Findings Of Fact Because of a 1984 Thanksgiving Day storm which inflicted damage in coastal areas, Barry Manson-Hing, an area engineer employed by the Department, issued emergency coastal construction permits from a temporary office in the Vero Beach Administration Building. On December 3, 1984, Respondent sought an emergency permit to allow him to place sand and sand-filled bags on his coastal property at 3755 Ocean Drive, Vero Beach, Florida. Respondent asked Mr. Manson-Hing if he could use sand from the beach to restore eroded areas. Mr. Manson-Hing said he could not, and told him that sand would have to be obtained from an upland source. Respondent replied that he had an available source of upland sand and would haul it by truck to the beach site. He also mentioned that he would remove an existing pine tree to allow vehicular access. On the next day, December 4, 1984, Mr. Manson-Hing issued an emergency coastal construction permit, #1R-127E, to Respondent. The permit allowed Respondent to place 1,500 cubic yards of sand fill material to restore eroded beach and dune areas at the site, and also permitted him to temporarily place sand-filled bags on filter cloth. In capital letters, the permit warned, "SCRAPING OF THE BEACH IS PROHIBITED." (Dept. Exhibit 4) On December 5, 1984, Lt. Raymond Barker of the Vero Beach Police Department, observed beach scraping activities being conducted on Respondent's coastal property. Respondent was present on the site. Beach sand seaward of the Coastal Construction Control Line for Indian River County had been scraped and deposited at the face of the sand dune. The removal of the sand created depressions in the beach area seaward of the Coastal Construction Control Line. Lt. Barker ordered Respondent to cease the activity until it could be determined he had the required authorization. Respondent complied with Lt. Barker's order. The scraping of the beach and removal of sand below the coastal construction control line was accomplished without a permit from the Department. On July 17, 1985, the Department entered its "Final Order" assessing Respondent a $500 fine for unauthorized coastal construction activities in violation of Section 161.054, Florida Statutes (1985). Respondent requested a hearing; resulting in this proceeding.
Recommendation Based on the foregoing, it is RECOMMENDED: That the Department assess, impose, and collect an administrative fine of $500, to be paid within 30 days of final agency action. DONE AND ORDERED this 20th day of June, 1986, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings the 20th day of June, 1986.
The Issue Whether the Sherry Petitioners have standing to initiate the proceeding in Case No. 10-0515? Whether the Oceania Petitioners have standing to initiate the proceeding in Case No. 10-0516? Whether the MACLA Intervenors have standing to intervene? Whether the Department should enter a final order that issues the JCP, the Variance and the SSL Authorization?
Findings Of Fact Setting and Preliminary Identification of the Parties These consolidated cases are set in Okaloosa County. They concern the Consolidated NOI issued by the Department to the County that indicate the Department's intent to issue state authorizations to allow the restoration of a stretch of beach known as the Western Destin Beach Restoration Project (the "Western Destin Project" or the "Project"). In addition to the Western Destin Project, there are other beach restoration efforts (the "Other Beach Restorations") which concern the Gulf of Mexico coastal system along the shores of the Florida Panhandle and about which the parties presented evidence in this proceeding. The applicants for the authorizations in the Other Beach Restorations efforts are either Okaloosa County or Walton County, the coastal county immediately to the County's east, and concern Okaloosa and Walton County property or are on federal property used by Eglin Air Force Base (the "Eglin Projects" or "A-3" or "A-13"). The Eglin Projects have been completed. The source of the sand use in the Eglin Projects is a borrow area designated by the County and its agent, Taylor Engineering, as "OK-A" ("OK-A" or the "OK-A Borrow Area"). The County intends that the OK-A Borrow Area be the source of sand for the Western Destin Project. West of East Pass, a passage of water which connects Choctawhatchee Bay and the Gulf of Mexico, the OK-A Borrow Area is between 4,000 and 5,000 feet off the shores of Okaloosa Island. Okaloosa Island is not an island. It is an area of the incorporated municipality of Fort Walton Beach that sits on a coastal barrier island, Santa Rosa Island. Except for the part of the final hearing conducted in Tallahassee, the final hearing in this case took place in Okaloosa Island. As Mr. Clark put it (when he testified in that part of the hearing not in Tallahassee), "I am in Okaloosa Island. [At the same time], I am on Santa Rosa Island." Tr. 521 (emphasis added). Petitioners in Case No. 10-0515, David and Rebecca Sherry and John Donovan (the "Sherry Petitioners") live along a stretch of beach that is in Okaloosa Island. They do not live along the stretch of beach that is within the area subject to the Western Destin Project. The Sherry Petitioners' stretch of beach is the subject of another beach restoration effort by the County (the "Okaloosa Island Beach Restoration Project"). The Okaloosa Island Beach Restoration Project, in turn, is the subject of another case at DOAH, Case No. 10-2468. The OK-A Borrow Area is much closer to the Sherry Petitioners' property than to the beach to be restored by the Western Destin Project. The Sherry Petitioners recognize the need for the restoration of at least some of the beaches in the Western Destin Project. The Sherry Petitioners initiated Case No. 10-0515, not to prevent the Western Destin Project from restoring those beaches, but because they are concerned that the beaches subject to the Okaloosa Island Project (including "their" beach) will suffer impacts from the dredging of the OK-A Borrow Area whether the dredging is done to serve the Western Destin Project or the other Projects the OK-A Borrow Area has served or is intended to serve. In contrast to the Sherry Petitioners, the Petitioners in Case No. 10-0516 (the "Oceania Petitioners") do, in fact, live on beaches in a section of the Western Destin Project that was slated for restoration when the Consolidated NOI was issued. The Oceania Petitioners are opposed to the restoration of the beaches subject to the Western Destin Project. They initiated Case No. 10-0516, therefore, because of that opposition. Walton County applied authorizations from the state for the Walton County/East Destin Project (referred-to elsewhere in this order as the "Walton Project"). The Walton Project, like the Eglin Projects, is completed. Unlike the Eglin Projects, and the intent with regard to the Western Destin Project and the Okaloosa Island Project, the Walton Project did not use the OK-A Borrow Area as its source of sand. The Walton Project used a Borrow Area to the east of OK-A (the "Walton Borrow Area"). The Walton Borrow Area is in an area influenced by the ebb tidal shoal formed by the interaction between East Pass and the Gulf of Mexico. The MACLA Intervenors (all of whom own property deeded to the MHWL of the Gulf in the stretch of beach subject to the Western Destin Project) together with the Sherry Petitioners and the Oceania Petitioners, seek findings in this proceeding concerning the impacts of the Walton Borrow Area to the beaches of Okaloosa County. They hope that findings with regard to Walton Borrow Area beach impacts will undermine the assurances the County and the Department offer for a finding that the Western Destin Project will not cause significant adverse impacts to the beaches of Okaloosa County. The Holiday Isle Intervenors support the Project. They are condominium associations or businesses whose properties are within the Project. Like the Eglin Projects, the Walton Project is complete. The Walton Project was the subject of a challenge at DOAH in Case Nos. 04-2960 and 04-3261. The challenge culminated at the administrative level in a Final Order issued by the Department that issued the state authorizations necessary to restore the Walton Project beaches. The Walton Project Final Order was appealed to the First District Court of Appeal where it was reversed. But it was reinstated in a decision by the Florida Supreme Court. The Florida Supreme Court decision was upheld when the United States Supreme Court issued a unanimous 9-0 decision less than two months before the commencement of the final hearing in these consolidates cases: Stop the Beach Renourishment, Inc. v. Fla. Dep't of Envtl Prot., 130 S. Ct. 2592 (2010). The Court held in Stop the Beach Renourishment that the Walton County Project was not a regulatory taking of property that demanded compensation to affected property owners under the Fifth Amendment to the United States Constitution. Stop the Beach Renourishment was argued before the United States Supreme Court in December of 2009, shortly before filing of the petitions that initiated these consolidated cases. The final hearing in these cases was not set initially until July 2010 in the hope that the Stop the Beach Renourishment case would be decided, a hope that was realized. In the meantime, another event threatened to affect these consolidated cases: the Deepwater Horizon Oil Spill (the "Oil Spill") in the Gulf of Mexico. The spill began with the explosion of the Deepwater Horizon oil platform in April of 2010 and continued until August of 2010 when the Oil Spill was stopped while these cases were in the midst of final hearing. The Joint Coastal Permit issued by the Department was revised to address impacts of the Oil Spill. No impacts, however, were proven in this proceeding by any of the parties. The Parties The Sherry Petitioners and Their Property David and Rebecca Sherry, husband and wife, are the leaseholders of "Apartment No. 511 [ a condominium unit] of Surf Dweller Condominium, a condominium with such apartment's fractional share of common and limited elements as per Declaration thereof recorded in Official Records . . . of Okaloosa County, Florida."2/ Their address is 554 Coral Court, #511, Fort Walton Beach, FL 32548. The Sherrys entered the lease for their condominium unit in May of 2002 in anticipation of it being their retirement home. After retirement, "towards the end of 2005," tr. 840, the unit became their permanent residence. They chose their home after an extensive search for the best beach in America on which to reside. The couple toured the Gulf Coast of Florida, the Keys and the Atlantic seaboard from South Florida into the Carolinas. Both explained at hearing why they picked the Panhandle of Florida in general and selected the Surf Dweller Condominium in particular as the place that they would live during retirement. Mr. Sherry testified: Tr. 841. This particular area we chose because of the beach quality. Quite frankly, . . . I was surprised when I first saw the place . . . the really stunning quality of it. The sand is absolutely beautiful. The water has that clear green hue. You can walk off shore and it just looks great. There isn't any other place like it in the Continental US that I've ever seen. Mrs. Sherry elaborated about the reasons for their choice to reside on the beach adjacent to the Surf Dweller and their enjoyment of the beach in the Okaloosa Island area of Santa Rosa Island. "We moved here for the quality of the beach, the sugar white sand." Tr. 936 (emphasis added). She explained that both she and her husband walk or run the beach daily. Mr. Sherry always runs; Mrs. Sherry's routine is to walk and run alternately. There are other distinctions in their daily traverses over the sugar white sand of Okaloosa Island. Mr. Sherry sometimes runs in shoes. As for Mrs. Sherry, however, she professed, I always run barefoot. I always walk barefoot and I take longer walks than he does. He runs the whole Island. I walk the whole Island and I run 3 miles at a time of the Island. So, that's the difference in the way we use [the beach.] Id. Mrs. Sherry described her activities on the beach more fully and how she enjoys it: I . . . swim. I surf on the skim board, float out in the water . . . I help Dave fish, we crab, . . . all sorts of things like that for recreation. Pretty much a beach person. I sit down on the beach under an umbrella with a lot of sunscreen. * * * I've always run barefoot. That's the reason [we chose the beach next to the Surf Dweller], it's not only the quality of the sand, [it's also] the fact that it's so soft because as I've aged, my husband and I have both been running for 30 years. He's in much better shape. I can still run barefoot and I can do a good pace, but if I've got shoes on, it's not nearly as much fun and I don't do nearly as much of it. So, to me, being able to have the squeak [of the sand underfoot], which you don't have with the restored sand is a big deal and having to wear shoes is a big deal. I really like to . . . [cross the beach] barefoot. Tr. 939. I actually think the project will impact me, at least, as much as my husband, David . . . my husband is . . . involved with . . . being board president of the Surf Dweller[.] I spend at least as much time as he does on the beach. And the way our furniture is arranged in the unit, it's so that when I'm in the kitchen, I bake the cookies, I see the beach, when I'm at the computer I can see the beach. I've got all the best views. So, I think I'm . . . extremely involved with it. It's the first thing I see in the morning; it's the last thing I see at night and I'm down there every morning. In fact, I was on the beach this morning before we came in . . . I don't miss my morning walk. Tr. 950. The Surf Dweller Condominium is located in Block 5 of Santa Rosa Island,3/ Okaloosa County, on real property that was deeded to the County by the federal government and then subsequently leased out by the County under long-term leases. The legal description of the Surf Dweller Condominium,4/ is: LOTS 257 TO 261, INCLUSIVE, LOTS 279, 280, 281, BLOCK 5, SANTA ROSA ISLAND, PLAT BOOK 2, PAGE 84, OKALOOSA COUNTY. Ex. P-8, PET7158. Block 5 of Santa Rosa Island is subject to Protective Covenants and Restrictions adopted by the Okaloosa Island Authority and recorded in the Official Records of the County at Book 121, Pages 233-250. See County Ex. 13. The Protective Covenants and Restrictions set up four classifications of areas denominated as Zones B-1 through B-4.5/ Block 5 of Santa Rosa Island is in Zone B-2, "Apartment, Hotel Court and Hotel Areas."6/ Part F of the Protective Covenants and Restrictions, provides, in part, Beach Protection * * * The beaches, for 300 feet inland from mean water level (or to the dune crest line, whichever is the greater distance), are under strict control of the Authority . . . One hundred fifty feet inland from the mean water line, in front of all B1 and B2 Areas, will be public beaches. The next 150 ft. inland will be private beaches as set out on subdivision plats . . . County Ex. 13, at page marked "BOOK 121 PAGE 242." The Surf Dweller Condominium property, lying between reference monuments R-6 and R-7, does not extend as far south as the mean high water line ("MHWL") of the Gulf of Mexico. From testimony provided by Mr. Sherry, see below, it appears that the Surf Dweller condominium property is deeded to the border with the beaches governed by Part F of the Protective Covenants and Restrictions. John Donovan is the leaseholder of "APARTMENT NO. 131 AND APARTMENT NO. 132, OF EL MATADOR, A CONDOMINIUM AS PER DECLARATION THEREOF, AS RECORDED IN . . . THE PUBLIC RECORDS OF OKALOOSA COUNTY, FLORIDA."7/ The address of the El Matador is 909 Santa Rosa Boulevard, Fort Walton Beach, FL 32548. Petitioner Donovan is not a resident of the State of Florida. His primary residence is in the State of Georgia. Mr. Donovan described in testimony his use and the use of his family of the beach seaward of El Matador and other parts of the Okaloosa Island area of Santa Rosa Island: I've . . . got to walk [for reasons of health] and I do walking every day I'm down here[.] I get all the way down to East Pass. I don't get down there every day, but I get down there a lot. My sons and my one grandchild take great pleasure in fishing off there, right at the end where the East Pass is right from the surf. * * * I swim. I don't swim probably as much as my co-petitioners [the Sherrys], but I'm sure I go out further. And I don't surf like David [Sherry] does but my grandchild would never tell me that I don't. I run as much as I can. Not as much as I used to. We also take long walks. Tr. 973-4. In a plat of El Matador Condominium introduced into evidence as part of Exhibit P-7, El Matador is described as: A CONDOMINIUM OF LOTS 557 THROUGH 590 INCLUSIVE, BLOCK 9 AND THE INCLUDED PORTION OF PORPOISE DRIVE THEREOF SANTA ROSA ISLAND A SUBDIVISION OF BLOCK 9 A RESUBDIVISION OF BLOCK 8 AS RECORDED IN PLAT BOOK 2, PAGE 190, PUBLIC RECORDS OF OKALOOSA COUNTY, FLORIDA Exhibit P-7, last page (un-numbered). Block 8 of Santa Rosa Island (like Block 5 in which the Surf Dweller Condominium is located) is also in Zone B-2 set up by the Protective Covenants and Restrictions. Block 8, just as Block 5, is governed by Part F, Beach Protection, of the Protective Covenants and Restrictions that places the beaches, for at least 300 feet inland, of the segment of Santa Rosa Island to which Block 8 is adjacent under the strict control of the County and makes the first 150 feet inland from the MHWL "public beaches." County Ex. 13, at page marked "BOOK 121 PAGE 242." El Matador Condominium lies between reference monuments R-1 and R-2. It is not deeded to the MHWL of the Gulf. The plat that is the last page of County Exhibit 13 shows the southern edge of the El Matador condominium property to be adjacent to the "FREEHOLDERS BEACH," Exhibit P-7, last page (un-numbered), landward of the Gulf of Mexico, that is, to the edge of the area of the private beach designated under the "Beach Protection" provision of the Protective Covenants and Restrictions, landward of the public beach designated by the same provision. Neither the Surf Dweller Condominium Property in which the Sherrys reside, nor the El Matador Condominium Property inhabited by Mr. Donovan abuts or is a part of the area subject to the Western Destin Beach Restoration Project. The two properties in Okaloosa Island are to the west of the Project. The Sherrys and Mr. Donovan did not initiate Case No. 10-0515 because they oppose the restoration of the beach subject to the Project. They initiated the proceeding because of concerns that the borrow area that will serve the Project is so close to Okaloosa Island and situated in such a way that once dredged it will cause adverse impacts to the Okaloosa Island beaches to the detriment of their use and enjoyment of the beaches. The Beach, Post-Hurricane Opal and Other Tropical Storms Beginning with Hurricane Opal in 1995, the beaches and shores adjacent to the Surf Dweller and El Matador Condominium Properties were seriously damaged. Nonetheless, there is a significant stretch of dry beach between the Surf Dweller and El Matador condominium properties and the MHWL of the Gulf. In the case of the Surf Dweller Property, Mr. Sherry estimated the width of the beach between the condominium property and the MHWL to be 300 feet. See his testimony quoted, below. The MHWL of the Gulf of Mexico is a dynamic line, subject to constant change from the natural influences of the coastal system. Whatever effect its ever-changing nature might have on the width of the beaches declared public and private8/ between the MHWL and the Surf Dweller and El Matador condominium properties, however, there can be no doubt on the state of the record in this proceeding that at the time of hearing there existed a 150 foot-wide stretch of beach water-ward of the two condominiums that the public has the legal right to occupy and use. Indeed, Petitioner David Sherry, when asked about the private beach and public beach governed by the Part F of the Protective Covenants and Restrictions in cross-examination conducted by Mr. Hall on behalf of the County, confirmed as much when he related the actual practice by the public in using it and the response that public use generated from him and his wife: Q If someone . . . crosses Santa Rosa Boulevard and utilizes this access[-]way that's marked on the map that you identified earlier, do they have the right to utilize any of the portion of [the private beach] of that 150-foot portion in front of your condominium? A . . . [N]o, they wouldn't have the right to do that. Q . . . [D]o they have the ability to set up an umbrella or place their towel within that 150-foot area [of private beach] in front of your condominium? A In that area, no. In the area south of that [the public beach] , which is where everyone actually sets up and wants to set up, in that area south, people set up and we don't have any problem with that. We let people do it -- Q On [the] public beach[.] A On the public beach they're perfectly free to do that. * * * Q I believe your testimony today, based on your GPS calculations, was that you have 300 feet of dry sand beach . . . running from the boundary of the condominium to the edge of the Gulf of Mexico; is that correct? A Essentially, from the building to the Gulf of Mexico. * * * Q So, 300 feet, roughly, from the boundary of the Surf Dweller Condominium common area down to the waterline? A Correct. Q So, there would be enough room today, based on the language of the restrictive covenants to have . . . 150 feet of public beach and then the 150 feet of Freeholders Beach as designated on the plat [in County Exhibit 13] now? A Much like it was in 1955 [when the Protective Covenants and Restrictions were adopted and recorded], yes. Tr. 891-3, (emphasis added). Since the first 150 feet of beach landward of the MHWL under the Protective Covenants and Restrictions is "public beach," there is no doubt that there is a stretch of beach between the Surf Dweller Condominium and the MHWL that is public beach and its width is at least 150 feet.9/ From aerial photographs introduced into evidence, the same finding is made with regard to beach that is public between El Matador and the MHWL of the Gulf. Mr. Donovan testified that his leasehold interest in his units at El Matador along with the interests of the other El Matador condominium unit leaseholders included 150 feet of private beach landward of the 150 feet of public beach adjacent to the MHWL of the Gulf of Mexico. His lawyer, moreover, advised him not to convert his leasehold interest into a fee simple ownership in order to protect his interest in access to the private beach designated by the Protective Covenants and Restrictions. See Tr. 986-87. Mr. Donovan is concerned about the erosion and turbidity impacts the borrow site could have on the Gulf and the beach. Erosion would change his view of the beach from the window of his condominium unit and aggravate a scalloping of the shore. The unevenness of the scalloped surface would cause him difficulties in his walks. Turbidity could attract sharks which would make it unsafe for him to swim. Most importantly to him, a change in the beach and shoreline along the El Matador Condominium property as drastic, in Mr. Donovan's view, as that contemplated by the Draft JCP could deter his family members (his grandchild included) from visiting him and vacationing at his unit in the El Matador Condominium. The Guidry Petitioners and Their Property Roland Guidry, a retired Colonel in the United States Air Force, is co-trustee of the Guidry Living Trust and the President of the Oceania Owners' Association, a condominium association governed by chapter 718, Florida Statutes. The Guidry Living Trust is the owner of Condominium Unit 605 in the Oceania Condominium, a condominium established under chapter 718, Florida Statutes. The address of the unit is 720 Gulf Shore Drive, Unit 605, Destin, Florida, 32541. In his capacity as co-trustee, Mr. Guidry has the independent power to protect, conserve, sell, lease or encumber, or otherwise to manage and dispose of trust assets, which include Unit 605 in the Oceania Condominium. The Oceania Owners' Association is mandated by the Oceania Declaration of Condominium to "maintain, manage and operate the condominium property." Ex. P-6 at 4. The declaration also declares, "[a]ll unit owners shall automatically become members of the association after completion of closing of the purchase of a unit in Oceania, A Condominium." Id. The Guidry Living Trust, therefore, is a member of Oceania Condominium Association. The powers of the officers and directors of the Oceania Owners' Association are set forth in the Declaration of Condominium that governs Oceania: The officers and directors of the association shall have the powers set forth in this declaration and the association bylaws, and shall, at all times, have a fiduciary relationship to the members of the association and shall operate and manage the association in the best interest of its members. Id. Oceania's Declaration of Condominium, furthermore, prescribes that "[t]he association shall have all powers granted by Chapter[s] 718 and 617, Florida Statutes." Id. at 5. Every member of the Oceania Owners' Association Board of Directors approved the initiation of Case No. 10-0516, according to the testimony of Colonel Guidry, but there was no documentary evidence offered that a vote had been taken of the Board of Directors at a board meeting on the issue of whether to file the petition that initiated Case No. 10-0516 or the outcome of any such vote. As an owner of a unit in Oceania, The Guidry Living Trust owns an undivided share of the Oceania Condominium's common property10/ which "comprise[s] all the real property improvements and facilities to Oceania, A Condominium, including all parts of the building other than the units . . . and . . . [certain] easements . . . ." P-6 at 1, 2. The Oceania Condominium real estate is deeded to the "APPROXIMATE MEAN HIGH WATER LINE OF THE GULF OF MEXICO". P-6, Exhibit "B." The Surveyor's Certificate on the survey of Oceania, A Condominium, attached to the Oceania Declaration of Condominium is dated January 16, 1996. The date is more than two months after Hurricane Opal made landfall and damaged the Okaloosa County coastline in October of 1995. Standing of the Oceania Petitioners Colonel Guidry did not appear at hearing in a personal capacity. He appeared in his capacities as co-trustee of the Guidry Living Trust and President of the Oceania Owners' Association. In contrast to the Sherry Petitioners, therefore, Colonel Guidry did not allege his personal use and enjoyment of the beach as a basis for standing. As to injury and standing of both the Guidry Living Trust and the Oceania Owners' Association, Colonel Guidry asserted a number of interests that he believed will be substantially affected by the Project. They fall into four categories of concern. The first concern is with regard to the action of the sand along the shoreline of the Oceania property after the two reaches of beach to the east and west will have been restored under the revisions to the Draft JCP. After construction activities, sand along the shoreline will equilibrate, that is, the sand will move or be transported so as to stabilize the shoreline. This stabilization or achievement of shoreline equilibrium will tend to move the shoreline along the Oceania property waterward. Colonel Guidry expressed his concern as follows: [The Oceania property] would be sandwiched . . . between two public beaches . . . mother nature will fill in what I call the Oceania Gap. Right now the only line we have on our beach is our southern property line [the MHWL of the Gulf][11] . . . . That's the only line I know of that's on our beach or will be placed on our beach. But if sand fills in, then that creates a cloud of confusion, if the State lays claim to this sand that accumulates in the Oceania Gap, as a result of the construction on both sides of us. Tr. 764, (emphasis added). The second category of concern relates to the location of the property post-construction between "two public beaches." Such a location, in Colonel Guidry's view, would make individual units at the Oceania Condominium less valuable. The third category is that the public would be more likely to trespass on private Oceania property. The fourth concern of Colonel Guidry is that the Project will have undesirable impacts to Oceania property owners' littoral rights to accretion and to touch the water. The first three concerns all stem from a decision made by the Board of County Commissioners after this proceeding was commenced to remove the Oceania property from the Project. Oceania Removed The beach and shore in the southern part of the Oceania condominium property,12/ (the "Oceania Beach Segment of Shoreline" or the "Oceania Gap") were originally subject to the Consolidated NOI for the Western Destin Beach Restoration Project. But on the eve of the date scheduled for the commencement of the final hearing in these cases, the Board of County Commissioners for Okaloosa County voted to remove the Oceania Beach Segment of Shoreline from the application for the Project. Taylor Engineering (the County's Agent) submitted a request to the Department that reads: On behalf of Okaloosa County, Taylor Engineering submits its request to modify the project area and Draft Joint Coastal Permit for the Western Destin Beach Restoration Project . . . The applicant has decided to remove the Oceania Condominium Property from the beach fill placement area. The revised project, as described in the enclosed permit drawings, includes two reaches: Reach 1 extends from the east jetty of East Pass to approximately 600 ft east of FDEP reference monument R-22 (R-22.6) and Reach 2 extends from approximately 200 feet east of R-023 (R- 23.2) to R-25.5. The Oceania Property defines the gap between Reach 1 and Reach 1. Additionally, we request the FDEP modify Specific Condition 1 of the Draft Joint Coastal Permit to reflect the modified project area. More specifically, we request that the Mean High Water Line Survey requirement of Specific Condition 1 exclude the Oceania Condominium property. Notice of Filing Request for Modification and Revised, Draft Joint Coastal Permit, Exhibit A. Revisions to the Original Draft JCP In light of the vote and based on the County's request, DEP filed a Revised Notice of Intent on July 26, 2010, which included revision of the Draft JCP (the "First Revised Draft JCP"). The First Revised Draft JCP eliminated the Oceania Beach Segment of Shoreline from the Project and took other action such as requiring the applicant to check for oil in the OK-A Borrow Area prior to construction by both visual inspection and analysis of sand samples because of the ongoing Deepwater Horizon Oil Spill in the Gulf. The revision also included changes to Specific Condition 5 of the Draft JCP.13/ On August 18, 2010, the Department gave notice of another revision of the JCP (the "Second Revised Draft JCP"). The Second Revised Draft JCP changed Specific Condition 1 of the JCP by eliminating the requirement that the County establish a pre-project MHWL prior to undertaking construction activities and instead requires the County to conduct a survey in order to locate an erosion control line ("ECL"). The revisions to the Draft JCP stirred interest in participating in this proceeding among a group of property owners who do not want the beaches along their properties restored: the MACLA Intervenors. The MACLA Intervenors and Their Properties On September 8, 2010, a petition to intervene (the "MACLA Petition to Intervene") was filed by nine putative intervenors: MACLA LTD II, a Limited Partnership ("MACLA"); H. Joseph Hughes as Trustee of the Betty Price Hughes Qualified Vacation Residence Trust ("Hughes Trust"); Kershaw Manufacturing Company, Inc. ("Kershaw"); Kayser Properties LLC ("Kayser"); Destin, LLC ("Destin"); Paul Blake Sherrod, Jr., and Cindy M. Sherrod ("Sherrods"); Blossfolly, LLC ("Blossfolly"); 639 Gulfshore, LLC ("639 Gulfshore"); and Laura Dipuma-Nord ("Nord"), (collectively, the "MACLA Intervenors.") All nine of the MACLA Intervenors own real property in the City of Destin within the Project area that fronts the Gulf of Mexico. All nine properties have the MHWL of the Gulf as their southern boundary. MACLA is a Texas Limited Partnership. Louise Brooker is its president. The address of its property is 620 Gulf Shore Drive. The Hughes Trust owns a one-third interest in real property at the address of 612 Gulf Shore Drive. H. Joseph Hughes is a trustee of the Hughes Trust. Kershaw is an Alabama corporation. The address of its property is 634 Gulf Shore Drive. The address of the Kayser property is 606 Gulf Shore Drive. The address of the Destin property is 624 Gulf Shore Drive. The address of the Sherrods' property is 610 Gulf Shore Drive. The address of the 639 Gulfshore property is 6346 Gulf Shore Drive. The address of the Blossfolly property is 626 Gulf Shore Drive. The address of Ms. Dipuma-Nord is 600 Gulf Shore Drive. The properties owned by the MACLA Intervenors are among 18-single family lots located between a rough mid-point of reference markers R-020 and R-021 and a rough mid-point of reference markers R-022 and R-023. See Ex. P-238. These 18 single-family lots are in the approximate middle of the Project. The Oceania property, eliminated from the Project at the time of the filing of MACLA Petition to Intervene, is just to the east of the 18 single family lots in which the properties of the MACLA Intervernors are located. (Reference marker R-023 is set along the shoreline adjacent to the Oceania property.) The MACLA Intevenors' properties and the Oceania property are within the area from R-020.3 to R-023.3 (the "Middle Segment", see discussion of Critically Eroded Shoreline, below). According to an evaluation conducted by the Department on January 7, 2009, the Middle Segment of the beach is one in which "[u]pland development is not currently threatened." Ex. P-238. Timeliness of the MACLA Petition to Intervene The MACLA Petition to Intervene was filed well after the commencement of the hearing. Under rule 28-106.205, because it was filed later than 20 days before the commencement of the hearing, it could only be accepted upon "good cause shown" or if the time for filing were "otherwise provided by law." The MACLA Petition to Intervene was also filed after the Department had entered an order dismissing petitions for administrative hearings filed by three of the MACLA Intervenors14/ to contest the Second Revised JCP. The order of dismissal with prejudice by the Department dated September 7, 2010, was entered on the following bases: First, the Petitioners had a clear point of entry to challenge the proposed permit after it was publicly noticed on January 9, 2010. The Petitioners failed to timely challenge the proposed permit when given the opportunity to do so. Second, it is well settled that any proposed modifications to a proposed permit made during the course of a de novo proceeding to formulate final agency action do not create a new point of entry. Accordingly, the Petition is dismissed without prejudice to amend. Petition to Intervene, filed September 8, 2010, Ex. A, at 2 of 8. The Department was aware that the Western Destin Project "because of its size, potential effect on the environment, potential effect on the public, controversial nature or location, is likely to have a heightened public concern or is likely to result in a request for administrative proceedings." Consolidated NOI, at 13 of 17. The Department therefore took pains to ensure that parties affected by the Western Destin Project would be provided notice of the Project and have an opportunity to timely assert their rights to challenge the permitting and authorization of the Project. The Consolidated NOI required publication within 30 days in the legal ad section of a newspaper of general circulation in the area a public notice of the Consolidated NOI. It also required proof of publication. The County complied on both counts. A notice was published on January 9, 2010, in the Destin Log, in Okaloosa County. The public notice specifically identified the project location as between reference monuments R-16.6 and R-25.5 in Okaloosa County, which includes the segment of the shoreline adjacent to the MACLA Intervenors Property. The Department also provided a detailed statement of the "Rights of Affected Parties," including their right to petition for an administrative hearing pursuant to sections 120.569 and 120.57 within 14 days of receipt of written notice of the Consolidated NOI. The point of entry into the administrative proceedings to challenge the Consolidated NOI, therefore, in the case of affected parties with notice by virtue of the publication on January 9, 2010, expired on January 23, 2010. The section of the Consolidated NOI that governed the rights of affected parties also warned: Because the administrative hearing process is designed to redetermine final agency action on the application, the filing of a petition for an administrative hearing may result in a modification of the permit or even a denial of the application. * * * The failure of any person to file a petition within the appropriate time period shall constitute a waiver of that person's right to request an administrative determination (hearing) under Sections 120.569 and 120.57, F.S. Consolidated NOI, at 14 of 17. The MACLA Intervenors read the Destin Log at least on occasion and communicated with counsel for the Oceania Petitioners. Some believed they were represented by counsel for the Oceania Petitioners and had contributed to legal fees incurred by the Oceania Petitioners. Despite the foregoing, the MACLA Petition to Intervene was granted (subject to proof of standing) on the basis that the MACLA Intervenors had shown good cause for the filing after the deadline imposed by rule 28-106.205. At the time a point of entry into administrative proceedings was provided by the combination of the Consolidated NOI in December of 2009 and publication in the Destin Log of the notice on January 9, 2010, the Draft JCP called for the applicant to provide a survey of a Pre-project MHWL rather than the establishment of an ECL. Neither notice of the Second Revised Draft JCP, filed on July 26, 2010, nor the Second Revised Draft JCP, itself provided a point of entry into formal administrative proceedings to parties whose substantial interest were at stake. A new substantial interest, however, had been injected into the proceedings by the Second Revised JCP. The Second Draft JCP requires the establishment of an ECL as a condition of the permit in lieu of provision of a survey of Pre-project MHWL. The MACLA Intervenors promptly sought a point of entry to contest what is plainly a drastic change in circumstances with significant consequences to the boundary of their properties toward the shoreline with the Gulf of Mexico. The effect of this change and the difficulty of keeping up with beach restoration activities in Okaloosa County, particularly for affected persons whose permanent residence is elsewhere, was demonstrated by the testimony of Louise Brooker, who lives in Amarillo, Texas. When asked "[w]hy did you wait until September of this year [2010] to file the intervention?," she testified: [O]ur group thought that we were being represented by the Oceania group . . . when I did find out [the JCP had been issued], it was after the 30-day period . . . I hadn't been reading the Destin Log every day because it's very difficult to do, and then it changed. * * * Then it made a huge difference between using the mean high water line * * * And then the ECL being established, which was the ECL that I do not agree with, then that was being put in the permit. So that changed things a great deal. (emphasis added). Tr. 1526-7. Once their petitions for formal administrative proceedings had been dismissed with prejudice by the Department (or in the case of the MACLA parties whose petitions for an administrative had not been dismissed yet but appeared likely to meet the same fate), the MACLA Intervenors promptly sought relief through filing the MACLA Petition to Intervene. When the petition to intervene of the MACLA Intervernors was opposed by the County and the Department, the placement of the substantial interest at stake in the proceeding of a fixed ECL as the southern boundary of their property by the Second Revised JCP and the quick action of the MACLA Intervenors in contesting in contesting it was viewed as good cause for the filing of their petition later than required by rule. The Other Parties Okaloosa County is a political subdivision of the State of Florida and the applicant for the JCP, the Variances and the SSL Authorization. The Department is the state agency responsible for administration of the state's regulatory authority as found in Part I of the Beach and Shore Preservation Act, chapter 161, Florida Statutes, and in particular, for the issuance of permits required by section 161.041 and the concurrent processing of "joint coastal permits" as allowed by section 161.055. It also serves as staff to the Board of Trustees of the Internal Improvement Fund and in that capacity handles the processing and issuance of SSL Authorizations. The Holiday Isle Intervenors are businesses and condominium associations, all of whose members own real property or conduct businesses along the segment of the beach to be restored by the Project. Their properties (unlike the Oceania property and the MACLA Intervenors' properties in the Project "gap" between R-22.6 and R-23.2) are along shoreline that has been designated by the state as critically eroded.15/ Critically Eroded Shoreline Florida Administrative Code Chapter 62B-36 governs the Beach Management Funding Assistance Program. It contains the following definition of "Critically Eroded Shoreline": "Critically Eroded Shoreline" is a segment of shoreline where natural processes or human activities have caused, or contributed to, erosion and recession of the beach and dune system to such a degree that upland development, recreational interests, wildlife habitat or important cultural resources are threatened or lost. Critically eroded shoreline may also include adjacent segments or gaps between identified critical erosion areas which, although they may be stable or slightly erosional now, their inclusion is necessary for continuity of management of the coastal system or for the design integrity of adjacent beach management projects. Fla. Admin. Code R. 62B-36.002(4), (the "Critically Eroded Shoreline Rule"). The Department determines whether upland development, recreational interests, wildlife habitat or cultural resources are threatened or lost based on a 25-year storm event. Consideration of the Project on this basis leads to the Project being broken into three segments: a segment from R-17 at the west end of the Project to roughly R-20.3 (the "Western Segment"); a segment roughly between R-20.3 and R-23.2 (the "Middle Segment"); and a segment roughly between R-23.2 and R-25.5 (the "Eastern Segment"). Mr. Clark described the impact of a 25-year storm event on the Western and Eastern Segments: [T]hose two areas, based on the evaluation and the projection of the impact of a 25-year storm event, which is a high frequency storm event, showed that there would be erosion through deflation of the beach profile and recession of the shoreline to such an extent that upland development and infrastructure would be threatened. Tr. 499. As for the Middle Segment, "the same evaluation did not show that the 25-year storm event would provide that same level of threat." Id. The Middle Segment, however, for the purposes of continuity of the management and design integrity, was also designated as Critically Eroded Shoreline and the entire stretch of shoreline, including all three segments, Western, Middle, and Eastern, was originally included in the Project.16/ The Project With the elimination of the Oceania Gap, the Project calls for the placement of 831,000 cubic yards or so17/ of beach- quality sand along 1.7 miles (less the 600 feet of the Oceania Gap) of shoreline within the City of Destin between reference monuments R-16.6 and R-22.6 and between R-23.2 and R-25.5. The Project is designed to restore the shoreline to conditions that existed before Hurricane Opal in 1995. The useful life of the Project is estimated to be eight years. The Project will restore beach along 32 separate parcels of property, 31 of which are privately owned. The exception is a small area of publicly owned beach at the extreme west end of the Project. The Project's Construction is intended to be facilitated by hopper dredge. The dredge excavates at a borrow site. A ship brings the excavated material to the beach fill site where it is discharged by pipe onto the beach. The pipeline runs perpendicular to the shore and extends about a quarter of a mile offshore. The contractor normally fences off a work zone that is about 500 feet wide. The work zone moves along the beach as construction progresses. "[I]n that work zone, there is a lot of heavy equipment that moves the sand around . . . looking at the Project . . . [from] an aerial view, roughly half the sand will be placed seaward and half the sand . . . landward of . . . [the] Mean High Water Line." Tr. 139. The Project's construction template or "the shape of the beach when it[']s constructed," id., consists of a dune, a back berm and a wide variable berm. The dune has an elevation of 8.5 feet and a crest width of 30 feet. The berm has an elevation of 5.5 feet. The width of the construction varies but averages about 200 feet. Over the first several months following the Project's construction, a calibration process takes place. About half of the berm erodes and deposits offshore in a near shore sand bar. "That near shore bar acts as a wave break . . . and dissipates wave energy during storms. So having a good healthy bar out there can definitely provide storm protection." Tr. 140. "Using "two to 250 feet a day,"18/ as a "good approximation for the progress . . . [in] constructing the"19/ Project, construction on any particular individual property should take between one or two days "depending on how . . . wide the property is and how fast the construction progresses." Tr. 141. A property along a lengthier segment of the beach, like the 600 feet at the seaward boundary of the Oceania Property had it remained a part of the Project, therefore, would take "two to three days." Tr. 142. Storm erosion models on the construction berm showed that the Project will provide protection from a fifty-year storm. Selection of the Sand Source: Borrow Area OK-A The engineers of the Project, ("Taylor Engineering," the "Project's Engineers" or the "Engineers") examined the Gulf's underwater expanse from Santa Rosa County to Walton County seaward to Federal waters. The search for a sand source included a reconnaissance phase and a detail phase investigation of geophysical and geotechnical data. After exhaustive study, two potential borrow areas were identified: a "far-shore" site and a "near-shore" site. The far-shore site is eight miles offshore and about a mile east of East Pass and is designated "OK-B." The near-shore site, three miles west of East Pass and centered about a mile and a quarter from the shores of the Okaloosa Island part of Santa Rosa Island, is designated "OK-A." With its edge within the designated Outstanding Florida Water boundary of the Gulf Islands National Seashore Park, it is within a relic ebb tidal delta in water depths of -36 to -51 feet, NGVD. Approximately 1.7 miles wide from east to west and approximately 0.9 miles wide north to south, it covers approximately 700 acres. At its landward-most side, it will be dredged to 10 feet into the existing bottom. Reference in documents of Taylor Engineering and the County to OK-A as the "near-shore site" does not mean it is located in the "nearshore" as that term is used in coastal geology. The coastal geologic term "nearshore" refers to the zone from the shoreline out to just beyond the wave breaking zone.20/ Borrow Area OK-A is well beyond the nearshore. It is clearly located "offshore," in "the relatively flat zone that is located from the surf breakers seaward out to the outer limits of the continental shelf."21/ Tr. 513. It is referred as the near- shore site by Taylor and the County to distinguish it from OK-B which is farther offshore and therefore was referred to as the "farshore site." The two sites, OK-A and OK-B, were selected for comparative review on three bases: sand quality; financial impact; and dredging impacts. Sand quality is "the number one criteri[on]." Tr. 143. It involves grain size, soil and shell content, and sand color. Financial impact is determined mainly by distance; the farther from the construction site, the more expensive to transport the sand. If the borrow area is close enough to shore, a Borrow Area Impact Analysis is conducted. An impact analysis was not conducted for OK-B. The Engineers assumed on the basis of its 8 miles distance from shore that it would not impact the shoreline in any way. The assumption was a reasonable one. Impacts to the shoreline or beach from the dredging of OK-B are unlikely.22/ A Borrow Area Impact Analysis was conducted of OK-A. The quality of the sand in OK-B was similar to that of OK-A but OK-A's "was slightly better." Tr. 144. The slight difference was not a significant factor in the determination that OK-A should be selected. The main factor in favor of OK-A was distance. Because it is so much closer to the Project than OK-B, use of OK-A "substantially reduces the cost of construction" id., compared to OK-B. Taylor Engineering (and ultimately the County) selected OK-A as the sand source. The selection process included a sand source investigation by Taylor. Taylor Engineers' final report on sand source was released in October of 2009. The report shows that in OK-A, the southeast corner of the area "seemed to contain a lesser quality sand than the borrow area as a whole and in terms of color." Tr. 145. Sand from the southeast corner of OK-A, nonetheless, was used in two beach restoration projects, both on Eglin Air Force Base property. Those projects were denominated A-3 and A-13.23/ The selection of OK-A was not upset by Taylor Engineering's OK-A Borrow Area Impact Analysis. Borrow Area Impact Analysis An Okaloosa County Sand Search Borrow Area Impact Analysis was prepared by Taylor Engineering for the Joint Coastal Permit Application and released in July of 2008. Aware that dredging the borrow site could affect both wave climate and current (the swift flow of water within a larger body of water), Taylor examined the impact of dredging the OK-A Borrow Area for those effects in the borrow area vicinity. The ultimate purpose of the Borrow Area Impact Analysis, however, was larger. It was to determine the changes to wave and current climate for impact to the beach, such as erosion. An increase in wave height, for example, would increase erosion. Two numerical modeling efforts were conducted. The first, called STWAVE, documents the impacts to wave climate. The second, ADCIRC, analyzes the effects of the dredging on currents. The STWAVE model requires wave characteristics as input. Taylor Engineering used "a 20-year hindcast of wave data from a WIS station located directly offshore in deep water. Under STWAVE modeling, impacts were examined for normal conditions and then 'under a 100-year storm condition.'" Tr. 149. The basis was the 100-year storm data from Hurricane Opal. The impacts of bottom friction were ignored, a common practice in applications like the County's JCP application that involves work on the open coast with a uniform sandy bottom. As Mr. Trudnak put it: Tr. 150. When you use . . . wave monitoring devices, you're trying to calibrate a model for the effects of bottom friction. And when the borrow area is this close to shore [as in the case of OK-A], . . . the propagation of distance of the waves is relatively short. And when you have a uniform sandy bottom you don't expect the impacts of bottom friction to be significant. So . . . in applications like [Okaloosa County's for the Western Destin Project], you ignore the effects of bottom friction. The analysis assumed that all of the sand in the borrow area would be removed when, in contrast, "the borrow site usually contains 50 percent more sand than what the Project requires on the beach." Tr. 152. In the case of OK-A, it is intended to serve the Eglin Air Force Base Project, the Okaloosa Island Project and the Western Destin Project. These projects require 4.7 million cubic yards of sand of the nearly 7 million cubic yards of sand available in OK-A. The impact analysis, therefore, was conservative in that it predicted more impact than would actually occur because significantly less sand would be removed from the site than was factored into the STWAVE modeling. With regard to normal conditions, the STWAVE modeling led to the conclusion that impacts from the permitted activities associated with the borrow area would be negligible. Under storm wave conditions, the STWAVE modeling showed "a certain wave angle or direction that increased the wave height." Tr. 151. The increase in wave height, however, was far enough offshore so as to never affect the "actual breaking wave height on the beach." Id. The modeling results enabled Taylor Engineering to conclude "that the borrow area did not have a potential to cause any impacts whatsoever." Tr. 152. ADCIRC is a state-of-the art hydrodynamic model that simulates tidal currents. Taylor Engineering conducted the ADCIRC modeling to analyze effects on the tidal currents and circulation in and around East Pass that would be caused by dredging the borrow area. Just as in the case of STWAVE, ADCIRC modeling showed that the impact of dredging the borrow area would be negligible whether in normal or "storm" conditions. The Application Coastal Construction Permits and CCCL Permits The Application was processed as one for a joint coastal permit (a "coastal construction" permit under section 161.041). It was not processed as an application for a coastal construction control line ("CCCL") permit. Section 161.041 (the "Shore Protection Statute") and chapter 62B-41 apply to JCPs. Section 161.053 (the "CCCL Statute") and chapter 62B-33 govern CCCL permits. The Department treats its JCP and CCCL permitting programs as independent from each other and as mutually exclusive permitting programs. A project that involves "beaches and shores" construction is permitted under one permitting program or the other but not under both permitting programs. See Tr. 424-5. Indeed, when it comes to beach restoration projects (or "shore protection" projects) such as the Western Destin Project, section 161.053 of the CCCL Statute provides as follows in subsection (9): "The provisions of this section do not apply to structures intended for shore protection purposes which are regulated by s. 161.041 [the Shore Protection Statute] " The Department interprets section 161.053(9) to exempt the Project from CCCL statutory requirements and the rules that implement the CCCL Statutes so that the only permit the Project requires, in the Department's view, is a JCP. b. The "Written Authorization" Provision Chapter 62B-14 is entitled "Rules and Procedures for Applications for Coastal Construction Permits." The Shore Protection Statutes serves as rule-making authority for every rule in 62B-41. Every rule in the chapter, moreover, implements, among other provisions, one provision or another of the Shore Protection Statute. Rule 62B-41.008 derives its rule-making authority from the Shore Protection Statute and section 161.055(1) and (2). Among the statutory provisions it implements are four subsections of the statute: (1), (2), (3) and (4). Section (1) of rule 62B-41.008 provides, in pertinent part, as follows: A Joint Coastal Permit is required in order to conduct any coastal construction activities in Florida. A person required to obtain a joint coastal permit shall submit an application to the Department . . . The permit application form, entitled "Joint Application for Joint Coastal Permit, Authorization to Use Sovereign Submerged Lands, Federal Dredge and Fill Permit" . . . is hereby incorporated by reference . . . . The application shall contain the following specific information: * * * (c) Written evidence of ownership of any property which will be used in carrying out the project, or authorization for such use from the property owner which is upland of mean high-water, or below mean high water but not sovereign land of the State of Florida. * * * (n) Written authorization for any duly- authorized member of the Department staff to enter upon any property to be used in carrying out the project, for the purpose of evaluating site conditions prior to final processing of the permit application. (emphasis added). Rule 62B-41.008(2) (the "Waiver Provision") lists requirements of rule 62B-41.008(1) which are to be waived by the Department under circumstances described in the Waiver Provision: "Any of the requirements contained in paragraph 62B-41.008(1)(f), (h), (i), (j), (k), (l), or (m), F.A.C., will be waived if the Department determined that the information is unnecessary for a proper evaluation of the proposed work." In its list of requirements that will be waived under certain circumstance, the Waiver Provision does not include paragraphs (c) or (n). The Application did not contain the "specific information" detailed in paragraphs (c) and (n) of rule 62B- 41.008(1). It did not contain written proof of ownership of any property that will be used in carrying out the Project nor did it contain authorization for such use from the property owner upland of mean high-water, information required by paragraph (c). It did not contain written authorization for any duly-authorized member of the Department staff to enter upon any private property to be used in carrying out the Project for the purpose of evaluating the site conditions prior to final processing of the permit application, information detailed in paragraph (n). As of the dates of final hearing, the County had not provided the Department with any written authorizations from the owners of the 31 privately-owned properties within the Project area, including the MACLA intervenors. As part of the Application, however, the County requested a waiver of the requirements related to authorizations. A waiver was requested under number 14 of the Application. It provides: Satisfactory evidence demonstrating that the applicant has sufficient control and interest in the riparian upland property, as described in Section 18-21.004(3)(b), Florida Administrative Code. Governmental entities that qualify for the waiver of deferral outlined in this rule must provide supporting documentation in order to be eligible. If the applicant is not the property owner, then authorization from property owner for such use must be provided. Joint Ex. 1, at 3 of 9. The County, through its agent, Taylor Engineering, responded to number 14 of the Application as follows: Response: The applicants request a waiver of the requested information under Rule 18- 21.004(3)(b), which grants an exception to the upland interest requirement for restoration and enhancement (e.g. nourishment) activities conducted by a government agency. According to Rule 18- 21.004(3)(b), satisfactory evidence of sufficient upland interest is not required for the proposed activity, because the proposed offshore borrow area is not riparian to uplands and the beach fill activities will not unreasonably infringe on riparian rights. Joint Ex. 1, Attachment A, at 3rd un-numbered page. Rule chapter 18-21 governs Sovereignty Submerged Lands Management. Rule 18-21.004(3)(b) ("the Upland Interest and Riparian Rights Rule") provides as follows: (3) Riparian rights. * * * (b) Satisfactory evidence of sufficient upland interest is required for activities on sovereign submerged land riparian to uplands, unless otherwise specified in this chapter. * * * Satisfactory evidence of sufficient upland interest is not required . . . when a governmental entity conducts restoration and enhancement activities, provided that such activities do not unreasonably infringe on riparian rights. (emphasis added). Item number 18 of the Application calls for signatures related to "any proprietary authorizations identified above," such as those identified in item number 14. Consistent with the request for a waiver from providing the requested information with regard to satisfactory evidence demonstrating sufficient control and interest in the riparian upland property, no signatures were provided by the County or its agent. Rule 62B-49.003(3), entitled "Policy" provides: Any application submitted pursuant to this chapter shall not be deemed complete, and the timeframe for approval or denial shall not commence until the Department has received all information required for: a coastal construction permit under Section 161.041, F.S., and Chapter 62B-41, F.A.C.; an environmental resource permit under Part IV of Chapter 373, F.S., and Title 62, F.A.C.; and a proprietary authorization, under Chapter 253, F.S., and Chapters 18-18, 18-20 and 18-21, F.A.C. See the material bound and attached to the Request for Official Recognition filed August 2, 2010, Tab "Chapter 69B-49, F.A.C." The Department deemed the Application complete on December 30, 2009. Amendment of the JCP re: Written Authorizations The petition for formal administrative hearing filed in Case No. 10-0516 challenged the Consolidated NOI on the bases, inter alia, that the Application had failed to "provide 'sufficient evidence of ownership' as defined in rule 62B- 33.008(3)(c), F.A.C., to be a proper applicant for the Permit"24/ and that the County had not "provided satisfactory evidence of sufficient upland interest to be entitled to a letter of consent to use sovereign submerged lands."25/ To support their allegation that the County is not a proper applicant for the JCP, the Oceania Petitioners amended their petition on July 13, 2010, to add the following: The County must provide the Department "[w]ritten evidence of ownership of any property which will be used in carrying out the project, or authorization for such use from the property owner which is upland of mean high-water, or below mean high-water but not sovereign land of the State of Florida", as required by [paragraph (c) of the JCP Application Specific Information Rule]. The Department must receive "[w]ritten authorization for any duly-authorized member of the Department staff to enter upon any property to be used in carrying out the project, for the purpose of evaluating site conditions prior to final processing of the permit application", as required by Rule 62B- 41.008)1)(n), F.A.C. The Amendment was made despite the existence in all of the versions of the Draft JCP, the original version and the revised versions, of General Condition Six: This permit does not convey to the Permittee or create in the Permitee any property right, or any interest in real property, nor does it authorize any entrance upon or activities on property which is not owned or controlled by the Permittee. The issuance of this permit does not convey any vested rights or any exclusive privileges. Joint Ex. III at Tab 9 at 4 of 26. With the filing of the Oceania Petitioners' Second Amended Complaint in Case No. 10-0516, the issues appeared to be fully joined. Before the case proceeded to hearing, however, the County voted to remove the Oceania Property from the Project (see paragraphs 31 and 32, above). The vote led to a formal request from the County to DEP to revise the Project and a revision by the Department of the Project's drawings and the Draft JCP (the "First Revised Draft JCP"), notice of which was filed on July 23, 2010. The revisions to the Draft JCP necessitated by the elimination of the Oceania property from the Project was not the only revision made to the Draft JCP as noticed on July 23, 2010. The Department also revised the Draft JCP's Specific Condition 5. This latter revision prompted the Sherry Petitioners to file a petition for an administrative determination concerning un- adopted rules. DOAH assigned the petition Case No. 10-6205RU. During the final hearing, the Department revised the Draft JCP a second time (the "Second Revised Draft JCP".) The second revision inspired the MACLA Petitioners' petition to intervene. Just as with the Sherry Petitioners, the revision to Specific Condition 5 prompted the MACLA Petitioners to petition for an administrative determination concerning un-adopted rules. DOAH assigned this second un-adopted rule challenge to Specific Condition 5 Case No. 10-8197RU. Case Nos. 10-6205RU and 10-8197RU In general, the revision to the Draft JCP's Specific Condition 5 advised the County that no beach restoration work can be performed on private upland property unless authorization from the owner of the property has been obtained and submitted to the Department ("the Upland Property Authorization Requirement"). The revision also provided an exception to the Upland Property Authorization Requirement: the County could submit an authorization from a court of competent jurisdiction that such an authorization is not required. Case Nos. 10-06205RU and 10-8197RU were heard at the same time as these consolidated cases.26/ A final order was issued with regard to the two cases on November 4, 2010. The final order dismissed the case because the Sherry Petitioners and the MACLA Petitioners had not demonstrated that they would be "substantially affected" by Specific Condition 5 as required by section 120.56(3) for a party to have standing to challenge an agency statement that constitutes a rule which has not been adopted pursuant to the rule-making procedures found in section 120.54(1)(a). Case Nos. 10-6205RU and 10-8197RU were two of three petitions seeking administrative petitions concerning un-adopted rules that were consolidated and heard with the consolidated cases subject to this Recommended Order. The third was a case that had been filed by the Oceania Petitioners earlier in the proceeding: Case No. 10-5384RU. Case No. 10-5384RU Case No. 10-5384RU was filed by the Oceania Petitioners in order to challenge as an un-adopted rule Specific Condition 1 as it appeared in the Original Draft JCP ("Original Specific Condition 1"). Original Specific Condition 1 contained several requirements. In general, it required the County to record a certificate before the commencement of construction associated with the Western Destin Project. The certificate was required to describe all upland properties along the shoreline of the Project. The certificate was also required to be accompanied by a survey of a pre-project mean high water line (the "Pre-project MHWL) along the entire length of the Project's shoreline. The case claimed that the Department had made another statement that constituted an un-adopted rule which violated the rule-making provisions of chapter 120: "that an Erosion Control Line (the 'ECL') is not required to be established pursuant to Section 161.161, Florida Statutes, for a beach restoration project unless 'state funds' are used for the construction (as opposed to just the design) of a beach restoration project." Case No. 10-5384RU, Petition for an Administrative Determination Concerning Unadopted Rules, at 2. During the course of the final hearing, however, the Department filed a notice of a set of revisions to the First Revised Draft JCP. These revisions (the "Second Revised Draft JCP") included a revision of Specific Condition 1. The Second Revised Draft JCP The notice by the Department that alerted the parties to the Second Revised Draft JCP was filed on August 18, 2010. The August 18, 2010, Notice contains two changes to the First Revised Draft JCP. The first change deletes entirely the existing language in Original Specific Condition 1 (the language challenged in Case No. 10-5384RU). It substitutes the following language: Prior to construction of the beach restoration project, the Board of Trustees will establish an Erosion Control Line along the shoreline of the beach restoration project. The Erosion Control Line shall be established consistent with the provisions of ss. 161.141-161.211, Florida Statutes. An Erosion Control Line shall not be established in conjunction with this joint coastal permit with respect to the shoreline seaward of the Oceania Owner's [sic] Association, Inc. members' common elements property. In lieu of conducting a survey, the Board of Trustees may accept and approve a survey as initiated, conducted, and submitted by Okaloosa County if said survey is made in conformity with the appropriate principles set forth in ss. 161.141-161.211. Department of Environmental Protection's and Board of Trustees of the Internal Improvement Fund's Notice of Revisions to the Proposed Joint Coastal Construction Permit, page 3 of 4. Thus, the first change noticed by the Department on August 18 deleted the requirement that the County submit a survey of a Pre-project MHWL. It requires, instead, that the county establish an ECL consistent with applicable statutory provisions. The second change was made with respect to Specific Condition 4(c) of the First Revised Draft JCP, which lists items to be submitted to the Department for approval prior to the commencement of construction and the issuance of a Notice to Proceed (with construction) by the Department. The existing language was deleted in its entirety and the following language was substituted: Id. Written documentation that the Erosion Control Line required by Special Condition Number 1 has been filed in the public records of Okaloosa County. Disposition of Case No. 10-5384RU The same Final Order that disposed of Case Nos. 10- 6205RU and 10-8197RU disposed of Case No. 10-5384RU. The Petitioners in Case No. 10-5384RU were found to lack standing to challenge Original Specific Condition 1 and the petition that initiated the case was dismissed. In addition, the Final Order concluded that had the Petitioners had standing to bring the challenge, the case would still have been decided in favor of the Department. This conclusion was based on the remedy called for by section 120.57(1)(e).27/ That remedy was found to have been achieved when the Department changed Specific Condition 1 to require an ECL rather than a Pre-project MHWL. See Final Order, Case No. 10- 5384RU (DOAH November 4, 2010). In addition to the record made with regard to the three rule challenges during the final hearing on the Sherry and Oceania Petitions, most of the rest of the evidence at the final hearing concerned the application of the regulatory authority of the Department and the Board of Trustees found in the Florida Statutes and the Florida Administrative Code, especially the environmental impacts of the Project as permitted by the Second Revised Draft JCP and as authorized under the Variance and the Sovereign Submerged Lands Use Authorization. Impacts The depth of OK-A should not exceed -49.4 feet, NGVD in an area where the depth of the ocean bottom is roughly -40 feet, NGVD. The excavation of the borrow site is designed in two dredging phases. The first phase, anticipated to provide up to 116 percent of the sand needed by the Project, is designed to a depth of 47.4 feet. "If for some reason, the contractor needs more sand . . ., then he can move into Phase II . . . [at a depth] of minus 47.4 to minus 49.4 feet [NGVD]. . . [,] a two foot deep layer throughout the entire borrow area." Tr. 165. OK-A is relatively wide, at least as compared to an existing borrow area not far away, the borrow area used for beach restoration in western Walton County and eastern Okaloosa County east of the City of Destin (the "Walton Borrow Area"). It is also a shallow borrow area when its depth is measured from the Gulf floor. It is in deeper water than the Walton Borrow Area. These factors make it less likely to cause impacts to the beach than the Walton Borrow Area.28/ Despite the width of OK-A, its relative shallowness measured from the Gulf floor, and its water depth, Dr. Dally, on behalf of the Petitioners, challenged the Taylor Engineering conclusion that there would be no impacts to the beach from the dredging of Borrow Area OK-A. The challenge from Dr. Dally, however, did not detail what the impacts would be or how serious they would be. Instead, Dr. Dally concluded that "not nearly enough study has been conducted of the proposed borrow area to ascertain that there will be no adverse impacts." Tr. 633. Dr. Dally's challenge to the conclusion by Taylor Engineering of no impacts to the beach from an excavated OK-A begins with an explanation in general of wave dynamics, sediment transport, and borrow site impacts. Wave Dynamics, Littoral Sediment Transport, and Borrow Site Impacts, Generally General Wave Dynamics "[W]aves in very deep water will start to turn and become more shore parallel in the case of Okaloosa County." Tr. 636. As they approach shore, a dynamic process of shoaling and refraction occurs. The waves may also become involved with diffraction. Shoaling is a growth in height from interaction with the shallow bottom or a shoal. Refraction is a process of alignment of waves with bottom contours. Diffraction is a spreading of waves or the bending of waves or change in wave direction after interaction with emergent structures or submerged features. As the process of shoaling, refraction and diffraction takes place, waves may be affected by bottom friction, depending on ocean bottom conditions. Dr. Dally offered the following description of wave changes as they close in on the face of the beach and approach interaction with the shoreline. The description includes the potential impacts of an excavated OK-A on the beaches and shores of Okaloosa Island adjacent to the Surf Dweller and El Matador condominium property: As they pass into the very nearshore . . . they, of course, grow in height. They then break . . . [or] [s]ometimes, as they pass over a [sand]bar, they'll stop breaking. And then begin breaking again when they get right up onto the beach face. Any time you put a bathymetric feature [such as a borrow area] into that otherwise natural system, you affect the wave transformation due to processes dependent upon the character of the perturbation . . . * * * Wave reflection from abrupt bathymetric changes. . . in this case, the landward most . . . notch of the borrow area would be a reflective surface . . . when something has perturbed the wave field like that, defraction [sic] becomes an important process. So, as the waves pass over this proposed borrow area and, especially, over the 10-foot or greater vertical face, they will reflect and begin defraction [sic] so that it becomes a . . . complicated wave field . . . . Tr. 636-7. In addition to the perturbation caused by the borrow area there is another factor at work that has the potential to affect the beach along the condominium properties owned by the Sherry Petitioners: sediment transport. Sediment Transport "Sand can move along or away from the beach in two ways." Tr. 1141. It can move along the shoreline or it can move offshore. Littoral transport of sediment, a factor important to erosion and accretion, is the movement of sediment, mostly sand, along or parallel to shore. It is caused by the intersection of waves that come ashore at an angle to the shoreline, rather than those that break straight onto the beach. The average net long-term littoral transport in the area of the Project and Okaloosa Island is east to west. The Sherrys and Mr. Donovan Petitioners own property down-drift from the OK-A site, or to the west. Dr. Young described the beaches down-drift of OK-A at hearing: "[t]hose beaches have, over the . . . last decade or so, been generally stable to accreting. There's a pretty nice beach out there right now." Tr. 1143. This area of the Okaloosa County's beaches and shores is the area most likely to be affected by an excavated OK- A if there are, in fact, any impacts to beaches and shores caused by the dredging of the borrow site. Borrow Site Impacts Two processes affecting waves in the Gulf would occur above an excavated OK-A Borrow Area. The first wave process would be "that part of the wave energy will actually reflect and go back out to sea," tr. 640, in essence, a scattering effect of the energy. Diffraction at the same time would cause the waves to radiate outwards from the borrow area rather than the waves going straight back out to sea. The second wave process creates the potential for the waves to become "very, very, complicated." Tr. 640. They could "trip", that is, the notch in the borrow area could break the waves. "[B]rag scattering" (tr. 641) could make the waves deteriorate into shorter period waves. If there are changes in waves, tide level or current, changes will be caused to the beach. As Dr. Dally succinctly put it at hearing, "[the beach] might erode, it might accrete, it might do both," tr. 641, by virtue of the presence of an excavated OK-A Borrow Area. If the impact of the excavation of the borrow area were to create shorter period waves, the result generally would be erosion. If the impact created longer period waves which generate water movement deep into the water column the result generally would be accretion. The borrow area has the potential in Dr. Dally's opinion to create both longer and shorter period waves. Wave angle of the waves breaking on the beach also is a factor in beach impacts. But Dr. Dally was unable to predict the impacts of the excavation of OK-A to Okaloosa Island beaches and shores without more study, data and analysis as to what effects a dredged OK-A would have on wave period and wave angle and the concomitant sediment transport. Just as Mr. Trudnak, Mr. Clark concluded that OK-A is too far offshore to cause adverse impacts to the beach. If, however, the Project were to utilize a borrow area along the same stretch of the beach but much closer to shore as in the case of the Anna Maria Island Project in which the borrow area was only 1000 feet from the shoreline, erosion impacts could occur on part of the beach. Beneficial impacts in such a case would occur to the beach downdrift of the borrow area. In the Anna Maria Island Project, beaches far enough to the south which were downdrift of the borrow area accreted. The impact to the Sherry and Donovan Properties, both being downdrift of a borrow area located along the same stretch of beach but within 1000 feet of shore and closer in than OK-A, would likely be beneficial. The area of shoreline that would be affected by wave impacts from an excavated OK-A is larger than the area in the immediate shadow zone of the borrow site, that is, a shadow zone perpendicular from the borrow site to the shore. The area affected by wave impacts depends on the angle of the waves. In the Destin area and along Okaloosa Island where the Sherry Petitioners reside, the waves come ashore predominately out of the east. If the waves come ashore along Okaloosa Island at a strongly oblique angle (more directly from the east), "the shadow zone now stretches further to the west and the diffraction pattern . . . increases the size of the shadow zone," tr. 680, to a size much larger "than the actual shadow zone of the . . . borrow area." Id. Along these same lines, if there are impacts to the beach caused by a dredged OK-A, the impacts should be greater the closer the beach is to the footprint of a dredged OK-A. Given the predominate tendency of the waves to come from the east along Okaloosa Island, if the beaches alongside both the Surf Dweller Property and the El Matador Property are affected, the beach alongside the Surf Dweller Property will incur the greater impact. Likewise, if beach impacts are incurred by beach alongside only one property or the other, it is much more likely that the beach alongside the Surf Dweller Property will be affected than the beach alongside the El Matador Property. Distance of an offshore borrow area from the shore is critical to the effect of the borrow area on diffraction and wave dynamics. If the borrow area is far off shore, as in the case of the alternative, potential borrow site identified by Taylor Engineering, OK-B, then, as explained by Dr. Dally, diffraction "has a lot of time and a lot of opportunity to smooth the waves out once again and things become uniform when they hit the beach." Tr. 645. A borrow area that is closer to the beach has higher potential for creating impacts. Dr. Dally again: "[I]f you move the borrow area closer to the beach, you have this scattering pattern induced by the reflection and the diffraction and refraction that doesn't have time to smooth itself out. And that's when you can really cause impacts to the beach, both accretive and erosive impacts." Id. (emphasis added). The underscored sentence from Dr. Dally's testimony quoted in the previous paragraph was directly addressed in the County's case through Mr. Trudnak's determination that OK-A, although not as far away as OK-B, is far enough away from the beach that it will not cause adverse impacts to the beach. Again, Dr. Dally's testimony, despite the underscored testimony in the previous paragraph, is not that OK-A will, in fact, cause impacts to the beach. His testimony, rather, is the equivalent of a statement that the closer a borrow area is to the beach the more likely that it will have impacts to the beach and that at some point, a borrow area, will be so close to the beach, that adverse impacts will occur. The fact that OK-A is much closer to the beach than OK-B does not mean that an excavated OK-A will cause impacts to the beach. Impacts of an excavated OK-A depend upon OK-A's actual distance from the beach rather than OK-A's distance relative to OK-B's distance. Thus, while it may be determined that the likelihood of impacts to the beach is greater in the case of OK-A than in the case of OK-B, actual impacts from OK-A to the beach (as far as the effect of distance) is a function of OK-A's actual distance from the beach without regard to OK-B's distance from the beach. In addition to Dr. Dally's certitude that there will be impacts to the beach by virtue of the presence of a dredged OK-A, Dr. Dally also took issue with the method by which Taylor Engineering reached the conclusion of no impacts in the OK-A Borrow Area Impact Analysis Report. The OK-A Borrow Area Impact Analysis Generally Mr. Trudnak was part of the Taylor Engineering team that prepared the Borrow Area Impact Analysis Report. Mr. Trudnak was not the only expert to defend the report's conclusion of no impact to the beach. The report was reviewed by Mr. Clark, the Department's expert, who also opined that there would be no impacts. Mr. Clark relied on more than the report for his opinion. He also relied on his extensive experience with beach restoration projects and monitoring data for those projects and visual observation of those projects post-construction. The only numerical data analysis specific to the excavation of the OK-A Borrow Area, however, that the Department used in determining that excavation of OK-A would not have any adverse impacts to the shoreline and coastal systems of Okaloosa Island was the Taylor Engineering OK-A Borrow Area Impact Analysis Report. The Report described its evaluative efforts: [T]his report evaluates two potential dredging templates in terms of their impacts on wave and tidal current patterns during normal and extreme conditions. The evaluation requires analysis of the wave climate and tidal currents before and after the borrow area dredging. The analysis required a balance between minimizing impacts to wave climate and current patterns, and providing acceptable nourishment volumes. STWAVE (Steady-State Spectral Wave Model) simulated normal (average) and extreme (100- year (yr) storm) waves propagating over the baseline and post-dredging bathymetries. ADCIRC hydrodynamic modeling simulated tidal flow over the baseline and post-dredging bathymetries for normal (spring) and extreme (100-yr storm) tide conditions. A comparison of the baseline and post dredging model results established the effects of borrow area dredging on the neighboring shorelines (Destin and Eglin AFB) and the inlet. County Ex. 1, Okaloosa County Sand Search Borrow Area Impact Analysis, at 6. Thus, the STWAVE modeling conducted by Taylor as part of the analysis attempted to simulate normal (average) and extreme (100-year storm) waves propagating over the baseline and post-dredging bathymetrics. Taylor Engineering relied on WIS (Wave Information Study) results in performing its STWAVE modeling. WIS data is not measured wave data. Instead, it consists of numerical information generated by specific stations in wind fields in various locations around the Gulf of Mexico. The data is then placed in a model coded to represent the entire Gulf. The WIS station from which data was collected by Taylor Engineering is located approximately 10 miles offshore where the depth is approximately 85 feet. It would have been preferable to have used comprehensive field measurement, that is, data obtained from wave gauges on both sides of the borrow area over enough time to support use of the data, rather than WIS data. Comprehensive field measurement would have produced much more information from which to predict impacts to the beach. As Dr. Dally explained, however, If you don't have [field measurement data], then . . . especially over the long-term . . . a year or more [or] if you're analyzing your beach profile data over a 10 year period, you would like to have . . . wave data to accompany that 10 year period. Generally we don’t and that's when we start relying on models to fill in this missing information. Tr. 645-6 (emphasis added). This testimony was consistent with Mr. Trudnak's testimony: the problem with field measurement is that "the useful data that you [get] from [field measurement] gauges is . . . limited to [the] deployment period." Tr. 1234. It is not practical to take 10 years' worth of field measurement. As Mr. Trudnak explained: Typically, you would install those gauges for . . . a month or a couple of months . . . you want to use representative conditions . . . you try to pick a winter month and a summer month so you can try to capture those extremes and wave conditions. * * * [W]hen you . . . install those gauges in the field, you have no idea what those conditions are going to be during your deployment period. You can install your wave gauge for a month in the winter but that can be an unusually calm month, it could be an unusually severe month. So, it's really hit or miss, whether you . . . capture representative conditions. Id. (emphasis added). The WIS information utilized is hind-casted. Hind- casting is a method for developing deepwater WIS data using historic weather information to drive numerical models. The result is a simulated wave record. The WIS information utilized includes 20 years of hind-cast information. The purpose of using such a lengthy period of information is that it ensures that representative conditions are captured in the data for purpose of the analysis. Such "lengthy period" information overcomes the concern that there is not enough data to capture representative conditions as in the case of typical field measurement data. For its extreme STWAVE modeling, Taylor relied on WIS information generated during Hurricane Opal in 1995. Analysis of the model results showed negligible impacts on wave height under normal conditions and increased wave height during extreme conditions. Increased wave height during extreme conditions, however, was no closer than 300 feet from the shoreline. The increased wave height and wave angle in storm conditions were far enough offshore that they "never impacted the actual breaking wave height on the beach." Tr. 151. The model's prediction of no impacts in wave height on the shoreline due to a dredged OK-A and no change in sediment transport rate by virtue of the presence of a dredged OK-A led Taylor Engineering to conclude that whether in normal or extreme conditions, a dredged OK-A Borrow Area would not cause impacts to the beaches and shores of Okaloosa County. Criticisms of Taylor's STWAVE Modeling Dr. Dally offered four basic criticisms of Taylor Engineering's STWAVE Modeling: a) the model did not account for wave transformation processes caused by bottom friction between the WIS Station (10 miles out in the Gulf) and the OK-A site; b) the model was not calibrated or verified; c) the model did not sufficiently account for wave transformation impacts from the dredging of Site OK-A; and d) Taylor did not plot wave direction results from its STWAVE models or conduct any sediment transport analysis. Mr. Trudnak offered refutations of the criticisms. For example, taking the first of them, wave transformation processes caused by bottom friction between the WIS Station and the OK-A site were not accounted for by Taylor Engineering in its analysis because "most of that distance [between the WIS Station and the OK-A site] is deep water, meaning the waves aren't . . . feeling the bottom so they're not being affected by the bottom friction." Tr. 1236. The refutations were not entirely successful. The second of Petitioners' experts, Dr. Young cast doubt on the validity of all modeling no matter how well any particular modeling activity might meet the criticisms leveled by Dr. Dally against Taylor Engineering's effort. Dr. Young accepted Dr. Dally's testimony about why Taylor Engineering's modeling were not sufficient to support an opinion of "no impacts", but he differed with Dr. Dally as to whether coastal engineering models should be utilized to predict impacts to beaches.29/ See Tr. 1157. Dr. Dally believes in the benefits of modeling as long as the modeling is conducted properly. Dr. Young does not. It is his opinion that no model produces a projection that is precisely accurate but the essence of his criticism is that "we don't know how wrong the models are." Tr. 1159. Models are "incapable of quantifying the uncertainty or how right or wrong that they might be." Id. With regard to the modeling used in Taylor's Borrow Area Impact Analysis, Dr. Young summed up: [W]hen we do this model run, especially with a model that isn't calibrated or verified, we get an answer . . . it's not precisely the right answer, but . . . nobody knows how wrong the answer is. I don't know it, Mr. Trudnak doesn't know and Mr. Clark doesn't know. And that's why being prudent is important and why relying on the monitoring data is critical because the monitoring data is real data. Tr. 1160. In contrast to Dr. Young, Dr. Dally, consistent with his faith in models appropriate for the investigation and conducted properly, took another tack in attacking the modeling used by Taylor Engineering. He criticized Taylor Engineering's failure to use a more comprehensive wave transformation model: the Boussinesq Model. Dr. Dally opined that the Boussinesq Model was superior to STWAVE principally because it takes diffraction into account. But Petitioners did not produce any off-shore Borrow Area Impacts Analyses which used the Boussinesq Model, and Mr. Trudnak testified that he was unaware of any.30/ Taylor Engineering used STWAVE and not Boussinesq as the model for the Borrow Area Impact Analysis because the Boussinesq Model is typically used where diffraction plays the dominant role, that is, within areas like inlets or ports which have structures that will cause wave perturbation. The open coast is not such an area, making the STWAVE Model, if not more appropriate than the Boussinesq Model, certainly an acceptable model under the Project's circumstances. When asked about the Bousinessq modeling's application in the context of his testimony that he could not say what would be the impacts of the dredging of the OK-A Borrow Area, their extent or whether they would be adverse, Dr. Dally testified that based on his experience (rather than actual testing or modeling the impacts of OK-A as done by Taylor), he was "almost certain," tr. 691, that Bousinessq modeling would show impacts to the beach adjacent to the Surf Dweller and El Matador Properties that could be a "type of accretion . . . [that is] momentary . . . due to the propagation of these features as they go up and down the beach." Id. This statement is consistent with Mr. Clark's opinion that if the Project's borrow area were within 1000 feet of shore, the impact of dredging OK-A to the Sherry and Donovan Properties would be beneficial. When asked if the beaches would develop scalloping (sand erosion in some areas and accretion in others), Dr. Dally said, "Right. This [wave transformation process caused by an excavated OK-A borrow area] makes a scalloping." Tr. 692. Perhaps the dredging of Borrow Area OK-A would aggravate scalloping along the shores of Okaloosa County but they would not create scalloping of an "un-scalloped" coastal system. Scalloping features in the Okaloosa Island portion of Santa Rosa Island existed at the time of final hearing. In short, Dr. Dally roundly criticized Taylor Engineering's STWAVE modeling. As to the impacts he was sure would occur, he was unable to state whether they would be adverse, beneficial or both. Most importantly to the weight to be assigned his testimony, he was unable to testify as to how significant the impacts would be; one cannot determine from his testimony whether the impacts will be entirely de minimus, see rule 62B-41.002(19)(c) or whether some could be significant, see rule 62B-41.002(19)(a). Dr. Dally's testimony with regard to the creation by the Project of scalloping did not indicate the significance of that scalloping to the coastal system of Okaloosa County, a system whose ocean bottom, beaches and shores already contain scalloped features. Suppositive impacts that would be caused by the Project to the beaches of Okaloosa County were not the only attack by Petitioners. They also challenged the impact analysis on the basis of the opinion that adverse impacts had been caused to beaches by another beach restoration project and its borrow area not far away: the Walton Project. The Walton Project and Its Borrow Area Completed in the late spring of 2007, the Walton Project placed sand dredged from the Walton Borrow Area on approximately 7 miles of beach in eastern Okaloosa County (East Destin) and western Walton County. Just as in the case of the Western Destin Project, Taylor Engineering performed a borrow site impact analysis for the borrow site used in the Walton Project. Location and Comparison to the OK-A Borrow Area The northwest corner of the Walton Borrow Area is roughly 2.75 miles from the northernmost point of the western boundary of the OK-A Borrow Site. See Ex. P-13. The area between the easternmost point of the OK-A Borrow site and the westernmost point of the Walton Borrow Area, therefore, is roughly half that distance or 1.375 miles. The northwest corner of the Walton Borrow Area is approximately 0.8 miles offshore; its easternmost point is roughly one-half mile off-shore. Comparison of the Walton Borrow Area and OK-A shows that OK-A is larger and will have more sand removed. It is also wider, shallow when measured from the Gulf floor, and in deeper water than the Walton Borrow Area. Nonetheless, Petitioners characterize the two borrow sites as similar,31/ mainly because with less than 1.5 miles separating them, they are relatively close to each other. Despite proximity, there are significant differences, however, between the two. A wider, less deeply dredged borrow area would have less impacts than one deeper and narrower. OK- A's location in deeper water makes it less likely to affect waves and current than the Walton Borrow Area. The footprints of the borrow areas are dissimilar. The Walton Borrow Area has an irregular shape. OK-A is in the shape of a rectangle with a uniform dredging depth although "the depth of sand that is dredged will taper off . . . further offshore . . .[s]o that the seaward most edge does not have significant thickness of sand. The maximum cut is towards the northern boundary." Tr. 306. In addition to distance from shore, the predominately significant difference between the two is the presence on the Gulf floor in the vicinity of the Walton Borrow Area of an ebb shoal: a large deposit of sediment. The ebb shoal exists because of interaction between East Pass and the waves, tides and currents of the Gulf. The Walton Borrow Area is "close to the East Pass ebb shoal . . . and it included the outer flanks of the ebb shoal." Tr. 155. It makes the littoral zone for the Walton Project more active than the littoral zone near which OK-A is located. Located a significant distance to the west of the East Pass ebb shoal, OK-A would not interact with its littoral zone in the way the Walton Borrow Area interacts with its littoral zone. Walton Borrow Area Impact Analysis and Monitoring Taylor Engineering's borrow area impact analysis for the Walton Borrow Area was similar to the impact analysis for OK-A in that both consisted of "wave models and hydrodynamic models." Tr. 156. The Walton impact analysis showed "one potential impact area about 2,000 feet long [on the beach] just west of East Pass," id., an impact area also described as extending from approximately 3,000 to 5,000 feet west of the westernmost jetty at East Pass. It anticipated that impact would be caused by wave action due to the perturbation resulting from the presence of the dredged Walton Borrow Area. The potential impact was projected by the analysis to be a reduction in the sediment supply to the beaches west of East Pass by 11,000 cubic yards per year. Because of that reduction, DEP included a mitigation condition in the Walton Project permit: placement of 55,000 cubic yards on the impacted beach. As a condition of the Walton Project, Taylor Engineering conducted monitoring of the impacts to the beach from the project in general and in particular from the Walton Borrow Area. At the time of hearing, reports for 2007, 2008, and 2009 had been completed and the engineering firm was working on the 2010 report. Mr. Trudnak described the results from the monitoring through 2008 at hearing. From the period of pre-construction in 2006 through immediate post-construction, the monitoring revealed "a huge volume of erosion." Tr. 159. Subsequent analysis from 2007 to 2008 revealed "a huge amount of accretion that actually exceeded the amount of erosion from the previous year." Id. The volumes of erosion and accretion "seemed abnormal." Id. The bottom line, however, of the two years of data is that the early erosion was more than countered by the accretion that occurred into 2008. After describing the impacts in the first two years of monitoring, Mr. Trudnak stressed the importance of what was revealed by additional monitoring. "[M]ore important is the long term trend . . . ." Id. From 2006 through 2009, the monitoring area "as a whole, actually accreted, it gained sand." Tr. 160. Determining the impacts to the beach caused by the Walton Project is complicated because of impacts caused by behavior of the beach at the time of construction and earlier. Consistent with the Department's "critically eroded" designations, data from March of 1996 (not long after Hurricane Opal), data from June, 2004 (before Hurricane Ivan) and 2006 pre- construction data showed the shoreline adjacent to the Walton Project Area to have been receding landward at a rapid rate. This "background" erosion is due mainly to the effects of tropical storms. In the wake of the dredging of the Walton Borrow Area it was difficult for Taylor Engineering to determine what impacts were caused by "background" erosion due to tropical storms and what impacts were caused by the dredging of the Walton Borrow Area. In contrast, it is not difficult to determine from monitoring data in the three years after construction of the Walton Project, however, that the beach west of the borrow area has accreted and that this appears to be the long-term trend. Tr. 159. Contrary to conclusions Petitioners would have drawn from the evidence presented by their experts, the more comprehensive data indicates that the Walton Project (including its borrow area) is having a beneficial impact on the beaches to the west of the project and its borrow area. Dr. Young opined on behalf of Petitioners that the problem with the OK-A Borrow Area Impact Analysis is that it is based on modeling which is far inferior to "real world" data. His opinion that actual data is superior to data generated by modeling, no doubt, is sound. The only "real world" data that will prove any impacts for sure, whether adverse or beneficial, from a dredged OK-A, however, is after-the-fact monitoring data. Such data is usually obtained annually after the construction of a project or after major storm events. It consists of obtaining near-shore and offshore monitoring profiles and involves determining shoreline changes and volumetric beach changes.32/ In the absence of data from monitoring impacts of a dredged OK-A, Dr. Young opined that the data derived from monitoring the Walton Borrow Area which showed erosion early after completion of the Project is superior to the modeling data reviewed by Taylor Engineering in predicting impacts to Santa Rosa Island beaches. There are two problems, however, with Dr. Young's conclusion. First, beach impacts after the dredging of the Walton Borrow Area do not necessarily support similar impacts from a dredged OK-A because the two borrow areas are materially different. Second, the trend revealed by the more comprehensive data gathered in the wake of the dredging of the Walton Borrow Area is that the beach is receiving impacts which are beneficial. Reasonable persons might differ as to the outcome of reasonable assurances with regard to impacts based on the testimony of Mr. Trudnak and Drs. Dally and Young. The balance, however, swings clearly in favor of the applicant in consideration of the testimony of Ralph Clark. Mr. Clark and The Department's Review of Western Destin Project Borrow Site Impacts Ralph Clark is a Registered Professional Engineer in Florida. The recent recipient of the Stan Tate Award from the Florida Shore and Beach Preservation Association, a lifetime achievement award for work over the years in beach preservation, at the time of hearing, Mr. Clark had worked for 37 years for the State of Florida as a coastal engineer. During his long career, Mr. Clark has worked on the State's two separate regulatory programs in the arena of beach management: a "Wet Beach Program, which is working below Mean High Water and includes projects such as beach restoration" tr. 485, and "the more dry beach program which involves construction seaward of Coastal Construction Control Lines and activities landward of Mean High Water . . . ." Id. He has been involved with the Department's Beach Management Program, a grants program for cost-sharing with local governments to develop a long-term comprehensive management plan for the state to solve critical impact problems around Florida which may include erosion. He has conducted or prepared the Critically Eroded Beaches Report every year "going back to the late 1980's" id., and he has "conducted Beach Erosion Studies and Storm Damage Impact Investigations around the State for the past four decades." Tr. 486. Among his specific duties is the review of "scopes of work and project feasibility studies that are provided . . . by the [Department's] Beach Management Section." Id. In this capacity, Mr. Clark conducted the Department's engineering review of the Western Destin permit application and additional information related to the Project. After review, Mr. Clark reached the conclusion that the "Project is a well designed Beach Restoration Project that's critically needed . . . to restore the beaches of Western Destin to provide needed storm protection, recreational benefits and wildlife habitat." Tr. 488. With regard to his overall conclusion as to the Project's physical impacts, Mr. Clark testified: Id. In my opinion, the placement of 831,000 cubic yards of beach compatible sand fill along Western Destin will provide a positive, beneficial impact to the beach and dune system of Western Destin. The excavation of that material from the proposed borrow area [OK-A], along with the excavation of material for four other fill projects proposed for Santa Rosa Island, three of which have been approved, is not expected to have any adverse impact to the beaches of Santa Rosa Island. Mr. Clark's opinions that the Project would be beneficial to the beach and dune system and that the excavation of OK-A is not expected to have adverse impacts have a solid base. His opinions are founded on extensive experience with beach restoration projects over 37 years; extensive experience with coastal processes, coastal morphology, and coastal hydrodynamics; review of the application and supporting information; experience with the Project area and vicinity; extensive experience with coastal storm impacts and beach erosion; and review of roughly three dozen technical documents. Mr. Clark has reviewed 136 beach restoration projects. Of these, 111 were in Florida, six in other states and Puerto Rico, and 19 in countries on every continent in the world other than Asia. But coastal engineering experience in Asia is not missing from Mr. Clark's resume. He has conducted beach erosion control projects and coastal and shore protection projects (as distinguished from beach restoration projects) in that continent as well. Among the "countless number" tr. 490, of such projects he has reviewed are ones in the Netherlands, Denmark, Italy, Turkey, Egypt, China, and the Bahamas." Id. The reason his experience extended beyond the State of Florida to nations all over the world is because "the Florida Beach Preservation Program is internationally recognized." Id. The State has received many requests for technical assistance from various world governments. Mr. Clark has also in his time away from his employment with the state served as a consultant to the governments of Mexico, the Cayman Islands, and the Island Nation of St. Bartholomew and the French West Indies. Mr. Clark has investigated the impacts of 83 tropical storms in the Gulf of Mexico. Most investigations have been in Florida but some have been in other Gulf states and along the coast of the country of Mexico. During some of those investigations and while acting as a coastal engineer for the state, Mr. Clark visited the vicinity of Santa Rosa Island 176 times, excluding academic field trips. In his capacity as a state coastal engineer, Mr. Clark provided the Department with detailed damage assessments for each of the eight tropical storms noted in the Consolidated NOI for the Western Destin Project Over his 37 years, Mr. Clark served on numerous task forces, committees and technical advisory groups relating to erosion control and beach management efforts by states along the Gulf and Mexico. Mr. Clark's early reports were used in the development of the state's Strategic Beach Management Plan and he prepared the first "Critically Eroded Beaches in Florida document" tr. 494, now electronically available to the public on the Department's website. The report prepared by Mr. Clark which led to the designation of the Western Destin Project beach as critically eroded showed that the areas from R-17 to roughly R-20.3 and R- 23.2 to R-25.5 revealed erosion through deflation of the beach profile and recession of the shoreline to such an extent that upland development and infrastructure would be threatened. The report is based on evaluation and projection of the impact of a 25-year storm event. The same report did not conclude that a 25-year storm event would provide the same level of threat to the area between R-20.3 and R-23.2 (the shoreline along the MACLA Intervenors' Property and the Oceania Gap) although that stretch of the beach is "potentially threatened by a 50 to a 100-year storm event." Tr. 499. The "R-20.3 to R-23.2" segment was included in the critically eroded designation for design and integrity of the Project and continuity of management of the coastal system. The designation of the Project area as critically eroded was made in 2006 and was updated by the Department at the request of the County in 2008. The 2008 update indicated no need to change the designation. Although not as threatened as the rest of the shoreline in the Project, the shoreline along the Middle Segment, (including the MACLA Intervernors' Property and the Oceania Gap) is erosional. Data obtained as late as October 19, 2009, indicate that there had been more erosion since a Mean High Water Survey located the MHWL in 2008. The data does not show volumetric change, only that "there is a continued trend of erosion" of the shoreline in the Oceania Gap. Tr. 506. With the Oceania Gap eliminated from the Project, elimination of the rest of the property in the Project's Middle Segment (between R-20.3 and R-23.2) would make the remainder of the Project unstable. It would "isolate a 2,000-foot segment between R-23.2 and R-25.5 [the Eastern Segment] . . . and a 2,000-foot fill segment is not long enough to be a stable fill segment." Tr. 507. Although the elimination of all of the Middle Segment would not hurt "the very far west end" of the Project "very much," tr. 508, the elimination of the entire Middle Segment from the Project would also make the very east end of the Western Segment "relatively unstable." Tr. 508. The Middle Segment, therefore, while not critically eroded, would benefit from beach restoration. Restoration will provide protection from the erosion it is experiencing and from 50-year and 100-year storm events should they occur during the life of the restoration. Restoration will include dune work that will provide protection from storm surge and dissipate the wave energy seaward of any structures in the Middle Segment. Recent storm events have been 50-year and 100-year events. In the area of the Project, "Hurricane Opal was comparable to a 100-year storm event." Tr. 509. In Pensacola Beach, Ivan was a 200-year event. In the Destin area, Ivan "probably dropped to just below a 100-year storm event in terms of its magnitude. Hurricane Dennis was probably comparable to a 50-year storm event." Id. The best defense against 25-year, 50-year, and 100- year storm events is beach restoration. The OK-A Borrow Area is an offshore borrow area. Mr. Clark gave a few examples of other borrow areas that are offshore borrow areas and that are as large as OK-A. These were borrow areas used in the restoration of beaches in Panama City, Delray Beach, Canaveral Shoals, and Anna Maria Island. In addition to Taylor's Borrow Area Impact Analysis Report, Mr. Clark based his opinion on review of monitoring data for the many restoration projects with which he has been involved. Mr. Clark has reviewed borrow area impacts on beach restoration projects that have had adverse impacts. But these projects, typically, were "in inlet ebb tidal deltas of tidal inlets." Tr. 518. Located about three miles east of the ebb shoal of East Pass, OK-A is not an inlet-related borrow area. Of the 111 beach restoration projects that Mr. Clark reviewed, there was one that had an off-shore borrow area that adversely impacted the adjacent beach: the Anna Maria Island Project. The Anna Maria Island Borrow Area was located "roughly 1,000 feet off the [adjacent] beach . . . ." Tr. 519. In comparison, OK-A "is four to five times further offshore than the Anna Maria Island borrow area." Tr. 520. If instead of OK-A, the Project were to use a borrow area as close to the shore as the Anna Maria Island Borrow Area, its impacts to the shoreline would be both adverse and beneficial. The impact to adjacent beach would be erosion, but to the beach to the west of the borrow area the impact would be accretion. Mr. Clark's opinion of no impacts to the beach from dredging OK-A would be entirely different if OK-A had been located in the near-shore zone where "it's a whole different ball game." Tr. 532. The location of OK-A, between 4,000 and 5,000 feet offshore is in a zone that is "no problem," that is, it is not in the near-shore and far enough off shore that it will not cause impacts, adverse or beneficial, to the beaches and shores of Okaloosa County. For all his experience and coastal engineering prowess, Mr. Clark is not an expert in modeling. He relies on others within the Department to evaluate the sufficiency of a model or its methodologies. Mr. Clark did not ask anyone in the Department to evaluate the models used by Taylor Engineering. Dr. Young disagreed with the opinions of Mr. Trudnak and Mr. Clark that there would be no adverse impacts to the beach. He was sure that the dredging of OK-A would cause an adverse impact that would be either erosion or a decrease in the accretion that occurred in recent years along the beaches of Okaloosa Island. Dr. Young also cast doubt on Mr. Clark's experience as support for the opinion that dredging of OK-A would cause no adverse impacts. "Nobody believes there's ever been an adverse impact from a borrow area . . . ." Tr. 1206. Dr. Young used the "real world" experience with the Walton Borrow Area to back up that doubt. "[T]he problem is that we're not doing a good job of monitoring this project [the Walton Project] and the problem is convenient interpretation of the monitoring results." Id. Dr. Young's doubt about the value of Mr. Clark's experience was tempered by the reality of beach restoration in contrast to other types of projects whose failure was sudden, dramatic and easily discernible. Dr. Young: [W]hen a bridge collapses, civil engineers converge on that failed project and they learn more from that failure than they could ever learn from a bridge that lasted 30 years. And . . . one of the problems with coastal project design is that never happens. We never have a beach nourishment project that disappears in six months or a borrow area that causes erosion and coastal engineers converge from around the country and say, wow, here's a project that went wrong. And I think that is one of the hurdles that we need to cross in order to do a better job of project design. * * * We have no clear definition of what a failed project is. So, that way you can never have one that fails. And to me, a failed project is one that does not meet the promises made in the design of that project. And a failed project is also one where there are impacts that occur as a result of the project that are not adequately mitigated or anticipated. Tr. 1150-1. When asked the question of whether there is a definition of a failed beach restoration project in the literature or that is generally accepted by the coastal engineering community, see tr. 1152, Dr. Young testified, "I have not seen one." Tr. 1152. He added, " I would assume they might offer a similar definition [to mine], if the project doesn't work the way we said it would, then we would consider that a failure. But there is certainly not large scale discussion of projects that did not perform as designed." Tr. 1152-3. Dr. Young, like Dr. Dally, did not perform any analysis to quantify any degree of erosion or decreased accretion. Nor has he ever performed modeling to analyze borrow area impacts in keeping with his view of the inutility of modeling for accurate prediction of beach impacts. Variance The "Variance" referenced in the Consolidated NOI concerns two related variances: one from rule 62- 4.242(2)(a)2.b., and the other from rule 62-4.244(5)(c). The northern boundary of the proposed borrow area is within Outstanding Florida Waters ("OFW"). That location led the County to seek a variance from the limitation in rule 62- 4.242(2)(a)2.b. that turbidity can exceed background conditions in OFW during permitted construction activity for no more than 30 days. Section (2) of rule 62-4.242 sets "standards applying to Outstanding Florida Waters." Subsection (a)2.b of section (2) of the rule reads as follows: (a) no Department permit . . . shall be issued for any proposed activity . . . within an [OFW] or which degrades an [OFW], unless the applicant affirmatively demonstrates that: * * * 2. The proposed activity . . . is clearly in the public interest, and . . . * * * b. the existing ambient water quality within [the OFW] will not be lowered as a result of the proposed activity . . . , except on a temporary basis during construction for a period not to exceed thirty days . . . . The County also sought a variance from rule 62- 4.244(5)(c) which governs mixing zones in surface waters and reads: In no case shall the boundary of a dredge and fill mixing zone be more than . . . 150 meters in radius in . . . bodies of water [other than flowing streams], where these distances are measured from the cutterhead, return flow, discharge or other points of generation of turbidity or other pollutants. Section 120.54(2) authorizes an agency to grant a variance as follows: Variances . . . shall be granted when the person subject to the rule demonstrates that the purpose of the underlying statute will be or has been achieved by other means by the person and when application of a rule would create a substantial hardship or violate principles of fairness. Nephelometric turbidity units ("NTUs") in OFWs cannot exceed zero at the edge of the 150 meter radius referenced in rule 62-4.244(5)(c). To keep NTUs at zero outside the 150 meter radius, the County "would have had to almost continually be shutting down . . . .[its hopper] dredge," tr. 415, because the turbidity plume created by the hopper dredge's activity would have regularly extended beyond the 150 meter radius. Use of a different type of dredge (such as a cutterhead) would not alleviate the need for the variances for the construction of the Project. A cutterhead dredge is substantially more expensive with regard to both mobilization costs and actual dredging: $15-$20 per cubic yard versus $8 per cubic yard for a hopper dredge. Cutterhead dredges, moreover, do not operate in waves as effectively as hopper dredges. In rough water, "a cutterhead would see much more down time and conditions [could cause] a cutterhead . . . to stop dredging and go into safe harbor into East Pass." Tr. 173. The variance from rule 62-4.244(5)(c), therefore, was needed because the standard size mixing zone would have created a substantial hardship for the County. In addition to outlining the substantial hardship, the County provided two additional bases in its application to justify the variances: (a) no resources in the area, such as hard bottom or sea-grass beds, would be affected by a turbidity plume and an expanded mixing zone; and (b) citation to the Pensacola Naval Air Station ("NAS") project claimed to be similar in that it involved OFW and had received a variance. Upon receipt of the application for the variances, the Department requested additional information to establish whether OK-A, in fact, would be within OFW and more analysis of the comparability with the Pensacola NAS project. The Department's engineering section determined that the comparability of the Pensacola NAS project was not adequately demonstrated because of a lack of detail about the hydrodynamics and mixing zone sizes of the two sites. Nonetheless, the staff responsible for making the final decision on the variances (and ultimately the Department) determined the County's information justifying the variances to be sufficient. In granting the variances, the Department did not rely on the County's comparison of the Project to the Pensacola NAS project. As explained by Dr. Edwards at hearing, "[H]aving the data . . . from an actual project to back up and . . . calibrate a mixing zone is an added bonus, but we just didn't have it in this particular case." Tr. 420. The Department based its decision, in part, however, on background knowledge from permitting of borrow areas and beach projects "all over the Panhandle," tr. 421, and the data gathered from them including "data from side scan sonar from seismic information all along this area." Id. Included in this background is knowledge of a similar mixing zone of 1,500 meters established for one of the Eglin AFB beach restoration projects which excavated OK-A with a hopper dredge and in which the 1500- meter mixing zone was determined to be appropriate. Independent of the information provided by the County, the decision, therefore, was founded on the Department's own knowledge that no resources would be impacted by an expanded mixing zone and that there was a comparable project in the area (not the Pensacola NAS project) that had been allowed a 1500- meter mixing zone. In applying the standard from section 120.54(2) related to the underlying intent of the rules at issue and the statutes, the Department determined that "[t]he Project in the OFW was clearly in the public interests, according to [section] 373.414 and the minimum Water Quality Standards, even within the mixing zone[,] would still be met." Tr. 421-2. There were at least two other mitigating factors that the Department entertained as support for its decision. First, because of the difficulty in controlling turbidity in open waters in the Gulf, the 1,500-meter mixing zone established by the Consolidated NOI actually "is on the small side," tr. 422, of a mixing zone for the dredging of a borrow area to serve a beach restoration project. Second, 29 NTUs is the maximum turbidity allowed in waters that are not OFW. An extended mixing zone to allow the County to exceed 29 NTUs outside OFW was not granted as part of the variances under the Consolidated NOI. Petitioners presented no evidence to rebut the testimony elicited by the Department and the County that the purpose of the statute underlying the rules from which the variances are sought will be met by other means and that the application of the rules will create a substantial hardship. Changed Site Conditions 267. Rule 62B-49.005(16) provides: If site conditions change during the processing of an application to such an extent that the data already provided can no longer be used to determine consistency as provided in this chapter, then the application shall be denied unless the applicant agrees to waive the 9-day time requirements of Chapter 120.60, Florida Statutes, and provides the additional information required to reanalyze the application. After the filing of the County's application, malfunction of British Petroleum's Deepwater Horizon offshore oil rig in the Gulf of Mexico led to the Oil Spill, a discharge of a massive amount of oil and natural gas into the Gulf of Mexico. No evidence was presented that showed the Oil Spill had caused impacts to the OK-A Borrow Area. The permit was revised, nonetheless, to add language in the wake of the Oil Spill that requires the County to visually inspect the borrow area prior to construction activity and to analyze sand samples from the borrow area. The County, therefore, plans to send a diver to collect samples to be analyzed for contamination. See tr. 175. Western Destin Erosion Control Line The requirement for an Erosion Control Line is in section 161.161: Once a project is determined to be undertaken, a survey of all or part of the shoreline within the jurisdiction of the local government in which the beach is located shall be conducted in order to . . . locate an erosion control line. * * * In lieu of conducting a survey, the board of trustees may accept and approve a survey as initiated, conducted, and submitted by the appropriate local government if said survey is made in conformity with the appropriate principles set forth in ss. 161.141-161.211. § 161.161(3), Fla. Stat. The Draft JCP as originally issued did not require the establishment of an ECL. It required the establishment of a Pre- project Mean High Water Line instead. The Second Revised Draft JCP dispensed with the requirement of a Pre-project MHWL. It requires that an ECL be established for all properties within the 1.7 miles stretch of beach in the Project area subject to beach restoration.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Environmental Protection enter a final order issuing the Joint Coastal Permit, Variance, and Sovereign Submerged Lands Authorization as revised during the course of these proceedings. DONE AND ENTERED this 29th day of June, 2011, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 2011.
The Issue At issue in this proceeding is what costs, if any, are recoverable by petitioner as a consequence of its successful prosecution of an appeal from the agency's final order heretofore rendered in the above-styled matter.
Findings Of Fact Background On January 14, 1988, respondent, Key Biscayne Limited partnership, formerly known as Biscayne Beach Hotel Association, Ltd. (the "Hotel") , filed an application with Respondent, Department of Natural Resources (DNR), for a coastal construction control line (CCCL) permit authorizing it to conduct construction activities seaward of the Dade County CCCL on Key Biscayne, Florida. As proposed, the Hotel, which currently owns the Sonesta Beach Hotel on Key Biscayne, sought authorization to construct a nine-story 124-unit habitable addition and a one-story non habitable addition, with understructure parking, to its existing facility. Incident to such construction, the Hotel also sought authorization to construct a deck and jacuzz-type hot tub south of the addition, and authorization to excavate approximately 1,400 cubic yards of fill for the pile foundation and caps, and to deposit such fill seaward of the CCCL. Excavation for the foundation would extend a maximum of 177 feet seaward of the CCCL and placement of the excavated material would extend a maximum of 300 feet seaward of the CCCL. On August 11, 1988, DNR issued a notice of intent to approve the Hotel's application and to is sue a CCCL permit subject to the following special conditions: The issuance of the permit placard shall be withheld pending staff receipt and approval of: Two sets of specifications and final certified construction plans accurately dimensioned with elevation referenced to NGVD. Details of the foundation of the 9-story and single- story addition, pile/pile cap/column connections, column/floor slab and roof slab connections, cantilevered balconies, garage floor slab, breakaway walls, storm drainage and domestic waste disposal, and fences shall be included in the plans. Two sets of certified dimensioned site plans showing the location of the control line, existing sea grape trees, the placement of excavated material seaward of the control line, and species of salt-resistant vegetation. The site plans shall be subject to review and acceptance by the Bureau staff. Evidence that written notice has been recorded in the deed covenants and restrictions for the subject property that: The construction of any future rigid coastal protection structures on the property shall be prohibited. The deed covenants and restrictions shall be recorded in the public records of Dade County. Such deed covenants and restrictions shall be enforceable and shall not be altered unless approved by the Department of Natural Resources. The use of gravel or other similar materials or structures with the potential for becoming aerodynamically propelled missiles shall not be included in the construction of the roof. Salt-resistant vegetation such as sea oats, sea grape, panic grass, salt jointgrass, and/or other approved salt- resistant species shall be planted on the fill area. In addition, the permittee shall irrigate and apply fertilizer as appropriate for the particular species planted until the vegetation is established. A 75 percent survival rate of the vegetations shall be ensured and replanting shall be conducted until a 75 percent overall survival rate is attained and until any sizeable barren portions of the area are covered. The excavated fill material to be placed on the beach shall consist of material compatible in grain size and coloration as the native beach sand and shall come from a source located landward of the coastal construction control line. The main structure of the addition shall not extend further seaward than the projected line of the existing retaining wall located seaward of the existing swimming pool. Petitioner, Key Biscayne Council (the "Council"), filed a timely protest of DNR's action. Essentially, the Council contended that the location of the proposed construction would be seaward of the 30-year seasonal high-water line and, therefore, prohibited by Section 161.053(6)(b), Florida Statues; that the proposed construction would adversely impact the beach-dune system and adjacent properties; that construction of similar projects along the coast would have a significant cumulative impact resulting in the general degradation of the beach or dune system along that segment of shoreline; and that the proposed construction failed to comply with the setback requirements or zoning or building codes of Dade County. The Key Biscayne Council In Its petition for formal hearing, the Council alleged that it was a not-for-profit Florida corporation which had, as one of its purposes, the preservation of the environment of Key Biscayne, including its beaches. The proof at hearing failed, however, to demonstrate that the Council enjoyed corporate status but, rather, demonstrated that it was an association formed in November 1987 to give the residents of Key Biscayne a more effective voice on matters of local interest, including the preservation of the environment of Key Biscayne. The Council is governed by nine individuals who are residents of Key Biscayne. These individuals are elected to their positions by the resident members of the association, who are also registered voters in Dade County. 4/ The Council meets at least once each month, and its meetings are open to the public. The agenda for each meeting is published in the local Key Biscayne newspaper, The Islander, the week before each meeting. Of particular interest to the Council is the preservation and protection of the beaches of Key Biscayne which form an important part of that community's and the Council members' lifestyle. To date, the Council has been a motivating force behind the enactment of Dade County Ordinance No. 89-23 discussed infra, which established the CCCL as the mandatory setback line for new construction on Key Biscayne, as well as efforts to fund a cleanup of the beaches, to establish a vegetation dune system, and to protect the sea turtle population. Here, by unanimous vote of the Council, it elected to contest the propriety of DNR's proposal to approve the Hotel's application to construct the proposed additions seaward of the CCCL. Key Biscayne and the surrounding topography Key Biscayne is the southernmost barrier island in what is now a chain of barrier islands extending southward from Miami Beach. Historically, Miami Beach was connected to some extent with Virginia Key, which lies to the north across Bear's Cut from Key Biscayne. In 1835, however, a hurricane struck the area, breached whatever connection existed between Miami Beach and Virginia Key, and formed what is now known as Norris Cut. The topography of the area was further altered in 1905 when construction of Government Cut, the navigational channel for the Port of Miami, was begun. Construction of that cut severed the southern tip from Miami Beach, and formed what is now known as Fisher Island. By 1927, a jetty had been constructed on the north side of Government Cut that created an effective barrier to any along shore sediment transport to the south. Over time the channel in Government Cut was deepened and jetties on its north and south sides extended. Today, the channel is 42 feet deep and extends two miles into the ocean. The north jetty extends 3,000 feet into the ocean, and the south jetty extends 2,750 feet into the ocean. Key Biscayne, which lies to the south of Government Cut and the other islands, is a sand island, roughly "drum-stick" in shape, formed on a limestone base, with elevations ranging from 5 1/2 to 6 1/2 feet. The northern and southern portions of its eastern shore are dominated by Crandon Park and Cape Florida State park, respectively, with development concentrated in the central portion of the island. It is along this central part of the island that the Sonesta Beach Hotel exists, and where the proposed construction is to occur. Immediately north of the existing hotel lies the Silver Sands Hotel and Sand Dollar Restaurant. To the south of the hotel lies the Sheraton Beach Hotel and Beach Club and, further south, the Key Biscayne Hotel and Villas. 5/ Although Key Biscayne is generally subject to mild weather conditions and a low energy environment, it has been subjected to erosion along its eastern shore, with the more severe erosion occurring along the central portion of its shoreline. Seaward of the northern and southern portions of its eastern shore, sand shoals exist which tend to dampen the force of wave energy that would otherwise be exerted against that stretch of coast line. The center of the island is not, however, accorded similar protection and the consequent concentration of wave energy causes sand to be transported from the center of the island to its outer ends. As a result, the central portion of the island, where the subject development is proposed, has historically eroded at a faster rate than the north or south ends of the island. In September 1984, as a consequence of the severe erosion suffered to the eastern shore of Key Biscayne, Dade County was authorized to place over 411,000 cubic yards of sand along approximately 10,000 feet of shoreline on Key Biscayne, and to construct a terminal structure at the south end of the island. The beach was restored by hydraulically pumping sand onto the beach from an offshore dredge and then redistributing the sand with a bulldozer. The resulting beach is characterized as "plan form," and is expected to assume a natural profile over time by responding to the natural forces of wind and waves. The fill pipes which were used to pump sand onto the beach were removed from the area of the Sonesta Beach Hotel on July 3, 1987, and the reprofiling or redistribution of sand in that area was completed around July 20, 1987. On September 26, 1987, the renourishment project was certified complete. The 30-year erosion projection Section 161.053(6)(b) Florida Statutes, provides that DNR may not issue a permit for construction seaward of the CCCL, except for certain specific structures not pertinent to this case, if the structure is "proposed for a location which, based on the department's projections of erosion in the area, will be seaward of the seasonal high-water line within 30 years after the date of application for such permit." The "seasonal high-water line" is a creature of statute, and is defined by Section 161.053(6)(a), Florida Statues, as "the line formed by the intersection of the rising shore and the elevation of 150 percent of the local mean tidal range above local mean high-water." Here, the seasonal high-water line, which is established as an elevation, calculates to approximately 5.4 feet NGVD, and according to the survey dated August 1, 1987, which was submitted with the Hotel's application, currently derives a line that is approximately 375 feet seaward of the proposed construction. To establish the 30-year erosion projection, DNR proposes to horizontally shift the profile which was depicted on such survey in a landward direction a distance equal to the expected erosion rate over a 30-year period. Ordinarily, DNR would calculate a 30-year erosion projection based on historic erosion rates, referred to as "horizontal change rates" in Rule 16B- 33.024, Florida Administrative Code, by reviewing two or more historical surveys taken over a period of time, and measuring the amount of shoreline recession that had occurred during that period. From that figure, an erosion rate would be derived by dividing the number of years which elapsed over the period of record chosen into the amount of shoreline recession that occurred during that period. The result would be the historic erosion rate which, when multiplied by 30, would establish the location of the 30-year seasonal high-water line. However, where, as here, the beach as been renourished, consideration of the effect and performance of such project must also be considered in making the 30- year erosion projection. Rule 16B-33.024(3)(e), Florida Administrative Code. Accordingly, to determine the expected location of the seasonal high-water line in 30 years in this case, it is necessary to establish a historical shoreline change rate and to evaluate the effect and performance of the beach renourishment project. To establish an appropriate historical erosion rate for the subject site, consideration must be given to both the tidal datum relied upon to obtain the rates, and the time period selected as the period of record for analysis of historic shoreline change rates. With regard to tidal datums, the Department's rule provides that horizontal shoreline change rate values may be obtained from one of several available tidal datums, including mean high-water, mean sea level, and mean low-water. Rule 16B-33.024(3)(a), Florida Administrative Code. However, the preferred and more reliable tidal datum to use in assessing historic erosion rates is the line of mean high-water. The time period used in calculating the historic shoreline change rate is required by DNR's rule to extend from the date of the field work for the applicant's survey, which was submitted as part of the application, to the earliest date for which reliable information is available. Rule 16R- 33.024(3)(b) Florida Administrative Code. The historic shoreline change rate analysis should generally include data from points 3,000 feet on either side of the proposed construction, with the change rate for each point averaged for the time period chosen. Rule 16R-33.024(3)(g), Florida Administrative Code. In the event that coastal or shoreline protection structures exist which have influenced the shoreline data for any of the reference points, such influence must be addressed, and if such influence renders the data unreliable the rate data obtained from that point during the period of influence must be rejected. 6/ Rule 16B-33.024(3)(c), Florida Administrative Code. Historic shoreline change rates for the subject project are properly determined by reference to DNR reference monuments R-101 to R-106, located on Key Biscayne. Monument R-104 is the closest monument to the project site, lying approximately 180 to 200 feet south of the site, with the project lying between monuments R-103 and R-104. To facilitate an accurate determination of historic shoreline change rates, DNR has created the Beaches and Shores Growth Management Data Base (DNR Data Base), which consists of data from primary source maps from various governmental agencies, including the United States Coastal and Geodetic Survey, National Ocean Survey, and United States Geologic Survey. These maps have been digitized relative to the DNR monuments, which are located along- the coast at- approximately 1,000-foot intervals, and the resulting data is used to assess shoreline changes over time. Inherent in these shoreline changes are the effects of natural forces on the shoreline, such as wind, wave height, and temperature. Pertinent to this case, the surveys available in the DNR Data Base prior to 1989 were those of 1851, 1919, 1927, 1935, 1945, and 1962. In or about February 1989, DNR contracted with Florida State University to redigitize maps of Key Biscayne. As a consequence, the accuracy of existing data was enhanced and a new survey, the 1913 United States Coastal and Geodetic Survey Map, was added to the DNR Data Base. The addition of the 1913 survey to the DNR Data Base is significant to this case, since the proof demonstrates that the data derived from the 1919 survey is unreliable and should be disregarded. Accordingly, the surveys that may be reasonably relied on in this case are those of 1851, 1913, 1927, 1935, 1945, and 1962. In selecting the appropriate period to determine the historic change rate in this case, several factors should be considered. First, in 1926 a hurricane, which came very close to Key Biscayne, resulted in severe damage to the beach. This storm was reported as at least a 100-year storm event, and is the major storm of record for the area. The 1926 storm, as a naturally occurring event, should be taken into consideration in arriving at an historic erosion rate, but should not be allowed to bias the data. Accordingly, any survey immediately preceding it should not ordinarily be used as a starting point for determining an historic erosion rate, because it would overestimate the historic change rate. Similarly, the immediate post-storm survey of 1927 should not be used as the starting point for determining the historic change rate, since this data would overestimate the effects of the post-storm rebound (accretion), but ignore the erosion caused by the 1926 storm and artificially lower the erosion rate. Finally, the 1962 survey should be the most recent survey used to establish an historic erosion rate, since it marks the end of the predevelopment phase of the study. In the mid-1960's, shoreline structures (seawalls) were erected along portions of the coast, and a beach renourishment project was carried out at Crandon Park in 1969 resulting in filling at DNR Monument R-101. These events render post 1962 data unreliable in assessing an historic change rate. Here, the proof demonstrates that the appropriate time period for analyzing the historic change rate is 1851 to 1962. Based on an analysis of the historic change data for such period, the appropriate historic erosion rate for the project site is -2.3 feet per year. In reaching the foregoing conclusion, the Council's contention that pre-1919 survey data should be rejected in deriving an historic change rate because the construction of Government Cut had, by 1927, interrupted a littoral supply of sand in the neighborhood of 200,000 to 400,000 cubic yards of sand to the south has not been overlooked. However, the more credible proof demonstrates that the littoral transport of sand along this area of Florida's coast is approximately 10,000 cubic yards per year, and that little of that sand ever reached Key Biscayne. Accordingly, the construction of Government Cut had little, if any, impact on Key Biscayne. Also, notable to this conclusion is the fact that an analysis of the historic change rate from 1913 to 1962 calculates an historic erosion rate of -2.5 feet per year, an insignificant difference from that calculated for the period of 1851 to 1962, and the existence of an erosional trend at the central portion of Key Biscayne prior to the construction of Government Cut. Following the establishment of an historic erosion rate, the next step in assessing the expected location of the seasonal high-water line in 30 years in situations where, as here, the beach has been renourished, is a consideration of the effect and performance of such renourishment project. The importance of this analysis cannot be gainsaid, since a beach nourishment project may behave differently than the natural beach, as the nourishment may erode faster or slower than the natural beach or it may accrete. Factors which may cause a beach nourishment project to behave differently than the natural beach include project design, such as the length and width of the project, the seaward slope of the fill material, and the nature of the fill material; and, natural and manmade factors, such as offshore shoals, jetties, and breakwaters. The length and width of a project is very significant in terms of how long the project will remain in place. A project which is short in length will have a tendency to erode at a faster rate than a long project or the natural beach. This loss, referred to as "end losses" or "spreading-out losses," is not necessarily a loss of material from the system, but rather a redistribution of the sediment to the outer edges of the nourishment project. These spreading-out losses are caused by the project's exposure to waves that occur from offshore. As a nourishment project is exposed to waves, it reacts to the force of those waves by spreading out in an alongshore direction, resulting in a reduction in the overall width of the project. A longer project, such as the nourishment project in the existent case, will erode from the ends more slowly than a small project and, consequently, maintain its width and life for a greater period of time. The seaward slope of the nourished beach will also affect the project's performance. When a nourishment project is constructed, the seaward slope of the beach may initially be steeper than the slope which existed prior to nourishment, and may be irregular in shape compared to the natural shoreline. During the slope adjustment process, gravity and waves act on the shoreline to create a more natural slope and shape. During this process, the upland portion of the beach, as well as any irregularities in the shoreline, will experience shoreline recession, with the material being redistributed along shore and offshore. This adjustment process, and the effects it will have on the project's performance, may extend over several years after nourishment is completed. The grain size of the material used in the nourishment project can also affect the performance of the project. If the sediments used to construct the nourishment project are essentially of the same grain size and quality of the sediments which existed on the natural beach, then the nourished beach can be expected to perform, after initial slope adjustment, in much the same manner as the natural beach.. Natural features or manmade structures which may affect the performance of the nourishment project include the shoreline and offshore characteristics of the area that can increase or slow the rate at which the material may otherwise erode, or a groin or natural feature that would tend to confine the project and prevent or minimize spreading-out losses. Here, the nourishment project is a long project, approximately 10,000 feet in length. This factor will contribute favorably to the project's longevity. The material used in the nourishment project is very similar to that which existed on the natural beach. Therefore, after initial slope adjustment, the nourished beach should perform in a manner similar to the natural beach. Finally, the portion of the beach fronting the hotel is bordered to the north and south by areas which are historically stable or accreting. This factor should stabilize the ends of the project, and reduce the alongshore spread which would otherwise occur. In sum, after the slope and shoreline have adjusted to a natural profile and shape, the nourishment project should perform in a manner very similar to the pre-nourishment beach. While the nourishment project should ultimately perform similar to the pre-nourished beach, little time has elapsed since completion of the project for slope and shoreline adjustment or to demonstrate stabilization. Here, the nourished beach was profiled by man (bulldozers), with the reprofiling in she area of the hotel being completed around July 20, 1987. The Hotel submitted its application for the subject permit on January 14, 1988, together with a survey of the area dated August 1, 1987. Based on this survey, DNR proposes to establish the 30-year seasonal high-water line by horizontally shifting the profile depicted on the survey in a landward direction. To predict the performance of the beach nourishment over time, the Hotel offered the results of an analytical computer model run by Dr. Robert Dean, an expert in coastal and oceanographic engineering and coastal processes. That model predicts spreading-out losses," and considers site specific factors that will affect the nourishment project, including pre-existing shoreline conditions, size and quality of the beach fill, volume, length of the project, conditions at the end of the fill, and the affect of wave forces on the coast. The wave data relied upon by Dr. Dean to drive his model was derived from a wave gauge located just north of Government Cut. The wave characteristics at Key Biscayne are, however, dissimilar to those experienced off Miami Beach due to the wave damping characteristics of the offshore area of Key Biscayne. While dissimilar, Dr. Dean opined that the data from Miami Beach could be reliably used as a conservative estimate of the force of waves at Key Biscayne, and that his model would, thereby, present a worst case scenario or prediction of spreading-out loss of sediment on the nourished beach. Based on such analysis, Dr. Dean predicted that shoreline recession on the nourished beach, attributable to spreading-out losses, would amount to 28 feet over the next 30 years, most of which would occur in the early years of the project. When combined with the historic change rate of -2.3 feet per year for 30 years, Dr. Dean calculates that 97 feet of erosion will occur at the subject site over a 30-year period, and that at the end of that period the proposed addition will be 102 feet landward of the seasonal high-water line. DNR also made an erosion projection to predict the performance of the beach nourishment over time. In its analysis, DNR relied on monitoring data Dade County had gathered regarding the performance of the project. Such data measured, at various monuments, the amount of accretion or erosion that had occurred within the first 6 months of the project, and the amount of accretion or erosion that had occurred over the next 12 months of the project. The data was not, however, complete for all monuments within 3,000 feet of the hotel, and was otherwise unpersuasive for reasons hereinafter discussed. In performing its analysis, DNR chose to focus on one monument, PL-5- DC, which is located 200 feet north of the hotel. The data at that monument showed that within the first six months the mean high-water line (MHWL) had receded 22 feet, and that over the next 12 months it had receded an additional 10 feet. Assuming a constant rate of erosion based on those two time points, DNR concluded that initial slope adjustment or stabilization would occur within four years, and that shoreline recession on the nourished beach over that 4-year period would amount to -41.6 feet. When combined with an historic change rate of -2.3 feet for the next 26 years, DNR's methodology calculates that 101.4 feet of erosion will occur at the subject site over a 30-year period, and that at the end of that period the proposed addition will be 99 feet landward of the seasonal high-water line. 7/ While Dr. Dean's model and DNR's analysis of Dade County data may yield similar results, neither methodology is, under the circumstances of this case, persuasive proof of how the nourishment project will perform or where the 30-year seasonal high-water line will be located. Here, the proof demonstrates that Key Biscayne enjoys a low-energy environment, and that the only force of significance ordinarily exerted along its coast occurs during the winter months when northeasters impact its shoreline. It is this wave energy that would, under normal circumstances, mold or adjust the seaward slope and shoreline of the nourishment project until it reached a more natural slope and shoreline, and after which the rate of erosion would be consistent with the historic change rate. However, since completion of the nourishment project, Key Biscayne has enjoyed unusually mild weather conditions, and the usual winter storms have not occurred. Consequently, the nourishment project has yet to be subjected to the forces of nature which can be reasonably expected to ultimately mold or adjust its seaward slope and shoreline. DNR's conclusion that the nourishment project will reach stability within four years, based on its analysis of the meager data provided by Dade County, is simply unpersuasive. That data, which appears on page 6 of DNR's exhibit 5, showed that at monument PL-5-DC the MHWL had receded 22 feet in the first six months of project existence and 10 feet over the course of the next 12 months. Based solely on these two measurements, DNR calculated a straight line decreasing rate of erosion to conclude that within four years the project would erode at the historic change rate. DNR's methodology and assumption, based on only two points of measure within the first 18 months of project existence, is not credible or persuasive proof of how the nourishment project will perform, and is rendered even less persuasive In view of the mild weather that affected Key Biscayne during such time period. Dr. Dean's opinion, based on his analytical computer model, which assessed shoreline recession on the nourished beach attributable to spreading- out losses, is likewise unpersuasive proof of how the nourishment project will perform. While Dr. Dean considered spreading-out losses and the historic change rate in reaching his conclusion, he failed to address offshore losses of sediment that will occur as the seaward slope of the project adjusts to a more natural profile. Here, the proof demonstrates that the seaward slope was constructed much more steeply than the natural slope, and that in the first 18 months of project existence significant quantities of fill have been lost offshore. At monument PL-5-DC the slope remains steep. Notably, while Dr. Dean calculated a spreading-out loss for the life of the project of 28 feet under what he termed a worse case scenario of wave height, the MHWL at the nourishment project has already receded 32 feet, under mild weather conditions, in the first 18 months of existence. Compared with Dr. Dean's and DNR's conclusions, the Army Corps of Engineers (Corps), which designed the nourishment project, calculated a loss rate of approximately 22,000 cubic yards of fill each year. Should the project perform consistent with the Corps' estimate of project life, it will have receded to the Dade County erosion control line within 10 years, and over the course of the next 20 years to a point such that the proposed addition would lie seaward of the 30-year seasonal high-water line. Under the circumstances of this case, a calculation of the probable location of the 30-year seasonable high-water line, based on the Corps' estimate of the performance of the nourishment project, is more compelling than that of Dr. Dean or DNR. 8/ Impact on the beach and dune system Where, as here, construction is proposed seaward of the CCCL, Section 161.053(5)(a)3, Florida Statutes, requires DNR to consider the potential impacts which the location of the proposed structures or activities may have on the beach-dune system. That system includes the beach, the dunes, and the overwash areas, which are interrelated by the sediment erosion and accretion process. 9/ DNR's analysis of potential impacts to the beach-dune system includes both short-term and long-term impacts of proposed construction. Short-term impacts are those which may arise during construction of a project and are often a concern in sensitive areas, such as those areas characterized by natural dune features and dune-stabilizing vegetation. Long-term impacts of a project may include increased flooding caused by a lowering of dunes and increased erosion caused by a lowering of dunes or by a net loss of sand from the beach-dune system. Impact to the beach-dune system can also be caused by increased pedestrian traffic associated with the construction of a major habitable structure. Pedestrian-caused impacts are, however, a potential concern only in areas where there are dune features and stabilizing vegetation which could be destroyed. In the absence, of these dune features, pedestrian traffic has no significant impact to the beach-dune system. Here, the site of the proposed construction does not have any prominent dune features or stabilizing dune features or stabilizing dune vegetation. In fact, the site is the present location of an asphalt parking lot, which extends 40 feet seaward of the footprint of the proposed construction. Construction of the project will not result in any net excavation of material. Since dunes will not be lowered and there will be no net loss of material, there will be no increased flooding or erosion caused by the project. Under such circumstances, the proof demonstrates that there will be no long-term or short-term impacts to the beach-dune system occasioned by the project. Adverse cumulative impact on the beach-dune system Section 161.053(5)(a)3, Florida Statutes, also requires DNR to assess the potential cumulative impacts to the beach-dune system that may be caused by construction seaward of the CCCL. Here, the proof demonstrates that the proposed project, either singularly or in combination with other existing or similar projects, would not have any adverse impact to the beach-dune system. Impact on adjacent property Construction activities proposed for a location seaward of the CCCL are also analyzed by DNR to assess their impact on adjacent properties. Rule 16B-33.007(2), Florida Administrative Code. Such analysis includes a determination of whether construction activities will be confined on-site; whether a lowering of dunes will occur such that increased flooding on adjacent property could occur; whether elevations on the proposed construction site will be lowered such that flooding of adjacent property could occur; and whether proposed construction, in the event of a major storm event, would potentially increase erosion on adjacent property. Here, the proof demonstrates that construction activities will be confined on site, there will be no lowering of the dunes or elevations, and that there will be no net excavation of materials such that any increased risk of flooding or erosion could occur to either the project site or to adjacent properties. Interference with public beach access One purpose of CCCL permitting is to preserve public beach access. Sections 161.053(1) and (5)(e), Florida Statutes. "Public access" is defined as "the public's right to laterally traverse the sandy beaches of this state where such access exists on or after July 1, 1987." Section 161.021(1), Florida Statutes. The public presently does not have east-west access to the beach at the Sonesta Beach Hotel, and is not entitled to such access by law. The Hotel does not propose to hinder existing north-south (shore parallel/lateral) beach access, and the proposed project would not impede such access until the seasonal high-water line receded to the project. 10/ While the project might limit lateral access at times once the seasonal high-water line recedes, such impact would be de minimis in the instant case since construction of the project would not be seaward of existing structures on the Hotel's property. Compliance with local zoning requirements In order for a permit application to be deemed complete, an applicant must provide DNR with written evidence, provided by the appropriate local governmental-agency having jurisdiction over the activity, that the proposed development does not contravene local setback requirements or zoning or building codes. Rule 16B-33.008(2)(c), Florida Administrative Code. By letter dated February 10, 1988, the Hotel submitted to DNR a letter from Metropolitan Dade County's Department of Building and Zoning which indicated that the site plan for the proposed project was consistent with existent regulations. On April 21, 1988, DNR deemed the Hotel's application complete. While not contesting the consistency of the proposed project with local regulations at the time the Hotel's application was deemed complete, the Council contends that subsequent events have rendered its proposal inconsistent with such regulations. In this regard, the proof demonstrates that the Hotel received site plan approval for the proposed addition from Dade County in November 1988, but that its application for a bull ding permit was denied and returned to the Hotel for further action. To date the Hotel has not sought to further process such application with the County. On April 4, 1989, Dade County enacted Ordinance No. 89-23, effective April 14, 1989, relating to construction seaward of the CCCL on Key Biscayne. Pertinent to this case, the ordinance prohibits the new construction of major habitual structures and severely restricts the construction of nonhabitable structures seaward of the CCCL, absent a variance. At hearing, no proof was offered that any portion of the proposed project would qualify for a variance, or that the nonhabitable portion of the project complied with the requirements of the new ordinance. 11/
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered denying the Hotel's application to construct and excavate seaward of the CCCL. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 5th day of September 1989. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of September, 1989.
Findings Of Fact The site of the revetment that is the subject of this litigation is located near the northerly coast of Pine Island in Charlotte Harbor. The property fronts on Pine Island Sound which is inside the barrier islands westward of Pine Island. Pine Island Sound is as an Outstanding Florida Water and Charlotte Harbor at this location is classified as Class II waters. Petitioner's property abuts the property owned by Meister Development Group. On Petitioner's property is located a two-story residence and two rental units. On Meister's property a four unit residential development has been erected. Sometime around 1970 a vertical seawall was erected to protect both Petitioner's property and Respondent's property. Since that time the beach has accreted to the point that by 1989 the sand beach extended an average of approximately twenty-five feet seaward of the seawall in front of Petitioner's property. However, this seawall ended near the middle of Respondents property and erosion of the beach became serious at the four unit residential development building located thereon in 1984. In 1984 the beach at this location had eroded to the point that the high water mark had passed the northern most portion of the building foundation and was threatening to undermine the structure. At this time this shoreline was devoid of aquatic vegetation. Meister employed an engineering firm to prepare a solution to the erosion problem. That firm concluded a revetment was needed and the application for the dredge and fill permit that is here contested was filed in July 1984. Since the application involved use of land seaward of the mean high water, permission of the Department of Natural Resources (DNR) was required before the application could receive final approval. To obtain the approval of DNR Meister agreed to provide a conservation easement to DNR and a public easement to allow the public access to cross the property seaward of the residential development. Additionally Meister conferred with Outstanding Florida Water Group to obtain their acquiescence to the project and agreed to provide navigational aids to mark the Jug Creek Channel across form the Meister property. Before a dredge and fill permit can be granted involving an Outstanding Florida Water the applicant must show the project to be in the public interest. In consulting with DER the applicant proposed a sloping revetment which is generally considered to better tolerate wave action than does a vertical wall. To enhance the public interest concept the applicant agreed to place toe stones at the foot of the revetment and plant mangroves. The toe stones would serve to hold sand in which the mangroves could grow and serve as a habitat for aquatic organisms. The applicant also agreed to place an artificial reef of rocks on the sand shoal which sits about one half mile north of applicant's and petitioner's property. Although the mangroves planted did not survive due to heavy wave action and the permit did not require survivability of these mangroves, at the hearing Meister agreed to a provision in the permit's next renewal that will include a requirement that a percentage of these mangroves planted in the toe stones survive. Landward of the residential development is a stormwater retention area that serves to keep contaminants out Pine Islands Sound. The erosion of the beach at the Meister property was threatening to extend further inland and allow contaminants to leach from the water retention area into Pine Island Sound and contaminate that body of water. Approval of the project would serve to remove that threat and be in the public interest. Finally consideration was given to the fact that the foundation of the condominium was being threatened which affected the dwelling of the residents. Protecting these residences is also considered to be in the public interest. The project was completed during a two weeks period in August 1986. The revetment generally takes off in the same line as the Vertical seawall on petitioner's property and is basically convex to fit the existing building and meet the zoning setback requirement of twenty-five feet from the building. To construct the revetment the existing vertical seawall on Meister's Property had to be removed. During construction turbidity screens were installed and construction was restricted to periods of low water to reduce turbidity. Any excess turbidity caused by the construction would settle out within twenty-four hours. Dr. O'Malley left Pine Island in March and returned in October 1986. At the time he left the beach in front of his seawall extended an average of twenty-five feet from the seawall. When he returned in October the revetment had been completed and approximately fifty-percent of Petitioner's beach had eroded. In October 1986 the beach on O'Malley's property extended two to twenty feet from the seawall. O'Malley was aware that prior to his departure the Meister property had suffered severe erosion. Believing that the construction of the revetment was the cause of the erosion of his beach Petitioner instituted this action. This was the only issue seriously contested. Petitioner's expert witness opined that the revetment acted like a groin east of Petitioner's property and caused a littoral drift, which is basically from east to west in this area, to take the sand from Petitioner's property. Further this witness opined that the longer fetch (area of open water to the north-east of Meister property) was the primary cause of the erosion of the Meister property. Historically beaches erode and accrete. Gentle waves have the tendency to cause accretion while storm waves result in seaward migration of beach sand. Photographs (exhibit 3) of Petitioner's property show typically storm wave generated erosion. The expert opinion of Respondents' witnesses that the erosion of Petitioner's property was caused by storm driven waves and was not caused by the revetment is deemed the more credible explanation of the erosion of Petitioner's beach.
The Issue Whether the permit application of Clifford S. and Maria Ray (the "Rays") meets the statutory and rule requirements for the Department of Environmental Protection ("DEP" or the "Department") to issue to the Rays a permit to construct a multi- family dwelling and related structures seaward of the coastal construction control line ("CCCL") on their property in Brevard County?
Findings Of Fact Legislative Intent re: Beaches and Coastal Barrier Dunes The Legislature has declared that the beaches and the coastal barrier dunes in this state, subject by their nature to severe fluctuations, represent one of the most valuable resources of Florida. See § 161.053(1)(a), Fla. Stat. The Legislature has further declared that it is in the public interest to preserve and protect the beaches and dunes from imprudent construction because it can "jeopardize the stability of the beach-dune system, accelerate erosion, provide inadequate protection to upland structures, endanger adjacent properties, or interfere with public beach access." Id. The Legislature has therefore directed the Department of Environmental Protection "on a county basis along the sand beaches of the state fronting the Atlantic Ocean [and other salt water bodies]" to "establish coastal construction control lines." Id. The "Coastal Construction Control Line" A line of jurisdiction, rather than a line of prohibition, the Coastal Construction Control Line (the "CCCL or the "Control Line") is defined in Chapter 62B-331 of the Florida Administrative Code. The Control Line is: the line established pursuant to provisions of Section 161.053, F.S., and recorded in the official records of the county, which defines that portion of the beach-dune system subject to severe fluctuations based on a 100-year storm surge, storm waves, or other predictable weather conditions. Fla. Admin. Code. R. 62B-33.002(12). The Department's Office of Beaches and Coastal Systems has regulatory authority to permit or deny construction seaward of the Control Line pursuant to statutory and rule criteria. This proceeding concerns the exercise of that authority in the form of issuance of a permit for activity seaward of the Control Line in Brevard County. Brevard County's Control Line The Control Line in Brevard County was established by the Department of Natural Resources, an agency of the state and a predecessor of DEP, in 1981 (the "1981 CCCL"). A second Control Line in Brevard County was established in 1986, again by the Department of Natural Resources. It is approximately 150 feet landward of the 1981 CCCL. It will be referred to in this order as "the CCCL" or "the Control Line." The line established in 1981 will be referred to as the "1981 CCCL," to distinguish it from the Control Line established in 1986, the Coastal Construction Control Line applicable to this proceeding. The Parties Mrs. Pope Petitioner, Carole C. Pope, owns with her husband James M. Pope, oceanfront property located at Wilson Avenue, Brevard County, Florida, where the Popes reside part time. The Popes' property has a Cocoa Beach mailing address, but is not within the city limits of Cocoa Beach. Littoral to the Atlantic Ocean, the Popes' property was identified in the pre-hearing stipulation in the Rule-related Cases (discussed in this Order's Preliminary Statement) as "Lot 11, Block 101, Avon by the Sea as described in Plat Book 3, page 7 [presumably the Official Records of Brevard County] and east to Ocean, except the west 13 feet of Lot 11." See Final Order, Pope v. Department of Environmental Protection et al., Case No. 03-3860RX, paragraph 7, page 9. The Popes have two duplex units on their property. Built in the 1950's, they consist of concrete foundations, block walls, and 10-foot-high flat roofs. Mrs. Pope and her husband have retained the native, salt-tolerant vegetation that surrounds the duplexes. Protective of the property because it serves to enhance and stabilize the primary/frontal dune, it also adds to Mrs. Pope's enjoyment and use of her property. She enjoys the native flora, an integral part of the habitat of native fauna (gopher tortoises and indigo snakes, for example) that she enjoys watching. She particularly enjoys feeding and interacting with the sociable scrub jay. The Department and its Office of Beaches and Coastal Systems The Department is responsible for the administration of Parts I and II of Chapter 161, Florida Statutes, the "Beach and Shore Preservation Act." § 161.011, Fla. Stat. The Act confers on the Department the authority "to adopt rules related to the following provisions of this section [§ 161.053]: establishment of coastal construction control lines; activities seaward of the coastal construction control line; exemptions; property owner agreements; delegation of the program; permitting programs; and violations and penalties." § 161.053 (21), Fla. Stat. Pursuant to its rule-making authority in Section 161.053 (together with other specific authority), Florida Statutes, the Department promulgated Rule Chapter 62B-33: "Office of Beaches and Coastal Systems - Rules and Procedures for Coastal Construction and Excavation (Permits for Construction Seaward of the Coastal Construction Control Line and Fifty-Foot Setback)." The Office is in the Department. Fla. Admin. Code R. 62B-33.002(11). Permits for construction or other activities seaward of the construction control line, such as the permit in this case, are issued pursuant to Section 161.053, Florida Statutes, by the Program Administrator of the Bureau of Beaches and Wetland Resources on behalf of the Department. See Respondents 1, Vol. 2, Tab 22. The Department has not delegated Chapter 161 permitting authority to Brevard County. The Rays Clifford and Maria Ray are the owners of the property adjacent to Petitioner's property and the holders of Permit No. BE-1083, preliminarily issued by the Department in its final order of September 19, 2003. The property consists of four 50-foot-wide lots, Lots 12, 13, 14 and 15 in Avon by the Sea. Lot 12 is immediately adjacent to Mrs. Pope's property. Some of the native vegetation on the property has been disturbed by the planting of sod and installation of an irrigation system seaward of the Brevard County coastal setback line and the Control Line. The activity is the subject of administrative enforcement actions by the County and DEP. Although government claims of violations had not been resolved finally as of the date of hearing, the Rays have not resisted the claims. The Permit was issued to the Rays under the authority of Section 161.053, Florida Statutes. It authorizes activities on the Ray property seaward of the CCCL. This activity includes the construction of an eight-story, multi-family dwelling, a swimming pool and deck, a wooden beach/dune walkway, a parking area, masonry wall and an exfiltration trench, as described in more detail in the section of the Permit entitled "PROJECT DESCRIPTION." Respondents Ex. 1, Vol. 2, Tab 22, Permit No. BE- 1083, p. 2-3. The Department was not aware of the claims of violations made against the Rays referred-to above at the time that Mr. Tammisetti, the engineer assigned to review the permit file initially, recommended that the permit be issued. Had Mr. Tammisetti been aware of the claims he still would have recommended issuance of the permit. Coastal Systems and Fixed Coastal Cells The term "Coastal System" is defined by the Department in its rules: "Coastal System" is the beach and adjacent upland dune system and vegetation seaward of the coastal construction control line; swash zone; surf zone; breaker zone; offshore and longshore shoals; reefs and bars; tidal, wind, and wave driven currents; longshore and onshore/offshore drift of sediment materials; inlets and their ebb and flood tide shoals and zones of primary tidal influence; and all other associated natural and manmade topographic features and structures. Fla. Admin. Code R. 62B-33.002(13). Within the coastal system are "fixed coastal cells," also defined by Department rule: "Fixed Coastal Cell" is a geomorphological component of the coastal system which is closely linked internally by active physical processes and is bounded by physical features which exercise a major control on refraction patterns or which compartmentalize or severely limit longshore sediment such as headlands or inlets. Fla. Admin. Code R. 62B-33.002(24). Within and adjacent to a fixed coastal cell of Florida's coastal system lie sea, shore, beach, dune system, vegetation, uplands and structures with which this proceeding is concerned. The Beach and Dune System within the Fixed Coastal Cell The Ray property and the Pope property are located in a fixed coastal cell that extends from Canaveral Inlet (north of R014, one of a series of coastal monuments installed by the state) southward to Monument R050. The community in which the property is situated is a "Coastal Uplands: Beach Dune" community characterized by a beach and dune system. There is one primary/frontal dune with a height at the top of the bank of about 13.4 feet NGVD seaward of the proposed project. The portion of property on which the project is sited is between 7.3 and 10.7 feet NGVD. The most recent DEP design wave height elevation for R015 is 14.2 feet NGVD, higher than the existing dune elevation at the Ray property. Much of the Ray property behind the dune is lower in elevation than the elevation of contiguous properties, the likely result of persistent cutting of native vegetation that acts to intercept wind-blown sand as it moves along the shoreline. Beach and Dune Data in DEP File BE-1083 In the application review process, Mr. Tammisetti submitted a memorandum dated May 24, 2001, to Mr. McNeal. The memorandum appears to have been a form with blanks into which information was inserted or handwritten close to the appropriate blank. For example, under Section I., of the form "PROPOSED PROJECT" is "A. Project Location:", followed by a description with blanks left for number of feet, direction (north, south, east, west) reference monument number, county and project address. Handwriting close to the blanks leads one to understand or gather that it intends to communicate the following statements: The location of this project is approximately 100 feet N to 103 feet S of the Department of Environmental Protection's Reference Monument R-15, in Brevard County. Project Address: Harding Ave, Cape Canaveral. This is within the local jurisdiction of Brevard County. Respondents 1, Vol. 2, Tab 13. The form also contains Section II., "CHARACTERIZATION OF BEACH/DUNE SYSTEM". The section calls for three categories of characterization: A., a general description; B., beach topography in terms of shoreline alignment, berm width in feet, berm elevation in feet (NGVD), direction of net littoral transport, volume of net littoral transport in cubic yards per year, and general conditions; and C., Primary Dune/Bluff Topography with dune width in feet. None of the information called for by this section has been filled in on the form. At hearing, Mr. Tammisetti testified2 that berm width was 220 feet and the berm elevation ranged from 3 to 10 feet NGVD. He testified that the direction of littoral transport was north to south but he did not know the volume of net littoral transport. He stated that the "general site condition" was an eroding shoreline. He estimated the dune width at between 30 to 40 feet. These facts and figures exist under an overarching consideration. The beach near R015 that fronts the Pope and Ray property is critically eroding.3 Vegetation on the Ray Property There is a sea grape cluster and numerous palm trees on the Ray property. The seaward most continuous line of native salt-resistant vegetation or the "vegetation line" is near the line at the toe of the slope of the dune bank depicted on the topographic survey drawing submitted as part of the application. Nanette Church, at the time an employee of Brevard County, visited the site on July 1, 2003. She documented the presence of fresh sod and a new irrigation system installed seaward of the County's coastal setback line, a line parallel to and 25-feet landward of the 1981 CCCL. Two days later, DEP Inspector Gene Verano conducted a site inspection and documented the placement of sod and the installation of an extensive irrigation system. On July 31, 2003, the Department under the signature of Jim Martinello, an Environmental Manager in the Bureau of Beaches and Wetland Resources, issued a warning letter to Mr. Ray with regard to "POSSIBLE UNAUTHORIZED ACTIVITIES SEAWARD OF THE COASTAL CONSTRUCTION CONTROL LINE." The letter reads, in part, Pope 3. [I]t appears that you have again been engaged in unauthorized activities on your property located approximately 100 feet north to 100 feet south of the Department of Environmental Protection's reference monument R-15, in Cocoa Beach, in Brevard County, Florida. The possible violation consists of the destruction/removal of native vegetation and placement of sod and an irrigation system seaward of the coastal construction control line without benefit of a permit from the [department.] The sod seaward of the CCCL has a negative effect on the stability of the dune system. A weakened dune system allows for storm surge and overwash to breach the dune and cause washout on the landward side of the dunes. Brevard County has not yet issued a land clearing or landscape permit to the Rays. A "Brevard County Land Development Site-Plan Approval" with an approval date of December 30, 2003, warned, "[i]t is the responsibility of the Owner/Engineer of Record to contact Office Natural Resources for a Land Clearing/Landscaping Permit." Respondents' 1, Vol. 1, Tab 12. The Rays are not contesting County or DEP enforcement actions relative to the land clearing, sod placement, and irrigation system installation. Project Description The project proposed by the Rays is to be located on their property in the unincorporated area of Brevard County known as "Avon-by-the-Sea," in the vicinity of Department monument R-015. The project is known by Brevard County as the Ray Condos and also as the Michelina Condominium. The location of the multi-family dwelling relative to the Control Line is "[a] maximum of 105.56 feet seaward." Id. Its exterior dimensions are "209.67 feet in the shore normal direction by 84 feet in the shore-parallel direction." Id. The type of foundation is "Pile." Id. There is no mention in the Permit of the height of the building. The swimming pool is described in the Permit in detail with regard to its dimensions and location (a maximum of 101.49 feet seaward of the control line), the type of construction and its maximum depth: six feet. Excavation/Fill for the project is described in terms of volume of excavation, its location, volume of fill as replacement, and location of fill. The Excavation/Fill description is subject to Special Permit Condition 6. Among other provisions of the condition, the fill is to be "from a source landward of the control line and shall consist of sand which is similar to that already on the site in both grain size and coloration." Id., p. 4. Other permitted structures and activities are listed and described in the Permit with reference to special permit conditions: A wooden beach/dune walkway structure of dimensions 174 feet shore-normal by 4 feet shore-parallel is to be located seaward of the control line. See Special Condition 7. A 4-foot to 14-foot swimming pool deck attached to the periphery of the swimming pool is to be located a maximum of 105.96 [feet] seaward of the control line. See Special Permit Condition 2.1. Paver-block parking area on the south side of the proposed dwelling. Masonry walls along the north and south property lines to extend a maximum of 105 feet seaward of the control line. See Special Permit Condition 2.2. An exfiltration system trench on the south side of the proposed dwelling. Among nine special conditions in the Permit are that no work can be conducted until a DEP "notice to proceed" has been received by the Rays. Another is that prior to the issuance of such a notice "two copies of detailed final site and grading plans and specifications" shall be submitted including two sets of landscape drawings. Id., p. 3, Special Permit Condition 2. See id., 2.3. The landscape plan must be submitted to Brevard County for approval under the Permit's special conditions. Given Brevard County's requirement that the Rays secure a Land Clearing/Landscaping Permit, there will be an ongoing process that poses the potential to ensure that the Rays' project will be designed to minimize the impact on native vegetation. The process also may require a restoration plan, as well, for the impact to native vegetation caused by the sod and the irrigation system. The Rays have submitted such a plan to the County. Relationship of the Proposed Project to the Pope Property The proposed multi-family dwelling is sited 10 feet south of the northern property line (the line that serves as the southern boundary of the Pope property). Ten feet is the minimum setback from adjacent property allowed by the county. The duplexes on the Pope property are situated in a range from 3.5 to 4.5 feet from the property line (the border with the Ray property.) The project, therefore, is proposed to be as close as 13.5 feet of the Pope duplexes. If built, running the length of the duplexes, it would create a relatively narrow space between the proposed structure and the Popes' duplexes that ranges from 13.5 feet to 14.5 in width. The Application The Rays submitted their CCCL permit application to the Department through their agent, Joyce Gumpher. On January 24, 2003, Ms. Gumpher executed a certification "that all information submitted with this application is true and complete to the best of [her] knowledge." Respondents Ex. 6, APPLICATION FOR A PERMIT FOR CONSTRUCTION SEAWARD OF THE COASTAL CONSTRUCTION CONTROL LINE OR FIFTY-FOOT SETBACK. The application was received by DEP on January 27, 2003. Additional information was requested by the Department. On April 21, 2003, the Department deemed the application complete. During the application process, several plan sheets were revised. Revised plan sheets were submitted after the application was deemed complete (see Respondents' Ex. 6, July 29, 2003 plans and September 5, 2003 plans) and once prior to DEP's determination of its completeness. (see id., April 7, 2003 plans). Review of the Application On August 26, 2003, Mr. Tammisetti submitted a memorandum to Mr. McNeal that recommended approval of the application with special permit conditions. The memorandum, similar in form to the memorandum submitted on May 24, 2001, except for the lack of Part II., is entitled "Description of Beach and Dune System Fronting the Subject Property and an Analysis of Impacts to be Expected From the Proposed Construction." Respondents 1, Vol. 2, Tab 20. It describes the proposed project but, lacking Part II., it neither characterizes nor describes the beach/dune system. Nor does it analyze the impacts of the proposed project other than to provide the "final comment" that "[t]he proposed project is landward of line of construction and 30-year erosion project. Impactive shore- parallel coverage is approximately 72%." Id., p. 3. Under its rules, after reviewing all information required, the Department is mandated to: Deny any application for an activity which either individually or cumulatively would result in a significant adverse impact including potential cumulative effects. In assessing the cumulative effects of a proposed activity, the Department shall consider the short-term and long-term impacts and the direct and indirect impacts the activity would cause in combination with existing structures in the area and any other similar activities already permitted or for which a permit application is pending within the same fixed coastal cell. The impact assessment shall include the anticipated effect of the construction on the coastal system and marine turtles. * * * Require siting and design criteria that minimize adverse impacts and mitigation of adverse or other impacts. Fla. Admin. Code R. 62B-33.005(3). As found earlier, the file in BE-1083 does not contain any documentation that the Department conducted the impact assessments required by the rule. Nonetheless, the Department based its evaluation on the portion of the fixed coastal cell from just north of R013 to approximately 400 feet south of R017 depicted on Respondents' 7. Respondents' 7 Respondents' 7 is an aerial photograph of developed uplands and off shore waters of the Atlantic Ocean in between which is the shore line and a stretch of beach in Brevard County. The sandy beach in the photo runs from north to south from Monument R013 to approximately 400 feet south of Monument R017, five monuments in a series set by the state along the Brevard County coast. The photograph is data the Department reviewed to determine if existing structures established a "reasonably continuous and uniform construction line closer to the mean high water line than [the coastal construction control Line]." § 161.053(5)(b), Fla. Stat. (This "reasonably continuous and uniform construction line" will be referred to as the "Construction Line" in this order.) The Pope property and the Ray property both straddle the Construction Line. The photograph shows four structures (the "Four Structures") that were determined by DEP to establish the Construction Line. Two are to the north of the Ray property; two are to the south. Of the two structures to the north, the closest is between 400 and 450 feet north of the northern boundary of the Ray property. It sits between Monument R015 and R014. The other structure to the north used to establish the Construction Line lies between Monument R014 and R013. Its southernmost corner is approximately 1200 feet to the north of the northern boundary of the Ray property. The roof of the closest of the Four Structures to the south, lying between Monument R015 and R016, viewed from the air above is rectangular indicating the structure to have a rectangular footprint. Positioned at an angle to the coast, its southeastern corner is along the 1981 CCCL. That corner is approximately 400 feet south of the southern boundary of the Ray property. The second structure to the south sits between R016 and R017. Its northernmost corner is roughly 850 feet south of the southern boundary of the Ray property. The Application Rule Florida Administrative Code Rule 62B-33.008(4), entitled "Permit Application Requirements and Procedures" (the "Application Rule"), requires that the Rays' application contain certain specific information, including that identified in subsection (f): Two copies of a topographic survey drawing of the subject property. The topographic information depicted in the drawing shall be from field survey work performed not more than six months prior to the date of the application. The rule further calls for the topographic survey drawing to include specific information such as "[t]he location of any existing vegetation line on the subject property." Fla. Admin. Code R. 62B-33.008(4)(f)9. The topographic survey drawing submitted as part of the application in January of 2003 reveals a survey date of "7/17/02." Respondent's Ex. 1, Sketch of Boundary and Topographic Survey, Lots 12-15, Block 101, Avon by the Sea, Brevard County, Florida. Other than the date of the survey, the evidence at hearing did not reveal when the fieldwork in support of the survey was conducted.4 In all likelihood the fieldwork was conducted close to July 17, 2002, but obviously prior to July 17, 2002. Whether the date of the application is considered to be the date of Ms. Gumpher's certification (January 24, 2003), or the date of its receipt by DEP (January 27, 2003), it does not depict "field survey work performed not more than six months prior to the date of the application." January 24, 2003, is six months and one week after July 17, 2002. January 27, 2003, is six months and 10 days after the date of the survey. The Vegetation Line The topographic survey drawing submitted as part of the application did not meet precisely the requirements of the Application Rule in several other ways. For one, it did not label the location of "any existing vegetation line on the subject property." At hearing, the Rays submitted a revised copy of the topographic survey drawing (still dated "7/17/02"). The revision labels a line indicated on the originally submitted topographic survey drawing as "TOE OF SLOPE" (within a few feet of the top of the dune bank) as "TOE OF SLOPE AND VEGETATION LINE." Thus, it is apparent that the originally submitted topographic survey drawing depicted the vegetation line; it merely failed in its labeling of the vegetation line. The Department, once it became aware of the omission of a reference to a vegetation line in the original submission, waived the requirement for one. At hearing, Mr. McNeal testified that the waiver was authorized by subsection (7) of the Application Requirements and Procedures Rule: The Department recognizes that the requirements specified in paragraphs 62B- 33.008(4). . . (f) . . ., F.A.C. may not, due to the project circumstances, be applicable or necessary to ensure protection to the beach and dune system. In such cases, the applicant shall, as part of the application, identify those requirements and state the reason why they are inapplicable. The Department shall waive requirements that do not apply. Fla. Admin. Code R. 62B-33.008(7). There is no evidence of record that the Rays informed DEP of a position that the "location of the vegetation line" on the topographic survey drawing was a requirement inapplicable or unnecessary to ensure protection to the beach and dune system.5 Nonetheless, construing its waiver authority to be broader than authority limited to cases in which identification of inapplicable and unnecessary requirements had been made by those seeking DEP waivers, the Department waived the requirement. The waiver was based on knowledge gained from the experience of DEP employees. The employees (Mr. Tammisetti and Mr. McNeal) knew that the vegetation line would be close to the top of the dune bank line and the toe of slope line, both of which were located on the topographic survey drawing.6 Respondents' 2 supports the Department's waiver since it labels the vegetation line where the Department roughly expected it to be. Complete Dimensions and Distance Perpendicular The Application Rule further demands that the topographic survey drawing contain: 15. Accurate dimensions and locations of the foundation outlines of any structures in the immediate contiguous or adjacent areas that the applicant contends have established a reasonably continuous and uniform construction line if the permit is requested under the provisions of Section 161.053(5)(b) or 161.052(2)(b), F.S., and the distance perpendicular [the "Distance Perpendicular"] from the CCCL or 50-foot setback to the seaward corners of the foundations of any major structures . . . . Fla. Admin. Code R. 62B-33.008(4)(f). The application contained the dimensions and locations of the two (2) duplexes located on the Pope property, that is, the adjacent area to the north of the Ray property. With regard to the adjacent area to the south of the Ray property, the application contained the seaward dimensions and locations of the major structure that makes up the Discovery Beach Resort structure. The topographic survey drawing did not contain the dimensions of the complete footprint of the Discovery Beach Resort. Nor did it contain the distance perpendicular from the CCCL or 50-foot setback to the seaward corners of the foundations of all major structures depicted. Mr. McNeal noticed that required elements were missing from the application. When he made the permitting decision, he waived them pursuant to a delegation of authority from the Office of Beaches and Coastal Systems. Delegations of Authority Office of Beaches and Coastal Systems The Director of the Office of Beaches and Coastal Systems has delegated certain authority to subordinates in the Office of Beaches and Coastal Systems with respect to the CCCL permitting program. The delegations, as reflected in a document entitled "Delegations of Authority, OFFICE OF BEACHES AND COASTAL SYSTEMS" (Pope Ex. 1), is to "the Director of Office of Beaches and Coastal Systems, or his/her designee." Id., 3.a. As the administrator of the CCCL program within the Bureau of Beaches and Wetlands Resources, Mr. McNeal has been delegated authority under Delegation "OBCS-9" (id., p. 14 of 24), to "[t]ake final agency action on permit applications . . . pursuant to Sections . . . 161.053 . . ., Florida Statutes, and Rule 62B-33, F.A.C., [subject to exceptions immaterial to this proceeding.]" Id. The authority so delegated is not without limitation. Among limitations enumerated and express in the Delegations of Authority document is that "[t]the exercise of any delegated authority shall conform with all statutes and rules applicable to the DEP." Id., 3.a. Waivers Pursuant to Delegated Authority Pursuant to the authority over final agency action on CCCL permit applications, Mr. McNeal, as the head of the CCCL Program in the Office of Beaches and Shores, waived the depiction of the location of the vegetation line on the topographic survey drawing, the full dimensions of the Discovery Resort in the adjacent area to the south of the Ray property and the notation of the Distances Perpendicular. He did so because the information contained on the topographic survey drawing was sufficient, in his view, to allow the Department to perform the calculations and analyses as part of the application process that would be served by a review of the topographic survey drawing. An example has been alluded to in this order. Based on years of collective experience, Mr. McNeal and Mr. Tammisetti concluded it was reasonable to assume the vegetation line would be very near the toe of the slope line in relation to the dune bank. Their assumptions were proved correct at hearing. The dimensions and locations of the major structures located immediately north and south of the proposed project (the Pope duplexes and the Discovery Resort structure) and the Distances Perpendicular were required to be included on the topographic survey drawing, but they were not intended by the Rays to establish a Construction Line. Establishment of any such line is governed by Section 161.053(5)(b), Florida Statutes: If in the immediate contiguous or adjacent area a number of existing structures have established a reasonably continuous and uniform construction line closer to the line of mean high water than the foregoing [the CCCL], and if the existing structures have not been unduly affected by erosion, a proposed structure may, at the discretion of the department, be permitted along such line on written authorization from the department, if such structure is also approved by the department [and other conditions are met]. A Construction Line The Rays contend in their application and DEP agrees that the Four Structures establish a Construction Line. Once such a line is established provided the structures are not duly affected by erosion, the Department is conferred with the discretion to permit a proposed structure along the line seaward of the CCCL under certain circumstances. See § 161.053(5)(b), Fla. Stat. Among those circumstances, the permit "shall not contravene setback requirements or zoning or building codes established by a county or municipality which are equal to, or more strict than, those requirements provided [by statute.]" § 161.053(5)(b), Fla. Stat. Furthermore, by rule of the Department, written evidence from local government must be provided that the location of the proposed structure along a Construction Line seaward of the CCCL is consistent with the Local Comprehensive Plan. See Fla. Admin. Code R. 62b-33. Written evidence that Brevard County regards the Rays' proposed site to be consistent with Local Comprehensive Plan and not contrary to local setback requirements or zoning codes was provided by Brevard County to the Department. Establishment of a Construction Line Whether a Construction Line can be established for a proposed project is unique to the project and its coastal location. To establish such a line, the Office of Beaches and Coastal Systems may rely exclusively on information provided by the applicant for a permit to construct along such a line. The Office may also refer to its own database of aerial photographs (as it did in this case) and other data with regard to the State's coastal systems. The Construction Line running across the Ray property accepted by DEP is nearly identical to the 1981 CCCL. In contesting the establishment of the Construction Line, Mrs. Pope makes a number of points, several of which are worthy of discussion. For one, in 1993, the Department considered an administrative challenge brought by Mrs. Pope to the CCCL permit for the construction of the Days Inn Tower (now Best Western) hotel (one of the structures used by the Rays to establish a Line of Continuous Construction). See, OR-1, Pope v. Department of Environmental Protection et al., Agency Final Order dated May 9, 1994, DOAH Case No. 93-4560 (the "1993 Pope Case.) The Pope duplex had been found to be three or four blocks north of the property for which the permit was sought. If her property had been found immediately adjacent to the Days Inn Tower property, Mrs. Pope would have been accorded standing to contest issuance of the permit to the Days Inn Tower applicant. The hearing officer had recommended that Mrs. Pope not be accorded standing under the rule because her duplex property was not "immediately adjacent" to the Days Inn Tower parcel. Since Mrs. Pope's parcel was separated by at least what has been identified in this proceeding as the Ray property and the property of the Discovery Resort, she did not qualify for standing under the DEP Rule. Nevertheless, Mrs. Pope was afforded the opportunity to acquire standing by proving that her substantial interests would be affected by issuance of the permit. The hearing officer concluded that her attempt in this regard failed.7 The Department accepted the hearing officer's recommendation that Mrs. Pope be determined to have no standing, in part because her property was not "immediately adjacent" to the Days Inn Tower property. Mrs. Pope also asserts that the Four Structures along the 1981 CCCL do not establish a Construction Line on the basis of the testimony of her witness, Dr. Harris. Dr. Harris opined that the structures to be used to establish the Line of Continuous Construction, if one exists, are not the four used by DEP that are in the area of the Ray property but the structures on the two pieces of property closer to the Ray property, that is, immediately adjacent: the Pope property to the north and the Discovery Resort property to the south. The easternmost point of the structure on the Pope property is approximately 50 feet landward of the 1981 CCCL and extends approximately 100 feet seaward of the Control Line. The structure on the Discovery Resort property to the south is along the Control Line. See Respondents' 7. The line that Dr. Harris would establish does not run parallel to the shore line, the 30-year erosion line, the 1981 CCCL or the Control Line. It would run at an angle of approximately 15 degrees from the easternmost point of the Pope duplexes (the "point of beginning") about 425 feet to the easternmost point of the Discovery Resort structure. The point on the Discovery Resort structure (at the end of the line) is approximately 100 feet seaward of the point of beginning. If these structures are to be considered in the determination of whether a Construction Line exists as Mrs. Pope argues, then continuing the line to include the Four Structures would yield broken lines rather than a reasonably "uniform" and "continuous" line. The Department did not consider the structures in the property immediately adjacent to the Ray property to break the line it determined is established by the Four Structures. It ignored other structures as well between the northernmost and the southernmost of the four structures. Mrs. Pope, therefore, describes the Construction Line established by the Department as "imaginary" and without a factual basis. This point is one of opinion. The Construction Line is neither imaginary nor without a factual basis. It has a factual basis in precisely the data used by DEP: the aerial photograph that shows four major structures between Monuments R013 and R017, Respondents' 7, along the 1981 CCCL. The disregard for the Pope duplexes and the Discovery Resort structure as well as other structures in the areas north and south of the Ray property is a matter that falls within professional opinion and Department expertise. The establishment of the Construction Line is justified by the data DEP examined: Respondents' 7 (on which the Four Structures were identified and circled by Mr. Tammisetti at hearing.) The greater weight of the evidence is that DEP's determination of the establishment of the Construction Line should not be disturbed. It is, moreover, not surprising that such a line exists. One would expect that structures built after 1981 but before 1986 would be located along the 1981 CCCL and that structures that followed (such as the Discovery Resort structure) would be built along that Construction Line. Post-establishment of a Construction Line Establishment of a Construction Line does not entitle an applicant to a permit to build along that Construction Line. After a Construction Line is accepted by DEP as established, an applicant must satisfy three remaining sets of conditions expressed in Section 161.053(5)(b), Florida Statutes. Section 161.053(5)(b), Florida Statutes A discretionary exercise Once a Construction Line is established, an application for a permit to allow a proposed structure is subject to the discretion of the Department: "a proposed structure may, at the discretion of the department, be permitted along such line on the written authorization of the department, if such structure is also approved by the department." ii. Local Requirements The Department has no such discretion, however, if the construction or activity would "contravene setback requirements or zoning or building codes established by a county or municipality which are equal to, or more strict than . . . requirements [in chapter 161]." Id. To this list, the Department, by rule, has added consistency with state-approved Local Comprehensive Plans. See Fla. Admin. Code R. 62B- 33.008(4)(d). Before exercise of department discretion and inquiry into compliance with local requirements, there is a more fundamental condition that must be demonstrated by the applicant: the existing structures that establish the Construction Line must not have been unduly affected by erosion: If in the immediate contiguous or adjacent area a number of existing structures have established a [Construction Line], and if the existing structures have not been unduly affected by erosion, a proposed structure may, at the discretion of the department, be permitted along such line . . . [h]owever, the department shall not contravene [local requirements] . . . equal to, or more strict than, those requirements herein. § 161.053(5)(b), Fla. Stat. Unduly Affected by Erosion The parties differ in their view of the testimony and evidence introduced at hearing with regard to whether structures that establish the Construction Line "have not been unduly affected by erosion." Id. Neither DEP employees nor the Rays' witnesses visited the shoreline between R0-13 and R-017 to evaluate the four structures that establish the Construction Line and the effects of erosion, if any.8 Mrs. Pope asserts in her Proposed Recommended Order, "[n]o evidence or testimony was offered as to whether the structures considered by DEP were affected by erosion." Petitioners' Proposed Recommended Order, p. 24. In contrast, Respondents cite to the testimony of Mr. Boehning and Respondent's 7 with the assertion, "[t]he existing structures, which form the line of continuous construction, have not been unduly affected by erosion." Respondents' 7 supports the claim of Respondents. It reveals a distance perpendicular from the Construction Line to the dark, wet sand along the shore to be approximately 275 feet. This distance encompasses white sandy beach that is approximately 175 feet and a vegetated area that is approximately 100 feet. The finding that the structures that establish the Construction Line are not unduly affected by erosion does not mean that there are not erosion problems in the area. In fact, as found earlier in this order, the beach depicted on Respondents' 7 is "critically eroding." The stretch of beach depicted in the aerial photograph that is Respondents' 7 has undergone considerable fluctuation since 1963 through erosion and beach nourishment. From 1972 to 2002, for example, the location of the mean high water line at R-015, the monument closest to the Pope and Ray properties, has varied by 206 feet from a low in September of 1972 to a high of 369.3 feet in April of 2001. Dr. Harris wrote this in a report introduced into evidence: The beach profile data show that at R-15 the beach and dune are subject to erosion. From 1972 to 2002 the variation in the MHW shoreline position was 206 feet. Beach nourishment and inlet sand by-passing operations were performed between some of the time periods, and are largely responsible for the periodic beach and dune widening. Even with the beach nourishment project, dune erosion continues to be a problem, and although the recent beach nourishment project greatly widened the beach, the position of the dune remained the same. The FDEP design wave height elevation for a 100-year storm is 14.2 feet NGVD for R-15, which is higher than the existing dune elevation. This means that the upland properties would experience storm surge, flooding and wave action during a 100-year storm. Pope 16. Projects of beach nourishment (placement of sand through human activity) were performed in 1972, 1986 and 2001. The need for beach nourishment and re-nourishment reinforces the status of the beach near R-015 as "critically eroding" and underscores the importance of protecting as much of the dune system as possible. That the beach is critically eroding is not inconsistent with a finding that the structures that establish the Construction Line are not unduly affected by erosion. Whether or not due to the 1986 and 2001 nourishment projects, the evidence of record is that, despite the status of the beach as critically eroding, the structures that establish the Construction Line are not unduly affected by erosion. Not Contrary to Local Requirements On December 30, 2002, a site-plan approval was issued by Brevard County with regard to "RAY CONDOS aka MICHELINA CONDOMINIUM" with a site address of "420 Harding Avenue, Cocoa Beach, FL 32931." Respondents' 1, Vol. 1, Tab 12, second page. Signed by the designee of the Director, Permitting and Enforcement, the development order is entitled, "BREVARD COUNTY LAND DEVELOPMENT SITE-PLAN APPROVAL" and contains the following: The site plan to which this approval is attached has been reviewed by affected County divisions, departments and agencies and has been determined to comply in general with the Brevard County Code of Ordinances and Comprehensive Plan Elements. * * * It is the responsibility of the Owner/Engineer of Record to contact Office of Natural Resources for a Land Clearing/landscaping Permit Two (2) sets of As-Built drawings must be provided to Land Development prior to the Issuance of a C.O. Id. The development order concludes with a statement related to the vested right of the Rays to develop in accord with the site plan: If a Certificate of Occupancy has not been issued for the principal structure by Dec. 30, 2005 the three (3) year vesting period, beginning with the date of site development plan approval, expires and said site plan shall become Null and Void. Only those phases of the development that have an active and valid building permit may be completed after the three-(3) year time period. Id. The reference in the site-plan approval to the "Brevard County Code of Ordinances" does not include building codes. The reference covers local setback requirements and zoning codes. Mrs. Pope appealed the issuance of the site-plan approval to the Brevard County Board of County Commissioners (the "Board"). Her appeal was heard over three meetings of the Board on May 6, 2003, June 8, 2003, and August 12, 2003. At the conclusion of the August 12, 2003, proceedings on the appeal, the Board voted unanimously to accept the staff recommendation to deny the appeal. An unnumbered resolution of the Board "DENYING THE APPEAL OF JAMES AND CAROLE POPE . . . PERTAINING TO THE MICHELINA CONDOMINIUM SITE PLAN" was produced by Mrs. Pope at the hearing together with the following statement of a Deputy Clerk for the Board: This is to advise that the Office of the Clerk to the Board of County Commissioners does not have any correspondence indicating a copy of the Findings of Fact on Michelina Condominium was forwarded to Mr. or Mrs. Pope. Pope 7. The resolution is signed by the Chairperson of the Board. Immediately below the signature block there appears the following: "(As approved by the Board on August 12, 2003)." Pope 8. The document is not stamped received by the Clerk of the Board or the County Clerk's Office, nor is there other clear indicia that the order has been rendered through a filing with the Clerk's office. On its face, however, appears an undated attestation of a deputy clerk under a seal of Brevard County that appears to attest to the Chairperson's signature. As of the dates of the final hearing in this proceeding, Mrs. Pope had not sought judicial review of the decision of the Board. At hearing, on the strength of the signed resolution denying Mrs. Pope's appeal of the site-plan approval and the site-plan approval, itself, and the apparent finality of the approval, Mrs. Pope was ruled estopped from presenting evidence that the Permit contravened local setback or zoning requirements or was inconsistent with the Local Comprehensive Plan. The establishment of a Construction Line, that the structures establishing the line are not unduly affected by erosion, and the collateral estoppel of Mrs. Pope's claim that construction or activity seaward of the Control Line along the Construction Line is contrary to local requirements, clears the way for the exercise of Department discretion as to whether to issue the permit. Department Discretion The Department's exercise of discretion must, of course, take into consideration the beach and dune system within the fixed coastal cell in which Ray property and the Pope property are located. No other conclusion could be gathered from the statements of legislative intent and the statutory scheme. Lest there be any misunderstanding, the Department has codified its policy statement on such matters: (1) The beach and dune system is an integral part of the coastal system and represents one of the most valuable natural resources in Florida, providing protection to adjacent upland properties, recreational areas, and habitat for wildlife. A coastal construction control line (CCCL) is intended to define that portion of the beach and dune system which is subject to severe fluctuations caused by a 100-year storm surge, storm waves, or other forces such as wind, wave, or water level changes. These fluctuations are a necessary part of the natural functioning of the coastal system and are essential to post-storm recovery, long term stability, and the preservation of the beach and dune system. However, imprudent human activities can adversely interfere with these natural processes and alter the integrity and functioning of the beach and dune system. The control line and 50-foot setback call attention to the special hazards and impacts associated with the use of such property, but do not preclude all development or alteration of coastal property seaward of such line; Fla. Admin. Code R. 62B-33.005, Department Policy Statement on Permits. The exercise of this discretion is guided by criteria under rule. Among those criteria are those found in 62B- 33.005(4)(g): The construction will not cause a significant adverse impact to marine turtles, immediately adjacent properties, or the coastal system unless otherwise specifically authorized in this rule chapter. Chapter 62B-33, Florida Administrative Code, defines the term "Impacts" to include separate definitions for the terms "Adverse Impacts," "Significant Adverse Impacts," "Minor Impacts," and "Other Impacts": "Impacts" are those effects, whether direct or indirect, short or long term, which are expected to occur as a result of construction and are defined as follows: "Adverse Impacts" are impacts to the coastal system that may cause a measurable interference with the natural functioning of the system. "Significant Adverse Impacts" are impacts of such magnitude that they may: Alter the coastal system by: Measurably affecting the existing shoreline change rate; Significantly interfering with its ability to recover from a coastal storm; Disturbing topography or vegetation such that the system becomes unstable or suffers catastrophic failure; . . . * * * (d) "Other Impacts" are impacts associated with construction which may result in damage to existing structures or property or interference with lateral beach access. Fla. Admin. Code R. 62B-33.002(30). Minimization of Impacts and No Significant Adverse Impacts The site selected on the Ray property for the proposed project poses impacts to Mrs. Pope's duplexes during a storm event such as a 100-year storm. Because of the shore- parallel dimension of the proposed structure (84 feet), storm- generated waves and storm surge would be concentrated into the relatively narrow gap between the proposed structure and the duplexes. The resulting hydrodynamic load would cause scouring of the foundations of the duplexes. The proposed project has "frangible" or "breakaway" ground level walls. They would pose the potential for generating waterborne missiles that, hydro-dynamically propelled, would damage the duplexes. The proposed project was designed in accordance with the American Society of Civil Engineers 7 Code ("ASCE-7") and most pertinently (since referenced in the Construction Line Statute), the Florida Building Code. But the Building Code does not take into consideration a proposed structure's design or proposed site on an adjacent property or the adjacent property's structures. The proposed project, moreover, is not designed and sited to mitigate aerodynamic loading on Mrs. Pope's duplexes. During high-wind conditions, there will be a number of wind effects on the duplexes caused by the proximity of the proposed project: gust loading, high turbulence shedding, and vortex shedding among others that can be reasonably expected to cause structural impacts to the duplexes such as suction loads on roofs and eaves, flying debris and window breakage. The proximity of the proposed structure to the Pope property will have a shading effect that will cause adverse impacts on the growth of native coastal vegetation on the Pope property. As a result, there will be a reduction in the interception of wind-driven sand by the vegetation that enables it to develop healthy, deep root systems that add to dune stability.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that: an impacts assessment be conducted as required by Florida Administrative Code Rule 33.005(3)(a); that the proposed project be re-sited to mitigate the impacts that its siting now poses to the Pope Property and the Popes' duplexes; that the proposed project be permitted to be constructed up to the Construction Line, provided that the permit is supported by both the impacts assessment and a re- siting of the proposed project to mitigate wind, water and shading impacts; and if the proposed project is not supported by an adequate impacts assessment, or if it cannot be re-sited to mitigate the impacts to the Pope Property, that the permit be denied. DONE AND ENTERED this 2nd day of March, 2004, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of March, 2004.
The Issue Whether the petition that initiated this case was timely as to Petitioner Fullman? If so, whether Petitioner Fullman has standing? Whether Petitioner Burgess has standing? Whether the record demonstrates reasonable assurances for approval of Martin County's application for a Consolidated Environmental Resource Permit and Sovereign Submerged Lands Lease to construct and operate a public mooring field in the Jensen Beach to Jupiter Inlet Aquatic Preserve and to construct and operate a "dinghy" dock immediately south of the Jensen Beach Causeway to support the mooring field?
Findings Of Fact The County, the Lagoon and the Aquatic Preserve Martin County (the "County") is located on the Atlantic Coast in southeast Florida. The Indian River Lagoon (the "Lagoon") runs along the eastern edge of the County in a north-south direction parallel to the coast. The Lagoon is separated from the Atlantic Ocean by barrier islands except for a connection to the ocean through the St. Lucie Inlet. The Lagoon is designated an "Outstanding Florida Water" ("OFW") and its waters are classified as Class III by the Department. The portion of the Lagoon within the County's boundaries is part of the state-designated Jensen Beach to Jupiter Inlet Aquatic Preserve (the "Aquatic Preserve"), one of three aquatic preserves in the Lagoon. The waters and submerged lands of the Aquatic Preserve are used extensively by the public for commercial, recreational, and scientific purposes consistent with statutory authority that allows uses other than preservation. Uses include commercial docking facilities, defined by rule 18-20.003(16) as "docking facilities for an activity which produces income, through rental or any other means " The Parties Martin County Board of County Commissioners The Martin County Board of County Commissioners (the "Board of County Commissioners") is the County's governing body. In the name of the Board of County Commissioners, the County applied for the permit and sovereignty submerged lands lease that is the subject of this proceeding. The Permit and Lease will allow the County to construct and operate a managed mooring field for boats (the "Mooring Field" or the "Project") to be located within a near-shore area of the Aquatic Preserve. Boats now commonly anchor in the area in a random, un-regulated manner and will continue to do so without the permit and the lease. b. The Department The Department is the state agency with responsibility to conserve, protect, and control water resources pursuant to Part IV, chapter 373, Florida Statutes, and chapter 62, Florida Administrative Code. The Department also has the authority to administer the state's program for leases of sovereignty submerged lands, unless such responsibility has been delegated by the Board of Trustees to a water management district or the Department of Agriculture and Consumer Services by an operating agreement. The parties agree that the Department has the authority to administer the sovereignty submerged lands lease applied for in this case. See Petitioners' Proposed Recommended Order, para. 3 at 6; Martin County's Proposed Recommended Order, para. 5 at 7; and the Department's Proposed Recommended Order, para. 2 at 6. Petitioners Petitioner Joseph Burgess resides with his wife in an unincorporated area of the County known as Jensen Beach. He has a direct view of the Lagoon from the rear deck of his home, approximately six-tenths of a mile west of the Project site. Mr. Burgess's wife holds record title to the property, acquired before their marriage. He has a spousal interest in the homestead. He helped his wife to design and build their home on the property and the two have lived there for the past 14 years. They intend to live there for the foreseeable future. Mr. Burgess visits the area of the Project several times a week. He frequently takes his grandchildren and out-of- town friends to the area to appreciate the beauty of the Aquatic Preserve, watch the fishermen, and enjoy the environmental diversity of the Lagoon. When Mr. Burgess drives to the area by way of the Jensen Beach Causeway (the "Causeway") he often finds it difficult to find a parking spot. Mr. Burgess attended community meetings when the Mooring Field was proposed and discussed its impact to the area with other members of the community including Petitioner Fullman. He contacted the Department regarding the status of the Project and requested notice of permit activity. Notice, however, was not provided to him directly; he learned of the Department's intent to issue the permit from counsel. Mr. Burgess has a number of concerns about the Project. He fears it will diminish his way of life and the character of the area in which he resides. He worries that it will add congestion to a near-by rotary for vehicular traffic that he negotiates to get to and from his home nearly every day. He is concerned that the Project will destroy habitat for marine life and the birds which nest and feed in the ecosystem of the Aquatic Preserve and the Lagoon. Petitioner Thomas Fullman owns and resides in a home in Jensen Beach overlooking the Project site. He and his family have enjoyed the Lagoon and the Aquatic Preserve for the past 20 years and he has a deep appreciation for them. Mr. Fullman's concerns for the Aquatic Preserve and the Lagoon led him to challenge the issuance of a permit to construct a seawall in another administrative proceeding. The seawall was proposed to be constructed on the opposite side of the Causeway several hundred feet north of the proposed Mooring Field. The challenge was successful. See Reily Enterprises, LLC v. Fla. Dep't of Envtl. Prot., 990 So. 2d 1248 (Fla. 4th DCA 2008). Mr. Fullman boated in the Lagoon frequently when his children were growing up. He now boats in the Lagoon once or twice a year. He enjoys fishing in the Lagoon. He is an avid bird-watcher who enjoys looking for osprey and hawks in particular. Mr. Fullman often walks by the site proposed for the Project and enjoys the natural scenery and wildlife that populates the Lagoon and the Aquatic Preserve. He frequently visits the Causeway Park adjacent to the Project site to observe the scenery and wildlife and to picnic with his family. In his practice as a family therapist, Mr. Fullman occasionally takes clients to the Causeway to view the Lagoon and the Aquatic Preserve because they provide a pleasant setting conducive to productive therapeutic discussion. Mr. Fullman plans to remain in his home. He is concerned that the Mooring Field, if installed, will affect his continued enjoyment of his property, cause an increase in vehicular traffic and traffic safety hazards on the route he takes to and from his home daily, limit public parking on the parkway he frequents for recreation and professional purposes, and cause harm to the Lagoon and Aquatic Preserve environmental resources important to him and his family. Mr. Fullman learned of the Department's intent to issue the permit through counsel and authorized counsel to request an extension of time to file a petition for a formal proceeding on his behalf. Mr. Burgess was "taking the lead on keeping in touch with DEP," tr. 714, but Mr. Fullman did not have a formal arrangement with Mr. Burgess regarding securing an extension of time for the filing of an administrative hearing. The Department issued an Order on April 5, 2011, that granted "a request made by the Petitioner, Joe Burgess, to grant an extension of time to file a petition for an administrative hearing." The Order extended the time for the filing to April 14, 2011. The Order did not mention Mr. Fullman. On April 14, 2011, a petition was filed with the Department on behalf of both Mr. Burgess and Mr. Fullman. Unlike Mr. Burgess, however, Mr. Fullman, had not been granted an extension of time for the filing of a petition on his behalf at the time the petition was filed. The County's Application The County submitted its application for the Permit and the Lease on December 24, 2009. The application was prepared by a consulting firm, Coastal Systems International ("CSI"), whom the County had hired to obtain the necessary approvals for the Project from the Department and the U.S. Army Corps of Engineers (the "Corps"). The Department acknowledged receiving the County's application in a letter to the County dated January 22, 2010. Beginning with a request for additional information ("RAI") included with that letter, the Department conducted a review process that included more RAIs from the County and from other State agencies. Nearly a year later, the Department notified the County by letter dated January 26, 2011, that the application had been deemed complete. After the application was deemed complete but before the Consolidated NOI (see, below) was issued, the County's consultant submitted additional information to the Department that included copies of documents submitted to the Corps in response to the Corps' requests for additional information. The additional information was overlooked by the Department and, therefore, was not incorporated into the Permit and Lease. During the review process, significant changes were made to the Project proposed by the application. For example, the configuration or "footprint" of the mooring field was made smaller than originally proposed and the number of buoys allowed was lowered. The dinghy dock was relocated and altered in design and materials. Additional terms and conditions were added to the operational requirements. The Project was modified to address the site specific conditions in the Preserve and the possible adverse impact of shading on seagrasses. (This included reduction and relocation of the Mooring Field, re- siting of the Dinghy Dock, and elimination of a proposed "wave attenuator.") The design of the Project considered the characteristics of the vessels that would use the Project, both in the Mooring Field and at the Dinghy Dock. On February 22, 2011, the Board of Trustees determined pursuant to rule 18-20.004(1)(b) that it is in the public interest to lease approximately 34.47 acres of sovereignty submerged lands to the County for 25 years for the Project. The amount of acreage to be leased is 25% less than what was originally proposed, consistent with the changes made to the Project during the review process. The Consolidated NOI, the Project Design and its Location On March 4, 2011, the Department issued a Consolidated Notice of Intent to Issue an Environmental Resource Permit and State Lands Authorization (the "Consolidated NOI") to the County. The Consolidated NOI authorizes the County to construct and operate a public mooring field within 34.29 acres of the Aquatic Preserve just south of the Jensen Beach Causeway. The proposed site of the Mooring Field is an area that was dredged for the filling of submerged lands to create the nearby west island of the Causeway. The general area of the Project is a busy waterway that has heavy boat traffic from the north, south, east and west. It is approximately 500 feet from the Intracoastal Waterway near the Intracoastal's intersection with the Okeechobee Waterway. The Project area is close to established upland facilities such as boat ramps, fish cleaning stations, a fishing pier, restrooms, picnic shelters, and public parking for cars and boat trailers, all maintained by the County on the west island of the Jensen Beach Causeway. The Causeway on its eastern end connects the mainland to a large, populated barrier island. On the mainland shore, several hundred yards west of the Project area is SunDance Marina, a commercial facility that offers fuel, repair, docking and other services for boaters. The facilities operated by the County, the marina, the local population and the heavy boat traffic in the area contribute to the per capita boat ownership in Martin County, among the highest for counties in Florida. Amenities in or near a county park at the west island of the Jensen Beach Causeway include 140-car parking spaces, 58 car/trailer parking spaces and a wooden viewing platform adjacent to the boat ramp on the south side of the Causeway. There is currently a small dock and a sandy beach along the causeway near the boat ramp along the south portion of the Causeway enjoyed by boaters while they also use the park facilities. Boaters would lose the use of the existing dock and the beach if the Project is constructed but would gain the benefits provided by the Project. The Causeway has a vertical concrete seawall parallel to the Project area. There is a section of the Causeway that connects to the shoreline, called a relief bridge that promotes flushing and circulation otherwise impeded by the Causeway. Prevailing winds are out of the southeast. Since the Lagoon is a large, open, water body, the wind traveling across it contributes to wave height which increases turbidity. At present, in the absence of a mooring field, approximately 20 vessels anchor in and around the Jensen Beach area at any one time. Many anchor in the shallow seagrass area and remain for extended periods of time. The anchoring is haphazard and poses a risk of scarring and otherwise damaging seagrass beds. The Project area has been plagued by dilapidated and sunken vessels. The County has removed seven of them recently, plus another three from nearby waters of the Aquatic Preserve. Dilapidated vessels pose the potential to leak hazardous materials, be navigational hazards and prevent seagrass growth, all of which can damage the Aquatic Preserve. The Project Area is not currently managed or maintained by the County. The Project is proposed as a management tool to encourage boaters to utilize mooring buoys located in an area where seagrass is either sparse or barren instead of anchoring in shallow seagrass areas where the boats may damage the seagrass. Known as the Jensen Beach Managed Mooring Field, the Project is authorized for 51 buoys permanently attached to helical mooring anchors drilled into the submerged bottom lands of the Preserve and a new Dinghy Dock on the south shore of the nearby west Causeway Island. The helical mooring anchor is approximately 12 inches in diameter and will be secured to the Lagoon bottom by hydraulic methods. The anchoring system contains a shock absorber designed to provide flexibility when a vessel is moored by allowing the vessel the ability to swing with wind and wave energy. This swinging mechanism reduces potential impacts to seagrass from shading. Vessels moored in a boat slip or at a marina do not have swinging capability. The anchors are designed to provide safe mooring withstanding winds up to 80 miles per hour. Removal of vessels is mandatory in the event of a Category One hurricane (74 miles per hour) or above. The Mooring Field will accommodate vessels from 20 to 60 feet in length. The Mooring Field will be open to the general public on a first-come, first-serve basis as defined in rule 18- 21.003(27). Furthermore, as a mooring field of buoys rather than a dock or marina with fixed boat slips, the waters of the Aquatic Preserve within the Mooring Field will remain open and accessible to public use by any vessels especially in the open, buoy-free lanes (or "Fairways") 75 feet wide. The fairways will bisect the Mooring Field in north-south and east-west directions and thereby create four quadrants in which buoys will be present. Permanent markers will mark the perimeter of the Mooring Field to provide notice of its existence. The Mooring Field will be operated by the County as a not-for-profit operation. A fee will be collected from users with the proceeds to pay for the County's management by a Harbormaster and for maintenance of the buoys, the Dinghy Dock and associated upland amenities available to the users of the Mooring Field. The design of the Mooring Field was determined by bathymetric depths taking into consideration the draft of the vessels that would occupy the field to ensure that there will be at least one foot between the draft of the vessels and the submerged bottom land. The depth inside the Mooring Field varies within a foot or so of 9 feet. The anticipated draft of the vessels entering the field will be 2 to 4 1/2 feet. Vessels traversing the field should not disturb the submerged land. In addition, 34.29 acres of sovereign submerged land in the Aquatic Preserve occupied by the Mooring Field, the Dinghy Dock will be 1,832 square feet and occupy .178 acres of the Preserve. It will L-shaped, with a 5' x 163.5' "access walkway" from shore out to a 5' x 203' "terminal platform" designed to allow temporary mooring of up to 18 small vessels. The access walkway at the Dingy Dock will be constructed from Fiberglass light-transmitting grates atop pilings and elevated as high as 6 feet above the water level. The terminal platform will float on the water in order to comply with requirements of the Americans with Disabilities Act for access by handicapped boaters. The Dinghy Dock is designed to ensure that environmental resources will not suffer impacts. It will connect to the bulkhead and existing riprap on the uplands. The pilings of the dock will be constructed of concrete. The slips will be 13 feet wide and 20 feet long and will accommodate a vessel up to 20 feet in length. A 20-foot vessel has a maximum draft of 2 to 2 1/2 feet. The water depth below the proposed Dinghy Dock's slips ranges from 7 to 10 feet. The Dinghy Dock's terminal platform will be located over an area with no seagrass or other submerged aquatic resources. Publication of Consolidated NOI On March 17, 2011, the County published the Department's Consolidated NOI in the Stuart News. Resources Located at the Site In the summer of 2010, Coastal Systems International, Inc. ("Coastal Systems") performed an inspection of the existing upland structures on the Jensen Beach Causeway west island and the submerged lands located southwest of the Causeway. "The surveyed area is the site of the proposed Jensen Beach Managed Mooring Field Project . . . ." MC Ex. 11. Three prior surveys had been conducted by Coastal Systems in the general Project area. In each of the surveys, in 2005, 2008 and 2009, "seagrass was observed along the mainland shoreline of Jensen Beach, west of the proposed Project area, and in the nearshore shoreline region of Jensen Beach Causeway, just north of the proposed mooring field." Id. at 2. Four species of seagrass were observed in the nearshore area: Manatee Grass, Shoal Grass, Paddle Grass and Johnson's Seagrass. Seagrass beds serve several functions important to the Aquatic Preserve. They stabilize sediments; entrap silt; recycle nutrients; provide shelter, habitat and substrate for animals and other plant life forms; are nursery grounds for fish and shellfish; and are important direct food sources for various species, including the endangered manatee. Many commercially important fishes spend at least part of their lives in seagrass beds. Coastal Systems submitted its Field Observation Report (the "Report") to the Department on July 16, 2010. The Report describes its purpose as follows: Id. The purpose of this inspection was to verify the previous marine resource survey of the submerged lands conducted in 2009 by Coastal Systems and to confirm the location, composition and density of marine resources, including the federally listed species Johnson's Seagrass (Halophila johnsonii . . .) . The Report concluded that consistent with the previous marine resource survey conducted in 2009, seagrasses were found in shallower portions of the survey area. The most extensive areas of seagrass "were observed in the immediate nearshore area along the southwest portion of the Causeway, the southwest quadrant of the survey area [different from the quadrants into which the Mooring Field is divided] and the southeast quadrant of the survey area (See sheet 5 in attachment 1)." MC Ex. 11, "Conclusion" at 3. Sheet 5 in Attachment 1 to the Report is entitled "Resources and Proposed Work" for the "Jensen Beach Mooring Field." It shows seagrass patches consistent with the description in the Report's Conclusion. Depicting the proposed Mooring Field divided by Fairways into four quadrants, Sheet 5 shows the two eastern quadrants to be barren of seagrass. Portions of the two western quadrants are shown to be sparsely inhabited by seagrass at a level of 1 percent or below. The northwest quadrant and the southwest quadrant are inhabited by seagrass at the 1 percent or below level. The area of sparse seagrass is no more than 10 percent of the northwest quadrant. In contrast, most of the southwest quadrant, at least 75 percent of its area, is shown to be inhabited by seagrass. The 2009 survey was confirmed in 2010 when the Report was prepared. Field work done both in 2009 and the next year in 2010 were done during the growing season when the seagrass, including federally-listed Johnson Seagrass, would be most prevalent and easily observed. The seagrass that was observed in the footprint of the Mooring Field was "paddle grass decipiens." Tr. 73. No Johnson Seagrass was observed within the footprint of the Mooring Field in either the 2009 survey or the field work done in July of 2010 during the growing season in advance of the Report. Fish and manatees feed in seagrass areas. They would likely feed in the areas of dense seagrass in the Project Area found outside the Mooring Field where the sediments consisted of shelly, sandy materials and where Paddle, Manatee and Johnson's Seagrass were identified. Macroalgae was present throughout the Project area in varying densities. The types observed included Common Caulerpa, Graceful Red Weed, Green Feather Algae, Hooked Red Weed, Spiny Seaweed, and Y Branched Algae. Macroalgae is a leafy algae and important marine resource. It provides habitat, shelter and food for various species in the Aquatic Preserve including the manatee and different fish species. Fish observed included Atlantic Spadefish, Gray Snapper, Gulf Pipefish, Leopard Sea Robin, Sheepshead, Southern Puffer and other unidentified juvenile fish. Other marine fauna observed during one field inspection included Amber Penshell, Blue Crab, Caribbean Spiny Lobster, Feather Duster Worms, Hermit Crabs, Horseshoe Crab, Hydroids, Lightning Whelk, Spaghetti Worms, Spider Crab and Sponges. The Project area is also habitat for various endangered and threatened species and species of special concern such as birds, reptiles and mammals, including the wood stork, manatee, Atlantic green turtles, and the saltmarsh snake. Wading birds such as the great blue heron and roseate spoonbill inhabit the area. The Florida Manatee uses the area and is known to feed on the types of seagrasses found there. Fish and manatees are unlikely to feed within the footprint of the Mooring Field because seagrass is either not present or extremely sparse. The Mooring Field's Footprint: Seagrass Opportunity The sediments within the mooring field are silty and muddy. Dependent on sunlight for growth, seagrass grows best in shallow areas of good water clarity that allows for sunlight penetration. Silty bottoms interfere with sunlight penetration whenever there is turbidity in the area that kicks up the silt. Seagrass is also more prone to grow in sandy sediments as opposed to silty or muddy sediments. Seagrass root systems hold fast in sandy sediments; they do not adhere well in silty sediments. The Mooring Field's sediment explains why its footprint is either barren of seagrass or inhabited by seagrass at such a sparse level. Nonetheless, the presence of seagrass within the Mooring Field indicates that seagrass has the opportunity to grow there, that is, at least in the parts of the two western quadrants of the Mooring Field which constitute seagrass habitat. Mr. Egan elaborated at hearing: [S]ince the footprint of the mooring area already contains sparse seagrass, that area which is within the footprint of the mooring field itself, though quite sparse now, could easily rebound in much thicker growth were water quality conditions to be good for it . . . . [T]o put a source of water quality impacts in close proximity to . . . the sparse seagrass fields . . . [eliminates] the opportunity for these seagrass beds to expand in an area where we have evidence to see that seagrass beds have been expanding. Tr. 859-60 (emphasis added). The impacts referred to by Mr. Egan are from shading caused by vessels moored in the four quadrants of the Mooring Field and the bioaccumulation in plants of toxic substances and biocides, like copper and zinc, that typically leach from the bottom paint of vessels. While Mr. Egan did not predict with certainty the impact of substances leaching from the bottoms of vessels in the Mooring Field, he was able to opine that in areas where circulation is reduced like the Project area because of the nearby Causeway, the levels of the toxic substances will increase and the plants and animals in the area can be expected to accumulate the substances to a degree that produces "a certain level of concern." Tr. 850. That seagrass beds are expanding in the Project area is evident from a comparison of images provided by the South Florida Water Management District between 2006 and 2009. They show a doubling of the seagrass beds on the side of the channel opposite the Mooring Field site. Whether such expansion will, in fact, occur in the Mooring Field footprint, however, were the footprint free of shading and toxic substances leached from boat bottoms, is speculative. The sediment would still remain silty and unlikely to provide a good basis for seagrass root structure. The Dinghy Dock The types of vessels that will most likely use the Dinghy Dock include johnboats, dinghies, and sailboats. The Project allows sufficient distance for boats to traverse the Mooring Field and gain access to the Dinghy Dock without encroaching on seagrass beds. The edge of the Dinghy Dock slip closest to the seagrass beds is approximately 25 feet away from the beds. Boater can avoid traversing marine resources whether seeking ingress or egress from their slips. Seagrass, moreover, is not likely to suffer impacts from vessels at the Dinghy Dock because there is a 7 to 10-foot depth under the slips. There is sufficient room between the Dinghy Dock and the Johnson's Seagrass. A small portion of the Dinghy Dock's walkway from the Causeway Island traverses a narrow band of nearshore seagrass. The access walkway is constructed of fiberglass grated decking material and is elevated 6 feet above high water to minimize the impact of shading. The grated decking allows sunlight to reach the seagrass when the sun is directly overhead. Keeping the walkway at a 6-foot elevation above high water allows light to penetrate under the walkway as the sun moves from east to west. The potential for impacts to seagrass from shading by the walkway is not significant. FWC and Archaeological/Historical Resources Florida Fish and Wildlife Conservation Commission ("FWC") recommended approval of the Project if two manatee conditions are added to the permit. The Department relies on FWC for its expertise related to impacts to endangered or threatened species and their habitats, including impacts to manatees or seagrass habitat. There are no archaeological or historical resources in the area. Resource Protection Areas Resource Protection Areas ("RPAs") are divided into three categories. The three categories are defined in rule 18- as follows: "Resource Protection Area (RPA) 1" - areas within the aquatic preserves which have resources of the highest quality and condition for that area. These resources may include, but are not limited to, corals; marine grassbeds; mangrove swamps; salt- water marsh; oyster bars; archaeological and historical sites; endangered or threatened species habitat; and, colonial water bird nesting sites. "Resource Protection Area 2" - Area within the aquatic preserves which are in transition with either declining resource protection are 1 resources or new pioneering resources within resource protection area 3. "Resource Protection Area 3" - Areas within the aquatic preserve that are characterized by the absence of any significant natural resource attributes. The existence of sparse seagrass in the footprint of the Mooring Field, the Johnson's Seagrass, and the dense seagrass beds nearby are indicia that the Project area is within a Resource Protection Area 2. Water Quality and the Management Plan Adverse impacts to water quality caused by haphazard anchoring will be eliminated when boaters instead use the Mooring Field. The Mooring Field will enable boaters to secure their vessels to mooring buoys instead of dropping anchors into the substrate. Anchors hitting bottom cause turbidity. Vessels anchored to the substrate are a continual source of turbidity because the anchor can move back and forth with the wind or water current. Impacts of turbidity from prop dredging when boats anchor in shallow areas would also be reduced because the Mooring Field is in deeper water. The Project will enhance water quality in the Jensen Beach area through the implementation of the Jensen Beach Management Plan (the "Management Plan"). The Management Plan is a list of best management practices. The provisions most significant to water quality enhancement include: 1) all vessels must pump out their septic tank waste within 24 hours of entering the Mooring Field and every three days thereafter; 2) all major repairs are prohibited; 3) the scraping of a vessel's hull is prohibited; 4) throwing trash overboard is prohibited; 5) cleaning a vessel is prohibited; 6) throwing anchor in the leased area is prohibited; and 7) all vessels are required to be operational. The Mooring Field and the Dinghy Dock will be regulated and managed by a harbor master under the plan. The harbor master is responsible for the day-to-day operations of the Mooring Field under the Management Plan. For example, if there is an illegal discharge, the harbor master is charged with notifying FWC so that it can conduct enforcement. The Board of Trustees proposed a lease condition that requires vessels to contain their graywater in onboard holding tanks so that it will not be discharged into the Aquatic Preserve. (Graywater is not potable and not contaminated with sewage but has been used, for example, dishwashing water.) Tierra Consulting Group, Inc. performed the water quality analysis at the Project site. Its findings indicate that water quality in the area meets water quality standards. Flushing in the area is adequate due to strong currents and the relief bridge which assist in offsetting the effects of the Causeway's presence. The Permit addresses water quality during the construction phase by implementing a turbidity management plan. The turbidity plan requires a curtain to be deployed during construction. The curtain will prevent water quality violations from occurring outside the curtained area during construction. The curtain will protect seagrass and microalgae outside the curtain from the effects of turbidity. The County has also agreed to conduct post-construction water quality monitoring to confirm that water quality in the Project area has not been impaired by construction. Navigation The Project is located a safe distance from the Intracoastal, existing boat ramps, and the Sundance Marina. The Mooring Field design provides adequate distance between buoys to ensure that vessels will be properly spaced. The Fairways provide safe corridors for two vessels to pass each other in the Fairways. Board of Trustees Authorization The Project requires a lease because it involves placing mooring buoys over sovereignty submerged lands. The lease is required to be approved by the Board of Trustees and could not be delegated to the Department for two reasons: 1) it was deemed to be a matter of "heightened public concern"; and 2) it would result in the addition of 50 slips. The Board's approval was unanimous. The upland portion adjacent to the Project is owned by the Board of Trustees. The public interest benefits from the Project include enhancement to water quality in the Aquatic Preserve; the first- come, first-serve basis on which it is open to the public; accessibility to the upland public amenities for patrons; protection of seagrass beds; and removal of dilapidated vessels in the area. The Board of Trustees agreed to waive lease fees because all of the revenue the County collects associated with the Project will be used to operate and maintain the facility. There are approximately 19 mooring fields currently in operation on lands owned by the Board of Trustees. None is located in an aquatic preserve. Two are located in the National Marine Sanctuary in the Florida Keys. The Aquatic Preserve Management Plan that applies to the Project area is the 1985 Indian River Lagoon Management Plan. The Conceptual State Lands Management Plan also applies to the Project area. The Conceptual State Lands Management Plan emphasizes balancing the resources of aquatic preserves with public use and benefit of the preserves. Most Current Permit Drawing and Management Plan The Department's Consolidated NOI does not contain the most current permit drawings or the most current management plan. Changes to the drawings and the plan occurred after the Department deemed the application complete. The changes were submitted by County with the intention that they be included. The most current drawings were attached to a Response to an Army Corps RAI. These drawings should have been included in the Department's Consolidated NOI but were overlooked. The changes clarify the dimensions of the Mooring Field boundary and elevated the dinghy dock from 5 feet to 6 feet to allow for more light penetration for the benefit of the seagrass. The most current management plan (also attached to the Response to the Army Corp RAI and submitted by the County to the Department in a timely fashion) includes two revisions. First, it revises section 2.5.1 to require the harbor master to fill Mooring Field Quadrants 1, 2 or 3 ahead of quadrant 4. Quadrant 4 is the quadrant with the seagrass. The order of filling was prescribed to protect the sparse seagrass observed by Coastal Systems in Quadrant 4. Second, the Management Plan was revised to address waste management and marine pollution by adding section 2.7. It provides a schedule for Martin County's waste management vessel to pump out the septic tanks of vessels that use the facility. It specifies how often vessels should be pumped out and requires that information be provided to each patron on arrival. If authorized, the changes to the drawings and the Management Plan not included in the Consolidated NOI will not have to be reviewed by the Board of Trustees because the Department regards them to be "minor modifications." See Fla. Admin. Code. R. 62-343.100(1)(a). The County's Aspiration and Past Department Action The County seeks authorization for the Project in hopes for less adverse impacts from boaters anchoring in seagrass, traversing seagrass, and discharging wastewater, graywater and waste materials into the Aquatic Preserve. Prior to this case, the Department has not authorized a Mooring Field within an Aquatic Preserve.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department enter a Final Order issuing Consolidated Environmental Resource Permit and Sovereign Submerged Lands Lease, Department File No. 43-0298844-001 and Lease No. 430345996, to the County. It is also recommended that the Consolidated Environmental Resource Permit and Submerged Lands Lease incorporate the current drawings and revised management plan submitted by the County after the application was deemed complete. DONE AND ENTERED this 7th day of November, 2011, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of November, 2011. COPIES FURNISHED: Virginia P. Sherlock, Esquire Howard K. Heims, Esquire Littman, Sherlock & Heims, P.A. Post Office Box 1197 Stuart, Florida 34995-1197 Ronald Woodrow Hoenstine, III, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 David A. Acton, Esquire Martin County 2401 Southeast Monterey Road Stuart, Florida 34996-3322 Herschel T. Vinyard, Jr., Secretary Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Tom Beason, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000 Lea Crandall, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000
Findings Of Fact Petitioner, Florida Clearwater Beach Hotel, Inc., is the owner of Lots 1-5 and 49-52 at 490 North Gulfview Boulevard, Clearwater Beach, Florida. Lots 1-5 are located on the southwest corner of Baymont Street and Gulfview Boulevard and front directly on Clearwater Beach. They measure approximately one hundred feet in depth and one hundred forty-one feet at their widest point. Lots 49-52 lie immediately across the street from Lots 1-5 and are approximately one hundred feet south of Baymont Street. They form a square and measure one hundred feet on each side. Petitioner purchased the property in question in 1978. Prior to that time the two parcels of land enjoyed common ownership and a common development pattern for at least forty years. A twenty-two room facility presently sits on Lots 1-5 and is rented out as ten units. Lots 49-52 are used as a parking lot for the tenants and guests of the facility. The property is presently zoned CTF-28 (High Density Commercial Tourist Facilities), which provides for a complete range of motel/hotel developments. The major emphasis of the district is tourist oriented with a permitted maximum density of forty-two hotel or motel units per acre. Petitioner wishes to destroy the existing structure and replace it with a new rectangular-shaped facility containing approximately twenty-two motel or hotel units. Because of the need to comply with flood ordinances, it must be built on pilings or piers. The proposed new structure will consist of four living levels over grade level parking. Petitioner's property measures less than two hundred feet in depth; therefore, the maximum height of its proposed facility cannot exceed forty feet under existing zoning requirements. Other property owners whose lots exceed two hundred feet in depth may construct buildings not to exceed eighty feet in height. Under present plans, the proposed hotel will have a forty-four foot height, which will require a four-foot variance. Petitioner contends that the hotel cannot be built with smaller dimensions. It also contends that a vista or side setback on the northwest corner of the building is required since present plans call for a small portion of the building to project into the vista area. This is due to the north property line running at an angle to the south property line and the proposed building being rectangular in shape. This variance will be contingent upon the City vacating a right-of-way adjacent to Baymont Street, thereby giving Petitioner an additional twenty feet in which to build its new facility. The City opposes the application on the ground that all criteria necessary to grant a variance have not been met. It specifically points out that the problems encountered by Petitioner are not unique to Petitioner alone, but are hardships common to all area owners.
The Issue Whether Petitioner was the subject of an unlawful employment practice based on his disability by Respondent.
Findings Of Fact Respondent, Fresenius Medical Care, provides dialysis treatment to end-stage renal disease patients. During the time relevant to this proceeding, Respondent operated 11 clinics in the Northwest Florida and South Alabama area. The Florida clinics were located in Pensacola, Navarre, Destin, Fort Walton Beach and Crestview. The South Alabama clinic was located in Andalusia. “Dialysis” is the cleansing of the body of unwanted toxins, waste products, and excess fluid by filtering the blood of patients through the artificial membrane of a dialysis machine. Purified water and dialysate are used during the process. Dialysis treatment is necessary when a patient’s kidneys are inadequate or no longer capable of acting as a filter to remove waste and fluids from a patient’s blood. While the frequency of treatment can vary for each patient, patients typically received dialysis at Fresenius’ clinics three times a week for four hours. The treatment requires piercing the skin and blood vessel so that each patient is intravenously attached to a dialysis machine. Because dialysis involves piercing the skin and blood vessels, as well as the removal and replacing of a person’s blood, patients are at an increased risk of infection. In order to protect patients from infection, proper maintenance, testing, and sanitation of the equipment used during dialysis is of primary importance. As such, dialysis is highly regulated by state and federal agencies responsible for health, safety, privacy, and reimbursement for health care. In order to fulfill its obligations to its patients and regulators, Fresenius maintained a Code of Business Conduct that outlined policies and procedures which every employee was required to follow. These policies and procedures were based on federal regulations enforced by the Centers for Medicare and Medical Services (CMS). The Code required that maintenance, sanitation, and tests for contaminants be regularly performed according to the schedules established for such procedures. The Code of Business Conduct also required all of Respondent’s employees to maintain accurate and complete records. In particular, biomedical equipment technicians were required to maintain logbooks of all the maintenance and tests done on each piece of equipment used in the dialysis process. Documentation was required to ensure that state and federal reporting requirements for maintenance and testing on dialysis machines was done. Documentation of every task performed by a biomedical technician was also required for review by Respondent’s internal and external auditors. Failure to perform these functions could subject Respondent to fines and other government actions, including loss of its Medicare certification and a shutdown of its clinics. Respondent also maintained a “Continuous Quality Improvement” (CQI) program which was designed to review indicators of the quality of treatment Respondent’s patients were receiving. These quality measures were reviewed by a CQI committee. The CQI committee was an interdisciplinary team consisting of the Medical Director, the doctor responsible for overseeing the medical care provided in a clinic; the Area Manager, the person responsible for managing all aspects of a clinic’s operations; the Clinical Manager, the registered nurse responsible for nursing care and technical services at a clinic; and the Biomedical Technician, the person responsible for maintaining, sanitizing, and testing the dialysis equipment at a clinic. Periodic meetings were held by the CQI committee to review all aspects of dialysis at a clinic. The periodic meetings included a review of machine maintenance, machine sanitation, and culture tests done on dialysis machines at a clinic, as well as a review of logbooks maintained by the biomedical technician, if necessary. The periodic meetings also included a review of all adverse events and all patient incidents that occurred at a clinic. Additionally, to ensure quality dialysis services, all of Respondent’s employees received initial and annual compliance training, which addressed relevant changes to Respondent’s policies, as well as state and federal laws. Petitioner, David J. Normandin, was a certified Biomedical Equipment Technician and nationally certified Biomedical Nephrology Technician. Petitioner received extensive training as a Biomedical Technician, including training on national standards for nephrology technicians and national protocols for testing, maintenance, and documentation of these efforts. Additionally, Petitioner received both initial and annual on-the-job training from Fresenius regarding required maintenance, sanitation, and record-keeping responsibilities. Petitioner worked for Respondent on two separate occasions. Initially, he worked at one of Respondent’s clinics in North Carolina, where he was a Chief Technician. Later, Petitioner moved to Florida and was employed by Renal Care Group as a Biomedical Technician. Eventually, Renal Care Group was purchased by Respondent in April 2006. After the purchase, Petitioner remained employed with Respondent as a Biomedical Technician until his termination on February 6, 2008. As a Biomedical Technician, Petitioner was assigned responsibility for three clinics. Petitioner’s responsibilities included providing preventive maintenance, troubleshooting, repairing, cleansing, and disinfecting of the clinic’s dialysis machines and water treatment equipment. His responsibilities also required taking water cultures and testing the water systems to ensure that the equipment and water were free from bacterial growth and pathogens. Without such maintenance, sanitation, and tests, it was dangerous for a patient to be intravenously hooked up to a dialysis machine that had not been properly tested or maintained. Every patient with whom the dialysis equipment might come into contact would be affected. Indeed, the consequences of not performing required routine testing, sanitation, maintenance, and record-keeping tasks were serious. At Fresenius’ clinics, Biomedical Technicians worked independently and were assigned to specific clinics. However, Biomedical Technicians assigned to other clinics sometimes helped other technicians when needed to complete their required duties. Such help only occurred if the foreign technician was available and not busy with meeting responsibilities for their own clinics. Petitioner admitted that the other technicians were usually “slammed” with the work at their own clinics and not generally available to help at Petitioner’s clinics. Indeed, the evidence did not demonstrate that other qualified technicians were generally or routinely available to assist Petitioner in his job duties. Similarly, the evidence did not demonstrate that it was reasonable for Respondent to hire additional technicians to help Petitioner perform his job duties. Petitioner was required to provide a monthly summary or technical report to the CQI committee for each clinic to which he was assigned. As part of the report, Petitioner was required to self-report what maintenance and tests were completed, and what maintenance and tests remained to be completed at each clinic. Petitioner was also required to self- report if he was behind in the performance of his routine job duties so that help might be provided, if it was available. If Petitioner failed to properly report any compliance deficiencies, such deficiencies would not normally be discovered until the Regional Technical Manager, Todd Parker, conducted an internal audit of the clinic or an unannounced CMS survey was performed. When he was initially hired by Respondent, Petitioner was responsible for the clinics in Fort Walton Beach, Crestview and Andalusia. At times, Petitioner assisted in or was responsible for the maintenance of two additional facilities in the area. These additional assignments generally occurred when Respondent was understaffed or training new staff. However, by April or June 2007, Petitioner was only responsible for the three clinics in Fort Walton Beach, Navarre, and Destin. The evidence did not show that Petitioner was responsible for more clinics than any other Biomedical Technician. Joan Hodson was the Clinic Manager for Respondent’s Fort Walton Beach clinic. As of April 2007, Petitioner’s direct supervisor was George Peterson, who in turn reported to Mr. Parker. Joan Dye was the Area Manager. Petitioner testified that he informed his employer in 2003 that he had a bad back. Petitioner admitted that he continued to perform his job duties without significant difficulty. There was no evidence that demonstrated his complaints were more than ordinary complaints about a sore back or that such complaints rose to the level of or were perceived as a handicap by his supervisors. However, sometime in 2007, Petitioner was diagnosed with two herniated discs and began having difficulty keeping up with his job duties. In March 2007, Petitioner was the on-call technician for emergency calls from the clinics in the area. He did not respond to several calls from the area clinics. These clinics complained about the missed calls to Ms. Dye and Mr. Parker during the March CQI meeting in Pensacola. As a consequence, Ms. Dye and Mr. Parker called Petitioner into the office to discuss the missed calls and to address the issue that his work was falling behind. They asked Petitioner if there was a problem. At the time, Petitioner was not under any medical restrictions from a healthcare provider. Petitioner informed Ms. Dye and Mr. Parker that he was on medications for his back which caused him to sleep very deeply and not hear the phone ring when clinics called. He also told them that he was having a hard time keeping up with his work because of the pain from his back. As a result of the meeting, Petitioner was taken off “call” duty and was no longer responsible for responding to other clinics’ calls for assistance. Petitioner was also informed that he would be provided help when it was available so that he could catch up on his assignments. Additionally, Petitioner was asked to provide a doctor’s note concerning his back condition and any limitations he might be under due to his back. This meeting was the first time Petitioner informed his employer that he had a serious back problem. On April 24, 2007, Petitioner provided Respondent with a doctor’s note concerning his back. The doctor’s note stated that for two months Petitioner was not to lift over 30 pounds, and was not to engage in repetitive bending, stooping, or kneeling. Petitioner was released to full duty on June 24, 2007. This is the only doctor’s note Petitioner ever provided to Respondent. Importantly, these restrictions did not impair Petitioner’s ability to document all of the jobs he had performed or to accurately self-report when specific maintenance and tests were not done or were behind. On October 3, 2007, Mr. Parker performed a technical internal audit of the Navarre clinic which was assigned to Petitioner. At the time, Petitioner was responsible for the Navarre clinic. The audit revealed that Petitioner had performed no dialysis and end toxin testing for the clinic during the year. These tests were required to be performed every six months. Moreover, Petitioner failed to disclose to anyone that he had not performed these tests even though he had the opportunity to self-report during CQI meetings or at any other time. Again, Petitioner met with Mr. Parker and Ms. Dye. When asked to explain why the tests had not been performed at the Navarre clinic, Petitioner told Mr. Parker and Ms. Dye that he “did not know” he had to do them, and that he had simply “misunderstood” the requirements. Petitioner’s claim was not credible. His supervisors found Petitioner’s explanation to be suspect, since he had previously completed dialysis and end toxin testing at both Navarre and the other clinics he was responsible for. In a memo he later prepared as to why he had not conducted the tests, Petitioner wrote: “so much to do, so far behind.” Petitioner never mentioned his back as an excuse for why he had not performed the tests in his meeting with Ms. Dye and Mr. Parker. At the hearing, Petitioner admitted that he simply “forgot” to conduct the dialysis tests. Clearly, Petitioner’s failure to perform his duties was not related to his back. Similarly, his failure to self-report with any specificity was not related to his back. Ms. Dye instructed Petitioner to complete the test samplings for the clinic that day. Ms. Dye also instructed Petitioner to maintain samplings per the policies at all of his clinics going forward. Petitioner also was instructed by Ms. Dye that he had to immediately test all of the machines at the Fort Walton Beach and Destin clinics for which he was responsible. Petitioner asked Mr. Parker for assistance in catching up on the dialysis testing at the Navarre clinic. Mr. Parker came to the clinic and performed half of the tests, while Petitioner performed the remainder. In November 2007, Petitioner saw a surgeon for his back and, for the first time, was specifically informed by a physician that he would need back surgery. It was anticipated that the surgery would be performed sometime after the first of the year. Petitioner told his employer about his need for surgery. They encouraged Petitioner to do whatever he needed to do to take care of his health, and take any necessary time off. Petitioner chose to continue to work. A CQI committee meeting for the Fort Walton Beach clinic was scheduled for Thursday, January 24, 2008. Prior to the meeting, Joan Hodson, the Clinical Manager for the clinic, asked Petitioner to meet with her early in the morning to review the clinic’s dialysis culture logbook. Petitioner missed the meeting and arrived after noon, with no explanation. He told Ms. Hodson that all cultures were good. Later, at the CQI committee meeting, Petitioner reported to the Medical Director, Dr. Reid, that all the cultures looked good. In reviewing, the printout report for the cultures, Dr. Reid noticed that one of the samples was high and asked that it be redrawn. Petitioner told Dr. Reid and the committee that he had already performed a redraw. He left the meeting to go get proof of the redrawn results. Petitioner’s claim that he did not tell the committee that he had already redrawn the culture and had the results is not credible. Petitioner left the CQI meeting and never returned. Later, Petitioner admitted he had not redrawn the sample. He was instructed to redraw the sample immediately. The day after the CQI meeting, Ms. Hodson called Petitioner asking for the redraw results. Petitioner still had not performed the redraw claiming that he was “too busy.” He was again instructed to immediately perform the redraw. Ms. Hodson called Petitioner the following day, inquiring about the redraw, but did not receive a return call. That weekend, Mr. Parker also called Petitioner to ensure that the redraw was done or would be performed immediately. During the call Mr. Parker informed Petitioner of the seriousness of his failure to redraw the culture immediately as he had been instructed to do and the inappropriateness of his actions regarding the culture before, during, and after the CQI meeting. Mr. Parker also instructed Petitioner to call Ms. Dye about the redraw results. Petitioner again did not perform the redraw as instructed. Ms. Dye also left Petitioner a voicemail to call her about the redraw. Petitioner never called Ms. Dye back. Petitioner’s repeated and willful failure to comply with his supervisors’ instructions was not related to his back. On January 30, 2008, as a consequence of Petitioner’s failure, Petitioner was relieved of his duties for the Destin clinic. He was also given a written warning in a Corrective Action Form (CAF), based on the incidents from January 24, 25, 26, and 28, 2008. The CAF specified “Expectations for Change,” which identified problems with Petitioner’s performance. Ms. Dye reviewed the CAF with Petitioner and instructed him that these problems had to be addressed immediately. These expectations included: Perform all culture draws according to FMC Technical Manual and review this with the Clinical Manager. Immediately report any cultures that are outside the FMS limits and any redraws to the CM. . . . When Dave is at the clinic, he will be expected to redraw any culture that day, if necessary; At CQI monthly meetings, will ensure that all cultures are reported correctly and proper protocol is followed. A Technical CQI summary monthly report and a Spectra monthly summary culture report must be presented to the CM and MD for review and signature; Implement a basic monthly schedule and submitted to his CM’s by the 1st day of each month, will ensure that if he is not at a specific location according to his schedule, he will contact the CM or the Charge Nurse of that clinic to inform them of his location. If called or paged by any clinic, or a member of management, he must respond within 15 minutes from the time he received the call or page; Will follow a more systemic time schedule and will incorporate his time with his monthly schedule. Will make himself readily available to be present, if one of his clinics develops a problem in the early morning hours, if necessary; and When on-call, the 15-minute rule also applies. If not on-call, no matter which clinic calls, will return the call or page and assist the clinic, inform them who is on-call and/or attempt to resolve the problem over the phone. That same day, January 30, 2008, Petitioner received a Developmental Action Plan from Mr. Peterson. Five goals and an Action Plan were identified that Petitioner had to meet within time frames set during the next 90 days. Goals in the Plan included incorporating all of his monthly cultures into the FMC (Fresenius Medical Care) logbook and developing a basic monthly preventive maintenance culture and disinfect schedule for all facilities. By March 31, 2008, the Technical Manager would evaluate and review the goals accomplished by Petitioner to determine if further action was necessary. Petitioner admitted that although he had been obligated to self-report all of the deficiencies in the Corrective Action Form at the CQI meeting in January 2008, he failed to do so. Petitioner testified that he told Ms. Hodson that he was “very much behind” on performing his job duties. He also admitted that he never provided her with any specifics as to the tasks he had not performed. Additionally, he admitted that, “I don’t even know all of the things that I was behind on” and “I don’t know which [logbooks] I’m missing.” The internal audit at the Fort Walton Beach clinic and Petitioner’s actions regarding the redraw of the culture caused Ms. Dye to be concerned about the integrity of the job Petitioner was performing at all three of his clinics. Based on Petitioner’s lack of honesty with the CQI committee, Ms. Dye was legitimately concerned that Petitioner was covering up his failure to do his work and that the safety of patients was at risk. As a result, Mr. Parker performed an audit of the Fort Walton Beach clinic on February 6, 2008. The audit revealed that no dialysate cultures had been performed since October 2007; two out of 31 machines lacked proper documentation of any preventive maintenance having been performed; no preventive maintenance logs were available for the building maintenance and ancillary equipment; two new machines had no documentation; and no electrical and safety checks had been performed since April 2007. All of these tasks were required to have been completed by Petitioner, and Petitioner’s failure to complete them was a serious violation of his job duties. Indeed, these deficiencies placed the Fort Walton Beach clinic in immediate jeopardy of being fined and shut down by CMS. A shutdown would have left 80 of Respondent’s patients without dialysis treatment and placed them at risk for illness and possibly death. The audit also uncovered that the written summaries Petitioner had submitted to the CQI committee in October, November, and December 2007, and the verbal reports he had given to the committee at those monthly meetings, indicating that the preventive maintenance logs were up to date, were in fact incorrect. Again, Petitioner’s failure to document was a serious violation of Petitioner’s job duties and was not related to his back condition. By this time, Ms. Dye had legitimately lost all faith in Petitioner’s honesty. She suspected that Petitioner had falsified certain records because he could not produce various records when he was asked to produce them and only later did the requested records appear. In short, Petitioner’s supervisors had lost faith in Petitioner and could no longer trust him to self-report or to inform others when his duties were not being performed. On February 6, 2003, Ms. Dye presented Petitioner with a second Corrective Action Form, noting the issues generated by the internal audit and suspending Petitioner from work. The CAF was reviewed and signed by Petitioner. Based on what was discovered from the Fort Walton Beach clinic audit, Ms. Dye ordered an audit of Petitioner’s other clinics, Navarre and Destin. The same issues and deficiencies were discovered at those clinics: 1) the dialysate cultures at the Navarre and Destin clinics had not been performed since October 2007; 2) no safety checks had been performed on four out of 18 machines at the Navarre clinic, and none had been performed at the Destin clinic since July 2007; and 3) preventive maintenance was late on five machines at the Navarre clinic and six at the Destin clinic. The audit confirmed once more that Petitioner had misled the CQI committee members during the January CQI meetings for those clinics by not reporting in his written summary or verbal report any deficiencies. In addition, although Ms. Dye had instructed Petitioner just the week before to immediately perform dialysate cultures at all of his clinics, Petitioner had failed to perform any of those cultures and ignored the instructions of his supervisors. Petitioner was given a final Corrective Action Form by Ms. Dye on February 8, 2008. Ms. Dye reviewed the audit results with Petitioner, as well as the Corrective Action Form, which he signed. Petitioner was terminated the same day. Petitioner was fired after being on the Developmental Action Plan for one week because he had misled the CQI committee in his reports, failed to self-report the extent of the job duties he had not performed to the committee, and had not performed any testing of his dialysate cultures and electrical safety checks or reported that he could not perform those tasks. Such reporting was not related to Petitioner’s back condition. Moreover, misleading the CQI committee was not related to any back condition Petitioner had. Both were egregious and terminable offenses by Petitioner. After Petitioner was terminated in February 2008, he applied for unemployment compensation and for multiple jobs. He never informed any prospective employer that he was disabled or needed an accommodation. Once he ultimately had surgery in March 2008, Petitioner told Respondent that he was better and could work, and he asked for his job back. Eventually, Petitioner went to massage therapy school, obtained his license, and worked sporadically as a massage therapist. Prior to the hearing, Petitioner completed work as a team leader with the Census Bureau. These facts demonstrate that Petitioner’s back condition was not a handicap. There was no evidence that Petitioner was terminated for a handicap or a perceived handicap, and the Petition for Relief should be dismissed.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED: That the Florida Commission on Human Relations enter a Final Order dismissing the Petition for Relief. DONE AND ENTERED this 18th day of November, 2010, in Tallahassee, Leon County, Florida. S DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of November, 2010. COPIES FURNISHED: Richard N. Margulies, Esquire Jackson Lewis 245 Riverside Avenue, Suite 450 Jacksonville, Florida 32202 R. John Westberry, Esquire 7201 North 9th Avenue, Suite A-4 Pensacola, Florida 32504 Denise Crawford, Agency Clerk Florida Commission on Human Relations 2009 Apalachee Parkway, Suite 100 Tallahassee, Florida 32301 Larry Kranert, General Counsel Florida Commission on Human Relations 2009 Apalachee Parkway, Suite 100 Tallahassee, Florida 32301