Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT D. HUEY, 87-004505 (1987)
Division of Administrative Hearings, Florida Number: 87-004505 Latest Update: Oct. 31, 1988

The Issue Whether Respondent violated Sections 489(1)(d),(j) and (m), Florida Statutes?

Findings Of Fact At all times relevant Respondent was licensed as a registered residential contractor in Florida and held license number RR0046781. Sometime in late April, 1985, Respondent entered into a contract with Mr. Reames. The contract called for Respondent to build a house at 1512 S.E. 24th Avenue, Ocala, Florida. Mr. Reames moved into the house on December 23, 1985, after a certificate of occupancy was issued, even though the house was not fully completed. Mr. Reames completed a "punch list," consisting of an undetermined number of items which needed to be completed, and asked Respondent to complete the items. Most items in the punch list were never completed by Mr. Huey. After the initial attempt by Mr. Reames to get Huey Construction Co. to complete the items in the punch list, Mr. Reames did not contact Huey Construction Co. about the other problems found subsequently. In March or April, 1986, Mr. Reames noticed that the wood floor was buckling and separating. He contacted Mr. Gassett, the person who had installed the floors, who determined that a water leak was causing the problem. In November, 1986, Mr. Reames hired Mr. Clyatt, a licensed general contractor, to inspect the house, to go over the punch list items which needed to be completed, and to correct other items which were discovered to be inadequate. In the first week of January, 1987, Mr. Norton, the chief building inspector for the City of Ocala, was asked by Mr. Reames to inspect the house. Mr. Norton found a number of problems and identified some violations of the City of Ocala Building Code (Code) which was in effect at the time the house was built. The inadequacies, problems and code violations found by Mr. Clyatt and Mr. Norton are set forth below. Ventilation The Code requires 1 sq. ft. of opening for each 150 sq. ft. of crawlspace, in order to provide ventilation. Since the house had 2720 sq. ft. of crawlspace, it needed 18 sq. ft. of openings. The house, however, had only 6 openings of 1 sq. ft. each, or 6 sq. ft. of openings. Additionally, the plans for the house indicated where the openings were to be located and the completed house did not meet the plan specifications in this area. Mr. Clyatt added 15 openings, 8 in. by 12 in. each. In addition to the inadequate openings, one area of the crawlspace was completely enclosed, with no ventilation. The Code requires that attic ventilation for this type of house be 1 sq. ft. of opening for each 300 sq. ft. of space. The plans called for 3 in. by 12 in. vents at 24 in. intervals. The openings in the house were approximately 2 in. in diameter and were placed sporadically. From a visual inspection, without taking actual measurements, the openings for attic ventilation were inadequate and did not provide the ventilation required by the Code. Roof The roof of the house contained exposed nails and staples on the shingles, including some which had rusted. Nails and staples should not be exposed on a shingle roof, since they can lead to leaks. The roof leaked in one area in the back of the house. Mr. Reames contacted H & B Roofing, the subcontractor who had installed the roof, who corrected the problems with the roof. Driveway The Code requires that a driveway permit be obtained prior to the installation of a driveway. Also, the Code requires an inspection of the driveway prior to the concrete being poured. Respondent obtained the required permit, but failed to call for the required inspection prior to pouring the concrete. By letter dated December 10, 1985, Respondent notified the Building Inspection Office of the City of Ocala that the driveway was poured according to the Code. By the time of the inspections by Mr. Norton and Mr. Clyatt, several cracks were present in the driveway. SubFloor Due to the water damage set forth in paragraph 5, supra, the wood floor was removed in late December, 1986 or early January, 1987. The plans originally called for the subfloor to be constructed of one-half inch plywood decking, particle board, and 15 lb. felt paper. However, the Code requires subfloors to be constructed using three-quarter inch plywood, and the plans contained a penciled in notation where the one-half inch was changed to eleven- sixteenths. The subfloor had been constructed using one-half inch CDX plywood decking with particle board on top. No felt paper had been used. Additionally, the subfloor had been nailed in violation of the Code. The Code requires nails to be spaced two and one-half inches on the perimeter of the plywood and four inches in the interior area of the plywood. The subfloor of the house contained boards which had only been nailed on the perimeter and boards which had a large number nails in one area, far in excess of the amount required by the Code. Girders When Mr. Clyatt inspected the house he discovered that approximately 6 of the wood girders supporting the floor appeared to have been cut short and, instead of bearing on the stem wall bearing plate, were supported by posts made of two-by-four and two-by-six non-pressure treated lumber. The posts were resting on soil and the bottom part of the posts had decayed. This construction is a violation of the Code which requires that pressure treated wood be used, and is a violation of construction standards which require that the girders rest on the bearing plate or on concrete. See Petitioner's Exhibit 6. Also, the girders supporting the wood floor were not resting directly on the block piers. Wood shims had been added to fill the space between the girders and the block piers. The wood shims were not pressure treated. The Code requires that pressure treated wood be used in this situation. Additionally, proper construction requires that the girders rest directly on the block piers. Foundation Wall A foundation wall was not bearing on the footing properly. The foundation wall was constructed of 8-inch block and portions of the wall had only one to two inches bearing on the footing; the rest of the wall was resting on the soil. This is a violation of the Code. This problem was corrected by Mr. Clyatt by removing the soil on which the wall rested and pouring concrete under the wall. See Petitioner's Exhibit 7. Cabinets The cabinets in or near the utility room area of the house were loose and separating from the soffit and the wall.

Recommendation Therefore, based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order reprimanding Respondent and imposing a fine of $1500.00. DONE and ORDERED this 31st day of October, 1988, in Tallahassee, Florida. JOSE A. DIEZ-ARGUELLES Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 1988. APPENDIX Case Number 88-5570 The parties submitted proposed findings of fact which are addressed below. Paragraph numbers in the Recommended Order are referred to as "RO ." Petitioner's Proposed Findings of Fact Proposed Finding of Fact Number Ruling and RO Paragraph Accepted. RO1. Accepted. RO2. Accepted. RO3,4. First sentence, Accepted RO7. Second sentence accepted for proposition that Mr. Reames paid Mr. Clyatt $30,000 for work done on the house. However, the evidence fails to establish what portion of this amount was paid for problems caused by Respondent. 5-10. Accepted generally as to what Mr. Clyatt observed. RO19,20. But see discussion in Conclusions of Law portion of this RO. Accepted. RO13. Accepted generally. RO14. Respondent was not asked to repair the shingles when this deficiency was discovered about one year after Respondent had ended work on the house. First sentence rejected. Second sentence, accepted R016, but no competent substantial evidence was presented to show what caused the cracks. Accepted generally as to what was observed. RO22. But see discussion in Conclusions of Law portion of RO. Accepted. RO18. Accepted. RO18. Accepted. RO21. Accepted. RO21. Accepted. RO10,11. Accepted. RO10,11. Accepted. RO17. Accepted. RO12. Accepted. RO12. Accepted. RO15. Accepted. RO15. Accepted. RO8. Respondent's Proposed Findings of Fact Respondent's post-hearing statement consists of a two page letter with attachments. The attachments have been addressed in the Background section of this Recommended Order. The proposed findings of fact contained in the letter are addressed below. References are to paragraphs and sentences within each paragraph. Proposed Finding of Fact Number Ruling and RO Paragraph Par. 2 RO2 establishes that a contract existed; no finding is made as to whether the contract was oral or written, or as to what the contract amount was. Par. 3 First sentence is not supported by the evidence. Second sentence, accepted. Third-Fifth sentences rejected as not supported by competent evidence; however, no finding is made as to who is at fault for this problem. See Conclusions of Law. Fifth sentence is not a finding of fact. Par. 4 Not a finding of fact. Par. 5 (References are to statements after each number in the paragraph) #8 is accepted generally. RO15. #9 rejected as not supported by competent evidence. #10 rejected as not supported by competent evidence; some of the allegations were proven to exist as set forth in this RO. #11 and 12 are not findings of fact. COPIES FURNISHED: David L. Swanson, Esquire Staff Attorney Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Robert D. Huey 3710 Southeast 12th Place Ocala, Florida 32670 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Lawrence A. Gonzalez, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Bruce Lamb General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (6) 120.57120.6017.001489.105489.119489.129
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs EDGAR R. NAZARIO, 10-000551PL (2010)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Feb. 08, 2010 Number: 10-000551PL Latest Update: Dec. 24, 2024
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs ARTHUR SIGNORE, 97-001435 (1997)
Division of Administrative Hearings, Florida Filed:Miami, Florida Mar. 21, 1997 Number: 97-001435 Latest Update: May 06, 1998

The Issue The issue for determination is whether Arthur Signore committed the offenses set forth in the administrative complaints and, if so, what action should be taken.

Findings Of Fact At all times material hereto, Arthur Signore (Respondent) was licensed by the Department of Business and Professional Regulation, Construction Industry Licensing Board (Petitioner) as a certified general contractor. He received his license in 1969, qualifying Deluccia Construction. Respondent was issued license number CG CA01004. Subsequently, in 1976, Respondent qualified Construction By Scott (CBS). He was issued license number CG CB01004. At all times material hereto, Respondent has been the qualifier of CBS, and the sole owner and president of CBS. At all times material hereto, Respondent's belief was that Petitioner permitted a general contractor to use his/her license to obtain building permits for construction projects for which the general contractor had no contracts through the business that he/she qualified. Respondent practiced his belief frequently by applying for and obtaining building permits for construction projects for which companies or individuals other than CBS had contracts. Collins Job (Case No. 97-1436) Sometime after Hurricane Andrew in 1992, Respondent made an oral agreement with Harold Bader to go into partnership with Bader and form a construction company, with Respondent qualifying the company. Respondent provided his name, his company's name (CBS), and his license number to Bader in order for the qualifying documents to be completed and submitted to the Petitioner. However, the company was not formed and the qualifying documents were never submitted. At no time material hereto was Bader licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that Bader was not licensed by the Petitioner. In March 1994, Thomas Sherry of American Building Industries, Inc. (ABI), began negotiating with Maria and Wayne Collins, husband and wife, for the remodeling of their home, located at 7417 SW 140th Court, Miami, Florida. On March 24, 1994, the Collins entered into a contract with ABI for the remodeling of their home at a cost of $12,500. Bader was the owner of ABI. Sherry was a salesperson for Bader. Sherry provided the Collins with a business card which showed, among other things, ABI's name, address and telephone number, and license number. The license number on the business card was Respondent's license number. All business cards were provided to Sherry by Bader. At no time material hereto, did Sherry talk with or meet Respondent. The records of the Metropolitan Dade County, Building and Zoning Department reflect, among other things, Respondent's name, his company's name (CBS) and license number on the building permit application for the construction to the Collins' home. However, the address listed for Respondent and his company was the address for ABI. Further, the said records reflect, among other things, that aforementioned information provided, as to Respondent, was used to obtain the building permit. Respondent did not complete the permit application for the building permit to remodel the Collins' home. The Collins paid $6,875 to ABI. Any and all checks were made payable to ABI. No money for the construction on the Collins' home was paid to or received by Respondent. In May 1994, problems developed on the job site between the Collins and ABI. The work performed by ABI failed numerous inspections. Mr. Collins wanted to talk with Respondent who was listed as the contractor on the permit and requested Bader to contact Respondent. Bader refused, indicating to Mr. Collins that all communication should be with him (Bader). Finally, in August 1994 the Collins fired ABI after more problems had developed. At that time ABI had completed some of the work. On August 29, 1994, Mr. Collins met with Respondent at Respondent's place of business. Prior to the meeting, Mr. Collins had called Respondent numerous times regarding his problems with ABI and Bader and requesting assistance from Respondent. Each time Respondent denied having any knowledge of the work being performed. When Mr. Collins met with Respondent, Mr. Collins discussed the problems that he had experienced with ABI and Bader. Respondent continued to deny knowing anything about the construction project but agreed to send his employees to examine the job and determine what could be done, if anything. The following day two of Respondent's workers came to the Collins' home and examined the work completed and the work remaining. Subsequently, Respondent contacted Mr. Collins. Respondent indicated to Mr. Collins that he could complete the job for $5,000. Mr. Collins refused to pay the additional monies since it would extend the remodeling cost beyond the contracted cost and since he was now directly paying the subcontractors. At no time did Respondent or his business (CBS) have a contract with the Collins. Until being contacted by the Collins, Respondent had no knowledge that Bader used his name, business name and license number to contract with the Collins and to obtain the building permit for the remodeling of their home. However, prior to being contacted by the Collins, Respondent had been contacted by other persons who had contracts with ABI, who had been informed by Bader that Respondent was the contractor for their jobs, who had problems with ABI, and who wanted assistance from Respondent. Furthermore, the building permits for the construction jobs of those persons reflected Respondent and Respondent's company as the contractor. At no time material hereto was Bader or ABI licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that neither Bader nor ABI was licensed by the Petitioner to engage in the practice of contracting. Respondent was placed on notice of their unlicensed activity after the contacts by the homeowners prior to the contact by the Collins. Even with the knowledge of the homeowners' complaints prior to the Collins' complaints, at no time did Respondent notify Bader to stop using his (Respondent's) name, company's name and license number. Further, at no time did Respondent notify the Metropolitan Dade County, Building and Zoning Department of Bader's misuse of his (Respondent's) name, company's name, and license number or to no longer issue permits to ABI under his (Respondent's) name, company and license. Walsh Job (Case No. 97-1435) In the Fall of 1995, Patrick and Susan Walsh entered into an oral agreement with John Petracelli for an addition to and the remodeling of their home, located at 761 Glen Ridge Road, Key Biscayne, Florida. On October 16, 1995, the Walshes entered into a verbal agreement with Petracelli for an engineer to produce a set of plans at a cost of $2,250 for the construction to their home. The Walshes paid Petracelli the $2,250 on October 16, 1995. On December 7, 1995, the Walshes entered into a written agreement with Petracelli for the construction work on their home at a cost of $84,000. Pursuant to this written agreement, the Walshes paid Petracelli $16,800 on December 7, 1995. Petracelli contacted Respondent and requested Respondent to be the contractor for the construction work on the Walshes' home. Respondent and Petracelli had met one another previously when Petracelli was a salesperson for Bader. Petracelli informed Respondent that he (Petracelli) had already told the Walshes that Respondent was the contractor. To the contrary, Petracelli had not informed the Walshes that Respondent was involved in the construction to their home. Respondent agreed to be the contractor but informed Petracelli that, until a set of plans was approved by the Village of Key Biscayne Building Division (Building Division), he could not provide Petracelli with a cost figure for the construction work. Petracelli informed Respondent that the plans were being prepared, but did not inform Respondent that the Walshes had paid for the preparation of the plans. Respondent agreed further to submit the completed plans to the Building Division for a "dry run" only. After the dry run, Respondent would provide a cost figure for the construction work. A dry run is a process in which a contractor, who has a complicated job which requires an engineer, submits a set of plans, together with an application for a building permit, to the Building Division for approval. The plans may be subject to several modifications requested by the Building Division before they are approved. As a result, the contractor does not know the estimated cost of a job until the plans have gone through the requested modifications, if any, and approved by the Building Division. After the plans are approved by the Building Division, the contractor is notified to come to the Building Division and sign for and obtain the building permit. Pursuant to the agreement between Respondent and Petracelli, on or about December 11, 1995, Respondent completed an application for a building permit for the addition to and the remodeling of the Walshes' home and gave it to Petracelli. The application reflected, among other things, CBS (Respondent's company) as the contractor, and Respondent as the qualifier. Respondent provided the application to Petracelli for the dry run process only. Further, Respondent reiterated to Petracelli that, once the plans were approved by the Building Division, he (Respondent) would meet with the Walshes and agree on a cost for the construction work on their home and that, after agreeing on the cost he (Respondent) would sign for and obtain the building permit for the construction to begin. Respondent was not aware that Petracelli and the Walshes had a signed agreement for the construction work. Petracelli submitted the plans, along with the permit application, to the Building Division for approval. The plans were modified several times to meet the approval of the Building Division, but were never approved. The Building Division considered the plans submitted to be substandard. Since no plans were approved, no building permit was issued. On or about January 3, 1996, the Walshes met at the Building Division with some of the Building Division's officials, Petracelli, and the engineer who prepared the plans. As a result of the meeting, among other things, the Walshes were able to review the permit application and discovered that Respondent, not Petracelli, was licensed and the contractor for the construction work; concluded that the engineer's work was considered so substandard by the Building Division that any modification produced by the engineer would not be approved by the Building Division; and determined that they no longer wanted Petracelli to perform the construction work on their home. Within 24 hours of the meeting, the Walshes telephoned Petracelli and terminated his services. Also, the Walshes requested the return of all of the monies paid to Petracelli by them; however, Petracelli did not return any of their money. At no time material hereto was Petracelli licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that Petracelli was not licensed by the Petitioner. At no time material hereto did Respondent or his company (CBS) have a contract with the Walshes. At no time material hereto did Respondent have any communication or contact with the Walshes. Biscayne Kennel Club Job (Case No. 97-2998) The Biscayne Kennel Club (BKC), located at 320 NW 115th Street, Miami Shores, Florida, was a track for greyhound racing. On October 30, 1995, the last race was run at BKC. In February 1996, the BKC sold its Pari-Mutuel license. On or about December 11, 1996, the BKC, by and through its representative, Carl Spitzer, entered into a written contract with Cuyahoga Wrecking Corporation (CWC), by and through its representative, Thomas Schwab, for, among other things, the removal of asbestos and the demolition and removal of BKC's grandstand structure and viewing area. The contract was prepared by Schwab, who had 25 years of experience in the demolition business, with 20 years of that experience in the State of Florida. All contract negotiations were between Schwab and Spitzer. At no time was the President and CEO of BKC, Kay Spitzer, involved in the contract negotiations. As to cost, the contract provided at Article 4 that the cost was $37,500 and that the $37,500 was "dedicated to the removal of the described ACM." Further, Article 4 provided that the "balance of the work to be paid for by the sale of the ferrous and non-ferrous metals by the contractor." In addition, the contract provided in Article 7 that, among other things, all permits were included in the contract price and that BKC and the "contractor" would share "equally all the proceeds of the non-ferrous metals minus whatever costs are incurred bringing it to market." The contract did not restrict or prohibit CWC from engaging the services of any individual or subcontractor to perform the work required in the contract. The grandstand structure and viewing area were one structure. Attached to the roof of the structure was a small building which was used by BKC personnel for viewing the races. The roof was the highest part of the structure, except for the small building. The distance from ground level to the top of the roof was 69 feet and 10 inches; and the top of the small building was approximately 15 feet higher than the top of the roof. CWC contracted with Sal's Abatement to perform the asbestos removal. Schwab was licensed by Dade County, Florida, as a specialty contractor. He was notified that the work for the BKC job was outside the scope of his license and that a contractor, licensed by the Petitioner, was required for the BKC job. Schwab contacted Respondent to be the general contractor. Schwab had worked with Respondent before on other, but smaller, jobs. Respondent agreed to be the general contractor in return for a percentage of the contract. Per the agreement, Respondent would obtain the necessary permits, provide the equipment necessary for the demolition, and supervise the workers on the job. On March 6, 1997, Respondent completed an application for a building permit with Miami Shores Village, Florida, for the demolition of the BKC grandstand. The application reflected Respondent's company (CBS) as the contracting company and Respondent as the qualifier. Carl Spitzer signed the permit application on behalf of BKC. On March 17, 1997, a building permit (permit number 41084) was issued by the Village of Miami Shores for the demolition of BKC's grandstand. On April 29, 1997, the cost of the permit, $566.50, was paid. At no time material hereto was Schwab or CWC licensed by Petitioner to engage in the practice of contracting. Respondent knew or should have known that neither Schwab nor CWC were licensed by Petitioner. At no time did a contract exist between Respondent or his company with BKC for the demolition job. Respondent supervised CWC's preparation of the grandstand for demolition. In preparing the grandstand for demolition, Respondent and Schwab met at the site at least 3 times to discuss the demolition and its progress. On May 16, 1997, the grandstand was scheduled to be demolished. On the morning of May 16th, as Schwab was leaving BKC, Respondent arrived. Shortly thereafter, the grandstand accidentally collapsed--the beams supporting the roof of the grandstand failed, and the roof collapsed. Two of CWC's workers were killed and three were seriously injured. After the collapse, BKC contracted with another company, Omega Contracting, to complete the demolition job. The Petitioner submitted documents reflecting that its costs of investigation and prosecution of the complaints against Respondent, excluding costs associated with attorney's time, to be $1,017.25. On May 22, 1997, pursuant to an Emergency Suspension Order, on May 22, 1997, the Petitioner suspended Respondent's license. Respondent has no prior disciplinary action taken against him by the Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order: Dismissing all counts in Case Nos. 97-1435 and 97-1436. Finding that Arthur Signore violated Subsections 489.129(1)(c), (e), and (j), 489.1265(3), and 455.227(1)(a), Florida Statutes (1995). Revoking Arthur Signore's certified general contractor's license. Requiring Arthur Signore to pay all reasonable costs of investigation and prosecution associated with the Department of Business and Professional Regulation's investigation and prosecution of the charges set forth in the Administrative Complaint of Case No. 97-2998.3 DONE AND ENTERED this 13th day of January, 1998, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1998.

Florida Laws (6) 120.569120.57455.227489.105489.1195489.129 Florida Administrative Code (3) 61G4-12.01861G4-17.00161G4-17.002
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer