Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ALBERT J. RUOCCO, 85-000671 (1985)
Division of Administrative Hearings, Florida Number: 85-000671 Latest Update: Nov. 12, 1985

The Issue By its Administrative Complaint filed on January 15, 1985, the Department of Professional Regulation charged Respondent with violations of Section 489.129(1)(h)(k) and (m) Florida Statutes, relating to diversion of funds, abandonment of a construction project and gross negligence, incompetency or misconduct. The issue in this proceeding is whether any violation occurred and, if so, what disciplinary action should be taken. The Respondent generally denies the charges. At the hearing, the Petitioner presented two witnesses: Don Riordan, the home-owner; and Stephen Douglas Gates, an employee of Brooks Glass Company who did an estimate of cost of completion for the project. Four Petitioner's exhibits were admitted without objection: a check for payment by Don Riordan to A1 Ruocco, the Brooks Glass estimate, letter from William Bambach to A1 Ruocco and letter from Bob Bambach to Donald Riordan. A fifth exhibit was withdrawn. The Respondent testified on his own behalf and presented no other witnesses. His eight exhibits included the contract and a series of letters between himself and Robert Bambach. At the outset of the hearing, Petitioner moved for leave to file the testimony of Robert Bambach at a later date, due to unsuccessful attempts to serve a subpoena. The Respondent objected and the motion was denied. Petitioner waited until two days before the hearing to attempt to serve the prospective witness even though the hearing had been scheduled since June and the location of the hearing had been established for two weeks. Petitioner filed its Proposed Recommended Order on November 1, 1985; none was filed by Respondent. The proposed findings of fact have been primarily adopted herein but are addressed more specifically in Appendix A, attached to this order.

Findings Of Fact The facts in this case are virtually uncontroverted, with the exception of the months and sequences of some events. At all times material to the Administrative Complaint, Respondent was a registered building contractor holding license number RB0030112, which license qualified River's Edge Construction Company, Inc., Melbourne, Florida. On March 11, 1983 a contract was entered between Albert Ruocco, President, River's Edge Construction Co., Inc. ("Ruocco") and Don Riordan, Jr., ("Riordan") to enclose a balcony with bronze awning windows and bronze tinted glass at Riordan's townhouse residence in Melbourne Beach, Florida. Ruocco and Riordan knew each other socially as Ruocco was a neighbor of Riordan's parents. Ruocco was recommended for the job by Riordan's parents. On March 31, 1983, Riorden paid Ruocco $1300.00 or the $1853.00 contract price. Riordan testified that Ruocco was doing him a favor because it was repair work and the principal amount of money was being paid up front to avoid a cash-flow problem on materials. (T-18). The idea was to get the work done as soon as possible. (T-16). Sometime around May or June 1983, the construction started with removal of existing screening and the installation of an aluminum kick plate and posts to hold the awning window frames. Sometime later the windows were put in for the first time. The actual work on the project was done by a Mr. Bambach, rather than Ruocco. What followed the first installation was a series of misadventures culminating in a lawsuit by Riordan and an $800.00 civil judgment against Ruocco. The work was never completed. The first windows installed were clear glass rather than tinted bronze. Riordan complained to Ruocco and the windows were removed within twenty-four hours. The windows were installed again, this time with film rather than tinted glass and Riordan called Ruocco the next day. Again the windows were removed immediately. Some time passed (by now it was early August) and bronze-tinted windows were installed. However, after a rain storm it became apparent that the installation was faulty, as the structure leaked. The metal strips had been damaged from the several removals. Riordan complained the third time and the windows were removed a third time. They were never replaced. Throughout this period Riordan was dealing with Ruocco, with whom he had the contract and Ruocco was dealing with Bambach, to whom he had given $800.00 as partial payment for the work. Relations between the individuals deteriorated as months passed and the windows were still not finally installed. Riordan called Ruocco about getting the work done and was told that Ruacco was having trouble with his worker. By the end of 1983 Riordan's attorney called Ruocco and said that the money had to be refunded. In the meantime, a stand-off had developed between Ruocco and Bambach, with Ruocco insisting that the work be completed prior to final payment and Bambach insisting that he be paid prior to re- installation of the windows. Bambach had taken the windows to a glass company to be fixed. Bambach alleged in his correspondence that Ruocco did not have the money to pay him, while Ruocco alleged that he tried to meet Bambach to give him the money but Bambach didn't show up. Ruocco testified that he possibly could have installed the windows himself but was trying to get Bambach to complete the job. (T-57). He further testified that he had two other persons look at the job but they wouldn't touch someone else's work. (T-58). Sometime in early 1984 Ruocco was made to understand that Riordan was not interested in waiting any longer for the project to be finished and wanted his money back.

Recommendation On the basis of the foregoing, I recommend that the Respondent be found guilty of misconduct as provided in Subsection 439.129(1)(m) Florida Statutes, and be reprimanded in accordance with Subsection 489.129(1) Florida Statutes. DONE and ORDERED this 12th day of November, 1985, in Tallahassee, Florida. MARY CLARK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of November, 1985. APPENDIX In accordance with Section 120.59(2) Florida Statutes, the following are recommended rulings on proposed findings of facts submitted by Petitioner in this case. The numbered paragraphs below conform to the paragraphs proposed by Petitioner. These findings are incorporated in Recommended Order, paragraph 1. These findings are incorporated in Recommended Order, paragraphs 2 and 6. These finding are incorporated in Recommended Order, paragraph 3. These findings are incorporated in Recommended Order, paragraph 5. These findings are incorporated in Recommended Order, paragraph 5. These findings are incorporated in Recommended Order, paragraph 5. These findings are incorporated in Recommended Order, paragraph 7. The findings related to the estimate of Brooks Glass Company are irrelevant. The estimate was done approximately one and a half years after the contract was entered between Riordan and Ruocco. The witness from Brooks Glass who testified about the estimate could not relate the quality of Brooks' windows to those intended by Ruocco for the project. (T. 41-43). To the extent that these findings are proposed to show the extent to which the project was left uncompleted, the fact that the windows were never re- installed was admitted by Ruocco and is reflected in Recommended Order paragraphs 4 and 5. These findings are incorporated in Recommended Order paragraphs 7 and 8. COPIES FURNISHED: Fred Roche, Seeretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Douglas Beason, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Albert J. Ruocco 604 Citrus Court Melbourne, Florida 32951

Florida Laws (3) 120.57489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. BRUCE ALLES, 81-002057 (1981)
Division of Administrative Hearings, Florida Number: 81-002057 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent Bruce G. Alles, is a certified general contractor, license number CGC C014472, and has been so licensed since the summer of 1979. At that time, he became the qualifying agent for Univel, Inc., Melbourne Beach, Florida, a general contracting firm. Prior to Respondent becoming the qualifier for Univel, Inc., one David Boland had been the qualifying agent for the company, and no apparent action was taken by Univel to remove Boland as a qualifier for an undisclosed period of time after Respondent assumed that function. (Pleadings, testimony of Respondent, K. Alles) The only project of Univel that Respondent supervised from 1979 until subsequent to April, 1981 was the renovation of several buildings called Ocean Landings. During the period of March or April, 1980 until April, 1981, he had no involvement in any of Univel's projects. Since April, 1981 he has pulled permits and supervised some small renovation or alteration projects. (Testimony of Respondent, K. Alles, Stipulation) For the past three and one-half years, Lawrence M. Stoner, a certified general contractor and qualifying agent for Dynamic Construction Company, Inc. has engaged in joint construction projects with Univel, Inc. In such instances, Stoner obtains the building permits and supervised construction of the projects. At some undisclosed point in time, Kenneth Alles, Vice President of Univel, Inc. consulted with and obtained assurances from legal counsel that, based upon Univel's relationship with Stoner and Dynamic Construction Company, it was unnecessary for Stoner to file a formal application as qualifying agent for Univel. In fact, Alles was of the opinion that at one point Univel had three qualifying agents simultaneously who were Respondent, Stoner, and Boland. (Testimony of K. Alles) At some undisclosed time subsequent to Respondent becoming the qualifying agent for Univel, that firm entered into a construction contract with Palm Harbor West, Inc. to construct a condominium building called Harbour Cay. Stoner supervised the construction of the building. There was an on-site superintendent of construction who was employed by Univel. Stoner and Univel co-signed a bank loan agreement for the project. (Testimony of K. Alles) Respondent was not involved in the Harbour Cay project in any respect. He did not affix his license number to the contract nor did he supervise of have any connection with the project. (Testimony of K. Alles, Stipulation) On March 27, 1981, the Harbour Cay building collapsed causing multiple deaths and injuries. (Testimony of K. Alles, pleadings)

Recommendation That the Construction Industry Licensing Board administer a written public reprimand to Respondent Bruce Alles for violation of Subsection 489.119(5), F.S., pursuant to Subsection 489.129(j), F.S. DONE and ENTERED this 23rd day of December, 1981, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of December, 1981. COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Post Office Box 1386 Tallahassee, Florida 32302 Joe Teague Caruso, Esquire Post Office Box 757 Cocoa Beach, Florida 32931 James K. Kinnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (3) 489.105489.119489.129
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs RALPH N. BATTAGLIA, INTERCONTINENTAL CONSTRUCTION CORPORATION, INC., 07-000052PL (2007)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Jan. 04, 2007 Number: 07-000052PL Latest Update: May 08, 2007

The Issue Whether Respondent committed the violations alleged in the Amended Administrative Complaint issued against him and, if so, what disciplinary action should be taken.

Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made to supplement and clarify the facts to which the parties stipulated at the outset of the final hearing (Parties' Stipulations)2: The contract referenced in the Parties' Stipulations (Building Contract) was signed by Mr. Stasinos (on behalf of ICC) and Mr. Skiera (on behalf of himself and his wife) on June 29, 2000. The home that ICC agreed to build for the Skieras (Skiera Residence) was described in the Building Contract as a "[c]ustom two-story residence with detached garage and riding cor[r]al for a total of 5,370 square feet." It was to be constructed on a tract of land owned by the Skieras in Boynton, Beach, Florida. The Building Contract provided for the following allowances: $20,000.00 for "electrical"; $17,000.00 for "plumbing"; $15,000 for "HVAC"; a "door hardware allowance" of "$50.00 per [interior] door"; $6,000.00 for a "stacked stone veneer" exterior; an "entry door hardware allowance" of "$100.00 per door"; $15,000.00 for "kitchen cabinetry and vanity"; $8,000.00 for "counter tops and vanity tops"; $9,000.00 for "landscaping," including "trees, shrubs, sod, automatic time clock, [and an] operated irrigation system with rain sensor"; and $7,000 for "driveways, walkways, [and] flatwork." There was no written statement in the Building Contract explaining a consumer's rights under the Construction Industries Recovery Fund, as then required by Section 489.1425, Florida Statutes. The Building Contract contained a "[p]ayment [d]raw [s]chedule," which provided as follows: Upon execution of contract: 10%- $36,608.00 Thereafter, progress payments based on schedule of values. This "schedule of values" (referred to in the "[p]ayment [d]raw [s]chedule") contained the following "scheduled values" (excluding change orders): 1. Permits $21,600.00 2. Clearing/Grading/Fill $10,800.00 3. Foot'gs. Undgr Plumb, Soil Treatmt $23,000.00 4. Foundation/Slab poured $32,760.00 5. Exterior Walls/Tie Beam $26,600.00 6. Roof Trusses $26,600.00 7. Roof Sheathing/Felt $19,400.00 8. Interior Framing Complete $14,000.00 9. Windows/Exterior Door Frames Set $14,400.00 10. 2nd Plumbing/Tub Set $7,200.00 11. Wiring Rough-In $14,400.00 12. HVAC Ducts Installed $7,200.00 13. Roof Shingles/Tiles Installed $14,400.00 14. Insulation (wall & ceiling) $4,200.00 15. Exterior Trim/Soffits $11,800.00 16. Drywall Hung $14,400.00 17. Drywall Finish $10,800.00 18. Interior Trim/Interior Doors Installed $13,400.00 19. Interior Paint $8,800.00 20. Siding/Stucco $14,400.00 21. Exterior Paint Complete $8,800.00 22. Exterior Doors & Garage Door Install $6,200.00 23. Cabinets/Countertops Installed $10,000.00 24. Plumbing Finish $3,600.00 25. Electrical Finish $5,600.00 26. HVAC-Compressor/A.H. Installed $10,920.00 27. Driveway/Walks Installed $3,600.00 28. Landscaping/Irrigation $7,200.00 There were six separate change orders. They were dated August 20, 2000 (Change Order No. 001), August 29, 2000 (Change Order No. 002), September 26, 2000 (Change Order No. 003), October 15, 2000 (Change Order No. 004), October 15, 2000 (Change Order No. 005), and November 10, 2000 (Change Order No. 006). As of December 21, 2000, ICC had been paid in full for all six change orders, as well as for items 1 through 8 on the "schedule of values." As of February 27, 2001, ICC had received additional monies from the Skieras: payment in full for items 9 through 12 and 15 on the "schedule of values" and partial (50 percent) payment for items 13 and 20 on the "schedule of values." As of April 10, 2001, ICC had been paid a total of $287,966.20 (all from the proceeds of a mortgage loan the Skieras had obtained from Admiralty Bank) for work done on the Skiera Residence. On May 1, 2001, the Skieras paid ICC an additional $16,800.00 for drywall work, bringing the total amount of payments that ICC had received from (or on behalf of) the Skieras, as of that date, to $304,766.20. The Skieras made no further payments to ICC. The "eight valid claims of lien" referenced in the Parties' Stipulations were filed by eight different subcontractors, all of whom had been hired by ICC to work on the Skiera Residence: Boca Concrete Pumping, Inc.; Gulf Stream Lumber Company; L & W Supply Corp., d/b/a Seacoast Supply; Waste Management of Palm Beach; B.T. Glass & Mirror, Inc.; Boca Raton Decorating Center Company; American Stairs; and Broten Garage Door Sales Inc.3 Boca Concrete Pumping was the "very first" subcontractor to work on the construction of the Skiera Residence. It did the "slab work, the foundation" (referenced in item 4 of "schedule of values"). Its lien was recorded on December 6, 2000. The lien was in the amount of $1,001.25, and it indicated, on its face, that it was for unpaid "concrete pumping" that had been furnished between September 8, 2000, and September 22, 2000. A satisfaction of this lien, dated March 8, 2001, was filed March 24, 2001. Gulf Stream Lumber's original lien was recorded February 15, 2001. It was in the amount of $67,872.59, and it indicated, on its face, that it was for unpaid "building material" that had been furnished between August 15, 2000, and January 24, 2001. An amended claim of lien was recorded May 3, 2001, in the amount of $36,530.59 for unpaid "building material" that, according to the lien, had been furnished between August 25, 2000, and March 27, 2001. A satisfaction of the original lien and amended claim of lien, dated November 30, 2001, was filed December 5, 2001. The liens were satisfied, pursuant to the terms of a Settlement Stipulation, upon the Skieras' payment of $39,579.28 to Gulf Stream Lumber. L & W Supply's lien was recorded April 30, 2001. It was in the amount of $4,536.98, and it indicated, on its face, that it was for unpaid "building materials [and] related items" that had been furnished between December 16, 2000, and January 30, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. The lien was satisfied by the payment of $10.00 "and other good and valuable consideration" (which was the payment of an additional $2,850.00 by check dated October 11, 2001). Waste Management of Palm Beach's lien was recorded May 31, 2001. It was in the amount of $1,665.89, and it indicated, on its face, that it was for unpaid "[w]aste [r]emoval [s]ervices" that had been furnished between August 30, 2000, and April 5, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. B.T. Glass & Mirror's lien was recorded June 29, 2001. It was in the amount of $3,560.00, and it indicated, on its face, that it was for an unpaid "glass/mirror package" that had been furnished between May 3, 2001, and May 31, 2001. A satisfaction of this lien, dated October 19, 2001, was filed November 13, 2001. The lien was satisfied by the payment of $1,600.00 (by check dated November 10, 2001), plus an agreement to provide "$2,000.00 in gazebo or arbor products from the Hitching Post," the Skieras' family business. Boca Raton Decorating Center's lien was recorded May 19, 2001. It was in the amount of $1,218.79, and it indicated, on its face, that it was for unpaid "paint, sealers [and] sundries" that had been furnished between May 1, 2001, to May 2, 2001. A satisfaction of this lien, dated October 11, 2001, was filed November 7, 2001. American Stairs' lien was recorded August 16, 2001. It was in the amount of $4,188.00, and it indicated, on its face, that it was for unpaid "[s]tairs and [r]ailings" that had been furnished between June 8, 2001, and June 15, 2001. A satisfaction of this lien was executed on October 15, 2001. Broten Garage Door Sales' lien was recorded September 5, 2001. It was in the amount of $3,214.00, and it indicated, on its face, that it was for the unpaid "sale and installation of garage doors and openers," which took place between June 25, 2001, and July 17, 2001. A satisfaction of this lien, dated January 31, 2002, was filed on February 5, 2002. At a meeting "in the early part of August [2001]" attended by Respondent, Mr. Stasinos, the Skieras, and the president of the bank from which the Skieras had borrowed the money to pay for the construction of their residence, Respondent announced that, on behalf of ICC, "he was filing [for] bankruptcy."4 ICC stopped working on the Skiera Residence after this meeting. At the time, the Skiera Residence was approximately 70 to 80 percent completed (and the Skieras had paid ICC a total of $304,766.20, or approximately 80 percent of the total contract price (including change orders) of $378,286.205). In addition to paying $57,316.62 to satisfy the "eight valid claims of lien" referenced in the Parties' Stipulations, the Skieras paid approximately an additional $57,000.00 to other subcontractors who provided goods and/or services "needed to complete the house." The $10,000.00 check referred to in the Parties' Stipulation 14 (that the Skieras received from Andover Construction, Inc.) did not "represent any kind of final settlement" between the Skieras and ICC. The October 4, 2001, Certificate of Occupancy for the Skiera Residence referred to in the Parties' Stipulations indicated, on its face, that ICC was the contractor, notwithstanding that ICC had abandoned the project "in the early part of August [2001]." Respondent has been a Florida-licensed general contractor since July 29, 1987. In his capacity as ICC's licensed qualifier, he has previously (by Final Order filed in DBPR Case Nos. 2001-03283 and 2001-03284 on December 23, 2003) been found guilty of, and disciplined for, violating (in connection with two residential construction projects undertaken by ICC for A. Richard Nernberg) the same subsections of Section 489.129(1), Florida Statutes (Subsections (1)(g), (i), and (m)) that he is accused of violating in the instant case. In these prior disciplinary proceedings, Respondent's license was suspended for two years, and he was fined $6,000.00 and required to pay $958.30 in investigative costs. Administrative complaints were also filed against Respondent in DBPR Case Nos. 94-15958 and 97-17352. Both of these cases were resolved by settlement stipulations in which Respondent "neither admit[ted] [nor] denie[d] the allegations of fact contained in the [a]dministrative [c]omplaint[s]."

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board issue a Final Order: finding Respondent guilty of violating Section 489.1425(1), Florida Statutes, as alleged in Count I of the Amended Administrative Complaint, and fining him $1,000.00 for this violation; (2) finding Respondent guilty of the violation of Section 489.129(1)(g)1., Florida Statutes, relating to Boca Concrete Pumping's December 6, 2000, $1,001.25 lien, alleged in Count II of the Amended Administrative Complaint, and taking the following disciplinary action against him for this violation: suspending his license for four years (with such suspension to run consecutively with his current suspension); (b) fining him $5,000.00; (c) requiring him to pay restitution in the amount of $1,001.25 to the Skieras; and (c) ordering him to reimburse the Department for all reasonable investigative and prosecutorial costs (excluding costs related to attorney time) incurred by the Department; and (3) dismissing all other charges in the Amended Administrative Complaint. DONE AND ENTERED this 8th day of May, 2007, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 2007.

Florida Laws (16) 1.01120.569120.5717.001206.20218.79455.2273458.331489.115489.119489.1195489.129489.140489.1425627.8405810.02
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs JOSEPH W. KAMINSKY, 93-006523 (1993)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 12, 1993 Number: 93-006523 Latest Update: May 29, 1996

Findings Of Fact At all times material hereto, Respondent has been a certified general contractor in the state of Florida, having been issued license number CG C027718. At all times material hereto, Respondent has been the qualifying agent for Classic Design Builders. William R. DeFreitas describes himself as a broker of building materials for third world countries. His wife is also employed in that same business. They had their office building constructed for them. When they subsequently determined to add an addition to their residence, they solicited bids from that contractor and from two other persons. Aaron Ware, who held himself out to be an architect and the president of a company known as L. A. Designs, Inc., was one of the persons from whom the DeFreitases solicited a bid. He submitted a bid dated April 26, 1990, and a draw schedule on May 3, 1990. The extent of the work to be performed was finalized on June 6, 1990, when Mr. DeFreitas initialed the changes to the initial bid. The construction project contemplated under that contract was the addition of a family room, a laundry room, a shower off the master bath, and a small bath at the front of the house. The June 6, 1990, contract also called for replacement of the garage door and "painting of some interior doors." The total contract price was $50,000. While Ware was negotiating with the DeFreitases, he was also discussing with Respondent entering into a joint venture agreement between Classic Design Builders and L.A. Designs for the DeFreitas construction project. Their verbal agreement was memorialized in a written agreement dated June 18, 1990. Thereafter, Respondent did not advise Petitioner that he had entered into a joint venture agreement and, similarly, did not qualify the joint venture as a separate business entity for licensure purposes. Pursuant to instructions from Ware, Mr. DeFreitas directed a letter to the City of Boca Raton advising the building department that he had entered into a contract to construct an addition to his residence with "L.A. Designs/ Classic Designs." On July 2, 1990, Respondent on behalf of Classic Design Builders obtained a building permit from the City of Boca Raton for the DeFreitas addition. On July 6, Ware began work on the addition. Ware worked on the project from July of 1990 through the end of that year. During the course of that construction, the DeFreitases made many changes in the scope of the work contemplated by the original contract, which increased the contract price to above $56,000. Additional work was performed, which was not covered by the contract and which the DeFreitases agreed to pay for directly to the supplier or subcontractor. On February 4, 1991, the DeFreitases directed a letter to Ware advising him that the construction was close to completion and that it was time for them to "settle our account" as to the extras for which the DeFreitases had not paid. In that letter, the DeFreitases also offered to produce the invoices for materials and labor that they had agreed to pay to finish the job. In July of 1991 the DeFreitases complained to the City of Boca Raton. Respondent, as the holder of the building permit, was contacted and advised that the DeFreitases were alleging that their contractor had failed to complete the project. Respondent immediately went to the DeFreitases' business, met with Mr. DeFreitas, inspected the home, and prepared a punch list of items to be completed, many of which were not covered by the construction contract but were done by Respondent in an attempt to achieve customer satisfaction. Respondent completed the project, obtained the final inspections, and presented the DeFreitases with a warranty and release of lien. The DeFreitases refused to accept the warranty or release of lien. As a result of the DeFreitases' complaints, Respondent and Ware were charged with violating local ordinances. In those prosecutions, as well as in this case, the DeFreitases have attempted to obtain $11,000 from Respondent as "restitution" for moneys they have had to spend or will have to spend to complete the work envisioned by their contract with L.A. Designs, Inc. Most of the items listed as components of the claim for restitution are not even part of the construction contract. Of those few items covered by the contract, the money claimed is not. For example, the contract allocated $500 to be expended on the bathroom cabinets. The DeFreitases spent $1,670 on the cabinets and, surprisingly, are claiming that Respondent should pay them the difference because they spent more than their contractual allowance. Finally, they have claimed the cost of replacing inferior building materials provided by them, such as wood French doors. The DeFreitases paid to Ware approximately $4,000 less than they had promised to pay him as a result of the work completed by L.A. Designs. Rather than suffering a loss, the DeFreitases have actually received a windfall. At no time material hereto was either Ware or L.A. Designs licensed in the state of Florida as a contractor, architect, professional engineer, or landscape architect. Respondent knew that Ware and L.A. Designs were not licensed. At the time that Classic Design Builders and L.A. Designs entered into their written joint venture agreement and at all other times material hereto, Respondent was not an officer, director, stockholder, or employee of L.A. Designs, and Ware was not an officer, director, stockholder, or employee of Classic Design Builders. When Ware approached Respondent about entering into a joint venture for the DeFreitas project, Respondent had already suffered a minor heart attack and two mini-strokes. The joint venture agreement itself recites Respondent's need to limit his activities due to health reasons. In July of 1990 Respondent additionally tore an Achilles tendon in his left leg and was in a cast until Christmas of 1990. Due to his immobility during that time period, Respondent delegated all of his construction jobs to others, understanding that he was ultimately responsible for those projects since he was the contractor of record on them. In the same way, he delegated to Ware the day-to-day responsibility for the DeFreitas project. Other than "pulling the permit" for the DeFreitas project, Respondent's only other involvement in the job until the time that he was contacted as a result of the DeFreitases' complaints to the City of Boca Raton in July of 1991, was right after the job was commenced regarding some problem concerning the lot line. He was able to resolve that problem with the City of Boca Raton by telephone. The DeFreitases did not know that Respondent was the contractor for their construction project and ultimately responsible for that work. Although Ware had advised them that a "buddy" would somehow be involved in the construction, and although Mr. DeFreitas referred to both L.A. Design and Classic Design Builders in his letter to the City of Boca Raton authorizing a building permit to be issued, the evidence is clear that had the DeFreitases known of Respondent's responsibility, they would have been insisting that he perform services months earlier. In 1987 Respondent was charged with abandoning a construction project and/or failing to timely complete it. Respondent entered into a settlement stipulation admitting that fact and agreeing to pay a fine to the Construction Industry Licensing Board in the amount of $1,000. A Final Order Approving Settlement Stipulation was entered on June 8, 1988. Respondent received no money from the DeFreitases or from Ware for the work Respondent performed on the DeFreitas addition. Respondent's out-of-pocket expenses for labor and materials on the DeFreitas residence between July of 1991 and June of 1992 total $1,747.50.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered: Finding Respondent guilty of Counts I, II and VII of the Administrative Complaint filed against him; Finding Respondent not guilty of Counts III, IV, and V of the Administrative Complaint filed against him; Requiring Respondent to pay an administrative fine in the amount of $1,000; and Placing Respondent's license number CG C027718 on probation for a period of two years. DONE and ENTERED this 16th day of November, 1994, at Tallahassee, Florida. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of November, 1994. APPENDIX TO RECOMMENDED ORDER Petitioner's proposed findings of fact numbered 2-10, 16-20, and 22 have been adopted either verbatim or in substance in this Recommended Order. Petitioner's proposed findings of fact numbered 11-15, 21, and 24 have been rejected as not being supported by the weight of the evidence in this cause. Petitioner's proposed finding of fact numbered 1 has been rejected as not constituting a finding of fact but rather as constituting a conclusion of law. Petitioner's proposed finding of fact numbered 23 has been rejected as being subordinate. COPIES FURNISHED: John David Ashburn, Esquire Department of Business and Professional Regulation 3932 RCA Boulevard, Suite 3210 Palm Beach Gardens, Florida 33410 Diane Perera, Esquire Department of Business and Professional Regulation 401 N.W. 2nd Avenue, Suite N-607 Miami, Florida 33128 Peter Mineo, Jr., Esquire 8220 State Road 84 Fort Lauderdale, Florida 33324 Copies furnished, continued Richard Hickok, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Jack McRay, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (4) 120.57455.227489.119489.129 Florida Administrative Code (2) 61G4-15.002261G4-17.001
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs ED J. ADAMS, 95-005908 (1995)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Dec. 04, 1995 Number: 95-005908 Latest Update: Aug. 14, 1996

The Issue The issues for determination are whether Respondent committed the acts alleged in the Administrative Complaint and, if so, what, if any, penalty should be imposed.

Findings Of Fact Petitioner is the governmental agency responsible for issuing licenses to practice as building contractors. Petitioner is also responsible for regulating such licensees on behalf of the state. At all times pertinent to this proceeding, Respondent has been licensed individually as a Certified General Contractor pursuant to license number CG C 0055328 issued by the Construction Industry Licensing Board (the "Board"). Respondent has never been licensed by the Board as the qualifying agent for Mr. Gary Butler ("Butler"), an unlicensed contractor. In 1993, Respondent entered into an agreement with Butler who has never been licensed by the Board. The terms of the agreement require Respondent to pull permits for construction projects entered into by Butler. Butler pays Respondent for each permit or weekly. Respondent supervises some, but not all, of the projects undertaken by Butler. In August, 1993, Mr. Lynn Kyler ("Kyler"), the owner of a residence constructed by Ms. Denise Pyke ("Pyke"), a Certified Residential Contractor, asked Pyke to find a contractor to build a new dock and boat house at Kyler's residence. The Kyler residence is a lake front home located at 10250 State Road 561 A, Clermont, Lake County, Florida. Kyler authorized Pyke to act as Kyler's agent for construction of the dock and boat house. Kyler resided in Indiana from August through late fall of 1993. Pyke obtained recommendations of various candidates including Butler. Butler represented himself as a licensed and insured builder of docks and boat houses. Butler provided Pyke with a business card representing that Butler is licensed and insured. Pyke obtained cost and design proposals from Butler and Norquist Construction Company and communicated the proposals to Kyler. Kyler chose Butler. Butler agreed to demolish the existing dock and construct a new dock and boat house (the "project"). Kyler paid Butler the full contract price of $6,897.60. Prior to the completion of the project, neither Respondent nor Butler disclosed to Pyke or Kyler that Butler was unlicensed. Nor did they disclose that Butler would use Respondent's license to pull the permit for the project. Respondent knew that Butler is not licensed as a contractor, in any capacity. On August 25, 1993, Respondent and Butler went to the Lake County Building Department. Respondent used his license to pull Permit Number T93- 04793 for the project. The permit was issued to Respondent, listed Respondent's license as the certified general contractor, and was maintained in the official records of the Lake County Building Department. Respondent listed himself on the permit as the contractor for the entire project without limitation and without reference to Butler. Respondent was not authorized by Pyke or Kyler to pull the permit or to participate in the project. At the time, neither Pyke nor Kyler were aware of Respondent's existence or his role in the project. Respondent did not participate and had no involvement in the project except pulling the permit. The project was commenced by Butler in August, 1993, and completed shortly thereafter. Respondent did not supervise or participate in the construction of the project. Butler began the project without first filing a Notice of Commencement. Butler constructed the project with only a 10 foot setback in violation of the 25 foot setback required in Lake County Code Ordinance 10.0401(3)(d). Butler also failed to obtain an electrical permit in violation of Standard Building Code, Section 103.1.1. (1991). The project, as built by Butler, has no value to Kyler. The project failed final inspection for violation of the 25 foot setback and failure to obtain an electrical permit. The roof tiles on the boat house had to be removed because they were falling off the roof. The project itself is coming apart. It will cost between $10,000 and $12,000 to bring the project into compliance with local code requirements and to make it usable. Respondent was aware of the 25 foot setback when he pulled the permit for the project. The project plans submitted for the permit reflect the 25 foot setback. Lake County allows contractors to withdraw permits that have already been pulled. Respondent never withdrew the permit for the project. Butler was unable to obtain a final inspection because he failed to file a Notice Of Commencement at the outset of the project. Pyke and Kyler filed the Notice Of Commencement in order to obtain the final inspection. As the contractor of record, it was Respondent's responsibility to ensure that a Notice of Commencement was filed and that the project passed final inspection. While obtaining the information necessary to file the Notice Of Commencement, Pyke and Kyler learned that Butler was unlicensed and uninsured and that Respondent had used his license to pull the permit. When confronted by Pyke, Respondent did not deny knowledge of the project and assured Pyke that the problems with the project would be corrected. Despite Respondent's assurances, the code violations have not been corrected. Nor have the defects in construction been corrected.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating: Sections 489.129(1)(c) and 455.227(1)(a); and Sections 489.129(1) (e), (f), (n), and (p). It is further recommended that the Board place Respondent on probation for three years, subject to reasonable conditions, impose an administrative fine of $5,000, and assess costs of $717.50 plus reasonable costs incurred by Petitioner subsequent to the date of this Recommended Order to investigate and prosecute this proceeding to its conclusion. RECOMMENDED this 28th day of March, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March 1996.

Florida Laws (3) 17.001455.227489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer