SUWANNEE RIVER WATER MANAGEMENT DISTRICT vs. NORMAN LEONARD, 88-001445 (1988)
Division of Administrative Hearings, Florida Number: 88-001445 Latest Update: Jun. 25, 1992

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Respondent owns real property located in Township 2 North, Range 7 East, Section 32, in Madison County, Florida, that has surface water flowing through it and is encompassed within what is defined as "wetlands." Respondent is in control and possession of the property in question and all work on the property that is material to this proceeding is under the control or direction of the Respondent. There were access roads on the property as early as 1973 as reflected by Respondent's exhibit 2, a 1973 aerial photograph, but the width of the roads or the existence of ditches or culverts cannot be determined from the photograph. Petitioner's exhibit 2, a 1981 aerial photograph, shows the roads still in existence in 1981 but the width of the roads or existence of ditches or culverts cannot be determined from the photograph. Sometime before the Respondent purchased the property and began construction to expand the roads, ditches and culverts were in place; however, there was no evidence as to when the ditches and culverts came to be in place. A 1976 survey of the property reflects 60 foot roads which were to provide access to platted but unrecorded lots. These roads had not been constructed when Respondent purchased the property or began construction to expand the roads. The newly constructed portions of the road indicates an attempt to build the roads in accordance with the 1976 survey. The previously existing roads attempted to follow the natural contour of the land and as a result were not always straight, and only had a negligible effect on the flow or storage of surface water in regard to the property. Sometime around October 1987, Respondent began to rebuild and construct roads on the property by straightening existing curves, removing fill material from adjacent wetlands to widen and heighten the existing roadbed or construct a new roadbed, and to increase the depth and width of existing ditches or dig new ditches. The initial portion of the existing road providing access to the property from the county graded road has been substantially rebuilt with portion of the roadbed being 40 to 43 feet wide. Ditches along this portion of the roadbed have had their width increased up to 14 feet and their depth increased up to 6 and 8 feet. Other portions of the road has been expanded beyond the previously existing roadbed by increasing the width and height of the roadbed. The increased size of the ditches and the expanded roadbed has increased the interception of surface water above that already being intercepted by the previous roadbed and ditches and, as a result, there is an increased amount of surface water impounded or obstructed. The effect is that surface water is removed from Respondent's property at a faster rate than before road construction began and, as a result, sheet flow of surface water is decreased which diminishes the storage of surface water on the property. Although new culverts were installed during road construction, there was insufficient evidence to show that these new culverts were in addition to the culverts already in place or if they replaced old culverts. There was insufficient evidence to show that the new culverts allowed water to flow in a different direction or be removed from the property at a faster rate than before or if they impounded or obstructed surface water more so than before. The previously existing roads had sufficiently served an earlier timber harvest on the property and, by Respondent's own testimony, were sufficient for his ongoing hog and goat operation. The extensive rebuilding and constructing of roads in this case was neither necessary nor a customary practice for construction of farm access roads in this area. Respondent is engaged in the occupation of agriculture in that he has a bona fide hog and goat operation. However, Respondent's silviculture occupation is somewhat limited in that he is presently harvesting the timber but shows no indication of replanting or continuing the forestry operation upon completing the present harvesting operation. The extensive rebuilding and constructing of roads in this case goes beyond what is necessary or is the customary practice in the area for a hog or goat operation or forestry operation such as Respondent's and is inconsistent with this type of agriculture or silviculture occupation. Respondent has never applied for nor received a surface water management permit from the Petitioner even though the Petitioner has informed Respondent that a permit was required for the work being done on his property. The present alteration of the topography of the land by Respondent has obstructed and impounded surface water in such a fashion that the interruption of the sheet flow of surface water has been increased, causing the storage of surface water on the property to be diminished. At the present time, Respondent has been enjoined by the Circuit Court of Madison County, Florida, from any further activity on this project. However, should Respondent be allowed to complete this project, it is evident that the sole and predominant purpose would be to impound and obstruct the sheet flow of surface water and diminish the storage of surface water on the property in question.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore, RECOMMENDED that the Petitioner, Suwannee River Management District, enter a Final Order requiring Respondent, Norman Leonard, to: (a) remove all unauthorized fill material placed within jurisdictional wetlands and return those areas to predevelopment grades and revegetate with naturally occurring local wetlands species to prevent erosion; (b) back fill excavated swale ditches, return road beds and excavated ditches to predevelopment condition and grades and seed disturbed non-wetland areas with a 50:50 mix of bahia and rye grass and; (c) refrain from any other development until and unless a required permit is obtained for such development. Respectfully submitted and entered this 13th day of February, 1989, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 1989. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 88-1445 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner 1. Adopted in Finding of Fact 1. 2.-3. Adopted in Finding of Fact 2. 4.-7. Are unnecessary findings for this Recommended Order. Adopted in Finding of Fact 18. Adopted in Finding of Fact 19. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Subordinate to the facts actually found in this Recommended Order. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12. Rejected as conclusions of law. Adopted in Findings of Fact 3 and 4. Adopted in Finding of Fact 8. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 8. Adopted in Finding of Fact 6. Adopted in Finding of Fact 7. Adopted in Finding of Fact 6. Adopted in Finding of Fact 10. Adopted in Findings of Fact 15 and 17. 26.-29. Adopted in Finding of Fact 12. 30. Adopted in Finding of Fact 13. 31.-32. Subordinate to facts actually found in this Recommended Order. Adopted in Finding of Fact 12. Adopted in Finding of Fact 16. 35.-38. Subordinate to facts actually found in this Recommended Order. 39.-42. Rejected as not being relevant or material. Specific Rulings on Proposed Findings of Fact Submitted by Respondent 1. The first paragraph adopted in Finding of Fact 16. The balance is rejected as a conclusion of law. 2.-3. Rejected as not being relevant or material. Not a finding of fact but a statement of testimony. However, it is subordinate to facts actually found in this Recommended Order. Rejected as not supported by substantial competent evidence in the record. The more credible evidence is contrary to this finding. COPIES FURNISHED: Janice F. Baker, Esquire Post Office Box 1029 Lake City, Florida 32056-1029 Norman Leonard, Pro Se Route 2, Box 172-D Live Oak, Florida 32060 Donald O. Morgan Executive Director Suwannee River Water Management District Route 3, Box 64 Live Oak, Florida Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Florida Laws (4) 120.57373.119373.406373.413 Florida Administrative Code (2) 40B-4.104040B-4.1070
# 1
ELSBERRY AND ELSBERRY vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-002095 (1975)
Division of Administrative Hearings, Florida Number: 75-002095 Latest Update: Mar. 21, 1977

Findings Of Fact Application 7500165 requested average withdrawal of water of 1,804,750 gallons per day from 4 wells located about a mile east of Highway 41 and a mile north of Apollo Beach. The four wells would be for irrigation of tomato crops on total acreage of 4 acres located in Hillsborough County (Exhibit 1, Testimony of Elsberry and Boatwright). Notice of hearing as to the application was published in a newspaper of general circulation in accordance with statute and rule (Exhibit 3). A letter of objection from Joseph S. Benham, Apollo Beach, Florida, dated November 19, 1975 was submitted to the Water Management District, wherein he expressed concern regarding water shortages and, although he does not seek to totally deny the application, is of the belief that the district must insure sufficient controls and management of irrigation activities so that resources are not wasted, water runoff to drainage ditches is eliminated and renewed justification is given each year for the withdrawal (Exhibit 2). A representative of the District staff established that there would be no violation of statutory or regulatory requirement for issuance of a consumptive water use permit in this case except as to the fact that potentiometric level of the applicant's property would be lowered below sea level as a result of withdrawal. It was agreed at the hearing that a period of thirty days should be granted both parties to formulate a stipulation as to control of runoff. An unsigned stipulation was received from the Water Management District by the hearing officer on March 1, 1976, which provided that the permit would be granted with the following stipulations: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expense install metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. (Testimony of Boatwright, Exhibit 4).

Recommendation That application 8500165 submitted by Elsberry and Elsberry, Inc. Route 2, Box 70 Ruskin, Florida, for a consumptive water use permit be granted with the conditions as follow: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expenseinstall metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. That the Board grant an exception to the provision of Rule 16J- 2.11(4)(e), F.A.C., for good cause shown. DONE and ENTERED this 15th day of March, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Elsberry & Elsberry, Inc. Route 2, Box 70 Ruskin, Florida

# 2
ROSE ANN DE VITO vs JOHN FALKNER, CHRISTOPHER FALKNER, AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 95-005763 (1995)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Nov. 27, 1995 Number: 95-005763 Latest Update: Jun. 03, 1996

The Issue The issue in this case is whether the application of Respondents Falkner to transfer and modify a Water Use Permit should be approved.

Findings Of Fact The Southwest Florida Water Management District (District) is responsible for regulation and protection of water resources in the geographic area involved in this proceeding. Since 1994, John Falkner has owned the property in Hillsborough County which is the subject of this proceeding. The Falkner property is farmed by Christopher Falkner, the owner's brother. Prior to purchasing the land, the Falkners farmed the property, also known as the Rogers farm, through a lease arrangement with the previous owner. Rose Ann DeVito owns property to the south of the Falkner property. In the time since Ms. DeVito purchased the property, the elevation of Sumner Road has been raised and culverts were replaced. A fish farm was constructed in close proximity to her property. The result of this and other development has been to direct all the water flow from the surrounding area into the stream adjacent to the DeVito property. Drainage patterns in the area of Ms. DeVito's property have been altered since she first occupied the property. A ditch along Sumner Road which used to handle runoff from her property has been blocked by a neighbor's driveway. Maintenance on the ditch, allegedly a county responsibility, is described as poor. The ditch at the rear of Ms. DeVito's property handled water flow to Bullfrog Creek until the water flow became blocked, and the water diverted onto her property. The effect is that Ms. DeVito's property often contains a large amount of water. A substantial amount of sand is visible on her property, allegedly deposited by water flow. According to Ms. DeVito, both the county and the District have blamed the Falkner farm for the water-deposited sand. Charles and Diana Booth own property adjacent and to the south of the Falkner property. From 1992 to 1994, the Booths suffered from water running off the Falkner/Rogers farm and flooding the Booth property. A flood of the Booth property in the Fall of 1994 was not caused by irrigation but was related to a ten inch rainfall event at the Falkner farm. A ten inch rainfall exceeds a 25 year storm event and would likely result in widespread flooding. The Booths' pasture, top soil and driveway were eroded by the flooding. During the two years of flooding, Mr. Booth complained on several occasions about the flooding to the Falkners' foreman, "Cleo." The complaints were not relayed to Mr. Falkner. In October 1994, Mr. Booth reported the problem to the Southwest Florida Water Management District. Soon after the complaint was made, a representative of the District inspected the property and determined that a ditch needed maintenance. Shortly thereafter, the ditch was cleaned and a berm was installed to redirect runoff away from the Booth property. There has been no further flooding of the Booth property. In October 1995, Mr. Booth became concerned that a ditch was filling with sand and would not continue to handle the runoff. After voicing his concern, a water diverter was installed in the ditch and appears to have remedied the situation. At the time the Falkners began to lease the Rogers property, an existing water use permit, numbered 206938.01, had been issued and was valid for the farm. The Falkners have applied to transfer the existing water use permit from the previous property owner. The Falkners also seek to modify the permit, increasing the total quantities which can be pumped by transferring previously approved quantities from another permit the Falkners currently hold. All of the relevant wells are within the District's Most Impacted Area (MIA) of the Tampa Bay Water Use Caution Area. The District allows a permit holder within the MIA to increase withdrawals from a well by transferring the quantities from another permitted well within the MIA. The other Falkner farm (the "301 farm") from which the quantities would be transferred is located approximately one-half mile to the south of the Rogers farm and is within the MIA. The District reviewed the application and, on September 29, 1995, issued its Proposed Agency Action to Issue Water Use Permit No. 206938.03. The proposed permit includes special conditions requiring monthly pumping reports, water quality reports, adherence to District irrigation allotments (irrigation levels established by the AGMOD computer model) and crop reporting. In reviewing the application the District utilized the criteria set forth in Florida Administrative Code, and the Basis of Review, incorporated into the code by reference. In order to obtain a Water Use Permit, an applicant must demonstrate that the water use is reasonable and beneficial, is in the public interest, and will not interfere with any existing legal use of water. Additionally, the applicant must provide reasonable assurances that the water use: will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters; will not adversely impact offsite land uses existing at the time of the application; will not cause water to go to waste; and will not otherwise be harmful to the water resources within the District. The uncontroverted evidence establishes that the water use is reasonable, beneficial and is in the public interest. The Falkners irrigate farmland to produce agricultural products. The production of food is in the public interest. The proposed use is reasonable and beneficial. Further, uncontradicted evidence and opinions of expert witnesses establish that the proposed use will not interfere with any existing legal use of water. The applicant must provide reasonable assurances that the water use will not cause quantity or quality changes which adversely impact the water resources, including both surface and ground waters. The evidence establishes that pumping from the Falkner wells will not adversely affect the quality of water within the aquifers from which the water is drawn. Mr. Booth asserted that he is having water quality problems, specifically with rust in his well. The Booth well is approximately 25 years old. There is no evidence that the rust is related to the Falkner pumping. The DeVito and Booth wells draw from the Intermediate aquifer. Review of the potentiometric surface map of the intermediate aquifer indicates that there is a water level variation of 17 feet between the rainy and dry seasons. The result of the variance can be "dry" wells. There are two wells on the Falkner/Rogers property relevant to this proceeding. The first (District ID number 1) is 770 feet deep, is cased to a depth of 160 feet, and opens to the Floridan aquifer. The second (District ID number 2) is 1100 feet deep, is cased to a depth of 140 feet, and opens to the Intermediate and the Floridan aquifers. A cased well does not withdraw water from the formations through which the casing is placed. For example, a well cased to a depth of 160 feet draws no water from the top of the casing (at approximately ground level) to the bottom of the casing at 160 feet. The Intermediate aquifer releases water at a much slower rate than the Floridan aquifer. Based on the type and location of the Falkner wells, the vast majority of the water pumped by the Falkners comes from the Floridan aquifer. Impacts on existing wells are calculated through computer modeling. The "MOD" flow model demonstrates impacts that will occur after 90 days of pumping at peak month levels with no recharge to the aquifer. The MOD flow model results in a conservative "worst case" projection. The MOD flow model calculation projects the drawdown at Falkner well number 1 to be approximately .9 feet. The MOD flow model calculation projects the drawdown at Falkner well number 2 to be approximately 1.4 feet. The MOD flow model calculation projects the drawdown at the Booth well to be approximately one-half foot. The impact on the DeVito well will not exceed that projected at the Booth well. District permitting criteria allow for projected MOD flow model drawdown impacts of less than five feet at existing wells. The impact possible after approval of this application falls well within the District's guidelines. The impact of pumping if the application at issue in this proceeding is approved will result in a maximum variation of one-half foot at the Booth well. The evidence fails to establish that any problems related to water quantity encountered by the Booths are related to agricultural pumping at the Falkner farms. The evidence also establishes that, based on the existing retention and drainage system, the proposed use will not adversely impact surrounding surface water bodies. A system of swales and ditches is utilized to retain the water on the farm property. The evidence fails to establish that runoff from the Falkner/Rogers farm will adversely impact surrounding surface waters if this application is approved. The applicant has provided reasonable assurances that the water use will not adversely impact offsite land uses existing at the time of the application. The evidence establishes that the runoff from the Falkner farm does not discharge directly to the stream at the rear of the DeVito property. Other agricultural property discharges into the stream adjacent to the DeVito property. There is a steady waterflow through the stream at all times, whether or not the Falkner pumps are operating. Ms. DeVito's property consists of Myakka soil, which has little capacity to absorb rainfall and generates large amounts of runoff. The altered drainage patterns in the area have resulted in substantial water on her property. The evidence in insufficient to establish that the Falkner farm pumping has resulted in flooding on Ms. DeVito's property. The evidence fails to establish that approval of the application at issue in this proceeding will cause adverse impact to the DeVito property or will result in water quality or quantity problems. The Booths are concerned that the existing drainage system will not be maintained and that increased pumping will result in their land being flooded again. The evidence fails to establish a substantial likelihood that the Falkner farm drainage system will not be maintained. The applicant has provided reasonable assurances that the water use will not cause water to go to waste. The Falkners use a semi-enclosed seep irrigation system at the Rogers farm. Irrigation is only used when necessary. Mushroom compost, humates, and plastic mulch retain moisture in the soil. A special condition of the permit requires the Falkners investigate the feasibility of tail water recovery and reuse. The applicant has provided reasonable assurances that the use will not otherwise be harmful to the water resources within the District. The permit application results in no increased withdrawal of water than is allowed under the existing permits for the Rogers and the "301" farms.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Southwest Florida Water Management District enter a Final Order granting the Falkner application and issuing permit number 206938.03. DONE and ENTERED this 26th day of April, 1996 in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1996. APPENDIX TO RECOMMENDED ORDER, CASES NO. 95-5763 and 95-5764 To comply with the requirements of Section 120.59(2), Florida Statutes, the following constitute rulings on proposed findings of facts submitted by the parties. Petitioners Booth The Petitioners Booth proposed findings of fact fail to comply with the requirements of Rule 60Q-2.031(3), Florida Administrative Code, which requires citations to the record of hearing. The proposed findings are rejected as irrelevant or not supported by the greater weight of the evidence except where they are consistent with the Findings of Fact set forth herein. Respondents The Respondents' joint proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 15. Rejected, cumulative. 28-29. Rejected, subordinate. 33. Rejected, subordinate. COPIES FURNISHED: Rose Ann DeVito, pro se 11001 Sumner Road Wimauma, Florida 33598 Diana P. and Charles B. Booth, pro se 10812 Sumner Road Wimauma, Florida 33598 Patricia Petruff, Esquire Dye and Scott, P.A. 1111 Third Avenue West Bradenton, Florida 34206 Martin Hernandez, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Peter G. Hubbell, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (1) 40D-2.301
# 3
RICHARD L. BUCHANAN vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 82-003543 (1982)
Division of Administrative Hearings, Florida Number: 82-003543 Latest Update: Nov. 01, 1991

Findings Of Fact Petitioner Richard L. Buchanan owns a lot in Franklin County, which lies on the north shore of Apalachicola Bay. Shellfish harvesting is prohibited in the water adjacent to his parcel despite, or perhaps because of, oyster houses having operated in the vicinity for many years. Mr. Buchanan is not an oysterman himself, but he does fish commercially, when he is able. He owns two licensed fishing boats. He goes floundering and also fishes with gill nets. Since he acquired the property 10 or 12 years ago, Mr. Buchanan regularly loaded nets from shore and unloaded fish and nets on shore, until the prop-dredging took place, even though a dock extends out into the Bay from his property. The outboard motor is hard to handle from the dock and it is virtually impossible to load the nets from the dock without fouling them. Until the prop-dredging he could bring his boats all the way in and lay their bows on the shore along the stretch of clean sand 35 to 50 feet wide at the western end of his 145 feet of Bay frontage. There was a sheer drop to a depth, at high water, of about 3.5 feet. The Sadler boy drowned there. Before the prop-dredging disturbed it, the configuration of the bottom that allowed small boats to come all the way into shore at that point had obtained for decades. Leo Nixon Harwell, son of the former owner of petitioner's property, remembered running the Harwells' oyster boat, which drew three feet, right up on the beach. Mr. Harwell, who looked to be in his 50's, testified that there had been deep water next to the shore ever since he was "no yearly boy." The further from shore the deeper it got till you reached Two Mile Channel. Between the sandy beach and the channel there was no vegetation to speak of although there was a marshy swash to the east of the sandy beach. In 1979, when Arman Earl Cloud had to haul his bay shrimper for repairs, he floated it to the beach in back of Mr. Buchanan's house and pulled it up on the beach, using rollers. The bow floated to the water's edge. The boat had a length overall of 25 to 28 feet, a beam of nine feet and drew three to three and a half feet of water. An oyster house sits on the next parcel west of the Buchanan property. The oyster house belongs to a man named Page, and a dock 100 feet long juts out toward Two Mile Channel from the oyster house. It used to be impossible to get an oyster boat in any closer to shore. When John Paul Whitehead was oystering some years back, they used to have to anchor out and transfer the oysters to a skiff to get them to the Page oysterhouse. In fact, when Diane Collins rented the oysterhouse (from Bobby Youngblood) in 1974 or 1975 it was impossible to bring even a flat-bottomed boat in as far as the waterward end of the dock. "On dead low tide all you seen was sand on either side of the dock." According to unrebutted testimony, the Pages changed all this by prop- dredging. (Mr. Page failed to honor the subpoena requiring his attendance at the final hearing.) Prop-dredging involves fixing the bow of a boat by grounding or otherwise, and turning the propeller at speeds high enough to move soils on the bottom. Bay this technique, the Pages dredged great quantities of sand on either side of their dock. Most of the sand stayed suspended in the water only long enough to settle in front of their neighbors' property. This illegal activity was brought to the attention of the marine patrol at the time, whose warning to the Pages to desist went unheeded, and at least one employee of respondent Department of Environmental Regulation was also apprised. The prop- dredging continued for some time, usually at night, and the eventual result was "a muck hill" in front of the Miracle Seafood property abutting the Pages to the west, and a sandbar in front of Mr. Buchanan's property that completely blocks access to his sandy beach. The Pages, with 55 front feet on the Bay, can now accommodate quite a fleet at their dock. One day six to eight boats were docked there. The sandbar in front of Mr. Buchanan's property attributable to the Pages' unpermitted and illegal prop-dredging has by now been there long enough that smooth cord grass (Spartina altiflora), saw grass and maiden cane have taken root. The dredging proposed by petitioner to restore access to his shoreline would disturb some 400 square feet, on which only Spartina altiflora is growing. On about a quarter of the proposed site, there is no vegetation. The Spartina altif lora helps stabilize the shoreline, serves to filter pollutants running off into the Bay and provides a habitat and food for insects, worms, oysters, shrimp and fishes. Dredging would resuspend any heavy metals in the soil, and increase the turbidity of the water, in the immediate vicinity. There is a boat ramp 500 feet from petitioner's property. DER would issue a permit for a marine railway at the site where petitioner hopes to dredge. Apalachicola Bay is classified as Class II waters, and as outstanding Florida waters, being part of an aquatic preserve. There is a clear public interest in permitting a private citizen, who is willing to restore, at his own expense, a part of the coastline disturbed by illegal activity which he responded to the authorities at the time, to the status quo which existed for as long as anybody can remember, before the illegal activity disturbed it. In an undated letter to Mr. Buchanan, James W. MacFarland, Director, Division of State Lands, Department of Natural Resources, advised that Upon the assurance that the environmental effects are acceptable and with the understanding that DER intends to issue the permit, we will request the dredge material severance fees and issue our authorization pursuant to Section 253.77, Florida Statutes, upon the permit receipt. The credible testimony of DER staff was to the effect not that the loss of some 300 square feet of Spartina altif lora would have unacceptable environmental effects, but that the cumulative effect of projects entailing destruction of such grasses would have unacceptable environmental consequences. Respondent's proposed findings of fact, conclusions of law and proposed recommended order have largely been adopted, in substance. To the extent any proposed finding of fact has been rejected, it has been deemed immaterial or unsupported by the weight of the evidence.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner grant respondent's application for a dredging permit on such reasonable conditions, including turbidity curtains, as are necessary adequately to protect the project vicinity. DONE and ENTERED this 8th day of August, 1983, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of August, 1983. COPIES FURNISHED: E. Gary Early, Esquire Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Richard L. Buchanan P. O. Box 33 Apalachicola, Florida 32320 Victoria Tschinkel, Secretary Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (1) 253.77
# 4
GAP CREEK HOMEOWNERS ASSOCIATION vs. OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS, ET AL., 80-000996 (1980)
Division of Administrative Hearings, Florida Number: 80-000996 Latest Update: Mar. 24, 1981

Findings Of Fact Respondent, Okaloosa County Board of County Commissioners, gave notice of a new storm water discharge to the Department for the proposed replacement of a 42" diameter storm water pipe with one 48" in diameter. Notice was given in letters, telephone calls and personnel meetings between representatives of Okaloosa County and the Department. Upon investigation of the project, the Department determined that the project would not significantly enlarge the storm water discharge system, nor enlarge the watershed which the system now drains. The Department also determined that the addition of an energy dissipater, a structure not now present at the discharge end of the pipe, would improve the performance of the discharge system by limiting the velocity of the storm water discharge to 2.3 feet per second. The Department determined that the new storm water discharge would not have a significant adverse impact on the water quality or designated uses of Gap Creek. On May 6, 1980, the Department issued to Okaloosa County a letter of intent to exempt the project from storm water licensing requirements. The Department considered the following in reaching its conclusion that the replacement of the existing pipe would not significantly affect water quality or designated usage: The use of an energy dissipater structure designed to limit the discharge velocity into Gap Creek to a maximum of 2.3 feet per second. The placing of sod around all storm water inlets associated with the pipe replacement to prevent the continued entry of sand into the system; and The pipe replacement and addition of the energy dissipater will not result in a significant enlargement of the existing storm water discharge system, nor otherwise result in the drainage of a larger area. The replacement of the drainage pipe by the county will not add to the amount of water entering Gap Creek, or significantly affect the quality of water in the Creek. Presently, storm water runoff travels within a county-owned drainage ditch and overflows at the point where the county intends to replace the existing 42" pipe. The present pipe is not capable of handling the amount of runoff in the ditch and this results in water overflowing the drainage ditch at the mouth of the pipe and traveling by natural contour to Gap Creek. The 48" replacement pipe and energy dissipater will allow a greater volume of water to remain in the drainage ditch and divert its flow away from the front and back yards of some Gap Creek residents.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a final order be entered by the State of Florida, Department of Environmental Regulation, granting the applicant, Okaloosa County, an exemption from storm water licensing requirements for the installation of a 48" storm water pipe to replace an existing smaller pipe that enters into Gap Creek. DONE and ORDERED this 27th day of February, 1981, in Tallahassee, Leon County, Florida. SHARYN L. SMITH, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of February, 1981.

Florida Laws (3) 120.52120.565120.57
# 5
HOWARD SAUTER vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 00-002885 (2000)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida Jul. 13, 2000 Number: 00-002885 Latest Update: Jan. 10, 2025
# 6
VINCENT D`ANTONI vs DAVID BOSTON AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 99-001916 (1999)
Division of Administrative Hearings, Florida Filed:Jacksonville, Florida Apr. 28, 1999 Number: 99-001916 Latest Update: May 08, 2000

The Issue The issues are whether David Boston should be issued an environmental resource permit and sovereign submerged lands authorization allowing him to construct 96 linear feet of rip rap revetment; construct a private dock of less than 1,000 square feet; and place 3,500 square feet of fill in non-jurisdictional areas; and whether he qualifies for a general permit to place a fill pad in isolated wetlands adjacent to the St. Johns River, a Class III waterbody.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: In this permitting dispute between neighbors, Petitioner, Vincent R. D'Antoni, Jr., contends generally that Respondent, David Boston (Boston), will cause flooding to Petitioner's property by reason of placing too much fill on an isolated wetland, which lies in the center of Boston's property. The filling is in conjunction with Boston's efforts to construct a single-family residence and private dock on his property, purchased in June 1998, which lies adjacent to the St. Johns River, a Class III waterbody, in Duval County, Florida. In preliminary decisions made on November 5, 1998, and January 21, 1999, Respondent, Department of Environmental Protection (DEP), "acknowledge[d] receipt" of Boston's intent to use a noticed general permit "to fill less than 4,000 square feet of an isolated wetland to facilitate construction of a single family home" on his lot (Case No. 99-2861), and gave notice of its intent to issue Boston an environmental resource permit and sovereign submerged lands authorization allowing him to construct a rip rap revetment and a dock and to place 3,500 square feet of fill in mainly non-jurisdictional areas (Case No. 99-1916). Although a number of objections were raised by Petitioner in his original filings, as clarified at the final hearing, Petitioner now contends that Boston placed excessive fill on his lot, including an isolated wetland, and that the fill has resulted in flooding, saturated soil, or standing water on Petitioner's property. He also contends that the location of Boston's proposed dock will affect the ability to use his own dock. Because no evidence was presented on the docking issue, and through admissions Petitioner acknowledged that there will be no adverse environmental impacts, no consideration will be given to those objections. Finally, Petitioner does not object to the placement of the rip rap revetment on the shoreline. Accordingly, the request for an environmental resource permit and consent to use sovereign submerged lands in Case No. 99-1916 should be approved. The property in issue lies just south of the Jacksonville University Country Club and a few blocks west of University Boulevard North on Wayland Street, which fronts the eastern side of the St. Johns River in a tract of land known as University Park. Except for the Boston lot, all other waterfront lots are now developed. When facing the river from Wayland Street, Petitioner's lot lies to the right of Boston's lot, while another lot owned by Robert Henderson (Henderson) lies to the left of Boston's lot. The lots are up to 500 feet deep; Boston's lot is around 96 feet wide, while Petitioner's lot has a similar width but narrows to only 20 feet or so near the river. At the river end of the D'Antoni, Boston, and Henderson lots is an area of contiguous wetlands. Until 1995, DEP regulated those wetland areas and this prevented D'Antoni and Henderson from placing any fill in those areas. Under DEP's current wetland delineation rule, however, such areas are non- jurisdictional, and any placement of fill at the river end is outside the purview of DEP's jurisdiction. Before Boston's lot was cleared and filled, it was about a foot lower in elevation than the D'Antoni lot; this was true even though Petitioner has never changed the natural grade of his property since it was purchased and developed. Therefore, water tended to flow naturally from an upland area north or east of the D'Antoni lot, through the D'Antoni lot to Boston's lot, and then through the lower part of the Henderson lot populated by "very mature cypress trees," and eventually into the St. Johns River. According to a 1977 aerial photograph, the Boston lot contained what appears to be a tidal connection from an uplands area through the wetlands on his property to the river. However, construction on property adjacent to the Henderson lot sometime after 1977 severed this connection, and a tidal connection (direct hydrologic connection) to the river no longer exists. Under Rule 62-341.475(1)(f), Florida Administrative Code, "a single family residence" is exempt from the Environmental Resource Program permitting and a general permit will be granted "as long as it is not part of a larger plan of common development," and "the total area of dredging or filling in isolated wetlands for the residence and associated residential improvement shall not exceed 4000 square feet." Since there is no longer a direct hydrologic connection between the wetlands on Boston's property and the St. Johns River, the wetlands are isolated within the meaning of this rule. Availing himself of the foregoing provision, on October 19, 1998, Boston gave notice to DEP "of [his] intent to use a noticed general permit to fill less than 4,000 square feet of an isolated wetland" on his property. He also provided certain drawings and other information (prepared by his surveyor) to show that he qualified for the permit. DEP does not "issue" a noticed general permit; rather, it only determines whether the applicant qualifies for a permit and then "acknowledges" this fact. Accordingly, on November 5, 1998, DEP "acknowledge[d] receipt" of Boston's notice. Although DEP encourages the user of such a permit to notify affected or adjoining property owners, there was no legal requirement that Boston do so, and he proceeded to clear the lot and then fill a part of the wetland area with two or three feet of dirt without giving notice to Petitioner or Henderson, his two neighbors. The filling raised the elevation of the Boston property at least two feet above the D'Antoni and Henderson lots and impeded the prior natural flow of water. At the same time, Boston constructed a three to four-foot timber wall (consisting of railroad ties) on the Henderson property line to retain the fill and a similar two-foot wall on Petitioner's line. These changes had the effect of impounding the water which had previously flowed naturally in a north-south direction through the wetlands from the D'Antoni lot to the Boston lot to the Henderson lot. It also generated runoff from the Boston lot to the D'Antoni lot, which had not previously occurred. When Petitioner observed the adjacent lot being cleared and filled, and the resulting erosion of fill onto his property, pooling of water, and damage to his chain link fence after a heavy rain in January 1999, he filed a complaint with DEP. An inspection was made by DEP, and Boston was told to stop work until corrective changes were made to ensure that such flooding would not occur. After a series of changes were made which satisfied DEP's concerns, the stop work order was lifted. Boston also signed a consent order and paid a $100.00 fine. However, pending the outcome of these cases, no further construction work has occurred. Petitioner has contended that Boston has placed more than 7,200 square feet of fill on his property in violation of the rule, which limits the amount of fill to less than 4,000 square feet. While this amount of filling has in fact occurred, approximately 3,500 square feet of fill was placed in non- jurisdictional areas between the shoreline and the isolated wetlands, and the rule only requires that Boston limit his fill to less than 4,000 square feet on the isolated wetland. Thus, contrary to a suggestion by Petitioner's engineer, the jurisdictional and non-jurisdictional filling are not totaled together to determine whether the threshold within the rule has been exceeded. Through photographs received in evidence and testimony by Petitioner and his wife, it was established that flooding or standing water has occurred on Petitioner's property during heavy rainfalls since the filling occurred, even as recently as January 2000. The evidence further shows that Petitioner's chain link fence has been damaged through the weight of the fill pressing against the fence. In addition, Petitioner has suffered the loss of "a couple of trees" because of "mucky" and "oversaturated" soil caused by excessive water. Also, a dog house on a raised platform in the back yard which was previously dry now "stays in water." These affected areas lie immediately adjacent to the filled area of the isolated wetland on Boston's property. Finally, there is an erosion problem beyond the isolated wetland consisting of sand and silt flowing from Boston's lot onto Petitioner's lot during heavy rainfalls. Despite these problems, Petitioner does not object to the development of the lot; he only asks that Boston do so in a manner which prevents these conditions from recurring in the future. Petitioner's engineering expert, Ronnie D. Perron (Perron), a professional engineer who visited the site in August 1999, ran a computer model (Interconnected Channel and Pond Routing, Version 2.11) showing runoff both before and after the fill was placed on Boston's lot. He concluded that "there was over one and a half feet of flooding in that wetlands due to filling Mr. Boston's lot" during a "mean annual storm event," which assumes five inches of rain during a 24-hour period. Even when he used more conservative estimates, Perron still arrived at water accumulations ranging from 0.6 feet to 1.5 feet. This excessive runoff is caused by the retaining wall and fill, which "blocks off" the water and causes it to "spread out in [Petitioner's] whole back yard." In response to Perron's model, a DEP professional engineer, David P. Apple (Apple), ran another computer model (PONDS, Version 2.25) received in evidence as Respondent's Exhibit No. 14. That model shows that during a three-year, one- hour storm event, the small depressed area on Boston's property (including the isolated wetland) had sufficient storage capacity to absorb up to six inches of runoff from off-site areas and not overflow back onto Petitioner's property. This size of storm event (which produces two and one-half inches of rain in an hour) is typically used by the Department in calculations for single- family residential property when the impervious area site is less than fifty percent. In this case, Apple didn't "feel that the impervious area out there was greater than [fifty] percent." Therefore, Apple concluded that the storm event used by Perron was too large, and that the smaller event used in his model was more appropriate. He also concluded that the Boston property could retain all water in a normal storm event without discharging any stormwater onto the D'Antoni lot. He did not, however, address the issue of the fill and retaining wall on the Boston lot impounding the water on his neighbor's lot. In developing the input perameters for his model, Apple assumed that water falling at the front (Wayward Street) side of the D'Antoni property drained to the front roadway; in fact, much of that water drains to the rear of the lot into the wetland area. A similar incorrect assumption was made regarding runoff on the Boston lot. If modifications were made to account for the proper drainage patterns, the Apple model would show larger amounts of water staging on the Boston property during rainfall events, which would increase the possibility of runoff onto the D'Antoni lot. Apple questioned the accuracy of the Perron model given the fact that Perron had used a larger storm event than he (Apple) believed was appropriate. However, even if Perron had used a three-year, one-hour storm event on his computer model, as advocated by Apple, he established that it would have resulted in flood staging on Petitioner's property between 0.97 and 1.64 feet during a smaller storm event. DEP proposed no solutions to the water problems on the D'Antoni lot, presumably because it concluded that the rule was satisfied; that by filling the Boston lot, it was no longer the "stormwater pond for the neighborhood runoff"; and that DEP had no other regulatory authority to solve this peculiar situation. The record shows clearly, however, that if no changes are made, water will continue to back up on Petitioner's property by virtue of the higher elevation on the Boston lot, and the possibility of runoff from Boston's lot exists during certain storm events. Neither condition existed before the fill was added. To correct the foregoing conditions, Perron proposes two corrective measures. First, Boston should install a yard drain (underground culvert) beginning in the wetlands area of his property and outfalling to the cypress trees on the adjacent Henderson lot. Besides providing an outfall for the excess water, this would also help recharge the mature cypress trees on the Henderson lot. Second, D'Antoni should install a series of "yard drains" using high-density polyethylene pipes to convey the standing water on his lot directly into the St. Johns River. The expert opined that neither activity would require a permit from DEP. These modifications are reasonable and appropriate and should be used by the factioning parties. Accordingly, the installation of a yard drain should be a condition for Boston to use his noticed general permit.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting the application for a permit and consent in Case No. 99-1916 and confirming that David Boston qualifies for use of a noticed general permit in Case No. 99-2861 provided, however, that such use be conditioned on Boston constructing an underground culvert with a yard drain from the wetland area on his lot to the St. Johns River. DONE AND ENTERED this 22nd day of March, 2000, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of March, 2000. COPIES FURNISHED: Kathy Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Vincent R. D'Antoni, Jr. 3824 Wayland Street Jacksonville, Florida 32277 David Boston 2262 Orchard Street Jacksonville, Florida 32209 Francine M. Ffolkes, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

Florida Laws (7) 120.569120.57120.68373.414373.4145373.4211403.813 Florida Administrative Code (6) 18-21.005128-106.21762-330.20062-341.20162-341.21562-341.475
# 7
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs BALM ASSOCIATES, INC., 02-001116 (2002)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Mar. 19, 2002 Number: 02-001116 Latest Update: Dec. 16, 2002

The Issue The issue is whether Respondents should be subject to civil penalties and required to submit a Compliance Plan for the reasons stated in the Administrative Complaint and Order filed on January 8, 2002.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this enforcement action, Petitioner, Southwest Florida Water Management District (District), proposes to assess civil penalties against, and require a compliance plan from, Respondents, Balm Associates, Inc. (Balm) and Goodson Farms, Inc. (Goodson), on the grounds that from March 1999 through July 2001 they made water withdrawals from certain property in Hillsborough County, Florida, without a water use permit, and after a permit was obtained in August 2001, they continued to exceed the annual average daily withdrawals authorized under the permit through the month of November 2001, or just prior to the preparation and issuance of the Administrative Complaint and Order (Complaint).1 While not denying that excessive pumpages may have occurred, and that a permit was not obtained until August 2001, Balm points out that it is the owner-lessor of the property and not the consumptive user of the water, and contends that the District has no authority to enforce its rules against, and recover civil penalties from, the non-user of the water. In its request for a hearing, Goodson did not specifically dispute the allegation that it consumed water without a permit, or exceeded the withdrawal limits under the new permit, but contended instead that the limits were unrealistic and should be modified. At the final hearing, however, Goodson disputed the accuracy of the water consumption figures used in the Complaint. The District is the administrative agency charged with the responsibility to conserve, protect, manage, and control water resources within its boundaries and to administer and enforce Chapter 373, Florida Statutes. Balm is a corporation registered to do business in the State of Florida. Its mailing address is 2101 Huntington Avenue, Sarasota, Florida 34232. It owns approximately 220 acres of land in Section 28, Township 31 South, Range 21 East, in Hillsborough County, Florida, which is the site of the alleged wrongdoing. Goodson is a corporation registered to do business in the State of Florida. Its mailing address is Post Office Box 246, Balm, Florida 33503. Goodson is in the farming business and operates a total of 13 farms, including the farm at issue in this proceeding. Permit Requirements Under Rule 40D-2.041(1), Florida Administrative Code, a water use permit is required whenever total withdrawal capacity from any source or combined sources is greater than or equal to 1,000,000 gallons per day (gpd); annual average withdrawal from any source or combined sources is greater than or equal to 100,000 gpd; or withdrawal is from a well having an outside diameter of 6 inches or more at the surface. Rule 40D-2.351(1), Florida Administrative Code, provides that a permittee must notify the District within 30 days of the sale or conveyance of permitted water withdrawal facilities or the land on which the facilities are located. The same rule also provides that where a permit has been issued to a party whose ownership or legal control of the permitted water withdrawal facilities subsequently ends, the party who assumes control over the facilities may apply to transfer the permit to himself or herself up to the renewal date of the transferor's permit. Finally, Rule 40D-2.351(2), Florida Administrative Code, provides that until a permit is transferred or a new permit is obtained, the party subsequently controlling the permitted water withdrawal facilities will be in violation of District rules for making withdrawals without the required permit. History of Permits on the Property On September 29, 1989, the District issued Water Use Permit No. 207135.001 (the .001 permit) to James Brown (Brown) and B & T Growers Partnership (B & T) for water withdrawals from one well for agricultural purposes on Balm's property. The .001 permit authorized annual average withdrawals of 102,000 gpd of groundwater for agricultural irrigation. On August 29, 1990, the District adopted new rules applicable to District permits within the Eastern Tampa Bay Water Use Caution Area (ETBWUCA). The .001 permit was within the ETBWUCA, and Brown and B & T were provided with a Notice of Permit Modification and new Permit Conditions. The new conditions became effective November 15, 1990. New Condition No. 5 provided that By July 31, 1995, all permitted withdrawal points shall be equipped with totalizing flow meters or other measuring devices as approved in writing by the Director, Resource Regulation Department. Such devices shall have and maintain accuracy within five percent of the actual flow installed. On December 14, 1992, the District approved the transfer of the .001 permit from Brown and B & T to B. Kenda Produce. The Unpermitted Water Withdrawals On June 30, 1997, Goodson entered into a two-year agricultural lease with Balm to use a portion of the property, including acreage previously used by B. Kendra Produce. At the time the lease was entered into, neither Respondent applied to the District to have the .001 permit transferred from B. Kendra Produce. It can be reasonably inferred from the evidence that after the first lease expired, the parties continued to execute new lease agreements at least through the time of the hearing. The portion of the property which Goodson leased and farmed is referred to as the "Sweat Loop Farm" and consists of approximately 100 acres. There is one well with an outside diameter of 10 inches at the surface located on the Sweat Loop Farm. The well's total withdrawal capacity is approximately 1,500 gallons per minute (gpm), which is over 1,000,000 gpd. Thus, withdrawals from the well required a water use permit. As noted earlier, Goodson operates a total of 13 farms on approximately 2,500 acres of land. There are approximately 15 wells on all 13 farms, including the Sweat Loop Farm. Michael E. Hare, an irrigation supervisor who is responsible for the irrigation of all 13 of Goodson's farms, installed a total of approximately 8 meters on the farms, including the meter on the Sweat Loop Farm. A totalizing flow meter, which was made by MiCrometer, was installed at the Sweat Loop Farm in June 1997. Mr. Hare acknowledged that he was familiar with MiCrometer meters and would be aware if the MiCrometer flow meter on the Sweat Loop Farm was not functioning properly. Whenever metering devices on the various Goodson farms have malfunctioned in the past, Mr. Hare has taken the malfunctioning meter to a metering company to be fixed. Goodson began irrigating the Sweat Loop Farm in June 1997. Since that time, Goodson has been the sole water user of the well on the farm. In March 1999, Goodson began submitting to the District monthly pumpage reports for the groundwater withdrawals on the Sweat Loop Farm. Although some unmeasured withdrawals presumably occurred prior to March 1999, the Complaint does not identify these as being a violation. Mr. Hare and other supervisors are responsible for collecting the meter readings which go on the monthly pumpage reports and providing them to the District. The information on the reports includes the permit number; the last month's meter reading; the current month's meter reading; the total gallons of water pumped for the current month; the meter total; and the meter factor. To determine the average daily withdrawal on the Sweat Loop Farm, the District relied upon the calculations provided by Goodson as to the total gallons of water pumped for the month and divided this number by 30 days. From March 1999 through July 2001, these quantities were as follows: MONTH/YEAR AVERAGE DAILY PUMPAGE March 1999 April 1999 531,487 No data available May 1999 364,930 June 1999 0 July 1999 0 August 1999 57,410 September 1999 49,563 October 1999 222,667 November 1999 250,667 December 1999 755,003 January 2000 689,433 February 2000 695,073 March 2000 544,427 April 2000 305,153 May 2000 597,720 June 2000 0 July 2000 62,120 August 2000 86,370 September 2000 123,233 October 2000 602,020 November 2000 409,550 December 2000 145,823 January 2001 957,690 February 2001 890,213 March 2001 391,280 April 2001 467,640 May 2001 617,177 June 2001 0 July 2001 0 Under Rule 40D-2.041(1)(a)-(c), Florida Administrative Code, a water use permit was required for Goodson's withdrawals since the well's total withdrawal capacity is approximately 1,500 gpm, which is greater than 1,000,000 gpd; the annual average withdrawals exceeded 100,000 gpd; and the well has an outside diameter of 10 inches at the surface. The withdrawals on the Sweat Loop Farm were not authorized by the .001 permit since neither Goodson or Balm was a permittee under the permit. Even if Goodson could rely on the permit, which it cannot, pumpage data provided by Goodson reflects that the water withdrawals (except for nine months) were in excess of that authorized by the permit. On June 16, 2000, the District mailed a Notice of Non-Compliance for excessive water withdrawals to Goodson. The Notice indicated that if the pumpage values submitted by Goodson were incorrect, Goodson was to explain the error and provide corrected quantities. On June 26, 2000, the District received a written response to the Notice of Non-Compliance from the superintendent of the Sweat Loop Farm who indicated that the pumpage values were correct, and that the excess usage was due to a "serious drought condition" which had caused a "significant financial hardship on [the] farm." The response also indicated that Goodson would contact Mr. Haftel, owner of Balm, to request that he "revise the water use permit for spring crops." On November 22, 2000, the District mailed Goodson a Notice of Violation indicating that the quantities authorized by the .001 permit were still being exceeded and that the District might seek monetary penalties if Goodson failed to come into compliance within 30 days. Despite the foregoing Notice, Goodson continued to make withdrawals without a permit and in excess of the quantities formerly authorized under the .001 permit until August 2001 when a new permit was finally obtained. Issuance of a New Water Use Permit On January 2, 2001, the District received an application for a General Water Use Permit seeking to modify the .001 permit to increase the withdrawal quantities and to transfer the permit from B. Kendra Produce to Balm. "Seymour Haftel/ Balm Associates, Inc." was listed as the applicant, and "Donn Goodson" from " Goodson Farms" was listed as the contact or consultant. Mr. Haftel signed the application on behalf of Balm. Goodson assisted Balm in securing the permit for the Sweat Loop Farm because Goodson wanted more water for irrigation purposes. Section 2.1 of the Basis of Review for Water Use Permit Application, adopted and incorporated by reference by Rule 40D-2.091, Florida Administrative Code, provides that "[a]pplications for leased property, except property leased from the District, must be either a joint application in the name of the lessee and the property owner(s) or be only in the name of the property owner(s)." In a Request for Additional Information mailed to Balm on January 29, 2001, the District asked whether Goodson should be listed as co-applicant on the application. On April 27, 2001, Balm submitted a response which indicated that Goodson should not be listed as co-applicant. On August 6, 2001, the District issued Water Use Permit No. 200007135.002 (the .002 permit) to Seymour Haftel/Balm Associates, Inc. authorizing an increase in the annual average withdrawals to 224,300 gpd. The permit had an expiration date of September 29, 2009. The permit contained a number of special conditions, none of which were challenged by Balm. Unauthorized Withdrawals Under the .002 Permit Special Condition No. 2 of the .002 permit requires in part that the permittee: continue to maintain and operate the existing non-resettable, totalizing flow meter(s), or other flow measuring device(s) as approved by the Regulation Department Director, Resource Regulation, for District ID No(s), Permittee ID No(s)[,] G-1. Such device(s) shall maintain an accuracy within five percent of the actual flow as installed. Total withdrawal and meter readings from each metered withdrawal shall be recorded on a monthly basis and reported to the Permit Data Section, Records and Data Department, (using District forms) on or before the tenth day of the following month. In the event a permittee chooses not to use a totalizing flow meter, as required by Special Condition No. 2, the District will review information provided by the measuring device's manufacturer to determine if the measuring device would maintain a five percent accuracy as required by the Condition. The meters have to be monitored and calibrated periodically for accuracy. It is the permittee's responsibility to comply with the conditions of the permit, including Special Condition No. 2, which requires the submittal of accurate pumpage reports. Goodson submitted the meter readings on behalf of Balm beginning in September 2001, which covered the withdrawals for the month of August 2001. The District relied on the meter readings submitted by Goodson to determine the annual average daily pumpage calculation for the .002 permit. The calculation is a running 12-month average, whereby each month the annual average daily quantity is recalculated based on the previous 12-month pumpage. The running annual average daily pumpage and percentage of pumpage which exceeded the .002 permit from August 2001 through May 2002 are as follows: MONTH/YEAR ANNUAL AVERAGE DAILY PUMPAGE PERCENTAGE OVERPUMPED August 2001 378,462 69 percent September 2001 382,622 71 percent October 2001 376,687 68 percent November 2001 383,008 71 percent December 2001 379,212 69 percent January 2002 327,343 46 percent February 2002 321,530 43 percent March 2002 350,701 56 percent April 2002 356,013 59 percent May 2002 338,131 51 percent As the foregoing data reflects, the withdrawals from the Sweat Loop Farm were in excess of that authorized by the .002 permit from August 2001 through May 2002.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Southwest Florida Water Management District enter a final order determining that Respondents are guilty of the charges in its Administrative Complaint and Order except as concluded in paragraph 48 above and endnote 2 below; that Respondents be required to submit an acceptable written plan (Compliance Plan) to the District for its consideration and approval within fourteen days after entry of the final order; that the Compliance Plan describe how Respondents shall achieve full compliance with the .002 permit; that the Compliance Plan include reductions in withdrawals, water conservation measures, and development and utilization of alternative resources; that the Compliance Plan establish deadlines for implementation and completion of corrective actions; that full compliance be achieved within 120 days after entry of the final order; and that any failure of Respondents to comply with any provision of the Compliance Plan shall constitute a violation of the final order. DONE AND ENTERED this 30th day of July, 2002, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 30th day of July, 2002.

Florida Laws (5) 120.56120.569120.57373.119373.219
# 8
TOWN OF LONGBOAT KEY vs. 360 NORTH CORPORATION & DER, 81-001445 (1981)
Division of Administrative Hearings, Florida Number: 81-001445 Latest Update: Dec. 10, 1981

Findings Of Fact Respondent 360 North Corporation is seeking a permit to fill .05 acre of land dominated by submerged and/or transitional plant species as defined by the DER. The purpose of this fill is to enable Respondent 360 North Corporation to construct a residential building on its property. Respondent 360 North Corporation has proposed to create .15 acre of wetland habitat on its land in the vicinity of the proposed fill area to compensate for whatever detriment may ensue as a result of the .05 acre fill. Respondent 360 North Corporation has produced evidence, uncontroverted at the hearing, that it is the record owner of the real property for which the permit is being sought and of the area in which the proposed mitigation is to be conducted. Respondent 360 North Corporation established by testimony that there was no practical alternative by which the two proposed buildings could be located within the property without requiring significant modification to the buildings' structure or without the use of fill. Credible expert testimony characterized the vegetation within the .05 acre fill area as dominated by black mangroves (Avicennia gerrninans) and white mangroves (Laguncularia racemosa), all of which are less than 2.5 feet in height. The proposed fill activity is to be conducted in wetlands contiguous to Longboat Pass, Sarasota County, Florida, described by the DER as a Natural Class III Water Body. Respondent 360 North Corporation's witness testified that the placement of .05 acre of fill as proposed will have no significant effect upon the water quality in Longboat Pass. Respondent 360 North Corporation submitted a proposal for wetland habitat creation with its modified permit application. This proposal indicates the methodology by which the mangroves from the area to be filled will be transplanted to the mitigation area. It also indicates that the proposed fill will have a gradual slope and will be replanted with wetland herbaceous vegetation to prevent erosion. Testimony by 360 North Corporation's expert witness established that with proper planting and monitoring, the mitigation area would have an 80 percent chance of success barring any unforeseen acts of nature such as an extreme frost or hurricane. In addition, the expert testified that once established the mitigation area will create an environmentally superior habitat to that now existing in the area to be filled and would add to the stability of the shoreline at the north end of Longboat Key. The expert for Respondent 360 North Corporation testified that transplantation should be done in the spring of the year, preferably in March. In addition, he recommended that the trees be removed with a tree spade and replanted on four-foot centers. Additional mangrove plants and seedlings from nursery stock should be planted in the understory on two-foot centers. It was also recommended that a monitoring program be initiated to ensure survival of the trees in the mitigation area. The trees should be monitored at weekly intervals for the first six weeks, decreasing to biweekly intervals for the remaining first year, then at semiannual intervals for two additional years. The parties agreed to resolve this dispute if the requested permit was issued containing conditions requiring planting and restoration as outlined by Respondent 360 North Corporation's expert in his testimony at the hearing and in the proposal submitted to the DER with the modified permit application. Respondent 360 North Corporation agreed to revegetate with wetland vegetation the area disturbed by the use of scaffolding or other equipment employed during construction. Respondent 360 North Corporation additionally agreed to post a bond or other form of financial assurance in the amount of $10,000 with the DER to insure compliance with the conditions of the permit.

Florida Laws (4) 120.57403.021403.061403.088