Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT O. BARTHOLOMEW, 83-000413 (1983)
Division of Administrative Hearings, Florida Number: 83-000413 Latest Update: Sep. 27, 1983

Findings Of Fact Robert O. Bartholomew is registered as a general contractor and as a residential contractor holding licenses No. RG0025081 and No. RR0035491. Be was so registered at all times here relevant. Neither Carl Robinson nor his company, Atlas Associates, Inc., is registered as a building contractor in Pasco County. Robinson, acting for Atlas Associates, Inc., entered into a contract with Betty Valdez to construct an addition to her mobile home in Lutz, Pasco County, Florida, and requested Respondent to pull the building permit as neither Robinson nor Atlas Associates, Inc., is registered in Pasco County. Respondent pulled the permit, as contractor, for the work to be done on Valdez' home although he was not a party to the contract. Both Robinson and Respondent testified they worked under a verbal arrangement as partners in several projects; however, Respondent has no ownership interest in Atlas Associates, Inc. The work was started by Robinson's foreman, Hubbard, but after a short period on the job Hubbard was fired and Respondent took over the construction. Disputes arose between Ms. Valdez and the contractor and the work was not completed by Atlas Associates, Inc. Part of the contract provided for a roof over the existing roof on the trailer. Pasco County requires this work, like electrical and plumbing, to be done by one licensed in that field. No licensed roofer was used and no permit to have such work done by a licensed roofer was pulled. Following unsatisfactory termination of the contract between Atlas and Valdez, liens were filed by Atlas Associates, Inc., and Respondent against Valdez' property and countersuits were instituted by Valdez before both sides agreed to drop their claims. Respondent's contention that Ms. Valdez' agreement to drop all claims in settlement of the dispute somehow precludes this action, is without merit. In a separate proceeding Robinson was disciplined by the Board for his violations of the Construction Industry Licensing Law in contracting with Ms. Valdez when not properly licensed to do so.

Florida Laws (1) 489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GILBERT SYKES, 83-003073 (1983)
Division of Administrative Hearings, Florida Number: 83-003073 Latest Update: Apr. 24, 1984

The Issue The issues in this case are those promoted by the Administrative Complaint by Department of Professional Regulation against Respondent accusing him of violations of Chapter 489, Florida Statutes, pertaining to work done for Mary Scott. This circumstance is more particularly discussed in findings of fact and conclusions of law.

Findings Of Fact Respondent is a registered building contractor and a registered roofing contractor, having been issued license No. RB 0009302 and RC 0032535. Said licenses were in effect as of the date of the hearing in this matter. Both of Respondent's licenses had become delinquent in July 1981 and were not renewed until June 1983. On or about November 11, 1982, Mary Scott entered into a contract with Henry Hodge, doing business as "Direct Interiors," pursuant to which Hodge was to construct an addition to the Scott residence located at 1439 West 2nd Street, Jacksonville, Florida. The contract price was $6,848.00. On November 24, 1982, Respondent used his registered building contractor's license to help obtain building permit No. 10047 from the City of Jacksonville, Building and Zoning Department, for the construction of the addition to the Scott residence under her contract with Henry Hodge. At no time material hereto was Henry Hodge or "Direct Interiors" licensed to engage in the business of contracting in the State of Florida. At no time did the Respondent qualify "Direct Interiors" to engage in the business of contracting. Respondent helped obtain the permit at Hodge's request, as a favor to Hodge. Respondent has never been partners or otherwise done business with Hodge. Respondent became casually acquainted with Hodge when they both were working on the same construction site, unrelated to this case. Respondent helped Hodge obtain the permit as follows: Hodge approached Respondent and asked Respondent to obtain the permit for the Scott jot. Respondent told Hodge to bring Respondent a building permit application form. Hodge did this, and Respondent then signed the application while it was still blank. Hodge thereafter filled in the details, took the application in to the building department, and received the building permit. Respondent had no knowledge of the size or other details of the work on the Scott job, other that it was a room addition. At not time while Henry Hodge was working on the Scott job did Respondent visit the job site or in any way supervise the work. Henry Hodge, as "Direct Interiors," completed construction of the addition and received $5,924.00 in payment from Mary Scott. The contract between Hodge and Scott called for building a room addition and for reroofing certain portions of the roof of the existing structure. After Hodge completed the job, portions of the reroofed area which had not leaked before Hodge reroofed it, began to leak. Mary Scott was not able to obtain satisfactory performance from Hodge concerning this problem. She then contacted the building department and found that the building permit was obtained upon Respondent's license. Until that point, she was unaware of Respondent. Subsequently, Respondent corrected the work done by Hodge.

Recommendation Upon consideration of the facts found, conclusions of law and matters in mitigation and aggravation, it is RECOMMENDED that a final order be entered imposing a $500.00 fine for the violations found. DONE AND ENTERED this 5th day of March 1984 in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of March 1984. COPIES FURNISHED: Harold M. Braxton, Esquire 45 Southwest 36th Court Miami, Florida 33135 Mr. Gilbert Sykes 4862 Soutel Drive Jacksonville, Florida 32208 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (4) 120.57489.115489.119489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PETER W. DETHLEFSEN, 88-000577 (1988)
Division of Administrative Hearings, Florida Number: 88-000577 Latest Update: May 20, 1988

Findings Of Fact Respondent has been a certified building contractor in the State of Florida. He held license number CB C033166. The license was first issued on March 7, 1985. As of March 31, 1988, Respondent had not renewed the license, which expired on June 30, 1987. Respondent is not and has never been certified as a contractor with the Orange County Building Department. On June 18, 1987, Respondent and Richard G. Rapagnani entered into a contract for Respondent to add a screen porch onto an existing slab at 8763 Belter Drive, Orlando, Orange County, Florida, which was Mr. Rapagnani's residence. The total contract price was $4013. The contract price was payable $1500 down, $1500 due upon completion of framing, and the balance due in two payments with the final payment due upon completion. Prior to obtaining the contract, Respondent assured Mr. Rapagnani that Respondent would take care of obtaining the necessary building permits for the job and that the job would be of high quality. Respondent began the work without obtaining the necessary building permits. He never obtained any permit or any inspection for the job. In performing the work, Respondent removed part of the existing roof. He placed a plastic sheet over the open area, but failed to affix the plastic so as to prevent rain from penetrating the roof, ceiling, and walls. After installing some posts and rafters, Respondent left the job. When asked numerous times by Mr. Rapagnani to return, Respondent offered various excuses. Respondent claimed that he needed more money and suggested that Mr. Rapagnani purchase some of the necessary materials directly from the suppliers. On July 10, 1987, Mr. Rapagnani paid Respondent $1000. Respondent in turn promised to work on July 17 and 18 with materials that he had recently purchased. However, when Respondent failed to show on July 17, Mr. Rapagnani called him and learned that he had no money left and no materials. Mr. Rapagnani then purchased shingles and skylights, and Respondent returned on July 18 to install them. He never completed the installation of these items, and the shingles and skylights that he did install leaked badly. Over a period of two months, Mr. Rapagnani called Respondent at least 50 to 60 times to request him to finish the job. Mr. Rapagnani paid Respondent a total of $2700 and paid an additional $789 for shingles, skylights, and other materials called for in the contract. In mid-August, Mr. Rapagnani fired Respondent. After hiring another contractor about six months later, Mr. Rapagnani was forced to spend approximately $3000 more to complete the work that Respondent had contracted to do. When the new contractor viewed Respondent's roofing job, the contractor determined that the roof was about to fall down due to faulty workmanship. Respondent had failed to secure the roof to the house. It took two to two and one-half days to correct the problem. While on the job, Respondent caused damage to the house and other property of Mr. Rapagnani. He damaged a window screen adjacent to the work area. He punched a hole through the drywall into the living room. His work on the roof led to water leakage into the bedroom. He dropped shingles onto Mr. Rapagnani's boat, thereby damaging it. He never fixed any of this damage. On October 27, 1987, the Orange County Building Department issued a Notice of Code Violation to Mr. Rapagnani listing 21 violations of the applicable code provisions. All of these violations, including the failure to obtain the necessary permits, were attributable to Respondent. Several of the violations pertained to work affecting the structural integrity of the roof and screen porch.

Recommendation In view of the foregoing, it is hereby RECOMMENDED that a Final Order be entered finding Respondent guilty of deliberately proceeding without a timely permit, deliberately failing to obtain a required inspection, and engaging in the contracting business with an expired license. It is recommended that the Final Order impose an administrative fine of $2500. ENTERED this 20th day of May, 1988, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of May, 1988. COPIES FURNISHED: David E. Bryant, Esquire Bryant, Reeves & Deer 220 East Madison Street Suite 530 Tampa, Florida 33602 Peter Dethlefsen 2190 Glenwood Drive Winter Park, Florida 32792 Peter Dethlefsen 628 Lander Road Winter Park, Florida 32792 Fred Seely Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201 William O'Neil General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.115489.127489.129
# 6
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs LEROY JONES, JR., 05-001496PL (2005)
Division of Administrative Hearings, Florida Filed:Miami, Florida Apr. 22, 2005 Number: 05-001496PL Latest Update: Dec. 13, 2005

The Issue Whether Respondent, a licensed general contractor, committed the violations alleged in the three-count Administrative Complaint filed by Petitioner and the penalties, if any, that should be imposed.

Findings Of Fact Respondent is the agency of the State of Florida with the responsibility to regulate building contracting. At all times relevant to this proceeding, Respondent has been licensed as a certified general contractor, having been issued license number CG C058340 in 1996. At all times relevant to this proceeding, Ms. McKinney owned and resided in a house (the House) in Opa Locka, Florida. Ms. McKinney’s mother, Mattie P. Mathis, also lived in the House. In 2001, Ms. McKinney solicited bids for an addition she wanted to put on the House. Ms. McKinney and her mother, Ms. Mathis, planned to pay for the addition with life insurance proceeds on the life of Ms. Mathis’s deceased daughter (Ms. McKinney’s sister). On the recommendation of a colleague at her work, Ms. McKinney asked Willie Muse, Jr., to bid on the work. Based on the bids she received, Ms. McKinney hired Mr. Muse to construct the addition to the House. Ms. McKinney told Mr. Muse that she wanted all work to comply with all applicable permitting requirements and laws. Mr. Muse represented to Ms. McKinney that he would get the necessary building permits and that the work would comply with all applicable laws. On July 18, 2001, Ms. McKinney and Ms. Mathis entered into a written contract with Mr. Muse whereby Mr. Muse agreed to construct the addition for the sum of $45,000.00. Mr. Muse has never been licensed as a general contractor in Florida. Ms. McKinney thought Mr. Muse was a licensed contractor and would not have entered into a contract with him if she had known that he was not licensed. Pursuant to the contract, Ms. McKinney and Ms. Mathis paid Mr. Muse the following amounts on the following dates: $6,000.00 on July 20, 2001; $7,500.00 on October 10, 2001; and $13,500.00 on November 2, 2001; for a total of $27,000.00. On or about August 21, 2001, Mr. Muse brought to Ms. McKinney a building permit application form for her to sign. The application form had been filled out before Mr. Muse presented it to Ms. McKinney. Respondent was not present when Mr. Muse presented the form to Ms. McKinney. Respondent’s name, signature, and contractor’s license number appeared on the application form when Mr. Muse presented the form to Ms. McKinney. Ms. McKinney signed the form on August 21, 2001. Ms. McKinney saw Respondent’s name for the first time when she read the building permit application form. Prior to that time, Ms. McKinney and Ms. Mathis had never known or heard of Respondent. At all times relevant to this proceeding, Respondent knew that Mr. Muse was not a licensed contractor. Mr. Muse submitted the building permit application form to the Miami-Dade County Building Department (Building Department), which issued a building permit for the work on the House on October 5, 2001. Mr. Muse commenced working on the House in October 2001, but he never finished. After he received the payment in November 2001, Mr. Muse stopped working on the House for an extended period of time. During that time, Ms. McKinney attempted on several occasions to persuade Mr. Muse to resume work on the House. Prior to stopping work on the House, Mr. Muse removed a portion of the roof of the existing structure, which exposed the interior of the House to the elements. That exposure resulted in extensive damages to the House, including the collapse of the kitchen ceiling from water intrusion. By letter dated April 15, 2002, the Building Department advised Ms. McKinney that her building permit would expire in approximately 30 days. That letter prompted Ms. McKinney to contact the Building Department, where she was told that Respondent was her contractor, not Mr. Muse. Ms. McKinney secured information (from the face of the building permit) that enabled her to contact Respondent’s mother.3 That contact resulted in two meetings between Ms. McKinney and Respondent towards the end of April 2002. During the first meeting, Ms. McKinney related to Respondent the history of the project, including the amounts that had been paid to Mr. Muse. She also showed him the work that had been done and the damages that had occurred. During the second meeting, Mr. Muse was in attendance. Ms. McKinney, Ms. Mathis, and Respondent reached a verbal understanding that was not reduced to writing. They agreed that Respondent would finish the work on the House for the unpaid balance of the contract price $45,000.00 less $27,000.00 paid to Mr. Muse, which equals $18,000.00.4 The parties agreed that Respondent would pay for labor and that Ms. McKinney and Ms. Mathis would pay material suppliers directly and receive credit toward the contract price for such payments. The parties contemplated that Mr. Muse would perform most of the labor because of the monies he had already received. On the basis of the verbal contract, Respondent resumed the work on the House. On June 12, 2002, Respondent presented a draw request for $3,500.00 for electrical, plumbing, and roofing work that had been performed. Ms. Mathis wrote Respondent a check in the amount of $3,500.00 for that work. Ms. McKinney was opposed to paying Respondent the sum of $3,500.00 because she believed he had not completed the work for which he was billing. Ms. Mathis paid that sum despite Ms. McKinney’s opposition. At some undetermined time following June 12, 2002, Ms. McKinney told Respondent that she did not want Mr. Muse working on the House. Respondent then asked to be paid in advance for work to be done on the House because he would have to pay his laborers. Ms. McKinney and Ms. Mathis would not agree to payment in advance. In July 2002, the project was not complete and Respondent’s progress on the work on the House became unsatisfactory to Ms. McKinney. On October 14, 2002, Ms. McKinney filed a complaint against Respondent with Petitioner, claiming, among other things, that Respondent had abandoned the project. Her complaint alleged that work ended on the project in July 2002. At some undetermined time between June and October 2002, Ms. McKinney filed a criminal complaint against Mr. Muse, which resulted in criminal misdemeanor charges being filed against him in Miami-Dade County Court. After she filed the criminal complaint against Mr. Muse, Ms. McKinney told Respondent that she wanted to wait to proceed with the project until she knew what was going to happen with her criminal complaint. In the criminal proceeding, the Court ordered Mr. Muse on April 11, 2003, to pay restitution to Ms. McKinney in the amount of $16,008.04, payable in monthly installments of $300.00. On March 2, 2004, the Court reduced the amount of restitution to $4,000.00, payable in monthly installments of $50.00 beginning April 1, 2004. As of the date of the final hearing in this proceeding, Mr. Muse had paid Ms. McKinney restitution in the total amount of $750.00. As part of the criminal proceeding, Respondent was asked to give his opinion as to the value of the work completed by Mr. Muse and his estimated cost of completing the work. Respondent valued the work completed by Mr. Muse at $14,073.75 (labor and materials). Respondent estimated that it would cost $22,200.00 to complete the project. Both estimates were dated March 23, 2003. On October 1, 2003, Theodore R. Gay, Assistant General Counsel for Petitioner wrote Ms. McKinney the following letter pertaining to the complaint she had filed in October 2002: The Legal Department has evaluated your complaint against the above named contractor [Respondent]. After reviewing the evidence gathered during the investigation of the referenced matter, we have determined that in accordance with the rules and policies of the Construction Industry Licensing Board, this case is appropriately closed with the issuance of a Letter of Caution to the contractor. Because this case has been dismissed without a finding of probable cause, the file will remain confidential and exempt from the public records. On January 6, 2004, Ms. McKinney wrote Mr. Gay a letter that provided, in part, as follows: This letter is a request to re-open the case [against Respondent] because as prior conversation (sic) when I spoke to you in late August 2003 or early September 2003, I informed you that Mr. Jones told me that he would help me as much as possible to complete the construction on my property. Since your letter that stated you didn’t find any error on Mr. Jones’ behalf, I have not heard or seen him since October 2003, nor has any work been performed on my property. . . . Respondent came back to the House after October 2003 and talked to Ms. McKinney about the work. Ms. McKinney told him that she would pay up to a total of $45,000.00 for the work, but that she would not pay above that figure. Because of the estimate Respondent provided in the criminal proceeding dated March 23, 2003, Ms. McKinney believed that Respondent wanted $22,0000.00 to complete the work. However, Respondent never told her that he would not complete the work for a sum equal to $45,000.00 less the sums that had already been paid. Ms. McKinney would not pay Respondent for work until after the work was completed. After Mr. Gay’s letter dismissing the complaint that Ms. McKinney had filed, Respondent did no further work on the House, but he did have further conversations about the project. Ms. McKinney and Respondent could not agree on payment terms for Respondent to complete the project. Ms. McKinney testified that she did not fire Respondent. However, it is clear that she would not let Mr. Muse do further work on her house and she would not pay Respondent until after the work had been done. Ms. McKinney changed the terms of her verbal contract with Respondent by prohibiting Mr. Muse from working on the project. In November 2003, Ms. McKinney and Ms. Mathis had an argument over the money that had been spent on the house. Ms. McKinney talked to Respondent about his helping her obtain a mortgage on the house to pay for the balance of the work on the House. Ms. McKinney told Respondent that she did not want Respondent to ask her mother for any more money. Ms. McKinney told Respondent that she would use him as the contractor to complete the work if she obtained the financing. Ms. McKinney was unable to get the financing due to the condition of the House. The permits obtained by Respondent are still valid. Ms. McKinney has hired various workers on her own in an effort to complete the work on the House. As of the final hearing, the work on the House had not been completed. As of May 19, 2005, Petitioner’s costs of investigation and prosecution of this case, excluding costs associated with attorney time, totaled $920.29.

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order that adopts the Findings of Facts and Conclusions of Law set forth in this Recommended Order. It is further recommended that the Final Order: Find Respondent guilty of the violation alleged in Count I of the Administrative Complaint and impose against him an administrative fine in the amount of $2,500.00; Find Respondent guilty of the violation alleged in Count II of the Administrative Complaint, but impose no additional administrative fine for that violation; Find Respondent not guilty of the violation alleged in Count III of the Administrative Complaint; Order that Respondent be jointly and severally liable to Ms. McKinney and Ms. Mathis with Mr. Muse for restitution in the amount of $4,000.00, minus $750.00 paid by Mr. Muse; and Order Respondent to pay costs of investigation and prosecution of this matter in the amount of $920.29. DONE AND ENTERED this 10th day of August, 2005, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 2005.

Florida Laws (9) 120.569120.5717.00117.002455.227489.1195489.125489.127489.129
# 7
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs EARL HENRY BENJAMIN, 00-002940PL (2000)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Jul. 18, 2000 Number: 00-002940PL Latest Update: Mar. 12, 2001

The Issue The issue in this case is whether Respondent violated Sections 489.119(2), 489.124(2), 489.129(1)(n) and (p), and 489.1425(1), Florida Statutes (1999) (hereinafter, "Florida Statutes"), respectively, by: engaging in contracting as a business organization without applying for a certificate of authority through a qualifying agent and under a fictitious name; failing to notify Petitioner of the mailing address and telephone number of the certificate holder or registrant; committing incompetency or misconduct in the practice of contracting; proceeding on a job without obtaining applicable building permits and inspections; and failing to provide a written statement explaining the consumer's rights under the Construction Industries Recovery Fund (the "Fund").

Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a contractor with license number CC C018992. At all relevant times, Respondent was registered or certified with Petitioner as the qualifying agent for Earl Benjamin and Company, Inc. ("EBCO"). As the qualifying agent, Respondent was responsible for all of EBCO's contracting activities in accordance with Section 489.1195. Respondent failed to obtain a certificate of authority from Petitioner. On April 4, 1998, EBCO entered into a contract with Mr. Joseph Chapman ("Chapman") to repair a leak in the roof of Chapman's residence at 1880 Jessica Road, Clearwater, Florida. On the advice of Mr. Dale Edwards, a representative of EBCO, Chapman entered into a second contract with EBCO to repair the entire roof for an additional cost. None of the contracts or other documentation provided by EBCO to Chapman contained a notice explaining the consumer's rights under the Fund. The contract prices for the first and second contracts were $4,500 and $7,500, respectively. After completing the work, Respondent sent another bill to Chapman for $1,750 for additional materials and repairs. Chapman paid, and Respondent accepted, $13,210 as payment in full of all amounts owed to Respondent. The checks signed by Chapman were made payable to "Earl Benjamin and Company and/or EBCO." After EBCO completed the work on the Chapman residence, the roof leaked in four places and continued to leak as of the date of hearing. Chapman contacted Respondent and other EBCO representatives repeatedly in attempt to stop the leaks. EBCO has been unable to stop the leaks in Chapman's home. The Pinellas County Building Department (the "Building Department") never performed a final inspection approving the work performed by Respondent. The Building Department issued building permit number 175919 to Respondent on April 23, 1998. On May 26, 1998, Chapman indicated to the Building Department that the roof leaked, and an inspector for the Building Department inspected the roof on the same date. The inspector found that the birdcage was not reassembled, some flashing was too short, and other eaves and rates were not constructed properly. The inspector issued a red tag for the violations. On June 16, 1998, the inspector inspected the roof again and issued a second red tag for some violations that remained uncorrected. On November 16, 1998, the inspector inspected the roof again and issued another red tag because the roof still leaked. On January 14, 1999, the inspector met with Chapman and representatives for EBCO to address the continuing problems with the roof. The inspector instructed Respondent to update his address and licensing information. On January 26, 1999, the inspector inspected the roof for the last time. The roof still leaked. On May 9, 1998, EBCO entered into a contract with Jack and Dawn Wilcox ("Wilcox") to repair the roof and install roof vents in the Wilcox residence at 247 144th Avenue, Madeira Beach, Florida. The contract price for the Wilcox job was $1,800. The Wilcoxes paid, and Respondent accepted, $1,800 as payment in full of all amounts owed to Respondent. The checks signed by the Wilcox's were made payable to "EBCO" or "EBCO Roofing." After EBCO completed the work on the Wilcox residence, the roof leaked around the vents installed by Respondent. The work performed by Respondent suffered from incompetent workmanship including ragged and non-uniform holes cut into the roof for the vents. Mr. Wilcox attempted to contact Respondent and other EBCO representatives repeatedly in an attempt to correct the leaks in the roof. No one from EBCO returned the messages from Mr. Wilcox. Mr. Wilcox attempted to physically locate Respondent at Respondent's business address, but Respondent's address was incorrect. The Wilcoxes incurred additional expenses of $1,500 to correct problems caused by Respondent. On October 24, 1998, Mr. Wilcox entered into a contract with Kurt Dombrowski Roofing Contractor ("Dombrowski") to repair the leaks in the roof and to re-install the vents in the roof. Dombrowski correctly performed the work, and Wilcox paid Dombrowski $1,500. The Wilcoxes have no further problems with the roof. Respondent never obtained a building permit for the work performed on the Wilcox roof. The Wilcox home was located within the jurisdiction of the City of Madeira Beach (the "City"). The City no longer has a building department. The Pinellas County Building Department assumed the responsibilities of the City. Respondent never obtained a building permit for the Wilcox job.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating Sections 489.119(2), 489.124(2), 489.129(1)(n) and (p), and 489.1425(1), imposing administrative fines in the aggregate amount of $3,200, requiring Respondent to pay restitution to Chapman and Wilcox in the respective amounts of $13,210 and $1,800, and requiring Respondent to pay costs of investigation and prosecution in the amount of $690.40. DONE AND ENTERED this 9th day of October, 2000, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of October, 2000. COPIES FURNISHED: Rodney L. Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Robert A. Crabill, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-3060 Earl Henry Benjamin 9914 Connecticut Street Gibsonton, Florida 33534

Florida Laws (5) 455.227489.119489.1195489.129489.1425 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROGER S. WILLIAMS, 81-002194 (1981)
Division of Administrative Hearings, Florida Number: 81-002194 Latest Update: Sep. 03, 1982

Findings Of Fact At all times relevant hereto, Respondent, Roger S. Williams, held registered building contractor license number RB0026339 issued by Petitioner, Department of Professional Regulation, Construction Industry Licensing board, authorizing him to perform contracting under his individual name. Respondent, Frederick S. Schreiner, held certified general contractor's license numbers CG C004811 and CG CA04811 also issued by Petitioner authorizing him to perform contracting under his individual name and under Cape Development Corporation. Williams served as president of Architectural Builders, Inc. (ABI), a development firm located in Palm Bay, Florida. Schreiner was engaged in the contracting business generally in the Brevard County, Florida area. He has done construction work for ABI and Williams for the past eight or nine years. ABI held no licenses from either the state or local governments. On October 31, 1979, ABI entered into a construction contract with Jack and Stella Oleksy to construct a home at 842 South Becker Street, Palm Bay, Florida. The contract was approved by R. S. Williams as president of ABI. At a later undisclosed date, Williams attempted to pull a City of Palm Bay building permit on behalf of ABI. Whether the City gave formal or informal approval at that point is not clear; in any event the construction of the home began shortly thereafter. Several weeks later the City's chief building official told Williams that because he did not have local competency with the City, he could not pull a permit for a job. Williams was also advised that a recent change in state law required ABI to qualify to do business if ABI intended to construct homes within the City. When told that Frederick Schreiner would be constructing the home for ABI and that Schreiner held an appropriate license, the City official told Williams to have a construction contract executed between ABI and Schreiner to build the home. Thereafter, Schreiner pulled a permit for the job and posted it on the building site. He also gave the City a contract executed by he and ABI and which was dated November 29, 1979. During the course of the construction, Schreiner visited the building site approximately six to eight times. The work was done entirely by subcontractors who had been used on other construction jobs by Williams and Schreiner. The subcontractors were paid by ABI but worked under the supervision of Schreiner. When the job was completed Williams signed the final payment affidavit on which it was indicated that Williams was the contractor on the job. Oleksy was on the site daily to inspect the work. He complained periodically about various aspects of the job to Roger Williams. His main complaint concerned the trusses on the roof which he contended were out of alignment causing a wavy and uneven roof line. After the house was essentially completed, Oleksy lodged a complaint with Williams concerning the workmanship on the roof. Williams sent a carpenter to visit the premises who found some "variations" and worked for approximately three hours to correct the problem. He was then told by Oleksy it looked okay. Within the next few days, Oleksy again complained to Williams that the roof was wavy. Williams then sent out a roofing crew to attempt to correct the problem. After they completed their work, Williams received no further indication that the owner was unhappy. Williams later had a local relator familiar with the subdivision and an experienced carpenter who had framed more than 150 homes to view the roof. Both concluded the roof was of good workmanship and of similar quality to other homes in the neighborhood. Oleksy later filed a complaint with the City of Palm Bay concerning his roof. The City sent its chief building official to inspect the home. He described the roof as being of "poor workmanship". The same conclusion was reached by the city building inspector who also inspected the property. Because of this, the City made the notation "Hold problem roof" in its file and did not issue a certificate of occupancy to Oleksy. However, the City did not construe the roof to constitute a violation of the building code. Respondents asserted that a 1979 change in the law as to the qualification of agents caused doubt and confusion as to what was required by ABI and Williams. They also point out that if indeed a violation occurred, it was not intentional. Rather, Respondents simply desired to comply with all applicable statutes and regulations so that their construction businesses could continue to operate in a lawful manner. Other than the alleged violations herein, Respondents were not shown to have been subject to any prior disciplinary proceedings.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent, Roger S. Williams, be found guilty as charged in Count I, and be given a public reprimand. the remainder of the charges should be dismissed. It is further RECOMMENDED that Respondent, Frederick L. Schreiner, be found guilty as charged of all allegations except willfully and deliberately violating a state law, and be given a public reprimand. DONE and ENTERED this 29th day of June, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1982.

Florida Laws (4) 120.57489.119489.127489.129
# 9
DEPARTMENT OF TRANSPORTATION vs. LUST INDUSTRIES, 82-002185 (1982)
Division of Administrative Hearings, Florida Number: 82-002185 Latest Update: May 21, 1990

Findings Of Fact Prior to March of 1981, Maxmedia held permits 8463-6 and 8462-6 issued by the Department for signs on property leased from Lust Industries located approximately at the intersection of U.S. 17/92 and Virginia Avenue in the city of Orlando, Florida. On March 23, 1981, Maxmedia advised the Department that the sign for which it held the above permits had been dismantled, and permits numbered 8463-6 and 8462-6 were returned to the Department for cancellation. On March 18, 1981, the Department received the application of Lust Industries for a sign at the location where the Maxmedia sign had been permitted, to be erected on property owned by Lust Industries. This application contained several irregularities, and the Department accepted it as an application only for the south face of the proposed sign. On May 27, 1981, the Department received the application of Lust Industries for the north face of this sign. The requested permits were issued by the Department on May 27, 1981. On February 24, 1981, Maxmedia executed a lease to property located approximately 30-50 feet south of the Lust Industries property. The term of this lease was to run from April 1, 1981 to April 1, 1984. On March 21, 1981, the Department received an application from Maxmedia for permits to erect signs at the location 30-50 feet south of the location owned by Lust Industries where Maxmedia had permits until it surrendered them. These permits were denied by the Department because of the permit application already received from Lust Industries for a sign 30 to 50 feet to the north. On March 23, 1981, Maxmedia applied to the city of Orlando for a building permit to erect the sign at its leased location south of the Lust Industries property, and this permit was issued to Maxmedia by the city. In January or February, 1981, Lust Industries had applied to the city of Orlando for a permit to build a sign on property near the sign of Maxmedia which was dismantled in March of 1981, but the requested city permit was denied because of the proximity of this location to the Maxmedia sign. After, the Maxmedia sign had been taken down, Lust Industries again applied for a city of Orlando building permit, but this was after the city permit had already been issued to Maxmedia; thus, the city again denied a permit to Lust Industries due to the existence of the outstanding permit held by Maxmedia. In May or June of 1981, after having received a building permit from the city of Orlando, and after having leased the property, Maxmedia proceeded to erect the sign 30-50 feet south of the Lust Industries property. It is this sign that is the subject of the Department's violation notice issued on June 30, 1982. It is the existence of this sign of Maxmedia, permitted by the city of Orlando, and erected on land currently leased, that prevents Lust Industries from obtaining the city of Orlando building permit it needs in order to be able to erect a sign 30 to 50 feet to the north. Thus, the Department seeks to revoke the state permits it issued to Lust Industries which violate the harmony of regulations provisions of the statutes and rules.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department issue its Final Order revoking the permits held by Lust Industries, dismissing the Notice of Violation against Maxmedia, Inc., and granting the application of Maxmedia, Inc., for permits as requested in its application received on March 24, 1981. THIS RECOMMENDED ORDER entered on this 18th day of April, 1984, in Tallahassee, Florida. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of April, 1984. COPIES FURNISHED: Charles G. Gardner, Esquire Haydon Burns Building, M. S. 58 Tallahassee, Florida 32301-8064 William F. Poole IV, Esquire 644 West Colonial Drive Orlando, Florida 32802 Gerald S. Livingston, Esquire P. O. Box 2151 Orlando, Florida 32802 Paul N. Pappas, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301

Florida Laws (4) 120.57479.07479.08479.15
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer