Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
ARLINGTON EAST CIVIC ASSOCIATION, ET AL. vs. JACKSONVILLE TRANSPORTATION AUTHORITY AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-001875 (1978)
Division of Administrative Hearings, Florida Number: 78-001875 Latest Update: May 14, 1979

Findings Of Fact The proposed project is a six-lane, combination low and high level bridge crossing Mill Cove and the St. John's River in Duval County, Florida. The project entails construction of approximately 6,000 feet of low level trestle-type bridge structure and approach spans beginning on the south side of Mill Cove and extending across the Cove to the northern edge of Quarantine Island, an artificial spoil island; 3,000 feet of high level bridge crossing the main channel of the St. John's River; and northern approach spans touching down on Dame Point on the northern shore of the St. John's River. In order to construct the proposed project, JTA is required to obtain a water quality permit and certification from DER. JTA filed its application with DER, accompanied by supporting data, including several studies performed by professional consultants. After review of the application, DHR filed notice of its intent to issue the requested water quality permit and certification, and Petitioners filed a timely request for a hearing pursuant to Section 120.57(1) Florida Statutes, to oppose the issuance of the permit and certification. Petitioners are various groups and individuals concerned about water quality in the St. John's River and the Jacksonville area. Petitioners' standing to seek relief in this proceeding was stipulated by all parties. Construction of the project will result in: filling of approximately .07 acres of wetlands to construct the south abutment on the shore of Mill Cove; dredging of approximately 185,000 cubic yards of material from Mill Cove to create a 4,400 foot long, 190 foot wide barge access channel, with a five foot navigation control depth parallel to the low level portion of the project; temporary filling of approximately .3 acres of wetlands above mean high water on the south shore of Quarantine Island to provide construction access to the island, which area is to be restored upon completion of construction; construction of a diked upland spoil containment site approximately 31 acres in size above mean high water on Quarantine Island to retain all dredge spoil associated with the project; construction of a temporary dock at the northern end of Quarantine Island for access and staging purposes, which is to be removed on project completion; and filling of approximately 16,000 cubic feet of material waterward of mean high water for rip-rap protection around main piers in the St. John's River. Dredged materials will be removed by hydraulic dredges. The St. John's River and its tributaries have been designated Class III waters by DER in the project area. The project involves dredging below mean high water and filling above mean high water, and is a dredge-and-fill project for purposes of Chapters 403 and 253, Florida Statutes, and Chapters 17-3 and 17-4, Florida Administrative Code, and is regulated by DER. The project is an element in a proposed eastern bypass around the City of Jacksonville. It is expected that, as a result of the project, existing area industry will receive more efficient transportation service, commuter trip miles from southeastern Jacksonville to northern Jacksonville will be reduced, transportation routes to education facilities will be improved, and tourist traffic will be routed around downtown Jacksonville, reducing miles traveled to nearby beach resorts and thereby relieving downtown congestion. The benefits to costs ratio of the project appears positive and beneficial to Duval County and Jacksonville, in that for every dollar spent to construct the project, $2.80 could be returned to the community in the form of increased economic activity and more efficient transportation. Testimony clearly established that the state waters in the project area are currently severely degraded and are not likely to meet Class III water quality standards. Violations of Class III standards for dissolved oxygen and some heavy metals, such as mercury, presently exist as background conditions in the St. John's River and Mill Cove. Further, a water quality analysis performed by DER in the project area indicates high background concentrations of heavy metals and PCB's in both the water column and sediments in the project area. When the pro posed project is analyzed within the context of these existing background water quality conditions, it appears highly unlikely that any impact from the project will further degrade existing conditions. The project as currently designed includes plans for total containment of spoil material resulting from dredging activity on the upland portions of Quarantine Island. There will be no direct discharge of dredge $materials from this containment area into the receiving waters of the state. JTA performed a water and sediment analysis of the project area, the purpose of which was to determine the existence and concentrations of specific pollutants that could adversely impact Class III waters if reintroduced into the aquatic system. JTA employed a consultant whose analytical program was designed in consultation with DER and complied with all standard testing procedures required by Rule 17-3.03, Florida Administrative Code. This analysis identified three primary-project activities where control of toxic and deleterious materials was critical: turbidity control; upland spoil containment; and direct discharge of spoil water to state waters. Sediments in the Mill Cove area are extremely fine and may be resuspended in the water column in quantities that could violate state water quality standards if dredging is done improperly. It appears from the evidence that any turbidity problem can be avoided by employing silt curtains and hydraulic dredging during channel excavation. Silt curtains should adequately retain turbidity below levels which would violate state water quality standards, in view of the fact that the JTA study hypothesized a "worst-case" condition for projecting turbidity and pollutant concentration by assuming no upland spoil containment, silt curtains or reasonable mixing zone. Although use of silt curtains and hydraulic dredging cannot absolutely guarantee zero-discharge of suspended sediments from the dredging area, the proposed system of turbidity control is adequate to provide reasonable assurance of non-violation of state water quality standards. Due to the existing toxic background conditions in Mill Cove, DER imposed a permit condition requiring spoil from dredging activities to be completely contained in an upland landfill-type site, with no overflow that could allow effluent to return to waters of the state. The upland dike system proposed in the project application is designed to retain all spoil material and water without direct discharge into state waters. Testimony established that the proposed dike system is designed to hold far more spoil material than the proposed project will generate. Although the dike system is to be constructed from dredged material previously deposited on Quarantine Island, it appears from the testimony that these materials were dredged from the main channel of the St. John's River and are cleaner and sandier in character than sediments in the Mill Cove area. The dike system, in conjunction with natural percolation and evaporation, is adequately designed to retain dredge spoil on the upland portion of Quarantine Island, and can reasonably be expected not to release toxic and deleterious substances into receiving waters of the state. It is also significant that a condition of the requested permit requires project water quality monitoring to afford continuing assurance that the project will not violate standards contained in Chapter 17-3, Florida Administrative Code. These standards and the conditions required to achieve them have been included in DER's letter of intent to issue the permit for this project. It is specifically concluded from the evidence that project dredging will not release toxic and deleterious substances into Class III waters in violation of state water quality standards, and that project dredging in Mill Cove incorporates reasonable safeguards for spoil disposal and turbidity control so as to assure non-violation of state water quality standards. JTA plans to use a direct discharge method to dispose of storm water from the bridge. Storm water will fall through 4-inch screened holes called "scuppers" placed at regular intervals along the bridge surface directly into either Mill Cove or the St. John's River. JTA was required to provide in its application reasonable assurance that storm water runoff from the Project would not exceed applicable state standards for turbidity, BOD, dissolved solids, zinc, polychlorinated biphenols, lead1 iron, oils or grease, mercury, cadmium and coliform. To this end, JTA submitted a study entitled Effect of Rainfall Runoff from Proposed Dame Point Bridge on Water Quality of St. John's River. This study analyzed the chemical composition of storm water runoff from an existing bridge, comparable in both size and design, to the proposed project, which crosses the St. John's River south of the City of Jacksonville. This study adequately established that storm water runoff into the St. John's River across the length of the proposed bridge will not degrade the water quality of the St. John's River below current water quality standards. All but three of the parameters tested in the study were within standards contained in Chapter 17-3, Florida Administrative Code. The remaining three pollutants were either not automobile-related, or would not violate applicable water quality standards after a reasonable opportunity" for mixing with receiving waters. One of these pollutants, mercury, is not automobile-related, and the concentration of mercury discovered in bridge runoff test samples was essentially the same as that measured in rainfall samples. The sampling for mercury was performed using the ultrasensitive "atomic absorption" method, which is capable of measuring tenths of a part per billion of mercury. Another method, the "Dithizone" method, is a technique recognized as effective by DER, and would have, if utilized, yielded a result within the "none detectable" standard contained in Rule 17-3.05(2) , Florida Administrative Code. As to the remaining two pollutants, coliform and lead, testimony established that a dilution rate of 400 to 1, after mixing with receiving waters, would not result in violation of applicable Class III water standards. Testimony also clearly established that water circulation in the project area would result in the requisite dilution ratio of approximately 400 to 1. The storm water runoff study was performed on a bridge similar in all important characteristics to the proposed project, and therefore validates the scientific methodology utilized to determine the expected impact of runoff from the proposed project on water quality in the St. John's River. The applicant has provided in its permit application the best practicable treatment available to protect state waters in the design of both the low and high level portions of the proposed bridge. Extensive research and analysis of design alternatives for both the low and high level portions of the bridge were undertaken by JTA and its consultants prior to selecting the proposed design for the bridge. JTA prepared and submitted to DER, as part of the application process, a document entitled Summary of Construction Techniques in Mill Cove, Dame Point Expressway. This document analyzed and summarized the available construction and design alternatives for the low level trestle portions of the project. The analysis included consideration of overhead construction, construction from a temporary wooden structure parallel to the project, and construction from barges using a shallow channel parallel to the project. The design chosen will cost more than one million dollars less than the next alternative, and will cut construction time by two years over the next alternative design. Given the demonstrated need for the proposed project, the already degraded water quality in the project area, the safeguards for water quality contained-in the project design, and the savings to be realized in both cost and time of construction, the design presently contained in the application is the best practicable. Both Petitioners and JTA have submitted proposed findings of fact. Petitioners' Proposed Findings of Fact numbered 1 through 4 have been substantially adopted herein. JTA's Proposed Findings of Fact numbered 1 through 7 have also been substantially adopted. To the extent that proposed findings of fact submitted by either Petitioners or JTA are not adopted in the Recommended Order, they have been specifically rejected as being either irrelevant to the issues in this cause, or as not having been supported by the evidence.

Florida Laws (5) 120.54120.57403.021403.061403.087
# 1
PUTNAM COUNTY ENVIRONMENTAL COUNCIL, INC.; STEWARDS OF THE ST. JOHNS RIVER, INC., AND LINDA YOUNG vs GEORGIA-PACIFIC CORPORATION AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 01-002442 (2001)
Division of Administrative Hearings, Florida Filed:Palatka, Florida Jun. 19, 2001 Number: 01-002442 Latest Update: Sep. 12, 2002

The Issue The issues are whether Georgia-Pacific Corporation is entitled to the issuance of an industrial wastewater facility permit under the National Pollutant Discharge Elimination System program that would authorize it to discharge industrial wastewater to the St. Johns River in Putnam County, Florida, and whether Georgia-Pacific Corporation has met the statutory criteria for a related administrative order for the interim discharge to Rice Creek in Putnam County, Florida.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: The Parties Respondent, Department of Environmental Protection (Department), is the state agency authorized under Chapter 403, Florida Statutes, to regulate discharges of wastes to waters of the State. Under approval from the United States Environmental Protection Agency (EPA), the Department administers the National Pollutant Discharge Elimination System (NPDES) permitting program in the State. The Department also enforces specific water quality standards that have to be achieved in order to ensure protection of the designated uses of surface waters in the State. Respondent, Georgia-Pacific Corporation (Georgia- Pacific), owns and operates a bleached and unbleached kraft pulp and paper mill in Putnam County, Florida. The plant presently discharges treated wastewater to Rice Creek, a Class III water of the State, and a tributary of the St. Johns River. Petitioner, Putnam County Environmental Council, Inc. (PCEC), alleged in the Petition for Formal Administrative Hearing (Petition) that it is a non-profit Florida corporation headquartered in Palatka, Florida. However, other than a statement by one witness that PCEC was incorporated on an undisclosed date prior to the hearing, PCEC failed to present any evidence to establish its corporate status or residency in the State of Florida. According to the same witness, the organization was created in an unincorporated status in 1991, and it currently has 65 members who use and enjoy the St. Johns River for recreational purposes. Petitioner, Stewards of the St. Johns River, Inc. (SSJR), also alleged in the Petition that it is a non-profit Florida corporation with headquarters in Jacksonville, Florida. Like PCEC, SSJR failed to prove its corporate status or residency in the State of Florida. Although the number of members in SSJR is unknown, "many" of its members are boaters and "most" live along the St. Johns River. Petitioner, Linda Young, is Southeast Regional Coordinator for the Clean Water Network and a citizen of the State of Florida. As such, she has standing to "intervene" in this action under Section 403.412(5), Florida Statutes. In this complex case, the parties have presented extensive and conflicting evidence regarding the factual issues raised by the pleadings. In resolving the numerous conflicts in that testimony, the undersigned has accepted the more credible and persuasive evidence, as set forth in the findings below. The Applicant's Mill Operation Georgia-Pacific's Palatka mill was built in the 1940's before the establishment of Department water quality standards and classifications. Because of the nature of the pulping process, the mill has not been able to fully meet water quality standards in Rice Creek because of poor dilution. Georgia-Pacific receives wood chips from a sister facility and purchases residual chips from local wood products facilities. Those chips are separated into pine and hardwood, conveyed into the pulp processing facility, and loaded into digesters, that is, industrial-sized pressure cookers, which cook the chips for several hours. Pulp from the digesters goes to the brown kraft, bleached kraft, and tissue manufacturing facilities. Water in the manufacturing process is used, re-used, and recirculated until it cannot be used again, at which point it is conveyed into a primary wastewater clarifier, which is used to settle out fiber and other settleable solids. Additional wastewater sources are collected in sumps located in the facility, which are discharged into the primary clarifier. The underflow from the primary clarifier flows into a solids settling area (sludge pond) while the water from the primary clarifier passes into a secondary treatment system. The secondary treatment system uses aerobic and facultative biological treatment. Stormwater at the facility also flows into the treatment system. The secondary treatment system consists of four ponds in series: Pond 1, 485 acres, aerated with over 1600 horsepower of aeration; Pond 2, 175 acres, with 140 horsepower of aeration; Pond 3, 130 acres, with 120 horsepower of aeration; and Pond 4, 100 acres. Pond 4 is a quiescent basin, used to settle solids in the wastewater before discharge. The treatment system has a very long hydraulic detention time; once water enters the system, it remains there for 50 to 60 days. After treatment, a side stream of roughly 8,000,000 gallons per day of treated effluent is withdrawn, oxygenated with liquid oxygen, and discharged at two locations in Rice Creek: 3.4 miles upstream from the St. Johns River (Outfall D-001); and 2.4 miles upstream from the St. Johns River (Outfall D-002). Under low flow conditions, effluent from the Georgia-Pacific mill dominates the flow in Rice Creek. The Application Process Rice Creek is a small tributary of the St. Johns River, particularly in its upper reaches where Georgia- Pacific's effluent discharge occurs. Over the years, there have been exceedances of certain Class III water quality standards including specific conductance, color, and periodically whole effluent toxicity. Because of this, and during the permit review process, the Department began considering alternatives for mitigating or eliminating those existing concerns with the facility's discharge. In October 1992, Georgia-Pacific applied to the Department for the renewal of its existing wastewater discharge permit. In June 1994, Georgia-Pacific submitted an application to the Department for the construction and operation of an industrial wastewater treatment and disposal system. This application included a request to relocate Georgia-Pacific’s existing discharge to the St. Johns River. Because Georgia-Pacific submitted timely permit applications, it is authorized to continue operations based on an "administratively extended permit." In June 1994, Georgia-Pacific also applied to the EPA for a permit under the NPDES program. In October 1994, the EPA acknowledged receipt of a timely application for the renewal of Georgia-Pacific's existing NPDES permit, advising Georgia-Pacific by letter that its permit was automatically extended and that continued operation was authorized in accordance with the existing permit and 5 U.S.C. Section 558(c). On May 24, 1995, the Department advised Georgia- Pacific that the EPA had granted the Department the authority to administer the NPDES program and that its state permit and existing NPDES permit were deemed combined into one order. In response to a Department request, in November 1995, Georgia-Pacific submitted to the Department an antidegradation review for the relocation of its discharge. After Georgia-Pacific applied to the Department for a renewal of its NPDES permit, the Department directed Georgia-Pacific to provide alternatives that would ensure compliance with water quality standards. Georgia-Pacific submitted a proposal to construct a pipeline that would enable it to discharge its effluent to the middle of the St. Johns River. Under that proposal, Georgia-Pacific would achieve compliance with water quality standards as a result of greater dilution in the St. Johns River. Based on a review of Georgia-Pacific's submittal, the Department determined that Georgia-Pacific could in fact achieve water quality standards by constructing a pipeline to the St. Johns River. Likewise, the EPA concluded that Georgia-Pacific could receive a permit to discharge to the St. Johns River through a pipeline, without additional process improvements. Although the Department concluded that compliance could be achieved solely by the construction of a pipeline, it began discussions with Georgia-Pacific and EPA in order to examine other approaches that might lead to compliance in Rice Creek. These discussions culminated in a decision that Georgia-Pacific would invest substantial funds in the installation of additional technology and also be assured of some ultimate means to achieve compliance with water quality standards. On May 1, 2001, the Department issued a Notice of Intent to Issue an industrial wastewater permit, together with an Order Establishing Compliance Schedules Under 403.088(2)(f), Florida Statutes (the Administrative Order). In late January 2002, Georgia-Pacific submitted a request to the Department asking for consideration of two changes to the proposed permit: first, a request to relocate a groundwater monitoring well; and second, a request to review the Department's proposed mixing zone in the St. Johns River for the transparency standard. The Department also proposes a minor change in permit conditions to allow approval of the bleach plant monitoring plan to take place within sixty days after the issuance of the final permit. Both of Georgia- Pacific's requests were reviewed by the Department, and it has recommended that they be included in the proposed permit. Technology-Based Effluent Limits and Water Quality- Based Effluent Limits When considering a permit application such as the one here, the Department reviews the application to determine compliance with technology-based effluent limits (TBELs) and water quality-based effluent limits (WQBELs). TBELs are minimum industry standards that all facilities must meet regardless of their discharge location. They are predominantly production-based, and they limit the mass of pollutants that may be discharged based on the mass of product produced. Those limits generally reflect EPA's assessment of the industry standard regarding what can be met in a given discharge. In the preparation of a permit, the Department practice is to first determine the TBELs that would apply. In contrast, a WQBEL reflects how low the discharge must be (or how effective treatment must be) for a given parameter to meet water quality standards. Relief mechanisms such as mixing zones are inherent in WQBELs. A WQBEL is necessary only for those parameters for which there is a reasonable potential for the facility either to exceed the water quality standard or come close to exceeding the standard. As a matter of agency practice, the Department does not impose a limit unless there is a reasonable potential to exceed a standard. In order to determine whether there is such a reasonable potential for exceeding a standard, the Department will review past operations and other information it may have regarding the characteristics of the discharge. For a discharge such as the one proposed in the present case, a "Level II" WQBEL is required. The Department's Point Source Section, with expertise in the field of water quality modeling, analyzes the Level II WQBEL. Georgia-Pacific must meet certain technology-based standards, such as those set forth in the Cluster Rule. The Cluster Rule has been promulgated by the EPA and adopted by the Department and requires the installation of technologies to eliminate the use of elemental chlorine in the bleaching process. The Palatka facility far exceeds (performs better than) technology-based effluent limits. In March 1998, the Department created a document titled "Level II Water Quality Based Effluent Limitations for the Georgia Pacific Corp. Palatka Mill" (the WQBEL Technical Report]. The WQBEL Technical Report has a typed notation on the title page reading "March 1998 -- Final." The WQBEL Technical Report contained the following effluent discharge limitations: The following are the effluent limitations for the Georgia-Pacific Palatka mill discharge to the St. Johns River based upon results from the Level II WQBEL. Review comments from EPA Region 4 are included in the correspondence section. Parameter Limitation Discharge 60 MGD Daily Maximum BOD5 Summer (June 1 - November 30) 3,500 lbs/day maximum thirty day average Winter (December 1 – May 31) 7,170 lbs/day maximum thirty day average TSS Summer (June 1 - November 30) 5,000 lbs/day maximum thirty day average Winter (December 1 – May 31) 10,000 lbs/day maximum thirty day average Dissolved Oxygen 2.7 mg/l minimum Specific conductance 3,220 umhos/cm daily maximum Un-Ionized Ammonia Nitrogen Summer (June 1 - November 30) .11 ug/l daily maximum Winter (December 1 – May 31) .13 ug/l daily maximum Iron (Total Recoverable) 2.91 mg/l daily maximum Cadmium (Total Recoverable) 3.46 ug/l daily maximum Lead (Total Recoverable) 5.87 ug/l daily maximum Zinc (Total Recoverable) 480 ug/l daily maximum When the WQBEL Technical Report was approved in 1998, the Department's Northeast District Office did not prepare a separate formal notice of approval. The WQBEL Technical Report was transmitted by memorandum from the Water Quality Assessment Section to the Department's Director of District Management for the Northeast District on April 13, 1998, where it remained on file. The WQBEL Technical Report complied with the plan of study previously approved by the Department, and it met the requirements of Rule 62-650.500, Florida Administrative Code. Both the Department and EPA staff concurred with the approval of the WQBEL Technical Report. They agreed that the construction of a pipeline and the relocation of the discharge to the St. Johns River would yield a net environmental benefit without additional process improvements. Upgrades Implemented and Required in the Proposed Agency Actions As described more fully below, Georgia-Pacific has modified its production and treatment processes in such a manner as to improve its overall environmental performance. In installing some of those modifications, Georgia-Pacific undertook what was required by federal and state law. For others, Georgia-Pacific has exceeded what it was required to do under state or federal law. To comply with the Cluster Rule, Georgia-Pacific eliminated two bleach plants and installed a new bleach plant, one which uses chlorine dioxide as opposed to elemental chlorine. The implementation of this technology is primarily aimed at eliminating the mechanism for the formation of dioxin in the bleaching plant. Compliance with the Cluster Rule generally requires, among other things, conversion to an elemental chlorine-free bleaching system. Georgia-Pacific is in compliance with the Cluster Rule. Under the Cluster Rule, Georgia-Pacific is required to sample for dioxin at its bleach plant, with a limit of under 10 picograms per liter. Georgia-Pacific has experienced reductions in the color of its effluent as the result of the chlorine dioxide conversion as well as reductions in specific conductance. The reductions in specific conductance are particularly significant because Georgia-Pacific has decreased its effluent flow, which would ordinarily increase specific conductance in the absence of additional improvements. After conversion to chlorine dioxide, Georgia- Pacific began monitoring for parameters defined by the Cluster Rule. In that monitoring, Georgia-Pacific has tested "non- detect" for dioxin and chlorinated phenolics. Specifically, Georgia-Pacific has monitored dioxin in its effluent, as well as within its process –- before dilution with other wastewater –- and the monitoring results at both locations are likewise "non-detect" for dioxin. Furthermore, levels of chloroform and adsorbable organic halides (AOX) have been well within the limits imposed by the proposed permit and the Cluster Rule. Georgia-Pacific has voluntarily agreed to install by April 15, 2006, an oxygen delignification system, or a like system that produces similar or better environmental benefits. Oxygen delignification is a precursor to bleaching, which removes lignins from the fiber before the product is bleached. This process is significant because lignin consumes chemicals, impedes bleaching, and prohibits achieving brightness targets in the bleach plant. The cost associated with the oxygen delignification system is $22,700,000. This commitment is reflected in the proposed Administrative Order and Permit. Oxygen delignification has been identified as having significant benefits in terms of reducing the color and specific conductance of effluent. Georgia-Pacific voluntarily agreed to install by August 15, 2003, a new brownstock washing system to replace four existing brownstock washing lines. A brownstock washer is a piece of equipment that washes organics away from fiber, after pulping and before oxygen delignification. The cost of this equipment is approximately $30,000,000. This commitment is reflected in the Administrative Order and Permit. The new brownstock washers are not required by Department rules, but they will be helpful in reducing the specific conductance of effluent. Georgia-Pacific has also voluntarily agreed to install a green liquor dregs filter. This system would remove dregs from the effluent system and reduce specific conductance and color in the effluent. The cost of the green liquor dregs filter is $1,100,000. This commitment is reflected in the Administrative Order and Permit. Under the proposed agency action, Georgia-Pacific is likewise required to install additional equipment for the implementation of its best management practices program to minimize leaks and spills in the process sewer. This equipment, including controls on the brownstock washer system, and the installation of a spill control system, pumps, and piping, has been installed at a cost of $7,100,000. Georgia-Pacific has also optimized the performance of its treatment system through the relocation of its aerators in the treatment ponds and modifying its nutrient feed system. This has led to reduced levels of biological oxygen demand (BOD) in the discharge, as well as improved treatment for total suspended solids. In addition, Georgia-Pacific has voluntarily installed a reverse osmosis system to recycle certain internal streams, which in turn has led to reductions in specific conductance, at a cost of $3,300,000. To comply with the proposed agency actions, Georgia- Pacific expects to expend a total of approximately $170,000,000 for upgrades for the purpose of producing environmental benefits. Additional money is earmarked for other environmental performance issues, such as water conservation. Except for technology-based limits adopted by rule, the Department does not dictate how a facility achieves compliance with water quality standards. Georgia-Pacific demonstrated that its environmental performance is substantially better than required by technology-based limits. Based on the foregoing, it is reasonable to find that Georgia-Pacific’s commitments to process improvements will lead to a general improvement in water quality in the receiving waters. Relocation of the Discharge As noted above, because of the minimal dilution available in Rice Creek, Georgia-Pacific has never been fully able to achieve water quality standards in Rice Creek, a Class III water body. Rice Creek continues to exceed water quality criteria for specific conductance and color; historically, the discharge had experienced exceedences for the chronic toxicity criterion. Under present conditions, with Georgia-Pacific discharging to Rice Creek and Rice Creek flowing to the St. Johns River, elevated levels of color are experienced along the shoreline of the St. Johns River in the area of existing grass beds. Modeling shows that under current flow conditions from Rice Creek, those color effects are observed on the northwest bank near the confluence of Rice Creek with the St. Johns River. If the discharge is relocated to the St. Johns River and discharged near the river bottom through a diffuser, it will beneficially change the distribution of color impacts both to Rice Creek and the St. Johns River. Color in Rice Creek will improve, returning to its background color of 100 to 150 platinum cobalt units (pcu). Specific conductance within Rice Creek will also be markedly reduced. Because the input will occur in the middle of the St. Johns River, with higher flows and greater turbulence, there will no longer be relatively highly colored water flowing along the shoreline. Therefore, the relocation will provide a significant benefit of moving highly colored water away from grass beds and will mitigate against any existing effects on those grass beds. It is beneficial to relocate discharges to the middle of a stream, as opposed to the edge of a shoreline, where effluent tends to hug the shoreline. Therefore, regardless of the process improvements, there will be a net environmental improvement by relocating the discharge to the middle of the St. Johns River The discharge from the proposed diffuser will be comparatively benign, in comparison to the present flow from Rice Creek into the St. Johns River. This is because the effluent would not reach or hug the shoreline in such a scenario but rather would be diluted in rising to the surface, as well as by its lateral movement in the direction toward the river bank. The relocation of the discharge to the middle of the St. Johns River will cause improvements through localized changes in concentrations near the diffuser and the confluence of Rice Creek and the St. Johns River. Based on the foregoing, it is found that Georgia- Pacific’s proposed discharge into the St. Johns River will not result in water quality degradation, but will instead lead to a general improvement in water quality. Proposed Conditions in the Permit and Administrative Order Before certifying completion of the required manufacturing process improvements, Georgia-Pacific is required to submit to the Department a report on its ability to optimize the modifications, as well as a separate report which would determine whether Georgia-Pacific can meet certain limits that would enable a continuing discharge to Rice Creek. If the water quality improvements are sufficient to achieve standards in Rice Creek, the permit would be reopened and Georgia-Pacific would be required to maintain the present discharge location to Rice Creek. Otherwise, Georgia-Pacific would be authorized to construct the pipeline to the St. Johns River. The permit is drafted so that Georgia-Pacific will verify the need for mixing zones, as well as the dimensions of proposed mixing zones, after process improvements are complete. The Administrative Order imposes interim effluent limitations during the compliance period described in that Order. The Administrative Order contains "report-only" conditions for certain parameters. For those parameters which do not have interim limits, there is no appropriate standard to apply because information on effluent and water quality conditions is incomplete. The Department also found it unreasonable to impose interim limits that will be met only after Georgia-Pacific completes the improvements requested by the Department. Under Department practice, it is reasonable to impose "report only" conditions for parameters when it is unclear whether the discharge for the facility presents a concern for potential exceedences of water quality standards. In addition, "report only" conditions are used when a facility is undertaking an effort to address problems for certain parameters during a period necessary to achieve compliance. The proposed permit includes mixing zones in the St. Johns River for dissolved oxygen, total recoverable iron, total recoverable cadmium, total recoverable lead, un-ionized ammonia, turbidity, and specific conductance. The length of each of those mixing zones is 16.5 meters, that is, limited to the rise of plume. A mixing zone is also required for transparency, which will require a length of 734 meters. Within 12 months after certifying completion of the manufacturing process improvements, Georgia-Pacific will be required to re-evaluate the need for mixing zones and effluent limits and re-open the permit as necessary to include final mixing zones, effluent limits, and monitoring requirements. Compliance with Ambient Water Quality Standards The Petition contends that Georgia-Pacific has not provided reasonable assurances that it would comply with the following standards: nutrients (paragraph 18); dissolved oxygen (paragraph 20); chronic toxicity (paragraph 21); total suspended solids (paragraph 23); iron (paragraph 25); and phenolic compounds (paragraph 26). Although no water quality standard is directly applicable, Petitioners also addressed the following water quality issues: biological oxygen demand (BOD) (paragraph 20); dioxin, "related compounds," chlorinated organics, AOX, and chemical oxygen demand (COD) (paragraph 22); color (paragraph 24); and total suspended solids (TSS), which is alleged to include total organic carbon (TOC) (paragraph 94). Petitioners asserted that dioxin, chlorinated organics, TSS, and AOX are significant in considering compliance with the "free-from" standard in Rules 62- 302.500(1) and 62-302.530. In determining whether water quality standards will be met, those allegations should only be considered in reference to those adopted standards for the "free-from" standard. The effluent data establishes that Georgia-Pacific will consistently meet the proposed permit limits for discharge to Rice Creek. Georgia-Pacific's treatment facility has the capacity to comply with the proposed permit limits for discharge to Rice Creek, and there is a very high degree of assurance that it has the capability to comply with those standards in the future. In addition, Georgia-Pacific's treatment facility is able to meet the WQBELs established for discharge into the St. Johns River. Evaluation and modeling demonstrate that if a discharge to the St. Johns River is undertaken, the St. Johns River will meet Class III water standards at the edge of the mixing zone if Georgia-Pacific complies with its proposed effluent limits. Also, the effluent will meet all applicable effluent guidelines and technology-based standards adopted in the Florida Administrative Code. The effluent will not settle, form deposits, or create a nuisance, and it will not float as debris, scum, or oil. Finally, the effluent will not produce color, odor, taste, or other conditions so as to create a nuisance. Georgia-Pacific performed an analysis to determine the effluent limits that would be necessary to achieve water quality standards. This analysis included water quality modeling, which is a method of summing up inputs and losses, calculating the amount of material in a system, and determining the concentration of a substance. The model was used to geometrically represent the St. Johns River, Etonia Creek, and the reach of the St. Johns River within the study area, which extended from Buffalo Bluff (15 miles upstream of the confluence of Rice Creek and the St. Johns River) to Mile Point 50. Rice Creek enters the St. Johns River at Mile Point 74. When a model is performed, the model will yield estimates or predictions of concentrations throughout a water body. Those predictions can be compared to field observations and measurements; if the model is done properly, the calculated numbers should agree with the measured numbers. Modeling is used to evaluate future conditions based on hypothetical future changes to the system. The modeling methods and advanced time-variable models employed by Georgia- Pacific's consultants were approved by the Department. Georgia-Pacific prepared a plan of study to obtain field data in the St. Johns River for the purpose of assuring that the models would simulate observed concentrations of constituents. The Department approved that plan of study and published a notice of approval. The Department also approved the quality assurance project plan for the collection of water quality data in Georgia-Pacific's modeling efforts. After approval of the plan of study and quality assurance project plan, Georgia-Pacific's consultants performed water quality surveys in November 1994 and May 1995. The models employed by Georgia-Pacific's consultants were calibrated and produced the observed water quality results. The proposed diffuser would be located about one foot from the bottom of the channel. As designed, the plume would leave the proposed diffuser and spread out, with the upper part of the plume going to the surface of the water. The plume model calculates the dilution at the centerline of the plume, where there would be a minimum of dilution. This method of using the centerline as a reference point leads to a conservative analysis, and it would require the Applicant to achieve more dilution than might otherwise be necessary to achieve water quality standards. For regulatory purposes, the Department usually uses the maximum height of the rise of the plume to determine a mixing zone, the point at which concentrations along the centerline of the plume would level off. Because of that practice, for certain parameters where the required mixing zone is less than the distance of the rise of the plume, a decrease in effluent limits would not lead to a decrease in the size of the mixing zone. Tidal actions will cause re-entrainment, that is, the movement of dissolved substances back into the plume area. This factor reduces the dilution factor that otherwise would apply to the system. This factor is accounted for in modeling by tying in a diffuser computation to a water quality model. The modeling employed by Georgia-Pacific assumes 7Q10 conditions, that is, a conservative assumption that flow is equal to the lowest one-week average for a ten-year period, where there is little dilution. The employment of this conservative method would minimize the probability of exceedences in the receiving water body. The projection employed by Georgia-Pacific's consultants was even more conservative because the 7Q10 flow rate is assumed to apply through a 60-day average flow, a condition that may never occur, and would not be expected to occur once in ten years. In contrast, the use of time-variable simulations would lead to less stringent permitting requirements. The permit provides reasonable assurance that the construction, modification, or operation of the treatment system will not discharge or cause pollution in violation of Department standards. The permit provides reasonable assurance that, based on the effluent limitations determined by the Department in the WQBEL Technical Report, water quality standards would be met outside the area of the proposed mixing zone for specific conductance, dissolved oxygen, un-ionized ammonia, iron, cadmium, lead, and zinc. Based on additional analysis as reflected in Georgia-Pacific's proposed amendment to the draft permit, Georgia-Pacific would achieve compliance with the transparency standard with the mixing zone described in its proposed amendment, that is, with a total length of 734 meters. The chronic toxicity criterion is a biological measurement which determines whether organisms are impaired by effluent. If impairment is demonstrated, the test does not indicate what component of the effluent is causing the effect. Georgia-Pacific is required to conduct testing for acute and chronic toxicity twice a year. Current tests undertaken in May and October 2001 are representative of effluent conditions after Georgia-Pacific undertook conversion of the bleach plant to chlorine dioxide. Those tests demonstrate that Georgia-Pacific is in compliance with the acute and chronic toxicity criterion since the conversion to chlorine dioxide bleaching. Georgia-Pacific is also in compliance with the biological integrity standard, based on the most recent fifth-year inspection. Because of the flow characteristics and the characteristics of pulp mill effluent, the pollutants associated with the effluent are not assimilated as the effluent travels from the point of discharge, through Rice Creek, to the St. Johns River. The particulates associated with pulp mill effluent are so small or fine that they will remain in suspension and thus not settle out in Rice Creek. In addition, because Rice Creek is channelized, there is no sloping side that would enable the growth of vegetation that would filter the water. Furthermore, even if there was a sedimentation process occurring in Rice Creek, no additional sedimentation would occur after the system reaches an equilibrium point. Although Rice Creek does cause a small decrease in BOD through oxidation, Georgia-Pacific has compensated for that factor by the injection of oxygen in the effluent. Thus, the direct piping of effluent to the St. Johns River (as opposed to a discharge into Rice Creek, which flows into the St. Johns River) would not result in any significant increase in pollutant loading to the St. Johns River. In addition, the construction of a pipeline would take place only after additional technologies have been implemented to maximize pollutant reduction. Compliance with the Reasonable Assurance Standard Georgia-Pacific has provided reasonable assurances for the proposed permit to be issued for a discharge into the St. Johns River. This finding is based upon Georgia-Pacific's ability to meet the effluent standards described in the draft permit, and modeling results demonstrating that, with the proposed mixing zones for certain parameters, a discharge into St. Johns River, as designed, will not result in a violation of Class III standards. Mixing Zones In Section H of their Petition, Petitioners challenged the proposed mixing zones set forth in the proposed Permit. Petitioners generally alleged that the proposed mixing zones were "enormous" and that they failed to comply with certain rules restricting mixing zones. In their Petition, Petitioners articulated three theories to support the proposition that the mixing zones were illegal: first, that the mixing zones would include a nursery area of indigenous aquatic life, including beds of aquatic plants of the type listed in Rule 63-302.200(16); second, that the mixing zone, by itself, would lead to a violation of the minimum criteria in Rule 62-302.500; and third, that the mixing zones, or a combination of those mixing zones, would result in a significant impairment of Class III uses in the St. Johns River. Petitioners were authorized to amend their Petition to add additional allegations to paragraphs 17 and 67 of their original Petition regarding the mixing zone. Under those amendments, Petitioners alleged that Georgia-Pacific’s proposed amendment to the draft permit would (a) improperly expand the mixing zone; (b) fail to account for the length of the diffuser; (c) improperly substitute "transparency" for "color"; and (d) prevent isolation of transparency impacts from color in the discharge. However, there is no evidence which ties those allegations to any regulatory standard that would affect the proposed agency action. Petitioners also contended that color was a surrogate for chemical oxygen demand, as well as for substances that are alleged to cause chronic or acute toxicity. However, as shown by the testimony of Department witness Maher, the permit condition for "color" was a surrogate only for the transparency standard. No evidence to support a contrary inference was presented. Petitioners also made general allegations that the proposed mixing zones are illegal, without a clear indication of what is deemed illegal about the mixing zones. Although the Petition includes a general argument in opposition to mixing zones, Petitioners were unable to suggest a legal basis for alleging that the mixing zones were illegal. For example, Petitioners alleged that certain mixing zones are enormous but failed to articulate why they are so enormous as to be illegal. They did not allege that the Department had erred by allowing a larger mixing zone than Georgia-Pacific should have received under applicable rules. Indeed, such a position would be antithetical to Petitioners' allegations that Georgia-Pacific had failed to achieve water quality standards for a number of parameters. The accepted testimony establishes that Georgia-Pacific's proposed mixing zones will comply with Department rules. No persuasive evidence was presented to the contrary. Because the effluent quality will differ from present conditions after completion of the process improvements, the proposed mixing zones will not be final until after process improvements have been made, the operation has been stabilized, and the mixing zones have been re- verified. No mixing zones are authorized in the Administrative Order. The Administrative Order contains a table setting forth potential mixing zones that are used as a benchmark to determine whether Georgia-Pacific can meet water quality standards in Rice Creek. The table sets out a series of hypothetical mixing zones at 800 meters, that is, the maximum presumptive distance afforded without additional relief mechanisms. Because no mixing zones are proposed to take effect in Rice Creek, there can be no issue of "illegal" mixing zones in Rice Creek. Within a range of potential discharge flows, from 20 MGD to 60 MGD, water quality standards will be met within the area of the proposed mixing zones for all parameters for which mixing zones are required. Mixing zones are allowed by Department rules and are considered a part of Florida water quality standards. In the context of the Department's permitting review, if a modeling analysis shows that the concentration of a pollutant in effluent is greater than the water quality criterion, the Department will determine if the amount of dilution in the receiving water is sufficient to assimilate the pollutants of concern. The Department will then determine either the length (in the case of a river) or area (in the case of an estuary) of a water body that would be necessary to achieve compliance through dilution. Based on chloride levels, the St. Johns River at the area of concern would not be considered an estuary under Department rules. Each of the proposed mixing zones would be less than 800 meters in length (as allowed by Department rule) and less than 125,600 square meters in area (a limitation that would apply only if the area was an estuary). The proposed discharge will comply with all minimum rule requirements with respect to mixing zones, such as those for dissolved oxygen, turbidity, and the absence of acute toxicity. Likewise, the proposed mixing zones will not impact any nursery areas for indigenous aquatic life. Nutrient Issues In Section I, Petitioners contested the Department's decision to not require effluent limits to prevent a violation of the narrative water quality criterion for nutrients. For reasons addressed in the undersigned's Order dated February 14, 2002, that issue is waived based because of Petitioners' failure to file a timely challenge to the WQBEL Technical Report. In addition, based on the findings set out below, Georgia-Pacific has provided reasonable assurances that it will not violate the narrative standard for nutrients. Further, the evidence shows that effluent limits for nutrients are not presently warranted. Petitioners presented testimony that the St. Johns River may be nitrogen-limited or phosphorous-limited at different times of the year, which means that concentrations of one or the other would limit algae growth at different times of the year. Relative light levels, as well as the penetration of light, also affect algae growth. Georgia-Pacific’s treatment system requires the addition of ammonia because ammonia or nitrate is a necessary nutrient for the growth of bacteria in the treatment system. Ammonia and nitrate are both nutrients. Although there can be a conversion from one form to the other, that conversion does not affect the net loss or gain of nutrients. Although nutrient issues are of concern to water bodies, it is absolutely necessary in a biological treatment system to have sufficient nutrients for the operation of the system to treat parameters such as BOD. The Georgia-Pacific facility is achieving a high level of treatment while managing its system at a minimum level of nutrient addition. Management of a treatment system requires attention not only to the influent and effluent, but also monitoring of conditions within the system itself to assure adequate treatment. Georgia-Pacific is continuing to refine its procedures for doing so. The State has adopted what is referred to as the "5- 5-3-1" (advanced wastewater treatment) limitation for municipal treatment plants that discharge to surface waters. This standard refers to five milligrams per liter for BOD, five milligrams per liter for suspended solids, three milligrams per liter for total nitrogen, and one milligram per liter for total phosphorous. This limitation has been in effect for many years and remains one of the most stringent state standards in the nation. Georgia-Pacific's facility would be in compliance with those standards for nitrogen and phosphorous. Effluent from the Georgia-Pacific mill increases the concentration of total nitrogen in Rice Creek, relative to background conditions. However, because of the relatively higher flow of the St. Johns River, when the load from the mill is transported to the St. Johns River, the increase in nitrogen concentration is so small as to be imperceptible. Nitrogen loading from Georgia-Pacific's Palatka mill on a long-term average (prior to upgrades of its treatment plant) has been measured at 1,196 pounds per day. The average loading at Buffalo Bluff, which is far upstream of Rice Creek and the Georgia-Pacific Palatka mill, is 36,615 pounds per day. Additional nonpoint sources contribute approximately 12,000 pounds per day in the study area. Thus, the loading from the Georgia-Pacific mill represents a 2.4 percent increase in nitrogen levels on the St. Johns River, a difference that cannot be measured. The largest point source of nutrients in the lower St. Johns River is the Buckman wastewater treatment plant in Duval County. That facility does not have nutrient limits on its discharge permit. Rice Creek does not provide any treatment (as opposed to dilution) for nitrogen in Georgia-Pacific's effluent. A review of probability distributions for nitrogen concentrations upstream and downstream of Rice Creek demonstrated that Rice Creek had no influence on nitrogen levels in the St. Johns River. Phosphorous concentrations from the effluent, if discharged to the St. Johns River, would dilute rapidly, decreasing to .2 milligrams per liter within the water column, five to six feet below the surface, after discharge from the diffuser, below the area in which light is absorbed at the surface of the water column. Chlorophyll-A is a parameter that is typically used as a measure of phytoplankton in the water column. Concentration distributions for chlorophyll-A at Buffalo Point (upstream of Rice Creek) matched concentrations for the same parameter at Racey Point, a station far downstream of Rice Creek. This analysis confirms that the inputs coming into the St. Johns River System from Rice Creek do not have a significant influence on the water quality of the St. Johns River, with respect to nutrients. With a discharge coming directly to the St. Johns River, and with nutrient loading being the same as from Rice Creek, the nutrient loading would not influence the St. Johns River. The Department does not have sufficient information at the present to impose a nutrient limit on Georgia-Pacific. The draft permit accounts for this issue through a re-opener clause which would authorize a limit when that information is available, if such a limit is necessary. Allegations Regarding "Deformities in Fish" Section J of the Petition includes allegations that Georgia-Pacific failed to provide reasonable assurances regarding adverse physiological response in animals under Rule 62-302.530(62), and that Georgia-Pacific has failed to provide reasonable assurances that its discharge will not be mutagenic or teratogenic to significant, locally occurring wildlife or aquatic species, or to human beings, under Rule 62- 302.500(1)(a)5. Petitioners suggest that the permit cannot be granted as proposed because it lacks effluent limits for (unstated) substances that are alleged to create potential violations of the free-from standard. This argument is barred as a matter of law for the reasons stated in the Order dated February 14, 2002. In addition, based on the following findings, this argument has been rejected because Georgia- Pacific has met the reasonable assurances standard without effluent limits on those unstated (and unknown) substances that are alleged to cause violations of those rules. Petitioners presented evidence that paper mill effluent in general contains chemicals which could cause the masculinization of the females in certain fish species, as well as hormonal effects in males. However, witness Koenig did not offer any testimony that Georgia-Pacific’s effluent, in particular, contained such chemicals. Dr. Koenig had collected no data and had not conducted any field studies in Rice Creek to support his testimony; rather, he relied on articles published by others and provided by Petitioner Linda Young. In agency practice and interpretation of the free- from standard in Rule 62-302.530(62), Florida Administrative Code, the question of whether a change is adverse depends on the overall community or population of that particular species. Tellingly, Petitioners did not present any competent evidence, through Dr. Koenig's testimony or otherwise, that Georgia-Pacific's effluent presents the potential for adverse effects on the overall community or population of any species. Dr. Koenig testified at length from his reading of studies performed by other scientists regarding changes in the hormone levels and gonadosomatic index (the relative weight of gonads) of fish in the St. Johns River in the vicinity of Rice Creek. In his testimony, Dr. Koenig relied on two published articles to address conditions in the vicinity of Rice Creek, both of which were primarily authored by M. Sepulveda. One of those articles showed hormonal changes taking place in a laboratory study where largemouth bass were exposed to mill effluent. That study also showed a change in the gonadosomatic index in the subject fish. Dr. Koenig did not offer any opinion that such changes would be adverse or that they would affect the reproduction of those fish. The other study was a field study with samples of fish at various regions in the vicinity of Rice Creek. This study did not include any fish from Rice Creek, but did include fish from the confluence of Rice Creek and the St. Johns River, as opposed to reference streams. The study showed lower levels of hormones in fish from the area of that confluence, but also showed similar effects at a reference stream 40 kilometers away. No testimony was presented to support the inference that the effects represented in the two studies were adverse, within the meaning of the free-from rule. Moreover, the data from those two studies were collected in 1996, 1997, and 1998, or before Georgia-Pacific converted its bleach plant to chlorine dioxide bleaching in March 2001. Therefore, Dr. Koenig had no data to support any theory that under current effluent conditions, Georgia-Pacific is producing or will produce compounds that would cause any changes of hormone concentrations in fish. With respect to the phenomenon of fish masculinization in Rice Creek, Petitioners' experts had no data to support a competent opinion on this subject. To support his testimony, Dr. Koenig only read one article that purported to demonstrate fish masculinization in 11-Mile Creek and the Fenholloway River, and one letter from an employee of the St. Johns River Water Management District [Young Exhibit 8A] that referred to "external anatomical anomalies" near Georgia-Pacific discharge points. The article attached to that letter and included in Young Exhibit 8A addressed data collected in Escambia County, and does not address conditions in Rice Creek. Petitioners attempted to present the theory that the potential for endocrine disruption or fish masculinization resulting from paper mill effluent would violate the free-from standard. As a condition to issuance of the permit, the Department proposes to require Georgia-Pacific to obtain approval of a plan of study to analyze the potential for significant masculinization effects from the discharge. Under the proposed conditions, Georgia-Pacific is required to determine the minimum concentration at which such effects may be detected. By its terms, the proposed permit may be reopened to adjust effluent limitations or monitoring requirements if the masculinization study shows a need for them. Department witness Brooks acknowledged a general concern for endocrine disruption resulting from paper mill effluent. In particular, Mr. Brooks referred to studies which showed that paper mill effluent could cause the elongation of an anal fin in the females of certain fish species. However, Mr. Brooks observed that although this appeared to be a physiologic response, there was no evidence or reason to believe that this effect was an adverse effect. Reports regarding masculinization, that is, the elongation of anal fins in female fish, are suspect because (among other reasons) the studies do not account for variances that would be expected based on the independent variables of sex, age, and growth. In any case, the data from those reports do not demonstrate significant, adverse effects in exposed populations. A critical and unbiased review of the published literature shows that impacts of masculinization are biologically interesting but preliminary in nature. Department witness Maher observed that the masculinization effect occurs naturally, and that the Department's plan of study is intended to determine whether this natural phenomenon becomes problematic or is enhanced by activity at the mill. Initial information reviewed by the Department indicates that the phenomenon is no longer experienced when a mill converts to a chlorine dioxide (ECF) bleaching process, as Georgia-Pacific has done in converting to ECF. According to witness Brooks, the observed effect known as "fish masculinization" is not confirmed to result from endocrine disruption. The Department has concluded that it has reason to be concerned about the potential for fish masculinization. From the Department's viewpoint, it is not clearly understood what is causing this effect. It has been shown that there is a direct relationship between concentration (or dilution) and the observation of those effects. This conclusion is consistent with Dr. Koenig's testimony, which observed a decline in observed effects based on the dosage or concentration of effluent. The Department has reviewed evidence showing that, with dilution, the effect of fish masculinization "go[es] away." In the Department's analysis of the fish masculinization issue in the present permit, the Department is requiring process improvements that would reduce this phenomenon, if it exists, in Rice Creek. In addition, if the discharge is relocated to the St. Johns River, the additional dilution would ameliorate the concern regarding fish masculinization, and the phenomenon will "go away." To give an even higher level of assurance that the resource will be protected, the Department is requiring a study to evaluate and confirm that the issue is resolved. The process changes required in the permit, the potential for further dilution in the St. Johns River if it becomes necessary, and the evaluations required in the permit condition render it very likely that any potential for fish masculinization will be mitigated. Thus, to the extent that fish masculinization could be deemed a violation of the free- from standard, Georgia-Pacific has provided reasonable assurances that it will not cause the masculinization of fish in the St. Johns River. Petitioners did not offer any credible evidence establishing that any specific compound or substance would cause the alleged effects of endocrine disruption or fish masculinization. Indeed, Dr. Koenig acknowledged that he was unable to find in his literature search the mechanism or chemical that is alleged to cause fish masculinization. Likewise, Petitioners were unable to suggest any concentration of that substance which would lead to those alleged effects. Dr. Koenig expressed a belief that chlorinated organic compounds from the paper manufacturing process may be responsible for endocrine disruption. Dr. Koenig also opined that within the general process of paper manufacturing, the bleaching process in particular was a concern. To the extent that Dr. Koenig may have had a concern regarding endocrine disruption from his review of studies performed using data from 1996 through 1998, it is reasonable to conclude that this concern is ameliorated by Georgia-Pacific's conversion to chlorine dioxide bleaching in March 2001. There is no evidence to establish a relationship between the presence or absence of dioxin and fish masculinization. Compliance with Dissolved Oxygen Standard (and BOD Concerns) In Section K, Petitioners disputed whether Georgia- Pacific had provided reasonable assurance of compliance with the adopted dissolved oxygen standard. The proposed permit contains different permit limits for BOD for winter and summer, because the impacts of discharges are different during those parts of the year. Georgia-Pacific has shown a substantial downward trend for BOD. The Georgia-Pacific facility discharges mass loadings of BOD at quantities which are much less than what is required to meet discharge standards. A review of effluent data shows that even for the worst period for performance, Georgia-Pacific's effluent was well below the proposed permit limits for BOD. A review of BOD discharges over the period of January 2000 to August 2001 demonstrates a consistent ability of the facility to meet the proposed permit limits, as well as a general trend of improvement that reflects Georgia-Pacific’s upgrade of the treatment system. Georgia-Pacific will meet the minimum standards for dissolved oxygen in mixing zones. With additional process improvements, Georgia-Pacific will also experience additional environmental benefits in the reduction of chemical oxygen demand. N. Dioxin and "Related Compounds" As to dioxin, Petitioners alleged in Section L of their Petition that Georgia-Pacific may discharge dioxin in concentrations that could cause a violation of the free-from standard. The proposed permit includes a permit condition for a plan of study to assess levels of "TCDD" and "TCDF" in fish tissue in the receiving waters. Department witness Brooks was unaware of any regulatory authority to require fish tissue sampling for dioxin. Department engineer Kohn was also uncertain of any regulatory authority for the Department to test for dioxin in fish tissue. Mr. Kohn agreed with the proposition that when a proposed permit condition is not specifically authorized by rule or statute, the condition must be withdrawn if the applicant objects. However, in this case, Georgia-Pacific did not object to the inclusion of a permit limit of .014 picograms per liter of dioxin in its final effluent. As noted above, Georgia-Pacific established that under its current effluent conditions, following conversion to chlorine dioxide bleaching, the facility is "non-detect" for dioxin. The Department does not have any adopted standards for fish tissue concentrations. Petitioners presented very little evidence of dioxin concentration in fish tissue following Georgia-Pacific's conversion to ECF bleaching, and they opposed the introduction of such data into evidence. A review of available data shows that there was not a statistically significant difference between the level of bioaccumulation of dioxin in fish tissue in Rice Creek versus a reference creek. The Florida Department of Health has concluded, based on review of prior fish tissue data, that a fish consumption advisory for Rice Creek was not warranted. Total Suspended Solids In Section M, Petitioners have alleged that TSS in the effluent would cause various environmental problems. However, Petitioners did not allege that TSS in the effluent would lead to a violation of water quality standards, and they did not present any accepted testimony or other evidence to support such a theory. There is no adopted water quality standard for TSS. According to the WQBEL Technical Report, effluent levels of TSS are generally comparable to background levels in the St. Johns River. The primary wastewater clarifier is designed to remove fiber or other settleable solids from the effluent before it travels to the secondary treatment system. Total suspended solids in Georgia-Pacific's effluent are primarily derived from biota in the treatment system, rather than fiber from the industrial process. Georgia-Pacific has shown a substantial downward trend for TSS. The facility reliably discharges TSS at quantities which are much less than what is required to meet proposed effluent limits. A review of discharge data for TSS demonstrates that Georgia-Pacific would perform in full compliance with the proposed permit limits. Petitioners presented no evidence to the contrary. Petitioners likewise presented no evidence to quantify any impacts from TSS. Color, the Transparency Standard, and Related Issues Petitioners have also alleged that the color in Georgia-Pacific's effluent would lead to nuisance conditions in violation of Rule 62-302.500(1)(a). However, they did not allege any potential violation of the one parameter traditionally associated with effluent color: the Department's transparency standard. Elevated levels of color in the effluent reduces the ability of light to penetrate into the water column, with potential effects on the growth of aquatic plants. This is translated into a "compensation point," that is, the water depth at which the light level reaches one percent. The state transparency standard prohibits a discharge from causing a decrease in the compensation point of more than ten percent, relative to natural background. The rate of decrease of light within a water column is related to increased color levels. Analysis performed by Georgia-Pacific's consultants shows that a ten percent change in compensation depth corresponds to a seventeen percent increase in color above natural background levels. Under the proposed permit, color was used as a surrogate, or alternative measure, for compliance with the transparency standard. Color was not used as a surrogate for any parameter other than transparency. Georgia-Pacific will, with additional process improvements, see additional environmental benefits in reducing the color of its effluent. For the purpose of the application, Georgia-Pacific's modeling analysis assumed that based on process improvements, its effluent would have a color of 1202 pcu. EPA's technical team had opined that Georgia- Pacific would, with process improvements, achieve a reduction in color to 500 pcu. Georgia-Pacific had opined that the improvements would achieve a color of 1202 pcu. Department witness Owen opined that the color reduction would be in a range between those two figures. Petitioners did not present any contrary evidence as to the ability of additional process improvements to reduce effluent color. Accordingly, using the most conservative (least optimistic) figure, Georgia-Pacific has provided reasonable assurances that before a discharge to the St. Johns River would be authorized, it will reduce the color of its effluent to 1202 pcu. The proposed permit takes into account the potential that Georgia-Pacific's process improvements will achieve greater improvements in color than anticipated. Under the proposed permit, the Department would reduce the size of the proposed mixing zone if Georgia-Pacific demonstrates that the color of its effluent is lower than projected. The modeling analysis further demonstrates that based on a discharge to the St. Johns River, assuming an effluent color of 1202 pcu, the change in compensation depth is greater than ten percent in the vicinity of the proposed diffuser. A 734-meter mixing zone for transparency would be required for a discharge to the middle of the St. Johns River. The required area for such a mixing zone is 64,000 square meters. Antidegradation Review In Section P, Petitioners have generally alleged that the Department failed to conduct a proper antidegradation analysis. More specifically, they alleged that the proposed discharge would reduce the quality of the receiving waters below the classification established for them. Because Georgia-Pacific presently discharges to Rice Creek, and because a separate relief mechanism (the Administrative Order) authorizes the discharge to Rice Creek, it appears that the antidegradation issues relate solely to the proposed discharge into the St. Johns River. If the relocation had resulted in degradation of the receiving water, the Department would have regulatory authority in its Rule 62-4.242(1)(c) to consider whether Georgia-Pacific could minimize its discharge through other discharge locations, the use of land application, or reuse. However, Petitioners failed to allege in their Petition that the Department misapplied that regulatory authority. Moreover, under Department practice, when a new discharge or relocation of a discharge will result in an environmental benefit, it is not necessary to conduct a review of other discharge options. The Department undertakes an antidegradation analysis in, among other scenarios, cases where a discharge will result in achievement of minimum water quality standards for a given designated use but will lead to an incremental lowering of water quality. The purpose of this analysis is to assure that the societal benefits of the discharge outweigh the cost of that incremental lowering. The proposed permit will not lead to the increase in discharge of any parameter, and the permit is more stringent and adds additional parameters or limits. In addition, there is a trend of improved performance for the treatment system. In the present case, the Department has concluded that the proposed project will result in a significant improvement in water quality by the reduction of pollutants associated with exceedences of water quality standards in Rice Creek. Regardless of whether the discharge remains in Rice Creek or is relocated to the St. Johns River, the proposed Permit and Administrative Order will lead to an improvement in water quality as opposed to a degradation of water quality. Based on improvements with respect to specific conductance parameters, the ability to relocate the discharge into the middle of the St. Johns River where better mixing will occur (relative to the confluence of Rice Creek), and anticipated improvements in grass beds, the proposed pipeline will lead to a net environmental benefit in the St. Johns River and Rice Creek. The project as set forth in the proposed Permit and Administrative Order will be clearly in the public interest because it will result in full achievement of water quality standards and full compliance with the designated use of the receiving water body. The project will result in a substantial reduction in pollutant loading in Rice Creek and the St. Johns River, regardless of the whether the discharge will be located in Rice Creek or in the St. Johns River. The Department adequately evaluated other discharge locations, alternative treatment, and disposal alternatives. Studies, including a land application pilot project, demonstrated that land application was not feasible based upon impacts to groundwater resources. In their Petition, Petitioners did not dispute the Department's analysis of those factors under applicable rules. Given these considerations, it is found that Georgia-Pacific has provided reasonable assurances that it will meet water quality standards, and it is evident that Georgia-Pacific will not reduce the quality of the St. Johns River below its Class III designation. Further, the proposed discharge will be clearly in the public interest for the purpose of antidegradation analysis. Further, the proposed discharge into the St. Johns River is important to and beneficial to the public health, safety, and welfare, taking into account the policies set forth in Rules 62-302.100 and 62-302.300, Florida Administrative Code. The proposed discharge into the St. Johns River will not adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. Instead, the proposed discharge would provide a benefit to fish and wildlife, and their habitats. No persuasive evidence was presented that the proposed discharge to the St. Johns River would adversely affect the fishing or water-based recreational values or marine productivity in the vicinity of the proposed discharge. Indeed, the record demonstrates a beneficial effect as to those factors. The proposed discharge has not been shown to be inconsistent with the applicable Surface Water Improvement and Management Plan (SWIM plan). Rather, the evidence shows that the proposed discharge would promote the implementation of the applicable SWIM plan. Monitoring Issues Section Q in the Petition generally challenged the adequacy of proposed monitoring requirements. As to this issue, the monitoring conditions imposed in the proposed permit are sufficient to ensure compliance with the proposed permit. Petitioner Young's witness Gilbert agreed that the proposed monitoring conditions were adequate to determine the result of process changes, that the proposed monitoring conditions were comprehensive, and that those conditions were beyond what the Department normally required. The Department does not propose to engage in water quality sampling at the end of the diffuser or at the edge of the mixing zone because of the technical difficulties associated with such an endeavor. Instead, the process for determining compliance is to determine the condition of the effluent and simulate water quality conditions of the receiving water body under low-flow conditions (when the river would be most vulnerable to pollution discharges). Such an approach is more protective because it eliminates variables that may not be representative of worst-case conditions. The evidence shows that the size of Georgia- Pacific's facility renders it impracticable for Georgia- Pacific to compromise the integrity of sampling results, as suggested by Petitioners. Flow Limitations In their Petition, Petitioners also contended that the proposed agency action violates Rules 62-4.240(3)(a) and 62-620.310(9)(a) by failing to specify the volume of discharge or flows. Under Department practice, flow must be specified but is not necessarily limited. Flow was adequately specified in the proposed permit, where the facility is described as 40 MGD wastewater treatment facility with a 22 MGD expected average flow. Volume limits are indirectly set through the establishment of a mixing zone and through mass loading limits in the permit, such as the loading limits for BOD and suspended solids. When flow is increased and the concentration of the effluent remains constant, the flow would be limited by the mass limits in the permit. Furthermore, the pipe and diffuser will have a hydraulic limitation, that is, a physical limitation on the amount that can physically be discharged. The pipeline and diffuser are hydraulically limited to 60 MGD based on the current design. Over a ten-year period, Georgia-Pacific has shown a trend toward reduced effluent flow. For example, in 1991, Georgia-Pacific discharged just under 40,000,000 gallons per day (GPD). In 2001, the discharge was less than 24,000,000 GPD. As a result of water conservation measures, Georgia- Pacific has been able to achieve a substantial reduction in effluent flow even when it experienced increased storm water flow into the treatment system. Because of stormwater inputs into the treatment system, it is very difficult to set a flow limit on the discharge from a pulp and paper mill. Indeed, the Department does not typically impose volume limits on NPDES permits for pulp and paper mills. Where volume or flow limits are imposed on pulp and paper mills, they are necessary in order to assure compliance with a specific standard. The Administrative Order Georgia-Pacific has submitted plans and a reasonable schedule for constructing, installing, or placing into operation an approved pollution abatement facility or alternative waste disposal system. No contrary evidence was presented, and no alternative construction schedule was proposed by Petitioners. In assessing a schedule to achieve compliance, the Department considered the time necessary to construct additional improvements as well as the reasonableness of the time period in light of Georgia-Pacific's capital investment. As part of this analysis, the Department also considered Georgia-Pacific's commitment to go beyond what they were legally required to do in environmental upgrades. The schedule of compliance is reasonable, given the cost and magnitude of the improvements required of Georgia-Pacific. Georgia-Pacific needs permission to continue its discharge to Rice Creek for a period of time necessary to complete research, planning, construction, installation, and operation of an approved and acceptable pollution abatement facility or alternative waste disposal system. The time period described in the Administrative Order will enable Georgia-Pacific to maximize the operation of the process improvements in order to determine if the discharge can meet water quality standards in Rice Creek. Given the cost and magnitude of the improvements required in the permit and Administrative Order, the schedule of compliance set forth in the Administrative Order is reasonable. There is no present, reasonable alternative means of disposing of wastewater other than to discharge it into waters of the State. In their Petition, Petitioners contested the Department's general antidegradation analysis but did not allege that any alternative means of disposal were improperly overlooked. The Department does not have specific regulatory authority to require facilities such as Georgia-Pacific to consider re-use as part of its antidegradation analysis, as it does with domestic waste discharges. Nonetheless, the Department did look at re-use and land application and determined that they were not feasible alternatives. Although it was not specifically required to do so by rule, Georgia- Pacific had exhausted every reasonable means to re-use (rather than discharge) water from its facility. Under earlier authorizations, Georgia-Pacific was not required to achieve standards for color, conductance, and chronic toxicity in Rice Creek. The granting of an operation permit will be in the public interest. This is because Putnam County will suffer an adverse economic impact if the facility is shut down and there will be net environmental benefits achieved through compliance with the requirements set forth in the Permit and Administrative Order. The Permit requires Georgia-Pacific to submit a written report to the Department if it appears that a mixing zone is needed for chronic whole effluent toxicity.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order (1) issuing proposed permit number FL0002763 to Georgia-Pacific Corporation, as set forth in Department Exhibit 175, and with the change in the permit conditions as requested in Georgia-Pacific Exhibit 102 and proposed by the Department during the hearing, and (2) approving Administrative Order No. 039-NE as set forth in Department Exhibit 176. DONE AND ENTERED this 3rd day of July, 2002, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 3rd day of July, 2002. COPIES FURNISHED: Kathy C. Carter, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Timothy Keyser, Esquire Keyser & Woodward, P.A. Post Office Box 92 Interlachen, Florida 32148-0092 Ralf G. Brookes, Esquire 1217 East Cape Coral Parkway, No. 107 Cape Coral, Florida 33904-9604 Jessica C. Landman, Esquire 1200 New York Avenue, Northwest Suite 400 Washington, D.C. 20005 Terry Cole, Esquire Jeffrey Brown, Esquire Oertel, Hoffman, Fernandez & Cole, P.A. Post Office Box 1110 Tallahassee, Florida 32302-1110 Teri L. Donaldson, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Francine M. Ffolkes, Esquire Thomas R. Gould, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

USC (2) 33 U.S.C 13425 U.S.C 558 Florida Laws (6) 120.569120.57403.051403.088403.0885403.412
# 2
BOBBY C. BILLIE AND SHANNON LARSEN vs ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND HINES INTERESTS LIMITED PARTNERSHIP, 00-002230 (2000)
Division of Administrative Hearings, Florida Filed:St. Augustine, Florida May 26, 2000 Number: 00-002230 Latest Update: Jul. 12, 2004

The Issue The issues to be resolved in this proceedings concern whether Environmental Resource Permit (ERP) No. 4-109-0216-ERP, should be modified to allow construction and operation of a surface water management system (project) related to the construction and operation of single-family homes on "Marshall Creek" (Parcel D) in a manner consistent with the standards for issuance of an ERP in accordance with Rules 40C-4.301 and 40C-4.302, Florida Administrative Code.

Findings Of Fact The Project The project is a 29.9-acre residential development and associated stormwater system in a wetland mitigation area known as "Parcel D." It lies within the much larger Marshall Creek DRI in St. Johns County, Florida, bounded on the northeast by Marshall Creek, on the south and southeast by a previously permitted golf course holes sixteen and seventeen, and on the north by the "Loop Road." The project consists of thirty residential lots of approximately one-half acre in size; a short segment of Loop Road to access Parcel D; an internal road system; expansion of previously permitted Pond N, a wet detention stormwater management pond lying north of the Loop Road and wetland mitigation areas. Approximately 1.15 acres of wetlands are located on the Parcel D site. The project plan calls for filling 0.63 acres of the wetlands for purposes of constructing a road and residential lots for Parcel D. Part of that 0.63-acre impact area, 0.11 acres, is comprised of a 760-foot-long, narrow drainageway, with 0.52 acres of adjacent wetland. Downstream of the fill area, 0.52 acres of higher quality wetland is to be preserved. Hines proposes to preserve 4.5 acres of existing wetland and 2.49 acres of upland, as well as to create .82 acres of forested wetland as mitigation for the proposed impact of the project. Additionally, as part of the project, Hines will implement a nutrient and pesticide management plan. The only pesticides to be used at the project will be approved by the Department of Agriculture for use with soil types prevailing at the site and only pesticides approved by the Environmental Protection Agency may be used on the site. All pesticides to be used on the project site must be selected to minimize impacts to ground and surface water, including having a maximum 70-day half-life. Stormwater Management System The majority of surface runoff from Parcel D will be diverted to a stormwater collection system and thence through drainage pipes and a swale into Phase I of Pond N. After treatment in Pond N, the water will discharge to an upland area adjacent to wetlands associated with Marshall Creek and then flow into Marshall Creek. The system will discharge to Marshall Creek. In addition to the area served by Pond N, a portion of lots fourteen though twenty drain through a vegetated, natural buffer zone and ultimately through the soil into Marshall Creek. Water quality treatment for that stormwater runoff will be achieved by percolating water into the ground and allowing natural soil treatment. The fifty-foot, vegetated, natural buffer is adequate to treat the stormwater runoff to water quality standards for Lots 14, 15 and 20. Lots 16, 17, 18 and 19, will have only a twenty-five foot buffer, so additional measures must be adopted for those lots to require either that the owners of them direct all runoff from the roofs and driveways of houses to be constructed on those lots to the collection system for Pond N or placement of an additional twenty-five foot barrier of xeriscape plants, with all non- vegetated areas being mulched, with no pesticide or fertilizer use. An additional mandatory permit condition, specifying that either of these measures must be employed for Lots 16, 17, 18 and 19, is necessary to ensure that water quality standards will be met. Pond N is a wet detention-type stormwater pond. Wet detention systems function similarly to natural lakes and are permanently wet, with a depth of six to twelve feet. When stormwater enters a wet detention pond it mixes with existing water and physical, chemical and biological processes work to remove the pollutants from the stormwater. Pond N is designed for a twenty-five year, twenty-four- hour storm event (design storm). The pre-development peak rate of discharge from the Pond N drainage area for the design storm event is forty cubic feet per second. The post-development peak rate of discharge for the design storm event will be approximately twenty-eight cubic feet per second. The discharge rate for the less severe, "mean annual storm" would be approximately eleven cubic feet per second, pre-development peak rate and the post-development peak rate of discharge would be approximately five cubic feet per second. Consequently, the post-development peak rate of discharge does not exceed the pre- development peak rate of discharge. Pond N is designed to meet the engineering requirements of Rule 40C-42.026(4), Florida Administrative Code. Because the pond is not designed with a littoral zone, the permanent pool volume has been increased by fifty-percent. Additionally, because Pond N discharges to the Class II waters of Marshall Creek, an additional fifty-percent of treatment volume is included in the pond design. The system design addresses surface water velocity and erosion issues through incorporation of best management practices promulgated by the District to prevent erosion and sedimentation, including; designing side slopes of 4:1; siding and seeding disturbed areas to stabilize soil; and the use of riprap at the outfall from Pond N. During construction, short- term water quality impacts will be addressed through installation of silt fences and hay bales. The majority of the eighteen-acre drainage basin which flows into the Parcel D wetland lies to the south and southwest of Parcel D. In accordance with the prior permit, water from those off-site acres will be intercepted and routed to stormwater ponds serving golf course holes sixteen and seventeen. The system design will prevent adverse impacts to the hydroperiod of remaining on-site and off-site wetlands. The remaining wetlands will be hydrated through groundwater flow. Surface waters will continue to flow to the wetlands adjacent to lots fourteen through twenty because drainage from those lots will be directed across a vegetated, natural buffer to those wetlands. There is no diversion of water from the natural drainage basin, because Pond N discharges to a wetland adjacent to Marshall Creek, slightly upstream from the current discharge point for the wetland which is to be impacted. This ensures that Marshall Creek will continue to receive that fresh-water source. An underground "PVC cut-off wall" will be installed around Pond N to ensure that the pond will not draw down the water table below the wetlands near the pond. Pond N has been designed to treat stormwater prior to discharge, in part to remove turbidity and sedimentation. This means that discharge from the pond will not carry sediment and that the system will not result in shoaling. There will be no septic tanks in the project. The system is a gravity flow system with no mechanical or moving parts. It will be constructed in accordance with standard industry materials readily available and there will be nothing extraordinary about its design or operation. The system is capable of being effectively operated and maintained and the owner of the system will be the Marshall Creek Community Development District (CDD). Water Quality Water entering Pond N will have a residence time of approximately 200 days or about fifteen times higher than the design criteria listed in the below-cited rule. During that time, the treatment and removal process described herein will occur, removing most of the pollutants. Discharge from the pond will enter Marshall Creek, a Class II water body. The discharges must therefore meet Class II water quality numerical and anti-degradation standards. The design for the pond complies with the design criteria for wet detention systems listed in Rule 40C-42.026(4), Florida Administrative Code. In addition to meeting applicable design criteria, the potential discharge will meet water quality standards. The pond will have low levels of nitrogen and phosphorous resulting in low algae production in the pond. The long residence time of the water in the pond will provide an adequate amount of time for pesticides to volatilize or degrade, minimizing the potential for pesticide discharge. Due to the clear characteristics of the water column, neither thermal stratification nor chemical stratification are expected. Periodically, fecal coliform and total coliform levels are exceeded under current, pre-development conditions. These are common natural background conditions. Because the detention time in the pond will be an average of 200 days, and because the life span of fecal coliform bacteria is approximately seven to fourteen days the levels for coliforms in the pond will be very low. Discharges from the pond will enhance water quality of the Class II receiving waters because the levels of fecal coliform and total coliform will be reduced. The discharge will be characterized by approximately 100 micrograms per liter total nitrogen, compared with a background of 250 micrograms per liter presently existing in the receiving waters of Marshall Creek. The discharge will contain approximately three micrograms per liter of phosphorous, compared with sixty-three micrograms per liter presently existing in Marshall Creek. Total suspended solids in the discharge will be less than one-milligram per liter compared with seventy-two milligrams per liter in the present waters of Marshall Creek. Biochemical oxygen demand will be approximately a 0.3 level in the discharge, compared with a level of 2.4 in Marshall Creek. Consequently, the water quality discharging from the pond will be of better quality than the water in Marshall Creek or the water discharging from the wetland today. The pollutant loading in the discharge from the stormwater management system will have water quality values several times lower than pre-development discharges from the same site. Comparison of pre-development and post-development mass loadings of pollutants demonstrates that post-development discharges will be substantially lower than pre-development discharges. Currently, Marshall Creek periodically does not meet Class II water quality standards for dissolved oxygen. Construction and operation of the project will improve water quality in the creek concerning dissolved oxygen values because discharges from Pond N will be subjected to additional aeration. This results from design features such as discharge from the surface of the system, where the highest level of dissolved oxygen exists, and the discharge water draining through an orifice and then free falling to a stormwater structure, providing additional aeration. Discharges from the system will maintain existing uses of the Class II waters of Marshall Creek because there will be no degradation of water quality. Discharges will not cause new violations or contribute to existing violations because the discharge from the system will contain less pollutant loading for coliform and will be at a higher quality or value for dissolved oxygen. Discharges from the system as to water quality will not adversely affect marine fisheries or marine productivity because the water will be clear so there will be no potential for thermal stratification; the post-development discharges will remain freshwater so there will be no change to the salinity regime; and the gradual pre-development discharges will be replicated in post-development discharges. Several factors minimize potential for discharge of pesticide related pollutants: (1) only EPA-approved pesticides can be used; (2) only pesticides approved for site-specific soils can be used; (3) pesticides must be selected so as to minimize impacts on surface and groundwater; (4) pesticides must have a maximum half-life of 70 days; and (5) the system design will maximize such pollutant removal. Archaeological Resources The applicant conducted an archaeological resource assessment of the project and area. This was intended to locate and define the boundaries of any historical or archaeological sites and to assess any site, if such exists, as to its potential eligibility for listing in the National Register of Historic Places (National Register). Only a portion of one archaeological site was located on the project tract. Site 8SJ3473, according to witness Anne Stokes, an expert in the field of archaeological assessment, contains trace artifacts dating to the so-called "Orange Period," a time horizon for human archaeological pre-history in Florida dating to approximately 2,300 B.C. The site may have been only a small campsite, however, since only five pottery fragments and two chert flakes, residuals from tool-making were found. Moreover, there is little possibility that the site would add to knowledge concerning the Orange Period or pre-history because it is a very common type of site for northeast Florida and is not an extensive village site. There are likely other campsites around and very few artifacts were found. No artifacts were found which would associate the site with historic events or persons. The applicant provided the findings of its cultural resource assessment, made by Dr. Stokes, to the Florida Division of Historical Resources. That agency is charged with the responsibility of reviewing cultural resource assessments to determine if significant historic or archaeological resources will be impacted. The division reviewed the survey techniques used by Dr. Stokes, including shovel testing, sub-surface testing and pedestrian walk-over and investigation. The division determined that the site in question is not of a significant historical or archaeological nature as a resource because it does not meet any of the four criteria for inclusion in the National Register.1 Thus the referenced agency determined that the site in question is not a significant historical or archaeological resource and that construction may proceed in that area without further investigation, insofar as its regulatory jurisdiction is concerned. Wetlands The wetlands to be impacted by the project consist of a 1,000 foot drainage-way made up of a 0.11 acre open-water channel, approximately four feet wide, and an adjacent vegetated wetland area of approximately 0.52 acres containing fewer than 30 trees. The open-water channel is intermittent in that it flows during periods of heavy rainfall and recedes to a series of small, standing pools of water during drier periods. The Parcel D wetland is hydrologically connected to Marshall Creek, although its ephemeral nature means that the connection does not always flow. The wetland at times consists only of isolated pools that do not connect it to Marshall Creek. Although it provides detrital material export, that function is negligible because the productivity of the adjacent marsh is so much greater than that of the wetland with its very small drainage area. Because of the intermittent flow in the wetland, base flow maintenance and nursery habitat functions are not attributed to the wetland. The Parcel D wetland is not unique. The predominant tree species and the small amount of vegetated wetland are water oak and swamp bay. Faunal utilization of the wetland is negligible. The wetland drainage-way functions like a ditch because it lacks the typical characteristics of a creek, such as a swampy, hardwood floodplain headwater system that channelizes and contains adjacent hardwood floodplains. The location of the wetland is an area designated by the St. Johns County comprehensive plan as a development parcel. The Florida Natural Areas Inventories maps indicate that the wetland is not within any unique wildlife or vegetative habitats. The wetland is to be impacted as a freshwater system and is not located in a lagoon or estuary. It contains no vegetation that is consistent with a saltwater wetland. The retaining wall at the end of the impact area is located 1.7 feet above the mean high water line. Wetland Impacts The proposed 0.63 acre wetland impact area will run approximately 760 linear feet from the existing trail road to the proposed retaining wall. If the wetland were preserved, development would surround the wetland, adversely affecting its long-term functions. Mitigation of the wetland functions is proposed, which will provide greater long-term ecological value than the wetland to be adversely affected. The wetland to be impacted does not provide a unique or special wetland function or good habitat source for fish or wildlife. The wetland does not provide the thick cover that would make it valuable as Black Bear habitat and is so narrow and ephemeral that it would not provide good habitat for aquatic-dependent and wetland-dependent species. Its does not, for instance, provide good habitat for woodstorks due to the lack of a fish population and its closed- in tree canopy. Minnow sized fish (Gambusia) and crabs were seen in portions of the wetland, but those areas are downstream of the proposed area of impact. Mitigation Mitigation is offered as compensation for any wetland impacts as part of an overall mitigation plan for the Marshall Creek DRI. The overall mitigation plan is described in the development order, the mitigation offered for the subject permit and mitigation required by prior permits. A total of 27 acres of the more than 287 acres of wetlands in the total 1,300-acre DRI tract are anticipated to be impacted by the DRI. Approximately 14.5 acres of impacted area out of that 27 acres has already been previously authorized by prior permits. The overall mitigation plan for the DRI as a whole will preserve all of the remaining wetlands in the DRI after development occurs. Approximately one-half of that preserved area already has been committed to preservation as a condition of prior permits not at issue in this case. Also, as part of prior permitting, wetland creation areas have been required, as well as preserved upland buffers which further protect the preserved wetlands. The mitigation area for the project lies within the Tolomato River Basin. The development order governing the total DRI requires that 66 acres of uplands must also be preserved adjacent to preserved wetlands. The overall mitigation plan for the DRI preserves or enhances approximately 260 acres of wetlands; preserves a minimum of 66 acres of uplands and creates enhancement or restores additional wetlands to offset wetland impacts. The preserved wetlands and uplands constitute the majority of Marshall Creek, and Stokes Creek which are tributaries of the Tolomato River Basin, a designated Outstanding Florida Water (OFW). Preservation of these areas prevents them from being timbered and ensures that they will not be developed in the future. The overall DRI mitigation plan provides regional ecological value because it encompasses wetlands and uplands they are adjacent to and in close proximity to the following regionally significant resources: (1) the 55,000 acre Guana- Tolomato-Matanzas National Estuarine Research Reserve; (2) the Guana River State Park; (3) the Guana Wildlife Management Area; (4) an aquatic preserve; (5) an OFW; and (6) the 22,000 acre Cummer Tract Preserve. The mitigation plan will provide for a wildlife corridor between these resources, preserve their habitat and insure protection of the water quality for these regionally significant resources. The mitigation offered to offset wetland impacts associated with Parcel D includes: (1) wetland preservation of 0.52 acres of bottom land forest along the northeast property boundary (wetland EP); (2) wetland preservation of 3.98 acres of bottom land forest on a tributary of Marshall Creek contained in the DRI boundaries (Wetlands EEE and HHH); (3) upland preservation of 2.49 acres, including a 25-foot buffer along the preserved Wetlands EEE and HHH and a 50-foot buffer adjacent to Marshall Creek and preserved Wetland EP; (4) a wetland creation area of 0.82 acres, contiguous with the wetland preservation area; and (5) an upland buffer located adjacent to the wetland creation area. The wetland creation area will be graded to match the grades of the adjacent bottomland swamp and planted with wetland tree species. Small ponds of varying depths will be constructed in the wetland creation area to provide varying hydrologic conditions similar to those of the wetland to be impacted. The wetland creation area is designed so as to not de-water the adjacent wetlands. All of the mitigation lands will be encumbered with a conservation easement consistent with the requirements of Section 704.06, Florida Statutes. The proposed mitigation will offset the wetland functions and values lost through the wetland impact on Parcel D. The wetland creation is designed to mimic the functions of the impact area, but is located within a larger ecological system that includes hardwood wetland headwaters. The long-term ecological value of the mitigation area will be greater than the long-term value of the wetland to be impacted because; (1) the mitigation area is part of a larger ecological system; (2) the mitigation area is part of an intact wetland system; (3) the wetland to be impacted will be unlikely to maintain its functions in the long-term; and (4) the mitigation area provides additional habitat for animal species not present in the wetland to be impacted. Certain features will prevent adverse secondary impacts in the vicinity of the roadway such as: (1) a retaining wall which would prevent migration of wetland animals onto the road; (2) a guard rail to prevent people from moving from the uplands into wetlands; and (3) a vegetated hedge to prevent intrusion of light and noise caused by automotive use of the roadway.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is RECOMMENDED: That a final order be entered granting the subject application for modification of Permit 4-109-0216A-ERP so as to allow construction and operation of the Parcel D project at issue, with the addition of the inclusion of a supplemental permit condition regarding the vegetated natural buffers for Lots 16 through 19 described and determined above. DONE AND ENTERED this 9th day of April, 2001, in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 2001.

Florida Laws (5) 120.57267.061373.086373.414704.06 Florida Administrative Code (5) 40C-4.09140C-4.30140C-4.30240C-42.02340C-42.026
# 3
GILLIS-FANNY SOCIETY, INC. vs. JOYCE K. ANDERSON, THOMAS BARNETT, AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 82-001432 (1982)
Division of Administrative Hearings, Florida Number: 82-001432 Latest Update: Dec. 06, 1983

Findings Of Fact Joyce K. Anderson and Thomas Barnett have filed an application for issuance of a permit to dredge and fill a small area in the littoral, or "near shore," zone of Gillis Pond, a "sandhill lake" lying in what is known as the "sandhill region" of Central Florida, generally northeast of Gainesville. The dredging and filling as now proposed would be on and waterward of two lakefront lots jointly owed by the permit applicants. They seek by their application, authorization to dredge and fill at only one site on the waterward margin of the two lots with that modified project area reduced in size to a dimension of 12 feet by 25 feet. Fifteen feet of the project would be waterward of the shoreline. The Respondent, the Department of Environmental Regulation, is an agency of the State of Florida charged with the duty of enforcing, as pertinent hereto, the provisions of Chapter 403, Florida Statutes, and Chapter 17-3 and 4, Florida Administrative Code, enforcing the water quality standards contained therein as they relate to dredge and fill projects of this sort, with concomitant permitting jurisdiction over such projects. The permit applicants desire this dredge and fill permit in order to make a safe, comfortable swimming area for Mrs. Anderson's family and friends. Mrs. Anderson desires to remove the tree stumps, roots and vegetation existing in the littoral zone area of the above dimensions in order to make access directly from the shore more comfortable and pleasant, especially for small children who are unable to swim in the deep water off the waterward end of the existing dock. Mrs. Anderson already has a 56 foot dock extending from her property into the lake. The water is 7 feet deep at the waterward end of the dock and the littoral zone containing aquatic vegetation extends beyond the length of the dock in a waterward direction. The project area would extend waterward of the shoreline, a distance of 15 feet, and would parallel the shoreline approximately a distance of 12 feet. The littoral zone vegetation at the site, however, extends waterward from the shoreline 50 to 60 feet. The proposed area to be dredged is quite small in size in relation to the total linear shoreline of the subject lake of approximately 4,000 feet. The dredged material would be excavated to a depth of approximately 6 inches over that 12 by 15 foot area and replaced with clean sand fill. The dredged material removed from the site would be secured on an upland site such that nutrient pollutants from that dredged material could not be leached or carried back into the lake through storm water runoff. Approximately one-third of the shoreline of the lake is bordered by a marsh or wet prairie which is approximately as large in area as the lake itself. The dominant vegetative species in the project area and surrounding the lake, including the marsh, are submerged freshwater species listed in Rule 17- 4.02(17), Florida Administrative Code, including maidencane, sawgrass and a rare aquatic plant, websteria confervodies. Gillis Pond is a Class III water of the state, although its water quality parameters, or some of them, clearly exceed in quality, the minimum standards for Class III waters. Gillis Pond is what is termed an "ultra- oligotrophic lake, which means that its waters are characterized by a high level of transparency and very low nutrient content, that is to say that they are essentially pristine in nature. An oligotrophic lake such as this is very sensitive to any addition of nutrient pollutants. Even a small addition of nutrients to such water can cause an imbalance in the fauna and flora which have evolved to become dependent upon a low nutrient aquatic environment. Specifically, the rare aquatic plant named above is very sensitive to any enhanced nutrient levels and thus serves as a barometer of the water quality in this body of water. The addition of any nutrient pollutants to the lake, even in small amounts, might alter the chemical balance of the water in a derogatory manner so that the websteria confervodies might be eliminated. The elimination of this species from the littoral zone vegetation band surrounding the lake would likely result in other forms of vegetation supplanting it, altering the balance and makeup of the community of fauna and flora native to the lake and possibly hastening the progress of the lake toward eutrophication and degradation. The present water quality in the lake is such that dissolved oxygen and other criteria are better than the Class III water quality standards. The vegetation in the littoral zone of the lake and extending out as much as 50 to 60 feet waterward performs a significant function in uptaking and fixing nutrient pollutants that wash into the lake from storm water runoff from the surrounding uplands. Inasmuch as 30 to 40 feet of this belt of littoral zone vegetation would remain waterward of the dredged and filled area if the permit is granted, the nutrient uptake function of the vegetation in the littoral zone would not be significantly degraded. There are two locations where littoral zone vegetation has been removed in a similar fashion and water quality and flora and fauna communities characteristic of an oligotrophic lake are still present and healthy. Further, there is an extremely low nutrient level in the lake at the present time, and no significant amount of nutrient pollutants are leached or washed into the lake through septic tanks, storm water runoff or other sources. There is no question that the project as proposed would result in some slight, transitory degradation of water quality in the form of increased turbidity and reduced transparency. Turbidity will be caused during and shortly after the dredging and filling operation itself, caused by stirring up of bottom peat or sediments and by removal of a 12 by 15 foot area of aquatic vegetation in the littoral zone of the lake. Turbidity curtains in still waters such as involved here, can substantially reduce the spread of turbidity caused by the stirring up of bottom material and can substantially reduce the period of its suspension in the water by containing it at the dredged site. The vast majority of the littoral zone vegetation surrounding and waterward of the area to be dredged will remain such that the nutrient uptake function will be essentially undisturbed, thus any adverse impact on water quality will be insignificant. In terms of cumulative effect of allowing a multiplicity of such projects, not even a 10 percent loss of the littoral zone band of vegetation in the lake, which would be the maximum possible loss if all riparian land owners were allowed a similar size dredged and filled area on the front of their lots, would cause a violation of Department water quality standards. Parenthetically, it should be pointed out that such riparian owners cannot be prevented by any water quality criteria in Chapter 403 or Chapter 17, Florida Administrative Code, from having access to the lake in front of their lots. Such human traffic will have the gradual affect of destroying a significant amount of the littoral zone vegetation on and waterward of those lots (which is a cause and result the Department is powerless to regulate). By confining the destruction of littoral zone vegetation to such a small area as that involved in the application at bar and thus guaranteeing adequate, comfortable access for the riparian owner, the survivability of the remaining critical littoral zone vegetation will be significantly enhanced.

Recommendation Having considered the foregoing Findings of Fact, Conclusions of Law, the evidence in the record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED: That the application of Joyce K. Anderson and Thomas Barnett for a dredge and fill permit as described in the modified and amended application be GRANTED; provided, however, that turbidity curtains are used during all dredging and filling activity and for a reasonable time thereafter until turbidity caused by the project has settled out of the water column. DONE and ENTERED this 26th day of September, 1983, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1983. COPIES FURNISHED: Tim Keyser, Esquire Post Office Box 92 Interlachen, Florida 32048 Dennis R. Erdley, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Joyce K. Anderson and Thomas Barnett 6216-B, Southwest 11th Place Gainesville, Florida 32601 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (4) 120.57403.031403.087403.088
# 4
AUDUBON SOCIETY OF SOUTHWEST FLORIDA vs. LEE COUNTY BOARD OF COUNTY COMMISSIONERS AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-002307 (1981)
Division of Administrative Hearings, Florida Number: 81-002307 Latest Update: Jul. 07, 1982

Findings Of Fact On April 2, 1981, Lee County applied to DER for a permit to construct an extension of Colonial Boulevard east to State Road 82B by dredging 4,600 cubic yards of material landward of the ordinary high water mark, and by depositing 83,000 cubic yards of fill landward of the ordinary high water mark in an area of Lee County known as the Six Mile Cypress Strand or Six Mile Cypress Slough. The permit application was made by Lee County on standard DER forms which would have been appropriate for an application under either or both Chapters 253 or 403, Florida Statutes. Additionally, Lee County tendered a permit application fee to DER sufficient to cover the cost of an application under both statutes. After review of the application, DER determined that it had no jurisdiction under Chapter 253, Florida Statutes, and refunded to Lee County that portion of the permit application fee required for a Chapter 253 permit. As indicated above, Lee County's application, on its face, reflected that no fill material or dredging was proposed waterward of the ordinary high water mark. The Six Mile Cypress Strand is a meandering swamp, approximately 44,000 acres in size, dominated by cypress trees. At periods of high water the waters of the swamp empty into Ten Mile Canal, an artificial water body which connects to Estero Bay by way of Mullock Creek, a natural stream. All water bodies involved in this proceeding are classified as Class III waters. Six Mile Cypress Strand functions as a major aquifer recharge area for the eastern central portion of Lee County. The area drained by the Strand receives approximately 54 inches of rainfall annually. The wetland vegetation and uneven contours of the Strand allow the assimilation of nutrients and reduction in turbidity and erosion which could otherwise adversely affect downstream waters. The drainage area north of the proposed project consists of approximately 5,000 acres, or 11 percent of the total drainage basin served by the Strand. The proposed roadway would cross the Strand through a corridor which contains three cypress heads, or flag ponds. These ponds generally retain water during dry periods and support a more diverse community of aquatic life than those portions of the Strand which become completely dry. At the time of final hearing in this cause, these ponds exhibited dry season characteristics and contained less than one foot of water in their deepest portions. During low water periods the Strand itself may be virtually dry except for standing water in the vicinity of cypress heads and flag ponds. Only during the rainy season, which occurs during approximately four months of the year, does the Strand contain standing water. During high water periods, however, water may flow continuously throughout the length of the Strand. During these latter periods, canoes and other such small water craft may be able to negotiate portions of the Strand. No evidence was presented, however, which would indicate that the Strand is now or has ever been utilized, or is susceptible to utilization, for commercial boat traffic. The lands in the Strand over which Lee County proposes to build the roadway were conveyed by the Trustees of the Internal Improvement Trust Fund to private ownership after having been acquired from the federal government under the Swamp and Overflow Grant Act of 1850. The Strand was not meandered in the original government survey of the area, and, in fact, the surveyor's field notes reflect that the area of the Strand was densely vegetated and crossed by several roads, including one crossing the section line in the same vicinity proposed for the Colonial Boulevard extension. The existence of this last referenced road is corroborated by biological evidence presently existing on the site, and from examinations of full infrared aerial photography of the area. It is approximately nine miles from the Strand to the nearest meander line contained in the original government survey. Further, evidence of record in this proceeding establishes that water craft may not presently be navigated from Estero Bay into the Strand because of man-made barriers, and no record evidence establishes that such navigation would have been possible at the time of Florida's admission to statehood in 1845 when the stream presumably was in its natural condition. The Department of Natural Resources was notified in accordance with DER policy, of the pendency of Lee County's application, and asserted no claim of ownership over sovereignty lands in the area of the proposed project. The design for the proposed roadway includes a system of collector and spreader swales on the upstream and downstream sides of the Strand, respectively, connected by large culverts to be located beneath the roadway. The swales and culverts are intended to minimize interruption of the Strand's hydroperiod, the natural fluctuation and flow of waters within the affected portion of the Strand. A vegetated swale system paralleling the roadway is also included in the proposed roadway design to provide treatment and nutrient uptake from storm water runoff generated from the surface of the roadway. In addition, the toe of the slope of the roadway will be replanted with native vegetation, and the edge of the fill area will be meandered to save some existing vegetation. It is anticipated that the roadway could result in runoff containing from .17 to .18 pounds per day of nitrogen, and from .01 to .07 pounds per day of phosphate. The grassy swales proposed for inclusion in the project design have the capability of assimilating from 1.8 to 3.6 pounds of these nutrients per day, thereby ensuring a significant safety factor. It can also reasonably be anticipated that the swale areas are capable of absorbing any BOD loading from the roadway surface. As a result, it can reasonably be anticipated that the construction of the project will not result in the discharge of nutrients into the Strand, and that any heavy metals will be bound in organic sediments and not result in degradation of existing water quality. Ambient water conditions in the Strand show low dissolved oxygen content together with high biochemical oxygen demand, neither of which should be exacerbated by construction of the project. No violation of water quality criteria relating to herbicides is anticipated in view of Lee County's commitment at final hearing in this cause to control vegetation by way of mowing instead of by the use of herbicides. The proposed construction will, of course, destroy aquatic vegetation in the area lying in the path or "footprint" of the roadway itself, consisting of approximately seven and one-half acres, three acres of which are predominantly cypress. However, because of the design features of the proposed roadway, including grass, collector and spreader swales and the culvert system, the anticipated impact on the hydroperiod upstream and downstream of the project, and thereby the effect on aquatic vegetation and water quality will not be significant. Construction fabric will be used to allow the road surface to be supported without demucking, thus minimizing turbidity during construction periods, although it is intended that construction be conducted during the dry season, thereby further reducing the potential for turbidity violations. Further, the detention swales which are to be equipped with French drains are designed to retain the first inch of rainfall. Culverts to be constructed on the roadway are designed to accommodate a 50-year, 24-hour storm event. The Secretary of DER issued the subject permit on August 18, 1981, without any prior notice of intent. ASSWF received notice of DER's action in the form of a complete copy of the permit on August 27, 1981. On September 2, 1981, ASSWF filed its petition requesting a formal Section 120.57(1), Florida Statutes, hearing. This petition was received by DER on September 8, 1981. ASSWF and Audubon, and the members of these organizations, use the Six Mile Cypress Strand in the vicinity of the proposed project for field trips and environmental education activities which will be impacted should the project be approved. In addition, Audubon owns property within the Strand which may also be affected by the proposed project if permitted. Intervenors, Community Council and Lehigh Acres of Florida, Inc., Ralph Marciano, Claudia Tipton and H. Mark Strong requested to be granted party status in this proceeding in support of the application. Ralph Marciano owns a business allegedly limited because of the present poor highway access to the business center of the city. Claudia Tipton owns an electrical construction business alleged to be seriously hampered because of extended transportation time in emergency trips. H. Mark Strong is a retired fire marshal and contends that paramedics are seriously hampered in transporting emergency patients to the community hospital located in Fort Myers. The Community Council of Lehigh Acres was formed to serve as a council representing the entire community of Lehigh Acres on problems and projects affecting the health, welfare, growth and prosperity of Lehigh Acres. Essentially, these intervenors assert that the general public welfare and, in some cases, their own personal business interests, will be enhanced by building the proposed roadway, thereby enhancing vehicular access to various portions of the community.

Florida Laws (3) 120.57403.087403.412
# 5
BRENDA B. SHERIDAN vs DEEP LAGOON BOAT CLUB, LTD., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 98-003901 (1998)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Sep. 04, 1998 Number: 98-003901 Latest Update: Feb. 02, 2000

The Issue The issue in DOAH Case No. 98-3901 is whether Respondent Deep Lagoon Boat Club, Ltd., is entitled to a maintenance dredging exemption from environmental resource permitting. The issue in DOAH Case No. 98-5409 is whether Respondent Deep Lagoon Boat Club, Ltd., is entitled to an environmental resource permit for the construction of a surface water management system.

Findings Of Fact The Parties Respondent Deep Lagoon Boat Club, Ltd. (Applicant), owns and operates Deep Lagoon Marina. In DOAH Case No. 98-3901, Petitioner and Intervenor challenge Applicant's claim of an exemption to maintenance dredge three canals serving the marina. In DOAH Case No. 98-5409, Petitioner challenges Applicant's request for an environmental resource permit to construct and operate a surface water management system on the uplands on which the marina is located. By stipulation, Petitioner has standing. Intervenor is a nonprofit organization of natural persons, hundreds of whom reside in Lee County. The primary purpose of Intervenor is to protect manatees and their habitat. Many of the members of Intervenor use and enjoy the waters of the State of Florida, in and about Deep Lagoon Marina, and would be substantially affected by an adverse impact to these waters or associated natural resources, including manatees and their habitat. Deep Lagoon Marina is within the jurisdiction of the South Florida Water Management District (SFWMD). By agreement with SFWMD, Respondent Department of Environmental Protection (collectively, with the predecessor agency, DEP) is the agency with permitting jurisdiction in DOAH Case No. 98-5409. The Marina Deep Lagoon is a short, largely mangrove-lined waterway that runs north into the Caloosahatchee River. The Caloosahatchee River runs west from Lake Okeechobee past Fort Myers to the Gulf of Mexico. Deep Lagoon Marina is on Deep Lagoon, less than one-half mile from the Caloosahatchee River. Deep Lagoon Marina comprises uplands and three canals adjoining MacGregor Boulevard south of downtown Fort Myers. Deep Lagoon Marina presently consists of 61 wet slips, 200 dry slips, and other marina-related buildings. One of Applicant's predecessors in interest dredged the three canals in the 1950s or 1960s, and a marina has existed at this location since that time. As a result of a purchase in 1997, Applicant owns the uplands and either owns the submerged bottoms of the canals or has a legitimate claim to such ownership. The attorney who examined the title at the time of the 1997 conveyance testified that the canals are entirely landward of the original mean high water line, so that the then-owner excavated the canals out of privately owned upland. Thus, the attorney opined that the canal bottom is privately owned. Some question may exist as to the delineation of the historic mean high water line, especially regarding its location relative to the waterward edge of the red mangrove fringe, which DEP would consider part of the historic natural waterbody. There may be some question specifically concerning title to the bottom of the northernmost canal where it joins Deep Lagoon. However, the proof required of Applicant for present purposes is considerably short of the proof required to prove title, and the attorney's testimony, absent proof to the contrary, is sufficient to demonstrate the requisite ownership interest to seek the exemption and permit that are the subject of these cases. From north to south, Deep Lagoon Marina comprises the north canal, which is about 1200 feet long and bounded on the north by a red mangrove fringe 10-20 feet wide; a peninsula; the central canal, which is also known as the central or main basin and is roughly the same length as the north canal; a shorter peninsula; and the south canal, which is about half the length of the central canal and turns to the southeast at a 45-degree angle from the midway point of the central canal. The three canals are dead-end canals, terminating at their eastern ends a short distance from MacGregor Boulevard. Manatees and Boating The Caloosahatchee River is critical habitat for the endangered West Indian manatee. Up to 500 manatees use the river during the winter. When, during the winter, the water cools, the animals congregate in waters warmed by the thermal discharge from a power plant about 13 miles upstream of Deep Lagoon. When, during the winter, the water warms, the manatees swim downstream, past and into Deep Lagoon searching for food. Manatees frequently visit Deep Lagoon. It is one of the few places between the power plant and the Gulf where manatees can find a quiet place, relatively free of human disturbance, to rest and feed. Within Deep Lagoon, the Iona Drainage District ditch runs parallel to the north canal, separated from the canal by the previously described mangrove fringe. The Iona Drainage District ditch empties into Deep Lagoon just north of the mouth of the north canal. Manatees frequently visit the ditch because it is a seasonal source of freshwater, which the manatees drink. Manatees visit the north canal due to its moderate depths and proximity to the freshwater outfalls of the Iona Drainage District ditch. Manatee mortality from watercraft is extremely high in the immediate vicinity of Deep Lagoon, and the mortality rate has increased in recent years. The rate of manatee deaths from collisions with watercraft has increased with the popularity of motorboating. Boat registrations in Lee County rose from 13,000 in 1974 to 36,000 in 1997. The potential for mitigation offered by the enactment of speed zones has been undermined by the fact that nearly half of the boaters fail to comply with the speed limits. Water Quality The Caloosahatchee River is laden with sediments, partly due to intermittent discharges from Lake Okeechobee. Seagrass in the riverbottom cannot grow in water much deeper than four feet. Some seagrass grows at the mouth of Deep Lagoon, but little seagrass extends into the lagoon itself. The water quality in the canals is very poor for dissolved oxygen and copper. Applicant stipulated that the water quality in Deep Lagoon violates state standards for dissolved oxygen, copper, and coliform bacteria. In 1997, the canals violated water quality standards for dissolved oxygen nearly each time sampled during the wet season and one-third of the times sampled during the dry season. The dissolved oxygen levels violated even the lower standards for Class IV agricultural waters two-thirds of the times sampled during the wet season. In 1997, the canals violated water quality standards for copper in the water column each time sampled during the wet season and two-thirds of the times sampled during the dry season. During three of the dry season samplings, copper levels were 20 to 30 times lawful limits. The three lowest wet season copper levels were double lawful limits. Copper is a heavy metal that is toxic to a wide range of marine organisms. Copper is applied to boat hulls to prevent marine life from attaching to the hulls. In 1997, the canals violated water quality standards for total coliform bacteria (for any single reading) three of the 60 times sampled during the dry season and one of the 56 times sampled during the wet season. The canals violated the more relaxed, 20-percent standard (which is violated only if 20 percent of the readings exceed it) during the wet season, but not during the dry season. In 1997, the canals violated water quality standards for lead in the water column in one sample (by 25 percent) out of 36, but did not violate water quality standards for oil and grease or fecal coliform bacteria. Results of testing for mercury in the water column (as opposed to sediments) are not contained in the record. As compared to 1987, the water quality in the canals has improved in all but one important respect. In 1987, the water column readings for copper were five to six times higher than the highest 1997 reading. In 1987, the total coliform bacteria were too numerous to count because the colonies had grown together in the sample. However, comparing the April 1987 data with the May 1997 data for the same approximate times of day and the same locations, the dissolved oxygen levels in the three canals have declined dramatically in the last 10 years. Ten years ago, in a one-day sampling period, there were no reported violations; ten years later, in a one-day sampling period, there were four violations. Even worse, the amount of dissolved oxygen in the water during daylight hours has been halved in the last 10 years with a smaller decrease during nighttime hours. Original Permit There are three types of permits relevant to these cases. The first is a dredge and fill permit (sometimes referred to in the record as a wetland resource permit or water resource permit)(DAF permit). The second is a surface water management (sometimes referred to in the record as a management and storage of surface water (MSSW) permit or stormwater management permit)(SWM permit). The third is an environmental resource permit (ERP). Several years ago, responding to a mandate from the Legislature, DEP and the water management districts consolidated DAF permits, which historically were issued by DEP, and SWM permits, which historically were issued by the water management districts, into ERPs. At the time of this change, DEP adopted, within the jurisdictional areas of each water management district, certain of the rules of each district. In 1988, DEP issued a DAF permit to Applicant's predecessor in title for additional wet slips (as modified, the Original Permit). Due partly to the likelihood of the replacement of some older, smaller slips with larger slips, there is some uncertainty as to the precise number of wet slips that Applicant would be able to construct under the Original Permit. However, Applicant would be able to construct approximately 89-113 new wet slips, with an additional 14,440 square feet of overwater decking, so as to raise its marina capacity to 150-174 wet slips. Applicant also plans to construct 227 dry slips, so as to raise its marina capacity to 427 dry slips, and add 115,000 square feet of buildings, including a restaurant. In general, the Original Permit authorizes Applicant to renovate and expand an existing marina from 61 wet slips to 174 wet slips by: excavating 0.358 ac of uplands to create a flushing canal, installing 375 linear feet of seawall along the sides of the flushing canal, excavating 2.43 ac of submerged bottom to remove contaminated sediments, backfilling 2.41 acres of the dredged area (the main basin and south canal to -7 ft. MLW and the north canal to -6 ft. MLW) with clean sand, renovating the existing 61 slips, and constructing an additional 14,440 square feet of overwater decking for 113 new slips, providing after-the-fact authorization for construction of 2 finger piers, creating a 400 sq. ft. mangrove fringe, constructing 180 linear feet of seawall in the vicinity of the mangrove fringe, and relocating and upgrading fueling facilities. The record contains various references to "MLW" or "mean low water," "MHW" or "mean high water," and "NGVD" or "National Geodetic Vertical Datum." The drawings attached to the Original Permit state that MHW equals 0.96 feet NGVD and MLW equals about 0.40 feet NGVD. The Original Permit authorizes activities to proceed in three phases: First, the majority of the water quality improvement measures will be implemented as required in Specific Condition 5. Second, the over water docking structures will be constructed and the fueling facilities will be upgraded and relocated as required in Specific Conditions 6 and 7. Third, the new slips will be occupied in accordance with the phasing plan in Specific Condition 9. Specific Condition 5 imposes several requirements designed "to ensure a net improvement in water quality." Among these requirements is that Applicant must obtain the ERP that is the subject of DOAH Case No. 98-5409 (New Permit). Specific Condition 5 states: In order to ensure a net improvement to water quality within the basin, the construction of any new docking structures or installation of any new pilings shall not occur until the below-listed conditions (A-K) have been met. . . . A baseline water quality study . . .. A stormwater treatment system providing treatment meeting the specifications of Florida Administrative Code 40E-4 for all discharges into the basins from the project site shall be constructed. . . . The boat wash area shall be re-designed and constructed as shown on Sheets 23 and 23A. All water in the washdown area shall drain into the catch basin of the wastewater treatment system shown on Sheet 23. The water passing through the wastewater treatment system shall drain to the stormwater management system which was previously approved by the South Florida Water Management District. The filters of the wastewater treatment system shall be maintained in functional condition. Material cleaned from the filter shall be disposed of in receptacles maintained specifically for that purpose and taken to a sanitary landfill. This system shall be maintained in functional condition for the life of the facility. [As cited, this subparagraph contains modifications stated in a letter dated March 26, 1997, from DEP to Applicant's predecessor in interest.] Contaminated sediments shall be dredged from the areas shown on Sheets 5 and 7 of 23. A closed-bucket clam shell dredge shall be used. The north canal shall be dredged to at least -9.9 feet MLW and backfilled with clean sand to -6 feet MLW. The [main] basin shall be dredged to at least -7.3 feet MLW and backfilled with clean sand to -7 feet MLW. The south canal shall be dredged to at least -10.5 feet MLW and backfilled with clean sand to at least -7.0 feet MLW. Backfilling shall be completed within 120 days of completion of dredging. . . . The sediments shall be placed directly in sealed trucks, and removed to a self-contained upland disposal site which does not have a point of discharge to waters of the state. A channel, 260 ft. long, 60 ft. wide, with a bottom elevation of -4.5 ft. MLW shall be excavated between the north canal and the main basin to improve flushing. * * * K. Upon completion [of] conditions A-J above, renovation of the existing 61 wet slips and construction of the 113 additional wet slips may proceed with the understanding that construction of all 113 additional slips is at the risk of the permittee and that if the success criteria in the monitoring and occupancy program are not met, removal of all or part of the additional slips may be required by the Department. Specific Condition 8 addresses the phasing of occupancy of the wet slips. Specific Condition 8 provides: Occupancy of the additional 113 wet slips shall occur in two phases, described below. Permanent occupancy of the slips shall require [DEP] approval, contingent upon the water quality monitoring program demonstrating a statistically significant (Specific Condition 9) net improvement for those parameters which did not meet State Water Quality Standards in the baseline study. The permittee agrees that if [DEP] determines that net improvement has not occurred, or if violations of other standards occur, and if the corrective measures described in Specific Condition 10 are not successful, all of the additional slips occupied at that time shall be removed. . . . Phase I--Upon completion of the baseline water quality study and the work specified in Specific Condition No. 5, the existing 61 slips and an additional 56 slips, totalling 117 slips, may be occupied. . . . If at the end of one year of monitoring, the data generated from the water quality monitoring program shows a statistically significant improvement over baseline conditions, for those parameters in violation of State Water Quality Standards, and no violations of additional parameters, . . . the new 56 slips which were occupied shall be considered permanent. Phase II--Upon written notification from [DEP] that Phase I was successful, the remaining 57 additional slips may be occupied. Water and sediment quality monitoring shall continue for two years after the occupancy of 140 of the 174 slips. If a statistically significant net improvement to water quality over baseline conditions for those parameters in violation of State Water Quality Standards [sic] and no violation of additional parameters is shown by the monitoring data, and confirmed by [DEP] in writing, the additional slips shall be considered permanent. * * * Specific Condition 11 adds: Implementation of the slip phasing plan described in Specific Condition 8 shall be contingent on compliance of boaters with existing speed zones in the Caloosahatchee River and trends in manatee and [sic] mortality. . . . Approval of additional slips will depend upon manatee mortality trends and boater compliance with speed zones in the Caloosahatchee River and additional slips may not be recommended. . . . Based on the results of the evaluations of Phases I and II, [DEP] may require that slips be removed to adequately protect manatees. Specific Condition 12 requires the construction of a 400 square-foot intertidal area for the planting of mangroves to replace the mangroves lost in the construction of the flushing channel. Specific Condition 14 prohibits liveaboards at the marina. Specific Condition 15 adds various manatee-protection provisions. Plan Views C and D, which are part of the Original Permit, depict submerged bottom elevations for the north and central canals, as well as from the south canal at its intersection with the central canal. Dated August 30, 1995, these "existing" bottom elevations across the mouth of the north canal are about -7, -8, and -4 feet (presumably MLW; see second note to Plan View B). The western two-thirds of the north canal passes over bottoms of about -6 feet MLW. Proceeding east, the bottom deepens to -7 to -9 feet MLW before it tapers up to -7, -6, and finally -3 feet MLW at the head; and the eastern third of the north canal passes over bottoms of about -7 feet MLW that tapers up to -6 feet and -3 feet MLW. The submerged bottom at the mouth of the central canal is about -8 to -9 feet MLW. The bottom drops to -6 to -10 feet MLW at the intersection with the south canal. Proceeding east, the bottom deepens slightly as it reaches the head, where it is -8 feet MLW. The submerged bottom of the south canal runs from -9 feet MLW at the intersection with the central canal and runs about 0.5 feet deeper at the head. Petitioner and others challenged the issuance of the Original Permit in 1988. The permit challengers appealed a final order granting the Original Permit and certifying, under the federal Clean Water Act, that state water quality standards were met. DEP premised its certification on the concept that water quality standards encompassed a net improvement in water quality of the poorly flushed canals. In Sheridan v. Deep Lagoon Marina, 576 So. 2d 771, 772 (Fla. 1st DCA 1991), the court, relying on the above-described 1987 water quality data, noted the "very poor water quality" of Deep Lagoon, as reflected in part by the presence of oil and grease 20 times the Class III standard, copper 13 times the standard, lead 20 times the standard, mercury 1000 times the standard, and coliform bacteria "too numerous to count." However, the court affirmed the issuance of the Original Permit under the statutory authorization of a permit where ambient water quality does not meet applicable standards, but the activity will provide a net improvement to the waters. On the certification issue, though, the court reversed and remanded. The court held that the hearing officer erroneously excluded evidence on DEP's certification of the activity as in compliance the federal Clean Water Act. Following remand, DEP issued a final order issuing the Original Permit. On the certification issue, the final order revoked the earlier certification of compliance and, citing 33 United States Code Section 1341 as authority, waived certification as a precondition to federal permitting. Maintenance Dredging: DOAH Case No. 98-3901 Background The contentions of Petitioner and Intervenor as to maintenance dredging are: the proposed dredging exceeded what was necessary to restore the canals to original design specifications or original configurations; the proposed dredging exceeded the maximum depth allowable for maintenance dredging of canals; the work was not conducted in compliance with Section 370.12(2)(d), Florida Statutes; the spoil was not deposited on a self-contained upland site to prevent the escape of the spoil into waters of the state; and the dredge contractor did not use control devices and best management practices for erosion and sediment control to prevent turbidity, dredged material, and toxic or deleterious substances from discharging into adjacent waters during maintenance dredging. On March 3, 1998, Applicant's engineering consultant submitted drawings to DEP with notification that Applicant intended to "maintenance dredge the internal canals of Deep Lagoon Marina," in conformity with Rule 62-312.050(e), Florida Administrative Code. The letter describes the proposed dredging as mechanical "with no discharge back into Waters of the State." The letter assures that Applicant's contractor will use turbidity curtains "around the dredging and spoil unloading operation" and advises that the contractor will unload the spoil "to the north peninsula upland area." The letter states that the dredging "will be to the design depth/existing canal center line depth of -7 NGVD," which was established by the Original Permit, and will be "done in conjunction with the required dredging under [Original Permit] Condition 5(D)." The consultant attached to the March 3 letter several drawings showing the dredging of all three canals. For each canal, the drawings divide the dredging into two areas. For 1.82 acres, the contractor would dredge contaminated materials from the dead-ends of the three canals (for the south canal, a portion running from the head along the northeast half of the canal) and then replace these materials with clean backfill material. This information is for background only, as the Original Permit authorized this contaminant dredging. For 4.84 acres, which run through the remainder of the three canals, the contractor would maintenance dredge in accordance with the cross-sections provided with the letter. The cross-sections for the north canal reveal relatively extensive dredging beyond the vegetation lines on both sides of the canal bottom. The dredging would extend up to, but not beyond, the edges of the prop roots of the mangroves on both sides of the canal bottom. The contours reveal variable, proposed slope profiles for the submerged sides of the canals, but the dredging would substantially steepen the submerged slopes of the north canal. It is difficult to estimate from the cross-sections the average depth and width to be dredged from the north canal, but it appears that the cross-sections proposed the removal of substantial spoil (an average of 4-6 feet) from areas from 20-40 feet from each side of the deepest point in the north canal. The dredging would alter the two most affected cross-sections, which are just inside the mouth of the north canal, by widening the deepest part of the canal bottom by 85 feet--from about 15 feet to about 100 feet. The drawings proposed much smaller alterations to the bottoms of the central and south canals: typically, spoil about 2 feet deep and 20 feet wide. All but one of the cross-sections revealed that spoil would be dredged only from one side of the deepest point. Additionally, the dredging in these canals would not involve any submerged vegetation; all but one of the canal sides was lined by existing seawalls. By letter dated March 13, 1998, DEP stated that it had determined that, pursuant to Rule 40E-4.051(2)(a), Florida Administrative Code, the proposed activity was exempt from the requirement that the Applicant obtain an ERP. The letter warns that, pursuant to Chapter 62-302, Florida Administrative Code, the construction and operation of the project must not cause water quality violations. The letter adds that DEP may revoke its determination of exemption if the "basis for the exemption is determined to be materially incorrect, or if the installation results in water quality violations." The letter provides a point of entry for persons whose substantial interests are affected by DEP's determination. Following receipt of DEP's letter acknowledging the exemption, Applicant's contractor proceeded to maintenance dredge the three canals. The dredging of the north canal took eight weeks. Applicant's contractor also performed the contaminant dredging and clean backfilling authorized by the Original Permit. As indicated in the March 3 letter and permitted in the Original Permit, the contaminant dredging took place at the dead-end heads of the north and central canals and along the northeast half of a slightly longer section of the south canal, starting from its dead-end head. In maintenance dredging the canals, Applicant's contractor did not exceed the specifications regarding depth and width stated in its March 3 letter. To the contrary, the contractor sometimes dredged slightly narrower or slightly shallower profiles than stated in the March 3 letter. For example, the contractor dredged the north canal to -6 feet NGVD (or -5.6 feet MLW), rather than -7 feet NGVD, as shown in the March 3 letter. The Depths, Widths, and Lengths of Dredging The March 3 letter asserts that -7 feet NGVD is the permitted elevation of the canal bottoms, pursuant to the Original Permit. This is incorrect in two respects. First, the assertion in the March 3 letter of a -7 foot permitted bottom elevation is incorrect for all but the relatively small part of each canal that DEP has determined is contaminated. The Original Permit specifies design elevations for canal bottoms only in the contaminated area within each canal. Nothing in the Original Permit permits bottom elevations for any portion of the bottoms of the three canals outside of these three contaminated areas. Second, the assertion in the March 3 letter of a -7 foot permitted bottom elevation is incorrect, even for the contaminated areas. The March 3 letter states -7 feet NGVD, but the Original Permit specifies bottom elevations, for contaminated areas only, of -7 feet MLW in the south and central canals and -6 feet MLW in the north canal. Thus, due to the differences between NGVD and MLW, the March 3 letter proposes dredging that would deepen the south and central canals by about five inches deeper than the depth permitted in the Original Permit and the north canal by one foot five inches deeper than the depth permitted in the Original Permit. Moreover, nothing in the record clearly establishes all aspects of the original design specifications of the three canals, whether permitted or not, or even all aspects of their original dredged configurations, if not permitted. There is no dispute concerning one aspect of the dredged configuration of the three canals: their lengths. Although there may be some dispute as to the original mean high water line near the mouths of the north and central canals, the original length of the canals is evident from the uplands that presently define them. As to the depth of the canals, although direct evidence is slight, Applicant has sufficiently proved indirectly the depths of the mouths of the canals pursuant to original design specifications or, if not designed, original configurations. The proved bottom elevations are -7 feet NGVD for each canal. Applicant proved these depths based on the prevailing elevations in Deep Lagoon in the vicinity of the mouths of the north and central canal and bottom elevations in areas of Deep Lagoon that are not prone to sedimentation. Additional proof of the bottom elevation of -7 feet NGVD at the mouths of the canals is present in the slightly higher permitted bottom elevations at the dead- ends of the north and central canals and landward portion of the south canal. There is some problem, though, with the proof of the depth of the canal bottoms between their mouths and heads (or, for the south canal, its landward portion of known contamination). Although the problem of the depth of the canals between their heads and mouths might be resolved by inferring a constant bottom elevation change from the deeper mouth to the shallower head, an unresolveable issue remains: the width of this maximum depth. As already noted, without deepening the deepest part of either cross-section, the contractor widened the deepest points along two cross-sections by 85 feet each. In terms of navigability and environmental impact, the width of the maximum depth of a canal is as important as its maximum depth. As to the width of the lowest bottom elevations of the canals, Applicant has produced no proof of original design specifications or, if not designed, original configurations. Nor has Applicant produced indirect proof of historic widths. Nothing in the record supports an inference that Applicant's predecessor in interest originally dredged the canal bottoms as wide as Applicant "maintenance" dredged them under the claimed exemption. Nothing in the record supports an inference that Applicant's predecessor geometrically dredged the canals so that their sides were perpendicular to their bottoms. Nothing in the record describes a sedimentation problem that might have narrowed the canals by such an extent that the dredging of the present widths, especially in the north canal, would be restorative. Nothing in the record even suggests that the original motive in dredging was navigability, which might have yielded relatively wide canal bottoms, versus upland fill, which would yield canal bottoms as wide as needed, not for navigability, but for uplands- creation. After consideration of all the evidence, no evidence supports a finding that the proposed dredging profiles, in terms of the widening of the areas of lowest elevation in each canal bottom, bear any resemblance whatsoever to the original canal profiles, as originally (or at any later point) designed or, if not designed, as originally (or at any later point) configured. It is at least as likely as not that this is the first time that these canal bottoms, especially the north canal bottom, have ever been so wide at any bottom elevation approaching -7 feet NGVD. There is simply no notion of restoration or maintenance in the dredging that produced these new bottom profiles for these three canals. Transforming MLW to NGVD, -5 feet MLW is -4.6 feet NGVD. All proposed and actual maintenance dredging in the three canals dredged the canal bottoms to elevations lower than -5 feet MLW (or -4.6 feet NGVD), despite the absence of any previous permit for construction or maintenance of the canal from the Trustees of the Internal Improvement Trust Fund or the United States Army Corps of Engineers. Impact of Dredging on Manatees and Spoil Containment Prior to dredging, Applicant deployed turbidity curtains around the mouths of the two canals that discharge directly into Deep Lagoon. In this case, the turbidity curtains performed two functions. They contained turbidity and resuspended bottom contaminants within the mixing zone behind (or landward of) the curtains, and they excluded manatees from the dangerous area behind the curtains where the dredging was taking place. Petitioner and Intervenor object to the use of the turbidity curtains on two general grounds. First, they claim that the curtains failed to contain turbidity and resuspended contaminants from escaping the mixing zone. Second, they claim that the curtains adversely affected manatees. As executed, the maintenance dredging did not result in the release of turbidity or resuspended contaminants outside of the mixing zone due to the use of turbidity curtains. Applicant's contractor ensured that the curtains extended from the water surface to the canal bottom and sufficiently on the sides to prevent the escape of turbidity or resuspended contaminants. Although the March 3 letter did not indicate where the contractor would deploy the turbidity curtains, the important point, in retrospect, is that the contractor properly deployed the curtains. There is some question whether turbidity or resuspended contaminants flowed across the mangrove fringe and into the Iona Drainage District ditch. Applicant's witness testified that water flows across the fringe only during the highest three or four tides per month. Petitioner and Intervenor's witness testified that water flows across the fringe as often as twice per day. The actual frequency is likely somewhere between these two extremes, but, regardless of the frequency, there is insufficient evidence to find that any turbidity or resuspended contaminants flowed from the north canal into the Iona Drainage District ditch. Nor did the deployment of the turbidity curtains injure, harm, possess, annoy, molest, harass, or disturb any manatees. Applicant and its contractor carefully checked each canal for manatees before raising the turbidity curtains at the mouth of each canal, so as not to trap any manatees in the area behind the curtains. By ensuring that the curtains extended to the canal bottom and extended fully from side to side, they ensured that the curtains excluded manatees during the dredging. There is no evidence that a manatee could have entered the north canal from the Iona Drainage District ditch by crossing the red mangrove fringe; any breaks in the fringe were obstructed by prop roots that prevented even a kayaker from crossing the fringe without portaging. Applicant and its contractor checked for manatees during dredging operations. Petitioner and Intervenor contend that the mere presence of the turbidity curtains in an area frequented by manatees adversely affected the animals. However, this argument elevates a speculative concern with a manatee's response to encountering an obstruction in its normal path over the practical purpose of curtains in physically obstructing the animal so as to prevent it from entering the dangerous area in which the dredge is operating, as well as the unhealthy area of turbidity and resuspended contaminants in the mixing zone. Under the circumstances, the use of the turbidity curtains to obstruct the manatees from visiting the dredging site or mixing zone did not adversely affect the manatees. In general, there is no evidence of any actual injury or harm to any manatees in the course of the dredging or the preparation for the dredging, including the deployment of the turbidity curtains. Petitioner and Intervenor offered evidence that maintenance dredging would result in more and larger boats and deterioration of water quality, which would both injure the manatees. However, as noted in the conclusions of law, the Administrative Law Judge excluded from DOAH Case No. 98-3901 such evidence concerning long-term impacts upon the manatees following the dredging. As for spoil containment, Applicant's contractor segregated the contaminated spoil from noncontaminated spoil by placing the contaminated spoil in a lined pit in the uplands. The contractor also brought onto the uplands clean fill mined from a sand quarry for backfilling into the dredged contaminated areas. There is evidence of the clean fill subsiding from its upland storage site and entering the canal waters in the mixing zone. Partly, this occurred during the loading of the barge, which transported the clean fill to the dead-end heads of the canals where the fill was placed over the newly dredged bottoms. The fill escaped into the water at a location about 100 feet long along the north seawall of the central canal, but the evidence does not establish whether this location was within the contaminated area at the head of the canal or whether the maintenance or contaminant dredging had already taken place. If the fill subsided into the water inside of the contaminated head of the south canal and the subsidence occurred prior to the contaminant dredging, the subsidence was harmless because the contractor would remove the fill during the dredging. If the fill subsided into the water inside the contaminated head of the south canal and the subsidence occurred after the contaminant dredging, the subsidence was harmless because the contractor intended to add the fill at this location. If the fill subsided into the water outside of the contaminated head of the south canal and the subsidence occurred prior to maintenance dredging, the subsidence was harmless because the contractor would remove the fill during the dredging. If the fill subsided into the water outside the contaminated head of the south canal and the subsidence occurred after the maintenance dredging, the subsidence was harmless because it restored the canal bottom to a higher elevation following the dredging to an excessively low elevation. The subsidence of the clean fill into the water along the north side of the central canal is the only material that entered the water from the uplands during the dredging. Specifically, there is no evidence of dredged spoil entering the water from the uplands during or after the dredging. There is also no evidence that the maintenance dredging significantly impacted previously undisturbed natural areas. There is no evidence of such areas within the vicinity of Deep Lagoon Marina. New Permit: DOAH Case No. 98-5409 New Permit Seeking to satisfy certain of the requirements of Original Permit Specific Condition 5, Applicant filed with DEP, on December 10, 1997, an application for an ERP and water quality certification to construct a surface water management system to serve 15.4 acres of its 24-acre marina. Prior to its reformulation as an ERP, the New Permit sought by Applicant would have been a SWM permit. The application notes that the general upland elevation is 5 feet NGVD and that stormwater runoff presently sheetflows directly to adjacent waterways without any treatment. During the application process, Applicant's engineer Christopher Wright, submitted a letter dated February 27, 1998, to Jack Myers, who is a Professional Engineer II for DEP. In response to a request from DEP for a "written procedure . . . to assure the proper functioning of the proposed . . . system," the letter states: Since the system is not designed as a retention system and does not rely upon infiltration to operate properly[,] operation and maintenance is minimal. Items that will need regular maintenance are limited to removal of silt and debris from the bottom of the drainage structures and the bleed down orifice of the control structure. A maintenance and inspection schedule has been included in this re-submittal as part of Exhibit 14. In relevant part, Exhibit 14 consists of a document provided Mr. Wright from the manufacturer of the components of the surface water management system. The document states that the manufacturer "recommends that the landowner use this schedule for periodic system maintenance . . .." The document lists 16 sediment-control items, but it is unclear whether all of them are incorporated into the proposed system. Four items, including sediment basins, require inspections quarterly or after "large storm events" and maintenance consisting of the removal of sediment; the "water quality inlet" requires inspections quarterly and maintenance consisting of "pump[ing] or vacuum[ing]"; the "maximizer settling chamber" requires inspection biannually and maintenance consisting of "vacuum[ing] or inject[ing] water, suspend silt and pump chamber"; and the "chamber" requires inspection annually and the same maintenance as the maximizer settling chamber. The proposed system includes the water quality inlet and one of the two types of chambers. By Notice of Intent to Issue dated November 5, 1998, DEP provided notice of its intent to issue the New Permit and certification of compliance with state water quality standards, pursuant to Section 401 of the Clean Water Act, 33 United States Code Section 1341. On February 6, 1999, DEP revised the notice of intent by withdrawing its certification of state water quality compliance. As it did with the Original Permit, DEP again waived state water quality certification. This waiver is consistent with a letter dated February 2, 1998, in which then-DEP Secretary Virginia Wetherell announced that DEP would waive state water quality certification for all activities in which the agency issues an ERP based on the "net improvement" provisions of Section 373.414(1)(b), Florida Statutes. The notices of intent (collectively, NOI) recite the recent permitting history of the marina. This history includes the Original Permit, a since-expired MSSW permit issued in 1988 by SFWMD, and then-pending requests--apparently all since granted--to revise the Original Permit by replacing the flushing canal with culverts, relocating a travel lift from the main canal to the north canal, and adding liveaboards to the marina. (Although mentioned below, these revisions, in and of themselves, do not determine the outcome of DOAH Case No. 98-5409.) Reviewing the proposed development for the site, the NOI states that the northerly part of the project would contain an indoor dry boat storage barn, a marina service operation consisting of a ship store and miscellaneous buildings, a harbor master building, an upgraded fueling facility, a parts and service center, a restaurant, retail and commercial facilities, and paved parking areas. The southerly part of the project would contain a new indoor dry boat storage barn, a boat dealership building, and paved parking areas in place of the existing buildings. The NOI states that the proposed water quality treatment system would comprise dry detention systems of several underground vaults with an overall capacity based on the total impervious area, including roofs, receiving 2.5 inches of rain times the percentage of imperviousness. Given the relatively high imperviousness of the finished development, this recommended order considers the percentage of imperviousness to be 100, but ignores the extent to which the post-development pervious surfaces would absorb any rainfall. For storms producing up to 2.5 inches of runoff, the proposed surface water management system, of which the underground vaults are a part, would trap the runoff and provide treatment, as sufficiently sized contaminants settled into the bottom of the vaults. Because the vaults have unenclosed bottoms, the proposed system would provide incidental additional treatment by allowing stormwater to percolate through the ground and into the water table. However, the system is essentially a dry detention system, and volumetric calculations of system capacity properly ignored the incidental treatment available through percolation into the water table. The New Permit notes that the wet season water table is 1.2 feet NGVD, and the bottom of the dry detention system is 2.5 feet NGVD. This relatively thin layer of soil probably explains why DEP's volumetric calculations ignored the treatment potential offered by percolation. The relatively high water table raises the possibility, especially if Applicant does not frequently remove the settled contaminants, that the proposed system could cause groundwater contamination after the thin layer of soil is saturated with contaminants. In any event, the system is not designed for the elimination of the settled contaminants through percolation. The treatment system for the boat wash areas would be self-contained, loop-recycle systems that would permit the separation of oil and free-settling solids prior to reuse. However, the NOI warns that, "during heavy storm events"-- probably again referring to more than 2.5 inches of runoff--the loop-recycle systems would release untreated water to one of the underground vaults, which would, in turn, release the untreated water into the canals. Due to the location of the boat wash areas, the receiving waters would probably be the north canal. As reflected in the drawings and the testimony of Mr. Wright, the surface water management system would discharge at three points: two in the north canal and one in the south canal. (Vol. I, p. 206; future references to the Transcript shall cite only the volume and page as, for example, Vol. I, p. 206). 67. The NOI concludes that Applicant has provided affirmative reasonable assurance that the construction and operation of the activity, considering the direct, secondary and cumulative impacts, will comply with the provisions of Part IV of Chapter 373, F.S., and the rules adopted thereunder, including the Conditions for Issuance or Additional Conditions for Issuance of an environmental resource permit, pursuant to Part IV of Chapter 373, F.S., Chapter 62-330, and Sections SFWMD--40E-4.301 and 40E-4.302, F.A.C. The construction and operation of the activity will not result in violations of water quality standards and will not degrade ambient water quality in Outstanding Florida Waters pursuant to Section 62-4.242, F.A.C. The Applicant has also demonstrated that the construction of the activity, including a consideration of the direct, secondary, and cumulative impacts, is clearly in the public interest, pursuant to Section 373.414(1)(a), F.S. However, the design capacity of the proposed surface water management system raises serious questions concerning the water quality of the discharges into the canals. Mr. Wright initially testified that the surface water management system would be over-taxed by "an extreme storm event, probably a 25- year storm event . . .." (Vol. I, pp. 208-09). The record contains no evidence of the frequency of the storm event that produces 2.5 inches of runoff for the relatively impervious post- development uplands; the record contains no evidence even of the frequency of the storm event that produces 2.5 inches of rainfall. According to Mr. Wright, the 25-year storm would typically produce 8-10 inches of rain. (Vol. I, pp. 223 and 233). As already noted, the relatively large area of imperviousness following upland development and the relative imperviousness of the upland soils present at the site suggest that the runoff will be a relatively large percentage of the rainfall produced by any given storm event. It thus appears that the design capacity of the system is for a storm substantially smaller and substantially more frequent than the 25-year storm. Attached to the NOI is a draft of the New Permit, which contains numerous specific conditions and conforms in all respects with the NOI. Omitting any mention of SFWMD's Basis of Review, the New Permit addresses, among other things, the operation, inspection, and maintenance of the components of the proposed system. As set forth in the testimony of Michael Bateman, who is a Professional Engineer III and statewide stormwater coordinator for DEP, the surface water management system's operation depends on periodic pumping of the "thick, fine sediment," which appears to be a "cross between mud and sand" and will be laden with oil, grease, metals, and other contaminants. (Vol. II, p. 66). However, contrary to Mr. Bateman's assurance that the New Permit requires the periodic pumping or removal of contaminants that have precipitated out of the runoff in the dry detention system and dropped to the bottom sediment (Vol. II, p. 20), neither the NOI nor the New Permit requires, in clear and enforceable language, the periodic removal of settled solids from the underground vaults or their manner of disposal. New Permit Specific Condition 8 requires that Applicant maintain the boat wash area in "functioning condition," although specific inspection and maintenance requirements are omitted from the New Permit. New Permit Specific Condition 7 requires that Applicant "inspect and clean" all stormwater inlets "as necessary, at least once a month and after all large storm events," although the New Permit fails to specify that cleaning shall be by either pumping or vacuuming. By contrast to the marginally adequate inspection and maintenance provisions applicable to the boat wash area (inspections are required in Specific Condition 6, cited below) and stormwater inlets, the New Permit completely fails to specify enforceable inspection and maintenance requirements for the underground vaults. New Permit Specific Condition 6 addresses the operation of the vault as follows: Upon completion of the construction of the stormwater collection and underground vault (Infiltrator) systems and on an annual basis thereafter by September 30 of each year, the Permittee shall submit reports to the Department as to the storage/treatment volume adequacy of the permitted system. The reports shall also include, but not be limited to, the condition of stormwater inlets and control structures as to silt and debris removal and the condition of the inlet wire mesh screens to function properly. The boat wash down areas shall be inspected for proper operation, i.e., no signs of wash water overflows from the containment area, condition of the containment area curbing, etc. Such reports shall include proposal of technique and schedule for the maintenance and/or repair of any deficiencies noted and shall be signed and sealed by a Florida registered Professional Engineer. A report of compliance with the aforementioned proposal shall be submitted by the Professional Engineer to the Department upon completion of the proposed work which shall be accomplished within three months of the initial report for each year. New Permit Specific Condition 6 requires annual reports concerning the sufficiency of the capacity of the underground vaults (first sentence), annual reports of the status of silt- and debris-removal from the inlets and control structures and the condition of the inlet wire mesh screens (second sentence), inspection at no stated intervals of the boat wash area (third sentence), and annual reports with suggestions of maintenance schedules and repairs for the items mentioned in the first two sentences (fourth sentence). New Permit Specific Condition 6 promises only the preparation of a maintenance schedule at some point in the future. Failing to supply an enforceable inspection and maintenance program, Specific Condition 6 indicates that Applicant shall consider in the future techniques and scheduling of maintenance, presumably based on the report concerning system capacity. Such a requirement may or may not impose upon Applicant an enforceable obligation to adopt an enforceable inspection and maintenance program in the future, but it does not do so now. There is no reason why the New Permit should not impose upon Applicant an initial, enforceable inspection and maintenance program incorporating, for example, the clear and enforceable requirements that Applicant inspect all of the underground vaults no less frequently that once (or twice, if this is the applicable recommendation of the manufacturer) annually and, at clearly specified intervals, remove the sediments by resuspending the sediments in the water, pumping out the water, and disposing of the effluent and sediments so they do not reenter waters of the state. Although the record does not disclose such requirements, Applicant could possibly find manufacturer's recommendations for the boat wash components and incorporate them into an enforceable inspection and maintenance program more detailed than that contained in Specific Condition 8. However, for the reasons noted below, water quality considerations require a substantial strengthening of such a program beyond what is set forth in this paragraph as otherwise acceptable. At present, the bottom line on inspection and maintenance is simple: the New Permit does not even incorporate by reference the manufacturer's recommended inspection and maintenance schedule, which Mr. Wright provided to Mr. Myers. Nor was this shortcoming of the New Permit in its treatment of inspection and maintenance necessarily missed by Mr. Wright. He testified that he submitted to DEP the manufacturer's maintenance program (Vol. I, p. 205), but when asked, on direct, if the "permit in any way incorporate[s] the commitment in your application to this maintenance?" Mr. Wright candidly replied, "That I don't know." (Vol. I, p. 206). Satisfaction of Basis of Review Section 5 Basis of Review Section 5--specifically Section 5.2.1(a)--imposes the "volumetric" requirement of 2.5 inches times the percentage of imperviousness, as discussed above and in the conclusions of law. Petitioner does not dispute Applicant's compliance with this volumetric requirement, and the record amply demonstrates such compliance. Applicability of Basis of Review Section 4 The main issues in this case are whether the environmental and water quality requirements of Basis of Review Section 4 apply to the direct, secondary, and cumulative impacts of the proposed activity. Because the record lacks any indication of other relevant pending or vested permits, without which, as noted in the conclusions of law, one cannot assess cumulative impacts, the remainder of the findings of fact will not discuss cumulative impacts, although, to some extent, increased boating pressure constitutes a secondary impact and a cumulative impact. Without regard to the differences between direct and secondary impacts, DEP has taken the position in this case that it could lawfully issue the New Permit upon satisfaction of the volumetric requirements of Basis of Review Section 5 and without consideration of the requirements of Basis of Review Section 4. In large part, DEP's witnesses justify this position by reliance on the historic differences between DAF permits and SWM permits and the fact that the New Permit is a former-SWM ERP. As discussed in detail in the conclusions of law, the Basis of Review imposes different requirements upon former-DAF and former-SWM ERPs, although the Basis of Review does not refer to DAF or SWM permits by their former names. The identifying language used in the Basis of Review for former-DAF ERPs is "regulated activity" "located in, on, or over surface waters or wetlands." References to "regulated activity" without the qualifying clause indicate that the following requirement applies to former-DAF ERPs and former-SWM ERPs. Several witnesses for DEP and Applicant testified that Applicant was entitled to the New Permit upon satisfaction of the volumetric requirements of Basis of Review Section 5. For example, Mr. Wright testified that the water quality requirements for the New Permit required only a "cookbook calculation" to determine volume. (Vol. I, p. 204). Agreeing with a question that analysis of the water quality portion of the system requires "simply a straightforward mathematical calculation," Mr. Wright testified that the quality of discharged water, following treatment, will comply with state water quality standards in storms producing no more than 2.5 inches of runoff. (Vol. I, pp. 210-11). When asked to explain his answer, Mr. Wright testified, "It's kind of an implied situation, in that if you follow the guidelines that you are required to follow with respect to the calculations of water quality, that the end product is going to be in compliance with state standards." (Vol. I, p. 211). DEP witnesses agreed with Mr. Wright's analysis. For instance, Mr. Bateman testified, "The stormwater portion of the Basis of Review gets at that question [meeting water quality standards] by stating, 'if you follow the design criteria in the basis, you are presumed to meet water quality standards.'" (Vol. II, p. 40). Mr. John Iglehart, the program administrator for DEP's South District Office in Fort Myers, testified on the same point: "if . . . you meet the criteria, the engineering criteria, than you have met the presumption that you meet the rule." (Vol. III, p. 52). Mr. Myers also agreed, testifying, "with the stormwater management system, it's for the most part, let's say, fairly cut and dried as far as meeting criteria that is established within these rules and Basis of Review." (Vol. III, p. 144). He added: "Since the criteria for reviewing stormwater management systems and the discharge is based upon a presumed compliance with stormwater criteria and with state water quality, it is presumed it [the proposed system] does meet it." (Vol. III, p. 148). Mr. Bateman explained the historic basis for the water quality presumption given surface water management systems that meet the volumetric requirements: the ERP is a combination of the surface water management rules and the environmental . . ., the dredge-and-fill, and they didn't merge, they didn't marry very well in certain areas. In stormwater we look at--it's a technology- based criteria. We say, "If you build it this way, treat 80 percent of the average annual pollutant load, we're going to give you the permit on the presumption that you're doing the best you can. You're going to meet standards. Once you get into the wetlands, we take--we put on whole new sets of glasses. ALJ: Are you saying that the old dredge-and- fill is more performance-based, and the old MSSW is more technology-based, in that if you've put in the required technology, you've done your job? WITNESS: That is--yes. Dredge-and-fill is a more case by case. We look at the water quality. We look at ambient conditions. We look at hydrographics [here, largely tidal flushing]. It's more like a waste load allocation in that we're very specific. In stormwater, we can't afford to be. MS. HOLMES: So what you're saying is you can't point to the specific rule provision or regulation that excludes these criteria from surface water management systems? WITNESS: Well, you have to read [Basis of Review] Section 4 as a whole. 4.1 is specific to wetlands and other surface waters. 4.2 is environmental review. I mean, if you look at the thing in total, and the--and I realize it's confusing. But these rules are exactly the same in all the water management districts. They were developed together as the wetland criteria, the new dredge-and-fill criteria. They're exactly the same. The stormwater rules of all the [water management districts] is all different. That is for another day, making those all consistent. So these environmental wetland- type dredge-and-fill criteria are all the same, and they refer to in-water impact. [All references in the transcript to "end water" should have been "in-water."] ALJ: What do you mean by that term, "in- water impact?" WITNESS: In other words, dredge-and-fill impact. Construct and--I can't-- MS. HOLMES: May I continue, then? ALJ: Let him answer. What were you going to say? WITNESS: I think it takes a little knowledge of how these [rules] developed to know how they're applied, unfortunately. In other water management districts, it's clearer that these are in-water impacts. (Vol. II, pp. 57-59). In testifying to the exclusivity of the volumetric requirements in Basis of Review Section 5, with respect to former-SWM ERPs, these witnesses likewise opined that the secondary-impact analysis required in Basis of Review Section 4 also was inapplicable to the New Permit. For example, after testifying both ways on the necessity of considering secondary impacts in issuing former-SWM ERPs, Mr. Bateman concluded, "I'm not sure that [the requirement of considering secondary impacts] applies in this case. Certainty the rules apply, I mean, the rules apply. But certain rules are not applicable in this particular instance. I mean, I'm trying to think of a secondary impact associated with stormwater system, and it's difficult for me to do so." (Vol. II, p. 45). Mr. Bateman then testified that DEP did not consider such secondary impacts, as additional boat traffic, and probably did not consider cumulative impacts, such as other marinas. (Vol. II, pp. 51-52). In response to a question asking to what extent DEP considered post-development inputs of contaminants, such as heavy metals, when issuing a former-SWM ERP, Mr. Bateman testified: I have to tell you, very little. I mean, we--stormwater is pretty black and white. The link to secondary and cumulative impact is generally associated with in-water impact. And I realize the line is a little grey here. When we build a Wal-Mart, we don't think about how many cars it's going to put on [U.S. Route] 41 and what the impact might be to an adjacent lake. We just don't. It would be a little burdensome. In this case, I mean, it's a little greyer. (Vol. II, p. 47). Mr. Bateman was then asked to compare the relative impacts from a vacant, but developed, upland without a surface water management system with a proposed activity that would add a surface water management system to facilitate an intensification of land uses on the site so as to add new contaminants to the runoff. Mr. Bateman testified that DEP would apply only the volumetric requirement and not address the complex issue of weighing the potential environmental benefit of a new surface water system against the potential environmental detriment of contaminant loading (at least in storm events greater than the design storm event). Mr. Bateman explained: "The way it works, it is not a water quality-based standard. In other words, we don't go in and say it's so many pounds [of contaminants] per acre per year now. We're going to make it this many pounds per acre per year, and look at it in a detailed fashion. We do the [Best Management Practices], retain an inch and you're there." (Vol. II, p. 49). Agreeing with Mr. Bateman that DEP was not required to consider secondary impacts resulting from the regulated activity, Mr. Iglehart testified: "It's our thought that we don't really look at secondary and cumulative impacts for the stormwater permit. . . . If it [the former-SWM ERP application] meets the criteria, it gets the permit. That--in the ERP, the previous dredge-and-fill side looks at the secondary and cumulative. The stormwater just--like Mr. Bateman testified." (Vol. III, p. 52). After some ambivalence, Mr. Myers also testified that DEP was not required to consider secondary impacts for the New Permit: WITNESS: . . . I did not or I do not consider secondary impacts for the stormwater management system. MS. HOLMES: So, what about cumulative impacts? WITNESS: No. MS. HOLMES: So it's your testimony that you did not review secondary and cumulative impacts-- WITNESS: That's correct. MS. HOLMES: --of this system? WITNESS: What I can say is that the existing system out there, from what I can tell, does not have any stormwater treatment. Basically, it's running off into the canals. The proposed project will provide stormwater treatment for, not only the new construction, which is proposed mainly on the northern peninsula, but it is also provided for that area which is now existing, it will provide stormwater treatment for that area also. And I consider that--I don't consider that to be a secondary impact. I see it as an offsetting improvement to potential as far as the water quality. (Vol. III, pp. 144-45). As discussed in detail in the conclusions of law, these witnesses have misread the provisions of the Basis of Review applicable to the New Permit. As noted in the conclusions of law, the requirements in the Basis of Review of analysis of secondary and cumulative impacts upon water quality and manatees are not limited to in-water or former-DAF activities. Satisfaction of Basis of Review Section 4 Direct vs. Secondary Impacts In terms of construction, the direct impacts of the proposed surface water management system are negligible. Nothing in the record suggests that the construction of the proposed system will violate any of the requirements of Basis of Review Section 4. In terms of maintenance, the direct impacts of the proposed surface water management system are negligible, except for the omission from the New Permit of any provision for the safe disposition of the contaminant removed from the underground vaults. However, the maintenance issues are better treated with the operation issues. In terms of operation, the direct impacts of the proposed surface water management system are substantial. As discussed in the conclusions of law, the analysis of the direct impacts of the operation of the proposed system is limited to the current level of uplands and marine activity at the marina. These direct impacts involve two aspects of the operation of the proposed system: the design capacity and the inspection and maintenance (including disposal of sediment) of the system components. As discussed in the conclusions of law, the secondary impacts involve the intended and reasonably expected uses of the proposed system. These impacts consist of the increased uplands and marine uses associated with the addition of 100 new wet slips, 227 new dry slips, and 115,000 square feet of building space with a restaurant. Apart from their contention that Applicant is required only to satisfy the volumetric requirements of Basis of Review Section 5, Applicant and DEP have contended that Petitioner is estopped from raising direct and secondary impacts because DEP considered these impacts when issuing the Original Permit four years ago. Perhaps the most obvious factual problem with this contention is that it ignores that the New Permit authorizes, for the first time, the construction of the 227 new dry slips and 115,000 square feet of buildings. As counsel for DEP pointed out during the hearing, the Original Permit was a DAF permit and did not extend to these upland uses. The contention that DEP considered these developments as secondary impacts because they were shown on drawings attached to the Original Permit gives too much significance to nonjurisdictional background items shown in drawings without corresponding textual analysis. More generally, the efforts of DEP and Applicant to restrict the scope of this case rely on a misreading of Original Permit Specific Condition 5. The purpose of Original Permit Specific Condition 5 is to "ensure a net improvement to water quality." The purpose of each of the requirements under Specific Condition 5 is to achieve an actual, not presumptive, improvement in water quality. Prohibiting the issuing agency from fully analyzing the direct and secondary impacts of the proposed surface water management system reduces the likelihood that the ensuing New Permit will perform its role, as envisioned in the Original Permit, of helping to achieve an actual, net improvement in water quality. The concept of a "net" improvement is exactly what DEP's witnesses disclaim having done in this case--balancing the potential environmental benefits to the water resources from the proposed surface water management system against the potential environmental detriments to the water resources from the development and land uses that are intended or reasonably expected to result from the construction of the proposed system. The failure to analyze the net gain or loss inherent in this important provision of Specific Condition 5.B undermines the likelihood that the effect of Specific Condition 5.B--a net improvement in water quality--will be achieved. It is therefore illogical to rely on Specific Condition 5.B, as DEP does, as authority for an artificially constrained analysis of the eligibility of the proposed system for a former-SWM ERP. The estoppel argument also ignores that Original Permit Specific Condition 5.B anticipated that the issuing agency would be SFWMD. It is unclear how the parties to the Original Permit, including DEP, would bind what appeared at the time to have to be SFWMD in the exercise of its lawful authority in issuing SWMs or former-SWM ERPs. The attempt of Applicant and DEP trying to limit the scope of this case also overlooks numerous changed circumstances since the issuance of the Original Permit. Changed circumstances militating in favor of the comprehensive analysis mandated for former-SWM ERPs include: increased trends in manatee mortality; increased boating pressure; persistent water quality violations in terms of dissolved oxygen, copper, and total coliform bacteria; a dramatic deterioration in dissolved oxygen levels; the initial presentation for environmental permitting of the previously unpermitted 227 additional dry slips and the 115,000 square feet of buildings; the current canal bottom profiles resulting from excessively deep maintenance dredging; the absence of an updated flushing study; and the failure to dredge the flushing canal required by the Original Permit. Disregarding the environmental and water quality requirements of Basis of Review Section 4 in this case would thus repudiate Specific Condition 5.B, especially when, among other things, the water quality of the canals has deteriorated dramatically with respect to dissolved oxygen, the canals continue to suffer from serious copper violations, the canals were recently maintenance dredged to excessive depths, no flushing study has examined these subsequent developments, and the intended uses to be facilitated by the New Permit more than double the capacity of the existing marina. 2. Water Quality The direct impacts of the proposed surface water management system, based on current levels of uplands and marine use at the marina, would adversely affect the quality of the receiving waters, in violation of Basis of Review Section 4.1.1(c). The excessively increased depths of the canals, especially with respect to the substantially widened depths of the north canal, raise the potential of water quality violations, especially given the history of this site. Potential sources of contaminants exist today in the canal bottoms, uplands, and marine activity associated with the marina. The potential for water quality violations, especially with respect to dissolved oxygen, increases in the absence of an updated flushing study. The potential also increases with the introduction of liveaboards and failure to dredge the flushing canal (or its replacement with culverts). In the face of these current threats to water quality, the New Permit fails to require a system with adequate capacity to accommodate fairly frequent storm events and fails to impose clear and enforceable inspection, maintenance, and disposal requirements for the underground vaults. Although better, the inspection and maintenance requirements for the stormwater inlets and boat wash area unnecessarily present enforcement problems. The effect of these failures in design capacity and inspection and maintenance is synergistic. Deficiencies in vault capacity mean that storms will more frequently resuspend the settled contaminants in the vaults and flush them out into the canal waters. Excessively long maintenance intervals and poor maintenance procedures will increase the volume of contaminants available to be flushed out into the canal waters. Improper disposition of removed contaminants endangers other water resources. The introduction of untreated or inadequately treated water into the canals means the introduction of two substances that will contribute to the current water quality violations. Organics, such as from the boat wash operations and other uplands uses, will raise biochemical oxygen demand, which will accelerate the deterioration in dissolved oxygen levels. Copper removed during boat wash operations, leaching from painted hulls, or remaining in the uplands from past marina operations will also enter the canals in this fashion. On these facts, Applicant has failed to provide reasonable assurance that the operation of the proposed surface water management system will not result, in the long-term, in water quality violations. Applicant has failed to demonstrate that the operation of the proposed system, even as limited to existing levels of use of the uplands and marine waters, will not contribute to existing violations of dissolved oxygen and copper levels. Obviously, the situation is exacerbated by consideration of the uses intended and reasonably expected to follow the construction of the proposed system. With the growing popularity of boating in Lee County over the past 20 years, it is reasonably likely that an expanded marina operation, located close to downtown Fort Myers, will successfully market itself. Thus, many more boats will use the marina because it will offer more wet and dry slips and new buildings, including a restaurant, and the pressure on water quality will intensify with the intensification of these uses. The added intensity of upland and marine uses will contribute to the above-described violations of water quality standards for dissolved oxygen and copper, probably will contribute to the above-described violations of water quality standards for total coliform bacteria and lead, and may contribute to the recurrence of water quality violations for other parameters for which the canals were previously in violation. On these facts, Applicant has failed to provide reasonable assurance that the direct and secondary impacts of the proposed system will not adversely affect the water quality of the canals. 3. Manatees and Manatee Habitat By letter dated June 26, 1998, from a DEP Environmental Specialist to a DEP permitting employee, the Environmental Specialist provided an initial opinion concerning the revisions that Applicant sought to the Original Permit so as to allow liveaboards, replace the flushing canal with culverts, and relocate the travel lift to the north canal. The letter accompanies a Manatee Impact Review Report, also dated June 26, 1998. The Manatee Impact Review Report notes the pending application for the New Permit. The report considers at length the extent of manatee use of Deep Lagoon and the nearby portions of the Caloosahatchee River. The Manatee Impact Review Report states: This project [i.e., the relocation of the boat lift to the north canal, addition of liveaboards, and conversion of the flushing canal to flushing culverts] is expected to add a significant number of boats to this system, significantly increase the level of boat traffic, and change boat traffic patterns in the study area. The vessels from this project are expected to produce significant adverse impacts to manatees that use the Deep Lagoon in the immediate vicinity of the project, as well as in the boater's sphere of influence of the project. Secondary adverse impacts include lethal and sublethal watercraft-related injuries, disturbance contributing to stress, and alteration of natural behaviors. The secondary impacts expected with this project are compounded by the cumulative secondary effects from other facilities in this system. Just south of this project site, another marina was recently constructed (Sun City Corporation aka Gulf Harbor Marina aka River's Edge), which has approximately 190 wet slips. Since October 1995, there have been seven watercraft-related deaths within five miles of this project location. The Gulf Harbor Marina was constructed in late 1995, and was almost fully occupied during 1996. Watercraft-related manatee deaths increased significantly during this time, with one in December 1995, two in 1996 and four in 1997. Additional on-water enforcement by the City of Cape Coral was considered part of the offsetting measures to address the expected impacts to manatees from increases in boat density. This offsetting measure, however, appears to be ineffectual at this time. The Manatee Impact Review Report concludes that the north canal and its mouth are "particularly important" for manatee because of the availability of freshwater from the adjoining Iona Drainage District ditch immediately north of the north canal and "historical use indicates that this area appears to be the most frequently used area in the Deep Lagoon system." The report cautions that the relocated travel lift may significantly increase the number of boats in the little-used north canal, whose narrowness, coupled with moored, large boats on the one side, "would produce significant, adverse impacts to the endangered manatee." The Manatee Impact Review Report finds that Applicant failed to provide reasonable assurance regarding the conservation of fish and wildlife, unless several new conditions were added. These conditions include prohibitions against boat launching along the shoreline of the north canal and the addition of manatee-exclusion grating to any culverts that may be approved. As defined in this recommended order, the direct impacts upon manatees from the proposed surface water management system would be moderate. As defined in this recommended order, direct impacts would not involve any increase in boating pressure. The greater impacts would be in the deterioration of two measures of water quality that are crucial to manatees: dissolved oxygen and copper. However, the secondary impacts are dramatic, not de minimis, and arise from the intended and reasonably expected uses to follow from the construction of the proposed surface water management system. The increased boat traffic intended and reasonably expected from more than doubling the marina capacity, through the addition of 100 wet slips and 227 dry slips, and the addition of 115,000 square feet of buildings, including a restaurant, would adversely impact the value of functions provided to manatees by the affected surface waters. Manatee mortality has increased as boat traffic has increased. Substantial numbers of boaters have ignored speed limits. Quality manatee habitat in this critical area along the Caloosahatchee River is not plentiful. On these facts, Applicant has failed to provide reasonable assurance that the secondary impacts of the proposed system will not adversely impact the abundance and diversity of wildlife and listed species, of which manatees are one, and the habitat of wildlife and listed species. 4. Minimization and Mitigation Due to their contention that Basis of Review Section 4 does not apply to this case, DEP and Applicant did not demonstrate compliance with the minimization and mitigation sections of Basis of Review Section 4. However, the record supports the possibility of design alternatives for water quality impacts, if not manatee impacts, that DEP and Applicant must consider before reanalyzing the direct, secondary, and cumulative impacts of the proposed system on the water resources and, if appropriate, potential mitigation options. Mr. Bateman testified that SFWMD is the only district that permits surface water management systems relying on the settling out of sediments in the bottom of a storage-type detention system. (Vol. II, p. 18). He explained that other districts rely on systems that, taking advantage of the three to four feet typically minimally available between ground surface and the top of the water table, retain the runoff and allow it to percolate into the ground. (Vol. II, p. 19). One relatively straightforward design alternative, which would address water quality issues, would be to perform a flushing study; analyze applicable drainage level of service standards imposed by state, regional, and local authorities; and increase the capacity of the surface water management system to accommodate the runoff from storms of sufficient size and frequency that would be accommodated by the proposed system. Another feature of this design alternative would be to impose for each component of the system a detailed, enforceable program of inspection, maintenance, and contaminant-disposal. This program would incorporate the manufacturer's recommendations for the manner and minimum frequency of inspection and maintenance, but would require more frequent removal of contaminated sediments during periods when larger storms are more numerous (e.g., a specified wet season) or more intense (e.g., a specified hurricane season), as well as any periods of the year when the marine and upland uses are greatest (e.g., during the winter season, if this is the period of greatest use). As testified by Mr. Bateman, the proximity of the water table to the surface, as well as South Florida land costs, discourage reliance upon a conventional percolation-treatment system, even though the site's uplands are 5 feet NGVD and the water table is 1.2 feet NGVD. The bottom of the proposed system is 2.5 feet NGVD, which leaves little soil for absorption. If the nature of the contaminants, such as copper, does not preclude reliance upon a percolation-treatment system, DEP and Applicant could explore design alternatives that incorporate more, shallower vaults, which would increase the soil layer between the bottom of the vaults and the top of the water table. If the technology or contaminants preclude reliance upon such an alternative, the parties could consider the relatively costly alternative, described by Mr. Bateman, of pool-like filters with an "actual filtration device." (Vol. II, pp. 19-20). The preceding design alternatives would address water quality concerns, including as they apply to manatees, but would not address the impact of increased boating upon manatees. The record is not well developed in this regard, but DEP and Intervenor have considerable experience in this area, and it is premature to find no suitable means of eliminating or at least adequately reducing the secondary impacts of the proposed system in this crucial regard as well. In any event, Applicant has failed to consider any design alternatives to eliminate or adequately reduce the direct and secondary impacts of the proposed surface water management system. Having failed to consider minimization, DEP and Applicant have failed to identify the residual direct and secondary impacts that might be offset by mitigation. Applicant has thus failed to mitigate the direct and secondary impacts of the proposed surface water management system.

Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order revoking its determination of an exemption for maintenance dredging in DOAH Case No. 98-3901 and denying the application for an environmental resource permit in DOAH Case No. 98-5409. DONE AND ENTERED this 24th day of November, 1999, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of November, 1999. COPIES FURNISHED: Kathy Carter, Agency Clerk Office of the General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Teri Donaldson, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 T. Elaine Holmes, Attorney 14502 North Dale Mabry, Suite 200 Tampa, Florida 33618 David Gluckman Gluckman and Gluckman 541 Old Magnolia Road Crawfordville, Florida 32327 Matthew D. Uhle Humphrey & Knott, P.A. 1625 Hendry Street Fort Myers, Florida 33901 Francine M. Ffolkes Senior Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000

USC (1) 33 U. S. C. 1341 Florida Laws (9) 120.57373.046373.069373.413373.414373.4142373.416403.813408.813 Florida Administrative Code (17) 40E-1.61140E-4.03140E-4.05140E-4.10140E-4.30140E-4.30240E-4.30340E-4.32140E-4.34140E-4.36140E-40.03140E-40.06140E-40.32140E-40.35162-312.05062-330.20062-4.242
# 6
AHMAD THALJI vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT AND H.B.J. INVESTMENTS, 99-001919 (1999)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Apr. 28, 1999 Number: 99-001919 Latest Update: Jun. 18, 2004

The Issue The issue is whether Respondent HBJ Investments, Inc. is entitled to an environmental resource permit to facilitate the construction of the Betty Jones Spa on property adjacent to property owned by Petitioner.

Findings Of Fact On November 17, 1998, Respondent HBJ Investments, Inc. (Applicant) filed an application (Application) with the South Florida Water Management District (District) for an environmental resource permit (ERP). The Application is for a Standard General (minor systems) ERP. The Application states that the proposed surface water management system is to serve a 11,564 square foot health spa with associated infrastructure improvements, such as parking, utilities, landscaping, and a stormwater detention facility. Section H of the Application responds to form questions that are intended to determine whether an application meets the requirements of a standard general ERP for a minor surface water system. Among the threshold requirements is that the proposed discharges from the site "will meet State water quality standards, and the surface water management system will meet the applicable technical criteria for stormwater management in the Basis of Review." Another threshold requirement is that the proposed activities will not cause significant adverse impacts individually or cumulatively. The Application states that the water quality treatment system will be on-line detention with effluent filtration. The Application and related documents describe the system in greater detail. The system consists of drains, inlets, a swale, an underground vault to provide effluent filtration through a sand filter and perforated pipe, an internal oil and grease skimmer, a control box, and a 15-inch diameter reinforced concrete pipe providing outfall from the vault. By Notice of Final Agency Action for Approval dated February 4, 1999, the District proposed the issuance of a "Standard General for Minor Surface Water Management Systems" ERP for the construction, operation, and maintenance of the proposed system (Permit). Permit Specific Condition 2 requires: "The discharges from this system shall meet state water quality standards as set forth in Chapter 62-302 and Rule 62-4.242, F.A.C., for class waters equivalent to the receiving waters." Permit Specific Condition 8 requires, for vault systems, that the system become dry within 72 hours after a rainfall event. Permit Specific Condition 9 requires the operation and maintenance entity to submit inspection reports for inspections to be performed every 18 months. Permit Specific Condition 10 requires a water quality monitoring program for systems, such as the proposed system, using an internal oil and grease skimmer. This condition obligates HBJ to take three samples during each of the first two annual rainy seasons following the commencement of operation of the system. The monitoring must take place immediately after rainfall events of sufficient magnitude to cause a discharge from the outfall structure. If the discharged water does not meet water quality standards for oil and grease, as established by Rule 62.302.510(3)(k), Florida Administrative Code, then the permittee must alter the system to attain compliance for this water quality parameter. The subject parcel is bounded by Fourth Avenue South on the north, First Street South on the east, Second Street South on the west, and an unnamed alley on the south. This site is just south of Al Lang Field. In its present state, the parcel is nearly entirely pervious surface. Some of the stormwater flowing onto the parcel percolates into the soils, and the remainder flows into City of Saint Petersburg stormwater sewers, from which it is carried about two city blocks to Tampa Bay, where it is discharged. The parcel was formerly used for single-family residential housing, but is now mostly cleared. The runoff from the site presently carries mostly sediments. After the proposed construction, 79 percent of the parcel would consist of impervious surface. Although small areas of the developed parcel might remain vegetated, and thus add nutrients into the runoff, the primary change in the runoff will consist of the addition of automobile-related contaminants, including, but not limited to, oil and grease. HBJ's engineer designed the proposed surface water management system to treat the first one-half inch of stormwater runoff. The engineer's report notes, in a letter dated November 13, 1998, that siltation in the vault reduces storage volume, so it is "required that cleaning be done every six (6) months." The report suggests the removal of grass clippings from the parking area, so that they are not transported to the retention vault. The report suggests that the underdrain system should be backflushed periodically, and the control structure should be checked monthly and all debris cleared. In general, the system would collect runoff from the roof downspouts and parking area. The system would provide treatment of the first 1/2 inch of runoff by capturing it in the vault, where it would filter through a layer of several cubic feet of sand before entering a perforated pipe leading to the City stormwater sewer. Runoff from rainfall in excess of the first 1/2 inch would receive little, if any, treatment. It is implicit that the first 1/2 inch of rainfall contains the first flush of contaminants from impervious surfaces. Nothing in the record specifies the efficacy of treatment provided by this standard, although it obviously is less than 100 percent efficient because of the higher standard imposed upon systems discharging into Outstanding Florida Waters (OFW). However, a pre- and post-development analysis of the runoff from the subject parcel would reveal an unknown additional volume of runoff from the developed site, due to the replacement of pervious surface with impervious surface. It is unclear whether the developed site would generate a reduced volume of sediments in this increased volume of runoff. Although little vegetated surface would exist post-development, the record does not reveal the extent to which the pre-development pervious area fails to capture the sediments prior to their entering the City stormwater system. More problematic are the automobile-related contaminants, such as oil and grease, that will be introduced into the runoff by the developed site. Presumably, the runoff from the undeveloped site contains few, if any, such contaminants. Thus, any automobile-related contaminants discharged from the surface water management system would likely be an increase from the amount of such contaminants presently discharged from the site. The runoff from the developed site would enter the City of Saint Petersburg stormwater sewer system and would be released in the nearby Tampa Bay. The record does not disclose the stormwater sewer line transporting the discharge, nor the outfall of the line into Tampa Bay. By stipulation, the parties agreed that Tampa Bay is an OFW and that discharge from the developed site would enter the City of Saint Petersburg stormwater sewer system. Tampa Bay is classified as Class II waters, which are approved for shellfish harvesting. The record does not disclose the point of discharge of the City stormwater line that would receive discharge from the developed site. However, the proximity of the site to Tampa Bay strongly suggests that the outfall would be in Tampa Bay, and it is only slightly less probable that the outfall would be at a point in the bay in the immediate vicinity of the site. The record suggests that the waters of Tampa Bay likely to receive the discharge from the site are impaired. For example, water quality conditions mandated the closing of "Lower Tampa Bay" to shellfish harvesting, for an unstated period of time, effective at sunset on July 5, 1999. Also, the Department of Environmental Protection listed two bayous in the immediate vicinity of the site as noncompliant with federal water quality standards due to excessive coliform bacteria counts and nutrients and insufficient levels of dissolved oxygen. The Basis of Review (BOR) is a document adopted by the District. It contains specific "criteria" for permitting. However, as BOR Section 1.3 explains, the goal of these criteria is to meet District water resource objectives, and the criteria are "flexible." Alternative methods of meeting "overall objectives" may be acceptable, depending upon the "magnitude of specific or cumulative impacts." The criteria, which are flexible, are the means by which the District assures that it meets its objectives, which are not flexible. BOR Section 3.1.0 recognizes that "a wide array of biological, physical and chemical factors affect the functioning of any wetland or other surface water community. Maintenance of water quality standards in applicable wetlands and other surface waters is critical to their ability to provide many of these functions." BOR Section 3.1.0 elaborates: "It is the intent of the Governing Board [of the District] that the criteria in subsections 3.2 through 3.2.8 be implemented in a manner which achieves a programmatic goal and a project permitting goal of no net loss of wetlands or other surface water functions." BOR Section 3.1.1 requires that an applicant provide "reasonable assurance" of several things. BOR Section 3.1.1(a) requires that "a regulated activity will not adversely impact the value of functions provided to fish, wildlife and listed species, including aquatic and wetland dependent species, by wetlands and other surface waters and other water related resources of the District. (paragraph 40D-4.301(1)(d), F.A.C.) (see subsection 3.2.2)." BOR Section 3.1.1(c) provides that: a regulated activity will not adversely affect the quality of receiving waters such that the water quality standards set forth in Chapters 62-3, 62-4, 62-302, 62-520, 62-522 and 62-550, F.A.C., including any antidegradation provisions of Sections 62-4.242(1)(a) and (b), 62-4.242(2) and (3), and 62-302.300 and any special standards for Outstanding Florida Waters . . . set forth in sections 62-4.242(2) and (3), F.A.C., will be violated (paragraph 40D-4.301(1)(e), F.A.C.). BOR Section 3.1.1(d) provides that "a regulated activity . . . located in close proximity to Class II waters . . . will comply with the additional criteria in subsection 3.2.5 (paragraph 40D-4.302(1)(c), F.A.C.)." BOR Section 3.1.l(f) provides that "a regulated activity will not cause adverse secondary impacts to the water resources (paragraph 40D-4.301(1)(f), F.A.C.) (see subsection 3.2.7)." BOR Section 3.1.1(g) provides that "a regulated activity will not cause adverse cumulative impacts upon wetlands and other surface waters . . . (paragraph 40D-4.302(1)(b), F.A.C.) (see subsection 3.2.8)." BOR Section 3.2.4 provides that an applicant must provide "reasonable assurance that the regulated activity will not violate water quality standards in areas where water quality standards apply. . . . The following requirements are in addition to the water quality requirements found in Chapter 5." BOR Section 3.2.4.2(c) provides that the applicant must address the long-term water quality impacts of a proposed system, including "prevention of any discharge or release of pollutants from the system that will cause water quality standards to be violated." BOR Section 3.2.5 provides: The special value and importance of shellfish harvesting waters to Florida's economy as existing or potential sites of commercial and recreational shellfish harvesting and as a nursery area for fish and shell fish is recognized by the District. In accordance with section 3.1.1.(d), the District shall: (b) deny a permit for a regulated activity in any class of waters where the location of the system is adjacent or in close proximity to Class II waters, unless the applicant submits a plan or proposes a procedure which demonstrates that the regulated activity will not have a negative effect on the Class II waters and will not result in violations of water quality standards in the Class II waters. BOR Section 3.2.7 provides that an applicant must provide "reasonable assurance" that "a regulated activity will not cause adverse secondary impacts to the water resource" as described in this section. However, this section explicitly disregards negligible or remotely related secondary impacts. BOR Section 3.2.8 provides that an applicant must provide "reasonable assurance" that "a regulated activity will not cause unacceptable cumulative impacts upon wetlands and other surface waters " BOR Section 4.2 limits off-site discharge "to amounts which will not cause adverse off-site impacts." For a proposed activity within an open drainage basin, as is the subject proposed activity, the allowable discharge is (presumably the greatest of) any amount determined in previous District permits, the legally allowable discharge at the time of the permit application, or historic discharge. Historic discharge is the peak rate at which runoff leaves a parcel of land by gravity under existing site conditions. BOR Section 5.1 requires that proposed discharges meet applicable state water quality standards. This chapter of the BOR requires that proposed systems satisfy certain quantitative criteria, depending on the type of water treatment system. However, BOR Section 5.1 warns: in certain instances a design meeting those standards may not result in compliance with the state water quality standards referenced above. Unless an applicant has provided reasonable assurance that a design will not cause or contribute to a violation of state water quality standards, the District may apply more stringent design and performance standards than are otherwise required by this chapter. Projects designed to the criteria found in this section shall be presumed to provide reasonable assurance of compliance with the state water quality standards referenced above. . . . BOR Section 5.2 sets quantitative criteria for various types of surface water management systems. The subject system is a detention, on-line treatment system. BOR Section 1.7.5 defines "detention" as the "delay of storm runoff prior to discharge into receiving waters." BOR Section 1.7.28 defines "on-line treatment system" as a "dual purpose system that collects project runoff for both water quality and water quantity requirements. Water quality volumes are recovered through percolation and evaporation while water quantity volumes are recovered through a combination of percolation, evaporation, and surface discharge." BOR Section 5.2.b applies to "[d]etention with effluent filtration system (manmade underdrains)." BOR Section 5.2.b.1 provides that proposed activities draining less than 100 acres "shall treat the runoff from . . . the first one-half inch runoff." BOR Section 5.2.b.6 adds: "Maintenance of filter includes proper disposal of spent filter material." BOR Section 5.2.c applies to "on-line treatment system[s]." This section also requires the treatment of the first one-half inch of runoff. However, BOR Section 5.2.e provides: Projects discharging directly into Outstanding Florida Waters (OFW) shall be required to provide treatment for a volume 50 percent more than required for the selected treatment system . . .. Applicant has provided reasonable assurance that the proposed surface water management system would not cause adverse water quantity impacts to receiving waters and adjacent lands and would not cause flooding. In terms of water quantity, the proposed system is designed to meet the requirements of the ten-year storm. The subject site is a short distance from Tampa Bay, and, as already noted, it is very likely that the runoff discharges into Tampa Bay at a location not far from the subject site. Thus, water quantity and flooding are irrelevant to this case. However, Applicant has not provided reasonable assurance that the proposed surface water management system would not cause adverse impacts to the value of functions provided to fish and wildlife by nonwetland surface waters and would not adversely affect the quality of receiving waters. The receiving waters of the discharge from the subject site are Class II waters that are OFW. However, these waters are also impaired sufficiently as to be in violation of certain federal water quality standards and to require the closure, at least at times, of shellfish harvesting. There are three deficiencies in the proposed permit. First, it does not specify, in clear and enforceable language, an inspection and maintenance program, which includes the undertaking by the Applicant to backwash the system at specified intervals, to replace the sand filtration medium at specified intervals, to dispose of the sand filtration medium so that the captured contaminants do not reenter waters of the state, to monitor the water discharged from the oil and grease skimmer at specified intervals following the first two years' monitoring, and generally to take any necessary action to correct deficiencies uncovered from inspections. Second, the treatment of the first 1/2 inch of runoff is insufficient for the system, which is discharging directly into an OFW. BOR Section 5.2.e raises this standard to 3/4 inch. Direct discharges requires the identification of the first receiving waters. Receiving waters are waters of the state that are classifiable as Class I-V waters. Receiving waters thus do not include waters in a stormwater sewer pipe, which are not waters of the state nor are they classifiable. Water quality determinations often require comparison of the quality of the discharged water with quality of the receiving waters. The off-site piping of the discharged water does not preclude such comparison. In such case, the analysis extends to the first receiving waters into which the pipe empties. The District's argument to the contrary invites circumvention of those provisions enacted and promulgated for the protection of OFWs. For example, several owners of land abutting an OFW could establish a jointly owned stormwater sewer line so that the point of comparison for their discharge would be the waters in the pipe rather than the OFW. Third, Applicant failed to submit a plan or propose a procedure demonstrating that the proposed activity would not have a negative effect on the Class II waters of Tampa Bay and would not result in violations of water quality standards in these Class II waters. The District failed to determine the outfall of the discharge from the subject site, so it failed to enforce the requirement of the plan required by BOR 3.2.5 for the protection of the special value of Class II waters. Although required to account for cumulative impacts, the plan will necessarily reflect the characteristics of the site--e.g., 1.6 acres contributing largely automobile-based contaminants and not nutrients--and the characteristics of the receiving waters--e.g., Tampa Bay is vast and relatively impaired, though, in the vicinity of the subject site, more likely due to excessive nutrients.

Recommendation It is RECOMMENDED that the Southwest Florida Water Management District enter a final order denying the ERP application of HBJ Investments, Inc. DONE AND ENTERED this 23rd day of December, 1999, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of December, 1999. COPIES FURNISHED: E. D. "Sonny" Vergara, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 John R. Thomas Wyckoff & Thomas, P.A. 233 Third Street North, Suite 102 Saint Petersburg, Florida 33701 Michael Jacobs Director, Legal Affairs 25 Second Street North, Suite 160 Saint Petersburg, Florida 33701 Anthony J. Mutchler Assistant General Counsel Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

USC (1) 33 U. S. C. 1313 Florida Laws (4) 120.57373.042373.086373.414 Florida Administrative Code (9) 40D -40.30140D-4.09140D-4.30140D-4.30240D-40.30140D-40.30262 -4.24262-302.30062-4.242
# 7
DEPARTMENT OF COMMUNITY AFFAIRS vs MONROE COUNTY (OCEAN REEF CLUB AND KEY LARGO FOUNDATION), 89-005853GM (1989)
Division of Administrative Hearings, Florida Filed:Homestead, Florida Oct. 31, 1989 Number: 89-005853GM Latest Update: Oct. 19, 1990

The Issue At issue in this proceeding is whether certain development orders issued by Monroe County to Homeowners, Ocean Reef Club and Key Largo Foundation (Applicants) for a project that would ultimately result in the construction of a flushing canal in the Ocean Reef Club development on north Key Largo are consistent with the Monroe County comprehensive plan and land development regulations.

Findings Of Fact The parties Petitioner, Department of Community Affairs (Department), is the state land planning agency charged with the responsibility of administering and enforcing the provisions of Chapter 380, Florida Statutes, and all rules promulgated thereunder. Section 380.031(18) and 380.032(1), Florida Statues. Respondent, Monroe County, is a local government within the Florida Keys area of Critical State Concern designated by Section 380.0552, Florida Statutes, and is responsible for the implementation of, and the issuance of development orders that are consistent with, the Monroe County comprehensive plan and land development regulations, as approved and adopted in Chapters 9J-14 and 28-20, Florida Administrative Code. Respondents, Homeowners, Ocean Reef Club and Key Largo Foundation (Applicants), are the owners of real property in the Ocean Reef and Harbour Course subdivisions, Key Largo, Monroe County, Florida; properties that are located within that part of Monroe County designated as an area of Critical State Concern. The Applicants have sought the development orders (permits) at issue in this proceeding incident to their 8-year quest to achieve regulatory approval to initiate a project that would restore the water quality of Dispatch Creek to Class III water standards. Background The site of the proposed project, the present terminus of Dispatch Creek, is located within the Ocean Reef Club development on north Key Largo. That development is bordered on the east by the Atlantic Ocean and John Pennekamp Coral Reef State Park, on the north by Biscayne National Park, and on the west by the Biscayne Bay/Card Sound Aquatic Preserve. Currently, the development at the Ocean Reef Club includes a number of canals and boat basins, an airstrip; three 18-hole golf courses, a 174-slip marina capable of docking vessels in excess of 100 feet, and extensive residential and-commercial uses. In the mid-1970's, Dispatch Creek was a natural, albeit shallow, waterbody that was able to maintain, through natural tidal actions, water quality standards. However, in 1977 Ocean Reef Club, under permits issued by the Department of Environmental Regulation (DER) in the mid-1970's excavated the creek to new depths to create a navigable channel and extended its length beyond its natural contours. When completed, the creek was converted from a natural waterbody, that could maintain water quality standards through natural tidal action, into a dead-end system, that could not maintain such standards through natural processes along the course of its extended terminus. 1/ Over time, the water quality of Dispatch Creek from its approximate midpoint to its dead-end terminus has steadily declined. The cause of this decline is reasonably attributable to the biochemical oxygen demand placed on the creek by the continuous input of detritus from mangroves, which boarder the creek on the east and to a lesser extent on the west, and the length of the channel, coupled with the dead-end basin surrounding an island, which has assured the continued decline of water quality due to poor water circulation. As a consequence, the creek, as a habitat, has been altered from an oxygen rich system supportive of aerobic life to an oxygen poor system supportive of anaerobic life. This has evidenced itself through algae blooms, the intermittent emission of hydrogen sulfide gas, and a change in water clarity to that of a "coffee au lait" color. Currently, a significant portion of Dispatch Creek is devoid of aerobic life, and unless its condition is reversed it could not support aerobic marine organisms in the future. /2 Today, conditions in portions of Dispatch Creek fail to meet DER standards. DER regulations establish the dissolved oxygen (DO) standard to be not less than five milligrams per liter in a 24-hour period, and never less that four milligrams per liter. The DO Standard is currently violated in Dispatch Creek beginning at the mid point of the creek to its terminus. At its terminus, DO levels are chronically below one milligram per liter. Additionally, DER nutrient standards prohibit the alteration of nutrient concentrations of a body of water so as to cause an imbalance in natural populations of aquatic flora or fauna. Here, the high nutrient levels of Dispatch Creek resulting from the mangrove detritus and lack of circulation has, as heretofore noted, caused the natural aquatic flora and fauna to be replaced by anaerobic life. As a consequence of the changes in water quality that had occurred in Dispatch Creeks the Applicants have, over the course of the past eight years, sought approval from various regulatory authorities, including DER and Monroe County, of a plan to improve the water quality in Dispatch Creek. Such approval has been garnered from DER, and Monroe County's approval is at issue in this proceeding. The DER permit On February 7, 1986, the Applicants received approval from DER for a permit to construct a flushing canal from the terminus of Dispatch Creek to the Atlantic Ocean. That permit authorized the Applicants: To construct a "flushing canal" between the dead end of Dispatch Creek Waterway and the Atlantic Ocean by: excavating approximately 13,000 cubic yards to create a canal approximately 3000 ft. long by 20 ft. wide with a bottom elevation of 6 ft. Mean Low Water; placing three 6 ft. by 6 ft. by 380 ft. box culverts in the canal alignment at the basin end; placing tidal actuated flap gates on the basin end of the culverts in a manner which will allow the basin to intake water from the flushing canal on incoming tides while preventing discharge into the flushing canal on outgoing tides; placing 5 pilings across the canal at it's juncture with the Atlantic Ocean to prevent navigation in the canal; and creating a 12,900 sq. ft. mangrove mitigation area by excavating approximately 1,450 cu. yds. from a spoil area to create an area with an elevation of +1.4 Ft. NGVD which will be planted with red mangroves. DER was, in evaluating the application pending before it, charged with the duty to apply, enter alia, the criteria of the 1984 Warren Henderson Wetlands Act, Section 403.918(2), Florida Statutes, as well as Chapters 17-3 and 17-4, Florida Administrative Code. Based on DER's decision to issue its permit, it is reasonable to conclude that DER, within its permitting jurisdiction, concluded that construction of the proposed circulation channel would not lower ambient water quality, and would not significantly degrade Outstanding Florida Waters (OFW), including those of John Pennekamp Coral Reef State Park. As heretofore noted, the Department does not contend that the subject project will violate any specific criteria within DER's Chapter 403, Florida Statutes, permitting jurisdiction. The Monroe County permits On July 19, 1989, Monroe County issued to the Applicants the building permit, excavation permit, and land clearing permit (development orders), each numbered 8930001680, at issue in these proceedings. As permitted, the project proposed by the Applicants is designed to improve the water quality of Dispatch Creek, particularly in the vicinity of its dead-end terminus, and consists of two phases. Phase I contemplates the installation and operation of an aeration system for at least one year, which will extend from the dead-end terminus of Dispatch Creek toward its midpoint, as well as a water quality monitoring program, until such time as the water quality of the entire creek comports with that of adjacent Class III waters. Should the Applicants be successful in Phase I, they would then be authorized to proceed with Phase II, which would allow the construction of the flushing canal contemplated by the DER permit. As approved by Monroe County, Phase I would consist of the installation of an aeration system around the island, located at the terminus of Dispatch Creek, and in the canal, as well as the suction dredging of loose sediments in the upper reaches of Dispatch Creek. The system would consist of fifteen microporus diffuser/aerators producing approximately 5 CFM per unit, and would be anchored near the bottom to maximize the introduction of dissolved oxygen into the anaerobic water and to optimize water movement. Operation of such system, coupled with the introduction of aerobic bacteria, will shortly reduce the concentration of hydrogen sulfide dissolved in the water, reduce the concentration of ionized sulfides in solution, retard the growth and propagation of anaerobics in the benthic layer, and activate the growth and propagation of aerobics in all strata. As a consequence, over time, water clarity will improve, which will allow the penetration of sunlight into the benthos. This illumination will spawn the growth of photosynthetic bacteria, as well as phytoplankton, which will aid in the continued aerobic cleansing of the water and bottom sediments. In all, installation and operation of the aeration system, which has proven successful at other locations, should, over time, restore the waters of Dispatch Creek to Class III standards, without any adverse impacts to adjacent waters or the park. While operation of the aeration system will, over time, restore the waters of Dispatch Creek to Class III standards, the perpetual maintenance of such system would be energy intensive and expensive. for this reason, the Applicants have proposed the Phase II canal, which would maintain, through natural tidal processes, water quality standards within the creek. The canal permitted by Monroe County under Phase II is consistent in all respects with the DER permit except the Monroe County permits require that the canal be sited 20 feet landward of the alignment permitted-by DER into previously scarified uplands. So aligned, the canal would begin at the landward terminus of Dispatch Creeks run easterly within the rear lot lines of at least 15 lots within Harbour Course South subdivision, a platted subdivision, pass through a fringe of red and black mangroves fronting the ocean, and terminate approximately 100 feet seaward of the mean high water line (MHWL) within the boundaries of John Pennekamp State Park. At the point where the canal would join with Dispatch Creek, three 6 foot by 6 foot by 380 foot box culverts would!! be installed with one-way tidal activated flap gates, which would permit waters from the Atlantic to enter Dispatch Creek on a rising tide, but would preclude an exchange of waters from Dispatch Creek on a falling tide. Through such design, sufficient mix and force will be exerted within the waters of Dispatch Creek to maintain Class III water quality standards by natural circulation, and to return the habitat offered by the creek to an oxygen rich system capable of supporting aerobic life. While construction of the canal would be beneficial, by restoring the waters: of Dispatch Creek to Class III standards, it is not without cost to the environment. As aligned, the canal, although predominately within previously cleared or scarified uplands, will require excavation through several types of habitat that are either undisturbed or reestablished, including undisturbed buttonwood association, salt marsh, hardwood hammock, transitional habitat, mangroves and submerged lands, and will require the removal of approximately one-tenth of an acre of red and black mangroves, a species of special concern, as well as a number of mahogany trees, twisted air plants, prickly pear cactus and barpar cactus, which are threatened species. Its construction would likewise sever the uplands from the adjacent transitional and wetland areas that traditionally buffer, insulate and protect nearshore waters from runoff from upland areas. Construction of the canal should not, however, adversely impact any threatened or endangered animal species since the proposed alignment is currently a poor habitat for threatened or endangered species, such as the Key Largo woodrat, that may reside in the area, and there is currently no threatened or endangered animal species inhabiting the site. This is not, however, to suggest that the site would not support such species in the future, provided that existing habitat is permitted to continue its progress towards reestablishment. To mitigate the loss of habitat types, the Monroe County permit provides: The agreed mitigation for the loss of all rare and/or endangered habitat types located within the area impacted by the dredging shall be carried out prior to initiation of the dredge project. This shall be based on existing vegetation surveys and an assessment of species currently located within the confines of the project area. Prior to initiation of any dredge activity, a formal inventory of the project site shall be made and a one-to-one replacement program (baked on species rarity or level of endangerment) shall be established and agreed upon. Such an agreement will include defining an appropriate site and the number and type of trees, as well as a maintenance plan for the agreed upon area. Additionally, the DER permit addresses the loss of mangroves, by requiring the establishment of a 12,900 square foot mangrove mitigation area. Under the facts of this case, the mitigation proposed would, assuming the propriety of such development under the Monroe County comprehensive plan and land development regulations, address the loss of habitat types occasioned by development of the proposed canal. To assure that water quality within Dispatch Creek comports with Class III standards before the canal is dug, and that the creek maintains such standards following construction, the Monroe County permits establish a water quality monitoring program. During the first year, samples will be taken and tests performed on a weekly basis for pH, DO, turbidity, Secchi Disc, temperature, and sulfite; on a biweekly basis for total bacterial count and composition; on a monthly basis for total nitrogen and phosphate; on a quarterly basis for: macro-invertebrates and macrophytes; and on a semiannual basis for heavy metals and pesticides. During the second yearn biweekly testing will be done for DO, temperature, hydrogen sulfide, turbidity and Secchi Disc; quarterly testing for total nitrogen and phosphate, macro- invertebrates, and macrophytes; and, annual testing for heavy metals and pesticides. After the second year, monthly tests will be done for DO, temperature, hydrogen sulfide, turbidity, and Secci Disc; quarterly tests for total nitrogen and phosphate, as well as macro- invertebrates; and annual tests for heavy metals and pesticides. Should the water quality of the creek fail to maintain Class III standards following construction of the canal, the Monroe County permit contains the following special condition: The water quality monitoring program shall be maintained to assess the quality of water in Dispatch Creek subsequent to the dredge project completion. If at any time the water quality fails to meet the standards established by this permit, the one way flushing valve shall be closed by the applicant, and in applicant's failure to do so, by the County. The applicant assumes all costs of closing said valve, whether closed by applicant or the County. Aeration, aid/or other means at the discretion of the applicant, shall be utilized to reestablish quality. The valve shall not be reopened until the water quality standard is met. The purpose of the foregoing condition, as well as the requirement that the waters of Dispatch Creek meet Class III standards before the canal can be dug, is to assure that operation of the canal will not lower ambient water quality within the Outstanding Florida Waters of John Pennekamp Coral Reef State Park, and thereby protect the park from any adverse impacts associated with the improved circulation of the creek. John Pennekamp Coral Reef State Park is a unique and world-renowned resource, attracting millions of visitors each year. At least fifty percent of the activities engaged in by visitors to the park are water-related, including fishing, observational diving and boating. Any degradation of the ambient quality of those waters would be contrary to DER's rules promulgated under Chapter 403, Florida Statutes, and could adversely impact the natural biota of the park, with a corresponding reduction in the number of visitors to the park and revenues contributed by those visitors to the local economy. Here, the proof demonstrates, consistent with DER's prior permitting, that the subject project, built as proposed, would not lower the ambient water quality of adjacent waters through the discharge of pollutants, and therefore would not adversely affect the park. If anything, the Monroe County permits, with one exception to be discussed infra, offer stronger assurances than the DER permit that adverse impacts will not occur. Notably, under such permits the Applicants must first bring the water quality of the Creek up to Class III standards before the canal can be dug. If the Applicants are ssuccessful at that phase of the project, there will not be excessive nutrient loading within the creek, and the detritus that may thereafter be removed from the creek by improved circulation would not adversely affect water quality or the park. Currently, there are no heavy metals in the sediments or water column of the creek which are at levels above those found naturally, and no pesticides or toxic organics. In sum, there is no basis to conclude, based on the record, that-there is any substance within the waters or sediments of Dispatch Creek that would, upon the waters achieving Class III standards, lower the amient quality of adjacent waters or adversely impact the park. /4 Ostensibly, as an added measure of protection to adjacent waters, the Monroe County permits contain a condition, with which the Applicants concur, that should the waters of Dispatch Creek fail to maintain Class III standards following construction of the canal, the one-way tidal actuated flap gates will be closed. That condition, a noted supra, provides: If at any time the water quality [of the creek] fails to meet the standards established by this permit, the one way flushing valve shall be closed by the applicant, and in the applicant's failure to do so, by the County. The applicant assumes all costs of closing by applicant or the County. Aeration, and/or other means at the discretion of the applicant, shall be utilized to reestablish quality. The valve shall not be reopened until the water quality standards is met. The foregoing condition presumes to address the possibility that should the proposed project fail to function as expected by the experts, as did the current Dispatch Creek fail to function as expected, that such failure will no result in an adverse impact to adjacent waters or the park. In this regard, it is worthy of note that DER's approval of the extension of Dispatch Creek to create a 7,200 foot dead-end canal in the mid-flush the pollutants from the canal into the park. The Applicants presented persuasive testimony, however, through their 1970's was, based on current knowledge, an error, and that today no dead-end system would be approved in excess of soon feet. Monroe County's condition, while preventing the discharge of degraded waters from Dispatch Creek to the park upon closure of the one way flushing valves, fails to address, however, the adverse impacts that could result from its closure. By closure of the valves, the flushing canal would be instantly converted into a 3,000-foot dead-end canal, and would suffer the same water quality problems as similar systems, with probable adverse effects to adjacent waters and the park. Accordingly, so as not to compound the existing error occasion by the extension of Dispatch Creek in the mid-1970's, prudence would dictate a proviso that, if the valves are shut, appropriate monitoring will occur within the waters of the flushing canal to detect any significant degradation of water quality, and that should such degradation pose a threat to adjacent waters or the park, that the Applicants be required, at their expense, to restore promptly the water quality within the flushing canal to Class III standards or restore the area to its present condition. Consistency of the proposed project with the Monroe County comprehensive plan and land development regulations Lack of plat approval As heretofore noted, the proposed canal would begin at the landward terminus of Dispatch Creek and run easterly within the rear lot lines of at least 15 lots in Harbour Course South subdivision, a platted subdivision, before it passed through fringing mangroves and terminated in the Atlantic Ocean. Currently, the final recorded plats of Harbour Course South subdivision do not reflect the proposed canal, as mandated by Section 177.091(15), Florida Statutes, and the Applicants have not sought to amend the plat to include the proposed canal. Pertinent to this case, the Monroe County Code (MCC), the land development regulations, /5 provides: Sec. 9.5-1. Purpose. It is the purpose of this chapter, the Land Development Regulations, to establish the standards, regulations, and procedures for review and approval of all proposed development of property in unincorporated Monroe County, and to provide a development review process what will be comprehensive, consistent and efficient in the implementation of the goals, policies and standards of the comprehensive plan . . . Sec. 9.5-2. Applicability. General Applicability: The provisions of this chapter shall apply to all land in unincorporated Monroe County. All development of whatever type and character, whether permitted as of right or as a conditional use, shall comply with the development standards and the environmental design criteria set forth in article VII hereof. No development shall be undertaken without prior approval and issuance of a development permit under the provisions of this chapter and other applicable laws and regulations. Sec. 9.5-81. Plat approval and recording required. * * * No building permit, 6/ except for single family detached dwellings and accessory uses thereto, shall be issued for the construction of any building, structure or improvement unless a final plat has been approved in accordance with the provisions of this division and recorded for the lot on which the construction is proposed. * * * (e) If a plat has been previously approved and recorded, technical or minor changes to the plat may be approved by the director of planning. All other changes shall be considered in accordance with the provisions of this Division. Sec. 9.5-94. Amendment of a recorded final plat. An amendment of a recorded final plat or portion thereof shall be accomplished in the same manner as for approval of the plat. Here, the subject permits were issued contrary to the foregoing provisions of the MCC because there was no final plat of record approving the canal as to each affected lot. While the Applicants offered proof, if credited, that the existing plat could be amended to include the canal as a "minor change" upon approval of the Director of Planning, it is noteworthy that no such approval has been obtained. More importantly, it is found that a change in the existing plat to include the canal would not constitute a "technical or minor change," and that formal amendment of the plat would be required. 7/ The provision of the MCC dealing with plat approval, provide a comprehensive scheme to assure, among other things, than the proposed plat is consistent with the purposes, goals and objectives of the comprehensive plan, the development regulations, and state laws, as well as affording an opportunity for public input. Of import here, the MCCs provide: Sec. 9.5-82. General Standards for Plat Approval. No preliminary or final plat shall be approved unless the plat is consistant with the purposes, goals and objectives of this plan, this chapter, applicable provisions of state law, the provisions governing the development of land set forth in article VII, and the procedures set forth in this article. Sec. 9.5-83. Preliminary Plat Approval. Generally. All applicants for approval of a plat involving five (5) or more lots shall submit a preliminary plat for approval in accordance with the provisions of this section. Application. An application for preliminary approval shall be submitted to the development review coordinator in accordance with the provisions of this section, accompanied by a nonrefundable fee as established from time to time by the board of county commissioners. The application shall contain the information required on a form provided by the director of planning. Staff Review. After a determination that the application for preliminary plat approval is complete under the provisions of section 9.5-44, the development review coordinator shall submit the application to the development review committee, which shall prepare a recommendation and report for the commission. Public Hearing and Action by the Planning Commission. The planning commission shall conduct a public hearing on an application for preliminary plat approval of a subdivision involving five (5) or more lots, in accordance with the requirements of sections 9.5-46 and 9.5-47. The commission shall review such applications, the recommendation of the development review committee, and the testimony at the public hearing, and shall recommend granting preliminary plat approval, granting approval subject to specified conditions, or denying the application at its next meeting following submittal of the report and recommendation of the development review committee. Effect of Approval of Preliminary Plat. Approval of a preliminary plat shall not constitute approval of a final plat or permission to proceed with development. Such approval shall constitute only authorization to proceed with the preparation of such documents as are required by the director of planning for a final plat. Sec. 9.5-84. Final Plat Approval. Generally. All applicants for approval of a plat shall submit a final plat for approval in accordance With the provisions of this section. Application. It shall be the responsibility of the developer to complete, have in final form, and submit to the development review coordinator for final processing the final plat, along with all final construction plans, required documents, exhibits, legal instruments to guarantee performance, certificates properly executed by all required agencies and parties as required in this article, and the recording fee, and any other documents or information as are required by the director of planning. After receipt of a complete application for final plat approval, as determined in accordance with section 9.5-44, development review coordinator shall submit the application and accompanying documents to the development review committee. Review and action by Development Review Committee. The development review committee shall review all applications for final plat approval. b. For a final plat for subdivision involving five (5) or more lots, if the plat conforms to the approved preliminary plate and the substantive and procedural requirements of this chapter, at its next regular meeting or as soon as practical after receipt of a complete application, the development reviews committee shall recommend to the planning commission approval of the final plat or approval with conditions. If the committee finds that the plant does not substantially conform to the approved preliminary plat or the substantive and procedural requirements of these regulations, the committee shall recommend denial, specifying the area(s) of nonconformity. Review and Action by the Planning Commission. The planning commission shall review all applications far final plat approval involving five (5) or more lots and the recommendation of the development review committee. If the commission finds that the final plat conforms to the approved preliminary plat and the substantive and procedural requirements of this chapter, the commission shall recommend to the board of county commissioners approval of the final plat, or approval with specified conditions, and shall submit a report and written findings in accordance with section 9.5-47. Public Hearing by the Board of Country Commissioners. The board off county commissioners shall conduct a public hearing on all applications for final plat approval involving five (5) or more lots in accordance with the procedures of section 9.5-46C. Action by the Board of County Commissioners. For proposed subdivisions involving five (5) or more lots the board of county commissioners shall review the application, the recommendations of the development review committee and the planning commission, and the testimony at the public hearing, and shall grant final plat approval, grant approval subject to specified conditions, or deny the application, in accordance with the provisions of section 9.5-47. Sec. 9.5-90.Maintenance of Private Improvements. If any plat of subdivision contains streets, easements, or other improvements to be retained for private use, the final plat for recordation shall indicate to the satisfaction of the director of planning and the county attorney the method or entity by which maintenance of the private improvements shall be performed. As a consequence of Monroe County's failure to comply with the provisions of its regulations which require final plat approval before a building permit may be issued, there has been no review by the Development Review Committee, no public hearing conducted by the Planning Commission, no recommendation of the Planning Commission, and no public hearing before the County Commissioners on the propriety of amending the subject plat to permit the proposed construction, or a resolution, through the plat approval process, as to whether the proposed canal is consistent with, inter alia, the purposes, goals, and objectives of the Monroe County comprehensive plan, as mandated by section 9.5-82(a), MCC. As importantly, where, as here, the proposed canal is to be retained for private use, there is no indication on the recorded plat, 4s required by MCC 9.5-90, of the method or entity by which maintenance of the canal shall be performed. Notably, the property through which the canal will be constructed is not owned by any of the Applicants but, rather, by Driscoll Properties , with whom the Applicants state they have an agreement to permit construction. 8/ Open space requirements and environmental design criteria Pertinent to this case, the MCC further provides: Sec. 9.5-3. Rules of construction. In the construction of the language of this chapter, the rules set out in this section shall be observed unless such construction would be inconsistent with the manifest intent of the board of commissioners as expressed in the Monroe County Comprehensive Plan or an element or portion thereof, adopted pursuant to chapters 163 and 380, Florida Statutes (1985). The rules of construction and definitions set out herein shall not be applied to any section of these regulations which shall contain any express provisions excluding such construction, or where the subject matter or context of such section is repugnant thereto. (a) Generally: All provisions, term , phrases and expressions contained in this chapter shall be liberally construed in order that the true intent and meaning of the board of county commissioners may be fully carried out. Terms used in this chapter, unless otherwise specially provided, shall have the meanings prescribed by the statutes of this state for the same terms. In the interpretation and application of any provision of this chapter, it shall be held to be the minimum requirement adopted for the promotion of the public health, safety, comfort, convenience and general welfare. Where any provision of this chapter imposes greater restrictions upon the subject matter than a general provision imposed by the Monroe County Code or another provision of this chapter, the provision imposing the greater restriction or regulation shall be deemed to be controlling . . (Emphasis added) Sec. 9-804 (MCLDR) Open space requirements. No land shall be developed, used or occupied such that the amount of open space on the parcel proposed for development is less than the following ratios, nor shall open space be cleared or otherwise disturbed including ground cover, understory, mid-story, and canopy vegetation. All such required areas shall be maintained in their natural condition. The amount of open space required on any parcel for development shall be determined according to each land type and no development activity within any individual land type shall exceed the open space ratio for that land type. Land Type on Existing Open Space Conditions Map Ratio Open Waters 1.00 Mangrove and Freshwater 1.00 Wetlands Salt Marsh and Buttonwood .80 Associations .85 High Hammock (High Quality) .80 High Hammock (Moderate Quality) .60 High Hammock (Low Quality) . 4 Low Hammock (High Quality) .80 Low Hammock (Moderate Quality) .60 Low Hammock (Low Quality) . 4 Palm Hammock .90 Cactus Hammock .90 Pinelands (High Quality) .80 Pinelands (Low Quality) .60 Beach Berm .90 Disturbed . 2 Disturbed with Hammock . 2 Disturbed with Salt Marsh and Buttonwood . 2 Disturbed Beach/Berm . 2 Disturbed with Exotics . 2 Disturbed with Slash Pines . 2 Offshore Islands . 9 (Emphasis added) Sec. 9.5-345. Environmental design criteria. No land, as designated on the existing conditions map and analyzed in accordance with the standards in sections 9.5-339 and 9.5-340, shall be developed, used ~re occupied except in accordance with the following criteria unless the county biologist recommends an authorized deviation from the following criteria in order to better serve the purpose and objectives of the plan and the director of planning or planning commission approves the recommendation as a minor or major conditional use. No recommendation for an authorized deviation from these environmental design criteria shall be made unless the county biologist makes written findings of fact and conclusions of biological opinion which substantiate the need and/or benefits to be derived from the authorized deviation. (m) Mangroves and Submerged Lands: Except as provided in subsection (3), only piers, docks, utility pilings and walkways shall be permitted on submerged lands and mangroves; All structures on any submerged lands and mangroves shall be designed, located and constructed such that: All structures shall be constructed on pilings or other supports; Bulkheads and seawall shall be permitted only to stabilize disturbed shorelines or to replace deteriorated existing bulkheads and seawalls; No structure shall be located on submerged land which is vegetated with sea grasses except as is necessary to reach waters at least four (4) feet below mean low level for docking facilities. (Emphasis added) From the foregoing regulations it is apparent that Monroe County has accorded mangroves the highest of protections. The regulations mandate a 100 percent open space ratio in such areas, and preclude any clearing or other disturbance of such areas. The only exception provided by the regulators, absent approval of an application for a minor or major conditional use, is for the construction of piers, docks, utility pilings and walkways, and then only when such structures are constructed on pilings or other supports to minimize their impact. Here, the proposed development, "permitted as of right" and not as a minor or major conditional use, fails to comply with the Monroe County land development regulations because it will result in the elimination of an existing mangrove community. In addition to the environmental design criteria established for mangroves by section 9.5-345, discussed supra, that section likewise establishes-specific performance standards for the development of any parcel (lot) depending on the habitat type, and where mixed habitat is encountered, requires that development occur on the least sensitive portions of the parcel. Here, while the Applicants did address the habitat types encountered along the canal alignment, the record fails to address the habitat types encountered on each of the platted lots through which the canal will run. Consequently, the Applicants failed to demonstrate that development of those lots, by construction of a canal within their rear boundary, would be consistent with the open space ratios mandated by section 9-804, MCLDR, or the environmental design criteria mandated by section 9.5-345, MCC. C. The Monroe County land development regulations further and implement the Monroe County comprehensive plan. The foregoing land development regulations were adopted by Monroe County, as well as approved by the Department and adopted by the Administrations Commission, to further and implement the standards, objectives and policies of the Monroe County comprehensive plan. That plan evidences a strong commitment to the protection, maintenance, and improvement of the Florida Keys environment. In this regard, the comprehensive plan provides: Sec. 2-104. Nearshore Waters The Florida Keys are dependent nearshore water quality for their environmental and economic integrity. The heart of the Florida Keys economy, the means by which Monroe County exists as a civil and social institution, is based on its unique, oceanic character. If nearshore water quality is not maintained, then the quality of life and the economy of Monroe County will be directly and immediately impacted. OBJECTIVES 1. To protect, maintain and, where appropriate, improve the quality of nearshore waters in Monroe County. POLICIES 1. To prohibit land uses that directly or indirectly degrade nearshore water quality. To prohibit the development of water dependent facilities, including marinas, at locations that would involve significant of the biological character of submerged lands. To limit the location of water- dependent facilities at locations that will not have a significant adverse impact on offshore resources of particular importance. For the purposes of this policy, offshore resources of particular importance shall mean hard coral bottoms, habitats of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of legs than four (4) feet, and all designated Aquatic Preserves under Ch. 258.39 et seq. the Florida Statutes. To limit the location of docking facilities to areas which have adequate circulation and tidal flushing. To protect wetland and transitional areas that serve to buffer, insulate and protect nearshore waters from run- off from upland areas. To prohibit the discharge of any pollutant directly or indirectly into nearshore waters. For the purposes of this policy, indirect discharge into nearshore waters shall include surface runoff, surface spreading or well injection of any effluent that does not meet state or federal standards for point and non-point discharges. To monitor nearshore water quality to ensure that growth and envelopment is not degrading nearshore water quality. To encourage the rehabilitation of canals and other water bodies where water quality has deteriorated. Sec. 2-105. Wetlands and Associated Systems Wetlands are an essential element of the Florida Keys and they play several vital roles. Wetlands serve as principal habitats for a wide variety of plants and animals, including juvenile forms of several commercially-exploited species of seafood. In addition, wetland plants play an important role in pollution control through nutrient uptake, and in primary production control through nutrient uptake, and in primary production for food webs. Wetland plants also serve as important natural buffers to the onslaught of storm-driven winds and water. OBJECTIVE To protect and maintain the functional integrity of wetlands and associated transitional areas within the Florida Keys. POLICIES To prohibit the destruction, disturbance or modification of any wetland or associated transition area, except where it can be demonstrated that the functional integrity of a wetland or associated transitional area will not be significantly adversely affected by such disturbance or modification. Marine Resources The great value attributed to Monroe County's marine resources is due to their crucial role in the local economy, and in providing a wide range of natural amenities and services. Health and integrity of the marine system is a fundamental prerequisite if these resources are to continue to provide social, economic, and environmental benefits that we have at times taken for granted. Mangroves, seagrasses, and coral reefs, all of which are susceptible to pollution and dredging, are extremely important in providing food and shelter for myriad forms of marine life, providing storm protection, and maintaining water quality. If uses and activities such as dredge and fill, destruction of natural vegetation, use of pesticides and fertilizers, improper sewage and solid waste disposal continue indiscriminately and uncontrolled; the ability of the marine system to function effectively will deteriorate, thereby resulting in the loss of many natural services and socioeconomic benefits to society. Therefore, it is imperative that such uses and activities be carefully regulated so as to insure conservation and protection of resources and long-term maintenance of their productivity. Marine Resources Management Policies Recognizing the crucial role that the marine environment plays in the economy, the protection, conservation, and management of marine resources will be viewed as an issue requiring the County's utmost attention. In an effort to protect and conserve marine resources, emphasis will be placed on protecting the entire marine ecosystem. To this end, maintenance of water quality; protection of marine flora and fauna, including shoreline vegetation; and preservation of coral reefs will be regarded as being absolutely essential to maintaining the integrity of the marine system. * * * Land and water activities which are incompatible with the preservation of marine resources because of their potential adverse effects will be prohibited, restricted, or carefully regulated depending upon the nature of activity and the extent of potential impact. * * * 3.2. Dredging and/or filling associated with maintenance or necessary water- dependent public projects shall be minimized and carefully managed to prevent unnecessary adverse environmental impact. The County will develop and enforce stringent development regulations to minimize water pollution from point and non-point sources in an effort to: improve and maintain quality of coastal waters. . Marine grass beds, mangrove communities, and associated shoreline vegetation will be preserved to the fullest extent possible. Removal of vegetation or modification of natural patters of tidal flow and nutrient input, cycling and export should be considered only in the case of overriding public interest. The County will encourage creation and restoration of marine grass beds, and mangrove communities in areas which could support such growth and could potentially enhance the environmental quality. As far as possible, natural patterns of gradual and dispersed runoff will be maintained. Land and water activity in the vicinity of stress areas (coral, grass bed, and inshore water quality) as identified and illustrated in the Florida Keys Coastal Zone Management Study and as may be discovered during any future study will be carefully controlled and regulated in an effort to arrest further deterioration. Research and study directed toward alleviating the stresses and restoring their condition to natural healthy state will be encouraged arid supported. Marine Resources Areas of Particular Concern Site-specific Designations Lignumvitae Key Aquatic Preserve. * * * Management Policies: B. Development activity on Upper and Lower Matecumbe Keys, including dredging and filling will be prohibited so as not to degrade the waters of the Preserve. * * * 3. John Pennekamp Coral Reef State Park and Key Largo Coral Reef Marine Sanctuary. Management Policies: * * * B. Development activity on Key Largo, including dredging and filling, urban runoff water, and the use of septic tanks will be controlled and regulated in order to minimize stresses which result in cater quality deterioration. Generic Designations All marine grass beds in waters off the Florida Keys. All patch reef coral and other reef formations found in the surrounding waters off the Keys. All shore-fringing mangrove and associated vegetation extending up to 50 feet laterally upland from the landward limit of the shoreline mangrove. Management Policies A. These biotic communities will be preserved to the fullest extent possible. Natural Vegetative Resources The diverse and often unique plant associations of the Florida Keys are a vital element of Monroe County's natural system and economic structure. The natural functions performed by these plant communities with1 regard to marine resources, unique and endangered wildlife, shoreline stabilization, filtering of urban runoff and scenic value make them vital elements in maintainance of the urban structure and attractions for the tourist base of Monroe County's economy. Natural Vegetation Management Policies In recognizing the need to preserve as much natural vegetation as possible, the County will direct its land use and development regulations; to minimize destruction of natural vegetation and modification of landscape. Guidelines and performance standards designed to protect natural vegetation from development will be developed and enforced. Clearing of native vegetation for development will be controlled. 3. Regulations controlling development in areas characterized primarily by wetland vegetative species such as mangrove and associated vegetation will emphasize preservation of natural vegetation to the maximum degree possible. 8. The existing County ordinances designed to protect and conserve natural vegetation will be strictly interpreted, rigidly enforced, and/or amended when necessary. Consistent with the Monroe County comprehensive plan, the Monroe County land development regulations further the standards, policies and objectives of the plan to protect, maintain and improve the Florida Keys environment. In this regard, the provisions of the regulations requiring final plat approval before a development order may issued provide assurance that the proposed activity will be -consistent with the comprehensive plan, the land development regulations, and applicable provisions of state law. Likewise, pertinent to this case, the provisions of section 9-864, MCLDR, regarding open space requirements, and section 9.5-345, regarding environmental design criteria, further the plan's policy to minimize the destruction of natural vegetation and modification of landscape, and to preserve to the maximum degree possible areas characterized primarily by wetland vegetation, such as mangroves and associated vegetation, and to permit such removal only in cases of overriding public interest. Here, while it cannot be concluded, as advocated by the Department, that the Monroe County comprehensive plan and land development regulations prohibit, under any circumstances, construction of the subject canal, it must be concluded, at this stage, that construction of the canal has not been demonstrated to be consistent with the plan and regulations. To be consistent, the Applicants would have to secure final plat approval for the canal, through the plat amendment process; a minor or major conditional use approval, as appropriate, as mandated by, inter alia, section 9 .5-345, MCC, for destruction of the mangrove community; and demonstrate that excavation of the canal on each of the platted lots would be consistent with the open space ratios of section 9- 804, MCLDR, and the environmental design criteria of section 9.5-34, MCC, or secure a conditional use as required by section 9.5-34-5, MCC. Amendment to the application post hearing In their proposed recommended order, submitted post hearing, the Applicants propose that the hearing officer recommend that, as a condition, the proposed canal terminate at the line of mean high water instead of extending approximately 100 feet into the boundaries of John Pennekamp State Park. The ostensible reason for the Applicants' request is their desire to eliminate the need for seeking approval from the Department of Natural Resources for intrusion into the boundaries of the park, and thereby shorten the time needed to secure all governmental approvals. While the Applicants did elicit testimony at hearing, albeit on rebuttal, that termination of the canal at the mean high water line would not significantly affect its performance as a flushing canal due to the extreme porosity of the caprock, the proof is not persuasive that the subject permits should be so limited or conditioned. Notably, the opinion that was offered in this regard was that of an expert hydrographic engineer who directed his remarks solely from a hydrographic viewpoint. The Applicants offered no testimony or other proof that would address the potential impacts, in any, that might occur to, inter alia, water quality or the biota, should the canal be terminated or closed in such a fashion. Under the circumstances, the Applicants failed to persuasively demonstrate that such amendment or condition is appropriate. This finding is not, however, preclusive of their applying for such modification to Monroe County.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Florida Land and Water Adjudicatory Commission enter a final order sustaining Monroe County's issuance of the subject permits in so far as they relate to Phase I of the proposed project, and reversing Monroe County's decision to issue the subject permits in so far as they relate to Phase II of the proposed project. It is further recommended that such final order specify those items set forth in paragraph 4, Conclusions of Law, as the changes necessary that would make the Applicants' proposal eligible to receive the requested permits for Phase II of their proposal. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 19th day of October 1990. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of October 1990.

Florida Laws (8) 120.57177.091258.39380.031380.032380.0552380.07380.08
# 8
RAYMOND H. HODGES, JR., AND ANNE G. HODGES vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-001088 (1981)
Division of Administrative Hearings, Florida Number: 81-001088 Latest Update: Dec. 01, 1981

Findings Of Fact On August 5, 1980, the Petitioners filed an application for a dredge and fill permit pursuant to Chapters 253 and 403, Florida Statutes, and Chapter 17-4, Florida Administrative Code, as well as for water quality certification pursuant to Chapter 401 of Public Law 92-500, as amended, United States Statutes At Large. On March 20, 1981, the Department gave the Petitioners notice that it intended to deny their application for the permit and notified Petitioners of their right to a hearing pursuant to Sections 120.57, Florida Statutes, which right they chose to exercise. The Petitioners own a tract of land adjacent to and partially within the landward extent of the Suwannee River in Dixie County, Florida. The Department of Environmental Regulation (Department) is an agency of the State of Florida charged with carrying out the mandates of Chapter 403, Florida Statutes, and the rules contained in Chapter 17, Florida Administrative Code, promulgated thereunder. The Petitioners propose to embark on a project involving the dredging of a canal approximately 200 feet long in a generally westerly direction from the navigable portion of the Suwannee River through the river berm into the river swamp or floodplain. Across and perpendicular to the landward end of that access canal the Petitioners propose to construct a boat basin approximately 100 feet wide by 275 feet long in the swamp floodplain. The proposed excavation would be to a depth of 6.25 feet below mean sea level and approximately 9000 cubic yards of fill material would be deposited as-fill in the adjacent swamp floodplain remaining around the boat basin and access canal. A boat ramp would then be constructed into the boat basin. A retaining wall would be constructed around the excavated areas along the north and south property lines of the property owned by the Petitioners. The property to be developed by the Petitioners lies within the landward extent of the Suwannee River in Dixie County and the Suwannee River constitutes waters of the State over which the Department has dredge and fill permitting jurisdiction pursuant to Rule 17- 4.28(2)(a), Florida Administrative Code. The project area lies within an "outstanding Florida water" as defined in Rule 3.041(3)(g), Florida Administrative Code. The river terrace or "berm" on the property immediately adjacent to the navigable portion of the river is caused by the natural deposition of alluvial material. The landward extent of the State waters which are the subject matter of this proceeding cross the property immediately behind this terrace and connect with the navigable portion of the river on an adjacent parcel of property. The proposed dredging operation would connect 37,500 square feet of a dead-end canal system excavated to minus 6.25 feet below mean sea level to the navigable portion of the Suwannee River. The dredging and filling operation would result in the permanent elimination of approximately 2.84 acres of the landward extent of the Suwannee River floodplain which is dominated by plant species listed in Rule 17-4.02(17) , Florida Administrative Code, which define jurisdiction of the Respondent. The proposed dredging and filling will cause and constitute a stationary installation reasonably expected to be a source of pollution. The Petitioners during the course of this application process cleared the subject property at least in part. Prior to that clearing operation, the terrace area was vegetated with bald cypress, blue beech, water hickory and sweet gum, with bald cypress and buttonbush becoming the dominant plant species progressing in a southerly direction along the terrace. Landward of the natural terrace or berm, the cypress-tupelo swamp was dominated by water tupelo, bald cypress, water ash, and buttonbush, all species listed in Rule 17- 402(17), Florida Administrative Code. An additional inspection conducted after the land-clearing operation revealed that the area was again sprouting or revegetating into the same swamp species, with the dominant species being bald cypress. The swamp area in question provides flood protection as well as control of sedimentation by the storing of flood waters and the filtering of sediment and particulates releasing them in a gradual fashion to the river system especially during dry periods when the river level is lower than that of the swamp. This also serves to augment the stream flow in the river itself during such periods. The proposed activity, by removing the trees and other plant species named above, as well as because of the dredging and filling of the swamp floodplain area, would cause degradation of local water quality. The swamp currently contributes to the maintenance of water quality in the navigable river itself by the filtering of sediment and particulates, as well as the assimilating, uptake and transforming of nutrients and other pollutants by the plant species growing on the site. The proposed project would destroy by tree- cutting, and the dredging and filling, this function of the swamp area in controlling pollution and promoting water quality in the river. The river swamp on this parcel of property, as well as on adjacent areas, serves as a habitat, food source and breeding ground for various forms of fish and wildlife. The proposed dredging and accompanying filling of the floodplain area with the associated removal of trees and other plants and increased turbidity would largely eliminate this function on the Petitioners' property and drastically alter the swamp area as a habitat, food source and breeding ground on adjacent areas, particularly downstream of the property. The most notable long-term adverse impact of this project would include excessive turbidity caused by the removal of the subject plant species and the deposition of the fill in the floodplain area. Turbidity would be a special problem during times of excessive rain and high or flood waters in the river and adjacent swamp land. An additional long-term detrimental effect will be excessive nutrient enrichment in the area due to the removal of the filtrative and assimilative functions performed by the trees and other plant life across the entire width of the swamp. As a result the adjacent areas will be unable to fully take up the nutrient load formerly assimilated by the plant life on the project area. The project will thus permanently eradicate the subject area's filtrative and assimilative capacity for nutrients, heavy metals and other pollutants. Because of its physical design and dimensions and tangential exposure to river currents and tidal flow, the proposed canal and boat basin will be characterized by sluggish circulation and will lack sufficient flushing action to maintain water quality at an appropriate level, particularly with regard to dissolved oxygen content. The lack of adequate water exchange or flushing will lead to an accumulation of oxygen-demanding sediment and organic waste in the canal and boat basin. This accumulation results in low-dissolved oxygen content in the water and anerobic conditions, which result in a substantially decreasing ability for the water to support aquatic and other wildlife. The lack of water exchange will lead to an accumulation of nutrients which can result in explosive growth of noxious aquatic weeds. In turn, these weeds grow and decay and contribute through the decay process to the low-dissolved oxygen levels in the canal. Thus, the long-term effects will result in violations of water quality criteria for biochemical oxygen demand, nutrient content and dissolved The cumulative effect of a proliferation of projects such as this one involving dredging of canals and associated filling, as well as filled roads across similar floodplain areas, will cause degradation of local water quality in violation of State standards both singly and in the aggregate. Such a project ultimately alters the hydro-period of the area, which is the average time during which flood waters are retained in the swamp and floodplain area for gradual, filtered release into the river itself. The altered hydro-period will result particularly from the removal of trees and other plant species which perform a filtrative function for flood waters and associated sediment. The removal of the plant life will result in a more rapid flow of waters through the subject swamp area which will prevent sediments from precipitating out of the water before it returns to the navigable river which effect will be heightened by the presence of the turbidity caused by the deposition of the fill material and its exposure to the erosive effect of flood waters. The Petitioners additionally failed to show that the project was necessary in order for them to have access to the navigable portion of the river. The Department advocated prior to and during the hearing that a viable and acceptable alternative would be the construction of a walk-way or a bridge on pilings across the jurisdictional area in question connecting the two upland portions of the Petitioners' property. Although the bridge or walkway would require a permit, the Department took the position that it would not object to such a permit for an elevated wooden walkway and dock into the navigable portion of the river or a bridge for vehicles and an attendant boat ramp. The Petitioners did not agree to such a solution of the controversy. It should also be noted that access is available for the Petitioners to the waterward portion of the property from the navigable side of the river berm by boat. The Petitioners contend they are entitled to a permit by default on the part of the Respondent. The Department received the application on August 5, 1980. Three days later on August 8, 1980, the Respondent requested additional information and informed the Petitioners that they had to present evidence of consent to the use of the State-owned land involved from the Board of Trustees of the Internal Improvement Trust Fund/Department of Natural Resources (DNR). The application was forwarded to the DNR on September 8, 1980. Another copy of the application was forwarded to the DNR on January 8, 1981. A letter from DNR to the Petitioners on approximately March 9, 1981, indicates that the application was held in abeyance pending notification of action by the DER, the Respondent herein. Ultimately, the DNR by letter of March 19, 1981, acknowledged receipt of payment for the subject fill material, but elected not to formally consent or reject the project. It has been the practice of the Respondent Department to await a DNR consent or rejection prior to issuance of its notice of proposed agency action. The Department issued its intent to deny by letter on March 20, 1981, which was 43 days after the Petitioners' last modification of its application on February 5, 1981. Thus, the application was not complete until February 5, 1981, since the Petitioners never furnished the lawfully requested information until that date.

Recommendation Having considered the foregoing-findings of fact, conclusions of law, the candor and demeanor of the witnesses and the pleadings and arguments of counsel, it is therefore RECOMMENDED that the petition of Raymond H. Hodges, Jr., and Anne G. Hodges for a dredge and fill permit be DENIED. DONE AND ENTERED this 16th day of October, 1981, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 1981. COPIES FURNISHED: Raymond H. Hodges, Esquire Post Office Box 1688 Zephyr Hills, Florida 33599 Silvia Morell Alderman, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (8) 120.57120.60253.77403.021403.031403.087403.0876403.088
# 9
FLORIDA ATLANTIC DEVELOPMENT CORPORATION vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-000175 (1978)
Division of Administrative Hearings, Florida Number: 78-000175 Latest Update: Apr. 30, 1979

Findings Of Fact Petitioner represents the owner of the property here involved, St. John's Riverside Estates, and was authorized by the owner to prosecute this appeal (Exhibit 19). Some years ago, circa 1960, the owner of the property dredged canals in each of the two parcels here involved, but the plug between the canals and the St. Johns River was not removed. Petitioner now proposes to remove these plugs and maintenance dredge a channel from the location of the removed plug to the St. Johns River. Spoil from the maintenance dredging will be deposited on lands owned by Petitioner. The existing canals are typical dead-end canals which are stagnant at present. By removing the plugs and opening the canals to the St. Johns River, Petitioner will improve the water quality of these canals. Developing the property along the canals as residential homesites will result in additional nutrients and pollutants entering the canals from surface water runoff. Petitioner proposes to use surface water runoff as one method of flushing the canals. Other flushing action would come from tidal flow in the St. Johns River. Although there was some conflict in the testimony regarding the propriety of using the rainfall from a twenty-five year storm event in lieu of of a one-year storm event to calculate the flushing action of the canals by rainfall, use of surface water to flush the canal appears to violate the provisions of Chapter 403, Florida Statutes, respecting water quality. As a condition to the development of the property, Respondent could require Petitioner to hold the surface water runoff in retention ponds to reduce the entry of pollutants into the river. If this was done, percolation and evaporation would further create a substantial reduction in flushing from this source. The St. Johns River is a Class III water body of the state. The water quality of the canals here under consideration are below the state water quality standards with respect to dissolved oxygen levels even using the samples taken during the winter months when dissolved oxygen levels are high. (Exhibits 1, 2 and 3). Generally, dissolved oxygen levels are lower at the bottom of such canals than at the surface. If the samples taken at the surface and bottom during the winter months are averaged for dissolved oxygen content, the result will be above the state minimum water quality standards. However, the dissolved oxygen of samples taken from the canals on May 5 and October 4, 1978, are predominately below the level of 5 mg/l prescribed as the minimum state standard. Removing the plugs would not result in satisfactory flushing of these canals by tidal action. Under the best assumed conditions, it would require 18 tidal cycles or 9 bays to flush 90 percent of the water from these canals by tidal action. An acceptable flushing rate is 2 to 3 days. These canals contain water hyacinths and grasses which increase the biochemical oxygen demand (BOD) which reduces the dissolved oxygen level. Not only do these vegetations reduce photosynthesis by shading the water from sunlight, but also when they die and fall to the bottom, they create a high BOD. Considerable evidence was presented depicting the area, the flora and fauna of the area and the present condition of the water quality of these canals. No evidence was presented to the effect that removing the plugs and allowing interchange between the low quality waters of the canals and the higher quality waters of the St. Johns River would not degrade the water quality of the St. Johns River. Also, no evidence was presented that the residential development of the area as proposed would not increase the coliform count, detergent level, or heavy metals content of the waters of the canals which would further cause a degradation of the river water if the plugs are removed and the waters of the river and canals are interchanged.

Florida Laws (1) 403.088
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer