respondents simply desired to comply with all applicable statutes and regulations so that their construction businesses could continue to operate in a lawful manner. Other than the alleged violations herein, Respondents were not shown to have been subject to any prior disciplinary proceedings.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Roger S. Williams, be found guilty as charged in Count I, and be given a public reprimand. the remainder of the charges should be dismissed. It is further RECOMMENDED that Respondent, Frederick L. Schreiner, be found guilty as charged of all allegations except willfully and deliberately violating a state law, and be given a public reprimand. DONE and ENTERED this 29th day of June, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1982.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Ramiro Palma, be found guilty as charged in the Administrative Complaint dated August 31, 1981. It is further RECOMMENDED that Respondent's registered building contractor's license be suspended for one year after the date of the final order entered in this proceeding and that Respondent pay a $1000 administrative fine. DONE and ENTERED this 3rd day of February, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of February, 1982.
The Issue The issue for consideration at this hearing is whether Respondent's certification as a communications systems specialty contractor in Pinellas County should be disciplined because of the matters alleged in the Administrative Complaint filed herein.
Findings Of Fact At all times pertinent to the issues herein, the Petitioner, Pinellas County Construction Licensing Board, was the county agency responsible for licensing contractors in the construction trades in Pinellas County and for the regulation of the profession of contracting in that county. Respondent, Michael G. Linton held license No. C-5513 as a certified communications systems specialty contractor in Pinellas County. On or about June 14, 1995, Kim and Vincent Carter, tenants at a residence located at 118 7th Street in Belleair Beach, Florida, contacted Respondent to secure his assistance in moving the satellite reception dish which he had initially installed for them to their new residence. On that date, Respondent issued an invoice to the Carters on which he indicated he was to reinstall their satellite system for $300.00. The statement was signed by Respondent and also bears the apparent signature of V.J. Carter. Mr. Linton claims it was Mrs. Carter who signed the statement authorizing the work, however, but she denies it and Mr. Carter claims it was he who signed it. Mr. Carter disconnected the system inside the residence and helped to take down the outside dish. Respondent moved the dish from the Carter's old residence to their new residence where it was to be reinstalled. Respondent did not pull a permit from the City of Belleair Beach to construct the base for the antenna dish. A permit was required. Mr. Linton claims he did not dig the hole for the base into which he poured the cement but that the base hole was dug by Mr. Carter. Mr. Carter denies having done so. Whoever dug the hole, it did not meet code requirements since it was only 20 inches deep and the code requires a base of concrete at least 48 inches deep. The length and breadth of the slab depends on the size of the satellite dish and the length of the pole on which it will be affixed. The Carters deny that they agreed to pull the permit for this work, claiming that since they are not the owners of the property, they cannot do so. This is not so, however, because, under the terms of the Code, (Section 6- 3(a)(1), either the owner of the property or the authorized agent of the owner can pull the permit. If authorized by the owner of the new residence, either the Carters or the contractor may have pulled the permit. Neither did. Respondent claims he was hired by the Carters only to help them move their satellite system. He was to be paid between $300.00 and $350.00, and Mr. Carter was to help. Because Carter and Mr. Moore, the building official, were old friends, Carter was to pull his own permit and that was put on the invoice. The Carters claim this notation was not there when they signed the invoice. Respondent claims he would have charged $150.00 extra to pull the permit. Respondent admits he holds himself out as a communications systems contractor and that he was retained by the Carters to do work related to the move of their satellite system from one residence to another, but only to help Mr. Carter. He admits he knew a permit was required for the construction of the new base and, though he may not have known whether a permit had been pulled before he poured the new base, he did not pull it himself or insure that one had been pulled. He now admits he should not have relied on the Carters' representations that they would take care of it. He also did not insure that the base which was poured conformed to the requirements of the approved engineering for the installation. The city's building official, Mr. Moore, inspected the work site, on two separate occasions. He first found the hole to be too shallow. When he came back to reinspect, the cement had been poured and he could not gauge the depth, finally accepting the certification of the subsequent contractor that the base conformed to specifications. The conforming work was not done by Respondent but by a subsequent contractor hired by the Carters, Satellite Communications and Electronics, Inc. The Carters were billed an additional $250.00 for this follow up work. This included a fee of $150.00 for pulling the required permit.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County Construction Licensing Board enter a Final Order finding Respondent guilty of the offenses alleged, placing his license on probation for six months, and imposing an administrative fine of $250.00. DONE and ENTERED this 12th day of April, 1996, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of April, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 95-5933 To comply with the requirements of Section 120.59(2), Florida Statutes (1993), the following rulings are made on the parties' proposed findings of fact: Petitioner's Proposed Findings of Fact. None submitted. Respondent's Proposed Findings of Fact. Respondent's counsel did not number the facts urged in that portion of his submittal described as "Respondent's version Of The Facts." Therefore, the four paragraphs in that section will be addressed individually. Accepted. Accepted, but the contractor must not begin work without a permit being issued. Not a proper Finding of Fact but a comment on the state of the evidence. Accepted. COPIES FURNISHED: William J. Owens Executive Director Pinellas County Construction Licensing Board 11701 Belcher Road, Suite 102 Largo, Florida 34643-5116 Louis Bakkalapulo, Esquire The Wilder Center Suite 404 3000 Gulf to Bay Boulevard Clearwater, Florida 34619
The Issue Whether the Respondent committed the violation alleged and, if so, what penalty should be imposed.
Findings Of Fact The Petitioner is the state agency charged with the responsibility of regulating building code administrators and inspectors. At all times material to the allegations of this case, the Respondent was either an applicant for licensure or held a building inspector license, license number BN 0002765. At all times material to this case, the Respondent was employed by the Martin County Building Department as a Building Inspector. Harriet R. Edwards owns a residence located at 2595 Hickory Avenue, Jensen Beach, Florida. This home is located in Martin County, Florida. At some point in early 1996, it became Ms. Edwards' desire to construct an addition to her residence. She retained a contractor to perform the work and returned to Ohio during the time of the construction. When Ms. Edwards returned to Florida she was dissatisfied with the quality of the work. Mr. Joyce, Ms. Edwards' friend, expressed that they had expressed a desire for, and requested only, a high quality of work for the addition to Ms. Edwards' home. Upon investigation it was discovered that the permit card located at the construction site had been initialed by the Respondent. All of the inspections listed on the permit card occurred prior to December 17, 1996. The Respondent was issued a provisional license to perform building inspections on or about December 17, 1996. All of the inspections initialed by the Respondent had been performed by another inspector employed by the Martin County Building Department, Bobby T. Chambers. Mr. Chambers was fully licensed at the times of the inspections and acted as the Respondent's training supervisor. The Respondent accompanied Mr. Chambers during a training period during which time Mr. Chambers was to instruct the Respondent in the procedures and practices of the Martin County Building Department. At all times material to the allegations of this complaint, the Martin County Building Department allowed unlicensed employees to assist its inspectors at construction sites. Such employees were authorized to initial permit cards and to radio to the main office the information regarding inspections performed at the job sites. Because of this informal and haphazard reporting system the official records maintained by the County falsely reflected that the Respondent had performed the inspections listed in this Administrative Complaint. He did not. The records were maintained inaccurately. By initialing the permit card and transmitting the information to the County, the Respondent was performing his duties as an employee-in-training and as directed by his supervisors. The Respondent did not intend to mislead officials and did not intend to file a false report required by law. As a result of the flawed training system used by the Martin County Building Department, this Respondent initialed permit documents prior to licensure.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Building Code Administrators and Inspectors Board, enter a final order dismissing the Administrative Complaint against this Respondent. DONE AND ENTERED this 23rd day of October, 2000, in Tallahassee, Leon County, Florida. J. D. Parrish Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 2000. COPIES FURNISHED: Dorota Trzeciecka, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399 Michael A. Rodriguez, Esquire County Attorney's Office 2401 Southeast Monterey Road Stuart, Florida 34996 Leif Grazi, Esquire LAW OFFICES OF GRAZI & GIANINO, P.A. 217 East Ocean Boulevard Stuart, Florida 34995 Anthony B. Spivey, Executive Director Building Code Administrators and Inspectors Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
The Issue Whether or not the business Respondent was associated with exceeded the scope of his contractor's license concerning the type of work undertaken, as described in the Amended Administrative Complaint, thereby violating Sections 489.129(1)(j), 489.115(1) and 489.117(2), F.S.? Whether or not Respondent failed to properly supervise the job site activities on that job, thereby violating Sections 489.129(1)(m), (j); 489.119, and 489.105(4), F.S.? Whether or not Respondent committed gross negligence, incompetence, or misconduct in connection with said job in violation of Section 489.129 (1)(m), by failure to supervise the contracting activities of the contracting business he was responsible for, so that Jorge Otero, President of Deluxe Construction Co., could obtain a building permit, exceed the scope of Respondent's license, and perform work that exhibited numerous defects? BACKGROUND AND PROCEDURE At the commencement of formal hearing, the parties stipulated ore tenus that Paragraph 6 of the Amended Administrative Complaint would be further amended to read: The business Respondent was associated with exceeded the scope of his license concerning type of work, violating Section 489.129(1)(j); 489.115(1)(b); 489.117(2). Thereafter, they entered into certain stipulated facts which are reflected among additional facts as found in this recommended order. Petitioner presented the oral testimony of Lolv Jaramillo, Herbert Gopman, Jorge Otero, and Frank Abbott, and had admitted four exhibits. Respondent presented neither oral testimony nor offered any exhibit. No transcript was provided. Respondent late-filed its post-hearing proposals, but each party's proposed findings of fact have been considered and are ruled upon in the appendix to this recommended order, pursuant to Section 120.59(2), F.S.
Findings Of Fact At all times material, Respondent was a licensed certified building contractor in the State of Florida, holding license number CB C002799 and was listed as the sole qualifying agent for Deluxe Construction Company. Deluxe could have had more than one qualifying agent but it did not. Jorge Otero was the sole owner, officer, and director of Deluxe Construction Company (Deluxe). He is not now, and never has been, a licensed contractor. Deluxe was formed in 1986, and Otero operated the company out of his home. In August 1986, Deluxe contracted with Lolv Jaramillo to remodel the Jaramillo residence in Miami for $23,800. Prior to the Jaramillo job, Deluxe had remodeled or added to several other residences. On those jobs, Respondent signed the building permit applications brought to him by Otero and made periodic inspections of the work, but Respondent never accepted any compensation from Deluxe for his services as qualifying agent of the company. Respondent was employed full-time otherwise. Before the Jaramillo job, Otero had had similar relationships with other contractors. Prior to beginning construction, Respondent met the Jaramillos at their residence at the request of Otero to discuss the possibility of the Jaramillos arranging a second mortgage through the brokerage firm which was Respondent's regular full-time employer. The Jaramillos were not told, and were not aware, that Respondent was affiliated with Deluxe. They relied on no representations of Respondent in eventually selecting Deluxe to do their construction job. The eventual contract between the Jaramillos and Deluxe was not conditioned on borrowing from Respondent's regular employer, and, in fact, the Jaramillos did not borrow from Respondent or his employer and obtained their financing elsewhere. The Jaramillos eventually instructed Otero to begin work, which he did. Otero first obtained the necessary building permit by going to the building department, filling in Respondent's contractor's license number on the application there, and signing his own name as qualifier. When Otero signed for the building permit, Respondent was out of town. Otero did not inform Respondent in advance of what he was going to do nor did Respondent discover Otero had done this until much later. On all previous contracts, Respondent had signed the permit applications and made the inspections in the manner described in finding of fact 5, supra. Respondent had done nothing to encourage Otero to think he could obtain a building permit as he did for the Jaramillo job. After Deluxe began construction at the Jaramillos' home, Otero was the sole supervisor on the job. After the Jaramillos paid Deluxe $14,000 of the contract price, they became dissatisfied with the pace and quality of the work done by Deluxe and they terminated the contract. According to Harry Gopman, structural engineer, the work done by Deluxe contained violations of local construction codes, but there is no evidence that Otero, Respondent, or anyone associated with Deluxe was convicted or found guilty of any crime. The work undertaken by Deluxe included plumbing work which Respondent was not licensed to perform. The work done by Deluxe and subcontractors under its supervision contained deviations from acceptable industry practice, including rendering a major load-carrying girder useless by penetrating it for the insertion of an air duct for the central air-conditioning system; cutting a concrete doorway lintel for insertion of another air duct, thus destroying the structural integrity of that lintel; and creating a structural hazard by placing a flat roof on the rear addition which severely "ponded" in rainstorms. From the evidence as a whole, it may be inferred that Respondent originally knew he was the sole qualifying agent for Otero/Deluxe. Otero did not affirmatively tell Respondent he had another qualifying agent for the job. However, since Otero kept telling Respondent that the Jarmillos were still having trouble getting financing, it was reasonable for Respondent to believe a building permit was not needed and construction would not begin until financing was found. It was after the commencement of construction, but prior to the termination of the contract by the Jaramillos, that Otero finally informed Respondent that he had begun work on the Jaramillo residence. It is not clear whether Respondent knew that the building permit bore his license number until after the termination of the contract. Respondent never visited the Jaramillo job site during construction. Respondent did not monitor the company finances, did not review subcontractual agreements, did not review invoices from subcontractors and materialmen, and did not call for inspections on the Jaramillo job. There is unrefuted expert testimony by Frank Abbott, architect and licensed general contractor, that a qualifying agent should do the things, but there is insufficient evidence to show that Respondent had a clear understanding that such was his position for the Jaramillo job.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing all charges against Respondent. DONE and RECOMMENDED this 31st day of August, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-0654 The following constitute rulings pursuant to S. 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of fact (FOF). Petitioner PFOF: 1-7, and 9-15. Accepted as modified to more exactly reflect the unrefuted testimony. 8. Accepted except for hearsay and subordinate and unnecessary material. Respondent's PFOF: 1-5, 7, 9. Accepted as modified to more exactly reflect the unrefuted testimony. 6. Rejected as stated. FOF 7 and 12 more correctly reflects the state of the record as a whole. 8. Rejected as stated because as stated it is a legal conclusion. A finding of fraud requires a finding of an affirmative intent which cannot be made upon the evidence presented. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 103 North Monroe Street Tallahassee, Florida 32399-0750 Lance Armstrong, Esquire 1035 Northwest 11th Avenue Miami, Florida 33136 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================