Findings Of Fact Respondent, Wesley Ash, currently holds license number CP C015871 issued by the Construction Industry Licensing Board to authorize Ash to engage in the pool contracting business. Dodd Complaint (Count I). Respondent, Wesley Ash, doing business as Wada Pools, Inc., contracted with Jerry Dodd on or about June 17, 1981, to build a pneumatic concrete pool with skimmer and recirculation system. The contract did not include installation of the concrete deck around the pool. Dodd decided to contract with another independent contractor to install the deck at a lower price than Ash wanted for the job. Ash completed his work by approximately August 1981. He installed the concrete pool shell, finished the inside surface and installed tile along the water line. He then attached the skimmer assembly, plumbing it so that it was level and attaching it to the concrete pool shell by means of the skimmer's PVC plumbing piping. After Ash finished his work, Dodd's other contractor came behind Ash. He used some of the dirt Ash had excavated from the pool site to raise the ground surrounding the pool by approximately six inches above grade. He then poured the concrete deck but failed to encase the skimmer assembly with the deck concrete in the process of pouring the concrete deck. It was not Ash's practice to make any special arrangements to stabilize the skimmer assembly when he installed both pool and concrete deck. He relies on the skimmer assembly plumbing to stabilize the skimmer assembly until the concrete deck is poured. In pouring the concrete deck, Ash encases the skimmer assembly with the deck concrete to stabilize the skimmer assembly and prevent leakage. In the case of the Poland pool (paragraphs 17 and 22, below), Ash used this method to install both the pool and the concrete deck, and Poland has had no complaint of leakage at the skimmer (nor was there any evidence of leakage at the skimmer). In the case of the Priests' pool (paragraphs 11 through 13, below), Ash followed the same procedures as he did with the Dodd pool, and another contractor poured the concrete deck. As with the Poland pool, there have been no complaints (nor was there any evidence) of leakage at the skimmer. Within approximately one and one-half years after installation of the Dodd pool, Dodd began to notice what he thinks is a leak in his pool. The water level in the Dodd pool drops approximately one-quarter inch per day. But the Department's own expert witness conceded that water loss of between one-eight and one-quarter inch can be explained by evaporation. It was not proved that the Dodd pool is leaking at all. If there is a leak causing a small increment of water loss above loss through normal evaporation, the leak would have to be very small and would be very difficult to detect. Ash and others have tried but have been unable to find a leak at the skimmer of Dodd pool. In approximately summer 1985, Dodd himself dug a hole under the concrete deck to expose the bottom of the skimmer assembly. The excavation revealed an unusual amount of moisture that might be the result of a leak at the skimmer. It also revealed that the contractor who poured the Dodd concrete deck did not encase the skimmer assembly as Ash had thought he would. The Department's expert - a professional engineer with a B.S. degree in civil engineering, an M.S. degree in structural engineering and a Ph.D. degree in environmental engineering - gave his opinion that a residential pool skimmer assembly should be either (1) encased with the concrete of the pool shell or (2) encased with deck concrete which is structurally tied to the concrete pool shell. He opined that the latter method would require either a very rough surface on the pool shell concrete or steel extending from the pool shell in order for the structural tie to be accomplished. But he also conceded that it is possible for deck concrete encasing a skimmer assembly to be sufficient to stabilize the skimmer assembly even without taking any extra measures to accomplish a structural tie. There was no evidence that any building code would require a pool contractor to take these measures to accomplish a structural tie between the pool shell and skimmer assembly. Nor was there any evidence that a reasonably prudent pool contractor (as opposed to a professional engineer) would be expected to take these measures. Based on this evidence, together with all the other evidence taken as a whole, the Department did not prove that Ash was either incompetent or grossly negligent in not taking any extra measurers to accomplish a structural tie between the concrete pool shell and the skimmer assembly. Based on the evidence in this case, the contractor Dodd hired to pour the concrete deck was either incompetent or grossly negligent (assuming he was even a licensed pool contractor a fact not shown by the evidence.) He did not encase the skimmer assembly with the deck concrete, allowing it to "float" unprotected in the fill under the concrete deck. Settling of the fill could have caused the deck to settle and crack, moving the skimmer assembly and causing a small leak. Ash may have been able to prevent this by warning the contractor to be sure to encase the skimmer assembly with deck concrete when he poured the concrete deck. But there was no evidence that Ash had a duty to advise the other independent contractor Dodd hired or was responsible for the other contractor's incompetence or gross negligence. Ash's failure to advise the other contractor was not incompetence or gross negligence on Ash's part. Dodd has no other complaints about the pool Ash built for him. Priests' Complaint (Count II). On or about October 11, 1984, Ash contracted with Joseph and Rita Priest to build them a pneumatic concrete pool. The Contract included a warranty that the labor, materials and workmanship would be free of defects for one year and that the shell would be structural sound and capable of holding the water for ten years. Like Dodd, the Priests contracted with another independent contractor to install the concrete deck around the pool. Ash was responsible only for placement of decorative "river rock" on top of the deck. Ash finished his work in February 1985. Like Dodd, the Priests complained of water loss from the pool although the Priests noticed the water loss sooner than Dodd (approximately March, 1985). The water level was dropping approximately one-quarter inch per day more than it was dropping in a bucket used as a control. In response to the complaint, Ash sent his employees to the Priests' pool on several occasions. They found no leak at the skimmer. To determine whether the pool's "caretaker system" 1/ was leaking, Ash's employees plugged all but one pair of the caretaker heads. After waiting a period of days, they would try to see whether the rate of water loss changed. They tested all four pairs of caretaker heads on the bottom of the pool and the pair in the spa attached to the pool. No leaks could be found. They did not replace the last two (in the spa), and Mr. Priest had to replace them. As with the Dodd pool, the Department did not prove that the Priests' pool is leaking at all. The Priests continue to complain of water loss of approximately one-quarter inch per day, within the range of water loss from normal evaporation. As with the Dodd pool, a leak responsible for a small increment of water loss above water loss from normal evaporation would be very small and difficult to find, especially if the leak were in the caretaker heads or pipes under the pool leading to the heads. Now the Priests suspect a water leak at the filter. But the Department's expert witness could not find a leak there large enough to account for much water loss. The minor leak at the filter is a normal maintenance item for a pool as old as the Priests' pool. There was no evidence how long it has existed, and there was no evidence that the Priests ever told Ash there was a leak at the filter. The Priests now also complain that one of the caretaker heads does not re-seat properly. But this has nothing to do with the leakage complaint to which Ash is charged with not reasonably responding. Taken as a whole, the evidence did not prove that Ash committed misconduct or deceit by failing to make reasonable response to warranty service requests within a reasonable time, as charged. Nor does the evidence prove misleading or untrue representations, gross negligence, incompetence or fraud in connection with the Priests' pool, as charged. Poland Complaint (Count III). On or about December 9, 1981, Ash entered into a contract with James Poland to build Poland a pneumatic concrete pool and concrete deck. Poland contracted with another independent contractor to build a screen enclosure around the pool. Before construction began, one of Ash's employees asked Poland to sign an addendum to the contract for an additional $235 to pay for foundation footers required to comply with Lee County building code provisions for the screen enclosures. Before Ash signed the initial Poland contract on December 9, 1981, he was unaware of the Lee County Aluminum Code, adopted March 18, 1981. The code requires eight inch foundation footers for "aluminum additions." Another part of the code addresses "screen enclosures with screen roofs known to the industry as birdcage swimming pool enclosures." The language of the code is not explicit that screen swimming pool enclosures are required to meet the foundation requirements for "aluminum additions," and at first Lee County did not interpret the code that way. With a change of personnel in code enforcement, Lee County began to interpret the code that way, and screen swimming pool enclosures Ash had under construction began to fail building inspection for inadequate foundation footers. Ash inquired why and was told about the aluminum code and how it was being interpreted. Ash argued that the interpretation was erroneous but, failing to dissuade enforcement personnel, began to comply. As part of his compliance efforts, Ash had his employees try to secure the contract addendum from Poland. Poland refused to sign the contract addendum, insisting on an opportunity to verify that the additional foundation footers were indeed new building code requirements. There still is a dispute between the parties whether Poland ever agreed to pay the additional $235 after he verified that the footers were being required. (He never signed the contract addendum.) But, in any event, the evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct in connection with the additional $235 charge. 2/ There was some evidence that Ash did not in fact comply with the Lee County Aluminum Code, as he was told it was being interpreted, in his construction of the Poland pool deck. In two places the foundation footers were 6 and 7 inches - deeper than the four-inch normal thickness of a concrete pool deck but short of the eight-inch requirement. But Ash was not charged with failure to comply with the foundation footer requirement. He had no legally sufficient notice that he should be prepared to defend against that charge and was not prepared to defend against that charge. Therefore, no finding is made whether Ash complied with the Lee County Aluminum Code. Ash performed the Poland contract between approximately January 27 and February 26, 1982. In September, 1985, Poland began to notice that some of the tile Ash installed at the waterline around the perimeter of the pool was coming loose. As explained by the Department's expert witness, the concrete deck settled in places, cracking slightly and rotating over the fulcrum created by the wall of the concrete shell of the pool. The rotating action pulled up on the tile attached to the inside of the pool wall in places, loosening the tile. In all, less than 10 percent of the 77 foot perimeter of the Poland pool experienced problems with loose tile. The loose tile easily can be removed and replaced. The minor deck cracking and loose tile problems at the Poland pool are within the normal range for a competently constructed pool under normal conditions of ground settlement. The evidence did not prove that Ash improperly installed the pool deck or that he was incompetent or grossly negligent in the construction of the Poland pool and deck. Besides the loose tile and minor cracks in the concrete deck, the Poland pool had no apparent defects. There also was evidence that the Poland pool was finished with a coating of marcite on the inside surface of the pool shell which was mottled gray in color instead of white. Poland complained persistently about the marcite3 and insisted that Ash make it white. But the discolored marcite was a factory defect of which Ash had been unable to know before he used it. There is no way to make mottled gray marcite white. Ash tried to explain this to Poland but the customer would not be satisfied. Taken as a whole, the marcite evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct. Nor does the evidence prove any of those violations for failure to cure the marcite problem under warranty. First, as already stated, there was no cure. Second, Ash and Poland also had a running dispute whether Poland had paid the full contract price, including the additional $235 for foundation footers, so as to entitle him to any warranty repairs. In light of this genuine dispute, failure to do warranty work, if otherwise a reasonable request, still could not be found to be misconduct, fraud or deceit.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing the Amended Administrative Complaint that has been filed against Respondent, Wesley Ash, in these cases. DONE AND ORDERED this 9th day of December 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of December, 1986.
Findings Of Fact In 1975 and 1976 John Morris, d/b/a Morris Pool Service, maintained the swimming pool at the Sunland Center in Miami, Florida under a contract with HRS. The contract for the year commencing July 1, 1976 and expiring June 30, 1977 (Exhibit 1) provided generally for Morris to maintain the Sunland Center pool for which he would be paid $520 per month. This contract further provided that a representative of Morris Pool Service check each day except Saturday and Sunday with Ms. O'Donohue, the Director of Training, or her successor. Recreation personnel at Sunland Center hoped to open the pool on Memorial Day; however, an impeller for the pump needed replacement and the pool was inoperative for some six weeks in May and June awaiting this part. During this time petitioner did little or no maintenance and the pool's condition was bad enough for the Superintendent to become involved and request a report from the Programs and Services Director (Exhibit 4). When the impeller did arrive in mid-June, 1977, the pool was in such bad shape it was necessary to drain the pool, scrub, and acid-wash the walls and floor of the pool to remove the accumulated algae and scum. Even a colony of frogs had taken up residence in the pool during this period. As a result of additional delays the next hoped-for opening date of July 4 was also missed. The pool was finally ready for operation and was opened the week following July 4, 1977. Although opened the water in the pool was not properly maintained by cleaning and chlorinating. In the latter part of July the gas chlorinator became inoperative and the pool's condition deteriorated as no chlorine was being added to the water. Under the contract Petitioner was to provide materials necessary to keep the pool water in a balanced condition. This contract expired on June 30, 1977. Nevertheless, Petitioner purported to continue working under the expired contract, pending the issuance of a new contract for 1977-1978. While the gas chlorinator was inoperative Petitioner did not hand-feed chlorine to the pool to maintain the proper chlorine level and to keep algae from growing. By early August, 1977, the pool had become so bad the supervisory personnel at Sunland Center called the Dade County Health Department to inspect the pool. A report of that inspection showing the pool unfit for use was admitted into evidence as Exhibit 3. Following the Superintendent's inquiry to Ms. Titus about the condition of the pool in June, 1977, she contacted Petitioner, who told her the pool would he hack in operation as soon as the impeller was received. Ms. Titus was the successor to Ms. O'Donohue and she told Petitioner to keep her advised regarding the status of the pool. Although the contract (Exhibit 1) required Petitioner to report to Ms. Titus daily (except Saturday and Sunday) she did not see him again, nor did she receive any report that he came to her office. Petitioner contends that he attempted to report to Ms. Titus but was unable to find her in her office and after a few attempts stopped trying. Ms. Titus and her assistant were both equipped with beepers and could be contacted any time of day by their office if they were out of the office. Following the Health Department's inspection on August 9, 1977, the pool was closed for several days, then reopened around mid-August after the chlorinator was repaired. When the pool was reopened in August its condition was barely satisfactory. Shortly after Labor Day the pool was again closed and remained closed throughout the balance of 1977. By October, the Sunland Center officials decided they should notify Petitioner that his contract would not be renewed for the 1977-1978 year and a letter dated October 27, 1977 (Exhibit 2) was forwarded to him by registered mail. This letter was mailed to an old address for Petitioner, was returned to the sender and remailed to the proper address. As a result, the letter was not received by Petitioner until December 14 or 15, 1977. Petitioner submitted bills to Respondent for services for the period July 1, 1977 through December 15, 1977, the approximate date he received Exhibit 2. Following August 10, 1977 some of Respondent's employees in the maintenance department saw Petitioner in the cafeteria at Sunland Center and on the premises, but none of them reported seeing Petitioner do any work on the pool. Petitioner contends he worked on the pool on a daily basis, however, the condition of the pool casts serious doubts on this testimony.
The Issue The issues presented for decision herein are whether or not Respondent failed to properly supervise a pool construction project, willfully violated local laws, is guilty of gross negligence, incompetence, misconduct, fraud or deceit in the practice of contracting and failed to discharge his supervisory duties as a qualifying agent in violation of sections 489.129(1)(d), (m), (j), and sections 489.119 and 489.105 (4), Florida Statutes.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I make the following relevant factual findings. At all times material hereto, Respondent was a registered pool contractor in Florida, holding license no. RP0015329 and served as the qualifying agent for Paradise Pools, Inc. (Request for Admission, responses 1- 4). Petitioner is the regulatory agency in Florida charged with the authority to regulate contractors and to determine compliance with applicable state and local building code requirements. On May 31, 1986, Respondent entered into a contract with Alex and Theresa Nitu for the construction of a swimming pool at the Nitu's residence at 9550 Lisa Road in Dade County, Florida. The following day, the Nitus were approached by John Davis, a partner of Paradise Pools, Inc. Davis identified himself as the owner of Paradise Pools and told the Nitus that Respondent was the company salesman. Davis is not a licensed contractor. During construction, Davis supervised the work for the Nitus' pool. Mrs. Nitu was ill and remained at home on the day the workers laid reinforcing steel for the pool shell. Mr. Nitu, an electrical contractor, took off work and was at home during the two days when the gunite work was done for their pool. Respondent was not present on the job site on those days. The day after the concrete deck was poured, the Nitus noticed that it contained several low spots which collected water and that rocks were protruding through the deck's surface. Additionally, a portion of the deck sloped toward the pool rather than away from it. The following day, the Nitus returned home from work to discover that the "whitecoat" for the deck surface was completed and their water hose, weighted down by a rock and a rag, was filling the pool. The pool was filled with water before the Nitus had completed a fence to secure the pool. At Mr. Nitu's request, James Tucker, a Dade County Building Inspector, inspected the pool on August 6, 1986. Tucker issued a notice of violation to Respondent for allowing water to be put in the pool without proper safety barriers in contravention of section 33-12, Dade County Code; for allowing the deck to slope toward the pool in contravention of section 5003.1 of the South Florida Building Code and for using concrete of less than 2500 psi strength in contravention of section 5003.1(a), South Florida Building Code. In an attempt to correct the low spots and improper slope of the patio, Davis poured an additional layer of cement over the pool deck and scored the surface to create the appearance of keystone. Thereafter, the Nitus discovered hollow areas under certain parts of the keystone. Eventually, the keystone began to separate from the original deck exposing large areas of the deck. Ben Sirkus was tendered and accepted as an expert in pool construction. Sirkus inspected the Nitu's pool on September 24, 1987, at Petitioner's request. Sirkus observed low spots in the pool deck which held water and contributed to the growth of algae. He also observed that large areas of the imitation keystone had separated from the original deck; that portions of the deck still drained towards rather than away from, the pool; that coping mortar had been left on the sides of the coping and the pool shell; that areas of the whitecoat were unusually rough and that the pool pump was off level, which in time could cause scoring of the bearings in the pump. Sirkus opined that the deficiencies observed could not have gone unnoticed by a pool contractor of average skill and ability; that deficiencies indicate poor supervision or gross negligence or that Respondent exhibited incompetence in contracting for the Nitu's pool. John Davis, Respondent's partner and the person who was usually on the site during all facets of the construction, credibly testified that when the angles were laid out for the sloping of the decks surrounding the Nitu's pool, Alex Nitu requested that his employees angle the deck toward the pool such that it would mesh with his patio. This required that Respondent's employees reslope the angles in accord with Mr. Nitu's wishes and contrary to the manner in which they originally sloped the deck. Mr. Davis also attempted to correct the problems that had surfaced surrounding the deck in accordance with the concerns expressed by the Nitus. However, the Nitus vehemently refused access to Respondent's employees and the matter therefore, remained unresolved. Respondent Reise was at the construction site on numerous occasions during the major facets of the construction. In addition to being the principal salesman for Paradise Pools, Respondent Reise has extensive experience in the construction of pools and frequently consulted with his partner, John Davis, about the ongoing construction of the Nitu's pool. Respondent Reise also attempted to gain access to the pool to attempt to correct the problems and other concerns expressed by the Nitus, to no avail. In this regard, a meeting was held at the Nitu's residence on January 30, 1987, by Jim Tucker and Robert Denery, employees of the Dade County Building and Zoning Department, a Mr. Wolf, Petitioner's investigator, Respondent and his partner, John Davis. After a lengthy discussion, it was agreed that all problems were to be resolved which included (1), repair and patch the keystone on the east end of the pool and (2), rework the slope on the northside of the pool to pitch away from the pool and (3), submit test results from an engineering test lab as to the structural strength of the patio slab and final approval by the electrical and plumbing departments of Dade County. Respondent agreed to correct the above-referenced items and agreed to do so as quickly as feasible. The Nitus refused to allow Respondent's employees back on the site to correct the problems. (Respondent's Exhibit 1). John Davis and Respondent's other employees denied that they started filling the Nitu's pool prior to the time that the Nitus had completed a fence to secure it. Their denial in this regard is incredible and is not worthy of belief. The Nitus, in this regard, credibly testified that they were at all times concerned about the safety of the pool and would never have started filling it prior to the time that it was secured. Respondent's employees, on the other hand, were in fact interested in completing the job and it is therefore believed that they started the water running into the pool and weighted the hose down with a rock and a rag as the Nitus found it when they returned home from work on the day that the "whitecoat" was completed. In all other respects, based on the Nitus' failure to permit Respondent's employees to return to the site to complete the deficiencies and other concerns noted, the undersigned finds that Respondent should have been afforded an opportunity to correct such deficiencies and cannot be held liable 1/ for the allegations that he improperly sloped the pool deck, used improper concrete or was otherwise negligent, incompetent, engaged in misconduct and other allegations of improper supervision, as alleged. I shall so recommend.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: Respondent be assessed an administrative fine in the amount of $250.00. Respondent be issued a written reprimand for allowing his employees to fill an unsecured pool in violation of the local building code. DONE and ORDERED this 16th day of September, 1988, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of September, 1988.
Findings Of Fact Respondent is the holder of currently active General Contractor's license No. RG-0023888. On January 18, 1977, Norwood W. Hope (hereinafter "Developer") entered into a contract with Respondent for the construction of a commercial swimming pool. Respondent was to have been paid the amount of $43,346.40 under the contract for construction of the pool. The contract amount was to be paid pursuant to a five-stage draw schedule as follows: 1. Framing and steel draw paid $10,836.60 2. Gunite draw paid 10,836.60 3. Mancite draw 7,224.40 4. Equipment set draw 7,224.40 5. Final approval draw 7,224.40 Respondent made application for an Alachua County building permit for the swimming pool project on February 23, 1977. The permit application was approved on February 25, 1977, and a building permit was issued. Thereafter, the project received Alachua County approval on a temporary power pole inspection on June 1, 1977. An interim inspection of the property was made by Alachua County officials on November 7, 1977, with no deficiencies noted. A final inspection on the electrical work on the project was made, with satisfactory results, on November 8, 1977. The Alachua County Building Code, by incorporation of the 1973 Southern Standard Building Code, 1974 Revision, provides, in part, as follows: 108.2--INSPECTIONS REQUIRED The Building Official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building or structure upon completion, prior to the issuance of the Certificate of Occupancy, as required in Section 109. * * * (c) The Building Official upon notifica- tion from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit bolder or his agent wherein the same fails to comply with the law: * * * Final Inspection: To be made after the building is completed and ready for occupancy. (Emphasis added). The contract entered into on January 18, 1977 between the Developer and Respondent called for Respondent to construct the swimming pool according to the plans and specifications admitted into evidence as Petitioner's Exhibit No. 1. Associated construction, including construction of concrete pool decking, a pumphouse and a fence surrounding the swimming pool site were either completed by the Developer or by other sub contractors. By invoice dated October 12, 1977, Respondent requested a final draw on the project in the amount of 87,000, which, if paid, would have left only $224.40 unpaid under the contract. This draw request indicated that a balance due for extra time and materials would be billed ". . . upon acceptance of total pool." (Respondent's Exhibit No. 4). On October 25, 1977, the Developer paid $6,000 of the $7,000 requested to be paid by Respondent's invoice of October 12, 1977. The Developer contested Respondent's expressed intention to bill for additional time and material, asserting that the Developer had not approved any additional sums for extras. In remitting the $6,000 payment to Respondent, the Developer indicated that "[t]his leaves a balance on our account of $1,224.40, which will be paid upon checking out the pool." (Respondent's Exhibit No. 2). (Emphasis added.) An invoice for back charges on the swimming pool project in the amount of $274 was forwarded to the Developer by Respondent by invoice dated November 8, 1977. In addition, on November 8, 1977, Respondent also invoiced the Developer for a final draw on the project in the amount of $1,224.40. At some time after notification from the Developer's representatives that tile targets in the racing lanes of the pool were improperly located, Respondent returned to the job site after November 9, 1977 to relocate the targets. Respondent performed this work as a result of a written request from the Developer dated November 9, 1977. Respondent completed primary construction of the pool prior to submission of the final draw request of October 12, 1977. At that time, back- filling around the exterior of the pool structure preparatory to the pouring of the concrete pool decking had not been completed. Although by October 12, 1977, Respondent had removed much of the excess dirt and debris from around the edges of the pool. There were still areas of exposed piping which would, in due course, be covered with back-fill and tamped by the decking subcontractor. Respondent did not attempt to back-fill or tamp any areas around the pool's piping system. At some time subsequent to October 12, 1977, which date is not clearly reflected in this record, a separate sub- contractor completed back-filling work around the pool, and poured the concrete decking. Neither the Developer nor his subcontractor advised Respondent that the back-filling had been accomplished and that the deck was to be poured. Prior to October 12, 1977, Respondent "pressure tested" the pool's piping system, and determined that the pool would hold water at a level above its scum gutters. The results of this testing indicated that, at least as of October 12, 1977, there was no leakage from the pool. Standard practice in the pool construction industry dictates that a minimum of three pressure tests be made of a pool's piping system during the course of construction. The first of these tests should occur immediately after installation of the pipes, and a second test should be performed immediately before final back-filling to cover the pipe system. A final pressure test should be conducted after tamping of the fill and prior to the pouring of concrete for the pool deck. The obvious purpose of this system of pressure testing is to discover any water leaks before concrete pool decking is poured to avoid having to cut out sections of the concrete in order to locate leaks. Because the Developer and his subcontractor failed to notify Respondent of further work being done on the pool. Respondent was unable to perform a pressure test either after back-filling was completed, after the back- fill had been tamped and before the concrete deck was poured. By letter dated January 17, 1978, Respondent was furnished by the Developer with a "punch list" indicating several areas of deficiency that needed to be corrected in the pool. In that letter the Developer requested that Respondent complete the necessary work within seven days. The Developer forwarded a second letter to Respondent dated February 23, 1978 advising Respondent that the punch list items had not been corrected, and urging Respondent to complete the work described in the punch list as soon as possible. From receipt of the punch list in January of 1978 through the middle of March, 1978 Respondent had workers on the job intermittently making the corrections indicated in the punch list. Respondent satisfactorily corrected fifteen of the eighteen items listed as defective n the punch list. Some of the items were repaired by other subcontractors. Respondent had difficulty obtaining some items of equipment, which he was required to back-order. When the back-ordered equipment was slow in arriving, the Developer opted to obtain these items from a source other than Respondent. Respondent replaced a defective pump associated with the pool construction at some time subsequent to January 18, 1977. The last work performed by Respondent on the pool project occurred some time between March 10 and March 16, 1978. At no time thereafter was Respondent ever advised by the Developer that any work performed under the contract was either unsatisfactory or incomplete. The pool received a final State of Florida, Department of Health and Rehabilitative Services inspection on July 13, 1978, at which time all necessary permits for operation of the pool under applicable regulations were issued. Respondent at no time requested that Alachua County officials come to the job site to conduct the necessary final inspection of the project, nor did he advise the Developer of the necessity to do so. At some time during 1979, subsequent to the completion of the swimming pool project, the Developer discovered that the pool was losing water at a rate of approximately 2,100 gallons per day. During this period, the water level inside the pool would drop to a level equal to the piping running around the exterior of the pool shell and under the pool decking. When the Developer was unable to ascertain the cause of the leak, an outside subcontractor was hired to check the pool. This sub- contractor performed pressure tests on the pool's piping system in an attempt to determine whether the leakage was occurring through the pipes. These tests apparently showed no leakage through the piping system. The Developer then caused the concrete decking around the edge of the pool to be removed in order to more closely inspect the interior piping. At this point it was discovered that there existed flaws and breaks in the neoprene piping surrounding the exterior shell of the pool. After repairs to the damaged piping, the pool decking was repoured and there has been no subsequent leakage problem in the pool. The Developer incurred expenses in the amount of $2,288 in removing the decking around the pool and repairing the neoprene piping. Because of the fact that several subcontractors in addition to Respondent worked in the pool area during construction of the pool project, it is impossible on the basis of this record to determine the cause of the damage to the neoprene piping. Respondent's testimony is uncontroverted that pressure testing performed prior to the conclusion of primary work on the pool in October of 1977 showed no leakage through the pool's piping system. Further, at the conclusion of the primary work in October, 1977, much of the pool's piping system was left exposed and could have been damaged either by the Developer's own workers or by employees of other subcontractors in the course of back- filling and tamping fill material preparatory to pouring concrete decking. The Developer's failure to advise Respondent of the schedule for back-filling, tamping and pouring of concrete deprived Respondent of an opportunity to properly pressure test the piping system at appropriate stages of construction. Respondent has submitted proposed findings of fact for consideration by the Hearing Officer. To the extent that those proposed findings of fact are not incorporated in this Recommended Order, they have been rejected as being either irrelevant to the subject matter of this proceeding or as not having been supported by the evidence.
Findings Of Fact The parties stipulated that Petitioner's Exhibit number 1, which is the Florida Construction Industry Licensing Board official records as they relate to Millard P. Hill, Jr., should be received into evidence. The parties noted further that there is little dispute as to facts, however, the Respondent contends that there is no diversion of funds based on the facts of this case. On June 10, Respondent advised Petitioner that he wished to qualify Master Pools, a corporation which he had applied to Petitioner to qualify as the name under which his pool contracting would be done to reflect the name H. B. Patten, Inc. as the name under which said contracting would be done. Petitioner changed its records to show this change. On July 12, Respondent entered into a contract with Manuel and Anna Bueno for a pool to be built at 6960 Northwest 4th Place, Margate, Florida, for a sum of $5,665. See Petitioner's Exhibit number 2 received into evidence and made a part hereof by reference. Anna Bueno testified that a hole was dug and tar paper and steel bars were erected in the hole and the work was abandoned thereafter. Prior to abandonment, the Bueno's paid approximately $4,100 to Patten Pools. To complete the construction, the Bueno's used Hallmark Pools to finish the pool which required an additional sum of approximately $5,000. As can be seen, this is approximately $3,300 over and above the contract price. The evidence also reveals that Patten Pools, Inc., through Millard P. Hill, applied for and obtained a permit for the construction of the pool for the Bueno's on August 5. See Petitioner's Exhibit number 3, received into evidence and made a part hereof by reference. On April 24, Mr. and Mrs. Edward Eskie entered a contract with Respondent for the erection of a swimming pool on their property located at 1525 Southeast 14th Court, Deerfield Beach, Florida for $6,786.00. See Petitioner's Exhibit number 4 received in evidence and made a part hereof by reference. Mr. Eskie testified that the excavation for the pool began on May 20, and on June 2 gunite services were complete. On July 9, he received a letter from Crockett- Bradley, Inc. a gunite subcontractor, indicating that it was filing a lien for $1,312 against the Eskie's property for services performed. The building permit for the Eskie project was obtained by Respondent on June 10. See Petitioner's Exhibit number 7 incorporated herein by reference. Edward Eskie paid Respondent approximately $4,778 and $1,312 was paid to Crockett-Bradley, Inc. to satisfy the lien which was placed against their property. The Eskie's completed their pool by payment of an amount in excess of $4,000 to another pool contracting firm. Prior to completing the pool and after the Respondent abandoned the project, Edward Eskie made numerous attempts to contract Respondent by phone to no avail. On June 27, Respondent entered a contract with Orlando Gonzalez for a pool to be built at his residence located at 353 Northwest 22nd Street, Boca Raton, Florida for $9,000.00. See Petitioner's Exhibit number 8 which was received and made a part hereof by reference. Orlando Gonzalez paid Respondent $3,600 through his bank toward the contract price. For that payment, Respondent dug a hole and the project was abandoned. After work was abandoned, Gonzalez made repeated attempts to contact Respondent to no avail. To complete the project, he paid another contractor approximately $6,000. On April 18, Respondent entered into a contract with Howard and Sheila Siclari for a pool to be built at their home located at 7812 Northwest 67th Avenue, Tamarac, Florida, for the sum of $4,280. To commence the construction, Respondent obtained a building permit on June 18, 1975. See Petitioner's Exhibits number 9 and number 10 received in evidence and made a part hereof by reference. The Siclari's paid Respondent $3,456.75. Thereafter they completed the work which cost them an additional $2,500 and they did most of the work themselves. James T. Anglen, a pool salesman for Patten Pools testified that he was initially employed by Master Pools until June, 1975. A reference to Petitioner's Exhibit number 1 indicates that Master Pools registered as Brian Sales Corporation as the first entity that Respondent registered with Petitioner on January 1, 1974. He was a superintendent of Patten Pools in June, 1975 when he commenced employment with Patten. He acknowledged that he received money from the Bueno's which was transmitted to Patten Pools. He also acknowledged that the Bueno's were probably hurt most of all the complaining parties in this case. Respondent discovered that its cash flow was short approximately $40,000 to $50,000 and that that amount in checks were floating with insufficient funds to cover them. He commenced efforts to try to straighten out the firms cash flow and that for a while the bank worked along with him. Anglen also acknowledged the abandonment of the Gonzalez project. He further acknowledged that monies received from projects were used to cover deficiencies on other projects to continue Respondent's operations.
The Issue The issue in this case is whether the Respondent, Dominick A. Solitario, committed the offenses alleged in the Amended Administrative Complaint and, if so, what disciplinary action should be taken.
Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. At all times pertinent to this proceeding, Respondent, Dominick Solitario, was licensed as a certified pool contractor in the state of Florida, having been issued license no. CP CA17558. At all times pertinent to this proceeding, Respondent was the licensed qualifying agent for Jade Pools, Inc. Sometime around February of 1988, Respondent contracted with Michael and Linda Skidd to remarcite the swimming pool at the Skidd's home in Coral Springs, Florida. The contract price for the remarciting of the Skidd's pool was $2000.00. Respondent has been paid in full for this work. There is no evidence that there were any leaks in the Skidd's pool prior to the time the work was undertaken by Respondent. At the time the work was begun, one of the Respondent's employees discovered an expansion plug that had been inserted in the main drain. The employee inquired as to whether the Skidds had experienced any problems with the drain. The Skidds denied having any problems. The evidence presented at the hearing was inconclusive as to whether the main drain was working properly. At the time the Respondent began work under the contract, the Skidds were using a "creepy crawler" to clean the pool. This device required the main drain to be shut off. While Mrs. Skidd testisfied that she thought the main drain was working properly, she admitted that her husband was more familiar with the cleaning and mechanical aspects of the pool. Mr. Skidd did not testify. Respondent contends that Mr. Skidd was present at the time the plug was removed from the main drain and that the condition was brought to his attention. However, it does not appear that either Respondent or Mr. Skidd knew why the drain was plugged or the significance of the situation. Respondent proceeded with his contractual work without conducting any tests to determine whether there was a leak in the main drain. When the work was completed, the workers directed the Skidds not to use their main drain. No explanation was given for this instruction. After the work was completed, the Skidds turned on the main drain and lost approximately four inches of water from the pool in a relatively short time. The Skidds turned off the drain and called Jade Pools. An employee of Jade Pools came out and inspected the premises. He advised the Skidds not to use the main drain, but instead to use their "creepy crawler." The Respondent's employee indicated that there was a leak in the main drain. It is not cler how he reached that conclusion. In order to complete the work on the Skidd contract, Respondent's employees were required to install a pressure release valve near the pool's main drain by drilling through the bottom of the pool. The hole for this valve was drilled several inches away from the main drain and its plumbing. Petitioner suggests that the Respondent's employees may have punctured the main drain or its plumbing when this hole was drilled. However, no persuasive evidence was introducted to prove this allegation. Respondent contends that the pool was improperly constructed and/or that the main drain line had been previously damaged and plugged shut to avoid detection of the leak. In order to perform the contracted work, Respondent's employees unplugged the drain and the alleged preexisting leak became evident. Respondent has inserted a plug into the main drain and claims that the pool is now in the same condition it was when he began his work. Respondent has refused to repair the main drain or perform any additional work unless he is paid for it. At the time that Respondent first proposed to enter into a contract with the Skidds, he was told by the Skidds that there was a suction leak at the pump. In retrospect, Respondent contends that this suction leak confirms the preexisting problem with the main drain. No conclusvie evidence was presented to establish why the pool is leaking. As of the date of the hearing, the Skidds are still unable to use their main drain. The Petitioner did not present persuasive evidence to establish that Respondent was responsible for the leak in the Skidds' pool. While it is possible that the Respondent's employees caused the leak when they drilled the hole for the pressure release valve, an equally likely explanation is that there was an existing problem that had been obscured by the prior plugging of the main drain. On or about June 29, 1987, Respondent contracted with Anthony Gallagher to construct a swimming pool and a deck at Mr. Gallagher's home in Coral Springs, Florida for the contract price of $17,800.00. Respondent has been paid in full for this work less $100 for damage caused during construction. The contract with Mr. Gallagher called for Respondent's company to top the existing patio slab and tie it into a newly added patio deck surrounding the pool. The building permit for this work was pulled by Jade Pools. Although the work on the Gallagher deck and pool was completed sometime in late 1987 or early 1988, the pool and deck have still not passed final inspection by the City. The local building officials have refused to approve the final inspection on the Gallgher's deck because of the excessive slope from the back of the house to the pool. The pitch of the deck constructed by Respondent's company from the back of the Gallagher's house to the pool is very severe, effectively rendering a portion of the deck unusable. A table cannot sit flat on this portion of the deck because of the slope. The Respondent's construction of a deck with such a severe slope that it is incapable of passing final inspection constitutes incompetency in the practice of contracting. In order to provide a usable deck, Respondent should have ripped out the existing deck or placed the pool at a higher elevation. Respondent contends that his contract did not call for him to rip out the existing deck, but only to top it. He claims the existing deck that was topped had a similarly severe pitch. Nonetheless, Respondent is responsible for insuring that his final product is functional and able to pass inspection. Respondent has failed to take any remedial action to obtain a successful final inspection. During construction, the Gallaghers, on several occassions, expressed displeasure with the deck and its excessive slope in some areas. On two occasions, Respondent sent his workmen out to correct certain aspects of the construction that the Gallaghers found unacceptable. Ultimately, the homeowners paid the Respondent in full and instructed Respondent to stay off their property. Although Respondent's presentation was somewhat unclear, he appears to argue that these actions by the Gallaghers relieve him of any liability for his work under this contract. However, the evidence established that the Respondent was never able to obtain a successful final inspection of his work at the Gallagher home. This failure is the direct result of the excessive pitch in the patio he constructed. While the Gallaghers have paid the full amount of the contract and are apparently using the pool and patio, these facts do not relieve Respondent from responsibility for the incompetently constructed deck. The City of Coral Springs requires a deck electrical inspection to insure that all the steel in the deck is on the same electrical field (same electrical bond) as the pool. Jade Pools failed to call for this electrical bond inspection before pouring the Gallagher's deck. Ultimately, the city building officials required the Respondent's company to expose a portion of the steel in the deck to confirm that the pool was properly bonded. This test indicated that the pool was in fact properly bonded. On or about August 10, 1988, Respondent contracted with Kevin Fusco to construct a swimming pool and deck at Mr. Fusco's home in Boca Raton, Florida for a total contract price of $10,030.00. Respondent has been paid in full under this contract. Jade Pools obtained the building permit for the Fusco's pool. Therefore, Respondent's company was responsible for obtaining all of the inspections for the construction, including the final inspection. Prior to the time that work was begun on the Fusco contract, Respondent's employees inspected the property and were advised as to some existing problems with drainage in the backyard of the house. The Fusco's lot was designed to drain from back to front. A berm runs behind the Fusco property and causes water to drain through the backyard. On some occasions prior to construction, this drainage situation resulted in standing water against the back of the house. The installation of the Fusco's pool seriously affected the drainage plan for the property. After the pool was installed, there was often standing water all around the deck following a rain. After construction was started and the deck was formed out, the county refused to give approval for pouring the deck because of anticipated problems with drainage in the backyard. One of Respondent's employees advised the Fuscos that if they removed approximately three feet of soil from around the deck, the county would allow them to proceed with pouring the deck. Based upon this recommendation, the Fuscos entered into a contract with a company recommended by Respondent. That company removed approximately six or eight feet of soil all around the deck and installed a rock bed in the area. The cost of this removal was in addition to the contractual price agreed to between Respondent and the Fuscos and was borne by the Fuscos. As indicated above, the installation of the pool greatly exacerbated the drainage problems that previously existed on the property. Respondent did not warn the homeowners prior to construction to expect this result nor did the Respondent take steps to preclude these additional drainage problems. While Respondent contends that the Fusco's property was inappropriately graded prior to the time the work was initiated, Respondent never brought this fact to the attention of the homeowners until after the pool was installed and the increased drainage problems became evident. After the work was completed, the county inspectors advised the homeowners that the pool did not pass final inspection because of drainage problems caused by the pool and deck. By the time the Fuscos found out the pool had not passed final inspection, Respondent had been paid in full under the contract. The Fuscos contacted Jade Pools, which refused to take any corrective action. The Respondent claimed that drainage problems were not part of his company's responsibility and refused to return to the property to correct the problem even though the pool had not passed final inspection. The Fuscos hired an engineer to design an acceptable solution to the drainage problem and arranged for the completion of the work at their own expense. In accordance with this solution, the homeowners installed a series of french drains around the back yard in order to try to get the water to percolate into the ground. After this additional work was completed, the pool passed final inspection by the county. It was approximately one year after Jade Pools finished its work before the final inspection was passed. The Fuscos continue to experience increased drainage problems on their property as a result of the installation of the pool and deck. These problems include standing water around the deck after a heavy rain and, in some instances, an overflow of water into the pool. While the Respondent was installing the Fusco's pool, Respondent was concurrently installing a pool at the house next door. There has been no drainage problems on the property next door because the elevation on that house is higher. The Fusco's pool was actually installed at a level that was at or below the surrounding ground level. The problems associated with such an installation were never explained to the homeowners prior to the time the work was commenced. Respondent contends that this situation was necessary because of the existing elevations of the house and lot. He says that the pool and deck had to be installed in a manner that provided a four inch step down from the house and also matched the existing slab. The drainage problems could have been minimized by swaling out from the pool area to the side of the house. While Respondent contends that such "landscaping" efforts were not part of his contract, he should have not undertaken the work unless he could adequately deal with the drainage problem and ensure that the final installation would pass inspection. The pool contractor is responsible for insuring that, after the pool is built, proper drainage is obtained around the pool. The efforts undertaken by the Respondent were insufficient to deal with the resulting drainage problems and constitute incompetency in the practice of contracting.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violations of Section 489.129(d) and (m), Florida Statutes, in connection with the Fusco and Gallagher contracts, issuing a reprimand and imposing a fine on Respondent in the amount of $2,000.00 for having committed these violations. In addition, Respondent should be placed on probation for two years and required to reimburse the Fusco's for the money they have expended to correct the drainage problems caused by Respondent. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 8th day of February, 1991. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of February, 1991.
Findings Of Fact The Petitioner is the Department of Professional Regulation. The Respondent is Phillip Whitaker, Jr., holder of certified pool contractor license number CP-C008325 at all times pertinent to these proceedings. He is the qualifying agent for the business known as Sunshine State Pools pursuant to requirements of Chapter 489, Florida Statutes. He is responsible for actions of that business relating to construction of the swimming pool which is the subject of this proceeding. His address of record is Miami, Florida. The customer, Ken Gibson, signed a contract with Sunshine State Pools on September 15, 1986. The contract called for construction of a residential swimming pool at 15840 S.W. 155th Avenue, Miami, Florida. The total contract price was $12,700. Testimony adduced at hearing establishes that Sunshine State Pools completed the layout of the customer's swimming pool and the excavation of soil from the proposed pool site by October 1, 1986. These tasks were accomplished under the Respondent's supervision. Metropolitan Dade County issued a building permit for construction of the swimming pool in response to a permit application bearing the signature of Phillip E. Whitaker. The permit and application are both dated October 10, 1986. At hearing, the Respondent acknowledged that initiation of construction prior to pulling the permit and termed this action an "oversight." Based on the candor, demeanor and experience of the Respondent, his explanation of the failure to timely obtain the construction permit is not credited. Initiation of construction for a swimming pool prior to obtaining permits constitutes a violation of part 301.1(n), of the South Florida Building Code and, by stipulation of the parties at hearing, the building code of Metropolitan Dade County. The Respondent was responsible for supervision of the actual pool shell construction. After completion and removal of the wood forms used in the process, steel rods or "rebar pins" required as support during the construction process were not removed. These rods extended some distance above the ground and posed a substantial hazard to Respondent's children while playing. Finally, the steel rods were removed by the customer a week after he requested the Respondent to remove them. Respondent admitted some of these reinforcements could have been left by his subordinates. Respondent admits responsibility for the "back fill" process completed on October 25, 1986. This was originally a responsibility of the customer under the contract as the party responsible for deck construction. The "back fill" process consists of compacting loose soil between the outside of the pool walls and surrounding earth by use of special tamping or pounding equipment. Under terms of the contract, the customer was responsible for construction of a sizeable two part deck surrounding at least sixty percent of the pool's circumference. There now exists a substantial height difference between the coping surrounding the perimeter of the pool and the deck or patio surface. The coping is elevated above the top of the patio approximately two to four inches. As adduced from testimony of Ben Sirkus (stipulated by both parties as an expert in swimming pools and swimming pool construction), coping along the top of the pool walls consists of flagstone rock in conformity with the contract terms. Some of the rocks are cracked. The rocky edge of the coping extends over the pool wall and has a dangerously sharp edge. The sharp edge of the coping overhang could have been avoided by cutting the flagstone coping smooth prior to installation, the acceptable practice among pool contractors. The bottom step to one set of the pool steps has a hazardous 19 inch riser as opposed to the 12 inch distance required by the building code. No hand rail is present. Hollow space under some of the coping stones are the result of either improper installation, dirty cement or sinking of the deck as a result of improper "back filling" upon completion of the pool shell. On one occasion, Respondent admitted responsibility for deficiencies in the pool coping to an employee named Rick Miro. The Respondent further stated to this employee that he intended to do nothing about the problem. Respondent was present during some, but not all, of the coping installation. The "skimmer," the apparatus by which debris is cleared from the pool water, is inoperable as a result of faulty construction of the pool. The failure of the Respondent, who admits to successful completion of approximately 2500 pools with only three complaints, to properly supervise job site activities was the major cause of the pool deficiencies identified at hearing.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be placed on probation for a period of two years upon such terms and conditions as may be determined by the Construction Industry Licensing Board and assessed an administrative penalty in the amount of $1500. DONE AND RECOMMENDED this 29th day of February, 1988, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of February, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-5053 The following constitutes my specific ruling on proposed findings of fact submitted by the parties. Petitioner's Proposed Findings Included in finding 2. Included in finding 3. Included in finding 4. Included in findings 5, 6 and 7. Included in findings 5 and 6. Included in finding 8. Included in finding 10 with exception of hearsay statement. Included in finding 11.1 Included in finding 12. Included in finding 11. Included in finding 11. Included in finding 11. Included in finding 11. Rejected as unnecessary. Rejected as unnecessary. Included in finding 11. COPIES FURNISHED: David L. Swanson, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark D. Press, Esquire 2250 Southwest Third Avenue 5th Floor Miami, Florida 33129 William O'Neil General Counsel 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 =================================================================
The Issue Whether the claimants herein are entitled to payment from the Construction Industries Recovery Fund and, if so, the amount of the payment to which each claimant is entitled. Whether the license of the Petitioner is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998).
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Fund is established by Section 489.140, Florida Statutes, for the purpose of reimbursing those persons who meet the eligibility requirements set forth in Section 489.141, Florida Statutes. The Board is the entity responsible for reviewing applications for payment from the Fund and entering orders approving or disapproving the applications. Sections 489.140(1) and 489.143(1), Florida Statutes. Mr. Kiselius is a licensed residential pool/spa contractor, having been first issued such a license in 1984. Mr. Kiselius's license is currently on inactive status, but at the times material to this action, Mr. Kiselius's license was active. Pool Masters was a Florida corporation incorporated on August 10, 1995. Frederick H. Martin and Abraham Zafrani were the sole shareholders of the corporation, and Mr. Martin was the President and Secretary of the corporation, and Mr. Zafrani was the Vice-President and Treasurer. From on or about October 24, 1995, until November 14, 1997, Mr. Kiselius was the qualifying agent for Pool Masters. The record does not reflect the date on which Pool Masters was issued its certificate of authority allowing it to engage in contracting as a business organization, but it was assigned Qualified Business Organization License Number QB0002327 on or about November 6, 1996. Pool Masters filed for bankruptcy pursuant to Chapter 7 of the United States Bankruptcy Code on January 1, 1998, and the corporation was administratively dissolved on October 16, 1998. DOAH Case No. 99-1665: Santibanez and Pappas Eugene Santibanez and Alexander Pappas entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 25, 1997. The total price stated in the contract was $21,000.00; a change order was executed on November 4, 1997, for an additional price of $2,890.00. Pool Masters represented to Mr. Santibanez and Mr. Pappas that it was a licensed swimming pool contractor. Pool Masters began work on the pool on or about May 17, 1997. Mr. Santibanez and Mr. Pappas made payments to Pool Masters pursuant to the contract, and Pool Masters excavated the hole for the pool, put in the foundation, and poured the concrete. Pool Masters ceased work on the swimming pool in late November 1997, after the concrete was poured. A week later, Mr. Santibanez heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. Santibanez and Mr. Pappas had paid Pool Masters a total of $19,690.00 for work done pursuant to the contract and change order. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. At least one lien was filed against Mr. Santibanez's and Mr. Pappas's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Santibanez and Mr. Pappas submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Santibanez and Mr. Pappas to file suit against Pool Masters. Mr. Santibanez and Mr. Pappas filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Santibanez and Mr. Pappas alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 3/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 4/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 5/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 6/ ] Mr. Santibanez and Mr. Pappas further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $17,975.50, and they included in the complaint an itemized list of expenditures to support their claim. The circuit court entered a Default Final Judgment on August 4, 1998, awarding Mr. Santibanez and Mr. Pappas $17,675.50, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Santibanez and Mr. Pappas submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Santibanez and Mr. Pappas did not receive any funds from the bankruptcy estate or any other source to satisfy the judgment against Pool Masters. Mr. Santibanez and Mr. Pappas satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $17,675.50. DOAH Case No. 99-1666: Klaus and Lucrecia Mueller Klaus and Lucrecia Mueller entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about February 24, 1997. The total price stated in the contract was $16,400.00. Pool Masters represented to Mr. and Mrs. Mueller that it was a licensed swimming pool contractor. Pool Masters began work on the pool in Spring 1997, and Mr. and Mrs. Mueller made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool, installed the steel frame, poured gunnite at the shallow end of the pool, and installed the brick and tile around the pool. Pool Masters last worked on the swimming pool in late November 1997. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Mueller had paid Pool Masters approximately $12,900.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Mueller's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Mueller submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Mueller to file suit against Pool Masters. Mr. and Mrs. Mueller filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Mueller alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 7/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 8/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 9/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 10/ ] Mr. and Mrs. Mueller further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,299.51. The matter was presented to the circuit court, ex parte, upon Mr. and Mrs. Mueller's Motion for Default Final Judgment. The court entered a Default Final Judgment in June 1998, awarding Mr. and Mrs. Mueller $13,299.51, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated June 23, 1998, Mr. and Mrs. Mueller submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Default Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Mueller did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Mueller satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $13,299.51. DOAH Case No. 99-1667: Mario and Martha Alboniga Mario and Martha Alboniga entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about March 17, 1997. The total price stated in the contract was $24,000.00. Pool Masters represented to Mr. and Mrs. Alboniga that it was a licensed swimming pool contractor. Pool Masters began work on the pool on November 10, 1997, and Mr. and Mrs. Alboniga made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and poured the concrete form of the pool. The last day Pool Masters worked on the swimming pool was November 19, 1997. Mr. and Mrs. Alboniga later heard that Pool Masters had declared bankruptcy. At the time Pool Masters ceased work on the pool, Mr. and Mrs. Alboniga had paid Pool Masters a total of $15,200.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. and Mrs. Alboniga’s property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. and Mrs. Alboniga submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. and Mrs. Alboniga to file suit against Pool Masters. Mr. and Mrs. Alboniga filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. and Mrs. Alboniga alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 11/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 12/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 13/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 14/ ] Mr. and Mrs. Alboniga further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $10,541.77. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. and Mrs. Alboniga $10,541.77, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. and Mrs. Alboniga submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. and Mrs. Alboniga did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. and Mrs. Alboniga satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $10,541.77. DOAH Case No. 99-1668: Salvator Militello and Sharon Sidorski Salvator Militello and Sharon Sidorski entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about April 6, 1997. The total price stated in the contract was $24,295.00. Pool Masters represented to Mr. Militello and Ms. Sidorski that it was a licensed swimming pool contractor. Mr. Militello and Ms. Sidorski made payments to Pool Masters pursuant to the contract. Pool Masters excavated the hole for the pool and spa, installed basic plumbing, and poured the concrete for the pool. Pool Masters last worked on the swimming pool in October 1997. At the time Pool Masters ceased work on the pool, Mr. Militello and Ms. Sidorski had paid Pool Masters $19,389.00 for work done pursuant to the contract. Although Pool Masters represented to them that the payments would be used to pay subcontractors and materialmen, there were subcontractors and materialmen who were not paid. Liens were filed against Mr. Militello's and Ms. Sidorski's property, and they paid the subcontractors and materialmen directly in order to get the liens released. On January 17, 1998, the United States Bankruptcy Court for the Southern District of Florida issued a Notice of Commencement of Case Under Chapter 7 of the Bankruptcy Code, showing that Pool Masters had filed for bankruptcy on January 7, 1998. On or about March 11, 1998, Mr. Militello and Ms. Sidorski submitted a Construction Industries Recovery Fund Claim Form to the Board, naming Pool Masters as the contractor. In an order entered April 20, 1998, the bankruptcy court lifted the automatic stay to allow Mr. Militello and Ms. Sidorski to file suit against Pool Masters. Mr. Militello and Ms. Sidorski filed a complaint against Pool Masters in the Circuit Court for the Seventeenth Judicial Circuit in Broward County, Florida, seeking damages for breach of the contract for construction of the pool. Mr. Militello and Ms. Sidorski alleged in the complaint that Pool Masters had failed to complete the work; failed to perform in a reasonable and timely manner and abandoned the project for more than 90 days which is a violation of F.S. 489.129(1)(k) [Section 489.129(1)(j)];[ 15/ ] falsely represented that monies paid to them were paid to materialmen and sub- contractors which resulted in financial harm to the Plaintiffs which is a violation of F.S. 489.129(1)(l) [Section 489.129(1)(k)];[ 16/ ] committed mismanagement and misconduct which caused Plaintiffs financial harm as of [sic] liens were recorded as against the Plaintiff's [sic] home in violation of F.S. 489.129(1)(h)(1) [Section 489.129(1)(g)1.];[ 17/ ] f [sic]. committed mismanagement and misconduct which caused Plaintiffs financial harm in that the percentage of completion is less than the percentage of the total contract price paid in violation of F.S. 489.129(1)(h)(2) [Section 489.129(1)(g)2.].[ 18/ ] Mr. Militello and Ms. Sidorski further alleged in the complaint that the cost to complete the pool after construction was abandoned by Pool Masters was $13,544.00 and that they paid $1,641.68 to satisfy liens and unpaid subcontractors and materialmen, for total damages of $15,185.68. The circuit court entered a Final Judgment "pursuant to stipulation" on August 4, 1998, awarding Mr. Militello and Ms. Sidorski $15,185.68, to be recovered from Pool Masters, plus interest at the statutory rate. In a letter from their attorney dated August 12, 1998, Mr. Militello and Ms. Sidorski submitted to the Board additional documents to support their claim against the Construction Industries Recovery Fund, based on their Final Judgment against Pool Masters. The final report of the Trustee of Pool Masters' bankruptcy estate, dated December 1, 1999, indicated that Pool Masters had no funds remaining after disbursement for administrative expenses. Mr. Militello and Ms. Sidorski did not receive any funds from the bankruptcy estate or any other source to satisfy their judgment against Pool Masters. Mr. Militello and Ms. Sidorski satisfy the statutory criteria for eligibility for payment from the Fund in the amount of $15,185.68. DOAH Case No. 00-0024: Jack and Paula Tieger Jack and Paula Tieger entered into a contract with Pool Masters for construction of a swimming pool. The contract was executed on or about December 17, 1995. The total price stated in the contract was $28,200.00. Pursuant to the contract, Pool Masters built a pool and screen enclosure, and Mr. and Mrs. Tieger paid Pool Masters the price specified in the contract. Mr. and Mrs. Tieger were not, however, satisfied with the work done by Pool Masters, and, in or around 1997, they filed a complaint for breach of contract against Pool Masters in the Circuit Court of the Seventeenth Judicial Circuit, in Broward County, Florida. In the complaint, Mr. and Mrs. Tieger alleged that Pool Masters had breached the contract: By failing to adequately explain the technical terms used in the Agreement to the TIEGERS; By failing to install a vacuum line with valve as specified in the Agreement; By failing to install anti-corrosive handrails in the swimming pool; By failing to properly install and/or provide a properly functioning waterfall as specified in the Agreement; By failing to properly fill the area behind the waterfall; By unilaterally, and or the TIEGERS' [sic] objection, placing a tile with the "Pool Masters" logo on the steps heading into the pool: By failing to re-route the TIEGERS' [sic] sprinkler system in a timely manner; By failing to advise the TIEGERS that they were going to need to pay for and install a separate circuit breaker box as part of the installation of the swimming pool; and By failing to install the second screen door as specified in the Agreement. Mr. and Mrs. Tieger did not identify the amount of damages they allegedly suffered as a result of Pool Masters's alleged breach of contract. Mr. and Mrs. Tieger were not aware that Pool Masters had declared bankruptcy until January 1998, when Mrs. Tieger went to Pool Masters' office and found the notice on the door. A non-jury trial was held before the circuit court on March 5, 1998; Pool Masters did not attend the trial. In a Final Judgment entered on March 25, 1998, the court awarded Mr. and Mrs. Tieger $4,200 as compensatory damages to be recovered from Pool Masters. In a Proof of Claim dated May 13, 1998, and filed with the United States Bankruptcy Court of the Southern District of Florida, Mr. and Mrs. Tieger submitted an unsecured claim against Pool Masters' bankruptcy estate in the amount of $7,300.00, which represented the compensatory damages awarded in the final judgment, together with attorney's fees and costs. Mr. and Mrs. Tieger have not collected any portion of their judgment against Pool Masters. Mr. and Mrs. Tieger submitted to the Board a Construction Industries Recovery Fund Claim Form dated December 5, 1998, and the Board awarded Mr. and Mrs. Tieger $800.00, representing the cost of the vacuum line with valve and the second screen door which Pool Masters had not installed. Mr. and Mrs. Tieger do not satisfy the statutory criteria for eligibility for payment from the Fund. Mr. and Mrs. Tieger failed to establish that they filed their claim with the Board within two years of the date they discovered the alleged deficiencies in the pool, and they failed to establish that the final judgment against Pool Masters was based on a violation of Section 489.129(1)(g), (j), or (k), Florida Statutes (Supp. 1998). The evidence presented herein is not sufficient to establish that Mr. Kiselius is the licensee against whom the claimants obtained final judgments.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, 25/ it is RECOMMENDED that the Construction Industry Licensing Board: Enter final orders as follows: In DOAH Case No. 99-1665, finding Eugene Santibanez and Alexander Pappas eligible for payment from the Fund in the amount of $17,675.00, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1666, finding Klaus and Lucrecia Mueller eligible for payment from the Fund in the amount of $13,299.51, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1667, finding Mario and Martha Alboniga eligible for payment from the Fund in the amount of $10,541.77, in satisfaction of a final judgment against Pool Masters, Inc.; In DOAH Case No. 99-1668, finding Salvator Militello and Sharon Sidorski eligible for payment from the Fund in the amount of $15,185.68, in satisfaction of a final judgment against Pool Masters, Inc.; and In DOAH Case No. 00-0024, dismissing the claim of Jack and Linda Tieger for payment from the Fund. Determine that Christopher P. Kiselius is not the "licensee" whose license is subject to automatic suspension pursuant to Section 489.143(7), Florida Statutes (Supp. 1998), as a result of payments to the claimants in DOAH Case Nos. 99- 1665, 99-1666, 99-1667, and 99-1668. DONE AND ENTERED this 31st day of August, 2000, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2000.
Findings Of Fact Respondent is, and has been at all times material to this proceeding, a registered and certified pool contractor having been issued license numbers RP 0023613 and CP 0012607. Respondent's license number RP 0023613 has been delinquent since June 30, 1983, but his license number CP 0012607 was active and in full force and effect until he ceased doing business in approximately September, 1985. Respondent conducted his pool contracting business in the name of Hallmark Pools for approximately 14 years. The business entity "Hallmark Pools" was properly qualified and named on the Respondent's license. In 1985, the Respondent began to enter the business of designing outdoor patios and fountains, as well as pools. He wished to retain the good will he had gained operating under the name "Hallmark Pools" while gaining good will in the new name under which he planned to conduct business in the future, "Aquatic Environments, Inc." During this transition period, and until he closed his business, the Respondent's contracts and letterhead contained the names "Hallmark Pools" and "Aquatic Environments, Inc.," but that name never appeared on his licensure. On or about March 12, 1985, Respondent, through Hallmark Pools/Aquatic Environments, Inc., contracted with customers Mr. and Mrs. Allan Schaeffer to construct a screened-in pool and spa at their residence located at Archer Street, Lehigh Acres, Florida, for a contract price of $20,000. Later approximately $1,700 of extras were added to the contract. On or about March 21, 1985, the Schaeffers paid the Respondent $2,000 on the contract. On or about May 23, 1985, the Schaeffers paid another $17,000 on the contract. Approximately, $2,600 remained owing on the contract. The customers reside part of the time in New Jersey. In the contract, Respondent promised a June 15 completion date. When the customers arrived in Florida on or about June 14, they found that the project was not complete. When the customers contacted the Respondent, the work was resumed. The pool was quickly completed and was usable by the beginning of the July 4th weekend. Some punch list items remained to be done, but the Schaeffers preferred that the Respondent wait until after they returned to New Jersey in August, 1985. The evidence did not prove that the Respondent promised a June 15 completion date while knowing that he would not be able to finish the work by that date. During the summer of 1985, personal problems the Respondent was facing at the time mounted, and eventually he decided he no longer could continue to operate his business. He began to plan to close his business and have all pending matters either resolved by himself before he went out of business or resolved by his brother Chad Jackson, also a licensed pool contractor, after going out of business. He did this by assigning pending contracts to his brother. He also attempted to insure that all suppliers were paid either by himself before he went out of business or by his brother out of payments due under the contracts assigned to him. Except for the Schaeffer job, the Respondent's arrangements to close out his business did not result in any complaints. Near the end of August, 1985, the Schaeffers gave the Respondent a punch list of work still due under the contract to be done while the Schaeffers were in New Jersey. The Respondent called and told Mr. Schaeffer that he was closing his business but that the punch list items would be taken care of. At the time, the Respondent also knew that approximately $1,300 was owed to Jones Industries Screen Enclosures, Inc. The Respondent expected his brother to pay Jones out of the $2,600 due on the Schaeffer contract, leaving $700 to compensate his brother for the punch list work and any warranty work. In fact, there also was $2,705.12 owed to a company named FAFCO Solar, which had subcontracted the solar heating on the Schaeffer contract. The Respondent had forgotten about this debt. FAFCO had billed the Respondent on July 15, 1985, but the Respondent did not pay it or arrange for its payment. FAFCO's second billing never reached the Respondent. The Respondent sent FAFC0, along with his other suppliers and subcontractors, a notice on August 22, 1985, that he was going out of business and that mail should be sent to his home address. On receipt of this notice on August 28, 1985, FAFC0 mailed a second billing to the home address but it was returned on August 30, 1985, marked: "Moved Left No Address". The Respondent's brother did the punch list work to Mr. Schaeffer's satisfaction and sent him a bill for the $2,600 balance due on the contract. Schaeffer never paid. The Respondent's brother never paid the Jones Industries bill (and never got the FAFCO bill). Jones Industries put a lien on the property at 1414 Archer Street for $1,388.75, which the Schaeffers eventually paid. FAFCO did not file a notice to owner and could not claim a lien on the property. FAFC0 never was paid. Both Jones Industries and FAFCO refused to do warranty repairs because they were not timely paid. The evidence did not prove that the Respondent inadequately supervised the Schaeffer job while he was still in business or after he went out of business. After he went out of business, he assigned the contract to a licensed pool contractor, his brother. Eventually, serious problems developed in the Schaeffer's pool at 1414 Archer Street. But the evidence did not prove that the Respondent or his brother were responsible. The serious problems of which the Schaeffers now complain should have been apparent from the outset if caused during construction of the pool. Yet complaints were not registered until much later. Meanwhile, improper maintenance of the pool by the Schaeffers or their pool maintenance contractor, or damage to the pool during maintenance, could have caused the current problems. For six months after the Respondent closed his business and left Ft. Myers, he was traveling in the western part of the country and had no mailing address and did not give one to the Construction Industry Licensing Board. Then, he returned to Florida to a St. Petersburg address which he gave to the Board.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order finding the Respondent guilty of violating Section 489.129(1)(g) and (m), Florida Statutes (1985), reprimand him for the violation of (g) and fine him $1000 for the violation of (m). RECOMMENDED in Tallahassee this 19th day of December, 1988. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of December, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-3468 To comply with Section 120.59(2), Florida Statutes (1987), the following rulings are made on the Petitioner's proposed findings of fact: Rejected. (The license number was left blank.) Accepted and incorporated. Rejected as contrary to facts found. The Respondent arranged for payment of the Jones debt but disputes among the Schaeffers, Jones and the Respondent's brother led to Jones imposing a lien on the property which the Schaeffers eventually paid. The Respondent did not make arrangements to pay FAFCO, and that bill remains unpaid. 4.-9. Rejected as contrary to facts found. COPIES FURNISHED: David Bryant, Esquire 500 North Tampa Street Tampa, Florida 33602 Thomas Jackson 5203 109th Way North St. Petersburg, Florida 33708 Fred Seely Executive Director Construction Industry Licensing Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750
Findings Of Fact On October 10, 1979, the Respondent entered into a written swimming pool contract with Mr. and Mrs. Stellato, wherein the Respondent agreed to construct a swimming pool for them on their property in accordance with the plans and specifications attached to the contract. Among other things this swimming pool contract provided for the payment of a total purchase price of $11,225.00 to be paid in the following manner: ten percent to be paid at the signing of the contract. fifty percent to be paid upon the installation of the tank. thirty-five percent to be paid upon completion of the base decking and screen enclosure. five percent, or the balance of the purchase price, to be paid when the filter system was put in operation. Further, this contract provided that if the purchasers of the swimming pool failed to pay the purchase price in accordance with the prescribed schedule, the contractor reserved the right to suspend all work on the swimming pool, and to suspend all warranty work due after completion of the pool. During the month of February, 1980, the Respondent, acting through his duly authorized representatives, did all acts necessary to cause the filter system of the subject swimming pool to become operable, and requested that the Stellatos pay the five percent balance due under the contract. The Stellatos failed to make this final payment, claiming that there was a problem with the pool decking. In response to this complaint the Respondent personally met with the Stellatos, and agreed to cover the problem area of the decking with Chattahoochee River Rock at no cost to the Stellatos. In exchange for this agreement the Stellatos agreed to pay the balance due under the contract. Thereupon, the Respondent installed Chattahoochee River Rock over a substantial portion of the decking at his own expense. During the installation of this Chattahoochee River Rock, Mrs. Stellato contacted the Respondent by phone and demanded that he also install, at his own expense, Chattahoochee River Rock over an existing concrete patio area that had not been built by the Respondent. The Respondent refused to incur this additional expense, because it was not in accordance with the agreement of the parties. Thereafter, the Stellatos again failed to pay the balance due under the contract. The subject swimming pool was inspected by an inspector for Palm Bay, and the City issued a certificate of occupancy in June of 1980. The pool was ready for a certificate of occupancy in February of 1980 except for the removal of one pile of dirt that still remained on the premises. All other aspects of the pool construction passed inspection in February of 1980 when the pool filter system was activated. Since February Of 1980, the Stellatos have had full use of the subject swimming pool. Except for alleging that some low spots remain in the pool decking, the Petitioner offered no substantial evidence of any other significant problem with the Respondent's construction. Notwithstanding the failure of the Stellatos to pay the balance of the contract price in a timely manner, the Respondent performed warranty work on the subject swimming pool after February of 1980. During the course of this warranty work the Respondent added chlorine chemicals to the pool because the Stellatos had failed to properly maintain it up to June of 1980. Another claim concerning a leaking pipe on the pool sweep did not manifest itself until April of 1981, after the expiration of the one year warranty period afforded by the Respondent to all customers. The Petitioner offered no evidence to show that the leak in this pipe was caused by the Respondent. Notwithstanding the expiration of the warranty period, and the lack of evidence to show that the leak was caused by the Respondent, he did send an employee to the job site and stopped the water leak, at no cost to the Stellatos. On several occasions when the Respondent or his employees attempted to satisfy the complaints of the Stellatos, they had to leave the job site because of the abusive language and conduct directed toward them by the Stellatos. In one instance Mr. Stellato ordered the Respondent's employees from the job site and prevented performance of any work under the contract.
Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Administrative Complaint, as amended, against John W. Thornett be dismissed. THIS RECOMMENDED ORDER entered this 9 day of June, 1982, in Tallahassee, Florida. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 Filed with the Clerk of the Division of Administrative Hearings this 9th day of June, 1982.