The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.
Findings Of Fact Respondent, Wesley Ash, currently holds license number CP C015871 issued by the Construction Industry Licensing Board to authorize Ash to engage in the pool contracting business. Dodd Complaint (Count I). Respondent, Wesley Ash, doing business as Wada Pools, Inc., contracted with Jerry Dodd on or about June 17, 1981, to build a pneumatic concrete pool with skimmer and recirculation system. The contract did not include installation of the concrete deck around the pool. Dodd decided to contract with another independent contractor to install the deck at a lower price than Ash wanted for the job. Ash completed his work by approximately August 1981. He installed the concrete pool shell, finished the inside surface and installed tile along the water line. He then attached the skimmer assembly, plumbing it so that it was level and attaching it to the concrete pool shell by means of the skimmer's PVC plumbing piping. After Ash finished his work, Dodd's other contractor came behind Ash. He used some of the dirt Ash had excavated from the pool site to raise the ground surrounding the pool by approximately six inches above grade. He then poured the concrete deck but failed to encase the skimmer assembly with the deck concrete in the process of pouring the concrete deck. It was not Ash's practice to make any special arrangements to stabilize the skimmer assembly when he installed both pool and concrete deck. He relies on the skimmer assembly plumbing to stabilize the skimmer assembly until the concrete deck is poured. In pouring the concrete deck, Ash encases the skimmer assembly with the deck concrete to stabilize the skimmer assembly and prevent leakage. In the case of the Poland pool (paragraphs 17 and 22, below), Ash used this method to install both the pool and the concrete deck, and Poland has had no complaint of leakage at the skimmer (nor was there any evidence of leakage at the skimmer). In the case of the Priests' pool (paragraphs 11 through 13, below), Ash followed the same procedures as he did with the Dodd pool, and another contractor poured the concrete deck. As with the Poland pool, there have been no complaints (nor was there any evidence) of leakage at the skimmer. Within approximately one and one-half years after installation of the Dodd pool, Dodd began to notice what he thinks is a leak in his pool. The water level in the Dodd pool drops approximately one-quarter inch per day. But the Department's own expert witness conceded that water loss of between one-eight and one-quarter inch can be explained by evaporation. It was not proved that the Dodd pool is leaking at all. If there is a leak causing a small increment of water loss above loss through normal evaporation, the leak would have to be very small and would be very difficult to detect. Ash and others have tried but have been unable to find a leak at the skimmer of Dodd pool. In approximately summer 1985, Dodd himself dug a hole under the concrete deck to expose the bottom of the skimmer assembly. The excavation revealed an unusual amount of moisture that might be the result of a leak at the skimmer. It also revealed that the contractor who poured the Dodd concrete deck did not encase the skimmer assembly as Ash had thought he would. The Department's expert - a professional engineer with a B.S. degree in civil engineering, an M.S. degree in structural engineering and a Ph.D. degree in environmental engineering - gave his opinion that a residential pool skimmer assembly should be either (1) encased with the concrete of the pool shell or (2) encased with deck concrete which is structurally tied to the concrete pool shell. He opined that the latter method would require either a very rough surface on the pool shell concrete or steel extending from the pool shell in order for the structural tie to be accomplished. But he also conceded that it is possible for deck concrete encasing a skimmer assembly to be sufficient to stabilize the skimmer assembly even without taking any extra measures to accomplish a structural tie. There was no evidence that any building code would require a pool contractor to take these measures to accomplish a structural tie between the pool shell and skimmer assembly. Nor was there any evidence that a reasonably prudent pool contractor (as opposed to a professional engineer) would be expected to take these measures. Based on this evidence, together with all the other evidence taken as a whole, the Department did not prove that Ash was either incompetent or grossly negligent in not taking any extra measurers to accomplish a structural tie between the concrete pool shell and the skimmer assembly. Based on the evidence in this case, the contractor Dodd hired to pour the concrete deck was either incompetent or grossly negligent (assuming he was even a licensed pool contractor a fact not shown by the evidence.) He did not encase the skimmer assembly with the deck concrete, allowing it to "float" unprotected in the fill under the concrete deck. Settling of the fill could have caused the deck to settle and crack, moving the skimmer assembly and causing a small leak. Ash may have been able to prevent this by warning the contractor to be sure to encase the skimmer assembly with deck concrete when he poured the concrete deck. But there was no evidence that Ash had a duty to advise the other independent contractor Dodd hired or was responsible for the other contractor's incompetence or gross negligence. Ash's failure to advise the other contractor was not incompetence or gross negligence on Ash's part. Dodd has no other complaints about the pool Ash built for him. Priests' Complaint (Count II). On or about October 11, 1984, Ash contracted with Joseph and Rita Priest to build them a pneumatic concrete pool. The Contract included a warranty that the labor, materials and workmanship would be free of defects for one year and that the shell would be structural sound and capable of holding the water for ten years. Like Dodd, the Priests contracted with another independent contractor to install the concrete deck around the pool. Ash was responsible only for placement of decorative "river rock" on top of the deck. Ash finished his work in February 1985. Like Dodd, the Priests complained of water loss from the pool although the Priests noticed the water loss sooner than Dodd (approximately March, 1985). The water level was dropping approximately one-quarter inch per day more than it was dropping in a bucket used as a control. In response to the complaint, Ash sent his employees to the Priests' pool on several occasions. They found no leak at the skimmer. To determine whether the pool's "caretaker system" 1/ was leaking, Ash's employees plugged all but one pair of the caretaker heads. After waiting a period of days, they would try to see whether the rate of water loss changed. They tested all four pairs of caretaker heads on the bottom of the pool and the pair in the spa attached to the pool. No leaks could be found. They did not replace the last two (in the spa), and Mr. Priest had to replace them. As with the Dodd pool, the Department did not prove that the Priests' pool is leaking at all. The Priests continue to complain of water loss of approximately one-quarter inch per day, within the range of water loss from normal evaporation. As with the Dodd pool, a leak responsible for a small increment of water loss above water loss from normal evaporation would be very small and difficult to find, especially if the leak were in the caretaker heads or pipes under the pool leading to the heads. Now the Priests suspect a water leak at the filter. But the Department's expert witness could not find a leak there large enough to account for much water loss. The minor leak at the filter is a normal maintenance item for a pool as old as the Priests' pool. There was no evidence how long it has existed, and there was no evidence that the Priests ever told Ash there was a leak at the filter. The Priests now also complain that one of the caretaker heads does not re-seat properly. But this has nothing to do with the leakage complaint to which Ash is charged with not reasonably responding. Taken as a whole, the evidence did not prove that Ash committed misconduct or deceit by failing to make reasonable response to warranty service requests within a reasonable time, as charged. Nor does the evidence prove misleading or untrue representations, gross negligence, incompetence or fraud in connection with the Priests' pool, as charged. Poland Complaint (Count III). On or about December 9, 1981, Ash entered into a contract with James Poland to build Poland a pneumatic concrete pool and concrete deck. Poland contracted with another independent contractor to build a screen enclosure around the pool. Before construction began, one of Ash's employees asked Poland to sign an addendum to the contract for an additional $235 to pay for foundation footers required to comply with Lee County building code provisions for the screen enclosures. Before Ash signed the initial Poland contract on December 9, 1981, he was unaware of the Lee County Aluminum Code, adopted March 18, 1981. The code requires eight inch foundation footers for "aluminum additions." Another part of the code addresses "screen enclosures with screen roofs known to the industry as birdcage swimming pool enclosures." The language of the code is not explicit that screen swimming pool enclosures are required to meet the foundation requirements for "aluminum additions," and at first Lee County did not interpret the code that way. With a change of personnel in code enforcement, Lee County began to interpret the code that way, and screen swimming pool enclosures Ash had under construction began to fail building inspection for inadequate foundation footers. Ash inquired why and was told about the aluminum code and how it was being interpreted. Ash argued that the interpretation was erroneous but, failing to dissuade enforcement personnel, began to comply. As part of his compliance efforts, Ash had his employees try to secure the contract addendum from Poland. Poland refused to sign the contract addendum, insisting on an opportunity to verify that the additional foundation footers were indeed new building code requirements. There still is a dispute between the parties whether Poland ever agreed to pay the additional $235 after he verified that the footers were being required. (He never signed the contract addendum.) But, in any event, the evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct in connection with the additional $235 charge. 2/ There was some evidence that Ash did not in fact comply with the Lee County Aluminum Code, as he was told it was being interpreted, in his construction of the Poland pool deck. In two places the foundation footers were 6 and 7 inches - deeper than the four-inch normal thickness of a concrete pool deck but short of the eight-inch requirement. But Ash was not charged with failure to comply with the foundation footer requirement. He had no legally sufficient notice that he should be prepared to defend against that charge and was not prepared to defend against that charge. Therefore, no finding is made whether Ash complied with the Lee County Aluminum Code. Ash performed the Poland contract between approximately January 27 and February 26, 1982. In September, 1985, Poland began to notice that some of the tile Ash installed at the waterline around the perimeter of the pool was coming loose. As explained by the Department's expert witness, the concrete deck settled in places, cracking slightly and rotating over the fulcrum created by the wall of the concrete shell of the pool. The rotating action pulled up on the tile attached to the inside of the pool wall in places, loosening the tile. In all, less than 10 percent of the 77 foot perimeter of the Poland pool experienced problems with loose tile. The loose tile easily can be removed and replaced. The minor deck cracking and loose tile problems at the Poland pool are within the normal range for a competently constructed pool under normal conditions of ground settlement. The evidence did not prove that Ash improperly installed the pool deck or that he was incompetent or grossly negligent in the construction of the Poland pool and deck. Besides the loose tile and minor cracks in the concrete deck, the Poland pool had no apparent defects. There also was evidence that the Poland pool was finished with a coating of marcite on the inside surface of the pool shell which was mottled gray in color instead of white. Poland complained persistently about the marcite3 and insisted that Ash make it white. But the discolored marcite was a factory defect of which Ash had been unable to know before he used it. There is no way to make mottled gray marcite white. Ash tried to explain this to Poland but the customer would not be satisfied. Taken as a whole, the marcite evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct. Nor does the evidence prove any of those violations for failure to cure the marcite problem under warranty. First, as already stated, there was no cure. Second, Ash and Poland also had a running dispute whether Poland had paid the full contract price, including the additional $235 for foundation footers, so as to entitle him to any warranty repairs. In light of this genuine dispute, failure to do warranty work, if otherwise a reasonable request, still could not be found to be misconduct, fraud or deceit.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing the Amended Administrative Complaint that has been filed against Respondent, Wesley Ash, in these cases. DONE AND ORDERED this 9th day of December 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of December, 1986.
The Issue At issue is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what penalty should be imposed.
Findings Of Fact Petitioner, the Department, is the state agency charged with the duty and responsibility of regulating the practice of contracting pursuant to Chapters 20, 455 and 489. At all times material to the allegations of the Administrative Complaint, Mike H. Kargar, d/b/a Kargar Construction, Inc., was licensed as a Florida State Certified Building Contractor and a Florida State Certified Pool/Spa Contractor, having been issued license numbers CBC 37867 and CPC 52530 respectively. His licensure status for each license is designated as "Current, Active." The Department's records establish that at no time material hereto did Kargar Construction apply for or obtain a Certificate of Authority as a Contractor Qualified Business in the State of Florida. On or about July 14, 1999, Respondent, doing business as Premier Pools, entered into a contract with Ronald and Gina Steger (the Stegers) for construction of a residential swimming pool to be located at 466 Champagne Circle, Port Orange, Florida. The contract price was $26,469.00. Respondent was paid in full by the Stegers for the construction of the swimming pool at their residence. While Respondent verbally informed Mr. Steger about the Construction Industries Recovery Fund, the contract does not contain a written statement explaining the consumer's rights under the Construction Industries Recovery Fund. Respondent has constructed thousands of residential pools during his career. Respondent proceeded with the construction of the Stegers' pool in the same manner as with all other pools he constructed. That is, he reviewed the contract documents, visited the job site to inspect the site during the various stages of construction, and was in charge of scheduling. As is his typical practice, Respondent also had superintendents who oversaw the project and subcontractors who performed most of the actual work on the excavation and construction of the pool. Respondent visited the Stegers' job site at least twice. He went to the pool site before the pool was "shot." During that visit, he did not observe anything that raised concerns regarding the soil conditions that existed at the Steger residence. He inspected the Stegers' job site after the shell was poured and did not observe any problems. He also observed the control joints for the concrete for the pool deck. The spacing of the control joints at the Stegers' job site was the same as his company usually utilizes in constructing pool decks. Robert Fleming is the owner/operator of Fleming Excavating, which is in the business of excavating for swimming pools. He has been in the business of excavating pools for about ten years and has excavated between 5,000 and 6,000 pools. He and persons who work for him performed the excavation of the Stegers' pool. As is typical on a pool excavation job, Mr. Fleming performed what he refers to as "LDS" on the Stegers' pool. That is, layout, dig, steel, and be ready for inspection. He staked out the pool, determining its shape, then excavated the dirt. After the dirt was excavated, he and his workers put in the steel for inspection. In digging the Stegers' pool, Mr. Fleming did not encounter any unusual subsurface soil conditions to give him any indication that there would be problems for the pool in the future. About two weeks after the project was completed, Mr. Steger observed what he perceived to be a half inch rotation of the pool shell in the ground. When the pool was initially filled with water, the water level followed the grout line of the tile around the pool. After a couple of weeks, the water level against the pool tile furthest from the home was at a different level than the tile toward the area of the pool closest to the home. This was reported to Respondent. Mr. Steger then noticed a crack in the pool deck on the backside of the pool. He described the shape of the initial crack to be the same shape as the backside of the pool shell in the decking. Other cracks formed. One is evident where pieces of tile around the pool shell have come off at the place where the crack in the pool deck meets the pool shell. The cracking is all on the deck, not in the pool itself. A representative of Respondent's company went to the Stegers' home in March of 2000 and documented on a warranty form as follows: Southwest deck, [less than] 1/32 separation around the perimeter south of beam. Northwest near expansion tile needs to be regrout. Watch for further expansion northeast. Near expansion tile needs to be regrout. Watch for further expansion. Between December 1999 and March 2000, Mr. Steger made two other requests for warranty work. These conditions were corrected by Respondent and signed off as satisfactorily completed by Mr. Steger. Sometime in the year 2000, Respondent became aware of the cracking problems in the Stegers' deck. He went to the Stegers' home and met with Mr. Steger. He observed that the cracks were in a circular type of pattern following the pool shape. Respondent offered to repair the deck cracks by "v- ing" out the cracks and inserting a urethane 500 product to stop the cracks from coming through. Once that process was completed, Respondent proposed that he would then "respray and re-acrylic the affected area of the deck." Respondent has used this process numerous times to cover cracks in decks, and once it is used, the cracks do not show. Mr. Steger did not agree to Respondent's proposal to repair the cracking of the deck area as illustrated by his testimony at hearing: Mr. Kargar came out and told me that he would, in fact, grind out the concrete in the cracks themselves, fill them in with some sort of epoxy substance in order to mask the cracking. However, that does not address the original problem of the pool shell shifting and the deck moving away from the pool. So, no, I did not accept that as a solution to the problem. Richard Kushner is a civil engineer with a concentration in geotechnical engineering and construction engineering. He works for Universal Engineering Science (Universal). Mr. Steger called Universal which conducted an investigation as to why the pool deck was cracking. A field representative from Universal went to the Stegers' home and performed four manual auger borings into the soil to test the type and condition of the soil under the pool deck, ran density and compaction tests to see how tight the soils were underneath the pool deck, and observed the cracking and the cracking patterns in the concrete. Mr. Kushner did not personally go to the Stegers' as it is customary in the field of geotechnical and construction engineering to review data, do whatever analysis is necessary, and come to a conclusion using an investigative report. Regarding the cause of the pool deck cracking, Mr. Kushner had three concerns: the compaction of the soil underneath the concrete slab was less than 90 percent, whereas the industry standard is 95 percent; evidence of wood rot was found at one of the auger borings, indicating that the original soils were not well stripped and cleared of debris, such as sticks and roots; and insufficient spacing of control joints in the concrete. Mr. Kushner concluded that the contractor and subcontractors who constructed the pool deck were responsible for the cracking in the pool deck. Mr. Kushner acknowledged that two of the three concerns, i.e., the soil compaction and the evidence of organic debris, are circumstances that may cause future problems but were not the cause of the current problems with the deck cracking. Mr. Kushner also acknowledged that the pool cracking is a problem which is cosmetic or aesthetic in nature and that the cracks in the pool deck are not structural problems. Universal's investigation and Mr. Kushner's report relate exclusively to the pool deck, not to the pool shell or the subsoil conditions under the pool shell. Mr. Kushner was not aware when he wrote the report relied upon by Petitioner that there was an issue regarding whether the pool shell was shifting; was not involved in any discussions about the pool shell; and was not aware that the cracks in the pool deck follow the shape of the pool. Mr. Kushner acknowledged that any shifting of the pool shell could be caused by soil conditions underneath the pool shell and could be the cause of deck cracking that followed the shape of the pool. However, the investigation conducted by Universal and his report were exclusively related to the cracking of the pool deck and did not examine anything regarding the pool shell itself. As of July 18, 2003, the Department's costs of investigation and prosecution, excluding legal costs, totaled $384.63.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the Construction Industry Licensing Board enter a final order imposing a $100.00 fine to be deposited in the Construction Industries Recovery Fund for a violation of Section 489.1425, issue a notice of noncompliance pursuant to Section 489.119(6)(e), and require Respondent to pay $384.63 in costs of investigation and prosecution. DONE AND ENTERED this 22nd day of August, 2003, in Tallahassee, Leon County, Florida. S ___________________________________ BARBARA J. STAROS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 2003.
Findings Of Fact Based on the evidence presented, the following facts were found: At all times pertinent to this case, Respondent held two active contractor's licenses issued by the State of Florida, RP 0033354 and CP 015029. Respondent's current address is 1316 Hoffner Avenue, Orlando, Florida 32809. At all times pertinent to this case, Respondent owned the firm Family Pools and did business as a pool contractor under that name. At no time did Respondent ever qualify his firm, under whose name he did business, with the Florida Construction Industry Licensing Board (CILB). On some date not specified, in June, 1980, Alphonse J. and Pauline L. Rodier contracted with Family Pools to build a pool at their residence at 601 Michigan Avenue, Englewood, Sarasota County, Florida for a price of 6,700. The contract was signed by Respondent for Family Pools. The pool price was to include a screened enclosure and deck, and the entire package was to be completed by July 4, 1980. The pool was paid for by two checks from Coast Federal Sayings and Loan Association in Sarasota from the proceeds of a home improvement loan and by a final check in the amount of $900 from the Rodiers, direct, on October 13, 1980. Respondent subcontracted the pool enclosure to Climatrol Screen Company of Enqlewood, Florida, for $2,065 but failed to pay this subcontractor. As a result, on November 26, 1980, Climatrol filed a lien against Rodier's property which was released only when the Rodiers paid an additional $790 which had not been satisfied by the Respondent. Respondent had satisfied part of the debt to Climatrol by relinquishing title to a truck he owned. On July 3, 1980, Family Pools contracted with Elmer J. and Carla T. Taylor, of Bunnell, Florida, to build an above-ground pool on their property for $4,800.00. The pool was to have a one year warranty against defective parts and a 20-year prorated replacement policy. According to the contract, the pool price included the pump, liner, filter, and walls, along with all other parts. The pool was constructed by employees of Family Pools about three or four weeks after the contract was signed. Not long after the pool was completed and filled, Mr. Taylor noticed that the vinyl liner was protruding out beneath the bottom of the metal retaining wall. His calls to Family Pools were never answered by Respondent with whom he asked to talk and repair work on this problem was not accomplished by the Respondent or Family Pools. Mr. Taylor had to do the work himself and Family Pools would not honor the warranty. Respondent offers the completion certificate executed by the Taylors on August 21, 1980,as evidence the pool was installed properly and the Taylors were satisfied. Mr. Taylor indicates he signed that certificate in blank under pressure from Respondent's agent, who cajoled him into doing it on the basis that if he did not, Family Pools could not be paid by the finance company under the installment sales contract. Also, during the period of the one year warranty, the pool pump burned out. Mr. Taylor had to replace that and pay for it himself, as the warranty was not honored. Respondent contends only a 90-day warranty on the pump, but that appears nowhere in the contract, which, in its description of the pool covered by the one year warranty, includes the pump. On August 29, 1980, Family Pools contracted with Janice Conover to build a swimming pool at her home in Venice, Florida for $4,780. The pool was to be completed approximately 30 days after excavation at the site. Between August 29, 1980, and December, 1980, Ms. Conover paid Family Pools a total of $4,741 by checks which were endorsed by "P. Vescera d/b/a Family Pools" or "Pasquale M. Vescera." On October 2, 1980, Respondent pulled a permit No. 7330- N from the Sarasota County Building Department, in his own name, to construct Ms. Conover's pool. In February, 1981, when the pool was only about fifty percent complete, Respondent ceased work on Ms. Conover's pool without giving her any notice or reason therefor. When Respondent stopped work, he had only dug the hole for the pool. The liner had been delivered but was not installed. The braces were there but not affixed, notwithstanding Ms. Conover had paid almost in full for the pool. As a result, she contracted with Richard Thompson, Respondent's former employee, to finish the work Respondent had started because at this point she could not find the Respondent. Thompson installed the brackets, the liner, and the deck. She had to pay extra for the pump, the chemicals, and the sweep--all of which, except for the sweep, she had paid for when she paid Respondent's price. Respondent never returned to complete Ms. Conover's pool. On July 7, 1980, Family Pools contracted with Robert A. and Florence L. Peipher to build a pool at their property in Port Charlotte, Florida, for a price of $6,900. Between July 7 and November 28, 1980, the Peiphers paid Family Pools, by checks, the sum of $6,905. All checks-were endorsed for deposit, "P. Vescera d/b/a Family Pools." The pool price was to include a screened pool enclosure and in September 1980, Family Pools contracted with Climatrol to build the screened enclosure for Peipher's pool for $1,807. Respondent and Family Pools failed to pay Climatrol for the enclosure and as a result, Climatrol filed a lien against the Peipher's property for $1,807 which was satisfied on March 9, 1981, by the Peiphers who paid Climatrol the amount owed. On March 2, 1981, the Peiphers filed a complaint against Respondent with the Contractor License Division of the Charlotte County Building Department because of Respondent's failure to pay Climatrol and the resultant cost to them. As a result of this complaint and the subsequent investigation into the allegations, the matter was referred to the Charlotte County Building Board which, at its meeting on May 7, 1981, after notice to Respondent, voted to revoke Respondent's permit privileges in Charlotte County until he made restitution to the Peiphers and to notify the State of Respondent's actions requesting state action against his license. Respondent suffered severe financial setbacks just about the time of these incidents. He was hospitalized for a period of five or six weeks and upon his return to his business found that he had been "robbed" of approximately $50,000 worth of fully paid for inventory. When he reported the shortage to the local law enforcement officials, they told him that since there was no evidence of a breaking in, they could do nothing about it. In addition, he could not recover from his insurance company for the same reason. There was no evidence other than Respondent's sworn testimony that there was a shortage or that he reported the loss to either agency. Respondent has been in the pool business in Florida for five years and in New Jersey for 32 years before that. He feels the cause of his problem is the fact that he trusted the people who worked for him who took advantage of him. During the entire period of time he was in business in Florida he took no money from the company for his personal use, living instead on income from a mortgage he owned in New Jersey. He subsequently filed for bankruptcy on March 9, 1981. The $15,000 in current accounts receivable he had on the books at that time was utilized in the bankruptcy proceeding to pay creditors. He got-none of it. He is now working in Orlando, Florida, for a pool rehabilitation company owned by his wife and her father. Respondent alleges that on July 15, 1980, he paid Richard Thompson $1,100 to complete work started on several pools, including that of Ms. Conover. Review of the prior findings of fact, however, shows that the contract with Ms. Conover was not entered into until approximately 45 days after Respondent supposedly made this payment to cover the work left undone on her pool. In light of that development, I find his contention completely without merit or basis in fact. Respondent admits that people were hurt as a result of his actions and he regrets this. However, he claims these few incidents are insignificant when compared with the over 500 satisfied customers he alleges he has served over the years. Finally, Respondent contends that early in 1980, after being advised that he had passed the test to be a certified pool contractor, he wrote to Petitioner and, after advising how he was registered and doing business, asked if he needed to make any changes in license registration. He did in fact do this and received no reply. He thereafter assumed he was acting correctly in that regard and that appears to be a justified assumption.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That Respondent's license as a contractor be suspended for two years and that he be assessed an administrative fine of $500. RECOMMENDED this 16th day of May, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Pasquale M. Vescera 1316 Hoffner Avenue Orlando, Florida 32809 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
Findings Of Fact Melnikoff is the holder of a certified pool contractor's license, having been issued license No. CP C032540. Melnikoff used this license to qualify Ken-Mel Enterprises and license no. CB C029067 was issued to Melnikoff qualifying Ken-Mel Enterprises. Ken-Mel entered into a contract with John and Edythe Milton to construct a residential pool at 7336 Pineville Drive, Jacksonville, Florida. Melnikoff applied for a building permit with the City of Jacksonville to construct the pool for the Miltons. His application included a set of plans and a site plan to be approved by the City of Jacksonville. The City of Jacksonville issued a building permit and provided an inspection sign-off card to be placed at the residence where the pool was to be constructed. Melnikoff and Ken-Mel constructed the pool and were paid in full. Melnikoff failed to request or obtain any inspections of the pool construction. This is a violation of the City of Jacksonville Building Code, Section 320.504. The pool is constructed in such a way that it is flawed, deficient and hazardous. Specifically, the water slide is hooked to a potable water system and to the hot water, which is both a serious code violation and a serious and hazardous condition. The water slide is positioned improperly and attached incorrectly, such that there is a danger of injury and this is a hazardous condition. The marcite is very rough and has started to peel away from the gunnite. The marcite is stained from the finish of the pool deck. The slurry from the gunnite and pool deck is buried near the pool and is improperly disposed of. Persons are mildly shocked when touching the railing in the pool, indicating that the pool is not properly bonded, which is a hazardous condition. The pool is not level or symmetrical and there are many imperfections in the continuous curve of the wall. Steel reinforcing bars are actually protruding through the concrete near the top of the pool. Building Code requires that there be a minimum coverage of 1 1/2" of concrete. The ceramic tile is falling off the wall and it is a very poor ceramic tile job. The expansion joints are improperly placed. The main drain cover has not been fastened down, which is a very dangerous situation and a code violation. There is no means or plan for discharging water from the pool, in violation of code. Part of the deck drain is under the slab of the Milton's house which is a serious problem. The pool is deeper than the plans indicated, in violation of the building code. The pool deck is very rough in places, does not drain away from the pool, and is cracked from improper compaction and improper placement of expansion materials. All of these defects and hazardous conditions establish that Melnikoff was grossly negligent and incompetent in the construction of this pool.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order finding Steve A. Melnikoff guilty of the violations charged and revoking Melnikoff's license as a certified pool contractor. DONE and ORDERED this 29th day of June, 1988, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1988. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 88-0567 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the Petitioner in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Department of Professional Regulation, Construction Industry Licensing Board 1. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1); 2(2); 3-5(3); 6(4); 7(5); and 8 & 9 (6) COPIES FURNISHED: John O. Williams, Attorney at Law 1343 E. Tennessee St. Tallahassee, Florida 32308 Steven A. Melnikoff 710 Rosedale Drive Stephens City, VA 22655 Tom Gallagher, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
Findings Of Fact Martin R. McAndrew is a licensed general contractor and licensed pool contractor holding general contractor's license number RG 0020560 and pool contractor's license number RP 0024861. Martin R. McAndrew was provided notice in accordance with the applicable rules and statutes of the formal hearing to consider the allegations of the administrative complaint filed against him by the Florida Construction Industry Licensing Board. Ray Dowell identified a notice of violation served on McAndrew by the Florida Construction Industry Licensing Board which was received into evidence as Exhibit 1. This notice of violation related to the construction undertaken by McAndrew for Lynn McMillan. Melvin C. Huebschman entered into a contract with McAndrew for the construction of a pool. The contract price for the pool was $5,000.00. Huebschman paid McAndrew $2,000 in two payments. The first payment was in the amount of $300.00 to cover the cost of transportation of the pool materials to Pensacola, Florida. The second payment in the amount of $1,700.00 was for the first phrase of construction on the pool. Subsequent to receiving payment McAndrew provided no materials or labor pursuant to the contract. Huebschman talked with McAndrew concerning completion of the work pursuant to the contract and McAndrew failed to perform under the contract throughout the spring and summer of 1977. In August, 1977, Huebschman wrote McAndrew advising him that it had been over ninety days since they entered into the contract and McAndrew had not performed any services pursuant to the contract. Huebschman gave McAndrew thirty days within which to commence work. McAndrew did not respond to this notice. McAndrew did not return any portion of the $2,000.00 paid to him by Huebschman. Lynn McMillan entered into a contract, identified as a portion of Exhibit 4, with McAndrew. This contract called for the construction of a pool for a contract price of $5,800.00. Pursuant to that contract, McMillan paid to McAndrew $4,350.00. Subsequent to payment of the third draw, McAndrew failed to complete the job. The last work performed by McAndrew on this construction project was on May 17, 1977. Prior to May 17, 1977, all materials for completing the pool were on the site and installed. Before abandoning the project, McAndrew removed from the building site all portions of the pool construction except the poured concrete and vinyl lining. McMillan subsequently entered into a contract with Surf Side Pools for the completion of the pool. The contract price was $1275.00, which included $800.00 for equipment and materials necessary to complete the pool. In addition, McMillan found it necessary to pay $230.00 to O'Brian Enterprises to remove stumps and spoil left on the construction project by McAndrew. McMillan also paid $200.00 to Warrick Electric Company to satisfy a claim by Warrick for materials and labor provided by Warrick to McAndrew. Finally, American Ready Mix Concrete filed a claim of lien in the amount of $436.80 against the property of Lynn McMillan for labor and materials provided under the contract with McAndrew which McAndrew did not pay. On May 27, 1977, McAndrew wrote a letter to McMillan advising that he would like the opportunity to finish the pool and was invited to do so. However, McAndrew did not return to the construction site or provide any further labor or materials pursuant to the contract. Sarah White Witt entered into a contract with McAndrew for the construction of a pool at a contract price of $4,500.00. Witt paid McAndrew $500.00; however McAndrew did not finish the pool construction. Subsequently, Witt was advised by the materialmen and labors of various liens against her property totalling $2,200.00. Daryl Jernigan, electrical and pool inspector for Escambia County, inspected the work done by McAndrew on the McMillan pool. He found that the pool had been filled with water but that the equipment necessary to recirculate and chlorinate the water had been removed from the pool, thereby permitting the water to stagnate. This inspection was conducted in June, 1977. Prior to that time, Jernigan had found it necessary to order work on a pool begun by McAndrew halted because McAndrew had failed to acquire a building permit prior to commencing construction.
Recommendation Based upon the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that Florida Construction Industry Licensing Board revoke the licenses of Martin R. McAndrew as a general contractor and as a pool contractor, and further fined a sum of $500.00. DONE and ORDERED this 24th day of May, 1978, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: J. K. Linnan Executive Director Florida Construction Industry Licensing Board P. O. Box 8621 Jacksonville, Florida 32211 Michael E. Egan, Esquire Attorney at Law 217 South Adams Tallahassee, Florida Martin R. McAndrew 3313 N. 17th Avenue Pensacola, Florida 32502
Findings Of Fact Respondent is the holder of currently active General Contractor's license No. RG-0023888. On January 18, 1977, Norwood W. Hope (hereinafter "Developer") entered into a contract with Respondent for the construction of a commercial swimming pool. Respondent was to have been paid the amount of $43,346.40 under the contract for construction of the pool. The contract amount was to be paid pursuant to a five-stage draw schedule as follows: 1. Framing and steel draw paid $10,836.60 2. Gunite draw paid 10,836.60 3. Mancite draw 7,224.40 4. Equipment set draw 7,224.40 5. Final approval draw 7,224.40 Respondent made application for an Alachua County building permit for the swimming pool project on February 23, 1977. The permit application was approved on February 25, 1977, and a building permit was issued. Thereafter, the project received Alachua County approval on a temporary power pole inspection on June 1, 1977. An interim inspection of the property was made by Alachua County officials on November 7, 1977, with no deficiencies noted. A final inspection on the electrical work on the project was made, with satisfactory results, on November 8, 1977. The Alachua County Building Code, by incorporation of the 1973 Southern Standard Building Code, 1974 Revision, provides, in part, as follows: 108.2--INSPECTIONS REQUIRED The Building Official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building or structure upon completion, prior to the issuance of the Certificate of Occupancy, as required in Section 109. * * * (c) The Building Official upon notifica- tion from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit bolder or his agent wherein the same fails to comply with the law: * * * Final Inspection: To be made after the building is completed and ready for occupancy. (Emphasis added). The contract entered into on January 18, 1977 between the Developer and Respondent called for Respondent to construct the swimming pool according to the plans and specifications admitted into evidence as Petitioner's Exhibit No. 1. Associated construction, including construction of concrete pool decking, a pumphouse and a fence surrounding the swimming pool site were either completed by the Developer or by other sub contractors. By invoice dated October 12, 1977, Respondent requested a final draw on the project in the amount of 87,000, which, if paid, would have left only $224.40 unpaid under the contract. This draw request indicated that a balance due for extra time and materials would be billed ". . . upon acceptance of total pool." (Respondent's Exhibit No. 4). On October 25, 1977, the Developer paid $6,000 of the $7,000 requested to be paid by Respondent's invoice of October 12, 1977. The Developer contested Respondent's expressed intention to bill for additional time and material, asserting that the Developer had not approved any additional sums for extras. In remitting the $6,000 payment to Respondent, the Developer indicated that "[t]his leaves a balance on our account of $1,224.40, which will be paid upon checking out the pool." (Respondent's Exhibit No. 2). (Emphasis added.) An invoice for back charges on the swimming pool project in the amount of $274 was forwarded to the Developer by Respondent by invoice dated November 8, 1977. In addition, on November 8, 1977, Respondent also invoiced the Developer for a final draw on the project in the amount of $1,224.40. At some time after notification from the Developer's representatives that tile targets in the racing lanes of the pool were improperly located, Respondent returned to the job site after November 9, 1977 to relocate the targets. Respondent performed this work as a result of a written request from the Developer dated November 9, 1977. Respondent completed primary construction of the pool prior to submission of the final draw request of October 12, 1977. At that time, back- filling around the exterior of the pool structure preparatory to the pouring of the concrete pool decking had not been completed. Although by October 12, 1977, Respondent had removed much of the excess dirt and debris from around the edges of the pool. There were still areas of exposed piping which would, in due course, be covered with back-fill and tamped by the decking subcontractor. Respondent did not attempt to back-fill or tamp any areas around the pool's piping system. At some time subsequent to October 12, 1977, which date is not clearly reflected in this record, a separate sub- contractor completed back-filling work around the pool, and poured the concrete decking. Neither the Developer nor his subcontractor advised Respondent that the back-filling had been accomplished and that the deck was to be poured. Prior to October 12, 1977, Respondent "pressure tested" the pool's piping system, and determined that the pool would hold water at a level above its scum gutters. The results of this testing indicated that, at least as of October 12, 1977, there was no leakage from the pool. Standard practice in the pool construction industry dictates that a minimum of three pressure tests be made of a pool's piping system during the course of construction. The first of these tests should occur immediately after installation of the pipes, and a second test should be performed immediately before final back-filling to cover the pipe system. A final pressure test should be conducted after tamping of the fill and prior to the pouring of concrete for the pool deck. The obvious purpose of this system of pressure testing is to discover any water leaks before concrete pool decking is poured to avoid having to cut out sections of the concrete in order to locate leaks. Because the Developer and his subcontractor failed to notify Respondent of further work being done on the pool. Respondent was unable to perform a pressure test either after back-filling was completed, after the back- fill had been tamped and before the concrete deck was poured. By letter dated January 17, 1978, Respondent was furnished by the Developer with a "punch list" indicating several areas of deficiency that needed to be corrected in the pool. In that letter the Developer requested that Respondent complete the necessary work within seven days. The Developer forwarded a second letter to Respondent dated February 23, 1978 advising Respondent that the punch list items had not been corrected, and urging Respondent to complete the work described in the punch list as soon as possible. From receipt of the punch list in January of 1978 through the middle of March, 1978 Respondent had workers on the job intermittently making the corrections indicated in the punch list. Respondent satisfactorily corrected fifteen of the eighteen items listed as defective n the punch list. Some of the items were repaired by other subcontractors. Respondent had difficulty obtaining some items of equipment, which he was required to back-order. When the back-ordered equipment was slow in arriving, the Developer opted to obtain these items from a source other than Respondent. Respondent replaced a defective pump associated with the pool construction at some time subsequent to January 18, 1977. The last work performed by Respondent on the pool project occurred some time between March 10 and March 16, 1978. At no time thereafter was Respondent ever advised by the Developer that any work performed under the contract was either unsatisfactory or incomplete. The pool received a final State of Florida, Department of Health and Rehabilitative Services inspection on July 13, 1978, at which time all necessary permits for operation of the pool under applicable regulations were issued. Respondent at no time requested that Alachua County officials come to the job site to conduct the necessary final inspection of the project, nor did he advise the Developer of the necessity to do so. At some time during 1979, subsequent to the completion of the swimming pool project, the Developer discovered that the pool was losing water at a rate of approximately 2,100 gallons per day. During this period, the water level inside the pool would drop to a level equal to the piping running around the exterior of the pool shell and under the pool decking. When the Developer was unable to ascertain the cause of the leak, an outside subcontractor was hired to check the pool. This sub- contractor performed pressure tests on the pool's piping system in an attempt to determine whether the leakage was occurring through the pipes. These tests apparently showed no leakage through the piping system. The Developer then caused the concrete decking around the edge of the pool to be removed in order to more closely inspect the interior piping. At this point it was discovered that there existed flaws and breaks in the neoprene piping surrounding the exterior shell of the pool. After repairs to the damaged piping, the pool decking was repoured and there has been no subsequent leakage problem in the pool. The Developer incurred expenses in the amount of $2,288 in removing the decking around the pool and repairing the neoprene piping. Because of the fact that several subcontractors in addition to Respondent worked in the pool area during construction of the pool project, it is impossible on the basis of this record to determine the cause of the damage to the neoprene piping. Respondent's testimony is uncontroverted that pressure testing performed prior to the conclusion of primary work on the pool in October of 1977 showed no leakage through the pool's piping system. Further, at the conclusion of the primary work in October, 1977, much of the pool's piping system was left exposed and could have been damaged either by the Developer's own workers or by employees of other subcontractors in the course of back- filling and tamping fill material preparatory to pouring concrete decking. The Developer's failure to advise Respondent of the schedule for back-filling, tamping and pouring of concrete deprived Respondent of an opportunity to properly pressure test the piping system at appropriate stages of construction. Respondent has submitted proposed findings of fact for consideration by the Hearing Officer. To the extent that those proposed findings of fact are not incorporated in this Recommended Order, they have been rejected as being either irrelevant to the subject matter of this proceeding or as not having been supported by the evidence.