Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
DUBOIS FARMS, INC. vs VEG SERVICE, INC., AND WESTERN SURETY COMPANY, 00-001746 (2000)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 25, 2000 Number: 00-001746 Latest Update: Oct. 04, 2024
# 1
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs JOSE FERNANDO ARISTIZABAL AND LILIANA URREA ARISTIZABAL, 07-003207 (2007)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Jul. 16, 2007 Number: 07-003207 Latest Update: Oct. 03, 2008

The Issue The issues in this case include: whether the Respondents constructed berms and ponds and dug ditches and filled wetlands on their Property in Highlands County without required permits, as alleged by the Southwest Florida Water Management District (SWFWMD) in its Administrative Complaint; and, if so, whether the Respondents are entitled to an agricultural exemption or an agricultural closed system exemption under Section 373.406(2)- (3), Florida Statutes.

Findings Of Fact Respondents' Activities on the Property In August 2003, the Respondents, José Fernando and Liliana Urrea Aristizabal, bought approximately 30 acres of land in Highlands County, near Lake Placid, south of Miller Road, to use for a palm tree nursery. This land (the Property) is in Section 30, Township 36 South, Range 29 East. There was a large marsh approximately in the center of the Property with additional wetlands surrounding the large marsh. On December 31, 2003, and again in February 2004, representatives of SWFWMD informed Mr. Aristizabal that, due to the presence of relatively high-quality wetlands on the Property, the plant nursery he intended to establish there would require an application for an environmental resource permit (ERP). After receiving this information from SWFWMD, Mr. Aristizabal retained a consultant to advise him. The consultant advised Mr. Aristizabal on how to construct an irrigation system that would be effective and permittable; however, the consultant cautioned him that construction would have to avoid impacting the wetlands on the Property. The consultant also advised Mr. Aristizabal as to the location of the wetlands on the Property, as well as the location of "potential wetlands." In response to the consultant's advice, Mr. Aristizabal dug a circular ditch around the large marsh in the center of the Property, with additional linear ditches radiating from the central, circular ditch and intersecting with a second, larger ditch around most of the perimeter of the irrigation system, extending along the east, north, and west sides of the Property. The ditches are approximately 5-7 feet wide and 5-7 feet deep. The soil from the ditches was spread between the linear ditches to raise the ground level and create planting beds. Mr. Aristizabal also deposited fill to the north and east of the perimeter ditch to create a berm approximately 4-6 feet wide and 2-4 feet high. Effects on Surface Waters of the State The evidence proved that there were approximately 11.64 acres of wetlands on the Property, including the large central marsh. Most of the ditches dug by Mr. Aristizabal and most of the fill deposited by him between the ditches were in wetlands. In all, approximately 0.86 acres of the wetlands on the Property were dredged, and approximately 4.97 acres of the wetlands on the Property were filled. The ditches intercept, divert, and impound surface water. The berms--particularly, the berm on the north side of the Property--also obstruct the flow of surface water. Agricultural Exemption Defense The Respondents did not apply for an agricultural exemption under Section 373.406(2), Florida Statutes, from the requirement to obtain an ERP. Instead, they raised the exemption as a defense to SWFWMD's enforcement action. Regarding the agricultural exemption defense, Mr. Aristizabal's berms and his ditching and filling of wetlands impounded, impeded, and diverted the flow of surface waters. These effects more than incidentally trapped or diverted some surface waters, e.g., as occurs when a pasture is plowed. For that reason, the activities were not consistent with the practice of agriculture. Even if those activities might be considered to be consistent with the practice of agriculture, they had the predominant purpose of impounding or obstructing surface waters. The berms and the ditching and filling of wetlands obstructed surface waters in that they had the effect of more-than- incidentally diverting surface water from its natural flow patterns. The ditches also impounded surface waters. SWFWMD reasonably determined that the predominant purpose of the berms and the ditching and filling of wetlands was to impound, impede, divert, and obstruct the flow of surface waters. Agricultural Closed System Exemption Defense The Respondents did not apply for an agricultural closed system exemption under Section 373.406(3), Florida Statutes. Instead, they raised the exemption as a defense to SWFWMD's enforcement action. The Respondents did not prove that their construction resulted in an "agricultural closed system." Rather, the evidence was that surface waters of the state are discharged from, and onto, the Property during most years. Requested Corrective Action SWFWMD seeks alternative corrective action by the Respondents: expeditiously apply for and obtain an after-the- fact permit; or expeditiously submit and perform an acceptable plan to restore the land to its natural grade and to remediate as necessary to restore any loss of wetland functions. The specifics of the requested alternative corrective action are set out in paragraphs 19 and 20 of the Administrative Complaint. The requested alternative corrective actions are reasonable.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Governing Board enter a Final Order requiring the Respondents to apply for the necessary after- the-fact permit and/or restore wetland impacts, as described in Finding 12, supra. DONE AND ENTERED this 21st day of August, 2008, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of August, 2008. COPIES FURNISHED: David L. Moore, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899 José Fernando Aristizabal Liliana Urrea Aristizabal 6650 Southwest 189th Way Southwest Ranches, Florida 33332 Joseph J. Ward, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604

Florida Laws (6) 120.569120.57373.403373.406373.616403.927 Florida Administrative Code (2) 40D-4.02140D-4.041
# 2
A. DUDA AND SONS, INC. vs ST. AMOUR SOD SERVICES, INC., D/B/A LANDSCAPE SERVICES AND AETNA CASUALTY AND SURETY COMPANY, 91-006388 (1991)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Oct. 07, 1991 Number: 91-006388 Latest Update: May 12, 1992

Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received at the hearing, the following findings of fact are made: In January, 1990, the Respondent filed an application for credit with the Petitioner. The terms and conditions of the credit application provided: "All written 'Terms and Conditions of Sale' on invoices, statements, contracts or other written agreements must be observed and performed as stated." Further, the application provided: Payment of all amounts due shall be made not later than 30 days from the billing date. Amounts in default will be subject to a SERVICE CHARGE of 1 1/2 % per month (18 % Per Annum) on the unpaid balance. Failure to make payment within terms will result in cancellation of credit. Following acceptance of that application, Respondent sought to purchase sod from Petitioner's LaBelle sod farm. Invoices issued by Petitioner to Respondent at the time of the delivery of the sod provided that the amounts owed would be payable upon receipt of invoice. Further, the printed invoice required the purchaser to make claims within 24 hours of delivery or pick up. The invoices reiterated the 18 percent service charge for past due accounts. From December, 1990, through January 17, 1991, Respondent purchased and accepted in excess of $45,000 worth of sod from the Petitioner. The invoices for those purchases are identified in this record as Petitioner's exhibit 2. From January 30, 1991 until March 4, 1991, Respondent purchased and accepted $4,664.00 worth of sod from the Petitioner. The invoices for those purchases are identified in the record as Petitioner's exhibit 3. In February, 1991, when the Petitioner became concerned about nonpayment for the amounts claimed, contact with the Respondent was made for the purpose of resolving the matter. When those efforts failed to secure payment, the Petitioner instituted action through the Department of Agriculture against the Respondent's bond. The Petitioner claimed $45,080.25 was due for the invoices prior to January 30, 1991. The Petitioner claimed $4,664.00 was owed for the invoices subsequent to January 30, 1991. Subsequent to its claims, Petitioner received payments from the Respondent in the following amounts: $5,000.00 on March 11, 1991; $5,000 on March 26, 1991; and $2,000.00 on April 30, 1991. Applying the total of those payments ($12,000) to the indebtedness on the first claim reduces that amount to $33,080.25. Prior to the claims being filed, Respondent had notified Petitioner that some sod deliveries had been unacceptable because of the quality of the sod or the amount. Respondent claimed the Petitioner had "shorted" the square footage amounts per pallet so that Respondent was being charged for a pallet that did not contain the requisite square footage of sod. On one occasion, in January, 1991, the Petitioner gave Respondent a credit in the amount of $1,173.75 for either refund on poor quality sod or a shortage. The Respondent continued to purchase sod from Petitioner until its credit was no longer accepted by Petitioner, i.e. March 4, 1991. Respondent did not, within 24 hours of receipt of sod, make a claim regarding the quality of the sod or the amount. By letter dated March 14, 1991, the Respondent, through its attorney, advised Petitioner as follows: St. Amour Sod Services, Inc., does not dispute the balance due to you as set forth in your letter and they will pay same in payments that are being determined now. For your information, the balance accrued because of the loss of several of our customers resulting from the poor quality of sod purchased from your firm. Respondent did not timely challenge the quality of the sod accepted, and did not present evidence regarding its alleged poor quality.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Department of Agriculture and Consumer Services enter a final order finding that Respondent is indebted to Petitioner in the amounts of $33,080.25 and $4,664.00, with service charge to be computed through the date of the final order; directing Respondent to make payment of the amounts to Petitioner within 15 days following the issuance of the order; and, notifying all parties that if such payment is not timely made, the Department will seek recovery from Respondent's surety, Aetna Casualty and Surety Company. DONE and ENTERED this 13th day of March, 1992, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of March, 1992. APPENDIX TO CASE NOS. 91-6388A AND 91-6389A RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY PETITIONER: 1. Paragraphs 1 through 4 are accepted. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY RESPONDENT: Paragraph 1 is accepted. Paragraphs 2, 3, 4, 6, 7, and 8 are rejected as contrary to the weight of the credible evidence or unsupported by the record in this case. With regard to paragraph 5, that portion of the paragraph which states the amount of payments made by Respondent ($12,000) is accepted. Otherwise, rejected as stated in 2. above. COPIES FURNISHED: Barry L. Miller P.O. Box 1966 Orlando, FL 32802 Gary A. Ralph 2272 Airport Rd. South, Ste. 101 Naples, FL 33962 Hon. Bob Crawford Commissioner of Agriculture The Capitol, PL-10 Tallahassee, FL 32399-0810 Richard Tritschler General Counsel Dept. of Agriculture & Consumer Svcs. The Capitol, PL-10 Tallahassee, FL 32399-0810 Aetna Casualty & Surety Company Attn: Legal Dept. 151 Farmington Ave. Hartford, CT 06156

Florida Laws (1) 604.15
# 3
DEPARTMENT OF INSURANCE vs TRINI LOVOSIER THOMAS, 00-000018 (2000)
Division of Administrative Hearings, Florida Filed:Tavares, Florida Jan. 05, 2000 Number: 00-000018 Latest Update: Oct. 04, 2024
# 4
BOBBY, SR, AND BOBBY, vs. GROWERS MARKETING SERVICES, INC., AND COMMERCIAL UNION INSURANCE COMPANY, 85-002824 (1985)
Division of Administrative Hearings, Florida Number: 85-002824 Latest Update: Jun. 16, 1986

Findings Of Fact Upon consideration of the oral testimony and documentary evidence adduced at the hearing, the following relevant facts are found: At all times pertinent to this proceeding, Petitioners were producers of agricultural products in the State of Florida as defined in Section 604.15(5), Florida Statutes (1983). At all times pertinent to this proceeding, Respondent GMS was a licensed dealer in agricultural products as defined by Section 604.15(1), Florida Statutes (1983), issued license no. 936 by the Department and bonded by Commercial Union Insurance Company (Commercial) in the sum of $50,000.00 - Bond No. CZ 7117346. At all times pertinent to this proceeding, Respondent Commercial was authorized to do business in the State of Florida. The complaint filed by Petitioner was timely filed in accordance with Section 604.21(1), Florida Statutes (1983). Prior to Petitioners selling or delivering any watermelons (melons) to Respondent GMS, Petitioners and Respondent GMS entered into a verbal contract whereby: (a) Petitioners would harvest and load their melons on trucks furnished by Respondent GMS at Petitioners' farm; (b) the loading, grading and inspection, if any, was to be supervised by, and the responsibility of Respondent GMS or its agent; (c) the melons were to be U.S. No. 1 grade; (d) the melons were purchased F.O.B. Petitioner's farm subject to acceptance by Respondent GMS, with title and risk of loss passing to Respondent GMS at point of shipment (See Transcript Page 95 lines 5-7); (e) the price was left open subject to Petitioners being paid the market price for the melons at place of shipment on the day of shipment as determined by Respondent GMS less one (1) or two (2) cent sales charge, depending on the price; and requiring Respondent GMS to notify Petitioners on a daily basis of that price and; (f) the settlement was to be made by Respondent GMS within a reasonable time after the sale of the melons by Respondent GMS. Respondent GMS was not acting as Petitioners agent in the sale of the melons for the account of the Petitioners on a net return basis nor was it acting as a negotiating broker between the Petitioners and the buyers. Respondent GMS did not make the type of accounting to Petitioners as required by Section 604.22, Florida Statutes had it been their agent. Although Respondent GMS purchased over twenty (20) loads of melons from the Petitioners, there are only ten (10) loads of melons in dispute and they are represented by track report numbers 536 dated April 29, 1985, 534 dated April 30, 1985, 2363 and 537, dated May 1, 1985, 2379, 2386 and 538 dated May 2, 1985, and 2385, 2412 and 2387 dated May 3, 1985. Jennings W. Starling (Starling) was the agent of Respondent GMS responsible for loading; grading- inspecting and accepting and approving the loads of melons for shipment that Respondent GMS was purchasing from Petitioners during the 1985 melon season. Petitioners and Starling were both aware that some of the melons had hollow hearth a conditions if known, would cause the melons to be rejected. Aware of this condition in the melons, Starling allowed Petitioners to load the melons on the truck furnished by Respondent GMS. Starling rejected from 20 percent to 40 percent of the melons harvested and brought in from Petitioners' fields before accepting and approving a load for shipment. Starling accepted and approved for shipment all ten (10) of the disputed loads of melons. On a daily basis, Robert E. McDaniel, Sr., one of the Petitioners, would contact the office of Respondent GMS in Lakeland Florida to obtain the price being paid that day by Respondent GMS to Petitioners but was not always successful, however, he would within a day or two obtain the price for a particular day. Robert E. McDaniel did obtain the price to be paid by Respondent GMS for the ten (10) disputed loads and informed his son Robert E. McDaniel, Jr. of those prices. The prices quoted to Robert E. McDaniel, Sr. by Respondent GMS on the ten (10) disputed loads were 12 cents, 10 cents, 8 cents, 8 cents, 8 cents, 8 cents, 8 cents, 7 cents, 7 cents, and 7 cents on tract reports number 536, 534, 2363, 537, 2379, 2386, 538, 2385, 2412 and 2387, respectively. No written record of their prices was produced at the hearing but the testimony of Robert E. McDaniel Sr. concerning these prices was the most credible evidence presented. After the melons were shipped, sometimes as much as one week after, a track report was given to Robert E. McDaniel Jr. by Starling for initialing. Sometimes a price would be indicated on the track report but this price was based on selling price at point of destination and not the market price at point of shipment. Also, the letters "H.H." would also appear on the track report which, according to the testimony of Starling, indicated hollow heart but the evidence was insufficient to prove that Starling had rejected these loads for shipment because of a hollow heart condition in the melons. The loads in question were paid for by Respondent GMS based on a price at point of destination under its drafts no. 831912 and 851311. The amount in dispute is as follows: DATE TRACK NET AMOUNT AMOUNT SHIPPED

Recommendation Based upon the Findings of Fact and Conclusions of Law recited herein, it is RECOMMENDED that Respondent GMS be ordered to pay to the Petitioners the sum of $11.212.31. It is further RECOMMENDED that if Respondent GMS fails to timely pay the Petitioners as ordered, then Respondent Commercial be ordered to pay the Department as required by Section 604.21, Florida Statutes (1983) and that the Department reimburse the Petitioners in accordance with Section 604.21, Florida Statutes (1983). Respectfully submitted and entered this 13th day of June, 1986, in Tallahassee, Leon County, Florida. Hearings Hearings WILLIAM R. CAVE Hearing Officer Division of Administrative The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative this 13th day of June, 1986.

Florida Laws (6) 120.68604.15604.17604.20604.21604.22
# 5
DEPARTMENT OF FINANCIAL SERVICES vs DANIEL P. ZUTLER, 03-004849PL (2003)
Division of Administrative Hearings, Florida Filed:Lakeland, Florida Dec. 24, 2003 Number: 03-004849PL Latest Update: Oct. 04, 2024
# 6
DEPARTMENT OF FINANCIAL SERVICES vs CREDIT GUARD OF FLORIDA, INC., 07-004799 (2007)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Oct. 22, 2007 Number: 07-004799 Latest Update: Oct. 04, 2024
# 7
MIKE ROSE vs SOUTH FLORIDA GROWERS ASSOCIATION, INC., AND AETNA CASUALTY AND SURETY COMPANY, 96-005654 (1996)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 02, 1996 Number: 96-005654 Latest Update: Jun. 26, 1997

The Issue Whether the respondent is indebted to the complainant for the sale of Florida-grown agricultural products, and, if so, the amount of the indebtedness.

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: Mr. Rose has a grove of lychee trees on his property; each year he harvests the lychee nuts for sale, but the sale of agricultural products is not his sole source of income. In mid-June, 1996, Mr. Rose heard that the Growers Association was offering $3.50 per pound for lychees, the highest price of which he was aware. Mr. Rose took his fruit to the Growers Association on June 18, 1996. Mr. Rose had not done business with the Growers Association previously but had sold his fruit to another company. Mr. Rose received a grower's receipt showing that, on June 18, 1996, he had brought in 298 pounds of fruit, that 14 pounds were culls, and that the Growers Association had packed 27.9 ten- pound boxes of fruit. The Growers Association packed only marketable fruit. Ninety-nine percent of the tropical fruit grown in Florida is handled in pools.1 According to industry practice, the "handler" does not purchase the fruit outright but is responsible for packing, storing, selling, and shipping the fruit and for accounting for and remitting the proceeds of sale, minus expenses, to the members of the pool on a pro rata basis. The pools are composed of all growers whose fruit is packed during a designated period of time. Prices initially quoted to growers participating in a pooling arrangement are not guaranteed because the actual sales price may vary, depending on market conditions. It was the practice of the Growers Association to handle lychees under a pooling arrangement, and the receipt Mr. Rose received from the Growers Association contained the notation "P- 407LY," which designated the pool to which Mr. Rose's fruit was assigned. The Lychee P-407LY pool to which Mr. Rose's fruit was assigned consisted of fruit packed by the Growers Association between June 15 and 21, 1996. Mr. Rose was told on several occasions by employees of the Growers Association that he would receive $920.70 after expenses for the sale of his lychees. This amount was reflected in a Pool Price Report generated by the Growers Association on July 10, 1997, which also showed that a total of 107.6 pounds of fruit was included in the pool and that the Growers Association anticipated receiving a total of $4,088.65 for the sale of the fruit in the pool. The Growers Association maintained in its files a work order showing that 83 ten-pound boxes of lychees were sold to Produce Services of America, Inc., at a price of $38.00 per box and that the fruit was shipped on June 21, 1996. According to the July 10 report, the Growers Association had received payment of $932.90 for 24.55 ten-pound boxes of lychees sold to "L & V" on June 21, 1996, at $38.00 per box, but there is no indication in the report that the anticipated payment of $3,154.00 had been received from Produce Services of America. Mr. Rose repeatedly called the Growers Association during July and August to inquire about when he would receive payment for his fruit. In accordance with the information he had consistently been given by employees of the Growers Association, he expected to receive $920.70. When he received a check from the Growers Association dated August 29, 1996, in the amount of $367.48, he called the Growers Association for an explanation of why he had received that amount rather than the $920.70 he was expecting. Ultimately, he spoke with Mr. Kendall in early September, who told him that the $367.48 was all he was going to receive as his pro rata share of the pool because Produce Services of American had not paid in full for the 83 boxes of fruit it purchased. As reflected in the Pool Price Report dated September 19, 1996, the Growers Association received a total payment of only $1,847.42 for the fruit in the pool, rather than the $4,088.65 shown in the July 10, 1996, report. After the Growers Association's expenses were deducted, a total of $1,417.25 was distributed to the five growers in the pool. Although a copy of this final price report for the P-407LY pool should have accompanied Mr. Rose’s check, it did not. According to the information contained in the September 19 Pool Price Report, the shortfall in the amount received for the sale of the fruit in the pool is attributable to the Growers Association's receiving only $913.00, or $11.00 per box, for the sale of the 83 boxes of lychees to Produce Services of America, instead of the anticipated $3,154.00. The $913.00 was paid to the Growers Association by check dated August 19, 1996. Mr. Rose did not present sufficient evidence to establish that he had a contract for the outright sale of 27.9 ten-pound boxes of lychees to the Growers Association. Rather, the evidence establishes that Mr. Rose's fruit was handled by the Growers Association under a pooling arrangement and that, consistent with the practice in the tropical fruit industry, the Growers Association assumed responsibility for packing, storing, selling, and shipping the fruit. The Growers Association failed to offer any credible evidence to explain why Produce Services of America paid only $11.00 per box for the 83 boxes of fruit shipped from the pool, notwithstanding that the agreed sales price was $38.00 per box.2 Even if the fruit was damaged or in poor condition when it was delivered to Produce Services of America, the Growers Association packed 27.9 ten-pound boxes of marketable fruit on Mr. Rose’s account, and, once packed, it had complete control of the fruit in the pool. The Growers Association failed to offer any evidence to establish that it acted with reasonable care in fulfilling its responsibilities under the pool arrangement. Consequently, it bears the risk of loss rather than Mr. Rose and is indebted to him for $553.22, which is the difference between the $920.70 Mr. Rose would have received as his pro rata share of the pool had Produce Services of America paid the agreed-upon sales price of $38.00 per box and the $367.48 which the Growers Association paid to Mr. Rose by check dated August 29, 1996.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Agriculture and Consumer Services enter a Final Order finding that the South Florida Growers Association, Inc., is indebted to Mike Rose for the sale of agricultural products and ordering the South Florida Growers Association, Inc., to pay Mike Rose $553.22 within fifteen (15) days of the date its order becomes final. The Final Order should also provide that, in the event that the South Florida Growers Association, Inc., fails to pay Mike Rose $533.22 within the time specified, Aetna Casualty and Surety Company, as surety for the South Florida Growers Association, Inc., must provide payment under the conditions and provisions of its bond. DONE AND ENTERED this 10th day of April, 1997, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of April, 1997.

Florida Laws (6) 120.57603.161604.15604.16604.20604.21
# 8
C. M. PAYNE AND SON, INC. vs GARRISON IRRIGATION, INC., AND CONTINENTAL CASUALTY COMPANY, AS SURETY, 04-003191 (2004)
Division of Administrative Hearings, Florida Filed:Mango, Florida Sep. 09, 2004 Number: 04-003191 Latest Update: Feb. 23, 2005

The Issue Whether Respondent, Garrison Irrigation, Inc., failed to pay amounts owing to Petitioner resulting from a verbal contract for four pallets of Bahia sod as set forth in the complaint dated July 20, 2004, and, if so, what amount Petitioner is entitled to recover.

Findings Of Fact Based upon observation of the witness and her demeanor while testifying, the documents received into evidence, and the entire record of this proceeding, the following relevant and material findings of fact are determined: At all times material to this proceeding, Petitioner, C.M. Payne and Son, Inc., was a producer of agricultural products as that term is defined in Subsection 604.15(5), Florida Statutes (2004). At all times material to this proceeding, Respondent, Garrison Irrigation, Inc. (Garrison), was licensed as a dealer in agriculture products as that term is defined in Subsection 604.15(1), Florida Statutes (2004). Respondent was licensed under number 13653, supported by Bond No. 929237754 in the amount of $10,000; written by Respondent, Continental Casualty Company, as Surety (Continental); Inception Date: December 4, 2003; Expiration Date: December 3, 2004; and Execution Date: December 4, 2003. At all times material, Continental is the surety which issued Garrison a surety bond. On January 23, 2004, Petitioner sold 16 pallets of Bahia sod to Garrison and, on Invoice 20027, billed Garrison a total of $599.20 for the 16 pallets of sod. On January 26, 2004, Petitioner sold 32 pallets of Bahia sod to Garrison and, on Invoice 20033, billed Garrison a total of $1,198.40 for the 32 pallets of sod. On January 27, 2004, Petitioner sold 16 pallets of Bahia sod to Garrison and, on Invoice 20039, billed Garrison a total of $599.20 for the 16 pallets of sod. On February 2, 2004, Petitioner sold 16 pallets of Bahia sod to Garrison and, on Invoice 20044, billed Garrison a total of $599.20 for the 16 pallets of sod. The terms of the sale between Petitioner and Garrison were for net payment for products sold within 30 days after the invoice date. Garrison did not appear at the hearing to contest or otherwise refute the charges alleged in Petitioner's complaint. Garrison is indebted to Petitioner in the amount of $2,996.00 for Bahia sod purchases from Petitioner on January 23, 26, and 27, 2004, and February 2, 2004. Garrison has failed to pay Petitioner for the sod purchases.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department issue its final order requiring that Respondent, Garrison Irrigation, Inc., pay to Petitioner, C. M. Payne and Son, Inc., the amount of $2,996.00 for the purchases of Bahia sod from Petitioner on January 23, 26, and 27, 2004, and February 2, 2004. It is further RECOMMENDED that if Respondent, Garrison Irrigation, Inc., fails to comply with the order directing payment, the Department shall call upon the surety, Continental Casualty Company, to pay over to the Department from funds out of the surety certificate, the amount needed to satisfy the indebtedness. DONE AND ENTERED this 22nd day of December, 2004, in Tallahassee, Leon County, Florida. S FRED L. BUCKINE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2004.

Florida Laws (5) 120.569120.57198.40604.15604.20
# 9
FLORIDA WILDLIFE FEDERATION vs CRP/HLV HIGHLANDS RANCH, LLC AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 12-003219 (2012)
Division of Administrative Hearings, Florida Filed:Jacksonville, Florida Sep. 26, 2012 Number: 12-003219 Latest Update: Jun. 14, 2013

The Issue Whether the Florida Department of Environmental Protection‘s (Department) notice of intent to issue an environmental resource/mitigation bank permit, and notice of intent to grant a variance waiving the financial responsibility requirements for the construction and implementation activities of the mitigation bank to Respondent, CRP/HLV Highlands Ranch, LLC (Highlands Ranch) should be approved, and under what conditions.

Findings Of Fact The Parties Petitioner is a Florida not-for-profit corporation in good-standing, originally incorporated in 1946, with its corporate offices currently located at 2545 Blairstone Pines Drive, Tallahassee, Florida. Petitioner‘s corporate purposes include, among others, ?the cause of natural resource conservation and environmental protection, to perpetuate and conserve the fish, wildlife, mineral, soil, water, clean air and natural resources of Florida.? The Department is an agency of the State of Florida having concurrent jurisdiction with the state‘s water management districts for permitting mitigation banks pursuant to chapter 373, Part IV, Florida Statutes. Highlands Ranch is a Delaware limited-liability corporation registered with the State to do business in Florida, with its corporate offices located at 9803 Old St. Augustine Road, Suite 1, Jacksonville, Florida. Highlands Ranch was the applicant for the SJRWMD Permit, and is the applicant for the DEP Permit and Variance that are at issue in this proceeding. The Property The property designated to become the HRMB (the Property) comprises approximately 1,575 acres, which includes 551.99 acres of wetlands, 990.90 acres of uplands, and 32.60 acres of miscellaneous holdings, including easements and a hunt camp. The Property is bounded by the Jennings State Forest on the eastern boundary, the conservation lands of Camp Blanding Joint Training Center on the southern boundary, and a titanium mine on the western boundary. The upland communities consist of mesic and xeric pine plantations. The wetland communities consist of 260.30 acres of hydric pine flatwoods, 80.26 acres of bay and bottomland, and 211.43 acres of floodplain. The wetland areas of the HRMB are generally associated with two creeks that traverse the property, Boggy Branch on the northern portion of the property, and Tiger Branch, which is a series of streams and branches in the southeastern and eastern portion of the property. Boggy Branch and Tiger Branch feed into the north fork of Flat Creek, some of which encroaches onto the eastern side of the property. In addition to Boggy Branch and Tiger Branch and their tributaries, there are isolated wetlands scattered throughout the HRMB property. Most of the uplands, and much of the wetlands have been altered from their native plant communities by historic and on- going silvicultural activities. The uplands currently consist largely of pine plantation planted in slash pine of various ages and densities, with one small area planted in longleaf pine. The property has an elevation gradient of approximately 90 feet, which extends generally from the higher xeric pine flatwoods, sloping down to the creek systems. A gradient of 90 feet over an area as small as the HRMB is a significant elevation change in Florida. Mitigation Banks A mitigation bank is ?a project permitted under 373.4136 undertaken to provide for the withdrawal of mitigation credits to offset adverse impacts authorized? by an Environmental Resource Permit (ERP) issued under Part IV, chapter 373, Florida Statutes. § 373.403(19), Fla. Stat. A mitigation bank permit is a type of ERP. The Department and the water management districts are legislatively authorized to require permits to establish and use mitigation banks. § 373.4136(1), Fla. Stat. Mitigation banks act as repositories for wetland mitigation credits that can be used to offset adverse impacts to wetlands that occur as the result of off-site ERP projects. Mitigation banks are intended to ?emphasize the restoration and enhancement of degraded ecosystems and the preservation of uplands and wetlands as intact ecosystems rather than alteration of landscapes to create wetlands. This is best accomplished through restoration of ecological communities that were historically present.? They are designed to ?enhance the certainty of mitigation and provide ecological value due to the improved likelihood of environmental success associated with their proper construction, maintenance, and management,? often within larger, contiguous, and intact ecosystems. § 373.4135(1), Fla. Stat. A mitigation credit is a "standard unit of measure which represents the increase in ecological value resulting from restoration, enhancement, preservation, or creation activities." Fla. Admin. Code R. 62-345.200(8). Ecological value is defined as the value of functions performed by uplands, wetlands, and other surface waters to the abundance, diversity, and habitats of fish, wildlife, and listed species. Included are functions such as providing cover and refuge; breeding, nesting, denning, and nursery areas; corridors for wildlife movement; food chain support; natural water storage, natural flow attenuation, and water quality improvement which enhances fish, wildlife, and listed species utilization. Fla. Admin. Code R. 62-345.200(3). When an ERP permit requires wetland mitigation to offset adverse impacts to wetlands, the permittee may purchase wetland credits from a mitigation bank and apply them to meet the mitigation requirements. When the permittee has completed the agreement with the mitigation bank and paid for the credits, those mitigation credits are debited from the mitigation bank's ledger. Every mitigation bank has a ledger that reflects how many credits have been released for use, and how many have been sold for use as mitigation. Uniform Mitigation Assessment Method Rule A mitigation bank is to be awarded mitigation credits ?based upon the degree of improvement in ecological value expected to result from the establishment and operation of the mitigation bank as determined using a functional assessment methodology.? § 373.4136(4), Fla. Stat. Section 373.414(18), Florida Statutes, provides, in pertinent part, that: The department and each water management district responsible for implementation of the environmental resource permitting program shall develop a uniform mitigation assessment method for wetlands and other surface waters. The department shall adopt the uniform mitigation assessment method by rule no later than July 31, 2002. The rule shall provide an exclusive and consistent process for determining the amount of mitigation required to offset impacts to wetlands and other surface waters, and, once effective, shall supersede all rules, ordinances, and variance procedures from ordinances that determine the amount of mitigation needed to offset such impacts. Once the department adopts the uniform mitigation assessment method by rule, the uniform mitigation assessment method shall be binding on the department, the water management districts, local governments, and any other governmental agencies and shall be the sole means to determine the amount of mitigation needed to offset adverse impacts to wetlands and other surface waters and to award and deduct mitigation bank credits . . . . It shall be recognized that any such method shall require the application of reasonable scientific judgment. The uniform mitigation assessment method must determine the value of functions provided by wetlands and other surface waters considering the current conditions of these areas, utilization by fish and wildlife, location, uniqueness, and hydrologic connection, and, when applied to mitigation banks, the factors listed in s. 373.4136(4). The uniform mitigation assessment method shall also account for the expected time lag associated with offsetting impacts and the degree of risk associated with the proposed mitigation. The uniform mitigation assessment method shall account for different ecological communities in different areas of the state . . . . In 2004, the Department adopted the Uniform Mitigation Assessment Method (UMAM) rule, Florida Administrative Code Chapter 62-345. In general terms, the UMAM is designed to assess impacts and wetland functions associated with projects that impact wetlands, along with necessary mitigation required to offset those impacts. As it pertains to this proceeding, the UMAM establishes the standards for evaluating mitigation banks and calculating the credits that may be awarded to a mitigation bank, and provides a standardized wetland assessment methodology that may be applied across community types. Permitting of a mitigation bank first involves a qualitative characterization of the property, known as a Part I evaluation. The Part I evaluation is conducted by dividing the subject parcel of property into assessment areas for wetlands and uplands. An assessment area is ?all or part of a . . . mitigation site, that is sufficiently homogeneous in character . . . or mitigation benefits to be assessed as a single unit.? Fla. Admin. Code R. 62-345.200(1). Each mitigation assessment area must be described with sufficient detail to provide a frame of reference for the type of community being evaluated and to identify the functions that will be evaluated. When an assessment area is an upland proposed as mitigation, functions must be related to the benefits provided by that upland to fish and wildlife of associated wetlands or other surface waters. Information for each assessment area must be sufficient to identify the functions beneficial to fish and wildlife and their habitat that are characteristic of the assessment area‘s native community type . . . Fla. Admin. Code R. 62-345.400. After the assessment areas have been established, a Part II assessment is performed using the scoring criteria established in the UMAM "to determine the degree to which the assessment area provides the functions identified in Part I and the amount of function lost or gained by the project.? Under the Part II evaluation, each mitigation assessment area is evaluated under its current condition --or for areas subject to preservation mitigation, without mitigation -- and its ?with mitigation? condition. The difference in those conditions represents the improvement of ecological value referred to as the ?delta? or the ?lift.? Fla. Admin. Code R. 62-345.500. The ?delta? for an enhancement or restoration area is subject to modification by applying any applicable time lag factor and risk factor to arrive at the numeric relative functional gain (RFG). The RFG is multiplied by the number of acres of the assessment area to determine the number of mitigation bank credits to be awarded. Fla. Admin. Code R. 62- 345.600. Time Lag Factor Section 373.414(18) provides, in pertinent part, that ?[t]he uniform mitigation assessment method shall also account for the expected time lag associated with offsetting impacts . . . .? Florida Administrative Code Rule 62-345.600(1) establishes the UMAM criteria for applying the time lag factor and provides, in pertinent part, that: Time lag shall be incorporated into the gain in ecological value of the proposed mitigation as follows: The time lag associated with mitigation means the period of time between when the functions are lost at an impact site and when the site has achieved the outcome that was scored in Part II. In general, the time lag varies by the type and timing of mitigation in relation to the impacts. Wetland creation generally has a greater time lag to establish certain wetland functions than most enhancement activities. Forested systems typically require more time to establish characteristic structure and function than most herbaceous systems. Factors to consider when assigning time lag include biological, physical, and chemical processes associated with nutrient cycling, hydric soil development, and community development and succession. There is no time lag if the mitigation fully offsets the anticipated impacts prior to or at the time of impact. * * * For the purposes of this rule, the time lag, in years, is related to a factor (T- factor) as established in Table 1 below, to reflect the additional mitigation needed to account for the deferred replacement of wetland or surface water functions. The ?Year? column in Table 1 represents the number of years between the time the wetland impacts are anticipated to occur and the time when the mitigation is anticipated to fully offset the impacts, based on reasonable scientific judgment of the proposed mitigation activities and the site specific conditions. TABLE 1. Year T-factor <or=1 1 2 1.03 3 1.07 4 1.10 5 1.14 6-10 1.25 11-15 1.46 16-20 1.68 21-25 1.92 26-30 2.18 31-35 2.45 36-40 2.73 41-45 3.03 46-50 3.34 51-55 3.65 >55 3.91 The time lag factor is a discounting process which adjusts the future value of the mitigation to a present value at the time credits are released, and is intended to account for the difference between the time that the impacts that the mitigation is to offset have occurred and the time that the final success upon which the credits are based is achieved. The application of the time lag factor is required when mitigation credits are released prior to the mitigation bank achieving the scored final "with-mitigation" condition. Risk Factor Section 373.414(18) provides, in pertinent part, that ?[t]he uniform mitigation assessment method shall also account for the . . . degree of risk associated with the proposed mitigation.? Florida Administrative Code Rule 62-345.600(2) establishes the criteria for applying the time lag factor and provides, in pertinent part, that: (2) Mitigation risk shall be evaluated to account for the degree of uncertainty that the proposed conditions will be achieved, resulting in a reduction in the ecological value of the mitigation assessment area. In general, mitigation projects which require longer periods of time to replace lost functions or to recover from potential perturbations will be considered to have higher risk that those which require shorter periods of time. The assessment area shall be scored on a scale from 1 (for no or de minimus risk) to 3 (high risk), on quarter- point (0.25) increments. A score of one would most often be applied to mitigation conducted in an ecologically viable landscape and deemed successful or clearly trending towards success prior to impacts, whereas a score of three would indicate an extremely low likelihood of success based on the ecological factors below. A single risk score shall be assigned, considering the applicability and relative significance of the factors below, based upon consideration of the likelihood and the potential severity of reduction in ecological value due to these factors. As with the time lag factor, the risk factor is a discounting process which is designed to account for the possibility that there may be occurrences that interfere with the ability of the mitigation bank to replace the ecological functions and values lost when wetland impacts are permitted prior to the final success or evidence that the mitigation bank is clearly trending towards success. DEP/SJRWMD Operating Agreement Sections 373.4135 and 373.4136 establish that the mitigation banking program was created to be jointly administered by the Department and the water management districts. In order to facilitate that joint administration, and to ?further streamline environmental permitting, while protecting the environment,? the Department and the SJRWMD have entered into a written Operating Agreement to ?divide[] responsibility between the DISTRICT and the DEPARTMENT for the exercise of their authority regarding permits . . . under Part IV, Chapter 373, F.S.? By that Operating Agreement, the Department expressly delegated its ?duties and responsibilities? under chapter 373 and Title 62, F.A.C. to the SJRWMD. The Operating Agreement has been adopted by rule by the Department, in rules 62-113.100(3)(x) and 62-300.200(2)(b), and by the SJRWMD in rule 40C-4.091(1)(b). The Department and the SJRWMD are clearly in privity with one another for projects that are subject to the written Operating Agreement. HRMB Permitting History On January 5, 2009, Highlands Ranch submitted an application to the SJRWMD for approval of the HRMB to be located on a 1,575.5-acre parcel of property in Clay County, Florida, specifically in Sections 9, 10, 15, and 16, Township 5 South, Range 23 East (the Property). The application was appropriately submitted to the SJRWMD pursuant to the terms of the Operating Agreement. The Mitigation Service Area (MSA) for the proposed HRMB incorporated portions of Baker, Clay, St. Johns, Putnam, and Duval Counties. The land area and MSA that was the subject of the SJRWMD Permit is identical to the Property encompassed by the proposed DEP Permit at issue in this proceeding. As established in the proceeding that resulted in the issuance of the SJRWMD permit: Highlands Ranch is proposing to place a conservation easement over the mitigation bank property and to conduct enhancement activities in those areas of the property needing improvement as a result of current land uses. Generally, it proposes to cease all pine production practices and cutting of cypress and hardwood trees after the permit is issued. It has also proposed to improve hydrologic conditions on the property by removing a trail road, installing four low water crossings, and removing pine bedding and furrows within all areas planted with pine on the property. Finally, supplemental plantings of appropriate canopy species will be conducted. The project will be implemented in three phases . . . . CRP/HLV Highlands Ranch, LLC v. SJRWMD, Case No. 10-0016, ¶20, (Fla. DOAH May 26, 2010; SJRWMD July 16, 2010). The general project description and phases were substantially identical to the phased proposal in the instant DEP Permit. When Highlands Ranch made its 2009 application to the SJRWMD, the District performed a review of the application, conducted multiple site inspections, met with the applicant's consultants, submitted requests for additional information, and reviewed other appropriate resources. On November 19, 2009, the SJRWMD issued its notice of intent to approve the application, and to approve 204.91 mitigation credits for the HRMB. The credits were calculated by the SJRWMD by applying the UMAM rule. Highlands Ranch filed a petition to challenge the number of credits with the SJRWMD, and requested a formal administrative hearing before the Division of Administrative Hearings. By the time of the final hearing, Highlands Ranch had modified its request to 425 credits, and the SJRWMD had modified its proposed agency action to reduce the number of credits to 193.56. A primary issue of contention in the SJRWMD permit hearing was whether the UMAM preservation adjustment factor (PAF) should be separately applied in areas proposed for enhancement activities in conjunction with preservation afforded by the conservation easement, or whether preservation should be considered as a subsumed element of the enhancement. The PAF is a process that assigns a value to the preservation of the property, and is scored on a scale from zero (no preservation value) to one (optimal preservation value) on one-tenth increments. Fla. Admin. Code R. 62-345.500(3)(a). Thus, preservation at anything less than optimal preservation will result in a downward adjustment of the RFG upon which credits for the acres in an assessment area are ultimately calculated. Under the ?two-step? process, after the functional gain associated with the preservation of the wetland assessment areas is determined, the second step of scoring the functional gain that would be achieved from the enhancement activities, which includes consideration of time lag and risk associated therewith, is performed. The preservation and enhancement scores are considered as separate forms of mitigation, and are each applied as multiples of the delta to arrive at the RFG. In contrast to the SJRWMD approach, Highlands Ranch used a "one-step approach," which scored any area that would be both preserved and enhanced/restored only as ?with mitigation? under UMAM and did not conduct a separate analysis for preservation or apply a separate preservation factor multiple. Neither the ?two-step? PAF nor the ?one-step? PAF is specifically described in the UMAM rule, and both are allowable interpretations of the rule. After the formal hearing, the administrative law judge entered a recommended order in which he determined that the SJRWMD‘s application of the UMAM standards, including its application of the ?two-step approach? was appropriate and correct, thus warranting an award of 193.56 mitigation credits for the HRMB. Neither Highlands Ranch nor the SJRWMD filed exceptions to the recommended order. On July 14, 2010, the SJRWMD entered its final order, which adopted the recommended order ?in its entirety as the final order of this agency.? The final order was not appealed. The SJRWMD permit, Permit Number 4-019-116094-2, was thereafter issued on August 4, 2010, and is currently valid. Development of the June 15, 2011 DEP Guidance Memo During the 2011 legislative session, a bill was proposed to amend the statutes governing mitigation banks. The legislation failed to pass. After the conclusion of the 2011 legislative session on May 7, 2011,1/ more than nine months after the issuance of the SJRWMD permit, counsel for Highlands Ranch contacted Mr. Littlejohn, who had been hired in March, 2011 as the Department‘s Deputy Secretary for Regulatory Programs, to express Highlands Ranch‘s ?frustration with . . . what they considered not an objective review at the [SJRWMD].? Mr. Littlejohn understood that Highlands Ranch believed the SJRWMD review of the application that led to the issuance of the SJRWMD Permit ?was not impartial.? After the telephone conversation, Mr. Littlejohn instructed Department staff to work with counsel for Highlands Ranch to develop guidance to interpret the UMAM rule. Counsel for Highlands Ranch prepared and provided drafts of a guidance document for the Department. There was no evidence of any private individual, other than counsel for Highlands Ranch, being given an opportunity to provide input or otherwise participate in the development of the guidance document. On June 15, 2011, the Department released its final ?Guidance Memo on Interpreting and Applying the Uniform Mitigation Assessment Method? (Guidance Memo). The Guidance Memo was designed to establish ?nuanced interpretations of the UMAM rule? in order to ?provide a uniform method throughout the state.? The Guidance Memo consisted of eight numbered paragraphs. According to Mr. Littlejohn, ?some of these paragraphs are completely unaltered from the [failed 2011] legislation, but I believe that most of them probably had some minor alteration in the subsequent review by the Office of General Counsel and during our own review internally, but . . . some form of Paragraphs 2 through 8 existed in . . . that legislation.? It was the intent of the Department that the Guidance Memo would reflect the current Department interpretation and direction to others in the application of the UMAM. The Guidance Memo was provided to the program administrators for each of the Department‘s six district offices, to the ERP program administrators for each of the water management districts, and to Broward County, which administered the only delegated local ERP program, with the intent that it be uniformly applied by each of them. The Guidance Memo is, and was intended to be, a Department-issued statement of general applicability that implements, interprets, or prescribes law or policy. The practical effect of the Guidance Memo was to reject the ?two-step? preservation adjustment factor (PAF) as applied by the SJRWMD, and establish the ?one-step? PAF as the only interpretation and application allowed by the UMAM rule. The development of the Guidance Memo would have made an appropriate subject for rulemaking, at which all affected stakeholders could have participated. Instead, the Department chose to limit participation to Highlands Ranch, offering no opportunity for other views, either in favor of or in opposition to the terms of the Guidance Memo. Notably, despite the legislature‘s encouragement, if not requirement, of cooperation between the Department and the water management districts in the development and implementation of the UMAM, the Guidance Memo, which was designed to override the method by which UMAM standards were applied by at least two of the water management districts, was developed without water management district knowledge or participation. SJRWMD Application for Modification On September 14, 2011, Highlands Ranch submitted an application for a modification of the SJRWMD permit to the SJRWMD. The application requested that the SJRWMD reconsider the permitted mitigation bank plan in light of the DEP Guidance Memo and, based thereon, modify the number of mitigation credits awarded. No other changes were made to the mitigation bank as permitted. Based on the application of the Guidance Memo alone, Highlands Ranch calculated that 425 mitigation credits was the appropriate number for the development and implementation activities presented in the original SJRWMD permit application. Highlands Ranch withdrew the application for a modification of the SJRWMD permit prior to November 2011. DEP Application for Modification On November 2, 2011, Highlands Ranch submitted an application to the Department for a modification of the SJRWMD Permit (the DEP modification application). In addition to a request that the Guidance Memo be applied, the modification made changes to the plan permitted by the SJRWMD, including supplemental planting of seedling longleaf pine, modification to the prescribed burn schedules, and modification of the monitoring plans and ?success criteria? for demonstrating ecological progress. The application proposed that 426.05 credits be awarded for the HRMB as modified. The DEP modification application was assigned for permit review to Constance Bersok who was, at the time, the Environmental Administrator for the Wetlands Mitigation Program. Ms. Bersok had been involved in the process of applying the UMAM since shortly after the 2000 legislative session, when she ?was in charge of the Department's part of [the UMAM rule] development and coordination? along with the water management districts and other affected entities. Ms. Bersok was identified as the primary Department contact for ?questions and other feedback? regarding the UMAM rule in the June 15, 2011 Guidance Memo. Ms. Bersok is knowledgeable and experienced regarding the interpretation and application of the UMAM rule. Thus, she was the appropriate staff person for primary oversight of the application. Special Cases Agreement The Department determined that it would process the modification application despite the assignment of such projects to the SJRWMD under the Operating Agreement. In order to assume control over the permitting of the HRMB, the Department entered into a ?Written Agreement Pursuant to the Special Cases Section of the Operating Agreement? with the SJRWMD (Special Cases Agreement). Section II, Part D. of the Operating Agreement provides that: By written agreement between the DISTRICT and the DEPARTMENT, responsibilities may deviate from the responsibilities outlined in II. A., B., or C. above. Instances where this may occur include: An extensive regulatory history by either the DISTRICT or the DEPARTMENT with a particular project that would make a deviation result in more efficient or effective permitting; Simplification of the regulation of a project that crosses water management district boundaries; The incorrect agency has begun processing an application or petition and transfer of the application or petition would be inefficient; or Circumstances in which a deviation would result in the application being more efficiently or effectively processed. The specific provisions of paragraphs 1-3 being inapplicable, the Department assumed control over the modification application by relying on the generic ?catch-all? reason set forth in paragraph 4. The basis for the Department‘s determination that it could ?more efficiently or effectively process[]? the application -- despite the fact that the HRMB Property was literally in the SJRWMD‘s back yard, that the SJRWMD had a recent permitting history regarding the Property, and that the SJRWMD had extensive existing knowledge of the condition of the Property -- is not apparent and was not explained. The Special Cases Agreement became effective on December 13, 2011, upon Mr. Littlejohn‘s signature. DEP Permit Application On November 22, 2011, Highlands Ranch submitted a second package to Ms. Bersok, which converted the HRMB application from one for a modification of the SJRWMD permit, to one for a new permit to be issued by the Department. The permit application made certain changes to the terms and conditions for the development of the mitigation bank established in the SJRWMD Permit, but otherwise encompassed the same boundary and service area of the SJRWMD Permit. Highlands Ranch proposed 426.05 mitigation credits as the appropriate number of credits for the activities in the DEP permit application. There has been no other instance in which the Department accepted, processed, or issued a second mitigation bank permit when there was an existing and valid permit issued by a water management district for the same property. Thus, this application is unique in that regard. The Special Cases Agreement provided that it was designed to allow the Department to process the ?[a]pplication for a modification of the Highlands Ranch Mitigation Bank wherein the applicant seeks to revise the mitigation plan.? Despite its apparent limitation to a modification of the SJRWMD permit, the Special Cases Agreement cites to the application number of the DEP Permit that is the subject of this proceeding, and became effective after the submission of the new permit application. There is no evidence of the SJRWMD having objected to the Department‘s continued processing of the application. Thus, although irregular, the Special Cases Agreement was broad enough in its scope to encompass the conversion of the application for modification to a separate permit application. In addition to the foregoing, the scope of the Special Cases Agreement is a matter between the Department and the SJRWMD. There is no question that both agencies have legislatively conferred authority with regard to permitting mitigation banks. The decision between those agencies as to which would have responsibility going forward with the HRMB is not one that affects the substantial interests of Petitioner. Creation of the New ?Performance-driven? Approach On or about February 10, 2012, Ms. Bersok was advised by Mr. Littlejohn that the Department was going to implement a new and previously untried ?performance-driven? approach to permitting the HRMB. Mr. Littlejohn testified that this performance-driven approach is an interpretation of existing mitigation banking rules, and was to provide greater certainty in environmental performance, mitigation success, and provide for a more consistent, predictable, and repeatable permitting process.2/ The more practical effect of the ?performance-driven? approach, as stated by Mr. Littlejohn, is that ?there may be some increase in credits upon not applying a risk or a time lag factor. Those are both discount factors which attach to the raw scoring. So there may be an increase in credits.? Mr. Littlejohn testified that under his ?performance- driven? approach, the current condition of the Property and the final ?success criteria? were the only relevant factors, not how the applicant chose to meet those criteria. Consistent with that approach, Ms. Bersok was instructed that there was no need to issue a request for additional information as to the details by which the performance goals would be met, as was the normal procedure for environmental resource permits, including mitigation bank permits.3/ Under the performance-driven approach as applied to the HRMB, mitigation credits are subject to interim release and available for use upon the satisfaction of ?success criteria? set forth in the permit. Pursuant to the credit release schedule set forth in the DEP Permit, credits may be released upon recording the conservation easement(s), posting the required financial responsibility instrument and providing site security, and thereafter upon meeting one of five ?interim release? milestones. The interim credit releases authorize the release of mitigation credits for use to offset wetland impacts well before the time when the site has achieved the outcome that was scored in the Part II assessment. Although Highlands Ranch will have performed the bulk of the active construction and implementation activities before being entitled to an interim release, the ecological benefit of the interim ?success criteria? does not represent the achievement of the structure and function that will be necessary for final success, nor does it guarantee that that final structure and function will ultimately be achieved. Complete Application Though instructed not to request additional information, Ms. Bersok sent an e-mail to the agent for Highlands Ranch that contained a recitation of what she would have sent the applicant in a request for additional information. On February 14, 2012, Highlands Ranch submitted supplemental information in support of the permit application to Ms. Bersok. The supplemental information contained some, though not all, of the information requested by Ms. Bersok. The submittals of November 1, 2011; November 22, 2011; and February 14, 2012, along with the application check, constitute the application to DEP. There were no written submittals designed to supplement, alter, or amend the proposed activities to enhance or preserve the Property after February 14, 2012. Thus, those documents constituted the complete application. The application contained Highlands Ranch‘s description of historic and existing vegetative communities. There was no suggestion that the description provided by Highlands Ranch was not accurate. The goal of the HRMB as reflected in the DEP application was to convert a silviculture operation to the appropriate native target communities. Mitigation activities proposed in the complete application included restoring or enhancing longleaf pine/xeric oak sandhill, mesic flatwoods, hydric or wet flatwoods, baygall/bay swamp, floodplain swamp/stream or lake swamp and bottomland forest/wetland forest mixed communities, generally through reversal of the existing silvicultural impacts and implementing hydrologic enhancement activities. Each phase of the HRMB would be subject to a conservation easement granted to the Department and the SJRWMD for preservation of the Property in its existing or enhanced condition. The complete application provided that enhancement and restoration would be accomplished through canopy thinning in existing upland and wetland pine plantation areas; control of nuisance and invasive exotic vegetative species; vegetative enhancement, including replanting thinned pine areas with appropriate species where necessary, and supplemental planting of historic native trees and ground cover; prescribed fire; and hydrologic enhancements. Ongoing management of the HRMB site would primarily involve monitoring; prescribed fire; and control of nuisance and invasive exotic vegetative species. Draft Permits As information regarding the application was submitted by Highlands Ranch, Ms. Bersok undertook to calculate the number of mitigation credits warranted by the complete application. She performed several calculations between December 8, 2011 and February 22, 2012. On February 22, 2012, Ms. Bersok performed her final written analysis of the application using the information contained in the November 22, 2011, submittal, including the mitigation activities and target levels and methodologies described by Highlands Ranch, and the information contained in the February 14, 2012, submittal. Thus, her assessment and review was based upon the complete application. In addition to the information regarding site conditions from the permitting file, Ms. Bersok had ?a couple of meetings? to discuss the application, made a site visit, and reviewed additional aerial images obtained on-line. Although her site visit was not comprehensive, Ms. Bersok felt that she had adequate information regarding the current condition for each of the different types of assessment areas that were on the site. Since her review was based in large measure on information and site descriptions regarding the current conditions provided by Highlands Ranch, her belief as to the sufficiency of the information regarding the assessment areas upon which she based her review is warranted and accepted. The November 22, 2011, submittal included the following mitigation activities that differed from the conditions of the SJRWMD permit: All areas subjected to prescribed burning would be burned on a 2-8 year rotation. Two burns necessary to reach final success criteria. Communities defined by both FLUFCS classification and FNAI classification. Basal area targets of less than 60 square feet per acre in U1 and 80 square feet per acre in U2 (perpetual management only). A total of 426.05 credits proposed. No credit withholding by phase. Completion of Construction and Implementation tasks results in 20% of credit release. Target levels and methodologies to determine percent cover and composition of canopy, shrub, and groundcover. The February 14, 2012, submittal included the following description of mitigation activities that differed from the conditions of the SJRWMD permit: The expected fire frequency for the hydric pine restoration areas to be a 1-3 year cycle, with actual burn frequency to be in the professional judgment of the burn manager and team ecologists. Further description of the low water crossings and structures. Since Ms. Bersok utilized the November 22, 2011, submittal, along with the information provided by Highlands Ranch on February 14, 2012, her review and analysis necessarily included the above-listed mitigation activities and target conditions. Ms. Bersok made assumptions designed to produce high quality outcomes that, at the time of her review, had not yet been incorporated as conditions to any proposed permit. Her assumptions/recommendations included the following: In those locations without sufficient pyrogenic groundcover, mechanical means of shrub reduction to carry a fire, and planting or seeding of the native ground cover to achieve and sustain the target community type. Planting of longleaf pine in the xeric (U1) and mesic (U2) communities, and similar mitigation in the hydric pine restoration (W1 and W2) assessment areas. Ms. Bersok‘s assumptions were ultimately incorporated in the DEP draft permit. Ms. Bersok‘s analysis included the ?one-step? approach to application of the preservation factor, wherein preservation was included as an element of enhancement in restoration or enhancement assessment areas, rather than as a separate factor, consistent with the approach outlined in the June 15, 2011 Guidance Memo. Thus, for the assessment areas that were not exclusively bay or floodplain preservation, the ?P-Factor? score was listed as ?n/a.? Ms. Bersok utilized the ?performance-driven? approach as instructed by Mr. Littlejohn. Therefore, her February 22, 2012, assessment assigned a score of 1.00 for both time lag and risk. As a result of her calculations, Ms. Bersok arrived at a total of 280.33 mitigation credits for the HRMB. Ms. Bersok‘s February 22, 2012, score of 280.33 credits incorporated all of the material changes to the SJRWMD permit that were proposed by Highlands Ranch in its complete application, and the material specific conditions that were ultimately included in the DEP proposed permit. The only changes to the SJRWMD permit that were not explicitly part of Ms. Bersok‘s calculation, either as a proposal by the applicant or as an assumption, were: two consecutive burns within a period of 1-3 years in the xeric, mesic, and hydric pine restoration areas to demonstrate final success. monitoring and recording of shrub height to meet success criteria. control of oak species ?to obtain the abundance appropriate to the sandhill community condition.? Those relatively minor changes are not significant in light of the overall information presented in the complete application and Ms. Bersok‘s accepted assumptions, and do not materially affect the final target conditions for the mitigation. Several days prior to May 8, 2012, Ms. Bersok met with Mr. Rach and Mark Thomasson to discuss progress on the application and draft permits. At that time, she reviewed a UMAM assessment that assigned 333 mitigation credits to the HRMB. She was instructed ?to look for some more credits, that [333 credits] wasn't enough.? Ms. Bersok advised Mr. Rach and Mr. Thomasson that 333 mitigation credits was more than could be ecologically supported.4/ On May 8, 2012, Mr. Rach presented Ms. Bersok with a draft pilot permit that called for the award of 424 mitigation credits for the HRMB. Mr. Rach was unable to identify who in the Department calculated the UMAM credits, but that ?the credits which were the result of the UMAM were one of the last things filled in in the permit. So I'm not sure at that point in time who it was.? On May 9, 2012, Ms. Bersok prepared a ?status memo? in which she expressed her opinion that she could not ecologically support the award of 424 mitigation credits for the HRMB, and expressed her ?objection to the intended agency action and refusal to recommend this permit for issuance.? On May 11, 2012, Ms. Bersok was removed from further involvement in the review of the HRMB permit application. Issuance of the DEP Permit and Variance Over the course of the next three months, the Department and Highlands Ranch had several meetings in which they developed the performance standards and ?success criteria? that would be applied to allow for the release of mitigation credits. The meetings included additional site visits. There was no evidence that the additional site visits revealed conditions of the site that were inconsistent with those set forth in the complete application. During the course of the hearing, it was suggested that ?additional activities [were] proposed? during the period when the permit application was being processed. There were, in this case, no requests for additional information, no written submittals memorializing any such additional activities, and no evidence of any alteration or amendment of the complete application. Those ?additional activities? were not specified or described during the final hearing. To the extent that the Department or Highlands Ranch purports to rely on unspecified ?additional activities? that are not contained in the application or the permitting file, or otherwise presented as evidence to support issuance of the permit, they may not be considered as part of the record of this proceeding. On August 17, 2012, the Department issued its Notice of Intent to Issue Environmental Resource/Mitigation Bank Permit and Variance (Notice) and draft permit that awarded 424.81 mitigation credits for the HRMB. The number of credits awarded by the Department ?was a collaborative effort with the Applicant over the course of several meetings,? with Mr. Thomasson ultimately signing off and agreeing to the final scores. The Notice provided that the UMAM assessment of the HRMB Property showed ?a potential of 424.81 total freshwater credits: 207.31 Hydric Flatwoods/Wet Prairie credits and 217.50 Freshwater Forested wetlands credits.? Thus, the credits awarded to the HRMB may be purchased and applied at impact sites in the MSA to offset 207.31 units of functional loss associated with hydric flatwoods and wet prairies, and 217.50 units of functional loss associated with freshwater forested wetlands. The 426.05 credits proposed by Highlands Ranch in the November 22, 2011 application were derived by calculating 291.99 credits for restoration of the upland pine assessment areas, 73.78 credits for restoration of the hydric pine assessment areas (thus 365.77 credits for restoration of overall pine assessment areas), 15.40 total credits for enhancement and restoration of floodplain, bottomland, and bay assessment areas, and 37.65 credits for preservation of floodplain and bay assessment areas. The 425.81 credits awarded by the Department were derived by calculating 317.64 credits for restoration of the upland pine assessment areas, 52.06 credits for restoration of the hydric pine assessment areas (thus 369.70 credits for restoration of overall pine assessment areas), 15.35 total credits for enhancement and restoration of floodplain, bottomland, and bay assessment areas, and 39.75 credits for preservation of floodplain and bay assessment areas. The number of credits awarded by the Department is roughly identical to the number requested by Highlands Ranch in the 2010 SJRWMD proceeding (425 credits), the number requested by Highlands Ranch in the November 1, 2012, application for modification of the SJRWMD permit (426.05 credits), the number requested by Highlands Ranch in the November 22, 2011 DEP permit application (426.05 credits), and the number preliminarily calculated by the Department and provided to Ms. Bersok on May 8, 2012 (424 credits). Credit Release Schedule Section 373.4136(5) provides that: SCHEDULE FOR CREDIT RELEASE.— After awarding mitigation credits to a mitigation bank, the department or the water management district shall set forth a schedule for the release of those credits in the mitigation bank permit. A mitigation credit that has been released may be sold or used to offset adverse impacts from an activity regulated under this part. The department or the water management district shall allow a portion of the mitigation credits awarded to a mitigation bank to be released for sale or use prior to meeting all of the performance criteria specified in the mitigation bank permit. The department or the water management district shall allow release of all of a mitigation bank‘s awarded mitigation credits only after the bank meets the mitigation success criteria specified in the permit. The number of credits and schedule for release shall be determined by the department or water management district based upon the performance criteria for the mitigation bank and the success criteria for each mitigation activity. The release schedule for a specific mitigation bank or phase thereof shall be related to the actions required to implement the bank, such as site protection, site preparation, earthwork, removal of wastes, planting, removal or control of nuisance and exotic species, installation of structures, and annual monitoring and management requirements for success. In determining the specific release schedule for a bank, the department or water management district shall consider, at a minimum, the following factors: Whether the mitigation consists solely of preservation or includes other types of mitigation. The length of time anticipated to be required before a determination of success can be achieved. The ecological value to be gained from each action required to implement the bank. The financial expenditure required for each action to implement the bank. Notwithstanding the provisions of this subsection, no credit shall be released for freshwater wetland creation until the success criteria included in the mitigation bank permit are met. Florida Administrative Code Rule 62-342.470(3) allows for the release of credits prior to final success criteria having been met, and provides that: Some Mitigation Credits may be released for use prior to meeting all of the performance criteria specified in the Mitigation Bank Permit. The release of all mitigation credits awarded will only occur after the bank meets all of the success criteria specified in the permit. The number of credits and schedule for release shall be determined based upon the performance criteria for the Mitigation Bank, the success criteria for each mitigation activity, and a consideration of the factors listed in subsection 373.4136(5), F.S. However, no credits shall be released until the requirements of Rules 62-342.650 and 62.342.700, F.A.C., are met. Additionally, no credits awarded for freshwater creation shall be released until the success criteria included in the Mitigation Bank Permit are met. Prior to achieving the final success criteria, Highlands Ranch will be eligible for interim credit releases when the ?success criteria? for each phase as set forth in the permit are met. The mitigation credits are scheduled for release as follows: Conservation Easement/Financial Assurance/Security Phase 1 - 23.45 credits Phase 2 - 21.78 credits Phase 3 - 18.49 credits Interim Criteria I Phase 1 - 39.09 credits Phase 2 - 36.29 credits Phase 3 - 30.82 credits Interim Criteria II-A Phase 1 - 9.38 credits Phase 2 - 8.71 credits Phase 3 - 7.40 credits Interim Criteria II-B Phase 1 - 3.13 credits Phase 2 - 2.90 credits Phase 3 - 2.47 credits Interim Criteria III Phase 1 - 32.83 credits Phase 2 - 30.49 credits Phase 3 - 25.89 credits Interim Criteria IV Phase 1 - 28.14 credits Phase 2 - 26.13 credits Phase 3 - 22.19 credits Final Success Criteria by Phase Phase 1 - 12.51 credits Phase 2 - 11.61 credits Phase 3 - 9.86 credits Final Bank Success Criteria - 21.25 credits The tasks related to Phase 1 are targeted to commence upon permit issuance, with active management activities -- i.e., recording the conservation easement, providing title insurance, executing financial assurance mechanisms, and providing security; and enhancement activities, e.g., tree thinning, crushing bedding rows, planting, and activities relating to trail roads and culverts -- to be completed within one year. The evidence indicates that some of the management activities, including tree thinning and crushing bedding rows were completed prior to the submission of the application for the DEP Permit. The tasks related to Phase 2 and Phase 3 are targeted to commence upon ?phase implementation,? with active management and enhancement activities within one year of the implementation of each phase. The application provides that the implementation date for Phase 2 and Phase 3 ?will be based upon market demand for mitigation within the mitigation service area.? Thus, the phases could be implemented immediately, or not at all, at the sole discretion of Highlands Ranch. The HRMB mitigation milestones that allow for interim releases of mitigation credits prior to the final success of the target communities and measures for which the bank was scored under the Part II assessment do not materially differ from standards for interim releases applicable to all mitigation banks pursuant to section 373.4136(5) and Florida Administrative Code Rule 62-342.480(3). In addition to the foregoing, though not dispositive of the issue, is the fact that the ?success criteria? in the HRMB permit are, in many cases, vague and non-quantifiable. Thus, in the absence of specific standards and comparators, the HRMB success criteria may allow for the release of credits to offset present wetland impacts without any specific or measurable ecological benefit. Application of the Time Lag Factor The Department calculated the credits for the HRMB using a time lag score of 1.00 for all assessment areas. Thus, in keeping with the UMAM, the Department necessarily made the decision that at the time of the interim releases, ?the mitigation fully offsets the anticipated impacts prior to or at the time of impact.? Meeting the ?success criteria? for an interim release of credits does not mean that the mitigation bank has met the success measures for which the bank was scored under the Part II assessment. Rather, meeting the ?success criteria? serves only to recognize that the project is meeting interim goals that show general progress towards the target goals if continued and successful into the future. In this case, there is a time difference between the achievement of the ecological benefits of the final target community, and the interim release of mitigation credits and their use to offset impacts at sites requiring mitigation. There is little practical ecological difference between releasing credits before final target communities are achieved based on ?success criteria? that are the result of implementing described activities, and releasing credits based on the physical implementation of those described activities. The effect in both cases is that mitigation credits are to be released during the ?time between when the functions are lost at an impact site and when the site has achieved the outcome that was scored in Part II.? There was testimony offered at the final hearing that the Department‘s time lag and risk scores of 1.00 were appropriate because the credit release schedule represents functional ecological improvement that must be achieved before credits are released. For the reasons set forth above, the undersigned finds that the functional ecological improvement represented by the ?success criteria? is not materially dissimilar from the means by which the ecological value of interim release milestones has been calculated for previously permitted and implemented mitigation banks. Thus, testimony that the success criteria as proposed in the DEP Permit warrants time lag and risk scores of 1.00 is not credited. Contrary to the evidence referenced in the preceding paragraph, Mr. Hull testified convincingly that there is a sizable percentage of credits released prior to the mitigation bank reaching the success proposed for many of the restoration assessment areas without time lag or risk. An example of time lag that should be applicable to the HRMB is the fact that final success for all assessment areas includes, among other criteria, the requirement that all plants, except those targeted for control or eradication, be reproducing naturally. In the case of longleaf pine, which is to be planted throughout the Property, the period before the achievement of that outcome is approximately 30 years. Furthermore, Ms. Bersok testified credibly that when starting with a community that has few ecological functions, the time necessary to ultimately achieve a high community structure score can take much longer than 15 to 20 years. That period before final success should have been reflected as time lag in the UMAM assessment, but was not. In accordance with the schedule proposed by Highlands Ranch, a significant number of the total credits awarded for the three phases may be released within one year of permit issuance. In that regard, the ?CE/Financial Assurance/Security? interim release allows for a three-phase total of 63.72 credits to be released for that interim step, estimated to occur within 30 days of permit issuance or phase implementation, while Interim Criteria I allows for a three-phase total of 106.20 credits to be released for that interim step, estimated to occur within one year of permit issuance or phase implementation. Thus, 169.92 of 425.81 credits, or 40 percent of the total, are potentially eligible for release within a short period, and years before any reasonable expectation of final target community success. It is that circumstance that squarely meets the standards for the application of the time lag factor. Based on the testimony and evidence adduced at the final hearing, the calculation of credits for the HRMB without accounting for the time lag before final success produces an unreasonable result, regardless of the application of the "performance-driven" approach that was created for the HRMB by the Department.5/ Thus, the decision to assign a time lag score of 1.00 to each of the restoration assessment areas is contrary to the facts of this case, and the plain language of the UMAM rule and its requirements. Application of the Risk Factor The Department calculated the credits for the HRMB using a risk score of 1.00 for all assessment areas. Thus, pursuant to the UMAM, the Department made the decision that the mitigation projects require no significant ?periods of time to replace lost functions or to recover from potential perturbations,? and that the mitigation activities are being ?conducted in an ecologically viable landscape and deemed successful or clearly trending towards success prior to impacts.? As set forth in preceding paragraphs, there is a sizable period of time between the interim release of credits - and their availability to replace lost functions at permitted impact sites -- and the time at which the mitigation has been established and monitored to the point at which it is ?clearly trending towards success.? Thus, a risk score of 1.00, meaning that there is essentially no risk, is not warranted. The risk in this case is that associated with the fact that the ?mitigation projects . . . require longer periods of time to replace lost functions or to recover from potential perturbations.? Although there were concerns expressed that the proposed activities might have heightened risk inherent in the mitigation methods, the testimony on that issue was vague and non-specific, and is not accepted. Based on the testimony and evidence adduced at the final hearing, the failure to account for the risk associated with the extended period of time expected before final restoration and enhancement success is not warranted, regardless of the application of the "performance-driven" approach. Thus, the decision to assign a risk score of 1.00 to each of the restoration assessment areas is contrary to the facts of this case, and the plain language of the UMAM rule and its requirements. Application of the Preservation Adjustment Factor The DEP Permit applied the preservation factor as a ?one-step? process as described above. Under that method, the PAF was not separately applied in any restoration or enhancement assessment area. That method was applied by Ms. Bersok in her February 22, 2013, UMAM scoring of the HRMB complete application. A PAF of 0.70 was applied to both of the preservation assessment areas. That score was also applied by Ms. Bersok in her February 22, 2013, UMAM scoring of the HRMB complete application. The ?one-step? application of the PAF was an allowable method under the UMAM rule. Petitioner failed to prove that the score of 0.70 for the preservation assessment areas was not warranted. Variance from Construction and Implementation Financial Responsibility Requirement Section 373.4136 provides that, in order to obtain a mitigation bank permit, an applicant must meet the financial responsibility requirements established by rule. § 373.4136(10), Fla. Stat. As it relates to financial responsibility for the construction and implementation of a mitigation bank, Florida Administrative Code Rule 62-342.700(4) provides, in pertinent part, that: Financial Responsibility for Construction and Implementation. No financial responsibility shall be required where the construction and implementation of the Mitigation Bank, or a phase thereof, is completed and successful prior to the withdrawal of any credits. * * * . . . When the bank (or appropriate phase) has been completely constructed, implemented, and is trending toward success in compliance with the permit, the respective amount of financial responsibility shall be released. The financial responsibility mechanism shall become effective prior to the release of any mitigation credits. Section 120.542(2) provides that: (2) Variances and waivers shall be granted when the person subject to the rule demonstrates that the purpose of the underlying statute will be or has been achieved by other means by the person and when application of a rule would create a substantial hardship or would violate principles of fairness. For purposes of this section, ?substantial hardship? means a demonstrated economic, technological, legal, or other type of hardship to the person requesting the variance or waiver. For purposes of this section, ?principles of fairness? are violated when the literal application of a rule affects a particular person in a manner significantly different from the way it affects other similarly situated persons who are subject to the rule. On July 16, 2012, Highlands Ranch filed a petition with the Department for a variance from the financial responsibility requirements of rule 62-342.700 for the construction and implementation activities of Highlands Ranch Mitigation Bank.6/ In its ?Petition for Variance from Rule Subsections 62-342.700(1)(a), (2), (3) and (4), F.A.C.?, Highlands Ranch requested that the variance be granted on the basis that the application of the rule would create a substantial hardship. Highlands Ranch did not assert that the application of the financial responsibility rule would violate principles of fairness. As indicated previously, the proposed permit authorizes a release of credits when Highlands Ranch records the conservation easement, provides title insurance, executes financial assurance mechanisms, and provides security. Thus, the proposed HRMB permit authorizes the release of mitigation credits prior to any construction being commenced, much less completed. Although certain interim criteria must be met in order for additional mitigation credits to be released, those interim steps do not constitute success of the target conditions scored under the Part II Assessment or, without more, demonstrate that the mitigation is ?trending toward success? in meeting those final target conditions. Financial assurance is required for construction and implementation activities at all mitigation banks, and may not be released until the mitigation ?is trending toward success in compliance with the permit.? Highlands Ranch asserts that the unique ?performance-driven? approach that has been applied to the HRMB warrants a deviation from the requirement that it financially guarantee the work. To the contrary, the financial responsibility required by rule provides assurance that the active construction and implementation is performed and, as would be the case with the ?performance-driven? approach, may be released only when the expected outcomes are trending towards success. Without question, any time a permitee is required to provide financial responsibility, it will have a financial effect on the permittee. However, the standard for a variance requires that the financial effect constitute a hardship to the person requesting the variance. In this case, Highlands Ranch failed to demonstrate that meeting the financial responsibility requirements applicable to all mitigation bank permittees would constitute an economic, technological, legal, or other type of hardship as applied to it. Highlands Ranch did not request a variance on the basis that the application of the financial-responsibility rule would violate principles of fairness. Nonetheless, the Department determined that ?principals of fairness? warranted its grant of the variance. For the reasons set forth herein, including the fact that the financial-responsibility instruments required of all permittees may be released only when the mitigation ?is trending toward success in compliance with the permit,? the undersigned finds that the financial-responsibility rule does not affect Highlands Ranch in a manner significantly different from the way it affects other similarly situated persons who are subject to the rule. Highlands Ranch failed to demonstrate that the application of Florida Administrative Code Rule 62-342.700(4) would create a substantial hardship or would violate principles of fairness as applied to Highlands Ranch and the HRMB. Highlands Ranch‘s Motion for Attorney‘s Fees and Costs Based on the evidence adduced in this proceeding, the undersigned finds that Petitioner did not participate in this proceeding for an improper purpose. In that regard, Petitioner is found to have prevailed on certain issues that substantially changed the outcome of the proposed agency action which is the subject of this proceeding regarding both the DEP Permit and the Variance. Furthermore, despite the evidence provided as to the source of payment for certain of Petitioner‘s costs and attorney‘s fees, there was insufficient evidence to support a finding that Petitioner brought this action ?primarily to harass or to cause unnecessary delay or for frivolous purpose or to needlessly increase the cost of litigation, licensing, or securing the approval of an activity.? § 120.595(1)(e)1., Fla. Stat. Ultimate Findings of Fact Based on the totality of the facts adduced at the final hearing, having weighed the evidence introduced by each of the parties, and having gauged the demeanor and credibility of the witnesses, the undersigned accepts the testimony of Ms. Bersok as constituting the most credible and reliable application of reasonable scientific judgment, resulting in an accurate calculation of the allowable credits (except as modified below) that may be awarded under the standards established by the UMAM rule. The competent and substantial evidence available to Ms. Bersok, including the complete application submitted by Highlands Ranch, and her assumptions that were ultimately incorporated in the DEP proposed permit, are found to have been sufficient to allow her to formulate reasoned opinions and conclusions regarding the number of mitigation credits that could be ecologically justified in this case. Therefore, the undersigned finds that the application of the UMAM standards to the HRMB property and the restoration, enhancement, and preservation activities to take place thereon, warrants an award of a maximum of 280.33 mitigation credits. Based on the testimony and evidence adduced at the final hearing, and as set forth herein, the undersigned finds that the facts of this case, including the ?performance-driven? approach that was developed for and applied to the HRMB application, do not warrant a determination that there is no time difference between the time wetland impacts being mitigated by released mitigation credits are anticipated to occur and the time when the mitigation is anticipated to fully offset the impacts. Based thereon, the application of a time lag score of 1.00 in the UMAM assessment was in error. Thus, the 280.33 mitigation credits that reflect the maximum allowable number should be revised by applying an appropriate time lag modifier to the ?delta? for each restoration and enhancement assessment area as calculated by Ms. Bersok, with the RFG and final credits calculated based thereon. Based on the testimony and evidence adduced at the final hearing, and as set forth herein, the undersigned finds that the facts of this case do not warrant a determination that there is no uncertainty that there may be a reduction in the ecological value of the mitigation assessment area. That finding is based on the length of time expected before final success, rather than any inherent vulnerability of the target communities. Based thereon, the application of a risk score of 1.00 in the UMAM assessment was error. Thus, the 280.33 mitigation credits that reflect the maximum allowable number should be revised by applying an appropriate risk modifier to the ?delta? for each restoration and enhancement assessment area as calculated by Ms. Bersok, with the RFG and final credits calculated based thereon. For the reasons set forth herein, Highlands Ranch failed to demonstrate that it was entitled to a variance from the financial responsibility requirements of Florida Administrative Code Rule 62-342.700.

Recommendation Based on the findings of fact and conclusions of law, it is RECOMMENDED that the Department of Environmental Protection enter a final order consistent with the findings of fact and conclusions of law set forth herein. DONE AND ENTERED this 11th day of April, 2013, in Tallahassee, Leon County, Florida. S E. GARY EARLY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of April, 2013.

Florida Laws (18) 120.52120.54120.542120.569120.57120.595120.60120.6828.1430.49373.403373.4135373.4136373.414403.4127.407.5090.803 Florida Administrative Code (3) 62-342.47062-342.70062-345.600
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer