Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
SCOTT ERIC BAKER vs CONSTRUCTION INDUSTRY LICENSING BOARD, 91-007580 (1991)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 25, 1991 Number: 91-007580 Latest Update: Jan. 25, 1993

Findings Of Fact Petitioner Scott Eric Baker ("Petitioner"), took the Certified Air Conditioning Class A Contractor examination in June 1991. The examination consists of two parts, Part One on business and financial management, and Part Two on actual air conditioning system mechanics. The Petitioner informally challenged the scoring of certain questions and received additional points but his total score of 68% was below the minimum passing score of 69.01%. Part One, Question 6 of the June 1991 directs the applicant to estimate the cost of refrigeration piping and related hardware shown in a related schematic. The schematic illustrates proposed refrigerant piping between a 15 ton air-cooled condensing unit and an air handler unit. Pipe joint connections are identified by standard symbols. The question states as follows: Refer to the Refrigeration System shown in Figure 1. Estimate the cost of the Refrigeration Piping. Add 6% Florida State Sales Tax to the total cost. The multiple choice list of possible answers to the question are: Less than $500.00. (B) Between $500.00 and $600.00 (C) Between $600.01 and $700.00 (D) More than $700.00 The pipe joint segments identified by the symbols on the schematic are 90-degree elbow joints. Elbow joints can connect pipe segments which have different elevations. Elbow joints can also be connected to construct a "swing joint" which provides for pipe alignment. Swing joints do not change the elevation between the pipe segments connected at the joint. According to the schematic, the first pipe segments, (two feet two inch pipes), run from the air-cooled condensing unit to a joint. The schematic does not identify the elevation of the air-cooled condensing unit or of the first pipe segments. The second pipe segments lie at an elevation of 104 feet 4 inches and connect via a pipe joint to the third pipe segments, which lie at an elevation of 104 feet 0 inches. The third segments connect via a pipe joint to the fourth pipe segments which are at an elevation of 103 feet 8 inches. The fourth segments connect to the pipe segments leading from the air handling unit (AHU 1). The correct answer to Question 6 is (B). The total cost for piping and hardware shown on the schematic is approximately $557. There are 83.3333 lineal feet of 1 and 3/8 inch diameter pipe at $3.96 per lineal foot, totaling about $330.00. There are 75.7527 lineal feet of 7/8 inch diameter pipe at $2.35 per lineal foot, totaling about $178.02. There are fourteen 90-degree elbows, (seven 1 and 3/8 inch elbows at 1.71 each and seven 7/8 inch elbows at .79 each) totaling 17.50. The total of materials is 525.52. Inclusion of the 6% tax results in an estimated cost of $557.05. Because there was no elevation shown for the first pipe segment between the condenser unit and the pipe joint, the Petitioner assumed that the pipe joint symbol indicated an elevation change and that the condenser unit could be located substantially above or below the identified 104 feet 0 inches elevation of the second segment. Accordingly, his answer to Question 6 was "(D) More than $700.00." The Petitioner's answer is based, not on the information provided in the schematic, but on unreasonable assumptions as to the condenser unit location, and is incorrect.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order dismissing Scott Eric Baker's challenge to the grading of his responses to the June 1991 examination for licensure as a Certified Air Conditioning Class A Contractor. DONE and RECOMMENDED this 29th day of April, 1992, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1992. APPENDIX TO RECOMMENDED ORDER The following constitute rulings on proposed findings of facts submitted by the parties. Petitioner The Petitioner's proposed findings of fact are accepted as modified and incorporated in the Recommended Order except as follows: 4. Rejected, unnecessary. 10-14. Rejected, recitation of testimony. Respondent The Respondent did not file a proposed recommended order. Copies furnished to: Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Jack McRay, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Scott Eric Baker 13438 Caribbean Boulevard Fort Myers, Florida 33095 Vytas J. Urba, Esq. Assistant General Counsel Department of Professional Regulation 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.111
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. FRANK WALLACE, 87-005050 (1987)
Division of Administrative Hearings, Florida Number: 87-005050 Latest Update: May 23, 1988

Findings Of Fact The following findings of fact are based upon the evidence presented, Respondent's admissions and matters deemed admitted due to Respondent's failure to timely respond to Petitioner's Second Request for Admissions: At all times material hereto, Respondent was licensed by the Construction Industry Licensing Board as a registered air conditioning contractor with license number RA-0035721. He was the qualifying agent for Wallace's Air Conditioning and Heating. Respondent's address of record is 4710 Cypress Ridge Place, Tampa, Florida 33624, and it was to this address that notice of the hearing was sent. At no time prior to the hearing did Respondent contact counsel for Petitioner or the undersigned regarding any problem he had with the date scheduled for this hearing. Respondent did not appear, and was not represented at the hearing which commenced at 9:00 a.m. on May 11, 1988. However, at 1:56 p.m. on the day of hearing, a letter from Respondent addressed to Petitioner's counsel was filed at the Division of Administrative Hearings in Tallahassee, Florida. This letter was postmarked on May 9, 1988 and requests rescheduling of the hearing due to his being out of town on "urgent business." By Order entered on May 13, 1988, Respondent's untimely and insufficient motion for continuance was denied for failure to comply with Rule 22I-6.017, Florida Administrative Code, and this case has proceeded to the issuance of this Recommended Order in accordance with the procedures established at hearing. On or about March 18, 1986, Respondent, as qualifying agent for Wallace's Air Conditioning and Heating, entered into a contract with General Engineering and Machine Company for the installation of heating, ventilation and cooling services (HVAC) at the Sebring Square Plaza shopping mall in Sebring, Florida. The work to be performed included the installation of heating, ventilation, air conditioning and temperature control systems for stores in the mall, which included Zayre's Department Store and thirty "strip stores." The contract price for this work was $275,460. Respondent thereafter began work on the mall under this contract. However, he has never held any certificate of competency, occupational license, or registration in the City of Sebring, as required by local ordinance sections 5-18 and 5-19. On or about May, 1986 Respondent entered into a subcontract agreement with Long's Air Conditioning and Heating for sheetmetal duct work, venting of exhaust fans and installation of flex duct and grilles at the Sebring Square Plaza. The original amount of Respondent's contract with Long's Air Conditioning was $69,200, but this was increased by agreement to $72,200. On or about June 19, 1986, work on the thirty "strip stores" was deleted from this subcontract agreement, and the contract price was then reduced by $3,760, making a final contract price of $68,440. Respondent received draw requests totaling $68,440 from Long's Air Conditioning for work performed under this subcontract. Although all contracted work was performed by Long's Air Conditioning, Respondent has only made payments totaling $66,500, leaving an unpaid amount of $1,940. In connection with his work on the Sebring Square Plaza, Respondent purchased equipment and supplies from Florida Air Conditioners, Inc., in the total amount of $122,019.80, but made no payments on this account. On October 6, 1986, Respondent's account with Florida Air Conditioners was paid in full by Highway 27 Associates, the owners of the Sebring Square Plaza, who in turn charged this amount to the general contractor, General Engineering and Machine Company, by reducing the amount they paid to said general contractor on the Sebring Square Plaza. Charles R. Baldwin was the general administrator on this shopping mall job for the general contractor, General Engineering and Machine Company. In accordance with his subcontract agreement with Respondent, if Respondent did not pay his materialmen, the general contractor was responsible, and, in fact, in this case the general contractor was charged for payments made by the mall owner on Respondent's account at Florida Air Conditioners. Respondent failed to regularly attend weekly job site status meetings with Baldwin. When schedules were established, Respondent voiced no objection, but he then frequently failed to complete work in accordance with those schedules. Respondent made little effort to complete his work on time, or to make up for delays. He failed to supervise the work he was performing at the Sebring Square Plaza. On or about June 24, 1986 Respondent walked off the job without completing the work which he had contracted to perform, and this caused further delay in the mall's completion since Baldwin had to find another contractor to complete Respondent's job. Baldwin paid Respondent $174,467.70 on June 18, 1986 in connection with this job after Respondent signed an affidavit certifying that he had paid all his materialmen and subcontractors. The record establishes that said affidavit was false. With the amount Baldwin was charged for Respondent's unpaid account with Florida Air Conditioners, and the amount paid on June 18, 1986, General Engineering and Machine Company paid or was charged approximately $296,000 for work performed by Respondent, although their contract with Respondent was only $275,460. According to Bernard Verse, who was accepted as an expert in commercial construction, Respondent's failure to pay for supplies and equipment, and his failure to complete his contract with General Engineering and Machine Company constitute misconduct in contracting. In addition, Respondent failed to properly supervise the work he was performing, and for which he contracted, on this job.

Recommendation Based upon the foregoing, it is recommended that the Construction Industry Licensing Board enter a Final Order suspending Respondent's license number RA- 0035721 for one (1) year and imposing an administrative fine of $5,000; provided that after the expiration of thirty (30) days from the issuance of the Final Order if Respondent pays said administrative fine in full, his license shall be immediately reinstated. DONE AND ENTERED this 23rd day of May, 1988, in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of May, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5050 Rulings on Petitioner's Proposed Findings of Fact: 1 Adopted in Finding of Fact 1. 2-3 Adopted in Finding of Fact 3. 4 Adopted in Finding of Fact 4. 5 Adopted in Finding of Fact 9 6 Adopted in Finding of Fact 5. 7 Adopted in Finding of Fact 7. 8 Adopted in Findings of Fact 7, 8. 9-10 Adopted in Finding of Fact 6. Adopted in Finding of Fact 10. Adopted in Finding of Fact 6. Rejected as irrelevant and not based on competent substantial evidence. Adopted in Finding of Fact 7. Rejected as irrelevant. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Frank W. Wallace 4710 Cypress Ridge Place Tampa, Florida 33624 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.105489.117489.129
# 2
DIVISION OF REAL ESTATE vs MARGARET L. PAGE, 98-005115 (1998)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Nov. 20, 1998 Number: 98-005115 Latest Update: Dec. 13, 1999

The Issue The issue for consideration in this case is whether Respondent's license as a real estate salesperson in Florida should be disciplined because of the matters set forth in the Administrative Complaint filed herein.

Findings Of Fact At all times pertinent to the issues herein, Petitioner, Division of Real Estate, was the agency in Florida responsible for the regulation of the real estate profession and the licensing of real estate professionals within this state. Respondent was licensed as a real estate sales person and employed as such in association with Today Real Estate, Inc., a real estate corporation trading as Re/Max Today, located at 2451-1 McMullen Booth Road in Clearwater, Florida. On July 16, 1997, James E. Brown and his wife submitted an offer to purchase a house located at 9813 Palmer Drive in New Port Richey. The offer was submitted by the Browns through their real estate agent, Nancy Riley, to the sellers who were represented by Respondent. As a part of the sales package, a home inspection report was completed on July 21, 1997, which indicated that the "air conditioning does not appear to be cooling enough." Thereafter, Respondent contacted Alvarez/Taylor, a plumbing and air conditioning company, to examine the unit and a representative of that company, William Taylor, went to the property on July 25, 1997, to inspect the unit. When he arrived, he found no one there and the house locked. He contacted his dispatcher who advised him to wait, and within a few minutes, Ms. Riley showed up. She let him in the house to do the inspection. The unit was low on freon, but the big problem with the unit that Taylor found was that it was old -- about 13 years old -- and at that age, he contends, units usually lose freon. He made an oral report to Ms. Riley who authorized him in writing to do whatever work was necessary on the unit to get it working properly. He installed the freon but that did not completely correct the problem. He advised Ms. Riley that he felt the unit should be replaced because of its age. She did not seem concerned about it, but she did not authorize the repairman to replace it. When he had done what he could do, short of replacing the unit, she again signed the work order, indicating the work had been done, and he gave her the pink copy of the form. This form showed his recommendation that the unit be replaced. According to Respondent, Ms. Riley called her after the air conditioner repairman had been at the house. She said the unit was working but was an older unit and somewhere down the line would have to be replaced. Respondent also claims that Ms. Riley told her she, Ms. Riley, had called Mrs. Brown and read her the report, and the Browns "were OK with it." Respondent did not see the repairman's report until July 28, 1997. At that time, she verified the repair charge of $140.00, and when she saw the recommendation for replacement on the form, she was upset by it. Respondent claims she had not been told by Ms. Riley that there was a recommendation for replacement, and she wanted to investigate the matter. She called Ms. Riley and left a message that she wanted to talk about it, and, on the recommendation of her own air conditioning repair firm, also called Alvarez/Taylor to ask for details on the recommendation for replacement. The repairman was not available, and she was unable to speak with anyone who was aware of the problem. All she was told was that the unit was old, would need constant repair, and should be replaced. When she asked to speak with the owner, he refused to speak with her. After several unsuccessful attempts to get information from Alvarez/Taylor, still on July 28, 1997, Respondent called Ms. Riley again and was told, she claims, that the situation was not so bad and the replacement recommendation was not immediate; that the Browns knew of the situation and were OK with it; and that the Browns hoped to get another year use out of the existing unit. Respondent claims she told Ms. Riley at that time she intended to remove the recommendation for replacement from the inspection report if she didn't hear back from Alvarez/Taylor, and that Ms. Riley agreed. Ms. Riley disputes this. Thereafter, she removed the recommendation for replacement from the inspection report, and on July 30, 1997, at the closing, Respondent gave the buyers an altered copy of the report of the air conditioning repairman. On this copy, the notation in the place reserved for recommendations that the unit was 13 years old and should be replaced was not present. The closing went forward and was consummated, and the Browns were given a copy of the altered inspection report. Almost a month later, on August 26, 1997, after the closing, Alvarez/Taylor furnished the Browns with a copy of the inspection report dated July 25, 1997 which reflected, in the space reserved for recommendations, that the unit should be replaced. The unit failed, and on September 3, 1997, Alvarez/Taylor replaced the unit due to its age and condition. The replacement cost the Browns $2,315.00. When the Browns started to look into the matter, and enlisted the aid of their agent, Ms. Riley, they also contacted Respondent who told them that she had altered the inspection report because she believed she had the authority to do that as a realtor. Respondent claims she was not trying to hide anything by altering the inspection report, nor was she trying to limit the Browns "or their representatives" access to the unit. She further contends she did not intend for anyone to reply on the altered inspection report. She says she believed everyone who needed to know, Ms. Riley and the Browns, were aware of the actual recommendation for replacement, and she was merely trying to correct the situation since she could not get what she considered to be appropriate information from Alvarez/Taylor.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Florida Real Estate Commission enter a final order finding Respondent, Margaret L. Page, guilty of concealment and breach of trust, imposing a suspension of her license as a real estate salesperson for six months under such terms and conditions as the Commission deems appropriate, and imposing an administrative fine of $500.00. DONE AND ENTERED this 29th day of September, 1999, in Tallahassee, Leon County, Florida. ARNOLD H. POLLOCK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6947 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 1999. COPIES FURNISHED: Ghunise Coaxum, Esquire Division of Real Estate Department of Business and Professional Development 400 West Robinson Street Suite N-308 Orlando, Florida 32801 David C. Levenreich, Esquire 406 South Prospect Avenue Clearwater, Florida 33756 Barbara D. Auger, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Herbert S. Fecker, Division Director Division of Real Estate Department of Business and Professional Regulation 400 West Robinson Street Post Office Box 1900 Orlando, Florida 32802-1900

Florida Laws (2) 120.57475.25 Florida Administrative Code (1) 61J2-24.001
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. NEAL O'CONNER, 89-000186 (1989)
Division of Administrative Hearings, Florida Number: 89-000186 Latest Update: May 25, 1989

Findings Of Fact By his answers to Petitioner's Request for Admissions, Respondent indicates, and it is so found, that he is currently licensed by the Florida Construction Industry Licensing Board under license CA C010372 as a certified air conditioning contractor; that his license was in effect at all times material to the allegations involved in this hearing; and that his license was in effect as of the date of the hearing. The Construction Industry Licensing Board, (Board), is the state agency responsible for licensing construction trades professionals in this state. Sometime prior to August 18, 1987, Respondent's firm contracted with Ralph Worthington to replace the air conditioning system at Mr. Worthington's home in Pinellas County, Florida. The contract price was $3,075.00. The work was completed. On August 19, 1987, Dale J. Parker, a mechanical inspector for the City of St. Petersburg, which utilizes the Standard Mechanical Code as a guideline for construction in the city, inspected the unit in question installed by Respondent's concern, Residential Air Conditioning. A permit to complete the work had been issued on June 25, 1987 for the work. No explanation was given for why the inspection was not done until approximately two months after the permit was issued, but that delay is not relevant to the issues here. During his inspection, Mr. Parker found that the provisions of Sections 303.2 and 303.3 of the Standard Mechanical Code had not been followed by the Respondent's firm in that no light was available in front of the unit, no electrical disconnect was furnished for the unit, and there was no clear access to the unit. Access is required to be through an unencumbered space no less than 22 by 36 inches. When he went up into the attic to examine the unit, he found the area to be tight and dark. At the time, he was unable to see any defects other than those he listed, but his general opinion of the installation was that it was "not a good job" and was somewhat "sloppy". As a result of the defects he saw, he rejected the work and "red tagged" it. Issuance of a red tag requires correction of the defect and reinspection of the work. Evidence indicates that the required light had not been there prior to Respondent's installation and the access to the unit, which required stepping over an air duct, was the same as it had been before the installation of the new unit. The Code requirement to correct these defects existed when the house was built. It is clear the initial installation, not done by Respondent, was also deficient. Respondent admits that when he installed the new unit, he assumed the responsibility for correcting the existing deficiencies and bringing the installation up to Code requirements. However, Mr. Worthington, the homeowner, would not allow Respondent's personnel back into his residence to correct the problems. This does not excuse the improper installation but would have resulted in a waiver of the reinspection fee. On October 1, 1987, William Rinehart, owner of Johnson's Air Conditioning, who had been contacted by Mr. Worthington, sent his technician, Mr. Aleshire out to the property to make the repairs. Mr. Aleshire discovered a lot of water in the insulation in the attic in the area around the air conditioning unit. He also noticed that duct work had come loose from the unit, that the unit was tilted, and that both the primary and secondary drain pipes were clogged with sand at the outside outlet. When he moved the insulation, he found the attic floor had rotted as a result of water condensation which had spilled out of the drain pans surrounding the unit onto the floor. As a result, the attic floor fell through into the room below. Mr. Aleshire found that the air handling unit was improperly tilted. So was the primary drain pan which was improperly tilted away from the drain. Since the drain was clogged, when the condensation collected in the pan, instead of draining out, it ran over the opposite side of the pan into the secondary pan from which it could not drain because that plug was clogged as well. As a result, the condensation water ran over out onto the attic floor. Aleshire also noticed that some of the wiring had to be replaced because of a lack of sealing and failure to use Romex connectors, both of which are required by the Code. In his opinion, however, except for the electrical problems and the tilted air handling unit and drain pans, the installation was up to Code. Had it not been for the clogged drains, the unit would probably have worked satisfactorily for a long period without problems. There is no evidence to connect the clogged outside drains with the Respondent. He is, however, responsible for the other defects noted. Both Aleshire and Rinehart consider the tilted installation of the air handling unit improper. Mr. Rinehart would have used adjustable bolts to affix the unit and a carpenter's level to insure the drainage was proper. The failure to level the unit is negligence and the failure to utilize proper sealant and Romex connectors constituted misconduct since both are required by the Code. Respondent does not deny either of these defects. He contends his firm did what it agreed to do. When Mr. Worthington complained, he initially responded and attempted to correct the problems but was unable to do so to Mr. Worthington's satisfaction. The problems were not corrected by Respondent. Nonetheless, Respondent contends his firm tried to do a proper job and feels Worthington overreacted, frequently complaining when a workman was only a few minutes late for a scheduled appointment. Respondent was not personally aware of the details of the installation in question, did not do any of the work himself; nor did he inspect the job when it was completed. When this work was being done, Respondent, who is in partnership with Mr. Neidrich was in Tampa opening another office for the firm. He first found out about it after a complaint was filed and, in an effort to work out their differences, attempted to contact Worthington up until the time the Department of Professional Regulation got into the picture. Respondent, who qualified the company under his license, is an engineer and his primary function with the company is to design complicated systems. He visits jobs of "difficult installation" but acts merely as a consultant on the company's routine business. He performs quality checks from time to time on routine as well as major jobs to insure the work is being done properly. Though he testified he does this on a weekly basis, he admitted his last inspection was four weeks before the hearing. The correction of the defects identified herein was subsequently accomplished by another contractor hired by Mr. Worthington at additional cost. He also paid $422.80 to replace floor covering damaged as a result of the tilted air conditioning unit.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that Respondent, Neal A. O'Connor be reprimanded and pay an administrative fine of $500.00. RECOMMENDED this 25th day of May, 1989 at Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of May, 1989. COPIES FURNISHED: Elizabeth A. Alsobrook, Esquire Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Neal A, O'Connor 1925 Hastings Drive Clearwater, Florida 34623 Kenneth A. Easley, Esquire General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION, Petitioner, vs CASE NO.: 89308 DOAH CASE NO.: 89-0186 NEAL A. O'CONNOR, LICENSE NO.: CA C010372, Respondent. /

Florida Laws (2) 120.57489.129
# 4
DEPARTMENT OF FINANCIAL SERVICES, DIVISION OF WORKERS' COMPENSATION vs L AND M AIRCONDITIONING SYSTEM, INC., 18-004144 (2018)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida Aug. 07, 2018 Number: 18-004144 Latest Update: Apr. 03, 2019

The Issue The issue is whether Respondent failed to secure workers' compensation coverage for its employees and, if so, the amount of the penalty to be assessed against Respondent.

Findings Of Fact Respondent installs and maintains air conditioning and heating equipment for residential and commercial applications. On May 2, 2017, Respondent was installing a duct system at 3128 East Hillsborough Avenue in Tampa. Two of Respondent's employees were performing work at the site and were not covered by workers' compensation. Leslie Michaud is the president and sole shareholder of Respondent. The air conditioning installation work performed by Respondent's employees is classified by the National Council on Compensation Insurance (NCCI) as class code 5537. This code is for "Heating, Ventilation, Air-Conditioning and Refrigeration Systems Installation, Service and Repair . . . ." During the audit period of May 3, 2015, through May 2, 2017 (Audit Period), code 5537 bore two rates. For the Audit Period, Respondent had no workers' compensation coverage for any of its employees, although it maintained an exemption for Mr. Michaud. For the Audit Period, Respondent's gross payroll was $213,327.49 exclusive of any payments to Mr. Michaud. Applying the manual rates during the Audit Period to the gross payroll yields unpaid workers' compensation premium of $14,870.43.

Recommendation It is RECOMMENDED that the Department of Financial Services, Division of Workers' Compensation, enter a final order determining that Respondent failed to secure workers' compensation coverage for its employees during the Audit Period and imposing a penalty of $29,740.86. DONE AND ENTERED this 7th day of January, 2019, in Tallahassee, Leon County, Florida. S ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of January, 2019. COPIES FURNISHED: Tabitha G. Harnage, Esquire Steven R. Hart Department of Financial Services 200 East Gaines Street Tallahassee, Florida 32399-4229 (eServed) Leslie G. Michaud L and M Airconditioning System, Inc. 49 North Federal Highway, No. 206 Pompano Beach, Florida 33062 Julie Jones, CP, FRP, Agency Clerk Division of Legal Services Department of Financial Services 200 East Gaines Street Tallahassee, Florida 32399-0390 (eServed)

Florida Laws (5) 120.569120.57327.49440.02440.10 DOAH Case (1) 18-4144
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE A. WALLACE, 85-000037 (1985)
Division of Administrative Hearings, Florida Number: 85-000037 Latest Update: Jul. 26, 1985

Findings Of Fact Respondent, George A. Wallace, was, at all times material hereto, licensed as a Class "A" air conditioning contractor by the State of Florida, having been issued license number CA CO13239. Respondent was, at all times material hereto, the qualifier for EMC Corp. On May 14, 1981, EMC Corp. entered into a written agreement with Sophie Griffin to replace the heating and air conditioning unit at Ms. Griffin's home in Fort Lauderdale, Florida. The unit was installed in May, 1981, and Ms. Griffin promptly paid the full contract price of $2,200.00. Section 301(a), South Florida Building Code, provides: It shall be unlawful . . . to install or alter any equipment for which provision is made or the installation of which is regulated by this Code without first having filed application and obtained a permit therefore from the Building Official. A permit shall be deemed issued when signed by the Building Official and impressed with the seal of the governmental agency issuing said permit. Section 301.1(1), South Florida Building Code, provides: Permits, to be issued by the Building Official, shall be required for the following operations: * * * The installation, alteration, or repair of any air conditioning or refrigeration apparatus. . . . The South Florida Building Code has been adopted by Broward County. EMC Corp. installed the new heating and air conditioning unit at Ms. Griffin's home without first having obtained a building permit from the City of Fort Lauderdale, Florida. On March 20, 1984, EMC Corp. obtained the required permit, and paid a penalty of $25.00 for having failed to secure the permit before undertaking the work. On March 26, 1984 an inspector with the City of Fort Lauderdale inspected the installation of the unit and found, contrary to the provisions of Sections 2306 and 4801.10, South Florida Building Code, that the unit had not been anchored. EMC Corp. promptly anchored the unit. Section 4505.1. South Florida Building Code, provides: PERMITS REQUIRED: It shall be unlawful to do or commence to do any electrical work on a new installation of permanent or temporary wiring, any electrical apparatus or equipment or make extensions and/or changes to existing wiring systems . . . without having first filed application and obtained an electrical permit therefore from the Electrical Inspector. APPLICATIONS: Applications for permit will be accepted from only qualified persons or firms. . . . Neither Respondent nor EMC Corp. was a qualified electrician, nor were they licensed by the state of Florida as electrical contractors. EMC, without an electrical permit, connected the wiring of the new unit with the existing electrical service. Respondent contends, and the City of Fort Lauderdale agrees, that it is an accepted practice for an air conditioning contractor to disconnect the leads from an existing air conditioning unit and reconnect them to the new unit, without the necessity of an electrical permit, if there is no difference between the units. In this case the evidence establishes that, although the replacement and existing units were 3-ton units, the amperage demands of the replacement unit were greater than the existing unit, and that the existing wiring was inadequate. However, no hazardous condition was created by EMC Corp. reconnecting the leads from the existing unit to the replacement unit. Apart from the foregoing discrepancies, EMC Corp.'s installation of Ms. Griffin's new unit met all standards established by the South Florida Building Code. Further, EMC Corp. has faithfully fulfilled all warranty and service work it contracted to perform.

Florida Laws (2) 489.113489.129
# 6
NORTH FLORIDA CONSTRUCTION vs DEPARTMENT OF TRANSPORTATION AND PRO-STEEL BUILDINGS, 94-002353BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 28, 1994 Number: 94-002353BID Latest Update: Sep. 15, 1994

The Issue Whether the Respondent acted fraudulently, arbitrarily, illegally or dishonestly in proposing to award a contract for State Project No. 99003-3501 to the Intervenor.

Findings Of Fact The Parties. The Respondent, the Department of Transportation (hereinafter referred to as the "Department"), is an agency of the State of Florida. The Department sought bidders for a construction project by invitation to bid. The Petitioner, North Florida Construction, Inc. (hereinafter referred to as "North Florida"), submitted a bid on the Department's construction project. The Intervenor, Pro-Steel Buildings, Inc. (hereinafter referred to as "Pro-Steel"), also submitted a bid on the Department's construction project. The Subject Invitation to Bid. The Department issued an Invitation to Bid for State Project Number 99003-3501 (hereinafter referred to as the "ITB"). The ITB solicited bids on a construction contract for the relocation of the Department's maintenance yard facility in Tallahassee, Florida. The ITB required that each prime contractor either subcontract at least 25 percent of the total contract price to a Certified Minority Business Enterprises (hereinafter referred to as a "CMBE"), or show a good-faith effort to meet the 25 percent goal. Pages 78-81, Joint Exhibit 1. Included in the Instructions to Bidders, at Section B-14, are instructions concerning "Listing of Subcontractors." Page 15, Joint Exhibit 1. Section B-14 of the ITB provides: In order that the Owner may be assured that only qualified and competent subcontractors will be employed on the project, each Bidder shall submit in triplicate with his proposal a list of the subcontractors who will perform the work for each Division of the Specifications utilizing the "List of Subcontractors" form enclosed as Exhibit 5. The Bidder shall have determined to his own complete satisfaction that a listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this Agreement and is qualified both technically and financially to perform that pertinent phase of this work for which he is listed. . . . Any bidder who lists a subcontractor not certified and/or registered by the State to perform the work of his trade if, such certification or registration is required for the trade by Florida Laws, will be rejected as non-responsive. No change shall be made in the list of subcontractors, before or after the award of a contract, unless agreed to in writing by the Owner. [Emphasis added]. Exhibit 5, List of Subcontractors, provides, in part, the following: THE UNDERSIGNED, HEREINAFTER CALLED "BIDDER", LISTS BELOW THE NAME OF EACH SUBCONTRACTOR WHO WILL PERFORM THE PHASES OF THE WORK INDICATED. FAILURE OF THE BIDDER TO SUPPLY SUFFICIENT INFORMATION TO ALLOW VERIFICATION OF THE CORPORATE, AND DISCIPLINE LICENSE STATUS OF THE SUBCONTRACTOR MAY DEEM THE BID AS BEING NON-RESPONSIVE. Page 55, Joint Exhibit 1. Exhibit 5 was required to be completed and submitted with all bids pursuant to Section B-14 of the ITB. From the technical specifications for Heating, Ventilation and Air Conditioning work (hereinafter referred to as "HVAC"), for the project at issue, it could be inferred that two 30-ton air conditioning units were required. The Bids Submitted by Pro-Steel and North Florida. Bids on the ITB were submitted and opened on March 24, 1994. North Florida submitted a bid in response to the ITB: On the envelope containing the sealed bid of North Florida, North Florida requested that $14,000.00 be deducted from its proposed contract price. North Florida submitted a bid of $2,997,007.00. North Florida was the apparent second low bidder. North Florida listed Gallon & Sons as the subcontractor responsible for HVAC work. North Florida also listed Gallon & Sons as a CMBE. Gallon & Sons was listed on Exhibit 5, the Minority Business Enterprise Utilization Summary, submitted with North Florida's bid. North Florida proposed to install two 30-ton air conditioning units. Pro-Steel also submitted a bid in response to the ITB. Pro-Steel submitted a bid of $2,993,000.00. Pro-Steel was the apparent low bidder. Pro-Steel listed "Watts Mechanical" as the subcontractor responsible for the HVAC work required by the ITB. Pro-Steel also listed Watts as one of two CMBE subcontractors. "Watts Mechanical" was listed on Exhibit 5, the Minority Business Enterprise Utilization Summary, submitted with Pro-Steel's bid. Pro-Steel's bid submittal proposed the installation of two 30-ton air conditioning units. The Department's Decision. It is the policy of the Department to waive minor irregularities in bid submittals. Irregularities with North Florida's bid were correctly determined to be minor by the Department and were waived. The bid tabulation sheet and the bids indicated that Pro-Steel submitted the lowest, responsive bid. The Department proposed to award the contract under the ITB to Pro-Steel. Without Watts as a CMBE, Pro-Steel would not meet the 25 percent CMBE participation goal of the ITB. The Department's project manager for the ITB determined that Watts was a CMBE in evaluating the bid submittals. Qualification of CMBE's to Perform Work Proposed. Gallon & Sons was at all times relevant to this proceeding, registered as a CMBE in hearing and air conditioning. Eddie Gallon, Sr., was at all times relevant to this proceeding, the registered qualified agent for Gallon & Sons. Mr. Gallon holds a Class A license in heating and air conditioning. The stock of Watts Mechanical, Inc. (hereinafter referred to as "Watts"), is owned 100 percent by Jacqueline Watts. Ms. Watts is also the President of Watts. Ms. Watts held and still holds a Class B HVAC license from the Department of Business and Professional Regulation. Ms. Watts was registered with the Department of Business and Professional Regulation as the qualifying agent for Watts. Watts was registered with the Department of Management Services as a CMBE under the category of heating and air conditioning contractors. On January 1, 1994, Watts acquired the assets of Energy Systems of Tallahassee (hereinafter referred to as "Energy Systems"). Energy Systems was then owned by Thomas Trapane. As of January 1, 1994, it was intended that Watts be renamed "Watts Mechanical and Energy Systems, Inc." Mr. Trapane held and still holds a Class A HVAC license from the Department of Business and Professional Regulation. Mr. Trapane was registered with the Department of Business and Professional Regulation as the qualifying agent for Energy Systems. As of January 1, 1994, Mr. Trapane became an employee of Watts. As of March 24, 1994, when bids were submitted on the ITB: Watts had not filed an amendment to its Articles of Incorporation reflecting the change in name to Watts Mechanical and Energy Systems, Inc. (hereinafter referred to as "Watts Mechanical and Energy"). The amendment was not filed until April 26, 1994. Mr. Trapane had not registered with the Department of Business and Professional Regulation as the qualifying agent for Watts or Watts Mechanical and Energy. It was not until May 2, 1994, that the Department of Business and Professional Regulation issued a letter indicating that Mr. Trapane was a secondary qualifying agent for Watts Mechanical and Energy. Watts had not notified the Department of Management Services of its name change with regard to its CMBE certification. Based upon the foregoing, at the date of the submittal of bids and the proposed award of contract pursuant to the ITB, Watts did not hold the license required in order for it to complete the work Pro-Steel had represented to the Department Watts would perform. Substitution of Subcontractors. It is the policy of the Department to allow contractors to substitute subcontractors for good cause if proper documentation is submitted. The evidence, however, failed to prove the Department's policy concerning substitution of subcontractors applies in this matter. The evidence also failed to prove that the Department's policy concerning substitution of contractors allows the Department to accept as meeting part of the CMBE requirement of the ITB a CMBE that was not qualified to perform the required work as of the date of bid award. Alternative Proposals. The ITB allows substitutions for specified systems or products contained in the ITB. Page 28, Joint Exhibit 1. Substitutions, however, must be requested of the Architect-Engineer and written approval from the Architect-Engineer must be obtained. Substitutions must be submitted within 45 days after award of the contract. No substitutions were submitted by Pro-Steel or Watts at the time of bid submittal. As of the date of the final hearing of this case, Watts had decided to suggest that the configuration of the HVAC of the project be changed in a manner that would not require a Class A license for the work to be performed. The evidence failed to prove that the Department was aware of this proposal at the time of its initial decision.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Transportation enter a Final Order declaring the bid submitted by Pro-Steel Builders, Inc., to be non-responsive. DONE AND ENTERED this 13th day of June, 1994, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of June, 1994 APPENDIX Case Number 94-2353BID The parties have submitted proposed findings of fact. It has been noted below which proposed findings of fact have been generally accepted and the paragraph number(s) in the Recommended Order where they have been accepted, if any. Those proposed findings of fact which have been rejected and the reason for their rejection have also been noted. North Florida's Proposed Findings of Fact Accepted in 2 and hereby accepted. Accepted in 1. Accepted in 3 and hereby accepted. Accepted in 4 and 10. Accepted in 10-11 and 13. Accepted in 6-8. Accepted in 14. Accepted in 15. Accepted in 7. Accepted in 25 and 32. Conclusion of law. Accepted in 9. Conclusion of law. See 27 and 32. Accepted in 32. Accepted in 15. Accepted in 20. Accepted in 7-8. See 33. The Department's Proposed Findings of Fact Accepted in 4. Accepted in 2-3 and 11-12. Accepted in 6. Accepted in 10-11. Accepted in 11 and 13. Accepted in 11 and 15. See 26, 28 and 32. Watts Mechanical, Inc. was a CMBE at the time of bid submittal. Watts Mechanical & Energy Systems, Inc., did not exist at the time of bid submittal. Accepted in 22. Accepted in 9. 9 Accepted in 24. 10-11 Accepted in 25. Accepted in 31. Accepted in 29. Accepted in 32. Accepted in 23. Hereby accepted. Accepted in 20. Accepted in 21. Accepted in 36. But see 37-38. Not relevant. See 7. Accepted in 8. 23 See 36-38. Not relevant. Accepted in 17. Pro-Steel's Proposed Findings of Fact Accepted in 4. Accepted in 7-8 Accepted in 8. Not supported by the weight of the evidence. Accepted in 34. See 35. Accepted in 17. 7 Accepted in 2-3, 10-11 and 18-19. Accepted in 14. Accepted in 9 and 36. See 25-26. But see 32. Accepted in 27, 29 and 31. The last sentence is not relevant. Accepted in 32. Not supported by the weight of the evidence. 14 See 34-35. 15 See 36-39 COPIES FURNISHED: Ben G. Watts, Secretary Attn: Eleanor F. Turner, M.S. 58 Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0450 Thornton J. Williams General Counsel 562 Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0450 Thomas H. Duffy Assistant General Counsel Department of Transportation Haydon Burns Building, M.S. 58 605 Suwannee Street Tallahassee, FL 32399-0458 Tommy Strickland North Florida Construction, Inc. Post Office Box 129 Clarksville, Florida 32430 Stephen J. Kubik, Esquire 155 Office Plaza Drive Tallahassee, Florida 32301

Florida Laws (3) 120.53120.68489.113 Florida Administrative Code (1) 60A-1.002
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CHARLIE S. HIERS, 82-003329 (1982)
Division of Administrative Hearings, Florida Number: 82-003329 Latest Update: Jun. 07, 1983

Findings Of Fact Respondent Charlie S. Hiers is registered as a Class B air conditioning contractor and qualifier for Hiers Air Conditioning and Refrigeration, Orlando, Florida. As of July 1, 1979, his license became delinquent. (Petitioner's Exhibit 1) In December, 1981, Myrtle D. Harris, who resided at 7505 Ranchero Street, Orlando, engaged the services of Respondent to repair the air conditioning unit at her home. He had performed satisfactory air conditioning work for her on two prior occasions in 1979 and 1980. She had originally contacted him through an ad in the telephone directory under the name "Temp Control Service." On each occasion she had given him a check payable to Temp Control Services which was later endorsed in that name by Respondent. (Testimony of Harris, Petitioner's Exhibits 2-3) Respondent advised Mrs. Harris on December 2, 1981, that the compressor of her air conditioning unit needed to be replaced with a new compressor. She thereupon gave him a check in the amount of $546.00 and he provided her with a bill marked paid in that amount. Her chock, dated December 2, 1981, was made payable to Charlie Hiers, and his bill of the same date merely had his handwritten name at the top. Mrs. Harris later added the words "Temp Control" in the payee portion of the check after it had been endorsed by Respondent and returned after payment. (Testimony of Harris, Petitioner's Exhibits 4-5) Respondent proceeded to remove the old compressor and later came by Mrs. Harris' house and told her that he had had to order a replacement part. However, he never came back to her home or performed the work for which he had been paid. Mrs. Harris attempted to reach Respondent by leaving her telephone number at his answering service but received no reply. Later, sometime in January, Respondent telephoned her and stated that he had the compressor on his truck and would install it on a specified date. However, he never fulfilled his promise. Mrs. Harris attempted to reach him on subsequent occasions by telephone, but was unable to contact him. On February 1, 1982, Mrs. Harris had her nephew write a letter to Respondent requesting that he either perform the work or return the payment of $546.00. Several months later, after not having heard from the Respondent, Mrs. Harris purchased a new air-conditioner. Respondent has taken no action to perform his agreement or to return the amount which he was paid. (Testimony of Harris)

Florida Laws (4) 489.115489.119489.127489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DENVER SAMMONS, 86-003516 (1986)
Division of Administrative Hearings, Florida Number: 86-003516 Latest Update: Aug. 05, 1987

Findings Of Fact At all times pertinent to the issues herein, the Respondent, Denver Sammons, was licensed by the State of Florida as a registered air conditioning contractor, Class B, and Respondent qualified Denny's Air Conditioning Service under his license. At the January 8, 1985 meeting of the Broward County Central Examining Board of Mechanical Technicians, (Board), the Board heard a complaint by Port Distributors, a local air conditioning supplier, to the effect that Mr. Sammons had submitted two checks to that company in August, 1982, both of which were returned for insufficient funds and that neither had been redeemed. The Board decided to notify the Respondent of the complaint against him and give him an opportunity to respond at the next regularly scheduled meeting of the Board which was held on March 12,1985. At that Board meeting, at which Respondent was present, Mr. Julius M. Farinhouse, Jr., representative of Port Distributors, outlined its complaint against the Respondent detailing the circumstances surrounding the issuance of the bad checks and the need by the recipient to secure a judgment against the Respondent for the amount represented by the checks. There was evidence presented to the Board that these checks issued to Port Distributors were not the only checks written by Respondent that were not properly and promptly honored. Respondent testified before the Board regarding the circumstances surrounding the issuance of the checks and contested the seriousness of the offense alleging that when notified of the bad checks, he had reimbursed Port Distributors for the majority of the sum covered by the two dishonored checks, but this repayment was applied toward current accounts rather than in satisfaction of the bad checks, contra to the intention of the Respondent. Having considered both the testimony presented by the complainants and the Respondent, the Board, that same date, March 12, 1985, nevertheless entered a Final Order finding that the passing of bad checks to Port Distributors by the Respondent constituted an act involving dishonesty, fraud, deceit, or lack of integrity in the operation of Respondent's contracting business; that he failed to make any effort to pay the outstanding bill owed to Port Distributors; and that this misconduct constituted a failure to comply with the standards of Section 9-7, Broward County Code. As a result, the Board ordered the Respondent's Broward County Certificate of Competency revoked that date. The Order of the Board made provision for Respondent to apply for reinstatement of his Certificate of Competency but no such application has ever been made. For several years prior to the issuing of the Certificate of Competency by Broward County, Respondent had, under the old procedure, held a Certificate of Competency issued by the City of Hollywood, Florida and had, each year, renewed that Certificate upon the payment of a $30.00 fee. The Certificate issued by the city was renewed effective January 1, 1985 and reflected on its face, that it was good until December 31, 1985. However, when the Broward County Board of Mechanical Technicians began to issue its county-wide Certificate of Competency, all prior city-issued certificates were declared to be null and void. As a result, though Respondent continued to hold his Hollywood certificate, it was ineffective and he should not have been allowed to renew it by the city, since he was, at that time, covered by a county Certificate of Competency. By action of the Board on March 12, 1985, Respondent's Board (County- wide) Certificate of Competency, which was the only valid certificate he held at the time, was revoked. Because of this revocation, Respondent was, thereafter, allowed to work as a journeyman for another Master Technician but could not contract in his own name or for his own business nor could he pull building permits from any county or city building office. Notwithstanding this, on or about August 12, 1985, Respondent entered into a contract acting as Denny's Air Conditioning, with Isabel Parra. This contract was to remove her old heating and cooling system in her residence at 2207 North 46th Avenue in Hollywood and to install a new unit to consist of a three ton gas furnace with air conditioning coil and condenser. Pursuant to the contract, Respondent did, in fact, remove the old unit and install a new one. However, he did not pull a building permit with the county or city building office and on August 26, 1985, officials of the City of Hollywood issued a Notice of Violation to Mrs. Parra reflecting that Denny's Air Conditioning installed a central air conditioning unit without permit and without possessing a valid contractor's license. Mrs. Parra further contended that when she turned on the unit, the noise it made was extremely loud and not to her satisfaction. Evidence introduced by both Petitioner and Respondent, however, indicates that the Respondent installed the new unit exactly as the old unit had been installed. Mrs. Parra testified that she had not heard the old unit in its heating mode and therefore had no idea whether it made as much noise as the new unit did. In any event, she withheld some of the funds that were due Respondent until such time as he agreed to have someone come out and correct the problem. It has been several months since the parties agreed to this and Respondent still has not corrected the problem. He contends that the contractor with whom he arranged to correct Ms. Parra's problem has been unable to get with her since she works during the days and is home only in the evenings. In any event, though not charged as a violation, it would appear that Respondent has failed to follow through on his work and on his commitment to complete an acceptable installation for Mrs. Parra. Petitioner also alleges that on or about June 25, 1985, the Broward County Consumer Protection Board issued a cease and desist order to Respondent for representing that he was qualified to perform contracting work in Broward County without possessing local competency. No evidence was introduced, however, to satisfy or establish this allegation. Because of the dispute between Mrs. Parra and the Respondent, and her dissatisfaction with the quality of his installation, she filed a complaint with the Board and on December 10, 1985, the Board again met and heard her testimony and that of Mr. Sammons. As a result, on December 20, 1985, the Board found that Respondent's contract with Mrs. Parra was based on a representation to her that he was a contractor when in fact the prior action of the Board had denied him this status. The Board further found that he failed to pull a permit for the installation of the unit in Ms. Parra's home and thereafter failed to comply with the warranty given to her under the contract executed by him on August 12, 1985, nor did he provide her with the rebate promised. Based on these Findings of Fact, the Board concluded that the Respondent willfully, deliberately, or negligently disregarded or violated the provisions of the South Florida Building Code; that he contracted to act as a qualifying agent for his business when he was not certified to do so; that he contracted and did work which was not within the description of the class (journeyman) for which he had been certified by the Board; and that he abandoned without legal excuse a construction project in which he was engaged and under contract to complete. As a result, the Board ordered that his journeyman's Certificate of Competency be revoked effective that day. Once the journeyman's certificate was taken away, Respondent was not authorized to act as an air conditioning installer or contractor under any circumstances. Notwithstanding this, on February 20, 1986, Respondent again, acting as Denny's Air Conditioning, entered into a contract with Dr. Eisenstein to install a new two-ton split system in the doctor's home in Hollywood for a total price of $2,530.00. Since Dr. Eisenstein had previously dealt with Respondent on several occasions and found him to be reliable, the doctor responded to Respondent's request for an advance by giving him a $2,000.00 deposit. The contract was not actually finalized until late in March, 1986 and work was to begin in early April. However, on April 1, 1986, Respondent called Dr. Eisenstein and advised him that his truck, in which was stored the equipment for installation into the doctor's home and the money bag which contained the balance of the doctor's downpayment had been illegally repossessed by Respondent's bank the night before. As a result, Mr. Sammons indicated he would not be able to begin the project but assured the doctor that someone else would do so starting at the end of the week. In fact, no work was ever started by the Respondent or anyone else on his behalf. After several days, when Dr. Eisenstein attempted to call Respondent, he found that Respondent's phone had been disconnected and when on April 5, 1986, the date promised by Respondent, no one came to begin work on the project, the doctor began undertook an investigation which led to the ultimate contact of the doctor by the Respondent. To reach Respondent, Dr. Eisenstein had checked with Respondent's business landlord and when Respondent finally called the doctor back, he was irate that the doctor had done so. During that conversation Dr. Eisenstein advised Respondent that he should either repay the money advanced or do the work. In fact, neither was done. During the month of April, 1986, Dr. Eisenstein sent Respondent two letters by certified mail requesting that he either refund the advance payment or do the work promised under the contract. One letter was returned undelivered. The other was apparently delivered. When neither letter resulted in any satisfaction, the doctor, in early June, 1986, sent a letter of complaint to DPR outlining the situation. Respondent tells an incredible tale regarding the facts and circumstances which led up to the dispute with Dr. Eisenstein. Admitting that he was somewhat in debt to his bank, he claims that certain payments that he made to the bank with part of the money advanced by the doctor was used improperly by the bank and applied toward other obligations rather than the debt on his truck. He claims the repossession of the truck was illegal and improper because, by the payment mentioned above, if properly applied, the truck would have been paid off. This story is almost a duplicate of that regarding the excuse for the bad checks to Port Distributors. Respondent further contends that that bank thereafter engaged in a conspiracy against him to bring about his financial ruin; that the bank hired several individuals to assault him and his wife outside their church; that he has received several threats of bodily harm from the bank; and that all of this has resulted in his filing suit against the bank in local court. This story was told by the Respondent under oath. However, Respondent failed to provide any names or documentation to support this with the exception of the name of the bank allegedly involved. When asked where copies of the documentation were that would support his allegations, he responded with, "Oh, they're at home in a file." In short, it would appear that Respondent's story is a gossamer of fantasy which, while possibly believed at this point by Respondent, has very little basis in fact. Respondent also contends, for example, that Dr. Eisenstein requested that he not pull a permit for the work to be done at his house because he did not want city officials for one reason or another to know that the work was being done. This information was not brought out through Dr. Eisenstein, but rather through the testimony of the Respondent. None of these stories were backed up by any document or supporting evidence. Consequently, it is found that while Respondent may well believe what he is saying, his are in fact, incredible. Respondent was disciplined on two separate occasions by the Broward County Central Examining Board of Mechanical Technicians and Respondent has not shown that these actions were procedurally violative of due process. Consequently, they are found to have occurred and to be valid. Respondent was not permitted to attack the circumstances leading up to the action by the board and the Hearing Officer declined to relitigate the factual propriety of the Board's two actions. Once having lost his Master Technician's license, Respondent was no longer authorized to pull building permits in Broward County and notwithstanding that, nonetheless did commence work for Mrs. Parra on a job which, under the ordinances of the county, required a permit be pulled. He also failed to live up to the terms of a warranty inherent in his contract with her. The evidence also established that subsequent to the withdrawal of his Journeyman's certificate, he nonetheless entered into a contract for the installation of a system in Dr. Eisenstein's house and accepted a substantial advance payment which he neither returned nor earned when he failed to begin any work on the project. In the opinion of the Petitioner's expert, Respondent's conduct in this instance was totally unprofessional and unethical. In fact, as a professional, if the circumstances occurred as alleged by Respondent, he should have made immediate arrangements to in some way make restitution of the funds to his client or have the work done by someone else. The evidence here shows that Respondent made no effort to make some accommodation to the client. He entered no promissory note (Respondent claims that as a gentleman, he has no need of notes as his word is sufficient); he made no attempt to let the client know what had happened; and in short, it appears that Respondent was out to make a quick buck (the expert's phrase) without attempting to in any way satisfy his client.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Respondent's license as a registered air conditioning contractor be revoked. RECOMMENDED this 5th day of August, 1987, at Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of August, 1987. COPIES FURNISHED: G. Vincent Soto, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mr. Denver Sammons Post Office Box 7437 4614 Madison Street Hollywood, Florida 33021 Mr. Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Van B. Poole, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Joseph A. Sole, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (3) 120.57489.117489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer