The Issue Whether, in making a preliminary decision to award a contract for the subject services, Respondent acted contrary to a governing statute, rule, policy, or project specification; and, if so, whether such misstep(s) was/were clearly erroneous, arbitrary or capricious, or contrary to competition. Specifically, Petitioner challenges the evaluation of the past performance section of the responses to the procurement document. Also at issue is whether Respondent violated the Sunshine Law in deciding to reject Petitioner’s bid protest.
Findings Of Fact Stipulated Facts Respondent is an agency of the State of Florida and is the procuring agency in this proceeding. Petitioner is a not-for-profit corporation duly organized under the laws of the State of Florida. On September 21, 2009, the Department issued the subject RFP. The RFP sets forth the purpose of the procurement (on Page 1 of the RFP) as follows: Request for Proposals (RFP): A 36-slot Facility-Based Day Treatment Program as described in the Services to be Provided (Attachment I) in a Provider owner/leased facility in Circuit 11, Miami-Dade County. The provider shall provide the day treatment program for youth placed on probation, and youth transitioning back into the community who are referred for conditional release or post-commitment probation services. The provider shall design, develop, implement and operate an evidence-based, facility- based day treatment program with the capability to provide an after- school/evening component. Petitioner submitted a timely response to the RFP. On December 18, 2009, Respondent posted its Notice of Agency Action which indicated its intent to award the contract to PSF. On December 28, 2009, Petitioner filed a Formal Written Protest and Petition for Administrative Hearing (Petition) pursuant to Section 120.57(3), Florida Statutes (2009), and Florida Administrative Code Rule 28-110.004. Pursuant to the provisions of Section 120.57(3)(d), Florida Statutes (2009), representatives from Petitioner and Respondent met in an attempt to settle or to resolve the formal bid protest filed by Petitioner. Respondent's representatives at the January 13, 2010, meeting included Tonja W. Matthews, Amy Johnson, Paul Hatcher, and Shahin Iranpour. Petitioner's representatives at the January 13, 2010, meeting were Thomas Petersen and Jennifer Fiorenza. No public notice was given ahead of, and no minutes were taken at, the meeting between Petitioner's representatives and Respondent's representatives on January 13, 2010. Respondent's representatives briefly met separately after hearing from Petitioner to determine whether or not any further questions or information was needed from Petitioner.1 After January 13, 2010, and before January 21, 2010, Respondent's representatives Amy Johnson, Rex Uberman, and Paul Hatcher individually or collectively discussed Petitioner's Bid Award Protest with some or all of the Respondent's personnel present at the January 13, 2010, meeting with Mr. Petersen and Ms. Fiorenza. They ultimately decided to uphold Respondent's Notice of Agency Action (issued December 18, 2009) as to the subject RFP. No public notice was given of the proposed agency action, i.e., Respondent's intended decision to uphold its Notice of Agency Action as to the subject RFP, nor were minutes taken which recorded this intended action. In a letter dated January 21, 2010, Respondent notified Petitioner of its decision to uphold its decision to award to PSF and inquired as to whether Petitioner wished to proceed with a formal hearing before DOAH. Petitioner responded in the affirmative, Respondent forwarded the Petition to DOAH, and this proceeding followed. Past Performance Section XIX of Attachment B sets forth "General Instructions for Preparation of the Proposal." Subparagraph F of Section XIX (found at page 17 of 73 of Joint Exhibit 1) provides, in part, as follows: F. Past Performance - (Volume 3) The purpose of this section is for the prospective Provider to demonstrate its knowledge and experience in operating similar programs by providing information requested on Attachment C, part I, II, and/or III. Each prospective Provider shall limit the Past Performance section to no more than 15 pages. These pages shall include the information requested on Attachment C, Parts I, II, and/or III and all required supporting documentation. . . . Attachment C, Part 1, is a form styled "Data Sheet: Past Performance of Non-Residential Programs" (page 21 of 73 of Joint Exhibit 1). That form has column headings for the vendor to insert the required information as follows: "Program Name," "Contract Number," "Program Type," "Contract Begin Date," "Contract End Date," "Most Recent QA Performance Percentage Score," "Most Recent QA Compliance Percentage Score (if evaluated prior to 2007)," "Failure to Report," "Number of Completions during FY 2006-2007," "2006-2007 Recidivism Rate," QA Deemed Status." Each column heading has a footnote that clarifies the type information required. For example, a footnote explains that QA is a reference to Quality Assurance. The column headed "Program Type" contains a footnote (footnote 3) which sets forth the non-residential programs that qualify for evaluation under the category "Past Performance of Non-Residential Programs" as follows: 3. During the past year from the date of the RFP issuance, the program type (Supervision, Day Treatment, Conditional Release, Respite, Independent Living, Diversion, Juvenile Assessment Centers) for the majority of the time the Vendor operated the program. Footnote 3 explicitly sets forth Diversion Programs and Juvenile Assessment Centers (JAC) as programs that will qualify for evaluation under the category "Past Performance of Non-Residential Programs." Petitioner did not file a challenge to the specifications of the procurement document within 72 hours of its posting as required by Section 120.57(3)(b), Florida Statutes. The scoring criteria and methodology for Past Performance are set forth in the RFP. Petitioner and PSF only operate programs in Florida. The scoring at issue in this proceeding is that of "Part I - Evaluation for Past Performance in Florida". Under that category, a vendor could receive a maximum of 420 points. Paul Hatcher is Respondent's employee who evaluated the responses to the Past Performance section of the RFP. Petitioner is the current provider of the services being solicited by the subject RFP. In its response to Attachment C, Petitioner listed that program in the appropriate columns of Attachment C. The program operated by Petitioner was appropriately listed because it is categorized by Respondent as being a non-residential program. There is no contention that Mr. Hatcher failed to appropriately evaluate Petitioner's Past Performance. Petitioner was awarded a total of 268 points under the Past Performance category, Part I - Evaluation for Past Performance in Florida. In its response to Attachment C, PSF listed one diversion program and two juvenile assessment centers (JAC) as non-residential programs it operated in the State of Florida. One JAC did not qualify for evaluation because it had not been in operation for a sufficient period of time. Mr. Hatcher evaluated PSF's Past Performance on the basis of the diversion program and one of the two JACs. PSF was awarded a total of 312 points under the Past Performance category, Part I - Evaluation for Past Performance in Florida. Mr. Hatcher appropriately included the diversion program and the JAC program in his evaluation of PSF's Past Performance for Non-Residential Programs because Footnote 3 explicitly includes those programs as programs non-residential programs that qualify for evaluation.2 There is no contention that Mr. Hatcher failed to score PSF's Past Performance in accordance with the scoring criteria and methodology set forth in the RFP. The RFP provides that vendors who operate DJJ contracted non-residential programs in Florida can be awarded a maximum of 1905 points. Respondent awarded PSF the higher overall score of 1422.27 points. Respondent awarded Petitioner a score of 1327.34 points. Petitioner failed to establish that Respondent incorrectly scored the two responses to the RFP, and it failed to establish that Respondent incorrectly determined to award the procurement to PSF. Sunshine Law Section 120.57(3)(d)1., Florida Statutes, provides the following after a bid protest is filed: (d)1. The agency shall provide an opportunity to resolve the protest by mutual agreement between the parties within 7 days, excluding Saturdays, Sundays, and state holidays, after receipt of a formal written protest. The purpose of the meeting on January 13, 2010, between the employees of Respondent and the representatives of Petitioner identified above, was to provide Petitioner an opportunity to argue why PSF should not be awarded the procurement. The group of employees represented Respondent's legal counsel and representatives from Respondent's Probation Programs (headed by Mr. Uberman) and its Bureau of Contracts (headed by Ms. Johnson). The purpose of the meeting was to determine the factual and legal basis for Petitioner's bid protest. The group of Respondent's employees who met with Petitioner's representatives on January 13, 2010, did not vote either during the meeting or after the meeting's conclusion. A day or two before she wrote her letter of January 21, 2010, Ms. Matthews contacted by telephone Ms. Johnson to determine whether the Bureau of Contracts thought some action other than the award of the procurement to PSF should be taken. Ms. Matthews also contacted by telephone Mr. Hatcher, who represented the Probation Programs, with the same inquiry. Ms. Johnson made the decision that the position of the Contract division was to uphold the award to PSF. Mr. Hatcher, after consulting with Mr. Uberman, made the decision that the position of the Probation Programs was to uphold the award to PSF. In separate telephone calls the Contract division and the Probation division advised Ms. Matthews that the award to PSF should be upheld. Ms. Matthews thereafter prepared and sent the letter that advised the vendors of the DJJ's decision.
Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that the Department of Juvenile Justice enter a final order that denies Petitioner's bid protest and upholds the award of the procurement to PSF. DONE AND ENTERED this 1st day of December, 2010, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 1st day of December, 2010.
The Issue Whether the Miami-Dade County School Board's failure to disqualify Magnum Construction Management Corporation from bidding on Project No. A0746 pursuant to paragraph G. of the General Requirements of the Request for Qualifications issued in connection with the project was clearly erroneous, contrary to competition, arbitrary, or capricious.
Findings Of Fact Based upon the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: The School Board The School Board is a duly constituted district school board charged with the duty of operating, controlling, and supervising all free public schools in Miami-Dade County, including, among many others, Westview Middle School (Westview) and Miami Coral Park Senior High School. The Westview Project Westview is currently undergoing expansion, remodeling, and renovation work (Westview Project). The project is almost complete. Blanca Bazan is a School Board employee who serves as project manager on School Board construction projects. At all times material to the instant cases, Ms. Bazan has been the Project Manager on the Westview Project. LIVS and Associates (LIVS), an architectural and engineering firm, has been the Project Architect/Engineer (or A/E of Record) on the Westview Project since October of 1997, when it entered into a written agreement (which is still in effect) to assume such responsibility in return for a "lump sum" payment, plus additional fees (LIVS Westview Agreement). Paragraph III.G. of the LIVS Westview Agreement describes the "basic services" LIVS is to provide during the "construction phase" of the project. It provides, in pertinent part, as follows: The following are to be performed by the A/E [LIVS], and shall in all cases be in accordance with the requirement of the contract documents: OBSERVATION a.) The A/E shall provide construction administration of the Contract for Construction as set forth in this AGREEMENT and in the General Conditions of the Contract for Construction unless otherwise provided in this AGREEMENT. The A/E shall visit the site at least weekly or as appropriate to the stage of construction or as otherwise directed by the BOARD to become generally familiar with the progress and quality of the Work completed and to determine in general if the Work is being performed in a manner indicating that the Work when completed will be in accordance with the Contract Documents. As part of the A/E's basic services, the A/E shall conduct 120 on-site observation visits. A/E shall provide a report to the PM [Project Manager] . . . . On the basis of on-site observations as the A/E, the A/E shall keep the BOARD and Contractor informed immediately in writing of the progress or lack of progress and quality of the Work, and shall endeavor to guard the BOARD against defects and deficiencies in the Work. The A/E shall at all times have access to the Work, wherever it is in preparation or progress. * * * b.) . . . . A/E will enforce the faithful performance of Contract and assure that the Work has been or is being performed in accordance with the Construction Documents. . . . A/E will provide written notice to BOARD if it observes or has reason to become aware of any defect or non- conformance with the Construction Documents. CONTRACTOR'S SUBMITTALS The A/E shall review and evaluate samples, schedules, shop drawings, and other submissions for conformance with the design requirements of the Project, applicable codes and ordinances. . . . The A/E shall also prepare in a timely manner change order items, including the proper documentation for DOE transmittal. . . . * * * 4. QUALITY CONTROL The A/E shall make a reasonable effort to evaluate materials and/or workmanship for conformance with Construction Documents, evaluate quality control testing reports, advise the Construction Contractor and the BOARD immediately of any unacceptable materials and workmanship the A/E may discover and [e]nsure that the Contractor take appropriate action to remedy unacceptable conditions. * * * CERTIFICATION OF PAYMENTS The A/E shall review the Contractor's notarized requisitions for payment, the schedule of values, subcontractor partial releases and the Project schedule. The A/E shall determine the amount which in the A/E's opinion should be paid to the Contractor and shall recommend for [the] BOARD'S approval certificates for payments in such amounts. These certificates will constitute a representation to the BOARD, based on site observations by all appropriate Designated Specialists for architectural and engineering disciplines and on the data comprising the application for payment, that the Work has progressed to the point indicated. By recommending a certificate for payment consistent with the contract documents, the A/E shall also represent to the Board that, to the best of the A/E's knowledge, information and professional judgment, the quality of work is in accordance with the Construction Contract Documents, unless the BOARD has been notified to the contrary in writing. Prior to issuing certification for payment, A/E shall review the status of Contractor's Construction Documents and Project schedule and verify that the documents and/or schedules are up-to-date and accurate to the extent visual observation of construction will disclose. A/E shall also confirm that after the first application for payment, each subsequent application shall be accompanied by subcontractor partial lien release fully accounting for subcontractor payments due for the previous application. If the Construction Documents and Project Schedule are not up-to-date and/or accurate, A/E shall include in its certification for payment a statement that the Construction Documents and/or Project Schedule are not up-to-date. In such event, BOARD may, a.) hold an additional ten (10)% of amount then due Contractor until A/E verifies that the Construction Documents and/or Project Schedule are up-to-date and accurate, b.) refuse to process the partial or final requisition for payment, or c.) pay Contractor. . . . The A/E's certification is a representation by A/E to Owner that all required items noted herein are submitted and proper and serves as a recommendation for payment only. The A/E shall make every reasonable effort to process the Contractor's requisition for payment in accordance with the timelines[] established in the General Conditions of the Construction Contract. . . . * * * SUBSTANTIAL COMPLETION The A/E, upon written notification by the Contractor that the Work is substantially complete and ready for substantial completion shall promptly conduct inspection to determine the date or dates of substantial completion for the work. . . . c) Not Substantially Complete If A/E determines that the Work has not achieved Substantial Completion, A/E will notify Contractor in writing of the deficiencies within ten (10) days of the Inspection. FINAL COMPLETION AND FINAL PAYMENT Upon receipt of written notice that the Work is ready for Final Inspection and Acceptance and upon receipt of a final Requisition for Payment, or at completion of the thirty (30) day punchlist period, whichever is earliest, A/E, its engineers and other consultants, BOARD and Contractor shall participate in a walk-through to inspect the Work. At the conclusion of the inspection, the Work shall be determined to be as follows: Finally Complete If it determined that the Work has achieved Final Completion, final payment shall be made in accordance with the Contract Documents. Not Finally Complete If it is determined that the Work has not achieved Final Completion, A/E shall prepare a Final Completion Punchlist and Final Completion shall be achieved in accordance with the Contract Documents and such other consequences as allowed by contract and at law shall be employed. . . . After all Final Inspection Punchlist items have been completed, A/E will recommend to BOARD acceptance of the Project and make recommendations regarding Contractor's final payment request. . . . Paragraph X.B. of the LIVS Westview Agreement provides as follows: If for any reason, the A/E is unable to perform the services under this contract, the BOARD reserves the right to either name or approve the A/E selected to complete the performance of this AGREEMENT. The BOARD reserves the absolute right to recommend a successor A/E or terminate the services of the A/E.[3] Paragraph XII. of the LIVS Westview Agreement provides that "[t]he BOARD may terminate this AGREEMENT, with or without cause, at any time upon thirty (30) days written notice to the A/E." With LIVS' assistance, a Project Manual for the Westview Project (Westview Manual) was prepared in anticipation of the letting of the Contract for Construction of the project through a competitive bidding process. Included in the Westview Manual were the General Conditions of the Contract for Construction. Subsections 3.1.1, 3.3.1, 3.3.2, and 3.3.3 of these General Conditions read as follows: 3.1.1 Contractor is the person, firm or corporation authorized to do business in the State of Florida and properly licensed or registered for the work to be performed with whom a Contract has been made with the Board for the performance of the Work described in the Construction Documents. * * * Contractor shall supervise and direct the Work in a manner consistent with contemporary community standards. Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Construction Documents give other specific instructions concerning these matters. Contractor shall be responsible to Board for acts and omissions of Contractor's employees, Subcontractors and their agents and employees and other persons performing portions of the Work under the Contract and shall be responsible to A/E and Board for coordination and complete execution of the Work in accordance with the Construction Documents. 3.3.3. Contractor shall not be relieved of obligations to perform the Work in accordance with the Construction Documents either by activities or duties of A/E in its administration of the Contract, or by tests, inspections or approvals required or performed by persons other than Contractor. In or around 1999, the Contract for Construction of the Westview Project was awarded by the School Board to J.V. Construction Corporation (J.V.). As required by law and the terms of the Contract for Construction, J.V. executed and delivered to the School Board a payment and performance bond issued by The Hartford Fire Insurance Company (Surety). J.V. subsequently defaulted and its right to proceed under the Contract for Construction was terminated by the School Board, which called upon the Surety to fulfill the Surety's obligations under the payment and performance bond it had issued. As a result, the Surety "essentially step[ped] into the shoes of [J.V.]" under the Contract for Construction.4 The Surety thereafter contracted with MCM to act as a "completion contractor" and complete the work J.V. had begun under the Contract for Construction. The School Board was not a party to this contractual arrangement. The Completion Contract into which the Surety and MCM entered (which has been in effect since October 25, 2001) provides, in pertinent part, as follows: THIS COMPLETION CONTRACT (the "Contract") is effective the 25th day of October 2001 by and between The Hartford Fire insurance Company (the "Surety") and Magnum Construction Management Corp. (the "Completion Contractor"). RECITALS WHEREAS, J.V. Construction Corp. (the "Former Contractor") and THE SCHOOL BOARD OF MIAMI-DADE COUNTY, FLORIDA (the "Owner") entered into a contract (the "Original Contract") for the Former Contractor to furnish all labor and material and perform all work for the construction of an addition to the Westview Middle School Project No. A0670 (the "Project") in accordance with the terms and provisions of the Original Contract including all contract documents forming a part of the Original Contract; WHEREAS, as required by law and under the terms of the Original Contract, the Former Contractor and Surety made, executed and delivered to the Owner a Performance Bond, Bond No. 21 BCS AE 8081, and Payment Bond, Bond No. 21 BCS AE 8081 (collectively, the "Bonds"), each in the penal sum of $6,678,000.00; WHEREAS, the Owner has terminated Former Contractor's right to proceed under the Original Contract, and the Owner has called upon the Surety to fulfill its obligations as surety under the terms of the Performance Bond; WHEREAS, the Completion Contractor has submitted a proposal dated July 25, 2001, to the Surety to complete the Original Contract, and said proposal is incorporated herein . . . ; and WHEREAS, the Surety and the Completion Contractor desire to enter into this Contract under the terms and conditions hereinafter set forth. NOW, THEREFORE, the Surety and the Completion Contractor, for and in consideration of the mutual obligations and promises herein set forth, do contract and agree as follows: AGREEMENTS Contract Documents. The Contract to the Surety consists of the terms and provisions contained herein, including the proposal from MCM Construction to the Surety dated July 25, 2001, to complete the Original Contract . . . ; and the Original Contract, including all General, Supplementary and Special Conditions, drawings, specifications, forms, addenda and documents forming a part of the Original Contract and any modifications to the Original Contract, all of which are incorporated herein by reference and which are hereinafter referred to collectively as the "Contract Documents." The Completion Contractor hereby warrants that it has received and read all of the Contract Documents. Strict Compliance. The Completion Contractor shall be bound to the Surety by all of the terms and provisions of the Contract Documents, including administrative as well as technical provisions, and shall strictly comply therewith in all respects. Furthermore, the Completion Contractor shall be bound in the same manner and to the same extent that the Surety and the Former Contractor or either of them would be bound to the Owner under the Original Contract, including but not limited to the conditions or determinations by the Owner with respect to all work done thereunder. The Completion Contractor shall have no responsibility or liability for indebtedness incurred by the Former Contractor. * * * Work to be Performed. The Completion Contractor shall furnish and pay for all labor, materials, services and equipment and shall do everything else necessary to perform and satisfactorily complete the work of the Original Contract as required by the Contract Documents to the satisfaction of the Surety and the Owner in such manner as to fully protect and save the Surety harmless as to its liability to the Owner for the completion of the original Contract (The "Work"). Time for the Performance of the Work. . . . . Subject to allowable time extensions as provided under the terms of the Original Contract, if the Completion Contractor fails to achieve Substantial Completion as defined in the Original Contract in the time allowed by this Paragraph, the Completion Contractor is liable to the Surety for all liquidated damages assessed against the Surety for the Work under the Original Contract after 713 days from the execution of this Agreement by both parties. The Surety may withhold from the Completion Contractor payments which otherwise may be due to the Completion Contractor in an amount equal to the liquidated damages assessed by the Owner. Price. The Surety shall pay to the Completion Contractor and the Completion Contractor agrees to receive and accept Four Million, Seven Hundred Eighty Eight Thousand, Three Hundred ($4,788,300.00) Dollars (the "Price") as full compensation for the performance and completion of the Work as described in the Contract Documents. . . . * * * 9. Payment. As specified in the Original Contract, the Completion Contractor shall prepare, sign and submit to the Owner, on behalf of the Surety, a request for payment (the "Surety/Owner Requisition") showing the value of the work completed and the materials stored to date in accordance with the terms of the Original Contract. The Surety/Owner Requisition shall be based on the Original Contract price of the Former Contractor. The amount of the Surety/Owner Requisition as approved by the Owner and the Surety shall be due and payable to the Completion Contractor within seven (7) days after the Surety receives payment from the Owner. If the Owner refuses to pay the Surety for any reason related to the Completion Contractor's performance, nonperformance, or in any way related to the Completion Contractor's actions, the Surety shall have no obligation to pay the Completion Contractor until the Owner pays the Surety. In this event, the Surety shall only be obligated to pay the Completion Contractor whatever amounts are received by the Surety within seven (7) days of the Surety's receipt of payment from the Owner. In the event Owner refuses to pay Surety for any reason NOT related to the actions of the Completion Contractor, or its Subcontractors, Surety shall make payment to completion contractor, for all work in place as of the date of the payment application, within the timeframe set forth in the Original Contract for payment to the Original Contractor from the Owner. * * * B. In the same time frame as specified in the Original Contract, the Completion Contractor shall prepare and submit to the Surety a request for payment (The "Surety/Completion Contractor Requisition") based upon the amount of the Completion Contractor's price to the Surety. The Surety/Completion Contractor Requisition shall be based on the same percentages of completion (the value of the work completed and the materials stored to date (as the Surety/Owner Requisition.). The Surety shall pay the Completion Contractor for the Surety/Completion Contractor Requisition as specified in the immediately preceding paragraph. * * * Defects in Work. The Completion Contractor shall be responsible for any and all defects in the work performed or materials supplied by the Completion Contractor and/or any of the Completion Contractor's subcontractors or materialmen after the execution of this Agreement by both parties. Independent Contractor. Except as otherwise provided in this Contract and the Original Contract the Completion Contractor will be permitted to exercise the full prerogatives of a prime contractor, in prosecuting the work, including but not limited to the selection and classification of supervisors and workers, scheduling, determination of equipment and material requirements, and the establishment of work hours and work week including overtime. It is further understood and agreed that the Completion Contractor is an independent contractor in connection with all work to be performed by it pursuant to the Contract Documents. * * * The Completion Contractor as the Surety's Representative on the Project. The Surety shall be represented at the Project by the Completion Contractor. Prior to the issuance of the Notice to Proceed, the Completion Contractor shall name, and the Surety shall specifically authorize in writing an individual with the Completion Contractor to be its representative (the "Authorized Individual") solely for the purposes set forth in this paragraph. The Authorized Individual will represent the Surety in dealing with the Owner on day to day construction issues with respect to the Project. The Surety hereby designates the Authorized Individual to prepare and process pay requisitions on the Contract. However, the Surety will sign all pay requisitions submitted to the Owner. Payments from the Owner shall be made payable to the Surety and transmitted to the Surety . . . . * * * 17. Termination of Agreement. Termination for Convenience. This Contract may be terminated in whole or in part by the Surety at any time for the Surety's convenience, provided the Completion Contractor is given not less than ten (10) calendar days written notice of intent to terminate and an opportunity for consultation with the Surety prior to termination. . . . Termination for Cause. Should the Completion Contractor, at anytime, in the judgment of either the Owner or the Surety, refuse or fail to supply a sufficient number of properly skilled workmen or materials, tools, equipment, facilities, or supplies of a proper quality; or fail in any respect to prosecute the work with promptness and diligence; or interfere with or impede the work of others on the Project; or fail in the performance of any of its obligations under this Contract or under the Original Contract, and should the Completion Contractor fail within three (3) days after receipt of written notice from either the Owner or the Surety to remedy such default; . . . or disregard the instructions of the Owner or the Surety; or for any other cause whatsoever shall not carry on the work in an acceptable manner, the Surety may, in any such event, either terminate this Contract or may exclude the Completion Contractor and its employees and agents from the work without terminating this Contract. . . . Following the execution of the Completion Contract, the Surety's attorney wrote a letter, dated November 7, 2001, to Ms. Bazan, which read as follows: The Hartford is in receipt of your letter dated November 2, 2001, and has requested that we respond on its behalf. In response to your specific questions, please be advised of the following: The Hartford's authorized representative on the project is: Mr. Fernando Munilla MCM Corp. 6201 S.W. 70th Street Second Floor Miami, Florida 33143 The Hartford has also authorized Mr. Fernando Munilla to prepare and process pay requisitions on the project. However, the Hartford will sign all pay requisitions submitted to the School Board. Payments from the School Board shall be made payable to the Hartford Fire Insurance Company and transmitted to The Hartford at the following address unless and until the School Board is notified in writing of a different address: The Hartford Fire and Insurance Company Hartford Plaza-T4 Hartford, Connecticut 06115 Attention: Robert Griffith, Esq. Bond Claims Mr. Fernando Munilla shall have, on behalf of The Hartford, the authority to negotiate and sign change orders for extra work requested or required by the School Board (hereinafter "Change Order") without The Hartford's prior written approval, provided that the Change Order does not exceed $10,000.00 and that MCM requests and is given additional time to perform the Change Order. If the Change Order does exceed $10,000.00, or if MCM requests additional time but no additional time is given to MCM to perform the Change Order, then The Hartford's written approval is required to negotiate the Change Order and the final Change Order must be signed by The Hartford and not Mr. Munilla. If the total of the approved Change Orders exceeds the sum of $50,000.00, then The Hartford, and not Mr. Munilla, must approve in writing all additional or subsequent Change Orders regardless of the amount of each such Change Order. Mr. Munilla has no authority to negotiate deductive Change Orders, credits, backcharges or net deductions from the Original Contract of any nature whatsoever without The Hartford's prior written approval. Mr. Munilla has no authority to negotiate on behalf of The Hartford on any disputes between MCM and The Hartford. I trust this letter answers all of your questions. Please do not hesitate to contact me should you require any additional information or clarification. Since the effective date of the Completion Contract, LIVS, acting pursuant to the LIVS Westview Agreement as the School Board's A/E of Record on the Westview Project, has been inspecting and evaluating the work performed by MCM under the Completion Contract and verifying that work for which payment is sought (through the submission of pay requisitions by MCM on behalf of the Surety) has been completed in accordance with the requirements of the Contract for Construction. If a pay requisition is approved by LIVS, it is then sent to Ms. Bazan for her review and approval. If everything is in order, Ms. Bazan signs the pay requisition and then "run[s] it through the chain of command." When all the necessary signatures are obtained, the School Board makes payment to the Surety, which, in turn, pays MCM under the terms of the Completion Contract. MCM does not have any contract with the School Board in connection with the Westview Project. The payment it receives for the work it does on the project comes from the Surety (with which it does have a contractual relationship), not from the School Board. The School Board considers the Surety to be the Westview Project "contractor" (as evidenced by MCM Exhibit 19, which is an excerpt of an October 30, 2002, printout listing School Board construction projects).5 In the Statement of Contractor's Qualification that MCM submitted to the School Board in 2002 to obtain its Certificate of Contractor Prequalification for "General Contractor [W]ork" (which certificate was effective July 10, 2002, until July 10, 2003, and authorized MCM "to have under contract with the [School] [B]oard at any one time a total dollar value of work in the amount of $100,000,000.000 and maximum dollar value of each individual project in the amount of $40,000,000.00"), MCM stated, among other things, the following under "Contracts in Progress": PROJECT NAME: WESTVIEW MIDDLE SCHOOL- REMODELING & RENOVATION OWNER: Miami-Dade County Public Schools, Blanca Bazan (305)995-4538 ARCHITECT: LIVS and Associates CONSTRUCTION COST: $4,788,300 START/COMPLETION: 10/01 to 10/03 DESCRIPTION OF PROJECT: Addition, renovation and remodeling of an existing middle school with very stringent phasing requirements and time frames. The project consists of three phases. The first phase is a new building with classrooms and a media center, as well as a new parking lot. The second phase consists of the renovation and remodeling of a one-story building with a courtyard, classrooms, locker rooms, band room, and shop class. The third phase is a two-story building with a parking lot, classrooms, auditorium and an immediate phasing that consists of remodeling a cafetorium during summer break. The remodeling and renovation includes: asbestos abatement, architectural, electrical and mechanical demolition. The Instant Project In or about July of 2002, the School Board issued a Request for Qualifications for Design-Build Firms for "State School 'MMM' 1600 Student Station Addition at: Miami Coral Park Senior High School (Project No. A-0746)" (RFQ). In a design-build project like the Instant Project (in contrast to the "traditional bid contract scenario"), the School Board enters into a single contract (with a design-build firm) for both the design and construction components of the project.6 In the Legal Advertisement that was part of the RFQ, the School Board announced that it "intend[ed] to pre-qualify three (3) to six (6) design-build firms to subsequently invite them to bid" on the Instant Project and further stated, in pertinent part, the following: Firms and companies desiring to participate in the design-build pre-qualification process shall submit an original qualification proposal and eight copies . . . . * * * If the applicant is a joint venture, an executed copy of the joint venture agreement must be submitted with the application. Percentages of participation of fees must be clearly stated for each joint venture partner. Only one submittal will be accepted per applicant, either as a single prime or as part of a joint venture. Firms or companies desiring to participate in this contract must have been pre- qualified by the Board, in accordance with Board rule for Pre-Qualification of Contractors for Educational Facilities Construction, prior to submitting their proposal for this advertisement. . . . The General Requirements portion of the RFQ provided, in pertinent part, as follows: In order to be considered, proposers must meet the following basic requirements: * * * A pre-proposal conference will be held . . . . Attendance is highly encouraged. This will be the only opportunity to present questions regarding the proposal. Written questions may be forwarded to Mr. Ivan M. Rodriguez, R. A., . . . and said questions will be answered at the pre-proposal conference. Questions and answers will be distributed to attendees. Proposers must be authorized to do business in the State of Florida and must possess all required registration, certification and licenses (including design and construction) in accordance with all applicable Florida Statues, ordinances, regulations, and/or Board Rules. A joint venture, including a joint venture composed of qualified business organizations, is itself a separate and distinct organization that must be qualified in accordance with Board Rules and Florida Statute 489.119(2)(c). Proposers must have been in business for a period of no less than five years. In the event of a joint venture or a newly formed company, at least one of the entities of the joint venture or principal of the newly formed company must have been in business for a period of no less than five years. Any proposer, firm or company desiring to participate in this process must not have as a part of its team an A/E firm presently under contract with the Board for a specific project and a General contractor for the same project. The Board considers this a conflict of interest and such proposals will not be considered for award of a contract under this Request for Qualifications. * * * M. MDCPS reserves the right to reject any proposal, to waive technicalities, or to accept the proposal that, in its sole judgment, best serves the interest of Miami-Dade County Public Schools. * * * Failure to file a protest within the time prescribed in §120.57(3), Florida Statutes, shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Any questions concerning this RFQ should be directed to the Department of A/E Selection, Negotiations & Design Management; attention, Mr. Ivan M Rodriguez, R. A. Director at . . . . The Pre-Qualification Process portion of the RFQ provided, in pertinent part, as follows: Intent: To pre-qualify between three (3) to six (6) design-build firms to subsequently invite them to bid on the following project: State School "MMM" 1600 Student Station Addition @ Miami Coral Park Senior High School (Preliminary estimated Construction Cost- $17,473,890) 8865 S.W. 16th Street, Miami, Florida 33165 Project No.: A0746 The selected proposer will be placed on a list of qualified bidders for bidding on design-build services for the above project. * * * C. Pricing The selected proposers will be allowed to bid the above listed project[], under a competitive bid process, based on design criteria established by a Design Criteria Professional under contract by MDCPS. The Evaluation/Scoring Process portion of the RFQ provided, in pertinent part, as follows: All proposers will be evaluated based on information presented in their submittals, utilizing the Board approved "Procedure[] for [] Selection of Design-Build Firms" dated January 5, 1994 (Updated March 10, 1999) . . . . The "Procedure[] for [] Selection of Design-Build Firms" referenced in this portion of the RFQ provided, in pertinent part, as follows: I. SELECTION PROCESS: INTENT To select Design-Build firms for bidding on each DCPS Design-Build project identified. Selected proposers will be placed on a list of qualified bidders for bidding on each DCPS Design-Build project as advertised. SCHEDULE: Dates for the items listed below shall be projected and become part of future Request for Proposals (RFP) advertisement. Board Review Mailing Advertisement Proposal Submittal Deadline Evaluation Interviews Bid on Design-Build Projects Award of Design-Build Project * * * PRICING: Selected proposers will be allowed to bid each Design-Build project identified under a competitive bid process. * * * EVALUATION/SCORING PROCESS: All proposers will be evaluated based on information presented in their submittals . . . . SCORING The evaluation/scoring process will be conducted in two steps. First, staff shall evaluate all factors in the Initial Screening section of Form-1 . . . . Second, the Selection Committee shall evaluate all factors contained in the Interview section of Form-1 . . . . The evaluation/scoring process shall be as follows: INITIAL SCREENING All proposers will undergo an initial screening process conducted by staff where they will be evaluating the proposer[]s' qualifications. The proposers will be evaluated by staff utilizing Form-1 . . . ; maximum score in this category is 115 points. Proposers that do not comply with the RFP will not be accepted and shall be duly notified. INTERVIEWS All proposers that comply with the RFP shall be contacted to schedule interviews by the Selection Committee. The Proposers will be evaluated by each of the members of the Selection Committee utilizing Form-1 . . . . The maximum score in this category is 115 points. RANKING Both the initial screening score and the interview score will be added, and the sum of both scores will determine the ranking of all proposers. The highest and lowest of the seven (7) total scores for each proposer will be dropped, and an average taken of the remaining five (5), to determine total score and ranking. Three (3) or more firms will be selected as eligible to bid on the project advertised. The Board shall have the right to make exceptions to this procedure when valid public emergency conditions warrant. INSTRUCTIONS FOR USE OF DADE COUNTY PUBLIC SCHOOLS DESIGN-BUILD SERVICES SELECTION-FORM 1 * * * INITIAL SCREENING (115 POINTS TOTAL) From the proposer's response to the RFP, staff will objectively evaluate the firm's abilities in accordance with those criteria listed below (Scores for each applicant will be based on comparison with all other applicants): * * * C. ARCHITECTURAL ENGINEERING DESIGN (30 POINTS): Submit General Services Administration Standard forms 254 (one for each discipline) and 255 (one for entire team), which best describes the proposed architectural/engineering design team. . . . * * * INTERVIEWS After the proposers have been evaluated based on their written applications, they will be invited to make a presentation to the Selection Committee on their approach to perform Design-Build projects for DCPS. . . . * * * The Submittal Requirements portion of the RFQ provided, in pertinent part, as follows: Note: Please refer to Pages 4-9 of the "Procedure[] for [] Selection of Design- Build Firms" attached hereto as Exhibit "C" of this RFQ, for additional information on the following items: * * * E. Architectural/Engineering design- Submit Forms 254 and 255 for A/E team members only. Identify the architect's experience in design-build, the A/E team's experience with DOE codes, MDCPS design criteria/standards, master specifications, educational specifications and furniture, fixtures and equipment. Describe the A/E team's design coordination and quality control systems. * * * P. State of Florida licenses (design and construction)- Provide current copy of State of Florida registration and licenses for proposer and all its professional consultants. * * * R. Contractors Pre-qualification Certificate- Provide current copy of MDCPS Contractor Pre-qualification Certificate. Proposers must have a valid certificate with a minimum of $17,473,890 single project capacity, in order to be considered. * * * The pre-proposal conference referenced in the RFQ was held on July 25, 2002. Attendees were given a written document which contained, among other things, the following questions (that had been submitted in advance of the conference) and answers (that had been given to these questions by "staff"): QUESTION Can an A/E firm presently under contract with the Board for a specific school project, join with the general contractor for the same school project and present a proposal. ANSWER No! The Board views this as a conflict of interest and will not consider such entities. QUESTION Can one firm submit two different proposals, one as a single prime firm and the other as part of a joint venture? ANSWER No! The legal advertisement is very specific to this issue and will only allow one submittal per applicant, either as a single prime firm or as part of a joint venture. QUESTION Can A/E firms presently under contract with the Board as term consultants participate in a design-build entity submitting a proposal? ANSWER Yes! Staff does not see any conflict with this situation. The Board, at their meeting of April 1994, has ruled that neither a direct nor an implied conflict exists. Question: Will there be a design evaluation at the time of bidding in determining the successful bidder? ANSWER No! The successful bidder will be determined based on the bid process. All bidders are to comply with the design criteria bidding documents. However, during the selection process, we will be evaluating the design approach to this project. Question: The RFP [sic] requires the applicant to be authorized to do business in the State of Florida as a design-build entity; however, when we called the State there is none available. What do we do? ANSWER You must comply with all State requirements including required registration and licenses (Design & Construction) in accordance with Florida law. It is your responsibility to comply. MCM was among those that submitted a qualification proposal in response to the RFQ (MCM's Qualification Proposal). MCM's Qualification Proposal was accompanied by a cover letter, dated August 1, 2002, from its President, Jorge Munilla, which read, in pertinent part, as follows: MCM is pleased to submit our qualifications to provide Miami Dade County Public Schools with Design-Build Service for State School MMM * * * MCM has substantial experience with the Design-Build process as it relates to constructing educational facilities. We have assembled a team of professionals that will deliver the quality and cost efficiency required by Miami Dade County Public Schools. The team includes: PJB Associates, who[] will provide architectural services; Bliss & Ny[i]tray, [who] will supply structural engineering requirements; Fortin, Leavy, Skiles, Inc., [who] will provide civil engineering services; LIVS [and] Associates,[7] [who] is providing mechanical, electrical, plumbing and fire protection consulting expertise; and the talented firm of Rosenberg Design Group, [who] will provide Landscape Architecture design. It is significant that our team members have all participated in Design- Build projects for Miami Dade County Public Schools and therefore are acquainted with the unique relationship which it necessitates. The MCM Design-Build team will deliver the cost effective construction, timely delivery, and quality design goals that are required by Miami-Dade County Public Schools. The information that follows this letter details precisely how the MCM team will satisfy these project objectives. * * * MCM's Qualification Proposal contained a Proposer's Profile, which provided, in pertinent part, as follows: TOTAL NUMBER OF YEARS IN BUSINESS MCM Corp. is confident that our team, if selected for this project, will execute the contract and deliver functionally effective facilities in concert with M-DCPS staff. The project team and our organization are structured in such a manner as to provide clear-cut lines of communication and accountability. . . . MCM Corp. has learned that a critical factor in the achievement of project goals is the selection of a project team that has the technical knowledge and experience to deliver. The following lists the principal occupation of each member of the design- build team, their occupational license number, and the number of years they have been engaged in that practice. Team Members License Years in Business MCM Corp. General Contractors CG C023834[8] 19 PJB Associates, P.A. Architects AA 0003085[9] 5 Fortin, Leavy, Skiles, Inc. Civil Engineering 3653 19 Bliss & Nyitray, Inc. Structural Engineering 674 39 LIVS Associates MEP EB 0004134[10] 17 Rosenberg Design Group Landscape LA 0000143 31 Also included in MCM's Qualification Proposal were Standard Forms (SFs) 254 (Architect and Related Services Questionnaires) for PJB Associates, P.A. (PJB); Fortin, Leavy, Skiles, Inc. (Fortin); Bliss & Nyitray, Inc. (Bliss); LIVS; and Rosenberg Design Group (Rosenberg); and an SF 255 (Architect and Related Services Questionnaire for Specific Project) completed by PJB as MCM's proposed Project Architect (or A/E of Record). Under the arrangements that had been made, if MCM were the successful bidder on the Instant Project, it would enter into an agreement for design services with PJB and PJB, in turn, would retain the services of Fortin, Bliss, LIVS, and Rosenberg (as sub-subcontractors/sub-subconsultants on the project, having no direct contractual relationship with MCM) to assist it in fulfilling its contractual obligations to MCM. The SF 254 for LIVS was filled out by Hector Vergara, the partner that is "in charge of all [the firm's] mechanical work, and it lists the Westview Project as an "example" of the projects the firm has done in the "[l]ast 5 [y]ears." According the form, the "[c]ost of [LIVS'] [w]ork" on the Westview Project was $6,800,000.00 and the "[c]ompletion [d]ate (. . . [e]stimated)" of such work was "2003." The SF 255 reflected that Fortin, Bliss, LIVS, and Rosenberg would be "consultants" to PJB on the Instant Project in the "[s]pecialit[ies] of "[c]ivil [e]ngineering," "[s]tructural engineering," "[m]echanical/[e]lectrical/ [p]lumbing/[f]ire [p]rotection," and [l]andscape [a]rchitect[ure]," respectively, and it contained "brief resumes" of "key persons" from these entities who would be working on the project. Among these "brief resumes" were those of Mr. Vergara and Arnold Leon of LIVS, which indicated that they both had done work on the Westview Project. Among the other documents that were part of MCM's Qualification Proposal were the "job descriptions" and "resumes" of MCM personnel who would be assigned to the Instant Project, including Fernando Munilla (a principal of MCM), Alexis Leal (MCM's Vice President of Purchasing), and Riccardo Salani (an Estimator-Scheduler with MCM). Fernando Munilla's, Mr. Leal's, and Mr. Salani's resumes each listed the Westview Project as one of the projects on which they had worked. This was not the first design-build project solicitation of the School Board's to which MCM had responded. It had, "several months before," submitted a qualification proposal in response to the School Board's Request for Qualifications for Design-Build Firms for State School "FF,"11 which contained the same General Requirements, including paragraph G., as the RFQ in the instant cases. As in the instant cases, PJB was MCM's proposed Project Architect (or A/E of Record) on the State School "FF" project. TLC Engineering (TLC) was the original proposed MEP (mechanical/electrical/ plumbing) sub-subcontractor/sub-subconsultant. After MCM had submitted its qualification proposal, however, MCM and PJB wanted to replace TLC with LIVS as the proposed MEP sub- subcontractor/sub-subconsultant. When School Board staff (Ms. Bazan, Carlos Hevia of Capital Construction, and Ivan Rodriguez of the Department of A/E Selection, Negotiations and Design Management) were asked whether such a substitution could be made, they indicated that it would be "no problem."12 MCM therefore assumed, when it submitted its Qualification Proposal in the instant cases, that its proposing LIVS as an MEP sub- subcontractor/sub-subconsultant would not result in MCM's disqualification from further consideration pursuant to paragraph G. of the General Requirements of the RFQ, notwithstanding that LIVS was the School Board's A/E of Record on the Westview Project and MCM was the "completion contractor" on that same project (the identical roles LIVS and MCM had had at the time MCM was competing for the State School "FF" design- build contract). Following the review and evaluation of the qualification proposals that had been submitted in response to the RFQ in the instant cases, the School Board posted an "official interview schedule," on which the competing "design- build firms'" "initial screening scores" were announced. These scores were as follows: 105.50 for SBR; 103.50 for James Pirtle Construction Company (Pirtle); 98.00 for Betancourt Castellon Associates, Inc. (Betancourt); 93.00 for MCM; and 77.50 for the Beck Group (Beck). This "official interview schedule" also contained the following "notes": NOTE 1: Each firm must bring all equipment necessary to conduct its presentation. NOTE 2: The initial scores shall be cumulative to the interview scores. The final ranking for each firm shall consist of the initial score plus the interview score. NOTE 3: The following firm has withdrawn from the interviews: The Haskell Company Prior the first scheduled interview, Beck withdrew its proposal, leaving only four proposers to compete for award of the contract for the Instant Project. The determination was thereafter made to "pre-qualify" for bidding all of the remaining proposers without conducting the scheduled interviews. The evidentiary record does not reveal that anyone protested this "pre-qualif[ication]" decision; however, neither does it reflect that the School Board gave notice of the opportunity any adversely affected persons13 had to file such a protest and of the consequences of their not taking advantage of such opportunity. Following this "pre-qualif[ication]" decision, the proposers were provided copies of the Criteria Documents (or design criteria package) that had been prepared for the Instant Project. Volume I of the Criteria Documents contained, among other things, an Instructions to Bidders, a List of Subcontractors Form, Special Provisions for Compliance with M/WBE, General Conditions of the Design-Build Contract, and General Requirements. The Instructions to Bidders provided, in pertinent part, as follows: INSTRUCTIONS TO BIDDERS * * * The Instructions to Bidders, General Conditions of the Design-Build Contract, Special Conditions for Design-Build Projects and all other documents and sections, listed in the Specifications under the Bidding Requirements, apply equally to each Section and Division of the Specifications. All sections of the Criteria Documents are complementary and are part of the contractual requirements. 2.7.1 Board reserves the right to waive informalities and irregularities in a proposal, to reject any bid that shows omissions, alterations or additions not called for in the Criteria Documents and to reject any bid containing conditions or unauthorized alternate bids. * * * 2.8.1 A bid may not be modified, withdrawn or canceled by the bidder during the stipulated time period following the time and date designated for the receipt of bids and the bidder so agrees in submitting the bid. * * * 3.2.2 When notified by Criteria Professional, prior to or after Award of Contract by Board, the successful bidder shall meet with representatives of Board at MDCPS/DCP/DB "Kick Off" meeting. At that time, the successful bidder shall bring the Design Build Team whose work is highly crucial to the completion of the Work. . . . The List of Subcontractors Form contained the following directions: This list of subcontractors shall be submitted to the Section of Contract Management, 155, N.E. 15th Street, Miami, Florida, 33132, no later than the end of the second working day after award, i.e., for bids awarded on Wednesday, list shall be submitted by 4:30 p.m. on Friday. If the list of subcontractors is not submitted as requested, the Board may initiate action which will result in rescinding the award. Subcontractor as used herein shall be defined in Florida Statute 713.01(16)- Subcontractor means a person other than a material supplier or laborer who enters into a contract with the contractor for the performance of any part of such contractor's contract. For each subcontract listed below, the bidder shall name the subcontractor or list the bidder's firm if he/she proposes to do the work. The cost of work as quoted by the subcontractor shall be listed. If the name of a subcontractor is deleted or added, the owner shall be notified immediately along with the justification for the change. The Special Provisions for Compliance with M/WBE provides, in pertinent part, as follows: Subcontractor/Subconsultant- A person other than material person or laborer who enters into a contract with a contractor for the performance of any part of such Design Builder's contract. Design or other required consultant services contracted for, in the performance of this contract will be considered as a Subcontractor. . . . The General Conditions of the Design-Build Contract provided, in pertinent part, as follows: General Conditions of the Design Build Contract * * * 1.1.2 The Contract The Contract represents the entire integrated agreement between the parties hereto and supercedes prior negotiations, representations or agreements, either oral or written. The Contract may be amended or modified only by a Modification. The contract shall not be construed to create a contractual relationship of any kind (1) between the Board and a Subcontractor or Sub-subcontractor, or (2) between any persons or entities other than the Board and the Design-Build Contractor. The Contract Documents include the Criteria Documents and the approved Construction Documents. * * * 3.1.1 The "Design-Build Contractor" is the person, firm or corporation authorized to do business in the State of Florida and properly licensed or registered for the work to be performed with whom the Contract has been made with the Board for the performance of the Work described in the Criteria Documents. "Contractor" refers to a third party Contractor. * * * 3.3.2 The Design-Build Contractor shall be responsible to the Board for acts and omissions of the Design-Build Contractor's employees, Subcontractors and their agents and employees and other persons performing portions of the Work under the Contract and shall be responsible to the Board for coordination and complete execution of the Work in accordance with the Contract. * * * 3.3.6 The Design-Build Contractor shall enforce strict discipline and good order among its employees and other persons carrying out the Contract including its Subcontractors and Sub-subcontractors. . . . * * * 3.9.2 During the Construction Phase, the Design-Build Contractor shall employ a competent, full time, on-site Superintendent, the Design-Build Contractor's A/E of Record Representative, who participated at least fifty percent (50%) of his/her time during the Design Phase, and shall be on site at a minimum of 50% of the working hours of each week. An M/E/P coordinator and necessary assistants shall be in attendance at the job site during the performance of the Work. . . . The Design-Build Contractor's A/E of Record on-site Representative shall not be used for checking shop drawings. The Superintendent, the Design-Build Contractor's A/E of Record Representative, M/E/P Coordinator and the major Subcontractor's Superintendents shall be fluent in English. * * * 3.12.1 Shop drawing are drawings, diagrams, schedules and other data specifically prepared for the Work by the Design-Build Contractor or a Subcontractor, Sub- Subcontractor, . . . to illustrate some portion of the Work. The Design-Build- Contractor, Subcontractor, Sub- Subcontractor, . . . shall not use the Design-Build Contractor's A/E of Record contract drawings as shop drawings, but the Design-Build Contractor shall require these entities to produce and submit such documents independently. * * * 3.18.1 The Design-Builder shall negotiate a fair and equitable agreement with each of the Architect/Engineer consultants listed in the Design-Builder's response to the request for qualifications for this project. The Design-Builder may choose additional A/E consultants, for which prior written notice to Board shall be given, but shall not terminate or replace those A/E consultants originally designated without the prior written approval of the Board. When requesting termination or replacement of A/E consultants, the Design-Builder must submit the following items: Letter requesting written Board approval of the action, stating clearly the reason for such request and the proposed replacement A/E consultant(s). Signed and sealed or notarized release from the A/E consultant(s) being replaced or justification acceptable to the Board that such release is not obtainable. Federal Standard Form 255 and 254 of the proposed A/E consultant(s). Site specific professional liability insurance incorporating the proposed A/E consultant(s) in the policy. A hold harmless clause signed and notarized . . . . * * * 4.1.1 The Board's Representative (also referred to as the "Design Criteria Professional" or "DCP") will provide administration of the Contract as described in the Criteria Documents . . . * * * 4.2.6 The DCP will review and approve or take other appropriate action upon Design- Build Contractor's submittals, previously approved by the Design-Build Contractor's A/E of Record such as Shop Drawings, Product Data and Samples, for conformance with the information given and the design concept expressed in the Criteria Documents. . . . * * * 4.2.12 The Design-Build Contractor and Design-Build Contractor's A/E of Record shall provide DCP which will confirm completeness and correctness of same and forward to Board for Board's review and records, the written documents required by the Contract to be provided such as Warranties, Operation and Maintenance Manuals, as-built drawings, releases of claim and other documents required of the Contract. The DCP will process any pending Change Order requests and evaluate the assessment of liquidated damages, if any. Upon its determination that the Design-Build Contractor and Contractor[']s A/E of Record has fulfilled the requirements of the Contract, the DCP will issue a final Certificate for Payment. * * * A Subcontractor is a person or entity other than a materialman or laborer who enters into a subcontract with the Design- Build Contractor for the performance of any part of the Design-Build Contractor[']s Work. The term "Subcontractor" is referred to throughout the Contract as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term "Subcontractor" does not include a separate contractor (sometimes referred to as a "third party contractor" ) or subcontractors of a separate (third party) contractor. A Sub-subcontractor is a person or entity other than a materialman or laborer who enters in to a sub-subcontract with a subcontractor for the performance of any part of such subcontractor's contract. The term "Sub-Subcontractor" is referred to throughout the Contract as if singular in number and means a Sub-subcontractor or any authorized representative of the Sub- subcontractor. The term "Sub-subcontractor" does not include separate subcontractors of a third party contractor. All Subcontractor's shall be licensed and/or certified as required by the Florida Building Code and state statutes. Separate permits may be required including but not limited to electrical, plumbing, mechanical, and roofing work. * * * As stated in the Instructions to Bidders, the Design-Build Contractor shall furnish in its proposal to Board the list of Subcontractors, Sub-subcontractors and materialmen (including those who are to furnish materials or equipment fabricated to a special design) proposed for each principal portion of the Work . . . . If Board has a reasonable objection to any proposed Subcontractor, Sub- subcontractor or materialman, Board will promptly notify Design-Build Contractor. The Design-Build Contractor shall not contract with any proposed Subcontractor, Sub-subcontractor or materialman to whom Board has made a reasonable objection pursuant to Subparagraph 5.2.2. If Board has a reasonable objection to a Subcontractor, Sub-subcontractor or materialman, the Design-Build Contractor shall propose another to whom the Board has no reasonable objection. A Subcontractor, Sub-subcontractor or materialman may be added to the list of Subcontractors, Sub-subcontractor[s] or materialmen if required for performance of Change Order Work. A listed Subcontractor, Sub-subcontractor or materialman may be changed only upon written approval of the Board. The request to change shall state reasons for the request and shall be accompanied by a signed and notarized release from the listed Subcontractor or Contractor's Affidavit to Board that such a release is not obtainable. * * * The General Requirements include Procedural Requirements, Subsections 2.03 and 9.01 of which provide as follows: 2.03 DESIGN-BUILDER ("D-B") D-B shall appoint its D-B Project Manager which is D-B's representative for the Project. The collective management of D-B services, including D-B'[s] architect, engineers and other consultants, is to be vested in D-B Project Manager. D-B Project Manager is the representative of D-B and all communications are to be through him/her to DCP and M-DCPS Project Manager. D-B Project Manager's role does not preclude the involvement of D-B's architect, engineers and other consultants. The architects, engineers and other consultants with responsibility for different aspects of the Project are to attend appropriate meetings but this must be coordinated with D-B Project manager. 9.01 PRE-CONSTRUCTION CONFERENCE Prior to beginning construction, DCP (through PM) shall schedule a Pre- Construction Conference. Ten (10) days notice is required for the meeting. At minimum, the following parties shall attend: DCP Team (DCP) Design-Builder Team (D-B) PM Major Subcontractors Region Superintendent Principal BCC Representatives Testing Lab Consultant HVAC Test & Balance Consultant H. Others as applicable. * * * Section 01012 of the General Requirements discusses the Project Architect. It provides as follows: PROJECT ARCHITECT (Also referred as Architect/Engineer of Record or D-B'[s] A/E. The Project Architect (A/E of Record) is a Principal, Partner, Agent, Subcontractor or Employee of the Design-Builder,[14] and is the person lawfully licensed to practice Architecture and Engineering or an entity lawfully practicing Architecture and Engineering identified as such in the Contract; and is referred to throughout the Criteria Documents as is singular in number. The term Architect/Engineer of Record means the Architect/Engineer of Record or its authorized representative. Whenever the terms Design-Builder's A/E or A/E is used throughout the Criteria Documents, it refers to the Project Architect. DUTIES AND RESPONSIBILITIES OF THE PROJECT ARCHITECT The Project Architect shall have all the duties and responsibilities established under the applicable State Statutes regulating the professions of Architects and Engineers. The Project Architect shall employ a Project Manager and necessary assistants, and shall be responsible for managing all design and production of Design and Construction Documents and the coordination of its implementation during the construction. The Project Architect shall review and approve or take other appropriate action upon Subcontractor submittals, such as Shop Drawings, Product Data and Samples prior to their submittal to the DCP for approval. The Project Architect shall consult with the DCP concerning all items related to the design and production of the Construction Documents. The Project Architect shall be responsible for the preparation of the Record Drawings. Prior to Design-Builder's request for determination by DCP of substantial completion, the Project Architect shall determine, on his/her own, that the Project has achieved substantial completion. The Project Architect shall inspect the work and provide, through the Design-Builder, a punchlist of all items to be completed or corrected. Upon receipt of request for determination of substantial completion from the Design-Builder, the DCP shall proceed to determine if the work is ready for inspection as provided under the General Conditions. All four remaining proposers, MCM, SBR, Pirtle, and Betancourt, submitted sealed bids. The bids were opened on December 17, 2002, and subsequently tabulated. MCM had the lowest "base bid" ($17,673,600.00). SBR had the second lowest "base bid" ($18,037,446.00). Betancourt's and Pirtle's "base bids" were $18,269,000.00 and $19,540,000.00, respectively. Following the tabulation of bids, School Board staff recommended to the members of the School Board that the contract for the Instant Project be awarded to MCM as the lowest bidder. On February 6, 2003, SBR, through counsel, filed a notice of protest with the School Board, which read as follows: This firm represents SBR Joint Venture, who as you know, has submitted a proposal for construction of the above-referenced [p]roject [the Instant Project]. It has come to our attention that MCM Corp. ("MCM") who submitted a proposal to provide design build services for the above- referenced project, must be disqualified from further consideration in connection with an award of the Project due to MCM's failure to comply with general requirements as promulgated by the Miami-Dade County Public Schools relative to the Project. Specifically, item I G of the General Requirements mandates that: " Any proposer, firm or company desiring to participate in this process must not have as a part of its team an A/E firm presently under contract with the Board for a specific project and a General [c]ontractor for the same project." As disclosed by MCM in its proposal to construct the [p]roject, MCM is currently performing substantial work connection with another project known as the Westview Middle School-remodeling and renovation ("Westview"). The architect under contract with the School Board regarding the Westview Project is LIVS and Associates. In conflict with the qualification general requirements, MCM's proposal to construct school MMM contemplates the formation of a design build team which will include LIVS and Associates, as its mechanical, electrical, plumbing and fire protection consulting engineers. As such, the proposal by MCM is violative of the requirements of design/build firms in order to qualify for the Project. Back-up documentation including, but not limited to, material portions of the request for qualifications and disclosures by MCM are attached for your review. Under the circumstances, we respectfully request that MCM be disqualified from performing any services in connection with [p]roject and the second [lowest] bidder, which is SBR Joint Venture, be awarded the Project. MCM responded to SBR's notice of protest by letter dated February 10, 2003, in which it argued that SBR's protest was without merit and "should be dismissed" and further stated, among other things, the following: The Contract documents permit[] the board to waive all irregularities. If the board were to consider that Ivan Rodriguez, Carlos Hevia and Blanca Bazan[15] misspoke on behalf of MDCPS when they approved LIVS as part of the MCM Design Build team, and or if the board were to consider the inclusion of LIVS as part of the Design Build Team as a conflict, then if that be the case, by this letter MCM hesitantly tenders substitution of LIVS (who has graciously agreed), with SDM Consulting Engineers, Inc., who is also fully qualified, has had extensive experience with DCPS and has agreed to take on the challenge. The members of the School Board were scheduled to vote at their February 12, 2003, meeting on staff's recommendation to award the contract for the Instant Project to MCM, but the "item [was] tabled" because of the pendency of SBR's protest. At the meeting, the School Board Attorney told the School Board members that he had "reviewed [SBR's] protest with staff and [they had] come to the conclusion that [they did not] agree with [SBR's] position," explaining, in part, as follows: The language [of paragraph G. of the General Requirements of the RFQ] is interpreted that if you have the A/E and the general contractor, who are under contract with the board on the same project, that is considered a conflict. In this particular instance, you have a third element here. One, is that the bonding company took over this project and the bonding company brought MCM in as a subcontractor, if you will, a completing contractor here in this particular instance. So, it was never the intent of this language to cover a situation other than one where you had both the A/E and the general contractor under contract with the board. Construing the language of paragraph G. of the General Requirements of the RFQ (which is not clear and unambiguous on its face) as not "cover[ing] [the] situation" present in the instant cases is not at all unreasonable. Because it has a contract with the Surety and not the School Board, MCM is not the Westview Project's "General contractor"16 as that term is typically used in the construction industry.17 Since there is no language manifest in the proposal/bid solicitation documents in evidence which compels the conclusion that, for purposes of the solicitation, this accepted industry meaning of the term was not intended, it is entirely appropriate to rely on this meaning and find, as did School Board staff, that MCM's role in the Westview Project does not disqualify its proposal from consideration under paragraph of the General Requirements of the RFQ.18 Moreover, even if it could not be reasonably disputed that MCM was the Westview Project's "General contractor" within the meaning of paragraph G. of the General Requirements of the RFQ (which, as noted above, is not the case), MCM's proposed use of LIVS on the Instant Project would still not, under every reasonable interpretation of the paragraph, create a "conflict of interest" of the type the paragraph prohibits. It is not beyond reason, particularly when the provisions of the Criteria Documents are considered19 (most significantly, Subsection 3.18.1 of the General Conditions and Section 01012 of the General Requirements), to conclude that an "A/E firm" on the design- build "team," within the meaning of paragraph G., does not refer to an entity, like LIVS, that is neither the design-builder seeking the contract for the Instant Project, a member of such a design-builder (where it is joint venture or partnership), the design-builder's proposed "Project Architect" as described in Section 01012 of the Criteria Documents' General Requirements (who is also referred to therein as the "Architect/Engineer of Record" or "A/E"), nor any other Architect/Engineer consultant with whom the design-builder intends to contract in accordance with the requirements of Subsection 3.18.1 of the Criteria Documents' General Conditions, but rather is merely a proposed MEP sub-subcontractor/sub-subconsultant (that is, a third-tier contractor). The evident purpose of paragraph G. of the General Requirements of the RFQ is to avoid a situation where a firm acting as the School Board's A/E of Record on another School Board project let under the "traditional bid contract scenario" is inclined to deal with the "General contractor" on that project in a lax manner compromising the School Board interests because of a relationship the firm has with that "General contractor" on the Instant Project.20 The chance of this happening if the firm were merely a third or lower tier contractor on the Instant Project would be remote, so remote that it is reasonable to believe (as John Pennington, the School Board's Director for Construction Compliance, who was "intimately involved in making [the language in paragraph G.] the final language," credibly testified) that it was not the School Board's intent, in including paragraph G. in the General Requirements of the RFQ, to eliminate a potential competitor based on this possibility.21 Had the School Board intended otherwise, it could have made its intent clear and unmistakable by having the first sentence of paragraph G. read as follows: "Any proposer, firm or company desiring to participate in this process must not propose to have working on the instant project in any capacity, including as a third or lower tier contractor, both a firm that is presently serving under a contract with the Board as the Board's A/E of Record on another project and a firm that is a General contractor for that same project." It did not do so, however. Instead, it used language in paragraph G. reasonably susceptible to the interpretation that, under this provision, proposing to use as an MEP sub-subcontractor/sub- subconsultant on the Instant Project a firm that is the School Board's A/E of Record on another project does not disqualify a proposer even if the proposer is the "General contractor" for that other project. Following the School Board meeting, SBR, on February 16, 2003, filed its formal written protest of the intended decision to award the contract for the Instant Project to MCM. On February 18, 2003, Fernando Munilla sent a letter to School Board member Dr. Marta Perez, which read, in pertinent part, as follows: MCM has been informed that unfortunately MCM's response to SBR's bid protest was not provided to you prior to the February 12, 2003, Board meeting. We enclose same for your ready reference. We respectfully request you inquire on the particulars raised in our letter, and if you agree with your staff's recommendation (that SBR's alleged irregularity in MCM's bid lacks [sic] merit), then we ask you move the Board to exercise its right to waive the alleged irregularity, as permitted by the bid documents under section 00100 page 4 subsection 2.7.1 in order that MCM continue to work on the project. On March 4, 2003, the School Board Attorney sent a memorandum to the Superintendent of Schools advising that upon further review of the matter he had changed his opinion and was now of the view that SBR's protest had merit, explaining in the memorandum as follows: This specification [paragraph G. of the General Requirements of the RFQ] prohibits a proposer from having as a part of its Design-Build team an Architect/Engineer (A/E) firm who is under contract with the Board for a specific project and General Contractor for the same project. The specification provides that the Board considers this a conflict of interest and such proposals would not be considered for award of the contract. MCM submitted a proposal which has LIVS [and] Associates, an A/E firm under contract for the Westview Middle School project as part of its team. MCM is the General Contractor on the Westview Middle School project under a contract with the surety company to complete the project as the completing contractor. MCM contends that in view of the fact that they are the completing contractor and are not in direct contract with the Board for the project, this particular provision should not apply. We disagree. The particular specification in question does not specify or require that the general contractor for the same project be under contract with the Board. Conflict exists by virtue of the fact that the A/E, acting on behalf of the Board for the Westview Project, has to inspect and review the work of MCM and, with this proposal, will be in business with MCM on another Board project. Accordingly, MCM's proposal should not have been considered for award. While it is true that, in paragraph G. of the General Requirements of the RFQ, the School Board did not include the words "under contract with the Board" after "General contractor," if it intended that "General contractor," as used in paragraph G., have the same common meaning as the term has in the construction industry (and there is no language in the proposal/bid solicitation documents in evidence compelling the conclusion that it did not have such an intent), these additional words would have been redundant because, as noted above, a "General contractor," as that that term is typically used in the construction industry, is necessarily one who is "under contract" with the owner. Furthermore, contrary to the suggestion made by the School Board Attorney in his March 4, 2003, memorandum, under MCM's proposal, MCM and LIVS would not have a direct business relationship22; rather, LIVS would be doing business with PJB.23 While LIVS' participation (as a third-tier contractor) in the Instant Project with MCM may create a potential "conflict" for LIVS, this potential "conflict," at least arguably, is not the type that is prohibited by paragraph G. of the General Requirements of the RFQ. On March 11, 2003, MCM and PJB sent the following letter to the School Board: This letter will serve as our formal request to replace the engineering firm of LIVS originally selected for State School MMM [with] SDM Consulting Engineers in which MCM's architect of record, PJB Associates, P.A., had entered LIVS as their mechanical and electrical consultants for the above referenced project [the Instant Project]. Even though we consider LIVS to be an excellent engineering firm, d[ue] to an alleged conflict of interest that is said to exist, we are respectfully requesting replacement to prevent controversy.[24] We also request that you submit this to M- DCPS's Legal Department to verify if there is any conflict; and if so, we respectfully request a written reply. In the absence of a reply within the next three working days, we will assume that this issue has been resolved. Thank you in advance for your attention. Also on March 11, 2003, MCM, anticipating that it would not be awarded the contract for the Instant Project, sent the School Board another letter, which read as follows: This letter will serve as notice of the intent of Magnum Construction Management Corporation (MCM) to protest any decision of the Miami-Dade County School Board to reject all bids on the Miami-Coral Park Project. Based on information obtained to date, MCM will assert that the decision to reject all bids is based on the false assumption that under the terms of the Request for Qualifications, MCM was disqualified to bid on the Miami-Coral Park Project and that bids on the project were over budget. MCM will assert that it was qualified to bid on the project and that its bid was responsive and within the budget. MCM subsequently filed a formal written protest and an amended formal written protest. On March 12, 2003, the Design Criteria Professional for the Instant Project sent a letter to Ms. Bazan advising her that the three lowest bids submitted for the Instant Project "were within the budget of $17,473,891.36," and that the two lowest bids, those submitted by MCM and SBR, were "substantially below the State of Florida allowable cost per student station under the Smart Schools Clearinghouse." On March 26, 2003, the School Board referred SBR's and MCM's formal written protests to DOAH. A day later, it referred MCM's amended formal written protest to DOAH.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board enter a final order rejecting SBR's protest and awarding the contract for the Instant Project to MCM. DONE AND ENTERED this 1st day of August, 2003, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 1st day of August, 2003.
The Issue Whether Petitioner failed to secure worker’s compensation coverage for seven employees who worked from February 28, 2006, to March 3, 2006, in violation of Chapter 440, Florida Statutes, and whether, as a result, Petitioner should be assessed a penalty in the amount of $1,115.52.
Findings Of Fact Respondent, Department of Financial Services, Division of Workers’ Compensation ("the Division"), is the state agency responsible for enforcing the statutory requirement that employers provide workers' compensation coverage for their employees. Subsection 440.107, Florida Statutes (2006). Petitioner, Boudreau Concrete, Inc. (BCI), was, at all relevant times, an employer and engaged in concrete construction work in Florida. John Cipyak is a vice president with Builders Plus, a Boynton Beach Company hired to work on a Westview Office Building Site, in Port St. Lucie, Florida. Builders Plus subcontracted with BCI to perform pre-concrete form carpentry work at the site, including construction of the foundation and panels into which the concrete slab would be poured. Near the end of February 2006, Mr. Cipyak told Mr. Boudreau that the Westview project was falling behind schedule and that BCI needed more laborers on the job. Mr. Cipyak testified that Mr. Boudreau specifically agreed that his company, BCI, would hire sufficient additional manpower and would not use subcontractors. That agreement was not reduced to writing. In response to the need for additional laborers, the Division claims that BCI violated the applicable statutes and the insurance code by hiring seven carpenters, who worked at the Westview site from February 27, 2006, through March 3, 2006, as employees of BCI without providing workers' compensation insurance coverage for them. The seven carpenters are Dimas Zelaya, Francisco Figueroa, Gerardo Nava, Hector Sevilla, Jeremias Martinez, Carlos Quevedo and Jesse Hernandez. BCI claims that the seven carpenters were employees of a subcontractor, J. A. J. Construction Company, owned by Jose Alfredo Jiminez, and that Mr. Jiminez, BCI believed, carried the required workers' compensation insurance. The arrangements to have the additional workers on the project were made during a telephone call between Mr. Boudreau, Mr. Jiminez and Mr. Zelaya, who got the other six men to come with him and once they reported to the job, served as a translator for them. On March 2, 2006, Lynn Cornelius, a manager with Woodland Construction Company, Inc. (“Woodland”), sent an e-mail to Thomas Puglis, of the Division, listing the names of seven former employees of Woodland who had left Woodland’s employment, on February 24, 2006, to work for a subcontractor on another project. He named the same seven people who started work on the Westview site on the following Monday, February 27, 2006. On March 3, 2006, Mr. Puglis and Lieutenant Vance Akins, both investigators for the Division, visited the construction site where the seven former Woodland employees were working. With the assistance of an interpreter over the telephone, because no Spanish speaker was available for the site visit, the investigators instructed the seven workers to fill out Spanish language questionnaires for public works contractor licensing, provided by St. Lucie County. The investigators also tape recorded a statement from the only one of the seven men who spoke some English, Dimas Zelaya, during which, at best, he could be understood to have recognized and identified a picture of Mr. Boudreau. Lieutenant Akins telephoned another Division investigator Robert Barnes from the work site. Mr. Barnes testified that he telephoned someone who identified himself as Todd Freeman, a BCI employee, from whom he got the name of William Yocum of First Financial Employee Leasing, Inc., as the leasing company that provided workers' compensation coverage for BCI. Although he had no personal knowledge about where the seven carpenters were working from February 27 through March 3, 2006, Mr. Yocum noted that they were not covered on the policy for BCI and that the failure of BCI to report the names of all of its employees to the leasing company would violate the agreement between those two companies. Mr. Boudreau, on behalf of BCI, wrote a check dated March 10, 2006, to J. A. J. Construction Services, Inc., for $3860.00, with the notation "7 men - 2/27-3/3." BCI had no evidence of a written agreement with J. A. J. and the compensation to J. A. J. was solely for the wages earned by the carpenters. The Division's case is essentially based on the inference, without corroborating evidence, that Mr. Boudreau fabricated the subcontractor relationship and furthered that deception by writing the check after he knew BCI was being investigated for failure to secure workers’ compensation insurance. The Division based its assertion on the fact that Mr. Boudreau could not name the subcontractor during his first interviews by Mr. Barnes, saying that he was dealing with the subcontractor through Mr. Zelaya. The Division also presented evidence to demonstrate that the nature of the working relationship between BCI and the seven men was that of employer and employee, not independent contractors. That evidence was inconclusive. Although Mr. Boudreau kept their time sheets and personally supervised the work at the job site everyday from Monday through Thursday, with the assistance of Mr. Zelaya, as a translator, the carpenters brought their own tools and used materials and supplies provided by Builders Plus. The argument that J. A. J.'s role was administrative in nature is not convincing, since the same can be said of the leasing company, with which the Division asserted BCI should have obtained coverage. Mr. Barnes testified that he reviewed records of J. A. J., that someone from his office questioned Mr. Jiminez, and that they determined that the seven carpenters were not covered by J. A. J.'s workers' compensation policy during the time that they were working for Mr. Boudreau, based on some sworn statement made by Mr. Jiminez to the investigators. Mr. Jiminez did not appear as a witness in this case. The Division's investigator conceded that the Division did not determine whether or not the seven workers should have been on the J. A. J. policy. Mr. Zelaya testified that he spoke to Mr. Jiminez about getting more pay and understood that he would ". . . work with the license and insurance of Jose Jiminez. Mr. Boudreau was going to pay Jose and Jose was to pay me." Further, he stated that "Jose gets the workers, Jose makes a dollar off of the pay that we make. Mr. Boudreau was to give Jose a check, and Jose was to pay us, but Jose never paid us." Before he paid Mr. Jiminez, Mr. Boudreau requested and received from J. A. J. a workers' compensation policy, but that certificate of insurance was dated March 6, 2006, and did not appear to cover BCI for the prior week. At the same time, Mr. Boudreau added some of the workers to his own lease company policy, in an apparent attempt to continue the job, but was unable to do so after the stop work order was issued.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Division enter a final order rescinding the Stop Work Order and Order of Penalty Assessment, Amended Order of Penalty Assessment, and Second Amended Order of Penalty Assessment. DONE AND ENTERED this 8th day of June, 2007, in Tallahassee, Leon County, Florida. S ELEANOR M. HUNTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of June, 2007. COPIES FURNISHED: John M. Iriye, Esquire Department of Financial Services Division of Workers' Compensation 200 East Gaines Street Tallahassee, Florida 32399-4229 Mary Morris, Esquire Morris & Morris, P.A. 224 Datura Street, Suite 300 West Palm Beach, Florida 33401 Honorable Alex Sink Chief Financial Officer Department of Financial Services The Capitol, Plaza Level 11 Tallahassee, Florida 32399-0300 Daniel Sumner, General Counsel Department of Financial Services The Capitol, Plaza Level 11 Tallahassee, Florida 32399-0307
The Issue Whether Petitioner's protest, challenging Respondent's decision to award to Intervenor, "pending a successful interview," the "Federal Relations Governmental Liaison" contract advertised in Request for Proposal 99-01, should be sustained?
Findings Of Fact Gibbons and Company, Inc. Gibbons and Company, Inc. (Petitioner) is a Washington, D.C.-based firm, 1/ which was incorporated in December of 1993, and whose primary business is advising clients on matters of public policy before the United States Congress, the White House, and federal agencies. It also provides advice and counsel to multinational businesses on market access around the globe. Petitioner's President is Clifford Gibbons, who has been with the firm since its formation. Its Chairman of the Board is Sam Gibbons, Clifford Gibbons' father. Sam Gibbons joined the firm as its Chairman of the Board on January 4, 1997, 2/ after serving, with great distinction, for 34 years as a United States Congressman from Florida. Sam Gibbons was an effective and influential member of Congress. He was Chairman of the Ways and Means Committee and head of the Florida delegation (which, with 23 members, is the fourth largest state delegation). Before his election to Congress, he served ten years in the Florida Legislature (six years as a member of the Florida House of Representatives and four years as a member of the Florida Senate). As a Florida legislator, he played a key role in the passage of legislation that created the University of South Florida, Florida Atlantic University, and the University of West Florida. James Pirius James Pirius is a graduate of the University of Minnesota with a double degree in political science and journalism. After graduating from college, Mr. Pirius (who has a certificate to teach in the State of Illinois) taught eighth grade communications and social sciences for two years. The following two years, he taught at the National College of Education in Evanston, Illinois. In 1975, Mr. Pirius returned to Minnesota to become the Minnesota State Senate's Director of Public Information. In 1977, Mr. Pirius went to work for Minnesota Congressman Bruce Vento as Congressman Vento's executive assistant. He was responsible for managing the Congressman's Washington, D.C. office (which was located in the House of Representative's Cannon Office Building). He remained in this position for four years. After the United States Department of Education (U.S. DOE) was created, Mr. Pirius received a call from Richard Moe, Vice President Walter Mondale's chief of staff, who asked him (Mr. Pirius) to be on the team to "open up the Department of Education." Mr. Pirius accepted the offer and became the Director of Legislative Policy at the U.S. DOE. As the Washington, D.C.-based Director of Legislative Policy, a position he held from 1981 to 1987, his primary duties involved lobbying education issues in the United States Congress. 3/ He was one of the agency's three key lobbyists on Capitol Hill. 4/ Mr. Pirius left his position with the U.S. DOE to become the Washington, D.C./federal relations representative for the Florida Department of Education (Florida DOE). He was hired by then Florida Commissioner of Education Betty Castor (who subsequently became the President of the University of South Florida). Mr. Pirius was the Florida DOE Washington, D.C./federal relations representative from 1987 to 1995. For the first four years, he provided such representation as a state employee. From 1991 to 1995, he operated as a paid consultant. After leaving the employ of the Florida DOE and becoming a paid consultant, Mr. Pirius was hired to become a Vice President of APCO Associates (APCO), a Washington, D.C. public affairs/governmental relations firm. Mr. Pirius headed the firm's education practice. APCO's Chief Executive Officer allowed Mr. Pirius to maintain his Florida DOE consultant contract "separate from [his] work at APCO." Since 1995, Mr. Pirius has served (as a paid consultant) as the Washington, D.C./federal relations representative of the University of South Florida. Although he does have direct dealings with the President of the University, Betty Castor, his immediate supervisor is Kathleen Betancourt, the University of South Florida's Associate Vice President for Government Relations. Mr. Pirius has also represented in Washington, D.C. (as a paid federal relations consultant) the Indiana and Minnesota Departments of Education. The Association of Governing Boards of Colleges and Universities has also been among his clients. At present, Mr. Pirius is technically on leave of absence from APCO. On July 1, 1998, Mr. Pirius moved his office from APCO to his home at 7910 West Boulevard Drive in Alexandria, Virginia (which is in the Washington, D.C. metropolitan area, inside the Beltway). He has resided at this location since 1987. In rush hour, it takes 30 minutes (by automobile) to reach the Capitol from Mr. Pirius' residence/office. When there is not rush hour traffic, the trip takes 20 minutes. Mr. Pirius has an agreement to sublease space from Broderick and Associates in the Hall of States Building (which is presently unoccupied and being reserved for Mr. Pirius) should he receive the contract that is the subject of the instant controversy. In addition, Dr. Lynda Davis, the President of Davis, O'Connell, Inc., a government relations consulting firm, has verbally agreed to provide Mr. Pirius space in her firm's office in the Hall of the States Building should the Broderick and Associates space become unavailable. The Hall of States Building, which is located at 444 North Capitol Street, is one of the best office locations in Washington, D.C. inasmuch as it offers easy foot access to the Capitol. It houses the Washington, D.C. offices of many governors and state education agencies, and has an excellent reference library, which includes educational journals and materials. Mr. Pirius has been continuously registered as a lobbyist with the Clerk of the United States House of Representatives and the Secretary of the United States Senate since 1994. He is currently registered under his own name (with the University of South Florida identified as his client 5/) and as a member of APCO's lobbying team. Mr. Pirius began doing business as JCP Associates in 1992. JCP Associates is not an incorporated entity. Mr. Pirius, who operates as a sole proprietor, does business as JCP Associates only when he needs to hire others to assist him in fulfilling the requirements of a project. 6/ (He does so for accounting purposes.) A federal tax identification number has not been assigned to JCP Associates; however, Mr. Pirius uses his social security number when he does business under the name JCP Associates. No registration under the name JCP Associates has been made under the federal Lobbying Disclosure Act of 1995. Mr. Pirius discussed the registration of JCP Associates with the Clerk of the United States House of Representatives and the Secretary of the United States Senate offices. He was told that it did not make any difference whether he registered under his own name (which he has) or under JCP Associates. State University System The State University System (SUS) consists of the Board of Regents and the ten state universities. Board of Regents The Board of Regents is responsible for establishing SUS policy and overseeing SUS activities. Chancellor Herbert Dr. Adam Herbert is the current Chancellor of the SUS. He has been Chancellor since 1998. He succeeded Charles Reed, who served as Chancellor from 1992 to January of 1998. Prior to becoming Chancellor, Chancellor Herbert was the President of the University of North Florida for approximately ten years. Vice Chancellor Healy Dr. Thomas Healy is now, and has been since June 1, 1998, the SUS's Vice Chancellor for Governmental Affairs and Development. 7/ Before becoming Vice Chancellor, he worked at the University of North Florida for approximately 26 years; first as a faculty member (the first seven years) and then as an administrator. The last position he held at the University of North Florida was Vice President for Governmental Affairs. As the SUS's Vice Chancellor for Governmental Affairs and Development, Dr. Healy reports directly to Chancellor Herbert and serves as Chancellor Herbert's "general adviser" on matters relating to governmental affairs. Among his responsibilities is to coordinate the state and federal lobbying efforts made on behalf of the ten state universities. SUS Representation in Washington, D.C. A team of private firms and individuals (the Advocacy Group team), paid with foundation monies from the ten state universities, began providing the SUS with federal relations representation in Washington, D.C. in 1992. These firms included: George Ramonas' and Robert Mills' firm, the Advocacy Group, Inc. (the Ramonas/Mills firm), with which the SUS contracted to provide such representation; Dona O'Bannon's and Clifford Gibbons' firm, O'Bannon and Gibbons; and Tom Spulak's firm, Shaw, Pittman, Potts and Trowbridge (Shaw Pittman). Gibbons and Company, Inc., replaced O'Bannon and Gibbons on the SUS representation team upon the dissolution of the latter and the formation of the former in December of 1993. The foundation monies used to pay for SUS representation in Washington, D.C. were collected and paid to the Ramonas/Mills firm. The Ramonas/Mills firm, in turn, paid the other two firms (which had a contractual relationship with the Ramonas/Mills firm) for the services they performed and their expenses. The contract into which the Ramonas/Mills firm entered to provide SUS representation was the culmination of a procurement effort that started in or around April of 1992, when the following "Request for Information" was sent to "Washington Consulting Firms" by Dr. John Lombardi, the President of the University of Florida, acting in his capacity as the Chairman of the SUS's Washington Representation Review Committee: The Washington Representation Review Committee of the State University System of Florida is seeking information from consulting firms conducting business in Washington, D.C. This committee is comprised of four University presidents, representing the Council of Presidents of the State University System. Consultants who are interested in further discussion with the State of Florida's State University System should submit materials that demonstrate: Proven ability to represent institutions of higher learning, both in Congress and in agencies of the U.S. government, including: Working relationship with key leaders, committee members and staff within the U.S. Congress and the White House; Federal agency contacts and regular communication system that enhances capabilities in identifying and securing grants in specified research fields; Systematic approach to representing a statewide system that includes universities with differentiated missions. Ability specifically to represent each of the universities of Florida's public system. The Committee is comprised of President Frederick Humphries, Florida A&M University; Modesto A. Maidique, Florida International University; Dale W. Lick, Florida State University; and John V. Lombardi, University of Florida. Interested firms should submit a brief narrative describing the types of assistance they could provide and the associated costs of such services to the State University System of Florida and documentation as outlined above by May 31 to: Dr. John V. Lombardi Office of the President University of Florida Gainesville, Florida 32611 The Ramonas/Mills firm, joined by the other members of the Advocacy Group team, responded to this "Request for Information," and on or about June 22, 1992, made a written presentation to the Washington Representation Review Committee. The written presentation revealed that George Ramonas founded the "Advocacy Group" in 1991, and was the "Advocacy Group's" President. It also provided information concerning the backgrounds of Clifford Gibbons, Thomas Spulak, Dona O'Bannon, and Robert Mills. On or about November 1, 1992, the Ramonas/Mills firm, along with the other Advocacy Group team members, submitted a "Supplemental Response to Washington Representation Review Committee," which contained the following "background information on the Advocacy Group and Organizational Structure":
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board of Regents enter a final order denying Petitioners' protest of the Chancellor's decision to award the contract advertised in RFP to Mr. Pirius "pending a successful interview." DONE AND ENTERED this 17th day of September, 1999, in Tallahassee, Leon County, Florida. STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of September, 1999.
The Issue The issue is whether Petitioner is entitled to rescind a "second election" to invest in the Florida Retirement System (FRS) Investment Plan on the ground that, when filed, the second election failed to comply with the requirements of sections 121.4501(4)(g) and 121.021(17)(b), Florida Statutes (2012).
Findings Of Fact On August 9, 2004, Petitioner first became eligible to participate in the FRS. At the time, she was employed by Monroe County in its building department. On February 21, 2005, Petitioner timely elected to participate in the FRS Pension Plan, which is a defined benefit plan, rather than the FRS Investment Plan, which is a defined contribution plan. Petitioner participated in the FRS Pension Plan until the events described in this paragraph. Her last day of work was in June 2012, although she did not formally terminate her employment until December 6, 2012. At the time, Petitioner was experiencing health problems that Petitioner worried would prevent her from continuing to perform the duties of her job with Monroe County. In July 2012, Petitioner called the FRS financial guidance line and discussed transferring to the FRS Investment Plan, so she could withdraw funds to live on during a period of extended unemployment for health reasons. Even though Petitioner did not work after June, from November 1 through 6, she received pay for 13.25 hours of unused sick leave and 5 hours of unused annual leave. For the remainder of the month, Petitioner was on leave without pay. On November 29, Petitioner called the FRS financial guidance line to discuss again transferring to the FRS Investment Plan. An FRS representative warned her that, to make an election, she would have to be "employed with the FRS service credit" to make a second election. On the same day, Petitioner filed a second election with Respondent to transfer from the FRS Pension Plan to the FRS Investment Plan. In a form mailed on December 3, 2012, Respondent acknowledged receipt of Petitioner's second election, effective December 1, 2012. There is some dispute as to whether Respondent adequately advised Petitioner of any grace period to rescind her second election, but she did not attempt to do so until over three years had elapsed, as noted below. On April 5, 2013, Petitioner called the FRS financial guidance line and asked about withdrawing some of the funds in her FRS Investment Plan. She was informed that, if she did so, she could not defer compensation to this account on regaining FRS-covered employment. In September or October 2015, Petitioner obtained FRS-covered employment at the library of the City of Islamorada. On November 1, 2015, Petitioner called the FRS financial guidance line and asked about rescinding her second election. An FRS representative told her that she would have to submit a request for "intervention." On February 10, 2016, Petitioner filed a request for intervention, stating that no one had warned her that, if she withdrew any funds from the defined contribution account, she could not again defer compensation to this account. By letter dated March 4, 2016, Respondent denied the request solely on the ground that Petitioner had earned service credit for the month of November 2012 when she filed her second election, so, since she had not yet terminated employment, her second election was lawful.
Recommendation It is RECOMMENDED that Respondent enter a final order dismissing Petitioner's request for hearing on Respondent's denial of her request for intervention to allow her to transfer from the FRS Investment Plan to the FRS Pension Plan. DONE AND ENTERED this 29th day of September, 2016, in Tallahassee, Leon County, Florida. S Robert E. Meale Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 2016. COPIES FURNISHED: T. A. Delegal, III, Esquire James C. Poindexter, Esquire Delegal Law Offices, P.A. 424 East Monroe Street Jacksonville, Florida 32202 (eServed) Brian A. Newman, Esquire Pennington, P.A. 215 South Monroe Street, Second Floor Tallahassee, Florida 32302 (eServed) Ash Williams, Executive Director and Chief Investment Officer State Board of Administration 1801 Hermitage Boulevard, Suite 100 Post Office Box 13300 Tallahassee, Florida 32317-3300
The Issue At issue in this proceeding is whether Petitioner overpaid Respondent in the amount of $14,190.41 for the pay periods between July 10, 2009, and October 15, 2009, and, if so, whether Respondent should be required to reimburse Petitioner for those overpayments.
Findings Of Fact On October 16, 2008, Respondent signed an employment contract with FAMU to act as the coordinator of statistical research for the "Teachers for a New Era" ("TNE") initiative, a project funded at FAMU and other universities by a grant from the Carnegie Corporation of New York. Dr. Gwendolyn Trotter is the director of the Carnegie-funded portion of the TNE initiative at FAMU. The contract signed by Respondent was an "Administrative and Professional (A&P) Employment Contract." The contract stated as follows, in relevant part: This employment contract between Florida A&M University (FAMU) Board of Trustees and the below-named employee is subject to the Constitution and Laws of the State of Florida as constitutionally permissible, and the regulations, policies, and procedures of the Board of Governors and Florida A&M University Board of Trustees (BOT), as now existing or hereafter promulgated... An employee's contract may be non-renewed and/or the employee may be separated from employment as set forth in University Regulation 10.106, regardless of the above appointment dates. Employment will cease on the date indicated, and no further notice of cessation of employment is required for the following categories of employees: (1) employees holding visiting appointments; (2) those appointed for less than one academic year; or (3) those who are paid from contracts, grants, auxiliaries, or local funds. The appointment dates set forth in Respondent's employment contract were October 10, 2008, through June 30, 2009. The contract stated that Respondent would be paid at an "annual salary rate" of $55,000. The contract further stated that the amount to be paid to Respondent during his appointment period would be $39,615.00, and that Respondent's bi-weekly salary would be $2,107.27. Respondent was an employee "paid from . . . grants" for purposes of the cessation of employment paragraph of the employment contract, as set forth in the third inset paragraph of Finding of Fact 2, supra. Under the heading "Appointment Status," the employment contract stated, "Regular." FAMU Regulation 10.106 provides, in relevant part: The President or President's designee may choose not to renew the employment of Administrative and Professional (A&P) employees, including the Executive Service. The notice of non-reappointment or intention not to reappoint an A&P employee shall be in writing. On or before March 1st of each contract year, the President or President's designee shall notify any employee who will be non-reappointed. * * * A&P employees who are appointed to established positions with an appointment status modifier or type, other than Regular (for example, Acting, Temporary or Visiting) are not entitled to a notice of non- reappointment. A&P employees who are issued an employment contract with a clause providing that employment will cease on the date indicated and further notice is not required, are not entitled to the notice of non-reappointment referenced in this regulation.1/ FAMU Regulation 3.019, relating to delinquent accounts, provides in relevant part that FAMU "shall use due diligence and make every effort in the collection of all accounts owed to the University by employees, students, vendors and other parties." FAMU Board of Trustees Policy 2005-19 provides that FAMU will seek reimbursement for salary overpayments. Respondent testified that when he was hired for the coordinator of statistical research position, Dr. Trotter told him that the TNE project would last for two years, but that his initial employment period would be for one year with a second year contingent upon his initial performance. This testimony was plausible, credible, and not contradicted by any testimony or documentary evidence presented by FAMU. The written A&P employment contract signed by Respondent was not for one year, but for the period from October 10, 2008 through June 30, 2009. Respondent testified that the provost's administrative assistant explained that no contract could extend beyond the end of the current fiscal year on June 30, 2009, and that he would be issued a second contract to cover the period from July 1, 2009, through October 9, 2009. Respondent was never given a second written contract extending beyond June 30, 2009, nor was he ever given written confirmation of the terms that he said were communicated orally to him by Dr. Trotter. FAMU's associate director of payroll, Jacqueline Lester, testified at the hearing and essentially confirmed Respondent's testimony that the university does not issue contracts that extend beyond the current fiscal year. Ms. Lester stated that if an A&P employee such as Respondent is to work beyond the end of the current fiscal year, he will be issued a new contract that covers the carryover portion of his engagement. Ms. Lester further testified that if a new contract is not issued, then the employee is expected to stop work at the end of the current fiscal year. Respondent testified that he and Dr. Trotter found themselves at odds over research protocols, and that this disagreement completely fouled their professional relationship. Respondent stated that Dr. Trotter thereafter set out to humiliate and intimidate him, and to isolate him professionally from the other members of the TNE initiative. As the end of the fiscal year approached in June 2009, Respondent noticed that his fellow employees were receiving new contracts for the upcoming fiscal year. On June 29, 2009, Respondent sent an e-mail to Dr. Trotter inquiring as to the status of his contract. Dr. Trotter responded on the same date with an e-mail informing Respondent that TNE would "take on an extremely targeted direction for the coming year." The e-mail went on to state the following: I am in the process of working through contracts starting July 1, 2009. Your contract does end on June 30, 2009. Your 2008-2009 contracted pay was based on a 12-month pay scale. However, your contract started in September 2008, and ends June 30, 2009. I am working with Mr. Herbert Bailey in Academic Affairs to conclude contracts ending on June 30, 2009. Dr. Trotter's e-mail twice stated that Respondent's contract would end on June 30, 2009, but also stated that she was "working through" contracts that would start on July 1, 2009, leaving open, in Respondent's mind, the possibility that his was one of the new contracts still being processed. Dr. Trotter did not unequivocally state that Respondent's services would no longer be required on the TNE initiative after June 30, 2009. On the morning of July 6, 2009, Respondent sent the following e-mail to Dr. Trotter: I am following up on the email I sent you regarding my contract. I received a reply from you stating that you were working on contracts ending June 30, 2009. I continue to come to work under the 12-month contractual agreement since October 10, 2008. I am therefore requesting definitive information about the status of my contract. Telephone discussions and further e-mail exchanges occurred between Respondent and Dr. Trotter over the course of the next two days. Respondent continued to insist that he had a 12-month contractual agreement, and attributed the misunderstanding to the fact that FAMU never issued an official letter of employment that explained the terms under which he had been hired. Finally, on the afternoon of July 8, 2009, Dr. Trotter sent the following e-mail to Respondent: As noted in an earlier e-mail your contract did end on June 30, 2009. You will be compensated for the days worked beyond June 30, 2009. You should not continue to work beyond tomorrow. Thanks for working with Teachers for a New Era. July 9, 2009, was the last day that Respondent worked pursuant to his A&P employment contract. Respondent was paid by FAMU pursuant to his A&P employment contract for all days worked through July 9, 2009. Due to an error on the part of FAMU, Respondent continued to receive regular bi-weekly gross pay of $2,107.28 from FAMU through the pay period ending October 18, 2009. At the hearing, Respondent conceded that he received these payments despite the fact that he had stopped working for FAMU as the TNE coordinator for statistical research on July 9, 2009. Respondent testified that he believed the university was paying him for the remainder of his one-year contract. On June 30, 2009, Respondent accepted an Other Personal Services ("OPS") appointment to work as an adjunct instructor in the FAMU Department of Economics. The OPS appointment was to teach one economics class per week. Respondent was to be paid $25.00 per hour, five hours per week, for a biweekly gross pay of $250.00. The appointment was for the sixteen-week fall semester, from August 24, 2009, through December 11, 2009, with Respondent receiving total gross pay of $2,000.00 for the period. However, Respondent worked in the OPS position for only one week before starting a full-time faculty position at Savannah State University in Georgia on September 11, 2009. Respondent was correctly paid by FAMU for the one week he worked in the OPS position. Due to an error on the part of FAMU, Respondent continued to receive regular bi-weekly gross pay of $250.00 through the pay period ending October 18, 2009. In total, Respondent received $14,190.41 in unearned compensation from FAMU.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered requiring Respondent to repay $14,190.41 to FAMU. DONE AND ENTERED this 8th day of March, 2011, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of March, 2011.
The Issue The amount of attorney's fees and costs to be awarded to Petitioner, pursuant to the order on remand from the Second District Court of Appeal, in Raven v. Manatee County School Board, 32 So. 3d 126 (Fla. 2d DCA 2009), pursuant to Subsection 120.595(5), Florida Statutes (2009).1
Findings Of Fact Petitioner retained the law offices of Kelly & McKee, P.A., to represent him in connection with his dispute over Respondent seeking to terminate his employment. Petitioner was successful in reinstating Petitioner to his position; however, the Administrative Law Judge was without authority to order the School Board to extend his contract beyond the May 25, 2007, expiration date. Petitioner seeks attorney's fees for the underlying proceeding and the appellate proceeding in the amount of $66,881.25, representing the total number of hours billed to Petitioner. Petitioner is also seeking $5,074.98 in costs. Melissa Mihok, Esquire, billed 286.75 hours at $225.00 per hour for legal services performed. The two principals of the firm, Mark Kelly, Esquire, and Robert F. McKee, Esquire, billed 1.75 hours and 5.0 hours, respectively, of legal services, for which they billed at $350.00 per hour. Petitioner's expert witness, Mark Herdman, Esquire, who has intensive experience in this area, testified that the hourly rate for employment of attorneys in the Tampa Bay Area ranged from $200.00 to $350.00 per hour and that the amount of time expended on this case was reasonable. Respondent's expert witness, Thomas M. Gonzalez, Esquire, testified that the amount of time spent and the fees claimed were not reasonable; that the fee usually charged for an attorney with five years' experience, representing a School Board employee, was between $150.00 to $200.00 per hour; that 19 hours of preparation time for an administrative hearing that took three hours was excessive; and, further, that 102 hours to prepare essentially the same brief three times in the form of a proposed order, a one-page exception, a response to Respondent's exception, and the appellate brief was not reasonable. Based on all the evidence, including the billing statement; the fact that Ms. Mihok testified that her regular hourly rate in representing teachers in administrative hearings was $100.00 per hour; and the credible and persuasive testimony of Respondent's expert, an hourly rate of $150.00 is reasonable. The amount of time expended on this matter was excessive and should be reduced by 50 hours, plus a reduction of 35 hours from the time spent on seeking and collecting attorney's fees. The reasonable amount of time spent on this matter is 201.75 hours. Therefore, the reasonable amount of attorney's fees for Ms. Mihok in this matter is $30,262.50, which is 201.75 hours at an hourly rate of $150.00. The fee for Mr. Kelly and Mr. McKee should be reduced by 1.5 hours at $350.00 per hour for the time spent on research for collecting attorney's fees. The total due for their legal services is 5.25 hours at $350.00 for a total amount of $1,837.50. Therefore, the lodestar amount for attorney's fees for the firm is $32,100.00, plus an enhancement of $5,000.00 for the establishment of new law. As for costs, the expert witness fee for attorney's fees is not recoverable. The amount of costs sought is reduced by $1,800.00, and $1,194.70 is awarded for court reporter fees. Therefore, the total recoverable costs are $4,469.68.
The Issue The issue is whether the proposed award of the contract for Request for Proposals (RFP) No. P2029 to Henry and Rilla White Youth Foundation, Inc. (White Foundation) is contrary to the specifications of the RFP.
Findings Of Fact DJJ issued RFP No. P2029 on April 17, 2007. The RFP solicited proposals for a “240-available slot Community-based Intervention Services program for boys and girls for Volusia, Flagler and Putnam counties ” The contract resulting from the RFP will be for a three-year term -- July 1, 2007 through June 30, 2010 -- with a renewal option for up to an additional three years at DJJ’s sole discretion. The RFP states that the maximum annual contract amount is $1,504,968, and prospective providers were required to propose a price at or below that amount. EYA and White Foundation submitted timely, responsive proposals in response to the RFP. White Foundation’s proposal offered a slightly lower price than EYA’s proposal.1 On June 18, 2007, DJJ posted notice of its intent to award the contract to White Foundation. Thereafter, EYA timely filed a notice of intent to protest and a formal written protest challenging the proposed award of the contract to White Foundation. The RFP provided that the proposals were to be evaluated and scored in three categories: technical proposal, financial proposal, and past performance. The past performance category focuses on the prospective provider’s knowledge and experience in operating non-residential juvenile justice programs. The criteria related to the past performance category are contained in Attachment C to the RFP. Attachment C consists of three parts: Part I - Past Performance of Non-Residential Programs; Part II - Evaluation for Past Performance in the United States Outside of Florida; and Part III - Evaluation for Professional Accreditation in the United States. The focus of the dispute in this case is on Part III. A proposal could receive a total of 1,000 points if, as is the case with both EYA and White Foundation, the prospective provider operated DJJ-contracted non-residential programs in Florida. The proposal could receive up to 240 points for Attachment C, with a maximum of 40 points for Part III. The RFP states that the proposal that receives the highest overall score will be awarded the contract. White Foundation’s proposal received a total of 785.98 points, which was the highest overall score. White Foundation’s score included 40 points for Part III of Attachment C. EYA’s proposal received a total of 752.03 points, which was the second-highest overall score. EYA received zero points for Part III of Attachment C. EYA contends that White Foundation should not have received any points for Part III, which would have resulted in White Foundation’s overall score being 745.98 and would have given EYA the highest overall score. Part III of Attachment C asks whether the prospective provider currently operates non-residential juvenile justice programs that are accredited and in good standing with certain accrediting agencies, including the Rehabilitation Accreditation Commission (CARF). If so, the RFP requires the prospective provider to include supporting documentation. The prospective provider receives 10 points for each accredited program listed in Part III of Attachment C. The RFP states multiple times that the supporting documentation “must include the start and end dates [of the programs], be current dated and valid at least through the start date of the Contract that results from this RFP,” and that it must state that “the program cited is a non-residential juvenile program and that is run by the prospective Provider.” The RFP also states multiple times that a prospective provider’s failure to provide the required supporting documentation “shall” result in zero points being awarded for Part III of Attachment C, and that DJJ “is not responsible for research to clarify the prospective Provider's documentation.” EYA did not list any programs in its response to Part III of Attachment C. Its wilderness programs are accredited by the Council on Accreditation (COA), but its non-residential juvenile justice programs are not accredited by COA , CARF, or any other organization. White Foundation listed four programs in its response to Part III of Attachment C: a conditional release program in Nassau County; a conditional release program in Duval County; a conditional release program in Clay County; and an Intensive Delinquency Diversion Services program in Circuit 2. The documentation provided by White Foundation to show that the listed programs are accredited was an undated certificate from CARF and a one-page “Survey Accreditation Detail” dated June 28, 2006. The CARF certificate states that “a three-year accreditation is awarded to the [White Foundation] for the following identified services: case management/services coordination: family services (children and adolescents)" and for “out-of-home treatment: family services (children and adolescents).” The seal on the certificate includes an expiration date of August 2007. The CARF certificate does not mention any of the programs listed by White Foundation in response to Part III of Attachment C. It only certifies that that White Foundation is accredited as an organization for certain services. The Survey Accreditation Detail document makes reference to survey number 32190; company number 200190; an accreditation decision of “three-year accreditation”; an accreditation expiration date of August 31, 2007; and Correction Services of Florida, LLC as the “company submitting intent.” The document lists six “companies with programs,” including the four programs listed by White Foundation in its response to Part III of Attachment C. The bottom of the Survey Accreditation Document includes the notation “page 1 of 2.” The second page of the document is not included in the portion of White Foundation’s response to the RFP that was received into evidence, nor is it included in the exhibit attached to the deposition of Paul Hatcher, the DJJ employee who evaluated the responses to the RFP with respect to Attachment C. Mr. Hatcher testified that he interpreted the Survey Accreditation Detail document to be “a summary of the prospective provider’s programs that received accreditation based on the CARF award letter.” That interpretation, while not implausible, is not adequately supported by the evidence of record. First, there is nothing on the Survey Accreditation Detail document to demonstrate that it was prepared by CARF, and Mr. Hatcher acknowledged that he did not know who prepared the document. Second, it cannot be determined from the Survey Accreditation Detail document whether the “three-year accreditation” referred to in the document relates to all of the “companies with programs” listed on the document, or just to Correction Services of Florida, LLC, which is identified as the “company submitting intent.” Indeed, each of the listed “companies with programs” has a different six-digit number in parenthesis following its name and only the number following Correction Services of Florida, LLC, matches the “company number” referenced at the top of the Survey Accreditation Detail document. Third, the record does not reflect the relationship, if any, between White Foundation and Correction Services of Florida, LLC. Indeed, Mr. Hatcher testified that he did not know anything about Correction Services of Florida, LLC, except that it appeared to have the same address as White Foundation. The CARF certificate and the Survey Accreditation Detail document do not on their face reflect whether the listed programs are non-residential programs (as compared to residential programs) or whether they are juvenile justice programs (as compared to juvenile programs that do not involve the juvenile justice system). However, Mr. Hatcher testified that all of the services identified on the CARF certificate correspond to non-residential facilities and that he was familiar with the listed programs and knew that they were juvenile justice programs. It cannot be determined from the CARF certificate and Survey Accreditation Detail document whether the four programs listed by White Foundation in its response to Part III of Attachment C are accredited. Indeed, Mr. Hatcher candidly acknowledged as much in his testimony.2 If DJJ had scored White Foundation’s proposal in accordance with the specifications of the RFP, the proposal would have received zero points for Part III of Attachment C, which would have resulted in EYA’s proposal receiving the highest overall score.
Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that DJJ issue a final order rescinding the proposed award of RFP No. P2029 to White Foundation. DONE AND ENTERED this 14th day of December, 2007, in Tallahassee, Leon County, Florida. S T. KENT WETHERELL, II Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of December, 2007.