Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
IN RE: FLORIDA POWER AND LIGHT COMPANY TURKEY POINT UNITS 6 AND 7 POWER PLANT SITING APPLICATION PA03-45A3 vs *, 09-003575EPP (2009)
Division of Administrative Hearings, Florida Filed:Miami, Florida Jul. 07, 2009 Number: 09-003575EPP Latest Update: Dec. 06, 2018

The Issue The issues are (1) whether the Governor and Cabinet, sitting as the Siting Board, should issue certification to Florida Power & Light Company (FPL) to construct and operate a 2,200 megawatt (MW) nuclear electrical generating facility and associated facilities, including electrical transmission lines, to be located in Miami-Dade County (County), and if so, what conditions should be imposed; (2) whether the Siting Board should direct the Board of Trustees of the Internal Improvement Trust Fund (Board of Trustees) to grant FPL three separate easements over state-owned lands for certain Project features; and (3) whether the Siting Board should approve FPL's request for a variance from section 24-43.1(6), Miami-Dade County Code (MDC), to allow use of the on-site package sanitary treatment 4 plant and other on-site cooling water and wastewater treatment and disposal in lieu of connecting the Project to a public sanitary sewer line for treatment and disposal of these waters by the County.

Findings Of Fact An Overview of the Project FPL is a subsidiary of NextEra Energy, Inc. As a regulated utility, FPL is granted an exclusive franchise by the PSC to provide reliable and cost-effective electric service to customers within its service territory in Florida. FPL's service territory covers all or parts of 35 Florida counties and serves approximately nine million customers. It has 14 electrical generation sites in Florida and an electrical transmission line system of approximately 6,500 miles. FPL proposes to construct, operate, and maintain two new 1,100 MW (net) nuclear electrical generating units (Units 6 12 and 7) and supporting facilities on an approximately 300-acre site (site) within its existing Turkey Point plant property, as well as new transmission lines and other off-site associated linear and non-linear facilities (the Project). This is FPL’s single largest project of this magnitude in over 40 years. The Project includes the following proposed non- transmission line associated facilities: a laydown area; a nuclear administration building; a training building; a parking area; a FPL reclaimed water treatment facility; a reclaimed water pipeline corridor; radial collector well system and associated pipelines; an equipment barge unloading area; corridors for construction access roads and bridges; and a potable water pipeline corridor. The Project also includes the on-Site Clear Sky electrical substation, expansion of the Levee electrical substation, two access-only transmission line corridors, and proposed corridors for the following transmission lines: Clear Sky-Turkey Point transmission line: a 230-kV line from the proposed Clear Sky substation to the existing Turkey Point substation on the Turkey Point plant property; Clear Sky-Davis and Davis-Miami transmission lines: a 230-kV line from the proposed Clear Sky substation to the existing Davis substation in southeast Miami-Dade County, and another 230-kV line from the Davis substation to the existing 13 Miami substation in downtown Miami, just north of the Miami River, in FPL's East Preferred Corridor; Clear Sky-Levee No. 1 and No. 2 transmission lines: two 500-kV lines from the proposed Clear Sky substation to the Levee substation in west Miami-Dade County in the West Consensus Corridor or, as a back-up, in FPL's West Preferred Corridor; and Clear Sky-Pennsuco transmission line: a 230-kV line from the proposed Clear Sky substation to the existing Pennsuco substation in northwest Miami-Dade County, also in the West Consensus Corridor or, as a back-up, in FPL's West Preferred Corridor. FPL has proposed to locate these transmission lines in approximately 88.7 miles of transmission line corridors: 52 miles in the West Preferred Corridor (or 51 miles in the West Secondary Corridor) and 36.7 miles in the East Preferred Corridor. FPL is now seeking certification of the West Consensus Corridor -- a combination of an alternate corridor proposed by MDLPA and FPL's West Preferred Corridor -— as its preferred western corridor. FPL is also seeking certification of the original West Preferred Corridor to serve as a back-up to the West Consensus Corridor should a contiguous right-of-way (ROW) be unable to be timely achieved within that West Consensus Corridor or if a right-of-way cannot be obtained in a cost- 14 effective manner. FPL is no longer seeking certification of the West Secondary Corridor. On April 11, 2008, the PSC issued its affirmative need determination for the Project in Final Order No. PSC-08-0237- FOF-EI. That Order was not appealed and is now final. By that Order, the PSC found that there is a need for the Project taking into account the need for electric system reliability and integrity; the need for fuel diversity and supply reliability; the need for base load generating capacity; the need for adequate electricity at a reasonable cost; and whether the Project is the most cost-effective alternative available. In making its determination of need, the PSC also found that there are no renewable energy sources and technologies or conservation measures reasonably available to FPL which might mitigate the need for Units 6 and 7. The PSC's need determination remains in legal effect and requires annual monitoring of the feasibility of construction of the Project. Reconsideration of that determination is neither permissible nor appropriate in this proceeding. Section 366.93 allows for the PSC's annual reviews and cost recovery for nuclear plant construction. The nuclear cost recovery process includes an annual hearing to review past, current, and subsequent year costs for the Project. The PSC's annual review considers "a detailed analysis of the long-term 15 feasibility of completing the power plant." Fla. Admin. Code R. 25-6.0423(5)(c)5. The PSC has annually approved FPL's requested nuclear cost recovery, and it has recognized and accepted the projected in-service dates for Units 6 and 7 of 2022 and 2023, respectively. In association with the Project, FPL has obtained from the Department an Air Construction/Prevention of Significant Deterioration Permit; Exploratory Well and Dual Zone Monitoring Well Permit; an Underground Injection Control (UIC) well construction and operational testing permit; Federal Aviation Administration (FAA) approvals for the Units 6 and 7 containment buildings; County Unusual Use Approval for a nuclear power plant and ancillary structures and equipment; an amendment to the County's Comprehensive Development Master Plan (CDMP) to allow roadway improvements to accommodate construction traffic; and a County zoning approval for the Radial Collector Well System, Reclaimed Water Treatment Facility (RWRF), and other various requests. Pending approvals for the Project include the Combined Operating License (COL) from the NRC; a Section 404 Dredge and Fill permit from the United States Army Corps of Engineers; and an Industrial Wastewater Permit modification from the Department. FPL has submitted three amendments to its application. The first amendment primarily removed the proposed FPL-owned 16 fill source from the application. The second amendment updated information presented in the original submittal of the application and completeness responses; it did not materially affect the environmental impact analysis or the conclusions presented. The third amendment related to two minor revisions in the previously-submitted groundwater model and corresponding groundwater modeling report. FPL also submitted errata to the second amendment, correcting page and appendix numbering issues. FPL has engaged in an extensive public outreach program for the Project, including among other things, direct mailings, newspaper notices, nine open houses, agency workshops, numerous presentations and meetings, a public survey, periodic e-mail updates to local and state agencies, a website, and toll free telephone number. The public outreach program activities provided the public and agency representatives opportunities to informally voice preferences on transmission line corridor selection and Project concerns. The application was available for public review at seven public libraries and at FPL and Department offices. All notices required by law were timely published by FPL, the Department, and the proponents of alternate transmission line corridors in accordance with section 403.5115 and rule 62-17.281. Proofs of publication were timely provided to the Department in accordance with rule 62-17.281(12). All 17 direct written notices required by law were timely mailed, and lists of landowners and residences notified were timely submitted to the Department in accordance with subsections 403.5115(6) and (7). The Department sent direct mailings for the sovereign submerged lands easements for the radial collector well laterals and Miami River crossing in accord with section 253.115 and rule 18-21.005(3). Plant and Non-Transmission Line Associated Facilities Generally FPL's Turkey Point plant property is located in unincorporated southeast Miami-Dade County, east of Florida City and the City of Homestead, and bordered by Biscayne Bay to the east. The existing 9,400-acre plant site consists of two nominal 400-MW natural gas/oil-fired steam electric generating units (Units 1 and 2), two nominal 800-MW nuclear units (Units 3 and 4), and a nominal 1,150-MW natural gas-fired combined-cycle unit (Unit 5). Units 3, 4, and 5 are certified under the PPSA. Units 1 and 2 pre-date the PPSA and are not certified. The Site for Units 6 and 7 is south of Units 3 and 4 and occupies approximately 300 acres within the existing permitted industrial wastewater facility. Proposed Units 6 and 7 are two 1,100-MW nuclear electric generating units. The principal structures are the nuclear reactors, a containment building, a shield building, an 18 auxiliary building, a turbine building, an annex building, a diesel generator building, and other related buildings. Each unit will include two standby diesel generators, two ancillary diesel generators, and one diesel-driven fire pump. FPL has selected the Westinghouse AP1000 as the plant design for Units 6 and 7. The Westinghouse design has been certified by the NRC as complying with federal regulations. This design incorporates the latest technology and advanced safety features. The NRC oversees the construction, safety, and operation of all nuclear units in the United States, including the transport and handling of nuclear fuel. Construction and operation of Units 6 and 7 require separate approval by the NRC. As part of the federal permitting process for nuclear power plants, FPL submitted a COL application to the NRC. The NRC is currently reviewing that application. As least one party in this case, the NPCA, has intervened in the NRC proceeding and opposes federal approval. The process for obtaining the state site certification under the PPSA is separate from the NRC approval process. Certification is not dependent upon prior issuance of the NRC's approval. In addition to the two reactor units, other Project facilities include six cooling towers with a makeup water reservoir, a blowdown sump, tanks, a sanitary wastewater 19 treatment plant, electrical transformers, and various buildings. A new electrical switchyard/substation, named Clear Sky, will also be located on the Site, and a laydown area will be located on the far western portion of the Site. New nuclear administration and training buildings, along with a parking area, will be located just north of the Units 6 and 7 Site. Other Project-related features to be located within the existing FPL Turkey Point plant property include the RWTF, a portion of the reclaimed water pipeline, radial collector well caissons and delivery pipelines, portions of new access roads to be used during Project construction, a portion of the potable water pipeline, and an equipment barge unloading area. The new units will use reclaimed water supplied by the County as the primary source of cooling water. This water will be supplied by a reclaimed water pipeline and will receive further treatment in the RWTF. That treatment facility will be located northwest of the Units 6 and 7 Site. When reclaimed water is not available in sufficient quantity and quality to meet the Project's water needs, cooling water will be supplied from a radial collector well system to be installed northeast of the Units 6 and 7 Site. The laterals for that well system will extend from the FPL plant property out beneath Biscayne Bay. 20 In accordance with Condition 4 of County Resolution Z- 56-07, as amended by Resolution Z-1-13, FPL will not use the Biscayne Aquifer as a primary source of cooling water for Units 6 and 7. The foundation for the nuclear units will include engineered fill and reinforced concrete that supports the containment building and auxiliary building. Site preparation will require removing the existing muck (organic layer) down to the initial rock layer. This muck is unsuitable for use in the foundation. The Site will then be backfilled with approximately 7.8 million cubic yards of structural fill (aggregate) to a finished grade of approximately 25.5 feet North American Vertical Datum of 1988 (NAVD 88) above mean sea level that will support power plant and ancillary facility construction. The design elevation of the plant floor is 26 feet NAVD 88. An additional three million cubic yards of fill will be required for other plant facilities, including the administration and training buildings and the RWTF. Material from excavation for the Site will be deposited on designated berms within the existing industrial wastewater facility or stock-piled on the Turkey Point plant property for other future uses. FPL will utilize best management practices to prevent erosion and sedimentation impacts during placement of the spoil materials on the berms to 21 protect nearby wetlands and surface waters. FPL will obtain the majority of fill from certified vendors. In accordance with Condition 14 of County Resolution Z-56-07 and Condition 17 of County Resolution Z-1-13, all fill used on the two units and onsite facilities will be "clean fill" as defined in section 24-5, MDC. All fill material will comply with section 24-48.3(4), MDC. FPL has prepared and submitted an earthwork and materials disposal plan to the reviewing agencies, including the County. FPL's earthwork and materials disposal plan is consistent with Condition 7 of County Resolution Z-56-07 and Condition 16 of County Resolution Z-1-13. FPL has fulfilled the requirements of those two conditions. In accordance with Condition 21 of County Resolution Z-56-07, FPL has designed the Project to accommodate water level increases on the order of one foot or more to accommodate potential physical modifications and operational changes to County and State drainage canals. Relative sea level is measured using tide or water level gauges to measure water levels with respect to tidal benchmarks. The hourly water level heights from the tide gauge are averaged to get a monthly or annual average. Using that information, the long-term change in the annual or monthly mean is determined over a period of decades or centuries. Relative 22 sea level is affected by vertical land motion; tectonic uplift; thermal expansion; glacial melt; ocean circulation; wind effects; changes in barometric pressure; and tides and tidal currents. The Project has been designed to accommodate potential sea level rise during the life of the Project. The proposed finish floor elevation at the Units 6 and 7 plant area was selected by FPL based on the calculation of probable maximum storm surge and coincident wind-wave effects. FPL input a conservative estimate of one foot of sea level rise over the life of the plant to the "Sea, Lakes and Overland Surge from Hurricanes" (SLOSH) Biscayne Bay Basin model. The SLOSH model was used to predict a maximum storm surge elevation of 21 feet during a probable maximum hurricane near the Site. The maximum water level at the safety-related structures, including predicted maximum storm surge elevation and estimated storm- related wave run-up, is calculated to be 24.8 feet. The design elevation of the plant floor is 26 feet NAVD 88. Facilities to be located at this elevation include, among other Project components, the reactors, the electrical turbines, and the emergency diesel generators. Impacts on support facilities and services for the Project will be managed through final design and by pre-planning for storm effects. In addition, plant procedures will be focused on nuclear and personnel safety 23 during a hurricane and post-storm recovery. Plant safety- related functions will not be adversely affected by sea level change or storm events. Based on available records from stations throughout the state -- Cedar Key, Fernandina Beach, Key West, Mayport, Miami Beach, Pensacola, and St. Petersburg -— sea level rise throughout Florida is tightly grouped around the level of 0.74 feet per century, with a very small standard deviation of plus or minus 0.07 feet per century. The nearest station with the longest (from 1913 to 2012) continuous sea level record to the Turkey Point Site is the Key West station; relative sea level rise there is 0.75 feet per century. Mathematically, the best explanation for the Key West relative sea level rise is a linear trend. There is no statistically significant evidence of acceleration in relative sea level rise at Key West. Given the available records in the area and the close grouping of values for sea level rise throughout the state, use of Key West records to project sea level rise at Turkey Point is appropriate. FPL used a linear trend method in assessing the relative sea level change for the Project. The linear trend is generally accepted by the scientific community as an appropriate method for evaluating relative sea level change. The sea level rise projections used by FPL are reasonable and conservative. FPL's projection appropriately responds to various assessments 24 on sea level rise. The plant design elevation accounts for more than maximum storm surge plus sea level rise. FPL has provided reasonable assurance that the Project is not contrary to the public interest as it relates to sea level rise. The plant and non-transmission line portion of the Project will be built above the 100-year flood level, and will not increase erosion or create a flood hazard to others. The Project will be constructed outside of the coastal high hazard area to comply with applicable flood protection requirements. The plant and non-transmission line portion of the Project has sufficient operational safeguards to protect the public welfare. The Project will meet the electrical energy needs of the state in an orderly, reliable, and timely fashion. The plant and non-transmission line portion of the Project will not adversely affect the public health, safety, welfare, or property of others. Water and Use Treatment Construction Dewatering Excavation is required to construct the foundations of Units 6 and 7. Concrete diaphragm walls around each foundation excavation will minimize horizontal flow of groundwater into the excavation. In addition, a horizontal grouted barrier constructed below the bottom of each unit to the bottom of the 25 diaphragm walls will minimize vertical flow of groundwater into the excavation. Grout will be injected in a series of "primary" borings. Subsequent borings will then be drilled in between the primary borings. Three sets of borings are possible after the primary set –- secondary, tertiary, and quaternary. Each set is drilled and grout is injected until refusal occurs. Quaternary borings may not be required at all locations, only where continuing seepage is observed as the excavation progresses. The diaphragm walls and grouting will minimize groundwater flow during construction to less than 100 gallons per minute (gpm) per unit, which will be controlled by sump pumps at the bottom of the foundation excavations. Dewatering effluent from construction of these facilities will be routed to the existing industrial wastewater facility or disposed in the underground injection wells. During the three-month grouting process, short-term maximum groundwater withdrawals from each unit will not exceed 1,000 gpm and average withdrawals will be 230 gpm. During the three-month excavation phase, the maximum groundwater withdrawals per unit will not exceed 1,000 gpm and average withdrawals will be about 400 gpm. These short-term withdrawals will be sequential, not simultaneous. During the 24-month foundation construction phase, the groundwater withdrawal rate for each unit will not exceed 100 gpm, and the maximum combined groundwater withdrawal rate (construction of 26 Unit 6 combined with grouting/excavation of Unit 7) will average about 430 gpm. Construction dewatering will not cause adverse impacts to ground or surface water resources. The projected inland groundwater impacts, expressed as drawdown, will not extend beyond the cooling canal system that surrounds the Units 6 and 7 Site or cause a water resource concern. No large-scale or area-wide dewatering is anticipated to be associated with construction of the cooling tower foundations, RWTF, the nuclear administration and training buildings, or parking area. However, local small-scale dewatering of these facilities and onsite pipelines may be required. Dewatering during construction of the radial collector wells will be limited to the caissons, which will be dewatered to allow for horizontal drilling of the well laterals. Construction dewatering will not cause saltwater intrusion into areas where saltwater is not already present. Hydrologic Evaluations and Water Conservation FPL submitted to the County an extensive and comprehensive hydrologic study for the Project as required by Condition 15 of County Resolution Z-56-07. FPL has fulfilled the requirements of that condition. FPL submitted a complete description of all surface and groundwater practices at the existing Turkey Point Plant to 27 the County as required by Condition 16 of County Resolution Z- 56-07. FPL has fulfilled the requirements of that condition. FPL has submitted a water conservation plan for the Project. FPL will implement the County's water use efficiency manual. FPL Reclaimed Water Treatment Facility and Reclaimed Water Pipeline Corridor The Project includes a RWTF. The proposed location for the RWTF is approximately 44 acres in size located northwest of the Site on the Turkey Point plant property. Pipelines will convey the treated reclaimed water from the RWTF to the cooling water makeup reservoir. The RWTF will polish the reclaimed water to remove dissolved solids, nutrients, and mineral content that would otherwise negatively impact the efficient and reliable operation of the cooling reservoir, the cooling towers, and the circulating water system. The treatment provided by the RWTF will allow FPL to utilize reclaimed water to the maximum extent possible. The treated water from the RWTF will comply with applicable Department requirements for use of reclaimed water in cooling towers. Operation of the RWTF and the use of reclaimed water will comply with applicable local government non-procedural requirements. 28 FPL has fulfilled the requirements of Condition 5 of County Resolution Z-56-07 through utilization of reclaimed water to the maximum extent possible and by conducting an evaluation of alternative water sources for the Project. FPL and the County have entered into an agreement for the County to provide the reclaimed water. This reclaimed water use is a beneficial and cost-effective means of maximizing the use of reclaimed water from the County and helps the County meet its reclaimed water compliance requirements. In the absence of reuse opportunities, this treated domestic wastewater would likely continue to be discharged to the ocean or deep injection wells. The County is required to eliminate ocean outfalls and increase the amount of water that is reclaimed for environmental benefit and other beneficial uses. The RWTF will be constructed at an elevation of 14 feet. This elevation is above the 100-year flood elevation of ten feet; will accommodate an additional one foot of increased water levels due to regional hydrologic restoration projects that affect the RWTF site; and will account for one foot of sea level rise. There will be a two-foot reserve capacity above any predicted water levels at the RWTF location. FPL has proposed an approximately nine-mile reclaimed water pipeline corridor for delivery of reclaimed water from the Miami-Dade Water and Sewer Department's (MDWSD) South District 29 Wastewater Treatment Plant to the FPL RWTF. FPL selected the reclaimed water pipeline corridor to utilize, to the greatest extent practicable, existing infrastructure in order to minimize environmental impacts. The reclaimed water pipeline corridor is also co-located with an existing FPL overhead transmission line right-of-way (ROW) for most of its route. The pipeline corridor varies in width from 500 feet to one mile. The pipeline will be installed below ground level the entire length with subaqueous canal crossings. Open cutting or trenching will be utilized for the majority of the reclaimed water pipeline installation. Trenchless technologies will be used when crossing canals. The reclaimed water pipeline will cross several SFWMD canals. When constructing the pipeline, FPL will avoid as much as practicable Biscayne Bay Coastal Wetland parcels, avoid longitudinal runs in the L-31 E canal right-of-way, and will use subaqueous crossings of SFWMD canals. All reclaimed water pipeline canal crossings will be located, designed, and constructed consistent with applicable SFWMD non-procedural requirements, including the Criteria Manual for Use of Works of the District. Radial Collector Well System The radial collector wells will be used as a backup source of cooling water. Radial collector wells have been used since the 1920s in commercial, industrial, and power plant 30 facilities, including another nuclear power plant. The wells will consist of four central caissons located on the Turkey Point peninsula. Up to 12 laterals will be directionally drilled from within each of the caissons horizontally at a distance of up to 900 feet beneath Biscayne Bay and at a depth of approximately 25 to 40 feet below the Bay bottom. The laterals will not extend beneath Biscayne National Park (BNP). The wells will be designed, sited, constructed, and operated to induce groundwater recharge from Biscayne Bay. FPL has agreed to a condition of certification that would limit operation of the radial collector wells to 60 days in any consecutive 12-month period. When using 100 percent salt water or saline water (based on 1.5 cycles of concentration in the cooling water system's cooling towers), Units 6 and 7 will use a maximum of 124.4 mgd. Each of the four wells will have a design capacity of 43.2 mgd. Operation of three wells will meet the plant make- up requirements, with the fourth well acting as a back-up. The caissons for the radial collector wells will be installed within previously-filled upland areas of the Turkey Point peninsula. Construction of the radial collector wells will not result in any discharges to Biscayne Bay, other than construction-period stormwater run-off. Sedimentation barriers 31 or other best management practices will be implemented to limit potential impacts to surface water bodies. The radial collector well laterals will be constructed using conventional rotary-type horizontal drilling with the drilling fluid consisting of formation water. The drilling will occur from inside the concrete caisson. The directional drilling for the laterals is designed to avoid "frac out," a situation where drilling mud enters a surface water body via a fracture or solution channel. Construction of the radial collector wells will not require dredging in Biscayne Bay. The radial collector wells will be constructed and operated in accordance with all Department, SFWMD, and local government applicable non-procedural requirements related to well construction and monitoring. No explosives will be used during construction of the plant and non-transmission line portion of the Project, including during construction of the radial collector wells. The radial collector well easement area is in the Biscayne Bay Aquatic Preserve. The radial collector well area includes the portion of the radial collector well system that will extend beneath State-owned submerged lands in Biscayne Bay. The Department's Division of State Lands reviewed the information submitted by FPL regarding the radial collector well sovereign submerged lands easement and concluded that the 32 Project is in the public interest. The Division of State Lands recommended that the Siting Board direct the Board of Trustees to issue the sovereign submerged lands easement for the radial collector well system. FPL owns the upland area adjacent to the requested easement for the radial collector wells. The radial collector wells will be designed and constructed to avoid restriction or infringement on riparian rights of adjacent upland landowners. Construction and operation of the radial collector wells is a water-dependent activity. By the nature of the design and location, the radial collector well laterals cannot be reasonably constructed without going under the Biscayne Bay Aquatic Preserve. The radial collector wells are "structures required for the installation or expansion of public utilities" and "reasonable improvements for public utility expansion," and are therefore specifically allowed by the Act that created the Biscayne Bay Aquatic Preserve. See § 258.397, Fla. Stat. Construction and operation of the Project, including the radial collector well system, is consistent with the Biscayne Bay Aquatic Preserve Management Plan and is in the public interest. 33 Groundwater Modeling FPL has conducted extensive groundwater modeling of the predicted impacts of the groundwater withdrawals associated with operation of the radial collector wells to supply cooling water. That modeling utilized the MODFLOW 2000 computational system. To support this modeling effort, FPL undertook an aquifer performance test (APT) at the Turkey Point peninsula to provide information on the potential yield from the water bearing units and to identify changes in existing water levels and water quality during pumping in the shallow aquifer at the location of the radial collector wells. The APT was undertaken in accordance with professional standards. MODFLOW 2000 was developed by the United States Geological Survey. It is a widely accepted computer code for groundwater modeling. The groundwater modeling was conducted consistent with the applicable SFWMD non-procedural requirements. The steady-state, constant-density, and three- dimensional groundwater model used conservative assumptions to produce an environmentally conservative assessment of potential environmental impacts. In assessing the potential impacts associated with operation of the radial collector wells, the model considered water levels prior to radial collector well operation, water 34 level changes as a result of operating the radial collector wells, seabed approach velocity, and a breakdown of the sources of water that will be withdrawn by the radial collector wells. Seabed approach velocity is the velocity of the water just prior to entering the seabed above the radial collector wells. The results of the groundwater model predict that the radial collector wells will withdraw water from a saltwater or saline aquifer that will be recharged from Biscayne Bay. FPL's model predicted that: (1) approximately 97.8 percent of the aquifer recharge will originate from boundaries representing Biscayne Bay; (2) approximately two percent will originate from boundaries representing the cooling canal system; and (3) approximately 0.2 percent will be from boundaries representing precipitation onshore. The modeling indicated that operation of the radial collector wells will not cause water from the existing cooling canal system to enter Biscayne Bay. The seabed approach velocity is predicted to be a maximum rate of 0.00002 feet per second overlying the laterals. To put this in perspective, a one-foot, wind-driven wave on Biscayne Bay in five to six feet of water can induce a velocity of approximately one foot per second near the Bay bottom. This wave velocity is about five orders of magnitude greater than the velocity predicted to be induced by the radial collector wells. Additionally, the United States Environmental Protection 35 Agency's (EPA) benchmark for regulating potential impingement of species from intake structures that draw directly from the water column is 0.5 feet per second. This is 25,000 times higher than the seabed approach velocity predicted for the radial collector wells. In terms of the predicted effect of operation of the radial collector wells, the maximum drawdown in groundwater levels of three feet occurs near the radial collector well laterals, located 25 to 40 feet below the Bay bottom. This drawdown reduces to one foot at a distance of 1,500 feet from the radial collector well caissons, and this level of drawdown is confined to off-shore of the Site. The 0.1 foot drawdown contour extends on-shore a maximum of 3,000 feet. Radial Collector Well Potential Impacts FPL's proposed water uses will not cause harm to wetlands or other surface waters or cause pollution of water resources or degradation of surface or ground water quality. Some of the areas contributing precipitation recharge to groundwater west of the radial collector wells contain wetlands. Water contributed to the radial collector wells from these areas is captured as it flows under natural conditions toward the coast. This water is not induced to flow from these areas by the operation of the radial collector wells; it would flow from these areas regardless of whether the radial collector 36 wells were pumping or not. The operation of the radial collector wells will not have an adverse impact to these wetlands. Construction and operation of the radial collector wells will not adversely impact the ambient water quality of Biscayne Bay, including the Biscayne Bay Aquatic Preserve and BNP. Construction and operation of the radial collector wells will not cause saltwater intrusion into areas where saltwater is not already present. FPL conducted extensive simulation modeling of the potential salinity impact to Biscayne Bay from operation of the radial collector wells using a regional hydrodynamic model. The model used a bounding approach, simulating operation of the radial collector wells at drawdown rates both below and well above the design flow rate as sensitivity analyses. At the design flow rate, the model predicted that any changes to salinity in Biscayne Bay caused by operation of the radial collector wells would be immeasurable and imperceptible. Even at a simulated rate of 850 mgd, or nearly seven times the design flow rate of the radial collector wells, the predicted change in salinity in Biscayne Bay would be very slight. Operation of the radial collector wells will not adversely impact salinity levels in Biscayne Bay. 37 The design of the radial collector well system minimizes adverse impacts to fish and wildlife habitat, including endangered and threatened species habitat, and other natural or cultural resources in Biscayne Bay, including Biscayne Bay Aquatic Preserve. Operation of the radial collector wells will not interfere with the ecology and aquatic life, regional fisheries, and recreational uses of Biscayne Bay. Construction and operation of the radial collector wells will not adversely impact fish and wildlife, including threatened and endangered species, or their habitats. FPL evaluated the potential entrainment and impingement impacts of the radial collector well system using particle drift modeling. The modeling considered conservatively bounded scenarios to evaluate potential impacts under varying levels of drawdown and natural environmental conditions. The modeling predicted that at the design flow rate of the radial collector wells, the expectation of entrainment and impingement impacts associated with the radial collector wells is zero. Even at 350 mgd, or more than double the design flow rate, the model predicted no entrainment or impingement of organisms. Operation of the radial collector wells will not result in impingement or entrainment of larvae or other biological particles. 38 FPL conducted a six-month long replicated mesocosm study to determine the impacts, if any, to seagrasses associated with the operation of the radial collector well system by simulating the downward movement of water into seagrass sediments. Mesocosms are generally accepted by the scientific community as an appropriate and accurate method of evaluating impacts to seagrasses. The study conservatively tested the potential stress to seagrass for three months, or one month longer than FPL would normally be allowed to operate the radial collector wells in any 12-month period. The results of the mesocosm study showed that operation of the radial collector wells could result in a 95 percent reduction in porewater nutrient concentrations. Despite that potential reduction, there was no evidence of an adverse impact on seagrass productivity. Leaf turnover rates fell within the range of values expected for healthy seagrass meadows and cumulative biomass production rates showed that the seagrass continued to grow over the course of the entire experiment. There was no evidence of reduced cumulative biomass production rates. Results during the recovery period of the experiment showed that porewater nutrient concentrations were capable of increasing to the higher levels found prior to the imposition of the downward flux of waters into the bottom sediments. 39 Construction and operation of the radial collector wells will not adversely impact submerged land resources, including seagrasses and other benthic resources, and will not impact the County's potable water wellfields. Those wellfields are not within the area impacted by the withdrawals. The radial collector wells are compatible with and will not detract from or adversely affect the natural conditions, propagation of fish and wildlife, and traditional recreational uses of Biscayne Bay, including Biscayne Bay Aquatic Preserve. Because the radial collector wells will not have an adverse impact on Biscayne Bay Aquatic Preserve, they will not contribute to a cumulative impact on the Preserve's natural system. FPL has a demonstrated need for the proposed water uses. FPL has provided reasonable projections of the Project's water needs, quantities, and sources. FPL has legal control over the Project site and facilities, and the proposed uses of water are compatible with the current land use at the Project site. FPL has a demonstrated demand for an alternative secondary or back-up cooling water source to be provided via the radial collector well system. FPL's proposed water uses are not inconsistent with SFWMD-established minimum flows and levels and will not withdraw 40 water reserved under chapter 40E-10. They will not be harmful to water resources. They are reasonable-beneficial uses, will not interfere with present existing legal users, and are consistent with the public interest. The water withdrawals will not harm off-site land uses. The Department, FWC, and SFWMD have proposed conditions of certification requiring monitoring of the impacts of the radial collector well system. FPL has agreed to those conditions as reflected in stipulations of the parties. FPL and the County have also stipulated to imposition of radial collector well system monitoring conditions. FPL's compliance with these agreed-upon conditions of certification fulfills its obligations under Conditions 3 through 12 of County Resolution Z-1-13. Potable Water and Potable Water Pipeline Potable water from the MDWSD will be used as makeup water for the service water system (SWS) cooling system. The SWS is a much smaller system that dissipates heat from reactor components. Unlike the collector well system that can be designed to use saltwater or freshwater, the SWS must use freshwater. Assuming four cycles of concentration, the normal amount of potable water needed for the SWS is 0.7 mgd. The SWS normal water use is approximately one percent of the total plant water use when the collector well system is using reclaimed 41 water and approximately 0.6 percent when using saltwater. Potable water will also be used for the potable water system, fire protection system, de-mineralized water treatment system, and other miscellaneous uses. The normal total amount of potable water needed for the Project is 1.3 mgd, including the water used in the SWS. The maximum amount of potable water needed is 3.7 mgd, including the SWS, potable water system, de-mineralized water system, equipment/floor washdown, and fire water system. It is highly unlikely that all of these streams will be at maximum capacity at the same time. Potable water will be delivered to the Site via an approximately nine-mile proposed pipeline that will connect to the County potable water supply system. The potable water pipeline ROW will be located within or adjacent to existing or planned roads and ROWs. Typically, pipe installation takes place by excavation and backfill techniques. SFWMD canals will be crossed by the potable water pipeline. Pipeline crossings of SFWMD canals will be located, designed, and constructed consistent with applicable SFWMD non- procedural requirements, including the Criteria Manual for Use of Works of the District. 42 Wastewater Disposal During the construction phase of the Project, wastewaters including dewatering effluent will be disposed by the injection wells or released to the cooling canal system. Construction site stormwater will be released to the cooling canal system. The cooling canal system is an existing permitted industrial wastewater facility. These releases will not cause adverse impacts to water quality. During operation, the major wastewater streams associated with the Project are the circulating water system blowdown, the service tower blowdown, and effluent from the de- mineralized water treatment system. These and other smaller wastewater streams, except stormwater, will be collected in a lined blowdown sump along with other Project waste streams and then will be discharged to the deep injection wells. Operation of Units 6 and 7 will not utilize the existing industrial wastewater facility for cooling or wastewater disposal, except that stormwater will be routed to this facility. The Project will not result in any discharge of industrial wastewaters to any jurisdictional surface waters during construction or operation. Construction and operation of the Project will not cause or contribute to violations of any applicable state and local surface or ground water quality standards. 43 It is not technically feasible to reuse Project wastewaters for discharge to the Biscayne Bay Coastal Wetlands Project. In accordance with Condition 6 of County Resolution Z- 56-07, FPL has prepared and submitted documentation comprising a wastewater discharge plan to the reviewing agencies, including the County. Underground Injection Well System The proposed underground injection well system consists of 12 or 13 Class I industrial deep injection wells and six or seven dual zone monitoring wells. At least two of these injection wells will serve as back-up wells. These injection wells will be designed to meet applicable injection well design requirements, including incorporating measures to protect the wells against corrosion or damage resulting from native groundwater and the injected fluids. The wells will be periodically tested for mechanical integrity. The underground injection wells will dispose of Site wastewaters into the Boulder Zone, which is within a geologic formation known as the Oldsmar formation approximately 3,000 feet below land surface. The water in the Boulder Zone has salinity close to that of sea water. The Boulder Zone is used extensively to dispose of wastewaters in Florida. 44 The Boulder Zone is located deep underground and separated and confined from the shallower aquifers that are classified and used as underground sources of drinking water in South Florida. The Boulder Zone at the Turkey Point Plant is classified by the Department as a G-IV aquifer because it is a confined aquifer with no potable use and with a total dissolved solids (TDS) content of 10,000 milligrams per liter (mg/L) or greater. Except for a prohibition on injection of hazardous waste, no groundwater quality criteria, including thermal standards or limitations, apply to discharges into the Boulder Zone. FPL analyzed the geology at the Turkey Point property to determine if it was suitable for disposal of wastewater through underground injection by constructing a 3,230-foot deep exploratory well. This exploratory well was authorized by a Department-issued underground injection control (UIC) permit, and it was constructed to the standards for a Class I injection well. On July 29, 2013, the Department issued UIC permit number 293962-002-UC, authorizing FPL to convert this exploratory well to an injection well to dispose wastewaters associated with the construction of Units 6 and 7. This converted exploratory well could also be used to dispose of industrial wastewater after 45 Units 6 and 7 become operational, subject to authorization for this purpose by the Department through another UIC permit. FPL also constructed a dual zone monitoring well approximately 75 feet from the exploratory well, within the 150- foot maximum distance of the Department's UIC rules. The dual zone monitoring well allows for collection of groundwater samples from two separate subsurface intervals. Dual zone monitoring wells help determine whether there is adequate confinement of the injected fluid. Construction of the exploratory well and dual zone monitoring well was in accordance with applicable Department requirements and authorized by a permit. During construction of the exploratory well, FPL conducted testing to determine the appropriate well casing setting depths, confirm the presence of an injection zone, and evaluate the confining characteristics of intervals overlying the injection zone. A report documenting this testing was prepared and provided to Department staff who agreed with the report's information and conclusions. This testing determined that the top of the injection zone occurs at a depth of approximately 2,915 feet below pad level and there is a confining unit of approximately 985 feet above the top of the injection zone. The injection zone is over 1,400 feet below the deepest potential underground source of drinking water as 46 defined by the Department. The injection zone is a confined aquifer with a total dissolved solids concentration greater than 10,000 mg/L. This injection zone is capable of receiving water at the proposed injection rate. Before beginning operational use of the injection wells, FPL will be required to further test the ability of the injection zone to receive the injected fluid. The Department UIC rules required FPL to conduct an "area of review" analysis to ensure that there were no wells, springs, mines, faults, or other geological features that could provide a pathway to allow Turkey Point injected wastewater to migrate upwards into an underground source of drinking water. FPL's area of review analysis found no wells, springs, mines, faults, or other geological features that could provide a pathway to allow the Turkey Point injected wastewater to migrate upwards into a potential underground source of drinking water. The Department reviewed FPL's area of review analysis as part of the exploratory well permit. To further ensure that the geology above the Boulder Zone was sufficient to confine the injected wastewater to the Boulder Zone, FPL performed a confinement analysis by comparing hydrogeologic data collected during the exploratory well testing to data from other injection wells. This data comparison, particularly comparing the sonic logs, demonstrated that the geology above the Boulder Zone has little evidence of 47 fracturing. This is indicative of effective vertical confinement. Finally, although not required by the UIC rules, FPL performed a density-dependent groundwater flow modeling analysis to determine how the injected wastewater would move through the underground formations. This groundwater flow model considered the geology of the area, the differences in the density of the injected wastewater compared to the native groundwater, and simulated a period of 60 years of injection followed by 40 years of no injection for a total of 100 years. The groundwater flow model showed that even after 100 years the injected wastewater did not move out of the confining layer and did not move into any potential underground source of drinking water. Additionally, the injected wastewater will not affect the mechanical integrity of the injection wells, will not jeopardize the integrity of the confining zone, and will not alter the hydrologic characteristics of the injection zone to the point of endangering the underground source of drinking water. All of the testing, analysis, and modeling demonstrate that there is adequate confinement to prevent upward migration of the injected wastewater out of the injection zone. Also, the injection of this industrial wastewater will not modify the ambient water quality of other aquifers overlying the 48 injection zone, and the injection zone can receive wastewater at the rate proposed by FPL. Thus, injection of industrial wastewater from Units 6 and 7 will not cause or allow the movement of fluid into underground sources of drinking water that would cause a violation of drinking water standards or otherwise adversely affect the health of persons. Even after 100 years of plant operation, the injected wastewater will remain over 1,000 feet below the base of the underground source of drinking water. The injection wells will be operated consistent with applicable injection pressure and fluid velocity requirements. The injection wells will also comply with applicable emergency discharge requirements. Through the underground injection control permitting process, FPL will be required to continually monitor these injection wells and report that information to the Department. The wastewater discharged to the underground injection wells will not be hazardous as defined by chapter 62- 730. Thus, the wastewater complies with the Department's Boulder Zone's G-IV aquifer requirements. Additionally, the wastewater is not a radioactive waste as defined by rule 62- 528.200(54). Thus, the injection wells are considered Class I industrial injection wells under rule 62-528.300(1)(a)2. 49 Separate from this certification proceeding, FPL has obtained a permit to convert the Class V exploratory well to a Class I injection well. The permit to convert the exploratory well to a Class I injection well includes a requirement to operationally test the injection well for up to two years. The construction of the other underground injection wells will require a Class I UIC construction permit from the Department. That permit will contain a requirement to operationally test the injection wells for up to two years. This operational testing will allow FPL to further confirm that the underground injection control system operates as designed with no upward fluid migration. This operational testing period data will, in part, support FPL's application for one or more separate Class I UIC operating permits from the Department for the system. The operating permit must be renewed by the Department every five years. Class I UIC permits require periodic monitoring of the injection process and reporting of that monitoring information to the Department. Thus, the Department will continually oversee FPL's deep well injection system and will re-review the system every five years as part of the Class I operation permit renewal. Stormwater/Surface Water Management FPL has prepared and submitted to the reviewing agencies as part of its application a stormwater management plan 50 for construction and operation of the Project at the Site and for the associated non-linear facilities. During construction of the Site and associated non- linear facilities, erosion control measures such as silt fences and hay bales will be used to decrease velocity of sheet flow and to control small amounts of sediment from disturbed areas in runoff. Temporary basins or sediment traps will be constructed to control runoff from larger disturbed areas. Temporary fill diversions will be used for slope protection and to divert runoff to sediment basins and stabilized outlets. Construction stormwater requirements will be addressed through compliance with rule 62-621.300(4) and other applicable agency regulations. During operation, the stormwater management system is designed to release stormwater runoff from the Units 6 and 7 site into the existing permitted industrial wastewater facility. The stormwater runoff from the nuclear administration building, training building, and parking area will also be released to the industrial wastewater facility. The industrial wastewater facility currently has sufficient capacity and will not be impacted by stormwater runoff from the Project during operation. All stormwater associated with industrial activity from the RWTF equipment area will be captured, treated as necessary, and reused within the reclaimed water treatment 51 process. Runoff from non-equipment areas will be routed to stormwater management facilities and released to local drainage. Stormwater during construction and operation of the non-transmission linear facilities will be handled in accordance with applicable Department, SFWMD, and County non-procedural requirements. The proposed reclaimed water and potable water pipelines will be installed underground. The construction access roads will include stormwater management facilities designed to meet applicable Department standards. Runoff from the potentially oil-contaminated areas, such as the containment area for transformers and other oil-containing or handling equipment, will first be directed through an oil/water separator and then routed to the industrial wastewater facility. There will be no adverse impacts from stormwater during construction, operation, or maintenance of the plant and non-transmission line portion of the Project. Construction, operation, and maintenance of the stormwater management systems for the plant and non-transmission line portion of the Project will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause flooding to on-site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely affect the quality of any jurisdictional waters or result in a violation of any 52 water quality standards; will not cause adverse secondary impacts to water resources; and will not cause adverse impacts to any SFWMD water resources. Domestic/Sanitary Wastewater Sanitary wastewater treatment for Units 6 and 7 will be provided by a new on-site package sanitary treatment plant. The sanitary treatment plant will be designed to process sanitary wastes from Units 1 through 7. This treatment plant will replace several existing septic tanks and an existing sanitary wastewater plant that serve Units 1 through 4 and that discharges to the surficial aquifer. Units 6 and 7 will have a sanitary drainage system that will collect sanitary waste from plant restrooms and locker room facilities and carry this waste to the sanitary treatment plant where it will be processed. Effluent from the proposed sanitary treatment plant will be disposed through the underground injection wells in compliance with applicable regulations. FPL is requesting that the final certification for the Project include approval for the use of the on-site package sanitary treatment plant and the other on-site cooling water and wastewater treatment and disposal facilities in lieu of connecting the Project to a public sanitary sewer line for treatment and disposal of these waters by the County. FPL has 53 requested a variance from section 24-43.1(6), MDC. No reviewing agency, including the County, objected to the requested variance. With the exception of this one requested variance, the Project will comply with all applicable non-procedural standards and requirements of all reviewing agencies. A pipeline of the required length to connect to the MDWSD system for the flow generated by the Project would be below the desired minimum design velocity for the pipeline. The sanitary wastewater treatment plant will provide secondary waste treatment and high level disinfection; it will be designed in accordance with sound engineering practice; and the design, construction, and operation of the sanitary wastewater facilities will be consistent with applicable Department and County non-procedural requirements. Storage Tanks The Project will include some above-ground storage tanks for petroleum products and for the storage of chemicals. Above-ground storage tanks will be inside buildings or covered and will have required secondary containment. All storage tanks will be constructed, operated, and maintained according to the applicable requirements of chapters 62-761 and 62-762. 54 Air Emissions, Controls, Impacts, and Airspace The sources of air emissions associated with the Project will include circulating water cooling towers and service water system cooling towers, standby diesel generators, ancillary diesel generators, diesel fire pumps, diesel fuel storage tanks, and general purpose diesel engines. There will also be air emissions associated with Site preparation and construction. The Project will have six circulating water cooling towers to support the operation of the nuclear units, with three towers for each unit. The primary air emissions from Units 6 and 7 during operation are particulate matter (PM) and PM with an aerodynamic diameter of ten microns or less (PM10) in the form of atmospheric drift. The primary source of the PM and PM10 emissions is the circulating water cooling towers. There will also be small amounts of PM and PM10 from the service water system cooling towers. There will be emissions of PM and PM10, nitrogen oxides (NOx), carbon monoxide, volatile organic compounds, and sulfur oxides from the use of emergency diesel generators. Cooling tower drift will be controlled through the use of state-of-the-art cooling tower design including drift eliminators designed to limit drift to 0.0005 percent of the amount of water circulating through the cooling towers. The use 55 of high efficiency drift eliminators represents Best Available Control Technology as required by the EPA and Department. The water treatment levels and location and the operation of the cooling towers will comply with the Department's regulations for the use of reclaimed water in cooling towers. The Department has issued Air Permit No. PSD-FL-409, Project No. 025003-013-AC. The Department found that the Project would not cause or significantly contribute to a violation of any ambient air quality standards. It also determined that the Project would comply with all applicable state and federal regulations. Construction and operation of the Project will not have an adverse impact on air quality in the vicinity, including air quality in the Everglades National Park, BNP, or Big Cypress National Preserve. There will be no adverse visibility, fogging, or icing impacts resulting from the operation of the Turkey Point Units 6 and 7 cooling towers. "Drift" is made up of various sized water droplets containing minerals. These water droplets fall out of the cooling tower plume at various distances from the cooling tower and deposit materials. Deposition results when the solution drift falls to a surface such as the ground or water. 56 The constituents in treated reclaimed water will not result in adverse environmental impacts as a result of cooling tower deposition. FPL's deposition analysis considered the quality of the treated reclaimed water and the areas that may be potentially impacted by deposition. The results demonstrate that, while deposition of the various constituents can be calculated, the resulting concentrations of the constituents will be negligible and immeasurable. The constituents in saltwater, when using the back-up cooling water source, will not result in adverse environmental impacts as a result of cooling tower deposition. FPL's deposition analysis considered the quality of water and the areas that may be potentially impacted. The results demonstrate that, while deposition of the various constituents can be estimated through modeling, the resulting concentrations of these constituents could not be measured since their concentrations are extremely small compared to natural variation, and concentrations of many constituents would be well below the detection limits of analytical methods. While the deposition of TDS is higher in the vicinity of the cooling towers than background deposition, that area consists of vegetation that is salt tolerant due to the close proximity to Biscayne Bay. Moreover, the resultant concentration from deposition is much lower than the levels found in the 57 environment and the use of saltwater would be short-term given the durational condition of certification to which FPL has agreed. When using either treated reclaimed water or saltwater, air emissions from the Project will not have an adverse effect on natural resources, including surface waters and wetlands, in the vicinity of the Project. Atmospheric deposition from the operation of cooling towers associated with the Project will not degrade or lower ambient water quality in Biscayne Bay, including Biscayne Bay Aquatic Preserve and BNP. Operation of Units 6 and 7 will avoid a considerable amount of air pollution emissions and greenhouse gases. Over a 40-year period of operation, Units 6 and 7 will avoid approximately 21,300 to 49,200 tons of NOx, approximately 14,200 to 75,400 tons of sulfur dioxide, and at least 266 million tons of carbon dioxide emissions. Open burning during Project construction will be conducted in accordance with applicable non-procedural requirements of state and local agencies. FPL has complied with Condition 19 of County Resolution Z-56-07. FPL has obtained authorizations from the FAA for the Units 6 and 7 containment buildings. FPL will submit applications for FAA permits for the construction cranes prior to construction. 58 In accordance with Condition 18 of County Resolution Z-56-07, FPL has coordinated with the Homestead Air Reserve Base and is in compliance with Article XXXV, Homestead General Aviation Airport Zoning in sections 33-372 through 33-387, MDC. The County is currently designated as being in attainment for all Ambient Air Quality Standards for all pollutants. The non-transmission line portion of the Project will comply with applicable state and local non-procedural requirements for control and protection of air quality. The Project complies with applicable County non- procedural requirements related to air quality and all provisions of the County's CDMP related to air quality and air space. The air emissions associated with the non-transmission line portion of the Project are consistent with all applicable environmental regulations. Equipment Barge Unloading Area FPL currently has a barge delivery facility at the Turkey Point plant that is used for fuel oil delivery. The barge delivery facility is located at the north bank of the barge turning basin, east of the existing Units 1 and 2. To allow for deliveries of Project components, equipment, and material during Project construction, the existing barge unloading area will be enlarged by excavation of uplands landward to approximately 90 feet by 150 feet, to a 59 depth of approximately nine feet. The excavation area will be isolated from surface waters with sheet piles or similar structures. FPL will implement other best management practices during this excavation to prevent impacts to surface waters. The maximum draft of the barges to be used for delivery during construction is 6.5 feet. Normal operation of Units 6 and 7 will not require regular barge traffic. Construction of the enlarged barge unloading area will not require any construction in Biscayne Bay or its natural tributaries. Construction Access Roadways and Traffic Impacts FPL is seeking certification for roadway improvements as associated linear facilities to the Project in order to accommodate peak construction traffic and provide access to Units 6 and 7 during construction. The roadways are those necessary to provide safe and secure access to the Project site. Improvements will be made to approximately 3.5 miles of existing paved roadways by widening those roads from two lanes to four lanes. In addition, improvements will be made to seven miles of unpaved roads by constructing three or four paved lanes. Improvements will also be made to six intersections by adding new turn lanes. The construction access roadway improvements include a new bridge over a SFWMD canal. This bridge will be located, 60 designed, and constructed consistent with applicable SFWMD non- procedural requirements, including the Criteria Manual for Use of Works of the District. In addition to roadway segment and intersection improvements, traffic control in the form of traffic signals or police control will be required at several intersections during the peak morning and afternoon periods. These traffic control measures are only required at times of high traffic volume entering and leaving the Site during Project construction. In addition, roadway improvements south of Southwest 344th Street will be patrolled by security personnel. The roadway and intersection improvements will be designed and constructed in accordance with applicable city, county, and state non-procedural requirements. The roadways will comply with the criteria established in the Traffic Circulation Element of the CDMP for the Project's construction access roads. The construction activities will involve the installation of silt fences, removal of vegetation, construction of drainage, removal of unsuitable soils, placement of road-base materials, laying asphalt, and striping. Typical road construction equipment will be used to construct the roadway improvements. The final design of the roadway improvements will maintain sheet flow across roadway alignments. The final design of the roadway improvements on the Turkey Point plant property 61 will account for increased water elevations of up to one foot planned as part of regional environmental restoration projects. FPL will pay all costs associated with construction and removal of the construction access roads. Construction of the roadway improvements will commence no sooner than two years prior to the commencement of construction of the Project. The roadway and intersection improvements are temporary and designed to accommodate traffic during the construction of the Project. Following construction, all temporary roadway improvements on publicly owned ROWs will be returned to the status of the roadway prior to the commencement of construction of the temporary roadways and roadway improvements. Any privately owned roadway will be returned to the minimum roadway width required to provide maintenance to FPL facilities and will not be more than two lanes. Roadway improvements on privately owned property will not be open to the general public. The County and other agencies with needed access will be granted access to these private roadways. Level of service standards and the County's reserve capacity standards will be met with the addition of Project- related traffic during construction and operation. The construction access roads and pipelines will not be located within local wellfields. 62 Land Use/Comprehensive Plan Land uses adjacent to the site and associated non- linear facilities comprise undeveloped land; electrical generating Units 1, 2, 3, 4, and 5; and transmission infrastructure. The industrial wastewater facility is located to the west and south of the Units 6 and 7 site. Canals that return cooling water to Units 1 through 4 surround that site. The BNP, Biscayne Bay Aquatic Preserve, and the FPL Everglades Wetland Mitigation Bank are adjacent to the larger Turkey Point plant property. The Homestead Air Reserve Base and the Homestead-Miami Speedway are northwest of the site. Most of the existing land uses in the vicinity of the larger FPL Turkey Point plant property are vacant land. The Project site and associated non-linear facilities are compatible with the existing proximate land uses. Existing land uses within and in the vicinity of the proposed corridors for the temporary construction access roads and the potable water pipeline are comprised of vacant land, agriculture, residential, electric power facilities, the Homestead Air Reserve Base, and the Homestead International Speedway. Most of the existing land uses in the immediate vicinity of the southern portion of the temporary construction access roads are vacant land. 63 Land uses within the proposed corridor for the reclaimed water pipeline comprise a water treatment facility, a landfill, agricultural land, and transmission infrastructure. The BNP and Biscayne Bay Aquatic Preserve are located to the east of the proposed reclaimed pipeline corridor. The Homestead Air Reserve Base and the Homestead International Speedway are located approximately five miles northwest of the corridor. Most of the existing land uses in the immediate vicinity of the proposed corridor are vacant land. The proposed temporary construction access roads, the potable water pipeline, and the reclaimed water pipeline are compatible with the existing land uses within those proposed corridors. FPL will grant the MDWSD an unobstructed utility easement along Southwest 360th Street from Southwest 177th Avenue to the plant property as required by Condition 2 of County Resolution Z-1-13. FPL will also grant the County an easement along section line road ROW on the Southwest 344th Street alignment east of Levee L-31 in accordance with Condition 13 of County Resolution Z-1-13. FPL will design the construction access roads to avoid impacts to County-designated Environmentally Endangered Lands. 64 The plant and non-transmission line portion of the Project will be consistent with local land development regulations (LDRs), including zoning ordinances. FPL intends to comply with all of the conditions of County Resolutions Z-56-07 and Z-1-13 and with all of the criteria of the CDMP amendment for the construction access roadways. The plant and non-transmission line portion of the Project will be consistent with the CDMP and the City of Homestead's comprehensive plan; consistent with the Strategic Regional Policy Plan of the SFRPC; and consistent with the State Comprehensive Plan. Wetlands and Wetlands Mitigation Construction of the Plant and non-linear associated facilities would permanently impact approximately 398 acres of wetlands. Approximately 250.2 acres are associated with construction on the site and are contained within the industrial wastewater treatment facility. The remaining permanent wetland impacts are associated with construction of the associated non- transmission line facilities. There will also be approximately 43.6 acres of temporary impacts associated with construction of the reclaimed water pipeline. Wetland impacts associated with the construction of the radial collector well system are limited to approximately 65 three acres of temporary wetland impacts during installation of the radial collector well delivery pipeline. The construction and operation of the radial collector wells will not impact wetland vegetation upon sovereign submerged lands. There will be no wetland impacts associated with construction of the equipment barge unloading area. FPL has made efforts to reduce and eliminate impacts to wetlands through a variety of engineering, design, and other measures, including for example, locating the site within the existing, previously impacted, permitted industrial wastewater facility; relocating the parking and laydown areas to locations within the existing Turkey Point plant property; reconfiguring the RWTF to reduce the footprint and relocating the RWTF; and restoration of roadways within the construction access improvements corridors. FPL conducted its wetlands assessment in accordance with the Department's Uniform Mitigation Assessment Method (UMAM). A total of 262 UMAM credits of functional loss are associated with construction of the plant and non-transmission line portion of the Project. This includes permanent, temporary, and secondary wetland impacts. FPL has proposed a wetland mitigation plan for the entire Project. FPL proposes to mitigate for wetland impacts associated with the plant and non-transmission line portion of 66 the Project through a combination of regional wetland restoration, enhancement, and preservation initiatives furthering regional restoration goals, as well as the use of credits obtained from the Everglades Mitigation Bank and restoration of temporary wetland impacts associated with pipeline installation. The mitigation plan includes over 800 acres of wetland restoration, enhancement, and preservation. Additional mitigation activities are proposed within the Model Lands Basin to the west and south of the Turkey Point plant, including creation of a crocodile nesting sanctuary and restoration of wetlands associated with the temporary construction access roadways. FPL's proposed wetland mitigation plan is appropriate to offset the expected wetland impacts. FPL's proposed wetland mitigation plan for the plant and non-transmission line portion of the Project will fully offset impacts to the functions of wetlands and other surface waters within the same drainage basins as the impacts and will avoid unacceptable cumulative impacts to wetlands or surface waters. FPL's proposed wetland mitigation plan for the plant and non-transmission line impacts of the Project will fully offset the effects, including functional wetland loss, caused by the construction, operation, and maintenance of the Project. 67 FPL is capable of successfully implementing the proposed mitigation plan. FPL's proposed wetland mitigation plan complies with Conditions 1 and 9 of County Resolution Z-56-07 and Condition 15 of County Resolution Z-1-13. The plant and non-transmission line portion of the Project is not contrary to the public interest. The plant and non-transmission line portion of the Project is consistent with relevant requirements of the SFWMD. Wildlife/Threatened and Endangered Species FPL has submitted to all reviewing agencies a comprehensive threatened and endangered species management plan for all listed species for the Project. FPL has preserved, to the maximum extent practicable, all habitat that supports or is critical to listed species. The threatened and endangered species management plan addresses short-term measures to be taken during construction and permanent measures necessary to protect critical habitat. No nests of listed species will be destroyed without prior approval and relocation, if required. The plan includes permanent measures to prevent direct and indirect impacts to critical habitat sufficient to prevent disruption of sensitive behaviors such as breeding, nesting, and foraging within critical habitat. 68 FPL's threatened and endangered species management plan complies with Conditions 2 and 11 of County Resolution Z- 56-07 and Condition 18 of County Resolution Z-1-13. The threatened and endangered species management plan includes a comprehensive inventory of all threatened or endangered flora and fauna and identifies all habitat that supports these species. FPL has avoided and minimized impacts to wildlife, including listed species, by locating the site and associated non-transmission line facilities within previously disturbed areas to the greatest extent practicable, avoidance of nesting habitat, commitment to conduct pre-clearing surveys, incorporation of wildlife protection features in the design of construction access roadway improvements, and requiring wildlife training of all construction employees. FPL's proposed wildlife protection features associated with the construction access roads include installing crocodile and wildlife underpasses on Southwest 359th Street east of the L-31E Canal; installing fencing (including fine mesh material along the base of the fencing) along Southwest 359th Street from the L-31E Canal to Southwest 137th Avenue and along portions of both Southwest 117th Avenue and Southwest 137th Avenue between Southwest 344th Street and Southwest 359th Street; providing a six-foot box culvert wildlife underpass 69 along Southwest 359th Street between Southwest 117th Avenue and Southwest 137th Avenue; providing a second wildlife underpass associated with the bridge on the west side of the L-31E along Southwest 359th Street; and installing enlarged arch culverts along Southwest 359th Street from the L-31E Canal Westward to Southwest 137th Avenue to replace existing culverts. FPL's proposed conservation and monitoring plans will protect listed species from adverse effects from construction and operation of the plant and non-transmission line portions of the Project. FPL's proposed mitigation plan offsets any potential impacts to listed species. The plant and non-transmission line portion of the Project is not anticipated to cause adverse impacts to the abundance and diversity of fish, wildlife, or listed species. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not adversely affect the conservation of fish, wildlife, listed species, or their habitat; will not cause adverse secondary impacts to water resources, or aquatic or wetland-dependent fish or wildlife; and will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. In accordance with Condition 3 of County Resolution Z-56-07, prior to construction, FPL will obtain all permits and 70 assessments required by United States Fish and Wildlife Service (USFWS) for the preservation and management of habitat for listed species in accordance with applicable state and federal law. Florida Panther The Florida panther is classified as an endangered species. The USFWS has not designated critical habitat for the Florida panther. USFWS has, however, designated a Panther Focus Area (PFA). Approximately 5.75 miles of the construction access roadway corridors are within the PFA. Where the potable water pipeline is co-located with the construction access roadway corridor, it is also within the PFA. The remainder of the plant and non-transmission line portion of the Project is outside of the PFA. The roads and pipeline corridors within the PFA will result in an impact to approximately 69 acres on the fringe of the PFA. The 69 acres have a panther habitat value of 297 panther habitat units (PHUs). There is a very low likelihood that Florida panthers would occur in the area of the Turkey Point plant and the non- transmission line portion of the Project. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not 71 destroy, degrade, or result in a reduction of habitat that is critical to Florida panthers. Panthers do not use the area of the construction access roadway corridors, including for denning or as a travel corridor. FPL's proposed wildlife protection measures are appropriate and sufficient to prevent adverse impacts to Florida panthers from any traffic mortalities associated with the access roads, and are appropriate mechanisms to enhance protection for wildlife in the area. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not impact the values of wetland or other surface water functions so as to cause adverse impacts to the habitat of the Florida panther. The construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not have an actual or potential negative impact on Florida panther habitat; will not have adverse impacts on Florida panthers, their habitat, or affect the conservation of the Florida panther and its habitat; will not have adverse secondary impacts on Florida panthers or their habitat; will not result in a reduction in the number of Florida panthers; will not destroy, degrade, or result in a reduction of habitat that is critical to Florida panthers; will comply with all applicable federal, 72 state, and local laws and regulations for protection of Florida panthers, including FWC requirements, County code and zoning requirements, CDMP provisions, and City of Homestead requirements; is in compliance with all applicable agency non- procedural requirements related to Florida panthers; and will minimize adverse effects on Florida panthers. American Crocodiles The American crocodile is listed as a threatened species by USFWS and endangered by FWC. The American crocodile was first designated as endangered by the USFWS in 1975, and reclassified (downlisted) as threatened in 2007. In the 1980s, FPL developed a comprehensive crocodile management program for the crocodiles that are found in the existing cooling canal system at Turkey Point. These activities instituted at Turkey Point have largely been responsible for the increase in American crocodile population in South Florida over the last 25 years. USFWS has designated critical habitat for the American crocodile. The site, the radial collector well system area and delivery pipeline area, nuclear administration building, a small portion of the training building, a portion of the parking area, a portion of the potable water pipeline corridor, and a portion of the construction access roadways are within designated critical crocodile habitat. Historical 73 monitoring of the crocodile population indicates occasional observations of basking crocodiles on the Units 6 and 7 site. There has been no habitual utilization of any of those areas of the Site for foraging or nesting by crocodiles due to the lack of suitable nesting substrate, altered and highly variable hydrology, and limited food supply. The proposed facility locations outside of the designated critical habitat likewise do not provide significant basking, nesting, or foraging habitat for American crocodiles. American crocodiles do not use any of the Units 6 and 7 plant and non-transmission line facility proposed locations for nesting. The areas proposed for spoil disposal are not suitable for crocodile nesting. Placement of the spoil will not affect crocodile movement into and out of the cooling canal system or result in any adverse impacts to American crocodiles. The plant and non-transmission line portion of the Project will not adversely impact American crocodile travel corridors. FPL will enhance and create crocodile habitat within and adjacent to the cooling canal system, including creation of additional juvenile low salinity refugia upon selected berms, vegetative restoration, substrate enhancement to create suitable nesting habitat upon selected berms that have not historically 74 supported crocodile nests, and construction of an additional American crocodile nesting and foraging sanctuary (the Sea Dade Canal Sanctuary) south of the cooling canal system within the Everglades Mitigation Bank. FPL's proposed constraints on traffic, maintenance, and construction within the cooling canal system and proposed wildlife protection measures, including crocodile underpasses, are appropriate and sufficient to enhance protection of American crocodiles. The measures proposed and agreed to by FPL are adequate to avoid adverse impacts to the size and health of the American crocodile population from construction and operation of the Project. The habitat that is being impacted by the plant and non-transmission line portion of the Project is not critical to American crocodile viability or survival, is not suitable for American crocodile nesting or foraging, and is only occasionally used for basking. The habitat that is being created far outweighs the value of any habitat being impacted. The plant and non-transmission line portion of the Project will not compromise the viability or survival of the American crocodile or result in a net reduction in the number of American crocodiles. 75 Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not impact the values of wetland or other surface water functions so as to cause adverse impacts to the abundance of the American crocodile; will not adversely affect the conservation of American crocodile habitat; will not have any adverse impacts, including secondary or cumulative impacts, on American crocodiles, their habitat, or affect the conservation of the American crocodile and its habitat; will not adversely impact nesting locations of American crocodiles; will not cause adverse impacts to the abundance and diversity of American crocodiles; will comply with all applicable federal, state, and local laws and regulations for protection of American crocodiles, including FWC requirements, County code and zoning requirements, CDMP provisions, and City of Homestead requirements; complies with all applicable agency non-procedural requirements related to American crocodiles; and will minimize adverse effects on American crocodiles. Eastern Indigo Snakes Eastern indigo snakes are classified as threatened by USFWS and FWC. No critical habitat has been designated for Eastern indigo snakes. Eastern indigo snakes have not been observed in the proposed locations for the Project Site or the construction 76 access roadways. The areas impacted by the plant and non- transmission line portion of the Project will not compromise the viability or survival of Eastern indigo snakes or result in a reduction in the number of Eastern indigo snakes. FPL's proposed pre-clearing surveys and wildlife protection measures along the construction access roadways are appropriate and sufficient to enhance protection of Eastern indigo snakes. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not impact the values of wetland or other surface water functions so as to cause adverse impacts to the habitat of the Eastern indigo snake; will not have adverse secondary impacts on Eastern indigo snakes; will not have any adverse impacts on Eastern indigo snakes, or affect the conservation of Eastern indigo snakes and their habitat; will not cause adverse impacts to the abundance of Eastern indigo snakes; complies with all applicable federal, state, and local laws and regulations for protection of Eastern indigo snakes, including FWC requirements, County code and zoning requirements, CDMP provisions, and City of Homestead requirements; complies with all applicable agency non-procedural requirements related to Eastern indigo snakes; and will minimize adverse effects on Eastern indigo snakes. 77 Manatees The Florida manatee is classified as endangered. The equipment barge unloading area, radial collector well system area, and the reclaimed water pipeline crossings of canals occur in or near areas that may be used by Florida manatees. The presence of the Florida manatee is known to occur in Biscayne Bay, but not within the site or the industrial wastewater facility, as the closed-loop cooling canals do not connect to the Bay. Manatees occasionally are found in some of the SFWMD canals connecting to Biscayne Bay north of the Turkey Point plant, some of which are contained within the reclaimed water pipeline corridor. Construction of the plant and non-transmission line portion of the Project will involve minimal in-water work and will be limited to the equipment barge unloading area and temporary impacts associated with canal crossings of the reclaimed water pipeline. The equipment barge unloading area will be constructed through excavation of uplands adjacent to the Turkey Point plant turning basin. No dredging within Biscayne Bay will be required. The FWC Standard Manatee Conditions for In-Water Work will be followed for all in-water activity located where waters are accessible to manatees. FPL will comply with the Project's 78 Manatee Protection Plan to avoid any impacts to the manatees during the equipment barge unloading area expansion. FWC- approved manatee observers will be on-site during all in-water construction activities and will advise personnel to cease operation upon sighting a manatee within 50 feet of any in-water construction activity. The plant and non-transmission line portion of the Project will not adversely impact manatees and is consistent with FWC requirements to conserve and protect manatees and will not have any adverse impacts on the Florida manatee. Avian Species FWC has not designated critical habitat for any of the listed avian species in the regional ecosystem of the plant and non-transmission line portion of the Project. While some habitat used by listed species will be affected by the plant and non-transmission line facilities, the extent of this habitat impact is minimal and will be fully mitigated. No wood stork nesting colonies are located within the vicinity of the Site or associated non-transmission line facilities. The plant and non-transmission line portion of the Project will have minimal impacts to wood storks, due to minimal loss of foraging habitat. Snail kites do not normally occur in the area of the plant and non-transmission line associated facilities. 79 Construction, operation, and maintenance of the plant and non- transmission line portion of the Project will not adversely impact snail kites. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not result in a net loss of shorebirds or their habitat. FPL's proposed mitigation offsets any impacts to shorebird habitat. FPL will employ measures to deter Least Tern nesting on the gravel parking areas. There are no known bald eagle nests in the vicinity of the plant and non-transmission line facilities. FPL's planned activities are unlikely to have any impact on the bald eagle. The plant and non-transmission line portion of the Project will not result in a reduction in the number of listed avian species. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project will not impact the values of wetland or other surface water functions so as to cause adverse impacts to the abundance and diversity of avian species, including listed species; will not adversely impact the conservation of avian species, including threatened and endangered avian species or their habitats; will not cause adverse secondary impacts to avian species; and complies with 80 all applicable federal, state, and local laws and regulations for protection of avian species, including FWC requirements, County code and zoning requirements, CDMP provisions, and City of Homestead requirements. The plant and non-transmission line portion of the Project complies with all applicable agency non-procedural requirements related to avian species; and will utilize reasonable and available methods to minimize adverse impacts to avian species and their habitat. Plants/Exotics/Landscaping Botanical surveys were conducted within the Site and associated linear facilities, resulting in a total of 33 threatened or endangered plant taxa observed. Many of these listed plant species were observed on side-slopes of existing roadways, transmission structure pads, and pine rockland soils that are subject to routine vegetation management such as mowing. Impacts to listed plant species will be avoided or minimized to the greatest extent practicable through pre- clearing surveys, relocation of individuals, if feasible, and/or modification of facility design, such as modification of access road or pipeline alignments so as to avoid impacting listed plants. FPL has prepared an exotic vegetation management plan. FPL will not plant listed exotic or nuisance species. If 81 encountered on the locations of the site and associated non- transmission line facilities or mitigation areas, they will be removed prior to construction in that location. FPL will maintain wetland mitigation lands free of exotic vegetation, as required by Condition 10 of County Resolution Z-56-07. FPL's exotic vegetation management plan complies with Condition 12 of County Resolution Z-56-07. FPL will undertake final tree surveys before commencement of construction of the plant and of the construction access roads and water pipelines. FPL will take measures to avoid impacts to protected trees during construction, in accordance with local requirements. FPL will provide mitigation for impacts to trees. All off-site landscaping, including for the construction access roadways, complies with the local non- procedural requirements for landscaping and with Condition 13 of County Resolution Z-56-07 and Condition 14 of County Resolution Z-1-13. Also, FPL will comply with Condition 19 of County Resolution Z-1-13. Comprehensive Everglades Restoration Project (CERP) The CERP was authorized by Congress in 2000 and provides a framework and guide to restore, protect, and preserve the water resources of central and southern Florida, including 82 the Everglades National Park. The plant and non-transmission line associated facilities are within the boundary of one CERP project; a small portion of the reclaimed water pipeline corridor falls within the Biscayne Bay Coastal Wetlands Project. All plant and non-transmission line associated facilities, including the reclaimed water pipeline and construction and operation of the radial collector wells are not inconsistent with that CERP Project. The plant and non-transmission line portion of the Project is consistent with CERP and its overall objectives. Archeological and Historic Sites FPL conducted cultural resources assessment surveys for the Site and associated non-linear facilities in compliance with applicable state and federal requirements. No historical or archaeological resources were identified. FPL also conducted a preliminary cultural resource assessment survey for the Project's associated linear facilities. It is typical practice when certifying corridors to conduct a review of known or previously-recorded resources, with the field surveys to be conducted after the final ROW location is finalized. No previously-recorded archaeological sites, archaeological zones, historic structures, historic districts, historic linear resources, historic cemeteries, or historic bridges were identified within or adjacent to the reclaimed 83 water pipeline corridor, the construction access roadway corridors, or the potable water pipeline corridor. The State Division of Historical Resources (DHR), State Historic Preservation Office (SHPO), reviewed the cultural resources assessment reports and agreed that the site and associated non-linear facilities will not have an effect on historic properties. The SHPO also concurred with the work plans submitted for the site and associated non-linear facilities and the linear facilities. The plant and non-transmission line portion of the Project will comply with the National Historic Preservation Act and applicable SHPO non-procedural requirements; all applicable County code non-procedural requirements related to cultural, archaeological, and historical resources; all CDMP provisions related to archaeological and historical resources; and all applicable non-procedural requirements of the City of Homestead code and comprehensive plan related to cultural, historical, and archaeological resources. The plant and non-transmission line portion of the Project will not have adverse impacts, including secondary impacts, on cultural, historical, or archaeological resources. Solid and Hazardous Waste All solid waste from construction and operation will be stored, recycled, processed, and disposed of in accordance 84 with the applicable federal, state, and local rules and regulations. All solid waste will be disposed of at a permitted solid waste management facility. Used oil from construction vehicles and equipment will be collected in appropriate containers and transported off- site for recycling or disposal at an approved facility. Hazardous waste materials generated during construction and operation will be managed and disposed of by a licensed hazardous waste contractor in accordance with all applicable federal, state, and local rules and regulations. Noise and Lighting Impacts Noise associated with construction and operation of the plant and non-transmission line portion of the Project will comply with the applicable County and City of Homestead non- procedural requirements. Construction and operation of the plant and non-transmission line portion of the Project will not have any adverse noise-related impacts. Units 6 and 7 will require outdoor lighting for security purposes and worker and plant safety, including lighted walkways, parking areas, and various equipment areas. The plant and non-transmission line portion of the Project will not have adverse lighting-related impacts and will comply with NRC, United States Occupational, Safety, and Health Administration, and County non-procedural requirements. 85 Socioeconomic/Public Impacts and Benefits The Project will have a positive fiscal impact on the County, the County School Board, and the community. The Project is anticipated to result in payment of $1.4 to $2.0 billion in property taxes to the County over the Project's operating life; payment of $52.6 to $74.2 million in state sales taxes during the construction period; payment of $1.1 to $1.7 billion in property taxes to the County School Board over the Project's lifetime; and payment of $138.3 million to $202.9 million to other taxing authorities over the Project's lifetime. From an economic impact perspective, the Project is anticipated to result in creation of 806 permanent, onsite jobs for plant operations; creation of approximately 3,950 direct onsite jobs and 3,689 indirect jobs (annual average) at peak during the construction period; $28.3 billion in total economic output over the operating period; and $8.2 to $11.2 billion in total economic output during the construction period. Project construction will take approximately 123 months. Construction and operation of the plant and non- transmission line portion of the Project will not have an adverse population impact to the County. There will be adequate housing and school capacity in the County to accommodate the construction and operation workforce and their families. Police, fire, emergency management, and medical facilities in 86 the region will be sufficient to accommodate construction and operation of the plant and non-transmission line portion of the Project. Construction and operation of the plant and non- transmission line portion of the Project will not have an adverse impact on regional scenic, cultural, or natural landmarks or on residential, commercial, or recreational facilities and uses. Construction, operation, and maintenance of the plant and non-transmission line portion of the Project likewise will not adversely affect fishing or recreational values or marine productivity. The Project meets an identified need for electrical power and has substantial economic and fiscal benefits. The Project will ensure electrical reliability for FPL's customers. The Project will also have environmental benefits. The environmental benefits include use of reclaimed water as the primary source of cooling water. The encouragement and promotion of water conservation and use of reclaimed water are State objectives and considered to be in the public interest. FPL's use of reclaimed water is also consistent with the County's efforts to meet the requirements of Florida's 2008 ocean outfall legislation. As described earlier, the use of nuclear power will also avoid substantial emissions of greenhouse gases. The evidence also shows that the Project will 87 fully offset all impacts to wetlands and includes additional mitigation activities conducted without credit for the generation of functional lift. The Project is clearly in the public interest and will serve the broad interests of the public. The PSC has determined that there is a need for the Project, and it reaffirmed that need through annual review. The Project will not result in any unmitigated adverse impacts to air and water quality, fish and wildlife, water resources, or other natural resources of the state. The Project effects a reasonable balance between the need for the facility and the impacts upon air and water quality, fish and wildlife, water resources, and other natural resources of the state resulting from the construction and operation of the Project. Road Right-of-Way Dedications The County has proposed conditions of certification to require FPL to dedicate to the County approximately 131 parcels of land at locations identified by the County in Attachment 3 to its Plant Agency Report. The County's zoning code is found in chapter 33, MDC. Section 33-133 establishes "minimum right-of-way widths for streets, roads and public ways for the unincorporated area of the County . . . ." Section 33-46 provides that "[n]o permit shall be issued for a building or use on a lot, plot, tract, or 88 parcel in any district until that portion of the applicant's lot, plot, tract, or parcel lying within the required official zoned right-of-way has been dedicated to the public for road purposes . . . ." Dedications are only required where the applicant owns the land in fee. The list of 131 locations was identified by the County Public Works Department and Environmental Resources Department. The County has existing roads at some of these locations, but it does not have the full dedicated road ROW at other locations. The County does not currently have plans to construct roads at other locations identified for dedication. The County is aware that FPL does not own the land in fee at some of the identified locations but did not identify if FPL owned the land at the listed locations. The County witnesses were not aware of prior permitting by the County Works Department or Environmental Resources Department, including permitting of transmission lines, requiring dedication of road ROW. At some locations, the County is seeking dedications in areas identified for restoration of the Everglades or Biscayne Bay under CERP; however, the County might make the dedicated road ROW available for CERP features and not use them for public roads. The County also seeks dedications to obtain County access to environmentally endangered lands managed by the 89 County. Instead of dedications for public roads at several locations, the County would require FPL to close roads and convey the land to the County. If the County later decides to not build a road, the landowner can file a petition to request that the County Commission abandon the road ROW dedication through a public hearing. Many of these 131 parcels are along or across the corridors for the electrical transmission lines, the reclaimed and potable water pipelines, and the construction access roads. The County did not identify where these parcels are located within established ROWs. Several parcels identified by the County for dedications are not located in areas proposed for Project-related facilities Transmission Facilities Overview Transmission Facilities As noted above, the transmission facilities associated with the Project proposed by FPL include the on-site Clear Sky electrical substation, expansion of the existing Levee electrical substation, two access-only transmission line corridors, and two transmission line corridors containing a total of five transmission lines. "Transmission facilities" refers to the proposed transmission lines in the application, as defined in sections 90 403.503(14) and 403.522(22), including the Clear Sky-Turkey Point 230-kV transmission line and the Clear Sky-Davis and Davis-Miami 230-kV transmission line (the eastern transmission lines); Clear Sky-Levee No. 1 and No. 2 500-kV transmission lines and Clear Sky-Pennsuco 230-kV transmission line (the western transmission lines); and the Clear Sky substation and Levee substation expansion. FPL originally proposed to locate the transmission lines in approximately 88.7 miles of transmission line corridors: 52 miles in the FPL West Preferred Corridor and 36.7 miles in the FPL East Preferred Corridor. For its western transmission lines, FPL is now seeking certification of the West Consensus Corridor/MDLPA No. 2 -- a combination of an alternate corridor proposed by MDLPA and FPL West Preferred Corridor -— as its favored western corridor. The West Consensus Corridor/MDLPA No. 2 and the FPL West Preferred Corridor are both approximately 52 miles in length. FPL is concurrently seeking certification of its original FPL West Preferred Corridor as a back-up, to be used only in the event a ROW for the western transmission lines in the West Consensus Corridor/MDLPA No. 2 cannot be secured in a timely fashion and at a reasonable cost. The proposed transmission lines are necessary to safely and reliably connect the new power generation from the Project to FPL's existing electrical transmission network. 91 Certification of the eastern and western transmission lines, as conditioned, serves the broad interests of the public by ensuring reliable electric service at a reasonable cost. An electrical transmission line is a high voltage system that is used to transfer power, typically from power plants or other generation facilities, to one or more substations that may be connected by the transmission line. A substation is a facility where the voltage of electricity carried on a transmission line can be increased or reduced by the use of transformers and other related electrical equipment for safe and practical transmission to other substations or distribution directly to customers. The general components of a transmission line are structures (single or multiple poles), insulators, conductors (wires that carry the electricity) and overhead ground wires (OHGW) that protect the conductors from lightning strikes and also provide for relay protection and telecommunications, other communications wires, various hardware, and access roads. In wet areas, a transmission line may also include structure pads. An access road is an integral part of a transmission line. It allows access to each structure location for construction purposes and also provides ongoing access for routine and emergency maintenance. The transmission line access 92 roads and structure pads required for the lines, if not already existing, will be unpaved. A structure pad is an unpaved area of compacted and stabilized fill that is of sufficient size to accommodate necessary access for construction and for subsequent maintenance, restoration, and emergency operation activities. Transmission line siting involves identifying a route for the transmission lines, selecting a corridor that encompasses that route, and ultimately acquiring the ROW within the corridor in which the transmission lines will be built, operated, and maintained. The route or route alignment is the line between the endpoints for the transmission lines. The corridor is the area within which the transmission ROW will be located. At a minimum, it must be wide enough to accommodate a ROW that in turn is wide enough for the planned transmission facilities; the corridor can be up to a mile wide. Once the ROW is acquired, the corridor boundaries narrow to include only the ROW. The ROW for the transmission line is established through the acquisition of property rights or through use of existing property rights. Including the alternate transmission line corridors proposed by other parties, there are a total of two corridors 93 proper for certification in the east study area and five corridors proper for certification in the west study area. 2. FPL's Siting and Corridor Selection Process FPL utilized a multidisciplinary transmission line siting team consisting of experts in land use, engineering, the environment, and public outreach to select its preferred corridors for both the eastern and western transmission lines. For the following reasons, the corridor selection process used by FPL is found to be reasonable, is consistent with the methodology, guidelines, and criteria used in prior corridor projects throughout the State, and therefore is appropriate for use in this proceeding. The fact that population data and/or density information, house-by-house or parcel-by-parcel, were not specifically used by FPL, does not detract from the validity of the selection process. The objective of FPL's corridor selection study was to select a certifiable corridor that balances land use, environmental, engineering, and cost considerations. Corridor selection methods were designed to be integrative of multidisciplinary siting criteria; rational and objective in decision-making; sensitive to social and environmental conditions; responsive to regulatory requirements; reflective of community concerns and issues; and capable of accurate documentation and verification. 94 The process sought to maximize collocation opportunities and minimize intrusion into siting constraints to the extent practicable. Collocation is the ability to follow (within or adjacent to) an existing linear feature, easement, or ROW, providing the opportunity to reduce the amount of new access road construction, impacts to wildlife habitat, and other impacts. It may include siting a utility within or adjacent to an existing vacant but established ROW. Collocation provides a way to minimize impacts in several ways. With an existing structure, the vegetation, wildlife habitat, and surrounding land uses have already been affected by the existing facility. Adding a new transmission line in such areas will add very little, if any, additional impact. In addition, positioning a corridor along existing roads where feasible to provide access often offers an opportunity to reduce wetland impacts. FPL uses existing access roads where available to minimize wetland impacts. Also, the transmission lines can be designed to avoid clusters of roadside canopy trees. The corridor selection process consisted of multiple steps, including project and study area definition, public outreach, resource mapping and alternative route delineation, quantitative and qualitative evaluation of alternate routes, and selection of a preferred corridor. 95 First, for both the eastern and western transmission lines, FPL defined the project and study area by specifying the voltages and typical ROW widths of the transmission lines to be built, the substation endpoints for the route to connect, the types of typical structures, and existing transmission line ROWs in the area. For the eastern transmission lines, FPL specified transmission structures for a single circuit, 230-kV transmission line to connect the proposed Clear Sky substation to the Turkey Point substation, and a single circuit, 230-kV transmission line to connect the Clear Sky, Davis, and Miami substations. The study area was developed to include those four substations and FPL's existing transmission line ROWs connecting them. The west study area included the Clear Sky, Levee, and Pennsuco substations and existing FPL transmission ROWs and other linear features that occur between these substations. For the western transmission lines, FPL specified two 500-kV lines extending from the on-site Clear Sky substation, extending west and then north to the existing Levee substation. From the proposed Clear Sky substation, FPL also specified a 230-kV transmission line from the on-site Clear Sky substation to the existing Pennsuco substation. 96 For the next corridor selection step, FPL evaluated collocation opportunities and siting constraints within the study areas in a regional screening mapping exercise. Public outreach was initiated to solicit information for the regional screening exercise. Resource mapping information was obtained from available information sources, including local, regional, state, and federal agency geographic information systems data. FPL used a technique of overlay mapping software programs to allow flexibility in adding new information as it became available and modifying layers to analyze certain constraints or opportunities. For all transmission line routes, the types of resources mapped included base map information, including: highways, roads, and streets; county and city boundaries; railroads, airports, and heliports; existing and proposed FPL substations; existing FPL transmission lines; existing FPL properties, ROWs, and easements; water bodies, rivers, streams, and canals; land use information (existing and proposed development for which local approvals are pending); planned unit developments and developments of regional impact; property boundaries; existing schools and County School Board lands; cemeteries and historical structures and districts; national parks, wildlife refuges, estuarine sanctuaries, landmarks, or historical sites; state parks, preserves, proposed and existing 97 Florida Forever lands, Areas of Critical State Concern, Save Our Rivers lands, and aquatic preserves; SFWMD-owned lands; County lands, parks, recreation areas, and mitigation lands; Native American lands; privately-designated wetland mitigation areas; privately-owned environmental preserves/sanctuaries; military properties; and environmental information, i.e., listed federal and state-protected species and unique habitats; USFWS- designated critical habitats; and wetlands as delineated on USFWS National Wetlands Inventory maps. Once those resources were mapped, the team used the study area regional screening maps as a visual tool, along with aerial photography, ground reconnaissance, and helicopter fly- overs, to develop alternative routes. The team identified routes designed to best avoid or minimize siting constraints and maximize use of collocation opportunities with existing linear features/ROWs. Using route selection guidelines developed by the multidisciplinary team and based on similar guidelines used in previous projects in Florida, several alternative route segments were developed that, when combined, could connect the Project substations. The route selection guidelines used were designed to: Maximize collocation with certain linear features (existing FPL transmission lines, easements, or ROW; roads; canals; etc.). 98 Follow parcel or section lines where practicable and when other linear collocation opportunities do not exist. Minimize crossing of constraints identified as a result of regional screening (e.g., environmentally sensitive lands, existing development, and proposed development for which local approvals are pending). Avoid known airports and private airstrips consistent with FAA and other applicable regulations. Follow disturbed alignments (ditches, roads) through wetlands, where practicable. Minimize crossing of existing transmission lines. Applying the route selection guidelines to the study area regional screening maps, FPL's multidisciplinary team identified 35 route segments that combined to form 134 eastern alternative routes and 34 route segments that combined to form 99 western alternative routes. Once alternative routes were identified, evaluation of these alternative routes involved a systematic, quantitative and qualitative evaluation of each route using environmental, land use, cost, and engineering criteria, integrating information received from the public and other stakeholders through FPL's outreach program. For all transmission line routes, the quantitative criteria used were: number of non-FPL parcels/lots crossed; 99 length of route not following FPL-owned ROW or other transmission line easements; length of route not following other linear features; length of route through existing parks/ recreation areas/designated conservation lands; length of forested wetlands crossed; length of non-forested wetlands crossed; number of eagle nests/wading bird colonies within one- half mile; and engineering/construction cost estimates. These criteria are based on the application of accepted transmission line siting factors used on previous projects across Florida. In addition, the quantitative route evaluation criteria included the number of buildings and schools/school properties within 200 feet of eastern route centerlines and within 500 feet of western route centerlines. The use of these measures of separation was not unreasonable. The proximity distance for this relative comparison among eastern routes was shorter than for the western routes due to the much higher density of development within the east study area. Data for quantitative route evaluation criteria came from the regional screening map data, recent digital aerial photography for the study area, input from agencies and local governments, ground and aerial surveys of routes, and input from the community outreach program. Each segment was analyzed for each quantitative criterion, and the value for each criterion was recorded by segment. The relative weight (importance) of 100 each criterion to be used in the alternative route evaluation was then established by the siting team. These criteria and weights were validated through input from the community obtained as part of the community outreach program. The weighting of criteria in this manner was not shown to be unreasonable. The next step of the integrated alternative route evaluation process involved performing a qualitative assessment of more localized conditions. This evaluation included analyses of siting issues and opportunities; siting constraints; additional ground and aerial surveys; and feedback, additional public input, and comments received at agency workshops and meetings, nine community open houses, and numerous individual and small group meetings with area residents, property owners, and local governments. Qualitative criteria evaluated for all transmission line routes included: available space within existing FPL ROW, easements, or fee-owned property; available ROW along roads, transmission lines, and railroads; road plans; proposed development plans; proximity of existing development; types of development in proximity; proximity and orientation of public airports and private airstrips; ingress/egress at substations; bridge crossings; constructability; acquisition status of existing and proposed conservation lands and/or greenways; ability to avoid or minimize wetland impacts; ability to avoid 101 or minimize impacts to parks, recreation, and conservation lands; proximity to historical districts, roads, and/or structures; review of potential underground scenarios where an overhead transmission line design is not feasible; potential listed species presence; crossing of Native American lands; potential use of local access roads/trails; proximity to known archaeological locations; and vegetative landscapes along streets (tall trees). Qualitative criteria for western transmission line routes also included the significance of the Everglades National Park and the ability to utilize or cross government-owned parcels. Environmental considerations and land ownership were key considerations in the west. FPL's corridor selection process took into account proposed development in the corridor areas, while avoiding environmentally sensitive areas to the extent practicable. It reflected a reasoned balancing of the need for the transmission lines against the potential impact on both the public and the environment. After quantitative and qualitative evaluation of all identified route alignments and consideration of public input throughout the corridor selection process, FPL selected preferred corridors and delineated corridor boundaries. 102 290. The PPSA requires a balancing analysis of "whether, and the extent to which" a number of considerations are satisfied. § 403.509(3), Fla. Stat.; In re: Gainesville Renewable Energy Center, LLC, Case No. 09-6641EPP, 2010 Fla. ENV LEXIS 174 (Fla. DOAH Nov. 1, 2010), 2010 Fla. ENV LEXIS 173 at *11 (Fla. Siting Bd. Dec. 15, 2010)(PPSA statutory scheme is one of balancing and reasonableness). Although the route selection criteria and process employed by FPL's team are not expressly enumerated in the PPSA, the criteria were used to quantitatively and qualitatively assess the balance of statutory factors that the various routes would achieve. Similar criteria were used to evaluate multiple proposed routes in numerous other successful transmission line certification proceedings for projects throughout Florida. In those proceedings, the criteria were vetted by agency review, local government review, and public input. Post-Certification Planning and Design, All Corridors Proper for Certification ROW Selection and Delineation 291. Once a corridor has been selected for a transmission line and certified, FPL establishes a ROW through multiple means, including (1) purchasing easement rights over the affected parcels; (2) purchasing the property in fee simple if necessary; and/or (3) acquiring longitudinal use permits and 103 licenses for public lands, where transmission lines cross or are longitudinally located within public properties or public rights-of-way. A combination of these three methods can take place over the length of a transmission line in order to establish a ROW for that line. FPL cannot construct transmission lines on ROWs for which it has not acquired the necessary property rights. Unless the transmission line is located on available public ROW, based on a review of recently completed projects, it costs FPL approximately four times the market value of land to actually acquire and assemble a ROW within a certified corridor. This is called the "acquisition factor." After certification, FPL will be required to submit its proposed transmission line ROW alignments to the Department, with copies to DOT, SFWMD, SFRPC, the County, and the affected municipalities delineating the proposed ROW for the areas within each agency's jurisdiction. Each agency will then have the opportunity to notify the Department of any apparent conflicts with the requirements of the Conditions of Certification. The final transmission line alignment will take into account approved development to be constructed in the area. For example, upon FPL's request, the County will identify the location of approved but not yet constructed development within the County's jurisdiction so FPL can plan to avoid or minimize 104 conflicts with any such development. Further, to address any concerns by local governments regarding future development, FPL is willing to comply with a condition of certification to accommodate approved but not yet constructed development in the design of the transmission line. Selection of a ROW within a corridor and optimal placement of structures within the ROW can also avoid potential obstructions and minimize wetland impacts. For example, the ROW can be positioned along existing roads to provide access, which can reduce wetland impacts. Transmission Line Design Standards FPL's transmission lines are designed to conform to applicable codes, guidelines, and industry standards, including: National Electrical Safety Code (NESC) standards, such as those for clearances, loading, strength, and extreme wind event design; Department standards for electromagnetic fields (EMF); DOT Utility Accommodation Manual specifications; American Society of Civil Engineers (ASCE) standards; Institute of Electrical and Electronic Engineers standards; American Society of Testing Material (ASTM) standards; American Concrete Institute (ACI) standards for the design of concrete transmission poles; United States Occupational Safety and Health Administration requirements for safe minimum approach distances; 105 applicable noise ordinances of local governments, and FPL's own design and hardening standards for transmission lines. The NESC is the standard adopted by the PSC with which FPL's transmission lines must comply to protect public safety. The NESC, rather than local building codes, is the national industry standard for construction and public safety that is most applicable for transmission lines. FPL presented evidence demonstrating that many of its internal design standards exceed those of the national standards. These internal design standards may require minimization of impacts even beyond regulatory requirements, where practical. For example, FPL may reverse phase on double circuit lines to minimize the magnetic field or may vary the span between structures to avoid significant environmental, historical, or archaeological resources or conflicts with existing land uses like driveways. Overhead design for its transmission lines constitutes FPL's current standard and customary practice where there is no engineering constraint requiring an underground installation. About 98 percent of FPL's transmission system is overhead in design. Undergrounding of FPL's proposed transmission lines is not justified by any asserted concern about their structural integrity. The concrete monopole structures are specifically 106 engineered to withstand extreme wind events, which meet or exceed NESC requirements. Extreme weather can affect both underground and overhead transmission lines. In some cases, restoration of an underground circuit can take significantly longer than for an overhead circuit. The Coral Gables/Pinecrest transmission line expert agreed that undergrounding transmission lines can involve reliability problems, and it could take weeks or months to repair a fault on an underground transmission line. FPL's overhead transmission lines such as those proposed for this Project have performed very well in extreme weather events over their operating history. The PSC, not local governments, has regulatory authority over undergrounding of electric utility lines. The incremental costs of undergrounding transmission lines, where overhead transmission lines are feasible, but undergrounding is requested for aesthetic reasons, are typically paid by the requesting entity. This cost allocation principle has been recognized by the PSC, the Florida Legislature, and the Florida Supreme Court to ensure that entities that benefit from extraordinary costs will bear those costs when other means are technically feasible. See § 366.03, Fla. Stat. ("No public utility shall make or give any undue or unreasonable preference or advantage to any person or locality, or subject the same to 107 any undue or unreasonable prejudice or disadvantage in any respect."); Fla. Power Corp. v. Seminole Cnty., 579 So. 2d 105, 108 (Fla. 1991)("Permitting cities or counties to unilaterally mandate the conversion of overhead lines to underground would clearly run contrary to the legislative intent that the [PSC] have regulatory authority over this subject."). Transmission Line Construction and Maintenance Process The first step in transmission line construction is to survey the land to locate property lines, property corners, section corners, and road ROW lines to prepare the easement descriptions for ROW acquisition or to establish the boundaries of an existing transmission ROW. After any necessary acquisition, additional surveying is undertaken to stake out ROW lines and stake locations for poles, anchors, structure pads, and access roads for ROW preparation. The second step in transmission line construction is ROW preparation. ROW preparation requires trimming or removal of vegetation in conflict with safe construction and operation of the transmission line. Where clearing is required in uplands or wetlands, trees and shrubs whose mature height could exceed 14 feet and which are very close to the transmission line will be evaluated for pruning or clearing to ground consistent with American National Standards Institute (ANSI) standards. Stumps may be removed or grubbed and treated with approved herbicides. 108 FPL will implement tree protection, replacement, and relocation measures in compliance with applicable non-procedural requirements of the local government within which the work is being conducted. In wetland areas, selective clearing of vegetation by hand may be required. Additionally, in wetlands and sensitive pine rockland communities such as County- designated Natural Forest Communities (NRCs), trees and shrubs whose mature height could exceed 14 feet which are very close to the transmission line will be pruned or cleared using only restrictive cutting techniques. Where there is an existing cluster of canopy trees, FPL can design the transmission lines to avoid removing the trees with higher structures or shorter or longer spans. FPL will implement tree protection and replacement measures in compliance with the applicable non-procedural requirements of the local government where the clearing is being conducted. Alternately, a contribution to a local government's tree fund may be made, where allowed. ROW preparation also includes construction of access roads and structure pads where required. FPL will evaluate existing access roads, both public and private, for possible use. If necessary, in some instances these existing access roads may need to be improved to accommodate the construction and maintenance equipment needed for the transmission lines. 109 Where new access roads and pads are necessary, they will be constructed with hauled in clean fill material. Culverts will be included in the design of the roads and pads as necessary to maintain existing surface water flow conditions. The next steps in transmission line construction are material hauling and spotting and structure erection. The transmission line poles are trucked to each pole location and can be laid out along the patrol or access road or can be installed as soon as they are delivered to the site. A hole will be augured at each pole location. For the concrete single- pole, this hole will typically be 18 to 25 feet deep and approximately 72 inches in diameter on average. The material excavated from the holes will be spread evenly onto adjacent uplands, either onto existing or recently constructed access roads or pads where appropriate, or be removed from the site. The pole will then be set by the use of cranes and backfilled with crushed rock. The framing process, or installation of hardware and insulators on the poles, may be done with the poles laid on the ground or once erected. Some of the transmission line structures, including most of the structures for the western transmission lines and some of the heavy angle structures for the eastern transmission lines, will also require the installation of anchors and guy wires. 110 Anchors will be either multi-helix screw-in-type anchors or pile-type anchors. Pile-type anchors provide strength applications by embedding a short reinforced concrete pole section to a required depth with backfill. Multi-helix anchors are installed using truck-mounted equipment to screw the anchor into the ground to the required length or torque to meet design requirements. Guy wires will be attached to hardware connected to the anchor extending above the ground and to the transmission line structure. Span lengths can be varied for several reasons. Sometimes a pole location or height is adjusted to avoid a wetland, cluster of canopy trees, or other environmentally sensitive feature, or to coincide with property lines or the location of existing distribution poles that will be displaced. Span length can also be adjusted to accommodate the location or crossing of other electric utility lines or poles, or over highways, canals, or other linear features. Once the poles are in place and the insulator assemblies and hardware are installed, conductors and OHGW will be installed. A rope will be used as a pilot line to pull the conductors and OHGW through the stringing blocks. Conductor pulls will be up to two miles apart, or about 10,000 feet or shorter between dead-end or heavy angle structures. A conductor or OHGW stringing operation typically has a puller at one end of 111 the installation and the conductor reels with the tensioner at the opposite end of the installation. The pilot lines will be pulled in one direction, and the conductors will be pulled in the opposite direction. After pulling, the conductors and OHGW will be spliced together and ultimately sagged (tensioned) to ensure that the conductor is installed with the proper clearance. The conductor will then be attached to the insulator assemblies, and the transmission line will be energized. FPL will minimize the potential for impacts to wetlands during construction through the use of sedimentation control devices to control erosion and turbidity, along with regrading and seeding/mulching of side slopes if needed after construction. The final step in constructing a transmission line is ROW restoration, which is the final clean-up of the ROW after construction is complete. Where necessary, this involves restoring areas that might have been disturbed during construction due to use of heavy vehicles. Restoration may also include stabilizing any potentially erodible areas or replacement of vegetation impacted during construction. FPL will conduct routine maintenance on the ROWs following construction. As is typical and customary for FPL transmission line construction, the transmission lines will require minimal maintenance. Vegetation on and adjacent to the 112 ROWs will be maintained to ensure the safe, reliable operation of the lines. In areas that are not in active agricultural or nursery use, FPL will manage vegetation on the ROW by a variety of methods, including trimming, mowing, and the use of approved growth regulators and herbicides, targeting species that are incompatible with the safe access and operation and maintenance of the transmission system. Where the transmission lines are located along a roadside, very little maintenance of the ROW will need to take place. FPL's management techniques will encourage a broad diversity of vegetation growth to remain on the ROW. FPL will control exotic vegetation within the ROWs in any certified corridor. Applicable Non-Procedural Requirements i. Wetland and Ecological Impacts In selecting the preferred transmission line corridors, and in comparing the alternate corridors proposed by other parties with the FPL preferred corridors, FPL analyzed wetland ecology within all proposed transmission line corridors through a combination of formal wetland delineation in the field, field reconnaissance, review of aerial photography, and review of SFWMD land use/land cover data. FPL conducted a wetlands assessment of the transmission line corridors in accordance with the UMAM. FPL evaluated the amount of mitigation required using the acreage of wetland impact based on 113 a conceptual transmission line design and the average quality of affected wetlands. In addition to reducing impacts to wetlands through collocation with existing linear facilities and reducing the construction footprint of the transmission lines, FPL has submitted a wetland mitigation plan for the entire Project to all reviewing agencies. FPL proposes to mitigate wetland impacts associated with the transmission line portion of the Project through purchase of credits from the agency-approved Hole-in-the-Donut Mitigation Bank and the Everglades Mitigation Bank. The service territory for the Hole-in-the-Donut Mitigation Bank and Everglades Mitigation Bank covers the entirety of the Project area. FPL's proposed wetland mitigation plan for the transmission line impacts will offset the adverse effects, including functional loss, caused by the location, construction, operation, and maintenance of the transmission lines in the certified corridors, and the transmission lines will not cause unmitigated secondary or cumulative impacts to wetlands or surface waters. FPL will use best management practices in constructing the proposed transmission lines to prevent, to the extent practicable, spills, erosion, dust generation, off-site 114 sedimentation, and pollution of waterways and storm drainage systems. No wastes will be discharged during location, construction, operation, and maintenance of the proposed transmission lines without being given the degree of treatment necessary to protect the beneficial uses of the waters of the state. FPL will not discharge any wastewater, stormwater, or groundwater from a transmission line excavation into a storm sewer. In light of the measures proposed in the conditions of certification, construction of the proposed transmission lines will not adversely affect navigation or the flow of water or cause harmful erosion or shoaling. FPL's location, construction, operation, and maintenance of the proposed transmission lines will not result in the discharge of any stormwater, surface water, groundwater, roof runoff, or subsurface drainage to the public sewer system. After construction, during the period that any planted vegetation is being established and afterward during maintenance of its ROW, FPL will comply with all applicable non- procedural requirements for water conservation and environmental resource protection. Location, construction, operation, and maintenance of the proposed transmission lines in the proposed transmission 115 line corridors will not have a significant adverse effect on wildlife habitat or the abundance and diversity of wildlife within that corridor, including listed plant and animal species; will not adversely affect the conservation of fish and wildlife populations, including endangered or threatened species, or their habitats; will not adversely affect the fishing or recreational values or marine productivity in the vicinity; will not adversely impact the functions of wetlands or other surface waters from a wildlife perspective; will not adversely impact the ecological value of uplands to avian or non-avian aquatic or wetland-dependent listed animal species for nesting and denning; and will not be inconsistent with CERP Projects or the overall CERP objectives. ii. Wildlife and Threatened and Endangered Species As noted above, FPL has submitted to all reviewing agencies a comprehensive threatened and endangered species management plan for all listed species for the Project. This plan includes sufficient protection measures for the Florida panther, the American crocodile, and avian species, among other species, regarding the proposed transmission lines. There is little likelihood that panthers are present in the transmission line corridors. In general, Florida panthers are not adversely affected by the presence of transmission lines, structures, fill pads, and access roads 116 within their home ranges. These features actually have the potential to benefit panther conservation by providing new movement corridors; by providing elevated habitat features likely to provide refuges during periods of high water; and by enhancing white-tailed deer populations, the principal prey species of panthers, in the herbaceous wetland habitats adjacent to the transmission line access roads. Location, construction, operation, and maintenance of the proposed transmission lines in any of the corridors proper for certification will not adversely impact the conservation and preservation of Florida panthers or their habitats; will not adversely impact the abundance of Florida panthers; will not adversely impact panther denning; will not impact travel corridors used by Florida panthers; and will not pose an actual or potential threat of adverse impacts to Florida panthers or their habitat, including secondary or cumulative impacts. 329. In the small geographic portion of the proposed corridors where the transmission lines intersect the designated American crocodile critical habitat, FPL has proposed conservation measures to prevent adverse impacts to American crocodiles. FWC has also proposed, and FPL has agreed to, conditions of certification to minimize impacts to American crocodiles. FPL's proposed mitigation measures will far outweigh any impacts to American crocodile habitat. The 117 wildlife protection measures proposed by FPL and the agreed upon conditions of certification, in Attachment 1, Section C.III, are sufficient to prevent adverse impacts to the American crocodile from the location, construction, operation, and maintenance of the transmission lines in any of the corridors proper for certification. The location, construction, operation, and maintenance of the proposed transmission lines in any of the corridors proper for certification will not adversely impact the conservation or preservation of American crocodiles or their habitat; will not adversely impact American crocodile nesting; will not impact travel corridors used by American crocodiles; will not impact the abundance of American crocodiles; and will not have any potential or actual adverse impacts on American crocodiles, including secondary or cumulative impacts. FPL has proposed conservation measures to prevent adverse impacts to Eastern indigo snakes. FWC has also proposed, and FPL has agreed to, conditions of certification to minimize impacts to Eastern indigo snakes. FPL's proposed mitigation measures will far outweigh any impacts to Eastern indigo snake habitat. The wildlife protection measures proposed by FPL and the agreed upon conditions of certification are sufficient to prevent adverse impacts to the Eastern indigo snake from the location, construction, and operation and 118 maintenance of the transmission lines in any of the corridors proper for certification. The location, construction, operation, and maintenance of the proposed transmission lines in any of the corridors proper for certification will not adversely impact the conservation or preservation of Eastern indigo snakes or their habitat; will not impact the abundance of Eastern indigo snakes; and will not have any potential or actual adverse impacts on Eastern indigo snakes, including secondary or cumulative impacts. FPL has proposed conservation measures, including an Avian Protection Plan (APP) to prevent adverse impacts to avian species, including the wood stork, Everglade snail kite, and least tern. FWC has also proposed, and FPL has agreed to, conditions of certification to minimize impacts to avian species. The wildlife protection measures proposed by FPL and the agreed upon conditions of certification are sufficient to prevent adverse impacts to avian species from the location, construction, operation, and maintenance of the transmission lines in any of the corridors proper for certification. Location, construction, operation, and maintenance of the proposed transmission lines in any of the corridors proper for certification will not adversely impact any listed avian species; will not impact the values of wetland or other surface 119 water functions so as to cause adverse impacts to avian species; will not have an actual or potential negative impact on avian species; will not adversely (including cumulatively) impact avian species or avian species conservation, including listed species, or their habitat; will not adversely impact nest locations or nesting behavior of avian species; will not cause adverse impacts to the ecological value of uplands to aquatic or wetland-dependent listed avian species, including nesting locations or nesting behavior; and will not cause adverse impacts to the abundance and diversity of avian species. The location, construction, operation, and maintenance of the transmission lines in accordance with the conditions of certification and the mitigation and species protection plans will not result in the intentional death or injury of migratory birds in violation of the Migratory Bird Treaty Act of 1918, as amended. The location, construction, operation, and maintenance of the transmission lines in any of the corridors proper for certification will not have any adverse impacts to the abundance and diversity of fish or to fish habitat. FWC, SFWMD, and the County have proposed, and FPL has agreed to, conditions of certification to minimize impacts to species, including listed plant and wildlife species. Location, construction, operation, and maintenance of the transmission 120 lines in any of the corridors proper for certification will not significantly adversely affect wildlife populations, including endangered or threatened species, or their habitats, and will not adversely impact the ecological value of uplands to aquatic or wetland-dependent listed animal species for nesting or denning. Public Health and Welfare FPL's proposed transmission lines will comply with applicable non-procedural pre-construction and construction requirements. The proposed transmission lines will comply with good engineering practices and safety standards for the design of such facilities. The design, location, construction, operation, and maintenance of the proposed transmission lines will ensure electric system reliability and integrity for the electric customers served by the transmission lines. Reliable, safe, cost-effective electrical service is in the public interest and supports the general welfare of the community. FPL will dispose of transmission line construction debris in compliance with all applicable non-procedural state, county, and local requirements. The design, location, construction, operation, and maintenance of the proposed transmission lines will comply with 121 all applicable design codes, standards, and industry guidelines, as well as FPL's customary internal design practices, and will have sufficient safety standards to protect the public. This includes compliance with local government public works requirements. Location, construction, operation, and maintenance of the transmission lines will comply with all applicable non- procedural public ROW requirements. FPL will comply with all applicable limitations on parking of large trucks in areas zoned residential during construction of the proposed transmission lines. FPL will maintain traffic during construction of the proposed transmission lines using a certified maintenance of traffic plan that complies with the DOT's Roadway and Traffic Design Standards, the Manual of Uniform Traffic Control Devices for streets and highways, or other applicable non-procedural requirements relating to traffic of the local jurisdiction within which the traffic is being maintained. During construction of the proposed transmission lines, FPL will not locate any temporary office, trailer, portable toilets, equipment, or storage materials and supplies within any temporarily obstructed public roads or ROWs. Waste created by location, construction, operation, or maintenance of the proposed transmission lines will not be 122 allowed to accumulate on the ROW. All waste will be collected on a daily basis during construction and disposed of in accordance with applicable state, county, and local non- procedural requirements. The location, construction, operation, and maintenance of the proposed transmission lines will comply with all applicable noise regulations; will not have an adverse impact on air quality; will not result in harmful quantities of contaminants being released to any existing or potential drinking water resource; and will not result in the creation of depressions in which water can accumulate in a manner that would encourage the propagation of mosquitoes. The proposed transmission lines will comply fully with the applicable Department standards for EMF from transmission lines. See Fla. Admin. Code Ch. 62-814. There is nothing unusual about the levels of EMF from the proposed transmission lines. The EMF levels are within the range to which people are exposed from many sources in everyday environments at home, work, and in public locations. The EMF levels are also many times lower than the international standards for public exposures to EMF and do not pose a health risk to people living or working near the proposed transmission lines. The large body of scientific research on EMF does not provide a reliable scientific basis to conclude that exposure to 123 EMF causes any adverse health effects, including the development or promotion of cancer or neurodegenerative illness in children or adults. The testimony presented by several members of the public claiming cancer or other risks was either unsupported by actual scientific evidence or was based on epidemiological studies whose results were inconsistent and did not establish a causal relationship between EMF and any adverse health effects. Dr. Barredo and Dr. Bailey presented the only credible expert testimony on EMF and health. Based on their detailed expert evaluations of the body of relevant scientific research, the EMF will not have an adverse health effect on the populations living and working near the lines. The proposed transmission lines will not result in any new public access points to public lands. FPL's ROW maintenance will comply with applicable non-procedural requirements related to vegetation in proximity to electric facilities. The location, construction, operation, and maintenance of the transmission lines in compliance with the conditions of certification will not cause harmful interference with microwave communications in South Florida. Archaeological/Historical Considerations In 2009, FPL conducted a preliminary cultural resources survey of the linear facilities associated with the 124 Project, including the associated transmission line corridors. The assessment included a desktop analysis as well as a visual survey. In the context of evaluating the alternate corridors proposed by other parties, FPL updated the preliminary assessment and also evaluated the alternate corridors. The assessment was consistent with the typical practice in the cultural resources profession when evaluating corridors for linear facilities and did not include field surveys. Field surveys will be conducted after the final ROW locations are finalized. 355. The Area of Potential Effect (APE) is the geographic area within which the Project may directly or indirectly cause changes to the character or use of historic properties listed or eligible for listing in the National Register of Historic Places. FPL considered an APE of 100 feet from each side of the proposed transmission line corridors for direct effects to cultural resources and 500 feet from each side of the proposed transmission line corridors for indirect effects to historic resources. The DHR agreed with the APE FPL used in its assessment. The APE for the cultural resources survey to be conducted post-certification will be established in consultation with that agency and will vary depending upon the character of the surrounding built and natural environments and final design and locations of the transmission line structures. The survey 125 of the transmission line ROWs will identify, document, and evaluate any resources that are 50 years or older, both previously recorded and unrecorded, and will include coordination with local governments. Any historical resources that may have been discovered or listed in the National Register of Historic Places or DHR's Florida Master Site File in the intervening time between preparation of the preliminary cultural resources assessment and the full survey will be identified during the post-certification survey. FPL's proposed transmission lines will comply with all applicable federal, state, and local requirements relating to the protection of archaeological and historic resources. FPL will avoid and minimize adverse impacts to historical and archaeological resources in all areas. The City of Miami expressed concerns regarding the proximity of the eastern corridors to historic resources within its boundaries, potential adverse effects on those resources, and the adequacy of FPL's assessment of those resources. The greater weight of the evidence does not support these concerns. Rather, the evidence shows that FPL's assessment was conducted in accordance with typical practice in the cultural resources profession, and that FPL will avoid and minimize adverse impacts to historical resources in all areas. Notably, the DHR concurs with FPL's recommendations. 126 Applicability of Local Government Comprehensive Plans, Zoning Codes, and/or Land Development Regulations Throughout this proceeding, the local governments have argued that FPL should be required to design its transmission lines to comply with local comprehensive plans and LDRs, such as height restrictions and locational constraints. At hearing, Department witnesses testified that the Department interprets the PPSA, and in particular section 403.509, to mean that there are no "applicable" local government comprehensive plans or LDRs for the proposed transmission lines and pipelines in this case. This interpretation of the PPSA is consistent with the plain language of sections 163.3164 and 380.04, is a logical and reasonable interpretation of the law, and should be accorded substantial deference. Moreover, the Department's interpretation of the PPSA was not shown to be contrary to the plain language in the statute or clearly erroneous. If local governments were permitted to regulate the design, height, size, or placement of transmission pole structures, FPL could be unable to implement transmission line designs that comply with necessary industry standards and safety codes, such as the NESC, with which transmission lines must comply; unable to provide service to a designated area or substation; or unable to acquire the necessary uninterrupted contiguous ROW needed between substations and designated service 127 areas. To validate these concerns, it was not necessary, as Coral Gables asserts, for FPL to analyze every zoning and comprehensive plan requirement that might apply, speculate on whether or how it would be applied by the local government, and then predict with specificity how the regulation would impact FPL's ability to build the transmission lines. For these reasons, transmission lines should not be subject to local comprehensive plans or LDRs, such as zoning codes. The Legislature has recognized this imperative by statutorily providing that transmission lines are not considered "development" for the purposes of local government comprehensive plans, LDRs, and zoning ordinances. See §§ 163.3164(14) and 403.50665, Fla. Stat. Local development or zoning regulations and comprehensive plan requirements that might impose constraints on the location, height, or type of transmission lines constructed do not apply to the proposed transmission lines. Economic Impact FPL conducted an analysis of the potential economic impacts of the proposed transmission lines on the municipalities located within the transmission line project areas. The location, construction, operation, and maintenance of the proposed transmission lines are anticipated to have little, if any, effect on the economy of the area or negative fiscal impact 128 on the municipalities located within the transmission line project areas. 363. The transmission lines will serve and protect the broad interests of the public by providing for a safe and reliable electrical system at a cost-effective price. Eastern Transmission Lines Typical Structures and Substation Proposed The following constitutes FPL's proposed eastern transmission lines: Clear Sky-Turkey Point transmission line: a 230-kV line from the proposed Clear Sky substation to the existing Turkey Point substation on the Turkey Point plant property (Clear Sky-Turkey Point); Clear Sky-Davis-Miami transmission line: a 230-kV line running from the proposed Clear Sky substation to the existing Davis substation in southeast Miami-Dade County (Clear Sky-Davis), and another 230-kV line running from the Davis substation east and then north, predominately along U.S. Highway 1, to the existing Miami substation in downtown City of Miami just north of Miami River (Davis-Miami); FPL proposes to locate these transmission lines in the approximately 36.7 miles of the FPL East Preferred Corridor. The entire construction process for the eastern transmission lines will take between 24 and 36 months. As part of this Project, FPL is proposing a new electrical substation, Clear Sky, on the Turkey Point Site in 129 southeastern Dade County. The Clear Sky substation will be connected to, and receive electricity from, proposed Units 6 and 7. That substation will occupy approximately 11.6 acres and will be the starting point for the two proposed 500-kV lines and the three proposed 230-kV lines associated with the Project. The substation site will be fenced and surrounded by a stormwater management area. The proposed Clear Sky substation, existing Turkey Point substation, existing Davis substation, and existing Miami substation are part of the proposed eastern transmission lines, although only the work at the Clear Sky substation is being certified in this proceeding. Work at the other three substations will be permitted separately, if needed. Zoning approval from the County for the construction of the Clear Sky substation as an "unusual use" has already been obtained. For a portion of the Davis-Miami transmission line, FPL proposes to replace an existing, concrete monopole 138-kV line with a double-circuit unguyed 230-kV line on a new concrete monopole designed to accommodate the two circuits, each with separate insulators. This practice is proposed for the approximately two-mile stretch of the FPL East Preferred Corridor along Ponce De Leon Boulevard in Coral Gables. 130 FPL constructs concrete monopole transmission structures throughout its service area in urban, suburban, and rural settings similar to the structures proposed for the FPL East Preferred Corridor. Monopole construction of the type proposed within the FPL East Preferred Corridor, whether guyed or unguyed, follows its usual and customary practice for such lines. Wooden transmission structures are not FPL's customary design for new transmission lines. Where poles are being replaced in urban areas in the east study area, old wooden structures have often been replaced by concrete monopoles as the need arises. The typical height of the proposed 230-kV monopole structures in the FPL East Preferred Corridor is between 80 to 105 feet. (By stipulation, FPL has agreed that within Coral Gables, the poles will not exceed 98 feet in height or 4.1 feet in width.) This is similar to the height of other monopoles FPL has installed in its service area, including several in other parts of the County. While urban density is a factor in corridor selection, it is not determinative as to the siting of a transmission line corridor. FPL provided evidence of numerous 230-kV transmission lines of similar design to the transmission lines proposed for 131 the FPL East Preferred Corridor. These transmission lines are in similar urban areas of FPL's service territory, including areas of Miami-Dade, Broward, and Palm Beach Counties. While sharply conflicting testimony on the issue was presented, the more persuasive evidence established that the transmission lines will be just one of many necessary urban features visible to the eye in the current urban landscape, such as street and traffic lights. Measures can be employed to minimize aesthetic impacts of the lines, such as landscaping to direct the eye away from the structures and adding new vertical elements to blend in with the pole. Numerous similar visible linear features exist in the U.S. Highway 1 multi-modal transportation corridor. The only location where the overhead installation of the proposed eastern transmission lines is not feasible is at the point where the Davis-Miami transmission line crosses the Miami River. An underground crossing of the Miami River is proposed for the Davis-Miami Segment. Corridor Selection Process for East Preferred Corridor FPL East Preferred Corridor 377. In the corridor selection process for the eastern transmission lines, FPL's multidisciplinary team used the same process described in Findings of Fact 269 through 290. 132 The east study area included the Clear Sky, Turkey Point, Davis, and Miami substations and existing FPL transmission ROWs and other linear features that occur between these substations. Between the Turkey Point plant property and the Davis substation area, the study area focused on FPL's existing 330-foot-wide ROW that contains multiple existing 230- kV lines and has space available to accommodate the new Clear Sky-Davis transmission line. From there, the study area was expanded to include numerous available transmission lines, roadways, railways, and other linear features that could provide collocation opportunities to follow to the Miami substation. Much of the east study area is dominated by dense urban and suburban development. It contains several historical districts and sites and a major multi-modal transportation corridor. In addition to the qualitative criteria evaluated for all corridor segments, qualitative criteria for eastern transmission line routes included assessment of crossings for the Miami River, historical districts, the availability and use of Miami-Dade Metrorail and/or Miami-Dade Transit Busway (Busway) ROW, and landscaping. Land uses and constructability constraints were key considerations in the east. FPL's corridor selection process attempted to reflect a reasoned balancing of the need for the transmission lines 133 against the potential impact on both the public and the environment. After evaluation of all identified route alignments and significant consideration of public input throughout the community outreach program, FPL selected the East Preferred Route and delineated corridor boundaries for the route. Filing of Alternate Corridors During this process, one alternate corridor was proposed jointly by Coral Gables and Pinecrest, referred to as the Pinecrest/Coral Gables Alternate Corridor (PAC), for the portion of the FPL East Preferred Corridor from the area east of the Davis substation to the Miami substation. The PAC is described in more detail below. Eastern Transmission Line Corridors Proper for Certification FPL and the Department filed notices of acceptance of the PAC. The Department determined that both the FPL East Preferred Corridor and PAC met the criteria for certification. While both the FPL East Preferred Corridor and PAC are proper for certification, the multidisciplinary team recommended, and FPL is seeking certification of, the East Preferred Corridor and opposes certification of the PAC. 134 FPL East Preferred Corridor General/Constructability Through the corridor selection process described above, FPL selected the East Preferred Corridor and delineated corridor boundaries. The FPL East Preferred Corridor is of variable width. This flexibility allows FPL to accommodate localized conditions, respond to future development between the times of corridor selection and construction, take advantage of certain collocation opportunities, and avoid siting constraints or utilize existing or relocated FPL ROWs. For the east 230-kV transmission lines, the typical span length in the FPL East Preferred Corridor will range from approximately 200 to about 700 feet, depending on location- specific factors, ROW widths, and other design considerations. No new access roads or structure pads are anticipated to be needed in the FPL East Preferred Corridor. The FPL East Preferred Corridor exits the Turkey Point plant property to the north and continues in a general north-south orientation following an existing FPL transmission line ROW. It follows this ROW west towards the Florida Turnpike, then northwestward to U.S. Highway 1, and then extends generally north to the Davis substation. The FPL East Preferred Corridor then continues generally east to the U.S. 1 corridor, then generally north following the U.S. Highway 1 corridor with 135 expansions around the downtown Kendall area and certain Metrorail stations, and terminating at the Miami substation immediately north of the Miami River in downtown City of Miami. In the FPL East Preferred Corridor, there is also a short proposed 230-kV transmission line between the proposed Clear Sky substation and the existing Turkey Point substation, both within the Turkey Point plant property. The Clear Sky-Turkey Point portion of the Corridor is approximately 0.4 miles long; the Clear Sky-Davis portion is approximately 19 miles long; and the Davis-Miami portion is approximately 17.7 miles long. Location, construction, operation, and maintenance of the Davis-Miami transmission line in proximity to the Metrorail facility in compliance with the conditions of certification will not interfere with operation of the Metrorail. Location, construction, operation, and maintenance of the Davis-Miami transmission line in proximity to the Metrorail facility in compliance with the conditions of certification will not exceed safety or industry limits applicable to the Metrorail facilities. Location, construction, operation, and maintenance of the Davis-Miami transmission line will not interfere with the use of U.S. Highway 1 as a multi-modal transportation corridor. 136 Location, construction, operation, and maintenance of the Davis-Miami transmission line will not interfere with the possible future southward extension of the Metrorail within the 100-foot Busway ROW. Location, construction, operation, and maintenance of the eastern transmission lines in either of the eastern corridors will not cause obstructions to visibility. FPL East Preferred Corridor: Land Use The FPL East Preferred Corridor leaves the proposed Clear Sky substation and passes through Homestead Bayfront Park, heading north and west. It then passes through a largely agricultural area with existing transmission lines. Shortly before reaching the Davis substation, it crosses into low density residential land use. From the Davis substation, the East Preferred Corridor proceeds east along an existing FPL transmission line ROW until its intersection with U.S. Highway 1, then northeast along U.S. Highway 1 and the Busway before reaching the Kendall Urban Center or Dadeland area. U.S. Highway 1 is a principal arterial roadway with six traffic lanes. For most of this segment along the U.S. Highway 1/Busway ROW, the Corridor is approximately 200 feet wide, ranging in width from approximately 200 feet to 350 feet. The FPL East Preferred Corridor in this area is co-located with a wide multimodal transportation 137 corridor. In this segment, the northern tip of the Village of Palmetto Bay and the western edge of Pinecrest are on the eastern edge of the Corridor, with the remainder of the Corridor being in unincorporated Miami-Dade County. The land uses within this segment are primarily commercial, with two parks on the east side of the Corridor, and industrial, commercial, and single-family residential uses on the west side. There are a limited number of cross streets compared to the east side of the Corridor. In the area of the County-designated Kendall Urban Center, the FPL East Preferred Corridor widens to allow greater flexibility. In this segment, the Corridor is bounded by commercial and multi-family residential development. The Corridor here also includes ROWs for several existing linear features such as State Road 826 and the SFWMD's ROW along Snapper Creek. The next segment of the FPL East Preferred Corridor narrows to follow the U.S. Highway 1/Metrorail ROW and stretches northeast through South Miami and Coral Gables, and into the City of Miami. For this segment, the Corridor ranges between 150 feet to 300 feet in width. Within South Miami, there is fairly continuous commercial development along the east side of U.S. Highway 1, including the Shops at Sunset and other highway strip commercial use. Uses along the west side of the Corridor 138 in South Miami include some single-family residential, South Miami Hospital, City Hall, South Miami Metrorail Station, and industrial uses. This segment then crosses Southwest 57th Avenue (Red Road), entering Coral Gables. Within Coral Gables, in addition to the Metrorail guideway, the M-Path, and U.S. Highway 1, the Corridor expands to include the Ponce de Leon Boulevard ROW and an existing 138-kV transmission line. This area has, from west to east, the University of Miami (with a large campus extending to the west), some commercial, multi- family, and single-family development on the west side of Ponce de Leon Boulevard, and the Metrorail guideway between Ponce de Leon Boulevard and U.S. Highway 1, and commercial development east of U.S. Highway 1. Farther north within Coral Gables, adjacent to the Corridor is multi-family residential and commercial development, including the Village of Merrick Park (a shopping mall), and an industrial area. In the portion of the Corridor along U.S. Highway 1, which contains limited single- family development, those homes are generally oriented away from U.S. Highway 1. Upon entering the City of Miami, the Corridor widens to include the Coconut Grove substation at Douglas Road (Southwest 37th Avenue) and Bird Road (Southwest 40th Street). Commercial development exists on either side of Bird Road in this portion of the segment. The Corridor returns to the U.S. Highway 1/Metrorail ROW, with single-family residential land use 139 on the northwest offset by a frontage road, and commercial land uses bordering the southeast side, with residential farther beyond. The Corridor then widens again around the Coconut Grove and Vizcaya Metrorail stations. In the next segment, the Corridor enters downtown City of Miami before the subaqueous crossing of the Miami River. Land uses in this area include single family, multi-family residential, Simpson Park, and commercial. It also crosses the City of Miami-designated Coral Way scenic transportation corridor in the vicinity of Interstate Highway 95 (I-95). Industrial and commercial uses are also adjacent to the Miami River in this area. The eastern transmission lines in either of the eastern corridors will be generally compatible with the communities' priorities and preferences as reflected in their comprehensive plans and LDRs. FPL East Preferred Corridor: Environment Most of the FPL East Preferred Corridor has been altered from its natural state. Surface waters are limited to canals, ditches, channelized waterways, and reservoirs. Closer to the Turkey Point Plant site, a variety of wetland communities of varying quality and types exist, including forested and herbaceous wetlands. Beyond this area of wetlands, wildlife habitats within the Corridor are generally lacking or absent in 140 the agricultural and urbanized uplands. Construction of the proposed transmission lines in this area would use existing transmission line and other ROWs, and existing access roads and structure pads where they are needed, limiting wetland and surface water impacts to less than one-half acre, requiring less than one-half credit of mitigation. 402. None of the lands within the Corridor contain native terrestrial ecological attributes in significant amounts. However, there is a small area of the Corridor that includes upland forest classified as NFC by the County within Simpson Park. There are also some NFCs adjacent to but not within the Corridor near the Davis substation. There is very little wildlife habitat value found north of Davis substation. South of the Davis substation, the native upland and wetland communities are limited and generally small. The presence of the existing transmission lines, adjacent agricultural operations, and other development means that existing wildlife communities have already adapted to these man-induced habitats in that area. 403. FPL will avoid and minimize impacts within the Simpson Park NFC and, to the extent practicable, will avoid placing any of the transmission lines within the NFC. FPL will only conduct minimum tree trimming, pruning, or topping of trees in the NFC to meet ANSI standards. High visibility markers will 141 be installed to protect trees in the NFC during construction. Exotic vegetation within the ROW in the NFC shall be controlled to the extent practicable. Impacts to this NFC or other NFCs due to placement of the proposed transmission lines in the Corridor are anticipated to be insignificant. 404. A portion of the Corridor, no more than 0.2 miles long immediately north of the Units 6 and 7 site, is within designated critical habitat for the American crocodile. The area of overlap is largely occupied by other proposed facilities, including the nuclear administration building, the construction and contractor parking area, and the training building. This area is largely void of vegetation and is primarily rock fill. As the Corridor progresses north beyond the area of designated critical habitat, it enters a highly urbanized area. No part of the Corridor is suitable for crocodile basking, nesting, or foraging. 405. American crocodiles are not commonly observed in the area of the FPL East Preferred Corridor. 406. Eastern indigo snakes, classified as threatened by USFWS and FWC, are not commonly found in southern Florida and are not commonly observed in the FPL East Preferred Corridor. Two recorded observations of Eastern indigo snakes occurred in the southern end of the Corridor in 2011. There is a moderate 142 likelihood of Eastern indigo snake occurrence within the Corridor south of the Davis substation. 407. The FPL East Preferred Corridor is entirely outside of the PFA and would not affect Florida panthers or their habitats. 408. The eastern transmission lines if constructed in either of the eastern corridors will not cause a flood hazard. FPL East Preferred Corridor: Traffic 409. There will be some temporary, short-term impacts to traffic during construction of the proposed transmission lines within the FPL East Preferred Corridor, but no permanent or long-term impacts to traffic or traffic flow patterns will occur. Transmission line construction may require closure of one or more traffic lane segments among the six or four lanes within the Corridor, particularly in the area of U.S. Highway 1. To avoid closure of a high-volume traffic lane, construction in most segments of the Corridor would occur at night. 410. The Corridor is compatible with DOT and Miami-Dade Transit long-range plans. The PAC General/Constructability 411. The PAC begins east of the Davis substation, where the FPL East Preferred Corridor along Southwest 131st Street intersects with the existing ROW for the North-South segment of 143 the FPL Turkey Point-Flagami transmission lines in the Kendall area. From there, the PAC continues north along the existing transmission line ROW for approximately 10.15 miles to FPL's - Flagami substation. From the Flagami substation, the PAC continues east for approximately 11.2 miles to FPL's Miami substation. The total length of the PAC where it diverges from the FPL East Preferred Corridor is approximately 21.35 miles. 412. The Flagami-Miami (i.e., east-west) portion of the PAC mostly follows very narrow residential streets with typically only 50-foot wide ROWs. Except for a few areas with a ROW of 50 to 80 feet, however, the FPL East Preferred Corridor does not have this narrow configuration. 413. While there are several other utility lines in the PAC, those lines are not in FPL-controlled or owned ROWs. The public ROWs are typically only 50 feet wide along narrow residential streets. To add another transmission line to those pole locations would require reconstruction of the poles to allow for a double-circuit configuration. As noted above, where double circuits are installed on a pole, two sets of insulators are also required to be installed, one set for each circuit. This configuration in ROWs along narrow residential streets would require acquisition of private strip easements along the frontage of hundreds of residential and commercial lots, with sets of conductors overhanging front yards, or removal of on- 144 street parking, swales, or vegetation to place the poles in those spaces. In some cases, there are buildings with no setbacks, precluding placement of a double-circuit pole. The PAC: Land Use 414. As the PAC diverges from the FPL East Preferred Corridor, the first segment stretches northward through unincorporated Miami-Dade County along the existing ROW for the North-South segment of the FPL Turkey Point-Flagami Kendall transmission lines in the Kendall area toward the Flagler Street area. Land uses vary from residential to commercial and also include some municipal and multi-family residential areas. 415. The second segment of the PAC extends from west to east between Southwest 92nd Avenue and Southwest 61st Avenue. Originating in unincorporated Miami-Dade County, the existing public road ROWs in this area are generally 50 feet wide. The PAC also encompasses an existing 138-kV transmission line in this area. This segment begins with a mix of residential areas, including townhomes and estate-zoned areas, and transitions toward more intense residential uses. Progressing into the City of Miami, the PAC enters dense, older neighborhoods. The residential home setbacks are shallower and the ROWs include sidewalks, parking spaces, and driveway access areas, which limit room for additional facilities. In addition, underground utilities likely exist within the ROWs. Depending on the 145 alignment of the Davis-Miami transmission line within the PAC, construction may require demolition of a residence. While most ROW in this City of Miami area is approximately 60 feet wide, Flagler Street along the northern edge of the PAC has a 100-foot ROW and an existing 138-kV transmission line. Throughout this segment, the residential uses face onto the proposed corridor. 416. Farther east into the City of Miami, the third segment of the PAC extends from west to east between Northwest 61st Avenue and Northwest 26th Avenue. This segment begins with largely single-family residential areas and transitions to multi-family residential, with as many as 65 dwelling units per acre in certain areas. It also includes elementary and middle schools. ROWs are approximately 50 and 60 feet in width. 417. The next segment of the PAC extends from west to east from Northwest 26th Avenue to Southwest 7th Avenue and also contains areas of 65 dwelling units per acre. Depending on the alignment, two aerial crossings of State Road 836 (an elevated roadway) may be required, which could require taller poles. Farther east, there are no existing transmission lines available for collocation. The higher-density residential neighborhoods have limited setbacks and contain primarily 50-foot road ROWs, occupied with sidewalks, parking, and driveway access, and homes facing the roadway. ROWs are as narrow as 30 or 45 feet in certain areas. For Americans with Disabilities Act compliance, 146 transmission line structures may have to be placed in what are currently parking areas. In addition, buildings with zero-foot setbacks in certain areas present design constraints. 418. Southwest 7th Avenue and Southwest 2nd Avenue bound the final segment of the PAC. In this area, the PAC approaches José Martí Park. It then encompasses the Miami River and I-95 before ultimately connecting to FPL's existing Miami substation. The PAC: Environmental 419. From the proposed Clear Sky substation to the Davis substation area, the PAC coincides with the FPL East Preferred Corridor. As such, the land uses and vegetation within the PAC in this area are identical to those described for the first segment of the FPL East Preferred Corridor. Similarly, wetland and surface water impacts throughout the PAC will be limited to less than one-half acre and would require mitigation of less than one-half credit. None of the lands within the PAC contain native wetland ecological attributes in significant amounts. 420. Wetlands and surface waters within the PAC are limited primarily to low quality, man-made ditches and canals that can be spanned. The construction of the proposed transmission lines would use existing transmission line ROW, existing access roads, and existing structure pads. Wetland and surface water impacts will be limited to less than one-half acre 147 and would require mitigation of less than one-half credit of mitigation. Where the PAC diverges from the FPL East Preferred Corridor, it traverses an existing transmission line ROW south of the Flagami substation and highly developed residential and commercial areas east of the Flagami substation that do not provide quality wildlife habitat. One federally-designated threatened plant species (Garber's Spurge) is recorded within the PAC. There is no difference between the FPL East Preferred Corridor and the PAC with regard to the presence of or impacts to American crocodiles, Eastern indigo snake, Florida panther, avian species, or fish species or habitat. The PAC: Traffic There will be some temporary, short-term impacts to traffic during construction of the proposed transmission lines within the PAC, but no permanent impacts to traffic or traffic flow patterns will occur. Because the PAC largely consists of two-lane roadways with narrow ROWs, lane closure for construction would require flag personnel to direct one lane of traffic in two directions. Because traffic volume in that area is not significant, construction within the PAC can be conducted during the day, though construction in certain road segments should be 148 conducted during night hours to avoid significant traffic disruptions. e. Hardening or Improving Existing Transmission Lines Within the PAC Coral Gables and Pinecrest argue that FPL should abandon its FPL East Preferred Corridor in favor of the PAC, which already contains existing 138-kV transmission lines. Their witnesses assert that co-locating the proposed Davis-Miami transmission line with existing 138-kV transmission lines in the PAC between the Flagami and Miami substations would provide an opportunity to harden or improve existing substandard or wooden poles by relocating existing transmission lines onto new, double-circuit concrete poles constructed for the 230-kV transmission line, thereby increasing reliability. No credible evidence was presented that certification of the PAC would necessarily result in the hardening or improvement of existing lines there, once FPL considered all relevant factors for final design of the new Davis-Miami transmission line, beyond FPL's routine hardening or improvement of its transmission lines. Moreover, there is no credible evidence to rebut the testimony of FPL's transmission line engineer regarding the proposed design. In any event, a double- circuit configuration with one circuit on each side of the pole, 149 a configuration suggested by Coral Gables and Pinecrest, cannot be accommodated along many locations within the PAC. While the Davis-Flagami segment of the PAC contains sufficient room to co-locate with existing FPL transmission lines, it contains significant barriers to placing the new transmission line on new poles together with the existing FPL transmission lines. In this segment, the road ROWs do not have sufficient width to accommodate the new, larger poles proposed for the Davis-Miami transmission line. This segment primarily contains narrow, two-lane residential streets with limited space, where sidewalks, road-side parking areas, and improvements on private, residential lots present a conflict for these larger poles. Co-locating an existing transmission line with the new transmission line on a single, double-circuit pole is not technically feasible in many areas of the PAC due to space constraints. For example, where a single-circuit transmission line pole is currently located adjacent to buildings that are built to the edge of the street, replacement of that pole with a larger double-circuited pole may not be technically feasible. The new transmission line structure may need to be installed across the street, resulting in transmission lines along both sides of the street, or moved to another street entirely. 150 429. In addition, FPL routinely engages in hardening or improvement of its existing transmission lines as a standard and customary business practice, including replacing existing wooden structures with concrete monopoles as the need arises. Such hardening and improvement along the PAC will occur through FPL's normal course of hardening as pole replacement is needed. Eastern Transmission Line Construction and Design Standards Undergrounding 430. City of Miami, Coral Gables, South Miami, and Pinecrest have urged the Siting Board to require undergrounding of the transmission line in their own jurisdictions and rely upon their local comprehensive plans and local regulations in support of their position. Although the County originally proposed undergrounding of the eastern transmission lines, the County and FPL have reached agreement on conditions for placement of the eastern transmission lines overhead in either of the eastern corridors. 431. Credible preliminary estimates indicate that undergrounding the Davis-Miami transmission line within the FPL East Preferred Corridor would cost approximately $13.3 to $18.5 million per mile. These numbers compare to a cost range of $1.5 to $2.5 million per mile for overhead facilities, with a cost differential of $10.8 to $17 million per mile. Thus, 151 underground construction in this area would be roughly nine times more expensive than overhead construction. 432. Extreme weather events do not require undergrounding transmission lines in the FPL East Preferred Corridor. 433. FPL generally uses underground design where overhead construction is not feasible or the requesting entity pays the incremental cost of underground construction. With the exception of the Miami River Crossing, no engineering constraints require the use of undergrounding. Miami River Crossing 434. Construction of the Davis-Miami 230-kV transmission line in any corridor proposed for the Davis-Miami transmission line will require an underground crossing of the Miami River. 435. In the area where the Davis-Miami transmission line crosses the Miami River, the Miami substation is bounded by the I-95 bridge west of Second Avenue and the Metrorail bridge to the east. These fixed bridges and their vertical clearances required for navigation prohibit the use of an overhead transmission line design into the Miami substation. Due to this engineering constraint, placement of the transmission line underground is the only technically feasible alternative. Accordingly, FPL proposes undergrounding the eastern transmission line at the Miami River Crossing. 152 436. A transition or termination structure will be required where the underground portion of the transmission line transitions to overhead. North of the Miami River, the termination structure will be within the Miami substation fence. South of the Miami River, the location of the transition structure has not been finally determined, but preliminarily its location has been identified as somewhere along Third Avenue on a private easement. 437. The proposed Miami River crossing is located within the Biscayne Bay Aquatic Preserve. This crossing requires an easement over sovereign submerged lands from the Board of Trustees, which was requested by FPL through this proceeding. FPL has existing underground transmission lines that cross the Miami River to the south of the Miami substation, with associated sovereign submerged lands easements. 438. The Miami River crossing can be constructed using horizontal directional drill technology. Construction of the Miami River crossing is a water-dependent activity. 439. The transmission line crossing of the Miami River is a "structure required for the installation or expansion of public utilities," constitutes "[r]easonable improvement for . . . public utility expansion," and is specifically allowed by the statute that created the Biscayne Bay Aquatic Preserve. § 258.397, Fla. Stat.; Fla. Admin. Code R. 18-18.006(3)(b)(iv)7. 153 Placement of the transmission line in the sovereign submerged lands easement will not disturb submerged land resources or result in unmitigated adverse impacts to sovereign lands. The underground transmission line will be constructed and operated in compliance with all applicable codes, standards, and industry guidelines. FPL will use best management practices in constructing the underground transmission line beneath the Miami River. The design, location, construction, operation, and maintenance of the proposed transmission line beneath the Miami River will ensure electric system reliability and integrity for electric customers served by the transmission line. FPL owns the existing Miami substation, but must acquire any necessary private property interests for the transmission line easements north and south of the sovereign submerged lands at the Miami River. The Miami River crossing will be designed and constructed to avoid restriction or infringement on riparian rights of adjacent upland owners. No wetland vegetation will have to be removed, cut, or destroyed to place the transmission line in the sovereign submerged easement for crossing the Miami River. There will not be any impacts to the shoreline from placement of the transmission line in the sovereign submerged lands easement for 154 crossing the Miami River. In this area, the Miami River is within bulkheads and seawalls. Though temporary construction impacts will occur, the area affected by the underground installation will be restored soon after construction and there will not be any permanent impacts to property owners along the Miami River as a result of the transmission line crossing. Construction of the underground portion of the transmission line beneath the Miami River will not affect navigation or the flow of water or cause harmful erosion or shoaling. During location, construction, operation, and maintenance of the underground portion of the transmission line, no wastes will be discharged without being given the degree of treatment necessary to protect the beneficial uses of the waters of the state. Likewise, harmful quantities of contaminants will not be released to any existing or potential drinking water source. The location, construction, operation, and maintenance of the underground portion of the transmission line will not have an adverse impact on air quality and will not result in any new public access points to public lands. Placement of the underground transmission line in the sovereign submerged lands easement will not detract from or 155 interfere with propagation of fish and wildlife, or traditional recreational uses. Rather, it will minimize adverse impacts on fish and wildlife habitat and other natural and cultural resources. Placement of the transmission line beneath the Miami River in the sovereign submerged lands easement is consistent with the Biscayne Bay Aquatic Management Plan. Placement of the transmission line beneath the Miami River in the sovereign submerged easement is clearly in the public interest. Maintenance of Hydrology/CERP Consistency FPL has submitted flowage easements to the County that provide for maintenance of existing flow across transmission corridors within the Biscayne Bay Coastal Wetlands CERP Project study boundaries and allowing improvements to sheet flow consistent with planned restoration projects in the area. These easements satisfy the requirements of Condition 17 of County Resolution Z-56-07. The eastern transmission lines in either of the eastern corridors are not inconsistent with CERP Projects or the overall objectives of CERP. Economic Impacts The Davis-Miami transmission line in the FPL East Preferred Corridor will have no quantifiable effect on property 156 values of adjacent properties. The evidence supports a finding that transmission lines will not adversely affect non- residential property values. Also, the more persuasive evidence shows that the effect on residential property values will be de minimis and below the levels that could be quantified to a reasonable degree of certainty. Accordingly, the placement of the proposed Davis-Miami transmission line within the FPL East Preferred Corridor will have little, if any, effect on the economy of the area or the fiscal situation of the municipalities. 455. The analysis regarding the transmission line's impact on property values within and adjacent to the FPL East Preferred Corridor and the PAC presented by Dr. Frishberg, a Coral Gables expert, was imprecise, methodologically flawed, and irrelevant to the extent it did not appropriately address the substantial amount of non-residential properties in both corridors. The analysis of Dr. Weisskoff, a public witness, was also flawed in several respects. For example, his analysis is based on a misrepresentation of the published literature, contained a substantial calculation error, and failed to take into account several important variables affecting property value impacts. Therefore, these witnesses' testimonies are not credited. 157 Clear Sky Substation 456. Construction of the Clear Sky substation expansion will require clearing and grubbing the expansion area. Turbidity screens and other erosion control devices and techniques will be used to minimize construction impacts to nearby wetlands and water bodies. The expanded substation yard area will be excavated, filled with clean fill that is trucked to the site, graded, and rolled to provide the necessary elevation. A new grounding grid will be constructed and a new security fence around the expansion area will be installed. Compliance with Design Standards 457. All of the transmission lines, including the Clear Sky substation, will be constructed and operated in compliance with all applicable design codes, standards, and industry guidelines, including NESC, the Department's EMF standards, and the industry standards adopted by ASCE, ASTM, ANSI, ACI, and the Institute of Electronic and Electrical Engineers. 6. Applicable Non-Procedural Requirements for Eastern Transmission Facilities a. Zoning Regulations and Comprehensive Plans As noted above, local zoning regulations and comprehensive plan requirements are not applicable non- procedural requirements for transmission facilities. To the extent local ordinances have been incorporated into the 158 conditions of certification, FPL has committed to comply with them. Otherwise, the often competing zoning regulations of local jurisdiction are not applicable. b. Work in SFWMD Rights-of-Way FPL's Davis-Miami transmission line will cross several SFWMD canals and may use a portion of SFWMD ROW along the Snapper Creek Canal. There are no levees within the vicinity of the FPL East Preferred Corridor. Location, construction, operation, and maintenance of the Davis-Miami transmission line will comply with the requirements for SFWMD ROW Occupancy Permits and, as such, will not interfere with the SFWMD's access, operations, or maintenance of the works of the district. Location, construction, operation, and maintenance of the eastern transmission lines in compliance with the conditions of certification will not interfere with the present or future construction, alteration, operation, or maintenance of the works or lands of the SFWMD that are crossed. This applies only to proposed future construction, alteration, operation, or maintenance known at the time of FPL's project design. Location, construction, operation, and maintenance of the proposed eastern transmission lines will comply with applicable SFWMD non-procedural requirements, including 159 requirements of the Criteria Manual for Use of Works of the District. c. Other Non-Procedural Requirements The location, construction, operation, and maintenance of the proposed transmission lines will comply with applicable Department non-procedural environmental resource permitting criteria and other regulations. The location, construction, operation, and maintenance of the transmission lines in either of the eastern transmission line corridors will comply with the tree ordinances of the local governments in which the facilities will be located. The City of Miami raised concerns over impacts to tree canopy and the replacement of trees that must be removed within the final ROW within the City. A City witness testified that it was her preference that FPL do more than comply with the City of Miami's tree ordinance in siting and constructing the transmission line within the City. To this end, FPL will comply with the City's tree ordinance, and it will confer with local officials to identify areas of tree canopy that can be spanned or addressed by other engineering solutions, to relocate or replace trees that must be removed, or mitigate for impacts by paying into a tree fund. Within the City of Miami, the amount of tree removal in either of the eastern corridors will be 160 similar. The City also desires a condition of certification requiring FPL to not only comply with the City's tree ordinance, but also to submit a tree survey, a tree disposition plan, and a landscape plan to replace any trees prior to doing any work within the City of Miami, and to install transmission poles to avoid large, existing trees to the extent practicable. FPL has committed to a condition of certification to address each of the items. 465. If constructed within either the East Preferred Corridor or the PAC, the proposed Davis-Miami transmission line will comply with the applicable non-procedural requirements of the local governments in which it will be located. These applicable non-procedural requirements include the requirements within the City of Miami, Coral Gables, South Miami, and the County that (1) FPL construct and maintain transmission lines in accordance with its customary practice; (2) FPL transmission lines not unreasonably interfere with traffic on public ROW or reasonable egress from and ingress to abutting property; (3) FPL transmission lines be located as close to the outer boundary of public ROW as practicable, or as agreed with the local government; and (4) FPL repair or restore any damage to public ROW caused by construction or maintenance of transmission lines. 466. During construction of the proposed Davis-Miami transmission line within the City of Miami, FPL will not 161 excavate, dig up, or obstruct any public street or sidewalk in a manner that creates an obstruction for more than two adjacent blocks at a time. If any such obstruction is required, FPL will complete the work on one block before proceeding to work in the second block. 467. If any sidewalk must be reconstructed following construction of the Davis-Miami transmission line within the City of Miami, FPL will use only natural, uncolored Portland cement concrete for that sidewalk reconstruction. 468. If any road pavement must be repaired following installation of the proposed transmission line within the City of Miami, FPL will use paving of a long-life, hard-surfaced type with sufficient base to ensure lasting service and a minimum expense for maintenance, as chosen in consultation with the City's Public Works Department. Eastern Corridors Comparison: Least Adverse Impacts, Including Cost Comparison of Land Use Considerations 469. While the final ROW for the Davis-Miami transmission line will be identified post-certification during final design, preliminary alignments within the PAC and the FPL East Preferred Corridor were identified to facilitate comparisons between the two corridors where they diverge. FPL analyzed three routes to compare the proposed eastern corridors: (1) a route within its 162 East Preferred Corridor (the EPC Alignment); (2) the alignment identified by Pinecrest and Coral Gables within the PAC (the PAC Alignment); and (3) an alignment identified by FPL's engineers that they believe constitutes a more technically feasible alignment within PAC than the PAC Alignment (the 2013 Alignment). 470. The PAC Alignment has 2,829 buildings within 200 feet of the alignment; the 2013 Alignment has 2,746. These figures reflect the density within the PAC. In contrast, the EPC Alignment has only 762 buildings within 200 feet of the alignment. The transmission line, if built within either of the PAC Alignments, would be in proximity to three times more buildings than the EPC Alignment. 471. The PAC Alignment would cross or abut 1,217 separate parcels; the 2013 Alignment would cross or abut 1,164. In contrast, the EPC Alignment would cross or abut only 363 separate parcels. The transmission line, if built within either of the PAC Alignments, would cross or abut three times more parcels than the EPC Alignment. 472. There are 15 schools within 200 feet of the PAC Alignment and 14 schools within 200 feet of the 2013 Alignment; there are eight schools within 200 feet of the EPC Alignment, including the University of Miami. 163 473. There are more residential uses and smaller lots along the PAC. In contrast, more commercial parcels of larger size are along the FPL East Preferred Corridor. 474. Along the PAC Alignment, the available road ROW space is generally only 50 feet in width, rendering it generally too narrow for the construction of the necessary double-circuit transmission line structures suggested by Pinecrest and Coral Gables without acquiring additional ROW space on adjacent private property, much of which is dense residential development on shallow, narrow lots. However, along the EPC Alignment, the available road/Metrorail ROW is generally 200 feet wide or wider, making it less likely that FPL will need additional ROW space on adjacent private property. Comparison of Engineering/Constructability Considerations 475. Where the FPL East Preferred Corridor and PAC diverge, both contain collocation opportunities. While the total length of existing FPL transmission lines for collocation along the PAC Alignments may be greater than the total length along the EPC Alignment, the Flagami-Miami segment of the PAC has significant barriers to implementing collocation with those existing FPL lines. 476. Besides the narrow ROWs along the PAC Alignments, there are many obstructions such as sidewalks, fences, porches, 164 and other improvements which constrain construction of the Davis-Miami transmission line as proposed by Pinecrest and Coral Gables. In contrast, along most of the EPC Alignment, the ROW has a larger amount of available open space with few obstructions. There is greater potential conflict with underground utilities along the PAC than the FPL East Preferred Corridor. This is due to the greater likelihood of underground utilities parallel to streets, perpendicular lateral lines to service the homes in the PAC, and limited flexibility to adjust pole locations to avoid such constraints. Proximity of the PAC to the Miami International Airport will require notification to the FAA and possibly the Miami-Dade Aviation Department for crane operations during construction. There are no airports near the FPL East Preferred Corridor for the Davis-Miami transmission line. The cost of constructing the Davis-Miami transmission line within the PAC Alignment, including the cost of acquiring the necessary ROWs, ranges from $83.1 million to $107.7 million; the cost of construction within the 2013 Alignment within the PAC ranges from $77.8 million to $100.6 million. In contrast, the cost of construction of the Davis-Miami transmission line within the EPC Alignment ranges from $50.7 million to $68.6 million. 165 Comparison of Environmental Considerations There are no material differences in environmental considerations between the PAC and the FPL East Preferred Corridor. There is no material difference between the FPL East Proposed Corridor and the PAC from a wetlands impacts or wetlands mitigation perspective. Construction of a transmission line within either of the two corridors would not impact any significant amount of wetlands or surface waters. The FPL East Preferred Corridor and the PAC are similar with respect to the likely magnitude of effects on the abundance and diversity of wildlife resulting from construction of a transmission line. From the point the FPL East Preferred Corridor and PAC diverge, approximately two miles east of the Davis substation, they largely traverse similar areas of dense urban development to reach the Miami substation. Neither corridor traverses high quality wildlife habitat or has the potential to impact listed species. Therefore, no adverse effects upon wildlife abundance and diversity would be anticipated. FPL will minimize impacts to NFCs in the FPL East Preferred Corridor, avoiding impacts to the extent practicable, consistent with the NFC standards and requirements contained in chapter 24, MDC. The PAC does not cross a NFC. 166 There is no difference between the FPL East Preferred Corridor and the PAC with regard to impacts to American crocodiles; both must cross the same 0.2-mile area. There is no difference between the FPL East Preferred and the PAC with regard to impacts to Eastern indigo snakes. Avian issues are minimal with both of the proposed corridors, and there is no significant difference between the two corridors. From the standpoint of impacts to Florida panthers and their habitat, there is no difference between the FPL East Preferred Corridor and the PAC because both corridors traverse urbanized, developed areas of the County outside of the PFA, and panthers are not likely to occur in those areas. Comparison of Traffic Impacts No material difference exists between the traffic impacts anticipated in the FPL East Preferred Corridor and the PAC. Both the PAC and the FPL East Preferred Corridor will involve moderate to significant disruption of traffic during the temporary construction activities. Construction in the FPL East Preferred Corridor requires lane closure in a higher-volume roadway (U.S. Highway 1) and would be limited during peak traffic hours. Construction in the PAC would impact lower- volume roadways and would not be limited to nighttime hours, but 167 would require flag personnel to direct one lane of traffic in two directions. Archaeological and Historic Sites There is no material difference between the FPL East Preferred Corridor and the PAC in terms of impacts to archaeological or historic resources. Location, construction, operation, and maintenance of the proposed transmission lines in accordance with the conditions of certification in either of the eastern transmission line corridors will not adversely impact archaeological or historic structures, sites, or resources, given the level of disturbance and alteration in both corridors. Summary Because of significant constructability issues and land use constraints within the PAC and in light of the relative costs for placement of the Davis-Miami transmission line within the two eastern corridors proper for certification, the FPL East Preferred Corridor represents the corridor which, on balance, has the least adverse impacts, including costs, considering the criteria in section 403.509(3). Western Transmission Lines Typical Structures and Substation Proposed 491. The following constitute FPL's proposed western transmission lines associated with the Project: 168 From the proposed on-Site Clear Sky substation, FPL is proposing two 500-kV lines extending west and then north to the existing Levee substation. The total length of this alignment of the West Consensus Corridor/MDLPA No. 2 and FPL West Preferred Corridor is approximately 43.6 miles. From the proposed Clear Sky substation, FPL is also proposing to extend a 230-kV transmission line to the west and then north to the existing Pennsuco substation. This line is proposed to be constructed in the same ROW as the previously described 500-kV lines, but will bypass the Levee substation and continue to the Pennsuco substation. From the Levee substation area to the Pennsuco substation, FPL has an existing multi-circuit transmission line ROW. The section of the proposed Clear Sky-Pennsuco 230-kV transmission line between Levee and Pennsuco will be placed within this existing ROW. This 230-kV-only portion of the West Consensus Corridor/MDLPA No. 2 and FPL West Preferred Corridor is approximately 8.4 miles long. Also as part of the western corridors, there are three access-only corridor laterals to be used only for vehicular access to the certified transmission lines. If the West Consensus Corridor/MDLPA No. 2 is certified and used for the placement of the western transmission lines, one of the access-only corridor laterals extends from the northwest corner of Government Lot 4 to Northwest 137th Avenue. It is 200 feet wide with 100 feet extending on each side of the north section line of government Lots 3 and 4. The second access-only corridor lateral for the West Consensus Corridor/MDLPA No. 2 extends south from the northwest corner of government Lot 4 to the north bank of the C- 4 Canal. It is 200 feet wide with 100 feet extending on each side of the west section line of Government Lot 4. From that point, it narrows to 100 feet in width and extends 169 to the west to include the bridge over the C-4 Canal at the entrance to the Trail Glades Sport Shooting Range. The third access-only corridor lateral extends from Krome Avenue to the L-31N ROW along the theoretical extension of Kendall Drive and is 200 feet in width. In addition, FPL will use the existing SFWMD access roadways on the L-31N levee and east of the L-31N canal within the SFWMD ROW, other public roadways, and newly constructed access roads within the corridor boundaries for access to transmission structures within the West Consensus Corridor/MDLPA No. 2 south of Tamiami Trail. If the FPL West Preferred Corridor is certified and used for placement of the western transmission lines, two access-only corridor laterals are also proposed. The Tamiami Trail Access Corridor is just north of Tamiami Trail where the FPL West Preferred Corridor crosses the road. This access corridor is a rectangle that adjoins the FPL West Preferred Corridor, is approximately 0.25 mile long and 370 feet wide, and includes the existing SFWMD levee access roadway and bridge associated with the L-29 canal. The Krome Avenue Access Corridor is proposed along the L-30 canal ROW and includes Krome Avenue from the point where the FPL West Preferred Corridor exits Water Conservation Area 3-B and turns east towards the Levee substation. This access corridor extends approximately five miles due north along SFWMD ROW, is approximately 600 feet wide, and includes the existing levee access roadway and bridge associated with the L-30 canal, as well as Krome Avenue. The total length of the western transmission lines is approximately 52 miles. 492. Construction of the proposed on-site Clear Sky substation is addressed above. The existing Levee substation is 170 a transmission substation with multiple existing 500- and 230-kV transmission lines connected to it. The substation property encompasses approximately 65 acres. The property currently includes the fenced area of substation equipment, stormwater retention areas, wetland mitigation areas, compacted access/ patrol roads, and undeveloped areas. The fenced area of the existing Levee substation must be expanded approximately 130 feet to the north along the entire length of the fence (approximately 800 feet) to accommodate installation of transformers, breakers, and switchgear, and the connection of the two proposed 500-kV transmission lines being extended from the proposed Clear Sky substation at the Turkey Point site. The proposed expansion of the fenced area of the substation is approximately 2.3 acres. The expansion area is within the geographic boundaries of the County's "unusual use" approval for the existing substation. Zoning approval from the County for the expansion of the Levee substation as an unusual use has already been obtained. 493. All transmission facilities, including the Clear Sky substation and Levee substation expansion, will comply with applicable design standards. 171 Corridor Selection: FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 FPL's Existing Transmission Line ROW, Turkey Point to Levee Substation 494. In the 1960s and early 1970s, FPL acquired a ROW between the Turkey Point plant property and the Levee substation for placement of transmission lines. The existing ROW is wide enough to accommodate the proposed new transmission lines; it already contains an existing transmission line along most of its length south of the Everglades National Park. 495. Approximately 7.4 miles of this ROW was encompassed by the addition of the Everglades National Park Expansion Area (Expansion Area) to the Everglades National Park in 1989. Subsequent to the expansion, the National Park Service (NPS) and several other land-owning agencies in the area negotiated with FPL to exchange FPL's currently owned transmission line ROW in the Expansion Area for a combination of easements and property that would provide a continuous transmission ROW between the Turkey Point plant property and the Levee substation, and provided for a slight adjustment of the eastern boundary of the Everglades National Park so the relocated ROW would be entirely outside the Everglades National Park. Collectively, these efforts are referred to as the "Land Exchange." The NPCA is actively opposing the Land Exchange. 172 If the Land Exchange is consummated, a total of approximately 12 miles of FPL's existing ROW is proposed for relocation. The Land Exchange has been authorized by federal legislation and is undergoing final environmental review by the NPS. In 2011, the NPS began developing an Environmental Impact Statement (EIS) to review the impact of the proposed Land Exchange, which is a required review for such a federal action. The current schedule estimates the Draft EIS should be available in late 2013 with the Final EIS due to occur in the fall of 2014, although those dates could change. Thirty days after issuance of the Final EIS, the Record of Decision should be available. Once finalized, the relocated ROW that will result from the Land Exchange will be within the FPL West Preferred Corridor and portions of it will be within the West Consensus Corridor/MDLPA No. 2. The existing transmission line ROW that FPL has owned since the 1960s and early 1970s in the area of the Land Exchange is identified in its application as the FPL West Secondary Corridor. However, the FPL West Secondary Corridor has been withdrawn from consideration by FPL. FPL desires to execute the Land Exchange and utilize a portion of those land rights for siting either the West Consensus Corridor/MDLPA No. 2 or the FPL West Preferred Corridor. 173 b. West Preferred Corridor Selection In the corridor selection process for the western transmission lines, the multidisciplinary team used the same process described in Findings of Fact 269 through 290 to evaluate potential corridors for the western transmission The west study area included the Clear Sky, Levee, and Pennsuco substations and existing FPL transmission ROWs and other linear features that occur between these substations. Much of the west study area is dominated by low- density residential development, agricultural and nursery operations, conservation lands, and mining activities. There are relatively few existing linear features that provide collocation opportunities. Each of the routes identified by the multidisciplinary team during the corridor selection process was evaluated in detail according to the quantitative and qualitative process described above. FPL's corridor selection process took into account planned development in the corridor areas, while avoiding environmentally sensitive areas to the extent practicable and reflected a balancing of engineering, environmental, and land use considerations against the need for the Project. After evaluation of all identified route alignments and consideration of public and agency input throughout the 174 community outreach program, FPL selected the West Preferred Route and delineated corridor boundaries for the route. The FPL West Preferred Corridor is of variable width, being wider in certain areas to give FPL flexibility in delineating the ROW within the corridor so as to accommodate localized conditions or take advantage of certain opportunities like following a property boundary, and narrower in other areas to avoid siting constraints, such as development or an environmentally sensitive area, or to utilize existing or relocated FPL ROWs, while maintaining a continuous route. c. Filing of Alternate Corridors During the certification process, four alternate western transmission line corridors were proposed for consideration in addition to the western corridors included by FPL in its application. MDLPA presented three alternate corridors and NPCA presented one, each to replace all or a portion of the West Preferred Corridor between approximately Southwest 120th Street and the Levee substation. MDLPA No. 2 is encompassed within the West Consensus Corridor/MDLPA No. 2 and is discussed in detail below, together with the FPL West Preferred Corridor. MDLPA No. 2 was developed after further discussions with the Everglades National Park and representatives of SFWMD and NPCA about the goal of reducing the potential impact on the Everglades National Park. The West 175 Consensus Corridor/MDLPA No. 2 achieves the combined goal of lessening potential impacts on the Pennsuco Wetlands and the Everglades National Park, while avoiding more urban uses to the east. It includes a segment of the FPL West Preferred Corridor, but also includes enough real estate east of the L-31N canal to potentially accommodate the full ROW where that proves to be a practical option for FPL and the rock mining companies. 507. The Pennsuco Wetlands, designated by the County as environmental protection lands, are a two-mile wide, approximately nine-mile long wetland between the Water Conservation Area 3B/Krome Avenue and rock mining lands known as the Lake Belt mining area. The Pennsuco Wetlands have long been a target of acquisition and restoration by various government agencies. Rock miners are still funding the ongoing acquisition and restoration of the wetlands as part of their wetland mitigation for mining wetlands within the Lake Belt mining area. About 80 percent of the Pennsuco Wetlands area has been acquired, and most of it has been restored. 508. MDLPA No. 1 was the first alternate corridor for the western transmission lines proposed by MDLPA and constitutes only a modest adjustment to the FPL West Preferred Corridor. MDLPA proposed its alternate corridor to avoid the FPL West Preferred Corridor's central crossing of the Pennsuco Wetlands. MDLPA No. 1 stays as close to the FPL West Preferred Corridor as 176 possible but crosses the Pennsuco Wetlands two miles farther south and eliminates much of the construction in Water Conservation Area 3B. MDLPA No. 3 was developed after discussion between the MDLPA and other interested parties, including NPCA. The goal was to develop a corridor with less impact west of the L-31N canal. However, the mining companies were not willing to propose a corridor with impacts on private property south of the parcel owned by CEMEX. Instead, MDLPA proposed a deviation from the FPL West Preferred Corridor which would move the corridor to the east to Krome Avenue on property owned by CEMEX and Kendall Krome Properties and Investments. NPCA filed one alternate corridor to be considered for portions of FPL's West Preferred Corridor, with a primary goal to eliminate potential impacts to conservation lands (primarily the Everglades National Park) and to wetlands. NPCA's corridor selection involved no analysis within the Everglades National Park itself. Potential impacts to future urban development in the Urban Expansion Area (UEA) of the County or encumbrances that might hinder use of NPCA's corridor were not considered in the selection process. NPCA's route selection team did not include a land use planner or a transmission line engineer. NPCA did not hold any publicly noticed open houses or workshops to solicit input from residents 177 and other stakeholders in the area before selecting its proposed corridor. Similarly, the number of government-owned parcels with encumbrances crossed by the proposed corridor was not considered. NPCA assumed parcels would likely be made available, despite a lack of confirmation through any final action or documentation. The County supports this corridor. d. Western Transmission Line Corridors Proper for Certification FPL and the Department filed notices of acceptance of the alternate corridors proposed by MDLPA and NPCA as proper for certification. The Department determined that all of the western alternate corridors met the criteria for certification. Consistent with its practice, the Department did not do a comparison of impacts among the different western alternate corridors. Each of the alternate corridors was evaluated by FPL's multidisciplinary team using the same quantitative and qualitative factors used to select the FPL West Preferred Corridor. Due to the withdrawal of the FPL West Secondary Corridor, only five western transmission line corridors are proper for certification as that term is used in sections 403.503(11) and 403.522(10). 178 514. FPL is seeking certification of the West Consensus Corridor/MDLPA No. 2 and the FPL West Preferred Corridor, with the FPL West Preferred Corridor to be utilized only if an appropriate ROW within the West Consensus Corridor/MDLPA No. 2 cannot be secured in a timely manner and at a reasonable cost. Both corridors are approximately 52 miles in length. 3. Corridor Descriptions 515. The western transmission line corridors can be divided into four separate geographic sections. Moving from south to north, these are referred to as the Turkey Point-U.S. Highway 1 Section, the U.S. Highway 1-Southwest 120th Section, the Southwest 120th-Levee Section (also known as the West Divergence Area), and the Levee-Pennsuco Section. The western transmission line corridors are co-existent in the Turkey Point- Highway 1, U.S. Highway 1-Southwest 120th, and Levee- Pennsuco Sections. They diverge only in the West Divergence Area. Sections Common to All Western Corridors 516. The Turkey Point-U.S. Highway 1 Section, common to all of the corridors, begins at the proposed Clear Sky substation on Turkey Point plant property and continues west for approximately ten miles, co-located with an existing transmission ROW, to approximately U.S. Highway 1. The next section common to all western corridors, U.S. Highway 1- 179 Southwest 120th Section, heads west and then north from U.S. Highway 1 to approximately Southwest 120th Street, just south of the Everglades National Park. The final section common to all western corridors is the section where the western corridors reconverge in the Pennsuco Wetlands north of Tamiami Trail and just west of the Levee substation, to the Pennsuco substation, the Levee-Pennsuco Section. Turkey Point-U.S. Highway 1 517. This Section of the western corridors coincides with FPL ROW containing existing transmission lines and access roads. Land uses are predominantly wetlands. Adjacent land uses already exist along this Section in a compatible manner with transmission line facilities. The proposed western transmission lines would be compatible with the land uses in this area. 518. The Turkey Point-U.S. Highway 1 Section consists of a variety of wetland habitats, including areas of mangrove wetlands in the vicinity of the L-31E canal, freshwater marshes dominated by sawgrass, occasional tree islands, as well as some areas dominated by nuisance and exotic species. Construction of the western transmission lines within this Section would result in no more than 59 acres of wetland impact, and likely less than that, based on the measures FPL has agreed to take to eliminate and reduce wetland impacts. The majority of wetlands within the 180 transmission line ROW would remain undisturbed, and the loss of wetland functions would be fully mitigated. Plants and wildlife found in the Turkey Point-U.S. Highway 1 Section common to all western corridors are those adapted to wetland cover types such as wading birds, raptors, amphibians, and reptiles, as well as small mammals and occasional deer. Very few upland habitats exist, and the Section comprises an existing FPL transmission line easement, including an access road, structures, and structure pads. U.S. Highway 1-Southwest 120th Street This Section of the western corridors coincides with FPL ROW containing existing transmission lines and access roads. Adjacent land uses have therefore adapted to the presence of transmission lines and have remained stable over time. Land uses are predominantly agricultural with some residential, and the northern end of this Section transitions to open lands. The western transmission lines would be compatible with the land uses in this area. The Section is primarily upland in nature and dominated by agricultural land uses, primarily tree nurseries. Other agricultural uses in this area include row crops and citrus. This Section traverses portions of two areas designated by the County as NFCs, the Sunny Palms Pineland and Kings Highway Pineland. These NFCs could also be home to various 181 species of state-listed plants. Wildlife found in this Section includes common reptiles, amphibians, birds, and mammals that are habituated to human-induced habitats. Wetland resources within this area of the corridors are limited to small areas of freshwater marsh, ditches, and canals. Construction of the transmission lines within this area will incur minimal wetland impacts, estimated to be less than one acre of relatively low- quality wetlands. iii. Levee-Pennsuco North of the West Divergence Area, in the Levee- Pennsuco Section, all of the western corridors travel along an existing multi-circuit transmission line ROW through unincorporated Miami-Dade County, Doral, and Medley, passing alongside agricultural, industrial, and multi-family residential uses. The Section comprises active rock mining facilities and contains very little undisturbed wildlife habitat. Rock quarries may contain some habitat for aquatic species, but very little native upland habitat exists. Wildlife usage is limited to common amphibians, reptiles, birds, and mammals found in the County. From the Florida Turnpike to the Pennsuco substation, the corridors are dominated by FPL's existing transmission lines with scattered uplands and herbaceous wetlands on the existing transmission line ROW. Adjacent land uses include residential, 182 commercial, and industrial uses in Doral. No unique wildlife usage is expected in any of this Section due to the fact the existing right-of-way has been in place and maintained for many years. Wildlife species have become accustomed to those habitats. 524. Construction of the transmission line between the Levee and Pennsuco substations will use the existing transmission line roads and structure pads to the greatest extent practicable, limiting estimated wetland impacts to approximately one acre. 525. Land uses for the western alternate corridors are identical to the land uses in the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 in the Turkey Point- U.S. Highway 1, U.S. Highway 1-Southwest 120th, and the Levee- Pennsuco Sections, as these Sections are common to all the corridors. West Divergence Area: FPL West Preferred and West Consensus Corridor/MDLPA No. 2 526. The West Divergence Area extends from the southernmost point where the first alternate corridor diverges from the FPL West Preferred Corridor to the Levee substation. This Section generally encompasses an area that will be entirely east of the Everglades National Park following the Land Exchange and includes the L-31N and L-30 levees/canals and eastward to 183 encompass the Krome Avenue area and Bird Drive Basin. It then runs northward to a point just west of the Levee substation where all the western corridors reconverge. 527. In the West Divergence Area, the FPL West Preferred Corridor turns due east at Southwest 120th Street towards the L-31N levee. Moving north from approximately Southwest 120th Street to Tamiami Trail, the FPL West Preferred Corridor straddles the L-31N canal and runs adjacent to the Krome Detention Center. After crossing Tamiami Trail, the FPL West Preferred Corridor then proceeds along the L-30 levee, passing the Miccosukee Casino property, and eventually parallels Krome Avenue to the north to a point just west of the Levee substation. The FPL West Preferred Corridor then proceeds due east across the Pennsuco Wetlands into the Levee substation. 528. Within the West Divergence Area, the ecological conditions differ among the various corridors. In this portion of the Corridor, freshwater marshes (sawgrass) dominate. These freshwater marshes provide suitable foraging habitat for a variety of wading birds, and support a variety of fish, amphibians, reptiles, and small mammals. Some tree islands also occur within the Southwest 120th-Levee Section of the Corridor and may provide suitable nesting habitats for wading birds, some of which are listed. No wading bird colonies exist within the Corridor, but there are two colonies within 0.5 mile of its 184 boundaries. These colonies have historically contained wood storks and listed wading birds during some nesting seasons. Additionally, the FPL West Preferred Corridor includes some historical nesting sites and marginally suitable foraging habitat for the endangered Everglade snail kite, particularly in the area north of Tamiami Trail. In any of the western corridors proper for certification, throughout the West Divergence Area, the potential for adverse impacts to any wildlife species is low. 529. In the West Divergence Area, the wetland quality in the Corridor tends to average between 0.70 and 0.80 using UMAM. Placing the ROW in the FPL West Preferred Corridor would impact no more than 137 wetland acres, given FPL's flexibility to site the ROW within the Corridor and position the transmission line structures to avoid or minimize wetland impacts to the extent practicable. 530. In the northern portion of the West Divergence Area, the wildlife habitats within the Corridor consist primarily of sawgrass marsh with scattered tree islands on the west side of the L-31N levee and Bird Drive Basin to the east, with scattered herbaceous marsh and tree islands. The Corridor itself is primarily co-located along disturbed areas including an existing levee and canal heading to the Levee substation. 185 531. Through much of the West Divergence Area, both the FPL West Preferred Corridor and the West Consensus Corridor/ MDLPA No. 2 straddle the L-31N levee, which represents a seam between the Everglades National Park to the west, and residential and agricultural uses to the east. Some of the lands are in transition and include agricultural lands, a few large single family estates (one unit per five acres), and open lands, with more urban development to the east. Farther north along L-31N levee, the land uses to the east of the FPL West Preferred Corridor and the West Consensus Corridor/MDLPA No. 2 are previously-disturbed uses, rail, and predominantly rock mining. Farther north, but south of Tamiami Trail, the FPL West Preferred Corridor continues to run along a seam between conservation uses to the west and more developed uses, including the Krome Detention Center, to the east. North of Tamiami Trail, the FPL West Preferred Corridor straddles the L-30 levee and runs between the conservation lands in Water Conservation Area 3B and the Miccosukee Casino property and then Krome Avenue further north. The Corridor then turns east on existing ROW through the environmental protection lands of the Pennsuco Wetlands, and then through rock mining land uses to the Levee substation. 532. Existing tall structures in the vicinity of the FPL West Preferred Corridor include the Miccosukee Casino and the 186 Krome Detention Center water tower, as well as power poles and radio towers. iii. West Consensus Corridor/MDLPA No. 2 533. In the West Divergence Area, the West Consensus Corridor/MDLPA No. 2 begins approximately one mile south of a hypothetical extension of Kendall Drive and extends to the Levee substation. Where it overlaps the FPL West Preferred Corridor along the L-31N levee, the Corridor widens eastward of the L-31N levee to encompass rock mining lands. It then diverges from the FPL West Preferred Corridor for approximately 13 miles, turning east at a point north of a hypothetical extension of 18th Street running just south of the Krome Detention Center. It then turns north at a point east of Krome Avenue, crossing Tamiami Trail and continuing north along the Dade-Broward Levee until it reaches the FPL West Preferred Corridor alignment; the West Consensus Corridor/MDLPA No. 2 then continues east until it reaches the Levee substation. 534. For most of the distance along the L-31N levee, the West Consensus Corridor/MDLPA No. 2 includes, but is wider than, the FPL West Preferred Corridor. This configuration provides enough room on both sides of the canal for placement of the proposed western transmission lines, with some flexibility to potentially locate all or part of the transmission lines on the rock-mining lands and other private and public property to the 187 east. The Corridor includes sufficient real property east of the L-31N Canal to accommodate the full transmission line ROW in some areas, if that proves to be a practical option for FPL and the rock mining companies. 535. Where the West Consensus Corridor/MDLPA No. 2 overlaps the FPL West Preferred Corridor in the West Divergence Area, such as along the L-31N Canal, the ecological conditions are the same, with conservation uses (the Everglades National Park) to the west and predominantly mining and rail uses to the east. However, the widened area of the West Consensus Corridor/MDLPA No. 2 immediately to the east of the FPL West Preferred Corridor includes primarily previously-disturbed rail and mining operations, as well as shrub and brushland, and remnant upland and wetland habitats. 536. The West Consensus Corridor/MDLPA No. 2 diverges from the FPL West Preferred Corridor by turning eastward along a hypothetical extension of Southwest 18th Street, at the northern boundary of the rock mining overlay west of Krome Avenue. In this area, the West Consensus Corridor/MDLPA No. 2 passes south of the Krome Detention Center, then runs eastward through the Bird Drive Basin overlay, consisting of open lands, wetlands, and conservation lands. The adjacent land uses in that area are open lands, wetlands, and conservation lands. In the Bird Drive Basin the land use is mixed ownership of governmental and 188 private parcels. The width of the corridor in this location provides flexibility to minimize crossings of private property in the Bird Drive Basin. 537. Where the West Consensus Corridor/MDLPA No. 2 crosses wetlands within the Bird Drive Basin and, north of Tamiami Trail, the eastern edge of the Pennsuco Wetlands, the wildlife habitats generally consist of herbaceous marsh (sawgrass), wet prairie, shrub/brushland, and tree islands (primarily melaleuca). This area is used by wetland-dependent wildlife, such as wading birds, reptiles, amphibians, small mammal, and deer. The West Consensus Corridor/MDLPA No. 2 is, however, located farther than the FPL West Preferred Corridor from known locations of wood stork colonies located along and north of Tamiami Trail. At the point where it turns north and for the remainder of its length until it reaches the Levee substation, the West Consensus Corridor/MDLPA No. 2 is very wide. This allows maximum flexibility in aligning the corridor so as to avoid obstacles and minimize impacts. 538. The Bird Drive Basin is a County regulatory zoning overlay that consists primarily of wetlands, although in many cases they are low-quality herbaceous wetlands with scattered tree islands (primarily melaleuca). It is located east of the rock mining zoning overlay and Krome Avenue from approximately Southwest 88th Street to Southwest 8th Street (Tamiami Trail). 189 Wetlands in the Bird Drive Basin and the east side of the Pennsuco Wetlands are generally lower in quality compared to wetlands located further to the west, due to increased proliferation of nuisance and exotic species of vegetation. Wetland quality within the West Consensus Corridor/MDLPA No. 2 tends to average between 0.70 and 0.80, and siting the ROW within the West Consensus Corridor/MDLPA No. 2 would impact no more than 122 wetland acres. The Urban Development Boundary (UDB) is an area designated by the County in the CDMP for existing urban uses, while the UEA, adjacent to the UDB, is designated by the County for anticipated future urban development after 2015, if there is a need based on population growth. Corridors farthest from these areas are more desirable from the standpoint of potential conflict with residential and urban land uses, although all would be compatible from a land use perspective. Both the West Consensus Corridor/MDLPA No. 2 and the FPL West Preferred Corridor are entirely west of the area designated by the County as the UEA and even farther west of the area designated as the UDB. There is no urban development near the West Consensus Corridor/MDLPA No. 2 or the FPL West Preferred Corridor. The western transmission lines in any of these corridors would be compatible and consistent with the adjacent 190 land uses, including the Everglades National Park, and would serve the broad interests of the public. c. West Divergence Area: Other Western Alternate Corridors Vegetation/wildlife habitats within the West Divergence Area of MDLPA No. 1, MDLPA No. 3, and the NPCA Corridor have a mixture of agricultural areas, uplands, and wetlands. Land is more disturbed and wetlands more degraded the farther east one heads, as compared to the areas closer to the Everglades National Park. Wildlife usage is more limited to the east than to the west as a result of the land disturbances. Wetland quality in MDLPA No. 1 tends to average between 0.70 and 0.80 using UMAM; MDLPA No. 3 wetlands were of somewhat lower quality in spots, averaging between 0.60 and 0.80. The NPCA Corridor, located farthest east, had the lowest quality wetlands, averaging between 0.60 and 0.70. In the West Divergence Area, the acres of wetlands potentially impacted by each alternate corridor, and therefore the amount of mitigation required to offset the impacts, also tends to decrease to the east and increase to the west. MDLPA No. 1 would impact no more than 199 acres of wetlands. In contrast, MDLPA No. 3 and the NPCA Corridor, located the farthest east, would impact 165 and 152 acres of wetlands, respectively. 191 546. Wildlife species usage in the West Divergence Area of the alternate corridors consists of common amphibians, reptiles, birds, and mammals of the region. Some listed wading birds would be expected to forage in certain portions of the alternate corridors. 547. Within the West Divergence Area, the alternate corridors cross agricultural lands, open lands, rock mining, residential parcels, and wetlands. MDLPA No. 1 548. In the north portion of the West Divergence Area, MDLPA No. 1 deviates from the FPL West Preferred Corridor for approximately four miles between Tamiami Trail and the Levee substation, turning east north of Tamiami Trail. It crosses the Pennsuco Wetlands approximately two miles farther south than the FPL West Preferred Corridor and is coexistent with the FPL West Preferred Corridor for its remainder, generally following the L- 31N levee and canal. Except in the area north of Tamiami Trail to the Levee substation, MDLPA No. 1 is identical to the FPL West Preferred Corridor. 549. The ecological conditions in the south and center portions of the West Divergence Area of MDLPA No. 1 are the same as the West Consensus Corridor/MDLPA No. 2. Like the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2, it 192 travels along the same seam between land uses along the L-31N levee and canal and adjacent to/within active rock mining areas. 550. Within MDLPA No. 1, uplands in the north portion of the West Divergence Area consist primarily of roads and levees. The wetlands are primarily sawgrass marsh with melaleuca- dominated tree islands. Wildlife species usage consists of common amphibians, reptiles, birds, and mammals of the region. No known listed species occurrences were identified, but it is expected that wading birds would use the area for foraging. The northern part of MDLPA No. 1 in the West Divergence Area is within 1,500 feet of one wading bird colony containing wood storks along Tamiami Trail. MDLPA No. 3 551. MDLPA No. 3 follows a more easterly pattern in the West Divergence Area than the West Consensus Corridor/MDLPA No. or the FPL West Preferred Corridor. It deviates from the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 for approximately 13 miles between Southwest 120th Street and the Levee substation. It turns east approximately one-half mile south of the theoretical extension of Kendall Drive, then north along Krome Avenue, then through the Bird Drive Basin and eastern Pennsuco Wetlands to the Levee substation. 552. In the south portion of the West Divergence Area, MDLPA No. 3 follows the West Consensus/MDLPA No. 2 and FPL West 193 Preferred Corridors until it turns east along Southwest 100th Street, through residential, agricultural, and open/mining land uses. 553. In the south portion of the West Divergence Area, MDLPA No. 3 includes agricultural and rock mining areas as well as sawgrass marsh, native wetland hardwoods, and exotic wetland hardwoods. Wildlife habitat in this area is very limited. 554. The wildlife habitats within the central portion of MDLPA No. 3 in the West Divergence Area consist of agricultural areas adjacent to Krome Avenue and lower quality wetlands east of Krome Avenue. These areas include wetlands consisting primarily of freshwater marsh, wet prairie, and tree islands (many of which contain melaleuca). 555. The north portion of MDLPA No. 3 in the West Divergence Area crosses wetland habitat within the Bird Drive Basin and Pennsuco Wetlands. Some listed wading birds would be expected to forage in this area although no breeding colonies are known in this area. In the Bird Drive Basin, there is a mixture of some low-quality exotic wetland hardwoods, sawgrass marsh, and wet prairie wetlands; the corridors cross Tamiami Trail, and then enter the Pennsuco Wetlands in an area where there is a mixture of exotic wetland hardwoods, sawgrass marsh, and wet prairie. All of the corridors converge just to the west of the Levee substation. 194 556. The center and north portions of MDLPA No. 3 and NPCA Corridor in the West Divergence Area are generally overlapping. From the intersection of Southwest 100th Street and Southwest 177th Avenue/Krome Avenue, MDLPA No. 3 and NPCA Corridor move north following Krome Avenue/Southwest 177th Avenue and angle northeastward near Southwest 72nd Street to run through environmental preservation/wetlands, open lands, and rock mining lands, and near to residential lands. They are both located within the Bird Drive Basin in this area. From the Bird Drive Basin area, the corridors travel northward generally along the Dade-Broward Levee alignment to the Levee substation. A portion of MDLPA No. 3 is located within the County-designated North Trail Basin. The two corridors are both wide at this location, angling to the east through Bird Drive Basin wetlands to the Dade-Broward Levee alignment. In this area, they also generally overlap the West Consensus Corridor/MDLPA No. 2, which is the widest choice of corridors in this area. 557. The two corridors both cross the UEA and are the closest corridors to the UDB. They also cross the property owned by Limonar, which has yet-to-be finalized plans for future residential and mixed-use development of its 485-acre tract. NPCA Corridor 558. The NPCA Corridor deviates from the FPL West Preferred Corridor near Southwest 120th Street to the Levee 195 substation for approximately 15 miles. It turns eastward in the Southwest 120th Street area to Krome Avenue, where it turns northward along Krome Avenue, generally following MDLPA No. 3 to a point just west of the Levee substation, where the alternate corridors all converge. 559. The south boundary of the West Divergence Area is defined by the southern boundary of the NPCA Corridor. It turns eastward and encompasses an area on the south side of Southwest 120th Street, including land outside the Everglades National Park and south of the FPL West Preferred Corridor. Between Southwest 194th Avenue and Southwest 197th Avenue, the NPCA Corridor jogs northward to be within the FPL West Preferred Corridor. It then turns north to run for a short distance along the L-31N levee, and then eastward again along Southwest 112th Street, where it turns northward again at Southwest 177th Avenue/Krome Avenue. Like MDLPA No. 1 and MDLPA No. 3, the NPCA Corridor runs through predominantly agricultural areas/rock mining areas along Krome Avenue as well as the Bird Drive Basin overlay and the North Trail Basin overlay. 560. As noted above, in the central portion, the NPCA Corridor overlaps MDLPA No. 3 and thus has the same adjacent land uses. It also crosses the UEA as well as the property owned by Limonar, which has plans, although not yet final, for future residential and mixed-use development of this property. 196 561. The NPCA Corridor has similar ecology as MDLPA No. 3 in the southernmost part of the West Divergence Area but traverses more agricultural areas. 562. The center portion of the NPCA Corridor in the West Divergence Area, like MDLPA No. 3, consists of agricultural areas and wetlands, providing suitable habitat for a variety of common wading birds, mammals, fish, reptiles, and amphibians. 563. From an ecological perspective, the northern part of the NPCA Corridor within the West Divergence Area is also the same as MDLPA No. 3. Both traverse wetland habitat within the Bird Drive Basin, the North Trail Basin, and the Pennsuco Wetlands. Some listed wading birds would be expected to forage in this area although no breeding colonies are known for this area. In the Bird Drive Basin, there is a mixture of some low- quality exotic wetland hardwoods, sawgrass marsh, and wet prairie wetlands. The corridors cross Tamiami Trail, and then enter the Pennsuco Wetlands in an area where there is a mixture of exotic wetland hardwoods, sawgrass marsh, and wet prairie. All of the corridors converge just to the west of the Levee substation. 564. Wetlands to the east of the L-31N levee within the Bird Drive Basin and the Pennsuco Wetlands, in which MDLPA No. 3 and the NPCA Corridor traverse, are somewhat lower in quality 197 compared to wetlands located west of the L-31N canal, in which MDLPA No. 1 traverses. 565. In the north portion of the West Divergence Area, the West Consensus/MDLPA No. 2, MDLPA No. 1, and MDLPA No. 3 narrow as they approach the Levee substation, limiting the crossing of the Pennsuco Wetlands and adjacent land uses, while the NPCA Corridor remains wide from north of the North Trail Basin to the Levee substation. 4. Western Transmission Line Construction and Design Standards 566. The location, construction, operation, and maintenance of the western transmission lines will comply with all applicable design standards. They will be located, constructed, operated, and maintained in a manner consistent with all applicable non-procedural regulatory standards; these standards are reflected in the Conditions of Certification, and FPL has committed to implementing those conditions. The entire construction process for the western transmission lines will take between four to five years. 567. Existing transmission lines and access roads in the certified corridor will first be assessed to determine whether they are suitable for construction and ongoing operation and maintenance activities for the proposed western transmission lines. If determined to be suitable, these features will be 198 used, which will minimize the need for new road construction in the area that could potentially impact wetlands or surface hydrology. 568. In the past, FPL has used the SFWMD's existing levees for access onto other projects and may seek to use these levees as access roads for this Project, which could further minimize the need for new access roads. 569. Where new access roads and structure pads are necessary, they will be constructed with clean fill material and unpaved. Access road and pad elevations will be established after a review of available drainage basin data, seasonal water elevations, and flow patterns. The final grade elevation of any necessary access roads and structure pads will be sufficient to ensure emergency access to provide at least 12 inches of clearance over seasonal or mean high-water levels or over controlled water levels in areas where water levels are regulated. The roads and pads will have two-to-one side slopes, which allows for a stable side slope. An 18-foot top width of the road is proposed to allow for large vehicular use during construction and maintenance. A variation on this width will occur in the southern portion of the corridor that is common to all of the western corridors proper for certification where the main plant construction temporary access road will be built over the location of the future permanent transmission line access 199 road. This wider plant access will also be used temporarily for transmission access. Once the plant construction is complete, the temporary additional width will be removed. 570. Where practicable, access roads and structure pads will be constructed outside of wetlands. Culverts will be installed under the access roads and structure pads as needed to maintain pre-construction flows. Culverts will be covered with at least two feet of clean fill to prevent them from being crushed by vehicles. 571. FPL will use sedimentation control devices to control erosion and turbidity, and will utilize stable, compacted fill material, along with seeding and mulching of side slopes, to minimize the potential for impacts to wetlands. 572. Transmission line construction includes material hauling, spotting, and structure erection. If multiple-piece structures are used for the western transmission lines (tubular steel poles installed on concrete caisson foundations), the augured holes will be approximately nine feet in diameter to accommodate the installation of concrete caisson foundations. 573. For the western 500-kV transmission lines, the typical span length will be approximately 1,000 feet between structures. For the west 230-kV transmission line, the typical span length from Clear Sky to the Levee substation area will be approximately 500 feet, and from the Levee substation area to 200 the Pennsuco substation, the typical span length will range from approximately 250 to 750 feet, following the alignment of the existing 230-kV transmission lines in that ROW. 574. Span lengths vary for several reasons. Sometimes a pole location is adjusted to avoid a tree canopy, wetland, or archaeological or historical site, or to coincide with property lines or the location of existing distribution poles that will be replaced. They can also be adjusted to accommodate the crossing of highways, water bodies, or other linear features. 575. The typical ROW width identified in the application to accommodate the three western transmission lines between the Clear Sky and Levee substations is approximately 330 feet, which for a majority of the length of the corridor comprises FPL's existing transmission line ROW. Between the Levee and Pennsuco substations the ROW will be approximately 170 feet, and the 230- kV transmission line will be mostly constructed within existing FPL transmission line ROWs, with the exception of the upland easement requested in a mining area. 576. FPL establishes a transmission line ROW through multiple means, such as the purchase of easement rights over affected parcels, property in fee simple, and for public ROW, the acquisition of longitudinal use permits and licenses for crossing permits. 201 577. Where FPL is not constrained to a 330-foot ROW, it may use its traditional 500-kV H-frame unguyed structures using a horizontal configuration. Use of such structures would allow greater span lengths between structures, potentially minimizing wetland impacts. 578. All of the western alternate corridors, including the West Consensus Corridor/MDLPA No. 2, cross property owned by state and federal agencies in the West Divergence Area east of the FPL West Preferred Corridor. FPL may not have the eminent domain authority to condemn all of the necessary rights in those government parcels. 579. No party presented evidence suggesting that undergrounding for any portion of the western transmission lines was appropriate for the proposed western transmission lines or that undergrounding was feasible for the western 500-kV transmission lines. 580. Construction of the Levee substation expansion will require clearing and grubbing the expansion area. Turbidity screens and other erosion control devices and techniques will be used to minimize construction impacts to nearby wetlands and water bodies. The expanded substation yard area will be excavated, filled with clean fill, graded, and rolled to match the existing substation yard elevation. The existing grounding 202 grid will be expanded and a new security fence around the expansion area will be installed. 581. After the substation expansion area is prepared, concrete caisson foundations will be installed for the new equipment using drilling rigs and large cranes. Once the foundations are complete, the new bus system, circuit breakers, switches, and other associated equipment will be installed. Applicable Non-Procedural Requirements Wetlands 582. The corridor selection process appropriately eliminated and reduced impacts to wetlands and waters of the state to the extent practicable, as required by applicable rules. First, FPL has eliminated consideration of the FPL West Secondary Corridor for this Project completely, despite having owned the ROW within this corridor for over 40 years. Second, assuming the West Consensus Corridor/MDLPA No. 2 can be feasibly and timely obtained, FPL's preference for the West Consensus Corridor/MDLPA No. 2 over the FPL West Preferred Corridor constitutes a substantial additional wetland impact elimination measure by moving a significant length of the lines in the West Divergence Area to the east side of the L-30 and L-31N levees and avoiding a central crossing of the Pennsuco Wetlands. Third, the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 are co-located with existing disturbed 203 ROWs, with existing linear facilities and using existing access roads and infrastructure where available. The need for new access roads will be minimized in the West Consensus Corridor/MDLPA No. 2, due to the ability to use existing access. 583. Additional minimization of impacts will be incorporated throughout the entire certified corridor during final transmission line design. Locating the transmission lines within corridors allows flexibility in routing and additional wetland avoidance/minimization opportunities such as adjusting the location of structure pads and access roads, and/or adjusting the span lengths between structures. 584. No significant adverse effect on the abundance and diversity of wildlife is anticipated as a result of construction in any of the corridors proper for certification. Pre-clearing listed species surveys will be conducted. Most herbaceous and low-growing wetland vegetation will not need to be cleared. Construction practices in wetlands will retain the vegetative root mat in areas not filled, thereby minimizing impacts to wetland vegetation. 585. Impacts will be rectified or mitigated to the extent practicable by restoring wetlands within the ROW that are not directly impacted by structure or pad installation. Also, FPL has committed to controlling exotic vegetation within the entire ROW (both wetlands and uplands). Any remaining unavoidable 204 impacts will be fully compensated through the Hole-in-the-Donut Mitigation Bank and the Everglades Mitigation Bank. These measures satisfy the state Environmental Resource Permit criteria and the County code criteria relative to wetland impacts. Wetlands to the east of the L-31N levee within the Bird Drive Basin (where the West Consensus Corridor/MDLPA No. 2, MDLPA No. 3, and NPCA Corridor are located) are lower in quality compared to wetlands located west of the L-31N levee (where the FPL West Preferred Corridor and MDLPA No. 1 are located). They also experience more shallow inundation compared to wetlands to the west of L-31N levee, reducing the amount of wetland fill required to elevate proposed roads and transmission structure pads and the amount of mitigation required for the wetland impacts. Construction, operation, location, and maintenance of the western transmission lines in any of the western corridors will not adversely impact the functions of wetlands or other surface waters from a wildlife perspective. Restrictive clearing techniques will be employed in forested wetlands and sensitive pine rockland communities. NPCA offered testimony regarding federal law and international treaties to underscore the importance of the Everglades National Park wetlands, including designation of part 205 of present-day Everglades National Park as a Wilderness Area (excluding the East Everglades addition) in 1978, designation of Everglades National Park as a world heritage site by the United Nations Educational, Scientific, and Cultural Organization in 1979, and inclusion of Everglades National Park among the Ramsar List of Wetlands of International Importance in 1987. However, all of these designations predated Congressional authorization of the Land Exchange. 591. In addition, the Everglades National Park Protection and Expansion Act of 1989 and the Water Resources Development Act of 2000, cited by NPCA witnesses, predated the negotiations and agreements, subsequently authorized by Congress, for the Land Exchange. Avian Species 592. The western corridors were analyzed for their potential to impact avian species, including wading birds and the endangered wood stork and Everglade snail kite, since they are known to occur in the area. 593. There are no known current nesting sites for listed avian species within any of the western corridors, but there are wading bird colonies in the vicinity of the FPL West Preferred Corridor in the area of Tamiami Trail. 594. The USFWS has recommended primary and secondary protection zones with specific management restrictions in order 206 to minimize wood stork colony disturbance. Such recommended management restrictions for wood storks and their colonies would not prohibit placement of the proposed transmission lines in the FPL West Preferred Corridor or West Consensus Corridor/MDLPA No. 2. 595. The wood stork is known to nest in four colonies both south and north of Tamiami Trail and west of the FPL West Preferred Corridor. These colonies have been well documented for years and are known as the Tamiami East 1 and 2, Tamiami West, and 3B Mud East colonies. The NPCA Corridor and MDLPA No. are the farthest from these colonies. The FPL West Preferred Corridor and MDLPA No. 1 fall within 1,500 feet of one of these colonies. The West Consensus Corridor/MDLPA No. 2 is located east of all of these colonies, and the closest colony (Tamiami East 1) is approximately one mile away from the closest corridor boundary. The West Consensus Corridor/MDLPA No. 2 falls outside the recommended primary (500 to 1,500 feet) and secondary (2,500 feet) management zones for the wading bird colonies published by the USFWS. No known listed species have been recorded in the West Consensus Corridor/MDLPA No. 2, MDLPA No. 3, or NPCA Corridor, but it could be expected that listed species would utilize portions of those corridors. 596. The primary and secondary management zones for these colonies are flexible and much smaller management zones may be 207 applied, as was done for the Tamiami Trail Modifications: Next Steps Project near the West Preferred Corridor. Three wood stork nesting colonies are located along Tamiami Trail to the west of the western corridors. One colony (3B-Mud East) is located farther north, to the west of L-30 levee. The FPL West Preferred Corridor crosses only portions of the secondary management zones for the Tamiami East 1 and 3B-Mud East colonies. None of the other western corridors cross either a primary or secondary management zone of a wood stork colony. 597. None of the Everglade snail kite's critical habitat areas, as designated by the USFWS, are crossed by any of the western corridors. The closest critical habitat area is over ten miles to the west, and not "in close proximity," as suggested by NPCA. 598. Although some parties contend otherwise, the record establishes there will be no adverse impacts on avian species, including listed species such as the wood stork and Everglade snail kite. In all of the corridors proper for certification FPL will implement design features to protect avian species. These include: (1) wide spacing of the energized conductors to avoid birds touching two conductors simultaneously, which is the manner in which many avian electrocutions on power lines occur; perch discouragers on every pole; and (3) bird flight 208 diverters on all of the spans on the overhead or ground wires within one-half mile of any wood stork colonies. 599. FPL has agreed to comply with very specific wood stork and Everglade snail kite conditions of certification proposed by FWC. These are sufficient to protect the species. 600. The location, construction, operation, and maintenance of the proposed transmission lines in the western transmission line corridors will not adversely impact the ecological value of uplands to aquatic or wetland-dependent listed avian species for enabling existing nesting by these species because the upland areas to be affected are of low value to wetland-dependent species. 601. FPL's APP outlines specific design and construction standards for distribution and transmission lines, substations, and other avian mortality reduction methods. These standards are designed to avoid and minimize potential bird impact issues such as electrocutions and collisions, as well as avian enhancement activities that can provide benefits to birds from FPL structures and activities. These steps should resolve the concerns expressed by NPCA at hearing. 602. The APP also provides FPL managers and field personnel with a single, accessible information resource describing avian protection background issues, relevant bird species, potential impact issues, applicable federal, state, and 209 local regulatory context, key resources and contacts for bird issue responses, and FPL responsibilities. 603. The APP also outlines specific training, response, reporting, and quality control protocols to ensure that FPL personnel are adequately prepared for responding to potential bird impact issues, focusing on bird mortality, injury, or nesting incidents, and on key potentially affected listed bird species, as well as personnel safety procedures to be implemented during responses to bird impact situations. 604. In light of these measures to be implemented, FPL has provided reasonable assurances that avian species in the region are unlikely to suffer electrocution from or collision with the transmission lines. 605. The location, construction, operation, and maintenance of the proposed transmission lines in any of the western corridors will not adversely impact wood storks. There will be no loss of nesting habitat as a result of the proposed transmission lines, any loss of wood stork foraging habitat will be fully mitigated, and there will be minimal to negligible exposure of wood storks to risk of electrocution as a result of the western transmission line corridors. There will be only a small risk of a wood stork collision with the transmission lines because their large wings enable them to fly slowly with higher maneuverability. Any risk will be further minimized by use of 210 flight diverters. While it is assumed juvenile wood storks are poorer flyers than adults and may be more susceptible to collisions, there has never been a documented case of a juvenile wood stork colliding with a transmission line. The period of exposure of young wood storks to hazards around the colony is very short, as they leave the colony within about 48 hours after fledging. 606. The location, construction, operation, and maintenance of the proposed transmission lines in the western transmission line corridors will not adversely impact Everglade snail kites. While the Everglade snail kite is known to occasionally forage within parts of some of the western transmission line corridors, the area currently lacks apple snails, which are the Everglade snail kite's primary food source. If apple snails were to return, however, Everglade snail kites could also return. Everglade snail kite foraging and nesting behavior is compatible with transmission facilities and habitats under transmission lines, so no impacts to Everglade snail kites are expected. By virtue of their flight morphology and behavior, Everglade snail kites are not likely to be exposed to any risk of electrocution or collision mortality from the transmission lines. 607. With respect to all other listed avian species, habitat loss will be minimal to negligible because they will be 211 restricted to a minor loss of foraging habitat for some wetland- dependent species with no significant adverse effect on the population, and this habitat loss will be fully mitigated. There is no risk of electrocution from the proposed transmission lines, as the separation of energized parts exceeds the maximum wingspan or bill tip to foot length of all listed bird species potentially occurring within the area. While some listed species will be exposed to risk of collision with the lines, this risk will be relatively small and is not likely to affect any populations. 608. In light of the APP and other protection measures described above, the location, construction, operation, and maintenance of the proposed transmission lines in any of the western transmission corridors proper for certification will be consistent and in compliance with FWC regulations related to the protection of threatened and endangered avian species, as well as the Migratory Bird Treaty Act of 1918, as amended. More strict measures than those imposed by the FWC, or described in the APP, are not necessary. 609. The location, construction, operation, and maintenance of the proposed transmission lines in the western transmission line corridors will not impact the values of wetland or other surface water functions so as to cause adverse impacts to the abundance and diversity of any listed avian 212 species because all wetland impacts will be mitigated consistent with applicable regulations and the approved mitigation plan. No adverse impact to the conservation of birds or their habitats, including endangered and threatened species, is expected. Impacts on birds, including listed species and their habitats, have been avoided and minimized through the siting of the corridors and design of the transmission lines. The risks to avian species are small and all impacts will be fully mitigated. The location, construction, operation, and maintenance of the proposed transmission lines in the western transmission line corridors will not cause adverse secondary impacts to avian species. The location, construction, operation, and maintenance of the proposed transmission lines in the western transmission line corridors will not adversely impact the population of any threatened or endangered avian species. The location, construction, operation, and maintenance of the proposed transmission lines in any of the western corridors proper for certification will not prevent the preservation of avian species. Through the use of reasonable and available methods, the location, construction, operation, and maintenance of the proposed transmission lines in any of the western corridors 213 proper for certification will minimize any adverse effects on avian species and their habitats. FPL has committed to taking a variety of steps to minimize any potential adverse impacts on avian species and their habitats including the siting of corridors, avian-protection design features and construction standards, and mitigation. 615. From an avian perspective, FPL's mitigation will fully compensate for any functions that may be lost on environmentally sensitive lands as a result of the location, construction, operation, and maintenance of the proposed transmission lines. 616. The location, construction, operation, and maintenance of the transmission lines will comply with all applicable non-procedural requirements related to protection of avian species, including listed avian species and their habitat. Non-Avian Wildlife Species 617. Impacts of location, construction, operation, and maintenance of the transmission lines on non-avian wildlife were also evaluated and specifically included evaluations of potential impacts to the Florida panther, Eastern indigo snake, and the American crocodile, since they are listed species known to occur in the area. 618. In all of the corridors within the west study area, the potential for adverse impacts to any wildlife species, 214 including listed species, is low. Care was taken in the corridor routing to avoid and minimize proximity to known listed species locations. Listed species pre-clearing and construction surveys will be conducted. Prior to conducting surveys, FPL will coordinate with the FWC and USFWS to obtain and follow the current survey protocols, as memorialized in the FWC-recommended conditions of certification to which FPL has agreed to comply in any of the western corridors. 619. The ecological value of the uplands to wetland- dependent listed species for nesting and denning will not be adversely affected by location, construction, operation, and maintenance of the western transmission lines in any of the western corridors. 620. The location, construction, operation, and maintenance of the proposed transmission lines in any of the western transmission line corridors will not have an adverse effect on the abundance and diversity of wildlife, including listed species, because all corridors offer flexibility in locating the ROW to avoid site-specific listed species locations, all corridors will be required to comply with conditions of certification requiring pre-clearing and construction surveys, and all wetland impacts will be mitigated. 621. Construction of the proposed transmission lines in any of the western corridors proper for certification, or any 215 portion thereof, will not have a significant adverse effect on fish habitat or the abundance or diversity of fish. The location, construction, operation, and maintenance of the proposed transmission lines in any of the western corridors will not adversely affect the conservation of fish and wildlife populations, including endangered and threatened species, or their habitats; will not adversely affect the fishing or recreational values or marine productivity in the vicinity; will not adversely impact the functions of wetlands or other surface waters from a wildlife perspective; and will not adversely impact the ecological value of uplands to non-avian aquatic or wetland dependent listed animal species for nesting and denning. Construction, operation, location, and maintenance will comply with all of the conditions proposed by FWC and all agency substantive requirements. In light of the proposed protective measures and the proposed mitigation, the location, construction, operation, and maintenance of the proposed transmission lines in any of the western corridors will not cause adverse secondary impacts to fish and wildlife; will not adversely affect the fishing or recreational values or marine productivity in the vicinity; and will not adversely impact the functions of wetlands or other surface waters from a wildlife perspective. 216 Panthers The proposed western transmission line corridors are within the extreme southeastern area of the range of the Florida panther in south Florida. All western corridors fall partially within the panther primary zone and partially within the panther secondary zone. Florida panthers have been recorded in the area of the proposed western transmission line corridors. There is, however, a very low likelihood that panthers would actually occur in the area during construction. There are positive benefits that accrue to Florida panthers and their habitat and prey associated with the placement of transmission lines within panther habitats. Therefore, the transmission lines will not result in the loss of panther habitat or adverse impacts to the panther. FPL has proposed protection measures for Florida panthers in the unlikely event they would occur in the transmission line ROWs, including training of construction personnel and unannounced inspections. FPL has also agreed to FWC-proposed protection measures for Florida panthers. Those protection measures are sufficient to prevent adverse impacts to Florida panthers from the location, construction, operation, and maintenance activities associated with the proposed western transmission lines. 217 628. The location, construction, operation, and maintenance of the transmission lines will comply with all applicable non-procedural requirements related to protection of Florida panthers. Eastern Indigo Snakes 629. Eastern indigo snakes have not been observed in the western corridors. The location, construction, operation, and maintenance of the transmission lines will comply with all applicable non-procedural requirements related to protection of Eastern indigo snakes. Hydrologic Considerations 630. New access roads, structure pads, and stormwater discharges during construction in any of the western corridors proper for certification have the potential to impact surficial hydrology. NPCA contends that FPL's current proposal to construct culverts in its preferred corridors will stop sheet flow, the proposed roads and structure pads will disrupt water flow, and this will adversely affect the hydrological resources of the Everglades National Park. For the following reasons, these concerns are not well-founded. 631. Where new access roads are needed or upgrades are required to accommodate construction vehicles, those access roads will be unpaved and constructed using clean fill. Culverts will be included in wetland areas to maintain channel 218 flow and overland flow. Culverts are also expected to be used under structure pads where required to maintain existing surface flows. These culverts would help to equalize water volume and maintain pool equilibrium. 632. The spacing, diameter, and length of the culverts for access roads and structure pads will be based on hydrological studies that will be conducted post-certification, where final project elements are reasonably expected to impact surface or groundwater. Any culverts will comply with applicable conditions of certification. A combination of different culvert sizes is expected to be used. The design will be dictated depending on where the corridor is located and the amount of water that will need to be managed, among many different criteria. Typically, culverts installed in wetlands are designed so the bottom of the culvert will match the wetland floor elevation. 633. The proposed western transmission lines will comply with applicable agency non-procedural requirements, including requirements of the County, SFWMD, and Department, as well as SFWMD ROW Occupancy Permit Criteria. In particular, the conceptual design specified by FPL in its application will maintain surface water flows and will not result in ponding or flooding. 219 The location, construction, operation, and maintenance of the proposed western transmission lines will comply with applicable Department non-procedural environmental resource permitting criteria and other non-procedural requirements. Based upon the conceptual design specified by FPL in its application, the design of the roads and structure pads will incorporate drainage features such as culverts to allow the free flow of water. The function of culverts is to allow water to flow freely without impeding natural systems. The design used for the western transmission lines will ensure that culverts maintain equilibrium of water on both sides of roads and structure pads. FPL will also implement and maintain erosion and sediment control devices and best management practices such as silt fences, hay bales, erosion control blankets, and turbidity screens. FPL proposes to conduct hydrologic studies if the final project elements are reasonably expected to impact surface or ground water to ensure that any impacts associated with hydrology, water quality, and water supply will be avoided and minimized. FPL has committed to a flowage easement that would maintain existing sheet water and allow for future improvement 220 of surface water flows across the transmission line ROW located within the Biscayne Bay Coastal Wetlands CERP Project study area boundaries, which traverse the Turkey Point-U.S. Highway 1 section of the western transmission corridors. 639. FPL has proposed specific design measures to protect surficial hydrology of the Wink Eye Slough and the Northeast Shark River Slough. These sloughs are unique environmental features. The Wink Eye Slough traverses the west corridors in the Turkey Point-U.S. Highway 1 Section, common to all the west corridors. The eastern edge of the Northeast Shark River Slough is within the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 in the L-31N levee portion of the West Divergence Area. The predominant hydrologic flow of the Northeast Shark River Slough occurs west of the L-31N levee. FPL will design the transmission line access roads and structure pads to avoid sheet flow impacts to these sloughs, considering design alternatives such as culverts, stabilized at-grade roads, geoswales, or other techniques to maintain the sheet flow in compliance with applicable non-procedural requirements. CERP 640. The location, construction, operation, and maintenance of the proposed western transmission lines in any of the western corridors proper for certification are not 221 inconsistent with CERP Projects or the overall objectives of CERP. FPL demonstrated that the western transmission line structures and access roads will be designed and constructed in any of the western corridors in such a manner as to maintain surface flows and sheet flow, and no flood hazards will be created as a result of the transmission lines or access roads. Access roads will be properly culverted and appropriately constructed so as to maintain drainage and manage water quality and will not interfere with sheet flow or the higher water levels anticipated as a result of CERP implementation. The transmission line structures and access roads will not negatively impact the quality, quantity, or timing of the distribution of water. Given these considerations, a contention that the West Consensus Corridor/MDLPA No. 2 or back-up West Preferred Corridor will negatively affect the CERP Modified Water Deliveries Project, or specific goals and objectives of the CERP Yellow Book (the blueprint for Everglades restoration), is rejected. FPL has submitted flowage easements to the County for review in accordance with Condition 17 of County Resolution Z- 56-07. 222 East Everglades Area of Critical Environmental Concern The County has a zoning overlay district known as the East Everglades Area of Critical Environmental Concern (EEACEC) that comprises approximately 242 square miles, part of which is within the Everglades National Park. See ch. 33B, MDC. A portion of the corridor common to all western corridors crosses the EEACEC south of Southwest 120th Street. In the West Divergence Area, the FPL West Preferred Corridor and portions of the West Consensus Corridor/MDLPA No. 2 and MDLPA No. 1 follow the extreme eastern edge of the EEACEC where they travel along the L-31N levee. The EEACEC's northern boundary is Tamiami Trail. The remaining alternate corridors are not located within the EEACEC in this area. For parcels within the EEACEC zoning overlay district, additional restrictions apply to development to ensure, singly or cumulatively, no adverse effects on the hydrologic or ecologic integrity of the east Everglades. See ch. 33B, MDC. For the reasons set forth in the Conclusions of Law, these EEACEC restrictions do not apply to transmission lines. Notwithstanding the inapplicability of these restrictions, the evidence establishes that the location, construction, operation, and maintenance of the western transmission lines in corridors traversing the EEACEC in 223 compliance with the agreed-upon conditions of certification will maintain existing flows and water quality and will not have an adverse impact on natural flow of water or cause a change in water quality or quantity in the adjacent Everglades National Park. 646. The location, construction, operation, and maintenance of the western transmission lines in any portion of the EEACEC likewise would not have an adverse impact on wetland flora and fauna within the adjacent Everglades National Park or cause material injury to wetland ecology on adjoining lands or on portions of the ROW not proposed for placement of the transmission lines. For example, FPL has committed to employ best management practices during construction to avoid sedimentation and undertake exotic vegetation control within the ROW. Bird Drive Everglades Wetland Basin and North Trail Basin 647. The County has two environmental districts within portions of the proposed western transmission line corridors, which have been adopted in chapter 24, MDC. The Bird Drive Everglades Wetland Basin (Bird Drive Basin) is located south of Tamiami Trail and east of Krome Avenue. The North Trail Basin is located north of Tamiami Trail and approximately two miles east of Krome Avenue. 224 648. Sections 24-48.20 and 24-48.21 require that all work within the Bird Drive Basin or the North Trail Basin must be consistent with the Land Management Plan to ensure the maintenance of biological resources in that area. Those provisions call for minimizing impacts to flood drainage; minimizing impacts to water storage capacity and Biscayne Aquifer recharge; and maintaining desirable biological values, or mitigating for loss of such values. 649. A portion of the West Consensus Corridor/MLDPA No. 2, MDLPA No. 3, and the NPCA Corridor traverse the Bird Drive Basin and North Trail Basin. The West Consensus Corridor/MDLPA No. 2 traverses a short distance of the northern portion of the Bird Drive Basin and the westernmost edge of the North Trail Basin. MDLPA No. 3 and the NPCA Corridor traverse a significant portion of the Bird Drive Basin and the western edge of the North Trail Basin. The FPL West Preferred Corridor and MDLPA No. 1 are not located within the Bird Drive or North Trail Basins. 650. The western transmission lines will not cause impacts to flood drainage, will minimize impacts to water storage capacity and Biscayne Aquifer recharge, and will allow the areas to maintain desirable biological values. The location, construction, operation, and maintenance of the western transmission lines in any portion of the Bird Drive Basin or 225 North Trail Basin will not cause any unmitigated impacts to wetlands. The placement of the western transmission lines in any of the western corridors within the Bird Drive Basin and North Trail Basin will be compatible with the County's land management plans for those areas. Natural Forest Communities Two NFCs are located in the section of the western corridors between U.S. Highway 1 and Southwest 120th Street, a section that is common to all the western corridors. In accordance with Condition 20 of County Resolution Z-56-07, FPL will minimize impacts to NFCs in the western corridors consistent with the NFC standards and requirements of chapter 24, MDC. FPL has agreed to a stipulation and associated conditions with the County to not place any structures within the edge of the Sunny Palms NFC, which is included in the western transmission line corridors. For the Kings Highway Pinelands NFC, FPL already has an existing easement and transmission line crossing in this area. Additional vegetation clearing and construction for the certified facilities will occur only in accordance with the stipulated conditions applicable to NFCs. 226 Use of SFWMD ROW, Crossings, and Levees FPL's proposed western transmission lines will cross several SFWMD canals and may use a portion of SFWMD ROW linearly along the L-31N and L-30 levees. The proposed western transmission lines also involve the crossing of SFWMD bridges. Crossings of SFWMD canals and crossing or use of SFWMD levees and bridges will be required for all western corridors. The FPL West Preferred Corridor traverses or runs longitudinally with the following SFWMD facilities: L-31E canal, C-113 canal, C-103 (Mowry) canal, C-102 (Princeton) canal, L-31N canal, C-1W (Black Creek) canal, C-4 (Tamiami) canal, L-29 Borrow Enlargement, and L-30N canal. The FPL West Preferred Corridor or West Consensus Corridor/MDLPA No. 2 may use SFWMD levees L-31N, L-30, and L-29 for access during construction, operation, and maintenance. MDLPA No. 1, MDLPA No. 3, and the NPCA Corridor may also require the crossing of several SFWMD facilities including canals and levees. The location, construction, operation, and maintenance of the proposed transmission lines will not interfere with the present construction, alteration, operation, or maintenance of the works or lands of the SFWMD that are crossed. While parallel runs have a potential for interfering with the District's operation and maintenance of its system, it is possible to accommodate transmission lines with site-specific 227 configurations. Transmission lines have been successfully designed and constructed within SFWMD ROW previously. The location, construction, operation, and maintenance of the proposed transmission lines will not interfere with proposed future construction, alteration, operation, or maintenance of the works or lands of the SFWMD that are crossed. This applies only to proposed future construction, alteration, operation, or maintenance known at the time of FPL's project design. The proposed transmission lines within SFWMD lands will not result in damage from soil erosion. Structural integrity of bridges crossed by vehicular traffic will be certified by a professional engineer registered in the State of Florida. Before FPL's use of levees for construction and maintenance access, FPL will coordinate with the SFWMD Right-of- Way Department to develop a plan for compatible use of these facilities. Any improvements within the associated canal ROWs will maintain the structural integrity of the levee(s) at a level as good as or better than the conditions in existence immediately prior to commencement of FPL's work activities. All activity within SFWMD ROWs will be conducted consistent with applicable SFWMD non-procedural requirements and 228 will be consistent with the development and regulation of dams (or levees) and other works to provide water storage for beneficial purposes. 662. The western transmission lines will not adversely affect the levees or other works crossed or paralleled by the transmission lines; unduly burden SFWMD interests; contribute to damage from floods, soil erosion, or excessive drainage; affect disease-carrying vectors and pests so as to impact public health and welfare; or have adverse effects on human health or waters of the state. 663. SFWMD has stipulated to the use of its ROWs in whichever corridor is ultimately approved for certification, provided the Conditions of Certification in Attachment 1 to this Recommended Order are met. 664. FPL has agreed to accept the conditions of certification offered by SFWMD, and FPL has demonstrated that the conditions offered by SFWMD relating to ROW occupancy permits will be met. Upland Easement 665. The 230-kV segment of the western transmission lines that is common to all western corridors proper for certification includes an approximately four-acre parcel of state-owned uplands. The parcel is adjacent to an existing FPL transmission line ROW through previously mined areas east of Levee substation 229 and northwest of the intersection of Doral Boulevard and the Homestead Extension of the Florida Turnpike. The area is currently subject to a commercial mining lease and is a limerock mine. FPL has requested that the Siting Board direct the Board of Trustees to issue an upland easement for this approximately four-acre parcel through this proceeding. 666. The upland easement over this narrow strip is required for the Clear Sky-Pennsuco 230-kV transmission line in order to comply with EMF standards and to accommodate conductor swing out in high winds. No construction will occur within the upland easement. 667. The narrow strip of uplands for which FPL is seeking an easement from the state is between two rock mine pits and currently used as a berm access road by mining operations. It has limited value to wildlife. All of the western corridors must use this same segment. 668. FPL will undertake all activities on the upland easement in accordance with best management practices. Placement of the proposed transmission line in the area of the requested upland easement over state lands will not have adverse impacts on conservation, the environment, natural resources, wetlands, or fish and wildlife values. 669. If the easement is not obtained, FPL could still construct the proposed line, but that would involve 230 reconstructing two of the existing transmission lines to make adequate space within FPL's existing ROW, and it may be very difficult to get the extended transmission line outages that would be required to reconstruct those facilities. 670. Grant of the easement is not contrary to the public interest, as the area is already subject to a commercial mining lease and is a limestone mine. There is a clear public need for the Project, and there are no reasonable alternative locations. The public does not use the area to be covered by the upland easement. General Considerations 671. The evidence establishes that the structural integrity of bridges, dams, or levees will not be affected by construction or operation of the western transmission lines; the lines will not cause damage from soil erosion; they will not cause or contribute to flood damage or excessive drainage; they will not affect disease-carrying vectors and pests so as to impact public health and welfare; and they will not have other adverse effects on human health or water resources. 672. The location, construction, operation, and maintenance of the western transmission lines in accordance with the conditions of certification will comply with applicable noise regulations and will not have an adverse impact on air quality. 231 The western transmission lines will comply fully with the applicable Department standards for EMF from transmission lines. The location, construction, operation, and maintenance of the proposed transmission lines in any of the western transmission line corridors proper for certification will not adversely impact archaeological or historic structures, sites, or resources. There is no material difference between the western transmission line corridors proper for certification in terms of impacts to cultural resources and archaeological and historic sites. All of the western corridors provide sufficient access to the proposed transmission lines, either via existing public roads, existing FPL access roads, or through the use of access corridors to ensure suitable access. All of the alternate corridors east of the L-31N and L-30 levees provide flexibility for access because there will be multiple opportunities for access on public roadways along those routes. There will be no adverse traffic impacts from construction of the proposed transmission lines in any of the western corridors. The western corridors are compatible with DOT and Miami-Dade Transit long-range plans. If constructed within any of the corridors proper for certification, the proposed western transmission lines will 232 comply with the applicable non-procedural requirements of the local governments in which they will be located. These applicable non-procedural requirements include the requirements of Florida City, Doral, Medley, and the County that FPL: (1) construct and maintain transmission lines in accordance with FPL's customary practice; (2) ensure that its transmission lines do not unreasonably interfere with traffic on public ROW or reasonable egress from and ingress to abutting property; (3) ensure that transmission lines be located as close to the outer boundary of public ROW as practicable, or as agreed with the local government; and (4) repair or restore any damage to public ROW caused by construction or maintenance of transmission lines. 678. Impacts to wildlife habitat and listed species in any of the western corridors will be avoided, minimized, and mitigated. All of the western transmission line corridors proper for certification are appropriate for placement of the proposed western transmission lines from a wildlife perspective. 679. The evidence establishes that all of the five western corridors proper for certification meet the criteria for certification set forth in section 403.509(3). 7. Corridor Comparison: Least Adverse Impacts Including Costs 680. As found above, the multidisciplinary team evaluated the various proposed western transmission line corridors based 233 on a theoretical centerline of the transmission lines through the middle of each corridor, with the centerline adjusted as needed to avoid certain obstacles. The comparative evaluation also assumed use of a ROW obtained through the implementation of the Land Exchange. For the NPCA Corridor, FPL evaluated both the alignment as proposed by NPCA and an adjusted centerline based on FPL's expertise as more feasible than that proposed by NPCA, to allow for a more equitable comparison. Environmental Comparisons 681. Within the West Divergence Area, the FPL West Preferred Corridor would impact a maximum of 137 wetland acres, although these figures will likely be significantly reduced through FPL's final transmission line design process. The West Consensus Corridor/MDLPA No. 2 would impact no more than 122 wetland acres. The wetland ecology in both corridors is generally similar, as is the estimated acreage of wetland impact. Wetland quality in both corridors ranges between 0.70 and 0.80 as measured by UMAM. 682. Within the West Divergence Area, MDLPA No. 1 and MDLPA No. 3 would impact up to 138 or 104 wetland acres, respectively, and those wetlands range in quality from 0.70-0.80 (MDLPA No. 1) to 0.60-0.80 (MDLPA No. 3). 234 683. Using either centerline alignment, the NPCA Corridor would impact up to 91 wetland acres, ranging in quality from 0.60 to 0.70. 684. Construction of the proposed transmission lines within the NPCA Corridor would traverse lower quality wetlands and require a smaller amount of mitigation to offset unavoidable wetland impacts, as compared to the other proposed western corridors. 685. In the certification analysis required by section 403.509, wetland impacts are only one factor of a multi-faceted analysis. Determination of the appropriate corridor for certification is a balancing of the criteria, and impacts to wetlands or other natural resources are not the only factors in the analysis. See § 403.509(3), Fla. Stat. 686. From a surficial hydrology perspective, there is no material difference between any of the western corridors proper for certification, because each corridor can be engineered to maintain sheet flow and other surface water flow. However, the amount of engineering that would be required to maintain sheet flow in each area and the level of complexity involved differs between the corridors. The FPL West Preferred Corridor, MDLPA No. 1, and West Consensus/MDLPA No. 2 would require equivalent levels of surficial hydrology engineering. MDLPA No. 3 and the 235 NPCA Corridor would involve the least surficial hydrology engineering. 687. The potential for adverse unmitigated impacts to listed species is equally low within the FPL West Preferred Corridor and MDLPA No. 1, and lower in the West Consensus Corridor/MDLPA No. 2, MDLPA No. 3, and the NPCA Corridor. 688. From the perspective of PHUs, the NPCA Corridor would require the least panther mitigation credits (7), followed by MDLPA No. 3 (76), West Consensus Corridor/MDLPA No. 2 (207), MDPLA No. 1 (288), and FPL West Preferred Corridor (374). While PHUs are one metric for comparing potential habitat impacts, there is no material difference in any of the western corridors from a Florida panther perspective. Florida panthers are not adversely affected by, and may even benefit from, the presence of transmission lines. 689. There is no material difference among the western corridors with respect to potential impacts to American crocodiles or Eastern indigo snakes or their habitats. 690. The presence of the Everglades National Park was considered in the comparison of the alternate corridors and in the selection of the FPL West Preferred Corridor because it potentially harbors more listed wildlife species and is the subject of various government-funded restoration projects. 236 691. From a wildlife habitat standpoint, the FPL West Preferred Corridor and MDLPA No. 1 are about equivalent, with West Consensus Corridor/MDLPA No. 2, MDLPA No. 3, and the NPCA Corridor ranked as somewhat more desirable. However, in all of the western corridors proper for certification, the potential for adverse impacts to any wildlife species, including listed species, is low, given the pre-clearing listed species surveys and construction methods to be employed that serve to avoid and minimize impacts, as discussed above. FPL's wildlife experts do not see a significant difference in impact between the corridors from a wildlife perspective, and FWC recommends the identical wildlife conditions of certification for all western transmission line corridors. 692. In the FPL West Preferred Corridor and MDLPA No. 1, the potential for adverse impacts to any wildlife species is low. In any of the other proposed western alternate transmission line corridors, that potential is lower. Land Use Comparison 693. The proposed western transmission lines in any of the western corridors will be compatible with adjacent land uses and consistent with the communities' priorities and preferences as reflected in the comprehensive plans and land development regulations. However, it is desirable from a land use perspective to be further from residential and urban land uses. 237 694. FPL balanced proximity to both existing and planned urban development/adjacent land use considerations, engineering considerations, and environmental considerations/effect on environmentally sensitive areas in comparing the western transmission line corridors and attempted to achieve the best balance of all of those considerations in selecting its preferred corridors. The presence of the Everglades National Park was one factor in the analysis. In contrast, NPCA and the County reviewed and considered primarily environmental impacts in proposing and comparing the various western corridors or assessing corridor impacts. 695. FPL assessed the visibility of the proposed transmission line structures from various vantage points. NPCA did no comparative visual impact analysis, including no assessment of visual impacts to Everglades National Park visitors. The County assessed only whether the proposed lines would be visible from Management Area 1, also known as the 8.5 Square Mile Area. 696. The west transmission line structures placed in any of the western corridors proper for certification would not be visible to visitors at the Everglades National Park Shark Valley Visitor's Center Observation Tower, which is approximately 16.7 miles west of the L-31N levee. At an airboat vantage point within Everglades National Park approximately 3.44 miles west of 238 the L-31N levee, existing structures in the area, such as the Miccosukee Indian Casino and numerous radio and cell towers, are visible, but the proposed transmission lines in the closest corridor proper for certification (the FPL West Preferred Corridor) would be barely visible on the horizon. 697. Transmission lines are not uncommon in rural areas. The location, construction, operation, and maintenance of the proposed western transmission lines in the west alternate corridors will not cause significant adverse effects to scenic or recreational values. 698. In the West Divergence Area, the FPL West Preferred Corridor is the farthest away from any urban or residential areas, minimizing potential for conflicts with adjacent land uses. The greater the distance a residence is from a transmission line, the likelihood of the visibility of that transmission line is reduced. Along the L-31N levee/Land Exchange area, there are three buildings within 500 feet of the FPL West Preferred Corridor centerline, one of which is residential. The FPL West Preferred Corridor is predominantly within existing ROWs or runs along existing linear features and would require crossing 49 individual parcels or lots throughout its length. 699. Regarding the number of buildings within 500 feet of the corridor centerline for the various corridor alignments, the 239 MDLPA No. 1 centerline has three buildings, one of which is residential; the West Consensus Corridor/MDLPA No. 2 centerline and the MDLPA No. 3 centerline each have nine buildings, two and four of which are residential, respectively; the NPCA Corridor recommended centerline has five buildings, all of which are residential; and the NPCA Corridor adjusted centerline has seven buildings, six of which are residential. The two NPCA Corridor centerline route alignments considered by FPL are close to urban areas. MDPLA No. 1 centerline would require FPL to cross 45 separate parcels, while the West Consensus Corridor/MDLPA No. 2 centerline would require crossing of 63 parcels, although some of these private parcels are owned by mining companies who may be amenable to land donations if the West Consensus Corridor/ MDLPA No. 2 is certified. MDLPA No. 3 centerline, the NPCA Corridor recommended centerline, and the NPCA Corridor adjusted centerline would require the crossing of 96, 108, and 104 individual parcels, respectively. The higher the number of parcels to be crossed, the higher the acquisition costs will be. 700. In considering the number of buildings in proximity and the number of parcels crossed, the West Consensus Corridor/MDLPA No. 2, FPL West Preferred Corridor, and MDLPA No. 1 rank equally. MDLPA No. 3 and both of the NPCA Corridor centerline alignments ranked as the least desirable when considering these two land use factors. 240 701. MDLPA No. 1, like the FPL West Preferred Corridor, follows along existing levees for a good portion of its length (11.1 miles); West Consensus Corridor/MDLPA No. 2 and MDLPA No. 3 follow 8.3 and 4.8 miles of linear features, respectively, while the two NPCA Corridor route alignments would follow 7.1 or 5.9 miles of such features, respectively. The ability to collocate with existing linear features is important from a land planning perspective, as linear features serve as a seam between land uses and avoid or minimize potential conflicts with adjacent land uses, in addition to minimizing impacts to wildlife and wildlife habitat. There is also an efficiency to be gained by collocating in an existing utility ROW in terms of maintenance. 702. Accordingly, MDLPA No. 1 and the FPL West Preferred Corridor rank as the "most desirable" in terms of the ability to co-locate the new transmission lines with existing linear features in the landscape and thereby minimize potential adverse land use impacts. The West Consensus Corridor/MDLPA No. 2 Corridor and the remainder of the proposed western transmission line alternate corridors ranked as less desirable for this aspect, although in no case would the transmission lines change the land uses within the corridor. 703. FPL's multidisciplinary team expressly considered whether and how much of a corridor was located in conservation 241 lands, and in particular, the Everglades National Park. The FPL West Preferred Corridor does not traverse the wetlands comprising the Bird Drive Basin or the North Trail Basin. In contrast, the other western transmission line alternate corridors impact either Bird Drive Basin or North Trail Basin wetlands, with MDLPA No. 1 impacting 0.11 acres, West Consensus Corridor/MDLPA No. 2 impacting 2.27 acres, and MDLPA No. 3 and the two NPCA Corridor alignments impacting between 4.81 and 5.92 acres of wetlands, respectively, in these basins. The West Consensus Corridor/MDLPA No. 2, MDLPA No. 3, and NPCA Corridor avoid most or all of the Pennsuco Wetlands. None of the corridors traverse the Everglades National Park. 704. The FPL West Preferred Corridor is located primarily along the L-31N levee, which represents a seam between conservation uses of the Everglades National Park and more developed land uses to the east. Around 4.8 miles will be located in conservation lands. MDLPA No. 1 also has 4.8 miles in conservation lands, and MDLPA No. 3 and the NPCA Corridor alignments range between 3.8 and 4.1 miles in such lands. In contrast, the West Consensus Corridor/MDLPA No. 2 has only 2.8 miles of its length in conservation lands. 705. The Land Exchange would give FPL fee simple or easement rights over a contiguous ROW within the West Preferred Corridor as well as portions of MDLPA No. 1 and West Consensus 242 Corridor/MDLPA No. 2. Those rights are contingent on the Land Exchange occurring. This would leave no ROW to be acquired over government-owned parcels in the FPL West Preferred Corridor. If the Land Exchange occurs, MDLPA No. 1 would cross six government-owned parcels, while the West Consensus Corridor/ MDLPA No. 2 and MDLPA No. 3 cross 27 and 49 government-owned parcels, respectively. The NPCA Corridor proposed alignment would cross 74 governmental parcels; the adjusted centerline alignment drawn by FPL in the NPCA Corridor would only cross 47 such parcels. Thus, the FPL West Preferred Corridor is the most desirable from this standpoint. MDLPA No. 1 is slightly less desirable, and the remaining western transmission line alternate corridors, which require substantially more government land crossings, are the least desirable since it is often significantly more difficult, costly, and time-consuming to acquire ROWs across government-owned parcels, and FPL may not have eminent domain authority to acquire those parcels if the agencies are not willing sellers. 706. Land uses within the FPL West Preferred Corridor and MDLPA No. 1 are canals and embankments and rock mining, the most desirable uses from a land use perspective. Land uses within the West Consensus Corridor/MDLPA No. 2 are rock mining and lands with regulatory overlays, somewhat less desirable due to the regulatory overlays. Lands within MDLPA No. 3 and the NPCA 243 Corridor are residential, agriculture, wellheads, and lands with regulatory overlays, which are less desirable land uses than those within the other three corridors. 707. The FPL West Preferred Corridor, MDLPA No. 1, and West Consensus Corridor/MDLPA No. 2 do not encroach on the UEA and are furthest from the UDB; thus, they are all equally the least likely of the western corridors to interfere with residential land uses. They run predominantly along seams between less developed, conservation lands to the west and transitional uses and more urban development to the east. They therefore avoid conflicts with more dense urban development. 708. MDLPA No. 3 and both NPCA Corridor alignments encroach on the UEA and are closest to the UDB. MDLPA No. 3 and the NPCA Corridor also cross the property of Limonar, a property owner with plans for future development that is opposed to the placement of transmission lines on its property. Also, placing a corridor over the UEA property would reduce the size of the UEA which has been identified by the CDMP that is available for urban development. 709. The mining companies prefer the West Consensus Corridor/MDLPA No. 2. It has the least interference with their uses and mining. It is on property where there is a lot of industrial activity associated with active rock mining, a heavy industry. In contrast, the mining companies are unsure of the 244 effect of MDLPA No. 3 on their ability to mine the eastern part of their property. There is a potential with the West Consensus Corridor/MDLPA No. 2 that the mining companies may be willing to donate their property for the transmission line ROW, thus offsetting the added cost of ROW acquisition in this corridor. However, the mining companies are not willing to do so for MDLPA No. 3. The West Consensus Corridor/MDLPA No. 2 is wide enough to provide flexibility in siting the proposed transmission lines so that both the 500-kV and 230-kV lines could potentially be located on mining property land in significant portions of that corridor. However, there are some features such as the rock processing plant and shipping area near the quarry that could limit or preclude siting of the proposed transmission lines, requiring the lines to be placed in other portions of the corridor in this area. MDLPA's goal for MDLPA No. 1 was simply to minimize potential impacts to the Pennsuco Wetlands; for the West Consensus Corridor/MDLPA No. 2 and MDLPA No. 3, the goal was both to minimize impacts on Everglades National Park and on Pennsuco Wetlands. The benefits of the West Consensus Corridor/MDLPA No. 2 include avoiding a central crossing of the Pennsuco Wetlands and completely removing the proposed transmission lines from Water Conservation Area 3B. This 245 corridor is also further removed from known wood stork colonies along and north of Tamiami Trail, and is farther east of potential Everglade snail kite foraging habitat within the Everglades National Park. Although the western transmission lines would not interfere with surface flows in any of the corridors, MDLPA believes use of the West Consensus Corridor/ MDLPA No. 2 would be less likely to interfere with any attempts to restore flow inside the eastern part of Everglades National Park and also removes any potential future conflict inside Water Conservation Area 3B, if any. Engineering Comparisons i. Traffic There is no material difference with regard to traffic impacts between any of the western corridors proper for certification. There is minimal to no risk of conflict with traffic or with future roadway expansion or road widening projects in the FPL West Preferred Corridor or MDLPA No. 1. The remaining western corridors present some risk of potential conflict with the proposed expansions of Krome Avenue near Kendall Drive and the State Road 836 Southwest Extension, but it is recognized that conflicts with these projects are highly speculative at this stage. 246 Construction and Maintenance Access In the West Divergence Area, while all of the western corridors provide reasonable access for construction and maintenance, access along the FPL West Preferred Corridor and West Consensus Corridor/MDLPA No. 2 may be limited to one-way traffic. ROW Acquisition For the West Preferred Corridor, FPL has executed agreements in place from all of the landowners involved in the Land Exchange area for conveyance of land clear of encumbrances. Already authorized by Congress, significant investment and commitment has been made to this exchange. It would also encompass portions of the West Consensus Corridor/MDPLA No. 2, MDLPA No. 1, MDLPA No. 3, and the NPCA Corridor. From an engineering/constructability standpoint, the difficulty or ease in acquiring the necessary property interest in the land underlying the corridors is a significant consideration. Following implementation of the Land Exchange, the FPL West Preferred Corridor would be highly desirable from a property acquisition standpoint, as FPL would own all of the necessary property interests for placement of the western transmission lines in the FPL West Preferred Corridor. The remaining corridors are less desirable from this perspective, as FPL would need to acquire permanent easements over numerous 247 government parcels within any of the alternate corridors. Since FPL does not have eminent domain authority over all government lands, its ability to acquire the necessary easements over government parcels is uncertain. Additionally, consistent with past practice, FPL would seek a ROW over lands owned by the SFWMD, which would lessen this concern for the other western transmission line alternate corridors, and in particular, MDLPA No. 1 and the West Consensus Corridor/MDLPA No. 2, both of which also incorporate the L-31N and L-30 levees. If the Land Exchange is timely implemented, no further ROW acquisition will be required for the West Preferred Corridor. A small portion of the West Consensus Corridor/MDLPA No. 2 will also use properties obtained through the Land Exchange. Between the point where the West Consensus Corridor/MDLPA No. 2 turns east from the SFWMD L-31N ROW and the point where it converges with the FPL West Preferred Corridor west of the Levee substation, FPL will need to establish a new ROW for the western transmission lines. Some of the government parcels in the area where the western alternate corridors diverge from the FPL West Preferred Corridor were purchased with federal funds or other grants that limit the uses of the property. These encumbrances may be overcome if FPL purchases substitute land for the encumbered parcels. But removal of the encumbrances held by federal 248 agencies would require action or review under the National Environmental Policy Act. It is not known how much time or cost would be required to clear these encumbrances. These uncertainties are the reason FPL is seeking certification of the FPL West Preferred Corridor as a back-up to the West Consensus Corridor/MDLPA No. 2. d. Cost Comparisons The FPL West Preferred Corridor would cost approximately $229.4 million to construct. MDLPA No. 1 would cost approximately $282.5 million, while the West Consensus Corridor/MDLPA No. 2 would cost around $273.2 million. The NPCA Corridor adjusted centerline alignment would cost approximately $262.15 million. MDLPA No. 3 and the NPCA Corridor centerline would cost approximately $298.25 million and $313.7 million, respectively. Conflicting testimony was presented on the cost of the NPCA Corridor ROW. Testimony by NPCA indicated that a transmission line ROW could be acquired within its alternate corridor for approximately $23.3 million. However, the methodology used to prepare this estimate has not been credited. FPL submitted an appraisal consistent with the Uniform Standards of Professional Appraisal Practice that showed the cost for FPL to acquire a transmission line ROW in the NPCA Corridor would be approximately $84 million. This estimate includes the cost of 249 the property, any damages to remainder parcels (severance damages), title work, survey work, legal fees, and appraisal fees, but does not include the cost to acquire and substitute lands for parcels within the transmission line ROW with federal encumbrances. Determination of the costs associated with exchanging substitute lands to clear encumbrances on government- owned parcels is not possible until a final ROW for the western transmission lines is identified and negotiations completed on the substitute lands to be accepted. Summary: Least Adverse Impacts, Including Cost Given these considerations, the West Consensus Corridor/MDLPA No. 2 has the least adverse impact, including costs, only if a ROW within that corridor can be acquired in a timely manner and at reasonable cost. If a ROW within the West Consensus Corridor/MDLPA No. 2 cannot be secured in a timely manner and at a reasonable cost, then the FPL West Preferred Corridor has the least adverse impact, including costs. While the FPL West Preferred Corridor is the least expensive and preferable from a land use perspective, including being farthest from urban uses that might potentially conflict with the transmission line, the West Consensus Corridor/MDLPA No. 2 is subject to an agreement limiting acquisition costs to no more than ten percent above the total projected costs of the FPL West Preferred Corridor, rendering the West Consensus Corridor/MDLPA 250 No. 2 the second least expensive. In addition, the West Consensus Corridor/MDLPA No. 2 is sufficiently wide to allow flexibility to site the ROW within the Corridor in a manner to minimize conflicts. Neither the FPL West Preferred Corridor nor West Consensus Corridor/MDLPA No. 2 encroaches on land designated as UEA. The FPL West Preferred Corridor includes a central crossing of the Pennsuco Wetlands, while the West Consensus Corridor/MDLPA No. 2 avoids such a crossing. From a cost and adjacent land use standpoint, the West Preferred Corridor is somewhat preferable to the West Consensus Corridor/MDLPA No. 2 and significantly preferable to the remaining western transmission line alternate corridors. From an environmental standpoint, the West Consensus Corridor/MDLPA No. 2 is somewhat preferable to the FPL West Preferred Corridor and MDLPA No. 1, but less preferable than the NPCA Corridor. The West Consensus Corridor/MDLPA No. 2 is fairly equivalent to MDLPA No. 1 from an adjacent land use standpoint, but has the added advantages of allowing the placement of transmission lines farther from Everglades National Park and is less expensive than MDLPA No. 1. Also, the West Consensus Corridor/MDPLA No. 2 is less expensive than MDLPA No. 3 or the NPCA Corridor, and is significantly preferable in terms of adjacent land uses and ROW acquisition to these western transmission line alternate corridors. The FPL West Preferred Corridor and West Consensus 251 Corridor/MDLPA No. 2 are roughly equivalent and both represent, on balance, the corridors with the least adverse impacts, considering the factors set forth in section 403.509(3), including costs. 722. Certification of the West Consensus Corridor/MDLPA No. 2 and the FPL West Preferred Corridor, as conditioned, serves the broad interests of the public by ensuring reliable electric service at a reasonable cost. Conditions of Certification Agreed Upon Conditions of Certification 723. In constructing, operating, and maintaining the Project, including the Plant and its associated non-transmission facilities and transmission lines, FPL has agreed to comply with the Conditions of Certification in Attachment 1 to this Recommended Order. 724. FPL has provided reasonable assurances that the Project, including the Plant and its associated non-transmission facilities and transmission lines, can be constructed in compliance with the agreed-upon Conditions of Certification in Attachment 1. 725. The Department has proposed and FPL has agreed that the conditions in Attachment 1 are appropriate or necessary. They are therefore authorized. 252 726. The only condition relative to the plant and non- transmission line portion of the Project remaining in dispute is addressed in the "Road Right-of-Way Dedications" section above. That condition is not authorized. Other transmission line conditions of certification proposed by local governments remaining in dispute are discussed below. Disputed Conditions of Certification – Transmission Lines Miami-Dade County 727. The County submitted its Agency Report on the proposed transmission lines associated with the Project to the Department's Siting Coordination Office, pursuant to sections 403.5064(4), 403.507(2), and 403.526(2). The Agency Report proposed 73 conditions of certification relating to the FPL transmission line corridors. 728. The County and FPL reached agreement on conditions to resolve the concerns in the Agency Report enumerated in General Conditions 1-5, 7-25, 27-29, and 32; East Conditions 1-17, 19, 20(b), 21, and 22; and West Conditions 1, 2, 3, 4(b), 5(c), 6-8, and 10-18 (with the exception of certain conditions to be applied in the West Corridor Divergence Area). The County and FPL have not reached agreement on proposed General Conditions 6, 26, 30, and 31; East Conditions 18 and 20; West Conditions 4, 5, and 9; the unnumbered conditions on page 59 of the Agency 253 Report; and the conditions to be applied in the West Corridor Divergence Area (General Conditions 14-23 and West Conditions 6- 8, 11-13, and 16-18). Those conditions remain in dispute between the two parties. 729. FPL will comply with the conditions included in Sections C.VII.A through C.VII.5 of Attachment 1, which reflect the conditions stipulated with the County. 730. The Department's PAR for the transmission line portion of the application did not include some of the County's proposed conditions of certification, noting that section 403.507(3)(c) and rule 62-17.133(4) require that agency recommendations for conditions of certification be limited to those within the proposing agency's jurisdiction and authorized by a specific statute, rule, or ordinance. All of the conditions that remain in dispute between FPL and the County were rejected by the Department in Appendix I to the PAR. 731. Proposed General Condition 6 relating to air quality is rejected because it is based on provisions of state regulations, the County's comprehensive plan, which is not applicable to the proposed transmission lines, and section 24- 7(6), MDC, establishing that the County Department of Environmental Resources Management has the authority to render assistance to persons operating equipment which may cause air pollution. The state regulations do not provide a proper basis 254 for a County condition and the comprehensive plan is not applicable to the proposed transmission lines, as discussed in the Conclusions of Law. Further, FPL established that the proposed transmission lines will not cause air pollution if constructed in compliance with the conditions of certification in Attachment 1. Thus, General Condition 6 is rejected. 732. For the reasons cited previously, proposed General Condition 26 (ROW dedication) is rejected. 733. Proposed General Condition 30 seeks to require FPL to compensate the County for its review of the application. The bases for this condition are sections 403.511(4) and 403.531(4), which allow local governments to charge "appropriate fees." These provisions, however, relate to post-certification reviews, and not review of the application. Thus, proposed General Condition 30 is rejected. 734. Proposed General Condition 31 seeks to require FPL to work with the County and the SFRPC to provide electric vehicle charging stations at County parking lots and other locations. However, the County offered no evidence to support this condition. Thus, proposed General Condition 31 is rejected. 735. Proposed East Condition 18 relates to conditions based on the land use designations of certain areas. These conditions are based on comprehensive plan provisions that are 255 not applicable to the proposed transmission lines, and are hereby rejected. 736. Proposed East Condition 20 relates to impacts within BNP. FPL is in the midst of federal government agency review of the Project, in which the United States Department of the Interior, representing BNP, is participating. Thus, any conditions regarding activities within BNP will be addressed in that federal process. The County cites only comprehensive plan provisions, which are not applicable to the proposed transmission lines, as bases for this condition. Further, it provided no evidence to even suggest that the proposed transmission lines will create negative impacts within BNP. Thus, proposed East Condition 20 is rejected. 737. Proposed West Conditions 4, 5, and 9 propose to restrict transmission lines based on land use designations and are based entirely on the comprehensive plan. Because the comprehensive plan is not applicable to the proposed transmission lines, these three conditions are rejected. 738. On page 59 of the Agency Report are listed five conditions of certification proposing to preclude the location of transmission lines in certain areas, including most of the West Corridor Divergence Area, based on the East Everglades Area Zoning Overlay District found in chapter 33B, MDC. Those zoning provisions are not applicable to the proposed transmission lines 256 and are not a proper basis for these proposed conditions. Other agencies, including the Department, SFWMD, and FWC, have proposed conditions that will require FPL to avoid and minimize impacts to the environmental resources in that area, and FPL has established that the transmission lines can be constructed, operated, and located to avoid and minimize impacts to the environmental resources in that area. Thus, these proposed conditions are rejected. Further, although the Department did not originally recommend the proposed conditions relating to wetlands protection and wildlife in its PAR, FPL is willing to accept those conditions in the West Corridor Divergence Area. These conditions are found in Attachment 1, §§ C.VII, I, J, and P. 739. The County has also proposed conditions for the West Consensus Corridor/MDLPA No. 2 that are similar to or the same as the conditions in the FPL West Preferred Corridor. Conditions 1 through 6 are based on the County zoning code and comprehensive plan, are not applicable to the proposed transmission lines, and are rejected. Further, FPL has established that the proposed transmission lines in the West Consensus Corridor/MDLPA No. 2 will not adversely impact the environmental resources in the West Corridor Divergence Area. Even so, FPL is willing to accept the County-proposed conditions relating to wetlands protection and wildlife in the West 257 Divergence Area. Those conditions have been included in Attachment 1. 740. Proposed Condition VII of County Exhibit 11, relating to alternate corridor access roads, tree islands, and Trail Glades Park, has been partially incorporated by the Department into the Conditions of Certification. FPL has agreed to comply with those conditions recognizing that "tree islands" are defined in section 24-5, MDC, as "a vegetative community located within freshwater wetlands whose dominant vegetation components consist of native hardwood trees and shrubs." Although the County proposed expanded versions of those conditions, those expanded versions are rejected because the County failed to present credible evidence to support those requirements. 741. Because PAC, MDLPA No. 1, MDLPA No. 3, and the NPCA Corridor are not recommended for certification, the County- proposed conditions for those corridors are rejected. 2. City of Miami 742. The City of Miami's Agency Report on the proposed transmission lines proposes conditions 5.1 through 5.15 to address its regulatory and other concerns related to the proposed transmission line. It also recommends denial of the proposed transmission line certification. 743. The City of Miami and FPL have reached an agreement on conditions to resolve the City's concerns set forth in 258 conditions 5.1, 5.3, 5.7, 5.8, 5.9, 5.11, 5.12, 5.13, 5.14, and 5.15 on the FPL Corridors, and conditions 5.1, 5.3, 5.7, 5.8, 5.9, 5.10, 5.12, 5.13, 5.14, and 5.15 on the Alternate Corridors. The stipulation acknowledged that the City of Miami's proposed conditions 5.2 (undergrounding), 5.4 (zoning), 5.5 (landscaping), 5.6 (EMF), and 5.10 (scenic transportation corridor) for the FPL East Preferred Corridor and 5.2, 5.4, 5.5, and 5.6 for the PAC remain in dispute between the two parties. FPL will comply with the conditions included in sections C.X.A. and C.X.C through C.X.G. of Attachment 1, which reflect the conditions stipulated with the City of Miami. 744. The Department's PAR for the transmission line portion of the application did not include some of the City of Miami's proposed conditions because section 403.507(3)(c) and rule 62-17.133(4) require that agency recommendations for conditions of certification be limited to those within the proposing agency's jurisdiction and authorized by a specific statute, rule, or ordinance. However, the Department included condition 5.10, as proposed by the City of Miami. 745. FPL will comply with the applicable non-procedural requirements of proposed condition 5.10 regarding the City of Miami's Scenic Transportation Corridor starting at Southwest 13th Street and continuing along Coral Way, as reflected in section C.X.B of Attachment 1. FPL also agrees that the 259 condition should be imposed on the construction of the transmission line within the East Preferred Corridor. This scenic transportation corridor is not located within the PAC, and is not relevant for that corridor. 746. FPL will comply with the applicable non-procedural requirements of the City of Miami's ordinances to protect and minimize impacts to trees in the construction and placement of the transmission line, and to replace or mitigate for any damage to, or removal of trees in, the construction and placement of the transmission line. To address the City of Miami's concerns regarding trees in proposed condition 5.5, FPL agrees that the condition in section II.A of Attachment 2 should be imposed on the construction of the transmission line within either of the east corridors proper for certification. 747. The City of Miami contends that FPL should exceed the applicable requirements of its ordinances to protect against tree impacts and/or replace trees damaged or removed as a result of the transmission line. However, such requirements are undefined, exceed the scope of the ordinances, and are rejected. See § 403.507(3)(c), Fla. Stat. 748. The City of Miami also proposed conditions 5.2 and 5.4 requiring underground construction of the transmission line in either of the east corridors. Those conditions are rejected 260 for the reasons previously discussed and in the Conclusions of Law. 749. The City of Miami proposed condition 5.6 regarding EMFs in both east corridors. However, it failed to offer into evidence this section of its two Agency Reports. The City's proposed condition is rejected because that topic is exclusively regulated by the Department; FPL has demonstrated that it will comply with the relevant, applicable Department standards; and the City of Miami presented no credible evidence to rebut that showing. 750. The City of Miami proposed condition 5.9 regarding historic resource preservation in both east corridors. On this issue, FPL established that it will comply with the applicable City of Miami non-procedural requirements through the conditions proposed in Attachment 2, section II.B. No credible evidence to the contrary was presented. Accordingly, condition 5.9 is rejected, and the condition proposed in Attachment 2, section II.B. is accepted. 3. City of Coral Gables Coral Gables' Agency Report on the proposed transmission lines proposed conditions A-Q relating to the FPL East Preferred Corridor. Coral Gables and FPL have reached an agreement on conditions to resolve Coral Gables' concerns set forth in 261 conditions A.5, C.1, D, E.1, E.2, E.3, E.4, F, G, H.1, H.2, I., J.1, J.2, K, L, M.1, M.2, M.3, N, O, and P in the Agency Report. However, they have not reached agreement on proposed conditions A.1, A.2, A.3, A.4, A.6, B, C.2, and Q. Those conditions remain in dispute between the two parties. FPL will comply with the conditions included in sections C.VIII.A. through C.VIII.P. of Attachment 1, which reflect the conditions stipulated with Coral Gables. The Department's PAR for the transmission line portion of the application did not include some of Coral Gables' proposed conditions because they fail to meet the requirements of section 403.507(3)(c) and rule 62-17.133(4). All of the conditions that remain in dispute between FPL and Coral Gables were rejected by the Department in Appendix I to the PAR. Proposed conditions A.1, A.2, A.3, and A.4 relate to aesthetic impacts of the proposed transmission line and are based on the zoning code and comprehensive plan. They are not applicable to the East Preferred Corridor and are rejected. Proposed condition A.6 seeks to require FPL to compensate Coral Gables for alleged "economic impacts" of the East Preferred Corridor. As discussed above, the more persuasive evidence establishes that the East Preferred Corridor will not cause negative economic impact to Coral Gables or properties within the City. Further, there is no ordinance 262 applicable to the proposed transmission lines that provides a basis for this condition. The proposed condition is rejected. 757. Proposed condition B seeks to require FPL to follow state laws regarding eminent domain in the acquisition of property rights for the proposed transmission line. However, FPL is already required to comply with state laws and regulations in the construction, operation, and maintenance of the transmission line, including in the acquisition of property rights. Further, Coral Gables cites no ordinance as a basis for this condition. Condition B is rejected. 758. Proposed condition C.2 seeks to require FPL to build the transmission line underground within the City, at FPL's expense. Coral Gables cites only its zoning code and comprehensive plan in support of the condition, which are not applicable to the proposed transmission line. For the reasons discussed above, this condition is rejected. 759. Finally, proposed condition Q, paragraphs 1 and 2, seek to require FPL to indemnify the City for any work done by FPL within the City. FPL is committed to comply with applicable ordinances requiring such indemnification and to comply with Condition C.VIII.P in Attachment 1 addressing this subject. Thus, no additional condition is required. Proposed condition Q, paragraph 3, seeks to require FPL to comply with all federal, state, and local regulations. FPL has committed to do so. 263 Thus, this condition is not required. Proposed condition Q, paragraph 4, seeks to require FPL to provide Coral Gables with any terms, benefits, or concessions or agreements provided to any other local government. Coral Gables has provided no applicable ordinance or other authority as a basis for this condition, and it is hereby rejected. Proposed condition Q, paragraph 5, adopts the recommendations and reports of the SFWMD, SFRPC, and the County. The issues of concern to those entities, as they relate to the FPL East Preferred Corridor, have been resolved to the satisfaction of those three agencies. Further, Coral Gables has identified no applicable non- procedural ordinance providing a regulatory basis for this condition. Accordingly, these proposed conditions are rejected. 4. Village of Pinecrest 760. Pinecrest's Agency Report on the proposed transmission lines proposed conditions A.1 through D.8 to address its regulatory and other concerns related to the proposed transmission line. It also recommended denial of the proposed transmission line certification. 761. The Department included proposed conditions C.3 (nuisances) and C.4 (emergency management) in the PAR. FPL will comply with those conditions, now found in section C.XII.A and C.XII.B of Attachment 1. 264 762. In addition, to address Pinecrest's concerns reflected in conditions A.2 (solid waste), A.3 (noise), B.1 (location of the transmission line within Pinecrest), B.3 (trees), D.2 (obstructions of visibility), D.5 (trees), D.6 (trees), and D.8 (ROW restoration), FPL agrees that the conditions in section III.A. through III.F. of Attachment 2 should be imposed on the construction of the transmission line within the East Preferred Corridor. FPL is willing to comply with these conditions and has demonstrated its ability to do so. 763. Proposed condition B.2 seeks to require that FPL coordinate with appropriate authorities to accommodate expansion plans for the Busway and Metrorail along U.S. Highway 1. FPL has coordinated with DOT, MDX, and Miami Dade Transit and reached agreement with those agencies on conditions of certification addressing future facilities. Thus, FPL has satisfied this requirement and there is no need for inclusion of the proposed condition in this Recommended Order. 764. For reasons previously stated, proposed condition C.1, which seeks to require FPL to construct the transmission line underground, is rejected. 765. Proposed conditions C.2 (pole placement information), D.1 (historical resources), D.3 (appearance of structures), D.4 (compliance with comprehensive plan), and D.7 (signs) seek to require FPL to comply with chapter 30 of Pinecrest's LDRs and 265 its comprehensive plan. These conditions are rejected for the reasons previously found. 5. Cities of Doral and South Miami 766. Doral and South Miami also proposed conditions of certification beyond those included by the Department in Attachment 1. However, these cities provided no evidence or legal argument to support these conditions, and they are rejected. Public Testimony and Comments 767. Six sessions on four separate days were held to allow members of the public to testify or offer comments on the Project. In addition, a number of written comments or letters were submitted by mail. Members of the public testified both in favor of and in opposition to the Project. 768. Members of the public who testified in favor of the Project commented on the economic benefits of the Project and specifically focused on the potential for job creation. Many members of the public also commented that they believe nuclear power is safe and clean and that this Project will allow South Florida to sustainably meet its future energy needs. Several members of the public testified that FPL is a good corporate citizen and environmental steward. 769. The individuals who testified in opposition to the Project raised a wide range of concerns, such as economic 266 impacts, property values, health-related and aesthetic impacts of the proposed transmission lines, as well as safety and environmental impacts of various features of the Project. 770. Some members of the public expressed concerns that the Project is not needed and should be deferred in favor of other energy alternatives. Several individuals testified that they believe the PSC's determination of need is out of date and should be reconsidered. A few members of the public testified that they are concerned that the power to be generated by the new nuclear units is actually intended for other areas of Florida. As to these concerns, the PSC has made its determination that the Project is needed to meet the needs of FPL's customers, based in part on the PSC's consideration of renewable and other energy resources. The PSC's need determination remains in legal effect. The PSC annually reviews the Project's costs. 771. Several members of the public expressed concerns related to radiological safety of the nuclear units. However, issues related to radiological safety are exclusively considered by the NRC and are beyond the scope of this proceeding. 772. Some members of the public expressed concerns about the safety of new nuclear units at the Turkey Point location in the event of a natural disaster, questioning sea level rise projections and storm surge and high winds during hurricanes. 267 Another member of the public testified regarding concerns related to the use of deep well injection. FPL considered reasonable sea level rise and storm surge projections in the design of the proposed nuclear units. Regarding the deep well injection, the evidence reflects that the Boulder Zone, which will receive the injection of Project wastewaters can adequately confine the planned volumes of wastewater. Underground injection has been extensively used in Florida. 773. Some members of the public testified that they are concerned about impacts to the Biscayne Aquifer, specifically expressing concerns about saltwater intrusion and other contaminants entering the water supply. A few members questioned how well isolated the proposed radial collector well laterals below Biscayne Bay will be from the Biscayne Aquifer. Others expressed concerns about conflicting water uses potentially increasing water costs. One individual testified that he believed that the APT was not adequate. FPL conducted an appropriate APT, in accordance with accepted professional procedures, at the site of the proposed radial collector wells as part of the extensive groundwater modeling of those wells. That modeling and other evaluations demonstrated that the operation of the radial collector wells would not cause saltwater intrusion or cause contamination or other adverse impacts to groundwater or drinking water sources. Under the 268 conditions of certification and an agreement with the County, FPL will use reclaimed water from the County as the primary source of cooling water and will use the radial collector wells only when reclaimed water is not available in sufficient quantity or quality. FPL's use of reclaimed water is a beneficial and cost-effective means of maximizing the use of reclaimed water and helps the County meet its reclaimed water compliance requirements. 774. A few members of the public are concerned about potential negative environmental impacts to Biscayne Bay. The evidence shows that the Project will not have negative effects on Biscayne Bay. Construction in upland areas near the Bay for the radial collector wells and the barge unloading area will utilize measures to prevent adverse impacts from runoff that might reach the Bay. The radial collector well laterals will be drilled beneath the Bay without any dredging in the Bay itself. Operation of the radial collector wells will not adversely affect the water quality including salinity, or the ecological resources including fisheries in the Bay, and the radial collector wells will be closely monitored to ensure there are no adverse impacts. 775. Members of the public testified both in favor of and in opposition to the proposed transmission lines. Several of the individuals who testified in opposition were only opposed to 269 the FPL East Preferred Corridor and supported the Project if the alternate corridor proposed by Coral Gables and Pinecrest is certified instead. Similarly, several individuals were only opposed to the alternate corridor proposed by Coral Gables and Pinecrest and support the Project with certification of the FPL East Preferred Corridor. The FPL East Preferred Corridor is the corridor with the least adverse impacts, including costs, when considering and balancing the statutory criteria in section 403.509(3). 776. Several individuals testified about negative aesthetic impacts or blight that may be caused by the installation of transmission lines within their communities. Several also stated that they were concerned about negative impacts to quality of life. Specific aesthetic concerns included the height and diameter of the transmission line poles as well as the sway of the transmission lines. A few individuals were concerned about maintaining the historic aesthetic of Coral Gables. The greater weight of the evidence offered with respect to quality of life impacts from the transmission lines did not support these concerns as expressed by the public. Aesthetic and economic impacts have been addressed, and the height and diameter of the transmission line poles was established as customary for FPL. FPL complies with local tree ordinances, including tree replacement planting where 270 appropriate. Landscaping and trees can help to minimize any aesthetic impacts. The final transmission line alignment will take into account approved and proposed development to be constructed in the area. The testimony established that while transmission lines in urban settings may involve aesthetic impacts, those aesthetic impacts from placing transmission lines such as within any of the eastern corridors would be minimal, and the transmission lines would be just one of many urbanized vertical elements in the landscape. Any aesthetic impacts from the proposed transmission lines would be no different in kind from those normally experienced every day in settings like those proposed for the transmission lines. Additionally, FPL is not required to comply with zoning ordinances relating to aesthetics because they are not applicable non-procedural requirements with which FPL is required to demonstrate compliance in the siting of transmission lines. 777. A few members of the public testified that they are concerned that the tree canopy and other landscaping will be negatively affected by the proposed transmission lines. FPL will comply with numerous conditions regarding NFCs and tree pruning/maintenance that will avoid adverse impacts on tree canopy. Additionally, FPL restores the landscaping in the ROW following construction in compliance with applicable regulations. 271 Members of the public expressed concerns about negative economic impacts that may be caused by the installation of transmission lines within their communities, including potential reductions in property values and the potential for a negative impact on the economic development of the areas surrounding the proposed FPL East Preferred Corridor. While the evidence was conflicting on this point, the more persuasive evidence demonstrated that the economic effects on the property values of residential or commercial properties adjacent to the transmission lines would be nominal. Several members of the public expressed concerns that the proposed transmission lines and associated poles are not in compliance with local codes and ordinances. A few members of the public expressed concerns about "humming" noises caused by the transmission lines. The transmission lines meet all applicable non-procedural requirements, including noise standards. Local zoning codes and LDRs are not applicable non- procedural requirements with which a transmission line is required to comply. Nevertheless, FPL has agreed to conditions of certification that incorporate, to the extent practicable, the desires and concerns of the local governments through which the transmission lines pass. Several members of the public expressed concerns that the proposed transmission lines will have negative impacts on 272 multi-modal transportation uses within FPL's East Preferred Corridor. On this issue, the evidence established that the construction, operation, and maintenance of the transmission lines in proximity to the Metrorail facility or the U.S. Highway 1 multi-modal corridor will not interfere with the operation of the Metrorail. Multi-modal uses will not be affected. A few members of the public expressed concerns about safety and health risks that they believe are associated with high-voltage transmission lines. The evidence established and the parties stipulated that the transmission lines will not have adverse effects on human health. In addition, the design and construction of the transmission line structures conforms to NESC requirements adopted by the PSC to protect public safety. No competent evidence was presented that proximity to transmission lines like the type proposed would cause adverse health effects. Also, there was no competent evidence of adverse health impacts associated with these lines. A few members of the public expressed concerns about interference that could be caused by the transmission lines, specifically referencing EMF and interference with radio communications. The evidence established that there will be no interference with radio or microwave communications. Some members of the public testified that they believe the proposed transmission lines should be or are 273 required to be placed underground. FPL is proposing underground construction only where an overhead design is not feasible; overhead design is feasible in all locations except when crossing the Miami River. 784. Several members of the public expressed concerns that some existing transmission lines are in poor condition and will never be improved if the FPL East Preferred Corridor is certified. The evidence established that FPL replaces inadequate or outdated transmission lines and poles on an as- needed basis; the certification of the East Preferred Corridor would not change this practice. 785. Several members of the public testified that they are concerned about allowing certification of transmission line corridors prior to the issuance of a license for the nuclear units by the NRC or a commitment to build the nuclear units by FPL. As discussed in the Conclusions of Law, the NRC proceeding need not be completed prior to the issuance of the site certification under the PPSA, including for the transmission lines. 786. Several members of the public expressed concerns about potential negative environmental and aesthetic impacts to Everglades National Park from the transmission lines. Several individuals were concerned about impacts to wading bird colonies. A few individuals expressed a concern about directing 274 freshwater away from the federal Everglades restoration program. A few other individuals expressed concerns about the proposed Land Exchange. FPL has minimized the impacts to the Everglades National Park by withdrawing its request to certify the West Secondary Corridor, which would have bisected the Everglades National Park. The evidence established that construction, operation, and maintenance of the transmission lines will not be inconsistent with Everglades restoration. Issues related to the Land Exchange involving the western corridors will be addressed by the United States Department of Interior. The evidence established that the transmission lines in the western corridors would not have adverse impacts to wading bird colonies. 787. Finally, one member of the public testified that traffic during construction within FPL's East Preferred Corridor is a concern. The evidence established that traffic impacts between both the East Preferred Corridor and the alternate corridor proposed by Coral Gables and Pinecrest are comparable, and these impacts only occur during the short time frame of construction.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Siting Board grant final certification to Florida Power & Light Company under chapter 403 for the location, construction, and operation of the Turkey Point Units 6 and 7 Project, representing a 2,200 MW nuclear generating facility, and including associated electrical transmission lines and other associated linear facilities, as described in the Site Certification Application and in the evidence presented at the certification hearing, and subject to the Conditions of Certification appended hereto. It is further RECOMMENDED that the Siting Board certify one of the corridors proper for certification for the eastern transmission lines and the western transmission lines. It is further RECOMMENDED that the Siting Board certify the following transmission line corridors pursuant to section 403.509: 326 East Preferred Corridor; West Consensus Corridor/MDLPA No. 2; and West Preferred Corridor as a back-up if an adequate right- of-way within the West Consensus Corridor/MDLPA No. 2 cannot be secured in a timely manner and at a reasonable cost. It is further RECOMMENDED that the Siting Board grant Florida Power & Light Company a variance from section 24-43.1(6), MDC, to allow use of the on-site package sanitary treatment plant and other on-site cooling water and wastewater treatment and disposal in lieu of connecting the Project to a public sanitary sewer line for treatment and disposal of these waters by the County. It is further RECOMMENDED that the Siting Board direct the Board of Trustees to grant to Florida Power & Light Company three separate easements over state-owned lands, including: (1) submerged lands owned by the State of Florida located within Biscayne Bay for the installation of the laterals associated with a radial collector well system to supply back-up cooling water; (2) submerged lands owned by the State of Florida located within the Miami River for the installation of a subaqueous 230- kV electrical transmission line; and (3) an approximate four- acre parcel of state-owned uplands along the western certified 327 corridor to allow the construction of a 230-kV electrical transmission line. DONE AND ENTERED this 5th day of December, 2013, in Tallahassee, Leon County, Florida. S D.R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of December, 2013. COPIES FURNISHED: Herschel T. Vinyard, Jr., Secretary Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Lea Crandall, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Matthew Z. Leopold, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 328 Toni L. Sturtevant, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Frederick L. Aschauer, Jr., Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Peter C. Cunningham, Esquire Hopping, Green & Sams, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526 Michael S. Tammaro, Esquire Florida Power & Light Company 700 Universe Boulevard, No. LAW/JB Juno Beach, Florida 33408-2657 Curtis Renner, Esquire Watson & Renner Suite 350 1400 16th Street, Northwest Washington, D.C. 20036-2227 Elizabeth M. Hernandez, Esquire Akerman Senterfitt One Southeast Third Avenue, 25th Floor Miami, Florida 33131-1700 William C. Garner, Esquire Nabors Giblin & Nickerson, P.A. Post Office Box 11008 Tallahassee, Florida 32302-3008 Victoria Mendez, Esquire City Attorney 444 Southwest 2nd Avenue, Suite 945 Miami, Florida 33130-1910 Dennis A. Kerbel, Esquire Miami-Dade County Attorney's Office 111 Northwest First Street, Suite 2810 Miami, Florida 33128-1930 329 Sara E. Fain, Esquire Everglades Law Center, Inc. Suite 246 1172 South Dixie Highway Miami, Florida 33146-2918 Richard J. Grosso, Esquire Shepard Broad Law Center Nova Southeastern University 3305 College Avenue Fort Lauderdale, Florida 33314-7721 Robert N. Hartsell, Esquire Robert N. Hartsell, P.A. Federal Tower 1600 South Federal Highway, Suite 921 Pompano Beach, Florida 33062-7520 Jason A. Totoiu, Esquire Everglades Law Center, Inc. Post Office Box 2693 Winter Haven, Florida 33883-2693 Francisco J. Pines, Esquire Francisco J. Pines, P.A. 3301 Ponce de Leon Boulevard Suite 220 Coral Gables, Florida 33134-7273 Patrick T. DiPietro, Esquire Patrick T. DiPietro Law LLC 8083 Northwest 66th Street Miami, Florida 33166-2729 Kerri L. Barsh, Esquire Greenberg Traurig, P.A. 333 Avenue of the Americas, Suite 4400 Miami, Florida 33131-2176 Ruth A. Holmes, Esquire South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33406-3007 Ronald S. Lieberman, Esquire 10625 Southwest 100th Street Miami, Florida 33176-2732 330 Michael Rosenberg, President Kendall Federation of Homeowner Associations, Inc. 12900 Southwest 84th Street Miami, Florida 33183-4320 Anthony J. Pinzino, Esquire Florida Fish & Wildlife Conservation Commission Farris Bryant Building 620 South Meridian Street Tallahassee, Florida 32399-1600 Francine T. Steelman, Esquire Miami-Dade Expressway Authority 3790 Northwest 21st Street Miami, Florida 33142-6812 Craig E. Leen, Esquire City Attorney City of Coral Gables 405 Biltmore Way Coral Gables, Florida 33134-5717 Jennifer Brubaker Crawford, Esquire Florida Public Service Commission 2450 Shumard Oak Boulevard Tallahassee, Florida 32399-0850 Kimberly C. Menchion, Esquire Department of Transportation Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0458 Michael D. Cirullo, Jr., Esquire Goren, Cherof, Doody & Ezrol, P.A. 3099 East Commercial Boulevard, Suite 200 Fort Lauderdale, Florida 33308-4311 Mitchell A. Bierman, Esquire Weiss, Serota, Helfman, Pastoriza, Cole & Boniske, P.L. 2525 Ponce de Leon Boulevard, Suite 700 Coral Gables, Florida 33134-6045 331 Thomas F. Pepe, Esquire Pepe & Nemire, P.A. 1450 Madruga Avenue, Suite 202 Coral Gables, Florida 33146-3163 John R. Herin, Jr., Esquire Gray Robinson, P.A. 401 East Las Olas Boulevard, Suite 1850 Fort Lauderdale, Florida 33301-4236 Jeff P. H. Cazeau, Esquire Kleiner & Cazeau, P.L. 901 Ponce de Leon Boulevard Penthouse Suite Coral Gables, Florida 33134-3061 Steven T. Williams, Esquire Monroe County Attorney's Office Post Office Box 1026 Key West, Florida 33041-0226 Sherry A. Spiers, Esquire Department of Economic Opportunity MSC 110 107 East Madison Street Tallahassee, Florida 32399-6545 Matthew J. Pearl, Esquire Weiss, Serota, Helfman, Pastoriza, Cole & Boniske, P.L. 200 East Broward Boulevard, Suite 1900 Fort Lauderdale, Florida 33301-1949 Michelle M. Niemeyer, Esquire Archer Bay, P.A. 25 West Flagler Street, Suite 1010 Miami, Florida 33130-1721

USC (2) 33 U.S.c 40842 U.S.C 2011 CFR (8) 14 CFR 7733 CFR 20833 CFR 38533 CFR 385.20(e)(2)33 CFR 385.26(c)40 CFR 144.39(a)40 CFR 144.40(a)40 CFR 144.41 Florida Laws (82) 10.15120.52120.57120.68120.69163.3164163.3194163.3209252.34253.02253.115258.397267.061334.03334.044335.182335.188337.401337.402337.403337.404361.01366.03366.04366.93373.016373.044373.085373.086373.089373.103373.113373.1391373.1501373.1502373.223373.229373.308373.309373.316373.413373.4135373.4136373.414373.416373.429373.4592373.603376.301379.2291379.2431380.04403.031403.061403.501403.502403.503403.504403.5064403.5065403.50665403.507403.508403.509403.510403.511403.5113403.5115403.514403.516403.519403.522403.526403.5271403.531403.531748.2048.217.017.02713.01872.02 Florida Administrative Code (30) 18-18.00418-18.00618-21.00325-6.034225-6.034528-106.21740E-2.09140E-20.30240E-3.10140E-4.09140E-4.30240E-6.01140E-6.04140E-6.22140E-6.31140E-6.35162-110.10662-17.13362-17.19162-17.21162-17.28162-17.66062-345.10062-345.40062-345.50062-345.90062-555.31062-672.87068A-16.00168A-16.002
# 1
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs BRUCE P. BOSTON, 06-003917 (2006)
Division of Administrative Hearings, Florida Filed:Gainesville, Florida Oct. 10, 2006 Number: 06-003917 Latest Update: Mar. 14, 2007

The Issue The primary issue for determination in this case is whether Respondent, Bruce P. Boston, engaged in the unlicensed practice of electrical contracting in the State of Florida without being certified or registered in violation of Chapter 489, Part II of the Florida Statutes; and secondarily, if Respondent committed that violation, what penalty should be imposed?

Findings Of Fact The Department of Business and Professional Regulation (Petitioner) is a state agency charged with the duty and responsibility of regulating the practice of electrical contracting in the State of Florida. Respondent's address is 18204 Southwest 200 Street, Archer, Florida 32618. At no time material hereto was Respondent certified or registered in the State of Florida to engage in the practice of electrical contracting or to perform electrical contracting work. Mrs. Dawn Wingert is the owner of the residence located at what is currently designated as 16675 Southwest 143rd Avenue, Archer, Florida. Mrs. Wingert, as lawful owner, had the authority to enter contracts regarding the residence. The Wingert residence was previously known as 110 Park Avenue, Archer, Florida, prior to the assignment of the current address. Wingert entered into a contract with Respondent to perform construction of a carport and perform electrical contracting work at Wingert’s residence subsequent to assignment of the address of 110 Park Avenue, Archer, Florida. Respondent received compensation for the contracted work directly from Wingert via personal check, which Respondent then cashed. Terry Vargas, a licensed electrical contractor having been issued license number ER 13012448, was subsequently contacted by Respondent to perform the electrical contracting work at the Wingert residence. Vargas installed an electrical outlet on the back porch, put a flood light on the back porch, moved the switch board to a more convenient location, and put a security light in the front of Wingert’s residence. All work required electrical fixtures to be permanently affixed and become a permanent part of the structure of the Wingert residence. Although Vargas completed the electrical contracting work at the Wingert residence, Wingert paid the Respondent for the services because the work was contracted for through Respondent. At no time pertinent to this matter did Terry Vargas contract with Wingert to complete the electrical services enumerated above. After he completed the work at Wingert’s residence, Vargas invoiced Respondent for the electrical contracting work. Respondent, however, refused to pay Vargas for the electrical contracting work performed, despite having received compensation for the work from Wingert.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that Petitioner enter a final order, in accordance with Section 489.533(2)(c), Florida Statutes, requiring that Respondent pay an administrative fine in the amount of $5,000.00 to the Department of Business and Professional Regulation. DONE AND ENTERED this 20th day of February, 2007, in Tallahassee, Leon County, Florida. S DON W. DAVIS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 2007. COPIES FURNISHED: Bruce P. Boston Post Office Box 331 Williston, Florida 32696 Drew F. Winters, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Nancy S. Terrel, Hearing Officer Office of the General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Josefina Tamayo, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (3) 489.505489.531489.533
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs SCOTT DELAFIELD AND CORAL ISLE POOLS AND SPAS, 07-004859 (2007)
Division of Administrative Hearings, Florida Filed:Dade City, Florida Oct. 24, 2007 Number: 07-004859 Latest Update: Apr. 03, 2008

The Issue The issue is whether Respondents committed the acts alleged in the Administrative Complaint, and if so, what discipline should be imposed.

Findings Of Fact Richard and Clara Marron have an in-ground, fiberglass pool at their home in Zephyrhills. The pool is approximately 25 years old. In December 2005, the Marrons' pool service company told them that the pool had a leak. The pool service company referred the Marrons to Coral Isle Pools and Spas (Coral Isle) in Zephyrhills. Coral Isle was owned and operated by Richard Delafield--the father of Respondent Scott Delafield--until his death on January 31, 2006. Richard Delafield was a registered building contractor, registered pool/spa contractor, registered plumbing contactor, and the qualifying agent for Coral Isle. On or about March 29, 2006, the Marrons went into Coral Isle's store and talked to Scott Delafield about fixing the leak in their pool.2 Mr. Delafield determined that the pool was leaking around the underwater light fixture and that the light needed to be replaced. He agreed to perform the necessary repairs for $858.55. The invoice prepared by Mr. Delafield described the work to be performed as follows: "dig under deck redue [sic] electrical conduit" and "labor to install light and do diagnostic on transformer." On May 6, 2006, the Marrons made an initial payment of $250.00 to Coral Isle. On May 15, 2006, Mr. Delafield performed the work on the Marrons' pool. Mr. Delafield did not obtain a permit from Pasco County before commencing the work on the Marrons' pool.3 The work was done in four stages. First, a trench was dug under the pool deck to provide access to the back of the light fixture. Second, the existing light was removed and replaced with a new light. Third, the wire for the new light was routed through PVC conduit pipe Mr. Delafield laid in the trench. Fourth, Mr. Delafield connected the wire to the "junction box"4 adjacent to the pool deck. The trench under the pool deck was dug by Carl Lind or Mark Pickett, not Mr. Delafield. Mr. Lind and Mr. Pickett were subcontractors of Coral Isle. Mr. Delafield removed the existing light by removing the screws on the front of the light fixture. He then installed the new light and ran the wire for the light through new PVC conduit pipe to the junction box. On May 17, 2006, the Marrons paid the balance of the invoice, $608.55. Mr. Delafield did not perform any work on the higher voltage electrical wires between the junction box and the breaker box at the house. Mr. Delafield did not drain the pool to replace the light. He was able to access the light fixture from the front because the water level in the pool was below the fixture as a result of the leak in the pool. At some point after Mr. Delafield completed his work on the pool light, Mr. Lind and/or Mr. Pickett drained the Marrons' pool in order to "patch" the fiberglass bottom of the pool.5 The light installed by Mr. Delafield works, and the pool no longer leaks. Indeed, the Marrons acknowledged in their testimony at the final hearing that the work done by Mr. Delafield fixed the leak and that the pool now "holds water." Mr. Delafield and Coral Isle were not licensed, registered, or certified to perform electrical contracting work at the time Mr. Delafield performed the work on the Marrons' pool light. In April 2006, the Department issued temporary emergency certifications to Mr. Delafield as a registered building contractor, registered pool/spa contractor, and registered plumbing contractor. The certifications authorized Mr. Delafield to complete Coral Isle's "projects in progress" at the time of Richard Delafield's death. The certifications did not authorize Mr. Delafield to enter into new contracts, nor did they authorize him to perform electrical contracting work. The Marrons' project was not in progress at the time of Richard Delafield's death. The agreement to perform the work was not entered into until several months after his death. In June 2006, the Marrons filed an unlicensed activity complaint against Mr. Delafield and Coral Isle. The Department incurred costs of $206.69 in its investigation of the complaint, not including costs associated with an attorney's time. In February 2007, the Marrons made a claim for $150,000 against Richard Delafield's estate in which they alleged that their pool and deck were "rendered useless" due to the negligence of Coral Isle. They also filed a civil suit against Mr. Delafield and others for damage to their pool. The Marrons did not pursue the claim against the estate, but the civil action is still pending. Coral Isle is no longer in business. Mr. Delafield testified that he planned to pursue licensure so that he could keep the business operating after his father's death, but that he never did so. Mr. Delafield was unemployed at the time of the final hearing.

Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department issue a final order that: Finds Mr. Delafield guilty of unlicensed electrical contracting in violation of Sections 455.228 and 489.531, Florida Statutes; Imposes an administrative fine of $1,000 on Mr. Delafield; and Requires Mr. Delafield to pay the Department's investigative costs of $206.69. DONE AND ENTERED this 25th day of February, 2008, in Tallahassee, Leon County, Florida. S T. KENT WETHERELL, II Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of February, 2008.

Florida Laws (10) 120.569120.57455.2273455.228475.25489.13489.501489.503489.505489.531
# 3
STANLEY SARENTINO, JR. vs DEPARTMENT OF AGRICULTURE AND CONSUMER SERVICES, 01-001920 (2001)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida May 17, 2001 Number: 01-001920 Latest Update: Nov. 06, 2001

The Issue The issue for determination is whether Respondent should grant Petitioner's application for a commercial telephone seller's license.

Findings Of Fact Petitioner, Stanley Sarentino, Jr. (Sarentino) is the owner and president of the The A/C Guy, Inc. (The A/C Guy) an air-conditioning service business based in Pompano Beach, Florida. The A/C Guy was incorporated in 1996, and serves residential and business customers in Broward and Palm Beach Counties. Respondent Department of Agriculture and Consumer Services (the Department) is the state agency charged with the enforcement of state regulation of telemarketing businesses in accordance with the provisions of the Florida Telemarketing Act, Chapter 501, Part IV, Florida Statutes (2000) (the Telemarketing Act). Sarentino has worked in the air-conditioning business in South Florida for over ten years. Both as an employee of other companies and since he formed The A/C Guy, Sarentino works exclusively as an air-conditioning mechanic. Sarentino has no expertise in, and has never been involved with, the daily running of the business, nor in the marketing of services, at the A/C Guy. Neither has Sarentino worked in the business side of any of the prior companies in which he was employed. Sarentino is assisted in managing The A/C Guy by his wife of 10 years. The Sarentinos have three children, and the family is well regarded in the community. Prior to the marriage, Sarentino's life was less exemplary. In 1991, Sarentino was charged with felony transportation of stolen stock certificates. Close in time to the stock charges, Sarentino was charged with unlawfully purchasing cocaine. Both incidents were disposed of by plea agreements which spared Sarentino a jail sentence. Since then, Sarentino has devoted himself to “turning his life around” by attending church, providing for his growing family, and otherwise occupying himself with lawful pursuits. Recently, Sarentino has made efforts to grow his small business. Those efforts included hiring John Frank Aiello, Jr. (Aiello) as full-time General Manager of The A/C Guy in the spring of 2001. Sarentino and Aiello came to believe that The A/C Guy had grown about as much as it could via word of mouth and print media advertising. They desired to expand the customer base for the business through telemarketing. Under the provisions of the Telemarketing Act, individuals who wish to have their business engage in telemarketing are required to be licensed (the Department). Aiello prepared a telemarketing license application for Sarentino in accordance with the instructions contained in the application package provided by the Department. Before commencing to prepare the application, Sarentino and Aiello carefully reviewed the licensing criteria. They paid special attention to the requirement that any criminal background be disclosed, and acted in good faith to disclose Sarentino’s history with as much precision as Sarentino’s 10-year-old memory would allow. The Department’s independent investigation corroborated that Sarentino had truthfully provided all requested information. Since his successful completion of probation for the decade-old incidents revealed on his telemarketing application, Sarentino has been a law abiding citizen. All applications for a telemarketer's license must be accompanied by a non-refundable $1500 processing fee. Applicants must also provide proof that they have paid the premium and have otherwise fulfilled the requirements to obtain a $50,000 bond from a private bonding company. The bond premium in this case was $1000.00. It is also necessary for applicants to provide extensive information about the business in whose name telemarketing will be conducted, along with information about individuals affiliated with the business, so that the Department may investigate their backgrounds for the public’s protection. Sarentino spent in excess of $350.00 in accounting fees for the preparation of financial statements required for the application. Prior to investing the time and incurring the expense associated with the application process, both of which are considerable, Sarentino carefully considered the question of whether he had a realistic chance to obtain a license. At the time he submitted his application, Sarentino reasonably believed, based upon the information provided by the Department itself, that his application would not be automatically rejected on account of his decade-old legal difficulties. After Sarentino’s application was submitted, Aiello, in his capacity as The A/G Guy general manager, had telephone conversations with the Department’s Regulatory Consultant Tom Kenny (Kenny) to follow-up on the status of the application. During the course of such conversations, Kenny revealed that the plea to the stock charge as well as the plea to the cocaine charge---each, by itself---would trigger the denial of the license application once the Department had independently confirmed that Sarentino had indeed truthfully disclosed the pleas. The evidence established and the Department conceded that there is an informal, unwritten practice enforced by Kenny's supervisor, James R. Kelly (Kelly), the Department’s Director of the Division of Consumer Services, that a plea of guilty to a felony charge, no matter what the felony, no matter how remote in time, no matter whether the applicant was rehabilitated or not will automatically result in the denial of a license application. The Department has no written rules, policies, or guidelines to which a citizen may refer in order to be apprised that the applications of individuals like Sarentino, and those similarly situated, are, in fact, dead on arrival. The Department's interpretation of the law is directly contrary to the discretionary language of the statute, which plainly does not foreclose all possibility that mitigating factors would be taken into account by Department officials in evaluating an applicant's criminal history. Sarentino has fulfilled all the statutory criteria for licensure. The Department would have granted the license were it not for its unwritten policy that the statute requires that any plea to a criminal charge mandates automatic denial.

Recommendation Based on the foregoing, it is hereby recommended that a Final Order be entered by the Department granting a commercial telephone seller's license to Stanley Sarentino, Jr. DONE AND ENTERED this 28th day of September, 2001, in Tallahassee, Leon County, Florida. FLORENCE SNYDER RIVAS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of September, 2001. COPIES FURNISHED: James Curran, Esquire 633 Southeast Third Avenue Suite 201 Fort Lauderdale, Florida 33301 William N. Graham, Esquire Department of Agriculture and Consumer Services Mayo Building, Room 515 407 South Calhoun Street Tallahassee, Florida 32399-0800 Brenda D. Hyatt, Bureau Chief Bureau of License and Bond Department of Agriculture and Consumer Services 541 East Tennessee Street India Building Tallahassee, Florida 32308 Honorable Terry L. Rhodes Commissioner of Agriculture Department of Agriculture and Consumer Services The Capitol, Plaza Level 10 Tallahassee, Florida 32399-0810 Richard Tritschler, General Counsel Department of Agriculture and Consumer Services The Capitol, Plaza Level 10 Tallahassee, Florida 32399-0810

Florida Laws (2) 120.57501.612
# 4
IN RE: FLORIDA POWER & LIGHT MANATEE UNIT 3 POWER PLANT SITING APPLICATION NO. PA 02-44 vs *, 02-000937EPP (2002)
Division of Administrative Hearings, Florida Filed:Parrish, Florida Mar. 01, 2002 Number: 02-000937EPP Latest Update: Feb. 19, 2003

The Issue The issue to be resolved in this proceeding is whether the Governor and Cabinet, sitting as the Siting Board, should issue certification to Florida Power & Light Company ("FPL") to construct and operate a new 1,100 megawatt (MW) combined-cycle electrical generating unit to be located at FPL's existing Manatee Plant site in Manatee County, Florida, in accordance with the Florida Electrical Power Plant Siting Act, Section 403.501, et seq., Florida Statutes.

Findings Of Fact Background Florida Power & Light Company is the largest electric utility in Florida, currently serving approximately seven million customers in its 34-county service area. That service area extends south from the northern Florida border along the east coast of the State, and includes all of the southern portion of the Florida peninsula up to and including Manatee County. FPL currently operates 34 generating units at 14 locations in Florida, including FPL's Manatee Plant. FPL has been supplying electricity in Florida for over 75 years. FPL’s Manatee Plant is located in the north central portion of Manatee County, Florida, approximately five miles east of the community of Parrish, Florida. The Manatee Plant is located in the unincorporated area of Manatee County. Access is by State Road 62, which runs east/west at the southern edge of the Plant site. S.R. 62 connects with U.S. 301 west of the Plant site in Parrish, Florida. The FPL Manatee Plant site contains approximately 9,500 acres. The existing FPL Manatee Plant includes two 800-megawatt steam-electric generating units known as Units 1 and 2. FPL applied for permits for Manatee Units 1 and 2 in June of 1972. Units 1 and 2 began commercial operation in 1976 and 1977, respectively. The Florida DEP issued a "Title V" air operation permit (No. 0810016-001-AV) for the Manatee Plant on May 29, 1998, pursuant to Chapter 403, Florida Statutes, and Rules 62-4, 62-210, 62-213 and 62-214, Florida Administrative Code. The Title V permit authorizes Units 1 and 2 to operate up to 8,760 hours per year, subject to comprehensive and detailed conditions pertaining to their air emissions, including but not limited to: emission limitations and standards; testing, monitoring, reporting, and record-keeping requirements; information on permitted fuels; and description of the two emission units and their maximum heat input rates. Existing Units 1 and 2 will remain in operation and will not be affected by the Project. The Manatee Plant site contains a 4,000 acre cooling pond, which provides cooling water to the two existing steam electric generating units at the site. Makeup water for the cooling pond is withdrawn from the Little Manatee River, pursuant to diversion schedules established under a Permit Agreement between FPL and SWFWMD, entered into in April 1973. Withdrawals from the Little Manatee River have occurred for over 25 years. Other facilities on the site include oil storage facilities, wastewater treatment facilities, an onsite system substation and transmission lines, construction and maintenance warehouses, and administration and ancillary facilities. The balance of the Manatee site is undeveloped or utilized for agricultural operations such as citrus groves, row crops, and cattle. Surrounding land uses are agricultural or undeveloped, with scattered residential development to the north and west of the Plant site. The nearest residence is approximately one-half mile away from the proposed Manatee Unit 3 site, within an outparcel contained within the larger FPL Manatee Plant site. Project Overview Manatee Unit 3 will consist of a natural gas-fired combined cycle power plant capable of generating 1100 MW (nominal) of electricity. Manatee Unit 3 will be located entirely within the existing boundaries of the FPL Manatee Plant site. Manatee Unit 3 will be located west of existing Units 1 and 2 in the Project Area comprising approximately 73 acres. The Unit 3 power block will be located in an area that has already been affected by existing uses at the Manatee Plant. Unit 3 will require approximately 26 acres for permanent facilities. The balance of the Project Area contains construction activities, existing warehouses, and stormwater facilities. The portion of the Manatee Plant site on which Unit 3 is proposed to be located, and for which FPL has sought site certification in this proceeding, does not include the existing Manatee Units 1 and 2. Neither FPL, nor any agency party, has invoked, or sought to invoke, the jurisdiction of the PPSA with respect to Manatee Units 1 and 2 or the air emissions from those existing generating units. All parties stipulated that Units 1 and 2 are not at issue in this proceeding. FPL undertook a community outreach program in connection with Manatee Unit 3. This effort included one-on-one discussions, group meetings and presentations, plant tours, and other opportunities. An open house was held at the Manatee Plant in May 2002. This ongoing communication program has contacted more than 1,800 people. FPL is continuing to update the community on the Project through presentations and mailings. Need for Manatee Unit 3 On December 10, 2002, the Florida Public Service Commission ("PSC") issued its Final Order determining the need for the FPL Manatee Unit 3 Project (as well as FPL's proposed Unit 8 at its Martin Plant). The PSC determined that FPL has a need for additional capacity to maintain the reliability of FPL's electrical system. FPL was found to have a need for Manatee Unit 3 taking into account the need for adequate electricity at a reasonable cost. The PSC found that FPL chose a proven technology and has the necessary experience in the construction and operation of combined cycle units. Further, the costs for both units were found to be reasonable. The PSC concluded there were no further energy conservation measures available to FPL that could offset the need for Manatee Unit 3. FPL was found to have implemented a considerable amount of cost effective energy conservation and demand side management. Based upon FPL's evaluation of other alternatives submitted in response to a request for proposals, the PSC found that Manatee Unit 3 and the separately-proposed Martin Unit 8, are the most cost effective alternative available to meet FPL's need for additional generating capacity beginning in 2005. The PSC concluded that FPL had met the statutory requirements under Section 403.519, Florida Statutes, for the determination of need for Manatee Unit 3. Project Schedule and Construction FPL expects to begin construction of Manatee Unit 3 in June 2003, or upon receiving final approvals for the Project. The new Unit is expected to be complete in June 2005, in order to meet FPL's customers' summer needs in that year. The simple cycle portions of Unit 3 are scheduled for completion beginning in August 2004, to allow operation in simple cycle mode while construction of the combined cycle unit is ongoing. Peak construction employment will be approximately 750 construction workers, management, and staff. Construction employment is expected to average about 275 workers. There will be no new construction of temporary or permanent roads that connect offsite as the existing plant entrance at S.R. 62 will be used for Project construction. Fugitive dust produced by traffic and excavation will be minimized through paving or the use of water sprinkling. Major pieces of equipment will be delivered by truck over existing road ways, or by rail over a rail line that already serves that site. The Unit 3 Project Area has been previously cleared for the existing units or will require minimal clearing. Impacts from creating material laydown areas will be minimal, temporary and mainly associated with grubbing and grading to create proper drainage. Soils will need to be excavated to provide support for the plant foundation and other facilities. Foundations for heavy loads will be supported by spread foundations or pilings. Subsurface excavations may require temporary dewatering by localized pumping of the shallow aquifer to lower the water table. The effluent from dewatering will be routed to the cooling pond. No offsite impacts to groundwater from dewatering activities are expected. The entire Project Area is outside the 100-year flood zone. Construction activities will alter runoff in parts of the site, but no adverse effects are expected from these activities. Construction period surface water runoff will be conveyed to stormwater ponds that can provide detention for all runoff from these areas. Impacts to offsite surface waters from construction- related runoff are expected to be negligible. Onsite construction activities will not cause adverse ecological effects as the Project Area is already highly altered, and maintained as either grassy or cultivated areas. These areas do not contain unique wildlife species and are not considered important wildlife habitats because of their disturbed nature. (No wetlands are located within the Project Area.) Construction noise will comply with the Manatee County Noise Control Ordinance. Construction noise will not affect wildlife in the vicinity of the site. The Manatee Plant site already has noise associated with operation of the existing facility and wildlife in the area is acclimated to such activities. Control measures will be implemented during construction to minimize fugitive air emissions and its potential impacts. Clearing will be kept to a minimum, thereby reducing air emissions from exposed surfaces. Watering will be used to control fugitive dust on highly traveled areas. During construction, portable chemical toilets and bottled water will be utilized. Solid and hazardous wastes generated during construction will be handled and disposed offsite by individual contractors. Project Description Manatee Unit 3 will consist of four advanced combustion turbines ("CT") and four heat recovery steam generators ("HRSG") in a configuration referred to as a "4-on-1" combined cycle unit. Each combustion turbine will generate approximately 170 MWs. The CTs operate much like a jet engine, in which air and fuel, in this case natural gas, are combined in the CT and then combusted. The heated gases then rotate a shaft that drives an electrical generator. The exhaust gases from the combustion turbines produce steam in the heat recovery steam generators, which is used in turn to drive a separate steam turbine generator. By utilizing the waste heat from the CTs, the resulting combined cycle unit will be more efficient than the simple cycle CTs and traditional steam-electrical units. Manatee Unit 3 will be among the most efficient electric generators in Florida. Duct burners are proposed for each HRSG and are fired during peak demand periods to achieve the total nominal generating capacity of Unit 3. The four CTs will be equipped with inlet air evaporative cooling which creates a more moisture-laden air stream in the CT, allowing additional power to be produced more efficiently. The CTs will also be capable of power augmentation, in which steam from the HRSG is injected into the CT during periods of peak electrical demand to increase electrical output. Each CT will be capable of operation in "peak" mode in which the firing temperature of the combustion turbine is increased, resulting in increased power. Exhaust gases from Unit 3 will be emitted from a stack associated with each HRSG unit. Each combustion turbine will also be capable of operating in simple cycle mode in which exhaust gases will be emitted either from a bypass stack associated with each CT or by the HRSG stack. Natural gas heaters will be used if the CTs are operated in simple cycle mode. The height of the four HRSG stacks will be a maximum of 150 feet. Cooling water for the Manatee Unit 3 will be provided by the existing cooling pond. Wastewaters and stormwater from the power block will be treated onsite and recycled to the cooling pond. Other onsite facilities to be constructed as part of the Project will include interconnections with the existing onsite transmission facilities, along with storage facilities for ammonia, hydrogen, demineralized water, and condensate water. Manatee Unit 3 will connect to the existing onsite electrical system substation via a new tie line. That substation will be expanded to accommodate the interconnection to FPL’s existing electric transmission system. No new offsite transmission lines are required. The Unit 3 project will utilize a number of other existing facilities at the Manatee Plant site. Natural gas will be the only fuel used in the Manatee Unit 3. Gas will be delivered to the Plant by pipeline. The Manatee Plant site is already served by an existing natural gas pipeline that may supply gas to the Unit 3, or another gas pipeline may be installed and would be independently permitted and constructed. Natural gas will not be stored onsite. Manatee Unit 3 will generate only small quantities of solid wastes. These will be limited to municipal solid wastes and infrequent replacement of inlet air filters. The catalyst in the selective catalytic reduction (SCR) system will be replaced periodically and disposed of in accordance with applicable requirements. Hazardous wastes will be produced in limited quantities. These will be collected and disposed of offsite by a licensed hazardous waste contractor. Air Emissions Air emissions from Manatee Unit 3 will result from both the combustion process and impurities in the fuel itself. Nitrogen oxides are formed through the oxidation of a portion of the nitrogen that is naturally found in natural gas. Additional nitrogen oxides are formed through the oxidation of the nitrogen contained in the combustion air. Carbon monoxide and volatile organic compounds are formed by incomplete combustion of fuel. Sulfur dioxide and particulate matter emission rates are dictated by the amount of sulfur in the fuel. Under state and federal Prevention of Significant Deterioration ("PSD") review requirements, all major new or modified sources of regulated air pollutants that are located in areas attaining compliance with ambient air quality standards must be reviewed. Manatee Unit 3 is considered a major modification to the existing Manatee Plant site because the Project's emissions will exceed the significant emission increase thresholds for several regulated air pollutants. Based on expected emissions from Unit 3, PSD review was required for: particulate matter ("PM"), sulfur dioxide ("SO2"), nitrogen oxides ("NOx"), carbon monoxide ("CO"), volatile organic compounds ("VOC") and sulfuric acid mist. PSD review is used to ensure that significant air quality deterioration will not result from new facilities like Unit 3. These analyses include a review of the proposed emissions control technology, a source impact analysis, an air quality impact analysis, source information, and additional air quality impact analyses. Air Emissions Control Technology Air emissions from Manatee Unit 3 will be minimized through the inherent efficiency of the combined cycle design, and the use of: natural gas as the exclusive fuel, advanced combustion control technology, and post-combustion control technology. Natural gas, the cleanest of fossil fuels, has very low levels of impurities and can be burned very efficiently. The use of dry low NOx combustion design in the CTs, and low NOx burners in the duct burners, will also minimize air emissions by inhibiting formation of thermal NOx by premixing of fuel and air prior to combustion, and by reducing flame temperatures. Selective Catalytic Reduction ("SCR") will provide additional control of emissions of NOx from Unit 3 when operating in combined cycle mode. In the SCR system, located in the HRSGs, ammonia is injected into the CT exhaust where NOx in the gas stream reacts with the ammonia in the presence of a catalyst to form nitrogen and water. State and federal PSD regulations require that Manatee Unit 3 meet all applicable emission limiting standards and that Best Available Control Technology ("BACT") be applied in order to control emissions. BACT is defined in Chapter 62- 210.200(38), Florida Administrative Code, as: An emission limitation, including a visible emissions standard, based on the maximum degree of reduction of each pollutant emitted which the Department [of Environmental Protection], on a case by case basis, taking into account energy, environmental and economic impacts, and other costs, determines is achievable through application of production processes and available methods, systems and techniques (including fuel cleaning or treatment or innovative fuel combustion techniques) for control of each such pollutant. The BACT requirements are intended to insure that the air emission control systems for Unit 3 reflect the latest in control technologies used in the electric utility industry and take into consideration existing and future air quality in the vicinity of the Project. BACT review includes a cost-benefit analysis of alternative control technologies capable of achieving a higher degree of emission reduction than the proposed technology. FDEP's determination on what constitutes BACT for Manatee Unit 3 is to be based on a balancing of environmental benefits with environmental, energy, and economic impacts and other costs. In its PSD review, the Department preliminarily determined that the air emissions control technologies proposed for Manatee Unit 3 are consistent with BACT as required under federal and state PSD regulations. The exclusive use of natural gas, combined with advanced combustion control technology, will provide the maximum degree of emission reduction for sulfur dioxide, particulate matter, volatile organic compounds, carbon monoxide and sulfuric acid mist. The dry low NOx control technology for the CT combustors and the duct burners, along with SCR, reflect the latest available control technologies for reducing NOx emissions from combined cycle systems. The emission limits for Manatee Unit 3 in the Department's recommended Conditions of Certification are identical to the emission limits proposed as BACT by the Department. The recommended NOx emission limit of 2.5 parts per million for combined cycle operation is equal to or lower than BACT determinations for other combined cycle units in the State of Florida, and is lower than any project previously certified by the Siting Board under the PPSA. Air Quality Impact Analysis Ambient air quality standards have been established by the U.S. EPA and FDEP to protect public health and welfare. Air quality in the vicinity of the Manatee Plant, and in the Tampa Bay area, currently meets all federal and state ambient air quality standards. Manatee County is classified as an "attainment" area for all criteria pollutants. Air quality modeling demonstrates that Manatee Unit 3 will comply with all state and federal ambient air quality standards, as well as PSD Class I and II increments. The air quality modeling conducted for the Project followed EPA and FDEP modeling guidelines. Two air quality models were utilized to assess air quality impacts in the area surrounding the Manatee Plant site. The modeling also assessed impacts in the nearest PSD Class I area, which is the Chassahowitzka National Wilderness Area (NWA), located approximately 72 miles to the north-northwest from the Project site. Local meteorological data from the National Weather Service was used in the modeling. The modeling incorporated maximum air emissions from the Unit 3 under both combined and simple cycle configurations and at various operating modes, loads, and ambient air temperatures, which may affect the emission rates from the Unit. The air quality modeling results indicated the maximum air impacts from the Project will comply with all ambient air quality standards and PSD Class I and II increments. EPA has established "Significant Impact Levels" for the various pollutants that are subject to PSD review, and the Department has adopted these Significant Impact Levels at Rule 62-204.200(29), Florida Administrative Code. The comparison of a project's air quality impacts with the Significant Impact Levels represents an initial screening analysis to determine which pollutants require a more detailed modeling analysis. Impacts of the emissions of all air pollutants from Unit 3 would be below the PSD Class I and Class II Significant Impact Levels, except for coarse particulate matter (PM10) over the 24-hour averaging period in the Class II areas. Accordingly, air impacts from Unit 3 are considered insignificant based upon this screening analysis for all pollutants except for PM10 over the 24-hour averaging period. More refined modeling was conducted for PM10 over the 24-hour averaging period. This modeling demonstrated that PM10 emissions from Unit 3, when considered along with other existing sources, would be well below each of the relevant air quality standards. Nitrogen oxides and volatile organic compounds are precursors to the formation of ozone in the atmosphere. The emission of these air pollutants from Manatee Unit 3 will not interfere with the ongoing compliance with the ambient air quality standard for ozone in the Tampa Bay region, and will not interfere with the area-wide strategy for reducing ozone concentrations. There are expected to be no air quality impacts due to associated industrial, commercial, or residential growth due to the Project or its location. There should also be no adverse impacts to the "Air Quality Related Values," including visibility, soils, vegetation, or wildlife, in the closest PSD Class I area at the Chassahowitzka NWA. Unit 3's potential impacts on regional haze in this Class I area were below the screening level. Water Uses and Sources Water uses for Manatee Unit 3 will include circulating water for the condensers and other cooling, demineralized water for use in the power generation process, and general service water for washdowns and other uses. The existing cooling pond, with makeup water provided from the Little Manatee River, will be the source of cooling, service, and process water for Unit 3, as it is currently the source of water for the existing Manatee Plant. Potable water will be supplied from an existing permitted onsite potable well. The existing cooling pond is man-made and has earthen embankments. The 4,000-acre pond has a gross storage volume of approximately 52,000 acre-feet of water. The pond contains two splitter dikes to prevent short circuiting in the circulating water, thereby enhancing the cooling pond's heat dissipation efficiency. A spillway is located on the northern embankment of the cooling pond and is designed to safeguard against overtopping of the embankment. The only planned releases from the cooling pond are annual testing of the spillway gates. Seepage from the cooling pond through the embankments is captured in a system of toe drains around the perimeter of the pond. The seepage is collected in sumps and returned to the cooling pond. An average of approximately three million gallons per day of seepage is returned to the cooling pond. The Unit 3 circulating water system may require the construction of new inlet and outfall structures within the cooling pond and installation of circulating water pumps and underground piping to move water to and from the new Unit 3. The existing inlet structure may be utilized and a new diffuser pipe may be installed as part of the circulating water system, which would eliminate the need to construct new facilities in the pond dike. The existing weir at the Little Manatee River intake will be upgraded to ensure minimum river flows are maintained. No other changes are needed to the cooling pond or the existing cooling water systems for Units 1 and 2 or to the cooling pond makeup system. An existing Permit Agreement between FPL and the Southwest Florida Water Management District, originally entered into in 1973, allows sufficient makeup water for the operation of the Manatee Plant cooling pond even with the addition of Unit Under the existing agreement, withdrawals may not exceed 190 cubic feet per second ("cfs") and are not allowed to lower river flow below 40 cfs. The existing agreement would allow FPL, under certain flows in the Little Manatee River, to withdraw up to 47 percent of the river flow. After Unit 3 begins operation, makeup water for the cooling pond will continue to be withdrawn from the Little Manatee River. FPL has proposed, and SWFWMD has recommended, a more restrictive schedule for diversions from the Little Manatee River beginning in October 2004. With the proposed diversion schedule, withdrawals will reduce the rate of river flow by no more than 10 percent. During emergency conditions, when the level of the cooling pond falls below 62 feet above mean sea level ("msl"), FPL will be allowed to revert to the existing diversion schedule for October through July, under the current Permit Agreement until the cooling pond reaches 63 feet msl. Under either schedule, diversions will neither reduce the river flow below 40 cfs nor exceed 190 cfs. A modeling analysis of the revised schedule indicates that the average monthly diversion or withdrawal for all three units from the Little Manatee River is estimated to be about 8.9 million gallons per day ("mgd") when Unit 3 becomes operational. Flow in the Little Manatee River averages 114 mgd near the FPL Manatee Plant. The modeling analysis showed that only three events in a 24-year period would qualify as "emergencies" in which the current diversion schedule would have been used. Under this analysis, withdrawals under the proposed diversion schedule would have exceeded 10 percent of the river flow only three percent of the time. Historical withdrawals for the FPL Manatee Plant have exceeded 10 percent of the river flow 18.5 percent of the time. The Little Manatee River is approximately 40 miles long from its origins to its mouth at Tampa Bay. The FPL Manatee Plant is about 18.5 miles above the mouth of the river. From its mouth up to about river mile 12, the vegetation in this part of the river is mangroves, salt marsh, and tidal marsh. At river mile 12 and above, the river is generally freshwater with freshwater bottom land stream swamp vegetation. Water flows and levels exhibit significant variability, with flows ranging between a low of four cubic feet per second and a high of 10,000 cubic feet per second at a location 3.5 miles downstream from the FPL Manatee Plant. At that location, water levels can vary between two feet and 12 feet above mean sea level. Withdrawals from the Little Manatee River have the effect of reducing flow in the river, which could affect water levels along the river, as well as the location of the saltwater interface in the river itself. The saltwater interface represents the point at which fresh and saltwater meet, and it may move up and down the river due to river flow and tidal forces. There has been no adverse effect on the ecology of the Little Manatee River or its estuary from the historical withdrawals for the FPL Manatee Plant. An evaluation of the hydrologic and ecological effects of the projected withdrawals under the revised diversion schedule indicate that the withdrawals after Manatee Unit 3 commences operation should not result in adverse impacts to the Little Manatee River. Hydrologic analyses indicate that the effects of withdrawals under the proposed diversion schedule on water levels, water flows, and salinity in the Little Manatee River will all be within the natural variability of the river and similar to the effects of the historical withdrawals for the Manatee Plant. No significant adverse effects on the ecological features of the Little Manatee River will result from the withdrawals under the new diversion schedule. Flora and fauna in the river are well adapted to fluctuating water levels and salinity. The new diversion schedule will more closely mimic natural rainfall patterns and the 40 cfs cutoff for diversions will protect critical low flow periods in the river. The new diversion schedule with Manatee Unit 3 will be more environmentally sensitive than the existing diversion schedule. These diversions will occur in a manner that better mimics the natural fluctuations in daily river flow by allowing more water to be diverted during high flow periods when the ecology of the river and its estuary is less sensitive to withdrawals. FPL has provided reasonable assurances that the proposed withdrawals after Unit 3 commences operation will have no adverse effects on the Little Manatee River and its estuary. SWFWMD has proposed that FPL undertake a hydrobiological monitoring program of the River. This program will map and monitor vegetation in the river and collect data on salinity and tides in the river. The monitoring program will require regular reports to SWFWMD on the effects of FPL’s withdrawals on the ecology of the Little Manatee River and its estuary. Surface Water Discharges from the Cooling Pond A mathematical model was also conducted of the thermal performance of the cooling pond to predict water quality in the pond over a 24-year period, based on historical weather data and expected plant water withdrawals. The model was used to estimate the dissolved solids level in the cooling pond so that water quality in the pond could be predicted for the future. The pond modeling indicates that water quality in the pond will not exceed surface water quality standards that apply to discharges from the pond. Currently, the only discharges from the pond occur during high-water controlled discharges during extreme rainfall events that exceed the 100-year, 24-hour storm, and during annual gate tests that are conducted to ensure reliability of the gates. When Unit 3 becomes operational, excess rainfall releases from the pond will become less frequent. The pond water level will be managed to provide sufficient storage to retain all direct rainfall and surface water runoff to the pond from a 100-year, 24-hour storm. The cooling pond modeling showed that, with Unit 3 operating, no high water discharges would have occurred over a modeled 24-year period. FPL will continue to analyze the pond water quality as required under an existing FDEP wastewater permit prior to any releases during gate tests. If the analysis shows water quality of a discharge would exceed applicable Class III surface water criteria, then the water in the stilling basin below the discharge gates is also analyzed for water quality criteria. If the combined discharge would violate Class III water quality standards, the gate test will not be performed. Plant Water and Wastewater Treatment The design and operation of Manatee Unit 3 will include a number of water conserving technologies or systems. The use of combined cycle generating technology reduces water use by 60 percent over the water use in a comparable traditional steam generating unit. Unit 3 will utilize only natural gas and thus will not require water to control air emissions of nitrogen oxides. Wastewaters and stormwater from the power block will be collected and recycled to the cooling pond. Process water for use in the plant will be treated in an existing permitted reverse osmosis ("RO") demineralizer system. Demineralized water is required to replace water lost in the steam cycle and to maintain water quality in the heat recovery steam generators, as well as for use in power augmentation and in inlet air fogging systems on the combustion turbines. Raw water will be taken from the Manatee Plant cooling pond for these purposes. The reject water from the RO system will be recycled to the cooling pond. The plant will also require general service water that will be provided by the service water system. The existing permitted domestic wastewater treatment system will handle any additional flows generated by Manatee Unit 3 and no new treatment facilities are planned. The proposed Manatee Unit 3 will utilize the existing Manatee Plant's process water treatment system and associated wastewater treatment systems. The only new wastewaters generated by Unit 3 will be blowdown required to maintain water quality in the HRSGs and equipment wash waters and stormwater from the power block. These wastewaters will be treated in the existing wastewater treatment systems, as necessary, and then recycled to the cooling pond. The cooling system for Manatee Unit 3 requires chlorination or use of biocides to prevent biofouling of the heat rejection system. The water in the steam cycle of the HRSG will be treated to prevent corrosion and scaling of the piping and boiler drums. The HRSG and its piping must also be chemically cleaned initially and then periodically during the life of the Plant. The chemicals required for this process will be delivered to the site by a contractor at the time of the scheduled cleanings. Chemical wastewaters resulting from drainage at chemical storage tanks or cleaning and maintenance operations will be contained and routed to the existing neutralization system for treatment or disposed offsite. Surface Water Management System The onsite drainage facilities for Manatee Unit 3 are to be constructed in accordance with applicable federal, state, regional, and local regulations for control of both stormwater quality and stormwater quantity. The new stormwater systems for Unit 3 will be designed to handle the rainfall from a 25-year, 24-hour storm. Runoff that does not contact industrial areas will be collected and routed to new detention ponds located in the western and southern portions of the Project Area or routed directly to the cooling pond. Stormwater in the CT/HRSG, switchyard, and the plant maintenance areas will be collected, treated for oil separation as needed, and recycled to the cooling pond. The perimeter roads surrounding the CT/HRSG area will contain the runoff from a 100-year, 24-hour storm. Drainage patterns at the existing units will be separated from the new Unit 3 areas. During construction, runoff will be routed to the stormwater ponds to prevent sediment transmission offsite and will be used while final construction of the Project stormwater system is completed. Temporary silt fences will be installed to prevent sediment from being displaced and carried offsite by construction runoff. Groundwater Impacts The only groundwater withdrawal associated with Manatee Unit 3 will be the withdrawal of approximately 1,000 gallons per day of additional groundwater for potable use. This would increase total potable groundwater withdrawals to 8,000 gallons per day. This is within the permitted withdrawal rates under the existing Manatee Plant's consumptive use permit for potable water. Thus, it is anticipated there will be no adverse impacts on groundwater supplies as a result of groundwater withdrawals for Unit 3. Groundwater will not be used in the cooling or other processes for the Project. The existing Manatee Plant cooling pond is the principal source of potential impacts to groundwater at the Plant. Because the cooling pond is generally above the surficial aquifer, seepage from the cooling pond may move laterally through the earthen embankments and vertically into the groundwater beneath the cooling pond. The cooling pond is surrounded by a toe drain system and sumps that are designed to collect horizontal seepage from the cooling pond. This system captures most, if not all, of the seepage and recycles it to the cooling pond, thereby minimizing potential groundwater quality impacts to the surficial aquifer. The Manatee Plant cooling pond was in existence in July 1982 and therefore it is an existing installation for purposes of groundwater discharges under Rule 62-522.200, Florida Administrative Code. Groundwater discharges from the cooling pond are required to meet the state's primary drinking water standards at the boundary of an existing zone of discharge. The groundwater zone of discharge extends to FPL's property boundaries and to the base of the surficial aquifer below the Manatee Plant site. An analysis of the groundwater discharges from the cooling pond indicates that the cooling pond discharges will comply with applicable groundwater standards at the edge of the existing zone of discharge. Noise Impacts of Construction and Operation A noise impact assessment was conducted for the Project, both during construction and operation. Baseline or ambient noise data was collected using sound monitoring equipment at five different locations within and near the Project Area. Using the ambient noise data and expected project noise levels for construction and operation, a noise impact evaluation was performed using an accepted noise propagation computer program. This assessment demonstrated that the construction and operation of Manatee Unit 3 will comply with the Manatee County Noise Ordinance. Socioeconomic Impacts and Benefits The Project Area is an appropriate site for the proposed new Unit 3. The Project consists of the installation of a new combined cycle unit at an existing power plant site that has been in use for that purpose since 1976. Surrounding properties are zoned for agricultural use and residential properties are some distance from Unit 3. The closest residential area is approximately two miles from the Unit 3 Project Area. The Project will also comply with the noise standards of Manatee County. The Manatee Unit 3 Project will benefit the economies of Manatee County and surrounding communities. Direct benefits will include employment opportunities during construction and operation of the Project. It is expected that most of the construction employees will be drawn from the Tampa Bay area and commute daily to the job site. Employment opportunities will result from construction job opportunities, as well as jobs indirectly generated through the purchase of goods and services in the area. Construction employment will average 275 jobs over a 24-month period with an estimated payroll of $95 million. In addition, approximately $20 to $25 million is expected to be spent within the state for materials and equipment during construction. Construction spending will have a multiplier effect in the economy, producing indirect jobs in sectors that support the construction industry. The number of indirect jobs expected to be created will average 175 jobs over the 24-month period. The principal impact from construction of Unit 3 will be short-term traffic impacts due to construction employees, equipment, and materials entering and leaving the site. A transportation analysis of the Project indicated that there could be undesirable delays at the existing Plant's driveway connection to S.R. 62 and at the intersection of S.R. 62 and U.S. 301 in Parrish, with the current stop signs that exist. Therefore, during peak construction periods, an off-duty officer would control the traffic at those intersections during those peak hours. This is the preferred means for traffic maintenance. Operation of Manatee Unit 3 will add approximately 12 new employees at the FPL Manatee Plant. Increases in employee traffic and deliveries to the Plant during operation will be de minimus compared to Manatee County's threshold for traffic impacts. No traffic improvements are needed for Unit 3's operation. Thus, the Project-related traffic during operation of Unit 3 will meet Manatee County's transportation concurrency standards. The additional annual payroll for these 12 new employees is estimated to be $600,000. The increased economic activity from this payroll is expected to generate an additional 18 indirect jobs in the local economy and generate about $310,000 in annual earnings, primarily in construction, retail trade, real estate, business service and health service. Estimated Manatee County property taxes from Unit 3 during operation are $8.2 million in 2006. Over the first five years of operation, tax payments to Manatee County and the State of Florida are expected to be $1 million in sales taxes and almost $38 million in property taxes. The power plant will require very little in the way of additional public services and thus, there should be little or no increase in demand for public services and facilities from Unit 3. Manatee Unit 3 will be consistent with the Manatee County Comprehensive Plan, the State Comprehensive Plan, and the Strategic Regional Policy Plan of the Tampa Bay Regional Planning Council. The Project will also comply with the applicable development standards in the Manatee County Land Development Code. Construction and operation of Manatee Unit 3 will not adversely affect any landmarks, sensitive areas, or archaeological or historical sites. The closest landmarks and sensitive areas within the five-mile radius of the Project will not experience any changes in air quality, noise level, water quality, or visual impacts. There will be no impacts to known archaeological resources. If archaeological materials are discovered, they will be evaluated by professional archaeologists and state historical preservation officials, if necessary. Public Comment Nine members of the public provided testimony during the certification hearing, and two exhibits were admitted as public comment. Several of the persons who provided public comment expressed concerns regarding the air emissions from Manatee Units 1 and 2. Several others expressed appreciation for the manner in which FPL has interacted with the community. No competent, substantial evidence that would alter the findings of fact set forth herein was received from members of the public at the certification hearing. Agency Positions and Stipulations The FDEP, the Florida Department of Community Affairs, the Florida Department of Transportation, the Florida Fish and Wildlife Conservation Commission, the Southwest Florida Water Management District, the Tampa Bay Regional Planning Council, and Manatee County each prepared written reports on the Project. Each of these agencies recommended approval of Manatee Unit 3, or otherwise did not object to certification of the proposed power plant. FDEP has proposed a series of Conditions of Certification for the Project that incorporate the recommendations of the various reviewing agencies. FPL states that it is prepared to accept and can comply with these Conditions of Certification in the design, construction, and operation of Manatee Unit 3. The Florida Department of Community Affairs stipulated that the Project would not conflict with the State Comprehensive Plan. The Tampa Bay Regional Planning Council stated in its agency report that the Project would not conflict with the Strategic Regional Policy Plan for Southwest Florida. Manatee County reported that the Project would be consistent with the County's comprehensive plan and land development code. No state, regional, or local agency has recommended denial of certification of the Project or has otherwise objected to certification of the Project.

Conclusions For Florida Power & Light Company: Peter C. Cunningham, Esquire Douglas S. Roberts, Esquire Hopping Green & Sams Post Office Box 6526 Tallahassee, Florida 32314 For the Department of Environmental Protection: Scott A. Goorland, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000 For the Southwest Florida Water Management District: Martha A. Moore, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899 For Manatee County: Jeffrey N. Steinsnyder, Esquire Jamie L. Althouse, Esquire Manatee County Attorney's Office Post Office Box 1000 Bradenton, Florida 34206-1000 For Tampa Bay Regional Planning Council: Roger Tucker, Esquire 9455 Koger Boulevard, Suite 219 St. Petersburg, Florida 33702-2491 For ManaSota-88, Inc.: Glenn Compton, Chairman 419 Rubens Drive Nokomis, Florida 34275

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Siting Board grant full and final certification to Florida Power & Light Company, under Section 403, Part II, Florida Statutes, for the location, construction, and operation of Manatee Unit 3, representing a 1,100 MW combined cycle unit, as described in the Site Certification Application and the evidence presented at the certification hearing, and subject to the Conditions of Certification contained in FDEP Exhibit 2 and as appended hereto. DONE AND ENTERED this 19th day of February, 2003, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 2003. COPIES FURNISHED: Ross Stafford Burnaman, Esquire James V. Antista, Esquire Fish and Wildlife Conservation Commission 620 South Meridian Street Tallahassee, Florida 32399-1600 Colin Roopnarine, Esquire Assistant General Counsel Department of Community Affairs 2555 Shumard Oak Boulevard Tallahassee, Florida 32399-2100 Roger Tucker, Esquire Tampa Bay Regional Planning Council 9455 Koger Boulevard, Suite 219 St. Petersburg, Florida 33702-2491 Jeffrey N. Steinsnyder, Esquire Manatee County Attorney's Office Post Office Box 1000 Bradenton, Florida 34206 Peter C. Cunningham, Esquire Douglas S. Roberts, Esquire Hopping Green & Sams Post Office Box 6526 Tallahassee, Florida 32314-6526 Sheauching Yu, Esquire Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450 Martha A. Moore, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899 Robert V. Elias, Esquire Martha Carter Brown, Esquire Florida Public Service Commission Gerald Gunter Building 2450 Shumard Oak Boulevard Tallahassee, Florida 32399-0850 Scott A. Goorland, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000 ManaSota-88, Inc. c/o Glenn Compton, Chairman 419 Rubens Drive Nokomis, Florida 34275 David B. Struhs, Secretary Department of Environmental Protection The Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard The Douglas Building, Mail Station 35 Tallahassee, Florida 32399-3000 Kathy C. Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Station 35 Tallahassee, Florida 32399-3000

# 5
FLORIDA POWER CORPORATION (TIGER BAY COGENERATION FACILITY) vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 97-004488EPP (1997)
Division of Administrative Hearings, Florida Filed:Fort Meade, Florida Sep. 26, 1997 Number: 97-004488EPP Latest Update: Jun. 26, 1998

The Issue The principal issue to be resolved in this proceeding concerns whether certification should be issued to Florida Power Corporation (FPC) for approval to operate a nominal 269 megawatt (MW) combined-cycle generating unit located at FPC's Tiger Bay Cogeneration Facility west of Ft. Meade, Florida, in accordance with the provisions of Section 403.501(2), Florida Statutes. The second issue to be resolved in this consolidated proceeding is whether the site of the Tiger Bay Cogeneration Facility is in compliance and consistent with the applicable land use plans and zoning ordinances of Polk County, pursuant to Section 403.508(2), Florida Statutes.

Findings Of Fact Florida Power Corporation is an investor-owned utility that provides electric service to more than 1.2 million customers in its Florida service area. Tiger Bay Limited Partnership completed the construction of the Tiger Bay Cogeneration Facility in late 1994. FPC entered into a power purchase agreement to purchase the power provided by the Tiger Bay Facility. On January 20, 1997, FPC agreed to purchase the Tiger Bay Facility from the Tiger Bay Limited Partnership. FPC now operates the Tiger Bay Plant as one of its electric generating facilities. The Tiger Bay Cogeneration Facility is an existing combined-cycle electrical generating plant which has been in operation since January 1995. The Facility consists of a combustion turbine (CT) and a steam turbine generator, that is currently limited to generating no more than 74.9 megawatts (MW) of electricity. The steam turbine has been specifically operated to produce no more than 74.9 MW. Therefore, the Plant was not subject to the Power Plant Siting Act. However, FPC has determined that the generating capacity of the steam turbine is nominally 10-15 MW greater than the capacity currently being used at the Plant. The Tiger Bay Facility is currently operating under separate environmental and other permits and approvals issued by FDEP, the Southwest Florida Water Management District (SWFWMD), Polk County and other agencies. The Tiger Bay Facility has been operated in compliance with those permits and approval, and no violations of those permits have occurred since the Plant began operation. By this certification application, FPC is seeking to consolidate the current permits and approvals for the Tiger Bay Facility into a single PPSA certification to authorize the use of the Plant's incremental steam-electric generating capacity. FPC proposes to utilize the additional steam-electric generating capacity in the steam turbine which would increase the generating capacity above the 75 MW threshold of the Power Plant Siting Act. Therefore, certification under the PPSA is required before FPC can obtain the additional electricity from the Plant. No physical changes to the facility or new construction are required to obtain the additional electricity. Only a minor operational change in the steam turbine controls is required to produce the incremental electricity through more efficient utilization of the steam. The Tiger Bay Facility is located on a 6.2 acre tract of land that is leased from the U. S. Agri-Chemical (USAC), Ft. Meade Chemical Complex. The lease extends until 2025 and may be renewed for an additional 25 years. The project's site boundaries will not be expanded to obtain the additional electrical generation. The site is located in southwest Polk County, Florida, approximately 3 miles west of Ft. Meade. The site is bounded on the north by S. R. 630. The project site is in the unincorporated area of Polk County. Ft. Meade is the only local government within a 5-mile radius of the Facility. The area surrounding the Tiger Bay Facility has been dominated by phosphate mining operations. Most of the land within a 5-mile radius of the Plant consists of active phosphate mining, reclaimed mine land, and lands in various stages of reclamation. Other land uses in the area include pasture land and citrus groves, along with limited residential, commercial and industrial uses. The nearest residence is over one mile from the project site. Land use in this area of Polk County is in transition as the phosphate industry completes mining phosphate deposits in the County. The Tiger Bay Plant site contains no significant environmental features. No wetlands, trees, shrubs or listed species or habitats exist within the site. Site vegetation consisted of ruderal and grassy communities prior to development for this project. No jurisdictional natural wetlands exist on the project site. No archaeological or historical sites were found on the project site when developed for this facility. The Tiger Bay Cogeneration Facility consists of one combustion turbine and electric generating unit, and one heat recovery steam generator (HRSG) and one steam turbine generator. In the CT, compressed air and fuel are ignited to provide energy to the air as it passes through the expansion section of the CT. The CT drives an electrical generator which has a nominal electrical output of 184 MS. Exhaust gases from the combustion turbine are then routed to the HRSG where water is boiled into steam. The steam from the HRSG powers a steam turbine which drives a second electrical generator, which will now generate 85.5 MW (nominal) of electricity. As a Cogeneration facility, the Tiger Bay Plant also exports up to 75,000 pounds per hour of low-pressure steam to the adjacent USAC Plant for use in its processes. This steam is extracted from the steam turbine part way through the steam electric generation process. The combined cycle facility is fired primarily with natural gas, with fuel oil as a backup fuel. Natural gas is supplied by a pipeline connected to the Florida Gas Transmission System. Oil will be stored in an onsite tank. The increase in steam generating capacity will be obtained by more efficient use of the steam that is already being produced in the HRSG. Currently, the steam is not fully utilized because its pressure is throttled by an internal control valve. To obtain the additional steam-generated electricity, the controls on this valve will be adjusted to increase the volume and pressure of the steam passing through the steam turbine. This increased steam pressure will generate additional electricity in the steam turbine generator. However, no physical modifications to the Tiger Bay Facility are required to obtain this additional steam generating capacity. Further, no increase in fuel use is required to obtain this additional capacity, and no increase in air emissions will result. All of the air emissions form the Facility are associated with the operation of the combustion turbine, which operates independently from the heat recovery steam generator. The main plant cooling-system begins with a steam condenser which cools the steam exhausted from the steam turbine. Heated cooling water is circulated to the on-site cooling tower where it is sprayed within the cooling tower to release the heat to the atmosphere. Fans at the top of the tower pull air into the tower in the opposite direction to the falling water. Cooled water collects in the bottom of the cooling tower and its returned back to the steam condenser. Approximately five percent of the cooling-water is lost in the cooling tower through evaporation and through drift, or water entrained in the air flowing through the tower. Two deep wells on site supply the makeup water for the cooling-water system. The other on-site water use is the potable water system, permitted for up to 1,000 gallons per day. Water is piped from an on-site well, filtered, and treated in a chlorinator before being distributed for use in the Plant. Wastewaters from the Plant consist of blowdown, or water withdrawn from the cooling tower and the heat recovery steam generator. This blowdown is necessary to prevent a buildup of dissolved solids in the waters from scaling in the circulating water system. Process wastewater and stormwater that contacts industrial processes are collected and recycled or routed to the adjacent USAC Plant where the wastewater is used in the phosphate production process. The Tiger Bay Facility has no off-site discharges of wastewater to either surface water or groundwater. The Facility also includes a back-up zero liquid discharge unit, which treats cooling-tower blowdown and process waters to remove the solids. The recovered high-quality water is recycled back into the Plant's process water stream. Domestic wastewater is treated and disposed on site through a septic tank system. Solid wastes that are generated at the Plant are typical of those associated with a light industrial facility. These wastes are re-cycled or re-used as much as possible. Solid wastes not re-cycled are picked up and disposed of in the Polk County landfill. The back-up zero liquid discharge system, when operational, produces a filter cake as result of drying the wastewater discharge. The non-hazardous material is also sent to the Polk County landfill for disposal. Electricity generated at the Plant is distributed from an on-site switchyard into the Florida Power Corporation transmission system. No changes to this transmission system are required for the additional electricity to be produced. Project Impacts: The Tiger Bay site is located in an area classified by FDEP as in "attainment" of all criteria air pollutants. The area is designated as Class II from a "prevention of significant deterioration" standpoint. The nearest Class I air-quality area is over 100 km to the northwest of the project site. The Tiger Bay Cogeneration Facility operates under an existing FDEP-issued Prevention of Significant Deterioration (PSD) permit. Nitrogen oxide (NOX) emissions are controlled with the use of low NOX burners when using natural gas, and with steam or water injection when firing oil. Particulate matter (PM) emissions are controlled through the use of clean fuels and combustion controls. Carbon monoxide and volatile organic compound emissions are also controlled through good combustion practices. Emissions of sulfur dioxide and metals, such as lead, mercury, beryllium and arsenic, are controlled through the use of clean fuels. PSD increments and ambient air-quality standards will be protected when the facility is being operated. The operation of the Plant at its increased steam generating capacity of 85.5 MW will not require any changes or additions to the facility. No increase in environmental impacts will result from the 10-15 MW (nominal) increase in steam generating capacity. The Plant will continue to operate within the currently permitted quantities of water for the facility, under the existing SWFWMD consumptive use permit. The project will not result in an increase in project- related traffic. The project also will not result in an increase in noise levels at the Plant site. The benefits of the project are that additional electricity is obtained without increasing either fuel use or environmental impacts from the Tiger Bay Plant. These "free megawatts" result from enhancing the efficiency of the Tiger Bay Plant, resulting in savings to FPC's customers. The project also conserves energy by using the additional existing generating capacity without increasing fuel use in the Plant. Consistency with Local Land-Use Plans and Zoning Ordinances: The Tiger Bay Cogeneration Facility is located in a future land-use classification of "PM" or phosphate mining on the Polk County future land-use map. Electrical power plants like the Tiger Bay Cogeneration Facility are permitted in that land- use category. The project site is zoned by Polk County as "RC" or rural conservation, which allows electric power generating facilities as a conditional use in that zoning district. Polk County issued a conditional use permit and site approval for the Tiger Bay Cogeneration Facility on November 20, 1992. The continued operation of the Tiger Bay Plant with its increased electrical output under site certification will be consistent with the land-use and zoning designations for the project site as well as the conditional use permit since there will be no physical changes made to the facility. The Polk County development approvals for the Tiger Bay Facility were consistent with the Comprehensive Plan in effect at the time the approvals were granted. Further amendments to the Polk County Comprehensive Plan are not retroactively applied to projects once they have received necessary development approvals. Agency Positions and Stipulations: The DEP, the Florida Department of Community Affairs (DCA), the Florida Game and Freshwater Fish Commission (FG&FWFC), the Southwest Florida Water Management District (SWFWMD), the Florida Department of Transportation (FDOT), and Polk County each prepared written reports on the Project, and all recommended approval of the Tiger Bay Cogeneration Project. The DCA determined the project, if certified, would be consistent and on balance with the state comprehensive plan. In its report, Polk County indicated that no changes to zoning at the project site were required as a result of certification of the project. Polk County also determined that the Facility would still meet the conditions of the County's original conditional use permit for the project and no further actions would be required by the Applicant. The Central Florida Regional Planning Council did not submit a report to the Department of Environmental Protection as part of its review of the project. No state, regional or local agency has recommended denial of certification. The recommended Conditions of Certification incorporate the existing permits for the Facility.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the Evidence of Record, and the pleadings and argument of the parties, it is, RECOMMENDED that: Florida Power Corporation be granted final certification, pursuant to Chapter 403, Part II, Florida Statutes, for the location and continued operation of the existing Tiger Bay Cogeneration Facility and its increased steam- electric generation capacity, as proposed in the Site Certification Application, and subject to the Conditions of Certification attached hereto; and The Siting Board find that the site of the Tiger Bay Cogeneration Facility, as described in the Site Certification Application, is consistent and in compliance with the existing land-use plans and zoning ordinances of Polk County, as they apply to the site, pursuant to Section 403.508(2), Florida Statutes. DONE AND ENTERED this 30th day of April, 1998, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1998. COPIES FURNISHED: Scott A. Goorland, Esquire Department of Environmental Protection Twin Tower Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Doug Roberts, Esquire Hopping, Green, Sams and Smith, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526 Charles T. Collette, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Station 35 Tallahassee, Florida 32399-3000 Robert V. Elias, Esquire Division of Legal Services Florida Public Service Commission 2540 Shumard Oak Boulevard Tallahassee, Florida 32399-0850 James V. Antista, Esquire Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, Florida 32399-1600 Andrew S. Grayson, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard Suite 315 Tallahassee, Florida 32399-2100 Earl Peterson, Director Division of Forestry Department of Agriculture and Consumer Services 3125 Conner Boulevard, C-19 Tallahassee, Florida 32399-1650 Hamilton Oven, Administrator Office of Siting Coordination Department of Environmental Protection 2600 Blair Stone Boulevard Mail Station 48 Tallahassee, Florida 32399-2400 Brian Sodt Central Florida Regional Planning Council 555 East Church Street Bartow, Florida 33830 Mary Miller, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458 George W. Perry, Director Director of Historical Resources Archives and History R. A. Gray Building 500 South Bronough Street Tallahassee, Florida 32399 Pepe Menendez, P.E. Department of Health Environmental Health Services 1317 Winewood Boulevard Tallahassee, Florida 32399-0070 Rich Tshantz, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Merle Bishop Polk County Florida Post Office Box 60 Bartow, Florida 33830 W. Jeffrey Pardue Florida Power Corporation Post Office Box 14042 MAC H2G St. Petersburg, Florida 33733 Doug Roberts, Esquire Hopping, Green, Sams and Smith, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526

Florida Laws (5) 120.68403.501403.502403.507403.508
# 6
CITY OF TALLAHASSEE (HOPKINS-TO-BAINBRIDGE) vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-001022 (1981)
Division of Administrative Hearings, Florida Number: 81-001022 Latest Update: Aug. 20, 1981

Findings Of Fact The proposed transmission line corridor is for the purpose of connecting a 230 kV line from the City of Tallahassee's existing system to the Georgia Power Transmission grid. The southern terminus of the corridor is in Leon County where the City's 230 kV line running north from the Hopkins' Power Plant makes a right angle turn toward the east, following Interstate Highway 10 (Section 13, Range 1 West, Township 1 North). The northern terminus of the corridor is that point where it ties to the Georgia system in Gadsden County, Florida, just south of the Florida State line in close proximity to the intersection of U.S. Highway 27 and SR 157 (Section 90, Range 1 West, Township 3 North, north of the Watson line). The corridor generally follows a center line conjunct with the Range 1 West range line, except that approximately 2.75 miles north of its southern terminus the corridor bends approximately 25 degrees to the east for a distance of approximately one-half mile before turning north for approximately 1.4 miles at which point the corridor turns west approximately 25 degrees for a distance of approximately 1.2 miles, and then turns east approximately 35 degrees for approximately 8 miles before once again turning north. The corridor encompasses several major highways, including Interstate Highway 10 and U.S. Highway 27. It also encompasses part of the Ochlocknee River, the Gadsden County, Florida landfill, part of the Tallahassee Commercial Airport, and part of the Ochlocknee Wildlife Management Area and Lake Talquin State Recreation Area. Just north of the rest stop on Interstate Highway 10, the corridor includes an area known as Riverwood Acres, a non-platted subdivision. The center line of the corridor bisects the subdivision. From its southern origin north, for approximately the first one mile of the corridor, the width of the corridor is approximately 9/16 mile. Thereafter the width of the corridor is approximately 1/2 mile. The location of the corridor is depicted in Figures 2-3, 2-6A, 2-6B, and 2-6C of the application. There being no more definitive a description of the location of the corridor than that shown in the maps comprising figures 2-6A, B, and C of the application, it is found as a matter of fact that those figures define the parameters of the proposed corridor. The length of the corridor is approximately 15 miles. The purpose of the corridor is to provide a 100 foot right-of-way for a 230 kV transmission line constructed upon H-frame wood poles, with an approximate span of 600 feet. Pursuant to the requirements of Section 403.537, Florida Statutes (1980 Supp.), the Florida Public Service Commission, by order dated March 31, 1981, found that: The construction of the proposed transmission line will enhance electric system reliability and integrity. The proposed transmission line will improve the availability of low-cost electric energy within the State of Florida. The point at which the City of Tallahassee proposes to connect to the construction of Georgia Power Company, and the point at which it proposes to connect to its own system, are the appropriate starting and ending points of the line. The Public Service Commission then concluded that the proposed transmission line is needed. Approximately 11.0 miles of the corridor's center line traverses land that is wooded and undeveloped. The remainder of the corridor center line, 3.9 miles, crosses land that reflects some type of human development or use. That includes land that is currently agricultural, in improved pasture, or simply open, cleared land. Although no residences lie within the corridor's center line, houses do lie elsewhere within the corridor. Several houses are located near the southern end of the corridor just north of Interstate Highway 10 in the area referred to as Riverwood Acres. Several houses are located near the Gadsden County Sanitary Landfill, and scattered houses are located in the corridor to the west of the Concord and to the south of the Darsey communities. Immediately beyond the eastern corridor boundary, but not within the corridor, is a developing neighborhood located in Township 1 north, Range 1 West, Section In that area residential property boundaries abut the eastern corridor boundary. Because of the objection by homeowners in the Riverwood Acres area, the width of the corridor has been slightly extended along the western and eastern boundaries so that the right-of-way may be placed with least impact upon the homes in that area. Approximately 0.05 acres of agricultural land will be directly disturbed by placement of transmission structures. It is expected that agricultural land can continue to be farmed between transmission structures. Where possible, existing road crossings or roads adjacent to the right-of-way will be utilized for maintenance and construction purposes. Where necessary, new access roads will be developed, but only to the extent needed for construction and maintenance of the line. The only major water body crossed by the proposed corridor is the Ochlocknee River. Impacts to the river should be negligible since the line structures on each side of the river will be physically located away from the river banks, and the lines and structures spanning the river will be situated well above the ordinary high water mark as defined by the United States Corps of Engineers. The uncontradicted evidence presented indicates that other streams or small water bodies crossed by the corridor will not be adversely impacted. Similarly, the uncontradicted evidence established that the two wetland areas to be crossed by the corridor center line will not be adversely impacted. A 230 kV transmission line is not considered an extra high voltage transmission line. Lines at 345 kV or larger are considered extra high voltage lines. The uncontradicted evidence establishes that there will be no significant noise impacts from the proposed transmission line operation. Except as otherwise noticed in the Findings of Fact herein, the uncontradicted evidence established that the proposed transmission line, if constructed along a right-of-way in the proposed corridor, pursuant to the conditions of certification, would have no significant adverse effect on the environment. Its impact on the environment will be minimal. Although none of the parties to this proceeding posed any objection to the proposed transmission line corridor and the transmission line to be constructed therein, three members of the public gave testimony in opposition to the site certification at the final certification hearing. The three persons were all residents of Riverwood Acres and were generally expressing the concerns of the neighborhood. Their sincere concern is evidenced by the excellent quality of their presentation. They expressed their opinion that their land value would be diminished by the construction of a transmission line adjacent or over their property. While it is difficult to consider the construction of such a transmission line as an enhancement to the property, as established by the testimony of their property will be diminished by the construction of the transmission line. These public witnesses also expressed a concern for the aesthetic damage to their neighborhood by the construction of this transmission line. It is found as a matter of fact that should the transmission line be constructed over or adjacent to these residential owners in Riverwood Acres, the aesthetic value of their environment would be diminished by the visual impact of the transmission line. Finally, these public witnesses expressed their concern and belief that the effects of the electric and magnetic fields generated by the transmission line would effect the health and welfare of the residents of the neighborhood. However, as established by the testimony of two witnesses expert in the areas of electrical engineering, radiation biology, and biophysics, the electric and magnetic field forces encountered in the vicinity of the transmission line at ground level will have essentially no biological effect, and will be no stronger than similar forces encountered in the normal course of modern daily life. These members of the public presented a thoughtful, well conceived proposed alternative routing which would take the proposed transmission line around their residential neighborhood. However, the evidence presented in this proceeding does not establish that the existence of the alternative proposed by these members of the public by itself indicates that the corridor for which site certification has been requested, will not produce minimal adverse effects on the environment, public health, safety and welfare. The Department of Environmental Regulation, the Department of Veterans and Community Affairs, the Department of Natural Resources, the Florida Game and Fresh Water Fish Commission, and the Northwest Florida Water Management District have all recommended that the proposed transmission line corridor will have minimal, if any, adverse effects on the environment and public health, safety and welfare. Those agencies have recommended no reason why the site should not be certified subject to the conditions proposed by the Department of Environmental Regulation, which conditions are attached to this Recommended Order. Notice of the final certification hearing was published on May 13, 1981, in the Tallahassee Democrat, a daily newspaper published at Tallahassee, in Leon County, Florida.

Recommendation Having reviewed the record of this proceeding, and based upon the Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that certification, pursuant to the Transmission Lines Siting Act, Chapter 403, Florida Statutes (1980 Supp.), be GRANTED to the City of Tallahassee for the transmission line corridor and the construction of the subject transmission lines as proposed in the application as amended and the evidence admitted to the record. It is further RECOMMENDED that certification be made subject to the Conditions of Certification attached hereto and the further condition pursuant to the requirement in Section 403.531(3), Florida Statutes (1980 Supp.), that the City of Tallahassee shall be required to seek any necessary interests in state lands, the title to which is vested in the Board of Trustees of the Internal Improvement Trust Fund, from the Board prior to engaging in any activity on or affecting such lands. DONE AND ENTERED this 23rd day of July 1981 in Tallahassee, Florida. CHRIS H. BENTLEY Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July 1981. COPIES FURNISHED: Louis F. Hubener, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 C. Laurence Keesey, Esquire Department of Veteran and Community Affairs Room 204, Carlton Building Tallahassee, Florida 32301 Paul Sexton, Esquire Public Service Commission 101 East Gaines Street Tallahassee, Florida 32301 Douglas Stowell, Esquire Northwest Florida Water Management District Route 1, Box 3100 Havana, Florida 32333 Kenneth Gilleland, Esquire Game and Fresh Water Fish Commission Bryant Building 620 South Meridian Street Tallahassee, Florida 32301 John Williams, Esquire Department of Natural Resources 3300 Commonwealth Building Tallahassee, Florida Ted Steinmeyer, Esquire Leon County Attorney Leon County Courthouse, Room 203 Tallahassee, Florida 32301 John Shaw Curry, Esquire Gadsden County Attorney Post Office Box 469 Quincy, Florida 32351 Barrett Johnson, Esquire c/o Mahoney, Hadlow & Adams Post Office Box 471 Tallahassee, Florida 32302 James R. Brindell, Esquire Post Office Box 3103 Tallahassee, Florida 32303 (Representing Riverwood Acres Neighborhood Association)

Florida Laws (5) 403.52403.526403.531403.536403.537
# 7
INDIAN TRAIL IMPROVEMENT DISTRICT vs DEPARTMENT OF ENVIRONMENTAL PROTECTION AND PALM BEACH COUNTY WATER UTILITIES DEPARTMENT, 05-002984 (2005)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 18, 2005 Number: 05-002984 Latest Update: Nov. 02, 2005

The Issue The issue is whether Palm Beach County's application for a permit to construct a domestic wastewater collection/transmission system in Palm Beach County should be approved.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Parties The County is a political subdivision of the State of Florida and is the permittee in this matter. The County Water Utilities Department currently serves approximately 425,000 persons, making it the largest utility provider in Palm Beach County and the third largest in the State of Florida. ITID is an independent water control special district created by special act of the legislature in 1957 and whose boundaries lie within the County. Portions of the transmission line to be constructed by the County will cross easements and roads, and pass under canals, owned by ITID. Petitioners Joseph Acqualotta, Michael D'Ordine, Ann Hawkins, and Lisa Lander all live in areas in close proximity to the proposed transmission line. Lander lives adjacent to the proposed route of the line along 40th Street North, while Acqualotta, D'Ordine, and Hawkins live adjacent to the proposed route along 140th Avenue North. Acqualotta, Hawkins (but not D'Ordine, who resides with Hawkins), and Lander own the property where they reside. Petitioners Troy and Tracey Lee (Case No. 05-2979), Lisa Gabler (Case No. 05- 2980), and Anthony and Veronica Daly (Case No. 05-2982) did not appear at the final hearing. The Department is an agency of the State of Florida authorized to administer the provisions of Part I of Chapter 403, Florida Statutes, and is the state agency charged with the responsibility of issuing domestic wastewater collection/ transmission permits under Section 403.087, Florida Statutes (2004).1 Background On December 15, 2004, the County filed its application with the Department for an individual permit to construct a domestic wastewater collection/transmission system (Transmission Line). The Transmission Line is one element of the County's Northern Region Utilities Improvement Project (Project) and will be approximately 41,050 feet long and comprised of approximately 32,350 linear feet of 20-inch force main and 18,700 linear feet of 30-inch force main (or nearly ten miles in length). A primary purpose of the Project is to provide water and wastewater service to the Village, a 1,900 acre parcel located in the unincorporated part of the County several miles west of the Florida Turnpike, south of State Road 710, and north of the Villages of Wellington and Royal Palm Beach. The Village will be the home of the Scripps Project and Campus. The Transmission Line will run from the southeastern corner of the Village south to Northlake Boulevard, then east to 140th Avenue North, then south along that roadway to 40th Street North, where it turns east until it interconnects with existing facilities. The wastewater will be collected in a regional pump station on the Scripps Project site, where it will be pumped through the Transmission Line to the East Central Plant, which will be the primary treatment facility. The East Central Plant is owned and operated by the City of West Palm Beach (City), but the County owns between forty and forty-five percent of the treatment capacity. Because the wastewater system is interconnected, the wastewater could also be treated at the County's Southern Regional Plant. Ultimately, the flow from the Scripps Project will be one or two million gallons per day. The Transmission Line is the only way that wastewater can be handled at the Scripps Project. A preliminary analysis by the Department and the South Florida Water Management District determined that on-site treatment was not feasible because of the environmentally sensitive nature of the area. The Scripps Project will include residential units, commercial entities, and institutional uses, such as medical clinics. Besides serving these customers, the Transmission Line will also serve other customers in the area. The County has already signed agreements with the Beeline Community Development District (which lies a few miles northwest of the Village) and the Village of Royal Palm Beach (which lies several miles south-southeast of the Village). At the time of the hearing, the County anticipated that it would also sign an agreement with Seacoast Utility Authority (whose service area is located just southeast of the Village) to transport wastewater through the Transmission Line. All of the treatment facilities have sufficient existing capacity to treat the estimated amount of domestic wastewater that will be generated by the Scripps Project and the other users that will discharge to the Line. The County commenced construction of the Transmission Line in May 2005 when the Department issued the Permit. On August 2, 2005, the County published the Department's Notice to issue the Permit, and once the Petitions were filed, the County stopped construction pending the outcome of this hearing. Approximately seventy percent of the Transmission Line is now completed. The Permit does not allow the Transmission Line to be used until it is pressure tested and certified complete. Upon completion, the County must receive an Approval to Place a Domestic Wastewater Collection/Transmission System into Operation from the Department. Such approval is given only after the County has given reasonable assurance that adequate transmission, treatment, and disposal is available in accordance with Department standards. See Fla. Admin. Code R. 62-604.700. On August 15, 2005, Petitions challenging the issuance of the Permit were filed by ITID and the individual Petitioners. ITID contends that the Transmission Line will convey not only domestic wastewater, but also industrial waste; that the County did not comply with all applicable technical standards and criteria required under the Department's rules; that the Project will be located on ITID's right-of-way, on which the County has no right to occupy; that the Project will be located within seventy-five feet from private drinking wells and does not provide an equivalent level of reliability and public health protection; and that the pipe material and pressure design is inappropriate for the Transmission Line's requirements. The individual Petitioners (who filed identical Petitions) are mainly concerned about the location of the Transmission Line in relation to their private drinking wells and property, the possibility of the pipe bursting or leaking once it becomes operational, and the restoration of their property to its original condition after construction is completed. As to the property claims by all Petitioners, the County plans to place the Transmission Line in property that it either owns or has an easement, in property that it is in the process of condemning, or in a public right of way. While the County acknowledges that it has already placed, and intends to place other portions of, the Transmission Line in easements that ITID says it has the exclusive right to use and for which a permit from ITID is required, the County alleges that it also has the right to use those easements without an ITID permit. The dispute between the County and ITID is the subject of a circuit court proceeding in Palm Beach County, and neither the Department nor DOAH has the authority to decide property interests. Petitioners' Objections Domestic wastewater and pretreatment The wastewater that will be generated by the Scripps Project is considered domestic wastewater; it will not include industrial wastewater. Waste that is industrial or non- domestic must be pretreated to protect the wastewater plant, collection system, and the health of system workers and the general public. The Department administers a pretreatment program through which it requires a public wastewater utility to police the entities that discharge to their wastewater plants. A central part of the pretreatment program is the local ordinance that gives legal authority to the utility to permit, inspect, and take enforcement action against industrial users who are part of the pretreatment program. The utility files an annual report with an industrial user survey, and the Department periodically inspects and audits local pretreatment programs to ensure they are being operated as intended. The system is not failsafe but is designed to ensure that potentially harmful wastes are rendered harmless before discharge. For example, the utility has the authority to immediately shut water off if a harmful discharge is occurring. Both the County and the City have pretreatment programs approved by the Department. The City has an ordinance that allows it to enforce the pretreatment standards for all entities that discharge to its wastewater system. The County Water Utilities Department has a written pretreatment manual, and the County has zoning restrictions on the discharge of harmful material to the wastewater system. It has also entered into an interlocal agreement under which it agrees to enforce the City ordinance. The County provides wastewater treatment to industrial, educational, and medical facilities, and it has never experienced a discharge from any of these facilities that has caused adverse health or environmental impacts. The County pretreatment program for the Southern Regional Facility was approved in 1997. The City pretreatment program for the East Central Regional Facility was approved in 1980. The Scripps Project must apply for a permit from the County and provide a baseline monitoring report, data on its flow, and information on the flow frequency and raw materials. Medical waste from the Scripps Project will be pretreated to render it safe before it is discharged into the Transmission Line. Transmission Line Design The Transmission Line was designed in accordance with the technical standards and criteria for wastewater transmission lines in Florida Administrative Code Rule 62- 604.300(5). That rule incorporates by reference a set of standards commonly known as the Ten State Standards, which contain several of the standards used in the design of this project. These standards are recommended, but are not mandatory, and a professional engineer should exercise his or her professional judgment in applying them in any particular case. The Transmission Line also meets the design standards promulgated by the America Water Works Association (AWWA). Specifically, the County used the AWWA C-905 design standard for sizing the polyvinyl chloride, or PVC, pipe used in the project. The County has received written certification from the manufacturer that the PVC pipe meets the standards in AWWA C-905. The Transmission Line is designed with stub-outs, which will allow for future connections without an interruption of service, and inline isolation valves, which allow the line to be shut down for maintenance. The Use of PVC Pipe There is no standard regulating the selection of PVC pipe material in the Department's rules. Instead, the Department relies on the certification of the applicant and the engineer's seal that the force main will be constructed to accepted engineering standards. The only specification applicable to the Transmission Line is the Ten State Standard, adopted and incorporated by reference in Florida Administrative Code Rule 62-604.300(5)(g). That document contains a general requirement that the material selected have a pressure rating sufficient to handle anticipated pressures in wastewater transmission lines. The Transmission Line will be constructed with PVC piping with a thickness of Dimension Ratio (DR) 32.5, which is the ratio of the outside diameter of the pipe to its thickness. Higher ratios mean thinner-walled pipes. This is not the first time the County has used 32.5 PVC piping for one of its projects, and other local governments in the State have used 32.5 or thinner pipe. The County is typically conservative in requiring thicker-walled pipe, because most transmission lines are built by developers, and the County is unable to design the entire line or control or inspect its installation. The specifications for wastewater transmission lines built in the County call for the use of DR 25 pipe. On this project, however, the County determined that thicker- walled pipe would have been an over-design of the system because the County controls the pump stations and oversees the installation; therefore, the Director of the Water Utilities Department has waived that requirement. The County considers the use of DR 32.5 PVC to be conservative. Although this pipe will be thinner than what is typically used in the County, it satisfies the Department's requirements. The Department has permitted many miles of similar PVC force mains in South Florida, and none have failed. PVC has benefits over other transmission line material, such as ductile iron. For example, PVC is more corrosion resistant. Wastewater generates hydrogen sulfide as it decomposes, which can form highly corrosive sulfuric acid. Some of the older transmission lines in the County that were made of ductile iron have corroded. PVC also has a superior ability to absorb surges, such as cyclical surges, than ductile iron. It is easier to install, and its interior flow characteristics are smoother than ductile iron or pre-stressed concrete pipe. Mr. Farabee, a professional engineer who testified on behalf of ITID, recommended a DR 14 pipe, which is thicker- walled than the DR 32.5 pipe used by the County. While he opined that the DR 32.5 pipe was too thin for the project, he could not definitively state that it would not pass the 150 per square inch (psi) pressure test. He also opined that the pipe is undersized because it will be unable to withstand the surge pressures during cleaning. The witness further testified that the pipe would be subject to much higher pressures than 150 psi, and therefore it was impossible to know whether the pipe would fail. In his opinion, this means the Department did not have reasonable assurance for the project. The County consulted with the Unibell PVC Pipe Association (Unibell) in the planning of this project. Unibell is a trade association that provides technical support for PVC pipe manufacturers. Robert Walker, a registered professional engineer and Unibell's executive director who testified on behalf of the County, disagreed with Mr. Farabee's conclusions concerning the adequacy of the PVC pipe in this project. The AWWA C-905 standard uses a safety factor of two, which means the pipes are tested at pressures that are at least twice their stated design strength. Mr. Walker explained the different standards that apply to PVC pipe. DR 32.5 pipe, which is used in this project, has a minimum interior pressure rating of 125 pounds per square psi. Each pipe section is tested before it is shipped at 250 psi, and the minimum burst pressure for the material is in excess of 400 psi. The pipe also meets a 1000- hour test at 270 psi. In light of these standards and testing, the pipe will pass the two-hour 150 psi test required by the Department. Mr. Farabee expressed some concern that the PVC pipe would be more prone to breakage than ductile iron or thicker PVC. However, the PVC pipe standards provide that the pipe can be flattened at sixty percent without splitting, cracking, or breaking. At shallow depths on dirt roads, ovalation, which occurs when PVC is flattened through pressure, will initially occur, but over time the soil around the pipe will become compacted and result in re-rounding of the pipe. The joints are three times stiffer than the body of the pipe, which will protect the joint from excessive ovalation and leaking, and the use of mechanical restrained joints will further strengthen the joints. There has been no joint leakage in Florida due to deflection of the joints. Finally, there have been no failures of PVC pipe caused by three-feet of fill, which is the depth to which the Transmission Line pipe will be buried. To further protect the pipe, the County optimized its pumping system to avoid cyclical surges by using variable frequency drive pumps that gradually increase and decrease speed rather than just turning on or off. In addition, the pump stations are fed by two power lines that come from different directions and emergency generators, which should lessen the chances of harmful surging. Testing the Installation The anticipated pressures in the Transmission Line will likely be about 50 psi. After installation, the Line will be pressure tested at 150 psi for two hours, which is sufficient to provide the Department with reasonable assurance that the Line will hold pressure and will not leak. Also, the County contract inspectors are on the construction site daily. If problems with the installation arise later, the County has committed to promptly fix the problem, even if it means digging up the line. During the hearing, ITID asserted that the Uniform Policies and Procedure Manual standards, which the County has adopted for use by developers when constructing wastewater transmission lines, should be applied to the County as well. This standard, which requires pressure testing to 200 psi for PVC pipes larger than 24 inches, has not been adopted by the Department and is not an applicable Department permitting standard. Even if it did apply, the Transmission Line would meet this criterion because it is designed to withstand 270 psi for at least 1,000 hours. Mr. Farabee believed that the entire Transmission Line would be pressure tested after the construction was complete, which would require digging up sections of the pipe to install bulkheads. However, this assessment of the County's testing program is incorrect. Leisha Pica, Deputy Director of the Water Utilities Department, developed the schedule for the project, helped develop the phasing of the work and budget, and oversaw the technical aspects. She stated that the County has successfully tested approximately fifty percent of the line that was already installed at 150 psi for two hours and not a single section of the line failed the test. Compaction The County has stringent backfilling and compaction requirements, which are sufficient to ensure the pipe will be properly installed and that there will be adequate compaction of the fill material. The County plans and specifications provide that compaction must be to ninety-five percent of the American Association of State Highway and Transportation Officials (AASHTO) standards for non-paved surfaces and one hundred percent of AASHTO standards for paved surfaces. Even ITID's expert agreed that the compaction specifications are sufficient. Mr. Farabee contended, however, that even though the standards are stringent, the County cannot properly test the installation for compliance with the standards. Mr. Farabee believed that testing of the backfill would be done after all of the construction was complete. In that case, he did not see how the testing could be done without digging many holes to check for the density of the backfill. These assumptions, however, are incorrect. The evidence shows that a total of two hundred sixty-four compaction tests have already been done on the portion of the Transmission Line that was completed. No part of the installation failed the tests. The County has an inspector who observes the installation and pressure tests. The compaction was tested at every driveway and major roadway, as well as every five hundred feet along the route. While Lander and D'Ordine pointed out at hearing that no compaction tests have been performed on the dirt roads which run adjacent to their property and on which construction has taken place, the Department requires that, before the work is certified as complete, non-paved roads must be compacted in accordance with AASHTO standards in order to assure that there is adequate compaction of the fill material. The Sufficiency of the Application When an application for an individual transmission/ collection line permit is filed with the Department, the applicant certifies that the design of the pipeline complies with the Department's standards. However, not all of the details of the construction will be included in the permit application. The Department relies on the design engineer to certify that the materials used are appropriate. The application form is also signed and sealed by a professional engineer registered in the State of Florida. All plans submitted by the County, including the original, modifications, and final version, were certified by professional engineers registered in the State of Florida. After receiving the application, the Department requested additional information before issuing the permit, and the County provided all requested information. The original construction plans that were submitted with the application were changed in response to the Department's requests for additional information. The Permit issued by the Department indicates the Transmission Line would be constructed with ductile iron pipe, but this was a typographical error. ITID maintains that all of the technical specifications for the project must be included in the application, and because no separate engineering report was prepared by the County with the application, the County did not meet that standard. While the County did not submit an engineering report, it did submit sufficient data to provide reasonable assurance that the project will comply will all applicable rules of the Department. As a part of its application package, the County submitted construction plans, which contain the specifications required by the Department. Also, the general notes included in the construction drawings specify the use of restrained joints where appropriate, the selection of pipe material, the pressure testing of the Transmission Line, and other engineering requirements. In addition, the plans contain numerous other conditions, which are also specifications sufficient to fulfill the Department's requirements. Finally, further explanation and clarification of the technical aspects of the application was given by the County at the final hearing. At the same time, the Department engineer who oversaw the permitting of this project, testified that a detailed engineering report was not necessary. This engineer has extensive experience in permitting transmission lines for the Department and has worked on over five hundred permits for wastewater transmission and collection systems. The undersigned has accepted his testimony that in a relatively straightforward permit such as this, the application and attachments themselves can function as a sufficient engineering evaluation. This is especially true here since the County is seeking only approval of a pipeline project, which would not authorize the receipt of wastewater flow unless other wastewater facilities are permitted. Impacts on Public and Private Drinking Water Wells As part of the design of the Transmission Line, the County located public and private drinking water wells in the area of the line. County personnel walked the route of the Transmission Line and looked for private wells and researched the site plans for all of the properties along the route. No public wells were found within one-hundred feet of the Transmission Line route, but they did find seventeen private wells that are within seventy-five feet of the line. None of the Petitioners have private wells that are within seventy- five feet of the line. While Petitioners D'Ordine and Hawkins initially contended that the well on Hawkins' property was within seventy-five feet of the Transmission Line, at hearing Mr. D'Ordine admitted that he "misread the plans and referred to the wrong property." In order to protect the private drinking water wells, Florida Administrative Code Rule 62-604.400(1)(b) requires that the County provide an extra level of protection for the wells that are within seventy-five feet of the Transmission Line. The County will provide that extra level of protection by installing restrained joints that will restrain the joints between the pipe sections. The restrained joints are epoxy-coated mechanical devices that reduce the tendency for the pipes to separate under pressure. The County has used these restrained joints on its potable water and wastewater lines in other areas of the County and has never experienced problems with the devices. The restrained joints will provide reliable protection of the private wells within seventy-five feet of the Transmission Line. The Department is unaware of any instances where restrained joints have failed in South Florida. If more wells are discovered that are within seventy-five feet of the Transmission Line, then the County will excavate the Line and install restrained joints. Minimum Separation Distances The County has complied with all applicable pipe separation requirements in the installation of the Transmission Line. More specifically, it is not closer than six feet horizontally from any water main and does not intersect or cross any reclaimed water lines. See Fla. Admin. Code R. 62-555.314(1)(a). It will be at least twelve inches below any water main or culvert that it crosses. See Fla. Admin. Code R. 62-555.314(2)(a). Finally, it will be a minimum of twelve inches below any culverts that it crosses. (However, the Department has no separation requirement for culverts crossed by the Transmission Line.) h. The M-Canal Crossing The Transmission Line must cross the M-canal, which runs in an east-west direction approximately midway between 40th Street North and Northlake Boulevard. The original design called for the Transmission Line to cross above the water, but the City and the Department suggested that it be located below the canal to eliminate the chance that the pipe could leak wastewater into the canal. In response to that suggestion, the County redesigned the crossing so that a 24- inch high density polyethylene pipe in a 48-inch casing will be installed fifteen feet below the design bottom of the canal. The polyethylene is fusion-welded, which eliminates joints, and is isolated with a valve on either side of the canal. Appropriate warning signs will be installed. See Fla. Admin. Code R. 62-604.400(2)(k)2.-5. The depth of the subaqueous line and the use of the slip line, or casing, exceeds the Department's minimum standards. See Fla. Admin. Code R. 62-604.400(2)(k)1. i. Flushing Protocol Section 48.1 of the Ten State Standard recommends that wastewater transmission lines maintain a velocity of two feet per second. When the Transmission Line becomes operational, it will not have sufficient flow to flush (or clean) accumulated solids from the lines at the recommended two feet per second velocities. (Sufficient flow will not occur until other customers connect to the Transmission Line during the first one to three years of operation.) Accumulated solids produce gases and odors that could create a problem at the treatment plant and might leak out of the manhole covers. To address this potential problem, Specific Condition 9 of the Permit requires the County to flush the lines periodically. Pursuant to that Condition, the County plans to flush the Transmission Line with additional water which will raise the velocity to three or four feet per second, so that the accumulated solids will be flushed. The water will be supplied by large portable tanks that will be temporarily set up at several locations along the Line. During the purging of the Line, sewage will collect in the pump stations until the purge is finished. There is sufficient capacity in the pump stations to contain the wastewater. In addition, the County will use a cleansing tool known as a pig, which is like a foam bullet that scrapes the sides of the pipe as it is pushed through the line. This protocol will be sufficient to keep the Line clean. ITID asserts that the County's plan for flushing is inadequate, because it does not provide enough water for long enough to flush both the 20-inch and 30-inch lines. Mr. Farabee calculated that the County would need almost twice the proposed volume, or almost six million gallons, to adequately flush the lines. ITID's analysis of the flushing protocol is flawed, however, because it assumes a constant flow in all segments of the pipe, which is not practical. In order to maintain the flushing velocity of three feet per second, the County will introduce water into the Transmission Line at three separate locations, resulting in a more constant flow velocity throughout the Transmission Line. In this way, it can maintain the proper velocity as the lines transition from a 20-inch to 30-inch to 36-inch pipe. The County has flushed other lines in the past using this protocol and has had no problems. This flushing protocol would only be in effect from one to three years. The County estimates that the necessary volumes to maintain a two-feet-per-second velocity in the 20- inch line would be reached in about one year. The 30-inch line should have sufficient flows sometime in 2008. These estimates are based on the signed agreements the County has with other utilities in the area to take their flows into the Transmission Line. Because of these safeguards, the Transmission Line will not accumulate solids that will cause undesirable impacts while flow is less than two feet per second. Other Requirements The construction and operation of the Transmission Line will not result in the release or disposal of sewage or residuals without providing proper treatment. It will not violate the odor prohibition in Florida Administrative Code Rule 62-600.400(2)(a). It will not result in a cross- connection as defined in Florida Administrative Code Rule 62- 550.200. The construction or operation of the Transmission Line will not result in the introduction of stormwater into the Line, and its operation will not result in the acceptance of non-domestic wastewater that has not been properly pretreated. If constructed and permitted, the Transmission Line will be operated so as to provide uninterrupted service and will be maintained so as to function as intended. The record drawings will be available at the Department's district office and to the County operation and maintenance personnel. Finally, concerns by the individual Petitioners that the County may not restore their property to its original condition after construction is completed are beyond the scope of this proceeding. At the hearing, however, the Deputy Director of the Water Utilities Department represented that the County would cooperate with the individual property owners to assure that these concerns are fully addressed. Reasonable Assurance The County has provided the Department with reasonable assurance, based on plans, test results, installation of equipment, and other information that the construction and installation of the Transmission Line will not discharge, emit, or cause pollution in contravention of the Department's standards.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order denying all Petitions and issuing Permit No. 0048923-017-DWC. DONE AND ENTERED this 18th day of October, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of October, 2005.

Florida Laws (4) 120.569120.57403.087403.973
# 8
MEMORIAL HOSPITAL OF JACKSONVILLE, ET AL. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 81-000041RX (1981)
Division of Administrative Hearings, Florida Number: 81-000041RX Latest Update: Mar. 12, 1981

Findings Of Fact The Respondent, Florida Department of Health and Rehabilitative Services, is an agency of the State of Florida charged with the responsibility, inter alia, for setting and enforcing health and safety standards for hospitals located within the state. In furtherance of this function, the Department has adopted rules set out Chapter 10D-28, Florida Administrative Code. Among these rules are provisions which set standards for hospital construction which are designed to assure the fire and electrical safety of patients, staff and visitors to hospitals. The Department enforces its rules by licensing or certifying hospitals which comply with them, and by refusing licensure or certification to those which do not. The Department's Rule 10D-28.79, Florida Administrative Code, relates to codes and standards for the physical plant of new and existing hospitals. The rule does not set out code provisions, but rather adopts various construction and life safety codes by reference. Rule 10D-28.79(5) provides in pertinent part: The following codes and regulations are herein adopted by the licensing agency [the Department], and it shall be the responsibility of the sponsor [licensed hospitals] to consult such codes for compliance with all matters not specifically set forth in this chapter. Standard Building Code, 1976 edition, Group I, Institutional Occupancy. National Fire Protection Association No. 101, Life Safety Code 1973 Edition; Appendix B of this Code adopts several other NFPA standards, which shall be met . . . This rule became effective on January 1, 1977. Copies of the codes that were adopted by reference did not accompany the rules as the were filed with the Office of the Secretary of State. The Life Safety Code is a publication of the National Fire Protection Association (NFPA). Appendix B to the Code, which is referenced in the Department's Rule 10D-28.79(5)(b) is titled "Referenced Publications" and provides in part as 7 follows: The following publications are referenced by this Life Safety Code and thereby comprise a part of the requirements or recommendations to the extent called for by the Code or Appendix A, respectively. The Appendix goes on to list more than fifty publications, including the 1971 National Electric Code, which is another publication of the National Fire Protection Association. The crux of this proceeding is a single paragraph of this publication. Paragraph 517-51(a) sets an electrical performance standard to be met in hospital areas where "electrically susceptible patients" are housed. The paragraph provides: In electrically susceptible patient areas the maximum 60-hertz alternating-current potential difference between any two conducting surfaces within thee reach of a patient, or those persons touching the patient, shall not exceed five millivolts measured across 500 ohms under normal operating conditions or in case of any probable failure. The Department has interpreted its Rule 10D-28.79(5)(b) as adopting as performance standards the provisions of all of the codes set out in Appendix B of the 1973 Life Safety Code, including the 1971 National Electric Code, and paragraph 517-51 thereof. There are conflicting provisions in the various Life Safety and Electrical Codes that the Department has adopted, and contends that it has adopted through its adoption of Appendix B of the 1973 Life Safety Code. The Department resolves these conflicts by requiring hospitals to develop solutions which will meet the provisions of all of the codes. The provisions of paragraph 517-51(a) of the 1971 National Electric Code are considerably more strict than similar provisions set out in later editions of the National Electric Code, including the 1975, 1978 and 1981 Codes. The Department contends that hospitals must comport with the most strict of these requirements, i.e. the ones set out in paragraph 517-51(a) of the 1971 Code. The Petitioner Memorial Hospital of Jacksonville is an accredited, licensed hospital in the State of Florida. Memorial Hospital is presently in the process of constructing a three million dollar renovation, including a renovation to its critical care unit. In order to comply with the provisions of paragraph 517-51(a) of the 1971 National Electric Code, Memorial Hospital would need to expend approximately $55,000 that would not need to be expended in order to comply with provisions of other codes. Memorial Hospital has requested a variance from the Department from the requirement of complying with this provision. The Petitioner St. Vincent's Medical Center is an accredited, licensed hospital located in Jacksonville, Florida. St. Vincent's Medical Center is currently involved in a project to renovate and add space to its existing facilities, including a thirty-two bed critical care unit. In order to comply with the provisions of paragraph 517-51(a) of the 1971 National Electric Code, St. Vincent's would be forced to expend from $75,000 to $80,000 which would not be necessary in order to comply with the provisions of other codes. St. Vincent's Medical Center has requested a variance from the requirements of that provision from the Department. Halifax Hospital Medical Center is an accredited, licensed hospital located in Daytona Beach, Florida. Halifax Hospital has been advised that it would be required to comply with the provisions of paragraph 517-51(a) of the 1971 National Electric Code in renovating and expanding its critical care unit. While the precise cost of complying with the provision cannot be determined, it is evident that Halifax Hospital would be required to expend more money to comply with the provision than would be required to comply with other provisions. The Petitioner Shands Teaching Hospital and Clinics, Inc., is an accredited, licensed hospital located in Gainesville, Florida. Shands Hospital is presently in the process of expanding and renovating its facility, including its critical care unit. Shands Hospital has been advised by the Department that it would need to comply with the provisions of paragraph 517-51(a) of the 1971 National Electric Code in connection with the critical care unit. The cost of complying with this provision would be approximately $140,000 over the cost of complying with other provisions. No evidence was presented with respect to the Petitioner Variety Children's Hospital. The Department's interpretation of its Rule 10D-28.79 as having adopted by reference the performance standard set out at paragraph 517-51(a) of the 1971 National Electric Code is in error. While the Department's rule references Appendix B to the 1973 Life Safety Code, it provides only that that Appendix adopts several other standards which must be met. While the Appendix references the 1971 National Electric Code, it adopts only the provisions of the 1971 National Electric Code and the other referenced publications to the extent that they are otherwise adopted in the 1973 Code or Appendix A thereto. Paragraph 517-51(a) of the 1971 Code is not referenced in Appendix A to the 1973 Life Safety Code, nor in any other pertinent place. The Department has, albeit erroneously, interpreted its rules as adopting paragraph 517-51(a) of the 1971 National Electric Code. This interpretation is being uniformly applied by the Department, and therefore itself constitutes a rule. The interpretation has not itself been adopted as a rule other than through the provisions of Rule 10D-28.79. The 1971 National Electric Code was not filed with the Office of the Secretary of State when Rule 10D-28.79 was filed, and is not generally available. It has been replaced by subsequent editions of the National Electric Code and is no longer generally available to members of the public at large. The effect of the Department's interpretation of its rules as adopting the standard set out in paragraph 517-51(a) is to require hospitals to install "isolated power sources" in critical care units. The standard by its terms applies to areas of a hospital where electrically susceptible patients are housed. Such patients are housed in operating rooms, rooms where highly flammable anesthetics are used, and in critical care units. Other standards adopted by the Department expressly require installation of isolated power sources in operating rooms and in rooms where flammable anesthetics are used. The fact that these are "wet" areas and areas where flammable materials are kept justifies those requirements. These conditions do not apply to critical care units. The electrically susceptible patients who are housed in critical care units are patients who have catheters inserted into their bodies, and extensions from the catheters protruding outside their bodies. The most common such patient is a patient with a pacemaker attached to his or her heart. With such patients an electrical device outside the body is connected through a catheter into a vein, and eventually to an area close to or actually at the heart. These patients are electrically susceptible because low levels of electrical current that might flow through the catheter could kill the patient. A power source of less than 100 millivolts if attached to the catheter in such a way that current could flow through the catheter could have the effect of fibrillating a patient's heart and killing him. This is much less power than would do any damage to a person under normal conditions, and considerably less voltage than would commonly result from short circuits or other malfunctions in equipment powered by conventionally grounded power sources. The amount of voltage that would be available given a fault or short circuit condition can be reduced through use of isolated power systems. Such a system includes a transformer which provides a demarcation between the incoming or primary power line, which is conventionally grounded, and the outgoing or secondary line. The secondary line is isolated from ground, neither wire being connected to ground. The secondary line runs into circuit breakers then to receptacles about the room. All of this equipment is installed in an electrical box. A monitor or gauge is installed on the face of the box. The monitor visually displays the extent of degradation of the secondary line, i.e. , whether the secondary line has become grounded. By observing the monitor, it is possible to avoid grounding a patient so that electrical currents cannot pass through the patient. The Department maintains that the 1971 Code standard can be met only through installation of isolated power sources. Under some fault circumstances this is correct, and, no other practical technology exists to meet the standard under any fault circumstances. Imposition of the standard set out at paragraph 517-51(a) of the 1971 National Electric Code is arbitrary and unreasonable. In the first place, no known technology can meet the standard. Even an isolated power system will meet the standard only in the case of line-to-ground faults. In cases where ground is lost, the isolated power system will not stay within the standard. The Department's action in requiring hospitals to install line isolation monitors thus meets the standard only under one fault circumstance, and it is not the one that most commonly occurs. Even as to those faults for which the line isolation monitor will accomplish the meeting of the 1971 standard, there is no valid reason for requiring their installation. The goal of protecting an electrically susceptible patient from electrocution can be easily and reliably accomplished by protecting the catheter from contact with electrical power sources. Basically, in order to create an electrical incident, or a shock, one part of a person's body has to touch some metal, another part has to touch some metal, and some current has to flow. This can be broken down into eight steps that would need to occur for a patient to be shocked: First, a power source or power line has to run close to the patient. Second, the line has to be exposed and touch metal. Third, the metal has to become live. Fourth, the metal must become ungrounded. Fifth, the patient has to touch the metal directly or through some conductive path. Sixth, a second conductive surface (more metal) has to be available. Seventh, the patient has to touch it. Eighth, the current has to be at a level that will cause harm. If any of these things does not happen, there will not be a shock. During the 1960's and early 1970's, the fact that very low levels of electrical current could cause fibrillation of the heart was not understood. This fact has been understood now for some time, and hospitals have looked to avoid placing patients in circumstances where the eight steps can occur. Looking at the problem in this manner allows hospitals to focus on what factors can easily be eliminated. Current practice is not to ground things which do not have to be grounded. It had previously been the practice to ground all of the metal around the patient, creating a "bathtub" effect. The line isolation monitor serves to eliminate the eighth of these steps by, in at least one fault circumstance, allowing only very low levels of current to flow. The other steps can be more easily eliminated. One means of accomplishing that is to isolate the power source to the catheter. Thus, battery powered equipment is now typically used, rather than equipment that attaches directly to the main power source. Furthermore, catheters protruding from a patient's body are now insulated, and critical care unit personnel are instructed not to touch them unless they are wearing rubber gloves. The taking of these steps eliminates the possibility for electrocution of an electrically susceptible patient through low voltage currents (microshock). There have been no documented deaths of patients through such microshock anywhere in the world since 1972. Even in that instance, which occurred in the United Kingdom, the accident did not happen in a critical care unit, but rather in an operating unit. The circumstances of the incident were that a hospital had been callously negligent in allowing its equipment to be modified so that inadequate switches were attached to an operating table and open current lines were exposed. Blood from a patient flowed to the open lines, and electrocution resulted. This incident bears no relevance to the instant rule. In the first place, it occurred in an operating room, where isolated power systems are properly required. In the second place, the hospital staff was incredibly negligent about its procedures and equipment. In addition to the fact that isolated power systems no longer accomplish any valid purpose in preventing microshock, there are disadvantages to their use. These disadvantages include: (1) Line isolation monitors limit the amount of power that is available at bedside in critical care units. There is a need for considerable available power at bedside, and line isolation monitors limit available power, and can contribute to power interruptions. (2) A component is added to the power distribution system so that an additional point of failure exists. (3) The isolation system is installed at the head of beds in a critical care unit, thus interfering with the possibility of putting other equipment in that place. (4) Isolated power systems with their transformers and monitors can produce an annoying hum. (5) Isolated power systems give off heat. (6) Line isolation monitors which go with isolated power systems can cause interference with other devices, such as electroencephalograms and electrocardiograms. (7) Several models of isolated power systems, including those required under the 1971 National Electric Code, require special electrical receptacles, thus limiting the use of various appliances in a critical care unit. (8) Personnel have to be trained as to the nuances of isolated power systems, and as to the meaning of readings on the monitor. (9) Isolated power systems can give personnel a false security and cause carelessness in preventing the factors which could cause and electrical current to flow through a catheter. Except for electrically susceptible patients as described herein, there is no reason to require installation of isolated power sources in critical care units. Petitioners have contended that other regulations of the Department which relate to the setting of fire protection standards in hospitals constitute invalid exercises of delegated legislative authority. No evidence was presented as to how these standards specifically affect any of the Petitioners. No evidence was presented to establish that any of the Petitioners are in any way injured or adversely affected by the rules.

Florida Laws (3) 120.52120.56120.57
# 9
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs IVAN MCKINLEY, 07-002762 (2007)
Division of Administrative Hearings, Florida Filed:Inverness, Florida Jun. 20, 2007 Number: 07-002762 Latest Update: Dec. 18, 2007

The Issue What if any, disciplinary action may be taken against Respondent based on alleged violations of Florida Statutes Section 489.531(1) (practicing electrical contracting or advertising one's self or business organization as available to engage in electrical or alarm system contracting without being certified or registered), and Section 455.227(1)(q) (engaging in the practice of unlicensed electrical contracting after previously being issued an Order to Cease and Desist from the unlicensed practice of electrical contracting.)

Findings Of Fact At all times material hereto, Respondent was not licensed nor had he ever been licensed to engage in electrical contracting in the State of Florida. Mr. George Hammond lives in Inverness, Florida in a single family dwelling with a detached garage. The house is serviced with a water well and electrical pump. On July 25, 2006, Mr. Hammond notified a long-time friend, Dennis Himmel that he had problems with his well and could not get water into his home. Mr. Himmel temporarily ran a wire between the well and garage so Mr. Hammond could get water, and suggested Mr. Hammond hire an electrician to do the permanent work. A few days later, Mr. Hammond told his friend, Craig Zeedick, that his well had been hit by lightening and someone was fixing it. Mr. Zeedick went to Mr. Hammond's house and observed Respondent kneeling down and making an electrical connection with the junction box. Respondent had stripped off the wire connections and made the wire nut connection. A boy was with Respondent, and the boy was burying an electrical cable to the well. The cable in the ground had no tubing or protection around it. At Mr. Hammond's request, Mr. Zeedick counted out approximately $947.00 in cash to Respondent for the electrical work. Sometime in August 2006, Mr. Himmel observed the work done at Mr. Hammond's home. He phoned Respondent to complain because the wire from the garage to the well was buried only four inches underground with no conduit (protective covering) over the wire into the garage. Respondent returned and covered the wire with conduit but then the pump did not work. Later, Respondent corrected the wire box connection, blaming the problems on Mr. Himmel. At some point in these machinations, Respondent succeeded in flooding Mr. Hammond's garage with water. Amy Becker, a license inspector with the Citrus County Building Division performed an investigation of the electrical contracting work done by Respondent at Mr. Hammond's residence, and took photographs. At that time, Mr. Hammond pointed out electrical wiring running from the well to the garage, and Ms. Becker observed there was a conduit and some plastic tubing. Ms. Becker then checked Respondent's licensing status, and found him to be unlicensed as an electrical contractor by either the State or Citrus County. She notified Petitioner, as the State licensing agency. On December 13, 2006, Ms. Becker cited Respondent for unlicensed contracting in wiring the water well pump at Mr. Hammond's residence. Respondent appeared before the County Board on December 13, 2006, and signed the citation signifying he wanted an administrative hearing. On January 24, 2007, Respondent, represented by counsel, was present for testimony before the Board, and the Board upheld the citation against Respondent. Respondent paid the citation on May 29, 2007. Respondent admitted to Petitioner's Investigator, Sharon Philman, during a telephone interview, that he had run wire from Mr. Hammond's garage to the well pump, for which work he charged approximately $940.00. On or about February 13, 2007, Petitioner issued a Cease and Desist Order against Respondent. The instant complaint/case followed. Petitioner put on no evidence concerning a prior 2005 case against Respondent.1/

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation enter a final order: Finding Respondent guilty of having violated Section 489.531(1)(a), Florida Statutes, on one occasion, and assessing Respondent an administrative fine in the amount of $2,500.00 therefor, as permitted by Section 455.228(2), Florida Statutes. Finding Respondent not guilty of having violated Section 455.227(1)(q) as pled in Count II of the Administrative Complaint herein. DONE AND ENTERED this 19th day of September, 2007, in Tallahassee, Leon County, Florida. S ELLA JANE P. DAVIS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 2007.

Florida Laws (5) 120.569120.57455.227455.228489.531
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer