Findings Of Fact Based on the stipulations of the parties, the exhibits received in evidence, and the testimony of the witnesses at the hearing, I make the following findings of fact: On April 21, 1983, the College filed an application with DER seeking a permit to relocate a drainage ditch that runs through the College property, to fill the existing drainage ditch, and to install a large culvert in the Coconut Creek Waterway which would serve as a road crossing connecting the proposed new College parking lot and N.W. 39th Avenue in Coconut Creek. Upon review of the original application, DER determined that it would not meet the DER's water quality criteria. On September 30, 1983, the College revised its application. It is the revised application which lies at the heart of the present controversy. The revised application no longer contains a proposal to fill in the entire ditch that runs through the College property. Rather, it is new proposed to install two 36-inch culverts in the existing ditch to provide access roads to the proposed new College parking lot. The College also proposed to dredge 832 cubic yards from .5 acres and to install a large structural culvert (measuring 14 feet, 1 inch, by 12 feet, 10 inches) in the Coconut Creek Canal. The existing ditch which runs through the College campus was originally constructed as a drainage ditch. The only water which would flow through that ditch would be provided by run off from the N.W. 11th Street area. At the present time the ditch through the College is plugged in two places. Some time in late July or early August of 1984, contractors employed by the College placed two earthen plugs in the ditch that runs through the College. This was done without benefit of a Department permit and was apparently the result of some confusion on the part of the contractors, the exact nature of which is not explained in the record in this case. The two earthen plugs were not installed in the manner proposed by the subject application, nor were they installed in the locations proposed in the subject application. In their present condition the two earthen plugs effectively prevent the flow of any water through the ditch that runs through the College. The north end of the ditch that runs through the College campus was formerly connected to Coconut Creek Canal. A portion of Coconut Creek Canal runs parallel to N.W. 11th Street. Following the installation of the earthen plugs there was a decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W. 11th Street. The water became cloudier than before and there was some silting. There were fewer base and bluegills and more mudfish. There has also been an occasional unpleasant odor from the area which was not present prior to the installation of the earthen plugs. Also, the residents along N.W. 11th Street complain of an increased mosquito Population since the installation of the earthen plugs. 1/ The proposed 36-inch culverts are substantially larger than is necessary to handle the anticipated flow of water through the College ditch. Calculations made using the methodology approved by the Florida Department of Transportation indicates that 21-inch culverts would have been sufficient to handle any anticipated flow of water through the College ditch. Although the culverts will require some periodic maintenance, they have been designed to minimize the need for maintenance. Properly maintained, the proposed 36-inch culverts will not pose any impediment to the flow of water through the College ditch. There is usually no detectable current or water flow in either Coconut Creek Canal or the College ditch in the area where the College proposes to install the three culverts. Accordingly, inasmuch as there is usually no detectable flow of water, any impediment to water flow which might be caused by the culverts is insignificant. This is particularly true with regard to the issue of weed growth. While it has been contended that the culverts might reduce the rate of water flow to the extent that aquatic weed growth would be promoted because of the stillness of the water, long before this permit was ever applied for and long before the earthen plugs were installed the City of Coconut Creek had serious problems with aquatic weeds growing in all of its canals. As described by one of the City's former mayors, several years ago the hyacinths covered the canals solid from bank to bank and were growing so thick and solid that rabbits could actually run across the canals hopping on the hyacinths. This type of hyacinth growth only occurs in still water. The City has been able to control the hyacinth problem by an ongoing weed control program which consists of spraying chemicals on the plants several times each year. The small amount of water flow which does occur in Coconut Creek Canal is directly related to stormwater runoff, including water generated by the residents along N.W. 11th Street washing their cars and watering their lawns. The portion of Coconut Creek Canal which extends eastward from the College ditch is a dead end system in which the only flushing is due to water runoff from the street. The installation of the proposed large culvert in Coconut Creek Canal would never cause the water to back up in the canal or otherwise impede the flow of water in the canal. A tube 21 inches in diameter would be sufficient to carry away the worst expected rain water conditions and the proposed culvert is, in essence, a tube with an average diameter in excess of 13 feet. The large culvert would cause no change in the volume of water flowing through the canal. It might cause a de minimis headloss, which is a change in the water level from one side of the culvert to the other. Any such headloss would be on a magnitude of approximately 1/1000th of a foot; about 1/3 of a millimeter. The installation of the large culvert in the Coconut Creek Canal would actually increase the velocity of any water flow through the culvert. In conjunction with the installation of the large culvert, the depth of Coconut Creek Canal would be increased to an average of six or six and one-half feet from its present average of approximately five or five and one-half feet. Notwithstanding the decrease in the water quality of the portion of Coconut Creek Canal that parallels N.W 11th Street which apparently resulted from the unauthorized installation of the two earthen plugs, when the water in that portion of the canal was tested by the City's export witness some eight or nine months later, the water quality was within established state standards. And while the construction activity associated with the installation of the two 36-inch culverts in the College ditch effect on the water quality in Coconut Creek Canal, there is no evidence that water quality standards would be violated on either a short or long-term basis. A small amount of habitat would be destroyed, but it is likely that there would be rapid recolonization. No rare or endangered animal species would be affected. The habitat for birds would also recolonize and the birds and fish displaced by construction would return. Any turbidity problems during construction would be controlled by the use of turbidity screens. With regard to navigability, once installed the large culvert would provide a vertical clearance from the surface of the canal of approximately six feet. This clearance would prevent larger boats from passing through the culvert. The vertical clearance of existing canal bridges in the area varies from six and one-half to eight feet. Installation of the larger culvert would not seriously impede navigation. The large culvert would not constitute a navigational hazard nor would it impede the flow of navigable water. As compared to the situation which existed prior to the installation of the two earthen plugs, installation of the two 36-inch culverts would totally stop any boat traffic through the ditch that runs through the College. Nevertheless, curtailment of boat traffic through the College ditch would not seriously impede navigation because any destination which could be reached by traveling through the College ditch could be reached via alternative canal routes which are not affected by this project. As with the larger culvert, the 36-inch culverts would not constitute navigational hazards nor would they impede the flew of navigable water. If the total project envisioned by the College is completed, the culverts will provide a new route for motor vehicle access to an expanded College parking lot. The increased volume of motor vehicle traffic would produce an increased amount of air and noise pollution in the vicinity of N.W. 39th Avenue. A study of the results of the increased motor vehicle traffic based on a "worst case" scenario reveals that even with the additional air and noise pollution generated by the increased motor vehicle traffic, the air and noise pollution levels in the area would be far below the air and noise pollution standards established by the state and federal governments. In the formulation of the foregoing findings of fact I have, of necessity, relied to a large extent on the opinions of expert witnesses who testified in the case. Where there is conflict in the testimony of the expert witnesses, I have generally credited the testimony of the expert witnesses called by the College and the Department because I have found their testimony to be more consistent with other evidence in the case and have found that there is a better factual foundation in the record for their opinions than for the opposing opinions.
Recommendation For the foregoing reasons it is Recommended that the Department issue a Final Order which would GRANT the College's application to install two 36-inch culverts in the College ditch and a 14-foot, 1-inch, by 12-foot, 10-inch, culvert in the Coconut Creek Canal, subject to the conditions set forth in the Department's Notice of Intent to Issue. DONE and ORDERED this 8th day of October, 1984, in Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of October, 1984.
Findings Of Fact On June 27, 1979, Respondent Department of Environmental Regulation's St. Johns River District office received an application from Petitioner John W. McPhail, Deland, Florida, for a permit to conduct dredge and fill activities on his property at Lake Johnson, DeLeon Springs, Florida. The application reflected that Petitioner desired to dredge 100 cubic yards of material Waterward of the lake mean high Water line and 100 cubic yards landward of the mean high water line, and then fill an adjacent cove area on his Property with the 200 cubic yards of material. (Respondent's Exhibit 1) Lake Johnson is a small privately owned lake about fifteen acres in area. There are two distinct "lobes" of the lake which are joined by a narrow band of water. Each of these lobes is approximately seven acres in area. Some four or five houses, including, Petitioner's, are located around the lake. In the early Seventies, Petitioner dredged part of his shoreline and, in the process, too much material was inadvertently removed from the present cove area and placed in the middle of the property, which left a hump of land in the middle. The shoreline now is irregular with steep ungraded banks, and the cove area is somewhat stagnant. Petitioner wishes to restore the property by dredging the "hump" created by prior filling, and return the material to its Original location by filling the cove area. This will produce an even, sloped shoreline extending some 200 feet and improve the appearance of the lakefront. It will also reduce present maintenance Problems. (Testimony of Petitioner, Vause, Petitioner's Exhibits 1-3) A field biologist in Respondent's District Dredge and Fill Permitting Section conducted an on-site inspection on August 28, 1979, and rendered a report of the inspection on October 2, 1979. He found that the dominant plant community along the banks of the shoreline consisted primarily of upland weeds and grasses such as broomsedge and bahaia grass. Additionally, primrose willow was found in that location. The vegetation along the shoreline includes maidencane and a small amount of bullrush while the open water area is predominately vegetated with water lilies. Primrose willow is a species of vegetation found in the transitional zone of a submerged land, and bullrush, maidencane, and water lily are also fresh water species of vegetation found in submerged lands, as defined in Chapter 17-4, Florida Administrative &ode. The water depth in the lake is approximately eight feet and the depth the water at the steep banks of the Petitioner's property is approximately three feet. Wetlands vegetation of the above types are conducive to the improvement of water quality by increasing dissolved oxygen levels after removal of polluting nutrients from the water. The removal of a significant amount of such vegetation may have a measurable adverse effect on water quality. Although Lake Johnson, a Class III body of water, presently has excellent Water quality, the vegetation along the shoreline has been removed to a degree of about ten to fifteen percent. The removal of fifteen to twenty percent or more of a shoreline in such a lake normally produces a measurable adverse effect on water quality. The dredging of material along a shoreline can produce short-term turbidity of the water. (Testimony of Vause, Respondent's Exhibits 2-3) Respondent's inspector found that although filling the cove would remove some beneficial aquatic and land vegetation, would most likely reestablish if proper sloping was maintained on the shoreline. He also noted in his report that the proposed project would restore approximately one-half acre of open water to the lake. He therefore interposed no objection to the filling aspect of the project, but believed that dredging should not be undertaken waterward of the ordinary high water line, and that the shoreline should be merely contoured without dredging. By letter of October 4, 1979, Respondent's district manager advised Petitioner of its intent to deny his application for permit for the reason that the proposed work would eliminate approximately .5 acres of wetland community and thereby degrade water quality in the areas of BOD, turbidity, and dissolved oxygen. (Testimony of Vause, Respondent's Exhibits 2-4)
Recommendation That Petitioner be issued the requested permit, subject to standard conditions. DONE and ENTERED this 13th day of February, 1980, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Segundo J. Fernandez Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 John W. McPhail Route 1, Box 692H Deland, Florida 32720 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION JOHN W. MCPHAIL, Petitioner, vs. CASE NO. 79-2174 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION Respondent. /
Findings Of Fact Background On January 29, 1981 respondent/applicant, George H. Hodges, Jr. (applicant or Hodges), filed application number 16 39644 with respondent, Department of Environmenta1 Regulation_ (DER), seeking a dredge and fill permit to generally authorize the excavation of 26,000 cubic yards of material from a 3,700 foot portion of an existing channel (Old Pablo Creek) just west of the Intracoastal Waterway (ICW) in Jacksonville, Florida. The channel then proposed was a straight channel along the northern boundary of his property. Hodges also sought to construct two boat slips, three floating docks, an 850 foot vertical bulkhead adjacent to the docks, and to dispose of all dredged material in a diked upland site. Thereafter, DER informally advised applicant that it intended to deny the application for various reasons, including the fact that the dredging would eliminate .75 acres of marsh and wetlands. After receiving this advice, Hodges proposed a series of amendments to his application in 1984 and 1985 in an effort to counter and satisfy DER's objections. The final amendment was made on September 10, 1985. As finally amended, Hodges proposed to confine all dredging to existing salt channels, thereby eliminating the objection that adjacent marshes would be destroyed. Applicant also proposed to restrict his dredging to only 2,250 feet along the northern portion of Old Pablo Creek and to remove 29,250 cubic yards of fill (silt) and sand and place the same in a 12.5 acre upland spoil site. By proposed agency action issued on February 28, 1985, DER announced it intended to issue the requested permit. This prompted a protest and request for hearing from petitioner, Jacksonville Shipyards, Inc. (JSI), which owns and operates a ship repair facility on the ICW just south of the proposed project. In its petition, JSI generally alleged that (a) Hodges had failed to give reasonable assurances that water quality standards would not be violated, (b) the project would adversely affect its property, (c) the project would have an adverse effect on the conservation of fish and wildlife, (d) the project would cause harmful erosion or shoaling, (e) DER failed to consider the long-term effect of the project on marine productivity and the cumulative impact of the project, and (f) the proposed vertical bulkhead did not meet statutory requirements. The Project The project site is a shallow horseshoe shaped creek approximately 3,700 feet in length which meanders through a vegetated salt marsh just west of the ICW in Duval County, Florida. Both ends of the creek connect into the ICW. The site is approximately one-half mile north of the bridge on Atlantic Boulevard which crosses the ICW. The ICW is a man-made channel constructed by the U. S. Corps of Engineers which runs in a north-south direction just east of the project site. It is commonly referred to as Pablo Creek. The channel or creek in which the dredging will occur is known as Old Pablo Creek (creek). An excellent aerial view of the entire area is shown in petitioner's exhibit 4 received in evidence. The creek is a predominately marine water classified as a Class III water of the State. Accordingly, it is subject to DER's regulatory jurisdiction. For purposes of this hearing, the parties have referred to the upper and lower portions of the creek as the northern and southern portions, respectively. Hodges intends to dredge the northern portion of the creek, which measures approximately 2250 feet in length from the ICW to a bend at its western end which crosses Hodges' property and where a residential site is located. According to Hodge's affidavit of ownership, he is the "fee interest owner of adjoining lands except for the dredge channel which is owned by the State of Florida". He acknowledged, however, that the residential site is owned by his superintendent, and that the marshes adjoining the most southern bend in the northern portion of the creek, and the southern portion of the creek, are owned by JSI. Except for the cleared residential site at its western end, the creek is surrounded by vegetation and salt marshes. The vegetated portion of the marsh is marked by a clearly delineated edge which separates it from the creek bottom. The dominant species of vegetation in the marsh are Juncus and Spartina. The marsh serves as a habitat and breeding ground for numerous species, including fiddler crabs, mussels, barnacles, mollusks, faunal communities and gastropods. In addition, the marsh is beneficial because of its biotic productivity and entrapment of nutrients and sediments. For this reason, the habitat should be maintained. Some forty years ago, the portion of the creek that Hodges intends to dredge was eight to twelve feet deep. However, dredging of the ICW by the Corps of Engineers and the placement of fill at the site of the Atlantic Boulevard Bridge have contributed to the shallowing of the creek over time. Today, portions of the creek are exposed and impassable under low tide conditions. Indeed, many parts of the creek are dry during the low tide phase of the ICW. At high tide, the creek is flooded to an approximate depth of four feet. Hodges proposes to dredge the creek channel to a uniform depth of five feet below mean low water (MLW) with side slopes at a 3:1 ratio to restore navigational access from his upland property to the ICW. He has represented that his use of the channel will be restricted to one, or possibly two, small boats for personal use and enjoyment. When completed, the creek channel will have a depth of nine feet at high tide, or an average depth of seven feet over a diurnal cycle. In his amended application, Hodges proposed to confine his dredging to existing creek channels, and to not disturb the actual body of the salt marsh or the vegetation bordering the creek. It is noted that there is no vegetation growing in the existing creek bottom. However, at hearing he conceded that dredging "may include some minor removal of isolated patches of grass growing in the creek channel". One such patch of grass lies in the elbow of the canal which reaches south of Hodges' property, a patch separated from the main body of the marsh by a five foot wide slough deep enough to be navigated at high tide. Hodges estimates this patch of grass to be less than 1/100 of an acre in size (10' x 40') and maintains the effect of its removal would be negligible. The excavation will be effected by means of a Mud Cat hydraulic dredge which operates by suctioning the sediment and water into a pipe. The dredge material (sediment/water mixture) will then be pumped into a series of containment cells on a 12.5 acre upland spoil site that lies approximately one-half mile northeast of the project. Any discharge from the spoil site will be to Greenfield Creek, a tidally influenced creek connected to the St. Johns River. The natural grade of the existing creek bottom is at or below the mean low water datum. At high tide the existing creek is 4.3 feet deep at its deepest point and gradually slopes upward to a depth of 2.4 feet near the marsh. The elevation of the creek where it meets the marsh is close to mean high water. Even so, the channel width does not always correspond with the mean high water line boundaries of the creek, and creek waters sometimes inundate and extend back into the marsh at high tide. Because Old Pablo Creek is tidally influenced, any water quality violations in the northern portion of the creek can be expected to also have an adverse effect in the southern portion as well. Creek Width Petitioner has raised the issue of whether the creek is as wide as Hodges represents it to be on the drawings attached to the amended application. This is significant since (a) the engineering plans are based upon the assumption that the measurements in the application are correct, (b) the proposed dimensions (depth and side slopes) of the new channel are dependent upon the existing creek having a minimum width of from sixty to eighty feet, as represented by Hodges, and (c) any excavation outside of the existing channel will result in the removal (destruction) of vegetation and marsh. In his application, Hodges reflects the top width of the creek to be sixty to eighty feet, which width will enable him to dredge the channel to an average depth of five feet below MLW, and maintain a side slope ratio of 3:1. This ratio is necessary because of the composition of the sediment in the creek. The minimum top width required to excavate a channel with 3:1 side slopes to a depth of five feet below MLW is fifty- four feet. Petitioner's exhibit 4 identifies five points along the eastern half of the northern portion which have been measured by the parties to determine the actual width of the creek. Although only five points were measured, it may be inferred that these distances are representative of the creek's width throughout its eastern half. At points five through eight, the widths are forty-nine, thirty-five, fifty and fifty feet, respectively, which are less than the measurements contained in the application. If the channel is constructed with the minimum top width (54 feet) required to have 3:1 side slopes, it will result in the elimination of 6 feet of marsh at point 5, 19.5 feet of marsh at point 6, and 4.1 feet of marsh at both points 7 and 8. This equates to the elimination of approximately .33 acres of marsh. Since the above measurements are representative of the eastern half of the northern portion, other areas of vegetation, albeit in unknown proportions, would also have to eliminated. If, for example, applicant attempts to construct a channel within the confines of the portion of the creek that has a top width of only thirty-five feet (point 6), the maximum channel that could be constructed would be V-shaped with a depth of one foot at low tide. Assuming the remaining part of the channel was excavated to -5' MLW, a stagnant area would develop in this portion of the channel and adversely affect water quality. However, to counter the problem at point 6, Hodges intends to remove one patch of grass 10' by 40' in size to achieve the desired width. Any adverse effects on the adjacent marsh at that particular point would be negligible. Because the estimated creek width is not accurate, even the agency now concedes the engineering plans are no longer useful. As a condition to the issuance of a permit, DER has suggested that Hodges be required to submit new certified engineering drawings depicting the proposed cross-section of the channel. It also suggests that the proposed cross-section comply with the top-widths depicted in applicant's exhibit 53, and depict side-slopes of three to one. It further suggests that a condition for the issuance of any permit be a requirement that the 3:1 ratio be maintained, and that other than point 6, no other grass be removed. Finally, the agency proposes that if the new plans and conditions do not permit a -5 MLW depth, the proposed depth be reduced accordingly. However, the evidence supports a finding that either vegetation must be removed at various points along the eastern half of the creek in order to maintain a 3:1 ratio for side slopes, or the depth must be reduced. By reducing the depth at certain points, stagnant areas in the creek will develop, thereby adversely affecting the quality of the water. Further, as noted hereinafter, the validity of the flushing analysis performed by applicant's experts rests upon the assumption that a -5' MLW uniform depth will be used. Finally, the applicant has not given reasonable assurance that the marsh and habitat will not be adversely affected by the elimination of the vegetation which is necessary to achieve the desired depth and concomitant 3:1 ratio. Therefore, the alternative conditions suggested by DER are neither reasonable or appropriate. The Spoil Area The spoil area to be used by applicant is a 12.5 acre upland disposal site approximately one-half mile northeast of Hodges' property. Applicant does not own the upland spoil site but has obtained easements from the owner which expire in March, 1987. In other words, he must complete all work on the project by that date or lose access to the property. The proposed spoil site is completely diked, and is sectioned off into three sections by interior dikes with overflow pipes. Internal baffles and silt fences are also designed into the area. Uncontradicted testimony established that the spoil area is "unusually well designed". Any discharge from the spoil area will be to Greenfield Creek, a tidally influenced creek connected to the St. Johns River. Discharge, if any, will be outfall from an overflow structure in the third section of the spoil area to a dump area land then by sheet flow to salt marshes adjacent to Greenfield Creek. The vegetation in Greenfield Creek consists of a salt marsh expanse of Spartina alterniTlora and Juncus roemerianus. Both species survive in and are indicative of regular introduction of saline waters, and show high tolerance to varying salinity levels. If saline waters from Old Pablo Creek were introduced into Greenfield Creek, it would have no adverse impact on the Greenfield Creek ecosystem. The size of the site was originally designed for a project of 100,000 cubic yards. The site will retain all |effluent from the dredging. The expected total effluent, both sediment and water, is roughly 5.3 million cubic feet of material, assuming a ratio of 6.7 cubic feet of water for each |cubic foot of sediment dredged. This is slightly lower than the 5.4 million cubic feet total capacity of the site. The supernatant from the discharge being deposited into the first cell of the spoil area will only flow into the next cell when the first cell fills and the level of the supernatant rises above the top of the vertical drain pipe overflow structure. If rainfall events cause the cells to fill with water during dredging and discharge operations, the discharge to the next cell or to Greenfield Creek will be primarily fresh water. This will occur because introduction of fresh rainwater into the brackish water from the dredge area will cause stratification, and the fresh rainwater will form a layer on top that will flow into the overflow structure. Turbidity Effects In removing the mud bottom from the creek to a depth of -5' MLW, some turbidity will occur. This is a natural by- product of using the hydraulic dredge. However, the amount of turbidity, and its effect on the waters at the dredge site and discharge point, are in issue. State water quality standards prohibit the discharge of water with a turbidity level greater than twenty-nine nephelometric units (NTU's) above the background levels of the receiving waters. The evidence indicates that the background turbidity levels at the creek are now in the range of ten to twenty NTV's. Excessive levels can result in adverse effects on local biota such as decreasing productivity by reducing light penetration. Excessive turbidity can also be expected to suffocate organisms. The area to be dredged contains sediment deposited from the surrounding salt marsh and carried in from the ICW. The sediment is composed of 14% clay, with the remainder being sand and silt. This was confirmed by a laboratory analysis conducted by JSI. As a general rule, the coarser the material, the faster it tends to settle out thereby creating less turbidity problems. Therefore, sand, which is of a grain size, can be expected to settle out quickly while silt takes somewhat longer. However, clay size particles are much smaller than silt and do not settle out as easily. Applicant made no laboratory analysis of sediment and consequently he erroneously assumed the mud to be sand and silt, and did not take the clay particles into account. The dredging in the creek will cause the turbidity levels to rise to 150 NTU's. However, the placement of a turbidity screen at the entrance to the ICW will prevent the release of this turbidity into that water body. Therefore, if a permit is issued, such screens should be used by Hodges at the dredge site. At the spoil site, clay size particles will also be included in the matter pumped for discharge. If these particles do not settle out, or are not treated, their discharge into Greenfield Creek (a jurisdictional water) will cause violations of the turbidity standards. To counter their effects, flocculants (chemicals) should be added when necessary to the confined material to aid the particles in settling. If a permit is issued, this should be made a condition in the permit. Dissolved Oxygen Impacts The dissolved oxygen (DO) levels in the creek fluctuate on a daily and seasonal basis. As a general rule, DO levels tend to be lower in warmer weather and during the early morning hours. Therefore, a "worst case" situation will generally occur in the summer months in the early part of the day. State water quality standards contained in Rule 17- 3.121(13), F.A.C., provide that in predominately marine waters, the concentrations of DO "shall not average less than 5 milligrams per liter in a 24-hour period and shall never be less than 4 milligrams per liter." Sampling conducted by petitioner at 5:00 a.m. in early July, 1986 during high tide revealed readings ranging from 3.06 mg/1 in the western portion of the creek to 4.59 mg/1 at the mouth of the creek. Dissolved oxygen levels in the ICW ranged from 3.94 to 4.68 mg/1. Hodges also sampled the creek and ICW in the late morning or early afternoon on August 6,1986 and determined DO levels to be 4.8 mg/1 in the creek and 5.8 mg/1 in the ICW. Testing at that hour of the day produced higher values than those found by JSI. The readings collectively confirm that DO levels in the creek are approximately 1.0 mg/1 less than the DO levels in the ICW. This deficit is primarily caused by the high oxygen demand exerted by the adjacent marsh and muds in the creek. This situation will not be changed by the dredging. The flushing time of the creek channel is an important factor in predicting post-dredging impacts on water quality. Flushing time determines how rapidly waters of the ICW will exchange and mix with the water in the creek channel. Both Hodges and JSI conducted tidal prism studies to determine how many tidal cycles would be required to flush a hypothetical pollutant to 10% of its initial concentration. Under worst case conditions, the channel is expected after dredging to flush every 3 to 4 tidal cycles or 1.6 days. Under more favorable conditions, the creek is expected to flush every 2 to 3 tidal cycles. This compares with the current system which flushes almost 100% every tidal cycle or once every twelve hours. The increased flushing time is due to the significantly greater volume of water that will enter the creek channel after dredging. Because of increased channel depths, the water will move at a slower velocity. Therefore, the oxygen consuming components have a longer period of time to react in the water column. This in turn will cause reductions in DO levels of between .7 mg/l and 1.5 mg/l in the creek. This was confirmed through tidal prism modeling performed by JSI. In this regard, it is noted that JSI's modeling was more sophisticated, better calibrated, and its assumptions were more accurate and reasonable. Consequently, its testing results are considered to be more reliable and persuasive than that of applicant. It must also be recognized that the deepening of those areas that are currently exposed at low tide will allow water to move more easily through the channel and remove some oxygen demanding sediments that now draw from a shallow water column. This will tend to have a beneficial effect on water quality. However, the overall impact of these beneficial effects is unknown, and it was not demonstrated that the otherwise adverse effect on DO will be offset or minimized by the unmeasured impact of deepening the shallow areas. Therefore, applicant has not given reasonable assurance that water quality standards will not be violated by the project. At the same time, it must be further noted that a reduction in the channel depth due to the smaller width of the creek will alter the results of the tidal prism studies, as well as negate some of the beneficial effects caused by deepening the shallow portions of the channel. To what extent the studies are changed, or benefits will be reduced, is not of record. Other Effects of Project As noted earlier, Hodges intends to use one or two boats on the deepened channel. The use of the boats will not introduce pollutants in any significant quantity. Hodges proposes to construct his docks and place rip- rap on the northern side of the widest portion of the creek channel. Little, if any, vegetation will be eliminated by these activities. The use of rip-rap for the construction of the bulkhead is the most environmentally sound means of bulkheading, and will stabilize the shoreline as well as provide habitat for aquatic organisms. The dredging of the creek channel will improve the navigability of the creek, and permit the use of boats in areas where access is now impossible under low-tide conditions. In addition, the sharp bends in the creek will prevent the operation of boats at high speeds. JSI's concern that boats may run aground once they leave the northern portion and enter the southern portion is not meritorious since few, if any, are expected to use the latter part of the creek, and the sharp bends will force boaters to operate at low speeds. Shoaling or erosion of the southern portion will not result from the proposed activities. Indeed, an increased flushing and introduction of new flow into the system may benefit the northern portion. Any situation occurring in that part of the creek should not exceed the rate of siltation occurring under current conditions. The benthic organisms which populate the bottom of Old Pablo Creek include crabs, mussels, barnacles and other species normally associated with estuarine systems. The removal of the mud bottom in the dredging operation may remove some of these organisms. However, this should not significantly change the habitat of these benthic organisms. Rapid recolonization by these species would be expected with recolonization substantially underway within forty-eight hours
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that application number 16-39644 of George H. Hodges, Jr. for a dredge and fill permit be DENIED. DONE and ORDERED this 2nd day of December, 1986 in Tallahassee, Florida. DONALD R. ALEXANDER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of December, 1986.
The Issue The issue to be determined in these consolidated cases is whether proposed Florida Administrative Code Rule 62-42.300 is an invalid exercise of delegated legislative authority.
Findings Of Fact The parties agree and the Administrative Law Judge has determined that there exists no genuine issue as to any material fact. In the December 4, 2014 SERC addendum, the Department described the changes to the proposed rule as follows: The Notice of Change filed on November 7, 2014 does not change the proposed minimum flows or the recovery strategy included in the proposed rules. The Notice of Change merely adds the existing technical information that the Administrative Law Judge found missing in the original rule text, which results in the proposed rule being found by the Judge to be vague. Specifically, these changes include: Adding the period of record used to establish the baseline flows in the Lower Santa Fe and Ichetucknee Rivers and subsequently used to develop the proposed minimum flows, and, Adding the method used for filling the data gaps in the baseline flow record for the Ichetucknee River. The Final Order in Still-I determined that the proposed minimum flows were vague because they did not include a period of record (of water flow data) to be used with the flow duration frequencies. Flow duration frequencies are percentages of time that a particular amount of flow (in cubic feet per second) is equaled or exceeded, which can vary depending on the period of record that is used. The proposed rule now describes the period of record that was used to derive the minimum flows. Petitioners contend that the rule is still vague because the rule does not identify the period of record that will be used in the future to determine whether the minimum flows are being achieved. Petitioners expressed concern that Suwannee River Water Management District might use a scientifically unsound period of record to determine that the MFL waterbodies are no longer “in recovery.” Neither the Department nor Suwannee River Water Management District identified in Still-I or in this proceeding the period of record that will be used to determine whether the minimum flows have been achieved. However, the Recovery Strategy for the MFL waterbodies is in its first phase. The rule contemplates that the MFL waterbodies will remain in recovery at least until completion of the North Florida Southeast Georgia Regional Groundwater Flow Model in 2019 and the MFLs and the Recovery Plan are re-evaluated with the model as part of phase See proposed Fla. Admin. Code R. 62-42.300(1)(d). This interpretation was confirmed by the Department and the District at the hearing on the motions for summary final order. The Supplemental Regulatory Measures (which are unchanged) do not require applicants for consumptive use permits to determine or show how a proposed withdrawal of water will affect the flow duration frequencies set forth in the rule. The period of record to be used in determining whether the minimum flows are achieved is not used in the permitting process.
Findings Of Fact By an application filed with the Department of Environmental Regulation on October 28, 1980, Pinellas County requested a dredge and fill permit to- construct a road and bridge crossing with an associated stormwater treatment system in connection with the improvement of County Road No. 1 across Curlew Creek and its wetland flood plain. The specific location of the project is in Section 12, Township 28 South, Range 15 East, in the City of Dunedin, Pinellas County, Florida. The project will involve the dredging of approximately 2,639 cubic yards of soil and include the placement of approximately 1,605 cubic yards of fill in the creek bottom. After an evaluation of the initial application the Department issued a letter of intent to deny the application on March 17, 1982, but the denial suggested several modifications to the project which were accepted by the County when it filed an amended application on September 30, 1932. It is on the basis of this amended application that the Department issued its notice of intent to grant on November 5, 1982. The County's initial application was complete before February I, 1982, the effective date of Chapter 17-25, Florida Administrative Code, the Department's new stormwater discharge rules. The Petitioners jointly own real property on which they reside immediately to the west and downstream of Curlew Creek. Their property is riparian to the creek. Curlew Creek is a natural water body which runs from near U.S. Highway 19 in a westerly direction to the Gulf of Mexico in Dunedin, Florida. It is an unnavigable Class III water of the state. At times it carries a heavy stormwater runoff load and passes private residences such as Petitioners' which border the creek in many areas. During design storm events there has been flooding when the creek exceeds its historic flood plain. That flooding has come up into Petitioners' back yard. At the project site where the creek now runs under the existing span for County Road No. 1, the creek is approximately 25 feet wide and 2 feet deep. The creek bottom is flat and consists of deep fine sand. The banks are well vegetated with a dense scrub layer and many large trees. This vegetation provides good soil stabilization and prevents erosion of the creek banks. Curlew Creek is presently traversed by County Road No. 1 over a two- lane bridge. Because of increased traffic flow the County proposes adding another bridge span to carry two more lanes of traffic. When the additional two lanes are complete the center line of the entire bridge complex will be moved to the west of its present location and therefore be closer to Petitioners' residence. Petitioners primary concern in opposing the project is their belief that when completed the project will increase the potential of Curlew Creek to flood their land. Curlew Creek, which generally runs in an east-west direction, takes a sharp bend to the south on the downstream side of the existing bridge. It later resumes its course to the west toward St. Joseph's Bay and the Gulf of Mexico. The creek's rapid change of direction underneath the bridge caused some confusion when the Department of Environmental Regulation issued its notice of intent dated November 5, 1982, to grant the requested dredge and fill permit. Condition number one for issuing the permit stated "The existing vegetation in an area more than 50 feet up and downstream from the bridge railing will not be disturbed except in the area of detention pond number 3 on the northeast side of the bridge." The author of the notice had intended that the condition mean vegetation would not be disturbed any further than 50 feet to the east or 50 feet to the west of the planned bridge railing, and not 50 feet upstream or downstream. The project plan is to remove a small sand spit which projects into the creek from the east bank immediately to the south of the bridge. Additional minor dredging is planned to smooth the water flow through the bridge area. Fill will be deposited to also provide a smoother water flow and consequently cut down on the eddies which presently arise under the bridge. The result of improved stream flow will be a reduction in the erosion of the creek banks and a lessening of turbidity in the creek water. Because the construction proposed will result in removal of certain vegetation along the creek bank which now provides soil stabilization, the County plans to use wet sand cement riprap or gabions for slope protection to stabilize the soil. Either method provides adequate erosion protection to ensure that the standards for Class III surface waters of the state will not be violated if the conditions of the proposed permit are followed. The expanded stormwater runoff facilities which are part of the project, as modified and subject to the condition in the Department's letter of intent to grant, will not have a significant impact on the water quality of Curlew Creek. These facilities provide adequate retention and settling capacity to ensure that the stormwater which eventually discharges into the creek will not cause pollution.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Environmental Regulation enter a Final Order approving the application of Pinellas County for a dredge and fill permit in order to construct the above described project in accordance with the conditions set out in the Department's letter of intent to grant dated November 5, 1982. DONE and RECOMMENDED this 24th day of October, 1983, in Tallahassee, Florida. MICHAEL P. DODSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of October, 1983.
Findings Of Fact Respondent, South Florida Water Management District (District) is a multipurpose water management agency of the State of Florida. Its duties include the operation and maintenance of a vast network of canals which provide flood control and other benefits to Palm Beach County. Pertinent to this proceeding, the District is the owner in fee of a 600' right of way which contains a canal known as C- The tidewater reach of C-18 extends east from a control structure (S-46) near State Road 706 downstream for a distance of 8,375' (1.6 miles) to the southwest fork of the Loxahatchee River. Of this distance, 7,322' lie upstream from a small bridge, which crosses the C-18 at Loxahatchee River Drive (the bridge) and 1,053' downstream. The canal is approximately 200' wide, with 200' of overbank right of way on its north and south sides. The River Trails Development Petitioner, River Trails, Ltd (River Trails) is the developer of a 28 acre condominium community in Palm Beach County known as River Walk. The River Walk development, comprised of 347 townhouse units, is contiguous to 2,500' of the south overbank right of way of the C-18, approximately midway between S-46 and the southwest fork of the Loxahatchee River. On December 9, 1983, River Trails filed an application with the District for a right of way occupancy permit to selectively clear and regrade the C-18 right of way and to construct a marina facility within the right of way consisting of a temporary parking area, boat ramp and 3 docking facilities with a combined capacity of 97 boats. The District approved River Trails' application and issued it a permit on January 12, 1984. That permit provided: WORK PROPOSED WILL BE COMPLETED ON OR BEFORE 1-31, 1985, otherwise, this permit is voided and all rights thereunder are automatically cancelled unless an extension to the construction period is applied for and granted. Upon receipt of the District's permit, River Trails began to selectively clear the bank of the canal of exotic vegetation, primarily Brazilian pepper, and to regrade the bank to a more gentle slope than its existing 12'-14' vertical drop on the west and 2'-3' vertical drop on the east. In the process, 28 mangrove trees were damaged or destroyed.1 To settle a dispute which arose between Palm Beach County and River Trails over the destruction of the mangroves, River Trails agreed to plant additional mangroves and spartina grass along the southeasterly shoreline of the C-18. To consummate that agreement, River Trails requested that the District modify its permit to allow the selective planting of mangroves and spartina grass along the shoreline and in a tidal slough, to alter the bank slope to provide a wider intertidal zone to accommodate the plantings, and to move the proposed docks further out from the bank of the canal. The District granted River Trails' requested modification on June 25, 1984 subject to the following special conditions: Construction of the boat dock facilities as originally permitted and modified hereunder is subject to the issuance of a permit from the DER. Prior to commencement of construction, the applicant shall submit a DER permit for the boat docking facilities. Any future modification of the boat docking facilities by the applicant must have the approval of the governing board prior to construction. Rule 40E 6.301(c), Florida Administrative Code, requires an applicant to give reasonable assurances that the proposed use of the works of the district "does not degrade the quality of the receiving body and meets the standards of the Florida Department of Environmental Regulation for the receiving body. The board may waive the strict enforcement of this provision." Neither issuance of the original permit nor this modification shall be construed as a waiver of this provision as it applies to the per- mitting activity of the DER relative to this project. Department of Environmental Regulation Permitting On December 22, 1983, River Trails applied with the Department of Environmental Regulation (DER) for a permit and water quality certification to construct its boat ramp and 97 slip marina. During the processing of that application, River Trails requested two waivers of the 90 day time period prescribed by Sections 120.60(2) and 403.0876, Florida Statutes, (180 days total) in order to conduct a hydrographic survey of the area in order to respond to water quality concerns raised by DER. River Trails did not submit a hydrographic survey to DER, nor did it offer such a survey in this proceeding. On December 20, 1984, DER advised River Trails that its proposed boat ramp was exempt from permitting requirements. Thereafter, on December 21, 1984, DER issued its "intent to deny" the balance of River Trail's application predicated on its conclusion that the project was expected to have a long and short term adverse impact on the water quality and biological resources of the C-18 canal and the adjacent Outstanding Florida Waters of the Loxahatchee River. Specifically, DER found that degradation of water quality in the project's Class II waters and the adjacent Outstanding Florida Waters would likely occur due to: Shading from docks and walkways that would likely prohibit recolonization of shoreline vegetation. Marinas can be expected to lower water quality by the accumulation of marina source contaminants, including heavy metals, greases, oils, detergent ,and litter. Increased boat traffic (97+ boats), and their associated wakes will result in increased shoreline erosion. This additional erosion can prohibit the recolonization of shoreline vegetation beneficial to water quality. The cumulative impact of this project and other similar projects within the C-18 canal would be expected to degrade water quality. Prop wash from outboard motor boats in shallow littoral shelf areas will cause turbidity problems and adversely impact existing benthic communities. DER further found the proposed activity contrary to the public interest provisions of Chapter 253, Florida Statutes, since the proposed marina would substantially interfere with the conservation of the Florida Manatee and the destruction of natural marine habitat. River Trails declined to pursue its DER application for the 97 slip facility any further. Instead, it filed an application with DER for a docking facility of less than 1,000 square feet, accommodating 37 boats, to qualify for the exemption provided by Section 403.812(2)(b), Florida Statutes. Following a successful rule challenge in April 1985, River Trails received its statutory exemption. The District's emerging management policy. Shortly after the District approved River Trail's modification on June 25, 1984, it began to receive a great deal of negative comment from the public, DNR, DER, and the United States Fish and Wildlife Service. These comments, of which the District was not previously aware, included concerns for the Loxahatchee River, the Florida manatee, and negative biological and water quality assessments. Accordingly, the District's Governing Board requested that its staff investigate and evaluate various management options for the overall development of the 18 right of way. During the ensuing months the District's staff solicited input from DER, DNR, the Florida Game and Fresh Water Fish Commission and the United States Fish and Wildlife Service; investigated the C-18; and formulated its recommendations for the future management of the canal. On January 10, 1985, the District's staff submitted its management plan to the Governing Board. The plan recommended that the intertidal zone be widened a minimum of 10 and planted in mangrove and spartina to combat erosion of the canal banks by boat wakes; that the canal banks be regraded to a minimum of one vertical on four horizontal slope and stabilized with a combination of grasses, native trees and shrubs; and that the overbank right of way be cleared of exotic species and replanted with native trees and shrubs. In keeping with the main goal of habitat improvement, staff recommended that the cumulative linear extent of areas provided for bankfishing and viewing be limited to 10 percent of the shoreline and that no structure be located waterward of the mean high water line. Subsequent to its January 10, 1985, meeting the District has pursued its management plan for the alteration of the shoreline and berms of C-18. Since that time two permits have been issued to large developers who agreed to reslope and revegetate, at their expense, the banks of the C-18 in accordance with the District's plan, and in exchange for the esthetic view accorded by C-18. No dockage, boat ramps, or other structures have been permitted. River Trails' permit expires Following DER's denial of its application for a permit to construct the 97 slip marina, River Trails requested that the District modify its permit to reflect a 37 slip facility and extend the permit for one year. River Trails subsequently withdrew its request to modify the permit. On January 10, 1985, the District entered an order denying River Trails' request for a one year extension of its permit. The District's denial was predicated on its perceived environmental sensitivity of the C-18 canal and the Loxahatchee River system, and its conclusion that the project was contrary to the restoration concept of the District's developing management plan for the C-18. River Trails filed a timely request for hearing, and the matter was referred to the Division of Administrative Hearings and assigned Case No. 85-2272. On July 16, 1985 River Trails reapplied to the District for approval of its modified proposal for a boat ramp and 37 slip marina. The District denied River Trail's request on September 12, 1985. Reasons for denial included adverse water quality impacts, endangerment of the manatee population, increased bank erosion and increased liability risks to the District associated with increased boat usage of the C-18. River Trails filed a timely request for hearing, and the matter was referred to the Division of Administrative Hearings and assigned Case No. 85- 3678. Impacts of the River Trails Development Because of its location and physical characteristics, boating activity in the C-18 has not been extensive. The canal joins the Loxahatchee River on its western shore, opposite the popular boating areas in the intercoastal waterway and Atlantic Ocean adjacent to the River's eastern shore. Access to the canal is restricted by a bridge with a 6' clearance, and its western expanse is blocked by S-46. Accordingly, boating activity within this 1.6 mile stretch of 18 has been generally limited to fishing trips to S-46, sightseeing, and occasional water skiing. River Trails' facility will increase boating within the C-18 well beyond the 37 slip capacity of its dock facility. River Trails proposes to provide upland storage for the boats of a all condominium unit owners, and expects a majority of owners to utilize the slips or boat ramp. Accordingly, use of the facility will not be limited to 37 boats but, rather, will reach into the hundreds. The District's management plan for the C-18 is designed to restructure the canal's present configuration to provide natural habitat, reduced erosion and scenic beauty. As originally designed, the C-18 had 1 on 2 side slopes throughout its reach, however, erosion of the bank downstream from S-46 has resulted in nearly vertical, unstable side slopes above mean high water along 40 percent of its length. The overbank right of way is heavily vegetated with exotic species. With the exception of several areas near the downstream end of the canal, mangroves are not well established along the existing shoreline due to the shading effect of overhanging Brazilian pepper and a rather narrow unstable intertidal zone. Currently, little use of the overbank right of way is made by the public due to its dense vegetation, and any view of the canal is severely impeded. Under the District's management plan the intertidal zone would be expanded and planted in mangroves and spartina to combat erosion from boat wakes and to provide natural habitat; existing vertical banks would be recontoured to a more gentle slope and stabilized with grasses and native trees; and the overbanks would be cleared of exotics so that native trees could prosper. To date the District has been successful in carrying out its plan; however, the survival of the mangrove seedlings and spartina is dependent on minimal disturbance. The introduction of the boats from River Trails would increase erosion and prevent the recolonization of shoreline vegetation beneficial to water quality, marine habitat, and canal bank stabilization. Furthermore, existing and proposed development along the C-18 right of way can be reasonably expected to exacerbate the erosion problem if River Trails' permit is granted. River Trails' proposed marina also raises the specter of adverse impacts to water quality, wildlife and habitat. The C-18 is classified as a Class II surface water body, and supports a diversity of aquatic life. Commonly observed species include snook, mullet, mangrove snapper, pinfish, needlefish and filter feeding organisms such as oysters. The endangered Florida Manatee, Trichechus manatus, is also observed in the C-18 and downstream in the Loxahatchee River. The Loxahatchee River is classified as outstanding Florida waters (OFW) and critical habitat for the Florida manatee. The river, as well as C-18 up to the S-46 control structure, has also been included by the Department of Natural Resources (DNR) within the Loxahatchee River Zone of the Florida Manatee Sanctuary Act.3 Due to the restricted access from C-18 into the Loxahatchee River, boats located at River Trails' development will likely be approximately 23' in length and powered by outboard motors. Such watercraft, through their introduction of oils and greases, contribute to a degradation of water quality however, neither party addressed the potential impacts to water quality which would be occasioned by the total number of boats that would utilize the boat ramp and boat slips at the proposed facility. By failing to address this issue, and limiting its proof to the impacts from a maximum of 97 boats, River Trails has failed to give reasonable assurances that its proposed project will not cause or contribute to a violation of Class II water quality standards. The impact of River Trails' project upon the Florida manatee is less clear than its impact upon the C-18. Although designated part of the manatee sanctuary, C-18 presently offers little in the way of food source for the manatee with the exception of some plant materials near S-46. The grass Fla. within the Loxahatchee River and the intercoastal waterway are the manatee's primary food source and congregating areas; however, as the mangrove and spartina plantings along the intertidal zone of the canal mature, the manatee may more often. venture into the canal. Whatever their frequency within the narrow confines of the C-18, the numbers of boats that would be introduced by River Trails would drive the manatee from the area. These boats would not, however, pose a significant threat to the manatee or its habitat within the Loxahatchee River since its navigation channels are well marked to avoid grass flats. Indeed, there has been no boat related manatee mortality in the Loxahatchee River area since 1977. The District's concern regarding increased liability risk is unpersuasive. Pursuant to rule the District requires that an applicant for a permit to occupy right of way provide the District with insurance coverage satisfactory to the District, There is no suggestion that the insurance coverage tendered by River Trails, and accepted by the District, was inadequate or otherwise unsatisfactory. The District's decision to deny River Trail's application was not inconsistent with its existing practice. While the District has permitted docks and boat ramps in other canals, there was no showing that those canals abutted a sanctuary or were under redevelopment to improve the works of the District.
The Issue The issues are whether Respondent, Mosaic Fertilizer, LLC (Mosaic), has provided reasonable assurances that the proposed mining and reclamation of the South Fort Meade Mine in Hardee County can be conducted in a manner that comports with the applicable statutes and rules such that the proposed Environmental Resource Permit (ERP), Conceptual Reclamation Plan (CRP), variance from minimum standards for dissolved oxygen, and variance from littoral zone percentage provisions for the Project should be issued by Respondent, Department of Environmental Protection (Department).
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Mosaic is a limited liability company authorized to do business in the State of Florida and is the applicant in these proceedings. It was formed by the merger of IMC Phosphates Company and Cargill, Inc., in 2004. Mosaic has applied for permits to mine, reclaim, and conduct associated activities on property in Hardee County, Florida, known as the South Fort Meade Hardee County tract. These activities are referred to in this Recommended Order as the "Project" or "site." The Department is a state agency with jurisdiction over ERP permitting under Part IV, Chapter 373, Florida Statutes, for phosphate mining activities with jurisdiction over phosphate mining reclamation under Part III, Chapter 378, Florida Statutes, and with jurisdiction over variances associated with phosphate mining under Section 403.201, Florida Statutes. Pursuant to that authority, the Department reviewed the ERP, CRP, DO Variance, and Zone Variance applications for the Project. Lee and Sarasota Counties are political subdivisions of the State of Florida. Both Counties have filed challenges to other mining applications and have been found to have standing in those cases. The site is located within the Greater Charlotte Harbor Basin, approximately sixty percent of which lies within Lee County. In this case, Lee County is concerned about the potential destruction of stream and wetlands in the mine area and the impact of mining and its effects on Charlotte Harbor and the Peace River. Sarasota County is a member of the Peace River Manasota Regional Water Supply Authority, and they jointly hold a water use permit, which authorizes them to withdraw water from the Peace River for potable supply. Sarasota County operates a water treatment plant on the Peace River downstream from the site and is concerned with potential impacts to water quality and wetlands. After three years of data collection and site analysis, on October 13, 2006, Mosaic filed applications with the Department's Bureau of Mine Reclamation for an ERP/Water Qualify Certification for the disturbance of approximately 7,756 acres of uplands, wetlands, and other surface waters within a 10,856– acre area which makes up the site; a CRP for the same parcel; and the associated Zone and DO Variances. Three sets of additional information were requested by the Department, and on January 31, 2008, the applications were deemed to be complete. On June 30, 2008, the Department issued Notices of Intent to issue the permits and grant the variances. The Project is located within the Peace River Basin. Little Charlie Creek, a tributary to the Peace River, enters the site in the northeast part of the tract and flows diagonally across the tract in a general southwest direction. The Project is located to the east of the Peace River, east of the town of Bowling Green, northeast of the City of Wauchula, and just south of the Polk-Hardee County Line in Hardee County, Florida. The Project site is twenty-nine miles from the Sarasota County line and fifty-three miles from the Lee County line. The Peace River eventually empties into Charlotte Harbor near Port Charlotte in Charlotte County. The Project consists of approximately eighty percent of upland land cover types, including large acreages converted to agricultural uses, such as cattle grazing, citrus production, and row crop production. The Project site consists primarily of citrus groves and pasture. Richard W. Cantrell, Deputy Director of Water Resources for the Department, has extensive experience and knowledge concerning agricultural parcels of this size in Central Florida. Based on his familiarity with the site, he indicated that all the streams have been impacted, the impacts to some areas of the site are severe, and the "site contains some of the most polluted streams with respect to sedimentation that I have ever seen." The other Mosaic and Department ecological experts familiar with the site concurred in that assessment, and the substantial data collections and application information support that assessment of the site. Of the 2,590.7 acres of wetlands on the property, approximately 751 acres of wetlands and other surface waters will be impacted. Of that 751, 91 are upland cut ditches or cattle ponds, 108 acres are other surface waters, and 274 acres are herbaceous wetlands. Virtually all of the native upland vegetation on the site has been destroyed due to the agricultural activities that have been undertaken on the site over time. Only remnant patches of native upland remain on the site. These comprise approximately nine percent of the site and are predominantly within the riparian corridors of Little Charlie Creek and the Peace River and are proposed to be preserved. The evidence established that the majority of the wetlands and streams proposed for impact are lower in quality; the higher quality wetlands are typically associated with the riparian stream corridors and are proposed to be preserved. The preserved uplands are primarily pasture but also include one hundred thirty-nine acres of upland forest. Twenty-nine distinct vegetative communities were mapped on the site during approximately two years of evaluation and assessment utilizing the Florida Land Use, Cover and Classification System (FLUCCS). There are numerous natural stream segments that were mapped on the parcel including the primary drainage systems on site, consisting of the Peace River, Little Charlie Creek, Lake Dale Branch, Parker Branch, and Max Branch. Substantial portions of the natural streams and their flood plains will be preserved; sixty-two natural stream segments totaling 58,769 linear feet will be mined. No sovereign submerged lands are proposed to be impacted by the activities. The Peace River to its ordinary high water line is sovereign submerged lands; however, no other streams on site are claimed as sovereign. Therefore, no authorization to utilize or impact sovereign submerged lands is required. The field work assessing the ecological condition of the site's wetlands, streams, and surface waters consisted of detailed quantitative and qualitative assessments using FLUCCS, the Wetland Rapid Assessment Procedure, and the Uniform Mitigation Assessment Methodology (UMAM) codified in Florida Administrative Code Rule Chapter 62-345. The level of assessment expended in evaluating the native upland and wetland habitats on the site was considerable and provided reasonable assurances that the current condition and relative value of the systems were adequately considered in the permitting process. From 2002 to 2004, Mosaic conducted intense ecological evaluations of the site, evaluating historical and aerial photography and other site documentation and conducting extensive examinations in the field, including vegetative, macroinvertebrate, and fish sampling and surveying, surface and ground water quality and quantity monitoring, wildlife observations, surveys and trapping, stream mapping and evaluation, soil analysis, and other efforts, both in areas to be mined and areas to be preserved, and in both uplands and in wetlands. The ecological assessments were primarily conducted prior to the hurricane events of 2004, although additional field work was conducted following the hurricanes. Mosaic and the Department's experts revisited the site in the fall of 2008 and agreed that the various ecological and biological assessments conducted prior to the hurricanes would tend to overstate the quality of the site as compared to its current condition. The hurricanes caused a significant amount of damage to the remaining forested habitats on the site. A formal wetland jurisdictional determination was issued and published without challenge in 2007 and therefore conclusively establishes the boundaries of the wetlands and surface waters on the site for permitting purposes. Seasonal surveys for wildlife on the site were conducted in 2003-2004 using the wildlife survey methodology prescribed and approved by the Florida Fish and Wildlife Conservation Commission. Specialized wildlife surveys and night-time surveys were also conducted. A total of 4,600 man hours of effort were expended to evaluate the presence of fish and wildlife, including threatened and endangered species, on the site. The entire site was surveyed, with over 2,600 miles of wildlife transects, to assess the presence of wildlife, and detailed information was recorded for all wildlife observations, including anecdotal observations by the ecologists performing the wetland assessments. Mosaic also engaged in an extensive effort to identify the natural stream channels proposed for impacts on the site. After discussion with the Department staff, Mosaic distinguished the natural streams in accordance with FLUCCS codes 511, 512, 513, and 514, as required by Florida Administrative Code Rule 62C-16.0051(4). Streams are a subset of the term "other surface waters" for ERP purposes. Although streams are defined in Section 373.019(18), Florida Statutes, as are other watercourses and surface waters, there is no operative use of, or reference to, streams in Part IV, Chapter 373, Florida Statutes, governing ERP permits. Also, there are no specific ERP mitigation requirements applicable to streams. Thus, the only specific regulatory use of the word "stream" occurs in the context of Florida Administrative Code Rule 62C-16.0051, and not the ERP rules. The Department and Mosaic established that the delineation of streams proposed for impact by mining on the site was sufficient and adequate for purposes of the CRP rules. In addition, Mr. Cantrell stated that, for purposes of the acre- for-acre, type-for-type (for wetlands) and linear foot (for streams) reclamation requirements in Florida Administrative Code Rule 62C-16.0051, the Department required Mosaic to delineate a stream as such until the point it enters or after it leaves a wetland area and to delineate the wetland polygon itself as a wetland, not a stream. This is true even if water continues to flow through the wetlands and reform as a stream at the other side. If the stream will not be impacted, then nothing in either the ERP or CRP rules requires its precise delineation, because the CRP rules apply only to reclamation of impacted areas. Thus, Lee County's assertion that "streams" has some special status by virtue of the definition in Section 373.019(18), Florida Statutes, has not been accepted. Mr. Cantrell further testified that the Department utilizes a substantially similar definition to delineate "streams" pursuant to Florida Administrative Code Rule 62C-16.0051(4), but as noted in Findings of Fact 44-46, subsection (5) of the rule requires restoration on a linear foot basis only of natural streams. Lee County contended that over 12,000 feet of natural streams were omitted or misidentified in the application. However, based upon the evidence presented, both historical and current, and applying the applicable regulations and statutes, this argument has been rejected. This contention was based on after-the-fact approximation of stream locations and lengths plotted from memory in a desktop analysis. Further, during his site visit to mark stream locations, Lee County's expert failed to use a handheld GPS device or maps. Therefore, the evidence submitted by Mosaic and the Department as to the location and length of the streams proposed for impact has been credited. Mr. Cantrell testified that even the best of the streams proposed for impact have been subjected to at least sixty years of agricultural disturbance and manipulation. For example, the system 22 series of stream segments will be impacted and replaced by the clay settling areas. While the witness characterized segment 22(o) as the most stable and least impacted of the streams to be mined, that segment is 376 feet long and located at the uppermost reach of the 22 systems. It is an extremely small percentage of the overall 12,000 plus feet of less stable and more severely impacted parts of system 22. Mosaic and the Department analyzed the origins and current condition of the streams to be impacted, most of which are less than three-to-four feet wide and one foot or less deep and flow only intermittently and seasonally. The ecological and hydrologic conditions of the site and its fish and wildlife populations and habitat values were assessed for purposes of the ERP and CRP regulatory criteria. Respondents' characterization of the functional value of the wetlands, streams, and surface waters is supported by a preponderance of the evidence. Lee and Sarasota Counties' assertion that the site wetlands and streams are in "good" condition and can be easily restored is not credited in light of the lack of empirical data to support this contention. The only way to recover the phosphate ore is through mining to remove the overburden layer and expose the phosphate matrix with a dragline. The first step prior to any land disturbance associated with phosphate mining is the installation of a "ditch and berm" system, which is recognized as a best management practice (BMP) by the Department and the United States Environmental Protection Agency. Installation of the ditch and berm system proceeds in phases to protect unmined wetlands and habitats from mining impacts as mining progresses; it is not constructed all at once. The ditch and berm remains in place around an individual mining unit until mining and reclamation have been completed and monitoring indicates the revegetation is sufficiently established such that no violations of water quality standards will occur upon re-connection to adjacent and downstream waters. It is then removed in accordance with the reclamation plan. The system serves a number of purposes described below. Berms are required to be constructed in accordance with specific design criteria. The height of the berm will be designed in accordance with rules specific to such structures to prevent water from overtopping the berm during a 25-year, 24- hour storm event, even if the ditch becomes blocked. Following installation of a ditch and berm system, bulldozers clear the mining area of vegetation. Up to three large electrically powered draglines operate generally in parallel rows to remove the overburden layer (the upper layer of sand and clay soil), which is approximately 23.6 feet thick on average, to expose the phosphate matrix, which is approximately 13-to-15 feet thick on average. The overburden is cast to the side in piles to be later reused in reclamation. The phosphate matrix is a mixture of sand, clay, and phosphate, which must be separated after mining. At the beneficiation plant, washing, screening, and flotation processes are used to separate the phosphate rock from the sand and clay. After washing and screening, the sand is pumped back to the mine cuts for use in reclamation, and the clay is pumped to clay settling areas (CSAs) in slurry form to decant. Both the transport of sand back to the mine areas for use in reclamation and the transport of clays to CSAs are considered "mining operations," not "reclamation." See Peace River/Manasota Regional Water Supply Authority, et al. v. IMC Phosphates Company, et al., DOAH Case No. 03-0791 (DOAH June 16, 2006; DEP July 31, 2006); Fla. Admin. Code R. 62C-16.0021(10) and (15). Thus, contrary to Lee County's allegation, the transportation of clays and sand is not a valid consideration in the financial responsibility required for mitigation. Through testimony and its materials balance tables, which are part of the application, Mosaic demonstrated that it has sufficient sand tailings and other waste materials to meet all of its reclamation requirements mine-wide, including both the Polk side and the Project site. However, while there is sufficient sand available to create the proposed reclamation topography and contours, the tables and testimony demonstrated a need, on a mine-wide basis, for lakes, as voids will remain otherwise. There will be only a very small pile of available sand remaining after all reclamation obligations on both the Polk side and the Project are met, an insufficient amount to eliminate the need for deep lakes as proposed. Mr. Myers, Mosaic's Vice-President of Mining, testified as to the three basic ways the waste materials generated by the beneficiation plant are disposed of on-site to facilitate reclamation. Sand tailings will be utilized in areas to be reclaimed as native habitats, wetlands, and streams. Clays will be disposed of in CSAs. However, based on the materials balance and logistical issues, the "land and lakes" reclamation method, which utilizes only the available overburden material remaining on-site after mining, will be used for the lake reclamation. This method allows sand tailings preferential use in reclamation of native habitats and use of shaped and contoured overburden in areas not proposed for wetland mitigation. Such is the case for the proposed reclaimed lakes. A CSA is an above-grade impoundment to hold clay slurry pumped from the beneficiation plant. This clay slurry is pumped into one side of a CSA in the form of muddy water. The clay settles to the bottom, and the clear water remains at the top. The clear water is drawn out from the opposite side of the impoundment, where it is recycled back to the beneficiation plant and mine for reuse. Over time, the clay consolidates and solidifies to form a solid soil, the surface area is drained, and the impoundment reclaimed. Three CSAs will be constructed on the northern portion of the site to hold the clay that cannot be stored in already- permitted CSAs in Polk County. The use of stage filling has allowed Mosaic to have additional usable space in its CSAs, minimizing the footprint of new CSAs in Hardee County. In addition, approximately fifty percent of the clay waste from the site will be disposed of at the Polk site to further minimize the clay disposal footprint and eliminate and reduce impacts. To evaluate the number of CSAs required, Mosaic asked Ardaman & Associates, a consulting firm, to examine different clay generation scenarios when predicting the CSAs required by mining and beneficiation. The life of mine waste disposal plan, most recently updated in September 2008, indicated that, in all but one scenario (the seventy percent clay containment scenario), all three CSAs would be required. However, Mosaic witness Garlanger established that all three CSAs in Hardee County would be necessary based on the best available information as to the amount of clays reasonably likely to be generated by mining; the seventy percent scenario is not likely. No evidence was presented to rebut that testimony. A diversion system was also voluntarily included for the CSAs by Mosaic. In the highly unlikely event of a dam failure, this system will re- direct any escaped water and/or clay materials to adjacent open mining cuts where they can be safely stored. The diversion system will be reclaimed when the CSAs are reclaimed. The evidence established that the ditch and berm system, CSAs, and diversionary structure are capable of being constructed and functioning as designed. The reclamation plan includes avoidance (no mining) of approximately 3,100 acres, or twenty-nine percent, of the site, including more than seventy-one percent of the total wetlands on-site. Of this, 2,100 acres will be placed in a perpetual conservation easement. There is a wide gamut of habitat types on the site that will be preserved and not mined, including both streams and wetlands. The most complex and least impacted habitats on the site have generally been included in the preserve area. The project includes disturbance of 751.3 acres of wetlands and other surface waters, which include non-wetland floodplains, cattle ponds, and upland-cut ditches, and mining of 58,769 linear feet of natural and modified natural streams. An additional 1,661 linear feet of stream channel will be disturbed but not mined for six temporary crossings for dragline/utility/ pipeline corridors. To mitigate for impacts to streams and wetlands under the ERP rules, Mosaic will create 641 acres of wetlands and other surface waters and 67,397 feet of stream channel and will also provide a conservation easement to the Department on 2,100 acres of unmined wetland and upland habitat associated with the major riparian systems. The conservation easement area will be permanently preserved and protected from secondary impacts. The UMAM rule is applied to ERP applications to measure the functional loss to wetlands and other surface waters proposed for impact and the functional gain associated with the proposed mitigation. Functional loss is compared to functional gain to determine whether sufficient mitigation has been offered that offsets the proposed impacts. The proposed preservation and wetland and surface water creation, along with certain upland enhancements, will provide more than enough UMAM mitigation "lift" (with 48 excess credits) to satisfy the ERP mitigation obligations and offset those wetland impacts that cannot be eliminated or reduced. The UMAM scores for the reclaimed areas are conservative, that is, using higher risk factors by assuming muck or other appropriate topsoil will not be available, and take into account the risk or difficulty associated with creation of a particular system, based on actual UMAM scores for existing reclaimed systems. Time lag, which is normally a factor considered in the UMAM mitigation equation, expressly does not apply to phosphate mines pursuant to Florida Administrative Code Rule 62-345.600. Thus, Lee County's attempt to argue that some greater amount of mitigation of streams is required to account for the time required to construct and reinstate flow and vegetation to the streams is not credited. Mr. Cantrell confirmed that "fat" was built into the foot-for-foot stream reclamation because 7,000 more feet of stream will be reclaimed beyond the amount impacted; some "stream" segments, specifically, stream segment 18(i), probably should not have been required to be reclaimed at all. Under Florida Administrative Code Rule 62C-16.0051, the 511 and 512 classified "natural" streams are the only streams warranting reclamation as streams under the Department's reclamation rules. Only natural streams currently existing immediately prior to mining are required to be reclaimed on a linear foot basis. Reclamation meeting the requirements of Florida Administrative Code Rule 62C-16.0051 is adequate mitigation under the ERP program in Part IV, Chapter 373, Florida Statutes, if it maintains or improves the functions of the biological systems currently existing onsite. See § 373.414(6)(b), Fla. Stat. Mr. Cantrell established that, under subsection (5) of the rule, the Department has discretion to request the applicant to restore wetlands and streams to a different type of system than existing on the site if "mitigating factors indicate that restoration of previously modified streams as a different type of lotic system would produce better results for the biological system and water quality." The evidence established that the rules do not require reclamation of artificially created water courses or remnant stream segments that lack the functions or landscape position one normally associates with natural streams. Instead, a better lotic system will be created that will improve existing functions and water quality, consistent with Section 373.414(6)(b), Florida Statutes, and the CRP rules. In addition to the wetlands and surface waters created to meet mitigation requirements, the Project will also reclaim uplands and will include what is known as "land and lakes" reclamation in the southeastern portion of the site. Utilizing shaped and contoured overburden, Mosaic will create four lakes totaling 180 acres and 43 acres of associated herbaceous littoral zone as CRP reclamation. This is based predominantly on the mine-wide materials balance showing a need for reclaimed lakes to account for mine voids on the Hardee site, the Polk site, or both. As a result, Mosaic has proposed 180 acres of reclaimed lakes in Hardee County in lieu of 500 acres of reclaimed lakes in Polk County, as this results in eliminating overall reclaimed lake acreage while satisfying Hardee County's request for deep lakes. In addition, timing and property logistics in that portion of the site make transport of tailings to the area from the beneficiation plant problematic. As the site is an extension of the existing South Fort Meade Mine in Polk County, Mosaic possesses permits that are not at issue in this proceeding, but are relevant to the project. Discharges from a mine recirculation system require a National Pollutant Discharge Elimination System (NPDES) permit. Discharges may only occur at specified discharge points upon verification that the discharge meets stringent water quality conditions in the permit, which are set to ensure that water quality standards in the receiving water are met at the point of discharge (without mixing) and that downstream water quality will be protected. A separate NPDES permit is not needed for the Project, because Mosaic already has a valid NPDES permit for the Polk County beneficiation facility, which will serve the site. Mosaic currently has a Water Use Industrial Permit (WUP) issued by the Southwest Florida Water Management District (SWFWMD). The WUP includes both the Polk County and Hardee County portions of the South Fort Meade mine and governs both dewatering of the mine area prior to mining and operation of water supply wells located in Polk County that will be used to provide supplemental water to the recirculation system. Mosaic's evidence demonstrated that the Project will not cause adverse water quantity impacts, consistent with Florida Administrative Code Rules 40D-4.301(1)(a), 40D-4.302(1), and 62C-16.0051 and related BOR provisions. Mosaic presented evidence concerning the potential long term impacts of the proposed project on surface and ground water quantities and flows both during active mining and reclamation activities, and after reclamation is complete. Extensive analyses were presented by Mosaic's expert witnesses and evaluated by the Department. Such analyses showed no adverse impacts to water quantity on the site, adjacent properties, or in the Peace River or Charlotte Harbor. The site was studied extensively by Mosaic, and detailed hydrology characteristics were assessed as part of the preparation of the ERP and CRP applications. Various surface water stations, topographic maps, and ground water sampling points were utilized and geologic information was developed by evaluation of various borings across the site. Mosaic witness Burleson, a professional engineer, further considered soil types, land use and vegetative cover, and existing site hydrologic factors such as culverts, bridges, and other such changes to the site by the prior owners. Mosaic's modeling expert, Dr. Mark Ross, considered these factors on a regional scale in his integrated modeling for the 360 square mile regional basin. In the region of Florida that encompasses the site, there are three major hydrogeologic layers that are significant to a hydrologic analysis: (1) the surficial aquifer system, comprised of the overburden (the top layer of soil) and the phosphate matrix; (2) the confining layer and intermediate aquifer system; and (3) the Floridan, or deep, aquifer system. The confining layer separates the surficial from the intermediate and Floridan aquifer systems. By understanding the surface and ground water systems and physical characteristics of the site, the Mosaic experts were able to apply appropriately-calibrated hydrologic models to assess (1) pre-mining and post-reclamation floodplains and storm event runoff comparisons; (2) base flows to reclaimed streams; (3) potential hydrologic impacts of stream crossings; (4) effectiveness of the perimeter "recharge ditches"; (5) hydroperiod of reclaimed wetlands; and (6) potential impacts of the project on flows in the Peace River. These models were used to predict with reasonable certainty the effect of the Project on water quantity on-site, off-site, and on a regional scale. As set forth below, the evidence established that water quantity and flows in adjacent unmined wetlands and streams will be maintained during mining activities as a result of the installation of the ditch and berm system as proposed. Before the ditch and berm system is constructed, Mosaic will refine the design of the system based on actual geological data and gradient information to assure the ditch and berm will function as proposed and modeled. The ditch and berm system is inspected regularly. Recharge wells within the recharge ditch are not required unless localized conditions dictate use of the wells. Contrary to Lee County's assertions, this site is distinguishable from the Ona mine site (which is also in Hardee County), and the depth of mining is far more shallow with relatively few areas mined to a depth of fifty feet, which was common at the Ona mine site. Additionally, Mosaic must install perimeter monitor wells at regular intervals adjacent to and downgradient of the ditch and berm system prior to mining. These wells are monitored prior to mining to establish a baseline and regularly throughout mining in accordance with the requirements of Mosaic's WUP and the ERP to assure that the water table in adjacent areas is not adversely affected by mining activities. The water in the ditch portion of the perimeter system must be maintained at levels sufficient to maintain groundwater levels in undisturbed areas. Maintaining water in the ditch at appropriate levels precludes drainage of groundwater from adjacent sites into open mine cuts. Mosaic witness Pekas, a professional engineer, conducted modeling to determine whether adequate base flow will be provided to protected streams and reclaimed streams during mining. Provided the ditch and berm system is operated properly, proper base flows will be maintained. All of the hydrologic experts agreed that proper operation of a ditch and berm system assures that adequate groundwater outflow, or base flow, is available to support adjacent streams and wetlands during mining. During active mining operations, the ditch and berm system collects rainfall on areas within the system. The ditch and berm system temporarily detains this rainfall, preventing the direct discharge of untreated, turbid runoff to adjacent wetlands and waters, but does not permanently retain the rainfall. The evidence demonstrated that most of the rainfall that falls on areas disturbed by mining and mining-related activities is detained by the perimeter ditches, routed to the mine recirculation system, and is subsequently discharged, when it meets water quality standards, through NPDES-permitted outfalls to waters of the state. This will serve to attenuate surface water flows, allowing surface water retained during storm events to be discharged during extreme low flow events, providing for less "flashiness" in the streams. Lee County's assertion that runoff will be permanently retained is not credited; the evidence clearly established that controlled releases of treated stormwater occur through the permitted NPDES outfalls. The evidence shows that Mosaic will re-connect mined and reclaimed areas at the mine in Polk County at a rate exceeding the rate at which the Project's mine areas will be diverted by the ditch and berm system. Thus, any potential downstream impact of the ditch and berm construction on the site will be offset and buffered beyond the safeguards incorporated in the project design. The evidence demonstrated that the proposed ditch and berm recharge and monitoring system described here is capable, based upon generally accepted engineering principles, of being effectively performed and functioning as proposed and will preclude any adverse impact on the surficial aquifer beneath the preserved areas and adjacent properties and on adjacent surface waters and wetlands. The Department will apply the relevant BOR criteria concerning water quantity impacts on a pre-mining/post- reclamation basis consistent with the application of these same criteria to other non-mining ERP applicants. In this case, the Department reviewed Mosaic's submittals, assessed the impacts, and determined no adverse impacts to water quantity would occur during mining. Mosaic submitted a detailed analysis of potential surface water quantity impacts that may occur after reclamation is complete. This analysis included evaluation of post- reclamation floodplains and storm event run-off compared to pre- mining patterns, and characteristics of reclaimed natural systems. Floodplains, run-off, and reclaimed natural systems were assessed in the manner described below. Mosaic modeled potential impacts of the project on surface water flow using existing site conditions to calibrate and verify the model. Mr. Pekas developed a water balance hydroperiod spreadsheet model calibrated using existing, on-site wetlands to evaluate the expected hydroperiods of various types of wetland systems proposed to be reclaimed at the site. The evidence shows that the Pekas spreadsheet model was an appropriate model for predicting hydroperiods for reclaimed wetlands. Appropriate ranges for the expected hydroperiods and other hydrological characteristics needed for the different types of wetland systems to be created in the post-reclamation landscape were established. In order to reflect natural conditions, the Department specifically requested that the targets for expected hydroperiods of reclaimed wetlands vary across the established range of the hydroperiod for the type of wetland at issue, and these target hydroperiods are summarized in Table E-6 to the draft ERP. Mosaic demonstrated and verified that the Pekas spreadsheet reasonably predicts the hydroperiods to be expected from a given design for a proposed reclaimed wetland. After mining, site-specific conditions such as hydraulic conductivity will be reassessed and final design parameters will be developed accordingly. Lee County's witness Jonas demonstrated the importance of hydraulic conductivity when she adjusted the value for wetland 2-1C (one of Mr. Pekas' verification wetlands) from 0.5 to 30, based on a value not from the Project site, but from an off-site reclamation project. Not surprisingly, she concluded that a conductivity of 30 would not provide hydrology to support the wetland functionality. Her analysis demonstrates the importance of requiring reclamation of subsurface hydrology not based on an off-property conductivity value, but on site- specific hydraulic conductivity information. In his own analysis, Mr. Pekas relied on actual soil borings on-site, and at wetland 2-1C the average hydraulic conductivity was 0.5, which when modeled, provided appropriate hydrology for that wetland. Furthermore, ERP Specific Condition 11 requires Mosaic to reclaim wetlands with functionally equivalent hydraulic conditions based on verified field information as to site- specific hydrologic properties existing after mining, and the wetlands will not be released until functioning as required. The preponderance of the evidence demonstrates that reclaimed wetland can be designed and built in a manner that will achieve the required hydroperiods for each wetland type proposed to be disturbed and reclaimed at the site, including the bay swamps. In addition, each of the wetlands must be individually evaluated immediately prior to construction to provide additional verification of site-specific hydrologic conditions to assess, re-model, and verify the final wetland designs prior to construction. Condition 11c of the draft ERP also requires Mosaic to mimic the existing hydraulic conductivity and gradients near streams to ensure that base flows will be present post-reclamation. All of this will ensure that reclaimed streams will be hydrologically supported, and wetlands with the target hydroperiods requested by the Department will be constructed. The contrary testimony of Lee County's hydrologists does not credibly rebut this evidence. In performing their calculations, they utilized unrealistic numbers. The claim of Lee and Sarasota Counties' experts that they lacked sufficient information to form an opinion as to the accuracy of the modeling is not sufficient to overcome the evidence submitted by Mosaic to meet this criterion. See, e.g., National Audubon Society, et al. v. South Florida Water Management District, et al., DOAH Case No. 06-4157, 2007 Fla. ENV LEXIS 164 at *21 (DOAH July 24, 2007, SFWMD Sept. 13, 2007). Mr. Burleson determined that the original drainage patterns of the site would be restored post-reclamation. Mosaic provided reasonable assurances that the proposed reclamation is capable of being constructed and functioning as proposed. The preponderance of the evidence demonstrated that the proposed mining and reclamation of the site will not cause adverse water quantity impacts post-reclamation, as addressed by Florida Administrative Code Rules 40D-4.301(1)(a) and (c), associated BOR provisions, and Florida Administrative Code Rule 62C-16.0051(8)(b). Mosaic presented evidence demonstrating reasonable assurances that the proposed project will not cause adverse flooding to on-site or off-site property, consistent with Florida Administrative Code Rules 40D-4.301(1)(b) and 62C- 16.0051(8) and associated BOR provisions. During mining, there is no reasonable likelihood that active mining and reclamation activities at the site will result in any increased flooding conditions upstream of, on, or downstream of the site. The ditch and berm system reduces direct surface water runoff from areas disturbed by mining operations during peak rainfall events. Subsequent NPDES discharges of water typically lag slightly behind the rainfall events. This lag during mining decreases peak discharges in adjacent streams while augmenting lower flows slightly, thereby attenuating peak flows. Mr. Burleson evaluated the pre-mining and post- reclamation peak flow analyses for the project site to determine whether the post-reclamation topography, soils, and vegetative cover would result in flooding, using the Interconnected Pond Routing program or "ICPR" model, an accepted model for stormwater modeling, as required by the BOR. Mosaic's evidence established that the Project will not adversely impact existing surface water storage and conveyance capabilities, consistent with Florida Administrative Code Rule 40D-4.301(1)(c) and related BOR provisions. Additionally, Mosaic proposes to preserve from mining the 100-year flood plain of Little Charlie Creek and the Peace River and most of the higher quality small tributaries on the site. The smaller streams to be mined will be restored in a way that maintains or improves pre-mining conditions and will not cause harmful or erosional flows or shoaling. The federal Hydrologic Engineering Center Reservoir Analysis System and the National Flood Frequency Program were used by Mr. Burleson to verify the floodplains are accurately mapped and also that there will not be an increase in flood risk in the post-reclamation condition. The preponderance of the evidence demonstrates reasonable assurances that the proposed mining and reclamation activities at the site will not result in adverse flooding impacts, consistent with Florida Administrative Code Rules 40D- 4.301, 40D-4.302(1)(a)3., and 62C-16.0051(8), and the BOR, including water quality standards in Chapter 4. The evidence presented by Dr. Ross established that the proposed mining and reclamation activities on the site will not adversely impact flows in the Peace River. No adverse effects of the Project will be observable at the Zolfo Springs United States Geological Survey (USGS) gauging station. A minimum flow for the Upper Peace River has been established pursuant to Section 372.042, Florida Statutes. A minimum low flow of 45 cfs from April to June (Upper Peace MFL) was established at Zolfo Springs by the SWFWMD; since the MFL has not been met since adoption, a recovery plan has been instituted. See Fla. Admin. Code R. 40D-8.041(7). Lee County asserts that the Project will violate the Upper Peace MFL and the recovery plan, arguing that a reduction in average annual flow, regardless of how infinitesimal, constitutes a violation of Florida Administrative Code Rule 40D-4.301(1)(g). This argument was refuted by Dr. Ross, who established that the project would increase flows during low flow periods. The Department concurred with, and the evidence supports, Dr. Ross' assessment that the project would not exacerbate the Upper Peace MFL or interfere with the recovery plan. Dr. Ross created a regional-scale integrated model utilizing public domain computer programs in an iterative fashion that coupled surface water and ground water to comprehensively evaluate the effects of the project on the flows in the Peace River post-reclamation. The regional approach included a full range of upstream and downstream influences on the site, not simply mining, that could affect the hydrologic evaluation of any impacts from the Project on the Peace River. The model domain included 360 square miles. To account for site-specific impacts in the model, Dr. Ross increased the refinement and discretization over the site. Thus, the model was capable of considering impacts from the site in its entirety within the region as measured at the Zolfo Springs USGS gauging station. Zolfo Springs is the first USGS gauging station directly downstream of the site and is the point of compliance for minimum flows adopted for the Upper Peace River system. The regional model predicted virtually no change in flows at the Zolfo Springs gauging station after the project as proposed is reclaimed, and that both the high and low flows observed at Zolfo Springs would be maintained post-reclamation. Dr. Ross concluded that there would not be any reduction of low flows at Zolfo Springs due to the Project. He further concluded that the Project will not impact or affect the recovery of minimum flows. Dr. Ross calculated the differences between the model- predicted high flows and low flows from the observed flows and found that the modeled high flows were slightly attenuated and the modeled low flows were slightly augmented at Zolfo Springs. The attenuation is consistent with the increased storage for water in the post-reclamation system. Consistent with Florida Administrative Code Rule Chapter 40D-8, the Department considered potential impacts to low flows as the determining factor in determining whether a minimum low flow requirement like the one set for the Upper Peace MFL will be met. It concluded that the project is consistent with the Upper Peace MFL and its recovery strategy. The recovery strategy discusses projects which, like the one proposed, would yield a long-term increase in low flow conditions by storing some peak flow volumes and releasing them in low flow conditions. The Department's interpretation of its ERP rules and BOR provisions regarding MFLs, as well as other governing rules, is reasonable and has been accepted. Lee County's experts based their MFL testimony on an inappropriate use of annual average flow information and improper interpretation of Mosaic's data. Further, they inappropriately attempted to reach conclusions by estimates and extrapolation, and the overall weight of the evidence supports Mosaic's evidence that mining and reclamation will not cause a violation of the Upper Peace MFL. Accordingly, Mosaic has provided reasonable assurances that the requirements of Florida Administrative Code Rule 40D- 4.301(1)(g) and associated BOR provisions have been satisfied. The ditch and berm system and other proposed BMPs, such as silt fences, at the site will provide water quality protection to adjacent undisturbed surface waters and wetlands during mining and reclamation activities. The actual construction of the ditch and berm and stream crossings will be conducted using BMPs to avoid adverse construction-related impacts. During mining, the ditch and berm system will preclude uncontrolled releases of turbid water to adjacent un-mined areas. The evidence established that the proposed Project will not cause a violation of water quality standards, either in the short-term or long-term. Dr. Durbin, an ecologist, evaluated water quality data from the existing South Fort Meade mine in Polk County and compared data from the 10-year period before the mine opened against the 10-year period after the mining began, finding water quality to be equivalent or better after mining began in Polk County. This allowed him to conclude that water quality on the site will not be adversely affected and, in light of existing agricultural activities, will be maintained or improved both during mining and post-reclamation; water quality in reclaimed systems will be sufficient to maintain designated uses of the systems. Dr. Durbin opined that the ERP contains detailed water quality monitoring requirements that, based on his long experience, are sufficient to establish a baseline, assess compliance, and detect significant trends. Sarasota County's witness has no experience in ERP or CRP permitting and his suggestion for far more frequent monitoring is not credited. No additional monitoring conditions or criteria are warranted. For the above reasons, Mosaic has demonstrated by a preponderance of the evidence that reasonable assurances that water quality standards will not be violated either during mining, while reclamation is underway, or post-reclamation. The evidence further established that accepted BMPs will be used during mining to protect the water quality of adjacent and downstream waters, and that these measures can be expected to be effective to prevent any violations of water quality standards. Dr. Durbin provided unrebutted evidence that water quality standards in waters of the state and downstream of the project will be met post-reclamation and existing water quality in the unmined and reclaimed wetlands and waters will be maintained or improved post-reclamation. Thus, no adverse water quality impacts to the Peace River or Charlotte Harbor will occur during mining or post-reclamation. Therefore, reasonable assurances have been given that the requirements of Sections 373.414(1) and 373.414(6)(b), Florida Statutes, Florida Administrative Code Rules 40D- 4.301(1)(e) and 62C-16.0051(7), and associated BOR provisions are satisfied as to water quality. There is a wide range of habitat types on the site that will be preserved and not mined, including both streams and wetlands. The most complex and least impacted habitats on the site have generally been included in the no-mine and preserved areas. Mosaic does not propose to mine all or even most of the jurisdictional wetland and surface waters. In fact, seventy-one percent will be avoided. When developing a mining plan, Mosaic considers how to eliminate or reduce proposed impacts to waters and wetlands. The evidence established that Mosaic and the Department engaged in a protracted elimination and reduction discussion throughout the review process associated with the site's ERP/CRP applications. BOR Section 3.2.1 emphasizes the effort required to assess project design modifications that may be warranted to eliminate and reduce impacts to ecological resources found on the site. This effort was undertaken with the Department as early as 2004 during the DRI pre-application conferences. The major project design modifications involved the preservation of the named stream channels, the 100-year floodplain of the Peace River and Little Charlie Creek, and the 25-year floodplain of the other named tributaries. These areas will be permanently preserved by a 2,100-acre conservation easement; 1,000 additional acres will remain unmined. Also, the project design was modified and developed to maximize resource protection by integrating the Polk and Hardee mining operations. The testimony established how the activities at the Hardee operation will be greatly facilitated by relying upon and using the beneficiation plant and infrastructure already in place and permitted at the Polk site. Almost fifty percent of the clays generated at the Hardee mine will be disposed of in the existing Polk County CSAs, thereby eliminating one CSA altogether and substantially reducing the footprint needed for CSAs on the site. Likewise, the Department established that mine-wide, approximately 320 acres of lakes were eliminated. The Department discussed further modifications to the mine plan with Mosaic throughout the lengthy review process, doing a wetland and stream-by-stream assessment of the functions provided and the reclamation capability to maintain or improve the functions of the biological systems present prior to mining. The balance was struck between temporary resource extraction, recognized by Florida law as inextricably related to wetland disturbance, and the significantly altered natural resource features found on the site. In light of the 3,100 acres already eliminated and reduced from impact consideration, the Department in its discretion did not find it necessary to pursue economic data or analysis on the "practicability" of any further reductions. The highly disturbed nature of the wetlands and other surface waters being impacted gave the Department a high degree of confidence that mitigation and reclamation of these areas would in fact maintain and improve the functions provided prior to mining. Specifically, Mosaic has eliminated impacts to stream systems to the greatest extent practicable. Based on a Department field evaluation in late August 2008, Mosaic was directed to revise the no-mine line in the 3A stream system to more accurately reflect the floodplain of the stream draining the two bay heads north of the stream. In October 2008, Mosaic made the revision to add approximately 2.7 acres to the no-mine area. The majority of the streams proposed for impact by mining cannot be avoided, given the location of the three CSAs that are required for clay disposal associated with mining. The evidence established that there is no other location for the three CSAs that will have a lesser ecological or public health, safety, or welfare impact than the proposed location, given the site topography. As noted above, the volume of clays to be disposed of on the site has been reduced by half, and three CSAs are still needed. The location was chosen to move the CSAs as far from the Peace River and Little Charlie Creek as possible in light of the site topography, and this location avoids all impacts to named stream systems. As set forth above, Mosaic has demonstrated by a preponderance of the evidence that the best and most complex habitats on the site have been preserved at the expense of a loss of a significant amount of phosphate reserves in the preserved areas. All significant stream systems have been avoided to the extent practicable in light of the necessary CSAs. Both Mosaic and Department witnesses testified that the proposed no-mine area was the result of design modifications to eliminate or reduce impacts to wetlands to the greatest extent practicable. This satisfies the requirements of applicable rules and Section 373.414(1)(b), Florida Statutes. Florida Administrative Code Rule 62C-16.0051(4) and (5) provides specific guidance on the classification and reclamation of natural streams. The Department provided direction to the applicant through the review process in the identification of natural streams and the design guidance manual to ensure foot-for-foot replacement and functional replacement or improvement. The permit reflects the 58,769 feet of the streams identified as numbers 511 and 512 to be impacted, and Mosaic has proposed approximately 65,700 feet of restored stream. Lee County's assertion that 2.3 miles of additional unmapped streams should be added to the reclamation obligation has been rejected. It is clear many of the areas alleged to be unmapped streams were depressions, low lying areas, or standing water within wetland areas more accurately identified as marshes or swamps. The fact that a discernible natural stream channel exists upstream and downstream of a wetland did not change the accuracy of acknowledging the different structure, form, and functional attributes that result in the wetland being distinct from the stream. Also, many of the alleged unmapped streams were located in the no-mine areas, and thus the alleged lack of delineation is of no consequence. Lee County's witness Erwin admittedly took no measurements of the alleged streams. Also, he provided no evidence that he or his staff delineated the alleged streams on- site. Rather, he reconstructed where they were located as a desktop exercise from memory, without any aids or tools used in the field. He then superimposed an alignment and put it on a GIS layer over an aerial photograph, resulting in an electronically generated approximation. The witness offered no physical evidence of depth, width, length, or bankfull width of stream function, but merely an assertion as to areas that appeared to have a bed or channel, even if dry, and the attributes or functions of a stream were immaterial or irrelevant to his analysis. No other independent witness attested to the alleged stream discrepancy, whereas both Mosaic's expert, Mr. Kiefer, a recognized fluvial geomorphologist, and the state's expert on jurisdictional delineations, Mr. Cantrell, who was the author of the applicable rules, expressly disagreed with these allegations. The testimony of Mosaic and the Department is found to be the most persuasive on this issue. Mosaic and the Department established that the proposed stream restoration plan is more than adequate to meet the requirements of Florida Administrative Code Rule 62C- 16.0051(5) and will ensure the reclaimed streams maintain or improve the biological function of the streams to be impacted. Dr. Janicki, a scientist who testified on behalf of Lee County, was critical of the stream restoration plan. However, he acknowledged he was not an expert in stream restoration and that part of his job was to "look at how we might improve . . . on some of those shortcomings in the [stream] restoration plan." Dr. Janicki incorrectly assumed the design curve numbers were based on regional curves from north and northwest Florida rather than site-specific measurements. He stated that the guidance document was generalized and lacking specificity, but Table 4 contained in the guidance document contains nineteen stream morphological parameters for all forty- nine of the stream segments to be reclaimed. Dr. Janicki has never designed nor implemented a stream restoration project, and he acknowledged that he is not a fluvial geomorphologist. Conversely, Mosaic witnesses Boote and Kiefer, both accepted in this area, stated unequivocally that the plan was sufficiently detailed and that a qualified restoration and construction contractor could implement the plan in the field with appropriate field adjustments and construction level refinements based on site conditions. The allegation that the plan does not comport with ERP and CRP requirements because it lacks sufficient specificity is not credited. First, the ERP rules do not contain stream-specific restoration criteria. Second, the CRP stream rules adopted in May 2006 have never been applied in a prior case, and in this case the Department determined in its discretion that the plan as proposed meets the stream reclamation requirements of the CRP rules. Similarly, the stream restoration plan was criticized because measurements from every single segment or reach of stream were not used to develop the post-mining stream. However, Mr. Boote and Mr. Kiefer confirmed that only the most stable and least impacted of the stream segments on site were used as templates for stream reclamation. None of the recognized stream experts suggested that erosive, unstable "F" and "G" classified stream segments should be replaced in that unstable form or used as the template for reclamation. By a preponderance of the evidence, Mosaic has established that the reclamation plan for the site will more than offset any adverse impacts to wetlands resulting from the mining activities, because it will maintain or improve water quality and the functions of biological systems present on the site today, as required by Sections 373.414(1) and 373.414(6)(b), Florida Statutes. The evidence established that applicable Class III water quality standards will not be violated and that the water in wetlands and surface waters on-site post-reclamation will maintain or improve and be sufficient to support fish and wildlife in accordance with Florida Administrative Code Rules 62C-16.0051 and 40D-4.301(1)(e) and relevant BOR provisions. The proposed mitigation will also restore a more appropriate or more natural hydrologic regime that will allow for a better propagation of fish and invertebrates in reclaimed systems. The reclamation plan will maintain the function of biological systems of wetlands to be mined on-site by replacing the wetlands to be impacted with wetlands of the same type and similar topography and hydrology in the post-reclamation landscape. In many cases, it will enhance the function of those systems by improving the landscape position of the wetlands, relocating them closer to the preserved Little Charlie Creek corridor, and moving cattle ponds and pasture away from the corridor. Likewise, the existing streams proposed for mining will be replaced with stream reaches modeled on streams that are comparable or better than the existing, unstable, and eroded streams. The Department has determined that Mosaic can reclaim the streams and wetlands to at least as good as or better than existing condition on the site. Mosaic has provided reasonable assurances that the proposed reclamation plan will maintain or improve the existing function of biological systems. Mosaic's reclamation plan for the site therefore satisfies the mitigation requirements of Part IV, Chapter 373, Florida Statutes, and the implementing regulations and the BOR, as applied to phosphate mining activities through Section 373.414(6)(b), Florida Statutes. Through the testimony of witnesses Durbin, Kiefer, and Simpson, as well as documentary evidence, Mosaic has established that the proposed project, as reclaimed, will cause no adverse impacts on the value of functions provided to fish and wildlife and will not adversely affect the conservation of fish and wildlife, including endangered or threatened species and their habitats, as required by Section 373.414(1)(a)2., Florida Statutes, Florida Administrative Code Rules 40D- 4.301(1)(d) and 40D-4.301(1)(a)2., as well as the associated BOR Section 3.2.2 provisions. Likewise, the CRP criteria pertaining to fish and wildlife will be met. See Fla. Admin. Code R. 62C- 16.0051(11). Mosaic's reclamation and site habitat management plan will maintain or improve the functions of the biological systems on the site with respect to fish and wildlife, including threatened and endangered species and their habitat. Mosaic witness Simpson provided unrebutted testimony that the proposed mining and reclamation will not have adverse impacts on wildlife populations or conservation of wildlife including threatened or endangered species and their habitats and that proposed reclamation would maintain or improve wildlife habitat values. The evidence shows that the mining and reclamation will not have adverse impacts on fish populations or conservation of fish. The fish habitat on the site will either be preserved or, if mined, will be replaced with in many cases superior habitat. There will be a net increase in suitable fish habitat post-reclamation. The wetland and stream fish habitats on the site will provide appropriate habitat for the fish and wildlife that can be expected to occur in the region. The sampling described above can be expected to reflect the majority, if not all, of the fish species reasonably expected to be present on the site. Mosaic witness Durbin further confirmed that the fish species collected on-site are consistent with similar sites in the immediate vicinity with similar agricultural usage with which he is familiar. In August and September 2008, verification of that fish sampling effort was performed by Dr. Durbin, an outside consulting firm (ECT), and the Department. They confirmed that the fish collection efforts reasonably reflect the native and exotic fish species that are likely to occupy the site. Through the testimony of Dr. Fraser, Lee County compared two streams on the Ona mine site with three stream segments on the Project site. However, the sole basis of the witness' comparison was recollections of field work he participated in over four years ago and photos taken at that time compared with photos taken at the new site. The witness conceded that he did not consider or compare sedimentation levels in the two stream systems. On the other hand, Department witness Cantrell established that the streams compared by Dr. Fraser were dissimilar. In fact, one of the streams Dr. Fraser held up as an apparent example of prime aquatic habitat was Stream 20C, which Mr. Cantrell demonstrated is nearly completely choked by sand and sedimentation. All of the streams proposed for impact are first or second order streams; most of them are intermittent, carrying flow only seasonally and therefore are only periodically occupied by fish and macroinvertebrate communities. The fish that do tend to utilize such systems in the wet season tend to be very small, usually less than one inch in size. The proposed preservation will preserve the best aquatic habitat on the property; the streams to be preserved are the main pathways and aquatic habitats utilized by fish. Mosaic witnesses Durbin, Keenan, and Kiefer all testified that the reclamation plan will restore better aquatic habitat for fish and other aquatic organisms than exists presently on site on a greater than acre- for-acre, type-for-type and linear foot basis. They further testified that the proposed reclamation will provide better aquatic habitat for fish and wildlife than currently provided, consistent with both ERP and CRP requirements. In addition, Dr. Fraser's suggestion that the fish sampling done on the site was insufficient and that the ERP should be modified to require fish collection as a success criterion for the reclaimed streams is not credited. This is because such a proposal is not a requirement of the ERP or CRP rules. Dr. Fraser's comparisons of reclaimed to unmined streams were inconsistent with his own anecdotal fish observations, and he testified as to the difficulty of ensuring adequate fish sampling or knowing where fish will be on any given day, given their mobility. Also, he provided no comparisons as to how the reclaimed streams sampled are constructed compared to the plan for the site and admitted he did not know how or when they were built. Dr. Fraser's discussion of fish in basins where mining has occurred was discredited by his own data showing that no reduction in the number of native fish species has occurred over time in those basins. Mosaic's reclamation plan, which consolidates the native upland and wetland habitats along the Little Charlie Creek corridor, will improve the fish and wildlife function of those systems and increase fish and wildlife abundance and diversity, as set forth above. There will be no adverse impacts to fish and wildlife and their habitat or to the conservation of fish and wildlife, including listed species, post-reclamation, because the fish and wildlife function of the tract will be maintained and in many cases improved by the reclamation and habitat management plans. This is particularly true in light of the existing condition, hydrologic connection, location, and fish and wildlife utilization of the wetlands and surface waters on site. Therefore, Mosaic has provided reasonable assurances that the requirements of Section 373.414(1)(a)2., Florida Statutes, Florida Administrative Code Rules 40D-4.301(1)(d) and 40D- 4.302(1)(a)2., and the relevant BOR provisions have been satisfied. Mosaic demonstrated that it has reclaimed wetlands, uplands, and streams consistent with the regulatory requirements and permit conditions in place at the time the area was reclaimed. Indeed, many of these reclaimed areas, whether or not under different ownership and control or whether released from further regulatory requirements, continue to demonstrate that they are successful and functioning ecosystems. The reclamation proposed for the site is state-of- the-art, reflecting the most recent evolution of reclamation techniques for uplands, wetlands and streams, with more planning and detail that should achieve the reclamation goals faster. Many older wetland projects were designed to meet a +/- 1-foot contour and were designed with older generations of equipment and survey techniques. However, Mosaic's third party contractor's bulldozers/tractors are now equipped with GPS and sensors to enable grade tolerances within two inches, allowing for much more accurate backfilling and wetland construction. Accordingly, Mosaic's newer wetlands contain both deep and shallow areas with gradation/zonation in between. Hydrologic regimes and hydroperiods can thus be effectively created to target and achieve more specific hydrologic conditions required by certain wetland systems such as seepage slopes and wet prairies. Nonetheless, the projected UMAM scores for the reclaimed systems take into account a higher risk factor for systems that historically were more difficult to reclaim. Mosaic has provided reasonable assurances of its ability to restore the hydrology and types of vegetation found on the site and of its ability to create ecosystems that will maintain or improve the function of the biological systems proposed for mining on the site. Mosaic has restored wetlands in a variety of configurations ranging from small round depressions of less than a few acres to large complex polygons in excess of two hundred acres, as well as wetlands with low slope gradients. For example, Mr. Kiefer described and depicted Mosaic's ability to restore a bay swamp at point 84(5) at the Fort Green Mine and at Alderman Bay. Lee and Sarasota Counties focused on bay swamps in particular, but failed to acknowledge that Mosaic will be reclaiming 98.5 acres of bay swamps while only impacting 62.1 acres. Mosaic demonstrated that herbaceous and forested wetlands can be and have been restored by Mosaic and its predecessors. Mosaic has demonstrated that it can restore the various zones and depths of freshwater marshes, including shrub marshes, from the deep emergent zone to the wet prairie fringe, and has demonstrated that these zones in reclaimed marshes are providing important and key wetland functions, such as water quality, food chain support, habitat, and other functions, similar to those functions provided by site marshes. This evidence was not effectively rebutted by Lee or Sarasota Counties. In fact, Sarasota County witness Lipstein acknowledged Mosaic is proposing to mitigate for all impacts. When asked if the proposed bay swamps will be successful or unsuccessful, she replied that she did not know and, "you will have to just wait and see if it reaches that success criteria." There have been different success criteria applied in Department permits over the years, and Mosaic has demonstrated the ability to meet those changing and more stringent criteria. In the past, stream restoration was accomplished relatively simply by contouring the stream valley and floodplain to support wetland vegetation, then allowing a flow channel to self-organize. While this technique has resulted in successful streams that met Department permit criteria, it can take many years to occur. For example, Dogleg Branch (which is located on the site of another mining operation) took almost twenty years to achieve success. Mosaic has previously developed successful stream restoration projects which have been documented to provide flow regimes similar to that of natural flatwoods streams, with in- stream aquatic habitat diversity similar to or better than the stream segments proposed for mining at the site and which met reclamation criteria. Mosaic witness Kiefer demonstrated this with evidence of the functions that various reclaimed streams provided. He also showed that, in newer stream restoration projects, like Maron Run, certain functions and form, such as habitat availability, bank stability, meander, and pool-riffle sequence, are developing rapidly. Also, Department witness Rivera testified to Mosaic's commitment to achieving stream success in its efforts to retrofit certain of these earlier reclaimed streams to achieve greater function and habitat diversity. Using an average sinuosity of 1.35, over 65,700 linear feet of streams will be created as part of the mitigation plan. The foot-for-foot requirement for the reclaimed streams will be exceeded by 7,000 feet. Mosaic's mitigation proposal incorporates state-of- the-art stream restoration techniques and the post-reclamation topography to be used as guidance for the final construction plans. The guidance is based on extensive data collected from twenty-one cross sections of reference reaches within the project area, including measurements for channel dimensions, sinuosity, bankfull, and entrenchment ratios. Snags, debris, and other woody material will be placed at appropriate intervals within the channel to provide in-stream habitat and aid in-channel stabilization and development. Restored streams will have primarily forested riparian zones. Trees will be planted using techniques that will assist rapid canopy closure and aid in rapid bank stabilization. Biodegradable erosion control blankets will be used to control erosion. The streams will be designed such that the stream morphology fits within the Rosgen Stream Classification System (Rosgen) described in the reference reaches. To create a design template, Mosaic's experts carefully measured the important geomorphic characteristics of the stream segments to be disturbed. The plan incorporates, among other factors, design specifications for meander patterns, longitudinal valley and bed slopes, bank slopes, cross-sectional area, widths, depths, large woody debris, pools, riffles, bends, and sediment composition. It is the second known low-order stream creation plan in Florida to provide this level of detail. The stream plan represents an overall improvement upon the existing conditions at the site, as Mosaic is generally only mining small, shallow, intermittent stream segments of significantly lower ecological value and will create streams that are less erosive and will have greater in-stream habitat diversity and availability than the segments to be mined. Accordingly, the reclaimed streams segments will at least maintain and in many cases improve the ecological functions served by the existing segments. Special emphasis has been placed on assuring that post-reclamation soils are a suitable growing medium for the proposed reclaimed habitat. Soils will be used to closely mimic the native Florida soils profile. Mosaic witness Schuster established that proposed reclaimed soil conditions do not pose limitations on Mosaic's ability to create upland and wetland ecosystems. The soil reclamation plan uses parent materials available after mining in a sequence similar to the textural or horizon sequence in soils present at the site before mining. This soil profile will have a created topsoil layer as a suitable growing medium and subsurface layers whose thicknesses can be adjusted to achieve the drainage class, that is, hydraulic conductivity or permeability, that is needed to support the post-reclamation hydrology. The overburden used to form the lower part of the reclaimed soil sequence is native Florida soil and underlying geologic material. The overburden is excavated so that the matrix can be mined, but then the material is put back in the mined areas in a sequence that resembles native soil horizons. Where available, the top layer of the soil sequence will be a direct transfer of muck/topsoil pursuant to the permit conditions. Where donor topsoil is not available, other appropriate materials can be used if approved by the Department. Possible methods may include establishment of cover crops, green manuring, mulching, and sod placement, all of which have been demonstrated to provide organic matter and a suitable growing medium for reclaimed wetlands and will facilitate success of the wetlands. These methods comport with the requirements of Florida Administrative Code Rule 62C-16.0051(3). For reclamation, Mosaic will use various thicknesses of materials including sand tailings and overburden, depending on the area to be reclaimed and the needed hydraulic conductivity as dictated by the modeling that is required. Sand tailings will be utilized in native habitats. Sand tailings have a much higher rate of hydraulic conductivity than overburden, which is low, but not impermeable. Reclaimed soils behave similarly to native soils. On site development of soil morphology at reclaimed sites has occurred, including organic matter accumulation in the topsoil formation of redox concentrations, and other components of soil structure, which evidence that the same natural processes are present in both reclaimed and native soils. Lee County's witnesses incorrectly assumed an overburden cap that will not be present. Mosaic has provided appropriate cost estimates for financial assurances of reclamation and has satisfied the BOR requirements of providing third-party estimates and draft financial assurance documentation. The first three years of mitigation at one hundred ten percent is $3,957,356.00. This amount is determined to be sufficient. Lee and Sarasota Counties' witnesses could provide no contrary cost estimates of actual comparable large-scale projects. The proffered costs of Lee County witness Erwin were rejected in another mining case (the Ona case), they ignore the definitions of "waste" and "mining operations," and they assume mitigation requirements not found in the BOR. The evidence supports a finding that all adverse impacts, including any secondary impacts, associated with the Project will be temporary and will be offset by the proposed reclamation. All of the proposed impacts from the Project will occur within the Peace River Basin, and Mosaic's proposed mitigation will all occur within the Peace River Basin as well. Therefore, the cumulative impacts review requirements of Section 373.414(8)(a), Florida Statutes, and Florida Administrative Code Rule 40D-4.302(1)(b) are satisfied. The BMPs put into place will prevent adverse secondary impacts from occurring during mining, and no adverse secondary impacts are expected from the project post- reclamation. No secondary impacts to listed wildlife are reasonably expected to occur, based on the buffers and on the post-reclamation habitat that will exist. In summary, Mosaic has demonstrated by a preponderance of the evidence that the proposed project meets the permitting criteria of Florida Administrative Code Rule 40D-4.301 and associated BOR provisions. Florida Administrative Code Rule 40D-4.302(1)(a) requires reasonable assurances the proposed activities "will not be contrary to the public interest" as determined by balancing seven factors. See also § 373.414(1), Fla. Stat. For the reasons set forth below, the preponderance of evidence supports a finding that the public interest factors set forth in the statute and rule weigh in favor of issuing the permit. The Florida Legislature has recognized that phosphate mining "is important to the continued economic well-being of the state and to the needs of society." See § 378.202(1), Fla. Stat. Mosaic has demonstrated by a preponderance of evidence that both the public and the environment will benefit from the project as described above. Mining of the site will also result in a more general benefit to the public, including local residents. It is estimated that mining of the site will result in fifty million tons of recoverable phosphate rock reserves, which will be used to make fertilizer. Mosaic employs 272 people at its South Fort Meade facility and spends approximately $75,000.00 per employee per year for direct wages, benefits, and compensation. In addition, it has been estimated there are four to five persons employed in support industries for each direct Mosaic employee, considering contractors, vendors, and suppliers. The site project is expected to generate up to $23 million in severance taxes, tangible taxes, property taxes, and other benefits to Hardee County over the life of the mine. The evidence shows that the proposed activities will not cause adverse impacts to the public health, safety, or welfare or to the property of others. Fla. Admin. Code R. 40D- 302(1)(a)1. Witness Burleson established that the water quantity criteria in BOR Chapter 4 have been satisfied and that no flooding problems will occur. No environmental hazards or public health and safety issues have been identified. Section 373.414(1)(a)1., Florida Statutes, Florida Administrative Code Rule 40D-4.302(1)(a)1., and BOR Section 3.2.3.1 have accordingly been satisfied. The evidence established that the proposed mining and reclamation will not cause adverse impacts to the conservation of fish and wildlife or their habitat, including endangered or threatened species, satisfying Florida Administrative Code Rule 40D-4.302(1)(a)2. and BOR Sections 3.2.2, 3.2.2.3, and 3.2.3.2. The evidence shows that the proposed activities will not cause adverse impacts to navigation or flow and will not cause harmful erosion or shoaling. Fla. Admin. Code R. 40D- 4.302(1)(a)3. The evidence shows that the proposed activities will not cause adverse impacts to fishing or recreation or marine productivity, and the lakes will enhance fishing and recreation. Fla. Admin. Code R. 40D-4.302(1)(a)4. As a matter of law, Section 378.202(1), Florida Statutes, provides that phosphate mining is a temporary activity. Fla. Admin. Code R. 40D-4.302(1)(a)5. The parties have stipulated that there will be no adverse impacts on historical or archaeological resources. Fla. Admin. Code R. 40D-4.302(1)(a)6. The evidence shows that the current condition and relative value of functions of the site landscape have been significantly affected over time by agricultural activities, causing alteration of natural streams and wetlands and low fish and wildlife utilization. A preponderance of the evidence established that these negative impacts will be ameliorated by the proposed reclamation. Fla. Admin. Code R. 40D-4.302(1)(a)7. In light of the above, Mosaic has provided reasonable assurances that Section 373.414(1)(a), Florida Statutes, Florida Administrative Code Rule 40D-4.302(1)(a), and associated BOR requirements for the public interest test have been satisfied, and those criteria weigh in favor of issuing the permit. Section 373.414(6)(b), Florida Statutes, establishes the appropriate mitigation for wetland and surface water impacts associated with phosphate mines as follows: "Wetlands reclamation activities for phosphate and heavy minerals mining undertaken pursuant to chapter 378 shall be considered appropriate mitigation for this part if they maintain or improve the water quality and the function of the biological systems present at the site prior to the commencement of mining activities." Part III of Chapter 378, Florida Statutes, addresses phosphate land reclamation, and the Department has adopted specific regulations pursuant to this part, which are found in Florida Administrative Code Rule 62C-16.0051. For the reasons set forth below, Mosaic has demonstrated by a preponderance of the evidence that the reclamation and restoration standards in Florida Administrative Code Rule 62C-16.0051 have been met. The parties stipulated the Project will meet the safety standards in subsection (1) of the rule. Any temporary structures will be removed following mining and the area then reclaimed. Appropriate BMPs will also be installed. The Project will meet the backfilling and contouring requirements of subsection (2). Specifically, the evidence shows that the area will be backfilled and contoured to achieve the desired landforms; slopes will be no steeper than a 4:1 ratio; bank stabilization techniques will be used; and post- reclamation contouring and topography will help ensure that the reclamation plan and hydrologic response is successful. The reclamation will meet the requirement in subsection (3) that Mosaic use good quality topsoil when available and other suitable growing media to achieve the planned vegetative communities. The Project will meet the acre-for-acre requirement for wetlands because more acres of wetlands and surface waters are being proposed to be restored than will be impacted. The Department uses FLUCCS Category II to determine whether the minimum type-for-type requirement is met. Thus, the type-for-type requirement is met by looking at the forested wetlands acreage overall and the herbaceous wetlands acreage overall. Subsection (4) has been satisfied by the proposed CRP. While the herbaceous wetland fringe of the lakes is included in the acre-for-acre, type-for-type calculation, the open waters of the lake are not. The Project will meet the type-for-type requirement in the rule because, category-by- category, type-for-type, more than a 1:1 ratio of forested and herbaceous wetlands are being restored. As noted above, the wetlands and streams were mapped during the application process in accordance with the directives of the Department and the requirements of subsection (4). Where wetlands are directly associated with or adjacent to streams, restoration of both is integrated and included in the restoration plan. Non-wetland and wetland floodplains will be restored as directed by the Department in accordance with this rule. No natural lakes or ponds exist on site, thus the portion of this rule related to natural lakes does not apply. All natural streams proposed for impact will be restored foot-for-foot based on Rosgen Level II. More stream linear feet (65,700 feet) are being replaced than are being mined (58,769 feet). Therefore, the requirements of subsection (5) have been met. Subsection (6) has been satisfied after accounting for the Littoral Zone Variance described below authorized by Florida Administrative Code Rule 62C-16.0051(13). The design of the reclaimed wetlands and lakes will maximize beneficial drainage, provide fish and wildlife habitat, maintain downstream water quality, and incorporate a variety of vegetation and hydraulic zones. Greenbelts of vegetation are incorporated. Subsection (7) has been satisfied. There will be no water quality concerns either during mining or post-reclamation with the reclaimed streams, lakes, wetlands or other surface waters. Subsection (8) has been met; the Project is not expected to cause flooding, and the original drainage pattern will be restored to the extent possible. Subsection (9) has been satisfied with respect to waste disposal. Areas used for clay settling will be minimized, and only three CSAs are proposed for the site, as fifty percent of the clays generated at the site will be disposed of in previously-permitted CSAs in Polk County. Backfilling of mine cuts is the highest priority use for the site's sand tailings. No tailings will be sold. The evidence showed that sand tailings will not be permanently stored above natural grade, although temporary stock piles are authorized to facilitate reclamation. Reclamation of CSAs will occur as expeditiously as possible. Solid waste was not an issue in this proceeding. The revegetation proposed for the Project will succeed to achieve permanent revegetation and meets the requirements of subsection (10). Mosaic has submitted a plan for revegetation that lists species by species what will be replaced through planting or seeding into each of the different types of wetlands. The revegetation plan and planting tables provide clear guidance to the entire reclamation plan and will minimize erosion, conceal the effects of mining, and recognize the requirements for fish and wildlife habitat. Upland cover and forested upland requirements in the rule will be met under the CRP; the appropriate forested densities are set forth in the CRP and can reasonably be expected to be established within one year. Likewise, the wetland vegetative cover requirements in the CRP meet the rule requirements and can be easily met. As set forth above, the wetlands to be created are of the types Mosaic has successfully recreated in the past, and advances in reclamation and maintenance techniques will further ensure the vegetation plan is successfully implemented. The vegetative plans, including the stream plan, provide appropriate habitat for fish and wildlife. The best available technologies will be used to restore and revegetate wetlands. Furthermore, the vegetation plan meets and exceeds the requirements for the use of indigenous species. Native plants and grasses will be used in all native habitats. As required by subsection (11), measures have been identified and incorporated into the CRP to offset fish and wildlife values lost as a result of mining operations. Special programs to restore and/or reclaim particular habitats, especially for endangered and threatened species have been identified. A Site Habitat Management Plan has been incorporated to prevent adverse impacts to threatened and endangered species, and the proposed conservation easement and reclamation plan will protect and restore currently impaired habitat to a better condition. Specifically, Dr. Durbin testified with respect to the CRP requirements for aquatic species, including fish and macroinvertebrates; the best fish and wildlife habitat onsite will be preserved. Mr. Simpson testified regarding habitat preservation and reclamation activities, the proposed wildlife management plans, and the proposed enhancements to habitat that will benefit wildlife, including listed wildlife. Mosaic has sufficiently addressed the requirements of subsection (11) of the rule in the CRP. Subsection (12) has been satisfied. The proposed mining and reclamation schedule in the application documents comports with the rule requirements by including time schedules for mining, waste disposal, contouring, and revegetation, and the completion dates for such activities comport with the rules. Mosaic has proposed, and the DEP has indicated an intent to issue, the Littoral Zone Variance as an experimental technique to improve the quality of the reclaimed lakes pursuant to this subsection and Section 378.212(1)(e), Florida Statutes. Given the depth of the proposed reclamation lakes, Mosaic applied for, and the Department has proposed to grant, a variance from the water quality standard for DO in the lower portions of the lakes. The DO Variance from Florida Administrative Code Rule 62-302.530(31) is being sought pursuant to Sections 373.414(6)(a), 373.414(17), and 403.201(1)(a), Florida Statutes, which provide the minimum standards for DO levels in surface waters. Class III freshwater water quality standards apply to those portions of the site that constitute surface waters as defined by Florida law. For at least those reclaimed lakes that will connect offsite to downstream waters or wetlands (Lakes 1, 3, and 4), there is no dispute that Class III water quality standards would apply. The minimum water quality standard for DO in freshwater systems is 5.0 milligrams per Litre (mg/L). The evidence demonstrated that alternatives to the lakes in terms of both size and location were considered. The Department considered the proposed lakes as part of the elimination and reduction of overall wetland impacts on both South Fort Meade Polk and Hardee. On balance, it is a preferable alternative to use the available sand resulting from mining of the Hardee County portion of the South Fort Meade mine to eliminate lakes and create additional wetlands on the Polk County portion of the mine rather than utilize that sand to eliminate all lakes on the Hardee County portion of the site. This is especially true given the desire of Hardee County for recreational lakes and the Department's preference to reduce the overall acreage of the reclaimed lakes at the South Fort Meade mine. It is not feasible to make the lakes shallower given the available materials. There is no practicable means known or available for increasing DO in the deep pockets of lakes of the proposed depths that would not have a potential negative effect. This fact has been established and recognized by the Florida Legislature in Section 373.414(6)(a), Florida Statutes, which provides that the deep pits left by mining operations may not meet the DO criteria below the surficial layers of the lakes. The Legislature has further provided that a variance from the DO standard can be issued where deep lakes must be left as part of the reclamation plan. Id. The evidence established that lower DO levels may at times occur in the deep pockets of some of the reclaimed lakes to the same extent and effect as those lower levels occur in natural lakes of similar depths. This effect will occur only in the hypolimnion, or lower levels, of the lakes in the hotter summer months. The evidence likewise established that it is very unlikely that DO levels below 1.0 mg/L will occur at any time in any of the proposed reclaimed lakes. Provided the DO levels do not drop below 1.0 mg/L for any extended period of time, the only expected effect of the occasional seasonal reduction in DO in the lowest level of the reclaimed lakes will be to temporarily exclude fish from those lower portions of the lake during the summer months, which is also true of natural deep lakes. The evidence established that reclaimed lakes function well and provide habitat for fish and wildlife. Water quality standards will be met in all of the lakes other than occasional seasonal DO violations in the lower portions of the deepest lake. All water quality standards, including DO, will be met at all lake outlets and discharge points. All other applicable regulatory criteria will be met in the reclaimed lakes. Dissolved oxygen levels in the upper layers of the lakes are expected and required to meet the minimum DO criteria in Florida Administrative Code Rule 62- 302.530 and will be adequate to support healthy fish populations. The evidence showed no downstream impacts will occur due to the DO Variance for the lakes. The evidence showed reclaimed lakes support healthy fish and macroinvertebrate communities and provide recreational fishing opportunities. Even older lakes, such as the Tenoroc lakes (located in an old mining area in Polk County), provide substantial recreational fishing and wildlife utilization opportunities. This testimony was not rebutted. The evidence offered by Lee and Sarasota Counties as a means to increase DO levels in the reclaimed lakes actually demonstrated that artificially attempting aeration of a deeper lake can have negative environmental effects. Therefore, the testimony of witnesses Janicki and Merriam has not been credited. By a preponderance of the evidence, Mosaic proved entitlement to the DO Variance for the lakes pursuant to Sections 373.414(6)(a) and 403.201(1)(a), Florida Statutes. Given the location of the reclaimed lakes and as a means of experimenting with different reclamation planting techniques to create a variety of shorelines, Mosaic also applied for, and the Department has proposed to grant, a variance from the reclamation requirements in Florida Administrative Code Rule 62C-16.0051 pertaining to the planting of littoral shelves or zones around reclaimed lakes. The Littoral Zone Variance is being sought under Section 378.212(1)(e), Florida Statutes, from Florida Administrative Code Rule 62C-16.0051(6)(a) and (b), which provides minimum water zones for emergent and submerged vegetation, known as the littoral zones of the lakes. Subsection (6) of the rule provides for a twenty-five percent high-water zone of water fluctuation to encourage emergent and transition zone vegetation, and that a twenty percent low water zone between the annual low water line and six feet below the annual low water line to provide fish bedding areas and submerged vegetation zones. These vegetative zones are collectively known as the littoral zone of a lake. Traditionally, these percentages have been met in reclaimed lakes by sloping and creation of a uniform fringe of herbaceous wetland vegetation completely encircling the lake; however, such uniform fringes are not typical around natural lakes, which vary in composition and width. Rather than create a uniform band of vegetation around the lakes, Mosaic has proposed to reclaim the littoral zones around the reclaimed lakes by concentrating them in several broad, shallow areas, including the outlets of the lakes where such outlets occur (Lakes 1, 3 and 4). Of the proposed lakes, one will meet the littoral zone requirement, two will have over twenty percent of the total area in littoral zone, and the remaining lake will have a littoral zone of just under fourteen percent of the total area. The littoral zones will be reclaimed by constructing broad shelves of differing depths and planting the shelves with herbaceous wetland plant species. This design provides the environmental benefit of herbaceous vegetation at the outlet to provide increased filtration of nutrients or sediments of any water overflowing from the lakes during other high water events. This increases environmental benefits at the outlet of the lakes and has the potential to improve water quality downstream. Further, the proposed clustering of the littoral zones in several broad shallow shelves, rather than creation of a thin fringe around the lakes as is customary, will benefit wildlife and fish by creating a more extensive wetland ecosystem in lieu of the monoculture typically created by the thin littoral fringe. The proposed littoral zone clustering also creates more useable shoreline for boating, fishing, and recreational activities in the areas where the littoral zones are not clustered, with the added benefit of tending to separate the wildlife usage in the littoral zone clusters from the human usage in the upland forested areas of the shoreline where minimal littoral zones are planned. This is an experimental technique that advances reclamation methods by balancing habitat, water quality, and recreational considerations. Mosaic has demonstrated that the Littoral Zone Variance comports with Section 378.212(1)(e), Florida Statutes, and may be issued.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order granting Mosaic's applications for the requested permits and variances. DONE AND ENTERED this 18th day of December, 2008, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of December, 2008.
The Issue The issue for consideration in this case is whether the Department of Environmental Protection should issue a permit to Sarasota Bay Hotel, Inc., to modify and expand an existing marina facility associated with an existing adjacent hotel, based on reasonable assurances from the applicant that the proposed project satisfies the applicable statutory and rule criteria.
Findings Of Fact At all times pertinent to the issues herein, the Department of Environmental Protection (Department) was the state agency in Florida responsible for the review of environmental resource permit applications and for the regulation of water pollution in specified waters of the state. SBH is a Florida corporation and the general partner of Hotel Associates of Sarasota, Limited (Hotel Associates), the owner of the property in question. The complex at issue is composed of the Hyatt Hotel and certain submerged land underlying the proposed project. SBH is the authorized agency for Hotel Associates for the purpose of obtaining the permit in issue. Petitioners are associations of condominium owners whose properties lie adjacent and to the west of the site in question. The parties stipulated that all Petitioners had standing in this proceeding. The site at issue, owned by Hotel Associates, consists of a portion of the submerged bottoms within a sea- walled, rectangular-shaped, man-made basin which runs in a north-south direction west of U.S. Highway 41 in Sarasota. It is connected by a narrowed channel to Sarasota Bay at its southern end. Hotel Associates owns approximately the northern one-third of the basin, and Petitioners own approximately the western one-half of the southern two-thirds of the basin. Petitioners' property is not covered in the proposed permit. The remaining portion of the basin, comprised of the eastern one-half of the southern two-thirds, is owned by an entity which is not a party to this action, and that portion of the bottom also is not covered by the proposed permit. However, in order for boat traffic to reach the property in issue, the boats must traverse the southern two- thirds of the basin. Both Petitioners and the unconnected third owner maintain existing finger piers within their respective portions of the basin outside the portion in issue. The basin in which the marina in question is located is classified as a Class III water body and is connected to Sarasota Bay, which is a Class III Outstanding Florida Water. Sarasota Bay is located approximately twelve hundred feet from the head of the basin and approximately eight hundred feet from the southern property line of the basin. As of the date of the hearing, the applicant, SBH, operated a permitted marina facility within the perimeter of the property in issue. This permit was issued years ago after the fact; that is, after the marina had already been constructed. As it currently exists, the marina is made up of perimeter docks which adjoin the northern and eastern sides of the basin and includes eight finger piers which provide ten to fifteen slips. In addition, a perimeter dock extends around an existing restaurant which sits on pilings over in the northeast end of the basin. Repairs and modifications were made to the facility under then-existing exemptions in 1995. These included the replacement of numerous copper, chromium, and arsenic (CCA) treated pilings and the re-decking of existing walkways and finger piers with CCA-treated wood. At the present time, seven of the finger-pier slips are under lease to a commercial charter fleet, Chitwood Charters, and one slip located along the perimeter dock is leased to a dive boat operation, Scuba Quest. At least one other finger-pier slip has a boat docked at it for an extended period. This boat is owned by Charles Githler, president of SBH. The remaining finger-pier and perimeter slips are ordinarily used on a transient basis by guests of the Hyatt Hotel and the restaurant. The existing facility, including the finger piers slips and the perimeter slips, contains approximately 6,700 square feet of docking space and is designed to accommodate between twenty to thirty boats, depending upon the length of the boats. On occasion, however, as many as 40 to 60 boats have been docked at the facility. At times, when demand increases, the larger slips have been subdivided to allow up to four boats to be stern-moored per slip. Even more boats have been docked at the facility for boat shows by the use of stern mooring or "rafting," which calls for boats to be moored tied together, side by side, out from the docks. By application dated May 18, 1999, and received by the Department's Tampa District office on June 16, 1999, SBH sought to obtain from the Department a permit to modify and expand its existing marina facility. It proposed to expand the existing approximately 6,700 square feet of dock space to approximately 7,000 square feet, thereby creating a marina with 32 designated slips. Conditions to issuance of the permit, agreed to by the applicant, include a limitation on the number of boats which may be moored at the facility at any time and the addition of storm water treatment capability to the existing storm water drainage system. SBH also agreed to reduce the terminal end of the middle pier from 900 to 400 square feet. SBH also agreed to accept the imposition of several other permit conditions required by the Department, and to offset any impacts on wildlife and water quality as a result of the operation of the permitted facility. In addition to requiring that all long-term slip leases incorporate prohibitions against live-aboards and dockside boat maintenance, these conditions include the following: Overboard discharges of trash, human or animal waste, or fuel shall not occur at the docks. Sewage pump-out service shall be available at the marina facility. * * * 18. Fish cleaning stations, boat repair facilities and refueling facilities are not allowed. 20. There shall be no fueling or fueling facilities at the facility. * * * 28. The shoreline enhancement indicated on Attachment A shall be implemented within 30 days. * * * 30. The permittee shall perform water quality monitoring within the basin at the locations indicated on Attachment A semiannually (January and July of each year) for a period of 5 years. * * * All piles shall be constructed of concrete with exception of 18 mooring piles identified in permit submittals. This permit authorizes the mooring (temporarily or permanently) of a maximum of [32] watercraft at the subject facility. A harbormaster must be designated and maintained at the subject facility. In order to be in compliance with this permit, the ”OARS Ultra-Urban" hydrocarbon adsorbent insert, or Department approved equal, must be installed within the catch basin inlets as shown on the approved drawings. At a minimum, the hydrocarbon adsorbent material shall be replaced and maintained in accordance with manufacturer's instructions. More frequent inspections and replacement of the filtration media may be required, depending on local conditions and results of the required water quality monitoring. * * * The permittee/grantee/lessee shall ensure that: In order to provide protection to manatees during the operation of this facility, permanent manatee information and/or awareness sign(s) will be installed and maintained to increase boater awareness of the presence of manatees, and of the need to minimize the threat of boats to these animals. SBH has also agreed to replace existing CCA-treated wood decking with concrete and fiberglass decking and to replace approximately 80 existing CCA-treated wood pilings with concrete pilings. Based on its analysis of the permit application and the supporting documentation submitted therewith, the Department, on March 2, 2000, entered a Notice of Intent to issue the permit for this project. Shortly thereafter, on March 25, 2000, after obtaining a minimal extension of time to file, the Petitioners filed a Petition for Administrative Hearing opposing the issuance of the proposed permit. Departmental decisions on water quality permits such as that in issue here are dependent upon the applicant satisfying the Department's requirements in several identified areas. These include the impact of the project on water quality; impact of the project on the public health, safety, and welfare; impact of the project on the conservation of fish and wildlife, including threatened or endangered species; impact of the project on navigation, the flow of water, erosion and shoaling; impact of the project on the immediate fishing, recreational values and marine productivity; impact of the project on archeological resources; impact of the project on the current condition and relative value of functions currently performed by areas to be affected; whether the project is permanent or temporary; and a balancing of the criteria, cumulative impacts, and secondary impacts. Addressing each of these in turn, it is clear that the current quality of the water within the existing marina is below established standards. Respondents admit that Petitioner has shown that the existing marina operation has diminished water quality conditions and created an environment that has potential adverse impacts to the fish and wildlife which frequent the basin as well as some of the neighboring property owners. This is not to say that these impacts were envisioned when the basin was constructed. However, other than as they relate to fish and wildlife and to water quality, the problems created by the marina do not relate to most permit criteria. The Respondent's experts calculate that due to its configuration and location, the basin naturally flushes approximately every 14.75 days. This is an inadequate time period to fully disperse any pollutants found in the basis. As a result of the inadequate flushing and the continuing use of the basin as a marina, there are resulting impacts to the water quality surrounding the existing facilities. Mr. Armstrong, Petitioner's water quality expert, indicated the project as proposed would lengthen even further the flushing time because of the addition of new boats and, to a lesser degree, the additional pilings and dock structure. These additions would, he contends, result in additional obstructions to water movement and cause a resultant increase in flushing time. While flushing is not a requirement of the permit, it has a bearing on water quality which is a consideration. Petitioners also argue that the mitigation measures proposed in the permit are inadequate and attack the qualifications of Mr. Cooper, the Department's storm water engineer. They point out alleged errors in Cooper's analysis and cite Mr. Armstrong, an individual with significant experience in water quality monitoring and analysis, to support their other witnesses' conclusions that more boats will increase the risk of hydrocarbon pollution from gasoline and diesel engines. Petitioners urge that the increased contamination, when coupled with the slow flushing action, would tend to settle down to where the pollutants enter the water - in the basin. Since it is clear these impacts would exist and continue even were the pending project not constructed, the issue, then, is whether the proposed project will worsen these environmental impacts. Respondents' authorities calculate they would not. In fact, it would appear the proposed changes called for in the permit, the removal of CCA-treated wood and its replacement with concrete piling and decking and the installation of storm water treatment apparatus, would reduce the adverse impacts to water quality within the basin and, in fact, improve it. It is so found. An issue is raised in the evidence as to the actual number of boats which can effectively use the marina at any one time. SBH contends the present configuration calls for between twenty to thirty boats. Evidence also shows that at times, during boat shows for example, many more boats are accommodated therein through "rafting." Even if the facility is expanded by the most significant number of slips, there is no concrete evidence there would be a significantly increased usage. The current usage is normally well below capacity. Modifications proposed under the pending permit could add as many as ten to fifteen additional slips. The Department has considered it significant that SBH has agreed to limit the number of boats that can be docked in this marina, even after modification. Unfortunately, no specific figure has been given for this limit, and, therefore, it cannot be shown exactly how much long-term water quality benefit can be expected. Nonetheless, it is a reasonable conclusion to draw, as the Department has done, that if the number of boats is limited to a figure at or even slightly higher that that which is currently experienced, a long-term benefit can be expected with the implementation of the other mitigation conditions. This benefit currently cannot be quantified, however. What can be established, and all parties agree, is that the basin currently does not meet water quality standards for copper and dissolved oxygen. The proposed permit addresses the issue of dissolved oxygen by requiring SBH to follow best management practices in the operation of the marina; to treat storm water discharge which enters the marina; and to provide a sewage pump-out station at the marina which would prevent the discharge of sewage into the water. The issue of the water's copper level is addressed by the removal of the CCA-treated pilings and decking and their replacement with concrete and fiberglass; the treatment of the storm-water discharge before its discharge into the basin; and the hiring of a harbor master to ensure that the prohibition against hull scraping at the basin is complied with. A restriction on the number of boats allowed into the marina at any one time would also treat the copper problem by reducing the exposure to anti-fouling paint containing copper. This is a condition of the permit. It is important to note that under existing statutory and rule exemptions, SBH could repair or replace the existing dock structure without the need for a permit. However, the issuance of a permit which permits modification and a slight expansion of the facility will prohibit the replacement of the existing CCA-treated wood with CCA-treated wood. The concrete and fiberglass pilings and decking will not leach copper into the water and, in time, should result in a lower concentration of that substance in the water. Another consideration of the permitting authorities relates to the impact the project would have on public health, safety, and welfare. Petitioners expressed concern that an increase in the number of slips called for in the proposed project would cause an increase in the number of boats that utilize the basin. Currently, though there are a limited number of slips available, there is no limitation on the number of boats which may use the facility. A reasonable estimate of capacity, considering the configuration of the docks and slips and the permit limitations established, indicates that no more than thirty-two boats will be permitted to use the basin at any one time. If this limitation is followed, it is reasonable to expect an improvement in the water quality. Petitioners also express concern that an increase in the number of authorized boats using the marina will result in an increase in the number of boats traveling at excessive speeds in entering and exiting. No evidence was introduced in support of this theory, but, in any case, Respondents counter- hypothesize that the increase in allowed boats will result in an increase in long term lessors over transients, and suggest that long term users are more considerate than transients. Neither side presented any substantial evidence in support of its positions. The impact on the conservation of fish and wildlife is a mandated consideration by the agency. No evidence was presented by either side regarding the existence of fish and wildlife in the area, much less threatened species, other than manatees. To be sure, these noble creatures inhabit the marina at times in appreciable numbers. The threat to them, however, comes from boat strikes, and no evidence was presented as to the number of strikes caused by boats in the marina or its approaches or the seriousness of these strikes. The agency to which the review of impacts to manatees was left, the Florida Fish and Wildlife Conservation Commission (FWCC) opined that the permit cap of 32 boats would keep to a minimum the potential impact to manatees from this project. Any increase in the number of boats, and the minimal impact increase thereby, should, it was considered, be offset by compliance with permit conditions. This opinion was contradicted by Mr. Thompson, Petitioner's manatee expert, who argued against any increase of boat traffic in manatee areas. This position is not the policy of the Department and is not controlling here. Further, it would appear this expert did not consider any mitigation factors proposed by SBH, as the Department is required to do. Taken together, the weight of the evidence supports a finding that the expected impact of this project on fish and wildlife, including those threatened and endangered species, is minimal. Based on the evidence of record, it is found that the expected impact of this project on navigation, the flow of water, erosion, and shoaling in the vicinity is virtually non- existent. The only factor bearing on this issue is the number of boats which will use the facility and its approach. Permit conditions call for a limitation on the number of water craft which will use the facility to be permitted to a number lower than that which uses it, at times, under current conditions. The water is a dead-end harbor, with no through traffic. There is no evidence of either erosion or shoaling now. It would not likely increase. A reduction in traffic as would occur under the conditions imposed by the permit can do nothing but reduce the potential for propeller dredging by boat traffic and the water turbidity that would accompany such strikes. This would improve navigation slightly, and there should be no adverse impact to the flow of water. The evidence presented at hearing did not establish any negative impact on fishing or marine productivity in the vicinity of the proposed project, which is permanent in nature. By the same token, no adverse effect to significant historical or archaeological resources was shown by the evidence of record. The facility in issue is currently a commercial activity consisting of a docking facility and a restaurant. No evidence was introduced to show that the project proposed would have an adverse impact on the current condition and relative value of the current function. In fact, the evidence indicates that the facility would be improved. Though not raised by the evidence, it should be noted that Petitioners presented no evidence that their property values as adjacent property owners, would be adversely effected by this project. In balancing the criteria, cumulative impacts and secondary impacts of the proposed project on the immediate and surrounding area, it appears that the applicant has provided reasonable assurances that the project is not contrary to the public interest. The marina supports the hotel and restaurant which is on it. Adjoining property owners, the Petitioners, expressed concern that the modifications to the existing marina will result in a decrease in water quality in the basin; will increase the potential for fuel spills with their related short term discomforts and long term damages; and will increase the danger to the manatee population which periodically uses the basin. While they are entitled to the quiet enjoyment of their property, it is unreasonable for those who live on the water to expect that the benefits of living by the water would not carry with it the potential for some periodic discomfort created by waterfront activity. The weight of the evidence presented in this case indicates no significant cumulative adverse impacts from this project. To the contrary, the state of the evidence suggests an improvement in water quality and navigation in the basin and its approaches, and any secondary impacts resulting from the accomplishment of the project would be minimal.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Environmental Protection enter a Final Order issuing to Sarasota Bay Hotel the requested permit to modify and expand the existing marina facility located adjacent to the existing Hyatt Hotel at 1000 Boulevard of the Arts in Sarasota, Florida. DONE AND ENTERED this 12th day of February, 2001, in Tallahassee, Leon County, Florida. ___________________________________ ARNOLD H. POLLOCK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6947 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of February, 2001. COPIES FURNISHED: Barbara B. Levin, Esquire Scott A. Haas, Esquire Abel, Band, Russell, Collier, Pitchford & Gordon 240 South Pineapple Avenue Sarasota, Florida 34236 Graig D. Varn, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Mark A. Hanson, Esquire Law Offices of Lobeck & Hanson, P.A. 2033 Main Street Suite 403 Sarasota, Florida 34237 Kathy C. Carter, Agency Clerk Office of the General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Teri L. Donaldson, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000
The Issue The issue in this case was whether the Respondent, City of Cape Coral (City), was entitled to an Individual Environmental Resource Permit (Permit) that would allow removal of the Chiquita Boat Lock (Lock) and associated uplands, and installation of a 165-foot linear seawall in the South Spreader Waterway in Cape Coral, Florida.
Findings Of Fact Based on the parties' stipulations and the evidence adduced at the final hearing, the following findings of fact are made: The Parties The Department is the administrative agency of the State of Florida statutorily charged with, among other things, protecting Florida's water resources. As part of the Department's performance of these duties, it administers and enforces the provisions of chapter 373, part IV, Florida Statutes, and the rules promulgated thereunder in the Florida Administrative Code. Pursuant to that authority, the Department determines whether to issue or deny applications for environmental resource permits. The City is a Florida municipality in Lee County. The City is the applicant for the Permit allowing the removal of the Lock and installation of a seawall (Project). The Project is located within the geographic boundary of the City. The South Spreader Waterway is a perimeter canal separating the City's canal system from shoreline wetlands to the west and south, which run the length of Matlacha Pass to the mouth of the Caloosahatchee River at San Carlos Bay.1/ The Association is a Florida non-profit corporation that was created in 1981. The Association was created to safeguard the interests of its members. The Association has approximately 150 members who reside in Matlacha and Matlacha Isles, Florida. A substantial number of its members have substantial interests in the use and enjoyment of waters adjacent to and surrounding Matlacha. The Association's members were particularly interested in protecting the water quality of the surface waters in the area. Matlacha is an island community located to the northwest of Cape Coral, the South Spreader Waterway, and the Lock. Matlacha is located within Matlacha Pass Aquatic Preserve. Matlacha Pass is classified as a Class II waterbody designated for shellfish propagation or harvesting, and is an Outstanding Florida Water (OFW). See Fla. Admin. Code R. 62-02.400(17)(b)36; 62-302.700(9)(h). Petitioner, Karl Deigert, is a resident and property owner in Matlacha. Mr. Deigert is the president of the Association. Mr. Deigert’s house in Matlacha is waterfront. He holds a captain’s license and has a business in which he gives sightseeing and ecological tours by boat of the waters around Matlacha. He fishes in the waters around his property and enjoys the current water quality in the area. He is concerned that removal of the Lock would have negative effects on water quality and would negatively impact the viability of his business and his enjoyment of the waters surrounding Matlacha. Petitioner, Melanie Hoff, is a resident and property owner in St. James City. St. James City is located to the southwest of Cape Coral. Ms. Hoff’s property is located within five nautical miles of the Lock. Ms. Hoff engages in various water sports and fishes in the waters around her property. She moved to the area, in part, for the favorable water quality. She is concerned that removal of the Lock would negatively impact water quality and her ability to use and enjoy waters in the area. Petitioner, Robert S. Zarranz, is a resident and property owner in Cape Coral. Mr. Zarranz’s house in Cape Coral is waterfront. He is an avid fisherman and boater. He is concerned that removal of the Lock would negatively impact water quality, and that the quality of fishing in the area would decline as a result. Petitioner, Yolanda Olsen, is a resident and property owner in Cape Coral. Ms. Olsen’s house in Cape Coral is waterfront. She enjoys watersports and birdwatching in the areas around her property. She is concerned that removal of the Lock would negatively impact water quality, and that her ability to enjoy her property and the surrounding waters would suffer as a result. Petitioner, Jessica Blanks, is a resident and property owner in Cape Coral. Ms. Blanks’ house in Cape Coral is waterfront. She is concerned that removal of the Lock would negatively impact water quality, and that her ability to enjoy her property and the surrounding waters would suffer as a result. Petitioner, Joseph Michael Hannon, is a resident and property owner in Matlacha. Mr. Hannon is a member of the Association. He enjoys boating, fishing, and kayaking in the waters surrounding Matlacha. He is concerned that removal of the Lock would negatively impact water quality, and that his ability to enjoy his property and the surrounding waters would suffer as a result. Petitioner, Debra Hall, did not appear at the final hearing and no testimony was offered regarding her standing. The Project and Vicinity The Project site is 0.47 acres. At the Lock location, the South Spreader Waterway is 200 feet wide, and includes a 125-foot wide upland area secured by two seawalls, the 20-foot wide Lock, a 32-foot wide upland area secured by one seawall, and 23 feet of mangrove wetlands. The Lock is bordered to the north by property owned by Cape Harbour Marina, LLC, and bordered to the south by mangrove wetlands owned by the state of Florida. The 125-foot wide upland area and the 20-foot wide Lock form a barrier separating the South Spreader Waterway from the Caloosahatchee River. The preponderance of the competent substantial evidence established that the South Spreader Waterway behind the Lock is not tidally influenced, but would become tidally influenced upon removal of the Lock. Joint Exhibit 1 at p. 46. The City proposes to remove the Lock and one of the seawalls, reducing the 125-foot upland area to 20 feet. The proposed future condition of the area would include 125 feet of open canal directly connecting the South Spreader Waterway with the Caloosahatchee River. Joint Exhibit 1 at p. 47. The primary purpose of the Lock's removal is to alleviate safety concerns related to boater navigation. The Project's in-water construction includes demolition and removal of the existing Lock, removal of existing fill in the 125-foot upland area, removal of existing seawalls, and construction of replacement seawalls. The City would employ Best Management Practices (BMPs) throughout the course of the Project, including sediment and erosion controls such as turbidity barriers. The turbidity barriers would be made of a material in which manatees could not become entangled. All personnel involved with the Project would be instructed about the presence of manatees. Also, temporary signs concerning manatees would be posted prior to and during all in-water project activities. History of the South Spreader Waterway In the mid-1970's, the co-trustees of Gulf American Corporation, GAC Properties Credit, Inc., and GAC Properties, Inc., (collectively GAC) filed for after-the-fact permits from the Department's predecessor agency (DER), for the large dredge and fill work project that created the canal system in Cape Coral. In 1977, DER entered into CO 15 with GAC to create the North and South Spreader Waterways and retention control systems, including barriers. The Lock was one of the barriers created in response to CO 15. The Spreader Waterways were created to restore the natural hydrology of the area affected by GAC's unauthorized dredging and filling activity. The Spreader Waterways collected and retained surface runoff waters originating from the interior of Cape Coral's canal system. The South Spreader Waterway was not designed to meet water quality standards, but instead to collect surface runoff, then allow discharge of the excess waters collected over and through the mangrove wetlands located on the western and southern borders of the South Spreader Waterway. This fresh water flow was designed to mimic the historic sheet flow through the coastal fringe of mangroves and salt marshes of the Caloosahatchee River and Matlacha Pass estuaries. The fresh water slowly discharged over the coastal fringe until it finally mixed with the more saline waters of the estuaries. The estuarine environments located west and south of the Lock require certain levels of salinity to remain healthy ecosystems. Restoring and achieving certain salinity ranges was important to restoring and preserving the coastal fringe. In 1977 GAC finalized bankruptcy proceedings and executed CO 15. CO 15 required GAC to relinquish to the state of Florida the mangrove wetlands it owned on the western and southern borders of the South Spreader Waterway. This land grant was dedicated by a warranty deed executed in 1977 between GAC and the state of Florida. The Petitioners' expert, Kevin Erwin, worked as an environmental specialist for DER prior to and during the construction of the Spreader Waterways. Mr. Erwin was DER's main representative who worked with the GAC co-trustees to resolve the massive dredge and fill violation and design a system to restore the natural hydrology of the area. Mr. Erwin testified that the Lock was designed to assist in retention of fresh water in the South Spreader Waterway. The fresh water would be retained, slowed down, and allowed to slowly sheet flow over and through the coastal fringe. Mr. Erwin also testified that the South Spreader Waterway was not designed to allow direct tidal exchange with the Caloosahatchee River. In Mr. Erwin's opinion, the South Spreader Waterway appeared to be functioning today in the same manner as originally intended. Breaches and Exchange of Waters The Department's second amended notice of intent for the Project, stated that the Project was not expected to contribute to current water quality violations, because water in the South Spreader Waterway was already being exchanged with Matlacha Pass and the Caloosahatchee River through breaches and direct tidal flow. This second amended notice of intent removed all references to mitigation projects that would provide a net improvement in water quality as part of the regulatory basis for issuance of the permit. See Joint Exhibit 1 at pp. 326-333. The Department's witnesses testified that waters within the South Spreader Waterway currently mix with waters of the Caloosahatchee River when the Lock remains open during incoming and slack tides. A Department permit allowed the Lock to remain open during incoming and slack tides. Department witness, Megan Mills, the permitting program administrator, testified that she could not remember the exact date that permit was issued, but that it had been "a couple years." The location of breaches in the western and southern banks of the South Spreader Waterway was documented on another permit's drawings and pictures for a project titled "Cape Coral Spreader Waterway Restoration." See Cape Coral Ex. 9. Those documents located three breaches for repair and restoration identified as Breach 16A, Breach 16B, and Breach 20. The modeling reports and discussion that support the City's application showed these three breaches connect to Matlacha Pass Aquatic Preserve. Breach 20 was described as a connected tidal creek. Breach 16A and 16B were described as allowing water movement between Matlacha Pass and the South Spreader Waterway only when relatively high water elevations occurred in Matlacha Pass or in the South Spreader Waterway. The Department's water quality explanation of "mixing," was rather simplistic, and did not consider that the waterbody in which the Project would occur has three direct connections with an OFW that is a Class II waters designated for shellfish propagation or harvesting. Such a consideration would require the Department to determine whether to apply the OFW permitting standards, and the Class II waters permitting criteria in section 10.2.5 of the Environmental Resource Permit Applicant's Handbook, Volume I. See Fla. Admin Code R. 62-330.302(1)(a); 62-4.242(2); and 62-302.400(17)(b)36. The Caloosahatchee River, at its entrance to the South Spreader Waterway, is a Class III waters restricted for shellfish harvesting. The mouth of the Caloosahatchee River is San Carlos Bay, which is a Class II waters restricted for shellfish harvesting. There was no evidence that the Department's regulatory analysis considered that the waterbody in which the Project would occur directly connects to Class III waters that are restricted for shellfish harvesting, and is in close proximity to Class II waters that are restricted for shellfish harvesting. See Fla. Admin. Code R. 62-302.400(17)(b)36. and 62-330.302(1)(c).2/ Total Nitrogen The City's expert, Anthony Janicki, Ph.D., testified that nitrogen concentrations in the Caloosahatchee River were higher than in the South Spreader Waterway in the years 2017 and 2018. Thus, he opined that if the Lock is removed, water from the South Spreader Waterway would not negatively impact the Caloosahatchee River. However, the City's application was supported by an analysis, with more than a decade of monitoring data, which showed nitrogen concentration values were comparable inside the South Spreader Waterway and in the Caloosahatchee River. Dr. Janicki also used the Department's Hydrologic Simulation Program – FORTRAN (HSPF) watershed model to estimate the Total Nitrogen (TN) loading that would enter the Caloosahatchee River through the Chiquita Lock. Dr. Janicki estimated that TN loading to the Caloosahatchee River, after removal of the Chiquita Lock, would amount to 30,746 pounds per year. The Caloosahatchee River is listed as impaired for nutrients and has a TN Total Maximum Daily Load (TMDL) that was set by the Department in 2009. Dr. Janicki opined that removing the Lock would not result in adverse impacts to the surrounding environment. But the Petitioners obtained his concession that his opinion was dependent on the City's completion of additional water quality enhancement projects in the future as part of its obligations under the Caloosahatchee Estuary Basin Management Action Plan (BMAP) for achieving the TN TMDL. Dr. Janicki additionally testified that the potential TN loading to the Caloosahatchee River did not anticipate an actual impact to the River's water quality because the TN loads from the South Spreader Waterway were already factored into the 2009 TMDL. He essentially testified that the Lock's removal was anticipated and was factored into the model when the TMDL was established in 2009. Thus, the Petitioners proved by a preponderance of the competent and substantial evidence that the Department and the City were not aligned regarding how the City's application would provide reasonable assurances of meeting applicable water quality standards. The Petitioners proved by a preponderance of the competent and substantial evidence that the City relied on future projects to provide reasonable assurance that the removal of the Lock would not cause or contribute to violations of water quality standards in the Caloosahatchee River and the Matlacha Pass Aquatic Preserve. The Petitioners proved by a preponderance of the competent and substantial evidence that the Department relied on a simplistic exchange of waters to determine that removal of the Lock would not cause or contribute to violations of water quality standards in the Caloosahatchee River and the Matlacha Pass Aquatic Preserve. Water Quantity and Salinity The engineering report that supports the City's application stated that when the Lock is removed, the South Spreader Waterway behind the Lock will become tidally influenced. With the Lock removed, the volume of daily water fluxes for the South Spreader Waterway would increase from zero cubic meters per day to 63,645 cubic meters per day. At the location of Breach 20, with the Lock removed, the volume of daily water fluxes would drastically decrease from 49,644 cubic meters per day to eight cubic meters per day. Dr. Janicki testified that Breach 20 was connected to a remnant tidal creek that meanders and eventually empties into an embayment. The evidence demonstrated that the embayment is Punta Blanca Bay, which is part of the Matlacha Pass Aquatic Preserve. Dr. Janicki opined that Breach 20 was an area of erosion risk and sediment transport into downstream mangroves that would be significantly reduced by removing the Lock. He explained that the reductions in flow would result in reductions in velocities through Breach 20 and in the South Spreader Waterway itself. Mr. Erwin testified that Breach 20 was not a "breach."3/ He described it as the location of a perpendicular intersection of the South Spreader Waterway with a small tidal creek, which connected to a tidal pond further back in the mangroves. Mr. Erwin testified that an "engineered sandbag concrete structure" was built at the shallow opening to limit the amount of flow into and out of this tidal creek system. But it was also designed to make sure that the tidal creek system "continued to get some amount of water." As found above, Lock removal would drastically reduce the volume of daily water fluxes into and out of Breach 20's tidal creek system. Mr. Erwin also testified that any issues with velocities or erosion would be exemplified by bed lowering, siltation, and stressed mangroves. He persuasively testified, however, that there was no such evidence of erosion and there were "a lot of real healthy mangroves." Mr. Erwin opined that removal of the Lock would cause the South Spreader Waterway to go from a closed, mostly fresh water system, to a tidal saline system. He described the current salinity level in the South Spreader Waterway to be low enough to support low salinity vegetation and not high enough to support marine organisms like barnacles and oysters. The City's application actually supports this opinion. Using the Environmental Fluid Dynamics Code (EFDC) model developed by Dr. Janicki for this Lock removal project, comparisons were made describing the salinity distribution within the South Spreader Waterway. The model was run with and without the Lock, for both a wet and dry year. Dr. Janicki testified, and the model showed, that removal of the Lock would result in increased salinity above the Lock and decreased salinity downstream of the Lock. However, he generally opined that the distribution of salinities was well within the normal ranges seen in this area. The City's application also concluded that the resultant salinities did not fall outside the preferred salinity ranges for seagrasses, oysters, and a wide variety of fish taxa. However, Dr. Janicki did not address specific changes in vegetation and encroachment of marine organisms that would occur with the increase in salinity within the South Spreader Waterway. Secondary Impacts to the Mangrove Wetlands Mr. Erwin testified that the mangroves located on the western and southern borders of the South Spreader Waterway are currently in very good health. He additionally testified that loss of the current fresh water hydraulic head and an increase in salinity within the South Spreader Waterway would negatively impact the health of the mangrove wetlands. In addition, the City's application stated that removing the Lock would result in a drop in the water level of one to one and a half feet within the South Spreader Waterway. Mr. Erwin credibly and persuasively testified that a drop in water level of only a few inches would have negative effects on the health of mangroves, and that a drop of a foot could result in substantial mangrove die-off. Mr. Erwin testified that the mangrove wetlands adjacent to the South Spreader Waterway consist of a variety of plants and algae in addition to mangroves. He described the wetlands as a mangrove community made up of different types of mangroves, and epiphytic vegetation such as marine algae. This mangrove community provides habitat for a "wide range of invertebrates." He further testified that these plants and algae uptake and transform the nutrients that flow over and through the mangrove wetlands before they reach the receiving waters. Thus, the mangrove wetlands on the western and southern borders of the South Spreader Waterway serve to filter nutrients out of the water discharged from the Waterway before it reaches Matlacha Pass and the Caloosahatchee River. Mr. Erwin's credible and persuasive testimony was contrary to the City's contention that Lock removal would not result in adverse impacts to the mangrove wetlands adjacent to the South Spreader Waterway. The City and the Department failed to provide reasonable assurances that removing the Lock would not have adverse secondary impacts to the health of the mangrove wetlands community adjacent to the South Spreader Waterway. Impacts to Fish and Wildlife, Including Endangered and Threatened Species The Florida Fish and Wildlife Conservation Commission (FWC) reviewed the City's application and determined that if BMPs for in-water work were employed during construction, no significant adverse impacts on fish and wildlife were expected. For example, temporary signs concerning manatees would be posted prior to and during all in-water project activities, and all personnel would be instructed about the presence of manatees. The FWC determination only addressed direct impacts during in-water construction work. The City's application contained supporting material that identified the major change resulting from removal of the Lock that may influence fish and wildlife in the vicinity of the Project, was the opportunity for movement to or from the South Spreader Waterway canal system. Threatened and endangered species of concern in the area included the Florida manatee and the smalltooth sawfish. The City's application stated that literature review showed the smalltooth sawfish and the Florida manatee utilized non-main-stem habitats, such as sea-wall lined canals, off the Caloosahatchee River. The City cited studies from 2011 and 2013, which showed that non-main-stem habitats were important thermal refuges during the winter, and part of the overall nursery area for smalltooth sawfish. The City concluded that removal of the Lock "would not be adverse, and would instead result in increased areas of useable habitat by the species." However, the Petitioner's expert witness, John Cassani, who is the Calusa Waterkeeper, testified that there is a smalltooth sawfish exclusion zone downstream of the Lock. He testified that the exclusion zone is a pupping area for smalltooth sawfish, and that rapid salinity fluctuations could negatively impact their habitat. The City also concluded that any impacts to the Florida manatee would not be adverse, "and would instead result in increased areas of useable habitat by the species, as well as a reduction in risk of entrapment or crushing in a canal lock system." At the same time, the City acknowledged that "watercraft collision is a primary anthropogenic threat to manatees." The City's literature review included a regional assessment by FWC's Fish and Wildlife Research Institute (FWRI) from 2006. Overall, the FWRI report concluded that the mouth of the Caloosahatchee River, at San Carlos Bay, was a "hot spot" for boat traffic coinciding with the shift and dispersal of manatees from winter refugia. The result was a "high risk of manatee- motorboat collisions." In addition, testimony adduced at the hearing from an 18-year employee of Cape Harbour Marina, Mr. Frank Muto, was that Lock removal would result in novice boaters increasing their speed, ignoring the no-wake and slow-speed zones, and presenting "a bigger hazard than the [L]ock ever has." Boater Navigation Concerns Oliver Clarke was the City’s principal engineer during the application process, and signed the application as the City's authorized agent. Mr. Clarke testified that he has witnessed boater congestion at the Lock. He also testified that lack of boating experience and weather concerns can exacerbate the boater congestion issues at the Lock. Petitioners presented the testimony of Mr. Frank Muto, the general manager of Cape Harbour Marina. Mr. Muto has been at the Cape Harbour Marina for 18 years. The marina has 78 docks on three finger piers along with transient spots. The marina is not currently subject to tidal flows and its water depth is between six and a half and seven and a half feet. He testified that they currently have at least 28 boats that maintain a draft of between four and a half and six feet of water. If the water depth got below four feet, those customers would not want to remain at the marina. Mr. Muto further testified that the Lock was in place when the marina was built, and the marina and docks were designed for an area with no tidal flow. Mr. Muto also testified that he has witnessed several boating safety incidents in and around the Lock. He testified that he would attribute almost all of those incidents to novice boaters who lack knowledge of proper boating operations and locking procedures. Mr. Muto additionally testified that there is law enforcement presence at the Lock twenty-four hours a day, including FWC marine patrol and the City's marine patrol.
Conclusions For Petitioners: J. Michael Hannon, Qualified Representative 2721 Clyde Street Matlacha, Florida 33993 John S. Turner, Esquire Peterson Law Group Post Office Box 670 Fort Myers, Florida 33902 For Respondent City of Cape Coral: Craig D. Varn, Esquire Amy Wells Brennan, Esquire Manson Bolves Donaldson Varn, P.A. 106 East College Avenue, Suite 820 Tallahassee, Florida 32301 Steven D. Griffin City of Cape Coral Assistant City Attorney Post Office Box 150027 Cape Coral, Florida 33915-0027 For Respondent Department of Environmental Protection: Kirk Sanders White, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-3000
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that: The Department of Environmental Protection enter a final order denying Individual Environmental Resource Permit Number 244816-005 to the City of Cape Coral for removal of the Chiquita Boat Lock. The final order deny Petitioners' request for an award of attorney's fees and costs. DONE AND ENTERED this 12th day of December, 2019, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of December, 2019.