Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
PINELLAS COUNTY CONSTRUCTION LICENSING BOARD vs RAUL FERNANDEZ, JR., 12-001925 (2012)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida May 24, 2012 Number: 12-001925 Latest Update: Jan. 09, 2025
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs GONZALO VEGA, 96-004148 (1996)
Division of Administrative Hearings, Florida Filed:Miami, Florida Sep. 03, 1996 Number: 96-004148 Latest Update: Jul. 15, 2004

The Issue Whether the Respondent committed the violations alleged in the Administrative Complaint, and, if so, the penalty that should be imposed.

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department of Business and Professional Regulation is the state agency responsible for investigating and prosecuting complaints involving violations of the requirements of Chapter 489, Part I, Florida Statutes. Sections 489.131(7)(e) and 455.225, Florida Statutes. Pursuant to Section 489.129(1), the Construction Industry Licensing Board ("Board") is the entity responsible for imposing discipline for any of the violations set out in that section. At all times material to this case, Mr. Vega was a certified general contractor operating under a license issued by the Construction Industry Licensing Board, numbered CG C046448. Mr. Vega has been a licensed general contractor in Florida since 1989, and since 1994, he has been the licensed qualifying agent for Group Construction South Florida, Inc. The residence of David M. Hudson, located at 19801 Southwest 84th Avenue, Miami, Dade County, Florida, was severely damaged in August, 1992, by Hurricane Andrew. In a letter dated October 13, 1992, Mr. Hudson, who holds a doctorate in biology and is the laboratory manager for the University of Miami Chemistry Department, proposed to Mr. Vega that he prepare plans for reconstructing the Hudson residence. On December 23, 1992, Mr. Hudson and Mr. Vega executed a contract for construction work to be performed on the Hudson residence. The parties contemplated that Mr. Vega would complete the work in accordance with the drawings and original blueprints prepared by Jose A. Sanchez, a structural engineer, at Mr. Vega's direction and based on preliminary plans approved by Mr. Hudson. Specifically, Mr. Hudson understood that the major elements of construction included in the December 23 contract were elevation of the house from one story to two stories, construction of a new living area on the second floor, and construction of a basement on the first floor to serve as a "bare bones storage area." The contract price specified in the December 23 contract was $146,338.33, with ten percent due upon acceptance of the proposal, ten percent due at completion of each of eight items of construction specified in the contract, and ten percent due upon completion of the project. The eight items of construction specified in the contract were "demolition work, rising work, tie beams, roof, doors & windows, plaster & tile, pool & fence, finish work and paint." On February 1, 1993, Metropolitan Dade County Building and Zoning Information Department issued Permit Number 93119957 to Mr. Vega for the Hudson project. The building permit was based on the original plans for the project submitted by Mr. Vega on January 19, 1993, together with some items that were added to the plans at the county's request. Mr. Vega began work on the project on February 1, 1993, the day the permit was issued. Mr. Vega hired Ruben Armas to act as foreman for the project, and his duties included hiring and supervising day laborers and procuring materials needed for construction. At the time, Mr. Armas was not licensed, registered, or certified by either Dade County or the State of Florida. Mr. Vega had an arrangement with Mr. Armas whereby he paid Mr. Armas periodic advances on a lump sum payment that Mr. Armas was to receive when the Hudson project was complete. Mr. Vega did not deduct FICA or withholding tax from the payments made to Mr. Armas under this arrangement. Mr. Vega dealt directly with Mr. and/or Mrs. Hudson regarding the project, although they would occasionally leave messages for him with Mr. Armas. Mr. Vega directly supervised Mr. Armas and gave him instructions on the work that was to be performed and the way it was to be done. Mr. Vega was routinely at the job site at least two or three times a day to inspect the work that had been done. Mr. Vega was present at the site during the entire time that cement was poured for footings or other structural elements. Mr. Vega arranged for various subcontractors to work on the project, including electricians, plumbers, air conditioning workers, roofers, carpenters, and drywall hangers. On April 14, 1993, a Department investigator conducted an inspection of the Hudson project during a "hurricane task force sweep." When she and the other members of the task force arrived on the job site, she observed Mr. Armas and two other men "inside working," but she did not observe them working or see the type of work they were doing. Mr. Armas walked out to meet the inspector and gave her a card that contained his name and phone numbers and the words "General construction & roof repair." Mr. Armas told the Department investigator that, when she arrived, he was "working on the footing for the elevation of the house." On April 21, 1993, Mr. Vega signed a Cease and Desist Agreement in which he acknowledged that the Department was investigating allegations that he had "engaged in the practice of aiding and abetting unlicensed contractor Ruben Armas." By signing the agreement, Mr. Vega agreed to cease "engaging in this activity," but he did not admit that the Department's allegations were true. The Department investigator was at the Hudson job site on April 14, 1993, for thirty minutes to an hour, during which time Mr. Vega did not appear at the site. This was the only time she was at the job site while work was being done. As the work progressed on the project, everything appeared to be going well, and Mr. Vega felt that he enjoyed a very good working relationship with Mr. and Mrs. Hudson. Mr. Hudson paid Mr. Vega a total of $116,400.00, or eighty percent, of the original contract price of $146,338.33, in ten percent increments as provided in the contract. By check dated December 23, 1992, Mr. Hudson paid the down payment of $14,633.38. By check dated February 5, 1993, Mr. Hudson paid $14,600.00 upon completion of the demolition work. By check dated March 5, 1993, Mr. Hudson paid $14,633.00 upon completion of raising the structure to two stories. By check dated March 24, 1993, Mr. Hudson paid $14,633.00 upon completion of the tie beams. By check dated April 19, 1997, Mr. Hudson paid $14,633.00 upon completion of the roof. By check dated May 13, 1993, Mr. Hudson paid $14,633.00 which should have been paid upon completion of the doors and windows but which he paid even though the installation of the doors and windows was not complete. By check dated June 23,1993, Mr. Hudson paid $12,000.00 of the $14,633.00 draw because, in his opinion, the project was not being completed on schedule. Finally, by check dated July 2, 1993, Mr. Hudson paid $17,000.00 to bring the payments up to the amount consistent with the contract schedule for completion of the pool and fence. In a letter to Mr. Vega dated June 7, 1993, Mr. Hudson stated that he wanted to make "a major change" in the plans. Specifically, Mr. Hudson wanted to eliminate the swimming pool, which he estimated would save $20,000.00 of the $146,633.00 contract price, and use the money saved "to completely finish the downstairs to be a nice guest area," to "install the better quality carpet we want, complete wooden fence, air conditioning in 1st floor, plumbing ~ electric in 1st floor, [and] indoor wooden shutters for all windows." Mr. Hudson went on to state that he wanted certain enumerated appliances, which would cost $4,108.00, and new furniture, which he estimated would cost $6,000.00, for a total of $10,108.00. According to Mr. Hudson's proposal, Mr. Vega should be able to "finish off the 1st floor the way we want it, install the nice carpet and tile, and do all the other jobs previously listed (fence, plumbing, etc., for 1st floor) for about $10,000.00." The basement area which Mr. Hudson wanted to finish as a "nice" living area consisted of approximately 2,000 square feet and had originally been designed as a storage area, with concrete floor and walls. Mr. Vega and Mr. Hudson discussed the proposal and the costs of the changes, but they did not reach an agreement on the cost of the additional work. 3/ Mr. Hudson asked Mr. Vega to leave the job site and cease work on the project on or about July 3, 1993, and Mr. Vega did not perform any work on the Hudson residence after this time. Mr. Hudson terminated Mr. Vega from the project solely because of the dispute with Mr. Vega over the cost of the changes he had requested in his June 7 letter. Mr. Hudson did not complain to Mr. Vega about the quality of the work that had been completed, and, although he thought that the project was getting behind schedule, Mr. Hudson issued a check dated July 2, 1993, which brought the total payments to eighty percent of the original contract price. When Mr. Vega stopped work on the project, the structure contained deviations from the original plans. 4/ Some of the deviations were items shown in the original blueprints which had not been incorporated into the structure; some were items that were not shown in the original blueprints but were incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson; some were deviations in the size of openings to accommodate doors and in the location and size of windows; most were minor deviations in the placement of electrical switches and receptacles or other similar deviations. The construction was, however, generally consistent with the original plans. 5/ There were three items that were significant deviations from the original plans. The most serious deviation concerned the changes made in the dimensions of the structural slab that formed the floor of the second floor balcony off the family room, kitchen, and dining room and the roof of the first floor terrace. The original plans included a second floor balcony with a width of six feet. The Hudsons asked Mr. Vega to increase the width of the balcony, and Mr. Vega called Mr. Sanchez, the structural engineer who had prepared the original plans, and asked if the width of the slab could be increased. Mr. Sanchez approved an extension from the original six feet to eight feet, eight inches, and he advised Mr. Vega of the additional reinforcement that would be needed to accommodate the increased width. On the basis of Mr. Sanchez's approval, Mr. Vega incorporated the additional reinforcement specified by Mr. Sanchez and poured the slab to the requested width of eight feet, eight inches. Even though Mr. Vega consulted a structural engineer, he did not submit revised blueprints to the building department and obtain approval for the structural change before doing the alteration. He was aware that the building code required approval before such a change could be incorporated into a structure and that his actions violated the code. 6/ The second significant deviation from the original plans was Mr. Vega's failure to construct the fireplace shown in the original plans. According to the plans, a fireplace was to be constructed in the living room, on the second floor. Although the roof was completed and the drywall installed, no accommodation had been made for the fireplace in either the wall or the roof. Mr. Vega intended to construct the fireplace and would have done so had he not been told to cease work on the project. The third significant deviation from the original plans concerns the windows installed in the structure. No window permits or product approvals were contained in the permit file for the Hudson project. In addition, some of the windows were not the size specified in the original plans, some were too deep, and some were placed lower than the thirty inch sill height specified in the original plans. Many of the items identified as "deviations" were actually items not shown on the original plans but incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson. Neither the requests for the additional items nor the costs of the items were reduced to writing by Mr. Hudson or Mr. Vega. At the time Mr. Hudson directed him to cease work on the project, Mr. Vega had contracts with subcontractors to provide the labor and materials specified in the original contract. He was prepared to complete the project in accordance with the original plans and for the original contract amount, with adjustments for the extras that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. He was also prepared to correct all deficiencies and code violations in the structure. After he was terminated from the project, Mr. Vega continued to negotiate with Mr. Hudson's attorney to arrive at an agreement for completion of the project that would be satisfactory to Mr. Hudson. In a proposal submitted to Mr. Hudson's attorney in the fall of 1993, Mr. Vega offered to complete the project in seven weeks in accordance with the original plans, as modified to incorporate the changes and upgrades Mr. Hudson had requested in the June 7 letter and the changes and upgrades that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. The total price for completion proposed by Mr. Vega was $56,750.00, which included the cost of the upgrades and extras and the $29,572.00 balance owing under the original contract. Mr. Hudson did not accept this proposal. Instead, he eventually hired a contractor named Robert Krieff, who did some work on the project. In February, 1994, Mr. Hudson took over the building permit himself and hired various subcontractors to work on the project. According to Mr. Hudson, in addition to the $116,400.00 he paid Mr. Vega, he has paid approximately $50,000.00 for work done after he terminated Mr. Vega, and he anticipates spending another $35,000.00 before a Certificate of Occupancy is issued. Mr. Hudson paid off a lien on his property for work done pursuant to his contract with Mr. Vega. A Claim of Lien in the amount of $4,712.00 was filed by Luis A. Roman on October 5, 1993, for drywall hung and finished at the Hudson residence under an arrangement with Mr. Vega. Summary of the evidence. The evidence presented by the Department is sufficient to establish that Mr. Vega willfully violated the building code with respect to the alteration of the width of the second floor balcony. Mr. Vega admitted that he knew he was violating the building code when he extended the width of the second floor balcony beyond the width specified in the original blueprints before submitting revised engineering plans to the county and receiving approval to make the alteration. This violation is one of procedure only, however, and there was no competent evidence presented to establish that Mr. Vega failed to include adequate reinforcement to compensate for the additional width prior to pouring the slab or that there were structural problems with the slab. 7/ The evidence presented by the Department is sufficient to establish that Mr. Vega violated the building code because the work completed by Mr. Vega on the Hudson project contained deviations from the original approved plans. 8/ On the other hand, the evidence presented by the Department is sufficient to establish that this violation is a minor one. The Department's experts testified that the construction done on the Hudson residence by Mr. Vega was generally consistent with the approved plans and that it was commonplace for contractors in Dade County to deviate from the approved plans and later submit revised plans for approval. The evidence presented by the Department is sufficient to establish that Mr. Vega did not file product approvals or obtain window permits prior to windows being installed in the Hudson project. The evidence presented by the Department is not sufficient, however, to establish that these omissions on Mr. Vega's part constituted a violation of section 204.2 of the South Florida Building Code, as alleged in the Administrative Complaint. Although there was some testimony that the building code requires that product approvals be filed and window permits obtained before windows are installed, the applicable code and section were not identified by the Department's witnesses or otherwise made a part of the record. Thus, there is no evidence of the precise obligations imposed on Mr. Vega by the code that was applicable at the time of the Hudson project. As a result, it is not possible to determine whether Mr. Vega fulfilled his obligations under the code. The evidence presented by the Department is not sufficient to establish that Mr. Vega assisted Mr. Armas in engaging in the unregistered or uncertified practice of contracting. There is no evidence in the record that Mr. Armas performed any work on the Hudson project that could be performed only by a licensed contractor. 9/ Notwithstanding the opinions stated by the Department's experts, the evidence presented by the Department is not sufficient to establish that Mr. Vega is guilty of incompetence or misconduct in the practice of contracting as a result of the work done on the Hudson project. The evidence presented by the Department is sufficient to establish that Mr. Hudson suffered financial loss in the amount of $4,712.00, which is the amount Mr. Hudson paid to clear the lien placed on his property by Luis A. Roman. Although this loss is attributable to Mr. Vega's failure to pay Mr. Roman for hanging and finishing drywall in the Hudson residence, the evidence presented by the Department is not sufficient to establish that Mr. Hudson suffered financial loss as a result of the violation with which Mr. Vega was charged and of which he was proven guilty.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board issue a Final Order dismissing Counts I and III of its Administrative Complaint, finding that Gonzalo Vega is guilty of violating section 489.129(1)(d), Florida Statutes (1993), and imposing an administrative fine in the amount of $1,000.00. DONE AND ENTERED this 3rd day of July, 1997, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of July, 1997.

Florida Laws (8) 120.569120.5717.001455.225489.105489.113489.129489.131 Florida Administrative Code (1) 61G4-17.003
# 3
# 4
# 6
# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs WINSTON BROWN, 07-003335PL (2007)
Division of Administrative Hearings, Florida Filed:Port Charlotte, Florida Jul. 18, 2007 Number: 07-003335PL Latest Update: Nov. 12, 2019

The Issue The issues in this case are whether Respondent violated Subsections 489.129(1)(g)2., 489.129(1)(j), and 489.129(1)(m), Florida Statutes (2004),1 and, if so, what discipline should be imposed.

Findings Of Fact Mr. Brown holds a current, active Florida State Certified General Contractor License number CG C062829. He is the owner and qualifying agent for Churchill’s Construction Co., Inc. (Churchill’s). Sometime in 2003, Churchill’s entered into two contracts with Walcott Allen to construct two homes in Charlotte County, Florida. Mr. Allen was a friend of Mr. Brown. Mr. Allen had had a contractor’s license, but the license had been revoked by the Department. Mr. Brown decided to make Mr. Allen vice president of operations for Churchill’s. The purpose was two-fold. First, Mr. Brown did not think that he would be able to be present at the construction sites of Mr. Allen's homes very often, but Mr. Allen would be at the construction most of the time. By making Mr. Allen a vice president of the company, Mr. Brown felt that the building inspectors would be satisfied that Churchill’s had a presence at the construction sites. Additionally, Mr. Brown was hopeful that Mr. Allen would be able to generate business through some of his business associates. Sometime in 2003 or 2004, Mr. Brown and Mr. Allen went to the real estate office of Debbye Fitzpatrick concerning the purchase of some lots. In 2004, Hurricane Charlie struck the Port Charlotte area and did considerable damage, including damage to the residence of John and Debbye Fitzpatrick. Debbye Fitzpatrick knew that Mr. Allen had done some construction work in the past and approached him about repairing the damage to her home. Mr. Allen advised Mr. Brown that the Fitzpatricks were interested in Churchill’s repairing the damage to their house. Sometime before December 15, 2004, Mr. Brown and Mr. Allen went to the Fitzpatricks' home to look at the damage. Neither Mr. Brown nor Mr. Allen advised the Fitzpatricks that Mr. Allen could not enter into a contract on behalf of Churchill’s. Mr. Allen gave the Fitzpatricks a business card indicating that he was the vice president of operations for Churchill’s. On December 15, 2004, the Fitzpatricks entered into a contract with Churchill’s to make the repairs to the Fitzpatricks' home. The contract was not written on the form usually used by Churchill’s. Mr. Allen signed the contract on behalf of Churchill’s. The contractor license number listed on the contract was Mr. Brown’s. The total contract amount was $65,728. Based on the contract, Churchill’s was to remove existing drywall ceilings and insulation and replace with new insulation and sheetrock, remove existing drywall and insulation for the walls and replace with new sheetrock and insulation, lay floor tiles, paint the ceiling and walls, replace all the electrical fixtures, and power wash and paint the exterior of the house. Churchill’s applied for a building permit for the repairs to the Fitzpatricks’ home. The permit application was signed “Winston Brown” and was notarized. Mr. Brown contends that he did not sign the application and that the signature is a forgery by Mr. Allen. To a layperson, the signature on the permit application for the Fitzpatrick house does differ significantly from the signature on other documents submitted by Mr. Brown, which documents he testified bore his signature. Mr. Allen commenced work on the Fitzpatrick house. On February 17, 2005, Debbye Fitzpatrick wrote a check for $7,500 made payable to Wally Allen as the initial payment for the construction work. Mr. Allen had asked Debbye Fitzpatrick to make the check payable to him rather than to Churchill’s. Debbye Fitzpatrick did not think it was out of the ordinary for the check to be made out to Mr. Allen, and she complied with his request. On March 29, 2005, Debbye Fitzpatrick wrote another check to Mr. Allen for $10,000 as a draw on the contract amount. On June 23, 2005, she wrote another check to Mr. Allen for $11,601.77. The work on the project did not go well according to the Fitzpatricks. Some of the tiles that were laid were cracked, and some of the tiles gave out a hollow sound when tapped with a wooden implement. Some of the tiles were not grouted. Some of the grout in the tile work was not sealed. Insulation was not replaced in some of the ceiling areas. Patches to the sheetrock on the walls and ceiling were visible. The texturing of the paint was not consistent, with some areas having too much texture and some areas not having enough. The workers were careless with their painting and got paint on the carpet, furniture, floors near baseboards, windows, window frames, soffits, and front porch. The workers also damaged some of the furniture and kitchen appliances during the performance of their work. The front entry door was not installed properly. The garage door was not primed and the paint peeled. The vanity top in the master bedroom was not installed properly and had to be redone by another contractor. In July, Mr. Allen and his workers stopped coming to the job site. No notice was given to the Fitzpatricks that work was going to be stopped. No one from Churchill’s ever came back to work on the project, and the work on the project was not complete and was unsatisfactory. The Fitzpatricks had to pay an electrician $1,500.00 to do work that was supposed to be included in the contract with Churchill’s. Although there was unrebutted testimony that the Fitzpatricks had to pay other contractors to repair the damage done by Churchill’s, there was no evidence presented to quantify the amounts paid and the damage sustained other than a payment to the electrician. Additionally, some of the work not completed by Churhill’s had not been done because the Fitzpatricks lack the funds to complete the work. Again, no effort was made to quantify the amount of money necessary to complete the work. Mr. Brown claims that he did not know anything about the project and that Mr. Allen acted without authority to bind Churchill’s to a contract for the project. Mr. Brown’s testimony is not credible. Mr. Brown made Mr. Allen a vice president of the company and went with Mr. Allen to the Fitzpatricks’ home to look at the work that was needed. According to Mrs. Fitzpatrick, “Mr. Allen did most of the talking as to what was to be done and what the procedure was to be and he [Mr. Brown] didn’t speak very much, but he did nod and go along with what the plan was.” One of the reasons that Mr. Brown made Mr. Allen a vice president of the company was to garner additional business. If Mr. Brown had not wanted Mr. Allen to act on behalf of Churchill’s, Mr. Brown should not have made Mr. Allen a vice president of the company. Mr. Brown knew that any work that Mr. Allen was able to secure would have to be done using Mr. Brown’s license because Mr. Allen’s license had been revoked.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding that Respondent violated Subsections 489.129(1)(j) and 489.129(1)(m), Florida Statutes, and did not violate Subsection 489.129(1)(g)2., Florida Statutes; placing Respondent on probation for two years; imposing an administrative fine of $1,000.00 for the violation of Subsection 489.129(1)(j), Florida Statutes; imposing an administrative fine of $1,000.00 for the violation of Subsection 489.129(1)(m), Florida Statutes; and requiring Respondent to make restitution to the Fitzpatricks in the amount of $1,500.00. DONE AND ENTERED this 14th day of March, 2008, in Tallahassee, Leon County, Florida. S SUSAN B. HARRELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of March, 2008.

Florida Laws (5) 120.569120.57120.68489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 9
PINELLAS COUNTY CONSTRUCTION LICENSING BOARD vs ROY M. TURNER, 01-000598PL (2001)
Division of Administrative Hearings, Florida Filed:Largo, Florida Feb. 12, 2001 Number: 01-000598PL Latest Update: Jan. 09, 2025
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer