Findings Of Fact Trans/Circuits is a manufacturer of electronic printed circuit boards located at 210 Newman Way, Lake Park, Florida. Trans/Circuits' manufacturing operation involves the deposition of copper on plastic boards and the use of a lead or tin etch resist in order to create an electrically conducting circuit board. In the course of the manufacturing process, rinsewaters are used which become contaminated with copper and lead from the manufacturing process. These rinsewaters undergo chemical treatment to remove the metals and other contaminants, and are then discharged into an unlined percolation pond located behind Trans/Circuits' facility. About 36,000 gallons of effluent are discharged into the pond every day. The percolation pond discharges into ground water underlying Trans/Circuits' facility which groundwaters contain less than 3000 milligrams per liter (mg/l) of total dissolved solids. Trans/Circuits uses a Havviland brand wastewater treatment system. The system at present does not provide treatment sufficient to remove copper, fluoride, and lead from the wastewater effluent in compliance with the DER class G-II groundwater standards for these metals, i.e., 1.0 mg/l of copper, 1.5 mg/l of fluoride, and .05 mg/l of lead. Trans/Circuits has exceeded the effluent limitations for copper and lead at almost all times since at least June 1984. Trans/Circuits is not likely to comply with those standards for at least six months, by Trans/Circuits' own admission. The Operating Permit Application, Case No. 83-3676 Trans/Circuits requested a hearing to contest the DER Notice of Intent to Deny the application for an operating permit. The burden of proof and burden of going forward is therefore on Trans/Circuits to show that it is entitled to issuance of the operating permit. In this regard, Trans/Circuits did not introduce into the case any evidence relating to the operating permit application and did not introduce the application, itself. Further, Trans/Circuits did not present any evidence that its installation will abate or prevent pollution, or that it can provide reasonable assurances that the system which it seeks to operate will not discharge, emit or cause pollution. The Trans/Circuits facility has never been in compliance with DER standards and cannot provide assurances that it will be in compliance at anytime in the foreseeable future. Further Trans/Circuits has been operating without an operating permit at least since October 1983. The Month-to-Month Authorization, Case No. 84-0191 On September 17, 1982, DER issued a Notice of Violation and Orders for Corrective Action (NOV) to Trans/Circuits. The NOV alleged that Trans/Circuits violated provisions of Chapter 403, Florida Statutes, and DER rules in operation of its industrial waste water treatment and disposal system. Trans/Circuits requested and received an informal conference to discuss the allegations of the NOV, which conference was held on October 20, 1982. At the informal conference, DER and Trans/Circuits reached agreement on a resolution of the issues raised by the NOV. On November 4, 1982, a Consent Order was issued by DER, setting forth the parties' agreement and requiring Trans/Circuits to perform certain corrective actions. In the consent order, Trans/Circuits agreed not to discharge industrial wastewaters into waters of the state "without an appropriate and valid permit authorizing such discharge or having otherwise obtained Department authorization." At the time the consent order was issued, Trans/Circuits was operating pursuant to a DER construction permit which was issued for the purpose of allowing Trans/Circuits to make certain modifications to its treatment system to bring the system into compliance with DER effluent standards. The construction permit expired in January 1983, but Trans/Circuits continued to operate. About one month after the construction permit expired, DER notified Trans/Circuits that it was violating the consent order by operating without DER authorization. The parties met to discuss the matter, and agreed that Trans/Circuits would cease operation for one week to conduct bench-scale testing to identify problem areas and possible corrective actions. Trans/Circuits did cease operation and conduct the testing as agreed. Trans/Circuits presented the data resulting from their bench scale testing to DER, and represented that it had identified problem areas that needed correction. DER evaluated the data and agreed to allow Trans/Circuits to operate for a limited time to gather plant effluent quality data which would form the basis for DER's decision whether to allow operation to continue. DER did not take enforcement action to have Trans/Circuits cease operation at that time because DER wanted to give Trans/Circuits time to show that it could comply with the effluent standards as it claimed it could. On March 23, 1983, DER notified Trans/Circuits that there had been a significant improvement in the plant's ability to produce effluent of acceptable quality, and DER authorized Trans/Circuits to make modifications in order to improve effluent quality. DER at that time gave Trans/Circuits authorization to operate for an indefinite period, with the condition that DER would rescind its approval if the program of sampling and system approval did not continue. Trans/Circuits accepted the authorization on DER's terms. On April 12, 1983, DER granted Trans/Circuits' month-to-month authorization to operate ". . . provided continued improvement is made in your system's operation and the Department can reasonably anticipate system compliance." This authorization was in response to a request from Trans/Circuits for 90-day temporary operating approval in order to demonstrate that the system could comply with state standards. By letter dated October 5, 1983, DER withdrew its authorization for month-to-month operation of Trans/Cirouits' facility because it believed that compliance with state standards could no longer be reasonably anticipated. Despite Trans/Circuits' best efforts, the facility was not in compliance and DER had no assurance that continued operation would bring the facility into compliance within a reasonable amount of time. Trans/Circuits has never ceased operation since DER withdrew its month-to-month operating approval. Trans/Circuits has not had a DER permit for construction or operation of the facility since the expiration of their last construction permit in January, 1983. At a meeting on December 1, 1983, Trans/Circuits' general manager admitted that he was aware that Trans/Circuits' was in violation of the terms of the consent order by continuing to operate without DER authorization. Analysis of Trans/Circuits' plant effluent for April 1983, shows that average lead levels were 0.21 parts per million (ppm) (or mg/l), average fluoride levels were 2.45 ppm, while average copper levels were 0.51 ppm. These were the effluent levels existing when Trans/Circuits was granted its month-to- month approval for operation. Since the month-to-month authorization was granted, the majority of Trans/Circuits' effluent samples have not complied with the DER standards for lead, copper, and fluoride. Since April 16, 1984, five percent or less of Trans/Circuits' effluent samples have complied with the effluent standards for lead and copper. In the week or two prior to hearing, the majority of effluent samples contained lead at a concentration of 0.2 to 0-5 ppm (with some higher), and contained copper at a concentration of between 2 and 3.5 ppm (with some higher). The most recent data available indicate that Trans/Circuits is not in compliance with the effluent standards for lead, copper and fluoride. Daily average effluent concentrations for lead and copper are significantly greater now than they were when DER issued its month-to-month authorization. Groundwater samples just outside Trans/Circuits' property show violations of the DER standards for lead. The evidence shows that Trans/Circuits effluent quality has not improved since April 1983. Effluent concentrations of lead and copper have actually increased significantly since October 1983, when DER withdraw its month-to-month authorization. Trans/Circuits does not even expect to know before December 1984, whether its present system can attain compliance with effluent standards. The Construction Permit Application On March 8, 1984, Trans/Circuits applied to DER for a permit to construct modifications and improvements to the existing Havviland wastewater treatment system. Although the stated purpose of the requested construction was to upgrade the system to achieve compliance with the Riviera Beach Sewer Use Code so as to allow a sewer tie-in, Trans/Circuits had abandoned that purpose by the time of the hearing. Trans/Circuits now seeks to upgrade the systems so that the effluent can comply with the applicable standards for discharge to ground water. When DER received the application, it was reviewed by a DER engineer to see if it was complete. The engineer determined it was not complete, and notified Trans/Circuits on April 6, 1984, that additional information was needed to complete the review process, all of which information was necessary to determine whether a permit should be issued for the requested construction. Trans/Circuits' general manager objected to the request for additional information, claiming that all the requested information was not necessary to review the application. However, at the request of Trans/Circuits' counsel, a meeting was held between representatives of Trans/Circuits and DER to discuss the request for information that was needed for review of the application. Trans/Circuits thereafter, withdrew their objections, and agreed to provide the requested information. Trans/Circuits responded to DER's request for additional information on June 27, 1984, at 3:30 P.M. the day prior to hearing. Trans/Circuits delivered a packet of information to DER at that time that purported to be the requested information. Also at that time, however, Trans/Circuits told DER that it had already performed some of the construction for which a permit was sought, and that it was not sure what, if any, of the remaining construction would be undertaken. The information that was submitted to DER was not all of the information requested by DER. No flow diagram was submitted and waste effluent analysis was lacking. Without this information, it is impossible to determine whether or not reasonable assurance has been provided by Trans/Circuits that DER standards will be met. Even if all of the requested information had been submitted, DER could not issue a construction permit to Trans/Circuits because its future construction plans are now only speculative. Trans/Circuits does not know what modifications it intends to construct, or when exactly such modifications will be made. All that is certain is that Trans/Circuits does not intend any longer to construct the modifications for which it made application. DER evaluates applications to determines whether all proposed modifications works as a system. Trans/Circuits is the applicant for this permit and has the burden of showing that it is entitled to issuance of the permit. Here Trans/Circuits failed to present any evidence of what construction it actually plans to do, let alone that the purposed construction meets the criteria and that it is entitled to the permit.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a Final Order be entered by the State of Florida Department of Environmental Regulation: Denying Trans/Circuits application for an operation permit; Denying Trans/Circuits application for a construction permit; and Withdrawing the month-to-month authorization for Trams/Circuits' operation. DONE and ENTERED this 19th day of September, 1984, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1984.
The Issue Whether petitioner should take disciplinary action against respondent for the reason alleged in the administrative complaint?
Findings Of Fact Respondent acknowledges the accuracy of the allegations in the first seven paragraphs of the administrative complaint, including the allegation that he holds a certified residential contractor's license, No. CR C027268. He has been licensed in Florida continuously since October of 1983. Petitioner's Exhibit No. 1. On August 14, 1986, respondent Stratton, doing business as Stratton Construction Company, executed a written contract with Aaron Lee and Valerie Patrice Cobb to renovate their home at 5017 Pearl Street in Jacksonville, Florida. He had actually begun work nine days earlier. The contract contemplated installation of a pier under an unsupported sill end, replacement of 17 windows and two doors, hanging a screen door and a storm door, shortening and capping the chimney, adding a roof over the front stoop, reshingling the entire roof, painting the outside of the house, and putting hose bibbs in the front and the rear of the house. In addition, the contract called for extensive work inside the house, replacement of sheetrock, installation of insulation, congoleum, carpeting, paneling, cabinets, new kitchen and bedroom appliances, a new central heating system, and numerous other improvements and repairs. The contract price totalled $18,600, including $2,071 for a utility room. ("Remove back porch and drop flooring to allow enough height to construct 8 foot by 8 foot utility room ... inside walls unfinished ...") Petitioner's Exhibit No. 1. Exclusive of plumbing, electrical, heating, and the utility room, the value of the repairs and renovations exceeded $200.00. As "Stratton Const." respondent contracted with Williams Plumbing Co., Inc. (Williams) on September 8, 1986, to re-pipe, install a working machine drain and furnish a water closet. Respondent's Exhibit No. 3. Respondent or Williams on his behalf obtained a plumbing permit from the City of Jacksonville, No. 25997, at or about the time Williams began work, but Williams "left town" (T.43) before the project was inspected by the City. On October 2, 1986, respondent contracted with Wayne Conn Plumbing (Conn) to do additional plumbing work. In order to obtain a plumbing permit for the additional work, respondent cancelled the first permit. (T.34) The same day he signed the contract with Conn, respondent obtained a second plumbing permit, No. 28215. Respondent's Exhibit No. 1. Conn finished the plumbing work, and it passed inspection by the City. Earlier, on September 5, 1986, respondent or a subcontractor obtained a City permit authorizing electrical work at 5017 Pearl Street. On October 8, 1986, respondent or a subcontractor obtained a mechanical permit for the house's new heating system. In due course, the work authorized by these permits passed City inspections. Petitioner's Exhibit No. 7. Before he began work on the Cobb's house, Mr. Stratton had only built new homes in Florida. He was unaware of any requirement to obtain a permit to effect repairs to the interior of a house other than those he did in fact obtain. He was aware, however, of the need to secure a building permit for construction of the utility room, involving, as it did, alterations to the foundation. Nevertheless, he only applied for this permit on June 11, 1987, long after the work had been completed, and after he had become embroiled in a dispute with the Cobbs. Jacksonville's Building Code, Part 4, makes it unlawful to begin work to contract, enlarge, alter, repair, move, remove or demolish a building or structure, or a part thereof ... without having first filed an application with and obtained a permit therefor from the Building official, except that, for general maintenance or repairs, not involving replacement of components specifically requiring permits, which do not change the occupancy or affect the electrical, plumbing or mechanical systems, the value of which does not exceed two hundred dollars ... no permit shall be required ... Petitioner's Exhibit No. 4, p. 5. In beginning work without a permit to remove the back porch or to replace it with a utility room or to effect general repairs the value of which exceeded two hundred dollars, respondent violated applicable provisions of a local building code. The evidence suggested that the requirement that contractors obtain permits to effect general repairs with a value in excess of two hundred dollars is more honored in the breach than in the observance. In fact, respondent testified that somebody told him no permit is needed "if you don't change the size of the building," (T.46) i.e., alter the foundation. The Building Code also calls for mandatory inspections of foundations and framing as they are completed, but a building inspector testified that inspection of pre-formed concrete piers like those on which the utility room stands would have been foregone. Because the addition stood on (new) piers and because its interior walls remained unfinished, it was possible for the City to inspect both the foundation and the framing, even after the work was finished. John Carlton Sturdevant, a field inspector for Jacksonville's Building and Zoning Department, saw nothing wrong with the framing, nor was there evidence of any problem with the foundation.
The Issue Whether Gar-Con's revised application for a permit to construct a sewage plant, and soakage trenches to dispose of the effluent, should be granted?
Findings Of Fact Eight to ten miles south of Melbourne Beach and 8.3 miles north of Sebastian Inlet, Gar-Con plans to develop a parcel of land stretching west from the Atlantic Ocean, across Highway A1A, to the Indian River. Gar-Con expects to build a motel and residential complex complete with tennis courts, parking garage, water treatment plant and the sewage treatment facility for which a construction permit is sought in these proceedings. The sewage treatment plant would be built on a site 480 feet west of Highway A1A and 90 feet south of Gar-Con's northern property line, at an elevation of 11 or 12 feet above mean sea level. Ocean Way Water and Sewer Association, Inc. is to be organized as a nonprofit corporation to own and operate the wastewater treatment facility. The Public Service Commission, through the director of its water and sewer treatment, has taken the position that the proposed "sewer system will fall within the exemption described in Section 367.022(7), Florida Statutes." DER's Composite Exhibit A. PACKAGE PLANT PROPOSED The facility Gar-Con proposes is designed to treat 100,000 gallons of sewage daily, which is the estimated "total flow" (T. 75) the sanitary engineer who designed the system anticipates from the development. Sewage generated by the development would flow to the plant, through a bar rack designed to remove rags and other large objects, and into aeration tanks where, over a 24 hour period, interaction with air and a biological mass would supply oxygen and cause the formation of biological floccules. The flocculant sewage would then move to a clarifier hopper. During its five hour stay there, solids which were not earlier segregated as the sewage moved over a weir into the clarifier, would be precipitated and removed. The clear, residual liquid would be pumped through one of two sand filters (each of which would also have granular activated carbon and be capable of filtering 100,000 gallons daily) into one of two chlorine contact chambers where a gas chlorinator would introduce chlorine for an hour. Under ordinary circumstances, the chlorinated effluent would then be pumped into one of two soakage trenches. The soakage trenches, each designed for use every other week, are to be gravel-filled ditches covered over first with felt paper, then with compacted fill. The gravel would lie at least one foot beneath the surface of the ground in a space ten feet wide and three feet deep stretching the 940 foot length of each soakage trench. Punctured like sieves, two six-inch PVC pipes would run through the gravel, sweating effluent from their pores. There is also a plan to dig a percolation pond or grassed swale five feet deep, 120 feet long and 80 feet wide near the wastewater treatment plant, which could serve as a receptacle for effluent, in case of "a 1:10 year storm or when the filters are down and/or if soakage trenches would need repair." Gar- Con's Exhibit 2-A. It would hold about 100,000 gallons. The solids caught by the weir, those extracted in the clarifying process, and those recovered from backwashing the filters would serve as catalyst for the aeration process as needed. Excess sludge, about 3,000 pounds monthly, would undergo "aerobic digestion," before being removed to Brevard County's Central Disposal Facility on Adamson Road, for disposal there. Gar- Con's Exhibit No. 7. Primary and secondary drinking water standards would be met by the effluent as it left the plant (although the engineer who designed the system would not drink the effluent himself), except that, from time to time, nitrate concentrations might reach 12 milligrams per liter, and except in the "event that a homeowner might put some type of [inorganic toxic or carcinogenic] material into the sewer system." (T. 86) The biological oxygen demand (BOD) would be ten milligrams per liter; suspended solids would probably amount to about five milligrams per liter; pH would probably be slightly under seven; nitrates would average approximately eight milligrams per liter but would "peak out at certain times during the year, for maybe extended periods up to two months, at twelve milligrams per liter," (T. 80); and there would be a chlorine residual after 60 minutes of two milligrams per liter. AMBIENT WATERS There would be no direct discharge to the Atlantic Ocean, Indian River or any other body of surface water, nor would any indirect effect on surface waters be measurable. No body of surface water lies within 500 feet of the site proposed for the plant and soakage trenches. Potable groundwater underlies the site; the groundwater table slopes toward the Atlantic Ocean, 9.5 to 12.5 feet below ground. "[D]uring the traditional rainy season," Gar-Con's Exhibit 2B, Attachment, p.3, the groundwater may rise to within seven feet of the surface. The PVC pipes in the soakage trenches are to be placed two and a half feet deep. As effluent percolated through the sandy soil, there would be "mounding" of the groundwater underneath the soakage trenches, and dispersal in all directions. Surface flow is to be diverted from the soakace trenches so that only rainwater falling directly on them would percolate down through the gravel beds. Taking soil characteristics into account, and assuming a "water table depth" of 20 feet, an engineer retained by Gar-Con predicted that "the maximum expected groundwater rises beneath the east and west trenches are 2.4 and 2.1 feet, respectively under a loading of 100,000 gpd for a period of 7 days." Gar-Con's Exhibit No. 3. The water table depth, "the height, the top of the groundwater from the first restrictive layer," (T. 172), is probably more like 40 feet than 20, which accounts in part for the "conservatism" of the mounding predictions. Under very severe weather conditions (a 100 year storm), groundwater would rise as high as the bottom of the trenches making them unavailable to receive effluent, but the effluent would not be forced above ground. In a 100 year flood, water would be expected to rise to seven feet above mean sea level. Under such conditions, people could be expected to evacuate the area. In a 25 year storm, the system could be expected to continue to function. Groundwater to the north and east of the proposed site was sampled, and the samples were analyzed. The water to the north had 380 milligrams of chlorides per liter and the water to the east had 450 milligrams of chlorides per liter. As it left the proposed treatment plant, the effluent would contain approximately 150 milligrams of chlorides per liter. SOUND AND LIGHT Lights like those used as street lights are to be installed at four places in the wastewater treatment plant. A timer, which can be overridden, would turn the lights on at dusk and off at eleven o'clock at night. The lights would illuminate the plant adequately. Pumps would move sewage to and through the proposed plant. Most of the pump motors would be submerged and unable to be heard. Two electric blowers, a flow meter and a totalizer would also have electrical motors. The blowers and the blower motors are to be equipped with insulated fiberglass covers and the blowers would also have intake and double outlet silencers. Four feet from the plant the noise of the motors would be comparable to that of a home air conditioning unit. At the nearest residence the noise level would scarcely exceed background noise. At hearing, Gar-Con revised its application and agreed to install an emergency generator which would also be encased in insulated housing and is to be equipped with a muffler. AEROSOL AND ODOR Unless the proposed plant loses electric power for 24 hours or longer, no offensive odors would emanate from it. The bar rack and weirs would be regularly hosed down. Against the possibility of a power failure, Gar-Con agreed at hearing to install permanently an emergency generator with sufficient capacity to keep both the wastewater treatment plant and the water treatment plant it plans to build operable. No aerosol drift is foreseen. The surface of the liquid In the aeration tanks would be 1.4 feet below the top of the rim. Walkways four feet wide along the inside perimeters of the aeration holding tanks would prevent dispersal of most of aerosol. A decorative hedge around the treatment plant, which would eventually be 15 feet high, is a final fail-safe. WELLS To the north are two shallow wells within 500 feet of the site proposed for the wastewater treatment plant. Both wells belong to Kel Fox, who wrote Gar-Con that he had no objection to their proposed wastewater treatment facility in light of Gar-Con's agreement to furnish drinking water to existing facilities on his property and reimburse him expenses incurred in disconnecting the two shallow wells. Gar-Con's Exhibit 2E. There is a deep well within 500 feet to the south. DER and Gar-Con have entered into the following stipulation, dated September 2, 1983: Existing Wells. Prior to the operation of its waste water treatment plant, Gar-Con will offer to supply drinking water at a reasonable cost to owners of property on which are located operational or approved shallow drinking water wells that are within 500 feet of Gar-Con's land application site. Gar-Con will make this offer to all such owners known to it prior to the operation of its plant. Gar-Con will further offer to provide reasonable compensation to such owners to disconnect their shallow wells. Gar-Con will endeavor to arrange for provision of drinking water to these owners and the disconnection of those wells prior to the operation of its plant. Future Wells. Should nearby individual (non-corporate) property owners propose to construct shallow drinking wells located within 500 feet of Gar-Con's land application site after Gar-Con begins operation of its waste water treatment plant, Gar-Con also will offer to supply them with drinking water at a reasonable cost and to provide reasonable compensation to them to disconnect those wells. However, Gar-Con shall have no obligation to make any such offer to owners of future wells if sampling of monitoring wells located at or near its external property line indicates that the groundwater meets the primary drinking water standards and, after July 1, 1985, the secondary drinking water standards listed in Florida Administrative Code Rule 17-22.104. Gar-Con agrees to record a master notice of restriction barring future owners of lots within the Ocean Way development, which are owned by Car-Con at the time of permit issuance, from installing shallow drinking water wells on such property or otherwise using the shallow aquifer beneath their property as a source for irrigation or for potable water, so long as use of the proposed sewage disposal system continues, and the Department has not found that this restriction is unnecessary. This restriction, which shall be a covenant running with the land, further shall require future owners to purchase water from Gar-Con or any successor owner of the development's water system if Gar-Con or the successor provides water service. These restrictions also shall be contained in all other appropriate documents of title. In addition, Gar-Con plans to create a non-profit water and sewer association to own and control the development's water and sewer system. Gar-Con will include in the Articles of Incorporation of this association a requirement that all property owners served by the system must be members of the Association. Gar-Con is entitled to a zone of discharge extending to its current property line with the exception that the zone of discharge shall not include the area contained within a 100' radius of Gar-Cons's proposed water supply wells. DER Staff concurs that the above conditions, in conjunction with the sewage treatment and disposal system and the groundwater monitoring program proposed by the applicant, to meet the requirements of Chapter 17-4, F.A.C. will provide reasonable assurance that existing and future off-site and on-site property owners will be protected from any adverse effects that might result from the operation of the proposed sewage treatment disposal system. Petitioner's Exhibit No. 10. There are to be a half dozen monitoring wells to allow sampling of the groundwater at strategic points in the shallow aquifer. NATURAL RESOURCES Turtles nest in the general vicinity but off the site of the proposed project. Construction and operation of the proposed waste water treatment facility would have no impact on the turtles apart from making it possible for more people to live closer to where they nest.
The Issue The issue is whether Respondents committed an act of discrimination based upon familial status against Petitioners in violation of the Florida Fair Housing Act.
Findings Of Fact Petitioners own Unit L-105 at The Collins, located at 6917 Collins Avenue, Miami Beach, Florida 33141. Petitioners have a three-year-old daughter who resides with them and claim membership, for purposes of alleging discrimination under the Florida Fair Housing Act, in the class of familial status. Petitioners have exclusive use of their private patio, a limited common element, adjacent to their ground floor unit, subject to the terms and conditions, as well as the rules of the Association. This patio is in close proximity to the Association’s ungated common swimming pool. Unlike most of the condominiums on floors above the pool area, Petitioners’ unit does not have a glass protective barrier on their patio, or any barrier whatsoever installed outside their unit by the Association. All of the units located above Petitioners’ unit that have balconies that are raised from the pool’s surface in heights varying between the second floor and many floors above, without a glass barrier at the end of the balconies, would have a significant and dangerous drop to the pool level for anyone stepping over the edge. Petitioners owned Unit L-105 for 13 years before having a daughter, now three years old, which changed their status to familial for the past three years. Petitioners sought to have the Association allow them to install a glass barrier between their patio and the ungated pool in order to end their claim of discrimination based upon familial status and protect their daughter from accidentally falling into the pool if left unattended on the patio. Respondents refused to install or allow the installation of a glass barrier on Petitioners’ patio, citing that it would not conform with the rules and regulations of the condominium association concerning the common elements of the condominium. Petitioners installed what they called a “temporary” fence around their patio. The fence involved the drilling of holes into the concrete surface of the pool deck and installing posts and netting into the holes to create a fencelike barrier. Claiming this was not approved and not in conformance with the rules and regulations for the common elements of the condominium, the Association brought in workers who removed the fence, the posts, and filled in the holes that had been drilled into the concrete. The Association billed Petitioners $1,200 for having the removal and repair work done for the unapproved installation of the fence. At some point, after the fencing had been removed, Petitioners moved out of their condominium unit, but remain the owners of it. At the time of the hearing, Petitioners had pending in circuit court an action regarding the pool fence. No further details were given regarding the nature of the action and relief sought. Mr. Riveiro testified that he and his wife are willing to bear the cost, including any needed permits, parts, labor, and inspections for installing a temporary fence that will protect their daughter from accidentally falling into the pool. Mr. Blanco, the Association’s board president, who has served on the board of the Association for 15 or more years, testified that, during his tenure, the board has never discriminated against persons for any reason, including based upon their familial status. Respondents offered several solutions to Petitioners, including allowing a temporary fence that could be easily removed, but did not involve drilling holes in the common area of the pool deck. According to the local code enforcement officials, all that is required for garden or pool level doors that open to an “ungated pool” are door alarms to alert the occupants when the door is opened from inside or out. Mr. Riveiro testified that he could not use door alarms and keep his doors open to enjoy the breeze and fresh air because, after a time, the alarms sounded to remind the occupants the door has been left open. Because of this, Petitioners were not satisfied with setting up an internal fence that would keep their daughter from running out the door. An internal fence was superfluous since always keeping the doors closed avoids the need for a fence, but restricts Petitioners full use and enjoyment of their unit. If the residents wanted fences to be installed on the pool level, they would have to be uniform in design and function. Because this would be considered a material alteration to the common elements, 75 percent of the unit owners would have to vote in favor of such a change. A material alteration to the common elements was neither requested by Petitioners nor voted upon by the Association’s unit owners upon request from any individual, family, or the Association board itself.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Florida Commission on Human Relations enter a final order finding Respondents not liable for housing discrimination and dismissing Petitioners’ Petition for Relief. DONE AND ENTERED this 22nd day of April, 2021, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 2021. COPIES FURNISHED: Tammy S. Barton, Agency Clerk Florida Commission on Human Relations 4075 Esplanade Way, Room 110 Tallahassee, Florida 32399-7020 Darrin Gursky, Esquire Gursky Ragan, P.A. 141 Northeast 3rd Avenue Miami, Florida 33132 Cheyanne Costilla, General Counsel Florida Commission on Human Relations 4075 Esplanade Way, Room 110 Tallahassee, Florida 32399-7020 Fernando Riveiro 14838 Southwest 35th Street Davie, Florida 33331 Mayelin Perez 4495 Southwest 67th Terrace, No. 207 Davie, Florida 33314
Findings Of Fact The proposed project involves tidal wetlands north of Atlantic Boulevard and west of the intercoastal waterway in Duval County, Florida. The proposed dredging would result in the permanent elimination of approximately 68,000 square feet of productive Juncus roemerianus marsh. The salt marsh at this proposed project site is a healthy system, serving as a nursery and feeding habitat for a variety of aquatic organisms. The salt marsh further serves in a filtrative capacity, thereby acting as a nutrient and pollution trap. Filtrative and recycling properties would be completely removed if the area were dredged. The flora of salt marshes provides the primary source of food in estuaries by producing detritus, which is utilized by a variety of consumer organisms. The project would eliminate such flora and thus cause a change in the aquatic community. The expected resultant community would be less desirable than the present community. Species of wildlife expected to utilize the site include the great blue heron, little blue heron, Louisiana heron, great egret, snowy egret, green heron, yellow-crowned night heron, black-crowned night heron, black rail, clapper rail, king rail, osprey, seaside sparrow, marsh rabbit, raccoon, Florida mink, and Eastern diamondback terrapin. Additionally, representative species dependent upon estuarine salt marshes for feeding, spawning, nursery, and refuge habitat include the Atlantic menhaden, Atlantic croaker, Southern flounder, spotted seatrout, juvenile tarpon, penaeid shrimp, and blue crab. Thus, the salt marsh at the project site provides a valuable habitat for a variety of fish and wildlife organisms, contributes to the production of detritus (a rich source of energy which supports the complex estuarine food web), and further contributes to the maintenance of Water Quality by filtering nutrients, sediments, and other pollutants from and upland runoff. The removal of the marsh at the project site would have a negative impact on the immediate area, contrary to the public interest. Additionally, the cumulative impact of the removal of commercially and biologically valuable marshes such as exist at the project site would ultimately result in a decline in fish and wildlife populations in addition to eliminating any such area's ability to naturally filter nutrients and pollutants entering or existing in the water body attendant to the salt marsh. The proposed project will cause short-term violations of the turbidity standard found in Section 17-3.05(2)(d), Florida Administrative Code (Supp. No. 81). Frequent maintenance dredging in the proposed canal will be required. The short-term violations that will occur during the initial dredging and during the subsequent maintenance dredgings will, on a cumulative basis, cause a long-term violation. The increased water depth caused by the dredging will cause inadequate flushing of the water body, resulting in long-term violations of dissolved oxygen and biochemical oxygen demand standards found in Sections 17- 3.05 (2)(e) and E)(Supp. No. 81), and 17-3.09(3)(Supp. No. 35), Florida Administrative Code. Such violations will further be increased on a short-term basis during the initial dredging activities and during maintenance dredgings. Flow in the existing creek will be altered by the artificial topographic discontinuity, causing a flow reduction. The flushing activity between the proposed channel and the receiving body of water will be substantially decreased, thereby causing solids suspension in the water column, impeded sunlight penetration, and turbidity. Pollutants would likely be absorbed by the suspended solids and be retained in the water column. Further, deleterious and toxic substances are likely to be generated and trapped in the channel. Although the area involved in the proposed project may be negligible and the loss in wildlife habitat and in filtrative capacity may not be subject to accurate measurement, clearly the proposed project would provide an adverse effect, and any proliferation of such projects would eliminate an essential wildlife habitat, an essential part of the aquatic food chain, and an essential filtration system.
Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED That the Petitioner's application for a dredge and fill permit be denied. RECOMMENDED this 17th day of April, 1980, in Tallahassee, Florida. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of April, 1980. COPIES FURNISHED: C. Ray Greene, Jr., Esquire 2600 Gulf Life Tower Jacksonville, Florida 32207 Ms. Silvia Morell Alderman Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Jacob D. Varn, Esquire Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact The applicant, Island Village Condominiums, prepared and submitted to the Department of Environmental Regulation a completed application for construction of its extended aeration sewage treatment plant. The relative distance and direction from the proposed treatment plant to major bodies of surrounding surface water are depicted in an aerial photograph which accompanied the application. The elevation of the surrounding waters in all directions is 39 feet. When the treatment plant is operated in compliance with its design features, the effluent from the plant will exceed the Department's standards for effluent discharge. The zone of discharge will be confined to the owners' property. Surface waters will not be involved in discharge. There will be no adverse impact upon ground waters. The treatment plant would not create a hazzard to the deep water wells of Point O' Woods Utilities, Inc. The treatment plant, as designed, meets or exceeds the engineering standards established by the Department. The likelihood of geologic subsurface failure is remote. Ground water levels are included on the schematic plan which accompanied the application to the Department. The tops of the holding ponds are above the 100-year flood level. The treatment plant will produce no noticeable odor. No exterior lights are to be used with the plant. The noise from the plant's operation would not travel more than 200 feet. The holding ponds would be more than 120 feet from the nearest surface water. The estimate of the cost is accurate at $98,000. Martin I. Gunn, Inc., is the developer of the property, which is also owned by the corporation, Island Village Condominiums, also known as Island Village of Inverness. The treatment plant will become the property of the home owners association and will be operated by the association from maintenance fees paid by the home owners. Martin I. Gunn/Island Village is not a public utility.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommends that the permit for the construction and operation of an extended aeration sewage treatment plant be issued to Island Village Condominiums subject to the general and specific conditions stated in the Department's original notice. DONE and ORDERED this 19th day of February, 1982, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1982. COPIES FURNISHED: Thomas V. Infantino, Esquire Post Office Drawer. B Winter Park, Florida 32790 Donald F. Perrin, Esquire New Bank of Inverness Building Highway 41, South Post Office Box 1533 Inverness, Florida 32650 William W. Deane, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria J. Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMENDED that the application of Jay Hall for a septic tank permit at Lot 1, Deerwood Estates, Baker County, Florida be DENIED. However, applicant should be given thirty days from date of the final order in this cause to raise the height of the system to Department recommended specifications. DONE and RECOMMENDED this 29th day of April, 1983, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1983.
Findings Of Fact Application 7500165 requested average withdrawal of water of 1,804,750 gallons per day from 4 wells located about a mile east of Highway 41 and a mile north of Apollo Beach. The four wells would be for irrigation of tomato crops on total acreage of 4 acres located in Hillsborough County (Exhibit 1, Testimony of Elsberry and Boatwright). Notice of hearing as to the application was published in a newspaper of general circulation in accordance with statute and rule (Exhibit 3). A letter of objection from Joseph S. Benham, Apollo Beach, Florida, dated November 19, 1975 was submitted to the Water Management District, wherein he expressed concern regarding water shortages and, although he does not seek to totally deny the application, is of the belief that the district must insure sufficient controls and management of irrigation activities so that resources are not wasted, water runoff to drainage ditches is eliminated and renewed justification is given each year for the withdrawal (Exhibit 2). A representative of the District staff established that there would be no violation of statutory or regulatory requirement for issuance of a consumptive water use permit in this case except as to the fact that potentiometric level of the applicant's property would be lowered below sea level as a result of withdrawal. It was agreed at the hearing that a period of thirty days should be granted both parties to formulate a stipulation as to control of runoff. An unsigned stipulation was received from the Water Management District by the hearing officer on March 1, 1976, which provided that the permit would be granted with the following stipulations: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expense install metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. (Testimony of Boatwright, Exhibit 4).
Recommendation That application 8500165 submitted by Elsberry and Elsberry, Inc. Route 2, Box 70 Ruskin, Florida, for a consumptive water use permit be granted with the conditions as follow: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expenseinstall metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. That the Board grant an exception to the provision of Rule 16J- 2.11(4)(e), F.A.C., for good cause shown. DONE and ENTERED this 15th day of March, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Elsberry & Elsberry, Inc. Route 2, Box 70 Ruskin, Florida