Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs STEPHEN C. ACHIN, 90-002527 (1990)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 27, 1990 Number: 90-002527 Latest Update: Jan. 25, 1991

Findings Of Fact At all times material hereto, Respondent has been a certified building contractor in the State of Florida, having been issued License No. CB CO24584. At all times material hereto, Respondent was the qualifying agent for Southern Construction Technologies, Inc. In March, 1988, Alfred and Martha Entrekin entered into a contract with Southern Construction Technologies, Inc., whereby they agreed to pay the sum of $178,000 for construction of a custom-built home. Since the Entrekins were unable to qualify for the financing needed for construction, Southern Construction obtained a construction loan on their behalf. Despite delays, construction commenced in May of 1988 and continued through October, when, the closing on the residence took place, subsequent to the issuance of a certificate of occupancy by the Town of Davie. Just prior to the closing, a "punchlist" was prepared by Respondent and the Entrekins. That punchlist, which became part of the closing, contains 24 numbered items. (Due to misnumbering, the punchlist says 25.) Thirteen 0of those items on the copy of the punchlist offered in evidence by the Petitioner have been crossed off that list. Of the remaining 11 items, the evidence at final hearing reveals that some were corrected and some items were not the subject of any evidence offered by either party at the final hearing. Although additional items appear to have been added to the punchlist by the Entrekins sometime after the closing, those items will not be considered in this cause since no evidence was offered to indicate that those items were agreed to by the Respondent at the time of closing and no evidence was presented as to when those items were added to the original punchlist by the Entrekins. At the time of closing, the sum of $1,500 was placed in escrow to ensure completion of the punchlist by Respondent. Respondent performed some of the punchlist work on the day of the closing and continued working on the punchlist items for the next three weeks. On January 11, 1989, the Entrekins' attorney sent a demand letter seeking the release of the funds placed in escrow at the closing. Attached to that demand letter was a list of 16 items allegedly remaining on the punchlist. Some of the items on the new "punchlist" submitted by the Entrekins did not appear on the punchlist agreed to by the parties at the closing. Others did appear on the closing punchlist but had been struck through and initialed by Mrs. Entrekin, assumedly as having been completed, on the copy of the closing punchlist offered by Petitioner as an exhibit in this cause. In response to the demand letter, Respondent authorized the release of the $1,500 in escrow to the Entrekins. Respondent admits that at the time that the money was released to the Entrekins, there were still some repairs needed to the rake tiles on the roof and he had not seeded the backyard. Respondent testified that four rake tiles on the eaves were missing, some were misaligned, and some had not been "mudded" in with mortar, but no broken tiles remained on the roof. He also testified that he had not seeded the backyard because the Entrekins had not yet placed fill in the backyard, an item which Mr. Entrekin admits was his responsibility as provided in the contract between the Entrekins and Southern Construction Technologies, Inc. The only evidence submitted in corroboration of the complaints of the Entrekins consists of several invoices. In March, 1989, the Entrekins obtained an estimate for roof repairs from Warren Roofing, Inc., in the amount of $1,200. That invoice indicates the need to replace 80 broken tiles on the roof, the need to remove and replace approximately 130 rake tiles to be secured with mortar tinted to match (although Donald Warren testified that the tile used is nail-on tile which does not require mortar), and the need to "repair defects" in two rear valley areas. Warren Roofing was never hired to effectuate the repairs for which it had submitted its $1,200 estimate. The extensive work set forth in the estimate in March of 1989 is inconsistent with the roofing inspection which would have taken place prior to the certificate of occupancy issued prior to the closing in October of 1988. The only roofing repair effectuated to the Entrekin house by anyone other than Respondent was work performed by Warren Roofing in July of 1989 repairing a leak around the skylight. Petitioner also offered in evidence two invoices from pool services dated March of 1989. One invoice in the amount of $275 represents the cost of acid washing the pool, and the other invoice is for $230 to "filter pool water." Due to electrical problems, the water in the pool was not filtered for two days during the period of construction of the Entrekin house. No evidence was offered to show that the absence of filtering a pool for two days would require it to be acid washed, and no evidence was offered in support of the services performed or the need for the services represented by the second invoice. Another invoice represents the cost of 20 loads of muck for the backyard at a cost of $600, and $150 to rent a bulldozer. Since the muck for the backyard was the responsibility of the Entrekins, the bulldozer charge accompanying the 20 loads of muck is, in all probability, also the responsibility of the Entrekins. The last invoice submitted in evidence also bears the date of March of 1989 and represents 50 pounds of grass seed, in the amount of $110.50, a cost item which Respondent admits was his responsibility at the time that the escrowed monies were released to the Entrekins.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding Respondent not guilty of the allegations contained in the Administrative Complaint filed against him and dismissing the Administrative Complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 25th day of January, 1991. LINDA M. RIGOT Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of January, 1991. COPIES FURNISHED: Charles N. Tetunic, Esquire Becker, Poliakoff & Streitfeld, P.A. Post Office Box 9057 Fort Lauderdale, Florida 33310-9057 Joseph Stephen Sharrow, Esquire Post Office Box 8995 Fort Lauderdale, Florida 33310 Daniel O'Brien Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Kenneth E. Easley General Counsel Department of Professional Regulation 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES ELLIS, 82-000632 (1982)
Division of Administrative Hearings, Florida Number: 82-000632 Latest Update: Jun. 07, 1983

Findings Of Fact The Respondent is a certified building contractor, having been issued license number CB C011621 as an individual contractor. The Petitioner is an agency of the State of Florida, having responsibility and authority to license building contractors and to regulate their licensure status and their standards of practice pursuant to Chapter 489, Florida Statutes. Sometime in December, 1979, the Respondent, doing business as Economy Steel Buildings, Inc., entered into a contract with Digital Machine and Tool Company to construct a steel building for that firm. The Respondent subsequently commenced the construction on land owned by Digital Machine and Tool Company and obtained a permit from Seminole County on December 6, 1979, authorizing the installation of a septic tank. On the face of the permit appeared language containing the specification that the "stub-out" or pipe exiting the septic tank be installed 12 inches above the original grade level. The Respondent observed that language on the face of the building permit and knew and understood its import, as his own testimony reveals. The Respondent subsequently subcontracted the installation of the septic tank to a company known as Al's Septic Tanks, which installed the tank and drain field during the early part of February, 1980. On February 10, 1980, an inspector for the Seminole County Health Department, Don Gross, inspected the septic tank installation and informed the subcontractor and the Respondent that it was not in conformance with Section 10D-6.25(2)(e), Florida Administrative Code, in that the subcontractor had not followed the instructions on the face of the building permit (12 inches above grade level), which were designed to satisfy that Administrative Code section. Sometime between February 10, 1980, and the end of April, 1980, the Respondent received a "Notice of Violation" from the Seminole County Health Department regarding the alleged improper installation of the septic tank. The Respondent admitted that sometime soon after installation of the septic tank he became aware that it did not pass the Seminole County Health Department inspection. The Respondent maintained that he made three attempts to contact the Health Department regarding the Notice of Violation during the month of April, 1980, but he introduced no competent, substantial evidence to show what efforts, if any, he made to correct the installation of the septic tank. There were ongoing disputes between Digital Machine and Tool Company, its representative, Galon Lyell, and the Respondent during this period, and on May 21, 1980, the Respondent was told to stay off the premises and perform no further construction on the site. There arose at about this time a civil dispute between the Respondent and Digital Machine and Tool Company which is outside the scope of this proceeding. In any event, the Respondent did not correct the installation of the septic tank and there is no question that the septic tank was not installed with the "stub-out" pipe 12 inches above the original grade level. Digital Machine and Tool Company later obtained a corrected installation of the septic tank so that it would be "stubbed-out 12 inches above original grade" from a different subcontractor, at its own additional expense, in the amount of $855. From the period of December, 1979, through the completion of the building for Digital Machine and Tool Company, the Respondent was performing contracting under the name of Economy Steel Buildings, Inc. The Respondent admitted that he was fully aware, as of November 19, 1979, that he could not properly perform contracting work under the name, Economy Steel Buildings, Inc., without properly qualifying that company. After a Notice of Violation (Respondent's Exhibit 6) was issued by the Construction Industry Licensing Board through Investigator Hunter, the Respondent was aware that contracting under an unqualified company name was improper. After that Notice of Violation, the Respondent made some attempts to separate his personal contracting business from that of his material supply company, Economy Steel Buildings, Inc. The Respondent, however, accepted payment for contracting and materials from his client, Digital Machine and Tool Company, for the subject project in the name of Economy Steel Buildings, Inc. The Respondent also paid Myron Roseland, a subcontractor, from Economy Steel Buildings, Inc.'s account for work attributable to the Digital Machine and Tool project. Finally, Petitioner's Exhibit 5 establishes that the Respondent attempted to discharge personal liability as a contractor, which attached to him through the Digital Machine and Tool Company project and other projects, by declaring bankruptcy pursuant to Chapter 11 of the Federal Bankruptcy Act as Economy Steel Buildings, Inc., since in that petition he listed numerous subcontractors, including Myron Roseland, who performed work on the Digital Machine and Tool Company job, as creditors of that corporation to be discharged. In summary, during the period of December, 1979, through the completion of the building for Digital Machine and Tool Company, the Respondent was performing contracting work as Economy Steel Buildings, Inc. During that time period, Economy Steel Buildings, Inc., was not properly qualified or registered with the Construction Industry Licensing Board by the Respondent, who was the owner and sole stockholder of Economy Steel Buildings, Inc.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED: That a Final Order be entered by the Petitioner finding the Respondent guilty of the violations alleged in Counts III and IV of the Amended Administrative Complaint and imposing an administrative fine of $1,000. The administrative fine should be suspended in part, provided the Respondent provides proof within sixty (60) days from the date thereof that he has made restitution to Digital Machine and Tool Company for the $855 it had to expend to obtain correction of the improper septic tank installation, as well as restitution of monies owed to Mr. Myron Roseland attributable to the Digital Machine and Tool Company project, in which event the Respondent's fine should be reduced to $250. DONE AND ENTERED this 10th day of February, 1983, at Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of February, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 James R. Lavigne, Esquire 1971 Lee Road Winter Park, Florida 32789 James Linnan, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (4) 120.57489.105489.119489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD T. WARNKY, 87-001718 (1987)
Division of Administrative Hearings, Florida Number: 87-001718 Latest Update: Jan. 28, 1988

Findings Of Fact At all times pertinent to the issues herein, Respondent was a certified general contractor in the State of Florida having been issued license Number CG C017772. On April 13, 1986, the Respondent, Richard T. Warnky, entered into a written contract with Jackson S. and Muriel Boyer to construct a home for them on Block 1244, Lots 7 and 8, Unit 19, Cape Coral, Florida, otherwise known as 2414 S.E. 28th Street for a contract price of $95,295.00. The Boyers gave Respondent a $550.00 down payment prior to signing the contract and at the time of signing, gave him an additional 10 percent of the contract price, or $9,529.50. The contract called for the payment of an additional 10 percent at commencement of construction and this payment was made at ground breaking. When the plumbing was roughed in and the slab poured, according to the contract, the Boyers paid Respondent an additional 10 percent and an additional 20 percent, or $19.059.00 when the masonry work was completed and the lintel poured. The contract called for three additional payments of 20 percent and two 15 percent payments, but for reasons subsequently to be discussed, none of these three payments was made. The contract called for the house to be completed in eight months, (240 days). According to Mr. Boyer, the Respondent left town for 8 weeks as soon as he had been paid the first 10 percent payment. Respondent claims that he was out of town for one week during which time he took ill and was physically unable to begin construction for an additional seven weeks. He also contends that he did not want construction to start without his being there to supervise it. Respondent's version of this situation is accepted. From the beginning of construction, Mr. and Mrs. Boyer had questions concerning the quality of the work being done When the slab was poured, it had holes in it and showed hills and valleys. Nonetheless, it passed inspection by the building inspector and the block work started. Pictures taken by Mr. Gogel, the licensing inspector for the City of Cape Coral at the request of Mr. Davenport, the building official, in July, 1986, reflect numerous deficiencies in the construction. They show large gaps in the vertical block joints; a lateral deflection in the tie beam poured at the top of the top course of blocks; blow out of the frame for the tie beam resulting in concrete running down the block walls; displacement of the tie beam which shows bulges and deformities; loose mortar in joints of the fifth course of blocks from the bottom; voids in joints; severe slippage in the top of the tie beam resulting in a reduction of the top; honeycombing of the concrete in the tie beam with rough attempts shown to patch it; slippage and deflection of the tie beam; and similar defects shown in the 14 pictures making up Petitioner's Exhibit 4 as well as the 15 additional pictures taken by Mr. Gogel and Mr. Davenport which were introduced as Petitioner's Composite Exhibit 6. On August 5, 1986, after Mr. Davenport and Mr. Gogel had visited the construction site at the request of Mr. Boyer, Mr. Davenport wrote Respondent a letter in which he discussed various items of workmanship on the property which needed Respondent's attention. In his letter, Mr. Davenport referred to the provisions of the American Concrete Institute Standards and the standards of the City of Cape Coral. He specifically pointed out that as to joints between cinder blocks, the joint should be not less than one quarter inch nor more than five eighths inch wide. His inspection indicated many of the masonry joints exceeded five eighths of an inch because the blocks were cut with a hammer rather than a block saw and in some cases, poured concrete extruded beyond the surface of the block. Mr. Davenport further addressed additional items which, he indicated, would require attention by the contractor in order for the work to meet the standards of acceptability for good residential construction in the City of Cape Coral. These included: waviness or blow out of sections of the tie beam; extrusion of concrete at the blow out patches; proper preparation of the cinder block walls for the receiving of stucco surface; honeycomb portions of the tie beam; and shimming and re-nailing of furring strips on the interior walls which had bent to follow the warped inner curve of the tie beam. These word descriptions are of the same defects shown in the photographs mentioned above. When Respondent reached that point in the construction where he felt an additional draw payment was called for, he requested it of the Boyers, but because of their dissatisfaction with the quality of the work he had done, they refused to make such payment. Mr. Warnky thereafter contacted his attorney who advised the Boyers by letter dated January 26, 1987, that their continued refusal to make draw payments as required by the contract, would jeopardize completion of the construction. No further payments have been made by the Boyers, however, since they consider the workmanship to be substandard and Mr. Warnky has done no further work on the project. The Boyers have had the work finished by another contractor at considerable additional expense. It should be noted, however, that the work done by the Respondent was passed by the building inspectors for the City of Cape Coral who did not indicate that it was below the cited code standards. Respondent is charged with gross negligence as a result of his failure to properly supervise the laying of the block walls with a resultant defect in the tie beam attached thereto. He admits that he was not present for approximately five to seven days during the ten days to two weeks that it took to lay the block on this project. Both Mr. and Mrs. Boyer contend that Respondent was not present at any time during the laying of the blocks by his employee, Mr. Sweebe. Since Mr. Boyer admits that he was not present at all times on all days that the blocks were being laid, it is impossible for him to indicate with any certainty that Respondent was never present. At best, the evidence shows that on those days when Mr. or Mrs. Boyer were present, Respondent was not present for the laying of the blocks. Based on his visit to the site and his observation of the workmanship, Mr. Davenport concluded that it was not of good quality. The materials used appeared to be suitable, but the application of the materials did not meet the criteria of the Southern Standard Building Code. These conditions are reparable, however, and it appears that Respondent did make efforts to repair some of the defects pointed out. For example, photographs taken on November 5, show an attempted "repair" of a honeycomb patch on the tie beam as does the November 19 photo. This latter picture, however, also shows that the tie beam is out of plumb and that furring strips were shimmed and covered with new furring in an attempt to comply with Mr. Davenport's letter of August 5. Further, this photo showing the waviness on a part of the tie beam indicates some grinding down in an attempt to bring it within standards. Notwithstanding, in Mr. Davenport's opinion, the workmanship by Respondent is below what is normally seen in the industry in Southwest Florida as it pertains to block masonry. These sentiments were reiterated by Mr. Verse, a certified general contractor in Sarasota for 13 years. Mr. Verse evaluated the various photographs taken by Mr. Gogel and Mr. Davenport and compared the work done by the Respondent as depicted on the pictures, against the accepted standards utilized by the building trade in Florida. He concluded that Respondent's work was not acceptable. He agreed with Mr. Davenport as to the deficiency in the joints, in the support of the tie beam, of the forming of the tie beam, and as to all masonry and concrete work. The negligence involved here was in letting this type of work go on when it was not up to code. A prudent general contractor would have stopped any subcontractor when he saw this type of work being done. If Respondent was not present to do so, then he failed to properly supervise. If he was present and allowed this substandard work to continue, he was grossly negligent. Mr. Verse rejects Respondent's excuse for washed out mortar joints, attributing them to rain, as unsatisfactory and unacceptable because a careful contractor will generally cover his work with a plastic sheet in the event rain is imminent. Respondent states that in his years as a contractor, he has never seen this done. Neither did Mr. Mahlmeister. In any case, a prudent contractor would make some provision to protect his work against any outside factor which might reasonably tend to threaten it. Respondent's failure to do so does not excuse the result. The honeycombing and bulging of the tie beam could occur from either improperly formed concrete or properly formed concrete which was improperly vibrated. Based on his examination of the photographs, Mr. Verse concluded it was probably improperly formed. Supports for the forming were not used. Had they been, they would have prevented the bulges that are seen. Even if the form work was properly braced and formed, if the concrete in the tie beams was improperly poured, the tie beam could bulge out at the bottom. Mr. Dililch, the individual who poured the concrete for Mr. Warnky, indicated that the procedure was accomplished at the very hottest part of the day in the hottest part of the year, which caused the concrete to dry out too rapidly and necessitated adding additional water to the mixture in order to keep it pourable throughout the process. Mr. Dililch indicates that though those abnormal steps were necessary, nonetheless, the concrete was poured in one session without any necessity to layer it. There appear to be no joints in the beam, the major defects being the honeycombing and bulging. Mr. Dililch recognizes there were blow outs where the concrete oozed out from under the framing, but contends that these are relatively common and occur on many different jobs by different contractors. Numerous factors could cause a blow out including loose braces, loose clamps, and things of that nature. Prior to pouring the concrete here, Mr. Dililch examined the form carefully and was satisfied it met standards and was safe. Nonetheless, the tie beam contained several examples of honeycombing. Blow outs are difficult to see before the concrete is formed. Older rental clamps quite often come loose and the looseness shows up only when the concrete is poured into the form generating the stress which forces the "mud" out through the joint. On every house he has worked on, there has been at least one blowout. It is, in his opinion, a common occurrence. His self-serving testimony is of little probative value here. The forming for the tie beam was inspected by Mr. Mahlmeister before the beam was poured and determined to be safe. Mr. Verse was shown pictures of work accomplished by other contractors which show similar defects to those attributed here to the Respondent and he admits that other contractors do, from time to time, substandard work. However, based on the opportunity he had to examine Respondent's work in this instance, the Respondent's performance showed defects throughout the entire project, not merely in isolated instances. The deficiencies in Respondent's work are broad based and wide spread. While all contractors make mistakes, the number of Respondent's mistakes take his performance beyond the realm of accident and indicate substandard work in general. Respondent is a small-contractor who does most of the work on his projects by himself and supervises the rest. It is his practice to be present on the construction scene every day but in this case, he admits he was not present all of every day. He has been a contractor in Florida for seven years, building approximately two houses per year. Prior to coming to Florida, he was a builder up north. He takes a great deal of pride in his work and has had very few complaints concerning the quality of his construction. In fact, he got the Boyer job because he had built a house for the Boyer's daughter who was happy with the quality of his construction. He believes his work is equal to the standards of most Cape Coral builders. Respondent admits that he makes mistakes, but he strongly contends that none of the deficiencies here were serious or would make the house unsafe. With all the complaints against it, the tie beam poured under Respondent's supervision, was never changed or altered. Most of the defects cited were cosmetic in nature and would have been corrected by him when the house was stuccoed. Respondent has been disciplined by the Petitioner, Construction Industry Licensing Board, previously, in 1984, when he was fined $250.00. It would appear that action was based on similar grounds to those in the instant action.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Respondent's license as a certified general contractor be suspended for six months, that he pay an administrative fine of $500.00, and that he be reprimanded. RECOMMENDED this 28th day of January, 1988, at Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of January, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 87-1718 The following constituted my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. BY THE PETITIONER Petitioner failed to number Findings of Fact submitted and included them in a section entitled FINDINGS OF FACT AND CONCLUSIONS OF LAW. However, as best as can be determined: Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. Rejected as a Conclusion of Law. Rejected as a restatement of testimony. Rejected as a restatement of testimony. Accepted. Rejected as a Conclusion of Law. Accepted as evidence of prior disciplinary action. BY THE RESPONDENT None submitted. COPIES FURNISHED: Lee Sims, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Richard T. Warnky 4924 S. W. 11th Court Cape Coral, Florida 33904 Fred Seely, Executive Director DPR, Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (2) 120.57489.129
# 3
JAMES A. BRAND vs FLORIDA POWER CORPORATION, 91-000004 (1991)
Division of Administrative Hearings, Florida Filed:Inverness, Florida Jan. 02, 1991 Number: 91-000004 Latest Update: Mar. 08, 1994

The Issue The ultimate issue is whether Florida Power Corporation (FPC) engaged in an unlawful employment practice by discriminating against James A. Brand on account of handicap in violation of Section 760.10, Florida Statutes (1989)

Findings Of Fact Florida Power Corporation is an electrical utility engaged in the generation, transmission, and distribution of electricity. FPC operates and maintains electrical generating plants throughout its service area, including Crystal River, Florida, where it operates two fossil generating plants, Crystal River South and Crystal River North, and a nuclear generating plant, Crystal River 3. The maintenance of the plants' equipment is performed by plant maintenance employees and by employees assigned from the System Maintenance Crew (SMC). Both regular and temporary employees work as members of the SMC in the job classifications of mechanic, certified welder mechanic, and electrician. Petitioner, James Brand, was employed by FPC on nine separate occasions during the years 1985 through 1988 as a temporary employee in the job classification of mechanic and certified welder mechanic on FPC's SMC. Temporary employees, such as Mr. Brand, are hired by FPC for the SMC for time periods of less than six months to perform overhaul and maintenance work on boilers, turbines, generators, pumps, fans, and other plant equipment during a unit or plant outage. Temporary employees are laid off and their employment is terminated as the outage work is completed. Mr. Brand had a preemployment physical examination before being initially hired as a temporary employee on the SMC in 1985. Thereafter, he had preemployment physical examinations on two occasions prior to reemployment by FPC. In June 1988, Mr. Brand was notified by letter from his attorney, Alwyn Luckey, that he has an asbestos-related lung disorder known as asbestosis. In June 1988, Mr. Brand received a clinical evaluation from Dr. Lewis J. Rubin, Head, Division of Pulmonary Medicine, University of Maryland School of Medicine, that he has pulmonary asbestosis. In approximately January or February 1989, Kathleen Moyer, a human resources representative in FPC's Crystal River office, contacted Mr. Brand regarding reemployment as a mechanic or certified welder mechanic on the SMC to work during a unit or plant outage. Mr. Brand went to Ms. Moyer's office to update his records and, at that time, provided her with Dr. Rubin's clinical evaluation reflecting that he has pulmonary asbestosis and with a copy of Mr. Luckey's June 21, 1988, letter. Ms. Moyer provided Dr. Rubin's report to Dr. Alex Sanchez, FPC's regional medical director. Mr. Brand was thereafter scheduled for a physical examination with Dr. Sanchez in February 1989. Mr. Brand also provided Dr. Sanchez with copies of Dr. Rubin's clinical evaluation and Mr. Luckey's June 21, 1988, letter. Dr. Sanchez asked Mr. Brand to get a second medical opinion. On March 4, 1989, Mr. Brand went to a physician, Dr. Nikhil Shah, who conducted a pulmonary examination and a pulmonary function or spirometry test. The results were given to Dr. Sanchez. Dr. Sanchez thereafter received a letter dated March 16, 1989, from Dr. Lewis Rubin, who had initially diagnosed Mr. Brand's medical condition as pulmonary asbestosis. Dr. Rubin stated in his March 16 letter that he had reviewed the pulmonary function test performed by Dr. Shah on March 4, and that Mr. Brand's asbestosis "should in no way impair his ability to do his job as long as he is not being exposed to noxious fumes or other environmental irritants." Dr. Ronald S. Kline, Director of Health Services for FPC, thereafter reviewed Mr. Brand's medical records, including Dr. Rubin's clinical evaluation diagnosing Mr. Brand as having pulmonary asbestosis and Dr. Rubin's March 16 letter. As Director of Health Services for FPC, Dr. Kline is responsible for the overall function of the medical department, which includes responsibility for determining whether a person has a physical or mental impairment which might limit his/her activities as they relate to his/her employment. Dr. Rubin's clinical evaluation states that Mr. Brand is at risk for the progression of pulmonary asbestosis even-in the absence of further exposure to asbestos. Dr. Kline did not request that Mr. Brand undergo any additional tests to determine if he suffers from asbestosis nor did Dr. Kline make an independent diagnosis that Mr. Brand has asbestosis. Dr. Kline accepted Dr. Rubin's evaluation and diagnosis of Mr. Brand. Dr. Kline had no reason to disbelieve the diagnosis of Mr. Brand's own physician, especially when the information regarding his medical condition was presented by Mr. Brand to FPC. On April 5, 1989, Dr. Kline issued a guideline to the human resources department placing the following restriction on Mr. Brand's employment activities: "No exposure to irritating gases or fumes, or any other environmental irritant." Dr. Kline based his recommendation on Dr. Rubin's evaluation and assessment. Moreover, Dr. Kline agreed, on the basis of his own medical experience, training, and education, that Dr. Rubin's recommendation of restrictions on Mr. Brand's activities was entirely reasonable. In Dr. Kline's medical opinion, Mr. Brand's continued employment in a position where he would be exposed to noxious fumes, gases, or other environmental irritants would pose a substantial risk of injury or harm to Mr. Brand's health. Dr. Kline does not and did not make decisions or recommendations regarding the hiring or reemployment of employment applicants. At no time did Dr. Rline recommend or otherwise indicate that Mr. Brand should not be reemployed by FPC. Rather, it was Dr. Kline's recommendation that he be employed in jobs in which he would not be exposed to noxious fumes, gases, or environmenta1 irritants. After receiving Dr. Kline's report, a human resources representative contacted Carey Hamilton, senior mechanical supervisor, and asked if he could employ a person in the position of mechanic or certified welder mechanic on the SMC who could not be exposed to irritating gases, fumes, and other environmental irritants. As senior mechanical supervisor, Mr. Hamilton is responsible for hiring and supervising the" regular and temporary mechanics and certified welder mechanics on the SMC. Mr. Hamilton has working knowledge of the environment inside the power plants due to his experience as an employee and supervisor on the SMC. He has been employed by FPC for over fifteen years in the job classifications of temporary mechanic, lab technician, certified welder mechanic, first line supervisor, and senior mechanical supervisor. He has worked as a certified welder mechanic, first line supervisor, and senior mechanical supervisor in all of FPC's power plants. Moreover, approximately ten years of Mr. Hamilton's experience has involved working with the SMC and supervising regular and temporary employees on the SMC, including during unit or plant outages. Based on his experience and firsthand knowledge of the work environment in the plants, Mr. Hamilton determined that he could not employ a person to work as a mechanic or certified welder mechanic on the SMC who could not be exposed to irritating gases, fumes, and other environmental irritants. At the time Mr. Hamilton responded to the human resources employment inquiry, he was unaware of the identity of the individual human resources was inquiring about or that this person has asbestosis. All employees on the SMC are initially hired into the mechanic classification. However, the temporary employees who are hired to work during a plant outage are usually upgraded to the certified welder mechanic position after they pass certain tests. The mechanics and certified welder mechanics working in the plant during an outage are continuously exposed to noxious fumes, gases, and other environmental irritants. Pulverized coal and fly ash, both of which have the consistency of face powder, exist in abundance throughout the plant in areas where the mechanics and certified welder mechanics are assigned to work. They are also exposed to other major irritants including sulfur dioxide gas, flue gases, smoke and dust created by tools, and irritants created by sandblasting and grinding. Mr. Brand was hired as a temporary on the SMC because of his welding and pipe fitting skills. He was qualified and certified to make safety-related pressure welds. FPC expends a significant amount of money in testing and certifying persons employed on the SMC so they can be used as welders. Prior to each period of his employment on the SMC, Mr. Brand was required to take welding certification tests in order to qualify as a certified welder. He always passed the certification tests and therefore was qualified to work as a certified welder mechanic. As a certified welder mechanic, Mr. Brand would work primarily in and around the boiler and boiler cavity. The work that is performed inside the boiler cavity by certified welder mechanics involves inspection, repair, and replacement of boiler tubes, replacement of burner fronts and defusers, and refractory repair. The certified welder mechanics clean the boiler tubes with a grinder prior to inspection. Thereafter, their work typically consists of repairing boiler tube leaks with a weld and replacing sections of the boiler tubes. The performance of this work involves grinding, burning, cutting, and welding, all of which produces fumes, gases, and other airborne irritants. The burner replacement and refractory repair work also exposes the certified welder mechanics to similar fumes, gases ~ and irritants. In addition to the boiler area, the certified welder mechanics perform work on the precipitators. This work involves burning, welding, and cleaning. The bottom ash hopper and the pulverizers that are used to crush coal are cleaned and repaired by certified welder mechanics during an outage. This work involves cutting, burning, grinding, and welding which produces noxious fumes and gases. Working on the water front and in the turbine areas during an outage exposes these SMC employees to fumes and dust particles created by sandblasting. During an outage, the SMC employees will be working on one unit that is out of operation; however, they are working next to a unit that is in operation. The unit that is in operation produces gases, fumes, and airborne irritants. The fact that Mr. Brand might work as a mechanic instead of a certified welder mechanic would not insulate him from exposure to noxious fumes, gases, and other environmental irritants. The duties of a SMC mechanic include sandblasting and grinding dirty or rusty metal, burning with a cutting torch, welding non-safety related welds, and' wire brushing. These activities are performed on a daily basis by mechanics. The sandblasting or grinding work is done with an abrasive disk that creates airborne particulates that contaminate the air. The burning process is used in making repairs such as in the steel ducts that transport air and gases to and from the boilers. Sulfur-based deposits collect in these ducts and when a torch is used in that area, the burning creates sulfur dioxide gas and other fumes. In addition, oxygen blasts are used in the burning process to increase the heat and blow metal out of the weld. This causes fly ash, dust, and other irritants to become airborne. The welding that is performed by mechanics also produces fumes and gases. All of the tools used by the SMC in the power plant are air-driven tools. The air discharged by these tools stirs up the dust, fly ash, gases, and other irritants in the workplace environment. During the time periods that a mechanic is not directly engaged in grinding, burning, or welding, he is working in close proximity to other employees who are performing those tasks, and thus, is exposed to the noxious gases, fumes, and irritants. Mr. Hamilton determined that he could not employ a certified welder mechanic on the SMC with the following restriction: "No exposure to irritating gases or fumes, or any other environmental irritant." He did not know that Mr. Brand was the proposed employee or that Mr. Brand has asbestosis. Mr. Hamilton knew that employing an individual to work as a mechanic or certified welder mechanic would expose that individual to gases, fumes, and other environmental irritants. The only positions supervised by Mr. Hamilton on the SMC are mechanic, certified welder mechanic, and tool room attendant. The tool room is housed in a large trailer parked outside of the plant. The tool room attendant's duties include issuing and receiving tools and repairing tools. These duties are performed in the tool room trailer. Because of his work location, the tool room attendant is not exposed to fumes, gases, and environmental irritants in the same way as the mechanics and certified welder mechanics. Mr. Hamilton later determined that Mr. Brand could be employed in the tool room consistent with the restrictions issued by Dr. Kline. Mr. Hamilton discussed with a human resources representative the possibility of employing Mr. Brand in the tool room. Mr. Hamilton had no objection to employing Mr. Brand in the tool room. However, there were no vacancies in that position and there have been no vacancies since that time. During 1990, Mr. Brand worked in Fluor Constructors Corporation, at Crystal River 3. Fluor Constructors is an independent contractor that is employed by FPC to perform repair and maintenance work. Mr. Brand received the referral to this job site through the Pinellas Park Local of the Pipefitters Union. While working for Fluor at Crystal River 3, he was supervised by Fluor's supervisors and not by FPC's supervisors. Mr. Brand is not seeking back pay for the period from February 23, 1991, through June 6, 1991. He was employed by a number of different employers during the period from January 1989 through May 1991. Such employers include Fluor Contractors, Inc., Teco Electric, Nisco, and a nuclear power plant in Mississippi. Mr. Brand would not be entitled to recover back pay or other monetary relief for the periods while working for other employers insofar as such interim employment periods coincided with SMC outage work periods. The hourly rate as well as other benefits of employment for temporary employees are set forth in the labor agreement between FPC and the International Brotherhood of Electrical Workers. As of December 5, 1988, the hourly wage rate for a mechanic was $16.51 per hour and for a certified welder mechanic was $18.72 per hour.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Florida Commission on Human Relations enter a Final Order denying the Petition for Relief. DONE and ENTERED this 11th day of July, 1991, in Tallahassee, Florida. DIANE R. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of July, 1991. APPENDIX The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, James A. Brand 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1); 1(2); 3(3&4); 475 (5-7); 6(63); 7(8); and 8-16(10-17). 2. Proposed findings of fact 17-19, 21-35, 50-54, 65-70, 76, 77, 84, 85, 91, and 92 are subordinate to the facts actually found in this Recommended Order. Proposed findings of fact 36-49, 55-64, 82, 83 and 86- 90 are irrelevant. Proposed finding of fact 20 is unnecessary. Proposed findings of fact ,1-75 and 78-81 are unsupported by the credible, competent and substantial evidence. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Florida Power Corporation 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1-63(1-62). COPIES FURNISHED: John Barry Relly II Attorney at Law Ray, Kievit & Kelly 15 West Main Street Pensacola, FL 32501 J. Lewis Sapp Sharon P. Morgan Attorneys at Law 800 Peachtree-Cain Tower 229 Peachtree Street, N.E. Atlanta, GA 30303 Ronald M. McElrath, Executive Director Florida Commission on Human Relations Building F, Suite 240 325 John Knox Road Tallahassee, FL 32399-1570 Dana Baird, General Counsel Florida Commission on Human Relations Building F, Suite 240 325 Johp Knox Road Tallahassee, FL 32399-1570

Florida Laws (3) 120.57760.01760.10
# 4
IN RE: LEE COUNTY SOLID WASTE ENERGY FACILITY, UNIT 3, POWER PLANT SITING SUPPLEMENTAL APPLICATION NO. PA90-30SA1 vs *, 02-004573EPP (2002)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 25, 2002 Number: 02-004573EPP Latest Update: Oct. 10, 2003

The Issue The issue to be determined in this case is whether a supplemental site certification should be issued to Lee County for the construction and operation of Unit No. 3 at Lee County's Solid Waste Energy Recovery Facility (Facility), in accordance with the provisions of the Florida Electrical Power Plant Siting Act (PPSA), Sections 403.501 - .518, Florida Statutes. (All statutory references are to the 2002 codification of the Florida Statutes.)

Findings Of Fact The Applicant The Applicant, Lee County, is a political subdivision of the State of Florida. Lee County owns the existing Facility and will own Unit No. 3. The Facility was designed, built and is operated by a private company, Covanta Lee, Inc. (Covanta), pursuant to a long-term contract with Lee County. It is anticipated that Covanta or another private company will design, construct and operate Unit No. 3 for the County. History of the Project In 1985, the Florida Legislature enacted the Lee County Solid Waste Disposal and Resource Recovery Act (the Act), which authorized Lee County to construct, operate, and maintain a solid waste disposal and resource recovery system for the benefit of Lee County's residents. In 1989, pursuant to the Act, Lee County adopted an Integrated Solid Waste Management Master Plan (Plan), which established a comprehensive plan for the management, reuse, recycling and/or disposal of the solid waste generated in Lee County. Lee County's Plan was based on the development of: (a) an aggressive recycling program to reduce the quantity of materials requiring disposal; (b) a waste-to-energy facility for waste reduction and energy recovery from those materials that are not recycled; and (c) a landfill for the disposal of ash and by- pass waste (i.e., materials that are not recycled or processed in the waste-to-energy facility). Lee County has implemented its Integrated Solid Waste Management Plan with innovative approaches and state of the art technology. Lee County has a comprehensive recycling program that handles a wide array of materials, including: (a) waste from residential, commercial, governmental, and institutional facilities; (b) household hazardous waste; (c) yard waste; (d) recovered materials; (e) construction and demolition debris; and (f) electronic waste. Lee County established a recycling and materials separation goal of 40 percent for its residents, even though the State of Florida's goal is 30 percent. From 1993 through 2000, Lee County exceeded the State's 30 percent goal. In 1998, Lee County's recycling rate was approximately 38 percent, which was higher than that of any other county in Florida. Consistent with its Plan, Lee County built a modern landfill, which is equipped with two synthetic liners, two leachate collection systems, and a network of groundwater monitoring wells to ensure the protection of the environment. Lee County's landfill is located in Hendry County, pursuant to an interlocal agreement between Lee County and Hendry County. Under this agreement, the solid waste from both counties is taken to Lee County's Facility for processing and then the ash and by-pass waste are taken to the landfill for disposal. This cooperative, regional approach to solid waste management issues has enabled Lee County and Hendry County to provide environmentally sound, cost-effective programs for the residents of both counties. In 1992, the Governor and Cabinet, sitting as the Siting Board, approved the construction and operation of Units No. 1 and No. 2 at the Facility, and certified an ultimate site capacity of 60 megawatts (MW), based on the operation of three municipal waste combustor (MWC) units. Units No. 1 and No. 2 have been in commercial operation since 1994. Despite Lee County's comprehensive recycling program, the amount of solid waste delivered to the Facility has increased each year since the Facility began operation, primarily due to population growth. In 1999, Lee County's solid waste deliveries were equal to the Facility's guaranteed processing capacity (372,300 tons). In 2000, the Facility processed more than 392,000 tons of solid waste, but the County still had to dispose of nearly 44,000 tons of processible waste in its landfill. Current population projections for Lee and Hendry Counties suggest that the amount of processible solid waste will continue to increase, reaching almost 550,000 tons by 2010. Lee County has decided that it should expand the Facility, consistent with Lee County's long-standing Plan, rather than discard processible waste in a landfill. The Facility was designed to readily accommodate the construction of a third MWC unit. If approved and built, the third unit (Unit No. 3) will be operating at or near its design capacity by 2010 (i.e., within five years after it commences commercial operations). For these reasons, on November 18, 2002, Lee County filed its Supplemental Application with DEP for the construction and operation of Unit No. 3. The Site The Facility is located east of the City of Fort Myers, in unincorporated Lee County. The Facility is approximately 2.5 miles east of the intersection of Interstate-75 and State Road 82, on the north side of Buckingham Road. The County owns approximately 300 acres of land at this location, but only 155 acres (which constitutes the Site) was certified under the PPSA for the Facility. The Site currently includes the Facility, a household hazardous waste drop-off area, a waste tire storage facility, a horticultural waste processing area, and a recovered materials processing facility. A solid waste transfer station is under construction at the Site. Even after the Facility is expanded to accommodate Unit No. 3, approximately 63 percent of the Site will be used solely as buffer and conservation areas. The Surrounding Area There are large buffer areas around the Site. A Florida Power & Light Company (FPL) transmission corridor, containing electric transmission lines, is located along the western boundary of the Site. Approximately three-quarters of a mile to the west of the Site is a limerock, fill, and topsoil mining operation. Immediately north of the Site is approximately 145 acres of undeveloped land owned by the County. A 135-acre County-owned park is adjacent to the Site's eastern property line. Scattered single-family homes are located northeast and farther east of the Site. An adjacent parcel southeast of the Site was previously used as a sanitary landfill (which has been closed and covered), and is now owned by the City of Fort Myers and private individuals who use it for livestock grazing. The land immediately south of the Site is undeveloped. The Gulf Coast Sanitary Landfill is located three miles directly south of the Site. Site Suitability The Site is well-suited for the addition of Unit No. 3. The Site has sizable buffer areas on all sides. Potable water, reclaimed water, and wastewater services are already provided to the Site through existing pipelines. The Facility is near an existing electrical substation (Florida Power & Light Company's Buckingham Substation). An existing electrical transmission line connects the Facility to the substation. Zoning and Land Use In 1991, the Siting Board determined that the Site and Facility are consistent and in compliance with the applicable land use plans and zoning ordinances, based on the construction and operation of three MWC units at the Facility. The Site was zoned for an Industrial Planned Development, and was designated as Public Facilities in the future land use map of Lee County's comprehensive land use plan, specifically to allow the Facility to be built and operated on the Site. The Existing Facility The Facility currently consists of Units No. 1 and No. 2, which have been in commercial operation since 1994. Each MWC unit has a nominal capacity of 600 tons per day (tpd) of solid waste (660 tpd using a reference fuel with a higher heating value of 5000 British thermal units per pound (Btu/lb)). The two MWC units generate steam that is used to drive an electric turbine generator, which generates approximately 39 MW of electricity. The Facility also includes an ash management building, cooling tower, stack, stormwater management ponds, water treatment system, electrical switchyard, electrical transmission lines, and related facilities. Solid waste collection trucks enter the Site from Buckingham Road. They follow an access road to the County's scale house, where the trucks are weighed, and then the trucks are directed to the Facility. The trucks drive inside the Facility and dump the garbage into a refuse pit. A crane mixes the garbage in the pit. The crane then places the garbage in a hopper, which feeds into the combustion chamber where the garbage is burned. The air in the combustion chamber passes through the Facility's air pollution control equipment, and then out the stack. Ash from the combustion process is quenched and then is deposited onto an enclosed conveyor, which takes the ash to an ash management building. The ash then is loaded into trucks and taken to the County's existing landfill in Hendry County. As a result of this process, the amount of fill being taken to the existing landfill is reduced by approximately 90 percent. The New Project-MWC Unit No. 3 The Project involves the construction and operation of a new MWC unit (Unit No. 3) at the Facility. The new unit will be substantially the same as the two existing MWC units. The new unit will have the capacity to process 600 tpd (nominal) of solid waste (660 tpd at 5000 Btu/lb). A new electric turbine generator will be installed and it will generate approximately 20 MW of additional electricity. In addition, the cooling tower will be expanded, the ash management building will be expanded, a lime and carbon silo will be installed, and the new unit may be connected with the two existing units. Construction of Unit No. 3 The Facility was originally designed and built to accommodate the addition of a third MWC unit, thus making the construction of Unit No. 3 relatively simple, without disrupting large areas of the Site. Unit No. 3 will be located adjacent to the two existing MWC units. The expansion of the cooling tower will be adjacent to the existing cooling tower. Construction of Unit No. 3 will occur in previously disturbed upland areas on the Site. Construction of Unit No. 3 will not impact any wetlands or environmentally sensitive areas on the Site. No new electrical transmission lines or improvements will need to be built to accommodate the additional electrical power generated by Unit No. 3. No new pipelines or other linear facilities will need to be built for the Project. Operation of Unit No. 3 The basic operation of the Facility will not change when Unit No. 3 becomes operational. Solid waste will be processed at the Facility in the same way it is currently processed. The Facility has been in continuous operation since 1994, and has an excellent record for compliance with all applicable regulations, including regulations concerning noise, dust, and odors. All of the activities involving solid waste or ash occur inside enclosed buildings. The refuse pit is maintained under negative air pressure, thus ensuring that dust and odors are controlled within the building. Because the operations at the Facility will remain the same after Unit No. 3 becomes operational, no problems are anticipated due to noise, dust or odors. The Facility's basic water supply and management system will remain the same after Unit No. 3 becomes operational. Treated wastewater from the City of Ft. Myers' wastewater treatment plan (WWTP) will be used to satisfy the Facility's need for cooling water. Potable water will be provided to the Facility from the City's water supply plant. On-site wells will be available for emergency water supply purposes; however, the wells have not been regularly used as a source of back-up cooling water since the Facility became operational. The County's water supply plan maximizes the use of reclaimed water and minimizes the use of groundwater. To the extent feasible, the Project uses all of the reclaimed water that is available before it relies on groundwater. The Facility also recycles and reuses water to the greatest extent practicable. Unit No. 3 will not discharge any industrial or domestic wastewater to any surface water or groundwater. Most of the wastewater from the cooling tower will be recycled and reused in the Facility. Any excess wastewater will be discharged to the City of Fort Myers' WWTP. Stormwater runoff from the Project will be collected and treated in the existing system of swales and detention/ retention ponds on the Site. Ultimate Site Capacity The construction of Unit No. 3 will not expand the Facility beyond the boundaries of the Site certified by the Siting Board in 1992. The operation of Unit No. 3, together with the operation of Units No. 1 and No. 2, will not increase the electrical generating capacity of the Site beyond the 60 MW certified by the Siting Board in 1992. Air Quality Regulations The County must comply with federal and state New Source Performance Standards (NSPS) and Best Available Control Technology (BACT) requirements, both of which impose strict limits on the Facility's airborne emissions. The County also must comply with Ambient Air Quality Standards (AAQS) and Prevention of Significant Deterioration (PSD) standards, which establish criteria for the protection of ambient air quality. The addition of Unit No. 3 must undergo PSD review because the Project is a new source of air pollution that will emit some air pollutants at rates exceeding the threshold levels established under the PSD program. PSD review for the Project is required for airborne emissions of particulate matter less than 10 microns in diameter (PM10), MWC metals, MWC organic compounds, MWC acid gasses, sulfur dioxide (SO2), nitrogen oxides (Nox), carbon monoxide, mercury, fluorides, and sulfuric acid mist (SAM). Best Available Control Technology A BACT determination is required for each pollutant for which PSD review is required. BACT is a pollutant-specific emission limit that provides the maximum degree of emission reduction, after taking into account the energy, environmental, and economic impacts and other costs. As part of the BACT determination, all available and feasible pollution control technologies being used worldwide are evaluated. As part of its BACT analyses, DEP determined that a fabric filter baghouse will control the Facility's emissions of particulate matter, a scrubber will control acid gases, a selective non-catalytic reduction system (SNCR) will control NOx, an activated carbon injection system (ACI) will control mercury emissions, and proper facility design and operating methods will control other pollutants. These air pollution control technologies are currently used in Units No. 1 and No. 2, and they have performed extremely well. Units No. 1 and No. 2 are among the best operated and controlled MWC units currently operating in the United States. Unit No. 3 will have better, more modern, and more sophisticated air pollution control systems than Units No. 1 and No. 2. In its PSD analysis for the Project, DEP determined the emission limits for the Project that represent BACT. All of the BACT emission limits determined by DEP for Unit No. 3 are as low as the limits established by the United States Environmental Protection Agency (EPA) in the NSPS (40 CFR 60, Subpart Eb) for new MWC units, based on the use of Maximum Achievable Control Technology (MACT). Indeed, DEP's BACT emission limits for Unit No. 3 are lower than EPA's MACT emissions limits for: (a) particulate matter; (b) sulfur dioxide; (c) carbon monoxide; (d) nitrogen oxides; and (e) mercury. The BACT emission limits, as determined by DEP, are included in the proposed Conditions of Certification for Unit No. 3. The Facility's proposed air pollution control systems are proven technologies that can achieve the proposed BACT emission limits. The Facility will use an array of continuous emissions monitors to help ensure that the Facility is continuously in compliance with the BACT emission limits. Protection of Ambient Air Quality The EPA has adopted "primary" and "secondary" National Ambient Air Quality Standards (NAAQS). The primary NAAQS were promulgated to protect the health of the general public, including the most susceptible groups (e.g., children, the elderly, and those with respiratory ailments), with an adequate margin of safety. The secondary NAAQS were promulgated to protect the public welfare, including vegetation, soils, visibility, and other factors, from any known or anticipated adverse effects associated with the presence of pollutants in the ambient air. Florida has adopted EPA's primary and secondary NAAQS, and has adopted some Florida AAQS (FAAQS) that are more stringent than EPA's NAAQS. Lee County and DEP analyzed the Project's potential impacts on ambient air quality, using conservative assumptions that were intended to over-estimate the Project's impacts by a wide margin. These analyses demonstrate that the maximum impacts from Unit No. 3 will be less than one percent of the amount allowed by the ambient air quality standards. The maximum impact from the Facility (i.e., all three units) will be less than or equal to 1.2 percent of the amount allowed by the FAAQS and NAAQS. Unit No. 3 and the Facility will not cause or contribute to any violations of the FAAQS or NAAQS. The maximum impacts of Unit No. 3 and the Facility, when operating under worst case conditions, will be less than the regulatory levels that are deemed "significant" (i.e., less than the numerical thresholds set by EPA as "significant impact levels"). The Facility's impacts on ambient air quality will be immeasurably small and will be indistinguishable from ambient background conditions. Non-criteria pollutants are substances for which there are no AAQS. The Department's Air Toxics Group has established non-enforceable guidelines known as ambient reference concentrations (ARCs) (also known as "No Threat Levels") for the non-criteria pollutants. DEP believes there is no health or environmental threat associated with ambient air impacts less than the ARCs. In this case, the maximum impacts of the Facility (3 MWC units) will be less than 50 percent of any of DEP's ARCs. For most parameters, the Facility's maximum impacts are less than 10 percent of the applicable ARCs. Other PSD Analyses The PSD program provides protection for those areas that have good air quality. Different areas of Florida have been designated as PSD "Class I" or "Class II" areas, depending upon the level of protection that is to be provided under the PSD program. In this case, the Project is located in a PSD Class II area. The nearest PSD Class I area is the Everglades National Park (Everglades), which is approximately 90 kilometers (km) south-southeast of the Site. The analyses performed by Lee County and DEP demonstrate that the Project's impacts on the ambient air quality in the vicinity of the Site will be insignificant. The analyses performed by Lee County and DEP also demonstrate that the Project's impacts on the ambient air quality in the PSD Class I area at the Everglades will be insignificant. The Project will not significantly affect visibility in the Class I area, regional haze, or other air quality-related values. Compliance With Air Standards Lee County has provided reasonable assurance that the Project will comply with all of the applicable state and federal air quality standards and requirements. Among other things, Lee County has provided reasonable assurance that the airborne emissions from the Project, alone and when operating with the two existing MWC units at the Facility, will not: (a) cause or contribute to the violation of any state or federal ambient air quality standard; (b) cause or contribute to a violation of any PSD increment for any PSD Class I or Class II area; (c) cause any adverse impacts on human health or the environment; (d) exceed any ARC guideline established by DEP for non-criteria pollutants; or (e) cause any adverse impacts to soils, vegetation or wildlife. Lee County also has provided reasonable assurance that Unit No. 3 and the Facility will be able to comply with the Conditions of Certification involving air issues. Human Health and Ecological Risk Assessments As indicated above, the County has performed extensive analyses of the Facility's emissions and impacts to demonstrate compliance with the requirements of state and federal air quality regulations. In addition, the County has taken other measures to address public concerns about the potential impacts associated with the Facility's airborne emissions. In 1992, the County's expert consultants conducted a human health and ecological risk assessment, which evaluated the potential impacts associated with the airborne emissions of mercury and dioxin from the County's Facility. The assessment demonstrated that the operation of the Facility would not adversely affect humans or threatened or endangered species. At the request of the United States Fish and Wildlife Service, the County conducted a supplementary risk assessment in 1992, to more thoroughly evaluate the potential impact of the Facility's mercury emissions on the Florida panther. Among other things, the supplementary assessment evaluated the panther's exposure to mercury through a complex food chain. The County's supplementary assessment confirmed that the Facility would not cause adverse impacts to the panther. The County also initiated a biomonitoring program, which was designed in conjunction with the U.S. Fish and Wildlife Service to identify background concentrations and trends for mercury in key indicator species within the local aquatic environment (i.e., largemouth bass, oysters, and mosquitofish). The County's biomonitoring program was started in 1993, and continued after the County's Facility commenced operations in 1994. The data collected in the biomonitoring program indicate that the mercury concentrations in these key species have not increased as a result of the operation of the Facility. In 2002, the County's consultants completed a new, large-scale, evaluation of the human health and ecological risks associated with the Facility's airborne emissions. The County's 2002 risk assessment evaluated the cumulative impacts of the entire Facility, with all three MWC units in operation. The County's 2002 risk assessment was conducted in compliance with current EPA guidance. The risk assessment considered hypothetical human receptors (e.g., infants, children, and adults) that were engaged in different types of behavior (e.g., a typical resident; a beef farmer; a subsistence fisherman) and were exposed through multiple pathways (e.g., inhalation; ingestion of soil; ingestion of local produce, beef and/or fish) to both acute short-term and chronic long-term impacts from the Facility. The risk assessment was designed to overestimate the potential impacts of the Project, and thus be protective of human health and the environment. The risk assessment relied upon the latest EPA data for mercury, dioxin, and the other chemicals of concern, as set forth in EPA's 1997 Mercury Report to Congress, EPA's 2000 Dioxin Reassessment, and other relevant documents. The County's 2002 risk assessment demonstrates that the Facility's airborne emissions will not measurably increase the typical concentrations of chemicals in the environment. For example, even at the point of maximum impact, the maximum environmental mercury and dioxin concentrations associated with the operation of the Facility will be far below the levels that are typically found in the environment and they will be immeasurably small. The County's 2002 risk assessment also demonstrates that the potential risks associated with the Facility's emissions will not exceed, and in most cases will be much less than, the risks that are deemed acceptable by the EPA and DEP for the protection of human health and the environment. The County's findings are consistent with the findings in environmental monitoring studies and risk assessments that have been performed for other modern waste-to-energy (WTE) facilities in the United States. Indeed, the environmental monitoring studies conducted at similar WTE facilities have shown that risk assessments, like the ones performed for Lee County, overestimate the actual impacts. In light of the evidence presented by the County in this case, the Facility should not have any measurable effect on human health or the environment, even when all three MWC units are operational. Other Potential Environmental Impacts The County's 2002 risk assessment primarily focused on the Facility's maximum impacts under worst case operating conditions. The maximum concentrations in the ambient air and the maximum deposition rates resulting from the Facility's mercury emissions will occur within 2.5 km (approximately 1.5 miles) of the Site. The ambient air concentrations and deposition rates at all other locations beyond the Site will be even lower. EPA studies of similar facilities have shown that mercury deposition rates decrease at least 100 times (i.e., by a factor of 100) within the first 10 km. In this case, the nearest portions of the Everglades are approximately 90 km from the Site. Moreover, the generally prevailing winds at the Site blow toward the Gulf of Mexico, not toward the Everglades. Approximately 90 percent of the time, the wind does not blow from the Site toward the Everglades. For these and other reasons, the Facility's mercury emissions will have an insignificant impact on the Everglades. The Facility's emissions of nitrogen oxides (i.e., NOx) will not cause or contribute to violations of any water quality standards in any surface waterbody. Environmental Benefits of the Project The addition of Unit No. 3 will provide significant environmental benefits to Lee County and Hendry County. The solid waste processed by Unit No. 3 will reduce the volume of processible solid waste by approximately 90 percent. By reducing the volume of processible waste, the Facility will significantly extend the useful life of the Lee County/Hendry County regional landfill, effectively postponing the need to build a new landfill in Lee County or Hendry County. The Project will also provide environmental benefits to the State of Florida. For example, the Facility will produce approximately 1.88 billion kilowatt-hours of electricity from discarded materials during the next 20 years. In this manner, Unit No. 3 will reduce the need to use fossil fuels to generate electricity at traditional power plants. Unit No. 3 will eliminate the need to use approximately 5.54 million barrels of oil, and thus will save approximately $150 million in oil purchases over the next 20 years. In addition, the County will recover ferrous and non-ferrous metals from the Facility's ash, thus recycling resources that otherwise would be buried with the County's solid waste in a landfill. Socioeconomic Benefits of the Project The local economy and labor market will benefit from approximately $70 million that Lee County will spend to construct the Project. A significant amount of construction supplies, such as concrete, structural steel, glass, piping, fittings, and landscape materials, are anticipated to be purchased from local businesses. The Project will provide jobs for over 125 construction workers during the peak of construction activities. The addition of Unit No. 3 will also provide approximately nine new permanent jobs at the Facility, with an increase in the Facility's annual payroll of approximately $400,000. WTE Criteria in Section 403.7061 Section 403.7061, Florida Statutes, establishes several criteria that must be satisfied before an existing waste-to- energy facility may be expanded. Lee County has provided reasonable assurance that the Project will satisfy all of the standards and criteria in Section 403.7061, Florida Statutes. Among other things, the County has demonstrated that Lee County's waste reduction rate will exceed 30 percent when Unit No. 3 begins operation. Compliance with Environmental Standards Lee County has provided reasonable assurance that the Project will comply with all of the nonprocedural land use and environmental statutes, rules, policies, and requirements that apply to the Project, including but not limited to those requirements governing the Project's impacts on air quality, water consumption, stormwater, and wetlands. The location, construction, and operation of the Project will have minimal adverse effects on human health, the environment, the ecology of the State's lands and wildlife, and the ecology of the State's waters and aquatic life. The Project will not unduly conflict with any of the goals or other provisions of any applicable local, regional or state comprehensive plan. The Conditions of Certification establish operational safeguards for the Project that are technically sufficient for the protection of the public health and welfare, with a wide margin of safety. Agency Positions and Conditions of Certification On December 11, 2001, the PSC issued an order concluding that the Project was exempt from the PSC's "determination of need" process, pursuant to Section 377.709(6), Florida Statutes. DEP, DOT, DCA, and SFWMD all recommend certification of the Project, subject to the Conditions of Certification. The SWFRPC determined that the Project is "Regionally Significant and Consistent with the Regional Strategy Plan," but did not recommend any conditions of certification for the Project. Lee County has accepted, and has provided reasonable assurance that it will comply with, the Conditions of Certification.

Recommendation Based on the foregoing Findings of Facts and Conclusions of Law, it is RECOMMENDED that the Governor and Cabinet, sitting as the Siting Board, enter a Final Order granting a supplemental site certification for the construction and operation of Unit No. 3 at the Lee County Solid Waste Energy Recovery Facility, in accordance with the Conditions of Certification contained in Appendix 1 to DEP Exhibit 2. DONE AND ENTERED this 19th day of August, 2003, in Tallahassee, Leon County, Florida. S _________________________________ RICHARD A. HIXSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of August, 2003.

CFR (1) 40 CFR 60 Florida Laws (9) 120.569377.709403.501403.502403.507403.508403.517403.519403.7061
# 5
DOROTHY BROWN-ALFARO AND AMILCAR ALFARO vs WHITE ROCK QUARRIES, 15-006014CM (2015)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida Oct. 23, 2015 Number: 15-006014CM Latest Update: Jan. 31, 2017

The Issue Whether Respondent’s use of explosives in connection with construction materials mining activities caused damages to Petitioners’ home, and, if so, the amount of damages to which Petitioners are entitled.

Findings Of Fact The Parties Petitioners reside in a single-family, one-story home located at 14699 Southwest 47th Street, Miramar, Broward County, Florida 33027. Petitioners are the third owners of the home, which was built in 1981. Petitioners have resided in the home since 1998. The home is approximately 3,000 square feet “under air,” and is composed of concrete block with stucco finishes, a shallow slab-on-grade foundation system, wood-framed interior walls, and ceramic tile flooring. Respondent engages in construction materials mining activities in Miami-Dade County, Florida. Specifically, Respondent utilizes explosives to procure construction materials (i.e., limestone) from quarries that are located in northwest Miami-Dade County, Florida. Respondent’s Blasting Activities The subject quarries are located within various geographic areas identified by different sections. Of particular relevance to the instant matter are sections 7, 6, and 4/5. Section 7 is approximately 2.6 or 2.7 miles from Petitioners’ home. Section 6 is approximately 2.3 or 2.4 miles from Petitioners’ home. Section 4/5 is approximately 1.6 miles from Petitioners’ home. Each of the sections have been utilized as a discrete location where blasting activities occur in order for Respondent to obtain construction materials. Section 7 was in operation from the mid-1990s through the end of 2015. Currently, no blasting activities occur in section 7. Section 6 was in operation from 2000 through 2015. Currently, no blasting activities occur in section 6. Section 4/5 began blasting operations in the first quarter of 2015 and halted in the fourth quarter while excavation was done. Blasting in section 4/5 resumed in January 2016. To monitor the impact of its blasting activities, Respondent utilizes the firm GeoSonics, Inc. (“GeoSonics”). GeoSonics has performed vibration measurement, evaluation, and reporting to Respondent since 1986. Jeffrey A. Straw is a seismologist with 39 years of experience and is employed by GeoSonics. As a seismologist, Mr. Straw is responsible for monitoring the impacts of vibration from Respondent’s blasting activities and analyzing their effects on structures. GeoSonics placed seismographs to monitor the impact of Respondent’s blasting activities. Peak particle velocity (“PPV”) is the speed at which a particle of ground oscillates as the vibration wave moves through the ground. The seismographs are used to determine if Respondent’s blasting activities are within the PPV limit of 0.5 inch per second established by the state of Florida. The seismographs must be located within one mile of each blast location to record the PPV resulting from the blasting activities. The seismographs are monitored and evaluated to ensure that their readings are accurate. The seismograph readings are evaluated by GeoSonics, which provides reports on the readings to Respondent and to the state fire marshall. Each seismograph undergoes testing to ensure that the instrument is working properly and providing effective and accurate readings. Every time a seismograph provides a reading concerning a blast, it sends a calibration pulse, which indicates whether the seismograph is working properly. Each seismograph instrument has an accompanying certification demonstrating that the instrument has successfully undergone testing and is working in accordance with the industry standards and specifications. There are six seismographs located within the vicinity of Petitioners’ home. The further the distance from the blasting location, the lower the blasting intensity. Each seismograph is located closer to the blasting location than Petitioners’ home. Thus, the PPV measured by the seismographs are greater than what the blasting intensity would be at Petitioners’ home. At no time have any of Respondent’s blasting activities reached or exceeded the 0.5 PPV limit. Petitioners Failed to Prove that Respondent’s Blasting Activities Caused Damages to Their Home In the instant case, Petitioners assert that Respondent’s quarrying activities caused damages to their home. Petitioners’ alleged damages center on “cracks” that exist throughout the home--specifically, cracks throughout the tile flooring inside the home; cracks on the cement flooring of the garage; cracks in the interior and exterior walls and ceilings; cracks in the semi-circular, stamp-concrete driveway and patio; and cracks around the surface of the windows. It is clear that cracks exist in Petitioners’ home. However, the issue to be determined in this case is whether the cracks were caused by Respondent’s blasting activities. They were not. In support of Petitioners’ position, Mrs. Alfaro presented at hearing a home inspection report. The inspection was conducted on April 18, 2016, and was not performed by a general contractor or structural engineer. Although the inspector identified various cracks based on his visual observations, the inspector specifically excluded any opinion regarding the cause of any need for repairs. Petitioners were specifically advised to obtain an opinion from a general contractor or structural engineer as to the cause of the damages. Mrs. Alfaro is an electrical contractor. She is not a licensed general contractor or structural engineer. At hearing, Mrs. Alfaro conceded that she does not have experience as a general contractor or seismologist. She has not had any training in seismology or blasting activities. Mrs. Alfaro’s testimony at hearing regarding the purported cause of the cracks is not credited and is unpersuasive. At hearing, Mrs. Alfaro presented the testimony of Barbara Hagan. Ms. Hagan resides in Country Club, Miami-Dade County, Florida, and is retired. She serves as the president of a civic association and secretary and treasurer of her homeowner’s association. She is not a general contractor, engineer, or seismologist. She has no experience in the use of explosives. She has never visited Petitioners’ home. At hearing, Ms. Hagan conceded that she has no opinion regarding the cause of any of the damages in Petitioners’ home. Mrs. Alfaro also presented the testimony of Paul Ingelmo. Mr. Ingelmo is a structural engineer who performed a visual inspection of Petitioners’ residence. Mr. Ingelmo did not review or analyze PPV data relevant to the blasts complained of by Petitioners. Mr. Ingelmo has no training or experience as to the appropriate threshold with respect to blasting activities and PPV. He is not familiar with how a wave behaves from a blast versus a seismic event. Mr. Ingelmo is not familiar with how PPV is measured or calculated. Importantly, Mr. Ingelmo could not give an opinion on whether the damages to Petitioners’ home were caused by Respondent’s blasting activities. In fact, Mr. Ingelmo conceded that the damages could have been caused by any number of unspecified factors. Finally, Mrs. Alfaro presented the testimony of Ismailia Rashid. Ms. Rashid is a general and roofing contractor. Ms. Rashid visited Petitioners’ home, conducted a visual inspection, and observed cracks on the patio, interior floors, and driveway. Ms. Rashid is not familiar with PPV or ground vibration. She has never been in a home where she was present and there was blasting. Importantly, Ms. Rashid did not offer an opinion on whether the damages to Petitioners’ home were caused by Respondent’s blasting activities. In sum, Petitioners failed to prove by a preponderance of the evidence that the damages to their home were caused by Respondent’s blasting activities. Rather, the preponderance of the evidence presented at hearing demonstrates that the damages to Petitioners’ home were not caused by Respondent’s blasting activities. In reaching this conclusion, the undersigned credits and finds persuasive the testimony of Respondent’s witnesses: Jeffrey A. Straw, David L. Teasdale, and Michael Schraeger. Mr. Straw visited Petitioners’ home twice: in April 2006 and January 2016. At those visits, Mr. Straw accompanied Michael Schraeger, a licensed general contractor with Diversified Services, Inc. On both occasions, Mr. Straw brought a camera and notepad with him to catalog the defects identified by Petitioners. Mr. Straw took extensive and comprehensive photographs detailing the cracks throughout Petitioners’ home and driveway. Mr. Straw testified that 90 percent of the alleged defects he observed in 2016 were items that he also observed in some format in 2006.1/ Mr. Teasdale is a civil structural engineer with Haag Engineering and serves as vice president of engineering and principal field engineer. Mr. Teasdale’s specialty focuses on the extent of damage to structures due to ground vibrations, explosions, and earthquakes. He is a licensed engineer in the state of Florida and 34 other states and has been a licensed engineer since 1988. He is extensively familiar with seismographs and has extensive experience installing and using them. Mr. Teasdale was accepted by the undersigned as an expert in structural behavior from ground motion and normal service loads, the influence of construction practices and environmental conditions on building features, soils and hardscape, the causes and conditions documented at the Petitioners’ residence, and lot features including the suitability of existing safe blasting standards in the state of Florida. Mr. Teasdale testified that there are substantial differences between an earthquake and quarry blasting. Mr. Teasdale explained that the fundamental difference between an earthquake and a quarry blasting is the amount of energy being released by the activity. Quarry blasting is a localized source event. An earthquake involves a fault line, which can extend for many miles and become mobilized. There is a direct correlation between the length of a fault line ripped versus the magnitude of an earthquake. Mr. Teasdale also explained that the measurement for quarry blasting, unlike the Richter Scale used for earthquakes, is a direct measurement; meaning that a PPV of 1.0 is twice the impact of a PPV of 0.5. Mr. Teasdale testified that for blasting to cause damage to a structure, distortion must occur. Distortion occurs where the foundation of a structure is accelerated laterally and causes the upper-part of the building to lag in response, which causes the building to shift back-and-forth and mimic a parallelogram shape. He explained that when distortion occurs, cracks will emanate from the corner of the walls and that those cracks will be mirrored on the opposite walls (inside and outside the structure). Mr. Teasdale explained that there was no damage to the foundation of Petitioners’ home, and the foundation and floor of a home would not experience distortion at 0.5 PPV or below because those limits are too low to produce the energy necessary to cause a structure to become mobilized. According to Mr. Teasdale, Petitioners’ home exhibited a variety of horizontal and vertical cracks and separations in the finishes, which are typical of environmental stresses in those materials. Mr. Teasdale also testified that distortion causes diagonal cracks, while thermal environmental stresses cause cracks vertically and horizontally. He explained that cracks caused by environmental conditions do not correlate on the inside and outside, while cracks caused by distortion do correlate on the inside and outside. He emphasized that the absence of corresponding cracks on the inside and outside of the structure generally precludes blasting as the cause of damages. Mr. Teasdale explained that from the moment the concrete is cast, it begins to shrink and develop cracks. Mr. Teasdale further explained that stucco, which is essentially the same material as concrete, is also prone to cracks due to normal environmental conditions. Mr. Teasdale testified that at the level in which Respondent has blasted below 0.5 PPV, it is impossible for Respondent’s blasting to have caused damages to Petitioners’ home. Based on his review and analysis of Petitioners’ home, Mr. Teasdale concluded that he would exclude blasting to a reasonable degree of scientific certainty as the cause of damages to Petitioners’ home. Mr. Schraeger is a general contractor and building inspector. He is self-employed through his company Diversified Services, Inc., and serves as the owner/operator. Mr. Schraeger has approximately 30 years of experience in commercial and residential construction. He has been licensed as a general contractor for 22 years and specializes in repairs, remodeling, and renovations of commercial and residential structures. He has 20 years of experience performing inspections of buildings relating to determination of material, construction failure, and defects. Mr. Schraeger was accepted by the undersigned as an expert in construction practices and environmental effects on materials and structures. Mr. Schraeger inspected Petitioners’ home in 2006 and 2016. He testified that 90 to 95 percent of the alleged defects he observed in Petitioners’ home in 2016 existed when he inspected the home in 2006. Mr. Schraeger testified that the cracks that he observed on the tile floor inside Petitioners’ home are very typical in a South Florida home because concrete typically cracks within all concrete structures. These types of cracks can be caused by poor installation of the tile or shrinkage of the monolithic slab over time. There was no evidence of foundation damage.2/ Mr. Schraeger further testified that in his professional opinion, some of the cracks in Petitioners’ home are the result of poor construction practices. For example, he explained that most of the cracks in the interior of Petitioners’ home are due to poor construction practices because of the use of an inappropriate method for finishing the joints in the drywall. During his 2016 inspection, Mr. Schraeger observed tape on some of the joints, which either had no joint compound under them, or the tape was applied after the compound started to dry, causing a bond failure. Some of the cracks generating from the corners of openings appeared to be from improperly secured corner bead. During his 2016 inspection, Mr. Schraeger also observed a crack in the master bedroom approximately eight feet in length, which appeared to be a joint in the drywall. This was apparent to Mr. Schraeger because the crack was visible on both sides of the joint tape, which had failed. According to Mr. Schraeger, the cause of this failure was moisture from a roof leak. Staining due to moisture on the ceiling in the area and a repair of the roof above this area indicated a previous leak. Notably, other areas of the home indicated roof leaks, including stains on the ceiling of the office area and staining around the skylight in the hallway. Mr. Schraeger further testified that the patio tile and driveway lack sufficient control joints, thereby making the stamped-concrete driveway and patio prone to crack. Mr. Schraeger also identified issues of poor maintenance by Petitioners. For example, he noted that the caulking around the windows was brittle and almost nonexistent. At hearing, Mrs. Alfaro acknowledged that in the 17 years she has owned the home, the windows have never been re-caulked. According to Mr. Schraeger, several cracks were observed on the stucco exterior walls of the home. With the exception of a severe crack on the wing wall on the rear of the patio, all of the cracks in the exterior walls of the home were attributed to common aesthetic cracks caused by the lack of control joints, dissimilar materials, bond failure, and improper maintenance. The crack on the wing wall of the patio, which ran along the bottom of a large tie beam, was attributable to poor construction methods.

Florida Laws (7) 120.569120.68552.32552.34552.36552.4095.11
# 7
DEPARTMENT OF ENVIRONMENTAL PROTECTION vs NEMI, INC., 09-000941EF (2009)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Feb. 18, 2009 Number: 09-000941EF Latest Update: Dec. 02, 2009

The Issue The issues in this case are whether Respondent, Nemi, Inc., should pay a $500.00 administrative fine for maintaining an unpermitted stationary installation that is reasonably expected to be a source of water pollution (Count I); whether it should pay an administrative fine of $9,500.00 for failing to submit a completed Site Assessment Report (SAR) within 270 days of discovery of the discharge of chemical solvents (Count II); whether it should pay investigative costs and expenses in the amount of $1,500.00 incurred by Respondent, Department of Environmental Protection (Department) (Count III); and whether it should take corrective action, as described in the Department's Notice of Violation, Orders for Corrective Action, and Administrative Penalty Assessment (Notice of Violation) issued on January 23, 2009.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Respondent is a for-profit corporation registered to do business in the State. Respondent's president and registered agent is Neil Schuberg, who represented the corporation at hearing. Respondent is the owner of a 1.1-acre parcel of real property located at 6801 Northwest 17th Avenue, Fort Lauderdale, Florida. The property is situated in what is known as the Gateway Industrial Center just south of the City of Pompano Beach and midway between the Florida Turnpike and Interstate 95. The parcel is rectangular shaped and is approximately 90 feet wide by 180 feet long. The property is further identified by the Broward County Property Appraiser as Parcel Identification Number 494209050040. A one-story warehouse and parking lot are located on the property, which is currently leased by Respondent to a testing laboratory. The evidence shows that for at least since 1981 David R. Ligh owned the property until his death. After he died, his widow, Elsie M. Ligh, sold the property in 1994 to Clayton John Pierce subject to a mortgage in the amount of $167,640.00. Mr. Pierce began operating a business on the premises known as Combined Roof Services, Inc. In 1995, Mr. Pierce decided to sell the property. A potential buyer, S & S Propeller Company, retained the services of Buck Eco-Logic, Inc., an environmental consulting firm, to prepare an environmental site assessment for the purpose of "determining the suitability of property for ownership by [S & S Propeller Company]." When it first inspected the site in July 1995, Buck Eco-Logic, Inc., discovered three thirty-five gallon drums and a twenty-gallon black plastic tub, all labeled "hazardous waste" and reflecting that they had contained tetrachloroethene (also known as perchloroethylene) waste. This is a chemical solvent that is typically used by dry cleaning establishments. The labels carried the name and "EPA ID number" of Family Dry Cleaners located at 6804 Stirling Road, Davie, Florida, an address which appears to be around ten to twelve miles south of the subject property. The three drums were lying on their sides on the northern end of an asphalt parking area beneath overgrown Brazilian pepper trees and were empty; the empty twenty-gallon tub was located inside the building on the property. Soil borings on the property performed by Buck Eco- Logic, Inc., revealed concentrations of tetrachloroethene at 10,613 parts per billion, which exceed allowable standards. Tetrachloroethene and its breakdown products are a solid waste, as defined by Florida Administrative Code Rule 62-701.200(113). A Phase I Environmental Site Assessment (Phase I ESA) dated August 13, 1995, was prepared by the consulting firm and sets forth in detail the results of its inspection. See Department Exhibit 2. The sale was never consummated. Later that year, Mr. Pierce engaged the same consulting firm to perform a Phase II Environmental Site Assessment of the property. That assessment revealed concentrations in groundwater ranging from 8,840 parts per billion to 173,000 parts per billion of tetrachloroethene, which exceed the State Clean Soil Criteria and State Maximum Contaminant Levels. The report, issued on October 13, 1995, was received in evidence as Department Exhibit 3. On October 30, 1995, a Mr. Pivnick, an attorney with the firm of Dombroff & Gilmore, P.A., which represented Mr. Pierce, notified the Department by letter that the empty drums and tub had been discovered on the property. The letter also attached a copy of the Phase I ESA. Mr. Pivnick was instructed by the Department to contact the local police department to report the incident as well as the state warning system for reporting discharges to the environment. Also, the Department contacted other local agencies and the United States Environmental Protection Agency (EPA). In October 1995, Mr. Pierce vacated the premises and ceased operating Combined Roof Services, Inc. In January 1996, he began leasing the property to Sun Valley Industries, also a roofing repair business, until that firm vacated the premises in December 1997. With the use of grant monies, the Department engaged the services of International Technology Corporation to prepare a Preliminary Investigation Report (PIR) for the property. That report was issued on February 13, 1997. See Department Exhibit The PIR recommended that additional monitoring of the site (through shallow monitoring wells, soil samples, groundwater samples, and groundwater flow direction) be made to quantify the presence of chlorinated solvents. Again with the use of grant monies, in 1997 the Department engaged the services of Post, Buckley, Schuh & Jernigan, Inc., to prepare a Site Inspection Report (Report) for the subject property. The Report was issued in March 1998. See Department Exhibit 5. Excessive tetrachloroethene, Cis-1, 2- dichloroethene, and trichloroethylene were detected in ground water samples, while tetrachloroethene was detected in all seven soil samples. On April 2, 1998, Ms. Ligh assigned the mortgage on the property to Nemi, Inc., for around $100,000.00. Mr. Schuberg explained that he was able to purchase it at a discount because Mr. Pierce had ceased making payments on the mortgage and had warned Ms. Ligh that if she foreclosed on the mortgage, she would be responsible for cleanup costs on the property exceeding a million dollars. While Mr. Schuberg acknowledged that he was aware of a contamination problem on the property, he says the mortgage was purchased as an investment, and he never thought he would actually acquire the property because he believed Mr. Pierce would continue to make the mortgage payments. After failing to make payments on the mortgage, on September 21, 1999, Mr. Pierce executed a Warranty Deed in Lieu of Foreclosure in favor of Nemi, Inc. Based on conversations with Mr. Pierce at that time, Mr. Schuberg says he was under the impression that the spill was much smaller than it actually was, and that it would be cleaned up by the Department. At hearing, Mr. Schuberg characterized Mr. Pierce as "a hustler and a liar." After Mr. Pivnick's report of contamination was received, the Department, along with the Broward County Department of Natural Resource Protection, initiated an investigation (probably in late 1995 or early 1996) in an attempt to verify the source of the contamination. Because Family Dry Cleaners "was on the top of [its] list," the Department first sought to determine whether that firm had actually deposited the drums and tub on the subject property. It learned that in 1994, or a year before the contamination was reported to the Department, Family Dry Cleaners had been evicted by its landlord, Lincoln Park. According to the Department, this "led to a dead- end" as far as Family Dry Cleaners was concerned. However, that business had been replaced by another tenant, Liberty Dry Cleaners. The Department then attempted to ascertain whether Lincoln Park or the new tenant might have been responsible for transporting the drums and tub to the subject property and dumping the waste. However, the Department was unable to confirm that either of the two had done so. Photographs of the drums and tub were made by Buck Eco- Logic, Inc., when it conducted an assessment in July 1995. Because the empty drums and tub were later removed from the site by unknown persons, the Department was only able to review the photographs when it conducted its investigation. Photographs of the drums indicated that they were larger than the twenty-gallon drums normally used by a dry cleaning establishment, and the labels on the drums were not perforated or dot matrix, which are more typical of those used by dry cleaners. For this reason, and because the empty tub was found inside the building on the property, the Department attempted to determine if Mr. Pierce had purchased the contaminants for use in his operations; it was not able to confirm this fact. The Department also contacted local law enforcement officials to see whether a criminal investigation could be launched. As noted above, however, the drums and tub had been removed by unknown persons while Mr. Pierce still had possession of the property and there was no forensic evidence for law enforcement officials to examine. The result of the investigation was that the Department was unable to determine who deposited the drums on the site or the exact location where the contents were first dumped. Although Respondent contended that the Department could have easily determined who removed the empty drums and tub from the subject property by examining the manifests of the carriers who engage in that type of business, the Department investigator did not attempt to do this since the yellow pages in the telephone directory reflected at least six pages of transporters in this type of business. Further, there is no evidence that a commercial transporter was even involved. For all of these reasons, the Department looked to the current owner of the property, Respondent, as the entity responsible for site rehabilitation since there were, and still are, contaminants leaching into the groundwater and aquifer system. Specifically, as of 2007, or twelve years after the discharge occurred, the groundwater on Respondent's property was still contaminated with tetrachloroethene, trichloroethylene, and cis-1, 2-dichloroethene exceeding the Department's groundwater standards. Also, the same contaminants exceeded the Department's soil cleanup target levels based on ground water criteria. Because rainfall and surface water continue to come into contact with the contaminated soil, and there is no liner or impervious cap in place, the installation is reasonably expected to be a source of water pollution. On September 12, 2001, the Department sent a letter by certified mail to Respondent advising that contamination was present on the property, that there were "possible violations of law for which you may be responsible," and that a Preliminary Contamination Assessment (PCA) must be filed within sixty days from the date of the letter. See Department Exhibit 6. Although a meeting of the parties was held on October 4, 2001, a PCA was never filed. 16. On April 27, 2006, March 12, 2007, and July 3, 2007, the Department issued Warning Letters to Respondent advising that an enforcement action would be initiated unless Respondent provided a SAR within a time certain. See Department Exhibits 7, 8, and 9. (The record is silent as to why no formal activity occurred between October 2001 and April 2006.) Exhibit 8 reflects that on November 21, 2006, "analysis results of sampling of one monitoring well were received by the Department." A meeting was later conducted by the parties on January 16, 2007, at which time Respondent agreed to "draft a suitable letter of [its] intentions with regard to conducting the required assessment and send it to the Department on or before January 31, 2007." There is no record of such a letter being sent. In August 2007, Respondent contracted with Florida Environmental Engineering, Inc., to perform a "limited site assessment report." In March 2008, that firm submitted to the Department a Preliminary Site Assessment Report (PSAR) See Department Exhibit 10. For this service, Respondent paid around $16,000.00. On March 21, 2008, the Department advised Respondent by letter that the PSAR was incomplete and that further information should be provided by April 30, 2008. See Department Exhibit 11. An Addendum to the PSAR was provided on May 5, 2008. See Department Exhibit 12. This report cost Respondent an additional $3,000.00. The PSAR indicated that contaminants (dichloroethene and trichloroethylene) in the water and soil on the property exceeded Department groundwater and soil cleanup target standards and levels. The report concluded, however, that "the discharge to the site is from an offsite source" (west of the property) and that "the property owner is no longer a responsible party." On August 27 and then again on October 22, 2008, the Department issued letters to Respondent advising that "there is not enough data to support the assumption that the discharge is offsite and the contamination is from an offsite source located west of the property." The Department reached this conclusion because, among other reasons, "[t]he contamination does not seem to be delineated towards the northern and southern portions of the site," "[t]here are no horizontal delineation wells to [the] north," the "iso contour maps provided appear to show the vertical delineation of the contamination but not horizontal delineation [of the plume]," "additional monitoring points need to be [added]," and "the onsite monitoring well, MW-2, shows a very high concentration of Perchloroethylene (PCE) at 81,000 ug/L [microgram per liter] and other contaminants, while the MW-1 does not exhibit groundwater contamination to that extent." See Department Exhibits 14 and 15. In plainer language, Respondent's report was deficient in that all contamination sources were not identified; it failed to delineate the horizontal and vertical extent of soil and groundwater contamination; and it failed to recommend a remedial action to clean up the contamination. The two letters advised that the site assessment was incomplete and that additional information described in the letters must be submitted by November 14, 2008. To date, Respondent has failed to submit the required information. According to Mr. Schuberg, to perform a study that would supply the additional information requested by the Department would cost him around $100,000.00, an amount he is unwilling to pay. More than 270 days has expired since a discharge was discovered on Respondent's property, and it has failed to submit a complete SAR, as described in Florida Administrative Code Rule 62-780.600(8). See also Table A, Fla. Admin. Code R. Ch. 62-780, which prescribes the specific time frame (within 270 days after the discharge is discovered) for submitting this report. The Department has incurred expenses in the amount of $1,500.00 while investigating this matter. See Department Exhibit 17. This amount is not disputed. As corrective action, the Department requests that within ninety days of the effective date of this Final Order, Respondent submit a complete SAR which addresses the deficiencies specified in the Department's August 27, 2008, letter. See Department Exhibit 14. To complete the SAR, additional soil and groundwater samples need to be collected to determine the vertical and horizontal extent of contamination, all source areas must be identified, and a remedial action must be developed to abate the contamination. Finally, the contaminated soil must be removed from the property so that it will no longer discharge into the groundwater. The Notice of Violation requests that upon approval of the SAR, Respondent "shall commence and complete in a timely fashion all further tasks" required by Florida Administrative Code Rule Chapter 62-780. These corrective actions are reasonable and are hereby approved. In calculating the penalty, Respondent has assessed a $500.00 administrative penalty for Respondent maintaining a stationary installation that is reasonably expected to be a source of water pollution without a permit. This is based upon a violation of Section 403.121(5), Florida Statutes, which makes it unlawful to not comply with a regulatory statute's requirement. Under Section 403.121(6), Florida Statutes, the Department has also assessed a $500.00 per day penalty against Respondent for failing to file a SAR for nineteen days, for a total of $9,500.00. When added to the $500.00 previously assessed, the total administrative penalty is $10,000.00, which is the maximum allowed in this type of proceeding. See § 403.121(2)(a), Fla. Stat. Throughout this process, Mr. Schuberg has contended that the responsibility for cleanup lies with the person or entity actually responsible for placing the drums and tub on the property in 1995. He says that the evidence clearly shows that Family Dry Cleaners is the responsible party. However, the Department and local authorities were never able to confirm who actually dumped the waste on the subject property. Although Mr. Schuberg says it will take "[i]n the hundreds of thousands of dollars" to clean up the site, the evidence shows that when he purchased the mortgage in 1998 and assumed ownership in 1999, he knew the property was contaminated. Mr. Schuberg further stated that because his consultant could never get "answers" from the Department, the consultant was instructed to stop work. However, Mr. Schuberg never contacted the Department to get clarification about what was required. At hearing, Mr. Schuberg also offered a lay opinion that his consultant's report filed in March 2008 proves that in 1995 the contents of the drums and tub were dumped on an offsite asphalt road adjacent to the property, surface water runoff then carried the chemical solvents onto his property, and the empty drums and tub were left in the parking lot. The Department's expert did not agree with this supposition, and there is no expert testimony to confirm the accuracy of this theory. Respondent has also contended that the property should be cleaned up with state funds. As pointed out by a Department witness, however, one problem is that the property does not meet the definition of a dry cleaner and thus cannot qualify for funds under that program. Then, too, a state-funded cleanup is a last resort which is used only after the Department has exhausted all enforcement remedies. Also, in this era of tight budgets, the Department has a finite amount of funds to use for this purpose, and is limited to cleaning up only a few sites per year. Finally, the responsible party must first acknowledge by affidavit that it lacks the necessary resources to clean up the property before the Department "may" seek cleanup funds. Respondent has not yet filed such an affidavit or admitted liability. In terms of mitigating evidence, Mr. Schuberg conceded that he has not done "a whole lot" to address the contamination problem since acquiring the property in 1999. In 2008, he did expend around $20,000.00 in having a PSAR and Addendum prepared for the Department. In all other respects, he steadfastly refuses to spend any more money on assessments or take responsibility for the cleanup since he believes that Family Dry Cleaners is the entity responsible for site rehabilitation.

Florida Laws (8) 120.569120.68403.031403.087403.121403.16157.04157.071 Florida Administrative Code (3) 62-520.20062-701.20062-780.600
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. BERNARD HANUS, 83-000528 (1983)
Division of Administrative Hearings, Florida Number: 83-000528 Latest Update: Dec. 02, 1983

Findings Of Fact Respondent is a certified general contractor, having been issued license number CG C012236. Respondent qualifies Ber-Pat Industries, Inc. On January 23, 1980, the Respondent, doing business through Ber-Pat Industries, Inc., contracted with Mrs. Benjamin Davis to construct an addition to the residence owned by Mr. and Mrs. Davis at 614 South Swinton Avenue, Delray Beach, Florida 33444. The contract between Mr. and Mrs. Davis and Ber-Pat Industries, Inc., was not for a fixed amount, but rather was a "cost-plus" contract. However, Respondent orally estimated to Mrs. Davis that the cost would he $21,500.00. Respondent commenced construction and received six draw payments totaling $29,184.78. Respondent's method of obtaining the draw payments was to invoice Mr. and Mrs. Davis, which he did on each of the six draws. The last invoice included $1,307.00 for the plumbing work which had been done by Priest Plumbing Company. Respondent did not pay the plumbing bill with the $1,307.00 given to him for this purpose. Rather, he used these funds to pay for ceramic tile which Mrs. Davis ordered on the date she paid Respondent for the plumbing work. Respondent did not inform the Davises of this diversion. Respondent thereafter sought a further draw for the ceramic tile costs. However, the project was then about 75 percent complete and costs were already $7,684.78 above the total project cost estimate. In view of this, the Davises believed Respondent had violated their agreement, and refused to make further payments. Because of their refusal to pay his costs, Respondent discontinued construction in late July, 1980.

Recommendation Based on the foregoing, it is RECOMMENDED: That Petitioner enter a Final Order dismissing the Administrative Complaint. DONE and ORDERED this 15th day of August, 1983, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of August, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 Mr. Bernard Hanus 3225 Lakeview Boulevard Delray Beach, Florida 33445 James Linnan, Executive Director Construction Industry Licensing Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (1) 489.129
# 9
GARDEN VILLAS HOME OWNER'S ASSOCIATION vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 95-000102 (1995)
Division of Administrative Hearings, Florida Filed:Shalimar, Florida Jan. 11, 1995 Number: 95-000102 Latest Update: Mar. 13, 2001

Findings Of Fact The Petitioner is comprised of residents of the residential neighborhood in close proximity to the construction and demolition debris disposal site or pit maintained by Whitrock Associates, Inc.. Its President is Jim Whitfield, a party Respondent to the subject Consent Order. The Petitioner complains that illegal dumping is occurring at the disposal site, that there is no guard maintained at the gate, and that the gate is not locked when no one is present. It complains that DEP does not inspect the facility enough by only inspecting it once per year and that the facility should be closed down. Its chief objections are that refuse is being dumped in what it considers to be a stocked fishing lake. The "lake" is a borrow pit partially filled with water, which resulted when excavation of the dirt in the pit penetrated below the ground water table. The chief objections raised by the Petitioner amount to the nuisance "eye-sore" nature of the facility and the concomitant deleterious effect its presence and activity has arguably had on property values and the Petitioner's members' ability to re-sell homes. The Petitioner's standing is not contested. The Respondent is an agency of the State of Florida charged with regulating landfills, construction and demolition debris disposal sites and other such waste sites, within the purview of Section 403.161, Florida Statutes, concerning pollution discharge and, more specifically, rules contained in Chapter 62-701, Florida Administrative Code, concerning solid waste and similar materials and disposal facilities. DEP is a party Respondent to this proceeding because the Consent Order it has entered into with the owner and operator of the site, Whitrock Associates, Inc., has been challenged, within the point of entry period afforded by that Consent Order, by the above-named Petitioner. Whitrock Associates, Inc. maintains a construction and demolition debris disposal site, in the form of an excavated pit, located between Carmel Drive and Vicky Leigh Road in Fort Walton Beach, Okaloosa County, Florida. An inspection of the facility by DEP personnel on October 13, 1994 revealed the disposal of organic debris in surface water at the site, the disposal of which is illegal in ground or surface waters. It also came to DEP's attention at this time that the facility was operating with an expired general permit. Consequently, an enforcement action was initiated against the owner and operator of the facility. After extensive negotiations, the subject Consent Order resulted, which has been challenged by the Petitioner. The essential provisions of the Consent Order would require that the Respondent to it, meaning Whitrock Associates, Inc., cease disposal of construction and demolition debris at the facility, which is not "clean debris". "Clean debris" is inert debris, such as brick, glass, ceramics, and uncontaminated concrete, including embedded pipe or steel. The Consent Order provides that within 60 days of its effective date, all such non-conforming construction and demolition debris shall be removed from the water at the site and that the Respondent, Whitrock Associates, Inc., shall submit a notification of intent to use a general permit for the construction and demolition debris disposal facility to DEP. Failure to proceed to obtain the general permit would result in closure of the facility, pursuant to Rule 62-701.803(10), Florida Administrative Code. The Consent Order also provides that a $2,300.00 civil penalty and cost payment shall be made to DEP in full settlement of the matters addressed in the Consent Order. That payment shall be made within 30 days of the effective date of the Consent Order. The Consent Order then enunciates, in great detail, the manner in which future penalties will be assessed for any violation of the Consent Order and related time limits, as well as payment methods and circumstances. It also provides a means for handling of delays in compliance with the Consent Order. It provides the means for enforcement of the terms of the Consent Order. Billy Ross Mitchell is an Environmental Specialist with 14 years of experience with DEP. He works in the solid waste section. Among his other duties, he inspects solid waste disposal facilities. He has a degree in environmental resource management. Mr. Mitchell established that this is the type of facility, where, because of the disposal of inert construction debris, which does not pose a significant pollution threat, a so-called "general permit" is sufficient authorization for operation of the facility. The facility was operating with an expired general permit at the time of Mr. Mitchell's inspection, but a new general permit has since been authorized. Mr. Mitchell performed the inspection of the facility, at which he observed illegal construction debris being placed in the water at the site. DEP's rules allow inert material, such as brick, glass, ceramics, and so forth to be placed in water at the site, which, in essence, is a borrow pit. The rules forbid organic materials, such as shingles, lumber and other similar materials, which can sometimes be constituted of pollutant substances, from being placed in the surface or ground water. As shown by the Respondent's Exhibit 3, a letter from Mr. Cooley, a District Director of DEP, to Mr. Lawrence Sidel of the Petitioner, uncontaminated dirt and "clean debris", such as chunks of concrete and the like, are not considered under Florida law to be solid waste. DEP takes the position that there is no prohibition against a person using clean fill, without a required permit, to fill land or bodies of water that are not "state jurisdictional water." The water body on the Whitrock property is not a state jurisdictional lake or water body. It is an old borrow pit, wholly contained on the Whitrock property. State law allows its owners to fill it with dirt or clean fill. Whitrock is not allowed to use any material classified as "solid waste" in filling the pit, hence the violation cited to that firm in the particular mentioned above, concerning the non-inert construction debris that was placed in the water. The Respondent's Exhibit 4 is an engineer's report prepared for the Whitrock facility involving the "notification of proposed use of a general permit" process for the operation of the construction and demolition debris disposal facility. This is the general permit notification process and general permit referenced in the Consent Order. 1/ The site has been used for many years as a borrow pit for dirt fill material or sand, as well as a disposal site for construction debris. In the general permit achievement process, the owner proposes to grade the site so that the final grade is the original, natural grade, with a slight two percent top slope to promote runoff to surrounding retention swales which will be installed at the site. The soil borings reflect that at all depths tested, sand is the underlying soil at the site. The borrow pit has been excavated below the natural water table, which has resulted in ponding of water on the floor of the borrow pit. This is proposed to be filled with "clean" debris, as it is received on site. Clean debris is solid waste which is virtually inert and which poses no pollution threat to ground or surface waters, is not a fire hazard, and is likely to retain its physical and chemical structure under expected conditions of disposal or use. Examples of it are as depicted in paragraphs six and seven, supra. Clean debris disposal is thus proposed within the pit bottom to an elevation of one foot above water table, above which construction and demolition debris will be disposed. The owner of the facility will be the person responsible for operation, maintenance, and closure of the proposed disposal facility. Procedures will be followed to control the types of waste received, the unloading, compaction, application of cover, final cover, and control of storm water at the site. The existing perimeter fence will remain with a lockable gate at the entrance to the site. In accordance with Rule 62-701.803(8), Florida Administrative Code, at least one spotter/operator will be on duty when the site is operating to inspect incoming waste. If prohibited waste is discovered, it will be separated from the waste stream and placed in appropriate containers for disposal at a properly-permitted facility. A commercial dumpster is located on site for unpermitted waste and is regularly emptied by a sanitation contractor. This practice is proposed to continue with the issuance of the general permit for the construction and demolition debris facility. Construction and demolition debris filling operations will proceed from the northwest corner of the site and progress in an easterly direction along the north property fence line. Due to the depth of the existing cut, approximately 25 feet, it will take approximately three separate "lifts" of waste and compacted material in order to reach a finished grade elevation, to match the original grade of the surrounding terrain. Additional soils required for intermediate cover material and final cover will be obtained off site from other sources. Filling operations should allow for approximately a 100-foot wide working face to aide in keeping a manageable disposal area. A dozer and front-end loader will be available on the site to compact waste material into the "working face." Each lift will be six to eight feet thick. Closure of each portion of the facility will occur as waste compaction approaches original grade. Final cover, seeding or planting of vegetated cover will be placed during stages, within 180 days after reaching final-design waste elevations. The final cover will consist of a 24-inch thick soil layer, with the top six inches being capable of supporting vegetation. The site shall be graded to eliminate ponding, while minimizing erosion. Upon final cover placement across the site, the owner will notify DEP within 30 days. Storm water will be controlled via retention swales surrounding the site. The swales are sized to accommodate one-half inch volume across the site. These specifications are those proposed to be installed and operated at the site in return for the grant of the general permit and are necessary elements of the negotiations and ultimate settlement agreement reached embodied in the Consent Order. Thus, they are required by the Consent Order, should it become final agency action. Chief among the Petitioner's concerns is the matter of the alleged non-compliance of the disposal site and facility with zoning for that area and land-use ordinances, as well as concerns regarding property values, tax assessments and the inherent difficulty in re-sale of homes caused by the presence and operation of the facility. 2/ The Petitioner, whose members, among others, are a number of adjoining landowners, some of whom testified, also complains of pollution of the water body involved, the standing water in the bottom of the borrow pit. Witness Mitchell, as well as Respondent's Exhibit 4, concerning the conditions under which the general permit will be obtained and operated (conditions also repeated in the Consent Order), established that the deposition of only construction and demolition debris and clean fill in the water will pose no pollution which violates Section 403.161, Florida Statutes, and attendant rules. The terms in the Consent Order, which require the general permit and the conditions referenced in the Respondent's Exhibit 4, concerning the general permit, will result in minimal hazards of pollutants entering surface or ground waters, or in polluted air or water emanating from the site in violation of regulatory strictures, assuming frequent inspections by DEP are made to insure compliance. Thus, it has been established that the proposed Consent Order is reasonable under the circumstances. 3/

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Consent Order issued in the case of State of Florida, Department of Environmental Protection v. Whitrock Associates, Inc. be ratified and adopted as final agency action, in accordance with Chapter 120, Florida Statutes. DONE AND ENTERED this 16th day of January, 1996, in Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of January, 1996.

Florida Laws (2) 120.57403.161 Florida Administrative Code (2) 62-701.73062-701.803
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer