Findings Of Fact Sarasota County's Comprehensive Plan Amendment RU-5 was adopted, as Sarasota County Ordinance No. 91-41, on July 3, 1991. RU-5 amends the 1989 "Revised and Updated Sarasota County Comprehensive Plan," which is also known as "Apoxsee." Res Judicata and Collateral Estoppel.-- The 1989 plan, Apoxsee, is the subject of the Final Order, Hiss v. Sarasota County, ACC 90-014, DOAH Case No. 89-3380GM (the Hiss Final Order). The Hiss Final Order resulted from the Section 163.3184(9) formal administrative proceeding Hiss initiated after notice by the Department of Community Affairs (the DCA) of its determination that the adopted Sarasota County comprehensive plan was "in compliance." After a final hearing, a Division of Administrative Hearings hearing officer entered a Recommended Order on August 14, 1990, recommending that, for certain specified reasons, the plan be found to be not "in compliance." After consideration of the Recommended Order and exceptions to it filed by Hiss, by the County and by the intervenors, the DCA determined that the plan was not in compliance, concluded that, with the exception of the remedial actions recommended by the hearing officer, the Recommended Order should be adopted. The DCA submitted the Recommended Order to the Administration Commission for final agency action (the Hiss Final Order), which was taken on June 4, 1991. The Hiss Final Order recited in part 4/: PRELIMINARY STATEMENT * * * The Recommended Order divides Hiss' numerous allegations for the plan's noncompliance into four categories: the first alleging adoption in a manner inconsistent with the minimum criteria regarding public participation, the second involving the Recreation and Open Spaces Element, the third involving the Future Land Use Element and Future Land Use Map, and the fourth involving urban sprawl. The Hearing Officer concluded that the plan was in compliance with regard to the first, second and fourth of these categories. But, with regard to the third category, the Future Land Use Element and Future Land Use Map, the Hearing Officer concluded that the plan was not in compliance for a number of reasons. * * * ACTION ON THE RECOMMENDED ORDER Pursuant to Section 120.57(1)(b)10., Florida Statutes, the Commission accepts the Findings of Fact and the Conclusions of Law contained in the Recommended Order . . . with the exception of the recommended Remedial Action to the extent inconsistent with the Remedial Action ordered below. The Sarasota County comprehensive plan, therefore, is determined to be not in compliance for the reasons set forth in the Recommended Order and the following remedial action is ordered. REMEDIAL ACTION The following remedial action pursuant to the schedule in paragraph 15, below, is hereby ordered to bring the comprehensive plan of Sarasota County into compliance: * * * a. Plan amendments ordered herein shall be prepared by the County and transmitted to the Department of Community Affairs by September 30, 1991. DCA by October 15, 1991 shall certify to the Commission that the plan amendments have been received. In the event the plan amendments are not received by that date the DCA shall notify the Commission by October 31, 1991 and the Commission shall review the matter as to the appropriate action to be taken. DCA shall report to the Commission on the progress of its review of the plan amendments by February 15, 1992. DCA shall forward a recommendation to the Commission regarding the County's conformance with the remedial action ordered herein no later than June 1, 1992. SANCTIONS Under the circumstances of this case, the Commission exercises its discretion to impose no sanctions on the County at this time. The Commission retains jurisdiction, however, to consider sanctions available under Chapter 163, Florida Statutes, and to impose sanctions in the future if the County fails to comply with the remedial actions of this order. Paragraph 10 of the "Remedial Actions" portion of the Final Order, which required the County to amend Policy 1.1.2 and add or amend other appropriate objectives and policies in the Public Facilities Plan as described therein, contained the following footnote: "Clarifica- tion of the language in the amendments ordered by Remedial Action 10, so long as they do not depart from the purposes of the remedial actions ordered, may be made by the County subject to review and compliance determinations by the Department of Community Affairs and this Commission." The Walton Tract. The Walton Tract is approximately 6,151 acres of land in south central Sarasota County. It is about a mile east of Interstate 75 and is presently undeveloped with vegetation typical of the pine flatwood community. At the time Apoxsee was adopted, the County was in the process of planning for a solid waste disposal complex on the Walton Tract but had not yet identified an exact landfill site on the tract. In Apoxsee, the entire Walton Tract was identifed as the general area for the proposed Central County Solid Waste Disposal Complex, and the entire Walton Tract was designated as "Public Resource Lands." Prior Proceeding.-- In part, the Recommended Order adopted in the Hiss Final Order found: Neither the FLUM nor the FLUE designates a category of land devoted to conservation use. Designations tending to include conservation uses are Public Resource . . .. The Public Resource Lands designation is assigned to, among other parcels, the Walton Tract where any preservation or conservation uses will be subjected to the use of a part of the tract as a landfill, as discussed in Paragraphs 246 et seq. The primary provision in the plan describing the uses associated with Public Resource Lands is Policy 1.2 of the FLUE, which is "[t]o acquire and protect Public Resource Lands." In addition, FLUE Policy 1.2.3 permits environmental management practices on such lands, including controlled burning. These provisions are readily applicable to the other three parcels designated as Public Resource Lands and the part of the Walton Tract undisturbed by the landfill. However, these provisions are inconsistent with the portion of the Walton Tract proposed for use as a major landfill and other areas affected by this intensive use. * * * The inclusion of the entire Walton Tract in the Public Resource Lands is inconsistent with the proposed use of a substantial part of the tract as a major landfill. If the County eliminates this inconsistency by designating the actual landfill area and other affected areas as institutional or other public facilities, the Public Resource Lands designation would be consistent with the conservation designation. If the actual landfill area remains designated as Public Resource Lands, the designation of the Walton Tract as Public Resource Lands precludes, to the exclusion of fair debate, a finding that the Public Resource Lands designation is consistent with the criterion of a conservation designation. * * * It is fairly debatable that the plan is consistent with the criterion of a policy addressing intergovernmental coordination with respect to the conservation, protection, and appropriate use of interjurisdictional vegetative communities. With one exception, it is fairly debatable that the plan is consistent with criteria of policies addressing the protection of natural reservations and the designation of environmentally sensitive lands. [F.A.C. Rule 9J-5.013(2)(b)7. and 9.] To the exclusion of fair debate, the plan is not consistent with the latter two criteria as applied to the designation of the entire Walton Tract as Public Resource Lands, despite the intended use of part of the tract as a major landfill. The early stages of planning for the landfill may prevent the plan from dealing specifically with the likely environmental impacts of a landfill yet to be designed or sited. However, the plan should contain many of the provisions of the management plan promised for the Walton Tract. If, as the Supportive Material indicates, the landfill disturbs one-third of the Walton Tract, siting the landfill among the important environmental resources in the area is a critical task requiring more from the plan than inaccurately designating the entire tract as Public Resource Lands or promising the issuance of a management plan at some point in the future. The plan fails to provide guidelines for a detailed management plan, and guidelines are especially critical for the coordination of a major landfill with sensitive natural resources in the area. Detailed and effective safeguards in the plan for the Walton Tract and surrounding natural resources would require that the landfill project conform to these requirements. If some aspect of the landfill design prevents conformance with such plan provisions, the County may amend the plan with in [sic] compliance with all procedural requirements of the Act, including public participation and review by DCA. Absent effective provisions concerning the landfill to be placed in the Walton Tract, it is impossible to find that the plan contains policies addressing implementation activities for the protection of existing natural reservations. The Walton Tract is designated in its entirety as Public Resource Lands, and the conversion of part of this land to a landfill is not consistent with the protection of the entire tract. The same findings apply with respect to the designation of environmentally sensitive land because the Walton Tract is the site of critical natural resources, including various types of wetlands, part of Cow Pen Slough, and part of the Myakka River floodplain, as well as a bank of part of the Myakka River. * * * 402. To the exclusion of fair debate, the FLUM is not consistent with provisions to protect and acquire environmentally sensitive lands due to the conflict between the Public Resource Lands designation of the Walton Tract on the FLUM and the proposed use of part of the tract as a major landfill . . .. In part, the Recommended Order adopted in the Hiss Final Order concluded: 76. Based on the ultimate findings of fact contained in Paragraphs 366 and 367, the plan . . . is consistent with the criterion of the designation on the FLUM of proposed conservation land uses, if the designation of the part of the Walton Tract proposed for actual landfill use and any other affected area are redesignated from Public Resource Lands to another designation such as institutional or other public facilities. Otherwise, the plan is not in compliance with the Act and Chapter 9J-5 because it is not consistent with the criterion of the designation on the FLUM of proposed conservation land uses. * * * Based on the ultimate findings of fact contained in Paragraphs 376 et seq., the plan is consistent with these [9J-5.013(2)(c)7.-9.] criteria with one exception. The plan is not in compliance with the Act and Chapter 9J-5 because the treatment of the entire Walton Tract is not consistent with criteria of the protection of existing natural reservations and designation of environmentally sensitive land for protection. The designation of the Walton Tract as Public Resource Lands despite the proposed use of part of the tract as a landfill demands, to the exclusion of fair debate, more specificity in the plan coordinating the land uses that will be permitted on the tract with the sensitive natural resources already there. Because of the intense use proposed for part of the tract and the proximity of important natural resources, the promise to adopt later a management plan for the Walton Tract is insufficient. . . . The proposed uses and special features of the Walton Tract require that, regardless of its future land use designation, the plan provide details of the management plan, if the plan is to contain policies addressing implementation activities for the protection of environmentally sensitive lands and existing natural reservations. [Fn. 43.--This determination remains applicable even if the County redesignates the Walton Tract as institutional or other public facilities. Although arguably redesignation could result in the tract losing its status as an existing natural reservation, the tract, or at least parts of it, would continue to represent environmentally sensitive lands, whose status is unaffected by any change in designation.] * * * 109. Based on the ultimate findings of fact contained in Paragraph 402, the plan is not in compliance with the Act and Chapter 9J-5 because the FLUM is not consistent with FLUE objectives and policies to protect and acquire environmentally sensitive lands with respect to the designation of the entire Walton Tract . . .. The Hiss Final Order required the following Remedial Action pertinent solely to the Walton Tract: 5. The County shall revise the section in the solid waste portion of the Public Facilities chapter that refers to "landfill Site Feasibility Report: Walton Tract and Central County Solid Waste Disposal Complex - Preliminary Cost Estimate" to reflect that the Walton Tract is currently only one potential location for the proposed landfill, subject to additional study. The County shall also adopt a policy requiring that at such time as a final decision is made on the location and type of solid waste treatment facility to be developed, the Future Land Use Plan Map Series and Public Facilities chapter will be amended accordingly to reflect that decision. The RU-5 Walton Tract Amendments.-- In part, RU-5 amends Figure 23, a part of the Future Land Use Map (FLUM) Series, to delineate 2,972 acres of the Walton Tract as "Public Resource Lands" and 3,179 acres of the Walton Tract as "Central County Solid Waste Disposal Complex and other Government Use." RU-5 specifically locates a proposed solid waste disposal complex on 550 acres of the 3,179 acres designated as "Central County Solid Waste Disposal Complex and other Government Use." The 2,972 acres in the Walton Tract designated as "Public Resource Lands" were zoned Open Use Conservation (OUC) by Sarasota County Ordinance 90-54. RU-5 also amends the Public Facilities Element of the Sarasota County Comprehensive Plan (Apoxsee) by adding Objective 2.6 and Policy 2.6.1. Objective 2.6 is: To develop a solid waste disposal complex and site which is economically feasible and which has minimal environmental impacts. Policy 2.6.1 states: The Central County Solid Waste Disposal Complex shall minimize, to the greatest extent possible, potential environmental impacts consistent with the adopted stipulations contained within Ordinance No. 90-54 and Resolution No. 91-149. Prior to development of the Central County Solid Waste Disposal Complex a resource based Land Management Program shall be adopted consistent with the "Principles for Evaluating Development Proposals in Native Habitats" and all other relevant policies in the Environment Chapter. The Public Facilities Supportive Material adopted as part of RU-5 states: The Board also approved a special exception for a 550 acre parcel for the Solid Waste Disposal Complex including a sanitary landfill and other uses associated with the landfill operations. * * * In order to minimize potential environmental impacts to the greatest extent possible, stipulations in the special exception approval include requirements for submission of studies such as the completion of a background Water Quality Monitoring Plan and a resource based Land Management Program, prior to the development of the landfill or other associated operations. Data and Analysis.-- The RU-5 amendments relating to the use of a portion of the Walton Tract for the Central County Solid Waste Disposal Complex are supported by the best available data and by appropriate analysis of the data. The County utilized all the appropriate data available at the time of the adoption of RU-5. All analysis required to be performed on the data through the time of the final hearing was performed and taken into consideration. Both the data and the analysis of the data through the time of the final hearing support the selection of the Walton Tract site for the Central County Solid Waste Disposal Complex. The total functional population of Sarasota County is projected to increase from 337,471 in 1990 to 475,353 in 2010. Meanwhile, with the closure of numerous unlicensed dump sites in the early 1970s, the County began operating the Bee Ridge Landfill in 1972. Although two of the County's four municipalities formerly operated landfills, those facilities have been closed due to environmental problems. Bee Ridge currently is relied on to serve all the municipalities as well as the entire unincorporated area of Sarasota County. Bee Ridge receives an average of 1,400 tons of solid waste per day (511,000 tons a year). Even assuming a 50% reduction in solid waste disposal through recycling, the County is projected to require solid waste disposal facilities capable of land filling over 850,000 tons per year. A County study entitled Solid Waste Management and Resource Recovery Plan, completed in 1980, indicated that landfilling would likely remain an essential means of managing the County's solid waste stream for the foreseeable future and that it would be necessary to obtain a replacement facility for the Bee Ridge Landfill. The Bee Ridge Department of Environmental Regulation (DER) permit expires in 1995. Bee Ridge was not constructed with liners meeting current DER permit requirements. Although the County has installed an underground "slurry wall" at the perimeter to attempt to prevent contamination from leaching out, there is no assurance that DER will renew the permit. In any event, Bee Ridge is projected to reach its maximum height by the mid-1990s. In addition, the ability to expand Bee Ridge is not assured, due to strong opposition from neighboring property owners. In 1986, the opportunity arose to acquire the Walton Tract without the use of condemnation, and the County authorized a specific feasibility study performed on the 6,151 acre tract. The study examined the parcel in terms of Florida statutory landfill requirements, physical characteristics of the site, hydrogeology and soils, landfill block configurations, environmental considerations, and regulatory agency comments. Although the study indicated that only 3,600 acres would be required for a landfill, the entire tract was purchased on advice of professional staff to maximize siting flexibility and ensure sufficient areas for perimeter buffers, wetland mitigation, and wildlife conservation areas. The purchase price was $8.6 million, paid out of the proceeds of an $80 million Solid Waste System Revenue Bond Issue. Preliminary cost estimates were prepared for the initial 20 years of the life of a landfill on the site. The estimate came to $39 million. At the time the Revised and Updated Sarasota County Comprehensive Plan was being compiled in the years prior to its adoption in 1989, the County had not yet identified an exact landfill site on the Walton Tract. Accordingly, Apoxsee identified the entire Walton Tract was identified as the general area for the proposed Central County Solid Waste Disposal Complex. The Walton Tract was also designated entirely as "Public Resource Lands" since the County regarded the "Public Resource Lands" use designation to permit public facilities in careful conjunction with large conservation areas of important native habitat, e.g., a potable water wellfield and water treatment plant on the Carlton Reserve; a solid waste disposal complex on the Walton Tract; and RV parks, campsites and active recreation facilities at Oscar Scherer State Recreation Area and Myakka River State Park. In the spring and summer of 1991, after entry of the Hiss Final Order, the Board of County Commissioners held public hearings to determine whether the Walton Tract should once again be designated as the site for the Central County Solid Waste Disposal Complex to accommodate a Class I landfill, composting areas for yard waste and yard waste/sludge recycling, and a Class III landfill for construction debris, and, if so, to determine the specific location and extent of the Complex, in the context of a rezoning and special exception proceeding. During the course of the hearings the County Commission considered detailed presentations by the county professional staff, expert consultants and the public concerning the suitability of the Walton Tract site, as well as other sites, for a solid waste disposal complex. The Commission also considered, as part of the evidence, a Draft Alternative Siting Study prepared by the engineering firm Camp Dresser & McKee (CDM) to meet the regulatory requirements of the EPA and Corps of Engineers under Section 404 of the Clean Water Act and the requirements of the Recycle Now! Chapter Amendment. At the conclusion of the hearings, the County Commission, by Ordinance 90-54 rezoned 3,179 acres of the Walton Tract to Government Use (GU) and 2,972 acres to Open Use Conservation (OUC). The Commission, by Resolution 91-149 also designated a reduced 550 acre site (instead of a 1,187 acre site) for the Central County Solid Waste Disposal Complex subject to final action on Comprehensive Plan Amendment RU-5, which was adopted by Ordinance 91-41 on July 23, 1991, after another public hearing at which all the evidence from the rezoning and special exception hearings was received into the record. (a.) Economic Feasibility.-- The Walton Tract site is centrally located in the County, between what are planned to be the County's major population concentrations, and close to the Laurel Road interchange with I-75 which is committed to be constructed by FDOT in 1993 under an agreement with the County. This location provides efficient transportation access to the rest of the County. The trend in solid waste management is toward centralizing solid waste disposal facilities due to the cost of the facilities, including the cost of permitting; the ability to achieve economies of scale; the increased reliability inherent in operating a limited number of facilities; and the advantages of focusing budget-limited management and regulatory compliance resources. Transportation costs with a centralized facility are offset by the use of transfer stations which greatly compress the solid waste to reduce the number of trips from the transfer station to the central facility. Sarasota County is already successfully using this system. The Draft Alternative Siting Study identifies three other properties besides the Walton Tract as suitable. During the public hearings before the County Commission, however, two of the sites (D and E) were strongly opposed by citizens living around those potential sites and the third site (G) was closer to the Myakka River and could be in conflict with the Myakka River Wild and Scenic Management Plan. From the standpoint of economic feasibility, the County Commission was advised: The County has certain bond obligations due to the purchase of site F [the Walton Tract] to provide a solid waste disposal facility. The legal and future bond financing issues must be considered against the potential benefits of selecting another site. The County's bond counsel also advised the County Commission that, if the County elected not to locate the solid waste disposal complex on the Walton Tract, the County would have to pay back to the Solid Waste System Revenue Bond enterprise fund the fair market value of the Walton Tract from some other revenue source. (b.) Adjacent Property.-- In contrast to the other suitable sites, the property owners closest to the proposed site on the Walton Tract are not opposed to the solid waste disposal complex in light of the County's ability to provide 1,000 foot buffers and avoid access conflicts due to the size and location of the Walton Tract. Due to the 6,151 acre size of the Walton Tract, the solid waste disposal complex, as approved by the County Commission, including all borrow pits, is located more than 8,000 feet from the closest point on the Myakka River, a designated Wild and Scenic River, and the testimony indicates that heavy equipment would not be heard on the river. Due to the flexibility in siting the solid waste disposal complex, and the 100 foot height limitation placed on the landfill by the County Commission, the landfill will not be seen on Lower Myakka Lake or the Myakka River. Due to the location of the solid waste disposal complex on the Walton Tract, together with the hydrogeologic characteristics of the site, no adverse impact on the Carlton (Ringling MacArthur) Reserve potable water wellfield located several miles to the east across the Myakka River is to be anticipated. The restriction of the solid waste disposal complex and associated borrow pits to the northwest portion of the Walton Tract and the designation by the County Commission of the remainder of the property as Public Resource Lands results in approximately 3,000 acres of the Walton Tract, contiguous to Myakka River State Park and the Carlton Reserve to the east, being placed in a conservation land use designation, linking these natural areas into a contiguous system of 55,000 acres of high quality native habitat in protected public ownership. (c.) Character of the Walton Tract.-- Hundreds of hours over a period of approximately five years were spend on-site at the Walton Tract by experts in environmental, engineering and other scientific disciplines to collect and analyze data on soils; topography; natural resources, including habitats, flora, and fauna; and historic resources to determine whether, and where, a solid waste disposal complex should be sited on the tract that would be economically feasible and minimize environmental impacts. Every wetland and upland habitat on the Walton Tract as well as likely ecological corridors and preservation areas, including the Myakka River 100 year floodplain and mesic hammocks, have been identified and verified in the field. The methods that were used to identify habitats, including likely habitats of threatened and endangered species, met professionally accepted standards, particularly for planning purposes. Environmental constraints were identified at the beginning of the assessment of the Walton Tract and drove or determined the siting process. Over the course of a five year period, there were no sightings of threatened or endangered species that would render the designated site of the complex or the borrow pits unsuitable for the proposed use. The designated site was suitable from the standpoint of minimizing environmental impacts. The pine flatwoods and isolated wetlands within the solid waste disposal complex footprint are neither rare nor endangered, constituting 57% and 17% of the area of the County, respectively, and there are suitable formerly improved pasture areas on the site to mitigate these wetlands on a type-for- type, one-for-one ratio. There is also a large 300 acre area adjacent to Cow Pen Slough suitable for mitigation by rehydrating wetlands previously impacted by the channelization of Cow Pen Slough in the 1960's. The proposed location of the landfill on the site is the most appropriate from the context of habitat, wetlands and wildlife. The complex and borrow pits protect water resources by being located outside the watershed of the Myakka River and outside the 100 year floodplain of Cow Pen Slough. Also, the Class I landfill will be elevated approximately three feet above grade, and the entire solid waste disposal complex will be surrounded with a bermed stormwater management system at least five feet above grade that will not only treat the stormwater to required standards but also provide additional protection against flooding beyond a 100 year flood event. The reduced 550 acre size of the solid waste disposal site is reasonable for meeting the solid waste recycling and disposal needs of the County for a 20 year planning period. CDM used the best available data, including the Federal Emergency Managment Agency (FEMA) Flood Insurance Rate Maps (FIRM), in siting the complex out of the 100 year floodplain. (The U.S. Soil Conservation Service 1985 Flood Plain Management Study of the Cow Pen Slough is not reliable data with respect to the extent of the 100 year floodplain.) The site designated for the landfill on the Walton Tract has no geotechnical or water resource factors that would preclude it from being suitable for a landfill. There is no realistic danger of groundwater contamination of either the surficial or the deeper Floridan aquifer beneath the landfill in light of the required multiple liners and the required leachate collection and treatment systems. A modern landfill operation is not necessarily incompatible with surrounding wildlife. The landfill would be limited to an exposed working face of solid waste no more than 100 feet by 200 feet which must be covered daily. This reduces the landfill's attactiveness to seagulls and other scavengers. Many species of birds, including sandhill cranes, woodstorks, and bald eagles, continue to be seen within several hundred yards of the working face of the Bee Ridge landfill and its heavy equipment. Over the 12 year existence of the Bee Ridge landfill, there has been no quantifiable decline in such wildlife. The herd of deer adjacent to the landfill had increased substantially over that period. Internal Consistency.-- It was not the intent of RU-5's Public Facilities Objective 2.6 and Policy 2.6.1 that the specifically designated site for the solid waste disposal complex on the Walton Tract would be invalidated if any other possible site were found to have even marginally less environmental impact. Although there are other sites arguably with less environmental impacts, according to a rating system developed for evaluating the suitability of potential sites, other factors also went into the selection of the Walton Tract site. Both Public Facilities Objective 2.6 and Policy 2.6.1 contemplate the development of a solid waste disposal complex and site. They mean that the designated site should be developed in a manner which reduces environmmental impacts as much as possible. It certainly is at least fairly debatable that they contemplate the development of the Walton Tract site as a landfill. RU-5's amended "Principles for Evaluating Development Proposals in Native Habitats," Section VI.A.2.e., provides in part: In cases where a wetland is no longer capable of performing defined environmental functions and providing defined environmental values, or in cases where no other reasonable alternative exists other than disrupting a wetland, some alteration may be allowed. As amended by RU-5, this portion of the "Principles for Evaluating Development Proposals in Native Habitats" focuses on wetland mitigation requirements on other portions of a landowner's property, when a wetland must be altered to allow reasonable, beneficial use of the property. Section VI.A.2.e. of these principles does not require the County, or any other property owner, to demonstate, prior to developing their property, that there is "no reasonable alternative location in the County which impacts less wetlands or an equivalent acreage of wetlands of less environmental value." It certainly is at least fairly debatable that they do not. The Supportive Material for Apoxsee's Recreation and Open Space Element states: "Large portions of the Walton Tract cannot be used for landfill purposes because they are in the floodplain of either the Myakka River or the Cow Pen Slough." Nothing in RU-5 is inconsistent with this data and analysis. The acreage being used for the landfill and associated uses are not in the floodplain. Through RU-5, Recreation Policy 1.1.4 of Apoxsee provided: "Ecologically benign, non-consumptive, resource-based uses shall be implemented at the Walton Tract and the Ringling-MacArthur Reserve." On March 10, 1992, RU- 6 was adopted and amended Recreation Policy to provide: "Recreational uses implemented on the Walton Tract and the T. Mabry Carlton, Jr., Memorial Reserve [formerly known as the Ringling-MacArthur Reserve] shall be limited to activities which are ecologically benign, non-consumptive and resource based." It is at least fairly debatable that this policy does not refer to the portion of the Walton Tract designated for use as a landfill. Future Land Use Element (FLUE) Objective 1.1, as amended through RU-5, restricts land uses on Public Resources Lands by requiring the County: "To protect environmentally sensitive lands, conserve natural resources, protect floodplains, maintain water quality, and maintain open space." FLUE Objective 1.2 is: "To acquire and protect Public Resource Lands." The implementing policies under FLUE Objective 1.2 include: Policy 1.2.1 -- Sarasota County shall attempt to coordinate efforts to acquire public lands for conservation, preservation and open space. Policy 1.2.2 -- Provide adequate buffering of Public Resource Lands for potentially incompatible adjacent land uses. Policy 1.2.3 -- Permit normal management practices associated with native habitats. Again, it is at least fairly debatable that these objectives and policies do not preclude the designation of a part of the Walton Tract for use as a landfill. The Supportive Material for Apoxsee's FLUE states that the County will adopt "detailed management plans" for the Walton Tract (and the Ringling- MacArthur Reserve) and adds: In conjunction with the development of a portion of these two County-owned properties as a waste disposal complex and potable water supply, respectively, subtantial acreage is to be preserved to provide for wildlife corridors, wetlands protection, buffering zones, recreation, education, and open space uses. It is critical that any development within, and adjacent to, these Public Resource Lands be compatible with their inherent environmental values as well as the public values ascribed to them. The management plans . . . will address this issue. The County has not yet adopted a management plan for the Walton Tract landfill. But Public Facilities Policy 2.6.1 incorporates the detailed protective stipulations contained in Ordinance 90-54, which zoned the Walton Tract "Government Use" and "Open Use, Conservation," and in Resolution 91-149, which designated the site of the Central County Solid Waste Disposal Complex. These stipulations: require submission of a background water quality monitoring plan for review and approval by the County Natural Resources Department; require a preapplication meeting with the Stormwater Management, Natural Sciences, and Pollution Control Divisions prior to submission of a Master Stormwater Management Plan; limit post development runoff volumes to predevelopment volumes for storm events up to the mean annual (2.33-year) storm; require design and planting of littoral zones in all stormwater detention lakes in accordance with the County Land Development Regulations; require design and planting of littoral zones in all borrow lakes in accordance with the County's Earthmoving Ordinance; require submission of a final mitigation plan, including engineer drawings and plans for creating and maintaining adequate hydroperiods in created wetlands for review and approval by the Natural Sciences Division; require clear delineation and, during construction, marking of Preservation/Conservation areas; require appropriate sediment control devices around buffers of all wetlands within 500 feet of construction; prohibit disturbances in any Perservation/Conservation area except in approved construction areas or to provide approved access roads, fire lanes, utility transmission lines or nature trails; require notification to the Natural Sciences Division for determination of appropriate remedial action in the event listed species are observed; prohibits development of the solid waste disposal complex until a resource-based Land Management Program is prepared, approved and adopted; and limits the height of the landfill to 100 feet. In addition, Public Facilities Policy 2.6.1 prohibits development of the solid waste disposal complex until a resource-based Land Management Program is adopted consistent with the detailed requirements of the "Principles for Evaluating Development Proposals in Native Habitats" and the policies of the Environment Chapter of Apoxsee, e.g., Environment Policy 5.5.13, as well as Recreation Policy 1.1.4 and Future Land Use Policies 1.2.2 and 1.2.3. The Hiss Final Order does not require that a detailed management plan be adopted as part of RU-5 in order for RU-5 to amend the FLUM Series to designate a portion of the Walton Tract as the new County landfill. Rather, it was critical that the 1989 "plan fails to provide guidelines for a detailed management plan, and guidelines are especially critical for the coordination of a major landfill with sensitive natural resources in the area." (Emphasis added.) Recommended Order, Finding of Fact 378. It stated that "the plan should contain many of the provisions of the management plan promised for the Walton Tract." (Emphasis added.) Recommended Order, Finding of Fact 377. While not specifying the management plan guidelines believed to be necessary, the Hiss Final Order found that the plan was not "consistent with criteria of policies addressing the protection of natural reservations and the designation of environmentally sensitive lands [referring to F.A.C. Rule 9J-5.013(2)(b)7. and 9.]." (Emphasis added.) Recommended Order, Finding of Fact 376. Elsewhere, it found it "impossible to find that the plan contains policies addressing implementation activities for the protection of existing natural reservations." (Emphasis added.) Recommended Order, Finding of Fact 379. F.A.C. Rule 9J-5.013(2)(b)7. and 9. require objectives that "[protect] existing natural reservations identified in the recreation and open space element" and "[designate] environmentally sensitive lands for protection based on locally determined criteria which further the goals and objectives of the conservation element." The plan, as amended through RU-5, contains guidelines for a management plan for the Walton Tract that are sufficiently detailed to meet the requirements of F.A.C. Rule 9J-5.013(2)(b)7. and 9. RU-5 is not inconsistent with the Support Material referred to in Finding 49, above. The final version of the management plan is not data or analysis that must precede the amendment of the FLUM Series. RU-6 amended Environment Policy 5.5.3 to read: By July 1, 1992, the Sarasota County Board of County Commissioners shall have adopted criteria for conducting and staff shall have conducted an analysis to identify habitats of high ecological values and strategies to physically link natural areas into a contiguous system. The criteria for identifying these areas should consider several major factors including the presence of endangered species, outstanding water resources, high quality natural habitat, and value as a wildlife corridor. The Future Land Use Map Series shall be revised to show the location of these areas of high quality ecological value. This provision is not inconsistent with RU-5. The portion of the Walton Tract designated for development as a landfill is made up of pine flatwoods and isolated, seasonal wetlands which are neither rare nor endangered habitats. Except for a minor portion of the westernmost borrow pit, it is outside the 100-year floodplain. 5/ It is outside the watershed of the Myakka River. It is set back from habitats of threatened or endangered species, as well as surrounding property owners. It is reasonably sized to meet the solid waste recycling and disposal needs of the County for the 20-year planning period. Consistent with Environment Policy 5.5.3, the 2,971 acres of the Walton Tract which RU-5 leaves designated Public Resource Land includes those areas which are contiguous to Myakka River State Park and the Carlton Reserve to the east, linking natural areas into a contiguous system, and providing protection to the outstanding water resources and high quality habitat in the Myakka River watershed and in the Cow Pen Slough watershed in the southernmost portion of the Tract. Historic and Archaeological Preservation.-- In part, the Recommended Order adopted in the Hiss Final Order found: 362. To the exclusion of fair debate, the plan is not consistent with the criterion of the depiction on the ELUM of historic resources. The depicted archaeological sensitivity zones, which represent projections of possible sites, do not purport to represent the location of, for example, the 78 or 79 sites on the Florida Master Site Plan and other historical resources, which are concededly vulnerable to development. In part, the Recommended Order adopted in the Hiss Final Order concluded: As relevant to the determinations contained in this section, . . . Rule 9J- 5.006(1)(a)(11), . . . requires that the "following generalized land uses shall be shown on the existing land use map or map series: . . . Historic resources." Rule 9J-5.003(35) defines "historic resources" to mean: all areas, districts or sites containing properties listed on the Florida Master Site File, the National Register of Historic Places, or designated by the local government as historically, architecturally, or archaeologically significant. Based on the ultimate findings of fact contained in Paragraph 362, the plan is not in compliance with the Act and Chapter 9J-5 because it is not consistent with the criterion of showing historic resources on the ELUM. For instance, there are 78 or 79 sites in the Florida Master Site File that are, by definition, historic resources, but are not shown on any ELUM. The Hiss Final Order required the following Remedial Action pertinent to historic and archeological preservation: 2. The County shall revise its existing land use map to show the location of historic resources, including the generalized location of sites listed in the Florida Master Site File or National Register of Historic Places or otherwise designated by the County as historically, architecturally or archaeologically significant. * * * 4. The County shall revise its Future Land Use Plan Map Series to include the historic resources mentioned in paragraph 2 above. RU-5 amends the Historic Preservation Chapter of Apoxsee to indicate that the map provided in Figure 3 in the Future Land Use Map (FLUM) Series shows the location of "National Register sites and other historically significant sites in Sarasota County." It also amends Figure 3 to identify 78 National Register sites from the Florida Master Site File. Appendix A to "Section 3: Sites in Unincorporated Sarasota County Listed in the Florida Master Site File" also is amended to list these sites. In essence, RU-5 follows from the updating of the supporting documentation to Apoxsee by adding to the Existing Land Use Map (ELUM) Series and the FLUM Series verified historically significant sites in Sarasota County, namely the sites found on the National Register and on the Florida Master Site File List. The County also has performed extensive study of portions of the County in an effort to locate significant historic and archaeological sites. The study has located many potential sites. However, the sites have not yet been fully evaluated to determine if they are historically, architecturally or archaeologically significant. Therefore, they have not yet been added, or proposed to be added, to the National Register or the Florida Master Site File List, and they do not appear in Apoxsee, as amended by RU-5. The County's determination not to identify and depict more sites on RU-5 is supported by the best available data and analysis. In addition, RU-5 adopted Future Land Use Element (FLUE) Policy 1.13.1 which provides for the coordination of land uses with the protection of historical resources. As part of the process for issuing development orders, the County has incorporated review by the County Historian to determine the likelihood of the site being historically significant, and the County places conditions on various development permits to protect historically significant sites. Except for the failure of Apoxsee, before RU-5, to depict the locations of, "for example, the 78 or 79 sites on the Florida Master Site Plan and other historical resources, which are concededly vulnerable to development," the Historic Preservation Chapter of Apoxsee already has been exhaustively scrutinized and found to be internally consistent and in compliance. See Hiss Final Order. Floodplain Delineation and Protection.-- In part, the Recommended Order adopted in the Hiss Final Order found: To the exclusion of fair debate, the FLUM is not consistent with criteria of the depiction of floodplains; Big Slough, whether it is classified as a river, floodplain, or wetland; and minerals and soils. . . .. The omission of floodplains is complete. Nothing in FLUM-2 corresponds to the floodprone areas shown in Figure 27 in the Supportive Material. For example, the Conservation/Preservation areas surrounding the Myakka River are not coextensive with the larger floodplain of the Myakka River depicted in Figure 27. The omission of floodplains is exacerbated by the absence of plan provisions providing effective protection for these critical natural drainage features, except for the Myakka River floodplain. * * * To the exclusion of fair debate, the plan is not consistent with criteria of objectives to ensure the protection of floodplains (other than that of the Myakka River), floodplain- associated soils, and wetlands (due to the inadequacy of the mitigation provision). Policy 5.5.8 of the Environment Element promises to adopt land development regulations to regulate develop- ment and specify necessary design standards for floodplains. In the absence of any undertaking in the plan to require that land uses in the floodplains be consistent with their function, Policy 5.5.8 does not resemble an objective ensuring the protection of floodplains. To the exclusion of fair debate, the plan is not consistent with criteria of objectives to coordinate the future land uses with topography, soil conditions, and availability of facilities and services, with respect to floodplains and the unrestricted use of septic tanks 6/ in the Urban area. The Supportive Material advises that future land uses in the floodplains must be less intensive than in the past. Except for the Myakka River floodplain, the plan fails to coordinate future land uses with the unique topography and soil conditions of the floodplains because the plan does not require that any development in the floodplains be consistent with their functions. In part, the Recommended Order adopted in the Hiss Final Order concluded: 83. Based on the ultimate findings of fact contained in Paragraphs 372 et seq., the plan is not in compliance with the Act and Chapter 9J-5 because it is not consistent with criteria of the depiction on the FLUM of floodplains, Big Slough (regardless of its classification as a river, wetland, or floodplain), and minerals and soils. * * * 96. Based on the ultimate findings of fact contained in Paragraph 388, the plan is not in compliance with the Act and Chapter 9J-5 because it is not consistent with criteria of objectives to ensure the protection of flood- plains other than that of the Myakka River, floodplain-associated soils, and wetlands due to the inadequacy of the mitigation provisions. 7/ The Hiss Final Order required the following Remedial Action pertinent to floodplain delineation and protection: The County shall amend "Figure 27: 100-year Floodprone Areas" to depict the location of all 100-year floodplains . . . and adopt Figure 27, as amended, as an addition to the Future Land Use Map Series. The county shall amend "Figure 5: General Soil Associations in Sarasota County" to indicate general locations of known sand and gravel deposits, and adopt Figure 5, as amended, as an addition to the Future Land Use Map Series. * * * 9. The County shall adopt a new policy in the Future Land Use Plan, to provide that no development order shall be issued which would permit development in floodplains or on floodplain- associated soils that would adversely affect the function of the floodplain, or that would degrade the water quality of water bodies associated with the floodplains in violation of any local, state or federal regulation, including water quality regulations. In part, RU-5 amends FLUE Objective 1.1 to state: "To protect environmentally sensitive lands, conserve natural resources, protect floodplains, maintain water quality, and maintain open space." RU-5 also adds the following policies: Policy 1.1.5: "All future development shall be consistent with the detailed master plans for each drainage basin as they are adopted through the Basin Master Planning Program." [Revision of Environment Policy 2.1.8.] Policy 1.1.6: "No development order shall be issued which would permit development in 100-year floodplains, as designated on Federal Emergency Management Agency [FEMA] Flood Insurance Rate Maps [FIRM] or adopted County flood studies, or on floodplain associated soils, defined as Soils of Coastal Islands, Soils of the Hammocks, Soils of Depressions and Sloughs, and Soils of the Floodplains and shown in figure 5, that would adversely affect the function of the floodplains or that would degrade the water quality of waterbodies associated with said floodplains in violation of any local, State, or federal regulation, including water quality regulations." Policy 1.1.8: "'Figure 27: 100 - Year Floodprone Areas' shall be adopted as Future Land Use Plan Map 5." Policy 1.3.2: "'Figure 5: General Soil Associations In Sarasota County' shall be adopted as Future Land Use Plan Map 4." RU-5 also adds Environment Policy 5.8.2: Floodplain functions shall be protected by application of the Land Development Regulations (Ordinance No. 81-12, as amended) and Goals, Objectives, and Policies of the Public Facilities and Future Land Use Plans. RU-5 adds Public Facilities Policy 3.2.8: New development in the 100-year floodplains shall be consistent with the Goals, Objectives and Policies of the Environment, Public Facilities, and Future Land Use Plans. By virtue of the RU-5 amendments, which use the best available data (the FEMA FIRM) and appropriate analysis, the Apoxsee now depicts the floodprone areas in the County and plans appropriately for their protection. It is at least fairly debatable that the plan provisions are internally consistent. Septic Tanks.-- In part, the Recommended Order adopted in the Hiss Final Order found: A similar lack of coordination exists with respect to the unrestricted use of septic tanks in Urban areas. The Supportive Material discloses "chronic" septic tank failures in areas south of the City of Sarasota, south of Venice, and in the Englewood area at the southern tip of the County on the coast. The last area is one of the few areas remaining near the coast with significant amounts of vacant, unplatted land. Each of the three areas is adjacent to estuarine waters. The Supportive Material cautions that, without centralized sewer in the Englewood area, the County's last remaining shellfish harvesting area, which is in Lemon Bay, is threatened. The Englewood area also includes wellfields that draw upon the surficial aquifer, which is highly susceptible to contamination in this region. Failing to coordinate future land uses with topography, soil conditions, and availability of facilities and services, the plan allows the unrestricted use of septic tanks in these critical Urban areas. Promises to study the problem, prioritize areas for centralized hookup, and in the meantime "discourage" the use of on-site sewage disposal systems offer little in the face of chronic failures of on-site sewage disposal systems and the absence from Table 80 of any expenditures for a centralized wastewater treatment system. Sarasota Exhibit 38, which is the 1986 Englewood Sector Plan, illustrates, in its discussion of septic tanks, the historic lack of coordination between future land uses and topography, soil conditions, and the availability of facilities and services. The Sector Plan notes that the soils of the majority of undeveloped lands in the Englewood area are poorly drained with less than two feet between the surface level and the groundwater table. A 1970 study by the County Health Department concluded: "Based on test results it would appear that Englewood has already reached the point where further development without adequate centralized sewerage facilities will lead to increased problems with regard to fecal pollution of ditches and waterways." [Fn. 30--The Sector Plan mentions various requirements imposed by the County that, if incorporated into the plan, would help coordinate future land uses with topography, soil conditions, and availability of facilities and services. County Ordinance 81-12 prohibits septic tanks within 100 feet of a 25-year floodplain unless the lot is at least five acres. The same ordinance reportedly requires that "the groundwater table be maintained at not less than forty-eight (48 inches) [apparently from the bottom of the drainfield]." Sector Plan, p. VI-4. Also, the County requires hookup to centralized wastewater systems for all new residential subdivisions within one-quarter mile of an existing sewer line, although this requirement can be waived. Id. at pp. VI-4 and VI-5. Finding insufficient septic-tank restrictions imposed by the Department of Health and Rehabilitative Services, the County has adopted several ordinances regulating on-site sewage disposal systems. Plan, p. 166. Ordinances 83-14, 83-83, and 86-03 detail these requirements, but Appendix D, 2 does not describe them in much detail. More important, the restrictions contained in all of these ordinances did not find their way into the operative provisions of the plan.] Sector Plan, p. VI-4. In the context of a plan that allows unrestricted use of septic tanks anywhere in the Urban area, coordination is not achieved by a plan provision requiring "reasonable assurance" that development proposals within the watersheds of existing public potable surface waters (i.e., the upper Myakka River, both Myakka Lakes, and Big Slough) will not "degrade the quality of such water." Nor is coordination achieved by a provision offering the general assurance of protection and conservation of surface water and groundwater resources, or another provision promising the adoption of land development regulations to specify "design standards" in environmentally significant/sensitive areas like watersheds and water recharge areas. No plan provisions guide the review of specific development proposals. The plan contains no performance or design standards or any requirements to guide the preparation of such standards. [Fn. omitted.] The vague provisions governing the use of septic tanks in the Urban area do not provide, in the plan, a meaningful basis upon which to coordinate, in the plan, future land uses with topography, soil conditions, and availability of facilities and services. In part, the Recommended Order adopted in the Hiss Final Order concluded: 97. Based on the ultimate findings of fact contained in Paragraphs 390 et seq., the plan is not in compliance with the Act and Chapter 9J-5 because it is not consistent with the criterion of an objective to coordinate future land uses with topography, soil conditions, and the availability of facilities and services, with respect to floodplains and the unrestricted use of septic tanks in the Urban area. Besides the provisions already mentioned in connection with floodplain delineation and protection, the Hiss Final Order required the following Remedial Action pertinent to septic tanks: . . .. The Public Facilities Element, Future Land Use Element, and other appropriate elements must contain objectives, with principles, guidelines and standards, to coordinate future land uses with topography, soil conditions, and available facilites and services, with respect to both floodplain protection and the use of septic tanks. The County shall amend Policy 1.1.2 and add or amend other appropriate objectives and policies in the Public Facilities Plan, as follows 8/: * * * Policy 3.2.2 The County shall prohibit the installation of septic tanks in areas designated urban on the Future Land Use Plan Map Series, unless the installation and use shall not adversely affect the quality of groundwater or surface water or adversely affect the natural function of floodplains; further, the County shall adopt regulations which, to the maximum extent permitted by law, mandate hookup of existing as well as new development to a centralized wastewater treatment system. RU-5 amends Public Facilities Policy 3.2.2 to provide: The County shall prohibit the installation of septic tanks in areas designated Urban and Barrier Island on the Future Land Use Plan Map Series, unless the installation and use shall not adversely affect the quality of groundwater or surface water or adversely affect the natural function of floodplains as required by the provisions of the County Land Development Regulations (Ordinance No. 81-12, as amended); Ordinance No. 83-83, regulating design, construction, installation, utilization, operation, maintenance and repair of individual on-site sewage disposal systems, as amended; and any more stringent regulations applicable. Further, the County shall revise as necessary or adopt regulations which, to the maximum extent permitted by law, mandate hookup of existing as well as new development to a centralized wastewater treatment system, when available. The County has admitted, for purposes of effectuating a settlement, that Public Facilities Policy 3.1.2 is not in compliance for the reasons set forth in the settlement Stipulation between the Department and the County. By the Stipulation, the County agrees to further amend Public Facilities Policy 3.2.2 by amending the last sentence to read: Further, the County shall require that all buildings served by on-site sewage disposal systems, except approved on-site greywater systems, connect to a publicly owned or investor-owned sewerage system within one year of notification by the County that such a system is available as defined in Chapter 10D-6.042(7), F.A.C. The County shall establish procedures for the notification of sewer availability. RU-5 also amends Public Facilities Policy 3.2.5 to make clear that the requirement for compliance with federal, state and local permit laws extends to individual on-site systems. It also provides: Soil surveys shall be required for septic tank permits. No individual on-site systems shall be permitted where soil conditions indicate that the system would not function without degrading water quality or where land alterations necessary to accommodate the system would interfere with drainage or floodplain functions. RU-5 also amends Public Facilities Policy 3.2.9 to provide: By 1994, the County shall begin implementation of its wastewater resource management program to be completed by 2020. The comprehensive plan, including the Captial Improvements Element, shall be amended by 1994 to reflect implementation of the program. Priority shall be given to providing centralized service to areas experiencing septic tank failure and areas where water quality has been adversely affected by current disposal methods. RU-5 added Environment Policy 5.8.3: Septic tanks shall not adversely affect water quality in accordance with Ordinance No. 83-83 and goals, objectives and policies of the Public Facilities and Future Land Use Plans. The vast majority of septic tanks in the County were installed prior to the adoption of increasingly stringent County regulations during the 1970s and 1980s. Since the early 1980s, there have been virtually no subdivisions approved for septic tanks in urban areas. With one seldom-used exception, all urban subdivisions (densities greater than one dwelling unit per acre) are required to have central sewerage facilities. (The exception, for subdivisions of half-acre lots where central water is provided, has proven not to be economically feasible for the developer in most cases.) Virtually all new subdivisions are being connected to large franchised systems. Consistent with Public Facilities Policies 3.2.2 and 3.2.5 and FLUE Policy 1.1.6, current regulations already provide that no septic tanks or drainfields are permitted within 100 feet of the 25-year portion of the 100-year floodplain. Under current County regulations, all lots are required to meet the County standards. When a septic tank system fails, the property owner is required to upgrade the system to the current county standards to the maximum extent physically possible on the property. Apoxsee's Capital Improvements Element provides for the expenditure of $3,403,000 for expansion of the County-owned centralized sewerage system. The County Health Department is currently developing a priority list for the extension of central sewerage systems into the older subdivisions in the County which are experienceing septic tank system failures due to the age of the systems. Funding for the extension of central sewerage into septic tank subdivisions is awaiting completion and approval of the priority list and an estimate of the costs. The timing of funding and implementation under RU-5 is reasonable and is supported by the best available data and appropriate analysis. Apoxsee specifically coordinates the density of urban development with central water and sewer service through FLUE Policies 1.7.2 and 1.7.3, as well as the application of the Urban Area Residential Checklist and the Urban Area Residential Density Matrix, which substantially reduces urban density when central water and sewer service are not provided. Potable Water Wellfields.-- In part, the Recommended Order adopted in the Hiss Final Order found: 242. The plan contains provisions conserving potable water and recharge areas. In the Public Facilities Element, for instance, Objective 3.1 is "[t]o establish a program of identifying and protecting existing and potential potable water supply sources." Policy 3.1.1 speaks of the adoption of a wellhead protection program by 1990, although this promise is nullified by the condition that the adoption of such a program is "subject to engineering studies and future deliberations and considerations." * * * Wellfields receive little direct protection in the plan. Objective 3.1 of the Public Facilities Element is "[t]o establish a program of identifying and protecting existing and potential potable water supply sources." As the language of this objective suggests, no such program exists, and the ensuing policies do little, if anything, in identifying implementation activities designed to achieve this objective. As already noted, Policy 3.1.1 states that the County will "ensure adequate protection for potable water supply systems," as well as recharge areas, "by initiating efforts to prepare and implement a wellhead protection program by 1990, subject to engineering studies and future deliberations and considerations." * * * Important protection of waterwells is derived from general provisions applicable to groundwater and potable water. Provisions governing groundwater have been discussed in connection with groundwater recharge. Provisions protecting potable water protect wellfields to the extent that groundwater provides potable water. For instance, Policy 5.3.2 of the Environment Element provides that the County shall implement water conservation measures. Measures to conserve water include the use of wastewater or stormwater runoff as a potable water source, as envisioned by Policies 2.1.4 and 2.1.5 of the Public Facilities Element. Likewise, Policy 1.2.6 promises that the County "will continue to explore ... water conservation strategies in cooperation with regional water supply authorities and other local entities." Water conservation measures will obviously protect wellfields by reducing demand and the possibility of overpumping. * * * 371. It is fairly debatable that the FLUM is consistent with criteria of the depiction of waterwells . . .. * * * It is fairly debatable that the plan is consistent with criteria of objectives and policies addressing the conservation of potable water, protection of natural groundwater recharge, and protection of waterwells. . . . . . .. With one exception, it is fairly debatable that the plan is consistent with criteria of policies addressing the protection of natural reservations and the designation of environmentally sensitive lands. To the exclusion of fair debate, the plan is not consistent with the latter two criteria as applied to the designation of the entire Walton Tract as Public Resource Lands, despite the intended use of part of the tract as a major landfill. * * * 385. It is fairly debatable that the plan is consistent with the criterion of an objective addressing the protection of water quality by the restriction of activities known to affect adversely the quality and quantity of identified water sources, including waterwells. The requisite protection is attained by policies protecting surface water and groundwater and conserving potable water, such as by investigating the use of treated wastewater effluent and stormwater runoff as potable water sources. * * * 387. It is fairly debatable that the plan is consistent with criteria of objectives to ensure the protection of waterwells . . .. In part, the Recommended Order adopted in the Hiss Final Order concluded: Based on the ultimate findings of fact contained in Paragraph 371, the plan is consistent with criteria of the depiction on the FLUM of waterwells . . .. There are no cones of influence that are required to be depicted on the FLUM because the Southwest Florida Water Management District has not identified any cones of influence in the County. According to Rule 9J-5.003(18), a "cone of influence" is "an area around one or more major waterwells the boundary of which is determined by the government agency having specific statutory authority to make such a determination based on groundwater travel or drawdown depth." * * * 91. Rule 9J-5.013(2)(c)1. requires that the plan contain "policies address[ing] implementation activities for the": 1. Protection of water quality by restriction of activities known to adversely affect the quality and quantity of identified water sources including existing cones of influence, water recharge areas, and waterwells[.] 92. Based on the ultimate findings of fact contained in Paragraphs 380 and 385-386, the plan is consistent with criteria of objectives addressing the conservation of potable water and protection of natural groundwater recharge areas and policies addressing implementation activities for the protection of water quality by restricting activities known to affect adversely sources of potable water. * * * 95. Based on the ultimate findings of fact contained in Paragraph 387, the plan is consistent with criteria of objectives to ensure the protection of waterwells . . .. The only pertinent thing RU-5 did with respect to potable waterwells was to amend Public Facilities Policy 3.1.1 to indicate that, whereas the 1989 plan stated that County was "initiating efforts to prepare and implement a wellhead protection program by 1990," by the time of RU-5, the plans were to "continu[e] efforts to immediately implement a wellhead protection program." The delay in implementation of the program was predicated on County staff's advice: The extension of the deadline . . . allows for the need to establish base line data and because of the extensive requirements for monitoring such a program. . . . In the face of this explanation, the intervenors did not prove that the extension of the deadline was not supported by the best available data and appropriate analysis. RU-5 also added Public Facilities Policy 3.1.2 Sarasota County will continue working in close cooperation with the Southwest Florida Water Management District and other professional regulatory agencies to develop and evaluate the feasibility of adopting a model wellhead protection ordinance for major public supply wells and well fields shown on the Future Land Use Map Series. This effort may include requests to the SWFWMD for cooperative funding or technical assistance to conduct an inventory and assessment of existing and potential public supply wells areas and conditions. and Public Facilities Policy 3.1.3 For existing and proposed public supply wells shown on the Future Land Use Map or Map Series, a zone of protection shall be delineated within which land use will be regulated to protect public water supply resources, consistent with the wellhead protection program. Where cones of influence have been delineated, the zone of protection shall be consistent therewith. Where cones of influence have not been determined, Sarasota County shall use its best available data to consider delineating interim protection zones of between 200 feet to 400 feet in radius, depending on variables including, but not limited to, soil characteristics and surrounding uses. When DCA found fault with the absence of an explicit time frame for implementation of the wellhead protection program in Public Facilities Policy 3.1.2, the County admitted, for purposes of effectuating a settlement, that Public Facilities Policy 3.1.2 was not in compliance for the reasons set forth in the settlement Stipulation between the Department and the County. The settlement Stipulation amends the first sentence of Public Facilities Policies 3.1.2 as follows: Sarasota County will continue working in close cooperation with the Southwest Flroida Water Management District and other professional regulatory agencies to develop a model wellhead protection ordinance, culminating in Sarasota County adopting a wellhead protection ordinance during fiscal year 1992 for major public supply wells and well fields shown on the Future Land Use Map Series. The Department agrees that this amendment would bring RU-5 into compliance. The balance of the intervenors' criticism of the potable waterwell protection amendments in RU-5 are foreclosed by the Hiss Final Order, as recited above. Wetlands Mitigation.-- In part, the Recommended Order adopted in the Hiss Final Order found: 266. The mitigation requirement applicable to Marshes, Sloughs, or Wet Prairies addresses the habitat function of these wetlands. However, this requirement does not address the critical drainage function of those wetlands altered because "no other reasonable alternative exists." The drainage function is especially pertinent to Marshes and Sloughs, which are contiguous wetlands. Additional findings concerning the treatment of wetlands are at Paragraph 315 below. [Fn. 17 omitted.] * * * 315. Ignoring alterations to wetlands causing the loss of drainage functions, the mitigation requirement fails even to ensure the protection of the habitat function of wetlands, whose loss triggers the obligation to mitigate. The mitigation provision leaves to the developer the task of monitoring the success of the artificial wetlands created to replace converted wetlands. Assuming that developer monitoring may suffice with County supervision, the plan supplies no standards by which to evaluate a mitigation project or sanctions by which to enforce a mitigation agreement. These short- comings undermine the protection afforded Swamps, Marshes, and Wet Prairies. Testimony established that many wetland-mitigation projects fail, largely due to the absence of performance standards and failure to monitor. The Hiss Final Order contains no conclusions of law regarding wetlands mitigation. However, for reasons not readily apparent from the Final Order, the Remedial Action 13 does address wetland mitigation by requiring the County to "amend the Freshwater Wetlands section 'Principles for Development Proposals in Native Habitats.'" In most respects, RU-5 follows the specified remedial action. In those respects, the intervenors are foreclosed from challenging RU-5's amendment to the "Principles for Evaluating Development Proposals in Native Habitats." In some respects, there are difference between the specified remedial action and RU-5. The Remedial Action in the Hiss Final Order requires that the "Principles for Development Proposals in Native Habitats," Section VI.A.2.e., be amended to read: All alterations in wetlands which result in a loss of wetlands shall be mitigated on at least a two-to-one basis for wooded wetlands. Mitigated wetlands shall restore the type, nature and function of the altered wetland. A wetland mitigation, maintenance, and monitoring plan based on best available technology shall be submitted for review and approval by the County prior to or concurrent with the preliminary plan or site and development plan development review process. The success of mitgation shall be monitored by the applicant or his designees and shall also be subject to monitoring and enforcement by the County. Except as otherwise authorized herein, wetlands shall not be filled, drained, dredged, or converted to lakes or borrow pits. Instead, RU-5 amends the "Principles for Evaluating Development Proposals in Native Habitats," Section VI.A.2.e., to read: All alterations in wetlands which result in a loss of habitat, shall be mitigated in accordance with performance standards adopted by the Board of County Commissioners. These performance standards shall ensure that the recreated wetlands provide values and functions equal to or, particularly in the case of an impacted or degraded wetland, greater than those of the wetland qualifying for alteration. Reasonable assurance shall be provided such that the recreated wetland will exhibit the defined environmental function, nature, and, where hydrologically feasible, similar type of the altered wetland. Mitigation ratios shall be as follows: One-to-one for herbaceous wetlands and two-to-one for wooded wetlands, in accordance with Level I performance standards; or Two-to-one for herbaceous wetlands and four-to-one for wooded wetlands in accordance with Level II performance standards. General Requirements for Level I and Level II Performance Standards: For all projects, a wetland mitigation, maintenance, and monitoring plan based on best available technology shall be submitted for review and approval by the County prior to or concurrent with the preliminary plan or site and development plan development review process. All federally listed threatened and endangered plant species shall be preserved, protected or relocated pursuant to a transplantation program to be implemented prior to construction authorization. The success of mitgation shall be monitored by the Applicant or his designees and shall also be subject to monitoring and enforcement by the County. Except as otherwise authorized herein, wetlands shall not be filled, drained, dredged, or converted to lakes or borrow pits. Specific performance standards shall be contained in the County's Land Development Regulations (Ord. 81-12, as amended). Criteria for Level I Performance Standards: Level I standards shall include the following: the diversity of plants in the wetlands to be impacted shall be approximated in the recreated wetland; the habitat value of the recreated wetland shall approximate or exceed that of the wetland to be impacted; similar substrate shall be provided in the recreated wetland; success criteria (e.g., plant survival, animal diversity, hydroperiods) shall be established based on the best availabale technology, and shall be met before monitoring can be completed; and a hydroperiod maintenance plan, acceptable to the County, shall be prepared. Mitigation at ratios as described in (1), above, and based on success criteria for Level I performance standards may be provided prior to the alteration of any wetland qualifying for alteration. Mitigation with Level I performance standards may be provided in a defined area that is part of an environmental system or corridor that can enhance wildlife values and functions. Off-site wetland mitigation shall be allowed only where on-site mitigation or preservation is not feasible, as determined by the County. Criteria for Level II Performance Standards: Level II standards shall include the following: recreated wetlands shall be planted with at least three different native species at specific distances between plants; mulching may be used in lieu of planting; a hydroperiod maintenance plan, acceptable to the County, shall be prepared; and monitoring of success shall be required for at least three years. The County has admitted, for purposes of effectuating a settlement, that Section VI.A.2.e. of the "Principles for Evaluating Development Proposals in Native Habitats" is not in compliance for the reasons set forth in the settlement Stipulation between the Department and the County. Under the settlement Stipulation, the County has agreed to revise Section VI.A.2.e. to specify that the "federally listed threatened and endangered plant species" to be preserved includes "those species that are listed or are C1 candidates for listing by the U.S. Fish and Wildlife Service; listed as threatened or endangered by the Florida Department of Agriculture and [C]onsumer [S]ervices pursuant to the Preservation of Native Flora Act, Section 581.185, Floirida Statutes; and listed by the Convention on International Trade in Endangered Species of Wild Fauna and Flora." There is no basis in the record for the intervenors contentions that RU-5, as amended by settlement Stipulation between the DCA and the County, is contrary to the required Remedial Action or inconsistent with the Growth Management Act. 9/
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Administration Commission enter a final order that: (1) Sarasota County's RU-5 amendments to its comprehensive plan are not in compliance, but only for the reasons set out in the settlement Stipulation between the County and the DCA; (2) that the RU-5 amendments are otherwise in compliance; and (3) that the County be required to take the remedial action agreed to in the settlement Stipulation. RECOMMENDED this 31 day of August, 1992, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31 day of August, 1992.
The Issue The issue to be determined in this case is whether the proposed amendment to the Pinellas Countywide Plan Map, changing the land use designations on 34.6 acres of land in Safety Harbor, Florida, should be approved.
Findings Of Fact The Parties Petitioner is the contract purchaser of 34.6 acres of land (“the Property”) located near the northeast corner of 10th Street South and McMullen-Booth Road in the City of Safety Harbor. Respondent is the Board of County Commissioners of Pinellas County, in their capacity as the CPA. The Proposed Amendment The Amendment would change the land use designations for nine parcels within the Property. The Amendment would make the following changes to the current land use designations: However, the parties’ dispute focuses on the 15.8-acre parcel that is now designated Industrial Limited (“IL”). The Amendment would change the designation of the parcel to Residential Medium (“RM”). Existing Land Uses on the Property and Surrounding Area Located on the 15.8-acre parcel (referred to hereafter as the “IL parcel” or “Richman parcel”) are numerous industrial buildings and structures associated with a citrus processing facility that is no longer in operation. There are no uses being made of the other eight parcels that comprise the Property. The balance of the Property is undeveloped and relatively undisturbed. There are wetlands as well as a creek on the Property. There is an extensive tree canopy in the undeveloped area. Access to the IL parcel is via 10th Street South (S.R. 590), which is a two-lane, undivided roadway on the southern boundary. There is no rail access to the IL parcel. To the north and east of the Property are relatively affluent neighborhoods of single-family residences on lands designated Residential Suburban and Residential Low. The residences on the north are separated from the IL parcel by the large undeveloped area, but the residences to the east are immediately adjacent to the IL parcel. McMullen-Booth Road, a six-lane arterial roadway, runs along the northwestern boundary of the Property. On the southwestern boundary, adjacent to the IL parcel, are lands designated Residential/Office/Retail where there is a drug store, car wash, and bank. Across 10th Street South, on the southeast corner of its intersection with McMullen-Booth Road, is a gas station/convenience store. Also across 10th Street South, opposite the entrance to the citrus processing facility, is land designated IL and used for warehousing, auto-repair, and other uses. The Scenic Non-Commercial Corridor McMullen-Booth Road has been designated by Pinellas County as a Scenic Non-Commercial Corridor (“SNCC”). The SNCC designation includes lands bordering both sides of McMullen-Booth Road. The SNCC designation identifies preferred land uses within the corridor to achieve the CPA’s goal to preserve and enhance the scenic qualities of the corridor. The western half of the IL parcel is within the McMullen-Booth Road SNCC. Under the SNCC policies, the preferred land use for the western half of the parcel is “Mixed Use.” The Amendment would allow for land uses consistent with the SNCC. The Development Agreement The proposed Amendment is accompanied by a Development Agreement between Richman and the City of Safety Harbor which provides more specifically for how the Property would be developed. Among other items, the Development Agreement provides for: 246 apartment units in three-story and four-story buildings; a 25,000-square-foot office building fronting on McMullen-Booth Road; a 182-foot buffer between the nearest apartment unit and the residences to the east; a requirement that no three-story building will be located within 450 feet of the eastern property line; and the preservation of more than 10 acres of the undeveloped area, including the creek and wetlands. Action on the Proposed Amendment Changing a land use designation in the City of Safety Harbor requires an amendment to the Countywide Plan Map, which depicts all land use designations in Pinellas County and its municipalities. Countywide Rules are used in conjunction with the Countywide Plan and they address amendments to the Countywide Plan Map. The Countywide Plan and Countywide Rules are created and administered by the CPA. Proposed amendments to the Countywide Plan Map are reviewed by the Pinellas County Planning Advisory Committee (“PAC”), which is comprised of planners from most of the local governments in Pinellas County. The PAC makes a recommendation to the Pinellas Planning Council on a proposed amendment. The PAC recommended approval of the Amendment. The staff of the Pinellas Planning Council prepared an “Agenda Memorandum,” which included the following findings which are supported by the preponderance of the evidence presented in this case and, therefore, are findings of fact in this Recommended Order: The RM land use is well-suited to serve as a transition from non-residential areas to the west and south and the residential neighborhoods to the east and north. The area is not part of a larger consolidated industrial area, but the Richman parcel, together with the IL parcel across 10th Street South, could function as a small industrial park. The IL category, with all potential uses allowed, is “in the broadest sense” inconsistent with single-family uses to the north and east. The IL parcel can accommodate certain “target employers.” At the final hearing, target employers were identified as “office light industrial and research and development.” The environmentally sensitive areas on the Property and adjacent to single-family residences limit the types of industrial uses that could be located on the IL parcel. The Amendment does not foreclose the opportunity to attract target employers to other parcels within the Property. “On balance,” the Amendment is consistent with the Countywide Rules. The Council staff recommended approval of the Amendment. As partial mitigation for the loss of the IL land use, the staff recommended that Richman work with the County to attract target employers to other parcels within the Property. The Council held a public hearing and voted to recommend approval of the Amendment. The Pinellas County planning staff recommended approval of the Amendment to the CPA. The CPA, at a public hearing, voted to deny the Amendment, based primarily on concern over the loss of industrial lands. Relevant Criteria Section 5.5.3.1 of the Countywide Rules states: In the consideration of a regular Countywide Plan Map amendment, it is the objective of these Countywide Rules to evaluate the amendment so as to make a balanced legislative determination based on the following six (6) Relevant Countywide Considerations, as they pertain to the overall purpose and integrity of the Countywide Plan. Of these six criteria, the parties stipulated that only the consideration stated in Section 5.5.3.1.1 is at issue in this case. That section states: Consistency with Countywide Rules. The manner in, and extent to, which the amendment is consistent with Article 4, Plan Criteria and Standards of these Countywide Rules and with the Countywide Plan as implemented through the Countywide Rules. The parties disputed what criteria are “implemented through the Countywide Rules.” Richman contends that to be implemented through the Countywide Rules, a policy must be contained in the Countywide Rules. The CPA contends that there are provisions of the Plan that must be considered even if they do not also appear in the Rules. As set forth in the Conclusions of Law, in order for a provision of the Countywide Plan to be implemented through the Countywide Rules so that the provision can act as a criterion applied by the CPA in the approval or denial of a proposed amendment to the Countywide Plan Map, the provision must be repeated, paraphrased, or adopted by reference in the Countywide Rules. In this regard it is noted that Resolution 06-3 of the Pinellas Planning Council, which discusses the need to reserve industrial parcels for target employers, was referred to in the Council's Agenda Memorandum and discussed in the public hearing before the CPA. However, Resolution 06-3 is not implemented through the Countywide Rules and, therefore, is not a source of criteria applicable to the Amendment. The SNCC designation for McMullen-Booth Road is in the Countywide Rules and, therefore, must be considered by the CPA in its review of the Amendment. Section 2.3.3.6.1 of the Countywide Rules is relevant to the issues raised and states in part: Category/Symbol – Industrial Limited (IL) Purpose – It is the purpose of this category to depict those areas of the county that are now developed, or appropriate to be developed, in a limited industrial manner; and so as to encourage the reservation and use of consolidated areas for industrial and industrial/mixed use in a manner and location consistent with surrounding use, transportation facilities, and natural resource characteristics. In addition to this statement of purpose, the section addresses locational characteristics, traffic generation characteristics, density/intensity characteristics, density/intensity standards, and “other standards.” Section 2.3.3.6.1 identifies the “primary uses” allowed in the IL land use category as office, research/development, light manufacturing/assembly, wholesale/distribution, and storage/warehouse. The “secondary” uses allowed are residential, retail/commercial; personal service/office support, commercial/business service, commercial recreation, temporary lodging, institutional, transportation/utility, recreation/open space, transfer/recycling, incinerator facility, and agricultural. The CPA’s desire for certain target employers to use the IL parcel fails to account for the fact that there are industrial uses of the site that are allowed under the IL land use category in the Countywide Plan that would cause noise, odor, truck traffic, or other conditions that are incompatible with adjacent residential uses. Understandably, the CPA would like to see the Richman parcel used in the future by one of the target employers, but the CPA does not acknowledge that the IL designation authorizes other uses that would be incompatible with surrounding uses. At the final hearing, the County’s Director of Economic Development testified that the Richman parcel is “perfect” for an IL land use, but that testimony only makes sense in the context of certain target employers. In the context of all the IL uses that are allowable under the Countywide Plan and Countywide Rules, the site is imperfect and impracticable because of the proximity of single-family homes and the access from an undivided, two-lane street used by residential traffic. Several years of marketing efforts by Richman and the County have not generated a single offer to purchase or lease the Richman parcel for any of the allowed IL uses, including target employers. Following the CPA’s denial of the Amendment, the staff of the Pinellas Planning Council undertook a review of its current policies regarding the preservation of industrial lands and recommended amending the Countywide Rules to identify industrial properties “worthy of preserving” and to develop criteria for the evaluation of proposed amendments to convert industrial land. These recommendations highlight the current lack of adequate guidance in the Countywide Rules. The determination by the CPA that the Amendment is inconsistent with the Countywide Rules is based primarily on three propositions which are contrary to the preponderance of the evidence. First, that the Richman parcel is being reserved for IL uses. The preponderance of the evidence shows that the parcel is inappropriate for several authorized IL uses and the CPA wants the parcel reserved only for a few target employers. Second, that the IL designation is not inconsistent with the McMullen-Booth Road SNCC. The identification of preferred land uses in the corridor would have no effect unless it was a factor to be considered by the CPA when it reviews proposed amendments to the Countywide Plan Map. The IL designation within the McMullen-Booth SNCC is inconsistent with the goal of the corridor and is a factor (not a requirement) in favor of changing current IL designation to another designation that qualifies as Mixed Use. Third, that the Richman parcel is part of a “consolidated area” for industrial uses in a location “consistent with surrounding uses” as described in Section 2.3.3.6.1. The preponderance of the evidence shows that this is not a consolidated area for industrial uses. It was once a consolidated area, but past land use decisions have eliminated more than half the industrial acreage. If Richman had proposed to consolidate its parcel with the IL parcel south of 10th Street South to create a large, integrated warehousing and distribution operation served by rail, the proposal would have been consistent with the core purpose for IL lands as expressed in Section 2.3.3.6.1. The impracticability of such a proposal, however, highlights the problem with the current IL designation for the Richman parcel. The County’s 2008 Target Employment and Industrial Land Study found that two-thirds of the “target industries” operating in Pinellas County are on lands not designated industrial, because these uses can often be accommodated on lands designated for office uses. The 2008 study recommended that the industrial designations of lands in five “prime industrial areas” be preserved. Richman’s IL parcel is not in one of these prime industrial areas. When all relevant factors are considered, the CPA appears to be taking a stand for preservation of industrial lands in the wrong place.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Countywide Planning Authority issue a Final Order approving the Amendment. DONE AND ENTERED this 18th day of November, 2013, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of November, 2013. COPIES FURNISHED: Scott A. McLaren, Esquire Edward D. Armstrong, III, Esquire Hill, Ward and Henderson, P.A. 3700 Bank of America Plaza 101 East Kennedy Boulevard Tampa, Florida 33602 Gordon Beardslee, General Planning Administrator Pinellas County Department of Strategic Planning and Initiatives 310 Court Street Clearwater, Florida 33756 Michael Crawford, Executive Director Pinellas Planning Council 310 Court Street, Second Floor Clearwater, Florida 33756-5137 Kenneth Welch, Commission Chairman Board of County Commissioners Pinellas County 315 Court Street Clearwater, Florida 33756 Nancy S. Meyer, Esquire David S. Sadowsky, Esquire Pinellas County Attorney's Office 315 Court Street, Sixth Floor Clearwater, Florida 33756
The Issue Whether the Plan Amendments to the St. Johns County Comprehensive Plan, adopted by Ordinance Number 2001-18, are "in compliance" as defined in Chapter 163, Part II, Florida Statutes, or are not "in compliance" as alleged in the petitions of The Sierra Club (Sierra) and Ellen A. Whitmer (Whitmer).
Findings Of Fact The Parties The Sierra Club. Sierra alleged in its Petition that it "does business in St. Johns County and has a substantial number of members who reside in and own property in St. Johns County." Sierra is registered as a California corporation and maintains offices in St. Petersburg and West Palm Beach, Florida. The National Organization of Sierra publishes Sierra Magazine, which members receive in the County. Sierra's basic mission is to provide an opportunity for its members to explore, enjoy, and protect the outdoors and natural systems, including those which exist in the County. The Florida Chapter of The Sierra Club (Florida Chapter) is subdivided into 10-12 "groups," including the approximately 1,400-member Northeast Florida Group, serving Duval, St. Johns, and Clay Counties, with approximately 325 members living in St. Johns County. There are approximately 24,000 Sierra members in the State of Florida. Sierra holds monthly meetings in the County. Speakers discuss various educational subjects with members attending the monthly meetings. Sierra members hike in the County, and canoe and kayak on, for example, the Tolomato and Guana Rivers. These activities can be expected to be enhanced if the Plan Amendments are approved and the approximately 1,630-acre preserve area dedicated as planned. Sierra has held fundraisers in the County for the benefit of the three-county Northeast Group. The Northeast Florida Group sends out monthly newsletters, published in and mailed from Duval County, and publishes the Sierra Sentry: Standing Watch on Northeast Florida. Sierra does not maintain a business address or bank account in the County; nor does Sierra own or lease real property, offices or buildings in the County. The Plan Amendments are not reasonably expected to constrain, inhibit, or prevent activities of Sierra's members, including their educational and permitting activities, although a Sierra member testified that the Plan Amendments would potentially "be adverse to [Sierra's] mission in terms of experiencing outdoors and the wildlife associated with the outdoors " Sierra submitted timely oral and written comments to the St. Johns County Commission between the time the County transmitted the Plan Amendment for review and the time the County adopted the Plan Amendment. Sierra made a presentation at the public hearing related to the Plan Amendments. Ellen A. Whitmer. Whitmer resides and owns property within the County and submitted timely oral and written comments to the County regarding the Plan Amendments. The parties agreed Whitmer has standing. Intervenors. SONOC owns the property which is the subject of the future land use map (FLUM) Plan Amendment being challenged in these proceedings. SONOC submitted oral and/or written comments to the County regarding the Plan Amendments. SONOC has expended approximately $3.5 million in the approval process. The PARC Group is the agent of SONOC, and is the applicant/developer of the Nocatee development, which is the subject of the Plan Amendments. The PARC Group submitted oral and/or written comments to the County regarding the Plan Amendments. St. Johns County. The County is a political subdivision of the State of Florida. Pursuant to Section 163.3191, Florida Statutes, the County prepared an evaluation and appraisal of the Plan and an Evaluation and Appraisal Report (the "EAR") in January 1998. The EAR process allows local government to periodically assess the success or failure of their comprehensive plan. The EAR is subjected to a sufficiency review by the Department. In May 2000, the County adopted the EAR-Based Comprehensive Plan Amendment (EAR-Based Plan Amendment), with supporting data and analysis, which the Department found to be "in compliance." This included the data and analysis for the future land use element (FLUE), which was adopted as part of the Plan. (Joint Exhibit 7-A). This is part of the data and analysis used to support the Plan Amendments at issue in this proceeding. The Department's "in compliance" review became final agency action without challenge. St. Johns County is located in the northeast portion of the State of Florida, south of Duval County and Jacksonville. The St. Johns River separates the County from Clay and Putnam Counties to the west. Flagler County borders the County to the south. There are three (3) incorporated municipalities located within the County, i.e., St. Augustine, St. Augustine Beach, and the Town of Hastings. The County comprises approximately 423,580 acres. St. Augustine is the largest municipality in the County. Agriculture and silviculture are the leading industries in the County. The County has a large portion of silviculture lands and there are more than 2.5 million acres in Northeast Florida. The intensive agriculture areas of the County are located in the southern part of the County. The Plan Amendments will not adversely affect the economic viability of agriculture or silviculture in the County. A barrier island runs the length of the County, from the Flagler County line to Duval County. Interstate 95 runs north and south through the County and is west of St. Augustine. U.S. Highway 1 also runs north and south and east of Interstate 95 and runs parallel to Interstate 95. The Tolomato and Matanzas Rivers form the majority of the Intercoastal Waterway on the eastern portion of the County and separate the barrier island from the mainland portion of the County. The Guana River State Park and Guana River State Wildlife Management Area form a significant part of the barrier island adjacent to the Tolomato River. The Department. As the state land planning agency, the Department reviewed the Plan Amendments and timely filed a Notice of Intent to find the Plan Amendments "in compliance." The Challenges While Petitioners cite to numerous statutory and rule provisions in their petitions, the principle allegations, that the Plan Amendments are not "in compliance," may be placed into three general categories: "need" and urban sprawl; natural resource protection; and economic feasibility. Under each of these general subject headings, Petitioners raise allegations that the Plan Amendments are inconsistent with Rule 9J-5, Florida Administrative Code, and Chapters 163 and 187, Florida Statutes, and that they are internally inconsistent with the St. Johns County Comprehensive Plan. The Nocatee Plan Amendments On February 23, 2001, the County amended its Comprehensive Plan by Ordinance No. 2001-18. The Ordinance contains four changes to the Plan. First, the Ordinance creates a new FLUE category known as "New Town Development" (Text Amendment). Second, the Ordinance changes the FLUM designation of approximately 11,332 acres of land from Rural/Silviculture to New Town (Map Amendment). Third, the Ordinance changes the FLUM designation for approximately 1,630 acres of land from Rural/Silviculture to Conservation (Preserve Amendment). (Petitioners are not challenging the designation of the Nocatee Preserve as "Conservation.") Fourth, the Ordinance adds text (Policy H.1.6.6) to the Plan authorizing the Nocatee DRI "to utilize the standards and guidelines set forth in [Section 163.3180(12), Florida Statutes] to satisfy the County's transportation concurrency requirements by payment of a proportionate share contribution is [sic] as stated in the Nocatee [DRI] Order, Special Condition 25, entitled Transportation Resource Impacts." (This latter provision allows the use of "pipelining" and is referred to herein as the Transportation Amendment.) These Plan Amendments are related to a proposed development known as "Nocatee." The New Town category was crafted to provide criteria and guidelines for large projects such as Nocatee. The acreage designated New Town by the Map Amendment is the proposed site of the Nocatee development. The acreage designated Conservation by the Preserve Amendment is for the purpose of establishing the "Nocatee Preserve." The Nocatee development will utilize the Transportation Amendment to address anticipated development impacts on the roadway system. These amendments and the Nocatee development are discussed in more detail below. Ordinance No. 2001-18 provides that "[t]he data and analysis supporting [these Plan Amendments] includes, but is not limited to, the Nocatee Application for Development Approval, Sufficiency Responses, and Nocatee Development of Regional Impact Development Order adopted concurrently with this Ordinance, application materials submitted by the Applicant and reports generated by the County Growth Management Department." Pursuant to Section 380.06, Florida Statutes, and Rule 9J-2, Florida Administrative Code, projects which must undergo Development of Regional Impact (DRI) review are subject to a multi-agency, multi-issue review of the proposed development's impacts and a process for mitigating those impacts. A DRI is a development order issued by a local government. It pertains to approval for a specific type of development for a particular site. A comprehensive plan is a different type of document, which considers long-term planning for an entire jurisdiction, taking into account the cumulative effect of many developments, including consideration of projected supply and demand in the future. DRIs are subject to the requirements of Chapter 380, Florida Statutes. One of the requirements for a DRI is that it be consistent with the requirements of the local government's comprehensive plan, a determination that is separate from that undertaken here. On the other hand, comprehensive plans and amendments, as here, must comply with Section 163.3184(1)(b), Florida Statutes, which defines "in compliance" as being consistent with Sections 163.3177, 163.3178, and 163.3191, Florida Statutes, the state comprehensive plan, regional policy plan, and Chapter 9J-5, Florida Administrative Code. A plan amendment does not have to be consistent with Chapter 380, Florida Statutes, to be "in compliance." A DRI development order does not guarantee that the site will be developed or developed as approved. For example, the development order may be amended through the substantial deviation process, or a development order may expire. Applications for DRI approval are prepared and submitted to the appropriate regional planning council by the developer. These applications are submitted in response to a set of criteria that differ from those applicable to a plan or plan amendment. Some of the information provided by a developer in support of a DRI request may be relevant to the review of a plan amendment, as here. However, a DRI development order, in general, and the Nocatee DRI Development Order specifically, are not subject to an "in compliance" review in this administrative proceeding conducted pursuant to Section 163.3184(1)(b), Florida Statutes. At the conclusion of the DRI process, if project approval is attained, the local government issues a development order. Section 380.06(15), Florida Statutes. The development order must include, among numerous other information, a detailed listing of each land use by acreage and magnitude. Rule 9J-2.025(3)(b)(5), Florida Administrative Code. This land use information from the DRI development order is incorporated into the County Plan for any approved New Town. See Finding of Fact 33. In this case, the Nocatee DRI Application for Development Approval (ADA) was reviewed by the Northeast Florida Regional Planning Council as required by Section 380.06, Florida Statutes, (and by other agencies), and the Council recommended that the ADA be approved, with conditions. It was stipulated that "[i]n considering comprehensive plan amendments, there is no requirement that favorable consideration be provided to a proposed amendment solely because it is a DRI." See generally Section 163.3187, Florida Statutes. The Nocatee DRI "is a proposed mixed use development on approximately 13,323 acres, of which approximately 11,332 acres are located in northeastern St. Johns County . . . and approximately 1,991 acres are located in southeastern Jacksonville, Florida." On February 22 and 23, 2001, concurrent with its consideration of the Plan Amendments, the St. Johns County Board of County Commissioners considered the merits of the Nocatee DRI ADA and approved same through Resolution No. 2001- 30. Accordingly, while Ordinance No. 2001-18, adopting the Plan Amendments, expressly relies on, in part, the data and analysis in the Nocatee DRI ADA and related documents, including the Nocatee DRI Development Order, and Policy A.1.19.15 expressly refers to the Nocatee DRI and incorporates the "allowable uses and mix of uses within the Nocatee" DRI,1 the Nocatee DRI is not subject to "in compliance" review in this administrative proceeding. See 1000 Friends of Florida and Robert Jenks v. City of Daytona Beach and Department of Community Affairs, et al., 16 F.A.L.R. 2428 (DCA June 16, 1994). See also Pinecrest Lakes, Inc. v. Shidel, 795 So. 2d 191 (Fla. 4th DCA 2001)(discussing the scope of Section 163.3215, Florida Statutes). The Text Amendment The Text Amendment adds Objective A.1.19, "New Town Development," to the Plan, which is a new future land use category. The purpose of this new land use category is described as follows: The New Town Future Land Use category shall guide development into a series of clearly identified and distinct villages that together form a larger New Town. Within the New Town there is a clear hierarchy of development types utilizing neighborhoods as the basic development unit. Several neighborhoods and one or two village centers combine to form a village, and several villages form a New Town. A central village functions as the Town Center Village, and includes the main employment[,] shopping, and cultural activities for the New Town. Villages shall have central focal points of higher densities and intensities that create an identity and a sense of place. The planned mix of uses of New Towns shall help to provide a positive fiscal impact for the County. New Towns shall offer a wide range of housing choices, including affordable housing. The New Town Future Land Use category may be requested for any Development of Regional Impact that meets the policies set forth herein. The Board of County Commissioners may approve or deny any New Town on a project-by-project basis, after the New Town review. The Text Amendment is proposed to be included in the County's Plan as FLUE Objective A.1.19 – which is quoted in full immediately above – and fifteen (15) implementing policies (Policies A.1.19.1 through A.1.19.15). Unlike many of the other land use categories in the Plan, which are defined only by the statutorily-required minimum list of allowable uses and standards, the New Town land use category contains detail on a wide spectrum of issues ranging from fiscal impact analysis, affordable housing, to the "[i]nterconnectivity of pedestrian and vehicular routes through the [New] Town to encourage multi-modal circulation." The detail contained in the Text Amendment is necessary to ensure that a specific form of development occurs on land bearing the New Town future land use designation. The land use pattern of this category is a tool to combat urban sprawl, as further explained below, and was crafted with guidance from the following Rule definition. "New town" means a new urban activity center and community designated on the future land use map and located within a rural area or at the rural-urban fringe, clearly functionally distinct from existing urban areas and other new towns. A new town shall be of sufficient size, population and land use composition to support a variety of economic and social activities consistent with an urban designation. New towns shall include basic economic activities; all major land use categories, with the possible exception of agricultural and industrial; and a centrally provided full range of public facilities and services. A new town shall be based on a master development plan, and shall be bordered by land use designations which provide a clear distinction between the new town and surrounding land uses. Rule 9J-5.003(80), Florida Administrative Code. The New Town category in the Text Amendment is consistent with and furthers the concept embodied in this definition, i.e., the creation of an efficient urban level of mixed-use development in a rural area. The Text Amendment sets 2,500 acres as the minimum size for any parcel to be eligible for designation as a New Town. The Text Amendment then establishes general land use standards applicable to the overall New Town parcel, which are embellished by more specific controls for the different components of the New Town. "At least 35% of lands within a New Town development shall be reserved for Open Space/Conservation and shall preserve a connected system of environmentally sensitive and passive recreation areas that will form a greenway system," and shall be provided for public uses. "The greenway system will serve the additional goal of surrounding and defining villages and the Town Center Village." ("Greenways, wetlands, and similar natural areas are open space/conservation. Open space/conservation does not include parks, golf courses, and other designated recreational lands.") At least 40 percent of the net developable acreage of a New Town must be residential units and, of the total residential units, at least 20 percent must be multi-family, and at least 50 percent must be residential single-family. Workplace land uses, i.e., retail, service, office, and industrial, must comprise at least five percent of the net developable acreage. This proportion of mix of uses is further refined in Policy A.1.19.9, where square footage requirements for each of the non-residential land uses are linked to the number of approved dwelling units, e.g., a minimum of 50 square feet of retail space for each dwelling unit and 30 square feet of civic space per dwelling unit in a Town Center Village and five square feet per dwelling unit for each Village. Other "specific use standards" are provided. New Towns are also required to provide land for libraries, fire stations, local government annexes, school sites and similar public uses and shall provide minimum park acreage equivalent to Comprehensive Plan LOS [level of service] requirements. In addition to this overall guidance, the Text Amendment directs a specific community form by assembling the several mixed uses into components which together will form the New Town. The "neighborhood" is designed to be the "basic development unit" within the New Town. Neighborhoods are to be compact residential areas with a mix of housing types. "Several neighborhoods and one or two village centers combine to form a village, and several villages form a New Town." Village Centers are areas designed to provide civic, service, limited retail, and elementary school uses for the surrounding neighborhoods. "A village shall contain distinct neighborhoods that will each have a central neighborhood park, which shall be called the neighborhood commons." At least 10 percent of each village must be retained in open space/conservation areas. While residential uses (at least 10 percent of net developable acreage) are also allowed in village centers, at least 45 percent of net developable acreage of the uses must be non-residential. Villages composed of these centers and neighborhoods are to be surrounded by greenways, golf courses, and natural features, and linked to the remainder of the New Town through interconnected roads and a pedestrian/bikeway system. Also, within villages, low density residential must have an overall net residential density between 1-2 units per acre. Medium density residential development must have an overall net density between 2-6 units per acre. Traditional neighborhoods must have an overall net density of 4-6 units per acre. In addition to the villages, each New Town is to contain a "Town Center Village," which "is intended to serve as the cultural, shopping, employment and civic center for the New Town, and shall include office uses, light industrial areas, and higher density residential uses surrounding a mixed-use core." In addition to some single-family residential and retail, the Town Center Village must contain at least 30 percent multi-family residential (percentage of units) and 45 percent (percentage of square feet) office use in order that "[t]he mixed-core shall have the characteristics of a downtown." The most intense of these uses are to be concentrated in the "Town Center Village Mixed-Use Core," which is to be the "pedestrian-oriented 'Main Street' area of retail, service, office, residential, and civic uses." Both the Town Center Village and its Mixed-Use Core are governed by specific design standards addressing matters such as sidewalks, signs, porches, and on-street parking. Overall, the Objective and Policies contained in the New Town land use category provide meaningful and predictable detail.2 The specific Policies describe the types and uses and how these uses will relate to one another, the mix of uses, transportation issues, interconnectivity, design, and urban features of New Towns. The Map Amendment In the same Ordinance in which the Text Amendment was adopted, the County adopted a Map Amendment changing the FLUM designation of approximately 11,332 acres from Rural/Silviculture to New Town. The Map Amendment was adopted to allow development of a project known as "Nocatee." As required by the Text Amendment, Nocatee has been designated as a New Town on the FLUM, and has been reviewed and approved as a DRI. The "allowable uses and mix of uses" within the Nocatee DRI Development Order have been incorporated into the County Plan Amendments. The Nocatee project includes approximately 11,332 New Town acres in St. Johns County. ("The Nocatee site consists of approximately 15,000 acres, with approximately 2200 acres in Jacksonville and the remainder in St. Johns County. The site is generally bounded on the west by [U.S.] 1, on the east by the Intercoastal Waterway, on the south by Pine Island Road, and extends north of CR 210 approximately 1.5 miles.") However, the portion of Nocatee in the southern portion of Duval County (Jacksonville) is not subject to the instant challenges. The land uses adopted in the Nocatee DRI Development Order and incorporated into the St. Johns County Plan are as follows: 2,872,000 square feet, 336 acres of office uses; 968,000 square feet, 150 acres and 3,900 parking spaces for retail commercial uses; 250,000 square feet, 29 acres and 500 parking spaces for light industrial uses; 12,579 total dwelling units, comprising 8,811 single family units, 3,228 multi-family units (including single-family attached units), and 540 assisted living units; 54 golf course holes, 485 hotel rooms, 5,531 acres of recreation/open space (including, but not limited to, parks, the Greenway, and golf courses), churches, schools, and civic uses. The uses described above are to be developed in five phases, each anticipated to last five years, with various combinations of uses allowed in each phase. Individual phases may be extended pursuant to Section 380.06(19), Florida Statutes, or accelerated provided that all mitigation requirements have been satisfied for the particular phase to be accelerated. The Nocatee DRI includes a Town Center Village, a secondary town center, seven other villages, and up to two village centers in each village. Village centers may include limited intensity office and retail commercial uses and an elementary school. However, "[t]he specific location of all land uses will be determined through the [Planned Unit Development] PUD approval process." The Nocatee DRI Development Order contains a "conversion table" which authorizes the conversion, at a defined rate, of one type of land use to another, but prohibits the conversion of non-residential land uses to residential uses during the first two phases of development. The conversion tables cannot be used to convert the Nocatee DRI land uses below those established in the New Town land use category. The Preserve Amendment Along with the Text and Map Amendments, the County adopted the Preserve Amendment, which re-designated approximately 1,630 acres of land from Rural/Silviculture to Conservation for purposes of establishing the "Nocatee Preserve." The Nocatee Preserve is an area of over 2500 acres including close to 1800 acres of land above the mean high water line. This strategic location with over 3 miles of frontage on the Tolomato River complements the Guana State Park and the Guana Wildlife Management area directly east of the river. The Nocatee Preserve will expand preserved environmental lands to both sides of the Tolomato River. This expansion of environmental lands will provide additional protection for the northern Tolomato River Basin and will provide passive recreation opportunities for both the Nocatee community and the entire region. Additionally, the Preserve will serve as a buffer between the Tolomato River and future development within Nocatee–a buffer that is between 1 and 1 1/2 mile wide. The Preserve includes the most ecologically significant (and economically valuable) part of the [Nocatee] property. Transportation Amendment The last change to the County Plan (Policy H.1.6.6) here at issue, the Transportation Amendment, provides: The Nocatee Development of Regional Impact, a multi-use development meeting the criteria of Chapter 163.3180(12), Florida Statutes, is authorized by the County to utilize the standards and guidelines set forth in the Statute to satisfy the County's transportation concurrency requirements by payments of a proportionate share contribution is [sic] as stated in the Nocatee Development of Regional Impact Development Order, Special Condition 25, entitled Transportation Resource Impacts. Pursuant to operation of the Transportation Amendment, Nocatee "will contribute up to $99,741,366 in cash payments and funded transportation improvements to offset the impacts of the Nocatee development upon the regional transportation system " Agency Review and Notice The Department is the state land planning agency and has the authority to administer and enforce the Local Government Planning and Land Development Regulation Act (Act), Chapter 163, Part II, Florida Statutes. Among the responsibilities of the Department under the Act is the duty to review plan amendments and determine if the plan amendments are in compliance with the Act. On or about June 1, 2000, the Department received the County's proposed Plan Amendments, and copies were distributed to various state, regional, and local agencies for their review and comments. On August 10, 2000, the Department submitted its Objections, Recommendations and Comments (ORC) Report issued pursuant to Rule 9J-11.010, Florida Administrative Code. Comments from the Department of Environmental Protection and the St. Johns River Water Management District were attached to the ORC. On or about January 22, 2001, the Applicant, The PARC Group, submitted its response to the Department's ORC. On February 22 and 23, 2001, the St. Johns County Board of County Commissioners held noticed hearings on the Nocatee DRI and related Comprehensive Plan Amendments and enacted Ordinance No. 2001-18 (Comprehensive Plan Amendment 01-01D), adopting changes to the Comprehensive Plan and Future Land Use Map, and also enacted Ordinance No. 2001-30, approving the Nocatee DRI. On March 5, 2001, the County furnished the Department with a submission package including documents relating to the Plan Amendments. On April 18, 2001, the Department caused to be published its Notice of Intent to find the Text Amendment, Map Amendment, Preserve Amendment, and Transportation Amendment "in compliance" pursuant to Sections 163.3184, 163.3187, and 163.3189, Florida Statutes. Need and Urban Sprawl The nomenclature "New Town," adopted as the title of the Text Amendment, is a reference to a form of land use described in Rule 9J-5, Florida Administrative Code. By definition, a "New Town" means, in part, "a new urban activity center and community designated on the future land use map and located within a rural area or at the rural-urban fringe, clearly functionally distinct or geographically separated from existing urban areas and other new towns." In addition, a "New Town" will necessarily contain a full range of uses in order to support a variety of economic and social activities "consistent with an urban area designation." See Rule 9J- 5.003(80), Florida Administrative Code. The new town land use generally described in Rule 9J-5.003(80), is a category expressly designed to combat urban sprawl. Rule 9J-5.006(5)(l), Florida Administrative Code, recognizes new towns as one of the "innovative and flexible" manners in which comprehensive plans may discourage the proliferation of urban sprawl. The weight of the evidence demonstrated that the New Town development form contained in the Text Amendment will discourage urban sprawl. For example, Dr. Downs and Mr. Porter, both of whom are national growth management experts with decades of experience, testified that new towns in general, and specifically, the Text Amendment adopted by the County, serve to discourage urban sprawl. Mr. Pennock, the primary author of the urban sprawl rule, which is now a part of Rule 9J-5, Florida Administrative Code, testified that the types and mix of uses in the Text Amendment are appropriate for a new town and will serve to discourage urban sprawl. The designated Nocatee New Town is located on the St. Johns County/Duval County line in the Northeast Planning District, and lies east of U.S. Highway 1, and straddles County Road 210. The Nocatee New Town lies in the rural/urban fringe, within the fastest growing sector of the County, in the regional growth corridor emanating from southeast Duval County and Ponte Vedra. This is an advantageous location because it is close enough to the main employment center in the area (Jacksonville), to afford residents employment opportunities. Additionally, the Nocatee New Town is a master-planned community, unlike piecemeal fragmented development which has occurred in other parts of the County. Consistent with the Text and Map Amendments, the Nocatee New Town is planned to include preserved natural areas and greenways and villages. Each village is expected to consist of neighborhoods and a village center, which will include elementary schools, civic and retail uses, and higher density housing. The Nocatee New Town serves as a cultural center, providing for a mix of higher density residential, retail, restaurant, hotel, office, and light industrial, schools, churches, a fire station, a library, a county annex, a police complex, parks and public spaces, and as athletic complex. The Nocatee New Town is geographically separated from existing areas by U.S. Highway 1 and preserved greenways, and is a functionally distinct land use. The Nocatee New Town is functionally similar in size and land use composition to other successful new towns, and includes basic economic activities in all major land use categories. Further, the Nocatee New Town is innovative planning, especially for a rapidly urbanizing county like St. Johns. In addition, it provides for flexibility in land use mixes by designating minimum land use percentages, but not requiring fixed percentages. This flexibility is desirable to allow for market adaptation over the 25-year build-out period. The expert testimony at the final hearing was persuasive that the location chosen for the Map Amendment is appropriate for a New Town in the County. Just a short distance to the north of the Map Amendment is Jacksonville, which was accurately described as "the major economic engine for the northeast Florida area . . . ." The past two decades of economic success for Jacksonville have resulted in growth along a corridor to the southeast, i.e., directly toward the site of the Map Amendment and the proposed Nocatee New Town. From 1991 to 1996, approximately 42 percent of the growth in St. Johns County occurred in the area around the proposed Nocatee New Town. The Nocatee New Town can be expected to improve the current, incremental and piecemeal development patterns of the County. Unfortunately, the emerging development pattern in the northeast area of the County exhibits indicators of sprawl. Currently, growth is not occurring in the most compact fashion. Sprawl is often viewed as a single-use or low- density residential setting. Here, the New Town concept offers a mixture of uses and the Plan Amendments, in particular, require an overall residential density range of three to eight units per net developable residential acre, whereas most of the residential areas of the County appear to have two residential unit per acre, and the proposed density for Nocatee is higher than the existing average in the northeast portion of the County. If Nocatee is developed according to its approved plan, it will be a New Town and will be a useful tool to fight this undesirable land use pattern of current development and is an anti-urban sprawl alternative to the existing sprawl development in the County. Petitioners maintain that the Text Amendment will allow, and the Map Amendment will promote, urban sprawl for essentially two reasons; first, there is no "need" for a new land use approval; second, there are insufficient guarantees that Nocatee or any future approval will actually develop as a New Town. The "need" question is founded in Section 163.3177(6)(a), Florida Statutes, which requires that "[t]he future land use plan shall be based upon surveys, studies, and data regarding the area, including the amount of land required to accommodate anticipated growth [and] the projected population of the area . . . ." This requirement is repeated in the statute's implementing rule, i.e., Rule 9J-5.005(2)(e), Florida Administrative Code ("The comprehensive plan shall be based on resident and seasonal population estimates and projections.") Finally, the "need" issue is one of the primary factors to be considered in any urban sprawl analysis. See Rule 9J-5.006(5)(g)1, Florida Administrative Code (urban sprawl may be present where a plan designates for development "uses in excess of demonstrated need"). The calculation of how much land is needed to accommodate the projected population involves comparing what is available for development under the comprehensive plan with the projected population over the same planning time frame applicable to the plan. An "allocation ratio" to express this need can be derived by dividing the development potential by the projected population. For example, if a comprehensive plan allocated 100 residential dwelling units over the planning time frame and the jurisdiction's population was projected to increase by 100 over the same time, there would be an allocation ratio of 1:1. This ratio would express an exact match between supply and demand. A ratio of 2:1, on the other hand, would demonstrate that the jurisdiction had twice as much land as designated for use as the projected population is expected to need. There is no allocation ratio adopted by statute or rule by which all comprehensive plans are judged. The testimony in this case from the planning experts is that there is no accepted "hard and fast" allocation ratio at which a local government would be required to deny all future plan amendments. (There is testimony from Department planners that there is a recommended guideline, which set a ratio of 1.25:1 of supply over demand. This ratio has not been adopted as a rule nor has it been proven to be an accepted ratio to be applied in this case.) Rather, the allocation ratio is a planning guideline to be used for two purposes: first, ensuring a local government has enough land to accommodate future population; second, discouraging urban sprawl. The County divides St. Johns County into four Planning Districts (part of the data and analysis of the Plan) for purposes of calculating allocation ratios of the amount of land needed for particular land uses compared to an amount of land so designated. (Disaggregating allocation ratios into planning districts is professionally acceptable.) Planning districts differentiate the County into different growth scenarios, development trends, and land use patterns. County staff explained the analysis performed regarding each of the four Planning Districts. Separate ratios were developed for each Planning District. Population projections were developed based on historical growth and compared to the Bureau of Economic and Business Research (BEBR) numbers. See footnote 5. In part, the County analyzed the amount of developable land designated in the FLUM, which was converted "into a very specific GIS map, so [they] had more definitive areas . . . ." Developable and un-developable land was analyzed. The County also examined the nature of the future land use densities existing on the developable lands to derive "a potential development for those developable areas and compare[d] those to the population projections which converted into housing units." A comparison was made "between population projections or need for housing units and the amount of dwelling units that can be accommodated in this developable area on the map."3 As otherwise noted further in Joint Exhibit 7-A, page A-37, in part: These population projections are then converted into housing demand by planning district as discussed in the Housing Element. The demand for these housing units will occur in different residential densities. However, as an aggregate measure, the total housing units needed is useful for comparison to the maximum net densities allowed for the various residential land use designations. It should be pointed out that rarely are the maximum net densities achieved, particularly at the higher density lands. For instance, while the Mixed Use Districts allow up to 13 units per acre, historically these acres have developed at much lower densities. This trend has been particularly significant due to the shortage of multi-family dwelling units constructed in the County. Single-family residential developments generally cannot achieve the densities at the high density level (6-13 units per acre), and rarely exceed the threshold for low density development (less than or equal to 2 units per acre). The May 2000, County EAR-Based Plan Amendment for the FLUE, provides residential land use allocation ratios for the year 2015 ranging between 1.63:1 for the Northeast Planning District to 11.59:1 for the Southwest Planning District, and an overall County allocation ratio of 3.08:1. These ratios appear in Joint Exhibit 7A at A-41, Table A-10, and were previously approved by the Department. ("A comparison of the allocation of dwelling units from the available developable land with the projected housing demand by planning district is provided in Table A-10.") Intervenors' expert independently calculated County allocation ratios, including the Nocatee New Town Map Amendment, and arrived at a ratio of 2.33:1 for the Northeast Planning District and 2.9:1 for the entire County, using data available as of February 2001.4 It is at least fairly debatable that these allocations ratios are supported by appropriate data and analyzed in a professionally acceptable manner. Numerous witnesses testified that allocation ratios should not be used as a bright line test because there are no adopted rules or clearly defined professional standards which establish a maximum ratio above which a plan amendment may not go. In other words, use of a maximum allocation ratio as a set upper limit, without consideration of other relevant factors to establish need, would offer no concrete, professionally accepted standard. Sierra offered no independent allocation ratios. Rather, Sierra elicited testimony from County staff that, if a series of assumptions supplied by Sierra were used to calculate the allocation ratios, based on Sierra's concept of using maximum theoretical density, the allocation ratios would be as high as 4.36:1 and 6.1:1 for the Northeast Planning District of the County. In other words, Sierra sought to have the County's calculations redone using the maximum theoretical density allowed under each land use category.5 The allocation ratios offered by Sierra raise a concern that, with the Nocatee development, there is a projected over-allocation of supply to meet the projected demand in the County, and, in particular, in the Northeast Planning District of the County. However, there is no persuasive evidence that the strict maximum theoretical density methodology offered by Sierra was professionally acceptable for use in the County to project the future need in light of the Plan Amendments. In fact, the testimony was that an allocation ratio utilizing the maximum theoretical density may be appropriate if only urban lands are included in the calculation, and if appropriate restrictions on the ability to realize this density are made a part of the equation. Sierra did not so limit its inquiry. Also, the weight of the evidence indicates that the use of maximum theoretical densities, as calculated according to Sierra, is more likely than not to overstate the realistic densities that will be achieved on the land designated for residential use by the County. While not mandating that every subsequent plan amendment must be categorically denied, the presence of an over-allocation will trigger a heightened, more thorough review of the indicators of urban sprawl when considering further plan amendments. Only amendments subjected to this greater scrutiny and still found to discourage urban sprawl may be found "in compliance" in the presence of an over- allocation. On the other hand, a higher allocation ratio may be appropriate in relatively high-growth counties, like the County, to offset the difficulties inherent in forecasting growth. An allocation ratio which is set too low may tend to reduce market choice, resulting in increased housing prices and a reduced employment base. There is persuasive evidence that the Map and Text Amendments meet this heightened level of sprawl analysis. Urban sprawl involves, at its core, the spreading of low density or strip commercial development from urban areas into rural lands. The determination of whether any amendment or plan constitutes urban sprawl is undertaken pursuant to the criteria of Rule 9J-5.006(5), Florida Administrative Code. The emerging development pattern in northeast St. Johns County exhibits numerous symptoms of sprawl. There is persuasive evidence that the Text and Map Amendments can be reasonably expected to make the situation better by providing "an anti-sprawl alternative to what's there now." The rule applicable to sprawl speaks directly to this situation. If a local government has in place a comprehensive plan found in compliance, the Department shall not find a plan amendment to be not in compliance on the issue of discouraging urban sprawl solely because of preexisting indicators if the amendment does not exacerbate existing indicators of urban sprawl within the jurisdiction. Rule 9J-5.006(5)(k), Florida Administrative Code (emphasis added). Neither Petitioner offered persuasive evidence to rebut the finding that the Map and Text Amendments improve the existing development pattern in northeast St. Johns County. Sierra attempted to imply that the Text and Map Amendments allow for the proliferation of urban sprawl in the form of low-density residential development. Contrary to this argument, the evidence shows, for example, that the three to eight dwelling units per net developable residential acre contained in the Text Amendment, coupled with the text provisions directing the location of higher density residential uses, affordable housing, and the myriad of non- residential uses, provide meaningful and predictable standards for the development of an anti-sprawl New Town. The flexibility built into the Text and Map Amendments afford a reasonable ability to change and meet the market demands over a long-term build-out. Natural Resource Protection Every New Town development must adhere to the Policies in the Plan. The Plan Amendment adds additional requirements to the Plan in the environmental section, Policy A.1.19.5, "Environmental Consideration." Policy A.1.19.5 of the Text Amendment affords natural resource protection by requiring that at least 35 percent of any land designated New Town shall be "reserved for Open Space/Conservation lands and shall preserve a connected system of environmentally sensitive and passive recreation areas that will form a greenway system." "At least 15% of this open space component must be uplands." At least ten percent of a village must be retained in open space/conservation areas. According to Policy A.1.19.5, "[s]ignificant environmental characteristics" must "be incorporated into the New Town design, particularly into the greenway system." The applicant for a New Town designation is required to "provide data and analysis regarding potential environmental impacts, including, but not limited to[,] impacts to wetlands, sub- surface waters, and surface waters and the presence of plant and animal species that are listed by the U.S. Fish and Wildlife Service or the Florida Fish and Wildlife Conservation Commission as threatened, endangered, or as a species of special concern." Natural resource protection is furthered through Objective A.1.19 which states: "The New Town Future Land Use category may be requested from any [DRI] that meets the policies set forth " in the Plan Amendments. The application form for a DRI requires a detailed listing of vegetation and wildlife. Rule 9J-2.010(1)(a), Florida Administrative Code. Any flora or fauna identified as listed must be protected in accordance with the Department's "Listed Plant and Wildlife Resources Uniform Standard Rule." Rule 9J-2.041, Florida Administrative Code. Master planning, such as in a DRI, better protects natural resource than piecemeal development. Moreover, there is persuasive evidence that natural resources can be better protected under the New Town category than in the existing Rural/Silviculture land use category. Pursuant to these provisions, there are 5,531 of the 11,332 acres designated as New Town set aside for recreation/open space, "including, but not limited to, parks, the Greenway, and golf courses." This set aside is based upon data and analysis compiled through the DRI review process. The Nocatee Preserve (an example of an "environmentally significant characteristic") is the most significant environmental resource on the Nocatee site and establishes additional resource protection. (The Plan Amendments designate approximately 1,630 acres (the Nocatee Preserve) lying above the mean high water line in the "Conservation" land use category. Petitioners do not object to this designation.) This Preserve is a mosaic of uplands and wetlands and includes tidal saltwater wetlands. It includes streams, uplands, and a variety of habitats. It fronts the Outstanding Florida Waters (OFWs) of the Guana/Tolomato preserve areas. The Preserve adds protection for the aquatic preserve. The Nocatee Preserve is located between the Nocatee New Town and the Tolomato River and protects the parcel's approximately 3.5 miles of frontage on the Tolomato River (Guana-Tolomato Aquatic Preserve). It is likely to ensure the protection of wildlife habitat on both sides of the Tolomato River and a natural view for recreational boaters and others. In addition to the Nocatee Preserve, which is approximately 1 1/2 miles wide, "the greenways," comprising a minimum of 4,961 acres (at least 960 acres of uplands at build-out) in St. Johns and Duval Counties, will be preserved. Greenways will consist of wetlands and uplands. Vegetative communities currently found on site will be preserved. The County's FLUM series includes Map 9-B, entitled "Environmentally Sensitive Lands (ESL)." Within the County, the ESL designation is given to OFWs, estuaries, wetlands, essential habitat to listed species, coastal barrier resources and beach and dune systems, and other areas specifically designated by the Board of County Commissioners.6 (Policy E.2.2.5 of the Plan also requires the County to protect ESLs "through the establishment of Land Development Regulations (LDRs) which address the alternative types of protection for each type of" ESL.) The weight of the evidence indicates that Map 9-B is a generalized depiction of these ESLs. On its face, the Map contains a disclaimer that the data are provided from multiple sources, with varying degrees of accuracy. In essence, Map 9-B is used by the County for "reference only" purposes, i.e., data and analysis only, and is not intended to be used as a predicate for decision-making, for example, a determination is made as to the "exact location of a wetland jurisdictional line." Map 9-B, although part of the data and analysis, is not the best available data for site-specific analysis. Policy A.1.11.7 of the Plan Amendment states that "[i]n the event of a conflict between any of the Maps and the text of the Plan, the text of the Plan shall control." Pursuant to the Plan Amendments, see, e.g., Policy A.1.19.5, the County requires applicants for New Town plan amendments to provide the County with site-specific information, including environmental, and wildlife surveys (conducted pursuant to the Florida Fish and Wildlife Conservation Commission's (FFWCC) requirements),7 including vegetative surveys, in order for the County to determine the extent of ESLs on the property, proposed for New Town designation. See Finding of Fact 95. This information is part of the data and analysis required under the Plan Amendments and is required to be based on professionally accepted methodologies. Site visits by County personnel are also required. Sierra alleges that the protective measures mentioned above in the Plan Amendments fail to adequately address natural resources because the term "significant environmental characteristics" in the Text Amendment and the protections attendant such areas are uncertain, and the depiction of greenways, wetland impacts, and development of the "Sandy Ridge Village" as depicted in various maps attached to the Nocatee DRI Development Order, allow undue impacts. The operation of the Text Amendment as a whole, including the provision for the protection of "significant environmental characteristics," when read in conjunction with the protections required in the Plan and Plan Amendments, can be expected to afford protection of natural resources. The remainder of Sierra's allegations rest on the presumption that the maps of development areas and greenways attached to the Nocatee DRI Development Order are part of the County Plan and are subject to this compliance review. However, the only portion of the Nocatee DRI Development Order incorporated into the Plan and subject to this review is the provision that establishes the "allowable uses and mix of uses." Policy A.1.19.15. The location of those uses, as shown in the Nocatee DRI Development Order is not incorporated into the Plan. (However, Ordinance No. 2001-18, recognizes the importance of the Nocatee DRI Development Order. See Ordinance No. 2001-18, Section 2, paragraph 5). Accordingly, and as further set forth below in the Conclusions of Law, Sierra's allegations that the Plan Amendment must be found not "in compliance," e.g., because of the location of uses and their potential impact on natural resources, is beyond the scope of this proceeding. Nevertheless, the data and analysis supporting the Nocatee DRI have been considered herein in order to determine whether the Plan Amendments are "in compliance." The Nocatee site in Duval and St. Johns Counties is approximately 15,000 acres, of which "approximately 8,000 acres of uplands and wetlands will be preserved in the Greenway, the Preserve and within preserved jurisdictional wetlands in the villages and Town Center Village " Further, it was apparent that when several maps are reviewed together, up to 474 acres of wetlands may be impacted by the development, subject to further permitting. At present, it is speculative as to the precise number of wetlands which will be impacted by the development. However, there are general depictions of wetlands delineated on, for example, Maps H-1 and H-3, which are anticipated to be preserved. Ultimately, the wetlands impacts are required to be addressed on a site- specific basis in future permitting by the United States Army Corps of Engineers and the St. Johns River Water Management District.8 Sierra's expert (Mr. Hoctor) opined that the proposed greenways were, in some instances, too narrow because protected areas should be located at least 330 feet from developed areas due to "edge effect." However, Mr. Hoctor also stated that the distance of the edge effect could be less than 330 feet, although he believed that 330 feet "is a good base-line estimate of edge effects." On the other hand, the County and Intervenors' experts opined that the greenways, as designated, are sufficiently wide, and can be expected to provide adequate habitat to sustain the environmental resources on site.9 In general, on the Nocatee site, buffers of upland areas ranging from 15 to 100 feet will be preserved in their natural state adjacent to wetlands systems. In some areas, the width of the proposed buffers will exceed current County requirements. The buffers serve to push incompatible land uses away from surface waters and protect wetland functions. Further, Deep, Durbin, Smith, and Sweetwater Creeks are proposed to be protected by a minimum 100-foot buffer along the Creeks, which is twice as wide as other County requirements for these areas. (Theoretically, estuary systems, require a 50-foot buffer, whereas the Nocatee project has committed to a 100-foot buffer.) The County Land Development Code requires upland buffers adjacent to contiguous jurisdictional wetlands, and the buffer sizes vary, dependent upon the location of the wetlands. For example, a 50-foot buffer is required along the Tolomato River in areas where the high water line can be set; and in all other areas with contiguous wetlands, a 25-foot buffer and a 25-foot setback are required. As noted in the Nocatee DRI ADA, Question 16, Second Sufficiency Response: "The state-of-the-art stormwater management system proposed for Nocatee will limit the 100-year flood plain to greenways, wetlands, and stormwater management facilities. No post-development developed areas in Nocatee will be in the 100-year flood plain." This representation is adopted in the Nocatee DRI Development Order. Further, the bald eagle is a protected species and the habitat for the bald eagle is an essential habitat. The bald eagle's nest on-the Nocatee site is being protected by means of a 1,500-foot management zone (360 degrees). (The United States Fish and Wildlife Service guidelines indicate that a 1,500-foot buffer should be utilized.) Petitioners also offered evidence, by and through the testimony of Mr. Hoctor, that "only about 60 acres of both sand hill and scrub are proposed for protection out of at least 180 acres of zeric communities on site. Most of it long leaf pine sand hill and xeric oak sand hill." According to Mr. Hoctor, these areas include a 70-acre sandy hill parcel in the proposed Sandy Ridge Village, which is not expected to be preserved, and a 25-acre parcel, which will be preserved. (A 17-acre parcel of scrub-type habitat will also be preserved in the southwest corner of the site.) The experts agree that gopher tortoises live in and need sandy soils to construct their burrows. Gopher tortoises will be impacted by the Nocatee development. One of the guidelines set by the FFWCC states that a minimum size patch of 25 acres is necessary for on-site protection of gopher tortoises. The experts disagree as to whether preservation of a proposed 25-acre site (to be incorporated into a 20-mile greenway on-site) is sufficiently large enough to accommodate the gopher tortoises (and gopher frogs, indigo snakes, and other species) on the Nocatee site. The County and Intervenors provided reasonable explanations for requiring the preservation of the 25-acre site (as a significant natural communities habitat) in lieu of the 70-acre site. At the very least, reasonable minds have differed on this issue. It is also subject to reasonable debate whether gopher tortoises will remain on-site given the preserved 25-acre site. On the other hand, the 25-acre site has canopy and good ground cover vegetation for the gopher tortoise community. Also, pursuant to the Nocatee DRI Development Order, "as mitigation for impacts to gopher tortoises and their commensals, the Developer will be responsible for off-site mitigation of the equivalent of approximately 66 acres of habitat, in conjunction with the permit requirements of the [FFWCC]." "This off-site mitigation will be accomplished by the Developer by issuance of an incidental take permit or by purchase of habitat at an off-site location within the jurisdictional boundaries of the Northeast Florida Regional Planning Council." Total preservation on-site is expected to be approximately 33 percent which exceeds the ten percent Plan requirement. Sherman Fox Squirrels are a species of special concern. It appears that two fox squirrels have been sighted on the Nocatee site in the general vicinity of the St. Johns County/Duval County lines. This species is "highly mobile" and "will very likely migrate to other suitable habitat when the [Nocatee site is developed]." "[F]ox squirrel habitat will be included in the incidental take permit." The preservation of the fox squirrels has been addressed in a general way, i.e., through preservation of significant natural communities and the 8,000 acres of land which is being preserved on-site. Petitioners also presented expert testimony that the Nocatee site is an essential habitat for the Florida Black Bear, which should be protected by preserving a "large swath" of most or all of the southern portion of the Nocatee site which "would serve as a potentially functional wildlife corridor." (The Florida Black Bear is a threatened species. The minimum acreage required to sustain a viable population for the Florida Black Bear is between 500,000 and 1 million acres.) The experts disagreed whether portions of the Nocatee site are essential habitat for the Florida Black Bear population and the extent of the impacts on the Florida Black Bear if the Nocatee site is developed as proposed. (Mr. Hoctor suggested during cross-examination that the Florida Black Bear population, east of U.S. Highway 1 in the County, stood "only a fair to poor chance of being viable.")10 Part of the habitat data discussed by Mr. Hoctor indicates that bear road kills were more than 15 years ago. More recent bear kills have occurred in other parts of the County (west of the river or adjacent to the Twelve Mile Swamp property), but not east of Interstate 95 in the Nocatee area. Even if Florida Black Bears use the Nocatee site, more than one-half of the site (approximately 8,000 acres), which will be preserved for wildlife corridors, potentially may be used by Florida Black Bears for migration and foraging. It is at least fairly debatable whether the environmental components of the Plan Amendments are "in compliance." Land Use Suitability The Nocatee site plan was based upon a land use suitability analysis, considering soils, wetlands, vegetation, archeological sites, and topography. The Nocatee DRI ADA contains appropriate data and analysis, including testimony during the final hearing, related to such topics as "vegetations and wildlife," "wetlands," "soils," "floodplains," and "historical and archeological sites." The Nocatee scientists spent approximately 8,000 man hours in the field (on the Nocatee site) over a course of two and one-half years collecting detailed data related to these issues. The data was collected and analyzed in a professionally acceptable manner. Economic Feasibility In General The Capital Improvement Element (CIE) of a Comprehensive Plan identifies facilities for which local government has financial responsibility, which include roads, water, sewer, drainage, parks, and solid waste. (As noted herein, this does not include schools for which the School Board has financial responsibility.) Petitioners raise numerous issues relating to the "financial feasibility" of the Plan Amendments. The record contains detailed data and analysis of existing and future public facility needs. The data and analysis were conducted in a professionally acceptable manner. Further, the County conducted a cost benefit analysis of the Nocatee development and determined that the development can be expected to produce a positive revenue stream for capital expenditures in each year. (For example, the County's Budget Director calculated that as of build-out (twenty-five year period), Nocatee will result in a net financial gain to the County of approximately $114 million.) This study was bolstered by Intervenors' cost benefit analysis documenting a net positive cash flow. Public Schools Sierra contends that the Map Amendment runs afoul of the State's growth management laws by not providing a financially feasible development that adequately addresses its impacts on the public school system. As set forth in the Conclusions of Law, existing laws do not require local governments to address public schools as part of comprehensive planning. This link between land use and public schools is currently optional and the County has not elected to pursue the option; this election is supported by extant law. There is persuasive evidence that the County is not responsible for funding public school facilities. Rather, the St. Johns County School Board is responsible for such funding. For example, the only portion of the school facilities construction paid by the County occurs when the School Board requests the County to pay for the upgrading of a facility to provide for use as a hurricane shelter. The Nocatee developers agreed to construct at least two such shelters in accordance with the Department of Education's standards. However, the placement of hurricane shelters is a decision made by the County, not the School Board. Furthermore, the County has not adopted a Public School Facilities Element or a school concurrency funding program. (Examples of concurrency requirements for the State of Florida include transportation, potable water, sanitary sewer, parks and recreation, drainage, and solid waste.) The St. Johns County School Board is an independent taxing authority with an established budget for school construction and operation. Nevertheless, with respect to the New Town Category, elementary schools are allowed within or adjacent to village centers and the Town Center Village. The Nocatee development will require an additional eight schools in the County in order to meet the projected need. (Mr. Toner projected that over a period of 25 years, eight new schools would be needed and that during the five-year planning horizon after construction begins at Nocatee, one middle school would be needed for the projected number of students, i.e., 450 would start to materialize. Mr. Toner desires that schools be built concurrently with development, which does not appear to be required.) The Nocatee developers have agreed to donate, at no charge to the County (or the citizens of the County), land for the eight public schools and to waive a credit against the school impact fees to which the developers would otherwise be entitled. The value of the land donation credit is approximately $12 million. Additionally, by build-out (in the twenty-fifth year), according to Intervenors' data and analysis, the School Board can expect to receive annual net revenue or gain of approximately $9.6 million. It is also expected that over the life of the Nocatee development and, in particular, during the later phases of the development, revenues will "significantly exceed the costs," in light of expected commercial, industrial, and additional residential development "that's generating the student load on the system." Transportation The Plan Amendments add Policy H.1.6.6. to the County's Comprehensive Plan stating: The Nocatee Development of Regional Impact, a multi-use development meeting the criteria of Chapter 163.3180(12), Florida Statutes, is authorized by the County to utilize the standards and guidelines set forth in the Statute to satisfy the County's transportation concurrency requirements by payment of a proportionate share contribution is [sic] as stated in the Nocatee Development of Regional Impact Development Order, Special Condition No. 25 entitled Transportation Resource Impacts. (See Ordinance No. 2001-18) The "pipelining" method of mitigating transportation impacts has been selected in the Plan Amendments. This method allows the transportation mitigation funds to be used to increase the transportation capacity of some links of a regional roadway network beyond that necessary to offset projected impacts. It allows impacts on the regional roadway network to be handled on a proportionate share basis. Pipelining contemplates that various proportionate share impacts along the regional roadway network are assessed and all of the calculated dollars under the pipelining method are aggregated to create "a pot of money" which is used "to build one or more whole transportation improvements." The pipelining statute takes precedence over the conflicting concurrency requirements of the County. Here, the mitigation package is based upon a "proportionate fair share" calculation, under which Nocatee will pay $99.7 million. This amount is supported by appropriate data and analysis based upon the application of professionally accepted methods. In addition to the payment, the mitigation will include right-of-way donation and roadway construction. Petitioners do not challenge the concept of "pipelining." Rather, Petitioners question whether the transportation components of the Plan Amendments are "economically feasible." Overall, there is persuasive evidence, presented in the form of data and analysis, that with the Nocatee approval and the Plan Amendments, the County's transportation capital funds are likely to be improved both at the 25-year build-out and within the first five years. (State law requires that land use decisions and transportation facility planning be coordinated over the five- year planning time frame in order to maintain and achieve adopted levels of service. See Section 163.3177(3)(a), Florida Statutes. The persuasive evidence indicates that the Nocatee development will not cause any roadway segment to fall below its adopted level of service (LOS) standard during the five-year planning time frame.) Petitioners, largely through the testimony and exhibits offered by Mr. Feldt (a former employee with the County whose area of expertise is transportation), contend that the proportionate fair share calculation was incorrectly calculated and that the Nocatee DRI development data and analysis understates transportation impacts which are likely to arise as a result of the Nocatee development. However, while Mr. Feldt maintained that the $99.7 million allocation would not be sufficient to cover some of the improvements he deemed necessary, such as right-of way, most of his concerns regarding the transportation component of the Nocatee DRI had been satisfied during the DRI review process leading up to the County's approval of the Nocatee DRI Development Order. It is at least fairly debatable that the pipelining transportation component of the Plan Amendments is supported by appropriate data and analysis, which is professionally acceptable.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be issued concluding that the Plan Amendments adopted by St. Johns County in Ordinance No. 2001-18 are "in compliance" as defined in Chapter 163, Part II, Florida Statutes, and the rules promulgated thereunder. DONE AND ENTERED this 20th day of May, 2002, in Tallahassee, Leon County, Florida. _________________________________ CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of May, 2002.
The Issue The issue is whether the City of Panama City's small scale development amendment adopted by Ordinance No. 2055.1 on February 8, 2005, is in compliance.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background Creekstone is a limited liability corporation and presumed to be the owner of a 3.212-acre tract of land at 305 East Beach Drive, Panama City.3 (The record does not show when or if Creekstone actually purchased the property; when the application for a land use change on the property was filed with the City, Creekstone was a contract purchaser. In its Proposed Recommended Order, however, the City states that Creekstone "recently acquired" the property.) The property lies at the northwest edge of a residential area known as The Cove and is just south of the central business district of the City. The Cove is separated from the business district by a small waterbody known as Massalina Bayou (Bayou), which is spanned by the Tarpon Bridge (Bridge) at one of the Bayou's most narrow points. The 225-foot Bridge provides the most direct and easiest access between the two areas of the City. For many years, and beginning before the City adopted its Plan, Tibbetts Boat Works, Inc. (Tibbets) occupied the site and was engaged in the boat repair business, consisting of hull repair, engine maintenance, other mechanical services, and boat bottom painting, a legal but nonconforming use under the City's land development code. Photographs of the area suggest that the business is no longer active, presumably because the property has been sold. On or about December 8, 2004, SFB Investment Company, LLLP (SFB), who then owned the property but had a contract to sell it to Creekstone, filed an application with the City Planning Board seeking a change in the land use and zoning on the property. At the Planning Board meeting on January 10, 2005, the staff noted that the proposed change would "allow an encroachment of commercial into a predominately residential area" and recommended denial of the application on the ground that the change "is inconsistent with the LDR and the Comp Plan."4 By a 3-1 vote, the City Planning Board rejected the staff recommendation and recommended that the application be approved. On February 8, 2005, by a 4-1 vote, the City accepted the recommendation of the City Planning Board and adopted Ordinance No. 2055.1, which amended the FLUM by reclassifying the land use designation on the property from MU to GC for the purpose of allowing the owner to "develop [a] multi-family project on [the] property." (Simultaneously with that change, the City also changed the zoning on the property from Mixed Use- 3 to General Commercial-2, which allows a wide range of activities, including residential, professional office and services, low-intensity commercial, public/institutional/ utilities, and high-intensity commercial.) The MU land use classification "is intended to provide areas for medium to high density residential development and low intensity commercial development," allows a density of "not more than twenty (20) dwelling units per acre," and an intensity of "[n]o more than 75% lot coverage as determined by the size of the lot compared to the amount of impervious roof and driveway/ parking lot surface." On the other hand, the GC district is "intended to provide areas for high intensity commercial development, including retail sales and services, wholesale sales, shopping centers, office complexes, and other similar land uses." There are no density restrictions, but intensity is limited to "[n]o more than 90% lot coverage." Thus, while the two land uses are similar in some respects, the highest and best use on the property will now be "high intensity commercial development," such as shopping centers and office complexes, a much more intensive use than is presently permitted under the MU land use category. To address this concern, witness Harper indicated that SFB has filed a restrictive covenant on the property which includes a shoreline buffer, as well as use, height, and setback restrictions. At the Planning Board meeting on January 10, 2005, however, the staff stated "that a covenant would not be enforceable." Under the existing land use (MU), the owner can construct up to 64 residential units on the property. That number is derived by multiplying the size of the property (3.212 acres) times the allowed density (20 units per acre). However, the current zoning on the property (which is apparently tied to the MU land use category) prohibits the construction of buildings which exceed 65 feet in height. Because of this height restriction, which limits the number of residential units that can be constructed on the property, the owner has requested a change in the land use (and zoning) so that it can develop a multi-family residential condominium project (nine stories in height) with approximately 77 units. On March 10, 2005, Mr. Cooper filed his Petition challenging the small-scale amendment. He later filed an Amended Petition on April 21, 2005. Mr. Cooper resides and owns property one-half block south of the subject property (in an area designated as a special historical zone of the City) and submitted objections to the amendment during the adoption process. As such, he is an affected person and has standing to file this challenge. Joint Exhibit 9 reflects that Creekstone is a "contract purchaser" of the subject property. It also reflects that it appeared through counsel at the adoption hearing on February 8, 2005, and offered comments in support of the plan amendment. As such, Creekstone is an affected person and has standing to participate in this case. In the parties' Pre-Hearing Stipulation, Mr. Cooper (through his former counsel) identified numerous issues, many of which were not raised in his Amended Petition. At hearing, however, he contended only that the GC land use is incompatible with the character of the surrounding area, and that the amendment is internally inconsistent with Objectives 1.1 and 1.4 and Policies 1.1.1, 1.2.1, and 1.4.1 of the Future Land Use Element (FLUE) of the Plan. All of the objectives and policies relate to the compatibility issue. In all other respects, Petitioner agrees that the plan amendment is in compliance. Because the City's action involves a small scale (as opposed to a large scale) development plan amendment, the Department of Community Affairs did not formally review the plan amendment for compliance. See § 163.3187(3)(a), Fla. Stat. The Subject Property West Beach Drive runs in a northwest-southeast direction through the downtown business portion of the City until a few blocks north of the Bridge, where it changes to East Beach Drive. The roadway continues south across the Bridge and in a southerly direction along the eastern edge of St. Andrews Bay, a much larger waterbody which lies between the City and Panama City Beach. Approximately one-half mile south of the Bridge, East Beach Drive takes a 90-degree turn to the east. Most, if not all, of the peninsula south of the Bayou and Bridge and continuing until East Beach Drive turns to the east is known as The Cove, a part of which has been designated by the City as a historic special treatment zone because of its historical significance. The predominate character of The Cove is older, single-family homes. As noted above, the Bayou separates The Cove from the central business district and serves as a natural barrier between the two areas. The property is an odd-shaped parcel which sits just east of the southern terminus of the Bridge and fronts on the Bayou. (The central business district lies directly across the Bayou to the north and northwest, is classified as General Commercial or Public/Institutional, and includes a wide array of offices, government buildings, restaurants, and other commercial and public uses.) The western side of the property faces East Beach Drive. Immediately across East Beach Drive to the west (and facing St. Andrews Bay) is the Cove Harbor Condominium, a nine-story, multi-family residential condominium which was apparently constructed under MU standards, which apply to that parcel. Immediately to the east of the property is a single- family residence and then a two-story townhouse complex. The southern boundary of the property (which appears to run approximately 325 feet or so) faces East Second Court, a local road which begins on East Beach Drive and runs eastward until Watson Bayou (perhaps a mile or so away). Although a map of the historical district was not introduced into evidence by the parties, the northern and western reaches of the special treatment zone appear to begin just east of the intersection of East Second Court and East Beach Drive since the homes at 114 and 122 East Second Court are designated as having historical significance. See Respondent's Exhibit 4. These two homes appear to lie directly across the street from the southern boundary of Creekstone's property. Except for a two-story, multi-family structure (Cedar Cove Townhouses) which sits across East Second Court facing the southwest corner of the subject property, the remainder of the southern boundary of Creekstone's property faces four single-family homes. Several other multi-family structures are scattered throughout the area to the south and east, while the remainder of the neighborhood extending for at least one-half mile to the south and all the way to Watson Bayou on the east is predominately single-family residences. Finally, a condominium is located about one-half mile south of the property on the waterfront where East Beach Drive makes a 90-degree turn to the east. Except for Tibbets' activities, there is no commercial encroachment (by non-conforming use or land use classification) in the immediate area south of the Bridge and Bayou. The current FLUM shows that, with three exceptions, the entire area south of the Bridge and the Bayou to the end of the peninsula, and extending east at least a mile to Watson Bayou, is either classified as Mixed Use or Residential Low Density. (Perhaps a mile or so to the southeast there is one parcel classified as Recreation, another as Public/Institutional (which is probably a school), and a smaller adjoining parcel classified as General Commercial.) Thus, if the change is approved, the subject property will be the only parcel south of the Bridge and Bayou (except for the above exceptions which lie around a mile away) which is classified as commercial; the remainder is either mixed use or residential. Over the years, Tibbets has been the subject of City code enforcement actions, investigations by City code enforcement personnel, and investigations by the Department of Environmental Protection (DEP). It has also caused chronic environmental problems in the area. On August 27, 2002, DEP and Tibbets executed a Consent Order to resolve certain violations. Also, on April 10, 2001, Mr. Paul L. Benfield, who apparently either owned Tibbets or was associated with it in some manner, entered into a Consent Order with DEP because of his unlawful filling of 0.114 acres of jurisdictional wetlands on the site. It is fair to describe the subject property as blighted, unsightly, and in disrepair. Photographs received in evidence suggest that the business is no longer active. The parcel is fenced on three sides, and, besides an older structure which apparently housed Tibbets' office, the property contains a mixture of empty storage crates, pilings, and various pieces of equipment that were once used in the boat repair business. There are also several docks or small piers extending into the Bayou from the northwestern corner of the site. Finally, it appears that much of the eastern half of the parcel contains wetlands and is largely undeveloped. Although the staff report dated December 31, 2004, recommended denial of the application, noting that it would allow "an encroachment of commercial into a predominately residential area," it acknowledged that "[a]llowing this request can make a case for helping to rid this area of a problematic non- conforming use." See Joint Exhibit 6, page 2. Petitioner's Objections As narrowed at hearing, Mr. Cooper contends only that the plan amendment is not compatible with the character of the adjoining land in The Cove and is thus internally inconsistent with Objectives 1.1 and 1.4 and Policies 1.1.1, 1.2.1, and 1.4.1 of the FLUE. He also relies upon Policy 2.5.5(6)(e) of the City's Land Development Code. However, plan amendments do not have to be consistent with land development regulations in order to be in compliance. See § 163.3184(1)(b), Fla. Stat. Objective 1.1 requires that the City maintain a FLUM "which coordinates future land uses with . . . [compatibility]5 of adjacent land uses." Policy 1.1.1, which furthers that objective, provides in part that the City will regulate land uses through the designation of land use districts on a FLUM, and that the "location and extent of development within the City" should be "consistent with . . . compatibility of adjacent land uses." Under this objective and policy, then, land use districts on the FLUM should be located in a manner which assures compatibility with adjacent land uses. Objective 1.4 provides that the City shall "maintain procedures for the elimination or reduction of land uses inconsistent with the character of the City and the future land uses designated in the Plan." In furtherance of that objective, Policy 1.4.1 requires that the City "restrict proposed development which is inconsistent with the character of the community." Taken literally, the objective encourages the City to reduce or eliminate land uses that are inconsistent with the character of the surrounding area or other land use districts. In the same fashion, the policy requires that the City prohibit development that is not consistent with the character of the adjoining area. Finally, among other things, Policy 1.2.1 requires that the City "administer land development regulations for implementation of the Comprehensive Plan" in such a manner as to "ensure the compatibility of adjacent land uses." (The City has adopted such regulations for this purpose.) Because the implementation of land development regulations is not in issue, the provision does not appear to be relevant. According to the City's Director of Public Works, The Cove, or at least that part which lies in the area around Creekstone's property, is considered to be a part of the central business district since the two areas are "contiguous," and therefore the extension of the commercial land use district across the Bayou would be consistent with the character of the immediate area. The same view was also expressed by witness Grey. However, the two areas are physically separated by a waterbody (the Bayou) and are connected only by a 225-foot bridge which spans the Bayou at one of its most narrow points. At the same time, the land uses in the two areas are distinctly different: the business district contains a wide array of commercial and public/institutional uses while the predominate character of The Cove is single-family residential, with a scattering of multi-family residential dwellings such as townhouses and a condominium. The fact that the City interprets its GC district (presumably through its zoning regulations) as allowing certain residential uses does not change this dichotomy in character. Therefore, it is inappropriate to consider The Cove and the central business district as being contiguous, or to base a finding of compatibility on the fact that commercial uses are now found across the Bayou in the business district. The commercial land use classification has never been extended into the residential neighborhood south of the Bayou. If the change becomes effective, the new land use would be incompatible with the Residential Low Density and Mixed Use land uses which now make up the entire neighborhood. It would also be incompatible with the historic special treatment zone, which lies directly across the street from Creekstone's property. Finally, the creation of a commercial district in this area of The Cove would change the character of the neighborhood, and it is fair to infer that, even if SFB's covenant is enforceable, it would still lead to, and justify, the reclassification of other nearby parcels into commercial uses. Given these considerations, the proposed land use is internally inconsistent with the City's objective and policy that there be "[compatibility] of adjacent land uses," see Objective 1.1 and Policy 1.1.1, and Plan provisions encouraging the elimination of land uses and associated development which are inconsistent with the "character of the community." See Objective 1.4 and Policy 1.4.1. The minutes of the two meetings which culminated in the adoption of Ordinance No. 2055.1 reflect that the City's (and Planning Board's) principal rationale for the reclassification of the property was to eliminate an unsightly nonconforming use (boat repair business) which occupied the site. While it is true that the City's Plan encourages the revitalization and redevelopment of blighted areas, and provides that developers should be given "flexibility" when seeking to revitalize blighted areas, see Objectives 1.3 and 1.15 of the FLUE, there is no evidence that these objectives are intended to override (and trump) the provisions of the Plan which require that adjacent land uses be compatible with one another and preserve the character of the neighborhood.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Administration Commission enter a final order determining that the plan amendment adopted by Ordinance No. 2055.1 is not in compliance. DONE AND ENTERED this 19th day of August, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of August, 2005.
The Issue The issue is whether the proposed site is consistent and in compliance with existing land use plans and zoning ordinances.
Findings Of Fact NOTICE In compliance with Rule 17-17.151(4)(e), Florida Administrative Code, notice of the hearing was published in the Florida Administrative Weekly on October 2, 1992. A news release containing notice of the hearing was given to the media on September 21, 1992, and October 21, 1992. A copy of the public notice was sent by certified mail, return receipt requested, to the chief executives of the local authority responsible for zoning and land use planning in Dade County, in compliance with Rule 17-17.151(4)(b), Florida Administrative Code. A copy of the public notice was posted at the site in compliance with Rule 17-17.151(4)(c), Florida Administrative Code. Additionally, notice was published on September 25, 1992, in the Miami Review, a newspaper of general circulation in Dade County, in compliance with Rule 17-17.151(4)(a), Florida Administrative Code. LAND USE AND ZONING CONPLIANCE The proposed expansion of Dade County's Resource Recovery Facility, as set forth in its Site Certification Application, will be within the confines of the certified site of the existing resource recovery facility. Hence, that existing site carries a presumption that its current use is consistent with land use considerations. The site of the proposed expansion is consistent with the Dade County Comprehensive Development Master Plan (Dade Master Plan) pursuant to the Growth Management Act of 1985. More particularly, the site has a land use designation of "Institutional and Public Facility" on the Future Land Use Plan Map of the Dade Master Plan. The "Institutional and Public Facility" designation permits the construction and operation of a resource recovery facility. Also, the proposed expansion of Dade County's Resource Recovery Facility is consistent with: Objective 5 and Policies 5-A and 5-B as set forth in the interpretive text to the Land Use Element of the Dade Master Plan; Objective 3 and Policies 3-A, 3-B, 3-C, 3-D, 3-E and 3-F of the Conservation Element of the Dade Master Plan; and Policies 1-K and 4-B of the Water, Sewer and Solid Waste Elements of the Dade Master Plan. The existing site is presently within the GU interim district. Resolution R-569-75, which granted county approval for the existing site, satisfies the need to show compliance with the zoning ordinance. The proposed expansion of the Dade County Resource Recovery Facility is consistent with the zoning code found in Chapter 33 of the Code of Metropolitan Dade County as well as Resolution R-569-75.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Governor and Cabinet, sitting as the Siting Board, enter a Final Order determining that the site of the proposed Dade County expansion of its resource recovery facility is consistent and in compliance with existing land use plans and zoning ordinances. DONE and ENTERED this 24th day of November, 1992, at Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of November, 1992. APPENDIX TO RECOMNENDED ORDER IN CASE NO. 92-4672EPP The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted in this case. Specific Rulings on Proposed Findings of Fact Submitted by the Applicant, Dade County Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 2-4(1); 5(2); 6(4); and 7(5). Proposed finding of fact 1 is unnecessary. COPIES FURNISHED: Ross McVoy, Attorney at Law Fine Jacobson Schwartz Nash & Block 215 South Monroe, Suite 804 Tallahassee, Florida 32301-1859 Stanley B. Price, Attorney at Law Fine Jacobson Schwartz Nash & Block 100 Southeast 2nd Street Suite 3600 Miami, Florida 33131-2130 Representing the Applicant Richard Donelan Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Representing DER Hamilton S. Oven, Jr. Office of Siting Coordination Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Gail Fels Assistant County Attorney Metro Dade Center, Suite 2800 111 Northwest First Street Miami, Florida 33128 Representing Dade County Lucky T. Osho Assistant General Counsel Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Representing DCA William H. Roberts Assistant General Counsel Department of Transportation 605 Suwanee Street, MS-58 Tallahassee, Florida 32399-0458 Representing DOT Toni M. Leidy Attorney at Law South Florida Water Management District 3301 Gun Club Road Post Office Box 24680 West Palm Beach, Florida 33416-4680 Representing SFWMD Michael Palecki, Chief Bureau of Electric & Gas Florida Public Service Commission 101 East Gaines Street Tallahassee, Florida 32399-0850 Representing PSC M. B. Adelson IV Assistant General Counsel Department of Natural Resources 3900 Commonwealth Blvd., MS-35 Tallahassee, Florida 32399-3000 Representing DNR James Antista, General Counsel Florida Game and Fresh Water Fish Commission Bryant Building 630 South Meridian Street Tallahassee, Florida 32399-1600 Representing GFWFC Carolyn Dekle, Executive Director Sam Goren, Attorney at Law South Florida Regional Planning Council 3440 Hollywood Boulevard, Suite 140 Hollywood, Florida 33021 Representing South Florida Regional Planning Council David M. DeMaio Attorney at Law One Costa del Sol Boulevard Miami, Florida 33178 Representing West Dade Federation of Homeowner Associations Honorable Lawton Chiles Honorable Jim Smith Governor Secretary of State State of Florida State of Florida The Capitol The Capitol, PL-02 Tallahassee, Florida 32399 Tallahassee, Florida 32399-0250 Honorable Robert A. Butterworth Honorable Tom Gallagher Attorney General Treasurer and Insurance State of Florida Commissioner The Capitol State of Florida Tallahassee, Florida 32399-1050 The Capitol Tallahassee, Florida 32399 Honorable Bob Crawford Commissioner of Agriculture Honorable Gerald A. Lewis State of Florida Comptroller The Capitol State of Florida Tallahassee, Florida 32399-0810 The Capitol, Plaza Level Tallahassee, Florida 32399 Honorable Betty Castor Commissioner of Education State of Florida The Capitol Tallahassee, Florida 32399
The Issue The issue in this case is whether it should be determined that the Highlands County Comprehensive Plan, as amended, was in compliance with Chapter 163, Fla. Stat. (1993), as of the adoption of the County Ordinance 94-1 on March 2, 1994.
Findings Of Fact Adoption History Highlands County adopted its first Comprehensive Plan with a land use map in 1991. The Department of Community Affairs (the DCA or Department) took the position that the initial comprehensive plan was not in compliance. On September 15, 1993, the County adopted an amended comprehensive plan. (County Exhibit 6) The DCA took the position that the amended comprehensive plan, in particular its natural resources element, did not adequately protect areas of important plant and animal habitat from agricultural land uses. (County Exhibit 8). Highlands County adopted remedial amendments on March 2, 1994. (County Exhibit 9) On March 16, 1994, DCA published a Cumulative Notice of Intent to find the Highlands County Comprehensive Plan and Remedial Comprehensive Plan Amendments in compliance. (County Exhibit 13) The Petition for Administrative Hearing by Heartland Environmental Council, Inc. (HEC) was filed on or about April 6, 1994. The HEC Petition was signed by Kris Delaney, as its president. The parties' Prehearing Stipulation filed on October 17, 1994, eliminated several of the issues initially raised in the HEC Petition. The Lake Wales Ridge Highlands County is special because of the presence of a feature known as the Lake Wales Ridge, which is only between five and 14 miles wide but stretches for about 100 miles in a north-south orientation through the County. Most of the Ridge is contained within Highlands County, but smaller portions extend into neighboring counties. The Lake Wales Ridge had its beginnings when the sea covered much of what is now the Florida peninsula. A paleo beach and dune system was formed at the edge between the sea and the Ridge. When the waters receded, it left behind a ridge of relatively high ground characterized by generally coarse sands. These sands, which began as beach sand, have been weathered for millions of years, rendering them very sterile and low in nutrients. Water passes very quickly through these sands, making the soil and environment resemble those occurring in much drier places. Although created through the same processes, the Ridge contains many different unique and specialized habitats. Because of these habitats, the Ridge is a national "hot spot" for endemism. This means that many different species of organisms occur in this relatively small area; many of these species occur exclusively or primarily on the Ridge. At least two dozen plant species are found exclusively or primarily on the Ridge, and it is believed that many species have yet to be discovered. In more recent times, the high and dry Ridge also has attracted a disproportionate share of the residential, commercial and agricultural development in the County. Development pressures have conflicted with the habitat needs for the survival of many of the plant and animal species that occurred on the Ridge. Urban and citrus development tend to obliterate habitat; they also compete for available water supply. In addition, as the Ridge has developed, the natural fires that served an important role in maintaining the special habitats of the Ridge were suppressed. More recently, although man has come to understand the importance of fire to these habitats and the species that thrive in them, the increasing presence of man's development has made fire management more problematic and, in some cases, impossible. With more and more development, the habitats of the Ridge with their many endemic plant and animal species have come under increasing pressure. The most widespread kind of natural habitat on the Ridge is called scrub. Scrub consists mainly of scrub oak and shrubs adapted to dry, low nutrient conditions. Scrub contains a disproportionate share of the threatened and endangered plant and animal species on the Ridge. These include the Florida scrub jay, the gopher tortoise, the sand skink, the scrub lizard and the Florida mouse. Natural scrub habitat is rapidly disappearing from the Ridge. By 1981, about 64 percent of the scrub on the southern Ridge had been severely altered. Along the central Ridge, losses were even greater--about 74 percent. By 1991, losses were estimated to be approximately 70 to 90 percent. Sandhill is the rarest natural community in the County. It is the historic high pineland community dominated by long leaf pines. (A vegetative community known as southern sandhill is not dominated by long leaf pines and is not true sandhill; it actually is a type of scrub.) Only about one percent of the original true sandhill still existed as of March, 1994. Although altered by fragmentation and fire suppression, the remaining sandhill still supports several important endemic plant and animal species, such as the gopher tortoise, Sherman's fox squirrel, and a plant called the clasping warea. A type of natural habitat unique to Highlands County portion of the Ridge is cutthroat seep. Cutthroat seeps occur where groundwater near and at surface elevation flows rapidly through areas usually adjacent to true wetlands, keeping the area wet but not ponded. These areas are dominated by cutthoat grasses, which require periodic burning to maintain their dominance. Drainage related to development lowers the water table and otherwise interrupts the needed lateral flow of water, allowing the invasion of woody species. In addition, development makes fire management more problematic and, in some cases, impossible. The most effective protection of cutthroat seep requires preservation of relatively large parcels, approximately ten acres or more. Smaller parcels are harder to fire manage. In addition, smaller parcels could be subjected to inadvertent hydrologic interruption from nearby development. There are about 18 plant species that occur only on the Ridge. Forty plant species occur only in Florida scrub and occur on the Ridge. Twenty-two plants on the Ridge are federally listed as either endangered or threatened. The Florida scrub jay is a federally listed endangered species that occurs only in peninsular Florida. The scrub jay also serves as an indicator species--management for scrub jay habitat will meet the habitat requirements of most other species that occur in scrub habitat. Scrub jays require the presence of scrub oak, as well as bare ground and low growing scrub. Periodic fire is necessary to maintain this mix. Scrub jays are very territorial. The tend to stay on one specific site. Scrub jays are monogamous, pairing to breed for life. Juveniles help feed and protect younger birds before dispersing to find a territory of their own. Dispersal distance typically is less than a mile. Each family group occupies a relatively large area--approximately 25 acres. Large sites are necessary to maintain a viable scrub jay population. Population viability models indicate that 150-200 individuals are needed for a population to persist for 200 years. Using this standard, fewer than ten potentially secure populations of scrub jay exist. It is believed that as much as 750 acres of scrub oak may be required to give a such a population a 90 percent chance of survival for 100 years. Development destroys scrub jay habitat. In addition, nearby development not only makes fire management difficult, if not impossible, it increases scrub jay mortality from feral cats and dogs and from motor vehicles. In the Base Documents supporting the Highlands County Plan, as amended, the County recognized the unique and sensitive natural resource represented by the Lake Wales Ridge. The Base Documents acknowledged that, before the comprehensive plan was adopted, the County did not have a "formal mechanism to examine the effects of proposed development and agricultural uses on natural vegetation and wildlife." The Base Documents also acknowledged that the Ridge required "more stringent controls and greater incentives for resource protection." Conservation, Use, and Protection of Natural Resources Natural Vegetation and Wildlife Subelement [sic] Highlands County has adopted, as the Natural Vegetation and Wildlife Subelement [sic] of its Natural Resources Element, Objective 3 providing that the County shall protect and acquire native vegetative communities which are endemic to Central Florida and shall restrict activities known to adversely affect the endangered and threatened species and their habitat. Under that Objective, Highlands County has adopted a number of Policies. Highlands County's approach to conservation, use, and protection of natural resources under Objective 3 and its policies is to identify, evaluate, and protect natural resources on a site-by-site basis. (County Exhibit 6, Pages NRE-10 through NRE-25, inclusive, and County Exhibit 9) The review procedures prepared by Petitioner's representative, Kris Delaney, for the Central Florida Regional Planning Council (CFRPC) also used a site-by-site approach. (Petitioner Exhibit 56) Kris Delaney is the immediate past president of HEC and was described by Petitioner's counsel as its main representative. Highlands County's approach to evaluation of natural resources also is comparable to the review processes adopted by federal statute and state law for the protection of threatened and endangered species. Site specific evaluation was necessary due to the variety of protected species needs, site conditions, and legal constraints. Under Policy 3.1, A., Highlands County has adopted a number of source documents to identify endangered or threatened species, including species of special concern. Under Policy 3.1, B., Highlands County has adopted a number of documents as guidelines for establishing mitigation, on-site protection, and remedial actions for the protection of habitats and listed species in the County's land development regulations. Under Policy 3.2, Highlands County adopted a Conservation Overlay Map series to be used as a general indicator for the presence of xeric uplands, wetlands, cutthroat seeps, historical and archeological resources, cones of influence for potable wells, and aquifer recharge areas. (See Findings 52-59, infra, for a detailed description and explanation of these maps.) Whenever a particular site is in an area where one of those resource categories is mapped on the Conservation Overlay Map series or are otherwise known to occur, Policy 3.3 of the Natural Resources Element requires the applicant to submit to the Highlands County Planning Department a preliminary field investigation report prepared by a County-approved professional, firm, government agency, or institution. If that field investigation determines that any of those resources actually exist on the site, an Environmental Impact Report is required of the applicant. Those Environmental Impact Reports (EIR's) must also be prepared by a County approved-professional, firm, agency, or institution. Policy 3.3, E., specifies the content of the EIR: (1) maps and a description of natural vegetative communities occurring on the proposed development site in terms of their habitat functions and significance; (2) maps and a description of the aforementioned natural resource categories which may be impacted by the proposed development; (3) an assessment of the potential impacts which would be sustained by a natural resource as a result of the proposed development; (4) an evaluation of water quality inputs and outputs; recommendations for appropriate mitigation and on-site protection measures; recommended land maintenance and management procedures to assure the continued viability or function of the natural resource after development; and a list of agencies which may have permit requirements pertaining to the proposed development. Under Policy 3.3, F., the application package and the EIR are transmitted for review and comment to the agencies listed in the Environmental Impact Report as having permit requirements and to the Highlands County Natural Resources Advisory Committee. Responsive comments and recommendations which are received are forwarded to the County employee or board having decision-making authority concerning the applicable permit and included in the County records pertaining to the project. Under Policy 3.3, G., after receiving the application packet, the EIR, and the comments and recommendations from other permitting agencies and the Highlands County Natural Resources Advisory Committee, the County evaluates and determines the permit conditions required to: (1) protect and preserve the water quality or natural functions of flood plains and drainage ways, potable water wells, and wetlands; (2) protect and preserve the function of native vegetative communities which are endemic to Central Florida or the habitats of endangered species, threatened species, or species of special concern; (3) preserve and protect historical and archeological resources; (4) establish measures to protect life and property from flood hazard; and (5) establish land maintenance and management procedures for the natural resource to assure its continued viability or function after development. Policy 3.3, G., further requires that the County's final development order must be conditioned upon adequate avoidance, preservation, mitigation, or remedial actions for the protection of the aforementioned resources and must be consistent with the wetlands, flood plain, aquifer recharge, water quality, and cultural resource protection measures set forth within the policies of the Comprehensive Plan. It also requires the County to require that the necessary state and local permits be obtained as a condition of approval for the project's final development order. In determining the appropriate conditions for the County's final development order, Policy 3.3, B., states that avoidance and preservation of the resource shall be the first choice for protecting the resource. Acquisition, conservation easements or dedications, and site design methods (including clustering development to the portion of the site where the resource does not exist or, if that is not possible, to the least environmentally sensitive portion of the site), are among the methods allowed to accomplish that purpose. Appropriate buffers between the development and the resource are also required. Policy 3.3, C., also provides that a mitigation fee may be imposed by the Board of County Commissioners for small, isolated tracts containing less significant habitat and that the mitigation fees collected would be used to fund off-site mitigation in order that preservation of equal or greater habitat type, function, and quantity can be achieved. This is consistent with the "Review Procedure for Special Habits: Xeric Uplands" prepared by Kris Delaney for the CFRPC which provides that "[L]ocal government may wish to establish procedural relationship with such agencies and, based on locally determined criteria, a minimum parcel size requiring review." Similarly, Policy 3.4 provides an environmental mitigation fee alternative for construction of single-family residences on preexisting lots of records to the extent consistent with state and federal regulations. These mitigation fee provisions are consistent with existing state and federal programs for protection of threatened and endangered species and species of special concern (Petitioner Exhibit 53, Pages 58 through 60; Petitioner Exhibit 56, Page 25, Level III, G.1 (cont.); and Petitioner Exhibit 78, Page 16) Policy 3.15 identifies several mitigation options which are consistent with those found in the "Review Procedure for Special Habitats: Xeric Uplands" prepared by Kris Delaney for the CFRPC. Policy 3.5, A., requires the County to institute an ongoing program to define, identify, and conserve its native vegetative communities and the habitats of endangered or threatened species and species of special concern and states that the conservation program must include the following implementation measures: (1) acquisition of lands using public funds and grants; (2) lease of land; (3) tax abatement; (4) land swaps and transfers of title; (5) establishment of conservation or open space easements; (6) density bonuses for cluster development; (7) density bonuses for development that preserves habitat and avoids impact on endangered or threatened species, including species of special concern; (8) density transfers for conservation set-asides to buildable portions of sites; and (9) mitigation fees and mitigation fee credits. Under Policy 3.5, B., the County has established as the top priority of its conservation program working with public and private agencies to acquire and preserve in their natural state: (1) scrub or sand hill habitats (xeric uplands); (2) endemic populations of endangered or threatened species, including species of special concern; (3) wetlands, cutthroat grass seeps, and estuaries; (4) important aquifer recharge areas; and (5) unique scenic or natural resources. In Policy 3.6, the County specifically references the "Review Procedure for Special Habitats: Xeric Uplands" prepared by Kris Delaney for the CFRPC as the model for its development review process for coordination with local, state, and federal regulatory agencies. Policy 3.6(g) specifically provides for coordination with local, state, and federal agencies concerning native vegetative communities or habitat areas spanning more than one local jurisdiction. Policy 3.7 establishes funding sources for the County's conservation trust fund and requires that the fund be used exclusively for the acquisition of the priorities listed in Policy 3.5, B., or the enhancement of other publicly- owned conservation-valued lands, as determined by the Board of County Commissioners. To discourage clearing of land prior to environmental review, the County adopted Policy 3.13, which requires property owners to obtain a County land clearing permit prior to land clearing. Issuance of the land clearing permit is conditioned upon completion of the environmental review process adopted in Policy 3.3. If property is cleared without a County land clearing permit, no development orders may be issued for that site for a period of three years after such clearing. Under Policy 3.13, C., of the Plan, as amended, no land clearing permit is required for "any agricultural activity not requiring a Highlands County land development order conducted by a lawfully operating and bona fide agricultural operation" on property "designated by the Future Land Use Map as either General or Urban Agriculture . . .." Under the policy, such operations are "encouraged to implement a Soil and Water Conservation District approved conservation plan, including the use of Best Management Practices, as applicable to the specific area being cleared, and [to secure all other permits required by State and federal agencies exercising jurisdiction over the natural resources referred to in Policy 3.2 and found on said property]." [Emphasis added.] In addition, Policy 3.9 of the Natural Resources Element provides for encouraging agricultural uses which are compatible with wildlife protection and water quality outputs, implementation of erosion control and Best Management Practices. Highlands County also has adopted many other policies in the Natural Vegetation and Wildlife Subelement [sic] of the Natural Resources Element for the protection of natural resources, including: Policy 3.8, providing for the removal and control of exotic plant species; Policy 3.10, requiring the County to incorporate the protection and conservation measures adopted under the Natural Vegetation and Wildlife Subelement [sic] into all County surface water management plans, public works projects and infrastructure improvement plans; Policy 3.11, encouraging the expansion of wildlife/greenbelt corridors; Policy 3.12, encouraging the creation of parks for the protection, preservation, and conservation of natural resources; Policy 3.14, requiring setbacks from environmentally sensitive land; Policy 3.16, providing for transfers of density and density bonuses to encourage preservation of environmentally sensitive lands and listed species through the use of planned unit developments; Policies 3.17 through 3.19, providing for the appointment, functions and responsibilities of the Highlands County Natural Resource Advisory Committee; Policy 3.20, providing for the adoption of a five-year acreage target for acquisition of natural resource lands; and Policy 3.21, providing for a buffer around Highlands Hammock State Park, publicly-owned conservation lands, and conservation lands being considered for acquisition with public funds. Wetlands Subelement [sic] Highlands County has adopted, as the Wetlands Subelement [sic] of its Natural Resources Element, Objective 4 providing for the protection of wetlands systems and their ecological functions to ensure their long term, economic, environmental, and recreational value and to encourage restoration of wetlands systems to a functional condition. Under Objective 4 of the Natural Resources Element, Highlands County has adopted a number of policies to protect wetlands systems. Policy 4.1 provides for the protection of ecological functions of wetlands systems by the County through actions such as supporting the restoration of wetlands systems, protecting the natural functions and hydrology of wetlands systems by buffering against incompatible land uses and mitigating development impacts, providing for clustering and open space buffering, intergovernmental cooperation, and the acquisition of wetlands systems, including cutthroat grass seeps. In Policy 4.2, Highlands County adopted definitions for wetlands and cutthroat seeps which are required to be mapped according to Policies 3.2 and 4.3. In Policies 4.4 through 4.7, the County provided for the adoption of land development regulations which: encourage the restoration of wetlands systems; provide that development orders in cutthroat seeps be conditioned upon the issuance of wetlands permits by the Army Corps of Engineers, the Florida Department of Environmental Protection, and the South and Southwest Florida Water Management Districts, as their jurisdictions apply, as a condition of approval of the project's final development order or land clearing permit; prevent the net loss or alteration of wetlands on a County-wide basis; and require conservation easements and delineation on final plats for wetland and cutthroat grass seep areas used for mitigation purposes. State and Federal Protections State and federal permitting processes protect threatened and endangered species and species of special concern found in Highlands County. See Conclusions 125-130 and 140-147, infra. The review processes required to obtain the state and federal permits pertaining to threatened and endangered species require site-specific review, comparable to obtaining environmental clearance from the County under Policy 3.3 of the Natural Resources Element. In view of the diversity of threatened and endangered species and species of special concern and their habitat needs, variations in quantity and quality of resources existing on site, and statutory and constitutional property rights protection, the County has chosen not to establish fixed set asides for every resource under every circumstance on a County-wide basis. By including in its permitting process notification to federal and state agencies having permitting responsibilities, Highlands County will be providing valuable assistance to state and federal environmental protection by bringing those agencies in at an early stage of the review process. Moreover, the County's requirements that the necessary federal, state, and local permits be obtained as a condition of approval for a project's final development order will assist those federal and state agencies in enforcing environmental permits in Highlands County. Measuring Success of Protection Measures Extensive work by federal and state agencies has been devoted to identifying and studying threatened and endangered species, both plant and animal. Threatened and endangered species and the habitats necessary for their survival exist throughout the State of Florida. Listed species found in Highlands County are also found in other areas of the State of Florida. The amount and land-cover types of conservation areas have been extensively studied for the entire State of Florida. The percentage of conservation lands in Highlands County (9.4 percent) exceeds the statewide median for the portion of conservation lands within individual counties (8.6 percent). The land cover types for the entire State of Florida have been identified and quantified by location and number of acres and the amounts of those habitats in conservation lands have also been determined. Likewise, for every county, the land cover types have been located, identified, mapped, and acreage determined for "natural" upland cover types, "natural" wetland cover types, and "disturbed" cover types. The "natural" upland cover type category includes coastal strand, dry prairie, pine lands, sand pine scrub, sand hill, xeric oak scrub, mixed hardwood-pine forest, hardwood hammocks and forest, and tropical hard wood hammocks. "Natural" wetland cover types include coastal salt marshes, fresh water marsh and wet prairie, cypress swamp, mixed hardwood swamp, bay swamp, shrub swamp, mangrove swamp, and bottomland hardwood forest. "Disturbed" cover types include grass land and agriculture, shrub and bush land, exotic plant communities and barren and urban land. Open water areas were also identified, located, mapped, and the acreage areas determined. The amounts of land in each of those land cover categories has been tabulated by county and for the State as a whole. The amount of land in each of those categories located in conservation lands has also been tabulated for each county and for the State as a whole. The tabulation for land cover types for Highlands County and the amount of conservation lands for each cover type are as follows: "Natural" upland cover types - coastal strand (0/0), dry prairie (427/112), pine lands (167/41), sand pine scrub (14/3), sand hill (0/0), xeric scrub oak (112/12), mixed hardwood-pine forest (4/0), hardwood hammocks and forests (46/5), tropical hardwood hammocks (0/0); "Natural" wetland cover types - coastal salt marshes (0/0), freshwater marsh and wet prairie (129/34), cypress swamp (21/8), mixed hardwood swamp (41/5), bay swamp (17/0), shrub swamp (21/5), mangrove swamp (0/0), bottomland hardwood forest (0/0); Open water (202/1); and "Disturbed" cover types - grass land and agriculture (1086/15), shrub and brush land (271/18), exotic plant communities (0/0), barren and urban land (307/11) Within the parenthesis above, the first number represents the total area in square kilometers and the second number represents the conservation lands in that category, also in square kilometers. There are approximately 247 acres per square kilometer. For Highlands County, these identified land cover types cover 2,866 square kilometers of which, 270.8 square kilometers are conservation lands. In addition to mapping those important habitat areas in each county in the State of Florida, the threatened and endangered species and species of special concern found in those habitat areas have also been identified. Those habitat areas and the threatened and endangered species and species of special concern which they support have been specifically identified and mapped for Highlands County. Since the land cover types in Highlands County have been identified, located, mapped, and quantified and the threatened and endangered species and species of special concern, both plant and animal, supported by those land cover types have been identified, Highlands County has the ability to objectively measure the success of its adopted Goals, Policies, and Objectives in protecting natural resources. Data and Analysis and Maps Eugene Engman, AICP, a planner/economist, was the principal author of the conservation element and Base Documents of supporting data and analysis for the County's 1991 Plan. The Base Documents indicate extensive analysis of the County's natural resources, including: surface waters; floodplains; mineral deposits; areas with erosion problems; and fisheries, wildlife habitat and vegetative communities. The Conservation Overlay Maps The Base Documents also contain a "methodology for conservation designation," that applies to areas identified as areas of outstanding natural resources and to areas containing special habitat (high quality scrub habitat, cutthroat grass seeps with predominantly native vegetation, and forested wetlands on and near the Ridge). With respect to the latter, it was not Engman's intention to map all vegetative communities on and near the Ridge; oak hammock and palm hammock, for example, was not mapped. It also was not Engman's intention to map the entire County. Engman did not believe that mapping of high quality scrub habitats, seeps and wetland forest was required, but he mapped them at no charge to the County to enable the County to better protect endangered species and other resources on and near the Ridge where most the special habitat and most development coincided. Following the methodology, Engman and his colleagues prepared the Resource Base Maps--County Exhibit 40. They consisted of 27 USDA Soil Conservation Service (SCS) quadrangle maps, two with acetate overlays. The quad maps themselves show some resources indicated by a separate legend available from the SCS. In addition, Engman and his colleagues indicated the location of scrub habitats, seeps and wetland forest through use of an additional legend they wrote on the quad maps. Some legends applied to more than one quad map. In addition to the SCS quad maps themselves, Engman and his colleagues used the Soil Survey field notes of Lew Carter of the SCS, 1985 infrared aerial photographs, and local knowledge of the Dr. James Layne of the Archbold Research Station, Lew Carter of the USDA Soil Conservation Service, Mike Sawyer of the Florida Division of Forestry, and County sources. The Base Documents also contains a Generalized Soils Map which references as its source "USDA/SCS, Soil Survey of Highlands County, Florida, July, 1989." The Base Documents also contained two maps at the scale of one inch equals three miles--one mapping outstanding natural resources, and the other mapping special habitat. These two maps were then combined into a third map at the scale of one inch equals five miles. This third map was designated the Conservation Overlay Map in the Base Documents. Each quarter section (160 acres) of the County that contained any of the identified resources depicted on the Resource Base Maps was depicted as "Conservation" on the Conservation Overlay Map. The Conservation Overlay Map advised that: "This map is for comprehensive planning purposes only. Specific locations are identifiable on the Resource Base Maps located in the Office of the County Planning Director." No duplicates or copies of the Resource Base Maps--County Exhibit 40-- were made before the final hearing in this case. They were available to the public during the development of the 1991 Plan, and they were forwarded to the County Planning Department when Engman's work was finished. There, they remained available for use by the County Planning Department in implementing the Plan, and remained available for public inspection, except for a period of approximately one year when they were misplaced and could not be located. FLU-54, the Conservation Overlay Map in the Future Land Use Map series, is the same map that is contained in the Base Documents as the Conservation Overlay Map. The Future Land Use Map Series In addition to FLU-54, the Future Land Use Map Series in the adopted plan, as amended through 1993, contained a Future Land Use Map Set of three large maps--a one inch equals two miles base map, and two one inch equals one/half mile maps--together with several letter-size maps at one inch equals five miles (one is at one inch equals four miles), which are FLU-55 through FLU- 62. The adopted plan, as amended through 1994, contained the same text as the plan as amended through 1993, along with an updated Future Land Use Map Set of six large color sheets. The base map is at a scale of one inch equals two miles and is a colorized version of the base map contained in the 1993 version of the plan; the other five maps are color insets from the base map at a scale of one inch equals one quarter mile. The rest of the Future Land Use Map Series is the same as in the Plan as amended through 1993. In addition to the FLU-54 Conservation Overlay Map, the future land use map series included: a Generalized Soils Map which identifies its source as "USDA/SCS, Soil Survey of Highlands County, Florida, July, 1989"; Highland's County Peat Deposits, whose source is "Adley Associates, Inc. September, 1988"; Wetlands 600, whose legend identifies "wetlands" and "ridge," and whose source is "Adley Associates, Inc. September, 1988"; Floodplains, whose legend identifies "floodplains" and "ridge," and whose source is "Adley Associates, Inc. September, 1988"; Water and Canal Map 500, whose legend identifies "generalized interim well protection zones (cones of influence) for potable water supply wells" and whose source is "Adley Associates, Inc., Highlands County Building and Zoning Department and DER," and which is dated December, 1990; Future Traffic Circulation Map State Roads, which depicts various types of roads and whose source is "Highlands County Engineering Department and FDOT"; Future Traffic Circulation Map County Roads, which depicts various types of roads and whose source is "Highlands Co. Engineering Department and FDOT"; Future Traffic Circulation Map County Roads, which depicts various types of roads and whose source is "Highlands Co. Engineering Dept. (9/88) and FDOT (11/90)"; and Modified Community Parks which depicts existing and proposed parks and "existing urban land use" and whose source is "Adley Associates, Inc. April, 1990". FLU-55, the Generalized Soils Map, was prepared using the 1989 USDA SCS Soil Survey. Major field work for the USDA/SCS Soil Survey was completed in 1986. It is the same map as the Generalized Soils Map contained in the Base Documents. FLU-57 maps wetland features which are not depicted on either the Resource Base Maps (County Exhibit 40) or the Conservation Overlay Map. The 1989 USDA SCS Soil Survey was used to identify wetlands on FLU-57. HEC's Contentions HEC contended that the maps in the Plan, as amended, were deficient. It became apparent during the course of the final hearing that HEC considered the FLU-54 Conservation Overlay Map in the Plan, as amended, to be the only map pertinent to the designation of conservation lands. HEC contended that FLU-54 is too small, not clear and legible enough, and inadequate for its purposes. It appeared that HEC learned of the existence of the Resource Base Maps (County Exhibit 40) during the final hearing. HEC contended that the Resource Base Maps were deficient because they were not based on the appropriate and best available data. As a result, HEC contended, the Base Resource Maps and FLU-54 Conservation Overlay Map "missed" some significant resources. Kris Delaney quickly reviewed the Resource Base Maps during the course of the final hearing and testified that on the Frostproof, Lake Arbuckle, Sebring, and Fort Kissimmee quad sheets some "significant areas of native vegetation were not shown on the mylar overlays." Delaney's observations regarding the five allegedly-inaccurate mylar quad map overlays were made with reference to the USDA Soil Conservation Service Soil Survey and what he believed was a wetland symbol on the underlying quad map. But it is not clear that Delaney understood the legend to the Resource Base Maps. Furthermore, he was not offered as an expert in photogrammetry, geography, or surveying, and the specifics of his personal knowledge of the areas in dispute were not made clear. Another HEC witness, Dr. Menges, testified to his opinion that the Base Resource Maps and FLU-54 Conservation Overlay Map did not map all native vegetative communities throughout the County. He testified that, to map native vegetative communities on a species-specific basis, Steve Christman's 1988 report for the Florida Game and Fresh Water Fish Commission would provide the best available data. (He also mentioned data from the Florida Natural Areas Inventory, but it was not clear that those data were not used or how available those data were.) However, it was not clear from the evidence that the Christman report was not used as a data source. In addition, Menges conceded that "the primary source for the distribution of (native vegetative) communities" (in Highlands County) would be the "Soil Conservation Service Survey map," and it is clear that the County's consultants used this data source, together with other soil survey information and aerial photography, as was appropriate. It should not be surprising that the Base Resource Maps and FLU-54 Conservation Overlay Map did not map all native vegetative communities throughout the County. As previously, stated, the effort was limited to high quality scrub habitat, cutthroat grass seeps with predominantly native vegetation, and forested wetlands on and near the Ridge. There was no intention to map all native vegetative communities throughout the County. Regardless of the alleged deficiencies with the Resource Base Maps and the FLU-54 Conservation Overlay Map, HEC did not take into account all of the maps in the Future Land Use Map series in contending that the mapping was deficient. HEC did not recognize that Policy 3.2 provides for the use of the "adopted Conservation Overlap Map series contained in the Future Land Use Element" as the "general indicator" for the resources described in the policy. The Future Land Use Map series includes not only FLU-54 and the Resource Base Maps (County Exhibit 40) but also: FLU-55 (the Generalized Soils Map), FLU-57 (the Wetlands 600 map), FLU-58 (the Floodplains map), and FLU-59 (the Water and Canals Map 500). HEC also did not recognize that the environmental clearance procedures under Policies 3.3 and 3.13 are triggered not only if the presence of the resources described in Policy 3.2 is mapped on the Conservation Overlay Map (which includes not only FLU-54, but also the Resource Base Maps), but also if they are known to occur by reference to any of the maps in the Future Land Use Map series, or are otherwise known to occur. The references acknowledged by the County in Policy 3.1 can serve as the source of knowledge of where the resources described in Policy 3.2 occur. It is not beyond debate that these sources of information, taken together, are adequate for purposes of indicating the existence of the resources described in Policy 3.2 and triggering environmental clearance review under Policy 3.3. HEC did not establish beyond debate that the County did not use appropriate or the best available data, that the County did not apply the data in a professional manner, or that the Plan, as amended, did not react to the data in an appropriate way. Future Land Use Element Residential Land Use Density In Agricultural Land Use Categories HEC presented no credible testimony or evidence to substantiate its allegation that the land use densities for agriculture and urban agriculture encourage "urban sprawl" or are not supported by adequate data. No expert testimony in land use planning was offered, although HEC had identified such potential experts on its witness list. The Base Documents stated that agricultural density was at 1 unit/acre prior to the adoption of the Plan and recommended that the density be decreased to 1 unit/10 acres. The draft of the Base Documents recommended a density of 1 unit/ 5 acres. The Plan established the General Agriculture land use category as the predominant land use for rural areas. It has the lowest development potential of all adopted land use categories. The General Agriculture land use category has a density range of one unit per ten acres. The Urban Agriculture land use category was established as a transitional zone between urbanized and rural lands. The Urban Agriculture land use category has a density range of one unit per five acres. (County Exhibit 6, Pages FLU-6 and FLU-7 There was no evidence to prove that lesser densities are required to discourage urban sprawl, to protect natural resources, to protect agricultural lands, or for any other reason. Population Accommodation Data and Analysis HEC did not present any population accommodation analysis. There was no competent evidence presented in this case as to the population accommodated in the year 2000 under either the Plan as amended and adopted on March 2, 1994, or the Plan as amended and adopted on September 15, 1993. HEC pointed to a projection in the Housing Element in the County's Plan indicating a need for 10,075 new housing units to accommodate 16,977 new residents by the year 2000. HEC also pointed to data and analysis indicating that there are approximately 108,000 residential lots in existing subdivisions of 100 lots or more in the County that potentially could be developed to accommodate new housing units. But HEC did not establish that it is realistic to project maximum development in those subdivisions at one unit per lot; nor did HEC establish the extent of vested rights to development in those subdivisions. Protection of Water Quality and Quantity The Base Documents contain extensive data and analysis of County geology and soils, including water supply considerations, and recharge. Aquifer recharge in Highlands County occurs primarily on the Lake Wales Ridge. Contamination of groundwater has been documented from hazardous waste associated with landfills, agricultural use of the pesticides EDB (ethylene dibromide) and Bromicil, and leaking underground storage tanks. Of these, only the agricultural pesticide use is documented to have impacted potable water supplies. EDB, the primary source of contamination noted, has not been used since 1983. While the presence of Bromacil is also noted, the number of wells is not mentioned. Moreover, the evidence does not mention a single health- related case. Where EDB contamination has been found, the State of Florida has paid the cost of connecting to public water supplies or installing carbon filters. There is no evidence that stormwater management activities has caused groundwater contamination. Highlands County has adopted a number of objectives and policies in both the Infrastructure Element and the Natural Resources Element of the Plan, as amended, intended to protect potable water wells, conserve potable water resources, and reduce the risk of groundwater contamination. Objective 6 under the Potable Water Subelement [sic] of the Infrastructure Element is to ensure public health by protecting the water quality of potable wells. Among the policies adopted to implement that objective is Policy 6.4, adopting stringent restrictions on activities within a 600 feet radius around public potable water wells. Highlands County also adopted Objective 7 and Policies 7.1 through 7.3 under the Potable Water Subelement [sic] to establish minimum design and construction requirements for all potable water wells to protect and assure delivery of potable water. Highlands County has also adopted a number of other objectives and policies under the Natural Resources Element intended to protect groundwater quality, including: prohibiting the location of hazardous waste treatment facilities in the County; requiring cooperation with the DEP "DRASTIC" program; prohibiting discharges of untreated stormwater and waste material into underground formations; adopting stormwater quality and quantity standards; mapping wellhead protection zones; and encouraging implementation of best management practices for agricultural operations in the County. HEC did not prove beyond fair debate that, taken together, the Goals, Objectives, and Policies of the Plan, as amended, do not ensure the protection and conservation of potable water supplies.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Community Affairs enter a final order determining that the Highlands County Plan adopted through County Ordinance 91- 1, as amended by County Ordinances 93-16 and 94-1, is "in compliance." DONE and ENTERED this 15th day of October, 1996, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 15th day of October, 1996.
The Issue The issue in the case is whether the Hillsborough County comprehensive plan is not in compliance for the reasons set forth in the petitions of Sierra Club, Inc.
Findings Of Fact Background Hillsborough County adopted its comprehensive plan on July 12, 1989. The County adopted Plan Amendments 90-I, 90-II, and 91-I on August 6, 1990, December 18, 1990, and August 28, 1991, respectively. The plan as so amended is referred to as the Plan. 3/ The Plan is the subject of these cases. The Plan is accompanied by data and analysis. The data and analysis of greatest significance are contained in the two- volume compilation of the Plan and other portions of Sierra Club Exhibit 1, which is the Plan and supporting data and analysis. Sierra Club Exhibit 1, which was prepared by Hillsborough County, includes background documents organized by elements, as well as oversized maps. Unless indicated to the contrary, the oversized maps are approximately 24" by 21" and are drawn on a scale of 1"= 2 miles. Many of the oversized maps bear numbers. Reference to such oversized maps shall be as follows: "Oversized Map [number]." Data and analysis from Sierra Club Exhibit 1 shall be referred to as "Data and Analysis." The Plan consists largely of goals, objectives, and policies. In addition to such operative provisions, Hillsborough County also adopted, as part of the operative provisions of the Plan, other sections contained in the two- volume compilation of the Plan. For example, each element of the Plan relevant to the present cases includes operative provisions under sections entitled, "Implementation" and "Definitions." Other important operative provisions are sections entitled "Land Use Plan Categories" and "Legal Status of the Plan" in the Future Land Use Element and "Costs and Revisions by Type of Public Facility," "Programs to Ensure Implementation," and "Requirements for Capital Improvements Implementation" in the Capital Improvements Element. The Department of Community Affairs (DCA) filed a petition on September 20, 1989, alleging that the original plan was not in compliance with the growth management law. This petition initiated DOAH Case No. 89-5157GM. Various parties challenging the plan intervened in DOAH Case No. 89- 5157GM. The Sierra Club, Inc. (Sierra Club) filed its petition to intervene on December 8, 1989. The petition incorporates the allegations of DCA and alleges additional grounds for a determination of noncompliance. As a result of the execution of a settlement agreement, DOAH Case No. 89-5157GM was abated. After Hillsborough County adopted settlement amendments on August 6, 1990, DCA determined that the plan amendments were in compliance. On or about September 21, 1990, DCA issued a Notice of Intent, which was published on or about September 23. On October 12, 1990, Sierra Club filed a petition challenging the plan amendments adopted in connection with the settlement agreement. This petition initiated DOAH Case No. 90- 6639GM. The allegations are the same as those raised by Sierra Club in DOAH Case No. 89-5157GM in its Second Amended Petition- in-Intervention, which was filed October 17, 1990. By Order entered October 30, 1990, DOAH Case Nos. 89- 5157GM and 90- 6639GM were consolidated for hearing. On April 15, 1991, Big Bend Area Group, Inc. (Big Bend) filed a petition to intervene to challenge the plan. A Second Amended Motion for Leave to Intervene was granted. Despite the allegations of noncompliance, Big Bend's proposed recommended order requests that the Plan be determined to be in compliance. Sierra Club and Big Bend each has members who reside in Hillsborough County. Each party submitted the required oral or written objections during the relevant review and adoption period. The County conducted the required hearings, gave adequate notice of the hearings, and otherwise substantially complied with the requirements of public participation. Data and Analysis General Hillsborough County is located on the Gulf Coast. The western boundary of the County abuts Tampa Bay and Pinellas County. Pasco County and a small part of Polk County are to the north, Polk County is to the east, and Manatee County is to the south. The only incorporated municipalities in Hillsborough County are Tampa, Temple Terrace, and Plant City. Tampa is at the north end of Tampa Bay and extends through the westcentral part of the County almost to the Pasco County line. Temple Terrace abuts the northeast boundary of Tampa. About 14 miles east of Tampa is Plant City, which is in the northeast part of Hillsborough County. The two cities are linked by Interstate (I-) 4, which runs from Daytona Beach to Tampa. In Tampa, I-4 intersects with I-275, which crosses upper Tampa Bay, runs south through Pinellas County, and spans the mouth of Tampa Bay before entering Manatee County. I-75 also runs through Hillsborough County. From the Pasco County line, where I-275 divides and proceeds southwest into downtown Tampa, I-75 runs generally due south. The path of I-75 lies just east of downtown, where the road turns southwest at a point north of the Little Manatee River. From there, I-75 parallels the shoreline of Tampa Bay until entering Manatee County. Other important roads in Hillsborough County include SR 60, which runs east-west through the center of the County and connects Tampa and Clearwater. US 301 runs along the Hillsborough River in the northeast part of the County, and then turns due south midway between Temple Terrace on the west and Lake Thonotosassa on the east. At this point, US 301 crosses I- 75 and runs due south, recrossing I-75 about three miles north of the Alafia River and just south of SR 60. US 41 runs due south from the Pasco County line into the center of Tampa and then turns east, before continuing south, parallel to the shoreline, varying from one-half to three miles inland from Tampa Bay. Natural Resources General The Data and Analysis accompanying the Conservation and Aquifer Recharge Element (CARE) describe the County's natural resources, past land use practices, and planning challenges: Hillsborough County, by virtue of its subtropical climate and variable hydrology and geology, supports a rich and diverse complement of natural resources. The County borders the largest estuary in the State, Tampa Bay . . .. The County is underlain by the Floridan aquifer, the largest and highest quality potable water aquifer in the State, as well as by some of the richest phosphate deposits in the world. The karst topography of the County has created a mosaic of solution sinks and depressions which contain a wide variety of wetland flora and fauna, while the higher well-drained elevations support rare xeric hammocks and scrub habitat. Over the past century, however, development has slowly destroyed and degraded the rich natural resources of the County. The unregulated filling of wetlands, discharge of pollutants, mining of phosphate deposits, clearing of forests, dredging of bay bottoms, channelizing of streams and rivers, and overpumping of groundwater supplies has irretrievably destroyed or altered much of the original natural resource base. Environmental legislation passed at the federal, state, regional and local levels over the past two decades has done much to stem the tide of this destruction; however, advance planning and further safeguards will be needed to ensure the preservation and conservation of the County's remaining natural resources for future generations. Hillsborough County is experiencing a high rate of population growth. Between 1970 and 1980, Hillsborough County's population grew from an estimated 490,265 to 646,939, an increase of 32 percent This population size ranked fourth among counties in the state. . . . Future population projections for Hillsborough County . . . generally show that the population of Hillsborough County may continue to increase, if the high estimate occurs, or may level off if the lower estimate proves more accurate. . . . Hillsborough County's population is concentrated primarily within the cities of Tampa and Temple Terrace. However, during the five year period of 1980 through 1985, the majority of the population growth for the County has taken place away from these areas. Population has decreased in portions of the City of Tampa and increased in the previously less populated portions of the County. The Future Land Use Element of the [Plan] identifies the major center of future growth as the I-75 corridor. If the upper population projections are realized over the next 15 years, directed growth into this area will threaten the integrity of many of the County's most valuable natural resources, including the three major river corridors, areas of high aquifer recharge/contamination potential, and sensitive estuarine wetlands. The [CARE] is needed to identify these potential problems and to set forth a plan and policy direction for ensuring environmental protection and orderly economic growth under all projected population scenarios. CARE, pages 2-3. Acknowledging the environmental degradation that has resulted from land use planning that has traditionally ignored natural features of the land and water systems, the Data and Analysis state: In past decades, land use decisions were based primarily upon socio-economic and demographic factors, with little considera- tion given to preserving or conserving the natural attributes of the land. As a result, urban land uses were often allowed to replace or permanently alter environmentally sensitive lands and natural systems. With a better understanding of the ecological impacts of land uses, it has become clear that the natural carrying capacity of the land must be carefully considered in land use decisions if the natural attributes and functions of the environment are to be maintained for future generations. Policies and regulations that appropriately preserve or conserve valuable natural resources while allowing for orderly economic growth are needed. CARE, page 73. 2. Tampa Bay Estuarine System The Tampa Bay estuary is a semi-enclosed coastal body of water having a free connection with the Gulf of Mexico and within which sea water is measurably diluted with freshwater derived from land drainage. ... [T]he Tampa Bay estuary is a zone of transition between fresh and salt water with unique and valuable ecological characteristics. Coastal Management and Port (Coastal) Element, page 13. The estuarine system includes tidal freshwater habitats as well as mangroves, salt marshes, and seagrass meadows along the shallow bottom and estuarine fringe. The functions of the estuarine system are described as follows: Because of their unique physical and chemical properties, estuaries are among the most biologically diverse and productive ecosystems in the world. Tidal wetland vegetation at the headwaters of estuaries trap silt and absorb excess nutrients resulting from land drainage, thus buffering the coastal ecosystem somewhat from upland sources of pollution. Tidal wetland vegetation also protects upland areas by stabilizing coastal sediments and preventing erosion from storm events. The real importance of estuarine plant communities such as mangrove forests, salt marshes, and seagrass beds lies in the vital functions they perform in the aquatic ecosystem. First and foremost is their role in converting sunlight and nutrients into food usable by marine animals, thus forming the base of the aquatic food chain. . . . Although relatively little of this plant material is eaten directly by higher animals, it is broken down into detritus by micro- organisms and consumed by small crustaceans and other animals which are, in turn, eaten by larger fishes and so on up the food web . . . . In addition to serving as a food source, estuarine wetland vegetation provides shelter and nursery areas for the young of many economically important species such as shrimp, seatrout, mullet, and red drum (redfish). . . . [I]t is estimated that nearly 98% of the most economically important fisheries species taken along the Gulf of Mexico coast are directly dependent upon estuarine habitat during some portion of their life cycle. . . . Coastal Element, pages 13-14. Florida's largest open water estuary, Tampa Bay covers about 400 square miles. Coastal Element Figure 6 depicts the Tampa Bay estuary, including its subdivisions. Old Tampa Bay separates Tampa and Pinellas County and forms the shoreline of northwest Hillsborough County. Hillsborough Bay extends from Tampa to Apollo Beach and forms the shoreline of central Hillsborough County, as well as the northern part of south Hillsborough County. The Hillsborough and Alafia Rivers empty into Hillsborough Bay, which joins McKay Bay at Tampa. Middle Tampa Bay, which forms the shoreline of most of south Hillsborough, runs from the southern ends of Old Tampa Bay and Hillsborough Bay down to the southern ends of Pinellas and Hillsborough Counties. The Little Manatee River empties into Middle Tampa Bay. A variety of nonfish wildlife is dependent upon the waters of Tampa Bay. In addition to the 100-200 bottlenose dolphin in Tampa Bay, as many as 55 West Indian manatees reside in the bay in the winter, congregating around industrial thermal discharges. The largest group--42--was found at the mouth of the Alafia River, which is the only designated State Manatee Sanctuary in Tampa Bay. About one-third of the laughing gull population in the southeastern United States breeds in the Tampa Bay region, as does nearly one-third of the brown pelicans in Florida. McKay Bay is an important feeding area for a variety of birds. General water quality in Tampa Bay is "good to excellent," but is "declining" in Old Tampa Bay and "undesirable" in Hillsborough Bay, including McKay Bay. Coastal Element, page 15. Both Hillsborough Bay and Old Tampa Bay receive little tidal flushing due to natural conditions, so they are not "particularly well suited for the discharge of municipal and industrial wastes, and . . . the continued flow of freshwater to Tampa Bay, especially Hillsborough Bay, is essential to maintain good circulation and flushing." Coastal Element, page 19. The water quality in Middle Tampa Bay ranges from "fair to good," but is periodically influenced by water from Hillsborough Bay. Water quality in and near the Cockroach Bay Aquatic Preserve is "excellent or good," except for occasional "fair to poor" conditions due to seasonal discharges from the Little Manatee River or periodically "poor" conditions due to malfunctioning septic tanks near Cockroach Bay. Coastal Element, page 15. "One of the most pristine biologically productive areas remaining in Tampa Bay," Cockroach Bay is part of the Cockroach Bay Aquatic Preserve, which is shown in Coastal Element Figure 17. Coastal Element, page 48. The only aquatic preserve in Hillsborough County, Cockroach Bay Aquatic Preserve runs from submerged lands along the Little Manatee River upstream to US 301. From the mouth of the Little Manatee River, the preserve runs along the Tampa Bay shoreline past Cockroach Bay, which is about three miles south of the mouth of the Little Manatee River, to the Manatee County line. Noting that the Governor and Cabinet approved the Cockroach Bay Aquatic Preserve Management Plan in 1987, the Data and Analysis acknowledge that "[s]uccessful implementation of this plan depends upon the cooperation of Hillsborough County." Coastal Element, page 48. The decline of water quality in Tampa Bay has had a predictably devastating effect upon commercially valuable fish in the area. "[O]nce the State's most productive and diverse estuarine system" with a diversity and abundance of marine life [in the 1960's] not exceeded by any other estuary between the Chesapeake Bay and the Laguna Madre of Texas, . . . [t]he productivity of Tampa Bay in terms of commercially valuable fisheries has . . . declined dramatically in recent decades due to man's influence on the Bay. Coastal Element, page 21. According to Coastal Element Figure 15, shellfish landings in Tampa Bay have declined from 20 million pounds in the mid 1950's to early 1960's to two million pounds in 1978. Finfish landings have declined from a high of 4.5 million pounds in 1964 to 1.75 million pounds in 1978. Five economically important shellfish species occur in Tampa Bay: bait shrimp, stone crab, blue crab, oysters, and quahog clams. By the mid 1950's, degraded water quality had eliminated from the estuary the bay scallop, which had formerly flourished in these estuarine waters. By 1970, degraded water quality "essentially eliminated" commercial harvesting of oysters, which had accounted for 500,000 pounds annually at the turn of last century. Coastal Element, page 22. Poor water quality has left bait shrimp and stone crabs as the only remaining commercially viable shellfish left in Tampa Bay. Areas approved for shellfishing are restricted to lower Tampa Bay where better flushing takes place. The Cockroach Bay Aquatic Preserve is conditionally approved, but "has been closed periodically due to coliform contamination from nearby septic systems and is being considered for permanent closure by the Florida Department of Natural Resources." Coastal Element, page 22. The majority of the recreational fish landings in Tampa Bay consist of spotted seatrout, red drum, and snook. These fish are also declining in numbers. Many species of birds in Tampa Bay have suffered population declines due in part to red tides, parasite outbreaks, dredge and fill operations, pesticide use, and oil spills. However, the reddish egret and roseate spoonbill have recently returned to Tampa Bay. Accompanying the decline in animal species has been a decline in estuarine plant species, such as seagrass meadows. The "catastrophic loss of seagrasses in Tampa Bay," which is attributable primarily to water quality degradation, is taking place at accelerating rates. About 81% of the seagrass meadows, which once covered 76,500 acres of Tampa Bay bottom, have been lost. Coastal Element, page 20. Tampa Bay is undergoing eutrophication. The process of eutrophication, or increasing concentrations of nutrients, has already led to algal blooms, noxious odors, decreases in water clarity, declines in dissolved oxygen, and periodic fish kills. Excessive nutrient levels have resulted in phytoplankton blooms in the water column and excessive epiphytic growth of macroalgae on the leaves of seagrasses, leaving insufficient sunlight for the growth and reproduction of seagrasses that help trap nutrients. The destruction of seagrasses is further hastened by widespread increases in water column turbidity caused by harbor- and channel-deepening projects, which, with boat prop dredging, also destroy seagrass. The loss of critical nutrient-trapping vegetation has simultaneously taken place in wetlands and upland adjacent to Tampa Bay, such as in the destruction of as much as 44% of the original emergent wetlands, which comprise salt marshes and mangrove forests. In the process of development, these wetlands have been dredged and filled, thereby removing the intertidal substrata necessary for these vegetative communities. Likewise, the loss of freshwater wetlands along rivers and streams has deprived the estuarine system of useful organic matter and filtration. Dredging and filling activities have dramatically changed the features of the Tampa Bay estuarine system. The extent of the system itself has been reduced by 3.6%, or 13.15 square miles, primarily by filling shallow tidal wetlands for the development of causeways, residences, power plants, and port facilities. Port development is responsible for about 60% of the reduction of the estuary due to the construction of channels, filled sites, and disposal sites for dredged materials. Dredge and fill projects routinely permitted in the 1950's and 1960's are no longer permitted. But expansion and maintenance of the Port of Tampa will generate annually about one million cubic yards of dredged material from the channel and port. Present disposal sites may be exhausted in 25 years, and the Data and Analysis recommend that the dredged material be considered for wetlands mitigation and restoration. The primary factors contributing to the eutrophic degradation of the water quality of Tampa Bay are, in addition to dredging and filling, the discharge of inadequately treated domestic and industrial wastewater and inadequately treated urban and agricultural runoff. In 1980, point sources contributed 2.35 and 3.58 million pounds of phosphorous and nitrogen, respectively, to Tampa Bay. The Alafia River carried 75% of the water contributed by permitted point discharges because the Alafia absorbs discharges from extensive phosphate mining operations in Polk County. Not surprisingly, the highest concentrations of organic carbon and nitrogen and total phosphate are in the sediments at the mouth of the Alafia River. But domestic wastewater treatment plants discharging directly into Tampa Bay accounted for 78% and 84% of the annual phosphorous and nitrogen loadings, respectively. The degraded water quality in Old Tampa Bay and especially Hillsborough Bay is due largely to sewage and industrial wastes. Old Tampa Bay continues to suffer from the discharge of inadequately treated domestic waste. However, the water quality in Hillsborough Bay improved substantially after over $100 million was spent to upgrade Tampa's Hookers Point sewage treatment facility in 1979 from primary to advanced or tertiary treatment. Only one of the six County regional wastewater treatment facilities fails to meet advanced water treatment standards, but "numerous subregional and interim plants" fail to meet these standards. Coastal Element, page 24. According to the Data and Analysis, passage of the Grizzle-Figg bill in 1986 "currently requires that all sewage treatment plants discharging into Tampa Bay attain advanced wastewater treatment standards." Coastal Element, page 24. Upon compliance with the Grizzle-Figg law, nutrient loadings into Tampa Bay will decrease and "a net reduction . . . is possible as interim package plants are ultimately phased out or upgraded." Id. Regarding wastewater discharges generally, including industrial wastewater, a major reduction in nutrient loadings since 1980 has been realized from the use of alternative effluent disposal methods (such as spray irrigation and deep-well injection), municipal and industrial water reuse, upgrading of treatment capabilities, and phosphate land reclamation projects. Nutrient loadings from stormwater runoff will "most likely be a more intractable problem" than inadequately treated domestic wastewater. Coastal Element, page 24. Runoff from streets, parking lots, and lawns may contribute up to 25% of the biochemical oxygen demand, 35% of the suspended solids, and 15% of the nitrogen loading. Referring to state rules regulating stormwater, 4/ the Data and Analysis anticipate that the state- imposed standards on stormwater runoff will become more stringent, so there should not be significant increases in stormwater nutrient loadings into the bay. However: little can be done to reduce current loading rates, as retrofitting of stormwater treatment facilities is most likely economically prohibitive. Retrofitting will probably only occur on a piecemeal basis as redevelopment occurs in previously urbanized areas. Coastal Element, page 24. Unsound land use practices introducing high levels of nutrients into Tampa Bay exacerbate background conditions that predate either all or recent development activity. The Data and Analysis caution that "there may always be a significant reservoir of nitrogen and phosphorous in Bay sediments to contribute to water quality problems in upper Tampa Bay." Coastal Element, page 16. The Data and Analysis explain: even with advanced wastewater treatment and improved stormwater management, localized pockets of polluted sediments in the Bay may still release excessive nutrients into the water column and cause water quality problems. The ultimate solution to this problem may involve the removal of excessively enriched sediments by dredging or the capping of polluted sediments with clean fill material. Coastal Element, page 24. Other unsound land use practices, such as the diversion of river flows and structural drainage improvements, greatly impact Tampa Bay in another respect not directly related to the eutrophication process. The Tampa Bay estuary and its dependent fish and shellfish rely upon the freshwater flow into the bay. Areas of the estuary with the lowest salinity, as well as low- salinity tidal marshes, are often the most productive nursery habitat for many marine and estuary species. The timing of the freshwater infusions are naturally correlated to the spawning periods of the fish. The salinity regimes of Tampa Bay may be disturbed by upstream demands for freshwater and the alternating excessive and insufficient flows of freshwater due to structural drainage improvements that hasten the natural drainage of uplands immediately following major storm events, leaving less water to drain slowly to the bay during relatively drier periods. Reviewing "numerous studies" that, for the past 30 years, "have documented the deterioration of water quality and habitat values of the estuary," the Data and Analysis attribute the environmental degradation of Tampa Bay to: direct habitat destruction from dredging and filling, and the hardening of shorelines for coastal development; degradation of water quality and eutrophication resulting from the discharge of municipal and industrial effluents, and stormwater runoff; and the reduction of natural freshwater inputs due to the impoundment and withdrawals from rivers and streams. Coastal Element, page 48. Concluding that "piecemeal urbanization" around Tampa Bay has resulted in its "broadscale environmental degradation," the Data and Analysis warn: "Without proper management and the proper balance between public and private uses, Tampa Bay could become a major liability rather than the area's main asset." Coastal Element, page 48. The Data and Analysis advise that the protection and restoration of the Tampa Bay estuary requires a "comprehensive, coordinated and holistic management approach." Id. 3. Rivers Covering 1072 square miles, Hillsborough County comprises five physiographic provinces, which reflect topography and soils. The physiographic provinces are Coastal Swamps, Gulf Coast Lowlands, Zephyrhills Gap, Polk Upland, and a small portion of the DeSoto Plain. Elevations range from sea level in the Coastal Swamps and Gulf Coast Lowlands, which separate the Polk Upland from the Tampa Bay estuary, to 160 feet above sea level in the Polk Upland at the Polk County line. CARE Figure 4 displays the topographic contours of Hillsborough County. The County's major rivers and drainage features are, from north to south, the Hillsborough, Alafia, and Little Manatee Rivers. Each of these rivers empties into Tampa Bay. The three major river basins together with six smaller basins transport, on average, more than 1.2 billion gallons per day of freshwater into Tampa Bay. This is almost 80% of the freshwater flow into the bay. CARE Figure 11 shows the major rivers and drainage basins in Hillsborough County. A fourth river, the Palm River, once drained lands between the Hillsborough and Alafia Rivers. Emptying into McKay Bay, the Palm River was "completely channelized and controlled" by 1970 and is now known as the Tampa Bypass Canal. Coastal Element, page 18. The Hillsborough River begins in the Green Swamp and flows southwest through Tampa and into the bay. Traveling nearly 54 miles, the river is supplied by many artesian springs, which supply the river with water from the Floridan aquifer. The natural drainage basin of the river is 690 square miles, including 120 square miles in Hillsborough County. The upper Hillsborough River is a Class I water, which means that it is suitable as a source of potable water. The lower Hillsborough River is a Class III waterbody, which means that it is suitable for propagation of fish and wildlife. The part of the river passing through the Hillsborough River State Park in the northeast area of the County is also designated as an Outstanding Florida Water. Two dams span the Hillsborough River. The upper dam is just north and east of I-75 near Fletcher Avenue. This dam, which is under the jurisdiction of the Southwest Florida Water Management District, is used for flood-control purposes. The lower dam is at 30th Street in Tampa and is operated by the City of Tampa to form a reservoir from which potable water is taken. Flow of the river ranges from 9.5 billion gallons per day during the wet season to under 30 million gallons per day at the end of the spring dry season. The average flow into Tampa's reservoir is 368 million gallons per day. Of the 55.5 linear miles of shoreline (both banks) along the Hillsborough River in the unincorporated County, 17.6 miles are private and 37.9 miles are public. The predominant land uses are rural, agricultural, and conservation. The riverbanks are in their native state with no seawalls and few boat docks or ramps, except for canoe access. The Alafia and Little Manatee Rivers originate in the Polk Upland and receive water from widely branching tributaries. The Alafia River begins in Polk County and runs west to Gibsonton and into the bay at a point about five miles south of Tampa. The Alafia drains a 420 square mile drainage basin. The average flow at the mouth of the river is million gallons per day. In general, the water quality of the Alafia River is "poor." CARE, page 13. A Class III waterbody, the river's entire corridor is rural or suburban, and much of its original floodplain wetlands are still intact. Phosphate mining has damaged the quality of the river's headwaters. The Little Manatee River begins in southeast Hillsborough County and flows west by Ruskin and into the bay at a point about ten miles south of Gibsonton. The Little Manatee River drains about 225 square miles. The average flow of the Little Manatee River is over 150 million gallons per day. Florida Power and Light pumps water from the river to supply an off-stream reservoir for cooling a thermonuclear power plant. The water quality of the Little Manatee River is "generally good." CARE, page 14. The river, which is a Class III waterbody, is designated an Outstanding Florida Water for its western two-thirds, with the portion of the river west of US 301 designated as an aquatic preserve. The river is more pristine than the other County rivers due to its "relatively unimpacted floodplains, swamps and tributaries." Id. However, the river is threatened by phosphate mining in its upper reaches. Rich deposits of phosphate matrix lie near the surface along the river's bed, and the easy extraction makes these areas extremely attractive for future mining. Id. In contrast to the well-developed stream systems of northeast, central, and southern Hillsborough County, northwest Hillsborough County has relatively few such streams. Rain in this area rapidly infiltrates the surficial soils through shallow creeks and solution features. The Data and Analysis concede that "surface water quality in Hillsborough County has been degraded due to a variety of unregulated water uses and adjacent land uses." CARE, page 54. The most prominent sources of water pollution have been discharges of wastewater, mining operations, and urban and agricultural runoff. The Data and Analysis recommend "[b]etter compliance with existing point and non-point source and stormwater regulations" and the consideration of "more stringent regulations for septic tank discharges." Id. 4. Floodplains and Drainage Over 30% of Hillsborough County is within the 100 year floodplain. The floodplains, which have been mapped throughout the County by the Federal Emergency Management Agency, are depicted on Oversized Map 9. Major portions of the 100 year floodplain cover the coastal high hazard area 5/ and the Hillsborough River valley in northeast Hillsborough County. Floodplains cover perhaps a quarter of northwest Hillsborough County, including an extensive area north of Tampa where I-275 and I-75 join at the Pasco County line. Considerable floodplains encompass the corridors of the Alafia River and its major tributary and the Little Manatee River, all of which extend into phosphate mining areas of east- central and southeast Hillsborough County. The County has adopted a flood-control ordinance. But this ordinance "does not provide the County with a comprehensive flood plain management program . . . for maintaining wildlife habitat protection, aquifer recharge protection and water quality benefits." CARE, page 20. The Data and Analysis discuss the floodplains and their functions: Lands that are naturally subject to flooding serve valuable functions in the regional hydrologic and ecological system. Flood- prone lands provide temporary natural storage of runoff from upland areas and overflow from water bodies. By temporarily detaining surface water, flood-prone lands help to regulate the timing, velocity and levels of flood discharges and enable the recharge of groundwater resources. In addition, flood- prone lands help to maintain water quality and provide habitat that is vital to the sustenance of fish and wildlife populations. Those lands that are most frequently flooded, i.e., wetlands, are the most important in terms of providing these functions, but less frequently flooded areas are also important for handling more severe floods and providing other natural benefits. The maintenance of natural storage is extremely important for regional water management. . . . During times of abundant rainfall, . . . rivers and lakes overflow their normal banks and occupy the floodplain. The floodplain provides storage for this additional water. Even a greater volume of water is stored in areas outside of the floodplain of established lakes and rivers. Cypress heads, swamps, marshes and isolated topographic depressions provide a large portion of the natural storage in this area. . . . By temporarily storing and retarding the flow of flood waters, flood-prone lands also help to regulate the velocity and timing of flood discharges. Runoff in southwest Florida is usually intercepted by wetlands or topographic depressions. When these areas are full, the overflow moves slowly through shallow swales and linear depressions toward streams and water bodies. Obstructions to flow such as logs, rocks, trees, undergrowth and meanders in the watercourse reduce the rate of flow and thereby help to minimize the level and velocity of downstream flooding. Flood-prone areas are also important sites for groundwater recharge. The water table aquifer is directly dependent on the levels of water in such low-lying areas as cypress heads, sinkholes, swales and floodplains. When these areas are flooded, they may help recharge the water table aquifer. Then, during dry periods, the water table aquifer may provide part or all of the base flow to rivers and streams. Water stored in the water table also serves to recharge the Floridan aquifer by percolating downward through breaches in impermeable layers. ... Another important benefit of natural flood- prone lands is in the maintenance of water quality. Water tends to travel slowly across flooded lands, giving suspended sediments time to settle and thereby clarifying water before it enters or returns to a watercourse or water body. . . . The stems, leaves and branches of plants in flooded areas, together with flooded soils, provide an enormous surface area for biological and chemical processes. Micro- organisms on these surfaces initiate complex chemical reactions involving nitrogen, phosphorus, heavy metals and other pollutants. The roots of indigenous plants also absorb and remove nutrients from the water. Flood-prone lands, particularly wetlands, thus act like a giant biological filter. . . . Flood-prone lands also play a regional ecological role that depends upon periodic inundation. Wetlands and bottomland hardwood forest are the most biologically diverse and productive areas in Florida, other than estuaries. They support a wide variety of plants, which provide vital habitat for . . . game and fur-bearing animals . . . and for such endangered and threatened species, such as the wood stork. Much of the food for game fish comes from wetlands and floodplains along the shores of rivers and lakes. Juvenile fish, in particular, tend to hide and feed in these areas. There would be drastic reductions in the number of species, the number of fish per acre and the pounds of fish per acre if these areas were eliminated. Periodic inundation, alternating with periods of relative dryness, is vital to the maintenance of these ecological systems. Flood-prone lands tend to have rich, organic soils with a high capacity to retain water. The micro-organisms and plant communities associated with these soils support a complex food chain. High water tables and regular flooding are necessary to maintain organic soils. Regular flooding is needed to bring additional rich sediments into flooded areas and make them accessible to foraging fish. In addition, flood water transports out of flooded lands a load of detritus, nutrients, minerals and sediments that is vital to maintaining the productivity of estuarine systems. CARE, pages 14-15. Describing the consequences of poor land use planning in floodplains, the Data and Analysis continue: Improperly designed and executed land development interferes with the natural functions described above. Water resources and related land resources can thereby be degraded and unnecessary expense, loss of property, personal injury and loss of life can result. Building in flood-prone areas is particularly unwise. When floods recur, which is inevitable, considerable damage to houses, roads, utilities and other structures results. . . . Roadbeds are often weakened, undermined or washed away by flood waters. Electrical, telephone, and cable television lines are seldom designed to be submerged. Flood waters can enter sewage lines, causing them to overflow and contaminate an area or overload the capacity of treatment facilities. . . . . . . The storage and detention capacity of a watershed can also be reduced by drainage improvements, such as clearing and straightening natural watercourses, constructing new channels, and creating impervious surfaces. . . . * * * Reducing the capacity of a watershed to detain and store flood waters has several harmful effects on water and related resources, in addition to those associated with increased flooding. Variations in the flow of rivers and streams become more accentuated. Flood discharges peak more quickly and at higher elevations, but less water flows during dry periods and they extend for longer periods of time. The effects of both drought and flood are thus enhanced. Consumptive water suppliers, riverine aquatic life and estuarine processes, all of which depend on natural flow, may be disrupted. Recharge of groundwater is reduced by draining surface water from recharge areas or by covering them with impervious surfaces. The total amount of runoff discharged is thus increased and the amount of water stored in aquifers and available for consumptive use or to maintain streams flows is correspondingly diminished. Development of natural storage and detention areas also tends to cause degradation of water quality. Wetlands, vegetated swales and floodplain forests act as giant biological filters. If these filters are destroyed or bypassed, pollutants are discharged directly into open water systems. CARE, pages 15-16. As typified by its flood-control ordinance, the County has traditionally pursued the structural approach to floodplain management and drainage generally. This approach consists of building systems of channels, dams, levees, and other structures to hold back flood waters or rapidly carry them elsewhere. However, the Data and Analysis identify serious shortcomings in the structural approach to floodplain management and drainage. In addition to problems involving cost and relocating flood damage, the structural approach substantially degrades other values and functions of flood-prone lands and natural watercourses. Water quality protection, groundwater recharge, maintenance of base flows, estuarine salinity regulation, detrital production and export, fish and wildlife habitat, and other natural resource functions are frequently impaired by the construction of structural works. CARE, page 17. The Data and Analysis set forth a number of guidelines for a comprehensive floodplain management program "to prevent flood damage and minimize interference with the beneficial functioning of flood-prone lands." CARE, page 17. The first guideline to floodplain management is to avoid building in areas likely to be damaged by flooding. The Data and Analysis recommend the use of the ten year floodplain for this purpose. The second guideline to floodplain management is to avoid interfering with the beneficial functions of floodprone lands, which are "storage, conveyance, groundwater recharge, maintenance of minimum flows and levels, water quality maintenance and habitat for fish and wildlife." CARE, page 18. In a discussion not limited to the ten year floodplain, the Data and Analysis advise: Buildings, fill, roads and other structures that displace or obstruct the flow of surface waters should not be located in flood-prone areas. In addition, these areas should generally not be drained and their natural vegetation should be maintained. Id. With respect to the environmental benefits inherent in the second guideline, the Data and Analysis discuss each of the functions separately. For storage functions, the Data and Analysis note that floodwaters are stored by floodplains contiguous to water bodies and wetlands considerably removed from water bodies, but connected to them by cypress strands, marshy sloughs, and the underground water table. Thus, "[i]n order to preserve storage, it is necessary to prevent building in these storage areas, diverting [building] instead to upland sites." CARE, page 18. For conveyance functions, the Data and Analysis observe that obstructions, such as buildings and roads, to the flow of floodwater cause flooding upstream of the obstruction. Thus, "[i]n order to preserve the conveyance capacity of flood-prone lands it is necessary to restrict building in these areas." CARE, page 18-19. For groundwater recharge functions, the Data and Analysis relate recharge to storage and conveyance. If water that would otherwise percolate downward into groundwater is blocked by impervious surfaces, removed by drainage works, or displaced by fill, the water contributes to increased flooding downstream. "Filling of flood-prone lands or drainage of them should therefore be restricted." CARE, page 19. For minimum flows and levels, the Data and Analysis recognize that the management of maximum flows--i.e., floodwaters--"is integrally related to minimum flows." By increasing floodwater flows, such as by reducing natural storage and conveyance through structural flood control, "there will be less water in storage in wetlands and groundwater to supply minimum flows." The reduction of minimum flows and levels adversely impacts "navigation, recreation, water supply, dilution of pollutants, estuarine systems and fish and wildlife." CARE, page 19. For water quality, the Data and Analysis acknowledge the "major role" of frequently flooded lands in water quality. Pollutants are removed from storage waters when they are stored in natural floodplains or wetlands. "Cleaning, filling or draining these areas will cause degradation of water quality and should be restricted." CARE, page 19. For fish and wildlife habitat, the Data and Analysis note the importance of floodprone lands as habitat. Maintenance of this function "frequently depends on maintenance of the natural hydrologic regime or is consistent with maintenance of the area's hydrologic values." CARE, page 19. The third guideline to floodplain management is to avoid alterations of the natural rate, quantity, and pattern of surface waters. Applicable to both "flood-prone lands and more upland sites," this guideline advises that the "rate, volume, timing and location of discharge of surface water should generally not be altered from predevelopment conditions." In this case, surface water includes floodwater. CARE, page 19. Acknowledging the increasing stress upon wetlands and floodplains from "increased growth pressure in the more marginally developable portions of the County," the Data and Analysis advise that: [w]here wetland or floodplain encroachment is unavoidable, a scientifically defensible and effective compensatory mechanism is needed to ensure than no net loss of wetland acreage occurs. Where feasible, previously altered wetlands should be restored or recreated to increase overall viable wetland acreage. CARE, page 56. The Data and Analysis set a level of service standard for stormwater, but only in terms of existing, structural stormwater management facilities, such as channels, canals, and ditches. The standard relates to the quantity but not quality of stormwater runoff. The stormwater level of service standard thus illustrates the traditional structural approach to drainage that ignores water quality, groundwater recharge, base flow, salinity requirements, detrital food supplies, and habitat values. Dealing strictly with how fast and how much floodwater can be conveyed, ultimately to Tampa Bay, the stormwater standard describes the rainfall event that a particular stormwater facility, such as a ditch, can accommodate without causing floodwaters to rise above a specified level. The selected rainfall event is expressed in terms of frequency and duration, such as the 10 year/24 hour duration storm event. The level of flooding is expressed by degree. Level A, which is the most restrictive, means "no significant street flooding." Level B is "no major residential yard flooding." Acknowledging that the level of service standard for stormwater facilities "consists primarily of attempting to minimize and alleviate flooding . . . in developed areas . . .," the Introduction to the Stormwater Management (Stormwater) Element promises: the overall [Stormwater Management] Program will be expanded to include not only the quantity aspects, but the quality aspects of stormwater runoff. Stormwater Element, page 18. The Data and Analysis likewise agree that the qualitative aspect of stormwater runoff must be addressed: Much attention has, in recent years, been focused on the quality aspects of stormwater management regulations relative to the establishment of regulations and corresponding design criteria for new development. The application of these regulations must continue in order to minimize the potential for "new" water quality degradation, and the design criteria must be refined to increase the effectiveness of treatment systems as technology advances. However, existing water quality problems may not be correctable without the effective maintenance of existing stormwater treatment systems, and perhaps more importantly, without the retrofitting of older public and private stormwater management systems with stormwater management technologies. . . . The use of wetlands should be promoted as a natural means of providing stormwater treatment, and the direct discharge of untreated stormwater runoff to the Florida Aquifer must be minimized. Stormwater Element, page 20. 5. Soils The soils in Hillsborough County are depicted in CARE Figure 9 and Oversized Map 10. In addition to mine pits and dumps, which are located south and east of Plant City, the maps show that the County soils are poorly drained to very poorly drained, moderately well drained to poorly drained, and well drained. The largest area of well-drained soils lies east of I-75 from US 301, which is south of the Hillsborough River, to just north of the Alafia River. The two other areas of well- drained soils are an area east of Tampa and south of Temple Terrace and the Little Manatee River valley upstream to US 301. The soils surrounding the Alafia River and its major tributaries are predominantly poorly and very poorly drained, as are the soils at the upper end of the Little Manatee River. The entire coastal fringe of the County abutting the east side of Tampa Bay is also poorly and very poorly drained for a distance of about one mile inland, as is the coastal fringe between Tampa and Pinellas County. Other poor to very poorly drained areas include several areas of northwest Hillsborough County, an area in north-central Hillsborough County where I-75 and I-275 join, the Hillsborough River corridor, and an L-shaped area straddling Big Bend Road between I-75 and US 301. Except in extreme cases, such as wetland soils, soil limitations can generally be alleviated for development purposes. Moderate limitations require more extensive alterations to the soils than do minor limitations. "Severe limitations may require the removal of the natural material and replacement with a more suitable soil type." CARE, page 7. However: [t]he use of septic systems for the treatment and disposal of sewage effluent may . . . be significantly limited by site specific soil conditions. The location of septic systems in improper soils may result in several undesirable effects. If the soils have wetness and poor permeability then the discharged effluent will not percolate properly and may runoff into, and contaminate, adjacent surface waters. The Cockroach Bay Aquatic Preserve has been closed to shellfishing numerous times in recent years due to improperly sited and maintained septic tanks in the Ruskin area. CARE, page 7. Conversely, "[i]n areas of excessively well-drained sand, septic effluent can migrate too rapidly for purification processes to occur, and carry contaminants into the groundwater supply." CARE, page 8. The surficial, intermediate, and Floridan aquifers are all subject to contamination by this means. 6. Geology Southeast Hillsborough County contains significant phosphate deposits. This area is the northwest extent of the Central Florida Phosphate District, which is located in Hillsborough, Manatee, Polk, and Hardee Counties. CARE Figure 10 and Oversized Map 8 show that phosphate mines are located in southeast Hillsborough County, at the headwaters of the Little Manatee River and a major tributary of the Alafia River. CARE Figure 10 and Oversized Map 8 show another phosphate mining area in eastcentral Hillsborough County adjacent to the headwaters of the Alafia River or another of its major tributaries. Providing "hundreds" of jobs in the Tampa Bay area in mining, shipping, marketing, and processing, the phosphate industry produces a "net capital inflow to Hillsborough County," although the text fails to identify what cost items associated with phosphate mining are netted. CARE, page 8. CARE Table 2 indicates that there are five major phosphate mining operations in the County involving 26,326 mineable acres and 5772 mined acres. Due to current market conditions, the only active mine accounts for 2510 mineable acres, 2890 mined acres, and 6933 total acres. The Data and Analysis warn: "phosphate mining severely complicates land use considerations in the central and southeast portions of the County. Large areas of known deposits are held by private companies for future mining." Id. In addition to the space demanded by clay settling ponds, which may consume a one square mile area for a single mine, a typically mining operation involves the "complete disruption" of up to 400 acres annually. The disruption involves the "on-site natural vegetation, drainage, and soil characteristics." Id. Mining may also result in the drawdown of groundwater supplies in the vicinity. Phosphate mining exposes the leach zone, which contains the greatest concentration of uranium. This process increases the risk that the radioactive material will enter the air or water. Heavy water demands in the mining process involve the removal of water from the surficial aquifer and return of used water, possibly with excessive radionuclides, to the Floridan aquifer. After the strip mining operations are completed: Reclamation and restoration of mined lands is extremely important for long-term land use planning in Hillsborough County. The vast acreages of mined trenches and slime ponds are virtually useless for long time periods unless effective reclamation measures are implemented. CARE, page 9. Recent reclamation techniques include surface contouring, use of original topsoil and vegetation types, and restoration of original drainage patterns. The Florida Department of Natural Resources and Hillsborough County both impose reclamation requirements. Noting the economic benefits bestowed on the Tampa Bay region from phosphate mining, the Data and Analysis nevertheless observe: the relatively unregulated mining industry of the past was also responsible for significant environmental damage, including the destruction of wetlands and floodplains, and the siltation and eutrophication of rivers and streams. In addition, large tracts of land have been committed to the maintenance of clay settling ponds and non-productive reclamation areas. Improved State and local regulation of the phosphate industry in recent years has reduced operational impacts on the environment. However, more effective and productive methods of reclamation, and greater enforcement of reclamation requirements, may be needed. CARE, page 63. CARE Figure 10 and Oversized Map 8 depict the location of numerous sand mines and shell mines, as well as one peat mine. Limestone deposits in the northeast part of Hillsborough County are near the surface and may be the subject of future limestone mining for use as road base, fill, concrete, and asphalt. Another mineral present in commercially significant quantities is sand. In areas underlain by limestone deposits, sinkholes may form, especially in northern and eastern Hillsborough County. The collapse of the limestone formation, which results in the sinkhole, is associated with reduced water tables. "Sinkhole areas are generally unsuitable for development." CARE, page 6. CARE Figure 8 depicts areas of observed and potential sinkhole development. 7. Groundwater The three aquifer systems present in most of Hillsborough County are the surficial, intermediate, and Floridan. The Floridan aquifer is the most productive freshwater aquifer system in Hillsborough County. The surficial aquifer runs through most of Hillsborough County. The water table in the County generally follows the topography, and groundwater flow is west and south. The average depth to the water table is five feet. Fluctuating seasonally less than five feet, the water table is lowest in April or May and highest in September. The surficial aquifer supplies the least amount of water in the County. An intermediate aquifer system forms from the Alafia River basin south in the County. The top of the intermediate aquifer is near sea level, and the intermediate aquifer system thickens to about 200 feet near the Manatee County line. The water quality in the intermediate aquifer is generally good and is primarily used for domestic water supply in extreme south Hillsborough County. The aquifer is most productive in the east and south part of the County, although the phosphate mines in southeast Hillsborough County use the intermediate aquifer as the injection zone for dewatering surficial deposits. The most suitable areas for groundwater development are the extreme northeast and southeast areas of the County. The Floridan aquifer is the major source of groundwater in the County. About 175 million gallons per day of the total 178.2 million gallons per day of groundwater withdrawals in Hillsborough County are taken from the Floridan aquifer. The top of the aquifer ranges from near land surface in the north part of the County to about 200 feet below sea level in the south part of the County. The aquifer thickness ranges from less than 1000 feet in the north part of the County to more than 1200 feet in the south part of the County. The water of the Floridan aquifer is more mineralized than the water of the surficial or intermediate aquifer. Concentrations of chloride exceed 250 mg/l near the coast, but are less than 25 mg/l in east and southeast Hillsborough County. Of the total groundwater withdrawn in the County, about 58%, or 103.3 million gallons per day, is devoted to agriculture. Other uses include 43.7 million gallons per day for public supply, 21.2 million gallons per day for industrial use, and 6.5 million gallons per day for rural use. 8. Aquifer Recharge Aquifer recharge is the "replenishment of water in an aquifer system." CARE, page 23. Hillsborough County contains no areas of high natural aquifer recharge. Areas of high natural aquifer recharge, where annual recharge rates range from 10-20 inches per year, are rare in Florida, representing only about 15% of the entire state. In terms of natural recharge rates, the County contains areas characterized by very low and very low to moderate recharge. The areas of very low to moderate recharge, in which the annual recharge rate is from 2-10 inches, are depicted in CARE Figure 14 and cover the northwest corner of the County, smaller areas in the northcentral and northeast areas of the County, and a large area in northeast Hillsborough County. The large recharge area in the northeast part of the County corresponds to the 100 year floodplain associated with the Hillsborough River basin; this is the largest contiguous 100 year floodplain in the County. Despite the absence of high natural recharge areas, the County contains areas highly susceptible to contamination of the Floridan aquifer. CARE Figure 15 shows three highly susceptible areas. One of these areas is the north half of northwest Hillsborough County. This area contains wellfields located along Gunn Highway and SR 597. The easternmost extent of this area is just east of the intersection of I-275 and I-75. Most of the highly susceptible areas in the northwest part of the County are in areas of very low to moderate natural groundwater recharge. Another area highly susceptible to contamination of the Floridan aquifer is in northeast Hillsborough County, north of I-4 and mostly east of US 301. This area includes two mining areas, but neither is a phosphate mine. The third area of high susceptibility to contamination of the Floridan aquifer runs from an area between Lake Thonotosassa and Plant City southwest through the parcels designated Light Industrial north of Gibsonton. Although similar contamination maps for the surficial and intermediate aquifer systems were not included, the surficial aquifer is highly susceptible to contamination due largely to its proximity to the surface, and the intermediate aquifer is less susceptible to contamination. The Data and Analysis warn that "[d]evelopment in areas of high recharge/contamination potential may . . . pose unacceptable threats to the long-term water quantity and quality within the aquifer system." CARE, page 58. Potable water supplies are also threatened by "the proliferation of improperly sited, constructed and maintained septic tanks." Id. CARE Figure 16 displays potential sources of contamination of the groundwater and surface water. The only potential source of contamination in the recharge area associated with the Hillsborough River basin is an active landfill situated at the southern edge of the recharge area, just southeast of Lake Thonotosassa. However, three active landfills and seven sewage treatment plants have been situated in the large recharge area in the northwest corner of the County, although these ten sites are southwest of existing public supply wells. 9. Sanitary Sewer An unnumbered oversized map entitled Hillsborough County Wastewater Element shows existing and proposed wastewater service areas and collection lines; the projected facilities are shown as of 1994 and 2010. Oversized Map 3, which is entitled Potable Water and Wastewater Facilities, also shows existing and proposed wastewater service areas as of 1994 and 2010. Sanitary Sewerage (Sewer) Element Figure 1 depicts the same information on a smaller scale, although the earlier year of projection is 1995, not 1994. Another unnumbered oversized map accompanying the Plan shows the location of domestic wastewater treatment plants, but the date of the map is omitted. In terms of the existing collection and conveyance system, Sewer Element Figure 1 depicts a central sewer system considerably more proposed than existing in the area south of the Alafia River. No sewer lines exist south of the Alafia River except for a one-mile segment along Big Bend Road east of US and west of Balm-Riverview Road; a little more than a half-mile segment on the peninsula extending from Apollo Beach; a half- mile segment southeast of the preceding segment, about midway between the shoreline and US 41; and roughly five miles of lines along SR 674 between I-75 and just east of US 301. In contrast to the seven miles of existing sewer lines described in the preceding paragraph, Sewer Element Figure 1 indicates that the area south of the Alafia River is proposed to receive another 30 miles of lines by 1994 and another 30 miles of lines by 2010. In other words, the County intends to expand the central sewer system by almost tenfold over 20 years in the area south of the Alafia River. Four to six sewage treatment plants are operating close to the Alafia River, and two such plants are operating close to the Little Manatee River. In addition, two sewage treatment plants and an active landfill are also operating between the two rivers, located west of US 41 and east of the shore of Tampa Bay. The Data and Analysis report that one of the assumptions in the Sewer Element is that all regional and subregional wastewater treatment plants will use advanced wastewater treatment except the Van Dyke plant, which uses secondary wastewater treatment. The Data and Analysis also indicate that, as sewer connections are made, interim and private wastewater plants will be phased out. The Data and Analysis recognize the risk that septic tanks pose to potable water supplies: "As more and more quantities of potable water are needed to supply the County and as urbanization of previously rural areas occurs, the possible dangers due to septic tanks systems contaminating potable water supplies increases." Sewer Element, page 14. As noted below, the Plan distinguishes among Urban, Suburban, and Rural general service levels. 6/ For sanitary sewer, Rural services means "there would most likely be no service connection to an area treatment plant." Sewer Element, page 3. For sanitary sewer, Urban or Suburban service means "there would most likely be current or planned service connection to an area treatment plant." Sewer Element, page 4. Only in "intense urban areas" can the Plan assure "there would be service connection to an area treatment plant." Id. Sewer Element Table 1 discloses that the design capacity of wastewater treatment plants--both publicly and privately owned--is 42.163 million gallons per day with 46% of the capacity in the northwest service area, 42% of the capacity in the central service area, and 12% of the capacity in the south service area. The Data and Analysis indicate that the County has embarked on an "vigorous construction program aimed at meeting the existing commitments within its service areas and providing capacity capable of accommodating growth through 1995." Sewer Element, page 5. However, the construction of treatment facilities has proceeded faster than the construction of collection and transmission lines. 9. Potable Water Oversized Map 3 shows the location of existing water lines, proposed water lines through 1994, proposed water lines through 2010, and water service area boundaries. Potable Water Element Figure 1 depicts on a smaller scale the same information, plus the location of the water service area boundaries in 1995 and 2010. In general, water lines cover a considerable portion of the northwest and central parts of Hillsborough County, appearing in all parts of the County to serve all land that is both designated Suburban Density Residential and contiguous to areas designated for greater densities. Again, as in the case of central sewer, the part of Hillsborough County south of the Alafia River is not as well served. Twelve miles of line run along US 301, south from the Alafia River to SR 674. About seven miles of line run west on SR 674 to a point about two miles east of the mouth of the Little Manatee River. About five miles of line cover the Ruskin area directly northeast of the previously described terminus, and one mile of line proceeds south toward the Little Manatee River. Closer to Tampa Bay, about seven miles of water line run along US 41 south from the Alafia River to a point a couple of miles south of Big Bend Road, stopping about three and one- half miles north of the nearest existing line in Ruskin. About eight miles of line run just south of, and parallel to, the Alafia River. Another five miles of water line run from the Alafia River south, along the scenic corridor (evidently a railroad line to be converted into a two- lane road, at least part of which may be known as the Jim Selvey Highway) running parallel to, and about one mile west of, the boundary between Rural and Suburban designations between SR 640 and the line extending east of the end of Big Bend Road. 7/ Oversized Map 3 discloses that the County can provide central water service to relatively little of the area south of the Alafia River within the Urban and Suburban areas. As is the case with central sewer, the County's plans for new central water service project the majority of construction activity toward the end of the 20-year period. Although starting with considerably more water line mileage--about 47 miles--than sewer line mileage south of the Alafia River, the County plans only about eight new miles in this area by 1994, but over 90 new miles by 2010. For potable water service, a Rural service area "would most likely be served by a system of private wells." Potable Water Element, page 3. Urban or Suburban service means "there would most likely be current or planned service connecting to this area." Potable Water Element, page 4. Again, as in the case of sewer service, a guarantee of central water service applies only to intensive urban service, where "there would be service connecting to this area." Id. After detailed analysis, the Data and Analysis conclude that the County will require 235-318 million gallons per day of water in 2000. Responsibility in coordinating water supplies in the Tampa Bay area has been assigned to the West Coast Regional Water Supply Authority (WCRWSA). According to CARE Figure 19, Hillsborough County will run short of potable water by the early 1990's and need water supplies from the WCRWSA. CARE, page 28. Due to assumptions of increased water usage in Pasco and Pinellas Counties, "there is concern that the 'safe yield' limit of regional groundwater aquifers may be approached in the foreseeable future." Id. The Data and Analysis report that additional water for the fast-growing southcentral area will come from a "planned" wellfield in northeast Brandon. Potable Water Element, page 9. CARE Figure 18 shows the location of major public supply reservoirs and water wells of more than 100,000 gallons per day. Oversized Map 18, which is dated February, 1990, depicts a 200-foot radius for each major public supply well. The greatest concentration of public supply water wells is in northwest Hillsborough County, especially the northern half of this area. Based on rough projections, the Data and Analysis warn that there is a "need to develop and communicate accurate water supply and safe yield projections to ensure sound water use planning. In addition, [there is a] need to immediately conserve existing water supplies and to develop new supplies." Id. In the meantime, potential water sources are threatened by development: The quantity and quality of groundwater resources may also be adversely impacted by land development. Because of the dry, well- drained soils, many of the most important aquifer recharge areas in the County are considered to be the most desirable sites for development. However, the increase in impervious surface cover associated with land development may, in theory, reduce the amount of water available to recharge groundwater aquifers by increasing the amount of surface runoff and evaporation. In addition, pollution discharges to groundwater, including septic drainfields, leaking underground storage tanks, etc., percolate rapidly through the topsoil and into the underlying rock in such areas, and may pose a significant contamination threat to existing and future water supplies. CARE, page 28. Water conservation will help extend existing potable water supplies. Residential water use may be reduced by 15% to 70% by conservation measures. Agricultural water use may be reduced by better irrigation practices, reducing losses to seepage, and using the lowest quality water necessary. Only 33 of the 267 wastewater treatment plants in the County presently use direct wastewater reuse options. The Data and Analysis recommend the exploration of this option. With respect to potable water sources, the Data and Analysis also consider desalinization. About 70 such plants currently operate in Florida. The reverse osmosis method of desalinization appears to be a particularly viable alternative for Hillsborough County. Noting the inevitability of new demands for potable water from population growth, the Data and Analysis warn that "significant increases in impervious surfaces may actually decrease the recharge potential and the available water supply below historically reliable levels." CARE, page 61. Excessive groundwater withdrawals in Hillsborough County have historically dewatered wetlands and surface waters; excessive groundwater withdrawals in other coastal areas in Florida have historically resulted in saltwater intrusion. Thus, the Data and Analysis recommend the establishment of "'safe yield' groundwater withdrawal limitations." Id. Until the development of more sophisticated means, the Data and Analysis recommend the use of the "Water Budget Concept" to estimate probable limits on potable water supply and demand. Id. 10. Natural Habitats Because of the size, location, and estuarine shoreline of Hillsborough County, representatives of over half of the major plant communities in Florida are found in the County. The 14 major plant communities found in Hillsborough County are: pine flatwoods, dry prairies, sand pine scrub, sandhills, xeric hammocks, mesic hammocks, hardwood swamps, cypress swamps, freshwater marshes, wet prairies, coastal marshes, mangrove swamps, coastal strand, and marine grassbeds. With the exception of marine grassbeds, these habitats are depicted on the multicolor fold-out map entitled "Natural Systems and Land Use Cover Inventory," which is identified as CARE Figure 20 in the Plan. Coastal Figure 11 depicts the established extent of seagrass meadows in Tampa Bay. Coastal Figure 14 shows the location in Tampa Bay of different classes of waters. The waters adjacent to the shoreline of northwest Hillsborough County are Class II waters that are closed to shellfish harvesting. The waters from about a mile south of Apollo Beach to Manatee County are also Class II waters with shellfish harvesting approved in the area of Cockroach Bay. The remaining waters are Class III. Coastal Figure 13 depicts the location of emergent wetlands along the fringe of Tampa Bay. Concentrations of emergent wetlands are notable south of Apollo Beach and upstream varying distances along the fringes of the three major rivers and the former Palm River. Emergent wetlands also fringe the shoreline of northwest Hillsborough County. Most of the County's natural habitat has been lost to urban, agricultural, and industrial development, which has altered over half of the original freshwater wetlands and over three-quarters of the uplands. The trend of habitat destruction, though abated by wetland protection laws, continues to apply to the upland habitats of xeric and mesic hammocks. Supplementing CARE Figure 20 are Oversized Map 8, which depicts "major natural systems" based on CARE Figure 20, and CARE Table 11, which indicates where, by specific habitat, each of the endangered, threatened, or special-concern plant or animal species may be expected to occur. The Data and Analysis acknowledge that the rapidly growing human population and its associated urbanization has resulted in a substantial loss of natural wildlife habitat, especially in the coastal portions of the County, while the cumulative impacts of development continue to divide and isolate large contiguous natural areas. . . . As a result of habitat destruction and alteration, the natural populations of many wildlife species have declined dramatically. . . . comprehensive wildlife protection and management program is needed to inventory populations of threatened or endangered species and species of special concern, and to inventory significant and essential wildlife habitat and protect those areas in the future. Coastal Element, page 68. The pine flatwoods habitat is characterized by long- leaf pines on drier sites and slash pine on wetter sites. Despite overlap between the understories of the two types of pine flatwoods communities, saw palmetto predominates in slash pine flatwoods and wiregrass predominates in long-leaf pine flatwoods. Pine flatwoods depend on fire to eliminate hardwood competition. Longleaf pine flatwoods are more susceptible to lack of water than are slash pine flatwoods. In the absence of fire, the pine flatwoods community is replaced by a mixed hardwood and pine forest. Various species that are endangered, threatened, or of special concern are associated with the pine flatwoods habitat. These species include the Florida golden aster, eastern indigo snake, short-tailed snake, gopher tortoise, gopher frog, Florida pine snake, peregrine falcon, Southern bald eagle, Southeastern American kestrel, red-cockaded woodpecker, scrub jay, and Sherman's fox squirrel. Originally, 70% of Hillsborough County was vegetated by pine flatwoods, but now only 5% of the County is pine flatwoods. The level surface, thick understory, and poorly drained soils of the pine flatwoods tend to retain and slowly release surface water, so the pine flatwoods enhance surface water quality and reduce downstream flooding. Dry prairies are treeless plains, often hosting scattered bayheads, cypress ponds, freshwater marshes, and wet prairies. Dry prairies resemble pine flatwoods without the overstory and perform similar functions in terms of surface water drainage. The endangered, threatened, or special-concern species using dry prairies include those using the pine flatwoods plus the Florida sandhill crane and burrowing owl. Sand pine scrub is found mostly on relict dunes or other marine features found along present and former shorelines. Sand pine forms the overstory, and scrubby oaks compose a thick, often clumped understory. Large areas of bare sand are present in the habitat of the sand pine scrub, which requires fires to release the pine seeds. Without fires, the sand pine scrub habitat evolves into a xeric oak scrub habitat. The rare sand pine scrub community hosts many of the endangered, threatened, or special-concern species found in the pine flatwoods habitat. Supporting the highest number of such species, the sand pine scrub habitat's extremely dry environment sustains highly specialized plants and animals that could survive nowhere else. The unique adaptations of species to the sand pine scrub environment generates much scientific research of this unusual habitat, which is easily disturbed by human activities. The rapid percolation typical of the deep sandy soils of the sand pine scrub makes the community an important aquifer recharge area that is also vulnerable to groundwater contamination. Featuring more organic material in its sandy soils, the sandhill community, like the sand pine scrub community, is uncommon in Hillsborough County. Longleaf pines form the overstory of the sandhill habitat, unless, due to fire suppression and logging, xeric oaks, like turkey oak and bluejack oak, have been permitted to grow sufficiently to form the overstory. In the absence of the pines, the community is known as the xeric oak scrub. Longleaf pines require frequent fires to control hardwood competition, as does wiregrass, which, when present, prevents the germination of hardwood seeds and serves to convey fires over large areas. The endangered, threatened, or special-concern species of the sandhill habitat are similar to those of the pine flatwoods. The plant and animal species using the sandhill habitat are, like those using the sand pine scrub habitat, adapted to high temperatures and drought. These plant and animal species are often found nowhere else but in the sandhills, which, like the sand pine scrub community, allows rapid percolation of water. The well-drained soils render the area useful for natural recharge of the aquifer, but also vulnerable to groundwater contamination. Xeric hammocks feature live oaks in well-drained, deep sand. Providing habitat for many of the species using the pine flatwoods, the xeric hammock canopy provides a microclimate of cooler, moister conditions and supplies good natural recharge to the aquifer. Mesic hammocks are the climax community of the area and contain a wide diversity of plant species. Trees include the Southern Magnolia, laurel oak, American holly, dogwood, pignut hickory, and live oak. Endangered, threatened, or special- concern species using the habitat are Auricled Spleenwort, Eastern indigo snake, peregrine falcon, Southern bald eagle, Southeastern American kestrel, and Sherman's fox squirrel. Not dependent upon fire, mesic hammocks efficiently use solar heat and recycle nutrients. Mesic hammocks are adaptable to development if native vegetation, including groundcover, is retained. Hardwood swamps, which are also known as floodplain swamps, riverine swamps, and hydric hammocks, border rivers and lake basins where the ground is saturated or submerged during part of the year. The wettest part of these swamp forests features bald cypress or black gum trees. In higher areas, the trees typically include sweet gum, red maple, water oak, American elm, water hickory, and laurel oak. Hardwood swamps rely upon periodic flooding, absent which other communities will replace the hardwood swamps. Endangered, threatened, or special-concern species associated with hardwood swamps are the American alligator, Suwanee cooter, peregrine falcon, wood stork, Southern bald eagle, little blue heron, snowy egret, tricolored heron, and limpkin. "The hardwood swamp is extremely important for water quality and quantity enhancement." CARE, page 38. The hardwood swamp also retains and slowly releases floodwaters, which, among other things, allows suspended material to settle out. The swamp vegetation then removes excess nutrients and produces detritus for downstream swamps, such as estuaries. Cypress swamps are found along river or lake margins or interspersed through pine flatwoods or dry prairies. Bald cypress is the dominant tree along lakes and streams, and pond cypress occurs in cypress heads or domes. The endangered, threatened, or special-concern species associated with cypress swamps are the same as those associated with hardwood swamps. Especially when found in pine flatwoods or dry prairies, cypress swamps are important to wildlife because of their cooler, wetter environment. Cypress domes function as natural retention ponds. Cypress swamps along rivers and lakes absorb nutrients and store floodwaters. Freshwater marshes and wet prairies are herbaceous plant communities on sites where the soil is saturated or covered with water for at least one month during the growing season. Wet prairies contain shallower water, more grasses, and fewer tall emergents than do marshes. Fire recycles nutrients back into the soil and removes older, less productive plant growth. Flooding also reduces competition. The endangered, threatened, or special-concern species are the same as those using the cypress swamps except that the freshwater marshes and wet prairies host the Florida sandhill crane and roseate spoonbill, but not the limpkin. Freshwater marshes and wet prairies are the most important vegetative communities functioning as a natural filter for rivers and lakes. The ability to retain water allows freshwater marshes and wet prairies to moderate the severity of floods and droughts. But the freshwater marshes and wet prairies have suffered most from agricultural and urban development. Wet prairies in particular are susceptible to damage from recreation vehicle use, horseback riding, and foot traffic. Among the many species using freshwater marshes and wet prairies as habitat, the sandhill crane depends on this community for nesting habitat. Coastal marshes are located on low-energy shorelines and are interspersed with mangroves. Coastal marshes may be found along tidal rivers. Tides contribute to the high productivity of the coastal marshes, as tidal waters provide food to, and remove waste from, the organisms found in the coastal marshes. Endangered, threatened, or special-concern species associated with coastal marshes are the American alligator, peregrine falcon, wood stork, Southern bald eagle, redish egret, snowy egret, tricolored heron, and roseate spoonbill. With the mangrove swamp, the coastal marsh is the "key to the extremely high levels of biological productivity found in estuaries such as Tampa Bay." CARE, page 40. Marsh grasses convert sunlight and nutrients into plant tissue, which decomposes once the plant dies and becomes available to a number of detritus-feeding organisms. These organisms are themselves food for large animals. Coastal marshes also serve as nurseries for young fish, stabilize shorelines, filter out nutrients, and trap sediments. Mangrove swamps also occur along low-energy shorelines. The mangrove community "provides much of the driving force behind the productivity of bordering estuaries." CARE, page 41. Leaves from the mangroves fall into the water, supplying food to organisms as large as mullet. Mangrove swamps host the same animals as do coastal marshes except for the absence of alligators and presence of brown pelicans. The environmental values of the mangrove swamps are the same as the values of coastal marshes. The coastal strand includes beaches and coastal dunes. Prime examples of this type of habitat in Hillsborough County are Egmont Key and the larger islands in Cockroach Bay and at the mouth of the Little Manatee River. Marine grassbeds are found in estuaries and consist of vast meadows of different types of seagrasses. Having evolved from terrestrial forms, seagrasses contain roots, stems, leaves, and flowers and are able to grow in soft, sandy, or muddy sediments. Species of seagrasses found in Tampa Bay are limited to a water depth of about six feet, which is the average depth through which light can presently penetrate. Fast-growing seagrasses trap material from the land, absorb nutrients, and convey animal and plant products to the open sea. 11. Coastal Area The County's "most significant surface water resource" is Tampa Bay. CARE, page 10. In northwest Hillsborough County, the coastal area, which is also known as the coastal zone, consists of a strip of land about five miles wide running from the shoreline between Tampa and the Pinellas County line in the northwest part of the County. The coastal area for central and south Hillsborough County encompasses a band of land of about similar width running from the Tampa line south along US 301 across the Alafia River, then south from the Alafia River along I-75 to the Little Manatee River, where the boundary runs west to US 41, and then south along US 41 to the Manatee County line. Coastal Figure 16 locates coastal marine resources in and adjacent to Tampa Bay. Two locations of wading birds are in the northwest part of Hillsborough County. The only resources depicted between Tampa and the Alafia River are shorebirds in the Bay. At the Alafia River are wading birds, shorebirds, and pelicans. Wading birds and shorebirds are located in the Cockroach Bay Aquatic Preserve, as are manatee and oyster beds. The Data and Analysis describe the different land use planning challenges in the coastal area: coastal land issues are unique primarily due to the intense competing and often incompatible use demands, serious environmental constraints or impacts and the limited supply of shoreline lands. Coastal Element, page 3. The intent of the Plan is that coastal land use should be dominated by those uses which can only take place in or near the shoreline. This concept, by which water- dependent and water-related uses receive priority, stems from logic furthered by the Federal Coastal Zone Management Act .. .. Coastal Element, page 2. According to Coastal Element Table 2, the coastal area comprises 20,946 acres of developed land and 54,011 acres of undeveloped land. The developed land includes 12,343 acres of residential (75% single family detached), 4638 acres of community facilities (75% utilities and recreation/open space), 2095 acres of commercial (equal amounts of heavy and light commercial), and 1870 acres of industrial. The undeveloped land includes 24,388 acres of natural land (including 16,533 acres of woodlands and wetlands), 29,025 acres of agriculture, and 598 acres of mines (consisting of 299 acres of active mines, 75 acres of reclaimed mines, and 224 acres of unreclaimed mines). Many of the residential uses in the coastal area are on floodprone lands or land formed from dredge and fill operations. Many of these residential areas are in the unincorporated areas of Town and Country, Clair Mel City, Apollo Beach, and Bahia Beach. The problems common to these areas are periodic flooding, cumulative adverse impacts to wetlands, soil erosion, non-functioning septic systems, high potential for surface water pollution, potential for salt water intrusion, and reduced public access to the shoreline. Coastal Element, page 4. Most commercial development in the coastal area is of the neighborhood, rather than regional, variety. Commercial uses have generally followed rather than preceded residential development in the coastal area. However, in the Hillsborough Avenue/Memorial Highway area, which is in the coastal area between Tampa and Pinellas County, extensive commercial activity serves Town and County and the area off SR 580 (Hillsborough Avenue) toward Pinellas County. Much of the County's heavy industry is located in the coastal area due to proximity to the port. Agriculture is treated as undeveloped land, although only one-third of agricultural uses are merely fenced pastureland. In any event, "urban growth is steadily displacing [agricultural and vacant land] uses forcing agricultural activities to move to more inland parts of the County." Coastal Element, page 5. The largest uses within the category of community facilities in the coastal area are electric power generating and transmission facilities. The next largest is recreation/open space. Both of these uses are water dependent. The coastal natural areas provide vital shoreline habitat and protect against storm surge. The Data and Analysis warn: Displacement of these natural areas by continued urban development will result in a net reduction of water quality within Tampa Bay and tidal rivers and creeks, loss of vital wildlife habitat, a diminished sense of open space, and the exposure of property and human life to the dangers of storm surge. Coastal Element, page 6. In discussing potential conflicts in potential shoreline land uses, the Data and Analysis note that more coastal areas that are vacant, recreational, or agricultural have been designated as Environmentally Sensitive Areas, Low Density Residential, Recreation and Open Space, or Natural Preservation. The development of the coastal area has resulted in the elimination of natural shoreline vegetative communities such as mangroves and wetlands. The Data and Analysis acknowledge the "urgency to more effectively manage coastal zone natural resources and direct urban development into areas more appropriate for such growth." Coastal Element, page 7. The Data and Analysis also note that stormwater runoff into Tampa Bay and its tributaries may constitute the "greatest impact to marine habitat." Id. According to the Data and Analysis, the main uses that are neither water-dependent nor water-related are commercial and industrial uses that "could function just as well inland as in a coastal location" and "intense urban residential." Coastal Element, page 9. The Data and Analysis endorse the trend toward displacing agricultural uses in the Apollo Beach/Ruskin area west of I-75 between the Alafia River and the Manatee County line. The Data and Analysis approve of the increased concentration of development closer to the amenities of the coastal area without using the coastal zone for non-water-dependent uses. Oversized Maps 11 and 12 respectively show the location of archaeological sites and historic resources. Oversized Map 11 indicates by Florida Master Site File number the location of at least 200 archaeological sites. Due to the presence of numerous archaeological sites in the coastal area, the County "needs to establish a method to protect, preserve, and restore its historic resources." Coastal Element, page 13. Because the County has not adopted a local preservation ordinance, the Data and Analysis admit that "historic resource management efforts are not clearly defined." Coastal Element, page 60. However, the Data and Analysis indicate that provisions in the Future Land Use Element and Coastal Element will preserve the historic resources in the coastal area. 12. Coastal High Hazard Area and Hurricane Planning The entire Tampa Bay region: has been identified by the National Weather Service as one of the most hurricane- vulnerable areas of the United States, with the potential for large scale loss of life. Coastal Element, page 37. The vulnerability of the County and its residents to hurricanes is due to geography and land use. The proximity of large numbers of persons near Tampa Bay and residing in low- lying areas or mobile homes increases the risk of loss of life and property. The hurricane vulnerability analysis is based on the 100 year storm event or Category 3 hurricane, which produces winds of 111-130 miles per hour and storm surge of 12-18 feet above normal. The Data and Analysis define the hurricane vulnerability zone as the area from which persons must be evacuated in the event of a Category 3 hurricane. The Data and Analysis also identify the coastal high hazard area, which is the area from which persons must be evacuated in the event of the less intense Category 1 hurricane. The coastal high hazard area is also the velocity zone shown on maps issued by the Federal Emergency Management Agency. Coastal Element Figure 18 depicts the coastal high hazard area as a strip of land fringing Tampa Bay. The northwest section of the coastal high hazard area between Pinellas County and Tampa is nearly one mile wide. The width of the coastal high hazard area from Tampa to Manatee County ranges from nonexistent to about 1.5 miles, and even more at the Little Manatee River, but averages about one mile. The Data and Analysis recognize the special planning issues that apply to the coastal high hazard area: The issue with respect to development in the coastal high hazard area is the protection of residents and the public expenditure of funds for areas that are subject to severe flooding from storm surge and rainfall and structure damage as a result of high winds. In addition to limiting development, the permitted development shall be designed to mitigate problems associated with stormwater runoff, wastewater treatment, and septic tanks. Coastal Element, page 61. Dealing with the provision of infrastructure in the coastal area, the Data and Analysis ask, but do not answer, the following questions: Does the provision of infrastructure encourage development of coastal areas? Should all citizens be required to bear the burden of increased public infrastructure cost in coastal areas? As development and redevelopment pressures continue in the coastal areas these questions and others must be answered. Coastal Element, page 64. Analysis of the County's hurricane preparedness requires consideration of the availability of shelters. The County has 46 primary shelters that, at the applicable ratio of 20 square feet per shelter resident, can accommodate about 59,000 persons. Unfortunately, about 60,000 of the 175,000 evacuees sought shelter space during Hurricane Elena, which, during the Labor Day weekend of 1985, came within 80 miles from the mouth of Tampa Bay. In any event, there is sufficient shelter space through 1995. Although secondary shelter space may be sufficient for awhile, the County will need more shelter space by 2000. Present estimated clearance times for hurricane evacuation range from 11-16 hours, depending upon the storm and evacuation conditions. After evaluating pre-landfall hazards, such as the inundation of low-lying evacuation routes, the clearance times are increased by 10 hours, so the range is 21-26 hours. Persons with special needs, which could enlarge the time needed for evacuation, have been encouraged to register with the County. The Data and Analysis inventory the hospitals and nursing homes whose occupants would need to evacuate in the event of a hurricane. Six of the 21 nursing homes and four of the 17 hospitals would be vulnerable to storm surge in a Category 3 storm. Tampa General, which is a County-operated facility, is subject to storm surge in a Category 1 storm, and the Data and Analysis warn that expansion plans should be carefully reviewed. Finding that clearance times of 11 and 16 hours are "acceptable," the Data and Analysis caution that the clearance times may increase as population increases in the Tampa Bay region. Options to be considered include exploration of vertical evacuation, discouragement of evacuation by nonvulnerable residents, expansion of road capacity, and imposition of the requirement that mobile home parks construct on-site shelter space. A variety of public infrastructure is contained in the coastal high hazard area. These public facilities include roads, bridges, and causeways; sanitary sewer facilities; potable water facilities; and shoreline protection structures. Private facilities include electric generating units and substations. The County does not own a sanitary sewer plant in the coastal high hazard area. But the County uses about 12% of the capacity of Tampa's Hookers Point plant, which is in the coastal high hazard area. The County owns three potable water facilities in the coastal high hazard area. A pump station and two elevated storage tanks are in the Apollo Beach area. In view of the vulnerability of parts of the County to a hurricane: government is responsible for ensuring that human life is protected and property damage is minimized in food-prone and coastal high hazard areas; that land use and development patterns are consistent with the vulnerable nature of the coastal high hazard and inland flood-prone areas; and that natural systems and vegetation that serve to reduce the impacts of severe weather are protected and preserved. In order to accomplish these ends, Hillsborough County must consider available options to reduce or limit exposure in the [coastal high hazard area]; develop guidelines/procedures for development in the [coastal high hazard area]; propose alternatives to reduce clearance times or reduce deficit public shelter space; and develop methods to redirect population concentrations away from the [coastal high hazard area]. Coastal Element, page 42. The Data and Analysis consider the question of post- hurricane redevelopment, which has not been an issue in the County since 1921, which marked the last time that a hurricane made landfall in Hillsborough County. After addressing the extent to which public funds might be available to assist in rebuilding infrastructure, the Data and Analysis confront the underlying issue whether infrastructure in the coastal high hazard area should be rebuilt in place or relocated outside the coastal high hazard area. The Data and Analysis conclude: A decision-making framework needs to be established by the County in order to determine if the infrastructure or facilities should be relocated, have structural modifications or be replaced. Coastal Element, page 45. The Data and Analysis recommend that decisions concerning redeveloping infrastructure be guided by the following factors: costs, environmental impacts, mitigative impacts, growth management consistency, impacts on the public, timeliness, legal issues, availability of funds, and necessity of infrastructure. 13. Air Quality The air quality in the Tampa urban area "is among the state's most polluted," but "severe conditions are often localized and short lived, due to prevailing winds and the area's non-confining topography." CARE, page 46. However, the Data and Analysis admit that "[a]ir quality in the Tampa Bay region . . . is degraded and in need of improvement relative to certain air pollutants." CARE, page 51. Of the six pollutants for which federal and state attainment standards exist, Hillsborough County is classified as non-attainment for ozone, for which automobile exhausts are indirectly responsible, and particulate matter. But point sources, especially power plants, are also responsible for air pollution. Since the mid 1970's, all criteria pollutants except ozone have decreased in the County. The Data and Analysis recommend "more stringent regulations and better compliance with existing regulations." CARE, page 52. Urban Sprawl Planning Strategy The Data and Analysis disclose that the County has adopted two major planning strategies. The Plan creates nodes and corridors and provides a range of lifestyles from the Urban to the Suburban to the Rural. The specific details of these planning strategies are found in the operative provisions of the Plan, which are set forth in the following section. However, the Data and Analysis offer a brief overview of the County's two major planning strategies. A node is a "focal point within the context of a larger, contiguous area surrounding it. It is an area of concentrated activity that attracts people from outside its boundaries for purposes of interaction within that area." Future Land Use Element (FLUE), page 8. The Data and Analysis explain that the Plan contains four types of nodes: high intensity nodes, which are for high intensity commercial uses, high density residential uses, and high concentration of government centers; mixed use regional nodes, which are for regional shopping centers, major office and employment areas, and sports and recreational complexes; community center nodes, which are focal points for surrounding neighborhoods; and neighborhood nodes, which are smaller scale community centers. Once nodes become established, "corridors" are intended to connect two or more nodes. Presently, the road network is the sole type of corridor. But mass transit may one day offer an alternative type of corridor. As part of the second major planning strategy, the Plan offers residents a variety of lifestyle options, primarily by varying residential densities. Population growth in Hillsborough County has historically radiated out from the central business district of Tampa. The emergence of nodes outside Tampa has altered this development pattern. The Plan's treatment of rural areas reflects the philosophy that "[r]ural areas need not be treated only as undeveloped lands waiting to become urban." FLUE, page 9. The Data and Analysis report that the Plan seeks to preserve the pastoral nature of the rural lifestyle by ensuring the availability of large lots for residential development. The size of the lots is in part driven by the absence of central water and sewer, so that individual wells and septic tanks will necessarily serve most rural development. In addition to providing small scale commercial uses at appropriate locations, the Data and Analysis recognize that the Plan must also ensure the preservation of unstructured open space, as well as competing rural uses, such as agriculture, that may not harmonize completely with adjacent residential development. The Data and Analysis describe the suburban residential option as part of a "gradual transition of land uses from very rural to more suburban blending into the urban environment." FLUE, page 10. Suburban areas would be accompanied by greater intensities of commercial uses and more extensive public facilities, as compared to the commercial uses and public facilities serving rural areas. The Data and Analysis describe densities of two or three dwelling units per acre on outlying suburban areas, gradually increasing to two to six dwelling units per acre on suburban areas closer to urban areas, and finally attaining even higher densities adjacent to the urban areas. Open space remains "quite important" for suburban areas and could be attained partially through clustering dwelling units. Id. The urban areas facilitate the provision of "very specialized public and private services that could not be justified anywhere else." FLUE, page 11. The Data and Analysis state: If the urban areas are permitted to increase their concentrations, it will lessen some of the development pressures in other areas of the County. One distinct advantage of intense urban development is that the potential, negative impacts of development upon the natural environment can be controlled more effectively. Additionally, the provision of public facilities is much more cost effective in the intense urban areas. Id. The Data and Analysis recognize the role of planning to ensure the attainment of the planning goals of the County: Hillsborough County has and will continue to experience a high population growth rate. Residential, commercial and industrial land development is expanding rapidly, and the County has been unable to keep pace with the demand for public facilities. The rapid rate of development has had many adverse impacts upon the environment, transportation, public facilities, historic resources and community design. . . . An overall, general guide to development outlining basic considerations during the development process is needed to protect the health, safety and welfare of the residents of Hillsborough County. FLUE, page 12. The Data and Analysis recognize that "much of the newer residential development is designed as enclaves with little or no functional linkages to the surrounding areas." FLUE, page 22. Addressing the linkage of residential to commercial uses, the Data and Analysis add: Commercial development has followed the sprawl of residential development into the County. Commercial strip development has been allowed to proceed relatively unchecked along the major arterials in the County creating undue congestion and safety hazards. A strong need was identified to develop a logical and functional method to determine the location and amount of future commercial development without interrupting the market system. FLUE, page 25. The Data and Analysis also address industrial and public facility land uses. The identification of specific areas for industrial development "will create a desirable development pattern that effectively maximizes the use of the land." FLUE, page 28. And the requirement that public facilities be available to serve new development "will create greater concentrations of land uses in the future." FLUE, page 27. 2. Existing Land Uses The Data and Analysis set forth the existing land uses by type and acreage. Using a total acreage for the County of 605,282 acres, the table of existing land uses by acreage, which is at page XVIII-B of the FLUE background document, divides developed land into four general categories: residential, commercial, industrial, and community facilities. Residential existing land uses total 73,104 acres. The total includes 55,546 acres of single family detached with an average density of 1.7 dwelling units per acre, 9709 acres of mobile home with an average density of 1.3 dwelling units per acre, 3643 acres of mobile home park with an average density of 4.6 dwelling units per acre, and 3006 acres of single family attached and multifamily with an average density of just under 12 dwelling units per acre. Commercial existing land uses total 8143 acres, consisting of 3613 acres of light commercial, 3029 acres of heavy commercial, 770 acres of transient lodging, and 731 acres of business and professional offices. Industrial existing land uses total 4122 acres, consisting of 1889 acres of heavy industrial, 1178 acres of warehouse and distribution, and 1055 acres of light industrial. Community facilities existing land uses, which consist of utilities, schools, and recreation/open space, total 19,439 acres, including 7981 acres of recreation/open space and 5200 acres of utilities. The remaining 500,474 acres in the County are divided into Natural, Agriculture, and Mining existing land uses. Natural existing land uses total 182,082 acres, consisting of 133,939 acres of woodlands and wetlands, 26,745 acres of vacant land in urban areas, and 21,398 acres of water. Agriculture existing land uses total 292,129 acres, including 104,870 acres of fenced pastureland, 103,773 acres of general agriculture, 40,600 acres of groves or orchards, and 38,867 acres of row crops. Mining existing land uses total 26,263 acres, consisting of 10,551 acres of active mines, 8655 acres of unreclaimed mined out areas, 6717 acres of reclaimed mines, and 340 acres of resource extraction. The County has prepared or obtained numerous existing land use maps (ELUM), either as small-scale maps contained in the two-volume compilation or as Oversized Maps. Most of the ELUM's have been described above. The ELUM's depict the Tampa Bay estuarine system including beaches and shores; rivers, bays, lakes, floodplains, and harbors; wetlands; minerals, soils, and sinkholes; natural systems and land use cover; areas of natural aquifer recharge and potential groundwater contamination; and various public facilities. ELUM's not previously described include Oversized Map 6, which is dated September, 1988, and is entitled Major Health and Education Facilities. Another Oversized Map dated February 1, 1988, shows the same types of facilities. Existing land uses are shown by a variety of maps. CARE Figure 20, which is the color map showing vegetative cover, provides some information as to the location of disturbed and undisturbed natural areas. Coastal Figure 1 shows existing land uses, but only for the coastal area. Those parts of the coastal high hazard area shown as vacant or agricultural or that otherwise received designations allowing higher densities or intensities are identified in Paragraphs 772 et seq. Most detailed is Oversized Map 2, which is the 1985 Generalized Land Use map. Oversized Map 2 shows the location of existing land uses by the following categories: agricultural and vacant, low density residential, medium and high density residential, commercial, industrial, major public, mining, and natural. As noted above, existing, major public supply wells are depicted on CARE Figure 18 and Oversized Map 18. The latter map also depicts 200-foot radii for "well protection areas." Oversized Map 18 also appears to depicts planned water wells, such as a cluster of four wells northeast of Brandon, which were omitted from CARE Figure 18. Other wells are also depicted on Oversized Map 18, but not CARE Figure 18, which thus appears to have been limited to existing wells. 3. Future Land Uses Under Plan The Data and Analysis accompanying the FLUE acknowledge that "[t]here are very few compact centers where commercial and residential uses interact positively in unincorporated Hillsborough County." FLUE, page 7. The projected population for unincorporated Hillsborough County in 2010 is 932,800, according to the Bureau of Economic and Business Research at the University of Florida. About 458,236 persons were projected to be residing, in 2010, in housing units existing in 1988. By land use category, as depicted on the Future Land Use Map, the County has 283,195 vacant acres on which residential development is permitted under the Plan. The following table sets forth, by category, the vacant acreage, permitted maximum density (expressed as a ratio of dwelling units per gross acre), and population capacity. 8/ Land Use Category Density Vacant Acres Pop. Capacity Agricultural/Mining 1:20 66,122 9,092 Agricultural 1:10 20,162 5,545 Rural Agricultural 1:5 65,115 35,813 Rural Estate 1:2.5 8,617 9,479 Rural Residential 1:1 18,533 50,968 Rural Residential Plan 1:5 7,325 4,029 Low Sub. Density Resid. 2:1 14,388 79,134 Low Sub. Density Resid. Plan 1:5 20,326 11,179 Suburban Density Resid. 4:1 24,667 271,337 Low Density Residential 6:1 10,625 175,313 Low Medium Density Resid. 9:1 945 16,755 Medium Density Residential 12:1 1,290 30,496 High Density Residential 20:1 765 30,141 Urban Level 1 12:1 17,850 421,974 Urban Level 2 20:1 4,495 177,103 Urban Level 3 50:1 1,760 173,360 TOTALS 283,195 1,501,718 Dividing the total population capacity of 1,501,718 persons by the projected population of 932,800, the Plan has overallocated density by a factor of 1.61. Nonresidential uses for which the Plan allocates land include industrial and commercial uses. The industrial uses and respective acreages in the Plan are Light Industrial (12,789), Light Industrial--Planned (746), and Heavy Industrial (4721). The commercial uses and respective acreages in the Plan are Community Commercial (5538), Regional Commercial (678), Community Office (294), and Research Corporate Park (1411). The industrial uses cover a total of 18,256 acres, or 3.04% of the total of 600,409 acres in Hillsborough County. The commercial uses cover a total of 7921 acres, or a little more than 1% of the total acreage in the County. If the acreage designated as Urban Level 1, 2, and 3 is treated as commercial, then the total commercial acreage equals 8.79% of the County. The remaining categories on the Future Land Use Map and respective acreages are: Natural Preservation--23,313 acres; Environmentally Sensitive Areas--81,880 acres; Water--6026 acres; Recreation/Open Space--2310 acres; and Public/Semi- Public--4142 acres. Excluding the Public/Semi-Public category, the remaining four categories, which by varying degrees involve open space, constitute 113,526 acres, or about 19% of the County. In addition to the matter of density allocations, the use of land involves the places where the County has chosen to locate its densities. CARE Figure 2 shows the location of the population in 1985. For unincorporated Hillsborough County, only about 45,000 persons lived south of the Alafia River with about two-thirds living west of I-75. Roughly 150,000 persons lived in northwest Hillsborough County, and another 150,000 persons lived in central Hillsborough County between the Alafia River and I-4. The remaining (as shown on Figure 2) 50,000 persons lived east of I-75 and north of I-4 in northcentral and northeast Hillsborough County. Oversized Map 14 shows areas of density changes effected by the Plan and revisions to a pre-1985 Act plan applicable to I-75 and south Hillsborough County that took place shortly before the adoption of the Plan and were incorporated into the Plan. Oversized Map 14 discloses large areas of density increases in the following locations, among others: the part of the coastal high hazard area between Cockroach Bay and the mouth of the Little Manatee River; an area immediately across US 41 from the previously described area and bounded by the Little Manatee River on the north and I-75 on the east; almost the entire I-75 corridor that is designated nearly exclusively Urban Level 1 and Urban Level 3; a large expanse of land designated mostly Low Suburban Density Residential Planned along the railroad right-of-way that is to be converted into a two-lane road, at least part of which is to be known as the Jim Selvey Highway; an area of Medium Density Residential just north of the mouth of the Little Manatee River near Ruskin; the northcentral area from I-75 and I-275 to the Hillsborough River; and relatively large portions of the north and west halves of northwest Hillsborough County, including almost the entire northwest corner of the County to Gunn Highway (east of Keystone Lake). Oversized Map 13 is the Vacant Land Suitability Analysis, which shows the location of critical lands or soils with very severe limitations, presumably with reference to the location of predominantly vacant lands. The range of soils with very severe limitations includes the entire coastal high hazard area, much of the corridors of the Little Manatee and Alafia Rivers, the Hillsborough River valley, several areas of about 1.5 square miles each in northwest Hillsborough County, much of the land north of the northernmost extent of Tampa and just east of I-275, and an L-shaped area east of I-75 and straddling Big Bend Road, as well as area just to the south of the L-shaped area. Lands of varying degrees of sensitivity are located throughout the areas of very severely limited soils. Locations of the two most critical classes of land are widely distributed among the phosphate mining area in southeast Hillsborough County and along the major southern tributary of the Alafia River, near Cockroach Bay and the mouth of the Little Manatee River, at the southeast and northwest ends of the coastal high hazard area of northwest Hillsborough County, just east of I-275 and I-75, in the Hillsborough River valley, and along the Alafia River and its northern tributary. Locations of the two less critical classes of land, but nevertheless sensitive or very sensitive, include areas along Big Bend Road at I-75, east of I-75 north of Big Bend Road, and in the northwest corner and northern half of northwest Hillsborough County. 4. Use of Public Facilities Under Plan Acknowledging that high population growth has contributed to many of Hillsborough County's problems, such as "infrastructure inadequacies," the Data and Analysis concede: The extension of public facilities has lagged behind the unincorporated County's rapid growth. One of the consequences of growth outpacing the provision of services and facilities is the development of outlying large lot residential with onsite water and sewer facilities (septic tanks, wells). The historic lack of services has continued to strain the county's fiscal ability to respond to these needs, and there will be a greater need for more intensive functional planning and action by county government. FLUE, pages 6-7. Part of the difficulty in matching population growth with public facilities has been due to historic land use patterns. The Data and Analysis note: There are very few compact centers where commercial and residential uses interact positively in unincorporated Hillsborough County. Threshold population densities needed to support many services do not exist in most parts of the County. The cost of providing services such as water, sewer, roads, mass transit, schools, fire and police protection are much higher per capita in low density areas than in more urban areas. Concentration of new development in areas with adequate levels of service for public facilities will create a more effective and efficient utilization of man-made and natural resources and encourage the full use and immediate expansion of existing public facilities while protecting large areas of the natural environment from encroachment. The concentration of new development in areas with adequate levels of service will also fulfill the requirement of subsection 9J-5.006(3)(b)7 to discourage urban sprawl. FLUE, page 7. Protection of Natural Resources Under Plan The Data and Analysis link effective land use planning with the protection of the County's natural resources and preservation of County residents' quality of life: . . . growth will continue to challenge and threaten the natural environment as daily development decisions confront the long-range need to preserve and protect irreplaceable natural environmental systems. Unplanned, rapid population growth will degrade the unincorporated county's environment. Development will encroach upon valuable wellfields and wildlife habitat and may further pollute the County's freshwater aquifers. One of the County's major needs is to assure the protection and viability of green open spaces and environmentally significant areas, which are crucial to the community's quality of life and economic health. The unincorporated County's potential to maintain and improve the quality of life for its residents will be contingent upon its ability to adequately serve existing and future demands for services. FLUE, page 7. 6. Protection of Agriculture Under Plan The Data and Analysis contain a position paper concerning agricultural issues. The paper reports that agriculture is the County's single largest industry, and Hillsborough County is the third largest agricultural county in the state. According to the position paper, the trend in agriculture in Hillsborough County has been toward increased productivity through improved technology and transition to the production of more profitable commodities. The position paper argues that the viability of agriculture is not dependent upon the maintenance of low residential densities to discourage the conversion of agricultural land to residential uses. Advocating reliance upon free-market forces to maintain the competitiveness between agricultural and residential uses, the position paper concedes that a density of one dwelling unit per five acres is "not low enough to discourage sale of the property for five acre ranchettes[, which] promote high consumption of land for housing and remove the land for agricultural production." FLUE Background Document, page XLVII. Plan Provisions The FLUM The subject cases present two problems regarding the FLUM. The first problem is to identify what constitutes the FLUM. The second problem is to determine the significance of one of the major designations on the FLUM: Environmentally Sensitive Areas. In its proposed recommended order, the County asserts that the FLUM consists of a series of maps. 9/ This assertion is groundless. Neither the Plan nor the adoption ordinance provides any basis whatsoever for finding that the FLUM comprises all of the maps and figures contained in Sierra Club Exhibit A local government must adopt operative provisions, such as a FLUM or goals, objectives, or policies. Hillsborough County did not adopt all of the Oversized Maps or the maps and figures in the two-volume compilation of the Plan. Hillsborough County adopted the Plan in Ordinance No. 89-28. The ordinance delineates the scope of the operative provisions of the Plan by noting that the Data and Analysis, or "background information," are not part of the operative provisions of the Plan: Material identified as background information in the Table of Contents for each Element, including data, analysis, surveys and studies, shall not be deemed a part of the Comprehensive Plan as provided in Subsection 163.3177(8), Florida Statutes. The Plan clearly includes among its operative provisions a FLUM. Several provisions describe the role of the FLUM and, in so doing, help identify what the County adopted as the FLUM. In the Introduction to the FLUE, the Data and Analysis state: "The policies of [the FLUE] are presented in written form, and they are graphically represented on the Future Land Use Map." FLUE, page 5. The Data and Analysis elaborate: The [FLUE] consists of two parts: Goals, Objectives and Policies; and a Future Land Use Map (Land Use Graphic), a copy of which is attached, and incorporated hereby by reference. FLUE, page 11. Operative provisions of the Plan likewise recognize the FLUM and its role as part of the operative provisions of the Plan. For instance, the Plan Implementation section of the FLUE begins: The primary tool of implementation for the [FLUE] are the Future Land Use Map and the Land Use Plan Categories. These are followed by other implementation tools that further define the intent of the Future Land Use Map and the Land Use Plan Categories. They include: locational criteria for neighborhood commercial uses; criteria for development within designated scenic corridors; and density credits. The Future Land Use Map is a graphic illustration of the county's policy governing the determination of its pattern of development in the unincorporated areas of Hillsborough County through the year 2010. The map is adopted for use as an integral part of the [FLUE]. It depicts, using colors, patterns, and symbols, the locations of certain land uses and man-made features and the general boundaries of major natural features. The Future Land Use Map shall be used to make an initial determination regarding the permissible locations for various land uses and the maximum possible levels of residential densities and/or non-residential intensities, subject to any special density provisions and exceptions of the [FLUE] text. Additionally, each regulation or regulatory decision and each development proposal shall comply with all applicable provisions within the . . . Plan. FLUE, page 54. The Legal Status of the Plan section of the FLUE adds: The Future Land Use Map is an integral part of this [FLUE], and it shall be used to determine the permissible locations for various land uses and the maximum possible levels of residential densities and/or non- residential intensities. The goals, objectives and policies of this [FLUE] shall provide guidance in making these determinations. FLUE, page 129. The FLUM at least includes a multicolor map entitled 2010 Land Use Plan Map. The multicolor map depicts the location of various future land uses, man-made features, and natural resources. The importance of the multicolor map is underscored by its relatively large scale of 1" = 1 mile. The only maps drawn on such a large scale are a black and white copy of the multicolor map and a green map, which is discussed below. The Oversized Maps discussed in this recommended order are drawn to a scale of 1" = 2 miles. The question remains, however, whether the FLUM includes maps or figures in addition to the multicolor map. The FLUE defines the FLUM as: The graphic aid intended to depict the spatial distribution of various uses of the land in the County by land use category, subject to the Goals, Objectives, and Policies and the exceptions and provisions of the [FLUE] text and applicable development regulations. FLUE, page 137. Consistent with the discussion of the FLUM contained in the Plan Implementation section of the FLUE, the multicolor map is the only map that depicts future land uses by colors, patterns, and symbols. No other map uses colors except for CARE Figure 20, which is the Natural Systems and Land Use Cover Inventory. CARE Figure 20 is obviously an ELUM with no designation of future land uses. With the exception of the green map discussed below, no other map uses any color whatsoever. The above-cited Plan references to the FLUM are in the singular. The FLUM is identified in the singular throughout the Data and Analysis set forth in the two-volume compilation of the Plan. See, e.g., FLUE pages 55, 56, 69, 70, 75, 94, and 137. 10/ With one exception, operative provisions of the Plan also refer to the FLUM in the singular. See, e.g., FLUE Policies A-3.2, B- 6.2, B- 6.7, B-7.9, and C-31 and Coastal Policy 7.1. But see CARE Policy 19.8, which requires the County to identify "Resource Protection Areas" on the Future Land Use Map "series." DCA referred to a single FLUM when DCA issued the Objections, Recommendations, and Comments (ORC) concerning the Plan as first transmitted. The County prepared detailed responses to the objections, recommendations, and comments. Three responses refer at length to the FLUM and refer to it in the singular, rather than as a map series. Hillsborough County Exhibit 35, responses 4, 8, and 26. Response 29 to the ORC answers the objection that the FLUM (in the singular) omits existing and planned waterwells, the cones of influence for such waterwells, and wetlands. The response states: Cones of influence have not been identified for Hillsborough County. Objective 5 of the [CARE] and its subsequent policies outline the County's strategy with regard to protecting its wellfields. Because of the multitude of wetlands in Hillsborough County and the lack of exact mapping capability, the "E" area on the land use plan map is indicative of major areas of hydric soils (per USDA Soil Conservation Services, Soil Suitability Atlas for Hillsborough County, Florida) of a scale to be seen on the map. Actual wetlands must be delineated by the Environmental Protection Commission of Hillsborough County prior to site development. Minerals and Soils are indicated on Figures 9 and 10 of the [CARE] of the Plan. The rest of the parameters will all be included on the revised existing land use map. Despite the confusion in the last two sentences of the response between the nature of ELUM's and FLUM's, the response is consistent in its presumption of a single FLUM, rather than a map series. Until the commencement of Plan litigation, 11/ the County did not consider the FLUM to be more than the multicolor map. Repeatedly, the County had opportunities--outside of the Plan and adoption ordinance--to identify the FLUM. Repeatedly, the County did not confer the FLUM status upon any map other than the multicolor map. Oversized Map 18 is an important example of the Plan identifying a map, but not adopting it as part of the FLUM. Describing Oversized Map 18, CARE Policy 5.8 states: By 1993, the County shall have developed and implemented a comprehensive wellfield protection program, which includes but is not limited to the determination and mapping of zones of contribution (also known as cones of influence) surrounding public wellfields and the adoption and implementation of a wellfield protection ordinance which protects these areas. In the interim, the County shall use the best available information to identify these areas. See map 18, Interim Wellfield Protection Areas . . .. CARE Policy 5.8 assigns Oversized Map 18 to the Data and Analysis, rather than the operative part of the Plan. The County's intent to relegate Oversized Map 18 to the Data and Analysis is restated in the March 14, 1990, cover letter from the County Planning Director transmitting the settlement amendments to DCA. The letter states: "The documents are incorporated by reference for background for informational purposes only." Oversized Map 18 is the first of the listed documents. The Plan deals similarly with other maps and figures; as better information becomes available, the graphic aids that are part of the Data and Analysis may change--without the requirement of a Plan amendment. For example, CARE Policy 5.2 mentions the DRASTIC maps, which indicate areas susceptible to groundwater contamination. In language similar to CARE Policy 5.8, Policy 5.2 states that the County will use the "best available information" concerning groundwater contamination areas and then mentions the graphic aid. Another possible FLUM is a black-and-white map with green and dotted green areas on a scale of 1" = 1 mile. The green colors are overlaid on a black-and-white version of the multicolor map. The green map contains a special legend for the green areas. The solid green areas depict "Environmentally Sensitive Areas." The dotted green areas depict "Environmentally Sensitive Areas Which Are Potentially Significant Wildlife Habitat." Notwithstanding the many references to the FLUM in the singular, the Plan anticipates the possible amendment of the FLUM or the addition of an overlay to show the location of Environmentally Sensitive Areas. CARE Policy 14.2 states: By 1991, the County shall identify and map natural plant communities which are determined to provide significant wildlife habitat in Hillsborough County. The natural systems and land use cover inventory map ([CARE] Figure 20), produced by the Florida Game and Freshwater Fish Commission, shall serve as the basis for this effort. Areas of significant wildlife habitat shall be indicated as environmentally sensitive areas on the Future Land Use Map or map overlay. The green map may be the map or overlay promised by CARE Policy 14.2. 12/ However, for purposes of these cases, the green map is not part of the FLUM. The green map had not been adopted by August 1, 1991, or even by the time of the final hearing. Transcript, pages 1095 and 1105; County's Proposed Recommended Order, Paragraph 180. In view of the considerable confusion surrounding the Environmentally Sensitive Areas designation, as explained below, it would be unfair to overlook this fact and treat the green map as part of the operative provisions of the Plan. Because of the clear understanding that the Plan included only amendments through August 1, 1991, the parties presumably did not take the opportunity to litigate the significance of the designations contained on the green map. Even though the County did not adopt the green map as part of the FLUM, for the purpose of these cases, it remains necessary to consider the effect of the Environmentally Significant Areas designation. The designation is found on the multicolor map (i.e., the FLUM) as well as the green map. Also, the green map is an important part of the Data and Analysis. The problem is to determine what does it mean for an area to bear the designation of Environmentally Significant Areas. Part of the confusion surrounding the Environmentally Significant Areas designation is due to its dual nature as an overlay, like Scenic Corridors, and underlying designation, like Suburban Density Residential or Light Industrial. An overlay typically depicts an area that, notwithstanding its underlying designation, is subject to special land use conditions in the Plan. Any underlying designation may and usually is subject to other provisions of a comprehensive plan, but an overlay ensures that these conditions are not overlooked and may elevate them in importance. The Environmentally Significant Areas designation on the multicolor map is never an overlay. For each area on the multicolor map designated Environmentally Significant Areas, there is no other designation. For this reason alone, the Environmentally Significant Areas designation itself should regulate land uses in some meaningful fashion; otherwise, areas so designated would lack generally applicable guidelines concerning permissible densities and intensities. However, according to the County Planning Director, the Environmentally Significant Areas does not regulate land uses. The Planning Director prepared a cover letter dated September 4, 1991, to DCA accompanying the first round of Plan amendments in 1991. The letter explains why the County was amending the Plan to redesignate certain County-owned, environmentally sensitive land from Environmentally Significant Areas to Natural Preservation. The letter states: We still recommend that these areas be changed to Natural/Preservation, since the "E" [Environmentally Significant Areas] designation is an identification only land use category to indicate that environmentally sensitive lands may be located on site. However, that category in and of itself does not regulate land uses on a site. The Natural/Preservation category is very restrictive and does not permit development on a site. Sierra Club Exhibit 1. From the letter, it appears that the County's intent was to use the Environmentally Sensitive Areas designation merely to indicate the general location of critical natural resources, rather than to assign specific densities and intensities. In other words, the Environmentally Sensitive Areas designation was to be merely an overlay showing some of the natural resources required by Chapter 9J-5 to be shown on the FLUM. If any land use restrictions applied to land with an Environmentally Sensitive Areas overlay, the Planning Director's letter implies that the restrictions were not imposed by textual Plan provisions defining land uses under the Environmentally Sensitive Areas designation. Under this interpretation, land use restrictions could be imposed by textual Plan provisions that, although never mentioning Environmentally Sensitive Areas, govern natural resources included within such areas, such as wetlands, wildlife habitat, or sand pine scrub habitat. Clearly, the Planning Director is correct in writing that one purpose of the Environmentally Significant Areas designation is to indicate the location of environmentally sensitive lands. The real question is whether the Planning Director is correct in his assertion that the Environmentally Sensitive Areas designation is merely locational and not regulatory. This would mean that all of the land designated Environmentally Significant Areas on the multicolor map bears only a designation indicative of the location of certain natural resources, but lacks an effective, generalized land use designation. The Plan defines Environmentally Sensitive Areas; in fact, it does so twice. The CARE defines "Environmentally Sensitive Areas" as: Lands which, by virtue of some qualifying environmental characteristic (e.g. wildlife habitat) are regulated by either the Florida Department of Natural Resources, the Florida Department of Environmental Regulation, the Southwest Florida Water Management District, or any other governmental agency empowered by law for such regulation. These include Conservation and Preservation Areas as defined in the [CARE]. CARE, page 97. The CARE defines "Conservation Areas" as: Environmentally sensitive areas which include the following: --Natural shorelines (other than those included in preservation areas); --Class III Waters; --Freshwater marshes and wet prairies; --Sand-pine scrub; --Hardwood swamps; --Cypress swamps; --Significant wildlife habitat. CARE, page 96. The CARE defines "Preservation Areas" as: Environmentally sensitive areas which include the following: --Aquatic preserves; --Essential wildlife habitat; --Class I and II Waters: --Marine grassbeds; --Coastal strand; --Coastal marshes; --Mangrove swamps; and --State wilderness areas. CARE, page 99. "Significant wildlife habitat" is "[c]ontiguous stands of natural plant communities which have the potential to support healthy and diverse populations of wildlife and which have been identified on the Florida Game and Freshwater Fish Commission natural systems and land use cover inventory map." CARE, page 100. "Essential Wildlife Habitat" is "[l]and or water bodies which, through the provision of breeding or feeding habitat, are necessary to the survival of endangered or threatened species, or species of special concern." CARE, page 97. The FLUE defines Environmentally Sensitive Areas as: This land use category is used to designate those major, privately owned lands which are environmentally sensitive. These areas include Conservation Areas and Preservation Areas, as defined in the [CARE]. Development in these areas may be is [sic] restricted by federal, state, and/or local environmental regulations. Development projects will be evaluated for compliance with the [CARE] and [Coastal Element]. The Environmentally Sensitive Area designations on the Future Land Use Plan map are very generalized, and include primarily wetland areas. The designations are not exhaustive of all sites. On-site evaluation will be necessary for specific project review. Development in these areas is subject to the Goals, Objectives and Policies of the [FLUE], [CARE], and [Coastal Element], applicable development regulations, and established locational criteria for specific land use. FLUE, page 136-37. The Land Use Plan Categories section of the FLUE 13/ does not repeat the typographical error in the preceding Plan provision, in which the Plan warns that development in Environmentally Sensitive Areas "may be is" restricted by federal, state, or local law. The definition of the Environmentally Sensitive Areas designation in the Land Use Plan Categories section omits the "is," implying more strongly that some development may take place on Environmentally Sensitive Areas. FLUE, page 126. The Land Use Plan Categories section of the FLUE equates in two respects the Environmentally Sensitive Areas designation with the Natural Preservation, Scenic Corridors, Major Recreation and Open Space, and Major Public/Semi-Public designations. In each of these five designations, residential densities and commercial or industrial intensities (expressed as maximum floor area ratios) are "not applicable." For the Natural Preservation, Major Recreation and Open Space, and Major Public/Semi-Public designations, the "not applicable" statement reflects the fact that residential, commercial, and industrial uses are prohibited by the land use designation in question. However, for the Scenic Corridors designation, which operates more as an overlay, the Plan provides no such prohibition, instead requiring special attention to aesthetic features of development in these areas. Thus, the "not applicable" language applicable to the Environmentally Sensitive Areas designation does not answer the question whether the designation is regulatory or merely locational and, if the former, what land uses are thereby regulated and how. The question whether the Environmentally Sensitive Areas designation operates as a locational overlay, as suggested by the Planning Director's letter of September 4, 1991, seems to be answered by the Table of Residential Densities in the Implementation section of the FLUE. For the Scenic Corridor designation, the Table of Residential Densities indicates that the maximum residential density allowed is, instead of a ratio, "Overlay--Scaled to Area." But for the Environmentally Sensitive Areas designation, the Table of Residential Densities states that "no residential uses [are] allowed" for Environmentally Sensitive Areas. FLUE, page 62. The Table of Residential Densities gives the same response for the Natural Preservation, Major Recreation and Open Space, and Major Public/Semi-Public designations. The failure of the Table of Residential Densities to assign any residential density to Environmentally Sensitive Areas is not inadvertent. The Data and Analysis indicate that, in calculating density allocations, the vast acreage designated Environmentally Sensitive Areas was not given any residential density. In the FLUE Background Document at page XXVIII, a table listing all of the FLUM designations shows no density for the 81,880 acres of Environmentally Sensitive Areas, which account for 13.64% of acreage of the County and is the second largest designation following 89,267 acres designated Agricultural/Rural. The density allocation table preceding page XXX contains no entry for Environmentally Sensitive Areas, although much if not all of the area so designated is vacant (or as the County classifies land, vacant or agricultural). The omission of residential uses in Environmentally Sensitive Areas, as contained in the Table of Residential Densities, suggests that the designation carries a regulatory force beyond the locational character identified by the Planning Director in his letter of September 4, 1991. Natural resources included within the definition of Environmentally Sensitive Areas are wetlands, sand pine scrub, wildlife habitat essential for the breeding or nesting of endangered, threatened, or special-concern species, and contiguous stands of natural plant communities with the potential to support healthy and diverse communities of wildlife. Some of these natural resources are not themselves unconditionally protected by textual Plan provisions. But if the Environmentally Sensitive Areas containing these natural resources are not assigned any residential uses, as the Table of Residential Densities implies, then the designation itself must preclude the conversion of these sensitive areas to residential uses. On the other hand, the textual Plan provisions contemplate some development of Environmentally Sensitive Areas because of various provisions requiring compensatory replacement following the loss of the natural resources to development. Despite implying that development in Environmentally Sensitive Areas may be permitted, as long as it complies with Plan provisions, the Land Use Plan Categories section of the FLUE states that the typical use of areas designated as Environmentally Sensitive Areas is "Conservation." Although not the same typical use as that set forth for Natural Preservation areas, which are limited to "Open space or passive nature parks," the definition of "Conservation Uses" is restrictive: Activities within land areas designated for the purpose of conserving or protecting natural resources of environmental quality and includes areas designated for such purposes as flood control, protection of quality or quantity of groundwater or surface water, floodplain management, fisheries management, or protection of vegetative communities or wildlife habitat. FLUE, page 135. At times in the Plan, the Environmentally Sensitive Areas designation appears to be merely locational. At times, the Environmentally Sensitive Areas designation appears to be regulatory. In the latter case, portions of the Plan suggest that the designation prohibits development, and portions of the Plan suggest only that the designation, standing alone, carries with it some degree of protection from development. FLUE Policy A-8.2 says as much: "Development shall be required to protect the Conservation and Preservation areas " But even if the Plan were interpreted to impose a regulatory functional upon the Environmentally Sensitive Areas designation, the failure of the Plan to specify clearly the land use restrictions generally applicable to the designation leaves open to doubt the land uses permitted on over 13% of Hillsborough County. And if some residential development were permitted in areas designated Environmentally Sensitive Areas, then the density allocation ratios have been calculated without regard to the density-bearing capacity of over 13% of the County. The FLUE definition of Environmentally Sensitive Areas, which states that development "may be is" restricted in such areas, may represent a unique, though inadvertent, disclosure of the County's ambivalence toward the degree of protection to extend to Environmentally Sensitive Areas. Perhaps in the belief that land use restrictions for Environmentally Sensitive Areas would emanate from federal, state, regional, or even other local governmental entities, 14/ the County has left to speculation the meaning of the critically important Environmentally Sensitive Areas designation. The only clear significance of the Environmentally Sensitive Areas designation is the role of areas bearing such a designation in calculating residential densities or commercial or industrial intensities. The acreage on which residential densities are calculated does not generally include Conservation or Preservation Areas or water bodies. (As noted above, Environmentally Sensitive Areas designation "include[s]" Conservation and Preservation Areas.) But the calculation of gross residential density may include acreage consisting of certain man-made waterbodies and certain Conservation and Preservation Areas. The qualification for Conservation and Preservation Areas is that the maximum area of such land (or wetland) is 25% of the total residential acreage. FLUE, pages 64-66. A similar provision applies for the calculation of floor area ratios or gross nonresidential intensity. FLUE, pages 67- 68. Illustrations in the FLUE apply the density formula described in the preceding paragraph. For example, if the proposed project consists of 80 acres, including 20 acres of land (or wetland) designated Environmentally Sensitive Areas, the total acreage upon which residential densities could be calculated would be 75 acres. This result is reached by starting with the 60 acres of proposed residential use that are not designated as Environmentally Sensitive Areas. Twenty-five percent of 60 acres is 15 acres, which is the maximum acreage designated Environmentally Sensitive Areas that is eligible to be included in the calculation of gross residential density. The designation given the 60 acres would allow a density, such as 4:1, which, when applied to 75 acres, yields 300 dwelling units. The implied presumption of the density formula--stated nowhere in the Plan--is that areas designated Environmentally Sensitive Areas acquire their actual land use restrictions, in terms of densities or intensities, from the adjoining lands. The intent of the density credit allowed for areas designated Environmentally Sensitive Areas is to protect the subject natural resources. FLUE Policy A-8.4 provides for density credits for development that is "sensitive to, preserves and maintains the integrity of wetlands [and] significant wildlife habitat." Again, though, the degree and type of protection are unclear. The density formula may be interpreted to prohibit inferentially any disturbance of Environmentally Sensitive Areas. In other words, the Environmentally Sensitive Areas acreage used in calculating the density bonus or perhaps the entire Environmentally Sensitive Areas acreage (even if some acreage were excluded from the calculation due to the 25% limitation) could not be disturbed by development. However, another interpretation is possible. The density formula, which is mandatorily imposed on all proposed projects containing Environmentally Sensitive Areas, does not, by its terms, prescribe where the resulting development is to be located. In the example above, the density formula effectively reduced the density of a project by 20 dwelling units (80 acres X 4 vs. 75 acres X 4). But the formula does not explicitly prohibit the location of some of the 300 permitted units in areas designated as Environmentally Sensitive Areas. 15/ If the Environmentally Sensitive Areas designation does not prohibit development, some degree of protection would be theoretically possible by reducing the actual density occupying the parcel containing Environmentally Sensitive Areas while still not actually prohibiting the location of dwelling units on all Environmentally Sensitive Areas. It is difficult to infer from the density formula whether the Environmentally Sensitive Areas designation is intended to prohibit the development of areas so designated or, if not, to what extent the designation restricts development of such areas. If the Environmentally Sensitive Areas designation does not regulate land uses so as to prohibit the development of areas so designated, the formula provides some protection to Environmentally Sensitive Areas by increasing the chance that such areas may be less densely populated, but also supplies the basis on which densities or intensities for areas designated Environmentally Sensitive Areas are to be inferred. If the Environmentally Sensitive Areas designation regulates land uses so as to prohibit the development of areas so designated, the formula can be interpreted as providing some compensation by allowing the use of some of the foregone development rights in adjoining areas under common ownership that are not designated as Environmentally Sensitive Areas. The question whether the density formula, as well as the closely related intensity formula, prohibit the development of Environmentally Sensitive Areas can be approached by considering another density formula. The upland forest density credit incentive, which is identified in FLUE Policy A-8.3, is described in detail in the Implementation section of the FLUE. The failure of the density formula, as well as the intensity formula, to prohibit the disturbance of Environmentally Sensitive Areas stands in contrast to the protection extended by the upland forest density credit incentive. The upland forest density credit incentive provides a bonus of 25% more density than otherwise allowed by a specific designation to the extent of the upland forest 16/ acreage preserved by the project. In other words, a 100-acre parcel designated at 1:1 might include 25 acres of upland forests within the single residential designation covering the entire 100 acres. If the proposed project preserved the 25 acres of upland forest from development, the 25 dwelling units attributable to the 25 acres are increased to 31.25 dwelling units and raise the total number of dwelling units to 106.25. Unlike the density and intensity formulas, the upland forest density credit incentive requires the landowner to record a conservation easement for the 25 acres of upland forest, so that this land may never be developed. FLUE, pages 71-73. The different approaches of the density and intensity formulas, on the one hand, and the upland forest density credit incentive, on the other hand, may arise partly from the fact that the latter formula is an incentive for which a landowner may qualify voluntarily. Upland forests would generally not be preserved by the Plan in the absence of the utilization of the upland forest density credit incentive. Regardless of their effect in preserving Environmentally Sensitive Areas, the density and intensity formulas are not optional; they are imposed whenever a proposed development contains Environmentally Sensitive Areas. Part of the discussion of the upland forest density incentive credit may shed some light on the meaning of the Environmentally Sensitive Areas designation, especially as it concerns the density and intensity formulas. The upland forest density incentive credit repeatedly refers to the density formula as involving wetlands or the protection of wetlands. Although wetlands make up a substantial part of the Environmentally Sensitive Areas, numerous uplands also qualify as Environmentally Sensitive Areas. Qualifying uplands include significant and essential wildlife habitat, as well as sand pine scrub (which is also included as an upland forest). Possibly the County incorrectly assumed that the Environmentally Sensitive Areas designation was limited to wetlands, or perhaps the designation was so limited in an earlier draft of the Plan. In either event, the County may have assumed that federal, state, regional, and other local restrictions against disturbing wetlands would effectively prevent the development of such Environmentally Sensitive Areas, or at least clearly regulate the extent to which such areas could be disturbed. As noted above, however, the Plan itself must supply such regulation through a generalized land use designation. The Environmentally Sensitive Areas designation is poorly integrated into the Plan. Plan provisions, including the density and intensity formulas, repeatedly address "wetlands" or "Conservation" or "Preservation" Areas, rather than Environmentally Sensitive Areas. If the Environmentally Sensitive Areas designation were not intended to regulate land uses and prohibit all development, but were merely locational as indicated by the Planning Director, then the Plan is deficient in failing to assign a regulatory land use designation to over 80,000 acres, or 13.64%, of the County. For these vast areas, in any event, the Plan provides no direct, and arguably not even any indirect, guidance as to what densities or intensities are permitted on Environmentally Sensitive Areas. The only conclusion that can be reasonably drawn from the Plan concerning that Environmentally Sensitive Areas designation is that it is, at least, locational. The designation shows where Conservation and Preservation Areas are located. The designation also serves to provide some protection to Environmentally Sensitive Areas through the density and intensity formulas. However, it may not be reasonably concluded that the density and intensity formulas prohibit the destruction of Environmentally Sensitive Areas by development. Nor can it be reasonably concluded that other provisions of the Plan preserve Environmentally Sensitive Areas, as such, from destruction or alteration by development. The full extent of the meaning of the Environmentally Sensitive Areas designation is lost in ambiguity. The FLUM does not identify existing and future potable water wellfields. The FLUM fails even to show the location of existing major public supply wellfields, as depicted in CARE Figure 18 and Oversized Map 18. The FLUM does not identify cones of influence for the existing wellfields to the extent known. Figures 32 and 33 of Sierra Club Exhibit 12 pertain to four wellfields located entirely in Hillsborough County and two wellfields located partly in the County. For these wellfields, which are located in the northern part of the County, Figures 32 and 33 respectively portray a wide-ranging decline in water table elevations and potentiometric surface of the Floridan aquifer due to wellfield pumpage. This information corresponds to drawdown depth of the source from which each wellfield draws its water. Even if these data sources are rejected in favor of the much more limited 200-foot protection zones outlined in Oversized Map 18, the County has failed to adopt Oversized Map 18 as part of the FLUM, as described in the preceding section. The FLUM does not identify historic resources or historically significant properties meriting protection. Oversized Maps 11 and 12 depict respectively Archaeological Sites and Historic Resources. However, these maps are not part of the FLUM. The FLUM does not depict the 100 year floodplain. Oversized Map 9 depicts the 100 year floodplain, massive amounts of which lie outside the future land use designations of Environmentally Sensitive Areas and Natural Preservation. But Oversized Map 9 is not part of the FLUM. The FLUM does not depict the minerals and soils of the County, except to the extent that minerals are contained in a general land use designation. CARE Figure 9 depicts soils and mine pits. Oversized Maps 8 and 10 also depict soils and mine lands. However, these maps are not part of the FLUM. The FLUM depicts wetlands. The designation of Environmentally Sensitive Areas on the FLUM (i.e., the multicolor map) includes wetlands. The FLUM depicts public facilities under the category of Major Public/Semi-Public and Electric Power Generating Facilities. The former category shows the location of, among other things, "churches, hospitals, schools, clubs and utility and transportation facilities." FLUE, page 122. The Plan Natural Resources CARE Objective 2 is: By 1995, the water quality of natural surface water bodies in Hillsborough County which do not meet or exceed state water quality standards for their designated use shall be improved or restored. CARE Policy 2.1 provides: The County shall not support the reclassification of any surface water body within County boundaries to acknowledge lower water quality conditions, unless necessary to protect the public health, safety or welfare. Where economically feasible, the County shall support the reclassification of surface water bodies to accommodate higher standards, where it can be demonstrated that improved water quality conditions will prevail in the future. The CARE defines "economically feasible" as follows: "Where the benefit to the public outweighs the cost of the action, and is within the County's capability to fund." CARE, page 96. CARE Policy 2.2 addresses the problem of wastewater discharges: The County shall require that all domestic wastewater treatment plans discharging effluent into Tampa Bay or its tributaries provide advanced wastewater treatment, or if specific alternative criteria developed by the Surface Water Improvement and Management Program can only be met by removing a surface water discharge, such a program shall be implemented, where economically feasible and in accordance with Policy 2.3 below. CARE Policy 2.3 requires the County to "continue to develop and promote environmentally acceptable effluent disposal alternatives to surface water discharge, including, but not limited to, reuse for irrigation and industrial purposes." Dealing with the problem of short-term solutions to sewage disposal, CARE Policy 2.4 states: To reduce the need for interim domestic wastewater treatment plants, the County shall plan for the construction of regional wastewater treatment facilities to serve areas designated for higher densities in the . . . Plan. CARE Policy 2.6 provides that, "where economically feasible," the County "shall provide improved domestic wastewater treatment service to developed areas where persistent water quality problems are clearly attributable to poorly functioning septic treatment systems." CARE Policy 2.7 further addresses the issue of septic tanks by providing that, by 1990, the County shall "request or initiate" agreements with third parties to develop "scientifically defensible siting criteria, performance standards, and density limitations for septic systems, to ensure protection of surface water quality." The policy adds that the County shall "request . . . special criteria and standards . . . for those septic systems to be located in areas adjacent to Class I and Class II Waters and Outstanding Florida Waters." The policy concludes with the promise that, within one year after the development of the criteria and standards, the County "shall amend appropriate development regulations" accordingly. CARE Policy 2.8 provides in part: Where economically and environmentally feasible, [a nutrient monitoring and control program for agriculture to be developed after 1995] shall require the implementation of Best Management Practices for controlling nutrient loadings, including retrofitting if needed to meet specific alternative criteria as established by the Surface Water Improvement and Management Program. The CARE defines "environmentally feasible" as follows: "Where the physical conditions or the necessity to protect natural resources do not preclude the action." CARE, page 97. CARE Policy 2.10 states: By 1991, the County shall require that existing developments planned for expansion, modification or replacement provide or support stormwater treatment improvements within the affected drainage basin where treatment facilities are lacking. Where economically and environmentally feasible, the County shall require retrofitting of stormwater treatment facilities in urbanized areas lacking such facilities. CARE Objective 3 is "no net loss of wetland acreage." The objective requires the County to "seek to achieve a measurable annual increase in restored wetland acreage," which shall be achieved by 1995 "through the restoration of degraded natural wetlands, until all economically and environmentally feasible wetland restoration is accomplished." CARE Policy 3.1 states that the County shall "continue to conserve and protect wetlands from detrimental physical and hydrological alteration and shall continue to allow wetland encroachment only as a last resort when reasonable use of the property is otherwise unavailable." CARE Policy 3.2 provides in part: Channelization or hardening (e.g., paving, piping) of natural streamcourses shall be prohibited except in cases of overriding public interest. The CARE defines "overriding public interest" as: "Actions required by local, state, or federal government, necessary for the promotion of public safety, health or general welfare." CARE, page 99. CARE Policy 3.6 is for the County to continue to promote through the development review process the use of desirable native wetland habitat species for the creation of wetland habitat and for biologically enhancing filtration and treatment of pollutants in newly constructed stormwater retention and detention ponds. CARE Objective 4 is: The County shall continue to prevent net loss of 100-year floodplain storage volume in Hillsborough County. By 1995, the County shall protect and conserve natural wildlife habitat attributes where they exist within the 100-year floodplains of major rivers and streams. CARE Policy 4.1 is for the County to amend its floodplain management regulations to "protect natural floodwater assimilating capacity [and] also protect fish and wildlife attributes where they exist within the 100-year floodplains of riverine systems." CARE Objective 5 is for the County to ensure compliance with state groundwater standards. CARE Policy 5.2 provides that, until the Southwest Florida Water Management District maps high aquifer recharge/contamination potential areas at a sufficient resolution, the County shall consider the best available hydrogeological information (e.g. SWFWMD DRASTIC maps), and may require the collection of site specific hydrogeologic data, such as soils borings and differences in head between the upper aquifers, when assessing the impacts of proposed land use changes and developments in areas of suspected high aquifer recharge/contamination potential. When required, this information shall be used in the determination of land use decisions, on a case-by-case basis. CARE Policy 5.5 refers to the high resolution mapping of recharge/contamination areas, as well as a study that the County will request the Southwest Florida Water Management District to conduct as to the effect of impervious surfaces on recharge. The policy states that, within one year after these tasks are completed: The County shall develop a comprehensive set of land use development regulations and performance standards for development activities proposed within areas of high aquifer recharge/contamination potential. Such regulations and performance standards may include, but not be limited to, control of land use type and densities, impervious surface limitations, and discharge to groundwater controls. CARE Policy 5.8 focuses on a wellfield protection program, which shall be "developed and implemented" by 1993. The task shall include the "determination and mapping of zones of contribution (also known as cones of influence) surrounding public wellfields and the adoption and implementation of a wellfield protection ordinance which protects these areas." In the meantime, CARE Policy 5.8 requires the County to use the best available information to identify these areas [cones of influence]. See map 18, Interim Wellfield Protection Areas for Public Water Supply Wells in Unincorporated Hillsborough County, Florida (Zones of Contribution Map). The County shall also adopt and implement an interim ordinance which sets forth a procedure, using the best available information, for reviewing development proposals which might adversely impact the zones of contribution surrounding public wellfields. CARE Policy 5.9 states: Through the land development review process, the County shall continue to regulate activities which would breach the confining layers of the Floridan aquifer by prohibiting land excavations that would breach the confining layers. CARE Policy 5.11 is identical to CARE Policy 2.7 except that CARE Policy 5.11 deals with groundwater pollution, rather than surface water pollution, and CARE Policy 5.11 provides that the County shall request the development of special septic-tank siting criteria and standards for areas of "demonstrated high recharge/contamination potential." CARE Policy 5.13 is for the County to "increase requested assistance" from the Southwest Florida Water Management District to ensure that excessive consumptive use of groundwater or excessive drainage does not "significantly lower water tables or surface water levels, reduce base flows, or increase current levels of saltwater intrusion." CARE Policy 5.15 prohibits the County from supporting the use of deep-well injection of effluent or waste disposal "except where it can be demonstrated that the capacity for receiving injection is sufficiently large and that such disposal will have no adverse effect upon existing or potential potable water aquifers." CARE Objective 6 is for the County to meet future water needs through the "conservation, reuse, and enhancement of groundwater and surface water supplies, and shall prevent significant environmental degradation due to excessive groundwater withdrawals." CARE Policy 6.1 is for the County to request that the Southwest Florida Water Management District and WCRWSA develop a regional water budget to calculate more accurately water supplies and demands. CARE Policy 6.2 is for the County, by 1992, to "adopt and implement a Water Reuse Ordinance which maximizes the use of treated sewage effluent for residential and recreational irrigation purposes, where such reuse can be demonstrated to be environmentally acceptable and no threat to public health." CARE Policy 6.4 is: The County shall require the use of the lowest quality water reasonably and feasibly available, which is safe for public health and the environment and suitable to a given use, in order to reduce the unnecessary use of potable water. CARE Policy 6.8 is for the County, by 1992, to develop, in cooperation with the Southwest Florida Water Management District, a water conservation program, including enforcement of specific building code requirements for water saving devices. CARE Policy 6.9 is for the County, by 1992, to evaluate the implementation of a user fee rate for potable water in order to discourage nonessential uses of potable water. CARE Policy 6.10 requires that the County, "through the land development review process, restrict the substantial lowering of the water table to meet stormwater treatment or storage requirements." CARE 6.11 requires that the County, "through the land development review process, . . . promote the use of xeriscape landscaping and low-volume irrigation " CARE Policy 6.12 is for the County, by 1995, to develop legal and financial mechanisms "to purchase, to the extent reasonably feasible, development or mineral rights, easements and partial or complete title to lands necessary to safeguard the public water supply." Suggested mechanisms include the transfer of development rights and tax benefits. CARE Policy 6.13 addresses groundwater recharge and stormwater management: By 1992, a program to improve groundwater recharge through the use of private and public stormwater management facilities will be developed and implemented. This program may require, among other things, that predevelopment groundwater recharge volumes and rates be maintained on site after development, if the site is located in an area of known or identified average annual aquifer recharge potential of at least two surface inches of water; and will include restrictions on the lowering of groundwater levels to meet stormwater management regulations. In the interim, where practical, and where feasible from a water quality standpoint, new development will be encouraged to consider retention of stormwater rather than stormwater detention in these areas. CARE Objective 7 is for the County to "continue to provide opportunity for and require the prudent operation of mining activities " CARE Policy 7.1 requires "sequential land use" in mineral-rich areas. The CARE defines "sequential land use" as "[a] practice whereby lands overlaying valuable mineral resources are protected from intensive urban development until such minerals can be mined, and that land reclaimed for a viable economic use." CARE Policy 7.2 requires the "phasing of mineral extraction to ensure that limited land areas are affected by excavation and settling ponds at one time and that reclamation occurs in the most effective manner." CARE Policy 8.1 requires the County, by 1991, to "identify environmentally sensitive areas which are not capable of being effectively restored following mineral extraction." CARE Policy 8.2 provides: The County shall restrict mining in areas which are ecologically unsuitable for the extraction of minerals, as identified in the natural systems and land use cover inventory, unless it can be demonstrated that such areas can be effectively restored utilizing the best available technology. CARE Policy 8.3 states: The County shall continue to prohibit mineral extraction within the 25-year floodplain, and shall restrict mining activities in the 100- year floodplain, of rivers and streams. CARE Policy 8.4 is: By 1992, the County shall prohibit mineral extraction in essential wildlife habitats which are documented, in accordance with the terms of Objective 14 and related policies thereunder, to support threatened or endangered species, or species of special concern, and from which such species cannot be effectively relocated. CARE Policies 8.5 and 8.6 require the use of the best available technology in restoring natural land forms and vegetative communities and minimizing natural resource impacts. CARE Policy 8.8 provides that the County shall continue to require proof of "long-term financial responsibility for the reclamation of mined lands." CARE Objective 9 requires the County to "protect the public health, safety and welfare from the adverse impacts of mining activities." CARE Policy 9.1 is for the continued requirement of "appropriate setbacks" between mining and adjacent land uses. CARE Objective 10 is for the County to "continue to regulate the location and operation of land excavation to minimize negative impacts on surrounding properties, ensure that land excavations are appropriately reclaimed, and encourage the productive reuse of such areas." CARE Policy 10.1 is for the County to "continue to prohibit land excavation activities which adversely impact surface or groundwater levels on surrounding property." CARE Policy 10.2 states that the County "shall require reclamation and reuse plans to ensure environmentally acceptable and economically viable reuses of land excavations." CARE Policy 10.3 demands that the County, by 1993, require the "preparation of wetland/lake management plans for the reclamation of land excavation projects to be reclaimed as lakes to ensure that such areas become viable and productive aquatic systems." CARE Policy 10.4 is for the County to "encourage" recreational development of reclaimed land excavations. CARE Policy 10.6 states that the County shall require setbacks between land excavations and adjacent land uses to protect the public health, safety, and welfare. CARE Policy 10.7 provides that, by 1992, the County shall prohibit land excavations in "essential wildlife habitats documented in accordance with the provisions of Objective 14 as supporting endangered, threatened, [or special- concern] species and from which such species cannot be effectively relocated." CARE Objective 11 is that the County shall "continue to require soil conservation and protection during land alteration and development activities." CARE Policy 11.1 provides that, during the land development review process, the County shall "recommend" the appropriate use of soils and shall require site-specific analyses when the use appears to be incompatible with the soils. CARE Policy 11.3 states that, during the land development review process, the County shall "continue to evaluate and utilize, where appropriate, soil capability analyses for flood hazard, stability, permeability, and other relevant soil characteristics when permitting new development." CARE Objective 14 is for the County to "protect significant wildlife habitat, and . . . prevent any further net loss of essential wildlife habitat . . .." CARE Policy 14.1 promises the initiation of the development and implementation of a wildlife and wildlife habitat protection and management program. CARE Policy 14.3 requires the County, by 1993, in consultation with the Florida Game and Freshwater Fish Commission, to "identify and map areas of essential wildlife habitat." CARE Policy 14.5 compels the County, by 1991, to develop and implement a program to "conserve and protect significant wildlife habitat from development activities." The program may include transfers of development rights, clustering and setback requirements, conservation easements, leaseback operations, fee simple purchases, land or mitigation banking, and tax incentives. CARE Policy 14.6 states: By 1992, the County shall restrict development activities which adversely affect areas identified and mapped as essential wildlife habitat. Where development activities are proposed in such areas the County may require site-specific wildlife surveys and other field documentation, as needed, to assess potential impacts. CARE Policy 14.7 provides: During the land use planning and development review processes, the County shall consider the effects of development on significant wildlife habitat, to protect wildlife corridors from fragmentation. Where necessary to prevent fragmentation of wildlife corridors, the County shall require the preservation of wildlife corridors within developments. CARE Objective 15 states: Populations of threatened or endangered species and species of special concern occurring within Hillsborough County shall be maintained. Where feasible and appropriate, the abundance and distribution of populations of such species shall be increased. CARE Policy 15.1 is for the County, by 1991, to consult with and consider the recommendations of the Florida Game and Freshwater Fish Commission in determining whether to issue development orders and, if so, what conditions to impose where development would impact endangered, threatened, or special- concern species. Conditions "shall ensure the maintenance and, where environmentally and economically feasible, increase the abundance and distribution of populations of such species." CARE Objective 16 is to "continue existing programs to minimize the spread of exotic nuisance species" and implement management plans for newly acquired natural preserve lands to reduce by 90% the extent of exotic nuisance plants. The objective requires the County to "conserve and use and continue to require the conservation and use of native plant species in the developed landscape." The objective adds that the County shall "continue to protect Conservation and Preservation Areas." CARE Policy 16.2 is for the County to "continue to require the use of native plant species in the landscaping of new development projects." Respectively addressing Conservation and Preservation Areas, CARE Policies 16.5 and 16.6 provide that, "except in cases of overriding public interest," the County shall, in the land use planning and development review processes, "protect [Conservation/Preservation] Areas from activities that would significantly damage the natural integrity, character, or ecological balance of said areas." CARE Objective 17 states: By 1995, the acreage of publicly owned or otherwise protected (through private ownership) natural preserve lands in the County shall be increased by at least 15,000 acres (which is approximately 50% more than 1988 acreage). The County shall seek to continue increasing the acreage of natural preserve lands and to ensure their protection and proper use. CARE Policy 17.1 is for the County, by 1990, to seek public approval by referendum to continue to levy an ad valorem tax for the acquisition of environmentally sensitive lands. CARE Policy 17.6 requires the County to provide multiple-use opportunities for County-owned natural reserve lands so as to protect and conserve natural resources. CARE Policy 17.8 requires the County, during the land use planning and development review processes, to "restrict incompatible development activities adjacent to publicly owned or managed natural preserves." CARE Objective 18 provides: The County shall seek to measurably improve the management of all natural preserves within County boundaries by implementing the following policies[.] CARE Policy 18.2 is for the County to initiate with the Florida Department of Natural Resources an agreement "to ensure that the Cockroach Bay Aquatic Preserve is maintained in its essentially natural condition and protected from development that would adversely affect the environmental integrity of the Preserve." CARE Policy 18.3 is for the County to "establish a scientifically defensible protective buffer zone between the Cockroach Bay Aquatic Preserve and adjacent upland land uses to prevent degradation of water quality and aquatic vegetative habitats." CARE Policy 18.8 requires the County to "participate" with the Florida Department of Natural Resources to "fully implement the Cockroach Bay Aquatic Preserve Management Plan " CARE Objective 19 states: The County shall continue to amend land development regulations which ensure the protection of the attributes, functions and amenities of the natural environment under all projected growth scenarios. CARE Policy 19.1 is for the County, by 1991, to initiate agreements with the Southwest Florida Water Management District or appropriate university to scientifically determine environmentally safe construction setback and buffer distances from wetlands, floodplains and water bodies (e.g. SJRWMD Wekiva River study). Within one year after completion of this study, the County shall use the results of the study to amend the County's Land Alteration and Landscaping Ordinance and Zoning Code, if such setbacks and buffer distances are determined to be warranted by the study. Until such study is completed and used to amend County ordinances, all current setbacks shall remain in effect. CARE Policy 19.2 states: By 1992, the County shall develop a comprehensive program, which may include tax incentives and transfer of development rights, to encourage the clustering of development away from environmentally sensitive areas, essential wildlife habitat or economically important agricultural or mineral resources. CARE Policy 19.3 provides: During the development review process, the County shall promote the preservation of representative examples of upland native plant communities by encouraging the use of the upland forest density credit incentive provision of the [FLUE]. CARE Policy 19.4 states that the County will consider developing a review process to provide incentives for planned unit developments that provide environmental benefits beyond what are required by law. CARE Policy 19.5 provides that the County will review its land development regulations to "better address the cumulative impact [of development] on the environment." CARE Policy 19.6 is: The County shall continue to encourage infilling and growth within identified and environmentally acceptable "activity centers," and shall discourage urban sprawl. CARE Policy 19.7 is for the County, in cooperation with the Southwest Florida Water Management District, to consider adopting appropriate modifications to current land development regulations which will reduce the removal of natural upland vegetation caused by site filling and will maintain natural drainage patterns and water table levels, where feasible. CARE Policy 19.8 states: The County shall identify Resource Protection Areas on the Future Land Use Map series. Specific policy directives which provide for special protective measures for all Resource Protection Areas, except Lake Thonotosassa, are located in one or more of the following elements: [CARE], Coastal . . ., and [FLUE]. See the definition of Resource Protection areas for both general and specific policy references. Policies which provide for special protective measures specially for Lake Thonotosassa shall be developed and included in the [Plan] after completion and approval of the Surface Water Improvement and Management Plan for Lake Thonotosassa by the Southwest Florida Water Management District. The CARE defines "Resource Protection Areas" as: Land or water bodies which are ecologically or economically significant natural resources for which special protective measures have been, or need to be established. Resource Protection Areas include the following [in each case, general citations to applicable elements of the Plan have been omitted]: --Hillsborough River and major tributaries; --Alafia River and major tributaries; --Little Manatee River and major tributaries; --Tampa Bay and associated tidal wetlands; --Cockroach Bay Aquatic Preserve; --Lake Thonotosassa; --Significant and essential wildlife habitat; --Areas of high aquifer recharge/ contamination potential; --Public potable water wellfields and their cones of influence; --Areas of major phosphate deposits. CARE, pages 99-100. Goal A of the Stormwater Element is to "[m]inimize the hazards of flooding attributable to stormwater runoff." Stormwater Element Objective 1 is to "[e]valuate the storage and discharge characteristics of existing stormwater conveyance, detention and retention systems, and identify existing and potential future flooding concerns." Stormwater Element Policy 1.1 is to complete, by 1996, a comprehensive stormwater management master plan. Stormwater Element Objective 2 is to "[d]evelop and implement programs to control flooding attributable to, and to maximize the usefulness of, stormwater runoff." Stormwater Element Policy 2.8 states: Total flood volume compensation will continue to be required for new developments which encroach into and displace 100-year flood storage or floodplain areas. Further, by [fiscal year 19]91, a program to control encroachment within 100-year flood conveyance areas will be developed and implemented. Stormwater Element Policy 2.10 provides that, by 1992, the County shall develop and implement a program to "improve groundwater recharge through the use of private and public stormwater management facilities." Stormwater Element Policy 2.11 states that new development will continue to be encouraged, through application of existing local regulations, to maintain, with minimal disturbance to natural characteristics, those streams, lakes wetlands, and estuaries for which stormwater conveyance and/or attenuation potential is significant. Stormwater Element Policy 2.15 provides: The use of detention facilities will be the preferred alternative to improving conveyance to alleviate flooding problems, where physically and environmentally practical and economically feasible. All flood control projects will seek to minimize, to the greatest extent practicable, impacts to wetland habitat, water quality and groundwater recharge functions. Where impacts are unavoidable, the projects will include measures to compensate for these lost functions. Goal B of the Stormwater Element is to "[m]inimize the degradation of water quality attributed to stormwater runoff." Stormwater Element Objective 4 is to "[i]dentify and evaluate the sources of water quality degradation which are related to stormwater runoff." Stormwater Element Objective 5 is to "[i]mplement programs that will maintain or improve the quality of stormwater runoff." Stormwater Element Policy 5.1 is to develop and begin to implement, by 1995, a program "to improve, "where economically feasible, the problem areas identified" in stormwater data- collection projects. The County will then require the use of Best Management Practices for "minimizing contributions of poor quality stormwater runoff to both groundwater and surface water bodies." Stormwater Element Policy 5.5 provides for the use of wetlands for stormwater treatment when effective pretreatment can ensure that the use of the wetlands will maintain or restore their long-term natural viability. Stormwater Element Policy 5.6 states that new stormwater management facilities may not discharge untreated stormwater runoff into the Floridan aquifer and that existing facilities that do so discharge into the Floridan aquifer will be modified where "economically feasible and physically practical." The goal of the Sewer Element is to "[p]rotect the [public] health, safety and welfare" and "protect and conserve the natural resources of Hillsborough County." Sewer Element Policy 1.1 is: Wastewater treatment facilities, prior to discharging to surface waters or natural wetlands, shall meet Advanced Wastewater Treatment standards. "Advanced Waste Treatment" is defined in the Sewer Element as "defined in Chapter 403.086, Florida Statutes or as amended in the future." Sewer Element, page 26. Sewer Element Policy 1.2 requires that "[w]astewater treatment facilities, prior to discharging to a managed artificial wetland or an irrigation system, shall meet or exceed Advanced Secondary Treatment Standards." "Advanced Secondary Treatment Standards" are defined as "[s]econdary waste treatment plus deep-bed dual media filtration." Sewer Element Objective 2 is to "[p]rotect and conserve the potable water resources, both groundwater and surface water, of Hillsborough County and continue to utilize and expand, where viable, existing recovered water reuse systems." Sewer Element Policy 2.1 requires later phases of developments with recovered water systems to use such systems. Sewer Element Policy 2.3 requires that, by 1992, the County implement by ordinance "mandatory recovered water reuse." Sewer Element Objective 7 is to "[m]inimize the possibility of existing and future sources of wastewater adversely impacting groundwater, surface waters and quality of life." Sewer Element Policy 7.1 is to "[c]ontinue to require that septic tank systems connect to the County system where a County system is available unless undue hardship is proven." Sewer Element Policy 7.2 is to "re-examine the maximum allowable density for septic tank systems within various areas of Hillsborough County" not later than one year following completion of a study presently underway pursuant to the Water Quality Assurance Act of 1983. In the same timeframe, Sewer Element Policy 7.3 requires that the County develop a "program to identify existing septic tank systems . . . that have a high potential for contaminating groundwater or the aquifer." The first goal of the FLUE is to: Ensure that the character and location of land uses optimizes the combined potentials for economic benefit and the enjoyment and the protection of natural resources while minimizing the threat to health, safety and welfare posed by hazards, nuisances, incompatible land uses, and environmental degradation. FLUE Objective A-1 is: Development orders shall not be issued unless development is compatible with the physical conditions of the land, including, but not limited to, topographical and soil conditions, and development mitigates those adverse impacts that it creates upon the physical conditions of the land that may affect the health, safety and/or welfare of the people who live and work within those particular areas. FLUE Policy A-1.2 states that "[s]oil capability analyses for flood hazards, stability, permeability and other relevant soil characteristics shall be considered when planning for new development." FLUE Policy A-1.3 adds: "Development shall be prohibited in areas where the on-site sewage disposal facilities would be located on soils unsuitable for such uses, unless the soils on the site can be altered to meet state and local environmental land use regulations." FLUE Policy A-1.4 provides that development within areas designated as "volume or peak sensitive" shall be subject to "higher performance standards to mitigate stormwater runoff." The Plan defines "Peak Sensitive Lands" as "[l]and that is prone to flooding because the outfall is inadequate to handle the water flow." FLUE, page 142. The Plan defines "Volume Sensitive Lands" as: Lands that drain into areas that do not have a positive outfall. Positive outfall is the condition when the natural or man-made stormwater conveyance system that drains the land is functioning adequately. This includes man-made swales, waterways or other means of conveyance systems. This does not include sheet flow. FLUE, page 147. FLUE Policy A-1.5 requires: "All development within the 100 year floodplain shall be in strict conformance with all development regulations that have jurisdiction development regulations." Certain future land use designations bear directly upon the natural resources of the County. Other future land use designations, although affecting natural resources, will be addressed in the following sections concerning urban sprawl and the coastal high hazard area. Three designations are especially important in protecting natural resources. They are Natural Preservation, Environmentally Sensitive Areas, and Major Recreation and Open Space. The Natural Preservation designation is used to designate major publicly owned or managed lands for primarily conservation purposes. Typically, these lands are environmentally unique, irreplaceable or valued ecological resources. Some of these lands may be suitable for compatible recreational use. FLUE, page 142. The Land Use Plan Categories section of the FLUE describes the intent of the Natural Preservation designation as follows: To recognize public lands of significant environmental importance set aside for primarily conservation purposes. No residential is permitted except for county facilities determined necessary to serve as a caretaker of the recreational or environmental property. All other development is prohibited in these areas except for compatible recreational development. Educational uses shall be limited to those which utilize the natural amenities found on the site, i.e., the study of flora [or] fauna . . .. FLUE, page 125. FLUE Policy A-3.1 promises that the County will study the possibility of adopting land development regulations providing for a transfer of development rights from land that is under consideration for Natural Preservation designation, as well as land under a Rural designation that is in long-term agricultural use. FLUE Policy A-3.2 prohibits, in Natural Preservation designations, any "new development [or] expansion [or] replacement of existing development[,] unless development is undertaken by federal, State or local government in the public interest, and the impacts are mitigated." The Environmentally Sensitive Areas designation has been discussed at length in the preceding section. The Land Use Plan Categories section of the FLUE describes the intent of the Environmentally Sensitive Areas designation as follows: To designate those privately owned lands that are environmentally sensitive and classified as Conservation or Preservation Areas as defined in the [CARE]. Development in these areas may be restricted by federal, state, and/or local environmental regulations. Development projects will be evaluated for compliance with the [CARE] and Coastal [Element]. The use of Environmentally Sensitive Areas for residential density credits is described in the [FLUE]. The Environmentally Sensitive Area designations on the Land Use Plan Map are very generalized and may not be exhaustive of all sites. On- site evaluation will be necessary for specific project review. FLUE, page 126. The Major Recreation and Open Space designation is used to designate, geographically on the Future Land Use Plan Map and/or textually in the [FLUE], those major existing park, recreation, and/or open space facilities available for public use, including those which may be privately owned, and for which the primary purpose is not conservation. This land use category is not intended for use in designating those lands used for calculating densities for residential projects as described in the "Density Credits" provision in the "Implementation Section["] of the [FLUE] or in designating those similarly used lands that are accessory to non-residential projects. This future land use plan classification is subject to the Goals, Objectives and Policies and the exceptions and provisions of the [FLUE], each of the other elements in the [Plan], and to all applicable development regulations. FLUE, page 143. The Land Use Plan Categories section of the FLUE describes the intent of the Recreation and Open Space designation as follows: To designate major existing parks and recreational facilities (regional, district, or community level), for which the primary purpose is not conservation. A more complete mapping of existing and proposed or needed parks is a function of the Recreation and Open Space Element. No residential is permitted except for county facilities determined necessary to serve as an employee serving the function of a caretaker of the property. FLUE, page 123. FLUE Policy A-3.4 states that "[r]ecreational development must be compatible with and sensitive to the surrounding natural systems." Numerous provisions in the FLUE address natural resources, without referring to the Natural Preservation, Environmentally Sensitive Areas, and Major Recreation and Open Space designations. FLUE Objective A-8 provides: Development must mitigate the adverse impacts upon the natural, environmental systems as described and required within the [CARE] and [Coastal Element]. FLUE Policy A-8.1 states: "The natural environment shall be protected, in part, by encouraging future population growth into existing urbanized areas." FLUE Policies A-8.2, A- 8.3, and A-8.4, which have been discussed above, provide for the protection of Conservation and Preservation Areas and describe the upland forest density credit incentive and density formulas regarding Environmentally Sensitive Areas. FLUE Policies A-8.5 and A-8.6 promise protection, "by a system of performance standards" left undefined in the Plan, for areas with "high potential for groundwater contamination" and "high aquifer recharge," respectively. FLUE Policy A-8.8 is to [r]equire that the littoral zones and photic zones of man-made stormwater management systems be designed to provide physical and chemical filtration of stormwater consistent with adopted levels in the [Plan] and subsequently adopted development regulations, [as well as] provide for wildlife habitat (primarily wading birds). FLUE Policy A-8.9 offers the use of publicly owned land designated as Major Public/Semi-Public for "appropriate multiple uses, such as parks, stormwater management systems and preservation of natural habitats." FLUE Policy A-8.10 is to "[e]ncourage the use of pervious pavement" through land development regulations. FLUE Policy A-8.11 requires the County to identify, during the rezoning process, any land that has been identified for possible acquisition by the Environmental Land Acquisition and Protection Program. FLUE Policy A-8.12 states the County "shall protect significant wildlife habitat." FLUE Policy A-8.13 provides that the County will "[p]reserve wetlands by discouraging the use of mitigation, dredge and fill and similar development activities by revising the development regulations to strictly limit such practices." FLUE Objective B-9 is to "[p]rotect environmentally sensitive areas from degradation or damage from agricultural activities by establishing regulatory activities." FLUE Policy B-9.2 is to "[e]stablish protective controls, which could include animal 'density' limits[,] on those grazing lands having environmentally sensitive areas subject to damage or degradation from over-grazing by pre- identified grazing species." FLUE Objective B-10 is to "[p]rotect the water supply needed by agriculture through regulatory mechanisms." FLUE Policy B-10.1 is to "[r]equire adoption or conversion to water conservation techniques that are beneficial for aquifer recharge and the maintenance of near normal water tables." FLUE Policy B-10.2 is to establish a phased-in program of water conservation. Addressing the County's rivers, the second goal of the FLUE, which appears at the beginning of the River Resources section, is: To make the rivers of Hillsborough County cleaner, safer and more attractive, protect the natural functions and wildlife habitats in the river corridors and promote the economic and recreational benefits provided by these water bodies. FLUE Objective C-1 is, by 1995, to "maintain or improve the quality of water in [County] rivers where the water quality does not meet or exceed state water quality standards for [their] designated use." FLUE Policy C-1.1 states: The developer of any project along the rivers shall provide stormwater management systems which filter out pollutants before the stormwater enters the rivers, in accordance with the Florida Department of Environmental Regulation and the Southwest Florida Water Management District rules including the exemption provisions of these rules. New drainage outfalls along the rivers shall be designed with stormwater treatment facilities rather than discharging stormwater directly into the rivers. Where environmentally feasible, the stormwater discharge from a detention pond shall flow into the rivers through a vegetated swale. FLUE Policy C-1.2 "[p]rohibit[s] discharges of raw sewage to the rivers and tributaries." FLUE Policy C-1.3 "[p]rohibit[s] any solid waste landfills and hazardous material facilities in unincorporated Hillsborough County that may adversely affect the rivers and tributaries." FLUE Objective C-2 is: By 1990, the County will require the preservation of natural shorelines and reverse the trend toward hardened shores and channelization. . . . FLUE Policy C-2.1 states: "Shore alteration which would harden riverbanks shall be prohibited, except in cases of overriding public interest." FLUE Policy C-2.2 requires the improvement of publicly owned or controlled lands by the "restoration of vegetated riverbanks." FLUE Policy C-2.3 requires the conservation and preservation of natural riverbanks and natural levees, except in cases of overriding public interest. FLUE Objective C-4 provides that, by 1992, the County will "establish standards for development in river corridors." FLUE Policy C-4.1 prohibits the construction of new overhead utilities within 250 feet of the rivers unless underground placement is environmentally or technically unsound. FLUE Objective C-5 provides that, by 1991, the County will "require the preservation and enhancement of wildlife habitats and archaeological resources." FLUE Policy C-5.4 requires the County to "restrict development activities in the river corridors which would adversely affect significant and essential wildlife habitat, in accordance with the terms of Objective 14 and related policies thereunder of the [CARE]." FLUE Policy C-6.1 prohibits the removal, within 100 feet of the rivers, of healthy, native trees of five inches diameter at breast height unless "reasonable property utilization is not possible without tree removal or in cases of overriding public interest." The third, fourth, and fifth goals in the FLUE pertain to the Hillsborough, Alafia, and Little Manatee Rivers, respectively. The third goal in the FLUE is "[t]o make the Hillsborough River cleaner, safer and more attractive." FLUE Objective C-7 is, by 1995, to "improve the quality of water in the river where it does not meet or exceed state water quality standards for its designated use, and protect this major source of drinking water." FLUE Policy C-7.2 states: The construction, reconstruction, extension, or alteration of any privy, cesspool, septic tank, drain field, or other sewage disposal device within . . . 200 feet, measured from the mean annual flood line, of the Hillsborough River and its tributaries from the Pasco County line, to the city limits of the City of Tampa, shall be prohibited. This policy shall not prohibit recommended maintenance of existing septic systems if no alternative means of sewerage treatment is available. FLUE Policy C-7.3 is to "[p]revent further destruction of desirable natural vegetative buffers along the Hillsborough River and its tributaries." FLUE Policy C-7.4 is to: Prevent potential contamination by effluent disposal from a wastewater treatment plant within the drainage basin by requiring advanced treatment and viral reduction of all sewage in the drainage basin which is part of an effluent disposal program. FLUE Objective C-8 is, by 1990, to "reverse the trend toward hardened shores and channelization." FLUE Policy C-9.1 provides: "New marinas shall be prohibited on the upper Hillsborough River." "To prevent riverbank erosion, protect wildlife habitat, and ensure public safety," FLUE Policy C-9.6 requires that the part of the Hillsborough River north of 56th Street be posted with "idle speed, no wake" signs. FLUE Objective C-10 is, by 1992, to "establish standards for development in the river corridor." FLUE Policy C- 10.2 states: "No additional areas shall be designated with industrial land use plan categories within 500 feet of the river." FLUE Policy C-10.3 requires the County to establish a new future land use designation or zoning classification to be known as "Riverfront." Land use guidelines that "should be addressed" in the new classification include performance standards precluding uses that pollute the river or eliminate visual access by the public, lowering densities for vacant private parcels along the upper river, and prohibiting heavy activities such as parking lots, truck service roads, loading docks, warehouses, manufacturing plants, ship building and repair, and dredging equipment operators. FLUE Objective C-11 is, by 1992, to "implement construction and placement standards for ramps, docks, and seawalls." FLUE Objective C-12 is, by 1994, to "manage the Hillsborough River as an important community asset and provide appropriate public access to this valuable natural amenity." FLUE Objective C-13 is, by 1991, to "preserve and enhance wildlife habitats and preserve archaeological resources." FLUE Policy C-13.1 states: "Draining, clearing or filling wetlands, including hydric hammocks[,] shall be prohibited within 500 feet of the river." FLUE Objective C-14 states: By 1990, preserve the rural character of the Upper Hillsborough River by discouraging additional development except for those sites improved or developed that are dedicated to passive recreational pursuits within the river corridor. . . . FLUE Policy C-14.1 states: "The upper Hillsborough River shall be managed as a wildlife habitat corridor to provide an area for wildlife passage." FLUE Policy C-14.3 prohibits in the upper Hillsborough River "additional boat docks and ramps," but not canoe launches. FLUE Policy C-14.4 prohibits, within 500 feet of the upper Hillsborough River and its tributaries, parking lots and service roads. The fourth goal in the FLUE addresses the Alafia River. The goal is: "To preserve, protect and promote the Alafia River and its natural resources and recreational benefits." FLUE Objective C-15 is: By 1995, to maintain water quality, and improve water quality where it does not meet or exceed State water quality standards for its designated use, thereby protecting and improving the habitat for marine life. . . . FLUE Objective C-16 is: "By 1991, preserve and restore natural vegetation, and wildlife habitats and preserve archaeological resources." FLUE Policy C-16.1 states: Draining, clearing or filling wetlands, including hydric hammocks, which comprise the riverine swamp system shall be prohibited within 500 feet of the river. FLUE Policy C-16.2 provides: Encourage the reclamation of mined lands along the Alafia River with native vegetation and encourage public acquisition for wildlife corridors, where appropriate. FLUE Objective C-17 is, by 1991, to "protect terrestrial and marine wildlife and their habitats." FLUE Policy C-17.1 requires the County to post reduced speed signs in areas of known manatee habitation. FLUE Objective C-18 is, by 1995, to "minimize river use conflict and mitigate public nuisances that adversely affect inhabitants along the river." FLUE Policy C-18.1 recognizes the river as important for canoeing as well as other recreational pursuits. FLUE Objective C-19 is, by 1990, to "preserve the natural shoreline and prevent further channelization." FLUE Policy C-19.1 "[p]rohibit[s] backfilling of waterfront properties or extension of these lots through artificial means." FLUE Objective C-20 is, by 1992, to "establish standards for development within the river corridor." FLUE Policy C-20.3 states: Septic tank and drainfield installation shall be prohibited within 200 feet of the Alafia River and its tributaries except in such cases where the 200-foot criterion cannot be met because of lot size. In such cases, placement and construction of such facilities shall be in accordance with State law and shall prevent adverse impact to water quality. FLUE Policy C-20.4 states: "No additional heavy industrial land use designations shall be located within 500 feet of the river." The fifth goal in the FLUE pertains to the Little Manatee River. The goal is: "To recognize and maintain this unique water resource which provides economic and recreational opportunities as well as vital wildlife habitat." FLUE Objective C-21 states: By 1995, water quality in each appropriate water classification found in the Little Manatee River will be maintained or improved where it does not meet or exceed state water quality standards for its designated use. ... FLUE Policy C-21.1, which generally prohibits the installation of septic tanks within 200 feet of the Little Manatee River and its tributaries, is otherwise identical to FLUE Policy C-20.3, which applies to the Alafia River. FLUE Objective C-22 is, by 1991, to "preserve wildlife habitats and archaeological resources." FLUE Policy C-22.1 provides that the County shall "participate" with the Florida Department of Natural Resources to "fully implement the Cockroach Bay Aquatic Preserve Management Plan." FLUE Policy C-22.2 prohibits "[d]raining, clearing or filling wetlands, including hydric hammocks, . . . within 500 feet of the river." FLUE Policy C-22.3 states that, until scientifically defensible setbacks and buffers are determined: clearing or filling of natural plant communities within 50 feet of the Environmental Protection Commission wetland jurisdictional line or within 100 feet of the mean and ordinary high water line, whichever is greater, shall be restricted in urban and suburban land use categories. FLUE Policy C-22.4 is to protect manatees by "posting reduced speed signs in areas of known manatee habitation." FLUE Objective C-23 is, by 1990, to: minimize urban encroachment upon the river bank by encouraging the establishment of a "green" river corridor. River corridor preservation can best be achieved through protection of the shoreline, and associated wetlands and uplands. . . . FLUE Policy C-23.1 states: "No heavy industrial land use designations shall be located within 500 feet of the river." FLUE Policy C-23.2 provides: "The Little Manatee River shall be recognized as providing important wildlife habitat and managed as a corridor for wildlife passage." FLUE Policy C-23.3 states: "The Little Manatee River shall be recognized as an important recreational resource." FLUE Policy C-23.4 adds: Recreation facilities in the Little Manatee River corridor shall be designed to minimize impacts upon essential and significant wildlife habitat. This is to be achieved by encouraging passive river corridor use, such as hiking, picnicking, nature study, photography, fishing, and canoeing. FLUE Policy C-23.5 prohibits parking lots and service roads within 500 feet of the Little Manatee River and its tributaries east of US 41. FLUE Objective C-24 is, by 1990, to "develop additional policies and strategies addressing the uniqueness and proper protection and use of the Little Manatee River." FLUE Policy C-24.2 states: "Appropriate provisions from the Cockroach Bay Aquatic Preserve Management Plan shall be considered for incorporation as policies in this plan." Policy C-24.3 promises the evaluation of the need for establishing a new land use category or zoning overlay "to ensure proper protection and use of the Little Manatee River and associated natural resources." FLUE Objective C-30 provides: Regulations and performance standards shall be developed to ensure that water quality and quantity, environmentally sensitive areas, wildlife habitats, rivers and creeks are protected from degradation by development. FLUE Policy C-30.2 states that the County "shall require the location and design of public roads and bridges within stream riverine corridors to minimize impacts adverse to wildlife habitats and vegetative communities." FLUE Policy C-30.4 provides: Designate as River Corridor Overlay Districts, riverine corridors within the Urban Level land use categories, which meet the following criteria in addition to the policies related to River Corridor Overlay Districts under the "River Resources" section within the [FLUE]. The qualifying criteria are that the water must be of Class III standards, the water body must provide "ecological benefits," most of the part of the water body proposed for designation must have a natural shore, and a 25 year floodplain map for the part of the water body proposed for designation must be available for public inspection. FLUE Policy C-30.6 provides: Restrict clearing or filling of natural plant communities within 50 feet of the Environmental Protection Commission wetland jurisdictional line of rivers and creeks designated as River Corridor Overlay Districts or within 100 feet of the mean and ordinary high water line of such rivers and creeks, whichever is greater. If no beneficial use of the property is possible without clearing or filling within this area, impose conditions which will mitigate the adverse impact of these activities on wildlife habitat, native vegetation and natural stormwater filtration systems. FLUE Policy C-30.7 is to "[e]ncourage the use of stilted structures rather than fill to meet flood elevation construction requirements within the River Corridor Overlay District." FLUE Policy C-30.8 is to "[r]estrict hardened shores (seawalls) within the River Corridor Overlay district to areas threatened by severe erosion." The Coastal Element addresses natural resources in the coastal area of the County. Coastal Element Policy 1.3 requires the County to reduce the need for interim wastewater treatment plants by planning for the construction of regional wastewater treatment facilities to serve areas designated for higher densities. Coastal Element Policy 1.4 provides that the County shall "continue to develop and use environmentally acceptable effluent disposal alternatives to surface water discharge to Tampa Bay and its tributaries, including but not limited to reuse for irrigation and industrial purposes." Coastal Element Policy 1.7 states: Where economically feasible, the County shall provide improved domestic wastewater treatment service to coastal areas where persistent water quality problems in Tampa Bay are clearly attributable to poorly functioning septic treatment systems. Coastal Element Policy 1.11 provides: By 1991, the County shall require that existing developments planned for expansion, modification or replacement in the coastal area provide or support stormwater treatment improvements within the affected drainage basin where treatment facilities are lacking. Where economically and environmentally feasible, the County shall require retrofitting of stormwater treatment facilities in urbanized coastal areas lacking such facilities. Coastal Element Policy 1.12 states: Where economically and environmentally feasible and consistent with the Surface Water Improvement Management Plan for Tampa Bay, the County shall consider dredging and removal of polluted estuarine sediments, and clean filling deep dredged areas, as a means of improving adjacent estuarine water quality. 2. Coastal High Hazard Area and Hazard Mitigation The only FLUE provision addressing the coastal area and coastal hazards is FLUE Policy A-1.6, which promises: Performance standards for new developments shall be established within coastal areas, as identified in the [Coastal Element], in order to protect the population in the coastal areas, and to minimize property damage in the event of a hurricane. Capital Improvements Element (CIE) 1.D.2 provides that the levels of service for public facilities, as set forth in the CIE, are subject to overriding conditions and limitations contained in the Coastal Element. In addition, CIE Objective 5 states: "The County shall protect the coastline and avoid loss of life and property in coastal areas by minimizing land development and public facilities in coastal areas. [Rule] 9J- 5.016(3)(b)2." CIE Policy 5.A states: "Publicly funded infrastructure shall not be constructed within the coastal high hazard area unless the expenditure is for: 5.A.1: Restoration or enhancement of natural resources or public access; 5.A.2: Land application of treated effluent disposal (irrigation) on public and private open spaces; 5.A.3: Flood-proofing water and sanitary sewer facilities; 5.A.4: The development or improvement of public roads and bridges which are on the Hillsborough County Metropolitan Planning Organization long range plan or the facility will serve a crucial need by ameliorating the evacuation time of residents of the County; 5.A.5: Reconstruction of seawalls that are essential to the protection of only existing public facilities or infrastructure; 5.A.6: A public facility of overriding public concern as determined by the Hillsborough County Board of County Commissioners; 5.A.7: The retrofitting of stormwater management facilities for water quality enhancement of stormwater runoff; or 5.A.8: Port facilities. Coastal Element Policy 6.1 defines the coastal high hazard area as the part of the County included in the Federal Emergency Management Agency V Zone and the area requiring evacuation during a Category 1 hurricane event. A Category 1 hurricane is characterized by winds of 74-95 miles per hour, which will cause damage primarily to foliage and unanchored mobile homes; storm surge 6-8 feet above normal; and inundation of low-lying coastal roads. Coastal Element, page 85. Coastal Element Objective 6 is to: Restrict development of residential population centers in the coastal high hazard area and require all development to meet standards established for the coastal area. Coastal Element Policy 6.2 requires that "[n]ew development within the coastal high hazard area shall be subject to a formal site plan review process." The process shall require owner-supplied data as to the impact of the proposed development upon existing infrastructure in the coastal high hazard area, evacuation clearance times, and shelter space. Coastal Element Policy 6.3 states that new development or "substantial expansions" of existing uses, except for government facilities, shall be approved through "a planned unit development process" if the development consists of commercial or industrial development on more than five acres of land or residential development exceeding the requirements of a "minor subdivision," as defined in the land development regulations. Policy 6.3 adds that developments within the coastal high hazard area and the I-75 corridor shall be subject to the more restrictive requirements. Coastal Element Policy 6.5 prohibits the development of "manufactured home communities" in the coastal high hazard area unless they meet the standards of the Southern Standard Building Code. Coastal Element Policy 6.6 is that, by 1994, the County shall, by land development regulations, require the underground installation of all utility lines in the coastal high hazard area. Coastal Element Policy 6.7 is that, except for cases of "undue hardship," "[t]he use of septic tanks for new development shall be prohibited in the coastal high hazard area." Coastal Element Objective 7 is to ensure the "orderly development and use" of the Port of Tampa by giving "priority to locating water-dependent and water-related land uses along the shoreline of the coastal area." Coastal Element Policy 7.1 provides that the County, by 1993, will amend the "Future Land Use Element and Map" to create a new future land use designation for "marine-related land uses." The designation will include criteria for siting water-dependent and water-related land uses. Coastal Element Policy 7.5 prohibits the development of new sites for heavy industrial uses along the shoreline of the coastal area unless the uses are "water-dependent or water- related or unless an overriding public interest is demonstrated." Coastal Element Objective 10 is: "Limit public expenditures for infrastructure and facilities in the coastal high hazard area." Coastal Element Policy 10.3 provides: "Wastewater treatment facilities shall not be constructed within the coastal high hazard area unless the expenditure meets the criteria of Policy 10.2." Coastal Element Policy 10.2 is the same as CIE Policy 5.A. Coastal Element Policy 13.1 states: "Interim wastewater treatment plants shall not be permitted in the coastal high hazard area except where the County service will be available within five (5) years." Coastal Element Policy 13.2 provides that the County will not assume jurisdiction for maintaining roadways in the coastal high hazard area unless the roadway is on the future Traffic Circulation Map. Coastal Element Policy 13.3 states that, by the 1993 hurricane season, the County shall complete an inventory of existing infrastructure in the coastal high hazard area and develop a program to relocate or retrofit such facilities where feasible and as replacement becomes necessary. Coastal Element Policy 13.4 is that the County "shall ensure" that future development and redevelopment within the coastal high hazard area is "consistent with coastal resource protection and will not increase clearance times along evacuation routes." Coastal Element Policy 13.6 is that the County shall not approve any "new solid waste or hazardous waste management sites" in the coastal high hazard area. Coastal Element Policy 12.2 is that the County, by the 1992 hurricane season: shall prepare a post-disaster redevelopment plan which will address long-term development, repair, and redevelopment activities, and which will include measures to restrict and eliminate inappropriate and unsafe development in the coastal high hazard area. Coastal Element Policy 12.5 provides that, by the 1992 hurricane season, the County "shall adopt a redevelopment decision-making matrix for deciding whether public infrastructure should be rebuilt, relocated, or structurally modified." Coastal Element Objective 11 provides: Through the year 2010 the County shall maintain the clearance times identified in the Tampa Bay Regional Planning Council 1988 Tampa Bay Regional Hurricane Study. Any proposed development shall not increase these clearance times. Coastal Element Policy 11.2 adopts a level of service standard of 20 square feet per person for shelter space. Coastal Element Policy 11.5 states that, by 1991, the development review process shall consider the effect of a proposed development in the hurricane vulnerability zone, which includes the coastal high hazard area, on evacuation clearance times and the number of persons requiring shelter. Coastal Element Policy 11.7 provides that each new mobile home park "not located" in the hurricane vulnerability zone shall include a building for use as a hurricane shelter. 3. Urban Sprawl FLUE Policy A-2.1 states: "Development shall not exceed the densities and intensities established within the [Plan]." According to the Implementation section of the FLUE, "[i]t is the intent of the [FLUE] to permit the maximum densities allowed within each land use plan category." FLUE, page 55. Many of the future land use categories of the Plan and their densities are set forth at Paragraph 219 above. The remaining categories and any permitted residential densities (expressed as dwelling units per gross acre) are: Community Commercial (20:1); Commercial--Office (20:1); Regional Commercial (20:1); Electrical Power Generating Facility (1:5); Scenic Corridor Overlay; Research/Corporate Park; Light Industrial; Light Industrial-- Planned; Heavy Industrial; Natural Preservation; Major Recreation and Open Space; Major Public/Semi-Public; and Environmentally Sensitive Areas (uses described in preceding section). The Land Use Plan section of the FLUE discusses each of the future land use designations in terms of service level, typical uses, density (applicable to residential uses only), maximum floor area (applicable to commercial, office, and industrial uses only), and intent of designation. The densities have been set forth above. Six designations fall exclusively under the Rural service level. These are Agricultural/Mining, Agricultural, Agricultural/Rural, Rural Estate, Rural Residential, and Rural Residential Planned. The typical uses of Agricultural/Mining include: farms, ranches, feed lots, residential uses, rural scale neighborhood commercial uses, offices, industrial uses related to agricultural uses, and mining related activities. Non-residential uses shall meet established locational criteria for specific land use. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 98. The maximum floor area for Agricultural/Mining is: Rural scale neighborhood commercial, office or industrial up to 40,000 sq. ft. or .25 FAR, 17/ whichever is less intense. Actual space footage limit is dependent on functional classification of roadway intersection where project is located. FLUE, page 98. The intent of Agricultural/Mining is: To designate either those areas of long term agricultural character, or those areas currently involved in agricultural productivity, or other rural uses. This category will also permit residential, rural scale neighborhood commercial, office, and industrial uses in those areas meeting established locational criteria. As long as no subdivision of land is involved, group quarters, temporary housing, rehabilitation centers and residential uses for agricultural/rural related activities can be exempt from the density limitations subject to the [FLUE] and applicable development regulations. In addition, mining activities and commercial and industrial uses directly related to or serving the local mining activities may be permitted in appropriate locations, in conformance with adopted [land development] regulations. Commercial and office above 5000 sq. ft.[,] multi-purpose projects and multi-use projects shall require a planned zoning district. FLUE, page 98. The typical uses, maximum floor area, and intent of Agricultural and Agricultural/Rural are the same as those stated for Agricultural/Mining. Densities are the main difference among the Agricultural/Mining (1:20), Agricultural (1:10), and Agricultural/Rural (1:5) designations. In addition to allowing a density of 1:2.5, the Rural Estate category differs in other respects from the other categories classified as rural in terms of service level. Typical uses for Rural Estate add "multi-purpose projects" and omit "feed lots," "industrial uses related to agricultural uses," and "mining related activities." Maximum floor area substitutes "multi-purpose projects" for "industrial." The intent of Rural Estate is: To designate areas that are best suited for agricultural development, usually defined as located on Short-Term Agricultural Lands, and for compatible rural residential uses. Other uses including rural scale neighborhood commercial, office and multi-purpose projects may be permitted when complying with the [FLUE] and applicable development regulations and conforming to established locational criteria for specific land use. Commercial and office above 5000 sq. ft., multi-purpose projects and multi-use projects shall require a planned zoning district. FLUE, page 101. The typical uses and intent of Rural/Residential and Rural/Residential Planned are the same as those stated for Rural Estate, except the Rural/Residential Planned also allows community commercial uses and clustered mixed use. A planned zoning district is required for the Rural/Residential Planned designation if the proposed commercial or office use is over 3000 square feet. The densities are different among the three designations. The Rural/Residential allows 1:1. Rural/Residential Planned allows the same density if the project is a Planned Village Concept on at least 160 acres; otherwise, the allowable density is 1:5. The maximum density for Rural/Residential Planned is allowable only if clustering and mixed uses are proposed. The concepts of mixed use and clustering specified for the Rural/Residential Planned are explained as follows: Mixed use . . . must demonstrate integration, scale, diversity and internal relationships of uses on site as well as provide shopping and job opportunities, significant internal trip capture and appropriately scaled residential uses. Land development regulations shall specify the thresholds for shopping, job creation and trip capture rates for developments appropriate to the scale of the project. Clustering . . . will be demonstrated through higher than typical residential net densities. Land development regulations shall provide thresholds for net densities required relative to project size and location, and will be used to determine allowable gross density. FLUE, page 103. The Suburban service level contains two designations: Low Suburban Density Residential and Low Suburban Density Residential Planned. The typical uses of Low Suburban Density Residential are: Residential, suburban scale neighborhood commercial, office uses, and multi-purpose projects. Non-residential uses shall meet locational criteria for specific land use. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 104. The typical uses of Low Suburban Density Residential Planned are the same except they include suburban scale community commercial and clustered mixed use projects. The maximum floor area of Low Suburban Density Residential is: Suburban scale neighborhood commercial, office, or multi-purpose projects limited to 110,000 sq. ft. or .25 FAR, whichever is less intense. Actual space footage limit is dependent on functional classification of roadway intersection where project is located. FLUE, page 104. The maximum floor area of Low Suburban Density Residential Planned is the same except the floor area ratio is .5, which governs certain mixed use projects: Mixed use projects utilizing the Planned Village Concept are not limited by square footages but may develop up to .5 FAR. Square footages will be limited by the scale and relationship within the project. In addition, mixed use projects utilizing the Planned Village Concept shall not be limited by the locational criteria found elsewhere for neighborhood commercial uses. Mixed use projects shall demonstrate internal relationships and pedestrian integration among uses. FLUE, page 105. The intent of the Low Suburban Density Residential designation is: To designate areas that are best suited for non-urban density residential development requiring a limited level of urban services, including in appropriate locations lots large enough to safely accommodate private wells and septic tanks or a combination of septic tanks and public water. Some areas, because of environmental or soil conditions, would be appropriate for only public water and sewer in this designation. In addition, suburban level neighborhood commercial, office and multi-purpose projects serving the non-urban areas may be permitted, subject to the Goals, Objectives, and Policies of the Land Use Element and applicable development regulations and conforming to established locational criteria for such land use. Commercial and office uses above 3000 sq. ft. and all multi-purpose and mixed use projects shall require a planned zoning district. FLUE, page 104. The intent of the Low Suburban Density Residential Planned appears erroneous, as it repeats the intent of the Rural/Residential Planned designation, including "rural residential uses" and "rural scale" commercial uses. The intent of the Low Suburban Density Residential Planned should probably state: "non-urban density residential development requiring a limited level of urban services" and the "suburban scale" commercial uses, which is the intent of the Low Suburban Density Residential. The Implementation section of the FLUE probably should have stated the intent of the Low Suburban Density Residential Planned designation is the same as the intent of the Low Suburban Density Residential designation except to add "suburban level community commercial, clustered mixed use, and multi-purpose projects." The densities for Low Suburban Density Residential and Low Suburban Density Residential Planned are both 2:1. However, this density is applicable to the Low Suburban Density Residential Planned only if the proposed project is a Planned Village Concept on at least 160 acres. Otherwise, the density for Low Suburban Density Residential Planned is 1:5. The Low Suburban Density Residential Planned density contains the same description of mixed use and clustering as is found in the Rural/Residential Planned designation. There are 14 designations exclusively within the Urban service level. The two lowest densities, among categories that are predominantly residential, are Suburban Density Residential and Low Urban Density Residential, which are, respectively, 4:1 and 6:1. Each density contains the following condition: This maximum residential density is provided only as a limit for application in situations which represent an ideal set of circumstances with regard to the compatibility of the proposed development with surrounding land uses, existing and/or approved, and with regard to the adequacy and availability of public facilities. FLUE, pages 106 and 107. The typical uses for Suburban Density Residential and Low Urban Density Residential are identical: Residential, urban scale neighborhood commercial, office uses, multi-purpose and mixed use projects. Non-residential uses shall meet established locational criteria for specific land use. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, pages 106 and 107. Disregarding another apparent typographical error, 18/ the maximum floor area for each designation is identical: Urban scale neighborhood commercial, office, multi-purpose or mixed use projects limited to 175,000 sq. ft. or .25 FAR, whichever is less intense. Actual square footage limitation is dependent on functional classification of roadway intersection where project is located. FLUE, pages 106 and 107. Disregarding two more likely typographical errors, 19/ the intent for each designation is also identical, except for the bracketed notation that applies only to Low Urban Density Residential: To designate areas that are suitable for low density residential development. In addition, urban scale neighborhood commercial, office, multi-purpose and mixed use projects serving the area may be permitted subject to the Goals, Objectives, and Policies of the Land Use Element and applicable development regulations and conforming to established locational criteria for specific land use. Multi-purpose, mixed use projects and any development above 3.0 [5.0] dwelling units per gross acre on a site larger than 10 acres shall require a planned zoning district. FLUE, pages 106 and 107. The next three designations in the Urban service level are Low/Medium Density Urban Residential, Medium Density Urban Residential, and High Density Urban Residential, which provide densities, respectively, of 9:1, 12:1, and 20:1. 20/ Each density is subject to the condition quoted above for Suburban Density Residential and Low Urban Density Residential concerning ideally suited circumstances. Ignoring one typographical error in the case of the High Density Urban Residential designation, 21/ the typical uses for each of the three designations are also identical, except for a minor distinction in language, with those stated for Suburban Density Residential and Low Urban Density Residential. The maximum floor areas for each of the three designations are identical to those stated for Suburban Density Residential and Low Urban Density Residential except that the floor area ratio for High Density Urban Residential is 0.75, not 0.25. The intent of each of the three designations is the same as the intent of the Suburban Density Residential and Low Urban Density Residential designations with a minor change in language. The only differences are that the primary intent in each case is to designate an area suitable for the type of residential development suggested by the category's name, such as low-medium density. Also, a planned zoning district is required for each of the three designations if the proposed development is denser than 8:1 for Low/Medium Density Urban Residential, 10:1 for Medium Density Urban Residential, and 16:1 for High Density Urban Residential. The last three designations exclusively within the Urban service classification that are projected to contain significant residential uses are Urban Levels 1, 2, and 3 with respective densities of 12:1, 20:1, and 50:1. Each density contains the following condition: The maximum residential density is provided only as a limit for application in situations in which all Goals, Objectives, and Policies and applicable development regulations are being complied with, especially those regarding compatibility of the proposed development with surrounding land uses, existing and/or approved, and with regard to the adequacy and availability of public facilities. FLUE, pages 111, 112, and 113. The typical uses for Urban Levels 1, 2, and 3 are identical: Mixed use development. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, pages 111, 112, and 113. The maximum floor area ratios are 0.5, 1.0, and 2.5 for Urban Levels 1, 2, and 3, respectively. The intent of the Urban Level 1 designation is: The UL1 category may be located within three miles of I-75, bounded at the limits of the urban level category by existing or proposed arterial roads. This category of land use shall serve as a transitional area which emphasizes compatibility with adjacent plan categories. The UL1 area shall be more suburban in intensity and density of uses, with development occurring as the provision and timing of transportation and public facility services necessary to support these intensities and densities become available. Commercial uses shall be clustered at arterial and collector intersections. Strip development with separate driveway access for commercial uses shall be prohibited. Rezonings shall be approved through a planned unit development rezoning process which requires, at a minimum, integrated site plans controlled through performance standards to achieve developments which are compatible with surrounding land use patterns and the Goals, Objectives and Policies of the Land Use Plan. FLUE, page 111. The intent of the Urban Level 2 designation is: The UL2 category shall be compatible with adjacent urban land use categories such as UL1, UL3, research corporate park, and medium density residential. The UL2 areas shall be urban in intensity and density of uses, with development occurring as the provision and timing of transportation and public facility services necessary to support these intensities and densities are made available. Commercial uses shall be clustered at arterial and collector intersections. Strip development with separate driveway access for nonresidential uses to arterials shall be prohibited. Rezonings shall be approved through a planned unit development rezoning process which requires, at a minimum, integrated site plans controlled through performance standards to achieve developments which are compatible with surrounding land use patterns and the Goals, Objectives and Policies of the Land Use Plan. FLUE, page 112. The intent of the Urban Level 3 designation is: The UL3 category shall form a regional activity center which incorporates internal road systems, building clustering and mixing of uses, with development occurring as the provision and timing of transportation and public facility services necessary to support these intensities and densities are made available. Commercial uses shall be clustered at arterial and collector intersections. Strip development with separate driveway access for nonresidential uses to arterials shall be prohibited. The UL3 category should be surrounded by other urban level plan categories and be located at high level transit lines. Rezonings shall be approved through a planned unit development rezoning process which requires, at a minimum, integrated site plans controlled through performance standards to achieve developments which are compatible with surrounding land use patterns and the Goals, Objectives and Policies of the Land Use Plan. FLUE, page 113. Three commercial designations in the Urban service classification that are not expected to contain substantial residential development are Community Commercial, Commercial Office, and Regional Commercial. Each of these designations carries a density of 20:1 and contains a condition similar to that contained in Urban Level 1, 2, and 3 regarding compatibility with surrounding land uses and availability of adequate public facilities. The typical uses of Community Commercial are: Sale of convenience goods and personal services, general merchandising, furniture, sales restaurants, bars, offices, hotels, motels, banks, theaters, auto sales, compatible residential uses, multi-purpose projects, and mixed use developments. Agricultural uses may be permitted pursuant to policies in the agricultural objective of the [FLUE]. FLUE, page 114. The maximum floor area of the Community Commercial is 300,000 square feet or .35 FAR, whichever is less intense. The intent of Community Commercial is: To designate areas typically located within low density residential, low-medium density residential, medium density residential and/ or high density residential land use categories in order to provide a variety of commercial and office uses to serve large areas and which are oriented to auto traffic. Neighborhood commercial and office activities will be allowed provided they meet the applicable development regulations. Due to potential intensity of activities, planned grouping [is] strongly encouraged. Compatible residential development up to 20.0 dwelling units per gross acre, multi-purpose projects, and mixed use developments may be permitted in this category in appropriate locations according to applicable development regulations. FLUE, page 114. The typical uses of Commercial Office are: Community Commercial type uses, office uses, mixed use developments, and compatible residential uses. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 115. The maximum floor area of Commercial Office is: General--0.75 FAR up to a maximum of 600,000 square feet, however, the commercial component cannot exceed 300,000 square feet, subject to applicable land development regulations. FLUE, page 115. The intent of Commercial Office is: "To recognize existing commercial and office centers and provide for future development opportunities." FLUE, page 115. The typical uses of Regional Commercial are: Shopping malls to include one or more major department stores. Community Commercial type uses, office uses, mixed use developments, and compatible residential uses. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 116. The maximum floor area of Regional Commercial is "1.0 FAR, subject to applicable land development regulations." FLUE, page 116. The intent of Regional Commercial is: "To recognize existing regional commercial centers and provide for future development opportunities." Id. The three remaining designations exclusively in the Urban service level do not permit any residential uses. They are Research/Corporate Park, Light Industrial, and Light Industrial Planned. The typical uses of Research/Corporate Park are: Research and development activities, related educational facilities, electronic components production, light restricted manufacturing and warehousing, offices, corporate headquarters, and related uses such as hotels, motels, restaurants, recreational facilities, and rural scale retail establishments. Rural scale neighborhood commercial uses limited to 30,000 sq. ft. or 20% of the project's land area. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 117. The maximum floor area of Research/Corporate Park is "1.0 FAR." The intent of Research/Corporate Park is: To provide opportunity for research and high technology and similar manufacturing and light warehousing uses to serve Hillsborough County and the Tampa Bay region. Development in this category has integrated internal and external design requirements including heavy buffering and landscaping, high visibility linear footage on arterials, interstates, and expressways, and locations adjacent to employment markets. Research/Corporate Parks will be permitted to be developed throughout the county provided they meet the requirements of the Goals, Objectives, and Policies of the Land Use Element, and applicable development regulations. Proposed developments at locations not shown on the Land Use Plan Map may be considered through the Plan amendment process. Support neighborhood commercial uses may be permitted for up to 20% of the total land area. The development of the neighborhood commercial uses shall be integrated and appropriately scaled to other project uses. All development in this category shall require a planned zoning district. FLUE, page 117. The typical uses for Light Industrial and Light Industrial Planned are: Food products storage, furniture or apparel manufacturing (except plastics or fiberglass), packaging plants, wholesaling, storage of nonhazardous materials, offices, research/corporate parks as the predominant uses and subordinate uses or services such as hotels, motels, restaurants, rural scale retail establishments, and recreational facilities. Rural scale neighborhood commercial uses limited to 30,000 sq. ft. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, pages 118 and 119. The maximum floor area of Light Industrial and Light Industrial Planned is ".5 FAR." FLUE, pages 118 and 119. The intent of Light Industrial is: This land use category is used to designate, geographically on the Land Use Plan Map and/ or textually in the Land Use Element, those areas in the County potentially suitable for industrial activities that create a minimal degree of impact to the surrounding environment, particularly in terms of non- objection[able] levels of noise, vibration, dust, and/or odor. Development in these areas is subject to the Goals, Objectives, and Policies and land use category descriptions related to industrial activities. [Convenience] commercial uses shall be limited to same criteria of size and location as rural scale neighborhood commercial. Any industrial development above a .4 FAR shall require a planned zoning district. FLUE, page 118. The intent of Light Industrial Planned restates the first sentence of the intent of the Light Industrial and adds: This land use plan category will be used in high volume transportation corridors that have high visibility where impacts to adjacent development need to be minimized. The adjacent use compatibility issues are a major concern, and new development and substantial expansion of existing uses shall be approved through a planned unit development rezoning process which requires, at a minimum, integrated site plans controlled through performance standards to achieve developments which are compatible with surrounding land use patterns and the Goals, Objectives and Policies of the Land Use Plan. FLUE, page 119. The remaining seven designations are in a service level identified as "Urban or Rural." Two of them involve industrial uses. They are Heavy Industrial and Electric Power Generating Facility. The Heavy Industrial designation allows no residential uses. The typical uses of Heavy Industrial are: Phosphate and other chemical plants, plastics and fiberglass products processing, port related uses, storage of hazardous materials and liquids, offices, existing electric generating plants and expansions thereof, and related uses such as hotels, motels, restaurants, establishments, recreational facilities and rural scale retail establishments. Rural scale neighborhood commercial uses limited to 30,000 sq. ft. maximum. Agricultural uses may be permitted pursuant to policies in the agricultural objective areas of the [FLUE]. FLUE, page 120. The maximum floor area of Heavy Industrial is: .5 FAR. FAR's not to be applied to processing, storage and other uses characterized by outdoor storage. FLUE, page 120. The intent of Heavy Industrial is the same as the intent of the Light Industrial except that, in the case of Heavy Industrial, the activities "may have objectionable accompanying effects such as noise, vibration, dust, and/or odor." FLUE, page 120. The Electric Power Generating Facility designation allows a residential density of 1:5. The typical uses are: "All new Electrical Power Generating Facilities and related uses and all uses allowed in the Agricultural/Rural (A/R) land use plan classification." FLUE, page 121. The maximum floor area of the Electrical Power Generating Facility is: 0.5 FAR. FAR's not to be applied to processing, storage and other uses characterized by outdoor storage. Development permitted in this designation is subject to the Goals, Objectives and Policies of the [Plan], applicable development regulations and established locational criteria for specific land uses. FLUE, page 121. The intent of Electrical Power Generating Facility is: This land use category is used to designate geographically on the Future Land Use Map and textually in the [FLUE] those areas that are potentially suitable for the construction and operation of future electric power generating facilities consistent with the infrastructure needs of the population and subject to the requirements of the [Plan] and all other Federal, State and Local Laws, policies and permits. The uses authorized in the Agricultural/Rural (A/R) land use plan category are also authorized. New development of uses associated with an electrical power generating facility shall be approved through a planned unit development rezoning process. An application to rezone land for an Electrical Power Generating Facility may only be filed after submission of an application to the State under the Power Plant Siting Act. If the Siting Board denies the Siting, then the zoning shall revert to the underlying Zoning in existence at the time of application. FLUE, page 121. The five remaining designations are Major Public/Semi- Public, Major Recreation and Open Space, Scenic Corridor, Natural Preservation, and Environmentally Sensitive Areas. The typical uses of Major Public/Semi-Public, which is intended to "recognize major existing and programmed public facilities," are "[m]ajor government-owned facilities and other public uses [and] semi-public uses generally available for public use, [such as] churches, hospitals, schools, clubs and utility and transportation facilities." However, "[t]he Land Use Plan Map only shows major existing facilities." FLUE, page 122. The typical uses of Major Recreation and Open Space are "[m]ajor parks and recreational facilities which are publicly or privately owned and operated for recreational uses and are available to the public." However, the designation shows only "major existing parks and recreational facilities" as the Recreation and Open Space Element contains maps of "existing and proposed or needed parks." FLUE, page 123. The intent of the Scenic Corridor is to create a designation "applied to road corridors . . . determined to have scenic qualities of local or countywide significance." FLUE, page 124. In addition to preserving or enhancing the aesthetic appearance of roads through buffering, landscaping, and control of nonresidential uses, the Scenic Corridor designation is intended to preserve or expand a system of roadways that will begin to form a boulevard system to connect different communities within unincorporated Hillsborough County. The boulevard system will also form a system of connections between parks and recreational areas of the county. FLUE, page 92. The typical uses of Natural Preservation are "[o]pen space or passive nature parks." The intent of the designation is to "recognize public lands of significant environmental importance set aside for primarily conservation purposes." The Natural Preservation designation excludes other uses except residential sufficient for a caretaker, "compatible recreational development," and limited educational uses. FLUE, page 125. FLUE Policy A-3.2 states: No new development nor expansion nor replacement of existing development shall be permitted within areas designated on the Future Land Use Map as Natural Preservation Areas, unless development is undertaken by federal, State or local government in the public interest, and the impacts are mitigated. The Environmentally Sensitive Areas designation has been discussed above. 22/ The Implementation section of the FLUE describes the locational criteria and development standards for Rural-, Suburban-, and Urban-scale neighborhood commercial uses, which may be approved in various land use categories. Different development standards also apply for community commercial uses. The development standards for neighborhood commercial uses require, among other things, a location within a commercial node at the intersection of least one collector or higher planned roadway and maximum square footage based on a matrix focusing on land use designation and roadway classification. FLUE, pages 75- 76. Additional requirements are imposed based on whether the use is Urban-, Suburban-, or Rural-scale. The relationship of the land use categories to the FLUM is explained in the Implementation section: The land use plan categories shown on the Future Land Use Map are named according to their predominant land use or maximum level of intensity intended for that category of land use. Other uses may be permitted in any land use category as described within the individual plan category descriptions. Specific locations for other such uses are not shown graphically because to do so would predetermine locations of individual uses, particularly neighborhood-related uses, at a level of detail beyond the scope of the Future Land Use Map. All uses shall be reviewed for conformance with all applicable provisions contained within the [Plan] and with applicable development regulations. FLUE, page 55. Various policies pertain to designated densities in the Plan and FLUM. FLUE Policy A-3.3 states: "Gradual transitions of intensities and between different land uses shall be encouraged." FLUE Policy A-3.1 provides in part: "Land development regulations shall be studied to determine whether to include provisions for the transfer of development rights which ... provide for the transfer of development rights to receiving zones where infill is indicated." The Implementation section of the FLUE provides a density credit for certain in-fill development. FLUE, page 69. The Implementation section also contains various density and intensity bonuses for the development of affordable housing. FLUE, pages 73a-73b. FLUE Policy B-3.6 pursues infilling by treating as a single dwelling unit "an accessory residential unit associated with an owner occupied single family residence." Several provisions in the FLUE concern the provision of public facilities. FLUE Objective A-5 is: All new development and redevelopment shall be serviced with potable water, sewerage, stormwater management facilities, solid waste disposal and parks that meet or exceed the adopted levels of service established by Hillsborough County. FLUE Policy A-5.2 establishes the concurrency requirement as follows: The public facilities that are needed to serve future development shall be provided by the applicant seeking a development permit and/or the County, in a timely manner that is concurrent with the impacts of development as defined in the [CIE]. FLUE Objective C-29 provides: Public facilities and services that meet or exceed existing or established County levels of service shall be provided in advance of, or concurrent with, the impacts of development. FLUE Policy C-29.1 is to: Ensure that public facilities operating at adopted levels of service are available when Certificates of Occupancy are issued by: Anticipating development and planning the Capital Improvements Program accordingly; Requiring conditions on development approvals that phase development with the availability of facilities; Allowing developers to improve or provide public facilities at their own expense; Entering into public-private partnerships, when appropriate, to provide public facilities. CIE Policy 3.C states: The Board of County Commissioners find that the impacts of development on public facilities within Hillsborough County occur at the same time as development authorized by a final development order as defined in Policy 1.A.3.a. The County shall determine, prior to the issuance of final development orders, whether or not there is sufficient capacity of Category A and Category B 23/ public facilities to meet the standards for Levels of Service for existing population and the proposed development concurrent with the proposed development. For the purpose of this policy, "concurrent with" shall be defined as follows: 3.C.1: No final development order shall be issued by the County after January 31, 1990, unless there shall be sufficient capacity of Category A and Category B public facilities to meet the standards for Levels of Service for the existing population and for the proposed development according to the following deadlines: a: Prior to the issuance of the Certificate of Capacity for the following public facilities: 3.C.1.a.(1): Potable water. 3.C.1.a.(2): Sanitary sewer. 3.C.1.a.(3): Solid waste. 3.C.1.a.(4): Stormwater management. 3.C.1.b: Prior to the completion of the same County fiscal year as the issuance of the Certificate of Capacity for arterial and collector roads. 3.C.1.c: For parks and recreation facilities, prior to the issuance of the Certificate of Capacity or within a year of the issuance of the Certificate of Capacity if the necessary facilities are the subject of a binding executed contract or are guaranteed in an enforceable development agreement which requires the commencement of actual construction of the facilities within one (1) year of the issuance of the Certificate of Capacity. CIE Policy 3.C.2 states that a favorable capacity determination, following mandatory review of a development order, remains valid for two years. CIE Policy 3.C.4 indicates that the levels of service determinations shall be applied on a County-wide basis for solid waste disposal and regional parks. Levels of service determinations for facilities involving arterial and collector roads and mass transit shall be made by "[a]djoining sites and areas affected by the project based on individual analysis of the proposed development." Levels of service determinations for stormwater management systems shall be by major drainage basin. Levels of service determinations for district or neighborhood parks shall be by the relevant planning area. Levels of service determinations for potable water systems and sanitary sewer systems shall be by treatment plant service area, except that individual transmission (water) or collection (sewer) system limitations shall not result in closing the entire area to development if plant capacity remains. CIE Policy 1.C.1.a adopts level of service standards for all County arterial and collector roads by listing road segments and maximum volume-to- capacity ratios. CIE Policy 1.C.1.b adopts level of service standards for stormwater management systems, which include "significant canals, channels, ditches, pipeline/culvert enclosures of open systems, and appurtenant structures at crossings/control points." CIE Policy 1.C.1.b.(1) sets the adopted level of service for any existing system as the existing level of service until the system is physically upgraded and the Plan is amended to reflect the upgrade. CIE Policy 1.C.1.b.(2) states that the ultimate level of service for major stormwater conveyance systems is generally the 25 year/24-hour duration storm at flood level B except the more rigorous flood level A applies to new development and a less rigorous five year storm event applies for systems discharging into Tampa's stormwater conveyance system, which is designed to meet the demands of only the five year storm event. CIE Policy 1.C.1.b.(6) sets stormwater level of service standards based on flood capacity for other stormwater systems--i.e., sewer/swales and detention ponds/lakes/storage areas. CIE Policy 1.C.1.c sets the potable water level of service standard at 140 gallons daily per person. CIE Policy 1.C.1.d sets the sewage level of service standard at 100 gallons daily per person plus 23.8% for nonresidential sewage. CIE Policies 1.C.1.f-1.C.2 set level of service standards for solid waste, parks and recreation facilities, mass transit, and non-County maintained public facilities. FLUE Policy A-5.3 addresses the concurrency monitoring system: Areas that have excess and deficient capacities for public facilities in unincorporated Hillsborough County shall be identified, and this information shall be updated no less than once a year. Development will be encouraged in areas with excess capacities for public facilities, and discouraged in areas with deficient capacities for public facilities unless these facilities can be provided concurrently with development and consistent with the [Plan], County Regulations and adopted levels of service for public facilities. The monitoring and enforcement aspects of the concurrency management system are detailed in the CIE's Implementation section, which is part of the adopted Plan. The Implementation section assures: "no final development order shall be issued which results in a reduction in the Levels of Service below the standard adopted in Policy 1.C.1 for Category A public facilities and Policy 1.C.2 for Category B public facilities." CIE, page 25. The concurrency determination is based on a monitoring program that calls for, among other things, annual reports on the capacity and actual levels of service of public facilities for which concurrency is required. The monitoring program requires a separate record of the cumulative impacts of all development orders approved year-to-date. CIE, page 27. FLUE Policy A-5.6 states: Public facilities and utilities shall be located to consider: (a) maximizing the efficiency of services provided; (b) minimizing their cost; and (c) minimizing their impacts upon the natural environment. FLUE Policy A-5.7 identifies procedures, such as development phasing and utility oversizing, "so that the location and timing of new development can be closely coordinated with local government's ability to provide public facilities." FLUE Policy A-5.8 adds that the County shall promote partnerships among governmental and private entities "to identify and build needed public facilities among the partners in proportion to the benefits accruing to each of them." Specifically addressing transportation facilities, FLUE Objective A-6 states: All new development and redevelopment shall be serviced with roads that meet or exceed the adopted levels of service established by Hillsborough County. FLUE Policy A-6.1 is to: Coordinate land use and transportation plans to provide for locally adopted levels of service consistent with the Transportation and Capital Improvements Elements . . .. FLUE Objective A-7 is: The concept plan is the overall, conceptual basis for the long range, Comprehensive Plan, and all plan amendments must be consistent with, and further the intent of the concept plan, which advocates nodal clusters of growth connected by corridors that efficiently move goods and people between each of the nodes. FLUE Policy A-7.3 states: The development of a variety of employment centers shall be encouraged at adopted locations, as defined by the concept plan and applicable development regulations, to provide employment opportunities throughout existing and planned development areas. The Implementation section of the FLUE describes the concept plan involving nodal development. The purpose of the nodal activity centers is to "begin to form an urban structure that encourages the cohesiveness of the neighborhood unit while facilitating the connection and interdependence of the region as a whole." FLUE, page 57. The Implementation section describes four types of nodes. The most intense is the high intensity node, which is limited to the Central Business District of Tampa. The next most intense is the mixed use regional node, which designates existing and future regional shopping centers, major office and employment areas, higher education institutions, and professional sports and recreation complexes. The mixed use regional nodes include the West Shore Business District, Urban Level 3 Regional Activity Center in the I-75 corridor west of Brandon, University of South Florida area, and Tampa Palms at CR 581 and I-75. Less intense than the mixed use regional node is the community center node, which "will designate and emphasize a focal point for surrounding neighborhoods that will include a variety of public facilities and services including commercial and office development." FLUE, page 57. The community center nodes include numerous named areas. Least intense is the neighborhood node, which designates areas "appropriate for some higher intensity residential development with the density tied to a relationship with the scale of existing surrounding development." FLUE, page 58. There are numerous existing and potential neighborhood nodes. FLUE Policy A-7.6 states: Scattered, unplanned, low density development without provisions for facilities and services at levels adopted in the [Plan] in locations not consistent with the overall concepts of the [Plan] shall be prohibited. To qualify for densities in excess of 1:5 in areas designated Low Suburban Density Residential Planned and Rural Residential Planned, FLUE Policy A-7.7 requires residential development to conform to the requirements contained in the FLUE Implementation section, such as clustering, on-site job opportunities, internal trip capture, and shopping opportunities. FLUE Policy A-7.8 explains that the clustering and mixed use requirements imposed upon development in areas designated Low Suburban Density Residential Planned and Rural Residential Planned are intended: to prevent urban sprawl, provide for the efficient provision of infrastructure, and preservation of open space and the environment. Clustering and Mixed Use shall be encouraged in the other suburban and rural plans categories. FLUE Policy A-7.10 states that developments in areas designated as Low Suburban Density Residential Planned and Rural Residential Planned and involving at least 160 acres, if proceeding under the Planned Village concept, "shall be served by a central wastewater system (i.e. franchise, interim plant, community plant, county/municipal regional or sub-regional service, or other privately owned central systems)." Housing Element Objective 1.3 states: By 1992, establish guidelines for locating low and moderate income housing accessible to employment centers, mass transit systems, shopping and cultural, educational, medical and recreational facilities. Housing Element Policy 1.3.5 provides: By 1992, proactive public land investment initiatives along with incentives for private developments shall be explored, and implemented which include but are not limited to the following: disposition of surplus public land with developer incentives, public land assembly, disposition, and developer incentives in a comprehensive redevelopment framework and/or neighborhood rehabilitation plans; supplementary public initiatives to support private land assembly and affordable housing development; and the creation of a public-private partnership corporation to undertake land investment and facilitate private development of affordable housing in desirable locations. Housing Element Policy 1.3.6 states: "The County shall pursue federal and state funding sources for infrastructure improvements and for the construction or rehabilitation of low and moderate income housing." FLUE Objective B-4 addresses the locational criteria by which commercial uses will be permitted under the Plan. The objective states: Locational criteria for neighborhood serving commercial uses shall be implemented to scale development consistent with the character of the areas and to the availability of public facilities and the market. FLUE Policy B-4.1 states that the amount of neighborhood-serving commercial uses permitted in an area shall be consistent with the table adopted in the Implementation Section of the [FLUE] relating to land use density and the functional classification of the road network. FLUE Policy B-4.6 is: "Scattered, unplanned commercial development shall be discouraged, and commercial concentration shall be encouraged." FLUE Policy B-4.7 adds: "Commercial development should be designed to decrease the need for motorized vehicle trips by designing convenient, safe, non- motorized access." FLUE Policy B-4.8 provides: The expansion of existing strip commercial areas shall be prohibited, except in accordance with infill provisions in existing neighborhood commercial areas, and office or higher density residential development shall be considered as a viable alternative when in accordance with applicable development regulations. FLUE Policy B-5.1 addresses the redevelopment of commercial areas: "The redevelopment or revitalization of rundown strip commercial areas shall be encouraged through incentives such as the use of residential density credits for infill development that could include mixed use development." Further refining the guidelines for commercial redevelopment, FLUE Policy B-5.3 states: The redevelopment of appropriate commercial areas to include residential and/or office development that will reduce the number of transportation trips by increasing a project's internal capture rate shall be encouraged through incentives such as the use of residential density credits for infill development. FLUE Objective B-6 promises ongoing studies to identify the areas suitable for different types of industrial uses. FLUE Policy B-6.2 states that light industrial uses-- specifically, research and development--shall be encouraged to locate within the I-75 corridor, adjacent to the Tampa International Airport, and within the I-4 corridor. FLUE Policy B-6.5 provides: Expansion or new development of non- industrially designated land uses in industrially designated areas shall be prohibited unless the use is determined to be an accessory and complementary use to the industrial area. Applicable development regulations shall contain standards and/or criteria for location and intensity of these types of non-industrial uses. The intent is to ensure the availability of lands for industrial development, and to ensure that such subordinate uses will be in conjunction with the surrounding industrial area, as long as the industrial uses in the area are the predominant uses. FLUE Policy B-6.7 states: "Future industrial development shall be concentrated within industrial and mixed use areas as defined on the Future Land Use Map." Addressing agriculture, FLUE Objective B-7 states: Hillsborough County shall take active measures to foster the economic viability of agricultural activities by recognizing and providing for [their] unique characteristics in land use planning and land development regulations. FLUE Policy B-7.1 is to "[p]romote the development and maintenance of Plant City and Ruskin as agricultural market centers that strengthen the agricultural economy, encouraging agricultural uses within and around both communities." FLUE Policy B-7.2 is to "[a]llow agriculture as a viable use both prior and subsequent to the mining of land designated or approved for mining purposes." FLUE Policy B-7.5 warns: Anyone seeking the maximum long-term protection for long-term agricultural activities either should locate these activities on land in the Agricultural, Agricultural/Mining, Agricultural/Rural, Rural Estate and Rural Residential designated land use categories or should seek having these designations placed on their current location. FLUE Policy B-7.6 advises: "Anyone seeking to farm until it is more feasible to develop the property non- agriculturally should locate and remain in non-rural designated areas." FLUE Policy B-7.7 guarantees, for areas designated Agricultural, Agricultural/Mining, and Agricultural/Rural, that minimum acreages needed for viable agriculture will remain after clustering is approved. FLUE Policy B-7.9 is to defer charging an on-going agriculturally used property designated Agricultural, Agricultural/Mining, Agricultural/Rural, Rural Estate, or Rural Residential for public water or sewer tie-ins until actual connections are made or the designation is changed to a non- rural land use category. FLUE Objective B-8 deals with the question of compatibility between agricultural and nonagricultural uses in areas designated other than Agricultural, Agricultural/Mining, Agricultural/Rural, Rural Estate, and Rural Residential. FLUE Policy B-8.4 is to "[d]iscourage the location of new non- agricultural uses adjacent to pre-existing agricultural uses in rural land use categories." FLUE Objective C-25 addresses the need for "urban level densities" to encourage single and mixed uses in the I-75 corridor. FLUE Policy C-25.2 is to: "Encourage provision of affordable housing within mixed use developments through public and private sector initiatives." FLUE Policy C-25.3 is to limit the maximum density to 8:1 in the Urban Level 1 area between Tampa and the Pasco county line. FLUE Policy C-25.5 is to encourage access to urban level development on county arterials rather than state highways. FLUE Objective C-27 states: Employment centers shall be planned throughout the I-75 corridor, and residential opportunities shall be permitted in each of the plan categories within the I-75 corridor in order to promote opportunities for all segments of the population to live and work within the corridor, regardless of age, sex, race and income. FLUE Policy C-27.2 is to: "Encourage the provision and integration of low and moderate income housing dispersed throughout the urban level categories." FLUE Objective C-28 states: "Mass transit opportunities shall be expanded within the I-75 corridor." FLUE Objective C-31 is: By 1991, the County shall pursue the Regional Activity Center designation for the area within the I-75 corridor defined as that area consisting of the Urban Level 3 land use plan category on the Future Land Use Plan Map. FLUE Policy C-31.2 is for the County to develop incentives for development to locate within the Regional Activity Center. Suggested incentives are transferable development rights, increased densities and intensities, priority public facility funding, and special taxing districts. FLUE Objectives C-32 and C-33 establish corridors for I-4 and North Dale Mabry, respectively. In the I-4 corridor, light industrial uses are encouraged. In the North Dale Mabry corridor, clustered commercial, such as shopping centers, are encouraged over "scattered unplanned commercial development." 4. Funding and Financial Feasibility 615. CIE Objective 2 is: Provide needed public facilities that are within the ability of the County to fund the facilities. . . from County revenues, development's proportionate share contributions, and grants or gift[s] from other sources. [Rule] 9J-5.016(3)(b)5. CIE Policy 2.A states: The estimated costs of all needed capital improvements shall not exceed conservative estimates of revenues from sources that are available to the County pursuant to current statutes, and which have not been rejected by referendum, if a referendum is required to enact a source of revenue. [Rule] 9J- 5.016(3)(c)1.f. CIE Policy 2.B provides: "Existing and future development shall both pay for the costs of needed public facilities." CIE Policy 2.B.1.a states: Existing development shall pay for some or all of the capital improvements that reduce or eliminate existing deficiencies, some or all of the replacement of obsolete or worn out facilities, and may pay a portion of the cost of capital improvements needed by future development. CIE Policy 2.B.1.b adds: "Existing development's payments may take the form of user fees, special assessments and taxes." Addressing future development, CIE Policy 2.B.2.a provides: The County will allocate the costs of new public facilities on the basis of the benefits received by existing and future residents so that current residents will not subsidize an urban sprawl pattern of new development. CIE Policy 2.B.2.b states: Future development's payments may take the form of, but are not limited to, voluntary contributions for the benefit of any public facility, impact fees, capacity fees, dedications of land, provision of public facilities, and future payments of user fees, special assessments and taxes. Future development shall not pay impact fees for the portion of any capital improvement that reduces or eliminates existing deficiencies. The Five-Year Schedule of Capital Improvements contained in the CIE discloses planned capital expenditures, as they were known in June and July, 1989. The Five-Year Schedule indicates that, for the five-year period ending with fiscal year end 1994, the following capital costs are projected by public facility type: roads--$273,668,000; parks--$28,611,000; water--$10,798,000; sewer--$55,848,000; stormwater-- $29,345,000; and solid waste--$16,250,000. The total of these capital expenditures is $414,520,000. For each project, the Five-Year Schedule describes the general funding source. The CIE contains a section entitled Costs and Revenues by Type of Public Facility, which is an adopted part of the Plan. The Costs and Revenues section, which was prepared in December, 1990, states: The [CIE] is 100% financed by revenue sources that are available to the County under current law, therefore the Element is financially feasible, as required by the Florida Administrative Code. There is no "unfunded" portion of the Schedule of Capital Improvements. The Costs and Revenues section identifies each of the public facilities for which concurrency is required, the total expenditures planned for each public facility for the five-year capital planning period, and general sources of revenue by facility type. The costs and revenues by public facility type are: roads--$193,684,000; parks--$17,865,000; water-- $9,265,000; sewer--$76,179,000; drainage--$25,000,000; and solid waste--$16,250,000. The total of these capital expenditures is $362,097,000. Evidently, budget cutbacks took place in the 18 months between the adoption of the Five Year Schedule in mid 1989 and the adoption of the Costs and Revenues section in December, 1990. 5. Transportation Level of Service Standards Transportation Element Policy 1.1.1 sets minimum peak hour level of service standards for County roads, subject to lower standards for certain roads listed in CIE Policy 1.C.1.a. Transportation Element Policy 1.1.4 sets minimum peak hour level of service standards for State roads, subject to lower standards for certain roads listed in Transportation Element Table 2. 24/ Transportation Element Tables 1 and 2 show that 58 of the 147 state road segments in Hillsborough County are operating below the level of service standards generally adopted in Policy 1.1.4. These standards are D for all Urban state roads except for minor arterials, which are E, and C for all Rural state roads except for minor arterials, which are D. Table 1 shows that, by 1995, an additional 33 state road segments will be operating below the generally adopted level of service standard. Transportation Element Policy 1.1.4 concludes: "No development orders will be issued that would further reduce the current level of service on those roads listed in Table 2 of this element except where the development is vested under law." Transportation Element Figure 4 shows the location of all roads operating at level of service F. None is south of the Alafia River. The impaired roads are entirely in northwest and northcentral Hillsborough County. Among the road segments operating below the generally applicable level of service standards for state roads are four of the 11 segments of SR 574 (Buffalo/King), 10 of the 15 segments of SR 597 (Dale Mabry Highway), four of the five segments of SR 580 (Hillsborough Ave.), seven of the 10 segments of I- 275, seven of the eight segments of I-4, and four of the five segments of US 41 (Nebraska Ave. portion only). Much less impacted state road segments include I- 75, which has no segment operating below its adopted level of service standards; US 301, which has two of nine segments operating below its adopted level of service standards; and US 41 (southern sections), which has no segment operating below its adopted level of service standards. Transportation Element Policy 1.1.4 states that state roads operating below adopted level of service standards are "backlogged" or "constrained" and shall have a level of service standard established by the volume-to-capacity ratio listed for each road on Table 2. The Data and Analysis discuss the transportation problems confronting Hillsborough County. Many of the impaired road segments are scheduled for capital improvements in the Florida Department of Transportation five year work program. One key exception is Dale Mabry Highway, which will remain at level of service F even after planned work is completed. Transportation Element, page 24. Transportation Element Policy 1.1.7 promises that, within one year after adoption of the Plan, the County will enter into an agreement with the Florida Department of Transportation to identify actions that the County will take to "maintain the existing average operating conditions" on backlogged or constrained state roads. Transportation Element Policy 1.1.14 provides that Hillsborough County will, by 1990, initiate studies to identify State and County road corridors not capable of undergoing further capacity-increasing improvements and are thus suitable for designation as constrained corridors. 6. Vested Rights and Developments of Regional Impact The Legal Status of the Plan, which is part of the FLUE, addresses vested rights. The Legal Status section requires the County to develop an administrative process by which vested rights can be determined. The Legal Status section preconditions a finding of vested rights upon the following: That the person owned the parcel proposed for development at the date of the adoption of this [Plan], or the person had a contract or option to purchase the parcel on such date, or that it would be inequitable, unjust or fundamentally unfair to deny an application for vested rights where the person acquired ownership prior to February 1, 1990; and That there was a valid, unexpired act of any agency or authority of Hillsborough County government upon which the person reasonably relied in good faith; and That the person, in reliance upon this act of government, has made a substantial change in position or had incurred extensive obligations or expenses; and That it would be inequitable, unjust or fundamentally unfair to destroy the rights acquired by the person. In making this determination, the County may consider a number of factors, including but not limited to consideration of whether actual construction has commenced and whether the expense or obligation incurred is unique to the development previously approved and is not reasonably usable for a development permitted by the [Plan] and land development regulations. FLUE, page 128. Ensuing provisions of the Legal Status section identify various vested rights based on whether a development is exempted from concurrency. The Legal Status section also addresses certain development orders under developments of regional impact (DRI). Between the Plan adoption date and February 1, 1990, the County will approve buildout of not more than a "limited stage" of the total proposed DRI. Generally, the buildout approval will be limited to the part of the proposed development that has received Site Development Approval within two years following the expiration of the development order's initial appeal period. The Legal Status section authorizes the approval of additional development stages beyond the two-year limit if the development application had been received by the County prior to the Plan adoption date, the developer made substantial expenditures before Plan adoption in conducting a transportation analysis, and the transportation analysis focused on impacts occurring beyond the two-year limit. Development activity following the approved initial stage shall be subject to the Plan, including the concurrency requirements. The Legal Status section also recognizes the practice of "pipelining." The Legal Status section states: "While 'pipelining' will remain a permitted transportation mitigation option, the Board of County Commissioners will closely scrutinize its use." FLUE, page 129. Miscellaneous Intergovernmental Coordination Intergovernmental Coordination Element (ICE) Objective 1 states: By 1990, Hillsborough County shall establish new and review existing coordination mechanisms that will evaluate and address its comprehensive plan and programs and their effects on the comprehensive plans developed for the adjacent local governments, school board, and other units of local government providing services but not having regulatory authority over use of land and the State, by an annual county-wide forum sponsored by The Planning Commission. Assistance for this effort shall be requested from regional and state agencies by The Planning Commission, as needed. ICE Objective 3 requires the County, by 1991, "to address through coordination mechanisms the impact of development proposed in the [Plan] upon development in adjacent jurisdictions, the region and the state." Dual Planning Timeframes The Plan contains dual planning timeframes. Overall, the Plan contains a 20-year planning timeframe. However, shorter planning periods are addressed, such as the five-year period covered in the Five-Year Schedule of Capital Improvements. Regional Plan Provisions The Tampa Bay Regional Planning Council has adopted a regional plan known as the Future of the Region: A Comprehensive Regional Policy Plan for the Tampa Bay Region dated July 1, 1987 (Regional Plan). The Regional Plan, which applies to unincorporated Hillsborough County, is divided into goals and policies. Regional Goal 8.1 is: "By 1990, there will be an ample supply of water to meet all projected reasonable and beneficial uses in the Tampa Bay region." Policy 8.1.4 states: "Land use planning and development decisions shall consider the impact on surface and groundwater quality." Regional Goal 8.5 is: "By 1991, the region will increase the protection of major public water supplies and wellfields." Policy 8.5.1 states: "Prime groundwater recharge areas and cones of influence of existing and future major public water supplies and well fields shall be identified and mapped." Regional Goal 8.7 is: "By 1991, new developments in the region will be required to use the best management practices and/or procedures to reduce pollutants in stormwater runoff." Policy 8.7.1 requires the development of programs to ensure water reclamation and reuse with respect to wastewater and stormwater. Regional Goal 8.8 is: "By 1995, existing developments will be required to make measurable progress toward meeting stormwater standards." Policy 8.8.1 provides: "Local governments should upgrade or retrofit drainage systems in urbanized areas to include stormwater treatment for water quality." Policy 8.8.4 requires that agricultural runoff "shall be handled with Best Management Practices to minimize its impact upon receiving waters." Regional Goal 8.9 is: "By 1995, there shall be an increase in the effectiveness of programs protecting or enhancing the ecological function of natural systems (aquatic, wetland and terrestrial systems)." Policy 8.9.1 is to develop regional and local programs "to identify, protect and conserve the natural character and function of area lakes, streams, estuaries, wetlands, floodplain areas, and upland areas." Policy 8.9.2 directs that local government comprehensive plans shall incorporate the following: a) adoption of criteria for work in lake, riverine and wetland systems which will protect water quality, wildlife habitat and natural hydrological functioning of these areas; b) conservation of valuable upland habitat and wetland systems; c) preservation of habitat for endangered and threatened species; d) establish ecological minimum flow criteria and hydroperiod for surface waters; e) utilization of biological treatment methods and natural areas, such as wetlands, for stormwater treatment in areas of development/redevelopment to the maximum feasible extent. Regional Goal 8.10 is: "By 1991, land use practices will reduce the disruption of natural floodplain functions." Policy 8.10.1 states: "Regulations should be developed to promote appropriate land use practices compatible with floodplain areas and provide for performance standards for these land uses." Regional Goal 9.1 is: "By 1990, coastal zone areas will have increased vegetation, enhanced beach systems and improved environmental quality." Policy 9.1.2 provides: "The protection of coastal vegetative communities, coastal wildlife habitats, and dune systems from the adverse effects of development shall be required." Regional Goal 9.3 is: "By 1995, aquatic preserves in the Tampa Bay region will be more productive than 1985 levels and have a significant improvement in quality over 1985 measurements." Policy 9.3.3 requires buffer zones or other appropriate protection "between pristine aquatic preserves and adjacent upland uses to prevent degradation of water quality, shoreline and marine habitats." Regional Goal 9.4 is: "By 1991, all marine resources will be protected from contamination from human-induced processes." Policy 9.4.1 states: To protect sensitive marine resources from immediate and near future degradation resulting from improper development practices and recreational misuse, priority shall be given to water dependent uses or other types of shoreline development such as marina, light industry, ports and shoreline compatible commerce. Policy 9.4.2 states that the exploration and development of mineral resources "shall only proceed in an ecologically sound manner which does not threaten marine, aquatic, and estuarine resources." Policy 9.4.5 provides: "Dredging or spoiling of undisturbed bay bottom shall be prohibited. " Regional Goal 9.5 is: "By 1995, there will be at least a 5 percent increase in productivity of marine fisheries habitat and other aquatic resources." Policy 9.5.1 states: "Long-term productivity of marine fisheries habitat and other aquatic resources shall be increased and restored through estuary and intertidal protection." Regional Goal 9.6 is: "By 1990, coastal area will be protected by local government controls and other building regulations that will enhance the character and function of barrier islands and other environmentally sensitive areas." Policy 9.6.1 states: "Land and water uses shall be compatible with the protection of sensitive coastal resources." Policy 9.6.2 provides: "The use of government funds to subsidize development should be prohibited in high-hazard coastal areas." Policy 9.6.3 is to identify coastal high hazard areas "where the expenditure of public funds to subsidize development shall be prohibited." Policy 9.6.4 states: "The use of public funds to rebuild public facilities damaged by hurricanes or other storms shall be limited to facilities essential only for public health and safety." Regional Goal 10.1 is: "By 1995, the Tampa Bay region's conservation areas will have increased environmental quality and functional characteristics that provide suitable habitat to all wildlife and flora indigenous to the region." Policy 10.1.1 states: "Protect the habitats and plant communities that tend to be least in abundance and most productive or unique." Policy 10.2.2 states: The hydrologic continuity and water quality of identified isolated wetlands shall be protected. Development activities or other land disturbances in the drainage area of the wetlands shall minimize alterations to the surface or subsurface flow of water into and from the wetland and shall not cause impairment of the water quality or the plant and wildlife habitat value of the wetland. Policy 10.2.3 requires "water users, such as agriculture and mining," to prepare mitigation plans "to minimize unavoidable impacts to nearby wetlands." Policy 10.2.4 requires: Mitigation measures shall be developed to provide water quality benefits and plant and animal habitat equivalent to the wetland destroyed or altered. Newly created wetlands should include at least 1:1 mitigation using the same type or more productive vegetation with at least an 80-85 percent natural cover rate, over a 2 to 5 year period. Regional Goal 10.3 is: "By 1993, regional preservation areas will be protected by regulations or practices from further development and will be preserved and/or restored to their natural state." Policy 10.3.1 states, in part: "Preservation areas, such as marine grass beds . . . and other vital or critical natural systems, shall be protected from any further development except in cases of overriding public interest." Policy 10.3.3 provides: "Unique upland communities and habitats in identified preservation areas should be protected from development that would significantly alter their character. Preservation and restoration of these communities shall be required." Regional Goal 10.4 is: "By 1991, development in the 100 year floodplains should be strictly regulated." Policy 10.4.1 allows new channelization only as a "last resort" in flood protection for existing development. Policy 10.4.4 prohibits channelization solely to create new lands for development. Policy 10.4.2 prohibits locating new development in river floodways (i.e., the area of highest velocity during flow) except in cases of overriding public interest. Policy 10.4.3 requires that new development in the flood fringe (i.e., the area of the floodplain outside the floodway) meet flood hazard construction requirements. Regional Goal 10.5 is: "By 1991, new or rebuilt development within the 25 year floodplain will not contribute adverse water quality impacts from stormwater runoff." Policy 10.5.2 states: "Development along all river floodplains shall be low density with adequate setbacks to maintain existing areas of natural habitat." Regional Goal 10.6 is that, by 1995, there shall be "measurable indications" of greater commitment from local governments and private parties to "conserve, protect, and enhance" populations and habitats of endangered, threatened, and special-concern species. Policy 10.6.1 recommends the adoption of incentives to encourage the preservation of native habitats. Policy 10.6.2 states: Identified areas that contain viable populations of, or suitable habitats for, species listed as endangered, threatened, or of special concern . . . shall be classified as environmentally sensitive, preservation, or conservation areas with future development limited to land uses compatible with the listed species. Regional Goal 10.8 is: "By 1991, there will be marked changes in land rearrangement and vegetation clearing practices that do not degrade the region's natural drainage and percolation patterns." Policy 10.8.1 requires the use of buffer zones between agricultural lands and water bodies. Regional Goal 10.9 is: "By 1995, the region's forested and woodland areas will not have decreased in size by more than 3 percent, or have any less characteristics than present in 1988." Policy 10.9.1 requires the addition to local government comprehensive plans of forest preservation plans for significant woodlands or forests. Policy 10.9.2 states that the forest preservation strategy shall consist of mapping of forests and woodlands, identifying those forest or woodland areas that are wetlands or habitat protection areas, and providing incentives for the conversion of other land uses to forested conditions. Policy 10.9.3 states that wildlife corridors should be maintained. Regional Goal 16.8 is: "As an ongoing goal, all dredge and fill activities shall be carried out only when necessary and in a manner least harmful to the surrounding environment." Policy 16.8.1 provides: Any project including unavoidable destruction of habitat shall mitigate all lost wetland habitat on a 1:1 in-kind basis, at minimum. Mitigation shall include monitoring with assurance of an 80-85% natural cover area after 2-5 years. Policy 16.8.2 states: "Unique and irreplaceable natural resources shall be protected from adverse effects." This policy is intended to apply to dredge and fill projects, as is clear from the standard by which compliance is to be measured, which is the "amount of dredging or filling within unique and irreplaceable natural resources." Regional Goal 13.6 is: "By 1995, groundwater contamination due to inappropriately located or improperly used septic tanks shall be eliminated." Policy 13.6.2 provides: "Permitting process criteria for septic tanks and their fields shall take into consideration adverse impacts on water quality and aquatic resources." Policy 13.6.4 requires a survey locating "septic tanks associated with all commercial and industrial activities" and an "evaluation . . . concerning potential adverse effects on groundwater resources, water supply wells, and ground water recharge potential." Regional Goal 13.9 is: "By 1995, water quality will be improved by the control of point and non-point discharges into surface waters." Policy 13.9.2 states: "Domestic sewage and industrial discharges shall be required to achieve best practical technological standards and to implement reuse systems to minimize pollution discharge." Regional Goal 13.10 is: "By 1995, the number of project-specific 'package plants' shall be reduced from 1988 levels." Encouraging private cost- sharing in the construction of regional wastewater facilities and the development of requirements for connecting package-plant systems to regional systems when available, Policy 13.10.1 also provides: When necessary, project-specific "package plants" shall be allowed but only where a detailed hydrogeological analysis of the site determines low potential for groundwater contamination from hazardous wastes or other pollutants. Regional Goal 14.4 is: "By 1991, mining practices will be designed to fully protect the natural environment from the adverse effects of resource extraction." Policy 14.4.1 states: "There shall be no mining in areas which are geographically or hydrologically unsuitable for the extraction of minerals or in areas which are crucial to the provision of essential public services." Policy 14.4.2 provides: "There shall be no mining in the 25-year floodplain." Policy 14.4.3 states: The mining of environmentally sensitive areas shall be avoided unless it can be demonstrated that technology associated with reclamation and restoration can restore those areas. Mining and reclamation procedures shall minimize permanent changes in natural systems and the permanent loss of environmental resources. The best available technology and practices shall be used to re-establish the land forms, land uses, and natural vegetation associations that existed prior to mining of the land to the extent feasible and desirable. Policy 14.4.4 provides that the portion of mining areas that contain endangered or threatened wildlife species shall be protected. Policy 14.4.5 states that mining and processing shall be conducted so as to "protect, manage and more efficiently utilize water resources." Regional Goal 16.1 is for ten percent of DRI's to be located in designated regional activity centers between 1986 and 1990. Regional Goal 16.2 is: "As an ongoing goal, new urban development, including in-fill, will occur on land which has the capacity to accommodate growth in terms of environmental and infrastructural impacts." Policy 16.2.1 states: "Contiguous development and the orderly extension and expansion of public facilities are necessary." Policy 16.2.2 encourages the location of higher density developments within existing urban areas where public facilities are available. Regional Goal 16.5 is: By 1991, the integrity and quality of life will be maintained in existing residential areas and will be required of new residential developments through the continued revision and adoption of local government comprehensive plans, environmental and land use regulations. Policy 16.5.1 provides that residential areas shall be located and designed to protect from "natural and manmade hazards such as flooding, excessive traffic, subsidence, noxious odors and noise." Policy 16.5.2 states: "Residential land uses shall be encouraged in a manner which is compatible with the type and scale of surrounding land uses." Policy 16.5.4 encourages local governments to locate high density residential areas near regional activity centers and reduce densities elsewhere to "facilitate the restriction of urban sprawl [and] use of mass transit." Policy 16.5.5 encourages mixed use developments with buffering of residential areas. Policy 16.5.6 recommends the location of shopping facilities, recreation areas, schools, and parks within high density residential areas. Regional Goal 16.6 is: By 1991, commercial development, compatible with environmental and economic resources, will occur in a planned and orderly fashion through the continued revision and adoption of local government comprehensive plans, environmental and land use regulations. Policy 16.6.1 states: Commercial land uses shall be located in a manner which ensures compatibility with the type and scale of surrounding land uses and where existing or programmed public facilities will not be overburdened. Policy 16.6.2 is to locate regional commercial areas in planned centers to ensure compatibility and "efficiency of economic and natural resources." Policy 16.6.3 "strongly discourage[s]" strip commercial development, which "compounds traffic and land use conflicts." Regional Goal 16.7 is the same as Regional Goal 16.6, except that Goal 16.7 applies to industrial uses. Policy 16.7.1 is to locate industrial areas near adequate transportation for materials, labor, and products. Policy 16.7.5 encourages the redevelopment of urbanized industrial locations near major transportation facilities, such as ports and airports. Regional Goal 22.1 is: "By 1991, the Tampa Bay region shall balance the needs of agricultural and nonagricultural land uses." Policy 22.1.1 encourages the "preservation and utilization of agriculture land for agriculture uses." Policy 22.1.3 provides: "The recognition of agriculture as a form of land use and a category on land use plan maps, not simply as a holding zone, is encouraged, where appropriate." Policy 22.1.6 recommends: "Agriculture should be recognized as a major contributor to the region's economic base, and should be retained where possible to maintain the diversification of the region's economy." Regional Goal 22.2 is: "By 1991, agricultural practices will be implemented to reduce the amount of pesticides and other agriculturally based pollutants in surface waters, groundwater and sediments." Policy 17.1.1 states: To relieve pressure on existing public facilities, programs such as temporary density bonuses, special zoning designations and public acquisition of tax-delinquent property should be developed to encourage infilling of vacant urban lands. Policy 17.1.5 provides: "Capital improvements programs should maximize the development of existing systems before allocating funds to support public facilities in undeveloped areas." Regional Goal 17.2 is: "By 1991, the planning of public facilities will serve as a proactive growth management tool." Policy 17.2.1 requires that the location of public facilities "shall be used to guide urban development" and the "rate of private development should be commensurate with a reasonable rate of expansion of public and semi-public facilities." Policy 17.2.2 recommends the advance acquisition of sites for potential public and semi-public facilities. Regional Goal 19.1 is: As an ongoing goal, planning for and maintenance of an integrated transportation system including highway, air, mass transit, rail, water, and pipeline systems, which efficiently services the need for movement of all people and goods within the region and between the region and outside world[,] will continue to be implemented. Policy 19.1.2 is to reduce dependency upon the private automobile by providing an adequate mass transit system. Policy 19.1.3 states: "The transportation system should promote the efficient use of energy resources and improvement of the region's air quality." Policy 19.8.8 states: An operational Level of Service (LOS) D peak hour shall be maintained on all regionally significant roadways in urbanized areas. An operational LOS C peak hour shall be maintained on all regionally significant roadways in rural areas. However, Policy 19.8.9 provides: An operation Level of Service (LOS) E peak hour shall be maintained on all regionally significant roadways in Special Transportation areas as agreed upon by the FDOT, the appropriate MPO, the regional planning council, and the local government. Policy 19.8.14 states: Pipelining shall be an acceptable and sufficient DRI transportation impact mitigation for existing and future DRIs provided that all the following provisions are met: Project approvals shall be phased and shall not exceed five years. Subsequent approvals shall be subject to further analysis and additional pipeline mitigation. Roadway improvement to be pipelined shall: be selected from the list of existing or proposed regional transportation facilities substantially affected by the development identified by the [regional planning council] during the DRI review. preferably be consistent with MPO and FDOT long-range plans. receive concurrence from the local government and [regional planning council] with review and comment by MPO and FDOT. The developer fair share pipeline contribution shall be equalto or exceed an amount calculated pursuant to DCA pipeline transportation policy. The developer shall receive credit against impact fees, pursuant to law. Local government, based upon traffic analysis or studies, and/or long range planning, may authorize alternative pipelining approaches and conditions, to those established in subparagraph 1 above, provided that such variations are technically appropriate and that the basis for, and the conditions of, such variations are specifically set forth in the Development Order. Regional Goal 11.1 is: "By 1995, land use-related airborne contaminants will be reduced within the region by a measurable percentage." Policy 11.1.1 is for each local government to develop procedures to assess air quality impacts from non-DRI development, such as strip shopping centers, that have a cumulative impact on traffic flow. Policy 11.1.4 is to "[i]nitiate control measures where construction, mining and other activities where heavy vehicular traffic and/or meteorological conditions result in significant air pollution." Regional Goal 11.2 is: "By 1992, the regional will maintain ambient sulfur dioxide, carbon monoxide, nitrogen dioxide, lead, ozone, and total suspended particulate levels that are equal to or better than the state and federal standards." Regional Goal 11.6 is: "By 1992, transportation related air quality impacts that adversely impact ambient air quality will be reduced." Policy 11.6.1 states that the metropolitan planning organizations and others entities involved in transportation planning "shall give priority to traffic flow improvements that reduce air pollution, particularly in areas that exceed ambient standards." Regional Goal 12.3 is: "As an ongoing goal, the most energy efficient and economically feasible means shall be utilized in construction, operation and maintenance of the region's transportation system." Policy 12.3.1 recommends consideration of incentives such as development or expansion of mass transit, "park and ride" programs, and public awareness of mass transit options. Regional Goal 20.2 is: "By 1990, the region's governments shall increase their efficiency and effectiveness." State Plan Provisions The state comprehensive plan is set forth at Sections 187.201 et seq., Florida Statutes. Section 187.201(8)(b)12 states: "Eliminate the discharge of inadequately treated wastewater and stormwater runoff into the waters of the state." Section 187.201(10)(b)5 provides: "Promote the use of agricultural practices which are compatible with the protection of wildlife and natural systems." Section 187.201(23) states the goal of agricultural policies as follows: Florida shall maintain and strive to expand its food, agriculture, ornamental horticulture, aquaculture, forestry, and related industries in order to be a healthy and competitive force in the national and international marketplace. Section 187.201(16) states the goal of land use policies as follows: In recognition of the importance of preserving the natural resources and enhancing the quality of life of the state, development shall be directed to those areas which have in place, or have agreements to provide, the land and water resources, fiscal abilities, and service capacity to accommodate growth in an environmentally acceptable manner. Section 187.201(18)(b)1 and 3 provides: Provide incentives for developing land in a way that maximizes the uses of existing public facilities. Allocate the costs of new public facilities on the basis of the benefits received by existing and future residents. Section 187.201(16)(b)2 states: "Develop a system of incentives and disincentives which encourages a separation of urban and rural land uses while protecting water supplies, resource development, and fish and wildlife habitats." Section 187.201(20)(b)2 provides: "Coordinate transportation investments in major travel corridors to enhance system efficiency and minimize adverse environmental impacts." Section 187.201(20)(b)9 states: "Ensure that the transportation system provides Florida's citizens and visitors with timely and efficient access to services, jobs, markets, and attractions." Section 187.201(11) states the following goal: "Florida shall reduce its energy requirements through enhanced conservation and efficiency measures in all end-use sectors, while at the same time promoting an increased use of renewable energy resources." Section 187.201(11)(b)2 adds: "Ensure that developments and transportation systems are consistent with the maintenance of optimum air quality." Section 187.201(12)(b)4 provides: "Ensure energy efficiency in transportation design and planning and increase the availability of more efficient modes of transportation." Section 187.201(12)(b)5 states: "Reduce the need for new power plants by encouraging end-use efficiency, reducing peak demand, and using cost-effective alternatives." Section 187.201(5)(b)4 states: "Reduce the cost of housing construction by eliminating unnecessary regulatory practices which add to the cost of housing." Section 187.201(21)(b)4 and 12 provides: "Eliminate regulatory activities that are not tied to specific public and natural resource protection needs" and "Discourage undue expansion of state government and make every effort to streamline state government in a cost effective-manner. Ultimate Findings of Fact Minimum Criteria of Data and Analysis Sufficiency of Data and Analysis (Issues 1-9) As to Issue 1, the ELUM's show existing and planned water wells, their cones of influence, historic resources, floodplains, wetlands, minerals, and soils. The ELUM's show many important existing public facilities, such as roads, potable water facilities, sanitary sewer facilities, and schools. The depiction of power line rights of way and power generating facilities is less clear, although major public and industrial uses are indicated. As to Issues 2 and 3, the Data and Analysis describe at length the fisheries, wildlife, marine habitats, and vegetative communities that are found in Hillsborough County. The text and CARE Table 11 identify endangered, threatened, or special-concern species associated with each habitat. As to Issue 3, for each of the vegetative communities or habitats found in Hillsborough County, the Data and Analysis identify various uses, known pollution problems, and potential for conservation, use, or protection. As to Issue 4, the Data and Analysis discuss the suitability of soils for septic tanks. The discussion notes the problems associated with the placement of septic tanks on poorly drained soils, as well as excessively drained soils. The Data and Analysis identify the parts of the County with such soils, especially the poorly drained coastal soils of the coastal high hazard area. As to Issues 4 and 5, the Data and Analysis acknowledge that septic tank failures have adversely affected the water quality of Cockroach Bay. The discussion of the impact of septic tanks in other parts of the Tampa Bay estuary is less specific geographically. But the Data and Analysis generally recognize the role of inadequately treated domestic wastewater and inadequately treated stormwater runoff in the eutrophication of Tampa Bay. As to Issue 6, the Data and Analysis consider the potential for conservation, use, and protection of all surface waters in Hillsborough County, including Tampa Bay. As to Issue 7, the Data and Analysis identify and analyze existing and future water needs and sources and natural groundwater recharge areas. Although Hillsborough County contains no areas of prime recharge to the Floridan aquifer nor of high natural recharge to any aquifer, the Data and Analysis identify locations of very low to moderate natural aquifer recharge and areas of high susceptibility to groundwater contamination. As to Issue 8, the Data and Analysis contain land use suitability analyses in which various land uses are correlated to natural features, including natural resources. Oversized Map 13 locates very severely limited soils and critical and sensitive lands in relation to vacant lands. Other ELUM's more specifically locate and analyze vacant lands, floodplains, wetlands, historic resources, minerals, soils, rivers, bays, lakes, harbors, estuarine systems, recharge areas, areas highly vulnerable to groundwater contamination, water wells, vegetative communities, wildlife habitat, and other natural resources appropriately considered in analyzing potential land uses for vacant land. The Data and Analysis textually analyze the suitability of various types of land for different land uses. In some cases, the analysis is incomplete, such as with respect to suitable land uses within the cones of influence of water wells or adjacent to wellfields. Even for such resources, however, the Data and Analysis support the inference that activities involving considerable water consumption or wastewater production, like traditional phosphate mining operations, should not be located in close proximity to water wellfields. The Data and Analysis explicitly identify the risk to groundwater posed by impervious surfaces and groundwater contamination such as from septic drainfields and leaking underground storage tanks. Thus, suitable land uses may at least be inferred with respect to areas of natural moderate aquifer recharge or artificially high aquifer recharge due to wellfield drawdowns. As to Issue 9, Coastal Element Figure 18 identifies the coastal high hazard area in Hillsborough County. 2. Supporting Data and Analysis (Issues 10-14) As to Issue 10, the failure of the Plan to require retrofitting of existing, deficient stormwater management systems is supported by the Data and Analysis. In the first place, the Plan addresses retrofitting to a significant extent. Coastal Element Policy 13.3, which deals with all infrastructure in the coastal high hazard area, commits the County to preparing, by the 1993 hurricane season, a program to relocate or retrofit public facilities where feasible. Where economically and environmentally feasible, CARE Policy 2.10 and Coastal Element Policy 1.11 provide for the retrofitting of urbanized areas lacking stormwater management facilities. CARE Policy 2.8 contains similar provisions regarding agricultural runoff. The Plan provisions cited in the preceding paragraph are supported by the Data and Analysis. Existing stormwater problems are sufficiently serious that the Data and Analysis question whether water quality problems can be corrected without retrofitting stormwater management systems. Stormwater Element, page 20. However, the Data and Analysis recognize that economic reality may limit retrofitting to redevelopment. The failure of the Plan to require retrofitting of stormwater systems generally is supported by the Data and Analysis, at least in the absence of stronger evidence that, without retrofitting in unincorporated Hillsborough County, the water quality problems in Tampa Bay cannot be effectively addressed. The other part of Issue 10 concerns the failure of the Plan to set a stormwater level of service standard in terms of water quality. This part of Issue 10 addresses the means by which the performance of stormwater management systems will be evaluated, regardless whether the systems are installed at the time of development or redevelopment. The failure of the Plan in this regard is dramatic. First, the Plan provides for a stormwater level of service standard strictly in terms of flood control. The stormwater level of service standard, which is stated in CIE Policy 1.C.1.b, defines storm events and their duration and then specifies the extent to which the stormwater facilities may flood in such events. Other Plan provisions address aspects of stormwater management other than mere flood control--even mentioning water quality. But these provisions lack the measurable and enforceable performance standards characteristic of level of service standards. 25/ The Data and Analysis offer no support for the Plan's preoccupation, when setting a level of service standard, with stormwater solely in terms of flood control, to the exclusion of other factors that affect the quality of receiving waters, such as runoff rate, quality, and hydroperiods. To the contrary, the stormwater level of service standard in the Plan is repugnant to the Data and Analysis. The Data and Analysis clearly identify the role of inadequately treated stormwater runoff in the eutrophication of Tampa Bay. One quarter of the biological oxygen demand and 35% of the suspended solids discharged into the bay are attributable to stormwater runoff. Important gains have been made in reducing the nutrient loading of the bay by inadequately treated domestic and industrial wastewater, such as through the enhancement of treatment levels at wastewater treatment plants or the implementation of wastewater reuse programs. But the Data and Analysis concede that nutrient loading from stormwater runoff will remain a more intractable program. Coastal Element, page 24. The problem is exacerbated by inadequate compliance with existing stormwater regulations. CARE, page 54. For areas within the substantial floodplains of Hillsborough County, and even to a certain extent for areas outside the floodplains, the stormwater issue is best approached from the perspective of floodplain management. The natural drainage of floodplains regulates the timing, velocity, and levels of flood discharges, as well as water quality through the processes of sediment detention and chemical filtration. CARE, pages 14-15. Stormwater management systems using only a structural approach to effect flood control destroy the natural drainage function of the floodplain. Structural improvements include such projects as channelizing natural watercourses (like the Palm River) and constructing new channels, dams, levees, and other structures to hold back floodwaters or rapidly convey them elsewhere. Consequently, flood discharges tend to peak more quickly. By increasing maximum flow, the flood-control structures decrease filtration, groundwater recharge, habitat maintenance, detrital production and export, maintenance of base flow (as minimum flows during later dry periods cannot draw upon water previously stored in the unaltered floodplains), and estuarine salinity regulation. CARE, pages 15-17. In short, the Data and Analysis disclose that a stormwater management program whose performance is evaluated exclusively in terms of flood control, such as that contained in the Plan, has systemic environmental implications whose economic costs are probably incalculable. The Data and Analysis identify the obvious planning considerations that underlie the establishment of a viable stormwater level of service standard. The third guideline for floodplain management is to avoid alterations to the natural rate, quality, and pattern of surface waters. Expressly applying the guideline to floodplains and "more upland sites," the Data and Analysis advise that the "rate, volume, timing and location of discharge of surface water should generally not be altered from predevelopment conditions." CARE, page 19. See also Stormwater Element, page 20. Yet, the best that the County offers, after acknowledging its preoccupation with flood control in setting the stormwater level of service standard, is to promise that a stormwater management program--deferred to land development regulations--will eventually address stormwater runoff in terms of quality, not merely quantity. Stormwater Element, page 43. As to the part of Issue 10 addressing the level of service standard, the Plan's stormwater standard is, to the exclusion of fair debate, not supported by the Data and Analysis because it fails to require that, for new development, redevelopment, and expansions of existing development, as "development" is defined in the Plan, postdevelopment stormwater urban and agricultural runoff shall be the same as (or, where appropriate, better than) predevelopment runoff in terms of volume, quality, rate, hydroperiod, and drainage basin. If the Plan fails to amend its stormwater level of service standard in the manner set forth in the preceding paragraph, many future land use designations, in addition to those discussed below, are, to the exclusion of fair debate, unsuitable and lack support from the Data and Analysis. The permitted densities and intensities, especially in the 100 year floodplain, will contribute dramatically to the degradation of natural drainage patterns in the County and ultimately to the degradation of Tampa Bay. Absent modification of the stormwater level of service standard to address urban and agricultural runoff in terms of volume, quality, rate, hydroperiod, and drainage basin, the Data and Analysis would not support Plan provisions that allowed any development, as that term is defined in the Plan, in the 100 year floodplain if such development's urban or agricultural runoff altered predevelopment drainage conditions in terms of its rate, volume, quality, timing, or location of discharge. As to Issues 11-14, assuming that the Plan is amended to broaden the scope of the stormwater level of service standard in the manner set forth in the preceding paragraph, the Plan is generally supported by the land use suitability analysis. However, there are 11 exceptions. First, in terms of urban sprawl, the overall densities in the Plan are supported by the Data and Analysis, at least to the extent that there is no indication of urban sprawl. The density allocation ratio of 1.61:1 is not an especially strong indicator of sprawl in this case. 26/ Several factors are important in evaluating a density allocation ratio, such as whether historic buildouts have been considered (not in this case) and the duration of the planning timeframe (20 years). Probably the most important consideration, though, is the location of the residential uses. A density allocation ratio of 3:1 generated by 100,000 acres of 1:1 residential is far more suggestive of inefficient use of land than the same ratio generated by 5000 acres of 20:1 residential in an existing or planned mixed use urban area, assuming the provision of adequate public facilities, protection of natural resources, and protection of agriculture. The Plan's two planning strategies involve the concentration of density in the I-75 corridor, with decreasing densities radiating outward, and the development of nodes where suitably scaled commercial uses are located in close proximity to residential uses. These two strategies have been effectively implemented in the Plan to counter urban sprawl. There is no plausible evidence in the record that the allocated intensities or acreage, in terms of commercial or industrial uses, are indicative of urban sprawl. As the Data and Analysis note, commercial development has historically followed residential development, not preceded it. An underallocation of commercial and industrial future land uses arguably invites sprawl by interfering with the development of functionally related land uses. There is no place for commercial, industrial, institutional, and recreational land uses once residential development has consumed the entire landscape, with respect to which adequate commercial, industrial, recreational, and institutional uses have not been timely reserved. In addition, allocation ratios for commercial and industrial uses are problematic, regardless whether expressed in acreage, which is necessarily a very gross measure of the intensity that is eventually built out, or floor area ratios, which are more precise but much more difficult to predict based on designated acreages of vacant land. Therefore, the overallocation of commercial and industrial uses does not serve as a useful beginning point for analysis, at least in the absence of proof of historic overbuilding with resulting disruption in the efficient use of land or public facilities or loss of natural resources or agriculture. As noted above, the key factor with respect to commercial and industrial uses is location. Through various devices, the Plan effectively pursues mixed land use patterns that will encourage the location of residential, commercial, and industrial, as well as institutional and recreational, uses in a functionally related manner. Notwithstanding the finding that the Plan designations are supported by the Data and Analysis in terms of urban sprawl, the Data and Analysis do not support specific designations involving considerable acreage, even assuming that the stormwater level of service standard will be broadened to include the above- cited factors in addition to flood control. The Data and Analysis recount the consequences of years of land use decisions based "primarily on socio-economic and demographic factors, with little consideration given to preserving or conserving the natural attributes of the land." But the Data and Analysis promise that, "[w]ith a better understanding of the ecological impacts of land uses, it has become clear that the natural carrying capacity of the land must be carefully considered in land use decisions . . .." CARE, page 73. For the 11 areas described below, socio-economic and demographic factors have again outweighed the natural carrying capacity of the land. The 11 areas have received unsuitable designations for which the Data and Analysis offer no or inadequate support. For each of these areas, the Plan has assigned designations whose excessive densities and/or intensities generally jeopardize important natural resources or life and property in the coastal high hazard area. A future land use is suitable if the designation is supported by the Data and Analysis. For the vast majority of areas, the Data and Analysis would support designations assigning a range of densities and/or intensities. The question whether a designation is supported by the Data and Analysis requires consideration of, among other factors, the nature of the density or intensity inherent in the designation of the subject area, the data and analysis concerning the nature of the natural resources affected by the subject designation (including off-site resources), the data and analysis concerning when and what type of public facilities will be available to service the subject area, the data and analysis indicating how the designated uses may impact natural resources, and operative Plan provisions that may or may not offer protection to the natural resources in question. 27/ The Plan assigns unsuitable designations to five areas in northwest and north Hillsborough County. The Data and Analysis fail to support two of these designations to the exclusion of fair debate and three of the designations by a mere preponderance of the evidence. One relatively small area whose designation is, to the exclusion of fair debate, unsupported by the Data and Analysis is designated Low Suburban Density Residential (2:1) at the southeast end of Keystone Lake. The extent of the subject area corresponds to the area designated Low Suburban Density Residential on the FLUM. This area is immediately north and west of Gunn Highway at Van Dyke Road. Shown as largely agricultural or vacant on Oversized Map 2, the area received an increase in density in the Plan, according to Oversized Map 14. The only area designated at a Suburban density in the northwest corner of northwest Hillsborough County, the area is the site of one or more major public supply water wells. By contrast, areas containing groups of wells just south of Keystone Lake and at the extreme northwest corner of the County are designated Natural Preservation, as is an area at the southwest corner of SR 597 and Van Dyke Road, about four miles east of the area in question. The area designated Low Suburban Density Residential occupies an area of relatively good natural aquifer recharge and is very susceptible to groundwater contamination. The subject area is included in the 1995 central water service area, but excluded from even the 2010 central sewer service area, according to Sewer Element Figure 1 and Potable Water Element Figure 1. The absence of effective Plan provisions protecting wellfields, cones of influence, and recharge areas further undermines the Low Suburban Density Residential designation of an area in such close proximity to a major public supply water well and in an area of relatively good natural aquifer recharge. The increased density for this area threatens a major wellfield with encroaching development, as predicted in the Data and Analysis. FLUE, page 7. A mere preponderance of the evidence shows that the Data and Analysis do not support the density and intensity assigned by the Plan to two, much larger areas in the northern half of northwest Hillsborough County. The extent of the subject areas corresponds to the areas whose densities were increased, according to Oversized Map 14 (excluding only the above-described Low Suburban Density Residential area). The western area of the two is a contiguous block surrounding Keystone Lake and proceeding east and west of the major public supply water wells about 1-2 miles south of Keystone Lake. This area extends to the northwest corner of Hillsborough County, except for the very corner, which is Natural Preservation. The eastern area is a contiguous block almost entirely west of SR 597, but crossing SR 597 at the southeast corner. This area abuts Pasco County on the north and an area of density decrease on the south. These two areas of increased density and intensity surround (or in some cases slightly encroach upon) the four largest collections of major public supply water wells in northwest Hillsborough County, as shown on Oversized Map Representing perhaps half of such collections of major public supply water wells in the entire County, these wells represent a very important source of potable water, especially for a County in which demand is now exceeding supply. The two areas in question are in areas of relatively good natural aquifer recharge and areas of high vulnerability to groundwater contamination. The Plan supplies no performance standards for activities that may introduce contaminants into the portion of the aquifer from which a major public supply water well draws. As the Data and Analysis note, increasing areas of impervious surface may reduce recharge and groundwater supplies. A considerable amount of the eastern area lies in the 100 year floodplain, which runs throughout both areas. The eastern area also includes a significant section of soils with very severe limitations, according to Oversized Map 13 and CARE Figure 9. The green map indicates two overlay areas of Environmentally Sensitive Areas which are potentially significant wildlife habitat. One of these areas is in the southwest corner of the eastern area, and the other covers the part of the eastern area designated Regional Commercial. The western area contains numerous sites described by Oversized Map 13 as Very Sensitive Lands and most of one significant section of soils with very severe limitations, according to Oversized Map 13 and CARE Figure 9. According to CARE Figure 20, the western area contains significant amounts of dry prairie and cypress swamps. According to the green map, the western areas's potentially significant wildlife habitat takes the form of two narrow corridors running east-west, although the northern one may have been excluded from the area receiving increased density. As noted above, contiguous wildlife corridors receive firm protection under the Plan. The designations are completely different for the two areas. The western area contains entirely Rural Residential (1:1) and Rural Estate Residential (1:2.5), except for small areas of Environmentally Significant Areas. The more densely designated eastern area contains mostly Low Suburban Density Residential (2:1) and smaller, but significant, amounts of Suburban Density Residential (4:1). Each of these areas would, under the Plan, host commercial uses scaled to their respective Rural and Suburban densities. But the southeast corner of the eastern area is designated Regional Commercial (20:1) and contains major natural systems according to Oversized Map 8. The natural systems appear to be dry prairie and cypress swamps on CARE Figure 20. According to Oversized Map 2, this corner is agricultural or vacant with natural area in its center. The unsuitability of the designations given both the eastern and western areas is about equal. Although the western area received less density, according to Sewer Element Figure 1, the western area is almost entirely outside the area that will be served by central sewer, even by 2010. Most of the western area will be served by central water by 2010, with a substantial area to be served by 1995, according to Potable Water Element Figure 1. By contrast, the eastern area already has some central sewer lines and what little area will not be within the 1995 central sewer boundary will be included in the 2010 boundary. The situation is identical with respect to central water. The unsuitability of the designations of the eastern and western areas is unaffected by the fact, as shown by Oversized Map 15, that the Plan brought portions of these areas into conformance with existing zoning. Zoning conforms to Plan designations. The Plan provides, where appropriate, for vested rights. The remedy for nonconforming zoning is to recognize vested rights, not to increase densities and intensities over wide areas to an extent not supported by the Data and Analysis. The key fact is that, for both the western and eastern areas, the Plan has designated excessive densities and intensities in areas containing sensitive and much-needed groundwater resources. And while increasing these densities and intensities, the County has not, at the same time, adopted effective Plan provisions ensuring the protection of wellfields, their cones of influence, natural recharge areas, and the natural functions of floodplains from the adverse impacts of development. Another area whose designation is, to the exclusion of fair debate, unsupported by the Data and Analysis is an area of about 2.5 square miles designated Urban Level 1 Limited (8:1) immediately east of I-275 and I-75. The extent of the subject area corresponds to the area designated Urban Level 1 Limited on the FLUM. The 2.5 square mile area is the only Urban Level designation that is not contiguous to the Urban Level designations constituting the I-75 corridor, except for a small Urban Level-1 "island" surrounded by Natural Preservation. 28/ The 2.5 square mile area designated Urban Level 1 Limited is separated from the remainder of the I-75 corridor by several miles of area designated Natural Preservation. Nor is the 2.5 square mile area bounded by existing or proposed arterial roads, as is required of Urban Level 1 areas. According to Oversized Map 4, the only arterial or higher roads in or near the 2.5 square mile area are I-75 on the west boundary (to which access is limited) and an arterial on the east boundary. There are no roads on the north and south boundaries, nor will there be by 2010, according to Oversized Map 4. Almost the entire 2.5 square mile area is overlaid with Environmentally Sensitive Areas which are potentially significant wildlife habitat, according to the green map. The northern half of the 2.5 square mile area is in the 100 year floodplain. The eastern and western thirds of the area consist of very poorly drained soils. The northern two-thirds of the area occupy an area of very low to moderate recharge, which is the highest recharge in Hillsborough County. Most of the western half of the area is in the area most susceptible to groundwater contamination. The eastern third appears to be entirely dry prairie and cypress swamps, through which a major tributary of the Hillsborough River runs. Oversized Map 8 shows nearly the entire parcel (less a small area at the western end) to be part of major natural systems. Oversized Map 2 shows that the 2.5 square mile areas is entirely agricultural or vacant. Despite this unusual confluence of natural features, the 2.5 square mile area, which is permanently separated from Tampa by a Natural Preserve protecting the Hillsborough River, received a density increase in connection with the I-75 and South County plan amendments that were incorporated into the Plan. The 2.5 square mile area is entirely omitted from even the 2010 central water and sewer service areas, according to Sewer Element Figure 1 and Potable Water Element Figure 1. The failure of Plan provisions to ensure the protection of the natural functions of floodplains and recharge areas exacerbates the unsuitability of the Urban designation for the 2.5 square mile area. The meaning of Urban Level 1 Limited is explained by FLUE Policy C-25.3, which limits the density in the 2.5 square mile area to 8:1. But even this "reduced" density fails to indicate that this remote area will undergo development suitable for the unusual range of natural resources present in the area. The circumstances suggest that the Urban Level 1 Limited designation cannot facilitate the development in this remote area of the kind of viable mixed uses for which Urban designations are intended. A mere preponderance of the evidence shows that the Data and Analysis do not support the density assigned by the Plan to a much larger L-shaped area designated Suburban Density Residential (4:1) extending from the 2.5 square mile area to just across CR 579. The extent of the subject area corresponds to the area designated Suburban Density Residential on the FLUM. The Suburban Density Residential L-shaped area, which is about 12 square miles, contains three major public supply water wells at its southeast corner. The green map overlays more than three quarters of the 12 square mile area with Environmentally Sensitive Areas which are potentially significant wildlife habitat. The 12 square mile area abuts the above- described 2.5 square mile area on the northwest, Tampa on the southwest and nearly all of the south, Pasco County and Agricultural/Rural (1:5) on the north, and Agriculture (1:10) on the east. According to CARE Figure 20, the portions of the 12 square mile area overlaid with the designation of Environmentally Sensitive Areas which are potentially significant wildlife habitat are dry prairie and cypress swamps, as is almost two- thirds of the land south of the subject area under the jurisdiction of the City of Tampa. According to CARE Figure 14, the western half of the 12 square mile area is in an area of relatively good natural aquifer recharge, but only a very small part of the subject area is in an area of high vulnerability to groundwater contamination. However, a large collection of major public supply water wells is in the Natural Preservation area just south of the extension of Tampa abutting the south boundary of the 12 square mile area. The closest wells are about one mile south of the southern boundary of the 12 square mile area. According to Oversized Map 13, the only part of the 12 square mile parcel with poor soils is the extreme northwest corner. Oversized Map 2 shows that the entire 12 square mile area that is not shown as natural areas is agricultural or vacant, as is the area of Tampa immediately south of the subject area. According to Sewer Element Figure 1 and Potable Water Element Figure 1, the 12 square mile area is not scheduled to receive central water or sewer by 2010. The remaining areas whose designations are not supported by the Data and Analysis are in the vicinity of the coastal high hazard area in south Hillsborough County and in the Urban designations and one Light Industrial designation along the I-75 corridor south of the Alafia River. The Plan assigns designations to two areas in or near the coastal high hazard area that, to the exclusion of fair debate, are not supported by the Data and Analysis. The Plan also assigns designations to four areas in (or adjoining, in the case of the Light Industrial area) the I-75 corridor south of the Alafia River that are not supported by the Data and Analysis to the exclusion of fair debate, in one area, and by a mere preponderance of the evidence in the other three areas. The coastal high hazard area begins at the Manatee County line and runs along US 41. At a point due east of Cockroach Bay, the line turns toward the bay and continues to run in a more northerly direction until it approaches the Little Manatee River. At this point, the coastal high hazard line follows the winding river to the east, then south, crossing US 41 before proceeding again north. The line runs along US 41 until, at the north end of Ruskin, the line cuts again toward the bay. After running north again for about one mile, the line returns to US 41, then proceeds west of US 41, in a north-northeasterly direction, until it almost intersects the bay at Apollo Beach. North of Apollo Beach, the line mostly follows US 41 to the Alafia River at Gibsonton. Oversized Map 14 discloses density increases in part of the coastal high hazard area between Cockroach Bay and the Little Manatee River. Initiated by the I-75 and South County plan amendments that were incorporated into the Plan, an irregularly shaped area about three square miles west of US 41 received a density increase. The Plan then increased the density of a smaller portion of the eastern end of the three square mile area. The extent of the subject area, which is only partly in the coastal high hazard area, corresponds to the area whose density was increased, according to Oversized Map 14, and that is presently designated, in the FLUM, as Low Suburban Density Residential Planned (2:1 if certain clustering and mixed use requirements are met; otherwise 1:5). Oversized Map 2 shows that the entire area so designated is entirely agricultural or vacant, except for a shell mine, three small, isolated areas of low density residential, and some small commercial uses along US 41. The density increase for the portion of the three square mile area lying in the coastal high hazard area is clearly unsupported by the Data and Analysis, which acknowledge the need to reduce, not raise, densities in this critical area in order to save lives and property. However, much of the three square mile area is outside of the coastal high hazard area and the unsuitability of the designation lies in the assigned density, not in the increase of density. About a third of the three square mile area is in the 100 year floodplain. Relatively little of it contains major natural systems or Environmentally Sensitive Areas which are potentially significant wildlife habitat, according to Oversized Map 8 and the green map. And none of the area is subject to recharge or significantly vulnerable to groundwater contamination. However, the three square mile area is bordered on three sides by three critical resources that remain in relatively pristine condition: Cockroach Bay, the Little Manatee River, and the portion of Tampa Bay connecting the river and Cockroach Bay. The entire shoreline along the three square mile area joins Hillsborough County's only aquatic preserve. Coastal Figure 11 indicates that the coast from just south of Apollo Beach to the Manatee County line, and especially from the Little Manatee River to Cockroach Bay, is the only location where seagrass meadows remain along the waters of unincorporated Hillsborough County, except for a smaller expanse of interspersed meadows along the shore of northwest Hillsborough County. These are also Class II waters. CARE Figure 9 shows that the western half of the three square mile area is dominated by very poorly drained soils. The Data and Analysis note that area septic tank failures have contributed to the pollution of Cockroach Bay and possible loss of the last shoreline location in the County at which shellfish harvesting is approved, although only conditionally. Significantly, in view of the poorly drained soils and history of septic tank failures, Sewer Element Figure 1 shows no existing or proposed sewer lines for the three square mile area, which inexplicably is nonetheless included in the 2010 central sewer service area. The area is due to receive central water lines by 2010. Given the critical and fragile nature of the area of Cockroach Bay and the Little Manatee River, as described by the Data and Analysis, the Low Suburban Density Residential Planned designation, which, with the I-75 and South County plan amendments, represented an increased density for the three square mile area, is not, to the exclusion of fair debate, supported by the Data and Analysis. The failure of the Plan to direct population concentrations away from the coastal high hazard area and ensure the protection of the natural functions of the 100 year floodplain exacerbates the unsuitability of the Low Suburban Density Residential Planned designation for the three square mile area. Just north of the Little Manatee River at Ruskin, Oversized Map 14 discloses another area of density increase, again initiated by the I-75 and South County plan amendments that were incorporated into the Plan. This area is designated Medium Density Residential (12:1) and extends two miles east-west by an average of one-half mile north-south. The southwest corner of the one square mile area abuts a portion of the Little Manatee River, and nearly the entire south boundary of the area abuts a tributary of the Little Manatee River. The extent of the subject area corresponds to the area designated Medium Density Residential on the FLUM. The entire square mile area lies west of US 41 and in the coastal high hazard area. The designation is, to the exclusion of fair debate, unsupported by the Data and Analysis for this reason alone. According to Oversized Map 2, the southern half of the square mile area is already in low and medium density residential, except for the western end that is agricultural or vacant. However, most of the northern half is agricultural or vacant. According to Oversized Map 13, the entire square mile area contains soils with very severe limitations and some critical lands. The entire area occupies the 100 year floodplain. And the area is not due to receive central sewer until 1995 or central water at all, although it is in the 1995 central water service area. Even absent the fact that the square mile area is in the coastal high hazard area, the Medium Density Residential designation is, to the exclusion of fair debate, unsupported by the Data and Analysis. The remaining four areas in the County whose designations are unsupported by the Data and Analysis are in the I-75 corridor, except for one of the areas that extends into an adjoining Light Industrial area. Nearly the entire contiguous corridor received higher densities as a result of the I-75 and South County plan amendments that were incorporated into the Plan. However, the four areas in question all lie south of the Alafia River. The first area is about 3.25 square miles at the southernmost end of the I-75 corridor, south of SR 674. Triangularly shaped, this area, which is Urban Level 1 (12:1), is bounded on the east and north by I-75. The extent of the subject area corresponds to the area designated Urban Level 1 south of SR 674 and I-75. The southern boundary of the triangular area represents an anomaly for the I-75 corridor; it abuts Rural Residential (1:1). Except for the portion of the north end of the I-75 corridor surrounding a Rural Residential "island" and the northernmost end of the I-75 corridor, which abuts the vast Natural Preservation area of the Hillsborough River valley, no other part of the I-75 corridor abuts land that is not designated at least Suburban. Contrary to the requirements for Urban Level 1 designations, the triangular area is not bound by existing or proposed arterials. The triangular area also abuts a Natural Preservation area at its southeast corner. The Little Manatee River is less than one-half mile from the southern boundary of the subject area. The southernmost mile of the subject area encompasses tributaries of the Little Manatee River. The northern half of the subject area adjoins Suburban Density Residential (4:1) and Low Medium Density Residential (9:1) on the east and Low Urban Density Residential (6:1) and Urban Level-2 (20:1) across I-75 on the west. The northern point of the subject area is in the vicinity of the I-75/SR 674 interchange. The triangular area is free from major natural systems or Environmentally Significant Areas which are potentially significant wildlife habitat, according to Oversized Map 5 and the green map. However, most of the southernmost mile of the subject area is within the 100 year floodplain. Oversized Map 2 reports that the subject area is predominantly agricultural or vacant, although it has interspersed, isolated low density and some medium density residential uses, mostly in the northeast portion. The triangular area is not scheduled for any central sewer lines until after 1995, and then the line will be limited to about one-half mile south of SR 674 along I-75. The area will be better served, by 2010, by central water. Given the Plan's failure to protect adequately floodplains and the proximity of the Little Manatee River, the evidence shows, to the exclusion of fair debate, that the Urban Level-1 designation of the southernmost mile of the triangular area is not supported by the Data and Analysis. The designation given to the remainder of the triangular area is not unsupported by the Data and Analysis. A mere preponderance of the evidence shows that the Data and Analysis do not support predominantly Urban Level 1 densities and intensities in two areas in the vicinity of I-75 and Big Bend Road. One of the areas in question is a Z-shaped linear area that largely tracks, but is not limited to, a strip of Environmentally Sensitive Areas. The strip begins at US 301 and a proposed westerly extension of SR 672. The area, which is limited to the Urban I-75 corridor, proceeds in a west- northwesterly direction to just east of I-75, runs north along the east side of I-75 to a point about one mile south of the Alafia River, and, now becoming Bullfrog Creek, turns west and crosses I-75 until it leaves the I-75 Urban Level corridor. The extent of the subject area corresponds to the areas in the vicinity of the Z-shaped area that are within any of the three following categories: the 100 year floodplain according to Oversized Map 9, Environmentally Sensitive Areas on the FLUM, or Environmentally Sensitive Areas on the green map. The lower half of the Z-shaped area occupies very severely limited soils. The upper half contains critical and very sensitive lands. According to Oversized Map 14, almost the entire Z-shaped area received increased densities due to the I-75 and South County plan amendments that were incorporated into the Plan. According to Oversized Map 2, existing uses of considerable portions of the Z-shaped area are natural areas and agricultural or vacant. CARE Figure 20 indicates that Bullfrog Creek is largely open water until it turns south just east of I-75, at which point a series of hardwood swamps extend through the remainder of the Z-shaped area to the south. The Z-shaped area, which runs about eight miles, has long been recognized as environmentally sensitive and generally unsuitable for development. 29/ The narrow band of Environmentally Sensitive Areas is afforded uncertain protection under the Plan. Moreover, the Urban Level 1 designation extends to portions of the Z-shaped area that are in the 100 year floodplain and the Environmentally Sensitive Areas which are potentially significant wildlife habitat, according to the green map. In the absence of stronger Plan provisions protecting the 100 year floodplain, as well as Environmentally Sensitive Areas, the Urban Level 1 designation given the Z-shaped area is, by a mere preponderance of the evidence, unsuitable and unsupported by the Data and Analysis. The unsuitability of the designation is underscored by the operation of the density and intensity formulas, which would allow even more intense and dense uses in close proximity, even assuming that development were prohibited in the Environmentally Sensitive Areas themselves. Two other areas bearing unsuitable designations are also in the vicinity of Big Bend Road and I-75. Unlike the remainder of the contiguous I-75 corridor, these areas mark significant expanses of Environmentally Sensitive Areas which are potentially significant wildlife habitat. One area runs from the southeast corner of the interchange along I-75 south past a proposed extension of Balm-Picnic Road or SR 672, where the area expands to an area of about one mile north-south by two miles east-west, with the western end crossing I-75. The extent of the subject area corresponds to the area shown on the green map as Environmentally Sensitive Areas which are potentially significant wildlife habitat. The subject area is designated exclusively Urban Level 1 except for a small area designated Environmentally Sensitive Areas. The upper portion of the subject area overlaps the part of the Z- shaped area running north-south just south of Big Bend Road. According to CARE Figure 20, the remainder of the narrower part of the subject area is wetlands. The wider portion of the subject area is predominantly dry prairie. According to Oversized Map 14, the entire subject area received increased density in the I-75 and South County plan amendments that were incorporated into the Plan. According to Oversized Map 2, the existing uses of the entire subject area are natural areas and agricultural or vacant. The Urban Level-1 designation given the subject area is, by a mere preponderance of the evidence, unsuitable and unsupported by the Data and Analysis. The allowable densities and intensities contradict the acknowledgement in the Data and Analysis of the need to protect these natural resources and frustrate other Plan provisions that extend some protection to these natural resources. The other area extends northwest of the intersection of Big Bend Road and I-75. The subject area runs about 1.5 miles north of the intersection, then widens to the west to encompass a portion of the Light Industrial designation between the I-75 corridor on the east and, on the west, Tampa Bay and the large Heavy Industrial area north of Apollo Beach. The extent of the subject area corresponds to the area shown on the green map as Environmentally Sensitive Areas which are potentially significant wildlife habitat. Except for the Light Industrial designation, the entire subject area is designated Urban Level 1 with a small area of Urban Level 2. According to CARE Figure 20, almost all of the subject area is wetlands, possibly with some pine flatwoods. Part of the subject area received a density increase by the I-75 and South County plan amendments that were incorporated into the Plan. According to Oversized Map 2, the existing uses of all of the subject area are natural area and agricultural or vacant, with a narrow corridor of major public area. The Urban Level 1 and 2 designations assigned to the subject area are, by a mere preponderance of the evidence, unsuitable and unsupported by the Data and Analysis for the same reasons set forth with respect to the preceding area. General Minimum Criteria Public Participation (Issue 15) As to Issue 15, the County adopted the Plan, including all amendments, in a manner consistent with the requirements of public participation. Contents of FLUM and Plan (Issues 16-36) FLUM (Issue 16) As to Issue 16, the FLUM depicts minerals in the Agricultural/Mining designation and various public uses in the Major Public/Semi-Public designation. Regardless of the ambiguity surrounding the significance of the designation, the Environmentally Sensitive Areas designated on the FLUM (i.e., the multicolor map) adequately show the location of wetlands. However, to the exclusion of fair debate, the FLUM is not consistent with the criterion of the depiction of existing and planned waterwells, cones of influence, historic resources or historically significant properties meriting protection, floodplains, or soils. All of these resources are depicted on ELUM's, but the County elected not to include these resources on the FLUM as part of the operative provisions of its Plan. Plan Provisions Regarding Natural Resources (Issues 17-22) As to Issue 17, the Plan contains objectives coordinating future land uses with topography, soils, and the availability of public facilities. Regarding topography and soils, FLUE Objective A-1 prohibits the issuance of development orders unless the development is "compatible with the physical conditions of the land, including, but not limited to, topographical and soil conditions . . .." FLUE Objective A-8 requires development to mitigate adverse impacts to natural systems. Regarding topography, FLUE Objective 4 is to protect the 100 year floodplain's storage volume. Somewhat vaguely, CARE Objective 19 is to amend land development regulations to "ensure the protection of the attributes, functions and amenities of the natural environment " Regarding the stormwater management aspects of topography, Stormwater Element Objective 4 is to identify and evaluate the sources of water quality degradation attributable to stormwater runoff. Stormwater Objective 5 is to maintain or improve the quality of stormwater runoff. Regarding soils, CARE Objective 11 requires soil conservation during land alteration and development activities. Although not objectives, two policies address the suitability of soils. CARE Policy 11.1 provides that, during the land development review process, the County shall "recommend" the appropriate use of soils and shall require site-specific analyses when land uses appear incompatible with soils. CARE Policy 11.3 states that, during the land development process, the County shall use soil capability analyses for flood hazard, stability, permeability, and other soil characteristics. Regarding mining, CARE Objective 7 requires the "prudent operation" of mining activities. CARE Objective 9 is to protect the public health, safety, and welfare from the adverse impacts of mining. CARE Objective 10 requires the County to regulate the location and operation of land excavation to minimize negative impacts on surrounding land uses and ensure the reclamation and productive reuse of excavated lands. Regarding public facilities, FLUE Objective A-5 is that all development and redevelopment shall be serviced at the adopted level of service standards by all public facilities for which concurrency is required. FLUE Objective C-29 requires that the needed public facilities be provided concurrent with the impacts of development. Although there are several instances where specific land use designations are unsuitable in terms of, among other factors, topography, soils, and the provision of public facilities, the Plan contains sufficient provisions to attain consistency with the criterion of an objective coordinating future land uses with topography, soils, and public facilities. As to Issue 18, numerous Plan provisions address numerous natural resources, as well as water sources. The rules cited in Issue 18 require one or more objectives ensuring the protection of natural resources, such as Tampa Bay and its tributaries, and one or more objectives conserving, appropriately using, and protecting water sources. 30/ For the purpose of Issue 18, natural resources have been identified as Tampa Bay, Cockroach Bay, rivers (primarily the Hillsborough, Alafia, and Little Manatee Rivers), surface waters generally, floodplains, wetlands, rare upland habitats, and wildlife habitat. Findings concerning soils are set forth above. The water sources have been divided into the following categories: wellfields and cones of influence, aquifer recharge, groundwater, water conservation, and septic tanks. Obviously, wellfields, cones of influence, and aquifer recharge areas are natural resources, and floodplains, wetlands, and the Hillsborough River (whose surface waters are an important potable water source) are related to water sources. There is thus considerable overlap in the following discussion of these categories. Regarding surface water generally, including Tampa Bay, Cockroach Bay, and the rivers, CARE Objective 2 promises that the water quality of natural surface water bodies shall be improved or restored if they do not at least meet state water quality standards. Unfortunately, CARE Objective 2 is not operative until 1995. If the objective had assured compliance with water quality standards, a deferred date of 1995 would have been suitable because the entire improvement cannot take place instantaneously. However, the intermediate end of CARE Objective 2 is much more modest; the water quality of substandard water bodies must only be improved. And the improvement--any improvement--is not required until 1995. The main threats to Tampa Bay also apply to surface water quality generally: inadequately treated wastewater and inadequately treated stormwater. The Plan does not generally ensure the protection of surface water through the objectives and relevant policies concerning stormwater. Stormwater Objective 5 is to implement programs to maintain or improve stormwater. The natural resources in question are not protected by maintaining the water quality of stormwater; they are not even protected by improving the water quality of stormwater absent a measurable goal. The failure of the stormwater objectives is exacerbated by the Plan's failure to set stormwater level of service standards in terms other than flood control. The Plan addresses to a much greater extent the protection of surface water through the objectives and relevant policies concerning wastewater. Sewer Element Objective 1 is for all wastewater treatment facilities to produce effluent of sufficiently high quality to meet or exceed all regulatory standards. Sewer Element Policy 1.1 requires that all wastewater discharged into surface waters or wetlands meet Advanced Wastewater Treatment standards. Sewer Element Objective 2 promises to assist in the wastewater problem by continuing to require the use and expansion of existing recovered water reuse systems. Sewer Element Objective 4 requires that central sewer facilities be provided to remedy current deficiencies in the system and to meet projected demands, based on the sewer level of service standard. Sewer Element Objective 7 is to "[m]inimize the possibility" that existing and future wastewater adversely impacts surface waters. The objective is not especially amenable to measurement. Sewer Element Policy 7.1 is useful, though, because it requires that septic tank users hook up to the County system when it becomes available, except in cases of undue hardship. Sewer Element Policy 4.8 also prohibits septic tanks in the coastal high hazard area except in cases of undue hardship. CARE Policy 2.6 promises better wastewater treatment in areas where septic tanks fail, at least where economically feasible. And CARE Policy 2.4 indicates that the County plans to supply regional wastewater treatment in the more densely populated areas. However, other policies under Sewer Element Objective 7 are less effective. Sewer Element Policy 7.2 promises that, within one year after the completion of a pending septic tank study, the County will reexamine the maximum usable density for septic tanks. Sewer Element Policy 7.3 promises, in the same timeframe, a program to identify existing septic tank systems with a high potential for contaminating groundwater. Regarding Tampa Bay, Coastal Element Objective 3 is to "maintain, and enhance where environmentally and economically feasible, the abundance and diversity of living marine resources in Tampa Bay." FLUE Objective C-30 requires the County to adopt land development regulations and unspecified performance standards to ensure that "water quality and quantity" are protected from degradation from development. CARE Objective 19 promises that the County shall continue to amend its land development regulations to "ensure the protection of the attributes, functions and amenities of the natural environment." In addition to relegating the regulatory mechanism to land development regulations, CARE Objective 19 does not state a specific, measurable, intermediate end that can be achieved. Coastal Element Policy 2.1 is to conserve and protect tidal wetlands from detrimental physical and hydrological alteration and prohibit unmitigated encroachment into tidal wetlands. Coastal Element Policy 2.2 prohibits channelization or hardening of natural coastal shorelines and tidal creeks except in cases of overriding public interest. Coastal Element Policy 2.6 prohibits development activities on submerged lands containing significant seagrass habitat and seeks the restoration of seagrass coverage. Coastal Element Policy 2.7 requires land developments within the coastal area to preserve those portions of native upland plant communities necessary to provide an effective buffer for coastal wetlands. Coastal Element Policy 2.9 is to review and "restrict as appropriate" proposed development adjacent to the Cockroach Bay Aquatic Preserve to ensure that water quality, shoreline, or estuarine habitat degradation does not occur due to development. Coastal Element Policy 6.7 prohibits the use of septic tanks for new development in the coastal high hazard area. Coastal Element Policy 7.4 forbids the development of water- related uses by dredging and filling wetlands or the natural shoreline. CARE Policy 19.8 requires the County to identify Resource Protection Areas on the FLUM. Resource Protection Areas include Tampa Bay, Cockroach Bay, the three main rivers, significant and essential wildlife habitat, areas of high aquifer recharge/groundwater contamination potential, public supply wellfields and their cones of influence, and areas containing major phosphate deposits. CARE, pages 99-100. For Tampa Bay, the CARE definition of Resource Protection Areas refers the reader to the Coastal Element. Coastal Element Objective 1 is identical to CARE Objective 2. Coastal Element Objective 1 addresses only the water quality of those parts of Tampa Bay and its tributaries not meeting state standards. By 1995, these waters will be improved or restored. In addition to failing to address the protection of those parts of Tampa Bay meeting or exceeding state standards, this objective promises only, as to substandard waters, that some improvement is to take place starting in 1995. As is the case with surface waters generally, the Plan contains various provisions adequately addressing wastewater. CARE Policy 2.2 and Coastal Element Policy 1.2 require Advanced Wastewater Treatment for all surface water discharge from all domestic wastewater treatment plants discharging into Tampa Bay or any of its tributaries. Coastal Element Policy 1.4 is to continue to develop and use effluent-disposal alternatives, such as reused water for agricultural and industrial uses, rather than surface water discharge into Tampa Bay and its tributaries. Coastal Element Policy 1.7 provides that, where it is economically feasible, the County shall provide improved domestic wastewater treatment in areas where persistent water quality problems in Tampa Bay are clearly attributable to poorly functioning septic tank systems. Again, the Plan offers less protection to Tampa Bay from inadequately treated stormwater runoff. However, addressing another source of excessive nutrients in Tampa Bay, Coastal Element Policy 1.12 provides for the dredging and removal of polluted estuarine sediments and their replacement with clean fill, where economically and environmentally feasible. Regarding the Hillsborough, Alafia, and Little Manatee Rivers, numerous goals, objectives, and policies in the FLUE provide protection for these resources. FLUE Goal 3 is to make the Hillsborough River cleaner. FLUE Objective C-7 is to protect the Hillsborough River as a major source of drinking water. Somewhat less effective are FLUE Objectives C-10 and C-12. Objective C-10 requires the County, by 1992, to establish development standards for the river corridor. Objective C-12 requires the County, by 1994, to manage the Hillsborough River as an important community asset. FLUE Policy C-9.1 prohibits new marinas in the upper Hillsborough River. FLUE Objective C-14 is to discourage additional development on the upper Hillsborough River. FLUE Policy C-14.1 requires the County to manage the upper Hillsborough River as a wildlife corridor. FLUE Objective C-13 requires the County to preserve and enhance wildlife habitats associated with the Hillsborough River. Because of the Hillsborough River's status as a source of surface potable water, it receives additional protection from CARE Objective 6, which requires the conservation, reuse, and enhancement of surface water supplies. Various policies add to the protection extended the Hillsborough River. FLUE Policy C-7.2 prohibits new septic tanks within 200 feet of the Hillsborough River, although, unlike similar provisions concerning the Alafia and Little Manatee Rivers, this prohibition is not extended to tributaries. FLUE Policy C-7.4 requires Advanced Wastewater Treatment for wastewater treatment discharging anywhere in the Hillsborough River drainage basin. FLUE Policy C-7.3 prevents further destruction of the natural vegetative buffers along the Hillsborough River. FLUE Policy C-10.2 prohibits the designation of new industrial land uses within 500 feet of the river. FLUE Policy C-13.1 prohibits the alteration of wetlands within 500 feet of the river. Regarding the Alafia River, FLUE Goal 4 is to preserve, protect, and promote the Alafia River and its natural resources and recreational benefits. FLUE Objective C-15 requires the County to maintain the water quality of this already impaired waterbody, but only by 1995. FLUE Objectives C-16 and C-17 require the County, by 1991, to preserve and restore native vegetation and wildlife habitats and protect wildlife, presumably along the Alafia River. FLUE Policy C-16.1 prohibits the alteration of wetlands within 500 feet of the river. FLUE Policy C-16.2 requires the County to "encourage" the reclamation of mined lands along the river with native vegetation. FLUE Objective C-20 requires the County, by 1992, to establish development standards for the corridor of the Alafia River. FLUE Policy C-20.4 prohibits the designation of "heavy" industrial land uses within 500 feet of the river. FLUE Policy C-20.3 prohibits the location of septic tanks within 200 feet of the Alafia River or its tributaries, except when required due to lot size and adverse impacts can be prevented. Regarding the Little Manatee River, FLUE Goal 5 is to recognize and maintain the river as a unique water resource, which provides vital wildlife habitat. As in the case of FLUE Objective C-15 regarding the Alafia River, FLUE Objective C-21 defers until 1995 the objective of maintaining or improving water quality where it does not meet state standards. FLUE Objective C-22 is to preserve wildlife habitats, presumably in association with the Little Manatee River. FLUE Objective C-23 is, by 1990, to establish a green river corridor for the river, although whatever protection is to be afforded by these provisions, if adopted in the Plan, appears already to be included in the Plan, given that the deadline in Objective C-23 had already passed by the time of the final hearing. The same is true for FLUE Objective C- 24, which is, by 1990, to develop additional policies addressing the uniqueness of the Little Manatee River. FLUE Policy C-21.1 prohibits the installation of septic tanks within 200 feet of the Little Manatee River unless required due to lot size and adverse impacts to the water can be prevented. FLUE Policy C-22.2 prohibits alteration of the wetlands within 500 feet of the river. FLUE Policy C-23.1 prohibits the designation of "heavy" industrial within 500 feet of the river. FLUE Policy C-22.3 only "restricts" the clearing or filling of natural plant communities within 50 or 100 feet of the river in Urban or Suburban designations. However, FLUE Policy C-23.2 is to manage the Little Manatee River as a wildlife corridor. Various Plan provisions apply to rivers generally. Some of these provisions restate objectives or policies adopted for one of the three major rivers. For instance, FLUE Objective C-1 is, by 1995, to maintain or improve the water quality of rivers not meeting state standards. FLUE Objective C-4 is, by 1992, to set standards for development in river corridors. Other provisions provide additional protection. FLUE Objective C-2 is to preserve natural shorelines and reverse the trend toward hardened shores and channelization. FLUE Objective C-30 requires the County to adopt land development regulations and unspecified performance standards to ensure that rivers are protected from degradation from development. FLUE Policy C-30.6 is to "restrict" the clearing or filling of natural plant communities within 50 or 100 feet of rivers. FLUE Policy C-6.1 generally prohibits the removal, within 100 feet of rivers, of any trees of at least five inches diameter at breast height. FLUE Policy C-1.3 prohibits the siting of solid waste or hazardous landfills that would adversely affect any river. Significantly, FLUE Policy C- 1.1 requires that development along the rivers install stormwater management systems to filter pollutants, although the extent of filtration is not specified. Regarding Cockroach Bay, the Plan offers some protection because, as an aquatic preserve, the bay is an Environmentally Sensitive Area. However, regardless of the extent of protection afforded by this designation to land- based areas, it is relatively unimportant as a regulatory mechanism over a water preserve, except to the extent that the designation is extended over adjacent land areas. Much of the land around the bay is designated Natural Preservation, which is afforded effective protection, and Environmentally Sensitive Areas, which is not. However, as noted above, Coastal Element Objective 3 requires the County at least to maintain the abundance and diversity of living marine resources in Tampa Bay. Underscoring the relationship between Cockroach Bay and Tampa Bay, Coastal Element Policy 3.1 is for the County to resist proposals to close permanently the Cockroach Bay Aquatic Preserve to shellfishing and to improve water quality to maintain the viability of shellfishing by implementing Coastal Objective 1 and its policies. However, as noted above, Coastal Objective 1 addresses only waters not meeting state standards and requires only that, by 1995, these water be improved. Cockroach Bay may receive some protection from FLUE Objective C-30, which requires the County to adopt land development regulations and unspecified performance standards to ensure that water quality and quantity are protected from degradation from development. In somewhat vague terms, CARE Objective 18 is for the County to "seek to measurably improve" the management of natural preserves, which include Cockroach Bay. Rather than exercise its jurisdiction, however, the County, in CARE Policy 18.2, promises only to initiate an agreement with the Florida Department of Natural Resources to ensure that Cockroach Bay is maintained in its natural condition. Equally ineffective, CARE Policy 18.3 is for the County, at no specified time, to establish a scientifically defensible buffer zone to prevent degradation of water quality and aquatic vegetative habitats in Cockroach Bay. CARE Policy 18.8, FLUE Policy C-22.1, and Coastal Element Policy 4.5 promise that the County will "participate" with the Florida Department of Natural Resources to implement the Cockroach Bay Aquatic Preserve Management Plan. Regarding floodplains, CARE Objective 4 is no "net loss of 100-year floodplain storage volume." CARE Policy 4.1 promises, by 1995, land development regulations to "not only protect natural floodwater assimilating capacity but also protect fish and wildlife attributes where they exist within the 100 year floodplains of riverine systems." CARE Policy 4.2 explains that the County shall prohibit "unmitigated" encroachment into the 100 year floodplain. CARE Policy 8.3 "prohibit[s]" mining in the 25 year floodplain and "restrict[s]" mining in the 100 year floodplain. Although still in terms of storage volume of the floodplain, Stormwater Element Policy 2.8 promises, by 1991, a "program to control encroachment into the 100 year floodplain." Regarding wetlands, CARE Objective 3 is "no net loss of wetland acreage." The objective states further that the County shall seek to achieve a "measurable annual increase in restored wetland acreage." CARE Policy 3.1 requires the County to continue to "conserve and protect" wetlands from "detrimental physical and hydrological alteration" and "allow wetland encroachment only as a last resort when reasonable use of the property is otherwise unavailable." CARE Objective 16 is to continue to protect and conserve Conservation and Preservation Areas, which include a variety of wetland habitats. Regarding rare upland habitats, CARE Objective 16 offers some protection, as sand pine scrub is a Conservation Area and significant and essential wildlife habitat are, respectively, Conservation and Preservation Areas. CARE Policies 16.5 and 16.6 are to protect Conservation and Preservation Areas, respectively, from activities that would "significantly damage the natural integrity, character or ecological balance of said areas, except in cases of overriding public interest." CARE Objective 17 is to increase the amount of acreage designated as Natural Preservation by 15,000 acres by 1995. Also, the upland forest density credit incentive assists in promoting the preservation of rare upland habitats. Despite the ambiguity surrounding the types of land uses allowed by the Environmentally Sensitive Areas designation, the Plan protects the wetlands and rare upland habitats. Regarding wildlife habitat, CARE Objective 14 is to "prevent any further net loss of essential wildlife habitat" and to "protect significant wildlife habitat." CARE Objective 15 is to maintain existing populations of endangered, threatened, and special-concern species and, where "feasible and appropriate," to increase the "abundance and distribution" of such species. FLUE Objective C-5 is, by 1991, to "require the preservation and enhancement of wildlife habitats." CARE Objective 4 is, by 1995, to protect wildlife habitat in the 100 year floodplain. CARE Policy 14.7 is to require the preservation of wildlife corridors within developments when necessary to prevent fragmentation. CARE Policies 8.4 and 10.7 prohibit mining and land excavation, respectively, in essential wildlife habitats unless relocation of the affected species is feasible. On balance, despite the noted shortcomings, the Plan is consistent with the criterion of one or more objectives to ensure the protection of natural resources. Regarding the conservation, appropriate use, and protection of existing and planned water sources, the resources and functions generally involve wellfields and their cones of influence, aquifers and recharge, groundwater contamination, water conservation and reuse, and wastewater discharges including septic tanks. Regarding wellfields and their cones of influence, the Plan fails to include an objective providing for the conservation, appropriate use, and protection of these water sources. CARE Policy 5.8 promises wellfield protection by 1993, and even then only through land development regulations. In the meantime, CARE Policy 5.8 provides for an interim land development regulation establishing a procedure for reviewing the impact of land development proposals on cones of influence. The policy fails even to suggest any standards to guide this procedural ordinance. The Plan contains no objectives addressing aquifers and their recharge. Stormwater Element Policy 5.6 prohibits new discharge of untreated stormwater to the Floridan aquifer, and existing stormwater facilities so discharging into the Floridan aquifer will be modified if economically feasible and physically practical. The remaining policies are largely ineffective in protecting natural aquifer recharge function. CARE Policy 6.13 suggests that, by 1992, a program will be implemented to improve groundwater recharge through stormwater management, and the program "may require" that predevelopment groundwater recharge volumes and rates be maintained postdevelopment. CARE Policy 5.2 notes the need for additional information regarding areas of relatively high natural recharge and allows the County to require developers to provide site-specific hydrogeological information. But the policy does not suggest what standards would be applied in making ensuing land use decisions on what it concedes is a "case-by-case" basis. CARE Policy 5.5 promises that, within a year after the completion of high-resolution mapping of areas of high aquifer recharge/contamination potential, the County will develop land development regulations and performance standards that "may include" such strategies as "control of land use types and densities, impervious surface limitations, and discharge to groundwater controls." Whatever regulation may eventually be imposed has no guidance from the Plan and will be relegated to the land development regulations. Similarly lacking regulatory provisions, Sewer Element Policy 7.3 promises that, within a year after completion of a pending study, the County will develop a "program" to identify areas with septic tanks with the potential to contaminate groundwater. CARE Policy 5.9 at least prohibits activities that would breach the confining beds of the Floridan aquifer. 31/ Though lacking as to the conservation, appropriate use, and protection of the recharge process, the Plan addresses more adequately groundwater. CARE Objective 6 is to conserve, reuse, and enhance groundwater and prevent excessive withdrawals from groundwater. CARE Objective 5 is to ensure compliance with state groundwater standards. Like CARE Policy 2.7, which applies to surface water protection, CARE Policy 5.11 says that the County will ask other agencies to develop septic tank siting criteria and then will add the criteria to County land development regulations. CARE Policy 5.15 indicates that the County will not support deep well injection of effluent unless the process will have no adverse effect upon existing or potential potable water aquifers. More effective, Sewer Element Objective 7 is to "[m]inimize the possibility of existing and future sources of wastewater adversely impacting groundwater." Also, Sewer Element Policy 7.1 requires septic tank users to connect to central sewer when it becomes available, in the absence of undue hardship. And FLUE Policy A-1.3 prohibits development dependent upon on-site sewage disposal systems, if the soils are unsuitable, unless the soils can be altered to comply with state law. Regarding water conservation, Sewer Element Objective 2 is to "protect and conserve the potable water resources, both groundwater and surface water" and expand recovered water reuse systems. As noted above, CARE Objective 6 requires the "conservation, reuse, and enhancement of groundwater and surface water supplies" to meet potable water demands. CARE Policies 6.2 and 6.4 require the use of recovered water under certain circumstances. FLUE Objective B-10 is to protect the agricultural water supply through regulations. As compared to whether the Plan is consistent with the criterion of one or more objectives to ensure the protection of natural resources, the question is closer as to whether the Plan is consistent with the criterion of one or more objectives conserving, appropriately using, and protecting water sources. The Hillsborough River is adequately protected. Groundwater is directly addressed, although aquifer recharge receives little direct attention. Wellfields and cones of influence are not directly addressed. However, on balance, the Plan is consistent with the criterion of one or more objectives conserving, appropriately using, and protecting the quality and quantity of current and projected water sources. As to Issue 19, however, the Plan is, to the exclusion of fair debate, not consistent with the criterion of one or more policies addressing implementation activities to protect water quality by restricting activities known to affect adversely the quality and quantity of identified water sources, including cones of influence, water recharge areas, and water wells. As discussed in the preceding paragraphs, the Plan does not address in any detail water wells, cones of influence, or water recharge areas. Although the Plan is nevertheless able to attain consistency with a criterion of an objective to protect, conserve, and appropriately use water sources, the Plan's relevant provisions are too vague to attain consistency with a criterion of policies to restrict activities affecting adversely cones of influence, water wells, and aquifer recharge areas. As to Issues 20-21, the Plan contains policies addressing implementation activities restricting activities known to affect adversely the survival of endangered and threatened wildlife and protecting native vegetative communities. It is unnecessary to consider the extent to which the Environmentally Sensitive Areas designation protects native vegetative communities and the habitat that some of these communities provide to endangered and threatened species. Other Plan provisions, including the density and intensity formulas and the upland forest density credit incentive, offer sufficient protection to these vegetative communities for the Plan to attain consistency with the criteria requiring specific policies. Coastal Hazards (Issues 22-23) As to Issue 22, the Plan is not, to the exclusion of fair debate, consistent with the criterion of an objective directing population concentrations away from coastal high hazard areas. Coastal Element Objective 6 is to "[r]estrict development of residential population centers" in the coastal high hazard area. CARE Objective 5 is to avoid loss of life and property by "minimizing land development" in coastal areas. As used in the Plan, "restrict" does not mean "prohibit." 32/ Restrict appears to mean merely regulate. And without standards to guide regulation, an objective to restrict, or minimize, is vague and undefined. The meaning of the criterion is clear and its importance is indisputable for one of the most hurricane vulnerable regions in the United States. Obviously, the County itself does not interpret Plan language to "restrict" and "minimize" development as synonymous with the criterion to "direct population concentrations away from." Allowing higher densities in the coastal high hazard area and new intense uses in vacant or agricultural areas within the coastal high hazard area, the Plan reflects the County's reasonable interpretation of Coastal Element Objective 6. The language of Objective 6 and the apparent interpretation of the language by the County mean that the County is required only to attempt to restrain the rate of growth in intensity and density in the coastal high hazard area. This is not tantamount to directing population concentrations away from this hazardous area. Plan provisions to maintain hurricane evacuation times may not direct population concentrations from the coastal high hazard area because evacuation times can be reduced by other means, such as road and bridge capacity improvements. The missing objective must reduce densities and labor-intensive and capital-intensive intensities in the coastal high hazard area. As to Issue 23, the Plan contains a policy identifying regulatory techniques for septic tanks as part of general hazard mitigation to reduce the exposure of life and property in part of the coastal area to natural hazards. Coastal Element Policy 6.7 prohibits, except in cases of "undue hardship," the use of septic tanks for new development in the coastal high hazard area. There is no similar provision governing septic tanks in the larger coastal area, of which the coastal high hazard area is only a part. However, Coastal Element Policy 1.3 requires the County to plan for the construction of regional wastewater treatment facilities for coastal areas planned for higher densities, thereby reducing the use of interim wastewater treatment alternatives. Coastal Element Policy 1.7 provides, where economically feasible, the County shall provide improved domestic wastewater treatment service to coastal areas where persistent water quality problems in Tampa Bay are attributable to malfunctioning septic tanks. Public Facilities (Issues 24-31) As to Issue 24, the Plan establishes peak hour level of service standards for state roads and explains why the adopted level of service standards for certain roads are below the generally applicable standards. As to Issue 25, the Plan appears to govern all action taken by Hillsborough County concerning development and development orders. The four major provisions concerning vesting are reasonable and do not extend unnecessarily the recognition of vested rights. As to Issue 26, the Plan contains a policy addressing programs and activities for the provision of public facilities for development authorized by development orders issued prior to the adoption of the Plan. CIE Policy 1.D.1 requires the County, in determining the scope of capital improvements needed for concurrency, to take into account "demand that is likely to occur from previously issued development orders as well as future growth." As to Issues 27 and 28, the Plan's allowance of pipelining road impact fees in connection with DRI development orders does not necessarily violate concurrency. The Regional Plan allows pipelining, although the County's Plan fails to incorporate the restrictive conditions set forth in Regional Plan Policy 19.8.14. CIE Policy 3.C.4 already provides for considerable flexibility in the selection of affected areas when making concurrency determinations for roads. Reasonable flexibility in identifying the range of roads impacted by a DRI and applying DRI road impact fees does not mean that the resulting developments will violate concurrency. Nonvested DRI's remain subject to the Plan, including the concurrency monitoring and enforcement provisions, and their failure to satisfy these provisions should result in the denial of a development order. As to Issue 29, the Plan contains policies providing for concurrency with respect to developments for which development orders were issued prior to the adoption of the Plan and new developments that are to be assessed a pro rata share of the costs of public facility improvements necessitated by the new development. As noted above, CIE Policy 1.D.1 takes into account the demand for public facilities from development orders issued before the adoption of the Plan. CIE Policy 2.B.1.a provides further that existing development shall pay for at least some of the capital improvements to reduce or eliminate existing deficiencies. CIE Objective 2 addresses the sources of funds for infrastructure, including "County revenues, development's proportionate share contributions, and grants or gift[s] from other source[s]." CIE Policy 2.B.2.a provides that the County will "allocate the cost of new public facilities on the basis of the benefits received by existing and future residents so that current residents will not subsidize an urban sprawl pattern of new development." As to Issue 30, the above-described Plan provisions, together with the five year schedule of capital improvements, establish funding mechanisms to correct existing deficiencies in required public facilities. As to Issue 31, the Plan is consistent with the requirement of financial feasibility based on the schedules of capital improvements and sources of revenues. The $52.4 million discrepancy between the cost of capital improvements in the Five Year Schedule and the Table of Costs and Revenues, which were prepared 18 months apart, does not prove lack of financial feasibility. In the absence of additional evidence, it is equally likely that the County displayed financial prudence in scaling back capital outlays to meet emerging revenue shortfalls. Urban Sprawl (Issues 32-35) As to Issue 32, the FLUM generally depicts urban and rural land uses with one major exception. To the exclusion of fair debate, there is no clear indication as to what land uses are permissible on lands designated Environmentally Sensitive Areas. As to Issue 33, the Plan contains provisions to discourage urban sprawl. The Plan generally provides for a viable mixture of residential and commercial uses in the concept underlying the Plan and the use of nodes. With the exception of the areas whose designations are not supported by the Data and Analysis, urban and rural land uses are separated. Regarding urban sprawl, various Plan provisions, such as FLUE Policies A- 7.6 and B-4.6, discourage urban sprawl and encourage the efficient use of land and provision of public facilities and the protection of natural resources and agriculture. As to Issue 34, the Plan contains provisions, regarding the protection of rural and agricultural lands, designating agricultural uses on the FLUM; setting objectives to conserve, appropriately use, and protect soils and natural vegetative communities; and setting policies to protect and conserve the natural functions of soils, wildlife habitats, rivers, bays, floodplains, harbors, and wetlands. The agricultural uses are primarily assigned to Rural designations, and the Rural designations generally specify densities that are low enough to promote agricultural uses. Plan provisions describe the extent to which agricultural uses may be located in Urban and Suburban designations. Some of the natural resources receive more protection than others, such as floodplains, but in general, and especially in the context of protecting rural and agricultural lands, the Plan is consistent with the cited criteria. Miscellaneous (Issues 35-36) As to Issue 35, the Plan contains provisions adequately addressing intergovernmental coordination. As to Issue 36, the Plan contains dual planning timeframes. One timeframe, as shown on the five year schedule of capital improvements, is five years, and the other, as shown on the FLUM, is 20 years. Minimum Criterion of Internal Consistency (Issues 37-38) As to Issue 37, the Plan is, to the exclusion of fair debate, internally inconsistent with respect to, on the one hand, Plan provisions to protect natural resources, which are identified as Conservation and Preservation Areas in the Plan, and, on the other hand, the failure to provide Environmentally Sensitive Areas with a designation that regulates land uses. The Plan is generally internally consistent with respect to the permitted densities and intensities and Plan provisions to protect natural resources. However, there are two major exceptions to this finding. First, if the stormwater level of service standard is not expanded in the manner described above, all designations allowing further development within the 100 year floodplain are, to the exclusion of fair debate, internally inconsistent with Plan provisions to protect natural resources, unless the development in the 100 year floodplain is prohibited from altering predevelopment drainage conditions in terms of rate, volume, quality, timing, or location of discharge. Second, even if the stormwater level of service standard is appropriately broadened, the densities and intensities determined, to the exclusion of fair debate, to be unsuitable or unsupported by the Data and Analysis are, to the exclusion of fair debate, internally inconsistent with Plan provisions to protect natural resources. This applies to the second and third clauses of Issue 37. The Plan is internally consistent with respect to the discouragement of urban sprawl and the adopted level of service standards for roads and the use of dual planning timeframes. As to Issue 38, the Plan is internally consistent with respect to the discouragement of urban sprawl and the Plan provisions requiring developers to pay a pro rata share of the cost of public facilities necessitated by their development. Minimum Criterion of Consistency with Regional Plan (Issue 39) As to Issue 39, the Plan is consistent, under either evidentiary standard, with the Regional Plan, construed as a whole, with respect to the Regional Plan's provisions requiring the discouragement of urban sprawl, identification of the coastal high hazard area, prohibition against publicly subsidized development in the coastal high hazard area (the Regional Plan lacks a provision requiring the direction of population away from the coastal high hazard area), adoption of road level of service standards, achievement of energy-efficient design of transportation facilities, enhancement of governmental efficiency, and attainment of compliance with national air quality standards. With respect to the Regional Plan's provisions for the protection of environmentally sensitive areas, the Plan is consistent in some respects and, to the exclusion of fair debate, inconsistent in other respects. The inconsistencies have all been addressed above in connection with inconsistencies with other criteria of Chapter 9J-5. These inconsistencies are the inadequate stormwater level of service standard, which conflicts with Regional Plan Goal 8.7; in the absence of the expanded stormwater level of service standard discussed above, the inadequate protection of the 100 year floodplain, which conflicts with Regional Plan Goals 8.10, 10.4, and 10.5 and related policies; the inadequate protection extended to public supply potable water wellfields and their cones of influence and aquifer recharge, which conflicts with Regional Plan Goals 8.1 and 8.5 and related policies. Minimum Criterion of Consistency with State Plan (Issues 40-41) As to Issue 40, the Plan is consistent, under either evidentiary standard, with the State Plan, construed as a whole, with respect to the State Plan's provisions as to the discouragement of urban sprawl, promotion of agricultural activities that are compatible with the protection of natural resources, reduction of the cost of housing construction by the elimination of costly regulatory practices, coordination of transportation improvements to enhance system efficiency and minimize environmental impacts, assurance that transportation improvements are consistent with the maintenance of optimum air quality and efficient use of energy and transportation modes, elimination of regulatory activities not tied to the needs of specific public and natural resource protection, reduction of the need for new power plants by encouraging end-use energy efficiency, and attainment of compliance with all national air quality standards. With respect to the State Plan's provisions as to the elimination of the discharge of inadequately treated stormwater runoff and wastewater into the waters of the state, the Plan is consistent with respect to wastewater, but, to the exclusion of fair debate, inconsistent with respect to stormwater due to the above-noted deficiencies concerning the stormwater level of service standard. As to Issue 41, the Plan is consistent, under either evidentiary standard, with the State Plan, construed as a whole, with respect to the State Plan's provisions as to the development of a system of incentives and disincentives to encourage a separation of urban and rural uses while protecting water supplies, resource development, and fish and wildlife habitats (notwithstanding general shortcomings regarding the protection of water supplies and specific unsuitable designations jeopardizing potentially significant wildlife habitat), promotion of agriculture, provision of incentives for developing land so as to maximize the uses of existing public facilities, allocation of the costs of new public facilities on the basis of the benefits received by existing and future residents, and assurance that the transportation system provides Florida's residents and visitors with timely and efficient access to services, jobs, markets, and attractions. With respect to the State Plan's provisions as to the direction of growth into areas that already have or will soon have the land and water resources, fiscal abilities, and service capacity to accommodate growth in an environmentally acceptable manner, the Plan is generally consistent. However, the Plan is inconsistent with this provision of the State Plan, to the exclusion of fair debate, with respect to those five areas for which unsuitable designations were demonstrated to the exclusion of fair debate, and the Plan is inconsistent with this provision of the State Plan, by a mere preponderance of the evidence, with respect to those six areas for which unsuitable designations were demonstrated by a mere preponderance of the evidence..
Recommendation 317
Findings Of Fact The Parties Coniglio through a profit sharing plan owns property in Sumter County which is affected by the plan adoption at issue here. He submitted written and oral comments, objections and recommendations during the plan review and adoption proceedings. He is a person affected by the plan adoption. Similarly Pownall, Cherry, Jones, the Turners and the Dixons as property owners and individuals who submitted written and oral comments, objections and recommendations during the plan review and adoption proceedings are affected persons. Moreover, Pownall, Cherry, Jones and Turner reside in Sumter County. The Dixons own and operate mining sites within Sumter County. Their residence and business interests in Sumter County create additional bases for determining that those individuals are affected persons. The department is the state land planning agency which has the responsibility of reviewing comprehensive plans in accordance with Chapter 163, Part II, Florida Statutes. That function was performed on this occasion associated with the comprehensive plan submitted by the county. The county is a local government required to adopt a comprehensive plan in accordance with Chapter 163, Part II, Florida Statutes. This county is a non-coastal county located in central Florida which is bordered by Citrus, Hernando, and Pasco counties to its west, Polk county to the south, Marion county to the north and Lake county to the east. It has within its boundaries five incorporated municipalities, Bushnell, Center Hill, Coleman, Webster and Wildwood. The unincorporated area of the county include approximately 350,000 acres. The 1991 unincorporated population of the county was 25,030 and was projected to increase to 30,773 within the ten-year planning horizon contemplated by the plan, in the year 2001. Plan Preparation, Adoption and Approval On March 27, 1991, the county submitted its proposed plan to the department for review as contemplated by Section 163.3184(3)(a), Florida Statutes. By such submission the county did not commit itself to the terms found within the proposed plan. Chapter 163, Part II, contemplates that the text within the proposed plan may change through the review, adoption and approval process that follows that submission. As anticipated by Section 163.3184(4), Florida Statutes, the department forwarded copies of the proposed plan to other agencies for review. The department in accordance with Section 163.3184(6), Florida Statutes, took into account the comments received from the other governmental agencies and prepared and transmitted its report of written objections, recommendations and comments (the ORC). The transmittal date for the ORC was July 2, 1991. The purpose of the ORC was to acquaint the county in detail concerning the department's objections, recommendations and comments. It was left over to the county to decide whether the suggested modifications recommended by the department would be adopted in an effort at establishing a plan which would be found "in compliance". The county considered the ORC report, to include the recommendations and made revisions to the text in the proposed plan when it adopted its plan on February 3, 1992. The adopted plan was transmitted to the department on February 28, 1992, for final review. In preparing and adopting the plan the county gave appropriate notice and provided the opportunity for public participation envisioned by law. On March 31, 1992, the department's secretary determined that the adopted plan met the requirements set forth in Chapter 163, Part II, Florida Statutes, and Rule 9J-5, Florida Administrative Code. Thus, the plan was found "in compliance". The determination finding the plan "in compliance" was memorialized through a memorandum dated March 24, 1992. On April 9, 1992, the department gave notice of its intent to find the plan "in compliance". The Coniglio Petition The Coniglio profit sharing plan owns 19.44 acres in Sumter County which Coniglio claims should be classified on the future land use map to the plan as industrial property not commercial property as the plan now describes. In particular, Coniglio asserts that the 19.44 acres that were designated as commercial was not by a decision based upon a survey, studies or data concerning that parcel and that the designation as commercial is inconsistent with the character of other parcels found within the immediate area. Coniglio argues that the analysis that was performed in classifying the property for designation in the future land use map has resulted in a land use which does not allow the best use or highest economic use of the subject property. This 19.44 acres is depicted on map VII-19 and is located to the north and east of the City of Wildwood. There is commercial acreage in the plan immediately adjacent to the property in question, all of which is part of a triangular shaped piece of land. There are present commercial uses adjacent to the property. Generally, the triangular shaped property, to include the 19.44 acres, is surrounded by other properties whose classification is municipal, industrial and rural residential. The property is further detailed in a sketch which is Respondent's Exhibit No. 1 and a Joint Exhibit No. 2. The property is south of County Road 462, west of the Seaboard Coastline Railroad line and east of U.S. 301. The southern boundary of the property is adjacent to an overpass which is 40 to 45 feet high. Coniglio's property has its longest axis fronting the railroad, contact with County Road 462 but no immediate contact with U.S. 301. The railroad line which is adjacent to the parcel is a principal track for the Seaboard Coastline Railroad carrying north/south traffic between Jacksonville and Tampa and Jacksonville and Orlando. The track splits in the City of Wildwood with some traffic going to Tampa and some traffic going to Orlando. A manufacturing plant is located east of the railroad in the vicinity where the subject property is found. This plant is Florida Corrugated which makes corrugated boxes. West of U.S. 301 in the vicinity of the property in question is found a company known as AST that manufactures steel pipes. In the vicinity of the property in question at the junction of County Road 462 and U.S. 301 a business is located known as McCormick Electric. In the immediate vicinity of the property is also found a convenience store and what previously was a motel that has been turned into rental units. Northeast of the intersection of County Road 462 and the railroad is property owned by Florida Power Corporation which is classified as industrial. The corrugated box plant is also on property classified as industrial, again referring to classifications in the future land use map. The AST property where stainless steel pipes are manufactured is on a parcel which is classified as industrial on the future land use map. As stated, the parcel in question is part of a larger triangular shaped parcel, that had been the topic for establishing an industrial park. In the proposed plan the subject parcel, a part of the larger parcel, had been classified as industrial. That designation of the parcel in the proposed plan was through the future land use map. Arrangements were made to provide water service to the industrial park. At present that service is available at the property in question. Arrangements, though not consummated, have also been made to extend sewer service from the City of Wildwood to the subject parcel. In anticipation of the use of the subject property under an industrial classification, Coniglio expended large sums of money. That included $85,000 for a railroad spur and in addition; $12,000 for track extensions, $8,500 for a water line and contribution of right-of-way for water service, sewer service and a road. All this effort was made by Coniglio's in the anticipation of the opening of the industrial park. Sumter County had been involved in the industrial park project through the process of an application to the Florida Department of Commerce seeking appropriation of $96,000 to construct a road associated with the industrial park. The county administered construction of the road and it is that road which Coniglio had donated right-of-way for. The railroad spur, water and sewer services would serve parcels other than the subject parcel owned by Coniglio. The county in preparing its proposed plan had worked with the Sumter County Development Council and other persons in the community in establishing the location for commercial and industrial classifications. One reason for designating the parcel in question as industrial was based upon its proximity to the railroad and as part of the overall industrial park which was being projected in the planning efforts by the county, the development council and others. Chemical Development Corporation appeared before the Sumter County Board of Adjustments to seek approval to operate its business of storage and treatment of hazardous waste on the subject property. The need to appear before the Sumter County Board of Adjustments, which operates independent of Sumter County and its governing board, the Sumter County Commissioners, was to gain a special exception to operate that type business in the county. A special exception needed to be granted by the Sumter County Board of Adjustments because the business to be engaged in involved hazardous waste. The decision by the Sumter County Board of Adjustments was upon a vote of 8 to 2 to grant the special exception following visitation to a plant similar to those activities the applicant for special exception hoped to be engaged in. That approval was granted in May, 1991 by the Sumter County Board of Adjustments. Following that approval the plan was adopted on February 3, 1992, and it changed the classification from industrial in the proposed plan to commercial in the adopted plan. Chemical Development Corporation the prospective tenant for the parcel in question was not granted an occupational license by the county and could not proceed with its operations. One of the enterprises that located in the proposed industrial park was Dairyman's Supply. It had completed construction and was ready for business before the plan was adopted. It began its operations in July, 1991. The decision to change the designation in the parcel in question from industrial to commercial was upon the recommendation of Glen Nelson, Director of Public Services for Sumter County. Among other reasons for the change, according to Nelson, was to thwart the purposes of Chemical Development Corporation in recognition that the change in classification from industrial to commercial would prohibit activities by that company. Notwithstanding the decision by the Sumter County Board of Adjustments to grant the special exception, that prohibition existed because industrial zoning was necessary for the would be tenant to proceed with its business at the site in question. By way of history, following the decision by the Sumter County Board of Adjustments to grant the special exception there was some opposition to the activities envisioned by the Chemical Development Corporation. That is to say, the establishment of a hazardous waste treatment facility. This community opposition predated the recommendation by Mr. Nelson, the decision by the Sumter County Commissioners to reject the application for an occupational license issued from the county, and the determination to present the subject parcel on the future land use map in the adopted plan as a commercial classification. The principal planner whom the county relied upon in preparing its plan was Jack Sullivan. He did not participate in the decision to change the subject parcel from industrial to commercial as reflected on the future land use map in the adopted plan. As explained by Mr. Nelson, other reasons for changing the plan related to the overall attempt by the county to meet perceived needs for balancing the amount of commercial and industrial acres within its adopted plan. To that end the March, 1991, proposed plan had contained approximately 200 acres on State Road 44 east of Wildwood designated as commercial that had been put there at the request of the Sumter County Development Council based upon the Council's discussions with a company that was considering the establishment of a distribution center. Between the time the proposed plan had been transmitted and the plan adoption took place the potential project located in Pasco County or some county south of Sumter County. Therefore, as stated by Mr. Nelson, the commercial designation was no longer needed. The commercial designation at that site changed to rural residential in the plan as adopted. To compensate for the loss of commercial on that 200 acres Mr. Nelson requested that an approximately 40 acre tract of land adjacent to Wildwood on the east side of State Road 44 be placed in the adopted plan as commercial together with 30 to 35 acres including the subject parcel. In making his recommendation to place the subject parcel as commercial Mr. Nelson was aware of those industrial activities in the general area surrounding the parcel in question that have been described. Mr. Nelson made his recommendation for change in the classification one or two months before the February 3, 1992 plan adoption. At the plan adoption hearing on February 3, 1992, Mr. Nelson indicated that the reason for changing the classification for the subject parcel was that the existing uses there were commercial and that the future land use map should reflect that reality. At the hearing no mention was made, by the provision of details, that the reason for changing was to compensate for the loss of the aforementioned 200 acres of commercial acres between the time of the proposed plan and the adoption of the plan on February 3, 1992. As Mr. Nelson explains, the action by the Sumter County Board of Adjustments in granting a special use exception to Chemical Development Corporation did not preclude the necessity to acquire the proper zoning on the parcel before proceeding with the business. That zoning had to be industrial and not commercial. In the more ordinary course the industrial zoning would have been sought first before the Sumter County Commissioners and the Sumter County Board of Adjustments would then have considered the special use. In this instance the Board of Adjustments acted first and the county made its determination second. Bill Keedy who sells industrial real estate expressed the opinion that the 19.44 acres would not be saleable as commercial real estate at least in the foreseeable future. Jim Morton who sells commercial, residential and agricultural properties expressed the opinion that the parcel in question has limited commercial value. Willard Peeples who owns a number of commercial rental properties did not believe that the subject property had commercial value due to limited access to road frontage. None of these individuals are certified in real estate appraisal. Mr. Keedy pointed out that the majority of commercial activity in the Wildwood area is in the middle of the town. Mr. Peeples observed that the commercial activity in Wildwood was located south of the city hall and on U.S. 301 and east and west on State Road 44. Mr. Morton expressed the belief that the highest and best use of the subject property was industrial. Mr. Keedy expressed the belief that an industrial use was promoted by the fact that the property on its east side was bordered by the railroad track. Mr. Nelson in making his recommendation to classify the property in question as commercial made that choice outside any experience in selling, owning or dealing in commercial property. There had been no commercial development north of the City Hall in Wildwood in the preceding ten years prior to hearing. Tony Arrant is an expert in land use planning employed by the department. He had significant involvement in the plan review performed by the department. He pointed out that the department's concerns about the plan and its land use classifications were based upon distribution of land uses throughout the entire county. The ORC did not offer objections to classification of any particular parcel. In the ORC there had been objection as to the extent and distribution of land uses based upon the belief that inadequate data and analysis had been provided to support the extent and distribution of land use. Moreover, the ORC found the plan in its proposed form deferred the establishment of densities and intensities for some land use categories within the plan. The ORC expressed concern about data and analysis supporting the future land use map. Therefore, objection was directed to the future land use map. However, the impression of the proposed plan was not based upon a policy to avoid commenting on specific parcels when occasion arose for such criticism. Mr. Arrant did not perceive that a change in classification of land use between the time that the proposed plan was reviewed by the department and the adoption of a plan was an irregular outcome. In fact, that possibility is a normal expectation. Mr. Arrant recalls the explanation by Mr. Nelson on February 3, 1992, when the plan was adopted concerning the change from the proposed plan to the adopted plan affecting the parcel in question, to have been based upon existing circumstances, existing land uses at that place and a movement in the distribution of parcels in the overall county associated with commercial and industrial classifications. Mr. Arrant pointed out, in the final perception he held about the adopted plan, that if the suitability analysis provided would support a commercial classification, that is to say, that it was equally suitable for commercial development or industrial development and there was data and analysis providing the need and extent of distribution for the classification, then it is the local government's choice to determine which site will be designated commercial and which site will be designated industrial. With that in mind, Mr. Arrant found no reason to take issue with the county in its commercial classification for the subject parcel. Mr. Arrant in his knowledge of the parcel in question found no wildlife habitat, wetlands, topographical, geographical or geophysical constraints which would limit the use of this property as commercial or industrial. Consequently, the choice in classification was left to the local government. Having in mind the facts previously found, it is recognized that the reasons for changing the land use classification on the subject parcel from industrial to commercial had a political component, stopping Chemical Development Corporation from doing business in Sumter County, unrelated to appropriate land use planning. Nonetheless other reasons the county gave for changing the classification from industrial to commercial when compared to the criticisms directed to the classification do not convince, to the exclusion of fair debate, that the county should be required to change the plan to reflect an industrial classification for the parcel in question. This finding is supported by review directed to the overall plan for land use classification within the county which is supported by appropriate data and analysis. Finally, Coniglio's expenditures associated with this parcel are not an appropriate topic for disposition in this case. Mining Policy 1.9.1 at pages VII-48 and 49 states the following in its preamble: Mining uses shall be provided for in areas designated as agricultural on the Future Land Use Map and shall be permitted upon approval of a conditional use permit and approval of an operating permit pursuant to a mining site plan as provided for in the Land Development Regulations. It was not proven to the exclusion of fair debate, in fact, no proof was offered to suggest that the approval of a conditional use permit as opposed to a zoning permit should be the proper approach in describing this policy. Consequently, that allegation concerning the county's policy choice in the mining element is without merit. Policy 1.9.1 at page VII-49 goes on to describe the guidelines for controlling land allocation for mining purposes where it states: The following guidelines shall be used to control land allocation for mining: Allocation of mining land use shall be based on a projected average need of 100 acres per year or a total of 1,000 acres during the ten year time period of the Plan and may be permitted pursuant to the goals, objectives and policies of the Plan as needed up to 1,000 acres. Allocation of mining land use above this projected need shall require a Plan amendment. For purposes of determining the amount of mining land permitted, the Board of County Commissioners shall issue a finding with each operating permit that clearly delineates the amount of land dedicated to the actual mined area plus ancillary uses such as processing plants, overburden piles, roads, administrative offices and other buildings necessary for the actual mining of land. Areas allocated for wetlands, buffers and other lands required in the application to insure compatibility with adjacent land uses or protection of resources shall not be counted toward the ten-year allocation of land for mining purposes. To ensure that an equitable balance among applicants is maintained in allocation of mining land, the following criteria shall apply: Within each calendar year, no individual mining operation shall receive more than 10% of the ten year allocation; No individual mining operation shall receive more than 25% of the ten year allocation within any five year period; Any land allocation requirement for mining purposes larger than those indicated in 1-2 above shall require a plan amendment. The calculation concerning the number of acres per year and total acreage allocated during the ten year review is based upon data collected from the Withlacoochee Regional Planning Council field survey of 1975 incorporated into the county's 1976 comprehensive plan which showed 2190 acres in mining effective 1975. That constitutes the base point for calculation and is related to a further data point in 1986 taken from the county tax assessor's data which established that 3082 mining acres existed in the county upon that date. The use of the data points is described in the data and analysis at page VII-104 where it states: The 1991 acreage was assumed to be the same as the 1986 analysis. The following methodology was used to calculate mining growth to the year 2001: Assume an additional 100 acres per year from 1986-2001 including buffer area. This estimate is based on 2,190 acres in mining in 1976 (1976 Comprehensive Plan) and 3,082 acres in 1986 (See Appendix A). This yields an average of 89 acres per year for the ten year period. This has been rounded upward to 100 acres per year to allow for market fluctuations. Mining shall be a permitted activity in agriculture districts. Applicants shall secure a conditional use permit to mine in agriculture areas; then a mining operating permit will be secured to delineate the exact location of the mined area. 100 acres/year X 15 years = 1,500 acres. 3. 3,082 + 1,500 = 4,582 acres mining in 2001. The goals and policies concerning allocation of mining acreage is clearly based upon appropriate data. The methodology utilized for data collection was appropriately applied and the use of the methodology to derive the allocation was a professionally acceptable methodology. The Petitioners challenge to the county's treatment of the future land use element related to mining would substitute a methodology which examines the amount of land devoted specifically to the mining activity as contrasted with the methodology here which takes into account the mined areas plus ancillary uses such as processing plants, overburden piles, roads, administrative offices and other buildings. In addition, the methodology that the challengers would employ does not take into account that the 100 acre per year allocation excludes wetlands, buffers, and other land required to ensure compatibility with adjacent land uses and protection of resources. This attempt at comparison of methodologies is not allowed in the compliance review. In criticizing the data supporting the allocation process, the challengers question whether that data is the best available existing data. They have failed to prove beyond fair debate that the data used in the plan element is not the best available existing data. The decision to exclude areas allocated for wetlands, buffers and other lands required to ensure compatibility with adjacent land uses and to protect resources from the mining acreage count is not part of the allocation methodology. It is an appropriate planning decision in protecting wetlands and other resources and ensuring compatibility with adjacent land uses. In further describing the manner in which the county will ensure compatibility of the mining uses with adjacent land uses and the preservation of natural resources, Policy 1.9.2 at page VII-49 states: Sumter County shall insure compatibility of mining uses with adjacent land uses and preservation of natural resources through the following requirements: Sumter County shall regulate mining to control buffer areas, maintenance of the mining area, groundwater withdrawals, unpermitted deposition of materials, soil stabilization, disturbance of wetlands, noise, vibration, air quality, security and reclamation of mined lands pursuant to Sumter County Ordinance 90-12(1990). Blasting shall be regulated pursuant to Sumter County Ordinance 81-11(1981). All mining lands permitted pursuant to these policies must be adjacent to existing legally permitted mine sites with no intervening non-compatible uses. Lands proposed for mining that are not adjacent to an existing permitted mine site shall require a plan amendment prior to approval of zoning and the mining plan. Enforcement of mining regulations shall be funded through operating permit fees levied against mining operators. The Petitioners challenging the mining element take issue with the term "adjacent" found at Policy 1.9.2c. They note that Sumter County Ordinance No. 90-12(1990), the mining ordinance, uses the term "contiguous". They argue that this difference in terminology between the ordinance and the plan describes an inconsistency between that ordinance and the plan. Moreover, the challengers claim that there is an internal inconsistency between Policy 1.9.2 and Policy within the conservation element. Policy 1.7.1 in the conservation element at pages III-13 and 14 states: Sumter County shall insure compatibility of mining uses with adjacent land uses and preservation of natural resources through the following requirements: Sumter County shall regulate mining activities to control buffer areas, maintenance of the mining area, groundwater withdrawals, unpermitted deposition of materials, soil stabilization, disturbance of wetlands, noise, vibration, air quality, security and reclamation of mined lands pursuant to Sumter County Ordinance 90-12 (1990). Blasting shall be regulated pursuant to Sumter County Ordinance 81-11 (1981). All mining lands permitted pursuant to these policies must be adjacent to existing legally permitted mine sites with no intervening non-compatible uses. Lands proposed for mining that are not contiguous to an existing permitted mine site shall require a plan amendment prior to approval of zoning and the mining plan. Enforcement of mining regulations shall be funded through operating permit fees levied against mining operators. The challengers claim that Policy 1.9.2 is inconsistent with the Land Development Code for Sumter County, Chapter 13 as it discusses mining activities. Finally, the challengers take issue with the decision to change policy 1.9.2 in its use of the word "contiguous" in a plan draft and the final decision to use the word "adjacent". In Webster's New World Dictionary the word "adjacent" is defined as: near or close to something; adjoining, joining. "Contiguous" is defined as: 1. in physical contact; touching. 2. near; adjoining. To the extent that the county chose to change the previous terminology in policy 1.9.2 found within the earlier draft from the word "contiguous" to the word "adjacent" in the adopted plan, there is no impropriety in that choice. Such changes are anticipated as being involved in the process. The plan as adopted in its use of the terminology "contiguous" or "adjacent" in the conservation and future land use elements as they discuss mining activities is not an internal inconsistency. The terms adjacent and contiguous taken in context are the same. The use of those terms affords no greater nor lesser protection for the benefit of adjacent land owners or in the protection of resources. Treatment of the mining issue within Sumter County Ordinance 90-12 and the Land Development Code for Sumter County, Chapter 13, when compared to the plan does not point to some inconsistency in using the terms "contiguous" and "adjacent". On balance the treatment afforded the mining element within the plan has adequately responded to the need for proper allocation for future land use compatible with adjacent land uses and the protection of resources.
Recommendation Upon consideration of the facts found and the conclusions of law reached, it is, RECOMMENDED: That a final order be entered which finds the plan for Sumter County to be "in compliance" and dismisses the petitions. DONE and ENTERED this 26th day of February, 1993, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of February, 1993. APPENDIX CASE NO. 92-2683GM The following discussion is given concerning the proposed fact finding of the parties: Coniglio: The proposed facts are accepted with the exception that Paragraph 4 is contrary to facts found. and Paragraph (w) is not necessary to the resolution of the dispute. Department: Paragraphs 1-12 are subordinate to facts found. Paragraph 13 is contrary to the facts in its suggestion that there is a lack of significant industrial activity in the area of the subject parcel. Otherwise, that paragraph is subordinate to facts found. Paragraphs 14 through 18 are subordinate to facts found with the exception that the latter sentence in Paragraph 18 is not accepted in its suggestion that the allegation of political considerations has not been proven. Paragraphs 19 and 20 constitute legal argument. Paragraphs 21 through 23 are subordinate to facts found. Paragraphs 24 through 27 are subordinate to facts found. Paragraphs 28 and 29 constitute conclusions of law. Paragraphs 30 and 31 are subordinate to facts found. Paragraphs 32 and 33 constitute conclusions of law. Paragraph 34 is subordinate to facts found. Paragraph 35 constitutes conclusions of law. Paragraphs 36 through 40 are subordinate to facts found. Paragraph 41 is not necessary to the resolution of the dispute. Paragraph 42 is subordinate to facts found. Pownall, Cherry, Jones and Turner: Paragraph 1 is contrary to facts found in its suggestion that appropriate notice and opportunity for public participation was not afforded. Paragraph 2 through 4 are contrary to facts found. The County and Intervenors: Paragraphs 1 through 7 are subordinate to facts found. Paragraph 8 constitutes conclusions of law. Paragraphs 9 through 13 are subordinate to facts found. Paragraphs 14 and 15 constitute conclusions of law. Paragraphs 17 through 22 are subordinate to facts found. Paragraph 23 constitutes conclusions of law. Paragraphs 24 and 25 are subordinate to facts found. Paragraph 26 constitutes conclusions of law. Paragraphs 27 through 31 are subordinate to facts found. Paragraphs 32 and 33 constitute conclusions of law. Paragraphs 34 through 39 are subordinate to facts found. COPIES FURNISHED: Michael P. Donaldson, Esquire Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 C. John Coniglio, Esquire P. O. Box 1119 Wildwood, Florida 34785 Bill Pownall 202 W. Noble Street Bushnell, Florida 33513 Randall N. Thornton, Esquire P. O. Box 58 Lake Panasoffkee, Florida 33538 Theodore R. Turner Nancy Turner Carousel Farms Route 1 Box 66T Post Office Box 1745 Bushnell, Florida 33513 Frances J. Cherry 3404 C R 656 Webster, Florida 33597 Kenneth L. Jones 3404 CR 656 Webster, Florida 33597 Steven J. Richey, Esquire P.O. Box 492460 Leesburg, Florida 34749-2460 Felix M. Adams, Esquire 236 North Main Street Bushnell, Florida 33513 Randal M. Thornton, Esquire Post Office Box 58 Lake Pnasoffkee, Florida 33538 Linda Loomis Shelley, Secretary Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100
The Issue The issues in this case are (1) whether the City of Panama City's (the City) Small Scale Comprehensive Plan Amendment No. 04-20S adopted by Ordinance No. 1985 (the Plan Amendment) is "in compliance," as that term is defined by Section 163.3184(1)(b), Florida Statutes, and (2) whether the petition challenging the Plan Amendment should be dismissed as untimely.
Findings Of Fact The Parties Robert E. Moore owns a home and resides at 1310 Kristanna Drive, Panama City, Florida. The northwestern property line of Mr. Moore's home is adjacent to the northeastern corner of the Property. JE 7; PE 98-B at RM.2 There is an approximate 100-foot-wide Bay County maintained canal or drainage ditch (canal) that forms the northern boundary of the Property, see Endnote 1 and PE 50 at 7, which runs in an east-to-west direction at the northern portion of his home. This canal eventually leads to North Bay to the west.3 Goose Bayou is located south of the Property. Mr. Moore taught respiratory care at Gulf Coast Community College for approximately 23 years and is retired. His residence was affected by a hurricane which passed through the area in September 2004. He noticed water appearing half-way up his driveway, which is not on the canal. He is concerned with the placement of additional homes in this area in light of his experience with the water level after the recent storm event. (Generally, Mr. Moore stated that there is a two- foot difference between low and high tide in this area. T 133, 137.) Mr. Moore, as well as the other Petitioners, made oral and written comments to the City Commission during the Plan Amendment adoption hearings. See City's Unilateral Pre-Hearing Stipulation at 5, paragraph E.4.; T 213. The St. Andrews Bay Resource Management Association (RMA) was established in 1986 and is a citizen's organization devoted to the preservation of the quality of St. Andrews Bay and its surrounding ecosystems. T 194. (St. Andrews Bay is a larger body of water which includes North and West Bay and Goose Bayou. See generally JE 12, Map 1.) The RMA has approximately 100 members. The RMA uses, but does not own, an office on the Panama City Marine Institute campus located within the City. The RMA occasionally conducts seminars or conferences and offers several programs for citizens, e.g., sea turtle nest watch, a water sampling program (Baywatch), and a sea grass watch program. The RMA meets every month except during the summer. T 195-196. The RMA opposes the Plan Amendment, in part, because of concerns with the effect of development on what Ms. Shaffer characterized as the "pine islands." Linda Anne Yori owns and resides in a house at 908 Ashwood Circle, Panama City, Florida, which is "just off Kristanna" Drive and to the east. See PE 98-C at the blue X. She teaches middle school science at a local public school. She has observed the Property, and generally described the Property, and vacant property to the north, as "upland hammock with salt marsh." T 209. In general, Ms. Yori opposes the Plan Amendment because she "believe[d] the environmental impact would be too great." Mary Rose Smith owns and resides in a house on Ashwood Circle, Panama City, Florida, two houses away from Ms. Yori's residence. Ms. Smith regularly jogs throughout the neighborhood. She believed that there are approximately 400 homes in Candlewick Acres and six vacant lots remaining. T 214- 215. As a result of recent hurricanes in the area, she observed flooding approximately half-a-mile upland along Kristanna Drive from the west-end to the east (half a mile to the turn off to Ashwood). PE 98-D at the blue 1/2 designation and blue line. While she cannot say for certain where the water came from, she believed the water "came from the bay or the bayou." T 220. The Bay County Audubon Society (BCAS) conducts membership and board meetings within the City limits and also owns a piece of property in the City. BCAS has approximately 400 members. Members live within the City. BCAS is concerned with the environment and with "the density of the proposed development" and "access to the pine islands." T 409-411. The City is the local government unit responsible for approving the Plan Amendment at issue in this proceeding. § 163.3187(1)(c), Fla. Stat. The Application, Review, and Adoption of the Plan Amendment On or about May 11, 2004, James H. Slonina, P.E., the president of Panhandle Engineering, Inc., filed an application on behalf of Robert H. and Barbara B. Hansman, requesting the City to annex "approximately 9.9 acres including lots, paved roadways and bridged drives" and further requested a land use designation to allow proposed residential development." The Property, see Endnote 1, is designated on a Bay County parcel map. A flood zone map is also included, but lacks clarity. The Property is vacant. JE 13. The purpose of the annexation and request for land use designation "is to accommodate the development of a 13+/- lot single-family residential waterfront development adjacent to North Shore Subdivisions." The application also stated: To support the residential home sites, there are adequate adjacent public roadways and utilities. Due to the unique physical configuration of the property, traditional RLD lot standards may not [sic] applicable. While we would prefer to pursue an RLD-1 designation, the application is submitted contingent upon confirmation of an appropriate land use designation and an approval of the proposed project. If another course of action is available, which would allow for the development of 13+/- single-family residential lots on 9.9 acres, please advise. JE 13. (It is represented throughout this record that the land use designation is requested for approximately 6.8 acres rather that approximately 9.9 acres. See, e.g., JE 7 at 1; JE 11 at 12-13.) The application was reviewed, in part, by Mr. Thomasson. JE 7. The staff report4 dated July 30, 2004, stated that the request is to amend the City's FLUM from Conservation (as previously designated by Bay County) to RLD with a Zoning District classification of RLD-1. (The staff report referred to several permitted uses under RLD-1. JE 7 at 2. The permitted uses for RLD-1 are those contained in the City's "Comprehensive Planning and Land Development Regulation Code (LDRC)" at section 4-6.1.2.a. JE 4 at IV:8-9. However, the propriety of the RLD-1 Zoning District classification for the Property is not at issue in this proceeding. T 266.) The staff report also stated that the Property "is currently zoned conservation, abuts property to the North that is designated conservation Land Use category in the County and is just North of an existing Special Conservation Treatment Zone," which is indicated on a map on page 1 of the staff report. JE 7 at 1. The staff report stated that "[w]ater and sewer infrastructure and other urban services are available to this property." See T 286-287, 301-303, 307-308; JE 7 at 1. Under the background section, it is stated that "[t]he property has been seen as environmentally significant and has been the object of an effort to purchase for perpetual protection by a local land trust organization. It is adjacent to an existing development to the East." Id. The Plan provides that an RLD land use district "is intended to provide areas for the preservation of development of low-density neighborhoods consisting of single-family dwelling units on individual lots" with a density of "[n]o more than five dwelling units per acre." The allowed intensity is "[n]o more than 40% lot coverage as determined by dividing the impervious areas by the gross area of the site or lot." JE 3 at 1-2. The staff report contained findings of fact with citations to the Plan, including the Future Land Use Element, the Coastal Management Element, and the Conservation Element. References to the LDRC are also provided. See also T 285-311, 315-317, 320-321; JE 7 at 2-3. Thereafter, specific findings are made: Staff finds that this property, as a part of the St. Andrews estuary, serves as a breeding, nursery, feeding and refuge are for numerous marine creatures, birds and upland wildlife. The three pine and oak hammacks [sic] are a few of a rare estuarian resource. The marsh throughout the area serves as home for seagrass and other marine organisms that are integral with the biodiversity of the estuary. There also exists a [sic] archaeological sites [sic] consisting of an ancient Indian midden that has already been classified by the Director of the Florida State Division of Historical Resources as deservant [sic] of mitigation and potentially eligible for the National Historic Registry (see attached documentation). The site overall has a biotic community of nearly 90% of it [sic] total area. Staff findings are that this proposed Land Use Amendment is inconsistent with the above listed mandates of the Comp Plan. Staff also finds that the proposed Land Use is inconsistent with the LDR Code, in that it is not in harmony with the Comp Plan (Subsection 2-5.5.6.e. above), as well as the requirements of the environmental protection standards of Section 5-5. This decision hinges on the whether the City intends to enforce it's [sic] environmental protection standards of the Comp Plan and the LDR Code and if the site is seen as environmentally significant. JE 7 at 4 (italics in original). Ultimately, staff recommended approval only with the following conditions: 1.) that the fullness of the subject property be designated as a Conservation Special Treatment Zone [CSTZ][5] and that the pine and oak hammacks [sic](as referred to as "Pine Islands" in the Bay County Comp Plan) are prohibited from being developed; and 2.) that the area of the subject property that is beyond the mean high tide of the mainland portion, which specifically means the marshes/wetlands and the oak and pine hammacks [sic], shall be placed in a conservation easement and dedicated to either the City, or a third-party land trust or conservancy. JE 7 at 4. (Mr. Hammons, the City Manager, disagreed with the staff report, in part, because there was no data to support several findings. T 119-124.) On August 9, 2004, the Planning Board of Panama City met in regular session to consider the application. The request was to approve a small scale land use amendment to the FLUM of the Plan from Conservation (under the Bay County Comprehensive Plan) to RLD with a zoning classification of RLD-1 for the Property. JE 11 at 2. But see Finding of Fact 15. Mr. Fred Webb and Dr. Frasier Bingham were present on behalf of the applicant. Mr. Webb advised that the Bingham's and the Webb's owned the property which consisted of approximately 6.5 acres of uplands. But see Finding of Fact 29 regarding the ownership of the Property. In part, Mr. Webb stated that the grass beds would not be impacted and that there was no legitimate environmental complaint. Dr. Bingham stated that he is an ecologist, specializing in shallow water ecology. JE 11 at 3. He said his family had purchased the upland property in 1948 and the submerged land in the 1960s. Beginning in 1991, Dr. Bingham stated he tried to get the government to purchase the property, but to no avail. He also recounted attempts to obtain permits from DEP and the United States Army Corps of Engineers (Corps). See, e.g., PE 60, 63-64.6 He believed that the bridge problem, identified by the Corps had been solved. JE 11 at 3 and 13. (There is no persuasive evidence in this record that the Corps has approved any permits for development of the Property.) Mr. Webb stated that all maintenance to the bridges and other utilities would be the responsibility of the association (for the developed Property) and not the City and that the City would only be responsible for police and fire. Id. at 4. Mr. Thomasson addressed the Planning Board. JE 11 at The staff report previously mentioned is incorporated in the minutes. Staff felt that the CSTZ designation would be the most appropriate designation due to the environmental issues and that the RLD-1 designation would be the least intense land use available under the Plan. Board member Pritchard inquired whether the application was incomplete "as it doesn't address the environmental issues." Mr. Thomasson stated the applicant did not believe there would be any environmental impact, while staff believed the property to be environmentally significant. JE 11 at 8. Dr. Bingham again addressed the Planning Board to refute the staff's findings of fact. Dr. Bingham said that "the wetlands would not be impacted, the grass beds would not be impacted, and the stormwater runoff already goes into the grass beds, which are, in his opinion, fine grass beds" and that "that 13 houses would not have any significant impact." He indicated that soils were not at issue and that the "property is sandy, not special." Id. at 9. Mr. Webb indicated that "they had evaluated the environmental aspects and added the raised bridges, swales, etc." JE 11 at 9. Numerous individuals spoke in opposition to the request. Apparently, by a show of hands "a large majority of those present were in opposition to the request." JE 11 at 12. It appears that two persons spoke in favor of the request. Id. at 9-11. Mr. Webb confirmed that the application requested approval of the land use designation and annexation for 6.8 acres. JE 11 at 12. He also advised that a limited liability corporation owned the 6.8 acres, while there are different owners of other parcels. Mr. Webb indicated that "only the uplands on the islands were being annexed," although "he was not sure the properties were 'islands' in legal terms." Id. at 13. Mr. Webb indicated that he was willing to indemnify the City against any legal expenses arising from this request. Id. The requested land use change was approved by a vote of three to two. Id. at 14. On September 28, 2004, the City Commission considered Ordinance No. 1985 pertaining to the requested land use designation change and Ordinance No. 1995 pertaining to the annexation of the Property. These Ordinances were read by title only as a first reading. JE 10 at 293-294. During this meeting, the minutes (JE 10) reflect that Mr. Webb stated that they would only be developing the upland islands and proposed to use bridges, which he says "the environmental regulatory community has considered to have almost no environmental impact. He said that the addition of thirteen single family residential homes to an area that has seven hundred homes will not materially affect level of service." JE 10 at 289. Several of the people who appeared before the Planning Board also appeared opposing the application for annexation and land use designation change. JE 10 at 290. Mr. Martin Jacobson, Planning and Zoning Manager for Bay County filed a formal letter of objection to the annexation. Id. Mr. Fred Beauchemin opposed the annexation and responded to eleven items which were discussed by Mr. Webb and Dr. Bingham during the Planning Board meeting, including representations of impacts to grass beds, wildlife resources, and soils. JE 10 at 290-292. Mr. Webb continued to feel that there would not be any destruction of the marshes. Id. at 292. Dr. Bingham again noted that he is a shallow water marine ecologist and felt that he was informed about the environmental situation on the Property. Id. at 293. After brief discussion by some of the Commissioners, Ordinance Nos. 1985 and 1995 were approved by a vote of three to two. JE 10 at 293-294. By a letter dated November 9, 2004, Daniel Shaw, A.I.C.P., memorialized the October 5, 2004, Bay County Commission's unanimous decision to contest the potential annexation of and land use change to the Property, referring to several provisions of the Bay County Comprehensive Plan. T 228; PE 69. Mr. Shaw opined that "[c]learly, development proposed for the annexed Pine Islands violates the County's Comprehensive Plan." PE 69 at 2. He further stated: What's more the proposed annexation also violates the City's Comprehensive Plan. City Policy 5-5.2, 5-5.3 related to preservation of Environmentally Significant Resources would prohibit the proposed development. The property is a part of the St. Andrews estuary, and serves as a breeding/refuge area for numerous marine creatures, birds and wildlife. The three pine and oak hammocks are a truly rare estuarine resource for Bay County and for the State of Florida. The marshlands contain valuable sea grass beds and are home to numerous marine creatures, which are integral to the biodiversity of the estuary. Finally, the property contains valuable archeological sites, consisting of ancient Indian middens that are classified by the State Division of Historical resources, and potentially eligible for the National Historic Register. I would concur with staff's memorandum of August 9, 2004, which cites numerous other examples of where the development would violate the City's plan. PE 69 at 2 (emphasis in original). Mr. Shaw also stated that the Property is located in the coastal high hazard area, within a "V" zone for flood regulations.7 He stated that "[t]hese designations argue for prohibiting development for public safety and infrastructure investment purposes." Again, Mr. Shaw stated that Bay County opposed the potential annexation and subsequent land use reclassification. PE 69 at 3. Mr. Shaw also testified during the final hearing and reaffirmed his prior position. T 232-245. Mr. Shaw stated that the Property, prior to annexation by the City, was designated Conservation under the Bay County Comprehensive Plan, which allows for limited residential use and the preservation of pine islands (an outright prohibition).8 He was not qualified, however, to make a determination whether any portion of the Property is a pine island. T 247. Mr. Shaw thinks that Bay County allows up to 15 units per acre in the coastal high hazard area. T 254. On November 9, 2004, the City Commission met and considered a final reading of Ordinance Nos. 1985 and 1995. Several people appeared opposing both ordinances including Mr. Moore, Ms. Smith, Ms. Yori, and others. JE 8 at 3-14; JE 9 at 3-5. Mr. Webb again addressed the City Commission and stated, in part, that "nothing in the marsh would be touched." He also indicated that he would fully indemnify the City in the event of a lawsuit. JE 8 at 14-21; JE 9 at 5. Dr. Bingham also addressed the Commission. JE 8 at He stated that he has designed an environmentally friendly community of 13 home sites. He indicated that he had a Ph.D. in shallow water marine ecology and attended Florida State University and the University of Miami. He said that he was thoroughly familiar with the Panama City area and had worked with a large list of groups as an ecologist. He reiterated that the homes sites will take up 6.8 acres and will be entirely uplands and no marshes or swamps. He said that he is trying to use one fifth of the property that he owns and "there are no wetlands involved in this particular operation that will be damaged." JE 8 at 23. He also indicated that there will be raised bridges constructed on the Property, and according to him, were suggested by the Corps. Id. After brief comments by several Commissioners, the Commission approved the annexation and land use designation change by a vote of three to two. JE 8 at 26-27, 30-31. Toward the end of the November 9, 2004, hearing, the City Attorney, Rowlett Bryant, advised that the minutes of the September 28, 2004, Commission meeting would be included with the minutes of the November 9, 2004, public hearing. In other words, the November 9, 2004, Commission meeting was the public hearing held on the application for the annexation and the land use designation change. JE 8 at 27-30. Mr. Bryant also noted that the Ordinance No. 1985, related to the land use designation, would be RLD-1 and that the prior reference to Special Treatment Conservation Zone in the title of Ordinance No. 1985, considered on September 28, 2004, was a recommendation of staff and was deleted from Ordinance No. 1985, which was approved by the City Commission on November 9, 2004. JE 8 at 31-32. Ordinance No. 1985, in fact, changed the land use designation of the Property (approximately 6.8 acres) "from Conservation (a Bay County Land Use designation) to Residential- Low Density-1 as described in Small Scale Amendment 04-S20." JE 1 at 2. However, Petitioners and the City agree that "[t]he city assigned a future land use map designation to the parcel of Residential Low Density in Ordinance No. 1985." See T 11, lines 10-23; Petitioners' Prehearing Stipulation at 2, IV.2. Data and Analysis As more fully discussed in the Conclusions of Law, "[t]he future land use plan shall be based upon surveys, studies, and data regarding the area, including the amount of land required to accommodate anticipated growth; the projected population of the area; the character of undeveloped land; the availability of public services; the need for redevelopment, including the renewal of blighted areas and the elimination of non-conforming uses which are inconsistent with the character of the community; the capability of uses on lands adjacent to or closely approximate to military installations; and, in rural communities, the need for job creation, capital investment, and economic development that will strengthen and diversify the community's economy." § 163.3177(6)(a), Fla. Stat. Florida Administrative Code Rule 9J-5.006(2) provides for "land use analysis requirements" and requires, in part, that the future land use element "be based upon the following analyses which support the comprehensive plan pursuant to subsection 9J-5.005(2) F.A.C." Subsection 9J-5.006(2)(b) requires "[a]n analysis of the character and magnitude of existing vacant or undeveloped land in order to determine its suitability for use, including where available: 1. Gross vacant or undeveloped land area, as indicated in paragraph (1)(b); 2. Soils; 3. Topography; 4. Natural resources; and 5. Historic resources." Further, "all goals, objectives, policies, standards, finding and conclusions within the comprehensive plan and its support documents, and within plan amendments and their support documents, shall be based upon relevant and appropriate data and the analyses applicable to each element. To be based on data means to react to it in an appropriate way and to the extent necessary indicated by the data available on that particular subject at the time of adoption of the plan or plan amendment at issue." Fla. Admin. Code R. 9J-5.005(2)(a)(emphasis added). "Data are to be taken from professionally accepted existing sources, such as the United States Census, State Data Center, State University System of Florida, regional planning councils, water management districts, or existing technical studies. The data shall be the best available existing data, unless the local government desires original data or special studies." Fla. Admin. Code R. 9J-5.005(2)(c). Petitioners question whether the record contains relevant and appropriate data, which was existing and available on or before November 9, 2004, to support the Plan Amendment. Petitioners further question whether the analysis of that data is adequate. The application, JE 13, requested approval of annexation of and a change in the land use designation for, as amended, approximately 6.8 acres. Aside from identifying the parcel in question, in relation to Goose Bayou and the subdivision to the east, the application does not contain adequate data and analysis to support the Plan Amendment. Mr. Slonina, a professional engineer and expert in civil engineering, testified during the final hearing as to the due diligence he and his firm performed in support of filing the application with the City. T 424. Mr. Slonina has been on the Property many times. T 456. As part of the due diligence, Mr. Slonina analyzed the area proposed for development on the Property, which are the upland areas, and, in part, stated that these areas are primarily free draining sands and have fairly high percolation rates. T 425, 453. He also characterized upland areas as fairly clean sands and satisfactory for development in this area based on his experience. He also examined the upland and wetland soils to determine suitability for a "post and beam timbered bridge system" that would be pile supported over the wetlands bridging upland areas. He opined that the soils on the uplands were nothing unique and were suitable for low density residential and suitable to support the bridge system he described. T 428, 442, 458-459. See also P 50, Attachment A. Regarding utilities which might be available to the Property, during the due diligence phase, he identified, from utility maps, the location of the closest water and sewer which could serve the Property, adjacent to the Property to the east. He also analyzed the ability of fire protection to be provided to the Property and concluded that it was feasible. T 428-432, 460-461. See also JE 7 at 1 regarding "utility and other urban services availability" and P 50 at 14-16 for a discussion of "utilities." Mr. Slonina also opined that a stormwater system could reasonably be designed for the Property and that it was feasible to design a stormwater system that would capture stormwater runoff before it went into the bayou. T 432-435. Mr. Slonina examined flood zone information and determined that the Property was "very typical" and that the flood zone information available would not preclude residential development on the Property. T 434-435, 450. But see Endnote 7. From a traffic concurrency standpoint, he examined traffic engineering data on trip generation for 13 single-family homes and determined that there was adequate capacity for that additional loading on "the only roadway that connects to the [P]roperty." His traffic impact analysis was limited "through the residential streets." T 435-436, 439-441. Mark O. Friedemann, is the executive vice-president at the Phoenix Environmental Group, Inc., an environmental consulting firm. T 466. Mr. Friedemann was retained on or about January 7, 2005, by the City's counsel for the purpose of "doing a basic assessment of the property and whether it was suitable for some type of development, residential in particular." T 474-475. Prior to conducting a survey of the Property, aerial photographs, data from the Florida Natural Areas Inventory, and various maps were reviewed. Id. Mr. Friedemann and an assistant conducted a field survey of the Property on January 12, 2005. They collected basic water quality data, observed wildlife, conducted several soil observations pits, looked for scat, and examined the vegetative community on the Property. T 476. For the purpose of the survey, the Property was divided into areas 1 through 4, which are labeled on CE 5, Figure 2. T 478. These upland areas were the major focus of the assessment along with the interior (wetland/marsh) areas. T 478, 565. CE 5 at 2, Figure 2. Mr. Friedemann and his assistant arrived on the Property at approximately 9:00 am on January 12, 2005, during low tide. They left the Property as the tide was starting to return. T 517, 532, 548. Area one is a rectangular portion of the Property, which runs north to south and forms most of the eastern boundary of the Property and is adjacent to Candlewick Acres. Area two is another upland area which is in the northwest portion of the Property and west of area one. Area three is in the southwest portion of the Property and southwest of area two. Area four is a small upland portion, which is almost due south of area one in the southeastern portion of the Property. CE 5 at 2, Figure 2; see also Endnote 6. Mr. Friedemann accessed area two from area one by walking along a path/spoil pile, which runs east to west and forms part of the northern boundary of the Property (the approximately 100 foot canal is north of and adjacent to the path/spoil pile). He walked to area three by stepping across a small rivulet of no more than a foot in width. He walked to area four from area three, stepping over another small tidal- influenced rivulet that passed between areas three and four. He approached area one from area four walking across "a rather high area." Mr. Friedemann "did not get the impression that area two was surrounded" by wetlands, salt marsh, or tidal mud flats. T 479-481, 500, 517, 556-557. He stated that area three would be surrounded, but was unsure about area four. T 556-559. Some of the areas photographed would be potentially inundated during high tide. T 521-525. Mr. Friedemann's report also contained, in part: water quality data taken on January 12, 2005; and a list of species seen on the same date; a recent undated aerial of the Property and surrounding area, downloaded from the DEP website, which was also magnified; and several aerials (dated 1953, 1962, 1967, 1974, 1978, and 1986) of the Property including the surrounding areas. Mr. Friedemann opined, based on his review of aerials, that there may have been a timber operation ongoing on the Property in the past although he would not hazard a guess. T 540. The report also included several photographs taken of the four areas, during the site visit on January 12, 2005. CE 5 at x-xxii. Although he did not "review any set of plans," or have any opinion regarding any specific development proposal, Mr. Friedemann opined that based on his observations in the field, "there is a viable project that could be built on this parcel."9 T 482, 501-502, 511, 520. Mr. Friedemann provided an analysis of the Property by and through his testimony regarding photographs taken of the Property during his site visit. From a biological or ecological perspective, he did not observe anything on the Property which would preclude residential development. He further opined that what he observed was not unique in the panhandle of Florida. T 501-502. Mr. Friedemann did not conduct a wetland delineation of the Property. T 556. However, the record contains an infrared Conceptual Site Plan dated October 22, 2002, indicating vacant land to the north of the Property, and residential areas to the east of the Property and east of the vacant parcels to the north. This particular site plan provided for the approximate wetland boundaries of the Property identified as south parcel (4). PE 98-D and PE 50 at Exhibit 1. Mr. Friedemann indicated that he had not observed the Property during a hurricane, during periods of high wind, or during periods of a combination of high wind and high tide. He agreed that the tides in the United States can be lower during the winter than they are during the spring and that the highest tides may be experienced during the spring called neap tides. T 532-533. Mr. Friedemann was also referred to a December 30, 2004, document apparently prepared by Panhandle Engineering, Inc., sheet number 2 of 4, CE 16, which delineated 13 lots. T 533. See Endnote 6. (City Exhibit 16 was admitted into evidence as an authentic document; however, there was no testimony regarding the preparation of this document. T 535-537.) Comparing sheet 2 of 4 with Figure two of CE 5, area two is depicted as being surrounded by rush marsh and connected to area one and area three by drawn-in bridges. Compare PE 50, Attachment E, Sheet 1 of 2, dated July 31, 1998, depicting the Property with 13 lots configured, interspersed with a "conservation area" designation and Attachment A, Figure 4., Project Base Map, depicting upland areas on the Property, interspersed with a "marsh" designation with PE 98-D south parcel (4) and "approximate wetland boundary. See also Endnote Mr. Friedemann stated that the indication of rush marsh on sheet number 2 of 4 did not comport with his observations of the Property during his site visit. He was unaware of this drawing. T 534-538. Gail Easley, A.I.C.P., an expert in urban and regional planning, opined that the Plan Amendment was consistent with various provisions of the City's Plan, the State Comprehensive Plan, and the West Florida Regional Strategic Policy Plan. She also opined the Plan Amendment was supported by data and analysis regarding the suitability of the Property for the RLD land use designation. In support, Ms. Easley stated in part: Understanding that the amendment is not really permitting the use, but understanding that the amendment establishes the uses that are allowed as I testified earlier, the suitability data that is available in addition to the data and analysis here in the Comprehensive Plan includes the information from Panhandle Engineering about, more specifically about the availability of facilities and services and the suitability of soils for use of residential low density, as well as the analysis contained in Mr. Friedemann's report regarding environmental issues and the suitability of this site for residential low density. So I found plenty of evaluation of suitability. T 586. See also T 610-611. Ms. Easley also opined that the Plan Amendment does not threaten coastal and natural resources in violation of Florida Administrative Code Rules 9J-5.006, 9J-5.012, and 9J- 5.013, and Sections 163.3177 and 163.3178, Florida Statutes, because she considered the data and analysis in the Plan, "as well as the suitability and capability [sic] analysis that were submitted by Panhandle Engineering and Mr. Friedemann demonstrated that there was not a violation of these provisions." T 617. Ms. Easley also stated that there was adequate data to support a need for residential (RLD) development on the Property. See, e.g., T 584-585, 621-622, 629-630, 632-634. See also JE 3 at Future Land Use Data, 1-1 - 1-10. During cross-examination, Ms. Easley was asked to identify the particular Panhandle Engineering report which she reviewed to support her opinion. The report is not in evidence. However, Ms. Easley stated: "It was a report that they prepared that addressed issues of suitability of the site with regard to the availability of water, the availability of sewer, the capacity for water and sewer, soil conditions on the site, and traffic situations on the site. I'm sorry, I do not recall the date of that particular suitability analysis, but it was prepared by Panhandle Engineering, and I reviewed it as a part of my analysis." T 626. Ms. Easley was also asked to provide the source of her data and analysis about environmental conditions on the site and she replied: "Two places, there is information in the City's data and analysis with regard to the vacant land analysis, as well as general environmental conditions in or around the City, I reviewed that data and analysis that I mentioned earlier. I also saw information specific to this parcel from Mr. Friedemann's report." T 627. Ms. Easley indicated that there was no specific data and analysis contained in the City's Plan about the Property, although the Plan referenced areas adjacent to the City. T 628. Ms. Easley reiterated that natural resources are considered during the plan amendment process. It also occurs during permitting. T 642. She again stated: "The suitability analysis was contained in two different reports. As I testified earlier, Mr. Slonina's report from Panhandle Engineering addressed soils and soil suitability. And Mr. Friedemann's report looked at other kinds of environmental issues. I reviewed both of those reports and determined that suitability analysis had been preformed to support the plan amendment." T 643. According to Ms. Easley, if there were environmental reasons creating an inconsistency with Rule 9J-5, then such reasons could serve as a basis for denial. T 643. (Ms. Easley also opined that a land use change to the FLUM "is an assignment of a land use category and the associated density and intensity, it is not a development activity." See T 587, 651.) Mark Llewellyn, P.E., is the president of Genesis Group. In October 2002, Genesis Group completed a planning and engineering analysis (Genesis Report)10 for Chandler and Associates, who, in turn, had a contract with the DEP to prepare an appraisal report for the Goose Bayou Marsh Property.11 The Goose Bayou Marsh Property included four parcels, including the south parcel (4), which is the Property in question, two north parcels (2 and 3), and the middle parcel (1), which is north and northeast of and adjacent (the west one- third) to the Property. All the parcels are vacant. See PE 98- D, which also appears at PE 50, Exhibit 1. Mr. Llewellyn identified three peninsular islands on the Property (south parcel 4)(PE 98-D at the blue X's), which roughly correspond with areas one and two in Mr. Friedemann's report at CE 5 at 2, Figure 2. T 160-161. See also Endnote 6. The two eastern peninsular islands (area one) are connected to the upland to the east, Candlewick Acres. The third peninsular island, located in the northwest corner of the Property, can be accessed, according to Mr. Llewellyn, by a berm or other geographical feature to the north of the Property and south of the drainage canal. Id. See also T 397. There is one larger upland island and a smaller upland island toward the southwest and southern portions of the Property, which appear to be surrounded by wetlands, waters of the state, salt marsh, or tidal mud flats. T 160-164. Each peninsular island and upland island is less than 20 acres. Mr. Llewellyn's analysis is consistent with the approximate wetland boundaries identified in the Conceptual Site Plan, PE 98-D. Mr. Llewellyn opined that the Property could be developed as a single-family development without having an impact on the Property if it is designed and maintained properly. T 157, 172. See also Endnote 6. The Genesis Report provided an analysis of the four parcels. Apparently the south parcel (4), the Property, contained approximately 16.2 acres as follows: wetlands 9.8+/- acres; upland islands 3.5+/- acres; peninsula uplands 2.9+/- acres; or 6.4+/- acres of total uplands. T 163; PE 50 at 12. Parcels 1-4 are analyzed in light of several factors, including but not limited, to the Bay County Future Land Use and Comprehensive Plan. The following is an analysis of the Bay County Future Land Use and Comprehensive Plan as applied to the north parcels (2 and 3): The Bay County Comprehensive Management Plan identifies the North Parcel's Future Land Use Designation as Conservation. The purpose of this land use is to identify public and private lands held for conservation of natural features. Allowable uses for this designation are natural resource protection, flood control, wildlife habitat protection, passive of recreation, silviculture and residential densities up to 2DU/acre. Commercial development is prohibited for properties with this land use designation. Additionally, the upland islands located on these parcels fit the definition for "Pine Islands" as defined in the Bay County Comprehensive Plan. A Pine Island is defined as a small upland area generally 20 acres or less, usually characterized by typical pine flatwood vegetation, which are surrounded by waters of the State, wetlands, salt marsh, or tidal mud flats. The Bay County Comprehensive Plan prohibits development on any "Pine Island". This means that it will be extremely difficult to develop the upland areas located on this parcel. PE 50 at 2. See also PE 50 at 2 (II.B.) and 13 (IV.B.) regarding the Panama City Future Land Use. (The Genesis Report was prepared approximately two years prior to the City's annexation of the Property. The City did not annex the vacant land to the north (parcels 1-3), which is part of the subject of the Genesis Report.) Regarding the analysis of parcels 1, and 4, the Property, and referring to the Bay County Future Land Use and Comprehensive Plan, it is noted that "[t]he same issues apply to this parcel." PE 50 at 7 and 13. The Genesis Report discussed wetlands on the Property: The wetlands within the property consist of estuarine salt marshes, which are connected to Goose Bayou and West Bay. According to an environmental assessment prepared by Biological Research Associates (BRA) the marshes are tidally influenced and dominated by black rush. Other species include seaside goldenrod, seashore dropseed grass, sea purslane, glasswort, salt grass, marsh hay cord grass, sea lavender, Chinese tallow, saw grass, cork wood, and saltbrush. Additionally, the salt marsh is habitat for two listed bird species; the snowy egret and the little blue heron (see Attachment A). As previously stated, a wetland delineation has been completed for this parcel and accepted by FDEP and ACOE. PE 50 at 13. The Genesis Report also provided a brief discussion of flood plain and cultural resource considerations, and also provided an analysis of site planning and engineering, including access, utilities, owner site plan/lot lay out, and probable development costs. PE 50 at 13-15. Regarding south parcel 4, the Property, the Genesis Report concluded, in part, that "[t]his parcel has limited development potential." A cost estimate is provided. It is also concluded that water and sewer could be provided without incurring significant increases in development costs. "Development of the upland islands would require bridges, which significantly increases the development cost. There is no guarantee that the development within the wetlands would be permitted at this time." PE 50 at 16. The Genesis Report also included a report prepared by Biological Research Associates, which appears as Attachment A to PE 50. Mark Andrew Barth, vice president/senior ecologist for Biological Research Associates, was one of the two signatories to a section of the Genesis Report and also testified during the final hearing. T 175; PE 50, Attachment A. He reiterated that they prepared a preliminary environmental assessment for a proposed acquisition by a State agency. T 176, 180. (While unclear, it appears that his study area included the approximate western one-third of the Property, see, e.g., T 189; PE 50, Attachment A, Figures 1, 3-4, although other portions of the Property were studied. See, e.g., Finding of Fact 93.) Referring to PE 98-C and the Property (outlined in black) and the vacant land to the north outlined in red, Mr. Barth testified that they are "mainly comprised of salt marsh and scattered pine dominated islands." According to Mr. Barth, the term "pine islands," "describes isolated upland patches within the salt marsh." T 177. The salt marshes consist of vegetation that extends beyond the water level usually in very shallow water. T 178. The Property is part of an estuary system, Goose Bayou, for example. Id. See also T 381; JE 12 at IV-14-16 and Map 1. The salt marsh is inundated by saline or marine water as opposed to fresh water. T 178. One of the most significant features of an estuary system "is providing nursery grounds and habitat for marine and estuarine fish and wildlife." T 179. Mr. Barth considered the Property, south parcel 4, PE 98-D, to be environmentally sensitive in light of the combination of estuarine and upland areas which are undisturbed. T 185-186. Mr. Barth did not have enough information to assess specific impacts to the surrounding salt marsh and water in light of a proposed development on the Property. He felt it depended on the type of development. T 182. "Middens" have been found on the south side of the Property, in and around area 3 (CE 5 at 2, Figure 2). See, e.g., T 558-559; PE 50, Genesis Report at 13 and Attachment A at 6-7 and Attachment E, Figure 4, Project Base Map and Figure 5, PBY139 Base Map. Ultimate Findings of Fact Regarding Adequacy of Data and Analysis Ultimately, whether the Plan Amendment is based upon relevant and appropriate data and analysis is a close question. This is particularly true here where critical portions of Mr. Friedemann's analysis are based on information, e.g., Mr. Friedemann's photographs, collection of water quality samples, and observations of the Property (species seen and terrain), which post-dated the City's adoption of the Plan Amendment on November 9, 2004. As a result, his analysis of this information has been disregarded, notwithstanding the lack of an objection to the admissibility of his report, CE 5. See Conclusions of Law 110-114. (Mr. Friedemann also provided several aerials of the Property and surrounding area which pre-date the date of adoption of the Plan Amendment and have been considered along with his analysis of this data.) Also, to the extent that Ms. Easley relied on Mr. Friedemann's report (CE 5) and the post- adoption information collected by Mr. Friedemann and his analysis of that information, her opinions have also been disregarded. Nevertheless, Petitioners have the burden to prove, by a preponderance of the evidence that the Plan Amendment is not based upon relevant and appropriate data and analysis, which Petitioners have not done. Accordingly, based on a review of the entire record in this proceeding, it is ultimately concluded that the Plan Amendment is based on relevant and appropriate data and analysis, except as otherwise stated herein. See § 163.3177(6)(a), Fla. Stat.; Fla. Admin. Code R. 9J-5.005(2), 9J-5.006(2), and 9J-5.012-.013. Consistency with the City's Plan, the West Florida Strategic Regional Policy Plan, the State Comprehensive Plan, and the City's Comprehensive Planning and Land Development Regulation Code Petitioners contend that the Plan Amendment is inconsistent with several provisions of the City's Plan: Future Land Use Element Policy 1.1.1.10; Coastal Management Element Goal 1, Objective 5.1, and Policies 5.1.1 and 5.1.3.3, and Goal 3; and Conservation Element Goal 1, Policies 6.6.2, 6.6.2.3, and 6.6.2.4. Petitioners contend that the Plan Amendment is inconsistent with several provisions of the LDRC: subsections 2- 5.5.6, 5-5.1, 5-5.2, 5-5.3, and 5-5.6.3.e. Petitioners also contend that the Plan Amendment is inconsistent with Section 187.201, Florida Statutes, and the West Florida Strategic Regional Policy Plan. The Plan Amendment changes the land use designation on the Property to RLD. The Plan Amendment is not a development order. See Strand v. Escambia County, Case No. 03-2980GM, 2003 WL 23012209, at *4 (DOAH Dec. 23, 2003; DCA Jan. 28, 2004), aff'd, 894 So. 2d 250 (Fla. 1st DCA 2005). It does not authorize any development to occur on the Property. Further, a special treatment zone, as used in the City's Plan, is not a FLUM land use district. Based on the plain and ordinary meaning of the various Plan provisions at issue, the Plan Amendment does not alter or interfere with the City's ability to maintain the quality of coastal resources; restrict the City's ability to maintain regulatory or management techniques intended to protect coastal wetlands, water quality, wildlife habitat, and living marine resources, for example, or prohibit the construction of docks, piers, wharves, or similar structures; interfere with the City's ability to provide for or have available adequate areas for public waterfront access or to provide the circumstances necessary for the conservation, protection, and use of natural resources; or interfere with the City's ability to enforce guidelines in its LDRCs related to, for example, the protection and conservation of the natural functions of existing soils, wetlands, marine resources, estuarine shoreline, stormwater management, wildlife habitat, or flood zones. Petitioners did not prove that the Plan Amendment is inconsistent with cited portions of the City's Plan, the State Comprehensive Plan, and the West Florida Strategic Regional Policy Plan. Further, the Plan Amendment need not be consistent with the City's LDRCs because it is not the subject of "in compliance" review.12
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Community Affairs enter a final order concluding that the Plan Amendment, adopted by the City of Panama City in Ordinance No. 1985, is "in compliance" as defined in Section 163.3184(1)(b), Florida Statutes. DONE AND ENTERED this 6th day of October, 2005, in Tallahassee, Leon County, Florida. S CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 6th day of October, 2005.
The Issue The issue to be determined in this case is whether the amendment of the Town of Eatonville Comprehensive Plan adopted through Ordinance 2014-2 (“Plan Amendment”) is “in compliance” as that term is defined in section 163.3184(1)(b), Florida Statutes (2014).
Findings Of Fact The Parties Respondent Town of Eatonville is a municipality in Orange County with a comprehensive plan which it amends from time to time pursuant to chapter 163, Florida Statutes. Intervenor Lake Weston, LLC, is a Florida limited liability company whose sole member is Clayton Investments, Ltd. It owns approximately 49 acres of land along Lake Weston on West Kennedy Boulevard in Eatonville (“the Property”), which is the subject of the Plan Amendment. Petitioners Sharon Leichering, Lori Erlacher, George Perantoni, Valerie Perantoni, and Doreen Maroth own or reside in unincorporated Orange County near Lake Weston. The record does not establish whether Dale Dunn lives or owns property in the area. Petitioner Kingswood Manor Association, Inc., is a non- profit corporation whose members are residents of Kingswood Manor, a residential subdivision near the Property. Petitioner Friends of Lake Weston and Adjacent Canals, Inc., is a non-profit corporation whose objective is to protect these waters. Standing Petitioners Sharon Leichering and George Perantoni submitted comments to the Eatonville Town Council on their own behalves and on behalf of the Kingswood Manor Association and Friends of Lake Weston, respectively, regarding the Plan Amendment. Petitioner Valerie Perantoni is the wife of Petitioner George Perantoni. She did not submit comments regarding the Plan Amendment to the Town Council. Petitioner Dale Dunn did not appear at the final hearing. There is no evidence Mr. Dunn submitted oral or written comments to the Town Council regarding the Plan Amendment. Petitioner Doreen Maroth did not appear at the final hearing for medical reasons. Ms. Maroth submitted oral comments to the Town Council regarding the Plan Amendment. Respondent and Intervenor contend there is no evidence that Lori Erlacher appeared and gave comments to the Town Council, but the Town Clerk testified that Petitioner Leichering was granted an extension of time “to speak for others” and Petitioner Leichering testified that the “others” were Lori Erlacher and Carla McMullen. The Plan Amendment The Property is zoned “Industrial” in the Town’s Land Development Code, but is designated “Commercial” on the Future Land Use Map in the Comprehensive Plan. The Town adopted the Plan Amendment to make the zoning and future land use designations consistent with each other. The Plan Amendment attempts to resolve the inconsistency by designating the Property as the “Lake Weston Subarea” within the Commercial land use category. The designation would appear on the Future Land Use Map and a new policy is made applicable to the Subarea, allowing both industrial and commercial uses: 1.6.10. Lake Weston Subarea Policy. Notwithstanding the provisions of Policy 1.6.9, within the Lake Weston Subarea Policy boundaries as shown on the Future Land Use Map, light industrial uses may be allowed in addition to commercial uses. The specific permitted uses and development standards shall be established by the Lake Weston Overlay District, which shall be adopted as a zoning overlay district in the Land Development Code; however, the wetlands adjacent to Lake Weston within the Lake Weston Subarea Policy boundaries are hereby designated as a Class I Conservation Area pursuant to Section 13-5.3 of the Town of Eatonville Land Development Code and shall be subject to the applicable provisions of Section 13-5 of the Land Development Code. The intent of this subarea policy and related Lake Weston Overlay District is to allow a range of commercial and industrial uses on the subject property with appropriate development standards, protect environmental resources, mitigate negative impacts and promote compatibility with surrounding properties. Subject to requirements of this subarea policy and of the Lake Weston Overlay district, the current industrial zoning of the property is hereby deemed consistent with the Commercial Future Land Use designation of the area within the boundaries of this subarea policy. Data and Analysis Petitioners contend the Plan Amendment is not supported by relevant and appropriate data and analysis. Relatively little data and analysis were needed to address the inconsistency between the Land Development Code and the Comprehensive Plan or to address the protection of Lake Weston and adjacent land uses. The need to protect environmental resources, to mitigate negative impacts of development, and to promote compatibility with surrounding land uses was based on general principles of land planning, the report of a planning consultant, as well as public comment from Petitioners and others. A wetland map, survey, and delineation were submitted to the Town. The effect of the Class I Conservation Area designation is described in the Land Development Code. The availability of public infrastructure and services was not questioned by Petitioners. The preponderance of the evidence shows the Plan Amendment is based on relevant and appropriate data and analysis. Meaningful Standards Petitioners contend the Plan Amendment does not establish meaningful and predictable standards for the future use of the Property. It is common for comprehensive plans to assign a general land use category to a parcel, such as Residential, Commercial, or Industrial, and then to list the types of uses allowed in that category. The Plan amendment does not alter the Comprehensive Plan’s current listing of Commercial and Industrial uses. The Plan Amendment designates the wetlands adjacent to Lake Weston as a Class I Conservation Area subject to the provisions of the Eatonville Wetlands Ordinance in the Land Development Code. This designation means the littoral zone of the lake and associated wetlands would be placed under a conservation easement. This is meaningful guidance related to the future use of the Property. The Plan Amendment directs the Land Development Code to be amended to create a Lake Weston Overlay District with the expressed intent to “protect environmental resources, mitigate negative impacts and promote compatibility with surrounding properties.” This direction in the Plan Amendment is guidance for the content of more detailed land development and use regulations. Contemporaneous with the adoption of the Plan Amendment, the Eatonville Land Development Code was amended to establish the Lake Weston Overlay District, which has the same boundaries as the Property. The Land Development Code describes in greater detail the allowed uses and development standards applicable to the Property. The preponderance of the evidence shows the Plan Amendment establishes meaningful and predictable standards. Internal Consistency Petitioners contend the Plan Amendment is inconsistent with the relatively recent Wekiva Amendments to the Comprehensive Plan, but Petitioners failed to show how the Plan Amendment is inconsistent with any provision of the Wekiva Amendments. Petitioners contend the Plan Amendment is inconsistent with objectives and policies of the Comprehensive Plan that require development to be compatible with adjacent residential uses. Compatibility is largely a matter of the distribution of land uses within a parcel and measures used to create natural and artificial buffers. These are matters usually addressed when a landowner applies for site development approval. Protection is provided in the Plan Amendment for Lake Weston and its wetlands. Petitioners did not show there are other factors that make it impossible to make light industrial uses on the Property compatible with adjacent residential uses. The preponderance of the evidence shows the Plan Amendment is consistent with other provisions of the Comprehensive Plan. Urban Sprawl Petitioners contend the Plan Amendment promotes urban sprawl based on the potential for more impervious surfaces and less open space. However, this potential does not automatically mean the Plan Amendment promotes urban sprawl. Section 163.3177(6)(a)9. sets forth thirteen factors to be considered in determining whether a plan amendment discourages the proliferation of urban sprawl, such as failing to maximize the use of existing public facilities. The Plan Amendment does not “trigger” any of the listed factors. The preponderance of the evidence shows the Plan does not promote the proliferation of urban sprawl.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Economic Opportunity enter a final order determining that the Plan Amendment adopted by Eatonville Ordinance No. 2014-02 is in compliance. DONE AND ENTERED this 3rd day of June, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 3rd day of June, 2015. COPIES FURNISHED: George Anthony Perantoni Friends of Lake Weston and Adjacent Canals, Inc. 5800 Shasta Drive Orlando, Florida (eServed) 32810 Dale Dunn 5726 Shasta Drive Orlando, Florida 32810 Lori A. Erlacher 1620 Mosher Drive Orlando, Florida 32810 (eServed) Sharon R. Leichering Kingswood Manor Association, Inc. 5623 Stull Avenue Orlando, Florida 32810 (eServed) Doreen Lynne Maroth 5736 Satel Drive Orlando, Florida 32810 (eServed) Valerie Lolita Perantoni 5800 Shasta Drive Orlando, Florida 32810 (eServed) Debbie Franklin, City Clerk Town of Eatonville, Florida 307 East Kennedy Boulevard Eatonville, Florida 32751 Joseph Morrell, Esquire Town of Eatonville 1310 West Colonial Drive, Suite 28 Orlando, Florida 32804 (eServed) William Clay Henderson, Esquire Holland and Knight, LLP 200 South Orange Avenue, Suite 2600 Orlando, Florida 32801 (eServed) Robert N. Sechen, General Counsel Department of Economic Opportunity Mail Stop Code 110, Caldwell Building 107 East Madison Street Tallahassee, Florida 32399-4128 (eServed) Jesse Panuccio, Executive Director Department of Economic Opportunity Mail Stop Code 110, Caldwell Building 107 East Madison Street Tallahassee, Florida 32399-4128 (eServed) Katie Zimmer, Agency Clerk Department of Economic Opportunity Mail Stop Code 110, Caldwell Building 107 East Madison Street Tallahassee, Florida 32399-4128 (eServed)