Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILLIP WHITAKER, JR., 87-005053 (1987)
Division of Administrative Hearings, Florida Number: 87-005053 Latest Update: Feb. 29, 1988

Findings Of Fact The Petitioner is the Department of Professional Regulation. The Respondent is Phillip Whitaker, Jr., holder of certified pool contractor license number CP-C008325 at all times pertinent to these proceedings. He is the qualifying agent for the business known as Sunshine State Pools pursuant to requirements of Chapter 489, Florida Statutes. He is responsible for actions of that business relating to construction of the swimming pool which is the subject of this proceeding. His address of record is Miami, Florida. The customer, Ken Gibson, signed a contract with Sunshine State Pools on September 15, 1986. The contract called for construction of a residential swimming pool at 15840 S.W. 155th Avenue, Miami, Florida. The total contract price was $12,700. Testimony adduced at hearing establishes that Sunshine State Pools completed the layout of the customer's swimming pool and the excavation of soil from the proposed pool site by October 1, 1986. These tasks were accomplished under the Respondent's supervision. Metropolitan Dade County issued a building permit for construction of the swimming pool in response to a permit application bearing the signature of Phillip E. Whitaker. The permit and application are both dated October 10, 1986. At hearing, the Respondent acknowledged that initiation of construction prior to pulling the permit and termed this action an "oversight." Based on the candor, demeanor and experience of the Respondent, his explanation of the failure to timely obtain the construction permit is not credited. Initiation of construction for a swimming pool prior to obtaining permits constitutes a violation of part 301.1(n), of the South Florida Building Code and, by stipulation of the parties at hearing, the building code of Metropolitan Dade County. The Respondent was responsible for supervision of the actual pool shell construction. After completion and removal of the wood forms used in the process, steel rods or "rebar pins" required as support during the construction process were not removed. These rods extended some distance above the ground and posed a substantial hazard to Respondent's children while playing. Finally, the steel rods were removed by the customer a week after he requested the Respondent to remove them. Respondent admitted some of these reinforcements could have been left by his subordinates. Respondent admits responsibility for the "back fill" process completed on October 25, 1986. This was originally a responsibility of the customer under the contract as the party responsible for deck construction. The "back fill" process consists of compacting loose soil between the outside of the pool walls and surrounding earth by use of special tamping or pounding equipment. Under terms of the contract, the customer was responsible for construction of a sizeable two part deck surrounding at least sixty percent of the pool's circumference. There now exists a substantial height difference between the coping surrounding the perimeter of the pool and the deck or patio surface. The coping is elevated above the top of the patio approximately two to four inches. As adduced from testimony of Ben Sirkus (stipulated by both parties as an expert in swimming pools and swimming pool construction), coping along the top of the pool walls consists of flagstone rock in conformity with the contract terms. Some of the rocks are cracked. The rocky edge of the coping extends over the pool wall and has a dangerously sharp edge. The sharp edge of the coping overhang could have been avoided by cutting the flagstone coping smooth prior to installation, the acceptable practice among pool contractors. The bottom step to one set of the pool steps has a hazardous 19 inch riser as opposed to the 12 inch distance required by the building code. No hand rail is present. Hollow space under some of the coping stones are the result of either improper installation, dirty cement or sinking of the deck as a result of improper "back filling" upon completion of the pool shell. On one occasion, Respondent admitted responsibility for deficiencies in the pool coping to an employee named Rick Miro. The Respondent further stated to this employee that he intended to do nothing about the problem. Respondent was present during some, but not all, of the coping installation. The "skimmer," the apparatus by which debris is cleared from the pool water, is inoperable as a result of faulty construction of the pool. The failure of the Respondent, who admits to successful completion of approximately 2500 pools with only three complaints, to properly supervise job site activities was the major cause of the pool deficiencies identified at hearing.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be placed on probation for a period of two years upon such terms and conditions as may be determined by the Construction Industry Licensing Board and assessed an administrative penalty in the amount of $1500. DONE AND RECOMMENDED this 29th day of February, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5053 The following constitutes my specific ruling on proposed findings of fact submitted by the parties. Petitioner's Proposed Findings Included in finding 2. Included in finding 3. Included in finding 4. Included in findings 5, 6 and 7. Included in findings 5 and 6. Included in finding 8. Included in finding 10 with exception of hearsay statement. Included in finding 11.1 Included in finding 12. Included in finding 11. Included in finding 11. Included in finding 11. Included in finding 11. Rejected as unnecessary. Rejected as unnecessary. Included in finding 11. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark D. Press, Esquire 2250 Southwest Third Avenue 5th Floor Miami, Florida 33129 William O'Neil General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 =================================================================

Florida Laws (3) 120.57489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STUART L. REISE, 87-003955 (1987)
Division of Administrative Hearings, Florida Number: 87-003955 Latest Update: Sep. 19, 1988

The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.

Florida Laws (4) 120.57489.105489.119489.129
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs MICHAEL E. SEAMON, 16-002845PL (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 23, 2016 Number: 16-002845PL Latest Update: Mar. 29, 2017

The Issue Whether Respondent practiced beyond the scope of his certified commercial pool/spa contractor’s license and proceeded on a job without obtaining applicable local building department permits and inspections, as alleged in the Amended Administrative Complaint and, if so, the nature of the sanctions to be imposed.

Findings Of Fact Petitioner is the state agency charged with the licensing and regulation of the construction industry, including pool and spa contractors and electrical contractors, pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. At all times material to the allegations in the Administrative Complaint, Respondent was licensed as a commercial pool/spa contractor in the State of Florida, having been issued license numbers CPC 05661, 1457406, and 1458031. Respondent was the primary qualifying agent of Cox Building Corporation, d/b/a Cox Pools (Cox Pools). Respondent has been registered, certified, or licensed as a swimming pool contractor since 1978. Over the course of his almost 40 years as a swimming pool contractor, Respondent has replaced thousands of pool lights and pool pumps. He believed that the replacement of pool equipment, which he understood to include pool lights, was within the allowable scope of work as a swimming pool contractor. On or about September 12, 2014, Cox Pools entered into a contract with John Patronis to replace four pool light fixtures, a booster pump, and other miscellaneous services for $4,681.17 at the Subject Property. The Subject Property falls within the jurisdiction of the Bay County Building Department. Respondent did not obtain an electrical permit for replacing the pool light fixtures at Subject Property. Mr. Carnley testified that the Bay County Building Department requires that pool light replacement be performed by a licensed electrician, and with a county-issued electrical permit. The permit must be obtained by an electrical contractor or a homeowner. Bay County would not have issued a permit to Respondent, because he was not an electrical contractor. The Bay County Building Department also requires an electrical permit for the replacement of a circuit breaker in the electrical box serving a swimming pool. A pool contractor is not authorized to replace circuit breakers. No permits were obtained to replace circuit breakers at the Subject Property. On September 15, 2014, during the course of replacing the pool light fixtures, an employee of Cox Pools, Joshua Cook, was electrocuted. The precise cause of the electrocution was not established, though no plausible basis exists for it being related to anything other than the replacement of the pool lights. After a period of several days following the accident involving Mr. Cook, Respondent returned to the Subject Property to complete the job. He personally went into the pool, put the light in the fixture and screwed it in, and left. The light was thereafter wired and energized by a Cox Pool service technician. Given the circumstances, Mr. Patronis was not asked to complete payment for the services performed. Nonetheless, it is clear that, but for the accident, Mr. Patronis would have been expected to pay for the services for which he contracted. The photographic evidence in this case demonstrates that between September 15, 2014, and some indeterminate time in 2016, a circuit breaker was replaced in the electrical box serving the Subject Property’s pool. The circuit breaker that existed on September 15, 2014, was a ground-fault circuit interrupter (GFCI). By 2016, the GFCI has been replaced with an arc-fault circuit interrupter (AFCI). Had Bay County performed an inspection of the electrical box with the AFCI, it would not have passed inspection. Respondent testified that he did not change the circuit breaker, that Cox Pools keeps no inventory of circuit breakers, and that service technicians do not carry circuit breakers on the trucks. Respondent acknowledged his understanding that replacing a circuit breaker is a job for an electrical contractor. At some time “recently,” Williams Electric was called to the Subject Property, at which time Mr. Williams “swapped out a breaker or two that was an incorrect type of breaker for the application.” Mr. Patronis was not clear whether an arc breaker was replaced with a ground breaker, or vice versa. Pool lights are sealed units. The light and its power cord come as a single unit. To replace a pool light, the main circuit breaker at the swimming pool sub-panel is turned off. The wires to the existing light are disconnected (unscrewed) from the circuit breaker. A lead is tied to the end of the wire. The light fixture is removed from the pool opening, and the wire is pulled through the existing conduit from the pool side. When the old fixture and wiring unit has been removed, the lead is removed from the end of the old unit’s wire, tied to the wiring of the new light, and drawn back through the conduit to the circuit breaker box. The new light is screwed into the fixture, and then energized by connecting the wires back into the existing circuit breaker. The point of connection of the light to the circuit breaker is the “load side” of the circuit. The experts who testified in this proceeding were all competent and qualified in their fields, and had served in leadership positions with the CILB (Mr. Weller, Mr. Del Vecchio, and Mr. Lenois), the Electrical Contracting Licensing Board (Mr. Tibbs), or the Florida Swimming Pool Association (Mr. Garner and Mr. Pruette). However, despite the relative simplicity of the statutes at issue, their opinions as to the allowable scope of work under a swimming pool contractor license were at odds. Respondent acknowledged, and the evidence in this case establishes, that electrical work associated with new pool construction is a task that is within the scope of work of an electrical contractor. Initial construction involves substantial work in bringing power from the main residential panel to the new pool panel, installing a junction box and circuit breakers, installing the wiring, and performing other electrical work of significantly greater complexity than that involved in the installation of equipment into a pre-constructed electrical system, which involves only the disconnect and reconnect of wires to the load side of a circuit breaker. As discussed by Mr. Lenois, a pool contractor can contract for the entire pool, but cannot self-perform the electrical components pursuant to section 489.113. As to the replacement of existing equipment, Petitioner’s experts testified that pool light fixtures differ from other pool-related equipment, e.g., pool pumps, in that the light fixtures have direct contact with the water, whereas other components do not. Lights are changed out in a submerged condition, which makes them extremely dangerous. As stated by Mr. Weller, “the whole area of electricity around pools gets complicated, between the bonding, the grounding, and all the other stuff.” It was Mr. Weller’s opinion that, although pool contractors can contract for pool light replacement, they cannot self-perform the work. Rather, the electrical work involved in replacing pool light fixtures should be subcontracted to an electrical contractor because “you can make mistakes in plumbing, and you can make mistakes in other areas, but with electricity, it's pretty non-forgiving, especially if you're around water.” Mr. Lenois distinguished pool lights, which he characterized as accessories since all pools do not have them, from pool equipment, which includes pumps and filters, heaters, specialty filters, and salt generators, which are mounted at the pump and filter area. Respondent’s experts were uniform in their opinions that the act of disconnecting and reconnecting pool lights, as well as other pool equipment, at the load side of a breaker does not constitute electrical contracting. Mr. Pruette testified that disconnecting and connecting a pool light at a circuit breaker is not a difficult or complex task, and can be easily performed with a little training. Mr. Del Vecchio testified that the disconnection and connection of pool lights at the circuit breaker is no different than that performed by a plumber in replacing a hot water heater, or an air-conditioning contractor in replacing a piece of air-conditioning equipment. Almost all of the experts either replaced pool lights as part of their routine scope of work or knew of pool contractors who did so, a practice that appears to be commonplace. Furthermore, several of the witnesses worked in areas of the state in which county building officials did not require permits, electrical or otherwise, for the replacement of pool lights, though the evidence in that regard was generally hearsay. Mr. Lenois, who testified on Petitioner’s behalf, stated his opinion that reasonable people could differ as to the meaning of the statutory language placing the “installation, repair, or replacement of existing equipment” within the scope of work of a pool/spa contractor. The issue of the extent to which electrical work is subsumed within the statutory scope of work of a pool/spa contractor of “installation, repair, or replacement of existing equipment” has been the topic of considerable discussion in the industry. In that regard, the Florida Pool and Spa Association has filed a Petition to Initiate Rulemaking with the CILB seeking, among other things, to “clarify[] the scope of a certified pool contractor’s license to include the installation, repair, and replacement of pool equipment, up to and including the electrical connection on the demand side of the power source.” There was no evidence as to the disposition of the petition. Respondent argued that Florida Administrative Code Rule 61G4-16.001(9), which establishes that five percent of the written certification exam for commercial pool/spa contractors is to cover “electrical work,” is evidence that electrical work is within the scope of work for a pool contractor. Electrical work associated with pool construction includes grounding for the pool shell itself. Thus, a degree of knowledge of basic electrical work and codes would be warranted, regardless of whether equipment electrical connections are within the scope of work for a pool/spa contractor. The parties introduced a series of DBPR-approved course outlines and instructor applications for a three-hour class, sponsored by the Florida Pool and Spa Association, entitled “Basic Electricity and the NEC [National Electric Code] for Swimming Pools,” and a one-hour class, sponsored by the Florida Pool and Spa Association, entitled “Basic Electrical Requirements for Pools.” The course outline prepared by the Florida Pool and Spa Association for each of the approved courses provides, in bold font, that: Instructor is aware that electrical work does not fall within the scope of work of licensed pool/spa contractors. No instruction on how to perform electrical work will take place. Course will provide much needed understanding of the basics of electricity as well as those aspects of the NEC as they pertain to pools and spas. Instructor will also emphasize the importance of using a licensed electrical contractor to perform required work.

Recommendation Upon consideration of the facts found and conclusions of law reached, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order finding that Respondent violated section 489.129(1)(o), Florida Statutes, as alleged in Count One; and sections 455.227(1)(o) and 489.129(1)(c), Florida Statutes, as alleged in Count Two, but only as that count pertains to the replacement of pool lights. It is further recommended that: Respondent be subject to a fine of $1,000 for a first violation of section 489.129(1)(o); Respondent be subject to a fine of $4,000, and that Respondent’s commercial pool/spa contractor licenses be subject to a period of probation for two years for a first violation of section 455.227(1)(o) and section 489.129(1)(c); and Respondent be required to complete an approved, live seven-hour continuing education course, in addition to any otherwise required continuing education, with an emphasis on chapter 489 and the rules enacted pursuant thereto. DONE AND ENTERED this 5th day of October, 2016, in Tallahassee, Leon County, Florida. S E. GARY EARLY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of October, 2016.

Florida Laws (15) 120.52120.56120.565120.569120.57120.6817.00120.165455.227455.2273489.105489.113489.117489.1195489.129 Florida Administrative Code (1) 61G4-18.001
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WESLEY ASH, 86-002642 (1986)
Division of Administrative Hearings, Florida Number: 86-002642 Latest Update: Dec. 09, 1986

Findings Of Fact Respondent, Wesley Ash, currently holds license number CP C015871 issued by the Construction Industry Licensing Board to authorize Ash to engage in the pool contracting business. Dodd Complaint (Count I). Respondent, Wesley Ash, doing business as Wada Pools, Inc., contracted with Jerry Dodd on or about June 17, 1981, to build a pneumatic concrete pool with skimmer and recirculation system. The contract did not include installation of the concrete deck around the pool. Dodd decided to contract with another independent contractor to install the deck at a lower price than Ash wanted for the job. Ash completed his work by approximately August 1981. He installed the concrete pool shell, finished the inside surface and installed tile along the water line. He then attached the skimmer assembly, plumbing it so that it was level and attaching it to the concrete pool shell by means of the skimmer's PVC plumbing piping. After Ash finished his work, Dodd's other contractor came behind Ash. He used some of the dirt Ash had excavated from the pool site to raise the ground surrounding the pool by approximately six inches above grade. He then poured the concrete deck but failed to encase the skimmer assembly with the deck concrete in the process of pouring the concrete deck. It was not Ash's practice to make any special arrangements to stabilize the skimmer assembly when he installed both pool and concrete deck. He relies on the skimmer assembly plumbing to stabilize the skimmer assembly until the concrete deck is poured. In pouring the concrete deck, Ash encases the skimmer assembly with the deck concrete to stabilize the skimmer assembly and prevent leakage. In the case of the Poland pool (paragraphs 17 and 22, below), Ash used this method to install both the pool and the concrete deck, and Poland has had no complaint of leakage at the skimmer (nor was there any evidence of leakage at the skimmer). In the case of the Priests' pool (paragraphs 11 through 13, below), Ash followed the same procedures as he did with the Dodd pool, and another contractor poured the concrete deck. As with the Poland pool, there have been no complaints (nor was there any evidence) of leakage at the skimmer. Within approximately one and one-half years after installation of the Dodd pool, Dodd began to notice what he thinks is a leak in his pool. The water level in the Dodd pool drops approximately one-quarter inch per day. But the Department's own expert witness conceded that water loss of between one-eight and one-quarter inch can be explained by evaporation. It was not proved that the Dodd pool is leaking at all. If there is a leak causing a small increment of water loss above loss through normal evaporation, the leak would have to be very small and would be very difficult to detect. Ash and others have tried but have been unable to find a leak at the skimmer of Dodd pool. In approximately summer 1985, Dodd himself dug a hole under the concrete deck to expose the bottom of the skimmer assembly. The excavation revealed an unusual amount of moisture that might be the result of a leak at the skimmer. It also revealed that the contractor who poured the Dodd concrete deck did not encase the skimmer assembly as Ash had thought he would. The Department's expert - a professional engineer with a B.S. degree in civil engineering, an M.S. degree in structural engineering and a Ph.D. degree in environmental engineering - gave his opinion that a residential pool skimmer assembly should be either (1) encased with the concrete of the pool shell or (2) encased with deck concrete which is structurally tied to the concrete pool shell. He opined that the latter method would require either a very rough surface on the pool shell concrete or steel extending from the pool shell in order for the structural tie to be accomplished. But he also conceded that it is possible for deck concrete encasing a skimmer assembly to be sufficient to stabilize the skimmer assembly even without taking any extra measures to accomplish a structural tie. There was no evidence that any building code would require a pool contractor to take these measures to accomplish a structural tie between the pool shell and skimmer assembly. Nor was there any evidence that a reasonably prudent pool contractor (as opposed to a professional engineer) would be expected to take these measures. Based on this evidence, together with all the other evidence taken as a whole, the Department did not prove that Ash was either incompetent or grossly negligent in not taking any extra measurers to accomplish a structural tie between the concrete pool shell and the skimmer assembly. Based on the evidence in this case, the contractor Dodd hired to pour the concrete deck was either incompetent or grossly negligent (assuming he was even a licensed pool contractor a fact not shown by the evidence.) He did not encase the skimmer assembly with the deck concrete, allowing it to "float" unprotected in the fill under the concrete deck. Settling of the fill could have caused the deck to settle and crack, moving the skimmer assembly and causing a small leak. Ash may have been able to prevent this by warning the contractor to be sure to encase the skimmer assembly with deck concrete when he poured the concrete deck. But there was no evidence that Ash had a duty to advise the other independent contractor Dodd hired or was responsible for the other contractor's incompetence or gross negligence. Ash's failure to advise the other contractor was not incompetence or gross negligence on Ash's part. Dodd has no other complaints about the pool Ash built for him. Priests' Complaint (Count II). On or about October 11, 1984, Ash contracted with Joseph and Rita Priest to build them a pneumatic concrete pool. The Contract included a warranty that the labor, materials and workmanship would be free of defects for one year and that the shell would be structural sound and capable of holding the water for ten years. Like Dodd, the Priests contracted with another independent contractor to install the concrete deck around the pool. Ash was responsible only for placement of decorative "river rock" on top of the deck. Ash finished his work in February 1985. Like Dodd, the Priests complained of water loss from the pool although the Priests noticed the water loss sooner than Dodd (approximately March, 1985). The water level was dropping approximately one-quarter inch per day more than it was dropping in a bucket used as a control. In response to the complaint, Ash sent his employees to the Priests' pool on several occasions. They found no leak at the skimmer. To determine whether the pool's "caretaker system" 1/ was leaking, Ash's employees plugged all but one pair of the caretaker heads. After waiting a period of days, they would try to see whether the rate of water loss changed. They tested all four pairs of caretaker heads on the bottom of the pool and the pair in the spa attached to the pool. No leaks could be found. They did not replace the last two (in the spa), and Mr. Priest had to replace them. As with the Dodd pool, the Department did not prove that the Priests' pool is leaking at all. The Priests continue to complain of water loss of approximately one-quarter inch per day, within the range of water loss from normal evaporation. As with the Dodd pool, a leak responsible for a small increment of water loss above water loss from normal evaporation would be very small and difficult to find, especially if the leak were in the caretaker heads or pipes under the pool leading to the heads. Now the Priests suspect a water leak at the filter. But the Department's expert witness could not find a leak there large enough to account for much water loss. The minor leak at the filter is a normal maintenance item for a pool as old as the Priests' pool. There was no evidence how long it has existed, and there was no evidence that the Priests ever told Ash there was a leak at the filter. The Priests now also complain that one of the caretaker heads does not re-seat properly. But this has nothing to do with the leakage complaint to which Ash is charged with not reasonably responding. Taken as a whole, the evidence did not prove that Ash committed misconduct or deceit by failing to make reasonable response to warranty service requests within a reasonable time, as charged. Nor does the evidence prove misleading or untrue representations, gross negligence, incompetence or fraud in connection with the Priests' pool, as charged. Poland Complaint (Count III). On or about December 9, 1981, Ash entered into a contract with James Poland to build Poland a pneumatic concrete pool and concrete deck. Poland contracted with another independent contractor to build a screen enclosure around the pool. Before construction began, one of Ash's employees asked Poland to sign an addendum to the contract for an additional $235 to pay for foundation footers required to comply with Lee County building code provisions for the screen enclosures. Before Ash signed the initial Poland contract on December 9, 1981, he was unaware of the Lee County Aluminum Code, adopted March 18, 1981. The code requires eight inch foundation footers for "aluminum additions." Another part of the code addresses "screen enclosures with screen roofs known to the industry as birdcage swimming pool enclosures." The language of the code is not explicit that screen swimming pool enclosures are required to meet the foundation requirements for "aluminum additions," and at first Lee County did not interpret the code that way. With a change of personnel in code enforcement, Lee County began to interpret the code that way, and screen swimming pool enclosures Ash had under construction began to fail building inspection for inadequate foundation footers. Ash inquired why and was told about the aluminum code and how it was being interpreted. Ash argued that the interpretation was erroneous but, failing to dissuade enforcement personnel, began to comply. As part of his compliance efforts, Ash had his employees try to secure the contract addendum from Poland. Poland refused to sign the contract addendum, insisting on an opportunity to verify that the additional foundation footers were indeed new building code requirements. There still is a dispute between the parties whether Poland ever agreed to pay the additional $235 after he verified that the footers were being required. (He never signed the contract addendum.) But, in any event, the evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct in connection with the additional $235 charge. 2/ There was some evidence that Ash did not in fact comply with the Lee County Aluminum Code, as he was told it was being interpreted, in his construction of the Poland pool deck. In two places the foundation footers were 6 and 7 inches - deeper than the four-inch normal thickness of a concrete pool deck but short of the eight-inch requirement. But Ash was not charged with failure to comply with the foundation footer requirement. He had no legally sufficient notice that he should be prepared to defend against that charge and was not prepared to defend against that charge. Therefore, no finding is made whether Ash complied with the Lee County Aluminum Code. Ash performed the Poland contract between approximately January 27 and February 26, 1982. In September, 1985, Poland began to notice that some of the tile Ash installed at the waterline around the perimeter of the pool was coming loose. As explained by the Department's expert witness, the concrete deck settled in places, cracking slightly and rotating over the fulcrum created by the wall of the concrete shell of the pool. The rotating action pulled up on the tile attached to the inside of the pool wall in places, loosening the tile. In all, less than 10 percent of the 77 foot perimeter of the Poland pool experienced problems with loose tile. The loose tile easily can be removed and replaced. The minor deck cracking and loose tile problems at the Poland pool are within the normal range for a competently constructed pool under normal conditions of ground settlement. The evidence did not prove that Ash improperly installed the pool deck or that he was incompetent or grossly negligent in the construction of the Poland pool and deck. Besides the loose tile and minor cracks in the concrete deck, the Poland pool had no apparent defects. There also was evidence that the Poland pool was finished with a coating of marcite on the inside surface of the pool shell which was mottled gray in color instead of white. Poland complained persistently about the marcite3 and insisted that Ash make it white. But the discolored marcite was a factory defect of which Ash had been unable to know before he used it. There is no way to make mottled gray marcite white. Ash tried to explain this to Poland but the customer would not be satisfied. Taken as a whole, the marcite evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct. Nor does the evidence prove any of those violations for failure to cure the marcite problem under warranty. First, as already stated, there was no cure. Second, Ash and Poland also had a running dispute whether Poland had paid the full contract price, including the additional $235 for foundation footers, so as to entitle him to any warranty repairs. In light of this genuine dispute, failure to do warranty work, if otherwise a reasonable request, still could not be found to be misconduct, fraud or deceit.

Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing the Amended Administrative Complaint that has been filed against Respondent, Wesley Ash, in these cases. DONE AND ORDERED this 9th day of December 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of December, 1986.

Florida Laws (3) 455.227489.105489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs MERWIN C. CARTER, 91-005266 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Aug. 21, 1991 Number: 91-005266 Latest Update: Apr. 16, 1992

Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825

Florida Laws (5) 120.5717.00140.34474.214489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WILBUR A. SELLARS, 83-001510 (1983)
Division of Administrative Hearings, Florida Number: 83-001510 Latest Update: Mar. 19, 1984

Findings Of Fact The Respondent Wilbur A. Sellars is licensed as a residential pool contractor by the Construction Industry Licensing Board through license number RP 0045541. Mr. Sellars was first licensed in 1975. At all times material to this case Respondent has owned and operated in Tallahassee, Florida, a pool contracting company called Pro Pools Service and Supply or Pro Pools, Inc. Cabana Construction In November 1977 Respondent entered into a contract with Dr. Frank S. Bilek to construct for him a 20' by 40' vinyl lined pool and a 20' by 40' cabana building. The contract price for the pool was $11,166.10. The price for the cabana was $14,517.30. The pool and building were constructed as provided in the contract. The cabana sits on an 800 square foot slab with footings and consists of three separate rooms. One room is a small bathroom containing a lavatory, water closet, and shower. Another room is fully enclosed by finished walls and sliding glass doors. The third room is open on two sides, one of which faces the swimming pool. The walls are typical stud construction with plywood siding on the exterior and half-inch drywall on the interior. The roof is supported by 2/12 2x4 prefabricated trusses with shingles on top. The ceiling inside the cabana is the same as would be found in a residential home and the floor is a cement slab covered by carpet. There is one overhead ceiling fan in the open room and another in the fully enclosed room. For all practical purposes the construction techniques and materials used in the cabana are the same as would be used in a residential dwelling, although they may not meet the code standards which would be applicable to a dwelling in the Killearn residential area where Dr. Bilek's home is located in Tallahassee, Florida. The cabana is equipped with plumbing for the bathroom and also for a wet bar in the kitchen area of the cabana. No pool accessories were located in the cabana at the time Petitioner's witness inspected the facility, however as with any other structure of its size, pool equipment such as vacuuming hoses, wands, etc., could be placed inside it. The original design for the cabana included large solar panels located on the roof. The purpose of these panels was to provide heating for the swimming pool water. After the panels were installed they malfunctioned and have since been removed from the cabana roof. Typically in home swimming pool installations such panels are placed on house roofs or are independently supported by a special structure located near the swimming pool. The swimming pool water recirculation pump and filter for Dr. Bilek's pool were not located inside the cabana in issue, but were located nearby out in the open. The cabana was not designed for the purpose of housing this equipment. It appears from the furnishings found in the cabana, its orientation with respect to the pool, and from its equipment that the cabana along with the pool coordinate to create a unified entertainment complex. Neither is essential to the other, however. The cabana could host a cocktail party without there being a drop of water in the pool and the pool can function perfectly without the cabana. Criminal Convictions On May 18, 1979 Respondent sent a work crew to Cairo, Georgia, for the construction of a residential swimming pool for Mr. and Mrs. Vanlandingham. The crew was using a dump truck to haul excavated dirt from the pool site to a dumping site several miles from the Vanlandinghams' residence. An inexperienced driver was operating the truck. Upon arrival at the dumping site he engaged the bed lift to dump the dirt but forgot to release the safety chains. As a result the chassis of the truck broke. Members of the crew called Mr. Sellars to give him the bad news. He instructed them to burn the truck, which they did. Respondent then submitted an insurance claim for the loss of his truck due to an accidental fire. As a result of this false claim he was convicted of insurance fraud as defined in Section 817.234(1)(a), Florida Statutes. He entered a guilty plea and judgment was entered on June 7, 1982. On the same date Respondent also pled guilty and was convicted on another count of insurance fraud arising from his filing a false claim for the alleged theft of three mobile radios from trucks operated and owned by Pro Pools Service and Supply. The radios had in fact not been stolen. Since his conviction Mr. Sellars has obtained insurance coverage for the business of Pro Pools including automobile liability, physical damage, general property and general liability insurance.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Construction Industry Licensing Board enter a Final Order finding the Respondent Wilbur A. Sellars guilty of Counts One, Two, Three and Four in the Amended Administrative Complaint and impose discipline in the form of an administrative fine of $200 and suspending Respondent's license as a residential pool contractor for a period of three months. DONE and RECOMMENDED this 23rd day of December, 1983, in Tallahassee, Florida. MICHAEL P. DODSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of December, 1983.

USC (1) 18 U.S.C 1464 Florida Laws (7) 120.57455.225489.101489.127489.129817.23495.111
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HARRY TINKLER, 81-003043 (1981)
Division of Administrative Hearings, Florida Number: 81-003043 Latest Update: Sep. 07, 1982

Findings Of Fact At all pertinent times, respondent Henry J. Tinkler was licensed by petitioner as a swimming pool contractor, holding license No. 0024949, under the name of "Henry J. Tinkler." At one time, Fred C. Charlton worked as a "salesman" of swimming pool construction contracts for a Ft. Lauderdale construction company. When the Ft. Lauderdale company failed, several contracts to build swimming pools remained unexecuted. So that his "sales" would not have been in valid, Mr. Charlton organized Aquapool in late 1978 or early 1979 to step in to the shoes of the Ft. Lauderdale contractor. He has been president of the corporation since its inception. He knew that he could not pull building permits himself; and Mr. Charlton did not involve himself in the actual construction of the pools. Respondent became vice-president of Aquapool and held this office until September of 1979. Respondent has built several pools pursuant to oral agreements with Charlton (acting for Aquapool), to build all pools Aquapool "sold" in Pinellas County. In these transactions, Charlton made a profit and Tinkler made a profit. Respondent never applied for any building permit under Aquapool's name. He always used his own name or the name "Hank's Custom Pools." Respondent never made application to qualify Aquapool as a registered pool contractor in Florida. Neither did respondent make application to qualify "Hank's Custom Pools" as a registered pool contractor. Not uncommonly, contractors do business under fictitious trade names like "Hank's Custom Pools." Eventually one Clay Andrews of Jacksonville made application to quality Aquapool as a swimming pool contractor in Florida until November 17, 1979. Harry George Pugh and Grace L. Pugh signed, on May 19, 1979, a contract with Aquapool for construction of a swimming pool at their Indian Rocks Beach home. Petitioner's Exhibit No. 2. On the building permit application form, Petitioner's Exhibit No. 3, the contractor is listed as "Hank's Custom Pools." The application is dated June 19, 1979. Mr. Pugh never met Mr. Tinkler. Guy Jean and Jane A. Narejo also contracted with Aquapool to build a swimming pool at their home in Largo, Florida. Petitioner's Exhibit No. 4. Mr. Pugh never met Mr. Tinkler. On June 14, 1979, "H. Tinkler" applied for a permit to build the pool. The permit issued the following day. Petitioner's Exhibit No. 5. Willard L. Marks and Helen J. Marks signed, on May 1, 1979, a contract with Aquapool for construction of a swimming pool at their home in Clearwater, Florida. Petitioner's Exhibit No. 6. Mr. Marks never met Mr. Tinkler. H. J. Tinkler applied for a permit to build the pool on June 7, 1979. Petitioner's Exhibit No. 7. Swimming pool contractors ordinarily subcontract electrical work. Sometimes as many as four or five subcontractors participate in the building of a swimming pool. Petitioner's proposed recommended order has been considered and proposed findings of fact have been adopted except where they have been deemed irrelevant or unsupported by the evidence.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration as a swimming pool contractor for sixty (60) days. DONE and ENTERED this 27th day of April, 1982, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 Telephone: (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1982. COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Tallahassee, Florida 32301 Gerald Nelson, Esquire 4950 West Kennedy Tampa, Florida 33609 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32302 Samuel R. Shorstein, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION/CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 81-3043 HENRY J. TINKLER, RP 0024949 d/b/a Individual 5243 27th Avenue St. Petersburg, Florida 33710 Respondent. /

Florida Laws (4) 120.57489.119489.127489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN H. HOLLAND, 79-002059 (1979)
Division of Administrative Hearings, Florida Number: 79-002059 Latest Update: Aug. 28, 1980

Findings Of Fact Respondent is the holder of currently active General Contractor's license No. RG-0023888. On January 18, 1977, Norwood W. Hope (hereinafter "Developer") entered into a contract with Respondent for the construction of a commercial swimming pool. Respondent was to have been paid the amount of $43,346.40 under the contract for construction of the pool. The contract amount was to be paid pursuant to a five-stage draw schedule as follows: 1. Framing and steel draw paid $10,836.60 2. Gunite draw paid 10,836.60 3. Mancite draw 7,224.40 4. Equipment set draw 7,224.40 5. Final approval draw 7,224.40 Respondent made application for an Alachua County building permit for the swimming pool project on February 23, 1977. The permit application was approved on February 25, 1977, and a building permit was issued. Thereafter, the project received Alachua County approval on a temporary power pole inspection on June 1, 1977. An interim inspection of the property was made by Alachua County officials on November 7, 1977, with no deficiencies noted. A final inspection on the electrical work on the project was made, with satisfactory results, on November 8, 1977. The Alachua County Building Code, by incorporation of the 1973 Southern Standard Building Code, 1974 Revision, provides, in part, as follows: 108.2--INSPECTIONS REQUIRED The Building Official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building or structure upon completion, prior to the issuance of the Certificate of Occupancy, as required in Section 109. * * * (c) The Building Official upon notifica- tion from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit bolder or his agent wherein the same fails to comply with the law: * * * Final Inspection: To be made after the building is completed and ready for occupancy. (Emphasis added). The contract entered into on January 18, 1977 between the Developer and Respondent called for Respondent to construct the swimming pool according to the plans and specifications admitted into evidence as Petitioner's Exhibit No. 1. Associated construction, including construction of concrete pool decking, a pumphouse and a fence surrounding the swimming pool site were either completed by the Developer or by other sub contractors. By invoice dated October 12, 1977, Respondent requested a final draw on the project in the amount of 87,000, which, if paid, would have left only $224.40 unpaid under the contract. This draw request indicated that a balance due for extra time and materials would be billed ". . . upon acceptance of total pool." (Respondent's Exhibit No. 4). On October 25, 1977, the Developer paid $6,000 of the $7,000 requested to be paid by Respondent's invoice of October 12, 1977. The Developer contested Respondent's expressed intention to bill for additional time and material, asserting that the Developer had not approved any additional sums for extras. In remitting the $6,000 payment to Respondent, the Developer indicated that "[t]his leaves a balance on our account of $1,224.40, which will be paid upon checking out the pool." (Respondent's Exhibit No. 2). (Emphasis added.) An invoice for back charges on the swimming pool project in the amount of $274 was forwarded to the Developer by Respondent by invoice dated November 8, 1977. In addition, on November 8, 1977, Respondent also invoiced the Developer for a final draw on the project in the amount of $1,224.40. At some time after notification from the Developer's representatives that tile targets in the racing lanes of the pool were improperly located, Respondent returned to the job site after November 9, 1977 to relocate the targets. Respondent performed this work as a result of a written request from the Developer dated November 9, 1977. Respondent completed primary construction of the pool prior to submission of the final draw request of October 12, 1977. At that time, back- filling around the exterior of the pool structure preparatory to the pouring of the concrete pool decking had not been completed. Although by October 12, 1977, Respondent had removed much of the excess dirt and debris from around the edges of the pool. There were still areas of exposed piping which would, in due course, be covered with back-fill and tamped by the decking subcontractor. Respondent did not attempt to back-fill or tamp any areas around the pool's piping system. At some time subsequent to October 12, 1977, which date is not clearly reflected in this record, a separate sub- contractor completed back-filling work around the pool, and poured the concrete decking. Neither the Developer nor his subcontractor advised Respondent that the back-filling had been accomplished and that the deck was to be poured. Prior to October 12, 1977, Respondent "pressure tested" the pool's piping system, and determined that the pool would hold water at a level above its scum gutters. The results of this testing indicated that, at least as of October 12, 1977, there was no leakage from the pool. Standard practice in the pool construction industry dictates that a minimum of three pressure tests be made of a pool's piping system during the course of construction. The first of these tests should occur immediately after installation of the pipes, and a second test should be performed immediately before final back-filling to cover the pipe system. A final pressure test should be conducted after tamping of the fill and prior to the pouring of concrete for the pool deck. The obvious purpose of this system of pressure testing is to discover any water leaks before concrete pool decking is poured to avoid having to cut out sections of the concrete in order to locate leaks. Because the Developer and his subcontractor failed to notify Respondent of further work being done on the pool. Respondent was unable to perform a pressure test either after back-filling was completed, after the back- fill had been tamped and before the concrete deck was poured. By letter dated January 17, 1978, Respondent was furnished by the Developer with a "punch list" indicating several areas of deficiency that needed to be corrected in the pool. In that letter the Developer requested that Respondent complete the necessary work within seven days. The Developer forwarded a second letter to Respondent dated February 23, 1978 advising Respondent that the punch list items had not been corrected, and urging Respondent to complete the work described in the punch list as soon as possible. From receipt of the punch list in January of 1978 through the middle of March, 1978 Respondent had workers on the job intermittently making the corrections indicated in the punch list. Respondent satisfactorily corrected fifteen of the eighteen items listed as defective n the punch list. Some of the items were repaired by other subcontractors. Respondent had difficulty obtaining some items of equipment, which he was required to back-order. When the back-ordered equipment was slow in arriving, the Developer opted to obtain these items from a source other than Respondent. Respondent replaced a defective pump associated with the pool construction at some time subsequent to January 18, 1977. The last work performed by Respondent on the pool project occurred some time between March 10 and March 16, 1978. At no time thereafter was Respondent ever advised by the Developer that any work performed under the contract was either unsatisfactory or incomplete. The pool received a final State of Florida, Department of Health and Rehabilitative Services inspection on July 13, 1978, at which time all necessary permits for operation of the pool under applicable regulations were issued. Respondent at no time requested that Alachua County officials come to the job site to conduct the necessary final inspection of the project, nor did he advise the Developer of the necessity to do so. At some time during 1979, subsequent to the completion of the swimming pool project, the Developer discovered that the pool was losing water at a rate of approximately 2,100 gallons per day. During this period, the water level inside the pool would drop to a level equal to the piping running around the exterior of the pool shell and under the pool decking. When the Developer was unable to ascertain the cause of the leak, an outside subcontractor was hired to check the pool. This sub- contractor performed pressure tests on the pool's piping system in an attempt to determine whether the leakage was occurring through the pipes. These tests apparently showed no leakage through the piping system. The Developer then caused the concrete decking around the edge of the pool to be removed in order to more closely inspect the interior piping. At this point it was discovered that there existed flaws and breaks in the neoprene piping surrounding the exterior shell of the pool. After repairs to the damaged piping, the pool decking was repoured and there has been no subsequent leakage problem in the pool. The Developer incurred expenses in the amount of $2,288 in removing the decking around the pool and repairing the neoprene piping. Because of the fact that several subcontractors in addition to Respondent worked in the pool area during construction of the pool project, it is impossible on the basis of this record to determine the cause of the damage to the neoprene piping. Respondent's testimony is uncontroverted that pressure testing performed prior to the conclusion of primary work on the pool in October of 1977 showed no leakage through the pool's piping system. Further, at the conclusion of the primary work in October, 1977, much of the pool's piping system was left exposed and could have been damaged either by the Developer's own workers or by employees of other subcontractors in the course of back- filling and tamping fill material preparatory to pouring concrete decking. The Developer's failure to advise Respondent of the schedule for back-filling, tamping and pouring of concrete deprived Respondent of an opportunity to properly pressure test the piping system at appropriate stages of construction. Respondent has submitted proposed findings of fact for consideration by the Hearing Officer. To the extent that those proposed findings of fact are not incorporated in this Recommended Order, they have been rejected as being either irrelevant to the subject matter of this proceeding or as not having been supported by the evidence.

Florida Laws (1) 120.57
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JIMMY G. MILLER, 86-003479 (1986)
Division of Administrative Hearings, Florida Number: 86-003479 Latest Update: Jan. 12, 1987

Findings Of Fact At all times material to the pending Administrative Complaint, Respondent was a registered pool contractor licensed by the State of Florida, having been issued license number RP 0029202. (Petitioner's First Request for Admissions, Item 2: Pet. Exh. C) On or about December 5, 1984, Respondent, d/b/a Miller Pools, contracted with Terry Kilpatrick to construct a pool at the Kilpatrick residence. (Pet. Exh. B; T. 9-10) The contract provided for a contract price of $10,963 for the construction of the pool and $1600 for the installation of fencing. (Pet. Exh. B; T. 10) Under the provisions of the contract and pursuant to the agreement of the parties, Respondent was responsible for all aspects of the pool construction and Kilpatrick was responsible for the installation of the fencing. (Pet. Exh. B; T. 10-11) As part of the contract, Respondent gave Kilpatrick a one-year warranty on the construction of the pool. (T. 19-20) The Kilpatrick residence was located in Putnam County, Florida, within the jurisdiction of the Putnam County Building and Zoning Department. (Pet. Exh. B; T. 37) In December 1984, the 1982 Standard Swimming Pool Code was in effect in Putnam County, having been adopted by county ordinance. (Pet. Exh. E, F; T. 40- 42) The Standard Swimming Pool Code in effect in Putnam County in December 1984 required that a building permit be obtained before the commencement of construction of a swimming pool at a residence in the county. (Pet. Exh. E; T. 42) Respondent obtained the necessary building permit for the Kilpatrick pool job. (Pet. Exh. D; T. 42) The Standard Swimming Pool Code in effect in Putnam County in December 1984 also required that certain inspections be done during the course of the construction of a swimming pool. (Pet. Exh. E; T. 43) Among the required inspections was an electrical inspection and a final inspection. (Pet. Exh. E; T. 44-45) It was the responsibility of Respondent as contractor to request the Putnam County Building and Zoning Department to conduct the necessary inspections of the pool. (Pet. Exh. E; T. 44) The purpose of requiring the various pool inspections, including the electrical and the final, was to make certain that the pool had been constructed and was operating correctly and safely. (T. 45) Respondent was aware that certain inspections were required by local law. On three occasions, December 19, 1984, January 7, 1985 and January 10, 1985, inspections were performed on the Kilpatrick pool at Respondent's request. (Pet. Exh. D; T. 23, 43) Respondent did not make arrangements for the electrical or final inspections to be performed on the Kilpatrick pool. (Pet. Exh. D; T. 23, 43-44) During the construction of the Kilpatrick pool, Respondent was at the job site infrequently. (T. 12-16, 18, 19, 22) Almost immediately after the pool construction was completed, Kilpatrick began to experience problems with the pool, problems which included pitting of the marcite finish, leaks in the tiled area of the pool, and chipping of the brick and coping. (T. 24-35) The problems experienced by Kilpatrick were problems related to the construction of the pool and were covered by the one-year warranty on the pool given to Kilpatrick by Respondent. (T. 19-20) Respondent failed to take any action to correct the problems until after Kilpatrick had contacted the Putnam County Building and Zoning Department and the Department of Professional Regulation to complain about the problems with the pool. (T. 25-28, 35-36, 46-50) As of the date of the hearing in this case, Kilpatrick continued to experience problems with the pool leaking around the tile. (T. 31-31, 34) By Final Order, dated March 17, 1986, in Department of Professional Regulation Case No. 0059028, the Construction Industry Licensing Board imposed an administrative fine of $1000 and suspended Respondent's registered pool contractor's license for five years as a result of Respondent's default in a disciplinary case in which Respondent had been charged with failure to supervise a swimming pool construction project and/or performing said construction in a grossly negligent and/or incompetent manner. (Pet. Exh. C)

Recommendation Having found the Respondent guilty of violating Subsections 489.129(1)(d) and (m), Florida Statutes, it is recommended that Respondent be fined $1000, and that his license be suspended for an additional year after the suspension imposed by the Construction Industry Licensing Board in its Final Order, dated March 17, 1986, in Department of Professional Regulation Case No. 0059028. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of January, 1987. COPIES FURNISHED: David R. Terry, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Jimmy G. Miller 706 Southeast 35 Avenue Ocala, Florida 32671 Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Wings S. Benton, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (2) 120.57489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RONALD B. HAENDIGES, 82-002873 (1982)
Division of Administrative Hearings, Florida Number: 82-002873 Latest Update: Dec. 04, 1990

Findings Of Fact Ronald B. Haendiges is a registered general contractor in the State of Florida holding license number RG 0039437. The Respondent was so licensed at all times material to the Administrative Complaint and at the time the Administrative Complaint issued. On May 29, 1981, the Respondent contracted with Mary Raney to put into operation a pool located at 479 East Main Street, Longwood, Florida, for a contract price of $4,025. Said pool had been partially floated out of the ground. The contract between Raney and the Respondent specifically provided that the Respondent would perform the following: Knock off existing tile; Reform beam; Reset new level of skimmer; Pressure-test existing plumbing and repair as needed (but not to exceed $300 of extra cost); Reform new deck area (450 square feet) Fill as needed; Place wire mesh in new deck area and pour new deck; Retile waterline, 6 by 6 bullnose; Re-(illegible) cracked area on bottom of pool; Recement pool with Pool-tight; Put cool deck topping on new deck area; Reform and pour new steps and tile step edge with matching tile; Replace pump and motor with new comparable. The Respondent commenced work in workmanlike fashion on or about May 29, 1981. As work progressed on the pool, he received various payments from Raney in accordance with their contract. The Respondent received a total of $2,750 of the $4,025 contract price. On or about July 13, 1981, the Respondent, nearing completion of his work, filled the swimming pool with water. At that time, additional cracks and leaks developed in the sides and bottom of the Raney pool. when these cracks developed, Raney refused to pay any of the balance of the contract price, or a total of $1,275. At that time, all work covered under the contract was completed, to include reinforcing the cracked areas with steel, except that the pool deck had not been poured. A square hole at one end of the pool and a larger area at the shallow end had not been finished. The cracks in the pool were created when the pool was filled with water because a void had been created beaten the bottom of the pool and the foundation of the pool when the pool floated up out of the ground. when the weight of the water was placed in the pool, it broke out the bottom of the pool. The problem with this void was not anticipated by Raney, the pool's owner, or the Respondent. Harvey's Bobcat Service provided fill dirt and labor to the Respondent for repairs on the pool, which were not paid for, and a lien of $382 was filed against the Raney property. Dove Henson performed marcite work and pool decking on the Raney pool for the Respondent. The Respondent was to pay Henson $400 for the work performed and, as of the date of the hearing, had not done so. The Respondent purchased Pool-tight on two occasions from Contractor's Supply of Orlando, Florida. On July 8, 1981, the Respondent purchased $275.60 worth of Pool-tight. On July 11, 1981, the Respondent purchased another $78 worth of Pool-tight from Contractor's Supply. On July 10, 1981, the Respondent paid $275.60 on this bill. This left a remaining balance of $78 due Contractor's Supply, which was not paid. Raney subsequently contracted with another contractor to repair the pool's bottom. This contract between Mary Raney and Reid Baker provided that Baker would perform the following work for a contract price of $2,780: Remove cracked bottom; Install or replace dead line and rock bottom and steel; Re-Gunite bottom and walls where necessary; Check all piping and repair; Marcite entire pool; Furnish and install grab rails; Recoat cool deck where necessary for a first-class job; Reinstall owner's filter, pump, valve, etc.; Clean up pool debris. The contract between Raney and the Respondent did not call for the replacement of the bottom of the pool, and the replacement of the bottom of the pool was not anticipated in said contract. The standard building code of the City of Longwood requires that a contractor obtain a building permit prior to construction or repair of a pool.

Recommendation Having found the Respondent, Ronald B. Haendiges, not guilty of violating Section 489.129(1)(h), Florida Statutes, the Hearing Officer recommends that this charge be dismissed. Having found the Respondent guilty of violating Section 489.129(1)(d), Florida Statutes, by failing to obtain a permit as required by the local building codes, the Hearing Officer recommends that the Respondent receive a letter of reprimand. DONE and RECOMMENDED this 15th day of April, 1983, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of April, 1983. COPIES FURNISHED: Stephanie A. Daniel, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Ronald B. Haendiges Post Office Box 388 Winter Park, Florida 32790 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 J. K. Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (2) 120.57489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer