The Issue The issue is whether Petitioner's application to sit for the water well contractor examination should be approved.
Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: On January 9, 2004, Petitioner, who resides in Baker County, Florida, filed his application with the District requesting that he be allowed to sit for the water well contractor examination. The requirements for qualification to take the examination are set forth in Florida Administrative Code Rule 62-531.300. Relevant to this controversy is the requirement that an applicant present "satisfactory proof of two years experience in the water well construction business." This requirement is normally met by the applicant providing a list of at least ten water well jobs he has completed during a consecutive 24-month period (together with their locations, major use, and approximate depth and diameter), the name and address of the owner of the well, and the approximate date the activity took place. See Fla. Admin. Code R. 62-531.300(6)(a). If the work has been completed in Florida, the applicant is also required to submit copies of completion reports for each of the ten wells. Id. Completion reports are filed by the contractor with the District within thirty days after the work is completed. See Fla. Admin. Code R. 40C-3.411. Finally, the applicant must submit letters from three persons attesting to the length of time the applicant has been working in the water well construction business as a major activity. See Fla. Admin. Code R. 62-531.600(6)(a). Alternatively, an applicant may present "satisfactory proof of equivalent experience," which may be accepted by the District "on a individual basis." See Fla. Admin. Code R. 62- 531.300(6)(b). While this option has rarely, if ever, been used by any applicant, at hearing the District suggested that this provision would allow an applicant to submit other credible documentary evidence, such as affidavits, attesting to the applicant's equivalent experience. Mr. Julian C. Varnes, Jr., a District water resource representative III, is in charge of reviewing water well contractor applications in four northeast Florida counties, including Baker County. Mr. Varnes reviewed Petitioner's application and concluded that he had failed to submit proof of two years' experience in the water well contracting business or satisfactory proof of equivalent experience, as required by the rule. In this case, Petitioner submitted ten completion reports with his application, but none of the reports indicated that he had been involved on those projects, and Petitioner acknowledged at hearing that he could not recall if he was even present on the job site. This is probably because the reports related to jobs performed between November 10, 1982, and July 31, 1985, by his father, a licensed water well contractor, when Petitioner was less than fifteen years old. In addition, the reports submitted by Petitioner covered work performed over a 32-month period, rather than over a 24-month period, as required by the rule, and some of the reports did not have the complete address of the location of the well. By letter dated February 4, 2004, the District advised Petitioner that his application was deficient because he had failed to submit the information required in Florida Administrative Code Rule 62-531.300(1)(b) and (6) relative to experience. The letter advised Petitioner that he must submit an "acceptable list of ten wells together with their completion reports, for wells that [he had] constructed, repaired, or abandoned, with completion dates distributed over a consecutive 24-month time period." Further telephonic discussions between Petitioner and District personnel concerning the request for additional information occurred on March 25 and 29, 2004, but they did not resolve the District's concerns. On June 15, 2004, the District staff again notified Petitioner in writing that he must submit the requested information within 30 days or his application would be denied. When no response was received from Petitioner, on July 27, 2004, the staff issued a Technical Staff Report recommending that the application be denied because of Petitioner's failure to comply with the requirements of Florida Administrative Code Rule 62- 531.300(1)(b) and (6). On August 23, 2004, a Notice of Staff Intent to Recommend Denial of Water Well Contractor Application No. 7300 and Notice of Rights was issued by the District. Petitioner's request for a hearing was then filed. After his first request for a hearing was dismissed, on November 18, 2004, Petitioner filed an amended request for a hearing. In that request, he alleged that the District was "not capable of locating completion reports filed by [Petitioner] and/or his father"; that the experience of he and his father was well known to two District staffers; that he had purchased a well drilling company from another individual and operated under the seller's license for over a year; that he is entitled to licensure because he has satisfactory equivalent experience; and that his father has paid all outstanding fines previously imposed by the District. As relief, Petitioner has requested that he be allowed to take the contractor's examination. At hearing, Petitioner explained that his father was in the water well contracting business for twenty years, and that beginning in 1983, when he was thirteen years old, he had helped his father on "hundreds of jobs" until his father's retirement in 1994. However, Petitioner cannot recall the names and addresses of customers who were serviced by his father's business, which is necessary in order for the District to retrieve completion reports presumably filed by his father. Because of the large number of completion reports filed by contractors throughout its multi-county jurisdiction, in order to retrieve one, the District must have the following information: the year the job was completed, the county in which the job was performed, and the address (township and range) of the well's owner. Petitioner is unable to provide this information.1 In addition, Petitioner stated that he had purchased a water well contractor's business (from Tim Johnson) shortly after his father retired in 1994 and that he operated the business under Mr. Johnson's license for a little more than a year. Although Petitioner produced no documentation concerning jobs he may have performed under Mr. Johnson's license, even if he had, that work would still constitute less than 24 consecutive months of experience, as required by the rule. Petitioner further asserted that Mr. Varnes, who oversees the water well contractors in Baker County, personally "knows" that he is an experienced well driller (having gained such experience through working for his father for many years) and that he possesses the skills necessary to take the examination. However, Mr. Varnes did not agree with this assertion. Finally, Petitioner asked that he be allowed to take the examination, which would be the best indicator of whether he possesses the necessary knowledge to be a contractor. He also pointed out that each completed project must be inspected by a District employee, and that such inspections would verify and ensure that his work is satisfactory. However, the rules require that before the examination can be taken, certain requirements must be met. Petitioner has not satisfied those requirements.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the St. Johns River Water Management District enter a final order denying Petitioner's application to sit for the water well contractor examination. DONE AND ENTERED this 25th day of January, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of January, 2005.
The Issue Whether Betmar Utilities, Inc.'s application for an expansion of territory under its water and wastewater certificates in Pasco County should be approved by the Public Service Commission.
Findings Of Fact Betmar Utilities, Inc. is a private utility company who owns and holds Florida Public Service Commission Certificates Number 137W and No. 98S. These certificates grant Betmar the right to operate a water and wastewater system in a specified territory within an unincorporated area of Pasco County. Betmar seeks an extension of its certified territory into the areas immediately to the north and south in an unincorporated area of the county. There is, or will be in the near future, a need for water and wastewater services in the proposed amended territory. An Application for Amendment of Territory was filed with the Commission to allow Betmar to service the area on November 13, 1989. When Betmar noticed the City of its pending application, an objection was filed to the proposed expansion. The objection specifically relates to the property on the south side of Geiger Road, which extends 330 feet south of the roadway, and adjoins the City's boundaries. Although the City does not currently provide services to this locale, it does own water and sewer lines on the northern side of Geiger Road in the Silver Oaks area. Other water and sewer lines in the City's system extend below the south side of Geiger Road at the far eastern portion of the area for which Betmar is seeking the extension of territory. In an interlocal agreement between the City and the County dated February 9, 1988, these governmental entities established designated service areas for water and wastewater services in this particular area of the county. The purpose of the agreement was to promote the economic delivery of services to citizens in the area, and to provide for the necessary long-range planning inherent in the provision of these services. Prior to the agreement, the County was authorized to provide the services to the areas for which an extension is sought by Betmar. The service area boundaries delineated in the agreement were to be periodically reviewed in conjunction with the review of each party's respective comprehensive plans. Pursuant to this agreement, the City and County determined that the City's Service Area Boundry would include the area south of Geiger Road that abuts Betmar's current service area. The City and the County each relied upon this interlocal agreement in the creation of their respective comprehensive plans. However, no additional action has been taken by the City to service the area. The City is not actually operating within the disputed area for a number of reasons. First of all, the City has adopted an ordinance which requires annexation of contiguous property as a condition of receiving its water and sewer services. The disputed portion of the proposed amended territory is not within the city limits and has not been annexed. Secondly, the City is not prepared to build utility lines to service the disputed proposed amended territory until the new bypass road along Geiger Road is built, and the proper right-of-way is obtained. At that time, the City would like to extend the Silver Oaks line under Geiger Road to the south, and the line along the eastern side of the disputed portion of territory to the west. These anticipated expansions correlate with the City's Service Area Boundry in the interlocal agreement which remains unchanged between the City and the County. A proposed service date was not provided by the City at the formal hearing. The City seeks to control land use and development of property along the Geiger Road corridor though its ability to provide or withhold utility services. Betmar also has water and sewer lines abutting or located on all properties described in its application for extension, including the area in controversy. These lines are currently active due to Betmar's water and sewer system which is in the center of the area targeted for expansion. Both Betmar and the City have the technical and financial ability to provide water and wastewater services in the proposed amended territory. Betmar has a tariff approved by the Commission which allows it to charge 110% of the cost of the extension of service from its existing lines to any property seeking service. Owners of property abutting Geiger Road have contacted Betmar about the possibility of providing service. A formal request for service has been made by Jake Developers for service in that area. Betmar's sewage collection facilities abutting the Geiger Road property are gravity lines. The City's sewage collection facilities in close proximity to the area are force mains. Betmar does not charge impact fees for connection into its system. The City charges a water impact fee of $350.00 and a sewer impact fee of $1,278.00 for connection into its system. Betmar anticipates a reduction in water and sewer rates if the extension is approved. Betmar presented no evidence about plans for further financial investment which would enable the utility to provide service in the area for which the extension has been requested because Betmar believes further investment is unnecessary. Betmar has an agreement with the County that states the County will provide bulk wastewater treatment to Betmar for the purpose of offering centralized wastewater services from the County's Southeast Subregional Wastewater Treatment Plant for a twenty-five year term. The County has placed a possible qualification on the term of years in the agreement by inserting the following clause: ... its first responsibility is to the customers inside its own service limits and that it reserves the right to act in the best interest of those customers in all circumstances. The agreement between the County and Betmar has not been approved by the Commission.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: The Commission should deny Betmar's application for an amendment to its certified territory in Pasco County as the applicant has failed to provide that it will be allowed the continued use of the County's Southeast Subregional Wastewater Treatment Plant for the twenty-five year term set forth in the agreement presented at hearing. DONE and ENTERED this 16th day of July, 1991, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of July 1991. APPENDIX TO RECOMMENDED ORDER Petitioner's proposed findings of fact are addressed as follows: 1. Accepted. See HO #2. 2. Accepted. See HO #1. 3. Accepted. See HO #3. 4. Accepted. See HO #11. 5. Accepted. See HO #4. 6. Accepted. See HO #9. 7. Accepted. See HO #11. 8. Accepted. See HO #13. 9. Accepted. See HO #14. 10. Accepted. See HO #9. 11. Accepted. See HO #9. 12. Accepted. See HO #11. 13. Accepted. Rejected. Improper legal conclusion. Accepted. See HO #5. Accepted. See HO #8. Accepted. See HO #14. Accepted. See HO #14. Accepted. Accepted. Accepted. Accepted. Accepted. See HO #15. Accepted. See HO #15. Accepted. See HO #16. Rejected. Improper legal conclusion. See HO #17. Accepted. See Preliminary Statement. Respondent's proposed findings of fact are addressed as follows: Accepted. See Preliminary Statement. Accepted. See Preliminary Statement. Accepted that an interlocal agreement between City and county existed. See HO #5. The rest of the paragraph is rejected as legal argument. Intervenor's proposed findings of fact are addressed as follows: 1. Accepted. See HO #2. 2. Accepted. See HO #12. 3. Accepted. See HO #12. 4. Accepted. See HO #3. 5. Accepted. See HO #11. 6. Accepted. See HO #4. 7. Accepted. See HO #12. 8. Accepted. See HO #9. 9. Accepted. See HO #9. 10. Accepted. See HO #9. 11. Accepted. See HO #5. COPIES FURNISHED: Scott L. Knox, Esquire 28870 U.S. Highway 19 North Suite 230 Clearwater, Florida 34621 Thomas P. McAlvanah, Esquire 37818 Highway 54 West Zephyrhills, Florida 34248 Robert J. Pierson, Esquire Florida Public Service Commission 101 East Gaines Street Tallahassee, Florida 32399-0863 David Swafford, Executive Director Florida Public Service Commission 106 Fletcher Building 101 East Gaines Street Tallahassee, Florida 32399-0850 Steve Tribble, Director Records and Recording Florida Public Service Commission 101 East Gaines Street Tallahassee, Florida 32399 Susan Clark, General Counsel Florida Public Service Commission 212 Fletcher Building 101 East Gaines Street Tallahassee, Florida
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: The Tamaron wastewater treatment facility (facility), located at 3800 Gatewood Drive, Sarasota, Florida, serves the Tamaron residential subdivision which was originally developed by U. S. Homes Corporation in 1976. The subdivision presently consists of 499 homes and was completely built out in the mid-1980's. The facility was originally owned and operated by U. S. Homes Corporation. Tamaron Utilities, a nonprofit entity comprised of the 499 homeowners, acquired the facility in November, 1987. At that time, the facility's existing operating permit was transferred to Tamaron Utilities. The facility is overseen by an elected board of volunteer homeowners. The Department is the agency of the State of Florida that is authorized to regulate domestic wastewater treatment and disposal facilities and permit their construction and operation. It is the successor agency to the Department of Environmental Regulation. By letter dated November 10, 1987, the Department notified Tamaron of the requirements of Chapter 87-303, Laws of Florida (Grizzle-Figg Amendment), which amended Section 403.086, Florida Statutes, and of the Department's intention to modify Tamaron's operating permit to incorporate a schedule of compliance with Section 403.086, Florida Statutes, as amended by Chapter 87-303, Laws of Florida. On August 23, 1988, an operating permit (D058-141783), which contained secondary water treatment requirements, was issued to the facility. Specific condition 7 of the permit required that the facility be in compliance with the Grizzle-Figg Amendment by October, 1990, or eliminate discharge to surface waters. On September 5, 1990, Tamaron filed an application with the Department to renew its domestic waste water treatment and disposal systems operation permit. Tamaron did not consider its facility as discharging waste into one of the specifically named water bodies set forth in the Grizzle-Figg Amendment or to "water tributary thereto" and thereby required to meet the advanced waste treatment criteria set forth in the Grizzle-Figg Amendment. However, in an abundance of caution, Tamaron proceeded to bring its facility into compliance with the advanced waste treatment criteria as set forth in the Grizzle-Figg Amendment. After numerous requests for additional information and several meetings between Tamaron and the Department, the Department issued its Notice of Permit Denial on April 9, 1991, asserting that Tamaron had not provided: (a) reasonable assurance that the requirements of Section 403.086(1)(c), Florida Statutes, mandating advanced waste treatment (AWT) before discharge to certain designated surface waters, would be met and; (b) reasonable assurance that the discharge to those certain designated surface waters would result in minimal negative impact as required by Section 403.086(5)(a), Florida Statutes. The facility continues to operate under its secondary treatment permit No. DO58-141783. The facility consists of a wastewater treatment plant designed for secondary treatment, with tertiary filtration. The design capacity of the facility is 155,000 gallons per day (0.155MGD) with actual flows of slightly over 100,000 gallons per day (0.100MGD+). Three percolation ponds surround the facility comprising the primary effluent disposal method for the facility. The Tamaron subdivision has a series of excavated surface water bodies (stormwater lakes), hydraulically connected, which eventually discharge at the northeast corner of the subdivision into Phillippi Creek. The direct path of surface water flow is from the subdivision's stormwater lakes to Phillippi Creek. These stormwater lakes are in multiple ownership. Under Department policy, stormwater systems permitted by the Department, its predecessor DER, or a water management district solely as stormwater treatment facilities under Chapter 17-25, Florida Administrative Code, are not considered "waters of the State". However, stormwater systems built prior to Chapter 17-25, Florida Administrative Code, permitting requirements, were considered "waters of the State" if they discharge more frequently than a twenty five year, twenty-four hour storm event. See Petitioner's exhibits 13 & 15. Tamaron's stormwater system was built prior to Chapter 17-25, Florida Administrative Code, permitting requirements, and was designed to discharge at a ten year, twenty-four hour storm event which is more frequent than a twenty five year, twenty-four hour storm event. Discharge of water into Phillippi Creek from the subdivision's stormwater lakes is fairly frequent; however, the volume of the discharge is low. Phillippi Creek is a natural surface water which eventually flows into Roberts Bay. Roberts Bay is a specifically named water body in the Grizzle-Figg Amendment (Section 403.086(1)(c), Florida Statutes). Since September, 1989, Tamaron has retained William Murchie, P.E. of AM Engineering, to evaluate the design and operation of the facility in order to comply with appropriate regulatory requirements. The facility provides biological treatment through a contact stabilization utilizing an activated sludge. This process typically provides high quality advanced secondary biological treatment. A chemical feed tank system utilizing ferrous sulfate was added to the facility several years ago to chemically precipitate out total phosphorus to meet the advanced waste treatment requirements. High-level disinfection is achieved in the large chlorine contact chamber and through two tertiary filters. At the design flow of 0.155MGD, the chlorine contact chamber provides nearly 80 minutes of contact time, while actual contact time for existing flows, not including time in filters, is calculated at 110 minutes. Upon leaving the chlorine contact chamber and the biological treatment components of the facility, the chlorinated effluent is directed through two tertiary filters to reduce the biochemical oxygen demand (BOD) and total suspended solids (TSS). After the tertiary filters, the effluent passes through the sample block where it is sampled for TSS, BOD and chlorine and is then piped sequentially into the first, second and third percolation ponds. The percolation ponds span two acres and provide residence time of 35 to 45 days, during which time the effluent is further biologically treated and nitrogen is reduced. From the percolation ponds, the effluent is pumped into a low pressure system which uniformly distributes effluent over two nitrogen reduction filters. The nitrogen reduction filters are located north of the plant and are immediately adjacent to one of the subdivision's stormwater lakes. The nitrogen reduction filters consist of deep sand beds covered with Bermuda grass to provide high nitrogen uptake. The irrigation of the two nitrogen reduction filters is alternated every half day. These nitrogen reduction systems were modified in October/November, 1990, by adding 3 to 3 1/2 feet of clean sand with a permeability rate of 28 feet per day, planting Bermuda grass, and installing an irrigation/distribution system. These filters replaced two sand pits with shallow layers of very coarse sand, after initial testing demonstrated the sand pits to be inadequate in removing nutrients consistent with statutory requirements. In January, 1992, an underdrain system utilizing perforated pipe was installed in the nitrogen reduction filters to create an aerobic zone and to provide a representative sample port after nutrient reduction in the filters. This sample port, used for the biweekly monitoring, consists of a single solid pipe, that collects effluent from the perforated pipes, with a tap to prevent discharge into the adjacent stormwater lake, except during sampling events. The biweekly sampling event results in effluent being discharged from the pipe for approximately 30 minutes to flush the pipe so as to get a proper sample. The underdrain sampling port at the nitrogen reduction filters replaced two earlier monitor wells between the nitrogen reduction filter and the stormwater pond, which proved ineffective because of their location. The perforated underdrains are situated in filter bed sand of medium grain size with a permeability rate 100 feet per day and located below 3 - 3 1/2 feet of clean sand with a permeability rate of 28 feet per day and above very permeable layers of sand, stone and coarse shell. (See Tamaron's exhibit 23 and Department's exhibit 14) The very permeable layers of sand, coarse shell, the perforated pipe and the single solid pipe are all located above the ground water table. Since the perforated pipe and sample port are both located above the ground water level and the surface of the adjacent stormwater lake, it is unlikely that the effluent sample taken from the sample port would be influenced by the ground water or a back flow of water from the adjacent stormwater lake. The coarse shell layer situated below the nitrogen reduction filters extends to the edge of the adjacent stormwater lake. Therefore, the effluent, other than the effluent trapped in the perforated pipe and carried to the sample port, that is irrigated onto the nitrogen reduction filters passes through the sand and into the coarse shell layer. The effluent is then transported laterally through the coarse shell layer to the underground edge of the adjacent stormwater lake where there is a subsurface discharge into the adjacent stormwater lake. Since the discharge to the stormwater lakes is primarily subsurface in nature, the logical compliance point to measure effluent parameters would be the underground sample port which collects the effluent prior to subsurface discharge into the stormwater lake. See Petitioner's exhibit 15. The direction of ground water flow at the facility is towards the north to the adjacent stormwater lakes as evidenced by the hydraulic gradient of the site determined using ground water table elevations. The location for sampling effluent from the facility for compliance with secondary standards was described in Specific Condition 5 of Tamaron's previous permit No. D058-141783 dated August 23, 1988. Specific Condition 5 states that the discharge from the chlorine contact chamber shall be sampled in accordance with Chapter 17-19, Florida Administrative Code, (now Chapter 17-601, Florida Administrative Code), for compliance with the stated secondary limits. The facility's tertiary filters are located after the chlorine contact chamber. Tamaron samples effluent for compliance with secondary standards (BOD,TSS, chlorine) at the sampling box after disinfection and tertiary filtration. Tertiary filtration is designed to achieve a more efficient removal of TSS and BOD. The resulting effluent is usually of higher quality than secondarily treated effluent. A secondary plant with tertiary filtration is referred to as an "advanced secondary treatment" plant. Data presented by Tamaron titled Tamaron 1991-1993 Data On FDER Permit Compliance (Tamaron's exhibit 17, page 1 of 2) shows reported values, sampled after tertiary filtration at the sample box, which suggest that secondary treatment parameters, including fecal coliform, are not being exceeded. The data actually shows a very high removal rate for the parameters sampled. The United States Environmental Protection Agency issued a National Pollutant Discharge Elimination System (NPDES) permit, number FL0042811, to Tamaron for the facility with an effective date of June 1, 1991, which authorized Tamaron to discharge from the facility to the receiving waters named Phillippi Creek to Roberts Bay in accordance with the effluent limitation, monitoring requirements and other conditions set forth in the permit. Since the facility was located in the Grizzle-Figg Amendment area of Florida certain changes were made from the draft permit to the final permit. Those changes appear in the Amendment To The Statement Of Basis At The Time Of Final Permit Issuance which is made a part of the final permit. The amendment provides for changes in Part I, Effluent Limitations and Monitoring Requirements. These changes, among other things, require that the Grizzle-Figg Amendment annual limits of 5 mg/l BOD, 5mg/l TSS, 3mg/l total nitrogen and 1mg/l total phosphorus be added to the effluent limits to adequately maintain water quality standards, and added monitoring requirements and measurement frequency regulations to give the basis for permit limits and conditions in accordance with Chapters 17-302, 17-600 and 17-601, Florida Administrative Code. Data presented by Tamaron titled Tamaron 1991-1993 Data On NPDES Permit Compliance (Tamaron's exhibit 17, page 2 of 2) show reported values sampled after nitrogen reduction filters which suggest that the maximum values for AWT parameters, including fecal coliform, are not being exceeded, particularly after January, 1992, when Tamaron began sampling effluent collected by the perforated underdrains at the sample port. Tamaron has been monitoring and reporting compliance under its final NPDES permit and providing copies to the Department. There was no evidence that Tamaron was ever in violation of its NPDES permit. Tamaron submitted documentation to the Department with its permit application that demonstrated high-level disinfection within the facility was being achieved. However, TSS was being sampled after the application of the disinfectant. Using this procedure, the facility continued to achieve high- level disinfection until the permit denial. After the permit denial, the facility resumed basic disinfection which was required under Tamaron's permit for secondary treatment. This same data indicates that there was compliance with the requirements for fecal coliform. The record is not clear as to the frequency and number of samples taken to provide the data for reporting compliance with the NPDES permit and the data presented in Petitioner's exhibit 17, page 2 of 2. However, there was no evidence, other than sampling for TSS after the disinfectant was added, that Tamaron was not complying with its NPDES Permit that required, among other things, that the monitoring requirements and measurement frequency of the Department's rules and regulations be followed by Tamaron. Tamaron has modified and upgraded the facility in order to achieve a treatment process which will produce effluent of a quality for discharge under the Grizzle-Figg Amendment. Tamaron has provided reasonable assurances, although not absolute assurance, that the facility can comply with the discharge permit requirements of Chapter 403, Florida Statutes, including Section 403.086, Florida Statutes, notwithstanding the testimony of Jay Thabaraj to the contrary concerning Tamaron's sampling technique and its method of obtaining high-level disinfection which can be addressed as a specific condition, if necessary. Studies conducted by the Tamaron's engineer included in Petitioner's exhibit 21 indicates that there was no adverse impact to the stormwater lakes from the facility's wastewater treatment and disposal system. Tamaron has provided reasonable assurances that the point of discharge is a reasonably access point, where such discharge results only in minimal negative impact.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department enter a final order granting Tamaron an operating permit for its facility as secondary treatment facility. In the alternative, that the Department enter a final order granting Tamaron an operating permit for its facility that requires compliance with the advanced waste treatment criteria set forth in Section 403.086(4), Florida Statutes, that, in addition to any general or specific conditions that are normally required, contains specific conditions that: (a) contains specific instructions on sampling technique, sampling frequency and reporting as set forth in Rule 17- 740(1)(b)2., Florida Administrative Code, and (b) sets forth compliance with high-level disinfection, with a time limit for compliance, that accomplishes the intent of the rule, if not the strict letter of the rule, without total redesign of the facility. DONE AND ENTERED this 3rd day of May, 1994, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of May, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 91-2968 The following constitutes my specific rulings, pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Petitioner, Tamaron's Proposed Findings of Fact: The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(1); 2(2); 3(3); 4(5,6); 5(6); 6(7); 8(12); 10(8); 11-12(13-25,38); 13(31-34); 14(8); 15(13); 16(14); 17-18(15); 19(36); 20(16); 21(17); 22(18); 23(19); 24(20); 25(21);26(22); 32(32,7); 33(33); 34(32,32); 36(31); 39-40(34); 41(36); 42- 43(34); 44(35); 47(4); and 51(10). Proposed findings of fact 27-31, and 35 are conclusions of law rather than findings of fact.. Proposed findings of fact 45, 46, 48-50, 56, 57, 59, and 61-72 are arguments rather than findings of fact. Proposed findings of fact 7, 9, 37, 38, 52-55, 58 and 60 are neither material nor relevant. Respondent, Department's Proposed Findings of Fact: The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(1,6); 2(2); 3(4,10); 5(9); 6(9,10); 8(11); 9-17(18-27); 18(8); 19(13); 20(5); 21(17); 22(30); 23(31); 24(14); 25(17); 26(18-23); 27(34); and 32(35,38). Proposed finding of fact 4 is neither material nor relevant but see Findings of Fact 18-25. Proposed findings of fact 7, 31 and 33 are arguments rather than findings of fact. Proposed findings of fact 28-30 are conclusions of law rather than findings of fact. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Kenneth Plante, General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Charles G. Stephens, Esquire C. Robinson Hall, Esquire Enterprise Plaza, Suite 1516 101 E. Kennedy Blvd. Tampa, Florida 33602 Francine Ffolkes, Esquire Office of General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400
The Issue The issues are whether Respondent's facility is a public water system subject to regulation by the Department of Environmental Regulation (DER) pursuant to Chapter 17-22, Florida Administrative Code, or whether it is exempt from those regulations by virtue of Rule 17-22.102 if the facility is subject to regulation by DER, whether Respondent should take the corrective actions set forth in the Notice of Violation and Orders for Corrective Action and should pay DER's expenses incurred in the pursuit of this case. DER presented the testimony of Cliff McKeown, a potable water engineer, and Linda Frohock, planning manager for the Department of Community Affairs (DCA). DER had Exhibits 1-4 admitted into evidence. Respondent, Lex Thompson, presented his own testimony and that of Hugh Kelly. The parties have submitted Proposed Findings of Fact and Conclusions of Law. They have been considered and a ruling has been made on each proposed finding of fact in the Appendix to this Recommended Order.
Findings Of Fact DER is the Florida administrative agency which has the authority to administer and enforce the provisions of the Florida Safe Water Drinking Act, and the rules and regulations promulgated thereunder. (See Prehearing Stipulation). Respondent is a natural person and citizen of the State of Florida. Respondent owns and is responsible for the construction of a potable water distribution main extension ("the facility") which serves a subdivision known as High Bluff Acres-near the community of Midway in Gadsden County, Florida. (See Prehearing Stipulation). On February 1, 1980, Respondent was issued construction permit number DS20-27385 for the facility. The construction permit described the facility as a potable water distribution main extension to the Talquin Electric Company's Midway water- system. The project was to be constructed with approximately 940 linear feet of four inch PVC valves and appurtenances. Specific condition number 15 of the permit restricted operation of the extension until department approval was issued. This approval would be granted upon receipt of certification by the engineer of record as to construction in accordance with the approved plans and specifications and receipt of two satisfactory bacteriological analyses. DER has not received this information and had not issued an approval for use of the facility. The construction permit expired on September 1, 1981. (See Prehearing Stipulation). Respondent modified the facility by constructing it with 550 feet of one inch to one and one-half inch PVC water mains. (See Prehearing Stipulation). DER conducted an inspection of the facility on February 23, 1982. The facility was found to be in use without final DER approval. By letter dated February 26, 1982, DER notified Respondent of his non-compliance with Chapter 17-22, Florida Administrative Code, and requested Respondent to submit specified compliance items. (See Prehearing Stipulation). In October of 1982, DER personnel contacted Respondent . by telephone. Respondent agreed to obtain a permit renewal and modify the unauthorized water line as soon as funds in the form of rent were released by the Department of Community Affairs (DCA). On November 1, 1982, DCA notified DER that payments were being made. (See Prehearing Stipulation). On June 8, 1983, DER notified Respondent of his non- compliance with Chapter 17-22, Florida Administrative Code, and requested a reply on actions to be taken to correct the deficiency. By letters dated October 18, 1984, and December 17, 1984, DER notified Respondent that the facility was not approved for use. Respondent was further requested to inform DER as to the status of the facility. DER received no response to these requests. (See Prehearing Stipulation). The facility was not constructed in accordance with DER-approved plans, and DER has issued no written approval or consent for alterations to the system. (See Prehearing Stipulation). Respondent placed the facility in service without submitting a certification of completion and a copy of satisfactory bacteriological results to DER for approval and clearance. (See Prehearing Stipulation). The facility is not designed to provide maximum hourly system demand without development of distribution pressure lower than 20 psi. (See Prehearing Stipulation). DER has incurred costs and expenses in the pursuit of this case in the amount of $453.50. (See Prehearing Stipulation). Respondent's facility consists of distribution and storage facilities only and does not have any collection or treatment facilities. It obtains all its water from and is not owned or operated by the Talquin Electric System. Further, Respondent is not a carrier which conveys passengers in interstate commerce. (See Prehearing Stipulation) The public water distribution system constructed by Respondent is connected to twenty dwelling units in twelve structures. The High Bluff Acres subdivision is a government- subsidized, but privately-owned, low-income housing development, wherein DCA, acting on behalf of the U.S. Department of Housing and Urban Development (HUD), subsidizes the payment of rent for the housing. Respondent entered into several agreements on behalf of Salter, Stephens and Thompson, with the DCA to rehabilitate existing structures at High Bluff Acres and thus qualify for the Section 8 Moderate Rehabilitation Housing Assistance Program (HAP) established by HUD. The purpose for entering into the HAP contracts is to provide low cost housing to low income persons. These agreements were entered into over a period of several months during 1981 and 1982. Upon satisfactory completion of the rehabilitation pursuant to the agreements, Respondent entered into a HAP contract for each structure in High Bluff Acres, for a total of twelve structures (20 dwelling units). The HAP contract establishes the contract rent that can be allowed for each individual dwelling unit in a structure (the contract covers one structure). The contract rent is calculated according to a formula established by HUD for such purposes, and includes monetary allowances for utilities or other services which are provided by the owner. It does allow the lessor to recover his capital expenses in rehabilitating an individual housing unit. DER Exhibits 3 and 4 are two of the twelve HAP contracts entered into by the Department of Community Affairs and Respondent, Lex Thompson. Each of these contracts has an Exhibit B which is entitled "statement of services, maintenance and , utilities to be provided by owner." These exhibits show that Respondent has agreed to provide water to the units under the HAP contract. Contract rents paid to Respondent as authorized agent for the partnership include an allocation of money to reimburse Respondent for providing water to the tenants in the dwelling units. However, subsequent to Thompson's and DCA's entering into the contracts for payment of these rental subsidies, Respondent notified DCA that he had incurred additional capital expenses. Since his rental payments were already at the maximum allowable rate, however, Respondent did not seek to modify the aforementioned contracts because the amendment would not result in any greater payment of monies to him. At no time has Respondent amended the terms of the HAP contracts with respect to provision of water to the tenants at High Bluff Acres. He is still receiving the reimbursement for provision of water to tenants. The general partnership which had been receiving contract rents for the dwelling units was dissolved in May, 1985, and the contracts for each structure were assigned to various individuals. Respondent, individually, owns one structure and his wife owns another. DER has received no potable water quality or quantity complaints regarding the High Bluff Acres subdivision. Moreover, the potable water system existing in the High Bluff Acres subdivision does not constitute a present threat to the public health, safety, and welfare.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order and therein order the following corrective actions: That within 45 days, Respondent shall hire an engineer registered in Florida to design a new distribution system for High Bluff Acres or modifications to the existing system, and submit a completed application to the Department for a permit to construct or modify the system. That within 60 days of issuance of the permit, Respondent shall have the distribution system installed, tested(including pressure testing, bacterial testing, disinfectant-testing) and shall have the engineer sign and seal the plans indicating to the Department that the system conforms with the approved plans, and both DER and American Water Works Association standards. It is further RECOMMENDED that Respondent be ordered to pay the Department's costs and expenses in the amount of $453.50, and that same be paid to the Department by cashier's check within 30days. DONE and ORDERED this 4th day of November, 1985, in Tallahassee, Florida. DIANE K. KIESL1NG Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of November, 1985 APPENDIX Rulings on Petitioner's Proposed Findings of Fact: Proposed Finding of Fact 1 is adopted in substance (See Finding of Fact 13). Proposed Finding of Fact 2 is adopted in substance (See Finding of Fact 15). Proposed Finding of Fact 3 is adopted in substance (See Finding of Fact 15). Proposed Finding of Fact 4 is adopted in substance (See Finding of Fact 17). Proposed Finding of Fact 5 is adopted in substance (See Finding of Fact 18). Proposed Finding of Fact 6 is adopted in substance (See Finding of Fact 19). Proposed Finding of Fact 7 is adopted in substance (See Finding of Fact 22). Proposed Finding of Fact 8 is adopted in substance (See Finding of Fact 21). Rulings on Respondents Proposed Findings of Fact: Proposed Finding of Fact 1 is adopted in substance (See Finding of Fact 1). Proposed Finding of Fact 2 is adopted in substance (See Finding of Fact 2). Proposed Finding of Fact 3 is adopted in substance (See Finding of Fact 3). Proposed Finding of Fact 4, first sentence, is adopted in substance (See Finding of Fact 4). The second sentence is rejected as being unsupported by the evidence and irrelevant. Proposed Finding of Fact 5 is adopted in substance (See Finding of Fact 5). Proposed Finding of Fact 6 is adopted in substance (See Finding of Fact 6). Proposed Finding of Fact 7 is adopted in substance (See Finding of Fact 7). Proposed Finding of Fact 8, first sentence, is adopted in substance (See Finding of Fact 8). The remainder of Proposed Finding of Fact 8 is rejected as irrelevant. Proposed Finding of Fact 9 is adopted in substance (See Finding of Fact 12). Proposed Finding of Fact 10 is adopted in substance (See Finding of Fact 14). Proposed Finding of Fact 11 is adopted in substance (See Finding of Facts 19 and 20). Proposed Finding of Fact 12 is rejected as unsupported by the evidence, irrelevant and conclusory. Proposed Finding of Fact 13 is adopted in substance (See Finding of Fact 23), except that it is rejected as it relates to a potential threat because that portion is unsupported by the competent, credible evidence. COPIES FURNISHED: Clare E. Gray, Esquire Daniel H. Thompson, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 William L. Hyde, Esquire 300 East Park Avenue Post Office Drawer 11300 Tallahassee, Florida 32302 Victoria Tschinkel Secretary Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue Whether the proposed Florida Administrative Code Rules 28-20.110, 28-20.120, and 28-18.210 are invalid exercises of delegated legislative authority.
Findings Of Fact Parties Petitioner, Florida Keys Citizens Coalition, Inc. ("FKCC"), is a non-profit Florida corporation whose address is 10800 Overseas Highway, Marathon, Florida 33050. The primary purpose of FKCC is to "protect the quality of life of the citizens of the Florida Keys." The primary emphasis of the organization involves issues related to the carrying capacity, the limits of the infrastructure, and the environmental qualities of the Florida Keys. Consistent with its purpose, FKCC opposes regulations which it believes will diminish the quality of the natural habitat in Monroe County and the City of Marathon and hinder safe and efficient emergency evacuation. FKCC has been involved in previous Monroe County litigation, including participating as a party to at least two formal administrative challenges to the 2010 Monroe County Comprehensive Plan (Monroe County Comprehensive Plan). Petitioner, Last Stand, Inc., is a non-profit Florida corporation whose address is Post Office Box 146, Key West, Florida 33041-0146. The primary purpose of Last Stand is to preserve and protect the quality of life in the City of Key West, the Florida Keys, and their environs, with particular emphasis on the natural environment. To that end, Last Stand opposes regulations that it believes diminishes the quality of the natural habitat in the Florida Keys and regulations that hinder safe and efficient emergency evacuation in the Florida Keys. Last Stand is an organizational member of FKCC. Moreover, many individual members of Last Stand are also members of FKCC. A substantial number of members of both FKCC and Last Stand live, work, and/or engage in various recreational activities in the City of Marathon or in nearby areas. For example, a substantial number of members of both of those organizations regularly use and enjoy the nearshore waters of Monroe County for recreational water activities, such as boating, diving, snorkeling, and/or swimming.3 A substantial number of members of both organizations also regularly use and enjoy terrestrial habitats in Monroe County, including the City of Marathon, for recreational activities such as hiking and bird-watching. A substantial number of the members of both FKCC and Last Stand may be adversely affected or impacted by the issues which are in dispute in this proceeding. Moreover, the issues in this proceeding are germane to the purposes of both FKCC and Last Stand. Also, both FKCC and Last Stand regularly represent their members' interests in formal administrative hearings and local commission meetings relative to environmental and growth management issues. Respondent, Administration Commission, consists of the Governor and Cabinet and is empowered to adopt, by rule, any enactment, amendment, or rescission of a land development regulation or element of a local comprehensive plan in the Florida Keys area. Respondent, Monroe County, is a local county government within the Florida Keys Area of Critical State Concern ("ACSC"). Respondent, City of Marathon, is a municipality within the Florida Keys ACSC. Intervenor, the DCA, is the state land planning agency responsible for the general supervision of the administration and enforcement of the ACSC program. As the state planning agency, the DCA is authorized to propose changes to local comprehensive plans and land development regulations within an ACSC for adoption by the Administration Commission. Economic Base of Florida Keys Tourism is the economic base of the Florida Keys. Moreover, the basis for the Florida Keys' tourism is a healthy natural environment that supports fishing, diving, water sports, boating, bird-watching habitat, visiting endangered species habitat, and other related activities. History of the Florida Keys ACSC The Florida Keys area is designated as an ACSC and consists of, unincorporated, Monroe County, the City of Layton, the City of Key Colony Beach, the Village of Islamorada, and the City of Marathon. See § 380.0552(3), Fla. Stat. (2004).4 The City of Key West has been separately designated as an ACSC pursuant to Florida Administrative Code Rule Chapter 28-36. The Florida Keys were originally designated by the Administration Commission in 1975 and re-designated by the Legislature in 1986. The legislative intent section and the Principles for Guiding Development, as set forth in Subsections 380.0552(2) and (7), Florida Statutes, together require an effective land use management system that protects the natural environment and character of the Florida Keys, maintains acceptable water quality conditions, ensures adequate public facility capacity and services, provides adequate affordable housing, supports a sound economic base, protects constitutional property rights, and requires adequate emergency and post- disaster planning to ensure public safety. During the past 20 years, the growth management process has been implemented in essentially two phases. The first phase involved developing, adopting, and implementing the first comprehensive plans and regulations under the new designation. These plans and regulations were adopted by the county and cities in the mid-1980s. The 1986 plan established a growth management system that substantially increased protection of natural resources and began to reduce the over-allocation of density in the Florida Keys. It also achieved the long-term protection of North Key Largo. However, several major problems were not adequately addressed by the 1986 plan, including maintaining evacuation capability, water quality protection, sewage treatment, stormwater treatment, and community character. In addition, although the plan required a focal point plan for Big Pine Key, this planning process did not result in a viable plan that adequately protected the Florida Keys deer. The required open space ratios proved difficult to maintain within habitats once development occurred, resulting in fragmentation of habitat. The second phase involved the planning process undertaken in the early 1990s to meet the requirements of the Growth Management Act and to update the plan based on lessons learned in implementing the 1986 plan. In developing, reviewing, and litigating the Monroe County Comprehensive Plan, the following critical issues emerged involving how to: maintain acceptable hurricane evacuation capability; retrofit existing development and provide new development with adequate wastewater and storm water facilities, including, where appropriate, upgrading of on-site systems; determine the carrying capacity of the Keys to withstand the impacts of additional land development and modify state and local plans, regulations and programs so that the carrying capacity is not exceeded; provide an adequate supply of affordable housing while maintaining acceptable hurricane evacuation and protecting the environment. In 1996, the Administration Commission adopted a rule which included a cap of 255 residential units per year for Monroe County. The rule also adopted a five-year Work Program into the Monroe County Comprehensive Plan with the local governments to construct sewage treatment facilities, replace cesspits, and purchase land to protect natural habitat. Monroe County, the City of Marathon, and the DCA were required to submit reports to the Administration Commission each year "documenting the degree to which the Work Program objectives for that year [had] been achieved." The rule contemplated that if the local governments did not make "substantial progress" towards accomplishing the tasks of the Work Program, the unit cap for new residential permits would be reduced by at least 20 percent for the following year. The Administration Commission found a lack of "substantial progress" in 1999 and adopted a rule which reduced the annual allocation of residential permits by 20 percent and extended the five-year Work Program to seven years. The Administration Commission found "substantial progress" had been accomplished in 2001 and began rulemaking to restore the permit allocation. However, the rule was challenged, and since the Administration Commission found a lack of "substantial progress" in 2002, the Commission adopted a revised rule which did not restore permits. The Carrying Capacity Study The 1996 Administration Commission rule amended the Monroe County Comprehensive Plan to require the completion of a carrying capacity analysis. The carrying capacity analysis shall be designed to determine the ability of the Florida Keys ecosystem, and the various segments thereof, to withstand all impacts of additional land development activities. The analysis shall be based upon the findings adopted by the Administration Commission on December 12, 1995, or more recent data that may become available in the course of the study, and shall be based upon the benchmarks of, and all adverse impacts to, the Keys land and water natural systems, in addition to the impact of nutrients on marine resources. The carrying capacity analysis shall consider aesthetic, socioeconomic (including sustainable tourism), quality of life and community character issues, including the concentration of population, the amount of open space, diversity of habitats, and species richness. The analysis shall reflect the interconnected nature of the Florida Keys' natural systems, but may consider and analyze the carrying capacity of specific islands or groups of islands and specific ecosystems or habitats, including distinct parts of the Keys' marine system. (Ref. 1991 Stip. Settlement Agreement). Agencies: County, DCA, DEP, DOH, DOT, GFC, SFWMD, NMS, SFRPC, EPA, USFWS, Army COE, and other interested parties to include representatives of environmental organizations and development interests. The Florida Keys Carrying Capacity Study ("FKCCS") was completed over a period of six years. Six million dollars was allocated by the DCA and the United States Army Corps of Engineers to produce the Monroe County Sanitary Wastewater Master Plan, the Stormwater Management Plan, and the FKCCS. The contractor, URS Corporation, completed the FKCCS and the Carrying Capacity/Impact Assessment Model ("CCIAM"), a separate component to be used in forecasting land use scenarios. A panel of external experts was used to peer review the scope of work. In September 2002, the study was completed. The National Research Council of the National Academy of Sciences ("Council") reviewed the CCIAM and FKCCS and, as a result of its review, adjustments were made to the CCIAM. The Council's review concluded that overall, due to data constraints and other issues in certain portions of the CCIAM, the model proved insufficient to develop a comprehensive carrying capacity framework that would allow for undisputable determinations of whether future development scenarios fall within the carrying capacity of the Florida Keys. The marine module, the most data- deficient, was subsequently removed from the CCIAM. The FKCCS recommended four main guidelines for future development in the Florida Keys: Prevent encroachment into native habitat. A wealth of evidence shows that terrestrial habitats and species have been severely affected by development and further impacts would only exacerbate an already untenable condition. Continue and intensify existing programs. Many initiatives to improve environmental conditions and quality of life exist in the Florida Keys. They include land acquisition programs, the wastewater and stormwater master plans, ongoing research and management activities in the Florida Keys National Marine Sanctuary, and restoration efforts throughout the Florida Keys. If further development is to occur, focus on redevelopment and infill. Opportunities for additional growth with small, potentially acceptable, additional environmental impacts may occur in areas ripe for redevelopment or already disturbed. Increase efforts to manage the resources. Habitat management efforts in the Keys could increase to effectively preserve and improve the ecological values of remaining terrestrial ecosystems. Partnership Agreement While preparing the Assessment Report for 2003, the DCA Secretary concluded that the existing policy direction, consisting of imposition of the Work Program by the Administration Commission and reduction of residential permits, due to lack of substantial progress, was not sufficient to solve the problems facing the Florida Keys. The Assessment Report described difficulties and delays in implementing the Work Program. Most of the sewage treatment facilities contemplated by the Work Program were not constructed and valuable upland habitat continued to be developed. On December 16, 2003, the Administration Commission concluded that Monroe County had not made substantial progress and directed the DCA "to determine changes that would be necessary to the comprehensive plan to fully implement the requirements of the Work Program[,] as well as habitat protection provisions." The Administration Commission also accepted the staff recommendation that it "determine substantial progress has been made for the City of Marathon, and that some permits will be provided back to the City of Marathon," the number to be determined at the Administration Commission's January 27, 2004, meeting. The DCA approached the Florida Keys local governments and community-based organizations and proposed a Partnership Agreement to "begin implementation of the Work Program associated with the Florida Keys Protection Act." The DCA Secretary addressed the governing boards of the Florida Keys' local governments concerning the proposed Partnership Agreement. Monroe County, the City of Marathon, and the Village of Islamorada adopted resolutions supporting the partnership proposal. By letter dated February 25, 2004, the DCA Secretary requested that the Governor, as a member of the Administration Commission, authorize the Administration Commission staff to initiate rulemaking to amend the Comprehensive Plans of Monroe County and the City of Marathon. According to the letter, this action was requested based upon a series of significant commitments made by each of these local governments which addressed issues related to habitat protection, affordable housing, wastewater and stormwater management projects, land acquisition, and nutrient credits. The letter also noted the following: A complete follow-through on these commitments would mean over $410 million would be spent in the coming years to address these issues in the Florida Keys. Habitat protection will be increased, environmentally-sensitive hammock and pinelands would be purchased, new wastewater and stormwater management projects would be initiated, and 230 units of affordable housing would be made available for residents of the Florida Keys. * * * In essence, we have developed proposals that allow additional units primarily for affordable housing in the Florida Keys, but also would ensure the most pressing issues will be jointly addressed by local and state government. Consistent with the February 25, 2004, letter, the Partnership Agreement consists of commitments by the Florida Keys' local governments and several state agencies to address habitat protection, wastewater and stormwater treatment, affordable housing, and hurricane evacuation. At its March 9, 2004, meeting, the Administration Commission accepted the DCA's recommendation to initiate rulemaking to implement the Partnership Agreement. The Proposed Rules 29. Proposed Rules 28-18.210, 28-20.110, and 28-20.120 were published in the Florida Administrative Weekly on July 16, 2004.5 According to the published notice, the purpose of Proposed Rule 28-18.210 is to amend Policy 101.2.14 of the Marathon Comprehensive Plan to address building permit allocations by increasing the annual residential permitting cap and specifying allocations authorized for market rate and affordable housing, restoring certain allocations authorized for market rate and affordable housing, authorizing certain unused rate of growth ordinance allocations to roll forward, and deleting the requirement for nutrient credits upon a date certain. The notice also provides that the Proposed Rule amends the Work Program set forth in Policy 101.2.14 of the Marathon Comprehensive Plan to establish Year Eight and Year Nine to address tasks not yet completed in the original Work Program. The published notice states that the purpose of Proposed Rules 28-20.110 and 28-20.120 is to amend Policy 101.2.13 of the Monroe County Comprehensive Plan to address building permit allocations by increasing the annual residential permitting cap and specifying allocations authorized for market rate and affordable housing, restoring certain allocations previously reduced to be targeted for affordable housing, authorizing certain unused rate of growth ordinance allocations to roll forward, and deleting the requirement for nutrient reduction credits upon a date certain. The notice also provides that the proposed rules amend the Work Program in Policy 101.2.13 of the Monroe County Comprehensive Plan to establish Work Program provisions for Year Eight, Year Nine, and Year Ten to address tasks not yet completed in the original Work Program. Finally, the notice states that the Proposed Rule amendments address the adoption of necessary land development regulations. The published notice cites Subsection 380.0552(9), Florida Statutes, as the specific authority for the Administration Commission's promulgating the Proposed Rules and Section 380.0552, Florida Statutes, as the law implemented. Petitioners challenge portions of Proposed Rule 28-18.210, which will amend the Marathon Comprehensive Plan and portions of Proposed Rules 28-20.110 and 28-20.120,6 which will amend the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations on the basis that they constituted invalid exercises of delegated legislative authority. Petitioners contend that the proposed rules should comply with Section 380.0552 and Chapters 163 and 380, Florida Statutes, and, therefore, should be analyzed for such compliance in this proceeding. Notwithstanding Petitioners contention to the contrary, for the reason stated in paragraph 199 below, Proposed Rules 28-18.210, 28-20.110, and 28-20.120 will be analyzed based on their consistency with Section 380.0552, Florida Statutes, because that is the provision which the proposed rules explicitly purport to implement. The published notice does not specify the subsection of Section 380.0552, Florida Statutes, that the proposed rules implement. However, the parties agree that the proposed rules must be consistent with Subsection 380.0552(7), Florida Statutes, which set forth the Principles for Guiding Development. Restoration/Increase of ROGO Allocations The Comprehensive Plans for Monroe County and the City of Marathon include a Permit Allocation System, under which Monroe County was originally allocated 255 permits per year for new residential units. As noted in paragraph 18 above, in 1999, the Administration Commission determined that substantial progress on the Work Program had not been accomplished and adopted a rule reducing the annual allocation of permits by 20 percent. After the incorporation of the Village of Islamorada and Marathon, and a voluntary reduction by the Village of Islamorada, the current annual allocation of residential development permits is 158 for Monroe County, 24 for Marathon, and 14 for the Village of Islamorada. Proposed Rule 28-20.110(1) amends Policy 101.2.13 of the Monroe County Comprehensive Plan by increasing the annual unit cap of 158 to 197, thereby restoring the original level of permits issued for new residential development under the Rate of Growth Ordinance ("ROGO"). The proposed rule requires that "[e]ach year's ROGO allocation of 197 new units shall be split with a minimum of 71 units allocated for affordable housing in perpetuity and market rate allocations not to exceed 126 new units per year." Proposed Rule 28-18.210 amends Policy 101.2.14 of the Marathon Comprehensive Plan by increasing the maximum number of permits for new residential units from 24 to 30 per year, thereby, restoring the original level of permits per year for new residential development under ROGO. The proposed rule requires that "[e]ach year's ROGO allocation of 30 units shall consist of 24 market rate and 6 affordable units" and that the affordable housing "remain as affordable housing in perpetuity." In addition to restoring the number of permits for new development to the original levels, Proposed Rule 28-20.110 amends the Comprehensive Plans of Monroe County and Marathon to restore available permit allocations that were unused in previous years and to allow unused ROGO allocations to be allocated in subsequent years. Proposed Rule 28-20.110 adds a new provision to the Monroe County Comprehensive Plan, providing that "effective July 12, 2004, 140 ROGO allocations, which represent unused reductions for ROGO Years Nine through 12, and 25 units lost in Year Ten due to lack of nutrient credits, are reallocated to the County exclusively for affordable housing purposes." Proposed Rule 28-18.210 adds a provision to the Marathon Comprehensive Plan that "effective July 12, 2004, 65 ROGO allocations, which represent unused ROGO allocations for ROGO Years 9 through 12, are to be reallocated to the City exclusively for affordable housing." Advancing/Borrowing Nutrient Credits The existing Comprehensive Plans of Monroe County and the City of Marathon include a nutrient credit system. According to the Monroe County Comprehensive Plan, nutrient reduction credits are earned when existing treatment systems are upgraded. The amount of nutrient reduction credits earned correlate to the type of treatment system to which an old system is upgraded. Thus, if a treatment system is upgraded to the "best centralized system" or the "advanced wastewater treatment system," Monroe County would earn the most nutrient credits possible. For example, elimination of a cesspit by connection to a centralized advanced wastewater treatment system earns 1.5 nutrient credits, and the elimination of a substandard on-site disposal system by connection to a centralized secondary treatment system earns 0.5 nutrient credits. Under the existing Comprehensive Plans of Monroe County and the City of Marathon, development permits for new residential development can only be issued if a nutrient reduction credit has been earned. The requirement that adequate nutrient credits be earned prior to issuance of permits is to mitigate for nutrient impacts of new residential development. However, Proposed Rules 28-18.210 and 28-20.110 provide that Monroe County and the City of Marathon will be permitted to "borrow" nutrient credits from the pool of nutrient credits that are anticipated from the construction and/or completing of sewage treatment facilities. The existing Comprehensive Plans of Monroe County and the City of Marathon provide that nutrient reduction credits are earned by the construction of the Little Venice system according to the schedules prescribed in the Comprehensive Plans. The schedules in the Comprehensive Plans provide that "213 of the total credits estimated to be available from the full operation of the system shall be earned when the wastewater permit is issued, the design/build contract for the system has been fully executed and construction of the system has commenced." The Comprehensive Plans also provide that all the remaining available credits shall be earned when the construction of the Little Venice System is complete, the collection system lines have been installed, and the final total of credits available from the operation of the systems has been calculated. Proposed Rules 28-20.110 and 28-18.210 amend the Comprehensive Plans of Monroe County and Marathon by allowing 213 of the total credits estimated to be available from the full operation of the Little Venice system to be earned, effective July 13, 2003. The proposed rules also provide that when the Little Venice system is completed, "[t]he total credits available shall be reduced by the 213 [credits] advanced in the year 2003." Proposed Rule 28-20.110 amends the Monroe County Comprehensive Plan by allocating 41 nutrient credits for market rate units and 193 nutrient credits for affordable housing units to Monroe County. The Proposed Rule 28-20.110 provides that the 41 nutrient credits will be subtracted from the nutrient credits subsequently earned from hookups to the Key West Resort Utilities Wastewater Facility ("Key West Resort Utilities"). The 193 nutrient credits will be subtracted from hookups to the Key West Resort Utilities, Bay Point, and Key Largo Wastewater Facilities. Repeal of Nutrient Reduction Provision As described in paragraph 42 above, the existing Comprehensive Plans of Monroe County and the City of Marathon have mandatory nutrient provisions that require nutrient credits to be earned prior to issuance of a permit for new residential units. Proposed Rules 28-20.110 and 28-18.210 amend the Comprehensive Plans of Monroe County and the City of Marathon by repealing the mandatory nutrient credit provisions. Pursuant to the proposed rules, "effective July 13, 2005, no nutrient credits shall be required if the local government has made satisfactory progress as determined by the Administration Commission in meeting the deadlines established by the Work Program as adopted by rule after March 15, 2004." Challenges to Increase/Restoration of Permits, Advancing Nutrient Credits, and Repeal of Nutrient Reduction Provision Petitioners contend that the increase in new residential permits is arbitrary and capricious and contravenes the law implemented because it will increase development even though the identified thresholds for growth in the Florida Keys--water quality, terrestrial habitat, and evacuation times-- have been exceeded and will "worsen" the water quality. Petitioners challenge the provision which allows the borrowing or awarding of nutrient credits before wastewater projects are completed as arbitrary and capricious, because it will allow a net increase in the nutrient impacts into the nearshore waters of the Florida Keys and will "worsen" the water quality. Proposed Rules 28-20.110(1) and 28-18.210 increase the number of permits for new residential units from the preceding years. However, the number of permits to be issued under the Monroe County Comprehensive Plan has not increased. Rather, the permits will be issued in a shorter time frame and without being subject to the previous conditions. Even though increased development could result in an increase in the nutrient impacts into the nearshore waters of the Florida Keys, the adverse effect of such nutrient loading is offset by the adequate treatment of wastewater and stormwater runoff. To address the problem of nutrient loading, the Proposed Rules 28-20.110 and 28-18.210 extend the years of the Work Programs and include in those programs tasks, such as construction and completion of wastewater facilities, as well as financing for those projects. Based on the commitments of Monroe County and the City of Marathon in the Partnership Agreement, there is a reasonable expectation that the projects included in the Work Program of the Proposed Rules will be completed. When completed, the wastewater treatment facilities will provide nutrient credits. In anticipation of the completion of the wastewater treatment facilities, Proposed Rules 28-20.110 and 28-18.210 restore the annual permits for new residential units to their original levels and allow previous unused ROGO allocations to be allocated. The Proposed Rules provide that the nutrient credits for these allocations will be borrowed from the pool of nutrient credits that are anticipated from the planned construction and completion of wastewater facilities. Petitioners' contention that the repeal of the mandatory nutrient reduction credit provision is arbitrary and capricious and contravenes the law implemented because such repeal allows the water quality to worsen, is inconsistent with the "no net nutrient" provision of the Comprehensive Plans and is unjustified given that the nutrient pollution has increased since the nutrient credit provisions were adopted. Petitioners also contend that the repeal of the nutrient credit provision is arbitrary and capricious because the repeal is effective on a date certain without further action and without regard for whether it is justified. Proposed Rules 28-20.110 and 28.18-210 repeal the mandatory nutrient reduction credit provisions of the Comprehensive Plans, but the condition precedent to the repeal is the Administration Commission's making a determination that Monroe County and the City of Marathon have "made satisfactory progress . . . in meeting deadlines established by the [new] Work Program." This determination must be made prior to the repeal going into effect. Presumably, the tasks in the Work Program for which satisfactory progress must be made are those relevant and reasonably related to and which result in nutrient credits. Contrary to Petitioners' assertion, the repeal of the mandatory nutrient credit provision does not automatically become effective on the date prescribed in the proposed amendments. Instead, the repeal is contingent on Monroe County's and the City of Marathon's making "satisfactory progress." The term "satisfactory" is not vague as asserted by Petitioners. In the context of Proposed Rules 28-20.110 and 28-18.210, "satisfactory" would be given its common and ordinary meaning, which is "sufficient to meet a demand or requirement."7 Annual Reporting Requirement The existing Comprehensive Plans for Monroe County and the City of Marathon provide that "beginning September 30, 2003, and each year thereafter, [the respective local government] Monroe County and the [DCA] shall report to the Administration Commission documenting the degree to which the Work Program objectives have been achieved." Proposed Rules 28-20.110 and 28-18.210, will modify the annual reporting requirements in the Monroe County and Marathon Comprehensive Plans. The proposed amended provision, which is underlined, and the existing provision are as follows: Beginning September 30, 2003, and each year of the work program thereafter, Monroe County and the Department of Community Affairs shall report to the Administration Commission documenting the degree to which the work program objectives for that year have been achieved. The report for years seven and eight shall be combined and provided to the Administration Commission by September 30, 2005. The Commission shall consider the findings and recommendations provided in those reports and shall determine whether substantial progress has been achieved toward accomplishing the tasks of the work program. Petitioners contend that the proposed rules, which delete the requirement for Monroe County and for the City of Marathon to submit the September 2004 progress report to the Administration Commission, are arbitrary and capricious. Petitioners assert that by deleting the requirement for the 2004 annual progress report, the proposed rules fail to establish an annual safeguard that is required to ensure that the environmental conditions and infrastructure limitation that the annual Work Program is designed to resolve, do not worsen. The proposed rules delete the requirement that Monroe County and Marathon submit their respective reports in September 2004 and delay submission of that report by a year. The time spent negotiating the Partnership Agreement and the proposed changes to the Monroe County Comprehensive Plans and the Land Development Regulations left little time for Monroe County and the City of Marathon to implement the new Work Programs. Moreover, the DCA and the Administration Commission would have had too short a time period in which to judge whether Monroe County and Marathon had made substantial progress. By combining the reports for Years Seven and Eight of the Work Program, the Administration Commission can expect a meaningful report on Monroe County's and the City of Marathon's progress in implementing their respective Work Programs. Monroe County Work Program Under Proposed Rules Proposed Rule 28-20.110 amends the Work Program Policy 101.2.13 of the Monroe County Comprehensive Plan by adding Years Eight, Nine, and Ten to the existing Work Program. Many of the tasks included therein address and are related to wastewater facilities, habitat protection, affordable housing, and hurricane evacuation and implement the Partnership Agreement. Year Eight of the Work Program requires that Monroe County and other designated agencies perform the specified tasks and provide, in relevant part, the following: Year Eight (July 13, 2004 through July 12, 2005) Review and revise (as necessary) the Conservation and Natural Areas Map. Initiate acquisition strategy for lands identified outside the Conservation and Natural Areas identified as worthy of protection. Begin public hearings for Conservation and Natural Areas boundaries. Conclude public hearings for the adoption of the amended Conservation and Natural Areas Boundaries. Adopt an ordinance to implement a moratorium on ROGO/NROGO applications that involves the clearing of any portion of an upland tropical hardwood hammock or pinelands habitat contained in a tropical hardwood hammock or pinelands patch of two or more acres in size located within a Conservation and Natural Area. Adopt amendments to the comprehensive plan and land development regulations to enact overlay designations, and eliminate or revise the Habitat Evaluation Index, and modify the ROGO/NROGO system to guide development away from environmentally sensitive lands. Amend land development regulations to prohibit the designation of Conservation and Natural Areas (Tier 1) as a receiver site for ROGO exempt development from sender sites; and to further limit clearing of upland native habitat that may occur in the Natural Areas (Tier I) and the Transition and Sprawl Reduction Area (Tier II) upon designation by the County. Develop Land Acquisition and Management Master Plan and address both funding and management strategies. Provide $40 million in financing secured by infrastructure tax for wastewater facilities. Begin construction of wastewater plants or laying of collection lines for Baypoint, Conch Key and Key Largo Trailer Village/Key Largo Park. Ensure the connection for up to 1,350 EDUs [equivalent development units] at Stock Island to Key West Resort Utilities. Complete the Lower Keys and Key Largo feasibility study. Complete projects identified in the Storm Water Management Master Plan. Evaluate and implement strategies to ensure that affordable housing remains affordable in perpetuity for future generations. Establish a partnership with non-profit organizations in order to construct affordable housing using additional state funds. Identify potential acquisition sites for affordable housing proposals and include in the Land Acquisition Master Plan. Provide up to $10 million in bond financing from the Tourist Impact Tax for acquisition of land for workforce housing and affordable housing sites. Complete a comprehensive analysis of hurricane evacuation issues in the Florida Keys and develop strategies to reduce actual hurricane clearance times and, thereby, reduce potential loss of life from hurricanes. As discussed below, several of the tasks in Year Eight of the Work Program implement parts of Goal 105 of the Monroe County Comprehensive Plan. Goal 105 reads: Monroe County shall undertake a comprehensive land acquisition program and smart growth initiatives in conjunction with its Livable CommuniKeys Program in a manner that recognizes the finite capacity for new development in the Florida Keys by providing economic and housing opportunities for residents without compromising the biodiversity of the natural environment and the continued ability of the natural and man-made systems to sustain livable communities in the Florida Keys for future generations. Goal 105, also referred to as the "Smart Growth Goal," provides a framework to implement the FKCCS and a 20-year land acquisition program. The initial phase of implementing Goal 105 calls for the drafting and adoption of "Tier Maps" to be used as guidance for the Monroe County's Land Acquisition Program. Pursuant to Policy 105.2.1 of the Monroe County Comprehensive Plan, the Tier maps will designate and map properties into one of the following three general categories for purposes of Monroe County's Land Acquisition Program and the smart growth initiatives: Natural Area (Tier I); Transition and Sprawl Reduction Area (Tier II); and Infill Area (Tier III). Tier I property is property where all or a significant portion of the land is characterized as environmentally sensitive by policies of the Monroe County Comprehensive Plan and applicable habitat conservation plan. Tier I is to be designated as a Natural Area. New development is to be severely restricted in Tier I. Tier II is any geographic property where scattered groups and fragments of environmentally-sensitive lands, as defined by the Comprehensive Plan, may be found and where subdivisions are not predominantly developed. New development is to be discouraged in Tier II, which is to be designated as Transition and Sprawl Area. Tier III is property where a significant portion of land is not characterized as environmentally sensitive, as defined by the Monroe County Comprehensive Plan, where existing platted subdivisions are substantially developed, served by complete infrastructure facilities, within close proximity to established commercial areas or where a concentration of non-residential uses exist. New development and re-development are to be highly encouraged in Tier III, which is to be designated as Infill Area. Petitioners contend that Task A, which requires Monroe County to "review and revise [as necessary] the Conservation and Natural Areas ["CNA"] Map, vests unbridled discretion to the County to amend the CNA map without adequate standards or criteria." Further, Petitioners assert that Task A does not identify the purpose for which the CNA map is to be used. Based on this assertion, Petitioners contend that Task A is arbitrary and capricious and contravenes law. Task A will assist in the implementation of the Comprehensive Plan by requiring Monroe County to review and revise the CNA map. In reviewing Task A, it is clear that the county must adhere to the criteria prescribed in Goal 105 of the existing Monroe County Comprehensive Plan. When Task A is read together with Goal 105 and its related policies, it is clear that the purpose of Task A is to provide guidance for the Monroe County Land Acquisition Program. As a part of the review and revision process, the Partnership Agreement, which Task A implements, provides that the Monroe County staff should prepare the CNA map utilizing Florida Marine Source Resources Institute ADID maps, the most recent aerial photographs, site visits as necessary, and obtain input from DCA and the public. Moreover, when Task A is read with Task B, and other relevant parts of the Monroe County Comprehensive Plan, it is clear that a CNA map is to be used to implement Goal 105 of the Monroe County Comprehensive Plan, which is related to land acquisition and "smart growth initiatives." Petitioners assert that Task B, which requires Monroe County to "initiate acquisition strategy for lands identified outside the [CNA] boundaries," is arbitrary and capricious and contravenes the law implemented, because it provides no standards or criteria. Task B is consistent with Policy 105.2.1 of Goal 105 of the Monroe County Comprehensive Plan. The Partnership Agreement consistent with Goal 105 provides that Monroe County will identify lands outside the CNA boundaries for acquisition and target for purchase appropriate environmentally-sensitive lands that are contained within upland habitat of two acres or more outside the CNA. Task C requires Monroe County to "begin public hearings for [CNA]." Task D requires Monroe County to conclude the public hearings for adoption of the amended [CNA] boundaries. Petitioners contend that Tasks C and D are arbitrary and capricious and contravene the law implemented, because they do not require that an end result be achieved as a result of these public meetings. When the provisions of Task C and Task D are read together, with Goal 105 and the relevant provisions of the Partnership Agreement, it is clear that the end result sought as a result of the public hearings is to receive public comment regarding the identification of lands to be included in the CNA. Furthermore, this is a reasonable meaning of Tasks C and D in light of the well-known purpose of public hearings. Petitioners challenge Task E, which requires Monroe County to "adopt an ordinance to implement a moratorium on ROGO/NROGO applications that involves the clearing of any portion of an upland tropical hardwood hammock or pinelands habitat contained in a tropical hardwood hammock or pinelands patch of two or more acres in size located within a [CNA]." The purpose of the moratorium is to prevent impacts to native habitat until Monroe County adopts permanent regulations and amendments. Petitioners contend that Task E of Year Eight of the Work Program, which requires Monroe County to "adopt an ordinance to implement a moratorium on ROGO/NROGO applications that involve the clearing of any portion of an upland hardwood hammock or pinelands habitat contained in a tropical hardwood hammock or pinelands patch of two acres or more . . . within a [CNA]," is arbitrary and capricious and contravenes the law implemented. Petitioners assert that the criteria for the interim ordinance required fails to protect all hammock and pineland, does not protect enough hammock to ensure that the carrying capacity of the Florida Keys terrestrial habitat to sustain degradation and loss is not exceeded, does not require that the interim protections last until replaced by permanent ones, and does not apply to ROGO-exempt allocations. The criteria for the interim ordinance required by Task E is reasonable and will result in strengthening habitat protection in the areas specified in that provision. The fact that Task E authorizes the adoption of an ordinance that protects less than "all" hammock and pineland, does not make the proposed rule arbitrary and capricious, nor does the proposed rule contravene the law implemented. Petitioners contend that Task F, which requires Monroe County to "[a]dopt amendments to the comprehensive plan and land development regulations to enact overlay designations, and eliminate or revise the Habitat Evaluation Index ["HEI"], and modify the ROGO/NROGO system to guide development away from environmentally sensitive lands," is arbitrary and capricious and contravenes the law implemented. Petitioners claim that the standard set forth in Task F, "to guide development away from environmentally sensitive lands," is no more specific than is statutory language. Petitioners assert that the proposed rule should specify (1) habitat types, patch sizes and other characteristics of the areas to which regulations will apply, and (2) the exact nature of the regulation (i.e. a prohibition on direct or secondary impacts, the application of negative points or open space rations, etc.) that will be relied upon to guide development away from such areas. Task F requires Monroe County to adopt amendments to the Comprehensive Plan and Land Development Regulations to enact the overlay designations requiring Monroe County to implement Policy 105.2.2 of the Monroe County Comprehensive Plan. Task F will implement Goal 105 of the Monroe County Comprehensive Plan. This task will identify areas to which future development will be directed. Also, the overlay designations will give property owners more certainty with respect to whether they can or cannot develop their property. The requirement in Task F, that the HEI be reviewed or eliminated, is reasonable in light of Goal 105 of the Monroe County Comprehensive Plan. The HEI is currently used by Monroe County to evaluate the environmental sensitivity of land and its suitability for development and acquisition. The HEI requires lot-by-lot evaluations, which fail to take into account secondary impact of development and has resulted in the loss of valuable habitat. The Tier System in Goal 105 is designed to move Monroe County away from the existing HEI. Implementation of Goal 105 requires that the existing HEI be eliminated or revised. Task G of Year Eight of the Work Program requires Monroe County to "amend land development regulations to prohibit the designation of [CNA] (Tier 1) as a receiver site for ROGO exempt development from sender sites; and to further limit clearing of upland native habitat that may occur in the [CNA] (Tier I) and the Transition and Sprawl Reduction Area (Tier II) upon designation by the County." Petitioners contend that Task G is arbitrary and capricious and contravenes the law implemented because it fails to permanently protect even that habitat which Monroe County claims is most important to protect, allows the geographic scope of the contemplated rules to be defined in the future without stated criteria or standards, and allows an unnecessary delay in the adoption of protections which the data and legal requirements demonstrate should have been adopted two years earlier. Task G is intended to strengthen protection of habitat by adopting land development regulations to prohibit development in specified areas and to further limit clearing in designated areas. Goal 105, specifically, provides guidance as to the standards that such regulations must follow in Policy 105.2.1 of the Monroe County Comprehensive Plan. Petitioners contend that Task K of Year Eight of the Work Program requiring Monroe County to ensure the connection for up to 1,350 units at Stock Island to Key West Resort Utilities, is arbitrary and capricious and contravenes the law implemented. Petitioners charge that the requirement in the proposed rule is vague and could be met by simply connecting one home to the referenced wastewater utility to remedy a documented, serious water quality problem. When the purpose of Task K is considered, the reasonable meaning of the provision is that the task requires that Monroe County connect approximately 1,350 units to the designated facility. Petitioners contend that Task M of Year Eight of the Work Program, which requires Monroe County to "complete projects identified in the Stormwater Management Master Plan," is arbitrary and capricious and contravenes the law implemented. In support of this contention, Petitioners assert that the Proposed Rule does not identify the name or number of stormwater projects that are to be completed. Petitioners argue that by referring only to "projects," without specifying the name or number of the projects to be completed, the Proposed Rule may require that only a minimum of two projects be completed. The reasonable interpretation of Task M is that Monroe County is required to complete all the remaining projects identified in the Stormwater Management Master Plan. This meaning is supported by a review of related tasks in the previous years of the Work Program. For example, Year Six of the Work Program required Monroe County and other designated agencies to "initiate construction of selected projects as identified in the Stormwater Management Master Plan." Year Seven of the Work Program required that Monroe County and other agencies "continue implementing selected projects identified in the Stormwater Management Master Plan." Petitioners contend that Task P in Year Eight of the Work Program, which requires Monroe County to "provide up to $10 million in bond financing from the Tourist Impact Tax for acquisition of land for workforce housing and affordable housing sites," is arbitrary and capricious and contravenes the law implemented. As a basis for this contention, Petitioners claim that Task P sets a vague requirement which could be met by simply providing $1.00 in bond financing to provide a need which the State and Monroe County claim is important enough to justify the permitting increase allowed by Proposed Rules 28-18.210 and 28-20.110. Contrary to Petitioners' assertions, the requirement to provide $10 million in bond financing could not be met by providing $1.00 in bond financing. The $10 million figure represents the approximate amount of bond financing that will be provided. For the reasons stated above, it is not possible to include an exact amount in this Work Program requirement. The Work Program for Year Nine provides that the following tasks be done between July 13, 2005, through July 12, 2006: In coordination with the Florida Key Aquaduct Authority and Key Largo Sewer District, initiate the process to obtain $80 million in bond financing secured by connection fees. Secure site for lower Keys and Key Largo wastewater facilities. Petitioners contend that Task A for Year Nine for the Work Program, which requires that Monroe County, "in coordination with the Florida Keys Aqueduct Authority and the Key Largo Sewer District, initiate the process to obtain $80 million in bond financing secured by connection fees," is arbitrary and capricious and contravenes the law implemented. Petitioners contend that Task A, which requires that Monroe County only "initiate" the process necessary to obtain the required bond financing, and does not require that the funds be secured and dedicated to actual improvements, delays funding to remedy a critical water quality problem. The reasonable meaning of the provision in Task A, that Monroe County will initiate the process to obtain "80 million in bond financing secured by connection fees," is that Monroe County will take all steps legally necessary to accomplish obtaining the bond financing. Petitioners contend that Task B of Year Nine of the Work Program, which requires Monroe County to "secure a site for lower Keys and Key Largo wastewater facilities," is arbitrary and capricious and contravenes the law implemented, because it delays an important remedy to a critical water quality problem. Task B reasonably requires that one of the first steps that must be taken prior to constructing any wastewater facility is to secure a site. Irrespective of the need for the wastewater facilities specified in Task B, unless a site is secured, no construction can occur. Proposed Rule 28-20.110(1), which amends Policy of the Monroe County Comprehensive Plan by adding Year Ten to the Work Program, provides the following: Year Ten (July 13, 2006 through July 12, 2007) Award Contract for design, construction, and operation of lower Keys and Key Largo wastewater facilities. Begin construction of the lower Keys and Key Largo wastewater plants. Initiate connections to lower keys and Key Largo wastewater systems. Complete construction and hookups for Bay Point, Conch Key and Key Largo Trailer Village/Key Largo Park. Obtain $80M in bond financing secured by connection fees Petitioners contend that Task A, which requires Monroe County to award a contract for design, construction, and operation of the lower Florida Keys and Key Largo wastewater facilities, is arbitrary and capricious and contravenes the law implemented, because it delays an important remedy to a critical water quality problem. Petitioners also contend that Task D, which requires that construction and hookups for specified areas be completed, and Task E, which requires Monroe County to obtain $80 million in bond financing secured by connection fees, are arbitrary and capricious and contravene the law implemented. That Tasks A, D, and E are required to be completed in Year Ten of the Work Program, between July 13, 2006, and July 12, 2007, is reasonable in view of the steps that must be taken prior to completing the responsibilities provided in those tasks. Petitioners contend that Task B, which requires Monroe County to "begin construction of the lower Florida Keys and Key Largo Trailer Village/Key Largo Park wastewater plants" between July 13, 2006, and July 12, 2007, is arbitrary and capricious and contravenes the law implemented. Petitioners assert that this portion of Proposed Rule 28-20.110 delays an important remedy to a critical water quality problem and does not require the completion of construction or the hookup and operation of the necessary facility. Task B of the Work Program, to begin construction of the lower Florida Keys and Key Largo wastewater plants, reasonably and logically follows the task in the preceding work year that required Monroe County to secure a site for the lower Florida Keys and Key Largo wastewater facilities. Given this chronology, it is reasonable that Task B does not require that the specified wastewater facilities be completed and fully operational the same year that construction begins. Petitioners contend that Task C of Year Ten of the Work Program, which requires Monroe County and Largo Sewer District to "initiate connections to lower Keys and Key Largo wastewater systems," is arbitrary and capricious and contravenes the law implemented. As a basis for this contention, Petitioners assert that Task C does not require the completion of connections and operation of the system, but requires only the undefined "initiation" of connections. Task C, which requires Monroe County to "initiate connections" to the lower Florida Keys and Key Largo wastewater facilities, is not arbitrary and capricious. Given the purpose of this task, this provision reasonably requires Monroe County to begin connecting units to the wastewater facilities. Even without a precise number, the reviewing agencies can evaluate the Work Program for Year Ten, including Task C, and determine if Monroe County has made substantial progress. City of Marathon Work Program Under Proposed Rules Proposed Rule 28-18.210 adds Year Eight and Year Nine to the existing Work Program in Policy 101.2.14 of the Marathon Comprehensive Plan. The tasks in the Work Program, many of which implement the Partnership Agreement, include tasks related to the construction of wastewater facilities, affordable housing, and hurricane evacuation. Year Eight of the Work Program of the Marathon Comprehensive Plan include, in relevant, part the following tasks: Year Eight (July 12, 2004 through July 12, 2005) Begin construction of wastewater collection lines for Little Venice Phase II by December 2004. Work with the Florida Keys Aqueduct Authority to initiate bond financing for citywide sewer facilities and to develop a schedule of events necessary to initiate process by December 2004. Develop and advertise a Request for Proposal for the design, construction, operation of Marathon Central Wastewater System by December 2004. Obtain necessary bond financing (60% of projected sewer cost) secured by connection fees by December 2004. Award contract for design, construction and operation of Marathon Central Wastewater System by December 2004. By January 2005, identify potential acquisition sites for affordable work force housing. Establish a partnership with non- profit organizations in order to construct affordable housing using additional state funds. Evaluate strategies to increase the time that affordable housing remains affordable; establish a maximum sales price for work force housing and establish a ceiling on down payments that are not subsidized by public programs; and amend comprehensive plan and/or land development regulations. * * * Develop a map or list of real estate numbers of lots containing environmentally sensitive lands in need of acquisition and submit to the Department of Community Affairs by July 2004. Assist the state in land acquisition efforts by establishing a land acquisition advisory committee to prioritize proposed acquisitions by July 2004. Complete a comprehensive analysis of hurricane evacuation issues in the Florida Keys and develop strategies to reduce actual hurricane clearance times and thereby reduce potential loss of life from hurricanes. Year Nine of the Work Program of the Marathon Comprehensive Plan includes in relevant part the following tasks: Year Nine (July 13, 2005 through July 12, 2006) Begin construction of Phase I of Marathon Central Wastewater System by January 2006. Evaluate wastewater master plan and indicate areas, if any, that will not receive central sewer. For any area that will not be served by central sewer, develop a septic tank inspection program and begin implementation of the program by September 2005. * * * E. Develop and implement a Building Permit Allocation System that discourages and limits development in environmentally sensitive areas within the proposed Marathon comprehensive plan by July 2005. Petitioners contend that Proposed Rule 28-18.210(1), which establishes the Work Program for Years Eight and Nine, is arbitrary and capricious and contravenes the law implemented, because it fails to adopt regulation and plan changes, or requires same, to protect terrestrial habitat to the extent shown necessary in the Carrying Capacity Study. The mere fact that the proposed Work Plan for Years Eight and Nine of the Marathon Comprehensive Plan does not address habitat protection, does not make those provisions arbitrary or capricious. Neither does it mean that they contravene law. In this case, it reflects that the Work Plan emphasizes other issues relevant to the City of Marathon Comprehensive Plan. Siting Utilities and Public Facilities The siting of public facilities in Monroe County is governed by existing Policy 101.12.4 in the Monroe County Comprehensive Plan. According to that policy, Monroe County requires that an "analyses be undertaken prior to finalizing plans for the siting of any new or significant expansion (greater than 25 percent) of any existing public facility," and that the analyses include "an assessment of needs, evaluation of alternative sites and design alternatives for the selected sites and assessment of direct and secondary impacts on surrounding land uses and natural resources." With regard to the assessment impacts on surrounding land uses and natural resources, existing Policy 101.12.4 provides the following: The assessment of impacts on surrounding land uses and natural resources will evaluate the extent to which the proposed public facility involves public expenditures in the coastal high hazard area and within environmentally sensitive areas, including disturbed salt marsh and buttonwood wetlands, undisturbed beach berm areas, units of the coastal barrier resources system, undisturbed uplands (particularly high quality hammock and pinelands), habitats of species considered to be threatened or endangered by the state and/or federal governments, consistent with 105.2.1 offshore islands, and Conservation Land Protection Areas. Proposed Rule 28-20.110(2) amends existing Policy 101.12.4, which deletes the term "Conservation Land Protection Areas" from the category of areas included as environmentally sensitive areas, as quoted above, and replaces it with the term, "Natural Areas (Tier I)." Proposed Rule 28-20.110(2) also adds the following provision to existing Policy 101.12.4. Except for passive recreational facilities on publicly owned land, no new public community or utility facility other than water distribution and sewer collection lines or lift stations, and the existing Key Largo Wastewater Treatment Facility, shall be allowed within the Natural Areas (Tier I) unless it can be accomplished without clearing of hammock or pinelands. Exceptions to this requirement may be made to protect the public health, safety and welfare, if all the following criteria are met: No reasonable alternatives exist to the proposed location; and The proposed location is approved by a super-majority of the Board of County Commissioners. Petitioners contend that Proposed Rule 28-20.110(2), discussed above, is arbitrary and capricious and contravenes the law implemented. Petitioners assert that the Proposed Rule allows the siting of public facilities in terrestrial habitats (CNA or Tier I) and also allows water distribution and sewer collection lines or lift stations to be built as a matter of right in a CNA or Tier I, contrary to the findings of the Carrying Capacity Study. Petitioners also contend that the provision in the Proposed Rule, discussed above, is vague, because it refers to the term "natural areas," but is intended to mean CNAs. In the recent past, a decision to site a sewage treatment facility in an environmentally sensitive hammock elicited considerable controversy. Ultimately, Monroe County and the DCA agreed that public facilities should not be located on environmentally sensitive land. The proposed change to Policy 101.12.4 strengthens the policy by requiring approval of a super majority of the Monroe County Board of County Commissioners (County Commission) for an exemption. This also adds specificity to the policy and provides more protection for natural areas and, thus, improves protection of environmentally- sensitive habitat. Contrary to Petitioners' assertion, the term "natural area" is not vague. The Monroe County Comprehensive Plan currently includes Goal 105, which describes a detailed land classification system. "Natural Area (Tier I)" represents natural areas that can be targeted for acquisition and is an updated term. On the other hand, the term "Conservation Land Protection Areas" refers to lands targeted for acquisition by federal and state agencies. ROGO Exemption for Public Facilities Both Monroe County and Marathon have a "Rate of Growth Ordinance," also known as ROGO. A site proposed for development is ranked based on the environmental sensitivity of the property and receives negative points for greater environmental sensitivity. A site proposed for development can also receive positive points for such things as providing its own water system or elevation above the minimum flood insurance elevation. Monroe County and the City of Marathon award their annual allocation of development permits to the top-scoring sites. Proposed Rule 28-20.110 will make several modifications to the ROGO point allocation system in the Monroe County Comprehensive Plan. Existing Policy 101.3.4 of the Monroe County Comprehensive Plan provides that "public facilities shall be exempted from the requirements of the Permit Allocation System for new non-residential development." The existing policy also provides that certain development activity by enumerated federally tax-exempt, not-for-profit organizations "may be exempted from the Permit Allocation System by the County Commission after review by the Planning Commission upon a finding that such activity will predominantly serve the County's non- transient population." Proposed Rule 28-20.110(3) amends existing Policy 101.3.4 by requiring that the County Commission make an additional finding as a condition of exempting certain development activity by certain federally tax-exempt not-for- profit organizations from the Permit Allocation System. Pursuant to the proposed rule, the County Commission must also find that the "development activity is not planned within an area proposed for acquisition by governmental agencies for the purpose of resource protection." Petitioners contend that the provision of Proposed Rule 28-20.110(3), discussed above, is arbitrary and capricious and contravenes the law implemented in that the development activities of the federally tax-exempt, not-for-profit organizations covered by the proposed rule allows development activity on some environmentally-sensitive areas and is inconsistent with the Carrying Capacity Study. Existing Policy 101.3.4 allows development activity by not-for-profit organizations without a permit allocation because such development does not include overnight accommodations which might impact hurricane evacuation. Since a permit allocation was not necessary, such development was not affected by the negative points awarded for development in an area proposed for acquisition for resource protection. However, some not-for- profit organizations proposed development in environmentally- sensitive areas. The proposed change will prevent ROGO-exempt development on such lands and improve the protection of environmentally-sensitive habitat. Lot Aggregation Existing Policy 101.5.4, of the Monroe County Comprehensive Plan addresses the issue of lot aggregation and provides that "points shall be assigned to Allocation Applications for proposed dwelling units, which include a voluntary reduction of density permitted as of right within subdivisions (residential units per legally platted, buildable lots) by aggregating vacant, legally platted, buildable lots." This policy sought to reduce density within subdivisions by awarding or assigning positive points to applicants who aggregated two or more contiguous, vacant, legally buildable lots. The existing policy motivated and allowed applicants to purchase any contiguous property in order to be awarded additional points and, thus, increased their chances of receiving an allocation, even if the lots were in areas targeted for public acquisition for resource protection. Proposed Rule 28-20.110(4) amends Policy 101.5.4, Subsection 3, by prohibiting the awarding of points to Allocation Applications "for lot aggregation within those areas proposed for acquisition by public agencies for the purpose of resource protection." Petitioners assert that the proposed rule is arbitrary and capricious and contravenes the law implemented because it fails to adequately protect terrestrial habitat to the extent shown necessary in the Carrying Capacity Study. The basis of Petitioners' assertion is that under Proposed Rule 28-20.110(4), an applicant can get positive points for aggregating habitat, if the area is not proposed for acquisition by public agencies for the purpose of resource protection. Proposed Rule 28-20.110(4) will direct applicants seeking to be awarded additional points for "lot aggregation away from areas proposed for acquisition by public agencies for resource protection and, thereby, improve protection of terrestrial habitat. Clearing of Native Vegetation Existing Policy 205.2.7 of the Monroe County Comprehensive Plan provides that the "clearing of native vegetation shall be limited to the immediate development area." Under the existing policy, an applicant with aggregated lots would demand to clear a portion of both lots, so that a large portion of all of the lots would be cleared. Proposed Rule 28-20.110 amends existing Policy 205.27.7 by adding the following provision relating to the clearing of vegetation areas where Allocation Applications have received points for lot aggregation: For applications that receive points for lot aggregation under the Permit Allocation System for residential development, clearing of vegetation shall be limited to the open space ratios in Policy 205.2.6 or 5,000 square feet, whichever is less. The clearing of vegetation for ROGO applications that receive points for lot aggregation is also addressed in Proposed Rules 28-20.120(4), which adds a new provision, Regulation 9.5-347(e), to the Monroe County Land Development Regulations. That new provision is as follows: Section 9.5-347 (e) Lot Aggregation and Clearing: For ROGO applications that receive points for lot aggregation under Section 9.5-122.3 (a)(3), clearing of vegetation shall be limited to the open space ratios in paragraph (b) above or five-thousand (5,000) square feet, whichever is less. Petitioners contend that Proposed Rules 28-20.110(b) and 28-20.120(4) are arbitrary and capricious and contravene the law implemented, because they do not prohibit clearing of aggregated lots and are inconsistent with the Principles Guiding Development and with the Carrying Capacity Study. Notwithstanding Petitioners' assertions, even though the proposed rules do not prohibit all clearing of native vegetation, they will limit the amount of clearing for applicants who receive a ROGO allocation based upon lot aggregation. Under Proposed Rule 28-20.120(4), the clearing will be limited to an amount necessary to construct a reasonably-sized house. Technical Coordination Letter Proposed Rule 28-20.110(5), which will add a new policy, Policy 101.5.11, to the Monroe County Comprehensive Plan, provides the following: If not listed in the document "Parcels Not Located in Threatened and Endangered Species Habitat and Not Subject to FWS Consultation", or involving minor development activity exempted by the U.S. Fish and Wildlife Service (USFWS)", any application for a ROGO or NROGO allocation shall contain a technical coordination letter from the USFWS. The County shall consider the recommendations of the USFWS's technical coordination letter in the issuance of the subject permit, except that if a low-effect habitat conservation plan is required by USFWS, the mitigation requirements of that plan shall be incorporated in the conditions of the permit. As a result of federal litigation, the U.S. Fish and Wildlife Service ("USFWS") created a list of "Parcels Not Located in Threatened and Endangered Species Habitat and Not Subject to FWS Consultation." Monroe County and the DCA have developed the practice of requiring a technical coordination letter from the USFWS for development on parcels that are not on that list or are not otherwise exempt from USFWS review. Proposed Rule 28-20.110(5) incorporates into the Monroe County Comprehensive Plan a current practice that resulted from federal litigation. Monroe County Land Development Regulation 9.5-120 Proposed Rule 28-20.120(1) adds the phrase "species of special concern" to the following terms defined in Section 9.5-120(b) of the Monroe County Land Development Regulation as shown by the underlining: (1) "Known habitat of threatened/endangered animal species or species of special concern"; (2) "Potential habitat of threatened/endangered animal species" or species of special concern; and (3) Wide-ranging threatened/endangered animal species or species of special concern. This proposed change will conform the land development regulations to the Monroe County Comprehensive Plan by expanding the list of species that result in negative points under the Permit Allocation System to include "species of special concern." Existing Regulation 9.5-120(b) includes in the definitions of "known habitat of threatened/endangered animal species" and "potential habitat of threatened/endangered species" the sentence, "The county's threatened and endangered species maps shall constitute prima facie evidence of the species unless determined otherwise by the director of environmental resources." The definition of "wide-ranging threatened/endangered animal species" includes the sentence, "The county's threatened and endangered species maps shall constitute prima facie evidence of wide-ranging threatened or endangered species unless determined otherwise by the director of environmental resources."8 Proposed Rule 28-20.120(1) amends Section 9.5-120(b) by deleting the phrase, "unless determined otherwise by the director of environmental resources" from the sentences quoted above. Proposed Rule 28-20.120(1)(a) adds the following provision to the section of Regulation 9.5-120, which defines the term "known habitat of threatened/endangered species or species of special concern": (1) . . . The county's threatened and endangered species maps shall constitute prima facie evidence of the species. Within areas designated for public acquisition for the purposes of resource protection, any threatened, endangered or species of special concern species observed on site while conducting a habitat evaluation shall be noted on the adopted Threatened and Endangered Species Maps. Such observations noted while conducting a habitat evaluation by County Staff Biologists, consultants certified by the County, conducting habitat evaluations, or state or federal agency representatives conducting field inspections shall also constitute evidence of species. Petitioners contend that the portion of Proposed Rule 28-20.120(1)(a), quoted above, is arbitrary and capricious. Petitioners assert that the Proposed Rule fails to account for potential observations of "known habitat of threatened/endangered animal species" on parcels that are not within "areas designated for public acquisition for purposes of resource protection." Also, Petitioners assert that the Proposed Rule limits observations of species required to be noted on the adopted threatened and endangered species maps to consultants or scientists on the parcel specifically to conduct an HEI analysis and fails to require field verification of the parcel. Proposed Rule 28.20.120(1)(a) will expand the circumstances in which observations of listed species will cause modification of the adopted threatened and endangered species maps. Under the present land development regulations, Monroe County modified the maps only if a county staff biologist observed a listed species and did not take into account other professional observations. Monroe County Land Development Regulation 9.5-122.3 Regulation 9.5-122.3(a)(8) of the Monroe County Land Development Regulations establishes and assigns evaluation criteria and point assignment for applications for proposed dwelling units in Monroe County. The existing regulation requires that negative points be assigned to applications that propose a dwelling unit within a "known habitat of a documented threatened/endangered species" and a "potential habitat of threatened/endangered species." Proposed Rule 28-20.120(2) adds the following language to Section 9.5-122.3.(a)(8),9 as shown by the underlined provisions: Point Assignment: Criteria: -10 An application which proposes a dwelling unit within a known habitat of a threatened/endangered species or a species of special concern. For species of special concern, negative points shall only be applied to areas designated for public acquisition for the purpose of resource protection. -5 An application which proposes a dwelling unit within a potential habitat of a threatened/endangered species or a species of special concern. For species of special concern, negative points shall only be applied to areas designated for public acquisition purposes of resource protection. Regulation 9.5-1223.(a)(8), as amended, adds "species of special concern" to the species covered by the existing regulation. Also, the amended regulation requires that negative points be assigned to applications that propose dwelling units in a habitat of a species of special concern, if the area is designated for public acquisition for purposes of resource protection. Petitioners contend that Proposed Rule 28-20.120(2), which amends Regulation 9.5-122.3(a)(8), is arbitrary and capricious. As a basis for this contention, Petitioners assert that even though the Proposed Rule increases situations where an application is awarded negative points, it decreases protection of habitat by limiting the negative point award only to habitat of special concern that have been designated for public acquisition. Proposed Rule 28-20.120(2) increases situations in which an application will be awarded negative points by adding "species of special concern" to the species covered by Regulation 9.5-122.3(a)(8). By awarding negative points as provided in the proposed rule, there is increased protection of habitat for species of special concern. Monroe County Land Development Regulation 9.5-336 Proposed Rule 28-20.120(3) amends Section 9.5-336(b) of the Monroe County Land Development Regulations as follows: (b) Review and Amendment: The existing conditions map may be refined to reflect conditions legally in existence on February 28, 1986. Such refinements shall be made pursuant to the procedures for typographical and drafting errors in section 9.5-511(e). The existing conditions map as referenced throughout this chapter is intended only to serve as a general guide to habitat types for the purpose of preliminary determination of regulatory requirements. The county biologist shall make the final determination of habitat type based upon field verification, except that existing conditions that reflect disturbed with hammock shall be classified as a low quality hammock. Unlawful conditions shall not be recognized when determining regulatory requirements. Petitioners contend that Proposed Rule 28-20.120(3) is arbitrary and capricious and contravenes the law implemented because it does not protect all habitat. The existing conditions map was prepared in the 1980s. Many of the sites designated on the map as "disturbed with hammock" have re-vegetated since then. The proposed change will protect those sites by requiring clustering away from the hammock and by controlling the amount of allowed clearing. Hurricane Evacuation Monroe County and Marathon face a unique hurricane evacuation challenge. There is only one road out of the Florida Keys, and everyone must use that road to evacuate. For a Category 3 or greater hurricane, all areas of the Florida Keys must be evacuated because of the low elevations, the vulnerability to storm surge, and the logistics of post-disaster recovery. The Monroe County Comprehensive Plan and the Marathon Comprehensive Plan currently state that each ". . . shall reduce hurricane evacuation clearance times to 24 hours by the year 2010." The 24-hour standard was adopted by the Administration Commission at the conclusion of prior litigation over the Monroe County Comprehensive Plan. The term "hurricane evacuation clearance time" refers to the time that the emergency managers must call the evacuation before the arrival of tropical storm force winds. Hurricane evacuation clearance time includes both the time for citizens to mobilize (i.e., get their affairs in order, shelter their houses, take care of their belongings), and the time to evacuate the vehicles from the roadway. Tropical storm force winds typically arrive eight to 12 hours before the eye of the storm. In order to achieve a 24-hour hurricane evacuation clearance time, emergency managers must call the evacuation 32 to 36 hours before the arrival of the eye. The DCA contracted with Miller Consulting, Inc., to create a computer model to estimate the actual hurricane evacuation clearance time for the Florida Keys. The Miller model provides the best available data and analysis for estimating the clearance time. The latest run of the Miller model performed by the DCA using 2000 Census data, supplemented with development permit data up to August 2004, provides the best estimate of clearance time. This run of the Miller model estimates a hurricane evacuation time of 23 hours and 56 minutes to reach the beginning of the Homestead Extension of the Florida Turnpike on the mainland, and 24 hours and 48 minutes to reach the hurricane shelter at Florida International University ("FIU"). The beginning of the Florida Turnpike in Florida City is the appropriate endpoint for hurricane evacuation clearance time estimates. Florida City is a point of relative safety outside of the Category 3 vulnerability zone. Florida City is also the point of dispersal for the Florida Keys, where evacuees disperse to any number of destinations, such as South Dade, the FIU shelter, or a hotel in Orlando. The Miller model estimates that if those permit allocations are restored and the annual allocation is increased as described above, the hurricane evacuation clearance time next year will be 24 hours and four minutes. This exceeds the 24-hour standard adopted by the Administration Commission. Proposed Rule 28-20.110 adds the following requirement to Year Eight of the Work Program in Policy 101.2.13 of the Monroe County Comprehensive Plan and Policy 101.2.12 of the Marathon Comprehensive Plan: "Complete a comprehensive analysis of hurricane evacuation issues in the Florida Keys and develop strategies to reduce actual hurricane clearance times and thereby reduce potential loss of life from hurricanes." The Florida Keys' local governments have begun the comprehensive analysis of hurricane evacuation issues by convening a workgroup comprised of local government-elected officials and staffed by the DCA. The hurricane workgroup is considering alternative strategies to reduce clearance times, such as constructing an additional outbound lane, using transportation system management to create a temporary outbound lane, updating the assumptions for the Miller model, reducing transient occupancy, or calling the evacuation earlier. The working group must develop a strategy that balances or accommodates development and also addresses hurricane clearance times. The hurricane workgroup must do much more than simply squeeze a few more minutes out of the Miller model. There are currently 13,000 to 14,000 vacant platted lots in the Florida Keys, which must be allowed to develop or must be purchased by government. On average, 3,000 dwelling units generates about one hour of clearance time. As an example, if 8,000 or so lots were purchased for habitat protection, then two more hours of clearance time will be needed to accommodate the remaining 5,000 or 6,000 lots. The hurricane workgroup must develop a strategy to handle the amount of development permitting that can be expected and a program to acquire the balance of the vacant lots. Affordable and Workforce Housing There is an affordable housing crisis in the Florida Keys. The geography of the Florida Keys hinders the ability of working families in the Florida Keys to find affordable housing. Unlike other expensive areas, such as Boca Raton, working families cannot find affordable housing nearby; the nearest area where housing prices are affordable is the mainland in Dade County. From 1999 to 2003, there were 693 allocations for affordable housing units in the Florida Keys. This amount includes all the allocations for affordable housing units for that time period, even those allocations for which affordable housing units were not constructed. The number of affordable housing allocations issued from 1999 to 2003 and the number being issued under the existing Comprehensive Plans of Monroe County and the City of Marathon, are not sufficient to address the need for affordable housing. The Partnership Agreements recognize and address the affordable housing shortfall by increasing the number of annual affordable housing allocations, restoring residential allocations lost in previous years, and providing funding for the acquisition of land and the construction of workforce housing. As discussed above, Proposed Rule 28-20.110 implements the provisions of the Partnership Agreement by amending the Monroe County Comprehensive Plan as follows: increasing the number of annual affordable housing allocations from 32 to 71; (2) reallocating 140 unused allocations to affordable housing; and (3) requiring that the affordable housing remain affordable in perpetuity. Additionally, as specified in paragraph 60, the Work Program in Proposed Rule 28-20.110 requires Monroe County to complete tasks which will be an improvement of the affordable housing situation in Monroe County. As discussed above, Proposed Rule 28-18.210 implements the Partnership Agreement by amending the City of Marathon Comprehensive Plan as follows: (1) increases the overall number, though not the percentage, of allocations for affordable housing to six; (2) restoring 65 unused allocations for affordable housing; and (3) requiring that the affordable housing remain affordable in perpetuity. Also, as specified in paragraph 101, Proposed Rule 28-18.210 requires the City of Marathon to complete tasks that will result in improving the affordable housing issues in the City of Marathon. Proposed Rules 28-20.110 and 28-18.210 only partially address the affordable housing shortage in the Florida Keys. Nonetheless, the proposed amendments to the Comprehensive Plans of Monroe County and the City of Marathon will improve the current affordable housing shortage by increasing the number of affordable houses and providing the financial resources to make that more likely to occur. The Principles Guiding Development Subsection 380.0552(7), Florida Statutes (2004), provides in relevant part: PRINCIPLES FOR GUIDING DEVELOPMENT.- -State, regional, and local agencies and units of government in the Florida Keys Area shall coordinate their plans and conduct their programs and regulatory activities consistent with the principles for guiding development . . . . For the purposes of reviewing consistency of the adopted plan or any amendments to that plan with the principles for guiding development and any amendments to the principles, the principles shall be construed as a whole and no specific provision shall be construed or applied in isolation from the other provisions. . . . [T]he following shall be the principles with which any plan amendments must be consistent: To strengthen local government capabilities for managing land use and development so that local government is able to achieve these objectives without the continuation of the area of critical state concern designation. To protect shoreline and marine resources, including mangroves, coral reef formations, seagrass beds, wetlands, fish and wildlife, and their habitat. To protect upland resources, tropical biological communities, freshwater wetlands, native tropical vegetation (for example, hardwood hammocks and pinelands), dune ridges and beaches, wildlife, and their habitat. To ensure the maximum well-being of the Florida Keys and its citizens through sound economic development. To limit the adverse impacts of development on the quality of water throughout the Florida Keys. To enhance natural scenic resources, promote the aesthetic benefits of the natural environment, and ensure that development is compatible with the unique historic character of the Florida Keys. To protect the historical heritage of the Florida Keys. To protect the value, efficiency, cost-effectiveness, and amortized life of existing and proposed major public investments, including: The Florida Keys Aqueduct and water supply facilities; Sewage collection and disposal facilities; Solid waste collection and disposal facilities; Key West Naval Air Station and other military facilities; Transportation facilities; Federal parks, wildlife refuges, and marine sanctuaries; State parks, recreation facilities, aquatic preserves, and other publicly owned properties; City electric service and the Florida Keys Electric Co-op; and Other utilities, as appropriate. To limit the adverse impacts of public investments on the environmental resources of the Florida Keys. To make available adequate affordable housing for all sectors of the population of the Florida Keys. To provide adequate alternatives for the protection of public safety and welfare in the event of a natural or manmade disaster and for a post-disaster reconstruction plan. To protect the public health, safety, and welfare of the citizens of the Florida Keys and maintain the Florida Keys as a unique Florida resource. In determining whether the Proposed Rules are consistent with the principles, the principles should be considered as a whole. No specific provision should be construed or applied in isolation from other provisions. Ability to Manage Land Use and Development Principle A, set forth in Subsection 380.0552(7)(a), Florida Statutes, is "to strengthen local government capabilities for managing land use and development so that local government is able to achieve these objectives without the continuation of the area of critical state concern designation." Monroe County and the City of Marathon have evidenced a willingness and commitment to provide the funding required to meet the objectives of the Principles Guiding Development. Both local governments have included in the Proposed Rules tasks which reflect their understanding of the need to provide critical facilities, such as wastewater treatment facilities. While the need for such facilities has previously been acknowledged, the Proposed Rules provide a specific source of revenue to provide the needed facilities. Moreover, with regard to Monroe County, the proposed rules/regulations at issue in this proceeding strengthen the environmental protections measures in the Comprehensive Plans while allowing reasonable development. The proposed rules for Monroe County and the City of Marathon are consistent with Principle A. Environmental Issues Subsections 380.0552(7)(b), (c), and (e), Florida Statutes, are principles which require consideration of the impacts on the environment of the Florida Keys. Principle B is "to protect shoreline and marine resources, including mangroves, coral reef formations, seagrass beds, wetlands, fish and wildlife and their habitat." Principle C is "to protect upland resources, tropical biological communities, freshwater wetlands, native tropical vegetation (for example, hardwood hammocks and pinelands), dune ridges and beaches, wildlife and their habitat." Principle E is "to limit the adverse impacts of development on the water quality of water throughout the Florida Keys." Principle I is "to limit the adverse impacts of public investments on the environmental resources of the Florida Keys." The Proposed Rules of Monroe County and the City of Marathon include amendments to the Work Program which provide significant funding for sewage treatment systems that will enhance the protection of the shoreline and marine resources. The Proposed Rules of Monroe County and the City of Marathon are consistent with Principle B. The Proposed Rules of Monroe County improve protection of terrestrial habitat, limit clearing of native vegetation, and provide safeguards to ensure that parcels in threatened and endangered species habitat are protected. The proposed rules of Monroe County are consistent with Principle C. The portions of the Proposed Rules of the City of Marathon that are the subject of this proceeding do not specifically address Principle C. However, the Proposed Rules of the City of Marathon are not inconsistent with Principle C. Accordingly, the proposed rules of the City of Marathon are consistent with Principle C. The Proposed Rules of Monroe County and the City of Marathon limit the adverse impacts of development on the quality of water throughout the Florida Keys by the funding commitments that will hasten the construction of the sewage treatment facilities. The Proposed Rules of Monroe County and the City of Marathon are consistent with Principle E. The Proposed Rules do not encourage any public investment that would have an adverse impact on environmental resources. To the contrary, the Monroe County and the City of Marathon Proposed Rules provide for public investments in waste water improvements that are accelerated. Also, the Monroe County Proposed Rules prevent the construction of public facilities within a hammock area. The Proposed Rules of Monroe County and the City of Marathon are consistent with Principle I. Economic Development Principle D in Subsection 380.0552(7)(d), Florida Statutes, is "to ensure the maximum well-being of the Florida Keys and its citizens through sound economic development. The basis of the Florida Keys' economy is tourism, which is attracted by a clean and healthy environment. The increased protection of water quality that should be achieved by the hastened construction of sewage treatment facilities and the improved protection of habitat will strengthen the economy of the Florida Keys and provide the basis for a sound economic development. Also, the Proposed Rules balance environmental protection with property rights. The Proposed Rules of Monroe County and the City of Marathon are consistent with Principle D. Historical Character and Heritage Principle F in Subsection 380.0552(7)(f), Florida Statutes, is "to enhance natural and scenic resources, promote the aesthetic benefits of the natural environment and ensure that development is compatible with the unique historic character of the Florida Keys." Principle G in Subsection 380.0552(7)(g), Florida Statutes, is "to protect the historical heritage of the Florida Keys." The Proposed Rules of Monroe County and the City of Marathon will have little or no impact on the historic character and historical heritage of the Florida Keys. Thus, the Proposed Rules do no harm to either the historic character or historical heritage of Monroe County or the City of Marathon. Public Investments Principle H in Subsection 380.0552(7)(h), Florida Statutes, is "to protect the value, efficiency, cost- effectiveness, and amortized life of existing and proposed major life investments," including: The Florida Keys Aqueduct and water supply facilities; Sewage collection and disposal facilities; Solid waste collection and disposal facilities; Key West Naval Air Station and other military facilities; Transportation facilities; Federal parks, wildlife refuges, and marine sanctuaries; State parks, recreation facilities, aquatic preserves, and other publicly owned properties; City electric service and the Florida Keys Electric Co-op; and Other utilities, as appropriate. . . . The Proposed Rules of Monroe County and the City of Marathon do nothing to undermine the value, efficiency, cost- effectiveness or amortized life of existing major investments. Rather, the Proposed Rules will result in funding and timely construction of the major sewage and disposal facilities that are already contemplated by Monroe County and the City of Marathon's existing Comprehensive Plans. Affordable Housing Principle J in Subsection 380.0552(7)(j), Florida Statutes, is "to make available adequate affordable housing for all sectors of the population of the Florida Keys." The Proposed Rules include a one-time allocation of 165 permits for affordable housing in Monroe County and 65 permits for affordable housing in Marathon. The Proposed Rules will require all future affordable housing to remain as affordable in perpetuity, rather for a limited time frame. The Propose Rules are consistent with Principle J. Natural or Man-made Disaster and Post-Disaster Relief Principle K in Subsection 380.0552(7)(k), Florida Statutes, is "to provide adequate alternatives for the protection of public safety and welfare in the event of a natural disaster or man[-]made disaster and for a post[-]disaster reconstruction plan." The Proposed Rules require officials of Monroe County and the City of Marathon to participate with other Florida Keys' local governments in a comprehensive analysis of hurricane evacuation issues. The Proposed Rules are consistent with Principle K. Health, Safety, and Welfare of Citizens and Maintenance of Florida Keys as Unique Resource Principle L in Subsection 380.0552(7)(l), Florida Statutes, is "to protect the health, safety, and welfare of the citizens of the Florida Keys and maintain the Florida Keys as a unique Florida resource." The Proposed Rules of Monroe County include provisions that increase protection of upland habitat and require a moratorium on ROGO/NROGO applications in hammocks and pinelands, revisions to the CNA maps, and amendments to the land development regulations. The Proposed Rules for Monroe County and the City of Marathon will improve the water quality by providing funding for and hastening the construction of sewage treatment facilities. The Proposed Rules of Monroe County and the City of Marathon will provide more permit allocations for affordable housing, require Monroe County to approve bond funding for the construction of affordable housing, and provide that all future affordable housing remain affordable in perpetuity. Also, the Proposed Rules require Monroe County and the City of Marathon to participate in a Florida Keys wide analysis and solution to the hurricane evacuation problem. The Proposed Rules of Monroe County and the City of Marathon further the objective of and are consistent with Principle K. The Proposed Rules of Monroe County and the City of Marathon are consistent with Principle L.
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Several years prior to1978, petitioner General Development Corporation (GDC) applied to the DER for a dredge and fill permit to remove a plug of land between the Ocean Breeze Waterway and the North Fork of the St. Lucie River. During the course of negotiations for this permit, it was discovered that the North Port St. Lucie Sewage Treatment Plant, owned and operated by General Development Utilities, Inc., a wholly-owned subsidiary of the petitioner, was operating without a permit from the DER and discharging effluent into a ditch which flowed into the Ocean Breeze Waterway. In March of 1978, a temporary operating permit was issued for the sewage treatment plant. In July of 1978, petitioner received from the DER Permit No. 253.123- 1031 to dredge an area approximately 800 feet in length, 90 feet in width and 6 feet in depth in order to connect the Ocean Breeze/Sagamore Waterways to the dead end oxbow of the North Fork of the St. Lucie River. The permit application was given special consideration pursuant to Rule 17-4.28(7), Florida Administrative Code. The purpose for obtaining the permit was to create direct navigable access to the North Fork of the St. Lucie River from thee Ocean Breeze Waterway. The Ocean Breeze Waterway was and is currently connected to the North Fork of the St. Lucie River by a narrow, shallow, meandering creek and lake system. However, there is not a large enough opening to allow the type of navigable access desired by the petitioner for the benefit of 118 lots plotted along the Ocean Breeze and Sagamore Waterways. Among the seven particular or special conditions attached to the dredge and fill permit issued to petitioner was that the earthen plug not be removed until such time as a permanent operational permit was issued for the sewage treatment plant owned and operated by General Development Utilities, Inc. More specifically, petitioner agreed to the following special conditions to the issuance of the dredge and fill permit: "(7) The applicant is aware that the GDC Utilities' sewage plant is providing an unknown quantity of discharge into Ocean Breeze Waterway and that this discharge may be a source of pollution to the receiving body of water unless affirmative steps are taken by the Utilities. The sewage treatment plant is currently operating under a Temporary Operating Permit (TP56-4601). In no case shall the plug at Cove Waterway be removed before an Operation Permit for the STP has been issued by the Department of Environmental Regulation." At time of issuance of the dredge and fill permit, DER personnel considered the quoted special condition number 7 to an integral part of the permit in terms of water quality assurances. General Development Utilities, Inc. has not been able to obtain a permanent operational permit from the DER for its sewage treatment plant which discharges into a ditch that flows into the Ocean Breeze Waterway. Therefore, particular condition number 7 has not been satisfied and petitioner has been unable to proceed with the dredging or removing of the plug under the permit. As a result of the delays in removal of the plug, petitioner has had to repurchase some 41 of the 118 plotted lots. The sewage treatment plant was and is still operating under a temporary permit. General Development Utilities, Inc. has requested a permanent operational permit for the sewage treatment plant and DER has issued a letter of intent to deny such a permit. As a result, General Development Utilities has petitioned DER for site specific alternative criteria pursuant to Rule 17-3.031, Florida Administrative Code. This matter is the subject of a separate proceeding currently being held in abeyance pending a determination of alternative criteria. General Development Utilities, Inc. v. Department of Environmental Regulation, DOAH Case No. 81-177. In September of 1980, petitioner sent a letter to DER requesting that special condition number seven be removed from its dredge and fill Permit No. 253.123-1031. It was intended that this request be considered as a minor modification to the dredge and fill permit. In response, DER's Chief of the Bureau of Permitting, Suzanne P. Walker, informed petitioner by letter dated October 15, 1980, that it was the staff's initial reaction, after a review of the original dredge and fill permit file, that the requirement that the sewage treatment plant obtain a permanent operational permit prior to dredging remain as a condition of the dredge and fill permit. Petitioner was informed that if it wished to pursue the matter further, the project must be reevaluated as a major modification to the dredge and fill permit. A major modification to a permit requires a new permit application and fee and is treated and processed as an initial application for a permit, with the applicant being required to provide reasonable assurances that the water quality standards will not be violated. Upon request for a minor modification, DER simply reviews the file and determines whether the request is obviously environmentally insignificant. After receipt of the letter from Mrs. Walker, petitioner supplied DER with additional water quality data. Based upon this additional data, discussions with DER staff who had been involved with the initial dredge and fill permit and the sewage treatment plant permit, and two days of sampling data collected by DER, DER determined that particular condition number seven was an integral part of the affirmative reasonable water quality assurance provided and should remain a condition of the permit. This determination was communicated to petitioner by letter dated January 7, 1981. The sewage treatment plant discharges treated effluent into a drainage ditch known as C-108. Effluent from the plant first goes into holding or retention ponds. Under its current flow, it takes about forty days for the effluent to be discharged from the plant to C-108 and the Ocean Breeze Waterway. C-108 flows into the Ocean Breeze Waterway, an artificial waterway which is presently connected to the North Fork of the St. Lucie River by a narrow, shallow meandering creek and lake system. The sewage treatment plant currently operates at 300,000 gallons per day but has an authorized capacity to operate at two million gallons per day. It currently contributes approximately two percent of the total daily flow to C-108. The Ocean Breeze Waterway and C-108, independent of the sewage treatment plant, drain approximately 4,000 square acres and produce about 35 percent of the water that will flow into the North Fork. The North Fork is tidal, with four one foot tides per day. The tidal action comprises almost 63 percent of the moving water. At a two million gallons per day discharge, the wastewater plant would be contributing about 12 percent of the water that would be going into the North Fork from the Ocean Breeze Waterway system. In comparison with two adjacent drainage systems, the Ocean Breeze system contributes only about three percent of the fresh water which flows into the North Fork. The dissolved oxygen levels of C-108 are chacteristically below the state standard of five milligrams per liter, primarily due to the seepage of ground water into the canal. Due to man-made alterations and to natural phenomena, the North Fork's dissolved oxygen levels also characteristically fall below state standards. The dissolved oxygen level of the Ocean Breeze Waterway is characteristically above state standards. Higher levels of dissolved oxygen coming from the sewage treatment plant improves the dissolved oxygen levels of the existing system. High levels of nitrogen, phosphate and chlorophyll have been found near the point of discharge. The quality of water in the North Fork is better than in the Ocean Breeze Waterway. It was the opinion of petitioner's experts that no change in dissolved oxygen levels would occur in the Ocean Breeze Waterway or the North Fork if the plug of land between these water bodies were removed. Petitioner's witnesses also opined that the Ocean Breeze/C-108 system was not a source of nutrient enrichment to the North Fork, and that the present creek system provided no water quality benefits in the form of nutrient uptake for the North Fork. It was estimated that, if the plug of land were removed pursuant to the permit, a pollutant placed at the upper end of the Ocean Breeze Waterway would be diluted by 98 percent in 26 hours in lieu of the present 39 hours due to increased flushing. These opinions were based upon analyses by petitioner's witnesses of various samplings and data regarding dissolved oxygen, nutrients and phytoplankton. The respondent's witnesses felt that the poor water quality in the Ocean Breeze Waterway was attributable in large part to the sewage treatment plant discharge and, if the plug of land were removed, the water quality problems would be moved to the North Fork and the St. Lucie River. It was felt that the present creek and lake system -- the narrow circuitous connection presently existing between the canal and the river -- reduces the nutrients which otherwise would flow into the river. These conclusions were based upon DER's own survey, a review of the dredge and fill permit file and a review of the additional data supplied by the petitioner General Development Corporation. No data regarding the water quality of the effluent from the sewage treatment plant was submitted by the petitioner at the time of DER's review of the original application for the dredge and fill permit.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the request of General Development Corporation to modify Permit Number 253.123-1031 by removing particular condition number seven be DENIED. Respectfully submitted and entered this 14th day of October, 1981, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of October, 1981. COPIES FURNISHED: Valerie Fravel Corporate Counsel General Development Corp. 1111 South Bayshore Drive Miami Florida 33131 Alfred J. Malefatto Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Honorable Victoria Tschinkel Secretary, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue The issue is whether Tampa Bay Water's award of a contract to Commerce Controls, Inc. to furnish control panel fabrications for a regional water treatment plant under Contract No. 2001-22 was contrary to competition, arbitrary, or capricious, as alleged by Petitioner.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this bid dispute, Petitioner, Universal Precision Industries, Inc. (UPI), contends that Respondent, Tampa Bay Water, acted contrary to competition and in an arbitrary and capricious manner when it proposed to award a contract to Intervenor, Commerce Controls, Inc. (CCI), the lowest responsive bidder. In its petition, UPI alleged that CCI failed to include in its bid documents "catalog cuts and information with complete model number, manufacturer's specifications, and dimension drawings describing the proposed component," as required by the specifications. As further clarified at hearing, UPI alleged that CCI deviated from the specifications in a material respect by submitting a price for a "customized-made panel" instead of a higher costing Hoffman panel (encloser), and by submitting prices for a mix of AC/DC surge protectors rather than 100 percent DC surge protectors. All other allegations in the petition have been abandoned. UPI goes on to contend that by CCI pricing out the two items in this manner, CCI gained a competitive advantage of around $36,000.00 over UPI. Tampa Bay Water is a regional water supply authority created and existing pursuant to Sections 163.01, 373.1962, and 373.1963, Florida Statutes, and an interlocal agreement among Pinellas, Pasco, and Hillsborough Counties and the Cities of Tampa, New Port Richey, and St. Petersburg known as the "Amended and Restated Interlocal Agreement Reorganizing the West Coast Regional Water Supply Authority," dated June 10, 1998. In all, Tampa Bay Water is responsible for meeting the potable water needs of approximately two million customers. The controversy began on January 8, 2001, when Tampa Bay Water issued an Invitation for Sealed Bids for Contract No. 2001-22 for the fabrication of certain control panels and associated parts for a regional water treatment plant. In paragraph 2 of the Instructions to Bidders, Tampa Bay Water specifically reserved the right "to waive any and all minor irregularities and technicalities." A mandatory pre-bid conference was held on January 23, 2001. Representatives of UPI, CCI, and Intervenor, Tampa Armature Works, Inc. (TAW), attended the conference and later submitted bids. Thereafter, the sealed bids were opened publicly on January 30, 2001. CCI submitted the lowest bid ($469,481.00), TAW the second lowest bid ($486,144.00), while UPI submitted the third lowest bid ($495,000.00). On February 5, 2001, Respondent announced its intention to award the contract to CCI, who submitted the lowest responsive bid. After efforts to informally resolve the dispute were unsuccessful, this action was filed. The bid documents The Instructions to Bidders required that "[q]uotations for services are to be provided on the Bid Schedule included herein." They further provided that "[p]roposals must be provided on the Bid Schedule included with the contract documents." The Bid Schedule form in the bid documents provided fourteen line items to be completed by the bidders: one line each for each of the seven control panels and one line each for the factory acceptance testing on each panel. The Bid Schedule also provided a pre-determined Owner's Allowance and then a "Total Contract Price" line for the fifteen line items. The Instructions to Bidders further required that "[a]ll quotations must reflect delivered cost which includes all packing, handling, shipping charges, taxes, discounts and delivery to Tampa Bay Water." In a section of the "Conditions of the Contract," the following requirements were imposed: The proposal shall include the following: Catalog cuts and information with complete model number, manufacturer's specifications, and dimension drawings describing the proposed components. Total cost to Owner of all components including a separately itemized freight cost to the project site. Per diem costs, expenses included, for supplying an experienced representative to the project site to assist with startup and operator training. Delivery time of all panels following receipt of purchase order. In the same section of the bid documents, under a heading entitled "Qualifications of Bidders," there is found a requirement that "[t]he Unit Control Panels shall be bid in detail, depicting a base unit price per device, utilizing an Excel spreadsheet supplied to the bidder." Finally, the bid documents contained seven spreadsheets, one for each of the panels, which set forth by line item a description of each component, its function, the manufacturer's name and model number, and the quantity required. The last column of each spreadsheet was blank and was titled "Costs." The purpose of a bidder submitting spreadsheets was to ensure that Tampa Bay Water was getting the specific components identified in those spreadsheets. Therefore, Tampa Bay Water wanted to ensure that the bidder was furnishing the parts specified, but it was not concerned with the manner in which a bidder may have priced any particular components. The specifications also called for a number of surge protectors for each of the seven panels. However, they did not specify whether the protectors would be AC or DC, or the number of each. Because there is a significant difference in price between the two, a few days before the bids were to be submitted, a UPI employee, Frank Dressel, made a telephonic inquiry with James L. Hall, an outside consultant who assisted in the preparation of the specifications, seeking clarification. Hall advised Dressel that he should price out his proposal using all DC surge protectors, even though the specifications were not clear on that point, and he was unsure of the exact number of DC surge devices that would ultimately be used. Hall later conveyed this same advice to all bidders before the bids were submitted. CCI's bid proposal CCI's bid proposal did not include the catalog cut sheets (product specification sheets) or the spreadsheets in its proposal. However, CCI provided a cover letter with its proposal which stated that The bid requirements asked for several items, for which there was no line on the bid form. This proposal addition serves to provide the additional information required. The equipment we are providing is the exact model as specified by Tampa Bay Water, therefore, we have not included the catalog cut sheets or major equipment listing with our bid. We can, if necessary, provide the information. Per diem expenses for an electrician for wiring field terminations to the control panels $336.00, based on an 8 hour day. Per diem expenses for a CCI start-up technician would be $900.00, based upon a 40 hour work week. Freight expenses are $7,000.00. After reading the letter, a Tampa Bay Water representative, Joseph Kehoe, "felt comfortable" with that statement and treated it as a representation by CCI that it would supply the exact parts specified by Tampa Bay Water. In an abundance of caution, however, Kehoe sought guidance from his General Counsel regarding the apparent irregularities in the CCI bid, as well as apparent irregularities in the second lowest bid submitted by TAW. The General Counsel advised that the irregularities appeared to be minor and could be waived, but that further clarification could be sought from the bidders with respect to any of the omitted information. Kehoe then sought clarification from CCI regarding the freight charges and delivery schedule. He also requested the spreadsheets and catalog cut sheets previously offered by CCI in its response. By letters dated February 2 and 5, and March 1, 2001, and a "Supplemental Information" submittal containing the spreadsheets and catalog sheets, CCI provided the necessary clarification. That information confirmed the accuracy of the representations in CCI's January 30, 2001, letter, which indicated that CCI would supply all of the required equipment at the price stated in its bid. UPI's concerns According to UPI's chief financial officer, John Sessa, CCI "did not provide pricing or part numbers to indicate that they were supplying" some of the items required by the specifications. More specifically, three of the seven panels required Hoffman enclosures. In reviewing the CCI proposal, Sessa could find no price quote for a Hoffman enclosure, but he did find a manufacturer's quote for a similar enclosure by another manufacturer, Thermal Designs and Manufacturing (TDM). Also, Sessa was unable to determine whether CCI's bid was based on all DC surge protectors. Therefore, Sessa concluded that CCI was not supplying the Hoffman enclosures or the required number of DC surge protectors. By CCI using lower costing parts in pricing out its bid, Sessa contended that CCI had obtained a competitive advantage over UPI. The prices used for CCI's bid were prepared by Karen R. Lawson, a sales engineer in CCI's Plymouth, Michigan office. Lawson gathered her estimates from catalogs and vendors and then submitted them to her supervisor, Jerry Zitterman, who in turn forwarded them to a CCI employee in St. Petersburg, Florida. Because she either gave the vendor an incorrect part number for a Hoffman panel, or there was a substantial lead time in obtaining such a unit, Lawson used a price for a customized panel made by TDM, and not the price for a Hoffman panel. That price, however, was later adjusted upward by more than 25 percent in the bid proposal, presumably to take into account the labor component. In pricing out the surge protectors, Lawson used an average unit price, which was derived by taking "both prices and [using] an average of those numbers." Notwithstanding the manner in which it had priced out the panel and surge protectors, CCI unequivocally agreed that it was obligated to supply all equipment specified by Tampa Bay Water by manufacturer and part number, and that was the intent of its January 30, 2001, letter included in its bid proposal. At the same time, Tampa Bay Water understood that CCI was supplying all of the items specified in the spreadsheets and that CCI would be held to its bid price as to all of the specified components. CCI's failure to supply the spreadsheets and catalog cut sheets at the time the bid proposal was submitted, and its manner of pricing out the required panels and surge protectors, were minor deviations from the specifications, did not give CCI a substantial advantage over other bidders, and did not adversely affect the interests of Tampa Bay Water. This is especially true here since CCI's bid proposal included a letter which indicated that CCI would provide all required equipment at the stated price. Under the terms of the Invitation for Sealed Bids, Tampa Bay Water properly waived the minor irregularities in order to achieve the purpose of securing the lowest responsible bid. UPI's bid proposal There were a number of irregularities in UPI's bid as well. For example, certain items in the spreadsheets had a dash instead of a price in the "Costs" column. UPI's bid proposal also failed to provide any information as to the per diem costs from an experienced representative to assist with start up and operator training. In addition, UPI changed the indicated quantities for each component in the spreadsheets from whatever Tampa Bay Water had specified to a quantity of one. Finally, as to two of the three different size fuses required for each of its panels, UPI's spreadsheet failed to list a price and showed a quantity of zero. A representative of Tampa Bay Water established that had UPI been the lowest bidder, the agency would have sought clarification from the bidder as to the above items in the same manner that it sought clarification from CCI. TAW's bid proposal TAW's bid also omitted the catalog cut sheets and the spreadsheets, and it failed to provide any information as to freight charges, per diem start up expenses, or delivery schedule. Clarification regarding these items would also have been required, had TAW submitted the lowest bid.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Tampa Bay Authority enter a final order awarding the contract to CCI, the lowest responsive bidder. DONE AND ENTERED this 4th day of May, 2001, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 4th day of May, 2001. COPIES FURNISHED: Donald D. Conn, General Counsel Tampa Bay Water 2535 Landmark Drive, Suite 211 Clearwater, Florida 33761-3930 Barrie S. Buenaventura, Esquire Tampa Bay Water 2535 Landmark Drive, Suite 211 Clearwater, Florida 33761-3930 Dominick J. Graziano, Esquire Bavol, Bush & Sisco, P.A. 100 South Ashley Street, Suite 2100 Tampa, Florida 33602-5311 Richard A. Harrison, Esquire Allen, Dell, Frank & Trinkle, P.A. Post Office Box 2111 Tampa, Florida 33601-2111 Steven D. Marlowe, Esquire Marlowe & McNabb, P.A. 324 South Hyde Park Avenue, Suite 210 Tampa, Florida 33606-4127 Michael M. MacInnis, Treasurer Tampa Armature Works, Inc. 440 South 78th Street Tampa, Florida 33619
Findings Of Fact Petitioner is a special taxing district providing fire protection and rescue services to the residents of the Estero area of Lee County. The fire station is located at 20241 Tamiami Trail, Estero, Florida. Petitioner employs 14 employees, including administrative staff and firefighters. The firefighters work 24 hours straight and then are off-duty for 48 hours. Two to four employees work each shift. Firefighting requires a fast response. Thus, Petitioner requires that on-duty firefighters remain at the station for their entire 24-hour shift, unless they are out fighting fires or performing rescue duties. The fire station contains an 8' x 13' bedroom with six mattresses located on three bunk beds. On-duty firefighters are allowed to bring pillows and sheets so they can sleep at the station while on duty. There are no dressers in the room, which contains small lockers that the firefighters may use to store a change of clothes. Petitioner provides kitchen facilities at the fire station and well water. The well water is used for washing equipment, taking showers, and flushing the toilet. The well water is not used for any other purposes, nor is it used by any other persons. Petitioner provides bottled water for drinking and cooking. All of the firefighters have residences apart from the fire station and within a reasonable commuting distance from the fire station. No firefighter has ever lived at the station. Petitioner does not charge, or reduce the pay of, the firefighters for their use of the limited sleeping facilities. Petitioner lawfully does not treat the use of the limited sleeping facilities by firefighters as gross income for the purposes of withholding federal income tax or making social security contributions. By letter dated July 18, 1995, Respondent informed Petitioner that the fire station's water system is a limited use community water system because the sleeping facilities constituted rental residences, as defined by Rule 10D- 4.024(21), Florida Administrative Code. Respondent advised Petitioner that it was therefore required to obtain a permit. As noted in the following section, the statute authorizes Respondent to regulate as limited use community public water systems those systems serving a certain number of "rental residences." The statute does not define "rental residence." In Rule 10D-4.024(21), Respondent defines a "rental residence" as follows: a dwelling unit, a structure or part of a structure that is rented for use, or furnished with or without rent as an incident of employ- ment, for use as a home, residence, sleeping place by one or more persons, a mobile home rented by a tenant. This term does not apply to facilities offering transient residency such as public lodging establishments. This term includes other facilities where residency or detention is incidental to the provision of medical, geriatric, educational, counseling, religious, or similar services. Respondent equated a "rental residence" with a "dwelling unit" when it based its definition of "rental residence" on the statutory definition of "dwelling unit" in Chapter 83, Part II, Florida Statutes, which is the Florida Residential Landlord and Tenant Act. A "dwelling unit" is a "residence." The American Heritage dictionary defines a "dwelling" as "a place to live in; residence; abode." Similarly, the same dictionary's first definition of "residence" is "the place in which one lives; a dwelling; an abode." But the statutory definition qualifies "residential" with "rental." The word "rental" requires consideration of the nature of the relationship of the occupant to the dwelling and its owner. Obviously, the Florida Residential Landlord and Tenant Act addresses rental transactions, but it does not do so in the definition of "dwelling unit." Other provisions of the Act describe the kind of activity that must take place for a person to be considered a tenant renting a dwelling unit. Most importantly, Section 83.43(6) defines "rent" as "periodic payments due the landlord from the tenant for occupancy under a rental agreement " The facts of this case present a revealing illustration of the distinction between a "residence" or "dwelling unit," on the one hand, and a "rental residence," on the other hand. There is no rental relationship between the occupants of the sleeping quarters at the fire station and the residence or dwelling itself. The firefighters do not pay, directly or indirectly, for these beds or the rooms in which the beds are located. Their employer legitimately does not include the value of the use of these sleeping quarters in the compensation paid to the firefighters. The firefighters have residences within commuting distance of the fire station and use the meager sleeping quarters and kitchen facilities only because they are required to spend long hours continuously at the fire station.
Findings Of Fact The Concerned Citizens of West Escambia County, Florida, is an unincorporated neighborhood association begun in the Spring of 1978. It has been concerned with local sewage and flood water problems. Many of the Citizens' members live in the LiFair subdivision abutting the Fairfield Village project on the south. FFV is a 72-unit low income federally subsidized housing project planned for development on a 7.47 acre site. The site is located on the west side of Fairfield Drive between Jackson Street and the Lillian Highway (U.S. 98) in Escambia County. On February 1, 1980, DER issued permit number CS17-25848 for the construction of a dry sewage collection system to serve Fairfield Village. That permit contained conditions 15, 16 and 17 which state: This permit does not authorize the connection of this collection to the Avondale STP. Separate authorization for the actual connection of this col- lection system to the Avondale STP is required from this department. Such authorization shall be applied for by separate letter to the Department. This permit shall not be construed to infer any assurance that the necessary authorization for connection shall be granted. Any such authorization shall be granted only when adequate treatment in accordance with rules, regulations, and issued permits of the Department is available for any flows transported by by the collection system. The system shall be inspected for any sediment debris and flushed prior to connection to the Escambia County sewer system. Subsequently on March 20, 1980, Paul F. McCartney on behalf of FFV requested that the above conditions be lifted as the moratorium on new connections to the ATP had been lifted. On January 1, 1980, C. H. Wigley, Jr., Director of Utilities for Escambia County gave notice that the two-year moratorium on new sewer taps into the ATP was lifted. This action was the result of a planned diversion of approximately 300,000 gallons per day (GPD) from the ATP to the Warrington Treatment Plant. DER on April 1, 1980, gave notice of its intent to remove conditions 15, 16 and 17 from FFV's permit. Petitioner on April 9, 1980, filed its petition for an administrative hearing on DER's proposed action. The anticipated waste water discharge from FFV is approximately 22,000 GPD. As a result of the 300,000 GPD diversion from the ATP to the Warrington Plant, there is more than adequate treatment capacity at the ATP for handling the FFV inflow. The ATP operates under DER permit number TP17-2080 issued on April 4, 1978 and has operated within its designed capabilities of 1,000,000 GPD since August, 1979. There is no showing that a connection of the FFV transmission line to the ATP will cause any violation of the plant's permit conditions. Evidence was presented by Petitioners that sewage lines in the Citizen's neighborhood frequently overflow. There was no showing however that any instance of overflow was caused by the ATP exceeding its operating capacity. It is more likely that their neighborhood sewage problems result from blockages in the transmission lines or result from pump-outages at the lift station between their neighborhood and the treatment plant. No showing was made that the connection of FFV to the ATP would adversely affect sewage collection in the LiFair subdivision. The monthly operating reports submitted to DER by the ATP were shown to be accurate. DER may reasonably rely on them in determining whether the requested permit modifications should be granted.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Environmental Regulation enter a final order authorizing the modification of permit number CS17-25848 by eliminating conditions 15, 16 and 17. It is further RECOMMENDED that the Petition of the Concerned Citizens of West Escambia County, Florida, be dismissed. DONE AND ORDERED in Tallahassee, Leon County, Florida, this day of 18th of December, 1980. MICHAEL PEARCE DODSON Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of December, 1980. COPIES FURNISHED: Artice L. McGraw, Esq. CETTI & McGRAW 26 East Garden Street Pensacola, FL 32501 P. Michael Patterson, Esq. 26 East Garden Street Pensacola, FL 32501 William W. Deane, Esq. Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32301 Alan C. Sheppard, Esq. EMMANUEL SHEPPARD & CONDON Seventh Floor, Century Bank Tower Post Office Drawer 1271 Pensacola, FL 32596